﻿Fiscal Year 1989
IM 0 
agS s 
!e 
Ann ll IIe ISIT 
mp
s1Ocoe 88-8 sa a a 8 
Sf 
v1*i-a 1 
e ..

FY 1989 STATISTICAL HIGHLIGHTS 
ITEM 
APPROPRIATION (S MILLIONS) 
Navigation 
Flood Control Total 
Flood Control 
Mississippi River and Tributaries' 
Multipurpose including power 
Beach Erosion Control 
Total New Work 
s 
Other Work* 
TOTAL 
NAVIGATION (Calendar Year)* 
Ton-Miles of Commerce (Millions) 
Foreign, Coastal Ports 
Foreign, Great Lakes Ports 
Domestic, Coastal (Intraterritory not compiled) 
Domestic, Great Lakes 
Domestic, Inland 
Domestic, Local 
TOTAL 
Tons of Commerce (Millions) 
Foreign, Coastal Ports 
Foreign, Great Lakes Ports 
Domestic, Coastal and Intraterritory 
Domestic, Great Lakes 
Domestic, Inland 
Domestic, Local 
TOTAL 
FLOOD DAMAGES PREVENTED ($ Billions) 
FLOOD DAMAGES SUSTAINED (S Billions) 
POWER 
Installed (Cumulative in millions of kw) 
Generated (Billions of kwh) 
RESERVOIR STORAGE (Millions of acre-feet) 
All Purpose 
Flood Control (Maximum) 
Water Supply 
Irrigation 
PUBLIC ATTENDANCE AT RESERVOIRS 
Recreation Days of Use (in Millions) 
Visitor Days (in Millions) 
1989 1988 1987 1986 1985 1984 1983 1982 1981 1980 
519 512 443 299 304 257 577 522 607 485 
856 840 787 673 676 647 832 774 772 873 
(222) (205) (206) (227) (225) (203) (291) (177) (145) (211) 
73 73 69 93 112 171 221 247 275 538 
27 27 23 17 12 25 5 7 12 9 
1,475 1,452.0 1,322.0 1,082.0 1,104.0 1,127.0 1,685.0 1,580.0 1,666.0 1,906.0 
1,770 1,826.0 1,813.0 1,658.0 1,797.0 1,567.0 1,734.0 1,417.0 1,331.0 1,296.0 
3,245 3,278.0 3,135.0 2,740.0 2,901.0 2,688.0 3,419.0 2,997.0 2,997.0 3,201.0 
56,208.2 50,985.0 47,274.2 44,769.3 46.508.8 45,286.7 51,2627 58,929.2 60,569.8 
24,448.4 22,003.3 24.235.2 27,171.9 32,249.4 24,309.4 27,165.5 35,294.0 33,679.6 
561,594.9 586,818.7 580,888.7 610,976.5 593,923.1 649,749.4 632.707.0 634,765.3 631,149.2 
58,159.4 50,076.4 43,198.2 48,184.0 49,784.4 43,088.2 35,623.3 62,148.3 61,747.1 
269,035.7 257,336.4 248,116.9 232,707.5 242,855.4 225,628.2 217.026.7 231,184.1 227,343.0 
1,238.4 1,183.9 1,197.2 1,102.0 1,157.1 1,099.7 1,111.7 1,315.6 1,596.4 
970,685.0 968,403.7 944,910.5 964,911.2 966,478.2 989,161.6 964,896.9 1,023,636.5 1,016,085.1 
923.7 845.1 791.4 723.0 744.5 702.7 769.2 823.9 860.8 
52.5 45.9 45.7 51.3 58.8 48.4 50.4 63.2 60.6 
330.3 328.2 312.0 313.2 311.1 312.8 313.9 325.1 333.2 
109.7 96.5 87.4 92.0 98.0 83.5 72.1 115.4 115.1 
588.1 569.8 560.5 534.7 542.5 487.1 496.5 520.7 535.0 
83.7 82.0 77.4 74.2 81.1 73.2 75.6 93.2 94.2 
2,088.0 1,967.5 1,874.4 1,788.4 1.836.0 1,707.7 1,776.7 1,941.5 1,998.9 
8.3 2.1 5.2 27.3 10.8 16.8 23.2 4.3 1.2 7.3 
1.1 0.5 17 6 0.5 4 4 1.5 1 1.5 
20.5 20.5 20.5 20.5 20.1' 20.1' 19.7' 19.7' 19.2' 19.0' 
81.6 72.2 74.0 80.7 88.3 91.2 88.2 75.8 77.3 77.8 
273.6 273.6 272.1 270.6 269.0 268.5 262.3 
123.3 123.3 123.0 123.0 123.0 122.7 120.4 
9.5 9.5 9.2 9.2 9.2 9.1 8.9 
7.8 7.8 7.8 7.8 7.8 7.8 7.8 
191 191 181 
506 502 482 480 480 469 457 
FUNDING 
General Investigation 142,405 138.767 136,287 128.272 
ConstructioGnen eral 1,184,735 1,200,175 1,152,150 919,345 
Operations and Maintenance, General 1,370,714 1,421.733 1,389,846 1,319.973 
Regulatory Program 63,752 55,262 
Flood Control Mississippi River & Tributaries 332,550 317,704 310,797 314,760 
General Expenses 120,000 115,000 115,000 107,000 
FloodC ontrol& CoastalE mergencies 20,000 20,000 10,000 25,000 
Revolving Fund 0 0 12,000 7,000 
Permanent Appropriations 9,000 9,000 *0 8.000 
TOTAL 3,245,261 3,278.091 3,135,080 2,830,050 
1 Included in Flood Control Total. 
2 Advanced engineering and design, and construction. (Including major rehabilitation projects.) 
Savings and slippages applied to projects. 
3 Operation and maintenance, surveys, administrative and misc, programs and activities. 
4 Includes New Melones and Spettisham, built by the Corps and operated by others. 
5 All Federal agencies changed to 'Visitor Days' at the direction of OMB. 
* For further information on waterborne commerce, see Waterborne Commerce of the United 
States, published annually. It may be obtained by writing the Commander, U.S. Army 
Engineer District, New Orleans, ATTN: CELMN-ED-S, P. O. Box 60267, New Orleans, 
LA 70160-0267.

DEPARTMENT OF THE ARMY 
OFFICE OF THE ASSISTANT SECRETARY 
WASHINGTON, DC 20310-0103 
21 JAN 1992 
TO: THE PRESIDENT OF THE SENATE 
AND THE SPEAKER OF THE HOUSE OF REPRESENTATIVES 
SUBJECT: Annual Report of the Secretary of the Army on Civil 
Works Activities for FY 1989 
I am submitting Volume II of the Annual Report on Civil Works 
Activities for the Fiscal Year 1989 in accordance with Section 8 of 
the Rivers and Harbors Act of 1988 and Section 925(b) of the Water 
Resources Development Act of 1986. 
This volume of field reports contains narrative summaries and 
statistics on water resources development projects of the Army 
Corps of Engineers where there has been activity between October 
1988 and September 1989. 
Nancy P. Dorn 
Assistant Secretary of the Army 
(Civil Works) 
HECSA TECzN L LIU ARY

CONTENTS 
New England Division .................................................................. 1-1 
North Atlantic Division: 
New York, NY, District ............................................................... 2-1 
Philadelphia, PA, District ........................................................... 3-1 
Baltimore, MD, District ................................................................ 4-1 
Norfolk, VA, District .................................................................. 5-1 
South Atlantic Division: 
Wilmington, NC, District .......................................................... 6-1 
Charleston, SC, District ................................................................ 7-1 
Savannah, GA, District ................................................................ 8-1 
Jacksonville, FL, District ............................................ 9-1 
Mobile, AL, District .................................................................... 10-1 
Lower Mississippi Valley Division: 
New Orleans, LA, District ..................................... 11-1 
Vicksburg, MS, District ............................................................... 12-1 
Memphis, TN, District ......................................................... ...... 13-1 
St. Louis, MO, District ................................................................ 14-1 
Ohio River Division: 
Nashville, TN, District ................................................................. 15-1 
Louisville, KY, District ................................................................ 16-1 
Huntington, WV, District ......................................................... 17-1 
Pittsburgh, PA, District ................................................................ 18-1 
O hio R iver ............................................................................... 19-1 
North Central Division 
Buffalo, NY, District ................................................................... 20-1 
Detroit, MI, District .................................................................... 21-1 
Chicago, IL, District ........................................................... 22-1 
Rock Island, IL, District ............................................................... 23-1 
St. Paul, MN, District .................................................................. 24-1 
Mississippi River between Missouri River and Minneapolis, MN................. 25-1 
Missouri River Division: 
Omaha, NE, District .................................................................... 26-1 
Kansas City, MO, District ............................................................ 27-1 
Southwestern Division: 
Little Rock, AR, District ........................................................... 28-1 
Tulsa, OK, District .................................................................. 29-1 
Fort Worth, TX, District............................................................. 30-1 
Galveston, TX, District .............................................................. 31-1 
Albuquerque, NM, District .......................................................... 32-1 
South Pacific Division: 
Los Angeles District .................................................................. 33-1 
San Francisco, CA, District ......................................................... 34-1 
Sacramento.CA, District ............................................................. 35-1

Pacific Ocean Division ................................................................ 
North Pacific Division: 
Portland, OR, District ................................................................ 37-1 
Seattle, WA, District ................................................................... 38-1 
Walla Walla, WA, District ........................................................... 39-1 
Alaska, AK, District .................................................................. 40-1 
Board of Engineers for River & Harbors ................................................. 41-1 
Mississippi River Commission ............................................................ 42-1 
Construction Engineering Research Laboratory ......................................... 43-1 
Cold Regions Research & Engineering Laboratory ..................................... 44-1 
Waterways Experiment Station ............................................................ 45-1 
Engineer Topographic Laboratories ....................................................... 46-1 
Water Resources Support Center .......................................................... 47-1 
Pernmanent International Association of Navigation Congresses ...................... 48-1 
International Boundary Waters Board .................................................... 49-1 
Investigation of Projects Under Federal Power Act .......................................... 50-1 
Regulatory Sunken Vessel Removal & National Emergency Preparedness .............. 51-1 
Natural Disaster Preparedness, Response & Recovery Activities........................... 52-1 
California Debris Comnission .............................................................. 53-1 
Appendices: 
Flood Control Reservoirs Operable ............................................... .. A-1 
Flood Control Projects Under Construction......................................... .B-1 
Navigation Locks and Dams Operable ............................................ .. C-1 
Navigation Projects Under Construction ........................................... .D-1 
Multiple-Purpose Projects Including Power in Operation ........................ .E-1 
Multiple-Purpose Projects Including Power Under Construction ................ F-1 
Flood Damages Sustained and Prevented .......................................... G-1 
In d ex ............................... ....................................................... 
36-1 
I-1

NEW ENGLAND DIVISION * 
The New England Division, an operating division with 
both district and division functions, comprises all of New 
England except western Vermont and small portions of 
Massachusetts and Connecticut along their western 
boundaries, and includes small portions of southeastern 
New York, all embraced in the drainage basins tributary 
to Long Island Sound and the Atlantic Ocean east of the 
New York-Connecticut State line. It also includes Fishers 
Island, NY. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control ............... 
2. Branford Harbor, CT ............... 
3. Cape Cod Canal, MA ................ 
4. Chatham (Stage) Harbor, MA ........ 
5. Great Salt Pond, Block Island, RI .... 
6. Green Harbor, MA ................. 
7. Harbor of Refuge, Block Island, RI ... 
8. Hyannis Harbor, MA ................ 
9. Jonesport Harbor, ME .............. 
10. Milford Harbor, CT ................. 
11. Nantucket (Harbor of Refuge), MA ... 
12. New Haven Harbor, CT ............. 
13. Plymouth Harbor, MA ............. 
14. Point Judith Pond and Harbor 
of Refuge, Point Judith, RI .......... 
15. Portsmouth Harbor and 
Piscataqua River, ME and NH ....... 
16. Providence River and Harbor, RI ..... 
17. Rockport Harbor, ME ................ 
18. Rockport Harbor and Pigeon Cove, 
Rockport, MA ................. 
19. Rye Harbor, NH .................... 
20. Saco River, M E ..................... 
21. Sesuit Harbor, MA .................. 
22. W ells Harbor, ME .................. 
23. Wood Island Harbor and Pool at 
Biddeford, ME ..................... 
24. Reconnaissance and condition surveys 
25. Other authorized navigation projects 
26. Navigation activities pursuant to 
Section 107, Public Law 86-645 
(Preauthorization) .................. 
27. Authorized bridge alteration ......... 
Beach Erosion Control 
28. Revere Beach, MA .................. 
29. Roosevelt Campobello International 
Park, Lubec, M E .................... 
30. Inspection of completed beach erosion 
control projects ..................... 
Page 
1-3 
1-3 
1-3 
1-4 
1-4 
1-4 
1-4 
1-5 
1-5 
1-5 
1-5 
1-6 
1-6 
1-7 
1-7 
1-8 
1-8 
1-9 
1-9 
1-9 
1-10 
1-10 
1-10 
1-11 
1-11 
1-11 
1-11 
1-11 
1-11 
1-12 
31. 
32. 
Other authorized beach erosion 
control projects .................... 
Beach erosion control activities 
pursuant to Section 103, Public Law 
87-874 (Preauthorization) ........... 
Flood Control 
33. Blackstone River Basin, MA and RI .. 
33A. West Hill Dam, MA ................ 
34. Charles River (Natural Valley 
Storage Areas), MA ................. 
35. Connecticut River Basin, VT, 
NH, MA and CT ................... 
35A. Ball Mountain Lake, VT ............ 
35B. Barre Falls Dam, MA ............... 
35C. Beaver Brook, Keene, NH ........... 
35D. Birch Hill Dam, MA ................ 
35E. Colebrook River Lake, CT........... 
35F. Conant Brook Dam, MA........... 
35G. Farmington River, Simsbury, CT .... 
35H. Knightville Dam, MA .............. 
35I. Littleville Lake, MA ................ 
35J. North Hartland Lake, VT ........... 
35K. North Springfield Lake, VT .......... 
35L. Otter Brook Lake, NH .............. 
35M. Riverdale, West Springfield, MA ..... 
35N. Surry Mountain Lake, NH ......... 
350. Townshend Lake, VT ............... 
35P. Tully Lake, MA ................... 
35Q. Union Village Dam, VT ............. 
35R. West Springfield, MA ............... 
36. Housatonic River Basin, CT and MA 
36A. Black Rock Lake, CT ............... 
36B. Hancock Brook Lake, CT ............ 
36C. Hop Brook Lake, CT ................ 
36D. Northfield Brook Lake, CT .......... 
36E. Thomaston Dam, CT ................ 
37. Merrimack River Basin, NH and MA 
37A. Blackwater Dam, NH ............... 
37B. Edward MacDowell Lake, NH ....... 
1-1 
Page 
1-12 
1-12 
1-12 
1-12 
1-12 
1-12 
1-13 
1-13 
1-14 
1-14 
1-14 
1-14 
1-14 
1-15 
1-15 
1-15 
1-15 
1-15 
1-16 
1-16 
1-16 
1-16 
1-17 
1-17 
1-17 
1-17 
1-18 
1-18 
1-18 
1-18 
1-18 
1-19 
1-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Page 
37C. Franklin Falls Dam, NH ............ 
37D. Hopkinton-Everett Lakes, NH ....... 
38. New Bedford, Fairhaven, and 
Acushnet, MA ...................... 
39. New London, CT ................... 
40. Brockton, MA ...................... 
41. Little River, Belfast, ME ........... . 
42. Perley Brook, Fort Kent, ME ........ 
43. Roughans Point, Revere, MA ........ 
44. Stamford, CT ....................... 
45. Thames River Basin, CT, RI and MA 
45A. Buffumville Lake, MA .............. 
45B. East Brimfield Lake, MA ............ 
45C. Hodges Village Dam, MA ........... 
45D. Mansfield Hollow Lake, CT .......... 
45E. West Thompson Lake, CT .......... 
45F. Westville Lake, MA ................. 
46. Town Brook, Quincy and 
Braintree, M A ..................... 
47. West River, New Haven, CT ......... 
48. Inspection of completed flood 
control projects ..................... 
49. Flood control reservoir 
operations .......................... 
50. Hurricane barrier operations ........ 
51. Other authorized flood control projects 
52. Flood control work under 
special authorization ................ 
53. Deauthorized projects ............... 
General Investigations 
54. Surveys ........................... 
55. Collection and Study of Basic Data ... 
1-19 56. Planning, Engineering and Design ... 
1-19 57. Preconstruction Engineering and 
Design ......................... 
1-20 
1-20 Tables 
1-20 Table 1-A Cost & Financial Statement ..... 
1-20 Table 1-B Authorizing Legislation ......... 
1-21 Table 1-C Other Authorized 
1-21 Navigation Projects ............. 
1-21 Table 1-D Other Authorized Beach 
1-22 Erosion Control Projects ........ 
1-22 Table 1-E Other Authorized 
1-22 Flood Control Projects .......... 
1-22 Table 1-F Other Authorized Multiple- 
1-22 Purpose Projects including 
1-22 Power ........................ 
1-22 Table 1-G Deauthorized Projects ........... 
Table 1-H Navigation Activities 
1-23 Pursuant to Sec. 107 ............ 
1-23 Table 1-I Beach Erosion Activities 
Pursuant to Sec. 103 ............ 
1-23 Table 1-J Flood Control Activities 
Pursuant to Sec. 205 ............ 
1-24 Table 1-K Blackstone River Basin ......... 
1-24 Table 1-L Connecticut River Basin ........ 
1-24 Table 1-M Housatonic River Basin ......... 
Table 1-N Merrimack River Basin ......... 
1-24 Table 1-0 Thames River Basin ............ 
1-25 Table 1-P Boston Harbor, MA ............. 
Table 1-Q Reconnaissance and 
Condition Surveys .............. 
1-25 
1-25
1-2 
Page 
1-25 
1-25 
1-26 
1-34 
1-39 
1-42 
1-43 
1-44 
1-45 
1-47 
1-47 
1-48 
1-48 
1-49 
1-51 
1-52 
1-53 
1-53 
1-54 
__

NEW ENGLAND DIVISION 
Navigation 
1. AQUATIC PLANT CONTROL 
Location. The program is conducted in all navigable 
waters, tributary streams, connecting channels and associated 
waters under the New England Division jurisdiction. 
Existing project. The purpose of the program is to 
provide technical assistance in the eradication or control 
of aquatic plants that are causing or have the potential 
to cause major economic problems in the above waterways. 
The plant control is done in the interest of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, public health and research. The program 
is administered by the Chief of Engineers, under the 
direction of the Secretary of the Army, and in cooperation 
with other Federal and state agencies. (See Table 
1-B at end of chapter for Acts authorizing existing program). 
Local cooperation. Local interests must contribute 
at least 50 percent of the cost of planning beyond the 
reconnaissance stage and at least 50 percent of the cost 
of controlling the aquatic plants,and in addition must 
hold the United States free from damages that may occur 
from control operations. 
Operations during fiscal year. On request, technical 
information was provided to local interests on specific 
aquatic weed problems. These problems included nuisance 
growth of Eurasian water-milfoil and excessive 
aquatic plant growth and basin filling due to nutrient 
enrichment. We continue to work closely with the States. 
2. BRANFORD HARBOR, CT 
Location. On north shore of Long Island Sound, 
5 miles east of New Haven Harbor, Connecticut. (See 
National Ocean Survey Chart 12372). 
Existing project. A channel 8.5 feet deep and 100 
feet wide from outer harbor to upper wharf in Branford 
Harbor, about 2.3 miles. The existing project was completed 
in 1907. (See Table 1-B at end of chapter for Act 
authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, comprising two wharves 
near head of the harbor and one at mouth of river, are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $71,951 were incurred for preparation of 
plans and specifications and accomplishing pre-dredge 
surveys in connection with maintenance of the Federal 
channel. A maintenance dredging contract was awarded 
in September 1989. Work had not started at close of fiscal 
year. 
3. CAPE COD CANAL, MA 
Location. This waterway is a sea level canal; extending 
from head of Buzzards Bay, MA, to a point on Cape 
Cod Bay about 15 miles southeast of Plymouth Harbor, 
MA. In general direction canal trends from Buzzards Bay 
easterly to Cape Cod Bay. (See National Ocean Survey 
Chart 13246). 
Existing project. For description of existing project 
see Annual Report for 1975. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Navigational 
improvements were completed in April 1963, with 
completion of East Boat Basin extension. Initial recreational 
development consists of public use facilities at 
various locations, which were completed in February 1965. 
Improvements to public use facilities at the East Boat 
Basin were completed in May 1974. Construction of public 
use facilities at Bourne Scenic Park were completed 
in May 1976. Canal is crossed by two high-level highway 
bridges and a vertical-lift railroad bridge. Initial major 
rehabilitation of Bourne Highway Bridge was completed 
in December 1965. More recent major rehabilitation of 
the two highway bridges crossing the canal is completed. 
Rehabilitation of the Bourne Highway Bridge was completed 
in 1981. The Sagamore Highway Bridge was completed 
in 1982. Minor rehabilitation of stone breakwater 
was completed in October 1963. 
Local cooperation. Fully complied with. Local interests 
must also bear 50 percent of future recreational 
development in accordance with 1965 Federal Water 
Project Recreation Act. 
Terminal facilities. There are seven terminals on the 
canal, of which three are privately owned. Four are used 
for receipt and freezing of fish and two are used for receipt 
and storage of oil. Seventh terminal is State pier, 
owned by Commonwealth of Massachusetts, and on north 
bank of canal at Bourne Neck. Terminals are adequate 
for purposes for which they are used. 
Operations during fiscal year. Maintenance: A contract 
for construction of a restroom at the East Boat 
Basin was completed last fiscal year. Final payment was 
still pending at close of fiscal year. A continuing contract 
to repair the abutment decks of the Bourne and Sagamore 
Bridges was completed in November 1988. Payments 
of $713,640 have been made to date on this contract. 
A contract for mooring dolphins and marine railway 
repairs in the West Boat Basin, awarded last fiscal year, 
was completed in March 1989. Payments of $540,414 
have been made thru this fiscal year with final payment 
still pending. A contract for rehabilitation of the vertical 
lift railroad bridge was awarded in November 1988. 
Complications from the re-evaluation of bidders and legal 
proceedings between the Corps and Bay Colony Railroad 
may result in termination of this contract. Work 
was not started at close of fiscal year. A contract for 
painting the Sagamore highway bridge was awarded in 
May 1989. At end of the fiscal year the contract was 42 
percent complete with earnings of $350,000. Other fiscal 
year 1989 costs for work accomplished by hired labor 
and contract were: overhaul patrol boat WAMPANOG 
$27,042; engineering and design for preparation of plans 
and specifications for major rehabilitation of railroad 
bridge $194,439; engineering and design of various ongoing 
maintenance contracts $198,554; replacement and 
repair of project maintenance equipment $68,000; replacement 
parts, repairs and service contract for com- 
1-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
puterized electronic traffic control system $48,830; resource 
management activities $43,000; supervision and 
administration of contract activities $156,554; operation 
and maintenance of railroad bridges $321,806; vessel 
traffic control activities $1,555,681; operation of recreational 
areas $499,600; supervision and administration 
by Division Office $146,451; real estate activities $34,716; 
operating cost of roads, bridges, and project facilities 
$1,043,077 and $135,283 for project condition surveys. 
4. CHATHAM (STAGE) HARBOR, MA 
Location. At northeastern corner of Nantucket Sound, 
about 16 miles east of Hyannis Harbor, MA and 66 miles 
south of Providence Harbor, RI at northern extremity of 
Cape Cod. (See National Ocean Survey Chart 13237). 
Previous project. For details see Annual Report for 
1942. 
Existing project. An entrance channel 10 feet deep 
and 150 feet wide from Chatham Roads into upper harbor. 
(See Table 1-B at end of chapter for Acts authorizing 
existing project). Construction of existing project was 
initiated in September and completed in October 1957. 
By 1961, a break in barrier beach connecting Morris and 
Monomoy Islands caused Federal Channel to fill in completely. 
Local interests dredged an emergency channel 
to obtain 8-foot depth in June 1962 and performed additional 
dredging in 1963. Minimal maintenance dredging 
by the Federal Government in April and May 1964 
provided access to inner harbor for 1964 boating season. 
A new 10-foot channel through Harding Beach to Morris 
Island was completed in July 1965. 
Local cooperation. Fully complied with. 
Terminal facilities. The town operates a wharf on 
the north side of the inner harbor which is leased out to 
commercial users. Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $5,585 were incurred for preparation of an 
environmental assessment and for preparation of plans 
and specifications in connection with proposed maintenance 
dredging to remove severe shoals from the 10-foot 
entrance channel. Work was deferred due to funding 
constraints. Hired labor costs of $63,892 were incurred 
for project condition surveys. 
5. GREAT SALT POND, BLOCK 
ISLAND, RI 
Location. On west shore of Block Island, about 11 
miles southwest by south from Point Judith Harbor, RI, 
and 18 miles southeasterly from Stonington Harbor, CT. 
(See National Ocean Survey Chart 13217). 
Existing project. Provides for a channel 18 feet deep 
from ocean to pond 300 feet wide with a central depth 
of 25 feet for a width of 150 feet; a riprap jetty at the 
entrance on a southerly side extending 350 feet beyond 
18-foot contour (actual length 1,691 feet, including 837 
feet built by State); stone revetment and sand fences to 
protect banks through original beach. (See Table 1-B at 
end of chapter for Acts authorizing existing project). South 
jetty was completed in 1905. 
Local cooperation. Not required on active portion of 
project. 
Terminal facilities. Consist of a wharf with about 
600 feet of publicly available berthage and several privately 
owned and operated small wharves and piers. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $10,849 were incurred for preparation of 
plans and specifications for proposed maintenance dredging. 
Work was deferred due to delays in securing State 
approval and subsequent funding constraints. 
6. GREEN HARBOR, MA 
Location. On west side of Massachusetts Bay within 
the town of Marshfield about 30 miles southeast of Boston 
and 9 miles north of Plymouth Harbor. (See National 
Ocean Survey Chart 13253). 
Existing project. Provides for channel 6 feet deep (8 
feet at entrance), 100 feet wide extending about 4,000 
feet from deep water to head of navigation with small 
turning basin at upstream limit; 5-acre anchorage near 
Town Pier, 6 feet deep; sealing, rebuilding in part, and 
a 200-foot extension of existing west jetty at elevation 
+ 12, with dike to beach berm at elevation + 14 feet, and 
raising east jetty to elevation + 14. (See Table 1-B at 
end of chapter for Act authorizing existing project). Construction 
was completed in October 1969. 
Local cooperation. Fully complied with. 
Terminal facilities. Major terminal facility is Town 
Pier in village of Brant Rock. Facility is a bulkheaded, 
earth-filled landing and parking area about 290 feet wide, 
extending 210 feet into harbor. A marina service is south 
of Town Pier; and a facility for recreational craft has 
been developed on south side of harbor near head of 
navigation. 
Operations during fiscal year. Maintenance: Hired 
labor costs included $281 for work by Waterways Experiment 
Station personnel to complete a report on possible 
entrance modifications (total cost of study to date 
is $89,192); $7,071 for preparation of plans and specifications, 
and $1,057 in connection with resolving a claim 
associated with a fiscal year 1987 dredging contract. Further 
dredging proposed for fiscal year 1989 was deferred 
due to funding constraints. 
7. HARBOR OF REFUGE, BLOCK 
ISLAND, RI 
Location. On east side of Block Island, near south end 
of inner curve of shoreline 13 miles south-southwest from 
Point Judith Harbor and about 25 miles southeasterly 
from Stonington Harbor, CT. (See National Ocean Survey 
Chart 13217). 
Existing project. For description of existing project, 
see Annual Report for 1976. (See Table 1-B at end of 
chapter for Acts authorizing existing project). Completed 
in 1916 except for inactive portion. 
Local cooperation. None required. 
Terminal facilities. Two wharves in harbor, both steel 
1-4

NEW ENGLAND DIVISION 
sheetpile bulkhead which comprises southern and eastern 
limits of basin. Total docking space amounts to 500 
feet. No mechanical-handling facilities are available. One 
wharf owned by town and open to public, is considered 
inadequate for present general needs of boating in harbor. 
There is limited room for expansion of terminal facilities. 
Operations during fiscal year. Maintenance: An 
emergency contract for maintenance dredging of the 15- 
foot entrance channel was awarded in August 1989 after 
required state approvals were secured. The contract was 
71 percent complete at end of fiscal year with earnings 
of $91,600. Hired labor costs of $21,141 were incurred 
for preparation of plans and specifications, $8,928 for 
pre-dredge surveys and $774 for supervision and inspection. 
8. HYANNIS HARBOR, MA 
Location. On south shore of Cape Cod about 16 miles 
west of Chatham, Massachusetts and 20 miles northeast 
of Vineyard Haven, Massachusetts. (See National Ocean 
Survey Chart 13237). 
Existing project. A stone breakwater 1,170 feet long, 
lying about 0.7 mile offshore, dredging to 15.5 feet deep 
in protected area behind breakwater; a channel 12 feet 
deep with widths of 150 and 100 feet in outer and inner 
harbors respectively, an anchorage area 12 feet deep and 
about 5 acres in area adjacent to inner harbor channel 
north of Harbor Bluff; and a riprap jetty 1,000 feet long 
extending south from Dunbar Point. Mean spring tidal 
ranges in outer harbor 3.1 and 3.7 feet, respectively. 
Breakwater was completed in 1882 and dredging behind 
breakwater in 1906. Rehabilitation was necessary to restore 
breakwater to its designed purpose of providing a 
harbor of refuge. Restoration was completed in November 
1961. Construction of 12-foot channel and anchorage 
was initiated in May and completed in November 1959. 
Commonwealth of Massachusetts constructed the jetty 
extending south from Dunbar Point in 1962. (See Table 
1-B at end of chapter for Acts authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. There are two town wharves in 
the inner harbor. One has a bulkhead frontage of about 
800 feet. Other private landings are available. Facilities 
are adequate for existing commerce. 
Operations during fiscal year. Maintenance: An additional 
payment of $11,347 was made on a contract for 
maintenance dredging completed in a previous fiscal year. 
A previous contract claim remained unresolved through 
the end of the fiscal year. 
9. JONESPORT HARBOR, ME 
Location. Jonesport Harbor is situated on the north 
side of Moosabec Reach in Washington County, Maine 
about 190 miles northeast of Portland, Maine, and about 
40 miles southwest of the Canadian border at Eastport, 
Maine. 
Existing project. Provides for a combined rubble 
mound and cellular steel sheet pile breakwater, 1,200 
feet in length; a 15-acre anchorage composed of 9 acres, 
6 feet deep, and 6 acres, 8 feet deep; and an entrance 
channel 100 feet wide and 8 feet deep. Latest approved 
cost estimate (July 1989) is $8,500,000. (See Table 1-B 
at end of chapter for Act authorizing existing project). 
Local cooperation. For full description see Annual 
Report for 1987. Local interests contributed $33,000 this 
fiscal year for a total to date of $833,000 toward their 
10 percent cash contribution during construction. Local 
interests must pay an additional 10 percent of project 
costs within a period of 30 years following completion. 
Terminal facilities. There are thirteen privately owned 
wharves in the harbor, twelve of which are used by local 
fishermen and one which is used for receiving about three 
million gallons of petroleum annually. 
Operations during fiscal year. New work: The 
breakwater and improvement dredging contract awarded 
in previous fiscal year was completed in November 1988. 
Final quantities are still pending with contract payments 
of $7,142,984 to date. Removal of rock encountered 
during dredging of anchorage area is expected to 
be accomplished in fiscal year 1990 by amendment to 
the existing contract. 
10. MILFORD HARBOR, CT 
Location. On north shore of Long Island Sound, about 
8 miles west of New Haven Harbor, CT. (See National 
Ocean Survey Chart 12370). 
Previous projects. For details, see Annual Report for 
1915 and Annual Report for 1938. 
Existing project. Provides for a channel, an anchorage 
and two riprap jetties. For further detailed description, 
see Annual Report for 1974. Project is complete 
except for an inactive 8-foot east basin anchorage. Burns 
Point jetty was repaired in 1963. (See Table 1-B at end 
of chapter for Acts authorizing existing project). 
Local cooperation. Specifically authorized project. 
Fully complied with for completed portion. Disposal areas 
are required for maintenance. 
Terminal facilities. Three bulkhead wharves near 
entrance are used by oyster industry. City wharf and 
launching ramp near head of navigation are open to 
public use. Connecticut State Shellfish Commission operates 
a small wharf not open to public. There are several 
yacht landings. Facilities are adequate for existing traffic. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $514 were incurred in connection with 
closing out the maintenance dredging contract completed 
last fiscal year. The final Federal portion of the 
contract was $496,879. Hired labor costs of $11,599 were 
incurred for project condition surveys. 
11. NANTUCKET (HARBOR OF 
REFUGE), MA 
Location. On north shore of Nantucket Island about 
26 miles southeast of Hyannis Harbor, Massachusetts. 
(See National Ocean Survey Chart 13241). 
1-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Previous project. For details see page 1747, Annual 
Report for 1915. 
Existing project. A channel 15 feet deep, without 
prescribed width, through the bar at entrance, about 1.6 
miles long, a riprap jetty on east side about 6,987 feet 
long, and a jetty on the west side 5,755 feet long. Existing 
project is complete. Channel completed in 1930; east jetty 
completed in 1907; and minor rehabilitation ofjetty completed 
in 1963. Approximately 4,955 feet of west jetty 
have been constructed. 
Local cooperation. Fully complied with. 
Terminal facilities. Five piers affording about 3,200 
feet of berthing space. Facilities are adequate for present 
commerce. 
Operations during fiscal year. Maintenance: Dredging 
of the 15-foot channel by the Government-owned 
hopper dredge CURRITUCK was accomplished from 7 
November to 9 December 1988 at a rental cost of $218,462. 
Approximately 55,600 cubic yards of material were removed. 
Hired labor costs of $36,538 were incurred for 
surveys associated with the dredging. 
12. NEW HAVEN HARBOR, CT 
Location. On north shore of Long Island Sound, about 
75 miles east of New York City. (See National Ocean 
Survey Chart 12371). 
Previous project. For details, see Annual Report for 
1915 and 1938. 
Existing project. A main channel 35 feet deep, 400 
to 800 feet wide, from Long Island Sound to Tomlinson 
Bridge; two anchorage basins below Tomlinson Bridge 
of 16- and 15-foot depths; a pile-and-riprap dike about 
4,200 feet long, to contract tidal flow at Fort Hale Bar; 
a channel 12 feet deep and 100 to 150 feet wide, from 
southwest corner of 16-foot anchorage basin via City 
Point and West Haven wharf front to Kimberly Avenue 
Bridge; thence 12 feet deep and prevailing width of 75 
feet up West River to about 600 feet upstream of Kimberly 
Avenue Bridge, and an anchorage basin 6 feet deep 
in West River opposite Mars wharf; a channel 100 feet 
wide and 12 feet deep from 15-foot anchorage basin toward 
Brewery Street, about 300 feet; a channel in Quinnipiac 
River 22 feet deep and 250 to 400 feet wide to a 
point about 1,000 feet above Ferry Street, thence 16 feet 
deep and 200 feet wide to Grand Avenue, with turning 
basin 22 feet deep, 200 to 800 feet wide, and 700 feet 
long at mouth of Mill River; a channel up Mill River 12 
feet deep, 200 feet wide to junction of two branches above 
Chapel Street, thence to Grand Avenue, 100 feet wide 
in East Branch and generally 125 feet wide in West 
Branch; and removal of certain obstructive rocks in Morris 
Cove. Modification authorized by 1986 Water Resources 
Development Act provides for deepening the main 
ship channel to 40 feet; widening main ship channel from 
400 to 500 feet; widening ship channel bend at Southwest 
Ledge from 500 feet to a minimum of 780 feet, straightening 
the channel bend downstream of the existing turning 
basin and; revising the configuration of the existing 
35-foot deep turning basin to provide a common, smaller 
40-foot turning basin. 
Total estimated cost (July 1988) for new work is 
$33,250,000 exclusive of $4,205,246 for new work completed 
before 1953 and amounts expended on previous 
projects. The 22-foot channel and turning basin is to be 
restudied. Estimated cost (1960) of this portion is $980,000. 
(See Table 1-B at end of chapter for Acts authorizing 
existing project). 
Local cooperation. Fully complied with for completed 
work. Assurances for 1986 modifications have not 
been requested. Local interests must provide all lands, 
easements, rights-of-way, and dredged material disposal 
areas necessary for construction and later maintenance 
of the project; pay 100 percent of the costs for local improvements, 
presently estimated at $6,735,000; pay 25 
percent of project costs allocated to deep draft navigation 
during construction, presently estimated at $6,630,000; 
and pay an additional 10 percent of project costs within 
the 30-year period following construction, offset by a 
credit for the value of lands, easements, rights-of-way, 
relocations (except utility relocations) and dredged material 
disposal areas. 
Terminal facilities. Port of New Haven is served by 
24 waterfront facilities; most are within city limits of 
New Haven. Improved waterways within port area along 
which facilities are located include West River, Main 
Harbor, West and East Branches of Mill River, and Quinnipiac 
River channels. Facilities are all privately owned 
and operated with exception of city wharf and U.S. Coast 
Guard wharf. Depths alongside piers and wharves range 
from 35 to zero feet at mean low water. Some of the 
facilities have rail connections and all are accessible by 
paved streets. Facilities are adequate for existing commerce. 
(For further details see Ports of Southern New 
England No. 4, revised 1983). 
Operations during fiscal year. New work: The modification 
authorized by the Water Resources Development 
Act of 1986 was officially placed in the "inactive" 
category as of October 5, 1989 due to insufficient economic 
justification. Maintenance: Maintenance dredging 
of the West River channel under a contract awarded last 
fiscal year was completed in February 1989. A total of 
107,051 cubic yards of material was removed at a cost 
of $776,055. Final contract amount was $851,055. Hired 
labor costs of $333,882 were incurred for sampling and 
testing, supervision and inspection, after dredge surveys 
and plotting. 
13. PLYMOUTH HARBOR, MA 
Location. Harbor is 45 miles by water south of Boston. 
Its outer anchorage, the "Cow Yard," is common to Plymouth, 
Duxbury, and Kingston. (See National Ocean Survey 
Chart 13253). 
Previous projects. For details, see Annual Report for 
1815 and 1938. 
Existing project. Provides for: protecting by riprap 
sections of Long Beach damaged by storm of November 
1898, and restoring Eel River to its former course; dredging 
a channel 18 feet deep and 200 feet wide, increased 
1-6

NEW ENGLAND DIVISION 
at entrance and on curves, from the bay to town wharves, 
formerly in areas south of State Pier, a distance of about 
2.5 miles, with a suitable turning basin at inner end; 
dredging a channel 150 feet wide, 15 feet deep, extending 
northwesterly about 0.3 miles from a point off site of 
northerly Craigs Wharf (now State Pier) with a turning 
basin 300 feet square, and of same depth, at its northwesterly 
end; maintenance of area dredged to 18 feet deep 
by the Commonwealth of Massachusetts, connecting 15- 
foot channel with 18-foot channel in vicinity of State 
Pier; a rubblestone breakwater extending 1,400 feet 
easterly from a point north of Town Wharf, and thence 
southeasterly for 2,100 feet; an anchorage 8 feet deep 
and 60 acres in area inside breakwater; and elimination 
of authorized 18-foot anchorage from existing project; 
recreational development, to provide for sport fishing 
from breakwater, consisting of stone causeway about 360 
feet long from westerly end of breakwater to land, guardrail 
along top of breakwater and causeway, footbridge 
spanning a navigation opening through breakwater, and 
public access, parking and sanitary facilities for sport 
fisherman use. (See Table 1-B at end of chapter for Acts 
authorizing existing project). Project is complete. Construction 
of anchorage 8 feet deep and 60 acres in area 
inside breakwater was completed in 1967. Construction 
of the rubblestone breakwater was completed in 1971. 
Rehabilitation of Long Beach Dike was completed in 
1971. 
Local cooperation. Fully complied with. 
Terminal facilities. There are three wharves of pile 
and timber construction; one is owned by the state, one 
by the town, and the third by Plymouth Yacht Club. 
State and town wharves are open to public use. In addition, 
there are two boatyards with marine railway facilities 
along waterfront, equipped for boat building and 
repairs. Local interests will maintain existing public 
landings open to all on equal terms, and provide all necessary 
mooring facilities in anchorage. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $9,268 were incurred for work on an environmental 
assessment and preparation of plans and 
specifications for repairs to a section of Plymouth Long 
Beach Dike. 
14. POINT JUDITH POND 
AND HARBOR OF REFUGE, 
POINT JUDITH, RI 
Location. Point Judith marks southwestern entrance 
to Narragansett Bay. Harbor lies in shallow bight west 
of point, about 14 miles southwest of Newport Harbor, 
RI, and 33 miles east of New London Harbor, CT. Point 
Judith Pond is a shallow salt pond, with a length north 
and south of about 4 miles, lying in rear of sandy beach 
of Rhode Island shore, just west of Point Judith Harbor 
by a narrow opening through sand dunes. (See National 
Ocean Survey Charts 13218 and 13219). 
Previous project. For details see Annual Report for 
1948. 
Existing project. For description of existing project 
see Annual Report for 1977. (See Table 1-B at end of 
chapter for Acts authorizing existing project). All work 
for project authorized prior to 1949 was completed in 
1950. Breakwaters were completed in 1914 and dredging 
of shoals in project area was done in 1921. Main and 
east shore arm breakwater had deteriorated and required 
restoration to project design. In 1962 reconstruction 
of east arm breakwater and main breakwater dock 
facilities were completed. Rehabilitation required for remainder 
of breakwater restoration was completed in October 
1963. The extension of the 15-foot channel was 
completed in April 1977. 
Local cooperation. Fully complied with. 
Terminal facilities. Consist of one town wharf of steel 
sheetpile bulkhead construction which comprises southern 
and eastern limits of basin. Total docking space 
amounts to 500 feet. No mechanical handling facilities 
are available. Wharf is owned by the town and open to 
the public. State of Rhode Island maintains two state 
piers, one in Galilee and one in Jerusalem, each having 
about 500 feet of berthing space. A facility comprising 
a bulkhead with 15 finger piers projecting channelward 
there from provides berthing space of about 4,000 linear 
feet. This facility is used for receipt of fish and fish products. 
Mechanical handling facilities including fish pumps, 
are available for discharge of cargo. In addition, there 
are approximately 10 small privately owned wharves 
used in the fishing business and passenger traffic. Facilities 
are adequate for existing commerce. 
Operations during fiscal year. Maintenance: Payment 
of $155,360 was made for claims relating to the 
main breakwater repair contract which was terminated 
in fiscal year 1984. Total contract costs through the end 
of the fiscal year amounted to $3,180,673. Hired labor 
costs associated with claims resolution this fiscal year 
totalled $11,593. Adjustments totalling $14,703 were 
made to correct prior year charges associated with the 
claim resolution. 
15. PORTSMOUTH HARBOR AND 
PISCATAQUA RIVER, ME AND NH 
Location. Piscataqua River forms a portion of boundary 
between Maine and New Hampshire. Mouth of this 
river is called Portsmouth Harbor. It is 45 miles northeast 
of Boston Harbor, MA and 37 miles southwest of 
Portland Harbor, ME. (See National Ocean Survey Chart 
13278). 
Previous project. For details see Annual Report for 
1892. 
Existing project. Removal of ledge rock areas in vicinity 
of Gangway Rock, southwest point of Badgers Island 
and Boiling Rock to 35 feet deep; widening 35-foot 
channel at bends by removal of ledge rock areas in vicinity 
of Henderson Point, Gangway Rock, Badgers Island, 
Maine-New Hampshire Interstate Bridge and Boiling 
Rock; and extending channel from above Boiling Rock 
to a point about 1,700 feet above Atlantic Terminal Sales 
dock in Newington generally 400 feet wide, and 35 feet 
deep below mean low water with manuevering basins 
above Boiling Rock and at head of project; channel 6 feet 
deep, 100 feet wide from Little Harbor through Rye-New 
1-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Castle drawbridge, then northerly between mainland and 
Leach's Island to deep water in vicinity of Shapleigh and 
Goat Islands, channel 75 feet wide 6 feet deep up Sagamore 
Creek to public landing on downstream side of 
Sagamore Avenue bridge and anchorage strip, 6 feet 
deep, 75 feet wide, totalling 3 acres, adjacent to channel 
in Sagamore Creek. Public Law 86-645, Sec. 107, 1960 
River and Harbor Act, as amended in 1965 and by Chief 
of Engineers, December 23, 1965 authorized construction 
of the 6-foot channels and anchorages. Modification 
authorized by 1986 Water Resources Development Act 
provides for: widening of the 35-foot deep channel from 
600 feet to 1,000 feet between two vertical lift bridges; 
widening northern limit of 35-foot deep channel adjacent 
to Badgers Island by 100 feet; and widening southern 
limit of existing 35-foot deep channel at Goat Island from 
400 to 550 feet. Total estimated cost (September 1989) 
for new work is $22,200,000 exclusive of $5,384,043 for 
new work completed before 1971 and amounts expended 
on previous projects. (See Table 1-B at end of chapter for 
Acts authorizing existing project). 
Local cooperation. Fully complied with for completed 
work. Assurances for 1986 modification were executed 
on February 4, 1988. Local interests must pay 
the initial 25 percent of project costs concurrent with 
project construction and reimburse the additional 10 percent 
within the 30-year period following completion of 
construction. In addition, local interests must do the following, 
for which there is no estimate of cost: provide 
all lands, easements and rights-of-way necessary for construction 
and later maintenance of the project including 
suitable areas determined by the Chief of Engineers to 
be required in the general public interest for initial and 
later disposal of dredged material and including necessary 
retaining dikes, bulkheads, and embankments 
therefor, or the costs of such retaining works; provide 
and maintain adequate terminal and transfer facilities 
open to all on equal terms; provide and maintain adequate 
depths in berthing areas and local access channels 
serving the terminals; accomplish all alterations and 
relocations of transportation facilities (excluding railroads, 
combined highway and railroad and publicly owned 
highway bridges and approaches thereto), storm drains, 
sewer outfalls, utilities and other structures and improvements 
made necessary by the project; prohibit the 
erection of any structure, within a distance to be determined 
by the Chief of Engineers, from the bottom edge 
of the proposed channel and turning basin. 
Terminal facilities. Waterfront terminals are chiefly 
on south bank of Piscataqua River in Portsmouth and 
Newington, U.S. Navy Yard is on opposite bank at Kittery, 
Maine. Eighteen piers, wharves, and landings represent 
available terminals for handling the port's waterborne 
commerce. Navy Yard is not used for commercial 
activities. On Maine side of river are a town landing and 
two docks. On New Hampshire side there are 13 terminals, 
6 of which include a public landing, 2 docks, 3 
facilities used for vessel mooring and landings, are at 
Portsmouth. In addition there are a number of private 
recreational boat docks. Terminal facilities are considered 
adequate for existing commerce. (See Port Series 1 
for Ports of Searsport and Portland, Maine, and Portsmouth, 
NH). 
Operations during fiscal year. New work: The contract 
for improvement dredging was awarded in July 
1989. The contract was 7 percent complete ending the 
fiscal year. Contract payments of $780,000 Federal and 
$260,000 Contributed Funds have been processed ending 
this fiscal year. Maintenance: Hired labor costs of $39,957 
were incurred for project condition surveys in preparation 
for scheduled maintenance dredging. 
16. PROVIDENCE RIVER and 
HARBOR, RI 
Location. Formed at city of Providence by junction of 
Seekonk River and two small streams which rise in 
northern Rhode Island. It is tidal and flows southerly in 
a deep channel between broad flats about 8 miles, emptying 
into Narragansett Bay. (See National Ocean Survey 
Charts 13224 and 13225). 
Previous projects. For details see Annual Report for 
1915, 1936 and 1938. 
Existing project. Channel 40 feet deep, generally 600 
feet wide from deep water in Narragansett Bay just south 
of Prudence Island Light to turn below Field Point at 
Providence, thence up to 1,700 feet wide to existing project 
limit at Fox Point, with easing of bends to minimum 
radius of 5,000 feet, excluding marginal strip 75 feet 
wide channelward of established harbor lines; channel 
30 feet deep and 150 feet wide, extending northeastward 
from upper end of existing project to vicinity of India 
Point at mouth of Seekonk River. Existing project was 
completed in January 1976 with the removal of rock and 
unclassified material in the 40-foot channel. Dredging 
of ordinary material in the 40-foot channel was completed 
in June 1971. The 35-foot channel was completed 
in 1949. (See Table 1-B at end of chapter for Acts authorizing 
existing project). 
Local cooperation. Assurances have been received. 
However, local interests have yet to provide berthing 
areas commensurate to channel depths. 
Terminal facilities. There are 27 water terminal facilities 
serving port of Providence, Rhode Island. Threefourths 
of all facilities have railway connections. Four 
facilities are owned by city of Providence and two by 
State of Rhode Island. Facilities are adequate for existing 
commerce. (For details see Port and Terminal Facilities 
of Southern New England No. 4, revised in 1952). 
Operations during fiscal year. Maintenance: Contract 
costs of $251,000 were expended for activity under 
the Dredged Material Management Program. In addition, 
hired labor costs of $54,092 were incurred for surveys, 
sampling and testing. 
17. ROCKPORT HARBOR, ME 
Location. On the westerly side of Penobscot Bay, about 
6 miles north of Rockland, Maine. (See National Ocean 
Survey Charts 13305 and 13307). 
1-8

NEW ENGLAND DIVISION 
Previous project. For details see Annual Report for 
1915. 
Existing project. Remove the ledge at the entrance 
to the depth of 15 feet at mean low tide thereby widening 
the entrance channel about 250 feet. The mean range in 
tides is 9.8 feet. Project was completed in December 1913. 
Local cooperation. None required. 
Terminal facilities. The major facility is a town operated 
marine park. There is a Rockport Boat Club, apprenticeshop, 
marina and a town operated commercial 
bulkhead. Facilities are adequate for existing commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $6,704 were incurred in connection with 
closing out the maintenance dredging contract completed 
in fiscal year 1988 and for project condition surveys. 
18. ROCKPORT HARBOR AND PIGEON 
COVE, ROCKPORT, MA 
Location. The town of Rockport is located on the seaward 
end of Cape Ann on the northeast Massachusetts 
coast about 35 miles north of Boston. The town is bordered 
by the city of Gloucester to the west, Essex Bay 
to the north, Massachusetts Bay to the south, and Sandy 
Bay to the east. (See National Ocean Survey Charts 13278 
and 13279). 
Existing project. Rebuilding the two breakwaters at 
entrance of harbor with rubblestone to a height of 18.5 
feet and removing the principal rocks in the harbor. This 
work was completed in 1905. Current modification: An 
access channel- 10 feet deep at mean low water (MLW) 
by 80 feet wide, leading from deep water outside the 
existing Federal breakwaters 1,100 feet to the town wharf 
at the center of the harbor. At the wharf the 10-foot 
channel branches to form two 40-foot-wide channels 
leading to the north and south inner anchorage basins 
which are separated by the wharf. The North Basin would 
have an area of 1.7 acres and a depth of -8 feet MLW. 
The South Basin would have an area of 1.3 acres and a 
depth of -8 feet MLW. Two additional outer harbor 
anchorages, both 8 feet deep at MLW would be located 
along the 80-foot wide access channel between the breakwaters 
and the town wharf. 
The plan of improvement developed for Pigeon Cove 
consists of a 75-foot wide channel -10 feet deep MLW 
extending from deep water outside the breakwater 550 
feet across the southeast end of the cove to the public 
pier and offloading facilities. An anchorage area north 
of the channel would be dredged to -8 feet deep MLW. 
(See Table 1-B at end of chapter for Acts authorizing 
existing project). 
Local cooperation. For the current modification: contribute 
in cash, prior to construction, 3.3 percent of the 
first cost of construction; provide, maintain and operate 
without cost to the United States, an adequate public 
landing with provisions for the sale of motor fuel, lubricants 
and potable water open and available to the use 
of all on equal terms; provide without cost to the United 
States all necessary lands, easements and rights-of-way; 
hold and save the United States free from damages that 
may result from construction, operation, and maintenance 
of the project, except for damages due to the fault 
or negligence of the United States or its contractors; 
accomplish without cost to the United States alterations 
and relocations as required in sewer, water supply, 
drainage and other utility facilities; provide and maintain 
mooring facilities as needed for transient and local 
vessels as well as necessary access roads, parking areas 
and other needed public-use shore facilities; assume full 
responsibility for all project costs in excess of the Federal 
statutory cost limitations; establish regulations prohibiting 
the discharge of untreated sewage, garbage, and 
other pollutants in the waters of the harbor. 
Terminal facilities. There are four commercial 
wharves, one of granite, the others of timber construction. 
There is one yacht club with a public landing. Facilities 
are adequate for present commerce. 
Operations during fiscal year. New work: Final adjustments 
on claims for improvement dredging completed 
in a previous fiscal year were made in May 1989. 
Final contract amount was $1,167,381. 
19. RYE HARBOR, NH 
Location. On Atlantic coast of New Hampshire about 
five miles south of Portsmouth Harbor. It is a natural 
cove of about 39 acres protected by two breakwaters. (See 
National Ocean Survey Chart 13283). 
Existing project. Provides for dredging a channel 100 
feet wide and 10 feet deep for 600 feet through entrance, 
thence 8 feet deep for 1,700 feet within harbor; dredging 
two 5-acre anchorages, one 8 feet deep and the other 6 
feet deep; and maintaining existing breakwaters. Project 
depths refer to mean low water. Mean range of tide is 
8.4 feet. Existing project was essentially completed in 
October 1962. Removal of ledge encountered during 
dredging process was completed in July 1964. (See Table 
1-B at end of chapter for Act authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. Much of the shoreline around Rye 
Harbor is undeveloped State property. Private ownership 
is limited to about 500 feet on the north shore west 
of Ragged Neck State Park, and to the south shore between 
the bridge and breakwater. State docking facilities 
and a boat launching ramp are available at the head 
of the harbor. Primarily, berthing is in the Federal and 
State anchorages. Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $16,082 were incurred for preparation and 
review of plans and specifications for proposed maintenance 
dredging and $7,600 for pre-dredge surveys. New 
specifications reflected a change from upland disposal to 
the Cape Arundel Disposal Site. 
20. SACO RIVER, ME 
Location. Rises in White Mountain region of New 
Hampshire at an elevation about 1,900 feet above sea 
1-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
level, flows about 105 miles in a general southeasterly 
direction, and discharges into Atlantic Ocean about 16 
miles southwest of Portland, Maine. (See National Ocean 
Survey Chart 13287). 
Existing project. For description of completed existing 
portion of project see Annual Report for 1978. For a 
description of completed improvement of project see Annual 
Report for 1983. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves of solid 
fill construction at Saco and Biddeford, none of which 
has railroad connection; and a small pier near mouth of 
river used for summer passenger business. 
Operations during fiscal year. Maintenance: Bids 
were opened in November 1988 for proposed maintenance 
dredging of the entrance channel and three downstream 
anchorages. Only one bid was received, and it 
was rejected as being substantially above the awardable 
limit. The bidder protested the reasonableness of the 
government estimate. Costs for the year included $7,591 
for preparation of plans and specifications, $15,647 for 
performing and plotting pre-dredge surveys, and $8,918 
for review of the bid protest by NED and East Coast 
Dredge Estimating Team personnel. Funds in the amount 
of $3,780 were deobligated from a fiscal year 1988 contract 
for locating and removing navigation hazards and 
spindles from the entrance area. 
21. SESUIT HARBOR, MA 
Location. Sesuit Harbor is located on the north shore 
of Dennis in Barnstable County, about 85 miles southeast 
of Boston, MA. The town of Dennis is bordered on 
the north by Cape Cod Bay, Brewster and Harwich on 
the east, Nantucket Sound on the south, and Yarmouth 
on the west. Land area within the town is 20.66 square 
miles and has a tidal shoreline of 29.8 miles. (See National 
Ocean Survey Chart 13250). 
Existing project. Provides for a channel 6 feet deep 
below mean low water and 100 feet wide from deep water 
in Cape Cod Bay to a point opposite the Dennis Yacht 
Club thence reducing in width to 80 feet at the entrance 
to the inner harbor basin, for a total channel length of 
2,400 feet. (See Table 1-B at end of chapter for Act authorizing 
existing project). Project was completed in August 
1982. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Hired 
labor costs in the amount of $865 were incurred in connection 
with closing out a maintenance dredging contract 
for work in fiscal year 1988. Funds in the amount 
of $1,103 were deobligated upon final payment. Hired 
labor costs of $1,397 were incurred for project condition 
surveys. 
22. WELLS HARBOR, ME 
Location. In town of Wells at mouth of Webhannet 
River about 20 miles northeast of Portsmouth Harbor 
and about 34 miles southwest of Portland Harbor. (See 
National Ocean Survey Chart 13286). 
Existing project. Repairs to an old Government pier 
about 750 feet long, made of cribwork ballasted with 
stone extending seaward from Drakes Island; and anchorage 
basin 7.4 acres in area and 6 feet deep; a channel 
100 to 150 feet wide, extending from deep water in the 
Atlantic Ocean to inner end of basin, with seaward section 
8 feet deep, and harbor section 6 feet deep; and two 
converging stone jetties, one extending 940 feet easterly 
from Wells Beach and the other 840 feet southerly from 
Drakes Island, separated so as to provide a clear opening 
400 feet wide, and for revetment of seaward face of tip 
of Wells Beach. Extension of the Wells Beach jetty to a 
total length of 2,140 feet and extension of Drakes Island 
jetty to a total length of 1,865 feet, and dredging a 300- 
by 450-foot settling basin south of the anchorage, was 
authorized by the Chief of Engineers on September 20, 
1965. Project was completed in April 1967. (See Table 
1-B at end of chapter for Acts authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. There is one wharf of pile and 
timber construction on the north side of the anchorage. 
Facility is owned and operated by the town of Wells and 
is considered adequate. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $63,945 were incurred for project condition 
surveys, sampling and testing, wave study and environmental 
assessment. 
23. WOOD ISLAND HARBOR AND 
POOL AT BIDDEFORD, ME 
Location. This harbor is situated at the southern end 
of Saco Bay, ME, immediately south of the mouth of the 
Saco River. It is 20 miles southwest of Portland, Maine, 
and 30 miles northeast of Portsmouth, New Hampshire. 
(See National Ocean Survey Chart 13286). 
Existing project. Provides for a basin in the Pool 6 
feet deep, approximately 9.7 acres in extent, and three 
icebreakers south of Fishermen's Wharf. The existing 
project was completed in 1956. (See Table 1-B at end of 
chapter for Act authorizing existing project). 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves in the 
harbor. Three are of pile and timber, and the other two 
are solid-fill construction. One wharf is used for the receipt 
of seafood, two are used in connection with a yacht 
club, and the remaining two are private. There is no 
public-owned wharf but one of the wharves is open to 
the public free of charge. None of the wharves have railroad 
connections. 
Operations during fiscal year. Maintenance: A contract 
for maintenance dredging of the 6-foot anchorage 
was awarded in December 1988 and completed in May 
1989. A total of 38,452 cubic yards of material was removed 
at a cost of $329,478. Hired labor costs included 
$6,393 for preparation of plans and specifications, $60,725 
1-10

NEW ENGLAND DIVISION 
for supervision and inspection, $23,334 for performing 
and plotting pre- and after-dredge surveys, and $11,040 
for field and NED laboratory work to examine suspended 
solids concentrations in dredging area waters. 
24. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 1-Q at end of chapter). 
25. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 1-C at end of chapter). 
26. NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 
(PREAUTHORIZATION) 
(See Table 1-H at end of chapter). 
Alterations of Bridges 
27. AUTHORIZED BRIDGE 
ALTERATION 
Location. Chelsea Street Highway Bridge, MA. Construction 
was completed in October 1961 with a Federal 
cost of $138,518. In addition non-Federal contributed 
funds amounted to $8,062. For details see page 63 of 
Annual Report for 1962. 
Beach Erosion Control 
28. REVERE BEACH, MA 
Location. In the city of Revere, Suffolk County, Massachusetts, 
approximately 7 miles north of the main entrance 
channel to Boston Harbor and 6 miles northeast 
of the city of Boston. (See National Oceanic and Atmospheric 
Administration Chart No. 13275 and U.S. Geological 
Survey Maps, Boston Bay quadrangle). 
Existing project. Placement of sandfill along 13,000 
feet of beach. The top of the sandfill will be placed at 18 
feet above mean low water, including a 50-foot wide berm, 
sloping one-foot vertical in 15 feet horizontal to meet the 
existing beach. The total width of the beach will extend 
approximately 300 feet, of which, about 185 feet is above 
the mean high water line. The estimated total first cost 
(October 1988) of the project is $8,900,000 of which 35 
percent is non-Federal. (See Table 1-B at end of chapter 
for Acts authorizing existing project). 
Local cooperation. Formal assurances have not been 
requested. Consistent with the cost sharing and financing 
concepts contained in the Water Resources Development 
Act of 1986 (P.L. 99-662), local interests are required 
to: contribute in cash 35 percent of the cost of 
construction of the project, presently estimated at 
$3,115,000; contribute in cash 35 percent of the periodic 
nourishment cost for an initial period of 50 years, now 
estimated at $22,000 annually, such contribution to be 
prior to each nourishment operation; assure the continued 
performance of the periodic nourishment and repair 
of the project after the first 50 years and during the 
economic life as may be required to serve the intended 
purpose; assure that water pollution that would endanger 
the health of bathers would not be permitted; hold 
the United States free from damages due to construction 
of the project; provide all necessary lands, easements and 
rights-of-way for the initial construction and subsequent 
nourishment of the project; assure continued public ownership 
of the shore and its administration for public use 
during the economic life of the project. 
Operations during fiscal year. New work: Preconstruction 
engineering and design continued, including 
the completion of contract plans and specifications. Major 
efforts concentrated on the obtaining of all required 
local permits by the non-Federal sponsor, coordination 
with the state regarding Coastal Zone Management consistency 
determination, and coordination of construction 
of this project with other major work concurrently planned 
for the Revere Beach Reservation by the sponsor. These 
actions must be finalized prior to execution of the Local 
Cooperation Agreement (LCA), and thus the LCA execution 
and initiation of construction (for which initial 
funds have been appropriated) have been delayed. 
29. ROOSEVELT CAMPOBELLO 
INTERNATIONAL PARK, LUBEC, 
ME 
Location. The Roosevelt Campobello International 
Park is located on the southeast end of Campobello Island. 
The island is politically part of New Brunswick, 
Canada and is separated from Lubec, Maine by the Lubec 
Narrows and connected by FDR Memorial Bridge. It is 
approximately 120 miles east of Bangor, Maine. 
Existing project. Stone slope protection to provide 
shoreline protection for the lighthouse at Mulholland 
Point. The stone protection extends 375 feet around the 
point at a height of about 10 feet and ties into stable 
ground at either end of the area protected. The upper 
slope, above the stone protection, is graded and seeded. 
(See Table 1-B at end of chapter for Act authorizing 
existing project). 
Local cooperation. Provide without cost to the United 
States, all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation and maintenance of the project, 
except where such damages are due to the fault or negligence 
of the United States or its contractors; maintain 
and operate the project after completion without cost to 
the United States in accordance with regulations prescribed 
by the Secretary of the Army; prevent future 
encroachment which might interfere with proper functioning 
of the project. 
Operations during fiscal year. New work: The contract 
for shoreline protection, awarded last fiscal year, 
was completed in March 1989. Final contract amount 
was $123,827. 
1-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
30. INSPECTION OF COMPLETED 
BEACH EROSION CONTROL 
PROJECTS 
Inspections of beach erosion projects were not conducted 
in fiscal year 1989. 
31. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 1-D at end of chapter). 
32. BEACH EROSION CONTROL 
ACTIVITIES PURSUANT TO 
SECTION 103 PUBLIC LAW 87-874 
(PREAUTHORIZATION) 
(See Table 1-I at end of chapter). 
Flood Control 
33. BLACKSTONE RIVER BASIN, 
MA AND RI 
Works covered by this plan include a dam and reservoir 
on West River and local protection works at three 
cities on Blackstone River. Flood Control Act of 1944 
authorized plan for a reservoir on West River and local 
protection works at Worcester, MA, and Woonsocket and 
Pawtucket, RI, substantially in accordance with House 
Document 624, 78th Congress, 2nd session. Flood Control 
Act of 1960 authorized a local flood protection project 
at lower Woonsocket, RI, substantially in accordance with 
Senate Document 87, 85th Congress, 2nd session. Local 
protection nonstructural project authorized in 1982 for 
Belmont Park section of Warwick, RI along the Pawtuxet 
River. Streambank protection projects on the 
Blackstone River in Millbury, MA and on the Clear River 
in Burrillville, RI were authorized in 1985. (See Table 
1-K at end of chapter on reservoir and local protection 
projects, Blackstone River Basin, for projects comprising 
authorized plan). 
33A. WEST HILL DAM, MA 
Location. Dam is on West River, MA, 3 miles above 
its confluence with Blackstone River and 2.5 miles northeast 
of Uxbridge, MA. (See Geological Survey maps- 
Blackstone, MA and RI, Milford, MA and Grafton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Work on contract for 
dam and appurtenant structures was initiated in June 
1959 and completed in June 1961. Construction of recreational 
facilities was completed in June 1967. 
Local cooperation. Section 3, Flood Control Act of 
1944 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
for seepage control awarded last fiscal year was completed 
in July 1989. Final contract amount was $198,829. 
A contract to install picnic shelters at various recreation 
parks was awarded in November 1988. The West Hill 
shelter was completed in July 1989 at a cost of $11,420. 
34. CHARLES RIVER (NATURAL 
VALLEY STORAGE AREAS), MA 
Location. The Charles River extends inland from Boston 
Harbor southwesterly toward the Massachusetts- 
Rhode Island border and is some 80 miles long with a 
watershed covering 307 square miles. 
Existing project. The project provides for Federal acquisition 
and protection of 17 natural valley storage areas 
totalling 8,102 acres in what is known as the Middle and 
Upper watershed of the Charles River. The acquisition 
in fee or by easement of the major natural valley storage 
areas within the Charles River watershed is intended 
as a multiple-purpose project for flood control, recreation, 
and fish and wildlife management. The latest cost estimate 
for new work is $9,000,000. (See Table 1-B at end 
of chapter for Act authorizing existing project). Land 
acquisition is complete. 
A total of 3,210 acres have been acquired in fee at a 
cost of $2,152,853 and restrictive easements have been 
obtained for 4,892 acres at a cost of $591,193. 
Local cooperation. Local interests are required to 
prevent modifications or alteration of existing roadways, 
utilities, bridges, culverts, and any other improvements 
that might affect the drainage characteristics of the natural 
storage areas; adopt and enforce regulations to restrict 
development of flood plan lands; and operate and 
maintain the existing dams along the Charles River. 
Local assurances have been received. 
Operations during fiscal year. New Work: Resolution 
of remaining condemnation cases continued. Two 
tracts remain to be settled. Fiscal year costs totalled 
$4,284 in hired labor costs for miscellaneous project 
administration activities and $1,102 for condemnation 
trial activity. Maintenance: Hired labor costs for project 
surveillance and inspection as well as land use administration 
were $127,825. 
35. CONNECTICUT RIVER BASIN 
VT, NH, MA and CT 
Location. Works covered by this project are a series 
of dams and reservoirs on tributaries of Connecticut River 
in Vermont, New Hampshire and Massachusetts, within 
a radius of 230 miles from Hartford, CT and local protection 
works at several cities in the basin. 
Existing project. Flood Control Act of 1936, as 
amended by Act of May 25, 1937, authorized construction 
of 10 reservoirs on tributaries of Connecticut River 
in accordance with plans in House Document 412, 74th 
Congress, 2nd session, as the same may be revised upon 
further investigation of 1936 flood. Flood Control Act of 
1938 approved a general comprehensive plan for control 
of floods and other purposes in Connecticut River Valley, 
as set forth in House Document 455, 75th Congress, 2nd 
session, and authorized $11,524,000 for construction of 
local flood protection projects in the plan. Act of October 
1-12

NEW ENGLAND DIVISION 
15, 1940, modified Act of June 18, 1938, to provide additional 
protection at East Hartford, CT, as set forth in 
House Document 653, 76th Congress, 3rd session. Act of 
August 18, 1941, modified comprehensive plan approved 
in 1938 to include improvements recommended in House 
Document 653, 76th Congress, 3rd session, and House 
Document 724, 76th Congress, 3rd session, with such 
further modifications as may be found justifiable in discretion 
of Secretary of the Army and Chief of Engineers. 
Latter Act also authorized to be appropriated additional 
$6 million for local protection works and $10 million for 
reservoirs. Act of October 26, 1942, further modified plan 
by including construction of Gully Brook conduit at 
Hartford, CT. Flood Control Act of 1944 authorized expenditure 
of $30 million in addition to previous authorization 
for comprehensive plan approved in 1938 and 
modified plan by directing specific consideration of an 
alternative plan of Vermont State Water Conservation 
Board instead of Williamsville Reservoir in West River 
Basin, VT; directing consultation with affected states 
during course of investigations and transmission of proposal 
and plans to each affected state for written views 
and recommendations for reservoir projects heretofore 
authorized for construction at Cambridgeport, Ludlow, 
South Tunbridge, and Gaysville, and resubmission of 
projects or modifications for construction of Sugar Hill 
site. Flood Control Act of 1950 modified project for flood 
control at Hartford, CT, authorized by Flood Control Act 
of 1938, as amended to include Folly Brook dike and 
conduit. Flood Control Act of 1954 modified plan for flood 
control in Connecticut River Basin to provide for construction 
of a reservoir on Otter Brook at South Keene, 
NH, in lieu of any reservoir or reservoirs heretofore authorized. 
This Act further modified plan for West River 
Basin of Connecticut River in Vermont to consist of three 
reservoirs at Ball Mountain, The Island, and Townshend 
sites, in lieu of plan of eight reservoirs authorized in 
Flood Control Act of 1944. Flood Control Act of 1958 
modified plan for flood control in Connecticut River Basin 
to include construction of Littleville Reservoir on Middle 
Branch of Westfield River, MA and Mad River Reservoir 
on Mad River, above Winsted, CT. Flood Control Act of 
1960 included authorization in Connecticut River Basin 
of plan for flood protection on Chicopee River, MA, substantially 
in accordance with House Document 434, 86th 
Congress; plan for flood protection on Westfield River, 
MA, substantially in accordance with Senate Document 
109, 86th Congress; plan for flood control and related 
purposes on Farmington River, CT, substantially in accordance 
with House Document 443, 86th Congress. Flood 
Control Act of 1968 included authorization in Connecticut 
River Basin of plan for construction of Beaver Brook 
Reservoir, on Beaver Brook in Keene, NH, substantially 
in accordance with Senate Document 60, 90th Congress; 
and plan for protection on Park River, CT, substantially 
in accordance with Senate Document 43, 90th Congress. 
Flood Control Act of 1970 deauthorized the construction 
of a reservoir at Claremont, NH. The Water Resources 
Development Act of 1976 deauthorized the construction 
of Gaysville Lake, Vermont project. Flood control projects 
at Cambridgeport Lake, Brockway Lake, Victory 
Lake, South Tunbridge Lake, Ludlow Lake and The Island 
Lake, Vermont; Honey Hill Lake, West Canaan 
Lake, and the Alternative to Sugar Hill Reservoir, New 
Hampshire, were deauthorized in August 1977 in accordance 
with Section 12 of the Water Resources Development 
Act of 1974. The authorization for Beaver Brook 
Lake, New Hampshire project expired in April 1978 due 
to lack of local cooperation. Local protection projects at 
Gardner, MA, Hartford, VT, Wethersfield, CT, and Keene, 
NH authorized and constructed in accordance with Section 
205 of 1948 Flood Control Act. Emergency streambank 
erosion control projects at Brownsville, VT and 
Conway, MA authorized in accordance with Section 14 
of the 1946 Flood Control Act were completed in 1987. 
(See Table 1-L at end of chapter for reservoirs and local 
protection works for Connecticut River Basin). Water 
Resources Development Act of 1986 modified the comprehensive 
plan for the control of flood-waters in the 
Connecticut River Basin, Vermont, New Hampshire, 
Massachusetts, and Connecticut, authorized by Section 
5 of the Act of June 22, 1936 (49 Stat. 1572) by authorizing 
the design, construction, operation, and maintenance 
of facilities at Townshend Dam, West River, Vermont 
to enable upstream migrant adult Atlantic salmon 
to bypass that dam and Ball Mountain Dam, Vermont, 
and to provide at both Townshend and Ball Mountain 
Dams facilities as necessary for the downstream passage 
of juvenile Atlantic salmon. The estimated project cost 
is $1,000,000. 
35A. BALL MOUNTAIN LAKE, VT 
Location. Dam is on West River, 29 miles above its 
junction with Connecticut River at Brattleboro, VT. It 
is 2 miles north of village of Jamaica, VT. (See Geological 
Survey map for Londonderry, VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1957 and 
completed in November 1961. Construction of initial recreation 
facilities was initiated in June 1975 and completed 
in June 1977. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $435,932. 
35B. BARRE FALLS DAM, MA 
Location. Dam is on Ware River in town of Barre, 
MA, 31.9 miles above confluence of Ware and Swift Rivers. 
It is 13 miles, northwest of Worcester, MA. (See 
Geological Survey maps for Barre, MA, and Wachusett 
Mountain, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1956 and 
completed in May 1958. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
1-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The Barre Falls shelter was 
completed in September 1989 at a cost of $11,306. 
35C. BEAVER BROOK, KEENE, NH 
Location. Keene is located in southwestern New 
Hampshire approximately 15 miles north of the Massachusetts 
border and 12 miles east of the Vermont border. 
Existing project. Consists of structural modifications 
to the outlet of the Three Mile Swamp and widening the 
Beaver Brook channel in the reach between Water Street 
and Marlboro Street. (See Table 1-B at end of chapter 
for Act authorizing existing project). 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work: Hired 
labor costs of $28,273 were incurred for preparation of 
the operation and maintenance manual to be furnished 
to local interests. 
35D. BIRCH HILL DAM, MA 
Location. Dam is on Millers River, 27.3 miles above 
its junction with the Connecticut River. It is 1.3 miles 
east of South Royalston, MA and 7.5 miles northwest of 
city of Gardner, MA. (See Geological Survey maps for 
Royalston and Winchendon, MA-NH and Templeton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in June 1940 and 
completed in February 1942. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. Local interests have contributed $32,000 
as their required 50 percent cost sharing of recreational 
development in accordance with 1965 Federal Water 
Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract, 
for guard rail replacement was awarded in February 
1989 and completed in September 1989. Contract amount 
was $40,414. A contract to repair bridges was awarded 
in August 1989. Work had not started at fiscal year end. 
35E. COLEBROOK RIVER LAKE, CT 
Location. Damsite is in town of Colebrook, Litchfield 
County, CT, on West Branch Farmington River about 
3.9 miles upstream from its confluence with Still River 
at Riverton, CT, and about 1.5 miles upstream from 
Goodwin (Hogback) Dam. (See Geological Survey map 
for Winsted, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1965 and 
completed in June 1969. Construction of recreation facilities 
was initiated in August 1969 and completed in 
June 1970. 
Local cooperation. Water supply contract was signed 
by Hartford Connecticut Metropolitan Water District. 
Repayment is being made in accordance with provisions 
of 1958 Water Supply Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final payment 
on the contract awarded last fiscal year to replace 
the emergency generators at various locations was made 
in December 1988. Total contract amount was $54,060 
of which $20,829 was the Colebrook River Lake portion. 
A contract awarded last fiscal year to repaint the service 
and reservoir bridges was terminated for default. A three 
megawatt hydropower facility has been under construction 
by the Metropolitan District of Greater Hartford for 
the last several years at Colebrook Lake. This generating 
facility, consisting of six turbines upstream of the 
intake works, began generation of power in 1989. 
35F. CONANT BROOK DAM, MA 
Location. Site is in south central part of Massachusetts 
in town of Monson. Damsite, across Conant Brook, 
is about 2 miles southeast of community of Monson. (See 
Geological Survey map for Monson, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, 
highway relocations, and appurtenances was initiated 
in June 1964 and completed in December 1966. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
for pavement repairs was awarded in February 1989. 
The contract was 73 percent complete at fiscal year end 
with earnings to date of $27,594. 
35G. FARMINGTON RIVER, 
SIMSBURY, CT 
Location. The town of Simsbury is located in the central 
portion of Hartford County in north-central Connecticut, 
approximately 25 miles east of the New York- 
Connecticut state line and 14 miles northwest of the city 
of Hartford, Connecticut. 
Existing project. The proposed project includes concrete 
grid block and stone slope protection along 900 feet 
of eroding Farmington River streambank. The project 
will protect the river bank and an adjacent 3-foot diameter 
sewer trunk line which has failed twice in the 
past 3 years. 
Local cooperation. The local sponsor shall provide, 
during the period of construction, a cash contribution of 
5 percent of total project costs; provide all lands, easements, 
rights-of-way, and dredged material disposal areas, 
and perform all relocations and alterations of buildings, 
utilities, highways, railroads, bridges, sewers, and related 
and special facilities determined by the Govern- 
1-14

NEW ENGLAND DIVISION 
ment to be necessary for construction of the project; provide 
an additional cash contribution such that the total 
non-Federal contribution is 25 percent of total project 
costs; pay all costs in excess of the Federal statutory cost 
limitation of $500,000; no less than once each year, inform 
affected interests of the limitations of the protection 
afforded by the project. 
Operations during fiscal year. New work: Surveys, 
including topographic and river cross sections, were completed 
during fiscal year 1989. Project layout and cross 
section design were initiated. 
35H. KNIGHTVILLE DAM, MA 
Location. Dam is on Westfield River, 27.5 miles above 
its confluence with Connecticut River. It is 4 miles north 
of town of Huntington, MA, and about 12 miles west of 
city of Northampton, MA. (See Geological Survey map 
for Westhampton, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in August 1939 
and completed in December 1941. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final payment 
on the contract awarded last fiscal year to replace 
the emergency generators at various locations was made 
in December 1988. Total contract amount was $54,060 
of which $15,160 was the Knightville Dam portion. A 
contract to install picnic shelters at various recreation 
parks was awarded in November 1988. The Knightville 
shelter was completed in August 1989 at a cost of $11,420. 
35I. LITTLEVILLE LAKE, MA 
Location. Dam is on Middle Branch of Westfield River, 
1 mile above its confluence with main stem of Westfield 
River and 25.2 miles above confluence of Westfield River 
with Connecticut River, in town of Chester. (See Geological 
Survey map for Chester, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenances was initiated under a multicomponent 
contract in June 1962 and completed in September 
1965. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, and Title III, Water Supply Act of 1958 
applies and fully complied with. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
for access road pavement repairs was awarded in June 
1989 and completed in September 1989. Earnings thru 
end of fiscal year were $24,658 with final payment pending 
at close of fiscal year. A contract for drainage repairs 
was awarded in June 1989. Work had not started at close 
of fiscal year. 
35J. NORTH HARTLAND LAKE, VT 
Location. Dam is on Ottauquechee River, 1.5 miles 
above its junction with Connecticut River and 1 mile 
northwest of North Hartland, VT. Reservoir extends upstream 
5.5 miles. (See Geological Survey map for Hanover, 
NH-VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
was initiated in June 1958 and completed in June 1961. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The contract was 54 percent 
complete at fiscal year end with total earnings of $68,294. 
Work on the North Hartland shelter had not started at 
close of fiscal year. 
35K. NORTH SPRINGFIELD LAKE, VT 
Location. Dam is in town of Springfield, VT, on Black 
River, 8.7 miles above its junction with Connecticut River, 
and 3 miles northwest of Springfield, VT. (See Geological 
Survey maps for Ludlow, VT and Claremont, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
was initiated in May 1958 and completed in November 
1960. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to repair and repaint the spillway bridge awarded last 
fiscal year was completed in August 1989. Final payment 
was pending at fiscal year end. Earnings thru end of 
fiscal year were $297,362. A contract for slope protection 
was awarded in September 1988 and completed in June 
1989. Final contract amount was $368,115. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The contract was 54 percent 
complete at fiscal year end with total earnings of $68,294. 
Work on the North Springfield shelter had not started 
at close of fiscal year. 
35L. OTTER BROOK LAKE, NH 
Location. Dam is on Otter Brook, 2.4 miles upstream 
from its junction with The Branch, which flows 2.5 miles 
to Ashuelot River at Keene. (See National Ocean Survey 
maps for Keene, NH-VT, and Monadnock, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in September 1956 
and completed in August 1958. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordi- 
1-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
nary operation and maintenance activities were conducted 
at a total cost of $583,497. 
35M. RIVERDALE, WEST 
SPRINGFIELD, MA 
Location. The town of West Springfield is situated in 
southwestern Massachusetts about 90 miles west of Boston 
and 135 miles northwest of New York City, on the 
west bank of Connecticut River. Riverdale is in the 
northern portion of the town of West Springfield. 
Existing project. The existing Local Protection Project 
constructed in 1950 involved the construction of approximately 
12,700 feet of earth levee, two pumping stations 
and three stop-log storage structures. The levee 
provides protection against a flood greater than any of 
record reduced by the approved plan of reservoirs. The 
grades are all points above the maximum stage of the 
greatest flood of record, that of March 1936. A plan of 
improvement authorized in 1987 calls for the expansion 
of the gravity outflow and pumping capacity of the existing 
Riverdale Pumping Station. This includes adding 
a 24-inch, diesel powered pump into the existing station. 
The proposed project also includes jacking a separate 5- 
foot diameter, reinforced concrete culvert through the 
dike, running parallel to the existing culvert to increase 
the gravity outflow capacity. The new gravity conduit 
will be equipped with an ungated inlet and an outlet 
structure which includes a 60" x 6" self contained, electronically 
operated sluice gate. During emergencies, the 
gate could be operated manually from a new bridge and 
tower structure on the river side of the dike. An existing 
9-foot diameter culvert, about 400 feet downstream on 
Bagg Brook will be replaced with a realigned 8-foot x 
13-foot corrugated metal arch and a 50-foot long transition 
aligned to tie smoothly into the existing downstream 
channel. Project cost estimate for the modification 
is $818,000. (See Table 1-B at end of chapter for 
Acts authorizing existing project). 
Local cooperation. Formal assurances for improvement 
authorized in 1987 have been requested. The local 
sponsor shall be solely responsible for operating, maintaining, 
replacing, and rehabilitating the project; provide, 
during the period of construction, a cash contribution 
of 5 percent of total project costs, currently 
estimated to be $40,900; provide all lands, easements, 
rights-of-way, and dredged material disposal areas, and 
perform all relocations and alterations of buildings, utilities, 
highways, sewers, and related and special facilities 
determined by the Government to be neceissary for construction 
of the project, currently estimated to be $2,000; 
provide during the period of construction an additional 
cash contribution of 19.8 percent, presently estimated at 
$161,600, that the total contribution equals 25 percent 
of total project costs; prescribe and enforce regulations 
to prevent obstruction of or encroachment on the project 
that would reduce the level of protection it affords, or 
that would hinder operation and maintenance; and the 
local sponsor will assume full responsibility for all project 
costs in excess of $5 million. 
Operations during fiscal year. New work: Plans and 
specifications are completed and a water quality certificate 
has been received from the State. Letter received 
from town of West Springfield in July 1989 confirmed 
town's desire to go forward with the project. The town 
has obtained appraisals for land easements required for 
construction. Initiation of construction dependent upon 
execution of the Local Cooperation Agreement and receipt 
of the sponsor's required cost-sharing funds. 
35N. SURRY MOUNTAIN LAKE, NH 
Location. Dam is on Ashuelot River, 34.6 miles above 
its junction with Connecticut River and 5 miles north of 
Keene, NH. (See Geological Survey maps for Keene and 
Bellows Falls, NH-VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in August 1939 
and completed in June 1942. Initial phase of additional 
recreational facilities completed in September 1969, secondary 
phase in 1980. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $351,551. 
350. TOWNSHEND LAKE, VT 
Location. Dam is on West River, 19.1 miles above its 
junction with Connecticut River at Brattleboro, VT, and 
about 2 miles west of Townshend, VT. Reservoir extends 
upstream about 4 miles. (See Geological Survey maps 
for Saxtons River, VT, and Londonderry, VT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in November 1958 
and completed in June 1961. Initial phase of additional 
recreational facilities completed in October 1969. Secondary 
phase completed in September 1971. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The contract was 54 percent 
complete at fiscal year end with total earnings of $68,294. 
Work on the Townshend shelter had not started at close 
of fiscal year. 
35P. TULLY LAKE, MA 
Location. Dam is on East Branch of Tully River, 3.9 
miles above its junction with Millers River. It is 1 mile 
north of Fryville, MA and 3.5 miles north of Athol, MA. 
(See Geological Survey map for Royalston, MA-NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
1-16

NEW ENGLAND DIVISION 
and appurtenant works was initiated in March 1947 and 
completed in September 1949. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. Local interests must also bear 50 percent 
of future recreational development, in accordance with 
1965 Federal Water Project Recreational Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The contract was 54 percent 
complete at fiscal year end with total earnings of $68,294. 
Work on the Tully shelter was completed in September 
1989 but payment was not processed prior to close of 
fiscal year. A contract for pavement repairs of the administration 
area was awarded in July 1989 and completed 
in September 1989. Final contract amount was $18,339. 
Earnings thru end of fiscal year were $17,139. A contract 
for inlet channel erosion repair was awarded in July 
1989. Work had not started at close of fiscal year. 
35Q. UNION VILLAGE DAM, VT 
Location. Dam is on Ompompanoosuc River, 4 miles 
above its junction with Connecticut River. It is one-fourth 
mile north of Union Village, VT and 11 miles north of 
White River Junction, VT. (See Geological Survey maps 
for Strafford, VT and Mount Cube, NH-VT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
was initiated in March 1947 and completed in June 1950. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $474,338. 
35R. WEST SPRINGFIELD, MA 
Location. The West Springfield Local Protective works 
are located in the town of West Springfield, MA. The 
project is on the west bank of the Connecticut River, 76 
miles above its mouth. (See Geological Survey maps for 
Springfield South and West Springfield, MA-CT). 
Existing Project. This project consists of a system of 
earth levees and concrete floodwalls approximately 24,500 
feet in length. The system starts at high ground, in the 
vicinity of Harrison Place, and extends downstream along 
the Connecticut River and up the north bank of the Westfield 
River to high ground at the Boston & Albany Railroad. 
The work involved raising 13,700 feet of existing 
levee, constructing 2,300 feet of floodwall, improving 2,400 
feet of river bank, and treating 6,100 feet of existing 
levee foundation. Three pumping stations with appurtenant 
drainage facilities were also constructed for the 
disposal of interior drainage. The project, with the approved 
plan of reservoirs, is designed to protect against 
a flood greater than any of record. The levee and floodwall 
grades are, at all points, above the maximum stage 
of the greatest flood of record, that of March 1936. 
The project is a unit of the comprehensive plan of flood 
control and other purposes in the Connecticut River Basin 
and was authorized by the Flood Control Act approved 
June 28, 1938. Construction of project work was initiated 
in March 1939 and completed in July 1942 with the 
exception of foundation treatment along the Westfield 
River south of Agawam Bridge, which was initiated in 
May 1947 and completed in November 1947, and relief 
well and drainage system, which was initiated in August 
1952 and completed in July 1953. (See Table 1-B at end 
of chapter for Acts authorizing existing project). 
Modified Project. A modification of the project was 
authorized in October 1982 providing for the raising of 
the floodwall sections by one foot and the provision of a 
flood forecasting system. Work for flood wall modification 
began in April 1984 and was completed in August 1984. 
The National Weather Service and the town of West 
Springfield have entered into a Memorandum of Agreement 
for the installation and operation of an automated 
flood forecasting system. This system includes a centralized 
micro-computer, four precipitation gages, two 
river gages and a repeater site. When fully functional, 
the automated flood forecasting system will provide the 
town with timely and accurate forecasts of potential 
flooding along both the Connecticut and Westfield Rivers. 
Local Cooperation. Fully complied with. 
Operations during fiscal year. New work: Installation 
of flood forecasting equipment began during August 
1989. The system has been installed and its operation 
is currently being tested. 
36. HOUSATONIC RIVER BASIN, 
CT AND MA 
Seven flood control reservoirs on tributaries of the 
Naugatuck River, principal tributary of the Housatonic 
River, and three local protection projects have been specifically 
authorized as part of an overall plan for flood 
control in the Housatonic River Basin. The Naugatuck 
and Housatonic Rivers converge 12 miles above mouth 
of Housatonic River. A project for emergency snagging 
and clearing of the Blackberry River, a tributary of the 
Housatonic River, was authorized under authority contained 
in Section 208 of the 1954 Flood Control Act. 
Emergency bank protection projects at: Alford, Green 
River, MA; Sheffield, MA; Salisbury, CT; and Squantz 
Pond, Fairfield, CT were authorized under authority provided 
by Section 14 of the 1948 Flood Control Act. Projects 
for local flood protection for: West Branch, Torrington, 
CT; East Branch, Torrington, CT; Pittsfield, MA; 
and Waterbury-Watertown, CT were authorized under 
authority provided by Section 205 of the 1948 Flood Control 
Act. (See Table 1-M on dams, reservoirs, and local 
protection projects for Housatonic River Basin). 
36A. BLACK ROCK LAKE, CT 
Location. Damsite is on Branch Brook about 2 miles 
upstream from its confluence with Naugatuck River in 
towns of Thomaston and Watertown, CT. (See Geological 
Survey map for Thomaston, CT). 
1-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Road relocation completed 
in November 1967. Contract for construction of 
dam and appurtenances was initiated in July 1967 and 
completed in July 1971. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $285,311. 
36B. HANCOCK BROOK LAKE, CT 
Location. Dam is on Hancock Brook in town of Plymouth, 
CT, about 3.4 miles above its confluence with Naugatuck 
River. (See Geological Survey map for Waterbury, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant structures was initiated in July 1963 
and completed in August 1966. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $90,163. 
36C. HOP BROOK LAKE, CT 
Location. Damsite is on Hop Brook in city of Waterbury 
and towns of Middlebury and Naugatuck, CT, about 
1.4 miles upstream of confluence of Naugatuck River and 
Hop Brook. (See Geological Survey map for Waterbury, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant structures was initiated in December 
1965 and completed in December 1968. Construction of 
a public use facility was completed in November 1973. 
Construction of an additional restroom was completed 
in 1980. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The Hop Brook shelter was 
completed in August 1989 at a cost of $11,420. 
36D. NORTHFIELD BROOK LAKE, CT 
Location. Dam is on Northfield Brook about 1.3 miles 
upstream from its confluence with Naugatuck River, in 
town of Thomaston, CT. (See Geological Survey map for 
Thomaston, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenances was initiated in May 1963 and completed 
in October 1965. Construction of recreation facilities 
was initiated in November 1966 and completed in 
August 1967. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $210,899. 
36E. THOMASTON DAM, CT 
Location. On Naugatuck River about 30.4 miles above 
its junction with Housatonic River and about 1.6 miles 
north of Thomaston, CT. Reservoir extends upstream 
about 6.4 miles. (See Geological Survey map for Thomaston, 
CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1958 and 
completed in November 1960. 
Local cooperation. Section 3, Flood Control Act of 
1944 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $432,468. 
37. MERRIMACK RIVER BASIN, 
NH AND MA 
Works covered by comprehensive plan are on Merrimack 
River and its tributaries in New Hampshire and 
Massachusetts. Flood Control Act of 1936 authorized 
construction of a system of flood control reservoirs in 
Merrimack River Basin for reduction of flood heights in 
Merrimack Valley. Flood Control Act of 1938 approved 
general comprehensive plan for flood control and other 
purposes as approved by Chief of Engineers pursuant to 
preliminary examinations and surveys authorized by Act 
of June 22, 1936, and modified project to provide in addition 
to construction of a system of flood control reservoirs, 
related flood control works which may be found 
justified by the Chief of Engineers. All operations pertaining 
to flood control in Merrimack River Basin are 
now carried on under and reported under projects for 
individual units of comprehensive plan referred to above. 
No further expenditures are contemplated under general 
project for flood control in Merrimack River Basin. For 
1-18

NEW ENGLAND DIVISION 
final cost and financial summary, see Annual Report for 
1946. 
A comprehensive plan for development of water resources 
of the North Nashua River Basin, a principal 
tributary of the Merrimack River, was authorized by 
1966 Flood Control Act substantially in accordance with 
Senate Document 113, 89th Congress. Plan provides for 
construction of coordinated system of four reservoirs and 
three local protection projects for flood protection, water 
supply, recreation and allied purposes. Water Resources 
Development Act of 1986 deauthorized two of the reservoirs 
and one of the local protection projects. 
The 1966 Flood Control Act also authorized construction 
of Saxonville local protection project substantially 
in accordance with Senate Document 61, 89th Congress. 
An emergency bank protection project at Amesbury, MA 
was authorized under authority provided by Section 14 
of the 1948 Flood Control Act. (See Table 1-N at the end 
of chapter for reservoirs and related flood control works 
for Merrimack River Basin). 
37A. BLACKWATER DAM, NH 
Location. Dam is on Blackwater River, NH, 8.2 miles 
above confluence with Contoocook River and 118.8 miles 
above mouth of Merrimack River. It is in the town of 
Webster, just above village of Swetts Mills, 18 miles by 
highway northwest of Concord, NH. (See Geological Survey 
maps for Penacook and Mount Kearsarge, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete except for construction 
of public facilities. Construction of dam and appurtenant 
works was initiated in May 1940 and completed in November 
1941. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final payment 
on a contract to replace the emergency generators 
at three damsites, completed last fiscal year, is still pending. 
To date the contractor has received $61,663 of which 
$21,863 is for Blackwater Dam portion. 
37B. EDWARD MACDOWELL LAKE, NH 
Location. Dam is on Nubanusit Brook, a tributary of 
Contoocook River, one-half mile upstream from village 
of West Peterborough, NH, and 14 miles east of Keene, 
NH. (See Geological Survey map for Peterboro and Manadnock, 
NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in March 1948 and 
completed in March 1950. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
for drainage improvements was awarded in October 1988. 
The contract was 98 percent complete at fiscal year end 
with earnings of $22,269. 
37C. FRANKLIN FALLS DAM, NH 
Location. Dam is on Pemigewasset River, NH, main 
tributary of Merrimack River, and about 2.5 miles upstream 
of Franklin, NH. (See Geological Survey maps 
for Penacook and Holderness, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in November 1939 
and completed in October 1943. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to replace the gate hoist cable was awarded in June 1989 
and completed in August 1989. Total contract amount 
was $24,990. A contract to replace the emergency generator 
was awarded in July 1989. Work had not started 
at close of fiscal year. 
37D. HOPKINTON-EVERETT LAKES, 
NH 
Location. Hopkinton Dam is on Contoocook River, 
NH, 17.3 miles above its junction with Merrimack River 
and about one-half mile upstream from village of West 
Hopkinton. Everett Dam is on Piscataquog River, NH, 
16 miles above its junction with Merrimack River and 
about 1.3 miles southeast of village of East Weare. Two 
interconnecting canals were provided to enable the two 
reservoir areas to function as one. (See Geological Survey 
map for Hillsboro, NH, and Concord, NH). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of two 
dams and appurtenant works was initiated in November 
1959 and completed in December 1962. Construction of 
recreation facilities was initiated in November 1974 and 
completed in September 1975. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. Local interests must also bear 50 percent 
of future recreational development in accordance with 
1965 Federal Water Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final payment 
on a contract to replace the emergency generators 
at three damsites, completed last fiscal year, is still pending. 
To date the contractor has received $61,663 of which 
$47,800 is for Hopkinton-Everett portion. Final payment 
on a contract for restroom renovations, completed last 
fiscal year, was $24,409. The contract to replace fuel 
tanks and furnaces awarded in June 1988 was completed 
in December 1988. Final contract amount was $28,905. 
A contract to install picnic shelters at various recreation 
parks was awarded in November 1988. The contract was 
54 percent complete at fiscal year end with total earnings 
1-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
of $68,294. Work on the Hopkinton-Everett shelters was 
not completed at close of fiscal year. 
38. NEW BEDFORD FAIRHAVEN, 
AND ACUSHNET, MA 
Location. Main harbor barrier is across New Bedford 
and Fairhaven Harbor in vicinity of Palmer Island. Supplemental 
dikes and walls are provided in Clark Cove 
area of New Bedford and Fairhaven. (See Geological survey 
maps for New Bedford North, New Bedford South, 
Marion, and Sconticut Neck, MA and National Ocean 
Survey Charts 13230, 13070 and 13218). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of barrier 
and appurtenances was initiated in October 1962 and 
completed in January 1966. Construction of the pumping 
station was initiated in October 1962 and completed in 
June 1964. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Operating 
costs included $14,751 for replacement of gate 
stem on conduit number 2; $126,478 for project operations 
and $32,192 for administrative activities. 
39. NEW LONDON, CT 
Location. In the city of New London, CT, about 45 
miles southeast of Hartford, CT, and 50 miles southwest 
of Providence, RI. (See Geological Survey map for New 
London, CT). 
Existing project. The hurricane protection project 
consists of approximately 715 feet of rock-faced earthfill 
dike and 800 feet of I-walls around the northerly shore 
of Shaw Cove and the regrading of approximately 21 
acres of land along the west shore of the cove to elevation 
12.5 feet mean sea level. Top of dike and floodwalls are 
14.5 feet mean sea level. Appurtenant structures include 
a street gate, pressure conduit and a pumping station to 
discharge interior drainage. Latest estimate (December 
1984) for the project is $11,560,000 for construction and 
$1,140,000 for lands and damages including relocations, 
a total of $12,700,000 for new work. Total includes local 
costs of $1,140,000 for lands and relocations and a 
$2,310,000 cash contribution. (See Table 1-B at end of 
chapter for Act authorizing existing project). Project construction 
is complete. 
Local cooperation. Local interests must: (a) Provide 
lands and rights-of-way for construction; (b) make alterations 
and relocations; (c) bear 30 percent of construction 
cost with credit allowed for (a) and (b); (d) hold the 
United States free from damages; and (e) maintain and 
operate all works. Assurances have been provided. 
Operations during fiscal year. New work: The City 
of New London finally completed its appraisal of project 
lands and submitted paperwork to the Corps for review 
and approval. New England Division completed its review, 
and the appraisal documents and figures are currently 
under review for approval at Corps headquarters. 
Final cost-sharing determination and project fiscal closeout 
are dependent upon the approved value of lands. 
40. BROCKTON, MA 
Location. Brockton is located in Plymouth County, 
18 miles south of Boston and 25 miles northwest of Providence, 
Rhode Island. 
Existing Project. The authorization provides for 
planning, engineering and design of flood control works 
for the protection of Brockton, particularly along Salisbury 
Brook, as well as improvements to ponds and a 
reservoir located in the uppermost part of the watershed. 
Proposed flood control measures included floodwalls and 
dikes, new bridges and culverts, utility relocations, stream 
diversions, and floodproofing. 
Local cooperation. Formal assurances have not been 
requested. Local interests would be required to contribute 
50 percent of planning and engineering costs and 25 
percent of construction cost including design of any measures 
that were subsequently authorized. 
Operations during fiscal year. New work: Draft report 
was finalized, however very low benefit to cost ratios 
computed for all of the plans prompted a recommendation 
that the project be reclassified from the active to 
the inactive category. Upon subsequent OCE approval 
of that recommendation the local and Congressional interests 
were informed of the change in the project's status. 
A probable snagging and clearing project under the 
authority of Section 208 of the 1954 Flood Control Act, 
as amended, was identified and studies under that authority 
were initiated. 
41. LITTLE RIVER, BELFAST, ME 
Location. The town of Belfast, Maine, is located approximately 
20 miles south of Bangor, Maine and lies 
on Maine's southern shoreline on Belfast Bay. 
Existing project. The plan to resolve the streambank 
erosion problem downstream of the southern abutment 
of the Little River Lower Dam would consist of approximately 
80 linear feet of precast concrete modular wall. 
This wall would vary in height from 10 to 20 feet and 
vary in depth from 4 to 8 feet. A 10-foot long cast-inplace 
concrete wall about 7 feet high will tie the modular 
wall into the downstream bank. 
Local cooperation. Provide without cost to the United 
States, all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation and maintenance of the project, 
except where such damages are due to the fault or negligence 
of the United States or its contractors; maintain 
and operate the project after completion without cost to 
the United States; contribute 25 percent of actual cost 
of construction and preparation of plans and specifications, 
(a minimum cash contribution of 5 percent of these 
costs is required); assume the responsibility for all costs 
in excess of the Federal cost limitation of $500,000; prevent 
future encroachment which might interfere with 
proper functioning of the project. 
1-20

NEW ENGLAND DIVISION 
Operations during fiscal year. New work: A contract 
for emergency streambank protection, awarded last 
fiscal year, was completed in December 1988. Contract 
payments to date were $127,029 with final quantities 
still pending at close of fiscal year. 
42. PERLEY BROOK, FORT KENT, ME 
Location. Fort Kent, Maine, is located in northern 
Aroostook County, about 50 miles northwest of Presque 
Isle, Maine, and adjacent to the United States-Canada 
border. Perley Brook is a tributary of the Fish River. 
Existing project. The project includes stone revetment 
along 100 linear feet of 6- to 10-foot high embankment 
adjacent to Route 161, the excavation of 4 river 
shoal areas, and placing gabions around the existing 
highway culverts. 
Local cooperation. Provide without cost to the United 
States, all lands, easements, rights-of-way, and utility 
relocations necessary for project construction; hold and 
save the United States free from damages due to the 
construction, operation and maintenance of the project, 
except where such damages are due to the fault or negligence 
of the United States or its contractors; maintain 
and operate the project after completion without cost to 
the United States; contribute 25 percent of actual cost 
of construction and preparation of plans and specifications, 
(a minimum cash contribution of 5 percent of these 
costs is required); assume the responsibility for all costs 
in excess of the Federal cost limitation of $500,000; prevent 
future encroachment which might interfere with 
proper functioning of the project. 
Operations during fiscal year. New work: An emergency 
streambank protection contract was awarded in 
December 1988 and completed in August 1989. Contract 
payments this fiscal year were $51,634. Final payment 
was still pending at close of fiscal year. 
43. ROUGHANS POINT, REVERE, MA 
Location. The city of Revere is located in Suffolk 
County on the Massachusetts coast about 2 miles northeast 
of the East Boston section of the city of Boston. 
Roughans Point is a low-lying, ocean front area of Revere. 
The area has 55 acres which lie below elevation 
10 feet NGVD. 
Existing project. Consists of stabilizing the existing 
facilities along the shore with a 4,080-foot long armor 
stone revetment to dissipate incoming waves. The revetment 
would extend from a point 400 feet north of Eliot 
Circle southerly to a point 200 feet south of the intersection 
of Winthrop Parkway and Leverett Avenue. The 
plan also calls for "backwater" protection by constructing 
an earth berm one foot high and 200 feet long on 
the existing median strip between Bennington Street 
and State Road. Interior drainage improvements consist 
of a new intake structure at the existing pump station, 
a new gravity drain and two sluice gates. The total estimated 
project cost (March 1989) is $11,000,000. (See 
Table 1-B at end of chapter for Act authorizing existing 
project). 
Local cooperation. Formal assurances have not been 
requested. Local interests must provide without cost to 
the United States, all lands, easements, and rights-ofway 
necessary for construction of the structural elements 
of the project, including ponding areas, borrow 
areas, and disposal areas for excavated material, presently 
estimated at $1,080,000; hold and save the United 
States free from damages due to construction, operation 
and maintenance of the project, not including damages 
due to the fault or negligence of the United States or its 
contractors; bear all costs of operation, maintenance and 
replacements, presently estimated at $13,000 annually; 
pay an amount in cash, presently estimated at $2,770,000, 
to bring the total non-Federal share to 35 percent of 
project costs allocated to storm damage reduction; provide 
and maintain necessary access roads; accomplish 
without cost to the United States all alterations and 
relocations of buildings, streets, storm drains, utilities, 
highway bridges, and other structures made necessary 
by construction of the project. 
Operations during fiscal year. New work: Preconstruction 
engineering and design continued with project 
layout, development of cross sections, and analysis of 
impacts to existing floodwall. 
44. STAMFORD, CT 
Location. In Fairfield County on north shore of Long 
Island Sound, about 30 miles east of New York City and 
20 miles southwest of Bridgeport, CT. (See Geological 
Survey map for Stamford, CT). 
Existing project. For description of completed improvement 
see Annual Report for 1974. (See Table 1-B 
at end of chapter for Act authorizing existing project). 
Project was completed in 1969. Local interests still owe 
a substantial amount based on claims settlements, including 
interest payment under the Contract Disputes 
Act. 
Local cooperation. Local interests will provide lands, 
easements, and rights-of-way; make modifications to existing 
storm drainage system which may be required to 
obtain full benefits of protection plan, all necessary modifications 
to existing sanitary sewer facilities required 
to prevent entry of tidal-waters, and all changes, alterations 
and additions to or relocations of any buildings 
and utilities made necessary by construction of project; 
bear 30 percent of total first cost, estimated at $4,340,000 
and consisting of cost items listed above plus a cash 
contribution estimated at $3,150,000; contribute in cash, 
in lieu of cost of annual maintenance and operation of 
tidal portion of East Branch barrier which is to be operated 
and maintained by the United States, an amount 
estimated at $880,000; maintain and operate all works 
after completion with exception of tidal portion of East 
Branch barrier and aids to navigation; and hold the United 
States free from damages. Assurances received and cash 
contributions have been deposited except for $662,000 
outstanding which is local share of final claims settlement 
including interest payment. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $209,717. 
1-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
45. THAMES RIVER BASIN, CT, RI, 
AND MA 
Works covered by this plan are a series of dams and 
reservoirs on tributaries of Thames River in Massachusetts 
and Connecticut, within a radius of 45 miles from 
Norwich, CT, and a channel enlargement on Shetucket 
River where it discharges into Thames River at Norwich. 
Flood Control Act of August 18, 1941, approved plan for 
a system of reservoirs and channel improvements in 
Thames River Basin in accordance with House Document 
885, 76th Congress, 3rd session, and authorized $6 
million for initiation and partial accomplishment of project. 
Flood Control Act of December 22, 1944, authorized 
completion of approved plan. Flood Control Act of July 
14, 1960, authorized project for West Thompson Reservoir, 
substantially as recommended in Senate Document 
41, 86th Congress, 2nd session. (See Table 1-0 at end of 
chapter on reservoirs and local protection districts, 
Thames River Basin, for projects comprising approved 
plan). 
45A. BUFFUMVILLE LAKE, MA 
Location. Dam is on Little River, 1.3 miles above its 
junction with French River and 8 miles northeast of 
Southbridge, MA. Reservoir extends upstream about 1.7 
miles northerly and 1.9 miles southerly. (See Geological 
Survey maps for Webster, MA and CT, and Leicester, 
MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in September 1956 
and completed in June 1958. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $214,535. 
45B. EAST BRIMFIELD LAKE, MA 
Location. Dam is on Quinebaug River, 64.5 miles above 
its confluence with Shetucket River and 1 mile southwest 
of village of Fiskdale, MA. (See Geological Survey 
maps for Whales, MA and CT, Southbridge, MA and CT, 
East Brookfield, MA, and Warren, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1958 and 
completed in June 1960. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $355,006. 
45C. HODGES VILLAGE DAM, MA 
Location. Dam is on French River, 15 miles above its 
confluence with Quinebaug River, at Hodges Village in 
town of Oxford, MA, about 5 miles north of Webster, 
MA. (See Geological Survey maps for Webster, MA, and 
CT, Leicester, MA, Worcester South, MA, and Oxford, 
MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works, initiated in March 1958, was 
completed in December 1959. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final payment 
on the contract for pavement repairs, completed 
last fiscal year, was made in November 1988. The final 
contract amount was $41,272. 
45D. MANSFIELD HOLLOW LAKE, CT 
Location. Dam is at Mansfield Hollow, CT, on Natchaug 
River, 5.3 miles above its confluence with Willimantic 
River. It is 4 miles northeast of city of Willimantic, 
CT. (See Geological Survey maps for Spring Hill 
and Willimantic, CT). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, 
initiated in 1949, was completed in May 1952. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $331,485. 
45E. WEST THOMPSON LAKE, CT 
Location. Dam is on Quinebaug River in town of 
Thompson, CT. Site is in village of West Thompson, 2 
miles upstream from city of Putnam, CT. (See Geological 
Survey map, for Putnam, CT). 
Existing Project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, 
road relocation, and appurtenances was initiated in August 
1963 and completed in October 1965. Initial phase 
of recreation facilities was completed in May 1976. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final payment 
of a contract to paint the spillway and service bridges, 
completed last fiscal year, was processed. Total contract 
amount was $24,995. A contract to install picnic shelters 
at various recreation parks was awarded in November 
1988. The West Thompson shelter was completed in August 
1989 at a cost of $11,420. 
45F. WESTVILLE LAKE, MA 
Location. Dam is on Quinebaug River, 56.7 miles above 
its confluence with Shetucket River, in towns of Stur- 
1-22

NEW ENGLAND DIVISION 
bridge and Southbridge, MA, and 1.3 miles west of center 
of Southbridge. (See Geological Survey maps for Southbridge, 
MA and RI, and East Brookfield, MA). 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in April 1960 and 
completed in August 1962. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to install picnic shelters at various recreation parks was 
awarded in November 1988. The Westville shelter was 
completed in July 1989 at a cost of $11,306. 
46. TOWN BROOK, QUINCY 
AND BRAINTREE, MA 
Location. The project is located in the city of Quincy 
and the town of Braintree on the south side of Massachusetts 
Bay, along the eastern shore of Massachusetts, 
7 miles south of Boston in Norfolk County. The watershed 
is approximately 4.5 square miles. 
Existing project. Provides for the construction of a 
12-foot diameter, 4,060-foot long, concrete lined tunnel 
in bedrock approximately 190 feet below ground, intake 
and outlet structures, and improvements to the Town 
River downstream of the outlet shaft. New reinforced 
concrete box outlets will be constructed under the Southern 
Artery and an adjacent automobile dealer parking 
lot. In conjunction with this, the left bank of the Town 
River below the Southern Artery will be widened to provide 
sufficient channel capacity. The tunnel and its appurtenances 
will be supplemented by reconstruction of 
the Old Quincy Reservoir Dam, located at the headwaters 
of Town Brook, including a new spillway and outlet 
structure. The estimated total project cost (October 1988) 
is $36,700,000, exclusive of the reconstruction cost which 
is a non-Federal responsibility, and includes $6,100,000 
in approved-for-credit compatible work that has been 
accomplished by the project sponsor. (See Table 1-B at 
end of chapter for Act authorizing existing project). 
Local cooperation. Formal assurances have not been 
requested. Local interests are required to provide all 
lands, easements, and rights-of-way, presently estimated 
at $260,000; reconstruct Old Quincy Dam to insure 
its structural integrity, presently estimated at 
$3,360,000; pay a cash contribution for the costs allocated 
to flood control, presently estimated at $2,815,000; 
so that the total contribution of local interests is equal 
to 25 percent of costs allocated to flood control; and bear 
all costs of operation, maintenance, and replacements, 
presently estimated at $23,000 annually. In addition, 
local interests must do the following, for which there is 
no estimate of cost: prescribe and enforce regulations to 
prevent encroachment on both the improvements and 
unimproved channels, and manage all project-related 
channels to preserve capacities for local drainage as well 
as for project functions. 
Operations during fiscal year. New work: Preconstruction 
engineering and design continued, including 
preparation of plans and specifications for the tunnel and 
inlet/outlet structures as well as for the reconstruction 
of the Old Quincy Dam. Extensive coordination work 
with the project sponsor (the Metropolitan District Commission) 
and the Commonwealth of Massachusetts resulted 
in the obtaining of the required wetlands permit 
and water quality certificate this fiscal year-both prerequisites 
to execution of the Local Cooperation Agreement 
(LCA) and initiation of construction. Initial construction 
funds have been appropriated, but the LCA 
has not yet been signed. 
47. WEST RIVER, NEW HAVEN, CT 
Location. New Haven, Connecticut is located in 
southern New Haven County, about 35 miles south of 
Hartford, Connecticut. The project area is located upstream 
of the intersection of Route 63 and West River 
in northwestern New Haven. 
Existing project. The West River will be widened for 
1,150 feet from its existing 25- to 30-foot width to a 50- 
to 70-foot width; a 1,150-foot modular wall will be built 
along the right bank and a 600-foot cantilever sheet pile 
wall will be built along the left bank. For Wintergreen 
Brook the channel will have a 20- to 30-foot width, and 
a 550-foot sheet pile wall and 450-foot dike on the right 
bank. A recreational walkway on top of the modular wall 
with lighting and fencing to connect two existing city 
parks is also included. The estimated total project cost 
(April 1988) is $6,100,000. 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on January 17, 1989 between the Corps 
and the Connecticut Department of Environmental Protection 
(DEP) for the project. Local interests are required 
to provide all lands, easements, rights-of-way and relocations, 
presently estimated at $1,700,000; pay a cash 
contribution for the costs allocated to flood control, presently 
estimated at 5 percent or $291,000 so that the total 
contribution of local interests is equal to 25 percent of 
costs allocated to flood control; pay 50 percent of the costs 
allocated to recreation, presently estimated to be $140,000; 
assume full responsibility for all project costs in excess 
of the Federal statutory limitation of $5,000,000; bear 
all costs of operation and maintenance, presently estimated 
at $7,000 annually. In addition, local interests 
must do the following, for which there is no estimate of 
cost: participate in and comply with applicable Federal 
flood plain management and flood insurance programs; 
prescribe and enforce regulations to prevent encroachment 
on the project which would reduce level of protection 
afforded; notify, not less than once a year, affected 
interests of the limitations of the protection afforded by 
the project. 
Operations during fiscal year. New work: State DEP/ 
city of New Haven have been pursuing necessary real 
estate acquisition involving 15 parcels and relocations 
required before project can be issued for bids. 
48. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
In accordance with provisions of the Flood Control Act 
of 1936, as amended, local flood protection works con- 
1-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
structed with Federal funds are transferred to local interests 
to operate and maintain. To insure compliance 
with regulations prescribed for their operation and 
maintenance, regular inspections of the following projects 
were made during the fiscal year: 
CONNECTICUT: April 1989-Bridgeport, Colchester, 
East Branch, Hall Meadow, Mad River, Milford, North 
Canaan, Salisbury, Sucker Brook, Torrington, Waterbury, 
Winsted, Woodbury; May 1989-Ansonia, Danbury, 
Derby, East Hartford, Hartford, New Fairfield, New 
London, Norwalk, Pawcatuck, Stamford, Wethersfield. 
MAINE: May 1989-Beals, Blaine, Castine, Cherryfield, 
Fort Kent, Gouldsboro, Harpswell, Hartland, Indian 
Island, Islesboro, Lubec, Machias, Ogunquit, Perry, 
Whiting. 
MASSACHUSETTS: April 1989-Alford, Canton, 
Conway, Gardner, Haverhill, Huntington, Lancaster, Lee, 
Lowell, Pittsfield, Scituate, Sheffield, Springfield, Three 
Rivers, Ware, West Warren, Westfield, Worcester; May 
1989-Amesbury, Blackstone, Charles River Dam, Chicopee, 
Chicopee Falls, Fitchburg, Hayward Creek, Holyoke, 
Millbury, Northampton, Quincy, Riverdale, Saxonville, 
Sheffield, Smelt Brook, West Springfield. 
NEW HAMPSHIRE: April 1989-Lincoln, Shelburne, 
Wilton; May 1989-Charlestown, Farmington, 
Nashua, North Stratford, West Stewartstown. 
RHODE ISLAND: April 1989-Burrillville; May 
1989-Woonsocket; August 1989-Lower Woonsocket. 
VERMONT: April 1989-Brownsville, Weston; May 
1989-Saxtons River. 
49. FLOOD CONTROL RESERVOIR 
OPERATIONS 
A coordinated system of reservoirs, many of which are 
multipurpose in nature and all containing significant 
amounts of storage for flood control purposes, has been 
established in five major flood producing basins in New 
England. During periods of flood flows, regulation of reservoirs 
is fully coordinated within each basin dependent 
upon its location in the watershed, its available storage 
capacity and origin of the flood. In addition to flood control 
releases, water supply, flow augmentation and hydropower 
releases were made from selected reservoirs. 
Winter pools are maintained at many projects to submerge 
the flood control gates and keep them from freezing. 
There were no significant storm events in New England 
during fiscal year. As a result there was no substantial 
flood control storage at any Corps reservoirs in 
New England and no flood control benefits associated 
with regulation of the reservoirs. 
CONNECTICUT RIVER BASIN 
Regulation for canoe activities occurred at Ball Mountain-
October 1988, April 1989, and May 1989; Birch 
Hill, Tully, Knightville, Littleville, and Otter Brook- 
April 1989; and Surry Mountain-May 1989. 
Non-flood releases were made from Colebrook Lake 
for low flow augmentation in July and September 1989 
and for water supply throughout the year. Non-flood releases 
from North Hartland Lake have been controlled 
by the Vermont Electric Generation and Transmission 
Cooperative for hydropower throughout fiscal year 1989. 
MERRIMACK RIVER BASIN 
Blackwater was regulated for canoe races in April 1989. 
THAMES RIVER BASIN 
Regulation activities in the basin included regulation for 
canoeing at Mansfield Hollow in June 1989, East Brimfield 
in April 1989, and Hodges Village in May 1989. Also 
the permanent pool at West Thompson was raised on several 
occasions during fiscal year 1989 to accommodate AKC 
retriever trials and powerboat competitions. 
50. HURRICANE BARRIER 
OPERATIONS 
Five hurricane barriers are situated along the southern 
coast of New England, protecting coastal communities 
from tidal flooding associated with hurricanes and 
severe coastal storms. The Corps operates the navigational 
elements of the Stamford, Connecticut and the 
New Bedford-Fairhaven, Massachusetts barriers. The Fox 
Point, Rhode Island and the Pawcatuck and New London, 
Connecticut barriers are operated by the local communities. 
A brief resume of operations for the fiscal year 
follows: 
STAMFORD BARRIER. The barrier gates were operated 
on seven different occasions for coastal storms 
during fiscal year 1989. Benefits associated with the operation 
of the Stamford Barrier totalled $250,000 for FY 
1989. 
NEW BEDFORD BARRIER. The New Bedford Barrier 
was operated on four different occasions during fiscal 
year 1989; however none of the closures resulted in damages 
prevented. 
FOX POINT HURRICANE BARRIER. The Fox 
Point Hurricane Barrier was not operated during fiscal 
year 1989 and did not experience damaging tidal flood 
conditions. 
PAWCATUCK HURRICANE BARRIER. The 
Pawcatuck Hurricane Barrier was not operated during 
fiscal year 1989 and did not experience damaging tidal 
flood conditions. 
NEW LONDON HURRICANE BARRIER. The New 
London Hurricane Barrier was not operated during fiscal 
year 1989 and did not experience damaging tidal flood 
conditions. 
51. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 1-E at end of chapter). 
52. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205. Public 
Law 858, 80th Congress, as amended (preauthorization). 
(See Table 1-J at end of chapter). 
1-24

NEW ENGLAND DIVISION 
Snagging and clearing activities pursuant to Section 
208 of the 1954 Flood Control Act. 
Fiscal year costs were as follows: 
Blackberry River, North Canaan, CT ........ $3,426 
Salisbury Brook, Brockton, MA ............. 31,974 
Emergency Bank Protection activities pursuant to Section 
14 of the 1946 Flood Control Act. 
Fiscal year costs were as follows: 
Belfast, M E ............................... $93,388 
(See Section 41 of Text) 
Blackstone River, Millbury, MA............. 1,349 
Chelsea Creek, East Boston, MA ............ 25,578 
Clear River, Burrillville, RI................. 731 
Connecticut River, Guildhall, VT............ 7,267 
Connecticut River, Whately, MA ............ 2,454 
Covered Bridge, Sheffield, MA .............. 1,752 
Farmington River, Barkhamsted, CT ........ 5,904 
Farmington River, Simsbury, CT ............ 23,646 
(See Section 35G of Text) 
Housatonic River, Sheffield, MA ............ 384 
Housatonic River, Shelton, CT .............. 8,354 
Kennebec River, Bingham, ME ............. .4,532 
Konkapot River, Monterey, MA ............. 6,767 
Machias River, Machias, ME ................ 595 
Machias River, Machiasport, ME ............ 1,956 
Marginal Way, Ogunquit, ME .............. 348 
Merrimack River, Merrimac, MA............ 7,500 
Mill Brook, Brownsville, VT ................ 2,003 
Nashua River, Leominster, MA ............. 28,838 
Neponset River, Canton, MA ................ 7,500 
North Nashua River, Fitchburg, MA ........ 6,421 
Ocean Grove Beach, Swansea, MA .......... 9,566 
Perley Brook, Fort Kent, ME .............. 47,116 
(See Section 42 of Text) 
Pleasant Point, Perry, ME .................. 895 
South River, Conway, MA .................. 1,664 
Surf Street, Saco, ME ...................... 137 
Town River Bay, Quincy, MA ............... 17,865 
Emergency flood control activities-repair,f lood fighting, 
and rescue work (Public Law 99, 84th Cong., and 
antecedent legislation). 
Federal costs for fiscal year were $160,348 for disaster 
preparedness. 
53. DEAUTHORIZED PROJECTS 
(See Table 1-G at end of chapter). 
General Investigations 
54. SURVEYS 
Costs for the fiscal year for surveys from regular funds 
were $2,653,914 of which $16,337 was for one navigation 
study; $1,345,970 for seven flood damage prevention 
studies; $279,247 for one shore protection study; $601,498 
for three comprehensive studies; and $410,862 for coordination 
studies. 
55. COLLECTION AND STUDY OF 
BASIC DATA 
The Division Engineer is the U.S. member on Saint 
Croix River Board of Control. Annual inspections are 
made of conditions on the Saint Croix River and a continuing 
program of compilation of basic hydrologic information 
is carried out. Division Engineer's representatives 
during the past year kept closely in touch with 
development in the basin and cooperated with their Canadian 
counterparts assisting in development of basins' 
resources. Total costs for the fiscal year were $14,663. 
Total costs to 30 September 1989 are $224,185 
Flood plain studies comprise compilation and dissemination, 
upon responsible local request, of information 
on floods and potential flood damages, including identification 
of areas subject to inundation by floods of various 
magnitudes and frequencies, and general criteria 
for guidance in use of flood plain area; and engineering 
advice to local interests for their use in planning to ameliorate 
flood hazard. Total costs for the fiscal year were 
$479,061. Total costs to 30 September 1989 are $6,016,330. 
56. PLANNING, ENGINEERING AND 
DESIGN 
Total costs for Planning, Engineering and Design were 
$15,279 for local protection studies for Brockton, Massachusetts. 
57. PRECONSTRUCTION 
ENGINEERING AND DESIGN 
Preconstruction Engineering and Design costs were 
- $1,902 for the navigation project at New Haven Harbor, 
Connecticut and $116,622 for the local protection 
project at Massachusetts Coastal, Roughans Point, Revere, 
Massachusetts. 
1-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
1. Aquatic Plant 
Control 
2. Branford Harbor, 
CT 
3. Cape Cod Canal, 
MA 
(Contributed 
Funds) 
4. Chatham (Stage) 
Harbor, MA 
(Contributed 
Funds) 
5. Great Salt Pond, 
Block Island, RI 
6. Green Harbor, 
MA 
(Contributed 
Funds) 
7. Harbor of Refuge, 
Block Island, RI 
8. Hyannis Harbor, 
MA 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Minor rehab. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
30,000 
31,931 
12,003 
12,003 
12,000 
8,770 
25,920 
25,920 
12,000 12,000 281,496 
14,169 9,454 275,046 
- - 9,537 
- - 9,537 
40,481 88,571 1,142,320 
39,481 83,722 1,136,471 
- - - 32,786,2191,2 
- - - - 32,786,2191,2 
6,093,171 5,850,021 4,363,013 5,338,954 102,248,572 
6,101,729 5,709,255 4,289,169 5,646,961 102,072,159 
- - - - 115,432 
- - - - 115,432 
- - - - 390,677 
- - - 390,677 
- - - - 26,609,000 
- - - - 26,609,000 
- - - - 266,70541 
- - - - 266,70541 
19,880 692,982 
19,880 692,995 
T -T 
20,482 - 
20,482 - 
- - 
58,116 310,696 
44,232 268,600 
9,658 - 
14,664 
14,664 
15,184 
16,473 
192,442 
192,442 
2,000 
6,490 
X8,043 70,392 2,711,39042 
27,436 70,326 2,710,71742 
- - 43,500 
- - 43,500 
- - 189,0376 
- - 189,0376 
10,000 18,085 578,321 
10,000 17,934 578,169 
- - 254,512 
- - 254,512 
55,764 24,947 2,156,706 
122,179 25,356 2,156,514 
- - 168,000 
- - 168,000 
- - 576,856 
- - 576,856 
1,000 167,854 1,777,116 
884 144,297 1,679,578 
- - 484,499 
- - 484,499 
- - 643,1957 
-188 11,347 642,4927 
- - 103,001 
- - 103,001 
1-26

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
9. Jonesport Harbor, 
ME 
(Contributed 
Funds-Required) 
10. Milford Harbor, CT 
(Contributed 
Funds) 
(Contributed 
Funds-Other) 
11. Nantucket (Harbor 
of Refuge), MA 
12. New Haven 
Harbor, CT 
13. Plymouth Harbor, 
MA 
(Contributed 
Funds-Required) 
14. Point Judith Pond 
and Harbor of 
Refuge, RI 
(Contributed 
Funds) 
15. Portsmouth Harbor and 
Piscataqua River, 
ME and NH 
(Contributed 
Funds-Required) 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
205,000 2 
261,017 
57,390 
57,390 
547 
547 
22,564 
25,795 
426,000 
425,264 
13,349 
2,800 
2,800 
1-27 
,860,000 3,830,000 550,000 7,750,000 
38,658 6,481,959 478,037 7,499,833 
80,000 720,000 33,000 833,000 
- 763,675 50,560 814,235 
- - - 90,50644 
- - - 90,50644 
35,275 597,049 11,599 1,323,68246 
35,274 596,536 12,113 1,323,68246 
- - - 11,380 
- - - 11,380 
200,000 -26,575 - 173,425 
- 173,425 - 173,425 
- - - 502,66147 
- - - 502,66147 
14,099 18,858 256,143 733,706 
14,099 17,858 257,143 733,706 
- - - 211,649 
- - - 211,649 
600,000 51,000 -83,000 4,773,2468 
276,753 288,070 - 1,902 4,768,1678 
15,514 306,241 980,519 14,091,9989 
16,214 140,632 1,142,399 14,088,2199 
- - - 2,127,21812 
- - - 2,127,21812 
70,000 315,743 10,360 1,321,00446 
69,405 315,712 10,128 1,320,14646 
- - - 573,000 
- - - 541,611 
- - - 894,475 
- - - 894,475 
- - - 2,714,51011 
- - - 2,714,51011 
927,000 1,152,000 153,000 6,074,884 
920,741 1,161,963 152,249 6,073,338 
- - - 1,926,000 
- - - 1,926,000 
- - - 17,587 
- - - 17,587 
200,258 100,000 4,400,000 10,084,30110 
138,211 69,157 1,378,000 6,969,4110 
12,121 8,169 40,157 1,997,406 
12,121 8,169 39,957 1,997,206 
- - 1,000,000 1,099,707 
- - 400,000 499,707

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
16. Providence River and 
Harbor, RI 
17. Rockport Harbor, ME 
18. Rockport Harbor 
and Pigeon Cove, 
Rockport, MA 
(Contributed 
Funds-Required) 
19. Rye Harbor, NH 
(Contributed 
Funds-Required) 
(Contributed 
Funds-Other) 
20. Saco River, ME 
21. Sesuit Harbor, MA 
(Contributed 
Funds-Required) 
22. Wells Harbor, ME 
(Contributed 
Funds) 
23. Wood Island Harbor 
and Pool at 
Biddeford, ME 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
50,000 
47,420 
39,000 
44,819 
44,819 
78,829 
88,333 
19,817 
19,817 
1,] 
1,C
31,640 1 
31,596 1 
127,000 
058,356 
39,000 
52,077 
51,644 
31,856 
31,981 
- - 25,417,0224 
- - 25,417,0224 
- 252,000 4,082,5023 
- 232,283 4,062,7853 
- - 32,0005 
- - 32,0005 
58,654 5,855 250,669 
57,849 6,704 250,669 
45,000 180,000 1,787,000 
96,638 216,411 1,783,930 
- 12,430 51,430 
- 12,151 51,151 
41,225 40,969 
41,225 40,651 
130,342 
130,342 
262,724 
261,973 
- - 61,338 
- - 61,338 
- - 81,548 
- - 81,548 
- - 1,064,983 
- - 1,064,983 
17,666 81,007 1,775,500 
17,151 81,385 1,775,288 
- - 226,306 
- - 226,306 
9,704 222,502 
9,050 212,396 
60,326 
60,326 
58,270 
58,270 
-9,603 
1,158 
263,111 
263,111 
124,588 
124,588 
- - 360,973 
- - 360,973 
7,711 63,945 1,686,852 
7,209 63,945 1,686,316 
17,216 481,690 
16,827 481,344 
212,000 
212,000 
143,112 
143,112 
571,883 
571,148 
12,000 
12,000 
1-28

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
28. Revere Beach, MA New Work 
Approp. 
Cost 
(Contributed New Work 
Funds) Contrib. 
Cost 
29. Roosevelt Campobello New Work 
International Park, Approp. 
Lubec, ME Cost 
33A. West Hill Dam, New Work 
MA Approp. 
Cost 
Maint. 
Approp. 
Cost 
34. Charles River New Work 
(Natural Valley) Approp. 
Storage Areas), MA Cost 
Maint. 
Approp. 
Cost 
35A. Ball Mountain New Work 
Lake, VT Approp. 
Cost 
Maint. 
Approp. 
Cost 
35B. Barre Falls Dam, New Work 
MA Approp. 
Cost 
Maint. 
Approp. 
Cost 
35C. Beaver Brook, New Work 
Keene, NH Approp. 
Cost 
35D. Birch Hill Dam, MA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contributed New Work 
Funds) Contrib. 
Cost 
35E. Colebrook River New Work 
Lake, CT Approp. 
Cost 
Maint. 
Approp. 
Cost 
35F. Conant Brook New Work 
Dam, MA Approp. 
Cost 
Maint. 
Approp. 
Cost 
35G. Farmington River, New Work 
Simsbury, Ct Approp. 
Cost 
34,807 
125,000 150,000 50,000 
124,486 65,132 105,664 
44,200 200,000 - 
41,990 17,207 157,390 
808,71213 
778,89413 
142,965 
142,965 
244,200 
216,587 
- - - - 2,306,90214 
- - - - 2,306,90214 
264,000 360,200 441,500 639,400 4,165,334 
243,999 338,096 447,811 690,987 4,154,959 
191,000 - - - 8,606,000 
96,871 46,706 34,804 7,236 8,562,933 
198,000 236,100 122,300 124,300 956,700 
156,239 248,942 147,186 127,825 950,264 
- - - - 11,039,29815 
- - - - 11,039,29815 
606,000 337,200 311,200 418,700 6,544,839 
660,207 352,118 374,174 435,932 6,537,816 
- - - - 1,967,819 
- - - - 1,967,819 
405,000 436,400 316,300 451,400 4,890,727 
334,097 476,702 368,633 478,718 4,874,472 
1,775,000 240,000 45,000 15,000 2,586,000 
1,731,994 330,001 27,978 28,273 2,582,120 
- - - - 4,815,67916 
- - - - 4,815,67916 
217,000 363,500 481,400 476,400 5,089,027 
215,317 281,087 414,096 623,168 5,077,076 
- - - - 32,00017 
- - - - 32,00017 
- - - - 14,263,971 
- - - - 14,263,971 
190,000 308,100 
185,002 275,495 
126,000 112,500 
115,990 102,705 
- 40,000 
- 35,436 
310,000 130,800 2,748,344 
303,553 178,771 2,746,009 
- - 2,950,530 
- - 2,950,530 
98,700 105,900 1,397,780 
104,497 126,417 1,395,145 
- 40,000 80,000 
4,540 23,646 63,622 
1-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
35H. Knightville Dam, 
MA 
35I. Littleville Lake, 
MA 
35J. North Hartland 
Lake, VT 
35K. North Springfield 
Lake,VT 
35L. Otter Brook 
Lake, NH 
35M. Riverdale, West 
Springfield, MA 
(Contributed 
Funds) 
35N. Surry Mountain 
Lake, NH 
350. Townshend Lake, 
VT 
35P. Tully Lake, MA 
(Contributed 
Funds) 
35Q. Union Village 
Dam, VT 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 3,415,64018 
- 3,415,64018 
296,000 384,000 389,800 507,500 6,210,204 
301,828 319,196 415,920 522,977 6,177,192 
- - - - 7,013,412 
- - - - 7,013,412 
464,000 268,500 349,500 561,200 4,389,091 
290,889 426,542 325,743 574,335 4,356,024 
- - - - 7,312,22519 
- - - - 7,312,22519 
279,000 298,300 264,500 433,900 4,769,515 
264,351 323,690 259,848 381,073 4,690,367 
- - - - 6,831,52620 
- - - - 6,831,52620 
861,000 559,000 950,500 1,196,369 8,687,966 
972,541 504,542 837,834 1,314,280 8,625,876 
- - - - 4,360,44821 
- - - - 4,360,44821 
356,000 299,100 426,500 456,600 4,901,814 
448,103 299,796 315,702 583,497 4,898,335 
20,000 105,000 - 15,000 1,278,000 
7,125 109,734 8,035 826 1,263,720 
- - - - 25,000 
- - - - 25,000 
- - - - 2,833,61022 
- - - - 2,833,61022 
280,000 289,100 302,100 330,000 5,414,643 
294,216 282,718 309,004 351,551 5,412,861 
- - - - 7,398,41323 
- - - - 7,398,41323 
472,000 456,300 295,200 392,000 6,219,971 
541,835 469,469 314,617 402,749 6,188,681 
- - - - 1,666,75224 
- - - - 1,666,75224 
313,000 323,000 338,000 455,900 4,716,886 
310,633 397,130 340,252 452,772 4,690,470 
- - - - 40,00017 
- - - - 40,00017 
- - - - 4,095,16025 
- - - - 4,095,16025 
216,000 251,900 257,000 482,900 4,517,356 
243,036 245,621 250,154 474,338 4,487,403 
1-30

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
35R. West Springfield, 
MA 
(Contributed 
Funds) 
36A. Black Rock Lake, 
CT 
36B. Hancock Brook 
Lake, CT 
36C. Hop Brook Lake, 
CT 
36D. Northfield Brook 
Lake, CT 
36E. Thomaston Dam, 
CT 
37A. Blackwater Dam, 
NH 
37B. Edward MacDowell 
Lake, NH 
37C. Franklin Falls 
Dam, NH 
37D. Hopkinton-Everett 
Lakes, NH 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 1,793,72443 
37 649 5,522 21,368 1,789,14143 
- - - - 13,000 
- - - 12,390 12,390 
- - - - 8,182,300 
- - - - 8,182,300 
191,000 213,400 171,400 272,300 2,827,709 
172,852 203,952 184,866 285,311 2,824,751 
- - - - 4,178,911 
- - - - 4,178,911 
84,000 68,700 112,400 87,900 1,344,649 
80,751 62,798 116,469 90,163 1,341,757 
- - - - 6,151,56226 
- - - - 6,151,56226 
531,000 523,900 925,600 920,300 6,300,685 
499,564 542,357 855,669 1,029,440 6,250,283 
- - - - 2,850,51227 
- - - - 2,850,51227 
200,000 165,300 195,300 158,500 2,166,811 
202,038 173,108 152,753 210,899 2,161,421 
- - - - 14,282,112 
- - - - 14,282,112 
343,000 621,400 385,200 349,400 5,648,767 
533,544 352,751 586,787 432,468 5,644,564 
- - - - 1,319,74628 
- - - - 1,319,74628 
248,000 216,000 254,700 323,300 3,644,985 
213,093 239,615 251,657 336,978 3,643,394 
- - - - 2,014,25329 
- - - - 2,014,25329 
277,000 379,700 301,000 341,400 4,393,492 
254,523 349,964 359,584 350,042 4,390,239 
- - - - 7,950,48730 
- - - - 7,950,48730 
367,000 389,122 345,500 561,500 6,690,259 
438,508 361,738 386,402 556,450 6,683,473 
- - - - 21,452,44031 
- - - - 21,452,44031 
512,500 528,722 860,500 817,400 8,395,162 
502,046 568,737 774,061 962,420 8,385,672 
1-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
38. New Bedford, 
Fairhaven, and 
Acushnet, MA 
(Contributed 
Funds) 
39. New London, CT 
(Contributed 
Funds-Required) 
(Other 
Contributed 
Funds) 
40. Brockton, MA 
41. Little River, 
Belfast, ME 
(Contributed 
Funds-Required) 
42. Perley Brook, 
Fort Kent, ME 
(Contributed 
Funds-Required) 
43. Roughans Point, 
Revere, MA 
44. Stamford, CT 
(Contributed 
Funds-Required) 
(Other 
Contributed 
Funds) 
45A. Buffumville Lake, 
MA 
45B. East Brimfield 
Lake, MA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 11,510,088 
- - - - 11,510,088 
120,000 122,400 118,300 193,400 3,993,964 
115,033 119,269 120,493 173,421 3,965,716 
- - - - 6,513,76332 
- - - - 6,513,76332 
- - - - 9,272,046 
124,061 24,802 -76,348 4,726 9,196,370 
- - - - 2,255,00033 
54,932 - 21 1 - 2,251,29433 
6,500 - - - 222,250 
3,500 - - - 219,250 
- - 60,000 15,000 75,000 
- - 59,721 15,279 75,000 
- 20,000 132,000 15,000 167,000 
- 19,840 39,065 93,388 152,293 
- - 43,000 - 43,000 
- - - 43,000 43,000 
- 12,500 25,000 50,000 87,500 
- 11,945 24,418 47,116 83,479 
- - - 18,600 18,600 
- - - 18,599 18,599 
183,000 150,000 67,000 245,000 660,779 
74,673 106,972 53,023 116,622 351,290 
- - - - 9,911,300 
- 22 - - 9,900,640 
156,000 113,100 124,600 195,700 2,891,772 
185,598 117,216 110,349 209,717 2,887,929 
- - - - 3,367,97034 
- - - - 3,367,45334 
- - - - 210,000 
- - - - 209,969 
- - - - 2,998,60335 
- - - - 2,998,60335 
243,000 213,400 228,900 205,700 3,737,322 
256,020 202,934 238,894 214,535 3,735,385 
- - - - 7,057,04336 
- - - - 7,057,04336 
215,000 254,400 212,000 339,300 3,326,383 
211,889 225,428 237,777 355,006 3,325,154 
1-32

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
45C. Hodges Village New Work 
Dam, MA Approp. - - - - 4,461,26837 
Cost - - - - 4,461,26837 
Maint. 
Approp. 271,500 484,400 437,500 510,200 4,416,188 
Cost 295,212 383,725 548,646 496,116 4,388,375 
45D. Mansfield Hollow New Work 
Lake, CT Approp. - - - - 6,447,16438 
Cost - - - - 6,447,16438 
Maint. 
Approp. 178,000 335,400 268,300 309,500 4,003,997 
Cost 173,872 322,863 258,483 331,485 3,998,003 
45E. West Thompson New Work 
Lake, CT Approp. - - - - 7,001,22039 
Cost - - - - 7,001,22039 
Maint. 
Approp. 423,000 318,400 345,300 404,100 4,424,798 
Cost 423,571 322,774 329,781 425,327 4,411,677 
45F. Westville Lake, New Work 
MA Approp. - - - - 5,684,68340 
Cost - - - - 5,684,68340 
Maint. 
Approp. 382,000 409,900 325,300 257,100 4,061,396 
Cost 342,850 461,487 322,201 304,048 4,057,487 
46. Town Brook, Quincy New Work 
and Braintree, MA Approp. 250,000 350,000 250,000 550,000 1,420,740 
Cost 217,001 345,011 297,725 509,110 1,368,847 
47. West River, New New Work 
Haven, CT Approp. 100,000 195,000 75,000 25,000 595,000 
Cost 79,088 209,861 66,149 34,747 589,534 
1 Includes $6,138,157 from Public Works Funds and 28 Includes $2,881 Code 711 funds. 
$4,849,740 from Emergency Relief Funds. 29 Includes $6,432 Code 711 funds. 
2 Includes $389,929 Code 711 funds and $511,089 Code 30 Includes $4,671 Code 711 funds. 
713 funds. 31 Includes $179,727 Code 711 funds. 
SIncludes $650,136 for previous projects. 32 Cash for construction only. Excludes $164,020 
4 Includes $3,761,412 for previous projects. expended to date for land condemnation. 
6 Excludes $15,000 expended for previous project. 3 Excludes $22,517 expended to date for land 
6 Improvement adequate for commerce. condemnations. 
7 Excludes $129,757 expended for rehabilitation; 34 Cash for construction only. Excludes $199,410 
breakwater repaired in 1961. expended to date for land condemnations. 
8 Includes $331,626 for previous projects. Includes 6 Includes $71,943 Code 711 funds. 
$290,877 National Industrial Recovery Funds and $59,207 36 Includes $207,700 Code 711 funds. 
Public Works Funds. 37 Includes $6,255 Code 711 funds and $40,353 Code 
9 Includes $32,570 for previous projects. 713 funds. 
lo Includes $130,393 for previous projects. 38 Includes $68,717 Code 711 funds. 
11 Includes $12,000 for previous projects. 39 Includes $315,420 Code 711 funds. 
12 Includes $188,647 for previous projects. 40 Includes $67,667 Code 711 funds. 
13 Excludes $73,800 for previous project. 41 Includes $7,889 for previous project. 
14 Includes $18,310 Code 711 funds. 42 Includes $83,276 for maintenance of previous 
15 Includes $504,062 Code 711 funds. project. 
16 Includes $618,469 Code 711 funds and $32,000 Code 43 Includes $245,000 Public Works Funds. 
713 funds. 44 Includes $42,340 for previous project. 
17 Recreational cost sharing. 45 Includes $3,160 for previous project. 
is Includes $199,303 Code 711 funds. 46 Includes $2,013 for previous projects. In addition 
19 Includes $229,436 Code 711 funds. $400 was expended for maintenance from Contributed 
20 Includes $59,536 Code 711 funds. Funds. 
21 Includes $364,688 Code 711 funds. 47 Includes $45,835 for new work for previous project; 
22 Includes $470,077 Code 711 funds. excludes $211,649 expended for rehabilitation; jetty 
23 Includes $245,168 Code 711 funds. repaired in 1963. 
24 Includes $3,695 Code 711 funds and $115,138 Code 713 
funds. 
25 Includes $88,931 Code 711 funds. 
26 Includes $143,538 Code 711 funds. 
27 Includes $20,000 Code 711 funds. 
1-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
June 13, 1902 
March 2, 1907 
Jan. 21, 1927 
(Section 2) 
Included in Public 
Works Administration 
program, 
Sept. 6, 1933 
June 26, 1934 
(Permanent 
Appropriations 
Repeal Act) 
Included in Public 
Works 
Administration 
Program, Apr. 29, 
1935 
Included in 
Emergency Relief 
Program, May 28, 
1935 
Aug. 30, 1935 
Mar. 2, 1945 
July 3, 1958 
Mar. 2, 1945 
June 3, 1896 
June 13, 1902 
Mar. 2, 1945 
July 14, 1960, as 
amended 
July 11, 1870 
Aug. 2, 1882 
Aug. 5, 1886 
June 3, 1896 
AQUATIC PLANT CONTROL (See Section 1 of Text). 
Control and progressive eradication of obnoxious Aquatic Plant 
growths from the waters and streams in the U.S. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BRANFORD HARBOR, CT (See Section 2 of Text). 
Channel between upper and lower wharves in the river. 
Channel at the mouth of the harbor. 
CAPE COD CANAL, MA (See Section 3 of Text). 
Purchase canal from Boston, Cape Cod & New York 
Canal Co., in accordance with contract dated July 29, 1921, 
executed by that company. 
Construct 3 bridges and widen canal to 250 feet 
Operation and care of works of improvement provided for the 
funds from War Department appropriations for rivers and 
harbors. 
Construct a mooring basin. 
Dredging and bank protection. 
Existing project for main canal adopted. 
15-foot channel and turning basin in Onset Bay. 
Extend East Boat Basin for an area of about 4.3 acres to a 
depth of 8 feet. 
CHATHAM (STAGE) HARBOR, MA 
(See Section 4 of Text). 
Entrance Channel 10 feet deep, 150 feet wide from Chatham 
Roads into upper harbor. 
GREAT SALT POND, BLOCK ISLAND, RI 
(See Section 5 of Text). 
Channel and jetties. 
Extending south jetty and dredging 
Channel and basin in inner harbor. 
GREEN HARBOR, MA (See Section 6 of Text). 
Channel 6 feet deep, 100 feet wide from deep water to head of 
navigation; anchorage near town pier; sealing, rebuilding in 
part and extension of existing west jetty. 
HARBOR OF REFUGE, BLOCK ISLAND, RI 
(See Section 7 of Text). 
The main breakwater 
Repairs to basin walls and cliff protection east of harbor. 
Breakwater inclosing inner harbor. 
Raising crest of main breakwater and making it sandtight. 
H. Doc. 37, 85th Cong., 1st sess. 
Public Law 87-874, 87th Cong. 
H. Doc. 251, 89th Cong. 
H. Doc. 100, 56th Cong., 2nd sess. 
and Annual Report for 1901, page 
1188. 
Specified in Act. 
H. Doc. 139, 67th Cong., 2nd sess. 
H. Doc. 795, 71st. Cong., 3rd sess. 
Do. 
Do. 
Do. 
Rivers and Harbor Committee 
Doc. 15, 74th Cong., 1st sess. 
H. Doc. 431, 77th Cong., 1st sess. 
H. Doc. 168, 85th Cong., 1st sess. 
H. Doc. 456, 77th Cong., 1st sess. 
Annual Report 1942. 
H. Doc. 57, 54th Cong., 1st sess. 
Specified in Act. Annual Report for 
1900, p. 1276. 
H. Doc. 330, 77th Cong., 1st sess. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, December 
15, 1965. 
Annual Report 1868, p. 785 and 
S. Misc. Doc. 81, 40th Cong., 
2nd sess. 
S. Ex. Doc. 26, 47th Cong., 1st sess. 
S. Doc. 27, 48th Cong., 2nd sess. and 
Annual Report 1885, p. 610. 
H. Doc. 83, 54th Cong., 1st sess. 
1-34

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1827 
July 11, 1871 
Aug. 5, 1886 
Mar. 2, 1945 
Oct. 27, 1965 
June 2, 1874 
October 16, 1879 
June 13, 1902 
August 26, 1937 
June 14, 1880 
August 5, 1886 
Aug. 2, 1882 
Mar. 3, 1899 
July 25, 1912 
Do. 
July 3, 1930 
Aug. 30, 19352 
Mar. 2, 1945 
July 24, 1946 
Aug. 16, 1949 
Aug. 9, 1955 
Nov. 17, 1986 
Mar. 3, 1899 
Mar. 4, 1913 
Sept. 22, 1922 
Oct. 23, 1962 
July 9, 1965 
Sept. 16, 1890 
Mar. 2, 1907 
June 25, 1910 
Mar. 2, 1919 
June 30, 1948 
July 14, 1960, 
as amended 
HYANNIS HARBOR, MA (See Section 8 of Text). 
Breakwater. 
Present dimensions of breakwater. 
Dredging behind breakwater. 
Channel, anchorage and jetty. 
JONESPORT HARBOR, ME (See Section 9 of Text). 
A steel sheetpile breakwater 1200 feet in length. 
A 15-acre anchorage composed of 9 acres 6 feet deep and 
6 acres 8 feet deep. 
An entrance channel 100 feet wide and 8 feet deep. 
MILFORD HARBOR, CT (See Section 10 of Text). 
East jetty at the mouth of the river. 
West jetty at the mouth of the river. 
Entrance channel. 
Anchorage west of channel and present project dimensions of 
channel above Merwin's Wharf 
NANTUCKET (HARBOR OF REFUGE), MA 
(See Section 11 of Text). 
West jetty.3 
East jetty and dredging when necessary. 
NEW HAVEN HARBOR, CT (See Section 12 of Text) 
Sandy Point dike. 
The 16-foot anchorage basin. 
Present project dimensions of channels in Mill River. 
Present project dimensions of West River channel and anchorage. 
18- and 16-foot channels in Quinnipiac River. 
25-foot channel 
30-foot channel and anchorage and present location of 16-foot 
anchorage. 
35-foot main channel, elimination of 30-foot anchorage, present 
location and extent of 16.-foot anchorage 
Brewery Street channel declared non-navigable. 
Abandonment of upper end of West River. 
Deepen main ship channel to 40 feet; widen main ship channel 
to 500 feet; widen at Southwest Ledge to minimum of 780 feet; 
straighten channel downstream of turning basin. 
PLYMOUTH HARBOR, MA (See Section 13 of Text). 
Beach protection. 
Dredging 18-foot channel. 
Dredging 15-foot extension, including turning basin. 
Rubblestone breakwater. Anchorages are 8 feet deep inside 
breakwater. Elimination of authorized 18-foot anchorage 
from existing project. 
Recreational development 
POINT JUDITH POND AND HARBOR 
OF REFUGE, POINT JUDITH, RI 
(See Section 14 of Text). 
The main breakwater. 
Present dimensions of eastern shore arm. 
Western shore arm. 
Removing 3 shoals from the harbor arm. 
Abandons project for entrance to Point Judith Ponds, and 
authorizes channels and anchorages in lower pond and 
upper pond. 
Extension of existing 15-foot channel. 
S. Doc. 32, 18th Cong., 2nd sess. 
H. Doc. 63, 41st Cong., 2nd sess. 
H. Ex. Doc. 96, 48th Cong., 2nd sess. 
H. Doc. 98, 77th Cong., 1st sess.' 
H. Doc. 481, 94th Cong., 2nd sess. 
Authorized by H. Res. September 23, 
1976 and S. Res. October 1, 1976 
pursuant to Section 201 of cited Act. 
H. Ex. Doc. 107, 42nd Cong., 3rd sess., 
and Annual Report 1873, p. 1042. 
Authorized by Dept., October 16, 1879. 
Annual Report for 1879, p. 342. 
H. Doc. 280, 56th Cong., 1st sess. 
H. Doc. 77, 75th Cong., 1st sess. 
H. Doc. 18, 45th Cong., 2nd sess. and 
Annual Report for 1880, page 423. 
Annual Report for 1885, page 579. 
Plans approved by a Board of Engineers, 
October 2, 1882. 
H. Doc. 82, 55th Cong., 1st sess. 
H. Doc. 26, 62nd Cong., 1st sess. 
H. Doc. 535 62nd Cong., 2nd sess. 
H. Doc. 686, 69th Cong., 2nd sess. 
H. Doc. 479, 72nd Cong., 2nd sess. 
H. Doc. 307, 76th Cong., 1st sess. 
H. Doc. 517, 79th Cong., 2nd sess.' 
H.R. 3511, 81st Cong., 1st sess., P.L. 
234 
Annual Report for 1899, p. 1089. 
H. Doc. 1194, 62nd Cong., 3rd sess. 
H. Doc. 996, 66th Cong., 3rd sess. 
H. Doc. 124, 87th Cong., 2nd sess. 
H. Doc. 66, 51st Cong., 1st sess. 
H. Doc. 60, 58th Cong., 2nd sess. 
H. Doc. 911, 60th Cong., 1st sess. 
H. Doc. 2001, 64th Cong., 2nd sess. 
S. Doc. 15, 80th Cong., 1st sess. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, September 
29, 1976. 
1-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sept. 3, 1954 
Oct. 23, 1962 
July 14, 1960, 
as amended 
Nov. 17, 1986 
August 26, 1937 
Aug. 11, 1888 
June 25, 1910 
July 14, 1960, 
as amended 
July 14, 1960, 
as amended 
Mar. 2, 1827 
June 23, 1866 
Sept. 19, 1890 
June 25, 1910 
Mar. 3, 1925 
Aug. 30, 1935 
July 14, 1960, 
as amended 
July 14, 1960, 
as amended 
June 10, 1872 
July 14, 1960, 
as amended in 
1965 
PORTSMOUTH HARBOR & PISCATAQUA RIVER, 
ME and NH (See Section 15 of Text). 
Removal of ledge rock; widening 35-foot channel; extending 
channel and maneuvering basins above Boiling Rock and at 
head of project. 
Modified existing project for widening and extending 35-foot 
channel 
Construct 6-foot channels and anchorages 
Widen 35-foot channel to 1,000 feet between two vertical lift 
bridges; widen northern limit of 35-foot channel by 100 feet 
and widen southern limit to 550 feet at Goat Island. 
PROVIDENCE RIVER and HARBOR, RI 
(See Section 16 of Text). 
35-foot channel. 
ROCKPORT HARBOR, ME (See Section 17 of Text). 
Dredge an area about 400 feet by 600 feet in front of wharves 
at the head of the harbor to a depth of 12 feet at mean low 
tide and for removal of a small ledge. 
Remove the ledge at the entrance to a depth of 15 feet at 
mean low tide; widening the entrance channel to 250 feet. 
ROCKPORT HARBOR AND PIGEON COVE, 
ROCKPORT, MA (See Section 18 of Text). 
An access channel -10 feet deep by 80 feet wide. Two outer 
harbor anchorages between the breakwater and the town 
wharf. 
Pigeon Cove consists of 75-foot wide channel -10 feet deep; 
dredge anchorage area north of channel to -8 feet. 
RYE HARBOR, NH (See Section 19 of Text). 
Dredge channel 100 feet wide and 10 feet deep for 600 feet 
through entrance, thence 8 feet deep within harbor; dredge 
2 anchorages and maintain existing breakwaters. 
SACO RIVER, ME (See Section 20 of Text). 
Extension of piers, placing of buoys, and removal of obstruction 
at entrance to harbor. 
Breakwater on north side of mouth of river. 
Jetty on north side of mouth of river. 
Channel improvements and jetty extension on south side of 
mouth of river. 
Present project channel dimensions and extensions of north 
breakwater about 1,600 feet. 
Extension of north breakwater to Sharps Ledge. 
Anchorage and maneuvering basin. 
SESUIT HARBOR, MA (See Section 21 of Text). 
Channel 6 feet deep and 100 feet wide. 
WELLS HARBOR, ME (See Section 22 of Text). 
Repairs of old government pier about 750 feet long; 
anchorage basin; channel 100 to 150 feet wide. 
Two stone jetties. 
Annual Report 1892. H. Doc. 556, 
82nd Cong., 2nd sess. 
H. Doc. 482, 87th Cong., 2nd sess. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, December 
23, 1965. 
Annual Report 1915, 1936, 1938. 
H. Doc. 173, 75th Cong., 1st sess. 
River and Harbor Act. H. Ex. 
Doc. 141, 50th Cong., 1st sess. 
River and Harbor Act. H. Doc. 963, 
60th Cong., 1st sess. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, March 27, 
1986. 
H. Doc. 439. 86th Cong., 2nd sess. 
S. Ex. Doc. 44, 48th Cong., 1st sess., 
and Annual Report 1884, p. 482 
H. Doc. 752, 61st Cong., 2nd sess.' 
H. Doc. 477, 68th Cong., 2nd sess. 
Rivers and Harbors Committee 
Doc. 11, 74th Cong., 1st sess.' 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers, November 
14, 1967. 
P.L. 86-645, Section 107. Authorized 
by Chief of Engineers. February 6, 
1980. 
H. Doc. 202, 86th Cong., 2nd sess. 
Authorized by Chief of Engineers, 
September 20, 1965. 
1-36

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Sept. 3, 1954 
Oct. 27, 1965 
July 7, 1964 
Mar. 7, 1974 
June 30, 1948, 
as amended 
July 24, 1946, 
as amended 
June 30, 1948, 
as amended 
June 28, 1938 
June 30, 1948, 
as amended 
July 3, 1958 
Oct. 23, 1962 
Oct. 22, 1976 
November 17, 1986 
July 24, 1946, 
as amended 
July 24, 1946, 
as amended 
WOOD ISLAND HARBOR and POOL at BIDDEFORD, 
ME (See Section 23 of Text). 
Dredged basin 6 feet deep and construction of three ice 
breakers 
REVERE BEACH, MA (See Section 28 of Text). 
Placement of sandfill for protection and improvement. 
Raising and widening of about 13,000 feet of beach by 
placement of sandfill. 
ROOSEVELT CAMPOBELLO INTERNATIONAL PARK 
LUBEC, ME (See Section 29 of Text). 
Stone slope protection for the lighthouse at Mulholland Point. 
CHARLES RIVER (NATURAL VALLEY STORAGE 
AREAS), MA (See Section 34 of Text). 
Federal acquisition and perpetual protection of 17 crucial 
natural valley storage areas totalling 8,422 acres in what is 
known as the Middle and Upper watershed of the Charles 
River. 
BEAVER BROOK, KEENE, NH (See Section 35C of Text). 
Construct improvements to reduce the damaging effects of 
floods. 
FARMINGTON RIVER, SIMSBURY, CT 
(See Section 35G of Text). 
Bank protection by clearing and grubbing existing slope and 
refilling eroded areas with compacted granular fill. 
RIVERDALE, WEST SPRINGFIELD, MA 
(See Section 35M of Text). 
Construct improvements to existing pumping station. 
WEST SPRINGFIELD, MA (See Section 35R of Text). 
A system of earth levees and concrete floodwalls approx. 24,500 
feet long. Work involves raising 13,700 feet of existing levee; 
constructing 2,300 feet of floodwall; improving 2,400 feet of 
river bank; treating 6,100 feet of existing levee foundation. 
Three pumping stations with appurtenant drainage facilities 
also constructed. 
Raise the floodwall section of the West Springfield project by 1 
foot in combination with a flood forecasting system. 
NEW BEDFORD, FAIRHAVEN AND ACUSHNET, 
MA (See Section 38 of Text). 
Hurricane barriers in New Bedford Harbor. 
NEW LONDON, CT (See Section 39 of Text). 
Hurricane barrier protecting city of New London from tidal 
damage. 
BROCKTON, MA (See Section 40 of Text). 
Flood control works for protection of Brockton. 
LITTLE RIVER, BELFAST, ME (See Section 41 of Text). 
Replace existing wing wall with approximately 80 linear feet of 
precast concrete modular wall. 
PERLEY BROOK, FORT KENT, ME 
(See Section 42 of Text). 
Construct stone revetment along 100 linear feet adjacent to 
Route 161. Excavate four river shoals. 
H. Doc. 49, 81st Cong., 1st sess. 
H. Doc. 146, 82nd Cong., 1st sess. 
H. Doc. 211, 91st Cong., 2nd sess. 
Authorized by H. Res. 15 Dec. 70 
and S. Res. 17 Dec. 70 pursuant to 
Section 201 of 1965 Flood Control 
Act. 
Roosevelt Campobello International 
Park Act, P.L. 88-363. 
Chief of Engineers report dated 
December 6, 1972. 
P.L. 80-858, Section 205. Authorized 
by Chief of Engineers, June 21, 
1985. 
P.L. 79-526, Section 14. Approved by 
Chief of Engineers, September 27, 
1988. 
P.L. 80-858, Section 205. Authorized 
by Chief of Engineers, June 13, 
1986. 
H. Doc. 455, 75th Cong., 2nd sess. 
P.L. 80-858, Section 205. Authorized 
by Chief of Engineers, October 5, 
1982. 
S. Doc. 59, 85th Cong., 1st sess. 
H. Doc. 478, 87th Cong., 2nd sess. 
P.L. 99-662, W.R.D.A. of 1986 
(Section 401 (c)). 
P.L. 79-526, Section 14. Authorized 
by Chief of Engineers, May 23, 
1988. 
P.L. 79-526, Section 14. Authorized 
by Chief of Engineers, August 22, 
1988. 
1-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ROUGHANS POINT, REVERE, MA 
(See Section 43 of Text). 
Nov. 17, 1986 Stabilize existing facilities along the shore with a 4,080-foot 
long armor stone revetment. Construct earth berm 1-foot 
high and 200 feet long on existing median strip between 
Bennington Street and State Road. 
STAMFORD, CT (See Section 44 of Text). 
July 14, 1960 Hurricane barrier protecting areas of Stamford from tidal H. Doc. 210, 86th Cong., 1st sess. 
damage. 
TOWN BROOK, QUINCY & BRAINTREE, MA 
(See Section 46 of Text). 
Nov. 17, 1986 Construct 12-foot diameter, 4,060-foot long, concrete lined H. Doc. 39, 99th Cong., 1st sess. 
tunnel in bedrock approximately 190 feet below ground. 
WEST RIVER, WEST HAVEN, CT 
(See Section 47 of Text). 
June 30, 1948, Widen river for 1,150 feet to 50-70 feet. Widen the Wintergreen P.L. 80-858, Section 205. Approved 
as amended Brook channel to 20-30 feet. Construct recreational walkway by Secretary of the Army, 
connecting two existing city parks. September 26, 1988. 
'Contains latest maps. 
2Also Public Works Administration, September 6, 1933. 
3Inactive (a portion 800 feet long). 
1-38

NEW ENGLAND DIVISION 
TABLE 1-C OTHER AUTHORIZING NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full 
Report 
See Contributed 
Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Andrews River, MA 16"15 
Apponaug Cove, RI' 
Bagaduce River, ME 3 ,4'5 
Bar Harbor, ME' 
Bass Harbor, ME 1,6 
Bass Harbor Bar, ME' 
Beals Harbor, ME1' 
Belfast Harbor, ME' 
Bellamy River, NH"3 '4 
Beverly Harbor, MA' 
Black Rock Harbor, CT' 
Boothbay Harbor, ME' 
Boston Harbor, MA 1 ,22 
Bridgeport Harbor, CT' 
Bristol Harbor, Bristol, RI 
Bucks Harbor, Machiasport, ME 1,6 
Bucksport Harbor, ME' 
Bullocks Point Cove, RI' 
Bunker Harbor, ME1"
6 
Buttermilk Bay Channel, MA1,6 
Camden Harbor, ME' 
Canapitsit Channel, MA"'4 
Cape Porpoise Harbor, ME' 
Carvers Harbor, Vinalhaven, ME' 
Cathance River, ME"3 
Clinton Harbor, CT' 
Coasters Island Harbor, RI"4 
Cobscook Bay, ME",3'4 
Cocheco River, NH1"
3 '4 
Cohasset Harbor, MA' 
Connecticut River (above Hartford), CTS 
Connecticut River below Hartford, CT' 
Corea Harbor, Gouldsboro, ME 1"
6 
Criehaven Harbor, ME' 
Cross Rip Shoals Nantucket Sound, MA' 
Cuttyhunk Harbor, MA' 
Damariscotta River, ME 1,4 
Deer Island Thoroughfare, ME"4 
Dorchester Bay and Neponset River, MA" 
Duck Island Harbor, CT' 
Duxbury Harbor, MA' 
East Boothbay Harbor, ME' 
Edgartown Harbor, MA' 
Essex River, MA' 
Exeter River, NH",4 
Fall River Harbor, MA5 
Falmouth Harbor, MA' 
Fivemile River Harbor, CT5 
Frenchboro Harbor ME' 
Georges River, ME1 
Gloucester Harbor and Annisquam River, 
MA' 
Greenwich Bay, RI' 
Greenwich Harbor, CT' 
Guilford Harbor, CT' 
Hampton Harbor, NH1"
6 
Harraseeket River, ME1"4 
Hay (West Harbor), Fisher's Island, NY 1 
Hendrick's Harbor, ME' 
Hingham Harbor, MA 1 
Housatonic River, CT5 
Ipswich River, MA 
Island End River, Chelsea, MA 1,6 
Isle Au Haut Thoroughfare, ME' 
Isle of Shoals Harbor, ME and NH' 
1988 
1964 
1912 
1932 
1965 
1920 
1959 
1971 
1897 
1951 
1988 
1953 
1984 
1983 
1987 
1976 
1907 
1979 
1969 
1985 
1960 
1899 
1977 
1964 
1884 
1985 
1911 
1866 
1913 
1979 
1932 
1988 
1984 
1939 
1954 
1987 
1906 
1916 
1968 
1953 
1978 
1953 
1978 
1948 
1913 
1984 
1978 
1969 
1978 
1978 
1983 
1893 
1969 
1983 
1988 
1896 
1931 
1957 
1954 
1983 
1969 
1983 
1980 
1977 
$ 219,042 
156,8742 
28,000 
406,591 
188,859 
4,076 
184,880 
61,56132 
34,643 
246,048 
18,000 
25,313,08333 
4,491,11949 
316,288 
277,420 
18,421 
170,902 
95,372 
163,855 
102,400 
9,113 
175,037 
190,438 
21,000 
104,957 
5,500 
4,173 
119,089 
267,76738 
116,324 
1,541,18552,53 
797,954 
40,776 
24,200 
27,176 
5,000 
40,000 
94,584 
482,166 
421,29729 
6,500 
65,61435 
21,759 
27,454 
6,164,75740 
123,763 
35,490 
657,345 
25,788 
1,296,93436 
2,000 
198,758 
137,222 
200,000 
30,963 
8,401 
28,204 
28,316 
859,691 
5,618 
311,850 
137,653 
80,691 
$ 490,220 
23,429 
39 
2,187 
21,475 
12,175 
119,267 
252,763 
16,821 
1,573,091 
22,983 
9,919,43819 
2,009,75450 
16,838 
20,833 
76,667 
28,406 
213,32346 
138,880 
12,279 
347,865 
9,021 
974,711 
13,161 
42,617 
259,978 
15,822 
15,284,83954 
83,243 
8,125 
54,328 
1,054,58947 
905 
362,224 
399,546 
843,179 
17,238 
62,980 
83,93814 
3,032 
2,064,76734 
312,100 
188,802 
24,616 
246,413 
1,494,557 
6,527 
204,872 
1,266,169 
2,116,805 
5,309 
38,026 
6,325 
162,626 
2,397,757 
32,947 
180,786 
643,364 
1-39 
187,500 
100,000 
147,887 
123,757 
69,323 
20,000 
127,000 
130,410 
11,643 
35,00030 
10,000 
35,000 
25,000 
100,000 
25,500 
193,761 
222,010 
192,33648

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full 
Report 
See Contributed 
Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Josias River, ME' 1977 115,565 122,173 26,813 
Kennebec River, ME' 1987 1,599,94031 2,319,407 
Kennebunk River, ME' 1985 261,417 1,234,403 88,917 
Kingston Harbor (North Plymouth), MA' 1895 8,940 - 
Lagoon Pond, Martha's Vineyard, MA"1,6 1976 99,098 9,089 80,990 
Lamprey River, NH" ,4 1913 19,980 33,563 
Little Harbor, NH1 ,4 ,26 1977 133,227 266,119 
Little Harbor, Woods Hole, MA"4 1906 18,000 5,224 
Lubec Channel, ME' 1956 380,322 23,941 
Lynn Harbor, MA' 1956 755,576 206,203 
Machias River, ME' 1972 32,000 212,337 
Malden River, MA",20 1922 104,853 45,097 62,000 
Matinicus Harbor, ME1 1962 14,00021 8,989 
Medomak River, ME' 1953 17,000 92,359 
Menemsha Creek, MA' 1981 56,926 629,644 12,500 
Merrimack River, MA' 1940 369,891 233,998 
Mianus River, CT' 1985 132,435 659,390 46,500 
Moosabec Bar, ME' 1930 11,400 25,227 
Mystic River, CT' 1957 197,582 143,385 14,000 
Mystic River, MA' 1986 3,222,777 2,009,244 
Narraguagus River, ME' 1969 821,144 71,087 
New Bedford and Fairhaven Harbors, MA' 1953 1,857,618 708,967 20,385 
New Harbor, ME' 1966 118,62024 26,944 7,015 
New Haven Breakwater, CT' 1950 1,242,246 40,273 
New London Harbor, CT' 1986 638,77417 1,849,944 
Newburyport Harbor, MA5 1988 569,22523 4,549,271 
Newport Harbor, RI' 1953 733,524 128,223 
Niantic Bay and Harbor, CT"1 ,6 1972 66,464 111,789 67,500 
Northeast Harbor, ME' 1954 138,942 51,047 
Norwalk Harbor, CT' 1983 531,12939 3,784,09242 34,500 
Owl's Head Harbor, ME13 1968 124,158 13,867 4,383 
Patchogue River, CT 1,22 1984 355,445 621,988 56,694 
Pawcatuck River, Little Narragansett Bay 
and Watch Hill Cove, RI & CT' 1978 318,78728 658,630 20,000 
Pawtuxet Cove, RI' 1975 295,356 152,105 295,356 
Penobscot River, ME' 1985 501,020 917,306 
Pepperell Cove, ME5 1969 171,351 46,882 
Pig Island Gut, ME"1,6 1966 191,753 86,456 
Pleasant River, ME' 1892 3,500 217 
Pollock Rip Shoals, Nantucket Sound, MA' 1956 1,083,504 846,590 
Portland Harbor, ME' 1985 9,588,71027 7,903,331 
Potowomut River, RI' 1882 5,000 50 
Provincetown Harbor, MA5 1985 3,548,95441 1,053,966 760,000 
Red Brook Harbor, Bourne, MA6,8 1972 38,764 - 
Richmond Harbor, ME",4 1883 20,000 - 
Richmond's Island Harbor, ME 1,4 1882 119,844 1,808 
Rockland Harbor, ME 1976 1,948,462 452,800 255,000 
Rockport and Old Harbors, Rockport, MA 1986 22,000 194,963 
Royal River, ME",6 1986 336,704 728,62212 49,56251 
St. Croix River, ME' 1950 179,550 36,392 19,892 
Sakonnet Harbor, RI' 1983 764,651 192,164 21,928 
Sakonnet River, RI , o 1909 38,427 9,549 
Salem Harbor, MA' 1969 1,693,202 509,290 
Sandy Bay (Harbor of Refuge), Cape Ann, 
MA' s 1922 1,925,553 16,060 
Sasanoa River, ME1 3'4 1915 35,000 124 
Scarboro River, ME' 1976 392,635 1,239,293 10,000 
Scituate Harbor, MA' 1971 379,851 148,751 69,976 
Searsport Harbor, ME' 1966 572,56816 45,270 
Seekonk River, RI' 1954 672,214 793,234 67,792 
South Bristol Harbor ME' 1971 89,593 12,706 2,663 
Southport Harbor, Cft 1962 96,9277 374,913 18,525 
Southwest Harbor, ME' 1962 180,042 66,540 7,501 
Stamford Harbor, CT5 1980 892,82437 1,727,72045 169,636 
Stockton Harbor, ME 1,3,4 1915 33,000 23,216 
1-40

NEW ENGLAND DIVISION 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 Contributed 
Full Report Funds 
See Annual Operation and Expended 
Project Report for Construction Maintenance (Construction) 
Stonington Harbor, CT' 1959 377,328 123,060 
Stonington Harbor, ME1"
6 1985 898,500 5,067 
Stony Creek, Branford, CT 1'6 1978 112,487 313,602 92,000 
Sullivan Falls Harbor, ME' 1914 19,871 - 
Taunton River, MA5 1948 442,895 32,917 
Tenants Harbor, ME' 1920 18,750 13,292 
Thames River, CT' 1967 1,471,919 1,603,730 
Union River, ME3",
15 1912 146,855 130,375 
Vineyard Haven, MA' 1943 27,186 8,699 
Wareham Harbor, MA5 1896 95,997 10,296 
Warren River, RI 1890 5,000- 
Warwick Cove, RI"6 1975 155,430 51,196 107,220 
Wellfleet Harbor, MA' 1981 157,63425 926,068 32,000 
Westcott Cove, CT' 1978 55,960 291,377 21,000 
Westport Harbor and Saugatuck River, CT5 1972 19,308 180,824 
Westport River, MA4,9 1942 -- 
Weymouth Back River, MA' 1944 48,740 26,411 20,000 
Weymouth-Fore & Town Rvrs., MA"1 22 1979 and 1983 30,194,61343 1,394,14544 630,133 
Wickford Harbor, RI1 ,22 1973 233,410 70,435 49,094 
Wilson Point Harbor, CT 1,4 1895 54,177- 
Winnipesaukee Lake NH' 1952 7,500 29,870 
Winter Harbor, ME1, 1976 162,937 9,935 
Winthrop Harbor, MA' 1895 8,992 38,515 
Woods Hole Channel, MA' 1940 230,000 51,718 
York Harbor, ME' 1977 239,654 351,090 32,161 
1 Completed. 
2 Excludes costs of $137,583 for local cooperation requirements, 
which includes $104,583 cash contribution. 
3 Abandonment recommended in H. Doc. 467, 69th Congress, 
1st session. 
" No commerce reported. 
s Completed except for inactive portion. 
6 Authorized by the Chief of Engineers (Public Law 86-645, 
Sec. 107). 
SIncludes $37,714 Emergency Relief Funds. Excludes $18,525 
Contributed Funds, of which $1,785 was for work outside approved 
project. 
8 Inactive. 
9 Awaiting local cooperation. Improvement to be 
restudied. 
o1C0 ommerce included under Tiverton Harbor, RI. 
11 Authorized work remaining on project is comprised of an 
incomplete and an inactive portion. 
12 Excludes $20,000 expended from Contributed Funds, Other 
for maintenance. 
13 Recommendation for abandonment of existing project made 
in H. Doc. 467, 69th Congress, 1st session. Portion of project 
authorized by the Chief of Engineers (P.L. 86-645, Sec. 107) is 
complete. 
4 Excludes $5,000 Contributed Funds expended. 
15 Improvement adequate for commerce. 
16 Costs to local interests for berth improvements are estimated 
to be $60,000. 
17 Includes $40,800 for previous project. 
18iAs bandonment recommended in H. Doc. 411, 64th 
Congress, 1st session, and in River and Harbor Committee 
Doc. 3, 65th Congress, 1st session. 
19 Includes $17,879 for previous projects. Excludes $17,767 
Contributed Funds. 
20 Under State maintenance. 
21 Excludes $114,327 expended for rehabilitation; breakwater 
repaired in 1962. 
22 Portion of project authorized by Chief of Engineers. 
23 Excludes $1,415,524 expended for Major Rehabilitation.
24 All assurances of local cooperation have not been fulfilled. 
Public landing at Back Cove has not been constructed. 
Portion of project authorized by Chief of Engineers (Public 
Law 86-645, Sec. 107). 
25 Includes $11,350 for previous project. 
26 H. Doc. 467, 69th Cong., 1st sess. recommended eliminatin 
maintenance dredging. 
27Includes $692,435 for previous projects. 
28 Includes $133,357 for previous project. 
29 Includes $37,000 for new work for previous project. 
30 Excludes local requirements of $65,000 consisting of 
$13,000 for public wharf and $52,000 for additional construction 
costs. 
31 Includes $509,411 for previous projects. 
32 Includes $22,000 for previous projects. 
33 Includes $1,465,123 for previous projects. Includes 
$935,303 Emergency Relief Funds and $1,030,806 Public Works 
Funds. 
34 Includes $81,410 for previous project. 
35 Includes $15,614 for new work for previous projects. 
1-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
36 Includes $21,000 for previous projects. 
3 Includes $135,143 for previous project. 
38 Includes $10,000 for previous project. 
3 Includes $162,517 for previous project. 
40 Includes $330,204 for previous project. 
41 Includes $215,801 for previous project. 
42 Includes $66,120 for previous projects. 
43 Includes for previous projects $735,900 (Weymouth, Fore 
River) and $25,000 (Town River). 
Includes for previous project $5,250 (Weymouth, Fore River) 
and $12,577 (Weymouth, Town River). 
45 Includes $59,420 for previous project. 
46 Includes $35,214 for previous project. 
47 Excludes $50,000 Contributed Funds expended for maintenance. 
48 Excludes $582,188 Contributed Funds, Other expended. 
49 Includes $378,450 for previous project 
50 Includes $11,949 for maintenance of previous project. 
5' Excludes $18,000 Contributed Funds, Other. 
52 Includes $287,374 for previous projects and excludes $9,000 
for subproject "Eightmile River, CT". 
S3Excludes $60,000 expended for Major Rehabilitation. 
64 Includes $366,348 for previous projects. 
TABLE 1-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last 
Full Report Cost to Amount 
See Annual Sept. 30, 1989 Expended by 
Project Report For Construction Local Interest 
Burial Hill Beach, Westport, CT' 1958 $ 5,810 $ 11,612 
Calf Pasture Beach Park, Norwalk, CT' 1964 56,386 120,179 
Clark Point Beach, New Bedford, MA' 1982 228,081 228,080 
Cliff Walk, Newport, RI6 1984 405,491 955,237 
Compo Beach, Westport, CT' 1962 84,544 169,089 
Cove Island, Stamford, CT' 1961 47,131 94,262 
Cummings Park, Stamford, CT' 1963 26,886 53,771 
Guilford Point Beach (Jacobs Beach), Guilford, CT' 1961 15,620 31,241 
Gulf Beach, Milford, CTi 1958 21,303 42,606 
Hammonasset Beach, Madison, CT' 1956 163,183 326,366 
Hampton Beach, Hampton, NH' 1966 260,868 385,641 
Jennings Beach, Fairfield, CT' 1956 14,401 28,802 
Lighthouse Point Park (Area 9), CT' 1961 3,930 7,859 
Lynn-Nahant Beach, MA 1986 50,000- 
Middle Beach, CT' 1958 8,810 17,620 
Misquamicut Beach, Westerly, RI3 1963 14,512 29,024 
Nantasket Beach, MA4 1971- 
North Scituate Beach, Scituate, MA' 1969 106,552 106,552 
Oak Bluffs Town Beach, Martha's Vineyard, MA' 1976 273,334 198,583 
Oakland Beach, Warwick, RI' 1982 559,200 181,175 
Plum Island, MA' 1977 118,882 104,875 
Prospect Beach, West Haven, CT' 1958 104,573 240,819 
Quincy Shore Beach, Quincy, MA' 1962 621,440 1,242,880 
Sand Hill Cove Beach, RI' 1959 40,143 82,000 
Sasco Hill Beach, Fairfield, CT' 1961 23,759 47,518 
Seaside Park, CT' 1958 150,000 329,921 
Sherwood Island State Park, Westport, CT' 1983 1,186,830 889,330 
Short Beach, CT' s-- 
Silver Beach to Cedar Beach, CT 1964 62,560 270,695 
Southport Beach, CT' 1960 17,631 35,263 
Town Beach, Plymouth, MA6 1964 5,490 10,981 
Wallis Sands State Beach, Rye, NH' 1966 65,131 435,942 
Wessagusset Beach, Weymouth, MA' 1971 180,944 200,208 
Willard Beach, South Portland, ME 1983 171,000 - 
Winthrop Beach, MA' 1960 176,567 353,134 
Woodmont Shore, Milford, CT' 1961 53,838 111,6792 
1 Completed. 
2 Excludes $118,215 expended for work beyond scope of project. 
3 Additional Federal participation will be required based on 
Public Law 87-874. 
" Project inactive. 
5 Project completed at no cost to Federal Government by 
using fill from Federal navigation improvement at Housatonic 
River. 
6 Completed except for inactive portion. 
1-42

NEW ENGLAND DIVISION 
TABLE 1-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Alford, Green River, MA3"4 
Alley Bay, Beals, ME3,4,"0� 
Amesbury, Powwow River, MA3'4 
Ansonia-Derby, CT3 
Bagaduce River, ME3,4"� 
Big River Reservoir, RI 
Blackstone River, Millbury, MA3'4,1o 
Bound Brook, Scituate, MA3'4 
Canton, MA3'4 
Charles River Dam, MA3 
Charlestown, NH3'4 
Cherryfield, ME3,4 
Chicopee, MA3 
Chicopee Falls, MA3 
Clear River, Burrillville, RI3,4 
Cocheco River, NH3,4 
Connecticut River, North Stratford, NH 3,4 
Connecticut River, W. Stewartstown, NH3,4 
Covered Bridge, Sheffield, MA3'4,"
� 
Danbury, CTa 
Derby, CT3 
East Branch Dam, CT 3 
East Hartford, CT3 
Fitchburg, MA (See No. Nashua River) 
Folly Brook, Wethersfield, CT3'4 
Fort Kent, ME3,4 
Fox Point Barrier, RI3 
Gardner, MA3'4 
Gulf Street, Milford, CT3 '4 "0 
Hall Meadow Brook Dam, CT3 
Hartford, CT3 
Hartford, White River, VT3'4 
Hayward Creek, Braintree-Quincy, MA3'4 
Holmes Bay, Whiting, ME3 ,4",o 
Holyoke, MA3 
Housatonic River, Pittsfield, MA3'4 
Housatonic River, Salisbury, CT3,4,"
0� 
Housatonic River, Sheffield, MA 3,4,"
0 
Huntington, MA3,4,10 
Island Avenue, Quincy, MA3,4 
Islesboro (The Narrows), ME3,4,10 
Johnson Bay, Lubec, ME 3,4",10 
Keene, NH '4 
Lancaster, Israel River, NH 3,4 
Lee, Housatonic River, MA3,4"o 
Little River Dike, Westfield, MA3 
Lowell, MA3 
Lower Woonsocket, RI3 
Machias River, Machias, ME 3,4 
Mad River Lake, CT3 
Marginal Way, Ogunquit, ME3'4 
Merriconeag Sound, Harpswell ME3 ,4",10� 
Mill Brook, Brownsville, VT ,4,1o 
Nashua, NH3 
Nonewaug River, Woodbury, CT3,4",10� 
Northampton, MA3 
North Canaan, Blackberry River, CT3,4 
North Nashua River, Fitchburg, MA3 
North Nashua River, Lancaster, MA3,4"10 
Norwalk, CT3.4 
Norwich, CT3 
Park River, Hartford, CT3 
Pawcatuck, CT 
Pawtuxet River, Warwick, RI3,4 
Penobscot River, Old Town, ME3 4 
Phillips Lake, MA 
Pleasant Point, Perry, ME3,4 
1977 
1979 
1978 
1977 
1985 
1987 
1986 
1974 
1964 
1981 
1976 
1963 
1954 
1978 
1987 
1963 
1982 
1976 
1988 
1978 
1977 
1973 
1951 
1979 
1979 
1976 
1970 
1988 
1970 
1960 
1973 
1979 
1980 
1953 
1985 
1982 
1981 
1960 
1983 
1985 
1985 
1955 
1982 
1976 
1945 
1977 
1987 
1973 
1987 
1980 
1988 
1950 
1985 
1950 
1977 
1981 
1979 
1952 
1960 
1986 
1966 
1986 
1986 
1982 
1987 
$ 41,419 
190,500 
132,113 
18,266,040 
129,500 
249,999 
47,300 
180,6706 
41,170,921 
113,330 
203,000 
1,433,6007 
2,183,912 
168,000 
183,100 
180,000 
54,703 
250,000 
13,143,000 
7,582,642 
1,959,836 
2,135,447 
220,284 
1,997,820 
11,112,801 
495,691 
250,000 
2,572,357 
6,094,1009 
332,236 
2,235,470 
207,390 
3,418,000 
739,003 
102,800 
205,608 
3,900 
172,000 
165,500 
163,082 
44,100 
551,606 
37,852 
5,000 
490,600"11 
6,600,681 
152,000 
4,773,020 
243,000 
107,681 
110,000 
270,0008 
222,500 
680,00017 
73,865 
3,241,42123 
81,671 
52,150 
1,209,000 
60,150,864 
644,311 
3,171,309 
178,045 
300,000 
189,000 
1-43 
', - 
21 
4,576 
92,891 
5,554,08815 
385 
411,29222 
166,526 
2
19 
7,637 
3,679,50014 
15,000 
21,000 
2,781,100 
24,447 
13 
1,266,63820 
327
16 
214,106

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Port 5 Facility, Bridgeport, CT3 '4 ,10 1986 227,500 - 
Prestile Stream, Blaine, ME3 ,4 ,10 1980 73,674 - 
St. John River Basin, ME24 - 13,070 - 
Salmon River, Colchester, CT3'4 1983 247,100- 
Sand Cove, Gouldsboro, ME 1984 127,500- 
Saxonville, MA3 1981 4,218,700 - 6 
Sebasticook River, Hartland, ME3'4 1985 1,857,475- 
Shelburne, Androscoggin River, NH 3,4,10 1977 37,657- 
Smelt Brook, Weymouth-Braintree, MA3,4 1978 1,803,739 - 
South River, Conway, MA 1987 133,500- 
Springdale, MA3 1952 700,000 - 
Springfield, MA3 1950 577,000s18 5,350 
Squantz Pond, New Fairfield, C'T3,4 1983 116,296- 
Stony Brook, Wilton, NH3'4 1973 19,500- 
Sucker Brook Dam, CT3 1976 2,227,712 58,800 
Three Rivers, MA3 1970 1,577,18912 
Torrington, East Branch, CT3 4 1963 389,200 - 
Torrington, West Branch, CT3' 4 1963 228,300- 
Trumbull Lake, CT' 1983 1,498,799 - 
Village of Saxtons, VyT, 3 4' 10 1985 140,500- 
Ware, MA3'4 1963 400,000- 
Waterbury-Watertown, CT3,4 1963 263,300- 
Weston, VT3'4 1957 13,000 1,800 
West Branch, Westfield River, Huntington, MA3'4 1983 116,492- 
West Warren, MA3,4 1964 389,200 41,000 
Whitmanville Lake, MA 1979 605,023- 
Winsted, CT3 1954 245,500- 
Woonsocket, RI3 1962 4,040,000 224,476 
Worcester Diversion, MA3 1978 5,086,859 79,316 
1 Inactive. 
2 Excludes $1,146,828 expended from Contributed Funds, 
Other. 
3 Completed. 
4 Authorized by Chief of Engineers. 
s Reflects FY1967 settlement of outstanding claims. 
6 Excludes $8,503 Contributed Funds, Other. 
7 Includes $295,000 Public Works Administration funds. 
8 Excludes $147,366 Flood Control and Coastal Emergency 
funds expended. 
9 Excludes $835,000 Public Works Administration funds. 
'o Emergency Bank Protection. 
11 Excludes $794,374 Public Works Administration funds. 
12 Excludes $565,168 Contributed Funds, Other. 
13 Excludes $3,000 Contributed Funds, Other. 
TABLE 1-F OTHER AUTHORIZED MU 
14 Cash for construction only. Excludes $245,000 expended 
for land condemnation. 
15 Excludes $1,674,567 Contributed Funds, Other. 
16 Excludes $259,408 Contributed Funds, Other. 
i1s Excludes $280,000 Public Works Administration funds. Excludes $355,000 Public Works Administration funds. 
19 Excludes $406,653 Contributed Funds, Other. 
20 Excludes $488,920 Contributed Funds, Other. 
21 Excludes $727,460 Contributed Funds, Other. 
22 Excludes $12,000 expended for land condemnations and 
$25,184 Contributed Funds, Other for relocations. 
23 Excludes $1,370,000 Public Works Administration funds 
expended on Fitchburg, MA. 
24 Irrigation demonstration project. 
LTI-PURPOSE PROJECTS 
INCLUDING POWER 
For Last Cost to September 30, 1989 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Passamaquoddy Tidal Power Project, ME' 1935 6,384,394 
1 Work discontinued in 1937. Facilities transferred to War Assets Administration. 
1-44

NEW ENGLAND DIVISION 
TABLE 1-G DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Contributed 
Project Report for Deauthorized Federal Funds 
Alternative for Sugar Hill Reservoir -Aug 1977 $ - $- 
Andover Lake, CT -. Aug 1977 - - 
Bagaduce River, ME (uncompleted portion) - Oct 1978 - - 
Baker Brook, MA 1972 Nov 1979 94,000 - 
Bar Harbor, ME (uncompleted portion) 1932 Nov 1986 - - 
Beards Brook Reservoir, NH 1949 Aug 1977 78,000 - 
Beaver Brook Lake, NH 1973 Apr 1978 378,300 - 
Bennington Reservoir, NH 1949 Aug 1977 205,000 - 
Black Rock Harbor, CT (uncompleted 
portion) 1986 Nov 1986 - - 
Brant Rock Beach, Marshfield, MA 1961 Nov 1979 - - 
Bridgeport Harbor, CT (uncompleted 
portion) 1980 Nov 1979 - - 
Brockway Lake, VT 1946 Aug 1977 - - 
Cambridgeport Lake, VT - Aug 1977 - - 
Chicopee, MA (uncompleted portion) 1954 Aug 1977 - - 
Claremont Lake, NH 1968 Dec 1970 242,700 - 
Clyde, RI 1948 Apr 1951 8,800 - 
Connecticut River below Hartford, CT 
(uncompleted portion) 1979 Oct 1978 - - 
Cotuit Harbor, MA 1962 Oct 1978 8,541 - 
Dickey-Lincoln School Lakes, ME 1984 Nov 1986 26,285,298 - 
Eastport Harbor, ME 1984 Nov 1983 638,675 141,530 
Edgartown Harbor, MA (uncompleted 
portion) 1978 Nov 1986 - - 
Fall River Harbor, MA (uncompleted 
portion) 1984 Nov 1986 - - 
Fivemile River Harbor, CT (uncompleted - - 
portion) 1969 Oct 1978 
Gaysville Lake, VT 1970 Oct 1976 206,600 - 
Great Salt Pond, Block Island, RI 
(uncompleted portion) 1983 Nov 1986 - - 
Greenwich Point Beach, CT 1959 Oct 1978 - - 
Harbor of Refuge, Block Island, RI 
(uncompleted portion) 1983 Nov 1986 - - 
Housatonic River, CT (uncompleted portion) 1979 Nov 1979 - - 
Honey Hill Lake, NH 1949 Aug 1977 92,000 - 
Ipswich River, MA (uncompleted portion) 1969 Nov 1986 - - 
Kennebec River, ME (uncompleted portion) 1986 Nov 1986 - - 
Ludlow Lake, VT - Aug 1977 - - 
Lynn Harbor, MA (uncompleted portion) 1956 Nov 1986 - - 
Manchester Harbor, MA 1949 Nov 1979 23,986 - 
Marblehead Harbor, MA 1968 Oct 1978 43,711 - 
Mattapoisett Harbor, MA 1950 Oct 1978 - - 
Milford Harbor, CT (uncompleted portion) 1981 Nov 1986 - - 
Monoosnoc Brook, MA 1967 Nov 1986 - - 
Monoosnoc Lake, MA 1967 Nov 1986 - - 
Mountain Brook Dam, NH 1949 Aug 1977 57,000 - 
Mystic, CT 1968 Aug 1972 67,700 - 
Mystic River, CT (uncompleted portion) 1986 Nov 1986 - - 
Nantucket, Harbor of Refuge, MA 
(uncompleted portion) 1965 Nov 1986 - - 
Napatree Beach, RI - Nov 1979 - - 
Narragansett Pier, RI 1966 Nov 1970 115,590 - 
New Bedford and Fairhaven Harbors, MA 
(uncompleted portion) 1953 Nov 1986 - - 
Newburyport Harbor, MA (uncompleted 
portion) 1986 Nov 1986 - - 
New Haven Harbor, CT (uncompleted 
portion) 1986 Nov 1986 - - 
Nookagee Lake, MA 1976 Nov 1986 563,677 - 
North Andover and Lawrence, MA 1949 Aug 1977 20,000 - 
North Hampton Beach, North Hampton, 
NH 1963 Nov 1981 - - 
Norwalk-Wilton, CT 1973 Nov 1979 - - 
Pawcatuck River, Little Narragansett Bay, 
RI and CT (uncompleted portion) 1978 Nov 1986 - - 
1-45

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-G (Continued) DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Contributed 
Project Report for Deauthorized Federal Funds 
Pawcatuck River, RI & CT (uncompleted 
portion) 1979 Nov 1979 - - 
Pawtucket, RI 1949 Nov 1977 - - 
Pepperell Cove, ME (uncompleted portion) 1969 Nov 1981 - - 
Pleasant Bay, MA 1971 Nov 1986 - - 
Point Judith, RI 1968 Nov 1977 198,477 - 
Pontiac Diversion, RI 1948 Apr 1951 24,200 - 
Providence River and Harbor, RI 
(uncompleted portion) 1976 Nov 1986 - - 
Provincetown Beach (Herring Cove), MA 1961 Oct 1978 - - 
Provincetown Harbor, MA (uncompleted 
portion) 1979 Oct 1978 - - 
Rockland Harbor, ME (uncompleted 
portion) 1976 Nov 1986 - - 
Saco River, ME (uncompleted portion) 1979 Oct 1979 - - 
Sakonnet Harbor, RI (uncompleted portion) 1982 June 1982 176,000 - 
Salem Harbor, MA (uncompleted portion) 1969 Nov 1986 - - 
Sandy Bay, Cape Ann, MA (uncompleted 
portion) 1922 Oct 1978 - - 
Silver Beach to Cedar Beach, CT' 1964 Nov 1986 - - 
South Coventry Lake, CT 1951 Aug 1977 96,000 - 
South Tunbridge Lake, VT - Aug 1977 - - 
Stamford Harbor, CT (2 projects 
uncompleted portions) 1979 Oct 1978 - - 
Stonington Harbor, CT (uncompleted 
portion) 1959 Nov 1986 - - 
Stonington Harbor, ME 1961 Nov 1979 2,543 - 
Stratford, CT 1973 Mar 1977 934,500 - 
Sugar Hill Reservoir, NH 1946 Dec 1944 - - 
Thames River, CT (uncompleted portion) 1967 Nov 1986 - - 
The Island Lake, VT - Aug 1977 - - 
Thumperton Beach, Eastham, MA 1961 Nov 1979 - - 
Town Neck Beach, Sandwich, MA 1961 Nov 1986 - - 
Wareham-Marion, MA 1965 Aug 1977 81,715 - 
Victory Lake, VT 1967 Aug 1977 168,400 - 
West Brookfield Reservoir, MA 1948 July 1960 67,000 - 
West Canaan Lake, NH 1948 Aug 1977 92,000 - 
Westerly, RI 1966 Nov 1986 - - 
Westfield, MA 1967 Se p 1969 507,200 - 
Westport, CT 1965 Feb 1970 29,634 - 
Westport Harbor and Saugatuck River, CT 
(uncompleted portion) 1972 Nov 1979 - - 
Williamsville Reservoir, VT 1949 Dec 1944 146,500 - 
Winthrop Beach, MA (uncompleted portion) 1960 Nov 1986 - - 
1 Walnut Beach and impermeable groins. 
1-46

NEW ENGLAND DIVISION 
TABLE 1-H NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
Fiscal Year 
Study Identification Costs 
Bar Harbor, ME $47,709 
Bass Harbor, Tremont, ME 59,073 
Bucks Harbor, Machiasport, ME 33,018 
Gloucester Harbor, Gloucester, MA 17,288 
Green Harbor, Marshfield, MA 3,696 
Hockanum River, Manchester, CT 67,508 
Nantucket Inner Harbor-Polpis, MA 2,498 
Narraguagus River, Milbridge, ME 24,218 
Nasketucket Bay, Fairhaven, MA 15,285 
Oak Bluffs Harbor, Oak Bluffs, MA 2,275 
Perkins Cove, Ogunquit, ME 9,175 
Pig Island Gut, Beals, ME 26,741 
Pine Point Harbor, Scarborough, ME 4,867 
Plymouth Harbor, Plymouth, MA 17,621 
Point Judith Pond, RI 39,563 
Provincetown Harbor, MA 82,395 
Saugus and Pine Rivers, MA 47,624 
Scituate Harbor, MA 33,018 
Stonington Harbor, Stonington, CT 25,916 
Winthrop Harbor, Winthrop, MA 45,300 
Wood Island Harbor, Biddeford, ME 34,789 
TABLE 1-I BEACH EROSION ACTIVITIES PURSUANT TO SECTION 103, 
PUBLIC LAW 78-874 (PREAUTHORIZATION) 
Fiscal Year 
Study Identification Costs 
Bullock Neck, East Providence, RI $ 9,602 
North Nantasket Beach, Hull, MA 3,816 
Ocean Grove Beach, Swansea, MA 13,932 
Prospect Beach, West Haven, CT 16,134 
Town Beaches, Sandwich, MA 15,500 
West Haven Beaches, CT 16,106 
Woodmont Beach, CT 58,613 
1-47

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-J FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858 (PREAUTHORIZATION) 
Study Identification 
Aroostook River, Fort Fairfield, ME 
Bay View Beach, Milford, CT 
Esopus Creek, Hurley, NY 
Esopus Creek, Shandaken, NY 
Esopus Creek (Pine Hill), Shandaken, NY 
Esopus Creek, Ulster, NY 
Mad River, Waterbury, CT 
Pawtuxet River, Warwick, RI 
Point Beach, Milford, CT 
Point of Pines, Revere, MA 
Rippowam River, Stamford, CT 
Sandberg Creek, Wawrsing, NY 
Saugatuck Shores, Westport, CT 
Spicket River, Salem, NH 
Winnipesaukee River, NH 
TABLE 1-K BLACKSTONE RIVER BASIN, MA AND RI 
(See Section 33 of Text) 
RESERVOIR 
Miles Estimated Federal Cost 
Above 
Mouth of 
Black- Reservoir Lands 
stone Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
West Hill2 Worcester, MA 25.8 51 Earthfill 12,400 $1,366,902 $940,000 $2,306,902 
1 Includes highway, railroad, and utility relocations. 
2 See individual report for details. 
1-48 
Fiscal Year 
Costs 
$24,286 
8,369 
8,807 
13,444 
4,842 
6,777 
74,586 
841 
6,710 
1,989 
1,243 
7,503 
5,162 
7,206 
95

NEW ENGLAND DIVISION 
TABLE 1-K (Continued) LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of 
Black- Lands , 
. 
stone and 
Location River Type of Structure Construction Damages' Total 
Worcester, MA 48 Diversion tunnel and channel $4,923,500 $1,179,0002 $6,102,500 
Woonsocket, RI 15 Channel improvement 3,740,100 1,069,0003 4,809,100 
Lower Woonsocket, Flood wall, conduits and 
RI 13 channel improvement 8,356,239 435,000 8,791,239 
Blackstone River, 
Millbury, MA 32 Slope protection 254,575 - 254,5755 
Clear River, 
Burrillville, RI 23 Retaining wall 168,000 - 168,000 
Pawtuxet River, 
Warwick, RI - Land acquisition 4,125,000 - 4,125,0004 
1 Includes relocation. 4 $3,300,000 Federal; $825,000 non-Federal. 
2 $158,000 Federal; $1,021,000 non-Federal. 5 $249,999 Federal; $4,576 non-Federal. 
3$300,000 Federal; $769,000 non-Federal. 
TABLE 1-L CONNECTICUT RIVER BASIN, VT, NH, MA AND CT 
(See Section 35 of Text) 
DAMS AND RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of 
Conne- Reservoir Lands 
cticut Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Vermont: 
Union Village2 White River 228.4 170 Earthfill 38,000 $3,186,860 $ 908,300 $4,095,160 
Junction 
North Hartland2 White River 211.7 185 Earthfill 71,400 6,349,225 963,000 7,312,225 
Junction 
North Springfield2 Springfield 191.3 120 Earthfill 50,600 4,781,526 2,050,000 6,831,526 
Ball Mountain2 Brattleboro 178.2 265 Rockfill- 54,600 10,689,298 350,000 11,039,298 
earth 
Townshend2 Brattleboro 168.3 133 Earthfill 33,200 5,520,413 1,878,000 7,398,413 
New Hampshire: 
Surry Mountain 2 Keene 174.4 86 Earthfill 32,500 2,448,610 385,000 2,833,610 
Otter Brook2 Keene 171.2 133 Earthfill 18,300 2,982,048 1,378,400 4,360,448 
Massachusetts: 
Birch Hill2 Gardner 153.3 56 Earthfill 49,900 1,740,679 3,075,000 4,815,679 
Tully2 Athol 148.7 62 Earthfill 22,000 1,298,752 368,000 1,666,752 
Barre Falls2 Worcester 130.2 62 Rockfill- 24,000 1,928,819 39,000 1,967,819 
earth 
Knightville2 Northampton 102.8 160 Earthfill 49,000 2,594,440 821,200 3,415,640 
Littleville2 Northampton 102.0 150 Earthfill 32,400 5,863,412 1,150,000 7,013,412 
Conant Brook 2 Springfield 122.0 85 Rockfill- 3,740 1,935,530 1,015,000 2,950,530 
earth 
Connecticut: 
Colebrook River 2 Winsted 116.0 223 Rockfill- 98,500 8,341,971 5,922,000 14,263,971 
earth 
Mad River Winsted 120.0 178 Earthfill 9,700 4,773,020 2,210,000' 6,983,020 
Sucker Brook Winsted 118.5 68 Earthfill 1,480 2,227,712 180,0003 2,407,712 
1 Includes highway, railroad, and utility relocations. 
2 For details, see individual report. 
3 Non-Federal cost. 
4 Non-Federal $670,000; Federal $1,540,000. 
1-49

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-L (Continued) LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of 
Conne- Lands 
cticut and 
Location River Type of Structure Construction Damages1 Total 
Beaver Brook, Keene, NH 170.4 Channel improvement $2,582,120 - $2,582,120 
Charlestown, NH 181 Riverbank protection 113,330 - 113,330 
Chicopee, MA 80 Wall and levee 1,434,000 $ 250,000 1,684,000 
Chicopee Falls, MA 83 Wall and levee 2,600,000 70,000 2,670,000 
East Hartford, CT 52 Wall and levee 2,135,447 271,000 2,406,447 
Folly Brook, 
Wethersfield, CT 50 Channel improvement 220,284 - 220,284 
Gardner, MA 163 Dam and levee 495,691 35,000 530,691 
Hartford, CT 52 Wall and levee 6,930,0004 1,150,000 8,080,000 
Hartford, White River, VT 216 Channel improvement 332,236 - 332,236 
Holyoke, MA 85 Wall and levee 3,418,000 150,000 3,568,000 
Huntington, MA 100 Riverbank protection 3,900 - 3,900 
Israel R., Lancaster, NH 314 Gabion overflow weir 551,606 - 551,606 
Keene, NH 167 Channel improvement 44,100 - 44,100 
Mill Brook, Brownsville, VT 200.3 Streambank stabilization 110,000 - 110,000 
Northampton, MA 94 Wall and levee 960,0005 150,000 1,110,000 
North Stratford NH 345 Slope protection 180,000 - 180,000 
Park River, CT 51 Conduit 60,150,864 1,300,000 61,450,864 
Riverdale, MA 80 Wall and levee 1,263,724 50,000 1,313,720 
Salmon R., Colchester, CT2 38 Slope protection 247,100 - 247,100 
South River, Conway, MA 107 Slope protection 133,500 - 133,500 
Springdale, MA 84 Wall and levee 700,000 57,000 757,000 
Springfield, MA 76 Wall and levee 932,0006 272,000 1,204,000 
Three Rivers, MA 98 Wall and levee 1,577,189 700,000 2,277,189 
Ware, MA 110 Channel improvement 400,000 85,000 485,000 
Weston, VT 195 Channel improvement 13,000 2,000 15,000 
West Springfield, MA 76 Wall and levee 1,789,1413 30,000 1,819,141 
West Warren, MA 111 Wall and levee 389,200 64,000 453,200 
Winsted, CT 115 Channel improvement 245,500 30,000 275,500 
1 To be borne by local interests. Also includes local interests 
portion of relocation. 
2 For details see individual report. 
3 Includes $245,000 Public Works Administration funds. 
4 Includes $835,000 Public Works Administration funds. 
* Includes $280,000 Public Works Administration funds. 
6 Includes $355,000 Public Works Administration funds. 
1-50

NEW ENGLAND DIVISION 
TABLE 1-M HOUSATONIC RIVER BASIN, CT AND MA 
(See Section 36 of Text) 
DAMS AND RESERVOIRS1 
Miles Estimated Federal Cost 
Above 
Mouth of 
Nagua- Reservoir Lands 
tuck Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages 2 Total 
Hall Meadow4 Torrington, CT 41.0 73 Rock and 8,620 $2,572,357 $1,290,0003 $3,862,357 
earthfill 
East Branch6 Torrington, CT 43.7 92 Earthfill 4,350 1,959,836 1,290,0003 3,249,836 
Thomaston Torrington, CT 30.5 142 Rock and 42,000 6,382,112 7,900,000 14,282,112 
earthfill 
Northfield Brook Torrington, CT 30.6 118 Earthfill 2,432 1,875,512 975,000 2,850,512 
Black Rock Waterbury, CT 29.0 154 Earthfill 8,700 5,223,700 2,958,600 8,182,300 
Hancock Brook Waterbury, CT 25.0 57 Earthfill 4,030 1,593,911 2,585,000 4,178,911 
Hop Brook Waterbury, CT 15.9 97 Earthfill 6,970 2,701,562 3,450,000 6,151,562 
1 For details of projects, see individual reports. 4 For last full report, see Annual Report for 1970. 
2 Includes highway, railroad, and utility relocations. 5 For last full report, see Annual Report for 1973. 
3 Includes cost of lands borne by local interests. 
LOCAL PROTECTION PROJECTS' 
Miles Estimated Cost 
Above 
Mouth of 
Housa- Lands 
tonic and 
Location River Type of Structure Construction Damages 2 Total 
Alford, Green River, MA 111.0 Earth dike and stone slope $ 41,419 $ - $ 41,419 
protection 
Ansonia-Derby, CT 13.0 Wall, levee, channel 18,266,040 1,178,000 19,444,040 
improvement and pumping 
station 
Danbury, CT 56.0 Walls, channel improvement 13,143,000 1,862,000 15,005,000 
and bridge replacement 
Derby, CT 12.0 Walls, levees and pumping 7,582,642 647,000 8,229,642 
station 
North Canaan, 83.0 Snagging and clearing project 73,865 - 73,865 
Blackberry River, CT 
Pittsfield, MA 133.0 Stone arch culvert 739,003 85,000 824,003 
Salisbury, CT 76.0 Gabionade with slope 102,800 - 102,800 
protection 
Sheffield, MA 96.0 Stone slope protection 205,608 - 205,608 
Squantz Pond, New 43.0 Timber bulkhead 116,296 - 116,296 
Fairfield, CT 
Torrington, East Branch, 51.0 Dike and channel 389,200 - 389,200 
CT improvement 
Torrington, West Branch, 52.0 Walls, dikes and channel 228,300 -228,300 
CT 
Waterbury-Watertown, 32.0 Wall, dike and channel 263,300 - 263,300 
CT
'For details of projects, see individual reports. 
2 To be borne by local interests. Includes relocations. 
1-51

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-N MERRIMACK RIVER BASIN, NH, AND MA 
(See Section 37 of Text) 
RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of 
Merri- Reservoir Lands 
mack Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages1 Total 
Franklin Falls2 Franklin, NH 118.2 140 Earthfill 154,000 $ 6,190,487 $1,760,000 $ 7,950,487 
Blackwater2 Concord, NH 118.8 75 Earthfill 46,000 766,746 553,000 1,319,746 
Hopkinton- Concord, NH 87.3 115 Earthfill 157,300 12,715,440 8,737,000 21,452,440 
Everett 2,4 
Edward Keene, NH 161.3 67 Earthfill 12,800 1,708,253 306,000 2,014,253 
MacDowell 2 
Phillips Fitchburg, MA 105.4 48 Earthfill 1,600 13,450,000 7,350,000 20,800,0003 
Whitmanville Fitchburg, MA 110.6 76 Earthfill 9,350 11,590,000 6,210,000 17,800,000 
1 Includes highway, railroad, and utility relocations. 
2 For details, see individual report. 
3 Based on "large" Phillips plan which would eliminate 
Nookagee Lake. 
4 Substituted for Bennington and Beards Brook. Distance 
and height are for Everett Dam. Distance and height for Hopkinton 
Dam are 118 miles and 76 feet, respectively. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of 
Merri- Lands 
mack and 
Location River Type of Structure Construction Damages' Total 
Amesbury, Powwow and 3.0 Wall and reventment $ 132,113 $ - $ 132,113 
Merrimack Rivers, MA2 
Nashua, NH2 55.0 Wall and levee 270,000 3,000 273,0004 
Lowell, MA2 39.0 Wall and levee 490,6006 90,000 580,600 
North Nashua River, MA2,3 100.5 Channel improvement 3,241,421 - 3,241,421 
Saxonville, MA2 69.0 Wall, levee, channel 4,218,700 530,000 4,748,700 
1 To be borne by local interests. 
2 Project completed. 
3 Excludes $1,370,000 Public Works Administration funds 
expended on Fitchburg, MA. 
4 Excludes $15,000 expended from Contributed Funds. 
5 Excludes $794,374 Public Works Administration funds. 
1-52

NEW ENGLAND DIVISION 
TABLE 1-0 THAMES RIVER BASIN, CT, RI AND MA 
(See Section 45 of Text) 
RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of Reservoir Lands 
Thames Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
Hodges Village2 Webster, MA 74.5 55 Earthfill 13,000 $1,317,268 $3,144,000 $4,461,268 
Buffumville2 Webster, MA 74.4 66 Earthfill 12,700 2,157,603 841,000 2,998,603 
East Brimfield2 Southbridge, MA 82.8 55 Earthfill 30,000 1,337,043 5,720,000 7,057,043 
Westville2 Southbridge, MA 75.2 80 Earthfill 11,000 2,284,683 3,400,000 5,684,683 
West Thompson2 Putman, CT 59.3 70 Earthfill 25,600 5,036,220 1,965,000 7,001,220 
Mansfield Hollow2 Willimantic, CT 40.0 70 Earthfill 52,000 4,107,164 2,340,000 6,447,164 
1 Includes highway, railroad, and utility relocations. 
2 For details, see individual report. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of Lands 
Thames and 
Location River Type of Structure Construction Damages' Total 
Norwich, CT 15.0 Channel improvements $1,209,000 $72,000 $1:281,000 
1 Borne by local interests. 
TABLE 1-P BOSTON HARBOR, MA 
Total Federal Cost for Existing Project to September 1989 
Funds New Work Maintenance Total 
Regular $21,881,851 $9,194,920 $31,076,771 
Public Works 1,030,806 - 1,030,806 
Emergency Relief 935,303 - 935,303 
$23,847,960 $9,194,9201 $33,042,880 
1 Excludes $17,767 contributed funds. 
1-53

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 1-Q RECONNAISSANCE AND CONDITION SURVEYS 
Date Survey Date Survey 
Project Conducted Prqject Conducted 
Connecticut 
Clinton Harbor 
Connecticut River (Brownstone Bar) 
Niantic River 
North Cove 
Norwalk Harbor 
Stony Creek 
Rhode Island 
Sakonnet Harbor 
Maine 
Bass Harbor 
Bunker Harbor 
Corea Harbor 
Kennebec River 
Little Harbor 
New Harbor 
Pepperell Cove 
South Bristol 
Southwest Harbor 
Tenants Harbor 
Wells Harbor 
Winter Harbor 
York Harbor 
Massachusetts 
Jul 1989 Andrews River 
Sep 1989 Chatham Harbor 
Oct 1988 Falmouth Harbor 
Apr 1989 Green Harbor 
Dec 1988 Hyannis Harbor 
Jan 1989 Merrimack River 
Mystic River 
Newburyport 
Feb 1989 Onset Bay 
Owls Head 
Scituate Harbor 
Mar 1989 
Mar 1989 
Oct 1988 
Apr 1989 
Mar 1989 
Sep 1989 
May 1989 
Mar 1989 
Aug 1989 
May 1989 
Sep 1989 
Oct 1988 
Mar 1989 
Jul 1989 
Jul 1989 
May 1989 
Feb/Apr 1989 
Apr/Aug 1989 
Aug 1989 
Nov 1988 
Apr 1989 
Jul 1989 
May 1989 
Jun 1989 
New Hampshire 
Hampton Harbor 
Piscataqua River (disposal area) 
Piscataqua River (Simplex Reach) 
Portsmouth Harbor (Back Channel) 
Rye Harbor 
Apr 1989 
Nov 1988 
Feb 1989 
Feb 1989 
Jan 1989 
Major activities under the Dredged Material Management Program included in the Providence River and New Haven 
programs for fiscal year 1989 were: (1) monitoring surveys at the Portland, New London, Rockland and, Foul Area disposal 
sites; (2) completion of the site designation reports of the Cape Arundel disposal site; and (3) maintenance, replacement, 
and repositioning of disposal site buoys. Additionally, several monitoring study reports were completed and a public 
symposium was held. Total cost of contracts was $251,000 and $189,000 for Providence River and New Haven, respectively. 
Labor costs of $81,000 for program management, sampling and testing, and environmental analysis were incurred for 
New Haven in fiscal year 1989. 
1-54

NEW YORK, N.Y. DISTRICT * 
This district comprises western Vermont, small portions of 
western Massachusetts and Connecticut, eastern New York 
including Long Island, and northeastern New Jersey, 
embraced in the drainage basins tributary to Lake Champlain 
and St. Lawrence River system east thereof and to the Atlantic 
Ocean from New York-Connecticut State Line to, but not 
including Manasquan Inlet, N.J. It exercises jurisdiction, 
however, over all matters pertaining to improvement of Great 
Lakes to Hudson River waterway. Under the direction of the 
Secretary of the Army, the District Engineer, as Supervisor of 
New York Harbor, also exercises jurisdiction under the laws 
enacted for the preservation of the tidal waters of New York 
Harbor, its adjacent or tributary waters, and the waters of 
Long Island Sound. 
IMPROVEMENTS 
I. Aquatic Plant Control ............................. 2-2 
2. Bay Ridge-Red Hook Channels, N.Y ........... 2-2 
3. East Chester Creek, N.Y .......................... 2-2 
4. East Rockaway Inlet, N.Y ........................ 2-3 
5. Fire Island to Jones Inlet, N.Y..................... 2-3 
6. Hempstead Harbor, N.Y. .... ............... 2-4 
7. Hudson River, N.Y................................. 2-4 
8. Hudson River Channel, N.Y. & N.J .............. 2-5 
9. Kill Van Kull-Newark Bay, N.J. & N.Y........... 2-6 
10. Long Island Intracoastal W/W, N.Y ............. 2-6 
11. Moriches Iilet, N.Y ............................... 2-6 
12. Narrows of Lake Champlain, N.Y ................ 2-7 
13. Newark Bay, Hackensack & 
Passaic Rivers, N.J ............................... 2-7 
14. New York and New Jersey Channels .............. 2-8 
15. New York Harbor-Collection and 
Removal of Drift .................................. 2-9 
16. New York Harbor-Entrance Channels 
and Anchorage Areas ............................. 2-9 
17. Portchester Harbor, N.Y..........................2-10 
18. Rondout Harbor, N.Y ............................ 2-10 
19. Supervisor of New York Harbor ................. 2-11 
20. Reconnaissance and Condition Surveys .......... 2-11 
21. Other authorized navigation projects.............2-11 
22. Navigation work under special authorization ..... 2-11 
Beach Erosion Control 
23. East Rockaway Inlet to Rockaway Inlet 
and Jamaica Bay, N.Y...........................2-12 
24. Sandy Hook to Barnegat Inlet, N.J............... 2-12 
25. Other Authorized Beach erosion 
control projects ................................... 2-13 
26. Beach erosion control work under 
special authorization ............................. 2-13 
27. Ardsley, N.Y.......................................2-13 
28. Liberty State Park Levee and Seawall, N.J........2-13 
29. Passaic River Basin, N.J. & N.Y..................2-14 
30. Inspection of completed flood control projects ... 2-15 
31. Other authorized flood control projects .......... 2-15 
32. Flood control work under 
special authorization ............................. 2-15 
33. Emergency streambank and shoreline 
protection under special authorization ........... 2-15 
34. 
35. 
36. 
General Investigations 
Surveys ........................................... 2-15 
Collection and study of basic data ................ 2-15 
Deauthorized projects.............................2-15 
Tables 
Table 2-A Cost & Financial Statement...............2-16 
Table 2-B Authorizing Legislation ................... 2-20 
Table 2-C Hudson River, N.Y. Features of 
Lock and Dam Included in 
Existing Project ........................... 2-25 
Table 2-E Supervisor of New York Harbor 
Statement of Activities .................... 2-25 
Table 2-F Reconnaissance & Condition Surveys...... 2-26 
Table 2-G Other Authorized Navigation Projects..... 2-27 
Table 2-41 Other Authorized Beach 
Erosion Control............................ 2-29 
Table 2-1 Other Authorized Flood 
Control Projects .......................... 2-29 
Table 2-J Surveys ..................................... 2-30 
Table 2-L Costs for Flood Plain Management 
Services..................... ................ 2-30 
Table 2-M Deauthorized Projects .................... 2-30 
Table 2-N Section 107 Reconnaissance Reports ...... 2-31 
Table 2-0 Section 103 Report ........................ 2-32 
Table 2-P Section 205 Projects ....................... 2-32 
Table 2-Q Section 14 Reports 
and Plans and Specs ...................... 2-32 
Navigation Page Flood Control Page

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
1. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in New York District. 
Existing Project. Provides for control and progressive 
eradication of water chestnut, Eurasian water milfoil, and 
other obnoxious aquatic plant growths from the navigable 
waters, tributary streams, connecting channels, and other 
allied waters of the United States, in the combined interest of 
navigation, flood control, drainage, agriculture, fish and 
wildlife conservation, public health, and related purposes, 
including continued research for development of the most 
effective and economic control measures. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. Local interests were required to provide 
30 percent of the cost of the program except as modified by 
1962 River and Harbor Act and agree to hold the United 
States free from damages. The Water Resources Development 
Act of 1986 changed the local responsibility from 30% to 
50%. In FY 87 the States involved in the program were 
permitted to keep the cost sharing at 30% by order of the 
Secretary of the Army. Starting FY 88, however, local sponsors 
contributed 50% of the costs. 
Operations and results during period. FY 1989 has been the 
eighth year of a control program started in FY 1982 for the 
removal of nuisance aquatic plants in Lake Champlain. This 
work has performed for the removal of water chestnut in the 
southern part of the lake at a cost of $121,300. 
Condition as of September 30. Reconnaissance report covering 
the aquatic plant problems of the North Atlantic Division 
areas was completed in August 1967. Planning for the 
water chestnut control in the Hudson-Mohawk basin was 
completed by the New York District, contracts for $189,363 
accomplished during FY 1970 through FY 1976. The General 
Design Memorandum for this program was completed in 
March 1982 by the State of Vermont. The total Federal cost 
of this control program to date is $1,490,650. 
2. BAY RIDGE AND RED HOOK 
CHANNELS, N.Y. 
Location. These channels lie along cast shore of Upper Bay, 
New York Harbor and, with Buttermilk Channel, form an 
easterly channel along Brooklyn waterfront from the Narrows 
to East River. (See National Ocean Survey Charts 12327 
and 12334). 
Previous projects. For details see Annual Reports for 1915 
and 1938, pages 1768 and 195, respectively. 
Existing projects. A channel 1,200 feet wide and 40 feet 
deep at mean low water from the Narrows to Bay Ridge 
Avenue, Brooklyn, thence 1,750 feet wide to junction of Bay 
Ridge and Red Hook Channels, thence 1,200 feet wide 
through Red Hook Channel to junction with Buttermilk 
Channel and a channel of same depth extending into Gowanus 
Bay from junction of Bay Ridge Channel with Red Hook 
Channel, narrowing uniformly in width to about 500 feet at 
28th Street, Brooklyn. Section included in project is 4 miles 
long. Mean tidal range, 4.7 feet; mean range of spring tides, 
5.6 feet; irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below mean low water up to 5.2 
feet above mean high water. New work for completed project 
cost $4,277,197 exclusive of amounts expended on previous 
projects. (See Table 2-B for Authorizing Legislation). 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, revised 1978. 
Vol. 2 
Operations and results during period. A contract for the 
removal of all material except ledge rock lying above the 
plane of 40 feet below mean low water in Bay Ridge and Red 
Hook Channels, N.Y. was awarded on I May 1989. Work 
commenced on 30 July 1989 and was completed on 18 September 
1989. A total of 801,000 cubic yards of material was 
removed for a total project cost of $3,090,241. 
Condition as of September 30. Work under existing project 
was commenced March 1901 and completed June 1940. 
3. EAST CHESTER CREEK, N.Y. 
Location. This creek, also known as Hutchinson River, is a 
small tidal stream emptying into East Chester Bay, an indentation 
in north shore of Long Island Sound immediately 
north of Throgs Neck, 12 miles southwest of Connecticut 
State line and 21 miles by water northeast of the Battery, New 
York City. (See Coast and Geodetic Survey Chart 12366). 
Previous projects. For details see Annual Reports for 1915, 
1929, 1938 and 1949, pages 1761, 167, 163, and 208, 
respectively. 
Existing project. A channel 10 feet deep at mean low water 
and generally 150 feet wide from Long Island Sound through 
East Chester Bay to a point 700 feet below Boston Post Road 
Bridge, and thence 70 feet wide extending to a point where the 
creek divides into a Y, thence approximately 1,000 feet into 
east branch of the Y and approximately 500 feet into west 
branch of the Y; a passing basin south of Boston Post Road 
Bridge; widening channel at Boston Post Road Bridge; and 
construction of a check dam at head of navigation. Section 
included in project is 5 miles. Mean tidal range, 7.3 feet in the 
estuary; mean range of spring tides, 8.6 feet; irregular fluctuations 
due to wind and atmospheric pressure vary from 3.9 feet 
below mean low water up to 8.1 feet above mean high water. 
Estimate of cost for new work is $2,550,000 (October 1976) 
exclusive of amounts expended on previous projects and 
inclusive of an estimated $40,000 non-Federal cost for lowering 
utilities, (See Table 2-B for authorizing legislation.) 
2-2

NEW YORK, N.Y. DISTRICT 
Local cooperation. River and Harbor Act of May 17, 1950, 
provides that local interests furnish lands, rights-of-way, and 
suitable areas for disposal of dredged material during construction 
and future maintenance, and hold the United states 
free from damages. City of New York has complied with 
requirements. Assurances are yet to be received from other 
local interests concerned with improvement. 
Terminal facilities. See Port Series No. 5, revised 1965, 
Vol. 2, Part 2. 
Operations and results during period. A contract for the 
removal of all material except ledge rock lying above the 
plane of 8 feet below mean low water in East Chester Creek, 
N.Y. was awarded on 21 April 1989. Work commenced on 28 
September 1989 and was completed on 3 November 1989. A 
total of 29,237 cubic yards of material was removed fora total 
project cost of $972,107. 
Condition as of September 30. No work has been accomplished 
under the existing project. Work under the 1930 project 
was completed in August 1941. 
4. EAST ROCKAWAY INLET, N.Y. 
Location. On south shore of Long Island between main 
body of island and western end of Long Beach. It is 10 miles 
east of Rockaway Inlet and about 27 miles by water south and 
east from the Battery, New York City. (See National Ocean 
Survey Chart 12353.) 
Existing project. A channel 12 feet deep at mean low water 
and 250 feet wide from 12-foot contour in Long Beach Channel 
protected by a jetty. Mean tidal range, 4.3 feet; mean range 
of spring tides, 5.2 feet; irregular fluctuations due to wind and 
atmospheric pressure vary from 3.9 feet below mean low 
water up to 5.6 feet above mean high water. New work for 
completed project cost $603,969, including $100,000 contributed 
funds (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with. 
Terminal facilities. There are 39 terminals in Oceanside, 
Island Park, Long Beach, and East Rockaway. Nine of these 
are oil terminals, one of which has a railroad spur. Other 
terminals are repair and mooring docks with a berthage of 
7,655 feet. Of these, 21 have marine railways and I has 
mechanical-handling facilities. There are public wharves at 
East Rockaway and Woodmere. Waterfront on north side of 
Long Beach has been bulkheaded. Facilities are considered 
adequate for existing commerce. 
Operations and results during period. A contract for the 
removal of all material except ledge rock lying above the 
plane of 14 feet below mean low water in East Rockaway 
Inlet, N.Y. was awarded on 19 April 1989. Work commenced 
on 20 April 1989 and was completed on 29 May 1989. A total 
of 225,000 cubic yards of material was removed for a total 
project cost of $855,866. 
Condition as of September 30. Work under existing project 
began February 1933 and is 100 percent complete. East jetty, 
4,250 feet long was completed in July 1934. Project channel 
was completed in May 1935. 
5. FIRE ISLAND TO JONES INLET, N.Y. 
Location. On south shore of Long Island, about 50 miles by 
water south and east of the Battery, New York City. Fire 
Island Inlet is the main entrance into Great South Bay from 
the Atlantic Ocean. (See National Ocean Survey Chart 
12352.) 
Existing project. A jetty at Fire Island Inlet extending 
generally southwest and south for 5,000 feet from high 
ground on Democrat Point at the west end of Fire Island and 
a channel generally parallel to the jetty 18 feet deep and 500 
feet wide from a littoral reservoir (sediment trap) in the ocean 
to deep water in the inlet. Mean tidal ranges at the ocean and 
inlet ends of Democrat Point are 4.1 feet and 2.4 feet respectively. 
Irregular fluctuations due to wind and atmospheric 
pressure vary from 2.5 feet below mean low water up to 6.2 
feet above mean high water on the ocean side. (See Table 2-B 
for Authorizing Legislation.) 
Local cooperation. Requires cost sharing and lands, easements 
and rights-of-way. 
Terminal facilities. None within the area immediately adjacent 
to the Federal improvements. 
Operations and results during period. An engineering and 
design effort for Fire Island Inlet, N.Y. was conducted at a 
cost of $30,120 during this period in anticipation of dredging 
in FY90. The contract for the removal of 994,568 cubic yards 
of sand lying above the plane of 14 feet below mean low water 
in Fire Island Inlet was awarded on 29 September 1988. Work 
commenced on 17 October 1988 and was completed on 9 May 
1989. The total cost of the work completed during the period 
was $6,567,180. 
Condition as of September 30. Dredging under the existing 
project was commenced in late 1973. As a result of three 
consecutive dredging operations completed in 1977, the project 
channel was brought to the approximate authorized 
dimension at that time. Due to local concerns about inlet 
dredging and erosion at Oak Beach, maintenance had been 
deferred since 1979 which has allowed the complete shoaling 
of the authorized project channel. To facilitate navigation in 
this period the existing natural channel was dredged in FY 
1985 and in FY 1987. In FY 1987 sand was deposited offshore 
of Gilgo Beach by hopper dredge. 422,460 cy was dredged at a 
cost of $882,000 operations and maintenance funds. O&M 
funds were also used during FY 1987 and 1988 to make 
repairs to the inner portion of the jetty. 
In March 1988 the District recommended a plan to maintain 
a realigned channel in the vicinity of the natural channel 
2-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
toa depth of 14 feet (plus 2 feet of allowable overdepth) and a 
width of 450 feet. The plan also recommended placement of 
the dredged material along Gilgo Beach for shore protection 
purposes. The recommended plan was approved by the 
Assistant Secretary of the Army for Civil Works on 2 August 
1988. 
6. HEMPSTEAD HARBOR, N.Y. 
Location. On the north shore of Long Island, 25 miles by 
water northeast of the Battery, New York City, and 13 miles 
southwest of Stamford Harbor, Conn. (Chart No. 12366.) 
Previous project. For details see page 165, Annual Report 
for 1953. 
Existing project. (a) a channel 13 feet at mean low water 
and 150 feet wide from deep water in the harbor to North 
Hempstead Turnpike Viaduct, a distance of 2.1 miles; (b) 
thence 6 feet at mean low water and 50-80 feet wide to head of 
navigation, a distance of 0.2 mile; and (c) a turning basin off 
west side of channel north of Viaduct 9 feet deep at mean low 
water, 190 in net width and 470 feet in maximum length. 
Dredging the 13-foot channel is subject to the condition that 
no work shall be done by the United States within 50 feet of 
any established pierhead line, wharf or other structure. Section 
included in project is about 2.3 miles long. Mean tidal 
range, 7.1 feet; mean range of spring tides, 8.4 feet; irregular 
fluctuations due to wind and barometric pressure vary from 
3.6 feet below mean low water up to 8.3 feet above mean high 
water. The present work in Hempstead Harbor involves removal 
of derelict barges and other debris in the shallow waters 
along the shore line. Estimated cost is $4,400,00 Federal funds 
and $2,200,000 non-Federal. 
Local cooperation. Complied with except for provisions of 
River and Harbor Act of 1968, which require local interests to 
furnish lands, easements and rights-of-way for construction 
and maintenance, and for construction and maintenance of 
aids to navigation; hold the United States free from damages; 
provide depths in berthing areas and access channels commensurate 
with related project depths; and make necessary 
utility or other relocations or alterations. Local interests must 
pay 33% of the construction cost of the barge removal project. 
A local cooperation agreement will be signed during FY 1990. 
Operations and results during fiscal year. The final GDM 
will be completed early in 1990. Plans and specs are also being 
prepared leading to a projected construction award in Sept. 
1990. N.Y. State has approved the required cost sharing, but 
the work will be contingent on the availability of the State 
funding. 
Condition at end of fiscal year. Work under the existing 
project was commenced March 1912 and is about 16% completed. 
The 6-foot channel was completed October 1912. 
7. HUDSON RIVER, N.Y. 
Location. Originates in Adirondack Mountains, about 250 
miles in a direct line and 315 miles along its course from the 
Battery, New York City, and flows generally southerly into 
New York Bay. Section under improvement extends from 
New York City about 156 miles to Waterford. (See National 
Ocean Survey Charts 12335, 12341, 12343, 12347, 12348, and 
14786.) 
Previous projects. For details see Annual Reports for 1915 
and 1938, pages 164 and 226, respectively. 
Existing projects. A channel 600 feet wide from New York 
City to Kingston, and thence 400 feet wide to Albany, with 
widening at bends, a turning basin 700 feet wide and 1,200 feet 
long at Albany, and 2 anchorages, 1 near Hudson and I near 
Stuyvesant, each 400 feet wide and an average length of 2,400 
feet; all with depths of 32 feet in soft material and 34 feet in 
rock to 2,200 feet south of the Mall Bridge; thence 27 feet deep 
and 400 feet wide to 900 feet south of Mall Bridge, thence 14 
feet deep at lower low water and generally 400 feet wide to 
Federal lock at Troy; and thence of same depth and 200 feet 
wide to southern limit of State barge canal at Waterford; and 
removal of State dam at Troy and construction of a lock and 
dam about 2.5 miles below Waterford. Channel is to be 
formed by dredging and rock excavation, and maintained by 
dredging and constructing new, and raising and repairing old, 
longitudinal dikes, built partly under previous projects and 
partly by the State of New York. 
In the tidal section below the Federal dam at Troy, the 
assumed lowest low water plane downstream to Albany is 3 
feet below mean sea level. Mean tidal range is about 5 feet 
below the dam and about 4.9 feet at Albany. The normal pool 
level above the dam from Troy to Waterford is 14.3 feet above 
mean sea level, with the mean range of pool level in seasons of 
moderate rains being 2.2 feet. (See Table 2-C for features of 
lock and dam included in existing project.) New work for 
completed project cost $39,050,019 exclusive of amounts of 
expended on previous projects. Widening to form harbors at 
Albany and Troy, N.Y., to 12 feet deep at a cost of $522,000 
(1954) and completion of 27-foot channel at Albany at a cost 
of $642,000 (1957) was placed in deferred for restudy category. 
All three features of work are excluded from foregoing 
description of existing project and cost estimate. Construction 
of mooring facilities has been authorized. (See Table 2-B 
for Authorizing Legislation.) 
Local cooperation. Complied with except that local interests 
must furnish suitable soil disposal areas for future maintenance 
as required. 
Terminal facilities. See Port Series No. 6 
Operations and results during period. A contract in the 
amount of $2,449,700 was awarded on September 29, 1988 to 
2-4

NEW YORK, N.Y. DISTRICT 
American Dredging Company for removal of approximately 
390,000 cubic yards of material from the Federal channel. 
Dredging operations associated with the Contract were completed 
during the first quarter of FY 1989, however, due to ice 
conditions forming earlier than anticipated, the total Hudson 
River Contract dredging quantity was reduced to 239,612 
cubic yards at a total Hudson River dredging cost of 
$1,463,558. Operations and maintenance in the amount of 
$711,432 was expended on engineering and design, supervision 
and administration and surveys for contract work during 
FY 1989 for this project. 
Government plant and hired labor were employed through 
the fiscal year in the removal of stumps, snags, and other 
obstructions which constituted a potential hazards to navigation 
at a cost of $201,096 for maintenance in FY 1989. 
Government plant and hired labor were employed through 
the fiscal year performing dredging and project condition 
surveys at a cost of $178,807 for maintenance in FY 1989. 
Government plant and hired labor were employed throughout 
the fiscal year with operation and maintenance of the 
Troy Lock and Dam including the associated buildings and 
grounds. Operation of the Lock was suspended for the 1988 
navigation season on November 28, 1988 and was resumed 
for the 1989 navigation season on May 1, 1989. Total cost 
incurrred for the operation and maintenance of the Troy 
Lock and Dam and the associated building and grounds was 
$483,686 for FY 1989. In addition, a continuing contract in 
the amount of $1,738,025 was awarded to the Hull Corporation 
on September 30, 1988 to perform Interim Repairs to the 
Troy Lock and Dam. These repairs are required to insure 
continued operability and safety of the Troy Lock and Dam. 
Funds in the amount of $1,200,000 were expended on work 
performed under the continuing contract in FY 1989. 
Condition as of September 30. Work under existing project 
began in July 1910 and was substantially completed in 
November 1965. New lock and dam at Troy, removal of dam 
at Troy and construction of 15,545 linear feet of dikes also are 
complete. In reconstruction of old dikes 39,676 linear feet 
were raised to adopted crest height. Channel from New York 
City to Albany is complete to a depth of 32 feet except for the 
1,500 linear-foot section at the northern end of the 32-foot 
project which has never been dredged to project depth. Additionally, 
the 1,300 linear feet of the 27-foot project remains 
undredged. Channel from Albany to Waterford is complete 
to a depth of 14 feet except for a small part of the widening to 
form a harbor at Troy. Work remaining under the project 
consists of completion of the 12-foot harbor at Troy and 
dredging the 27-foot and the remainder of the 32-foot channels 
at Albany which are not deemed necessary at this time; 
and reconstruction of dikes. 
8. HUDSON RIVER CHANNEL, N.Y. & N.J. 
Location. Hudson River empties into Upper Bay of New 
York Harbor at the Battery, New York City. Section included 
under this title extends from deep water in Upper New York 
Bay about 14.5 miles to just north of Harlem River (Spuyten 
Duyvil Creek). 
Previous projects. For details see Annual Report for 1915 
and 1938, pages 1765, and 213 respectively. 
Existing project. A channel 48 feet deep and 2,000 feet 
wide, suitably widened at bends from West 59th Street, Manhattan, 
to West 40th Street, thence 45 feet deep of same width 
to deep water in Upper Bay; a channel 40 feet deep to full 
width of river extending from northline of 59th Street to 
south side of Little Basin, and thence a channel of same depth 
to deep water in Upper New York Bay off Ellis Island, substantially 
as shown on maps in H. Doc. 309, 72d Cong., I1st 
sees., subject to provision that no dredging be done under 
project within 50 feet of pierhead lines; a channel 750 feet wide 
and 30 feet deepalong Weehawken-Edgewater waterfront; 
removal of a shoal on New York side between West 59th and 
West 61st Streets to a depth of 40 feet; and removal of an 
obstruction north of mouth of Spuyten Duyvil Creek to depth 
surrounding river bottom. Channel included in project is 
about II miles long. Plane of reference is mean low water. 
Mean tidal range at the Battery, 4.4 feet, and West 129th 
Street, 4.1 feet; mean range of spring tides, 5.3 and 4.9 feet 
respectively; irregular fluctuations due to wind and atmospheric 
pressure vary from 3.8 feet below mean low water at 
the Battery up to 6.2 feet above mean high water and at West 
129th Street from 3.6 feet below mean low water up to 5.3 feet 
above mean high water. (See Table 2-B for Authorizing 
Legislation.) 
Operations and results during period. A contract for the 
removal of all material except ledge rock lying above the 
plane of 40 feet below mean low water in Hudson River 
Channel, N.Y. was awarded on 7 April 89. Work commenced 
on 13 April 1989and was completed on 24 April 1989. A total 
of approximately 40,000 cubic yards of material was removed 
for a total project cost of $294.998. 
Conditions as of September 30. Work under existing project 
as commenced April 1913 and completed September 
1952. Widening and deepening Weehawken-Edgewater 
Channel to project dimensions was completed in August 
1937. Widening 40-foot channel for full width of river from 
Ellis Island to West 59th Street, Manhattan, was completed in 
March 1939. Widening 48-foot project to full project width of 
2,000 feet from West 40th Street to West 59th Street was 
completed in November 1950. Deepening 45-foot channel for 
a width of 2,000 feet from Upper Bay to West 40th Street was 
completed to project dimensions in September 1952. 
2-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
9. KILL VAN KULL - NEWARK BAY 
CHANNEL, N.J. & N.Y. 
Location. The project includes Kill Van Kull connecting 
upper New York Bay with Newark Bay, and channels in lower 
Newark Bay serving Port Newark and Elizabeth Marine 
Terminal. These terminals are located on the west shore of 
Newark Bay. (See National Ocean Survey Chart 12333.) 
Existing project. Deepening the existing Kill Van Kull 
channel and channels in lower Newark Bay, including turning 
and maneuvering areas, as well as deepening the Elizabeth 
and Port Newark channels. The deepening to be done from 
the existing 35 foot depth incrementally to 40 feet and then 44 
feet. The Federal cost of construction is estimated at 
$270,800,000 with an additional 177,340,000 to be contributed 
by local interests (Oct. 89 P.L.). 
Local cooperation. The Port Authority of New York and 
New Jersey, the local cooperating agency, has entered into a 
local cooperation agreement with the Government which was 
executed on 30 May 1986. A supplemental agreement was 
executed on 21 May 1987. 
Terminal facilities. See Port Series No. 5, Vol. 2. 
Operations and results during period, and condition as of 
Sept. 30. Stage I, channel deepening to 40 feet in five contracts, 
is underway. Contract No. 1, awarded in June 1987, is 
completed. Contract No. 2 was awarded in July 1988. Contract 
No. 3 was awarded in Sept. 1988 after a mistake in bid 
claim by the initial low bidder caused a delay in the award 
procedure. Contract No. 4 is planned to remove rock and 
hard material in the Kill Van Kull and Newark Bay. This 
work will be awarded in two contracts, 4A and 4B with the 
first award scheduled for October 1990. Contract No. 5 was 
awarded in May 1988 and was completed in July 1989. 
10. LONG ISLAND INTRACOASTAL 
WATERWAY, N.Y. 
Location. Extends from East Rockaway Inlet, on the south 
side of Long Island, to Great Peconic Bay at the eastern end of 
Long Island. Section included under this project extends 
from Great South Bay opposite Patchogue to the South end 
of Shinnecock Canal. (See National Ocean Survey Chart 12352.) 
Existing project. A channel 100 feet wide and 6 feet deep at 
mean low water from the federally improved channel in Great 
South Bay, opposite Patchogue to south end of Shinnecock 
Canal. Section included in project is 34 miles long. Mean tidal 
range varies from I foot in Shinnecock Bay to 0.7 foot in 
Patchogue Bay; mean range of spring tides varies from 1.2 
feet to 0.8 foot; irregular fluctuations due to wind and atmospheric 
pressure vary from 1.8 feet below mean low water to 12 
feet above mean high water. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except local interest, 
must furnish suitable spoil-disposal areas for future maintenance 
as required. 
Terminal facilities. There are 17 boat repair and storage 
yards within the areas immediately adjacent to the Federal 
improvement. There is ample room for expansion and development 
of terminals when future commerce warrants. 
Operations and results during period. An engineering and 
design effort for Long Island Intracoastal Waterway, N.Y. 
was conducted during this period in anticipation dredging in 
FY90. The total cost of the work was $71,296. 
Condition as of September 30. Original work under the 
existing project was commenced October 1939 and completed 
September 1940. 
11. MORICHES INLET, N.Y. 
Location. On the south shore of Long Island, about 80 
miles by water east of the Battery, New York City. It is an 
opening through the narrow sandy barrier beach on the south 
shore of Long Island which separates the Atlantic Ocean from 
a series of interconnected bays. (See National Ocean Survey 
Chart 12352.) 
Existing project. Provides for a channel, 10 feet deep at 
mean low water and 200 feet wide extending from that depth 
in the Atlantic Ocean to Moriches Bay, a distance of 0.7 mile; 
thence a channel 6 feet deep and 100 feet wide to the Long 
Island Intracoastal Waterway, a distance of 1. I miles; rehabilitation 
of the existing jetties and revetments. Estimate of cost 
of work is $12,989,000 (October 1988 P.L.) including $50,000 
from Coast Guard and $4,544,000 to be contributed by local 
interests. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. In accordance with the project authorization, 
local interests are required to furnish all easements, 
rights-of-way including relocations that are necessary for 
improvements at an overall 35% cost sharing basis. The 
annual Operations and Maintenance cost is estimated to be 
$1,860,000 of which the local share is 50% or $930,000 per 
year. An Agreement of Local Cooperation was executed on 
30 June 1986. The New York State Department of Environmental 
Conservation is the local sponsor. 
Terminal facilities. No terminals are within the area immediately 
adjacent to the Federal improvement. However, several 
yacht clubs, boatyards, and public wharfs and landings, 
and numerous private landings are located in Moriches Bay. 
The yacht clubs and boatyards have equipment for servicing 
boats. There are boat basins open to the public. The facilities 
existing in the bay are considered adequate for present and 
probable future needs under present conditions of Moriches 
Inlet. There is room for expansion should future commerce 
warrant. 
2-6

NEW YORK, N.Y. DISTRICT 
Operations and results during period. Work was initiated 
on rehabilitation of the east jetty. After this is complete 
similar work is scheduled for the west jetty. Present plans call 
for award of a contract for channel dredging in mid 1990 but 
this will be contingent on cost sharing by the State. 
Condition as of September 30. Pre-construction planning 
resumed in October 1977. Coordination continued with Federal, 
State and local agencies on current problems and need 
for all project purposes (i.e., navigation; beach erosion control; 
water quality improvement). A post authorization 
change was approved in September 1983 to allow construction 
of each project purpose separately which clarified 
authority to defer all purposes except navigation. In January 
1980, a breach occurred adjacent to the eastern jetty. Emergency 
funds ($11.3 million) were authorized under the authority 
of PL84-99 to close the breach. About 1,185,000 yards of 
sand fill were used to effect closure of the breach by March 
1981. 
12. NARROWS OF LAKE CHAMPLAIN, 
N.Y.& VT. 
Location. This waterway, 37 miles long, comprises southern 
end of Lake Champlain and extends from Whitehall to 
Crown Point, N.Y. at southern extremity of lake, northerly to 
Benson Landing, Vt. (See N.O.S. Chart 14784). 
Previous projects. For details, see Annual Reports for 
1931, and 1963, pages 256 and 177, respectively. 
Existing project. A channel extending from Whitehall, 
N.Y. at head of Lake Champlain to Benson Landing, 12 feet 
deep at low lake level and generally 150 feet wide, and installation 
of fender booms at Putts Rock, Putts Leap, Narrows 
near Dresden, Pulpit Point and Cedar Mountain. Reference 
plane of low lake level is 93 feet above mean sea level. Section 
included in project is about 13.5 miles. Usual annual variation 
of lake level is 5.8 feet and extreme variation varies from 0.6 
foot below up to 8.8 feet above low lake level. 
Widening channel throughout its entire length to project 
width of 200feet is inactive and excluded from foregoing 
description of existing project and cost estimate. (See Table 
2-B for Authorizing Legislation. 
Local cooperation. None required. 
Operations and results during period. Government plant 
and hired labor were employed intermittently during the fiscal 
year in removal of stumps and snags that posed a potential 
hazard to navigation at a cost of $23,202. Government plant 
and hired labor were employed in replacing deteriorated 
fender booms at a cost of $8,648. Operations and maintenance 
funds in the amount of $23,403 were expended in FY 
1989 on preliminary engineering and design, and surveys for 
future maintenance dredging. 
Condition as of September 30. Work under the existing 
project was commenced June 1919 and is about 77 percent 
complete. A channel 12 feet deep at low lake level and least 
width of 150 feet has been excavated throughout the length of 
the improvement, except at the Elbow, where the width is 110 
feet. Fender booms have been placed at the elbow. (Putts 
Leap and Putts Rock.) 
13. NEWARK BAY, HACKENSACK 
AND PASSAIC RIVERS, N.J. 
Location. Newark Bay is an estuary about 1.25 miles wide 
and 6 miles long extending southerly from confluence of 
Hackensack and Passaic Rivers to New York and New Jersey 
Channels. Hackensack River rises near Haverstraw, Rockland 
County, N.Y. and flows about 45 miles into Newark Bay. 
Passaic River rises in highlands of northeastern New Jersey 
and flow; about 80 miles into Newark Bay. (See National 
Ocean Survey Charts 12333 and 12337.) 
Previous projects. For details see 1926 Annual Report, 
pages 265 and 266; and Annual Reports for 1929, 1938, 1954, 
and 1976, pages 301, 244, 134, and 2-11 respectively. 
Existing project. A main channel 700 feet wide to the 
branch channel to Port Newark, thence 500 feet wide to a 
turning basin 1,300 feet long and 900 feet wide at the junction 
of the Hackensack and Passaic River channels, length about 
4.7 miles; a maneuvering area south of the removed Central 
Railroad of New Jersey Bridge 2,200 feet long and 300 feet 
wide with depths of 38 feet in the south half and 35 feet in the 
north half; a combined bend cutoff and maneuvering area at 
the south side of the junction with Elizabeth branch channel; 
and widening bends at the Kill Van Kull and Port Newark 
Channels. (Authorized depth 35 feet except as noted above.) 
(adopted 1966.); including a triangular area east of Shooters 
Island with a depth of 37 feet. 
At Port Newark - A branch channel 800 feet wide leading 
to an inshore channel 400 feet wide 1.6 miles (adopted 1945). 
Authorized depth 37 feet in rock and 35 feet in soft material; a 
pierhead channel 200 feet wide along the east bulkhead 
between the Port Newark and Elizabeth branch channels, 
length 4,100 feet. Authorized depth 35 feet (adopted 1962.) 
At Elizabeth Marine Terminal - A branch channel 500 
feet wide, length about 1.4 miles; a pierhead channel along the 
east bulkhead 290 feet wide, length about 1.1 miles; a south 
channel along the south bulkhead 290 feet wide, length about 
2,600 feet, a southern approach area just above former Central 
Railroad of New Jersey Bridge enlarged for turning and 
maneuvering, with a maximum length of about 2,700 feet and 
width (between the pierhead channel and Newark Bay channel) 
of about 80G feet. Authorized depth 35 feet (adopted 
1962.) 
NOTE: The above channels and areas were completed. However the 
authorized depths, except for the Newark Bay channel north of the 
Port Newark entrance, have been modified by the Kill Van Kull- 
Newark Bay project, which specifies deepening to 40 and 44 feet. This 
work is now underway. 
2-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. River and Harbor Act of 1954 provides 
local interests furnish lands, rights-of-way, the suitable spoildisposal 
areas for initial construction and future maintenance; 
provide depths commensurate with channel depth in 
approaches and berths at terminals of companies which 
would use improvement; and hold the United States free from 
damages. River and Harbor Act of 1962 provides that local 
interests must provide lands, easements and rights-of-way for 
maintenance and construction, hold United States free from 
damages, provide and maintain adequate public terminal and 
transfer facilities, and accomplish without cost to the United 
States, removal or relocation of pipelines, cable and other 
utilities. Assurances were furnished by Port of New York 
Authority and accepted Jine 12, 1964. Local cooperation 
required by previous modifications is fully complied with. 
Terminal facilities. See Port Series No. 5, revised 1978, 
Vol. 2. 
Operations and results during period. The engineering and 
design effort for the Passaic River and the lower portion of 
the Hackensack River was initiated during this period. This 
effort consisted of performing sampling and testing of bottom 
sediment to determine material characteristics and disposal 
options. The total cost of the work was $103,511. 
Condition as of September 30. Work under the active 
portion of the original project began June 1976 and is 100 
percent complete. Work remaining to complete existing original 
project consists of deepening the Hackensack River 
channel to depths of 32 feet and 15 feet. 
14. NEW YORK AND NEW JERSEY CHANNELS 
Location. Extends from deep water northwest of Sandy 
Hook, through Lower New York Bay and Raritan Bay, to 
Perth Amboy, and thence through Arthur Kill, Lower 
Newark Bay, and Kill Van Kull to deep water in Upper New 
York Bay. This route is approximately along boundary line 
between states of New York and New Jersey. (See National 
Ocean Survey Charts 12333, 12331, and 12327.) 
Previous projects. For details see 1963 Annual Report 
pages 184 and 185. 
Existing project. A channel through Lower New York Bay, 
Raritan Bay, Arthur Kill, Lower Newark Bay, and Kill Van 
Kull to Upper New York Bay and Raritan Bay and in Arthur 
Kill to a point 1,000 feet north of Smith Creek, widened to 800 
feet in vicinity of Seguine Point and Wards Point, respectively; 
thence 500 wide to a point 1,000 feet south of Piles 
Creek; thence 500 to 600 feet wide and passing north of 
Shooters Island and protected by a dike on its northern side to 
junction of channel into Newark Bay; thence 800 feet wide 
through Kill Van Kull to Constable Hook; thence 1,000 feet 
wide for a point opposite the east end of Constable Hook to a 
point near the intersection with the channel along New Jersey 
pierhead line; and thence 1,400 feet wide through Kill Van 
Kull to Upper New York Bay; with an anchorage 38 feet deep 
to accommodate five vessels south of Perth Amboy, all with 
suitable easing at bends and junctions. Section included in 
project is 30.8 miles long. In addition, construction of a dike 
north of Shooters Island and two secondary channels 30 feet 
deep and 400 feet wide, one south of Shooters Island and the 
other in Raritan Bay connecting with Raritan River, were 
completed under previous projects and maintained under 
existing project. A triangular area at the eastern end of the 30 
foot channel south of Shooters Island was deepened to 35 feet 
in order to provide additional widening in the vicinity of 
Bergen Point and is included in the Newark Bay project. All 
depths refer to plane of mean low water. Mean range of tides 
varies between 4.7 and 5.1 feet; mean range of spring tides 5.7 
to 6.3 feet; irregular fluctuations due to wind and atmospheric 
pressure vary from 3.9 feet below mean low water up to 6.9 
feet above mean high water. Anchorage at Sandy Hook, and 
cutoff at junction of Main Ship Channel are deferred for 
restudy and excluded from foregoing description and cost 
estimate. (See Table 2-B for Authorizing Legislation.) 
Location cooperation. Fully complied with except for the 
middle section of Arthur Kill where local interest must furnish 
spoil disposal areas for maintenance. 
Terminal facilities. See Port Series No. 5, revised 1978, 
Vol. 2. 
Operations and results during period. A continuing contract 
for the removal of all material except ledge rock lying 
above the plane of 25,35 and 37 feet below mean low water in 
N.Y. & N.J. Channels, Perth Amboy Anchorage was 
awarded on 11 August 1988. Work commenced on 12 September 
1988 and was completed on 7 February 1989. A total 
of 351,065 cubic yards of material was removed for a total 
project cost of $1,222,679. 
Conditions as September 30. Work under active portion of 
existing project began in October 1933. Work completed 
consists of providing authorized project depth and widths 
throughout entire channel from Lower New York Bay to 
Upper New York Bay and providing depths of 37 and 25 feet 
in Perth Amboy Anchorage. In addition to above mentioned 
work, construction of dike north of Shooters Island, two 
secondary channels 30 feet deep and 400 feet wide, one south 
of Shooters Island, the other in Raritan Bay connecting with 
Raritan River were completed under previous projects. Work 
remaining under existing project consists of dredging cutoff 
at junction of Main Ship Channel to dimensions authorized 
by River and Harbor Acts of August 30, 1935, and May 17, 
1950, dredging anchorage in vicinity of Sandy Hook. 
2-8

NEW YORK, N.Y. DISTRICT 
15. NEW YORK HARBOR - 
COLLECTION AND REMOVAL OF DRIFT 
Location. Applies to Lower and Upper Bays, New York 
Harbor; East River, Harlem River, Hudson River Channel, 
N.Y., New York and New Jersey Channels, Newark Bay, N.J. 
and their tributaries. 
Existing project. Provides for collection, removal and disposal 
of drift, derelict vessels, deteriorated shore structures 
and debris along shores of New York Harbor and tributary 
waters, and for the repair of certain other piers, wharves and 
shore structures. Work authorized before Act of 1970 was 
restricted solely to removal of drift from waterways and was 
funded as a maintenance activity. Estimate of first cost under 
the 1987 Supplemental Appropriations Act is $137,670,000 
(October 87 P.L.) including $26,970,000 cash contribution 
from local interests plus $56,770,000 to be contributed for 
repair and disposal of deteriorated shore structures in use. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local cooperation conditions of the 
plans currently under review by the Chief of Engineers provide 
that local interests must furnish all lands, easements and 
rights-of-way required for the improvement; hold the United 
States free from damages; enact and enforce local legislation 
to prevent creation of sources of drift, contribute in cash one 
third of the first cost of the Federal work, and make necessary 
repairs to deteriorated structures in use so as to eliminate 
them as a source of drift. These conditions are subject to 
approval by the Secretary of the Army and the President, as 
stipulated in Section 113 of the authorizing law, Public Law 
91-611. 
Operations and results (New work - cumulative to date): 
A total of five Liberty State Park contracts have been completed 
at a cost of $10,321,121. East River-Manhattan Waterfront 
contract was completed at a cost of $1,477,806. A contract 
for the removal of Piers 17 and 18 on the East River was 
completed at a cost of $219,604. The City of Elizabeth contract 
was completed at a cost of $791,656. The Stapleton, 
Staten Island contract was completed at a cost of $2,910,400. 
A contract for the City of Hoboken was completed at a cost of 
$2,123,404. Work along the Jersey City South waterfront was 
completed at a cost of $979,580. Contract Number One at 
Weehawken to Edgewater was completed at a cost of 
$1,697,487. The Brooklyn Reach One contract was completed 
at a cost of $5,092,920. Work is continuing on the Weehawken 
to Edgewater contract No. 2. The Bayonne (mainland) 
contract has been completed at a cost of $735,800. 
Engineering and design is in progress for Brooklyn Reach 2. 
Maintenance. U.S. Debris Boats Driftmaster, Gelberman 
and Hayward and auxiliary plant were assigned the task of 
removing and disposing of floating debris that is a hazard to 
navigation. Removal and disposal of 571,645 cubic feet (4,466 
cords) of floating debris consisting mainly of driftwood, ranging 
in size from small blocks to large timbers, including 
pilings, pieces of wreckage, derelict vessels and sections of 
deteriorated pier structure was accomplished at a cost of 
$3,856,047 in FY 1989. 
Conditions as of September 30. For work authorized by the 
Water Resources Development Act, removal of drift sources 
has been completed in New Jersey at Liberty State Park, the 
City of Elizabeth, Hoboken, and parts of Jersey City, Weehawken 
and Edgewater. In New York City, work has been 
completed along the Manhattan side of the East River inclusive 
of Piers 17 and 18, Stapleton, Staten Island. Removal 
work is currently underway at Brooklyn. 
16. NEW YORK HARBOR-ENTRANCE 
CHANNELS AND ANCHORAGE AREAS 
Location. In Upper and Lower Bays, New York Harbor is 
330 miles southwest by water of Boston Harbor, Mass, and 
165 miles northwest of entrance to Delaware Bay, N.J. The 
Upper Bay extends about 5.5 miles southerly from junction of 
Hudson and East Rivers opposite the Battery, New York City 
to the Narrows. Lower Bay extends about 9 miles from the 
Narrows. Lower Bay extends about 9 miles from the Narrows 
to the sea. (See National Ocean Survey Charts 12327, 12334, 
12335, and 12349.) 
Existing project. Ambrose Channel 45 feet deep and 2,000 
feet wide, extending about 10.2 miles from sea to deep water 
in the Lower bay; Anchorage Channel, an extension of 
Ambrose Channel, with same depth and width, in the Upper 
bay, opposite anchorage grounds, about 5.7 miles long; a 
southerly entrance channel, Sandy Hook Channel (East Section) 
35 feet deep and generally 800 feet wide extending 3.4 
miles from 35-foot ocean contour to Bayside Channel along 
an alignment generally west of the South Channel; and elimination 
from authorized project of that portion of Bayside- 
Gedney Channel east of junction with new southerly entrance 
channel; for Bayside Channel 35 feet deep and 800 feet wide, 
extending about 5.3 miles from Bayside Channel to deep 
water in Lower bay; a channel along New Jersey pierhead line 
connecting Kill Van Kull with deep water in anchorage 
Channel, south of Liberty Island anchorage, 20 feet deep for 
500 feet wide with widening at bends to 800 feet and about 3 
miles long; an anchorage in vicinity of Liberty (Bedloes) 
Island (about 160 acres in extent) 20 feet deep; and for removal 
of Craven Shoal to 30 feet deep; for a channel 16 feet deep, 
200 feet wide, and about 2.3 miles long, extending from bell 
buoy 23 to Hoffman and Swinburne Island; for an anchorage 
area in Red Hooks Flats to depths of 45, 40 and 35 feet and an 
anchorage area in Gravesend Bay to 47 feet deep. Project 
depths refer to mean low water. Mean tidal range is 4.7 feet at 
Fort Hamilton; mean range of spring tides, 5.7 feet; irregular 
fluctuations due to wind and atmospheric pressure vary from 
3.9 feet below mean low water up to 6.2 feet above mean high 
water. 
2-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Location cooperation. Fully complied with. 
Terminal facilities. See Port Series no. 5, revised Vol. 2. 
Operations and results during period. The U.S. Army 
Corps of Engineers Dredge "McFarland" was employed in 
June & July 1989 to restore project dimensions in New York 
Harbor Red Hook Flats Anchorage. Removed 222,212 cubic 
yards at a cost of $1,470,000. 
Conditions as of September 30. Work under existing project 
began in 1885 and is 100 percent complete. Main Ship and 
Bayside-Gedney Channels were completed to 30 feet deep in 
February 1891. Deepening of Bayside-Gedney Channel to 35 
feet for a width of 800 feet was completed in June 1939. 
Ambrose Channel was completed to 40 feet deep for a width 
of 2,000 feet in April 1914 and substantially completed to 45 
feet for a width of 2,000 feet in 1951. Relocation of Anchorage 
Channel was completed to 40 feet deep in October 1932. 
Center 800 feet was dredged to 45 feet in June 1947 and 
westerly 600-foot strip in April 1948. Easterly 600-foot strip 
was substantially completed in June 1953. Channel between 
Staten Island and Hoffman and Swinburne Islands was completed 
in December 1920 up to within 300 feet of southerly 
limits of the project. Dredged channel meets all needs of 
navigation and no further work of improvement is contemplated 
for the present. Channel along New Jersey pierhead 
line from Kill Van Kull to Anchorage Channel was completed 
in March 1939. Widening at bends near southerly and northerly 
ends authorized in 1948 was completed to depths of 45, 
and 35 feet in October 1976. Anchorage Channel was relocated 
to the westward in 1982. Red Hook Flats Anchorage 
was accordingly increased in area. No dredging was required. 
Liberty (Bedloes) Island anchorage was completed to 20 feet 
in October 1944. Sandy Hook Channel (east section was 
completed to a depth of 35 feet in June 1963. Gravesend Bay 
was completed to a 47-foot depth in November 1977. 
17. PORT CHESTER HARBOR, N.Y. 
Location. At boundary between States of New York and 
Connecticut, comprises the tidal mouth, about 1.7 miles long, 
of Byram River whose source is in Byram Lake about 12 miles 
north of Port Chester. River empties into Long Island Sound 
about 32 miles by water east of the Battery, New York City. 
(See Coast and Survey Chart 12367.) 
Previous projects. For details see Annual Report for 1915, 
1758, and Annual Report for 1938, page 157. 
Existing project. An anchorage basin near breakwater constructed 
at Byram Point under a previous project, 12 feet 
deep, for fenders on east bank opposite southern end of Fox 
Island, and a channel 12 feet deep at mean low water and 150 
feet wide from Long Island Sound to mouth of river at 
southerly point of Fox Island; thence 10 feet deep and 100 feet 
.wide to 900 feet below fixed bridge at Mill St'eet in Portchester, 
including a turning basin opposite steamboat landing; 
thence 3 feet deep and 175 to 100 feet wide to 100 feet below 
bridge. Section included in project is about 1.7 miles long. 
Mean tidal range, 7. I feet; mean range of spring tides, 8.5 feet; 
irregular fluctuations due to wind and barometric pressure 
vary from 4 feet below mean low water up to 8.6 feet above 
mean high water. Cost of new work for completed project was 
$358,475, exclusive of amounts expended on previous projects, 
and $5,500 to be contributed by local interests. Widening 
turning basin and construction offenders on bank opposite 
southern end of Fox Island, at a cost of $93,000, (1954) is 
inactive and excluded from foregoing description of existing 
project and cost estimate. 
Local cooperation. River and Harbor Act of 1930 provides 
that local interests contribute $5,500 in cash toward widening 
channel at turning basin. This condition has not been fulfilled 
and there is no indication as to when compliance may be 
expected. 
Terminal facilities. There are 34 terminals in Port Chester 
between Fox Island and Mill Street Bridge, with a total 
berthage of about 5,300 feet, of which 3,120 feet are available 
for dockage. Village of Port Chester owns several bulkheads 
which are used as public landings for small pleasure craft. 
Several boatyards with storage space for 75 boats and 
equipped with a total of 3 marine railways are available for 
pleasure craft. Facilities adequate for existing commerce. 
Operations and results during period. An engineering and 
design effort for Port Chester Harbor, N.Y. was conducted 
during this period in anticipation dredging in FY90. The total 
cost of work was $101,998. 
Condition as of September 31. Work on active portion of 
existing project was completed October 1938. Controlling 
mean low water depth (June 1952 and Nov. 1965) was 12 feet 
for a width of 140-50 feet from Long Island Sound to Fox 
Island, 8 feet in anchorage, thence 10 feet fora width of 90-40 
to turning basin, 10 feet in turning basin, thence depths varyfrom 
3 to zero feet for full width to upper limit of 3-foot 
project. Work remaining under existing project consists of 
turning basin and constructing fenders on bank opposite 
southern end of Fox Island (inactive). 
18. RONDOUT HARBOR, N.Y. 
Location. Comprises tidal mouth about 3.5 miles long, of 
Creek, whose source is about 18 miles west of Roundout. 
Creek empties into Hudson River from the west, about 89 
miles north of the Battery, New York City, and 55 miles south 
Albany. 
Existing project. A channel 100 feet wide, widening at 
bends, and 14 feet deep from deep water in Hudson River to 
highway bridge, 1.3 miles above mouth, thence 12 feet deep to 
3.5 miles above mouth, two parallel dikes 350 feet apart to 
maintain channel, and a branch dike to extend upstream from 
outer end of north dike to protect that dike from running ice 
2-10

NEW YORK, N.Y. DISTRICT 
in Hudson River. Mean tidal range, 3.7 feet; mean range of 
spring tides, 4.2 feet; extreme range, 8.2 feet; irregular fluctuations 
due to freshets vary from 2 feet below mean low water up 
to 2.5 feet above mean high water. New work for completed 
project cost $131,140. (See Table 2-B for Authorizing 
Legislation.) 
Local cooperation. River and Harbor Act of 1965 provides 
local interests furnish lands, easements, and rights-of-way for 
construction and future maintenance of the Federal project as 
modified and for construction and maintenance of aids to 
navigation upon request of the Chief of Engineers, including 
suitable spoil-disposal areas and necessary retaining dikes, 
bulkheads and embankments therefore or the cost of such 
retaining works; hold the United States free from damages, 
and provide and maintain depths in berthing areas serving 
terminals commensurate with depths provided in related project 
areas. Assurances of local compliance were furnished by 
town of Ulster on June 9, by city of Kingston on June 17, and 
by town of Esopus on June 20, 1966. 
Terminal facilities. Seventeen timber wharves with available 
dockage of 12,132 feet along waterway. Four terminals are 
equipped with transfer facilities; all are private owned. Terminals 
adequate for present needs of commerce. (For latest 
full description see Port and Terminal Facilities at the Ports 
on Upper Hudson River, 1941, Corps of Engineers.) 
Operations and results during period. A contract in the 
amount of $2,737,750 was awarded to the Hull Corporation 
on March I I, 1988 for rehabilitation of the dike system. 
Funds in the amount of $614,539 was expended on this contract 
during the period and the continuing contract was completed 
during the third quarter of fiscal year 1989 at a total 
contract cost of $2,614,539. Operations and maintenance 
funds in the amount of $87,554 were expended on engineering 
and design, supervision and administration, and surveys for 
contract work during FY 1989 on the project. 
Condition at end of fiscal year. Work under existing project 
was commenced April 1873 and is about 87 percent complete. 
Part of diking originally proposed was not built because it 
was deemed of doubtful usefulness. Two parallel dikes of an 
aggregate length of about 5,000 feet, generally 350 feet apart, 
with a now obsolete spur from the old lighthouse south of 
south dike were built across the bar at mouth of creek. A 
branch dike about 1,000 feet long, extending northerly from 
outer end of north dike, was also constructed. Work remaining 
consists of removal of shoals in the 12 and 14 foot projects 
and rehabiliation of deteriorated sections of the parallel and 
branch dikes. 
19. SUPERVISOR OF NEW YORK HARBOR 
(PREVENTION OF OBSTRUCTION 
AND INJURIOUS DEPOSITS) 
The District Engineer, New York District, was designed 
Supervisor of New York Harbor under the provisions of the 
River and Harbor Act of June 29, 1888 (33 U.S.C. 441-451), 
as amended July 12, 1952. Under this Act, the supervisor of 
New York Harbor is charged with the mission of preventing 
the deposit of obstructive and injurious materials in New 
York Harbor and its adjacent and tributary waters, including 
Long Island Sound. The River and Harbor Act of August 18, 
1894 (33 U.SC. 452) makes it unlawful for any person or 
persons to engage in fishing or dredging for shellfish in any of 
the channels leading to and from New York Harbor, or to 
interfere in any way with the safe navigation of those channels 
by ocean steamships and ships of deep draft; the River and 
Harbor Act of March 3, 1899 (33 U.S.C. 403, 307, 409) 
prohibits obstructions to navigable waters such as unauthorized 
structures, unauthorized fill, deposit of refuse, and willfuil 
or negligent abandonment of vessels. Other laws relating 
to the supervision of New York Harbor and its tributary 
waters are the Clean Water Act, the Marine Protection, 
Research and Sanctuaries Act of 1972, the Coastal Zone 
Management Act of 1969, the fish and Wildlife Act of 1956, 
the Federal Power Act of 1920, the National Historic Preservation 
Act of 1966, the Endangered Species Act of 1973, the 
Deepwater Port Act of 1972, the Wild and Scenic Rivers Act, 
and the Land and Water Conservation Fund Act. 
Direct supervision of the waters under jurisdiction of the New 
York District was accomplished by means of a patrol vessel 
whose scope of duty includes surveillance of the waterfront 
for unauthorized construction or fill, surveillance of the 3- 
mile limit of tows enroute to dumping grounds in the Atlantic 
Ocean to ensure that material is not illegally deposited in the 
waters of New York Harbor, and investigation of wrecks and 
abandoned vessels. In addition to the patrol vessels, whose 
range of patrol was limited to New York Harbor, inspectors 
utilizing government vehicles equipped with two-way radios 
patrolled shorefront facilities and property. These inspectors 
operate out of field offices located at Hauppage, New York 
and one inspector working at the New York District Office. 
Their duties include inspection of authorized construction, 
fill or excavation in waterways, including wetland areas, to 
ensure that work is performed in accordance with the Corps 
permit. The inspectors also patrol all waterways in their 
respective areas and inform the public of the Corps role and 
jurisdiction as well as provide assistance in the preparation of 
permit applications. (See Table 2-E at end of chapter.) 
20. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 2-F at end of chapter.) 
21. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 2-G at end of chapter.) 
22. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities pursuant to Section 107, Public Law 
645, 86th Congress as amended (Pre-authorization). 
(See Table 2-N at end of chapter.) 
2-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
BEACH EROSION CONTROL 
23. EAST ROCKAWAY INLET TO 
ROCKAWAY INLET & JAMAICA BAY, N.Y. 
Location. Atlantic coast of New York City, between East 
Rockaway and Rockaway Inlets, and the lands within and 
surrounding Jamaica Bay. The coastal area (about 10 miles 
long) is a peninsula in Queens County separating the ocean 
and the bay. (See National Ocean Survey Charts 12327, 
12350, and 12326.) 
Existing project. The project provides for approximately 
8.7 million cubic yards of sand fill including the advanced 
placement of a two year supply of beach nourishment of the 
shore protection works for 10 years after completion of the 
initial beach fill. Federal participation (50 percent) includes 
first cost and periodic beach nourishment, the total estimated 
at $25,400,000 (Oct. 1986 P.L.) 
Local cooperation. Local interests must provide lands and 
rights-of-way, including borrow areas; bear 50 percent of 
total first cost presently estimated at $25,400,000 consisting of 
a cash contribution of $8,813,500 the final apportionment of 
costs to be made after actual costs and values have been 
determined and $16,586,500 for periodic nourishment, hold 
the United States free from damages; maintain, during economic 
life of project, continued public ownership and use of 
non-Federal publicly-owned shores upon which Federal participation 
in beach protection is based; maintain and operate 
all works after completion, control water pollution to the 
extent necessary to safeguard the health of bathers; local 
cooperation agreement was executed by the State May 17, 
1974 and approved for Secretary of Army May 21, 1974. On 
May 22, 1974 sent to State an approved Escrow Agreement. 
Operations and results during period and condition as of 
September 30. A draft report on monitoring study of the 
completed project has been provided to the Waterways 
Experiment Station who will publish an official report. Final 
Environmental Impact Statement on file with Council of 
Environmental Quality on April 16, 1971. Initial beach restoration 
completed in FY 1977. Contract for first increment of 
periodic nourishment was completed in August 1982. Contract 
for construction of stone groin at Beach 149th Street was 
completed in September 1982. Periodic nourishment contracts 
Nos. 3, 4, and 5 have been completed. Additional 
legislation is necessary in order to continue this project, and 
the State must request that the work be done. Funding is not 
yet available. 
24. SANDY HOOK TO BARNEGAT INLET, N.J. 
Location. The northern portion of the Atlantic coast of 
New Jersey extending from Sandy Hook southerly to Barnegat 
Inlet - length about 48 miles. Erosion has seriously 
reduced the width of most beaches in the study area with 
consequent exposure of the shore to storm damage. Because 
of this erosion of the shore the area does not provide sufficient 
recreational beaches for the proper accommodation of the 
present and prospective tributary population. 
SECTION I - SEA BRIGHT TO 
OCEAN TOWNSHIP, N.J. 
Location. That portion of the Atlantic coast of New Jersey 
in Monmouth County extending from Sea Bright southerly to 
Ocean Township - length about 12 miles. Sea Bright is about 
30 miles by water south of the Battery, New York City. 
Authorized project. The Water Resources Development 
Act of 1988 (PL 100-676) authorized a plan substantially in 
accordance with the plan recommended in the General 
Design Memorandum for the project dated May, 1988. In 
general' the plan provides for beach erosion control along 
approximately 12 miles of coastline, extending from Sea 
Bright southward to Ocean Township. New Jersey, by artificial 
placement of sand to widen the beach berm to 100 feet at 
an elevation of 10 feet above mean low water with an additional 
2 foot high berm cap to provide an extra increment of 
protection from overtopping. The project also provides for 
the notching of 15 groins, a feeder beach in the vicinity of 
Long Branch and periodic nourishment throughout the economic 
life of the project. Total estimated Federal cost is 
$409,700,000. Total estimated non-Federal cost for all 
requirements of local cooperation is $229,600 000. 
Local cooperation. Includes reconstruction of sea wall at 
Sea Bright and all lands easements, rights of way and drainage 
outfall extensions. 
Operations and results during period and condition as of 
September 30. Construction has not been initiated, but project 
is in active status. The final GDM is currently under 
review at the Washington level. 
SECTION II - ASBURY PARK TO 
MANASQUAN, N.J. 
Location. That portion of the Atlantic coast of New Jersey 
in Monmouth County extending from Asbury Park southerly 
to Manasquan - length about 9 miles. 
Recommended project. Provides for Federal participation 
in the restoration and protection of the shore from Asbury 
Park to Manasquan by artificial placement of sand to widen 
the beach to a minimum width of 100 feet at an elevation of 10 
feet above mean low water. The project provides for Federal 
participation in periodic nourishment costs for a period of 50 
years from the year that the total quantity of fill placed has 
equalled that required to restore the beach to project dimensions. 
Total estimated Federal cost is $210,400,000. Total 
estimated non-Federal cost is $137,300,000 (See Table 2-B for 
Authorizing Legislation.) 
2-12

NEW YORK, N.Y. DISTRICT 
Operations and results during period, and conditions as of 
September 30. The project is in active status with work on the 
Preconstruction Engineering & Design (PED) effort initiated 
in FY 1987. The PED effort which is continuing will result in 
the development of a General Design Memorandum (GDM), 
Environmental Impact Statement (EIS), as well as the Plans 
and Specifications. 
25. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 2-H at end of chapter.) 
26. BEACH EROSION CONTROL 
WORK UNDER SPECIAL AUTHORIZATION 
Beach Erosion Control activities pursuant to Section 103 
Public Law 826, 84th congress as amended (preauthorization). 
(See Table 2-0 at end of chapter.) 
FLOOD CONTROL 
27. ARDSLEY, N.Y. 
Location. The Village of Ardsley in Westchester County, 
New York is located on the Saw Mill River approximately 5 
miles upstream from its junction with the Hudson River. (See 
U.S Geological Survey Map, White Plains, N.Y.) 
Existing project. The Federal flood control project provides 
for relocation of the existing channel from the upstream 
limit of the project downstream for approximately 1,000 feet, 
and approximately 290 feet of concrete channel upstream of 
the New Ashford Avenue Bridge. Upstream of the concrete 
channel along the left bank of the Saw Mill River, 425 feet of 
floodwall will be constructed running north of the Conrail 
Bridge. Ponding areas, drainage ditches and other drainage 
structures will be provided. The total estimated Federal cost 
for the project is $5,676,000 exclusive of land, relocations and 
other work to be provided by local interests at an estimated 
cost of $1,892,000 (October 1988 P.L.) 
Local cooperation. In accordance with cost sharing and 
financing concepts reflected in S.1567, local interests are 
required to furnish all lands, easements and rights-of-way 
including relocations that are necessary for flood control 
improvements. 
The local sponsor has contributed a total cash contribution 
of $840,000 of which $150,000 was contributed in FY 1987 
and FY 1988. The final cash payment for FY 1989 was made 
in January 1989 in the amount of $690,000. The New York 
State Department of Environmental Conservation, the local 
sponsor, in an II December 1973 letter, indicated its intent to 
comply with the items of local cooperation and reaffirmed 
this on 15 August 1979 and 23 August 1985. The State of New 
York, in a 18 October 1985 letter, expressed this willingness to 
assume responsibility as local sponsor in accordance with the 
Cost sharing and financing concepts agreed to by the Administration 
and Senator Majority Leadership Compromise as 
reflected in the Water Resources Development Act of 1986. 
Operation and results during period and condition as of 
September 30. Construction of the downstream reach (the 
base bid) began in April 1988 and was completed in June 
1988. Construction of Option Iland Option II began in July 88 
and were scheduled for completion in November 89. The 
project will be turned over to the local sponsors for operation 
and maintenance. 
28. LIBERTY STATE PARK 
LEVEE AND SEAWALL, N.J. 
Location. At Liberty Park, in Jersey City, Hudson County, 
New Jersey, directly behind Ellis Island and Statue of Liberty, 
In Upper New York Bay. (See National Ocean Survey Chart 
12334.) 
Existing project. Construction of a levee and seawall, and 
pedestrian walkways; over environmentally sensitive areas. 
The construction of the levee project will allow the creation of 
a large Greenpark to include a wetlands preserve, an inland 
water course and boat basin, a marina, an amphitheater, 
indoor and outdoor recreation facilities, picnic areas, historic 
areas, community facilities, restaurants, plaza, and many 
other areas for both active and passive recreational and aesthetic 
benefit to visitors. The stone armored levee will also 
serve as a settlement-free base for subsequent construction of 
a tree-lined promenade, the Liberty Walk, curving along the 
water's edge. The Federal cost of construction is estimated at 
$19,150,000; with an additional $19,150,000 a contribution by 
local interests including lands, certain relocations, utilities, 
and interior drainage. 
Local cooperation. In accordance with the project authorization, 
local interests are required to furnish all land, easements 
and rights-of-way including relocations, save those 
existing utilities passing through the proposed levee, necessary 
for the flood control improvements and to operate and 
maintain the project at an annual cost estimated to total 
$58,000. The State will assume all costs for construction of an 
interior drainage system to provide (10) year level of protection 
estimated to be $5,100,000. Local interest have agreed to 
voluntarily pay 50% of project cost. The New Jersey Department 
of Environmental Protection is the local sponsor. The 
local cooperation agreement was executed on 26 June 1986. 
Operation and results during period and conditions as of 
September 30. Phase I is completed. A contract for the levee 
and seawall was awarded in February 1987 and construction 
was completed in February 1988 with the exception of the 
Ellis Island Bridge location. A contract for the pedestrian 
walkways was awarded in June 88. The work was scheduled 
for completion in Dec. 89. The completed project will be 
turned over to the local sponsor for operation and 
maintenance. 
2-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
29. PASSAIC RIVER BASIN, N.J. & N.Y. 
Location. The Passaic River Basin, comprising 787 square 
miles in northeastern New Jersey and 148 square miles in 
southern New York State, is located in the greater New York 
City Metropolitan area. The Passaic River Basin is roughly 
elliptical in shape 26 miles long and 56 miles wide - and 
contains portions of Bergen, Essex, Morris, Passaic, Hudson, 
Somerset, Sussex and Union Counties in New Jersey. The 
Basin also includes parts of Orange and Rockland Counties in 
New York. 
Previous projects. Three Federal flood control projects 
have been completed by the Corps of Engineers in Passaic 
River Basin. A $67,400 desnagging, debris removal, and 
channel restoration project was completed in 1951 along 
Beaver Brook and the Pequannock Township Ditch, tributaries 
of the Pompton River in Pequannock Township, N.J. 
Along the Pompton River, a channel clearing project 
including shoal removal and channel restoration was implemented 
in the two-mile reach from the Delaware, Lackawanna 
and Western Railroad Bridge to the Erie Railroad 
(Greenwood Lake Branch) Bridge. This work, in Pequannock 
Township, Wayne Township and Lincoln Park Borough, 
N.J., was completed in 1954 at a cost of $50,000. 
At $1.5 million basin-wide project to improve the Flood 
Warning and Preparedness System was completed in 1988. 
This project includes enhanced and increased number of rain 
and stream flow gauges in combination with a state-of-the-art 
communication and computer system designed to improve 
the timeliness, occupancy and reliablity of flood warning in 
the Passaic River Basin. The project was implemented by the 
Corps of Engineers in conjunction with the National Weather 
Service and U.S. Geological Survey, the State of New Jersey 
is the non-Federal sponsor of the project. 
Existing project. The project was authorized for Phase I 
advance engineering and design study in Section 101(a) of the 
Water Resources Development Act of 1976 in accordance 
with the February 18, 1976 report of the Chief of Engineers. 
the estimate of Federal cost under the authorizing legislation 
is $880,000,000 (October 1989 P.L.), plus a $208,700,000 cash 
contribution from local interests and $101,300,000 for items 
of work to be contributed by local interests. The rcommended 
plan for flood protection navigation, hurricane protection 
and recreation, included a flood detention reservior, channel 
diversions and modifications, levees and floodwalls, and 
streambank filling and grading. These works would provide 
protection against a storm with a recurrence interval of 235 
years, which is 20 percent larger than the October 1903 flood 
of record. Six independent tributary local protection plans 
were also recommended. However, because of a lack of public 
support for structural components of the project in the New 
Jersey portion of the Basin, the entire project was reformulated 
during the Phase I study. 
The House Public Works Committee Report (94-1702) on 
the 1976 Water Resources Development Act directed "... the 
reformulation of the plan for water management and flood 
control for the entire Passaic Basin." This report further 
stated that local opposition to any plan which relies upon 
extensive use of dikes, dams and levees, such as those proposed 
in previous survey reports, mandates that the following 
alternatives, or any combination thereof, shall be the only 
ones surveyed and considered: (a) A full range of nonstructural 
flood control alternatives to include land acquisition, 
flood plain mapping, flood-proofing, developing early warning 
systems and relocation of buildings; (b) A tunnel diversion 
plan; (c) A system of tunnels addressing the needs of the entire 
basin; (d) Plans that combine local protection works where 
locally acceptable and nonstructural solutions including 
improvements to stream carrying capacity in accordance with 
different needs in the Lower Basin and in the Central Basin; 
(e) Evaluation of fulfilling water supply objectives together 
with flood control; (f) Aquifer recharge and underground 
storage; and (g) Reservoir management in the headwaters. 
The Phase I Study considered these alternatives in the formulation 
of revised plans. 
Conditions as of September 30. The reformulation study 
was initiated in October 1977 under the existing authorization 
and Congressional Guidance in House Report 94-1702. The 
overall study was completed in December 1989 at an estimated 
cost of $21,300,000. A wide range of feasible Basinwide 
alternative plans were developed. These alternatives, 
which were presented for extensive public review, included 
tunnel diversions, channel modification, levees and floodwalls, 
and nonstructural measures. In April 1984, the Passaic 
Basin experienced flooding estimated to be the worst in 40 
years. Local protection plans were completed for tributary 
flood damage areas along the Ramapo and Mahwah Rivers at 
Mahwah, N.J., and Suffern, N.Y., Molly Ann's Brook at 
Haledon, Prospect Park and Paterson, N.J., the Ramapo 
River at Oakland, N.J., and the Lower Saddle River in Bergen 
County, N.J. These projects were authorized in the Water 
Resources Development Act of 1986. In June 1984, The State 
of New Jersey selected a dual inlet diversion tunnel plan as the 
local option for detailed plan formulation. The Phase I 
General Design Memorandum and draft Environmental 
Ilupact Statement, (EIS), recommending the Pompton 
River/ Passaic Dual Inlet Tunnel Diversion Plan, were completed 
during FY 1988. The Phase I report was approved by 
the Board of Engineers for Rivers and Harbors (BERH) on 
July 23, 1988 and by the office of the Chief of Engineers on 3 
February 1989. The final EIS was filed with EPA in 
December 1988, with the comment period ending in January 
1989. The report is currently under review by the Assistant 
Secretary of the Army for Civil Works. 
2-14

NEW YORK, N.Y. DISTRICT 
30. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspections of (26) completed flood control works and 
beach erosion and hurricane protection projects were performed 
to determine the extent of compliance by local interests 
with operation and maintenance requirements. 
31. OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
(See Table 2-I at end of chapter.) 
32. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Natural Disaster and Emergency Flood Control Activities. 
Pursuant to Public Law 84-99 and antecedent legislation 
provides for advance preparation, emergency operations, 
rehabilitation, emergency drinking water, advance measures 
and drought assistance. 
Under disaster preparedness, the New York District completed 
revisions of various emergency manuals and phamphlets, 
attended meetings and seminars dealing with emergency 
response and preparation, and purchased supplies and 
equipment to maintain its' flood fighting and response 
capability. 
Under emergency operations, the New York District provided 
technical assistance and sandbags to local and county 
governmental organizations which requested such aid during 
several minor storm/flood events. 
33. EMERGENCY STREAMBANK 
AND SHORELINE PROTECTION 
Activities pursuant to Section 14, Public Law 526, 
79th Congress as amended (Preauthorization). 
(See Table 2-Q at end of chapter.) 
34. SURVEYS 
(See Table 2-J at end of chapter.) 
35. COLLECTION AND STUDY 
OF BASIC DATA 
Costs for the period of $112,847 for flood plain management 
services are set forth in Table 2-L at the end of chapter. 
36. DEAUTHORIZED PROJECTS 
A total of 23 projects were deauthorized by Congressional 
Action pursuant to Section 12 of Public Law 93-251. Water 
Resources Development Act of 1976. 
(See Table 2-M at end of chapter.) 
2-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-A COST AND FINANCIAL STATEMENT 
See 
Section Funding FY 86 FY 87 FY 88 FY 89 Total Cost to 
in Text Projects September 30, 1989 
1. Aquatic Plant 
Control 
2. Bay Ridge & Red 
Hook Channels, N.Y. 
3. East Chester Creek, 
N.Y. 
4. East Rockaway Inlet 
5. Fire Island To 
Jones Inlet, N.Y. 
6. Hempstead Harbor, 
N.Y. 
7. Hudson River, N.Y. 
8. Hudson River 
Channel, N.Y. 
NeW Work 
Approp., 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
220,000 170,000 160,000 
277,065 182,791 141,905 
140,000 
121,294 
164,000 2,842,000 583,200 3,091,000 
159,069 2,847,961 583,099 3,090,000 
- 50,000 
- 47,489 
2,030,000 
2,042,166 
82,000 969,000 
79,892 972,107 
50,000 416,000 855.000 
49,360 414,791 855,866 
1,593,806 
1,541,631 
5,523,297 
5,523,297 
36,685,188 
36,683,110 
592,056 
592,056 
2,572,042 
2,571,301 
83,969 
533,334 
8,842,736 
8,842,603 
594,355 
594,355 
425,000 
438,934 
60,000 8,082,492 
58,340 2,008,955 
486,000 
6,567,178 
- 57,000 360,000 
- 37,024 306,703 
1,792,600 4,545,900 1,666,000 2,110,000 
1,873,853 4,549,347 1,643,954 2,114,916 
- 295,000 
- 294,998 
1 
2 
27 
16 
28 
13,753,896 
13,816,270 
456,468 
383,195 
75,194 
75,194 
44,249,803 678 
44,249,865 
37,697,315 
37,578,496 
6,771,870 
6,771,870 
25,265,637 
25,265,635 
2-16

NEW YORK, N.Y. DISTRICT 
TABLE 2-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section Funding FY 86 FY 87 FY 88 FY 89 Total Cost to 
in Text Projects September 30, 1989 
9. Kill Van Kull-Newark 
Bay, N.J. & N.Y. 
10. Long Island 
Intracoastal 
Waterway, N.Y. 
11. Moriches Inlet, N.Y. 
12. Narrows of Lake 
Champlain, N.Y. 
13. Newark Bay, 
Hackensack & 
Passaic River, N.J. 
14. New York and New 
Jersey Channels 
15. New York Harbor- 
Collection and 
Removal of Drift 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
240,000 7,100,000 44,374,000 14,904,000 
254,025 1,504,912 10,607,346 42,443,863 
975,000 776,000 2,447,785 
971,074 769,107 2,434.114 
95,000 
64,000 
82,000 
82,930 
47,000 
71,296 
3,475,000 3,138,000 1,103.000 
167,509 2,568,517 3,821,785 
66,618,000 
54,825,146 
235,964 
235,964 
7,949,647 
7,962,366 
7,857,000 
7,634,093 
9,422 
9,422 
36,000 
30,379 
25,000 
29,900 
55,000 
55,253 
- 630,000 
- 630,000 
955,000 803,000 974,943 
956,975 799,434 891,906 
1,332,000 794,000 3,103,000 
1,397,900 792,986 1,679,987 
58,000 
103,511 
97,000 
1,222,679 
2,105,000 3,657,000 6,100,000 1,269,000 
2,351,181 1,992,556 2,872,931 3,137,515 
3,210,000 3,145,000 3,343,000 3,656,000 
3,270,340 2,988,000 3,299,714 3,856,047 
681,811 
681,8 11 
1,137,693 
1,137,206 
12 
29,014,510 2229 
9,014,511 
30,041,979 24 
25,006,278 
73,053,435 ... 
73,053,435 
10,302,359 
44,353,226 
454,773 
454,773 
40,360,000 
26,573,925 
64,321,767 19 
64,576,675 
2-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section Funding FY 86 FY 87 FY 88 FY 89 Total Cost to 
in Text Projects September 30, 1989 
16. New York Harbor- 
Entrance Channels 
17. Port Chester Harbor 
N.Y. 
18. Rondout Harbor, 
N.Y. 
19. Supervisor of New 
York Harbor 
23. East Rockaway Inlet 
to Rockaway Inlet 
and Jamaica Bay, N.Y. 
(Required 
Contributed 
Funds) 
24. Sandy Hook to 
Barnegat Inlet, N.J. 
27. Ardsley, N.Y. 
28. Liberty State Park 
and Seawall, N.J. 
(Required 
Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
45,009,710 20 
45,009,710 
4,033,000 2,013,000 1,142,900 4,708,000 
4,130,537 2,022,305 1,108,460 4,699,288 
- 102,000 
- 101,998 
58,000 
58,000 
75,000 2,163,000 727,000 
70,814 2,166,223 702,093 
577,000 600,000 610,000 725,000 
576,363 593,071 613,715 724,927 
3,445,000 
3,212,342 
3,145,000 
2,909,104 
50,000 3,526,000 
96,784 189,818 3,535,315 
162,226 
1,435,000 2,300,000 2,000,000 1,200,000 
1,435,815 2,186,594 2,112,616 946,329 
83,000 300,000 2,146,000 2,680,000 
83,000 237,963 496,676 4,186,689 
25,000 7,175,000 6,900,000 4,303,000 
20,250 6,093,751 3,202,496 7,553,581 
- 7,170,000 - - 
- 5,999,657 - - 
2-18 
48,246,424 
51,032,528 
433,470 
433,470 
1,162,795 
1,162,096 
142,437 
142,437 
3,165,462 
3,139,567 
30,075,447 
30,554,469 
24,921,356 
24,905,686 
17,120,961 
19,438,942 
8,235,000 
7,932,649 
5,569,000 
5,336,652 
18,603,043 
17,050,166 
7,170,000 
5,999,657

NEW YORK, N.Y. DISTRICT 
1. Of which $12,500 is for North Atlantic Division 
Accounts. 
2. Of which $12,127 is for North Atlantic Division 
Accounts. 
4. Excludes $100,000 for new work expended from contributed 
funds and includes $82,600 for new work 
expended from public work fund. 
6. Includes $5, 112,694 for new work for previous project. 
7. Includes $238,350 for new work expended from public 
works funds and $311,461 emergency relief funds. Excludes 
$81,373 expended from contributed funds. 
8. Excludes $454,273 expended between August 18, 1915 
and June 30, 1935, for operation and care of lock and 
dam at Troy, N.Y., under permanent indefinite appropriation. 
Excludes $23,735 reimbursement for repairs 
to Troy Lock. 
9. Includes $346,797 for maintenance for previous 
projects. 
12. 
15. 
Includes $115,000 for new work for previous projects. 
Includes $12,809,975 for new work for previous projects 
and $6,621 for new work for Lemon Creek, Staten 
Island, N.Y. 
18. Includes $1,160,380 for maintenance for previous project, 
and $1,621 for maintenance of Lemon Creek, 
Staten Island, N.Y. 
19. Includes $2,491,206 expended to date for construction 
of a land-based overfire air pit incinerator ($1,493,393 
in maintenance funds and $997,813, in O & M funds.) 
20. Includes $116,530 applied to removing wrecks authorized 
by acts prior to adoption of existing projects. 
22. Includes $1,836,403 for new work expended from contributed 
funds. 
23. Excludes $285,600 for new work expended from contributed 
funds. 
24. Includes $1,490,715 for maintenance for previous 
projects. 
26. Includes $111,419 for maintenance for previous projects 
and $64,560 extended form public works funds. 
27. Includes $1,246,100 for new work for previous projects 
and $64,560 extended from public works funds. 
28. Excludes $90,190 for new work expended from contributed 
funds. 
17. Includes $807,000 for new work expended from public 
works funds and $2,023,308 for new work expended 
from emergency relief funds. 
2-19 
TABLE 2-A (continued) COST AND FINANCIAL STATEMENT

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
River and Harbor 
Act of 1958 
Section 104 and Harbor 
Act of 1958 
Section 302 River and 
Harbor act of 1965 
March 3, 1989 
March 2, 1907 
July 30, 1930 
May 17, 1950 
July 3, 1930 
August 26, 1937 
May 17, 1950 
1958 River & Harbor Act 
1962 River & Harbor Act 
June 25, 1910 
August 13, 1968 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and Progressive Eratication of obnoxious 
Aquatic Plant growths 
Provided that all research and Planning cost to be borne fully by 
the United 
States 
Modified project to include control of waterchestnut 
BAY RIDGE AND RED HOOK CHANNELS, N.Y. 
(See Section 2 of Text) 
Channel 40 feet deep and 1,200 feet wide 
Dredging to obtain first a depth of 35 feet, subsequently increasing 
depth of 40 feet for full width. 
Widening of Bay Ridge Channel to 1,780 feet. 
EAST CHESTER CREEK, N.Y. 
(See Section 3 of Text) 
Channel 10 feet deep and 150 to 70 feet wide. 
EAST ROCKAWAY INLET, N.Y. (See Section 4 of Text) 
Channel 12 feet deep and 250 feet wide, and a jetty. 
FIRE ISLAND TO JONES INLET, N.Y. (See Section 5 of Text) 
construction of jetty. 
Channel 10 feet deep. 
Three dredging operations with sand serving as nourishment to the 
beaches westerly of the inlet. 
Extension of existing jetty, a littoral reservoir, a navigation channel 
and dikes, sand deposit on westerly beaches 
HEMPSTEAD HARBOR, N.Y. (See Section 6 of Text) 
Channel 6 feet deep, 50-80 feet wide. 
Channel 13 feet deep, 150 feet wide, and turning basin 9 feet deep. 
H. Doc. 37, 85th Cong., 
Ist sess. 
H. Doc. 337, 54th Cong., 
2nd sess. (Annual Report 
1899, P. 1177.) 
Rivers & Harbors Committee 
Doc. 44, 71st Cong. 2nd sess. 
H. Doc. 749, 80th Cong., 
2nd sess. 
H. Doc. 19, 71st Cong., I1st sess. 
Rivers & Harbor Committee 
Doc. 33, 75th Cong., Ist sess. 
H. Doc. 762, 80th Cong., 
2nd sess. 
H. Doc. 411, 84th Cong., 
2nd sess. 
H. Doc. 115, 89th Cong., 
Ist sess. 
Rivers & Harbors Com. 
Doc. 1, 61st Cong., 2nd sess. 
H. Doc. 101, 90th Cong., 
I st sess. 
(contains latest published map). 
2-20

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 25, 1910 
March 3, 1925 
July 3, 1930 
July 1, 1935 
August 30, 1935 
June 20, 1938 
September 3, 1954 
P.L. 89-72 
March 4, 1913 
March 4, 1915 
August 8, 1917 
March 3, 1925 
January 21, 1927 
July 3, 1930 
August 30, 1935 
August 30, 1935 
August 26, 1937 
HUDSON RIVER, N.Y. (See Section 7 of Text) 
Channel 12 feet deep from Hudson to Waterford, remove State 
lock and dam at Troy and construct a new lock and dam. 
Channel 27 feet deep from Hudson to Albany, NY 
Channel 27 feet below Hudson. 
Operation and care of lock and dam at Troy were included 
in project. 
Relocation of 12 foot channel between Troy and Waterford. 
Deepen channel between Albany and Waterford to 14 feet with no 
change in depths for harbors in front of Albany & Troy. 
Deepen channel between New York City and Albany to 32 feet 
and construct a turning basin and 2 anchorages. 
Mooring facilities 
HUDSON RIVER CHANNEL, N.Y. 
(See Section 8 of Text) 
Channel 30 feet deep from Ellis Island t Neward St., 40 feet deep 
through shoal from Newark St. to Castle Point and channel 26 by 
550 feet along Weehawken-Edgewater waterfront. Remove shoal 
east side of river between West 19th and West 32nd Sts.; remove 
rock near Battery to 40 feet; remove obstruction near Spuyten 
Duyvil Creek. 
Additional dredging through shoal from Newark St. 
to Castle Point. 
Remove shoal between West 32nd and West 61st Sts. to 40 feet 
and widen 40 foot channel between the Battery and Canal St. to 
2,000 feet. 
Channel 30 by 750 feet along Weehawken-Edgewater waterfront. 
Modification of conditions of local cooperation affecting channel 
along Weehawken-Edgewater waterfront. 
Channel 40 feet deep between pierhead lines from 20th St., Manhattan, 
to a point 1,300 feet below Newark St. Hoboken, thence 
2,800 feet wide to deep water off Ellis Island. Channel 30 feet deep 
between 40 foot channel and channel along Jersey City waterfront. 
Widen 40 foot channel to full width of river from north line of 
59th St. to south side of Little Basin, thence a channel of same 
depth to deep water off Ellis Island. 
Waiver all conditions of local cooperation affecting channel along 
Weehawken-Edgewater waterfront. 
Channel 45 and 48 feet deep and 2,000 feet wide. 
H. Doc. 719, 61st Cong., 
2nd sess. 
H. Doc. 350, 68th Cong., 
Ist sess. 
H. Doc. 210, 70th Cong., 
Ist sess. 
S. Doc. 155, 72nd Cong., 
2nd sess. 
H. Doc. 572, 75th Cong., 
3rd sess. 
H. Doc. 228, 83rd Cong., 
1st sess. 
H. Doc. 719, 
62nd Cong., 
2nd sess. 
Annual Report 1914, pp. 234-235 
H. Doc. 1697, 
64th Cong., 2nd sess. 
H. Doc. 313, 68th Cong., 
Ist sess. 
H. Doc. 450, 
70th Cong., 
2nd sess. 
H. Doc. 309, 
72nd Cong.. 
1st sess. 
Rivers & Harbors Committee 
Doc. 49, 72nd Cong., 2nd sess. 
Senate committee print, 
75th Cong., Ist sess. 
2-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
FY 1985 Supplemental 
Appropriations Act 
(PL99-88) 
August 26, 1937 
July 14, 1960 
August 8, 1917 
March 2, 1907 
February 27, 1911 
July 25, 1912 
January 21, 1927 
July 3, 1930 
March 22, 1945 
March 2, 1945 
September 3, 1954 
October 23, 1962 
November 7, 1966 
KILL VAN KULL-NEWARK BAY, N.J. & N.Y. 
(See Section 9 of Text) 
Deepening existing 35 foot channels in increments to 40 feet and 
then 
44 feet. 
LONG ISLAND INTRACOASTAL WATER, N.Y. 
(See Section 10 of Text) 
Channel 6 feet deep and 100 feet wide. 
MORICHES INLET, N.Y. (See Section 11 of Text) 
Channel 10 feet deep and 200 feet wide in inlet and 6 feet deep and 
100 feet wide in the Bay, and 2 jetties. 
NARROWS OF LAKE CHAMPLAIN, N.Y. AND VERMONT 
(See Section 12 of Text) 
Channel 12 feet deep and 150 feet wide. 
NEWARK BAY, HACKENSACK & PASSAIC RIVER, N.J. 
(See Section 13 of Text) 
16-foot channel in Passaic River 
Widening 16-foot channel in Passaic River 
20-foot channel in Passaic River 
10-foot channel in Passaic River 
30-foot channel in Passaic River 
35 and 37 feet in main channel of Newark Bay and branch channel 
to an inshore channel at Port Newark terminal and remove portion 
of rock area at Bergen Point to same depths. 
Modification of local cooperation for 10-foot channel in 
Passaic River 
34-32 foot channel in Hackensack River including approach channel 
in Newark Bay from branch channel at Port Newark Terminal 
and a 25-foot turning basin. 
35-foot channels at Port Elizabeth 
Widening 35-foot channel in Newark Bay, provision of two 
maneuvering areas, widening entrance: into Port Elizabeth and 
Port Newark branch channels, deepening and widening Newark 
Bay 32-foot channel and provision of a turning basin at junction 
of Hackeesack and Passaic Rivers; and deepening 12-foot channel 
in Hackernsack River to 15 feet. 
H. Doc. 181, 75th Cong., 
Ist sess. 
H. Doc. 126, 86th Cong., 
1st sess. 
H Doc. 1387, 62nd Cong., 
3rd sess. 
H. Doc. 441, 59th Cong., 
2nd sess. 
H. Doc. 441, 59th Cong., 
2nd sess. 
H. Doc. 707, 62nd Cong., 
H. Doc. 284, 60th Cong., 
2nd sess. 
H. Doc. 156, 71st Cong., 
2nd sess. 
S. Doc. 250, 
79th Cong., 
2nd sess. 
H. Doc. 430, 76th Cong., 
Ist sess. 
H. Doc. 252, 
82nd Cong., 
1st sess. 
H. Doc. 289, 88th Cong., 
2nd sess. 
H. Doc. 494, 
89th Cong., 
2nd sess. 
2-22

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
September 6, 1933 
August 30, 1965 
May 28, 1935 
May 17, 1950 
October 27, 1965 
March 4, 1915 
July 3, 1930 
December 31, 1970 
March 7, 1974 
July 5, 1884 
March 3, 1899 
June 25, 1910 
August 8, 1917 
August 8, 1917 
June 25, 1910 
NEW YORK AND NEW JERSEY CHANNELS 
(See Section 14 of Text) 
Anchorage off Perth Amboy to 35 feet. 
Channels 35 feet deep from lower bay to upper bay, except 
between vicinity of Smith Creek and vicinity of Piles Creek to 30 
feet with anchorage 38 feet deep at Sandy Hook and 
Perth Amboy. 
Channel 35 feet deep from vicinity of Smith Creek to vicinity of 
Piles Creek. 
Widen entrance to Kill Van Kull to 1,400 feet narrowing to a minimum 
width of 1,000 feet. 
NEW YORK HARBOR, COLLECTION AND REMOVAL OF 
DRIFT (See Section 15 of Text) 
Allotment from appropriations made for New York Harbor and 
its immediate tributaries may be used for collection and removal 
of drift in these waterways. 
Carrying on this work as a separate and distinct project. 
Increase scope of project to include removal and disposal of derelict 
vessels, some deteriorated shore structures and debris along 
shores; and the repair of other shore structures; all subject to 
approval by Secretary of the Army and the President. 
Removal and disposal of derelict vessels, some deteriorated shore 
structures and debris along shores and the repair of other 
shore structures. 
NEW YORK HARBOR, ENTRANCE CHANNELS AND 
ANCHORAGE AREAS (See Section 16 of Text) 
Main-Ship-Bayside-Gedney to 30 feet for width of 1,000 feet 
(Dimensions fixed by Secretary of War, December 27, 1986 by 
authority of Act of August 5, 1886). 
Ambrose Channel (East Channel) to 40 feet. 
Maintenance of entrance channel under I head. 
Anchorage Channel, extension of Ambrose Channel into 
Upper Bay. 
Removal of Craven Shoal 
PORT CHESTER HARBOR, N.Y. (See Section 17 of Text) 
Entrance channel 12 feet deep, thence 10 feet deep to and and 
including turning basin, thence 3 feet deep to head 
of improvement. 
Rivers & Harbors Committee 
Doc. 17, 71st Cong., 2nd sess. 
H. Doc. 133, 74th Cong., 
1st sess. 
H. Doc. 233, 8 I1st Cong., 
Ist sess. 
H. Doc. 108, 98th Cong., 
1st sess. 
P.L. 91-611, 91st Cong., 
H.R. 1987 
P.L. 93-251, 93rd Cong. 
Annual Reports 1887, p. 62 and 
1888, p. 63 
H. Doc. 159, 55th Cong., 
2nd Sess. 
(contains published map.) 
H. Doc. 518, 63rd Cong., 
2nd sess. 
H. Doc. 557, 64th Cong., 
Ist sess. 
H. Doc. 1165, 60th Cong., 
2nd sess. 
Widening turning basin, dredging anchorage basin, and construct- Rivers and Harbors Committee 
ing fenders on east bank. Doe. 23, 70th Cong., 2nd sess. 
(contains published map). 
2-23 
July 3, 1930

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 10, 1872 
August 30, 1935 
October 27, 1965 
1965 Flood Control Act 
1974 Water Resources 
Development Act 
July 3, 1958 
Section 201 
Flood Control Act 
of 1965 
1976 Water Resources 
Development Act 
1976 Water Resources 
Development Act 
Section 101 (a) 
RONDOUT HARBOR, N.Y. (See Section 18 of Text) 
Parallel dikes, branch dike, and entrance channel 14 feet deep. 
Extension of 14 foot channel and for 12 foot channel. 
Extend 12 food channel from mile 1'.8 to 3.5 
S. Ex. Doc. 35, 42nd Cong., 2nd 
sess. Annual Report 1872, p. 810 
Rivers & Harbors Conm. 
Doc. 17, 73rd Cong., 2nd sess. 
H. Doc. 288, 89th Cong., 
Ist sess. 
(contains latest published map.) 
EAST ROCKAWAY INLET TO ROCKAWAY INLET AND 
JAMAICA BAY, N.Y. (See Section 23 of Text) 
Hurricane barrier, dikes, levees, floodwalls, fill, placement, stoplog 
structures, stairways, ramps, road raising, fishing platforms, annual 
nourishment. 
Authorized beach erosion control aspect to be constructed independent 
of the hurricane flood protection aspect of this 
project. 
SANDY HOOK TO BARNEGAT INLET, N.J. 
(See Section 24 of Text) 
Restoration of beach to minimum width of 100 feet at height of 10 
feet above mlw, and construction of 23 new groins and extension 
of 14 existing groins. 
ARDSLEY, N.Y (See Section 27 of Text) 
Channel improvement, concrete flume, flood walls, levees, various 
drainage structures. 
LIBERTY STATE PARK LEVEE AND SEAWALL, N.J. 
(See Section 28 of Text) 
Approximately 7,000 feet of seawall and elevated 
pedistrian walkway. 
PASSAIC RIVER BASIN, N.J. & N.Y., PHASE I 
(See Section 29 of Text) 
Advanced engineering and design study, involving reformulation 
of plans for flood control and water resource management. 
H. Doc. 215, 
89th Cong., 
1st sess. 
H. Doc. 332, 85th Cong., 
2nd sess., modified by Appr. Act 
for Energy & Water Dev. for FY 
85 
H. Doc. 215/89/1 
H. Rpt. 94-1702 
2-24

NEW YORK, N.Y. DISTRICT 
TABLE 2-C HUDSON RIVER, N.Y. 
FEATURES OF LOCK AND DAM INCLUDED IN EXISTING PROJECT 
(see Section 7 of Text) 
Location: 
Below Waterford 2.2 miles 
Above Battery, New York City 152.6 miles 
Locks: 
Clear Width 44.4 feet 
Greatest length available for full width 492.5 feet 
Lift at lowest stages 17.3 feet 
Depth on miter sills: 
Upper (at normal pool level) 16.3 
Lower (at lowest low water) 13.0 feet 
Character of foundation: Rock 
Kind of dam: Fixed Crest 
Type of construction: Concrete 
Complete: 1917 
Cost $1,463,014 
TABLE 2-E SUPERVISOR OF NEW YORK HARBOR 
(See Section 19 of Text) STATEMENT OF ACTIVITIES - FY 1989 
1. Number of Patrols 
a. Shore 241 
b. Vessel 239 
c. Air (helicopter) 5 
TOTAL 485 
2. Number of Inspections 
a. Shore Facilities 241 
b. Vessels 239 
TOTAL 480 
3. Disposition of Cases 
a. Voluntary Restoration 34 
b. After-the-fact Permit Applications Accepted 17 
c. Permit not required or already under permit 72 
d. Submitted for litigation to OCE or US Attorney 2 
e. Other Misc. 19 
f. Cases pending as of October 1, 1988 222 
TOTAL 366 
2-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-F RECONNAISSANCE AND CONDITION SURVEYS - FY 1989 
NAME OF PROJECT DATE SURVEY CONDUCTED 
NEW JERSEY 
Cheesequake Creek................................................ . .. ..... ............ * 
Keyport Harbor ....................................................................... ................ Aug 89 
Matawan Creek ............................................................... .. ..... .................. Aug 89 
Newark Bay Hackensack & Passaic Rivers................... ............... Apr 89, Jun 89, Aug 89 
Raritan River Cutoff ..................................................................... ......... .......... * 
R aritan R iver ...................................................... ......... . ...... .... . ................ Sep 89 
Shark River.......................................................................... .... ....... ...... . ..... * 
Shoal Harbor & Compton Creek ................................ ................................ Sep 89 
Shrewsbury River .................................................................... ................... Jul 89 
NEW YORK 
Bay Ridge & Red Hook Channels ..................................................................... Sep 89 
B ronx R iver ............................................................................................ Jun 89 
Brow ns C reek ......................................................................................... O ct 88 
Butterm ilk C hannel .................................................................................... Sep 89 
Eastchester C reek ........................................................................................... * 
East Rockaway Inlet ......................................................................... Jan 89, Sep 89 
East R iver .......................................... .................................................. Jun 89 
Fire Island Inlet .......................................................................................... * 
Flushing Bay & C reek .................................................................................. O ct 88 
G len C ove C reek ...................................................................................... Feb 89 
G reat South Bay....................................................................................... M ay 89 
H arlem R iver ........................................................................................... Sep 89 
H em pstead H arbor........................................................................................... * 
H udson R iver C hannel........................................................ ............................... * 
H untington H arbor .......................................................................................... * 
Jam aica B ay .................................................................................................. * 
Jones Inlet .............................................. ................................................ O ct 88 
Long Island Intra. W'Way ........................................................................... Aug 89 
Lake M ontauk H arbor ...................................................................................... * 
M am aroneck H arbor.................................................................................. Oct 88 
M anhasset Bay .............................................................................................. * 
M attituck H arbor ............................................................................................ * 
N ew tow n C reek ........................................................................................ A ug 89 
N ew Y ork H arbor ...................................................................................... M ar 89 
New York & New Jersey Channels .......................................................... Dec 88, Feb 89 
Port Chester Hatbor ...................................................... Dec 88 
Sheepshead Bay ....................................................................................... Feb 89 
Shinnecock Inlet........................................................ Apr 89 
Tarrytow n H arbor ........................................................................................... * 
*Items for which no date is furnished reflect costs for gathering data only. 
Total cost of Reconnaissance and Condition Surveys in Fiscal Year 1989 was $2,057,354. 
2-26

NEW YORK, N.Y. DISTRICT 
TABLE 2-G OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sept. 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Bronx River 
Browns Creek 
Burlington Harbor, Vt. 1 
Buttermilk Channel, N.Y. 
Channel between North & South Hero Island, 
Lake Champlain, Vt.' 2 
Coney Island Channel, N.Y. 
East River, N.Y. 
Echo Bay Harbor, N.Y.1 
Flushing Bay & Creek, N.Y. 
Glen Cove Creek, N.Y. 
Gordons Landing, Lake Champlain, Vt.12 
Gowanus Creek Channel, N.Y. 
Great Chazy River, N.Y. 
Great Kills Harbor, N.Y. 12 
Great Lakes to Hudson River Waterway, N.Y. 
Great South Bay, N.Y.1 
Greenport Harbor, N.Y. 1 
Harlem River, N.Y. 1 
Huntington Harbor, N.Y. 
Jamaica Bay, N.Y. 
Jones Inlet 
Keyport Harbor, N.J. 
Lake Montauk 
Larchmont Harbor, N.Y. 
Lemon Creek, N.Y. (Inactive) 23 
Little Neck Bay, N.Y. 1 
Mamaroneck Harbor, N.Y. 
Manhasset Bay, N.Y. (Inactive) 3 
Matawan Creek, N.J. 
Mattituck Harbor, N.Y. 
Milton Harbor, N.Y. 
Newtown Creek, N.Y. 
New Rochelle Harbor, N.Y. 12 
New York State Barge Canal, N.Y. 
Northport Harbor, N.Y. 1 
Orowoc Creek, N.Y.(Inactive) 3 
Otter Creek, Vt. 
Peconic River, N.Y.1 
Peekskill Harbor, N.Y.1 
Plattsburgh Harbor, N.Y. 
Port Henry Harbor, N.Y.' 
Port Jefferson Harbor 
Raritan River 
Raritan R-Arthur Kill Cut/Off, N.J. 
Rouses Point, Lake Champlain, N.Y.' 
Sag Harbor, N.Y. 1 
St. Albans Harbor, Lake Champlain, Vt.12 
Sandy Hook Bay, N.J. 
Sandy Hook Bay at Leonardo, N.J.1 2 
Saugerties Harbor, N.Y. 
1987 
1987 
1966 
1988 
1909 
1973 
1988 
1953 
1988 
1986 
1982 
1972 
1980 
1962 
1976 
1974 
1953 
1969 
1953 
1988 
1987 
1985 
1987 
1970 
1937 
1969 
1981 
1948 
1984 
1981 
1984 
1986 
1971 
1988 
1956 
1949 
1977 
1953 
1951 
1986 
1931 
1977 
1987 
1988 
1895 
1964 
1917 
1985 
1967 
1988 
2-27 
$1,149,946 
33,976 
706,414 s 
4,590,201 
31,000 
111,371 
32,723,662 
64,584 
2,102,905 
29,760 
34,750 
346,831 
18,000 
137,301 15 
266,857 
74,681 
3,616,119 
91,081 
4,545,753 
1,822,530 
40,475 
791,680 
76,065 
6,621 
1,741,210 19 
513,764 
21,000 
I77,925' 
151,373 18 
1,168,354 
73,214 8 
78,644 23 
60,254 
25,000 
19,400 
198,415 
69,406 25 
221,128 31 
1,551,470 
810,500 
98,468 
121,805 26 
3,125 
508,936 
56,470 
81,905 
$2,844,853 
673,369 
299,574 
4,392,907 
1,288 
294,109 
5,126,798 
21,571 
5,665,299 
130,760 
115 
255,291 
292,919 
88,029 
457 
1,290,469 
21,720 
480,777 
57,527 
4,814,926 
12,720,892 
868,630 
979,952 
267,768 
1,621 
537 
650,510 
4,636 
257,237 
1,063,786 
986,520 
1,690,748 
152,411 
11,487 
4,951 
27,059 
116,500 
66,037 
256,415 
1,299 
359,294 
13,701,319 
3,142,336 
249 
11,710 
385 
3,902,330 
93,964 
429,18028

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-G (continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sept. 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Shark River 
Sheepshead Bay, N.Y.1 
Shoal Harbor & Compton Creek, N.J. 
Shrewsbury River, N.J. 
Staten Island Rapid Transit Railway Co. 
bridge across Arthur Kill, N.Y. 
Sumpawanus (Babylon Creek) Inlet, N.Y.' 2 
Tarrytown Harbor, N.Y.' 
Wallabout Channel, N.Y.' 
Wappinger Creek, N.Y.N.Y.12 
Washington Canal and South River, N.J.' 
Waycake Creek, N.J. 23 
Westchester Creek 
Woodbridge Creek, N.J.' 
1,987 
1948 
1984 
1986 
1973 
1895 
1974 
1953 
1950 
1953 
1949 
1987 
1953 
150,000 
33,828 
124,572 20 
1,145,457 
7,730,476 
7,000 
69,836 
18,174 
13,000 
206,116 
175,933 
48,823 
1,161,722 
5,364 
1,227,183 
2,556,404 
431,199 
36,312 
44,691 
212,82730 
2,781 
3,871,311 
178,398 
1. Completed. 
2. No commerce reported. 
3. Awaiting local cooperation. 
5. A portion of this project is classified "inactive." 
6. Includes $69,036 for new work and $26,921 for maintenance 
for previous project. Excludes $10,000 for new work 
expended from contributed funds. 
8. Includes $43,175 for new work for previous projects. 
9. Includes cost of maintenance prior to July 1, 1886. 
Excludes $1,425,133 for rehabilitation. 
14. Excludes $94,366 for rehabilitation. 
15. Excludes $104,805 for new work expended from contributed 
funds. 
17. Excludes $19,546 for new work expended from contributed 
funds and $31,454 to be contributed. 
18. Excludes $119,276 required contributed funds and $72,619 
other contributed funds. 
19. Excludes $1,741,210 for new work expended from contributed 
funds. 
20. Includes $17,000 for new work for previous projects. 
21. Includes $169,700 for maintenance for previous 
projects. 
23. Excludes $15,000 for new work expended from contributed 
funds. 
24. Includes $16,369 for maintenance for previous projects. 
25. Excludes $1,000 for new work expended from contributed 
funds. 
26. Excludes $66,758 for rehabilitation. 
28. Includes $15,000 for maintenance for previous projects. 
30. Includes $84,934 for maintenance for previous projects. 
31. Includes costs for new work $171,427 and maintenance 
$10,646 for previous projects. 
32. Excludes $34,580 for new work from contributed funds. 
2-28

NEW YORK, N.Y. DISTRICT 
TABLE 2-H OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS
Cost to Sept. 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Atlantic Coast of N.J., Sandy Hoof to Barnegat Inlets 1959 
Fire Island Inlet to Jones Inlet, N.Y. 1981 18,044,667 217,899 
North Shore of Long Island, Suffolk County, N.Y. 1979 8,800,000 
Perth Amboy, N.J. 1966 - - 
TABLE 2-I OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report 
See Annual Operation and 
Projects Report For Construction Maintenance 
Adams, Hossie River Basin, Mass.1 
Bennington, Vt. 
Byram River at Pemberwick, Conn.1 '3 
East Barre Dam, Winooski River, Vt.' 
East Rockaway Inlet to Rockaway Inlet 
and Jamaica Bay, N.Y. (Part II) 
Elizabeth, N.J. 
Fire Island to Montauk Point, N.Y. 
Herkimer, N.Y. 
Hoosic Falls, Hoosic River Basin, N.Y.' 
Lamoille River, Vt.: Hardwich Dams4'5'6 
Missisquoi River at Richford, Vt.1'3 
North Adams, Hoosic River Basin, Mass. 
North Ellenville, N.Y. 
Rahway, N.J. 
Rahway, South Branch, N.J. 
Raritan Bay and Sandy Hook Bay, N.J. 
Rosendale, N.Y. 
Rutland, Otter Creek, Vt.4 
Sandburg Creek, Spring Glen, N.Y. 
Sawmill R. Elmsford & Greenburgh, N.Y. 
South Amsterdam, Mohawk River, N.Y.1 
South Ellenville, N.Y. 
South Orange, N.J. 
Staten Island, N.Y, 
Wappinger Creek at Pleasant Valley, N.Y.1'3 
Waterbury Reservoir Winooski River Basin, Vt. 
Winooski River, Vt.1 
Wrightsville Dam, Winooski River Basin, Vt. 
Yonkers,. N.Y. 
6,282,307 2 
670,000 
363,515 
2,898,334 
1964 
1974 
1959 
1963 
1976 
1985 
1984 
1973 
1956 
1939 
1965 
1968 
1978 
1971 
1979 
1981 
1975 
1963 
1976 
1987 
1967 
1984 
1981 
1983 
1959 
1976 
1940 
1970 
1984 
1,185,365 
54,165,128 
12,512,957 6 
1,240,255 9 
1,064,626 
238,169 
15,571,688 ' 
3,900,650 
973,142 8 
15,863,723 
11,0671,256 
3,684,966 
211,015 
109,702 
59,142 
1,564,976 
289,702 
6,857,484 
644,998 
142,075 
1,438,845 
5,897,427 
1,549,929 
13,641,771 10 
2-29 
- 
143,753 
262 
8,200

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-I (continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
1. Completed. 6. Includes $3,788,341 contributed funds. 
2. Excludes costs of $913,360 under other contributed 7. Excludes cost of $21,000 under other contributed funds. 
funds. 
8. Excludes cost of $51,500 under other contributed funds. 
3. Authorized by Chief of Engineers pursuant to Sec. 205, P8uthbl c oLnwg 8a8s, mened.9. 9. UUnnccoommpplleetteedd ppoorrttiioonn hhaass bbeeeenn ddeeaauutthhoorriizzeedd oonn AAuugust 
Public Law 858, 80th Cong. as amended. 5, 1977. 
4. Inactive. 10. Includes $622,871 contributed funds. 
5. Includes $213,507 emergency relief funds. 
TABLE 2-J SURVEYS 
Study Class Cost 
Navigation Studies 
Flood Control Studies 
Beach Erosion Studies 
Special Studies' 
TOTAL SURVEYS 
$700,634 
3,886,861 
1,534,125 
957,741 
7,077,361 
'Includes review of Authorized Projects, Inspection of Dams, Coordination Studies with Other Agencies, Planning Assistance to 
States, International Water Studies Investigations, Review of FERC Licenses and Preconstruction Engineering and Design. 
TABLE 2-L COSTS FOR FLOOD PLAIN MANAGEMENT SERVICES 
Studies and Services Cost 
Flood Plain Technical Services $52,847 
Flood Plain Management Unit 60,000 
TOTAL. 112,847 
TABLE 2-M DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed Operation 
See Annual And Funds Funds sad 
Projects Report For Authority Expended Construction Expended Maintenasce 
Bronx River, N.Y. 4'd 
Brown's Creek, N.Y. 
Cheesequake Creek, I.J.4' 
1981 
1980 
1953 
Aug. 1982 
Aug. 1977 
Aug. 1982 
1,149,946 
33,976 
40,000 
1,159,946 
33,976 S 
40,000 
'120,000 1,947,853* 
505,369 
30,675 
2-30

NEW YORK, N.Y. DISTRICT 
TABLE 2-M (continued) DEAUTHORIZED PROJECTS 
Coney Island Creek, N.Y. 4 '6 
East Rockaway (Debs) 
Inlet, N.Y. 
Elizabeth, N.J. 
Glen Cove Harbor, N.Y. 
Hudson River, NYC to 
Albany 4'18 
Huntington Harbor, N.Y. 
Irvington Harbor, N.Y. 
Lamoille River, Vt. 
Newark Bay, Hackensack 
and Passaic River, N.J.16 
N.Y. & N.J. Channels4' 18 
Portchester Harbor, N.Y. 2'3 
Proctor, Otter Creek, 
Basin, Vt.6'7 
Rahway River 6'7 
Raritan River, N.Y.4'6 
Rome Mohawk River, N.Y. 6'7 
Swanton Harbor, Vt. (Inactive) 6 
Ticonderoga River, N.Y.1'6 
Waterbury (1941 Act), Vt.7'6 
Waterford, N.Y. 6'7 
Westchester Creek, N.Y. 
1952 Aug. 1982 
1963 Aug. 1977 
1948 Aug. 1977 
1966 Aug. 1977 
1982 Aug. 1982 
1953 Aug. 1977 
1947 Aug. 1977 
1939 Aug. 1977 
1982 
1982 
1967 
1937 
1948 
1981 
1959 
1888 
1895 
1951 
1939 
1981 
Aug. 1982 
Aug. 1982 
Aug. 1977 
Aug. 1977 
Aug. 1982 
Aug. 1982 
Aug. 1982 
Aug. 1977 
Nov. 1983 
Nov. 1981 
Aug. 1982 
Aug. 1982 
69,489 
3,503,969 13 
60,481 
165,882 
69,489 
100,000 
1,622 
829,421 
60,481 
165,882 4'11 
49,035 68,581,451 
49,837 
433,470 
1,551,470 
7,000 
167,760 
9,253 
175,933 
19,546 
49,837 
433,470 
37,000 4 
1,617,470 s15 
7,000 
70,500 4 
16,500 
9,253 
175,933 
- 441,656 
- - 
66,000 
No commerce reported. 
Completed. 
A portion of this project is classified "inactive." 
Uncomplete portion deauthorized. 
Excludes $19,546 for new work expended from contributed 
and $31,454 to be contributed. 
Inactive. 
Entire project deauthorized. 
Excludes $71,423 for rehabilitation. 
Deferred. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
Under Section 12 Public Law 93-251. 
Includes $93,882 for Rehabilitation. 
Includes $10,000 expended from contributed funds. 
Includes $100,000 expended from contributed funds. 
Includes $19,546 expended from contributed funds. 
Includes $66,000 expended from contributed funds. 
1912 authorization. 
1935 authorization. 
1910 construction dikes. 
TABLE 2-N SECTION 107 
(See Section 22 of Text) 
Name of Project Cost to Sept. 30, 1989 
COMPLETE RECONNAISSANCE REPORT 
Belford, N.J. 
Keyport Harbor, N.J. 
LaPlatte R. Shelburne Bay, Vt. 
2-31 
59,391 
2,455 
51,566 
307 
10,113,903 
235 
1,260 
2,921,311 
I. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
$32,358 
39,516 
1,224

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 2-0 SECTION 103 
(See Section 26 of Text) 
Name of Project Cost to Sept. 30, 1989 
COMPLETE RECONNAISSANCE REPORT 
Asharoken Beach, Huntington, N.Y. $7,045 
TABLE 2-P SECTION 205 
(See Section 32 of Text) 
Name of Project Cost to Sept. 30, 1989 
COMPLETE RECONNAISSANCE REPORT 
Great Chazy River, Champlain, N.Y. $30,025 
Hackensack River, N. Milford, N.J. 502 
COMPLETE PLANS AND SPECIFICATIONS 
Ramapo River, Monroe, N.Y. 465 
Yonkers, Nepera Park, N.Y. 5,098 
CONTINUE CONSTRUCTION 
Wallhill River (Black Dirt), N.Y. 5,414 
COMPLETE CONSTRUCTION 
Passaic River Basin, N.Y. & N.J. 54,672 
TABLE 2-Q SECTION 14 
(See Section 33 of Tett) 
Name of Project Cost to Sept. 30, 1989 
COMPLETE RECONNAISSANCE REPORT 
Arnolds Bay, Vt. 
Crown Point, N.Y. 
Fire Island to Jones, N.Y. 
COMPLETE FEASIBILITY REPORT 
Pascack Brook, N.J. 
Spring Lake, N.J. 
COMPLETE PLANS AND SPECIFICATIONS 
Green Brook, Green Brook, N.J. 
Green Brook (Regional Center), N.J. 
$36,005 
1,717 
46 
14,545 
32,443 
97,900 
20,112 
2-32

PHILADELPHIA, PA DISTRICT * 
This district comprises a portion of southeastern New 
York, eastern Pennsylvania, western and southern New 
Jersey, northern and southeastern Delaware, and a small 
Part of northeastern Maryland embraced in the drainage 
basins tributary to the Atlantic Ocean from Manasquan 
River, NJ inclusive, to south boundary of Delaware. It also 
includes Chesapeake and Delaware Canal and approach 
channel thereto in Chesapeake Bay and Elk River, MD. 
IMPROVEMENTS 
Navigation Page 
1. Absecon Creek, NJ.......................................... 3-2 
2. Alloway Creek, NJ .......................................... 3-2 
3. Barnegat Inlet, NJ ......................................... 3-2 
4. Big Timber Creek, NJ..................................... 3-3 
5. Cape May Inlet 
to Lower Twp., NJ........................................... 3-3 
6. Cedar Creek, NJ............................................. 3-4 
7. Cohansey River, NJ...................................... 3-4 
8. Cold Spring Inlet, NJ...................................... 3.4 
9. Cooper River, NJ............................................. 3-4 
10. Delaware River between 
Philadelphia, PA ,and Trenton, NJ................ 3-5 
11. Delaware River, PA, NJ, and DE 
Philadelphia to the Sea................................... 3-5 
12. Indian River Inlet and Bay, DE ..................... 3-6 
13. Inland Waterway from Delaware River 
to Chesapeake Bay, DE, and MD................... 3-7 
14. Inland Waterway from Rehoboth Bay 
to Delaware Bay, DE....................................... 3-8 
15. Mispillion River, DE ...................................... 3-9 
16. Murderkll River, DE ..................................... 3-9 
17. Navigation Work Under Special 
A uthorization.................................................. 3-9 
18. New Jersey Intracoastal Waterway .............. 3-9 
19. Pepper Creek, DE.......................................... 3-10 
20. Schuylkill River, PA...................................... 3-10 
21. Wilmington Harbor, DE................................ 3-11 
Beach Erosion Control Page 
22. Shoreline Erosion Control ............................ 3-12 
23. Beach Erosion Control Work 
Under Special Authorization........................ 3-12 
Flood Control Local Protection Page 
24. Beltzville Lake, PA........................................ 3-12 
25. Blue Marsh Lake, PA.................................... 3-12 
26. Delaware Coast Protection, DE....................3-13 
27. Flood Control Work Under Special 
Authorization................................................ 3-13 
28. Emergency Bank Protection ......................... 3-13 
29. Francis E. Walter Dam, PA .......................... 3-13 
30. General Edgar Jadwin Dam and 
Reservoir, PA ................................................ 3-14 
31. Inspection of Completed Flood 
Control Projects............................................. 3-14 
32. Inspection of Non-Federal Levees ................ 3-14 
33. Prompton Lake, PA ....................................... 3-15 
34. Reconnaissance and Conditions 
Surveys ......................................................... 3-15 
35. National Emergency Preparedness.............. 3-15 
36. Tam aqua, PA ................................................ 3-15 
General Investigations Page 
37. Surveys ......................................................... 3-15 
38. Collection and Study of Basic Data.............. 3-16 
39. Preconstruction, Engineering and Design ... 3-16 
Tables Page 
TABLE 3-A Cost and Financial Statement........ 3-17 
TABLE 3-B Authorizing Legislation .................. 3-21 
TABLE 3-C Other Authorized 
Navigation Projects......................... 3-26 
TABLE 3-D Other Authorized Beach 
Erosion Control Projects................. 3-28 
TABLE 3-E Other Authorized Flood 
Control Projects............................... 3-28 
TABLE 3-F Multiple Purpose Project 
Including Power .............................. 3-29 
TABLE 3-G Deauthorized Projects..................... 3-29 
* All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at 
the end of this chapter. 
3-1

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
NAVIGATION 
1. ABSECON CREEK, NJ 
Location: This creek rises in and flows easterly 5 
miles through Atlantic County, NJ emptying into Ab.- 
secon Bay about 5 miles northwest of Atlantic City. (See 
U.S. Coast and Geodetic Survey Chart No. 1217.) 
Existing project: This provides for a channel 5 feet 
deep, at mean low water, 80 feet wide from deep water in 
Absecon Bay across the flats to the mouth of the creek, a 
distance of 1 mile thence 50 feet wide to the highway 
bridge at Absecon village a further distance of 2 miles, 
including a turning basin at the head of navigation. The 
mean range of tide is 3.4 feet. The extreme range of tide 
is from 1 foot below mean low water to about 1 foot above 
mean high water. Cost for new work for completed project 
was $11,935. The existing project was adopted by the 
River and Harbor Act of July 25, 1912 (H.Doc. 71, 62d 
Cong., 1st sess). The latest published map is in that 
document. (See Table 3-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation: None required. 
Terminal facilities: There are four pile and timber 
wharves and landings on this stream. The facilities, are 
considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: BCR update was accomplished. 
2. ALLOWAY CREEK, NJ 
Location: This creek rises in Salem County, NJ, flows 
southwesterly 15 miles below Philadelphia, PA. The 
drainage area is 60 square miles. The length of the tidal 
reach is about 14 miles. At the mouth and at Quinton the 
high-water widths are 260 feet and 102 feet, respectively; 
the low-water widths at the same points are 245 feet and 
90 feet. (See U. S. Coast and Geodetic Survey Chart No. 
294) 
Previous project: None 
Existing project: This provides for a channel 6 feet 
deep at mean low water beginning at Fosters Bottle, 1 
mile above the mouth, where a cut-off was provided, 
which shortened the distance 1 mile, thence upstream to 
Quinton, a distance of 8 miles, 75 feet wide to a point 
1,000 feet above Upper Hancock Bridge, and thence 60 
feet wide to Quinton, including dikes at "The Square," 
and above Upper Hancock Bridge, and an increased 
width at "The Canal" to 150 feet between low-water lines. 
The mean range of tide at the mouth is 6 feet, at Hancock 
Bridge 5 feet, and at Quinton 4 feet. The extreme range 
of tide is from about 1 foot below mean low water to about 
2 feet above mean high water. 
The existing project was adopted by the following River 
and Harbor acts: The act of September 19, 1890 (H. Doc. 
No. 60, 51st Cong., 1st sess., and Annual Report for 1890, 
p. 910), provided for all features except the dike above 
Upper Hancock Bridge, which was added in 1896, and the 
cut-off at Fosters Bottle, which was provided for by the 
river and harbor act of March 2, 1907. There is no published 
map. 
Local cooperation: As required by law, all land 
needed for the cut-off at Fosters Bottle was furnished by 
local interests free of cost to the United States, title to the 
land having been approved by the Department of Justice, 
July 30, 1908. 
Terminal facilities: There are two pile and timber 
wharves on this stream. All are privately owned, but may 
be used by the public when not in use by owners. The 
facilities are adequate for existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: BCR economic update was completed. 
3. BARNEGAT INLET, NJ 
Location: On the east coast of New Jersey about 50 
miles south of Sandy Hook, between Island Beach on the 
north and Long Beach on the south (See U.S.Coast and 
Geodetic Chart Nos. 825 and 1216). This inlet is main 
entrance to Barnegat Bay, largest of the bays on New 
Jersey coast which are separated from the ocean by 
narrow barrier beaches. 
Previous Project: None 
Existingproject: The existing project, adopted as HD 
73-19 in 1935 and modified as HD 74-85 in 1937 and HD 
79-358 in 1946, provides for a channel eight feet deep 
through the inlet and ten feet deep through the outer bar, 
protected by two converging stone jetties and a channel 
of suitable hydraulic characteristics extending in a 
northwesterly direction from the gorge in the inlet to 
Oyster Creek channel and through the latter channel to 
deep water in the bay. The project was modified in 1946 
to provide for the maintenance of a channel eight feet 
deep and 200 feet wide to connect Barnegat Light Harbor 
with the main inlet channel. The project length is about 
4.5 miles. (For details see page 203, Annual Report 1964.) 
The Supplemental Appropriation Act of 1985 contained 
language stating that the existing project has not 
worked as projected and, in fact, has created a hazard to 
navigation. As a result, the following administratively 
approved modifications are to be constructed as design 
deficiency correction measures: a new south jetty 4,270 
feet in length along an alignment generally parallel to the 
existing north jetty, extending from the existing groin 
located near the Barnegat Lighthouse to the tip of the 
existing south jetty; a navigation channel 300 feet wide 
to a depth of 10 feet below mean low water from the outer 
bar in the Atlantic Ocean to the north end of the existing 
sand dike in Barnegat Bay; remove the shoal located 
between the north jetty and the proposed navigation 
channel; jetty sport fishing facilities on the new jetty. All 
dredged material from initial construction would be 
placed on the shores of Barnegat Light between the 
existing and new south jetties, and would be stabilized by 
vegetation and sand fence. Dredged material from main- 
3-2

PHILADELPHIA, PA. DISTRICT 
tenance operations would be placed on the down draft 
beaches, the area between the existing and new south 
jetties, or in other locations as determined by a shoreline 
monitoring program. Estimated cost for new work (October 
1987) Federal share is $27,700,000 and non-Federal 
is $15,200,000. (See Table 3-A at end of chapter for total 
cost for existing project to Sept. 30, 1989.) 
Local cooperation: Fully complied with. A local 
cooperation agreement for the approved modification was 
executed on 19 May 1986 and a modification to the local 
cooperation agreement was executed on 20 March 1987. 
Terminal facilities: There are four docks or terminals 
in inner harbor at Barnegat Light which furnish 
adequate facilities for present commerce of locality. 
Operations during fiscal year: New Work, contract: 
Construction of South Jetty and hydrographic survey. 
New Work, hired labor: Engineering and design, and 
supervision and administration. 
Maintenance, hired labor: Work included general 
maintenance, surveys, and supervision and administration. 
Work also included maintenance dredging by 
Dredge CURRITUCK from October 1, 1988 to November 
2, 1988 removing 50,000 cubic yards of material at a cost 
of $154,000. Dredging by the U. S. Government Side 
Casting Dredge Merritt was accomplished from February 
23, 1989 to May 14, 1989 removing 85,000 cubic yards of 
material at a cost of $342,300. 
From August 9, 1989 to September 8, 1989, U. S. 
Government Side Casting Dredge FRY did dredging 
removing 40,000 cubic yards of material at a cost of 
$213,900. 
4. BIG TIMBER CREEK, NJ 
Location: This creek rises in Camden and Gloucester 
Counties, NJ, and with its south branch flows 
northwesterly 16 miles along the boundary line between 
the two counties, emptying in to Delaware River opposite 
the south portion of Philadelphia, PA. (See U.S. Coast and 
Geodetic Survey Charts Nos. 280 and 295.) 
Existing project: This provides for a channel 10 feet 
deep at mean low water, generally 75 feet wide from the 
10-foot contour in Delaware River to the mouth and 
within the creek to Marters sand plant, 3 1/2 miles above 
the mouth, and thence 60 feet wide to Clements Bridge, 
5 miles above the mouth, including four cutoffs. The total 
length of the section included in the project is about 5 1/2 
and at Clements Bridge 4.3 feet. The extreme tidal range 
is from about 1 1/2 feet below mean low water to about 2 
feet above mean high water. 
The cost for new work for the completed project was 
$58,665, exclusive of $50,000 contributed funds. (See 
Table 3-B at end of chapter for Acts authorizing existing 
project.) 
Local cooperation: Fully complied with. 
Terminal facilities: There are four wharves and one 
boatyard for the repair and storage of small boats at 
Westville. The wharves are privately owned but open to 
public use. The facilities are considered adequate for 
existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: BCR update was completed. 
CAPE MAY INLET TO LOWER TWP., NJ 
Location: The proposed project is located in Cape May 
County and extends along the beach front from the northern 
side of Cape May Inlet to the boundary of Lower 
Township, and Cape May City. 
Existing project: The plan, as presented in HD 94- 
641, was authorized for the Phase I Design Memorandum 
Stage of Advance Engineering and Design by Section 
101a of the Water Resources Development Act of 1976, 
proposes the following features: breakwater on the 
updrift side of Cape May Inlet; beachfill from Cape May 
Inlet to Cape May Point; provision of a dune with sand 
fence and grass from Cape May Inlet to Wilmington 
Avenue; construction of two groins in Cape May City and 
seven groins in Lower Township; inclusion of all groins 
comprising the existing project; and periodic nourishment 
of the beaches and maintenance of the dune and 
dikes. 
The Phase I GDM, completed in August 1980 and 
approved by the Chief of Engineers in December 1981, 
determined that only beach erosion control measures in 
Cape May City are warranted. The plan proposed in that 
document consists of modifying the existing navigation 
project for Cape May Inlet to provide; a weir-breakwater 
at Cape May Inlet with construction being deferred pending 
demonstration of need; two new groins at Trenton and 
Baltimore Avenues in Cape May City; placement of 
beachfill between Cape May Inlet and the terminal groin 
at Third Avenue in Cape May City; maintenance of two 
new groins and existing groins in Cape May; periodic 
beach maintenance with material obtained from deposition 
basin on the northeast side of Cape May Inlet; and 
institution of a beach monitoring program in Lower 
Township area. Project estimate costs (October 1987) is 
Federal, $74,500,000 non-Federal costs are $8,300,000. 
The existing authority is for Phase I studies as 
provided by Section 101(a) of the Water Resources 
Development Act of 1976 in accordance with the provision 
of House Document 94-641. Continuation of planning and 
engineering for this proposed project was initiated in 
October 1977. The Phase I GDM was completed in 
August 1980 and approved by the Chief of Engineers in 
December 1981. Phase II AE&D studies were completed 
in July 1983. The project was authorized for separable 
elements under Section 501(a) of the Water Resources 
Development Act of 1986, PL 99-662. (See Table 3-A at 
end of chapter for total cost for existing project to Sept. 
30, 1989.) 
Local cooperation: The State of New Jersey furnished 
a letter of intent on 6 May 1981 regarding their 
3-3
5.

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
willingness to comply with the above items of local 
cooperation. In addition, a draft Section 221 local 
cooperation agreement has been coordinated with letter 
of intent on 31 May 1983 regarding compliance with the 
items of local cooperation. 
Operations during fiscal year: New work, contract: 
Work was accomplished on Groin contract, and USCG 
Beachfill contract. 
New Work, hired labor: Work was accomplished on 
reevaluation of benefits, plans and specifications, and 
supervision and administration. 
6. CEDAR CREEK, NJ 
Location: In the northeastern corner of Sussex County, 
DE, approximately five miles east of the Town of 
Milford. The area is accessible via State Route 36. 
Existing project: Cedar Creek, with headwaters in 
Sussex County, meanders northward through coastal 
salt marsh to its terminus at Mispillion River. The creek 
currenty ranges in depth from 13 feet below mean low 
water at the Route 36 bridge to less than 5 feet at several 
locations. The channel width varies from approximatel 
75 feet to 250 feet. Tidal range in the lower reaches of 
the creek is approximatel 4 feetExisting project was 
adopted by the Chief of Engineers, 10 December 1979, 
under the small navigation program, section 107, River 
and Harbor Act of 1960. 
Local cooperation: Fully complied with. 
Terminal facilities: Five marinas are located along 
the lower stretch of the creek, with residential areas 
being situated near the Delaware Bay shore. The area is 
sparsely poplulated, and there are no major metropolitan 
areas nearby. 
Operations during fiscal year: Maintenance, hired 
labor: Ecomomic analysis and BCR update. 
7. COHANSEY RIVER, NJ 
Location: Rises in Salem County, NJ, flows southerly 
and southwesterly 27 miles through Cumberland County, 
and empties into Delaware Bay about 62 miles below 
Philadelphia, PA.(See Coast and Geodetic Survey Chart 
1218).. 
Previous projects: For details see page 1785, Annual 
Report for 1915,and page 348, Annual Report for 1938. 
Existing project: A channel 12 feet deep, 100 feet 
wide from that depth in Delaware Bay through a neck of 
land at the mouth and within the river to the south side 
of Glass Street in Bridgeton, 19 miles above the mouth; 
thence a channel 8 feet deep, 100 feet wide to Broad 
Street; and thence 75 feet wide to Commerce Street 
Bridge, 19.25 miles above the mouth; and a turning basin 
12 feet deep and 800 feet long formed by widening the 
channel on the south side to a maximum widthof 250 feet 
just below Glass Street. Section included in project is 
about 19.5 miles long. All depths refer to the plane of 
mean low water. Extreme tidal range is from about 2 feet 
below mean low water to about 3 feet above mean high 
water. Completed project cost $110,756 for new work, 
exclusive of amounts expended on previous projects.(See 
Table 3-B at end of chapter for Acts authorizing existing 
project. See Table 3-A at end of chapter for total cost for 
existing project to Sept. 30, 1989.) Existing project was 
completed in 1939. 
Local cooperation: Complied with except local interest 
must furnish suitable spoil-disposal areas for 
required maintenance. 
Terminal facilities: Twenty wharves, of which 16 are 
at Bridgeton and 4 at Greenwich. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: Work included plans and specifications on dredging 
and supervision and administration. 
COLD SPRING INLET, NJ 
Location: In Cape May County, southern New Jersey, 
about 3 miles east of Cape May City and about 16 miles 
northeast of Delaware breakwater. Inlet connects Cape 
May Harbor and New Jersey Intracoastal Waterway with 
the Atlantic Ocean and is about 1 mile long. (See Coast 
and Geodetic Survey Charts 234, 827 and 1219). 
Existing project: An entrance channel 25 feet deep 
and 400 feet wide, protected by two parallel jetties, and 
extending from the 25-foot depth curve in the Atlantic 
Ocean to a line 500 feet harborward of a line joining the 
inner ends of the jetties, thence 20 feet deep and 300 feet 
wide to deep water in Cape May Harbor. The total length 
of the section included in the project is about 2.25 miles. 
Extreme tidal range, due to ocean storms, is about 11 feet. 
Project was completed in 1942.(For details see page 238, 
Annual Report for 1962. See table at end of chapter for 
Acts authorizing existing project. See Table 3-A at end 
of chapter for total cost for existing project to Sept. 30, 
1989.) 
Local cooperation: Complied with Act of 1907, except 
work of deepening and enlarging inner harbor which 
is 80 percent complete. 
Terminal facilities: See page 238 Annual Report for 
1962. 
Operations during fiscal year: Maintenance, hired 
labor: Work included maintenance dredging by U. S. 
Government Side Casting Dredge Merritt from October 
1, 1988 to October 7, 1988 removing 5,000 cubic yards of 
material at a cost of $27,300. From September 1989 to 
September 30, 1989, U. S. Government Side Casting 
Dredge FRY did dredging removing 20,000 cubic yards of 
material at a cost of $151,800. Work also included plans 
and specifications. 
9. COOPER RIVER, NJ 
Location: This river rises in Camden County, NJ, 
3-4
8.

PHILADELPHIA, PA. DISTRICT 
flows northwesterly 13 miles, passing through the northern 
part of the city of Camden, and empties into Delaware 
River opposite the central portion of Philadelphia, PA. 
(See U.S. Coast and Geodetic Survey Charts Nos. 280 and 
295.) 
Existing project: This provides for a channel 12 feet 
deep at mean low water and 70 feet wide in Delaware 
River to the mouth and within the river to what was 
formerly Brownings Chemical Works, 1 1/2 miles above 
the mouth. The total length of the section included in the 
project is about 1 3/4 miles. The mean tidal range at the 
mouth is 6 feet. The extreme tidal range is about 14 feet. 
The cost for new work for the completed project was 
$33,102. 
The existing project was adopted by the River and 
Harbor Act of June 3, 1896 (H.Doc. 176, 53d Cong., 3d 
sess., and Annual Report for 1895, page 1102 et seq.) The 
latest published map is in House Document 134, 63d 
Congress, 1st session. 
Local cooperation: None required. 
Terminal facilities: There are 11 wharves on the 
river, all in the city of Camden; 10 are privately owned 
and 1 is owned by the city. The facilities are considered 
adequate for existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: BCR update was accomplished. 
10. DELAWARE RIVER BETWEEN 
PHILADELPHIA, PA, AND 
TRENTON, NJ 
Location: Rises in southeastern New York, flows 
generally southerly 367 miles, forming boundary line 
between New York and New Jersey on the east and 
Pennsylvania and Delaware on the west, and empties 
into Delaware Bay.(See U.S.Coast and Geodetic Survey 
Charts 1218, 280, 294, 295, and 296.) 
Previous projects: For details see page 1778 of annual 
report for 1915, page 311 of Annual Report for 1924, 
page 220 of Annual Report for 1934, and page 296, Annual 
Report for 1938. 
Existing project: A channel from Allegheny Avenue, 
Philadelphia, 23.5 miles to upstream end of Newbold 
Island 40 feet deep and 400 feet wide, with suitable 
widening of bends, including relocation of channel at 
Delair Railroad bridge, and reconstruction of bridge, 
thence 5.5 miles to upper end of Trenton Marine Terminal, 
35 feet deep and 300 feet wide, with a turning 
basin 800 feet wide and 1,700 feet long at the terminal; 
and maintenance of a channel 12 feet deep and 300 feet 
wide from upper end of 34-foot channel to Penn Central 
railroad Bridge at Trenton, dredged under a previous 
project. Project also provides for an auxiliary channel 20 
feet deep and 200 feet wide east of Burlington Island, 
extending easterly from main channel to upper end of 
U.S.Pipe and Foundry Co.'s property at East Burlington, 
with a turning basin 450 feet wide at upper end; for initial 
excavation, only, of a cross channel 8 feet deep and 200 
feet wide through artificial island opposite Delanco, NJ, 
and for construction of such bank protection works as 
may be necessary. Section included in project is about 
30.5 miles long, excluding auxiliary channel east of Burlington 
Island, which is 1.4 miles long, and cross channel 
opposite Delanco. Lower end is about 55 miles above river 
mouth at Liston Point and about 105 miles above Harbor 
of Refuge at mouth of Delaware Bay. Freshets, which 
occur usually during February and March, attain a 
height of 9 to 20 feet above mean low water in the vicinity 
of Trenton. Navigation is occasionally suspended during 
a portion of winter months due to ice. Existing project is 
90 percent complete. A 40-foot channel under the 1954 
modification from Allegheny Avenue to upper end of 
Newbold Island was completed April 1964. Work remaining 
is dredging from upper end of Newbold Island to 
Trenton Marine Terminal and widening turning basin at 
terminal which is in deferred category. (See Table 3-B at 
end of chapter for Acts authorizing existing project. See 
Table 3-A at end of chapter for total cost for existing 
project to Sept. 30, 1989.) 
Local cooperation: Modification authorized by 1954 
River and Harbor Act provides local interests must provide 
suitable terminal facilities, furnish lands and 
rights-of-way for construction and future maintenance, 
and hold the United States free from damages. Local 
interest complied with requirements, except city of Trenton 
has not provided suitable terminal facilities. 
Terminal facilities: There are 21 piers, wharves, and 
docks from Allegheny Avenue, Philadelphia, PA to Trenton, 
NJ facilities are considered adequate for existing 
commerce. (For details see Port Series No. 8 (revised 
1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, contract: 
Stream gaging by USGS and maintenance 
dredging by Gates Construction Company from October 
1, 1988 to April 11, 1989 removing 1,142,465 cubic yards 
of material at a cost of $4,498,431 was accomplished. 
Maintenance, hired labor: Work included general 
maintenance, surveys, BCR update, engineering and 
design, and supervision and administration was accomplished. 
11. DELAWARE RIVER, PA, NJ, 
AND DE, PHILADELPHIA TO 
THE SEA 
Location: See U.S.Coast and Geodetic Survey Charts 
1218, 394, 295, and 280. 
Previous projects: For details see page 1779 of Annual 
Report for 1915, and page 299, Annual Report for 
1938 
Existing project: Provides for a channel from deep 
water in Delaware Bay to a point in the bay, near Ship 
John Light, 40 feet deep and 1,000 feet wide; thence to 
Philadelphia Naval Base, 40 feet deep and 800 feet wide, 
3-5

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
with 1,200-foot width at Bulkhead Bar and 1,000-foot 
width at other bends; thence to Allegheny Avenue, 
Philadelphia, PA, 40 feet deep and 500 feet wide through 
Horseshoe Bend and 40 feet deep and 400 feet wide 
through Philadelphia Harbor, along west side of channel; 
and for anchorages at Reedy Point, Deepwater Point, 
Marcus Hook, and Mantua Creek, each 40 feet deep and 
2,300 feet wide with respective length of 8,000, 5,200, 
12,650, and 11,500 feet; anchorage at Gloucester 30 feet 
deep and about 3,500 feet long. Project also provides for 
construction of dikes and training works for regulation 
and control of tidal flow; for maintenance of an area on 
north side of channel opposite Philadelphia Naval Base 
between Shipway 3 and Schuylkill River to 40 feet deep 
and width of 150 feet on Mifflin Range and 200 feet on 
West Horseshoe Range; and for maintenance of any areas 
dredged by local interests to 35 feet deep between channel 
and a line 100 feet channelward of pierhead line between 
Point House wharf and Philadelphia Naval Base, when 
in opinion of Chief of Engineers such areas are so located 
as to be of benefit to generate navigation. Section included 
in project is about 96.5 miles long. All depths refer 
to plane of mean low water. Under influence of heavy and 
long-continued winds extreme tidal range is about 14 
feet. Normal maximum velocity of tidal currents in the 
dredged channel varies between 2 and 3.5 miles per hour. 
Storm tides may increase maximum to as much as 4.5 
miles per hour. Estimated cost for new work is 
$71,630,000 (July 1972) exclusive of amounts expended 
on previous projects. Channel to 37 deep and 500 feet 
wide through Horseshoe Bend and 37 feet deep and 60 
feet wide through Philadelphia Harbor along east side of 
channel and Port Richmond anchorage to 37 feet deep, 
except for that portion of channel which forms a part of 
40 feet deep and 400 feet wide channel portion is to be 
restudied and excluded from foregoing cost estimate. 
Estimated cost (July 1960) of this portion of project is 
$2,951,000. Existing project, excluding work deferred for 
restudy, is about 66 percent complete. The 40-foot channel 
from Naval Base to the sea was completed in 1942. 
Dredging Naval Base to Allegheny Avenue to 40 feet deep 
was completed in 1962. Enlarging anchorage at Marcus 
Hook was completed in 1967. Work remaining is to construct 
new anchorages at Reedy Point and Deepwater 
Point, and enlarge Mantua Creek anchorage, channel 
dredging from 35 to 37 feet deep over a width of 500 feet 
through Horseshoe Bend and about 600 feet through 
Philadelphia Harbor, and deepening Port Richmond 
Anchorage to 37 feet, all of which have been deferred for 
restudy. (See Table 3-B at end of chapter for Acts 
authorizing existing project. See Table 3-A at end of 
chapter for total costs for existing project to Sept. 30, 
1989.) 
Local cooperation: Requirements under 1938 River 
and Harbor Act for maintaining channel and anchorage 
in Philadelphia Harbor annually by cities of Philadelphia 
and Camden were removed (see 1962 Annual Report for 
details). 
Terminal facilities: There are 217 piers, wharves, 
and docks between Allegheny Avenue, Philadelphia and 
the sea, 135 on the waterfront of Philadelphia, Camden, 
and Gloucester, and 82 below Philadelphia. Facilities are 
considered adequate for existing commerce. (For further 
details see Port Series Nos. 7, revised 1967, and 8, revised 
1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, contract: 
Work included general maintenance of disposal 
area and construction of dikes and sluices. Maintenance 
dredgingby American Dredging Company from 1 October 
1988 to 29 March 1989 removing a total of 2,968,505 cubic 
yards of material at a cost of $5,009,355; and from 5 
December 1988 to 18 December 1988 removing 50,000 at 
a cost of $352,186. Dredging was accomplished by Norfolk 
Dredging Company from 10 August 1989 to 30 September 
1989 removing 1,050,000 cubic yards of material at a cost 
of $1,110,000 and by Great Lakes Dredge & Dock Company 
form 22 July 1989 to 31 August 1989 removing 
100,000 cubic yards of material at a cost of $1,060,067. 
Maintenance, hired labor: Work included construction 
of dikes and sluices, disposal ditching, and plans and 
specifications on maintenance dredging, subsurface testing, 
engineering and design, and supervision and 
administration. Dredging by U.S. Government Hopper 
Dredge McFarland at the Brandywine Range removing 
271,000 cubic yards of material at a cost of $814,100 from 
23 July 1989 to 16 August 1989; at the Reedy Island 
Range removing 141,500 cubic yards of material at a cost 
of $591,150 from 16 August 1989 to 2 September 1989; at 
the Baker Range removing 123,800 cubic yards of 
material at a cost of $420,000 from 02 September 1989 to 
14 September 1989; and the Reedy Island Range removing 
115,525 cubic yards of material at a cost of $560,000 
from 15 September 1989 to 30 September 1989. 
12. INDIAN RIVER INLET 
AND BAY, DE 
Location: Indian River rises in Sussex County, DE, 
and flows easterly 13 miles into Indian River Bay which 
is a shallow lagoon 6 miles long and 2 miles wide on the 
Delaware Coast about midway between Cape Henlopen 
and the Maryland State line. The inlet is an opening 
through the barrier beach separating Indian River Bay 
and the Atlantic Ocean (See U.S.Coast and Geodetic 
Survey Chart No.1219.) 
Previous projects: Adopted by River and Harbor Act 
of August 2, 1882. For further details see page 744, 
Annual Report for 1888. 
Existing project: This provides for the fixation of the 
inlet by the construction of two parallel jetties of steelsheet 
pile and stone design extending to approximately 
the 14-foot depth curve in the ocean, and for dredging an 
entrance channel 15 feet deep and 200 feet wide, for a 
distance of 7,000 feet inshore from the jetties; thence a 
channel 9 feet deep, 100 feet wide in the bay, and 80 feet 
wide in the river, to and including a turning basin 9 feet 
deep, 175 feet wide, and 300 feet long at Old Landing; 
thence a channel 4 feet deep and 60 feet wide to the 
highway bridge at Millsboro. The project also provides 
3-6

PHILADELPHIA, PA. DISTRICT 
that the interior channel dimensions may, at the discretion 
of the Chief of Engineers, be modified as found 
desirable to increase the hydraulic efficiency of the channel, 
without increasing the cost. The total length of the 
section included in the project is about 13.75 miles. All 
depths refer to the plane of mean low water. The extreme 
tidal range at the highway bridge is about 6 feet. Existing 
project was completed in 1951. For details see Annual 
Report for 1963.(See Table 3-B at end of chapter for Acts 
authorizing existing project. See Table 3-A at end of 
chapter for total costs for existing project to Sept. 30, 
1989.) 
Local cooperation: Fully complied with except that 
local interest are required to furnish suitable areas for 
disposal of dredged material during maintenance as and 
when needed, and provide terminal facilities. 
Terminal facilities: There is a privately owned basin 
with berthing facilities for small boats located .75 miles 
west of the highway bridge near the inlet and .25 miles 
north of the inlet channel, connected therewith by a 
channel 6 feet deep and 40 feet wide; a U.S. Coast Guard 
wharf on the north side of the inlet channel in the same 
locality; and two wharves at Oak Orchard in Indian River 
Bay. The facilities are considered adequate for existing 
commerce. 
Operations during fiscal year: Maintenance, contract: 
Work included inlet scour and repair to South Jetty. 
Maintenance, hired labor: Work included inlet scour 
and supervision and administration. 
13. INLAND WATERWAY FROM 
DELAWARE RIVER TO 
CHESAPEAKE BAY, DE, 
AND MD 
Location: The Waterway begins at Reedy Point on 
Delaware River, about 41 miles below Philadelphia, PA, 
and passes through the sea level Chesapeake and 
Delaware Canal, a distance of 14 miles, to Back Creek, at 
Chesapeake City, MD. It then passes for 5 miles down 
Back Creek, thence 9 miles down Elk River to 
Chesapeake Bay and thence 18 miles down Chesapeake 
Bay to a point near Pooles Island. A branch channel 
connects Delaware River at Delaware City, DE, with 
main channel at a point about 1.5 miles west of Reedy 
Point.(See U.S.Coast and Geodetic Survey Charts 294, 
1226, 570, and 572.) 
Previous projects: For details see Annual Report for 
1934, page 242, and Annual Report for 1938, page 312. 
Existing project: A channel 35 feet deep and 450 feet 
wide from Delaware River through Elk River and 
Chesapeake Bay to water of natural 35-foot depth in 
Chesapeake Bay including a cutoff at Penn Central Railroad 
crossing, and having a maximum radius of 
curvature of 7,000 feet at bends; a high-level, fixed railroad 
bridge with vertical clearance of 135 feet and 
horizontal clearance of 600 feet at the railroad crossing 
over the cutoff (economic study of railroad crossing requested 
by Office of Management and Budget resulted in 
construction of a single track vertical lift bridge in lieu of 
a high-level fixed railroad bridge); high-level fixed highway 
bridges over canal at Reedy Point, St. Georges, 
Summit, and Chesapeake City; a bascule drawbridge 
across Delaware City Branch Channel; extension of 
entrance jetties at Reedy Point; and anchorage in Elk 
River, 35 feet deep and 1,200 feet wide, with an average 
length of 3,700 feet; enlargement of anchorage and moor. 
ing basin in Back Creek to afford an area about 400 feet 
wide, 1000 feet long, and 12 feet deep;dredging Delaware 
City Branch Channel to 8 feet deep and 50 feet wide, and 
deepening existing basin to same depth; revetment of 
banks of canal as required between Delaware and Elk 
Rivers, and on banks of Delaware City Branch Channel 
east of Fifth Street Bridge; and construction of 
bulkheads. Total of section included in project, excluding 
Delaware City Branch Channel, which is about 2 miles 
long, is about 46 miles. All depths refer to plane of low 
water in Delaware River. Extreme tidal range is from 6.3 
feet above mean high water to 3 feet below mean low 
water. Existing project is about 89 percent completed. 
Channel 27 feet deep and 250 to 400 feet wide. Delaware 
River to Pooles Island, completed in 1938. High-level 
fixed highway bridges were completed at St. Georges 
(4-lane) in 1942; at Chesapeake City (2-lane) in 1949; and 
at Summit (4-lane) in 1960. Relocation of Penn Central 
Railroad bridge was completed December 21, 1965. Enlargement 
to 35 feet deep and 450 feet wide St. Georges 
and Summit bridges and Summit and Goose Island was 
completed on June 20, 1972 and February 18, 1972, 
respectively. Removing the old Penn Central railroad 
bridge was completed on January 21,1972. Channel work 
for Part II is about 87 percent complete. Work remaining 
consists of completing channel enlargement to 35 feet 
deep and 450 feet wide between Reedy Point Bridge and 
St. Georges Bridge; widening and deepening the channel 
between Delaware River and Reedy Point Bridge, the 
completion of recreation facilities, and miscellaneous 
completion items. Deepening of the Delaware City 
Branch Channel from 6 to 8 feet from a point 400 feet east 
of Fifth Street Bridge to its junction with the canal has 
been deferred for study. 
Original cost of canal including purchase was 
$10,709,755; estimated cost of new work for modifications 
of 1935 and 1954 is federal cost $135,300,000 and nonfederal 
cost $15,234,000 (October 1987). Major 
Rehabilitation of St. Georges and Summit Bridges are 
estimated at $23,700,000 federal cost. Portion of project 
comprising completion of Delaware City Branch Channel 
from a point 400 feet east of Fifth Street Bridge to its 
junction with canal is to be restudied and excluded from 
foregoing estimate. Estimated cost of this portion is 
$145,000 (July 1954).(See Table 3-A at end of chapter for 
total costs for existing project to Sept. 30, 1989. See Table 
3-B at end of chapter for Acts authorizing existing 
project.) 
Local cooperation: River and Harbor Act of 1954 
provided that local interests furnish lands and rights-ofway 
required for bridges. Assurances accepted and 
3-7

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
approved February 16, 1955. Requirements for Summit 
and Reedy Point Bridges have been met. 
Terminal facilities: Ample mooring facilities at eastern 
and western ends of canal and bulkheads at Delaware 
City and St. Georges were constructed by the United 
States. A small-boat harbor was provided and a wharf 
constructed at Chesapeake City. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year: Maintenance, contract: 
Work included aerial mapping, and painting of 
Summit Bridge. There was also maintenance dredging by 
Great Lakes and Dock Company from 22 November 1988 
to 28 December 1988 removing a total of 773,560 at a cost 
of $1,430,523. 
Maintenance, hired labor: Work included general 
maintenance and design of disposal areas and bridges, 
maintenance of rip-rap, roadways, canal banks, night 
lighting, building, grounds, and banks. Also accomplished 
was environmental drainage of disposal 
areas, lease of equipment, bridge inspections, engineering 
surveys, environmental monitoring, and advance 
maintenance dredging. Also accomplished were plans 
and specifications, sub-surface testing of disposal areas, 
mosquito control, construction of dikes and sluices, ditching, 
operation and maintenance of museum, engineering 
and design, and supervision and administration were 
completed. 
14. INLAND WATERWAY from REHOB(YOTH 
BAY TO DELAWARE BAY, DE & MD 
Location: The Waterway begins at Reedy Pint on 
Delaware River, about 41 miles below Philadephia, PA, 
and passes through the sea level Chesapeake and 
Delaware Canal, a distance of 14 miles, to Back Creek, at 
Chesapeake City, MD. It then passes for 5 miles down 
Back Creek, thence 9 miles down Elk River to 
Chesapeake Bay and thence 18 miles down Chesapeake 
Bay to a point near Pooles Island. A branch channel 
connects Delaware River at Delaware City, DE, with 
main channel at a point about 1.5 miles west of Reedy 
Point. (See U.S.Coast and Geodetic Survey Charts 294, 
1226, 570, and 572. 
Previous project: For details see Annual Report for 
1934, page 242, and Annual Report for 1938, page 312. 
Existing project: A channel 35 feet deep and 450 feet 
wide from Delaware River through Elk River and 
Chesapeake Bay to water of natural 35-foot depth in 
Chesapeak Bay including a cutoff at Penn Central Railroad 
crossing, and having a maximum radius of 
curvature of 7,000 feet at bends; a high-level, fixed railroad 
bridge with vertical clearance of 135 feet and 
horizontal clearance of 600 feet at the railroad crossing 
over the cutoff (economic study of railroad crossing requested 
by Office of Management and Budget resulted in 
construction of a single track vertical lift bridge in lieu of 
a high-level fixed railroad bridge); high-level fixed highway 
bridges over canal at Reedy Point, St. Georges, 
Summit, and Chesapeake City; a bascule drawbridge 
across Delaware City Branch Channel; extension of 
entrance jetties at Reedy Point; and extension of entrance 
jetties at Reedy Point; and anchorage in Elk River, 35 feet 
deep and 1,200 feet wvide, with an average length of 3,700 
feet; enlargement of anchorage and mooring basin in 
Back Creek to afford an area about 400 feet wide, 1,000 
feet long, and 12 feet deep; dredging Delaware City 
Branch Channel to 8 feet deep and 50 feet wide, and 
deepening existing basin to same depth; revetment of 
banks of canal as required between Delaware and Elk 
Rivers, and on banks of Delaware City Branch Channel 
east of Fifth Street Bridge; and construction of 
bulkheads. Total of section included in project, excluding 
Delaware City Branch Channel, which is about 2 miles 
long, is about 46 miles. All depths refer to plane of low 
water in Delaware River. Extreme tidal range is from 6.3 
feet above mean high water to 3 feet below mean low 
water. Existing project is about 89 percent completed. 
Channel 27 feet deep and 250 to 400 feet wide. Delaware 
River to Pooles Island, completed in 1938. High-level 
fixed highway bridges were completed at St. Georges 
(4-lane) in 1942; at Chesapeake City (2-land) in 1949; and 
at Summit (4-Lane) in 1960. Relocation of Penn Central 
Railroad bridge was completed December 21, 1965. Enlargement 
to 35 feet deep and 450 feet wide St. Georges 
and Summit bridges and Summit and Goose Island was 
completed on June 20, 1972 and February 18, 1972, 
respectively. Removing the old Penn Central railroad 
bridge was completed on January 21,1972. Channel work 
for Part II is about 87 percent complete. Work remaining 
consists of completing channel enlargement to 35 feet 
deep and 450 feet wide between Reedy Point Bridge and 
St. Georges Bridge; widening and deepening the channel 
between Delaware River and Reedy Point Bridge, the 
completion of recreation facilities, and miscellaneous 
completion items. Deepening of the Delaware City 
Branch Channel from 6 to 8 feet from a point 400 feet east 
of Fifth Street Bridge to its junction with canal has been 
deferred for study. 
Original cost of canal including purchase was 
$10,709,755; estimated cost of new work for modification 
of 1935 and 1954 is $139,574,000 (October 1985). Total 
estimated cost of new work including original purchase 
is $147,534,000. Portion of project comprising completion 
of Delaware City Branch Channel from a point 400 feet 
east of Fifth Street Bridge to its junction with canal is to 
be restudies and excluded from foregoing estimate. Estimated 
cost of this portion is #145,000 (July 1954).(See 
Table 3-A at end of chapter for total costs for existing 
project to Sept. 30, 1989. See Table 3-B at end of chapter 
for Acts authorizing existing project.) 
Local cooperation: River and Harbor Act of 1954 
provided that local interest furnish lands and rights-ofway 
required for bridges. Assurances accepted and 
approve February 16, 1955. Requirements for Summit 
and Reedy Point Bridges have been met. 
Terminal facilities: Ample mooring facilities at eastern 
and western ends of canal and bulkheads at Delaware 
City and St. Georges were constructed by the United 
3-8

PHILADELPHIA, PA. DISTRICT 
States. A small-boat harbor was provided and a wharf 
constructed at Chesapeake City. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: Plans and specifications and surveys were accomplished. 
15. MISPILLION RIVER, DE 
Location: Rises in Kent and Sussex Counties, DE, 
flows northeasterly 15 miles along the boundary line 
between the two counties and empties into Delaware Bay 
about 16 miles above Cape Henlopen.(See Coast and 
Geodetic Survey Chart 1218.) 
Previous projects: For details see page 1786, Annual 
Report for 1915, page 448 of Annual Report for 1918, and 
page 327 of Annual Report for 1938. 
Existing project: Project is about 31 percent complete. 
Four cutoffs for 6-foot channel were completed in 
1923; 6-foot channel from Delaware Bay to Milford in 
1924; and jetties at the mouth in 1939. Work remaining 
is dredging channel to 9-foot depth, 80 feet wide in 
Delaware Bay to the mouth, thence 60 feet wide to Milford, 
with the provision of three cutoffs to eliminate 
bends, and a turning basin at Milford. Controlling depths 
at mean low water; in October 1964 from Delaware Bay 
to mouth 7.1 feet, and thence to fixed highway bridge at 
Milford, 6.1 feet. For details see page 243 of Annual 
Report for 1957. (See Table 3-A at end of chapter for total 
costs for existing project to Sept. 30, 1989.) 
Local cooperation: Assurances required by 1954 
River and Harbor Act have not been furnished. For 
details see page 243, Annual Report for 1957. Prior requirements 
fully complies with. 
Terminal facilities: For details see page 244, Annual 
Report for 1957. 
Operations during fiscal year: Maintenance, contract: 
Work included dredging by Cottrell Engineering 
Company from 31 May 1989 to 28 June 1989 removing 
7,259 cubic yards of material at a cost of $181,804. 
Maintenance, hired labor: Work included maintenance 
dredging, and supervision and administration. 
16. MURDERKILL RIVER, DE 
Location: Rises in Kent County, DE, flows northeasterly 
19 miles through county, and empties into 
Delaware Bay about 25 miles above Cape Henlopen. (See 
U.S. Coast and Geodetic Survey Chart no. 1218.) 
Existing project: Provides for a channel 7 feet deep 
at mean low water, 150 feet wide in Delaware Bay to 
mouth, and thence 80 feet wide to Frederica, 7.5 miles 
above mouth. Total length of section included in project 
is about 8.5 miles. Extreme tidal range is from about 1 
foot below mean low water to about 2 feet above mean 
high water. 
Estimated cost for new work revised in 1954 is $38,000. 
Portion comprising widening channel to project width 
throughout its length is to be restudied and excluded from 
foregoing cost estimate. Estimated cost of this portion 
last revised in 1954 was $86,000. Project was authorized 
by River and Harbor Act of July 13, 1892 (H. Ex. Doc. 
21,52d Cong., 1st Sess. See page 981 Annual Report for 
1892). Latest published map is in House Document 
1058,62d Congress 3d Session. 
Existing project about 30 percent complete, including 
revision to be restudied. Channel 7 feet deep and 60 feet 
wide was completed in 1911. Work remaining is widening 
the channel to project width. (See Table 3-A at end of 
chapter for total costs for existing project to Sept. 30, 
1989.) 
Local cooperation: None required. 
Terminal facilities: There are a number of light 
timber wharves on both sides of river near mouth and two 
wharves at Frederica, all privately owned. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, contract: 
Work included maintenance dredging by Cottrell 
Engineering Company from 31 May 1989 to 28 June 1989 
removing 39,291 cubic yards of material at a cost of 
$305,695. 
Maintenance, hired labor: Work included supervision 
and administration and maintenance dredging. 
17. NAVIGATION WORK 
UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant To Section 107, Public 
Law 86-645 (Preauthorization) 
Name of Project Cost to 30 September 1989 
Feasibility Reports 
Wills Hole Thorofare, Pt. Pleasant, NJ $ 19,340 
18. NEW JERSEY 
INTRACOASTAL 
WATERWAY 
Location: A sea level inland water route approximately 
parallel with New Jersey coast, extends from Atlantic 
Ocean at Manasquan Inlet, about 26 miles south of Sandy 
Hook, NJ to Delaware Bay about 3 miles above Cape May 
point. Waterway extends through inlet and up 
Manasquan River about 2 miles; thence by Point Pleasant 
Canal through high ground for 2 miles to head of Barnegat 
Bay. It then passes through a series of bays, 
lagoons, and thoroughfares along New Jersey coast to 
Cape May Harbor; thence across Cape May County to 
Delaware Bay through a land cut by way of New England 
Creek basin.(See U.S.Coast and Geodetic Survey Charts, 
234, 795, 825, 826, 827, 1216, 1217, 1218, and 1219.) 
Existing project: This provides for a channel 12 feet 
deep at mean low water and generally 100 feet wide, 
3-9

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
extending from the Atlantic Ocean at Manasquan Inlet, 
NJ to Delaware Bay above Cape May, NJ, by the further 
improvement of Manasquan River and Inlet, NJ, and the 
present New Jersey Intracoastal Waterway, and by the 
construction of a canal of similar dimensions from Cape 
May Harbor to Delaware Bay via the New England Creek 
basin, with adequate jetties at the Delaware Bay 
entrance. The total length of the project is about 117 
miles. Normal tide range in sections of the waterway 
remote from inlets is 0.5 foot. 
Estimated cost for new work is $71,549 (July 1969), 
exclusive of $1,824,940 Navy Department funds and 
$99,000 contributed by local interests. Portion of project 
extending from Manasquan River to Cape May Harbor is 
to be restudied and excluded from new work costs estimate. 
Estimated cost of this portion is $6,470,000 (July 
1954). Existing project was adopted by 1945 River and 
Harbor Act (H.Doc 133, 76th Cong., 1st Sess.) Latest 
published map is in project document. River and Harbor 
Act of 1946 (Public Law 525,79th Cong., 2nd Sess., as 
extended by Public Law 240,82d Cong.), authorized use 
for a period not to exceed 6 years, of funds from appropriations 
heretofore or hereafter made for maintenance and 
improvement of rivers and harbors, for maintenance of 
canal from Cape May Harbor to Delaware Bay constructed 
as an emergency wartime project with Navy 
Department funds, including cost of maintaining temporary 
railroad andcseashore highway bridges over canal. 
Existing project is about 25 percent complete. A canal 
12 feet deep and 100 feet wide from Cape May Harbor to 
Delaware Bay was completed in 1942 as well as two 
parallel stone jetties at Delaware Bay entrances and a 
temporary highway and a railroad bridge in 1944, all with 
Navy Department funds. Work remaining consists of 
dredging a channel 12 feet deep and 100 feet wide from 
Atlantic Ocean at Manasquan Inlet to Cape May Harbor, 
has been deferred for restudy; however, the project between 
Ottens Harbor and Richardson Channel and from 
that point to Cape May are being maintained to 10 feet 
and 12 feet, respectively, since they were originally 
dredged to these depths by the State. Section 860 of the 
Water Resources Development Act of 1986 authorized, 
for preconstruction engineering and design, a 15 foot 
depth in the Vicinity of Cape May Harbor, titled as Cold 
Spring Inlet. (See Table 3-A at end of chapter for total 
costs for existing project to Sept. 30, 1989.) 
Local cooperation: The project is subject to the conditions 
that the State of New Jersey cede to the United 
States all right, title, and interest that it has acquired to 
lands, easements, rights-of-way, and structures other 
than bridges for the Bayhead-Manasquan Canal; that the 
State of New Jersey furnish, free of cost to the United 
States, all lands, easements, rights-of-way, and disposal 
areas required for construction of the Cape May Canal 
and for improvement of the proposed waterway and for 
their subsequent maintenance; that local interests provide, 
maintain, and operate suitable bridges over the 
waterway; that the State of New Jersey donate to the 
United States the navigation aids in use on the present 
New Jersey Intracoastal Waterway; and that the State of 
New Jersey hold and save the United States and its 
agents free from any claims for damages resulting from 
the work of improvement. Compliance with these conditions 
was completed January 15, 1954, except that local 
interests are required to furnish disposal areas for the 
construction and the subsequent maintenance of the 
proposed improvement. 
Terminal facilities: See Annual Report for 1962. 
Operations during fiscal year: Maintenance, contract: 
Work included Pt. Pleasant bulkhead coating 
Phase 2, and lease equipment. Bank stabilization, water 
supply study, repair of bulkhead and dredging of Cape 
May Canal was accomplished. There was maintenance 
dredging by Barnegat Bay Dredging Company from 26 
June 1989 to 30 September 1989 removing a total of 
110,000 cubic yards of material at a cost of $565,347. 
Maintenance, hired labor: Work included general 
maintenance, bank stabilization, coating of Pt. Pleasant 
Canal bulkhead, engineering and design, and supervision 
and administration. 
19. PEPPER CREEK, DE 
Location: Rises in south central part of Sussex County, 
DE, and flows north to Dagsboro about 48 miles south 
of Dover, DE, thence east-northeast to Indian River Bay. 
(See Coast and Geodetic Survey Charts 411 and 1219 and 
Army Map Service Quadrangle Sheet 5961 II SW, of 
Frankford, DE) 
Existing project: A channel 6 feet deep and 60 feet 
wide from such depth in Indian River Bay 3.9 miles to 
Cattail Marsh. Existing project was adopted by the Chief 
of Engineers, June 12, 1963, under the small navigation 
program, section 107, River and Harbor Act of 1960. Tidal 
range in creek is 1 foot at mean sea level. Tidal range in 
the ocean at Indian River Inlet is 3.8 feet. Costs for 
completed project were $138,094 Federal, and $41,500 
non-Federal. 
Local cooperation: Project was approved subject to 
certain requirements by local interests, as defined in 
detailed project report, "Small Navigation Project For 
Pepper Creek, DE." Assurances of cooperation were 
received from Delaware State Highway Department, 
January 16, 1964, and approve by District Engineer, 
February 25, 1964. Contributed funds of $41,500 were 
received from local interests, March 30, 1964. 
Terminal facilities: Launching and unloading 
facilities exist at Helms Landing, Timmons Cove, and 
Pools Landing. Facilities consist of wooden bulkheads 
which permit boats to anchor alongside and unload onto 
trucks on the shore. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year: Maintenance, hired 
labor: BCR update was accomplished. 
20. SCHUYLKILL RIVER, PA 
Location: Rises in Schuylkill County, PA, flows 
3-10

PHILADELPHIA, PA. DISTRICT 
generally southeasterly 150 miles, and empties into 
Delaware River at Philadelphia, PA (See U.S. Coast and 
Geodetic Survey Charts 295 and 280.) 
Previous project: For details see page 325, Annual 
Report for 1932. 
Existing project: This provides for a channel 33 feet 
deep and 400 feet wide in Delaware River the mouth and 
within the river to 29th Street, .75 mile above the mouth; 
thence the same depth and 300 feet wide to Passyunk 
Avenue Bridge, 3.5 miles above the mouth; thence 26 feet 
deep and 300 feet wide to Gibson Point, 4.5 miles above 
the mouth; and thence 22 feet deep and 200 feet wide to 
University Avenue Bridge, 6 miles above the mouth, 
including widening at bends. The total length of the 
section included in the project is about 6.5 miles. All 
depths refer to the plane of mean low water. The extreme 
tidal range, due to freshets and prolonged heavy winds, 
is about 14 feet. 
The cost for new work for the completed existing 
project was $2,809,007. Existing project was completed 
in September 1962. For details see Annual Report for 
1962. (See Table 3-A at end of chapter for total costs for 
existing project to Sept. 30, 1989. See Table 3-B at end of 
chapter for acts authorizing existing project.) 
Local cooperation: The River and Harbor Act of July 
24, 1946, imposed the condition that the City of Philadelphia 
agree to remove 60,000 cubic yards, place 
measurement, of material annually from that portion of 
those portions of the project which the District Engineer 
may designate until such time as adequate municipal 
sewage-treatment works are constructed and placed in 
effective operation. Compliance with this condition has 
been met through the completion of sewage-treatment 
works by the City of Philadelphia. All other requirements 
have been fully complied with. 
Terminal facilities: There are 38 wharves, piers, and 
docks within limits of improvement. Facilities are considered 
adequate for existing commerce. (For further 
details see Port Series No. 7, Revised 1967, Corps of 
Engineers.) 
Operations during fiscal year: Maintenance, hired 
labor: Work included general maintenance, plans and 
specifications on dredging, and supervision and administration. 
21 WILMINGTON HARBOR, DE 
Location: Formed by Christina River, which rises in 
New Castle County, DE, flows northeasterly 16 miles, 
passing through the City of Wilmington, DE, and empties 
into Delaware River about 29 miles below Philadelphia, 
PA (See U.S. Coast and Geodetic Survey Chart 294.) 
Previous projects: For details see page 1785 of Annual 
Report for 1915 and page 308 of Annual Report for 
1938. 
Existing project: This provides for a channel 38 feet 
deep and 400 feet wide from west edge of Delaware River 
ship channel to Lobdell Canal, a distance of about 1.2 
miles; thence 21 feet deep and 250 feet wide for the 
distance of .8 mile to the mouth of Brandywine River; 
thence the same depth and 200 feet wide for a distance of 
about 2.2 miles to a point approximately 4.2 miles from 
the Delaware River ship channel; thence decreasing to a 
depth of 10 feet in a distance of 750 feet to Penn Central 
Railroad bridge No.4; and thence 7 feet deep and 100 feet 
wide for a distance of of about 5.6 miles to Newport, DE, 
approximately 9.9 miles above Delaware River ship channel, 
including a turning basin 38 feet deep opposite the 
Wilmington Marine terminal and extending upstream 
from the mouth to Lobdell Canal, 320 feet wide, 2,900 feet 
long on the north side of the channel and decreasing to a 
length of 2,000 feet on the north side of the basin. It also 
provides for the removal of about 1,200 feet of the outer 
end of a stone-filled, pile-and-timber crib jetty constructed 
2,150 feet long on the north side of the entrance; 
for a steel sheet-pile jetty 2,300 feet long, with 120-foot 
inshore wing, on the south side of the entrance, and for a 
V-shaped stone-filled pile-and-timber jetty at the mouth 
of Brandywine River 430 feet along the north side of 
Brandywine and 260 feet long on the Christina. Depths 
refer to the plane of mean low water. The extreme tidal 
range, due to prolonged heavy winds, is about 13 feet. 
Existing project was completed in 1962. (For details see 
page 222, Annual Report 1962.) Authority from Section 
107 of the River and Harbor Act of July 1960 provide for 
channel and turning basin deepening from 35 to 38 feet 
and the turning basin widened from 200 to 320 feet. (See 
Table 3-A at end of chapter for total costs for existing 
project to Sept. 30, 1989. See Table 3-B at end of Chapter 
for Acts authorizing existing project.) 
Local cooperation: Fully complied with. 
Terminal facilities: There are 18 piers, wharves, and 
docks within limits of the improvement. Facilities considered 
adequate for existing commerce. (For further 
details see Port Series No.8, revised 1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, contract: 
Work included plans and specifications, water 
quality and shad monitoring, lease of equipment, 
drainage and construction of dikes and sluices, construction 
of disposal area, subsurface testing, investigation of 
a sunken vessel, and USGS Stream Gaging. There was 
maintenance dredging by Great Lakes and Dock Company 
from 21 October 1988 to 07 November 1988 
removing a total of 496,668 cubic yards of material at a 
cost of $447,501; and by American Dredging Company 
from 02 August 1989 to 23 August 1989 removing a total 
of 436,328 cubic yards of material at a cost of $473,605. 
Maintenance, hired labor: Work included general 
maintenance, disposal area and dredge monitoring, surveys, 
environmental coordination for reef design, 
maintenance of Stream Gaging by USGS, ditching, engineering 
and design, and supervision and 
administration. 
3-11

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
Beach Erosion Control: 
22. SHORELINE EROSION CONTROL 
DEMONSTRATION 
Location: Demonstration projects were undertaken at 
a total of 16 sites nationwide, 6 of which are located in 
the Delaware Bay and include Pickering Beach, Kitts 
Hummock, Slaughter Beach, Bowers Beach, Broadkill 
Beach, and Lewes, Delaware. The latter three sites were 
only monitored as there are presently Federal and State 
projects in progress. 
Existing project: Section 54 of Water Resources 
Development Act of 1974 authorized a nationwide, 5 year 
program to test and evaluate low cost shoreline erosion 
control measures, both structural and vegetative, which 
can be implemented by individual private property 
owners. The emphasis of the program was not to solve 
individual problems, so much as to explore the effectiveness 
of various ways to control erosion at different types 
of shorelines, and provide this information to private and 
public landowners. The construction and evaluation at all 
sites are completed and information dissemination has 
been started. Development and dissemination of public 
information guide books. As such we are the repository of 
these guide books. 
Operations during fiscal year: Maintenance, hired 
labor: Dissemination of reports as requested by OCE. 
23. BEACH EROSION CONTROL 
WORK UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, Public Law 87-874 (Preauthorization). 
Name of project Cost to 30 September 1989 
Detailed Project Reports 
North Shore-Indian River Inlet $301,306 
South Shore-Indian River Inlet 475,017 
Flood Control 
24. BELTZVILLE LAKE, PA 
Location: Damsite is on Pohopoco Creek about 4.5 
miles' upstream from its confluence with Lehigh River 
and 4 miles east of Lehighton, PA (See Geological Survey 
Quadrangle Map for Lehighton, PA-1960.) 
Existing project: This is a multiple-purpose development 
project providing water supply, flood control, and 
recreation. Plan of improvement provides for an earth 
and rock fill dam 4,200 feet long rising 170 feet above 
creekbed; a spillway around the north end of dam; and 
gate control outlet works discharging through a conduit 
on rock along right abutment. The lake, a unit of comprehensive 
plan for flood control and other purposes of 
Delaware River Basin, has a reservoir capacity of 68,250 
acre-feet at spillway crest level with 1,390 acre-feet of 
inactive storage, 39,830 acre-feet for water supply and 
recreation, and 27,030 acre-feet for flood control. The cost 
of project was $22,931,400 including $6,100,000 required 
non-Federal reimbursement for costs allocated to water 
supply storage during life of project. The construction of 
the dam and appurtenances was completed in 1971. (See 
Table 3-A at end of chapter for total costs for existing 
project to Sept. 30, 1989.) 
Local cooperation: Project was approved subject to 
certain requirements of cooperation by local interests as 
defined in approved House Document. Resolution of 
Delaware River Basin Commission providing assurances 
of repayment of water supply and pollution control costs 
was accepted June 7, 1965. A contract for repayment of 
water supply costs was signed October 16,1966. 
Operations during fiscal year: Maintenance, contract: 
Work included recreation safety program, USGS 
Stream Gaging equipment, snow survey program, repair 
and maintenance of specific gages, water quality testing 
and monitoring, bulkhead water quality monitoring, 
painting of service bridge, monumentation survey, and 
repair outlet channel side slope. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir, instrumentation and surveillance, 
safety inspection, and USGS Stream Gaging. 
Work also included water quality testing and monitoring, 
test and evaluation of emergency bulkhead, water control, 
plans and specifications on bulkhead, replacement 
of valves, engineering and design, and supervision and 
administration. 
25. BLUE MARSH LAKE, PA 
Location: Dam site is on Tulpehocken Creek about 1.5 
miles upstream from its confluence with Plum Creek and 
about 6 miles northwest of Reading, PA(See Geological 
Survey Quadrangle Sheet, Bernville, PA) 
Existing project: This is a multiple-purpose development 
project providing water supply, flood control, and 
recreation. Construction started in 1974 and was completed 
in 1980. The dam is 1,775 feet long and rises 98 
feet above creekbed, with spillway about 1,500 feet south 
of dam, and gate-controlled outlet works discharging 
through a conduit on rock along right abutment. The lake, 
a unit of comprehensive plan for flood control and other 
purposes of Delaware River Basin, has a capacity of 
50,010 acre-feet at spillway crest level, with 3,000 acrefeet 
of inactive storage, 14,620 acre-feet for water supply 
and recreation, and 32,390 acre-feet for flood control.(For 
details see H.Doc 533 87th Cong., 2nd Sess.) Cost of 
project $63,163,791. Existing project was authorized by 
1962 Flood Control Act. (See Table 3-A at end of chapter 
for total costs for existing project to Sept. 30, 1989.) (H. 
Doc. 533, 87th Cong., 2d Sess., contains latest published 
maps.) 
Local cooperation: Project was approved subject to 
certain requirements by local interests, as prescribed in 
House Document cited above. Delaware River Basin 
Commission on December 29, 1964, adopted a prelimi- 
3-12

PHILADELPHIA, PA. DISTRICT 
nary resolution providing for repayment of water supply 
costs. 
Operations during fiscal year: Maintenance, contract: 
Work included maintenance, recreation safety 
program, sewage treatment plant, sewage vacuum system, 
USGS Stream Gaging, snow survey and NOAA 
Weather Service Cooperation. Work also included maintenance 
and repair of specific gages, water quality testing 
and monitoring, installation of computer terminal and 
peripherals, lawn maintenance, janitorial services, trash 
removal, purchase and repair of water supply equipment, 
and cost incurred for Lower Heidelberg Township police 
department. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir and recreation area, annual 
safety inspection, instrumentation and surveillance, installation 
of WCDS equipment, reservoir regulation data 
collection, water quality testing and monitoring. There 
was joint use of water facilities, erosion control, repair 
access road, plans and specifications on treatment plant 
roof, engineering and design, and supervision and administration. 
Also incurred were costs for seasonal 
employment at recreation area and boat launch repairs. 
26. DELAWARE COAST 
PROTECTION, DE 
Location: The project is located in Sussex County, 
Delaware, on the Atlantic Ocean and starts immediately 
south of Delaware Bay extending in a southerly direction 
a distance of 24.5 miles to Fenwick Island on the 
Delaware-Maryland border. 
Previous Project: The previous project, adopted as 
HD 85-216 in 1958 and modified by P.L. 87-874 in 1962, 
provided for Federal participation in the cost of restoration 
and subsequent periodic nourishment, and the initial 
periodic nourishment was completed in 1957 by local 
interests. The second increment of beach replenishment 
by local interest was completed in 1963. 
Existing project: Provides a plan of improvement 
which consists of the construction of a sand bypass system 
and periodic nourishment until 2027. (For details, 
see S. Doc. 90,90th Cong. 2d Sess.) Estimated cost of 
project (October 1986) $9,720,000 includes $5,180,000 
required non-Federal costs. The construction of the 
feeder beach north of Indian River Inlet was completed 
in 1973 and nourished in 1978, and 1984. Other work 
undertaken has been engineering and design associated 
for the remaining portion of the project. (See Table 3-A 
at end of chapter for total costs for existing project to Sept. 
30, 1989.) Section 869 of the Water Resources Development 
Act of 1986 deauthorized the unshceduled portion 
of the project. 
Local cooperation: Assurances of local cooperation 
were provided by the State of Delaware, January 13, 
1981. 
Operations during fiscal year: New work, contract: 
Work included initial construction of sand bypassing 
plant. 
New work, hired labor: Work included planning 
management, engineering and design and supervision 
and administration. 
27. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 838, 80th Congress, as amended (Preauthorization). 
Name of Project Cost to 30 Sept. 1989 
Reconnaissance Reports 
Assunpink Creek Basin, NJ $37,645 
Lehigh River Basin, PA 43,462 
Newton Creek, Collingswood, NJ 19,485 
Newton Creek, Woodlynne, NJ 15,863 
Shabakunk Creek, Ewing, NJ 51,919 
Willsey Creek, Wurtsboro, NJ 69,058 
Feasibility Reports 
Palmerton, PA 
Construction 
Pennypack Creek, Hatboro, PA 
8,490 
$54,019 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
antecedent legislation). 
Fiscal year costs were $200,762 for disaster preparedness. 
28. EMERGENCY BANK PROTECTION 
Emergency Bank Protection Section 14, Public Law 
79-526. 
Feasibility Reports 
Manasquan River, NJ 
Reconnaissance Reports 
Buckwha Creek, PA 
Ontelaunee Creek, Lehigh County, PA 
Little Neshaminy Creek, PA 
$31,934 
$ 4,280 
$ 9,661 
$ 7,819 
29. FRANCIS E. WALTER DAM, 
PA 
Location: Reservoir is in northeastern Pennsylvania 
on Lehigh River between White Haven and Stoddartsville. 
Dam is about 0.4 mile below mouth of Bear 
Creek, about 60 miles above confluence of Lehigh River 
and Delaware River at Easton, PA(See Geological Survey 
Quadrangle Sheet, Stoddartsville, PA) 
Existing project: Plan of improvement authorized by 
1946 Flood Control Act (H. Doc. 587,79th Cong.,2d Sess.) 
provided for a single-purpose flood control reservoir. 
Modification of project, authorized by 1962 Flood Control 
Act (H. Doc.522,87th Cong., 2d Sess.), provides for a 
multiple-purpose development for water supply and 
recreation in addition to present single-purpose flood 
3-13

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
control project. Plan of improvement requires altering 
spillway, increasing height of dam, constructing a new 
intake tower, extending outlet tunnel by addition of a 
concrete conduit, and constructing new dikes and raising 
existing dikes. Modified dam will rise 264 feet above 
riverbed and be 3,500 feet long. Reservoir modification, a 
unit of comprehensive plan for flood control and other 
purposes of Delaware River Basin, will have a reservoir 
capacity of 181,000 acre-feet spillway crest level with 
3,000 acre-feet of inactive storage, 70,000 acre-feet for 
water supply and recreation and 108,000 acre-feet for 
flood control. Estimated Federal cost of new work (October 
1986) is $14,270,000 including $107,730,000 
required non-Federal reimbursement for costs allocated 
to water supply storage during life of project after use of 
this storage is initiated. Project as authorized under the 
1946 Flood Control Act was completed June 1961. Settlement 
for lands was completed October 1962. The advance 
engineering and design for the modified project is completed. 
(See Table 3-A at end of chapter for total costs for 
existing project to Sept. 30, 1989.) 
Local cooperation: None required under 1946 Flood 
Control Act. Under 1962 Flood Control Act, project was 
approved subject to certain requirements by local interests, 
as defined in House Document 522 cited above. The 
Delaware River Basin Commission expressed its support 
by a resolution dated 23 April 1980 and reiterated its 
sponsorship for the modified project in August 1985, 
October 1985, and July 1988. 
Operations during fiscal year: Maintenance, contract: 
Work included general maintenance, USGS 
Stream Gage repair & maintenance, repair access road, 
analysis mapping, snow surveys, NOAA Weather Service, 
water quality testing and monitoring, and 
monumentation of surveys. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir and recreation facilities, 
instrumentation and surveillance of reservoir, repair access 
road, safety inspection, initial reservoir filling plan, 
emergency planning, USGS Cooperative Stream Gaging, 
installation of WCDS equipment, reservoir regulation 
data collection, water quality testing and monitoring, 
engineering and design, and supervision and administration. 
30. GENERAL EDGAR JADWIN 
DAM AND RESERVOIR, PA 
Location: In Dyberry Creek valley in central part of 
Wayne County, PA, between borough of Honesdale and 
village of Tanners Falls. Dam is about 3 miles above 
confluence of Dyberry Creek and Lackawaxen River in 
Honesdale and 29 miles above confluence of Lackawaxen 
and Delaware Rivers. (See Geological Survey Quadrangle 
Sheet, I-onesdale, PA) 
Existing project: A single-purpose flood control 
reservoir with a capacity of 24,500 acre-feet formed by an 
earth embankment, about 1,225 feet long at crest and 
rising 109 feet above creek bed. It also has a tunnel with 
intake structure and a chute-type spillway with a stilling 
basin in left abutment. Reservoir controls runoff from a 
drainage area of 65 square miles which is 91 percent of 
watershed of Dyberry Creek and 39 percent of Lackawaxen 
River watershed above Honesdale, PA. 
Construction of project was authorized by 1948 Flood 
Control Act (H.Doc. 113, 80th Cong., 1st Sess.). Federal 
cost of new work was $4,064,510. Non-Federal funds not 
required. Project completed in June 1960. (See Table 3-A 
at end of chapter for total costs for existing project to Sept. 
30, 1989.) 
Local cooperation: Assurances of Compliance with 
requirements of local cooperation were accepted July 30, 
1956. For details see page 251, Annual Report for 1962. 
Operations during fiscal year: Maintenance, contract: 
Work included instrumentation survey, USGS 
Stream Gaging, and NOAA Weather Service. 
Maintenance, hired labor: Work included operation 
and maintenance of the reservoir, instrumentation and 
surveillance, safety inspection and training, water control, 
engineering and design, and supervision and 
administration. 
31 INSPECTION OF 
COMPLETED FLOOD 
CONTROL PROJECTS 
To ascertain whether local interests were maintaining 
and operating completed projects as required, inspections 
were made as follows: 
PROJECT 
Lehigh River at Allentown, PA 
Lehigh River at Bethlehem, PA 
Delaware River at East Branch, NY 
Rancocas Creek at Mount Holly, NJ 
Chester Creek at Chester, PA 
Beach Erosion & 
Hurricane Protection 27 & 
INSPECTION 
DATES 
9 November 1988 
19 May 1989 
14 November 1988 
15 May 1989 
3 November 1988 
11 May 1989 
28 October 1988 
19 May 1989 
25 May 1989 
29 September 1989 
Local interests are satisfactorily maintaining and 
operating projects in accordance with regulation. Costs 
during the period were $16,577. Total costs were $16,934. 
32. INSPECTION OF 
NON-FEDERAL LEVEES 
Inspection of non-Federal levees was conducted at a 
cost of $357,000 at the following sites: 
Stroudsburg, East Stroudsburg, PA 13 June 1989 
Hawley, PA 14 June 1989 
Port Jervis, NJ 27 October 1988 
33. PROMPTON LAKE, PA. 
Location: In Lackawaxen River Valley in central part 
3-14

PHILADELPHIA, PA. DISTRICT 
of Wayne County, PA, between borough of Prompton and 
village of Aldenville. Dam is within corporate limits of 
Prompton, 4 miles upstream from Honesdale, PA, and 
approximately 30 miles above confluence of Lackawaxen 
and Delaware River. (See Geological Survey Quadrangle 
Sheet, Honesdale, PA) 
Existing project: Plan of improvement authorized by 
1948 Flood Control Act (H. Doc. 113, 80th Cong., 1st 
Sess.) provides for a single-purpose flood control reservoir. 
Modification of project authorized by 1962 Flood 
Control Act (H.Doc 522, 87th Cong., 2d Sess.) provides for 
a multiple-purpose development for water supply and 
recreation in addition to present single-purpose flood 
control project. Plan of improvement requires construction 
of control tower with gates and service bridge, 
placing an impervious blanket on valley walls and floor 
upstream from dam, widening spillway, and clearing 
land and relocating roads in reservoir. Dam, completed 
under 1948 Flood Control Act which will not be modified, 
is 1,230 feet long and rises 140 feet above riverbed. 
Existing spillway, cut into rock of right abutment, will be 
modified and present uncontrolled outlet works discharging 
into a concrete conduit along right bank, and will be 
provided with gates and a control tower. Reservoir 
modification, a unit of comprehensive plan for flood control 
and other purposes of Delaware River basin has a 
capacity of 52,000 acre-feet: 3,500 acre-feet for inactive 
storage, 28,200 acre-feet for water supply and recreation, 
and 20,300 acre-feet for flood control. Estimated Federal 
cost of new work (October 1987) is $45,600,000 including 
$40,000,000 required non-Federal reimbursement for 
costs allocated to water supply storage during life of 
project after use of this storage is initiated. Project as 
authorized under the 1948 Flood Control Act was completed 
in November 1960. (For details, see page 358, 
Annual Report for 1963.) Work accomplished under the 
1962 Flood Control Act was preconstruction engineering 
and design. 
Local cooperation: Project modification was approved 
subject to certain requirements by local interests, 
as defined in House Document 522 cited above. Assurances 
of compliance under Flood Control Act of 1948 have 
been met. Delaware River Basin Commission on March 
18, 1966, gave their view that the need for water supply 
was not urgent at that time. However recent studies 
conducted by DRBC have determined that there is now a 
need for water supply. In August 1983, DRBC expressed 
their strong support for the project modification. 
Preconstruction engineering and design was initiated 
in 1966 and suspended in 1968 and resumed in FY 1986. 
Operations during fiscal year: Maintenance, contract: 
Work included instrumentation survey, USGS 
Cooperative Stream Gaging, NOAA Weather Service, 
repair and maintenance of specific gages, water quality 
monitoring and testing, and installation of relief well. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir, instrumentation and surveillance, 
periodic inspection, water quality monitoring 
and testing, repair access road, engineering and design, 
and supervision and administration. 
34. RECONNAISSANCE AND 
CONDITION SURVEYS 
Condition Surveys 
Cedar Creek, DE 
Mispillion River, DE 
Murderkill, DE 
Cohansey River, NJ 
Broadkill River, DE 
Date Survey Conducted 
16 November 1988 
23 November 1988 
10 February 1989 
16 March 1989 
11 April 1989 
35. TAMAQUA, PA 
Location: The authorized project is located in Tamaqua 
Borough and Walker Township, PA. Both 
municipalities are within Schuylkill County. 
Existing project: The project as authorized provides 
for a 2,930-foot long tunnel, 10 feet in diameter with 
appurtenant structures, through Sharp Mountain. The 
tunnel would extend from Wabash Creek on the west 
boundary of Tamaqua to the Little Schuylkill River just 
south of its confluence with Wabash Creek. The proposed 
basin, and a 70-foot long highway bridge. The Phase I 
portion of the advance engineering and design was completed 
in 1981. The findings from that phase resulted in 
the addition of a small dry detention dam to the project 
plan. Phase II of advance engineering and design was 
completed in 1984 and reduced the level of protection to 
100-year. This reduced the tunnel's diameter to 9 feet. 
Estimated cost of project (October 1987) is $12,300,000 
including $3,075,000 required non-Federal costs. The 
local sponsor, by letter of October 2, 1985, requested the 
project be constructed in two stages. It was also requested 
that the tunnel be constructed first followed by the dam. 
Local cooperation: The Borough of Tamaqua is the 
local sponsor. The borough, by letter of June 25, 1968, 
indicated its intention to comply with the items of local 
cooperation. The assurance was reaffirmed by the 
Borough on September 2, 1977, September 2, 1980, and 
again on October 2, 1985. 
Operations during fiscal year: Maintenance, hired 
labor: Engineering and design work was accomplished. 
36. NATIONAL EMERGENCY 
PREPAREDNESS 
The total fiscal year cost for this category amounted to 
$64,714. 
General Investigations 
37. SURVEYS 
Cost for the period were $771,442 for navigation 
studies: $89,700 for flood control studies: $533,195 for 
special studies: a total of $1,394,337. 
3-15

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
38. COLLECTION AND STUDY 39. PRECONSTRUCTION ENGINEERING 
OF BASIC DATA AND DESIGN 
Cost and expenditures during the period for flood plain Cost and expenditures during the period $153,538 for 
information studies were $344,371. navigation studies; 336,588 for flood control: a total of 
490,126. 
3-16

PHILADELPHIA, PA. DISTRICT 
TABLE 3-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY86 FY87 FY88 FY89 SEPT. 30,1989 
Absecon Creek, NJ 
(Regular 
Funds) 
Alloway Creek, NJ 
(Regular 
Funds) 
3. Barnegat Inlet, 
NJ 
(Regular 
Funds) 
(Contributed 
Funds) 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
18,000 
16,504 
20,000 
19,356 
110,000 4,425,000 
61,094 1,442,663 
515,000 619,000 
509,472 624,227 
- 1,992,000 
- 226,659 
5,218,000 7,025,000 
3,795,557 8,449,126 
711,000 734,000 
709,603 727,581 
- 4,550,000 
1,616,239 3,523,181 
4. Big Timber Creek, NJ New Work 
(Regular Approp 
Funds) Cost 
Maint. 
Approp. 
Cost 
(Contributed New Work 
Funds) Approp. 
Cost 
5. Cape May Inlet 
to Lower Twp., ,NJ 
(Regular Funds) 
(Contributed 
Funds) 
6. Ceder Creek, 
DE 
(Regular 
Funds) 
(Contributed 
Funds) 
7. Cohansey River, 
NJ 
(Regular 
Funds) 
8. Cold Springs Inlet, 
NJ 
(Regular 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
18,000 
17,939 
- 150,000 125,000 4,759,000 
- 130,150 139,258 3,502,390 
- - - 200,000 
- - - 58,993 
- - - 287,200 
- - - 285,095 
- - - 35,100 
- - - 35,100 
1,434,000 132,000 324,000 
1,424,916 137,808 327,772 
57,300 
56,228 
266,000 158,000 331,000 173,000 
264,703 151,386 333,407 178,547 
3-17 
2. 
11,935 
11,935 
185,6821 
184,186 
21,398 
21,398 
55,761 
55,117 
17,451,849 
14,407,286 
12,589,135 
12,578,736 
6,842,000 
5,669,079 
58,665 
58,665 
71,9861 
71,925 
50,000 
50,000 
5,184,000 
3,921,798 
200,000 
58,993 
256,100 
256,100 
287,200 
285,095 
35,100 
35,100 
146,75621 
146,75621 
2,786,231 
2,785,022 
879,275 
879,275 
3,318,507 
3,318,164 
1,134,346 
1,134,346

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
TABLE 3-A (Contined) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY86 FY87 FY88 FY89 SEPT. 30,1989 
(Contributed 
Funds) 
9. Cooper River, 
NJ 
(Regular 
Funds) 
10. Delaware River 
Between Philadelphia,
PA and 
Trenton,NJ 
(Regular 
Funds) 
(Contributed 
Funds) 
11. Delaware River 
PA,NJ and DE 
Philadelphia 
to the Sea 
(Regular 
Funds)* 
Rehab. 
12. Indian River 
Inlet and Bay, 
DE 
(Regular 
Funds) 
(Contributed 
Funds) 
13. Inland Waterway 
from Delaware 
River to Chesapeake 
Bay, DE 
and MD 
(Regular Funds) 
14. Inland Waterway, 
Rehoboth 
Bay to,Delaware 
Bay, DE 
and MD 
(Regular Funds) 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
18,000 
17,284 
3,005,000 261,000 4,729,000 1,757,000 
3,009,484 260,475 4,730,789 1,756,834 
14,309,000 14,655,000 
14,287,846 14,662,843 
12,145,000 13,316,400 
12,143,791 13,275,220 
150,000 10 
150,000 10 
33,102 
33,102 
397,244 1 
396,528 1 
72,147,800 3 
72,147,800 3 
39,588,860 4 
39,588,296 4 
15,000 
15,000 
57,879,872 5 
57,879,872 5 
364,060,552 6 
363,986,655 6 
508,324 
508,324 
511,2107 
511,210 
64,000 30,000 400,000 
65,196 30,145 388,801 
11,129,053 21,925,400 10,272,600 
11,295,557 21,846,349 10,345,251 
- 6,095,000 3,697,000 
- 6,065,412 3,713,393 
208,000 335,800 
208,523 338,986 
1,200 
-1,155 
23,000 
33,809 
6,566,500 
6,527,440 
576,000 
578,316 
43,400 
44,600 
3,280,923 
3,280,490 
1,323,775 
1,323,775 
210,000 
210,000 
132,535,5918 
132,532,598 8 
198,329,2589 
198,238,406 
10,368,000 
10,357,121 
561,514 
561,514 
1,912,378 
1,912,278 
60,000 
60,000 
3-18

PHILADELPHIA, PA. DISTRICT 
TABLE 3-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY86 FY87 FY88 FY89 SEPT. 30,1989 
15. Mispillion 
River, DE 
(Regular 
Funds) 
16. Murderkill 
River, DE 
(Regular 
funds) 
17. New Jersey 
Intracoastal 
Waterway 
(Regular 
Funds) 
(Contributed 
Funds) 
18. Pepper Creek, NJ 
(Regular Funds) 
(Contributed 
(Funds) 
19. Schuylkill 
River, PA 
(Regular 
Funds) 
20. Wilmington 
Harbor, DE 
(Regular 
Funds) 
(Contributed 
Funds) 
24. Beltzville Lake, 
PA 
(Regular 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Appro 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Appro 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
211,000 37,000 
210,107 34,758 
153,000 41,000 
149,713 43,653 
63,300 197,000 
66,775 196,938 
800 335,100 
540 335,016 
2,563,300 2,533,000 3,185,000 1,648,000 
2,560,237 2,478,900 3,239,387 1,643,711 
18,000 
16,947 
125,000 104,000 954,000 141,000 
125,433 97,895 957,727 140,940 
4,207,700 13,826,200 10,887,000 
4,217,572 13,768,314 10,869,878 
- - 225,850 
- - 82,437 
5,585,800 
5,613,926 
97,431 
515,000 617,500 658,000 406,500 
496,875 635,506 637,498 427,026 
385,34818* 
385,34818 
1,878,86619 
1,871,807 19 
253,491 
253,491 
37,630 
37,630 
1,645,255 
1,644,276 
71,54911 
71,549 1 
29,511,871 12 
29,504,577 12 
1,196,581 
1,196,581 
99,000 
99,000 
138,094 2 
138,094 2 
19,797 1 
18,744 
38,988 
38,988 
3,334,007 13 
3,334,00713 
27,266,033 
27,263,381 
1,954,725 14 
1,954,725 14 
65,304,465 
65,249,248 
285,850 
239,868 
22,931,831 
22,931,130 
7,000,175 
6,998,294 
3-19

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
TABLE 3-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY86 FY87 FY88 FY89 SEPT. 30,1989 
25. Blue Marsh 
Lake, PA 
(Regular 
Funds) 
26. Delaware Coast 
Protection 
(Regular Funds) 
(Contributed 
Funds) 
29. Francis E. 
Walter Dam, PA 
(Regular 
Funds) 
30. General Edgar 
Jadwin Dam and 
Resevoir,PA 
(Regular 
Funds) 
33. Prompton Lake 
PA 
36. Tamaqua, PA 
New Work 
Approp. 
Cost 
Maint. 
Appro 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
-1,551 
1,053,000 
1,058,095 
550,000 
148,701 
1,052 
-1,730 -113 11,874 
1,106,322 1,308,000 1,442,500 
1,122,178 1,282,070 1,429,509 
9,080 
- 1,100,000 
13,587 920,187 
- 424,000 
- 328,272 
- - - 900,000 
- - - 712,986 
460,000 474,500 451,000 549,000 
449,970 465,297 465,096 546,206 
222,000 155,500 145,000 129,000 
210,796 156,995 151,308 114,381 
287,000 296,000 1,031,000 506,700 
295,841 282,282 1,043,084 497,921 
- 50,000 
- 34,712 
40,000 
53,887 
11,399 
12,448 
63,180,300 
63,177,976 
10,419,022 
10,356,391 
4,103,95320 
3,139,746 20 
215,350 
215,350 
1,033,473 
1,033,473 
12,403,432 15 
12,216,418 15 
6,468,021 
6,449,222 
4,073,105 
4,073,105 
2,042,064 
2,023,716 
4,609,48316 
4,609,48316 
4,533,862 
4,521,011 
625,00017 
625,00017 
* Total Adjusted to correct discrepancies in prior years. 
** For Construction, General funds only on legislative 
Phase I AE&D, or support work for Phase II AE&D. 
1: Includes cost incurred for prepariation of Environmental Impact 
Statement. 
2. Excludes $12,774 for study report under General Investigations. 
3. Includes $2,489,173 for new work for previous projects, 
$105,000 for preauthorization studies and minus $142,015 
adjustment (new work) to Delaware River, Philadelphia 
to Sea project from this project under 1954 modification. 
4. Included $552,720 for maintenance for previous projects, 
and $685,000 Jobs Bill Funds. 
5. Excludes $12,976,054 for new work for previous projects 
and $142,015 adjustment from Delaware River, 
Philadelphia to Trenton, NJ under 1954 modification. 
6. Includes $1,025,409 for maintenance of previous projects, 
and $8,000 Jobs Bill funds. 
7. Excludes $10,000 for previous project. 
8. Includes $10,709,755 for new work for previous projects. 
9. Includes $6,903,748 for maintenance for previous projects, 
and $9,500 Jobs Bill funds. 
10. Includes $50,000 Navy Department Funds. 
11. Excludes $1,824,940 Navy Department Funds. 
12. Excludes $286,953 Navy Department funds expended for 
maintenance. 
13. Includes $525,000 for previous projects. 
14. Includes $402,121 for new work for previous project, and 
$206,177 emergency relief funds. 
15. Includes $40,000 appropriated and expended under Code 
710 Recreation Facilities. 
16. Includes $63,000 appropriated and $61,551 expended 
under Code 710 Recreation Facilities, excludes $23,600 
preauthorization studies under 1948 modification. 
17. Transfer from Baltimore District in Fiscal Year 1989. 
18. Includes $148,798 for new work on previous projects. 
19. Includes $61,172 for maintenance on previous projects. 
20. Includes $704,000 AE&D. 
21. Includes $36,000 for new work for previous projects. 
22. Includes $1,399 transferred from revolving fund. 
3-20

PHILADELPHIA, PA. DISTRICT 
TABLE 3-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 25, 1912 
Sept. 19,1890 
Dec 10, 1896 
March 2, 1907 
Aug 30, 1935 
Aug 26, 1937 
July 24, 1946 
July 2, 1985 
July 3, 1990 
Aug. 30, 1935 
Nov 17, 1986 
Dec 10, 1979 
Mar 2, 1907 
Aug 26, 1937 
Mar 2, 1907 
Mar 2, 1945 
ABSECON CREEK, NJ (See Section 1 of Text) 
Channel 5 feet deep, 80 feet wide in Absecon Bay to mouth of creek. 
ALLOWAY CREEK, NJ (See Section 2 of Text) 
Formation of a channel 6 feet deep by dredging 
and 60 feet wide from Quinton to 1,000 feet above 
upper Hancock Bridge; and a channel of same depth 
and 75 feet wide to the "Square". 
To provide for dike formed by a single row of piles 
above Upper Hancock Bridge. 
Construction of a cut-off at Fosters Bottle 
BARNEGAT INLET, NJ (See Section 3 of Text) 
An 8-foot depth through inlet to Oyster Creek 
Channel across inner bar, 10-foot depth through 
outer bar and for jetties. 
A channel of suitable hydraulic characteristics from 
gorge to Oyster Creek Channel, and thence to deep 
water in bay. 
Maintenance dredging of channel to connect main inlet 
channel with Barnegat City Harbor. 
Construction of a parallel, 4270 foot rubble mound 
south jetty and dredging a channel 10 feet deep, 300 
feet wide, and 11,300 feet long. 
BIG TIMBER CREEK NJ (See Section 4 of Text) 
For a 10 foot depth from Delaware River 
to Marters sand plant. 
Extension of project to Clements Bridge. 
CAPE MAY INLET TO LOWER TOWNSHIP, NJ 
(See Section 5 of Text) 
Consists of beach fill; dune fill; new groins; maintenance 
of existing groins; rehabilitation of an 
existing seawall; and a breakwater with weir and 
deposition basin at Cape May Inlet. 
Project may be constructed separately or in combination 
with any other feature of the project. 
CEDAR CREEK, NJ (See Section 6 of Text) 
Creek ranges in depth from 13 feet at the Route 36 
bridge to less than 5 feet at several locations. 
Channel with varies from 75 feet to 250 feet. 
COHANSEY RIVER, NJ (See Section 7 of Text) 
Channel 7 feet deep over entire project. 
Channel 12 feet deep to Glass Street, thence 8 feet 
to Commerce Street with turning basin. 
COLD SPRING INLET, NJ (See Section 8 of Text) 
An inlet channel 25 feet deep and jetties. 
A 20-foot channel to deep water in harbor 
H.Doc. 71, 62d Cong., 
1st sess. 
H.Doc. 60,51st Cong., 
1st sess. 
River and Harbor 
Act of 1894 
River and Harbor Act 
of 1906 
Rivers and Harbors 
Committee Doc. 19, 73d Con.,2d sess. 
Rivers and Harbors 
Committee Doc. 85, 
74th Cong., 2d sess. 
H. Doc.358, 79th Cong 
2d sess. 
H. Doc.236, 99th Cong 
2d sess. 
H.Doc No.217, 
70th Cong. 1st sess. 
Rivers and Habors 
Comm. Doc. No.15, 
73d Cong., 1st Sess. 
Rivers & Harbors 
Act of 1968 
WRDA of 1986 
River and Harbor Act 
of 1960. 
H. Doc.645,59th Cong 
1st sess. 
Senate Committee print, 
75th Cong.,lst sess. 
H. Doc.388,59th Cong 
2nd sess. 
H. Doc.262,77th Cong 
1st sess. 
3-21

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
TABLE 3-B 
Acts 
June 3, 1896 
AUTHORIZING LEGISLATION 
Work Authorized 
COOPER RIVER, NJ (See Section 9 of Text) 
Provides for a channel 12 feet deep and 70 
feet wide in Delaware River to the mouth 
and 1 1/2 miles above the mouth. 
Documents 
H.Doc 176,53d Cong., 
3d sess. 
July 3, 1930 
Aug 30, 1935 
Aug 30, 19352 
Aug 26,1937 
July 24, 1946 
Sept 3, 1954 
June 25, 1910 
July 3, 1930 
Aug 30, 19353 
June 20, 19384 
Mar 2, 19455 
Mar 2, 19455 
Mar 2, 19455 
Sept. 3, 1954 
July 3, 1958 
Aug 26, 1937 
DELAWARE RIVER BETWEEN PHILADELPHIA, PA 
AND TRENTON, NJ (See Section 10 of Text) 
A channel 28 feet deep, 300 feet wide between 
Allegheny Ave., Philadelphia, PA and Delair Bridge 
Channel 25 feet deep from Delair Bridge to Trenton, 
NJ, and maintenance of 12-foot channel from upper 
end of 25-foot project to Penn Central R.R. Bridge 
at Ferry St., Trenton. 
Auxiliary channel, 20 feet deep east of Burlington 
Island. 
A cross channel 8 feet deep, opposite Delanco, NJ 
Anchorage at mouth of Biles Creek 
A channel 40 feet deep and 400 feet wide between Allegheny 
Ave., Philadelphia, PA, and upstream end of Newbold Island, 
thence 35 feet deep to Trenton Marine Terminal and turning 
basin to 800 feet wide. Relocate channel at railroad bridge 
at Delair and suitably reconstruct bridge. Construct 
necessary bank protection works; and eliminate authorized 
anchorage near mouth of Biles Creek, PA 
DELAWARE RIVER, PA, NJ, AND DE, PHILADELPHIA 
TO THE SEA (See Section 11 of Text) 
Channel 35 feet deep from Allegheny Ave., 
Philadelphia, PA to Delaware Bay. 
Anchorages 35 feet deep at Port Richmond and Mantua 
Creek, a 30 foot anchorage at Gloucester, NJ and 
extend 1,000 foot channel in Philadelphia Harbor to 
Horseshoe Bend. 
An anchorage 35 feet deep at Marcus Hook, PA 
A channel 37 feet deep from Philadelphia - Camden 
Bridge to Navy Yard, thence 40 feet deep to deep 
water in Delaware Bay. 
A 37-foot depth channel from Allegheny Ave., 
Philadelphia, PA to Philadelphia-Camden Bridge 
A 37-foot depth in an enlargement of anchorage near 
Mantua Creek and Marcus Hook. 
Maintain enlarged channel opposite Philadelphia 
Navy Yard. 
A channel from Allegheny Ave., to Naval Base 40 feet 
deep, 400 feet wide along west side of channel 
throughPhiladelphia Harbor and 500 feet wide through 
Horseshoe Bend. 
Anchorages at Reedy Point, Deepwater Point, Marcus 
Hook, and Mantua Creek 40 feet deep and 2,300 feet 
wide with mean lengths of 8,000, 5,200,13,650 and 
11,500 feet respectively. 
INDIAN RIVER INLET AND BAY, DE (See Section 12 of text) 
A 15-foot inlet channel, steel and stone jetties, 
6 foot channel from end of inlet channel to deep 
water in the bay and authority to modify interior 
inlet channel. 
Rivers and Harbors 
Committee Doc. 3, 
71st Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 11, 
73d Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 66, 
74th Cong., 1st sess 
Rivers and Harbors 
Committee Doc. 90, 
74th Cong.,2d sess. 
H. Doc. 679, 79th 
Cong., 2d sess. 
H. Doc. 358, 831d 
Cong., 2d sess. 
H. Doc. 733, 61st Cong. 
2d sess. 
H. Doc. j304 , 71st Cong. 
2d sess. 
Rivers and Harbors 
Committee Doc.5, 73d 
Cong., 1st sess. 
S. Doc. 159, 75th Cong. 
3d sess. 
H. Doc. 5 0,76th Cong. 
1st sess. 
H. Doc. 340, 77th Cong. 
1st sess. 
Specified in Act. 
H. Doc. P58 , 83rd Cong. 
2d sess. 
H. Doc. 185, 85th Cong. 
1st sess. 
74th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 41, 
75th Cong. 1st sess. 
3-22

PHILADELPHIA, PA. DISTRICT 
TABLE 3-B 
Acts 
AUTHORIZING LEGISLATION 
Work Authorized 
Mar 2, 1945 
Aug 30, 1935 
Aug 7, 1939 
Sept 3, 1954 
Aug 30, 1935 
July 25, 1912 
Aug 30, 1935 
Mar 2, 1945 
Mar 2, 1919 
Aug 26, 1937 
Sep 3, 1954 
July 13, 1982 
A 9-foot channel from inlet to Old Landing, including 
basin, and 4-foot channel to highway bridge at 
Millsboro. 
INLAND WATERWAY FROM DELAWARE RIVER TO 
CHESAPEAKE BAY, DE & MD (See Section 13 of Text) 
A sea level channel 27 feet deep, 250 feet wide from 
Delaware River to Elk River and 400 feet wide down 
Elk River and Chesapeake Bay to deep water at or 
near Pooles Island; alter existing bridges over 
canal; enlarge Delaware City Branch Channel to 8 
feet deep and 50 feet wide, with a basin same depth 
and revetment of both banks east of Fifth Street; 
enlarge anchorage and mooring basin in Back Creek to 
400 feet wide, 1,000 feet long and 12 feet deep; 
extend jetties at Reedy Point; and construct bulkheads. 
Construct a 4-lane high-level fixed highway bridge 
at or near St. Georges. 
A channel 35 feet deep and 450 feet wide from 
Delaware River through Elk River and Chesapeake Bay. 
For an 8-foot depth and width increased to 150 feet 
in Delaware Bay. 
INLAND WATERWAY FROM REHOBOTH BAY 
TO DELAWARE BAY, DE (See Section 14 of Text) 
For a 6-foot depth canal to connect Rehoboth Bay and 
Delaware Bay. 
For a 6-foot depth entrance near Lewes, for jetties, 
for widening the canal from Broadkill River to 
Lewes and basin. 
For a 10-foot depth from Delawareay to Lewes and 
in basin, and for extending jetties. 
MISPILLION RIVER, DE (See Section 15 of Text) 
A 6-foot depth and extension of south jetty. 
Extension of north jetty. 
A channel 9 feet deep, 80 feet wide from like 
depth in Delaware Bay to the landward end of the 
jetties and thence 60 feet wide to Milford, 
including 3 cutoffs, with a turning basin at Milford. 
MURDERKILL RIVER, DE (See Section 16 of Text) 
A channel 7 feet deep at low water from Frederica 
to the 7 foot curve in Delaware Bay, 80 feet wide 
down to the mouth, and 150 feet wide at bottom and 
250 feet wide at top from the mouth to the 7 foot 
curve in the bay. Embankment of dredged material 
on each side to a height of at least 2 feet above 
high spring tides. 
NEW JERSEY INTRACOASTAL WATERWAY 
(See Section 18 of text) 
A channel 12 feet deep at mean low water and 
generally 100 feet wide, extending from the Atlantic 
Ocean at Manasquan Inlet, NJ to Delaware Bay above 
H.Doc. 133,76th Cong., 
1st Sess.) 
Rivers and Harbors 
3-23 
Documents 
H. Doc. 330,76tp 
Cong., 1st sess. 
H. Doc. 201, 72d Cong., 
1st sess. and Rivers 
and Harbors 
Committee Docs. 18 
and 24,1736 Cong., 
2d sess. 
Public Law 310, 76th 
Cong., 1st sess. 
S. Doc. 23, 83d Cong. 
2d sess. 
H.Doc.2175,73d Cong. 
2d sess. . 
H.Doc 823,60th Cong., 
1st sess. and Rivers 
and Harbors 
Committee Doc. 51, 
61st Cong., 3d sess. 
Rivers and Harbors 
Committee Doc 56 
75th Cong., 2nd sess 
H.Doc 344, 77th Cong., 
1st Sess. 
H. Doc. p78, 62d Cong. 
2d sess. 
Rivers and Harbors 
Committee, Doc. 83 
74th Cong., 2d sess 
S. Doc 229, 81st Cong., 
2d sess 
H.Ex.Doc. 21, 52d Cong., 
1st Sess.)(See page 981 
Annual Report of 1892.) 
July 1, 1954

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989" 
TABLE 3-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov 17, 1986 
Aug 8, 1917 
July 3, 1930 
July 24, 1946 
Committee Doc.525 
79th Cong., 2d sess. 
WRDA of 1986 
H. Doc. 1270, 64th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 40, 
71st Cong., 2d sess 1 
H. Doc. 699, 79th Cong., 
2d sess1 
Cape May, NJ. Construction of a canal of similar 
dimensions from Cape May Harbor to Delaware Bay via 
the New England Creek basin, with adequate jetties at 
the Delaware Bay entrance. 
To increase the depth of the 2,000, foot reach of the 
Waterway in Cape May County to 15 feet. 
SCHUYLKILL RIVER, PA (See Section 20 of Text) 
Depths of 35 feet from mouth to Girard Point 
thence 30 feet, 26, and 22 feet to University 
Avenue Bridge, Philadelphia. 
A depth of 30 feet instead of 35 feet between the 
mouth and the conditional restoration and 
maintenance of the channel below Passyunk Ave., 
by the United States. 
A depth of 33 feet from the channel in Delaware 
River to Passyunk Ave., restoration of the project 
channel dimensions between Passyunk Ave., and 
University Ave., and full maintenance of the entire 
project. 
WILMINGTON HARBOR, DE (See Section 21 of Text) 
Depths of 21,10 and 7 feet and jetties. 
Purchase or construct a dredge and auxiliaries 
including a wharf and depot, and maintenance of 
project. 
Entrance channel and basin with 25-foot depth and 
construction by local interests of new south jetty. 
A 30-foot depth between Delaware River and Lobdell 
Canal and modification or removal of a portion of 
north jetty. 
Completion of new south jetty by the United States 
subject to provision that city of Wilmington 
reimburse the United States for cost, without 
interest, of any part of structure that may 
subsequently be occupied and utilized for city 
activities. 
Permit temporary occupancy by city of Wilmington 
of any part of south jetty for city activities 
under revocable license, provided occupied portion 
of jetty is properly maintained without expense to 
the United States. 
A 35-foot depth between Delaware River ship channel 
and Lobdell Canal including turning basin of same 
depth, opposite Wilmington Marine Terminal, 200 feet 
wide, 2,900 feet long on north side of channel, and 
2,000 feet long on north side of basin. 
BELTZVILLE LAKE, PA (See Section 24 of Text) 
Provides for multiple-purpose development for water 
supply flood control and recreation 
BLUE MARSH LAKE, PA (See Section 25 of Text) 
Provides for multiple purpose development for water 
supply, flood, control, and recreation. Site is 
located on Tulpehocken Creek about 1 1/2 miles upstream 
from its confluence with Plum Creek and about 
six miles northwest of Reading, PA. 
H. Doc.522, 87th Cong., 
2d sess. 
H. Doc. 522, 87th Cong., 
2d sess. 
3-24 
H. Doc. 66, 54th Cong., 
1st sess. 
Annual Report, 1897 
p. 1250k 
H. Doc. 359, 62d Cong., 
2nd sess. 
H. Doc. 114, 67th Cong., 
1st sess. and S. 
Committee Print, 68th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 20, 
71st Cong. 2d sess. 
Rivers and Harbors 
Committee Doc. 32 
73d Cong., 2d sess. 
H. Doc. 658, 76th Cong., 
3rd sess. 
H. Doc. 88, 86th Cong., 
2d sess. 
June 3,1896 
July 25,1912 
Sep 22,1922 
July 3,1930 
Aug 30, 19358 
Oct 17, 1940 
July 14, 1960

PHILADELPHIA, PA. DISTRICT 
TABLE 3-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
DELAWARE COAST PROTECTION (Section 26 of Text) 
Provides for Federal participation in the cost H. Doc.90, 90th Cong 
of restoration and subsequent periodic nourishment, 2nd sess. 
not to exceed 10 years, of the shore from Rehoboth 
Beach to Indian River Inlet. 
Nov 17, 1986 Project is modified to authorized the construction WRDA of 1986 
of sand bypass facilities and stone revetmen erosion Sec. 869 
control measures at Indian River Inlet, DE. 
FRANCIS E. WALTER DAM, PA (Section 29 of Text) 
Provided for a single-purpose flood control reservoir H. Doc 587, 79th Cong., 
2d sess. 
Provides for a multiple-purpose development for H. Doc 522,87th Cong., 
water supply and recreation. 2d sess. 
GENERAL EDGAR JADWIN DAM AND RESERVOIR, PA 
(Section 30 of Text) 
A single-purpose flood control reservoir with a H. Doc 113, 80th Cong., 
capacity of 24,500 acre-feet formed by an earth 1st sess. 
embankment. 
PROMPTON LAKE, PA (Section 33 of Text) 
Provides for a single-purpose flood control reservoir. H. Doc. 113, 80th Cong., 
1st sess. 
Provides for multiple-purpose development for water H. Doc 522, 87th Cong., 
supply and recreation in addition to present single- 2d sess. 
purpose flood control project. 
1. Contains latest published maps. 
2. Also Public Works Administration, September 6, 1933, and 
Emergency Relief Administration, May 28,1935 
3. Also Public Works Administration. 
4. Channel 37 feet deep and 600 feet wide from Naval Base 
to Philadelphia-Camden Bridge, deferred for restudy. 
5. Channel 37 feet deep and 600 feet wide from Philadelphia-Camden 
Bridge to Allegheny Ave. deferred for restudy. 
6. Extension of jetties considered to be active. 
7. The 10 and 12 foot anchorages are considered inactive. 
8. Also May 28,1935,under Emergency Relief Administration. 
9. Deauthorized the remaining portion of the project. 
10. Extension of jetties considered to be active. 
3-25

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1989" 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Active Projects Status Report For Construction Maintenance 
Absecon Inlet, NJ 
Appoquinimink River,DE 
Broadkill River, DE 
Delaware River, Pennsville, NJ 
Double Creek, NJ' 
Harbor of Refuge 
Inland Waterway from Chincoteague 
Bay to Delaware Bay 
Little River, DE 
Mantua Creek, NJ 
Maurice River, NJ 
Delaware Bay to Millville 
Millville fixed bridge to upper 
end of project 
** Neshaminy State Park Harbor, PA 
Oldmans Creek, NJ 
Raccoon Creek, NJ 
St. Jones River, DE 
Delaware Bay to Lebanon 1'9 
Jetties and entrance at mouth 
Manasquan River, NJ 
Salem River, NJ 
Schuylkill River above Fairmount 
Dam, PA' 
Smyrna River, DE 
Delaware River tp Wharf at 
Smyrna Landing 
Wharf at Smyrna Landing to 
fixed bridge. 
Toms River, NJ 
Channel 5 feet deep 1 
Channel 12 feet deep 6 
Tuckerton Creek, NJ 
Waterway from Indian River Inlet 
to Rehoboth Bay, DE 
Woodbury Creek, NJ' 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
SEE TABLE 3-G 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
SEE TABLE 3-G 
COMPLETED 
SEE TABLE 3-G 
COMPLETED 
COMPLETED 
COMPLETED 
1988 
1934 
1976 
1912 
1985 
1981 
1980 
1966 
1948 
1968 
1941 
1981 
1961 
1986 
1988 
1955 
1949 
1950 
1986 
1981 
1940 
534,20920 
36,973 
68,228 
256,624 
7,800 
516,230 
168,41211 
12,016 
169,687 
143,98417 
128,20313 
31,188 
83,66512 
207,102 
8,006,80714,16 
107,63418 
4,291,810 
198,844 
10,050 
60,242 
90,908 
27,09310 
5,965,67421 
41,270 
243,641 
3 
1,104,769 
98,36014 
288,310 
339,340 
..- 
161,913 
54,601 
32,125 
341,734 
66,093 
3,417,55715 
2,103,00419 
3 
197,327 
33,311 
638,860 
253,833 
56,474 
3-26

PHILADELPHIA, PA. DISTRICT 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Active Projects Status Report For Construction Maintenance 
Aquatic Plant Control INACTIVE 1975 87,594 - 
Dennis Creek, NJ' INACTIVE 1897 4,701 - 
Goshen Creek, NJ1 INACTIVE 1905 15,359 870 
Ice Harbor at Marcus Hook, PA1'4 INACTIVE 1928 208,964 14,336 
Ice Harbor at New Castle, DE" 4 INACTIVE 1898 224,704 - 
Leipsic River, DE 1 INACTIVE 1931 36,956 32,345 
Little Egg Harbor, NJ "1 2 INACTIVE -5 15,048 - 
Maurice River, NJ-Channel 8 feet 
deep, Delaware Bay to mouth INACTIVE 1948 - - 
For Last 
Full Report Cost to September 30,1989 
See Annual Operation and 
Deferred Projects Status Report For Construction Maintenance 
St. Jones River, DE 1961 - - 
Delaware Bay to Lebanon 1' 10 - 207,102 66,093 
Jetties and new entrance at 
mouth7 DEFERRED - - - 
Completed. 
Maintenance assumed by local interests. 
Harbor not now required by commerce. 
Last appropriation for project was in 1852. No information is at 
hand relative to work done. 
Includes $3,000 for new work for previous projects. 
Deferred 
Includes $54,590 new work and $28,935 maintenance funds ex 
pended on previous projects. 
Includes $55,085 new work and $22,723 maintenance funds 
expended on previous projects. 
Includes $2,950 new work funds expended on previous projects. 
Entire amount expended on previous projects repealed in 1905. 
Excludes $2,000 contributed funds and includes $25,330 for 
aintenance for previous project. 
12. Includes $757 new work funds expended on previous projects. 
13. Excludes $327,957 contributed funds allotted expended for new 
work. 
14. Includes $39,000 for new work for previous projects. 
15. Includes $2,054 for maintenance for previous projects. 
16. Includes $555,600 for previous project. 
17. Incl. $43,000 New Work funds expended on previous projects. 
18. Includes $55,809 for new work funds expended on previous 
project. 
19. Includes $1,285 for reconnaissance and condition survey in 
FY 1957, $1,792 operation and maintenace cost incurred for 
preparation of environmental impact statement, and $48,000 
expended for maintenance on previous project. 
20. Includes $116,497 for new work for previous projects. 
21. Includes $23,786 for maintenance for previous projects. 
* Operation and maintenance figure includes cost incurred for preparation of environmental impact statements. 
** Projects authorized by the Chief of Engineers. 
3-27 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
10. 
11.

"REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1989" 
OTHER AUTHORIZED 
TABLE 3-D BEACH EROSION CONTROL PROJECTS 
For Last 
Full Report Cost to September 30,1989 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Brigantine Island ACTIVE - - 
Corson Inlet and Ludlam Beach,NJ ACTIVE 1978 314,400 
Great Egg Harbor Inlet and Peck 
Beach, NJ ACTIVE 1978 387,882 5 
Hereford Inlet ACTIVE - - 
Long Beach Island ACTIVE - - 
Townsend Inlet and Seven Mile 
Beach, NJ ACTIVE - - 
Atlantic City, NJ INACTIVE 1972 2,083,289 -1 
Ocean City, NJ INACTIVE 1969 395,8313 1 
Stone Harbor, NJ INACTIVE 1961 - -1 
Barnegat Light, NJ DEFERRED 1964 70,908 -1 
Cape May City, NJ DEFERRED 1961 22,9572 1 
Long Beach Island, NJ DEFERRED 1964 40,665 -1 
North Wildwood, NJ DEFERRED 1961 - -1 
Rehoboth Beach to Indian River 
Inlet, DE4 1965 326,116 -1 
Ventnor, Margate and Longport,NJ DEFERRED 1961 - -1 
1.Operation and maintenance required under Public Works Accelera- 3.Excludes cost of $1,146,325 to local interests and $272,766 Federal 
tion Program for by law to be assumed by local interests. Extension participation expended under extension of five existing groins cornof 
five existing groins completed pleted 11 May 1964. 
2.Excludes $58,585 Accelerated Public 11 May 1964. Works funds ex- 4.This project was included in and modified by the Delaware Coast 
pended for extension project. 
5.Excludes $130,175 for Preconstruction Engineering and Design. 
* NO CURRENT YEAR FUNDS. 
OTHER AUTHORIZED 
TABLE 3-E FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allentown, Lehigh River, PA COMPLETED 1961 1,615,581 1 
Bethlehem, Lehigh River, PA COMPLETED 1966 4,520,995 -1 
Mt. Holly, NJ COMPLETED 1946 283,655 -1 
Pottstown, PA ACTIVE 1984 487,366 - 
Hay Creek, Birdsboro, PA INACTIVE 1984 335,299 
1. Maintenance assumed by local interest as required by authorizing 3. $1,316,464 expended for preconstruction planning only. 
project. 
2. Ne project deferred. 
3-28

TABLE 3-F 
REPORT OF THE CHIEF OF ENGINEERS, U.S. ARMY 1988 
MULTIPURPOSE PROJECT INCLUDING POWER 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Project Report For Construction Maintenance 
Tocks Island Lake, PA, NJ and NY2 1979 65,106,2601 
Tocks Island (Relocation of U.S. 
Route 209 only) PA 1979 195,223 - 
1. Includes $3,489,088 for AE&D. thority to proceed with the project. Legislation would be required to 
2. National Parks and Recreation Act of 1978 terminated Corps' au- proceed with the project. 
TABLE 3-G DEAUTHORIZED PROJECTS 
For Last Full Date Federal Contributed 
Report See Annual And Funds Funds 
Navigation Projects Report For Authority Expended Expended 
Appoquinimink River, DE1 1931 3 Oct 78 
HD 95-351 $ 78,243 - 
Aquashicola Reservoir, PA 1963 17 Nov 86 
PL 99-662 46 Stat. 
918 - - 
Chester River, 17 Nov 86 
Delaware County, PA 1931 PL 99-662 52 Stat. 
323 $ 7,139 - 
Delaware River, Mouth of 5 Aug 77 
Neversink 1917 HD 94-192 - - 
Maurice River, NJ 1948 Section 12 PL 93-251 
Millville fixec2bridge to upper 
end of project - - 
Maiden Creek Reservoir, PA 1963 17 Nov 86 
PL 99-662 46 Stat. 
918 - - 
Oldmans Creek, NJ 3 1941 2 Nov 79 
Section 12 PL 93-251 $ 63,313 - 
Rancocas River, NJ4 1942 2 Nov 79 
Section 12 PL 93-251 $ 57,590 - 
Smyrna River, DE5 1949 2 Nov 79 
Wharf at Smyrna Landing to fixed HD 95-157 $396,169 - 
bridge. 
Toms River, NJ6 1950 2 Nov 79 
Channel 12 feet deep Section 12 PL 93-251 $ 43,361 - 
Trexler Lake, PA 1981 
17 Nov 86 
PL 99-662 76 Stat. 
1180 - - 
Flood Control Projects 
2 Nov 79 
Lehigh River at Bethlehem, PA7 Section 12 
1966 PL 93-251 $4,520,995 - 
1. Includes $36,973 new work, and $41,270 for maintenance. 
2. There is no need now for this portion of the project. 
3. Includes $31,188 new work, and $32,125 for maintenance. 
4. Includes $44,500 new work, and $13,090 for maintenance. 
5. Includes $143,759 new work, $55,085 previous project, $174,602 
for maintenance, and $22,723 maintenance, previous project. 
6. Includes $10,050 new work, and $33,311 for maintenance. 
7. Maintenance assumed by local interest. 
3-29

BALTIMORE, MD DISTRICT * 
This district comprises the watershed of Susquehanna 
River and its tributaries from headwaters in south 
central New York State through central Pennsylvania to 
its mouth in Chesapeake Bay; watershed of the Potomac 
River and its tributaries from headwaters in Maryland, 
eastern West Virginia, and Northern Virginia to its 
mouth in Chesapeake Bay; District of Columbia; and 
southwestern portion of Delaware. It includes that portion 
of Chesapeake Bay and its tributaries north of Smith 
Point, MD, on western shore of the bay, and includes that 
portion of Maryland between Chesapeake Bay and 
Atlantic Ocean. 
IMPROVEMENTS 
Navigation Page 
1. Baltimore Harbor and 
Channels, MD and VA ................ 4-3 
2. Baltimore Harbor, MD, 
Collection and Removal of Drift ......... 4-4 
3. Cambridge Harbor, MD.................4-4 
4. Crisfield Harbor, MD .................. 4-5 
5. Fishing Bay, MD ....................... 4-5 
6. Herring Bay and Rockhold 
Creek, M D .. ........... ............. 4-5 
7. Herring Creek, Tall Timbers, MD ........ 4-6 
8. Honga River and 
Tar Bay, MD ........................ 4-6 
9. Little Wicomico River, VA ............... 4-6 
10. Monroe Bay and Creek, VA ............... 4-7 
11. Nanticoke River (Including 
Northwest Fork), DE & MD ........... 4-7 
12. Ocean City Harbor and Inlet and 
Sinepuxent Bay, MD ................. 4-7 
13. Pocomoke River, MD .................. 4-8 
14. Potomac and Anacostia 
Rivers, DC, Collection 
and Removal of Drift .................. 4-8 
15. Potomac River-Aquatic 
Plant Control, MD, VA, DC ............. 4-8 
16. Potomac River below 
Washington, DC............. .......... 4-9 
17. Prevention of Obstructions 
and Injurious Deposits, 
Baltimore Harbor, MD ................. 4-9 
18. Shallow Creek, MD............ .......... 4-9 
19. St. Catherines Sound, MD ................ 4-9 
20. Washington Harbor, DC ................. 4-10 
21. Wicomico River, MD .................... 4-10 
22. Reconnaissance and Condition Surveys ..... 4-11 
23. Navigation work under special 
authorization ............... ......... 4-1 1 
Navigation (cont'd) 
Beach Erosion Control 
24. Beach Erosion Control Work 
under special authorization 
Page 
. .. . . . . . . .... 4-11 
Flood Control 
25. Cumberland, MD, and Ridgeley, WV ....... 4-11 
26. Hills Point Road, 
Dorchester Co., MD .................. 4-11 
27. Isle of Wight Bay, 
Ocean City, M D ...................... 4-11 
28. Jennings Randolph Lake, MD and WV ..... 4-12 
29. Lackawanna River Basin, PA ............. 4-12 
29A. Aylesworth Creek Lake, PA .............. 4-12 
30. Raystown Lake, Raystown Branch, 
Juniata River, PA ........... .......... 4-13 
31. Southern New York Flood 
Control Projects ............ .......... 4-13 
31A. Addison, NY ......................... 4-13 
31B. Almond Lake, NY ..................... 4-13 
31C. Arkport Dam, NY ...................... 4-13 
31D. Avoca, NY ........................... 4-14 
31E. Binghamton, NY ...................... 4-14 
31F. Canisteo, NY ......................... 4-14 
31G. Corning, NY ......................... 4-15 
31H. East Sidney Lake, NY..................4-15 
31I. Elmira, NY ........................... 4-15 
31J. Hornell, NY .......................... 4-16 
31K. Lisle, NY . ............. ............. 4-16 
31L. Oxford, NY ................ .......... 4-16 
31M. Whitney Point Lake, NY ............... 4-16 
31N. Whitney Point Village, NY .............. 4-17 
32. Spring Brook Creek, 
Pittston Township, PA ................. 4-17 
33. Stillwater Lake, Lackawanna 
River, PA ................ .......... 4-17 
4-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Flood Control (cont'd) Page 
34. Susquehanna River Flood Control 
Projects, NY and PA .................. 4-17 
34A. Cowanesque Lake, PA ................... 4-18 
34B. Tioga-Hammond Lakes, PA .............. 4-18 
35. Tunkhannock Creek, 
Tunkhannock Township, PA ............ 4-19 
36. West Branch of Susquehanna 
River, PA .................. ......... 4-19 
36A. Alvin R. Bush Dam, PA ................ 4-19 
36B. Curwensville Lake, PA ................. 4-19 
36C. Foster Joseph Sayers Dam, PA .......... 4-19 
37. York, Indian Rock Dam, PA .............. 4-20 
38. Inspection of Completed Flood 
Control Projects ...................... 4-20 
39. Scheduling Flood Control Reservoir 
Operations ........................... 4-20 
40. Flood Control Work under special 
authorization ......................... 4-20 
Water Supply 
41. Washington Aqueduct .................. 4-20 
General Investigations 
42. 
43. 
44. 
Surveys ...................... ....... 4-21 
Collection and Study of Basic Data ....... 4-21 
Pre-construction Engineering and 
D esign .......................... .... 4-21 
Tables 
Table 4-A Cost and Financial Statement .... 
Table 4-B Authorizing Legislation ......... 
Table 4-C Other Authorized 
Navigation Projects ............ 
Table 4-D Other Authorized Beach Erosion 
Control Projects ............... 
Table 4-E Other Authorized Flood 
Control Projects ............... 
Table 4-F Not Applicable 
Table 4-G Deauthorized Projects .......... 
Table 4-H Reconnaissance and 
Condition Surveys ............. 
Table 4-I Inspection of 
Completed Projects ........... 
..... 4-22 
..... 4-27 
.... .4-33 
.... .4-35 
..... 4-36 
..... 4-37 
..... 4-38 
..... 4-39 
4-2 
Page

BALTIMORE, MD DISTRICT 
Navigation 
1. BALTIMORE HARBOR AND 
CHANNELS, MD AND VA 
Location. Baltimore Harbor is at the head of the 
navigable portion of Patapsco River about 12 miles 
from Chesapeake Bay. The Patapsco River rises near the 
town of Westminster in Carroll County, MD, and flows 
generally southeast for about 65 miles to enter Chesapeake 
Bay. (See National Ocean Survey Chart 12278.) 
Existing Project. 
a. A uniform main channel depth of 50 feet between 
Cape Charles, VA, and Fort McHenry at Baltimore, MD, 
with dimensions as follows: (1) Cape Henry Channel: 50 
feet deep and 1,000 feet wide from the 50-foot depth curve 
in the Atlantic Ocean to that depth in Chesapeake Bay, 
a distance of 3.0 miles; (2) York Spit Channel: 50 feet deep 
and 1,000 feet wide connecting the 50-foot depth curves 
in Chesapeake Bay near York Spit, a distance of 18.4 
miles; (3) Rappahannock Shoal Channel: 50 feet deep and 
1,000 feet wide connecting the 50-foot depth curves in 
the Chesapeake Bay opposite the Rappahannock River, 
a distance of 10.3 miles; and (4) Baltimore Harbor 
Approach Channels: 50 feet deep and generally 800 feet 
wide, widened at the approach and bends, from the 50- 
foot depth curve in Chesapeake Bay opposite the mouth 
of the Magothy River to Fort McHenry on the Patapsco 
River, a distance of 20.2 miles. 
b. Branch channels with dimensions as follows: (1) 
Connecting Channel to Chesapeake and Delaware Canal 
Approach Channel: 35 feet deep, 600 feet wide, and 15.6 
miles long from the Cutoff Angle in the main channel to 
the 35-foot depth curves in the natural channel on the 
east side of Chesapeake Bay which is part of the inland 
waterway from Delaware River to Chesapeake Bay. The 
channel includes the Brewerton Extension and Swan 
Point and Tolchester Sections; (2) Curtis Bay: 50 feet 
deep, 600 feet wide, and 2.3 miles long from the main 
channel to and including a turning basin at the head of 
Curtis Bay; (3) Curtis Creek: (a) a channel, 35 feet deep 
and generally 200 feet wide, from the 50-foot channel in 
Curtis Bay to 750 feet downstream of the Pennington 
Avenue Bridge; (b) a channel, 22 feet deep and generally 
200 feet wide, from the 35-foot channel to and along the 
marginal wharf of the Curtis Bay Ordnance Depot; (c) 
an irregular shaped 3-acre basin, with a depth of 18 feet, 
adjacent to the head of the 22-foot channel; (d) a basin, 
15 feet deep and 450 feet wide, from the end of the 22-foot 
channel to the end of the marginal wharf; and (e) a channel, 
22 feet deep and 200 feet wide, from the 22-foot 
channel south of the Baltimore and Ohio Railroad Bridge 
to the vicinity of Arundel Cove, a distance of 2,800 feet, 
thence 100 feet wide in Arundel Cove for a distance of 
2,100 feet, with an anchorage basin, 700 feet square, adjacent 
to the channel and southwest of the wharf of the 
Coast Guard Depot at Curtis Bay; (4) Middle Branch: (a) 
Ferry Bar East Section: a channel, 42 feet deep and 600 
feet wide, from the main channel at Fort McHenry to 
Ferry Bar, a distance of 1.5 miles; (b) Ferry Bar West 
Section: a channel, 35 feet deep and 400 feet wide, from 
the Ferry Bar East Section to Ferry Bar, a distance of 
0.8 mile; (c) Spring Garden Section: a channel, 27 feet 
deep and 250 feet wide, from Ferry Bar to and including 
a turning and anchorage basin immediately below the 
Western Maryland Railway Bridge, a distance of 1.0 mile; 
and (5) Northwest Branch: Federal maintenance of 
39-foot or 35-foot deep channels after either depth has 
been provided by local interests: (a) East Channel: a channel, 
49 feet deep, 600 feet wide, and 1.0 mile long with 
a turning basin at the head of the channel from that 
depth existing at the time of construction; and (b) West 
Channel: a channel, 40 feet deep, 600 feet wide, and 1.3 
miles long with a turning basin at the head of the channel 
from that depth existing at the time of construction. 
c. The following anchorages: (1) Quarantine Anchorage: 
35 feet deep, 3,500 feet long, and 600 feet wide; (2) Riverview 
Anchorage No. 2: 30 feet deep, 2,400 feet long, and 
1,200 feet wide; (3) Riverview Anchorage No. 1: 35 feet 
deep, 4,500 feet long, and 1,500 feet wide; and (4) Fort 
McHenry Anchorage: 35 feet deep, 3,500 feet long, and 
400 feet wide. 
The mean range of tide is 2.8 feet at the Cape Henry 
Channel, 2.3 feet at the York Spit Channel, 1.4 feet at 
the Rappahannock Shoal Channel, 0.8 foot at the 
Craighill Entrance, 0.9 foot in the Cutoff Section, 1.1 feet 
at Fort McHenry, and 1.2 feet at Pooles Island in the 
upper Chesapeake Bay. Depths refer to mean low water. 
Estimated cost for new work is $376,441,000 which includes: 
$8,330,000 for completed work through the River 
and Harbor Act of 1945; $38,411,000 for work completed 
under the River and Harbor Act of 1958 of which 
$33,991,000 is Corps of Engineers, $60,000 is U.S. Coast 
Guard and $4,360,000 is non-Federal; and $329,700,000 
(October 1988 prices) for work authorized by the River 
and Harbor Act of 1970, of which $460,000 is U.S. Coast 
Guard and $329,240,000 is Corps of Engineers and non- 
Federal. 
Widening 35-foot depth from Port Covington Channel 
from 150 to 400 feet to Ferry Bar, widening 27-foot depth 
channel from 150 to 250 feet to Hanover Street Bridge, 
and providing a channel 27 feet deep by 250 feet wide 
to Western Maryland Railway Bridge with an anchorage 
and turning basin at upper end is considered inactive and 
is excluded from the foregoing estimate. Estimated cost 
(1954) of this portion is $1,603,000. 
Local cooperation. Requirements are described in full 
on page 4-3 of Fiscal Year 1982 Annual Report. 
Terminal facilities. The Port of Baltimore has 45 miles 
of waterfront of which 25 miles are industrially developed. 
There are 94 covered and open overseas piers for 
the loading and discharging of 173 ships, providing 84 
general cargo, 65 specialized cargo, and 24 public bulk 
cargo berths. The existing ground storage is equivalent 
to 53,700 railroad cars of cargo. There are 31 public 
general merchandise warehouses, with 4.9 million square 
feet of storage space and 4.7 million cubic feet of cold 
storage space. Eight ship-building, ship repair, and ship 
dismantling yards are available for handling up to 90 
vessels. The three grain elevators in the port have a 
capacity of about 13 million bushels. Latest description 
of terminal facilities is in "Port Series No. 10 (revised 
1983)" on Port of Baltimore, MD, (issued by Board of 
Engineers for Rivers and Harbors). 
4-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations and results during fiscal year. New Work, 
Baltimore District: Construction of the work authorized 
by the River & Harbor Act of 1970 was initiated in 
February 1987. Condition surveys of the project were 
made. New work dredging, by contract, of 12,702,000 
cubic yards at a cost of $43,854,300 to deepen the 
Craighill Entrance, Craighill Channel, Craighill Upper 
Range, Cutoff Angle, Brewerton Channel, Brewerton 
Angle, Fort McHenry Channel, and Curtis Bay Channel 
from 42 to 50 feet, and to complete deepening the East 
Channel, Northwest Branch from 35 feet to 49 feet 
(Maryland Channels II contract) commenced on August 
18, 1989 and was approximately 15 percent complete as 
of September 30, 1989. 
New Work, Norfolk District: New work dredging, by 
contract, to deepen a portion of the York Spit Channel 
(Contract II) from 42 to 50 feet commenced on May 14, 
1988 and was completed on March 19, 1989. Approximately 
10,164,760 cubic yards of material were dredged 
and deposited in the approved Wolf Trap Alternate open 
water disposal area in the Chesapeake Bay at a cost of 
$22,570,200. New work dredging, by contract, of 
3,023,800 cubic yards of material at a cost of $13,972,100, 
to deepen the Cape Henry Channel from 42 to 50 feet 
commenced on April 5, 1989, and was 87% complete as 
of September 30, 1989. Approximately 2,668,800 cubic 
yards of material were dredged, of which 1,335,800 cubic 
yards were deposited at the Dam Neck ocean disposal 
area, 1,200,000 cubic yards were placed on Virginia 
Beach, and 133,000 cubic yards were placed on East 
Ocean View beach. 
Maintenance, Baltimore District: Condition surveys of 
the project channels were made. Maintenance dredging, 
by contract, of 1,559,100 cubic yards of material from 
the Craighill Entrance, Craighill Channel, Craighill Upper 
Range, Cutoff Angle, Brewerton Channel, Brewerton 
Angle, and Fort McHenry Channel at a cost of $4,926,400 
commenced on August 18, 1989, in conjunction with new 
work dredging of the work authorized under the River 
and Harbor Act of 1970 and was approximately 15% 
complete as of September 30, 1989. 
Maintenance, Norfolk District: A condition survey of 
the Rappahannock Shoal Channel was made. Maintenance 
dredging of 213,200 cubic yards of material from 
the York Spit Channel (Contract II) at a cost of $437,060 
commenced on May 14, 1988 in conjunction with new 
work dredging of the work authorized under the River 
and Harbor Act of 1970 and was completed on March 
19, 1989. Maintenance dredging of 213,200 cubic yards 
of material from the Cape Henry Channel at a cost of 
$437,060 commenced on April 5, 1989 in conjunction with 
new work dredging of the work authorized under the 
River and Harbor Act of 1970 and was 87% complete as 
of September 30, 1989. 
2. BALTIMORE HARBOR, MD 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Project applies to Baltimore Harbor, MD, 
and its tributaries. 
Existing project. Provides for collection and removal 
of drift from Baltimore Harbor and its tributary waters, 
and authorizes the Secretary of the Army to allot such 
amounts as may be necessary for work from appropriations 
for maintenance and improvement of existing river 
and harbor works or other available appropriations, and 
that this work shall be carried as a separate and distinct 
project. It is wholly a work of maintenance. Purpose of 
work is to afford relief from variable conditions of 
obstruction. 
Local cooperation. None required. 
Terminal facilities. See Section 1 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations, by hired labor, consisted of collection 
and disposal of 16,740 cubic feet of driftwood, 
ranging from small blocks up to timbers of large 
dimensions. 
3. CAMBRIDGE HARBOR, MD 
Location. This harbor is a tidal estuary on the south 
side of Choptank River about 18 miles above its mouth. 
It is approximately 70 miles southeast of Baltimore 
Harbor. (See Coast and Geodetic Survey Chart 1225.) 
Previous project. For details see page 1789 of Annual 
Report for 1915, page 424 of Annual Report for 1924, and 
page 373 of Annual Report for 1938. 
Existing project. Provides for a channel 150 feet wide 
and 25 feet deep at mean low water from that depth in 
the Choptank River for an approximate distance of 2,000 
feet; then widen into a triangular shaped turning basin 
25 feet deep, 1,400 feet long and 750 feet wvide; then 
continue with a channel 150 feet wide and 16 feet deep 
to the Market Street Bridge over Cambridge Creek; then 
100 feet wide and 16 feet deep to the head of the harbor 
with a turning basin of the same depth and irregular 
dimensions comprising approximately 2.4 acres; an 
anchorage basin 10 feet deep, 400 feet long and 175 feet 
wide on the west side of the channel; another basin of 
the same depth, 225 feet long, and 200 feet wide on the 
east side of the channel below the bridge; and a channel 
60 feet wide and 7 feet deep from that depth in the 
Choptank River to the municipal boat basin north of the 
harbor entrance. 
Local cooperation. Fully complied with except local 
interests are to furnish spoil disposal areas for future 
maintenance. 
Terminal facilities. The waterfront of Cambridge is 
generally built of solid bulkhead wharves and pile and 
timber piers, only a few of which have mechanical freighthandling 
facilities. With the exception of a State owned 
terminal which is open to the public, the wharves are privately 
owned. There are town marine railways with boatrepair 
shops, five oil and gasoline terminals, two large 
fertilizer companies and one large packing house located 
on the shore of Cambridge Creek. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was completed 
November 11, 1988. A total of 36,000 cubic yards 
of material was removed. 
4-4

BALTIMORE, MD DISTRICT 
4. CRISFIELD HARBOR, MD 
Location. Along western limits of town of Crisfield on 
east bank of Little Annemessex River, an estuary of 
Tangier Sound on east side of Chesapeake Bay. (See 
Coast and Geodetic Survey Chart 1224.) 
Previous project. For details see page 279 of Annual 
Report for 1962. 
Existing project. A channel 12 feet deep at mean low 
water, 425 feet wide from the 12-foot depth curve in 
Tangier Sound to Somers Cove Light, thence 266 feet 
wide to the bend about 1,800 feet southwest of railroad 
pier, and thence of irregular width to a point opposite 
Consumers Ice Co.; a spur channel 10 feet deep and 100 
feet wide from the ice plant to Hop Point; a channel 7 
feet deep and 60 feet wide from the 7-foot depth curve 
in Little Annemessex River via Cedar Creek, a landcut, 
and Daugherty Creek Canal to Big Annemessex River; 
a mooring basin 7 feet deep, 160 feet wide and about 875 
feet long roughly parallel to Brick Kiln Road, with a 
channel 7 feet deep and 100 feet wide leading therefrom 
to 7-foot project channel connecting Little Annemessex 
and Big Annemessex Rivers; and an anchorage basin in 
Somers Cove 10 feet deep, 600 feet wide, and 1,000 feet 
long, with an approach channel 10 feet deep and 60 feet 
wide from the 10-foot depth curve in Little Annemessex 
River through the present entrance to Somers Cove. 
Mean range of tide at Crisfield is about 1.9 feet. 
Local cooperation. Local interests have furnished spoil 
disposal areas as needed for proposed fiscal year 1990 
maintenance dredging. 
Terminal facilities. Waterfront of Crisfield Harbor is 
built up principally with solid-bulkhead wharves and pileand-
timber piers. Most wharves are privately owned, but 
are open to the public for transaction of business with 
the owners. Few of the terminals have mechanical freighthandling 
devices, but most of the freight is transferred 
by hand. There are three boat-repair yards with marine 
railways having capacities up to 250 tons. Existing 
terminals are adequate for present and reasonably 
prospective commerce. Sufficient areas are available 
north of Hop Point and on Somers Cove for construction 
of additional terminals as needed. 
Operations and results during fiscal year. Maintenance: 
Engineering and design was accomplished in 
connection with proposed maintenance dredging in fiscal 
year 1990. 
5. FISHING BAY, MD 
Location. McCreadys, Goose, and Farm Creeks are 
small tidal estuaries of Fishing Bay, a large estuary at 
head of Tangier Sound. Fishing Bay is connected by 
Hooper Strait with Chesapeake Bay to the west about 
15 miles above mouth of Potomac River. Goose Creek 
enters the bay about 3.5 miles above the mouth. Farm 
Creek enters Fishing Bay about 6 miles above the mouth 
and approximately opposite mouth of McCreadys Creek. 
(See Coast and Geodetic Survey Chart 1224.) 
Existing project. Provides for channels 6 feet deep and 
generally 60 feet wide at mean low water, suitable 
widened where necessary to offer adequate sheltered 
anchorage space from deep water in Fishing Bay to 
vicinity of county or packing house wharves in 
McCreadys, Farm, and Goose Creeks. Mean range of tide 
is about 2 feet. 
Terminal Facilities. A public wharf built with aid of 
Federal funds is on McCreadys Creek about 200 feet 
above the mouth. There is a privately owned pile-andtimber 
pier about 1,500 feet above the mouth of Goose 
Creek. There are two privately owned wharves on Farm 
Creek and a public wharf owned by Dorchester County. 
Private wharves on each of the waterways are open to 
the public for transaction of business with the owners. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was completed 
on June 22, 1989, at Goose Creek. A total of 28,021 
cubic yards of material was removed. Dredging of 
McCready Creek and Farm Creek are planned for fiscal 
year 1990. 
6. HERRING BAY AND 
ROCKHOLD CREEK, MD 
Location. Herring Bay is a wide-mouthed indentation 
on the west side of Chesapeake Bay about 20 miles below 
Annapolis, MD. It is about 3 miles long from north to 
south and penetrates the shore for a depth of about 1 
mile. Rockhold Creek, which is about 2.5 miles long, is 
an estuary which extends northward from the northerly 
end of Herring Bay. (See U.S. Coast and Geodetic Survey 
Chart 1225.) 
Existing project. Provides for channel 7 feet deep and 
60 feet wide from 7-foot contour in Herring Bay to 
vicinity of county wharf on Rockhold Creek, with turning 
basin of same depth, 100 feet wide and 150 feet long 
at head of channel, and a stone breakwater approximately 
900 feet long east of entrance channel. Mean 
range of tide is about 1.5 feet and extreme tidal range 
about 4 feet. The Federal cost of new work for completed 
project was $50,591. 
Local cooperation. Fully complied with except local 
interests are to furnish disposal areas for future maintenance 
as needed. 
Terminal facilities. Consists of a public wharf on Rockhold 
Creek about 600 feet below the county bridge, open 
to all, together with a few private landing stages. No 
freight-handling devices are installed on any of the 
wharves which are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Modification for fiscal year 1988 maintenance 
dredging contract was paid to settle the contractor's 
claim. 
4-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
7. HERRING CREEK, 
TALL TIMBERS, MD 
Location. Herring Creek in St. Marys County, MD, is 
a small tidal stream 13 miles in length which flows in 
a westerly direction and enters the north bank of the 
Potomac River 16 miles upstream of its mouth at 
Chesapeake Bay and 92 miles downstream from 
Washington, DC (See U.S. Coast and Geodetic Survey 
Chart No. 557.) 
Existing project. This provides for an entrance channel 
6 feet deep, 60 feet wide, and approximately 1,630 feet 
long extending from deep water in the Potomac River to 
deep water within the creek, a turning basin of irregular 
shape 6 feet deep adjacent to the proposed public wharf, 
and riprap-stone jetties on the upstream and downstream 
sides of the entrance channel 770 and 650 feet long, 
respectively. The plane of reference is mean low water. 
The tidal ranges are: Mean, 1.6 feet; irregular, 1.9 feet; 
and extreme, approximately 7 feet. The project was modified 
in 1986 under Section 111 of the River and Harbor 
Act of 1968. The modification consists of constructing 
250 feet of beachfill, 2,187 linear feet of stone revetment 
and upgrading 350 linear feet of existing revetment along 
the Tall Timbers waterfront south of the project inlet to 
preclude shoreline erosion induced by the project jetties. 
Local cooperation. The Local Cooperation Agreement 
(LCA) includes the following provisions: 
1. Compliance with the Uniform Relocation Assistance 
and Real Property Acquisitions Policies Act of 1970. 
2. Provide without cost to the United States, when 
and as required all lands, easements, rights-of-way 
and soil-disposal areas necessary for the construction 
and subsequent maintenance of the project. 
3. Hold and save the United States free from damages 
to other property resulting from the improvement. 
Terminal facilities. There are a number of small 
wharves and landings within the creek, all privately 
owned. The facilities are considered adequate for present 
commerce. 
Operations and results during fiscal year. New work: 
Locals were reimbursed $215,359 required by the modified 
Local Cooperation Agreement (LCA). Maintenance: 
Maintenance of the beachfill portion of the project was 
deferred due to the inability of local interests to obtain 
the necessary lands, easements, and rights-of-way. 
8. HONGA RIVER AND TAR BAY 
(BARREN ISLAND GAPS), MD 
Location. Honga River is a tidal estuary of Chesapeake 
Bay and penetrates Dorchester County on Eastern Shore 
of Maryland between Hooper Islands and the mainlands; 
Tar Bay lies between Barren Island and the mainland and 
Hooper Islands. Fishing Creek connects Tar Bay and 
Honga River. Back Creek is a branch of Honga River extending 
into Hooper Islands; the mouth is about 2 miles 
south of Fishing Creek. (See Coast and Geodetic Survey 
Chart 1224.) 
Existing project. Provides for a channel 60 feet wide 
and 7 feet deep at mean low water from the 7-foot contour 
in Chesapeake Bay, through Tar Bay and Fishing 
Creek to the 7-foot contour in Honga River, 25,300 feet 
long, and a channel in Back Creek 7 feet deep and 60 feet 
wide from the 7-foot depth curve in Honga River to a 
point near the head of Back Creek with a turning basin 
of the same depth 150 feet long and 200 feet wide at the 
head of channel, about 5,500 feet long. Mean range of tide 
is about 1.4 feet. Federal cost of new work for the completed 
project was $66,119. 
Local cooperation. Local interests furnished spoil placement 
areas for maintenance dredging in fiscal year 1990. 
Terminal facilities. Numerous small private wharves 
are scattered along Fishing Creek and Back Creek. A 
public wharf is on Fishing Creek. A public wharf, 4 oyster 
houses, and a marine railway are on Back Creek. Facilities 
are adequate for existing and reasonable prospective 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished in connection 
with proposed maintenance dredging in fiscal 
year 1990. 
9. LITTLE WICOMICO RIVER, VA 
Location. A tidal estuary 6 miles long in Northumberland 
County, VA, flowing southeasterly to Potomac 
River, which it enters on the right bank one-half mile upstream 
of its mouth and about 108 miles downstream 
from Washington, DC. (See U.S. Coast and Geodetic Survey 
Chart 1223.) 
Existing project. A channel 8 feet deep, 150 feet wide, 
and 4,800 feet long, extending from deep water in the 
Potomac River to deep water in the Little Wicomico 
River; two stone jetties, extending to the 8-foot contour 
in Potomac River; and bulkhead walls from the inner ends 
thereof extending sufficiently into Little Wicomico River 
to stabilize the dredged inner channel. Plane of reference 
is mean low water. Tidal ranges in Potomac River at the 
entrance are: Mean 1.2 feet; irregular, 2.5 feet; and extreme, 
about 7 feet. Mean tidal range within the river is 
about 1 foot. Federal cost of new work for the completed 
project was $81,885, exclusive of $5,000 contributed 
by local interests. 
Local cooperation. Fully complied with. 
Terminal facilities. Two wharves open to the public 
and numerous small wharves and stagings for private 
use, an oyster shucking, and packing plant, and a marine 
railway and boat-building yard. Facilities are considered 
adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
4-6

BALTIMORE, MD DISTRICT 
10. MONROE BAY AND CREEK, VA 
Location. Monroe Bay is an indentation on the right 
bank of Potomac River in Westmoreland County, VA, 34 
miles upstream of Chesapeake Bay and 75 miles downstream 
from Washington, DC. Monroe Creek is a tidal 
stream 5 miles long which flows southerly and discharges 
into Monroe Bay. (See Coast and Geodetic Survey Chart 
558.) 
Existing project. A channel 8 feet deep, 100 feet wide, 
and 950 feet long, through the bar at the entrance, and 
within the creek a channel 7 feet deep, 100 feet wide, and 
2,500 feet long, with turning and anchorage basin 500 
feet wide at upper end in vicinity of Colonial Beach waterworks. 
The mean range of tide is 1.6 feet. Cost of new 
work for completed project was $12,460. 
Local cooperation. Fully complied with. 
Terminal facilities. There are numerous wharves and 
landings in the creek, of which 3 are open to the public. 
There are two marine railways. 
Operations and results during fiscal year. Maintenance: 
Dredging of the entrance channel to Monroe 
Creek, by contract, began on March 15, 1989 and was 
completed on April 6, 1989. A total of 8,561 cubic yards 
of material was removed and deposited ashore in an approved 
disposal area at a cost of $139,842. 
11. NANTICOKE RIVER (INCLUDING 
NORTHWEST FORK), DE & MD 
Location. Headwaters of Nanticoke River consist of 
numerous branches rising mainly in the northern portion 
of Sussex County, DE. The river is about 50 miles long 
and flows southwesterly from its source to Tangier 
Sound. 
Northwest Fork is a branch of Nanticoke River which 
rises in Kent County, DE, and flows past Federalsburg, 
MD, generally southerly through Dorchester County, 
MD, to its junction with the main river opposite Riverton, 
MD. It is about 30 miles long. (See Coast and Geodetic 
Survey Chart 77.) 
Existing project. Nanticoke River: Channel 12 feet deep 
and 100 feet wide from the 12-foot depth curve in Tangier 
Sound to the highway bridge at Seaford, DE, with a turning 
basin at the upper end. Disjointed sections included 
in the project is about 4 miles long, extending over 32 
miles of river; lower end of the first section of the project 
is about 8 miles above the mouth of the river. Mean range 
of tide is 3.4 feet, and the extreme tidal range is 4.3 feet. 
Northwest Fork: Dredging a channel 6 feet deep and 
60 feet wide at mean low water from upper Browns wharf 
to within one-half mile of the southern boundary of town 
of Federalsburg, with a turning basin at the upper end. 
Section included in the project is about 4 miles long, and 
its lower end is 11.75 miles above the mouth of the river. 
Mean range of tide is 2.6 feet. 
Local cooperation. Local interests furnished a spoil disposal 
area for proposed fiscal year 1990 maintenance 
dredging. Locals are also required to hold and save the 
United States free from all damages. 
Terminal facilities. Waterfront at Seaford consists 
largely of unconnected pile-and-timber bulkhead wharves 
with earthfills. One public wharf is used as a launching 
ramp. Remaining wharves are privately owned. A rail siding 
extends along a considerable portion of waterfront 
and offers facilities for interchange of rail and water 
traffic. Existing terminals are reasonably adequate for 
present and prospective commerce. 
Terminal facilities on Northwest Fork are all privately 
owned and open to general public use. They consist 
of one solid bulkhead wharf of 80-foot frontage and 3 
landings each with 60-foot frontages. Depths of water are 
from 2 to 8 feet. Landings are log revetments backed by 
earthfill and are in poor condition. 
Operations and results during fiscal year. Maintenance: 
Engineering and design was accomplished in 
connection with proposed fiscal year 1990 maintenance 
dredging. 
12. OCEAN CITY HARBOR AND 
INLET AND SINEPUXENT BAY, MD 
Location. Ocean City is on a barrier island between 
Sinepuxent Bay and Atlantic Ocean about 35 miles south 
of entrance to Delaware Bay. (See U.S. Coast and 
Geodetic Survey Chart 1220.) 
Existing project. This provides for an inlet channel 300 
feet wide and 16 feet deep from the 16-foot depth curve 
in Atlantic Ocean through the inlet to the channel in the 
Isle of Wight Bay, protected on the south side by a stone 
jetty with a top elevation of 8.8 feet above mean low 
water and a top width of 18 feet, and on the north side 
by a stone jetty with a top elevation of 9 feet above mean 
low water and a top width of generally 20 feet, thence 
generally 200 feet wide and 16 feet deep to the project 
harbor; a depth of 14 feet and 150 feet wide to the head 
of the harbor, a length of approximately 3,400 feet; a 
channel 6 feet deep and 150 feet wide in Sinepuxent Bay 
from the inlet to Green Point, and thence 100 feet wide 
in Chincoteague Bay; and for a channel 6 feet deep and 
125 feet wide from the inlet channel to a point opposite 
North Eighth Street in Ocean City, thence 75 feet wide 
into the Isle of Wight Bay. Depths in the inlet channel 
and harbor refer to project datum. Depths in the bay 
channels refer to mean low water. 
The elevation of mean low water in the bays above 
mean low water in the ocean at Ocean City varies from 
about 0.8 foot in the vicinity of the inlet to 1.7 feet at 
their heads. The mean range of ocean tide is 3.4 feet. The 
extreme range is from 3 feet below mean low water to 
about 3.5 feet above mean high water, a total of 9.9 feet. 
In the bays the mean range of tide varies from approximately 
2.5 feet at the inlet to 0.3 foot at their heads. 
Greater fluctuations are caused by prolonged high winds. 
Federal cost of new work for the completed project was 
$1,190,530, exclusive of $500,000 contributed by local 
interests and exclusive of $3,700,000 for rehabilitating 
the south jetty. 
4-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Fully complied with except local 
interests must furnish spoil disposal areas for future 
maintenance as needed. 
Terminal facilities. On bay side of Ocean City: two 
storage basins, for pleasure and small commercial craft, 
and numerous privately owned pile-and-timber piers and 
bulkhead wharves. At project harbor: a public landing 
about 1,000 feet long, several privately constructed bulkhead 
wharves open to the public for transaction of business 
with the owners, and a boat repair yard with a 
marine railway capable of handling boats up to about 150 
tons. All piers and wharves are accessible by highway. 
Port facilities have been expanded to include all available 
space in the Fish Harbor. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
Hydrographic surveys determined that no maintenance 
dredging was required this fiscal year. 
13. POCOMOKE RIVER, MD 
Location. Pocomoke River is a tributary of Pocomoke 
Sound, a tidal estuary on the east side of Chesapeake Bay 
about 40 miles north of Cape Charles, VA. 
Existing project. Provides for a channel 11 feet deep 
at mean low water and 150 feet wide from the 11-foot 
depth in Pocomoke Sound to Tulls Point, thence 100 feet 
wide to deep water in Pocomoke River above Williams 
Point, and for construction of a dike along the offshore 
side of channel between Tulls Point and the end of the 
existing dike; and a channel 9 feet deep at mean low water 
and 100 to 130 feet wide from Shad Landing to the bridge 
at Snow Hill. Length of project is about 8.7 miles from 
Pocomoke Sound to Williams Point, and about 4.5 miles 
from Shad Landing to Snow Hill, MD. Shad Landing is 
about 25.7 miles above the mouth of the river. 
Mean range of tide is 2.4 feet in Pocomoke Sound and 
2.5 feet in the river at Snow Hill. Prolonged high winds 
on Chesapeake Bay frequently cause greater fluctuations. 
Estimated cost (1969) for new work is $1,071,458 exclusive 
of amounts expended under previous projects. Extension 
of channel above the bridge at Snow Hill, 100 feet 
wide, 9 feet deep and widened to 150 feet to form a turning 
basin at upper end, if considered inactive and is excluded 
from the foregoing estimate. Estimated cost of 
this portion is $22,000 (1956). 
Local cooperation. Complied with for section of project 
from Pocomoke Sound to Pocomoke River and from Shad 
Landing to the highway bridge at Snow Hill, authorized 
by acts of June 3, 1896, and August 30, 1935, except local 
interests must furnish releases from damage to oyster 
beds and spoil disposal areas as required for future maintenance. 
Terms for the section of the project above the 
highway bridge at Snow Hill, authorized by act of March 
2, 1945, required local interests to furnish all lands, easements, 
rights-of-way, and spoil disposal areas for initial 
work and future maintenance, hold the United States free 
from damages resulting from the improvement; and 
contribute one-half the initial cost of that portion of 
project, but not to exceed $4,250. This portion is considered 
inactive. Terms for the 11-foot depth channel 
from Pocomoke Sound to deep water in Pocomoke River 
above Williams Point, authorized by act of September 
3, 1954, require local interests provide all lands, easements, 
rights-of-way, and spoil disposal areas for construction 
and future maintenance of the project; and hold 
the United States free from damages due to construction 
and maintenance, including such damages as may occur 
to the public or leased oyster beds. 
Terminal facilities. Waterfronts at Pocomoke City and 
Snow Hill are built up principally with earthfilled timber 
bulkheads, the majority of which are privately owned. 
A few of the warehouses and factories on the river at 
these communities have railroad sidings and mechanical 
freighthandling facilities. Any appreciable increase in 
commerce at Pocomoke City or Snow Hill would necessitate 
construction of new facilities and repair of existing 
structures. Adequate space is available for development 
of additional terminals. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed fiscal year 1990 maintenance 
dredging. 
14. POTOMAC AND ANACOSTIA 
RIVERS, DC COLLECTION AND 
REMOVAL OF DRIFT 
Location. Project applies to the Potomac and 
Anacostia Rivers, Washington, DC and their tributaries. 
Existing project. Collection and removal of drift from 
the waters of the Potomac and Anacostia Rivers and 
their tributaries in the Washington area from the head 
of tidewater to Mount Vernon, VA. Total length of 
project, considering both sides of the waterway, is about 
50 miles. 
Local cooperation. None required. 
Terminal facilities. See Section 23 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations by hired labor consisted of collection 
and disposal of 203,040 cubic feet of driftwood, ranging 
from small blocks up to timbers of large dimensions. 
15. POTOMAC RIVER AQUATIC PLANT 
CONTROL, MD, VA, DC 
Location. The project is located in the Potomac River 
and its tributaries with the northern boundary at Chain 
Bridge in Washington, DC extending southward to the 
U.S. Route 301 Bridge (See U.S. Coast and Geodetic 
Chart 12289). 
Existing project. On July 2, 1986 the Chief of Engineers 
under the authority of Section 302 of the 1965 
River and Harbor Act, as amended, authorized the control 
of hydrilla and other nuisance plants using mechanical 
harvesting to clear a 60 foot wide, 6 foot deep 
connecting channel from open waters to eligible public 
use areas. 
4-8

BALTIMORE, MD DISTRICT 
Local cooperation. The Local Cooperation Agreement 
(LCA) was signed on June 6, 1986 between the Corps, 
MD, VA, DC and Metropolitan Washington Council 
of Governments. The LCA which must be reexecuted 
annually expired on September 30, 1989 included the following 
provisions: 1. Local sponsors share 50 percent of 
the program cost; 2. Local sponsors provide lands, easements, 
and rights-of-way; 3. Metropolitan Washington 
Council of Governments is responsible for coordinating 
local interests and issuing work orders for the program. 
Terminal facilities. There are 75 marina activities 
between DC and the U.S. Route 50 Bridge providing 
approximately 3,400 commercial and recreational boat 
slips and 50 boat ramps. 
Operations and results during fiscal year. New Work: 
Harvesting operations resulted in 36 acres of nuisance 
aquatic plants at sites in Maryland and Virginia. There 
were no harvesting operations conducted in District of 
Columbia this fiscal year. 
16. POTOMAC RIVER BELOW 
WASHINGTON, DC 
Location. Potomac River is formed 21 miles below 
Cumberland, MD, and flows southeasterly about 285 
miles and enters Chesapeake Bay, about 80 miles from 
Atlantic Ocean. Washington, DC is 108 miles upstream 
of mouth, and head of tidewater is at mile 117. (See Coast 
and Geodetic Survey Charts Nos. 557, 558, 559, and 560.) 
Existing project. Provides for a channel 24 feet deep 
and 200 feet wide between the mouth of the river and 
Giesboro Point at Washington, DC a distance of 108 
miles. Plane of reference is mean low water. Tidal ranges 
are: mean, 1.3 feet at mouth, 2.9 feet at Washington; 
irregular, 2 feet at mouth, 4.5 feet at Washington; extreme, 
about 6 feet at mouth, 10.7 feet at Washington. 
Federal cost of new work for the completed project was 
$153,836. 
Local cooperation. None required. 
Terminal facilities. In general, the improvement is a 
main river channel, and terminal facilities are only served 
where the channel runs close to either bank of river. In 
all, 11 wharves are thus served. These wharves are of 
open and solid fill construction and bulkhead type. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
17. PREVENTION OF OBSTRUCTIONS & 
INJURIOUS DEPOSITS, 
BALTIMORE, MD 
Location. Project applies to tidal waters of the harbor 
of Baltimore and its adjacent and tributary waters and 
to all tidal waters of Chesapeake Bay and in Maryland. 
Existing project. Patrol and inspection throughout the 
project location to detect violations of sections 13 and 
15 of the River and Harbor Act of March 3, 1899 and 
to investigate obstructions to navigation pursuant to 
Federal regulations (33 CFR 209.109). 
Local cooperation. None required. 
Operations and results during fiscal year. Maintanance: 
Operations, by Supervisor of Harbor of Baltimore 
included inspections of approximately 75 Federal 
navigation channels within the project location to insure 
channels are not obstructed to general navigation by 
debris, sunken vessels/wrecks and/or fishing appurtenance. 
There were two detailed investigations of obstructions 
or sunken vessels/wrecks. Neither of these 
affected approaches to private docks and required no further 
action. 
18. SHALLOW CREEK, BALTIMORE, MD 
Location. Shallow Creek is a tidal water tributary of 
the Chesapeake Bay and is located directly adjacent to 
Fort Howard Veteran's Hospital in southeast Baltimore 
County, approximately 10 miles southeast of Baltimore, 
Maryland. (See NOAA Chart No. 12278.) 
Existing project. Provides for a channel 50 feet wide 
and 5 feet deep from that depth in Chesapeake Bay to 
and including a turning basin of the same depth, 100 feet 
wide and 100 feet long at the head of the channel. Total 
project length is 4,000 feet. 
Local cooperation. Fully complied with except local interests 
are required to provide or pay to the Government 
the full cost of providing dredged material disposal areas 
for future maintenance as needed. 
Terminal facilities. There are a number of small 
wharves and landings within the creek, all privately 
owned. The facilities are considered adequate for present 
commerce. 
Operations and results during fiscal year. New Work: 
A dredging contract was completed on March 9, 1988. 
A total of 36,000 cubic yards of material was removed 
at a cost of $401,924. 
19. ST. CATHERINES SOUND, MD 
Location. St. Catherines Sound, a tidal estuary of the 
Potomac River, is in St. Marys County, MD. It is situated 
near the junction of the Potomac and Wicomico 
Rivers, 34 miles upstream of the Chesapeake Bay, and 
76 miles south of Washington, DC. It is 2 miles in length 
and flows in a southeasterly direction parallel with the 
Potomac River. (See U.S. Coast and Geodetic Survey 
Chart 558.) 
Existing project. Provides for a channel 6 feet deep, 
100 feet wide and 700 feet long at the lower entrance from 
the Potomac River and a channel 6 feet deep, 80 feet wide 
and 3,300 feet long at the upper entrance from the 
Wicomico River. Mean range of tide is 1.9 feet. 
The cost to the Federal Government for new work for 
the completed project was $29,947, exclusive of $600 contributed 
by local interests. 
4-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Fully complied with, except that 
local interests are to furnish releases from damages and 
spoil disposal areas for future maintenance as required. 
Total actual costs for all requirements of local cooperation 
under terms of the project authorization, including 
required non-Federal contributions, amount to $600. 
Terminal facilities. There are numerous privately 
owned wharves and stagings located in St. Catherines 
Sound and White Neck Creek, a tributary of St. Catherines 
Sound, of which three are open to the public. There are 
two marine railways in White Neck Creek. The terminal 
facilities are considered adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was awarded 
on April 16, 1989 and completed on April 29, 1989. A 
total of 17,724 cubic yards of material was removed. 
20. WASHINGTON HARBOR, DC 
Location. Within District of Columbia at junction of 
Anacostia River with Potomac River which flows southeasterly 
108 miles to Chesapeake Bay. It is southerly 202 
miles by water from Baltimore, MD, and northerly 195 
miles from Norfolk, VA. (See U.S. Coast and Geodetic 
Survey Chart 12289.) 
Existing projects. A combination and extension of 
latest projects for Potomac River at Washington, DC, 
and Anacostia River, DC. The Washington Harbor 
project provides for a channel in the Potomac River from 
Giesboro Point to Key Bridge, a second channel from 
Giesboro Point to the end of Washington Channel, and 
a third channel from the mouth of the Anacostia River 
to the foot of 15th Street, SE, with turning basins opposite 
the Naval Weapons Plant (800 feet wide and 2,400 
feet long) and at the head of the Anacostia Channel (400 
feet square). Channel dimensions are 24 feet deep and 400 
feet wide except upstream from Anacostia Bridge where 
the width is reduced to 200 feet and from Giesboro Point 
to a point 3,000 feet downstream of Arlington Memorial 
Bridge and above Easby Point where channel dimensions 
are 20 feet deep and 200 feet wide. Channel lengths including 
turning basins are: Virginia Channel, 5,000 feet; 
Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and operation and maintenance of the inlet 
gates and lock and the outlet gates of the Tidal Basin 
constructed under a previous project to flush Washington 
Channel. Plane of reference is low-water datum which 
is 0.35 foot below mean low tide as observed from 1932 
to 1942. Tidal ranges are: mean, 2.9 feet; irregular, 4.5 
feet; and extreme, 10.7 feet. Federal cost of new work for 
the completed project was $162,006. 
Local cooperation. None required. 
Terminal facilities. There are four wharves generally 
of bulkhead type on Virginia Channel that are privately 
owned and not open to the public except by special 
arrangement. On Washington Channel there are four 
piers under jurisdiction of District of Columbia, two of 
which are open to the public and one open to the public 
by special arrangement. In Anacostia River there are four 
privately owned piers and eight governmental piers and 
slips. None of the piers are open to the public except by 
special arrangement. Terminal facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
The tidal basin gates were inspected and maintained 
by hired labor. 
21. WICOMICO RIVER, MD 
Location. Wicomico River has its source in northern 
part of Wicomico County, MD, and flows generally southwardly 
emptying into Monie Bay, a tributary of Tangier 
Sound on the east side of Chesapeake Bay about 85 miles 
southeast of Baltimore. Webster Cove is site of improved 
small-boat harbor on southeast bank of Wicomico River 
about 3 miles above the mouth. (See U.S. Coast and 
Geodetic Survey Charts 567 and 1224.) 
Existing project. Channel 14 feet deep and 150 feet 
wide from Chesapeake Bay to Salisbury, section included 
in project is 37 miles long, including about 12 miles 
from mouth of river to Chesapeake Bay; 14 feet deep in 
channels and turning basins in north and south prongs 
with channel widths of 100 feet, and a channel 6 feet deep 
and 60 feet wide extending from 6-foot contour in 
Wicomico River to and including a basin in Webster Cove 
of same depth, 100 feet wide and 400 feet long; and 
extension of basin 200 feet long and 100 feet wide on each 
side. Plane of reference is mean low water. Mean range 
of tide is about 3 feet and extreme tidal range is 4.4 feet. 
Cost of new work for completed project was $421,609, 
exclusive of amounts expended on previous project. 
Local cooperation. Fully complied with, except that 
local interests are to furnish spoil disposal areas for 
future maintenance as needed and hold the United States 
free from such damages as may occur to public or leased 
oyster beds. 
Terminal facilities. Present waterfront at Salisbury 
consists of pile-and-timber bulkheads with earthfills. 
Some wharves have warehouses and factories with 
mechanical freight-handling facilities and rail sidings. All 
terminals are privately owned. A shipyard, with two 
marine railways with capacities of 1,200 and 500 tons, 
respectively, is on right bank of river below prongs. Areas 
for development of new terminals on north prong are 
limited. Areas for considerable expansion of terminal 
facilities are available on main river. There is a pileand-
timber wharf about 4 miles above mouth of river at 
Mount Vernon. A wharf of similar construction is at 
White Haven. There is a county wharf at head of basin 
in Webster Cove, a pile-and-timber pier at oyster house 
on southwest side of basin, a T-shaped pile-and-timber 
pier at cafe on southwest side of basin and several small 
timber piers on walkways that local interests constructed 
around the basin. Fueling facilities are available at the 
T-shaped pier. Sufficient areas are available for construction 
of additional facilities when required. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was completed 
on December 4, 1988. A total of 200,000 cubic yards 
of material was removed. 
4-10

BALTIMORE, MD DISTRICT 
22. RECONNAISSANCE AND CONDITION 
SURVEYS 
(See Table 4-H at end of chapter.) 
23. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year costs were $14,990 for Cambridge Harbor, 
MD; $28,521 for Island Creek, St. Marys Co., MD; 
$26,805 for Solomon Island Harbors, MD; and $9,527 for 
Tedious Creek, Dorchester Co., MD. 
Beach Erosion Control 
24. BEACH EROSION 
CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Beach Erosion Control pursuant to Sec. 103 of Public 
Law 727, as amended (preauthorization). 
Fiscal year costs were $40,566 for town of North Beach, 
MD. 
Non-Federal contributed costs for the fiscal year were 
$1,346 for town of North Beach, MD. 
Flood Control 
25. CUMBERLAND, MD, AND 
RIDGELEY, WV 
Location. On North Branch of Potomac River, 21 miles 
upstream from its junction with the South Branch of the 
Potomac River and 197 miles upstream from Washington, 
DC. (See Geological Survey Quadrangles, Frostburg 
and Flintstone, MD, WV, and PA.) 
Existing project. Channel improvements of North 
Branch of Potomac River from the Western Maryland 
Railway bridge in South Cumberland upstream to the 
mouth of Wills Creek, with levees and fill along the left 
bank and levees along the right bank from downstream 
corporate limits of Ridgeley, WV, to a point about 150 
feet above Johnson Street Bridge; channel improvements 
along Wills Creek from its mouth upstream to a point 
in the Narrows about 500 feet upstream from the highway 
bridge on U.S. Highway 40; levee and flood wall in 
West Cumberland, MD, on the left bank of the North 
Branch of the Potomac River from the mouth of Wills 
Creek upstream to Kelly Boulevard; levee and flood wall 
in Ridgeley, WV, on the right bank of the North Branch 
of the Potomac River from Carpenter Avenue upstream 
to Patapsco Street near the upstream corporate limits 
of Ridgeley, WV; interior drainage facilities in Cumberland 
and West Cumberland, MD, and Ridgeley, WV; 
removal of the Chesapeake and Ohio Canal dam and construction 
of a new industrial dam on the North Branch 
of the Potomac River immediately above mouth of Wills 
Creek; and alteration and reconstruction of highway and 
railroad bridges. Federal costs of new work for the completed 
project were $15,633,970, which includes $49,998 
emergency relief funds and is exclusive of $197,513 public 
works acceleration funds. Estimated cost to local interests 
is $2,900,000 of which $1,402,001 is contributed 
funds and $1,497,999 is for lands and damages. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Removal of gravel deposits, grass cutting of 
areas channelward of levees, and removal of brush and 
debris from channel were accomplished as required in 
channel area. 
26. HILLS POINT ROAD, 
DORCHESTER CO., MD 
Location. Hills Point Road (Maryland State Route 343) 
is located in Dorchester County on Brannock Bay 
approximately 10 miles west of Cambridge, Maryland. 
(See NOAA Chart No. 12266.) 
Existing project. On August 19, 1988, the Chief of 
Engineers, under the authority provided by Section 14 
of the 1946 Flood Control Act, as amended, authorized 
the construction of stream bank protection. The work 
consists of five offshore stone rubble mound breakwaters, 
each 50 feet long, located a distance of about 100 feet 
offshore. The project also provides for bank stabilization 
with beachfill and planting of vegetation to prevent erosion 
of the roadway. The project is designed to prevent 
erosion and storm damage to Hills Point Road which 
services the community of Thomas, Maryland. The estimated 
project implementation cost is $191,700 of which 
$47,900 will be funded by the sponsor. 
Local cooperation. The July 19, 1988 Local Cooperation 
Agreement between DOA and Dorchester County, 
MD, in brief requires the local sponsor to: Provide all 
lands, easements and rights-of-way; provide modifications 
and relocations of buildings, roads, bridges, and 
related utilities; operate and maintain completed works; 
hold and save U.S. from damages; pay 25 percent of the 
total project costs; provide cash contribution not less 
than 5 percent of total project costs; assume responsibility 
for all costs in excess of the $500,000 Federal 
limitation. 
Operations and results during fiscal year. New Work: 
The construction contract was awarded on December 27, 
1988 in the amount of $148,728 and was physically completed 
on May 3, 1989. 
27. ISLE OF WIGHT BAY, 
OCEAN CITY, MD 
Location. The project is located on Chicago Avenue 
along the Isle of Wight Bay between 2nd and 4th Streets, 
in downtown Ocean City, Worcester County, Maryland. 
Ocean City is located on the Atlantic Ocean approximately 
20 miles south of the Maryland-Delaware line. (See 
NOAA Chart No. 12211.) 
4-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. On October 6, 1988 the Chief of Engineers, 
under the authority provided by Section 14 of 
the 1946 Flood Control Act, as amended, authorized the 
construction of shoreline protection. The work consists 
of the placement of 3,500 tons of stone against a deteriorated 
steel sheetpile bulkhead along Chicago Avenue. 
This stone is required to prevent the bayward movement 
of the bulkhead due to increased scour at the toe of bulkhead. 
The estimated project implementation cost is 
$520,000 of which the sponsor will be paying $127,600. 
Local cooperation. The July 14, 1988 Local Cooperation 
Agreement between DOA and Ocean City, in brief, 
requires the local sponsor to: Provide all lands, easements 
and rights-of-way; provide modifications and relocations 
of buildings, roads, bridges, and related utilities; operate 
and maintain completed works; hold and save U.S. 
from damages; pay 25 percent of the total project costs; 
provide cash contribution not less than 5 percent of total 
project costs; assume responsibility for all costs in excess 
of the $500,000 Federal limitation. 
Operations and results during fiscal year. New Work: 
The construction contract was awarded on December 6, 
1988 in the amount of $394,240 and is 99 percent 
complete. 
28. JENNINGS RANDOLPH LAKE, 
MD & WV 
Location. Project is located on the North Branch 
Potomac River on the state line between Garrett County, 
MD, and Mineral County, WV. The damsite is located 
approximately 7.9 miles upstream from the confluence 
with Savage River at Bloomington, MD. It is also about 
5 air miles southwest of the tritowns of Luke and 
Westernport, MD, and Piedmont, WV. (See Geological 
Survey quadrangle sheets, "Kitzmiller" and "Westernport," 
MD.) 
Existing project. The improvement consists of a rolled 
earth and rock fill dam with an impervious core and an 
800-foot long dike on the left bank. Top of dam is 296 
feet above streambed with a total length of 2,130 feet. 
When filled to spillway crest, the reservoir will extend 
about 6.6 miles upstream and inundate 965 acres. Flood 
control storage of 36,200 acre-feet is provided. Storage 
available for low flow augmentation for water supply and 
water quality improvement is 92,000 acre-feet. The reservoir 
controls a drainage area of 263 square miles. Recreation 
facilities are provided for picnicking, camping and 
boating. Estimated cost (October 1986) of new work is 
$176,270,300 of which $58,521,700 is required non- 
Federal reimbursement. 
Local cooperation. See page 4-15 of the 1977 Annual 
Report for requirements. A water supply contract 
between the Federal Government and the Washington 
Suburban Sanitary Commission in concert with the Fairfax 
County Water Authority, VA, and the District of 
Columbia has been executed for repayment of all water 
supply costs. The first of 50 annual payments began in 
July 1981. Federally approved water quality standards 
put into effect by Maryland, Virginia, West Virginia, and 
the District of Columbia are considered satisfactory 
assurances of intent to control pollution. Satisfactory 
assurances have been received from Maryland, West 
Virginia, and Virginia that they will protect downstream 
channels from encroachment that would adversely affect 
operation of the project. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
29. LACKAWANNA RIVER BASIN, PA 
Flood Control Act of 1962 authorized construction of 
Aylesworth Creek Lake, Fall Brook Lake, and local protection 
works on Lackawanna River at Scranton, PA, 
substantially as recommended by the Chief of Engineers 
(S. Doc. 141, 87th Cong., 2d Sess.). The Basin includes 
an area of 346 square miles in northeastern Pennsylvania. 
29A. AYLESWORTH CREEK LAKE, PA 
Location. Project is located in Lackawanna County on 
Aylesworth Creek about one mile above its confluence 
with the Lackawanna River, near the community of East 
Jermyn, PA. 
Existing project. Provides for an earthfill dam with a 
maximum height of 90 feet above streambed and a top 
length of 1,200 feet. The spillway located adjacent to the 
left abutment is an open cut channel 80 feet wide with 
a concrete sill. The outlet works consist of a 3-foot 
diameter uncontrolled conduit. Project controls a 
drainage area of 6.2 square miles and provides flood control 
storage of 1,700 acre-feet equivalent to 5.1 inches of 
runoff from the drainage areas. The lake will extend 
about 4,600 feet and inundate 87 acres when filled to spillway 
crest. Recreation facilities constructed by local 
interest include a bathing beach, bathhouse, and picnic 
area. Federal cost of new work was $2,268,200 of which 
$2,153,559 was for construction and $114,641 for lands 
and damages. In addition $52,200 Federal and $52,200 
non-Federal funds were expended for construction of 
bathhouse facilities under the recreation facilities for 
completed projects program. 
Local cooperation. None required. The Aylesworth 
Creek Reservoir Park Authority, representing the 
Boroughs of Archbald and Jermyn, operate and maintain 
limited day use facilities including a small beach. In 
September 1978 a cost-sharing agreement for construction 
of bathhouse facilities was signed. The cost for the 
facilities which were completed in July 1979 was $104,400 
of which $52,200 was Federal and $52,200 was non- 
Federal. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
4-12

BALTIMORE, MD DISTRICT 
30. RAYSTOWN LAKE, RAYSTOWN 
BRANCH, JUNIATA RIVER, PA 
Location. Dam site is on Raystown Branch, about 5.5 
miles upstream from its confluence with Juniata River. 
Project is about 10 miles south of Huntingdon, PA. (See 
Geological Survey Quadrangle sheets, Huntingdon, Mt. 
Union, Broad Top and Everett, PA.) 
Existing project. The rock and earthfill dam rises 225 
feet above streambed with a gated concrete spillway and 
auxiliary spillway in the right abutment. The reservoir 
has a storage capacity of 762,000 acre-feet, of which 
248,000 acre-feet are for flood control, 476,000 acre-feet 
for recreation and water quality control, and the balance 
for sediment reserve. At full flood control pool elevation, 
the reservoir would inundate 10,800 acres and extend 34 
miles upstream. Recreation facilities are provided for 
boating, fishing, camping, swimming, hunting, hiking, 
and picnicking. Federal cost for new work was $77,408,700 
of which $46,120,931 was for construction and 
$31,287,769 was for lands and damages including 
relocations. Construction of a private hydroelectric plant 
at Raystown Lake was completed May 1988. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
31. SOUTHERN NEW YORK FLOOD 
CONTROL PROJECTS 
Authorized plan provides for construction of reservoirs 
and related flood control works for protection of towns 
in New York and Pennsylvania. The improvements are 
located in the upper watershed of the Susquehanna River 
to and including the Chemung River. 
31A. ADDISON, NY 
Location. At confluence of Tuscaroroa Creek and 
Canisteo River in the City of Addison, NY. (See Geological 
Survey map for Addison, NY.) 
Existing project. Provides for construction of about 
3,100 feet of earth levee and 700 feet of concrete flood 
wall on the right bank of the Canisteo River, extending 
from high ground on Steuben Street near the Baltimore 
& Ohio Railroad to the mouth of Tuscarora Creek; 
removal of existing dam, mill, and raceway from the 
channel; construction of about 2,200 feet of earth levee 
on the left bank of Tuscarora Creek, extending from 
Tuscarora Street to Canisteo River; construction of 4,600 
feet of earth levee on the right bank of Tuscarora Creek, 
extending from high ground at the southwest edge of the 
village to high ground at the southeast edge of the 
village; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
31B. ALMOND LAKE, NY 
Location. Dam is located two miles upstream from 
Hornell, NY, on Canacadea Creek, a tributary of the 
Canisteo River. (See Geological Survey map for Hornell, 
NY.) 
Existing project. The dam is an earthfill structure, 
1,260 feet long rising 90 feet above the streambed, with 
a concrete spillway and a gated outlet conduit in the left 
abutment. The outlet works consist of three 5-foot by 
10-foot service gates and three emergency gates of the 
same size. The reservoir has a storage capacity of 14,640 
acre-feet at spillway crest. The project controls a draining 
area of 56 square miles, 36 percent of the watershed 
of the Canisteo River upstream from Hornell, NY. Recreation 
facilities include a boat-launching ramp and dock, 
bathing beach, picnic area, and tent and trailer camping 
area. 
Local cooperation. None required. Local interests have 
developed recreational facilities at the lake in conjunction 
with the Federal Government. These facilities are 
operated and maintained by the Steuben County Board 
of Supervisors. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
31C. ARKPORT DAM, NY 
Location. Dam is located five miles upstream from 
Hornell, NY, on the Canisteo River, a tributary of the 
Chemung River which flows into the Susquehanna River. 
(See Geological Survey map for Arkport, NY.) 
Existing project. The dam is an earthfill structure, 
1,200 feet long, exclusive of spillway, rises 113 feet above 
the streambed, with a concrete spillway and an ungated 
outlet in the right abutment. The outlet structure consists 
of an 8-foot diameter reinforced concrete lined 
conduit, 660 feet long. A cast iron nozzle is placed in the 
lower end of the conduit, reducing the outlet size to 4 feet 
4 inches. The reservoir has a storage capacity of 7,950 
acre-feet at spillway crest. The project controls a 
drainage area of 31 square miles, 20 percent of the 
watershed of the Canisteo River upstream from Hornell. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
4-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
31D. AVOCA, NY 
Location. On the Cohocton River at the Village of 
Avoca, NY, about 30 miles upstream from the confluence 
of the Cohocton and Chemung Rivers. (See Geological 
Survey map for Avoca, NY.) 
Existing project. Provides for improvement and realignment 
of about 8,300 feet of Cohocton River channel, 
extending from above the Erie Railroad to below the 
junction of Main Street and U.S. Highway 15; construction 
of about 8,500 feet of earth levee on left bank of the 
Cohocton River, extending from high ground above 
Alexander Avenue to about 1,300 feet below the junction 
of Main Street and U.S. Highway 15; and 4,500 feet 
of earth levee on the right bank of Salmon Creek, extending 
from high ground above Alexander Avenue to the 
Erie Railroad; a new highway bridge for U.S. Highway 
15 over Cohocton River, raising of the Erie Railroad 
bridge 4 feet; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
31E. BINGHAMTON, NY 
Location. At the confluence of the Chenango and 
Susquehanna Rivers in the City of Binghamton, NY. (See 
Geological Survey map for Binghamton, NY.) 
Existing project. Provides for construction of earth 
levees, concrete flood walls, and appurtenant drainage 
structures, consisting of about 850 feet of channel 
excavation and about 1,375 feet of earth levee along 
Phelps Creek, Town of Port Dickinson; new concrete wall 
on the right bank of the Chenango River, extending 
downstream from high ground near the city limits to an 
existing flood wall below DeForest Street, a distance of 
about 520 feet; about 150 feet of concrete wall just below 
Cutler Dam; about 180 feet of concrete wall at the pumphouse 
near McDonald Avenue; raising existing earth 
levees on the right bank of Chenango River, extending 
from Cutler Dam downstream for about 1,220 feet; about 
2,915 feet of earth levee on the left bank of Chenango 
River north of the city limits in the Village of Port 
Dickinson, extending from Church Street to high ground 
just north of the city line; about 3,900 feet of earth levee 
on the left bank of Chenango River, extending from 
DeForest Street to Cutler Dam; new concrete flood walls 
and riverbank revetment for about 5,570 feet extending 
on the left bank of Chenango River from Cutler Dam to 
the junction with the Susquehanna River; about 540 
feet of new concrete flood wall and raising about 1,085 
feet of concrete flood wall on the right bank of the 
Susquehanna River, extending from the Delaware, Lackawanna 
& Western Railroad downstream to Tompkins 
Street Bridge; about 1,940 feet of earth levee; about 1,940 
feet of concrete flood wall and capping about 125 feet of 
concrete flood wall, on the right bank of the Susquehanna 
River from Stuyvesent Street to mouth of Chenango 
River; about 8,380 feet of earth levee, about 2,180 feet 
of new concrete flood wall and raising about 125 feet of 
existing flood wall on the left bank of the Susquehanna 
River extending from Pierce Creek to high ground at 
State Highway 17; a debris dam and flume between 
Corbett and Hotchkiss Streets and a concrete pressure 
conduit, 1,060 feet long to carry flow of Park Creek from 
Vestal Avenue to the Susquehanna River; about 665 feet 
of levee extending from the Erie Railroad to high ground 
along the right bank of Chamberlain Creek near the 
mouth; closure structures at Erie Railroad and at Court 
Street; a weir, a drop structure, and about 1,800 feet of 
earth levee, about 2,235 feet of channel excavation, about 
645 feet of channel paving and raising, about 470 feet 
of existing concrete flood wall, and about 200 feet of new 
concrete flood wall for improvement of Pierce Creek from 
its mouth to about 1,000 feet above Conklin Avenue; and 
appurtenant drainage structures. Improvement, supplemented 
by authorized flood control dams above the 
area, will provide protection for the City of Binghamton 
against a flood discharge about 20 percent greater than 
the maximum flood of record, which occurred in July 
1935 on the Chenango River and in March 1936 on the 
Susquehanna River. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New Work: 
A construction contract to correct the underseepage at 
the First Ward Area, was awarded in January 1988 and 
work was completed in January 1989. Maintenance: Normal 
operation and maintenance of the project continued. 
31F. CANISTEO, NY 
Location. On Purdy and Bennetts Creeks in the Town 
of Canisteo, NY, situated along the south side of the 
Canisteo River, at the confluence of Bennetts Creek and 
the Canisteo River. (See Geological Survey map for 
Canisteo, NY.) 
Existing project. Provides for construction of about 
8,000 feet of earth levees on the right bank of the 
Canisteo River, extending from high ground 1,570 feet 
west of State Highway Route 21 above the Town to a 
point at the intersection of Ordway Lane and East Main 
Street; about 7,400 feet of earth levee on the left bank 
of Purdy and Bennetts Creeks, extending from the Main 
Street Bridge to high ground above Greenwood Street; 
1,000 feet of earth levee on the right bank of Bennetts 
Creek extending upstream from the Main Street Bridge; 
a concrete check dam with wing levees from Greenwood 
Street; a new highway bridge at Greenwood Street; 
alterations to existing timber check dams in Bennetts 
Creek; channel excavation in Bennetts and Purdy Creeks; 
and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
4-14

BALTIMORE, MD DISTRICT 
31G. CORNING, NY 
Location. On the Chemung River in the City of Corning, 
NY, about 44 miles upstream from the confluence 
of Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Corning, NY.) 
Existing project. Flood protection for this community 
was originally authorized by the Flood Control Act of 
1936. Plan of improvement provides for construction of 
a pumping station, earth levees, and concrete flood walls, 
consisting of: about 4,300 feet of earth levee, enlargement 
of about 8,610 feet of existing earth levee and 
about 3,100 feet of concrete flood wall on the right bank 
of the Chemung River, extending from the Erie Railroad 
Bridge to high ground at Park Avenue below the City; 
about 200 feet of concrete flood walls; about 2,500 feet 
of earth levees and enlargement of about 11,500 feet of 
existing earth levee on the left bank of the Chemung and 
Cohocton Rivers, extending from the Erie Railroad 
Bridge over Cohocton River to the mouth of Post Creek; 
about 2,500 feet of earth levee and enlargement of about 
4,700 feet of existing earth levee on the right bank of Post 
Creek from its mouth to Watkins Street; realignment of 
about 3,000 feet of channel, about 8,800 feet of earth 
levee, about 3,000 feet of channel excavation, a pressure 
conduit about 400 feet long, a drop structure and a weir 
for improvement of Cutler Creek, extending from its 
mouth to high ground at Deckertown Road and Hornby 
Road; and appurtenant drainage structures. Flood protection 
on Monkey Run was authorized by the Flood 
Control Act of 1950. Plan of improvement provides for 
construction of 2,010 feet of open flume, 2,320 feet of 
pressure conduit storm sewers, and appurtenant facilities 
between the existing improved channel above Sixth 
Street and the Chemung River at a point immediately 
east of Pine Street East. Modified improvement will provide 
protection for the City of Corning against a flood 
discharge in Chemung River approximately equal to the 
maximum flood of record, which occurred in May 1945, 
and on tributary streams against floods of greater 
magnitude than known to date. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operaton and maintenance of the project 
continued. 
31H. EAST SIDNEY LAKE, NY 
Location. Dam is located near East Sidney, NY, on the 
Ouleout Creek, about five miles above the confluence of 
the creek with the Susquehanna River. (See Geological 
Survey map for Franklin, NY.) 
Existing project. The dam is an earthfill and concrete 
structure, 2,010 feet long, including spillway, rises 130 
feet above the streambed and consists of a concrete 
gravity-type section with a compacted earth-dike section 
at the right abutment. The outlet works consist of five 
rectangular conduits each 3.5 feet by 5.85 feet and 105 
feet long. The reservoir has a storage capacity of 33,500 
acre-feet at spillway crest. The project controls a 
drainage area of 102 square miles which is 93 percent of 
the Ouleout Creek drainage area, and 5 percent of the 
watershed of the Susquehanna River upstream from 
Binghamton, NY, exclusive of the separately controlled 
Chenango River. Recreation facilities include a bathing 
beach, picnic and camping areas, and boat-launching and 
docking facilities. 
Local cooperation. None required. The Town of Sidney, 
NY, cooperated in the development of recreation facilities 
and operates and maintains all the facilities with the 
exception of the recreational pool, which is the responsibility 
of the Federal Government. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. A contract was awarded on April 12, 
1989 in the amount of $950,500 to stabilize the weir, the 
estimated completion date is February 28, 1990. 
31I. ELMIRA, NY 
Location. On the Chemung River in the City of Elmira, 
NY, about 27 miles upstream from the confluence of the 
Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Elmira, NY.) 
Existing project. Provides for about 17,700 feet of 
earth levees, and about 4,100 feet of concrete flood wall 
on the right bank of the Chemung River, extending from 
South Hoffman Street to a point below the city near the 
upper end of Big Island; about 12,100 feet of earth levee 
and about 6,300 feet of concrete wall on the left bank of 
the Chemung River extending from Durland Avenue to 
the Delaware, Lackawanna & Western Railroad at the 
mouth of Newton Creek; about 10,000 feet of earth levee 
on right bank of Newton Creek, extending from about 
the intersection of Delaware, Lackawanna & Western 
Railroad and East Church Street to high ground near 
intersection of Sullivan and Warren Streets; about 4,300 
feet of earth levee on the right bank of Divan Creek; 
about 2,000 feet of concrete conduit enclosing Hoffman 
Brook from West Second Street to the Chemung River; 
clearing islands and riverbanks of trees and brush for 
about 3.5 miles in the Chemung River; about 14,300 feet 
of earth levee on the left bank of Seely Creek, extending 
from the Erie Railroad to high ground approximately 
1,000 feet northwest of the intersection of South Broadway 
and Pennsylvania Avenue; a pumping plant for disposal 
of interior drainage; an interceptor sewer about 
6,000 feet long varying in size from 48 to 96 inches in 
diameter; and appurtenant structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
4-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
31J. HORNELL, NY 
Location. On the Canisteo River in the City of Hornell, 
NY, about 42 miles upstream from the confluence of the 
Canisteo and Tioga Rivers. (See Geological Survey map 
for Canisteo, NY.) 
Existing project. Provides for channel realignment and 
earth levees, concrete flood walls, and check dams consisting 
of: realignment of about 4,600 feet of the 
Canisteo River channel, and about 5,800 feet of earth 
levee on its right bank, extending from Seneca Street 
upstream to the junction of the Pittsburgh, Shawmut & 
Northern Railroad and the Erie Railroad; about 4,500 feet 
of earth levee, extending on both sides of Seneca Street 
from the Canisteo River to Wrightman Avenue and the 
junction of Cleveland Avenue and Bethesda Drive; about 
7,200 feet of earth levee, about 2,500 feet of concrete flood 
wall, and raising about 1,500 feet of existing concrete 
flood wall, on the right bank of the Canisteo River, and 
about 12,000 feet of channel improvement, extending 
from Seneca Street to the Erie Railroad; about 2,500 feet 
of earth levee, about 2,100 feet of concrete flood wall on 
the left bank of the Canisteo River extending from a point 
opposite Walnut Street to the Erie Railroad; a ring-earth 
levee about 2,800 feet long around the sewage-disposal 
plant on the left bank of the Canisteo River; about 4,500 
feet of realignment and improvement of the Canisteo 
River Channel with about 4,500 feet of earth levee on its 
right bank extending from Cedar Street downstream to 
about 1,400 feet above East Avenue; about 2,400 feet of 
channel paving, 1,400 feet of earth levee, raising about 
1,900 feet of concrete flood wall, and construction of one 
check dam on Canacadea Creek; about 1,600 feet of 
channel paving and construction of three check dams on 
Chauncey Run with about 300 feet of new wall and about 
300 feet of capping; a weir, a check dam, 3,030 feet of 
channel paving, 4,800 feet of flood walls and levees, and 
related work on existing walls, on Crosby Creek; removal 
of 6 bridges, erection of 4 bridges, miscellaneous bridge 
structures, and 3 drop structures; and appurtenant 
drainage structures and small stream control works. 
Improvement, supplemented by Arkport and Almond 
Reservoirs above the area, provides protection for the 
City of Hornell against a flood discharge approximately 
double the maximum flood of record, which occurred in 
July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. An overall engineering analysis of the 
condition of the project continued. 
31K. LISLE, NY 
Location. On the Tioughnioga River in the Village of 
Lisle, NY, about 12 miles upstream from the confluence 
of the Tioughnioga and Chenango Rivers. (See Geological 
Survey map for Lisle, NY.) 
Existing project. Provides for channel realignment and 
construction of earth levees and concrete flood walls, consisting 
of: relocation of about 3,000 feet of Dudley Creek 
Channel, extending from 1,200 feet west of the intersection 
of Cortland and Main Streets to the confluence with 
Tioughnioga River, realignment of some 5,700 feet of 
Tioughnioga River Channel east of the Village; about 
4,150 feet of earth levee and 970 feet of concrete wall on 
the right bank of Dudley Creek and Tioughnioga River; 
realignment of some 5,700 feet of Tioughnioga Street to 
the railroad crossing on River Street; raising about 1,860 
feet of the Delaware, Lackawanna & Western single track 
railroad over the levee; relocation of about 1,600 feet of 
Cortland Street; a new bridge over relocated Dudley 
Creek; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
31L. OXFORD, NY 
Location. On the Chenango River in the Village of 
Oxford, NY, about 40 miles upstream from the confluence 
of the Chenango and Susquehanna Rivers. (See 
Geological Survey map for Oxford, NY.) 
Existing project. Provides for earth levees and clearing 
of Chenango River Channel, consisting of about 2,100 
feet of earth levees on the left bank of the Chenango 
River, extending from high ground near Cemetery Drive 
and running mostly along the railroad to high ground 
near Main Street; removal of dam and island below Main 
Street; raising the Delaware, Lackawanna & Western 
Railroad over the levee; and appurtenant closure and 
drainage structures. Improvement provides protection 
for the Village of Oxford on the left bank against a flood 
discharge substantially larger than the maximum flood 
of record, which occurred in July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
31M. WHITNEY POINT LAKE, NY 
Location. Dam is located near Whitney Point, NY, on 
the Otselic River about 0.7 mile upstream from its confluence 
with Tioughnioga River. (See Geological Survey 
map for Whitney Point and Willet, NY.) 
Existing project. The dam is an earthfill structure, 
4,900 feet long, exclusive of a spillway, rises 95 feet above 
the streambed, with a concrete spillway and gated outlet 
in the left abutment. The outlet works consist of three 
5-foot by 10-foot gates and one emergency gate of the 
same size. The reservoir has a storage capacity of 86,440 
4-16

BALTIMORE, MD DISTRICT 
acre-feet at spillway crest. The project controls a 
drainage area of 255 square miles, the entire watershed 
of Otselic River, or 16 percent of the Chenango River 
watershed upstream from Binghamton, NY. Recreation 
facilities, constructed in cooperation with local interests, 
provide for swimming, picnicking, camping, boating, fishing, 
and hunting. 
Local cooperation. None required. Local interests operate 
and maintain all of the recreation facilities. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. A contract was awarded on April 13, 
1989 in the amount of $328,820 to stabilize the weir, the 
estimated completion date is February 28, 1990. 
31N. WHITNEY POINT VILLAGE, NY 
Location. On the Tioughnioga River at the confluence 
of the Tioughnioga and Otselic Rivers, tributaries of the 
Susquehanna River. (See Geological Survey map for 
Whitney Point, NY.) 
Existing project. Provides for channel realignment and 
earth levees, consisting of realignment of about 1,800 feet 
of Tioughnioga River Channel, above the confluence with 
Otselic River; about 7,100 feet of earth levee along the 
right bank of the Tioughnioga River, extending from high 
ground on Main Street above the village to Collins Street 
just below the Village; and appurtenant drainage 
structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
32. SPRING BROOK CREEK, 
PITTSTON TOWNSHIP, PA 
Location. The project is located in the Township of 
Pittston along the banks of Spring Brook Creek adjacent 
to PA state route 502. Pittston Township is located in 
northeastern Luzerne County, PA approximately 1 mile 
southeast of Scranton, PA. (See USGS quad sheets "Pittston, 
PA" and "Avoca, PA".) 
Existing project. On January 26, 1989, the Chief of Engineers, 
under the authority provided by Section 14 of 
the 1946 Flood Control Act, as amended, authorized construction 
of streambank protection. The work consists 
of the excavation and backfilling of the existing streambank 
and placement of approximately 870 feet of stone 
riprap. Additional riprap is being placed as a betterment 
that was proposed by the sponsor. The estimated project 
implementation cost is $460,000, of which the sponsor 
will be paying $115,000 as well as providing $40,000 for 
the betterment. 
Local cooperation. The July 24, 1989 Local Cooperation 
Agreement between DOA and Pittston Township, 
in brief, requires the local sponsor to: Provide all lands, 
easements and rights-of-way; provide modifications and 
relocations of buildings, roads, bridges, and related utilities; 
operate and maintain completed works; hold and 
save U.S. from damages; pay 25 percent of the total 
project costs; provide cash contribution not less than 5 
percent of total project costs; assume responsibility for 
all costs in excess of the $500,000 Federal limitation. 
Operations and results during fiscal year. New Work: 
The construction contract was awarded on September 30, 
1989 in the amount of $325,000 and is scheduled for completion 
in Spring 1990. 
33. STILLWATER LAKE 
LACKAWANNA RIVER, PA 
Location. Dam is on the Lackawanna River, 39 miles 
from the mouth of the stream and about 4 miles upstream 
from Forest City, Susquehanna County, PA (See Geological 
Survey Quadrangle sheet, Honesdale, PA.) 
Existing project. Dam is earthfill type, rising 77 feet 
above the streambed, with a controlled outlet conduit and 
side channel spillway in the left abutment. Reservoir 
capacity is 12,000 acre-feet, of which 11,600 acre-feet is 
flood control storage and the remainder utilized to maintain 
the existing water supply reservoir for Forest City, 
PA, at this site. Reservoir area is 422 acres,and the pool 
extends about 2.1 miles upstream. Reservoir controls 52 
percent of the watershed above Carbondale, 26 percent 
above Olyphant, and 17 percent above Scranton. Federal 
cost of new work, completed in 1965, was $5,725,700 of 
which $4,500,500 was for construction and $1,225,200 
was for lands and damages. 
Local cooperation. None required. Section 2, Flood Control 
Act of June 28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
34. SUSQUEHANNA RIVER FLOOD 
CONTROL PROJECTS, NY AND PA 
Plan of improvement authorized by the 1958 Flood 
Control Act provides for construction of Cowanesque 
Lake, PA, Tioga-Hammond Lakes, PA, local protection 
works at Elkland, PA, and Nichols, NY, and channel 
improvements at Cortland, NY. This project plan supplemented 
the comprehensive flood control program for 
Southern New York and Northern Pennsylvania which 
4-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
included the Southern New York flood control project 
and Stillwater, Genegantslet, and South Plymouth 
Reservoirs. 
34A. COWANESQUE LAKE, PA 
Location. Dam is on the Cowanesque River about 2.2 
miles above its confluence with Tioga River at Lawrenceville, 
PA. (See Geological Survey map for Tioga, PA.) 
Existing project. The project constructed under the 
Flood Control Act of 1958 provides for an earthfill dam 
3,100 feet long and rising 151 feet above the streambed, 
an uncontrolled spillway in the right abutment, a gated 
conduit in the Valley floor, and flood control storage is 
82,000 acre-feet. Relocation of the Town of Nelson to a 
new townsite was authorized by Section 121 of the Water 
Resources Development Act of 1976. The Federal cost 
of this new work was $106,030,700 of which $61,743,600 
was for construction and $44,287,100 was for lands and 
damages and relocations (which includes $5,755,000 for 
relocation of the Town of Nelson). Within the discretionary 
authority of the Chief of Engineers the project was 
modified in March 1983 in accordance with the Water 
Supply Act of 1958, as amended, and the Flood Control 
Act of 1944, as amended. The modification provides for 
reallocating 25,600 acre-feet of present flood control 
storage for water supply storage by raising the permanent 
pool from elevation 1,045 to 1,080 mean sea level. 
Other features include modifying the existing intake 
tower and two access ramps, stabilizing the reservoir 
slope near the relocated Town of Nelson, replacing 
existing day-use recreation facilities, and expanding both 
day-and overnight-use recreation facilities to accommodate 
an expected increase in annual visitation due to the 
larger pool. Estimated cost (October 1988) of the modification 
is $54,314,000 of which $1,110,000 is Federal (for 
expanded recreation facilities) and $53,204,000 is non- 
Federal (which includes $39,414,000 for reimbursement 
of the cost of existing flood control storage reallocated 
to water supply storage, $12,680,000 cash contribution 
for the water supply modification, and $1,110,000 cash 
contribution for expanded recreation facilities). 
Local cooperation. The Water Resources Development 
Act of 1976, which authorized relocation of the Town of 
Nelson, provides that before the Secretary of the Army 
acquires any real estate property for the new townsite, 
appropriate non-Federal interests shall furnish binding 
contractual commitments that all lots in the new townsite 
will be either occupied when available, replacements 
for open space and vacant lots in the existing town, or 
will be purchased by non-Federal interests at the fair 
market value. The required contractual agreement for 
local cooperation was executed with Nelson Township on 
August 25, 1977. The March 1983 project modification 
(discussed above) requires non-Federal interests repay 
100 percent of the investment cost of project modifications 
allocated to water supply, to terrestial wildlife 
habitat mitigation, and to in-kind replacement recreation, 
plus the allocated share of the project's original cost 
(escalated to current price levels). Additionally, they are 
required to pay annual costs of operation, maintenance, 
and major replacements allocated to water supply and 
to provide 50 percent of the cost of expanded recreation 
facilities, as well as, all operation, maintenance, and 
replacement costs for the expanded facilities. Water 
supply and recreation contracts were executed by the 
Assistant Secretary of the Army (Civil Works) and the 
Susquehanna River Basin Commission on June 30, 1986. 
Operation and results during fiscal year. New Work: 
Contract work was completed on the slope modification, 
intake tower and access ramp modification and the cultural 
and historical field work. Work progressed on recreation, 
fish and wildlife and reservoir clearing. 
Maintenance: Normal operation and maintenance of the 
project continued. 
34B. TIOGA-HAMMOND LAKES, PA 
Location. The dams are located in Tioga County, PA, 
upstream from the confluence of the Tioga River and 
Crooked Creek. Tioga Dam is located on the Tioga River 
and Hammond Dam on Crooked Creek, approximately 
opposite the Tioga damsite, about 3.3 miles above its 
mouth and less than one mile from the Village of 
Brooklyn. (See Geological Survey map for Tioga, PA.) 
Existing project. Tioga Dam is 2,600 feet long, rising 
140 feet above the streambed, with a controlled outlet 
conduit. Hammond Dam is 5,900 feet long, and has a 
maximum height of 121.5 feet above the streambed, with 
a concrete spillway. Both dams are of earth and rockfill 
construction. The Tioga-Hammond Lakes project controls 
a total drainage area of 402 square miles, with Tioga 
Dam controlling 280 square miles of the Tioga River 
Basin and Hammond Dam controlling 122 square miles 
of the Crooked Creek Basin. Recreation facilities are 
provided for swimming, camping, picnicking, boating, 
and fishing. Estimated Federal cost (October 1988) of 
new work is $193,120,000 of which $125,029,000 is for 
completed construction, $60,591,000 is for lands and 
damages and relocations and $7,500,000 is for construction 
of the Mill Creek recreation facilities. 
Local cooperation. None required on the completed 
portion of the project; however, construction of the Mill 
Creek Area recreation facilities relies on local interests 
providing specialized facilities including buildings, 
lodges, demonstration centers, and non-water oriented 
equipment and accepting full responsibility for operation 
and malntenance of the entire recreation area. 
Operations and results during fiscal year. New Work: 
Planning for the joint development of the Mill Creek 
Recreation Area continued by the Baltimore District and 
Mansfield University including preparation of plans and 
specifications for construction of the Federal project. The 
design of the Federal project is 95% complete. Progress 
was slowed down due to non-Federal sponsor lack of 
funds. Local sponsor fund-raising has been less than successful. 
Project will be terminated if local sponsor cannot 
raise non-Federal share. Maintenance: Normal 
operation and maintenance of the project continued. 
4-18

BALTIMORE, MD DISTRICT 
35. TUNKHANNOCK CREEK, 
TUNKHANNOCK, PA 
Location. The project is situated on Tunkhannock 
Creek adjacent to Saint Peter's Episcopal Church located 
in the town of Tunkhannock, Wyoming County, PA. The 
town of Tunkhannock is located approximately 15 miles 
northwest of Scranton, PA. (See USGS quad. sheet titled 
Tunkhannock, PA.) 
Existing project. On September 22, 1988, the Chief of 
Engineers, under the authority provided by Section 14 
of the 1946 Flood Control Act, as amended, authorized 
the construction of streambank protection. The work consists 
of the removal of a shoal in the creek and the placement 
of fill material capped with stone riprap along 
approximately 250 feet of the streambank. The estimated 
project implementation cost is $223,400 of which $55,000 
will be funded by the Local sponsor. 
Local cooperation. The November 25, 1988 Local 
Cooperation Agreement between DOA and Tunkhannock 
Township, in brief, requires the local sponsor to: Provide 
all lands, easements and rights-of-way; provide modifications 
and relocations of buildings, roads, bridges, and 
related utilities; operate and maintain completed works; 
hold and save U.S. from damages; pay 25 percent of the 
total project costs; provide cash contribution not less 
than 5 percent of total project costs; assume responsibility 
for all costs in excess of the $500,000 Federal limitation. 
Operations and results during fiscal year. New Work: 
The construction contract was awarded on September 30, 
1989 in the amount of $160,000 and is scheduled for completion 
in Spring 1990. 
36. WEST BRANCH OF 
SUSQUEHANNA RIVER, PA 
A system of three flood control reservoirs, in the headwaters 
of the West Branch Susquehanna River, PA, are 
known as Curwensville, Alvin R. Bush (formerly known 
as Kettle Creek) and Foster Joseph Sayers (formerly 
known as Blanchard) on the West Branch about 2.5 miles 
upstream from Curwensville, PA; on Kettle Creek 8.4 
miles above the mouth and 17 miles upstream from 
Renovo, PA; and on Bald Eagle Creek about one mile upstream 
from Blanchard, PA, respectively. 
In accordance with the terms of local cooperation, the 
Commonwealth of Pennsylvania furnished assurances 
that it will coordinate operation of George B. Stevenson 
Reservoir (formerly known as First Fork Reservoir) with 
operation of Curwensville, Alvin R. Bush, and Foster 
Joseph Sayers Reservoirs to secure optimum flood 
control benefits from system operation. George B. 
Stevenson Reservoir on the First Fork Sinnemahoning 
Creek in Cameron and Potter Counties, PA, was constructed 
by the Commonwealth of Pennsylvania at a first 
cost of $12,240,000 and an estimated $30,000 annually 
for operation and maintenance. 
36A. ALVIN R. BUSH DAM, PA 
Location. Alvin R. Bush Dam (formerly Kettle Creek 
Dam) is located on Kettle Creek about 8.4 miles above 
the mouth and 15 miles upstream from Renovo, PA. (See 
Geological Survey map for Keating, PA.) 
Existing project. Dam is an earthfill structure,about 
1,350 feet long, rises 165 feet above the streambed, with 
an uncontrolled spillway located in rock adjacent to the 
right abutment, and has a horseshoe-shaped outlet tunnel 
with 3 service gates. The reservoir has a storage capacity 
of 75,000 acre-feet at spillway crest. The project controls 
a drainage area of 226 square miles or about 92 percent 
of the Kettle Creek watershed. Recreation facilities are 
provided for camping, fishing, boating, picnicking, 
hiking, winter sports, hunting, and swimming by the 
State of Pennsylvania at Kettle Creek State Park. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
36B. CURWENSVILLE LAKE, PA 
Location. Dam is on the West Branch of the Susquehanna 
River approximately 2.5 miles upstream from 
Curwensville, Clearfield County, PA. (See Geological 
Survey map for Curwensville, PA.) 
Existing project. Dam is an earthfill structure, about 
1,850 feet long, rises 131 feet above the streambed, and 
has an open-cut concrete sill 1,750 feet from the left 
abutment. The outlet works, located in the left abutment, 
consist of a 15-foot diameter circular outlet conduit with 
3 slide control gates 5.5 feet wide and 12 feet high. The 
reservoir has a storage capacity of 124,200 acre-feet at 
spillway crest. The project controls a drainage area of 
365 square miles, or about 98 percent of the West Branch 
Susquehanna River at Curwensville and about 75 percent 
at Clearfield. Clearfield County provides recreation including 
boating, fishing, picnicking, and swimming. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
36C. FOSTER JOSEPH SAYERS DAM, PA 
Location. Dam is located on Bald Eagle Creek in Centre 
County, PA, about one mile upstream from Blanchard 
and about 14 miles above the confluence of Bald Eagle 
Creek with the West Branch Susquehanna River at Lock 
Haven, PA. (See Geological Survey map for Howard, PA.) 
Existing project. Dam is an earthfill structure, about 
6,835 feet long, rises 100 feet above the streambed, and 
has an open-cut concrete chute and uncontrolled concrete 
4-19

REPORT OF THE SECRETARY OFTHE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
weir 600 feet wide located in rock in a saddle adjacent 
to the left abutment. The outlet works, located in the left 
abutment, consist of a 15-foot diameter circular outlet 
conduit with two hydraulically-operated wheel gates 7 
feet wide and 15 feet high. The reservoir has a storage 
capacity of 99,000 acre-feet at spillway crest. The project 
controls a drainage area of 339 square miles or 88 percent 
of the drainage area above Beech Creek and 43 percent 
of the Bald Eagle Creek drainage area. Recreation 
facilities are provided for boating, camping, fishing, picnicking, 
hunting, swimming, hiking, and winter sports 
by the State of Pennsylvania at Bald Eagle State Park. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
37. YORK, INDIAN ROCK DAM, PA 
Location. On Codorus Creek 10 miles above its confluence 
with the Susquehanna River. Codorus Creek has 
tributary branches in York County in the south and 
central parts of Pennsylvania. (See Geological Survey 
Quadrangle sheets, Pennsylvania-York and Hanover.) 
Existing project. Indian Rock Dam is an earth and 
rockfill dam about 1,000 feet long at the top, rising 83 
feet above the streambed, with a reservoir providing for 
control storage of 28,000 acre-feet. Dam is on the main 
branch of Codorus Creek about 3 miles above York. Outlet 
works are in the right abutment and the uncontrolled 
spillway is on the right bank. Reservoir will control entire 
drainage area of the main branch of Codorus Creek 
and 41 percent of the drainage area above York. Improvements 
in Codorus Creek in the vicinity of and through 
the City of York provide for 22,969 feet of channel extending 
from 300 feet above Richland Avenue to a point downstream 
from the Pennsylvania Railroad crossing known 
as Black Bridge. Improvements, which will increase 
channel capacity to 24,000 cubic feet per second, include 
widening and deepening the channel, bank protection, 
removal of York Roller Mill Dam, and a low water channel 
about 3,900 feet long in the vicinity of York Roller Mill 
Dam. Cost of new work for the completed project was 
$5,061,167, of which $4,566,446 (regular funds) and 
$11,588 (emergency relief funds) were for construction and 
$483,133 (regular funds) was for lands and damages. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the project continued. 
An overall engineering analysis of the condition 
of the Codorus Creek Local Flood Protection continued. 
38. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Projects in New York, Pennsylvania, Maryland, 
District of Columbia, and Virginia were inspected during 
the period by hired labor. See Table 4-I. 
39. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Operations and results during fiscal year. The operation 
of George B. Stevenson Dam, PA, was coordinated 
with the operation of Alvin R. Bush, Curwensville, and 
Foster Joseph Sayers Dams in the West Branch Susquehanna 
River Basin in order to secure optimum flood control 
benefits from the system operation. Costs during the 
period were $38,797. 
Supplemental instructions for the operation of Savage 
River Dam, MD, were provided, during periods of high 
water, to insure maximum protection for downstream 
localities. Costs during the period were $60,257. 
40. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
antecedent legislation). 
Cost for the period was $259,634 for the Disaster Preparedness 
Program. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (pre-authorization). 
Fiscal year costs were $9,712 for Conklin-Kirkwood NY. 
Non-structural study for Conklin-Broome (Ice Jam) NY; 
$88,783 for Gwynns Falls, Baltimore, MD; $7,021 for 
Solomons Creek, Ashley, PA; $26,527 for Sterrick Creek, 
PA; $5,238 for Spring Brook, Trout Creek, PA; $35,826 
for Binghamton (Lourdes Hospital Area), NY; $2,965 for 
Hunting Creek, Thurmont, MD; and $38,569 for Frankstown 
Branch, PA. 
Non-Federal contributed costs for the fiscal year were 
$82,410 for Gwynns Falls, MD. 
Water Supply 
41. WASHINGTON AQUEDUCT 
Location. The diversion dam and raw water supply intakes 
at Great Falls, the two collecting conduits, part of 
Dalecarlia receiving reservoir, the booster pumping station 
and the Little Falls raw water pumping station are 
located in Maryland. All other structures of the water 
supply system including parts of the raw water collecting 
system, two purification plants, pumping stations, 
storage reservoirs, and transmission mains are in the District 
of Columbia. Federal owned water mains are maintained 
in Virginia and Maryland. 
Existing project. Control of the water supply system 
is vested in Chief of Engineers (See Acts of March 3, 
1859, and March 2, 1867, November 22, 1973 and Sec. 
1800 of Revised Statutes). The project includes: administration; 
operation and maintenance of the collection, 
4-20
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
REPORT OF THE SECRETARY OF THE ARMY

BALTIMORE, MD DISTRICT 
purification, pumping, and transmission facilities; protection 
of the water supply system; engineering; and construction 
of major water system additions and 
improvements. 
Authority to supply water to Arlington County, the 
City of Falls Church, and other jurisdictions in Virginia 
is contained in Public Law 119, 69th Congress, approved 
April 14, 1926; and Public Law 118, 80th Congress, 
June 26, 1947. 
Local cooperation. Requirements are described in full 
on page 4-19 of the Fiscal Year 1981 Annual Report. 
Operations and results during fiscal year. An uninterrupted 
and adequate supply of purified water was 
furnished to the District of Columbia; Arlington County, 
and Falls Church, VA; and to Federal establishments in 
the District of Columbia, Arlington County, VA and 
Montgomery and Prince Georges Counties in Maryland. 
Total consumption for Fiscal Year 1989 was 66,339 
million gallons; the maximum daily consumption was 232 
million gallons and average daily consumption was 181 
million gallons. The average amount furnished Arlington 
County and Falls Church, VA was 41.1 million gallons 
per day. The Corps of Engineers was reimbursed in the 
amount of $5,316,969 for water furnished to the Virginia 
communities by the Washington Aqueduct. 
The treated water delivered to the 1.1 million consumers 
served by the Washington Aqueduct met or surpassed 
all Water Quality standards promulgated by the 
U.S. Environmental Protection Agency under the Safe 
Drinking Water Act (P.I. 93-523.) 
General Investigations 
42. SURVEYS 
Federal costs for the fiscal year were $2,652,060 of 
which $1,295,810 was for flood damage prevention 
studies, $430,503 for shoreline protection studies, 
$563,103 for special studies, $116,987 for special investigations, 
$24,000 for interagency Water Resource development, 
and $221,657 for coordination with other 
agencies and non-Federal interests. 
Non-Federal contributed costs for the fiscal year were 
$49,928 for shoreline protection studies, and $722,408 for 
flood damage prevention studies. 
43. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for flood plain management activities and 
general planning guidance during the period was 
$401,104. Providing assistance and guidance to local 
interests on methods and procedures for preventing and 
reducing flood damages was in progress at end of fiscal 
year. 
44. PRE-CONSTRUCTION ENGINEERING 
AND DESIGN 
Susquehanna Basin at Harrisburg, PA-The authorized 
project provides for an impervious railroad embankment/
floodwall line of protection 3,800 feet long, a pump 
station and floodgates for interior drainage, a dry detention 
dam along Asylum Run (a small tributary of Paxton 
Creek), an enlarged earth and concrete channel for Paxton 
Creek about 4 miles long, and minor recreation and fish 
and wildlife facilities. The General Design Memorandum 
was terminated during the fiscal year due to lack of economic 
justification. Non-structural flood control measures 
are being identified to reduce the effects of future 
flood events. The planning and engineering cost is 
$2,952,000. Total costs during the fiscal year were 
$89,211. 
Lock Haven, PA-The authorized project provides for 
36,600 feet of levee, 1,000 feet of flood wall, five closure 
structures, one pumping station, non-structural flood 
control measures for Woodward Township, and minor 
recreation facilities. Plans and specifications were essentially 
completed for the West Branch Susquehanna River 
levees. The planning and engineering cost is $4,547,000. 
Total costs during the fiscal year were $961,841. 
Wyoming Valley, PA (Levee Raising)-The authorized 
project provides for raising the existing levees and flood 
walls between 3 and 5 feet, modifying closure structures, 
relocating utilities, and providing some new flood walls 
and levees to maintain the system's integrity. The plan 
also includes raising four other local protection projects, 
removing an abandoned railroad bridge, and providing 
non-structural measures to mitigate any significant induced 
damages and the potential of a catastrophic failure 
of an existing project. Preparation of a Phase II General 
Design Memorandum continued during the fiscal year. 
The estimated planning and engineering cost is 
$7,700,000 and costs during the fiscal year were 
$1,651,689. 
Atlantic Coast of Maryland & Assateague Island, 
VA-The authorized project provides for constructing a 
steel sheet pile bulkhead about 1.5 miles, and constructing 
a sand dune about 6.7 miles for hurricane protection. 
Preparation of a General Design Memorandum was essentially 
completed during the fiscal year. The estimated 
planning and engineering cost is $2,640,000 and costs 
during the fiscal year were $905,318. 
Washington, DC & Vicinity-The authorized project 
would provide for raising the grade of a portion of P 
Street, filling an area near the Lincoln Memorial (along 
23rd Street) regrading the area adjacent to 17th Street 
and constructing a removable closure structure across 
17th Street. These measures were authorized to restore 
the design level of protection of the existing project and 
to reduce the need for emergency closure in the event of 
a flood. Preparation of a General Design Memorandum 
continued during the fiscal year and total costs were 
$640,225. Estimated preconstruction planning cost is 
$2,300,000. 
4-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-A COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
1. Baltimore Harbor 
and Channels, 
MD and VA 
2. Baltimore Harbor 
MD Collection 
& Removal of 
Drift 
3. Cambridge 
Harbor, MD 
4. Crisfield Harbor, 
MD 
5. Fishing Bay, MD 
6. Herring Bay & 
Rockhold Creek, 
MD 
7. Herring Creek, 
Tall Timber, MD 
8. Honga River and 
Tar Bay, MD 
9. Little Wicomico 
River, VA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5,904,000 25,579,000 31,700,000 
5,585,736 25,840,645 28,277,257 
7,440,7912 5,992,204' 2,501,5046 
7,440,790 5,992,0276 2,498,018' 
14,100,000 124,134,7121 
17,579,367 124,062,4191 
3,748,4858 85,659,84410 
3,752,0649 85,659,75510 
- 17,674,000 22,186,480 13,178,920 
- 17,198,010 21,171,953 13,769,831 
236,000 
239,574 
217,000 
217,002 
10,000 
10,000 
20,000 
20,000 
503,200 
478,502 
138,000 
137,999 
398,500 
423,195 
79,100 
79,100 
215,359 
210,742 
228,000 
228,000 
176,700 
176,699 
26,870 
5,869 
50,200 
50,200 
48,000 
48,000 
187,400 
187,400 
99,400 
99,403 
224,000 
223,999 
61,000 
61,001 
-7,680 
13,321 
53,000 
52,995 
331,000 
330,999 
4,000 
4,001 
220,359 
218,397 
3,000 
3,000 
- -215,359 
4,617 -215,359 
38,000 
38,000 
138,600 
134,210 
24,555 
28,946 
70,000 
70,000 
45,000 
45,001 
53,039,400 
52,139,794 
4,016,210 
4,016,208 
195,97411 
195,97411 
925,958 
925,958 
19,190 
19,190 
349,15412 
349,15412 
673,521 
673,516 
33,87413 
33,87413 
1,094,592 
1,094,591 
50,591 
50,591 
803,648 
803,648 
1,506,259 
1,504,297 
148,329 
148,329 
10,306 
10,306 
66,11914 
66,11914 
3,106,926 
3,106,926 
81,88516 
81,88516 
1,457,207 
1,457,207 
4-22

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
10. Monroe Bay 
and Creek, VA 
11. Nanticoke River 
(Including 
Northwest Fork 
DE & MD 
12. Ocean City Harbor 
and Inlet and Sinepuxent 
Bay, MD 
13. Pocomoke 
River, MD 
14. Potomac and 
Anacostia Rivers, 
DC, Collection & 
Removal of Drift 
15. Potomac River- 
Aquatic Plant 
Control, MD, 
VA, DC 
16. Potomac River 
below Washington, 
DC 
17. Prevention of 
Obstructions & 
Injurious Deposits, 
Baltimore Harbor, 
MD 
18. Shallow 
Creek, MD 
19. St. Catherines 
Sound, MD 
12,460 
12,460 
180,000 
180,000 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
422,600 
493,639 
38,000 
47,143 
12,100 
12,102 
497,000 
497,399 
1 
51,800 
51,800 
53,200 
53,196 
74,100 
74,100 
36,000 
36,000 
516,000 
516,324 
175,000 
257,475 
-20,278 
27,202 
55,900 
56,312 
372,000 
372,000 
905 
905 
40,000 
40,000 
33,000 
33,000 
575,800 
575,767 
162,065 
127,424 
80,781 
120,462 
100,000 
99,574 
444,000 
444,000 
39,214 
387,685 
387,685 
143,13416 
143,13416 
689,777 
689,773 
350,19317 
350,19317 
9,777,708 
9,777,708 
4,335,900 
4,335,900 
191,72618 
191,72618 
1,606,535 
1,606,535 
7,793,175 
7,793,174 
1,764,065 
1,747,947 
291,866 
287,333 
153,836 
153,836 
2,032,574 
2,032,559 
5,357,040 
5,357,040 
274,405 
268,314 
226,843 
222,138 
29,9471m 
29,9471) 
648,618 
648,618 
417,000 
432,664 
378,000 
323,826 
54,363 
35,825 
84,000 
84,040 
43,500 
7,600 
481,200 
480,942 
164,000 
156,250 
177,000 
103,844 
85,000 
85,011 
230,000 
220,595 
219,843 
212,538 
7,000 
9,600 
53,000 
53,000 
324,000 
324,000 
4-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
20. Washington 
Harbor, DC 
21. Wicomico River, 
MD 
25. Cumberland, MD 
and Ridgeley, 
WV 
26. Hills Point 
Road, Dorchester 
Co., MD 
27. Isle of Wight 
Bay, Ocean 
City, MD 
28. Jennings Randolph 
Lake, MD & WV 
29A. Aylesworth Creek 
Lake, PA 
30. Raystown Lake, 
Raystown Branch, 
Juniata River, PA 
31A. Addison, NY 
31B. Almond Lake, 
NY 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total 
to 
FY86 FY87 FY88 FY89 Sept. 30, 1989 
- - - - 3,191,07720 
- - - - 3,191,07720 
44,000 
44,000 
47,800 
47,800 
32,000 
32,000 
20,000 
19,996 
4,894,29621,22 
4,894,29221,22 
471,60923 
471,6092' 
49,000 
49,001 
61,000 
61,000 
46,100 
13,362 
26,678 
366,000 
365,999 
64,000 
63,998 
30,953 
9,500 
9,337 
993,000 
993,000 
71,000 
71,002 
23,000 
24,589 
39,600 
71,000 
57,902 
742,000 
742,002 
72,000 
72,000 
120,800 
115,991 
8,320 
45,794 
313,800 
231,421 
127,612 
85,083 
55,000 
55,000 
1,759,000 1,121,700 1,113,900 1,244,200 
1,759,018 1,111,628 1,119,760 1,247,520 
101,000 
101,071 
116,900 
116,104 
113,000 
113,740 
214,000 
213,962 
2,108,000 2,149,400 2,279,865 2,568,100 
2,138,283 2,160,024 2,263,777 2,587,911 
14,100 
14,091 
234,000 
234,127 
9,300 
9,309 
324,800 
322,169 
6,700 
6,700 
307,535 
308,416 
13,800 
13,780 
322,000 
323,336 
8,063,737 
8,063,737 
15,633,97024 
15,633,97024 
846,229 
846,229 
189,900 
184,895 
47,920 
45,794 
394,300 
298,660 
127,612 
85,083 
176,325,300 
176,321,783 
9,213,778 
9,212,846 
2,320,400 
2,320,400 
1,407,502 
1,407,401 
77,408,770 
77,408,770 
24,821,160 
24,817,454 
827,050 
827,050 
207,955 
207,935 
5,760,211 
5,760,211 
3,977,175 
3,976,747 
4-24

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
31C. Arkport Dam, 
NY 
31D. Avoca, NY 
31E. Binghamton, NY 
31F. Canisteo, NY 
31G. Corning, NY 
31H. East Sidney Lake, 
NY 
311. Elmira, NY 
31J. Hornell, NY 
31K. Lisle, NY 
31L. Oxford, NY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
148,000 
148,073 
24,300 
24,300 
383,000 
40,480 
35,200 
35,200 
25,900 
25,874 
38,500 
38,500 
330,000 
329,995 
28,300 
28,297 
135,900 
135,901 
26,100 
26,098 
11,300 
11,290 
199,900 
199,401 
31,300 
31,300 
320,000 
20,392 
28,700 
28,700 
27,800 
27,827 
50,100 
50,100 
378,800 
378,421 
27,600 
27,603 
242,400 
242,399 
28,600 
28,602 
9,100 
9,110 
144,100 
143,850 
9,200 
9,200 
415,000 
396,857 
17,400 
17,400 
45,100 
45,100 
43,800 
43,800 
142,000 
141,763 
9,100 
9,098 
30,000 
50,271 
30,700 
30,700 
42,400 
42,366 
26,700 
26,655 
364,500 1,130,600 
364,266 1,130,829 
7,900 
7,900 
266,000 
266,000 
22,600 
22,600 
5,900 
5,900 
12,100 
12,100 
567,400 
567,337 
32,000 
31,998 
11,000 
11,000 
4-25 
1,910,00025 
1,910,00025 
2,077,174 
2,076,179 
436,37426 
436,37426 
430,261 
430,258 
3,460,00027 
3,460,00027 
490,581 
490,581 
1,183,11128 
1,183,11128 
733,435 
733,400 
3,322,00029 
3,322,00029 
762,158 
762,113 
6,049,504 
6,049,504 
5,321,219 
5,320,819 
6,883,305 
6,883,305 
312,149 
312,149 
4,558,69880 
4,558,69880 
4,065,933 
4,065,866 
661,19991 
661,19931 
725,322 
725,320 
131,00032 
131,00032 
226,732 
226,732

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
31M. Whitney Point 
Lake, NY 
31N. Whitney Point 
Village, NY 
32. Spring Brook 
Creek, Pittston 
Twp, PA 
33. Stillwater Lake, 
Lackawanna 
River, PA 
34A. Cowanesque Lake, 
PA 
34B. Tioga-Hammond 
Lakes, PA 
35. Tunkhannock 
Creek, Tunkhannock, 
PA 
36A. Alvin R. Bush 
Dam, PA 
36B. Curwensville Lake, 
PA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
644,000 
643,908 
18,400 
18,380 
218,000 
218,056 
195,000 
418,395 
894,200 
897,042 
90,000 
65,546 
1,329,800 
1,330,248 
43,500 
33,209 
463,000 
452,583 
628,000 
628,049 
403,800 
398,680 
16,600 
16,620 
17,500 
11,736 
223,800 
223,206 
532,000 
535,149 
16,300 
16,300 
54,000 
38,986 
239,800 
239,286 
622,000 278,000 
197,929 699,422 
974,300 938,900 
970,947 939,625 
1,277,000 5,010,000 
577,849 4,451,354 
360,000 
265,978 
1,412,600 
1,403,881 
7,352 
537,700 
546,080 
456,300 
455,574 
140,000 
167,374 
1,888,400 
1,892,334 
2,281 
369,200 
369,237 
449,300 
448,896 
731,700 
733,420 
20,100 
20,098 
287,000 
20,976 
315,000 
392,400 
393,128 
5,421,539 
5,421,539 
5,762,640 
5,762,210 
424,096 
424,096 
376,661 
376,659 
358,500 
71,698 
315,000 
5,725,700 
5,725,700 
2,916,209 
2,915,810 
- 108,860,700 
-524,248 108,330,971 
1,110,400 
1,111,622 
5,341,000 
5,572,939 
3,779 
1,333,600 
1,337,198 
131,600 
1,902 
52,933 
426,000 
427,276 
449,600 
450,171 
7,692,954 
7,690,900 
11,628,000 
10,602,142 
19,244,800 
19,152,477 
13,019,254 
13,017,998 
175,100 
44,744 
52.933 
7,103,001 
7,103,001 
5,463,522 
5,462,764 
20,396,060 
20,396,060 
7,344,589 
7,344,001 
4-26

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
39C. Foster Joseph New Work 
Sayers Dam, PA Approp. - - - - 30,887,063" 
Cost - - - - 30,887,063" 
Maint. 
Approp. 424,000 549,400 518,100 550,300 6,523,884 
Cost 423,980 549,169 516,250 551,937 6,523,411 
37. York, Indian New Work 
Rock Dam, PA Approp. - - - - 5,061,167' 
Cost - - - - 5,061,167" 
Maint. 
Approp. 548,000 384,300 547,500 617,400 6,416,417"5 
Cost 557,982 384,227 546,776 617,951 6,416,139" 
1. Includes $8,764,003 for previous projects. 17. Includes $283,008 public works funds and $67,185 
2. Includes $967,791 for sections of project in Norfolk emergency relief funds; excludes $500,000 contributed funds. 
District. 18. Unconstructed portion of the project is inactive. In- 
3. Includes $967,791 for sections of project in Norfolk cludes $20,500 for previous project. 
District. 19. Excludes $600 contributed funds. 
4. Includes $127,604 for sections of project in Norfolk 20. Includes $3,029,001 for previous project. 
District. 21. Includes $1,831,609 for previous project. 
5. Includes $127,518 for sections of project in Norfolk 22. Excludes $4,000 for emergency dredging under pro- 
District. visions of Section 3, 1945 River and Harbor Act. 
6. Includes $558,504 for sections of project in Norfolk 23. Includes $50,000 for previous project and excludes 
District. $14,000 contributed funds. 
7. Includes $555,057 for sections of project in Norfolk 24. Includes $49,998 emergency relief funds. 
District. 25. Includes $62,577 emergency relief funds. 
8. Includes $310,485 for sections of project in Norfolk 26. Includes $109,944 emergency relief funds. 
District. 27. Excludes $163,096 contributed funds. 
9. Includes $314,269 for sections of project in Norfolk 28. Includes $207,520 rehabilitation funds. 
District. 29. Excludes $34,729 contributed funds. 
10. Includes $399,802 for previous projects. 30. Includes $250,899 emergency relief funds and excludes 
11. Excludes $3,998 contributed funds and includes $15,000 contributed funds. 
$61,321 for previous project. 31. Includes $71,557 emergency relief funds. 
12. Includes $87,740 for previous project. 32. Includes $73,465 emergency relief funds. 
13. Includes $2,839 for previous project. 33. Excludes $263,900 contributed funds in accordance 
14. Excludes $2,200 contributed funds and includes with the Tri-party Agreement for construction of sanitary 
$27,668 emergency relief funds. system for public use. 
15. Excludes $5,000 contributed funds. 34. Includes $11,588 emergency relief funds. 
16. Includes $5,000 for previous project. 35. Includes $15,000 for deferred maintenance. 
TABLE 4-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
BALTIMORE HARBOR AND CHANNELS, MD and VA 
Aug. 8, Branch channel 35 feet deep to head of Curtis Bay, and one 35 feet deep and 
1917 400 feet wide Fort McHenry to Port Covington entrance channel, thence 
150 feet wide to Ferry Bar, and thence 27 feet deep and 150 feet wide to 
Hanover Street Bridge, widen approaches and bends, and enlarge anchorage 
basin near entrance. Inclusion of Patapsco River and tributaries into one 
project for Baltimore Harbor.' 
Jan. 21, Change in location of anchorage near upper end of Fort McHenry Channel. 
1927 
Jul. 3, Increased anchorage facilities. 
1930 
H. Doc. 799, 
64th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 11, 
70th Cong., 1st Sess. 
4-27 
1.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-B (Continued) 
See Date 
Section Authorizing 
in Text Act 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
Jul. 3, For 37-foot depth in that portion of channel to Baltimore lying between 37-foot 
1930 depth curve near Baltimore Light to Sparrows Point entrance channel; widen 
angle between Fort McHenry and Ferry Bar section; and for width of 400 
feet in Curtis Bay section. 
Oct. 17, For 22-, 18-, and 15-foot channels in Curtis Creek from 22-foot depth below 
1940 Pennington Avenue Bridge to upper end of marginal wharf of U.S. Ordnance 
Depot. 
Mar. 2, Uniform main channel 39 feet deep from the ocean through York Spit section 
1945 and Craighill entrance to Fort McHenry, additional anchorage area, 2,400 
feet long, 1,200 feet wide, and 30 feet deep; a connecting channel 400 feet 
wide and 27 feet deep from Cutoff Brewerton Angle in main channel to Inland 
Waterway from Delaware River to Chesapeake Bay; a channel in Curtis Creek 
200 feet wide and 35 feet deep from head of existing 35-foot project channel 
in Curtis Bay to a point in the creek about 750 feet below Pennington 
Avenue Bridge. 
Mar. 2, A channel 22 feet deep and 200 feet wide from 22-foot depth curve south of 
1945 Baltimore & Ohio R.R. bridge about 2,800 feet to vicinity of Arundel Cove, 
thence 100 feet wide in Arundel Cove for about 2,100 feet; with an anchorage 
basin about 700 feet square adjacent to channel southwesterly of Coast 
Guard wharf. 
Jul. 3, Main channel 42 feet deep and 1,000 feet wide in Cape Henry section at 
1958 entrance to Chesapeake Bay and in York Spit section; 42 feet deep and 800 
feet wide in Rappahannock Spit section and in approach channel to Baltimore 
Harbor from Craighill entrance to Fort McHenry, with widening at entrance 
and bends; channels 42 feet deep and 600 feet wide in Curtis Bay and Ferry 
Bar sections of harbor; a connecting channel 35 feet deep and 600 feet wide 
from main channel to approach channel to Chesapeake and Delaware Canal; 
and for three disjointed sections of channels of same depth and width in 
Chesapeake Bay leading to Chesapeake and Delaware Canal; and to provide 
Federal maintenance of 39-foot depth in Northwest Branch, in areas dredged 
to that depth by local interests. 
Dec. 31, Deepening of the Cape Henry Channel to 50 feet at the existing width of 
1970 1,000 feet, with widening at bends; deepening of the Spit Channel to 50 feet 
at the existing width of 1,000 feet, with widening at bends; enlargement of 
the Rappahannock Shoal Channel to a depth of 50 feet and a width of 1,000 
feet; deepening of the main ship channel from Chesapeake Bay to Fort 
McHenry to a depth of 50 feet at the existing width of 800 feet, with widening 
at bends and at the Craighill Entrance; deepening of the Curtis Bay 
Channel to a depth of 50 feet at the existing width of 600 feet, and deepening 
of the 950-foot wide and 980-foot long turning basin at the head of channel 
to the same depth; deepening of the Northwest Branch-East Channel to 
a depth of 49 feet from the depth existing at the time of construction at a 
width of 600 feet, and deepening of the 950-foot wide and 950-foot long turning 
basin at the head of the channel to the same depth; and deepening and 
extension of the Northwest Branch-West Channel to a depth of 40 feet from 
the depth existing at the time of construction, at a width of 600 feet, and 
with an irregularly shaped turning basin at the head of the channel 40 feet 
deep and about 2,000 feet long with a maximum width of 1,150 feet. 
BALTIMORE HARBOR, MD-COLLECTION AND REMOVAL OF 
DRIFT 
Jun. 30, Collection and removal of drift from Baltimore Harbor and its tributary 
1948 waters. 
CAMBRIDGE HARBOR, MD 
Mar. 3, Channel 12 feet deep and 150 feet wide to the drawbridge 10 feet deep and 
1925 100 feet wide from the bridge to the upper end of the harbor with a turning 
basin. 
Aug. 26, Channel 14 feet deep from that depth in Choptank River to the head of the 
1937 harbor with widths of 150 feet below the Market St. Bridge in Cambridge 
and 100 feet above, and a turning basin of the same depth at the head of the 
channel; for an anchorage basin 10 feet deep, 400 feet long, and 175 feet wide 
H. Doc. 86, 
85th Cong., 1st Sess. 
Adopted as a national 
defense project. (No 
printed report.) 
H. Doc. 741, 
79th Cong., 2nd Sess. 
In accordance with 
plans on file in the 
Office, Chief of 
Engineers 
H. Doc. 86, 
85th Cong., 1st Sess. 
H. Doc. 181, 
94th Cong., 1st Sess. 
River and Harbor Act 
of 1948 
H. Doc. 210, 
68th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 7, 
75th Cong., 1st Sess. 
4-28 
Documents 
2. 
3. 
I

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
on the west side of the channel and a second basin of the same depth 225 
feet long and 200 feet wide on the east side of the channel; and a channel 
60 feet wide and 7 feet deep from that depth in Choptank River to the 
municipal boat basin. 
Jun. 30, Modification providing for deepening of the channel in Choptank River and 
1948 Cambridge Creek to 16 feet, with a turning basin of the same depth and of 
irregular dimensions comprising approximately 2.4 acres. 
Jun. 16, Modification providing for Federal maintenance of locally constructed channel 
1978 150 feet wide and 25 feet deep, from that depth in the Choptank River to 
and including a irregularly shaped turning basin of the same depth, with 
such modifications as in the discretion of the Chief of Engineers may be 
advised at an added first cost to the United States presently estimated at 
$257,000. 
4. 
Mar. 3, 
1925 
Aug. 26, 
1937 
Aug. 26, 
1937 
CRISFIELD HARBOR, MD 
A 12-foot channel of varying widths to opposite Consumers Ice Co., thence 
10 feet deep and 100 feet wide from ice plant to Hop Point. 
7-foot channel 100 feet wide from opposite Hop Point to an anchorage parallel 
to Brick Kiln Road. 
For the 7 foot x 60 foot channel in Little Annemessex River... 
Mar. 3, A mooring basin 7 feet deep, 160 feet wide, and about 875 feet long roughly 
1945 parallel to Brick Kiln Rd., with a channel 7 feet deep and 100 feet wide 
leading therefrom to the 7-foot project channel connecting Little Annemessex 
and Big Annemessex Rivers. 
Sep. 3, An anchorage basin in Somers Cove 10 feet by 600 feet by 1,000 feet with an 
1954 approach channel 10 feet by 100 feet from 10-foot depth in Little Annemessex 
River through a land cut in Jersey Island to south side of basin. 
Aug. 14, Change location and dimensions of approach channel to Somers Cove to plan 
1958 No. 2 through the present entrance, at no increase in Federal cost of 
modification. 
FISHING BAY, MD 
Aug. 26, Provided for channels 6 feet deep and generally 60 feet wide at mean low 
1937 water, suitably widened where necessary to offer adequate sheltered 
anchorage space from deep water and in Fishing Bay to vicinity of county 
or packing house wharves in McCreadys, Farm, and Goose Creeks. 
HERRING BAY & ROCKHOLD CREEK, MD 
Jul. 3, A channel 60 feet wide, 5 feet deep, from the 6-foot contour in Herring Bay 
1930 to the 3-foot contour in Rockhold Creek. 
Jun. 20, For the present project channel dimensions, 7 feet deep and 60 feet wide, 
1938 the turning basin 7 feet deep, and a stone breakwater 900 feet long. 
HERRING CREEK, TALL TIMBERS, MD 
Jul. 3, Provides for an entrance channel 6 feet deep and 60 feet wide with a 
1950 turning basin of irregular shape and 6 feet deep, and riprap stone jetties 
on the upstream and downstream sides of the entrance channel 770 and 650 
feet long, respectively. The project length is 1,630 feet. 
Mar. 7, 
1986 
Sec 111 
Constructing 250 feet of beachfill, 2,187 linear feet of stone revetment, 
and upgrading 350 feet of existing revetment along the Tall Timbers 
waterfront. 
HONGA RIVER AND TAR BAY (BARREN ISLAND GAPS), MD 
Aug. 30, Channel 60 feet wide and 7 feet deep from the 7-foot contour in Chesapeake 
1935 Bay through Tar Bay and Fishing Creek to the 7-foot contour in Honga 
River. 
H. Doc. 381, 
80th Cong., 1st Sess. 
H. Doc. 355, 
95th Cong., 2 Sess. 1 
H. Doc. 355, 
68th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 2, 
75th Cong., 1st Sess. 
H. Doc. 72, 
75th Cong., 1st Sess. 
H. Doc. 457, 
76th Cong., 1st Sess. 
H. Doc. 435, 
81st Cong., 2d Sess. 
H. Doc. 435, 
81st Cong., 2d Sess. 
H. Doc. 186, 
75th Cong., 1st Sess 1 
Rivers and Harbors 
Committee Doc. 34, 
71st Cong., 2nd Sess. 
H. Doc. 595, 
75th Cong., 3rd 
Sess.' 
H. Doc. 159 
84th Cong., 1st Sess. 1 
Detailed Project 
Report 
July 18, 1985 
Rivers and Harbors 
Committee, Doc. 35, 
74th Cong., 1st Sess. 
4-29 
5. 
6. 
7. 
8.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun. 30, Modification providing for a channel in Back Creek 7 feet deep and 60 feet 
1948 wide from the 7-foot depth curve in Honga River to a point near the head 
of Back Creek, with a turning basin of the same depth, 150 feet long and 
200 feet wide. 
LITTLE WICOMICO RIVER, VA 
Aug. 30, A channel 8 feet deep and 150 feet wide from Potomac River to deep water 
1935 in Little WVicomico River; two stone jetties 1,000 feet and 1,300 feet long 
at the entrance; and 1,004 linear feet of timber bulkhead to stabilize the 
dredged inner channel. 
MONROE BAY AND CREEK, VA 
Jul. 3, A channel 8 feet deep, 100 wide, and 950 feet long, through the bar at the 
1930 entrance, and within the creek a channel 7 feet deep, 100 feet wide, and 
2,500 feet long, with turning and anchorage basin 500 feet wide at upper end. 
11. 
Jun. 3, 
1896 
Jun. 25, 
1910 
Jun. 25, 
1910 
Mar. 2, 
1945 
NANTICOKE RIVER (INCLUDING NORTHWEST FORK), DE & MD 
A 9-foot channel, 100 feet wide up to Seaford, DE, with a turning basin. 
Slight widening between bridges in harbor at Seaford, DE. 
A channel 6 feet deep, 60 feet wide in Northwest Fork, together with turning 
basin. 
A channel 12 feet deep, 100 feet wide from 12-foot contour in Tangier Sound 
to highway bridge at Seaford, DE. 
OCEAN CITY HARBOR & INLET & SINEPUXENT BAY, MD 
Aug. 30, Construction of an inlet between the Atlantic Ocean and Sinepuxent Bay, 
1935$ 10 feet deep and 200 feet wide, protected by jetties; a channel 8 feet deep 
and 100 feet wide from the inlet to Ocean City, 6 feet deep and 150 feet 
wide to Green Point, and 100 feet wide into Chincoteague Bay. 
Aug. 30, Modification providing a 10-foot by 100-foot channel from the inlet to the 
1935' west side of the bay with two turning basins; a channel 6 feet deep and 125 
feet wide from the inlet channel to opposite North 8th Street, Ocean City, 
and 75 feet wide into Isle of Wight Bay. 
Sep. 3, Modification providing for raising the north jetty to an elevation 9 feet 
19456 above mean low water, and a channel 300 feet wide and 16 feet deep from 
the ocean through the inlet to the Isle of Wight Bay Channel, thence 200 
feet to the project harbor, and a depth of 14 feet in the project harbor. Channel 
depths refer to project datum, 
13. 
Jun. 3, 
1896 
Aug. 30, 
1935 
Mar. 2, 
1945 
Sep. 3, 
1954 
POCOMOKE RIVER, MD 
A 9-foot channel from Shad Landing to Snow Hill. 
A channel 7 feet deep and 100 feet wide from Pocomoke Sound to Pocomoke 
River. 
Extend channel above bridge at Snow Hill, 100 feet wide, 9 feet deep, 
widened to 150 feet to form a turning basin at upper end. 
Channel 11 feet deep by 150 feet wide from Pocomoke Sound to Tulls Point, 
thence a channel of the same depth and 100 feet wide to deep water in 
Pocomoke River above Williams Point, and dike construction along south 
side of channel from existing dike to Tulls Point. 
POTOMAC & ANACOSTIA RIVERS, DC-COLLECTION & 
REMOVAL OF DRIFT 
Oct. 27, Collection and removal of drift from waters of the Potomac and Anacostia 
1965 Rivers and their tributaries in the Washington, DC area from the head of 
the tidewater to Mount Vernon, VA. 
9. 
4-30 
10. 
H. Doc. 580, 
80th Cong., 2nd Sess.1 
Rivers and Harbors 
Committee Doc. 24, 
72nd Cong., 1st Sess. 
H. Doc. 172 
70th Cong., 1st sess. 
H. Doc. 323, 
53rd Cong., 3rd Sess., 
and Annual Report, 
1985, p. 1165. 
H. Doc. 674, 
61st Cong., 2nd Sess. 
H. Doc. 869, 
60th Cong., 1st Sess.2 
S. Doc. 69, 
77th Cong., 1st Sess., 
Rivers and Harbors 
Committee Doc. 38, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 60, 
74th Cong., 1st Sess. 
H. Doc. 444, 
82nd Cong., 2nd Sess. 
Annual Report for 
1895, p. 1167. 
H. Doc. 227, 
74th Cong., 1st Sess.' 
H. Doc. 429, 
76th Cong., 1st Sess.' 
H. Doc. 486, 
81st Cong., 2nd Sess. 
H. Doc. 286, 
89th Cong., 1st Sess. 
12. 
14.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
POTOMAC RIVER AQUATIC PLANT CONTROL, MD, VA, DC 
Jul. 2, Control of Hydrilla and other nuisance plants using mechanical harvesting 
1986 to clear a 60 foot wide, 6 foot deep connecting channel from open waters to 
eligible public use areas. 
POTOMAC RIVER BELOW WASHINGTON, DC 
Mar. 3, A channel 24 feet deep and 200 feet wide between mouth at Chesapeake Bay 
1899 and Giesboro Point at Washington, DC, a distance of 108 miles. 
PREVENTION OF OBSTRUCTIONS & INJURIOUS DEPOSITS, 
BALTIMORE HARBOR, MD 
Aug. 28, Continuous patrol and inspection of Baltimore Harbor, Chesapeake Bay, 
1958 and its tributaries to prevent and detect violations, and issue permits as 
required for transporting and depositing waste materials in navigable 
waters. (The project is limited to the tidal waters of Chesapeake Bay and 
its tributaries that lie within the State of Maryland.) 
18. 
May 22, 
1987 
Sec. 107 
SHALLOW CREEK 
Dredging a navigation channel, 5 feet deep at mean low water, 50 feet wide, 
and 2,700 feet long from the Patapsco River to a turning basin, 100 feet 
wide by 100 feet long at the head of creek. 
ST. CATHERINES SOUND, MD 
Mar. 2, Channel 6 feet deep, 100 feet wide and 700 feet long at the lower entrance 
1945 from the Potomac River and a channel 6 feet deep, 80 feet wide and 3,330 
feet long at the Upper entrance from the Wicomico River. 
WASHINGTON HARBOR, DC 
Aug. 30, Provides for: (a) Virginia Channel, from Giesboro Point to area for 25,000 
1935 square feet; (b) Washington Channel, from Haines Point to head of Washington 
Channel, 24 feet deep and 400 feet wide; (c) Anacostia River from 
Giesboro Point to Anacostia Bridge, 24 feet deep and 400 feet wide, with 
turning basin 800 feet wide and about 2,400 feet long of same depth opposite 
Naval Weapons Plant; (d) Anacostia River from Anacostia Bridge 24 feet 
deep and 200 feet wide to turning basin 400 feet square of same depth at 
foot of 15th Street SE Channel lengths including turning basins are: Virginia 
Channel, 25,000 feet; Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and (e) operation and maintenance of inlet gates and lock and 
outlet gates of Tidal Basin constructed under a previous project to flush 
Washington Channel. 
21. 
Sep. 19, 
1890 
Jun. 25, 
1910 
Mar. 2, 
1919 
Jul. 3, 
1930 
Aug. 26, 
1937 
WICOMICO RIVER, MD 
Channel 9 feet deep from Main Street Bridge to about 2 miles below. 
Extend 9-foot depth into north prong from Main Street Bridge to the 
Salisbury Dam and turning basin. 
Extend 9-foot depth into south prong to head of navigation at Cathell Street, 
including a turning basin, and extend project down to mouth of river in 
Monie Bay. 
A 12-foot channel below the Main Street Bridge. 
A 14-foot channel, 150 feet wide; depths of 14 feet in the north and south 
prongs and a basin 6 feet deep at Webster Cove and approach channel 
thereto of the same depth. 
Sep. 3, Enlarge existing basin at Webster Cove, by dredging an extension 6 feet 
1954 deep, 100 feet wide, and 200 feet long on each side of existing basin to 
form a T-shaped harbor. 
16. 
17. 
4-31 
15. 
State Design 
memorandum 
July 2, 1986 
H. Doc. 33, 
52nd Cong., 1st Sess. 
River and Harbor Act, 
June 29, 1888 as 
amended by Public 
Law 85-802, dated 
August 28, 1958 
Detailed Project 
Report Jan. 1986 
H. Doc. 242, 
76th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 22, 
74th Cong., 1st Sess.1 
H. Doc. 20, 
51st Cong., 1st Sess., 
and Annual Report 
1890, p. 947, 
H. Doc. 569, 
61st Cong., 2nd Sess. 
H. Doc. 1509, 
63rd Cong., 3rd Sess. 
Senate Committee 
Print, 75th Cong., 
3rd Sess.1 
H. Doc. 619, 
81st Cong., 2nd Sess. 
19. 
20.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun. 22, 
1936 
Jul. 24, 
1946 
Aug. 19, 
1988 
Sec. 14 
Oct. 6, 
1988 
Sec. 14 
Oct. 23, 
1962 
25. 
LACKAWANNA RIVER BASIN, PA 
Oct. 23, Construction of Aylesworth Creek Lake, Fall Brook Lake, and local pro- 
1962 tection works on Lackawanna River at Scranton, Pennsylvania. 
RAYSTOWN LAKE, RAYSTOWN BRANCH, JUNIATA RIVER, PA 
Oct.23, Construction of dam and appurtenant facilities. 
1962 
Jun. 22, 
1936 
modified 
by Acts 
of Jun. 
28, 1938; 
Aug. 18, 
1941; 
Dec. 22, 
1944; 
May 17, 
1950; and 
Jul. 3, 
1958 
Jan. 26, 
1989 
Sec. 14 
Aug. 18, 
1941 
SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
Construction of detention reservoirs and related flood control works for 
protection of Binghamton, Hornell, Corning and other towns in New York 
and Pennsylvania. 
SPRING BROOK CREEK, PITTSTON TOWNSHIP, PA 
Consists of the excavation and backfilling of the existing streambank and 
placement of approximately 870 feet of stone riprap. 
STILLWATER LAKE, LACKAWANNA RIVER, PA 
Construction of a flood control reservoir. 
SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, NY AND PA 
Jul. 3, Construction of Cowanesque and Tioga-Hammond reservoirs, local flood 
1958 protection works at Elkland, PA, and Nichols, NY and channel improvement 
at Cortland, NY. 
Oct. 22, Modification in connection with the construction of Cowanesque Lake to 
1976 relocate the Town of Nelson, PA, to a new townsite. 
Mar. 1, Modification of Cowanesque Lake to include water supply as provided by 
1983 Section 4 of the Flood Control Act of 1944 (PL 78-534) and Section 301 of 
Water Supply Act of 1958 (PL 85-500). 
CUMBERLAND, MD AND RIDGELEY, WV 
Levees, retaining walls, movable dam, and channel clearing for Cumberland, 
West Cumberland and South Cumberland, MD and Ridgeley, WV. 
Levees, wall, channel improvement, remove Chesapeake and Ohio Canal 
Dam and construct new industrial dam. 
HILLS POINT ROAD, DORCHESTER CO., MD 
Consists of five offshore stone rubble mound breakwaters, each 50 feet long, 
located a distance of about 100 feet offshore. Also the project provides for 
bank stabilization with beachfill and planting of vegetation to prevent erosion 
of the roadway. 
ISLE OF WIGHT BAY, OCEAN CITY, MD 
Consists of the placement of 3,500 tons of steel sheetpile bulkhead along 
Chicago Avenue. 
JENNINGS RANDOLPH LAKE, MD & WV 
Construction of Bloomington Lake project. 
4-32 
26. 
H. Doc. 101, 
73rd Cong., 1st Sess. 
Report on file in 
Office, Chief of 
Engineers. 
Detailed Project 
Report Dec. 1988 
Initial Appraisal 
Report Jul. 1986 
H. Doc. 469, 
87th Cong., 2nd Sess. 
S. Doc. 141, 
87th Cong., 2nd Sess. 
H. Doc. 565, 
87th Cong., 2nd Sess. 
H. Doc. 702, 
77th Cong., 2nd Sess. 
Initial Appraisal 
Report Nov. 1985 
H. Doc. 702, 
77th Cong., 2nd Sess. 
H. Doc. 394, 
84th Cong., 2nd Sess. 
27. 
28. 
29. 
30. 
31. 
32. 
33. 
34.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
35. TUNKHANNOCK CREEK, TUNKHANNOCK TOWNSHIP, PA 
Sep. 22, Consists of the removal of a shoal in the creek and the placement of fill Initial Appraisal 
1988 material capped with riprap along approximately 250 feet of the Report Mar. 1986 
Sec. 14 streambank. 
36. WEST BRANCH OF SUSQUEHANNA RIVER, PA 
Sep. 3, Construction of three flood control reservoirs. H. Doc. 29, 
1954 84th Cong., 1st Sess. 
37. YORK, INDIAN ROCK DAM, PA 
Jun. 22, Construction of Indian Rock Dam and channel improvements on Codorus H. Doc. 702, 
1936 Creek. 77th Cong., 2nd Sess. 
1. Contains latest published maps. September 16, 1933. The site chosen for the inlet under this 
2. Exclusive of portion considered inactive. Inactive por- authorization was that opened just south of Ocean City by 
tion is widening 35-foot depth channel from 150 to 400 feet from natural forces during a severe storm in August 1933. This 
Port Covington to Ferry Bar, widening 27-foot depth channel eliminated the necessity for an 8-foot channel from the inlet to 
from 150 to 250 feet to Hanover Street Bridge, and providing Ocean City. 
a channel 27 feet deep by 250 feet wide to Western Maryland 4. Included in Emergency Relief program 1935. 
Railway Bridge with an anchorage and turning basin at the 5. Raising of the north jetty to an elevation of 9 feet above 
upper end. mean low water was accomplished with maintenance funds in 
3. Included in Public Works Administration program 1956. 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Accotink Creek, VA' 
Anacostia River and Flats2 
Annapolis Harbor, MD 
Aquia Creek, VA 
Back Creek, MD 
Betterton Harbor, MD 
Black Walnut Harbor, MD 
Bonum Creek, VA' 
Branson Cove, 
Lower Machodoc River, VA 
Breton Bay, MD7 
Broad Creek River, DE 
Broad Creek, MD 
Chester River, MD 
Choptank River, MD" 
Claiborne Harbor, MD 2 
Corsica River, MD 
Cypress Creek, MD 
Duck Point Cove, MD 
Elk and Little Elk Rivers, MD ' s 
Fishing Creek, MD 
Goose Creek, MD'6 
Island Creek, MD 
Completed 
Deferred 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1878 
1953 
1946 
1928 
1946 
1960 
1982 
1982 
1950 
1950 
1964 
1962 
1988 
1979 
1987 
1948 
1947 
1982 
1932 
1987 
1973 
1948 
$ 5,000 
3,910,582 
34,250' 
52,4654 
23,061 
3,482 
32,631 
202,0006 
15,755 
47,924'8 
64,510' 
28,227 
70,49510 
96,796 
42,974 
39,07112 
3,057 
25,289 
90,1211' 
111,242 
75,900 
6,230 
- 
17,366 
11,770 
41,378 
431,478 
155,314 
17,675 
12,621 
114,373 
82,630 
1,638,924 
94,095 
669,933 
90,736 
10,528 
325,765 
53,80816 
1,422,100 
8,312 
54,828 
4-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C (Continued) 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Island Creek, St. Georges Island, MD Completed 1988 23,836 478,009 
Knapps Narrows, MD Completed 1988 46,12118 1,887,575 
La Trappe, MD Completed 1980 8,064 40,475 
Little Creek, Kent Island, MD Completed 1958 23,0001 7,327 
Lowes Wharf, MD Completed 1986 21,000 317,829 
Lower Machodoc Creek, VA Completed 1904 9,916 25,143 
Lower Thorofare, Deal Island, MD Completed 1988 1,787,15818 640,938 
Madison Bay, MD6 Completed 1977 125,550 33,353 
Manokin River, MD 19 Completed 1919 34,78820 43,534 
Middle River and Dark Head Creek, MD Completed 1947 38,71521 34,354 
Muddy Hook and Tyler Coves, MD6 Completed 1984 64,001 425,780 
Nan Cove, MD6 Completed 1965 34,861"2 22,498 
Nanticoke River at Bivalve, MD'3 Completed 1983 240,817 142,131 
Nanticoke River, MD Completed 1971 73,243 76,895" 
Neabsco Creek, MD Inactive 1978 14,600 - 
Neale Sound, MD Completed 1988 12,60024 348,771 
Neavitt Harbor, MD6 Completed 1968 36,500 34,533 
Nomini Bay and Creek, VA25 Completed 1946 78,446 42,063 
Northeast River, MD Completed 1984 28,48928 937,074 
Occoquan Creek, VA18 Completed 1971 66,25387 203,198 
Parish Creek, MD Completed 1988 19,17028 516,648 
Patuxent River, MD12 Completed 1905 14,00029 - 
Potomac River and Tributaries at and 
below Washington, DC, Elimination 
of Waterchestnut Completed 1977 - 184,394 
Potomac River at Alexandria, VA Completed 1965 95,214 506,394 
Potomac River at Lower Cedar Point, MD Completed 1920 10,234 6,216 
Potomac River at Mt. Vernon, VA18 Completed 1984 17,000 331,219 
Potomac River North Side 
of Washington Channel, DC' Completed 1956 1,744,69250 27,461" 
Queenstown Harbor, MD Completed 1985 72,85881 321,803 
Rhodes Point to Tylerton, MD Completed 1988 304,000 1,003,857 
Rock Hall Harbor, MD Completed 1982 1,072,5002 77,113 
Shad Landing State Park, MD Completed 1966 33,53183 14,921 
Slaughter Creek, MD Completed 1987 4,140 591,570 
St. Georges Creek, MD Completed 1985 147,650 - 
St. Jeromes Creek, MD Completed 1988 44,3574 443,542 
St. Michaels Harbor, MD6 Completed 1964 16,723" 14,403 
St. Patricks Creek, MD Completed 1987 15,752 133,403 
St. Peters Creek, MD6 Completed 1963 46,74098 31,716 
Smith Creek, MD Completed 1936 5,252 16,448 
Susquehanna River 
above and below Havre De Grace, MD Completed 1985 293,570"7 929,019 
Susquehanna River at Williamsport, PA9 Completed 1974 57,031"8 41,437 
Tilghman Island Harbor, MD Completed 1983 424,80039 386,985 
Town Creek, MD Completed 1950 43,220 41,959 
Tred Avon River, MD Completed 1988 523,310 845,243 
Tuckahoe River, MD Completed 1980 9,727 23,489 
Twitch Cove and 
Big Thorofare, MD Completed 1988 193,175 2,554,411 
Tyaskin Creek, MD Completed 1923 16,297' o 54,302 
Upper Machodoc Creek, VA Completed 1971 20,281 34,777 
Upper Thorofare, MD Completed 1987 62,446 814,657 
Warwick River, MD Completed 1984 22,041^' 148,728 
4-34

BALTIMORE, MD DISTRICT 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C (Continued) 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
1. Unconstructed portion of the project was deauthorized 
August 5, 1977. 
2. Project deferred for restudy. 
3. Includes $8,476 for previous project. 
4. Includes $31,065 for previous project. 
5. Authorized by Chief of Engineers. 
6. Unconstructed portion of the project is inactive. 
7. Excludes $3,998 contributed funds. 
8. Includes $37,500 for previous project. 
9. Includes $50,000 for previous project. 
10. Includes $38,041 for previous project. 
11. Authorization for the unconstructed portion of the 
project was withdrawn by the Chief of Engineers January 
22, 1979. 
12. Includes $30,000 for previous project. 
13. Unconstructed portion of the project was deauthorized 
November 2, 1979. 
14. Includes $79,626 for previous project and excludes 
$8,414 contributed funds. 
15. Includes $24,321 for previous project. 
16. Includes $46,121 public works funds. 
17. Excludes $1,100 contributed funds. 
18. Includes $5,000 for previous project. 
19. Abandonment recommended in 1926 (H. Doc. 467, 69th 
Cong., 1st sess.) 
20. Includes $2,000 expended outside project limits. 
21. Excludes $111,581 expended by Navy Department and 
$54,000 from contributed funds. 
22. Excludes $565 contributed funds. 
23. Excludes $101,162 Public Health Service funds expended 
for waterchestnut removal. 
24. Excludes $1,000 contributed funds. 
25. Unconstructed portion of the project was deauthorized 
November 6, 1977. 
26. Includes $20,640 for previous project. 
27. Includes $25,000 for previous project. 
28. Includes $19,170 Works Progress Administration 
funds. 
29. Includes $10,617 for previous project. 
30. Excludes $389,000 contributed funds. 
31. Includes $19,000 for previous project. 
32. Excludes $672,880 contributed funds. 
33. Excludes $24,125 contributed funds. 
34. Includes $26,500 for previous project. 
35. Excludes $600 contributed funds. 
36. Excludes $6,984 contributed funds. 
37. Unconstructed portion of the project was deauthorized 
November 6, 1977. Includes $22,905 Works Progress funds and 
$97,390 for previous project. 
38. Excludes $40,000 contributed funds. 
39. Excludes $16,409 contributed funds. 
40. Includes $10,158 for previous project. 
41. Includes $6,000 for previous project. 
OTHER AUTHORIZED BEACH 
TABLE 4-D EROSION CONTROL PROJECTS 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Oxford, MD' Completed 1978 $ 97,750' - 
Colonial Beach, VA Active 1986 518,0308 - 
1. Authorized by Chief of Engineers. 
2. Excludes $80,648 contributed funds. 
3. Excludes $414,977 contributed funds. 
4-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 4-E 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Anacostia River and Tributaries, Flood Protection 
and Navigation Improvements, DC and MD Completed 1980 $ 6,042,325 $1,417,655 
Anacostia River and Tributaries, 
Prince Georges Co., MD2 Completed 1977 1,000,0008 - 
Bainbridge, NY'4 Completed 1959 382,000 - 
Bath, NY6 Completed 1970 638,332 - 
Bayard, WV' Completed 1965 55,2188 - 
Black Walnut Point, MD Completed 1985 200,500 - 
Bridgewater, VA' Completed 1953 136,500 - 
Bull Run, PA Completed 1984 2,742,000 - 
Conklin-Kirkwood, NY' Completed 1955 71,000 - 
Cortland, NY' Completed 1970 324,486 - 
Elkland, PA Completed 1971 1,297,850 - 
Endicott Johnson City and Vestal, NY Completed 1979 7,034,5348 - 
Forest Heights, MD' Completed 1964 430,000' - 
Fourmile Run, VA Completed 1987 52,480,000 - 
Greene, NY' Completed 1951 37,000 - 
Kingston-Edwardsville, PA Completed 1979 4,731,39410� - 
Kitzmiller, MD' Completed 1965 501,500" - 
Latta Brook Rd., NY Completed 1984 115,500 - 
Lock Haven, PA' 2 Active 1980 450,000'1 - 
Nichols, NY Completed 1974 1,487,800 - 
Norwich, NY' Completed 1950 94,500 - 
Painted Post, NY5 Completed 1970 414,181 - 
Plymouth, PA Completed 1958 1,911,689" - 
Savage River Dam, MD Completed 1954 2,271,93916 33,999 
Scranton, PA'8 Completed 1971 2,006,800 - 
Sunbury, PA Completed 1953 6,063,000 7 - 
Swoyersville-Forty Fort, PA Completed 1968 2,728,113 - 
Tyrone, PA8 Deferred 1980 6,401,016 - 
Unadilla, NY Completed 1970 1,000,000 9 - 
Upper Marlboro, MD' Completed 1965 590,013 - 
Verona Lake, VA20 Deferred 1978 992,000 - 
Washington, DC and Vicinity Completed 1953 331,9271 - 
Wilkes-Barre, Hanover Township, PA Completed 1958 3,853,4572" - 
Williamsport, PA Completed 1979 12,964,893" - 
Wyoming Valley, PA Completed 1987 25,624,499 - 
1. Local interests will not accept operation and maintenance 
responsibility of the project until the severe erosion 
and sedimentation of the project caused by tropical storm Eloise 
is corrected and the project is restored to design condition. 
2. Excludes $357,022 contributed funds. 
3. Authorized by Chief of Engineers. 
4. Unit of Southern New York Flood Control Projects. 
5. Excludes $182,672 Public Works Acceleration funds 
and $4,290 contributed funds. 
6. Unit of Susquehanna River Flood Control Projects. 
7. Excludes $154,694 contributed funds. 
8. Excludes $87,720 contributed funds. 
9. Includes $1,162,548 emergency relief funds and excludes 
$225,877 emergency relief funds expended prior to adoption 
of project. 
10. Excludes $6,616 contributed funds. 
11. Authorized for Phase I design memorandum stage of 
advanced engineering and design. 
12. Excludes $481,000 for Phase I funded under General 
Investigations beginning October 1, 1978. 
13. Includes $4,357 emergency relief funds. 
14. Includes $200,000 expended from contributed funds. 
15. Unit of Lackawanna River Basin Projects. 
16. Excludes $140,504 contributed funds. 
17. The unconstructed portion of the project was reclassified 
to the deferred category January 8, 1981. 
18. Excludes $132,578 contributed funds. 
19. Authorized for the design memorandum stage of advanced 
engineering and design. 
20. Cost of previous project. Includes $106,500 emergency 
relief funds. 
21. Includes $872,715 emergency relief funds. Excludes 
$36,375 emergency relief funds expended for new work before 
adoption of project. 
22. Includes $1,887 emergency relief funds and excludes 
$110,835 contributed funds. 
4-36

BALTIMORE, MD DISTRICT 
DEAUTHORIZED PROJECTS 
TABLE 4-G 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Almond Village, NY1' 2 
Baltimore Harbor & Channels, MD 
(Ferry Bar & Spring Garden Channel) 
Broadwater Creek, MD 
Cadle Creek, MD2 
Channel Connecting Plain 
Dealing Creek and Oak 
Creek, MD 
Coan River, VA 
Copes Corner Lakes, NY 2 
Cuckold Creek, MD4 
Cunninghill Cove, MD 4 
Davenport Center Lake, NY 2 
Fall Brook Lake, PA5 
Genegantslet Lake, NY 
1970 
1920 
1949 
1949 
1940 
1937 
1970 
1978 
1977 
1970 
1970 
1954 
1950 
1937 
1950 
1950 
1949 
1941 
Governors Run, MD 
Harpers Ferry, WV 
Hellens Creek, MD 
Lake Ogleton, MD 
Mill Creek, MD 
Moorefield, WV 
May 26, 1953 
1941 Flood 
Control Act 
Nov. 17, 1986 
1986 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1914 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Oct. 3, 1978 
1974 Water 
Res. Dev. Act 
4-37 
$ 24,622* 
787,710 
212 
112 
106,7009 
5,720 
11,200 
286,4009 
46,100 
214,5789 
7,928k

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 4-G (Continued) 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Saint Georges Creek, MD 1971 Sep. 23, 1986 $ -- 
1974 Water 
Res. Dev. Act 
Sixes Bridge Lake, MD & PAe 1974 Dec. 29, 1981 -- 
1974 Water 
Res. Dev. Act 
South Plymouth Lake, NY 1953 May 6, 1981 100,036- 
1974 Water 
Res. Dev. Act 
Waterway from Little Choptank River to 1939 Aug. 5, 1977 305- 
Choptank River, MD 1974 Water 
Res. Dev. Act 
West Oneonta Lake, NY2 1970 May 6, 1981 189,1003 
1974 Water 
Res. Dev. Act 
1. Local cooperation withdrawn, project authorization 5. Unit of Lackawanna River Basin Projects. 
expired May 26, 1953. 6. Authorized for the design memorandum stage of ad- 
2. Unit of Southern New York Flood Control Projects. vanced engineering and design. 
3. Cost for preliminary work only. 
4. Project authorization was withdrawn by the Chief of 
Engineers. 
RECONNAISSANCE AND CONDITION SURVEYS 
TABLE 4-H 
Date Survey 
Project Completed 
MARYLAND 
Back Creek 
Black Walnut Harbor 
Chester River 
Lower Thorofare, Deal Island 
Madison Bay 
Muddy Hook and Tyler Coves 
Neavitt Harbor 
Northeast River 
Rhodes Point to Tylerton 
St. Michaels Harbor 
St. Peters Creek 
Smith Creek 
Town Creek 
Upper Thorofare 
Warwick River 
VIRGINIA 
Potomac River at Mt. Vernon 
Occoquan Creek 
August 1989 
Sept ember 1989 
July 1989 
April 1989 
March 1989 
September 1989 
March 1989 
August 1989 
September 1989 
March 1989 
April 1989 
May 1989 
April 1989 
April 1989 
September 1989 
September 1989 
December 1988 
4-38

BALTIMORE, MD DISTRICT 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
INSPECTION OF COMPLETED PROJECTS 
TABLE 4-I 
Date Inspected 
MARYLAND 
Anacostia River Basin 
Cumberland 
Forest Heights 
Kitzmiller 
Savage River Dam 
Upper Marlboro 
NEW YORK 
Addison 
Avoca 
Bainbridge 
Bath 
Binghamton 
Canisteo 
Cincinnatus 
Conklin-Kirkwood 
Corning-Monkey Run 
Cortland 
Elmira 
Endicott-Johnson City & Vestal 
Greene 
Hornell 
Lisle 
Nichols 
Norwich 
Owego 
Oxford 
Painted Post 
Port Dickinson 
Sherburne 
Unadilla 
Vestal 
Whitney Point Village 
PENNSYLVANIA 
Elkland 
Sunbury 
Williamsport 
VIRGINIA 
Bridgewater 
Fourmile Run 
WEST VIRGINIA 
Bayard 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
October 1988 
4-39 
Project

NORFOLK, VA DISTRICT *
NORFOLK, VA DISTRICT 
This district comprises the State of Virginia, except the 
Potomac, Roanoke, and Ohio River Basins; the entire area on the 
eastern shore of Virginia except for the project for Pocomoke River, 
Maryland and Virginia. On the west shore of Chesapeake Bay, all 
waterways south of Smith Point, VA, at the mouth of the Potomac 
River except the project for Little Wicomico River, VA. North 
Carolina, only the Chowan River Basin downstream to and including 
the mouth of the Meherrin River, and the Dismal Swamp Canal 
Route of the Atlantic Intracoastal Waterway to the Albemarle 
Sound. West Virginia, only the James River Basin. 
IMPROVEMENTS 
NAVIGATION PAGE 
1. Appomattox River, VA ................. 5-2 
2. Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL ................. 5-2 
3. Baltimore Harbor and Channels 
(Norfolk District) .................... 5-2 
4. Cape Charles City Harbor, VA ............... 5-2 
5. Chincoteague Inlet, VA.................. 5-3 
6. Deep Creek, Newport News, VA ........... . 5-4 
7. Greenvale Creek, VA ................... 5-4 
8. Hampton Creek, VA .................. 5-4 
9. Hampton Roads, VA 
(Collection and Removal of Drift) ........... 5-4 
10. Horn Harbor, VA ..................... 5-5 
11. James River, VA .................... 5-5 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
Little Machipongo River, VA ............... 5-5 
Norfolk Harbor and Channels (Deepening), VA ... 5-6 
a. Atlantic Ocean Channel, VA ........... 5-6 
b. Channel to Newport News, VA .......... 5-6 
c. Norfolk Harbor Channels, VA ............ 5-6 
d. Thimble Shoal Channel, VA ............ 5-7 
Rudee Inlet, VA...................... 5-7 
Supervision of the Harbor of 
Hampton Roads (Prevention of 
Obstructive and Injurious Deposits) .......... 5-8 
Waterway on the Coast of VA ............. 5-8 
Whitings Creek, VA .................. 5-8 
Navigation Work Under Special 
Authorization ....................... 5-8 
BEACH EROSION CONTROL 
19. Tangier Island Shore Protection . . . . 
20. Virginia Beach, VA ............ 
PAGE 
........ 5-8 
..... ... 5-9 
FLOOD CONTROL 
21. Gathright Dam and Lake Moomaw, VA ....... 5-9 
22. Richmond, VA ...................... 5-9 
23. Scottsville, VA ....... .. ... .......... 5-10 
24. Virginia Beach Streams, 
Canal Number 2, VA ................... 5-10 
25. Flood Control Work Under 
Special Authorization . . . . . . . . .. . . .... .. 5-10 
26. Emergency Flood Control Activities .......... 5-10 
GENERAL INVESTIGATIONS 
27. Surveys .......................... 5-10 
28. Collection and Study of Basic Data .......... 5-10 
TABLES 
TABLE 5-A Cost and Financial Statement . . . .. . . . . 5-11 
TABLE 5-B Authorizing Legislation ............ 5-16 
TABLE 5-C Data Relative to the Completed Locks . . .. 5-20 
TABLE 5-D Other Authorized Navigation Projects . . . . 5-21 
TABLE 5-E Other Authorized Beach Erosion 
Control Projects ................. 5-22 
TABLE 5-F Other Authorized Flood Control Projects . . . 5-22 
TABLE 5-G Reconnaissance and Condition Surveys . . . 5-23 
5-1

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
Navigation 
1. APPOMATTOX RIVER, VA 
Location. This river rises in Appomattox County, VA, flows 
northeasterly 137 miles, and empties into the James River at 
Hopewell, VA. The portion under improvement extends from its 
mouth to Petersburg, VA, adistanceof 11 miles, which is the length 
of the tidal and navigable reach. (See U.S. Coast Geodetic Survey 
Chart No. 531.) 
Previous Projects. For details seepage 469 of Annual Report 
for 1938. 
Existing Project. This provides for a channel 80 feet wide 
and 10 feet deep from the mouth of the river to a point 400 feet 
above Lieutenant Run; thence 80 feet wide and of such depth, not 
exceeding 10 feet, as can be obtained without rock excavation to 
the head of navigation atPetersburg; including a basin at the mouth 
of Poes Run 200 feet long, 150 feet wide, and 20 feet deep: and a 
turning basin at the mouth of Lieutenant Run 500 feet long, 140 to 
160 feet wide, and 12 feet deep in the upper 300 feet, the removal 
of rock to a depth of 18 feet in the north half of the lower 200 feet, 
and removal of soft material to rock in the south half of the lower 
200 feet of this basin. All depths are referred to mean low water. 
The project also provides for a dam at Petersburg and the 
excavation for a width of from 200 to 300 feet of a diversion 
channel connecting the river above the dam with the river at a point 
2.5 miles below; for about 1.7 miles of levees on the low grounds 
between the navigable and the diversion channels; for a highway 
bridge and a railway bridge across the diversion channel; and for 
other work incidental to the diversion channel. 
Under ordinary conditions the mean tidal range is 2.9 feet and 
the extremes 2.4 and 3.3 feet. There are no records available of the 
heights of stage due to ordinary floods. These are estimated at 6 
to 8 feet above mean low water at Petersburg, where the extremes 
are from 15.6 feet to 17.1 feet. 
Local cooperation. Fully complied with. For details see page 
212 of Annual Report for 1969. 
Terminal Facilities. There are about 2,500 feet of wooden 
bulkhead and a shore landing in Petersburg Harbor. These 
facilities are in an abandoned, dilapidated condition and have not 
been used by commercial traffic on the river since 1950. There are 
two large recreational facilities now in operation on the Appomattox 
River. One is located about 2 miles downstream from 
Petersburg, VA and the other is at Hopewell, VA near the confluence 
of the Appomattox and the James. 
Operations and results during fiscal year. Maintenance 
engineering and design and supervision and administration 
amounted to $211,957. 
2. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN 
NORFOLK, VA AND ST. 
JOHNS RIVER, FL 
(NORFOLK DISTRICT) 
Location. Two inland water routes approximately paralleling 
Atlantic coast south of Norfolk, VA between a point in Southern 
Branch of Elizabeth River, Va 2,500 feet upstream of Norfolk & 
Western Railway bridge and Virginia-North Carolina state line in 
North Landing River, a distance of 27.2 miles; and 64.6 miles 
between mouth of Deep Creek, VA and mouth of Pasquotank 
River, NC. These routes are shown on National Ocean Service 
Chart 12206. 
Existing project. A channel 12 feet deep at mean low water 
and 90 to 250 feet wide following Southern Branch of Elizabeth 
River, 5.2 miles, Virginia Land Cut, 8.3 miles, and North Landing 
River, 13.7 miles; and construction of tidal guard lock at Great 
Bridge, VA. It also provides channels 10 feet deep at mean low 
water and 90 to 100 feet wide in Deep Creek, 3.1 miles, Turners 
Cut, 4.3 miles and Pasquotank River, 35.1 miles; maintaining 
Dismal Swamp Canal, 22.1 miles, to about 9 feet deep mean canal 
level over a width of 50 feet; protection of banks in Turners Cut 
with sheet piling, and cutting certain sharp points in Pasquotank 
River to shorten its course. (See Table 5-C at end of chapter on 
Data Relative to Completed Locks included in Project.) 
Project includes operating and care of completed locks, dams 
and bridges, under maintenance. Southern Branch of Elizabeth 
River and Deep Creek sections of the two routes are tidal, mean 
range being about 3 feet with extremes of minus 3.5 and plus 9.6 
feet Remaining sections are nontidal with fluctuations of 1 to 2 
feet in level due to winds. Cost for new work for completed project 
was $3,396,276. Protection of canal property at Great Bridge 
portion is considered inactive and excluded from foregoing cost. 
Estimated cost of this portion (1954) is $265,000. For details of 
previous projects, see page 476 of Annual Report for FY 1938. (See 
Table 5-B for Authorizing Legislation.) 
Local Cooperation. None required. 
Terminal facilities. Existing facilities are considered adequate. 
See Annual Report for FY 1970. 
Operations during fiscal year. Maintenance: Work on the 
5-year operation and maintenance contract, awarded Feb 88 is 
progressing satisfactorily. A contract to maintain approximately 
250 lineal feet of bulkheading and 1,000 feet of riprap at Deep 
Creek on the Dismal Swamp Canal was awarded at the end of fiscal 
year 1988 and was completed at the end of fiscal year 1989. 
Ordinary operation and maintenance of the project was accomplished 
to include care of locks and dams, condition and 
operation studies, outgranting, engineering and design, supervision 
and administration. 
3. BALTIMORE HARBOR 
AND CHANNELS 
(NORFOLK DISTRICT) 
Existing project. Provides for deep water approach channels 
in Baltimore Harbor. Northern portion including Baltimore Harbor 
is under jurisdiction of Baltimore District. Portion under jurisdiction 
of Norfolk District is more fully described below. 
3A. CAPE HENRY CHANNEL, VA 
Location. At mouth of Chesapeake Bay opposite Cape Henry. 
(See National Ocean Service Chart No. 12222.) 
Existing project. A channel about 2.3 miles long, 1,000 feet 
wide, and 50 feet deep at mean low water through shoal at mouth 
5-2

NORFOLK, VA DISTRICT 
of Chesapeake Bay opposite Cape Henry. Under ordinary conditions 
mean range of tide 2.5 feet and extreme 3 feet. Extremes of 
irregular fluctuation due to combined effect of wind and tides, 
referred to mean low water, are minus 2 feet and plus 9.5 feet. (See 
Table 5-B for Authorizing Legislation.) 
3B. RAPPAHANNOCK SHOAL 
CHANNEL, VA 
Location. In lower Chesapeake Bay opposite mouth of RappahannockRiver 
and about 50 miles northerly from Atlantic Ocean 
at entrance of Chesapeake Bay. (See National Ocean Service Chart 
No. 12225.) 
Existing project. A channel about 9.9 miles long, 1,000 feet 
wide, and 50 feet deep at mean low water between contours of that 
depth in Chesapeake Bay, opposite Rappahannock River. Under 
ordinary conditions mean tidal range is 2.5 feet and extreme 3 feet. 
Extremes of irregular fluctuation due to combined effect of wind 
and tides, referred to mean low water, are minus 2 feet and plus 9.5 
feet. (See Table 5-B for Authorizing Legislation.) 
3C. YORK SPIT CHANNEL, VA 
Location. In lower Chesapeake Bay opposite mouth of York 
River and about 20 miles northerly from Atlantic Ocean at entrance 
of Chesapeake Bay. (See National Ocean Service Chart No. 
12221.) 
Existing project. A channel about 18.2 miles long, 1,000 feet 
wide, and 50 feet deep at mean low water between contours of that 
depth in Chesapeake Bay opposite York Spit. Under ordinary 
conditions mean tidal range is 2.5 feet and extreme 3 feet. Extremes 
of irregular fluctuation, due to combined effect of wind and tides, 
referred to mean low water, are minus 2 feet and plus 9.5 feet. For 
details of previous projects see Annual Report for 1932. (See Table 
5-B for Authorizing Legislation.) 
Terminal facilities. These three channels form the access 
between lower and upper Chesapeake Bay. 
Operations during fiscal year. A dredging contract on York 
Spit Channel began May 14, 1988 and was completed March 18, 
1989. A total 4,657,882 cubic yards of material were removed of 
which all were new work. A dredging contract on Cape Henry 
Channel began April 5, 1989 and was completed November 5, 
1989. A total 2,977,772 cubic yards of credited material were 
removed of which 2,911,735 were new work and 66,037 were 
maintenance. Other operations performed included condition 
studies, engineering and design and supervision and inspections. 
4. CAPE CHARLES CITY 
HARBOR, VA 
Location. Town of Cape Charles, VA is on Chesapeake Bay 
on west side of peninsula separating the bay from Atlantic Ocean. 
It is about 11 miles north of the southern extremity of the peninsula 
and 45 miles south of Maryland-Virginia State line. Cape Charles 
City Harbor is an artificial land-locked harbor on the south side of 
the town. (See National Ocean Service Chart 12222.) 
Existing project. A channel 18 feet deep and 500 feet wide 
from that depth in Chesapeake Bay through Cherrystone Bar and 
inlet to the entrance to Cape Charles City Harbor, a distance of 2.71 
miles; a basin in the harbor of the same depth 400 to 800 feet wide 
and 3,000 feet long; a channel 10 feet deep, 100 to 180 feet wide 
and 260 feet long connecting a basin of same depth 180 feet wide 
and 420 feet long at head of Mud Creek, and a harbor of refuge on 
the north side of Mud Creek, 7 feet deep, 200 to 250 feet wide, and 
375 feet long connected to Mud Creek with an entrance channel 7 
feet deep and 60 feet wide. Project also provides for protective 
works in form of a stone jetty on north side of harbor entrance and 
sand mole 1,350 feet long south of harbor entrance. All depths are 
referred to mean low water. Mean tidal range is 2.3 feet with 
extremes of 2.5 feet below and 8 feet above mean low water. Cost 
for new work for completed project was $628,644, including 
$6,000 from contributed funds. Widening the basin an additional 
200 feet is considered inactive and excluded from foregoing cost. 
Estimated cost of this portion (1954) is $207,000. 
Local cooperation. Items of local cooperation in connection 
with Harbor of refuge have been complied with. 
Terminal facilities. The Pennsylvania Railroad owns a 
wooden pier 200 feet long and two transfer ships in the outer 
harbor. On the south side of the harbor, Bay Shore Concrete owns 
an 800-foot bulkhead. A bulkhead providing 200 feet of berthing 
space is on the south side of the main harbor and is owned by a fish 
plant. There are about 1400 feet of city-owned bulkhead open to 
the public. The Coast Guard owns a 100-foot pier on Mud Creek. 
The harbor of refuge should accommodate about 50 boats when 
berthing facilities are completed. 
Operations during fiscal year. Maintenance: A modification 
was completed to the dredging contract on the entrance channel, 
turning basin, and Mud Creek. Other operations performed included 
condition studies, engineering and design and supervision 
and inspections. 
5. CHINCOTEAGUE INLET, VA 
Location. Chincoteague Inlet at the southern end of Assateague 
Island provides access to the Atlantic Ocean from the 
inland waterway near the town of Chincoteague, VA. (See National 
Ocean Service Chart 12211.) 
Existing project. Provides for a channel 12 feet deep and 150 
feet wide across the ocean bar in the Atlantic Ocean and to the 
mouth of the inlet, a channel 9 feet deep and 100 feet wide from 
the inlet through the canal and then along Chincoteague Channel 
to a point approximately 2,000 feet north of the state highway 
bridge to Chincoteague, a distance of about 6.6 miles. Mean range 
of tide is about 3 feet. All depths are referred to mean low water. 
(See Table 5-B for Authorizing Legislation.) 
Local cooperation. For details see Annual Report for 1974. 
Terminal facilities. Existing facilities at Chincoteague are 
considered adequate for current and prospective traffic. 
Operations during fiscal year. Maintenance: A dredging 
contract of the entrance channel began on November 26, 1989 and 
was completed December 14, 1989. A total 121,184 cubic yards 
of credited material were removed under this contract. Other 
operations performed included condition studies, engineering and 
design and supervision and inspections. 
5-3

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
6. DEEP CREEK, NEWPORT 
NEWS, VA 
Location. Deep Creek is a tidal estuary of the James River, 
lying wholly in the city of Newport News, Va. It is about 3 miles 
in length, flows in a southeasterly direction, and empties into the 
James River on its northerly side about 10.5 miles upstream from 
the mouth of the James River. (See U.S. Coast and Geodetic 
Survey Chart No. 12222.) 
Previous projects. For details, see page 360 of Annual Report 
for 1962. 
Existing project. This provides for an approach channel 8 
feet deep at mean low water and 100 feet wide extending from the 
8-foot depth contour in James River to a point where the natural 
creek entrance to Deep Creek is constricted, a distance of 9,040 
feet: thence 8-feet deep and 60 feet wide through the constricted 
entrance, a distance of 700 feet: the enlargement of the harbor in 
Deep Creek opposite Menchville, extending upstream to a point 
near Parkers Landing and to the foot of Maxwells Lane, form 6.4 
acres to about 20 acres with depth of 8 feet, 400 to 740 feet wide 
and 1,940 feet long, and a harbor 300 feet wide by 600 feet long to 
a depth of 6 feet upstream of the existing harbor. 
Under ordinary conditions the mean tidal range is 3 feet. The 
extremes of irregular fluctuations referred to mean low water due 
to the combined effect of wind and tides are minus 2 feet and plus 
9.8 feet. 
Local cooperation. (a) Fully complied with for initial construction 
under Section 122 of the 1976 Water Resources Development 
Act. The Secretary of the Army, acting through the Chief of 
Engineers, is authorized and directed to review the requirement of 
local cooperation with respect to providing a spoil disposal area for 
the project at Deep Creek, Warwick County (now within the city 
of Newport News), Virginia authorized by the Act of August 26, 
1937 (commonly referred to as the River and Harbor Act of 1937, 
50 Stat. 846), to determine if (1) such requirement should be 
eliminated, and (2) Craney Island disposal area should be used as 
the spoil disposal area for dredged material from such project. 
(b) Beginning on the date of enactment of this section. (1) the 
requirement of local cooperation described in subsection (a) shall 
be suspended, and (2) Craney Island disposal area shall be used as 
the spoil disposal area for dredged material from such project until 
Congress, by a statute enacted after the date on which the report 
required by subsection (a) is submitted, removes such suspension. 
Terminal facilities. There are four privately owned piers and 
one public county pier and bulkhead of wooden construction at 
Menchville. One pier is used for pleasure craft only. The 
remainder are commercial. There is also a shore landing for the 
receipt of sand and gravel, several privately owned wooden piers 
and two marinas are on the south side of the harbor. The wharves 
have no rail connections, but are served by State highways. The 
existing facilities are considered adequate for present commerce. 
Operations and results during fiscal year. Maintenance 
engineering and design and supervision and administration costs 
amounted to $26,297. 
7. GREENVALE CREEK, VA 
Location. A tidal estuary that enters the north side of Rappahannock 
River about 20 miles above its mouth. It is wholly in 
Lancaster County, Virginia about 60 miles north of Norfolk, Virginia. 
(See National Ocean Survey Chart No. 12237.) 
Existing project. A channel 6 feet deep at mean low water 
and 60 feet wide from that depth in Rappahannock River about 950 
feet to the mouth of Greenvale Creek, then 6 feet deep and 60 feet 
wide from the mouth into the creek for about 2,400 feet. 
Local cooperation. Fully complied with. For details see 
Annual Report for 1965. 
Terminal facilities. Existing facilities are considered adequate. 
For details see page 215 of Annual Report for 1969. 
Operations during fiscal year. Maintenance engineering 
and design and supervision and administration costs amounted to 
$79,932. 
8. HAMPTON CREEK, VA 
Location. A tidal estuary of Hampton Roads within the city 
of Hampton, Va. It is about 3 miles long, flows southerly and 
empties into Hampton Roads about 1.5 miles west of Fort Monroe. 
(See Coast and Geodetic Survey charts 400 and 1222.) 
Previous projects. For details, see Annual Report for 1938. 
Existing project. Provides for a channel 12 feet deep from 
vicinity of Old Point Comfort across Hampton Flats and up the 
creek to Hampton Highway Bridge at Queen Street about 2.8 miles, 
with a width of 200 feet in outer portion of channel and 150 feet in 
the creek, suitably widened at the bends; a channel in Herberts 
Creek 180 feet wide and 12 feet deep, extending from the channel 
in Hampton Creek upstream to Kecoughtan Road about 0.6 mile. 
Under ordinary conditions, the mean tidal range is 2.6 feet. 
Local cooperation. The conditions imposed by the River and 
Harbor Acts of August 30, 1935, and March 2, 1945, pertaining to 
the initial construction, have been fully complied with. The River 
and Harbor Act of October 27, 1965 deleted requirement for 
providing spoil disposal areas for maintenance. Local interests 
have contributed toward disposal costs for material deposited in 
Craney Island Disposal Area. 
Terminal facilities. Terminal facilities are adequate for existing 
commerce. (For details see page 319 of Annual Report for 
1967.) 
Operations and results during fiscal year. Maintenance 
engineering and design and supervision and administration costs 
amounted to $93,122. 
9. HAMPTON ROADS, VIRGINIA 
COLLECTION AND 
REMOVAL OF DRIFT 
Location. Hampton Roads is a natural harbor 300 miles south 
of New York and 180 miles south of Washington, D.C. Its principal 
tributaries are James River, affording a natural deep harbor 
at Newport News, VA; Elizabeth River, with its Southern, Eastern, 
and Western Branches providing harbors for Norfolk and 
Portsmouth, VA; and Hampton Creek, serving the harbor at 
5-4

NORFOLK, VA DISTRICT 
Hampton, VA. (See National Ocean Service Chart Nos. 12248, 
12245 and 12253.) 
Existing project. Collection and removal of drift in Hampton 
Roads and its tributary waters authorizes the Secretary of the Army 
to allot necessary amounts of work from appropriations for maintenance 
and improvement of existing river and harbor works or 
from other available appropriations and that this work shall be 
carried on as a separate and distinct project. It is wholly a work of 
maintenance. The purpose of work is to afford relief from variable 
conditions of obstruction. No advance estimate of the amount of 
work is required. (See Table 5-B for Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Norfolk Harbor, VA and Channel to 
Newport News, VA. 
Operations during fiscal year. Maintenance: Operation of 
the project resulted in collection and disposal of 85,400 cubic feet 
of a variety of floating refuse. Operations were performed using 
government plant and hired labor. 
10. HORN HARBOR, VA 
Location. A tidal estuary 4 miles long in Mathews County, 
VA, entering Chesapeake Bay on its western shore 43 miles northerly 
of Norfolk, VA. (See U.S. Coast and Geodetic Survey Chart 
No. 494.) 
Existing project. Provides for a channel 7 feet deep and 100 
feet wide across entrance bar. Plane of reference is mean low water. 
Mean tidal range is about 2 feet with winds causing additional 
variations of 2 to 3 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 3 wharves, 5 piers, and a 
marine railway within the harbor. Wharves are open to the public. 
Existing facilities are considered adequate. 
Operations and results during fiscal year. Maintenance 
engineering and design and supervision and administration costs 
amounted to $58,169. 
11. JAMES RIVER, VA 
Location. The river is formed by junction of the Cowpasture 
and Jackson Rivers in Botetourt County, VA, flows easterly 340 
miles and empties into Hampton Roads at Newport News, VA. (See 
National Ocean Service Chart Nos. 12248 and 12251.) 
Existing project. A channel 35 feet deep and 300 feet wide 
form the mouth to Richmond Deepwater Terminal, and a channel 
18 feet deep and 200 feet wide from the Deepwater terminal to 
Richmond Lock; amooring basin 35 feet deep, 180 to 220 feet wide 
and 2,100 feet long alongside the channel opposite waterfront at 
Hopewell; enlargement of the turning basin at Richmond Deepwater 
Terminal to 825 feet wide, 2,770 feet long and 35 feet deep; 
a turning basin in Richmond Harbor 200 feet wide, 600 feet long 
and 18 feet deep; and construction of spur and training dikes. Depth 
of channels are referred to mean low water. Total length of channel 
included in the project is 87 miles, which is the navigable section. 
Mean tidal ranges under ordinary conditions for different parts of 
the river are: mouth, 2.6 feet; Jamestown, 2 feet; City Point, 2.6 
feet; and Richmond, 3.2 feet. Spring tide ranges under ordinary 
conditions at the same localities are mouth, 3.1 feet; Jamestown, 
2.4 feet; City Point, 3 feet; Richmond, 3.2 feet. Ordinary fluctuations 
of stage at Richmond, due to floods are 6 to 12 feet above 
mean low water. Extreme fluctuations are 16 to 32 feet. Flood 
heights below Richmond diminish rapidly. The extreme according 
to available information is about 11 feet lower at Dutch gap, 14 
miles below and 17 to 18 feet lower, 20 miles below. The estimated 
(1971) total cost for new work is $71,145,940 including required 
non-Federal cost for conditions of local cooperation imposed by 
the River and Harbor Act of 1930, 1945, and 1950, estimated 
(1939) to be $1,949,700; and by the River and Harbor Act of 1962, 
estimated (1971) to be $2,950,000. For previous projects, see 
Annual Report for 1938. (See Table 5-B for Authorizing Legislation.)
Local cooperation. Fully complied with for conditions imposed 
by River and Harbor Act of 1962. 
Terminal facilities. River commerce at Richmond is handled 
by city-owned terminals, city wharf, Richmond dock, and 16 
privately-owned wharves within or in the immediate vicinity of 
Richmond Harbor. The city's Upper Terminal, located on the north 
bank within the manufacturing section of Richmond, provides for 
750 feet of concrete wharf and 80,000 square feet of warehouse 
and transit shed. The other terminal is located approximately 4 
miles downstream from the Upper Terminal which provides about 
1,250 feet of wharf and 2 concrete warehouses with about 190,000 
square feet of floor space. This deepwater terminal at the head of 
the 25-foot deep improved channel serves oceangoing vessels and 
larger ships engaged in coastwide trading. Below the deepwater 
terminals the improvement is served by 42 wharves. Richmond 
terminals and wharves together with wharves between Richmond 
and the river's mouth are adequate for river's commerce. 
Operations during fiscal year. Maintenance: A dredging 
contract on the shoals above Hopewell began on September 27, 
1988 and was completed November 21, 1988. A total 191,274 
cubic yards of credited material were removed under this contract. 
Other operations performed included condition studies, engineering 
and design and supervision and inspections. 
12. LITTLE MACHIPONGO RIVER, VA 
Location. This river, locally known as Parting Creek, has its 
source in the marsh of Bell Neck, Northampton County Va., flows 
in a southerly and easterly direction about 5 miles, and empties into 
Great Machipongo River, about 12 miles by water from Great 
Machipongo Inlet, and about 28 miles by water from Cape Charles, 
VA. The Great Machipongo Inlet and the Great Machipongo River 
are the waterways connecting with the Atlantic Ocean, and have a 
controlling depth of 16 feet. Willis Wharf, a town with a population 
of about 500, is located on the west bank about 1 mile above 
its junction with the Great Machipongo River. The high-water 
width varies from about 450 feet at the mouth to 350 feet at Willis 
Wharf. (See National Ocean Service Chart No. 1221.) 
Existing project. This project provides for a channel 8 feet 
deep at mean low water and 80 feet wide from the town of Willis 
Wharf to deep water in the river below. The mean range of tide is 
about 0.7 foot below mean low water to about 2 feet above mean 
high water. 
Localcooperation. None required for existing project. However, 
for the turning basin, Northampton County, Virginia, must 
agree to the following items of local cooperation: 
5-5

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
(a) Provide without cost to the United States all lands, easements, 
and rights-of-way required for construction and maintenance. 
(b) Hold and save the United States free from damages that 
may result from construction, operation, and maintenance except 
damages due to the fault or negligence of the United States or its 
contractors. 
(c) Assume full responsibility for all project costs in excess 
of the Federal cost limitation of $2,000,000. 
(d) Accomplish without cost to the United States such alterations 
and relocations that the Chief of Engineers may deem necessary 
with respect to sewer, water supply, drainage, electrical, and 
other utility facilities. 
(e) The county in acquiring lands, easements, rights-of-way, 
and disposal areas for project construction, operation, and maintenance 
will comply with the provisions of the "Uniform Relocation 
Assistance and Real Property Acquisition Policies Act of 
1970," Public Law 91-646 approved January 2, 1971. 
(f) The county will comply with Section 601 of Title VI of the 
Civil Rights Act of 1964 (Public Law 88-352), which states that no 
person shall be excluded from participation in, denied the benefits 
of, or be subjected to discrimination in connection with this project 
on the grounds of race, color, or national origin. 
Terminal facilities. At the town of Willis Wharf, there are 
three wharves with a total wharfage space of about 300 feet, five 
bulkheads with a total wharfage space of about 1,140 feet, and two 
marine railways which will accommodate vessels up to 50 feet in 
length. All facilities are privately owned, being used for packing 
seafoods and servicing fishing vessels. The wharves have no 
railroad connections, but are served by local roads connecting with 
the country and State highway system. The facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. New work dredging a turning 
basin was accomplished at a total cost of$121,819 during the fiscal 
year. 
13. NORFOLK HARBOR AND 
CHANNELS (DEEPENING), VA 
The four projects, Atlantic Ocean Channel, VA; Channel to 
Newport News, VA; Norfolk Harbor, VA; and Thimble Shoal 
Channel, VA, are grouped under the above heading for construction 
purposes only. Estimated Federal cost (1988) for new work for 
all three projects is $97,800,000, exclusive of amounts expended 
for previous projects. Details of each project are given below. 
13A.ATLANTIC OCEAN CHANNEL, VA 
Location. The Atlantic Ocean Channel is located offshore of 
Virginia Beach, VA in the Atlantic Ocean. It extends 
southeastward from a point approximately 3.5 nautical miles offshore 
of Cape Henry to approximately 10 nautical miles offshore 
of Rudee Inlet, Virginia Beach, VA. 
Previous project. None. 
Existing project. A channel 57 feet deep at mean low water, 
1,000 feet wide and approximately 10 miles long between 57-foot 
contours in the mouth of the Chesapeake Bay and the Atlantic 
Ocean. 
Local cooperation: See "Norfolk Harbor" writeup. 
Operations during fiscal year. New Work: Preparation of the 
General Design Memorandum for construction was completed. 
13B. CHANNEL TO 
NEWPORT NEWS, VA 
Location. West of north entrance to Norfolk Harbor Channel, 
connects deep water in James River with Hampton Roads. (See 
National Ocean Service Chart No. 400.) 
Previous project. For details see Annual Report for 1938. 
Existing project. Dredging a channel 55 feet deep at mean 
low water and 800 feet wide from Norfolk Harbor Channel in 
Hampton Roads to Newport News, a distance of about 4.5 miles, 
and two deep-draft anchorage berths opposite Newport News 45 
feet deep over a 1,200-foot swinging radius. Under ordinary conditions 
mean tidal range is 2.7 feet and extremes 2.1 and 3 feet. 
Extremes of irregular fluctuations due to combined wind and tides, 
referred to mean low water, are minus 2 feet and plus 9.5 feet. 
Local cooperation. See "Norfolk Harbor" Writeup. 
Terminal facilities. See Port Series No. 11, (Revised 1971, 
Part II) on Ports of Hampton Roads, prepared by Board of Engineers 
for Rivers and Harbors. 
Operations during fiscal year. New Work: A dredging contract 
to deepen the entire channel to 50 feet was completed December 
2, 1988 with 1,028,286 cubic yards of credited material being 
removed. Other operations performed included quantity surveys 
and supervision and inspection. 
13C. NORFOLK HARBOR 
CHANNELS, VA 
Location. Norfolk, VA is 187 miles south of Baltimore, MDI) 
and 30 miles from entrance to Chesapeake Bay at Cape Charles 
and Cape Henry. Harbor extends 18.3 miles from 40-foot contour 
in Hampton Roads to a point 2,500 feet above Norfolk and Western 
Railway bridge over a Southern Branch of Elizabeth River. (See 
National Ocean Service Chart Nos. 400 and 452.) 
Previous Projects. For details see Annual Report for 1938. 
Existing project. 
HAMPTON ROADS AND ELIZABETH RIVER: A channel 
55 feet deep and 1,500 feet wide from that depth in Hampton Roads 
to a point approximately 6.3 miles upstream from the Hampton 
Roads Bridge-Tunnel; thence 55 feet deep and 800 feet wide to 
Lamberts Point; thence 45 feet deep and 750 feet wide to the 
junctSioOnU oTfH SEouRtNhe rBnR BArNanCcHh :a nd Eastern Branch. A channel 45 feet deep and 450 feet 
wide from the junction with the Eastern Branch to the Norfolk and 
Portsmouth Belt Line Railway Bridge; thence 45 feet deep and 375 
feet wide to the Norfolk and Western Railway Bridge; thence 40 
feet deep and 250 feet to 500 feet wide to the U.S. Routes 460 and 
13 highway bridge; thence 35 feet deep and 250 to 300 feet wide 
to a point 0.8 mile above Interstate 64 high level bridge. Project 
includes an approach and turning basin 45 feet deep opposite the 
Norfolk Naval Shipyard; a turning basin at the mouth of St. Julians 
Creek 40 feet deep, 400 to 600 feet long, and 800 feet wide; a 
turning basin at the mouth of Milldam Creek 40 feet deep and 800 
5-6

NORFOLK, VA DISTRICT 
feet square and a turning basin at the mouth of Mains Creek, the 
upstream end of the project, 35 feet deep and 800 feet square. 
EASTERN BRANCH: A channel 25 feet deep and 500 feet 
wide from the junction of the branches to Norfolk and Western 
Railway Bridge, from the Norfolk and Western Railway Bridge a 
channel 25 feet deep and 200 feet wide to the Campostella Bridge, 
channel 25 feet deep and 200 feet wide to the Norfolk and Western 
Railway Bridge (formerly Virginian), including a turning basin 25 
feet deep and approximately 5.5 acres in size located at the 
upstream end of the project. 
WESTERN BRANCH: A channel 24 feet deep and 300 feet 
wide to a point 0.78 mile from the 40-foot channel, thence 24 feet 
deep and 200 feet wide for a distance of 0.38 mile; thence 18 feet 
deep and 150 feet wide for 0.57 mile to a point 0.34 mile above the 
West Norfolk Bridge. 
SCOTTS CREEK: A channel 12 feet deep at mean low water 
and 100 feet wide from the 40-foot channel for a distance of 0.73 
mile.
ANCHORAGES: Three fixed mooring anchorage facilities 
with a depth of 55 feet, each capable of accommodating two large 
vessels simultaneously; two anchorages opposite Sewells Point, 45 
feet deep over a swing radius of 2,300 feet; anchorage area on the 
west side of the 55-foot channel opposite Lamberts Point aggregating 
173 acres consisting of open space 1,500 feet square and 38 
feet deep, one space 1,500 feet square and 35 feet deep, and one 
space 3,000 feet long, 1,000 feet wide and 20 feet deep; and a 
45-acre anchorage, 12 feet deep, near Pinners Point. 
DISPOSAL AREA: a disposal area of about 2,500 acres 
adjacent to and north of Craney Island, enclosed by stonefaced 
levee of sand; rehandling basin, approach and exit channels connecting 
rehandling basin and Norfolk Harbor 55-foot channel and 
hopper dredge unloading facility. 
Local cooperation. The local sponsor (Commonwealth of 
VA) shall: 
(1) Provide without cost to the United States all lands, easements, 
and rights-of-way necessary for implementation and later 
maintenance of the project and for aids to navigation upon the 
request of the Chief of Engineers; including suitable areas determined 
by the Chief of Engineers to be required in the public interest 
for initial and later disposal of dredged material; 
(2) Accomplish without cost to the United States, all alterations 
and relocations of buildings, transportation facilities, tunnels, 
storm drains, utilities, and other structures and improvements including 
pier modifications made necessary by plan implementation, 
except for altering or replacement costs for obstructive 
railroad and public highway bridges, such costs to be apportioned 
in accordance with the principles of Section 6 of the Bridge 
Alteration Act of June 21, 1940, as amended; 
(3) Provide and maintain without cost to the United States 
depths in berthing areas and local access channels serving the 
terminals; 
(4) Hold and save the United States free from damage due to 
implementation, operation, and maintenance of the project except 
where such damages are due to the fault or negligence of the United 
States or its contractors; 
(5) Prohibit the erection of any structures within a distance to 
be determined by the Chief of Engineers from the bottom edge of 
the proposed 55-foot, 45-foot, and 40-foot channels and turning 
basin; and 
(6) Provide without cost to the United States, all retaining 
dikes, wasteweirs, bulkheads, and embankments, or the costs of 
such retaining works required for the project including all monitoring 
features and stilling basins. 
Terminal facilities. See Port Series No. 11, (revised 1971, 
Part II) on Ports of Hampton Roads, prepared by Board of Engineers 
for Rivers and Harbors. 
Operations during fiscal year. MAINTENANCE: Operation 
and maintenance of the Craney Island portion of the project 
consisted of operation and maintenance of roads, service facilities, 
rental equipment and government plant, engineering and design 
and supervision and inspection. 
13D. THIMBLE SHOAL CHANNEL, VA 
Location. In lower portion of Chesapeake Bay between 
Hampton Roads and the ocean, 20 miles northeast of center of 
Norfolk Harbor, extending southeasterly 13.4 miles from a point 
1-1/4 miles east of Thimble Shoal Lighthouse toward entrance to 
Chesapeake Bay. (See National Ocean Service Chart No. 1222.) 
Previous projects. For details see Annual Report for 1966. 
Existing projects. Provides for dredging a channel 55 feet 
deep at mean low water, 1,000 feet wide and approximately 13.4 
miles long between 55-foot contours in lower Chesapeake Bay. 
Local cooperation. See "Norfolk Harbor" writeup. 
Terminal facilities. Project serves as an entrance channel to 
Hampton Roads. See "Norfolk Harbor," "Newport News Channel, 
VA," etc. 
Operations during fiscal year. New Work and Maintenance: 
Preconstruction engineering and design is complete for deepening 
the channel from 45 to 55 feet. Maintenance dredging was performed 
July 20 through August 19, 1989 with 102,945 cubic yards 
of credited material removed. Other operations performed included 
condition surveys, budgeting and scheduling and engineering 
and design. 
14. RUDEE INLET, VA 
Location. Rudee Inlet is located on the Atlantic Ocean at 
Virginia Beach in an area where boating is a major activity. It 
provides a gateway to a variety of oceanic pursuits varying from 
pleasure cruising to commercial deep sea fishing. 
Existing project. An entrance channel 10-ft deep, 110 to 72-ft 
wide and 1605-ft long; an inner channel 7-ft deep, 72 to 53-ft wide 
and 2,495-ft long including a safety area 7-ft deep, and approximately 
1.9 acres in size and a turning basin 7-ft deep, 175-ft 
wide and 1,570-ft long; a sand trap 18-ft deep and approximately 
3.3 acres in size; and a weir and jetty system at the mouth of the 
inlet.
Local cooperation. The Local Sponsor is the City of Virginia 
Beach.An addendum to the Local Cooperation Agreement with the 
City of Virginia Beach was signed October 2, 1989. 
Operations during fiscal year. New Work: Plans and 
specifications are complete. Dredging was pending local cooperation 
at the end of the fiscal year. 
5-7

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
15. SUPERVISOR OF NORFOLK 
HARBOR (PREVENTION OF 
OBSTRUCTIVE AND INJURIOUS 
DEPOSITS) 
The District Engineer, Norfolk District, was designated Supervisor 
of the harbor of Hampton Roads under the provisions of the 
River and Harbor Act of June 29, 1888 (33 U.S.C. 441-451) as 
amended July 12, 1952. Under this Act, the Supervisor of the 
harbor of Hampton Roads is charged with the mission of preventing 
the deposit of obstructive and injurious materials in the tidal waters 
of the harbors of Norfolk, Portsmouth, Newport News, Hampton 
Roads, and their adjacent and tributary waters, so much of the 
Chesapeake Bay and its tributaries as lies within the State of 
Virginia, and so much of the Atlantic Ocean and its tributaries as 
lies within the jurisdiction of the United States within or to the east 
of the State of Virginia. The River and Harbor Act of March 3, 
1899 (33 U.S.C. 403,407,409) as amended prohibits obstructions 
to navigable waters such as unauthorized structures, unauthorized 
fill, deposit of refuse, and sinking of vessels. Other laws relating 
to the supervision of Norfolk Harbor and its tributary waters are 
the Clean Water Act, the Marine Protection, Research and 
Sanctuaries Act of 1972, the Coastal Zone Management Act of 
1969, the Fish and Wildlife Act of 1956, the Federal Power Act of 
1920, the National Historic Prevention Act of 1966, the Endangered 
Species Act of 1973, the Deepwater Port Act of 1972, the 
Wild and Scenic Rivers Act, and the Land and Water Conservation 
Fund Act. 
Direct supervision of the waters under the jurisdiction of the 
Norfolk District was accomplished by means of two patrol vessels 
performing inspections, removing debris and investigating navigational 
hazards and sunken or abandoned vessels. A derrickboat and 
crane barge performed removal of sunken vessels and navigational 
hazards and supported Federal dredging projects. In addition, 
surveillance of the harbor was performed regarding the Corps' 
regulatory program, using also two small outboard craft, motor 
vehicles from land and occasional chartered aerial reconnaissance. 
This regulatory surveillance involved compliance surveys of permitted 
activities and evaluation of navigational impacts of 
proposed piers and other structures. 
16. WATERWAY ON THE COAST 
OF VIRGINIA 
Location. Between barrier beach along Atlantic Ocean on the 
east and Virginia portion of mainland peninsula on the west. It 
extends for 83.7 miles from south end of Chincoteague Bay 
through a number of creeks, thoroughfares and bays to enter 
Chesapeake Bay in the vicinity of Fisherman Island, just south of 
Cape Charles on the southern tip of the peninsula. (See National 
Ocean Service Chart Nos. 12211, 12210, and 12221.) 
Existing projects. An inland waterway 6 feet deep at mean 
low water and 60 feet wide from Chesapeake Bay to Chincoteague 
Bay, VA. Mean range of tide is about 3 feet. Greater fluctuations 
in water level are caused by high winds and storms. A modification 
of the project approved during 1970 under Section 201 of the Flood 
Control Act of 1965 authorized relocation of portions of the waterway 
and widening of 100 feet. (See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. Complied with except that local interests 
are to furnish spoil disposal areas for future maintenance. 
Terminal facilities. Existing facilities are considered adequate. 
For details see Annual Report for 1969. 
Operations during fiscal year. Maintenance: Dredging was 
accomplished March 26 through May 19, 1989. A total of 282,529 
cubic yards of credited material were removed. 
Other work performed included a long term disposal analysis, 
before and after dredging surveys, condition studies, engineering 
and design and supervision and inspection. 
17. WHITINGS CREEK, VA 
Location. Whitings Creek lies entirely within Middlesex 
County, VA, and is a small tidal estuary 1.5 miles long flowing in 
a westerly direction and entering the right bank of the Rappahannock 
River about 13 miles upstream of its mouth at Chesapeake 
Bay. The creek is 73 miles northerly of Norfolk, VA. (See U.S. 
Coast and Geodetic Survey Chart No. 534.) 
Existing project. Provides for a channel 4 feet deep, 70 feet 
wide and 3,100 feet long from the 4-foot contour in the Rappahannock 
River across the offshore bar into the creek. The plane of 
reference is mean low water. The tidal ranges are: mean, 1.5 feet; 
irregular, 2 feet; and extreme approximately 7.8 feet. 
Local cooperation. Fully complied with. For details see page 
353 of Annual Report for 1962. 
Terminal facilities. There is a public wharf and parking 
facility on the project. In addition there are a number of privatelyowned 
wharves and landings on the creek. These facilities are 
considered adequate. 
Operations and results during fiscal year. Maintenance 
engineering and design and supervision and administration costs 
amounted to $58,169. 
18. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
The District continued work on four studies: Eastern Branch 
of the Elizabeth River, VA; Scotts Creek, VA, Tylers Beach, VA; 
and Bennett Creek, VA. Total expenditures amounted to $62,088. 
19. TANGIER ISLAND 
SHORE PROTECTION 
Location. Tangier Island is a marshy island about 5 miles long 
and 1-1/2 miles wide, approximately 65 miles north of Norfolk, 
VA and 15 miles southwest of Crisfield, MD. Located in Accomack 
County, VA, it is the southernmost of a series of islands 
separating the Chesapeake Bay from Tangier and Pocomoke 
Sounds. 
Existing project. The project will consist of a 5,700-foot long 
stone riprap seawall along the western side of the populated portion 
of the island. The crest elevation of the seawall will be 6 feet above 
low water. The seawall will extend from the Tangier Channel on 
the north to a point south to the airport runway. 
5-8

NORFOLK, VA DISTRICT 
Local cooperation. The local sponsor is the state of Virginia 
acting through the Virginia Port Authority. Requirements are 
described in full on page 5-8 of Annual Report for FY 88. 
Operations during fiscal year. New Work: Construction 
was initiated in February 1989 and was in progress at the end of 
the fiscal year. 
BEACH EROSION CONTROL 
20. VIRGINIA BEACH, VA 
Location. On the Atlantic Seaboard, 22 miles north of Virginia-
North Carolina State line, 3.5 miles south of Cape Henry, and 
19 miles east of Norfolk, VA. (See National Ocean Service Chart 
12207.) 
Existing project. Federal participation in restoration and 
protection of shore of Virginia Beach between Rudee Inlet and 49th 
Street by artificial placement of sand to provide a minimum beach 
width of 100 feet at elevation 7 feet above mean low water, and 
maintenance of such beach by periodic replenishment of losses to 
ensure continuous protection; including construction of a groin 
system to be undertaken at such times as estimated annual charges 
therewith would be less than the annual cost of beach replenishment 
alone. The United States shall participate in the first cost of 
the project to the full extent of its proportionate share of cost as a 
landowner, plus one third total first cost of restoring and protecting 
all publicly-owned sections of the shore. The 1962 modification 
provided that the United States shall further participate in periodic 
beach nourishment of the beach in the amount of one third the cost 
for 25 years from date of commencement of operations in placing 
an initial quantity of nourishment material equal to deficiency in 
the design beach at that time. Section 103 of the 1962 River and 
Harbor Act increased Federal participation to one-half of the cost 
incurred after October 23, 1962. Estimated Federal cost (1987) is 
$5,000,000. Estimated cost to local interests is $5,000,000. Construction 
of the groin system is not included in the above estimate. 
The 1962 estimate for this work was $549,000 Federal cost and 
$531,000 cost to local interests. 
The 1974 modification which provides for structural and nonstructural 
improvements was authorized for construction by the 
Water Resources Development Act of 1986. Structural measures 
will be provided for the 6 mile reach of shoreline between Rudee 
Inlet and 89th Street This will include maintaining the beach at an 
elevation of 5.4 feet and a width of 100 feet and construction of a 
stepped-face concrete seawall just seaward of the existing 
bulkhead from Rudee Inlet to 58th Street, and raising and 
strengthening sand dunes from 58th Street to 89th Streets. The 
estimated cost (1989) of the structural improvements are Federal 
$35,900,000 and non-Federal $19,400,000. 
Local cooperation. Requirements are described in full on 
page 5-11 of Annual Report for FY 81 and for 1962 modification 
and on page 5-11 of FY 87 Annual Report for 1974 modification. 
The city of Virginia Beach has complied with the 1962 requirements. 
Operations during fiscal year. New Work: The project, as 
authorized by the River and Harbor Act of 1962, expired Feb 87. 
Federal participation has been extended from 25 years to 35 years, 
on March 10, 1988 by the Assistant Secretary of the Army for Civil 
Works. 
The 1974 modification project is in the preconstruction engineering 
and design phase. 
FLOOD CONTROL 
21. GATHRIGHT DAM AND 
LAKE MOOMAW, VA 
Location. Gathright Dam is on the Jackson River, a tributary 
of James River at mile 43.4 in Alleghany County. Gathright Dam 
site is in the reach of the Jackson River known as the Gorge, about 
19 miles upstream from Covington, VA At the elevation of the top 
of the conservation pool, the lake extends upstream about 9 miles. 
(See Falling Spring and Mountain Grove, Virginia-West Virginia 
quadrangles of geological survey.) 
Existing project. GathrightDam consists ofa 1,172-footlong, 
rolled-rock-fill dam with an impervious core, with the top at 
elevation 1,684.5; outlet works consisting of a concrete intake 
structure located in the right bank 500 feet upstream from the axis 
of the dam; a 1,075-foot long outlet tunnel through the right 
abutment and a stilling basin; and a 2,450-foot long fixed-crest 
emergency spillway excavated in a low saddle in the divide at 
Fortney Branch about 2.5 miles south of the dam. Discharges 
through the maximum conservation pool elevation 1,582 will be 
provided for water quality control. The reservoir area at elevation 
1,582 will be 2, 530 acres. A total of 302,000 acre-feet of storage 
between elevation 1,582 and the spillway crest (elevation 1,663.5) 
will be reserved for flood control. At the spillway crest the reservoir 
will have an area of 4,540 acres.(See Table 5-B for Authorizing 
Legislation.) 
Local cooperation. None required. 
Operations during fiscal year. Care of service and recreationalfacilities, 
watercontrol management, testing and monitoring, 
supervision and administration and engineering and design. 
22. RICHMOND, VA 
Location. The city of Richmond, the capital of Virginia, is 
located in the Piedmont Plateau and is bordered on the north by 
Henrico County and on the south by Chesterfield County. The 
James River flows directly through Richmond separating its business 
district into two areas, the Shockoe Creek area on the north 
bank and the industrial-commercial complex on the south bank. 
Previous project. None. 
Existing project. The project will provide a system of floodwalls 
and levees on both sides of the river in the downtown area 
which would protect against a flood higher than that which occurred 
in June 1972 which is the maximum flood of recent record. 
The project to be constructed is that generally described in House 
Document 98-178, 98th Congress, 2nd Session with modifications 
recommended by the Assistant Secretary of the Army on February 
21, 1984. The present construction cost of the project is now 
estimated at $99,700,000. 
5-9

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
Local Cooperation. A Local Cooperation Agreement was 
signed with the city of Richmond on June 16, 1986. For details see 
Annual Report for 1986. 
Operations during fiscal year. New Work: Preconstruction 
engineering and design continued. Construction was initiated 
December 1988 and is continuing. Completion is scheduled for 
Sep 1993. 
23. SCOTTSVILLE, VA 
Location. The town of Scottsville, VA is located in Albemarle 
and Fluvanna Counties, on the north bank of the James River, 185 
miles above its mouth. 
Previous project. None. 
Existing project. A combination of earth levee, floodwall and 
pump station in the downtown area. The town encompasses 130 
acres and the 1980 population was 250. It includes small commercial 
establishments and dwellings including many of historical 
value. A relatively large tire manufacturing plant is located adjacent 
to the town in Albemarle County and is the largest employer 
in the area with about 270 employees. 
Local cooperation. Requirements are described in full on 
page 5-11 of FY 85 Annual Report. 
Operations during fiscal year. New Work: Construction, 
initiated in FY 85, was completed November 21, 1988 and turned 
over to the town of Scottsville in December 1988 (by letter). 
24. VIRGINIA BEACH STREAMS 
CANAL NUMBER 2, VA 
Location. The canal number 2 watershed with a drainage area 
of about 37 square miles lies within the city of Virginia Beach. The 
city consists of 255 square miles of primarily low, flat terrain with 
about 75 percent of the area below elevation 15 feet, mean sea level. 
The existing canal, from the Eastern Branch of the Lynnhaven 
River to the North Landing River is about 12 miles long and follows 
a north-south alignment. (See National Ocean Survey Chart No. 
12205.) 
Existing project. The project will provide for channelization 
of an existing canal for a length of 1.1 miles. The canal bottom 
width will range from 45 feet to 80 feet and a depth from -4 feet 
mean sea level to -8 feet mean sea level with a flow capacity great 
enough to carry a 100-year flood. Its construction will require 
dredging 741,000 cubic yards of material. 
Local cooperation. Requirements are described in full on 
page 5-14 of FY 81 Annual Report. 
Operations during fiscal year. New Work: Construction 
initiated in FY 88 is continuing. 
25. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
The District completed work on two studies: James River 
Eagle Rock, VA, and James River Buchanan, VA. The District 
continued work on one study: Scottsville, VA. Total expenditures 
amounted to $270,946. 
26. EMERGENCY FLOOD CONTROL 
ACTIVITIES 
During FY 89, $174,385 was spent on the National Emergency 
Preparedness Program. 
GENERAL INVESTIGATIONS 
27. SURVEYS 
Total cost of surveys during the fiscal year amounted to 
$566,428. Work performed consisted of: Navigation Studies, 
$55,690; Miscellaneous Activities, $40,586; Coordination Studies 
With Other Agencies, $196,000; Supplemental Preauthorization 
Studies, $274,152. 
28. COLLECTION AND STUDY OF 
BASIC DATA 
During the fiscal year, cost of collection and study of Basic 
Data was $154,051 consisting of $47,370 for Management Service 
Unit, $50,036 for Technical Services, and $56,645 on a Hurricane 
Evacuation Study. 
5-10

NORFOLK, VA DISTRICT 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Sect. Project Funding FY 86 FY 87 FY 88 FY 89 To 30 Sep 1989 
In Text 
1. Appomattox River, VA 
(Regular Funds) 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
- 870,341 
- 870,341 
26,053 
26,053 
212,025 1,101,218 
211,957 1,101,150 
2. Atlantic Intracoastal 
Waterway, beween 
Norfolk, VA and 
St. John's River, FL 
(Norfolk District) 
(Regular Funds) 
3. Baltimore Harbor and 
Channels 
(Norfolk District) 
(Regular Funds) 
4. Cape Charles City 
Harbor, VA 
(Regular Funds) 
5. Chincoteague Inlet, VA 
(Regular Funds) 
(Contributed Funds) 
6. Deep Creek, Newport 
News, VA 
(Regular Funds) 
7. Greenvale Creek, VA 
(Regular Funds) 
New Work 
Approp - 
Cost - 
Maint 
Approp 1,964,374 
Cost 1,931,265 
Major Rehab 
Approp- 
Cost - 
Recreation 
Approp - 
Cost - 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
968,902 
967,792 
113,223 
113,222 
- 3,688,3721 
- 3,688,372 
2,699,229 
2,723,252 
2,484,827 2,255,274 52,608,6652 
1,754,396 3,046,911 52,607,846 
- 479,947 
- 479,947 
- 59,871 
- 59,871 
- 8,015,0733 
- 8,015,073 
127,604 
127,518 
558,504 
555,057 
495,612 1,259,327 
184,301 1,570,639 
319,453 10,651,949 
323,236 10,651,089 
- 622,6444 
- 622,644 
34,670 2,396,540 
34,670 2,396,540 
227,000 
227,000 
65,107 1,041,410 
65,508 1,041,409 
408,732 
397,984 
713,341 7,607,997 
723,695 7,607,602 
3,850 
3,850 
288,278 
- 288,278 
13,059 
13,059 
26,297 2,093,557 
26,297 2,093,557 
20,003 
20,003 
5-11

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Sect. Project Funding FY 86 FY 87 FY 88 FY 89 To 30 Sep 1989 
In Text 
8. Hampton Creek, VA 
(Regular Funds) 
(Contributed Funds) 
9. Hampton Roads, VA 
(Collection and 
Removal of Drift) 
10. Horn Harbor, VA 
(Regular Funds) 
11. James River, VA 
(Regular Funds) 
(Contributed Funds) 
12. Little Machipongo 
River, VA 
(Regular Funds) 
(Contributed Funds) 
13. Norfolk Harbor 
and Channels 
(Deepening), VA 
(Regular Funds) 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
37,196 
37,196 
6,014 
6,014 
92,119 
92,009 
321,258 
321,148 
- 186,237 
- 186,237 
304 
304 
93,122 1,210,378 
93,122 1,210,378 
62,969 
62,969 
90,636 
90,636 
185,105 
185,163 
260,000 
257,865 
191,000 
193,135 
88,366 
88,366 
2,311,895 
2,312,981 
63,000 
15,127 
2,424 2,424 
935,997 
1,045,823 
8,063 
1,434 
84,934 243,262 
84,735 243,463 
802,909 
800,216 
10,879 
4,664 
26,083 
26,083 
193,000 3,584,984 
193,000 3,584,984 
58,169 
58,169 
13,987 
13,987 
235,023 
235,023 
7,639,9045 
7,639,904 
900,219 31,162,606 
898,399 31,157,027 
- 413,456 
- 379,792 
120,000 
120,608 
14,843 
14,843 
5,600 
1,211 
2,075,000 
2,042,215 
4,615,000 
2,625,036 
213,500 
211,872 
514,516 
514,516 
5,600 
1,211 
5,796,000 2,207,000 14,784,8096 
5,903,145 3,532,235 14,102,631 
- 143,000 
- 143,000 
143,0006 
143,0006 
5-12

NORFOLK, VA DISTRICT 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Sect. Project Funding FY 86 FY 87 FY 88 FY 89 To 30 Sep 1989 
In Text 
(Contributed Funds) 
13a. Atlantic Ocean 
Channel, VA 
(Regular Funds) 
(Contributed Funds) 
13b. Channel to 
Newport News, VA 
(Regular Funds) 
(Contributed Funds) 
13c. Norfolk Harbor, VA 
(Regular Funds) 
(Contributed Funds) 
13d. Thimble Shoal 
Channel, VA 
(Regular Funds) 
(Contributed Funds) 
14. Rudee Inlet, VA 
(Regular Funds) 
(Contributed Funds) 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
2,945,500 5,650,000 1,594,000 10,189,0006 
2,239,892 5,928,863 2,005,552 10,174,3076 
208,750 
218,413 
316,470 
320,816 
(2,589) 
(2,459) 
1,278,130 
1,214,701 
5,369,398 
4,840,919 
(8,897) 
625 
225,293 
51,948 
178,371 2,238,183 
130,937 2,300,473 
(100) 
(100) 
143,000 
143,000 
309,005 
337,269 
334,020 
1,344,891 
44,748 
44,898 
143,0006 
143,0006 
753,3526 
608,255
06 
06 
3,086,2466 
4,097,117 
231 5,763,639 
331 5,763,639 
54,000 3,335,818 1,424,410 4,814,228 
49,784 3,135,118 1,780,206 4,965,108 
386,827 2,127,386 1,015,121 4,826,6676 
386,484 2,210,361 1,185,908 4,997,454 
3,031,795 
3,259,794 
3,967,562 3,384,391 85,281,4027 
4,094,369 3,633,105 85,276,374 
- 134,500 1,565,962 
- 112,104 1,491,775 
271,650 4,058,699 
288,285 2,106,990 
- 188,611 
- 169,820 
- 2,756,500 
- 2,078,004 
30,000 
29,482 
10,000 
545 
1,205,138 
1,340,363 
799,059 
692,850 
748,220 
1,301,970 
16,000 
23,170 
104,989 1,805,4516 
145,452 1,749,331 
548,854 6,118,5446 
664,167 4,399,805 
1,089,830 13,103,233 
1,214,710 13,103,112 
64,601 3,569,3216 
79,894 3,459,868 
143,000 
143,000 
1,799 
50,000 
6,592 
143,000 
143,000 
251,000 
249,962 
50,000 
6,592 
5-13

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Sect. Project Funding FY 86 FY 87 FY 88 FY 89 To 30 Sep 1989 
In Text 
15. Supervision of the 
Harbor of Hampton 
Roads, VA (Prevention 
of Obstructive and 
Injurious Deposits) 
(Regular Funds) 
16. Waterway on the 
Coast of VA 
(Regular Funds) 
17. Whitings Creek, VA 
(Regular Funds) 
(Contributed Funds) 
18. Navigation Work 
Under Special 
Authorization 
19. Tangier Island 
Shore Protection, VA 
20. Virginia Beach, VA 
(Regular Funds) 
21. Gathright Dam and 
Lake Moomaw, VA 
(Regular Funds) 
22. Richmond, VA 
(Regular Funds) 
(Contributed Funds) 
23. Scottsville, VA 
(Regular Funds) 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
260,225 354,000 
261,036 348,498 
529,000 
515,277 
518,000 6,504,824 
536,031 6,503,630 
850,498 
850,498 
1,048,097 
900,425 
1,027,841 
1,174,569 
718,660 
711,922 
26,196 
26,196 
996,215 13,653,445 
999,506 13,648,245 
58,169 
58,169 
21,630 
21,630 
196,698 
196,698 
500 
500 
130,220 44,800 97,959 62,088 
27,000 2,733,000 2,760,000 
20,662 1,707,235 1,727,897 
1,130,000 
1,158,971 
880,842 
851,948 
1,613,000 
1,602,465 
1,505,000 
1,465,942 
300,000 
298,670 
919,322 
916,775 
1,153,000 
1,055,916 
772,000 
728,838
0 
1,330 
513,000 7,860,195 
157,402 7,387,165 
- 80,970,527 
- 80,970,527 
1,020,000 1,086,000 10,283,164 
987,565 1,159,993 10,267,825 
1,400,000 3,800,000 7,966,182 
1,254,904 3,339,978 7,253,263 
90,012 
- 100,000 
722,029 1,024,288 
40,000 
1,201,415 
90,012
0 
- 3,443,500 
254,947 3,401,908 
5-14

NORFOLK, VA DISTRICT 
TABLE 5-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Sect. Project Funding FY 86 FY 87 FY 88 FY 89 To 30 Sep 1989 
In Text 
(Contributed Funds) New Work 
Approp 32,954 - - - 32,954 
Cost - - - 32,000 32,000 
24. Virginia Beach New Work 
Streams, Canal Approp 408,000 1,200,000 1,739,000 982,000 4,764,000 
Number 2, VA Cost 43,661 28,022 1,973,718 1,537,182 4,002,583 
(Regular Funds) 
(Contributed Funds) New Work 
Approp - - 110,205 205,000 315,205 
Cost - - 103,205 180,158 283,363 
25. Flood Control Work Cost 7,500 67,065 17,796 15,999 
Under Special 
Authorization 
26. Emergency Flood Cost 112,610 132,649 218,347 174,385 
Control Activities 
27. Survey Cost 705,175 452,575 307,349 550,842 
28. Collection and Cost 181,707 119,383 156,603 154,051 
Study of Basic Data 
1 Includes $292,096 for previous projects. 
2 Includes $52,804 for previous projects. 
3 Costs prior to 1942 are included in the project "Baltimore Harbor and Channels, MD (BaltimoreDistrict)." 
Costs listed are for York Spit Channel, VA; Cape Henry Channel, VA and Rappahannock Channel, VA. 
4 Includes $445,291 military funds expended from new work dredging on existing project and $83,041 
expended military funds for construction of a wharf. 
5 Includes $763,000 for previous projects. 
6 Excludes previous projects. See Annual Report for FY 1986. 
7 Includes $72,039 for previous projects. 
5-15

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 3, 1871 
June 13, 1902 
March 3, 1909 
June 25, 1910 
Jan. 21, 1927 
Mar. 2, 1945 
APPOMATTOX RIVER, VA (See Section 1 of Text) 
Channel 12 feet deep at mean high water and 60 feet wide. 
Diversion channel and work incidental thereto. 
Increasing channel to width of 80 feet and maintenance of 
diversion works. 
Channel 80 feet wide and 10 feet deep at mean low water 
between mouth and Petersburg. 
Existing project dimensions. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA AND ST. JOHNS RIVER, FL 
(NORFOLK DISTRICT) (See Section 2 of Text) 
Mar. 3, 1899 Existing project dimensions and original route, waterway 
from Norfolk, VA to sounds of North Carolina 
July 25, 1912 
July 25, 1912 
Mar. 3, 1925 
Original route to Norfolk-Beaufort Inlet section 
Purchase of Albemarle & Chesapeake Co. Canal 
Purchase of Lake Drummond Canal (Dismal Swamp Canal) 
July 3, 1930 Construct a tidal lock at Great Bridge at a cost not to exceed 
$500,000 
June 26, 1934 Operating and care of works of improvement provided for with 
funds from War Department appropriations for rivers and 
harbors 
Mar. 2, 1945 Construct dikes for protection of canal property against 
floodtides 
Annual Report 1874, pt. II p. 54 
H. Doc. 139, 56 Cong., 2d sess. 
and Annual Report 1901, p. 1467 
H. Doc. 952, 60th Cong., 1st sess. 
H. Doc. 215, 69th Cong., 1st sess. 
H. Doc. 223, 76th Cong., 1st sess.(1) 
H. Doc. 317, 54th Cong., 1st sess. 
AR 1896 
H. Doc. 131, 55th Cong., 3rd sess. 
AR 1899 
H. Doc. 391, 62nd Cong., 2nd sess. 
H. Doc. 589, 62nd Cong., 2nd sess. 
Rivers & Harbors Comm. Doc. 
67th Cong., 2nd sess. 
S. Doc. 23, 71st Cong., 1st sess.1 
Not available 
H. Doc. 117, 76th Cong., 1st sess. 
BALTIMORE HARBOR AND CHANNELS (NORFOLK 
DISTRICT) (See Section 3 of Text) 
CAPE HENRY CHANNEL, VA (See Section 3 of Text) 
July 3, 1958 Channel 42 feet deep; 1,000 feet wide 
Dec. 31, 1970 Channel depth increased to 50 feet 
RAPPAHANNOCK SHOAL CHANNEL, VA 
(See Section 3 of Text) 
July 3, 1958 Channel 42 feet deep and 800 feet wide 
Dec. 31, 1970 Channel width increased to 1,000 feet and depth increased 
to 50 feet 
Mar. 3, 1905 
Mar. 4, 1913 
July 3, 1930 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
Sept. 19, 1890 
July 14, 1960 
(Sec. 107) 
YORK SPIT CHANNEL, VA (See Section 3 of Text) 
Channel 35 feet deep, 600 feet wide 
Channel width increased to 1,000 feet 
Channel depth increased to 37 feet 
Channel depth increased to 39 feet 
Channel depth increased to 42 feet 
Channel depth increased to 50 feet 
CAPE CHARLES CITY HARBOR, VA (See Section 4 of Text) 
Dredging a channel through Cherrystone Inlet and bar 
CHINCOTEAGUE INLET, VA (See Section 5 of Text) 
Existing Project 
DEEP CREEK, NEWPORT NEWS, VA (See Section 6 of Text) 
Aug. 26, 1937 Channel 6 feet deep from James River to Hicks Landing with widths of 
80 feet and 50 feet; a turning basin 6 feet deep, 100 feet wide and 105 
feet long; an anchorage basin 6 feet deep and 6.4 acres in area; and a 
timber jetty 800 feet long on the north side of the anchorage. 
Jun. 30, 1948 Existing project dimensions and elimination of timber jetty. 
Jul. 14, 1960 Widening of Federal entrance channel to 100 feet and extend harbor 
upstream 600 feet. 
July 14, 1960 
(Sec. 107) 
GREENVALE CREEK (See Section 7 of Text) 
Existing Project 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report, Sept. 21, 1970 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report, Sept, 21, 1970 
H. Doc. 186, 57th Cong., 2nd sess. 
H. Doc. 190, 62nd Cong., 3rd sess. 
H. Doc. 29, 71st Cong., 1st sess. 
H. Doc. 741, 79th Cong., 2nd sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report Sept. 21, 1970 
Unknown 
Approved in 1972 
H. Doc. 76, 74th Cong., 2d sess. 
H. Doc. 601, 80th Cong., 2d sess. 
Approved in 1979 
Approved in 1965 
5-16

NORFOLK, VA DISTRICT 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
HAMPTON CREEK, VA (See Section 8 of Text) 
Sept. 19, 1980 Channel 9 feet deep, varying from 300 feet wide on bar at mouth Annual Report, 1889, p. 974 
to 200 feet wide at Hampton Highway Bridge. 
Aug. 30, 1935 Channel 12 feet deep and 200 feet wide across Hampton Flats River and Harbors Committee Doc. 
and 12 feet deep and 150 feet wide in Hampton Creek 34, 72d Cong., 1st sess. 
Mar. 2, 1945 Channel in Herberts Creek 80 to 100 feet wide and 12 feet deep H. Doc. 559, 76th Cong., 3d sess. (2) 
from Hampton Creek to Kecoughtan Roads. 
Oct. 27, 1965 Delete requirement for providing spoil-disposal area. H. Doc. 201, 89th Cong., 1st sess. 
HAMPTON ROADS AND HARBORS OF NORFOLK AND 
NEWPORT NEWS, VA COLLECTION AND REMOVAL 
OF DRIFT (See Section 9 of Text) 
May 17, 1950 Collection and removal of floating debris in Hampton Roads and specified in Act 
its tributary waters 
HORN HARBOR (See Section 10 of Text) 
July 3, 1930 Existing project H. Doc. 124, 70th Cong., 1st sess. 
Aug. 30, 1935 Removed requirement for local contribution River & Harbors Comm. 
Doc. 22, 73d Cong., 2nd sess. 
JAMES RIVER, VA (See Section 11 of Text) 
July 5, 1884 Channel 22 feet deep from mouth of Richmond and construct spur 
and training dikes 
June 13, 1902 Extension of improvement to Richmond lock gate 
Mar. 3, 1905 Form a tumrning basin by widening channel at Richmond 
July 3, 1930 Channel 25 feet deep mouth to Richmond Deepwater Terminal 
Aug. 26, 1937 Removal of Trigg cofferdam 
Mar. 2, 1945 Tumrning basin at Richmond Harbor 
May 17, 1950 Maintaining turning basin at Richmond Deepwater Terminal 
Oct. 23, 1962 Channel depth increased to 35 feet to Richmond Deepwater 
Terminal 
UTTLE MACHIPONGO RIVER, VA (See Section 12 of Text) 
July 3, 1930 Existing Project 
NORFOLK HARBOR AND CHANNELS (DEEPENING), VA 
(See Section 13 of Text) 
Oct. 17, 1986 ATLANTIC OCEAN CHANNEL, VA 
(See Section 13A of Text) 
Construct a 60 foot channel 
CHANNEL TO NEWPORT NEWS, VA 
(See Section 13B of Text) 
Oct. 17, 1986 Deepen existing 45-foot channel 
to 55 feet 
NORFOLK HARBOR CHANNEL, VA 
(See Section 13C of Text) 
Hampton Roads and ElIzabeth River 
Mar. 2, 1907 Channel 30 feet deep to Navy Yard 
June 25, 1910 Depth of 35 feet to Navy Yard 
Aug. 8, 1917 Depth of 40 feet and width of 750 feet to mouth of Southern 
Branch 
Sept. 3, 1954 Widen 40-foot channel to 1,500 feet from 40-foot contour in 
Hampton Roads to a point just south of Norfolk 
International Terminal 
Oct. 27, 1965 45 feet deep Ft. Wool to Lambert Point, 800 feet wide Norfolk 
Intemrnational Terminal to Lambert Point 
Oct. 17, 1986 Deepen existing 45 foot channel to 55 feet deep 
SOUTHERN BRANCH 
June 25, 1910 Channel with a depth of 22 and 25 feet 
Aug. 8, 1917 Depth of 40 feet and width of 450 feet from mouth to Belt Line 
RR Bridge 
Mar. 30, 1925 Channel 30 feet deep and 375 feet wide to Virginia RR bridge: 
S. Ex. Doc. 714, 47th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 314, 71st Cong., 2nd sess. 
Rivers & Harbors Comm. Doc. 68 
74th Cong., 1st sess.2 
H. Doc. 738, 77th Cong., 2nd sess. 
H. Doc. 191, 81st Cong., 1st sess. 
H. Doc. 586, 87th Cong., 2nd sess. 
H. Doc. 260, 71st Cong., 2d sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 381, 59th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2nd sess. 
H. Doc. 140, 65th Cong., 1st sess. 
S. Doc. 122, 83rd Cong., 2nd sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 551, 61st Cong., 2nd sess. 
H. Doc. 140, 65th Cong., 1st sess. 
H. Doc. 226, 68th Cong., 1st sess. 
5-17

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
thence 25 feet deep and generally 200 feet wide to Norfolk & 
Western RR bridge 
Aug. 30, 1935 Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to a point 2,500 feet above with a turning basin 500 
feet square 
June 30, 1948 Approach and turning area 40 feet deep and a maximum width 
of 830 feet opposite Norfolk Naval Shipyard: thence a channel 
35 feet deep and 375 and 250 feet wide to a point 1900 feet 
above Norfolk & Western RR bridge and a tumrning basin 35 
feet deep and 600 feet at upstream end 
Oct. 27, 1965 45 feet deep Belt Line bridge to Old Virginia bridge, 35-foot 
deep tumrning basin opposite St. Julians Creek 
Oct. 22, 1976 Extend existing 35-foot project to a channel 35 feet deep and 
250 feet wide upstream 1.5 miles to the Norfolk and 
Portsmouth Belt ULine RR bridge and a turning basin at the 
mouth of Mains Creek 35 feet deep and 800 feet square 
Oct. 17, 1986 Deepen existing 40-foot portions to 45-feet deep 
Deepen portion of the 35-foot, from mile point 15 to Gilmerton Bridge, 
to 40 feet deep 
EASTERN BRANCH 
Mar. 2, 1907 Width of 500 feet and depth of 25 and 22 feet 
Removal of shoals at mouth 
Mar. 3, 1925 Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to Virginia RR bridge 
July 3, 1930 30-foot channel to a point opposite terminal of Imperial 
Tobacco Co. in Berkley 
Mar. 2, 1945 Depth of 25 feet and width of 300 feet from Norfolk & Western 
RR bridge to Campostella bridge 
WESTERN BRANCH 
Mar. 4, 1913 Channel 24 feet deep and 300 & 400 feet wide to West 
Norfolk highway bridge 
July 3, 1930 For 18-foot channel to a point about 3,000 feet above West 
Norfolk highway bridge 
SCOTTS CREEK 
July 3, 1930 Channel 12 feet deep and 100 feet wide to a point 100 feet above 
the Atlantic Coast Line RR bridge 
June 25, 1910 
Aug. 8, 1917 
Sept, 3, 1954 
Oct. 27, 1965 
Oct. 17, 1986 
ANCHORAGES 
30-foot anchorage at Lambert Point 
12-foot anchorage at Pinner Point 
An anchorage 38 feet deep and 1,500 feet square: anchorage 
35 feet deep and 1,500 feet square: and an anchorage 20 
feet deep, 1,000 feet wide and 3,000 feet long 
Two anchorages opposite Sewells Point 45 feet deep with 
1,200-foot swinging radius 
Construct a 55-foot anchorage and increase the radius 
to 1500 feet for an existing 45-foot anchorage 
THIMBLE SHOAL CHANNEL, VA 
(See Section 13D of Text) 
Aug. 8, 1917 A channel 40-feet deep and 750 feet wide 
Sep. 3, 1954 Channel width increased to 1,000 feet with side 
channels on either side 32-feet deep and 450 feet wide 
Oct. 27, 1965 A channel 45 feet deep and 100 feet wide 
Oct. 17, 1986 Deepen existing 45-foot channel to 55-feet 
RUDEE INLET, VA (See Section 14 of Text) 
Oct. 17, 1986 Project Authorized 
June 25, 1910 
Mar. 2, 1945 
Oct. 27, 1965 
WATERWAY ON THE COAST OF VIRGINIA 
(See Section 16 of Text) 
Existing project adopted 
Project modified 
Project widened to 100 feet, partially relocated, and 
H. Doc. 182, 73rd Cong., 2nd sess.2 
H. Doc. 545, 80th Cong., 2nd sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 355, 94th Cong., 2nd sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 373, 59th Cong., 1st sess. 
Specified in act. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 37, 71st Cong., 1st sess.3 
H. Doc. 224, 76th Cong., 1st sess. 
H. Doc. 556, 62nd Cong., 2nd sess. 
H. Doc. 265, 70th Cong., 1st sess. 
H. Doc. 189, 70th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2nd sess. 
H. Doc. 605, 63rd Cong., 2nd sess.1 
S. Doc. 122, 83rd Cong., 2nd sess. 
H. Docs. 187 & 143, 89th Cong., 1st sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 140, 65th Cong., 1st sess. 
H. Doc. 122, 83rd Cong., 2nd sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 957, 60th Cong., 1st sess. 
H. Doc. 268, 76th Cong., 1st sess. 
Approved in 1970 
5-18

NORFOLK, VA DISTRICT 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized 
(Sec. 107) incorporated in Delaware Bay-Chesapeake Bay Waterway 
in Delaware-Maryland-Virginia 
WHITINGS CREEK (See Section 17 of Text) 
Mar. 2., 1945 Existing Project H. Doc 
TANGIER ISLAND SHORE PROTECTION 
(See Section 19 of Text) 
Oct. 17, 1986 Project authorized Unpub 
VIRGINIA BEACH, VA (See Section 20 of Text) 
Sept. 3, 1954 Project authorized H. Doc 
Oct. 23, 1962 Project modified H. Doc 
Mar. 7, 1974 Project modification authorized for Phase I Advanced H. Doc 
Engineering and Design 
Oct. 17, 1986 Project Modified Chief c 
May 2 
GATHRIGHT DAM AND LAKE MOOMAW, VA (See Section 21 of Text) 
July 24, 1946 Project authorized H. Doc 
RICHMOND, VA (See Section 22 of Text) 
Aug. 15, 1985 Existing project H. Doc 
Oct. 17, 1986 Project authorized for construction H. Doc 
SCOTTSVILLE, VA (See Section 23 of Text) 
1948 (Sec. 205) Project approved H. Doc 
VA. BEACH STREAMS, CANAL NO.2, VA BEACH, VA 
(See Section 24 of Text) 
Oct. 27, 1965 Project authorized H. Doc 
(Sec. 201) 
.582, 76th Cong., 3rd sess. 
lished report 
186, 83rd Cong., 1st sess. 
.382, 87th Cong., 2nd sess. 
.365, 92nd Cong., 2nd sess. 
Df Engineers Report, 
2, 1985 
.325, 61st Cong., 2nd sess. 
178, 98th Cong., 2nd sess. 
1013, 99th Cong., 2nd sess. 
. 551, 84th Cong., 1st sess. 
.640, 94th Cong., 2nd sess. 
1Contains latest published map. 
2Included in Emergency Relief Administration Program May 23, 1935. 
3For latest published map, see H. Doc. 1246, 62nd Cong., 3d sess. 
5-19 
Documents

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
TABLE 5-C ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA AND ST. JOHNS RIVER, FLORIDA: 
DATA RELATIVE TO THE COMPLETED LOCKS 
(See Section 1 of Text) 
Dimensions 
Greatest 
Length Depth on 
Width Available Miter Sills Year 
Miles of for Full Character Opened 
From Location Chamber Width Uft Upper Lower of to Cost 
Norfolk, VA feet (feet) (feet) (feet) (feet) Foundation Navigation 
12.4 Albemarle and 75 600 2.7 1 1 Piles in sand 1932 $499,913 
Chesapeake Canal and shells 
(Great Bridge, VA) 
10.7 Dismal Swamp 52 300 12 12 12 Natural earth 1940 $348,879 
Canal (Deep Creek) with cutoff 
walls 
33.1 Dismal Swamp 52 300 12 12 13 Natural earth 1941 $372,556 
Canal with cutoff walls 
(South Mills, NC) 
116 feet at mean low water. 
5-20

NORFOLK, VA DISTRICT 
TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30,1989 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Appomattox River, VA21 1980 $870,341 1,101,150- 
Aberdeen Creek, VA2 1975 109,643 201,364- 
Blackwater River VA 
Active portion" 1975 342,118 151,750 19,300 
Broad Creek, VA2 1986 27,888 605,355 500 
Cape Charles, VA 1984 622,644 2,396,540- 
Carters Creek, VA 
Active portion2 3 1951 28,398 3,277- 
Channel to Newport News, VA 1985 4,097,117 5,763,639 4,965,108 
Channel from Phoebus, VA 
to deepwater in Hampton Roads2 1944 11,500 39,468 1,200 
Channel connecting York River, VA 
Back Creek to Slaights Wharf2 1950 14,855 38,024 2,500 
Chesconessex Creek, VA2 1968 25,516 32,042 
Chincoteague Bay, VA 1984 25,126 376,150- 
Chincoteague Harbor of Refuge, VA 1985 49,396 134,483- 
Chowan River, NC2 1975 107,220 - 5,700 
Cockrells Creek, VA4 1949 - - 
Cranes Creek, VA 1986 6,274 409,072- 
Davis Creek, VA 2 1971 97,612 163,122 4,000 
Deep Creek, Accomack Co., VA 1974 83,000 43,158 
Deep Creek, Newport News, VA2 1980 288,278 2,093,557 
Dymers Creek, VA2 1953 5,582 4,610- 
Finney Creek at Wachapreague, VA 1988 68,656 - 7,763 
Greenvale Creek, VA2 1986 20,003 321,148- 
Hampton Creek, VA 1981 186,237 1,210,378 62,969 
Horn Harbor, VA2 1964 13,987 235,023 
Hoskins Creek, VA2 1977 44,100 668,527 500 
Jackson Creek, VA2 1971 8,500 34,514 
Jarvis Creek, VA4 1979 39,259 -- 
Kings Creek, VA4 1957 5,593 -- 
Lafayette River, VA2 1982 242,047 155,592 188,962 
Little Machipongo River VA 1987 211,872 514,516 1,211 
Little River (Creek) VA 13 1966 168,623 481,972 16,955 
Locklies Creek, VA 1928 11,581 9,560- 
Lynnhaven Inlet, VA 1987 445,354 2,842,591- 
Meherrin River, VA 1987 - 54,764- 
Millford Haven VA2 1950 24,568 32,803- 
Mill Creek, VAA 1937 5,445 4,346- 
Mulberry Creek, VA2 1950 2,393 2,458 
Nandua Creek, VA2 1950 6,988 39,939 
Nansemond River, VA6 1978 167,477 439,225 
Newport News Creek, VA2 1962 135,600 179,981 
Nottoway River, VA2 1986 44,295 8,734 43,000 
Occohannock Creek, VA 
Active portion2 1951 13,859 78,283- 
Onancock River, VA2 5 1963 187,914 466,018- 
Oyster Channel, VA2 1984 119,117 670,184- 
Pagan River, VA2 6 1950 51,425 294,213 
Pamunkey River. VA 
Active portion 1964 31,376 161,183 
Parker Creek, VA 1987 15,530 230,924 
Parrotts Creek, VA2 1957 37,045 45,725 
Portsmouth Harbor, VA Channel to 
Nansemond Ordnance Depot2 1947 165,566 66,162 
Queens Creek 2 1979 26,949 142,004 
Quinby Creek, VA 1987 104,176 1,072,662 
Rappahannock River, VA9 1012 1983 414,633 1,959,306 
Rappahannock River at 
Bowlers Wharf, VA4 1950 - - 
Starlings Creek, VA 1981 66,242 675,430- 
Tangier Channel, VA 1988 116,550 2,886,076- 
Taskinas Creek, VA 1975 7,479- 135- 
Totuskey Creek, VA 1970 167,869 451,032 2,000 
Tylers Beach, VA2 1982 261,201 410,129 
Urbanna Creek, VA2 7 1963 55,724 107,913- 
5-21

Report of the Secretary of the Army on Civil Works Activities For FY 1989 
TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30, 1989 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Whitings Creek, VA 1971 21,630 196,698 500 
Winter Harbor, VA2 1981 171,334 307,279 2,973 
Willoughby Channel, VA2 1953 8,500 41,700- 
Wishart Point Channel, VA2 1975 118,762 102,527 30,625 
York River, VA 
Active portion2 1986 180,904 285,104- 
1Includes $22,500 for previous projects. lncludes $30,000 for new work and $7,000 for maintenance for previous 
2Completed. projects. 
3in addition, $700 for maintenance was expended from contributed funds. SIn addition, $168,091 was expended for rehabilitation. 
4lnactive. 10Includes $197,146 for previous new work projects. 
sIncludes $33,549 for new work and $24,754 for maintenance for 11Includes $15,000 for new work for previous projects. 
Sprevious projects. 
12 lncludes $113,500 for previous maintenance projects. 
Includes $20,671 for new work for previous projects. 3 7 Federal funds expended by the U.S. Navy for new work. In addition, $61,087 was expended for rehabilitation. 
TABLE 5-E OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Full Cost to Sept. 30, 1989 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Anderson Park, VA 1979 $471,474 - $176,671 
Newport News, VA 
Hampton Institute, VA 1976 $156,906 - $175,845 
Saxis Island, VA 1987 $273,600 - $ 3,145 
TABLE 5-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to Sept. 30, 1989 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
Buena Vista, VA 1977 $417,9001 -- 
Newmarket Creek, VA 1970 1,000,000 12,283 $550,097 
Norfolk Floodwall, VA 1973 1,851,933 32,877 516,256 
Richmond Filtration Plant, VA 1985 478,224 - - 
Salem Church Lake, VA 1976 1,896,7161 2-- 
1 Preconstruction planning terminated. 2 Includes $144,785 for previous projects. 
5-22

NORFOLK, VA DISTRICT 
TABLE 5-G RECONNAISSANCE AND CONDITION SURVEYS 
PROJECT NAME MONTH/YEAR TYPE OF SURVEY 
Chincoteague Inlet, Accomack Co., VA 
James River 
City Point Shoal 
Jordan Point - Windmill Point 
Richmond Harbor, Richmond, VA 
Rocklanding Shoal Channel 
Tribell Shoal Channel 
Little Machipongo River, Accomack Co., VA 
Lower Northlanding River, Va. Beach, VA 
Newport News Creek, Newport News, VA 
Norfolk Harbor 
40-FT Channel 
Onancock River, Accomack Co., VA 
North Branch 
Oyster Channel, Northampton Co., VA 
Queens Creek, Mathews Co., VA 
Rappahannock Shoal Channel 
Waterway on the Coast of VA 
Bradford Bay 
Fishermans Inlet 
Magothy Bay Channel 
Metompkin Bay Channel 
York River Entrance Channel 
Jun 89 
Jun 89 
May 89 
May 89 
May 89 
May 89 
Jan 89 
Feb 89 
Jan 89 
Oct 88 
Apr 89 
Mar 89 
Mar 89 
Apr 89 
Feb 89 
Feb 89 
Feb 89 
May 89 
Sep 89 
Jun 89 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Reconnaissance 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
5-23

WILMINGTON, N. C., DISTRICT * 
This district comprises central and eastern North 
Carolina and a portion of south-central Virginia, embraced 
in drainage basins tributary to the Atlantic Ocean from 
the southern boundary of Virginia to the Shallotte River, 
inclusive, with exception of the Meherrin River Basin 
above Murfreesboro, N. C., the Chowan River Basin above 
the confluence of the Nottaway and Blackwater Rivers, 
and the Pasquotank River and its tributaries for navigation 
only. Also included are those portions of the Yadkin- 
Pee-Dee and Catawba River basins within the state of 
N. C. as well as a portion of the Atlantic Intracoastal 
Waterway from the northern boundary of North Carolina 
to Little River, S. C., and a portion of the waterway from 
Norfolk, Va., to the Sounds of North Carolina, south of the 
north shore of Albemarle Sound. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control 
(R & HActof 1965)................. ......... 6-2 
2. Atlantic Beach Channels, N. C............... 6-3 
3. Atlantic Intracoastal Waterway 
Between Norfolk, Va. and St. Johns 
River, Fla. (Wilmington District)..............6-3 
4. Beaufort Harbor, N. C................... 6-4 
5. Belhaven Harbor, N. C.................. 6-5 
6. Cape Fear River, N. C. Above Wilmington...... 6-5 
7. Channel from Back Sound to 
Lookout Bight, N. C................... 
8. Far Creek, N. C.................... 
9. Lockwoods Folly River, N. C............. 
10. Manteo (Shallowbag) Bay, N. C............ 
11. Morehead City Harbor, N. C............... 
12. Ocracoke Inlet, N. C................... . 
13. Pamlico and Tar Rivers, N. C............. 
14. Roanoke River, N. C.................... 
15. Silver Lake Harbor, N. C................. 
16. Smith's Creek (Pamlico County), N. C....... 
17. Waterway Connecting Pamlico Sound 
and Beaufort Harbor, N. C................ 
18. Wilmington Harbor, N. C................. 
.... 6-6 
S... 6-6 
.... 6-6 
.... 6-7 
.... 6-8 
S... 6-8 
.... 6-8 
.... 6-8 
S... 6-9 
S... 6-9 
... 6-9 
... 6-10 
Flood Control 
19. Cape Fear River Basin, N. C..................6-11 
19A. B. Everett Jordan Dam and Lake, N. C......... 6-11 
19B. Randleman Lake, N. C.... ............ 6-11 
20. Carolina Beach and Vicinity, N. C..............6-12 
21. Dan River, Madison Wastewater 
Treatment Plant, N. C.......................6-12 
22. Leesville, Va., Roanoke River, 
Sec. 32, Demo. Project......................6-13 
23. Neuse River Basin, N. C..................... 6-13 
23A. Falls Lake, N. C.................. .......... 6-13 
24. Stuart, Va....................... ....... 
25. Wrightsville Beach, N. C................... 
26. Yadkin River Basin, N. C. and S. C........... 
26A. W. Kerr Scott Damn and 
Reservoir, N. C....................... 
27. Inspection of Completed 
Flood Control Projects .................... 
28. Flood Control Work Under 
Special Authorization..................... 
Multiple-Purpose Projects, 
Including Power 
29. Roanoke River Basin, Va. and N. C.... 
29A. John H. Kerr Dam and Reservoir, 
Va. and N. C.................. 
29B. Philpott Lake, Va.............. 
30. Scheduling Flood Control 
Reservoir Operations.............. 
Page 
S..6-14 
.. 6-14 
. 6-14 
S.6-14 
.. 6-15 
. 6-15 
......... 6-15 
....... 6-15 
......... 6-16 
......... 6-16 
General Investigations 
31. 
32. 
33. 
Surveys......................... 
Collection and Study of Basic Data ...... 
Preconstruction Engineering and Design. 
Tables 
...... 6-17 
...... 6-17 
...... 6-17 
Page 
Table 6-A Cost and Financial Statement.......... 6-18 
Table 6-B Authorizing Legislation............... 6-22 
Table 6-C Other Authorized 
Navigation Projects.................6-25 
Table 6-D Other Authorized Beach Erosion 
Control Projects....................6-26 
Table 6-E Other Authorized Flood Control 
Projects........................6-27 
6-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Page 
Not Applicable 
Deauthorized Projects................ 6-28 
Reconnaissance and 
Condition Surveys...................6-29 
Table 6-I Navigation Work Under 
Special Authorization....... 
Table 6-J Dams and Reservoirs...... . 
Table 6-K Flood Control Work Under 
Special Authorization....... 
.......... 6-29 
.......... 6-30 
.......... 6-31 
Navigation 
1. AQUATIC PLANT CONTROL (RIVER AND HARBOR 
ACT OF 1965) 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in Wilmington 
District. 
Existing project. The existing project provides for control 
and progressive eradication of water-hyacinth, 
alligatorweed, Eurasian watermilfoil, and other obnoxious 
aquatic plant growths from navigable waters, tributary 
streams, connecting channels, and other allied waters of 
the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of the most effective 
and economic control measures in cooperation with other 
Federal and State agencies in accordance with the report 
of the Chief of Engineers, House Document 251, 89th Congress, 
1st session. The project was authorized by Section 
302, 1965 River and Harbor Act (H.D. 25, 89th Cong., 1st 
sess.). The Act provides that research and planning costs 
shall be borne fully by the United States. 
Local cooperation. Local interests must agree to hold 
the United States free from damages that may occur from 
operations performed in connection with this project, and 
participate to the extent of 50 percent of the cost of the 
program. Recon studies are 100 percent Federal. Requirements 
are being met. 
Operations and results during fiscal year. New work: 
Operations for FY 89 included chemical control of 70 acres 
of alligatorweed and 25 acres of hydrilla, biological control 
on 210 acres of hydrilla, and monitoring of past biological 
control on 175 acres of hydrilla. 
All alligatorweed control in FY 89 was by the application 
of rodeo herbicide. Annual herbicide treatments in 
areas under maintenance control, including the Scuppernong 
Basin (7 acres), Little River Basin (1 acre), New River 
Basin (3 acres), Pasquotank River Basin (12 acres) and 
Mackeys Creek (5 acres) continued in FY 89. Maintenance 
control on about 80% of the project area has been achieved 
on the Alligator River Basin (17 acres treated in FY 89) 
and the Lumber River (18 acres treated in FY 89). Total 
maintenance control of both of these areas is expected by 
FY 90. Sweetwater Creek (a tributary to the Roanoke 
River) continues to be a problem area with significant annual 
reinfestation of the navigation channel by alligatorweed 
from the adjacent swamp. Seven acres of alligatorweed 
were treated in Sweetwater Creek in FY 89. No 
new alligatorweed treatment areas were added to the program 
in FY 89. 
Hydrilla control efforts included both chemical and biological 
control. Twenty-five acres of hydrilla in high use 
areas of Fred Bond Park Lake were treated with Aquathol 
Granular at a rate of 75 lbs./ac. Fred Bond Park Lake was 
previously stocked with triploid grass carp (FY 87) with no 
noticeable effect by the spring of 1989. 
New biological hydrilla control sites which were stocked 
with triploid grass carp in FY 89 include: Crabtree Project 
Lakes (95 acres of hydrilla @ 7-17 fish/surface acre), Lake 
Holt (100 acres of hydrilla @ 33 fish/surface acre), and Big 
Lake at William B. Umstead State Park (15 acres of 
Hydrilla @ 20 fish/surface acre). 
Two lakes which were infested with hydrilla, Lake 
Wheeler (100 acres) and Lake Rogers (75 acres), were 
stocked with triploid grass carp in FY 87 at a rate of 20 fish 
per vegetated acre. Lake Wheeler was also stocked in the 
fall of 1985 (also at a rate of 20 fish per vegetated acre) with 
marginal results. Monitoring of these sites to determine 
the effectiveness of the stocking continued in FY 89. 
Planning included field investigations and the preparation 
of an Environmental Assessment and Finding of No 
Significant Impact for the Inclusion of New Hydrilla Control 
Sites in the North Carolina Aquatic Plant Control Program. 
Several reconnaissance investigations of aquatic 
weed problems in response to requests by others were 
also made in FY 89. Control work was accomplished for a 
Federal cost of $35,496. Planning was accomplished at a 
Federal cost of $40,149. 
Condition at end of fiscal year. Annual alligatorweed 
maintenance control continues to be effective. All sites 
under maintenance control in FY 89 are expected to remain 
under maintenance control and should require only 
spot treatments in FY 90. 
Results from FY 89 maintenance alligatorweed control 
in the Alligator River and Lumber River Basins have been 
excellent and both are expected to be under total 
maintenance control in FY 90. Alligatorweed control in 
Sweetwater Creek resulted in some reduction in infested 
area with the creek channel open for recreational navigation 
throughout the summer and fall; however, reinfestation 
from adjacent swamps is expected. 
The triploid grass carp stocked in Lake Wheeler for 
hydrilla control continued to provide weed control 
throughout the FY 89 recreation season and long-term control 
is expected. Some hydrilla reduction has occurred in 
Lake Rogers; however, control is not occurring as quickly 
as expected. Good hydrilla control in Lake Rogers is not 
expected until FY 91. Grass carp had no noticeable effect 
on hydrilla growth in Fred Bond Park Lake; however, 
chemical control has been excellent in FY 89 and the grass 
carp are expected to provide long-term residual hydrilla 
6-2 
Tables 
Table 6-F 
Table 6-G 
Table 6-H

WILMINGTON, N. C., DISTRICT 
control. Although evidence of grass carp feeding has been 
observed in all of the triploid grass carp stocking sites for 
FY 89, control is not expected until FY 92. 
Investigations of aquatic weed problems, in response to 
requests by county governments and municipalities, may 
result in the addition of new treatment sites and species in 
future years. 
2. ATLANTIC BEACH CHANNELS, N. C. 
Location. In Carteret County, on south side of Bogue 
Sound, 3 miles west of Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Existing project. A channel 6 feet deep and 50 feet 
wide from the Atlantic Intracoastal Waterway in Bogue 
Sound to the marina east of Money Island; and a channel 
6 feet deep and 50 feet wide from the intersection of 
Money Island and Causeway Channel in Bogue Sound to 
the southern end of Causeway Channel. The length of 
channels is 28 miles. Existing project was authorized 
November 23, 1965, under authority of Section 107, 1960 
River and Harbor Act. 
Local cooperation. Local interests must provide lands, 
easements, and rights-of-way for construction and 
future maintenance, and aids to navigation, including 
suitable spoil-disposal areas, and necessary retaining 
dikes, bulkheads, and embankments therefor or the cost 
of such works; hold the United States free from damages; 
provide and maintain adequate public terminal 
and transfer facilities open to all equally in both Money 
Island Channel and Causeway Channel; provide and 
maintain depths in berthing areas and local channels 
commensurate with the depths provided in the related 
project areas; and provide a cash contribution toward 
the first costs of the project, expressed as a percentage 
of the Federal construction costs, of 50 percent for 
Money Island Channel, and 41.5 percent for Causeway 
Channel. Fully complied with. 
Terminal facilities. Numerous wharves and piers exist 
along Causeway Channel, and a marina near Money 
Island has berthing facilities for about 100 boats. Existing 
facilities are not adequate, and additional 
facilities will be provided by local interests. 
Operations and results during period. Maintenance: 
Design for future year pipeline dredging cost $9,419. 
Condition at end of fiscal year. Project completed 
April 1966. 
3. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA. (WILMINGTON DISTRICT) 
Location. The project is located on the east coast of the 
United States, between Norfolk, Va., and St. Johns River, 
Florida. The section within Wilmington District begins at 
the Virginia-North Carolina State line and extends 
generally southerly and southwestwardly to Little River, 
S. C., a total of 308 statute miles. (See Coast and Geodetic 
Survey Charts 830 to 842, inclusive.) 
Previous projects. For details see Annual Reports for 
1915, 1926, 1932, and 1938. 
Existing project. The authorized project provides for a 
waterway, 12 feet deep, with widths varying from 90 feet 
in land cuts to 300 feet in open waters; the construction, 
operation and maintenance of suitable bridges; saltwaterintrusion 
preventive measures in the vicinity of Fairfield, 
N. C.; a channel in Peltier Creek, 6 feet deep and 50 feet 
wide from the Intracoastal Waterway in Bogue Sound to 
and including a basin in Peltier Creek, 6 feet deep, 200 feet 
wide, and 600 feet long; a channel, 6 feet deep and 90 feet 
wide between the Intracoastal Waterway and the gorge in 
Bogue Inlet, then 8 feet deep and 150 feet wide across the 
ocean bar; a channel, 12 feet deep and 90 feet wide to a 
turning basin, 200 feet wide and 350 feet long, at 
Swansboro; a channel, 6 feet deep and 90 feet wide in New 
River Inlet, and a connecting channel of the same dimensions 
to the Intracoastal Waterway near the mouth of New 
River; a channel, 10 feet deep, and 90 feet wide in New 
River, between the Intracoastal Waterway and the 
Seaboard Coastline Railroad bridge at Jacksonville, N. C.; 
a channel through New Topsail Inlet, 8 feet deep and 150 
feet wide and a channel from New Topsail Inlet to the Intracoastal 
Waterway by way of Old Topsail Creek, 7 feet 
deep and 80 feet wide; a channel, 7 feet deep and 80 feet 
wide, in Banks Channel, from New Topsail Inlet, paralleling 
the barrier beach, to the Atlantic Intracoastal Waterway; 
a channel, 14 feet deep and 400 feet wide, across the 
ocean bar at Masonboro Inlet, with suitable jetties at the 
entrance, thence 12 feet deep and 90 feet wide to the channel 
of the Intracoastal Waterway at Wrightsville Beach by 
way of Banks and Motte Channels; a turning basin, 15 feet 
deep, 300 feet wide, and 700 feet long, on the east side of 
Banks Channel near Masonboro Inlet, with three 15-pile 
dolphins therein; a channel, 8 feet deep and 150 feet wide 
across the ocean bar at Carolina Beach Inlet to the Atlantic 
Intracoastal Waterway; a channel, 6 feet deep, 80 feet 
wide, and 8,000 feet long, to and including a turning basin 
of the same depth, 130 feet wide and 180 feet long, at 
Carolina Beach; a yacht basin, 230 feet wide, 450 feet long, 
and 12 feet deep, at the town of Southport, connected to 
the waterway by a suitable channel of the same depth; and 
maintenance of the general navigation features of the 
North Carolina State Ports Authority Small-Boat Harbor 
at Southport, consisting of an entrance channel, 150 feet 
wide and 400 feet long, an eastern harbor-access channel, 
70 feet wide and 430 feet long, a western harbor-access 
channel, 60 feet wide and 185 feet long, to a turning basin, 
180 feet wide and 550 feet long, all to a depth of 6 feet. A 
modification providing for the replacement of five Federally 
owned and operated highway bridges was authorized in 
December 1970. A modification providing for 100 percent 
Federal funding for Walter B. Jones (formerly Wilkerson 
Creek) and Joseph P. Knapp (formerly Coinjock) bridges 
was authorized in October 1976. A modification providing 
for 100 percent Federal funding at Core Creek, Hobucken, 
and Fairfield bridges was authorized in November 1986. 
Estimated Federal cost is $65,800,000 (1989). The tidal lock 
at Snow's Cut was deauthorized September 23, 1986, 
under authority of Sec. 12, PL 93-251. The 12-foot~deep 
channel in Peltier Creek was deauthorized by the Water 
Resources Development Act of 1986. The south jetty at 
6-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Masonboro Inlet has an estimated Federal cost of 
$9,410,000 (1989) and is complete except for the training 
wall. A Section 111 project to mitigate damages caused by 
the north jetty was authorized in October 1980 and was 
completed in April 1981. Length of channels and basins 
total 347.7 miles. Plane of reference is mean low water. 
In the waterway north of Neuse River, variations in 
water surface due to winds seldom exceed 2 feet above or 
below mean stage. Between Beaufort and the Cape Fear 
River, normal tidal range varies from 3.5 feet at the inlets 
to 1 foot at points between. Average range of tide is 4 feet 
on the ocean side of Bogue Inlet and 2.5 feet just inside the 
inlet. At New River, tidal range varies from 3.5 feet at the 
inlet to 1 foot at the head of the marshes and zero at Tar 
Landing, 31 miles above. From Cape Fear River, N. C., to 
Little River, S. C., mean tidal range varies between 4.7 
feet in Cape Fear River and 4 feet at the intermediate inlets, 
and 2 feet at points midway between the inlets. On October 
15, 1954 (Hurricane Hazel), the tide at Holden Beach 
reached an elevation of 17.6 feet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date except 
for the uncompleted modifications. The State of North 
Carolina has agreed to keep the bridges toll free and upon 
completion of each bridge, accept maintenance, replacement, 
and ownership responsibilities thereof. They have 
withdrawn their offer to contribute 25 percent of the first 
cost. The Water Resources Acts of 1976 and 1986 modified 
the terms of local cooperation to delete the non-Federal 
cost-sharing requirement for all five bridges. 
Operations and results during fiscal year. New work: 
Design of Core Creek Bridge was continued at a cost of 
$496,701. Design of Hobucken Bridge was initiated at a 
cost of $53,671. The supplement for the Masonboro Inlet 
South Jetty GDM cost $302. Maintenance: Through Channel 
-During intermittent periods the U.S. debris boat Snell 
conducted clearing and snagging operations and maintained 
dredging ranges and mooring facilities at a cost of 
$72,645. Between October 24, 1988 and January 2, 1989, 
the contract dredge Marion removed 190,435 cubic yards 
from shoals in the Alligator-Pungo landcut at a cost of 
$555,246. Between March 26 and April 26, 1989, the contract 
dredge Hampton Roads removed 149,952 cubic yards 
from shoals in the through channel between Bear and 
Brown inlets at a cost of $313,017. Between January 8 and 
August 6, 1989, the contract dredge Richmond removed 
749,206 cubic yards from shoals in the through channel between 
New River and the S. C. state line at a cost of 
$2,429,161. Costs in connection with prior year pipeline 
dredging was $12,909. Design for FY 90 pipeline dredging 
cost $32,498. Marking of easements along the AIWW cost 
$9,051. Marking easements and investigating encroachments 
in Hyde County cost $84,520. Disposal area 
stabilization at Swansboro and New River cost $30,485. 
Mosquito control in disposal areas cost $44,920. Archeological 
investigations of sounds and inlets cost $2,500. 
Condition and operation studies cost $458,590. Periodic inspection 
of three remaining bridges cost $34,915. Longterm 
environmental dredging and monitoring study cost 
$101,730. Master plan supplement for Snow's Cut cost 
$11,312. Three highway bridges and utilities were 
operated and maintained at a cost of $526,528. Bogue Inlet 
- During intermittent periods the U. S. sidecasting dredge 
Merritt removed 75,502 cubic yards from shoals in Bogue 
Inlet at a cost of $273,347. Condition and operation studies 
cost $27,163. Environmental coordination and investigation 
of disposal site cost $412. A marine archeological 
survey of the inlet cost $446. Carolina Beach Inlet -During 
intermittent periods the U. S. sidecasting dredge Merritt 
removed 44,422 cubic yards from shoals in Carolina Beach 
Inlet at a cost of $110,522. During intermittent periods the 
U. S. hopper dredge Currituck removed 68,665 cubic yards 
from shoals in Carolina Beach Inlet at a cost of $237,140. 
During intermittent periods the U. S. sidecasting dredge 
Fry removed 13,389 cubic yards from shoals in Carolina 
Beach Inlet at a cost of $56,010. Monitoring of Carolina 
Beach Inlet cost $9,239. Marine archeological survey of 
wrecks cost $74. Condition and operation studies cost 
$22,726. Masonboro Inlet - Monitoring at Masonboro Inlet 
cost $14,082. Condition and operation studies cost $4,357. 
New River Inlet - During intermittent periods the U. S. 
debris boat Snell maintained dredge mooring dolphins at a 
cost of $12,000. During intermittent periods the U. S. 
sidecasting dredge Merritt removed 99,736 cubic yards 
from shoals in New River Inlet at a cost of $242,189. During 
intermittent periods the U. S. sidecasting dredge Fry 
removed 105,538 cubic yards from shoals in New River Inlet 
at a cost of $293,039. Condition and operation studies 
cost $34,567. New Topsail Inlet - Cost in connection with 
prior year pipeline dredging in Topsail Creek was $21,379. 
During intermittent periods the U. S. debris boat Snell 
repaired mooring dolphins at a cost of $16,868. During intermittent 
periods the U. S. sidecasting dredge Merritt 
removed 91,098 cubic yards from shoals in New Topsail Inlet 
at a cost of $206,868. During intermittent periods the 
U. S. sidecasting dredge Fry removed 33,068 cubic yards 
from shoals in New Topsail Inlet at a cost of $136,519. Condition 
and operation studies cost $23,597. 
Condition at end of fiscal year. The project was completed 
in September 1983 except for the training wall, three tieup 
dolphins at Masonboro Inlet and the three remaining 
bridges. Joseph P. Knapp Bridge was completed on 
November 13, 1986. Design of Core Creek Bridge was initiated 
in FY 87 and Hobucken in FY 89. Total cost of existing 
project to September 30, 1989 was $136,816,982, of 
which $42,615,329 was for new work including $86,851 in 
contributed funds and $94,201,653 was for maintenance, including 
$667,300 in contributed funds. 
4. BEAUFORT HARBOR, N. C. 
Location. The project is just inside Beaufort Inlet, adjacent 
to Morehead City Harbor. (See Coast and Geodetic 
Survey Chart 420.) 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing project. The authorized project provides for 
stopping erosion at Beaufort Inlet by jetties and sand 
fences at Fort Macon and Shackleford points and other 
shore protection; channels 15 feet deep at mean low water 
and 100 feet wide in Bulkhead and Gallants Channels, ex- 
6-4

WILMINGTON, N. C., DISTRICT 
cept for a depth of 12 feet in the upper 5,000 feet of 
Gallants Channel; a harbor of refuge in Town Creek 12 feet 
deep, 400 feet wide, and 900 feet long connected to 
Gallants Channel by a channel 12 feet deep, 150 feet wide, 
and 1,400 feet long; a basin 12 feet deep, 600 feet wide in 
front of the town of Beaufort except for a channel 15 feet 
deep, 100 feet wide through the basin; a stone bulkhead 
from Town Marsh across Bird Shoal to the west end of 
Carrot Island; a channel 14 feet deep, 70 feet wide, and 
1,900 feet long from Bulkhead Channel to a turning basin 
14 feet deep, 150 feet wide and 300 feet long near the upper 
end of Morgan Creek; and a channel in Taylors Creek 
15 feet deep, 100 feet wide, extending about 2.6 miles 
easterly from about opposite Marsh Street in Beaufort to 
Lennoxville Point at North River, except for an 800-footlong 
section at the east end which is 12 feet deep. Total 
length of channels is 7.3 miles. Average tidal range is 2.5 
feet at Beaufort and 3.5 feet at the inlet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are fifty waterfront facilities 
with a total frontage of 2,000 feet. These facilities are adequate 
for present commerce. 
Operations and results during fiscal year. Maintenance: 
Cost in connection with prior year pipeline dredging was 
$852. Survey cost in connection with cancelled dredging 
contract was $3,060. Between March 29 and June 29, 1989, 
the contract dredge Cherokee removed 30,117 cubic yards 
from shoals in Bulkhead Channel at a cost of $90,047. Condition 
and operation studies cost $7,841. Contributed funds 
of $750 were returned. 
Condition at end of fiscal year. The project was completed 
in October 1965 except for the Morgan Creek 
modification which was completed November 12, 1983. 
(For further details see Annual Report for 1962.) Costs 
under existing project to September 30, 1989, were 
$827,040 for new work, including $34,000 contributed 
funds and $3,778,513 for maintenance, including $326,225 
contributed funds, a total of $4,605,553. 
5. BELHAVEN HARBOR, N. C. 
Location. The town of Belhaven is at the junction of 
Pantego Creek and Pungo River, about 11 miles above the 
mouth of the latter. The harbor consists of the lower 
reaches of Pantego Creek and is about 6,000 feet long. 
Pungo River forms part of the Intracoastal Waterway between 
Norfolk and the St. Johns River. Norfolk is 130 miles 
north of Belhaven and Beaufort 66 miles south. (See Coast 
and Geodetic Survey Chart No. 123.) 
Existing project. This provides for a channel 12 feet 
deep at mean low water and 100 feet wide, extending from 
deep water in Pungo River to a point about 800 feet east of 
the highway bridge, with a turning basin 800 feet long and 
300 feet wide at the upper end; and for the construction of 
timber breakwaters at the mouth of Pantego Creek. Pungo 
River is a nontidal stream with little slope. Variations in 
the water surface, due to winds, seldom exceed 2 feet 
above or below mean stage. The project was authorized by 
River and Harbor Acts of July 3, 1930 and June 20, 1938. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 12 wharves along the 
town waterfront, all of timber construction; one is owned 
by the town and is open to all without charge; four have 
rail connections. The facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Adjustment in cost of timber breakwater repair resulted 
in a decrease of $1,305. 
Condition at end of fiscal year. The project was completed 
in September 1940. 
6. CAPE FEAR RIVER, N. C. 
ABOVE WILMINGTON 
Location. The river is formed by confluence of the Deep 
and Haw Rivers at Moncure, Chatham County, N. C., and 
empties into the Atlantic Ocean at Cape Fear, near the 
southern extremity of the State. (See Coast and Geodetic 
Survey Chart 426.) 
Previous project. For details see Annual Reports for 
1915 and 1938. 
Existing projects. The authorized project provides for a 
channel 25 feet deep and 200 feet wide from Wilmington to 
a turning basin 400 feet wide and 550 feet long at Navassa 
(2.9 miles); a channel 12 feet deep and 140 feet wide from 
Navassa to mileboard 30 at Acme, with five channel 
cutoffs, 12 feet deep and 150 feet wide to eliminate sharp 
bends; a channel 8 feet deep from mileboard 30 to 
Fayetteville by constructing three locks and dams and by 
dredging river shoals; and recreational facilities at the 
locks and dams. Total length of the project channels is 
113.9 miles. The project was authorized by River and 
Harbor Acts of June 25, 1910; June 26, 1934; August 30, 
1935; August 26, 1937; October 27, 1965; and Section 4, 
Flood Control Act of 1944. For further details see Annual 
Reports for 1962 and 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. There are twelve waterfront 
facilities on the river, with a total frontage of 1,190 feet. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
snagged and cleared and maintained the buoy systems at 
the locks at a cost of $197,450. Periodic inspections of locks 
and dams cost $9,849. Emergency electrical repairs at 
three locks and dams cost $21,894. Construction of a metal 
building at lock and dam No. 1 cost $24,349. Repair of 
damage to pile clusters at lock and dam No. 2 cost $6,327. 
Condition and operation studies cost $65,763. Operation 
and maintenance of three locks and dams cost $248,391. 
Condition at end of fiscal year. The project was 
completed in June 1970. Total costs of existing project to 
September 30, 1989, were $18,598,940 of which $3,610,454 
(including $1,226,385 public works) was for new work and 
$14,988,486 for maintenance. 
6-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
7. CHANNEL FROM BACK SOUND TO LOOKOUT 
BIGHT, N. C. 
Location. The project is located on the coast of North 
Carolina, 8 miles east of Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 7 feet deep from Back Sound, 
through Shackleford Banks to Lookout Bight. The project 
was authorized by River and Harbor Acts of August 26, 
1937, and March 2, 1945. For details see Annual Report for 
1959. 
Local cooperation. Fully complied with. 
Terminal facilities. Not required. 
Operations and results during fiscal year. Maintenance: 
Disposal area stabilization and monitoring at Bardens Inlet 
cost $7,067. Improvement of disposal area cost $142,818. 
Condition and operation studies cost $7,048. 
Condition at end of fiscal year. The project was completed 
in May 1965. 
8. FAR CREEK, N.C. 
Location. Flows easterly from Engelhard into Pamlico 
Sound, about 95 miles south of Norfolk, Va. (See Coast and 
Geodetic Survey Chart 1232). 
Existing project. A channel 12 feet deep and 80 to 100 
feet wide from Pamlico Sound to highway bridge at 
Engelhard, with a turning basin 12 feet deep, 200 feet wide 
and 900 feet long at the head. Project was authorized by 
River and Harbor Acts of July 3, 1930, and May 17, 1950. 
For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Project is served by 12 waterfront 
facilities with a total frontage of 2,300 feet, all privately 
owned. Existing facilities are adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Design for future years pipeline dredging cost $6,602. Condition 
and operation studies cost $2,098. 
Condition at end of fiscal year. Project completed June 
1957. 
9. LOCKWOODS FOLLY RIVER, N. C. 
Location. The project is located on the south coast of 
North Carolina about 12 miles west of Cape Fear River. 
(See Coast and Geodetic Survey Chart 1236 and Geological 
Survey Map of North Carolina.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 6 feet deep at low water from 
the ocean to the bridge at Supply 12.5 miles above, to be 
obtained by dredging through oyster rocks and mudflats. 
The completed river portion of the project above the 
waterway was reclassified to the active category in 1971. 
Lunar tidal ranges in Lockwoods Folly River are 4.5 feet 
at the inlet and 2 feet at the head of navigation at Supply. 
The existing project was authorized by the 1890 River and 
Harbor Act. (See Annual Report for 1887, page 1099.) A 
modification to enlarge the channel from 6 to 12 feet deep 
and from 100 to 150 feet wide across the ocean bar for a 
distance of 4,700 feet was approved by the Chief of 
Engineers on June 3, 1980, under Section 107 of the 1960 
River and Harbor Act. During dredging operations it 
became apparent that establishment of the 12-foot project 
would not be possible with currently available equipment. 
Therefore, the Chief of Engineers, on December 20, 1983, 
approved the District's recommendation that further construction 
activity for the Lockwoods Folly Inlet project be 
suspended until suitable equipment becomes available and 
that the project be maintained at an 8-foot project depth in 
the interim. 
Local cooperation. For the new modification local 
interests must: (a) pay, contribute in kind, or repay with 
interest, one-half of the first costs of construction allocated 
to recreational boating; (b) hold and save the United States 
free from damages resulting from changes in groundwater 
levels, saltwater intrusion, or wave action due to the 
construction works, except damages due to the fault or 
negligence of the United States or its contractor; (c) 
provide without cost to the United States all lands, 
easements, and rights-of-way necessary for the 
construction and subsequent maintenance of the project 
and for aids to navigation upon the request of the Chief of 
Engineers and, (d) provide depths in berthing areas 
commensurate with the project depths, and provide 
service facilities. 
Terminal facilities. Thirty-one piers and wharves on the 
Atlantic Intracoastal Waterway at Holden Beach, about 
1.25 miles west of Lockwoods Folly Inlet, with a total 
frontage of about 1,980 feet available. At Dixons Landing, 
about 2 miles upstream of the inlet, there are five wharves 
with a total frontage of 240 feet. Numerous natural 
landings are used for loading and unloading small boats. 
Berthing space in the vicinity of Lockwoods Folly Inlet 
totals about 2,220 feet. Facilities are considered adequate 
for present commerce. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. sidecasting dredge 
Merritt removed 43,610 cubic yards from shoals in 
Lockwoods Folly Inlet at a cost of $91,492. During 
intermittent periods the U. S. sidecasting dredge Fry 
removed 89,145 cubic yards from shoals in Lockwoods 
Folly Inlet at a cost of $229,404. Cost in connection with 
prior year pipeline dredging was $241. General 
archeological investigations cost $1,533. Archeological 
investigations of the Bendigo and new wrecks cost $2,295. 
Condition and operation studies cost $28,421. 
Condition at end of fiscal year. The active portion of the 
project was completed in June 1965 except for the latest 
modification. Work was initiated on the latest modification 
on September 23, 1982, with a depth of 8 feet being 
reached in October 1982. The project will be maintained at 
the 8-foot depth until suitable equipment for deepening to 
12 feet becomes available. 
6-6

WILMINGTON, N. C., DISTRICT 
10. MANTEO (SHALLOWBAG) BAY, N. C. 
Location. The project is located on the northeastern side 
of Roanoke Island, North Carolina. (See Coast and 
Geodetic Survey Chart 1229.) 
Existing project. The authorized project provides for a 
channel 14 feet deep and 400 feet wide from the Atlantic 
Ocean through Oregon Inlet with connecting 12-foot channels, 
100 feet wide, to Pamlico Sound, Manteo, and Wanchese; 
and a channel 6 feet deep and 100 feet wide connecting 
the Manteo-Oregon Inlet Channel with Albemarle 
Sound. Length of channels is 25.4 miles. A newly authorized 
modification provides for stabilization of Oregon Inlet 
with a dual rubble-mound jetty system, including means 
for sand transfer to the downdrift beach; a channel, 20 feet 
deep and 400 feet wide, through the ocean bar at Oregon 
Inlet; a channel, 14 feet deep and 120 feet wide, from the 
gorge in Oregon Inlet to and through Roanoke Sound to 
and including a 15-acre basin of the same depth at Wanchese; 
and a channel 10 feet deep and 100 feet wide from 
the 12-foot-deep channel in Manteo (Shallowbag) Bay 
through Roanoke and Albemarle Sounds to deep water 
near the northern end of Croatan Sound. The 12-foot 
Croatan Sound channel has been deferred due to lack of 
economic justification. The estimated Federal cost for the 
modification is $86,100,000 (1989). The project was 
authorized by River and Harbor Acts of June 25, 1910; October 
17, 1940; May 17, 1950; and December 31, 1970; and 
under Section 107 of the 1960 River and Harbor Act. 
Local cooperation. For the new modification, local interests 
must: (a) provide all lands, easements, and rightsof-
way for construction and subsequent maintenance of the 
project, including suitable areas required for initial and 
subsequent disposal of spoil and also necessary retaining 
dikes, bulkheads, and embankments therefor, or the cost 
of such retaining works; (b) hold and save the United 
States free from damages due to the construction works 
and subsequent maintenance; (c) continue to provide and 
maintain adequate terminal and transfer facilities, open to 
all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (d) provide and maintain necessary 
mooring and berthing facilities in any enlarged basin, open 
to all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (e) provide and maintain depths in 
berthing areas and local access channels serving the terminals 
commensurate with depths provided in the related 
project areas; (f) accomplish such alterations as required in 
sewer, water supply, drainage, electrical powerlines, 
telephone lines, or other utility facilities as well as their 
maintenance; (g) establish a competent and properly constituted 
public body empowered to regulate the use, 
growth, and free development of the harbor facilities, with 
the understanding that said facilities will be open to all on 
equal terms; (h) and establish regulations prohibiting the 
discharge of untreated sewage, garbage, and other 
pollutants in the water of the harbor by the users thereof, 
which regulations shall be in accordance with applicable 
laws or regulations of Federal, State, and local authorities 
responsible for pollution prevention and control; (i) pay 
one-half of the separable and joint costs allocated to 
recreational navigation presently estimated at 
$12,700,000, and bear all costs of operation, maintenance 
and replacement of recreational navigation facilities 
presently estimated at $1,294,000 annually; (j) pay 10 percent 
of the costs allocated to navigation during construction 
presently estimated at $8,200,000; (k) pay an additional 
10 percent of the costs allocated to navigation within a 
period of 30 years following completion of construction offset 
by a credit allowed for the value of lands, easements, 
rights-of-way, relocations (except utility relocations), and 
dredged material disposal areas presently estimated at 
$7,300,000. Reasonable assurances have been received. 
The State of N. C. has constructed the Wanchese Harbor 
portion and was reimbursed under Sec. 215, PL 90483. 
Terminal facilities. The project is served by 33 waterfront 
facilities with a total frontage of 3,320 feet. Additional 
wharves and facilities will be provided with the 
enlarged basin at Wanchese. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
maintained dredging ranges and mooring dolphins at a 
cost of $33,307. During intermittent periods the U. S. 
sidecasting dredge Merritt removed 91,987 cubic yards 
from shoals in Oregon Inlet at a cost of $181,041. Adjustment 
for correction of prior year cost resulted in cost of 
$112,000 for the Merritt. Merritt cost also includes 
$559,000 which should have been charged to the 
Schweizer. During intermittent periods the U. S. 
sidecasting dredge Schweizer removed 870,982 cubic 
yards from shoals in Oregon Inlet at a cost of $1,748,231 including 
the $559,000 that was charged to the Merritt. During 
intermittent periods the U. S. hopper dredge Currituck 
removed 77,638 cubic yards from shoals in Oregon 
Inlet at a cost of $53,976. Cost in connection with prior 
year hopper dredging was $105,104. A claim in connection 
with FY 86 hopper dredging cost $178. Between January 6 
and February 11, May 5-28 and July 9 and August 11, 1989, 
the contract dredges Hampton Roads, Cherokee and 
Marion removed 546,901 cubic yards from shoals in Old 
House Channel and Channel to Wanchese at a cost of 
$1,332,274. Between August 31 and September 30, 1989, 
the contract dredge Hampton Roads removed 110,000 
cubic yards from shoals in the vicinity of Oregon Inlet at a 
cost of $156,099. Between April 3-27, 1989, the contract 
dredges Atchafalaya and Mermentau removed 159,000 
cubic yards from shoals in Oregon Inlet at a cost of 
$556,118. Between January 7 and April 3, 1989, the contract 
dredge A tchafalaya removed 290,000 cubic yards 
from shoals in Oregon Inlet at a cost of $687,056. Cost in 
connection with prior year hopper dredging was $1,884. 
Design for cancelled pipeline dredging contract was 
$4,250. Expansion of disposal islands cost $14,996. Improvements 
to disposal areas cost $230,143. Environmental 
coordination for realignment of intersection from Old 
House Channel to the inlet cost $8,272. Archeological investigations 
cost $3,396. Project monitoring cost $35,549. 
Condition and operation studies cost $181,523. Contributed 
funds of $418,000 were received for depositing of dredge 
material on Pea Island. 
Condition at end of fiscal year. The project is complete 
except for the latest modification. (For further details, see 
Annual Report of 1962.) 
6-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
11. MOREHEAD CITY HARBOR, N. C. 
Location. The project is located on the northern shore of 
Bogue Sound, adjacent to Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Previous project. For details see page 470 of Annual 
Report for 1935. 
Existing project. The authorized project provides for 
deepening of the channel, from the 42-foot-depth contour in 
the Atlantic Ocean through the ocean bar to the gorge in 
Beaufort Inlet, to 42 feet over a bottom width of 450 feet, 
thence to a depth of 40 feet in the east leg of the turning 
basin including the 1,200-foot diameter turning area, with 
widths of 600 feet in the cutoff channel, and 400 feet wide 
to the turning basin and connecting shallow-draft channels. 
Project deepening was completed on August 2, 1978. Jetties 
at Beaufort Inlet were reclassified to the "active" 
category on March 8, 1972. The jetties were deauthorized 
by the Water Resources Development Act of 1986. In 
general the project as it now exists was authorized by the 
1958 River and Harbor Act (S.D. 54, 84th Cong., 1st sess.) 
and the River and Harbor Act of December 31, 1970. For 
further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Twenty-six waterfront facilities 
serve the port, with a total frontage of 1,250 feet. Marine 
terminals provide 5,300 feet of berthing space, with a 
depth alongside of 35 feet, and facilities for transfer of 
cargoes between rail and water carriers. Improvements to 
facilities were completed in 1969. For further details see 
Port Series No. 12, revised 1987, Corps of Engineers. 
Operations and results during fiscal year. Maintenance: 
Between March 29 and June 29, 1989, the contract dredge 
Cherokee removed 269,178 cubic yards from shoals in the 
inner harbor and 46,758 cubic yards from shoals at the 
State Ports at a Federal cost of $568,453 and contributed 
funds cost of $82,762. Between June 20 and August 24, 
1989, the contract dredges Mermentau and A tchafalaya 
removed 539,192 cubic yards from shoals in the ocean bar 
at a cost of $1,016,406. Design for cancelled pipeline dredging 
contract cost $9,180. Cost in connection with prior 
years dredging was $3,616. Monitoring at Morehead City 
Harbor cost $39,397. Ocean dumping monitoring in conjunction 
with EPA cost $11,123. Condition and operation 
studies cost $126,912. 
Condition at end of fiscal year. The existing project is 
complete except for the jetties. (For further details, see 
Annual Report for 1962.) Total cost of the existing project 
to September 30, 1989, was $52,503,694 of which $6,501,569 
was for new work (including $553,477 public works funds) 
and $46,002,125 for maintenance, including $1,256,686 
contributed funds. 
12. OCRACOKE INLET, N. C. 
Location. The inlet connects Pamlico Sound with the 
Atlantic Ocean, about 30 miles southwest of Cape Hatteras 
and 43 miles northeast of Cape Lookout. (See Coast and 
Geodetic Survey Chart No. 1232.) 
Existing project. The authorized project provides for a 
channel across the ocean bar 18 feet deep and 400 feet 
wide. Construction of a jetty extending from Ocracoke 
Island to the Atlantic Ocean was deauthorized by the 
Water Resources Development Act of 1986. The project 
was authorized by the River and Harbor Act of July 14, 
1960. For further details, see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. None required. 
Operations and results during fiscal year. Maintenance: 
Archeological investigation of the inlet cost $695. Condition 
and operation studies cost $8,553. 
Condition at end of fiscal year. Construction was completed 
in August 1971. 
13. PAMLICO AND TAR RIVERS, N. C. 
Location. The two names apply to the same river, 
known as the Tar above and as the Pamlico below 
Washington, N. C. This stream rises in Person County, 
flows southeasterly 180 miles to Washington, thence 38 
miles to Pamlico Sound. (See Coast and Geodetic Survey 
Chart 537.) 
Previous project. For details see page 502 of Annual 
Report for 1938. 
Existing project. A channel 12 feet deep at mean low 
water and 200 feet wide from 12-foot contour in the river 
below Washington to Atlantic Coastline Railroad bridge at 
Washington; thence 12 feet deep and 100 feet wide to a turning 
basin of same depth, 200 feet wide, 300 feet long, in 
Hardee Creek, 1,500 feet above its mouth; thence 6 feet 
deep, 75 feet wide to Greenville; thence 20 inches deep, 60 
feet wide to Tarboro; and thence to clear the natural channel 
to Little Falls. Project was authorized by River and 
Harbor Acts of August 14, 1876; March 3, 1879; August 11, 
1888; March 2, 1907; July 25, 1912; July 3,1930; and August 
26, 1937. For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 54 wharves on the portion 
of this river under improvement, of which 34 are along the 
waterfront at Washington, 19 between Washington and 
the mouth, and only 1 in usable condition above 
Washington. They have a frontage of 3,570 feet. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Between July 22 and 25, 1989, the U. S. debris boat Snell 
snagged and cleared at a cost of $18,100. 
Condition at end of fiscal year. Project is complete. (For 
details see Annual Report for 1962.) 
14. ROANOKE RIVER, N. C. 
Location. Rises in Blue Ridge Mountains, west of 
Roanoke, Va., flows southeasterly about 398 miles, and 
empties into westerly end of Albemarle Sound, N. C. (See 
Coast and Geodetic Survey Chart 1228 and Post Route 
Map of North Carolina.) 
6-8

WILMINGTON, N. C., DISTRICT 
Existing project. A channel 12 feet deep and 150 feet 
wide from Albemarle Sound to 1 mile above Plymouth, 
N. C.; thence a channel 10 feet deep and 100 feet wide to 
Hamilton; and thence a channel 8 feet deep and 80 feet 
wide to Palmyra Landing. Project authorized by River and 
Harbor Acts of March 3, 1871; July 3, 1930; and June 20, 
1938. For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Thirty-two waterfront facilities 
serve the waterway. Facilities appear adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Between April 4 and 17, 1989, the U. S. debris boat Snell 
snagged and cleared at a cost of $22,000. 
Condition at end of fiscal year. Project is complete. 
15. SILVER LAKE HARBOR, N. C. 
Location. The project is located at the southwest end of 
Ocracoke Island, a portion of the Outer Banks on the 
southeast coast of North Carolina, separating Pamlico 
Sound from the Atlantic Ocean. (See Coast and Geodetic 
Survey Chart No. 1232.) 
Existing project. The authorized project provides for 
basin depths of 12 feet in Silver Lake Harbor; an entrance 
channel 12 feet deep and 60 feet wide, from the basin to 
Teaches Hole Channel; a channel, 12 feet deep and 150 feet 
wide, from the entrance channel through Big Foot Slough 
Bar to the 12-foot contour in Pamlico Sound; a channel, 12 
feet deep and 150 feet wide, from the entrance channel 
through Teaches Hole Channel to the gorge in Ocracoke 
Inlet; a channel, 12 feet deep and 150 feet wide, across 
Bluff Shoal; and for rubble-mound training walls on the 
north and south sides of the entrance channel, 300 feet and 
400 feet long, respectively. Mean tidal ranges are 1.9 feet 
in the throat of Ocracoke Inlet and 1 foot at Ocracoke. 
Variations in the water surface of Pamlico Sound are 
generally due to winds and seldom exceed 1 or 2 feet above 
or below mean stage. Severe storms have raised the water 
surface as much as 7 feet above normal water level at 
Ocracoke. (See Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Twelve waterfront facilities serve 
the harbor. These facilities are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Between February 28 and May 3, 1989, the contract 
dredges Enterprise and Marion removed 193,695 cubic 
yards from shoals in Big Foot Slough and Teaches Hole 
Channels at a cost of $658,970. Condition and operation 
studies cost $10,530. 
Condition at end of fiscal year. The project was completed 
July 28, 1970. (For further details see Annual 
Report for 1961.) 
16. SMITHS CREEK (PAMLICO COUNTY), N. C. 
Location. Smiths Creek rises in Pamlico County, flows 
generally southerly, and empties into Neuse River at the 
town of Oriental, 25 miles southeast of New Bern, N. C. It 
is about 5 miles long but navigable for only 2 or 3 miles 
above its mouth. (See U. S. Coast and Geodetic Survey 
Chart No. 538.) 
Existing project. This project provides for a rubblemound 
breakwater starting at a point on the mainland in 
Oriental and extending 800 feet southwesterly; and an entrance 
channel in Smiths Creek, 10 feet deep and 150 feet 
wide, from that depth in Neuse River to and including a 
basin, generally parallel to the breakwater 10 feet deep, 
300 feet wide, and 800 feet long at Oriental. The total 
length of the channel and basin is about 5,000 feet. Variations 
in water level due to winds seldom exceed 2 feet 
above or below mean stage. Observations of 4 years duration 
show that the extreme range of wind tides is 8.3 feet. 
The existing project was authorized by the River and Harbor 
Acts of June 25, 1910, and September 3, 1954. 
Local cooperation. Fully complied with. 
Terminal facitilies. There are 16 wharves in this harbor, 
all of timber construction with pile foundations. They have 
a frontage varying from 6 to 40 feet, the total frontage being 
about 400 feet. None have rail connections. One wharf 
was built by the town and is to be maintained in perpetuity 
as a public wharf. The remaining wharves are all privately 
owned but are generally open to the public when not required 
by their owners. The facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Design for future year dredging cost $2,508. 
Condition at end of fiscal year. The existing project was 
completed in March 1956. 
17. WATERWAY CONNECTING PAMLICO SOUND 
AND BEAUFORT HARBOR, N. C. 
Location. The project is located in Core Sound, west of 
the outer banks of eastern North Carolina. (See Coast and 
Geodetic Survey Charts Nos. 420 and 1233.) 
Existing project. The authorized project provides for a 
through channel to Core Sound 7 feet deep and 75 feet 
wide from Pamlico Sound to Beaufort Harbor; an alternative 
route of the same dimensions through Back Sound 
by way of channels at the east and west ends of Harkers 
Island; a channel 7 feet deep and 70 feet wide from the 
through channel to the local harbor at Cedar Island, including 
the authorized passage and future maintenance of 
a channel through the existing private basin, and an access 
channel 6 feet deep, 50 feet wide and about 400 feet long to 
a basin the same depth, 60 feet by 100 feet; a channel 7 feet 
deep and 75 feet wide from the through channel to Atlantic; 
a channel 7 feet deep and 75 feet wide, with a basin 200 
feet by 500 feet, the same depth, at Sealevel; a channel 5 
feet deep and 75 feet wide, with basin 150 feet by 130 feet, 
the same depth, at Davis; a channel 6 feet deep and 60 feet 
wide with a basin 100 feet by 600 feet, the same depth, at 
Marshallberg; an entrance channel 6 feet deep and 60 feet 
wide, from Back Sound to harbor of refuge 120 feet by 250 
feet, the same depth in Brooks Creek at the west end of 
Harkers Island; and a channel 7 feet deep and 70 feet wide, 
from the existing side channel at Atlantic, N.C., to the 
6-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
mouth of Little Port Brook; thence 7 feet deep and 50 feet 
wide, along the Brook to a basin 600 feet long, 180 feet 
wide, and 7 feet deep, with a breakwater, beginning at a 
point between the mouth of Little Port Brook and White 
Point, running along the channel approximately 2,000 feet. 
Plane of reference is mean low water. The length of the 
authorized channels is about 50.6 miles. (See Table 6-B for 
authorizing legislation.) 
Local cooperation. Fully complied with to date for completed 
portion. 
Terminal facilities. Sixteen small wharves serve the 
waterway. Additional facilities are needed along Core 
Sound. 
Operations and results during fiscal year. Maintenance: 
Between February 28 and May 3, 1989, the contract 
dredges Enterprise and Marion removed 30,753 cubic 
yards from shoals in Wainwright Slough at a cost of 
$269,200. Condition and operation studies cost $597. 
Condition at end of fiscal year. The project was completed 
in September 1972. (For further details, see Annual 
Report for 1961.) 
18. WILMINGTON HARBOR, N. C. 
Location. The project is located on the Cape Fear River, 
on southeast coast of North Carolina, between the Atlantic 
Ocean and Wilmington, North Carolina. (See Coast and 
Geodetic Survey Chart No. 426.) 
Previous projects. For details, see page 1804 of Annual 
Report for 1915 and page 533 of Annual Report for 1938. 
Existing project. The authorized project provides for a 
channel 40 feet deep and 500 feet wide from the Atlantic 
Ocean through the ocean bar and entrance channels to 
Southport, thence 38 feet deep and 400 feet wide to the 
upper end of the anchorage basin (foot of Castle Street) at 
Wilmington, thence 32 feet deep and 400 feet wide, to 
Hilton Bridge over Northeast Cape Fear River; a 38-footdeep 
anchorage basin at Wilmington; a 32-foot-deep 
turning basin opposite the principal terminals; a channel 
12 feet deep and 100 feet wide, about 3 miles long, in Cape 
Fear River; and a channel 25 feet deep and 200 feet wide 
from Hilton Bridge over Northeast Cape Fear River to a 
point 1.66 miles above, including a turning basin of the 
same depth, 700 feet wide and 500 feet long, at a point 1.25 
miles above the bridge. The project was authorized by 
River and Harbor Acts of July 3, 1930; March 2, 1945; May 
17, 1950; October 23, 1962; and March 10, 1964; under 
Section 107 of the 1960 River and Harbor Act. A modification 
to widen the existing anchorage basin by 100 feet 
was authorized on July 13, 1982, under Sec. 5 of the Cong. 
Appro. Act of March 4, 1915. A modification to widen the 
38-foot by 400-foot Fourth East Jetty Channel to 500 feet; 
deepen the 32-foot by 400-foot channel between Castle 
Street and the N. C. 133 bridge to 35 feet; widen the 
32-foot by 1000-foot by 800-foot turning basin just above 
the mouth of the Northeast Cape Fear River by 50 feet on 
the west side and deepen to 35 feet; and environmental 
improvements to include acquiring, by easements or fee 
title, about 2,800 acres of wetlands, river bluffs and 
ecotones and provision for a minimum number of specially 
designed corridors across the wetlands for industrial 
access to the river was authorized by the Water Resources 
Development Act of November 17, 1986 (PL 99-662). The 
estimated Federal cost is $9,180,000 (1989). (For further 
details of authorization, see 1962 Annual Report.) 
Local cooperation. Fully complied with to date except 
for latest modification. In accordance with the cost-sharing 
and financing concepts reflected in the Water Resources 
Development Act of 1986, the non-Federal sponsor must (1) 
provide all lands, easements, rights-of-way, and dredged 
material disposal areas including necessary retaining 
dikes presently estimated at $870,000, and bear all 
operation and maintenance costs for dikes presently 
estimated at $4,000 annually; (2) modify or relocate 
buildings, utilities, roads, bridges (except railroad bridges), 
and other facilities, where necessary in the construction of 
the project, presently estimated at $8,400,000; (3) pay 25 
percent of the costs allocated to deep draft navigation 
during construction presently estimated at $1,730,000 and 
reimburse an additional 10 percent of the costs allocated to 
deep draft navigation within a period of 30 years following 
completion of construction (which is entirely offset by a 
credit allowed for the value of lands, easements, rights-ofway, 
relocations (except utility relocations), and dredged 
material disposal areas); and (4) pay 25 percent of the first 
costs allocated to fish and wildlife enhancement presently 
estimated at $1,270,000, and pay 25 percent of the costs of 
operation, maintenance, and replacement of fish and 
wildlife facilities presently estimated at $14,000 annually. 
Terminal facilities. Forty-three principal wharves, piers, 
and docks at port of Wilmington, with a berthing space of 
about 20,000 linear feet serve the harbor. These facilities 
handle general cargo and petroleum products. (For further 
details, see Port Series No. 12, revised 1987, Corps of 
Engineers.) 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
snagged and moved buoys at a cost of $88,767. Between 
January 17 and 31, 1989, the U. S. hopper dredge 
McFarland removed 235,557 cubic yards from shoals in the 
ocean bar at a cost of $638,453. Between January 3 and 
March 14, 1989, the contract dredge Enterprise removed 
959,982 cubic yards from shoals in the anchorage basin and 
93,046 from shoals at the State Ports at a Federal cost of 
$776,461 and a contributed funds cost of $123,751. Between 
August 10 and September 30, 1989, the contract dredge 
Manhattan Island removed 888,851 cubic yards from 
shoals in the ocean bar at a cost of $1,797,282. Between 
December 9 and 28, 1988 and February 1 and 2, 1989, the 
contract dredge Hampton Roads removed 97,285 cubic 
yards from shoals in the 32-foot project at a cost of 
$222,569. Contributed funds of $7,259 were expended for 
spillway pipe and installation. Cost in connection with 
prior year bucket and barge contract was $3,597. Environmental 
analysis of proposed dredged material 
disposal sites cost $20,259. Ocean dumping monitoring cost 
$8,873. Endangered species study cost $9,628. Sec. 933 
dredge material disposal study for Bald Head Island cost 
$5,685. Condition and operation studies cost $316,777. Contributed 
funds of $100,728 were expended for dike repair 
and construction on Eagle Island. 
6-10

WILMINGTON, N. C., DISTRICT 
Condition at end of fiscal year. The active portion of the 
project was completed October 1982 except for latest 
modification. (For further details, see Annual Report for 
1962.) Total cost of the existing project to September 30, 
1989, was $75,181,778 of which $14,089,612 was for new 
work and $65,212,255 was for maintenance, including 
$4,242,024 contributed funds. 
Flood Control 
19. CAPE FEAR RIVER BASIN, N. C. 
Location. Work covered by this project consists of a 
series of dams and reservoirs on tributaries of the Cape 
Fear River in North Carolina within a radius of 100 miles 
from Raleigh, North Carolina. (See Geological Survey Map 
of North Carolina.) 
Existing project. Public Law 88-253, approved 
December 30, 1963, authorized three principal dams and 
reservoirs and a series of smaller reservoirs on tributaries 
of the Cape Fear River in accordance with the comprehensive 
plans in House Document 508, 87th Congress, 2d 
session. The act also provides that the appropriate 
agencies of the Departments of the Army and Agriculture 
shall conduct joint investigations and surveys and prepare 
a report on the upper tributaries of the Cape Fear River in 
the interest of watershed protection and flood prevention, 
and the conservation, development, utilization, and 
disposal of water. The report was prepared in compliance 
with provisions of Public Law 87-639. The study was 
unfavorable and has been submitted to Congress. No 
further action will be taken. A list of the dams and 
reservoirs included in the comprehensive plan follows. 
(See Table 6-J on Dams and Reservoirs.) Estimates of cost 
as given are based on 1960 price levels, except the ones for 
B. Everett Jordan Dam and Lake and Randleman Lake, 
which were revised in 1989, and Howards Mill Lake in 
1980. These three projects have been authorized for 
construction in accordance with the above authorization. 
Howards Mill Lake was reclassified to the "deferred" 
category in October 1980 due to the current lack of 
economic justification. 
Local cooperation. Requirements are given in the 
individual project reports. 
19A. B. EVERETT JORDAN DAM AND LAKE, N. C. 
Location. The project is located on the Haw River, N. C., 
4.3 miles above its mouth, and 2.5 miles north of Moncure, 
N.C. 
Existing project. The project provides for an earth dam 
1,330 feet long with a maximum height of 112 feet above 
the streambed, an uncontrolled, unpaved chute spillway, 
and a controlled 19-foot diameter outlet structure. Some 
saddle dikes are required beyond the spillway. The 
reservoir has a gross storage capacity of 753,500 acre-feet, 
of which 538,400 acre-feet is for flood control and a 
conservation pool of 215,100 acre-feet for water-quality 
control, water supply, and sedimentation. The reservoir 
will be operated as a unit of a coordinated system for 
control of floods in the Cape Fear River Basin and for 
water supply, water-quality control, and other purposes. 
Estimated cost for new work is $143,500,000 (1989), 
consisting of $85,130,000 for construction, and $58,370,000 
for lands and damages, including highway, railroad, and 
utility relocations. The existing project was authorized by 
Public Law 88-253 approved December 30, 1963 (H.D. 508, 
87th Cong., 2d sess.). 
Local cooperation. Local interests must protect 
downstream channels from encroachments and obstructions 
which would adversely affect operation of the 
project; reimburse the Federal Government for all costs 
allocated to municipal and industrial water supply, 
presently estimated at $3,600,000 and bear all annual costs 
for operation, maintenance, and major replacements 
allocated to municipal and industrial water supply, an 
amount presently estimated at $42,000 annually; and 
contribute toward the cost of the ranger security 
buildings, an amount presently estimated at $100,000. A 
contract between the State of N. C. and the United States 
for water supply storage space was executed by ASA (CW) 
on April 10, 1988. In addition, the State of N. C. has leased 
the project for public park, recreational, fish, wildlife, and 
other natural resource management purposes and the 
estimated cost to the State for O&M under this lease is 
$778,000 annually. 
Operations and results during fiscal year. New work: 
Relocation of Public Service Gasline was initiated at a cost 
of $175,000. Construction of wildlife subimpoundments 
was completed at a cost of $102,887. The N. C. maintenance 
center was completed at a cost of $323,356. Ebenezer 
Church recreation area was completed at a cost of 
$1,267,006. Poplar Point recreation area was continued at a 
cost of $590,695. Crosswinds recreation area was 
continued at a cost of $240,450. Seaforth recreation area 
was completed at a cost of $921,711. Repairs at Crosswinds 
Marina due to slope failure cost $85,427. The State 
administration center was continued at a cost of $558,922. 
Total Federal expenditures were $5,392,728, including the 
above items. Contributed funds of $31,572 were expended 
for the maintenance center security building. Status of 
plans and specs: New Hope Overlook and Robeson Creek, 
15 percent; and Rivers End and Wilderness Island O&M 
roads, 1 percent. Maintenance: Automatic gate control 
system and piezometer reading equipment cost $54,086. 
Sedimentation surveys cost $16,816. Drought management 
plan cost $3,705. Embankment criteria report cost $23,373. 
Periodic inspection report cost $27,093. Archeological 
surveys cost $1,186. Ditch repairs and electric 
modifications to intake tower cost $37,073. Normal 
operation and maintenance cost $814,315. Maintenance 
and operation of dams cost $73,000. 
Condition at end of fiscal year. All facilities are basically 
complete expect for Public Service Gasline, recreation 
facilities, and project operations facilities. Impoundment 
was completed in February 1982 with dedication on May 1, 
1982. Project completion is scheduled for June 1993. 
19B. RANDLEMAN LAKE, N. C. 
Location. The project is located on Deep River, N. C., 
6-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
about 15 miles south of Greensboro and about 2 miles 
upstream from the town of Randleman. The damsite and 
about two-thirds of the reservoir would lie in Randolph 
County. The upper one-third of the reservoir would lie in 
Guilford County. 
Existing project. The authorized project provides for 
construction of an earth dam 2,300 feet long with a maximum 
height of 110 feet above the streambed to create a 
reservoir with gross storage of 108,000 acre-feet, consisting 
of 46,000 acre-feet for flood control and a conservation 
pool of 62,000 acre-feet for water supply, water-quality 
control and sedimentation. Randleman Lake is the second 
project of the comprehensive plan of development for the 
Cape Fear River Basin, providing reservoir storage for 
flood control, water supply, and recreation. Estimated cost 
of new work is $117,000,000 (1989), consisting of 
$57,956,000 for construction and $59,044,000 for lands and 
damages, including relocations. The existing project was 
authorized by the 1968 Flood Control Act (H.D. 343, 90th 
Cong., 2d sess.). 
Local cooperation. Based on the termination of Federal 
interest in the project by the ASA(CW), no local cooperation 
is required. 
Operations and results during fiscal year. New work: 
Project coordination cost $308. 
Condition at end of fiscal year. Preconstruction planning 
was completed in FY 1982. The Piedmont Triad Regional 
Water Authority is building a water supply and possible 
recreation facility at Randleman. All pertinent data that 
may be useful in the construction has been provided. 
20. CAROLINA BEACH AND VICINITY, N. C. 
Location. The project is in New Hanover County, about 
15 miles southeast of Wilmington, N. C., on the peninsula 
which separates lower Cape Fear River from the Atlantic 
Ocean. (See Coast and Geodetic Survey Map 834.) 
Existing project. The authorized project provides for 
construction of a dune with a base generally bordering at 
or near the building line, with a crown width of 25 feet at 
an elevation of 15 feet above mean low water, together 
with integral construction of a beach berm with a crown 
width of 50 feet at elevation 12, extending about 31,800 
feet from the northern limits of Carolina Beach to the 
southern limits of Kure Beach; initial deposition of sufficient 
material north of Carolina Beach to serve as a feeder 
beach; and Federal participation in the cost of beach 
nourishment for a period not to exceed 10 years from the 
year of completion of initial placement. Along the northern 
2,050 feet, the project includes a rock revetment at elevation 
12 fronted by a 130-foot-wide berm at elevation 8. The 
area south of Carolina Beach was reclassified to the active 
category, June 1985. Approved estimated Federal cost for 
new work is $16,400,000 (1989). The project was authorized 
by the 1962 Flood Control Act (H.D. 418, 87th Cong. 2d 
sess.). The Water Resources Development Act of 1986 
authorized Federal participation in future nourishment for 
50 years. This cost has not been included. 
Local cooperation. Local interests must: (a) Provide 
lands, easements, and rights-of-way for construction; 
(b) make required relocations and alterations of streets, 
utilities, or structures; (c) contribute 37.9 percent of the 
total first cost, with credit allowed for (a) and (b); 
(d) hold the United States free from damages; (e) maintain 
all works after completion; (f) maintain continued public 
ownership of the shore; (g) adopt and enforce appropriate 
ordinances to provide for preservation of improvement 
and its protective vegetation; (h) control water pollution to 
extent necessary to safeguard health of bathers; and 
(i) at least annually inform interests affected that project 
will not provide any substantial protection from ocean 
surges higher in elevation than that of Hurricane Hazel, 
October 15, 1954. Requirements have been fulfilled to date 
for the town of Carolina Beach portion of the project only. 
Operations and results during fiscal year. New work: 
An economic reanalysis of the area south of Carolina Beach 
Beach was initiated at a cost of $179,364. Final cost from 
project nourishment in FY 1988 resulted in a decrease in 
Federal cost of $2,600 and an increase in contributed funds 
cost of $3,510. 
Condition at end of fiscal year. Project construction was 
completed August 12, 1982, except for grassing which was 
completed in September 1983. The second increment of 
renourishment was completed in May 1988. 
21. DAN RIVER, MADISON WASTEWATER 
TREATMENT PLANT, N. C. 
Location. The town of Madison is located in northcentral 
North Carolina in Rockingham County about 25 
miles north of Greensboro, N. C. The Madison Wastewater 
Treatment Plant, which is the object of this project, is 
located on the west bank of the Dan River, about 3,500 feet 
upstream from its confluence with the Mayo River. (See 
USGS quadrangle sheet, Mayodan, N. C.) 
Existing project. The project provides for a riprap layer 
placed on a layer of stone fill and extension of an 18-inch 
outfall pipe. The protection extends 500 feet. The project 
was approved by the Chief of Engineers on February 17, 
1988, under Section 14, 1946 Flood Control Act as 
amended. 
Local cooperation. Local interests must provide all 
lands, easements, and rights-of-way, including suitable 
borrow and disposal areas, and all alterations and 
relocations of buildings, transportation facilities, storm 
drains, utilities, and other structures and improvements 
necessary for construction; provide, during the process of 
construction, an amount equal to not less than 25 percent 
of total project costs, at least 5 percent of which will be 
cash with credit to be allowed for the above items; hold 
and save the United States free from damages; maintain 
and operate the project after completion; and assume full 
responsibility for all project costs in excess of the Federal 
cost limitation of $500,000. Fully complied with to date. 
Operations and results during fiscal year. New work: 
Final cost adjustments resulted in a decrease in Federal 
cost of $2,881 and an increase in contributed funds cost of 
$3,908. 
6-12

WILMINGTON, N. C., DISTRICT 
Condition at end of fiscal year. The project was 
completed in August 1988. 
22. LEESVILLE, VA., ROANOKE RIVER, SEC. 32, 
DEMO. PROJECT 
Location. The project is located on the Roanoke (Staunton) 
River in southwest Virginia near the Town of 
Leesville in Campbell and Pittsylvania Counties. (See 
USGS quadrangle sheet, Leesville, Va.) 
Existing project. The project provides for a total of 
about 2,200 linear feet of streambank protection on two 
separate sites along a 3-mile segment of the river between 
Leesville Dam and the town of Leesville. Three methods of 
erosion control were used, they were: stone rubble with 
vegetation, rubber tire mattress and rock windrow. The 
project was funded for construction by the Chief of 
Engineers in February 1978, under Section 32, P.L. 93-251. 
Local cooperation. Fully complied with to date. 
Operations and results during fiscal year. New work: 
Monitoring of Leesville and Little Rockfish Creek cost 
$3,330. 
Condition at end of fiscal year. Construction was 
completed in March 1981. The project is functioning as 
designed. 
23. NEUSE RIVER BASIN, N. C. 
Location. Works covered by this project consist of a 
series of dams and reservoirs in the Neuse River Basin in 
North Carolina within a radius of 50 miles from Raleigh, 
North Carolina. (See Geological Survey Map of North 
Carolina.) 
Existing project. The Flood Control Act of 1965 
authorized construction of the Falls project as the key 
project in the recommended general plan of development 
of the Neuse River Basin. The plan will serve as a guide for 
immediate and future development of the basin's water 
resources as set forth in House Document 175, 89th Congress, 
1st Session. A list of projects included in the general 
plan of development follows. (See Table 6-J on Dams and 
Reservoirs.) Estimated costs as given are based on 1963 
price levels, except for Falls Lake which was revised in 
1989. 
23A. FALLS LAKE, N. C. 
Location. The project is on the Neuse River about 10 
miles north of the city of Raleigh, North Carolina. 
Existing project. The authorized project provides for an 
earth dam 1,915 feet long with a maximum height of 95 
feet above streambed. The dam has a 30-foot top width. An 
uncontrolled chute spillway, 100 feet wide, is located in the 
east abutment. The reservoir has a gross storage capacity 
of 374,450 acre-feet, of which 243,050 acre-feet is for flood 
rnntrnl. 45.000 acre-feet for water supply for the city of 
Raleigh, 61,330 acre-feet for water quality control, and 
25,070 acre-feet for sediment storage. The reservoir will be 
operated as the initial unit of a coordinated system for control 
of floods in the Neuse River Basin for water supply, 
water quality control, recreation, and other purposes. 
Estimated cost of new work is $180,000,000 (1989) consisting 
of $85,858,000 for construction and $94,142,000 for 
lands and damages, including highway, railroad, and utility 
relocations. The project was authorized by the 1965 Flood 
Control Act (H.D. 175, 89th Cong., 1st sess.) 
Local cooperation. Local interests must prevent encroachment 
on downstream channels that would interfere 
with the operation of the reservoir; pay the United States 
in accordance with the Water Supply Act of 1958, as 
amended, the entire amount of construction cost allocated 
to water supply, presently estimated at $13,800,000 and 
entire amount of operation, maintenance, and replacement 
costs allocated to water supply, presently estimated at 
$98,000 annually, the final amounts to be determined after 
actual costs are known; administer project land and water 
areas for recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be through 
user fees), with interest, one-half of the separable cost of 
the project allocated to recreation and one-fourth of the 
separable cost allocated to fish and wildlife enhancement, 
the amount involved currently being estimated at 
$19,800,000, and bear all costs of operation, maintenance, 
and replacement of recreation and fish and wildlife lands 
and facilities, the amount involved currently being 
estimated at $1,340,000 on an average annual basis. Formal 
assurances have been received. The N. C. Department 
of Natural and Economic Resources has been authorized 
by an act of legislation to assure payment of all non- 
Federal costs allocable to water supply in all Federal projects 
as required by law. The State will require repayment 
of water supply costs, by the users. A contract between 
the city of Raleigh and the United States for water-supply 
storage space was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement for cost 
sharing of recreational lands and facilities in accordance 
with P.L. 89-72 was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement in accordance 
with Section 221 of P.L. 91-611 was executed on October 
10, 1972. 
Operations and results during fiscal year. New work: 
Wildlife subimpoundments were continued at a cost of 
$2,359,963. State maintenance center was completed at a 
cost of $1,090,587. Rolling View campground and recreation 
facilities were continued at a cost of $593,362. State 
administration center was continued at a cost of $129,138. 
Rehabilitation of the Mangum House was continued at a 
cost of $202,933. Total Federal expenditures were 
$6,188,558, including the above items. Status of plans and 
specs: Beaverdam recreation area, 98 percent; Holly Point 
recreation area, 25 percent; and B.W. Wells and Shinleaf 
Peninsula recreation area, 5 percent. Maintenance: 
Repairs for erosion on the I-85 utility fill cost $168,860. Intake 
tower gate maintenance cost $108,986. Normal operation 
and maintenance cost $770,991. Maintenance and 
operation of dams cost $73,000. 
Condition at end of fiscal year. Reservoir filling was 
completed on December 7, 1983. Dedication ceremonies 
were held on April 30, 1983. All facilities are basically complete 
except for fish and wildlife facilities, recreation 
6-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
facilities, State management and 0 & M facilities and project 
modifications due to the water storage shortage. 
24. STUART, VA. 
Location. The project is located on the South Mayo 
River at Stuart, Va., above and below Route 8 highway. 
(See USGS quadrangle sheet, Stuart, Va.) 
Existing project. The recommended plan consists of a 
100-foot bottom-width high flow diversion channel combined 
with downstream river widening. A weir will be placed 
across the entrance to the diversion channel and a bench 
channel design will be used for the downstream river 
widening. The South Mayo River above Route 8 highway 
will be widened to a 50-foot bottom width, using a 
trapezoidal channel design and the commercial site northwest 
of Route 8 will be filled to the elevation of approximately 
the 200-year frequency flood. All river widening, 
except for a short distance above Route 8, will be done on 
the north bank. The project was approved by the Chief of 
Engineers on February 1, 1985, under Section 205, 1948 
Flood Control Act, as amended. 
Local cooperation. Local interests must provide all 
lands, easements, rights-of-way, including suitable borrow 
and spoil disposal areas, and all alterations and relocations 
of buildings, transportation facilities, storm drains, 
utilities, and other structures and improvements 
necessary for construction; hold and save the United 
States free from damages; maintain and operate the project 
after completion; assume full responsibility for all project 
costs in excess of the Federal cost limitation of $4 
million; prescribe and enforce regulations to prevent 
obstruction or encroachments; continue to enforce flood 
plain regulations that comply with FEMA guidelines; and 
at least annually, inform affected interests regarding the 
limitations of the protection afforded by the project. Fully 
complied with to date. 
Operations and results during fiscal year. New work: 
Construction was completed at a cost of $2,107. 
Condition at end of fiscal year. Construction was completed 
and turned over to locals in November 1987. 
25. WRIGHTSVILLE BEACH, N. C. 
Location. A small island 10 miles east of Wilmington, 
N. C. (See Coast and Geodetic Survey Map p. 834.) 
Existing project. Construct a dune with a base bordering 
at or near the building line, with a crown width of 25 
feet at elevation 15 feet above mean low water, together 
with integral construction of a beach berm with a crown 
width of 50 feet at elevation 12, extending about 14,000 
feet from Moores Inlet on the north to Masonboro Inlet on 
the south. Existing project was authorized by 1962 Flood 
Control Act (H.D. 511, 87th Cong., 2d sess.). The Water 
Resources Development Act of 1986 authorized Federal 
participation in future nourishment for the life of the project.
Local cooperation. Fully complied with to date. 
Operations and results during fiscal year. New work: A 
reevaluation report to determine if the Federal government 
will continue to participate in future nourishment for 
the life of the project cost $50,000. 
Condition at end of fiscal year. All work under the initial 
authorization has been completed. 
26. YADKIN RIVER BASIN, N. C. AND S. C. 
Location. The river rises on the eastern slope of the 
Blue Ridge Mountains in western North Carolina, flows 
generally easterly about 100 miles to the vicinity of Donnaha, 
North Carolina, thence southeasterly 104 miles to its 
confluence with Uwharrie River near Badin, North 
Carolina, where its name changes to Great Pee Dee River. 
(See U.S. Geological Survey map of North Carolina.) 
Existing project. The Flood Control Act of July 24, 1946, 
authorized construction of four flood control dams in the 
Upper Yadkin River Basin, two on the Yadkin River above 
Wilkesboro, North Carolina, and two on Reddies River, a 
tributary stream. Studies made subsequent to authorization 
established the economic advantage of providing 
needed flood-control storage in only two reservoirs, one on 
the Reddies and one on the Yadkin. Present planning considers 
only the two-reservoir plan, W. Kerr Scott Dam and 
Reservoir constructed 1962 and Reddies River Lake. W. 
Kerr Scott was transferred to the Wilmington District 
from Charleston in fiscal year 1980. Any future work on 
Reddies River will also be done by the Wilmington 
District. (See Table 6-J on Dams and Reservoirs.) 
26A. W. KERR SCOTT DAM AND RESERVOIR, N. C. 
Location. W. Kerr Scott Dam and Reservoir is on 
Yadkin River, North Carolina, about 6 miles upstream 
from Wilkesboro. At full flood-control pool elevation (1,075 
feet mean sea level), the reservoir extends 15.7 miles 
upstream to the Wilkes-Caldwell County line. 
Existing project. The project consists of a rolled earthfill 
dam 1,740 feet long, with top of dam at elevation 1,107.5 
feet mean sea level or about 148 feet above streambed 
elevation; a spillway near the north abutment of the dam 
in a rock cut with crest elevation 1,075; and outlet works 
consisting of an intake structure, control tower, and a circular 
concrete conduit 12.25 feet in diameter through the 
base of the dam near the south abutment. The reservoir 
has a gross capacity of 153,000 acre-feet of which 112,000 
acre-feet are reserved for flood control, 33,000 acre-feet 
will be used as required for water supply, and 8,000 acrefeet 
being contained in the minimum pool. Estimated cost 
is $9,110,000 (1983) for new work. The existing project was 
authorized by the 1946 Flood Control Act. 
Local cooperation. Requirements fully satisfied. For 
details, see page 413 of Annual Report for 1963. 
Operations and results during fiscal year. Maintenance: 
Seismic studies cost $6,003. Design of the management 
center cost $18,103. Liquefaction study cost $45,114. 
Drought management plan cost $1,013. Periodic inspections 
cost $21,876. Intake tower gate maintenance cost 
$29,383. Design for stilling basin repairs cost $17,766. Ar- 
6-14

WILMINGTON, N. C., DISTRICT 
cheological surveys cost $1,549. Updating flood control 
data cost $57,753. Downstream economic study cost $1,787. 
Normal operation and maintenance cost $1,077,973. 
Maintenance and operation of dams cost $73,000. 
Condition at end of fiscal year. The project was commenced 
in August 1960 and placed in operation for flood 
control and water storage purposes in August 1962. 
27. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections 
were made for the following projects during fiscal year 
1988: Ellis Swamp, Gates County, N. C.; Gapway Swamp, 
Columbus County, N. C.; Old Field Swamp, Robeson County, 
N. C.; Gardners Creek, Martin County, N. C.; New 
River, Beaufort County, N. C.; Filberts Creek, Edenton, 
N. C.; Pantego and Cucklers Creek, Beaufort County, 
River, Beaufort County, N. C.; and Filberts Creek, Edenton, 
N. C.; Pantego and Cucklers Creek, Beaufort County, 
N. C.; White Oak Dike, Bladen and Pender Counties, N. C.; 
Ellerbe Creek, Durham County, N. C.; Pasquotank Dike, 
Pasquotank County, N. C.; Perquimans River, Perquimans 
County, N. C.; Core Creek, Craven County, N. C.; 
Princeville Dike, Edgecombe County, N. C.; Swift Creek, 
Pitt County, N. C.; Carolina Beach, New Hanover County, 
N. C.; Wrightsville Beach, New Hanover County, N. C.; 
Goldsboro, Neuse River, Wayne County, N. C.; Broad 
Creek, Beaufort County, N. C.; Little Rockfish Creek, 
Hope Mills, N. C.; Black River, Harnett County, N. C.; Lick 
Run, Roanoke, Va.; Deep Creek, Edgecombe County, N. C.; 
Joyce Creek, Camden County, N. C.; Ararat River, Surry 
County, N. C.; South Mayo River, Stuart, Va; and Leith 
Creek, Scotland County, N. C. Responsible local officials 
were advised of inadequacies in maintenance and operation 
on local flood protection works where appropriate. 
Cost for the period was $40,500. Total cost to September 
30, 1989, was $453,059, charged to operations. 
28. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization). 
(See Table 6-K.) 
Emergency flood control activities and hurricane flood 
and shore-protection activities at Federally authorized 
projects (Public Law 99, 84th Congress, and antecedent 
legislation). 
National Emergency Preparedness Program cost 
$154,118. Disaster Preparedness Program cost $92,433. 
Multiple-Purpose Projects, Including Power 
29. ROANOKE RIVER BASIN, VA. AND N. C. 
Location. The project is on the Roanoke River and its 
tributaries in Virginia and North Carolina within a radius 
of 100 miles from Danville, Virginia. 
Existing project. The Flood Control Act of 1944 approved 
a general plan for the comprehensive development of 
the Roanoke River Basin for flood control and other purposes, 
and authorized construction of John H. Kerr and 
Philpott Reservoirs. (See Table 6-J for a list of dams and 
reservoirs included in the comprehensive plan.) 
Local cooperation. None required. John H. Kerr and 
Philpott Reservoirs are the only projects in the comprehensive 
plan that have been authorized for construction. 
(See Table 6-J on Dams and Reservoirs.) 
29A. JOHN H. KERR DAM AND RESERVOIR, VA. 
AND N. C. 
Location. The project is on Roanoke River, about 178.7 
river miles above its mouth, in Mecklenburg County, 
Virginia, and 20.3 miles downstream from Clarksville, 
Virginia. The reservoir extends upstream on Roanoke 
River 56 miles and on Dan River 34 miles. 
Existing project. The authorized project provides for a 
concrete gravity dam with wing and saddle dikes on the 
right and left banks, with a total length of about 22,285 
feet. The reservoir is operated as a unit of a coordinated 
system of reservoirs in the Roanoke River Basin for 
control of floods, generation of hydroelectric power, 
regulation of low-water flow, and for other purposes. The 
power installation is 204,000 kilowatts. (For further details 
see Annual Report for 1962.) Estimated cost is $67,529,000 
(1983) for construction and $24,521,000 for lands and 
damages, including relocation of highways, railroads, and 
utilities, a total of $92,050,000 for new work. The existing 
project was authorized by the 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Cost-sharing with the State of N. C. at various sites cost 
$2,131. Maintenance: Final cost on the management center 
was $4,276. Work in connection with acquistion of land in 
South Boston area cost $4,810. Study on the impact of 
water withdrawals cost $951. Work on the fire protection 
system for the powerhouse cost $3,301. Replacement of the 
powerhouse computer was continued at a cost of $117,161. 
Periodic inspection of the dam bridge cost $155. Final 
guide taking line study cost $81. Investigation and 
stability analysis of earth dikes cost $66,957. Investigation 
and stability analysis of Island Creek dam cost $25,200. 
Adjustment in cost of courtesy docks caused a decrease of 
$23,826. Northbend Park water system improvements cost 
$361,807. Replacement of powerhouse roof cost $236,784. 
Recreational road paving cost $145,229. Design and award 
for management center exhibits cost $26,657. Design for 
renovation of Rudds Creek recreation area cost $45,250. 
The real estate DM for acquisition in the South Boston 
area cost $55,685. Investigation of deep seated sliding of 
the dam cost $335,159. Drought management plan cost 
$5,908. Periodic inspection and evaluation of dam cost 
$13,342. Archeological survey cost $12,552. Design of 
quardrails for the earth dikes cost $19,245. Vegetative 
erosion control research cost $1,540. Powerhouse power 
study cost $2,472. Normal operation and maintenance cost 
$4,800,035. Maintenance and operation of dams cost 
$73,000. 
6-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities. Production of 
power and protection from floods are provided by project. 
29B. PHILPOTT LAKE, VA. 
Location. On Smith River, Virginia, 44.3 miles above its 
junction with Dan River, and 35 miles upstream from 
Virginia-North Carolina State line in Franklin and Henry 
Counties. 
Existing project. The authorized project provides for a 
concrete gravity dam 892 feet long and with a maximum 
height of 220 feet. Reservoir is operated as a unit of a coordinated 
reservoir system for flood control in the Roanoke 
River Basin, generation of hydroelectric power, regulation 
of low-water flow, and for other purposes. The powerhouse 
has a total installation of 14,000 kilowatts. (For further 
details see Annual Report for 1962.) Federal cost estimate 
is $13,933,000 (1983) for construction and $1,157,000 for 
lands and damages, a total of $15,090,000. Existing project 
was authorized by 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Construction of management and visitors center was completed 
at a cost of $5,148. Replacement of the powerhouse 
computer was continued at a cost of $50,602. Periodic inspection 
and evaluation of the dam cost $8,906. Construction 
of the exhibits for the management center cost 
$167,580. Installation of a tile field for Salthouse Branch 
recreation area cost $58,890. Design of a boathouse and 
bulkhead at Philpott Park cost $1,292. Normal operation 
and maintenance cost $1,527,461. Maintenance and operation 
of dams cost $73,000. 
Condition at end of fiscal year. The project is complete 
except for additional recreational facilities, and is providing 
power and flood protection. 
30. SCHEDULING FLOOD CONTROL RESERVOIR 
OPERATIONS 
B. Everett Jordan Dam and Lake, located iri the Cape 
Fear River Basin, North Carolina, began fiscal year 1989 at 
elevation 210.52 feet m.s.l. or 5.48 feet below normal pool. 
The minimum elevation of the fiscal year occurred on October 
3 at elevation 210.32 feet, m.s.l., or 5.68 feet below 
normal pool. Jordan fluctuated near elevation 211 feet, 
m.s.l. until the end of October when heavy rainfall pushed 
the lake level up to near elevation 214 feet m.s.l. Excessive 
rainfall near the end of November pushed the lake level up 
to the normal pool elevation of 216 feet m.s.l. Jordan Lake 
remained near normal pool through mid-February when a 
series of rainfall events followed causing the lake to rise to 
the highest elevation of the fiscal year at 226.72 feet m.s.l., 
or 10.72 feet above normal pool on March 9. Jordan Lake 
was drawn down to within one foot of normal pool when 
another rainfall event pushed the lake level to elevation 
224.99 feet M.S.L. at the end of March. Three other lake 
level peaks of 219.27, 221.62 and 218.48 feet m.s.1. occurred 
on April 11, May 4 and July 18, respectively. Otherwise, 
Jordan Lake remained near normal pool for the remainder 
of the year. On September 30, Jordan Lake was at 216.18 
feet m.s.1, or 0.18 foot above normal pool. Total flood and 
conservation storage utilized during the year was 35 percent 
and 49 percent, respectively. Flood damages 
prevented during fiscal year 1989 were $1,123,600 making 
the cumulative total since inception of the project at 
$12,490,600. Total cost of functional operation for the 
period was $131,938. 
Falls Lake, located in the Neuse River Basin, North 
Carolina, began fiscal year 1989 at elevation 246.90 feet 
m.s.l., or 4.1 feet below rule curve. Downstream minimum 
flow requirements kept the lake level near elevation 247 
feet m.s.l. throughout October, even with greater than normal 
rainfall. The minimum elevation for the fiscal year occurred 
on October 31 at 246.77 feet M.S.L., or 3.33 feet 
below rule curve. Heavy rainfall events on October 31 and 
November 1 brought the lake level up to near elevation 
249 feet m.s.l. where it remained until early January. Rainfall 
at the end of December and early January brought the 
lake level up near the rule curve elevation of 250.1 feet 
m.s.l. where it remained until mid February. Multiple 
storm events caused a significant rise to elevation 258.09 
feet m.s.l., or 7.99 feet above rule curve on March 8 which 
was the maximum elevation for the fiscal year. After dropping 
to elevation 252 feet m.s.l., another storm caused the 
lake level to rise to elevation 256.05 feet m.s.l. on March 26. 
The lake level returned to near rule curve in mid April. 
Heavy rains in late April and early May caused Falls Lake 
to rise to elevation 255.27 feet m.s.l. on May 3. The lake 
level returned to near the rule curve level of 251 feet m.s.l. 
by mid May and remained there until mid July when rainfall 
caused a rise to elevation 253.90 feet m.s.l. Two other 
minor lake rises occurred in August with the higher peak 
at elevation 253.02 feet m.s.l. With the threat of Hurricanes 
Gabrielle and Hugo, the Falls Lake level was 
brought below the rule curve to near the bottom of the 
controlled flood pool level of 250.1 feet m.s.l. during 
September. Falls Lake ended the fiscal year at elevation 
250.33 feet m.s.l. Total flood and conservation storage 
utilized during the year was 51 percent and 38 percent, 
respectively. Flood damages prevented during fiscal year 
1989 were $10,545,000 making the cumulative total since 
inception of the project at $32,103,000. Total cost of functional 
operation for the period was $120,571. 
John H. Kerr Dam and Reservoir, located in the 
Roanoke River Basin, Virginia and North Carolina, began 
fiscal year 1989 at elevation 297.36 feet m.s.l. or 2.1 feet 
below rule curve. The Kerr Reservoir level reached the 
rule curve at the end of October and rose to elevation 298.3 
feet m.s.1. in early November. The reservoir level was 
drawn back down to rule curve by mid December. The 
minimum elevation of the fiscal year was 295.06 feet m.s.l., 
or 0.44 foot below rule curve on December 19. Kerr Reservoir 
fluctuated slightly above rule curve through the middle 
of February 1989. Excessive rainfall then pushed the 
reservoir level to elevation 302.63 feet m.s.l., or about five 
feet above rule curve. The distance between rule curve 
and actual pool level decreased as the rule curve rose to 
elevation 301 feet m.s.L in the month of March. Kerr 
Reservoir reached the rule curve by mid April. Heavy 
6-16

WILMINGTON, N. C., DISTRICT 
rainfall during the last few days of April and the beginning 
of May caused Kerr Reservoir to rise to elevation 309.96 
feet m.s.l., or 7.96 feet above rule curve on May 11. This 
was the maximum elevation for the fiscal year. Kerr 
Reservoir was drawn down to rule curve by the end of 
May. Again excessive rainfall during the first two weeks 
in June caused the lake to rise and fluctuate about four 
feet above rule curve through the end of June. Kerr Reservoir 
continued to fluctuate one to two feet above rule 
curve through the end of September due to cyclic rainfall 
events. On September 30, Kerr Reservoir elevation was 
301.55 feet m.s.l., or 2.05 feet above rule curve. In cooperation 
with state and federal fish and wildlife agencies, the 
Wilmington District agreed to test a new fish flow regime 
in the lower Roanoke River to enhance the striped bass 
fish spawning. Fish flows commenced on the first of April 
and concluded on June 15. Flow rates under the new plan 
for the striped bass coincide with natural flow rates with 
heavier flows being released in April and lower flow rates 
occurring in June. Preliminary reports from state fisheries 
personnel indicate that the fish flow season was of average 
success. Total flood and current contractural power pool 
storage utilized during the year was 43 percent and 73 percent, 
respectively. Gross generation for the fiscal year 
amounted to 498,707,000 kilowatt hours and net marketed 
power revenue was $6,000,318 making a cumulative total 
since inception of $135,946,363. Flood damages prevented 
during fiscal year 1989 were $2,300,000, making the 
cumulative total since inception of the project at 
$141,507,000. Total cost of functional operation for the 
period was $343,924. 
Philpott Lake, located on the Smith River in the Dan 
River Basin, Virginia, began fiscal year 1989 at elevation 
965.32 feet m.s.l., or 6.18 feet below rule curve. This low 
lake level was due to the continuing effects of the drought 
which occurred during the summer of 1988. The minimum 
elevation of the fiscal year occurred on November 4 at 
elevation 963.54 feet m.s.l., or 7.96 feet below rule curve. 
Philpott Lake rose only three feet by mid February 
because of below normal rainfall. Heavy rains during mid 
February to early March produced a rapid rise in lake 
level to the rule curve elevation of 973.2 feet m.s.l. on 
March 25. Philpott Lake remained at or near rule curve 
during April. Above normal rainfall occurred during the 
remainder of the fiscal year producing several peak elevations 
near elevation 976 feet m.s.l. The highest elevation of 
the fiscal year was 976.64 feet m.s.l., or 3.14 feet above rule 
curve on May 8. Philpott Lake ended the fiscal year at 
elevation 974.35 feet or 2.85 feet above rule curve. Total 
flood and current contractural power pool storage utilized 
during the year was 23 percent and 49 percent, respectively. 
Gross generation for the fiscal year amounted to 
24,280,840 kilowatt hours and net marketed power 
revenue was $1,283,507 making a cumulative total since inception 
of $18,482,284. Flood damages prevented during 
fiscal year 1989 were $8,921,000, making the cumulative 
total since inception of the project at $151,756,000. Total 
cost of functional operation for the period was $141,827. 
W. Kerr Scott Dam and Reservoir, located in the 
Yadkin-Pee Dee River Basin, North Carolina, began fiscal 
year 1989 at elevation 1,028.07 feet m.s.l., or 1.93 feet 
below normal pool. This was also the minimum elevation 
of the fiscal year. The reservoir rose gradually to normal 
pool by November 5. W. Kerr Scott Reservoir remained 
near normal pool through early December when below 
average rainfall and streamflows caused the elevation to 
drop to 1,028.74 feet m.s.l. on November 19. The reservoir 
returned to normal pool by early January and remained 
there through the end of the fiscal year except for three 
peak elevations between elevations 1,033 and 1,035 feet 
m.s.1. A fourth event caused by the remnants of Hurricane 
Hugo produced the maximum elevation of the fiscal year of 
1,039.43 feet m.s.l., or 9.43 feet above normal pool on 
September 23. W. Kerr Scott Reservoir ended fiscal year 
1989 at elevation 1,030.60 feet m.s.1. Total flood and 
conservation storage utilized during the year was 13 
percent and 7 percent, respectively. Flood damages 
prevented during fiscal year 1989 were $3,470,000 making 
the cumulative total since inception of the project at 
$67,762,000. Total cost of functional operation for the 
period was $115,589. 
General Investigations 
31. SURVEYS 
Cost for the period was $1,009,361, of which $138,588 
was for navigation studies, $678,675 was for flood control 
studies, $86,105 was for beach erosion studies, $56,355 for 
Special Investigations, $7,401 for FERC licenses review, 
$15,969 for interagency water resources development, 
$3,000 for soil conservation service, $6,291 for hydrologic 
studies, and $16,977 for cooperation with states. Contributed 
funds in the amount of $137,500 were expended 
for navigation studies. 
32. COLLECTION AND STUDY OF BASIC DATA 
Flood plain information studies, as authorized by Section 
206, 1960 Flood Control Act, as amended, comprise 
compilation and dissemination, upon the request of a State 
or a political subdivision thereof, of information on floods 
and flood damages, including identification of areas subject 
to inundation by floods of various magnitudes and frequencies, 
and general criteria for guidance of Federal and non- 
Federal interests and agencies in the use of flood plain 
areas; and provide advice to other Federal agencies and 
local interests for their use in planning to ameliorate the 
flood hazard. Total costs for the period were $328,834. 
Total costs to September 30, 1989 were $4,619,459. 
33. PRECONSTRUCTION ENGINEERING AND 
DESIGN 
Preconstruction engineering and design (PED) for 
Wilmington Harbor, Northeast Cape Fear River, N. C., 
was continued at a cost of $166,198. PED was continued on 
Roanoke River Upper Basin, Virginia, Headwaters Area at 
a cost of $515,241. PED was continued on Brunswick 
County Beaches, N. C., at a cost of $86,400. 
6-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 6-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
1. Aquatic Plant Control 
(R&H Act of 1965) 
(Regular Funds) 
(Contributed Funds) 
2. Atlantic Beach 
Channels, N. C. 
(Regular Funds) 
(Contributed Funds) 
3. Atlantic Intracoastal 
Waterway between 
Norfolk, Va. & St. 
Johns River, Fla. 
(Regular Funds) 
(Contributed Funds) 
4. Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
5. Belhaven Harbor, N.C. 
6. Cape Fear River, 
N. C. above 
Wilmington 
7. Channel from Back 
Sound to Lookout 
Bight, N. C. 
8. Far Creek, N. C. 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
100,000 
83,917 
58,000 
73,934 
66,000 
20,711 
78,000 
75,645 
9,419 
9,419 
6,469,000 
7,324,248 
9,777,600 
9,563,186 
718,630 
653,300 
51,200 
51,221 
135,000 
113,712 
8,742,100 
8,535,338 
220,000 
326,924 
4,627,900 
5,002,474 
570,000 
550,674 
6,375,785 
6,462,571 
-65,330 
444,000 
444,000 
- 116,142 
- 116,142 
13,800 
13,800 
73,200 
63,200 
618,000 967,000 
468,696 1,111,720 
13,000 
12,754 
63,000 
62,713 
1,100 
100 
21,400 
20,428 
42,000 
41,250 
250,100 
260,100 
704,300 
707,999 
293,500 
292,720 
-1,000 
106,200 
101,800 
750 
-1,305 
-1,305 
479,777 
31,809 
31,8091 
18,501 
18,501 
76,049 
76,049 
10,600 
10,6002 
42,776,9733 
42,727,1853 
93,830,445' 
93,641,987' 
86,851 
86,8515 
667,300 
667,300 
818,0406 
818,0406 
3,470,514' 
3,465,142 
34,000 
34,000 
326,225 
326,225 
126,687 
126,687 
376,401 
376,401 
- 3,759,5738 
- 3,759,5738 
577,200 15,002,114 9 
574,023 14,996,664 9 
- 88,328 
- 88,328 
154,800 2,780,471 
156,933 2,780,096 
8,700 
8,700 
164,642 
164,642 
1,190,704 
1,190,704 
6-18

WILMINGTON, N. C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
9. Lockwoods Folly 
River, N. C. 
(Regular Funds) 
(Contributed Funds) 
10. Manteo (Shallowbag) 
Bay, N. C. 
(Regular Funds) 
(Contributed Funds) 
11. Morehead City 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
12. Ocracoke Inlet, N. C. 
13. Pamlico and Tar 
Rivers, N.C. 
14. Roanoke River, N.C. 
15. Silver Lake 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
16. Smith Creek 
(Pamlico County), N. C. 
17. Waterway Connecting 
Pamlico Sound and 
Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib: 
Cost 
746,200 
746,165 
287,500 
280,694 
- 165,000 
109,007 158,185 
4,126,500 4,598,700 
4,315,962 4,605,597 
- 156,000 
- 156,000 
6,262,000 
6,310,359 
261,550 
122,543 
11,000 
12,438 
1,639,000 
1,595,803 
-54,579 
299,670 
11,700 
11,497 
400 
432 
588,000 
603,609 
17,681 
3,508,600 
3,469,509 
1,356,500 1,87 
1,355,855 1,77 
- 8 
- 8 
9,500 
9,656 
44,227 
44,227 
346,700 
353,386 
241,272 0 
241,2721 " 
4,608,046 
4,608,046 
92,650 
92,65012 
- 7,649,945 13 
- 7,649,94513 
5,526,300 47,702,007 
5,445,397 47,568,125 
418,000 1,645,940 
- 1,221,732 
11 
45 
45 
168,000 
177,145 
232,732 
232,732 
831,000 
875,000 
1,325 
1,325 
22,878 
21,878 
- 6,546,053"14 
- 6,546,0531' 
13,400 45,172,173 15 
15,087 45,029,99615 
39,778 1,264,414 
32,762 1,256,686 
-- 346,240 
- 346,240 
8,000 937,344 
9,248 937,344 
- 674,651 
- 674,651 
8,000 885,205 
8,000 885,205 
22,000 
22,000 
651,300 
651,300 
13,200 
12,692 
239,310 
259,337 
669,500 
669,500 
2,000 
2,508 
269,200 
269,797 
404,584 
404,584 
572,409 
572,409 
184,284 
184,284 
5,802,418 
5,802,418 
75,000 
75,000 
113,273 
113,273 
52,912 
52,912 
502,567 
502,567 
2,940,709 
2,940,333 
2,452 
2,452 
6-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
18. Wilmington Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
19A. B. Everett Jordan 
Dam and Lake, N. C. 
(Regular Funds) 
(Contributed Funds) 
19B. Randleman Lake, N. C. 
20. Carolina Beach and 
Vicinity, N. C. 
(Regular Funds) 
(Contributed Funds) 
21. Dan River, Madison, 
N. C. 
(Regular Funds) 
(Contributed Funds) 
22. Leesville, Va. - Roanoke 
River 
Sec. 32 Demo. Project 
23A. Falls Lake, N. C. 
24. Stuart, Va. 
25. Wrightsville Beach, N.C. 
(Regular Funds) 
(Contributed Funds) 
26A. W. Kerr Scott Dam 
and Reservoir, N. C. 
29A. John H. Kerr Dam 
and Reservoir, Va. & N.C. 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
2,590,000 
2,553,489 
452,560 
398,651 
8,10 
8,59 
81 
87
2' 
2,322,500 
2,357,116 
338,215 
86,662 
9,000 9,834,000 
5,667 8,662,787 
4,400 911,000 
9,704 893,708 
- 100,000 
- 20,000 
- 490,000 
7,356 498,881 
-40,739 
-52,624 
40,789 
17,840 
37,000 
35,586 
23 
2,694,000 7,045,000 
3,876,795 5,969,059 
1,748,000 1,164,000 
1,461,526 1,331,436 
570,000 1,540,000 
202,768 1,623,188 
1,216,100 1,236,000 
1,159,355 1,252,762 
5,400 
199,367 
6,857,000 
6,576,725 
-
373 
5,222,900 
5,372,772 
4,158,100 
4,119,530 
220,843 
404,819 
8,974,000 
8,007,874 
979,500 
954,485 
10521 
14,415 
137,000 
142,284 
920,000 
914,556 
1,100,000 
975,979 
123,000 
108,787 
40,000 
29,915 
5,218,000 
4,913,377 
830,400 
966,316 
-100,000 
186,740 
- 18,715,226 18 
- 18,715,22618 
3,868,100 61,596,02017 " 
3,888,351 61,572,84517 
422,041 4,763,64418 
231,738 4,421,07518 
3,647,000 
5,392,728 
1,002,400 
1,050,647 
31,572 
308 
270,000 
176,764 
-120,511 
3,510 
-18,508 
-2,881 
-6,177 
3,908 
3,330 
5,050,000 
6,188,558 
1,095,000 
1,121,837 
-9,600 
2,107 
50,000 
50,000 
136,612,641 
133,790,266 
7,219,25619 
7,163,634 20 
1,821,494 
1,787,376 
4,797,588 
4,785,659 
9,088,533 
8,958,252 
6,674,45422 
6,674,45422 
141,49223 
141,492 24 
33,823 
33,823 
367,755 
367,755 
152,327,996 
151,370,501 
7,364,60019 
7,329,83120 
2,220,400 25 
2,220,400 26 
1,597,100 
1,597,100 
1,466,088 
1,466,08827 
-- - 8,841,326 
- - 8,841,326 
1,556,600 1,307,000 16,666,14828 
1,597,277 1,351,320 16,606,86429 
- - 94,402,927 
2,480 2,131 94,402,927 
6,653,600 5,245,400 76,973,94230 
5,698,688 6,333,731 76,566,188'31 
6-20

WILMINGTON, N. C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
29B. Philpott Lake, Va. New Work: 
Approp. -5,400 - - - 14,796,384 
Cost 22,770 - - - 14,796,384 
Maint: 
Approp. 2,089,000 1,672,000 1,942,000 1,796,600 24,355,906 32 
Cost 2,082,671 1,759,343 1,821,459 1,892,879 24,206,309 3 
1. Includes $2,369 refund to local interests in FY 82. 
2. Includes $2,055 refund to local interests. 
3. Includes $198,707 for previous projects. 
4. Includes $107,634 for previous projects. 
5. Includes $13,934 refund to local interests. 
6. Includes $25,000 for previous projects. 
7. Includes $12,854 for previous projects. 
8. Includes $149,119 for previous projects. 
9. Includes $8,178 for previous projects. 
10. Includes preauthorization study funds: FY 64, $3,000; 
FY 65, -$2,755; FY 71, $8,000; FY 72, $2,000; FY 74, $9,000; FY 
75, $25,000; FY 76 & 76T, $20,000; FY 77, $2,500; FY 78, $8,800; 
FY 79, $3,000; FY 81, $1,680; and preconstruction planning 
funds: FY 80, $15,000 and FY 81, $19,320. 
11. Includes preauthorization study costs: FY 64, $219; FY 
65, $26; FY 71, $8,000; FY 72, $1,448; FY 73, $552; FY 74, $9,000; 
FY 75, $11,925; FY 76 & 76T, $27,977; FY 77, $7,598; FY 78, 
$7,449; FY 79, $4,351; FY 81, $1,680; and preconstruction planning 
costs: FY 80, $5,686 and FY 81, $1,471. 
12. Includes $69,145 refund to local interests. 
13. Adjusted by $6,361 to reflect actual cost. 
14. Includes $44,484 for previous projects. 
15. Includes $284,557 for previous projects. 
16. Includes $4,625,614 for new work on previous projects. 
17. Includes $602,614 for previous projects. 
18. Includes refunds to local interests: FY 78, $92,374; FY 
79, $8,000; FY 80, $14,007; FY 81, $1,847; FY 82, $2,823; FY 85, 
$60,000. 
19. Includes maintenance and operation of Dams funds: 
FY 87, $66,678; FY 88, $75,000; FY 89, $73,000. 
20. Includes maintenance and operation of Dams costs: FY 
87, $66,678; FY 88, $75,000; FY 89, $73,000. 
21. Amount should not have been on records. Will be 
deducted in FY 90. 
22. Includes refunds to local interests: FY 83, $400,000; FY 
84, $128,345; FY 85, $82,600. 
23. Includes preauthorization study funds: FY 87, $37,000; 
FY 88, $2,926; and preconstruction planning and construction 
funds: FY 88, $120,074. 
24. Includes preauthorization study costs: FY 87, $35,586; 
FY 88, $4,340; and preconstruction planning and construction 
costs: FY 88, $104,447. 
25. Includes preauthorization study funds: FY 83, $45,000; 
FY 84, $9,986; and preconstruction funds: FY 84, $50,014; FY 
85, $115,000. 
26. Includes preauthorization study costs: FY 83, $42,496; 
FY 84, $12,490; and preconstruction costs: FY 84, $23,281; FY 
85, $127,330. 
27. Includes $61,585 refund to local interests. 
28. Includes Special Recreation Use Fees funds: FY 74, 
$4,000; FY 75, $5,500; FY 76 & 76T, $3,600; FY 77, $5,800; FY 
78, $7,200; FY 79, $8,000; FY 80, $10,000; FY 81, $10,000; FY 82, 
$11,040; FY 83, $7,000; FY 84, $9,000; and maintenance and 
operation of Dams funds: FY 87, $66,678; FY 88, $75,000; FY 89, 
$73,000. 
29. Includes Special Recreation Use Fees costs: FY 74, 
$4,000; FY 75, $4,400; FY 76 & 76T, $4,666; FY 77, $5,193; FY 
78, $6,824; FY 79, $7,506; FY 80, $11,312; FY 81, $9,688; FY 82, 
$9,727; FY 83, $7,000; FY 84, $8,444; FY 85, $2,379; and 
maintenance and operation of Dams costs: FY 87, $66,678; FY 
88, $75,000; FY 89, $73,000. 
30. Includes Special Recreation Use Fees funds: FY 74, 
$35,000; FY 76 & 76T, $48,000; FY 77, $51,400; FY 78, $115,100; 
FY 79, $63,000; FY 80, $60,000; FY 81, $80,000; FY 82, $67,160; 
FY 83, $77,759; FY 84, $73,000; and maintenance and operation 
of Dams funds: FY 79, $167,646; FY 87, $66,678; FY 88, $75,000; 
FY 89, $73,000. 
31. Includes Special Recreation Use Fees costs: FY 75, 
$35,000; FY 76 & 76T, $13,606; FY 77, $85,692; FY 78, $114,604; 
FY 79, $1,120; FY 80, $118,718; FY 81, $83,760; FY 82, $67,160; 
FY 83, $77,759; FY 84, $67,850; FY 85, $5,149; and maintenance 
and operation of Dams costs: FY 79, $167,350; FY 80, $296; FY 
87, $66,678; FY 88, $75,000; FY 89, $73,000. 
32. Includes Special Recreation Use Fees funds: FY 75, 
$47,000; FY 78, $40,400; FY 79, $22,000; FY 80, $25,000; FY 81, 
$20,000; FY 82, $20,240; FY 83, $21,000; FY 84, $19,000; and 
maintenance and operation of Dams funds: FY 87, $66,678; FY 
88, $75,000; FY 89, $73,000. 
33. Includes Special Recreation Use Fees costs: FY 75, 
$13,741; FY 76 & 76T, $31,666; FY 77, $1,593; FY 78, $39,771; 
FY 79, $22,629; FY 80, $24,619; FY 81, $20,381; FY 82, $20,240; 
FY 83, $21,000; FY 84, $19,000; and maintenance and operation 
of Dams costs: FY 87, $66,678; FY 88, $75,000; FY 89, $73,000. 
6-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 6-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 25, 1912 
July 25, 1912 
August 8, 1917 
July 18, 1918 
January 21, 1927 
July 3, 1930 
March 4, 19332 
June 26, 19343 
August 26, 1937 
August 26, 1937 
June 20, 1938 
June 20, 1938 
March 2, 1945 
June 30, 1948 
May 17, 1950 
May 17, 1950 
September 3, 1954 
November 29, 1963, 
sec. 107 
July 14, 1960 
April 7, 1966, 
sec. 107 
July 14, 1960 
November 7, 1966 
November 7, 1966 
December 31, 1970 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., and ST. JOHNS RIVER, 
FLA. (See Section 3 of text) 
Original route of the Norfolk-Beaufort Inlet section. 
Purchase of canal. 
Change in route; following changes approved by 
Secretary of War, April 14, 1919: 
Albemarle Sound-Pamlico Sound section: Changed from 
"Alligator River-Rose Bay route" to "Alligator River- 
Pungo River route." 
Pamlico Sound-Neuse River section: Changed from 
"Pamlico Sound-Brant Shoal Neuse River route" to 
"Goose Creek-Bay River route." 
Alligator River-Pungo route (proposed land cut connecting 
the rivers): Changed from a straight line to a bent 
line approaching nearer town of Fairfield, N. C. 
A 12-foot channel 90 feet wide from Beaufort to Cape 
Fear River, N. C., including highway bridge and tidal 
lock." 
An 8-foot channel 75 feet wide from Cape Fear River to 
Winyah Bay, S. C. 
Construct a suitable bridge near Fairfield, N. C. 
Operating and care of works of improvements provided 
for with funds from War Department appropriations for 
rivers and harbors. 
Increasing dimensions of waterway to 12 feet deep and 
90 feet wide. 
A 12-foot side channel 90 feet wide to Swansboro. 
A yacht basin near Southport, 12 feet deep, 230 feet 
wide, and 450 feet long, with connecting channel. 
A 6-foot channel 90 feet wide from New River Inlet to 
Inland Waterway. 
Six mooring basins.5 
A 12-foot channel in New River. 8 
Vicinity of Fairfield - drainage. 
Masonboro Inlet and connecting channels, including jetties 
at the inlet.7 
A 12-foot channel and basin in Peltier Creek.8 
A 6-foot channel 90 feet wide from Intracoastal Waterway 
to Bogue Inlet gorge. 
An 8-foot channel 150 feet wide through New Topsail Inlet, 
thence a 7-foot channel 80 ft. wide to Intracoastal 
Waterway by way of Old Topsail Creek; and a 7-foot 
channel 80 feet wide in Banks Channel from New Topsail 
Inlet, paralleling barrier beach, to Intracoastal 
Waterway. 
Maintenance of a channel, 6 feet deep, 80 feet wide, and 
8,000 feet long, from the through channel of the waterway 
to and including a basin of the same depth, 130 feet 
wide and 180 feet long at Carolina Beach. 
Maintenance of general navigation features of N. C. 
State Ports Authority Small Boat Harbor at Southport. 
Replacement of Federally-owned and operated highway 
bridges at Coinjock, Fairfield, Wilkerson Creek, 
Hobucken, and Core Creek. 
H. D. 391, 62d Cong., 2d sess. 
H. D. 589, 62d Cong., 2d sess. 
H. D. 1478, 63d Cong., 3d sess. 
and H. D. 1136, 64th Cong., 1st 
sess.' 
Approved by Secretary of War, 
May 15, 1919. 
H. D. 450, 69th Cong., 1st sess. 
H. D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 5, 72d Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 6, 75th Cong., 1st sess.' 
Rivers and Harbors Committee 
Doc. 16, 75th Cong., 1st sess.' 
H. D. 549, 75th Cong., 3d sess.' 
H. D. 691, 75th Cong., 3d sess.' 
H. D. 660, 76th Cong., 3d sess.' 
H. D. 421, 80th Cong., 1st sess.' 
H. D. 723, 80th Cong., 2d sess.' 
H. D. 341, 81st Cong., 1st sess.' 
H. D. 379, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1963. 
Detailed Project Report 
July 1965 
H. D. 515, 89th Cong., 2d sess.' 
H.D. 514, 89th Cong., 2d sess.' 
H. D. 142, 92nd Cong., 1st sess. 
6-22

WILMINGTON, N. C., DISTRICT 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
October 22, 1976 
August 13, 1968 
February 18, 1982, 
sec. 107 
July 14, 1960 
September 7, 1983, 
sec. 107 
July 14, 1960 
November 17, 1986 
March 3, 1881 
March 2, 1907 
March 3, 1925 
July 3, 1930 
March 2, 1945 
May 17, 1950 
May 21, 1965, 
sec. 107 
July 14, 1960 
August 12, 1983, 
sec. 107 
July 14, 1960 
July 3, 1930 
October 17, 1940 
February 7, 1967, 
sec. 107 
July 14, 1960 
August 30, 19359 
August 26, 1937 
March 2, 1945 
Modification of terms of local cooperation to allow for 
full Federal funding of Wilkerson Creek and Coinjock 
Bridges. 
Mitigation of damages caused by north jetty at Masonboro 
Inlet. 
An 8-foot channel 150 feet wide through Carolina Beach 
Inlet to the Intracoastal Waterway. 
An 8-foot channel 150 feet wide from the gorge in 
Bogue Inlet through the ocean bar. 
Modification of terms of local cooperation to allow for full 
Federal funding of Core Creek, Hobucken, and Fairfield 
Bridges. 
BEAUFORT HARBOR, N. C. (See Section 4 of text) 
A 9-foot channel 200 feet wide through Bulkhead Channel 
to Beaufort; a 6-foot channel 100 feet wide to North River 
and Core Sound; and construct jetties on Shackleford 
Point. 
Repairs to Fort Macon jetties and additional jetties and 
shore protection. 
Bulkhead across Bird Shoal. 
Increase in depth to 12 feet in Bulkhead Channel, Gallants 
Channel, and in front of Beaufort. 
Increase in width and length of basin in front of Beaufort, 
all to 12 feet deep. 
Increase in depth to 12 feet and in width to 100 feet in 
Taylors Creek; transfer to Beaufort Harbor project. 
Channels 15 feet deep, 100 feet wide in Bulkhead, Gallants 
and Taylors Creek channels, and through turning basin in 
front of Beaufort; and harbor of refuge in Town Creek, 12 
feet deep, 400 feet wide, and 900 feet long connected to 
Gallants Channel by channel 12 feet deep, 150 feet wide, 
and 1,400 feet long. 
A channel 14 feet deep, 70 feet wide, and 1,900 feet long, 
from Bulkhead Channel to a turning basin 14 feet deep, 
150 feet wide, and 300 feet long near the upper end of 
Morgan Creek. 
SILVER LAKE HARBOR, N. C. (See Section 15 of text) 
Entrance channel, 5 feet deep and 50 feet wide, from 
Pamlico Sound to the 3-foot contour in the lake, and training 
wall at entrance. 
Channel, 10 feet deep, and anchorage basin of same depth, 
100 feet wide across Big Foot Slough and 60 feet wide in 
entrance. 
Basin depth of 12 feet in Silver Lake Harbor; channels 12 
feet deep, 150 feet wide, in Teaches Hole and Big Foot 
Slough Channels and across Bluff Shoal; entrance channel, 
same depth, 60 feet wide; and training wall on south side of 
entrance channel. 
WATERWAY CONNECTING PAMLICO SOUND AND 
BEAUFORT HARBOR, N. C. (See Section 17 of text) 
A 7-foot channel 75 feet wide from Pamlico Sound to 
Beaufort Harbor via Wainright Channel. 
A 7-foot channel 75 feet wide to Atlantic. 
Channels 7 feet deep, 75 feet wide, at east and west 
ends of Harkers Island and side channel 5 feet deep, 75 
feet wide, with basin 150 by 130 feet, same depth, at Davis. 
H. D. 597, 94th Cong., 2d sess. 
Approved by OCE Oct. 2, 1980 
Detailed Project Report 
June 1980 
Detailed Project Report 
May 1983 
Annual Report, 1881, p. 1013 
Specified in act. 
Rivers and Harbors Committee 
Doc. 8, 68th Cong., 2d sess.1 
H. D. 776, 69th Cong., 2d sess.1 
H. D. 334, 76th Cong., 1st sess.' 
H. D. 111, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1965 
Detailed Project Report 
June 1983 
Rivers and Harbors Committee 
Doc. 3, 70th Cong., 1st sess. 
H. D. 325, 76th Cong., 1st sess.' 
Detailed Project Report 
July 9, 1965 
H. D. 485, 72d Cong., 2d sess.' 
Rivers and Harbors Committee 
Doc. 92, 74th Cong., 2d sess.' 
H. D. 99, 77th Cong., 1st sess.' 
6-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 2, 1945 A 7-foot side channel 75 feet wide, with basin 200 feet by S. D. 247, 77th Cong., 2d sess.' 
500 feet, same depth, at Sealevel. 
May 17, 1950 A 6-foot side channel 60 feet wide, with basin 100 feet by H. D. 68, 81st Cong., 1st sess.1 
about 600 feet, same depth, at Marshallberg. 
July 11, 1963, A side channel 7 feet deep, 70 feet wide to local harbor at Detailed Project Report 
sec. 107 Cedar Island and an access channel 6 feet deep, 60 feet Dec. 12, 1962 
July 14, 1960 wide and about 400 feet long to a basin same depth, 60 by 
100 feet. 
September 22, 1967, An entrance channel 6 feet deep, 60 feet wide, from Back Detailed Project Report 
sec. 107 Sound to harbor of refuge 120 by 250 feet, same depth, at March 13, 1967 
July 14, 1960 west end of Harkers Island in Brook Creek. 
February 17, 1969, A channel 7 feet deep, 70 feet wide, from existing side Detailed Project Report 
sec. 107 channel at Atlantic to a basin 600 by 180 feet, same depth, Dec. 21, 1967 
July 14, 1960 with a breakwater, between mouth of Little Port Brook 
and White Point. 
April 3, 1975, Deepening the existing 5-foot channel and basin at Davis Detailed Project Report 
sec. 107 to 7 feet. Feb. 8, 1974 
July 14, 196010 
1. Contains latest published maps. 
2. Public Law No. 443, 72d Cong. 
3. Permanent Appropriations Repeal Act. 
4. Tidal lock in land cut between Myrtle Sound and Cape 
Fear River, deauthorized September 23, 1986, under authority 
of Sec. 12, PL 93-251. 
5. Deauthorized August 5, 1977 under authority of Sec. 
12, PL 93-251. 
6. A 12-foot by 90-foot channel in New River from Intracoastal 
Waterway to and including a basin at Jacksonville, 
N. C. 
7. Jetties on each side of Masonboro Inlet. 
8. A 6-foot by 50-foot channel provided under Section 3, 
River and Harbor Act of March 2, 1945; 12-foot by 90-foot project 
deauthorized November 17, 1986 under authority of Sec. 
1002, PL 99-662. 
9. Included in the Public Works Administration Program, 
Jan. 3, 1934. 
10. Deauthorized by the Chief of Engineers March 31, 
1982. 
6-24

WILMINGTON, N. C., DISTRICT 
TABLE 6-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Aquatic Plant Control 
(R & H Act of 1958 and 1962) 1969 70,664 - 
Avon Harbor, N. C.1 1986 74,096 440,364 
Bay River, N. C.1 1950 44,382 49,627 
Black River, N. C. 1969 12,358 124,846 
Cashie River, N. C. 1950 40,403 15,905 
Channel Connecting Thoroughfare Bay 
with Cedar Bay, N. C.1 1975 69,610 25,615 
Channel from Pamlico Sound to Rodanthe, N. C. 1975 42,029 5,685 
Chowan River, N. C. 1950-- 
Contentnea Creek, N. C.1 1941 64,395 32,247 
Drum Inlet, N. C.1 1979 166,119 1,050,579 
Edenton Harbor, N. C.1 1960 73,750 47,642 
Fishing Creek, N. C.' 1922 22,715 8,633 
Knobb's Creek, N. C.1 , 2 19613 80,500 48,969 
Mackay Creek, N. C.' 1938 13,375 6,273 
Neuse River, N. C.1 1982 477,223 s 328,607 
Newbegun Creek, N. C. 1928* 4,802 247 
Northeast Cape Fear River, N. C.' 1950 10,688 61,139 
Pembroke Creek, N. C. 1976 60,000 - 
Perquimans River, N. C.1 1910 13,750 414 
Rollinson Channel, N. C. 1988 589,105 1,742,951 
Scuppernong River, N. C.1 1950 81,164 80,682 
Shallotte River, N. C. 1988' 18,181 527,557 
Smiths Creek (Wilmington), N. C.' 1950 8,507 18 
South River, N. C.' 1936 12,452 23,686 
Stumpy Point Bay, N. C.' 1984 268,381 736,815 
Swift Creek, N. C.' 1940 1,600 5,422 
Trent River, N. C.1 ,4 1968 115,199 143,579 
Wallace Channel, Pamlico Sound, N. C. 1965 132,834 85,299 
Waterway - Norfolk, Va. to Sounds of N. C. 1976 751,196 2,893,812 
Waterway Connecting Swanquarter 
Bay with Deep Bay, N. C. 1984 911,099 182,725 
Wrights Creek, N. C.' 1984 68,325 166,602 
1. Completed. 
2. Transferred from Norfolk District (FY 1970); Meherrin 
River, N. C., Transferred to Norfolk District. 
3. Report of Norfolk District. 
4. 8-foot modification deauthorized August 5, 1977, under 
authority of Sec. 12, PL 93-251. 
5. Includes $1,959 refund to local interests on Dawson 
Creek, N. C. 
6-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
TABLE 6-D 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Fort Fisher and Vicinity, N. C. 1984 490,000 - 
Fort Macon Park, N. C.' 1973 620,000 - 
1. Uncompleted portion of project was deauthorized 
November 17, 1986, under authority of Sec. 1002, PL 994662. 
6-26

WILMINGTON, N. C., DISTRICT 
TABLE 6-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Ararat River, Mount Airy, N.C.' 
Black River, Harnett County, N. C.' 
Broad Creek, Beaufort County, N. C.' 
Brunswick County Beaches, N. C. 
(Cape Fear to North Carolina - 
South Carolina State Line)" 
Conetoe Creek, N. C.' 
Contentnea Creek, N. C.' 
Core Creek, N. C.' 
Deep Creek, Edgecombe County, N. C.' 
Ellerbe Creek, Durham County, N. C.' 
Ellis Swamp, Gates County, N. C.' 
Filberts Creek, N. C.' 
Gapway Swamp, N. C. & S. C.','10 
Gardners Creek, N. C.' 
Genoa Sewer Facility, Wayne County, N. C.' 
Goldsboro, Neuse River, N. C. 
Howards Mill Lake, N. C. 12 
Joyce Creek, Camden County, N. C.' 
Leith's Creek, Scotland County, N. C.', '3 
Lick Run, Roanoke, Va.' 
Little Rockfish Creek, Hope Mills, N. C.' 
Little Sugar Creek, Charlotte, N. C.','10 
New River, N. C.' 
New River, Onslow County, N. C.' 
Northeast Cape Fear River, N. C.' 
Old Field Swamp, N. C.',' 0 
Pantego Creek and Cucklers Creek, N. C. 
Pasquotank River, N. C. 
Perquimans River, N. C.' 
Pungo Creek, N. C.' 
Pungo River, N. C.' 
Reddies River Lake, N. C.' 3 
Roaring River Lake, N. C.13 
Simmons Bay, N. C.'10 
South Creek, N. C.' 
Swift Creek, Pitt and Craven Counties, N. C.' 
Tar River, N. C. 
Tar River, N. C.' 
Tar River and tributaries, N. C.' 
Tar River, Princeville, N. C. 
Trent River, N. C.' 
Waccamaw River & Seven Creeks, N.C. & S.C.', 10 
White Oak Dike, Bladen and Pender 
Counties, N. C.' 
1987 
1984 
1972 
1976 
1960 
1939-1943 & 1958 
1965 
1984 
1963 
1971 
1970 
1969 
1972 
1985 
1984 
1980 
1984 
1982 
1974 
1978 
1979 
1950 & 1956 
1972 
1961 
1969 
1963 
1960 
1961 
1972 
1971 
1980 
1978 
1963 
1971 
1966 
1964 
1947 
1943 
1967 
1953 
1961 
1963 
1. Project authorized by Chief of Engineers under special 
continuing authority. 
2. Includes $17,356 refund to local interests. 
3. Adjusted to reflect actual cost. 
4. Includes $3,081 refund to local interests. 
5. Includes $116,508 refund to local interests. 
6. Includes $1,519 refund to local interests. 
7. Includes $387 refund to local interests. 
8. Includes $338 refund to local interests. 
9. Adjusted $3,000 to include preauthorization cost prior to 
FY 1960. 
10. Transferred from Charleston District, FY 1980. 
11. Reclassified to inactive category February 3, 1976. 
12. Reclassified to deferred category October 2, 1980. 
13. Transferred from Charleston District, FY 1984. 
14. Includes $1,057 refund to local interests. 
6-27 
4,901,854 
475,574 
283,846 
572,114 s 
29,867 
50,889 
236,223s 
394,055 
223,413 
138,117 6 
37,777 3 
374,005 
54,5978 
167,800 
50,430 
698,400 
606,189' 
430,151 
1,280,317 
113,657 
763,022 
51,896 
580,977 
95,873 
86,600 
517,948 
80,931 
6,366 
582,270 
296,6022,3 
985,800 
370,000 
186,435 
194,3677 
611,096 
81,266 
18,624 
22,660 
390,249 
64,769 
67,821 
623,687 
61,473 
-
-
-
- 
-
-
-
- 
623,687 
_-
-
-147 
214,286

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 6-G DEAUTHORIZED PROJECTS 
For Last Full Report Federal Contributed 
See Annual Report Date Funds Funds 
Project For Deauthorized Expended Expended 
Adkin Branch, N. C. 
AIWW - Mooring Basins 
AIWW - Peltier Creek, 
12-foot project 
AIWW - Tidal Lock in Snows Cut 
Bodie Island, N. C. 
Cape Lookout, N. C. 
Conoho Creek, N. C. 
Contentnea Creek, N. C. 
Davis, N. C. 
Fort Macon State Park, 
N. C., Remaining Work 
Harbor of Refuge, N. C. 
Hominy Swamp, N. C. 
Hyde County Dike, N. C. 
MacKay Creek, N. C. 
Mann's Harbor, N. C. 
Mill Creek, N. C. 
Mocassin Swamp, N. C. 
Morehead City Harbor, N. C., 
Jetties at Beaufort Inlet 
Moyock Creek, N. C. 
Nahunta Swamp, N. C. 
Neuse River, N. C. 
Neuse River Barrier, N. C. 
Neuse River, 300 ft.-wide 
channel in front of 
New Bern 
North River Dike, N. C. 
Ocracoke Inlet Jetty, N. C. 
Ocracoke Island, N. C. 
Roanoke River, 50 mile long 
Channel from Palmyra 
Landing to Weldon 
Rockfish Creek, N. C. 
Scuppernong River, N. C. 
Six Runs Creek, N. C. 
Sweetwater Creek, N. C. 
Thoroughfare Swamp, N. C. 
Topsail Beach and 
Surf City, N. C. 
Tranters Creek, N. C. 
Trent River, Basins and 
Access Channels at 
New Bern, N. C. 
1. Deauthorized under authority of Sec. 12, PL 93-251. 
2. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 205 of the 1948 FC Act, as 
amended. 
3. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 208 of the 1954 Flood Control 
Act. 
4. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 107 of the R&H Act of 1960 
as amended. 
5. Deauthorized under authority of Sec. 1002, PL 9.662. 
6-28 
1982 
None 
None 
None 
None 
None 
1974 
1972 
1982 
1973 
1934 
1973 
None 
1976 
1973 
1973 
1973 
1986 
1973 
1973 
None 
None 
None 
None 
1986 
1975 
1983 
1976 
1987 
1971 
1973 
1976 
None 
1974 
None 
8 Sept. 812 
5 Aug. 771 
17 Nov. 865 
23 Sept. 86' 
5 Aug. 77' 
5 Aug. 77' 
31 Mar. 782 
31 Mar. 783 
31 Mar. 824 
17 Nov. 865 
1 Nov. 81' 
31 Mar. 782 
5 Aug. 77' 
31 Mar. 782 
31 Mar. 784 
31 Mar. 782 
31 Mar. 782 
17 Nov. 865 
31 Mar. 782 
31 Mar. 782 
31 Mar. 784 
5 Aug. 77' 
5 Aug. 77' 
5 Aug. 77' 
17 Nov. 865 
17 Nov. 865 
17 Nov. 865 
31 Mar. 782 
20 Apr. 882 
31 Mar. 782 
31 Mar. 782 
31 Mar. 782 
5 Aug. 77' 
11 Jan. 852 
5 Aug. 77' 
219,477 
79,782 
4,250 
25,419 
1,396,653 
107,472 
130,900 
7,265 
116,395 
36,680 
- 
64,416 
65,673 
30,911 
129,592 
157,721 
234,032 
64,977 
64,584 
132,767 
139,339

WILMINGTON, N. C., DISTRICT 
TABLE 6-H RECONNAISSANCE AND CONDITION SURVEYS 
Project Date Survey Conducted 
None 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public Law 86-645 (preauthorization) 
TABLE 6-I 
Study Identification Fiscal Period Cost 
Bogue Inlet, N. C. 10,000 
Harkers Island Harbor, N. C. -157 
New River Inlet, N. C. 26,145 
Whittaker Creek, Oriental, N. C. 32,888 
Wilmington Harbor, N. C., Bald Head Island' 39,591 
Wilmington Harbor, N. C., Passing Lane 97,322 2 
Wilmington Harbor, N. C., Turns and Bends 136,794 3 
Wilmington Harbor, N. C., Turning Basin 63,313 
1. Section 111 project. 
2. Includes $48,446 contributed funds. 
3. Includes $52,301 contributed funds. 
6-29

TABLE 6-J DAMS AND RESERVOIRS 
See Miles Height Reservoir Power Estimated 
Section Project Name Nearest City River Above of Type Capacity Development Construc- Cost Lands Total 
in Text Mouth Dam (ft) (acre-feet) (kilowatts) tion and Damages' 
19. Cape Fear 
River Basin, 
N.C. 
23. Neuse River 
Basin. N.C. 
24. Yadkin River 
Basin, N.C.&S.C. 
29. Roanoke River 
Basin, Va. and 
N.C. 
B. Everett Jordan
2 
Howards Mill 
2 , 14 
Randleman
2 
Small reservoirs 
Falls2 
Wilson Mills 
Beulahtown 
Bakers Mills 
Little Buffalo 
Buckhorn 
Wiggins Mill 
Stantonsburg 
Great Swamp 
Black Creek 
Aycock Swamp 
Hillsboro 
Orange 
W. Kerr Scott. N.C. 
John H. Kerr, Va., and 
N.C.
2 
Philpott, Va. 
2 
Gaston, Va. and N.C.
6 
Roanoke Rapids, N.C. 
7 
Smith Mountain, Va. 
8 
Leesville, Va.
9 
Taber, Va. 
Melrose. Va. 
Randolph, Va. 
Stuart, Va. and N.C. 
Schoolfield. Va. and N.C. 
Moncure, N.C. 
Carthage, N.C. 
Randleman, N.C. 
Falls, N.C. 
Wilson Mills, N.C. 
Kenly, N.C. 
Princeton, N.C. 
Kenly, N.C. 
Wilson, N.C. 
Wilson, N.C. 
Stantonsburg, N.C. 
Fremont, N.C. 
Wilson, N.C. 
Fremont, N.C. 
Durham, N.C. 
Durham, N.C. 
Wilkesboro, N.C. 
Boydton, Va. 
Bassett, Va. 
Roanoke Rapids, N.C. 
Roanoke Rapids, N.C. 
Altavista, Va. 
Altavista, Va. 
Altavista, Va. 
Prookneal. Va. 
Chase City, Va. 
Spray. N.C. 
Danville. Va. 
Haw 
Deep 
Deep 
Various 
Neuse 
Neuse 
Little 
Little 
Little Buffalo Creek 
Contentnea Creek 
Contentnea Creek 
Tisnot Swamp 
Great Swamp 
Black Creek 
Aycock Swamp 
Eno 
Little 
Yadkin Pee Dee 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
4.3 
55.0 
85.0 
404.0 
178.7 
336.2 
144.9 
137.0 
314.2 
293.7 
275.0 
262.9 
227.8 
297.2 
265.9 
112 
106 
110 
20 to 70 + 
92 
81 
50 
53 
51 
63 
42 
36 
39 
33 
37 
136 
107 
E
E
E
E
E
CG,E 
E
E 
148 E 
753,500 
233,000 
108,000 
923,000 
374,450 
201,000 
81,000 
36,000 
13,000 
119,000 
35,000 
48,000 
18,000 
17,000 
7,000 
123,000 
57,000 
153,000 
- 85,130,000 58,370,000 
- 18,874,000 14,726,000 
- 57,956,000 59,044,000 
- 85,858,000 94,142,000 
-5,749,343 3,360,657 
144 CG,E 2,808,000 204,000 67,529,000 24,521,000 92,050,0005 
220 
108 
75 
244 
95 
54 
110 
147 
138 
126 
CG
1 1 
CG,E 
CG 
CG 
CG,E 
CG 
CG,E 
CG,E 
E
CG,E 
249,800 
432,000 
59,300 
825,000 
76,900 
34,000 
120,000 
350,000 
163,000 
248,000 
14,000 
54,000 
83,000 
41,000 
20,000 
12,000 
43,000 
48,000 
15,000 
80,000 
13,933,000 
27,000,000 
31,300,000 
28,000,000 
9,100,000 
8,000,000 
17,700,000 
22,100,000 
9,000,000 
27,800,000 
1,157,000 
3,500,000 
800,000 
3,800,000 
1,000,000 
1,700,000 
6,000,000 
4,700,000 
1,100,000 
6,400,000 
1. Includes highway, railroad, and utility relocations. 
2. For details, see individual report. 
3. Includes $3,600,000 presently allocated to water supply to be reimbursed in the future by 
local interests and $100,000 cash contribution for construction of ranger security buildings. 
4. Includes $12,900,000 presently allocated to water supply and $18,700,000 recreation and fish 
and wildlife to be reimbursed in the future by local interests. 
5. Exclusive of transmission lines. 
6. Construction completed in 1963 by Virginia Elect.ic and Power (o. 
7. Based on modified plan developed in fiscal year 1949. Construction completed June 1955 by 
Virginia Electric and Power Co. 
8. Construction completed in February 1966 by Appalachian Power Co. 
9. Construction completed in June 1963 by Appalachian Power Co. 
10. Includes cost of earth dam on Whipping Creek. 
11. Authorizing legislation provided for earth dam; concrete gravity dam constructed. 
12. Includes $1,600,000 presently allocated to recreation and fish and wildlife. 
13. Includes $69,993,000 presently allocated to water supply, $8,371,000 allocated to recreation 
and $7,836,000 to flood control to be paid by local interests during construction. 
14. Reclassified to the deferred category October 2, 1980.
Key 
Earth 
Concrete Gravity 
143,500,000' 
33,600,0002 
117,000,000'" 
38,454,000 
180,000,000' 
13,000,000 
9,300,000 
6,600,000 
1,100,000 
17,300,000 
6,700,000 
5,100,000 
1,800,000 
1,500,000 
550,000 
8,100,000 
3;500,000 
9,110,000 
0
0
C
0 
15,090,000 
30,500,000 
32,100,000 
31,800,000 
10,100,000 
9,700,000 
23,700,000 
' 
26,800,000 
10,100,000 
36,000,000 
E 
CG

WILMINGTON, N. C., DISTRICT 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
TABLE 6-K (Preauthorization) 
Study Identification Fiscal Period Cost 
Blackberry Creek, Henry County, VA. 34,970 
Buffalo Creek, Lee County, N. C. 2,283 
Dry Branch, Salem, VA. 41,596 
First Broad River, Polkville, N. C. 2,176 
Great Coharie Creek, N. C. 30,816 
Lower Creek, Lenoir, N. C.' 26,051 
Maggoddee Creek, Franklin County, VA. 1,232 
Mason Creek, VA. 87,529 
Matrimony Creek, Rockingham County, N. C. 997 
Nags Nead, N. C.2 51,342 
Neuse River, Oriental, N. C.3 32,654 
Roanoke Island, Dare County, N. C.2 5,675 
Sandy River, Danville, VA. 10,000 
South Fork Catawba River, Cramerton, N. C. 9,597 
Tinker Creek and Tributaries, VA. 65,000 
1. 
2. 
3. 
Includes $72,675 contributed funds. 
Section 103 project. 
Section 14 project. 
6-31

CHARLESTON, S.C., DISTRICT* 
This district comprises all of South Carolina (except 
local watersheds draining into the Savannah River). It 
embraces the drainage basins tributary to the Atlantic 
Ocean between Little River and Port Royal Sound, 
except watersheds of Mackey and Skull Creeks, and 
excluding Hilton Head Island. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control, SC ................. 7-1 
2. Atlantic Intracoastal Waterway Between 
Norfolk, VA and St. Johns River, FL ........ 7-2 
3. Charleston Harbor, SC ..................... 7-2 
4. Cooper River, Charleston Harbor, SC ........ 7-3 
5. Cooper River Seismic Modification, SC ...... 7-3 
6. Folly River, SC ........................... 7-4 
7. Georgetown Harbor, SC ................... 7-4 
8. Jeremy Creek, SC ......................... 7-4 
9. Little River Inlet, NC & SC ................ 7-5 
10. M urrells Inlet, SC ........................ 7-5 
11. Port Royal Harbor, SC .................... .7-6 
12. Shipyard River, SC ....................... 7-6 
13. Town Creek, SC ........................... 7-6 
14. Reconnaissance And Condition Surveys ..... 7-7 
15. Other Authorized Navigation Projects ....... 7-7 
16. Navigation Work Under Special 
Authorization .... ..................... 7-7 
Beach Erosion 
17. Other Authorized Beach Erosion 
Control Projects ......................... . 7-7 
18. Beach Erosion Work Under Special 
Authorization ............. .............. 7-7 
Flood Control 
19. Inspection of Completed Flood Control 
Projects .................................. 7-7 
20. Other Authorized Flood Control Projects ..... 7-7 
21. Flood Control Work Under Special 
Authorization ............................ 7-7 
Miscellaneous 
22. Streambank Erosion Under Special 
Authorization ............................ 7-7 
General Investigations 
23. Active Investigations ..................... 7-7 
Tables 
Table 7-A Cost and Financial Statement ...... 7-8 
Table 7-B Authorizing Legislation ........... 7-10 
Table 7-C Other Authorized Navigation 
Projects .......................... 7-13 
Table 7-D Navigation Work Under Special 
Authorization .................... 7-13 
Table 7-E Other Authorized Beach Erosion 
Projects .......................... 7-13 
Table 7-F Other Authorized Flood Control 
Projects .......................... 7-14 
Table 7-G Flood Control Work Under 
Special Authorization ............. 7-14 
Table 7-H Other Authorized Streambank 
Erosion Projects .................. 7-14 
Table 7-I Active General Investigations ....... 7-15 
*All costs and financial statements for projects are 
listed at the end of this chapter. All other tables are referenced 
in text and also appear at the end of this 
chapter. 
Navigation 
1. AQUATIC PLANT CONTROL, S.C. 
Location. The project includes all public waters in 
the State of South Carolina. 
Existing Project. The project provides for the control 
and progressive eradication of noxious aquatic 
plant growths from public waters in the combined 
interest of navigation, flood control, drainage, agriculture, 
fish and wildlife conservation, and public 
health. 
Local Cooperation. Local interests must agree to 
hold the United States free from damages that may 
occur from operations performed in connection with 
this project and contribute 50 percent of the total cost. 
The South Carolina Water Resources Commission is 
designated as the State's lead agency for aquatic plant 
management and meets local interest requirements. 
Operations and results during fiscal year. Aquatic 
plants now infest approximately 30,000 acres, with the 
worst problems being in Lake Marion. During FY 89, 
2,445 acres of aquatic plants in 23 water bodies were 
treated with herbicides. Grass carp were purchased 
7-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
and stocked in three lakes to control aquatic plants in 
4,105 acres. 
The total cost of work performed in FY 89 was 
$491,838. 
Condition at end of fiscal year. The project is ongoing. 
Federal costs for the project to date have been 
$3,544,880 for new work. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA. AND ST. JOHNS 
RIVER, FL (CHARLESTON DISTRICT) 
Location. The project starts near Little River at the 
North Carolina-South Carolina state line and extends 
generally south along the coast of South Carolina 62 
miles to Winyah Bay; thence 63.5 miles to Charleston; 
thence 84.5 miles to and including Port Royal Sound; a 
total of 210 miles (See National Ocean Survey Charts 
Nos. 11513, 11521, 11531, 11534, and 11535.) 
Previous projects.For further details see page 613 of 
Annual Report for 1932. 
Existing project. The project provides for a waterway 
twelve feet deep and not less than 90 feet wide with 
a branch channel of the same dimensions to McClellanville 
and construction of three bridges crossing the 
waterway in Horry County, South Carolina. (See table 
at end of chapter for acts authorizing existing project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are rail-water terminals 
at Georgetown, Charleston, Johns Island, and Port 
Royal and numerous open-pile wharves mostly for 
shipping agricultural products, fish, oysters, pulpwood, 
wood products, and petroleum products. Marinas are 
located at convenient intervals along the waterway 
where limited supplies and repair facilities are available 
for both commercial vessels and pleasure craft. 
Facilities are considered adequate for existing commerce 
and recreation requirements. 
Operations and results during fiscal year. Maintenance: 
Maintenance was performed by pipeline 
dredge: (a) in the Winyah Bay to Charleston area, removing 
1,098,845 cubic yards of material at a cost of 
$785,227 and (b) in the Atlantic Intracoastal Waterway 
(AIWW) to Port Royal area, removing 503,204 cubic 
yards at a cost of $443,869. The mosquito abatement 
control contract costs were $3,670. The cost of operating 
the Snagboat Snell in the Charleston to Little River area 
was $120,950. Costs of $236,683 were incurred for 
contract dike management. Condition and operation 
studies, natural resource management, inspections and 
reports, real estate, project operations management, 
lands and damages, water control management, bank 
stabilization, engineering and design, and supervision 
and administration costs were $747,202. 
Condition at end of fiscal year. Existing project was 
c1o9m36p. letFede deinr al1 9c4o0s; tst horfe ee xbisrtiidngge sp rwojeercet ctoo mdpalteet ehda vine 
been $7,345,888 for new work and $49,008,381 for maintenance, 
for a total of $56,354,269. 
3. CHARLESTON HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina about 15 miles south of the midpoint of the 
coastline, 50 miles southwest of Winyah Bay, S.C., and 
80 miles northeast of the mouth of Savannah River. (See 
National Ocean Survey Charts Nos. 11521 and 11524.) 
Previous projects. The existing project provides for 
a channel 35 feet deep with varying widths from the 
Atlantic Ocean to the mouth of Goose Creek, a total of 
26.3 miles, together with a 35-foot depth by 500-foot 
width channel via Town Creek. Also, a ten foot depth by 
110-foot width channel on the Mount Pleasant side of the 
harbor into Shem Creek to U.S. Highway 17 Bridge, 
and a 30-foot anchorage basin in the lower harbor 
between Castle Pinckney and Fort Moultrie. A 40-foot 
channel estimated to cost $6,060,000 (1960) was 
authorized to be executed when found necessary in the 
interest of national defense from the 40-foot contour in 
Atlantic Ocean to U.S. Naval Base. For further details 
see page 425 of the Annual Report for 1962; page 1808 of 
the Annual Report for 1915; page 579 of the Annual 
Report for 1926; and page 562 of the Annual Report for 
1938. 
Existing project. The project as authorized by the 
1986 Water Resources Development Act provides for 
deepening of the 35-foot channel to 40 feet (42 feet in the 
ocean bar and entrance channel) from the 42-foot ocean 
contour to Goose Creek, a total distance of 26.9 miles, 
construction of one turning basin, modification of existing 
turning basins, deepening and modification of the 
anchorage basin, deepening Shipyard River to 38 feet, 
maintain the Wando River Channel to 35 feet at federal 
expense and the deepening of this channel to 40 feet. 
(See table at end of chapter for acts authorizing existing 
project.) 
Local cooperation. Local interests have fully complied 
with their responsibility to date. 
Terminal facilities. Piers and slips extend for about 
one mile along the eastern waterfront of the City of 
Charleston with an additional mile of marginal 
wharves. The South Carolina State Ports Authority 
operates eight piers for fruit, wood, cold storage 
facilities and general cargo, a grain elevator and a beltline 
railway which serves the entire Cooper River 
waterfront. Modern facilities are also at wharves of 
seven major petroleum companies including storage 
tank farms. Modern facilities for marine repairs and 
servicing are available at Detyens Shipyard, located 
approximately ten miles northeast of Charleston on the 
Wando River. The U.S. Navy Department has modern 
facilities for maintenance of naval vessels including 
nuclear-powered submarines. Loading docks and 
storage areas for missile-carrying type vessels have also been constructed and are being operated by the U.S. 
Navy. For further details see Port Series No. 13, 1980, 
Corps of Engineers. 
7-2

CHARLESTON, SOUTH CAROLINA DISTRICT 
Operations and results during fiscal year. New 
Work: All new work is cost shared 75/25, federal/nonfederal 
respectively. Contract dredging was performed: 
(a) by pipeline dredge in the Rebellion to Folly 
Reach during October 1988-May 1989, removing 
877,918 cubic yards of material, at a cost of $1,156,660, 
(b) in the Shutes to Myers Bend Reach by pipeline 
dredge during October 1988-February 1989, removing 
1,044,777 cubic yards, at a cost of $876,882, (c) by 
hopper dredge in the Entrance Channel during October 
1988-April 1989, removing 2,363,653 cubic yards, at a 
cost of $3,929,297, (d) in Shipyard River by pipeline 
dredge during the period April 1989-June 1989 
removing 295,868 cubic yards at a cost of $273,048, (e) 
during May-September 1989 by pipeline dredge in the 
Wando River, removing 1,328,117 cubic yards of 
material at a cost of $1,655,070, and (f) during June- 
September 1989 in the Entrance Channel (Stations 
+28+00 to -370+00) by hopper dredge, removing 
1,085,085 cubic yards of material at a cost of $1,834,819, 
for a total contract cost of $9,725,776. Cultural resources 
costs were $2,226, engineering and design and 
supervision and administration costs were $835,427 
and $434,889, respectively. Federal costs for the project 
were $8,248,738. Maintenance: Maintenance dredging 
was performed by pipeline dredges (a) on Shoal 6a 
during the period May-September 1989, removing 
90,886 cubic yards of material, at a net cost of $278,062, 
(b) in Shipyard River during April-June 1989, removing 
83,450 cubic yards of material at a cost of $77,837, 
(c) in the Anchorage Basin during the months of 
October 1988-May 1989, removing 493,587 cubic yards 
at a cost of $1,059,652 and (d) on Shoal 6a and Shoal 6a 
Turning Basin during the period October 1988- 
February 1989, removing 96,586 cubic yards at a cost of 
$231,885. Total contract maintenance dredging cost for 
FY 89 was $1,647,436. Dike management costs were 
$701,214. The cost of mosquito abatement for FY 89 was 
$59,938. Condition and operation studies, water control 
management, natural resource management, project 
operations management, lands and damages, engineering 
and design, and supervision and administration 
costs were $754,807. 
Condition at end of fiscal year. Jetties protecting 
the entrance channel across the bar were completed in 
1895. The previous project was completed in October 
1962 except for the national defense portion. Federal 
costs under the previous project to date have been 
$10,165,564 for new work and $101,269,918 for maintenance, 
a total cost of $111,435,482. Federal costs 
through FY 89 for the existing project have been 
$11,640,460 for new work. No new work maintenance 
costs have been incurred. 
4. COOPER RIVER, CHARLESTON HARBOR, 
S.C. 
Location.Cooper River is located in Charleston and 
Berkeley Counties, S.C., and empties into the Atlantic 
Ocean at Charleston (See National Ocean Survey 
Charts Nos. 11521 and 11524.) 
Existing project. The major cause of the shoaling 
problem in Charleston Harbor was the diversion of 
fresh water from the Santee River through Pinopolis 
Dam into the salt water of Charleston Harbor, which 
caused density currents which trapped sediments resulting 
in a phenomenal rate of depostion. The most 
practical solution of the shoaling problem was to 
redivert most of the Santee River waters above 
Pinopolis Dam back into the lower Santee River 
through a canal beginning at Lake Moultrie and 
extending to the Santee River, as authorized by the 1968 
River and Harbor Act, provided that the discharge 
through the existing Pinopolis Hydroplant be reduced 
to a flow which would not establish a density current in 
the harbor. This flow was estimated at 3,000 cubic feet 
per second (cfs) during the design phase of the project, 
but after operational tests this flow is estimated at 4,500 
cfs. The excess water impounded in Lake Moultrie is 
being directed through a new canal above St. Stephen, 
South Carolina, to enter the Santee River at a point well 
below the Lake Marion Spillway (Wilson Dam). A new 
hydroelectric facility was constructed on the new canal 
at the edge of the swamp adjacent to the Santee River. 
This plant replaces those features made less effective at 
Pinopolis through curtailment of flows. The average 
flow of 11,000 cfs at the new powerplant, plus the 4,500 
cfs average release planned for Pinopolis, approximates 
the historical average flow at Pinopolis. The three 
generators at the new plant are rated at 28,000 kilowatts 
each, for a total of 84,000 kilowatts. In the interest 
of fish and wildlife resources of the area, the project includes 
a herring lift at the new powerhouse site and a 
relocated fish hatchery. 
Estimated cost of the project (1985) is $191,600,000, 
all Federal. (See table at end of chapter for acts 
authorizing existing project.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
Work: Funds were received for initiation of construction 
during FY 75. Costs during FY 89 were $9,484 for 
engineering and design and supervision and administration. 
Maintenance: Funds of $3,745,712 were spent 
for maintenance of completed work. 
Condition at end of fiscal year. Construction was 
initiated March 1977. The project is 99% complete. The 
power-on-line date was March 1985. Federal costs for 
the existing project to date have been $189,808,221 for 
new work and $15,589,011 for maintenance, a total of 
$205,397,232. 
5. COOPER RIVER SEISMIC MODIFICATION, 
S.C. 
Location. The Cooper River Seismic Project is 
located in Berkeley County, South Carolina, about 50 
miles north of Charleston, South Carolina. 
Existing project. The Santee-Cooper Project was 
7-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
constructed in the early 1940's using the latest state-ofthe-
art design for that time. The project is currently 
licensed by the Federal Energy Regulatory Commission 
(FERC) as project number 199. The FERC requires 
that the project receive independent inspections 
at least once every five years. It was during the 1977 
inspection that the seismic deficiency of both the West 
and North Dams was noted. This was confirmed again 
in the 1982 inspection. As a result of studying the 
possible consequences of the loss of both dams, the S.C. 
Congressional Delegation introduced legislation which 
was approved in the 1983 Supplemental Appropriations 
Act to provide $2 million for design and $20 million 
for construction of remedial measures. The design 
and construction responsibility was assigned to the U.S. 
Army Corps of Engineers. The Corps began to study 
various alternatives to provide remedial measures for 
the liquifiable foundation of the West Dam in August 
1983. 
Current estimated cost of the project is $30,400,000, of 
which $29,500,000 is Federal and $900,000 is non- 
Federal. 
Local cooperation. Requirements are fully satisfied. 
An LCA was signed on 29 March 1988. 
Operations and results during fiscal year. New 
Work: The contract was advertised on 7 March 1988 
and awarded on 29 April 1988 for $21,069,540. As of the 
end of FY 89, construction was 66% complete. FY 89 
costs totaled $13,123,808 with $348,958 being used for 
engineering and design, $962,623 for supervision and 
administration, and $11,812,227 for the contract. 
Federal costs for the contract to date have been 
$12,949,325. 
Condition at end of fiscal year. Federal costs thru 
FY 89 for the existing project have been $18,001,788. 
6. FOLLY RIVER, S.C. 
Location. The project begins in Folly River and Folly 
Creek north of the Town of Folly Beach and follows a 
southwesterly course into the Atlantic Ocean. (See 
National Ocean Survey Chart No. 11521.) 
Existing project. The project provides: an entrance 
channel, eleven feet deep by 100 feet wide extending 
from the Stono River one mile through the ocean bar; a 
channel within Folly River nine feet deep and 80 feet 
wide, extending three miles downstream from U.S. 
Highway 171 to the confluence of Folly and Stono 
Rivers; and a channel within Folly Creek nine feet deep 
by 80 feet wide extending three miles downstream from 
Highway 171 to the confluence with Folly River. 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging was performed in Folly 
River by the sidecaster dredge Fry during June-July 
1989, at a cost of $213,900. Costs incurred for maintenance 
dredging performed in FY 88 were $14. Condition 
and operations studies, water control management, 
inspections and reports, engineering and design, 
and supervision and administration costs were $46,002. 
Condition at end of fiscal year. The existing project 
was completed in FY 1979. Federal costs for the existing 
project to date have been $337,736 for new work and 
$2,087,662 for maintenance, a total of $2,425,398. 
7. GEORGETOWN HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina 50 miles northeast of Charleston Harbor and 
90 miles southwest of the entrance to Cape Fear River, 
North Carolina. (See National Ocean Survey Chart No. 
11532.) 
Previous projects. For further details see page 1806 
of Annual Report for 1915; page 549 of Annual Report 
for 1938; and page 442 of Annual Report for 1944. 
Existing project. The authorizations provide for a 
channel 27 feet deep with varying widths of 600 feet to 
400 feet from the Atlantic Ocean to and including a 
turning basin at the U.S. Highway 17 bridge over 
Sampit River, with a side channel 2,400 feet long and 
not less than 200 feet wide leading to a turning basin at 
the upper end of the built-up portion of the city waterfront, 
a total of 17.9 miles. The project also provides for 
the continued maintenance to a depth of 18 feet and a 
width of 400 feet for the bypassed portion of Sampit 
River opposite the City of Georgetown. (See table at end 
of chapter for acts authorizing existing project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. Terminal facilities at the Port of 
Georgetown, suitable for oceangoing vessels, consist of 
one marginal concrete pier and one of creosoted-timber 
construction. For intracoastal waterway traffic there 
are a number of smaller wharves and landings along 
the Georgetown waterfront on the old channel. For 
further details, see Port Series No. 13, 1980, Corps of 
Engineers. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging was performed (a) in 
the Sampit River and Upper Winyah Bay from November 
1988-April 1989, removing a total of 1,757,228 
cubic yards of material at a cost of $1,779,295. Contract 
dike management costs were $294,901.Mosquito abatement 
control costs were $28,062. Water control 
management, natural resources management, condition 
and operation studies, project operations management, 
income credits to operations, engineering and 
design and supervision and administration costs were 
$743,155. 
Condition at end of fiscal year. The existing project 
was completed in 1951. The jetties were completed in 
1903-1904. Federal costs for the existing project to date 
have been $4,615,903 for new work and $50,411,796 for 
maintenance, a total of $55,027,699. 
8. JEREMY CREEK, S.C. 
Location. Jeremy Creek is located at McClellanville, 
S.C. approximately 40 miles northeast of Charleston 
7-4

CHARLESTON, SOUTH CAROLINA DISTRICT 
and 20 miles southwest of Georgetown. (See National 
Ocean Survey Charts Nos. 11531 and 11518.) 
Existing project. The dredging of Jeremy Creek or 
"Side Channel to McClellanville" was authorized as a 
part of the channel from Charleston to McClellanville 
(or part of what is now the Atlantic Intracoastal Waterway) 
by the River and Harbor Act of 2 March 1907. 
The project provides for a waterway twelve feet deep at 
mean low water and a width of not less than 90 feet. 
Local cooperation. Local requirements have been 
met by the S.C. Coastal Council. 
Terminal facilities. There are three shrimping 
facilities, one oyster packing shed, a crabbing operation, 
an icehouse, a fuel dock and a public launching 
ramp located on Jeremy Creek. The commercial 
facilities are privately owned, but are open to all on an 
equal basis. The existing facilities are considered adequate 
for present and near future commerce. There are 
areas along the east bluff shore available for the expansion 
of existing facilities or the construction of new 
ones. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging was performed during 
the period January 1989, removing 57,834 cubic yards 
of material at a cost of $43,546. Condition and 
operations studies, water control management, inspection 
and reports, and project operations management 
costs were $10,515. 
Condition at end of fiscal year. Federal costs of 
existing project to date have been $49,987 for new work 
and $64,897 for maintenance, a total of $114,884. 
9. LITTLE RIVER INLET, N.C. AND S.C. 
Location. The project is located near the North 
Carolina-South Carolina state line. Little River enters 
the Atlantic Ocean at Little River Inlet at the state line 
and affords the only connection between the Atlantic 
Intracoastal Waterway and the ocean along 68 miles of 
coastline from Shallotte, N.C. to Georgetown, S.C. (See 
National Ocean Survey Chart No. 11535.) 
Existing project. The project provides for an entrance 
channel twelve by 300 feet across the ocean bar; 
thence a ten by 90-foot inner channel to the Atlantic Intracoastal 
Waterway. The entrance channel is stabilized 
by jetties extending seaward 3,200 feet and 3,000 
feet long on the north and south sides of the inlet, 
respectively. 
Emergency dredging on an annual basis was 
authorized by the Water Resources Act of 1974. 
Previous work was done under the authority of the 
River and Harbor Act of 1945, Section 3, P.L. 79-14. 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are eight marinas, 
numerous private docks, and several public boat ramps 
located in or near Little River. It is expected that 
existing facilities will expand and new ones will be 
added as demands for services exceed current capacity. 
Operations and results during fiscal year. New 
Work: None. Maintenance: A 5-year monitoring program 
was initiated in 1981 to provide information for 
management of the project and to determine the effect 
of the project on nearby coastal areas. Charleston District 
(CESAC) collects the data and Coastal Engineering 
Research Center (CERC) performs data analysis 
and interpretation. Following conclusion of the initial 5- 
year monitoring plan (February 1986), CERC presented 
results of their preliminary analysis to CESAC 
and South Atlantic Division at a meeting in Charleston 
on 8 April 1986. The data indicated that coastal 
processes in the vicinity of the inlet have not reached an 
equilibrium condition and recommended continued 
monitoring at a reduced level. This effort is currently 
underway. Condition and operation studies and water 
control management, inspection and reports, project 
operations management, and engineering and design 
costs were $57,918. 
Condition at end of fiscal year. The initial construction 
contract was awarded 14 January 1981. The 
project was completed in FY 1984. Federal costs for the 
existing project have been $17,037,428 for new work 
and $2,413,462 for maintenance, a total of $19,450,890. 
10. MURRELLS INLET, S.C. 
Location. The project is located on the coast of South 
Carolina, in Georgetown County, about 13 miles southwest 
of the City of Myrtle Beach. The inlet is the ocean 
entrance through a barrier beach to several tidal 
streams in the Murrells Inlet-Garden City estuarine 
area. (See National Ocean Survey Chart No. 11535.) 
Existing project. The project provides for an entrance 
channel twelve by 300 feet across the seaward 
bar; thence a ten by 90-foot inner channel to a turning 
basin at the old Army crashboat dock. The entrance 
channel is stabilized by ocean jetties extending seaward 
3,445 feet and 3,319 feet on the north and south sides of 
the inlet, respectively. The recreational project includes 
a walkway on the south jetty with access road and 
parking area. Emergency dredging on an annual basis 
was authorized by the Water Resources Act of 1974. 
Previous work was done under the authority of the 
River and Harbor Act of 1945, Section 3, P.L. 79-14. 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are five marinas and 
numerous private docks located about the Murrells 
Inlet Harbor. There are several public boat ramps in 
the area. Facilities are expected to be expanded and 
new ones added as demands for services outstrip 
capacity. 
Operations and results during fiscal year. New 
Work: None. Maintenance: No maintenance dredging 
was performed during FY 89. 
A monitoring program was initiated in April 1978 to 
provide site specific information for proper management 
of the project and to provide data on coastal 
response to the project. Charleston District collects 
most of the data and Coastal Engineering Research 
7-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Center (CERC) performs data analysis and interpretation. 
The monitoring program has been adjusted 
several times based on CERC recommendations. 
Currently the program includes daily littoral environmental 
observations (LEO), annual aerial photography, 
jetty surveys and site inspections, semi-annual surveys 
of beaches and the deposition basis. Channel surveys 
are not scheduled but are conducted on an "as needed" 
basis. 
Results of the monitoring program have led to 
recommendations for dredging the deposition basin, 
nourishment of a reach of eroded beach at North Litchfield 
Beach and erosion protection of a section of the 
south jetty sand dike. Natural resource management, 
lands and damages, condition and operation studies, 
water control management costs and engineering and 
design, supervision and administration costs were 
$124,252. 
Condition at end of fiscal year. The existing project 
was completed in 1981. Federal costs for the existing 
project to date have been $13,407,465 for new work and 
$3,442,935 for maintenance, a total of $16,850,400. 
11. PORT ROYAL HARBOR, S.C. 
Location. The harbor is located on the coast of South 
Carolina 47 miles southwest of Charleston Harbor and 
23 miles northeast of Savannah River, Georgia. (See 
National Ocean Survey Chart No. 11516.) 
Existing project. The authorized project provides 
for a channel from the ocean through Port Royal Sound 
to Port Royal, South Carolina, 27 feet deep and 500 feet 
wide across the ocean bar and in Port Royal Sound for 
approximately 12.7 miles, thence 24 feet deep and 300 
feet wide in Beaufort River and Battery Creek for approximately 
8.3 miles to and including a turning basin 
27 feet deep and 600 feet wide opposite the wharf of the 
South Carolina State Ports Authority. (See the table at 
the end of the chapter for acts authorizing the existing 
project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. The South Carolina State Ports 
Authority constructed a marginal concrete wharf and 
operates modern terminal facilities which are considered 
adequate for present commerce of the port. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging was performed in the 
Entrance Channel by hopper dredge during the period 
August 1989 to September 1989, removing 31,091 cubic 
yards of material, at a cost of $400,000. Natural resource 
management, condition and operation studies, 
water control management, project operations management, 
engineering and design and supervision and 
administration costs were $73,388. 
Condition at end of fiscal year. The existing project 
was completed in 1959. Federal costs for the existing 
project to date have been $1,786,100 for new work and 
$7,403,970 for maintenance, a total of $9,190,070. 
12. SHIPYARD RIVER, S.C. 
Location. This waterway is a tidal tributary of 
Charleston Harbor, South Carolina. It has its source 
about one-half mile below the U.S. Naval Base, whence 
it flows southerly about three miles and empties into the 
Cooper River about three-fourths miles above Drum 
Island. (See National Ocean Survey Chart No. 11524.) 
Previous projects. For details, see page 610 of 
Annual Report for 1932 and page 463 of Annual Report 
for 1944. 
Existing project. The authorized project provides 
for a channel 30 feet deep from Cooper River to 
MacAlloy Corporation's plant, including two turning 
basins, one opposite Gulf Oil Corporation Terminal and 
another at the upper end of project. (See table at end of 
chapter for acts authorizing existing project.) 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. In the lower three-quarters of a 
mile of the channel are large marginal wharves of the 
Gulf Oil Corporation and Shipyard River Terminal 
Company. These wharves accommodate deep-draft, 
oceangoing vessels for handling petroleum products, 
coal and fertilizer materials. In the upper channel is 
MacAlloy Corporation's wharf for handling ores. For 
further details see Port Series No. 13, 1980, Corps of 
Engineers. 
Operations and results during fiscal year. Maintenance: 
No maintenance dredging was performed. FY 
1989 diking costs were $72,916. Condition and operations 
studies, water control management, project 
operations management, engineering and design, and 
supervision and administration costs were $23,272. 
Condition at end of fiscal year. The existing project 
was completed in 1951. Federal costs under the existing 
project to date have been $487,824 for new work and 
$9,290,273 for maintenance for a total of $9,778,097. 
13. TOWN CREEK, S.C. 
Location. Town Creek Channel begins at the AIWW 
directly south of the Town of McClellanville in Charleston 
County, S.C. The channel follows Five Fathom 
Creek in a southerly direction to the Atlantic Ocean. 
(See National Ocean Survey Chart No. 11531.) 
Existing project. The project provides a channel ten 
feet deep by 80 feet wide from the AIWW to the mouth 
of Five Fathom Creek, a distance of 6.2 miles. The project 
includes an entrance channel twelve feet deep by 
100 feet wide across the ocean bar, a distance of 4.0 
miles. (See table at end of chapter for acts authorizing 
existing projects.) 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. Maintenance: 
Maintenance dredging was performed in the 
entrance channel by the sidecaster dredge Schweizer 
during May-July 1989 at a cost of $347,200. Condition 
and operations studies, water control management, 
inspection and reports, project operations manage- 
7-6

CHARLESTON, SOUTH CAROLINA DISTRICT 
ment, engineering and design, and supervision and 
administration costs were $45,759. 
Condition at end of fiscal year. The existing project 
was completed in 1975. Federal costs under the existing 
project to date have been $219,521 for new work and 
$3,395,130 for maintenance, a total of $3,614,651. 
14. RECONNAISSANCE AND CONDITION 
SURVEYS 
Costs incurred for condition surveys were as follows: 
Adams Creek, S.C. $1,075 
Ashley Creek, S.C. 345 
Edisto River, S.C. 200 
Great Pee Dee River, S.C. 200 
Lynches River & Clark Creek, S.C. 200 
Mingo Creek, S.C. 200 
Salkehatchie River, S.C. 200 
Santee River, S.C. 200 
Village Creek, S.C. 1,928 
Waccamaw River, N.C. & S.C. 200 
Wateree River, S.C. 200 
Total $4,948 
15. OTHER AUTHORIZED NAVIGATION 
REPORTS 
(See Table 7-C.) 
16. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Work Under Special Authorization Pursuant 
to Section 107, Public Law 86-645, as amended 
(Preauthorization) and Section III, Public Law 90-433, 
as amended. (See Table 7-D.) 
Snagging and clearing for navigation (Sec. 3 of 1934 
River and Harbor Act, Public Law 14, 79th Congress.) 
None. 
Beach Erosion 
17. OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
(See Table 7-E.) 
18. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, 1960 River & Harbor Act, as amended, consisted of 
one reconnaissance study on Pawleys Island, S.C. FY 
1989 costs on this study were $7,907. 
Flood Control 
19. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections 
were made of the following projects during June 1989: 
Buck Creek, Cow Castle Creek, Cowpens Swamp, 
Crabtree Swamp, Eagle Creek, Gapway Swamp, 
Kingstree Branch, N. Edisto River, Pompion Hill 
Chapel, Sawmill Branch, Scotts Creek, Simpson Creek, 
Shot Pouch Creek, Todd Swamp, Turkey Creek, and 
Wilson Branch. Responsible local officials were advised 
of inadequacies in maintenance and operation on local 
flood protection works when appropriate. Cost for the 
period was $16,353. 
20. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 7-F.) 
21. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (Preauthorization). 
(See Table 7-G). 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th 
Congress, and Antecedent Legislation). 
Federal costs for FY 1989 were $176,116 for Flood 
Control and Coastal Emergencies, $2 for Inspection of 
Non-Federal Levees, and $147,950 for the National 
Emergency Preparedness Program. 
Miscellaneous 
22. STREAMBANK EROSION UNDER 
SPECIAL AUTHORIZATION 
The only streambank erosion activity pursuant to 
Section 14 of the 1946 Flood Control Act (as amended) 
was Atlantic Intracoastal Waterway (AIWW), Myrtle 
Beach Wastewater Treatment Facility, S.C. and 
AIWW, Laurel Hill Bluff, S.C. FY 1989 costs for these 
projects were $2,519 and $25,000, respectively. (See 
Table 7-H for previous work in this category. 
General Investigations 
23. ACTIVE INVESTIGATIONS 
See Table 7-I which covers: Surveys, Collections, and 
Study of Basic Data, and Research and Development 
Activities. 
7-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 7-A 
See 
Section 
in 
COST AND FINANCIAL STATEMENT 
Text Project 
1 Aquatic Plant 
Control, SC 
(Regular Funds) 
(Contributed Funds) 
2 Atlantic Intracoastal 
Waterway 
Between Norfolk, 
Va. and the St. 
Johns River, FL 
3 Charleston Harbor, 
SC 
(Regular Funds) 
(Contributed Funds) 
4 Cooper River, 
Charleston Harbor, 
SC 
5 Cooper River Seismic 
Modification, SC 
6 Folly River, SC 
7 Georgetown Harbor, 
SC 
8 Jeremy Creek, SC 
9 Little River Inlet, 
NC and SC 
(Regular Funds) 
(Contributed Funds) 
.--- --.- , .. r" _ 
7-8 
--- Funding 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp, 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
FY 86 
638,000 
585,625
00 
00 
3,024,000 
3,080,530
00 
4,476,000 
4,575,020
0
0 
4,700,000 
5,804,764 
2,948,000 
3,349,732 
198,000 
233,086
00 334,000 
325,791
00 
3,242,000 
3,263,966
00 
00 
-33,000 
437 
87,000 
94,771
0
0 
FY 87 
566,000 
602,642
00 
00 
754,000 
674,155
00 
2,831,000 
2,924,406
00 
0 
426,587 
3,572,000 
3,863,929 
745,000 
749,898
00 
328,000 
343,680
00 
3,544,000 
3,241,898
00 
5,000 
4,073
00 
52,000 
55,353
00 
FY 88 
550,000 
337,950
00 
00 
1,328,000 
1,011,405 
5,385,000 
2,769,772 
4,294,000 
4,067,062 
1,297,000 
923,083 
-13,000 
37,675 
2,226,000 
2,192,630 
20,755,000 
1,786,164
0
0 
313,000 
313,587
0
0 
1,292,000 
1,493,218
00 
6,000 
3,763
00 
88,000 
78,974
00 
FY 89 
427,000 
491,838
00 
00 
2,019,400 
2,337,601 
7,045,000 
8,248,738 
2,914,900 
3,163,395 
2,763,000 
2,749,580 
125,000 
9,484 
3,764,200 
3,745,712 
3,602,000 
13,123,808
0
0 
260,600 
259,916
00 
2,893,400 
2,845,413
00 
51,000 
54,061
00 
52,000 
57,918
00 
Total Cost to 
Sept. 30, 1989 
3,710,605 
3,544,880 
52,028 
52,028 
7,455,3781/ 
7,455,3781/ 
49,193,4042/ 
49,077,8032/ 
23,217,5643/ 
21,806,0243/ 
101,320,4874/ 
101,269,9184/ 
4,060,000 
3,672,663 
191,594,583 
189,808,221 
15,841,200 
15,589,011 
27,600,000 
18,001,788 
337,736 
337,736 
2,089,600 
2,087,662 
7,061,7555/ 
7,061,7555/ 
50,723,1806/ 
50,526,3526/ 
49,987 
49,987 
65,000 
64,897 
17,037,428 
17,037,428 
2,417,676 
2,413,462 
1,521,920 
1,521,920

CHARLESTON, SOUTH CAROLINA DISTRICT 
TABLE 7-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
10 Murrells Inlet, SC New Work: 
(Regular Funds) Approp. 0 0 0 0 13,419,240 
Cost -24 342 0 0 13,407,465 
Maint: 
Approp. 107,600 118,100 2,111,000 143,000 3,538,2697/ 
Cost 103,438 125,715 2,104,198 124,252 3,509,9357/ 
(Contributed Funds) New Work: 
Approp. 0 0 0 0 1,380,000 
Cost 0 0 0 0 1,379,148 
11 Port Royal Harbor, New Work: 
SC Approp. 0 0 0 0 1,786,100 
Cost 0 0 0 0 1,786,100 
Maint: 
Approp. 892,000 52,000 84,000 474,000 7,416,408 
Cost 896,186 51,385 72,789 473,388 7,403,970 
12 Shipyard River, New Work: 
SC Approp. 0 0 0 0 491,9748/ 
Cost 0 0 0 0 491,9748/ 
Maint: 
Approp. 106,000 34,500 327,000 40,000 9,293,692 
Cost 107,700 32,891 273,810 96,188 9,290,273 
13 Town Creek, SC New Work: 
(Regular Funds) Approp. 0 0 0 0 219,521 
Cost 0 0 0 0 219,521 
Maint: 
Approp. 325,000 422,000 352,000 393,000 3,396,000 
Cost 525,242 435,622 352,155 392,959 3,395,130 
(Contributed Funds) New Work 
Approp. 0 0 0 0 8,600 
Cost 0 0 0 0 8,600 
1/ Includes $109,490 for new work for previous project. 
2/ Includes $69,422 for maintenance of previous projects. 
3/ Includes $10,165,564 for previous projects and $622,000 for 
Preconstruction, Engineering and Design. 
4/ Includes $401,989 for maintenance of previous projects. In 
addition, $600 for maintenance expended from contributed 
funds. 
Includes $2,445,852 for new work for previous projects. 
Includes $114,556 for maintenance of previous projects. 
Includes $67,000 accomplished under authority of Section 3, 
P. L. 79-11 incurred through FY 73. 
Includes $4,150 for new work on previous projects. 
7-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 7-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of Oct. 27, 1965 
R&H Act of Sep. 19, 1890 
R&H Act of June 13, 1902 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 2, 1907 
R&H Act of Mar. 3, 1925 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 19351' 
R&H Act of Aug. 30, 19352 
R&H Act of Aug. 30, 19352 
R&H Act of Aug. 26, 1937 
R&H Act of Mar. 2, 1945 
R&H Act of June 18, 1878 
R&H Act of Aug. 8, 1917 
R&H Act of July 18, 1918 
R&H Act of Jan. 21, 1927 
R&H Act of Oct. 17, 1940 
R&H Act of Mar. 2, 1945 
R&H Act of Sep. 3, 1945 
AQUATIC PLANT CONTROL, SC 
(See Section 1 of text.) 
Provides for control and progressive eradication of 
water hyacinth, alligatorweed, Eurasian water-milfoil 
and other obnoxious acquatic plant growths from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the U.S., in combined 
interest of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation, public 
health and related purposes, including continued research 
for development of most effective and economic 
control measures in cooperation with other Federal and 
state agencies. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., AND ST. JOHNS 
RIVER, FL. 
(See Section 2 of text.) 
Channel from Minim Creek to Winyah Bay. 
Channel from Charleston to a point opposite 
McClellanville. 
Branch channel to McClellanville. 
Extending the channel to Minim Creek, thence through 
the Esterville-Minim Canal to Winyah Bay. 
Cut across the Santee Delta at Four Mile Creek. 
Widening and deepening the waterway from Charleston 
to Beaufort. 
A waterway eight feet deep and 75 feet wide from Cape 
Fear River to Winyah Bay. 
Construction of bridges across the waterway in Horry 
County, S.C. 
Cutoff between Ashepoo and Coosaw Rivers. 
Enlarging the channel from Winyah Bay to Charleston 
including the branch channel to McClellanville, to 
depth of ten feet and bottom width of 90 feet. 
Increasing dimensions of waterway to twelve feet deep 
and 90 feet wide. 
Anchorage Basin 125 feet wide, 335 feet long, twelve 
feet deep, near Myrtle Beach, S.C.4 
(Deauthorized by 1986 WRDA) 
CHARLESTON HARBOR, S.C. 
(See Section 3 of text.) 
2 jetties.5 
Increase in depth to 30 feet with width of 500 feet 
between the jetties and 1,000 feet seaward thereof. 
The 40-foot channel to the Naval Base. 
Act provided that the 40-foot channel should not be 
undertaken "until the proposed new drydocks at this 
navy yard, carrying a depth of 40 feet of water over the 
blocks, has been authorized." This dock was authorized 
in the Naval Appropriations Act approved July 1, 1918 
(40 Stat. L. 725). 
A 30-foot channel from the sea to Goose Creek via Cooper 
River, together with a 30-foot channel through Town 
Creek for commercial purposes. The act also provided 
that the 40-foot channel be prosecuted only as found 
necessary for national defense. 
The 35-foot channel depth from the sea to the head of the 
project via Cooper River and Town Creek, also a channel 
in Shem Creek to Mount Pleasant, 110 feet wide and ten 
feet deep, including a turning basin at the upper end. 
An anchorage area 30 feet deep in the water area 
between Castle Pinckney and Fort Moultrie. 
(Deauthorized by 1986 WRDA) 
Deepen the 30-foot channel north and east of Drum 
Island to 35 feet. 
Sec. 302, 1965 Rivers and Harbors 
Act (H.D. 251, 89th Cong., 1st Sess.) 
Annual Report, 1889, p. 1184. 
H.D. 84, 56th Cong., 1st sess. 
and Annual Report 1900, p. 1908 
Annual Report 1903, p. 1133. 
H.D. 178, 63rd Cong., 1st sess. 
H.D. 237, 68th Cong., 1st sess. 
S.D. 178, 68th Cong., 2nd sess. 
H.D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 14, 72nd Cong., 1st sess. 
H.D. 129, 72nd Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 11, 72nd Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 6, 75th Cong., 1st sess.3 
H.D. 327, 76th Cong., 1st sess. 
Annual Report 1878, pp. 553-572. 
H.D. 288, 62nd Cong., 2nd sess. 
H.D. 1946, 64th Cong., 2nd sess., 
pt. 1, pp. 21-29, 57, 58, and 61-63. 
H.D. 249, 69th Cong., 1st sess. 
H.D. 259, 76th Cong., 1st sess. 
H.D. 156, 77th Cong., 1st sess. 
S.D. 136, 83rd Cong., 2nd sess.3 
7-10

CHARLESTON, SOUTH CAROLINA DISTRICT 
TABLE 7-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
R&H Act of July 14, 1960 
Water Resources Development 
Act of Oct. 22, 1976 
Water Resources Development 
Act of 17 Nov. 1986 
R&H Act of Aug. 13, 1968 
Authorized by Chief of Engrs. 
on Dec. 23, 1977 under 
authority of Section 107 R&H 
Act of 1960, as amended. 
R&H Act of Aug. 5, 1886 
R&H Act of June 25, 1910 
R&H Act of Mar. 2, 1945 
R&H Act of June 30, 1948 
R&H Act of Mar. 2, 1907 
R&H Act of 1945, Sec. 3 
Auth. by Senate Public Works 
Comm. and the House Public 
Works Comm. on Oct. 12, 1972, 
under auth. of Sec. 201, P.L. 
89-298, 1965 FC Act. 
Shem Creek Channel modified by extending 1,150 feet 
upstream and downstream from mouth to Atlantic 
Intracoastal Waterway. 
Project is authorized for the Phase I design 
memorandum stage of Advanced Engineering and 
Design. 
Deepening 35 foot channel to 40 feet (42 feet in the ocean 
bar and entrance channel) from the 42 foot ocean 
contour to Goose Creek, a distance of 26.9 miles, 
construction of one turning basin, modification of 
existing turning basins, deepening and modification of 
the anchorage basin, deepening Shipyard River to 38 
feet, maintain the Wando River Channel to 35 feet at 
Federal expense and the deepening of this channel to 
40 feet if economically justified. 
COOPER RIVER, CHARLESTON, S.C. 
(ST. STEPHEN PROJECT) 
(See Section 4 of text.) 
Redivert most of the Santee river waters above 
Pinopolis Dam into the Lower Santee River through a 
canal beginning at Lake Moultrie and extending to the 
Santee River in the vicinity of St. Stephen, South 
Carolina. 
COOPER RIVER SEISMIC MODIFICATION, 
S.C. 
(See Section 5 of text.) 
Install a closure structure in the diversion canal 
between Lake Marion and Lake Moultrie and construct 
such measures as necessary to improve the seismic 
stability of the Pinopolis West Dam on the Cooper River. 
FOLLY RIVER, S.C. 
(See Section 6 of text.) 
Consists of stable all-tide channel nine feet deep and 80 
feet wide in Folly River and an entrance channel at 
Stono Inlet 100 feet wide and eleven feet deep. 
GEORGETOWN HARBOR, S.C. 
(See Section 7 of text.) 
Jetties and earthen dike to protect south jetty. 
Previous project channel dimensions and training wall. 
27-foot channel from ocean, including a turning basin 
in Sampit River. 
Cutoff and side channel in Sampit River. 
JEREMY CREEK, S.C. 
(See Section 8 of text.) 
To provide a waterway twelve feet deep at mean low 
water and a width of not less than 90 feet. 
LITTLE RIVER INLET, N.C. AND S.C. 
(See Section 9 of text.) 
Provides for an entrance channel twelve feet by 300 feet 
across the ocean bar; thence ten feet by 90-foot inner 
channel to the Atlantic Intracoastal Waterway. 
H.D. 35, 86th Cong., 1st sess. 
H.D. 436, 94th Cong., 2nd sess. 
H.D. 99-1013, 99th Cong., 2nd sess., 
P.L. 99-662. 
Rivers and Harbors Act of 1968, 
S.D. 88, 90th Cong. 
H.D. 3069, 98th Cong., 1st sess. 
Detailed Project Report 
H.Ex. Doc. 258 48th Cong., 2nd 
sess., and Annual Report 1885, pp. 
1154-1170, and H. Ex. Doc. 117, 
50th Cong., 2nd sess., and Annual 
Report 1889, pp. 1110-1111. 
H.D. 395, 58th Cong., 2nd sess. and 
Annual Report 1904, pp. 1591-1605. 
H.D. 211, 76th Cong., 1st sess. 
H.D. 21, 81st Cong., 1st sess. 
Detailed Project Report 
P.L. 79-14 
H.D. 362, 92nd Cong. 
7-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 7-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Water Resources Development 
Act of 1974. 
R&H Act of 1945, Sec. 3 
Auth. by the House Committee 
on Public Works on Nov. 10, 
1971 and the Senate Committee 
on Public Works on 
Nov. 18, P.L. 89-298, 1965 FC 
Act. 
Water Resources Development 
Act of 1974. 
R&H Act of Sept. 3, 1954 
R&H Act of July 25, 1912 
R&H Act of Mar. 3, 1925 
R&H Act of July 3, 1930 
R&H Act of Aug. 30, 1935 
R&H Act of Aug. 26, 19372 
R&H Act of Mar. 2, 1945 
Auth. by Chief of Engrs. on 
Feb. 12, 1974 under Auth. of 
Sec. 107 of R&H Act of 1960, 
as amended. 
Authorized emergency dredging operations as the Chief 
of Engineers determines necessary to maintain channel 
depths sufficient to permit free and safe movement of 
vessels until such time as the authorized project is 
constructed. 
MURRELLS INLET, S.C. 
(See Section 10 of text.) 
Provides for an entrance channel twelve feet by 300 feet 
across the seaward bar, thence ten by 90-foot inner 
channel to a turning basin at the old Army crash boat 
dock. 
Authorized emergency dredging operations as the Chief 
of Engineers determines necessary to maintain channel 
depths sufficient to permit free and safe movement of 
vessels until such time as the authorized project is 
constructed. 
PORT ROYAL HARBOR, S.C. 
(See Section 11 of text.) 
A channel from the ocean through Port Royal Sound to 
Port Royal, S.C.; 27 feet deep and 500 feet wide across 
the ocean bar and in Port Royal Sound for approximately 
12.7 miles; thence 24 feet deep and 300 feet wide in 
Beaufort River and Battery Creek for approximately 
8.3 miles to and including a turning basin 27 feet deep 
and 600 feet wide opposite wharf of the S.C. State Ports 
SHIPYARD RIVER, S.C. 
(See Section 12 of text.) 
Channel depth of 15 feet and width of 100 feet. 
Deepening of channel to 18 feet from deep water in 
Cooper River upstream 1-1/16 miles. 
Channel depths of twelve to twenty feet. 
28-feet from Cooper River to Gulf Oil Corp's terminal, 
and the deepening of the channel above that point to 
twenty feet from the depth of twelve feet previously 
authorized without local cooperation. 
Enlargement of the channel to a depth of 30 feet and a 
width of 200 feet up to the Gulf Oil Corp's terminal, 
with a turning basin 30 feet deep at the latter point. 
Extension of the existing 30-foot channel to vicinity of 
the Pittsburg Metallurgical Co. Plant, with a turning 
basin at the upper end. 
TOWN CREEK, S.C. 
(See Section 13 of text.) 
An entrance channel twelve feet deep by 100 feet wide 
across the ocean bar a distance of 4.0 miles and a channel 
ten feet deep by 80 feet wide from the mouth of Five 
Fathom Creek to the Atlantic Intracoastal Waterway, a 
distance of 6.2 miles. 
H.D. 10203, 93rd Cong., 2nd sess. 
P.L. 79-14 
H.D. 137, 92nd Cong. 
H.D. 10203, 93rd Cong., 2nd sess. 
River and Harbor Act, H.D. 469, 
81st Cong., 2nd sess. 
S.D. 350, 62nd Cong., 2nd sess. 
H.D. 288, 68th Cong., 1st sess. 
Rivers & Harbors Committee Doc. 
Rivers & Harbors Committee 
Doc. 43, 73rd Cong., 2nd sess. 
Rivers & Harbors Committee 
Doc. 38, 75th Cong., 1st sess. 
H.D. 93, 79th Cong., 1st sess. 
Detailed Project Report. 
1/ Included in Public Works Administration Program September 
6, 1933. 
2/ Included in Emergency Relief Administration Program 
May 28, 1935. 
3/ Contains latest published maps. 
4/ Inactive. 
5/ Completed under previous projects. 
6/ For national defense. 
7-12

CHARLESTON, SOUTH CAROLINA DISTRICT 
TABLE 7-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 15 of Text) 
For Last 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Adams Creek, S.C. 1 1978 $125,697 $ 22,111 
Aquatic Plant Control, N.C. and S.C. 1 5 1968 379,680 -- 
Archers Creek, S.C. 1914 20,646 -- 
Ashley River, S.C. 1 1955 260,996 535,049 
Edisto River, S.C. 1 2 1938 33,103 1,100 
Great Pee Dee River, S.C.'1 3 1950 183,712 269,873 
Mingo Creek, S.C. 1 2 1950 29,050 7,350 
Lynches River and Clark Creek, S.C. 1 1982 9,500 84,370 
Salkahatchie River, S.C. 1 2 4 1896 15,841 200 
Santee River, N.C. & S.C.1 1950 99,750 180,833 
Village Creek, S.C. 1985 26,500 107,044 
Waccamaw River, N.C. & S.C. 1 1978 262,814 278,370 
Wateree River, S.C. 1940 60,000 151,984 
1/ Completed. 
2/ No commerce reported. 
3/ Curtailment recommended in 1926 (H.D. 467, 69th Cong., 1st Session.) 
4/ Abandonment recommended in 1926 (H.D. 69th Cong., 1st Session.) 
5/ Pilot Program. 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
TABLE 7-D 
(See Section 16 of Text) 
Study Identifications Section Fiscal Year Costs 
Brookgreen Gardens, S.C. 107 $ 3,971 
Shipyard River, S.C. 107 16,676 
OTHER AUTHORIZED BEACH EROSION PROJECTS 
TABLE 7-E 
(See Section 17 of the Text) 
For Last 
Full Report 
See Annual Operations & 
Project Report For Construction Maintenance 
Hunting Island Beach, S.C. 1984 $2,872,7171 
1/ Excludes $1,249,336 contributed funds. 
7-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 7-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Buck Creek, N.C. & S.C. 1 2 1970 $ 298,167 -- 
Cow Castle Creek, S.C. 1 2 1985 250,000 -- 
Cowpens Swamp, S.C. 1 2 1960 18,679 -- 
Crabtree Swamp, S.C. 1 2 1969 97,000 -- 
Eagle Creek, S.C. 1 2 1986 1,245,063 -- 
Edisto River, S.C. 1 3 1947 6,379 -- 
Edisto River, North Fork, S.C. 1 2 1969 127,660 -- 
Edisto River, Vicinity Canaday's Landing, S.C. 1 2 1958 3,160 -- 
Gapway Swamp, S.C. 1 1969 339,197-- 
Kingstree Branch, Williamsburg County, S.C. 1 1978 247,242 -- 
Leith's Creek, S.C. 1 2 1982 430,951 -- 
Reddies River Lake, N.C. 1980 985,800 -- 
Reedy River, S.C. 1 3 1974 4,500 -- 
Roaring River, Wilkes County, N.C. 1 4 1978 370,000 -- 
Saluda River, S.C. 1 2 1963 99,000 -- 
Sawmill Branch, S.C. 1 2 1971 248,605 -- 
Shot Pouch Creek, Sumter County, S.C. 1 2 1971 77,400 -- 
Simpson Creek, S.C. 1 2 1957 81,000 -- 
Todd Swamp, S.C. 1 2 1964 29,000 -- 
Turkey Creek, Sumter County, S.C. 1 2 1974 319,669-- 
Wilson Creek, Sumter County, S.C. 1 2 1985 277,111 -- 
1/ Authorized by Chief of Engineers. 3/ Discontinued due to lack of interest. 
2/ Completed. 4/ Phase I only. 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
TABLE 7-G 
PREAUTHORIZATION STUDIES (See Section 21 of Text) 
Study Identifications Section Fiscal Year Costs 
Camp Branch/Lynches Lake, Lake City, S.C. 205 $ 140 
Crooked Creek, Bennettsville, S.C. 205 1,496 
Hemingway Creek, S.C. 205 17,429 
Kinley Creek, Lexington County, S.C. 205 18,070 
Maple Swamp, S.C. 205 26,233 
Rawls Creek, S.C. 205 41,674 
Socastee Creek, Horry County, S.C. 205 7,422 
OTHER AUTHORIZED STREAMBANK EROSION PROJECTS 
TABLE 7-H 
(See Section 22 of the Text) 
For Last 
Full Report 
See Annual Operations & 
Project Report For Construction Maintenance 
Cooper River, Pompion Hill Chapel, S.C. 1987 $211,000 1/ -- 
1/ Completed. 
7-14

CHARLESTON, SOUTH CAROLINA DISTRICT 
TABLE 7-I ACTIVE GENERAL INVESTIGATIONS 
ITEM FISCAL YEAR COSTS 
FLOOD DAMAGE PREVENTION STUDIES (CATEGORY 120) 
Gills Creek, S.C. $ 50,185 
SHORELINE PROTECTION STUDIES (CATEGORY 130) 
Myrtle Beach, S.C. $ 107 
South Carolina Shores 204,176 
MISCELLANEOUS ACTIVITIES (CATEGORY 170) 
Special Investigations $ 64,846 
FERC Licensing Activities 4,604 
Interagency Water Resources Development 15,898 
COORDINATION STUDIES WITH OTHER AGENCIES (CATEGORY 180) 
Department of Agriculture, SCS $ 2,903 
Planning Assistance to States 64,542 
TOTAL (CATEGORY 100) $407,261 
FLOOD PLAIN MANAGEMENT SERVICES (CATEGORY 250) $241,196 
HYDROLOGIC STUDIES (CATEGORY 260) 
Hydrologic Studies 5,000 
TOTAL (CATEGORY 200) $246,196 
CONTINUATION OF PLANNING AND ENGINEERING (CATEGORY 400) 
Charleston Harbor Deepening, S.C. $ 65 
TOTAL (CATEGORY 400) $ 65 
ADVANCE ENGINEERING & DESIGN (CATEGORY 600) 
Charleston Harbor Deepening, S.C. $ 19,561 
Folly Beach, S.C. 237,938 
TOTAL (CATEGORY 600) $257,499 
TOTAL GENERAL INVESTIGATIONS $911,021 
7-15

SAVANNAH, GA, DISTRICT * 
The District comprises drainage basins that flow 
into the Atlantic Ocean between Port Royal Sound, 
SC, and Cumberland Sound, GA and FL, and includes 
the Atlantic Intracoastal Waterway between 
these points. This area covers the headwaters of the 
Savannah River in southwestern North Carolina, 
eastern Georgia, and a small portion of northeastern 
Florida. 
IMPROVEMENTS 
Navigation 
1. Altamaha, Oconee, and Ocmulgee 
Rivers............................ 8-1 
2. Aquatic Plant Control .............. 8-2 
3. Atlantic Intracoastal Waterway 
Between Norfolk, VA, and St. Johns 
River, FL (Savannah District) .......... 8-2 
4. Brunswick Harbor, GA ............. 8-3 
5. Savannah Harbor, GA ............. 8-4 
6. Savannah River Below 
Augusta, GA ....................... 8-5 
7. Reconnaissance and Condition 
Surveys .......................... 8-5 
8. Other Authorized Navigation 
Projects ........................... 8-5 
9. Navigation Work Under Special 
Authorization ....................... 8-5 
Beach Erosion Control 
10. Beach Erosion Control Work 
Under Special Authorization ........ 
11. Tybee Island, GA ................ 
... 8-5 
... 8-6 
Flood Control 
12. Broadway Lake, Anderson County, 
SC ............................... 8-6 
12A. Savannah River Basin at 
Oates Creek ....................... 8-6 
13. Inspection of Completed Flood 
Control Projects .................... 8-7 
14. Flood Control Work Under Special 8- 
Authorization ....................... 8-7 
Emergency Streambank and 
Shoreline Protection 
16. Emergency Streambank and Shoreline 
Protection Under Special 
Authorization ..................... 8-7 
Multiple-Purpose Projects Including Power 
17. Savannah River Basin, GA and SC ..... 8-7 
17A. J. Strom Thurmond Dam and Reservoir, 
GA and SC (Formerly Clarks Hill Lake, 
GA and SC) ....................... 8-7 
17B. Hartwell Lake, GA and SC .......... 8-8 
17C. Richard B. Russell Dam and Lake, 
GA and SC (Formerly Trotters Shoals 
Lake, GA and SC) .................. 8-8 
18. West Point Lake, Chattahoochee 
River Basin, GA and FL ............. 8-9 
General Investigations 
19. Surveys ........................... 8-9 
20. Collection and Study of89 
Basic Data ......................... 8-9 
21. Research and Development .......... 8-9 
22. Continuation of Planning 
and Engineering.................... 8-9 
Tables 
Table 8-A Cost and Financial Statement .. 8-10 
Table 8-B Authorizing Legislation ....... 8-11 
Table 8-C Other Authorized Navigation 
Projects ...................... 8-16 
Table 8-D Other Authorized Flood Control 
Projects ....................... 8-17 
Table 8-E Savannah River Basin, GA and 
SC Dams and Lakes ............ 8-17 
Navigation 
1. ALTAMAHA, OCONEE, AND OCMULGEE 
RIVERS, GA 
Location. These rivers are entirely within the State 
of Georgia. (See National Oceanic and Atmnospheric 
Administration Survey Map of Georgia, formerly 
U. S. Geological Survey Map of Georgia.) For 
a full description of these rivers, see page 636, Annual 
Report for 1932. 
Previous projects. Prior projects for the Altamaha 
River have been adopted, and expenditures made 
under them, by the River and Harbor Acts of March 3, 
1881, and September 19, 1890; for the Oconee River 
by the River and Harbor Acts of June 18, 1878, September 
19, 1890, and March 3, 1905; for the Ocmulgee 
River, by the River and Harbor Acts of 
August 14, 1876, and September 19, 1890. 
For Further Details, see page 1815, Annual Report 
for 1915, and page 589, Annual Report for 1938. 
8-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. The authorized project provides 
for an appropriation of $40,000 annually for the Altamaha, 
Oconee, and Ocmulgee Rivers, to maintain 
a 3-foot depth during ordinary summer low water 
and to gradually increase channel depth so far as 
practicable without sacrificing the maintenance 
work. This project covers the entire Altamaha River 
(including a channel between the river and Darien, 
GA), a length of 137 miles. The lower 139 miles of 
the Oconee River has a mean tidal range of 6.4 feet 
at its mouth which gradually decreases to mile 33, 
where there is no perceptible tidal effect. At Doctortown, 
mile 59, ordinary floods attain a height of 
about 10 feet above low water, and at extreme 
floods, a height of about 15 feet above low water. 
On the Oconee River at Dublin the ordinary fluctuations 
attain a height of 22 feet, and the extreme fluctuations 
a height of 32 feet above low water. On the 
Ocmulgee River at Macon the ordinary fluctuations 
attain a height of 15 feet, and the extreme fluctuations 
a height of 25 feet above low water. There is no 
approved estimated cost for improvement or for 
maintenance. 
Published maps of these rivers are in the following 
documents; Altamaha River, HED 282, 51st Cong., 
2d sess., Oconee River, HED 211, 51st Cong., 1st 
sess., Ocmulgee River, HED 215, 51st Cong., 1st 
sess., and Lower Altamaha River and Darien Harbor, 
GA, HD 610, 77th Cong., 2d sess. (See Table 
8-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Along these rivers there are numerous 
natural shore landings which are considered 
ample for existing commerce. Facilities for recreational 
boats have been constructed at several 
points. 
Operations and results during fiscal year. Maintenance: 
There were no maintenance costs this fiscal 
year. 
Condition at end of fiscal year. The existing project 
is such that the percentage of completion cannot 
be stated. Channel depths have been increased 
by excavating rock shoals and sandbars, by constructing 
contraction and bank-protection works, 
and by closing cutoffs. Navigation has been rendered 
safer by removing obstructions. Many of the 
closing dams and contractions and bank-protection 
works need repairs. The notice of availability on 
the Final Environmental Impact Statement appeared 
in the Federal Register October 21, 1977. 
2. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Savannah District. 
Existing project. The project provides for control of 
water-hyacinth, lynhbya, alligator weed, Eurasian 
water milfoil, and other noxious aquatic plants from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interests of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, public health, and related purposes. 
The project provides for continued research for developing 
the most effective and economic control 
measures in cooperation with other Federal and 
State agencies in accordance with report of Chief of 
Engineers, H. S. 251, 89th Cong., 1st sess. The 
authorizing act provides that research costs shall be 
borne fully by the United States. (See Table 8-C for 
Authorizing Legislation.) 
The Final Environmental Impact Statement was filed 
with EPA on August 6, 1979, and its notice of availability 
appeared in the Federal Register August 17, 
1979. (See Table 8-A for Cost and Financial Statement). 
Local cooperation. Local interests must agree to 
hold the United States free from damages that may 
occur from operations performed in connection with 
this project and participate to the extent of 50 percent 
of the cost of the planning and actual control 
operations of the program. Requirements are being 
met. 
Operations and results during fiscal year. The 
Georgia Game and Fish Division, Department of 
Natural Resources, who maintain surveillance of potential 
aquatic plant problem areas, reported nuisance 
aquatic plant infestation in Lakes Jackson, 
Blackshear, Worth, and in Ebenezer Creek. Total 
projected cost of the FY 90 program will be $185,457 
of which the portion contributed by the Federal government 
is $92,730. FY 90 treatments include introduction 
of biological control agents and chemical 
applications. 
3. ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA, AND THE ST. JOHNS 
RIVER, FL (SAVANNAH DISTRICT) 
Location. This 161-mile section of waterway connects 
Port Royal Sound, SC, with Cumberland 
Sound, GA and FL. (See NOAA charts 
11489-11507, formerly Coast and Geodetic Survey 
Charts 838-841, inclusive.) 
Previous project. (Between Savannah, GA, and 
Femandina, FL) For details see pages 1814, 
8-2

SAVANNAH, GA, DISTRICT 
1821-1823 of Annual Report for 1915 and page 585 
of Annual Report for 1938. 
Existing project. The project provides for a waterway 
12 feet deep at mean low water and not less 
than 90 feet wide between Port Royal Sound, SC, 
and Savannah, GA; 12 feet deep at mean low water, 
with widths of 90 feet in land cuts and narrow 
streams and 150 feet in open waters between 
Savannah, GA, and Cumberland Sound, GA and FL; 
and a suitable anchorage basin at Isle of Hope, GA. 
Mean tidal range between Port Royal, SC, and Cumberland 
Sound, GA and FL is from 6 to 8 feet with 
fluctuations from 1.5 to 2.5 feet due to winds and lunar 
phases. (See Table 8-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Exclusive or adequate terminal 
facilities at port of entry, this improvement serves 
numerous wharves, some of which are open to the 
public on equal terms. Facilities are considered ample 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: The District utilized an 8(a) Minority 
Contractor to dredge the Intracoastal Waterway during 
this Fiscal Year. The contractor removed a total 
of 1,090,420 cubic yards of sediment for a total cost 
of $1,649,045.75, the highest price yet paid by the 
District for maintenance work on the project. The 
contract was stopped after the total pay amount 
was reached, even though there was material remaining 
in the portions of the project south of the 
Jekyll Island Bridge. The District has scheduled a 
smaller scale contract for FY 90 to complete the remainder 
of the work. The District also performed 
work in conjunction with the Jekyll Island Authority to 
construct a dike across an abandoned marina on 
Jekyll Island. The Corps will utilize the site as a disposal 
area until sufficient elevations are reached to 
allow marsh vegetation to establish on the material. 
Once the vegetation is established, the dike will be 
allowed to erode and approximately 50 acres of 
marsh will be created. 
Condition at end of fiscal year. The main channel 
of the existing project, completed in 1941, is maintained 
at 12 feet. The former main channel, now an 
altemate route through the westerly end of the south 
channel and northerly end of Wilmington River, will 
be maintained to a depth of 7 feet mean low water for 
traffic points north and south of Savannah Harbor. 
Relocation of the main channel from the Frederica to 
Mackay River near St. Simons Island, GA, was accomplished 
after construction of a new bridge for 
the Torras Causeway. The notice on the Final Environmental 
Impact Statement appeared in the Federal 
Register October 29, 1976. Total expenditures 
for the project are $21,430,862 of which $ 958,096 
was for new work. Costs of existing completed project 
to September 30, 1989, were $21,430,862 of 
which $958,096 was for new work and $20,472,766 
was for maintenance. (See Table 8-A for Cost and 
Financial Statement.) 
4. BRUNSWICK HARBOR, GA 
Location. The harbor entrance is 70 statute miles 
south of the entrance to Savannah Harbor, GA, and 
25 statute miles north of the entrance to Fernandina 
Harbor, FL. (See NOAA Chart 11215, formerly Coast 
and Geodetic Survey Chart 447.) 
Previous projects. For details see page 1818 of 
Annual Report for 1915 and page 591 of Annual Report 
for 1938. 
Existing project. The project provides for a stone 
jetty 4,350 feet long at the entrance to East River and 
the following channels: 32 feet deep and 500 feet 
wide across the bar; 30 feet deep and 400 feet wide 
through St. Simons Sound, Brunswick River, and 
East River to the foot of Second Avenue; 30 feet 
deep and 300 feet wide in Turtle River to the Allied 
Chemical Co. wharf, formerly the Atlantic Refining 
Co.; 27 feet deep and 350 feet wide in East River 
from Second Avenue to its confluence with Academy 
Creek; 24 feet deep and 150 feet wide from St. 
Simons Sound to the mouth of Mill Creek; and a 
channel in Terry Creek 10 feet deep and 150 feet 
wide from St. Simons Sound to the mouth of Mill 
Creek; and a channel in Terry Creek 10 feet deep 
and 80 feet wide from its mouth to a point immediately 
above the wharf of the former Glynn Canning 
Company. All depths refer to mean low water. Mean 
tidal range on the bar is 6.5 feet, at the City of 
Brunswick 7.3, and 7.6 feet at the upper end of the 
harbor. For further details see Annual Report for 
1962. 
Local cooperation. Complied with to date. 
Terminal facilities. Eighteen wharves and piers, almost 
all privately owned, have a berthing space of 
7,530 linear feet. The Port of Brunswick and the State 
of Georgia have a transit shed and modemrn docks 
with 1,640 feet of berthing space (three general 
cargo berths) on East River. For further details see 
Port Series No. 14, Corps of Engineers (revised 
1982). 
Operations and results during fiscal year. 
Maintenance: A total of two maintenance projects 
were completed in the Brunswick Harbor during FY 
89. They were both dredging of the East River. The 
District used two contractors to dredge the East 
River twice durina the fiscal year. The first was Atkin- 
8-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
son Dredging Company, of Chesapeake, Virginia. 
Their dredge, the Hampton Roads, removed 
194,622 cubic yards of silt at a total contract price of 
$504,573.10. Later during the fiscal year, it became 
necessary for another contract to remove shoaling 
that had occurred after the previous contract. Southern 
Dredging Company used the pipeline dredge 
Clinton to remove 377,397 cubic yards at a price of 
$414,697.00. These contracts maintained the East 
River portion of the channel, as well as performing 
reimbursed work for others. The work for others consisted 
of dredging in front of three of Georgia Ports 
Authority's (GPA) docks at the contract price. The 
GPA then reimbursed the District for the work performed 
outside of the Navigation channel. No work 
was performed on the Entrance Channel this fiscal 
year due to funding problems. 
Total operation and maintenance cost amounted to 
$1,063,076 for FY 89. (See Table 8-A for Cost and 
Financial Statement.) 
Condition at end of fiscal year. The existing project 
was completed in December 1960. General 
condition of the harbor works is satisfactory, providing 
maintenance dredging continues. The notice on 
the Final Environmental Impact Statement appeared 
in the Federal Register October 3, 1975. Authorized 
depths were maintained throughout the fiscal year. 
Costs for existing completed project to September 
30, 1989 were $67,611,303 of which $4,573,433 was 
for new work and $63,037,870 was for maintenance. 
(See Table 8-A for Cost and Financial Statement.) 
5. SAVANNAH HARBOR, GA 
Location. Harbor entrance is 75 statute miles south 
of Charleston, SC, and 70 miles north of Brunswick 
Harbor, GA. (See NOAA Chart 11512, formerly 
Coast and Geodetic Survey Chart 440.) 
Previous projects. For details see page 1810 of 
Annual Report for 1915 and page 578 of Annual Report 
for 1938. 
Existing project. The project provides for a channel 
40 feet deep and 600 feet wide across the ocean bar 
about 7.0 miles; 38 feet deep and 500 feet wide to 
the Seaboard Coast Line terminal; 38 feet deep and 
400 feet wide to the vicinity of Garden City (Georgia 
Ports Authority terminal) and 36 feet deep and 400 
feet wide to the vicinity of the Savannah Sugar Refinery 
of Savannah Foods and Industries, Inc. about 
22.6 miles; and 30 feet deep and 200 feet wide to a 
point 1,500 feet below the Atlantic Coastal Highway 
Bridge, about 1.5 miles, a total length of 31.1 miles; 
Fig island and Marsh Island Turning Basins 34 feet 
deep by 900 feet wide by 1,000 feet long in the vicinity 
of the Seaboard Coast Line terminal, and American 
Oil Company terminal; Kings Island Tumrning Basin 
38 feet deep by 1,500 feet wide by 1,600 feet 
long in the vicinity of the Garden City terminal of the 
Georgia Ports Authority; Argyle Island and Port 
Wentworth Turning Basins 30 feet deep by 600 feet 
long near Savannah Refinery terminal and at the extreme 
upper limit of the project near the Continental 
Can Company terminal; and a 1,200 foot long by 
1,050 foot wide by 40 foot deep Oyster Bed Island 
Turning Basin in the vicinity of Georgia Ports Authority's 
LASH facility. The project also provides for sediment 
control works consisting of a tide gate structure 
across Back River; a sediment basin 40 feet 
deep, 600 feet wide; about 2 miles long, with an entrance 
channel 38 to 40 feet deep and 300 feet wide; 
a drainage canal across Argyle Island 15 feet deep 
and 300 feet wide; control works and canals for supplying 
fresh water to the Savannah National Wildlife 
Refuge; and facilities to mitigate damages to presently 
improved areas other than refuge lands. Mean 
range of tide is 7.9 feet at the upper end of the harbor 
and 6.9 feet at the lower end. Extreme ranges are 
about 11.1 and 10.7 feet, respectively. 
Local cooperation. Local interests must provide 
suitable disposal areas and retaining dikes for construction 
and future maintenance of the project. The 
Chatham County Board of Commissioners, as local 
assurers, have met all requirements to date. 
Terminal facilities. Sixty-one piers and wharves 
adequately serve existing waterborne commerce of 
the port. These facilities, with use of dolphins, have 
a combined berthing space of 46,930 linear feet at 
mean low water. Included in the berthing space are 
six container berths with 271 acres of handling area. 
All have railway and highway connections. LASH facilities 
are located at the entrance to the harbor and 
have depths ranging up to 38 feet mean low water. 
The berthing space of LASH facilities is included in 
the above combined berthing space. For further details, 
see Port Series No. 14, Corps of Engineers (revised 
1982) and Annual Report for 1962. 
Maintenance. The District had two dredging contracts 
in the Savannah Harbor during FY89, the Navigation 
Channel from Station 79 to 112 + 500 and the 
Sediment Basin. The Ship Channel contract removed 
828,683 cubic yards of sediment at a cost of 
$922,776.50. The work was performed by Southern 
Dredging Company's pipeline dredge Clinton. This 
contract insured that the Upper Harbor and the Turning 
Basins remained available for ships to use. The 
other contract was the removal of 3,264,924 cubic 
yards of silt from the Sediment Basin by Atkinson 
Dredging for $906,147.66. The extreme low price is 
the result of dredging in the Sediment Basin, an area 
where the tidegate structure allows the silt to settle 
out of the water column in a location away from the 
8-4

SAVANNAH, GA, DISTRICT 
ship channel and close to disposal areas. Funding 
problems led to the delay of the Entrance Channel 
dredging until FY 90. 
Total operational costs for the harbor were 
$1,183,821 including such items as salinity monitoring, 
surveying, and cultural resource surveys. Total 
operation and maintenance costs for the fiscal year 
amounted to $3,620,820 of which $132,098 was 
spent on the operation of the Tidegate structure. 
Condition at the end of the fiscal year. Training 
walls, jetties, and other structures are in fair condition. 
Authorized channels are maintained by a 
planned dredging program with work at critical areas 
when necessary. The notice on the Final Environmental 
Impact Statement appeared in the Federal 
Register June 25,1976. Notices of availability 
on two Final Supplements to the Environmental Impact 
Statement appeared in the Federal Register 
September 25, 1978, and January 8, 1980. 
Costs of existing projects to September 30, 1988, 
were $199,560,700 of which $46,651,552 was for 
new work and $152,909,148 was for maintenance. 
(See Table 8-A for Cost and Financial Statement.) 
6. SAVANNAH RIVER BELOW AUGUSTA, GA 
Location. Savannah River is formed by the confluence 
of the Tugaloo and Seneca Rivers on the 
boundary line between South Carolina and Georgia. 
It flows southeast 314 miles, forming the boundary 
line between two states, and empties into the Atlantic 
Ocean 16.6 miles below Savannah, GA. (See 
NOAA Charts 11514 and 11515, formerly Geological 
Survey maps of South Carolina and Georgia.) 
Previous project. For details see page 1813 of Annual 
Report for 1915 and page 581 of Annual Report 
for 1938. 
Existing project. The authorized project provides 
for a channel 9 feet deep and 90 feet wide (at ordinary 
summer flow of 5,800 second-feet at Augusta, 
GA) from the upper end of the Savannah Harbor to 
the head of navigation at Augusta, 3 miles above the 
Fifth Street Bridge, a total distance of about 181 
miles. A lock and dam is located approximately 15 
miles below the upper limit of the project at New 
Savannah Bluff. Improvement is to be obtained by 
construction of contraction works, closure of cutoffs, 
bank protection, dredging, removal of snags, 
over hanging trees and wrecks, and open-river 
regulation. Mean tidal variation at the mouth of the 
river is 7 feet. Freshet variation above the normal 
pool level (elevation 114.5 mean sea level) of New 
Savannah Bluff Lock and Dam at mile 187 is ordinarily 
about 13 feet with an extreme of 34 feet. Latest 
approved project cost estimate for providing a 
9-foot channel (September 1963) is $6,576,000 exclusive 
of amounts expended on previous projects. 
For further details see Annual Report for 1962. 
Local cooperation. Complied with to date. 
Terminal facilities. The only water terminals served 
by this improvement are at Augusta, Sylvania, and at 
or near Savannah. Augusta provided a municipal 
dock valued at $50,000 and Georgia Ports Authority 
constructed a state port at Augusta, GA, costing 
about $418,000. These facilities were expanded in 
1965 at an additional cost of about $250,000. These 
are supplemented by natural landings along the 
river and extensive facilities at Savannah. 
Operations and results during fiscal year. In general, 
open-channel works are in good condition. 
The notice on the Final Environmental Impact Statement 
appeared in the Federal Register February 18, 
1977. The total cost for the year was $212,123. There 
were no dredging projects during this fiscal year. Inspection 
of completed works amounted to $16,852. 
7. RECONNAISSANCE AND CONDITION SURVEYS 
Survey Section performed condition surveys on the 
following active O&M navigation projects: 
Savannah Harbor 
Brunswick Harbor 
AIWW 
Savannah River Below Augusta 
General regulatory function expenditures for the fiscal 
year were $1,387,804. 
8. OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Table 8-C.) 
9. NAVIGATION WORK UNDER 
AUTHORIZATION 
SPECIAL 
The Valona, GA, detailed project study was continued 
in FY 89 for a total expense of $24,379.06. Feasibility 
studies were initiated for the South Brunswick 
River, Brunswick Harbor, Georgia. $69,576.76 of the 
$97,000 initial work allowance was expended in FY 
89. Total expenditures for this category was 
$78,653.39. 
Beach ErosIon Control 
10. BEACH EROSION CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
A reconnaissance investigation was completed and 
expanded to the feasibility phase on the shoreline 
8-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
erosion problems at Crooked River State Park, GA, 
at a fiscal year cost of $29,464.33. 
11. TYBEE ISLAND, GA 
Location. Tybee Island is located directly south of 
the Savannah River entrance, about 17 miles east of 
the City of Savannah, GA. (See NOAA Charts 11512, 
11513, and 11509, formerly U. S. Coast and Geodetic 
Survey Charts Nos. 440, 1240, and 1241, and 
on maps included in HD 92-105, 92nd Cong.) The 
only portion of the island that has developed is 
bounded on the north by the south channel of the 
Savannah River, on the east by the Atlantic Ocean, 
and on the south and west by Tybee Creek and other 
small tidal streams. This area, hereinafter referred to 
as "Tybee Island," is occupied by the City of Tybee 
Island. The ocean face of this area has a wide sandy 
beach. Tybee Island is about 3.5 miles long from its 
northerly tip to the mouth of Tybee Creek with an average 
width of about 0.5 mile. Behind the beach lies 
a line of sand dunes, a number of which have been 
removed during the years to make room for Improvements 
and for various other reasons. Those that remain 
are from 10 to 20 feet high. The ground elevation 
west of the dunes is from 10 to 18 feet and 
slopes westward to the salt marsh. 
Existing project. The approved project plan of improvement 
provides for an 800-foot rock groin at the 
north end of the island, with a 225-foot tie-in to high 
ground. An additional 1,200-foot extension of this 
groin is deferred, as are two additional intermediate 
groins (480 feet long); these will be added at a later 
date, if needed. The plan also provides for the initial 
restoration of approximately 13,300 feet of beach, 
from the vicinity of 18th Street to the terminal groin 
located at the northern end of the island. Periodic 
nourishment will be provided as needed to maintain 
suitable beach dimensions. In 1981, the plan was 
modified and now calls for the addition of a groin at 
the south end and modification and rehabilitation of 
the north rock groin and renourishment. 
Local cooperation. Local interests must: (a) contribute 
in cash the required percentage of the first 
cost (including costs for construction, engineering 
and design, and administration; and excluding the 
cost of lands, easements, rights-of-way and relocation) 
of all items of work to be provided by the 
Corps of Engineers. The local contribution is presently 
estimated at 51.0 percent to be paid in a lump 
sum prior to start of construction or in installments 
prior to the start of pertinent work items in accordance 
with construction schedules as required by 
the Chief of Engineers, the final apportionment of 
cost to be made after the actual costs have been determined; 
(b) provide maintenance and repair of the 
groins, and provide (after the first 10 years of project 
life) periodic nourishment of the restored beach as 
may be required to serve the intended purpose during 
the life of the project; (c) provide without cost to 
the United States all lands, easements, rights-ofway, 
and relocations required for construction and 
subsequent nourishment of the project; (e) control 
water pollution to the extent necessary to safeguard 
the health of bathers; and (f) provide without cost to 
the United States access and facilities necessary 
for realization of the public benefits upon which Federal 
participation is based, and maintain continued 
public use of the beach and administer it for public 
use during the life of the project, and provide further 
that construction on the project shall not be started 
until local interests furnish lands for beach access 
and parking, satisfactory to the Chief of Engineers, 
for the reach from First Street to the terminal groin. To 
date, local cooperation is being provided as required. 
Condition at the end of the fiscal year. In January 
1987, the South Groin contract was completed at a 
cost of $607,392. In February 1987, the first periodic 
renourishment contract was awarded, calling for the 
placement of approximately 1 million cubic yards of 
sand on two reaches of the island; the south end 
from the mouth of Tybee Creek to 14th Street, and 
the north end from the North terminal groin to about 
6th Street. The contract was completed in May 1987 
at a contract cost of $1,988,843. 
FLOOD CONTROL 
12. BROADWAY LAKE 
Location. Broadway Lake is located about 4 miles 
southeast of Anderson, South Carolina. It is formed 
at the junction of Broadway Creek and Neals Creek 
in the headwaters of Rocky River, a tributary of the 
Savannah River. 
Operations and results during the fiscal year. The 
project was deauthorized during FY 88 under procedures 
specified in PL 99-662, section 1001(b), 
dated November 17, 1986. 
12A. SAVANNAH RIVER BASIN AT OATES 
CREEK, GA. Oates Creek is a major drainage outlet 
for flood waters from an urban area of Augusta, 
GA. A flood control study of Oates Creek was 
authorized and completed as part of the Savannah 
River Basin study. The Qates Creek study area is located 
just south of Augusta, in Richmond County. 
The recommended plan is a channel and bridge 
modification flood control plan and has received 
support from Federal, State, and local governmental 
agencies with no environmental opposition. The local 
sponsor, Richmond County, expressed support 
for the project and intent to participate financially. 
8-6

SAVANNAH, GA, DISTRICT 
The plan consists of improvements to approximately 
12,300 feet of channel and consists of concrete-
lined channels, grass-lined channels, a low 
levee, modifications of bridges and culverts, and relocation 
of utilities. The CP&E effort began in October 
1983 and consisted of the preparation of a General 
Design Memorandum (Sep 1986). Upon the 
completion and approval of the General Design 
Memorandum, negotiations were initiated with the 
local sponsor to develop a Local Cooperation 
Agreement (LCA). The LCA was signed by Richmond 
County and the Assistant Secretary of the 
Army (Civil Works) on 10 March 1988. Fiscal year expenditures 
were $271,390 Federal and 320,000 
Non-federal. 
13. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
(See Table 8-D.) 
14. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 858, 80th Cong., as amended 
(preauthorization studies). Feasibility studies continued 
through FY 89 on Placentia Canal, GA, and 
Springfield Canal, GA. The efforts expended on 
Placentia Canal resulted in the approval of the Detailed 
Project Report at no additional costs for FY89. 
Feasibility studies continued in FY 89 on Springfield 
Canal, GA, at a cost of $7,959.44. Reconnaissance 
studies were completed in FY 89 for: Big Indian 
Creek, GA - $9,148.21; Conley Creek, Clayton Co. 
GA - $8,959.70; Panther Creek, Clayton Co. GA - 
$9,682.17; Rum Creek, Clayton Co., GA - 
$9,882.11; St. Augustine Creek, Chatham Co. GA - 
$9,760.34. None of these recommended further 
studies. Two reconnaissance studies were expanded 
to full efforts in FY 88 and completed in FY 
89. Expenditures in FY 89 for these two studies were 
Hunger and Hardship Creek, GA - $8,189.54 and 
Reeves Creek, GA - $5,097.04. The total fiscal year 
cost for pre-authorization studies was $68,678.55. 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong. and antecedent legislation). Revisions to 
emergency manuals, emergency operations, and 
exercises fiscal year costs were $209,290. 
Emergency Streambank and Shoreline Protection 
16. EMERGENCY STREAMBANK AND SHORELINE 
PROTECTION UNDER SPECIAL AUTHORIZATION. 
No work was performed in FY 89 under authorization 
of Section 14, Flood Control Act of 1946 as 
amended. 
Multiple-Purpose Projects Including Power 
17. SAVANNAH RIVER BASIN, GA AND SC 
Location. Works covered by this project consist of 
a series of 11 dams and lakes on the Savannah 
River and its tributaries in GA and SC. (See Geological 
Survey maps of GA and SC.) 
Existing project. The Flood Control Act of 1944 approved 
the general plan for comprehensive development 
of the Savannah River basin for flood control 
and other purposes (H.D/ 657, 78th Cong., 2d sess.) 
and authorized construction of the J. Strom Thurmond 
Dam and Reservoir Project on the Savannah 
River in Georgia and South Carolina as the initial 
step of this development. The Flood Control Act of 
1950 authorized construction of Hartwell Lake under 
the general plan. Richard B. Russell (formerly Trotters 
Shoals) was authorized for construction by the 
Flood Control Act of 1966 at an estimated cost of 
$84,900,000. J. Strom Thurmond Dam and Reservoir, 
Hartwell Lake, and Richard B. Russell Dam and 
Lake are the only projects in the comprehensive 
plan that have been constructed. (See Table 8-E on 
Dams and Lakes.) 
Duke Power Company has completed construction 
on the Keowee-Toxaway power complex on the 
Keowee River in the headwaters of Hartwell Lake 
and construction of the Jocassee pump-storage 
power project in the headwaters of the Keowee- 
Toxaway project. The Keowee-Toxaway power 
complex is located on the Newry-OId Pickens site 
identified in the approved comprehensive plan. Individual 
reports on J. Strom Thurmond Dam and Reservoir, 
Hartwell, and Richard B. Russell Lakes follow. 
Local cooperation. None required. 
17A. J. STROM THURMOND DAM AND RESERVOIR, 
(Formerly Clarks Hill Lake) GA AND SC 
Location. J. Strom Thurmond Dam and Reservoir is 
located at mile 237.7 on the Savannah River about 
22 miles upstream from Augusta, GA. (See Geological 
Survey maps of GA and SC.) 
Existing project. The authorized project provides 
for construction of J. Strom Thurmond Dam and Reservoir, 
the final cost of which was $79,156,300. The 
dam has a concrete section 2,282 feet long with a 
maximum height of 200 feet and a controlled spillway 
1,1096 feet long. The concrete section is 
flanked on the west side by a rolled-earth embankment 
of 2,069 feet and on the east side by a similar 
embankment of 1,329 feet. 
The total length of the dam is 5,680 feet. The lake 
covers 71,100 acres at maximum power pool eleva- 
8-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
tion 330. It provides a total storage capacity of 
2,900,000 acre-feet allocated as follows: flood 
control 390,000 acre-feet; hydropower 1,405,000 
acre-feet; dead storage 1,465,000 acre-feet. 
Seven 40,000-kilowatt generators have a combined 
generating capacity of 280,000 kilowatts with an average 
annual output of 700 million kilowatt-hours of 
electrical energy. 
Local cooperation. None required. 
Operations and results during fiscal year. Gross 
generations of electric energy for the period was 
331,177,004 kilowatt-hours, most of which was delivered 
to the Southeastern Power Administration. 
Prevented flood damages were estimated at zero 
due to the extreme drought in 1989. 
Maintenance: Operation and maintenance costs 
during the fiscal year amounted to $10,858,490. The 
notice of availability on the Final Environmental Impact 
Statement on J. Strom Thurmond Dam and 
Reservoir Operation and Maintenance appeared in 
the December 18, 1981 Federal Register. In FY 89 
5,775,600 persons visited the facility. 
Condition at the end of the fiscal year. Construction 
is complete except for providing additional recreational 
development.(See Table 8-A for Cost and 
Financial Statement.) 
17B. HARTWELL LAKE, GA AND SC 
Location. Hartwell Lake is on the Savannah River 
305 miles above its mouth and 89 miles upstream 
from Augusta, GA.(See Geological Survey maps of 
GA and SC.) 
Existing project. The dam is a concrete gravitytype 
structure 1,900 feet long with a maximum height 
of 204 feet and a controlled spillway 568 feet in 
length. The concrete section is flanked on the east 
and west abutments by earth embankments totaling 
13,390 feet in length and by a saddle dike 2,590 feet 
long also on the west side. Total length of the dam is 
17,880 feet. At maximum conservation pool elevation 
of 660 feet the lake covers 55,950 acres. Total 
capacity of the lake is 2,843,000 acre-feet of storage 
allocated as follows: flood control - 293,000 
acre-feet, hydropower - 1,416,000 acre-feet, dead 
storage - 1,134,000 acre-feet. Four 66,000 kilowatt 
generators having a generating capacity of 264,000 
kilowatts were installed initially with provisions for a 
future unit. A fifth 80,000 kilowatt generating unit has 
been installed which increased the rated capacity to 
344,000 kilowatts. 
Local cooperation. None required. 
Operations and results during the fiscal year. 
Cost of activities during this fiscal year amounted to 
$8,003,569. 
The fiscal year upper diversion dam rehabilitation 
cost amounted to $21,922 used mainly for monitoring 
activities. Gross generation of electrical energy 
for the period amounted to 253,014,700 kilowatthours, 
most of which was delivered to the Southeastern 
Power Administration. Flood damages prevented 
were estimated to be zero due to the extreme 
drought of 1989. 
Maintenance. Operation and maintenance costs 
during the fiscal year amounted to $8,003,569. The 
notice on the Final Environmental Impact Statement 
on the operation and maintenance of Hartwell Dam 
and Lake appeared in the Federal Register on 
August 21,1978. Approximately 15,034,800 persons 
visited the lake in FY 89. 
17C. RICHARD B. RUSSELL DAM AND LAKE, GA 
AND SC (Formerly Trotters Shoals Lake, GA AND 
SC) 
Location. Richard B. Russell Dam is located on the 
Savannah River 275.1 miles above its mouth, 29.9 
miles below Hartwell Dam, and about 37.4 miles 
above J. Strom Thurmond Dam (formerly Clarks Hill 
Dam). (See NOAA Survey maps of GA and SC.) 
Existing project. The authorized project provides 
for construction of Richard B. Russell Dam and Lake 
substantially in accordance with the recommendations. 
The latest approved (fiscal year 1989) cost estimate 
for the project is $555,000,000 of which 
$430,289,000 is for construction; $28,580,000 for 
lands and damages; $4,683,000 for cultural resources; 
and $91,498,000 for engineering/design 
and supervision/administration. Approval was received 
in January 1977 to include minimum provisions 
for pumped storage. 
A Feasibility Report and Final Environmental Impact 
Statement to address the installation and operation 
of four 75 MW reversible pump-turbines were prepared 
in 1979 with the Record of Decision signed in 
August 1980. The Richard B. Russell Fish and Wildlife 
Mitigation Plan was completed in 1981, approved 
by the Assistant Secretary of the Army (Civil 
Works) in September 1982, and the provisions are 
being implemented. 
Since 1986, the District has been conducting various 
fishery studies in the Russell tailrace and J. 
Strom Thurmond Lake (formerly Clarks Hill Lake) 
downstream. In addition, the District is conducting 
water quality studies, hydraulic modeling, and an 
evaluation of various fish protection measures associated 
with hydroelectric projects. The results of 
8-8

SAVANNAH, GA, DISTRICT 
these study efforts will be used to evaluate the need 
for fish protection at the Richard B. Russell Project 
associated with pumped storage operations. This 
evaluation will be presented in a supplement to the 
Final Environmental Impact Statement(SEIS) on 
pumped storage. The draft SEIS is scheduled to be 
coordinated in the summer of 1989. 
McCalla State Park Recreation Facilities is scheduled 
to be awarded in FY 90. 
During FY 89 268,265,000 kilowatts of power were 
generated. 
Maintenance. The operation and maintenance cost 
for the fiscal year amounted to $3,497,898. These 
funds were for management of lake activities. Approximately 
802,000 persons visited the lake in FY 
89. 
Condition at the end of fiscal year. The project is 
88 percent complete. 
Costs of project to September 30, 1989 were 
$501,596,457 of which $482,507,225 was used for 
new work and $19,089,232 for maintenance. (See 
Table 8-A for Cost and Financial Statement.) 
18. WEST POINT LAKE, CHATTAHOOCHEE 
RIVER 
Location. The West Point Lake is located on the 
Chattahoochee River, 2.8 miles upstream from West 
Point, GA, and was authorized by the Flood Control 
Act of 1962 (H.D. 570, 87th Cong., 2d sess.). The 
project was designed and constructed for flood control, 
power, recreation, fish and wildlife development, 
and stream flow regulation for downstream 
navigation. Design and construction was accomplished 
by the Savannah District, U. S. Army Corps 
of Engineers for the Mobile District, U.S. Army Corps 
of Engineers. For more detail, see the Mobile, AL, 
District's Report of the Chief of Engineers, U. S. 
Army 1987. 
General Investigation 
19. SURVEYS 
Fiscal year costs were $823,594 of which $145,140 
was for navigation studies; $514,002 for flood control 
studies; $54,999 for special investigations; 
$82,973 for coordination with other agencies; 
$15,289 for dam safety criteria studies, and $11,191 
for review of completed projects. 
20. COLLECTION AND STUDY OF BASIC DATA 
Work continued under the Flood Plain Management 
Services on the compilation of flood information, 
potential flood damages, and identification of those 
areas subject to inundation. Fiscal year expenditures 
for Flood Plain Management Services were 
$92,357 while expenditures for Technical Services 
were $108,987. 
Flood Plain Management Services included responses 
to other Federal agencies to aide them in 
fulfilling the requirements of EO 11988 (Management 
of Base Flood Area). Through the Technical 
Services Program, flood problems in several areas 
were analyzed and possible improvements were 
identified. During FY 89, the Flood Plain Management 
Services Branch continued the Coastal Georgia 
Hurricane Evacuation Study. This study is a three 
year joint effort of the state of Georgia, local officials, 
the Federal Emergency Management Agency, 
and the U. S. Army Corps of Engineers. Funds available 
for the study in FY 89 were $24,611 of which 
$6,000 came from the U. S. Army Corps of Engineers 
Flood Plain Management Program funds. Fiscal 
year expenditures were $21,107. The hydrologic 
studies costs were $3,500. 
21. RESEARCH AND DEVELOPMENT 
No funds were expended for research and development 
during the fiscal year. 
22. CONTINUATION OF PLANNING AND ENGINEERING 
Lake Lanier Reregulation Dam. In FY 88, the Lake 
Lanier Reregulation Dam General Design Memorandum 
was completed at a total cost of $2,206,000. 
The recommended plan is for reallocation of Lake 
Lanier storage from hydropower to water supply. 
Savannah Harbor Widening. The Savannah Harbor 
Widening project is designed to increase the 
width of the navigation channel from 400 to 500 feet 
along a 5.6 mile section of the Savannah River. During 
FY 89 the Chatham County Commissioners, the 
local sponsor, worked at acquiring the necessary 
LERR's as required bythe LCA. Fiscal year expenditures 
were $150,161. 
8-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 8-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
1. Altamaha, Oconee, 
& Ocmulgee Rivers, 
GA 
2. Aquatic Plant 
Control (1965 
R&H Act) 
3. Atlantic Intracoastal 
Waterway 
between Norfolk, 
VA, and the St. 
John's River, FL 
4. Brunswick Harbor, 
GA 
5. Savannah Harbor, 
GA 
6. Savannah River 
below Augusta, 
GA 
11. Tybee Island, GA 
12. Broadway Lake, 
SC 
13. Inspection of 
Completed Flood 
Control Works 
17.A J. Strom Thurmond 
Dam and Reservoir, 
GA and SC 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
821,457 1 
821,457 1 
46 3,684 -- 
50,000 205,000 90,000 
58,950 143,065 78,264 
-- 1,917,9822 3 
-- 1,917,9822 3 
75,000 
39,402 
711,159 
588,238 
-- -- -- -- 958,096 4 
-- -- -- -- 958,096 4 
608,000 1,531,800 391,500 2,036,500 20,516,721 s 
752,177 1,536,950 393,423 2,010,362 20,472,766 6 
-- -- -- -- 4,573,608 6 
-- -- -- -- 4,573,608 6 
8,101,443 3,050,000 4,406,400 651,500 63,144,794 7 
8,110,481 2,974,663 4,066,019 1,063,076 63,037,870 7 
-- 1,870,000 
-- 315,648 
-- 48,057,721 8 
150,161 46,651,552 8 
3,635,000 2,866,500 3,479,400 3,581,000 153,018,040 s 
3,528,413 2,799,769 3,752,042 3,620,820 152,909,148 9 
-- -- -- -- 6,740,031 10 
-- -- -- -- 6,740,03110 
543,000 804,000 726,000 153,550 17,824,042 
550,000 788,320 753,458 212,123 17,783,489 
1,053,000 387,000 
209,486 1,225,729 4,980 
18,500 21,000 16,000 
29,646 18,135 19,141 
-- 4,357,24911 
-- 4,357,24911 
17,000 
16,852 
99,000 
99,000 
238,018 
237,859 
-- -- -- -- 84,841,29012 
-- -- -- -- 84,840,26312 
6,386,000 7,997,022 8,437,800 10,508,885 96,105,73913 
6,288,836 7,739,609 8,872,632 10,858,490 95,856,27513 
8-10

SAVANNAH, GA, DISTRICT 
TABLE 8-A (Cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
17.B Hartwell Lake, GA 
and SC 
17.C Richard B. Russell 
Dam and Lake, GA 
and SC (Formerly 
Trotters Shoals) 
17.D Oates Creek, 
Richmond County 
GA 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
-35,000 
73,980 -12,213 9,709 
-- 115,937,98514 15 
-26,878 115,874,81914 15 
6,404,500 6,823,622 7,654,400 7,566,035 83,608,461 1e 
6,208,294 6,725,929 7,895,745 8,003,569 84,157,97318 
69,000 
82,425 6,849 27,831 
9,310,000 19,000,000 28,700,000 
7,217,141 9,753,114 17,772,233 
3,734,000 3,599,922 
3,233,598 3,760,665 
21,922 
6,619,000 
6,609,526 
12,800,000 487,299,509 
31,104,225 482,506,542 
3,685,000 3,419,698 10,263,920 
3,866,344 3,497,898 19,089,232 
-- 348,000 1,800,000 
-- 224,921 271,390 
2,148,000 
496,311 
1. Includes $760,610 for previous projects. 
2. Includes $111,950 for previous projects. 
3. Does not include $69,356 contributed funds. 
4. Includes $194,497 for previous projects. 
5. Includes $134,789 for previous projects. Does not include 
$35,000 appropriated but unexpended of contributed funds in 
FYs 86 and 87. 
6. Includes $643,456 for previous projects and $97,521 expended 
from Public Works Funds for existing project. Does not 
include $10,000 contributed funds. 
7. Includes $54,414 for previous projects, $4,995 expended 
from Public Works Funds for existing project, and $2,150,000 
under 1983 Job Bill Act. Does not include contributed funds by 
Brunswick and Georgia Port Authority. 
8. Includes $7,260,384 for previous projects. Does not include 
$46,847 for removal of sunken vessels or contributed funds. 
9. Includes $298,894 for previous projects and $855,941 contributed 
funds. 
TABLE 8-B AUTHORIZIN 
10. Includes $93,480 for previous projects and $1,634,562 from 
Public Works Fund. 
11. Does not include $3,756,758 contributed funds. 
12. Does not Include $395,634 accelerated Public Works Funds. 
Includes $4,558,613 appropriated under Code 710. Also includes 
$1,000,000 expended under the 1983 Job Bill Act. 
13. Includes $316,760 under special recreation use fees and 
$736,000 under the 1983 Job Bill Act. 
14. Includes $17,515,000 appropriated for construction of 5th 
Unit of which $17,469,002 has been expended. 
15. Does not include $276,200 accelerated Public Works Funds. 
Includes $4,861,000 appropriated under Code 710 of which 
$4,851,306 has been expended and $545,000 expended under 
the 1983 Job Bill Act. 
16. Includes $576,019 expended special recreation use fees. 
IG LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
1. July 25, 1912 
& March 2, 1945 
Oct. 27, 1965 
Section 302 
ALTAMAHA, OCONEE, AND OCMULGEE RIVERS, GA 
Channel 3 feet deep and 60 to 100 feet wide. HD 443,62D Cong., 2d sess. 
HD 610, 77th Cong., 2d sess. 
Provides for control and progressive eradication 
of noxious aquatic plant growths. 
HD251, 89th Cong., 1st sess. 
8-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
3. June 3, 1896 
Mar. 3, 1899 
July 13, 1892 
Mar. 3, 1905 
July 25, 1912 
Aug. 8, 1917 
Mar. 2, 1919 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 26, 1937 
Aug. 26, 1937 
June 20, 1938 
Mar. 2, 1945 
Oct. 15, 1981 
4. Mar. 3, 1879 
Mar. 2, 1907 
Mar. 2, 1919 
July 3, 1930 
July 3, 1930 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA, AND ST. JOHNS 
RIVER, FLA, (SAVANNAH DISTRICT) 
Section from Beaufort, SC, to Savannah, GA 
Route No. 2 adopted. 
Route No. 1 adopted. 
Section from Savannah, GA, to Fernandina, 
FL. Original 7-foot channel. 
Provided for Skidaway Narrows. 
Incorporated alternative routes previously 
improved as separate projects and the 
auxilIary channels. 
Section from Cumberland Sound, GA and FL to 
St. Johns River, FL. Consolidation of the 
HD 295, 53d Cong., 3d sess. 
HD 295, 53d Cong., 3d sess. 
HD 41, 52d Cong., 1st sess. 
HD 450, 58th Cong., 2d sess. 
HD 1236, 60th Cong.,2d sess. 
3 sections shown above, into "Waterway between 
Beaufort, SC, and St. Johns River, FL." 
Section from Beaufort, SC, to Cumberland 
Sound, GA and FL. Removing logs and snags 
from Generals Cut. 
Improving Back River to provide a channel 7 
feet deep and 150 wide. 
Channel 75 feet wide between Beaufort, SC, 
and Savannah, GA. 
Channel from Baileys Cut to Dover Creek. 
A 7-foot protected channel around St. 
Andrews Sound. 
A 12-foot channel between Beaufort, SC, and 
Savannah, GA, via Beaufort River and Port 
Royal Sound. 
A 12-foot channel between Savannah, GA, and 
Fernandina, FL, various cutoffs; and 
anchorage basin at Thunderbolt, GA. 
An alternate route 9 feet deep and 150 feet 
wide in that part of Frederica River, GA, 
not now traversed by the main route, at no 
additional cost to the United States. 
Main channel relocated in the from Frederica 
River to Mackay River in the vicinity of 
Torras Causeway. 
BRUNSWICK HARBOR, GA 
Construction of East River jetty. 
Channels in the inner and outer harbors 
of 30-foot depth at mean high water, with 
widths varying from 150 feet in Academy 
Creek to 400 feet across the outer bar, 
extension of training wall in East River 
and construction of two spur dikes. 
Channels 27 feet deep at mean low water 
over the bar and at Brunswick point; and 
24 feet deep at mean low water in the inner 
harbor and provides for a cut from Academy 
Creek to Turtle River, if deemed advisable. 
A channel in Back River 230 feet deep and 
150 feet wide. 
Increased Channel dimensions of the bar, 
Brunswick Point, East River, and Turtle 
River, as given in the then existing 
HD 581, 63d Cong., 2d sess. 
HD 1391, 62d Cong., 3d sess. 
SD 178, 68th Cong., 2d sess. 
SD 43, 71st Cong., 2d sess. 
Senate committee print, 74th 
Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 6, 75th Cong.,3d sess. 
HD 618, 75th Cong., 3d sess. 
HD 114, 77th Cong.,1st sess. 
Project authorized by Chief 
of Engineers under the Small 
Navigation Project Authority, 
Sec. 107, PL 86-645 as amended. 
Annual Report, 1980, p.959. 
HD 407,59th Cong., 1st sess. 
HD 393,64th Cong., 1st sess. 
SD 57, 71st Cong., 2d sess. 
SD 132, 71st Cong., 2d sess. 
8-12

SAVANNAH, GA, DISTRICT 
June 20, 1938 
May 17, 1950 
Oct. 22, 1976 
Oct. 17, 1986 
5. Mar. 2, 1907 
June 25, 1910 
July 25, 1912 
Aug. 8, 1917 
Jan. 21, 1927 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Nov. 7, 1945 
project. 
A 10-foot channel in Terry Creek. 
Increased channel dimensions of the bar, 
St. Simons Sound, Brunswick River, East 
River, and Turtle River, as given in 
the existing project. 
Provides for Phase I AE&D studies for 
deepening portions of existing harbor 
(East River and Entrance Channel) and for 
provision of a navigation channel to 
Colonels Island. 
Incorporated Georgia Port Authority's 
30 foot deep by 300 foot wide by 8000 
foot channel in South Brunswick River 
serving Colonel's Island into Brunswick 
Harbor Navigation Project. 
SAVANNAH HARBOR, GA 
Tentative provisions for a 26-foot channel 
from the Quarantine Station to the Seaboard 
Air Line Ry. Bridge. 
Definite provision for the 26-foot channel. 
A 21-foot channel from the Seaboard Air 
Line Ry. Bridge to the foot of Kings Island. 
A 30-foot depth from the sea to the 
Quarantine Station. 
A 21-foot channel above Kings Island. 
Channel 30 feet deep, with general width 
50 feet, from the ocean to the Quarantine 
Station, thence 26 feet deep, general width 
400 feet, to the Seaboard Air Line Ry. Bridge, 
thence 21 feet deep and 300 feet wide to 
Kings Island. Widening at West Broad and 
Barnard Streets; anchorage basin; mooring 
dolphins; regulating dam across South Channel; 
relocation of the Inland Waterway; dredging 
Drakes Cut to 13 feet; widening to 525 ft. at 
Kings Island; extension of training walls, 
revetments, and jetties. Consolidation of 
projects relating to Savannah Harbor. 
Channel 26 feet deep and 300 feet wide 
from the Seaboard Air Line Ry. Bridge to 
the foot of Kings Island. 
Authorized the 30-foot project and eliminated 
from the project (a) the relating dam across 
South Channel; (b) the relocation of the 
Inland waterway; and (c) the further extension 
of training walls, revetments, and jetties. 
Deepening the channel and turning basin above 
the Seaboard Air Line Ry. Bridge from 26 to 
30 feet and widening the channel opposite 
the Atlantic Coast Line Terminals to a 
maximum of 550 feet for a length of 5,000 
feet. 
Deepening the channels to 36 feet deep and 
500 feet wide across the ocean bar; 34 
feet deep and generally 400 feet wide, 
increased to 550 feet opposite the Atlantic 
Coast Line Terminals, with a turning basin 
34 feet deep at the Mexican Petroleum Corp. 
HD 690, 75th Cong., 3d sess. 
HD 110, 81st Cong.,1st sess. 
Report of Chief of Engineers 
dated Aug. 18, 1976. 
HR 6,99th Cong. 2d sess. 
Section 846 
HD 181,59th Cong.,1st sess. 
HD 563, 62d Cong., 2d sess. 
HD 1471, 64th Cong.,2d sess. 
HD 261,69th Cong., 1st sess. 
HD 262,69th Cong., 1st sess. 
SD 39,71st Cong., 1st sess. 
HD 276, 73d Cong., 2d sess. 
HD 283,76th Cong., 1st sess. 
HD 227,79th Cong., 1st sess. 
8-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
July 24, 1946 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
Oct. 27, 1965 
SPCW Resolution 
June 15, 1976 
and HPWTC of 
June 9, 1976 
under authority 
of Sec. 201 of 
Flood Control 
Act of 1965 
Oct. 17, 1986 
Refinery; and with such modifications 
thereof as the Secretary of War and the 
Chief of Engineers may consider desirable. 
Extending channel 30 feet deep, 200 feet wide 
upstream from Atlantic Creosoting Terminal 
to a point 1,500 feet below the Atlantic 
Coastal Highway Bridge, with turning 
basin 30 feet deep at upper end. 
Deepening the channel to 34 feet and widening 
to 400 feet from the upper end of the 
presently authorized 34-foot channel in the 
vicinity of the American Oil Company 
Refinery wharf, to the Savannah Sugar 
Refinery Corp. with a turning basin at the 
upper end of the proposed improvement, 
made by widening the channel to 600 feet 
for a length of 700 feet and providing 
approaches. 
Enlargement of turning basin near Kings 
Island to a width of 900 feet and a length 
of 1,000 feet, with suitable approaches, 
at a depth of 34 feet. 
Deepening the bar channel from 36 feet to 
40 feet, the channel between the bar channel 
and Garden City Terminal from 34 feet to 38 
feet. and the channel from the Garden City 
Terminal to the vicinity of the Savannah Sugar 
Refining Corp., from 30 feet to 36 feet; 
widening the bar channel from 500 feet to 600 
feet, the channel between Fort Pulaski and the 
Atlantic Coast Line Terminal from 400 feet to 
500 feet, and the channel between Garden City 
Terminal and the Savannah Sugar Refinery Corp. 
from 200 feet to 400 feet; providing necessary 
wideners of the bends; constructing a new 
turning basin 900 feet wide by 1,000 feet long 
by 34 feet deep opposite the Atlantic Coast 
Line Terminals; and enlargement of existing 
turning basin at the American Oil Company 
Terminal from 600 feet wide by 600 feet long 
to 900 feet wide by 1,000 feet long. 
Providing sediment control works consisting 
of tide gate structure across Back River; 
sediment basin 40 feet deep, 600 feet wide 
about 2 miles long, with entrance channel 
38 to 40 feet deep and 300 feet wide; control 
works and canals for supplying fresh water to 
Savannah National Wildlife Refuge; and 
facilities to mitigate damages to presently 
improved areas other than refuge lands. 
Provided for modification of the existing 
project to include (1) incorporation of 
the LASH Turning Basin as an element of 
the existing Federal navigation project for 
maintenance purposes, (2) enlargement of 
Kings Island Turning Basin to 1,500 feet by 
38 feet. 
Savannah Harbor widening as described in 
Report of Chief of Engineers date Dec. 
HD 678, 79th Cong., 2d sess. 
HD 110, 83d Cong., 1st sess. 
SD 115,87th Cong., 1st sess. 
HD 226,89th Cong., 1st sess. 
HD 223,89th Cong., 1st sess. 
HD 94-520, 94th Cong. dated 
June 8, 1976. 
HD 6, 99th Cong., 2d sess. 
Dated Oct 17, 1986 
8-14

SAVANNAH, GA, DISTRICT 
19, 1978. Widen channel from 400 feet to 
500 feet between Kings Island tumrning Basin 
and Fig Island Turning Basin. 
Allows planning, engineering and design to 
remove drift and debris as part of 
operations and maintenance. 
6. Sep. 19, 1980 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
May 17, 1950 
11. SPWC Resolution 
June 22, 1971 
HPWC of June 23, 
1972 under 
authority of 
Sec. 201 of FC 
Act of 1965 
Oct. 17, 1986 
12A. Water Resources 
Development Act 
of Mar. 7, 1974 
12B. Water Resources 
Development Act 
of 1986, Oct. 17,1986. 
17A. Flood Control 
Act of Dec. 22, 
1944 
Oct. 17, 1986 
Jan. 1988 
17B. Flood Control Act 
of May 17, 1950. 
Flood Control Act 
of July 3, 1958. 
SAVANNAH RIVER BELOW AUGUSTA, GA 
For a 5-foot channel. HD 255, 51st Cong., 2d sess. 
& Annual Report,1980,pg.1328 
Special improvement by bank protection HD 962,60th Cong., 1st sess. 
work of 20 or 25 miles of the river 
immediately below Augusta. 
The present 6-foot channel project and HD 101,70th Cong., 1st sess. 
Lock and Dam, GA. 
Provision made for locating the lock Senate Committee Print, 73d 
and dam at New Savannah Bluff. Cong., 2d sess. 
Conditions of local cooperation modified. Rivers and Harbors Com.,Doc. 39, 
75th Cong., 1st sess. 
Provides for a 9-foot channel. SD 6, 81st Cong., 1st sess. 
TYBEE ISLAND, GA 
Project will provide for beach erosion HD 105, 92d Cong. 
control, consisting of beach restoration, 
groin nourishment. 
Extends authority for renourishment with HR 6 99th Cong., 2d sess. 
Federal participation from 15 to 50 years. Dated Oct.17, 1986 
Section 867 
BROADWAY LAKE, SC 
Provided for undertaking a demonstration PL 93-251, 93d Cong. 
removal of silt and aquatic growth from 
Broadway Lake. 
OATES CREEK, GA 
Provided for construction of the Oates HR 699th Cong., 2d sess. 
Creek Project. dated Oct. 17, 1986 
Section 401 
J. STROM THURMOND DAM AND RESERVOIR 
Approved the general plan for the HD 657, 78th Cong., 2d sess. 
comprehensive development of the Savannah 
River Basin and provided for construction 
of the Project. 
Recreation and fish and wildlife added as HR 699th Cong., 2d sess. 
name changed. (Formerly Clarks Hill Lake). Section 864 
HJR 376 
HARTWELL LAKE, GA AND SC 
Provided for construction of Hartwell HD 657, 78th Cong., 2d sess. 
Project. PL 516,81st Cong., 2d sess. 
Provided for the completion of the PL 85-500, 85th Cong., 
Hartwell Project. 2d sess. 
8-15 
Section 201 
Section 867

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Water Resources 
Development Act 
of 1976. 
17C. Flood Control Act 
of Nov. 7, 1966. 
Water Resources 
Development Act 
of 1986, 
dated Oct. 17, 1986 
Provides for installation of 5th unit. 
RICHARD B. RUSSELL DAM AND LAKE, GA 
Provided for construction of the Trotters 
Shoals Project. 
Authorized mitigation plan, based on 
Report of the Chief of Engineers, dated 
May 11, 1982, House Document 
numbered 97-244 
PL 94-587, Sec. 182b. 
85th Cong. 
SD 52, 89th Cong., 1st sess. 
HR 699th Cong., 2d sess. 
Section 601 
TABLE 8-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 8 In text) 
For Last Cost to Sept. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Aquatic Plant Control (R&H Act 1962) 
Bellville Point, GA 
Cedar Point, GA 
Darien Harbor, GA 
Fancy Bluff Creek, GA 1 
St. Mary's River, GA and FL, and 
North River, GA 
Sapelo Harbor, GA 2 3 
Satilla River, GA 1 5 6 
Completed 1968 
Completed 1986 
Completed 1982 
Completed 1975 
Completed 1935 
Completed 1951 
Completed 1929 
Completed 1951 
Savannah River above Augusta, GA 2 3 4 See Notes 
Savannah River at Augusta, GA 2 3 5 
1929 
See Notes 1929 
1. Channel adequate for commerce. 
2. Project recommended for abandonment in H.D. 467, 69th Cong., 1st sess. 
3. No commerce reported. 
4. About 84 percent completed. Owing to construction of two power dams which submerged much of the work under the present 
and former projects, this improvement cannot be completed as originally planned. 
5. Excludes $185,000 contributed funds ($172,151 for construction and $12,849 for operation and maintenance). 
6. Water Resources Development Act of 1986 authorized demonstration project on the Umbrella Creek - Dover Creek for the 
purpose of reducing shoaling. Monitor for 10 years, develop a hydrodynamic model. 
8-16 
$25,700 
656,233 
199,723 
8,000 
15,688 
17,906 
9,452 
69,600 
200,556 
185,433 
7,200 
69,936 
19,594 
57,172 
5,870 
17,444

SAVANNAH, GA, DISTRICT 
TABLE 8-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 14 In text) 
For Last Cost to Sept. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Augusta, Savannah River, GA 
Curry Creek Dam and Lake, GA 1 
Dunn Branch, Woodbine, Camden 
County, GA 
Macon, GA 
Oates Creek, GA 
Peacock Creek, Liberty County, GA 
Completed 
See Note 
Completed 
Completed 
Authorized 
Completed 
1941 
1974 
1977 
1955 
N/A 
1976 
$643,016 
132,640 
380,043 
745,400 2 
582,163 
$38,242 
5,219 
38,243 
5,219 
1. Feasibility report completed. Project not authorized for construction. 
2. Authorized by HR 6, Water Resource Development Act of 1986 dated Oct. 17, 1986. First Federal cost of $9,600,000 and 
non-federal cost of $4,100,000. 
SAVANNAH RIVER BASIN, GA AND SC 
DAMS AND LAKES 
(See Section 16 in text) 
Estimated Cost 
Name River Federal Non-Federal Total 
J. Strom Thurmond Dam 
& Reservoir, GA and SC 
Hartwell, GA and SC 
Goat Island, GA and SC 6 
Middleton Shoals, GA and SC 6 
Chattooga Units(4), GA and SC 
Tallow Hill, GA 
Anthony Shoals, GA 
Newry-OId Pickens, SC 6 
Savannah 
Savannah 
Savannah 
Savannah 
Chattooga 
Broad 
Broad 
Keowee 
$79,156,000 4 
89,240,000 
36,400,000 
16,500,000 
41,700,000 
39,000,000 
18,100,000 
29,500,000 
$79,156,0001 4 
89,240,0002 
36,400,0003 
16,500,0003 
41,700,0003 
39,000,0003 
18,100,0003 
29,500,0003 
1. Final Cost. (Excludes $127,000 for preauthorization study.) 
2. Approved Aug. 1963. (Excludes $73,000 for preauthorization study.) 
3. Approved July 1954. 
4. Excludes Code 710 funds. 
5. Replaced by Richard B. Russell Dam and Lake (formerly Trotters Shoals Lake). 
6. Site of Duke Power Co. Keowee - Toxaway Project. 
8-17 
TABLE 8-E

JACKSONVILLE, FLA. DISTRICT* 
JACKSONVILLE, FLA. DISTRICT 
With the exception of a small area in the northeastern 
section of Florida, this district comprises a 
portion of south-central Georgia and all of peninsular 
Florida, embracing the watersheds tributary to 
Navigation 
the Atlantic Ocean and the Gulf of Mexico from, and 
including the harbor at Fernandina, Florida, to and 
including the Aucilla River. It also includes Puerto 
Rico and the Virgin Islands. 
IMPROVEMENTS 
Page 
1. Aquatic Plant Control (R&H Act 
of (1965) ......................... ............ 2 
2. Arecibo Harbor, P.R ...................... 2 
3. Atlantic Intracoastal Waterway 
between Norfolk, Va. and St. 
Johns River, Fla ............... ............ 2 
4. Bakers Haulover Inlet, Fla ............... 3 
5. Canaveral Harbor, Fla .................... 3 
6. Channel from Naples to 
Big M arco Pass ................. ............ 4 
7. Charlotte Harbor, Fla ..................... 4 
8. Cross Florida Barge Canal ................ 4 
9. Eau Gallie Harbor, Fla ................... 5 
10. Fernandina Harbor, Fla .................. 5 
11. Fort Myers Beach, Fla .................... 5 
12. Fort Pierce Harbor, Fla .................. 6 
13. Intracoastal Waterway, Caloosahatchee 
River to Anclote River, Fla ............... 6 
14. Intracoastal Waterway, Jacksonville 
to M iam i, Fla .................. ............. 7 
15. Jacksonville Harbor, Fla .................. 7 
16. Jacksonville Harbor (Mill Cove), Fla. ...... 8 
17. John's Pass, Fla .............. ............. 9 
18. Longboat Pass, Fla............ ............ 9 
19. Manatee Harbor, Fla ..................... 9 
20. Mayaguez Harbor, P.R ................... 10 
21. Melbourne Harbor, Fla ................... 10 
22. Miami Harbor, Fla ........................ 10 
23. New Pass, Sarasota, Fla .................. 11 
24. Okeechobee Waterway, Fla ............... 11 
25. Oklawaha River, Fla ...................... 12 
26. Palm Beach Harbor, Fla................... 12 
27. Ponce de Leon Inlet, Fla............. 13 
28. Ponce Harbor, P.R....................... 13 
29. Port Everglades Harbor, Fla............. 14 
30. Removal of Aquatic Growth From Navigable 
Waters in the State of Florida ....... 14 
31. St. Augustine Harbor, Fla ................ 15 
32. St. Johns River, Jacksonville to 
Lake Harney, Fla. ......................... 15 
33. St. Lucie Inlet, Fla ........................ 15 
34. San Juan Harbor, P.R .................... 16 
35. Tampa Harbor, Fla ....................... 17 
Navigation (cont.) Page 
36. Navigation Projects on which 
Reconnaissance and Condition Surveys 
only were Conducted during Period ....... 18 
37. Other Authorized Navigation 
Projects ..................................... 
38. Navigation Work under Special 
Authorization ............. ............... 
18 
18 
Beach Erosion Control 
39. Brevard County, Fla ...................... 18 
40. Broward County, Fla. Beach Erosion 
Control and Hillsboro Inlet, Fla., 
Navigation Project ......................... 19 
41. Duval County, Fla ......................... 19 
42. Indian River County, Fla ................. 19 
43. Palm Beach County, Fla. from Martin 
County line to Lake Worth Inlet and 
from South Lake Worth Inlet to 
Broward County line ...................... 20 
44. Pinellas County, Fla ...................... 20 
45. Other Authorized Beach Erosion 
Control Projects ............................ 21 
46. Beach Erosion Control Activities 
under Special Authorization............... 21 
Flood Control 
47. Central and Southern Florida ............. 21 
48. Dade County, Fla ......................... 23 
49. Dade County, N. of 
Haulover Beach, Fla ...................... 23 
50. Four River Basins, Fla ................... 24 
51. Portugues and Bucana Rivers, P.R ....... 24 
52. Inspection of Completed Flood 
Control Projects ............................ 25 
53. Other Authorized Flood Control 
Projects ..................................... 25 
54. Flood Control Work under Special 
Authorization .............. ............... 25 
General Investigations 
55. Surveys ............... ..................... 25 
56. Collection and Study of Basic Data ........ 25 
*All cost and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear 
at the end of this chapter. 
9-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. AQUATIC PLANT CONTROL 
(R&H) ACT OF 1965) 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Florida. 
Existing project. The authorized project provides 
for control and progressive eradication of water 
hyacinth, alligatorweed, Eurasian water-milfoil, 
and other noxious aquatic plant growths from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in combined interest of navigation, flood 
control, drainage, agriculture, fish and wildlife 
conservation, public health, and related purposes, 
including continued research for development of 
most effective and economical control measures in 
cooperation with other Federal and State agencies 
in accordance with report of Chief of Engineers, 
House Document 251, 89th Congress, 1st session. The 
Water Resource Development Act of 1986 amended 
the R&H Act of 1965 requiring the local sponsor to 
share 50 percent of planning costs and 50 percent 
of research cost that are local in nature. The cost 
of research that is regional or national in scope shall 
be borne fully by the United States. 
Local cooperation. Florida Dept. of Natural 
Resources holds the United States free from 
damages that may occur from operations performed 
in connection with this project and contributes 50 
percent of cost of operations. Compliance with 
requirements of local cooperation is on schedule. 
Operations and results during fiscal year. New 
work: There were 24,501 acres of hyacinth and/or 
water lettuce, 10,195 acres of hydrilla and 194 acres 
of minor plant controlled during the period. Costs 
incurred for engineering and design and supervision 
and administration were $229,575 and $36,562, 
respectively, and $2,510,571 for operations. 
Condition at end of fiscal year. Operations by the 
Corps and the State of Florida are in progress, water 
hyacinths within Florida are under maintenance 
control. Hydrilla is continuing to spread throughout 
the state and is causing major problems in some 
areas. 
2. ARECIBO HARBOR, P. R. 
Location. The harbor is located on the north shore 
of Puerto Rico about 40 miles west of San Juan 
Harbor. (See NOAA Nautical Chart No. 25668.) 
Previous project. For details see page 504 of 1956 
Annual Report. 
Existing project. The project provides for a channel 
25 feet deep and 400 feet wide, with flare at entrance 
and widening at inner end to form a maneuvering 
area, and a stone breakwater 1,200 feet long. Place 
of reference is mean low water. Mean tidal range 
is 1.1 feet. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. A bulkhead wharf 688 by 220 
feet providing a deep water berthing space of 
approximately 500 feet, and a 300 by 100 foot transit 
shed. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and Design costs were 
$18,387.56. 
Condition at end of fiscal year: Project was 
completed in 1944. Breakwater was repaired in 
1952. Wave action has since caused damage. Total 
Federal costs under existing project through 
September 30, 1989 were $1,128,075 for new work 
and $4,310,118 for maintenance, a total of $5,438,193. 
3. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLD, VA. AND 
ST. JOHNS RIVER, FLA. 
(JACKSONVILLE DISTRICT) 
Location. That part of Intracoastal Waterway 
between southerly limit of Fernandina Harbor, 
Florida, at junction of Lanceford Creek and Amelia 
River, and St, Johns River, Fla. (See NOAA Nautical 
Chart No. 11489.) 
Previous project. For Details see page 605 of 1938 
Annual Report. 
Existing project. Channel 12, 90 to 150 feet wide 
from Fernandina Harbor to St. Johns River about 
22 miles long. Plane of reference is mean low water. 
Mean tidal range is 6 feet at Fernandina and 3.8 
feet at St. Johns River. (See Table 9-B for Authorizing 
Legislation.) 
Existing project was authorized by River and 
Harbor Acts of 1913 (HD 898/62/2) and 1938 (HD 
618/75/3). 
Local cooperation. Fully complied with to date. 
Terminal facilities. There is a commercial marina 
located at Sisters Creek. No other facilities exist 
along this section of the waterway and none are 
currently required. 
Condition at end of fiscal year. Project was 
completed in 1941. Total costs under the existing 
project to September 30, 1989, have been $263,659 
9-2

JACKSONVILLE, FLA. DISTRICT 
for new work and $5,300,742 for maintenance, a total 
of $5,564,401. 
4. BAKERS HAULOVER INLET, FLA. 
Location. The Harbor connects the Intracoastal 
Waterway and the Atlantic Ocean and is located 2 
miles north of Miami Beach in Dade County, Florida. 
Existing project. The authorized project provides 
for an entrance channel 11 x 200 feet, thence 8 x 
100 feet to the Intracoastal Waterway, and a marina 
basin 8 x 200 feet. The length of the project is 1.02 
miles. Plane of reference is mean low water. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project was 
completed in December 1964. Project depths have 
been restored. 
5. CANAVERAL HARBOR, FLA. 
Location. The harbor is located on the east coast 
of Florida in Canaveral Bight, about 146 miles south 
of the entrance to Jacksonville Harbor and 69 miles 
north of the entrance to Fort Pierce Harbor. (See 
NOAA Nautical Chart Nos. 11478 and 11484.) 
Existing project. The authorized project provides 
for maintenance of the 44-foot-deep entrance channel 
and 35-foot-depth turning basin; construction and 
operation of a sand transfer plant; relocation of the 
perimeter dike about 4,000 feet westward and 
extension of the harbor westward; two entrance 
jetties 100 feet long (constructed of native stone core 
and granite sides and cap); a lock; a channel and 
turning basin 31 feet deep near the relocated dike; 
and a barge canal 12 by 125 feet from the turning 
basin to the Atlantic Intracoastal Waterway. Plane 
of reference is mean low water (Banana River) for 
barge canal. The project is about 11.5 miles long. 
Mean tidal range is 3.5 feet at the entrance and 
practically non-tidal in Banana and Indian Rivers. 
(See Table 9-C for Data Relative to Lock.) 
Estimated cost (Oct. 1989 price levels) of the 1962 
modification to the project is $17,062,000 Federal 
cost and $4,695,000 non-Federal cost ($138,000 
contributed funds and $4,557,000 other costs); 
$700,000 costs to NASA and $85,000 costs to U.S. 
Coast Guard. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must; provide all 
lands, rights-of-way, spoil-disposal areas, retaining 
dikes, and embankments; hold United States free 
from damages; provide and maintain four-lane 
bridge and roadway subject to Federal contribution 
of 65.3 percent of constructing roadway subject to 
Federal contribution of 65.3 percent of cost of 
constructing bridge and 51.2 percent of constructing 
roadway; provide public terminal and transfer 
facilities; and make alterations as required in 
berthing facilities. For further details see Senate 
Document 140, 87th Congress, 2nd session. Non- 
Federal contribution for new work is $1,106,000. 
Terminal facilities. Canaveral Harbor has 27 
commercial waterfront facilities. The General Cargo 
Facilities consist of 1,900 feet of usable berthing 
space and 5 transit sheds with a total shed storage 
space capacity of 168,000 square feet. The Oil 
Handling Facilities operate with 3,760 feet of usable 
berthing space and 22 storage tanks providing a total 
of 1,195,620 barrels of tank storage. Available 
warehouse storage includes 28,000 square feet of dry 
storage and 2,500,000 cubic feet of cold storage. Two 
hundred sixty-six acres of open storage is also 
available. 
Two cruise ship berths totaling 1200 feet long by 
41-foot depth and two 8800 square foot cruise 
terminals are also located on the south side. The 
western cruise ship berth is equipped with a roll on/ 
off ramp and is adjacent to 20 acres of trailer storage 
area. 
Hoisting facilities consist of one 45-ton floating 
crane and crawler and mobile cranes, with capacities 
from 70 to 200 tons, available from local crane rental 
services. There are tow water-front marine repair 
facilities with the nearest drydock facilities located 
at Port Everglades and Jacksonville. Two tugs with 
ratings of 1,600 and 2,250 horsepower are also 
available. There is no rail service available at the 
port. The nearest rail service is the Florida East 
Coast Railway located 9 miles away. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. New 
Work: Harbor extension contract underway at a cost 
of $2,658,723. Engineering and design costs were 
$12,060. 
Maintenance: Maintenance and operation of lock 
and dam amounted to $361,968 for the fiscal year. 
Natural resource management cost $73,233. Condition 
and operation studies, environmental studies 
and periodic inspections cost $301,334. Real estate 
management was $23,201. Contracts for FY 89 for 
maintenance dredging of the entrance channel and 
the inner channel were $3,870,391. Engineering and 
design and supervision and administration costs 
were $235,810 and $80,056 respectively. 
Condition at end of fiscal year. The existing project 
is about 97 percent completed. The perimeter dike 
and jetties are in good condition. 
9-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Work remaining to complete the project is 
completion of the harbor extension and construction 
of the sand transfer plant. 
6. CHANNEL FROM NAPLES TO 
BIG MARCO PASS, FLA. 
Location. Naples Bay is on the southwestern side 
of the Florida peninsula about 35 miles south of the 
mouth of the Caloosahatchee River and approximately 
1 mile inland and parallel to the Gulf of 
Mexico coastline. (See NOAA Nautical Chart No. 
11430.) 
Existing project. The authorized project provides 
for an interior channel 6 by 70 feet from Naples to 
Big Marco Pass; a channel 12 by 150 feet from the 
Gulf of Mexico to Gordon Pass, thence 10 by 100- 
70 feet to a 10-foot-depth turning basin in the upper 
Naples Bay; and an 8-foot depth turning basin at 
the municipal yacht basin. Plane of reference is mean 
low water. Mean tidal range is 2.1 feet. (See Table 
9-B for Authorizing Legislation.) 
For further details see Annual Report of 1962. 
Local cooperation.. Fully complied with to date. 
Contributed funds for new work were $159,975. 
Terminal facilities. Four seafood packing houses, 
4 marine repair yards; a municipal pier and basin 
for use by recreational boats; and numerous private 
piers and slips for both commercial and recreational 
craft are available. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project is 
complete. 
7. CHARLOTTE HARBOR, FLA. 
Location. The Harbor is located on the west coast 
of Florida about 68 miles south of the entrance to 
Tampa Bay and 150 miles north of Key West. (See 
NOAA Nautical Chart No. 11429.) 
Previous projects. For details, see page 457 of 1959 
Annual Report. 
Existing project. The authorized project provides 
for a channel 32 by 300 feet, inCreased to 700 feet 
at the bend, from the Gulf of Mexico to Port Boca 
Grande to and including a turning basin 200 feet 
square at the municipal terminal at Punta Gorda. 
Plane of reference is mean low water. The project 
is about 29.5 miles long. 
Mean tidal range is one foot at Port Boca Grande 
and 1.4 feet at Punta Gorda. Extreme range is about 
3 feet at Port Boca Grande and 3.8 feet at Punta 
Gorda. Strong southwesterly winds raise water level 
about 1.5 feet; strong northerly and easterly winds 
lower it about one foot. (See Table 9-B for Authorized 
Legislation.) Estimated cost of new work (Oct. 1988 
price levels) $2,350,000 Federal and $2,360,000 non- 
Federal ($2,360,000 contributed funds.) 
Local cooperation. Local cooperation is fully 
complied with to date. 
Terminal facilities. Existing facilities consist of a 
phosphate wharf at Port Boca Grande and a 
municipal earthfill pier about 850 feet long at Punta 
Gorda, both open to the public. Railway connections 
are available at Port Boca Grande, and highway and 
railway connections are available at Punta Gorda. 
There is a tank farm at Port Boca Grande for storage 
and rehandling of bunker fuel oil and numerous 
facilities are available in the area for docking and 
servicing small craft. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost 
$156,941. Engineering and design and supervision 
and administration costs were $26,169 and $484, 
respectively. 
Condition at end of fiscal year. The project was 
completed in 1959. 
Total costs under existing project through September 
30, 1989 have been $533,169 for new work 
and $12,477,580 for maintenance, a total of 
$13,010,749. In addition, $15,563 was expended from 
contributed funds for new work in Boca Grande 
entrance channel. 
8. CROSS FLORIDA BARGE CANAL 
Location. The proposed canal extends up the St. 
Johns River, past Palatka, thence up the valley of 
the Oklawaha River across the divide south of Ocala, 
and down the valley of the Withlacoochee River to 
the Gulf of Mexico, about 95 miles north of Tampa, 
Florida. 
Existing project. The authorized project provides 
for a lock canal with project depth of 12 feet and 
a minimum bottom width of 150 feet, with five locks 
and two earth dams. Project including the section 
in the St. Johns River is 184 miles long. (See Table 
9D for Locks and Dams.) 
Operation and maintenance of the locks and dams 
is a Federal responsibility. Estimated cost of new 
work (1970) is $179,000,000 Federal, and $19,500,000 
non-Federal for lands, rights-of-way, and other costs. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction of canal; 
9-4

JACKSONVILLE, FLA. DISTRICT 
hold the United States free from damages; and 
operate and maintain all highway bridges and 
roadways built in connection with project. 
Terminal facilities. None. 
Operations and results during fiscal year. New 
Work: Engineering and design costs were $159,240. 
Maintenance: (See Table 9-E for work accomplished.) 
Regulation. 
a. Lake Ocklawaha. During the period the lake 
continued to be regulated at 18.0 feet, NGVD by 
discharging through the Rodman spillway. 
b. Lake Rousseau. During the period, the lake 
continued to be regulated at 27.5 ft., NGVD by 
discharging through the Inglis Main and Bypass 
Spillways. 
Condition at end of fiscal year. Construction of 
project commenced February 25, 1964, and is 36 
percent completed. Inglis Lock, Dam, and Spillway; 
Rodman Dam and Spillway, Eureka Lock, Dam, and 
Spillway; Henry H. Buckman Lock; and canal from 
Palatka to Lake Ocklawaha and from Withlacoochee 
River to Gulf of Mexico, including Inglis Bypass 
Channel, are completed. Construction work on the 
project was terminated in FY 1971 by order of the 
President. A restudy report and environmental 
impact statement were completed in February 1977. 
9. EAU GALLIE HARBOR, FLA. 
Location. The Harbor is located on Indian River 
about midway of the State of Florida, 176 miles south 
of Jacksonville Harbor and 174 miles north of Miami 
Harbor. 
Existing project. The authorized project provides 
for a channel 8 x 100 feet from Indian River to and 
including a 300 x 600-foot turning basin in Eau 
Gallie. The project is about 2,700 feet long. Plane 
of reference is mean low water. The harbor is almost 
nontidal. 
Local cooperation. Fully complied with to date. 
Terminal facilities. A privately owned boatyard 
in Eau Gallie Harbor provides more than 600 feet 
of docking space used chiefly by pleasure boats. 
There are also two marine railways and repair and 
storage facilities available. The facilities are 
considered adequate for the present needs of 
navigation. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project was 
completed in 1939. In December 1982, the 
controlling depth of the channel was 5 feet. 
10. FERNANDINA HARBOR, FLA. 
Location. Entrance to the harbor is located on the 
northeast coast of Florida about 95 miles south of 
the entrance to Savannah Harbor, Georgia, and 22 
miles north of the entrance to Jacksonville Harbor, 
Florida. (See NOAA Nautical Chart No. 11503.) 
Existing project. The authorized project provides 
for a 32-foot-depth channel (maximum channel in 
active status: 28 feet) generally 300-400 feet wide 
from deep water in the ocean to the junction of 
Lanceford Creek with Amelia River; an 800-footwide 
turning basin at the first bend below Lanceford 
Creek; and two jetties, 19,150 and 11,200 feet long. 
Plane of reference is mean low water. The project 
is 7 miles long. Mean tidal range is 5.8 feet on the 
bar and 6 feet in the inner harbor. (See Table 9-B 
for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. Non- 
Federal contribution for new work was $875,000. 
Terminal facilities. There are two large wharves 
operated by industrial plants; twelve wharves 
serving fishing boats, recreational craft, and other 
vessels; three oil handling wharves with pipelines; 
and a Municipal Marina and Sportsman's Wharf 
with public facilities for small craft. Total berthing 
space is approximately 4,065 feet. Most terminals are 
served by rail, and all have highway access. 
Facilities are considered adequate for existing 
commerce. (See Post Series No. 16 (Part 2), 1964.) 
Operations and results during fiscal year. New 
work: Engineering and design costs were $74,855. 
Maintenance: Condition and operation studies cost 
$59,696. Maintenance dredging by government, 
Hopper and Contract Dredge, was $664,893.* 
Condition at end of fiscal year. The active portion 
of the existing project is complete. Jetties are in poor 
condition and are badly in need of repair. Remaining 
work is to deepen the inner harbor channel and 
turning basin to 32 feet when and if the presently 
inactive 1950 authorization is reactivated. The 
entrance channel has been deepened to 40 feet for 
the Kings Bay project. 
*Engineering and design and supervision and administration were 
$38,592 and $3,839 respectively. 
11. FORT MYERS BEACH, FLA. 
Location. Fort Myers Beach is on Estero Island 
near the mouth of the Caloosahatchee River, about 
20 miles below Fort Myers and 110 miles south of 
Tampa, Florida. (See NOAA Nautical Chart No. 
11427.) 
Existing project. The authorized project provides 
for a channel 12 by 150 feet from that depth in San 
9-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Carlos Bay into Matanzas Pass, thence 11 by 125 feet 
in Matanzas Pass to and including a turning basin 
2,000 feet upstream from the upper shrimp 
terminals. Plane of reference is mean low water. 
Project is 2.5 miles long. 
Mean tidal range is 1.7 feet. Spring range is about 
2.3 feet. Strong northerly winds lower the water 
surface 1 to 2 feet; strong southerly winds have an 
opposite effect. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are three shrimppacking 
houses and several fish-packing houses, two 
marine railways, a fuel terminal and an ice manufacturing 
plant in the area. There are several commercial 
facilities for servicing shrimp boats. 
Recreational craft facilities include nine marinas, a 
boat motor testing laboratory which is closed, and 
numerous privately owned piers and wharves. All 
terminals have highway access. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost 
$11,488. 
Condition at end of fiscal year. The project is 
complete. 
12. FORT PIERCE HARBOR, FLA. 
Location. On east coast of Florida, about 218 miles 
south of entrance to St. Johns River and about 124 
miles north of entrance to Miami Harbor. (See 
NOAA Nautical Chart No. 11475.) 
Existing project. A channel 350 feet wide at the 
27-foot contour in the ocean, tapering to a width of 
200 feet at Sta. 100 + 00, thence 200 feet wide to Sta. 
30 + 00, and thence flaring to a turning basin 900 
feet wide. Entrance channel is 27 feet deep to Sta. 
130 + 00 and thence 25 feet deep to and including 
the turning basin. Project includes the maintenance 
of two jetties and shore revetments at the inlet. 
Length of project is about 3.5 miles. 
Mean tidal range is 2.6 feet at the entrance and 
0.7 feet at terminals. (See Table 9-B for Authorization 
Legislation.) 
For further details see 1961 Annual Report. 
Estimated cost of new work (Oct. 1988 price levels) 
$4,290,000 Federal and $2,418,000 non-Federal 
($1,650,000 contributed funds, $660,000 reimbursement, 
and $108,000 other cost); $20,000 costs to Coast 
Guard. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was $18,574. 
A 25% contribution and an additional 10% reimbursement 
over 30 years from locals is required. 
Terminal facilities. Two earth-filled piers forming 
a slip 200 feet by 300 feet, with bulkhead wharf at 
inner end, affording berthing space of about 1,653 
feet. The south pier and bulkhead wharf are 
municipally owned. Facilities also include a cooling 
plant, a warehouse and a fruit packing house. The 
north pier is served by railway and both piers by 
highway connections. North of the turning basin 
local interests have provided deep-draft berthing 
and pier facilities. Also available is a bulkhead wharf 
with a depth of 25 feet with ample room for open 
storage and with tank storage for petroleum in the 
rear. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Ocean disposal studies cost $18,895. 
Maintenance dredging costs were $411,021. Engineering 
and design costs, and supervision and 
administration costs were $45,258, and $31,114 
respectively. 
Condition at end of fiscal year. The project was 
completed in 1938 except for the fishing walkway 
atop the south jetty which was completed by local 
interests in 1968. Local interests installed lighting 
atop the jetty in 1969. 
The south jetty and revetments are in good 
condition. 
13. INTRACOASTAL WATERWAY, 
CALOOSAHATCHEE RIVER TO 
ANCLOTE RIVER, FLA. 
Location. The Waterway extends from the mouth 
of the Caloosahatchee River at Punta Rassa, Florida, 
to the mouth of Anclote River, Florida, following in 
general an almost continuous series of protected 
inside waterways along the gulf coast of Florida. (See 
NOAA Nautical Charts Nos. 11411, 11425 and 
11427.) 
Previous projects. For details see page 767 of 1945 
Annual Report. 
Existing project. The authorized project provides 
for a channel 9 by 100 feet from Caloosahatchee 
River to Anclote River; deepening the existing 
channel at Caseys Pass to 9 feet; a channel 6 by 80 
feet (Cats Point Channel) along the southeastern side 
of Boca Ciega Bay past Frenchman Creek and 
Gulfport; maintenance of bulkheads, revetments, 
and two jetties built at Caseys Pass under previous 
project; and improvement and maintenance of 
Sunshine Skyway Channel. Plane of reference is 
mean low water. The project includes about 160 
miles of channels. 
9-6

JACKSONVILLE, FLA. DISTRICT 
Mean ranges of tide are 1.7 feet at Punta Rassa, 
1 foot at Port Boca Grande, 1.4 feet in Tampa Bay 
at Anna Maria, and 2 feet at entrance to Anclote 
River. Extreme ranges are about 4.5 feet at Punta 
Rassa, about 3 to 4 feet between Port Boca Grande 
and Corey Causeway over Boca Ciega Bay, and 
about 5.5 feet at entrance to Anclote River. 
Southerly winds over the area generally raise water 
level by 1 to 1.5 feet; northerly winds lower water 
level by 1 to 2 feet. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Existing facilities include one 
municipal concrete pier, one railway pier, one freight 
wharf, one marginal wharf 500 feet long on terminal 
island, and eleven privately owned landings, all at 
Sarasota. Municipal pier and freight wharf are open 
to the public. All piers have highway connections. 
There are six wharves along Boca Ciega Bay and a 
number of small privately owned piers and wharves 
at various points along waterway for use of commercial 
fishing boats and recreational craft. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Maintenance of channel slopes and berms 
cost $8,955. Real estate audits and administration 
costs were $18,965. Condition and operations studies 
cost $35,348. 
Condition at end of fiscal year. Existing project 
is complete. A contract to maintain the jetties at 
Casey's Pass was completed in 1983. 
Total Federal costs under existing project through 
September 30, 1989 were $7,597,078 for new work 
and $5,673,153 for maintenance, a total of 
$13,270,231. In addition, $14,473 contributed funds 
were expended for Sunshine Skyway and Boca Ciega 
Bay channels. 
14. INTRACOASTAL WATERWAY, 
JACKSONVILLE TO MIAMI, FLA. 
Location. The waterway extends from Jacksonville 
to Miami, Florida, following the St. Johns River 
to the mouth of Pablo Creek and thence following 
in general an almost continuous series of protected 
inside waterways along the Atlantic coast of Florida 
to Miami. (NOAA Nautical Chart Nos. 11489, 11485, 
11472 and 11467.) 
Previous projects. For details, see pages 618-619 
of 1938 Annual Report. 
Existing project. The authorized project provides 
for a channel 12 by 125 feet from Jacksonville to 
Miami, modified to 10-foot depth from Fort Pierce 
to Miami by Chief Engineer's report of July 22, 1960; 
side channels at Sabastian and Daytona Beach and 
turning basins at Sabastian and Vero Beach, all to 
an 8-foot depth, and operation and maintenance of 
Palm Valley highway bridge. Project is 370 miles 
long, including 21 miles in Jacksonville Harbor. 
Mean range of the tide is 3.8 feet at St. Johns River, 
0.7 foot in the Indian River at Fort Pierce, 1.8 feet 
in Lake Worth at Port of Palm Beach terminals, 2.3 
feet at the Port of Palm Beach terminals, 2.3 feet 
at the Port Everglades terminals, and 2 feet in 
Biscayne Bay. The extreme range is about 7 feet at 
St. Johns River, 1.5 feet at Fort Pierce, and 3 feet 
in Biscayne Bay. Plane of reference is mean low 
water. Tidal effect is imperceptible at points along 
waterway distant from inlets. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was $61,000. 
Terminal facilities. There are a number of privately 
owned piers, wharves, and landings at various 
points along waterway. Terminals with railway 
connections are available at Jacksonville, Fort Pierce, 
West Palm Beach, Port Everglades, and Miami. 
Municipal piers or wharves have been constructed 
at Titusville, Cocoa, Melbourne, and Vero Beach for 
handling general freight and at St. Augustine, 
Daytona Beach, New Smyrna Beach, Eau Gallie, 
West Palm Beach, Delray Beach, Fort Lauderdale, 
and Miami for use of recreational craft. Yacht basins, 
open to the public, have been provided at Jacksonville 
Beach, Daytona Beach, Titusville, Eau Gallie, Vero 
Beach, Fort Pierce, West Palm Beach, Fort Lauderdale, 
Hollywood, and Miami. Facilities are considered 
adequate for existing commerce. (For further 
details on facilities at Jacksonville, see Port Series 
No. 15, 1969, and at Palm Beach, Port Everglades, 
and Miami, see Port Series No. 16, Revised 1972.) 
Operations and results during fiscal year. Maintenance: 
The cost for maintenance dredging in FY 
88 was $330,578. Condition and operation studies and 
Environmental studies cost was $303,752. Real 
estate management was $166,418. Engineering and 
design and supervision and administration costs 
were $156,359 and $26,202, respectively. The 
highway bridge bear Palm Valley was operated and 
maintained at a cost of $60,506. 
Condition at end of fiscal year. The existing project 
as modified by the Chief of Engineers is complete except 
for construction of the channel and turning basin 
at Sebastian, Florida, which is in an inactive status. 
Total Federal costs under existing project through 
September 30, 1989, were $19,156,822 for new work; 
$30,196,444 for maintenance, a total of $49,353,266 
regular funds. In addition, $2,199,842 has been 
expended from public works funds for new work. 
15. JACKSONVILLE HARBOR, FLA. 
Location. The authorized project comprises the 
9-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
lower 24.9 miles of St. Johns River which empties 
into the Atlantic Ocean near the northeasterly corner 
of the Florida peninsula. (See NOAA Nautical Chart 
No. 11491.) 
Previous projects. For details, see page 607 of 
Annual Report, 1938. 
Existing project. The authorized project provides 
for a channel 38 by 400-1,200 feet from the ocean 
to mile 20 via Dame Point-Fulton Cutoff, thence 
34 feet to Commodore Point, and thence 30 feet deep 
to the F.E.C. Railway bridge at Jacksonville, 
including a 30 foot channel in Arlington Cut and in 
the Old Dame Point- Fulton Channel; maintenance 
of the existing 42 and 40-foot-depth entrance 
channel; maintenance of jetties at channel entrance; 
and constructin of training walls and revetments. 
Plane of reference is mean low water. The project 
is about 26.8 miles long. 
Mean tidal range is 5.3 feet on the bar, 4.9 feet 
at Mayport, 2.6 feet at Dame Point, and 1.1 feet at 
Jacksonville. The extreme range varies from about 
9 feet on the bar to about 1.5 feet at Jacksonville. 
Strong northeasterly winds raise the water level 
about 2 feet at Mayport and Jacksonville. Strong 
southwesterly winds lower the water about 1.5 feet 
at Mayport and 1 foot at Jacksonville. (See Table 9- 
B for Authorizing Legislation.) 
Local cooperation. Local interests have fully 
complied with requirements of local cooperation for 
work performed to date. For work authorized by the 
1965 River and Harbor Act, local interests were 
required to contribute 2.6 percent of the contract 
price plus supervision and administration for work 
provided by the Corps; provide all lands and rightsof-
way; save the United States free from damages; 
and provide and maintain public terminal and 
transfer facilities. Assurances of local cooperation 
for this work were accepted February 11, 1966. Non- 
Federal contribution for new work was $927,654. 
Terminal facilities. Jacksonville Harbor has 84 
waterfront facilities. Available at the General Cargo 
Facilities are 11,140 feet of usable berthing space 
and 12 transit sheds with a total storage space of 
1,009,800 square feet. The Oil Handling Facilities 
consist of 7,843 feet of usable berthing space and 179 
storage tanks providing a total of 8,478,900 barrels 
of tank storage. Warehouse storage at the port 
includes 3,266,900 square feet of dry storage and 
4,071,100 cubic feet of cold storage. Available open 
storage is 233 acres. 
Four fixed cranes with capacities from 40 to 100 
tons are located at the port. Available locally are 
crawler and truck cranes with capacities up to 100 
tons. Various phases of marine repair work are 
accomplished by 7 waterfront repair facilities and 
numerous other companies located offwater. Drydock 
facilities consist of 6 floating drydocks with 
capacities from 800 to 33,000 tons. Floating 
equipment includes 25 tugs with up to 3,300 
horsepower and 16 tank barges with capacities up 
to 20,700 barrels. Three major railroads furnish rail 
service from port docks to all points outside of 
Jacksonville. 
Facilities are considered adequate for existing 
commerce. (See Port Series #15, Rev. 1978.) 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost 
$253,097. Real estate management $43,844. Cost 
shared recreation development $1,872. Maintenance 
dredging costs were $25,154. Engineering and 
design and supervision and administration costs 
were $141,396 and $12,493 respectively. 
Condition at end of fiscal year. Construction of the 
modification to the project, authorized by 1965 River 
and Harbor Act, is completed. The north jetty is in 
fair condition and partially submerged at high tide. 
The south jetty was repaired in FY 1985 to prevent 
further damage to the Mayport Naval Station. 
Revetments and retaining walls were in poor 
condition. 
Total Federal costs under existing project through 
September 30, 1989, were $44,165,055 for new work, 
$59,767,275 for maintenance, a total of $103,932,330 
regular funds. In addition $290,013 has been 
expended from public works funds for new work. 
16. JACKSONVILLE HARBOR (MILL 
COVE), FLA. 
Location. The authorized project comprises the 
upper 6 square miles of the Upper St. Johns River 
near the Jacksonville Harbor which empties into the 
Atlantic Ocean near the northeasterly corner of the 
Florida peninsula. (See NOAA Nautical Chart No. 
11491.) 
Previous project. None. 
Existing project. The authorized project provides 
for a channel 38 feet deep by 400-1,200 feet wide 
from ocean to mile 20 via Dame Point-Fulton 
Cutoff, thence 34 feet to Commodore Point, and 
thence 30 feet deep to the FEC railway bridge at 
Jacksonville, including a 30-foot channel in Arlington 
cut in the old Dame Point-Fulton channel; 
maintenance of the existing 42 and 40 foot depth 
entrance channel; widening of channel by 100 feet 
near mile 5 and by 200 feet near mile 7; maintenance 
of jetties at channel entrance; construction of 
training walls and revetments; a navigation and 
floodway channel 26 x 200 feet along south side of 
Commodore Point; on approach and mooring basin 
9-8

JACKSONVILLE, FLA. DISTRICT 
20 feet deep, 1,300 feet long at 20 foot depth contour 
and 600 feet long at pierhead line near Naval Reserve 
Armory in south Jacksonville; a depth of 24 feet 
between that depth contour and the pierhead line 
from Hogan Creek to the foot of Laura St.; and a 
depth of 28 feet to within 60 feet of pierhead line 
between foot of Laura St. and St. Elmo W. Acosta 
(formerly Upper State) bridge. Length of project is 
about 26.8 miles. In addition the Navy has provided 
funds for a deeper Jax Harbor entrance channel 42 
feet deep and 800 long. Intersecting with the Navy's 
Mayport entrance channel to the Mayport Turning 
basin also an extension of the existing project to 
provide 38 foot depth at the Navy fuel depot, 
Drummond Creek. 
Mean tidal range is 4.9 feet at entrance, 4.5 feet 
at Mayport, 3.0 feet at Dame Point, and 1.2 feet at 
Jacksonville. Strong northeasterly winds raise the 
water level about 2 feet at Mayport and Jacksonville. 
Strong southwesterly winds lower the water about 
1.5 feet at Mayport and 1 foot at Jacksonville (See 
Table 9-B for authorizing legislation.) 
Cost estimate for new work (Oct. 1988 price levels) 
was $4,164,000 Federal. 
Local cooperation. In conformance with Section 
221, Public Law 91-611, and prior to commencement 
of construction, the Jacksonville Port Authority, as 
local sponsor, must provide written agreement to the 
following local cooperation requirements: provide 
without cost to the United States all lands, easements, 
and rights-of-way required for construction 
and subsequent maintenance of the project; hold and 
save the United States free from damages that may 
result due to construction and maintenance other 
than damages due to the fault or negligence of the 
United States or its contractors; accomplish without 
cost to the United States such utility and other 
relocations or alterations as necessary for construction. 
Terminal facilities. None. 
Operations and results during fiscal year. New 
work: Mill Cove Restoration Project cost was 
$2,893,518. Engineering and design and supervision 
and administrations costs were $628 and $87,425, 
respectively. 
Maintenance: None. 
Condition at end of fiscal year. Total cost under 
existing project through September 30, 1989 was 
$3,356,050 Federal funds. 
17. JOHNS PASS, FLA. 
Location. A natural inlet on the west coast of 
Florida connecting Boca Ciega Bay with Gulf of 
Mexico. The pass is located about 8 miles morthwest 
of lower Tampa Bay directly across Boca Ciega Bay 
from St. Petersburg, Fla. (See NOAA Nautical 
Chart No. 11411.) 
Existing project. Channel 10 by 150 feet in the gulf, 
thence 8 by 100 feet inside pass, and 6 by 100 feet 
to the Intracoastal Waterway, and suitable protective 
measures over a frontage of approximately one 
thousand linear feet of shore along the north end of 
Treasure Island. Plane of reference is mean low 
water. Mean range of tide is 1.5 feet. Project is about 
2.6 miles long. 
Project was authorized December 2, 1964 by Chief 
of Engineers under Section 107 of the 1960 River 
and Harbor Act and by Section 110 of the 1966 River 
and Harbor Act. 
Local cooperation. Fully complied with to date. 
Terminal facilities. Only small marinas and repair 
yards for recreational craft in the general vicinity. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and Design Costs to support 
maintenance dredging were $32,425. 
Condition at end of fiscal year. Project was 
completed in 1968. 
18. LONGBOAT PASS, FLA. 
Location. Longboat Pass is located on the west 
coast of Florida about 11 miles northwest of Sarasota 
and 23 miles south of St. Petersburg. Located in 
Manatee County, it is one of several natural inlets 
connecting Sarasota Bay, a tidal estuary, with the 
Gulf of Mexico. (See NOAA Nautical Chart No. 
11425). 
Existing project. The authorized project provides 
for an entrance channel 12 by 150 feet from the Gulf 
to Longboat Pass Bridge, thence a channel 10 by 100 
feet from Longboat Pass Bridge along a north to 
northeasterly alignment to the Intracoastal Waterway 
to Cortez Bridge. The mean tidal range is 2.2 
feet and the maximum tidal range is about 5 feet. 
Currents are predominantly tidal. 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. See 1978 
Annual Report for detailed local cooperation 
requirements. Contributed funds for new work were 
$172,324. 
Terminal facilities. From Sarasota north to 
Tampa Bay there are about 28 small craft facilities 
9-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
including marinas, boat repair yards, and boat 
basins along the Intracoastal Waterway. Nine of 
them are located within 2 miles of Longboat Pass. 
Numerous private mooring piers and wharves also 
exist in the area. The marina and repair facilities 
appear adequate for the general boating needs of the 
area. 
Operations and results during fiscal year. Maintenance: 
Engineering and design costs to support 
maintenance dredging were $49,954. 
Condition at end of fiscal year. Construction of the 
project is complete. 
19. MANATEE HARBOR, FLA. 
Location. The project is located in Manatee County 
on the east side of Tampa Bay 10 miles from The 
Gulf of Mexico. (See NOAA Nautical Chart No. 
11414). 
Existing project. The authorized project provides 
for maintenance of the existing 40-foot deep draft 
navigation channel and turning basis which extends 
from the Tampa Bay Channel to berthing facilities 
at Port Manatee. Also provide initial construction 
for a widener at the northwest end of the Manatee 
Harbor Channel and initial construction to deepen 
approximately 6.6 acres adjacent to the southern 
berthing area to provide a larger turning basis. All 
material from the project will be placed on upland 
sites west and northeast of the port slip. 
Estimated cost of new work (Oct. 1988 price levels) 
$8,205,000 Federal and $13,400,000 non-Federal 
($3,250,000 contributed funds and $9,330,000 for 
other costs and reimbursements). 
Local cooperation. Fully complied with to date. A 
25% contribution and an additional 10% reimbursement 
over 30 years from locals are required. 
Terminal facilities. Existing facilities at Port 
Manatee consist of 675 acres of port operational 
lands, a ship basin 1,500 feet long by 788 feet wide; 
and an approximately 3-mile access channel, with 
a design width of 400 feet, which connects with the 
Federally authorized Tampa Bay Channel. The 
Manatee project was constructed between August 
1968 and February 1970. The required design depth 
was 40 feet, and the dredging contractor was allowed 
a pay overdepth of 2 feet. Port Manatee also operates 
its own terminal railroad, which is licensed under 
the Interstate Commerce Commission, and publishes 
a switching tariff as a Class III railroad. It also 
maintains and operates two switch engines and 
about 30,000 feet of track which connect with the 
Seaboard Coastline Railroad. 
Operations and results during fiscal year. New 
Work: Engineering and design cost was $218,089. 
Condition at end of fiscal year. Construction has 
not started. LCA will be negotiated in 4th Quarter 
FY 1990. Construction scheduled to start late FY 
1990. 
20. MAYAGUEZ HARBOR, P.R. 
Location. The project is on the west coast of Puerto 
Rico, about 110 miles by water from San Juan 
Harbor. (See NOAA Nautical Chart No. 25673). 
Existing project. The authorized project provides 
for a 30 by 1,000 foot approach channel to the deep 
water terminal, decreasing to a 500 foot width 
opposite westerly end of terminal, thence the same 
width to easterly end of terminal. (See Table 9-B for 
Authorizing Legislation). 
Local cooperation. Fully complied with to date. 
Terminal facilities. A modern deep water terminal 
is located in the northeast section of the harbor 
consisting of a bulkhead wharf about 1,270 feet long 
with a storage transit shed 800 by 60 feet immediately 
shoreward. The Puerto Rico Industrial Development 
Company, an agency of the Commonwealth of 
Puerto Rico, owns a bulkhead wharf of about 200 
feet in line with the existing deep water terminal 
plant located within the industrial harbor area. In 
addition, Bumble Bee Packing Company, Inc., owns 
and operates a dock of about 200 feet for docking 
tuna fish boats. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design costs to support FY 
89 maintenance dredging were $716. 
Condition at end of fiscal year. Project was 
completed in 1934. 
21. MELBOURNE HARBOR, FLA. 
Location. The project is on Indian River about 
midway of the State of Florida, 179 miles south of 
Jacksonville Harbor and 171 miles north of Miami 
Harbor. 
Existing project. The authorized project provides 
for a channel 8 x 100 feet from Indian River to a 
400- x 800-foot turning basin in Crane Creek. Project 
is about 3,150 feet long. Plane of reference is mean 
low water. The harbor is almost non-tidal. 
Terminal facilities. The Municipal Marina on the 
north end of the turning basin has a 350-foot steel 
bulkhead with eleven finger piers about 40 feet long 
each. There are also two privately owned storage and 
repair facilities and several privately owned 
9-10

JACKSONVILLE, FLA. DISTRICT 
boathouses and docks. The facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
None. 
Condition at end of fiscal year. The project was 
completed in 1938. As of September 1984 channel 
depths as authorized were available throughout the 
project. 
22. MIAMI HARBOR, FLA. 
Location. Miami is near the northern end of 
Biscayne Bay, about 71 miles south of the entrance 
to Palm Beach Harbor. Miami River has its source 
in the Everglades and flows southeasterly to enter 
Biscayne Bay at Miami. (See NOAA Nautical Chart 
No. 11468). 
Existing project. The authorized project provides 
for a 38- by 500-foot channel from the ocean to the 
outer end of the north jetty, thence 36 by 400 feet 
through the entrance and across Biscayne Bay to and 
including a turning basin at the municipal terminals; 
a 36-foot depth turning basin at Fisher Island; 
two rubblestone jetties at the entrance; a channel 15 
by 200 feet from the mouth of Miami River to the 
turning basin at the municipal terminals; a channel 
8 by 200 feet from the mouth of Miami River to the 
Intracoastal Waterway and thence 100 feet wide to 
Government Cut; a channel 15 feet deep in Miami 
River varying in width from 250 feet at mouth to 
90 feet inland; and a channel 12 by 100 feet from 
Miami to a harbor refuge in Palmer Lake. Plane of 
reference is mean low water, except for 15-foot 
channel in Miami River where depths are based on 
flood conditions. Total length of the project is about 
15.3 miles. 
Mean tidal variation is 2.5 feet at entrance and 
2 feet in the bay. Extreme variation is about 4.5 feet 
at entrance and 3 feet in Biscayne Bay. Strong 
easterly winds raise the water level about 1.5 feet 
at entrance and 1 foot in the bay. Strong westerly 
winds lower water level about 1 foot at entrance and 
about 0.5 foot in the bay. (See Table 9-B for 
Authorization Legislation). 
Local cooperation. Fully complied with to date. See 
1978 Annual Report for detailed local cooperation 
requirements. Non-Federal contribution for new 
work was $2,300,710. 
Assurances of local cooperation for the 1968 
modification to the project were accepted December 
18, 1968. 
Terminal facilities. There are 91 commercial 
waterfront facilities serving the port. The General 
Cargo Facilities include 21,373 feet of usable 
berthing space, 13 transit sheds with a total capacity 
of 474,300 square feet, and 9 freight stations with 
a total storage capacity of 270,400 square feet. Oil 
Handling Facilities consist of 2,714 feet of usable 
berthing space and 36 storage tanks with a total 
storage capacity of 744,475 barrels. Available 
sharehouse storage includes dry storage at 1,450,500 
square feet and cold storage at 11,204,000 cubic feet. 
There are 117.1 acres of open storage at the port. 
Hoisting Facilities located at the port include two 
40-ton cranes and cranes with capacities up to 200 
tons available through local rental. Twelve waterfront 
repair yards and two offwater yards serve the 
port. Drydock facilities available include 7 marine 
railways and 4 boat lifts with haulout capacities 
ranging from 40 to 1,000 tons and lifting capacities 
ranging from 70 to 500 tons. Nine tugs, with ratings 
up to 3,000 horsepower, and thirteen tank barges, 
with capacities up to 35,000 barrels, are also 
available. Rail Facilities at the port are served by 
the Seaboard Coast Line and the Florida Coast 
Railway. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982). 
Operations and results during fiscal year. Maintenance: 
Condition and operations studies cost 
$122,825. Engineering and design costs were $46,268 
and Real Estate activities were $350. 
Condition at end of fiscal year. Construction of the 
modification to the project, authorized by River and 
Harbor Act of 1968, is complete. South and north 
jetties are in good condition. 
23. NEW PASS, SARASOTA, FLA. 
Location. Sarasota Bay is a tidal lagoon along the 
west coast of Florida immediately south of Tampa 
Bay. New Pass is a gulf inlet across the bay from 
Sarasota, Fla. (See NOAA Nautical Chart No. 
11425). 
Existing project. The authorized project provides 
for an entrance channel 10 feet deep and 150 feet 
wide in the Gulf of Mexico diminishing to 8 by 100 
feet through New Pass and extending across 
Sarasota Bay to the Intracoastal Waterway with side 
channels to, and turning basins at, Payne Terminal 
and city pier. Plane of reference is mean low water. 
Mean range of tide is 1.3 feet in Sarasota Bay; mean 
spring range is 1.7 feet. Project is about 4 miles long. 
(See Table 9-B for Authorizing Legislation). 
Local cooperation. Fully complied with to date. 
Terminal facilities. Consist of Payne Terminal, a 
slip 200 by 650 feet, and city pier, 400 feet long with 
9-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
two finger piers equipped with adequate facilities 
at each location. 
Operations and results during fiscal yar. Maintenance: 
Engineering and design costs to support FY 
90 maintenance dredging were $65,413. 
Condition at end of fiscal year. Project was 
completed in 1964. 
24. OKEECHOBEE WATERWAY, FLA. 
Location. The waterway traverses the southern 
part of the Florida peninsula via the Caloosahatchee 
River, Lake Okeechobee, and St. Lucie Canal, 
connecting coastal waterways along the Gulf and 
Atlantic Shores. (See NOAA Nautical Chart No. 
11428). 
Previous projects. For details, see page 785 of 1949 
Annual Report. 
Existing project. The authorized project provides 
for replacing the old locks on the St. Lucie Canal 
by a single new lock; a channel 10 by 100 feet from 
Ft. Myers for about 5 miles upstream, thence 8 by 
80 to 100 feet to the Intracoastal Waterway, 
Jacksonville to Miami; near Stuart; an 8-foot depth 
basin at Stuart; a side channel at Ft. Myers; 
operation and care of St. Lucie Lock; and mainenance 
of features completed under previous projects 
as follows: a 12- by 200-foot channel from the Gulf 
to Punta Rassa, thence 10 by 100 feet to Fort Myers 
with a 10-foot depth basin at Fort Myers; a 6- by 
80-foot channel along the south shore of Lake 
Okeechobee from Clewiston to St. Lucie Canal; a 6- 
by 60-foot channel in Taylor Creek from the town 
of Okeechobee to the Lake; and operation and care 
of Moore Haven and Ortona Locks. 
(See Table 9-B for Authorizing Legislation). 
For further details see 1962 Annual Report. 
Local cooperation. Fully complied with for 
completion portion of project. Non-Federal contribution 
amounted to $503,700. 
Terminal facilities. There are 3 freight piers, 1 
municipal recreation pier, 4 privately owned piers, 
and a municipal yacht basin on the Caloosahatchee 
River near Fort Myers. The Corps has provided a 
boat basin, launching ramp, and a 120-foot wharf 
on the Caloosahatchee River about one-quarter mile 
below Ortona Lock. there are tie-up dolphins above 
and below all 5 locks. Commercial yacht basins are 
provided on the south side of the Caloosahatchee 
River about halfway between Ortona and Moore 
Haven Locks and about 3 miles east of LaBelle. A 
commercial/municipal yacht basin is provided on the 
north side of the St. Lucie Canal at Indiantown. 
There are numerous small wooden-pile landings 
along the Caloosahatchee River on St. Lucie Canal, 
and on the St. Lucie River, including one railroad 
terminal pier, municipal pier, and a pier for 
handling petroleum products at Stuart. Also, 550 
feet of wharves have been provided on the west side 
of Taylor Creek immediately landward of Hurricane 
Gate No. 6 and 150 feet on the east side of the creek. 
A yacht basin has been provided on the west side 
of the creek immediately landward of the hurricane 
gate. The installations of Taylor Creek are privately 
owned, but are open to the public. A breakwater 
protected harbor is available at Pahokee. There is 
a 440-foot marginal wharf on the Industrial Canal 
at Clewiston; a 125-foot wharf at LaBelle; a 150-foot 
wharf at Belle Glade; a 125-foot wharf at Moore 
Haven; a 50-foot wharf at Alva; and a 30-foot wharf 
on Taylor Creek at the town of Okeechobee. A 
docking facility for loading raw sugar was constructed 
in 1967 on Herbert Hoover Dike near Belle Glade. 
All have highway and/or railway connections. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. (See 
Table 9-F for work accomplished.) 
Condition at end of fiscal year. The project is 
complete except for providing the 8-foot depth basin 
at Stuart, which is inactive. 
Total Federal costs under the existing project 
through September 30, 1988, were $5,178,315 for 
new work, $27,430, 845 for maintenance ($67,558 
excluded which represents services rendered 
without reimbursement), a total of $32,609,160. 
25. OKLAWAHA RIVER, FLA. 
Location. The river has its source in a system of 
large lakes in the central part of the Florida 
peninsula and flows generally northerly, then 
easterly, emptying into St. Johns River 22 miles 
above Palatka. The extreme head of the system is 
considered to be Lake Apopka, 120 miles above the 
river's mouth. 
Previous projects. For details, see page 613 of 1938 
Annual Report. 
Existing project. The authorized project provides 
for a channel 6 feet deep from the river mouth to 
the head of Silver Springs Run; clearing a channel 
to Lake Griffin; maintaining dikes to obtain a 
navigable depth of about 4 feet to Leesburg and 
construction of a lock and dam at Moss Bluff. The 
project length is about 85.7 miles in the river and 
5.4 miles in Silver Springs Run. (See Table 9-B for 
Authorizing Legislation.) 
9-12

JACKSONVILLE, FLA. DISTRICT 
Local cooperation. Fully complied with to date. 
Terminal facilities. Several private and public 
landings and boat-launching ramps are locatedalong 
the river. Public recreation-craft basins and boat 
launching ramps are near Silver Springs and State 
Road 40 and 316 bridges. There is a municipal wharf 
on Lake Griffin at Leesburg. A dam has created Lake 
Ocklawaha (13,000 acres) with egress to the St. Johns 
River through Buckman Lock. Along the lake are 
4 launching ramps; Payne's Landing, Orange 
Springs, Kenwood Landing, and Rodman Recreation 
Area. Access below the dam is at the Ocklawaha Boat 
launch ramp and at State Road 19. Facilities are 
considered adequate for existing commerce. 
Operations at end of fiscal year. Maintenance: 
Channel maintenance costs were $71,731. Real estate 
management costs were $802. 
Condition at end of fiscal year. The project is 
complete except for providing a 6-foot depth channel 
from the mouth of the river to the head of Silver 
Springs run, which is in an inactive status. The Moss 
Bluff lock and dam structure was replaced under 
the Four River Basins, Fla., flood control project. 
Total Federal costs under the existing project 
through September 30, 1988 have been $311,352 for 
new work and $2,165,596 for maintenance, a total 
of $2,476,948. 
26. PALM BEACH HARBOR, FLA. 
Location. The authorized project is located on the 
east coast of Florida about 71 miles north of the 
entrance to Miami Harbor and about 264 miles 
southeasterly from the entrance to Jacksonville 
Harbor. (See NOAA Nautical Chart No. 11472.) 
Existing project. The authorized project provides 
for an entrance channel 35 by 400 feet merging with 
an inner channel 33 by 300 feet to and including a 
turning basin; tank revetment; and restoring jetties. 
Plane of reference is mean low water. The project 
is about 1.6 miles long. 
Mean range of tide in the ocean at the entrance 
is 2.8 feet and at the turning basin, 2.2 feet. Extreme 
range of tide is about 4.5 feet at the inlet and 3 feet 
at the terminals. Seven-foot tidal ranges have 
occurred during storms. For details, see 1962 Annual 
Report. (See Table 9-B for Authorizing Legislation.) 
Local ooperation. Fully complied with to date. For 
requirements, see 1961 Annual Report. 
Terminal facilities. The port has 13 commercial 
waterfront facilities. The General Carge Facilities 
include 5,156 feet of usable berthing space and 6 
transit sheds with a total of 118,030 square feet 
storage capacity. The Oil Handling Facilities consist 
of 10 storage tanks with a total capacity of 2,029,600 
barrels. Usable berthing space is not available at the 
Oil Handling Facilities. Dry storage is available at 
150,500 square feet, cold storage at 19,200 cubic feet 
and open storage at 27.1 acres. 
Seven cranes with capacities from 15 to 230 tons 
are located at the port. There are no floating cranes, 
repair facilities or drydock facilities located at the 
port. A 100 ton vertical boat lift is located on the 
Intracoastal Waterway south of the port for heavy 
lifts. Two tugs with ratings of 900 and 1000 
horsepower are available. The Palm Beach Belt Line 
which connects with the Florida East Coast Railway 
serves the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. New 
work: Engineering and design were $26. 
Maintenance: Condition and operation studies for 
the project totaled $43,899.* A continuing contract 
for maintenance dredging was $816,152. 
Engineering and design and supervision and 
administration costs were $27,285 and $37,490 
respectively. 
Condition at end of fiscal year. The Project was 
completed in 1967. Jetties and revetment are in need 
of repair. The south jetty was completed in FY 86. 
*Real Estate costs were $6,167. 
27. PONCE DE LEON INLET, FLA. 
Location. Ponce de Leon Inlet is on the Atlantic 
coast of Florida about 65 miles south of St. Augustine 
Harbor and 57 miles morth of Canaveral Harbor. 
(See NOAA Nautical Chart No. 11485.) 
Existing project. The authorized project provides 
for an entrance channel 15 by 200 feet across the 
ocean bar, thence 12 by 200 feet and 12 by 100 feet 
through the inlet; thence southward in Indian River 
North, 12 by 100 feet, and northward in Halifax 
River, 7 by 100 feet, each leg continuing to the 
Intracoastal Waterway; ocean jetties on the north 
and south of the inlet 4,200 and 2,700 feet long, 
respectively, and weir in the north jetty with an 
impoundment basin inside the jetty. Plane of 
reference is mean low water. Mean range of tide is 
4.1 feet in the ocean and 2.3 feet inside the inlet. The 
project is about 5 miles long. 
Local cooperation. Fully complied with to date. 
Non-Federal contribution for new work was 
$2,415,600. 
Terminal facilities. None in the immediate area. 
9-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations and results during fiscal year. Maintenance: 
Real estate management costs were $6,238. 
Engineering and design and administrative costs 
were $19,838 and $166,221, respectively.* 
Condition at end of fiscal year. Construction of the 
project is complete. Repair of the north jetty was 
completed in FY 86. 
*A continuing Contract for Maintenance dredging was 
awarded in the amount of $2,609,099. 
28. PONCE HARBOR, P.R. 
Location. Ponce Harbor is an open bay about 
midway on the south coast of Puerto Rico. From the 
center of the city of Ponce, the harbor is about 3 miles 
south. (See NOAA Nautical Chart No. 25677.) 
Previous project. For details, see page 12 of Annual 
Report for 1975. 
Existing project. The authorized project provides 
for a seawall 362 feet long extending northwesterly 
across the rock reef from near the landward end of 
the municipal pier, 30 feet deep and containing about 
18 acres; a breakwater 2400 feet long extending 
southwesterly from Punta Carenero; a channel 36 
feet deep by 600 feet wide extending from the 
Caribbean Sea approximately 2.8 miles up to the 
port, thence a channel 400 feet wide by 36 feet deep 
into the harbor, and a 36-foot-deep, irregularly 
shaped turning basin with a diameter of 950 feet. 
Plane of reference is mean low water. Mean tidal 
range is 0.6 foot, extreme varies between about 1 foot 
below and 2 feet above mean low water. Estimated 
cost of new work (Oct. 1988 price levels) is $6,420,000 
Federal ($6,410,00 Corps and $10,000 U.S. Coast 
Guard) and $4,049,000 non-Federal (other costs). 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Sould provide all lands, 
easements and rights-of-way; provide and maintain 
at local expense depths in berthing areas and local 
access channels; hold United States free from any 
damages resulting from construction and maintenance 
of the project; relocate without cost to the 
United States all cables, sewer mains, water supply, 
drainage and other utility installations as required; 
provide adequate public terminal and transfer 
facilities open to all on equal terms. A letter has been 
received from mayor of Ponce, assuring compliance 
with local requirements and to cost share the project. 
Non-Federal contribution for new work was 
$774,068. A 25% contribution is required and an 
additional 10% reimbursement over 30 years from 
locals. 
Terminal facilities. The municipality of Ponce 
owns and operates the only deep-draft terminal 
facilities in Ponce Harbor, which consist of a 
municipal pier 515 feet long and 108 feet wide, and 
a bulkhead wharf 3,811 feet long. Both are equipped 
for transfer and storage of freight. A 40 ton container 
lift shore crane is available for the handling of loaded 
containers. The municipal pier has a steel transit 
shed 386 by 85 feet. The bulkhead wharf has four 
steel transit sheds totaling over 103,000 square feet. 
Three concrete and steel warehouses are available 
providing 800,000 square feet for general storage. 
Open storage areas for structural steel, lumber, and 
other bulk and package commodities are also 
provided. Bulk cement is handled and loaded into 
cement cargo ships by the use of a private pipeline 
loading facility. A tuna fish processing and canning 
factory is located on the premises, with direct access 
to the bulkhead wharf. Existing facilities are open 
to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New 
Work: Engineering and design and supervision and 
administration costs were $9,441 and $222,912 
respectively. 
Maintenance: None. 
Condition at end of fiscal year. Construction of the 
1976 modification of the project has not commenced. 
South and north jetties are in fair condition. 
29. PORT EVERGLADES HARBOR, FLA. 
Location. The harbor is on the east coat of Florida 
about 23 miles north of Miami and about 48 miles 
south of Palm Beach Harbor, Florida. (See NOAA 
Nautical Chart No. 11470.) 
Existing project. The authorized project provides 
for an ocean entrance channel 45 by 500 feet through 
an ocean bar tapering to 42 by 450 feet between 
rubblestone entrance jetties, and continuing at that 
depth to an irregularly flared entrance and turning 
basin of same depth; enlarging Pier 7 channel to 36 
by 400 feet for distance of about 1,600 feet; maintenance 
of the locally dredged channel opposite 
Berth 18 to 36 feet deep over a length of 700 feet 
with varying widths of 200 to 150 feet; construction 
of a south jetty fishing walkway; and, maintenance 
of the jetties. Plane of reference is mean low water. 
The project is about 1.9 miles long. Mean range of 
tide is 2.5 feet at the entrance and 2.3 feet at the 
terminals; extreme range is about 4.5 feet with storm 
tides of about 6.5 feet. 
Estimated cost of new work (Oct. 1980 price levels) 
of the 1974 authorization is $33,800,000 Federal 
(Corps of Engineers) cost and $7,062,000 non- 
Federal cost, $160,000 contributed funds and 
9-14

JACKSONVILLE, FLA. DISTRICT 
$6,902,000 other costs). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local Cooperation has been 
fully complied with for work completed to date. For 
work under House Document 144/93/1, local interest 
must: provide all lands, easements, and rights-ofway; 
save United States free from damages; 
accomplish utility and other relocations or alterations; 
provide depths in berthing areas and local 
access channels serving the terminals commensurate 
with depths provided in the related project areas; 
establish regulations prohibiting discharge of 
pollutants into waters of the channel by users thereof; 
prohibit erection of any structure within 100 feet of 
project channel as authorized at time of construction; 
provide and maintain public terminal and transfer 
facilities; contribute 50 percent of total first costs of 
recreational jetty fishing facility; and operate and 
maintain jetty fishing facility. Assurances of local 
cooperation for the 1974 authorization have been 
furnished by the local sponsor. 
Terminal facilities. There are 22 commercial 
waterfront facilities serving the port. The General 
Cargo Facilities include 13,807 feet of usable 
berthing space, 7 transit sheds with a total capacity 
of 393,870 square feet, and 6 container yards with 
space for 3,965 containers. Oil Handling Facilities 
consist of 232 storage tanks with a total storage 
capacity of 9,564,800 barrels. There is no usable 
berthing space located at the Oil Handling Facilities. 
Dry storage is available at 225,000 cubic feet and 
open storage at 100.3 acres. 
Hoisting facilities available from a local firm 
include 5 cranes with capacities from 20 to 155 tons. 
No floating cranes or derricks for heavy lifts are 
available at the port. There are 2 marine repair 
yards. Drydock facilities include 2 drydocks with 
capacities of 2,200 and 3,200 tons and a 4,270-ton 
vertical boat lift. Three tugs with ratings up to 4,290 
horsepower serve the port. The Port Everglades Belt 
Line connects with the Seaboard Coast Line railroad 
to serve the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series #16, Rev. 1982.) 
Operations and results during fiscal year. New 
work: Contract underway for canals and channels 
cost $244. Engineering and design and supervision 
and administration costs were $2,618 and $4,648, 
respectively. 
Maintenance: Condition and operations studies were 
$20,668. 
Condition at end of fiscal year. Work required to 
complete the project is construction authorized in 
House Document 144/93/1. 
30. REMOVAL OF AQUATIC GROWTH 
FROM NAVIGABLE WATERS IN THE 
STATE OF FLORIDA. 
Location. Water hyacinth, hydrilla and water 
lettuce are found in freshwater streams and lakes 
in various parts of the district. 
Existing project. The authorized project provides 
for destruction or removal of aquatic growth in 
navigable waters of the State so far as they constitute 
an obstruction to navigation and commerce, using 
any mechanical, chemical or other means not 
injurious to cattle, and use of log booms to close 
sloughs and backwaters as an auxiliary means. No 
estimate of the final cost of work has been made. 
(See Table 9-B for Authorizing Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. Non required. 
Operations and results during fiscal year. Maintenance: 
Operations continued during the year. (See 
Table 9-B for Authorizing Legislation.) (See Table 
9-G for spraying operations.) 
Condition at end of fiscal year. The project is for 
maintenance of navigable waterways. During the 
year 20,807 acres of floating vegetation (water 
hyacinths and/or water lettuce), and 2,714 acres of 
hydrilla were controlled in approximately 2,200 
miles of waterways. Hyacinths in Lake Okeechobee 
and in St. Johns River Watershed are under 
maintenance control. 
31. ST. AUGUSTINE HARBOR FLA. 
Location. The harbor is on the east coast of Florida, 
about 35 miles south of the entrance to St. Johns 
River and about 180 miles north of Fort Pierce 
Harbor. (See NOAA Nautical Chart No. 11485.) 
Previous project. For details see page 412 of 
Annual Report for 1958. 
Existing project. The authorized project provides 
for a channel 16 feet by 200 feet along the best natural 
alinement as may exist from time to time across the 
new inlet bar, thence 12 feet deep to the Intracoastal 
Waterway; a sandtrap groin on the north side of the 
inlet extending seaward from the shore of Vilano 
Beach, and a sand-tight jetty on the south side of the 
channel extending seaward from the shore of Conch 
Island parallel to and coextensive with the groin, 
future landward extension of the groin and jetty; and 
a channel 10 by 100 feet in San Sebastian River from 
the Intracoastal Waterway to King Street Bridge, 
with a turning basin near the upper end. Length of 
the inlet channel is about 1.5 miles, and length of the 
San Sebastian River channel is about 2.6 miles. Plane 
9-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
of reference is mean low water. The mean tidal range 
is 4.5 feet in the ocean at St. Augustine Inlet and 4.2 
feet at the city waterfront. Strong northerly winds, 
mostly in the winter, lower the water surface about 
1 foot. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are several timber docks 
on the Matanzas waterfront of St. Augustine. In this 
area of the harbor is a concrete dock which serves 
as a municipal yacht pier. It has fuel facilities, 19 
slips and accommodates boats up to 60 ft. in length. 
A large public boat ramp is also available. The 
principal terminals are the numerous shrimp docks 
in the San Sebastian River which flows southward 
through the city into the Matanzas River south of 
the bridge; these consist of timber wharves, with 
frame and corrugated iron warehouses thereon, and 
9 marine railways for small boats. There is also a 
marine supply facility and several boat yards. The 
present terminals have highway connections and 
several of the shrimp docks have rail connections. 
They are considered adequate for existing commerce 
and recreational craft. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Project is completed 
except for the North Jetty which is in a deferred 
status. The groin is in good condition except for the 
300 feet which has subsided to about elevation 3.0 
feet, mean low water. The jetty is in good condition, 
but is submerged at high tide. Total Federal costs 
under the existing project through September 30, 
1989 were $1,405,131 for new work and $4,714,107 
for maintenance, a total of $6,119,238. 
32. ST. JOHN'S RIVER, FLA., JACKSONVILLE 
TO LAKE HARNEY 
Location. Rises in marshes of Brevard County, 
Fla., near east coast, and flows northwesterly to 
Jacksonville, thence easterly into the Atlantic Ocean, 
122 miles south of Savannah River. River is about 
285 miles long, of which 161.5 miles are included 
in project. (See NOAA Nautical Chart No. 11492.) 
Previous projects. Adopted by River and Harbor 
Acts of June 14, 1880 and July 5, 1884. For further 
details see Annual Reports for 1915 and 1938. 
Existing project. Channel 13 feet deep and 200 feet 
wide from Florida East Coast Railway bridge at 
Jacksonville to Palatka, thence 12 by 100 feet to 
Sanford, and thence 5 by 100 feet to Lake Harney, 
with side channel to Enterprise and maintenance of 
two jetties. 
Existing project was authorized by River and 
Harbor Acts of March 2, 1945 (H. Doc. 445, 78th 
Cong., 2d sess.) and July 24, 1946 (S. Doc. 208, 79th 
Cong., 2d sess.). For further details see Annual 
Report for 1962. 
Terminal facilities. There are 36 piers and 
wharves along project, including municipal piers 
and wharves at Green Cove Springs and Palatka, 
12 Navy piers at Green Cove Springs, a municipal 
recreational pier at Sanford, and 19 privately owned 
piers, 5 of which have nearby tank storage facilities 
for petroleum projects. Facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Active portion is 
complete. Condition of project as a whole is adequate 
for present needs of navigation. (For more detailed 
information refer to Annual Report for F.Y. 1963). 
33. ST. LUCIE INLET, FLA. 
Location. The inlet is on the east coast of Florida 
about 19 miles south of the entrance to Fort Pierce 
Harbor, Florida, and 100 miles north of the entrance 
to Miami Harbor, Florida. (See NOAA Nautical 
Chart No. 11472.) 
Previous project. For details see page 764 of 
Annual Report for 1949. 
Existing project. The authorized project provides 
for extending the north jetty about 500 feet and 
modifying existing jetty to provide a sand bypass 
weir section about 500 feet long; excavation of a sand 
impoundment basin adjacent to the bypass weir in 
the north jetty; construction of a south jetty 
consisting of a rubblemound structure about 2,400 
feet long with walkway for recreational fishing; 
channel between existing bar cut and the Intracoastal 
Waterway 10 by 500 feet through the bar cut, 
tapering to 150 feet through the inlet, and 100 feet 
wide and 7 feet deep to the Intracoastal Waterway; 
and transfer of 380,000 cubic yards of material to 
the south beach during each two year maintenance 
period. Plane of reference is mean low water. Total 
project length is about 1.9 miles. Mean tidal range 
is 2.6 feet on the ocean side and about 1 foot on the 
land side of the inlet. 
The estimated cost of the 1974 modification (Oct. 
1979 price levels) to the project is $6,290,000 Federal 
cost and $2,525,000 non-Federal cost ($2,260,000 
contributed funds and $265,000 other costs). (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must: contribute 
19.9 percent of construction cost allocated to 
navigation in the combined project, 23.2 percent 
allocated to beach erosion, and 50 percent of 
construction cost of jetty fishing walkway; provide 
9-16

JACKSONVILLE, FLA. DISTRICT 
39.8 percent of the annual maintenance cost allocated 
to navigation and 23.2 percent of the annual costs 
for maintenance dredging allocated to beach erosion 
control for periodic beach nourishment and 100 
percent of the annual jetty maintenance costs 
allocated to beach erosion control; maintain jetty 
fishing walkway; agree that each five years the 
amount of local cost sharing for maintenance is to 
be adjusted; provide all lands, easements, and rightsof-
way; hold United States free from damages; 
provide marina with mooring facilities and utilities; 
provide and maintain depths in berthing area and 
local access and feeder channels commensurate with 
the depths provided in the project; accomplish such 
alterations as required in sewer, water supply, 
drainage, and other utility facilities, and take action 
to place in effect statutes and/or regulations which 
will protect the water quality for the authorized uses 
of the project. Assurances of local cooperation for the 
1974 modification were signed by the local sponsor 
on August 24, 1978. Non-Federal controbution for 
new work was $3,086,026. 
Terminal facilities. A municipal pier provides 
facilities for docking and servicing charter fishing 
and small recreational craft. At Stuart there is a 
dock for handling bulk petroleum products and 
several marinas which provide facilities for mooring, 
servicing and minor repair of small craft. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition and operations studies 
and environmental dredging studies cost $2,818. 
Maintenance dredging cost was $312,899. Engineering 
and design costs and supervision and administration 
costs were $563 and $47,518 respectively. 
Condition at end of fiscal year. Work required to 
complete the project is construction authorized in 
House Document 294/93/1. Total Federal costs 
under existing project through September 30, 1989 
were $10,948,511 for new work (including $3,086,026 
contributed funds) and $6,609,412 for maintenance, 
a total of $17,557,923. 
34. SAN JUAN HARBOR, P. R. 
Location. San Juan Harbor is on the north coast 
of Puerto Rico and about 35 miles from the island's 
east end and 1100 miles southeast of Miami, Florida. 
(See NOAA Nautical Chart No. 25670.) 
Previous projects. For details see Annual Reports 
for 1915, 1916, 1938. 
Existing project. Modification of the authorized 
project to provide the deepening of the Bar Channel 
to 48 feet and shifting its alinement 350 feet west; 
deepening Anegado and Army Terminal to 40 feet; 
deepening Graving Dock Channel, the Cruise Ship 
Basin, Puerto Nuevo Channel, and San Antonio 
Channel to 36 feet; and deepening Anchorage Area 
E to 38 feet while reducing its size and constructing 
six mooring dolphins within its limits. A 1500-footlong 
extension to San Antonio Channel would be 
added to the Federal project and Sabana approach 
deepened to 32 feet. Estimated cost of new work (Oct. 
1989 levels) $49,570,000 Federal and $29,200,000 non- 
Federal ($19,100,000 contributed funds, $7,630,000 
reimbursement, and $2,470,000 other costs). 
Local cooperation. Should provide all lands, 
easements and rights-of-way; hold the United States 
free from any damages; provide and maintain depths 
in berthing areas and local access and feeder 
channels; provide alterations as required in sewer 
water supply, and other utility facilities. It is further 
recommended that local interests be reimbursed for 
work performed by them on the project subsequent 
to project authorization. A 25% contribution and an 
additional 10% reimbursement over 30 years from 
locals are required. 
Terminal facilities. There are 28 piers and 
bulkhead wharves in the harbor capable of docking 
deep-draft vessels, which have an aggregate berthing 
length of about 23,700 feet. Eleven piers and 
bulkhead wharves are on the north shore, two piers 
and a three-level ramp facility for roll-on/roll-off 
operations at Front Graving Dock turning basin and 
channel, nine at the eastern side and three at the 
western side of the Army Terminal basin and 
channel, and three on the south shore of San Antonio 
Channel. One pier and bulkhead wharf are privately 
owned, seven are U.S. Government property, and 24 
owned by the Commonwealth of Puerto Rico. Twenty 
piers and wharves are equipped with mechanical 
crane transfer facilities. Five wharves are equipped 
with a special crane for the handling of loaded 
containers. Twenty-four are open to general public. 
Pier No. 6 has been repaired and improved in 1985. 
There is an aggregate length of about 1,339 feet 
of berthing space at Catano Point used principally 
by small vessels within the 18-foot draft range. This 
space is also open to the public. In addition, there 
are 10 piers and bulkhead wharves with approximately 
6,910 feet of berthing space owned and 
operated by different agencies of the Federal 
Government. This space is not open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Breakwater 
and jetty maintenance costs were $16,446. 
Maintenance dredging costs were $2,160,000. 
Engineering and design and supervision and 
9-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
administrative costs were $32,476 and $54,372 
respectively. 
Condition at end of fiscal year. Remaining work to 
complete project is modification authorized in 1976. 
Total Federal costs under the existing project 
through September 30, 1989 were $13,027,284 for 
new work and $14,337,931 for maintenance, a total 
of $27,365,215 regular funds. In addition, $747,684 
was expended for new work and $44,730 for 
maintenance from public works funds and $100,000 
for new work from contributed funds. Existing 
project includes the entrance channel and turning 
basin to Army Terminal which cost $1,543,712; this 
expenditure was made from military appropriations 
and is not included in above costs. 
35. TAMPA HARBOR, FLA. 
Location. Tampa Harbor is in a large natural 
indentation of the Gulf of Mexico about midway of 
the west coast of Florida. The entrance is about 220 
miles north of Key West and about 330 miles 
southeast of Pensacola. (See NOAA Nautical Chart 
Nos. 11413 and 11414.) 
Previous projects. For details see page 665 of 1938 
Annual Report. 
Existing project. The authorized project provides 
for a channel from the Gulf of Mexico to Port Sutton 
and Tampa; 46 by 700 feet from the Gulf of Mexico 
to Mullet Key; 44 by 600 feet in Mullet Key Cut 
Channel; 44 by 500 feet in Tampa Bay from Mullet 
Key Cut to Hillsborough Bay and Port Tampa 
Channels; 44 by 500 feet in Hillsborough Bay from 
junction with Tampa Bay and Port Tampa Channels 
to the junction with Port Sutton entrance channel, 
thence 42 by 400 feet to the junction with Seddon 
and Garrison Channels; 44 by 400 feet in Port Sutton 
entrance channel; 42 by 400 feet in Sparkman 
Channel; 40 by 300 feet in Ybor Channel; 42 by 400 
feet in Port Tampa Channel; 44 by 400-500 feet in 
East Bay entrance channel; 44 by 300 feet in East 
Bay approach channel; 30 by 300 feet in Seddon and 
Garrison Channels; 30 by 200 feet in Alafia River; 
9 by 100 feet in Hillsborough River to a point 2,000 
feet above Columbus River bridge; a breakwater; 
turning basins at Port Sutton, Ybor Channel, Port 
Tampa, East Bay, mouth of Hillsborough River, and 
in Alafia River; and maintenance of a channel 12 
by 200 feet in Hillsborough River, 44 by 200 feet in 
Port Sutton terminal channel, and 34 x 300 in East 
Bay Channel. (The 46-foot and 44-foot depth portions 
of the project include a 5-foot underkeel clearance. 
Special studies on the project concluded that a 4-foot 
underkeel is sufficient. Therefore, a 1-foot overdepth 
has been placed in an inactive status, resulting in 
active project depths of 45 and 43 feet, respectively.) 
Plane of reference is mean low water. The project 
is about 67 miles long, including 10 miles in 
Hillsborough River and 3.6 miles in Alafia River. 
Mean range of tide is 1.3 feet at the lower end of 
the bay, 1.6 feet at Port Tampa, and 1.8 feet at 
Tampa. Extreme range is about 3.8 (feet at the lower 
end of the bay and 4.8 feet at Tampa. Strong 
southwesterly winds raise the water level about 1.5 
feet. Strong northerly winds, which usually occur in 
the winter, lower the water level about 2 feet. 
Estimated cost of new work (Oct. 1988 price levels) 
of the 1970 modification to the project is $211,562,000 
Federal ($209,267,000 Corps and $2,295,000 U.S. 
Coast Guard) cost and $13,418,000 non-Federal cost 
($13,000,000 contributed funds and $418,000 other 
costs). (See Table 9-B for Authorizing Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. Local cooperation has been fully 
complied with for work completed to date. See 1978 
Annual Report for requirements for work authorized 
by the River and Harbor Act of 1970, HD 401/ 
91/2 and HD 150/91/1. Assurances of local cooperation 
for the 1970 authorization were approved by 
the Secretary of the Army on January 10, 1973. The 
LCA for branch channels was signed 20 June 1986. 
An amendment to the LCA reflecting cost sharing 
requirements of WRDA of 1986 for section 6 was 
signed 31 Aug. 1987. Non-Federal contribution for 
new work was $1,083,162. A 25% contribution is 
required and an additional 10% reimbursement over 
30 years from locals. 
Terminal facilities. There are 102 commercial 
waterfront facilities serving Tampa Harbor. The 
General Cargo Facilities consist of 7,226 feet of 
usable berthing space and 15 transit sheds with a 
total of 585,200 square feet of shed storage space. 
The Oil Handling Facilities include 16,440 feet of 
usable berthing space and 316 storage tanks for a 
total capacity of 11,610,350 barrels. Dry storage is 
available at 1,904,750 square feet, cold storage at 
14,309,000 cubic feet, and open storage at 59.4 acres. 
There are 2 wharves available for coal storage at 
750,000 tons total storage and grain elevators with 
a 3,400,000 bushel total capacity. One elevator on 
Ybor Channel is a 1,000,000 bushel capacity. 
Hoisting Facilities include 13 cranes, fixed and 
mobile, with capacities from 45 to 150 tons and other 
crawler and mobile cranes available locally. Marine 
repair yards include 9 waterfront repair facilities 
and numerous other offwater companies engaged in 
various phases of marine repair. There are 4 floating 
and 4 graving docks available at the port with 
capacities ranging from 548 to 5,400 long tons. 
Floating equipment includes 24 tugs with up to 3,350 
horsepower and 4 companies with tank barges of 
9-18

JACKSONVILLE, FLA. DISTRICT 
capacities up to 14,000 barrels. The Seaboard System 
Railroad serves the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series -17 revised 1979). 
Operations and results during fiscal year. New 
work: Continuing dredging contract costs were 
$1,587,118 (federal) and $320,372 (non-Federal). 
Engineering and design and supervision and 
administration costs were $23,903 and $265,979, 
respectively. 
Maintenance: District Radio Communication 
Network cost was $9,500. Condition and operation 
studies cost was $71,339. Real estate management 
cost was $179. Maintenance dredging cost was 
$3,177,585. Engineering and design and supervision 
and administrative costs were $51,849 and $128,480 
respectively. 
Condition at end of fiscal year. Work authorized 
by the River and Harbor Act of 1970 (HD 401/91/ 
2 is 65 percent complete). 
Total Federal costs under the existing project 
through September 30, 1989 were: Main project: 
$197,158,668 for new work and $23,071,663 for 
maintenance, a total of $220,230,331 regular funds. 
In addition, $853,050 was expended for new work 
from public funds, $1,463,000 from emergency relief 
funds, and $1,029, 180 from contributed funds. On 
Hillsborough River $270,466 was expended for new 
work. 
36. NAVIGATION PROJECTS ON WHICH 
RECONNAISSANCE AND CONDITION 
SURVEYS ONLY WERE CONDUCTED 
DURING PIERIOD. 
(See Table 9-H). 
37. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See Table 9-I.) 
38. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation Activities Pursuant to Section 107, 
Public Law 86-645 (Preauthorization) 
Fiscal year costs for Aquadilla Harbor, P.R., 
$27,347; Benner Bay-Mangrove Lagoon, V.I., $1,550; 
Blount Island, FL, $7,609; Cedar Island-Keaton 
Beach Channel, FL, $799,064; Madiera Beach 
Channels, FL, $0; Miami River Park, FL, $1,245; 
North Lake Channel, Hollywood, FL, $0; Rockhouse 
Creek, FL, $0. 
Snagging and clearing for navigation (Sec. 3 of 1945 
River and Harbor Act, Public Law 14, 79th Congress.) 
No costs incurred. 
Beach Erosion Control 
39. BREVARD COUNTY, FLA. 
Location. The project is on the east coast of Florida 
at approximately the midpoint of the peninsula. (See 
NOAA Nautical Chart Nos. 11484 and 11476). 
Existing project. The authorization provides for a 
protective and recreational beach with a berm 50 
feet wide at elevation 10 feet above mean low water 
and a natural seaward slope as would be shaped by 
wave action, along 14,600 feet of beach at the city 
of Cape Canaveral and 10,600 feet of beach at 
Indialantic and Melbourne beach, and for periodic 
nourishment of the restored beach at Indialantic and 
Melbourne beach limited initially to a period of 10 
years. Nourishment of the restored beach at the city 
of Cape Canaveral would be provided by the 
authorized sand-transfer plant for construction at 
Canaveral Harbor. The project also provides for 
improvement of the Federally owned shores for 
beach erosion control or hurricane protection to be 
accomplished by the Federal agencies involved, 
subject to their own determination of economic 
justitification. The areas involved include 4.9 miles 
of shore at Kennedy Space Center, 4.0 miles at Cape 
Kennedy Air Force Station, and 2.3 miles at Patrick 
Air Force Base. 
Mean tidal range in the area is 3.5 feet. Estimated 
cost of the project (Oct. 1988 price levels) is 
$8,700,000 Federal costs and $8,803,000 non-Federal 
cost ($8,700,000 cash contribution and $103,000 for 
lands). (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
50 percent of all first costs of the work and 50 percent 
of the nourishment cost at Indialantic and Melbourne 
Beach for the first 10 years of the project life; provide 
lands and rights-of-way; provide, after the first 10 
years of project life, periodic nourishment of the 
restored beach at Indialantic and Melbourne beach 
during project life; maintain continued public 
ownership of the shore upon which the amount of 
Federal participation is based; control water 
pollution; and hold the uNited States free from 
damages. Assurances of local cooperation were 
approved by the Secretary of the Army on July 9, 
1973. Non-Federal contribution for new work was 
$2,262,000. 
Operations and results during fiscal year. New 
work: Engineering and design cost $16,410. 
9-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Condition at end of fiscal year. Initial beach fill 
has been provided at Indialantic and Melbourne 
beaches. 
40. BROWARD COUNTY, FLA. BEACH 
EROSION CONTROL AND HILLSBORO 
INLET, FLA., NAVIGATION PROJECT 
Location. Broward County is on lower east coast 
of Florida, 300 miles south of Jacksonville and about 
30 miles north of Miami. Hillsboro Inlet is northern 
part of Broward County. (See NOAA Nautical Chart 
No. 11466.) 
Existing project. The authorization provides for 
Federal participation toward cost of a shore 
restoration and protection project and a project to 
and maintain a channel adequate for small craft 
navigation. Plan provides for restoration of a 
protection and recreational beach at four locations 
generally 100 feet wide with berm elevation of 10 
feet above mean low water, a navigation channel 8 
by 100 feet from the Intracoastal Waterway to a point 
1,500 feet oceanward in Hillsboro Inlet, thence 10 
by 150 feet in the ocean; jetties on north and south 
sides of ocean entrance; a permanently based floating 
dredge; and on a deferred basis, a trestle-mounted 
sand-transfer plant, if needed. Navigation portion of 
the project is in an inactive status. Mean range of 
tide in areas is 2.5 feet. Plane of reference is mean 
low water. Cost estimate for new work (Oct. 1987 
price levels) is $25,700,000 Federal and $21,900,000 
non-Federal contribution. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must contribute 
90.5 percent of the first cost of beach restoration in 
the reach between north county line and Hillsboro 
Inlet, 90 percent of first cost allocated to beach 
restoration, and 50 percent of first cost allocated to 
navigation for reach between Hillsboro Inlet and 
Port Everglades and 72.4 percent of beach restoration 
in reach between Port Everglades and south 
county line; provide all lands and rights-of-way; 
obtain approval of Chief of Engineers of plans and 
specifications if local interest construct beach erosion 
features; and furnish assurances that they will hold 
the United States free from damages, provide and 
maintain adequate public landing or wharf at 
Hillsboro Inlet, establish a public body to cooperate 
financially and to provide and operate local facilities 
for navigation, control water pollution, maintain 
ownership of publicly owned shores, and maintain 
all project works except the jetties (maintenance of 
the channel to revert to the United States if sandtransfer 
plant is constructed). Assurances of local 
cooperation were accepted November 22, 1968. Non- 
Federal contribution for new work was $1,758,841. 
Operations and results during fiscal year. New 
work: Engineering and design costs were $12,777. 
Condition at end of fiscal year. Project was 
constructed by local interests and is complete. 
41. DUVAL COUNTY, FLA. 
Location. On upper east coast of Florida, within 
20 miles of Florida-Georgia line. Ocean shoreline is 
about 16 miles long. (See NOAA Nautical Chart No. 
11488). 
Existing project. Provides for Federal participation 
toward cost of construction with artificial fill, 
a beach 60 feet wide at elevation 11 feet above mean 
low water with a natural slope seaward, and for 
periodic nourishment for 10 years. Federal participation 
to be 100 percent of the first cost of 
construction applicable to the Federal shore and 50 
percent applicable to the other publicly owned shore 
and 55.5 percent of periodic nourishment cost for 
first 10 years of project life. Mean tidal range at south 
jetty in St. Johns River is 4.9 feet. 
Estimated cost of new work (Oct. 1988 price levels) 
$16,300,000 Federal and $13,884,000 non-Federal 
($11,500,000 contributed funds and $2,334,000 for 
other costs). 
Project was authorized by River and Harbor Act 
of 1965 (HD 273/89/1). 
Local cooperation. Local interests must contribute 
50 percent of first cost of constructing non-Federal 
publicly owned shores; contribute 44.5 percent of 
periodic nourishment costs for first 10 years of 
project life; provide all lands, rights-of-way, and 
relocations; hold the United States free from 
damages; control water pollution; and furnish 
assurances that they will maintain continued public 
ownership of the shore upon which the amount of 
Federal participation is based during economic life 
of project. Assurances of local cooperation were 
accepted on November 29, 1973. Non-Federal 
contribution for new work was $10,667,650. 
Operations and results during fiscal year. New 
work: A contract for beach nourishment continued 
at a cost of $1,609,268. Engineering and design and 
supervision and administration costs were $416,334 
and $1,019, respectively. 
Condition at end of fiscal year. Initial beach fill 
and four year advance nourishment has been 
completed. 
42. INDIAN RIVER COUNTY, FLA. 
Location: Indian River County is on the east coast 
of Florida, midway between Jacksonville and 
Miami. The authorized project comprises 2.65 miles 
9-20

JACKSONVILLE, FLA. DISTRICT 
of beach along the ocean shore of Vero Beach and 
1.7 miles along the Sebasian Inlet State Park. (See 
NOAA Nautical Chart Nos. 11474 and 11476). 
Existing project. The authorized project provides 
nourishment for 8,870 feet (1.68 miles) of the State 
Park, south of Sebastian Inlet. The initial beach fill 
would consist of 202,000 cubic yards of nourishment 
material. An estimated 202,000 cubic yards of 
periodic nourishment at 5-year intervals would be 
required. The Federal share of the first cost was 
estimated to be 65% of this segment. 
The plan also provided for nourishment of 9,180 
feet (1.74 miles) of Vero Beach. The initial beach fill 
consisted of 572,000 cubic yards of material, 
including advance nourishment. The restored beach 
would have a 20-foot-wide level berm at an elevation 
of 15 feet above mean low water. The beach fill as 
designed would provide protection against a 10-year 
return interval storm. An estimated 120,000 cubic 
yards of period nourishment would be required at 
5-year intervals. In additional to the beach fill a 
'Sabecon" reef breakwater was recommended. The 
structure would be placed 500 feet offshore of the 
new beach and would be 400 feet in length, with a 
zero mean low water crest elevation. The Federal 
share of the first cost was estimated to be 43.7 percent 
for this segment. 
The project was authorized on November 17, 1986 
(Public Law 99-662 by the 1986 Water Resource 
Development Act.) 
Estimated cost of new work (Oct. 1988 price levels) 
$26,300,000 Federal and $28,000,000 non-Federal 
($27,900,000 contributed funds and $100,000 for 
other costs). 
Local cooperation. The authorization of a beach 
erosion control project for Indian River County, 
Florida was made with the provision that the State 
and local interests will, in addition to the general 
requirements, agree to comply with the following 
requriements: provide all necessary lands, easements 
and rights-of-way; including borrow areas 
and disposal areas for excavated material, and 
relocations; hold and save the United States free 
from claims for damages; assure continued conditions 
of public ownership and public use of the shore; 
assure maintenance and repair during the economic 
life of the project; provide and maintain inecessary 
access roads, parking areas and other public use 
facilities; provide a cash contribution for periodic 
nourishments for the life of the project; provide an 
additional cash contribution for the Sebasian Inlet 
State Park Beach. The project, as authorized, 
provides that the work may be accomplished in 
separate units or features and that the written 
agreement with non-Federal interests be obtained. 
The Indian River County Board of Commissioners, 
by letter dated December 21, 1984 and January 15, 
1987, affirmed their support for the project and their 
willingness and ability to share in project costs. 
Operations and results during fiscal year. New 
work: Engineering and design costs $207,547. 
Condition at end of fiscal year. total cost under 
existing project through September 30, 1989 was 
$46,539 Federal funds. 
43. PALM BEACH COUNTY, FLA. 
Location. Palm Beach County is on east coast of 
Florida about 300 miles south of Jacksonville and 
70 miles north of Miami. Northerly reach of the 
project is separated from the southerly reach by 
Palm Beach Island. Project consists of about 12.2 
miles of ocean coastline. (See NOAA Nautical Chart 
No. 11466). 
Existing project. Provides for Federal participation 
toward the cost of local shore project for 
restoration of beaches to a general width of 100 feet 
with a berm elevation of 10 feet above mean low 
water, and periodic nourishment for 10 years from 
the year of intial nourishment, as follows: 62.1 
percent of the cost for the Martin County line- 
Jupiter Inlet segment; 55.8 percent of cost for Jupiter 
Inlet-Lake Worth Inlet segment; and 50 percent for 
south Lake Worth Inlet-Delray Beach; and 53 
percent of cost for Delray Beach-Boca Raton inlet 
segment. Mean range of tide is 2.8 feet in the Atlantic 
ocean at Palm Beach and 2.3 feet at Boca Raton Inlet. 
Estimated cost (Oct. 1988 price levels) is $5,500,000 
Federal and $15,400,000 cash contribution. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must obtain 
approval by Chief of Engineers of plans and 
specifications prior to commencement of work and 
furnish assurances that they will maintain public 
ownership of publicly owned shores, maintain 
protective measures and provide periodic nourishment 
of protective beaches, and control water 
pollution. 
Operations and results during fiscal year. New 
work: Continuing beach replenishment costs were 
$36,769. Engineering and design costs were $75,450. 
Condition at end of fiscal year. Local interests 
provided initial beach fill at Delray Beach which was 
completed in August 1973. A periodic nourishment 
contract at Delray Beach was awarded in FY 1978 
by local interests and the contract has been 
completed. 
44. PINELLAS COUNTY, FLA. 
Location. Pinellas County is on the Gulf coast of 
Florida, about midway of the peninsula. It extends 
9-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
northerly about 39 miles from the main entrance to 
Tampa Bay to the vicinity of the mouth of Anclote 
river. (See NOAA Nautical Chart No. 11411.) 
Previous project. For details see page 429 of Annual 
Report for 1965. 
Existing project. The authorized project provides 
for Federal participation in preserving and 
protecting the shores of Pinellas County, Florida, 
by: restoration of 5,000 feet of beach at Clearwater 
Beach Island; restoration of 49,000 feet of beach at 
Sand Key; restoration of 9,200 feet of beach at 
Treasure Island; construction of 600 feet of 
revetment at Long Key; and advance nourishment 
of Long Key and periodic nourishment of each 
island. Estimated cost (Oct. 1988 price levels) is 
$22,000,000 Federal funds and $23,662,000 non- 
Federal funds ($23,600,000 contributed funds and 
$62,000 other costs). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must: (a) 
contribute in cash the required percentages of the 
first costs of work provided by the Corps of 
Engineers, the percentages varying with the type of 
beach ownership; 94.1 to 50 percent of the beach 
restoration at Clearwater Beach; 98.1 to 50 percent 
of the improvement at Sand Key; 94.3 to 50 percent 
of the improvement at Treasure Island; and 50 
percent of the first cost of the revetment at Long Key; 
(b) contribute in cash an amount computed in 
accordance with the cost sharing provision contained 
in P.L. 826, 84th Congress as amended by P.L. 87- 
874, for beach nourishment cost for the first 10 years 
of the project life; (c) provide lands, easements, and 
rights-of-way; (d) assure maintenance and repair of 
the stone revetment of Long Key; (e) assure periodic 
nourishment of the restored beaches; (f) assure 
public ownership of beaches; (g) assure against water 
pollution; (h) hold the United States free from 
damages; and (i) provide beach for public use. 
Assurances of local cooperation were accepted 
March 22, 1967. 
Operations and results during fiscal year. New 
work: Contract for Redington shore breakwater and 
groin cost $454,413. Contract for Long Key 
breakwater and beach nourishment costs were 
$2,653,972. Engineering and design and supervision 
and administration costs for the fiscal year were 
$781,005 and $18,100, respectively. 
Condition at end of fiscal year. Construction of the 
project commenced in 1969 and is 28 percent 
completed. Total costs under existing project 
through September 30, 1989 were $6,944,777 
Federal funds and $4,321,634 contributed funds for 
new work and $5,625 for maintenance. 
45. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 9-J.) 
46. BEACH EROSION CONTROL 
ACTIVITIES UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 
103, Public Law 87-874 (preauthorization) 
Reports incurring costs during the fiscal year were 
Boca de Congrejos, P.R., $2,923; Dunedin Shores, Florida, 
$8,906; Guanica Public Beach, P.R., $232; Gulfport, 
Florida, $7; Key Biscayne, Fla., $41,518; Puerto 
Nuevo Beach, P.R., $8,781; E.G. Simmons Hillsborough 
County, FL, $24; Ft. Clinch State Park, FL, $0; 
Ft. Louise Augusta, VI, $53; Ft. Pierce Beach, FL, 
$3,344 and Palm Beach County, FL, (Reimb) $112,220. 
Beach erosion control activities pursuant to section 
III, Public Law 90-433 Mitigation of Shore Damages 
Attributable to Navigation Projects. 
No costs were incurred under the above authorization. 
Beach erosion control activities pursuant to Shoreline 
Erosion Control Act of 1974, Public Law 93-251. 
No costs were incurred under the above authorization. 
Flood Control 
47. CENTRAL AND SOUTHERN FLORIDA 
Location. The project is located generally within the 
southeastern eighteen counties of Florida covering an 
area of about 15,200 square miles. It is comprised of 
the Upper St. Johns River basin in the northeastern 
section of project, Kissimmee River basin in central 
section above the Lake Okeechobee-Everglades area 
in the central and southwestern section, and the east 
coast Everglades area in southeastern section. 
Previous projects. Completed works for control of 
Lake Okeechobee were included in and constructed 
under the navigation project for Okeechobee 
Waterway, Fla. (formerly Caloosahatchee River and 
Lake Okeechobee drainage area, Fla.) and under 
provisions of River and Harbor Acts of July 3, 1930, 
and August 30, 1935. For further information, see 
Annual Reports, 1948 and 1949. 
Existing project. The authorized project is for flood 
relief and water conservation and provides principally 
for: an east coast protective levee extending 
from the Homestead area north to the eastern shore 
of Lake Okeechobee near the St. Lucie Canal; three 
conservation areas for water impoundment in the 
9-22

JACKSONVILLE, FLA. DISTRICT 
Everglades area west of the east coast protective 
levee with control structures to effect transfer of 
water as necessary; local protective works along the 
lower east coast; encirclement of the Lake Okeechobee 
agricultural area by levees and canals; enlargement 
of portions of Miami, North New River, 
Hillsboro, and West Palm Beach Canals; enlargement 
of the existing Lake Okeechobee levees and 
construction of new levees on the northeast and 
northwest shore of the lake; increased outlet capacity 
for improved control of Lake Okeechobee; floodway 
channels in the Kissimmee River basin, with suitable 
control structures to prevent over-drainage; an 
interrelated system of canals, levees, pumping 
stations, and structures in southwest Dade County 
to control water levels; and facilities for regulating 
floods in the Upper St. Johns River basin; a system 
of canals and control structures for gravity drainage 
of Martin County and distribution of available water 
supplies to portions of Martin and St. Lucie Counties; 
and works to improve the supply, distribution, and 
conservation of water resources in central and 
southern Florida, including the Lake Okeechobee 
agricultural area, Everglades National Park, and 
other related areas. The project will provide water 
control and protection from recurrence of the 
devastating floodwaters from the Everglades and 
local sources, for the highly developed urban area 
along the lower east coast of Florida and for the 
productive agricultural areas around Lake Okeechobee 
(including towns around lake), in the Upper St. 
Johns and Kissimmee River basins, and in South 
Dade County. Project also provides for navigation 
improvements suitable for recreational craft, 
consisting of locks and channel dredging in the upper 
Kissimmee and St. Johns basins. 
The project includes a total of 990 miles of levees, 
978 miles of canals, 30 pumping plants, 212 floodway 
control and diversion structures, 56 railroad bridge 
relocations, and 2 highway bridge relocations. 
The project also provides that upon completion, 
local interests assume operation and maintenance of 
all completed works except levees, channels, locks, 
and control works for regulation of Lake Okeechobee 
and the main control structures of conservation 
areas, which will be operated and maintained by the 
United States. 
The principal features of the hurricane gates, 
constructed under previous projects for Okeechobee 
Waterway and maintained under existing project 
since July 1, 1950, are set forth in Table 9-K. See 
also Table 9-L for principal features of locks and 
dams. 
Estimated cost for new work (Oct. 1988 price 
levels) is $872,000,000 Federal funds ($869,600,000 
Corps and $2,400,000 U.S. Coast Guard) and 
$216,255,000 contributed funds, exclusive of river 
and harbor funds expended on previous projects. 
Estimated cost to local interests of lands, rightsof-
way, and relocations is $308,748,000. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. (See Table 9-M for local cash 
contribution.) Local interests must also: provide 
lands, rights-of-way, and spoil disposal areas; hold 
the United States free from damages; bear the cost 
of maintenance and operation of all works except 
those having to do with regulation of Lake Okeechobee 
and the main control structures of conservation 
areas; construct and maintain lateral drainage 
facilities; prohibit encroachment on flood-carrying 
capacity of the improved channels; and assume cost 
of all new highway bridges, relocations of existing 
bridges and alterations to utilities incident to 
construction of the project. In addition, for small boat 
navigation channels, local interests must provide, 
maintain, and operate adequate public landings, 
sanitary and access facilities, and establish regulations 
prohibiting discharge of pollutants into the 
waters of the locks and channels by users thereof. 
Assurances of local cooperation have been accepted 
by the District Engineer for all items of work 
authorized to date except those for the Small Boat 
navigation feature added in 1970 under Section 201 
of the Flood Control Act of 1965. 
Operations and results during fiscal year. (See 
Table 9-N for work accomplished.) 
Operations and care. a. Features completed under 
previous navigation project for Okeechobee Waterway 
and being maintained under this project are: 
a levee about 70 miles long following in general the 
south shore of Lake Okeechobee and a north shore 
levee 15.8 miles long; spillways at Ortona and St. 
Lucie locks; 5 hurricane gates; 20 gated drainage 
culverts through the levee; and 16 spillways along 
St. Lucie Canal. 
b. Features completed under existing project that 
are to be maintained with operation and maintenance 
funds are: (1) Levees 47, 48, 49 and 50- total 
length 63 miles and enlargement of existing levees 
L-D1, L-D2, L-D3, L-D4, and L-D9, (2) spillway 
structures S-10, S-11, S-12, S-18C, S-77, and S-78 (3) 
C-43, Sec. 4 (Caloosahatchee River), and (4) W.P. 
Franklin Lock and Dam. 
In addition to the actual facilities listed above it 
is necessary under operation and maintenance to 
continue meteorological studies, water level records, 
stream gaging stations, etc., for proper regulation 
of the level of Lake Okeechobee and storage of water 
in Conservation Areas 1, 2 and 3. 
9-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Corps of Engineers - The Corps of Engineers 
operates and maintains the major outlets to Lake 
Okeechobee and Water Conservation Area Nos. 1, 
2A and 3A in central and southern Florida. 
South Florida Water Management District - 
SFWMD is responsible for operation and maintenance 
of the remainder of the project facilities, 
including major pumping stations, spillways, locks 
(except on Okeechobee Waterway), levees and 
culverts. 
Condition at end offiscal year. The scheduled work 
of project is 81 percent complete. Planning for the 
entire project began in November 1948 and has been 
continued. For construction completed prior to 
Fiscal Year 1980 see Annual Reports for 1960-1979. 
Construction completed under existing project 
during the fiscal year is set forth in Table 9-0. All 
Federally maintained features of the project were 
generally in good condition at the end of the fiscal 
year. (For status of work under contract at end of 
fiscal year see Table 9P.) 
Total Federal costs under the existing project 
through September 30, 1989 were $313,397,919 for 
new work, $59,031,926 for maintenance, a total of 
$372,429,845. In addition, $53,510,956 has been 
expended from contributed funds for new work. 
48. DADE COUNTY, FLA. 
Location. Dade County is on the southeast coast 
of Florida. Project area consists of that part of the 
Atlantic shoreline of the county from Government 
Cut north to Bakers Haulover Inlet and at Haulover 
Beach Park. (See NOAA Nautical Chart No. 11466.) 
Existing project. Project provides for a protective 
and recreational beach having a dune at elevation 
11.5 feet and a level berm 50 feet wide at elevation 
9 feet, mean low water, for beach erosion control and 
hurricane protection between Government Cut and 
Bakers Haulover Inlet; a protective and recreational 
beach with a berm elevation of 9 feet for beach 
erosion control at Haulover Beach Park; and Federal 
participation in the initial construction and in 
periodic nourishment of both the above reaches for 
the first 10 years of project life. Plane of reference 
is mean low water. Mean range of tide in the area 
is 2.5 feet. 
Estimated cost of the project (Oct. 1988 price 
levels) is $49,700,000 Federal cost and $42,839,000 
non-Federal cost ($41,000,000 cash contribution and 
$1,839,000 other costs.). 
Project was authorized by Flood Control Act of 
1968 (HD 335/90/2). 
Local cooperation. Local interests must (a) contribute 
for the first cost of the work: between 
Government Cut and Bakers Haulover Inlet amounts 
ranging from 60.2 percent of the cost of the fill within 
the project limit with existing shorefront ownership, 
and 100 percent of the cost of fill required landward 
of the project limit; and for the work at Haulover 
Beach Park, contribute 21.3 percent of the entire 
first cost excluding costs for lands, easements, rightsof-
way, relocations, and preproject work, but 
including credit for preproject work; (b) contribute 
in cost for the first 10 years of project life, amounts 
ranging from 88.9 percent of the nourishment cost 
for the beach, with existing ownership, to 60.7 
percent with public ownership, and the entire 
maintenance cost for the dune, all between Government 
Cut and Bakers Haulover Inlet; (c) provide all 
lands and rights-of-way; (d) hold United States free 
from damages; (e) assure continued public ownership 
and use of the shore upon which the amount 
of Federal participation is based; (f) assure maintenance 
of the groin, and after the first 10 years of 
project life, periodic nourishment of the protective 
beach and maintenance of the dune during the 
economic life of the project; (g) assure that water 
pollution will not be permitted; (h) prevent removal 
or relocation by man of fill from the beach berm and 
dune; (i) prevent the erection of barriers to the littoral 
movement of material that would interfere with the 
nourishment of the beach; (j) maintain at the parks 
qualifying for 70 percent Federal participation a 
zone that excludes permanent human habitation; (k) 
at least annually inform interests affected that the 
project will not provide complete protection from a 
hurricane tide level equal to or higher in elevation 
than that of the hurricane of September 1926; and 
(1) establish in public ownership for public use the 
beaches within project limits as a requirement for 
Federal participation in the allocated beach erosion 
control costs of improvement of shores presently in 
private ownership. Assurances of local cooperation 
were accepted January 16, 1973. A supplemental 
agreement for Bal Harbour portion was approved 
30 June 1976. Non-Federal contribution for new 
work was $26,136,085. 
Operations and results during fiscal year. New 
work: Continuing beach replenishment cost was 
$28,318. Engineering and design and supervision 
and administration costs were $131,245 and $-52, 
respectively. 
49. DADE COUNTY, NORTH OF 
HAULOVER BEACH, FLA. 
Location. On the southeast coast of Florida. Project 
area consists of that part of the Atlantic shoreline 
9-24

JACKSONVILLE, FLA. DISTRICT 
extending 2.5 miles north of Haulover Beach Park. 
(See NOAA Nautical Chart No. 11466.) 
Existing project. The existing shore protection 
project for Dade County provides for Federal 
participation in the cost of construction of a beach 
fill for the purpose of erosion control and hurricane 
protection along 9.3 miles of shore between Government 
Cut and Bakers Haulover Inlet and for the 
construction of a beach fill for the purpose of erosion 
control along the 1.2 miles of shore fronting Haulover 
Beach Park and provides for protection and nourishment 
of 2.5 miles of beach shore north of Haulover 
Beach Park and for extension of the period of 
Federal participation in the nourishment of the 
existing project from 10 years to the life of the 
project. Cost estimate for new work (Oct. 1988 price 
levels) was $12,100,000 Federal and $10,900,000 non- 
Federal cash contribution. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Consistent with the cost-sharing 
and financing concepts agreed to be the administration 
and the Senate Majority Leadership, local 
interests will be required to provide lands, easements 
and rights-of-way and relocations, pay 50% of the 
separable and joint costs allocated to recreation, pay 
35% of the cost allocated to storm damage prevention, 
hold the United States free from damages, control 
water pollution and furnish assurances that they will 
maintain continued public ownership of the shore 
upon which the amount of Federal participation is 
based during economic life of project. Assurances of 
local cooperation have been requested from local 
sponsors. Non-Federal contribution for new work 
was $8,075,000. 
Operations and results during fiscal year. New 
work: Continuing beach replenishment costs were 
$4,394,957. Engineering and design and supervision 
and administration costs were $34,114 and $99,110, 
respectively. 
Condition at end of fiscal year. Continuation of 
planning and engineering. 
50. FOUR RIVER BASINS, FLA. 
Location. The Four River Basins area covers about 
6,000 square miles within 14 counties in central and 
southwest peninsular Florida. Project includes all or 
part of the four main stream basins - the Hillsborough, 
Oklawaha, Withlacoochee, and Peace Rivers 
- and all of three smaller coastal basins north of 
Tampa, Florida, drained by the Pithlachascotee and 
Anclote Rivers and Lake Tarpon. 
Existing project. The authorized project provided 
for improvements for control of floods and drainage, 
and for water conservation through construction of 
necessary canals, levees, reservoirs, and control 
structures. More specifically, the project provided 
for: Green Swamp Area - a conservation area and 
three storage reservoirs with necessary canals and 
control structures; Hillsborough River - four floodstorage 
reservoirs, with necessary channels, control 
structures, and levees; Oklawaha River - a levee on 
the north shore of Lake Apopka, improvement of 
part of the river channel and a west bank levee below 
Moss Bluff lock and dam, and replacement of the 
lock and dam; Withlacoochee River - one floodstorage 
reservoir with outlet canals and control 
structures; Peace River - Peace Creek canal and 
control structures and improvements to the existing 
water control and drainage features; Gulf Coastal 
Areas-Lake Tarpon; outlet canal and control 
structure; Anclote River: control structure and 
channel improvement; Pithlachascotee River: 
reservoir with outlet canals and control structures. 
(See Table 9-Q on Moss Bluff Lock.) 
Estimated cost for new work (Oct. 1988 price level) 
is $156,000,000 Federal funds and $132,400,000 non- 
Federal cost. ($32,900,000 contributed funds; 
$99,500,000 for lands and damages.) (See Table 9- 
B for Authorizing Legislation.) 
Local cooperation. Local interests must furnish all 
lands, and rights-of-way; provide all alterations or 
replacements of public and private utilities, roads, 
bridges (except railroad bridges), etc.; hold the 
United States free from damages; operate and 
maintain all project works after completion; construct 
and maintain such associated works as are 
necessary to realize benefits made available by the 
project works; and contribute in cash 17 percent of 
the first cost of construction and 50 percent of 
recreation costs. 
Operations and results during fiscal year. New 
work: Continuing contracts for recreation facilities 
cost was $803,608. Engineering and design and 
supervision and administration costs were $62,249 
and $213,743, respectively. 
Condition at end of fiscal year. Construction of the 
project commenced April 18, 1966 and the scheduled 
work is 98 percent complete. See Table 9-R for 
construction of major features of the project 
completed to date. 
51. PORTUGUES AND BUCANA RIVERS 
P.R. 
(This project authorized as Lago de Cerrillos, Lago 
de Portugues, and Channel Improvement at Ponce.) 
Location. Portugues and Bucana Rivers originate 
on the southern slopes of Cordillera Central divide 
of Puerto Rico and flow from this central ridge of 
9-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
the island to the Caribbean Sea. Their drainage areas 
are 22.6 and 31.4 square miles, respectively. Ponce, 
the second largest city in Puerto Rico, is located in 
the lower coastal area along Portugues River and 
is the only urban community in the two basins. 
Existing project. The authorized project provides 
for two multiple-purpose reservoirs for flood control, 
water supply, general recreation, and fish and 
wildlife enhancement - one on Portugues River and 
the other on Cerrillos River, a tributary to the 
Bucana River; enlargement of about 5.7 miles of the 
Bucana River, with an additional 0.2-mile tieback 
levee at the upstream terminus of the improvement; 
enlargement of 2.1 miles of the Portugues River, with 
an additional 0.5 mile of tieback levee at the 
upstream terminus of the improvement; and a 1.3 
mile diversion channel connecting Portugues River 
to lower Bucana River. Estimated cost of the project 
(Oct. 1988 price level) is $313,000,000 Federal cost 
and $91,500,000 non-Federal cost ($11,700,000 
contributed funds; $59,252,000 for lands and 
damages; $20,548,000 for relocations; and highway 
bridges and approaches). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must provide all 
lands, easements and rights-of-way; hold the United 
States free from damages; operate and maintain all 
project works after completion; repay construction 
cost allocated to water supply in accordance with 
Water Supply Act of 1958; pay one-half of the 
separable cost allocated to recreation and fish and 
wildlife enhancement; prohibit discharge of inadequately 
treated sewage and other pollutants into the 
reservoir; and prevent encroachment on downstream 
channels. Assurances of local cooperation 
have not been completed, except for Cerrillos 
Reservoir which was signed March 15, 1982. Non- 
Federal contribution for new work was $220,000. 
Operations and results during fiscal year. New 
work: Contract for Cerrillos Dam & Spillway 
continued at a cost of $11,095,213, hired labor costs 
were $16,109. Contract for the Upper Portugues for 
Bucana Debris Basin excavation and Portugues 
channel improvement and debris control basin has 
respective costs of $77,397 and $14,730. Contracts for 
Section 6D and Gabion Levee Project has respective 
costs of $21,992 and $746,456. Cost for Entrance 
Channels, Contract #2 was $1,136,259. Ponce 
Channel Recreation cost for Ceiba Park was 
$303,S78. Hired Labor costs for Channels and Canals 
was $5,442. Cultural resource investigations cost 
$167,000. Area office equipment cost $45,426. 
Buildings, grounds and utilities cost was $12,366. 
Engineering and design and supervision and 
administrations costs were $21,153,063 and 
$4,366,762 respectively. 
Condition at end of fiscal year. Construction of 
the project commenced in September 1975 and is 
60 percent complete. 
52. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Features transferred to the Central and Southern 
Florida Flood Control District and Southwest 
Florida Water Management District were inspected 
quarterly during the fiscal year at a total cost 
of $27,180. 
53. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 9-S.) 
54. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 685, 84th Congress, as amended 
(preauthorization). 
(See Table 9-T.) 
Emergency flood control activities - repair,f lood 
fighting, and rescue work (Public Law 99, 84th 
Congress and antecedent legislation). 
Federal costs for the fiscal year were $115,950 
for the Disaster Preparedness Program, and 
$137,311 for national emergency and mobilization 
readiness plans. 
Emergency streambank and shoreline protection 
activities pursuant to Section 14, Public Law 526, 
79th Congress as amended (preauthorization.) 
Federal costs for the fiscal year were $142,172 
for Barrio Barrero, Rincon, Puerto Rico; and 
$206,652 for Highway 187, El Terraplan, Puerto 
Rico. 
General Investigations 
55. SURVEYS 
Hired labor costs during the fiscal year (all 
Federal funds) were: navigation studies, $409,968, 
flood damage prevention studies $1,598,544, 
shoreline protection studies, $0; for a total of 
$2,008,512. 
Review of authorized projectsd cost was $32,164; 
Special investigations cost was $50,693; and 
coordination with other agencys and non-Federal 
interests costs were $150,643. 
9-26

JACKSONVILLE, FLA. DISTRICT 
56. COLLECTION AND STUDY OF BASIC 
DATA 
The requirement for preparation of regular flood 
plain information studies has been rescinded. FPI 
studies that deal with land use changes will 
continue to be prepared. FPMS Unit Jacksonville, 
Fla., $89,137. Technical services, $95,377, Black 
Creek, FL flood warning and evacuation study, 
$6,985, Puerto Rico hurricane evacuation study, 
$38,804; and Southeast Florida hurricane evacuation 
study, $47,956; and Gold Coast hurricane 
evacuation study, $41. 
9-27

COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
Aquatic Plant 
Control (R&H 
Act of 1965) 
(Federal Funds) 
Arecibo Harbor, 
P.R. 
(Federal Funds) 
Atlantic 
Intracoastal 
Waterway 
between 
Norfolk, Va. and 
St. John's River, 
Fla. 
(Federal Funds) 
Bakers Haulover 
Inlet, Fla. 
(Federal Funds) 
Canaveral 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
Channel from 
Naples to Big 
Marco Pass, Fla. 
(Federal Funds) 
(Contrib. Funds) 
Charlotte 
Harbor, Fla. 
(Federal Funds) 
Cross-Florida 
Barge Canal 
(Federal Funds) 
EHaaurb Gora,l lFiela. 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
2,300,000 2,516,000 2,405,0000 2,450,000 
2,190,290 2,666,855 2,333,423 2,510,571 
341,000 
365,282 
8,429 
8,630 
0 18,387 
467 18,387 
5,032 
5,032 
7,525 
10,290 
148,000 
2,886,993 
3,853,000 
4,014,577 
33,523 
623,853 
642,523 
1116,918 
199,761 
25,000 
82,642 
1,563,000 
1,603,791 
172,000 
202,624 
2,979,000 
2,894,020 
1,034,500 
1,032,134 
43,100 
-22,317 
-20,216 
50,000 
42,756 
150,000 
10,931 
1,720,500 
1,745,887 
-2,616 
-410,000 
302,675 
3,537,000 
2,728,192 
12,441 
103,000 
946,841 
4,850,000 
109,295 
2,404,000 
1,837,662 
11,902 
4,966,850 
4,945,994 
171 
183,290 
183,595 
3,107,979 
3,096,182 
29,165,670 
29,124,998 
1,128,0751 
1,128,0751 
4,291.731 
4,291.731 
361,2252 
361,2252 
5,300,742 
5,300,742 
243,2353 
243,2353 
185,688 
185,688 
14,138,9104 
14,137,8614 
46,179,671 
45,312,869 
1,106,000 
1,092,235 
305,290 
305,290 
1,606,530 
1,606,531 
159,975 
159,975 
533,169b 
533,1696 
11,722,526 
12,661,181 
68,197,473 
63,306,681 
26,676,942 
26,061,664 
9,627 
9,627 
710,900 
705,668 
9-28 
TABLE 9-A

COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
10. Fernandina 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
11. Fort Myers Beach 
Channel, Fla. 
(Federal Funds) 
12. Fort Pierce 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
13. Gulf Intracoastal 
Waterway, 
Caloosahatchee 
River to Anclote 
River Fla. 
(Federal Funds) 
14. Intracoastal 
Waterway, 
Jacksonville to 
Miami, Fla. 
(Federal Funds) 
(Contrib. Funds) 
15. Jacksonville 
Harbor, Fla. 
(Federal Funds) 
(Contrib. Funds) 
16. Jacksonville 
Harbor (Mill Cove), 
Fla. 
(Federal Funds) 
17. Johns Pass, Fla. 
(Federal Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
17,575 
577,562 
594,389 
367,561 
377,389 
136,675 
153,614 
88,200 
98,667 
391,036 
486,735 
61,000 
771,854 
781,020 
25,000 
50,000 
62,193 
68,000 
11,778 
150,000 1,365,000 
143,378 308,847 
4,000 
87,500 
81,006 
403,000 
401,755 
5,636 
320,000 
175,651 
106,000 1,929,000 
99,824 146,521 
3,095,500 
3,093,169 
1,736,000 
909,058 
61,000 
4,000,300 
3,952,929 
3,695,000 
857,548 
25,000 
961,000 2,581,000 
148,856 3,277,997 
268,015 
269,265 
9-29 
89,000 
56,997 
766,950 
766,931 
59,000 
17,858 
10,145 
11,488 
506,326 
506,288 
61,209 
63,268 
904,692 
983,309 
399,700 
415,056 
4,354,8167 
4,243,4747 
25,015,969 
23,951,500 
875,000 
828,912 
158,1408 
158,1408 
1,184,091 
1,184,315 
356,056 
356,056 
5,019,361 
4,870,791 
18,574 
18,574 
8,112,5579 
8,112,5579 
7,975,94710 
6,187,16910 
19,251,59811 
19,251,59811 
32,161,65912 
31,392,97512 
61,000 
61,000 
47,596,27813 
47,596,278s13 
63,597,28914 
60,725,73114 
102,813 
102,813 
927,654's15 
927,65415 
25,000 
25,000 
3,992,000 
3,504,906 
82,0981e 
82,0981e 
1,440,075 
1,440,075 
450,000 
78,053 
32,245 
32,245 
TABLE 9-A (Continued)

TABLE 9-A (Continued) 
See 
Section 
in Text Project 
18. Longboat 
Pass, Fla. 
(Federal Funds) 
(Contrib. Funds) 
19. Manatee 
Harbor, Fla. 
(Federal Funds) 
20. Mayaguez 
Harbor, P.R. 
(Federal Funds) 
21. Melbourne 
Harbor, Fla. 
(Federal Funds) 
22. Miami Harbor, 
Fla. 
(Federal Funds) 
(Contrib. Funds) 
23. New Pass 
Sarasota, Fla. 
(Federal Funds) 
24. Okeechobee 
Waterway, Fla. 
(Federal Funds) 
(Contrib. Funds) 
25. Oklawaha 
River, Fla. 
(Federal Funds) 
26. Palm Beach 
Harbor, Fla. 
(Federal Funds) 
.... .. 
COST AND FINANCIAL STATEMENT 
Funding FY 86 FY 87 FY 88 
New Work: 
Approp. - - - 
Cost - - - 
Maint: 
Approp. 232,525 - - 
Cost 245,401 - - 
New Work: 
Approp. - - - 
Cost - - - 
New Work: 
Approp. - - 478,00( 
Cost - - 224,28 
New Work: 
Approp. - - - 
Cost - - - 
Maint: 
Approp. 11,154 - - 
Cost 11,632 - 19,47 
New Work: 
Approp. - - - 
Cost - - - 
Maint: 
Approp. 251,338 - - 
Cost 252,188 - - 
New Work: 
Approp. 5,190,000 1,650,000 - 
Cost 3,871,286 1,820,111 - 
Maint: 
Approp. 129,211 - 127,00 
Cost 183,359 1,097 74,31 
New Work: 
Approp. - 38,000 - 
Cost - 11,885 - 
New Work: 
Approp. - - - 
Cost - - - 
Maint: 
Approp. 75,893 - - 
Cost 77,449 - 52,28 
New AWpporrokp:. - 5,000 
Cost - 4,940 
Maint: 
Approp. 1,683,000 1,735,200 2,587,00 
Cost 1,779,336 1,795,491 1,749,66 
New Work: 
Approp. - - - 
Cost - - - 
New Work: 
Approp. ... 
Cost .... 
Maint: 
Approp. 45,572 55,000 58,00 
Cost 48,143 58,759 62,28 
New Work: 
Approp. - 20,000 - 
Cost - 7,183 - 
Maint: 
Approp. 685,212 793,000 979,00 
Cost 711,384 780,280 181,13
08 
1
00 
9
02 
04 
03 
9-30 
-. 
Total Cost to 
FY 89 Sept. 30, 1989 
- 1,020,233 
- 1,020,233 
49,954 1,450,441 
49,954 1,450,441 
- 172,324 
- 172,324 
200,000 678,000 
218,089 442,377 
- 328,187 
- 168,903 
716 1,033,390 
716 1,052,861 
- 17,696 
- 17,696 
- 634,864 
- 634,863 
- 32,636,06617 
- 30,739,66717 
203,755 2,842,580 
203,754 2,789,478 
- 2,300,71018 
- 2,274,59518 
- 45,811's19 
- 45,811's19 
65,422 3,173,726 
65,414 3,226,006 
- 21,405,5902 
- 21,405,5302 
2,931,330 38,798,49621 
2,952,854 37,958,89321 
- 503,700 
- 503,700 
- 315,264 - 
- 315,264 - 
72,595 2,233,9152 
72,535 2,238,1302 
- 6,924,02124 
- 6,911,2042 
934,651 11,916,7692 
930,993 11,100,1202 -.

COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
27. Ponce de Leon 
Inlet, Fla. 
(Federal Funds) 
(Contrib. Funds) 
28. Ponce Harbor, 
P.R. 
(Federal Funds) 
(Contrib. Funds) 
29. Port Everglades 
Harbor, Fla. 
(Federal Funds) 
30. Removal of 
Aquatic Growth 
(Federal Funds) 
31. St. Augustine 
Harbor, Fla. 
(Federal Funds) 
32, St. Johns 
River, Fla. 
Jacksonville 
to Lake Harney 
(Federal Funds) 
33. St. Lucie 
Inlet, Fla. 
(Federal Funds) 
(Contrib. Funds) 
34. San Juan 
Harbor, P.R. 
(Federal Funds) 
35. Tampa Harbor, 
Fla. (Main 
Project) 
(Federal Funds) 
(Contrib. Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
106,192 
108,285 
25,795 
23,506 
24,117 
53,000 
283,422 
36,810 
36,790 
132,500 
140,306 
136,000 
114,769 
2,802,500 
2,801,297 
200,000 775,000 1,325,000 
77,861 45,078 1,954,609 
10,200,000 
10,098,627 
574,329 
42,012 
62,523 
85,000 
24,077 
199,739 
679,406 
-45,000 
7,266 
20,698 
20,668 
1,953,277 
1,953,277 
18,305,586 
18,273,838 
2,415,600 
2,415,600 
1,379,000 
612,663 
2,782,9072 
2,530,2462 
1,612,870 
1,327,870 
774,068 
721,418 
54,463,7737 
54,415,3707 
1,718,178 
1,643,155 
2,474,000 2,738,000 2,736,000 2,815,387 36,300,757 
2,477,801 2,744,421 2,511,647 2,820,856 36,054,434 
367,049 
387,772 
16,039, 
20,077 
30,986 
60,091 
57,293 
74,172 
2,339,241 
2,376,226 
1,354,000 
1,669,404 
255,000 
262,361 
11,543 
3,167 
92,000 
93,740 
115,050 
114,847 
200,000 
158,499 
430,000 
431,706 
44,450 
1,811,737 
364,279 
363,799 
110,000 2,260,504 
81,330 2,263,294 
1,650,000 
1,661,897 
2,436,000 
3,438,932 
8,750 
9,531 
17,967 
884,410 
857,218 
1,476,4342 
1,476,4342 
4,714,107 
4,714,107 
1,171,2432 
1,171,2432 
1,300,2993o 
1,300,2993 
7,863,60231 
7,862,48531 
5,172,285 
5,161,473 
3,086,026 
3,086,026 
13,744,9683 
13,744,9683 
16,696,6353 
16,670,7553 
197,708,6433 
197,625,4363 
22,972,9323 
23,945,9883 
1,083,162 
1,038,711 
9-31 
TABLE 9-A (Continued)

COST AND FINANCIAL STATEMENT 
See 
Secetion 
in Text Project Funding 
39. Brevard County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
40. Broward County, New Work: 
Fla. Beach Erosion Approp. 
Control and Hills- Cost 
boro Inlet, Fla., Maint: 
Navigation Project Approp. 
(Federal Funds) Cost 
Contrib. Funds) New Work: 
Approp. 
Cost 
41. Duval County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
42. Indian River New Work: 
County Fla. Approp. 
(Federal Funds) Cost 
43. Palm Beach New Work: 
County, Fla. from Approp. 
Martin County line Cost 
to Lake Worth Maint: 
Inlet to Broward Approp. 
County line Cost 
Federal Funds 
44. Pinellas County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
47. Central and New Work: 
Southern Florida Approp. 
(Federal Funds) Cost 
Maint: 
Approp. 
Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
48. Dade County, New Work: 
Fla. Approp. 
(Federal Funds) Cost 
(Contrib. Funds) New Work: 
Approp. 
Cost 
49. Dade County, New Work: 
N. of Haulover Approp. 
Beach, Fla. Cost 
(Federal Funds) 
(Contrib. Funds) New Work: 
Approp. 
Cost 
Total Cost to 
FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
3,598 13,667 4,275 
- 244,000- 
17,615 14,771 - 
-506,000 3,544,000 500,000 
1,221,457 564,947 2,881,443 
- 3,955,250 
272,094 1,862,188 1,160,445 
- - 200,000 
- - 46,539 
-300,000 234,000 - 
35,599 58,893 - 
803,000 885,000 2,200,000 
943,102 746,218 1,503,562 
549,250 1,435,000 868,000 
439,840 407,100 2,123,578 
6,065,000 9,814,000 15,300,000 
7,814,088 9,487,398 11,613,403 
4,733,500 4,507,200 5,211,000 
4,916,056 4,517,244 3,627,164 
1,322,261 179,183 8,230 
813,118 1,025,861 1,224,366 
940,000 
1,759,116 3,359,000 200,000 
3,101,419 -513 
741,000 1,985,000- 
683,129 1,601,237 324,658 
135,000 100,000 6,883,000 
12,939 45,309 5,928,340 
- 1,500,000 6,575,000 
- - 4,425,621 
9-32 
16,410 
12,777 
2,511,000 
380,337 
174,579 
100,000 
207,547 
64,028 
2,992,000 
674,349 
135,542 
241,027 
16,100,000 
17,603,265 
4,807,619 
4,685,876 
971,000 
1,407,080 
1,711,000 
149,102 
576,000 
10,408 
351,400 
-576,000 
2,182,572 
2,346,492 
2,309,101 
29,001 
29,001 
2,262,000 
2,257,081 
11,277,100 
11,028,031 
26,884 
26,884 
1,758,8413 
1,758,8413 
15,467,900 
12,208,386 
10,667,650 
8,533,253 
300,000 
254,086 
4,797,834 
3,962,330 
13,621 
13,621 
7,789,693 
6,538,456 
5,625 
5,625 
5,541,183 
5,409,601 
333,335,39740 
329,833,82640 
65,760,280 
64,010,545 
56,532,049 
56,219,098 
38,553,9567 
36,416,00137 
26,136,0853 
25,122,436@ 
7,133,000 
6,337,988 
7,499,000 
6,608,193 
TABLE 9-A (Continued)

COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
50. Four River New Work: 
Basins, Fla. Approp. 903,000 566,000 696,000 400,000 74,042,09541 
Federal Funds) Cost 1,714,126 581,791 778,523 342,380 73,943,89041 
Contrib. Funds) New Work: 
Approp. 360,000 - 735,000 425,981 13,907,841 
Cost 347,003 259,425 252,986 856,061 13,738,949 
51. Portugues and New Work: 
Bucana Rivers, Approp. 20,949,000 39,697,000 29,080,000 8,500,000 218,651,568 
P.R. Cost 21,238,471 27,285,097 16,547,880 30,861,960 214,396,989 
Federal Funds) 
Contrib. Funds) New Work: 
Approp. - - 220,000 50,000 270,000 
Cost - - 171,698 22,901 194,599 
JACKSONVILLE, FLA. DISTRICT 
1. Excludes $288,000 contributed funds for new work. 
2. Includes $97,566 for previous project. 
3. Excludes $243,235 contributed funds for new work. 
4. Excludes $700,000 contributed by NASA in connection 
with construction of lock. 
5. Includes $113,000 for new work on previous project; 
excludes $15,563 expended for new work on existing project 
from contributed funds. 
6. Excludes $113,744 for maintenance and operations of 
dams. 
7. Includes $174,880 expended for recreation facilities. 
8. Includes $10,128 cost for reconnaissance and detailed 
project report prepared under Sec. 107 modification to the 
project. Excludes $1,095 contributed funds for new work. 
9. Includes $515,479 for new work for previous projects: 
$8,472 for new work on Sunshine Skyway Channel; and $9,707 
for new work for Cats Point Channel. Excludes $14,473 
contributed funds for new work. 
10. Includes $450,749 for maintenance for previous project. 
11. Includes $94,776 for work for previous projects. 
Excludes $2,199,842 expended from public works funds for 
new work. 
12. Includes $213,222 for maintenance on previous projects 
and $3,179 operating and care under provisions of permanent 
indefinite appropriation. 
13. Includes $3,520,137 new work on previous project and 
$290,013 for new work expended from public works funds. 
14. Includes $543,399 maintenance on previous projects. 
15. Includes unused contributed funds of $64,136 returned 
to local interests. 
16. Project authorized December 2, 1964, by Chief of Engineers 
under Section 107 of 1960 R&H Act and by Section 
110 of the 1966 R&H Act. Cost of new work excludes $53,732 
contributed funds. 
17. Includes $5,502,126 expended from public work funds 
for new work. Includes costs of $6,777,906 for recreation 
facilities. 
18. Includes $381,479 work-in-kind and $172,314 in costs 
for north jetty recreation facility. 
19. Excludes $45,811 contributed funds for new work. 
20. Includes $16,222,275 for new work under previous 
project, $626,925 for recreational facilities (Code 710), and 
$27,574 for reconnaissance and detailed project report 
prepared under Section 107 modification to the project. 
21. Includes $7,581,150 for maintenance for previous 
projects. Excludes $1,000 for maintenance from contributed 
funds on previous projects, $67,558 which represents services 
rendered without reimbursement, and $113,744 for maintenance 
and operations of dams. 
22. Includes $3,912 for new work for previous projects. 
23. Includes $11,414 for operating and care under provisions 
for the permanent indefinite appropriation. 
24. Includes $80,000 new work from public works funds. 
Excludes $509,506 contributed funds. 
25. Includes $30,000 for maintenance from public works 
funds. 
26. Includes $11,588 expended for restudy, but excludes 
$21,960 expended for new work from contributed funds. 
27. Excludes $1,033,069 contributed funds. 
28. Includes $71,303 for new work on previous project. 
Excludes $137,500 contributed fund. 
29. Baresford cutoff and completion of cutoffs and easing 
of bends in Putnam Lake and Volusia Counties in inactive 
status were deauthorized by Public Law 93-251 section 12. 
Includes $29,566 for new work under previous project. 
30. Includes $25,838 under previous project. 
31. Includes $26,689 for new work under previous project. 
32. Includes $747,684 for new work under previous project. 
Excludes $100,000 expended for new work from contributed 
funds. 
33. Includes $44,730 in maintenance under previous 
project. 
34. Includes $853,050 for new work under previous project. 
Excludes $270,466 for new work for Hillsborough River and 
$13,939 for new work from contributed funds. Includes 
$215,000 Appropriation and $139,792 cost for new work East 
Bay Channel. 
35. Includes $17,107 for maintenance under previous 
project. 
' 36. Excludes work-in-kind. 
37. Includes $2,294,134 for reimbursement costs to Bal 
SHarbor. 
38. Excludes unused contributed funds of $17,969 returned 
to local interests. 
39. Excludes $300,083 in property for services furnished 
by local interests in lieu of cash contribution. 
40. Excludes $15,543 for property received without 
reimbursement and R&H Funds, expended on previous 
projects (see cost and financial statement for Okeechobee 
Waterway, Fla., project for these costs). Excludes $100,000 
advanced by local interests toward federal costs. Includes 
$175,000 appropriation and $175,000 cost for new work at 
C&SF St. Johns Water Mgtm. District. 
41. Includes costs of $89,691 for recreation facilities at Moss 
Bluff and $2,638,272 at Lake Tarpon. 
9-33 
TABLE 9-A (Continued)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
October 27, 1965 
August 26, 1937 
March 4, 1913 
June 20, 1939 
July 14, 1960 
March 2, 1945 
October 23, 1962 
Report of the 
Chief of Engineers 
Oct. 1985 
June 20, 1938 
July 14, 1960 
July 25, 1912 
March 3, 1925 
July 3, 1930 
August 26, 1937 
May 17, 1950 
P.O. 675/77 
July 23, 1942 
November 17, 1986 
June 20, 1938 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and progressive eradication of obnoxious aquatic plants, and 
continuedresearch to develop best method of control 
ARECIBO HARBOR, P.R. (See Section 2 of Text) 
Construction of breakwater 1,200 feet long and dredging channel 
25 feet deep and 400 feet wide with flare at entrance and widening 
at inner end to form a maneuvering area. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA. AND THE ST. JOHNS RIVER, FLA. 
(See Section 3 of Text) 
Channel 7 x 100 feet 
Channel 12 feet deep and 90-150 feet wide with cutoffs 
BAKERS HAULOVER (See Section 4 of Text) 
Channel 11 x 200 feet in ocean entrance, thence 8 x 100 feet to 
Intracoastal Waterway; Marina basin 8 x 200 feet; reconstruction 
of jetties and protection of inlet shores. 
CANAVERAL HARBOR, FLA. (See Section 5 of Text) 
Entrance channel jetties, a turning basin enclosed by a dike, and a 
barge canal with a lock. 
Maintain improved channel, turning basin, enlarge barge channel and 
lock, relocate dike, provide channel and turning basin west of 35- 
foot turning basin, construct and operate sand-transfer plant 
Mitigation of fish and wildlife losses at Port Canaveral West Turning 
Basin Project. 
CHANNEL FROM NAPLES TO BIG MARCO PASS, FLA. 
(See Section 6 of Text) 
Interior channel 6 x 70 feet 
Channel 12 x 150 feet from the Gulf to Gordon Pass, thence 10 x 100 
feet to a point 400 feet south of U.S. Highway 41 Bridge, thence 10 
x 70 feet to bridge and two turning basins 
CHARLOTTE HARBOR, FLA. (See Section 7 of Text) 
Channel 24 x 300 feet through Gulf through Boca Grande entrance 
Depth of 27 feet at entrance and width of 500 feet at the bend 
Channel 10 x 100 feet to Punta Gorda and a turning basin 
Depth of 30 feet at entrance and width of 700 feet at bend 
Depth of 32 feet in entrance channel 
CROSS-FLORIDA BARGE CANAL (See Section 8 of Text) 
Barge Canal 12 x 150 feet 
Establishment of the Cross Florida National Conservation Area. 
EAU GALLIE HARBOR, FLA. (See Section 9 of Text) 
Channel 8 x 100 feet and a turning basin 
H. Doc. 251, 89th Cong., 
1st sess. 
Rivers & Harbors Committee 
Doc. 43, 75th Cong., 1st sess. 
H. Doc. 898, 62nd Cong., 
2d sess. 
H.Doc. 618, 75th Cong., 
3d sess. 
H.Doc. 189, 86th Cong., 
1st sess. 
H.Doc. 367, 77th cong., 
1st sess. 
S.Doc. 140, 87th Cong., 
2d sess. 
P.L. 99-662, 17 November 1986 
99th Congress 2nd Sess. 
H.Doc. 596, 75th Cong., 
3d sess. 
H.Doc. 183, 86th Cong., 
1st sess. 
H.Doc. 699, 62nd Cong., 2d sess. 
H.Doc. 113, 66th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 1, 70th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 95, 74th Cong., 2d sess. 
H.Doc. 186, 81st Cong., 
1st sess. 
H.Doc. 109, 79th Cong., 
1st sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
H.Doc. 497, 75th Cong., 
3rd sess. 
9-34

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
June 14, 1880 
July 13, 1892 
March 2, 1907 
June 25, 1910 
March 3, 1925 
June 20, 1938 
March 2, 1945 
May 17, 1950 
July 14, 1960 
Auth. by Chief of 
Engineers 
December 6, 1968, 
under Sec. 107 of 
1960 R&H Act. 
Def. Act of 
March 4, 1931 
War Dept. Approp. 
Act, March 4, 1933 
August 30, 1935 
March 2, 1945 
June 30, 1948 
May 17, 1950 
September 3, 1954 
May 10-16, 1957 
Auth. March 1, 1962 
By Senate 
and House 
Public Works 
Committee 
Auth. by Chief of 
Engineers 
March 1, 1963, 
under Sec. 107 of 
1960 R&H Act 
FERNANDINA HARBOR, FLA. (See Section 10 of Text) 
Entrance jetties 
Raising and extending jetties to provide 19-foot depth 
Improvement of inner harbor to obtain 20- to 24-foot depth and 400- to 
600-foot channel width 
Combining improvement of Fernandina Harbor and Cumberland 
Sound under the general heading of Fernandina Harbor 
Provided for a 26-foot channel 
Provided for the 28-foot channel and turning basin 
Provided for reducing the maximum width of turning basin from 
1,000 to 800 feet, for shifting channel line in this vicinity 50 feet 
northwesterly and for including in authorized project small area 
dredged by Rayonier, Inc. 
Provided for 32-foot channel and turning basin 
FORT MYERS BEACH, FLA. (See Section 11 of Text) 
12- x 150 foot channel in San Carlos Bay, thence 11 x 125 feet in 
Matanzas Pass to upper shrimp terminals 
Extension of 11- x 125-foot channel easterly about 2,000 feet to and 
including a turning basin adjacent to natural deep water in 
Matanzas Pass 
FORT PIERCE HARBOR, FLA. (See Section 12 of Text) 
Expenditure of $20,000 for dredging channel, maintenance by local 
interests 
Expenditure of up to $30,000 for dredging channel 
Maintaining channels, jetties, and revetments, and enlarging channels 
and turning basin to existing project dimensions 
INTRACOASTAL WATERWAY CALOOSAHATCHEE RIVER 
TO ANCLOTE RIVER, FLA. (See Section 13 of Text) 
9- x 100-foot channel; deepening channel at Caseys Pass to 9 feet and 
construction of highway bridge at Venice 
Original route may be modified at no excess cost to U.S. 
Any route in Venice-Lemon Bay area may be used 
Use of alternate Route C-1 in Venice-Lemon Bay area 
Local interests to bear costs of Venice Avenue highway bridge and any 
other necessary crossing over Route C-1 
Sunshine Skyway Channel to be improved and maintained to 9 x 100 
feet 
Annual Report 1879 
Annual Report 1891 & 1896 
H.Doc. 388, 59th Cong., 
1st sess. 
H.Doc. 227, 68th Cong., 
1st sess. 
H.Doc. 284, 77th Cong., 
1st sess. 
H.Doc. 284, 87th Cong., 
1st sess. 
H.Doc. 662, 80th Cong., 
2d sess. 
H.Doc. 183, 86th Cong., 
1st sess. 
Specified in Act 
Specified in Act 
H.Doc. 252, 72nd Cong., 
1st sess. and Rivers and 
Harbors Committee Doc. 21, 
74th Cong., 1st sess. 
H.Doc. 371, 76th Cong., 
1st sess. 
Specified in Act 
Specified in Act 
Specified in Act 
H.DOc. 109, 85th Cong., 
1st sess. 
H.Doc. 109, 85th Cong., 
1st sess. 
6- x 80-foot channel in Boca Ciega Bay 
January 21, 1927 
INTRACOASTAL WATERWAY, JACKSONVILLE TO MIAMI, 
FLA. (See Section 14 of Text) 
Channel 8 x 75 feet from Jacksonville to Miami H.Doc. 586, 69th Cong., 
2d sess. 
9-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
PARA June 26, 1934 
August 26, 1937 
March 2, 1945 
Do. 
Do. 
July 3, 1958 
Chief of Enginers 
Report of July 22, 
1960, Mod. 12-foot 
channel 
March 2, 1907 
Report of the 
Chief of Engineers 
12 Feb 1982 
Auth. by Chief of 
Engineers December 
2, 1964 under 
Sec. 107 of 1960 
R&H Act and Sec. 
110 of 1966 R&H 
Act 
Auth. by Chief of 
Engineers 
April 20, 1976 
under Sec. 107 of 
1960 R&H Act, 
as amended 
Report of the 
Chief of Engineers 
12 May 1980 
August 30, 1935 
August 20, 1937 
July 3, 1930 
Channel width of 100 feet 
Operation and care of Palm Valley Bridge 
Turning basin at Jacksonville Beach 
Channel 12 x 125 feet 
Side channel and turning basin at Sebastian 
Turning basin at Vero Beach 
Maintenance of side channel at Daytona Beach 
Channel 10 x 125 feet from Ft. Pierce to Miami 
JACKSONVILLE HARBOR, FLA. (See Section 15 of Text) 
ST. JOHNS RIVER, FLA. OPPOSITE THE CITY OF 
JACKSONVILLE 
The 24-foot area from Hogan Creek to Florida East Coast Railroad 
bridge 
JACKSONVILLE HARBOR (MILL COVE), FLORIDA 
(See Section 16 of Text) 
Enlarge weir structure and west opening controlling flow into Mill 
Cove, to reduce shoaling and improve navigation as well as 
circulation. 
JOHN'S PASS, FLA. (See Section 17 of Text) 
Channel 10 x 150 feet in gulf, 8 x 100 feet inside pass, 
6 x 100 feet to IWW-2.6 miles long. 
LONGBOAT PASS, FLA. (See Section 18 of Text) 
12- x 150-foot entrance channel from Gulf of Mexico to Longboat 
Bridge; 10- x 100-foot channel from Longboat Bridge northeasterly 
to IWW; channel from north channel to Cortez Bridge 
MANATEE HARBOR, FLORIDA (See Section 19 of Text) 
Provide for maintenance of the existing 40-ft. deep draft navigation 
channel and turning basin from Tampa Bay to Port Manatee. 
Initial construction of a widener at Manatee Harbor and deepen 
area adjacent to berthing area. 
MAYAGUEZ HARBOR P.R. (See Section 20 of Text) 
Approach channel 30 feet deep to and along deep water terminal 
MELBOURNE HARBOR, FLA. (See Section 21 of Text) 
Channel 8 x 100 feet and a turning basin 
MIAMI HARBOR, FLA. (See Section 22 of Text) 
MIAMI RIVER 
The 15-foot channel in Miami River, 150 feet wide at the mouth 
9-36 
S.Doc. 71, 71st Cong., 
2d sess. 
Specified in Act 
H.Doc. 180, 75th Cong., 
1st sess. 
H.Doc. 740, 79th Cong., 
2d sess. 
H.Doc. 336, 76th Cong., 
1st sess. 
H.Doc. 261, 76th Cong., 
1st sess. 
H.Doc. 222, 85th Cong., 
1st sess. 
H.Doc. 663, 59th Cong., 
1st sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd Sess. 
H.Doc. 215, 72nd Cong. 
1st sess. & River and 
Harbor Committee Doc. 1, 
73rd Cong., 1st sess. 
H.Doc. 390, 74th Cong., 
2nd sess. 
Specified in Act

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Auth. by Chief of 
Engineers November 
5, 1968, under 
Sec. 107 of 1960 
R&H Act 
September 19, 1890 
March 2, 1907 
June 25, 1910 
July 25, 1912 
July 27, 1916 
PARA June 26, 1934 
March 13, 1934 
December 10, 1934 
August 30, 1935 
March 2, 1945 
May 17, 1950 
July 14, 1960 
Report of the 
Chief of Engineers, 
10 December 1985 
October 27, 1965 
March 3, 1925 
August 30, 1935 
March 2, 1945 
H.R. September 
23, 1976 
S.R. October 1, 
1976 
Enlarge existing 8- x 90-foot section of Okeechobee Waterway for 
about 5 miles upstream from Ft. Myers to 10 x 100 feet 
OKLAWAHA RIVER, FLA. (See Section 25 of Text) 
Clearing obstructions for channel 4 feet deep from mouth to Leesburg 
Channel 6 feet deep from mouth to head of Silver Springs Run 
Maintenance of levels in the lakes at head of river 
Acceptance of certain artificial waterways in lieu of portions of 
natural river bed 
Operation and care of lock and dam provided for with funds from 
appropriations for rivers and harbors 
PALM BEACH HARBOR, FLA. (See Section 26 of Text) 
Maintenance of improvement previously constructed by local interests 
Deepening the channels and turning basin, as constructed by local 
interests, to 20 feet 
Authorized the work previously approved by Public Works 
Administration, and widening the channels to existing project 
dimensions, enlarging the 700-foot-square turning basin eastward 
removing the obstructive point on south side of the inlet, revetting 
the banks of the inlet, and restoring existing jetties 
Deepening the channels and turning basin to 25 feet 
Extending the turning basin 550 feet southward over a 900-foot width, 
with a flare to the east; provided that local interests may be 
reimbursed not to exceed $305,000 for work done by them on this 
modification subsequent to July 1, 1949 
An entrance channel 35 feet deep, 400 feet wide, and 0.8 mile long, 
merging with an inner channel 33 feet deep, 300 feet wide and 0.3 
mile long, thence flaring into a turning basin, 1,400 feet northsouth 
by a minimum of 1,200 feet east-west 
Assume maintenance 
PONCE DE LEON INLET, FLA. (See Section 27 of Text) 
Widening and deepening channels; jetties on north and south side of 
inlet; a weir in the north jetty and an impoundment basin inside the 
weir 
PONCE HARBOR, P.R. (See Section 28 of Text) 
Dredging 3 continuous areas, aggregating 153 acres, to depths of 30, 
18, and 9 feet, and construction of a seawall, costs to be shared by 
U.S. and local interests 
Modified conditions of local cooperation to provide that U.S. undertake 
all dredging at Federal expense and return local funds previously 
contributed for dredging, all other portions of the improvement 
hereafter to be at the expense of local interests 
Eliminate previously authorized 9-foot dredging area, and provided 
for dredging 30-foot-depth area and 18 acres off the municipal pier 
and for construction of the breakwater off Punta Carenero 
Eliminate previously authorized 18-foot and a portion of the 30-foot 
project outside the proposed 36-foot and a portion of the adjacent to 
the municipal bulkhead. Channel 36 x 600 feet from Caribbean Sea 
to harbor; channel 36 x 400 feet into harbor; and a 36-foot turning 
basin 
9-37 
Annual Report, 1889, p. 1360 
H.Doc. 782, 59th Cong., 
1st sess. 
Specified in Acts 
Specified in Act 
Specified in Act 
H.Doc. 185, 73d Cong., 
2d sess. 
Recommended by Chief of 
Engineers to Public 
Works Administration 
October 17, 1934 
H.Doc. 185, 173d Cong., 
2d sess. and Rivers and 
Harbors Committee Doc. 42, 
74th Cong., 1st sess. 
H.Doc. 530, 78th Cong., 2d sess. 
H.Doc. 704, 80th Cong., 
2d sess. 
H.Doc. 283, 86th Cong., 
1st sess. (contains latest 
published map) 
P.L. 99-662 17 Nov. 1986 
99th Cong. 2nd sess. 
H.Doc. 74, 89th Cong., 
1st sess. 
H.Doc. 532, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 18, 72d Cong., 1st sess. 
H.Doc. 745, 79th Cong., 
2d sess. 
H.Doc. 532, 94th Cong., 2d sess.

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
PWA Program 
September 6, 1933 
June 13, 1902 
March 2, 1907 
March 4, 1913 
March 3, 1925 
July 3, 1930 
August 30, 1935 
August 26, 1937 
March 2, 1945 
March 2, 1945 
July 14, 1960 
August 13, 1968 
Auth. by Chief of 
Engineers 
April 20, 1964 
under Sec. 107 of 
1960 R&H Act 
PARA June 26, 1934 
August 26, 1937 
March 2, 1945 
Do. 
March 2, 1945 
Do. 
The channel at the Dinner Key Airport 
An 18-foot channel in a landcut across the peninsula and construction 
of the north jetty 
Construction of the south jetty and increase of channel width 
to 100 feet 
Modification of local cooperation requirements imposed by the Act of 
July 25, 1912 
A channel 25 feet deep with present widths from the ocean to Biscayne 
Bay, thence 200 feet wide across the bay to but not including the 
municipal turning basin, and extension of both jetties 
A channel width of 300 feet across the bay and enlarging the 
municipal turning basin, with expenditures thereon limited to 
$200,000 
A depth of 30 feet from the ocean to and in the turning basin, with the 
existing authorized project widths, including the 300-foot width in 
the channel across the bay 
Extending the turning basin 200 feet to the southward 
The Virginia Key improvement 
For incorporation of the project for Miami River in that for Miami 
Harbor, the widening at the mouth of Miami River to existing 
project widths; the channels from the mouth of Miami River to the 
turning basin and to Government Cut; and the channel from Miami 
River to the harbor of refuge, provided that local interest 
contribute one-third of the cost 
Deletion of Virginia Key development and the Dinner Key approach 
channel, widening the existing ship channel by easing the ocean 
bend and increasing the width of the 300-foot-wide section to 500 
feet, enlarging the existing turning basin 300 feet along both the 
south and northeasterly sides, and dredging a turning basin along 
the north side of Fisher Island about 39 acres in extent and 30 feet 
in depth 
Enlarging existing entrance channel to 38 x 500 feet, deepening 
existing 400-foot-wide channel across Biscayne Bay to 36 feet; 
deepening existing turning basins at Biscayne Blvd. terminal and 
Fisher Island to 36 feet 
NEW PASS, SARASOTA, FLA. (See Section 23 of Text) 
10- x 150-foot entrance channel; 8- x 100-foot inner channels; and 
8-foot-deep turning basins at Payne Terminal and City Pier 
OKEECHOBEE WATERWAY, FLA. (See Section 24 of Text) 
Operation and care of locks and dams provided for with funds from 
R&H appropriations 
New lock and wier structure in St. Lucie Canal 
Deepening to 8 feet from Ft. Myers to JacksonvilleMiami waterway 
near Stuart view channel across lake from Clewiston 
Channel to yacht basin at Ft. Myers and a basin at Stuart 
Deepening to 8 feet from Ft. Myers to JacksonvilleMiami waterway 
near Stuart via channel across lake from Clewiston 
Channel to yacht basin at Ft. Myers and a basin at Stuart 
S.Doc. 95, 72d Cong., 1st sess. 
and specified in Act 
H.Doc. 622, 56th Cong., 
1st sess. (Annual Report 
1900, p. 1987) 
Specified in Act 
Specified in Act 
H.Doc. 516, 67th Cong., 
4th sess. 
Rivers and Harbors Committee 
Doc. 15, 71st Cong., 2d sess. 
Sen. Comm. Print. 
73d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 86, 74th Cong., 2d sess. 
S.Doc. 251, 79th Cong., 2d sess. 
H.Doc. 91, 79th Cong., 
1st sess. 
S.Doc. 71, 85th Cong., 
2d sess. 
S.Doc. 93, 90th Cong., 
2d sess. 
Specified in Act 
Rivers and Harbors Committee 
Doc. 28, 75th Cong., 
1st sess. 
H.Doc. 696, 76th Cong., 
3d sess. 
H.Doc. 736, 79th Cong., 
2d sess. 
H.Doc. 696, 76th Cong., 
3d sess. 
H.Doc. 736, 79th, Cong., 
2d sess. 
9-38

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
August 30, 1935 
June 20, 1938 
July 24, 1946 
July 3, 1958 
H.R. May 9, 1974 
S.R. May 31, 1974 
March 3, 1899 
June 13, 1902 
March 3, 1905 
June 20, 1938 
May 17, 150 
March 3, 1899 
March 2, 1919 
June 14, 1880 
June 25, 1910 
July 3, 1930 
March 2, 1945 
March 2, 1945 
July 24, 1946 
March 2, 1945 
November 7, 1966 
PORT EVERGLADES HARBOR, FLA. (See Section 29 of Text) 
Maintenance of harbor constructed by local interests H.Doc. 357, 71st Cong., 
2d sess. 
Enlarge entrance channel and complete turning basin to 1,200 feet Rivers and Harbors Committee 
square Doc. 25, 74th Cong., 
1st sess. 
Widen turning basin 350 feet on north side H.Doc. 545, 75th Cong., 
3d sess. 
Widen turning basin 200 feet on north side, 500 feet on south side and H.Doc. 768, 78th Cong., 2d sess. 
enlarge flare at entrance channel 
Deepen and widen entrance channel on a new alinement and increase H.Doc. 346, 85th Cong., 2d sess. 
turning basin in size and depth 
Deepen and widen entrance channel, enlarge turning basin, widen H.Doc. 144, 93d. Cong., 
Pier 7 channel, maintenance of Berth 18 channel, and planning for 1st sess. 
a south jetty fishing walkway with construction contingent upon 
need as developed by detailed postauthorization studies 
REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE 
WATERS IN THE STATE OF FLORIDA (See Section 30 of Text) 
Construction and operation of a suitable vessel and use of log booms for Annual Report 1899 
removal of water hyacinths in the navigable waters of the State 
Extermination and removal of water hyacinths by any mechanical, Specified in Act 
chemical, or other means 
Prohibits use of any chemical process injurious to cattle Specified in Act 
ST. AUGUSTINE HARBOR, FLA. (See Section 31 of Text) 
Channel 27 x 200 feet protected by a groin H.Doc. 555, 75th Cong., 
3d sess. 
Channel 16 x 200 feet across bar, and thence 12 feet deep to H.Doc. 133, 81st Cong., 
Intracoastal Waterway; jetty on south side of inlet; future landward 1st sess. 
extension of groin and jetty; and channel 10 x 100 feet in San 
Sebastian River 
ST. JOHNS RIVER, FLA., JACKSONVILLE TO LAKE 
HARNEY (See Section 32 of Text) 
A channel 13 feet deep and 200 feet wide from Jacksonville to Palatka H.Doc. 523, 55th Cong., 2d sess. 
and Annual Report for 1989, 
p. 1343 
The improvement of Deep Creek H.Doc. 699, 63rd Cong., 
2d sess. 
Two jetties at Volusia Bar (Maintenance only; new work completed Annual Report for 1879, 
under previous project.) pp. 795-798 
A channel 100 feet wide, 8 feet deep from Palatka to Sanford with a H.Doc. 1111, 60th Cong., 
side channel to Enterprise, and thence 5 feet deep to Lake Harney 2d sess. 
Cutoffs at Butcher Bend, Shake Creek, and Starks Landing, and H.Doc. 691, 69th Cong., 
easing bends at other points 2d sess. 
A channel 10 feet deep and 100 feet wide from Palatka to Sanford, H.Doc. 603, 76th Cong., 
with a side channel to Enterprise and with cutoffs and easing of 3d sess. 
bends 
Combining the two projects above into a single project for St. Johns H.Doc. 445, 78th Cong., 
River, Fla., Jacksonville to Lake Harney, and for a cutoff 5 feet 2d sess. 
deep and 75 feet wide between Lake Monroe and the vicinity of 
Osteen Bridge (Woodruff Creek Cutoff) 
A channel 12 feet deep and 100 feet wide from Palatka to Sanford, and S.Doc. 208, 79th Cong., 
in the branch to Enterprise 2d sess. 
ST. LUCIE INLET, FLA. (See Section 33 of Text) 
Channel 10 x 200 feet H.Doc. 391, 77th Cong., 
1st sess. 
Modification to maintain existing channel 6 x 100 feet H.Doc. 508, 89th Cong., 
2d sess. 
9-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
H.R. May 9, 1974 
S.R. May 31, 1974 
August 8, 1917 
September 22, 1922 
July 3, 1930 
August 30, 1935 
August 26, 1937 
October 17, 1940 
March 2, 1945 
July 3, 1958 
August 4, 1976 
Report of the 
Chief of Engineers 
23 Dec. 1982 
March 3, 1899 
March 3, 1905 
June 25, 1910 
Extending north jetty and modifying existing jetty to provide a sand 
bypass weir section; excavation of sand impoundment basin; 
construction of south jetty with walkway for recreational fishing; 
channel 10 x 500 feet through bar cut, tapering to 150 feet through 
the inlet, and 100 feet and 7 feet deep to the Intracoastal Waterway; 
and transfer of 380,000 cubic yards of material to the south beach 
during each two-year maintenance period 
SAN JUAN HARBOR, P.R. (See Section 34 of Text) 
Anchorage (inner harbor) area of 206 acres and San Antonio Channel 
to 30-foot depth 
Substitution of a 68-acre area 30 feet deep along southeasterly side of 
anchorage area, for one 25 acres in extent and of same depth 
extending easterly from eastern end of the San Antonio project 
channel 
Modified condition of local cooperation 
Entrance channel across outer bar 38 feet deep and 800 feet wide, and 
thence across bay to anchorage area (Anegado Reach Channel) 30 
feet deep and 700 feet wide and increasing anchorage area to 239 
acres to 30-foot depth 
Widening Anegado Reach Channel and increasing anchorage area to 
329 acres 
Removal to 8-foot depth of Anegado, Largo, and Capitanejo Shoals, 
and dredging to 30-foot depth the entrance channel and turning 
basin to the Graving Dock 
Maintenance of the 30-foot depth entrance channel and turning basin 
to the Army Terminal 
Deepening portions of entrance and approach channels and basins to 
Army Terminal and San Antonio Pier areas to 35-45 feet; new 32- 
foot depth Puerto Nuevo Channel; new 36-foot depth anchorage 
A bar channel 48 by 800 feet, shifting the centerline 350 feet west; 
deepening Anegado Channel in steps from 46 to 40 feet while 
reducing reducing width to 800 feet; deepening Army Terminal 
Channel and turning basin to 40 feet while widening the channel to 
450 feet; deepening Puerto Nuevo Channel to 40 feet and widening 
it to 400 feet; deepening Graving Dock Channel to 40 feet at 
existing 400-foot width; deepening San Antonio Channel to 38 feet 
at varying widths, minimum of 500 feet; deepening cruise ship 
basin to 36 feet at an irregular width; maintaining Sabana 
Approach Channel at 30 by 250 feet; provide a 38-foot depth in 
Anchorage Area "E" with irregular width; six mooring dolphins 
for vessels using the area 
Modification of the authorized project to provide the deepening of the 
Bar Channel to 48 feet and shifting its alinement 350 feet to the 
west; deepening Anegado, and Army Terminal to 40 feet; 
deepening Graving Dock Channel, and Cruise Ship Basin, Puerto 
Nuevo Channel, and San Antonio Channel to 36 feet; and deepening 
Anchorage Area E to 38 feet while reducing its size and 
constructing six mooring dolphins within its limits. A 1500-footlong 
extension to San Antonio Channel would be added to the 
Federal project and Sabana approach deepened to 32 feet. 
TAMPA HARBOR, FLA. (See Section 35 of Text) 
TAMPA BAY 
For a channel 27 feet deep from the Gulf of Mexico to Port Tampa, 500 
feet wide across the bar and 300 feet wide in the bay 
For a channel depth of 26 feet with sufficient width from the Gulf of 
Mexico to Port Tampa 
TAMPA AND HILLSBOROUGH BAYS 
For a depth of 24 feet in Hillsborough Bay 
9-40 
H.Doc. 294, 93rd Cong., 
1st sess. 
H.Doc. 865, 63d Cong., 
2d sess. 
Specified in Act 
H.Doc. 45, 71st Cong., 
2d sess. 
R&H Comm. Doc. 38, 
74th Cong., 1st sess. 
R&H Comm. Doc. 42, 
75th Cong., 1st sess. 
H.Doc. 364, 76th Cong., 
1st sess. 
Specified in Act 
H.Doc. 38, 85th Cong., 
1st sess. 
H.Doc. 574, 94th Cong., 
2d sess. 
P.L. 99-662 17 Nov. 1986 
99th Cong. 2nd Sess. 
H.Doc. 52, 55th Cong., 
3d sess. (Also printed in 
Annual Report 1899, p. 1640) 
Channel dimensions 
specified in Act 
Specified in Act 
H.Doc. 634, 61st Cong., 
2d sess.

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
August, 8, 1917 
March 3, 1899 
September 22, 1922 
July 3, 1930 
August 30, 1935 
June 20, 1938 
Do. 
March 2, 1945 
Do. 
Do. 
May 17, 1950 
September 3, 1954 
October 23, 1962 
December 31, 1970 
Do. 
Do. 
Do. 
For a 27-foot depth from Gulf of Mexico up to and in the several 
channels of Hillsborough Bay, the widths to be 500 feet on the bar, 
300 feet in Tampa Bay, Ybor, and Garrison Channels, and 200 feet 
in Hillsborough Bay, Sparkman, and Seddon Channels, with 
turning basins at the mouth of Hillsborough and at Ybor Estuary 
HILLSBOROUGH RIVER 
For a 12-foot channel to within 100 feet of the Lafayette St. highway 
bridge (maintenance only; new work completed under a previous 
project under the title Improving Hillsborough Bay, Fla.) 
TAMPA HARBOR 
Consolidation of the above projects to form a single project for 
Tampa Harbor 
Increasing the depth of Egmont Channel to 29 feet and the width of 
Sparkman Channel to 300 feet 
For a depth of 32 feet and a width of 600 feet on Egmont Bar, a depth 
of 30 feet and a width of 400 feet in Mullet Key Cut, and a depth of 
30 feet and a width of 300 feet in all other project channels in 
Tampa Harbor (except in Hillsborough River and in the channel 
leading to Alafia River); and for a turning basin 2,000 feet long and 
500 feet in maximum width at the entrance to the Port Tampa 
terminals 
For widening the bend between Sparkman Channel and Cut D of 
Hillsborough Bay Channel by 250 feet; widening Ybor Channel to 
400 feet and extending the turning basin at the west end of 
Garrison Channel (mouth of Hillsborough River) easterly for 300 
feet 
For construction of a breakwater at Peter O. Knight Field, Davis 
Islands, its maintenance to be assumed by local interest 
For widening Sparkman Channel to 400 feet and Ybor Channel to 500 
feet; widening the bend between Sparkman and Garrison Channels 
an additional 250 feet to extend the turning basin westerly; and 
widening the bend between Seddon and Garrison Channels by 150 
feet (in lieu of 300 feet previously authorized) to extend the turning 
basin easterly 
For a channel 9 feet deep and 100 feet wide in the Hillsborough River 
for about 2.4 miles above the upper end of the existing 12-foot 
channel, and for the removal of obstructions thence to the Florida 
Avenue Bridge 
For a channel 25 feet deep and 150 feet wide from the Hillsborough 
Bay channel to and including a turning basin in the Alafia River 
(Revoked by Act of May 17, 1950) 
For deepening Egmont Channel to 36 feet; enlarging Mullet Key Cut, 
Tampa Bay Channel, Hillsborough Bay Channel, Port Tampa 
Channel and Port Tampa turning basin to present project 
dimensions; deepening Sparkman Channel and Ybor turning basin 
to 34 feet; a channel 30 feet deep and 200 feet wide from 
Hillsborough Bay Channel to and inclduing a turning basin in 
Alafia River, 700 feet wide and 1,200 feet long (in lieu of the 
improvement previously authorized); and substantial widening at 
entrance, bends, and turns 
Extended removal of obstructions in Hillsborough River to City Water 
Works Dam. Maintenance of cleared channel to be assumed by 
local interests 
Channel and turning basin at Port Sutton 30 feet deep, Ybor Channel 
34 x 400 feet 
For federal maintenance of Port Sutton Channel, 280 feet wide and an 
irregularly shaped turning basin.both to a depth of 34 feet 
Enlarge entrance channel across Egmont Bar to 46 x 700 feet from the 
Gulf to Mullet Key 
Enlarge Mullet Key Cut Channel to 44 x 600 feet 
Enlarge Tampa Bay Channel to 44 x 500 feet from Mullet Key Cut 
through Tampa Bay to the junction of Hillsborough Bay and Port 
Tampa Channels 
9-41 
H.Doc. 634, 61st Cong., 
1st sess. 
H. Doc. 545, 55th Cong., 
2d sess. and Annual Report 
1898, pp. 1357-1360 
Specified in Act 
H.Doc. 100, 70th Cong., 
1st sess. 
S.Doc. 22, 72d Cong., 
1st sess. 
S.Doc. 164, 75th Cong., 
3d sess. 
Sen. Comm. Print. 
76th Cong., 1st sess. 
S.Doc. 183, 78th Cong., 
2d sess. 
H.Doc. 119, 77th Cong., 
1st sess. 
S.Doc. 16, 77th Cong., 
1st sess. 
H.Doc. 258, 81st Cong., 
1st sess. 
H. Doc. 567, 81st Cong., 
2d sess. 
H.Doc. 529, 87th Cong., 
2d sess. 
H.Doc. 150, 91st Cong., 
1st sess. 
H.Doc. 401, 91st Cong., 
2d sess. 
Do. 
Do.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
August 15, 1985 
Report of the 
Chief of Engineers 
25 Jan. 1979 
W.R.D.A. 
17 November 1986 
BEACH EROSION 
CONTROL PROJECTS 
August 13, 1968 
October 27, 1965 
Report of the 
Chief of Engineers 
2 April 1982 
August 13, 1968 
Enlarge Hillsborough Bay Channel to 44 x 500 feet from the junction 
with Tampa Bay and Port Tampa Channels to the junction with 
Port Sutton entrance channel, and thence deepening to a depth of 
42 feet at the existing width of 400 feet to the function with Seddon 
and Sparkman Channels 
Enlarge Port Sutton entrance channel to 44 x 400 feet 
Enlarge Port Sutton turning basin to a depth of 44 feet and a turning 
diameter of 1,200 feet 
Deepening Sparkman Channel to 42 x 400 feet 
Deepening Ybor Channel to 40 x 300 feet 
Enlarge turning basin at the entrance to Ybor Channel to a depth of 
42 feet and an additional width of 200 feet on the southwest edge of 
the present basin 
Deepening Port Tampa Channel to 42 feet at its existing width from 
the junction with Hillsborough and Tampa Bay Channels to the 
turning basin 
Deepening the Port Tampa turning basin to 42 feet over its existing 
length of 2,000 feet and width of 900 feet 
An entrance channel in East Bay 44 x 400 feet and 500 feet north 
from the Port Sutton turning basin for a distance of about 2,000 
feet 
A turning basin in East Bay at a depth of 44 feet and with a turning 
diameter of 1,200 feet 
An approach channel in East Bay 44 x 300 feet north from the East 
Bay turning basin for a distance of about 2,500 feet 
Maintenance of Port Sutton Terminal channel to 44 x 200 feet for a 
distance of 4,000 feet 
Maintenance of East Bay channel to 34 x 300 feet for a distance of 
5,500 feet 
TAMPA HARBOR BRANCH CHANNELS 
Enlarging Hillsborough Bay Cut D, Sparkman Channel, Port Tampa 
Channel and existing turning basins at the entrance to Ybor 
Channel and at Port Tampa, all to a depth of 41 ft. with varying 
lengths and widths and deepening Ybor Channel to a depth of 39 
feet. This work will be associated with the Main Channel 
deepening. 
TAMPA HARBOR EAST BAY CHANNEL 
Maintenance dredging 
BREVARD COUNTY, FLA. (See Section 39 of Text) 
Federalparticipation in cost of shore protection project 
BROWARD COUNTY, FLA. BEACH EROSION CONTROL 
AND HILLSBORO INLET, FLA., NAVIGATION PROJECT 
(See Section 40 of Text) 
Improvement for beach erosion control in Broward County, Fla. and a 
combined beach erosion and navigation improvement to 
Hillsborough Inlet and the shore south thereof to Port Everglades 
CHARLOTTE COUNTY, FLORIDA 
Shoreline Protection 
DADE COUNTY, FLA. (See Section 41 of Text) 
Federal participation in cost of shore protection and hurricane-flood 
control project 
9-42 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
H.Doc. 236, 99th Cong., 
1st sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd Sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd Sess. 
H.Doc. 352, 90th Cong., 
2nd sess. 
H.Doc. 91, 89th Cong., 
1st sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd Sess. 
H.Doc. 335, 90th Cong., 
2d sess. 
]

TABLE 9-B (Continued) 
JACKSONVILLE, FLA. DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
August 15, 1985 
Report of the 
Chief of Engineers 
27 Dec 1983 
October 27, 1965 
W.R.D.A. 
17 November 1986 
Report of the 
Chief of Engineers 
22 April 1984 
October 23, 1962 
November 7, 1966 
Report of the Board 
of Engineers for 
Rivers and Harbors 
23 April 1985 
Report of the 
Chief of Engineers 
28 Feb. 1986 
Report of the 
Chief of Engineers 
26 Feb. 1980 
FLOOD CONTROL 
PROJECTS 
June 30, 1948 
September 3, 1954 
July 14, 1960 
October 23, 1962 
Do. 
DADE COUNTY-NORTH OF HAULOVER BEACH, FLA. 
(See Section 42 of Text) 
Federal participation in cost of shore protection and hurricane-flood 
control project 
Extending of existing shore protection project for Dade County to 
provide for protective beach fill and subsequent nourishment along 
2.5 miles of shore north of Haulover Beach Park. 
DUVAL COUNTY, FLA. (See Section 43 of Text) 
Federal participation in cost of shore protection project 
INDIAN RIVER COUNTY, FLORIDA 
(See Section 42 of Text) 
The plans provide for a 2.65 mile beach fill along the ocean shore of 
Vero Beach a 1.7 mile beach fill along the ocean shore of Sebastian 
Inlet State park and for periodic nourishment of the new beaches. 
MONROE COUNTY, FLORIDA 
Modification of existing project from 6200-ft. long to 8770-ft. long 
beach fill stabilized with two groins and periodic nourishment. 
PALM BEACH COUNTY, FLA., FROM MARTIN COUNTY 
LINE TO LAKE WORTH INLET AND FROM SOUTH 
LAKE WORTH INLET TO BROWARD COUNTY LINE 
(See Section 44 of Text) 
Federal participation in cost of local shore protection project and sandtransfer 
plant 
PINELLAS COUNTY, FLA. (See Section 45 of Text) 
Federal participation in cost of shore protection project 
Restoration of 5,000 ft. of beach at Clearwater Beach Island, 49,000 ft. 
of beach at sand Key, 92,000 ft. of beach at Treasure Island, and 
construction of 600 ft. of revetment at Long Key. Also, 
renourishment of each island. 
SARASOTA COUNTY, FLORIDA 
Shoreline protection along 12,600 ft. of shoreline on central Longboat 
and 21,100 ft. on Manasota Key in the vicinity of Venice, Florida 
and periodic nourishment of these areas. 
ST. JOHNS COUNTY, FLORIDA 
Shoreline protection along 2.5 miles of problem area in the St. 
Augustine Beach and Coquina Gables area and periodic 
nourishment 
CENTRAL AND SOUTHERN FLORIDA (See Section 48 of 
Text) 
First phase of comprehensive plan for flood control and other purposes 
Modification and expansion of authorization to include entire 
comprehensive plan of improvement 
Canals, levees, and water-control and drainage structures in the 
Nicodemus Slough area, Glades County 
Flood protection on Boggy Creek, near Orlando 
Flood protection in the Cutler Drain area, near Miami 
H.Doc. 236, 99th Cong., 
1st sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
H.Doc. 273, 89th Cong., 
1st sess. 
P.L. 99-662 17 Nov. 1986 
99th Congress 2d sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
H.Doc. 164, 87th Cong., 
1st sess. 
H.Doc. 519, 89th Cong., 
2d sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
H.Doc. 643, 80th Cong., 
2d sess. (Contains latest 
published map). 
H.Doc. 643, 80th Cong., 
2d sess. 
S.Doc. 53, 86th Cong., 
1st sess. 
S.Doc. 125, 87th Cong., 
2d sess. 
S.Doc. 123, 87th Cong., 
2d sess. 
9-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. 
Do. 
Do. 
October 27, 1965 
Do. 
August 13, 1968 
Do. 
Approved 
December 17, 1970 
under the provisions 
of Section 
201 of the Flood 
Control Act of 
1965 
October 23, 1962 
December 31, 1970 
Report of the 
Chief of Engineers 
25 April, 1986 
Flood control and drainage works for South Dade County 
Project Shingle Creek between Clear Lake and Lake Tohopekaliga for 
flood control and major drainage, including development of Reedy 
Creek Swamp 
Improvement of easterly section of West Palm Beach Canal for flood 
control and major drainage 
Primary works for flood control and major drainage in southwest 
Dade County 
Primary works for flood control and major drainage in Hendry County 
Gravity drainage in Martin County and distribution of available water 
supplies to portions of Martin and St. Lucie Counties 
Improvement of supply, distribution and conservation of water 
resources in Central and Southern Florida, including Lake 
Okeechobee agricultural area, Everglades National Park and other 
related areas 
Navigation improvements suitable for recreational craft 
FOUR RIVER BASINS, FLA. (See Section 49 of Text) 
Control of floods and improvement of drainage, and for water 
conservation through construction of necessary canals, levees, 
reservoirs, and control structures 
PORTUGUES AND BUCANA RIVERS, P.R. 
(See Section 50 of Text) 
LAGO de CERRILLOS, P.R. 
Multiple purpose dam and lake for flood control, water supply and 
recreation 
LAGO de PORTUGUES, P.R. 
Multiple purpose dam and lake for flood control, water supply and 
recreation 
PONCE, P.R. 
Diversion and enlargement of existing channels through Ponce for 
flood control 
RIO PUERTO NUEVO, P.R. 
Project for flood control 
S.Doc. 138, 87th Cong., 
2d sess. 
S.Doc. 139, 87th Cong., 
2d sess. 
S.Doc. 146, 87th Cong., 
2d sess. 
S.Doc. 20, 89th Cong., 
1st sess. 
H.Doc. 102, 88th Cong., 
1st sess. 
S.Doc. 101, 90th Cong., 
2d sess. 
H.Doc. 369, 90th Cong., 
2d sess. 
H.Doc. 394, 91st Cong., 
2d sess. 
H.Doc. 585, 87th Cong., 
2d sess. 
H.Doc. 422, 91st Cong., 
2d sess. 
P.L. 99-662 17 November 1986 
99th Congress, 2nd sess. 
9-44

JACKSONVILLE, FLA. DISTRICT 
TABLE 9-C CANAVERAL HARBOR, FLA. PROJECT 
DATA RELATIVE TO LOCK 
(See Section 5 of Text) 
Distance to nearest town 9.9 miles via 12-foot barge canal and 
Intracoastal Waterway 
Name of nearest town Cocoa, Fla. 
Distance from Intracoastal Waterway 6.5 miles 
Lock Dimensions 909 wide; 6009 long' 
Lift Varies with tide 
Depth of sills (mlw, ocean) 14 feet 
Character of foundation Piles in sand 
Year completed and opened to navigation 1965 
Contract cost $2,979,592 
156 x 400 feet authorized. At request of NASA lock was constructed increased to 600 feet to be compatible with increased width. Oper- 
90 feet wide with NASA bearing additional cost ($700,000). Length ation and maintenance of lock is a Federal responsibility. 
TABLE 9-D CROSS-FLORIDA BARGE CANAL PROJECT 
LOCKS AND DAMS 
(See Section 8 of Text) 
Henry H. R. N. 
Buckman Eureka Lock Bert Dosh Dunnellon Inglis Lock 
Lock and Dam Lock Lock and Dam 
Nearest town Palatka, Sparr, Ocala, Dunnellon, Inglis, 
(miles) 11.2 15.8 8.9 2.5 3.2 
Miles from Atlantic 
Intracoastal 
Waterway 90.4 111.4 127.7 156.5 168.6 
Lock dimensions (ft.)' 84 x 600 84 x 600 84 x 600 84 x 600 84 x 600 
Normal lift (ft.) 20 20 0-152 12-272 28 
Depth over sills 
at normal pool levels: 
Upper (ft.) 14 17 16-312 16-312 18 
Lower (ft.) 15 14 16 18 15 
Character of Piles in Piles in Piles in Rock Rock 
foundation sand sand sand 
Kind of dam Movable Movable None None Movable 
Type const. Earth3 Earth3 - - Earth3 
Percent complete 100 100 0 0 100 
Estimated contract $6,094,000 $7,975,000 $7,430,000 $9,500,000 $7,800,000 
cost 
'Clear width and greatest available length. 
2Pool level varies with natural ground water profile from minimum 
elevation of 40 feet to maximum elevation of 55 feet. 
3With concrete spillway and movable gates. 
9-45

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
TABLE 9-E CROSSFLORIDA BARGE CANAL 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 8 of Text) 
Work Performed Cost 
Operation and Maintenance: 
Operations of locks, operations and maintenance of 
dams, spillways, reservoirs and bypasses, debris 
removal, performance monitoring system $ 566,811 
Buildings and grounds maintenance, 
trash removal, potable water testing 81,758 
Natural Resource Management 13,900 
Operation and maintenance of recreation facilities, 
sanitary facilities, service and maintenance of 
traffic counters and contract maintenance of grounds 245,278 
Condition and operations studies and periodic inspections 76,299 
Energy Conservation 3,219 
Water quality studies, data collection and processing, 
reimbursement to USGS, water control analysis, 
Lake Oklawaha and Inglis Bypass, and water 
management control 156,088 
Real Estate audits, inspections and outgrants 4,018 
OSHA medical exams 3,955 
Supervision and Administration 22,123 
Sub-Total 1,173,449 
Maintenance: 
Maintenance of dams and spillways and contract maintenance $ 1,255,188 
Maintenance of locks and lock repair contract 39,960 
Maintenance of roads, bridges 205 
Maintenance of Recreational Facilities 10,975 
Maintenance, Recreational Roads and Bridges 10,241 
SRUF 31,349 
Maintenance of permanent operating equipment (Recreation) 1,221 
Maintenance and purchase of non-recreational permanent 
operating equipment 196,964 
Bank stabilization-maintenance of slopes and berms, 
Rodman and Inglis dams, and bank 91,065 
stabilization contract 
Maintenance of canals, clearing and snagging 67,423 
Engineering and Design 27,147 
Supervision and Inspection 193,368 
Real Estate encroachments 3,186 
Sub-Total 1,928,292 
Income Credits 6,090 
Sub-Total 1,928,292 
Grand Total 3,095,651 
9-46

JACKSONVILLE, FLA. DISTRICT 
FOR FY 1988 
TABLE 9-F OKEECHOBEE WATERWAY 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 24 of Text) 
Work Performed Cost 
Operations and Maintenance: 
Operations: 
Operations of Locks, and Permance 
Monitoring System 773,810 
Contract maintenance buildings grounds, potable 
water testing, repair and replacement of project 
signs, operation and maintenance of District 
communications network 166,581 
Natural resource management 77,316 
Management of recreation areas and facilities 255,478 
Real estate management and energy conservation reports 32,759 
OSHA medical exams and inspections 6,609 
Condition and operation studies, periodic inspections 79,354 
Supervision and Administration 62,448 
Sub-Total 1,454,355 
Maintenance: 907,228 
Maintenance of locks and dams 
Real estate acquisitions, surveys, encroachments and 62,444 
monumentation 
Maintenance of Roads and levees and floodwalls 164,669 
Maintenance of recreational facilities, recreational 30,791 
permanent operating equipment, and recreation roads 
Maintenance of permanent operating equipment, 64,526 
non-recreational 
Channel and canal maintenance 53,532 
Engineering and Design 73,333 
Supervision and Inspection 158,076 
Sub-Total 1,514,659 
Income Credits 18,158 
Total 2,951,856 
9-47

TABLE 9-G REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS 
IN THE STATE OF FLORIDA 
CONTROL OPERATIONS 
(See Section 30 of Text) 
Locality Acres Controlled Cost 
St. John's River and tributaries and 
Withlacoohee, Kissimmee and Crystal Rivers 11,631 1,481,403 
Okeechobee Waterway and tributaries 5,443 855,060 
Acquisition and maintenance of airboats, - 131,300 
engines and work tools 
Income credits 
OSHA medical exams 
Engineering design - 181,833 
Supervision and Administration - 171,260 
Total 17,074 2,820,856 
TABLE 9-H NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND 
CONDITION SURVEYS ONLY WERE CONDUCTED DURING FISCAL YEAR 
(See Section 36 of Text) 
Date Cost Incurred 
Survey During 
Project Conducted Period 
AIWW, Jacksonville to Miami, Fla. 10-88 2,665 
AIWW, Norfolk to St. Johns River, Fla. 12-88 9,258 
Anclote River, Fla. 9-87 2,711 
Arecibo Harbor, P.R. 5-89 12,570 
Bakers Haulover Inlet, Fla. 6-89 383 
Channel, Naples to Big Marco, Fla. 6-86 1,254 
Clearwater Pass, Fla. 9-89 36,970 
Fort Myers Beach, Fla. 8-88 1,973 
Fort Pierce Harbor, Fla. 5-89 4,548 
Johns Pass, Fla. 10-89 28,991 
Longboat Pass, Fla. 10-89 23,592 
Mayaguez Harbor, P.R. 6-89 11,750 
Miami Harbor, Fla. 8-89 6,612 
Miami River, Fla. 1-89 9,035 
New Pass, Fla. 10-89 1,095 
Oklawaha River, Fla. 11-84 4,414 
*Palm Beach Harbor, Fla. 8-89 1,058 
Pass-A-Grille Pass, Fla. 2-89 200 
San Juan Harbor, P.R. 10-89 1,525 
St. Augustine Harbor, Fla. 6-89 1,250 
Withlacoochee River, Fla. 11-88 60,436 
*Port Everglades 5-89 2,372 
Total 224,662 
9-48

JACKSONVILLE, FLA. DISTRICT 
OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 37 of Text) 
For Last Cost to Sept. 30, 1988 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Anclote River, Fla. 1974 267,427 636,153 
Aquatic Plant Control, Fla. 
(R&H Acts of 1958 & 1962) 1968 2,619,7002- 
Atlantic Gulf Ship Canal, Fla. 1939 5,099,153- 
Bayport, Fla.3 1972 58,4954 - 
Cedar Keys Harbor, Fla. 1977 168,5696 76,023 
Christiansted Harbor, St. Croix, V.I.6 1964 303,317 57,800 
Clearwater Pass, Fla.21 1980 46,3497 1,257,241 
Courtenay Channel, Fla.' 1940 22,346 26,779 
Crystal River, Fla.' 1941 25,000 128,000 
Everglades Harbor, Fla.' 1964 221,5098 51,034 
Fajardo Harbor, P.R.8 1945 - - 
Guayanes Harbor, P.R.3 1945 
Gulf Intracoastal Waterway 
St. Marks to Tampa Bay, Fla.3 1974 38,850- 
Homosassa River, Fla.' 1937 3,9999 23,334 
Horseshoe Cove, Fla. 1977 347,521 161,864 
Hudson River, Fla.3 1974 9,889- 
Intracoastal Waterway, Miami to Key West, Fla.3 1963 243,079 28,046 
Key West Harbor, Fla.' 1972 1,548,89210 534,623 
Kissimmee River, Fla.' 1931 23,479 112,954 
Lake Crescent and Dunns Creek, Fla." 1931 10,276 9,035 
Largo Sound Channel, Fla. 1,12 1966 117,44313 51,149 
Little Manatee River, Fla.3, 11 1949 11,90314- 
Manatee River, Fla.'5 1970 123,350 194,516 
New River, Fla.' 1956 36,518 31,296 
Orange River, Fla.' 1962 2,000 24,918 
Ozona, Fla, channel and turning basin1 1963 105,527 15,089 
Palm Beach, Fla, side channel and basin3 1946 - - 
Pass-A-Grille Pass, Fla., 1, 16 1966 41,29717 60,468 
Pithlachascotee River, Fla. 1973 400,00018 261,401 
Rice Creek, Fla.' 1957 85,208'19 18,814 
St. Petersburg Harbor, Fla. 1983 255,60820 1,570,45921 
St. Thomas Harbor, V.I.3 1949 1,989- 
Steinhatchee River, Fla.' 1940 135,053 43,329 
Suwannee River, Fla.'5 1977 76,41822 219,261 
Withlacoochee River, Fla.15 1969 614,91223 431,187 
1. Complete. 
2. Excludes $918,205 contributed funds. 
3. Inactive. 
4. Includes $41,222 for reconnaissance and detailed project 
reports under Section 107 of the R&H Act of 1960. 
5. Includes $82,500 expended under previous project. Excludes 
$1,473 contributed funds. 
6. Project as modified by Chief of Engineers in report of June 
30, 1961, is complete. Previously authorized depth of 25 feet in 
inactive status. 
7. Excludes $42,783 contributed funds. 
8. Excludes $36,000 contributed funds. 
9. In addition, $1,000 expended from contributed funds. 
10. Includes $27,500 for new work under previous project. 
Excludes $35,371 contributed funds. 
11. Deauthorized by Public Law 93-251, Section 12. 
12. Authorized April 20, 1964 by Chief of Engineers under 
Section 107 of 1960 R&H Act. 
13. Includes $25,008 for detailed project report but excludes 
$86,716 expended from contributed funds. 
14. Expended on restudy. 
15. Inactive portion of project deauthorized by Public Law 
93251, Section 12. 
16. Authorized November 19, 1964 by Chief of Engineers under 
Sections 107 of R&H Act of 1960. 
17. Excludes $41,297 contributed funds. 
18. Excludes $215,728 contributed funds. 
19. Excludes $93,000 contributed funds. 
20. Includes $32,689 under previous project. 
21. Includes $20,532 under previous project. 
22. Includes $10,154 expended under previous project. 
23. Includes $30,000 expended under previous project. 
9-49 
TABLE 9-I

TABLE 9-J OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 46 of Text) 
For Last Cost to Sept. 30, 1988 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cape Florida State Park 1969 34,8621 
El Tuque Beach, Ponce, P.R. 1985 1,396,730 - 
Key West, Fla. 1963 96,3402 3,794 
Lee County, Fla. 1971 - - 
Lido Key, Fla. 1971 - - 
Mullet Key, Fla. 1973 436,2013 1,656 
Manatee County, Fla. 1983 217,600 - 
Punta Salinas, P.R. 1984 855,5114 - 
Palm Beach County, Fla., from Lake Worth Inlet to 
South Lake Worth Inlet 1970 195,1405 6,257 
San Juan, Puerto Rico 1965 - - 
Virginia Key and Key Biscayne, Fla. 1978 1,708,7386 1,022 
1. Includes $2,462 cost of reconnaissance and detailed project 4. Excludes $360,000 contributed funds. 
reports but excludes $13,818 contributed funds. 5. Excludes $781,188 in property or services furnished by local 
2. Excludes $192,168 contributed funds. interests in lieu of cash contribution. 
3. Excludes $187,133 contributed funds. 6. Excludes $825,771 contributed funds. 
TABLE 9-K CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF HURRICANE GATES 
(See Section 48 of Text) 
Depth Character 
Over of Year 
Gate' Nearest Town Distance Sills Founda- Corn- Actual 
No. Name (miles) (ft.) tion pleted Cost 
2. Clewiston, Fla. 0.5 10 Pile 1935 $309,748 
3. Lake Harbor, Fla. 0.5 10 Rock 1935 316,938 
4. Belle Glade, Fla. 4.0 10 Rock 1935 350,025 
5. Canal Point, Fla. 0.0 10 Rock 1935 262,465 
6. Okeechobee, Fla. 0.5 7 Pile 1936 373,273 
'All are 50 feet wide with available length unlimited. They are Gate No. 6 has an auxiliary culvert spillway with automatic conconstructed 
of concrete with steel sector gates and have no lift. trol. Moore Haven Lock serves as Hurricane Gate Structure 1. 
9-50

TABLE 9-L CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF LOCKS AND DAMS 
(See Section 48 of Text) 
Miles Elevation 
From Lock Normal of Normal Character Kind Kind 
Nearest Nearest Dimensions lift Pool Depth of of of of Percent Contract 
Town Town (ft.) (ft.) surface (ft.) sills (ft.) foundation Dam Construction Complete Cost 
W.P. Franklin At Olga 
Lock and Dam' 
S-65 Lock Frostpr 
S-65A Lock 
S-65B Lock 
S-65C Lock 
S-65D Lock 
S-65E Lock 
)of 
0 
23 
Avon Park 26 
Sebring 20 
Sebring 25 
Okeechobee 14 
Okeechobee 10 
Moore Haven Moore Haven 0.5 
Lock (HGS-1 
Mod.) 
S-310 Clewiston 0.5 
(HGS-2 Mod.) 
S-193 Okeechobee 0.5 
(HGS-6 Mod.) 
S0308B Pahokee 11 
(Port Mayaca) 
S-57 Ashton 9 
S-58 Ashton 5 
S-59 Kissimmee 6 
S-60 Ashton 6 
S-61 St. Cloud 6 
S-62 Ashton 10 
S-63 Ashton 12 
S-63A Ashton 14 
S-96 Sebastian 14 
S-96A Sebastian 16 
S-53 Eau Gallie 8 
S.-55 Christmas 12 
S-157 Sebastian 4 
S-158 Titusville 15 
56 x 400 2.5 3.0 14 Piles in Movable Reinforced 
clay concrete 
30 x 90 4.2 48.5-52.33 6 Earth None Reinforced 
foundation, concrete 
sand rigid frame 
30 x 90 6.3 46.3 6 Earth None Reinforced 
foundation, concrete 
sand rigid frame 
30 x 90 6.0 40.0 6 Earth None Reinforced 
foundation, concrete 
sand rigid frame 
30 x 90 7.2 34.0 6 Earth None Reinforced 
foundation, concrete 
sand rigid frame 
30 x 90 5.8 26.8 6 Earth None Reinforced 
foundation, concrete 
sand rigid frame 
30 x 90 4.6 21.0 6 Earth None Reinforced 
foundation, concrete 
sand 
50 x 250 9.4 15.5-17.53 11 Piles in None Steel sheet pile 
sand lockwalls 
50 x 60 
50 x 60 
56 x 400 
20 x 90 
20 x 90 
20 x 90 
20 x 90 
30 x 90 
20 x 90 
20 x 90 
20 x 90 
20 x 60 
20 x 60 
20 x 60 
20 x 60 
20 x 60 
20 x 60 
5.0 
7.5 
4.0 
1.0 
2.0 
3.0 
2.0 
2.0 
3.0 
5.0 
4.5 
4.0 
7.5 
3.5 
10.0 
20.0 
4.5 
15.5-17.53 
15.5-17.53 
15.5-17.53 
62.0 
64.0 
58.0 
64.0 
55.0 
61.0 
62.0 
57.0 
24.0 
25.0 
17.5 
14.0 
20.0 
4.0 
12.9 
7.5 
18
6
666 
6
6
6
666
66
66 
Slab on 
sand 
Piles in 
sand and 
slab on sand 
Slab on 
sand 
Earth 
foundation, 
sand 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
None 
None 
Fixed 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
None 
Reinforced 
concrete 
Reinforced 
concrete 
Reinforced 
concrete 
Concrete and 
steel sheet 
pile 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
100 $3,803,655.00 
100 $1,211,464,70 
100 $1,531,489.91 
100 $1,068,396.69 
100 $1,357,246.12 
100 $1,242,908.51 
100 $1,320,039.84 
0 $369,0002 
100
0 
100
0
00 
10 
100
0
0
0
00 
0
0
00 
$3,448,406 
$523,0002 
$8,308,700.00 
$2,004,0002 
$2,004,0002 
$2,000,0002 
$2,004,0002 
$689,217 
$2,004,0002 
$2,004,0002 
$1,962,0002 
$1,757,0002 
$1,672,0002 
$1,623,0002 
$1,664,0002 
$2,116,0002 
$1,913,0002 
1Operation and care of W.P. Franklin Lock and Dam (S-79) is a Federal responsibility. 3The normal pool level varies seasonally between the two elevations. 2Estimated (Oct. 1984). 
c
0
z
C
-1 
r
r
LT!J 
vM 
I 
r
d
y 
d 
n
y 
et

TABLE 9-M CENTRAL AND SOUTHERN FLORIDA PROJECT 
LOCAL COOPERATION 
(See Section 48 of Text) 
Flood Control Act Work Authorized Cash Contributions' 
June 30, 1948 First phase of comprehensive plan 15.0 
Sept. 3, 1954 Second phase of comprehensive plan 20.0 
July 14, 1960 Nicodemus Slough area 31.5 
Oct. 23, 1962 West Palm Beach Canal 12.8 
Boggy Creek Basin 29.7 
Shingle Creek Basin 25.9 
South Dade County area 19.2 
Reedy Creek Swamp 50.0 
Oct. 27, 1965 Southwest Dade County 46.0 
Hendry County area 19.5 
Aug. 13, 1968 Martin County 
Flood Control Features 34.0 
Irrigation Features 49.0 
Backflow Features 20.0 
PL 89-72 Recreation Features 50.0 
Water Resources - St. Lucie 20.0 
Recreation Features 50.0 
Approved Dec. 17, 1970 Navigation improvements suitable for 50.0 
under Provisions of recreational craft 
Section 201 of 1965 
Flood Control Act 
'Computed on total contract cost and supervision and 
administration except for Reedy Creek Swamp and Recreation 
Features which are computed on all costs, including engineering 
and design and land. 
9-52

TABLE 9-N CENTRAL AND SOUTHERN FLORIDA PROJECT 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 48 of Text) 
Work Performed Cost 
New Work: 
Construction of: 
Railroad bridges $ 0 
Channels and canals 0 
Levees 6,154,146 
Floodway control and diversion structures 6,512,829 
Pumping Plants 0 
Buildings, grounds and utilities 0 
Cultural Resource Preservation 12,354 
Equipment operation 0 
Depreciation 0 
Engineering and design 4,516,957 
Supervision and administration 1,657,330 
Total cost 18,833,616 
Operations: 
Operation of locks, dams, reservoirs and performance system 568,848 
Maintenance, buildings and grounds, operation of District 
communications network, repair and replacement of project signs 83,635 
Patrol, inspection, and maintenance of Herbert Hoover Dike, 
HGS 3, 4, and 5, operation and maintenance of drainage 
ditches, culverts and 16 spillways, and pumping costs 1,072,943 
Natural resource management 157,407 
Operation and Maintenance of recreation facilities, service 
and maintenance of traffic counters, master planning 221,010 
Condition and operation studies, periodic inspections, 
dam safety studies 63,300 
Water quality/water control studies, data collection, 
regulation of Lake Okeechobee and three conservation areas 933,135 
Energy conservation 2,153 
Real Estate outgranting 1,000 
OSHA Insps. 382 
Supervision and Administration 76,769 
Sub-Total 3,180,582 
Maintenance: 
Real Estate encroachments and boundary monumentation contract 246,113 
Maintenance of locks and dams 18,885 
Maintenance of non-recreational roads and bridges 
Repair and stabilization of Crown Road, Herbert Hoover Dike, 
removal of weeks, rebuilding and regrading of levee slopes, 
modification and maintenance of safety barriers, HGS 3, 4, and 5, 
cleaning landslide toe ditches, repair of culverts, replacement 
of fences, removal of trees, topping of trees, control of 
Melaleuca, replacement of rip rap on slopes and berms 449,142 
Maintenance of recreational facilities 36,451 
Maintenance of recreational roads and bridges 25,313 
Maintenance of recreational permit Op. Equip. 1,370 
Maintenance of hydrometrological network 21,119 
Maintenance and purchase of non-recreational permanent 
operating equipment 337,190 
Bank stabilization contract 133,662 
Non-dredging channel maintenance and debris removal 
Engineering and Design 89,796 
Supervision and Inspection 150,644 
Income credits 4,391 
Sub-Total 1,505,294 
Total 4,685,876 
Special recreation user fees 44,420 
9-53

TABLE 9-0 CENTRAL AND SOUTHERN FLORIDA PROJECT 
CONSTRUCTION COMPLETED UNDER EXISTING PROJECT DURING FISCAL YEAR 
(See Section 48 of Text) 
Date transferred to 
Flood Control District 
Construction for Operation and 
Feature Period Maintenance 
Channels and Canals: 
C-151 East End May 1982 - June 1987 
Structures: May 1982 - June 1987 
S-155 
TABLE 9-P CENTRAL AND SOUTHERN FLORIDA PROJECT 
STATUS OF WORK UNDER CONTRACT AT END OF FISCAL YEAR 
(See Section 48 of Text) 
Construction Approx.* 
Feature Started Complete 
Levees: 
Herbert Hoover Dike Revetment 
1st Contract (4 miles) March 1983 100 
3rd Contract February 1985 45 
4th Contract July 1985 98 
5th Contract August 1986 32 
6th Contract December 1986 100 
Structures: 
HGS-4 Replacement (S-351) January 1986 91 
HGS-5 Replacement (S-352) April 1987 88 
HGS-3 (S-354) August 1988 0 
TABLE 9-Q FOUR RIVER BASINS, FLORIDA PROJECT 
MOSS BLUFF LOCK 
(See Section 49 of Text) 
Nearest town 20 miles 
Name of nearest town Ocala, Fla. 
Distance above mouth of River 65.5 miles 
Lock dimensions 30 x 125 feet 
Normal lift 18.0 feet 
Elevation of normal pool surface 58 feet 
Depth of sills 12 feet 
Character of foundation Piles in sand 
Kind of dam None 
Type of construction Reinforced concrete 
Percent complete 100 
Estimated Cost (including dam and spillway) $1,990,138 
9-54

TABLE 9-R FOUR RIVER BASINS, FLORIDA PROJECT 
CONDITION AT END OF FISCAL YEAR 
(See Section 49 of Text) 
Date transferred to 
Construction Southwest Florida 
Feature Period for Operation and Maintenance 
Bridges: 
B-194 
Alteration of Facilities B-195 
B-594 
Alteration of Facilities B-196 
SCL RR Br., B-196 
Channels and Canals: 
C-135 
C-135, Sec. 1A 
C-135, Sec. 1B 
C-135, Sec. 1C & 2 
C-135, Sec. 3A 
C-135, Sec. 3B 
C-135, Sec. 4A 
C-136 
C-231, Phase I 
C-231, Phase II 
C-331 
C-531 
C-534 
C-135 
Structures: 
S-160 
S-161 
S-162 
S-353 
Moss Bluff Lock and Spillway 
S-551 
Levees: 
L-212, Sec. 1 
L-212, Sec. 2 
L-112 
L-112 & Floodway 
S-155 
S-163 
S-159 Middle & Lower 
S-159 Upper 
Recreation: 
Morris Bridge & 
Flint Creek Sites 
Dead River Sites 
July 1968 - Mar. 1970 
May 1971 - Jan. 1973 
Jan. 1973- Jan. 1974 
Oct. 1972 - Jan. 1975 
Dec. 1972 - July 1975 
May 1967- Dec. 1968 
July 1966- Aug. 1967 
May 1968- Sep. 1972 
Jan. 1971- Dec. 1973 
Dec. 1972- Apr. 1975 
Feb. 1975- Aug. 1977 
Apr. 1976-Jan. 1979 
Aug. 1975- May 1977 
July 1973- Apr. 1975 
July 1973- Jan. 1974 
July 1967- Sep. 1968 
Apr. 1966 - Jan. 1969 
June 1970 - July 1971 
March 1977 - Oct. 1980 
May 1967- Dec. 1968 
Aug. 1975- May 1977 
Apr. 1975 - June 1977 
July 1967- Sep. 1968 
Apr. 1967 - Mar. 1969 
July 1970- Feb. 1972 
June 1968 - July 1970 
July 1970- Sep. 1971 
March 1977- Oct. 1980 
May 1978 - July 1981 
May 1978 - July 1981 
May 1978 - July 1981 
April 1979 - Aug. 1981 
June 1979 - Sep. 1981 
December 1982 - August 1984 
March 1985- July 1986 
Not transferred 
Do. 
Do. 
Do. 
July 1975 
Dec. 1968 
Oct. 1967 
Not transferred 
Not transferred 
Oct. 1977 
Not transferred 
Not transferred 
Nov. 1977 
Dec. 1975 
Dec. 1975 
Sep. 1968 
Apr. 1969 
Nov. 1971 
Dec. 1968 
Nov. 1977 
Apr. 1977 
Nov. 1968 
Dec. 1975 
Not transferred 
Dec. 1975 
Dec. 1975 
Oct. 1980 
Jan. 1983 
Jan. 1983 
Jan. 1983 
Oct. 1981 
Jan. 1985 
Dec. 1986 
9-55

TABLE 9-S OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 52 of Text) 
For Last Cost to Sept. 30, 1985 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arch Creek, Dade County, Fla. 1960 $66,4851 
Biscayne Bay, Fla., Hurricane Protection2 1966 - - 
Hillsborough Bay, Fla.2 1969 - - 
Phillippi Creek Basin, Fla.2 1966 
1. Excludes $11,734 cost of preauthorization studies. Project 2. Deauthorized by Public Law 93-251, Section 12. 
was authorized February 20, 1959, by Chief of Engineers under 
Section 205 of the 1948 Flood Control Act as Modified by P.L. 
685, 84th Congress. 
TABLE 9-T FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
PURSUANT TO SECTION 205, PUBLIC LAW 685, 
(PREAUTHORIZATION) 
(See Section 53 of Text) 
Study Identification Period Costs 
Detailed Project Report: 
Alligator Creek Basin, CL Fla. $ 0 
Bear Creek, Adel, Ga. 0 
Crane Creek, Melbourne, Fla. 0 
Estate Mon Bijou, St. Croix, V.I. 37,082 
Ft. Clinch State Park, Fla. 0 
Lagrange Gut, Frederiksted, V.I. 7,454 
Manatee River, Manatee County, Fla. 0 
Naquabo River, P.R. 59,708 
Parceles Figueroa, P.R. 1,615 
Ponce Regional, P.R. 847 
Rio Anton Ruiz-Runta Santiago, P.R. 1,855 
Rio Cibuco, Vega Baja, P.R. 125,050 
Rio Descalabrada, Santa Isabel 29,317 
Rio Guamani, Guayana, P.R. 20,731 
Rio Manati, Barceloneta, P.R. 1,141 
Rio Niqua, Arroyo, P.R. 873 
Rio Tallaboa-Penuelas, P.R. 0 
Sabana Grande, P.R. 1,133,364 
Savan Gut, St. Thomas, V.I. 272,366 
Seminole Basin, Largo, Fla. 125 
Sion Farm, St. Croix, V.I. 0 
Sugar Creek, Valdosta, Ga. 0 
Turpentine Run, St. Thomas, V.I. 132,812 
Wares Creek, Bradenton, Fla. 5,445 
9-56

MOBILE, AL., DISTRICT * 
This district comprises a small portion of 
southeastern Tennessee, western Georgia, western 
Florida, all of Alabama south of Tennessee River 
Basin, eastern Mississippi, and a small portion of 
southeastern Louisiana embraced in drainage basins 
tributary to the Gulf of Mexico, west of Aucilla River 
Basin, to and including the Pascagoula River Basin. 
The Pear River Basin, Mississippi was included as 
part of the Mobile District until October 1, 1981, 
when responsibilities were transferred to Vicksburg 
District, Lower Mississippi Valley Division. A 
section of the Gulf Intracoastal Water from St. 
Marks, Florida, to Lake Borgne Light No. 29, 
Louisiana is also within Mobile District 
IMPROVEMENTS 
Navigation Page 
1. Apalachicola Bay, FL ................................ 10-3 
2. Aquatic Plant Control 
(R & H Act of 1965) .................................... 10-3 
3. Bayou Coden, AL ....................................... 10-3 
4. Bayou La Batre, AL..................................... 10-4 
5. Biloxi Harbor, MS ....................................... 10-4 
6. Black Warrior and Tombigbee 
Rivers, AL................................................... 10-5 
6A. Jackson Port, 
Vicinity of Jackson, AL ............................... 10-6 
6B. Oliver Lock and Dam 
(Replacement), AL...................................... 10-6 
7. Bon Secour River, AL.................................. 10-7 
8. Dauphin Island, AL...................................... 10-7 
9. Dog and Fowl Rivers, AL............................ 10-8 
10. East Pass Channel From Gulf of Mexico 
into Choctawhatchee Bay, FL...................... 10-8 
11. Fly Creek, Fairhope, AL .............................. 10-9 
12. Gulf Intracoastal Waterway between 
Apalachee Bay, FL and 
Mexican Border............................................ 10-9 
13. Gulfport Harbor, MS.................................. 10-10 
14. Mobile Harbor, AL ................................... 10-10 
15. Panama City Harbor, FL ......................... 10..-.1 1 
16. Pascagoula Harbor, MS.............................. 10-12 
17. Pensacola Harbor, FL................................. 10-12 
18. Perdido Pass Channel, AL ................ 10-13 
19. Tennessee-Tombigbee 
Waterway, AL and MS ............................. 10-13 
20. Deauthorized Projects ............................... 10-14 
21. Other Authorized 
Navigation Projects.................................... 10-14 
22. Navigation Work Under 
Special Authorization................................. 10-14 
23. Reconnaissance and 
Condition Surveys...................................... 10-14 
Page 
Beach Erosion Control 
24. Beach Erosion Control Projects 
Under Special Authorization...................... 10-14 
25. Other Authorized Beach Erosion 
Control Project ........................................... 10-15 
Flood Control 
26. County Line Road Bridge, 
Itawamba Co., MS .................................... 10-15 
27. Cribbs Mill Creek, 
Tuscaloosa, AL .......................................... 10-15 
28. Eslava Creek, Mobile, AL.......................... 10-15 
29. Gulf Breeze, 
Santa Rosa Co., FL ................................... 10-15 
30. Highway 39 Bridge, 
Gainesville, AL .......................................... 10-16 
31. Hintonville Road Bridge, 
Perry Co., M S............................................. 10-16 
32. Hurricane Creek, 
Prentiss Co., M S......................................... 10-16 
33. Leaf and Bowie Rivers, 
Hattiesburg, MS ........................................ 10-17 
34. Little Cove Creek, 
Glencoe, AL .............................................. 10-17 
35. Magby Creek, 
Columbus, MS .......................................... 10-17 
36. Mill Creek, Dalton, GA.............................. 10-18 
37. Murder Creek, Brewton, AL ...................... 10-18 
38. Okatibbee Lake, MS ................................. 10-18 
39. Raccoon Creek, 
Baconton, GA............................................. 10-19 
40. Sewerline Protection, 
Valley, M S ................................................ 10-19 
41. Sope Creek, 
M arietta, GA ............................................. 10-19 
42. Sowashee Creek, 
M eridan, M S ............................................. 10-20

REPORT OF THE SECRETARY OF THE ARMY, 1989 
Flood Control Page 
43. Tallahalla Creek, Laurel, MS .................. 10-20 
44. Threemile Creek, Mobile, AL.................. 10-20 
45. Tombigbee River 
(East Fork), MS & AL............................10-21 
46. Tombigbee River and 
Tributaries, MS & AL.............................. 10-21 
47 Upper Gordon Creek, 
Hattiesburg, MS ...................................... 10-21 
48. Village Creek, 
Birmingham, AL ...................................... 10-22 
49. Whorton's Bend Road, 
Etowah Co., AL ...................................... 10-22 
50. Flood Control Work 
Under Special Authorization.................... 10-23 
51. Inspection of Completed 
Flood Control Projects ............................. 10-23 
52. Other Authorized 
Flood Control Projects ............................. 10-23 
Multiple Purpose Projects Including Power 
53. Alabama-Coosa Rivers, AL & GA .......... 10-23 
53A. Carters Dam and Reservoir, GA ............. 10-24 
53B. Claiborne Lock and Dam, AL.................. 10-24 
53C. Coosa River, Montgomery to 
Gadsden, AL ............................................ 10-25 
53D. Millers Ferry Lock and 
Dam, AL ................................................. 10-25 
53E. Robert F. Henry Lock and Dam, AL ....... 10-25 
54. Allatoona Dam 
Coosa River Basin, GA ............................ 10-26 
Multiple Purpose Projects Includ. Power Page 
55. Apalachicola, Chattahoochee, and 
Flint Rivers, AL, FL & GA...................... 10-26 
55A. Buford Dam, 
Lake Sidney Lanier, GA..........................10-27 
55B. George W. Andrews Lock and 
Dam, AL & GA.......................................10-28 
55C. Jim Woodruff Lock and 
Dam, FL & GA ....................................... 10-28 
55D. Walter F. George Lock and 
Dam, AL & GA.......................................10-29 
55E. West Point Lake 
Chattahoochee River Basin, AL & GA.... 10-29 
56. Scheduling Flood Control 
Reservoir Operations...............................10-30 
57. Deauthorized Projects...............................10-30 
Miscellaneous 
58. Flood Control and Coastal 
Emergencies (FC&CE) ........................... 10-30 
59. National Emergency Preparedness 
Program (NEPP)......................................10-30 
60. Regulatory Functions Program................10-30 
General Investigations 
61. Surveys....................................................10-31 
62. Collection and Study of Basic Data ......... 10-31 
63. Advance Engineering and Design...........10-31 
64. Continuation of Planning 
and Engineering........................................ 10-32 
65. Rivers and Harbors 
Contributed Funds.................................... 10-32 
Tables 
Table 10-A 
Table 10-B 
Table 10-C 
Table 10-D 
Table 10-E 
Table 10-G 
Table 10-H 
Table 10-I 
Table 10-J 
Cost & Financial 
Statement ...................................... 10-33 
Authorizing Legislation...............10-39 
Other Authorized 
Navigation Projects ..................... 10-49 
Other Authorized Beach 
Control Erosion Control Project... 10-49 
Other Authorized Flood 
Control Projects............................10-50 
Deauthorized Projects..................10-50 
Navigation Work Under 
Special Authorization...................10-51 
Beach Erosion Control 
Project Under Special 
Authorization................................10-51 
Flood Control Work Under 
Special Authorization..................10-51 
Table 10-K 
Table 10-L 
Table 10-M 
Table 10-N 
Table 10-0 
Table 10-P 
Reconnaissance and Condition 
Surveys ......................................... 10-52 
Alabama-Coosa Rivers, AL and GA 
Development Proposed Under 
Existing Project...........................10-52 
Apalachicola, Chattahoochee, and Flint 
Rivers, Al, GA, and FL, Locks and 
Dams and Multiple-Purpose 
Development Included In 
Existing Projects...........................10-53 
Black Warrior and Tombigbee 
Rivers, AL....................................10-54 
Tennessee-Tombigbee Waterway, 
AL and MS .................................. 10-55 
Completed Flood Insurance Studies 
And Flood Hazard Information Reports 
For FY 1982 Thru FY 1989 ......... 10-56 
10-2

MOBILE, ALABAMA DISTRICT 
Navigation 
1. APALACHICOLA BAY, FL 
Location. The project is on the coast of northwest 
Florida 160 miles east of Pensacola Harbor. (See Coast 
and Geodetic Survey Chart 11401.) 
Previous project. For details, see page 1833, Annual 
Report for 1915, and page 689, Annual Report for 1938. 
Existing project. The authorized project provides for: 
(a) A channel 10 feet deep and 100 feet wide from the 10- 
foot depth in Apalachicola Bay, across St. George Island, 
to within 300 feet of the gulf shore, thence increasing 
uniformly in width to 200 feet at the shore and continuing 
with that width to the 10-foot depth in the Gulf of Mexico, 
with twin jetties extending from the dune line to the outer 
end of the channel; (b) an inner bar channel, 10 feet deep 
and 100 feet wide, in Apalachicola Bay; (c) a boat basin 
200 feet by 880 feet and nine feet deep at Apalachicola, 
Florida, with a connecting channel 9 feet deep and 80 feet 
wide through Scipio Creek to Apalachicola River, (d) a 
channel known as Link Channel, 10 feet deep and 150 feet 
wide, in Apalachicola Bay; (e) a channel generally parallel 
to the shore at Eastpoint, Florida, 6 feet deep, 100 feet 
wide, and about 6,000 feet long, and a connecting channel 
6 feet deep and 100 feet wide to water at the same depth in 
St. George Sound, with twin breakwaters on either side 
parallel to the shore and having a total length of 5,300 
feet; (f) a channel 10 feet deep and 100 feet wide through 
Bulkhead Shoals, connecting Apalachicola Bay with St. 
George Sound; and (g) a 6-foot by 100-foot channel about 
one mile long, generally parallel to the shore at Two Mile, 
Florida, with a 6-foot by 100-foot connecting channel to 
water of the same depth in Apalachicola Bay. Mean range 
of tide throughout this harbor is 1.6 feet. Extreme range, 
except during storms, is about three feet. Plane of reference 
is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Requirements have been fully complied 
with. 
Terminal facilities. Facilities consist of pile-and-timber 
wharves which are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Condition surveys and other miscellaneous 
costs amounted to $76,043. 
Condition at end of fiscal year. The existing project, 
authorized by the 1954 River and Harbor Act, was completed 
in 1959, including reimbursement to local interests 
for approved work, as authorized by the 1958 River and 
Harbor Act. Improvements at Two Mile except for 
modifications authorized in 1975 were completed in September 
1964. Construction of the breakwater and channel 
improvements authorized in 1975 at Two Mile was completed 
in September 1977. Construction of breakwaters at 
Eastpoint authorized in 1983 was completed in March 
1984. Total Federal cost under existing project as of September 
30, 1989 is $2,033,461 for new work and 
$3,766,330 for maintenance, a total of $5,799,791. 
2. AQUATIC PLANT CONTROL (RIVER 
AND HARBOR ACT OF 1965) 
Location. Navigable water, tributary streams, connecting 
channels and other allied waters in Mobile District. 
Existing project. The authorized project provides for 
management and control of water hyacinth, alligatorweed, 
Eurasian watermilfoil, hydrilla, and other obnoxious 
aquatic plant growths from navigable water, tributary 
streams, connecting channels, and other allied waters of 
the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of the most effective 
and economical control measures to be administered by 
the Chief of Engineers, under the direction of the 
Secretary of the Army, in cooperation with other Federal 
and State agencies. Research and planning cost prior to 
construction shall be borne fully by the United States. (See 
Table 10-B for authorizing legislation). 
Local cooperation. Local interests shall agree to hold 
and save the United States free from claims that may occur 
from control operations and to participate to the extent of 
50 percent of such operations. Requirements are being met 
in the state of Alabama by the Department of Conservation 
and NIatural Resources. 
Operations and results during fiscal year. Contract 
for field work with State of Alabama was $13,196 less 
than award. Water quality studies and overhead amounted 
to $5,793. 
Condition at end of fiscal year. Total Federal cost 
under the existing project as of September 30, 1989 is 
$634,524. Contributed funds for maintenance amount to 
$21,225. 
3. BAYOU CODEN, AL 
Location. The project is located in a small tidal stream 
on the southern coast of Mobile County, Alabama, emptying 
into Mississippi Sound about 7.6 miles northwest of 
10-3

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Cedar Point, the southern tip of western mainland shore of 
Mobile Bay. (See Coast and Geodetic Survey Chart 
11376.) 
Previous project. For details see Annual Report for 
1945, page 843. 
Existing project. The project provides for a channel 
eight feet deep by 60 feet wide extending from La Belle 
Avenue bridge south for about 3,000 feet through the 
bayou to Portersville Bay, thence eight feet deep by 100 
feet wide extending about 2.3 miles westward across 
Portersville Bay to connect with the Bayou La Batre channel, 
and a tumrning basin eight feet deep by 60 feet wide by 
100 feet long on the west side of the bayou channel about 
500 feet south of the La Belle Avenue bridge. Mean tidal 
range is 1.75 feet, and extreme, except during storms, is 
3.5 feet. Plane of reference is mean low water. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with fishing industry in 
this locality are adequate for existing commerce. A marina 
which will accommodate about 12 small recreational craft, 
and a slip with facilities for loading oyster shells are located 
near the mouth of the bayou, and are maintained by 
the Alabama Department of Conservation. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Pre-dredging cost totaled $39,999. Condition 
surveys cost $10,395. Water control management totaled 
$1,767. 
Condition at end of fiscal year. That portion of the 
project authorized prior to the 1969 modification was 
completed in 1956. Construction authorized in 1969 was 
initiated March 31, 1975 and completed March 26, 1976. 
Total Federal cost under existing project as of September 
30, 1989 is $330,701 for new -work and $806,612 for 
maintenance, a total of $1,137,313. Contributed funds expended 
for new work amount to $100,000 and $50,000 for 
maintenance. 
4. BAYOU LA BATRE, AL 
Location. Bayou La Batre is a tidal stream about 10 
miles long, emptying into Mississippi Sound on the 
southern coast of Mobile County, Al., about 10 miles. 
northwest of Cedar Point, the southern tip of the western 
mainland shore of Mobile Bay. (See Coast and Geodetic 
Survey Chart 11373.) 
Previous project. For details see Annual Report for 
1945, page 844. 
Existing project. The authorized project provides for a 
12-foot by 100-foot channel from the 12-foot depth in 
Mississippi Sound to a point about 2,800 feet south of the 
highway bridge, thence a channel 12 feet deep by 75 feet 
wide to the bridge, an overall distance of about 33,500 
feet, with the channel widened at a point 0.6 mile below 
the bridge to provide a turning basin 12 feet deep and 
about 2.6 acres in area. Mean tidal range is 1.75 feet, and 
extreme, except during storms, is 3.75 feet. Plane of reference 
is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Wooden wharves have been 
provided at seafood processing plants and public launching 
ramps are available. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Pre-dredging 
cost totaled $60,014. Condition surveys cost $31,560. 
Engineering and design and water control management 
cost $24,604. Supervision and administration and other 
miscellaneous costs total $3,237. 
Condition at end of fiscal year. The existing project 
was modified December 30, 1966 under the discretionary 
authority of the Chief of Engineers to include a turning 
basin. The project was completed in March 1967. Total 
Federal cost under existing project as of September 30, 
1989 is $311,095 for new work and $3,226,406 for maintenance, 
a total of $3,537,501. Contributed funds from 
local interests for new work amount to $10,500. 
5. BILOXI HARBOR, MS 
Location. The project is located on Mississippi Sound 
in southeastern Mississippi, 32 miles by water west of Pascagoula 
Harbor, Mississippi, and 14 miles east of Gulfport 
Harbor, Mississippi (See Coast and Geodetic Survey Chart 
11373.) 
Previous project. For details see page 584, Annual 
Report for 1962. 
Existing project. The authorized project provides for a 
continuous channel 12 feet deep, 150 feet wide and 23 
miles long from the Gulf Intracoastal Waterway through 
Mississippi Sound east of Deer Island, Biloxi Bay, Back 
Bay, Cranes Neck, and a land cut to Gulfport Lake, including 
a 500-foot by 2,600-foot basin in the lake, thence a 12- 
foot deep by 100-foot wide channel for about two miles 
westward from the west end of the lake, terminating in a 
300-foot by 500-foot basin; a 12-foot by 100-foot channel 
10-4

MOBILE, ALABAMA DISTRICT 
from the main channel in Big Lake to and up Bayou Bernard 
to the Air Force oil terminal at about mile 2.6; a 12- 
foot by 150-foot spur channel from the main channel in 
Biloxi Bay for about one mile, terminating in a 400-foot 
by 600-foot turning basin opposite Ott Bayou; continuation 
of maintenance of the 12- by 150-foot lateral channel 
westward about 2.2 miles to Biloxi's south waterfront; a 
10-foot by 150-foot channel from Mississippi Sound, passing 
west of Deer Island to a point where it connects to the 
12-foot by 150-foot lateral channel at Biloxi's south 
waterfront. Construction for the modifications lateral 
channel authorized by River and Harbor Act of Nov. 7, 
1966 was commenced in FY 1974 and completed in Feb. 
1975. Further modifications to the project were authorized 
by the Chief of Engineers on March 28, 1979, which 
provided for a channel 10 feet deep, 100 feet wide and 300 
feet long extending northward from the Biloxi Lateral 
Channel, and into a rectangular basin, approximately 300 
by 370 feet. This work was completed in April 1980. 
Cost of modification as authorized by the 1966 River 
and Harbor Act was $664,390. That portion of the project 
providing for an entrance channel 6 feet deep, 50 feet 
wide, and about 1,800 feet long into Old Fort Bayou, as 
authorized by the 1945 River and Harbor Act, is inactive. 
Estimated cost (1954) of this portion was $6,000. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of wooden piling-andtimber 
piers for small craft and fishing boats, a bulk 
gasoline terminal, several boat ways, and concrete 
products plant are available. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging removed 2,581,347 
cubic yards at a cost of $1,025,173. Condition surveys cost 
$150,525. Engineering and design, water control management, 
and miscellaneous costs totaled $93,195. 
Condition at end of fiscal year. The existing project, 
prior to the modification authorized in 1966, was commenced 
in 1931 and completed in 1962. The 1966 
modification was completed in FY 1975. The 1979 
modification was completed in FY 1980. Total Federal 
cost under existing project as of 30 September 1989 is 
$1,431,919 for new work and $9,666,563 for maintenance, 
a total of $11,098,482. Contributed funds for new work 
amount to $102,600. Contributed funds for maintenance 
amount to $238,640. 
6. BLACK WARRIOR AND 
TOMBIGBEE RIVERS, AL 
Location. Black Warrior River rises in nothern 
Alabama above Birmingham and flows generally southwesterly 
to unite with the Tombigbee River at Demopolis, 
Alabama. Thence the Tombigbee flows south, uniting with 
the Alabama River to form the Mobile River 45 miles 
above the head of Mobile Bay. Distance by water from 
Mobile to vicinity of Birmingham is about 415 miles. 
Previous project. For details see page 732, Annual 
Report for 1938. 
Existing project. The authorized project provides essentially 
for a channel 9 feet deep and 200 feet wide from 
the mouth of the Tombigbee River, 45 miles above 
Mobile, to the vicinity of Birmingham, via the Tombigbee 
and Black Warrior Rivers, to mile 430.4 on Sipsey Fork, 
mile 429.6 on Mulberry Fork and mile 407.8 on Locust 
Fork, and for maintenance by snagging of Mobile River 
above the mouth of Chickasaw Creek, a total waterway 
distance of about 408 miles. The total lift of 255 feet is accomplished 
by six locks and dams. The original construction 
program, consisting of 17 dams and 18 lifts, was 
completed in 1915. Replacement of the original structures 
with new locks and dams, under the modernization program 
is as follows: William Bacon Oliver replaced locks 
10, 11, and 12; Demopolis replaced locks 4, 5, 6, and 7; 
Armistead I. Selden replaced locks 8 and 9; Coffeeville 
(Jackson) replaced locks 1, 2, and 3; and Holt replaced 
locks 13, 14, 15, and 16. Thus, 16 of the original locks 
have been replaced by five new locks. Bankhead Lock and 
Dam (Lock 17) rehabilitation to replace the original 
double lift lock with a single lift lock was completed in 
1980. The Coffeeville Lock and Dam wildlife refuge, 
authorized in 1960, includes 4,250 acres within the reservoir 
area and along its boundaries. A replacement lock for 
the old Oliver Lock has been authorized and will be located 
2,300 feet downstream. The replacement lock will 
have dimensions of 110 feet by 600 feet. A fixed crest 
spillway will extend 815 feet across the river. Minimum 
provision will be provided to allow construction of a 
hydropower plant. (See Table 10-B for authorizing legislation.) 
Tidal influence extends upstream from Mobile 101.6 
miles to the old lock 1, where tidal effect is apparent only 
at low stages of the river. At Mobile the mean and extreme 
tidal ranges are 1.5 and 3.6 feet, respectively. These are at 
times slightly increased by the effect of winds. The 
greatest fluctuation of river stages is at Demopolis, Ala., 
the maximum being 59.7 feet. Maximum fluctuations at 
other points are 40 feet at lock 1,100.6 miles from Mobile; 
10-5

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
57.8 feet at Tuscaloosa, 346.1 miles from Mobile; 13 feet 
at Birmingport, 404.9 miles from Mobile; and 27 feet at 
Cordova, 424.3 miles from Mobile. Ordinary fluctuations 
at these points are at old lock 1, 20 feet; at Demopolis, 35 
feet; at Tuscaloosa, 40 feet; at Birmingport, four feet; and 
at Cordova, seven feet. Works of improvement reduced 
the amount of fluctuations at different points by three to 10 
feet. 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Docks, storage facilities, and handling 
equipment have been provided as required at most 
loading and unloading points along the waterway. These 
include facilities for handling petroleum and petroleum 
products, coal, ores, sand and gravel, pulpwood, manufactures, 
and various other commodities. While most terminal 
facilities are privately owned, many are available for use 
by the general public. Facilities are considered adequate 
for existing commerce. (See Table 10-N for existing locks 
and dams.) 
Operations and results during fiscal year. 
New work: None. 
Maintenance: Contract dredging of the river system 
removed 1,037,184 cubic yards of material at a cost of 
$2,465,400. Condition surveys costs $659,400. Engineering 
and design cost $987,100. Supervision, administration 
and other general charges for the overall river project totaled 
$2,347,054. Recreation and resource management 
cost $2,592,200. Recreation attendance CY 1988 totaled 
6,496,372 user days. 
Other maintenance costs for the system include: Coffeeville 
Lock and Dam, $1,821,100; Demopolis Lock and 
Dam, $596,100; Selden Lock and Dam, $645,300; Oliver 
Lock and Dam, $378,900; Bankhead Lock and Dam, 
$935,700; Holt Lock and Dam, $553,900. 
Condition at end of fiscal year. Work on the project, 
commenced in 1887, was essentially completed in 1915. 
Since then three of the original locks and dams (10, 11 and 
12) were replaced by William Bacon Oliver (Tuscaloosa) 
Lock and Dam which was opened to navigation in August 
1939; four original lock and dams (4, 5, 6 and 7) were 
replaced by Demopolis Lock and Dam which was opened 
to navigation in August 1954; two original locks and dams 
(8 and 9) were replaced by Warrior Lock and Dam which 
was opened to navigation in October 1957; three original 
locks and d1ams (1, 2 and 3) were replaced by Coffeeville 
Lock and Dam which was opened to navigation in August 
1960; and four original locks and dams (13, 14, 15 and 16) 
were replaced by Holt Lock and Dam which was opened 
to navigation in June 1966. Rehabilitation of the spillway 
at John Hollis Bankhead Lock and Dam commenced in 
1966, and physically completed February 6, 1970. Replacement 
of the double lift lock with a single lift lock at 
John Hollis Bankhead Lock and Dam commenced in April 
1970 and was completed in 1980. The cost to September 
30, 1989 for replacement of the lock was $52,292,880. 
The power plant at John Hollis Bankhead Lock and Dam 
was built and is operated by the Alabama Power Co. Engineering 
and design and land acquisition for the new 
Oliver Lock and Dam are complete. Project construction 
began in November 1986 and is scheduled for completion 
in 1992. Total Federal cost under existing project as of 
September 30, 1989 is $88,461,935 for new work and 
$220,234,873 for maintenance, and $52,292,880 for major 
rehabilitation, a total of $360,989,688. 
6A. JACKSON PORT, JACKSON, AL 
Location. The project is located on the Tombigbee 
River in Clarke County in southwest Alabama in the city 
of Jackson, Alabama, approximately 90 miles north of 
Mobile, Alabama. 
Existing project. None. The authorized Port would be 
located on the Black Warrior-Tombigbee River System, 
which is a federally authorized 9 x 200 feet navigation 
project connecting Birmingham, Alabama with the Port of 
Mobile. In conjunction with the realignment project on the 
existing navigation project, the plan is to construct a spur 
canal 9 feet deep, 290 feet wide, and 680 feet long. 
Local cooperation. Local Cooperation Agreement is 
scheduled for execution in December 1989. 
Operation and results during fiscal year. New work: 
Engineering and design $59,078; and supervision and administration 
$8,459. A total Federal cost of $67,537 for 
new work. 
Condition at end of fiscal year. No feasible project 
could be found that warranted Federal participation. However, 
the report is being modified to show impacts of the 
new channel realignment proposed in the GDM. Studies 
under the project authority will continue until all project 
feasibility can be satisfied. Total Federal cost under existing 
project to September 30, 1989 is $147, 026. 
6B. OLIVER LOCK AND DAM 
(REPLACEMENT), AL 
Location. The project is located at mile 338.1 on the 
Black Warrior-Tombigbee River System at Tuscaloosa, 
Alabama. The Black Warrior-Tombigbee River System 
10-6

MOBILE, ALABAMA DISTRICT 
extends 429 miles north from Mobile to the vicinity of 
Birmingham, Alabama. 
Existing project. The existing authorized channel is 9 x 
200 feet and there are six (6) locks having a total lift of 
255 feet. Five (5) of the locks have chamber dimensions of 
110 x 600 feet while Oliver Lock has dimensions of 95 x 
460 feet. Original work on the waterway was authorized 
by the River and Harbor Act of 1884. The 17 original 
locks have been replaced by the existing six (6) locks with 
Oliver Lock being the first of the replacements completed 
in 1940. 
Plan of improvement is to replace the existing Oliver 
Lock with a lock located 2,300 feet downstream. The replacement 
lock will have dimensions of 110 x 600 feet. A 
fixed-crest spillway will extend 800 feet across the river. 
Minimum provisions will be provided to allow construction 
of a hydropower plant. Land acquisition is complete. 
Construction was initiated in November 1986 with the 
award of the Alabama Power Company relocation contract. 
The first stage cofferdam and river diversion contract 
was awarded in February 1987. For other information 
see description of Black Warrior and Tombigbee Rivers 
project. 
Local cooperation. A local cooperation agreement is not 
required. One-half of the total cost of construction of the 
navigation lock and dam will be paid by amounts appropriated 
from the Inland Waterways Trust Fund. 
Operation and results during fiscal year. New Work: 
Minor real estate cost $7,244; construction contracts 
$10,638,218; engineering and design $262,825; and 
$1,114,439 for supervision and administration and miscellaneous 
expenditures. A total Federal cost of $4,150,000 
for new work. Contributed funds expended in FY 1989 totaled 
$11,988,032. 
Condition at end of fiscal year. River Diversion and the 
Phase I Cofferdam have been completed. Excavation was 
completed and concrete placement began in March 1989. 
Concrete placement is continuing and the first monolith 
reached its final elevation in November 1989. Concrete 
placement will be completed in the lock chamber during 
the summer of 1990. Scheduled completion date is 
December 1992 with an estimated cost of $111,000,000. 
Total Federal (Corps of Engineers) cost under existing 
project to September 30, 1989 is $29,550,360 for new 
work. Contributed funds (Inland Waterways Trust) expended 
total $30,761,808. 
7. BON SECOUR RIVER, AL 
Location. Rises 2 miles south of Foley, Ala., and flows 
southerly about 8 miles, emptying into Bon Secour Bay, 
an arm of Mobile Bay in southwest Alabama. 
Existing project. A 10- by 80-foot channel from Gulf 
Intracoastal Waterway through Bon Secour Bay to mouth 
of Bon Secour River and extending up river to vicinity of 
Swifts Landing, thence 6 by 8 feet up river to a point about 
600 feet above Oak Landing with two turning and 
maneuvering areas 150 feet wide and 1,100 to 1,200 feet 
long opposite Swifts Landing and ice loading dock. Plane 
of reference is mean low water. Overall length of improvement 
is about 4.7 miles. Mean tidal range is about 1.5 feet 
and extreme, except during storms, is 3.5 feet. Existing 
project was authorized by Chief of Engineers, May 16, 
1963, under authority in Section 107, River and Harbor 
Act of 1960. 
Local cooperation. Fully complied with. 
Terminal facilities. A number of pile-and-timber marginal 
wharves used by the seafood industry and a marine 
ways are located along the existing project. These, 
together with numerous privately owned piers, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys and supervision and administration 
cost $93,934. 
Condition at end of fiscal year. Project was commenced 
in July and completed in October 1964. Total 
Federal cost under existing project as of September 30, 
1989 is $118,615 for new work and $383,453 for maintenance, 
a total of $502,068. Contributed funds for new 
work amounted to $9,700. 
8. DAUPHIN ISLAND BAY, AL 
Location. The project is located between Dauphin and 
Little Dauphin Island on the west side of the entrance to 
Mobile Bay, about 30 miles south of Mobile, Alabama and 
55 miles west of Pensacola, Florida. (See Coast and 
Geodetic Survey Chart 11376.) 
Existing project. The authorized project provides for* 
(a) A channel seven feet deep and 150 feet wide from 
Mobile Bay to an anchorage basin of the same depth, and 
about seven acres in area, in the marsh just north of Fort 
Gaines on Dauphin Island; a channel four feet deep and 40 
feet wide from the anchorage basin to Dauphin Island 
Bay; and a jetty and revetment to protect the entrance 
channel; and (b) an anchorage basin seven feet deep and 
10-7

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
500 feet square at Dauphin Island Village, with an 
entrance channel of like depth, 100 feet wide and about 
8,300 feet long, extending to the 7-foot hydrographic contour 
in Mississippi Sound. Mean tidal range is 1.1 feet, and 
extreme, except during storms is about four feet. Plane of 
reference is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Several privately-owned wharves 
for handling seafood, a public dock and mooring slip, and 
a pier for recreational craft are located on the village basin. 
A marina, public launching ramp, and a number of private 
piers are located on the bay. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. New 
Work: Engineering and designs $28,634; supervision and 
administration $4,358. 
Maintenance: Condition surveys cost $9,240. Water 
control management and other miscellaneous costs 
amounted to $67,947. Contract dredging removed 150,000 
cubic yards at a cost of $221,513. 
Condition at end of fiscal year. The project was completed 
in July 1959. Total Federal cost under existing 
project as of September 30, 1989 is $327,949 for new 
work and $1,733,643 for maintenance, a total of 
$2,061,592. 
9. DOG AND FOWL RIVERS, AL 
Location. Dog and Fowl Rivers are primarily tidal 
streams emptying into the west side of Mobile Bay, 8.5 
and 17 miles, respectively, south of central Mobile (See 
Coast and Geodetic Survey Chart 11376.) 
Existing project. The Dog River project provides for a 
7 by 100-foot channel to provide access to the Mobile ship 
channel. The total length to be dredged is 3,300 feet. 
The Fowl River project provides for a channel eight feet 
deep and 100 feet wide from Mobile Bay into and up Fowl 
River to deep water about 6,700 feet above its mouth. 
Total length of the channel is about 2.6 miles. Plane of reference 
is mean low water. Mean range of tide is about 1.5 
feet in Dog River. Extreme range during storms is about 
3.6 feet. This segment of the project was completed in 
November, 1973. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Existing facilities consist of a 
boatyard for fabricating steel vessel hulls, nine marinas, 
four marine ways, a yacht basin on Dog River, two 
marinas on Fowl River, and numerous timber piers and 
docks on both rivers. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. New work: 
Cost to complete contract dredging of the Dog River 
Channel to specifications was $11,851. 
Maintenance: Condition surveys and water control 
management cost $10,606. Supervision and administration 
and miscellaneous costs total $4,681. 
Condition at end of fiscal year. The existing Fowl 
River portion of the project was commenced in August 
1973 and completed in November 1973. Work on the Dog 
River channel was initiated and completed during FY 
1986. Total Federal cost on the existing project as of September 
30, 1989 is $2,003,783; $11,851 for new work and 
$1,991,932 for maintenance. Contributed funds for new 
work amounted to $195,250. 
10. EAST PASS CHANNEL FROM 
GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL 
Location. East Pass Channel is located in the entrance 
from the Gulf into Choctawhatchee Bay at eastern end of 
Santa Rosa Island, 48 miles east of the entrance into Pensacola 
Bay and 49 miles west of the new entrance to St. 
Andrews Bay. (See Coast and Geodetic Survey Chart 
11388.) 
Previous project. For details see page 672 of Annual 
Report for 1937. 
Existing project. The authorized project provides for a 
12-foot by 180-foot channel from the Gulf of Mexico into 
Choctawhatchee Bay, and a 6-foot by 10-foot channel 
from East Pass Channel into Old Pass Lagoon. The project 
consists also of two converging jetties spaced 1,000 feet 
apart at the seaward end. Mean range of tide is 1.3 feet; 
extreme range, except during storms, is 2.5 feet. Plane of 
reference is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been complied with to date. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with the fishing industry in 
this locality are considered adequate for existing commerce. 
10-8

MOBILE, ALABAMA DISTRICT 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $58,028. Supervision and 
administration and miscellaneous costs totaled $43,293. 
Condition at end of fiscal year. Construction of the 
1965 modification was commenced October 1967 and 
completed January 1969. Total Federal cost under existing 
project as of September 30, 1989 is $916,715 for new 
work and $7,607,517 for maintenance, a total of 
$8,524,232. Contributed funds for new work from local 
interests amount to $398,000. 
11. FLY CREEK, AL 
Location. Fly Creek (Volanta Bayou) is a small stream 
about 4.5 miles long rising in Baldwin County, Ala., 3 
miles east of town of Fairhope, from whence it flows northerly, 
thence westerly and southerly, to form an estuary 
on eastern shore of Mobile Bay just north of Fairhope and 
about 13 miles southeast of Mobile, Ala. (See U.S. Coast 
and Geodetic Survey Chart No. 11376.) 
Existing project. Provides for a channel 6 feet deep, 80 
feet wide, and about 1,650 feet long from 6-foot depth in 
Mobile Bay to a turning basin of same depth, 100 feet 
wide and 350 feet long, in Fly Creek. Mean tidal range in 
vicinity of project is about 1.3 feet, and extreme, except 
during storms, is 3.5 feet. 
Existing project was authorized by the River and Harbor 
Act of May 17, 1950, (H. Doc. 194, 81st Cong., 1st 
Sess.). The project document contains the latest published 
map. 
Local cooperation. Fully complied with. 
Terminal facilities. Fairhope Yacht Club has facilities 
for small recreational craft on both banks near mouth of 
creek, consisting of a small pile-and-timber service wharf, 
several sheet metal boat sheds, boat slips, and other mooring 
facilities. There is also a marginal timber wharf and 
shed for commercial fishing boats on right-bank of creek 
immediately above first bend. 
Operations and results during fiscal year. Maintenance: 
Environmental studies cost $31,843. Supervision 
and administration and miscellaneous costs totaled $8,008. 
Condition at end of fiscal year. Project was commenced 
in August and completed in October, 1957. Total 
project costs as of September 30, 1989 amounted to 
$502,033 of which $29,000 was for new work and 
$473,033 for maintenance. 
12. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FL 
AND MEXICAN BORDER 
(MOBILE DISTRICT) 
Location. The project extends westward from 
Apalachee Bay, Florida, along the Gulf coast to the 
Rigolets, Louisiana, via a series of coastal lakes, bays, 
sounds, and land cuts. (For further details see Annual 
Report for 1962.) 
Previous project. For details see page 906, Annual 
Report for 1930. 
Existing project. The authorized project provides for a 
waterway 12 feet deep and 125 feet wide at mean low 
water from Apalachee Bay, Florida, to Mobile Bay, 
Alabama, and 12 feet deep and 150 feet wide from Mobile 
Bay, Alabama to Rigolets, Louisiana (Lake Borgne Light 
No. 29), and for a tributary channel (Gulf County Canal), 
12 feet deep, 125 feet wide and about six miles long connecting 
Intracoastal Waterway at White City, Florida, with 
St. Joseph Bay. The waterway between the 12-foot depth 
contours in Apalachee Bay and Lake Borgne Light No. 29 
at the Rigolets is 379 miles long. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been fully complied with. 
Terminal facilities. Facilities are available for public 
use at Carrabelle, Apalachicola, Panama City, and Pensacola, 
Florida; Mobile and Bayou LaBatre, Alabama; and 
Pascagoula, Biloxi, Gulfport, Pass Christain, and Bay St. 
Louis, Mississippi. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: 
Carrabelle-Apalachicola Bay section: Contract dredging 
removed 685,754 cubic yards of material at a cost of 
$358,000. Condition surveys, water control management 
and miscellaneous costs totaled $170,900. 
Apalachicola Bay - St. Andrew Bay section: Contract 
dredging removed 90,000 cubic yards of material at a cost 
of $130,406. Condition surveys cost $62,000. Routine 
maintenance of channels cost $38,100. Miscellaneous 
costs totaled $24,100. 
10-9

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
St. Andrew Bay - Choctawhatchee Bay section: Bank 
stabilization cost $586,900. Condition surveys cost 
$62,100. Dredged material disposal facility maintenance 
cost $158,400. Supervision, administration and miscellaneous 
costs totaled $268,800. 
Choctawhatchee Bay - Pensacola Bay section: Condition 
surveys cost $20,800. Water control management and 
miscellaneous costs totaled $1,200. 
Pensacola Bay - Mobile Bay section: Condition surveys 
cost $68,400. Miscellaneous costs totaled $102,300. 
Mobile Bay - Rigolets section: Condition surveys, 
water control management, supervision and administration 
costs totaled $56,200. 
Condition surveys, water control management and miscellaneous 
cost pertaining to the waterway in general and 
not site specific totaled $258,600. Direct charges to 
Mobile Area Office for supervision and administration 
were $170,600 and to Panama Area Office totaled 
$89,300. 
Condition at end of fiscal year. The existing project is 
complete except for the portion between Apalachicola Bay 
and St. Marks, Florida, which has been deauthorized. 
Modification of the Gulf County Canal to provide a 12- 
foot by 125-foot channel was commenced July 1968 and 
completed June 1969. Total cost of the existing project to 
September 30, 1989 is $62,758,271, of which $6,480,299 
was for new work and $56,277,972 for maintenance. 
13. GULFPORT HARBOR, MS 
Location. The project is located on Mississippi Sound 
in southeastern Mississippi, about 35 miles west of Pascagoula, 
Mississippi, and 60 miles east of New Orleans. 
(See Coast and Geodetic Survey Chart 11373.) 
Previous project. For details see page 747, Annual 
Report for 1938, and page 995, Annual Report for 1948. 
Existing project. The authorized project provides for: 
(a) A channel 32 feet deep, 300 feet wide, and about eight 
miles long across Ship Island Bar, a channel 30 feet deep, 
220 feet wide, and about 11 miles long through Mississippi 
Sound, and an anchorage basin at Gulfport 30 feet deep, 
1,320 feet wide, and 2,640 feet long; and (b) maintenance 
of the existing commercial smallboat harbor about 26 
acres in area, and a straight-approach channel, 100 feet 
wide and about 4,300 feet long, from deep water in Mississippi 
Sound to a smallboat basin, all at a depth of eight 
feet. Under ordinary conditions mean tidal range is about 
1.75 feet, and extreme range, except during storms, is 
about 3.5 feet. Plane of reference is mean low water. It is 
proposed to modify the existing ship channel to 36 x 300 
feet in Mississippi Sound, and 38 x 400 feet across the bar, 
with changes in the channel alignment and the entrance to 
the anchorage basin for safe and unrestricted navigation. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Conditions of local cooperation 
have been fully complied with to date. 
Terminal facilities. Existing modem rail-cooperation 
terminal facilities at this port are considered adequate for 
existing commerce. (See Port Series 19, revised in 1979.) 
Operations and results during fiscal year. New work: 
Engineering and Design for Gulfport Harbor cost $3,540. 
Maintenance: Contract dredging removed a total of 
470,000 cubic yards of material at a cost of $163,500. 
Condition surveys cost $136,500. Supervision and administration 
and miscellaneous costs amounted to 
$115,393. ' 
Condition at end of fiscal year. The main harbor was 
commenced 1932 and completed April 1950. Maintenance 
for small boat harbor and approach channel, constructed 
by local interests in 1950, was authorized by 1958 River 
and Harbor Act. Total Federal cost under existing project 
as of September 30, 1989 is $969,000 for new work and 
$35,801,954 for maintenance, a total of $36,770,954. 
14. MOBILE HARBOR, AL 
Location. The project is located along the lower five 
miles of Mobile River, in southwestern Alabama, 91 miles 
by water west of Pensacola Harbor, Florida, 90 miles east 
of Gulfport Harbor, Mississippi, and 144 by water northeast 
of mouth of Mississippi River. (See Coast and 
Geodetic Survey Chart 11376.) 
Previous project. For details see page 503, Annual 
Report for 1963. 
Existing project. The authorized project provides for: 
(a) A 42-foot by 600-foot channel about 1.5 miles long 
across Mobile Bar, (b) a 40-foot by 400-foot channel in 
Mobile Bay to mouth of Mobile River, (c) a 40-foot channel 
in Mobile River to highway bridge, varying from 500 
to 775 feet wide; (d) a 25-foot channel from highway 
bridge to and up Chickasaw Creek to a point 400 feet 
south of mouth of Shell Bayou, widths being 500 feet in 
Mobile River and 250 feet in Chickasaw Creek; (e) a turning 
basin 40 feet deep, 2,500 feet long, and 800 to 1,000 
feet wide, opposite Alabama State Docks; (f) a turning 
basin 40 feet deep, 1,000 feet wide, and 1,600 feet long 
opposite Magazine Point; (g) a 27-foot by 150-foot chan- 
10-10

MOBILE, ALABAMA DISTRICT 
nel from Mobile Bay Channel along Arlington pier to a 
turning basin 800 feet long and 600 feet wide opposite 
Brookley Complex ocean terminal, and continuing thence 
a turning basin 250 feet wide and 800 feet long in Garrows 
Bend, thence a 22-foot by 150-foot channel to the 
causeway linking McDuffie Island to the mainland; (h) a 
channel 40 feet deep and 400 feet wide from the main ship 
channel in Mobile Bay and extending northwesterly for 
about 5.3 miles to the shore of Mobile Bay, including an 
anchorage basin near the shoreline, thence a land cut 40 
feet deep, 300 feet wide and 1.9 miles long to and including 
a 42 acre trapezoid turning basin 40 feet deep, and a 
barge channel 12-by 100-feet, extending 6500 feet and terminating 
in a 300-by 300-foot turning basin; and (i) maintenance 
of Three Mile Creek by snagging, from its 
intersection with Industrial Canal to Mobile River. The 
project provides also for an anchorage area 32 feet deep, 
100 feet wide, and 2,000 feet long opposite site formerly 
occupied by the U.S. Quarantine Station at McDuffle 
(Sand) Island. Prior to widening the Mobile Bay Channel 
as authorized in 1954, the Quarantine Station anchorage 
area was maintained to a project width of 200 feet. Construction 
by local interests of a solid-fill causeway across 
Garrows Bend Channel between McDuffie Island and the 
mainland is also provided for under existing project. Total 
length of the bay and river channels is about 41.7 miles. 
Plane of reference is mean low water. Under ordinary conditions 
mean tidal range at the lower end of the improvement 
is 1.2 feet and at the upper end 1.5 feet. Extreme 
tidal range is 3.4 feet at the lower end and 3.6 feet at the 
upper end. Further authorization provides for future 
development to deepen and widen entrance channel over 
the bar to 57 feet by 700 feet about 7.4 miles long, deepen 
and widen bay channel to 55 feet by 550 feet about 27.0 
miles long, deepen and widen an additional 4.2 miles of 
bay channel to 55 feet by 650 feet and provide 55 foot 
deep anchorage area and turning basin in vicinity of Little 
Sand Island. All dredged material will be placed in an approved 
disposal area in the Gulf of Mexico. (See Table 10- 
B for authorizing legislation.) Although the authorized 
project is for the construction of a 55 foot by 550 foot 
channel, the plan of improvement, which is currently 
under construction, consists of deepening the entrance 
channel from 42 feet to 47 feet for a distance of 6.1 miles 
from the Gulf of Mexico to Mobile Bay; and deepening 
the bay channel from 40 feet to 45 feet from the mouth of 
the bay north for a distance of 31.2 miles to the McDuffie 
Coal Terminal. Completion of this project element is 
scheduled for June 1990. 
Local cooperation. A local cooperation agreement was 
signed by the local sponsor to construct the project in increments. 
The first increment is described above. 
Terminal facilities. Modemrn rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 18, revised in 1979.) 
Operations and results during fiscal year. New work: 
Construction contract cost $13,960,266, engineering and 
design $83,808, and supervision and administration cost 
$251,497 
Maintenance: Contract dredging removed 11,000,000 
cubic yards of material from Mobile Harbor and Theodore 
ship channel at a cost of $2,424,813. Condition surveys 
cost $1,038,417. Dredged material disposal facility construction 
cost $1,655,549 and disposal facility maintenance 
cost $444,107. Water control management, 
engineering and design and supervision and administration 
cost $583,636. 
Condition at end of fiscal year. The existing project 
was commenced in 1931 and completed in July 1965 except 
for the Theodore Channel portion, which was essentially 
completed in August 1981. For details see Annual 
Report for 1965. Current estimated Federal cost is 
$258,550,000, and non-Federal cash contributions is 
$221,450,000. Total Federal cost under existing project as 
of September 30, 1989 is $90,103,445 for new work and 
$100,407,099 for maintenance, a total of $190,510,544. 
Contributed funds expended amounted to $16,851,076 for 
new work. 
15. PANAMA CITY HARBOR, FL 
Location. The project is located on the northwest coast 
of Florida, 102 miles east of entrance to Pensacola Harbor. 
(See Coast and Geodetic Survey Chart 11389.) 
Previous project. For details see page 710, Annual 
Report for 1938. 
Existing project. The authorized project (as modified) 
provides for a channel about 3.7 miles long extending 
from deep water in St. Andrew Bay to the Gulf of Mexico, 
300 feet wide and 40 feet deep in the bay and 450 feet 
wide, 42 feet deep and about 1.1 miles long in the approach 
channel in the Gulf, protected by two jetties, each 
about 700 feet long; branch channels 38 feet deep and 300 
feet wide, leading from the inner end of the main entrance 
channel westward to the Port Authority terminal at Dyers 
Point and eastward to the Bay Harbor terminal, about 3.4 
and 3.6 miles in length, respectively; turning and 
maneuvering areas comprising about 55 acres opposite 
Dyers Point, and 42 acres opposite Bay Harbor, both at a 
depth of 38 feet; and an anchoring and loading basin for 
LASH type intermodal carriers, 40 feet deep and contain- 
10-11

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
ing about 177 acres in St. Andrew Bay near the inner end 
of the main entrance channel; a channel in Watson Bayou, 
100 feet wide and 10 feet deep from that depth in St. 
Andrew Bay to the highway bridge, about 1.75 miles; 
channel 100 feet wide and 8 feet deep in Grand Lagoon to 
a point about 2,400 feet east of State Highway 392 Bridge, 
with branches to serve terminal facilities. The east and 
west jetties have been reworked and are presently about 
2,075 and 2,896 feet long, respectively. Mean tidal range 
is about normally 1.3 feet and 3.0 feet extreme. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Available terminal facilities are 
considered adequate for existing commerce. (See Port 
Series No. 19.) 
Operations and results during fiscal year. New 
work: None. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $40,946. Engineering and 
design, water control management, and miscellaneous 
costs totaled $53,478. 
Condition at end of fiscal year. The existing project 
(prior to modifications) was completed in November 1949. 
Repairs to jetties were commenced in June 1961 and completed 
October 1968. Modifications to the project at Grand 
Lagoon were completed in January 1972. Total Federal 
cost under existing project as of September 30, 1989 is 
$1,638,045 for new work and $8,349,849 for maintenance, 
a total of $9,987,894. Contributed funds expended for new 
work amount to $80,000. 
16. PASCAGOULA HARBOR, MS 
Location. The project is located along lower 6.8 miles 
of Pascagoula River, the lower six miles of Dog River, and 
in Bayou Casotte (about four miles east of the mouth of 
Pascagoula River), in southeastern Mississippi, about 38 
miles west of Mobile, Alabama, and about 100 miles east 
of New Orleans, Louisiana. (See Coast and Geodetic Survey 
Chart 11373.) 
Previous project. For details see page 741, Annual 
Report for 1938. 
Existing project. The authorized project provides for 
(a) An entrance channel 40 feet deep and 350 feet wide 
from the Gulf of Mexico through Horn Island Pass, including 
an impounding area for littoral drift, 40 feet deep, 200 
feet wide, and about 1,500 feet long adjacent to the channel 
at the west end of Petit Bois Island; (b) a channel 38 
feet deep and 350 feet wide in Mississippi Sound and Pascagoula 
River to the railroad bridge at Pascagoula, including 
a turning basin 2,000 feet long and 950 feet wide 
(including channel area) on the west side of the river 
below the railroad bridge; (c) a channel 38 feet deep and 
225 feet wide from the ship channel in Mississippi Sound 
to the mouth of Bayou Casotte, thence 38 feet deep and 
300 feet wide for about one mile to a turning basin 38 feet 
deep, 1,000 feet wide, and 1,750 feet long; (d) a 22-foot 
deep by 150-foot wide channel up Pascagoula River from 
the railroad bridge to the mouth of Escatawpa (or Dog) 
River, then up Escatawpa River to Highway 613 (formerly 
63) bridge; (e) a 12-foot by 125-foot channel from the 
highway bridge, via Robertson and Bounds Lakes, to mile 
6 on Escatawpa River, and (f) a 12-foot by 80-foot channel 
extending from deep water in the Pascagoula River 
(about one-half mile north of the railroad bridge) to a tuning 
basin in Krebs Lake a distance of about 1,500 feet, 
then along the south bank of the lake a channel 10-foot by 
60-foot and terminating at a second turning basin, a distance 
of 2,700 feet from the first. Under ordinary conditions 
mean tidal range is 1.75 feet, and extreme range is 
3 75 feet. Plane of reference is mean low water. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 19.) 
Operations and results during fiscal year. Maintenance: 
Pre-dredging cost totaled $50,000. Condition surveys 
cost $66,715. Water control management, 
supervision and administration, and miscellaneous costs 
totaled $403,919. 
Condition at end of fiscal year. The existing project 
was completed in August 1965 and the Krebs Lake project 
was completed in November 1983. Total Federal cost of 
existing project to September 30, 1989 is $6,572,985 for 
new work and $41,391,975 for maintenance, a total of 
$47,964,960. Contributed funds expended for maintenance 
amounted to $3,104,623. 
17. PENSACOLA HARBOR, FL 
Location. The project is located in a landlocked bay on 
the coast of northwest Florida about 50 miles east of the 
entrance to Mobile Bay. (See Coast and Geodetic Survey 
Charts 490 and 11382.) 
Previous project. For details see Annual Report for 
1938. 
10-12

MOBILE, ALABAMA DISTRICT 
Existing project. The authorized project provides for: 
(a) A 35-foot by 500-foot entrance channel about five 
miles long, from the Gulf of Mexico to lower Pensacola 
Bay; (b) a 33-foot by 300-foot bay channel; (c) two 33- 
foot by 300-foot parallel approach channels to opposite 
ends of the inner harbor channel; (d) an inner harbor channel 
500 feet wide, 33 feet deep, and 3,950 feet long; (e) a 
30-foot by 250-foot approach channel to the pierhead line 
south of Muscogee wharf; and (f) a 15-foot by 100-foot 
entrance channel into Bayou Chico, thence a channel 14 
feet deep, 75 feet wide, and about 4,400 feet long to a 
turning basin 14 feet deep and 500 feet square. Mean 
range of tide throughout the harbor is about 1.1 feet near 
the entrance and about 1.6 feet at the head of bay. Extreme 
tidal range, except during storms, is about three feet. Plane 
of reference is mean low water. Modification of the Bayou 
Chico project to provide for enlarging the entrance channel 
to 21 by 100 feet, the bayou channel to 20 feet by 100 
feet, and deepening the turning basin to 20 feet has been 
deferred for restudy. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modem rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce (See Port Series No. 19, revised in 1979.) 
Operations and results during fiscal year. Maintenance: 
Corps of Engineers dredges removed 272,652 
cubic yards from harbor channel at a cost of $670,045. 
Condition surveys cost $21,007. Water control management 
and miscellaneous costs totaled $287,491. 
Condition at end of fiscal year. New work is completed 
except for features which are deferred for restudy. 
The modification authorized in 1962 was commenced in 
March and completed in May 1965. Total Federal cost of 
the existing project to September 30, 1989 is $1,469,693 
for new work and $8,155,547 for maintenance, a total of 
$9,625,240. 
18. PERDIDO PASS CHANNEL, AL 
Location. The project is located about midway between 
Pensacola, Florida and Mobile, Alabama. (See Coast and 
Geodetic Chart 11378.) 
Existing project. The existing project provides for a 
channel 12 feet deep and 150 feet wide for about 1,300 
feet from the Gulf of Mexico into the inlet, thence nine 
feet deep and 100 feet wide for about 2,200 feet to the 
highway bridge, where the channel branches into two 
arms, each having dimensions of 9 by 100 feet, one of 
which extends about 3,400 feet into Terry Cove and the 
other about 3,200 feet into the southern arm of Perdido 
Bay. The project also provides for two jetties spaced 600 
feet apart at the seaward end. The east jetty has a low weir 
section, 1,000 feet long to permit passage of littoral drift 
into a dredged deposition basin 800 feet by 1,200 feet located 
between the east jetty and the navigation channel. 
Mean tidal range is 1.1 feet and extreme is 2.8 feet. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Six marinas, numerous timber 
piers, docks, and several launching ramps are available. 
These facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $36,789. Water control 
management and miscellaneous costs totaled $20,943. 
Condition at end of fiscal year. The existing project 
was commenced in May 1968 and completed in March 
1969. Total Federal cost of the existing project to September 
30, 1989 is $629,860 for new work and $6,065,346 for 
maintenance, a total of $6,695,206. Contributions from 
local interest amount to $510,000 for new work and 
$10,325 for maintenance. 
19. TENNESSEE-TOMBGIBEE 
WATERWAY, AL AND MS 
Location. The waterway extends from mile 215 in 
Pickwick pool on the Tennessee River, southerly through 
northeastern Mississippi and western Alabama, a total of 
234 miles, to the confluence of the Black Warrior and 
Tombigbee Rivers at Demopolis, Alabama. 
Previous project. For details see Annual Report for 
1953. 
Existing project. The authorized project provides for a 
waterway 234 miles long, connecting the Tennessee and 
Tombigbee Rivers via the East Fork of Tombigbee River 
and Mackeys and Yellow Creeks. The plan of improvement 
consists of three sections. (1) the river section, a 9- 
foot by 300-foot channel for 149 miles between 
Demopolis and Amory, Mississippi; (2) the lateral canal 
section, 12 feet by 300 feet for 46 miles from Amory to 
Bay Springs; and (3) the divide section, a 12-foot by 300- 
foot channel (except in the 27 mile long divide cut in 
which the bottom width would be 280 feet) for 39 miles 
from Bay Springs through the dividing ridge to the Tennessee 
River; the total lift of 341 feet to be accomplished 
by 10 locks. (See Table 10-B for authorizing legislation.) 
10-13

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Local interests must make and 
maintain alterations in highways and highway bridges and 
in sewer, water-supply, and drainage facilities and provide 
and maintain suitable and adequate river and canal terminals. 
Officials of the State of Mississippi were notified 
of these requirements on December 13, 1949, and officials 
of the State of Alabama were notified on December 20, 
1949. Legislation enabling boards of supervisors of the 
various counties concerned to enter into agreements with 
the United States relative to navigation projects was 
adopted by the State of Mississippi in 1950. A compact 
between the States of Alabama, Mississippi, Tennessee, 
Kentucky and Florida has been formed for the purpose of 
promoting the project. The name of this organization is the 
Tennessee-Tombigbee Waterway Development Authority. 
During its 1962 session the Mississippi Legislature 
authorized the formation of the Tombigbee River Valley 
Water Management District. The District was organized in 
accordance with the enabling legislation and is empowered 
to fulfill the requirements of local cooperation for the portion 
of the project in Mississippi. A satisfactory resolution 
has been furnished. During its 1967 session the Alabama 
Legislature authorized the formation of a public corporation 
to be named the Tombigbee Valley Development 
Authority for the purpose of further development of the 
Tombigbee River and tributary streams. The organization 
was formed in accordance with the enabling legislation 
and in a referendum held December 5, 1967 the voters of 
Alabama authorized a bond issue not to exceed 
$10,000,000 to finance participation in this project and the 
Tombigbee River and Tributaries project. A satisfactory 
resolution has been furnished. 
Terminal facilities. Docks, storage facilities and handling 
equipment are still being developed along this new 
waterway. As of September 30, 1989, twelve such 
facilities were operational, while five were under construction, 
and five more are planned. The operational facilities 
are handling grain, wood chips, and logs. When all 
facilities are complete, about half will be publicly owned 
and operated. Additional ports and terminals must be completed 
before the waterway can achieve its full potential. 
(See Table 10-N for existing locks and dams.) 
Operations and results during fiscal year. New work: 
Project construction cost $3,348,383, engineering and 
design cost $425,478 and supervision and administration 
cost $1,331,154, a total of $5,105,015 for new work. 
Maintenance: Contract dredging on the river system 
removed 968,300 cubic yards at a total cost of $1,546,000. 
Total cost for operation and maintenance of the project for 
FY 89 amounted to $19,614,116, which included general 
charges of $7,361,100; Gainesville Lock and Dam, 
$474,900; Tom Bevill Lock and Dam, $799,700; Columbus 
Lock and Dam, $719,700; Aberdeen Lock and Dam, 
$640,300; Lock A, $415,200;, Lock B, $476,600; Lock C, 
$444,400; Lock D, $385,400; Lock E, $422,600,; Bay 
Springs Lock and Dam, $499,700. Recreation costs totaled 
$5,428,500. Recreation attendance for CY 1988 totaled 
6,742,000 user days. 
Condition at end of fiscal year. Total Federal cost 
under the existing project as of September 30, 1989 is 
$1,001,496,660 for new work, and $104,194,509 for maintenance 
for a total of $1,105,691,169. Construction formally 
began December 12, 1972 and overall project is 
essentially complete. The waterway was opened for 
navigation in January 1985. 
20. DEAUTHORIZED PROJECTS 
(See Table 10-G.) 
21. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 10-C.) 
22. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645, as amended (Preauthorization). Studies conducted 
under this authority amounted to $151,537 in FY 
1989. (See Table 10-H.) 
23. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 10-K.) 
Beach Erosion Control 
24. BEACH EROSION CONTROL 
PROJECTS UNDER 
SPECIAL AUTHORIZATION 
Studies conducted under Section 103, 1962 River and 
Harbor Act, as amended, amounted to $243 in FY 1989. 
(See Table 10-I.) 
10-14

MOBILE, ALABAMA DISTRICT 
25. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECT 
(See Table 10-D.) 
Flood Control 
26. COUNTY LINE ROAD BRIDGE, 
ITAWAMBA COUNTY, MS 
Location. County Line Road Bridge crossed Mantachie 
Creek in Itawamba County, Mississippi and is located approximately 
one mile west of Centerville along an unnumbered 
county road between County Hwy. 363 and the 
county line. The Mantachie Creek drainage area is located 
in northeast Mississippi and is a part of Tombigbee River 
Basin. 
Existing Project. The project would provide protection 
for both banks and the channel at the bridge crossing Mantachie 
Creek. The banks and channel would be graded and 
protected with 24 inches of riprap on 6 inches of bedding 
material and filter fabric. This would preclude any streambank 
erosion from high velocities or from sudden drawdown 
associated with receding floodwaters. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Engineering and design cost $17,979. Supervision and administration 
costs amounted to $2,418. Contributed funds 
expended in FY 1989 $8,000. 
Condition at end of fiscal year. Construction contract 
was awarded in August 1989 and is scheduled to be completed 
in March 1990. Estimated Federal cost is $99,000; 
and the non-Federal portion is $33,000. Total Federal cost 
to date is $30,497 for new work. 
27. CRIBBS MILL CREEK, 
TUSCALOOSA, AL 
Location. Cribbs Mill Creek begins in the northeastern 
part of the city of Tuscaloosa, AL and flows generally 
southwestward through the city into the Warrior River. 
Existing project. The project consists of channel 
modification of about 7,300 feet of the creek. Modification 
would consist of widening the existing channel. The 
proposed plan would extend upstream from 1-359 to the 
confluence of Tributary 1 with the creek. Work would also 
be performed on 600 feet of Tributary 5. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Engineering and design cost $39,071. Supervision and administration 
costs amounted to $5,382. 
Condition at end of fiscal year. Construction contract 
was awarded in November 1989 and is scheduled to be 
completed in September 1990. Estimated Federal cost is 
$1,800,000; and the non-Federal portion is $1,200,000. 
Total Federal cost to date is $417,602. 
28. ESLAVA CREEK, 
MOBILE, AL 
Location. The city of Mobile, Alabama, which is located 
on the Gulf Coast of Alabama. The project begins at 
Pine Hill Drive and ends 2.1 miles upstream at Emogene 
Street. 
Existing project. None. The plan of improvement consists 
of channel enlargement, bank stabilization measures, 
and increasing the size of the box culvert at Airport 
Boulevard by adding an additional barrel. (See Table 10-B 
for authorizing legislation.) 
Local cooperation. A Local Cooperation Agreement 
with the city of Mobile was completed on September 14, 
1987. The local sponsor has also agreed to make all required 
payments concurrently with project construction. 
Operation and results during fiscal year. New work: 
Construction contract $180,074; engineering and design 
$89,193; and supervision and administration $24,373. A 
total Federal cost of $1,608,651 for new work. Contributed 
funds expended in FY 1989 $25,500. 
Condition at end of fiscal year. Preparation of plans 
and specifications are completed. The first increment of 
work was awarded in February 1988 and completed in 
August 1988. The second increment of work is awaiting 
for the city to obtain necessary rights-of-way for construction. 
Anticipate a construction contract to be awarded in 
July 1990 and construction to be completed in September 
1991. Current estimated Federal cost is $2,580,775; and 
the non-Federal portion is $1,046,800 for land and relocation, 
and $190,925 cash contributions. Total Federal cost 
under existing project to September 30, 1989 is 
$1,608,651. Contributed funds expended $25,500. 
29. GULF BREEZE, 
SANTA ROSA CO., FL 
Location. East End of the Old Highway 98 Bridge over 
Pensacola Bay at Gulf Breeze, Florida. 
10-15

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. The recommended plan will take 
emergency actions to stop shoreline erosion around a 
water supply pumping station for the City of Gulf Breeze, 
FL.
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Project construction costs amounted to $90,103; engineering 
and design cost $9,004; and supervision and administration 
costs amounted to $9,131. Contributed funds 
expended in FY 1989 $36,094. 
Condition at end of fiscal year. A construction contract 
was awarded on 10 January 1989 and construction 
was completed in May, 1989. Total Federal cost to date is 
$136,183 for new work. 
30. HIGHWAY 39 BRIDGE, 
GAINESVILLE, AL 
Location. The project is located on the Tombigbee 
River, upstream of the Highway 39 bridge in Gainesville, 
AL.
Existing project. The authorized project provides for 
slope protection for a 2000-foot reach of the east bank of 
the Tombigbee River, immediately upstream of the existing 
Highway 39 bridge. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. The Water Resources Development 
Act (WRDA) of 1986 (P.L. 99-662) requires any flood 
control project not under construction by April 30, 1986 to 
enter a binding agreement with the Secretary of the Army 
to pay 100% of the operation and maintenance, and replacement 
and rehabilitation costs of the project, and to 
pay the required non-Federal share of the costs of construction. 
Subject to the cost sharing requirements of the 
WRDA of 1986, a non-federal sponsor has not been identified. 
Operations and results during fiscal year. New work: 
Engineering and design cost $1,974. 
Condition at end of fiscal year. Total cost of the 
project to date is $70,364. 
31. HINTONVILLE ROAD BRIDGE, 
PERRY CO., MS 
Location. The Hintonville Road Bridge crosses 
Thompson Creek in Perry County, Mississippi and is located 
approximately one mile east of Hintonville along an 
unnumbered county road. The Thompson Creek drainage 
area is located in southeast Mississippi and is part of the 
Pascagoula River Basin. 
Existing project. The project would provide protection 
for the bridge side slopes channel bottom, and to realign 
the channel thru the center span of the bridge. The banks 
350 feet upstream and 200 feet downstream from the 
bridge would be graded and protected with 24 inches of 
riprap on 6 inches of bedding material and filter fabric for 
100 feet upstream and 150 feet downstream of the bridge. 
A 40-foot bottom width channel would be excavated and 
riprapped thru the center span of the bridge. A stone training 
dike would be constructed on the left bank of the 
project channel to direct low flows through the project 
channel and away from the left bank and left bridge abutment. 
The dike would be protected with 12 inches of 
riprap and 6 inches of bedding material and filter fabric. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Engineering and design cost $26,835. Supervision 
and administration costs amounted to $2,719. 
Condition at end of fiscal year. Construction contract 
was awarded in September 1989 and is scheduled to be 
completed in May 1990. Estimated Federal cost is 
$264,000; and the non-Federal portion is $88,000. Total 
Federal cost to date is $39,663 for new work. 
32. HURRICANE CREEK, 
PRENTISS CO., MS 
Location. Southeast Prentiss County, Mississippi. 
Marietta-Hazeldell Road Bridge crosses Hurricane Creek 
Tributary to Big Brown Creek and is located about 20 
miles northeast of Tupelo, Mississippi. 
Existing project. The project would provide emergency 
streambank protection to the banks and the bottoms of 
the channel to retard erosion at the Marietta-Hazeldell 
Road Bridge crossing Hurricane Creek, a tributary to Big 
Brown Creek. The banks and bottoms would be graded 
and protected with 12 inches of riprap on 6 inches of bedding 
material and filter fabric upstream of and downstream 
from the bridge. Through the bridge section, 18 inches of 
riprap would be placed on 6 inches of bedding materials 
and filter fabric. This wouldi preclude any streambank 
erosion from high velocities or sudden drawdown associated 
with receding floodwaters. 
Local cooperation. Fully complied with. 
Operations and results during flecal year. New 
Work: Engineering and design cost $13,054. Supervision 
and administration costs amounted to $1,224. 
10-16

MOBILE, ALABAMA DISTRICT 
Condition at end of fiscal year. A construction contract 
was awarded on 10 August 1989 and construction 
was essentially completed in December, 1989. Total 
Federal cost to date is $21,296. 
33. LEAF AND BOWIE RIVERS, 
HATTIESBURG, MS 
Location. The Leaf River forms the east boundary of 
the city of Hattiesburg, the county seat of Forrest County, 
located in south-central Mississippi. The river separates 
Hattiesburg from the smaller city of Petal. Bowie River 
flows southeasterly along the northern boundary of Hattiesburg 
and joins the Leaf River at the northeast corner of 
the city. 
Existing project. The project provides for channel 
snagging, overbank clearing within the flood plains, riprap 
protection of the Southern Railroad and River Avenue 
Bridge piers and removal of the Petal sewage lagoon. 
Work will also include installation of a flood warning system. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Project construction contract costs amounted to $41,125. 
Condition at end of fiscal year. The project was essentially 
completed in FY 1987. The remaining work consists 
of minor grassing and installation of the flood warning 
system. Total Federal cost as of September 30, 1989 is 
$1,584,214. 
34. LITTLE COVE CREEK, 
GLENCOE, AL 
Location. Glencoe, Alabama is located five miles 
southeast of Gadsden, Alabama. Little Cove Creek is approximately 
seven miles long, originating in the foothills 
of Colvin mountain about five miles southeast of Glencoe. 
It flows northwest for five miles paralleling U.S. Highway 
431, until it reaches the east edge of Glencoe. The creek 
flows two miles north to Hokes Bluff where it joins Cove 
Creek north of U.S. Highway 431. 
Existing project. The existing project on Little Cove 
Creek was constructed under the Section 205 of the Flood 
Control Act of 1948 and was completed in 1963. This 
project consisted of enlargement and realignment of 
10,840 feet along Little Cove Creek to provide a channel 
bottom width of 25 feet and an average depth of 6 feet. 
Also included in the project were associated channel and 
overbank clearing and bridge modification work. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Engineering and design cost $16,691. Supervision 
and administration costs amounted to $2,172. 
Work accomplished to date: A supplement to the 
Detailed Project Report was completed in September 
1988. Current recommendations for rehabilitation of 
project consists of an upstream transition section to 
prevent head cutting and extending the project 
downstream to provide an adequate outlet for the existing 
project and reshaping of its existing channel side slopes 
and grassing these slopes. 
Problems, issues, and constraints: The Detailed 
Project Report estimated the benefit-to-cost ratio to be 
0.15 to 1, clearly indicating that the work is not economically 
justified. After review of the report, concern was expressed 
over the economics of the project. A more detailed 
economic analysis was completed in December 1989. A 
revision to the supplement will be issued in February 
1990. Estimated Federal cost is $790,800; and the non- 
Federal portion is $53,200. Total Federal cost to date is 
$124,916 for new work. 
35. MAGBY CREEK 
COLUMBUS, MS 
Location. Magby Creek originates in Pickens County, 
Alabama about 13 miles east of the Mississippi-Alabama 
State line. From its source, the creek flows in a westerly 
direction through a rural area of Mississippi and Alabama 
for a distance of 25 miles to enter the Luxapalila Creek .6 
miles above Propst Park in Columbus, MS. 
Existing project. The project consists of clearing and 
snagging Magby Creek from mile 0.83 upstream to mile 
2.06. An additional 60 feet on the right overbank will be 
cleared of underbrush and any trees less than 6 inches in 
diameter. This 60 feet will alternate to the left bank, where 
there are deep bands, creating a straighter floodway effect. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Project construction costs amounted to $6,000, engineering 
and design cost $26,032, and supervision and 
administration costs amounted to $2,142. 
Condition at end of fiscal year. Preparation of Plans 
and Specifications were initiated in August 1987 and essentially 
completed. A construction contract was awarded 
in July, 1989 and construction was completed in November, 
1989. Total Federal cost to date is $126,506 for new 
work. 
10-17

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
36. MILL CREEK, 
DALTON, GA 
Location. The Mill Creek watershed comprises an area 
of 51.0 square miles in northeastern Walker County and 
west central Whitfield County, Georgia. The creek rises 
about 8 miles southwest of Dalton and flows in a northerly 
direction to its confluence with the North Fork of Mill 
Creek. From this point the creek flows generally in an 
easterly direction through the northern part of Dalton and 
enters Coahulla Creek 5.5 miles above its mouth. 
Existing project. The recommended plan consists of 
clearing and snagging Mill Creek from its mouth to 
downstream face of Willowdale Drive or a distance of 8.6 
miles. This work would involve the clearing of all 
material, trees, shrubs, and any underbrush within the 
creek banks. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Engineering and design cost $5,552. Supervision 
and administration costs amounted to $5,802. 
Condition at end of fiscal year. The Detail Project 
Report was revised and submitted in November 1987. 
These revisions reflected the changes due to cost sharing 
and contained a revised local cooperation agreement. The 
project advertised for a construction contract in August, 
1989, and a construction contract was awarded on 6 
November 1989. Project construction is scheduled to be 
completed in May, 1990. Estimated Federal cost is 
$300,000; and the non-Federal portion is $200,000. Total 
Federal cost to date is $251,045 for new work. 
37. MURDER CREEK, 
BREWTON, AL 
Location. The project is located in the city of Brewton, 
AL near the confluence of Murder and Burnt Corn Creeks 
in the commercial district of downtown Brewton. 
Previous project. A limited stream clearing and snagging 
project was completed in 1980 on portions of both 
creeks to remove obstructions to flows. This jnterim 
measure was undertaken to reduce flooding in Brewton 
and East Brewton. Further, an evacuation plan for East 
Brewton was implemented under the Section 205 
authority. The project involved removal of damageable 
structures from the low-lying flood plain of Murder Creek. 
Existing project. The authorized non-structural project 
provides for the alleviation of flood problems at Brewton 
by the removal of 31 damageable structures from the 10- 
year flood plains of Murder and Burnt Corn Creeks. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New work: 
Real estate acquisitions during FY 1989 cost $211,236; 
engineering and design $3,690; and $610 for supervision 
and administration. 
Condition at end of fiscal year. Total cost of project as 
of September 30, 1989 is $1,160,438. 
38. OKATIBBEE LAKE, MS 
Location. The project is located on Okatibbee Creek 
37.7 miles above its mouth, in Lauderdale County, Mississippi, 
seven miles northwest of Meridian. 
Existing project. The project provides for a dam and 
reservoir for flood control, water supply, water quality 
control, fish and wildlife, and recreation. The dam consists 
of a compacted earth fill 6,540 feet long with the top 
elevation 369.8 feet above national geodetic datum, with 
top width of 18 feet. The spilway, which is located 1,500 
feet east of the east end of the dam, is an unpaved free 
overflow type, 1,500 feet long with a fixed crest at elevation 
359. A sluice intake structure near the center of the 
dam serves a 9.0-foot diameter concrete conduit. Storage 
allocated for water supply and water quality control varies 
seasonally form 21,400 acre-feet to 34,300 acre-feet between 
a minimum elevation of 328 and top-of-conservation-
pool elevation varying from 339 to 343. Storage 
varying from 46,500 to 59,500 acre-feet between the top 
of the conservation pool and elevation 352 has been 
reserved exclusively for storage of flood waters. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Complied with to date. 
Operations and results during fiscal year. New work: 
None 
Maintenance: Costs for the year for ordinary maintenance 
and recreational management amount to 
$1,057,387. Recreation attendance at the reservoir during 
CY 1988 totaled 1,135,392 recreational user days. 
Condition at end of fiscal year. Construction began in 
June 1965, and was completed in November 1968. Total 
Federal cost of the existing project as of September 30, 
1989 is $9,739,528 for new work and $11,345,920 for 
maintenance, a total of $21,085,448. 
10-18

MOBILE, ALABAMA DISTRICT 
39. RACCOON CREEK 
BACONTON, GA 
Location. The community of Baconton is located in 
northwest Mitchell County approximately 20 miles due 
south of Albany and 40 miles northeast of Bainbridge, 
Georgia. Raccoon Creek rises in the northeastern portion 
of Mitchell County known as the Tifton Upland and flows 
almost due west across the Daugherty Plains, where it 
enters the Flint River at river mile 81.1 on the Flint. The 
total drainage area, as it flows by Baconton, is 98 square 
miles. The total drainage area is comprised mostly of 
agricultural lands, which grow pecans, soybeans, and 
peanuts. The floodplain in Baconton varies in width from 
about 2,000 to 6,000 feet with an average fall of about 1 
foot per mile. 
Exiting project. The flood control project would consist 
of raising about 1500 feet of South Jackson Street near 
the West Daniels Street bridge to elevation 176.0 feet 
NGVE. The channel and 30 feet on each overbank of Raccoon 
Creek would be cleared and snagged from State 
Hwy. 3 to U.S. Hwy. 19. Raising South Jackson Street 
would prevent overbank flows from entering downtown 
Baconton. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Engineering and design cost $43,243. Supervision 
and administration costs amounted to $3,394. 
Condition at end of fiscal year. Preparation of plans 
and specifications were initiated in August 1988. A construction 
contract was advertised in May 1989, and a contract 
was awarded on 29 August 1989. The project is 
scheduled to be completed in February, 1990. Estimated 
Federal cost is $285,000; and the non-Federal portion is 
$95,000. Total Federal cost to date is $173,143 for new 
work. 
40. SEWERLINE PROTECTION, 
VALLEY, AL 
Location. Valley, Alabama is located on the west bank 
of the Chattahoochee River in the southeast corner of 
Chambers County. The West Point Lake and Dam is located 
approximately 11 miles up river from Valley and 
controls a drainage area of approximately 3600 square 
miles. A sanitary sewage line and pumping station were 
built in 1972 to provide service from approximately 200 
homes and several businesses located near Valley. This 
line serves as the only sewage transport for this area. 
Existing project. The project provides for the restoration 
of approximately 1600 linear feet of streambank. This 
work consisted of approximately 1550 cubic yards of No. 
5 riprap on 4445 square yards of filter fabric. Reshaping of 
the bank was done by placing backfill material as opposed 
to cutting the existing streambank. The reshaped bank was 
then grassed. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New work: 
Engineering and design cost $1,628. 
Condition at end of fiscal year. Construction was initiated 
in FY 1985 and completed in FY 1986 at a total 
cost to date of $180,937 for new work. 
41. SOPE CREEK, 
MARIETTA, GA 
Location. The project is located in Marietta, Georgia in 
Cobb County which is in the north-central section of 
Georgia, just north-northwest of Atlanta. Sope Creek is a 
small tributary of the Chattahoochee River and flows 
generally from northwest to southeast from its beginning 
in the city of Marietta. 
Existing project. The project provides for flood control 
measures along Sope Creek in Cobb County, Georgia. The 
project provides for both a structural and nonstructural 
component. The structural component provides for clearing 
and snagging of the creek. This would involve the 
clearing of all material, trees, shrubs and any underbrush 
less than 12 inches in diameter from a strip 30 feet wide 
on each side of the creek and removing all trees, shrubs 
and underbrush within the creek banks. Snagging would 
involve the removal of all fallen trees and debris which are 
in the creek. The nonstructural component provides for the 
evacuation of 13 structures located on the west side of the 
creek within the Fox Hills subdivision. The project 
provides for purchase and removal of the structures. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. New Work: 
Construction cost $76,158, engineering and design 
$10,086, and supervision and administration cost $20,104. 
Condition at end of fiscal year. All 13 homes have 
been acquired and a clearing and snagging construction 
contract was awarded to Small Business Administration 
Program 8(a) in 1988. The 8(a) contract defaulted. A construction 
contract was awarded in December 1988 and 
project construction was completed in September 1989. 
Total Federal cost to date is $1,525,444 for new work. 
10-19

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
42. SOWASHEE CREEK, 
MERIDIAN, MS 
Location. The project is located in East Central Mississippi, 
Lauderdale County, in the city of Meridian, which is 
approximately 90 miles east of Jackson, Mississippi. 
Existing project. In 1955, the Corps of Engineers completed 
channel improvement on the lower 10.5 miles of 
Sowashee Creek. This work was accomplished under the 
authority of Section 205 of the Flood Control Act of 1948, 
as amended. The plan of improvement consists of a combination 
of channel enlargement (3.9 miles), and clearing 
and snagging (6.6 miles) over a reach of 10.5 miles. One 
(1) railroad bridge and several highway roads and bridges 
and utilities will require modification for the channel improvement. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. A Local Cooperation Agreement 
with the Pat Harrison Waterway District was completed on 
September 23, 1987. The local sponsor has also agreed to 
make all required payments concurrently with project construction. 
Operation and results during fiscal year. New work: 
Construction contract cost $1,183,662; engineering and 
design $315,571; and supervision and administration 
$54,572, a total Federal cost of $3,487,725 for new work. 
Condition at end of fiscal year. The initial construction 
contract was awarded on December 18, 1987 and 
project completion is scheduled for November 1991. Current 
estimated Federal cost is $13,520,000; and the non- 
Federal portion is $5,104,000 for land and relocation, 
$980,000 cash contributions, and $458,000 for recreational 
facilities. Total Federal cost under existing project to September 
30, 1989 is $3,487,725 for new work. Contributed 
funds expended $59,025. 
43. TALLAHALLA CREEK, 
LAUREL, MS 
Location. The Pascagoula River Basin lies in 
southeastern Mississippi and a small part of southwestern 
Alabama. The Pascagoula River system drains an area of 
9700 square miles. The study area, located in Jones County, 
includes the city of Laurel and the unincorporated communities 
of Walters and Pendorf as well as the outlying 
areas of the city of Ellisville adjacent to the Tallahala 
Creek Flood plain. 
Existing project. The project along Tallahalla Creek 
would consist of channel clearing and snagging with overbank 
clearing of brush and trees less than 4 inches 
diameter for a distance of 30 feet on each bank. The 
project would begin about 1.5 miles below Queensburg 
Avenue Bridge and extend 7.25 miles to US Highway 84. 
Also, a flood warning system would be installed in the 
Tallahalla Creek Basin to relay data to a base station. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Engineering and design cost $43,282. Supervision 
and administration costs amounted to $3,030. 
Condition at end of fiscal year. The advertisement for 
bids for clearing and snagging portion of the project was 
cancelled in August, 1989 due to erosion at two sites along 
Masonites Lagoon Dikes. Redesign of the project is underway 
to rectify the erosion problems and prevent velocities 
increases along the dikes due to project construction. It is 
anticipated that a construction contract will be awarded in 
May, 1990. A flood warning system for the Tallahala 
Creek basin is scheduled to be awarded in January, 1990. 
Estimated Federal cost is $822,640; and the non-Federal 
portion is $307,360. Total Federal cost to date is $62,080 
for new work. 
44. THREEMILE CREEK, 
MOBILE, AL 
Location. The project is located near the Gulf of 
Mexico in the southwest corner of the state of Alabama 
and in the city of Mobile, approximately 180 miles southwest 
of Montgomery, Alabama. Threemile Creek 
originates in the western part of Mobile and flows easterly 
about 14 miles to enter Mobile River near the Alabama 
State Docks. The drainage area of the basin consists of 39 
square miles of urbanized area. 
Existing project. None. The authorized flood control 
project will consist of channel widening and deepening 
from about 2,000 feet downstream of Stone Street to a 
point about 6,300 feet upstream of Interstate 65 or a total 
distance of 5.6 miles. The plan also includes development 
of certain recreational facilities of the type associated with 
urban parks. (See Table 10-B for authorizing legislation.) 
Local cooperation. The Local Cooperation Agreement 
with the city of Mobile, Alabama was completed on September 
30, 1987. The local sponsor has agreed to make all 
payments concurrently with project construction. 
Operation and results during fiscal year. New work: 
Construction contracts $670,562; engineering and design 
$143,359; and supervision and administration $98,612. A 
total Federal cost of $2,136,257 for new work. 
10-20

MOBILE, ALABAMA DISTRICT 
Condition at end of fiscal year. Plans and Specifications 
were initiated in December 1986 and a construction 
contract was awarded on 30 September 1987 for the first 
increment of work. Preparation of Plans and Specifications 
on the remaining work is essentially completed. The first 
increment of work was completed in October 1988. The 
remaining work depends on the local sponsor obtaining 
necessary real estate and relocations for project. Current 
estimated Federal cost is $16,691,000; and the non-Federal 
portion is $6,563,000 for land and relocation, $1,216,000 
cash contributions, and $160,000 for recreational facilities. 
Total Federal cost under existing project to September 30, 
1989 is $2,136,257 for new work. Contributed funds expended 
$112,458. 
45. TOMBIGBEE RIVER (EAST FORK), 
MS AND AL 
Location. The project is located on the Tombigbee 
River and its tributaries between the junction of Browns 
and Mackeys Creek in Itawamba County, Mississippi, for 
a distance of 53 miles along the East Fork of the Tombigbee 
River, from Walkers Bridge at the junction of Browns 
and Mackeys Creeks to the Monroe County line. 
Existing project. Provides for alleviation of floods from 
the Tombigbee River by clearing and snagging and excavation 
of 13 cut-off channels, and other related channel 
improvements. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with on work done 
under the 1936 Flood Control Act. Work to be done under 
authority of the 1941 Flood Control Act requires local interest 
to provide all lands, easements, and rights-of-way 
for project construction; hold and save the United States 
free from damages due to construction of the project; and 
maintain and operate all the works after completion in accordance 
with regulations prescribed by the Secretary of 
the Army. 
Operations and results during fiscal year. Maintenance: 
Routine maintenance of channels cost $66,102. 
Condition at end of fiscal year. The project for 
Itawamba County, as authorized in the 1936 Flood Control 
Act, was completed during fiscal year 1940. No work has 
been done on the extension of the project authorized in the 
1941 Flood Control Act. Total Federal cost of the existing 
project as of September 30, 1989 is $134,801 for new 
work and $2,711,371 for maintenance, a total of 
$2,846,172. 
46. TOMBIGBEE RIVER 
TRIBUTARIES, MS AND AL 
Location. The Tombigbee River rises in extreme northeast 
Mississippi and flows southerly through eastemrn Mississippi 
and westemrn Alabama, emptying into the Mobile 
River about 45 miles above its mouth at Mobile, Alabama. 
Tributaries to be improved for flood control are all in 
northeast Mississippi and northwest Alabama. 
Existing project. The authorized project provides for 
improvement of 22 tributaries of the Tombigbee River 
Basin by means of channel clearing and snagging. Approved 
estimate of cost (1989) for new work is 
$43,411,000; consisting of $38,364,000 Federal funds, and 
$5,047,000 non-Federal funds. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests must furnish lands 
and rights-of-way for construction; make all roads, highway 
bridge, and utility changes, alterations, additions, and 
relocations necessary for the project; hold the United 
States free from damages; prevent future encroachments 
along the improved channels; maintain all works after 
completion, with the exception of Twenty Mile Creek 
from mile 11.7 to mile 22.0. 
Operations and results during fiscal year. New work: 
Real estate cost $160,493; Channel and canals contract 
cost $733,789, engineering and design $283,582, and supervision 
and administration cost $113,631. Total Federal 
cost to date is $23,606,623 for new work. 
Condition at end of fiscal year. Construction commenced 
in July 1965, and is proceeding stream by stream 
as funds are made available. Total Federal cost of existing 
project as of September 30, 1989 is $23,606,623 for new 
work. Contributed funds for new work amounted to 
$63,342. 
47. UPPER GORDON CREEK, 
HATTIESBURG, MS 
Location. The proposed project on Gordons Creek is 
located in Hattiesburg, MS. 
Existing project. A Federal project on the lower 2.5 
miles was constructed in 1979 under the Section 205 of 
the Flood Control Act of 1948. The project consisted of 
clearing and snagging from the creek's confluence with 
the Leaf River upstream to Bay Street and channel widening 
to a 40-foot bottom width between Bay and Broad 
Streets. 
10-21

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
The first increment of Work Phase I will consist of real 
estate acquisition of nine (9) residences on Brookland 
Street and South 17th Avenue and removed from 
floodplain; habitat mitigation and channel enlargement for 
1.1 miles between Broad and Hardy Streets; and flood 
damages mitigation downstream of Broad Street. The 
second increment of Work Phase II will consist of channel 
enlargement from US Hwy. 11 upstream about 2.7 miles 
to South 40th Avenue and Lincoln Road. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Engineering and design cost $148,089. Supervision 
and administration costs amounted to $5,495. 
Work Accomplished to Date: Preparation of Plans and 
Specifications for Contract I is essentially completed. It is 
anticipated a construction contract would be awarded in 
the fourth quarter FY 1990, provided necessary right-ofways 
for Contract I channel improvement are available 
and necessary relocations are performed by local sponsors. 
Also, initiation of the mitigation of damages downstream 
of Broad Street and real estate acquisition of nine residences 
upstream of Hardy Street have been initiated. Plans 
and specifications for Contract II were initiated in December, 
1989, and are 60 percent completed. It is anticipated a 
construction contract for the second and final increment of 
work will be awarded in second quarter FY 1991. Estimated 
Federal cost is $4,412,250; and the non-Federal 
portion is $3,087,750. Total Federal cost to date is 
$608,276 for new work. 
48. VILLAGE CREEK, 
BIRMINGHAM, AL 
Location. The project is located in central Alabama, 
Jefferson County, in the city of Birmingham, Alabama. 
Existing project. None. The project is basically nonstructural 
and includes evacuating 642 structures, in six (6) 
separate neighborhoods, from the floodplain; enlarging 2 
miles of the stream channel in the vicinity of the 
Municipal Airport which also involves modification of 
three (3) bridges, demolishing two (2) unused bridges, and 
relocating two (2) waterlines and other utilities, installing 
three (3) emergency floodwarning devices; and creating an 
area of 210 acres which can be utilized for future recreation 
development. Channel enlargements (2 miles) will 
reduce annual damages near Municipal Airport by 82 percent 
and evacuation of 627 structures will reduce annual 
damages in residential areas by 61 percent. 
Local cooperation. The Local Cooperation Agreement 
with the city of Birmingham, Alabama war completed on 
December 14, 1988. The local sponsor has also agreed to 
make all required payments concurrently with the project 
construction. 
Operation and results during fiscal year. New work: 
Real Estate cost $1,695,226; engineering and design 
$39,589; Cultural Resources $285,515; and supervision 
and administration $51,241. A total Federal cost of 
$2,308,622 for new work. 
Condition at end of fiscal year. Real Estate design 
memorandum complete February 1988. Real Estate acquisition 
scheduled to start January 1989. Project 
scheduled to be completed June 1994. Current estimated 
Federal cost is $31,965,000; and the non-Federal portion is 
$1,960,000 for land and relocation, and $10,075,000 cash 
contributions. Total Federal cost under existing project to 
September 30, 1989 is $2,308,622 for new work. 
49. WHORTON'S BEND ROAD, 
ETOWAH CO., AL 
Location. The area under consideration is approximately 
500 feet along the right bank of the Coosa River 
upstream of the State Highway 77 bridge on Whorton's 
Bend Road in Etowah County, Alabama, south of 
Gadsden. 
Existing project. The project would provide emergency 
streambank protection along the left bank of the Coosa 
River to retard erosion of Whorton's Bend Road. The 
project consists of excavation and grading of approximately 
1850 cubic yards (cy) of earth and of placement of 
11,070 cy of riprap graded for a minimum layer thickness 
of 30 inches. This would preclude any streambank erosion 
with the Alabama Power operations on the Coosa River 
and receding floodwaters. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
Work: Project construction costs amounted to $205,985, 
engineering and design cost $37,689, and supervision and 
administration costs amounted to $48,308. Contributed 
funds expended in FY 1989 $114,000. 
Condition at end of fiscal year. A construction contract 
was awarded in February, 1989 and construction was 
essentially completed in November, 1989. Estimated 
Federal cost is $370,000; and the non-Federal portion is 
$139,000. Total Federal cost to date is $308,377 for new 
work. 
10-22

MOBILE, ALABAMA DISTRICT 
50. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
Snagging and Clearing for flood control pursuant to 
Section 208 of Flood Control Act of 1954, as amended. 
Emergency streambank and shoreline protection pursuant 
to Section 14 of the Flood Control Act of 1946, as 
amended. 
(See Table 10-J) 
Emergency flood control activities - repair, flood fighting, 
and rescue work under Public law 99, 84th Congress, 
and antecedent legislation, and disaster relief and assistance 
under Public law 288, 93d Congress. 
(See Table 10-J) 
51. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Local flood protection works for which inspection is 
performed under this heading consist of levee projects at 
West Point, Georgia, ont eh Chattahoochee River, Beaver 
C reek at Montezuma, Georgia, in the Flint River Basin; 
Elba and Geneva, Alabama in the Choctawhatchee River 
Basin; Rome, Georgia, and Little Wills Creek at Collinsville, 
Alabama, in the Alabama-Coosa River Basin. 
Channel recitification projects include Little Cove Creek, 
Glencoe, Alabama and Black Creek, Gadsden, Alabama in 
the Alabama-Coosa River Basin; Big Brown Creek, 
Donivan Creek, Twenty Mile Creek and Mantachie Creek, 
near Fulton, Mississippi, Burketts Creek and Stanifer 
Creek near Amory, Mississippi, Houlka Creek and 
Sakatonchee Creek in Chickasaw and Clay Counties, Mississippi, 
James Creek in Monroe County, Mississippi, and 
Luxapalila Creek, Lowndes County, Mississippi, all in the 
Tombigbee River Basin; Sowashee Creek, Meridian, Mississippi 
in the Pascagoula River Basin; Burnt Corn and 
Murder Creeks, Brewton, Alabama in the Conecuh River 
Basin; Autauga Creek, Prattville, Alabama; Poley Bridge, 
Goose Pone and Walnut Creeks, Clanton, Alabama; 
Pinchgut Creek, and Cahaba River, Trussville, Alabama; 
Town Creek, Americus, Georgia; and Lake Douglas in 
Bainbridge, Georgia. Shore protection and erosion control 
projects include Harrison County, Mississippi; Leaf River, 
Mahned, Mississippi; Chattahoochee River at La Grange, 
Troup County, Georgia; Pumpkinvine Creek, Emerson, 
Georgia; and Chickasawbogue Creek, US Highway 43 
Bridge, Linden, Alabama. The project at Rome and Montezuma, 
Georgia and Collinsyville, Alabama include pumping 
stations. Inspections were made during FY 89 to determine 
the extent of compliance with approved regulations 
for maintenance and operation of the project. Responsible 
local officials were advised of inadequacies in the maintenance 
and operation of the local flood protection works 
under their jurisdiction where appropriate. Followup for 
compliance of the deficient projects continued during the 
year. Fiscal year costs were $70,070. Total cost to September 
30,1989 is $564,478 charged to maintenance. 
52. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 10-E.) 
Multiple-Purpose Projects Including Power 
53. ALABAMA-COOSA RIVERS, 
AL AND GA 
Location. Alabama River is formed 18 miles above 
Montgomery, Alabama, by the junctions of the Coosa and 
Tallapoosa Rivers. It then flows southwesterly through 
Alabama 318 miles and unites with the Tombigbee River 
about 45 miles north of Mobile, in southwestern Alabama, 
to form the Mobile River. (See Geological Survey maps 
for central and southwest Alabama.) The Coosa River is 
formed at Rome, Georgia, in northwest Georgia, by the 
junction of the Oostanaula and Etowah Rivers, which have 
their sources in southeastern Tennessee and northern 
Georgia. From Rome the Coosa River flows southwesterly 
through Georgia and Alabama 286 miles and unites with 
the Tallapoosa River near Montgomery, Alabama, at about 
the center of the State, to form the Alabama River. (See 
Geological Survey maps for northeast Alabama, southeast 
Tennessee, and northwest Georgia.) 
Previous project. Projects for Alabama River. for 
details see page 1837, Annual Report for 1915; page 725, 
Annual Report for 1938; and page 592, Annual Report for 
1944. Projects for Coosa River: for details see page 1837, 
Annual Report for 1915; page 728, Annual Report for 
1938; and page 594, Annual Report for 1944. 
Existing project. The authorized project provides for 
full development of the Alabama-Coosa Rivers and 
tributaries for navigation, flood control, power, recreation, 
and other purposes, in accordance with plans under 
preparation by Chief of Engineers, subject to modifications 
thereof which may be advisable for increasing 
development of hydroelectric power. (See Table 10-B for 
authorizing legislation.) Public Law 436, 83rd Congress, 
10-23

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
suspended authorization of the comprehensive plan, insofar 
as it provides for development of hydroelectric 
power for Coosa River, to permit non-Federal interests to 
develop the Coosa River by construction of a series of 
dams in accordance with conditions of a license issued 
pursuant to Federal Power Act and in accordance with certain 
other provisions and requirements of the aforementioned 
public law. The plan was further modified by the 
WRDA of 1986 to authorize planning, engineering and 
design for the project generally in accordance with the 
plans contained in Design Memorandum No. 1, General 
Design, dated May 1982. The present phase of improvement 
provides for construction of Robert F. Henry and 
Millers Ferry multiple-purpose improvements. Claiborne 
Lock and Dam, and supplemental channel work providing 
for a nine-foot deep navigation channel from the mouth of 
the Alabama River to Montgomery, Alabama, and for construction 
of Carters Dam, a multiple-purpose improvement 
on Coosawattee River, Georgia. 
Local cooperation. Requirements of local cooperation 
will be determined as formulation of plans for development 
of projects progress. No action in the matter of local 
cooperation has been initiated. 
Terminal facilities. On the east bank of the river a 
natural landing connects with city streets at Montgomery. 
Wofford Oil Company has a small wharf about 10 miles 
below Montgomery equipped for handling petroleum 
products. There are also various natural landings along the 
river. Facilities and natural landings on Alabama River are 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Contract maintenance dredging of the river system 
removed 420,828 cubic yards at a cost of $1,528,800. 
General charges for water control management, condition 
surveys, engineering and design, supervision and administration 
amounted to $3,376,511. Claibome Lock and 
Dam charges were $500,700 with recreation and resource 
management costs of $998,500. Non-dredging channel 
maintenance cost $1,898,500. 
Condition at end of fiscal year. Construction was initiated 
on Carters Dam in April 1962, on Millers Ferry 
Lock and Dam in April 1962, on Millers Ferry Lock and 
Dam in April 1963, Claibome Lock and Dam in May 
1965, and Robert F. Henry Lock and Dam in March 1966. 
Carters Dam was completed in FY 1980. The authorized 
nine-foot navigation channel to Montgomery, Alabama 
was opened to traffic in January 1972. Overall construction 
is essentially complete at Millers Ferry Lock and 
Dam. Construction of Robert F. Henry Lock and Dam is 
essentially complete. Total Federal cost of the existing 
project as of September 30, 1989 is $61,480,533, including 
$3,245,400 for new work and $58,235,133 for maintenance. 
(See Table 10-L.) 
53A. CARTERS DAM AND 
RESERVOIR, GA 
Location. The damsite is in Murray County, Georgia, 
on the Coosawattee River 26.8 miles above its junction 
with Conasauga River, one of the headwater tributaries of 
the Alabama-Coosa system. It is 60 miles north of Atlanta 
near the town of Carters, Georgia. The reservoir is in both 
Murray and Gilmer Counties. 
Existing project. The authorized project consists of a 
1,950-foot long rockfill dam across the river, three saddle 
dikes on the left bank, a 258-foot long high-level, gated 
spillway on the left bank, a powerhouse on the right bank 
having two conventional units with a generating capacity 
of 125,000 kilowatts each and two pump-generating units 
of the same size, and a regulating dam 2,855 feet long with 
a gated spilway 208 feet long 1.5 miles downstream from 
the main dam. The lake has an area of 3,220 acres, at maximum 
power pool elevation 1,072, total capacity of 
472,800 acre-feet, of which 134,900 acre-feet is usable for 
power and 95,700 acre-feet reserved for flood control and 
242,200 acre-feet dead storage. For other information see 
description of Alabama-Coosa project. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance of the dam, 
reservoir, powerhouse, service and recreational activities 
and administration totaled $4,958,589. Gross power 
generation amounted to 411,135,000 kilowatt hours during 
FY 1989, of which 408,343,700 were delivered to 
Southeastern Power Administration. Recreation attendance 
during CY 1988 totaled 964,073 user days. 
Condition at end of fiscal year. Construction which 
commenced in April 1962 was essentially completed in 
September 1980. Total Federal cost of the existing project 
as of September 30, 1989 is $135,415,018, including 
$111,140,340 for new work and $33,087,925 for maintenance. 
53B. CLAIBORNE LOCK AND DAM, AL 
Location. The site is in Monroe County at mile 81.8 on 
the Alabama River, 15 miles northwest of Monroevine and 
5.7 miles upstream from the U.S. Highway 84 bridge. 
Existing project. The authorized project consists of a 
short earth dike on the right bank, a combination of a 
fixed-crest and gated spillway extending across the river 
10-24

MOBILE, ALABAMA DISTRICT 
channel and into the left bank, a navigation lock and 
mound on the left bank, and an earth dike extending across 
the left overbank to high ground. Normal upper pool is 
elevation 35 and the minimum pool will be elevation 32 to 
provide storage for reregulation of Millers Ferry 
powerplant releases. The 60-mile long reservoir has an 
area of 5,850 acres and a volume of 96,360 acre-feet. For 
other information see description of Alabama-Coosa 
projects. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance of the lock 
and dam totaled $500,700. Recreation attendance during 
CY 1988 totaled 652,000 user days. 
Condition at end of fiscal year. Construction began in 
May 1965 and was completed in FY 1976 at a total cost of 
$27,997,450. 
53C. COOSA RIVER, MONTGOMERY 
TO GADSDEN, AL 
Location. The Coosa River is one of the two major 
tributaries forming the Alabama River approximately 18 
miles northeast of Montgomery, Alabama. From its source 
at the juncture of the Etowah and Oostanaula Rivers in 
northwest Georgia, it flows southwesterly about 286 miles 
to join with the Tallapoosa River in forming the Alabama 
River. 
Existing project. The improvement of the Alabama- 
Coosa River for navigation to Rome, Georgia was 
authorized by Congress in the River and Harbor Act of 
1945. A report in House Document 320, transmitted to 
Congress on January 27, 1960, recommended that the 
navigation project for the Coosa River from Montgomery 
to Gadsden be accomplished after the waterway to 
Montgomery was assured.The plan of improvement identified 
in House Document 320 provided for a waterway 9 
feet deep with widths of 200 feet to Montgomery, 
Alabama, and 150 feet to Rome, Georgia. The waterway 
to Montgomery has essentially been completed. The plan 
for the Coosa River segment of the waterway between 
Montgomery and Gadsden was further modified by the 
WRDA of 1986 to authorize planning, engineering and 
design for the project generally in accordance with the 
plans contained in Design Memorandum No. 1, General 
Design, dated May 1982. Total Federal cost of the existing 
project as of September 30, 1989 is $14,986,400 for new 
work. 
53D. MILLERS FERRY LOCK AND 
DAM, AL 
Location. The site is in Wilcox County at mile 142.2 
on the Alabama River, 10 miles northwest of Camden, 
Alabama, and 30 miles southwest of Selma. 
Existing project. The project consists of an earth dike 
on the right bank, a concrete, gravity-gated spillway in the 
river channel, a lock and mound on the left bank, an earth 
dike extending downstream paralleling the lock, to the 
powerhouse intake structure; a powerhouse, and an earth 
dike extending to high ground on the left bank. Normal 
upper pool is at elevation 80. The powerplant contains 
three 25,000 kilowatt units. The 103-mile long reservoir 
has an area of 17,200 areas at normal pool level and a total 
capacity of 331,800 acre-feet. The lock chamber is 84 by 
600 feet with a 13-foot depth over the miter sills. For other 
information see description of Alabama-Coosa project. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance of lock, dam, 
powerhouse, reservoir, and administration cost 
$3,917,320. Gross power generation amounted to 
408,898,000 kilowatt hours during FY 1989, of which 
405,912,000 kilowatt hours were delivered to Southeastern 
Power Administration. Recreation attendance at William 
"Bill" Dannelly Reservoir during CY 1988 totaled 
2,445,718 user days. 
Condition at end of fiscal year. Construction began in 
April 1963. The lock was placed in temporary operations 
in June 1968 and opened to full use in November 1969. 
The powerhouse units were placed on line during April 
and May 1970. The project was essentially completed in 
1980. Total Federal cost of the project as of September 30, 
1989 is $63,125,300 for new work and $38,383,287 for 
maintenance, a total of $101,508,587. 
53E. ROBERT F. HENRY LOCK AN D 
DAM, AL 
Location. The site is in Lowndes and Autauga Counties 
at mile 245.4 on the Alabama River, 26 miles west of 
Montgomery. 
Existing project. The authorized project provides for a 
navigation lock, a gated spillway, and a power plant located 
at mile 245.4. The normal upper pool is at elevation 
125.0 and the minimum lower pool due to the Millers 
Ferry Lock and Dam is at elevation 80.0. The structures 
consist of earth dikes and a power plant on the right bank, 
a gated spillway in the river channel, a lock and mound on 
10-25

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
the left bank, and an earth dike extending upstream parallel 
to the Western Railway of Alabama. The total length of 
the structures is about 14,962 feet with maximum height 
above the foundation at the power plant intake about 101 
feet. The power plant contains four 17,000-kw. units. The 
88-mile long reservoir has an area of 12,300 acres at normal 
pool level and a total capacity of 234,200 acre-feet. 
The lock has a chamber 84 feet wide and 600 feet long and 
provides a 12-foot depth over the lower miter sill. For 
other information see description of Alabama-Coosa 
project 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance costs 
amounted to $2,289,096. Gross power generation 
amounted to 372,600,000 kilowatt hours during FY 1989, 
of which 370,849,000 kilowatt hours were delivered to 
Southeastern Power Administration. Recreation attendance 
during CY 1988 totaled 2,830,500 user days. 
Condition at end of fiscal year. Construction began in 
March 1966 and is essentially complete. The first powerhouse 
unit was placed in operation in June 1975, with the 
last unit on line in November 1975. Total Federal cost of 
the project as of September 30, 1989 is $106,782,654, including 
$83,360,800 for new work and $23,421,854 for 
maintenance. 
54. ALLATOONA DAM, COOSA 
RIVER BASIN, GA 
Location. The project is on Etowah River in Bartow 
County, Georgia, about 48 miles upstream from Rome, 
Georgia, about five miles due east of Cartersville, Georgia, 
and about 2,000 feet downstream from mouth of Allatoona 
Creek. The reservoir extends about 28 miles up the 
Etowah River at maximum power-pool elevation of 840 
feet above mean sea level. 
Existing project. The authorized project provides for a 
dam and reservoir for flood control, regulation of 
streamflow for navigation, and development of 
hydroelectric power. Height above the river bottom of the 
concrete, gravity-type dam is about 190 feet, from elevation 
690 feet to 880 feet national geodetic datum. The 
spillway, with crest at elevation 835, is controlled by nine 
tainter gates, 40 feet wide by twenty-six feet high, and two 
tainter gates, 20 feet wide by twenty-six feet high; having 
a combined discharge capacity of 321,000 cubic feet per 
second with the water surface at elevation 870.3 One 48- 
inch diameter sluicing conduit with a free discharge valve 
and four sluices, 5 feet-8 inches wide by 10 feet high, are 
included in dam. Installed generating capacity consists of 
two 36,000 kilowatt units and one 2,000 kilowatt unit, or a 
total of 74,000 kilowatts. Ultimate installed capacity will 
be 110,000 kilowatts. The reservoir, covering 19,200 acres 
at elevation 860, has a storage capacity of 670,000 acrefeet. 
The initial construction cost was $31,424,738, excluding 
the addition of recreation facilities at the 
completed project. (See Table 10-B for authorizing legislation.) 
Local cooperation. None required. (Sec. 2, Flood Control 
Act of June 28, 1938, applies). 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance of the dam, 
reservoir, powerhouse, service and recreational activities, 
and administration totaled $5,267,320. Gross power 
generation amounted to 132,174,000 kilowatt hours during 
FY 1989 of which 131,046,500 kilowatt hours were 
delivered to Southeastern Power Administration. Recreational 
attendance at Allatoona Lake during CY 1988 totaled 
13,320,349 user days. 
Condition at end of fiscal year. Construction of the 
existing project began in March 1944 and was completed 
in October 1955. Total Federal cost under existing project 
as of September 30, 1989 is $35,709,085 for new work 
and $69,392,007 for maintenance, a total of $105,101,092. 
55. APALACHICOLA, 
CHATTAHOOCHEE, AND FLINT 
RIVERS, AL, GA, AND FL 
Location. The Apalachicola River is formed at the 
southwest comer of the State of Georgia by the junction of 
the Chattahoochee and Flint Rivers and flows south 108 
miles emptying into Apalachicola Bay. Florida River 
enters the Apalachicola River from the east at mile 45.4 
and the River Styz also enters from the east at mile 36.7 
and Chipola River enters from the west at mile 28.2. (See 
Coast and Geodetic Survey Chart 11401.) The Chattahoochee 
River, 418 miles long, rises in northeast Georgia 
and flows southwesterly to West Point, and thence 
southerly to join the Flint River at the southwest comrner of 
Georgia, forming the Apalachicola River. (See Geological 
Survey maps for northwest Georgia.) The Flint River, 330 
miles long, rises in west central Georgia, flows generally 
southeasterly to Albany, and thence southwest to the 
southwest comer of the State, where it joins the Chattahoochee 
River to form the Apalachicola River. (See 
Geological Survey maps for southwest Georgia.) 
Previous project. For details see page 484 of Annual 
Report for 1963. 
10-26

MOBILE, ALABAMA DISTRICT 
Existing project. The authorized project provides for 
development of the Apalachicola, Chattahoochee, and 
Flint Rivers for navigation, flood control, hydropower, and 
recreation. Navigation features of the existing project consist 
of a continuous 9-foot by 100-foot channel in the 
Apalachicola River from the intersection of the Gulf Intracoastal 
Waterway to the confluence of the Chattahoochee 
and Flint Rivers, 104 miles, thence to 
Columbus, Georgia, on the Chattahoochee River, 164 
miles, and to Bainbridge, Georgia, on the Flint River, 29 
miles, and a 3-foot by 100-foot channel on the Flint River 
from Bainbridge to Albany, Georgia, 74 miles, thence a 
channel suitable for light draft vessels at moderate stage to 
Montezuma, Georgia, 79 miles to be accomplished by 
dredging, contract works, and construction of three locks 
and dams (Jim Woodruff, George W. Andrews, and Walter 
F. George) along the 9-foot depth channel, two multipurpose 
dams (West Point and Buford) on the 
Chattahoochee River. Three multipurpose dams (Lower 
Auchumpkee Creek, Lazer Creek, and Spewrell Bluff) on 
the Flint River were authorized in the Water Resources 
Development Act of 1986. The project also provides for 
minor improvements of certain streams tributary to the 
Apalachicola River, including a 9-foot by 100-foot side 
channel, approximately 2,000 feet long, from 
Apalachicola River to Apalachicola River Industrial Park 
at Blountstown, Fla. Plane side of reference is mean low 
water. Hydropower and flood control storage is provided 
at Sidney Lanier, Walter F. George, and West Point, and 
hydropower is provided at Jim Woodruff. For further 
details see Annual Report for 1962. The project was 
originally authorized in section 2 of the River and Harbor 
Act of 1945, was further modified by the WRDA of 1986 
(P.L. 99-662). (See Table 10-B for authorizing legislation.) 
Mean range of tide at the mouth of Apalachicola River 
is 1.6 feet. At the point where the river is formed the variation 
between low and high water is about 37 feet. On the 
Chattahoochee River, variation between average low and 
high water is about 20 feet, and extreme fluctuation is 65.3 
feet at Eufaula. On the Flint River the extreme fluctuation 
of stage due to flood is 40 feet, while average variation between 
low and high water is about 21.5 feet. A water 
supply study is currently being conducted on the upper 
portion of the ACF River System. 
Local cooperation. Fully complied with to date. 
Terminal facilities. About 200 feet of public docks, in 
addition to private wharves, are available at Apalachicola, 
Florida. There are numerous constructed and natural landings 
along the entire system for launching small craft. For 
details of other terminal facilities, which are considered 
adequate for existing commerce, see individual project 
descriptions. See also Table 10-M on locks and dams and 
multiple-purpose development included in existing 
project. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Contract dredging on the river system 
removed 767,858 cubic yards at a total cost of $1,199,000. 
George W. Andrews Lake recreational and resource 
management costs totalpd $377,200. Operation and maintenance 
of George W. Andrews Lock and Dam cost 
$338,400. All other costs for the project amounted to 
$1,718,007. Recreational attendance during CY 1988 totaled 
379,269 user days. 
Condition at end of fiscal year. Improvement of 
Apalachicola River channel by dredging to provide project 
dimensions throughout is complete. All major construction 
on Lake Sidney Lanier Dam, George W. Andrews Lock 
and Dam, Jim Woodruff Lock and Dam, and Walter F. 
George Lock and Dam, is complete. West Point is essentially 
complete with the exception of adding recreation 
facilities. Channel rectification in Apalachicola River was 
completed December 1970. More detailed information 
concerning condition at the end of fiscal year for individual 
locks and dams and multiple-purpose developments 
comprising the system is presented under their 
respective project titles elsewhere in this report. Total 
Federal cost under existing project as of September 30, 
1989 is $4,452,162 for new work and $88,390,651 for 
maintenance, a total of $92,842,813. (See Tables 10-A and 
10-M for fiscal year costs and summaries of overall 
project.) 
55A. BUFORD DAM, 
LAKE SIDNEY LANIER, GA 
Location. Buford Dam is on the Chattahoochee River 
about 348.9 miles above its mouth, 50 miles above Atlanta 
and five miles northwest of Buford, Georgia. The reservoir, 
Lake Sidney Lanier, extends about 47 miles upstream 
along the Chattahoochee River, and about 21 miles up the 
Chestatee River, which enters the Chattahoochee River 
14.5 miles above the dam. 
Existing project. The authorized project provides for a 
rolled-earth dam 1,630 feet long with crest at elevation 
1,106 feet national geodetic datum, or about 192 feet 
above streambed elevation; three earth saddle dikes with a 
total length of 5,406 feet; a chute spiliway with crest at 
elevation 1,085; a powerhouse in a deep cut with steel 
penstocks in tunnels, and concrete intake structure at the 
upstream end of the tunnels; and a flood control sluice tunnel 
paralleling the power tunnels. The Lake Sidney Lanier 
reservoir has a gross capacity of 2,554,000 acre-feet of 
which 637,000 acre-feet of storage is reserved for flood 
10-27

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
control storage. The power installations consist of one 
generating unit of 6,000 kilowatts and two units of 40,000 
kilowatts each, or a total of 86,000 kilowatts. (See Table 
10-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance cost 
$8,015,948. Gross power generation amounted to 
98,198,000 kilowatt hours during FY 1989, of which 
96,733,400 kilowatt hours were delivered to Southeastern 
Power Administration. Recreational attendance at Lake 
Sidney Lanier during CY 1988 totaled 17,102,500 user 
days. 
Condition at end of fiscal year. Construction commenced 
in March 1950 and was completed in June 1960. 
The reservoir was in useful operation for flood control in 
February 1956. The first power generating unit was placed 
on the line June 19, 1957; the second on July 26, 1957; 
and the third on October 10, 1957. Total Federal cost 
under existing project as of September 30, 1989 is 
$53,028,418 for new work and $88,390,651 for maintenance, 
a total of $141,419,069. (See also Table 10-M.) 
55B. GEORGE W. ANDREWS LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 46.5 miles above its mouth and about one mile 
below the town of Columbia, Alabama, near the head of 
Jim Woodruff Reservoir. (See Geological Survey maps for 
southeast Alabama). The pool extends up the navigation 
channel about 28 miles upstream to Walter F. George 
Lock and Dam. 
Existing project. This single-purpose project provides 
for a concrete fixed-crest spillway 340 feet long extending 
into the right bank with a crest at elevation 102 feet national 
geodetic datum, a concrete gate spillway adjacent to 
the lock 280 feet long with crest at elevation 82 feet national 
geodetic datum, a single-lift lock with usable chamber 
dimensions of 82 feet by 450 feet, and a maximum lift 
of 25 feet. Depths are 13 feet over the lower sill and 19 
feet over the upper sill at normal pool elevation. The underlying 
foundation is limestone. The project provides for 
maintenance and care. The House Committee on Public 
Works, by resolution adopted May 19, 1953, approved the 
plan as proposed by the Chief of Engineers for a high dam 
at Walter F. George site and a low dam at the Fort Benning 
site and a high dam at the upper Columbia site, construction 
of which was authorized by the 1946 River and 
Harbor Act as the initiation and partial accomplishment of 
the plan for full development of the Apalachicola, Chattahoochee, 
and Flint River system. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests must operate all 
movable span bridges, provide suitable public terminals, 
and hold the United States free from damages. These conditions 
are being complied with. 
Terminal facilities. At Columbia, Alabama, there is a 
public wharf with concrete deck for handling general 
cargo and a bulk petroleum terminal with an unloading 
dock. Facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Operation and maintenance of lock and dam cost 
$338,900. Recreational and resource management cost 
$377,200. Recreational attendance during CY 1988 totaled 
379,269 user days. Maintenance cost included under overall 
Apalachicola, Chattahoochee and Flint project. 
Condition at end of fiscal year. Construction of the 
lock and dam began in March 1959 and was completed in 
November 1963. (See also Table 10-M). 
55C. JIM WOODRUFF LOCK AND DAM, 
GA AND FL 
Location. The project is located on the Apalachicola 
River 107.6 miles above its mouth, about 1,000 feet below 
confluence of the Chattahoochee and Flint Rivers, and 1.5 
miles northwest of Chattahoochee, Florida. Reservoir extends 
about 46.5 miles upstream along the Chattahoochee 
River to the vicinity of Columbia, Alabama, and about 47 
miles upstream along Flint River, or 17 miles above 
Bainbridge, Georgia. (See Geological Survey maps for 
southwest Georgia.) 
Existing project. The authorized project provides for a 
concrete open-crest spillway 1,634 feet long on the right 
bank, with a crest at elevation 79 feet national geodetic 
datum; a single-lift lock with usable chamber dimensions 
of 82 by 450 feet, a maximum lift of 33 feet, and depth 
over the sills of 14 feet; a gated spillway of 766 feet long 
with the bridge at elevation 107 feet national geodetic 
datum, or about 67 feet above the streambed elevation; a 
powerhouse with an intake section constituting a portion 
of the dam; an earth section 506 feet long to accommodate 
the switchyard and substation; and an overflow dike section 
2,130 feet long on the left bank, with a crest at elevation 
85. The underlying foundation is limestone. At the 
normal pool elevation of 77, the reservoir has a total 
10-28

MOBILE, ALABAMA DISTRICT 
capacity of 406,160 acre-feet. The power installation consists 
of three units of 10,000 kilowatts each, or a total of 
30,000 kilowatts. (See Table 10-B for authorizing legislation.) 
Local cooperation. Required cooperation is being fulfilled. 
Easements for rights-of-way and spoil-disposal 
areas were provided as required along the Apalachicola 
River. Adequate public terminals were constructed by 
local interests at Bainbridge, Georgia, on the Flint River, 
and at Columbia, Alabama, on the Chattahoochee River. 
Facilities are being planned for other localities on the 
project. 
Terminal facilities. A public wharf with concrete deck 
for handling general cargo, a bulk storage terminal for 
petroleum, a grain elevator, and private riverside facilities 
at Bainbridge, Georgia, on the Flint River, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance cost 
$6,029,775. Gross power generation, Jim Woodruff 
Powerhouse, amounted to 202,719,000 kilowatt hours 
during FY 1989, of which 200,869,000 kilowatt hours 
were delivered to Southeastern Power Administration. 
Recreational attendance at Lake Seminole during CY 1988 
totaled 3,702,657 user days. 
Condition at end of fiscal year. Construction of the 
lock was commenced in 1947, and completed in 1957. The 
pool was opened to navigation in May 1954, and the pool 
was raised to project level in January 1957. The first 
power-generating unit was placed on-the-line on February 
1, the second on March 1, and the third on April 26, 1957. 
Total Federal cost under existing project as of September 
30, 1989 is $47,978,751 for new work and $62,357,100 
for maintenance, a total of $110,335,851. (See also Table 
10-M.) 
55D.WALTER F. GEORGE LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 75.2 miles above its mouth and about 1.5 miles 
above Fort Gaines, Georgia. (See Geological Survey maps 
for southw.est Georgia.) " 
Existing project. The authorized project provides for a 
concrete dam, gated spillway, and single-lift lock, with 
earth embankments at either side. The non-overflow section 
of the dam includes a powerhouse and an intake structure. 
The gated spillway is 708 feet long with a fixed crest 
at elevation 163 feet national geodetic datum. The two 
earth embankments, of almost equal lengths, have a total 
length of 12,128 feet, with a crest elevation at 215, and a 
maximum height of about 68 feet The nonoverflow section 
of the concrete dam is 200 feet long, with the deck of 
the powerhouse section at elevation 208. The lock, with 
usable chamber dimensions of 82 feet by 450 feet, has a 
lift of 88 feet with the normal upper pool elevation at 190. 
Depths are 13 feet over the lower sill and 18 feet over the 
upper sill at normal pool elevation. The underlying foundation 
is limestone. Total reservoir capacity is 934,400 
acre-feet, with 244,000 acre-feet reserved for power. The 
power installation consists of four units of. 32,500 
kilowatts each, or a total of 130,000 kilowatts. The project 
provides for maintenance, including operation and care. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Local interests must maintain and 
operate all utility and highway facilities which may be 
relocated or otherwise altered as part of the improvement, 
provide suitable public terminal facilities, and hold the 
United States free from damages. Local agencies and other 
organizations have indicated their willingness and ability 
to comply. 
Terminal facilities. Public wharves at Eufaula and 
Phenix City, Alabama, and Columbus, Georgia, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operation and maintenance cost for FY 
1989 was $7,664,649. Gross power generation amounted 
to 369,182,000 kilowatt hours, of which 366,566,000 
kilowatt hours were delivered to Southeastern Power Administration. 
Recreational attendance during CY 1988 totaled 
6,805,616 user days. Major rehabilitation costs 
$1,111. 
Condition at end of fiscal year. Construction was 
completed in 1963. The lock was opened to navigation in 
June 1963. The first power generating unit was placed onthe-
line in March, the second in May, the third in September, 
and the fourth in November 1963. Total Federal cost 
under existing project as of September 30, 1989 is 
$88,295,780 for new work, major rehabilitation cost 
$10,457,685 and $84,597,062 for maintenance, a total cost 
of $183,350,527. (See also Table 10-M.) 
55E. WEST POINT LAKE, 
CHATTAHOOCHEE RIVER BASIN, 
GA AND AL 
Location. The damsite is on the Chattahoochee River 
2.8 miles upstream from West Point, Georgia, 201.4 miles 
10-29

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
above the mouth of the Chattahoochee River, and 309.2 
miles above the mouth of the Apalachicola River. At the 
full power pool elevation of 635 feet above national 
geodetic datum, the reservoir would lie in Troup and 
Heard Counties, Georgia, and in Chambers and Randolph 
Counties, Alabama (See Geological Survey maps of Georgia 
and Alabama.) 
Existing project. The authorized project provides for 
flood control, power, recreation, fish and wildlife development, 
and streamflow regulation for downstream navigation. 
The project provides for a gravity-type concrete dam 
896 feet long with earth embankments at either end 1,111 
feet long on the east end and 5,243 feet long on the west 
end. The total length of the dam and spillway is 7,250 feet. 
The main dam consists of a concrete non-overflow section, 
185 feet long on the west side and an earth embankment 
retaining wall on the east side; a gravity concrete spillway 
390 feet long, including piers and abutments, with six 
tainter gates, each 50 feet by 41 feet. A monolith intakepowerhouse 
section and erection bay 321 feet long is constructed 
directly west and adjacent to the spillway. At the 
full power-pool elevation of 635 the reservoir provides a 
total storage of 605,000 acre-feet of which 307,000 acrefeet 
is usable. During the critical flood season the reservoir 
is operated with maximum power pool elevation at 625 
feet to provide flood storage between elevations 625 and 
635. The initial power installation of 73,375 kilowatts consisting 
of units 1, 2 and 3 were placed on operation in 
March and April, 1975. The ultimate installation is 
108,375 kilowatts. (See Table 10-B for authorizing legislation.) 
A flammable storage area will be constructed near 
the existing dam maintenance area. 
Local cooperation. None required. 
Operations and results during fiscal year. New work: 
Cultural Resources facility contract cost $35,616. 
Maintenance: Operation and maintenance of the project 
totaled $5,771,673. Gross power generation amounted to 
158,964,000 kilowatt hours during FY 1989, of which 
157,964,000 kilowatt hours were delivered to Southeastern 
Power Administration. Recreational attendance during CY 
1988 totaled 7,259,633 user days. 
Condition at end of fiscal year. Construction of the 
project, which was initiated in June 1966, was essentially 
complete at the end of FY 1984. Total Federal cost under 
existing project as of September 30, 1989 is $131,565,287 
for new work and $47,633,546 for maintenance, a total of 
$179,198,833. (See also Table 10-M.) 
56. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Mobile District monitors flood control operations of 
Alabama Power Company's Weiss, H. Neely Henry, and 
Logan Martin Dams on Coosa River, Alabama, and their 
Lewis Smith Dam on Sipsey Fork (headwaters of Black 
Warrior River, Alabama), for compliance with regulation 
plans prepared in accordance with Public Law 436, 83rd 
Congress, and Federal Power Commission licenses. Fiscal 
year cost for these activities on the Weiss, H. Neely 
Henry, and Logan Martin Dams are included under operation 
and maintenance costs for the Alabama-Coosa Rivers. 
Fiscal year cost for the Lewis Smith Dam is included 
under the overall operation and maintenance costs for the 
Black Warrior-Tombigbee Rivers System. 
57. DEAUTHORIZED PROJECTS 
(See Table 10-G.)
Miscellaneous 
58. FLOOD CONTROL AND 
COASTAL EMERGENCIES (FC & CE) 
Disaster Preparedness Program ............................ $659,985 
Emergency Operations..............................................42,645 
Advance M easures......................................................8,492 
Total FC & CE $711,122 
59. NATIONAL EMERGENCY 
PREPAREDNESS PROGRAM (NEPP) 
Mobilization Preparedness.................................... $121,770 
Government Preparedness ......................................... 96,785 
Emergency Facilities.........................................................38 
Total NEPP $218,593 
60. REGULATORY FUNCTIONS 
PROGRAM 
Permit Evaluation............................................... $1,600,225 
Enforcement..................... 165,739 
Studies.........................49,484 
Other Navigation Regulations .............. 15,765 
Total Regulatory $1,831,213 
10-30

MOBILE, ALABAMA DISTRICT 
General Investigations 
61. SURVEYS 
During FY 1989, costs of $1,028,540 were incurred as 
shown below: 
Flood Damage Preventive Studies ........................ $810,484 
Navigation Studies ......................................... .. 118,521 
Dam Safety ................................................................. 12,450 
Special Investigations ................................................ 42,888 
Coordination with Other Agencies, 
and non-Federal Interests..........................................32,514 
Federal Energy Regulatory Commission................1...1,526 
Review of Authorized Projects......................................157 
Total Surveys $1,028,540 
62. COLLECTION AND STUDY OF 
BASIC DATA 
Collection and study of basic data continued during the 
fiscal year with the initiation of Flood Insurance studies, 
the cost of which was reimbursable by FEMA. In addition, 
Flood Plain Management services were performed at a 
cost of $268,964. (See Table 10-P for listings of studies 
completed during FY 1989.) 
Costs incurred for environmental data studies total 
$1,479. 
The National Program for inspection of non-Federal 
dams cost $117. 
63. ADVANCE ENGINEERING 
AND DESIGN 
Gulfport Harbor, MS. The authorized plan of improvement 
consists of modifying the existing ship channel 
to 36 x 300 feet in Mississippi Sound, and 38 x 400 feet 
across the bar, with changes in the channel alignment and 
the entrance to the anchorage basin for safe and unrestricted 
navigation. Dredged material disposal will be in 
the Gulf of Mexico. 
The General Design Memorandum (GDM) was completed 
in June 1989, and approved by SAD in August 
1989. A Feasibility Review Conference was held in 
August 1989, and the Project Guidance Memorandum was 
received by the district in late November 1989. Revisions 
to the GDM, and preparation of the Project Management 
Plan are underway. Preparation of plans and specifications 
will be initiated as soon as additional funds are made 
available. Fiscal year 1989 expenditures for AE & D were 
$366,549. 
Pascagoula Harbor, MS. The authorized plan of improvement 
calls for. Deepening and widening the Gulf 
entrance channel to 44 x 550 feet, relocating that channel 
about 500 feet westwardly, and providing for future 
realignment as conditions warrant. Deepening the main 
ship channel in Mississippi Sound to 42 feet. Deepening 
and widening the Bayou Casotte Channel to 42 x 350 feet, 
and constructing a turning basin at the mouth of Bayou 
Casotte. Provide for bend widening at those locations 
presenting a problem to navigation and allow for reconfigurating 
the impoundment basin at the entrance channel. 
A resurvey of project economics and initial coordination 
on environmental issues have been initiated. Indications 
are that the project is economical. A letter of 
assurance was received from Jackson County Port 
Authority. Feasiblity study completed and the GDM 
preparation is nearing completion. Fiscal year 1989 expenditures 
for AE & D were $802,444. 
Montgomery to Gadsden, Coosa River Channel, AL. 
The authorized improvements consist of five (5) locks 
with chamber dimensions of 84 x 600 feet to be constructed 
in the existing Alabama Power Company dams 
which will provide a navigation channel 9 feet deep and 
150 feet wide from Montgomery to Gadsden, Alabama, 
and a barge canal on Black Creek (9' x 150') with a turnming 
basin of 350' x 600'. 
Based on data provided in the economic reevaluation, 
which is currently being finalized, there does not appear to 
be an economically favorable alternative for the development 
of navigation along the Coosa River Channel between 
Montgomery and Gadsden, Alabama. The final 
report is scheduled to be completed at the District level by 
January 1990. Fiscal year 1989 expenditures for AE & D 
were $198,062. 
Fort Toulouse, AL. The authorized plan consists of a 
curved 4500-foot long cutoff within the inside of the bend 
opposite the unstable slope, 3600 feet of riprap protection 
on the outside of the curved channel, and closure of the 
existing river channel adjacent to the Fort and Indian 
Mounds with two (2) dikes, filled in between with dredged 
material. The plan which will be recommended in the 
General Design Memorandum consists of approximately 
1200 feet of riprap bank protection adjacent to the Fort 
and Indian Mounds with a 700-foot free standing stone 
dike from the Indian Mound downstream. 
Plans and Specifications are scheduled to be initiated in 
FY 1990 and construction initiated in FY 1991. Fiscal year 
1989 expenditures for AE & D were $9,685. 
Moundville, AL. The authorized plan for bank protection 
consists of the upper 1600 feet of the project protected 
10-31

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
with riprap armor up to elevation 130.0 on a graded slope 
with a stone toe dike constructed at the base of the slope; 
and also the lower 800 feet of the project protected with 
sheet pile cells, back filled with grass covered pervious 
material. The General Design Memorandum plan consists 
of approximately 800 linear feet of riprap slope protection, 
with a stone toe dike, extending up the bank to elevation 
125.0 with protective vegetation extending to the top of 
the bank. Steeper upper bank sections will be protected by 
the use of a 250 feet long gabion wall. 
Plans and Specifications are scheduled to be initiated in 
FY 1990 and construction initiated in FY 1991. Fiscal year 
1989 expenditures for AE & D were $10,166. 
Total Fiscal year 1989 expenditures for advance engineering 
and design were $1,608,888. 
Panama City Beaches, FL. The authorized plan consists 
of the placement of a protective beach to elevation 4', 
with a storm berm to elevation 7', together providing a 
110-foot wide beach, with an artificial dune system having 
a top width of 30 feet at elevation 15 and stabilized by 
vegetation. 
A comprehensive damage survey was completed during 
FY 1989 as part of the reevaluation effort. Fully controlled 
aerial photographs were taken early in FY 89, first for use 
in the damage survey and also for later development of 
topographic maps. The Reevaluation Report was completed 
with favorable results and submitted in September 
1989. Fiscal year 1989 expenditures for AE & D were 
$221,983. 
64. CONTINUATION OF 
PLANNING AND ENGINEERING 
William Bacon Oliver Lock and Dam (Replacement), 
AL. The project is located at mile 338.1 on the 
Warrior-Tombigbee River System at Tuscaloosa, 
Alabama. The plan consists of replacing the existing 
Oliver Lock with a lock located 2,300 feet downstream. 
The replacement lock will have dimensions of 110 x 600 
feet. A fixed-crest spillway will extend 800 feet across the 
river. Construction was initiated in November 1986 and is 
scheduled to be completed in December 1992. Fiscal year 
1989 expenditures for CP & E were $4,488. (See also section 
6A Text). 
Bayou La Batre, AL. The authorized plan for the 
project consists of an 18-foot deep channel from the turning 
basin within Bayou La Batre, extending into Mississippi 
Sound then along the Gulf Intracoastal Waterway 
alignment connecting with the existing Pascagoula ship 
channel. Extensions of the existing channel to above the 
Highway 188 bridge at a depth of 14 feet and into Snake 
Bayou at a depth of 12 feet are also incrementally justified. 
The Final Feasibility report was completed, and has 
been through all required Washington level review. The 
project will be proposed for authorization in the 1990 
Water Resources Development Act (WRDA). 
Preconstruction Engineering and Design (PED) work is 
proceeding on schedule and will be completed in September 
1991. Provided that the project is authorized in the 
1990 WRDA, construction funding is appropriated in the 
1992 Fiscal Year, and the requirements of local sponsorship 
are met, project construction would likely begin in 
June 1992 and complete in November 1994. Fiscal year 
1989 expenditures for CP & E were $40,077. 
65. RIVERS AND HARBORS 
CONTRIBUTED FUNDS 
Contributed funds required for authorized Federal 
studies included $9,194 for Bayou La Batre, AL; $17,435 
for Mississippi Gulf Coast Area, MS; $48,458 for Valley 
Creek, AL; and $36,915 for Escatawpa River, MS; a total 
of $112,002 for contributed funds. 
10-32

TABLE 10-A 
See 
Section 
is Taext Project 
Navigation 
1. Apalachicola Bay 
2. Aquatic Plant 
Control 
(Contributed Funds) 
3. Bayou Coden, AL 
(Contributed Funds) 
(Contributed Funds) 
4. Bayou La Batre, AL 
(Contributed Funds) 
5. Biloxi Harbor, MS 
(Contributed Funds) 
(Contributed Funds) 
6. Black Warrior & 
Tombigbee Rivers, 
AL 
6A. Jackson Port 
Jackson, AL 
6B. Oliver Lock & Dam 
(Replacement), AL 
(Contributed Funds) 
7. Bon Secour River, 
AL 
(Contributed Funds) 
8. Dauphin Island, 
Bay, AL 
MOBILE, ALABAMA DISTRICT 
COST AND FINANCIAL STATEMENT 
Tetal Cet to 
Funding FY86 FY87 FY88 FY!9 Set304 1989 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Contrib. 
Cost 
New Woik: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contnib. 
Cost 
New Work: 
Approp. 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
683,000 
689,170 
27,000 
36,475 
322,000 
325,982 
326,000 
326,248 
140,000 
145,490 
2,001,000 
2,014,130 
166,536 
166,535 
468 
8,424,000 
9,317,927 
-62,000 
482 
2,850,000 
1,055,336 
23,000 
26,531 
55,000 
55,015 
93,000 
37,674 
16,000 
16,251 
50,000 
50,674 
-25,800 
723 
510,000 
510,101 
72,104 
72,105 
-4,000 
29,220 
14,942,300 
14,993,606 
50,000 
22,766 
6,205,000 
5,246,606 
10,181,000 
7,513,161 
72,000 
71,942 
47,900 
49,892 
76,085 
7,200 
7,808 
41,300 
40,995 
198,200 
198,391 
2,837 
13,494,000 
13,252,508 
70,000 
56,722 
16,866,000 
11,230,691 
16,866,000 
11,260,615 
19,200 
20,008 
10,000 
76,000 
76,043 
45,000 
-7,398 
58,000 
52,161 
119,000 
119,415 
1,273,000 
1,268,893 
13,772,500 
13,982,154 
45,000 
67,537 
4,150,000 
12,017,726 
4,150,000 
11,988,032 
94,500 
93,934 
30,00 
2,03,4611 
2,033,4611 
3,766,7071 
3,766.3301 
697,687 
634,524 
21,225 
21,225 
330701 
330,701 
812,733 
806,612 
100,000 
100,000 
50,000 
50,000 
311,095 
311,095 
3,227,152 
3,226,406 
10,5004 
10,500' 
1,431,9195 
1,431.919" 
9,671,306 
9,666,563 
102,600 
102,600 
238,640 
238,640 
88,461,935' 
88,461,935 
220,409,4765 
220,234,873" 
52,292,880 
52,292,880 
165,000 
147,026 
30,106,000 
29,550,360 
31,197,000 
30,761,808 
118,615 
118,615 
384,178 
383,453 
9,700 
9,700 
332,864 
10-33

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
In Text Project 
9. Dog and Fowl 
Rivers, AL 
(Contributed Funds) 
10. East Pass Channel 
Fromn Gulf of 
Mexico into Choctawhatchee 
Bay, FL 
(Contributed Funds) 
11. Fly Creek, AL 
12. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL 
and Mexican Border 
13. Gulfport Harbor, 
MS 
14. Mobile, Harbor, AL 
(Contributed Funds) 
15. Panama City 
Harbor, FL 
(Contributed Funds) 
16. Pascagoula Harbor, 
MS 
(Contributed Funds) 
17. Pensacola Harbor, 
FL 
(Cotributed Funds) 
Funding 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Apptrorxpp.. 
Cos 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.m: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maimnt.: 
Approp. 
New Work: 
Approp. 
Cost 
Maint.: 
Approp.. 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Main.: 
Approp. 
Cost 
Main.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Main: 
Contrib. 
Cost 
FY86 FY87 FY88 FY89 
.- 209143 32992 
163,000 
165,309 
217,000 
124,622 
922,000 
925,433 
8,150o 
55,893 
588,000 
768,130 
1,000 
15,356 
3,502,000 
3,515,992 
185,000 
187,812 
-112,000 
-70,000 
130,000 
89,275 
8,646,000 
8,796,672 
2,685,000 
1,968,039 
617,000 
620,887 
3,154,000 
3,162,738 
75,456 
75,456 
19,000 
20,328 
80,000 
79,698 
-20,000 
60,784 
91,000 
90,207 
25,257 
425,500 
337,172 
80,000 
79,255 
2,967,000 
2,926,095 
769,000 
652,807 
1,733,000 
1,733,914 
1,015,000 
444,538 
4,889,000 
4,759,579 
1,650,000 
1,612,400 
125,000 
123,729 
2,653,000 
2,593,971 
305,885 
279,250 
114,000 
114,524 
40,800 
41,305 
3,402 
81,200 
81,699 
112,200 
200,069 
40,400 
30,566 
10,000 
5,576,000 
5,577,136 
124,842 
2,220,600 
2,220,857 
24,003,000 
7,172,578 
7,324,000 
7,032,275 
2,171,000 
2,972,467 
1,045,700 
1,044,813 
2,083,200 
2,143.997 
940,413 
651,209 
887,100 
886,252 
28,77 
298,500 
298,700 
3,567 
11,851 
19,500 
15,287 
101,000 
101,321 
30,000 
39,851 
-10,000 
2,522,000 
2,554,913 
3,540 
415,000 
415,393 
1,000,000 
14,295,571 
5,680,300 
6,146,522 
5,070,000 
5,277,168 
93,000 
94,424 
516,000 
520,634 
163,162 
417,737 
981,000 
978,543 
312,350 
297,587 
10-34 
Total Cost to 
Sept , 30,1989 
327,949 
1,734,326 
1,733,643 
391,354 
391,354 
1,977,293 
1,991,932 
197,450 
195,250 
916,715 
916,715 
7,607,860 
7,607,517 
398,000 
398,000 
29,000 
29,000 
474,021 
473,033 
6,480,299 
6,480,2999 
56,293,72210 
56,277,9721o 
969,000n 
969,000n 
35,802,49812 
35,801,95412 
9,265,93513 
90,103,445 
100,419,48314 
100,407,099" 
16,858,500 
16,851,076 
1,638,0451' 
1,638,0451s 
8,351,03416 
8,349,84916 
80,000 
80,000 
6,572,9857 
6,S72,98517 
41,393,6201s 
41,391,9751 
3,220,884 
3,104,623 
1,469,6939 
1,469,69319 
8,159,338w 
8,155,547w 
312,350 
297,587

MOBILE, ALABAMA DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
In Text Project 
18. Perdido Pass 
Channel, AL 
(Contributed Funds) 
19. Tennessee- 
Tombigbee 
Waterway 
AL and MS 
Flood Control 
26. County Line 
Road Bridge, 
Itawamba Co., MS 
27. Cribbs Mill Creek, 
Tuscaloosa, AL 
28. Eslava Creek, 
Mobile, AL 
(Contributed Funds) 
29. Gulf Breeze, 
Santa Rosa Co., FL 
30. Hwy. 39 Bridge 
Gainesville, AL 
31. Hintonville Road 
Bridge, 
Perry Co., MS 
32. Hurricane Creek 
Prentiss Co., MS 
33. Leaf and Bowie 
Rivers, Hauttiesburg, 
34. Little Cove Creek, 
Glencoe, AL 
35. Magby Creek, 
Columbus, MS 
36. Mill Creek, 
Dalton, GA 
37. Murder Creek, 
Brewton, AL 
38. Okatibbee Dam, 
MS 
39. Raccoon Creek, 
Baconton, GA 
40. Sewerline Protection 
Valley, AL 
41. Sope Creek, 
Marietta, GA 
42. Sowashee Creek, 
Meridian, MS 
Fuanding 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
New Work: 
Approp. 
Cost 
NAepwp rWopo.rk: 
Cost 
NAewpp Wropo.rk: 
Cost 
New Work: 
Approp. Cost 
NAewpp Wroopr.k: 
Cost 
New Work: 
CAopsptrop. 
New Work: 
Approp. 
Cost 
Maint.: 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
FY86 FY87 FY88 FY89 
- -. - - 
936,000 
944,695 
26,496,000 
24,174,109 
13,159,425 
13,171,967 
80,000 
71,962 
100,000 
66,674 
50,000 
1,254 
1,340,000 
1,067,472 
80,000 
7,414 
20,000 
27,370 
10,000 
9,342 
550,000 
234,624 
119,906 
793,000 
877,052 
44,491 
150,482 
-20,000 
314,854 
28,000 
27,430 
31,600 
32,761 
- - 
-5,060,000 6,160,000 
15,256,360 7,898,488 
18,816,000 18,970,000 
18,765,500 18,516,261 
- 25,000 
- 10,100 
65,000 45,000 
58,145 48,771 
147,000 1,105,000 
181,328 974,600 
- 196,000 
- 88,000 
- 53,000 
- 27,945 
50,000 
62,867 4,269 
- 50,000 
- 10,109 
7,500 15,000 
7,018 
155,000 
290,108 113,765 
- 50,000 
62,866 35,773 
25.500 - 
4,703 9,606 
10,000 15,000 
12,502 162 
390,000 200,000 
427,607 186,048 
283 73 
1,031,800 1,050,000 
1,020,843 995,073 
36,800 48,000 
38,208 16,177 
-14,000- 
2,924- 
-165,000 95,000 
18,584 67,609 
350,000 2,400,000 
226,458 1,707,461 
10-35 
Total Cot to 
Sept. 30, 1989 
58,000 
57,732 
11,000,000 
5,105,015 
19,043,400 
19,614,116 
84,000 
20,397 
85,000 
44,453 
1,435,000 
293,640 
25,500 
93,500 
108,238 
1,974 
224,000 
29,554 
34,000 
14,278 
41,125 
15,000 
18,863 
63.750 
34,174 
10,000 
11,354 
215,536 
1,000,000 
1,057,387 
261,000 
46,637 
-63 
1,628 
25,000 
106,349 
1,100,000 
1,553,805 
629,860 
629,860 
6,065,817 
6,065,346 
510,000 
510,000 
10,325 
10,325 
1,012,378,2002 
1,001,496,66021 
104,512,156m 
104,194,50922 
109,000 
30,497 
469,327 
417,602 
2,884,121 
1,608,651 
196,000 
113,500 
146,500 
136,183 
100,000 
70,364 
274,000 
39,663 
56,500 
21,296 
1,585,000 
1,584,214 
145,000 
124,916 
169,250 
126,506 
265,000 
251,045 
1,240,000 
1,160,438 
9,739,528 
9,739,528 
11,369,692 
11,345,920 
423,300 
173,143 
180,937 
180,937 
1,540,000 
1,525,444 
3,850,000 
3,487,725

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
FY86 FY87 
- 60,000 
- - 
In Text Project Funding 
(Contributed Funds) New Work: 
Contrib. 
Cost 
43. Tallahalla Creek, New Work: 
Laurel, MS Approp. 
Cost 
44. Three Mile Creek, New Work: 
Mobile, AL Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
45. Tombigbee River New Work: 
(East Fork), Approp. 
MS and AL Cost 
Maint.: 
Approp. 
Cost 
46. Tombigbee River New Work: 
Tributaries, Approp. 
MS and AL Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
47. Upper Gordon Creek, New Work: 
Hattiesburg, MS Approp. 
Cost 
48. Village Creek, New Work: 
Birmingham, AL Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
49. Whorton's Bend Road, New Work: 
Etowah, Co., AL Approp. 
Cost 
Multiple Purpose Projects, Lock and Dam 
53. Alabama-Coosa New Work: 
Rivers, AL and GA Approp. 
Cost 
Maint.: 
Approp. 
Cost 
53A. Carters Dam and New Work: 
Reservoir, GA Approp. 
Cost 
Maint.: 
Approp. 
Cost 
53B. Claibome Lock and New Work: 
Dam, AL Approp. 
Cost 
53C. Coosa River, New Work: 
Montgomery to Approp. 
Gadsden, AL Cost 
53D. Millers Ferry Lock New Work: 
and Dam, AL Approp. 
Cost 
Maint.: 
Approp. 
Cost 
53E. Robert F. Henry New Work: 
Lock and Dam, AL Approp. 
Cost 
Maint.: 
Approp. 
Cost 
54. Allatoona Dam New Work: 
Coosa River Basin, Approp. 
GA Cost 
Maint.: 
Approp. 
Cost 
300,000 
218,592 
29,000 
125,000 
125,246 
3,027,000 
1,811,493 
77,000 
31,309 
50,000 
47,052 
10,000 
415 
4,866,800 
4,818,838 
3,064,800 
2,923,539 
153,000 
164,098 
2,297,000 
3,297,214 
50,000 
45,287 
2,691,000 
3,259,533 
-106,000 
866 
2,437,000 
2.507,840 
5,745 
38,776 
2,360,000 
2,392,094 
-187,000 
793 
1,844,575 
1,858,604 
7,671 
5,278,000 
5,746,764 
2,136 
2,585,000 
2,608,238 
2,024,800 
2,040,427 
5,315,800 
5,327,800 
10-36 
FY88 
430,000 
124,999 
42,000 
15,767 
4,348,000 
1,005,132 
436,000 
28,300 
141,000 
141,928 
2,932,600 
2,280,647 
60,000 
103,363 
225,000 
189,999 
71,000 
19,980 
5,360,000 
5,292,445 
3,773,000 
3,854,658 
FY89 
290,000 
59,025 
130,000 
46,312 
-2,300,000 
912,533 
112,458 
66,000 
66,102 
1,291,495 
250,000 
153,585 
2,310,000 
2,071,571 
647,000 
487,000 
320,000 
287,982 
8,300,100 
8,392,210 
4,905,500 
4,958,589 
3,780,000 
3,917,320 
2,220,000 
2,289,096 
4,977,900 
5,267,320 
Total Cost to 
Sept. 30,1989 
780,000 
184,025 
172,000 
62,080 
2,348,000 
2,136,257 
465,000 
140,758 
134,801 
134,801 
2,712,100 
2,711,371 
24,565,825 
23,606,623 
94,700 
63,342 
717,000 
608,276 
2,585,000 
2,308,622 
647,000 
487,000 
401,000 
308,377 
3,245,400 
3,245,400 
58,278,560 
58,235,133 
111,140,340 
111,140,340 
33,209,600 
33,087,925 
27,997.450 
27,997,450 
14,986400 
14,986,4003 
63,125,300 
63,125,300 
38,432,865 
38,383,287 
83,360,800 
83,360,800 
23,455,153 
23,421,854 
35,709,085" 
35,709,085- 
69,483,223 
69,392,007 
657 
3,106,500 
3,030,927 
2,286,000 
2,261,938 
6,100,000 
5,962,769 
-49,000

MOBILE, ALABAMA DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cot to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
55. Apalachicola, New Work: 
Chattahoochee Approp. - - - - 4,452,162 
and Flint Rivers, Cost - - - 4,452,162" 
AL and GA Maint.: 
Approp. 3,088,000 5,120,000 4,208,600 3,608,500 80,167,37 
Cost 3,909,709 5,198,930 4,159,830 3,633,107 80,125,563 
55A. Buford Dam New Work: 
Lake Sidney Approp. - - 53,030,038 
Laer, GA Cost -2,038 2,041 - - 38,418" 
Maint.: 
Approp. 7,152,000 9,729,900 8,394,600 7,533,100 68,501,507 
Cost 7,328,659 9,107,400 8,654,475 8,015,948 88,390,651 
55B. George W. Andrews New Work: 
Lock and Dam, Approp. - - - - 13,038,427k 
AL and GA Cost - - - - 13,038,427" 
Maint.: A.p3 0 30 30 30 30 
ACposptrop. 3o 3o 3o 3o so 
55C. Jim Woodruff Lock New Work: 
and Dam, GA and Approp. - - - 48,017,851 
FL Cost 796 - - - 47,978,7513 
Maint.: 
Approp. 4,768,000 6,451,800 7,131,800 5,728,500 62,432,380 
Cost 4,910,998 5,630,585 7,709,369 6,029,775 62,357,100 
55D. Walter F. George New Work: 
Lock and Dam Approp. - - - 88,295,78032 
Al and GA Cost7 - - - 88,295,780 
Maint.: 
Approp. 7,063,000 6,894,800 8,188,000 7,421,000 84,673,364 
Cost 7,347,633 6,823,873 8,140,417 7,664,649 84,597,062 
Major Rehab.: 
Approp. -700,000 -- 23,000 - 10,477,000 
Cost 468,153 4,240 204,570 1,111 10,457,685 
55E. West Point Lake, New Work: 
Chattahoochee River Approp. - - 11,400 - 131,568,7603s 
Basin, GA and AL Cost 1,432 9,149 19,162 35,616 131,565,287s 
Maint.: 
Approp. 5,266,000 6,368,800 6,009,000 5,753,000 47,762,100 
Cost 5,288,528 6,372,604 6,122,806 5,771,673 47,633,546 
1. Includes $134,613 for previous projects and $28,500 for DPR on 
Two-Mile. 
2. Includes $168,766 for previous projects. 
3. Includes $5,650 for previous projects. 
4. Cost for providing spoil dikes for work authorized by 1965 River and 
Harbor Act. 
5. Includes $44,382 for previous projects of which $5,000 was 
contributed funds. 
6. Includes $96,509 for previous projects of which $10,200 was 
contributed funds. 
7. Includes $606,931 for previous projects and $1,243,661 for 
recreational facilities on completed projects. 
8. Includes $50,000 for previous projects. 
9. Includes $45,605 for previous projects. 
10. Includes $65,137 for previous projects. 
11. Includes $269,017 for previous projects. 
12. Includes $2,312,297 for previous projects and $442,836 Special O 
and M Funds. 
13. Includes $6,683,104 for previous projects, $14,000 Public Work 
funds, and $41,242 Emergency Relief funds. 
14. Includes $4,096,681 for previous projects and $494,136 Special O 
and M funds. 
15. Includes $203,560 for previous projects, $581,959 Public Works 
funds, $457,467 rehabilitation of jetties under existing project and $48,001 
for Grand Lagoon modification. 
16. Includes $513,604 for previous projects. 
17. Includes $904,442 for previous projects. 
18. Includes $412,624 for previous projects, $124,565 Special O and M 
funds, and $829,472 Emergency Work Funds. 
19. Includes $594,688 for previous projects. 
20. Includes $126,649 for previous projects. 
21. Includes $1,993,000 transferred to National Park Service; $210,249 
GI funds expended during FY 1957 thn FY 1961. Previous project cost 
amounted to $197,651. 
22. Includes $234,331 for previous projects. 
23. Includes $3,692,483 for previous projects. 
24. Includes $2,978,050 for previous projects. 
25. Includes $3,347,489 for recreational facilities. 
26. Includes $1,883,193 Federal funds, $1,924 contributed funds for 
previous projects; and $809,553 for Laser Creek design and $301,310 for 
Rysco Channel. 
27. Includes $2,246,233 for previous projects. 
28. Includes $8,233,325 for recreaional facilities. 
29. Includes $84,014 for recreational facilities. 
30. Included under maintenance for overall Apalachicola, Chattahoochee 
and Flint Rivers project. 
31. Includes $1,515,822 for recreational facilities. 
32. Includes $2,441,029 for recreational facilities. 
33. Includes $35,045 for previous project costs. 
10-37

MOBILE, ALABAMA DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documaents 
Mar. 2, 1907 
Jan. 21, 1927 
Sep. 3, 1954 
Sep. 3, 1954 
Jul. 3, 1958 
Nov. 21, 19631 
Feb. 5, 19751 
Aug. 11, 1983 
Jul 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
Jun. 2, 19691 
Oct. 27, 1965 
APALACHICOLA BAY, FL. (See Section 1 of Text) 
Channel 18 feet deep through West Pass and Link Channels. 
10 feet deep across the inner bar, and 9 feet deep 
through Bulkhead Shoals. 
Modify project to provide for channel 10 feet deep from 
mouth of inner bar channel to Gulf via Link and West 
Pass Channels, and 10-foot depth in Bulkhead Shoals 
Channel. 
At Eastpoint, Fl., a channel 6 feet deep, 100 feet wide, 
and about 6,000 feet long, parallel to shore, with 
connecting channel 6 feet deep aqd 100 feet wide to St. 
George Sound, and at Apalachicola, Fl., a small-boat 
basin 200 feet and 9 feet deep, with a connecting 
channel 9 feet deep and 80 feet wide through Scipio 
Creek to the Apalachicola River. 
Modify project to provide for a channel 10 feet deep and 
100 feet wide from the 10-foot depth in Apalachicola 
Bay across St. George Island to within 300 feet of the 
Gulf shore, thence increasing uniformly in width to 200 
feet at shore and continuing at this width to the 10-foot 
depth in the Gulf, with two jetties extending from the 
dune line on St. George Island to the outer end of 
channel, and for abandonment of West Pass Channel upon 
completion of channel through St. George Island. 
Modify improvement of Apalachicola Bay, Fl., authorized 
by River and Harbor Act of Sept. 3, 1954 to provide 
that the Secretary of the Army shall reimburse local 
interests for such approved work as they may have done 
based upon the reduction in the amount of material 
which will have to be removed to provide project 
dimensions at such time as Federal dredging of the 
channel is undertaken. 
A channel 6 feet deep, 100 feet wide and about 1 mile long, 
parallel to shore at Two Mile, Fl., with a 6-by 100-foot 
connecting channel to water of the same depth in 
Apalachicola Bay. 
A channel 6 feet deep and 100 feet wide extending from the 
eastern end of the existing Two Mile channel and 
generally paralleling the shoreline for a distance of 
about 9,000 feet to intersect with the Gulf Intracoastal 
Waterway about 1,650 feet south of Gorrie Bridge at 
Apalachicola, and a breakwater built to elevation 4.0 
feet above mean low water along the seaward side of the 
existing channel parallel to the shore at Two Mile. The 
total length of the breakwater of about 6,150 feet, 
includes two 860-foot legs paralleling the existing 
entrance channel. 
Modify Eastpoint project to include breakwaters with a 
total length of 5,300 feet. 
AQUATIC PLANT CONTROL (See Section 2 of Text) 
Aquatic plant control for N.C., S.C., Ga., FL, AL, Ms., 
and La. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BAYOU CODEN, AL. (See Section 3 of Text) 
Channel4 by 40feet 
Channel 8 by 60 feet to connect with Bayou La Batre 
channel. 
BAYOU LA BATRE, AL. (See Section 4 of Text) 
A 12- by 100-foot channel from that depth in Mississippi 
Sound to a point about 2,800 feet south of the highway 
bridge, thence a channel 12 by 75 feet to the bridge, an 
overall distance of about 33,500 feet. 
H. Doc. 422, 59th Cong., 
1st Seas. 
H. Doc. 106, 69th Cong., 
1st Seas. 
H. Doc. 156, 82d Cong., 
1st Seas. 
H. Doc. 557, 82d Cong., 
2d Sess. 
DPR(Sec. 107) 
DPR (Sec. 107) 
DPR (Sec. 107) 
H Doc 37, 85th Cong., 
1st Sess. 
Public Law 87-874 
87th Cong. 
H. Doc. 251,89th Cong., 
1st Sess. 
H. Doc. 824, 77th Cong., 
24 Seuss. 
DPR (Sec 107) 
H. Doc. 327, 88th Cong., 
2d Sess. 
10-39 
TABLE 10-B

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
AUTHORIZING LEGISLATION 
Acts Work Authorized Doueta 
Jul. 3, 1930 
Jun 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
May 17, 1950 
Jul. 14, 1960 
Nov. 7, 1966 
Mar. 28, 19791 
Jul. 5, 1884 
Mar. 3, 1899 
Sep. 19, 1890 
Sep. 19, 1890 
Mar. 2, 1907 
Mar. 3, 1909 
Aug. 22, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
BILOXI HARBOR, MS. (See Section 5 of Text) 
Channel 10 feet deep and 150 feet wide from Mississippi 
Sound west and north of Deer Island to deep water in 
Back Bay of Biloxi 
Relocation of channel. 
Entrance channel 6 feet deep and 50 feet wide into Old 
Fort Bayou. 
Entrance channel 8 feet deep and 100 feet wide through 
Cranes Neck into Bayou Bernard. 
Maintain channel 6 feet deep and 40 feet wide from Biloxi 
Harbor to Ott Bayou. 
Continuous channel 12 feet deep from Mississippi Sound 
the Air Force terminal on Bayou Bernard via Bak Bay 
and Cranes Neck. 
A 23-mile-long through channel 12 feet deep and 150 feet 
wide from the Gulf Intracoastal Waterway through: 
Mississippi Sound, Biloxi Bay (east of Deer Island), Back 
Bay, Big Lake, and via land cut to Gulfport Lake, 
including a 500-by 2,600-foot turning basin in the lake, 
thence, a channel 12 by 100 feet from the western end of 
Gulfport Lake for about 2 miles to a 300- by 500- foot 
turning basin; adoption for maintenance of a 12- by 150- 
foot spur channel from the main channel in Biloxi Bay, 
westward about 1 mile to a 400- by 600- foot turning basin 
opposite Ott Bayou, and abandonment of the existing 6-by 
40- foot channel into Ott Bayou; continuation of maintenance 
of the 12- by 150-foot lateral channel westward about 2.2 
miles from the main channel in Biloxi Bay to a point 
opposite Oak Street; continuation of maintenance of the 
channel west of Deer Island. 
A channel 10 feet deep; 100 feet wide and 300 feet 
long extending northward from the Biloxi Lateral Channel 
and, into a rectangular basin approximately 300 feet 
by 370 feet. 
BLACK WARRIOR AND TOMBIGBEE RIVERS, AL. 
(See Section 6 of Text) 
Original appropriation for improving Black Warrior River. 
Original project for slack-water improvement authorized by 
Secretary of War, Apr. 19, 1887 
Construction of the first locks between Tuscaloosa and Demopolis. 
(Maintenance of the section of Tombigbee River below 
lock 1 to its mouth (66 miles) included in the existing project.) 
Construction of locks and dams 1, 2, and 3. Merging of 
the individual project for the Black Warrior and Warrior 
Rivers and the Tombigbee River below Demopolis. 
Construction of locks and dams 14, 15,16, and 17. 
Provided for reconstruction of obsolete structures, modified 
in plan and location, to provide efficient and economical 
maintenance and operation. 
Lift of lock 17 changed to 63 feet, and construction of locks 
and dams 18 and 19 eliminated from the project 
Extension of slack-water improvement to Sanders Ferry 
on Mulberry Fork and Nichols Shoal on Locust Fork. 
Raising of various dams 2 feet and raising the lock walls 2 
feet at lock 1 to provide a minimum depth of 8 feet at 
low water, widening the channel to 150 feet where 
practicable. 
For snagging Mobile River from the mouth of Chickasaw 
Creek to the junction of the Alabama and Tombigbee Riven. 
H. Doc. 754.69th Cong., 
2d Ses. 
H. Dec. 639.75th Cong., 
34 Se. 
H. Doc. 258.76th Cong., 
1st Sess. 
H. Doc. 326.76th Cong., 
1st Sess. 
H. Doc. 256. 81st Cong., 
1st Seus. 
H. Doc. 271, 86th Cong., 
2d Ses. 
H. Doc. 513, 89th Cong., 
2d Sess. 
DPR (Sec. 107) 
Annual Report, 1887, 
pt. 2, P. 1302. 
H. Doc. 178, 56th Cong., 
2d Seas., and Annual 
Re ort 1901, pt. 3, 
p. 1858 
HD. ec. 165, 57th Cong., 
1st Seas., and Annumal 
Report, 1902, p. 1293 
Public Law 317 
H. Doc. 72, 62d Cong., 
1st Seas. 
Annual Report, 1918, 
p. 876 
H. Doc. 728, 71st Cong., 
3d Seas. 
10-40

TABLE 10-B (Continued) 
MOBILE, ALABAMA DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Aug. 30, 1935 
Jun. 26, 1934 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 14, 1960 
Dec. 21, 1982 
Jul. 30, 1983 
Nov. 17, 1986 
Nov. 17, 1986 
Oct. 18, 1986 
Nov. 17, 1986 
Aug. 15, 1985 
May 16, 19631 
Mar. 2, 1945 
Sep. 3, 1954 
Increase channel dimensions to 9 by 200 feet; construct 
crest gates at lock and dam 17; add flashboards at all 
dams; Sunflower Bend Cutoff. 
Construction of a lock and dam below Tuscaloosa to replace 
original locks and dams 10, 11, and 12 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers harbors. 
Recreation facilities. 
Construction of a lock and dam near Demopolis to replace 
existing dams 4, 5, 6, and 7. 
Provide increased spillway capacity at dam 1. 
Coffeeville Lock and Dam Wildlife Refuge. 
Provides for a wider navigation opening at the Franklin 
Ferry Bridge, Jefferson County, Al. 
Authorized to widen, as necessary for safe passage. 
the navigation opening of Franklin Ferry Bridge, Jefferson County, Al. 
Conduct a feasibility study of protection 
from erosion problems on the southemrn bank from 
river mile 253 to river mile 255. 
MOUND STATE PARK (See Section 23 of Text) 
Correct erosion problems along the 
banks of the Warrior River in order to 
protect Mound State Park, near 
Moundville, Alabama. 
JACKSON PORT, AL (See Section 6A of Text) 
Construct a spur canal 9 feet deep, 280 feet 
wide, and 680 feet long in conjunction with the 
realignment project on the existing navigation project. 
(Jackson Port) 
OLIVER LOCK AND DAM (REPLACEMENT), AL 
(See Section 6B of Text) 
Construction of a lock and dam to replace the 
William Bacon Oliver Lock and Dam. 
Construction and land acquisition for Oliver Lock 
Replacement 
BON SECOUR RIVER, AL. (See Section 7 of Text) 
A 10-by 100-foot channel from Gulf Intracoastal Waterway 
through Bon Secour Bay to mouth of Bon Secour River and 
extending up river to vicinity of Swift's Landing, thence 6 by 
80 feet up river to a point 600 feet above OakLanding, with two 
turning and maneuvering areas 150 feet wide and 1,100 to 1,200 
feet long opposite Swift's Landing and ice loading 
dock. Overall length of improvement is about 4.7 miles. 
DAUPHIN ISLAND BAY, AL. (See Section 8 of Text) 
A channel 7 feet deep and 150 feet wide from Mobile Bay to 
an anchorage basin of same depth, about 7 acres in area, in 
marsh just north of Fort Gaines on Dauphin Island; a 
channel 4 feet deep and 40 feet wide from anchorage basin 
to Dauphin Island Bay; and a jetty and revetment to protect 
entrance channel; and (b) an anchorage basin 7 feet deep and 500 
feet square at Dauphin Island Village, with an entrance channel 
of like depth, 100 feet wide and about 8,300 feet long, 
extending to 7-foot hydrographic contour in Mississippi Sound. 
H. Doc. 56, 73d Cong., 
1st Sea., and Rivers 
and Harbors Committee 
Doc. 45.73d Cong. 
Rivers and Harbors 
Committee Doc. 26. 
74th Cong., 1st Sess. 
H. Doc. 276, 76th Cong., 
1st Sess. 
H. Doc. 382, 76th Cong., 
1st Seas. 
S. Doc. 50, 86th Cong., 
1st Seas. 
Public Law 97,377 
Public Law 98-63 
Water Resource Development 
Act of 1986 
(P.L. 99-662) 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
Energy and Water 
Development Appropriation 
Act 1987 
(P.L. 99-591) 
Water Resources 
Development Act of 
1986 (P.L. 99-662) 
The Supplemental 
Appropriations Act, 
1985 (P.L. 99-88) 
DPR (Sec. 107) 
H. Dc. 333, 76th Cong., 
1st Seas. 
H. Doc. 394, 82d Cong., 
2d Sess. 
10-41

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
AUTHORIZING LEGISLATION 
Acts Work Authorized Doe 
May 19, 19691 
Jul. 3, 1930 
Oct. 24, 1951 
Oct. 27, 1965 
Oct. 1, 1980 
May 17, 1950 
Jun. 25, 1910 
Aug. 30, 1935 
Jun. 25, 1910 
Aug. 30, 1935 
Jul. 3, 1930 
Jul 3, 1930 
Jul3, 1930 
Jul 23, 1942 
Jun. 17, 1943 
Mar. 2, 1945 
May 17, 1950 
Nov. 7, 1966 
Mar. 3, 1899 
DOG AND FOWL RIVERS, AL (See Section 9 of Text) 
To provide stiall craft navigation on west side of Mobile Bay. 
EAST PASS CHANNEL FROM GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL. (See Section 10 of Text) 
Maintenance of 6-foot channel by 100-foot channel from 
Choctawhatchee Bay into Gulf. 
Maintenance of 12-foot channel from Choctawhatchee Bay 
into Gulf, and maintenance of 6-foot channel into Old Pass Lagoon. 
Construction of twin jetties. 
(Present project dimensions.) 
Modifications to provide a channel length of approximately 3,800 
feet in lieu of 2,000 feet from the East Pa Channel into 
Old Pass Lagoon, with no changes in width and depth. 
FLY CREEK, FAIRHOPE, AL (See Section 11 of Text), 
A channel 6 feet deep, 80 feet wide, and about 1,650 
feet long from 6-foot depth in Mobile Bay to a turning 
basin of same depth, 100 feet wide and 350 feet long, in Fly Creek. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL., AND MEXICAN BORDER 
(Mobile District) (See Section 12 of Text) 
APALACHICOLA RIVER TO ST. ANDREW BAY, FL. 
A channel 5 feet deep at mean low water and 65 feet 
wide at the bottom. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
CHOCTAWHATCHEE BAY TO WEST BAY, FL. 
A channel 9 feet deep at mean low water and 100 feet wide 
at the bottom. 
A channel 6 feet deep at mean low water, with no 
reference to width. 
CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FL. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
PENSACOLA BAY, FL., TO MOBILE BAY, AL. 
A channel 9 feet deep at mean low water aid 100 feet 
wide at the bottom. 
MOBILE BAY, AL, TO NEW ORLEANS, LA. 
A channel 300 feet wide and 10 feet from the 10 
foot contour in Mobile Bay to the 10-foot contour 
in Mississippi Sound. 
A channel 100 feet wide and 9 feet deep from Lake 
Pontchartrain to Mississippi Sound. 
APALACHEE BAY, FL., TO NEW ORLEANS, LA. 
A channel 12 feet deep and 125 feet wide at mean low 
water, except in the section between Mobile, Al., 
and New Orleans, La., where the width is to be 
150 feet. 
Conditional acquisition of Gulf County Canal, Fl. 
and enlargement of the canal to 9 feet deep and 100 
feet wide. 
Construction of a movable span in the Georgia, Florida 
& Alabama R.R. bridge crossing the Ochlockonee River. 
Abandonment and closure of original channel between 
Big Lagoon and Pensacola Bay and construction of a 
new channel to enter the bay north of original 
entrance. 
Authorized enlargement of Gulf County Canal to 12 by 
125 feet. 
GULFPORT HARBOR, MS. (See Section 13 of Text) 
A channel 19 feet deep and 300 feet wide from the 
anchorage basin at Ship Island to Gulfport, Ms., and an 
anchorage basin next to the shore end 19 feet deep and not 
less than 2,640 feet by 1,320 feet in area. 
10-42 
DPR (Sec. 107) 
H. Doc. 209, 70th Congress 
1st Sees. 
H. Doc. 470, 81st Cong., 
2dSeas. 
H. Doc. 194. 88th Cong., 
2d Ses. 
Energy and Water Development 
Approprisation 
H. Doc. 194, 81st Cong., 
lit Sess. 
H. Doc. 670, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Comnmittee Doc. 52, 
72d Cong., 2d Sees. 
H. Doc. 259, 72d Cong., 
1st Seas. 
H. Doc. 565, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 42, 
73d Cong., 2d Seses. 
H. Doc. 42, 71st Cong., 
1st Seas. 
Rivers and Harbors 
Committee Doc. 4, 
71st Cong., 1st Sess. 
H. Doc. 341,71st Cong., 
2d Sess. 
Public Law 675, 77th 
Cong., 2d Seas., and 
H. Doc. 96, 79th 
Cong., 1st Sess. 
H. Doc. 257, 76th Cong., 
1st Seas., and Public 
Law 75, 78th Cong. 
1st Seas. 
H. Doc. 442, 76th Cong., 
1st Seas. 
H. Doc. 325, 81st Cong., 
1st Seas. 
Public Law 89-789, 89th 
Cong. 2d Ses. 
H. Dc. 120, 55th Cong., 
3d Sess.

TABLE 10-B (Continued) 
Acts 
MOBILE, ALABAMA DISTRICT 
AUTHORIZING LEGISLATION 
Work Authorized 
Mar. 2, 1907 
Feb. 27, 1911 
Jan. 21, 1927 
Jul. 23, 1930 
Jun. 30, 1948 
Jul. 3, 1958 
Aug. 15, 1985 
Nov. 17, 1986 
Nov. 17, 1988 
Aug. 26, 1937 
Mar. 2, 1945 
Sep. 3, 1954 
Sep. 3, 1954 
Jul. 26, 1970 (SR) 
Dec. 15, 1970 (HR) 
Combined Ship Island Pass with Gulfport Harbor project. 
Increased depth to 26 feet and width to 300 feet across 
ShipIsland Bar anddepth to 19 feet in channel from 
anchorage basin at Ship Island to anchorage basin at Gulfport. 
Authorized relocation of channel across Ship Island Bar. 
Increased depth to 27 feet and width to 300 feet across Ship 
Island Bar, 26 feet deep and 220 feet wide through Ms. 
Sound and depth of 26 feet in the anchorage basim at Oulfport. 
Increased depth of 32 feet and width to 30 feet across Ship 
Island Bar, 30 feet deep and 220 feet wide through Ms. Sound 
and a depth of 30 feet in the anchorage basin at Gulfport 
Maintenance of the existing commercial rsmall-boat harbor 
and an approach channel 100 feet wide and 4,300 feet 
long, from deep water in Ms. Sound to the small-boat 
basin, all at a depth of 8 feet. 
Modify the existing Ship Channel to 36 x 300 feet in Mississippi 
Sound, and 38 x 400 feet across the bar, with 
changes in the channel alignment and the entrance to 
the anchorage basin for safe and unrestricted navigation. 
Modification of FY 1985 Supplemental Apopriations Act. 
Dredged material from project shall be disposed of in 
open water in the Gulf of Mexico in accordance with all 
provisions of Federal law. 
Modify the WRDA of 1986 and authorize 
disposal of dredged material in open waters 
of the Gulf of Mexico; and by Thin-layer disposal 
in Mississippi Sound under a demonstration program. 
MOBILE HARBOR, AL. (See Section 14 of Text) 
For improvement of Threemile Creek by snagging from 
Mobile River to the Industrial Canal. 
Adoption of existing channel through Garrows Bend from 
Choctaw Point to Arlington pier, 27 feet deep and 150 
feet wide, with 2 turnin; basins. Adoption of the 
existing channel alongside Arlington pier from the 
of Garrows Bend Channel, 27 feet deep and 150 feet wide. 
A channel 25 feet deep and generally 500 feet wide in 
Mobile River from the highway bridge to the mouth of 
Chickasaw Creek, then 25 feet deep and 250 feet wide in 
Chickasaw Creek to a point about 400 feet below Shell Bayou. 
Enlarging Mobile Bay Channel to 42 by 600 feet, 
Enlarging Mobile Bay Channel to 40 by 400 feet. 
Deepening Mobile River Channel below highway bridge to 
40 feet over present widths, including existing 
turning basins and anchorage areas. Widening river 
channel opposite Magazine Point to provide a 40- by 800- 
by 1,400-foot turning basin. The turning basin was 
further modified for maintenance by SAD letter of 
27 November 1973 under authority contained in 
ER-1130-2-307 to increase the turning basin's 
dimensions to 1000' x 1600'. 
Closure of Garrows Bend Channel by construction and 
operation of an earth-filled causeway across said channel 
(work to be done by local interests). 
To provide a channel 40 feet deep and 400 feet wide from 
the main ship channel in Moble Bay and extending 
northwesterly for about 5.3 miles to the shore of Mobile 
Bay including an anchorage and turning basin 
near the shoreline, thence a land-cut 40 feet deep, 300 feet 
wide and about 1.9 miles long to and including a 
trapezoidal turning basin 40 feet deep and 
approximately 42 acres, 40 feet deep; a barge channel 
12- by 100-feet extending 6500-feet and terminating in a 
300-foot by 300-foot terminal basin 
H. Doc. 2, 60th Cong., 
1st Seas. 
H. Doc. 692, 69th Cong., 
2d Sess. 
H. Doc. 112, 81st Cong., 
1st Seass. 
S. Doc. 123, 84th Cong., 
2d Sess. 
The Supplemental 
Appopriations 
Act, 1985 (P.L 99-88) 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
Water Resources 
Development Act 
of 1988 
(P.L. 100-676) 
Rivers and Harbors 
Committee Doc. 69, 
74th Cong., 1st Sess. 
H. Doc. 739, 79th Cong., 
2d Sess. 
H. Dec. 74, 83d Cong., 
1st Sess. 
H. Doc. 74, 83d Cong., 
2d Sess. 
(Under provision of 
Section 201 of the 
1965 Flood Control 
Act) 
10-43 
Documents

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
AUTHORIZING LEGISLATION 
Acts Work Authorized Doamnemats 
Aug. 15, 1985 
Nov. 17, 1986 
Nov. 17, 1986 
Aug. 30, 1935 
Mar. 2, 1945 
Jun. 30, 1948 
Mar. 23, 1967' 
Jun. 14, 1972 
Mar. 4, 1913 
Mar. 4, 1915 
May 17, 1950 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 14, 1960 
Jul. 14, 1967 
Oct. 23, 1962 
Deepen and widen entrance channel over the bar to 57 by 
700 feet, a distance of about 7.4 miles, deepen 
and widen Mobile Bay Channel from mouth of 
bay to south of Mobile River, 55 by 550 feet, a distance 
of about 27.0 miles, deepen and widen an additional 
4.2 miles of Mobile Bay Channel to 55 by 650 feet, 
provide 55 foot deep anchorage area and turning 
basin in vicinity of Little Sand Island, and construct 
a 1710 acre disposal area adjacent to the Brookley 
Industrial Complex. 
Modification of FY 1985 Supplemental Appropriations Act. 
Dredged material from project shall be disposed of in 
open water in the Gulf of Mexico in accordance with all 
provisions of Federal law. 
PANAMA CITY BEACHES, FL 
Shoreline protection to provide a 110-foot 
wide beach with an artificial dune system 
and stabilization of vegetation. 
PANAMA CITY HARBOR, FL. (See Section 15 of Text) 
Channels 27 and 29 feet deep. Abandonment of project 
adopted by act of June 25, 1910. 
Maintenance of a channel in Watson Bayou 100 feet wide 
and 10 feet deep from that depth in St. Andrew Bay to 
the highway bridge. 
Channels 32 and 34 feet deep. 
A channel 8 by 100 feet in Grand Lagoon from St. Andrew 
Bay to a point about 2,400 feet east of State Highway 
392. Bridge with branches to serve shore facilities 
which terminate at the bridge. 
Channels 38, 40, 42 feet deep. 
PASCAGOULA HARBOR, MS. (See Section 16 of Text) 
Provides for through channel from the Gulf to mile 4 on 
Dog River, 25 by 300 feet through Horn Island Pass. 
thence 22 by 225 feet across Mississippi Souind and up 
150 feet in Pascagoula River above bridge, and up Dog 
River to mile 4, all subject to financial participation 
by local interests. 
Waived requirement for financial participation by local 
interests. 
63d Cong., 2d Sess. 
Cutoff channel, 12 by 125 feet, from State Highway 63 
bridge to mile 4 on Dog River, via Robertson and 
Bounds Lakes. 
Modification to provide for channel dimensions of 35 by 
325 feet through Horn Island Pass, thence 30 by 275 feet 
across Mississippi Sound and up Pascagoula River to the 
railroad bridge, and a turning basin just below the 
bridge. 
Reimbursement of local interests for work done on Dog 
River cutoff ($44,000). 
Modification to provide for maintenance of 12- by 125-foot 
channel to mile 6 on Dog River, and maintenance of 30- by 
225-foot side channel from main ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, thence 
30 by 300 feet in Bayou Casotte to a turning basin of the 
same depth 1 mile above the mouth. 
Deepening the Horn Island Pass channel to 38 feet and 
deepening the main ship channel in Mississippi Sound, 
the river channel to the railroad bridge, and the 
turning basin all to 33 feet 
Enlarging Horn Island Pass Channel to 40 by 350 feet 
provision of an impounding area adjacent to and east of 
channel 40 feet deep, 200 feet wide, and about 1,500 feet 
The Supplemental 
47ians Act, 
1985 .L99 -88) 
Water Resources 
Developmnt Act 
of 1986 
(P.L 99-662) 
Water Resources Developmeant 
Act of 1986 
(P.L 99-662) 
H. Doc. 33, 73d Cong., 
1st Seas. 
H. Dec. 555, 76th Cong., 
3d Sess. 
H. Dec. 559, 80th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Dec. 196, 924 Cong., 
2d Sess. 
H. Doc. 682, 62d Cong., 
2d Sess. 
River and Harbor 
Committee Doc. 12, 
H. Doc. 188, 81st Cong., 
lst Sess. 
H. Dec. 98, 86th Cong., 
H. Doc. 98, 86th Cong., 
1st Sess. 
Chief of Engineers Report 
dated Nov. 3,1960. 
H. Dec. 560, 87th Cong., 
2d Sess. 
10-44

TABLE 10-B (Continued) 
MOBILE, ALABAMA DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 11, 19831 
Nov. 17, 1986 
Jun. 13, 1902 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 27, 1962 
Oct. 27, 1965 
Jul. 24, 1946 
long, enlarging main channel in Mississippi Sound and 
river channel to railroad bridge to 38 by 350 feet, and 
deepening turning basin in river and Bayou Casotte 
channels and basin to 38 feet. 
Modification to provide for channel dimensions 12 x 80 feet 
extending about 2,750 feet from deep waters in the 
Pascagoula River into Krebs Lake to a turning basin, 
thence, along the south bank of the lake a channel with 
dimensions of 10 x 60 feet terminating at a second 
turning basin, a distance of about 2,750 feet. The 
project was constructed by hydraulic dredging with 
the disposal placed in an unpland diked area. 
Deepen and widen gulf entrance channel to 44 by 550 feet; 
widen Horn Island channel to 600 feet, relocating that 
channel about 500 feet westwardly; deepen Mississippi Sound 
portion to 42 feet; widen and deepen Bayou Casotte to 42 
350 feet and construct turning basin. Disposal of all new 
work material in Gulf of Mexico. 
PENSACOLA HARBOR, FL. (See Section 17 of Text) 
A channel 30 feet deep at mean low water and 500 feet 
wide from the Gulf of Mexico to the dock line at the 
east end of the city of Pensacola, and also provided 
that $150,000 may be used in constructing or purchasing 
a seagoing suction dredge. 
Modified the existing project for the present inner 
channels and the deepening of the entrance channel to 32 feet. 
Improvement of Bayou Chico. 
Maintenance of the entrance channel from the Gulf of 
Mexico to lower Pensacola Bay, a distance of about 5 
miles to dimensions of 35 feet deep and 500 feet wide; 
maintenance of a channel along the south side of the 
aircraft carrier mooring basin, a distance of about 2.5 
miles, to dimensions of 33 feet deep and 300 feet wide; 
a bay channel 33 feet deep, 300 feet wide, and about 2.1 
miles long; parallel approach channels to opposite ends 
of the inner-harbor channel, about 1.3 and 1.4 miles in 
length, each 33 feet deep, 300 feet wide, and flared at 
the junctions with the inner-harbor channel; and 
deepening the existing 500-foot wide inner-harbor channel 
to a depth of 33 feet and lengthening it to 3,950 feet, 
PERDIDO PASS CHANNEL, AL. (See Section 18 of Text) 
A 12- by 150-foot channel stabilized by twin rubblemount 
jetties, from the Gulf of Mexico into Perdido Pass, 
thence 9 by 100 feet into Perdido Bay with a spur channel 
of the same dimensions into Terry Cove. 
TENNESSEE-TOMBIGBEE 
WATERWAY, AL AND MS (See Section 19 of Text) 
A waterway connecting Tennessee and Tombigbee Rivers via 
East Fork of Tombigbee River, Mackeys and Yellow Creeks. 
Plan of improvement consists of three sections: river section 
9- by 300-foot channel for 149 miles between Demopolis 
and Amory, Ms.; canal section, 12 by 300 feet for 46 miles 
from Amory to Bay Springs; divide section 12 by 300 feet 
(except in the 27 mile-long divide cut in which bottom width 
be 280 feet) for 39 miles from Bay Springs through dividing 
ridge to Tennessee. Total lift of 341 feet to be accomplished 
by 10 locks. Total length of project is 234 miles. 
10-45 
DPR (Sec. 107) 
Water Resources Development 
Act of 1986 
(P.L 99-662) 
H. Dec. 253, 72d Cong., 
1st Seas. 
Rivers and Harbors 
Committee Doc. 96, 
74th Cong., 2d Sess. 
H. Doc. 528, 87th Cong., 
2d Sess. 
H. Doc. 94, 88th Cong., 
2d Sess. 
H. Doc. 486, 79th Cong., 
2d Sess.

TABLE 10-B (Continued) 
REPORT TO THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 17, 1986 
Oct. 7, 19884 
Nov. 17, 19872 
Sep. 10, 19872 
Oct. 7, 19884 
Jul. 2, 1986 
Oct. 7, 19884 
Oct. 7, 19884 
Oct. 3, 19852 
Aug. 15, 1985 
Oct. 13, 19882 
Oct. 13, 19882 
Apr. 18, 19862 
Oct. 23, 1962 
Oct. 13, 19882 
TENNESSEE-TOMBIGBEE WILDLIFE MITIGATION 
Acquire from willing sellers in a timely manner at fair 
market value 88,000 acres of land for mitigation of wildlife 
losses resulting from construction and operation of the 
project for the Tennessee-Tombigbee Waterway. 
COUNTY LINE ROAD BRIDGE, ITAWAMBA CO., MS 
(See Section 26 of Text) 
Provides protection for both banks and the channel at the bridge 
crossing Mantachie Creek. 
CRIBBS MILL CREEK, TUSCALOOSA, AL 
(See Section 27 of Text) 
Channel modification of about 7,300 feet of the creek. Modification 
consists of widening the existing channel. 
ESLAVA CREEK, MOBILE, AL 
(See Section 28 of Text) 
Channel enlargement, bank stabilization measures, 
and increasing the size of the box culvert at Airport Boulevard by 
adding an additional barrel. 
GULF BREEZE, SANTA ROSA CO., FL 
(See Section 29 of Text) 
Emergency action to stop shoreline erosion around a water 
supply pumping station for the City of Gulf Breeze, FL. 
HIGHWAY 39 BRIDGE, GAINESVILLE, AL 
(See Section 30 of Text) 
Slope protection for a 2000-foot reach of the east bank of 
the Tombigbee River, immediately upstream of the 
existing Highway 39 Bridge. 
HINTONVILLE ROAD BRIDGE, PERRY CO., MS 
(See Section 31 of Text) 
Provides protection for the bridge side slopes channel bottom, 
and to realign the channel thru the center span of the bridge. 
HURRICANE CREEK, PRENTISS CO.,MS 
(See Section 32 of Text) 
Provides emergency streambank protection to the banks and the 
bottom of the channel to retard erosion at the Marietta-Hazeldell 
Road Bridge crossing Hurricane Creek. 
LEAF AND BOWIE RIVERS, HATTIESBURG, MS 
(See Section 33 of Text) 
Channel snagging; overbank clearing within the flood plains; 
riprap protection of the Southern Railroad and River 
Avenue Bridge piers, and removal of the Petal sewage 
lagoon. Work also includes installation of a flood 
warning system. 
LITTLE COVE CREEK, GLENCOE, AL (See Section 34 of Text) 
The project consists of enlargement and realignment of 
10,840 feet along Little Cove Creek to provide a channel 
bottom width of 25 feet and an average depth of 6 feet. Also 
included in the project were associated channel and overbank 
clearing and bridge modification work. 
MAGBY CREEK, COLUMBUS, MS (See Section 35 of Text) 
For clearing and snagging Magby Creek from mile 0.83 upstream 
to mile 2.06. 
MILL CREEK, DALTON, GA (See Section 36 of Text) 
For clearing and snagging Mill Creek from its mouth to downstream 
face of Willowdale Drive or a distance of 8.6 miles. 
MURDER CREEK, BREWTON, AL (See Section 37 of Text) 
Non-structural project providing for the alleviation of 
flood problems at Brewton by the removal of 31 damageable 
structures from the 10-year flood plains of Murder 
and Burnt Corn Creeks. 
OKATIBBEE LAKE, MS (See Section 38 of Text) 
Provides for a dam and reservoir for flood control 
water supply, water quality control, and recreation. 
RACCOON CREEK, BACONTON, GA 
(See Section 39 of text) 
Raise about 1500 feet of South Jackson Street Bridge to elevation 176.0 
feet NOVE. Clear and snag from Hwy. 3 to U.S. Hwy. 19. 
Water Resources Development 
Act of 1986 
(P.L. 99-662) 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 205) 
DPR (Sec. 14) 
Urgent Supplemental 
Appropriation Act, 1986, 
(Public Law 99-349). 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 205) 
Supplemental Appropriation 
Act of 1985, 
(Public Law 99-88). 
DPR (Sec. 205) 
DPR (Sec. 205) 
DPR (Sec. 205) 
H. Doc. 549, 87th Cong., 
2d Sess. 
DPR (Sec. 205) 
10-46

TABLE 10-B (Continued) 
MOBILE, ALABAMA DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Apr. 18, 19854 
Aug. 23, 19842 
Nov. 17, 1986 
Sep. 30, 19882 
Nov. 17, 1986 
Aug. 18, 1941 
Jul. 23, 1958 
Jul. 8, 1980 
Oct 13, 19882 
Nov. 17, 1986 
Oct. 13, 19884 
Mar. 2, 1945 
Jun. 28, 1954 
SEWERLINE PROTECTION, VALLEY, AL 
(See Section 40 of Text) 
The project provides for the restoration of approximately 1600 linear 
feet of streambank. This will consist of placing 1550 cubic yards of 
riprap on 4445 square yards of filter fabric. 
SOPE CREEK, MARIETTA, GA (See Section 41 of Text) 
The project provides for flood control measures along Sope Creek in Cobb 
County, Georgia, by clearing and snagging and evaluation of 13 structures. 
SOWASHEE CREEK, MERIDIAN, MS (See Section 42 of Text) 
Channel enlargement, and clearing and snagging over a reach of 10.5 miles. 
One railroad bridge and several highway roads and bridges and utilities 
will require will require modification for the channel improvement. 
Development of recreation facilities. 
TALLAHALLA CREEK, LAUREL, MS 
(See Section 43 of Text) 
Channel clearing and snagging with overbank clearing of brush and 
trees less than 4 inches diameter for a distance of 30 feet on each bank. 
THREEMILE CREEK, MOBILE, AL (See Section 44 of Text) 
Channel widening and deepening from about 2,000 feet downstream 
of Stone Street to a point about 6,300 feet upstream of Interstate 65 
or a total distance of 5.6 miles. Development of recreational facilities. 
TOMBIGBEE RIVER (EAST FORK), MS AND AL 
(See Section 45 of Text) 
Provides for alleviation of floods from the Tombigbee River 
by clearing, snagging, and excavation of 13 cut-off 
channels, and other related channel improvements. 
TOMBIGBEE RIVER TRIBUTARIES, MS AND AL 
(See Section 46 of Text) 
Provides for improvement of 22 tributaries of Tombigbee 
River. 
Extends project limits on Twenty Mile Creek and 
eliminates local cooperation for this remedial work. 
UPPER GORDON CREEK, HATTIESBURG, MS 
(See Section 47 of Text) 
Real Estate acquisition of nine (9) residences; habitat mitigation 
and channel enlargement. 
VILLAGE CREEK, JEFFERSON COUNTY, 
BIRMINGHAM, AL (See Section 48 of Text) 
Basically nonstructural and includes evacuating 642 structures in six 
separate neighborhoods from floodplain; enlarge 2 miles of channel 
and relocate necessary facilities; Install flood warning devices. 
WHORTON'S BEND ROAD, ETOWAH CO., AL 
(S Section 49 of Text) 
Pruvides emergency streambank protection along the left bank 
of the Coosa River to retard erosion on Whorton's Bend Road. 
MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
ALABAMA-COOSA RIVERS, AL. AND GA. 
(See Section 53 of Text) 
Provides for full development of Alabama-Coosa Rivers and 
tributaries for navigation, flood control, power, recreation, and 
other purposes. 
Authorized construction of Carters Lake, GA 
Claibomrne Lock and Dam, AL, Jones Bluff Lock and 
Dam, AL, and Millers Ferry Lock and Dam, AL. 
Suspended comprehensive plan to permit non-Federal interests 
to develop Coosa River by constructing series of dams. 
DPR (Sec. 14) 
DPR (Sec. 205) 
Water Resources 
Development Act of 1986 
(P.L. 99-662) 
DPR (Sec. 205) 
Water Resources 
Development Act 
of 1986 (P.L 99-662) 
Special Report on Record 
in OCT. (Public Law 222,) 
77th Cong., 1st Sess. 
H. Doc. 167, 84th Cong., 
1st Sess. 
Supplemental Appropriations 
and Recession Act, 
DPR (Sec. 205) 
1980 (P.L. 96-304) 
Water Resources 
Development Act 
of 1986 (P.L 99-662) 
DPR (Sec. 14) 
H. Doc. 414, 77th Cong., 
1st Sess. 
Public Law 436, 83rd 
Cong. 
10-47

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
AUTHORIZING LEGISLATION 
Acts Work Authorized Docmmemnts 
May 25, 1982 
Nov. 17, 1986 
Nov. 17, 1986 
Aug. 18, 1941 
Dec. 22, 1944 
Mar. 2, 1945 
Jul. 24, 1946 
Dec. 22, 1944 
Jan. 27, 1981 
Nov. 17, 1986 
Jul. 24, 1944 
Jul. 24, 1946 
Dec. 22, 1944 
Dec. 22, 1944 
May 19, 1953 
Oct. 23, 1963 
Designated change of name from Jones Bluff to 
Robert F. Henry Lock and Dam. 
Modification to the plan for the Coosa River segment 
of the waterway between Montgomery and Gadsden, AL to carry 
out planning, engineering, and design in accordance 
with the Montgomery to Gadsden, Coosa River Channel, 
AL, Design Memorandum No. 1., General Design, dated May 1982. 
FORT TOULOUSE (See Section 23 of Text) 
Preserve and protect the Fort Toulouse National Historic 
Landmark and Taskigi Indian Mound by instituting 
bank stabilization measures. 
ALLATOONA LAKE, COOSA RIVER BASIN, GA 
(See Section 54 of Text) 
Provides for dam and reservoir for flood control, regulation 
of stream flow for navigation, development of hydroelectric 
power and recreation. 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
RIVERS, AL., GA. AND FL. (See Section 55 of Text) 
Development of Apalachicola, Chattahoochee, and Flint 
Rivers for navigation, flood control, hydropower, and recreation. 
Modified general plan for full development of 
Apalachicola, Chattahoochee, and Flint River System and authonzed 
construction of Lake Sidney Lanier multipurpose reservoir. 
Authorized recreation facilities. 
Modified the existing project to provide for nine foot 
deep by 100-foot wide side channel into the 
Apalachicola River Industrial Park, Blountstown, F1. 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
Modified Rivers and Harbors Act of 1945 to restore and 
maintain access to bendways and interconnecting waterways 
in the course of routine mamintenance dredging; and 
to acquire lands for and to construct, operate, and 
maintain water-related public use and access facilities. 
LAKE SIDNEY LANIER, GA. (See Section 55A of Text) 
Provision of recreation facilities. 
GEORGE W. ANDREWS LOCK AND DAM, AL. AND GA. 
(See Section 55B of Text) 
Construction of high dam at Walter F. George site 
and low dam at George W. Andrews site. 
Provided recreation facilities. 
JIM WOODRUFF LOCK AND DAM, GA. AND FL. 
(See Section 55C of Text) 
Provided recreation facilities. 
WALTER F. GEORGE LOCK AND DAM, AL, AND GA. 
(See Section 55D of Text) 
Authorized construction of high dam at Walter F. George 
site and low dam at Columbia site. 
WEST POINT LAKE, CHATTAHOOCHEE RIVER 
BASIN, GA. AND AL. (See Section 55E of Text) 
Authorized construction for flood control, power 
recreation, fish and wildlife development, and 
streamflow regulation for downstream navigation. 
1. Authorized by Chief of Engineers under Section 107 of 1960 
River and Harbor Act, as amended. 
2. Authorized by Chief of Engineers under Section 205 of 
Flood Control Act of 1948, as amended. 
3. Authorized by Chief of Engineers under Section 208 of Flood 
Control Act of 1954, as amended. 
4. Authorized by Chief of Engineers under Section 14 of Flood 
Control Act of 1946, as amended. 
10-48 
S.2034 97th 
Cong., 2d Seas. 
Water Resources 
Developnent Act 
of 1986 
(P.L 99-662) 
Water Resources 
Develomnent Act 
of 1986 
(P.L 99-662) 
Public Law 228, 77th 
Cong., 1st Seas. 
H. Dc. 674, 76 Cong., 
3d Seas. 
H. Doc. 342, 76th Cong., 
1st Sess. 
H. Doc. 300, 80th Cong., 
1st Seas. 
DPR (Sec. 107) 
Water Resources 
Developnent Act 
of 1986 
(P.L. 99-662) 
H. Doc. 300, 80th Cong., 
1st Seas. 
H. Comm. on 
Public Works 
H. Doc. 570, 87th Cong., 
2d Sess. 
1

MOBILE, ALABAMA DISTRICT 
TABLE 10-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 22 of Text) 
For Last 
Full Report 
See Annual 
Report For 
Blackwater River, FL 
Bluff Creek, MS1 
Cahaba River, AL2 
Cadet Bayou, MS 
Carrabelle Bar and Harbor, FL 
Choctawhatchee River, FL and AL 
Escambia-Conecuh Rivers, AL and FL 
Holmes Creek, FL 
LaGrange Bayou, FL 
Leaf and Chickasawhay River, MS2 
Noxubee River, MS1 
Ochlockonee (Ochlociey) River, GA and FL1 2 
Old Town Creek, MS" 
Oostanaula and Coosawattee River, GA1 2 
Panacea Harbor, FL 
Pascagoula River, MS 
Pass Christian Harbor, MS 
Port St. Joe Harbor, FL 
Removing Water Hyacinths 
St. Marks River, FL 
Tallapoosa River, AL2 
Tombigbee River at Columbus Port, MS 
Upper Chipola River, FL, from Marianna to 
its mouth1 2 
Wolf and Jordan Rivers, MS 
1. Abandonment recommended in H. Doc. 467, 69th Cong. 
2. Uncompleted portion of project deauthorized by H. Doc. 
1981 
1963 
1894 
1984 
1979 
1973 
1981 
1931 
1972 
1919 
1902 
1900 
1887 
1907 
1979 
1956 
1976 
1984 
1984 
1965 
1893 
1988 
Consta 
$41 
4' 
8' 
48: 
17: 
20 
28S 
2? 
4
3: 
12 
1
5 
1,96( 
1,71( 
4. 
50 
1941 
1979 
Cost to September 30,1989 
Operation and 
ruction Maintenance 
1,650 $302,539 
1,000 6,883 
5,000 
7,921 1,137,227 
1,627 379,413 
1,885 291,694 
8,499 1,102,094 
8,562 36,800 
9,496 133,038 
3,090 42,676 
7,528 14,472 
5.000 v,v 3,000 
2,656 
2,383 
5,000 
9,313 
0,862 
0,809 
3,972 
D,500 
36,781 
29,195 
92,443 
179,535 
139,653 
2,947,5113 
1,100,471 
84,115 
63,193 
481,515 
96- 157, 1st Session. 
3. Includes $80,000 contributed funds. 
TABLE 10-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT 
(See Section 26 of Text) 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation ad 
Report For Construction Maltemance2 
Harrison County, MS, shore protection 1 1953 $1,133,000 
1. Completed. 
2. Operation and maintenance is the responsibility of local 
interests. 
10-49

TABLE 10-E 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 48 of Text) 
For Last Cost to September 30,1989 
Full Report 
See Annual Operaon 
Report For Construction Malate 
Alabama River at Montgomery, AL 1965 $144,194 - 
Armuchee Creek, GA 1966 115,547- 
Beaver Creek, Montezuma, GA 1958 149,815- 
Big Brown Creek, Prentiss Co, MS 1987 137,500 
Biloxi River at Lorraine Road, Harrison County, MS 1985 132,174 - 
Black Creek, Gadsden, AL 1953 125,389- 
Black Warrior River, U.S. Hwy. 11 Bridge, Fosters, AL 1986 181,500- 
Boligee Canal, Boligee, AL 1987 178,600 
Burketts Creek, Amory, MS 1984 1,366,454- 
Chattahoochee River, Eufaula, AL 1988 206,600- 
Chickasaw Bogue Creek, U.S. Highway 43 Bridge, Linden, AL 1985 121,718- 
Clanton, AL 1964 274,024- 
Collinsville, AL 1940 71,119- 
Goodfood Creek, Chickasaw Co., MS 1988 91,500- 
Gordons Creek, Hattiesburg, MS 1985 802,026- 
Houlka Creek, Chickasaw & Clay Counties, MS 1982 238,219 
Houston School Rd. Bridge, Itawamba Co., MS 1988 59,300- 
Interstate 59 Bridges, Fosters, AL 1987 155,200- 
Lake Douglas, Decatur County, GA 1970 164,998- 
Leaf River, County Road Bridge, Mahned, MS 1986 231,618- 
Little Cove Creek, Glencoe, AL 1965 113,849- 
Martin Creek, Prentiss County, MS 1988 78,500- 
Murder and Burnt Corn Creeks, Brewton, AL 1980 190,974 
Murder Creek, East Brewton, AL 1986 903,474- 
Noxubee River Relief Bridge, Shuqualak, MS 1988 119,500- 
Old Hwy. 82 Bridge, Columbus, MS 1987 143,500- 
Osborne Creek, Highway 362 Bridge, Prentiss County, MS 1985 250,000- 
Prattville, Autauga Creek, AL 1946 649,280- 
Pumpkinvine Creek, Emerson, GA 1985 85,029 - 
Rome, Coosa River, GA 1955 384,550- 
Sowashee Creek, Meridian, MS 1956 142,637- 
Sun Creek, Okibbeha County, MS 1984 55,569- 
Tallabinella Creek, Chickasaw County, MS 1988 81,000- 
Tallahala Creek, Pascagoula River, MS 1988 3,945,757 
Town Creek, Americus, GA 1965 340,409- 
Trim Cane Creek, Okibbeha County, MS 1984 145,519- 
Trussville, AL 1965 141,334- 
Twenty Mile Creek, Airport Road Bridge, Frankstown, MS 1986 215,860- 
West Point, Chattahoochee River, GA 1955 599,637- 
Wolf Creek, Highway 362 Bridge, Prentiss County, MS 1985 114,753 
Wolf Creek, U.S. Hwy. 45 Bridge, Prentiss County, MS 1986 154,641 
Yellow Jacket Creek, Hogansville, GA 1966 330,734 
1. Engineering, design, supervision, and administration (no 2. Operation and maintenance is the responsibility of local interests. 
construction work has been done. Includes $17,000 for 
pre-authorization studies. 
TABLE 10-G DEAUTHORIZED PROJECTS 
Year of Last Deauthorization Date 
Project Type Full Report Document Deauthorized 
Bayou Galere, MS1 Navigation 1946 H. Doc. 192,94th Cong., Aug 5, 1977 
1st Seas., as amended. 
GIWW; Apalachicola Bay to Navigation 1986 Public Law 99-662, Nov 17, 1986 
St. Marks River, FL 99th Congress 
Lazer Creek Lake, GA Hydroelectric power 1986 Public Law 99-662, 99th Congress Nov 17, 1986 
Lower Auchumpkee Creek, Hydroelectric power 1986 Public Law 99-662, Nov 17, 1986 
GA 99th Congress 
Pensacola Harbor Modification, FL Navigation 1986 Public Law 99-662, Nov 17, 1986 
99th Conrs 
Spewrell Bluff Lake, GA Hydroelectric power 1986 Public Law 99-662, Nov 17, 1986 
99th Congress 
1. H. Doc. 96-157 deauthorized uncompleted portions of certain 
projects as shown in Table 10-C. 
10-50

MOBILE, ALABAMA DISTRICT 
TABLE 10-H NAVIGATION WORK UNDER SPECIAL AUTHORIZATON 
(See Section 23 of Text) 
Fiscal Year 
Study Authority 1989 Costa 
Bayou Cumbest, Jackson Co., MS 107 $1,122 
Eastpoint Channel, FL 107 2,063 
Little Lagoon, Gulf Shores, AL 107 20,136 
Ocean Springs Harbor, MS 107 9,519 
Scipio Creek, Franklin, FL 107 25,135 
Soldiers & Palmetto Creek, AL 107 23,084 
South Fork, Bon Secour River, AL 107 5,642 
Weeks Bay, AL 107 19,993 
Total $106,6941 
1. Excludes construction costs of $11,851 for Dog River Channel, AL, and $32,992 for Fort Gaines, Dauphin Island, AL. These 
costs are reflective in respective project cost 
TABLE 10-I BEACH EROSION CONTROL PROJECT UNDER 
SPECIAL AUTHORIZATION (See Section 25 of Text) 
FIscal Year 
Study Authority 1989 Costs 
Boggy Bayou Shoreline, Valparaiso, FL 103 2 
Total $243 
TABLE 10-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 46 of Text) 
Fiscal Year 
Study Authority 1989 Costs 
Five Mile, Brookside, AL 205 256 
Greens Creek, Petal, MS 205 41,860 
Indian Camp Creek & Tribs, Noxubee, MS 205 2,733 
IrondaleAL 205 52,941 
Mill Creek, Sumrall, MS 205 4,484 
Mixons Creek, Lamar Co., MS 205 10,642 
Proctor Creek, Atlanta, GA 205 4,362 
Silver Creek, Rome, GA 205 2,937 
Tishtony Creek, Mantachie, MS 205 3,374 
Alabama River, Selma, AL 14 15,433 
Boggy Bayou Shoreline, Valpariso, FL 14 7,750 
Portersville Bay Shoreline, AL 14 2 
Total $170,076 
10-51

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 10-K RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 24 of Text) 
Cost Durh 
Project Date of Survey ical Year 
Bayou La Batre, AL July, 1989 20,740 
Bayou Texar, FL April, 1988 2,148 
Biloxi Harbor, MS June, 1989 670 
Blackwater River, FL August, 1989 10,452 
Bon Secour, AL May, 1989 639 
Cadet Bayou, MS January & August, 1989 9,837 
Carrabelle Harbor, FL November, 1989 7,778 
Escambia Bay, FL April, 1989 24,224 
Fly Creek, AL April, 1989 188 
La Grange Bayou, FL August, 1988 2,372 
Panama City, FL September, 1989 295 
Pensacola Harbor, FL November, 1989 435 
St. Marks River, FL October, 1989 16,760 
Wolf and Jordan Rivers, MS August, 1989.9 
Total $106,078 
TABLE 10-L ALABAMA-COOSA RIVERS, ALA. AND GA. 
DEVELOPMENT PROPOSED UNDER EXISTING PROJECT 
(See Sections 49 and 50 of Text) 
Clalborne Millers Ferry Robert F. Henry Carters Allatoonma 
Proposed Structures Lock and Dam Lock and Dam Lock and Dam Lake Dam3 Dam 
Miles above mouth of river 81.11 42.21 245.41 26.82 47.84 
Nearest town Claibomrne, Ala. Camden, Ala. Benton, Ala. Carters, Ga. Cartersville, Ga. 
Distance (miles) 7 10 3 2 4 
Greatest lock length available 
for full width (feet) 600 600 600 - - 
Width of lock chamber (feet) 84 84 84 - - 
Maximum lift (feet) 30 48 47 - - 
Elevation of normal pool surface 
(mean sea level) 35 80 125 1072 840 
Depth over sills at low water 13 Upper 15 Upper 15 -- 
(feet) Lower 13 Lower 12 
Character of foundation Rock Rock Rock Rock Rock 
Kind of spillway Gated and Gated Gated Gated Gated 
Fixed Crest 
Height of dam (feet) 95.5 99.5 94 451 190 
Type of construction Concrete Concrete Concrete Rock-fill Concrete 
Earth Core 
Total reservoir capacity 
(acre-feet) 96,360 331,800 234,200 472,800 670,050 
Power development (kw) - 75,000 68,000 500,000 74,000 
Percent complete 100 100 100 100 100 
Cost to date: $27,997,450 $63,125,300 $83,360,800 $111,140,340 $35,709,085 
1. Above mouth of Alabama River (river miles) 
2. Above mouth of Coosawattee River (river miles). 
3. Reregulation dam (Carters) 25.3 (river miles). 
4. Above mouth of Etowah River (river miles). 
5. Includes cost of added recreation facilities as shown in Table 10A. 
10-52

MOBILE, ALABAMA DISTRICT 
TABLE 10-M 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, ALA., GA., 
AND FLA., LOCKS AND DAMS AND MULTIPLE-PURPOSE 
DEVELOPMENT INCLUDED IN EXISTING PROJECT 
(See Section 51 of Text) 
Existing Projects 
Jim George W. Walter F. Buford Dam 
Woodruff Andrews Geoge Lake 
Lock Lock Lock West Point Sidney 
and Dam and Dam and Dam Lake Lanier 
Miles above mouth 107.61 46.52 75.02 201.42 348.32 
Nearest town Chattahoochee FL., Columbia, Al. Ft. Gaines, Ga. West Point, Ga. Buford, Ga. 
Distance (miles) 1 1 2 2.8 5 
Greatest lock length 450 450 450 - - 
available for full width (feet) 
Width of chamber (feet) 82 82 82 -- 
Maximum lift (feet) 33 25 88 - - 
Elevation of normal pool 77 102 190(Summer) 635(Summer) 1071(Summer) 
surface (msl) 185(Winter) 625(Winter) 1070(Winter) 
Depth over sills at low 14 13 13 -- 
water (feet) 
Character of foundation Limestone Limestone Limestone Rock Rock 
Kind of spillway Fixed-gated Fixed-gated Gated Gated Fixed 
Height of dam (feet) 67 62 114 95 192 
Type of construction Concrete Concrete Concrete Concrete Earth 
and Earth and Earth and Earth 
Total reservoir capacity 367,300 18,180 934,400 604,500 2,554,000 
(acre-feet) 
Power-development 30,000 - 130,000 73,875 86,000 
(kilowatts) 
Percent complete 100 100 100 100 100 
Year opened to navigation 1954 1962 1963 - - 
Estimated cost:... 
Cost to date:3 $47,978,751 $13,038,427 $98,753,4654 $131,565,287 $53,028,418 
Above the mouth of Apalachicola River (river miles). 
Above mouth of Chattahoochee River (river miles). 
Includes cost of added recreational facilities as shown 
in Table 10-A. 
4. Includes $333,198 cost of land for wildlife refuge and 
$10,457,685 for major rehabilitation. 
10-53 
1. 
2. 
3.

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 10-N BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. 
(See Section 6 of Text) 
Armistead L William John Heis 
Coffeevlle Demopolls Selden Bacon Oliver Holt Bankhead 
Lock Lock Lock Lock Lock Lock 
and Dam and Dam and Dam and Dam and Dam and Dam 1 
Miles above Mobile2 116.7 213.2 261.1 338.2 347.0 365.5 
Nearest town (Alabama) Coffeeville Demopolis Eutaw Tuscaloosa Tuscaloosa Oak Grove 
Distance (miles) 3(within city) 6 15 
Lock 
Greatest length available 
for full width (feet) 600 600 600 450 600 600 
Width of chamber (feet) 110 110 110 95 110 110 
Maximum lift (feet) 34 40 22 28 64 68 
Depth over sills at low 
water (feet) 13.0 13.0 13.2 12.0 13.0 14.0 
Character of foundation Rock Rock Sand, clay Hard shale Shale, Sandstone 
sandstone 
Kind of spillway FixedGated Fixed Gated Fixed Gated Gated 
Type construction 
Lock Concrete Concrete Concrete Concrete Concrete Concrete 
Dam Concrete Concrete Earth- Concrete Concrete Concrete 
Concrete 
Year completed 1965 1962 1962 1940 1969 1985 
Year opened to navigation 1960 1954 1957 1939 1966 1975 
Actual cost of lock and dam3 $21,597,264 $19,774,583 $13,295,553 $4,450,874 $28,100,000 $52,292,880 
1. Single life lock. 
2. Navigation mileage from foot of Government Street, Mobile, Ala. 
3. Excludes cost of adding recreation facilities. 
10-54

MOBILE, ALABAMA DISTRICT 
TABLE 10-0 
TENNESSEE-TOMBIGBEE WATERWAY, ALABAMA AND MISSISSIPPI 
(See Section 19 of Text) 
Galusve A terile Columbus Aberdeen Lock A Lock B Lock C Lock D Lock E Bay Springs 
Lock Lock Lock Lock and and ad ad sad Lock and 
sadDam sad Dam and Dam and Dam Spliway Splway Spillway Spillway Spliway and Dam 
Miles above mouths 266 307 335 358 371 376 39 398 407 412 
Nearst town Gainesville, AL Aliceville, AL Columbus, MS Aberdeen, MS Amory, MS Smithville, MS Fulton, MS Fultn, MS Belmont, MS Tupelo, MS 
Greatest lock length 600 600 600 600 600 600 600 600 600 600 
mavailable for full 
mwidth (feet) 
Width of Chamber (feet) 110 110 110 110 110 110 110 110 110 110 
Maximum lift (feet) 36 27 27 27 30 25 25 30 30 84 
Elevation of normal 109 136 163 190 220 245 270 300 330 (Summer)414 
mpool surface (mu) (Wir)409 
Depth over sinalts 15 15 15 15 15 18 18 18 18 18 
mlow water (feet) 
Characterof foundation Moomevill e Eutaw Form. Emaw Form. Etaw Form. Eumaw Form. Eutaw Fon. Gordo Foun. Euaw Form. Godo Form. Sandstone 
Chalk Sad & Clay Sand & Cay Sand Lam. Sand Sand & Clay Clay Sand Clay and Shale. 
Kind of spillway Flied & Fixed & Gated Gated Gated Gated Gated Gaed Gated N/A 
Gated Gated 
Height of dam (feet) 56 57 57 57 46 48 53 52 44.5 103 
Type of onruction Concate Canesee Cancte Canaute Canaste Conaste Conaste Coaue Canaste Canaste 
&Eahth &Bank & Eath & Earth & Eah & Bah &Bank &arth &Earth 
Total reservoir capacity 45,290 655 59,483 31,564 4,400 19,000 13,300 24,900 6,900 (Swnmer)180,000 
m(ace-feet) (Winter)I43,000 
Percentcomplete 100 100 100 100 100 100 100 100 100 100 
Yearopmed to 1978 1979 1981 1984 1985 1985 1985 1985 1985 1985 
Estimatsed Cost $103,214,000 151,255,000 182,650,000 128,262,000 102,685,000 96,905,000 71,375,000 98,205,000 88,173,000 147,000,000 
Cost to date $100,010,600 143,190,800 174,620,500 112,620,200 92,190,500 93,106,700 62,197,000 89,610,800 76,917,700 130398,000 
1. Miles aboe Mobile, Aleae(M ile0isa Bankhead Tunne US. Highway 90) 
10-55

TABLE 10-P 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
COMPLETED FLOOD INSURANCE STUDIES AND FLOOD 
HAZARD INFORMATION REPORTS FOR FY 1982 THRU FY 19891 
(See Section 58 of Text) 
Date Federal 
Study Requesting Agency Completed Cost 
Flood Insurance Studies 
Anniston, Alabama Federal Emergency Management Agency (FEMA) Apr 82 $80,900 
Calhoun County, Alabama Federal Emergency Management Agency (FEMA) Apr 82 61,200 
Cave Springs, Georgia Federal Emergency Management Agency (FEMA) Jan 84 22,500 
Floyd County, Georgia Federal Emergency Management Agency (FEMA) Dec 84 230,000 
Columbus, Mississippi Federal Emergency Management Agency (FEMA) Feb 85 36,000 
Lowndes County, Mississippi Federal Emergency Management Agency (FEMA) Feb $5 229,000 
Aberdeen, Mississippi Federal Emergency Management Agency (FEMA) May 85 35,000 
Amory, Mississippi Federal Emergency Management Agency (FEMA) May 85 50,000 
Cherokee County, Georgia Federal Emergency Management Agency (FEMA) July 85 168,000 
Monroe County, Mississippi Federal Emergency Management Agency (FEMA) Oct 85 140,000 
Dale County, AL Federal Emergency Management Agency (FEMA) Dec 86 82,000 
Lauderdale County, MS Federal Emergency Management Agency (FEMA) Mar 87 144,000 
Houston County, AL Federal Emergency Management Agency (FEMA) Apr 87 114,000 
St. Clair County, AL Federal Emergency Management Agency (FEMA) Jun 87 43,000 
Marengo County, AL Federal Emergency Management Agency (FEMA) Nov 87 36,000 
Greene County, AL Federal Emergency Management Agency (FEMA) Mar 88 18,550 
Covington County, MS Federal Emergency Management Agency (FEMA) Apr 88 35,000 
Pickens County, AL Federal Emergency Management Agency (FEMA) Apr 88 50,000 
Fulton County, GA Federal Emergency Management Agency (FEMA) May 88 180,000 
Monroe County, AL Federal Emergency Management Agency (FEMA) Jun 88 33,000 
Colquitt County, GA Federal Emergency Management Agency (FEMA) Sep 88 48,000 
Murray County, GA Federal Emergency Management Agency (FEMA) Sep 88 68,000 
Special Flood Hazard Information 
Chattahoochee River, Supplement Atlanta Reg. Planning Mar 82 5,000 
to Buford to Whitesburg Report Commission 
Oothcalooga Creek Gordon Co., Ga Board of Jun 82 10,000 
Commissioners 
Canton Creek, Ga. City of Canton, Ga. Dec 82 3,000 
Oktasasi Creek, Ala. Alexander City, Ala. Jan 83 3,000 
Cordele Creek & City of Cordele, Ga. May 83 4,000 
Malcolm Branch, GA. 
Hull Branch, MS East Central Planning and Jun 84 7,000 
Development District 
Percosin Creek & Tribs., GA City of Albany, GA Nov 84 14,000 
Coosawattee, Ellijay and Cartecay City of Ellijay, GA Jul 86 22,000 
Rivers, Vicinity of Ellijay, GA 
Rocky Creek and Basie Branch, MS Ellisville, MS Jan 87 19,000 
Springers Branch, MS Starkville, MS May 87 13,000 
Dixie Creek, GA La Grange, GA Jun 87 15,000 
Little Scooba Creek, MS Scooba, MS Jun 87 18,000 
Dearmenville & Golden Springs, AL Anniston, AL Mar 88 9,000 
1. For list of reports completed by Mobile District for FY 1965 thru FY 1974, see FY 1974 Annual Report, page 10-50; reports completed in FY 
1975 see FY 1975 Annual Report, page 10-44; and for reports completed in FY 1976 and FY 1977, see FY 1977 Annual Report, page 10-46. See 
page 10-48 FY 1978 Annual Report for FY 1978 reports, and see page 10-43 FY 1984 Annual Report for FY 1979 through FY 1984 reports. 
10-56

NEW ORLEANS, LA, DISTRICT * 
District comprises a portion of Louisiana, embraced 
in drainage basins tributary to Mississippi River and 
Gulf of Mexico, except Mississippi River above mile 
325.5 above Head of Passes (AHP), drainage area of 
Ouchita-Black River Basin, and small eastern and 
western portions of Louisiana tributary to Pearl River 
and Sabine River and Lake. 
It includes sections of the Gulf Intracoastal Waterway 
from Lake Borgne Light 29 at the mouth of Pearl 
River to Sabine River, and the Passes of the Mississippi 
River. It exercises jurisdiction over flood control 
work on Mississippi River from mile 325.5 AHP to 
Gulf of Mexico; Atchafalaya River; and in Atchafalaya 
Basin; and maintenance of project navigation 
channel of Mississippi River below mile 325.5 AHP, 
under supervision of President, Mississippi River commission 
(MRC), and Division Engineer, Lower Mississippi 
Valley Division. 
IMPROVEMENTS 
Navigation 
1. Mississippi River, Baton Rouge 
to Gulf of Mexico, LA................. 
2. Mississippi River-Gulf Outlet, LA ...... 
3. Mississippi River Ship Channel, 
Gulf to Baton Rouge, LA .............. 
4. Waterway from Intracoastal 
Waterway to Bayou Dulac, LA 
(Bayous Grand Caillou and 
LeCarpe, LA ......................... 
5. Navigaton work under 
special authorization.................. 
Flood Control 
6. Grand Isle and vicinity, LA ........... 
7. Lake Pontchartrain and vicinity, 
LA, (hurricane protection) ............. 
8. Larose to Golden Meadow, LA 
(hurricane protection)................. 
9. Morgan City and vicinity, LA 
(hurricane protection)................. 
Page Flood Control (cont.) 
10. New Orleans to Venice, LA 
11-2 (hurricane protection).............. 
11-3 11. Westwego to Harvey Canal, LA 
(hurricane protection)............... 
11-4 12. Inspection of completed .flood 
control projects..................... 
13. Flood control work under special 
authorization ...................... 
11-5 
11-5 Tables 
Table 11-A Cost and Financial 
Statement ......... 
Table 11-B Authorizing Legislation ..... 
11-6 Table 11-C Other Authorized Navigation 
Projects ................... 
11-6 Table 11-D Other Authorized Flood 
Control Projects ............ 
11-7 Table 11-E Active General 
11-8 Investigations .............. 
11-8 
11-1 
Page 
11-10 
11-11 
11-12 
11-14 
11-17 
11-19 
11-21 
.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
1. MISSISSIPPI RIVER, 
BATON ROUGE TO 
GULF OF MEXICO, LA 
Definitions. AHP is an abbreviation for Above 
Head of Passes and is a means of referring to river 
mileage for the lower Mississippi River. Likewise, 
BHP is an abbreviation for Below Head of Passes and 
is used to refer to mileages in the Mississippi River 
passes. LWRP is an abbreviation for Low Water Reference 
Plane and refers to the datum from which the 
project depth is measured. Its value varies from +2.53 
feet NGVD at Baton Rouge to +0.48 feet NGVD at 
New Orleans. LDB and RDB are left and right 
descending bank, respectively. This usage eliminates 
the need for a potentially confusing reference to 
cardinal directions (N, E, SE, etc.) on a meandering 
river. 
Location. This reach of the river flows southeasterly 
through southeastern portion of Louisiana. At 
Head of Passes, approximately 233.8 miles below U.S. 
Highway 190 bridge at Baton Rouge, river branches 
into three main passes: Southwest Pass, South Pass, 
and Pass a Loutre, two of which, Southwest Pass and 
South Pass, are improved under existing project. 
Head of Passes to mouths of Southwest and South 
Passes are 20.1 and 13.5 miles, respectively. Mouth of 
Southwest Pass is 141 miles west of Mobile, AL, and 
349 miles east of Galveston, TX. Mouth of South Pass 
is 18.5 miles northeast of mouth of Southwest Pass. 
(Refer to NOAA Coast Charts Nos. 11361, 11364, and 
11369; MRC alluvial valley map, and Zachary, Baton 
Rouge, White Castle, Donaldsonville, Thibodaux, 
Mount Airy, Bonnet Carre', Hahnville, New Orleans, 
St. Bernard, Barataria, Pointe a la Hache, Black Bay, 
Empire, Forts, West Delta, East Delta, and Southwest 
Pass quadrangles and 1988 (55th edition) folio of flood 
control and navigation maps, Mississippi River, 
Cairo, IL, to Gulf of Mexico, LA, published by the 
MRC.) 
Previous projects. For details see page 552 of 
Annual Report for 1963. 
Existing project. Provides for channel dimensions 
as follows: Between a line one-tenth mile below U.S. 
Highway 190 bridge at Baton Rouge (Mile 233.8 
AHP) to Philadelphia Point (Mile 181.0 AHP) in the 
vicinity of Donaldsonville, 40 feet deep (LWRP) by 500 
feet wide; from Philadelphia Point to the downstream 
limit of the Port of New Orleans (Mile 86.7 AHP), 45 
feet deep (LWRP) by 500 feet wide; in addition, within 
the limits of the Port of New Orleans (Miles 104.5 to 
86.7 AHP), 35 feet deep (LWRP) laterally between the 
45 ft channel and a line 100 feet from the face of the 
wharves on the LDB; from Mile 86.7 AHP through 
Head of Passes (Mile 0.0), 45 feet deep (NGVD) by 750 
feet wide; in Southwest Pass, Miles 0.0 to 17.0 BHP, 
45 feet deep (NGVD) by 750 feet wide; thence tapering 
to 600 feet wide at mile 17.5 BHP, these dimensions 
extending through the jetty channel and bar 
channel, mile 21.5 BHP. Plane of reference below 
New Orleans is mean low gulf. Plane of reference 
above and through New Orleans is low water reference 
plane. General plan of improvement of Southwest 
Pass provides for constructing pass to uniform cross 
section with about 1,420-foot surface width by means 
of jetties, spur dikes, and bulkheads; for channel maintenance 
by dredging from Cubits Gap, Mile 3.5 AHP 
through the gulf entrance channel, Mile 21.5 BHP; for 
construction of small revetted openings through narrow 
portions of banks of pass for purpose of strengthening 
and nourishment of banks; for closure of minor 
outlets not required for maintenance of banks; for construction 
of sills to prevent enlargement of the Venice 
Jump and Cubits Gap; for repairs to sill across Pass 
a Loutre and bank revetment at Head of Passes; for 
construction of dikes with a view to reducing width 
of river above Head of Passes; for construction of a 
submerged deflecting dike above Head of Passes; and 
for other minor work. East jetty is about 24,950 feet 
long and west jetty 19,699 feet. Jetties are composed 
of a substructure of brush mattresses, orginally built 
to about elevation of mean low gulf, surmounted with 
a superstructure of concrete blocks and large riprap 
and/or stone rubble mound of core and cover stone. 
Spur dikes are constructed of round timber piles 
and/or triangular prestressed concrete piles, with 
riprap at the landward ends to connect the dikes to 
the bank line. General plan of improvement of South 
Pass provides for construction and maintenance of jetties 
and spur dikes; for channel maintenance by dredging 
from Head of Passes through the Gulf Entrance 
Channel beyond mile 13.5 BHP; maintenance of a sill 
across Pass a Loutre, and for seaward extension of 
east jetty at mouth of pass; removal of west dike and 
construction of spur dikes and bank revetment at 
Head of Passes; removal of false point at head of South 
Pass to bottom elevation of minus 45 feet and revetment 
of new bank line and construction and maintenance 
of east and west headland structure at Head of 
Passes. East jetty foundation is 12,070 feet long; inner 
east jetty is 11,170 feet long; west jetty is 7,820 feet 
long; and inner west jetty is 4,710 feet long. Jetties 
are composed of a substructure of brush mattresses 
surmounted by a superstructure of stone and/or concrete 
blocks and large riprap. Plane of reference is 
mean low gulf. Variation of water surface is 16 inches 
at mouths and 10 inches at head of the passes, due 
to tides. Extreme range of tides at mouths of passes 
due to hurricanes is about 10 feet. At New Orleans 
extreme range of water surface is about 20 feet due 
to floods. At Baton Rouge extreme range is about 45 
feet due to floods. 
Estimated cost of existing project (October 1987) is 
$268,000,000 Federal. In addition, Coast Guard is to 
provide navigation aids at an estimated cost of $29,000 
and $2,000,000 non-Federal pipeline relocations. 
Local cooperation. None required, except for modification 
of project in connection with Mississippi 
River-Gulf Outlet, which is reported separately. 
Terminal facilities. Piers, wharves, or docks serve 
the Port of New Orleans. Most wharves on east or left 
bank parallel riverbank forming nearly a continuous 
11-2

NEW ORLEANS, LA, DISTRICT 
covered quay about 10 miles long. Public wharves controlled 
by Board of Commissioners, Port of New 
Orleans (the Dock Board), cover 62 percent of 
improved waterfront. These facilities include a shipside 
grain elevator, general cargo and cotton wharves, 
fruit landings, bunkering facilities, terminal warehouses, 
railroad terminals, marine railways, and drydocks. 
(For further details see Port Series No. 20, 
"The Port of New Orleans, LA" revised 1977.) A foreign 
trade zone is located in Port of New Orleans. City 
of Baton Rouge has a reinforced concrete dock for 
deep-sea vessels with mechanical-handling facility. 
Attached to downstream end of wharf is a floating 
wharf boat 231 by 40.5 feet, of 2,000-ton capacity. 
Facilities are served by a transfer boat and municipal 
terminal having a capacity of 40 cars per day. Private 
terminals for handling oil, grain, bauxite ore, and 
other products are at points on both sides of river 
between New Orleans and Baton Rouge. Facilities are 
considered adequate for existing commerce. (For further 
details, see "Port Facilities" included in "Flood 
Control and Navigation Maps of the Mississippi River, 
Cairo, IL, to the Gulf of Mexico, LA," published annually 
by the MRC, and Port Series No. 19, vol. 1, "Port 
St. Joe, FL, Pensacola, FL, Baton Rouge, LA, and 
Lake Charles, LA," revised 1979.) 
Operations and results during fiscal year. Operations 
and maintenance during the fiscal year 
totalled $45,725,400. Of this amount, the following 
was spent on major maintenance items: 
(a) Baton Rouge to New Orleans: One Government 
dustpan dredge and one contract dustpan dredge 
removed approximately 6,000,000 cubic yards of material 
at a cost of $4,645,500. 
(b) New Orleans Harbor: One leased cutterhead 
dredge removed approximately 2,700,000 cubic yards 
of material at a cost of $1,506,800. 
(c) Cubits Gap (Mile 3.5 AHP) through Southwest 
Pass: Two Government hopper dredges, two leased 
hopper dredges, and two contract cutterhead dredges 
removed approximately 32,183,000 cubic yards of 
material at a cost of $21,947,500. 
(d) Jetty Repairs: Repairs to the east and west jetties 
in Southwest Pass were performed at a cost of 
$1,499,400. 
(e) Pile Dike Repairs: Repairs to the pile dikes in 
Southwest Pass were performed by contractors at a 
total cost of $2,853,400. 
(f) Headland Dike Repairs: Repairs to the west headland 
dike by hired labor and to the east headland dike 
by contract have totalled $368,000 this fiscal year. 
(g) Foreshore rock dike work was conducted at a 
cost of $4,804,000. 
(h) rock bulkhead tie-ins were constructed for 
$3,022,000. 
Construction: One foreshore dike contract was 
awarded for Miles 10.4 to 8.0 AHP on the right 
descending bank. Work on bank nourishment, Miles 
10.4 to 8.0 AHP on the left descending bank is 90 percent 
completed. 
Condition as of Sep. 30. The existing project is 50 
percent complete. Deepening Southwest Pass to 40 
feet mean low gulf, as authorized by the modification 
of Mar. 2, 1945, was completed in September 1963. 
Deepening the channel to 40 feet mean low water 
from Baton Rouge to New Orleans and to 40 feet 
mean low gulf in New Orleans Harbor, as authorized 
by the modifications of Oct. 23, 1962, was completed 
in August 1963. Seventeen miles of foreshore dike 
have been completed on the right descending bank 
from Mile 8.0 AHP to Mile 17.4 BHP and 23.5 miles 
on the left descending bank between Miles 11.2 AHP 
and 17.7 BHP. In addition, bank nourishment 
between Miles 4.0 and 0.5 AHP on the right descending 
bank and between Miles 11.2 and 4.2 AHP on the 
left descending bank is complete. Dredging a 45-foot 
channel at Belmont and Smoke Bend crossings was 
completed, thus extending the 45-foot channel to 
Donaldsonville, LA. 
Ongoing work includes construction of a foreshore 
dike from Miles 10.4 AHP to 8.0 AHP on the right 
descending bank, and lateral dike tie-ins and breakwater 
construction between Mile 17.0 BHP and Mile 
19.0 BHP. Pending work includes construction of the 
East Jetty Head, and rehabilitation of the east and 
west jetties. Bank nourishment will be performed 
through a combination of maintenance dredging and 
borrow dredging for those areas where maintenance 
is not required. 
2. MISSISSIPPI RIVER-GULF 
OUTLET, LA 
Location. In State of Louisiana and the territorial 
waters of the United States and extends from existing 
Inner Harbor Navigation Canal at a point 7,500 feet 
north of existing lock and about 11,000 feet from Mississippi 
River, to a turning basin south of Michoud, 
LA, and then as a land and water cut from turning 
basin south of Michoud, LA, southeasterly to and 
along south shore of Lake Borgne and through 
marshes to and through Chandeleur Sound to 38-foot 
contour in Gulf of Mexico. (Refer to NOAA Coast 
Charts Nos. 11340, 11360, 11363, 11369, 11371, and 
11373. Also see MRC 1980 (48th edition) folio of maps, 
Mississippi River-Cairo, IL, to Gulf of Mexico, LA.) 
Existing project. Provides for a seaway canal, 36 
by 500 feet, extending 76 miles as a land and water 
cut from Michoud southeasterly to and along south 
shore of Lake Borgne, and across Chandeleur Sound 
to Chandeleur Island and increasing gradually to 38 
by 600 feet in Gulf of Mexico, with protective jetties 
at entrance, a permanent retention dike through Chandeleur 
Sound, and a wing dike along islands as 
required. It also provides for an inner tidewater harbor 
consisting of 1,000- by 2,000-foot turning basin 36 
feet deep at landward end of seaway canal, and a connecting 
channel 36 by 500 feet wide extending westerly 
along Gulf Intracoastal Waterway from turning 
basin to Inner Harbor Navigation Canal, including 
construction of a suitable highway bridge with 
11-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
approaches to carry Louisiana State Highway 47 (formerly 
61) over channel. Plan further provides for 
future construction of a channel and lock in the vicinity 
of Meraux to furnish an additional connection 
between tidewater harbor and Mississippi River. Estimated 
cost for new work (October 1989) is 
$523,000,000 Federal and $285,900,000 non-Federal. 
This does not include modification for Mississippi 
River-Gulf Outlet, Michoud Canal, which is reported 
separately. The Federal cost excludes $45,000 for aids 
to navigation by U.S. Coast Guard. 
Local cooperation. Requirements of local cooperation 
are fully described on page 11-4 of FY 1986 
Annual Report. 
Terminal facilities. The only facility on the waterway 
is the Public Bulk Terminal of New Orleans constructed 
by Board of Commissioners, Port of New 
Orleans, on left descending bank at Mile 63. Two newcontainer 
ship berths have begun operation at the 
Industrial Canal end of the seaway. 
Operations and results during fiscal year. New 
work by hired labor: Engineering and economic 
studies continued for the new lock and connecting 
channels feature. 
A Reconnaissance Report entitled "Mississippi 
River - Gulf Outlet, St. Bernard Parish, Louisiana 
(Bank Erosion) - 10241" dated Mar. 10, 1988, recommended 
structural methods to provide bank erosion 
abatement at three critical reaches on the north bank 
of the channel. The study indicated that greater than 
90 percent of the potential benefits of this work would 
accrue due to reduced Federal maintenance of the 
channel. The report recommended preparation of a 
supplement to the General Design Memorandum 
(GDM) for the MRGO project instead of conducting 
feasibility studies. This report was approved on May 
6, 1988. Studies were initiated in FY 1988, and the 
GDM Supplement is scheduled for completion in 
September 1990. 
Maintenance dredging under two contracts in 
Breton Sound removed 4,900,000 cubic yards at a cost 
of $3,622,700. The U.S. hopper dredge Wheeler 
removed 300,000 cubic yards of material in the Gulf 
Entrance Channel at a cost of $2,643,100. South Jetty 
Repairs were completed at a cost of $1,190,900. 
Condition as of Sep. 30. Construction was initiated 
March 1958 and entire project is 75 percent complete. 
The channel was opened to navigation Jul. 25, 1963, 
and completed Jan. 20, 1968. Paris Road Bridge was 
opened to traffic Jul. 21, and completed Nov. 14, 1967. 
Approximately 3 miles of first- and second-lift stone 
dikes have been constructed on north side of channel 
and approximately 8.27 miles of first-lift and 7.34 
miles of secondlift stone dikes have been constructed 
on south side of channel in Breton Sound. Principal 
work required to complete project, construction of 
new ship lock, raising and extending dikes and foreshore 
protection. Inner Harbor Navigation Canal to 
Bayou Bienvenue, is in a deferred status. The site for 
the lock remained the major problem. President Carter, 
as a result of his review of water resource projects 
in April 1977, changed the site for the proposed shiplock 
to the Industrial Canal in Orleans Parish and recommended 
that, if justified, the existing lock should 
be replaced and expanded in place and that care 
should be taken to minimize dislocation of residents 
living adjacent to the site. These recommendations are 
being addressed in an Evaluation Report scheduled 
for completion in FY 1990. The foreshore protection, 
south bank, Chalmette Area, Station 367+00 to Station 
1007+00 is complete. 
3. MISSISSIPPI RIVER 
SHIP CHANNEL, 
GULF TO BATON ROUGE, LA 
Location. The project is located in the southeastern 
portion of Louisiana below Baton Rouge, consisting 
of the Mississippi River and its outlets to the Gulf 
of Mexico. 
Existing project. Provides more efficient deepdraft 
navigation access to the New Orleans and Baton 
Rouge reaches of the Mississippi River via Southwest 
Pass by enlarging the existing channel to a project 
depth of 55 feet and enlarging the adjacent channel 
along the left descending bank in New Orleans 
Harbor to a 40-foot depth, a turning basin at Baton 
Rouge, and training works in the passes to reduce 
maintenance. 
Estimated cost of existing project (Oct. 1, 1989) is 
$148,000,000 Federal and $347,000,000 non- 
Federal. In addition, Coast Guard is to provide navigation 
aids at an estimated cost of $1,200,000. 
Local cooperation. The cost sharing provisions contained 
in the Water Resources Development Act of 
1986 require that prior to initiation of construction, 
local interests shall: (a) Provide to the Federal Government 
lands, easements, rights-of-way, and dredged 
material disposal areas, and perform the necessary relocations 
required for construction, operation, and 
maintenance of the project; (b) Hold and save the 
United States free from damages due to the construction 
or operation and maintenance of the project 
except for damages due to the fault or negligence of 
the United States or its contractors; (c) Provide to the 
Federal Government, the non-Federal share of all 
other costs of construction of the project. These costs 
include 25 percent of the construction costs incurred 
for construction of the navigation channel to a depth 
of 45 feet, and 50 percent of the construction costs 
incurred for deepening the channel between 45 and 
55 feet. In addition, the local sponsor shall repay the 
Government 10 percent of the construction costs over 
a 30-year period. The local sponsor may be permitted 
to include, toward sums to be reimbursed, all or part 
of the value of any lands, easements, rights-of-way, 
and dredged material disposal areas and relocations 
(other than utilities) contributed or expended by the 
non-Federal sponsor; (d) Be responsible for 50 percent 
of the incremental maintenance below 45 feet on a 
channel depth greater than 45 feet. 
11-4

NEW ORLEANS, LA, DISTRICT 
A Local Cooperation Agreement (LCA) between the 
Government and the State of Louisiana was signed on 
Jun. 30, 1986. A supplement to the LCA was signed 
on Jun. 15, 1987, to comply with the cost sharing and 
financing concepts reflected in the Water Resources 
Development Act of 1986, Public Law 99-662. This 
agreement provides for the dredging of a 45-foot channel 
from the gulf to Mile 181.0 AHP. The State of Louisiana 
has requested that we proceed with the construction 
of the 45-foot channel from Mile 181.0 AHP to 
Baton Rouge. We have entered into negotiations for 
the Local Cooperation Agreement for this reach. 
Terminal facilities. See Mississippi River, Baton 
Rouge to the Gulf of Mexico, LA. 
Operations and results during fiscal year. The 
dredging of the Belmont and Smokeband crossings 
between New Orleans and Mile 181.0 AHP was completed 
on Dec. 17, 1988. This completes the dredging 
of the 45-foot channel from the Gulf to Mile 181.0 
AHP. 
As a result of the severe drought conditions in the 
midwest part of the country during the summer of 
1988, saltwater intrusion mitigation measures for the 
45-foot channel were implemented on Jul. 14, 1988. 
Construction of an underwater dredged material sill 
in the Mississippi River at mile 63.7 AHP was 
initiated on Jun. 30, 1988, and completed to an elevation 
of -45.0 feet NGVD on Aug. 1, 1988. 
Before the sill was built, the saltwater wedge was 
advancing upstream at a rate of about 2 miles per 
day. It was anticipated that, without the sill and with 
continuing low river flows, the toe of the wedge would 
advance to at least Mile 116 AHP. Shortly after the 
sill was begun, the upstream movement of the wedge 
slowed and on Jul. 11, 1988, the advance of the wedge 
stopped near Mile 104 AHP, just below the Carrollton 
water intake for the city of New Orleans. Assisted by 
increasing flows in late July and early August, the sill 
initiated a retreat of the wedge. By Aug. 11, the 
wedge had become discontinuous upstream of the sill, 
and surface salinities upstream of it had returned to 
near background levels. Once river stages returned to 
normal, the sill was gradually washed away. The sill 
will be constructed again if low river flows require 
protection of freshwater supply. 
The other part of the mitigation plan was to barge 
freshwater to two municipal water treatment plants 
at Boothville, and West Pointe a la Hache, LA, downstream 
of the sill. Barging was initiated on Jul. 14, 
1988, and was completed on Dec. 2, 1988. Approximately 
101,000,000 gallons of water were barged. 
Operations and Maintenance general funds were used 
for the barging operation. 
In summary, the intrusion event was dealt with 
effectively, and both the sill and the barging of freshwater 
to Lower Plaquemines Parish have been demonstrated 
to be practicable. 
Condition as of Sep. 30. The 45-foot channel is completed 
from the Gulf to Mile 181.0 AHP. Studies are 
underway to determine the most economical plan to 
mitigate for saltwater intrusion caused by the deeper 
channel. Until these studies are complete, an interim 
plan has been developed that will provide for the barging 
of fresh raw water to two water treatment plants 
in Plaquemines Parish. The construction of mooring 
facilities for the barges at both of these plants is 
complete. 
4. WATERWAY FROM 
INTRACOASTAL WATERWAY 
TO BAYOU DULAC, LA 
(Bayous Grand Caillou and 
LeCarpe, LA) 
Location. Bayou LeCarpe is a tidal stream which 
rises about 1.5 miles southeast of Houma in Terrebonne 
Parish and flows southerly into Bayou Pelton, 
thence into Bayou Grand Caillou, which flows southwesterly 
into Caillou Bay, a total distance of about 40 
miles. (Refer to Coast and Geodetic Survey Chart No. 
1116 and Geological Survey maps of Houma, Dulac, 
Bayou DuLarge, and Dog Lake quadrangles.) 
Existing project. As modified, provides for a 10- 
by 45-foot channel in Bayou LeCarpe from Gulf Intracoastal 
Waterway 2.6 miles to Houma navigation 
canal; a 5- by 40-foot channel through Bayou Pelton 
and Bayou Grand Caillou to Bayou Dulac, a distance 
of about 13.7 miles. Between Miles 2.6 and 5, this project 
coincides with or is adjacent to 15- by 150-foot 
Houma navigation canal. Normal range of tide is 3 to 
10 inches; from winds, 1 to 3 feet. Cost of new work, 
completed in August 1964, was $129,662. 
Local cooperation. Requirements of local cooperation 
are fully described on page 11-5 of FY 1986 
Annual Report. 
Terminal facilities. Many terminal and transfer 
facilities are in Houma and along waterways which 
flow through area between Houma and Gulf of Mexico. 
All facilities are privately owned and operated. 
Facilities are adequate for existing commerce and for 
reasonably prospective commerce. Ample space exists 
for expansion of existing facilities or for construction 
of new wharves and appurtenances. 
Condition as of Sep. 30. The 5- by 40-foot channel 
was constructed from January 1938 to August 1938, 
and modification of Oct. 23, 1962, for enlargement of 
2.54 miles of Bayou LeCarpe to 10 feet by 45 feet was 
initiated in May and completed August 1964. 
5. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
Preauthorization studies costs as of Sep. 30, 1989, 
were Bayou DuLarge, LA, for $57,151; Lake Charles 
Ship Channel for $39,666; Bayou Grand Caillou, 
$2,735; North Pass-Pass Manchac, LA, $38,482; and 
Trinity Bayou, Terrebonne Parish, $7,500. 
11-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Flood Control 
6. GRAND ISLE AND VICINITY, LA 
Location. In south Jefferson Parish, LA, along the 
Gulf of Mexico, about 50 miles south of New Orleans 
and 45 miles northwest of Southwest Pass (Mississippi 
River). 
Existing project. The project provides protection 
from waves driven by hurricanes that have a frequency 
of recurrence of up to once in every 50 years. 
The plan consists of a berm and vegetated dune extending 
the length of Grand Isle's gulf shore and a jetty 
to stabilize the western end of the island at Caminada 
Pass. The dune would have a 10-foot-wide crown at 
an elevation of 11.5 feet NGVD, 1 on 5 side slopes, and 
protective vegetation. The sandfill berm would slope 
from an elevation of 8.5 feet NGVD at the toe of the 
dune 180 feet gulfward to an elevation of 3 feet NGVD 
and, from this point, would assume its natural slope 
to the offshore bottom. The jetty provided by the plan 
has a top width of 6 feet at an elevation of 4 feet mean 
sea level, 1 on 2 side slopes, and extends approximately 
3,600 feet along the western end of the island 
at Caminada Pass. Estimated cost of project (October 
1989) is $18,677,000 Federal and $13,899,000 non- 
Federal, including $8,338,000 contributed funds. 
Local cooperation. Local interests have the responsibility 
of providing rights-of-way, 30 percent of hurricane 
protection costs, 75 percent of beach erosion 
costs, and operation and maintenance of the completed 
work. The Louisiana Legislature, by Act 833 of 1982, 
authorized the Office of Public Works of the Louisiana 
Department of Transportation and Development to 
provide the non-Federal assurances for the Grand Isle 
Hurricane Protection and Beach Erosion Project. On 
Jan.11, 1983, the Louisiana State Government authorized 
the Office of Public Works to execute the 
required assurances as a co-sponsor with the town of 
Grand Isle. The required assurances were executed on 
Mar. 16, 1983, the construction rights-of-way were provided 
on May 4, 1983, and local interest provided a 
cash contribution of $2,100,000 on Jun. 1, 1983, 
$70,000 in November 1985, $368,000 in September 
1987 and $259,000 in May 1989. An additional amount 
of approximately $5,800,000 will be required prior to 
project completion based on repair estimates as of 
October 1989. Maintenance of the project is the responsibility 
of the local assurer. The local assurer will 
receive Federal aid for repairing erosion and other 
damage to the project for a period of 15 years. The 
average annual Federal maintenance cost identified 
in the Act of Assurances is $44,000; however, this is 
not a fixed amount. Periodic nourishment to repair erosion 
will not necessarily be conducted every year, but 
as needed, with an estimated frequency of one in eight 
years on the average. It is estimated that the Federal 
share of the maintenance cost will be 12 percent for 
the 15-year period. 
Operations and results during the fiscal year. 
The repair and restoration of Grand Isle will be accomplished 
by two separate contracts. The jetty extensions 
and sand bar removal contract (partial fix), which 
was completed in early 1988, consisted of a 500-foot 
extension of the west jetty and a 200- foot extension 
of the east jetty, removal of about 408,000 cubic yards 
of sand from the cuspate bar, and placement of the 
excavated sand on the eroded beach in the East End 
State Park. The dune repair and structural reinforcement 
contract (total fix) will accomplish all additional 
items of work necessary to fully restore the project, 
including the placement of about 1.5 million cubic 
yards of sand to reconstruct the beach and dune, construction 
of offshore breakwaters, placement of a clay 
core in portions of the dune, and restoration of vehicular 
ramps, pedestrian crossovers, and dune vegetation. 
The partial fix contract was awarded Sep. 16, 
1987 and completed Mar. 10, 1989. 
Condition as of Sep. 30. Approximately 50 percent 
of the project is capable of providing wave damage 
protection for the 50-year storm in its present 
condition. 
7. LAKE PONTCHARTRAIN AND 
VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In southeastern Louisiana, vicinity of 
New Orleans, in St. Charles, Jefferson, Orleans, St. 
Bernard, and St. Tammany Parishes, comprising 
lower land and water area between Mississippi River 
alluvial ridge and the Pleistocene escarpment to north 
and west. The dominant topographic feature is Lake 
Pontchartrain, a shallow landlocked tidal basin, about 
640 square miles in area and averaging 12 feet deep, 
connecting with lesser Lake Maurepas to the west and 
through Lake Borgne and Mississippi Sound to the 
Gulf to the east. The lake drains about 4,700 square 
miles of tributary area. (Refer to Geological Survey 
quadrangles Yscloskey and Malheureaux Point, Drum 
Bay, Door Point, Lake Eugenie, Oak Mound Bayou, 
Mitchell Keys, Lake Eloi, and Morgan Harbor; Engineer 
quadrangles Slidell, Covington, Ponchatoula, 
Springfield, Denham Springs, Donaldsonville, Mt. 
Airy, Bonnet Carre', Spanish Fort, Chef Menteur, 
Rigolets, St. Bernard, New Orleans, and Hahnville; 
and Coast and Geodetic Survey Charts Nos. 1115 and 
1116. 
Existing project. Provides protection to the 
greater New Orleans area and other communities 
bordering Lake Pontchartrain from the effects of 
hurricane-generated floods. The project is comprised 
of two major features: The Chalmette Area Plan and 
the High Level Plan. The Chalmette Area Plan consists 
of a levee and floodwall system around the 
Chalmette area and along the Mississippi River-Gulf 
Outlet, with connections to the Mississippi River levees. 
The High Level Plan will provide for heightening 
and strengthening the existing hurricane protection 
levee systems in Orleans Parish and the east bank of 
Jefferson Parish, repairing and rehabilitating the 
11-6

NEW ORLEANS, LA, DISTRICT 
Mandeville Seawall in St. Tammany Parish; building 
a new mainline hurricane levee on the east bank of 
the St. Charles Parish just north of U.S. Highway 
61 (Airline Highway); raising and strengthening the 
existing levee which extends along the Jefferson- 
St. Charles Parish boundary between Lake Pontchartrain 
and Airline Highway; and deferring construction 
of the proposed Seabrook lock until its feasibility 
as a feature of the Mississippi River-Gulf Outlet navigation 
project can be determined. Areas which will 
be enclosed by the levee and floodwall construction 
will be provided protection against tidal surge 
resulting from the Standard Project Hurricane 
(SPH). The estimated project cost for work (October 
1989) is $423,000,000 Federal and $177,000,000 non- 
Federal. 
Local cooperation. Provide all rights-of-way; bear 
30 percent of the first cost, consisting of fair market 
value of providing all lands, easements, and rights-ofway, 
including borrow and spoil disposal areas for construction, 
accomplish alteration and relocation of 
roads, railroads, pipelines, cables, wharves, drainage 
structures, and other facilities; maintain and operate 
all works after completion; and hold and save the 
United States free from damages. See H. Doc. No. 
231, 89th Cong., 1st sess. for more detailed requirements 
of local cooperation. 
Assuring Agency: The Orleans Levee District, Lake 
Borgne Basin Levee District, St. Bernard Parish 
Police Jury, Louisiana Office of Public Works, and 
Pontchartrain Levee District. The State of Louisiana 
formed the Jefferson Levee District and assigned to 
it the Jefferson Parish levees, previously the responsibility 
of the Pontchartrain Levee District. Basic assurances 
were received from the following: Orleans Levee 
District for the entire barrier plan and that portion 
of the Chalmette Area Plan in Orleans Parish; Pontchartrain 
Levee District for the Barrier Plan; Lake 
Borgne Levee District and St. Bernard Parish Police 
Jury for the Chalmette Area Plan in St. Bernard Parish. 
Supplemental assurances covering Public Law 
91-646 have been received from the Orleans Levee District 
and the Pontchartrain Levee District. Lake 
Borgne Basin Levee District, St. Bernard Parish 
Police Jury, and the East Jefferson Levee District. 
The St. Tammany Parish portion of the project has 
been placed in an inactive status since the local sponsors 
have not provided acceptable assurances. Supplemental 
Assurances in connection with the High Level 
Plan were executed by the Orleans Levee District on 
May 29, 1985, and approved by the United States Jun. 
21, 1985. Supplemental Assurances for the High Level 
Plan were executed by the East Jefferson Levee District 
for the Jefferson Parish portion of the project on 
Jan. 16, 1987. Supplemental Assurances for the High 
Level Plan were executed by the Pontchartrain Levee 
District for the St. Charles Parish portion of the project 
on Apr. 20, 1987, and accepted on behalf of the 
United States on Aug. 7, 1987. Supplemental Assurances 
for the High Level Plan are not required from 
St. Bernard Parish Police Jury and the Lake Borgne 
Basin Levee District for St. Bernard Parish. 
Operations and results during fiscal year. Preparation 
of design memorandums and plans and specifications 
continued by hired labor. Preparation of 
three design memorandums are underway. Two were 
completed in FY 89, and one is scheduled for completion 
in FY 90. 
A Draft Reevaluation Report (including Draft Environmental 
Impact Statement) recommending the tentatively 
selected High Level Plan (lieu of Barrier 
Plan) was submitted by New Orleans District to the 
Lower Mississippi Valley Division in December 1983. 
The final Reevaluation Report was submitted to 
LMVD on Aug. 8, 1984. A Record of Decision was 
signed in February 1985 by the Office, Chief of 
Engineers. 
The final Environmental Impact Statement was 
filed with the Council on Environmental Quality on 
Jan. 17, 1975. By Court Order dated Dec. 30, 1977, 
a revised Environmental Impact Statement was 
ordered. A draft revised Environmental Impact Statement 
(EIS) for the High Level Plan and reevaluation 
report which documents the proposal to adopt that 
plan instead of the Barrier Plan was released to the 
public and filed with the Environmental Protection 
Agency on Dec. 16, 1983. The final revised Environmental 
Impact Statement was filed with the Environmental 
Protection Agency on Dec. 7, 1984. 
A draft mitigation report with corresponding 
EIS was prepared and distributed for public review 
on Mar. 16, 1988. A series of public meetings and 
workshops were held to facilitate participation in 
mitigation plan formulation by other agencies, environmental 
groups, local sponsors, and other interested 
groups. Prior to selecting the tentative plan, 
the three final plans were presented to the public 
at a meeting on Jul. 29, 1985. 
Condition as of Sep. 30. Construction started May 
1967 and is 77 percent complete. 
Contract work continued on nine contracts. Plans 
and specifications are underway on four contracts 
scheduled for award in FY 1990. 
8. LAROSE TO GOLDEN MEADOW, 
LA (HURRICANE PROTECTION) 
Location. In coastal section of Louisiana, along 
Bayou Lafourche, and includes lands on both banks 
of the bayou from Larose to 2 miles south of Golden 
Meadow. (Refer to Geological Survey quadrangles Cutoff, 
Lake Felicity, Bay Dosgris, Golden Meadow 
Farms, Bay Tambour, Mink Bayou, Caminada Pass, 
Leeville, Belle Pass, Pelican Pass, and Calumet 
Island; Engineer quadrangles New Orleans, Hahnville, 
Point a la Hache, Barataria, and Fort Livingston; 
and Coast and Geodetic Survey Charts Nos. 1115 
and 1116. 
Existing project. Provides a loop levee about 40 
miles long along both banks of Bayou Lafourche from 
Larose to South Golden Meadow; enlargement of 
11-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
3 miles of existing levee at Golden Meadow; floodgates 
for navigation and hurricane protection in Bayou 
Lafourche at upper and lower bayou crossings; about 
8 miles of low interior levees to regulate intercepted 
drainage. Estimated cost for new work (October 1989) 
is $70,700,000 Federal and $30,300,000 non-Federal. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-of-way, 
including borrow areas and spoil disposal areas, and 
accomplish alterations to roads, pipelines, cables, 
wharves, oil wells, and any other facilities necessary 
for the construction of the project; all at an estimated 
cost of $14,115,000; bear 30 percent of the total project 
cost, a sum presently estimated at $30,300,000 consisting 
of the items listed above, and a cash contribution 
presently estimated at $16,185,000 or equivalent work 
specifically undertaken as an integral part of the project 
after authorization and in accordance with construction 
schedules as required by the Chief of Engineers; 
hold and save the United States free from 
damages due to the construction works; maintain and 
operate all the works after completion in accordance 
with regulations prescribed by the Secretary of the 
Army; and prevent any encroachment on ponding 
areas unless substitute storage capacity or equivalent 
pumping capacity is provided promptly without cost 
to the United States; comply with the provisions of the 
Uniform Relocations Assistance and Real Property 
Acquisition Policies Act of 1970 (Public Law 91646) 
and with the provisions of Section 221 of the Flood 
Control Act of 1970 (Public Law 91-611) in acquiring 
real property. 
The Board of Commissioners of the South Louisiana 
Tidal Water Control Levee District executed the 
required Agreement of Local Cooperation on Nov. 13, 
1972, which was executed by the United States on Jul. 
10, 1973, and approved on behalf of the Secretary of 
the Army on Aug. 29, 1973. Section 38, Paragraph 
1051 et seq., Louisiana Revised Statutes created the 
South Lafourche Levee District. The South Lafourche 
Levee District assumed the rights and obligations of 
the South Louisiana Tidal Water Control Levee District 
with respect to this project. Local interests have 
requested and received funds from the State of Louisiana 
for right-of-way acquisition and relocations 
required to support construction work. 
Operations and results during fiscal year. Two 
contracts were awarded in FY 89 and plans and specifications 
are underway on one contract scheduled for 
award in FY 1990. 
Condition as of Sep. 30. Construction commenced 
in February 1975 and is 59 percent complete. 
9. MORGAN CITY AND 
VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In south-central Louisiana, Morgan City 
proper, and the adjacent areas. It includes the land 
south of Grand Lake, Six Mile Lake, and Lake 
Palourde extending from Morgan City westward to 
Charenton drainage and navigation canal. Lower 
Atchafalaya River and Wax Lake Outlet, the principal 
outlets for Atchafalaya Basin Floodway, traverse 
the area. Gulf Intracoastal Waterway crosses the area 
in an east-west direction. Numerous bayous and artificial 
canals excavated for drainage purposes or for 
access to oil developments exist throughout the area. 
(See Engineer quadrangles Bayou Sale, Jeanerette, 
Foster, Belle Isle, Point Au Fer, Morgan City, and 
Lake Decade; and Coast and Geodetic Survey Chart 
1116.) 
Existing project. Morgan City: Construction of 
about 5.6 miles of new levees along shore of Lake 
Palourde and west bank of Bayou Ramos and about 
0.5 mile of new levee from Southern Pacific railroad 
embankment near Wyandotte to tie in with Bayou 
Boeuf lock levee, and construction of three gravity 
drainage structures. 
Franklin and vicinity: Enlargement of about 21.6 
miles of back levee and construction of about 3.5 miles 
of new levees to effect a complete closure of area to 
be protected, construction of one floodgate and eight 
gravity drainage structures, and alteration of existing 
drainage facilities where necessary. Normal range of 
tide is 1.6 feet. Storm and hurricane tide have produced 
elevations up to 10 feet while northerly storms 
during winter depress the gulf level as much as 3 feet 
below mean sea level. During low water periods on 
Atchafalaya River, generally September through 
November, the effect of tide extends about 35 miles 
above Morgan City. 
Local cooperation. For details see page 11-8 of the 
FY 1986 Annual Report. 
Operations and results during period. The GDM 
for the Morgan City area was completed in FY 1985. 
Condition as of Sep. 30. Due to lack of financial 
local support this project has been moved to a 
deferred status. 
10. NEW ORLEANS TO VENICE, LA, 
HURRICANE PROTECTION 
Location. includes land subject to inundation by 
hurricane tides extending along both banks of the Mississippi 
River below New Orleans from vicinity of 
Phoenix to Venice, LA. 
Existing project. Provides for improvements along 
Mississippi River below New Orleans, LA, for prevention 
of hurricane tidal flood damages by increasing 
heights of existing back levees and modifying existing 
drainage facilities where necessary in three separate 
reaches: Reach A, on the west bank from City Price 
to Empire, 15 miles, 4,340 acres protected; Reach B, 
on the west bank from Empire to Venice, 21 miles, 
4,900 acres protected; and Reach C, on the east bank 
from Phoenix to Bohemia (construction recently completed 
by local agency with credit given as equivalent 
work), 16 miles, 5,470 acres protected, and raising the 
11-8

NEW ORLEANS, LA, DISTRICT 
river levee on the west bank (MR&T levee) from City 
Price to Venice, to a grade high enough to prevent 
overtopping by tidal surges from the east, generally 
called the West Bank River Plan. Reach B was later 
divided into two units, Reach B-1 from Empire to 
Fort Jackson and Reach B-2 from Fort Jackson to 
Venice, LA, as a result of a request made by the local 
agency. 
Estimated cost of new work (October 1989) is 
$160,000,000 Federal and $68,000,000 non-Federal, 
including $50,551,000 cash contributions or equivalent 
work. 
Local cooperation. Provide all lands, easements, 
and rights-ofway including borrow areas and spoil disposal 
areas necessary for the construction of the project, 
at costs presently estimated at $7,598,000; accomplish 
all necessary alterations and relocations to roads, 
pipelines, cables, wharves, and other facilities 
required by the construction of the project at costs 
presently estimated at $11,759,000; bear 30 percent of 
the first cost, a sum presently estimated at 
$68,000,000, and cash contribution presently estimated 
at $50,551,000 to be paid either in a lump sum 
prior to initiation of construction or in installments 
prior to start of pertinent work items, in accordance 
with construction schedules as required by the Chief 
of Engineers, or as a substitute for any part of the 
cash contribution, accomplish in accordance with 
approved construction schedules items of work of 
equivalent value as determined by the Chief of Engineers, 
the final apportionment of costs to be made 
after actual costs and values have been determined; 
hold and save the United States free from damages 
due to the construction works; maintain and operate 
all works after completion in accordance with regulations 
prescribed by the Secretary of the Army; prevent 
any encroachment on ponding areas unless substitute 
storage capacity or equivalent pumping is 
provided promptly; and at least annually, notify those 
affected that the project will not provide complete protection 
from tidal flooding and that further local 
actions must be taken during hurricane emergencies. 
Local interests are also required to comply with the 
provisions of the Uniform Relocation Assistance and 
Real Property Acquisition Policies Act of 1970 (Public 
Law 91-646), in acquiring real property. 
Public Law 91-611. Not applicable. Construction 
started prior to Jan. 1, 1972. 
Public Law 91-646. A constitutional amendment 
was provided by the Louisiana Legislature on Feb. 1, 
1972, allowing local interests to comply. The estimated 
cost to local interests is $48,000. 
Assurances of local cooperation for Reaches A, B-i, 
B-2, and C, furnished by the Plaquemines Parish Commission 
Council were accepted on behalf of the United 
States on Apr. 14, 1965. Supplemental assurances covering 
provisions of the Uniform Relocations Assistance 
and Real Property Acquisition Policies Act of 
1970, Public Law 91-646, furnished by the Plaquemines 
Parish Commission Council were accepted on 
behalf of the United States on Jun. 20, 1973. Local 
interests were requested to furnish separate assurances 
for the East Bank Barrier Levee on Jun. 10, 
1975, Feb. 23, 1976, and again on Aug. 19, 1983. By 
letter dated Feb. 5, 1985, the local sponsor requested 
the Corps of Engineers to defer further work on the 
design of Reach A and direct their efforts toward earliest 
possible construction of the East Bank Barrier 
Levee or a suitable alternative thereto. The Corps, 
with the concurrence of the local sponsor, selected a 
West Bank Levee alternative to the East Bank Barrier. 
On Dec. 29, 1987, the local sponsor provided supplemental 
assurances for the West Bank River Levee. 
These assurances were accepted on behalf of the 
United States on Jan. 28, 1988. By letter dated Jul. 
28, 1987, the local sponsor also requested the Corps 
of Engineers to advance construction on Reach A, 
based on the results of the geotextile test section. 
All negotiations for relocations are the responsibility 
of local interests. These mainly consist of raising 
several petroleum and natural gas pipelines to the 
levee configuration and relocation of privately owned 
frame structures used as fishing and boating camps. 
To assure that there will be no delay in construction 
of levees, local interests are notified well in advance 
so that the owners of the pipelines can be advised. 
Assuring Agency: Plaquemines Parish Government. 
Assurances for all reaches of the project have 
been furnished. 
Operations and results during fiscal year. Construction 
during FY 89 was initiated on five contracts 
and continued on three others. Plans and specifications 
were initiated on ten construction items scheduled 
for award in FY 90. 
The levee on the west bank from Tropical Bend to 
Venice would impact about 14,000 acres of which 
approximately 9,000 acres are marsh and 4,000 acres 
are shallow open waters. Although most of these 
impacts are temporary, about 1,000 acres of marsh 
would be permanently lost. To compensate for this 
loss, a mitigation plan has been formulated which 
would result in the creation of natural marsh on the 
Delta-Breton National Wildlife Refuge. 
Condition as of Sep. 30. Construction began on the 
project in September 1968 and the total project is 
approximately 42 percent complete. 
11. WESTWEGO TO HARVEY CANAL, 
LA (HURRICANE PROTECTION) 
Location. The project includes the Urban area 
within Jefferson parish between Westwego and the 
Harvey Canal on the west bank of the Mississippi 
River in the vicinity of New Orleans, Louisiana. 
The project area is generally bounded by the Harvey 
Canal to the east, Lakes Cataouatche and Salvador 
to the west, the Mississippi River to the north, and 
Barataria Bay to the south. Tidal waters can be carried 
into the project area through Lakes Cataouatche 
and Salvador, which connect to the Gulf of Mexico 
through Barataria Bay, and into the Bayou Segnette 
11-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
and the Harvey Canal. Fresh water comes into the 
area from the Mississippi River via the Harvey and 
Algiers Locks, direct rainfall, and pumpage from 
leveed areas. 
Existing project. The recommended plan will consist 
of approximately 22 miles of new and enlarged 
levees along the permitted alignment from the Westwego 
area to the V-levee, along the existing V-levee 
alignment to the vicinity of Estelle Pumping Station, 
and along the existing Harvey Canal-Bayou Barataria 
Levee to the Roussell Pumping Station. Existing levees 
will be raised approximately 2 to 5 feet. New levees, 
ranging from 10 to 12 feet, will also be constructed. 
From that point, a floodwall is proposed to 
parallel the Harvey Canal and tie back into the Harvey 
Lock. I-type and T-type floodwalls will also be 
used along the levee alignment mentioned above when 
tieing into pumping stations and where land constraints 
dictate. The entire project is scheduled. 
The estimated project cost for work (October 1989) 
is $55,200,000 Federal and $29,700,000 non-Federal. 
Local cooperation. Prior to construction, local 
interests must give assurance satisfactory to the Secretary 
of the Army that they will: 
(1) Provide all lands, easements, and rights-of-way, 
including borrow and excavated material disposal 
areas necessary for construction, operation, and maintenance 
of the project at an estimated cost of 
$7,370,000. 
(2) Accomplish all necessary alteration and relocations 
to roads, railroads, pipelines, cables, wharves, 
and other facilities required by the construction of the 
project at an estimated cost of $4,850,000. 
(3) Hold and save the United States free from damages 
due to the construction, operation, and maintenance 
of the project, except where such damages are 
due to the fault or negligence of the United States or 
its contractors. 
(4) Bear 35 percent of the first cost of construction, 
a sum currently estimated at $29,700,000. Funds provided 
by non-Federal interests for interim hurricane 
protection may be considered beneficial expenditures 
and may be credited as a part of the non- Federal contribution 
of the project pursuant to the Water 
Resources Development Act of 1986. 
(5) Maintain and operate all features of the project 
in accordance with regulations prescribed by the Secretary 
of the Army, including levees, floodgates and 
approach channels, drainage structures, drainage 
ditches or canals, floodwalls, and stoplog structures. 
(6) Provide a cash or in-kind contribution for fish 
and wildlife mitigation features of the project in an 
amount equal to the same percentage as the non- 
Federal share of the basic project, a sum currently 
estimated at $900,000 which is included as part of 
(1) above. 
(7) Comply with the applicable provisions of the 
Uniform Relocations Assistance and Real Property 
Acquisition Policies Act of 1970 (PL 91-646). 
(8) Comply with Section 221 of Public Law 91-611, 
Flood Control Act of 1970; and 
(9) Comply with Section 601 of Title VI of the Civil 
Rights Act of 1964 (PL 88-352) that no person shall 
be excluded from participation in, denied the benefits 
of, or subjected to discrimination in connection with 
the project on the grounds of race, creed, or national 
origin. 
Requirements of PL 91-611 and 96-646: 
(1) Local interest are legally qualified to execute 
the assurances. 
(2) A constitutional amendment was provided by 
the Louisiana legislature on Feb. 1, 1972 allowing 
local interest to comply. 
The local sponsor (West Jefferson Levee District) 
has applied for and received ASA (CW) approval 
(May 13, 1988) for $6.7 million working credit for 
work accomplished during the 5-year period prior to 
project authorization. 
Operations and results during fiscal year. Two 
design memorandums were completed during FY 89, 
and one scheduled for completion in FY 90. Plans and 
specifications are currently underway for two contract 
awards in FY 90. 
The final Environmental Impact Statement was 
filed with the Environmental Protection Agency on 
Oct. 23, 1987. It has undergone departmental and public 
review and the Record of Decision was signed Mar. 
28, 1989. 
The project was opposed by the Department of Interior 
(DOI) and the Environmental Protection Agency 
(EPA). DOI and EPA opposed levee construction that 
would impact 33 acres along and within the perimeter 
of the Jean Lafitte National Historical Park, and that 
would further impact 59 acres along and within the 
perimeter of the Bayou aux Carpes Section 404(c) site. 
The recommended levee alignment has been changed 
to avoid these environmentally sensitive areas, and 
there is presently no known environmental opposition 
to the project. 
Two Section 404(b)(1) Evaluations were signed on 
Dec. 9, 1986, one for the mitigation dike and the entire 
alignment except that portion encroaching into the 
EPA 404(c) Site, and another for that portion of the 
alignment in the EPA 404(c) Site. An amended 
404(b)(1) evaluation will be prepared for the V-levee 
North SPH alternative. Application will be made for 
a State of Louisiana Water Quality Certificate. 
Conditions as of Sep. 30. Construction funds were 
approved for FY 90. Plans and specifications are 
underway on two contracts scheduled for award during 
FY 90. 
12. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(a) Various hurricane protection projects, as well as 
small flood control projects, were inspected during 
FY 1989. Also, periodic inspection and continuing evaluation 
of completed civil works structures were conducted 
in accordance with ER 1110-2-100, at various 
times during the year on an as needed basis. 
11-10

NEW ORLEANS, LA, DISTRICT 
Fiscal year costs for the period were $259,180. Total 
costs to Sep. 30, 1989, were $2,764,907. 
(b) Mississippi River and Tributaries floodwalls, levees 
and flood control projects were inspected during 
FY 1989. Also, periodic inspection and continuing evaluation 
of completed civil works structures were conducted 
in accordance with ER 1110-2-100, at various 
times during the year on an as-needed basis. 
Fiscal year costs for the period were $259,180. 
Total costs to Sep. 30, 1989 were $2,764,907. 
13. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities--repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecendent legislation.) 
Disaster preparedness, fiscal year costs for the 
period were $164,979. 
Emergency operations: Total costs to Sep. 30, 
1989, were $41,769. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Detailed studies continued on Bayou DuPortag at 
a cost of $8,161; and Schneider Canal, LA, $55,425. 
11-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 11-A 
See 
Section 
in Text Project 
1. Mississippi 
River, Baton 
Rouge to the 
Gulf of 
Mexico, LA 
2. Mississippi 
River-Gulf 
Outlet, LA 
(Regular Funds) 
(Contrib. Funds) 
3. Mississippi 
River Ship 
Channel-Gulf 
to Baton Rouge 
(Contrib. Funds) 
4. Waterway from 
Intracoastal 
Waterways to 
Bayou Dulac, 
LA (Bayou 
Grand Caillou & 
LeCarpe, LA) 
6. Grand Isle 
and Vicinity, 
LA 
(Contrib. Funds) 
7. Lake Pontchartrain 
and Vicinity, 
LA (Hurricane 
Protection) (Regular 
Funds) 
(Contrib. Funds) 
8. Larose to Golden 
Meadow, LA 
Hurricane 
Protection) 
(Contrib. Funds) 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Total Funds to 
FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
$ 13,251,000 
16,022,664 
24,957,067 
25,630,318 
6,933,000 
7,684,892 
6,663,500 
6,808,104 
631,000 
1,074,000 
1,240,276 
1,239,090 
56,395 
31,470 
30,669 
1,000,000 
735,330 
70,000 
70,000 
20,358,000 
21,676,920 
510,988 
1,102,053 
4,221,000 
4,073,880 
20,110,000 
15,429,842 
25,153,650 
25,117,781 
594,000 
691,278 
8,340,000 
8,373,119 
3,730,000 
3,591,928 
1,070,453 
1,396,000 
849,700 
861,475 
532 
376,800 
377,601 
961,000 
42,691 
368,000 
13,375,000 
13,331,227 
281,518 
34,518 
4,813,000 
5,018,844 
250,000 
234,087 
29,132,000 
29,835,724 
30,889,100 
30,626,352 
850,000 
787,029 
5,164,000 
4,860,872 
3,270,000 
3,356,435 
1,168,000 
1,068,455 
740,000 
1,930,000 
368,000 
13,140,000 
8,425,930 
349,052 
436,000 
4,600,000 
4,007,473 
105,760 
15,913 
2,819,615 
46,691,600 
45,725,384 
1,450,000 
1,370,207 
4,469,000 
4,809,722 
1,167,000 
820,130 
318,000 
671,315 
1,901,000 
1,849,231 
259,000 
258,318 
9,214,000 
13,770,957 
636,579 
404,647 
2,675,000 
2,386,886 
105,760 
84,302,989' 
83,036,909' 
570,738,261 
569,101,899 
91,167,200 
90,915,496 
120,287,080 
120,282,641 
1,240,4775 
1,196,4775 
9,494,000 
9,450,595 
2,882,000 
2,810,315 
10,740,776 
10,732,538 
637,622 
641,608 
1,276,032 
1,276,032 
12,944,500 
12,827,602 
2,907,000 
2,796,318 
217,325,000 
215,605,662 
5,588,321 
5,828,894 
54,276,000 
52,167,808 
2,627,481 
2,599,028 
11-12

NEW ORLEANS, LA, DISTRICT 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
iSne cTtieoxnt Project Funding Total Funds to FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
9. Morgan City and New Work 
Vicinity, LA Approp. -79,000 - - - 1,953,000 
(Hurricane Cost 21,762 - - - 1,975,628 
Protection) 
10. Mississippi New Work 
River Delta at Approp. 971,000 4,908,000 2,850,000 17,200,000 79,318,000 
and below New Cost 1,449,660 4,546,692 3,032,675 16,623,500 78,522,984 
Orleans, LA (New 
Orleans to Venice, 
LA, Hurricane 
Protection) (Regular 
Funds) 
(Contrib. Funds) New Work 
Contrib. 1,368,989 340,000 - - 4,758,989 
Cost 984,106 724,883 - - 4,758,989 
1. Includes $1,729,989 for previous project. 
2. Does not include allotment of $40,000 (9613123). 
3. Does not include expenditures of $63,370 (9613123). 
4. Includes $169,055 for previous projects and $3,379,676 
from permanent indefinite appropriation. 
5. Contributed by Board of Commissioners, Port of New 
Orleans, for providing fill for future industrial sites adjacent to 
turning basin and for dredging cable and pipeline crossings. 
11-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 11-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Water 
Resources 
Development 
Act, 1986 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 29, 1956 
Oct. 22, 1976 
Water 
Resources 
Development 
Act, 1986 
Approp. Act of 
1985, dated 
Jul. 2, 1986 
(PL 99-88) 
Nov. 17, 1986 
(PL 99-662) 
LAKE CHARLES, LA 
The project for deepening of the project for navigation, Lake 
Charles, Louisiana, to a depth of 45 feet, at a total cost 
of $1,070,000. 
MISSISSIPPI RIVER, BATON ROUGE TO GULF OF 
MEXICO, LA (See Sec. 1 of Text) 
Combines projects of Mississippi River, Baton Rouge to New 
Orleans, Mississippi River, South Pass, and Southwest Pass, 
adding thereto project for Mississippi River from New Orleans 
to Head of Passes, to provide a single project, "Mississippi 
River, Baton Rouge to the Gulf of Mexico," with channel 
dimensions as follows: Baton Rouge to New Orleans, 35 by 500 
feet; port limits of New Orleans, 35 by 1,500 feet; New Orleans 
to Head of Passes, 40 by 1,000 feet, Southwest Pass, 40 by 800 
feet; Southwest Pass Bar Channel, 40 b 600 feet; South Pass, 
30 by 450 feet; South Pass Bar Channel 30 by 600 feet. 
Deepen existing channel from 35 to 40 feet by 500 feet wide 
from one-tenth mile below Louisiana Highway Commission 
bridge at Baton Rouge to upper limits of Port of New Orleans, 
and also 40 by 500 feet withmin presently authorized 35- by 
1,500-foot channel in port limits of New Orleans. 
MISSISSIPPI RIVER-GULF OUTLET, LA (See Sec. 2 of 
Text) 
Construct a seaway canal 36 feet deep and 500 feet wide from 
Michoud to 38-foot contour in gulf and an inner tidewater harbor 
consisting of a 1,000- by 2,000-foot turning basin 36 feet 
deep and a connecting channel 36 feet deep and 500 feet wide 
to Inner Harbor Navigation Canal and provides, when economically 
justified, for construction of a lock to Mississippi River in 
the vicinity of Meraux, LA. 
Amends above Act making the construction of bridge relocations 
a Federal responsibility when required by the construction 
of the Mississippi River-Gulf Outlet channel. 
The Mississippi River-Gulf Outlet feature is modified to provide 
that the replacement and expansion of the existing industrial 
canal lock and connecting channels or the construction of an 
additional lock and connecting channels shall be in the area of 
the existing lock or at the Violet site. 
MISSISSIPPI RIVER SHIP CHANNEL, GULF TO 
BATON ROUGE, LA (See Sec. 3 of Text) 
Will provide more efficient deep-draft navigation access to the 
New Orleans and Baton Rouge reaches of the Mississippi River 
via Southwest Pass by enlarging the existing channel to a project 
depth of 55 feet and enlarging the adjacent channel along 
the left descending bank in New Orleans Harbor to a 40-foot 
depth, a turning basin at Baton Rouge, and training works in 
the passes to reduce maintenance. 
Formalizes the cost sharing provisions of the project, permits 
the State of Louisiana to enact user fees to defray their portion 
of the project costs, and implements harbor maintenance fees 
to help pay for the Federal cost of the project. It also provides 
an option to the local sponsor to defer their initial payment for 
one year following initiation of construction. In terms of channel 
depths up to 45 feet, ,the cost sharing requirements are 75 
percent Federal and 25 percent non-Federal for construction 
and 100 percent Federal for maintenance. For channels deeper 
than 45 feet, the cost sharing requirements are 50 percent Federal 
and 50 percent non-Federal for both construction and 
maintenance. 
Public Law 99-662, Nov. 17, 
1986 
H. Doc. 215, 76th Cong., 1st 
sess. 
S. Doc. 36, 87th Cong., 1st 
sess. 
H. Doc. 245, 82nd Cong., 1st 
sess. 
Sec. 186, Water Resources 
Development Act of 1976 
(PL 94-587) 2d sess. 
Public Law 99-662, Nov. 17, 
1986. 
H. Doc. 2577, 99th Cong., 
1st sess. 
WRDA of 1986, 99th Cong.. 
2d sess. 
11-14

NEW ORLEANS, LA, DISTRICT 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1985 
Oct. 23, 1962 
Water 
Resources 
Development 
Act, 1986 
Adopted by 
Committee 
Resolutions 
Sep. 23, 1976, 
and Oct. 1, 
19762 
Oct. 27, 1965 
Water 
Resources 
Development 
Act, 1986 
Nov. 17, 1988 
Oct. 27, 1965 
Oct. 27, 1965 
Oct. 23, 1962 
WATERWAY FROM INTRACOASTAL WATERWAY TO 
BAYOU DULAC, LA (Bayous Grand Caillou and LeCarpe, 
LA) (See Sec. 4 of Text) 
Channel 5 by 40 feet from Intracoastal Waterway at Houma 
through Bayou LeCarpe, Bayou Pelton, and Bayou Grand 
Caillou to Bayou Dulac, about 16.3 miles. 
Channel 10 by 45 feet in Bayou LeCarpe from Gulf Intracoastal 
Waterway to Houma navigation canal. 
BAYOU RIGOLETTE, LA 
A project to construct six additional floodgates at Bayou 
Rigolette, LA, adjacent to the existing drainage structure, at a 
total cost of $2,300,000. 
GRAND ISLE AND VICINITY, LA (See Sec. 6 of Text) 
To provide hurricane protection by placement of a berm and 
vegetated dune extending the length of Grand Isle's gulf shore 
and a jetty to stabilize the western end of the island at 
Caminada Pass. 
LAKE PONTCHARTRAIN AND VICINITY, LA 
(HURRICANE PROTECTION) (See. Sec. 7 of Text) 
Control of hurricane tides by construction of two independent 
units, the Lake Pontchartrain Barrier plan and the Chalmette 
Area plan. 
LAKE PONTCHARTRAIN, NORTH SHORE, LA 
The project for navigation, Lake Pontchartrain North Shore, 
LA: Report of the Chief of Engineers, dated February 14, 
1979, at a total cost of $1,310,000, with an estimated first 
Federal cost of $655,000 and an estimated first non-Federal 
cost of $655,000. 
LAROSE TO GOLDEN MEADOW, LA (HURRICANE 
PROTECTION) (See Sec. 8 of Text) 
A loop levee about 36 miles long along both banks of Bayou 
Lafourche from Golden Meadow to Larose; enlargement of 3 
miles of existing levee at Golden Meadow; floodgates for 
navigation and hurricane protection in Bayou Lafourche at 
upper and lower bayou crossings; about 8 miles of low interior 
levees to regulate intercepted drainage; and seven 
multibarreled culverts controlled by flapgates. 
MORGAN CITY AND VICINITY, LA, HURRICANE 
PROTECTION (See Sec. 9 of Text) 
Construction of new levees along Lake Palourde and Bayou 
Ramos, levee to tie-in with Bayou Boeuf lock levee andthree 
gravity drainage structures in Morgan City unit and 
enlargement of bank levee, construction of new levee, and 
construction of one floodgate and five gravity drainage 
structures in Franklin and vicinity unit. 
NEW ORLEANS TO VENICE, LA, HURRICANE 
PROTECTION (See Sec. 10 of Text) 
Improvements along Mississippi River below New Orleans, LA, 
for prevention of hurricane tidal flood damages by increasing 
heights of existing back levees and modifying existing 
drainage facilities where necessary in five separate reaches. 
H. Doc. 206, 72d Cong., 1st 
sess. 
Public Law 99-662, Nov. 17, 
1986. 
H. Doc. 639, 94th Cong., 
2d sess. 
H. Doc. 231, 89th Cong., 1st 
sess. 
Public Law 99-662, Nov. 17, 
1986., 99th Cong., 2d sess. 
H. Doc. 184, 89th Cong., 1st 
sess.' 
H. Doc. 167, 89th Cong., 1st 
sess. 
H. Doc. 550, 87th Cong., 2d 
sess. 
11-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
WEST BANK HURRICANE PROTECTION LEVEE, 
JEFFERSON PARISH, LA 
Water Structural and nonstructural measures to prevent flood damage Public Law 99-662, Nov. 17, 
Resources to those areas identified in the Feb. 1984 draft Environmental 1986. 
Development Impact Statement for the West Bank Hurricane Protection 
Act, 1986 Levee, Jefferson Parish, LA, at a total cost of $61,500,000, with 
an estimated first Federal cost of $40,000,000 and an estimated 
first non-Federal cost of $21,500,000. Funds provided by non- 
Federal interest for interim hurricane protection may be considered 
beneficial expenditures and may be credited as part of 
the non-Federal contribution of the project pursuant to Section 
104 of this Act. 
1. Contains latest published map. 
2. Permanent Appropriation Repeal Act. 
11-16

NEW ORLEANS, LA, DISTRICT 
TABLE 11-C OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1989 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Alteration of Berwick Bay Bridge' 
Amite River and Bayou Manchac, LA 
Aquatic Plant Control Program, LA 
Atchafalaya River Bayous Chene 
Boeuf, and Black, LA 
Atchafalaya River, Morgan City to Gulf 
of Mexico, LA 
Baton Rouge Harbor, 
Segment between Mi. 2.5 and 5.02 
Barataria Bay Waterway, LA 
Bayou Bonfouca, LA 
Bayou Dorcheat, Loggy Bayou and 
Lake Bisteneau, LA3. 4.5.6 
Bayou Dupre, LA7 
Bayou Grosse Tete, LA8 
Bayou Lacombe, LA 
Bayou Lafourche and Lafourche Jump 
Waterway, LA 
Bayou La Lautre, St. Malo, and 
Yscolskey, LA 
Bayou Plaquemine Brule, LA 
Bayou Queue de Tortue, LA 
Bayou Segnette Waterway, LA 
Bayou Teche, LA 
Bayou Teche & Vermilion River, LA 
Bayou Terrebonne, LA4.9 
Bayou Vermilion, LA4 
Big Pigeon and Little Pigeon 
Bayous, LA3 
Calcasieu River and Pass, LA 
Calcasieu River at Coon Island, LA'o 
Calcasieu River at 
Devil's Elbow, LA 
Cascasieu River Salt Water 
Barrier, LA" 
Cane River, LA3,6 
Chefuncte River and Bogue Falia, LA 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA' 2 
Freshwater Bayou, LA 
Grand Bayou Pass, LA 
Gulf Intracoastal Waterway 
between Apalachee Bay, L & 
Mexican Border 
Houma Navigation Canal, LA 
Inland Waterway from Franklin 
to Mermentau River, LA" 3 
Intracoastal Waterway from the 
Mississippi River to 
Bayou Teche, LA14 
Lake Borgne and Chef Menteur- 
Bulkheads and Jetties 
Lake Charles Deep Water Channel, 
LA'5 
Leland Bowman Lock, LA 
Little Caillou Bayou, LA 
Complete 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Deauthorized 
Complete 
Complete 
1967 
1978 
1984 
1984 
1981 
19462 
1984 
1974 
1887 
1968 
1969 
1967 
1984 
1970 
1950 
1970 
1958 
1984 
1983 
1961 
1947 
1936 
1984 
1976 
1981 
1973 
1910 
1967 
1971 
1984 
1950 
1985 
1984 
1960 
1956 
19422 
1950 
1987 
1973 
$ - 
28,234 
14,193,662 
$ - 
69,087 
30,356,691 56,440,678 
501,963 
1,572,685 
30,997 
5,000 
38,915 
4,716 
1,624,424 
96,916 
33,410 
33,355 
238,828 
754,330 
2,891,822 
120,089 
34,900 
21,049,499 
320,758 
104,1877 
123,454 
119,191 
887,056 
223,616 
36,780 
28,315 
400,045 
5,469,902 
1,668,036 
251,691 
200,169 
- 37,169 
27,807,310 116,919,245 
1,015,81410 - 
5,856,200 - 
4,197,262 
2,500 
58,342 
202,817 
7,116,224 
7,676 
2,000 
463,401 
452,611 
18,091,741 
14,48012 
63,284,470 408,569,554 
- 20,405,960 
249,052 
32,200,010 
77,761 
552,780 
11,699 
241,896 
751,485 
11-17 
1928 
1914 
Nov. 1979 
Nov. 1963 
1931 
1939 
May 1981 
1938 
May 1956 
1915 
March 1923 
March 1957 
1916 
1896 
3 
Oct. 1968 
April 1974 
Sep. 1978 
Jan. 1968 
1959 
Dec. 1914 
Aug. 1968 
1939 
Nov. 1979 
Mar. 1985 
1929

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 11-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(Continued) 
Cost to Sep. 1989 
For Last Mo. and Yr. 
Full Report Operation Completed 
Project See Annual and Deauthorized Status Report For: Construction Maintenance or Reclassified 
Mermentau River, Bayou Nezpique, 
and Bay Des Cannes, LA Complete 1977 5,197,97516 114,519 
Mermentau River, LA Complete 1985 4,672,579 21,397,784 Jul. 1952 
Mississippi River-Gulf Outlet, 
Michoud Canal, LA Complete 1976 2,499,555 - Nov. 1974 
Mississippi River Outlets, 
Venice, LA Complete 1986 10,008,100 13,697,084 Complete 
Navigation work under special 
authorization (Calcasieu Pass 
channel in Old River Bend 
at Cameron, LA) 17 - 1957 - 139,755 
Pass Manchac, LA Complete 1950 79,845 13,545 1912 
Petite Anse, Tigre, and 
Carlin Bayous, LA Inactive 1981 - 1,450,172 Nov. 1980 
Removal of Aquatic Growth, LA 1984 - 27,352,189 
Sulphur River, AR and TX3,6 - 1919 45,989 - 
Tangipahoa River, LA - 1985 - 1,050,201 
Tickfaw, Natalbany, Ponchatoula, 
and Blood Rivers, LA4 Complete 1973 8,115 92,163 1921 
Vinton Waterway, LA2i Deauthorized 1950 - - Nov. 1979 
Waterway from White Lake to 
Pecan Island, LAla3 - 1948 10,904 0,742 
Waterway from Empire, 
LA, to Gulf of Mexico Complete 1981 1,068,142 1,038,671 Jun. 1950 
1. Transferred to Department of Transportation. Authorized 
under Truman-Hobbs Act. 
2. Date authorized. 
3. Completed. Date will be furnished when available. 
4. Includes previous project costs. 
5. No commerce reported. 
6. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st sess. 
7. Includes $56 cost incurred in 1969. 
8. Completed except that portion above mile 10.3 providing 
for widening from 40 feet to 60 feet, which is inactive. 
9. By Public Law 88-404, that portion of Bayou Terrebonne 
between point where Barrow Street crosses said 
stream and a line determined by prolonging and extending 
eastern right-of-way line of New Orleans Boulevard southerly 
to south bank of said stream was declared nonnavigable. 
10. Includes $66,000 contributed funds. 
11. Operation and maintenance of the structure reported 
under project "Calcasieu River and Pass, LA." 
12. Excludes $50,000 contributed funds. 
13. Not completed; incorporated in navigation project 
"Mermentau River, LA." 
14. Not completed; superseded for most of its length by 
present 12- by 125-foot Gulf Intracoastal Waterway, which 
coinc1i5d.e sM waiinthte noarn cpea rallels it. project; no future work schedules. 
16. Includes $57,555 ($29,974 of which was from Public 
Works funds) for new work on previous project. Includes 
$114,519 for maintenance of previous project. 
17. Work is under continuing authority. 
11-18

NEW ORLEANS, LA, DISTRICT 
TABLE 11-D OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
For Last Cost to Sep. 1989 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA' 
Amite River and Tributaries, LA 
Bayou Bodcau, Red Chute, and Loggy 
Bayou, LAl"2 
Bayou Choupique, LA3 
Bayou Nicholas, Coushatta, LA3 
Bayou Pierre in vicinity of 
Shreveport, LA" 2,"
2 
Bayou Rapides, LA3 
Black Bayou Reservoir, LA" 4' 5, 12 
Black Bayou-Pine Island Area, LA3 
Campti-Clarence Area in Natchitoches 
Parish, LA 
Choctaw Bayou and Tributaries, LA" 7" 2 
Colfax, Grant Parishes, LA"7 
Cooper Lake and Channels, TX8 
East Point, LA 
Ferrells Bridge Dam-Lake O' the Pines, 
TXS,9 
Garland City, AR12 
Grant Parish below Colfax, LA", 
Harvey Canal, Bayou Barataria Levee, LA 
Hempstead County Levee District No. 1, 
AR. 1,9,12 
Maniece Bayou, AR." 2212 
McKinney Bayou, Finn Bayou 
Segment, AR.10,12 
Natchitoches Parish, LA" 2 
Pineville, Red River, LA",3,12 
Posten Bayou, AR.".12 
Red River Parish, LA" , "2 
Red River in vicinity of Shreveport, LA1.12 
Saline Point, LA" 9 
Apr. 
Feb. 
Jan. 
Mar. 
Jun. 
1955 
1964 
1948 
1954 
1964 
Jun. 1939 
Dec. 1951 
May 1963 
Jul. 1978 
Apr. 1976 
1956 
1964 
1948 
1954 
1964 
1951 
1952 
1945 
1963 
1978 
1977 
1938 
1979 
1969 
1979 
1976 
1941 
1979 
1941 
1970 
19631o0 
1956 
1953 
1973 
1939 
1953 
1945 
$ 1,653,189 
3,034,2552 
319,200 
129,930 
70,717 
243,3362 
95,179 
336,063 
1,655,700 
741,892 
70,348 
20,839,300 
486,069 
14,175,197 
1,335,842 
38,809 
1,018,005 
88,006 
970,9322 
1,529,478 
232,426 
149,435 
3,908,000 
124,111 
8,301,021 
Aug. 1968 
Jul. 1974 
Aug. 1977 
Aug. 1969 
Aug. 1955 
Dec. 1951 
Mar. 1953 
Mar. 1953 
11-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 11-D 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
For Last Cost to Sep. 1989 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Twelvemile Bayou, LA: 
- 1966 335,433 - May 1965 
Wright Patman Dam and Lake, TXX - 1979 35,659,176 11,195,021 - 
1. Authorized under project "Red River Below Denison 
Dam."
2. In addition, the following was expended from contributed 
funds: 
Amite River and tributaries ........... $ 430 
Bayou Pierre in vicinity of 
Shreveport, LA ....................... 89,047 
Choctaw Bayou and Tributaries, LA .... 170,799 
Harvey Canal, Bayou Barataria 
Levee, LA ..... ........................ 425,209 
Maniece Bayou, AR.....................39,293 
Natchitoches Parish, LA ................ 250,000 
3. Authorized by Chief of Engineers. (Sec. 205, 1948 
Flood Control Act, as amended.) 
4. Construction not initiated. 
5. Inactive. 
6. Includes $92,000 for preauthorization studies. 
7. Completed under provisions of Sec. 7, Flood Control 
Act 1928, as amended by Sec. 9, Flood Control Act 1936, 
and included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
8. These projects transferred to the Fort Worth District, 
Southwestern Division, during FY 1979. 
9. Completed. Date will be furnished when available. 
10. Date authorized. 
11. Posten Bayou Project, authorized by Senate and 
House Resolutions, Dec. 17 and 15, 1970, deleted the plan 
authorized by the Flood Control Act dated Aug. 3, 1955. 
12. These projects transferred to the Vicksburg District 
during FY 1983. 
11-20

NEW ORLEANS, LA, DISTRICT 
TABLE 11-E ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 89 Categories 
SURVEYS (Category 100) 
Navigation (110) 
Bayou Lafourche & Lafourche-Jump Waterway, LA -1009 
GIWW LA & TX Section -10032 
Mississippi River-Gulf Outlet, St. Bernard Parish, LA 
(Bank Erosion) -10241 
Flood Control Studies (120) 
Aloha-Rigolette Area, LA -12123 
Amite River & Tributaries, LA -50100 
Louisiana Coastal Area, LA, Hurricane Protection -12445 
Louisiana Coastal Area, LA, Land Loss & Marsh Creation -12348 
Louisiana Coastal Area, LA, Mississippi River Delta -12637 
Louisiana Coastal Area, LA, Shore & Barrier Island Erosion -12354 
Louisiana Coastal Area, LA, Louisiana Coastal Comprehensive 
Wetlands -12636 
Mermentau, Vermilion & Calcasieu Rivers & Bayou Teche, LA -34014 
Upper Bayou Teche, LA -12435 
Vermilion River & Bayou Tigre, LA -12439 
West Bank of Mississippi River-Vicinity of New Orleans, LA -59360 
Review of Authorized Projects (160) 
Deauthorization Review -77000 
Miscellaneous Activities (170) 
Special Investigations -17250 
Interagency Water Resources Development 
Coordination Studies with Other Agencies (180) 
Planning Assistance to States (186) -14822 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 
South East Louisiana Hurricane Evacuation -83001 
Special Study-Lafayette Parish, LA 
TOTAL (Category 250) 
Coastal Data Collection (280) 
Re-evaluation of Section 54 Projects -53891 
TOTAL (Category 200) 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
Flood Control Projects (650) 
Westwego to Harvey Canal, LA -75457 
GRAND TOTAL GENERAL INVESTIGATIONS 
$ 88,145 
207,178
2 
295,325 
70,169 
248,132 
1,245 
231,543 
209,058 
-9,829 
176,529 
421,415 
119,439 
123,433 
528,133 
2,199,267
0 
20,604 
17,466 
38,070 
98,340 
$2,551,002 
194,962 
16,017 
1,333 
212,312 
212,312 
1,291,465 
1,291,465 
$4,054,779 
11-21

VICKSBURG, MS, DISTRICT * 
This district comprises western and central Mississippi, 
southern Arkansas, northern Louisiana, 
and a very small portion of southwestern Tennessee, 
embraced in drainage basins of eastern tributaries 
of Mississippi River south of Horn Lake Creek to 
and including Buffalo River; Pearl River Basin in 
Mississippi; independent tributaries of the Gulf of 
Mexico south of the Buffalo River Basin to the 
Mississippi-Louisiana state line; western tributaries 
of Mississippi River between White and Atchafalaya 
Rivers including Arkansas River Basin below 
a point 3 miles upstream from Pine Bluff and Arkansas 
River below mile 36.1 near Pendleton. AR; Ouachita 
and Black Rivers in Arkansas and Louisiana; 
and Red River in Louisiana and Arkansas to the 
Texas-Arkansas state line. 
IMPROVEMENTS 
Navigation 
1. Ouachita and Black Rivers below 
Camden, AR ........................ 
2. Red River emergency bank 
protection ........................... 
3. Red River Waterway-Mississippi 
River to Shreveport, La ............. 
4. Navigation work under special 
authorization ........................ 
Flood Control 
5. Bayou Bartholomew and 
tributaries, AR and LA ............. 
6. Bayou Bodcau and tributaries, 
AR and LA ......................... 
7. Lead Bayou, MS .................... 
8. Ouachita River Levees, LA.......... 
9. Ouachita River and tributaries 
AR and LA ......................... 
10. Pearl River Basin, MS and LA ...... 
11. Pearl River, Slidell, St. Tammany 
Parish, LA .......................... 
12. Porter Bayou, MS .................... 
13. Red River below Denison Dam 
(Vicksburg Dist.) .................... 
14. Red River below Denison Dam, levees 
and bank stabilization 
(Vicksburg District) .................. 
Page Flood Control (cont) 
12-2 
12-2 
12-2 
12-3 
15. Red River Waterway-Shreveport, 
LA, to Index, AR ................. 
16. Inspection of completed Flood 
Control Projects ................... 
17. Flood control work under 
special authorization............... 
Tables 
Table 12-A Cost and Financial 
Statement ................... 
Table 12-B Authorizing Legislation..... 
12-3 Table 12-C Ouachita and Black Rivers, 
AR and LA (9-Foot Project), 
12-4 Locks and Dams .......... 
12-4 Table 12-D Other Authorized Navigation 
12-4 Project................... 
Table 12-E Ouachita River and Tribu- 
12-5 taries Existing Project ..... 
12-5 Table 12-F Red River Below Denison 
Dam (Vicksburg District) 
12-6 New Projects............. 
12-6 Table 12-G Red River Below Denison 
Dam (Vicksburg District) 
12-7 Incorporated Projects ...... 
Table 12-H Other Authorized Flood 
Control Projects ............ 
12-7 Table 12-I Active General Investigations 
12-1 
Page 
12-7 
12-7 
12-8 
12-9 
12-11 
12-14 
12-15 
12-17 
12-18 
12-19 
12-20 
12-22

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. OUACHITA AND BLACK RIVERS 
BELOW CAMDEN, AR 
Location.Ouachita River rises in Polk County, AR, 
and flows southeasterly and southerly about 600 miles. 
Below its confluence with the Tensas and Little Rivers 
at Jonesville, LA, it is called Black River, which 
enters Red River 35.5 miles from the Mississippi 
River. 
Previous projects. See page 683 of Annual Report 
for 1962 for details. 
Existing project.See page 684 of Annual Report 
for 1962 for details of the old 6.5-foot navigation project. 
New work for completed project costs 
$7,064,031.68, exclusive of amounts expended under 
previous projects. Modified project and project for 
Red River below Fulton, AR, provide for a channel 
9 feet deep and 100 feet wide in Red River between 
Old River and mouth of Black River, and in Black and 
Ouachita Rivers from mouth of Black River to 
Camden, AR. Authorized features for the modified 
project include four new locks and dams, in-river construction 
dredging to achieve a 9-foot navigation channel 
depth, and channel realignment. All 4 locks and 
dams are complete and in operation and initial channel 
dredging is complete providing 9-foot navigation 
depth. Remaining work consists of realignment of 25 
restricted bendway sites between river miles 195 at 
Sterlington, LA, and river mile 335 at Camden, AR, 
on the Ouachita River. With these improvements in 
place the river system will be navigable by a fourbarge 
tow (two abreast) to Crossett, AR, river mile 
237, and a two-barge tow (abreast) to Camden, AR. 
Mitigation features include the 65,000-acre Felsenthal 
National Wildlife Refuge in Arkansas, the 18,000-acre 
D'Arbonne National Wildlife Refuge in Louisiana, a 
series of recreation facilities along the waterway, and 
improvements to Catahoula Lake to preserve it for 
migratory waterfowl. Estimated total cost for the 
nine-foot navigation project is $272,833,000, which 
includes $256,000,000 Federal costs and $16,833,000 
non-Federal costs. 
Local cooperation.Local interests are required to 
furnishing the construction rights-of-way for the realignment 
work. Seven of the 25 sites are within the 
Felsenthal National Wildlife Refuge and are already 
owned by the Federal Government. However, there 
have been no indications that the land for the remaining 
18 sites will be forthcoming because of strong opposition 
to the realignment work by local environmental 
groups. The six remaining recreation facilities are 
unscheduled at this time due to the lack of required 
cost sharing agreements. 
Terminal facilities. Public loading docks are at 
Columbia, LA, and Camden and Crossett, AR. Privately 
owned docks and loading and unloading facilities 
are at Columbia, Monroe, and Sterlington. LA, 
and El Dorado, Calion, and Camden, AR. Two 
grain-handling facilities and a petroleum-loading 
facility are in the vicinity of Jonesville, LA, and a 
grain-handling facility is in the vicinity of Acme, LA. 
Operations and results during fiscal year. The 
Vicksburg District completed in FY 89 construction 
of Crossett Harbor Phases I and II Recreation area, 
Grand Marais Phases I and II Recreation area, and 
H. K. Thatcher Lock and Dam Access site in 
October 1988, November 1988, and December 1988, 
respectively. 
Maintenance dredging performed by the contract 
dredges Butcher, and Pontchartrain during the FY 
89 removed 1,465,277 cubic yards of material from the 
waterways. 
Condition as of Sep. 30. The project is 92 percent 
complete and provides limited navigation as far north 
as Camden, AR. All four locks and dams associated 
with the project are complete and in operation. Design 
is complete for the channel alignment plan, but due 
to lack of right-of-way and continued opposition, this 
work is on hold. Design is underway for placement of 
mooring facilities in the lower two pools and a construction 
contract was awarded Jan. 31, 1989, for the 
installation of a hinged crest gate in the navigation 
pass of Felsenthal Lock and Dam. 
2. RED RIVER EMERGENCY 
BANK PROTECTION 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red and Old Rivers 
between the Mississippi River and the head of the 
levee system above Index, AR. 
Existing project. Provides for realigning the 
banks by means of cutoffs and training works and for 
stabilizing banks by means of revetments, dikes, and 
other methods as emergency conditions may require 
in advance of developing the design for the entire Red 
River Waterway project. Estimated cost for this work 
(October 1989) is $83,300,000 Federal and $2,182,000 
non-Federal, including a cash contribution of $7,000. 
Local cooperation. Fully complied with. For details 
see pages 11-19 to 11-20, Annual Report FY 80. 
Operations and results during fiscal year. Work 
by hired labor consisted of preparing plans and specifications, 
surveys, and general engineering. Completion 
of the Candler Lake Revetment, river mile 365-R, 
and Temple Revetment, mile 422-L, Bear Realignment, 
river mile 413.5 to 422.7, was initiated. 
Condition as of Sep. 30. Construction was initiated 
in October 1972 and is 87 percent complete. 
3. RED RIVER WATERWAYMISSISSIPPI 
RIVER TO 
SHREVEPORT, LA 
Location. From east central to northwest Louisiana 
along the Red and Old Rivers between the Mississippi 
River and Shreveport, LA. 
12-2

VICKSBURG, MS, DISTRICT 
Existing project. Provide a navigation route from 
the Mississippi River at the junction with Old River 
via Old and Red River to Shreveport, LA, developing 
a channel approximately 236 miles long, 9 feet deep, 
and 200 feet wide. The development will include five 
locks and dams, realignment and contraction of the 
river as necessary to develop an efficient channel, and 
bank stabilization as necessary to hold the newly developed 
channel in position. Facilities to provide opportunities 
for recreation and for fish and wildlife development 
are an integral part of the project. Estimated 
cost for new work is $1,688,317,000 Federal and 
$87,691,000 non-Federal, including $44,160,000 contributed 
funds. The Federal cost includes $317,000 for 
aids to navigation by U.S. Coast Guard. 
Local cooperation. For details see page 11-21, 
Annual Report FY 80. 
The Red River Waterway Commission, governing 
body of the Red River Waterway District, executed an 
act of assurance for all project features in Louisiana 
on Feb. 26, 1969, supported by resolution dated Jan. 
30, 1969. The assurances were accepted for and on 
behalf of the United States on Apr. 15, 1969. The Commission 
furnished amended assurances covering the 
provisions of Public Law 91-646 and Public Law 
91-611 on May 23. 1973, for the portion of the project 
within Louisiana. These were accepted for and on 
behalf of the United States on Nov. 14, 1973. 
Terminal facilities. Local interests are to provide 
adequate terminal facilities along the waterway. The 
Corps entered into an agreement with the City of Alexandria, 
LA, whereby material excavated from the 
Philip Bayou Realignment could be used as fill for 
port construction at mile 109. Construction of the realignment 
and port fill are complete. 
Operations and results during fiscal year. Hired 
labor continued work on Design Memoranda, preparation 
of Plans and Specifications, Surveys, General 
Engineering, and Model Studies. The following contracts 
were awarded in FY 89: Pool 1 - Hog Lake 
dikes, Moncla Reach and Below Gin Lake capouts, 
and the Lock and Dam 1 Water Service; Pool 2 - 
Phase II of the Alexandria Front revetment, Phase I 
of the Lock and Dam 2 recreation facilities, and the 
Lock and Dam 2 Water Service; Pool 3- Fausse Revetment 
downstream extension and Crain Revetment; 
and in Pool 4 - Piermont and Howard Realignments, 
and Hammel and Williams downstream extension 
revetments. Work was also initiated on the Alexandria 
switchyard for the Louisiana and Arkansas Railroad 
Bridge relocation. 
Items continuing including: Pool 1 - Lorran Lake 
Realignment; Pool 2 - Kateland Revetment extension 
and initial construction dredging below Alexandria; 
Pool 3 - Phase III of Lock and Dam 3, Powhatan and 
Campti Realignments, and Eureka and Nantachie/ 
Red Bayou extension revetments; and in Pool 4- Nicholas, 
Carroll Phase II, and Gahagan Realignments. 
The following contracts were completed: Pool 1 - 
Lock and Dam 1 timber wall extension and excavation, 
and initial construction dredging; Pool 2 - 
Deloges Bluff Revetment, Darrow Realignment, Alexandria 
Front Revetment, and the Boyce-Raven Camp 
Reach; Pool 3 - Phase IIc of Lock and Dam 3, St. Maurice, 
Kadesh, Socot, and Ile Au Vaches Realignments, 
and Lumbra Revetment; and Pool 5 - Wilkerson Point 
Realignment, and Cupples Revetment downstream 
extension. 
Maintenance dredging was performed by the Contract 
Dredge Butcher during Fiscal Year 1989. All 
maintenance dredging was below Alexandria, LA. 
2,289,151 cubic yards of material was removed from 
the channel. 
Condition as of Sep. 30. Construction was initiated 
in July 1973, and project is 56 percent complete. 
4. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 87-645, as amended (preauthorization). 
In regard to Yellow Bend, AR, Congress has added 
$1,000,000 to the FY 89 Senate Energy and Water 
Appropriations Bill. In FY 1988, $314,575 was 
expended on Yellow Bend Port and construction was 
initiated in July 1989. 
Flood Control 
5. BAYOU BARTHOLOMEW AND 
TRIBUTARIES, AR AND LA 
Location. Bayou Bartholomew rises in Jefferson 
County, AR, about 10 miles northwest of Pine Bluff 
and flows southerly about 370 miles to join the Ouachita 
River upstream from Sterlington, LA. 
Authorized project. Project includes ten waterretention 
lakes in the western tributaries of Bayou Bartholomew 
in Arkansas and six local levee units along 
the main stem of Bayou Bartholomew in Louisiana. 
However, because of public opposition to construction 
of the loop levees, preconstruction planning of the six 
loop levees has been deferred until such time as there 
is sufficient support by local interests. Channel 
improvements previously authorized are deferred. Latest 
approved (1979) estimated cost of new work is 
$46,913,000 including $44,800,000 Federal and 
$2,113,000 non-Federal. 
Local cooperation.Requirements of local cooperation 
are fully described on page 12-5 of Fiscal Year 
1980 Annual Report. 
Operations and results during fiscal year. Preconstruction 
planning and design have been deferred 
pending favorable benefit-cost ratios. 
Condition as of Sep. 30. Preparation of general 
design memorandum has been deferred due to lack of 
economic justification. 
12-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Status of studies. A re-evaluation study has been 
completed as part of the Ouachita River and 
Tributaries, AR and LA Study. The authorized project 
is not economically feasible. Project included on 
list for deauthorization Dec. 1989 in accordance with 
Sec. 1001 WRDA 1986. 
6. BAYOU BODCAU AND 
TRIBUTARIES, AR AND LA 
Location. In east bank flood plain of Red River. 
Bayou Bodcau rises in vicinity of Hope, AR, and flows 
southerly through Bayou Bodcau Reservoir and Bodcau 
Lake to join Cypress Bayou and form Red Chute 
Bayou, continues through Red Chute Bayou, Flat 
River, and Loggy Bayou to Red River, about 40 miles 
below Shreveport, LA. 
Authorized project. Cypress Bayou-Red Chute 
Bayou levee: Extend existing levee from about 8 miles 
southeast of Benton, LA, proceeding southerly to junction 
of Cross and Red Chute Bayous, and then parallel 
to Red Chute Bayou on the right descending bank to 
its junction with Cutoff Bayou for a total distance of 
approximately 25 miles; construct landside drainage 
channel and several culverts with flap gates to Red 
Chute Bayou; construct approximately 5 miles of levee 
on left descending bank of Red Chute Bayou extending 
south from Louisiana Highway 612, and relocate 
utility lines as needed. 
Flat River-Loggy Bayou levee: Extend from lower 
end of existing Red River levee in vicinity of Ninock, 
LA, along high (left descending) bank of Red River 
to a point on right descending bank of Loggy Bayou, 
about 1 mile above its mouth, thence generally along 
right descending bank of Loggy Bayou, Red Chute, 
Cutoff Bayou, and Flat River to Taylortown to tie into 
existing Red River levee; close Flat River near its junction 
with Cutoff Bayou and install one 36-inch round 
corrugated metal pipe with automatic flap gate to 
drain isolated pockets and provide uninterrupted 
drainage; construct drainage structures on Flat River 
near its junction with Red Chute Bayou and along 
alignment of the Loggy Bayou in the vicinity of 
Grassy Lake; and make necessary utility relocations. 
Flat River channel improvement: Enlarge to average 
bottom width of 50 feet with flat side slopes and 
deepen by 2 to 6 feet from the confluence with Cutoff 
Bayou to junction with Cooper Bayou, 11.6 miles, 
including required relocations and modifications of 
utilities. 
The subject project was one of the Water Resources 
projects reviewed in March 1977 in accordance with 
the President's request. As a result of this review, the 
President recommended that project construction be 
halted and the project be deauthorized. Congress subsequently 
directed the Corps to take the following two 
actions: Construct levees on Red Chute Bayou below 
Cutoff Bayou that are required to prevent induced 
flood damage that would otherwise result from the 
abandonment of partly completed project. Initiate 
studies to determine if modifications to the authorized 
project would permit its completion in a form consistent 
with the current executive policy. 
Engineering and design work for the induced flood 
prevention plan below Cutoff Bayou and project modification 
studies were being conducted when President 
Reagan signed, on Dec. 4, 1981, the Energy and 
Water Development Appropriations Bill of 1982, 
which contained language that "reconfirmed without 
further study and analysis" the plan for flood control 
for the project as approved by the Flood Control Act 
of 1965. 
Resumption of construction was scheduled to begin 
in 1984. The project sponsor, however, requested that 
construction be delayed while a reevaluation of the 
project was made. 
The reevaluation study has been completed. A summary 
of study results was submitted in January 1987 
which recommended no further Federal action. The 
Lower Mississippi Valley Division approved the 
report and a notice of study termination was disseminated 
in June 1987. 
Local cooperation. For details see pages 11-24 and 
11-25, Annual Report for FY 80. 
Operations and results during fiscal year. New 
work by hired labor forces consisted of completion of 
the reevaluation study. 
Condition as of Sep. 30. Construction was initiated 
in October 1974 and is 17 percent complete. Alternatives 
to provide flood protection are being considered 
and these efforts will continue. 
7. LEAD BAYOU, MS 
Location. Lead Bayou is a tributary of the Sunflower 
River in Bolivar and Sunflower Counties, MS, 
approximately 30 miles from the Mississippi River 
near Cleveland, MS. 
Existing project. The plan of improvement was for 
enlargement of the existing Lead Bayou channel to provide 
a 1.5-year degree of protection to agricultural 
areas and a 10-year degree of protection to the small 
developed area near Cleveland, MS. Total estimated 
Federal cost was $1,724,400. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. The construction contract 
was completed Sep. 14, 1983. The stabilization of 
three bridges was completed in early FY 89. 
8. OUACHITA RIVER LEVEES, LA I 
Location. East bank of Ouachita Riber between Bastrop, 
LA, and Sandy Bayou. Loop levees on the west 
bank at West Monroe, Columbia, and Bawcomville. 
Existing project. There are 105.8 miles of levee on 
the east bank and 11.6 miles of levee in the three loops 
on the west bank. A letter report, approved by the 
12-4

VICKSBURG, MS, DISTRICT 
Chief of Engineers, authorized gravel surfacing 40.3 
miles of levee, enlargement of 40.4 miles of levee, and 
a 5.7-mile southward extension of the east bank levee. 
Estimated Federal cost is $8,300,000. Estimated 
non-Federal cost is $14,100,000. 
Local cooperation. Requirements and assurances 
of local cooperation are fully described on page 12-6 
of FY 80 Annual Report. 
Condition as of Sep. 30. Item 1 of the Monroe to 
Sandy Bayou Levee enlargement project was completed 
Jul. 7, 1978. Additonal work was deferred 
pending results of a comprehensive study of the entire 
Ouachita River Levee System. A summary report 
indicating that it is economically feasible to raise portions 
of the existing levee to authorized grade and that 
complete rehabilitation of thc levee system is necessary 
was approved by LMVD on Oct. 1, 1986. The 
study results were disseminated to the project 
sponsor and interested parties in October 1986. The 
Project was reclassified as an active project on May 
7, 1987. The final summary report was sent to the 
Office of the Chief of Engineers. The final summary 
report was sent to the Office of the Chief of Engineers 
in July 1988 and design was initiated on the 
Bawcomville segment of the Ouachita River levees. 
A construction contract for the Bawcomville segment 
is scheduled for third quarter FY 90 pending 
approval of the Supplemental Agreement with the 
local sponsor. 
9. OUACHITA RIVER AND 
TRIBUTARIES, AR AND LA 
Location. Improvements comprising comprehensive 
projects are on main stem Ouachita River, AR 
and LA, on its tributaries, Caddo and Little Missouri 
Rivers, and in Pine Bluff, AR. Description of Ouachita 
River Basin is presented in greater detail on page 690 
of Annual Report for 1962. 
Existing project. The authorized general plan for 
flood control and other purposes in the Ouachita River 
Basin includes the projects listed in Table 12-E. The 
1966 Flood Control Act modified the Bayou 
Bartholomew and Tributaries, AR and LA, project to 
include 10 water-retention lakes in the western 
tributaries of Bayou Bartholomew in Arkansas and 
6 local levee units along the main stem of the bayou 
in Louisiana. 
Local cooperation. Fully complied with for completed 
features of comprehensive project. (See individual 
statements for further details.) 
Operations and results during fiscal year. Operations 
for Blakely Mt. Dam-Lake Ouachita, DeGray 
Lake, Narrows Dam-Lake Greeson, Bayou Bartholomew 
and Tributaries, and Ouachita River Levees 
are shown in individual reports in 1985. 
Condition as of Sep. 30. Pertinent data on those 
features which are complete or not started are in 
Table 12-E. Conditions of Blakely Mt. Dam-Lake 
Ouachita, DeGray Lake, and Narrows Dam-Lake 
Greeson are given in the individual reports in 1985 
report. 
An overall basin study is continuing. Interim study 
of the Ouachita River Levees is compiete. The Interim 
Report recommended raising selected portions of the 
levee to authorized grade. The levee project has been 
reclassified as active. Interim milestones have been 
removed for Monroe-West Monroe and Arkansas 
Lakes. Results of these studies will be reported in the 
Overall Basinwide Report. A new start reconnaissancc 
study for flooding problems in the vicinity of 
Hot Springs, Garland County, AR, will be initiated 
under this authority during FY 89. Publication of the 
Final Basinwide Report will be deferred until completion 
of these studies. 
Favorable continuing authorities reports have been 
approved for Chauvin and Youngs Bayou. Planning 
and design are underway on these items. 
10. PEARL RIVER BASIN, 
MS AND LA 
Location. The basin comprises most of the Southcentral 
portion of Mississippi and a small part of 
southeast Louisiana. The Pearl River begins in 
Neshoba County, MS, and flows southwesterly 113 
miles to the vicinity of Jackson, MS, then southeasterly 
233 miles to the vicinity of Bogalusa, LA. At that 
point, the Pearl River splits into the East and West 
Pearl Rivers, and flows southerly 44 and 48 miles, 
respectively, before entering the Rigolets and Lake 
Borgne. 
Existing projects. The Jackson-East Jackson 
Flood Control Project provides for improvements of 
the Pearl River at Jackson, MS. This project includes 
two levee systems totaling 13.1 miles in length, with 
two pumping stations, four gated outlets, and 5.34 
miles of channel rectification including three cutoffs 
with a total length of 2.2 miles in the Pearl River. This 
project was authorized by the Fiood Control Act of 
Jul. 14, 1960. Construction began in July 1964 and 
work was completed in FY 68. Total Federal cost of 
the project was $7,190,200. The FY 83 Jobs Bill authorized 
extension of the Jackson-East Jackson West 
Bank levee system along the Fortification Street 1-55 
exit. This extension was initiated and completed in 
FY 84. 
Public Law 98-63, dated Jul. 29, 1983, authorized 
the vicinity of Jackson project. This authority provided 
for additional measures to prevent recurring 
flood damages along the Pearl River at Jackson and 
included 3.3 miles of floodway clearing and enlarging 
the opening at the Highway 25 Bridge. This work has 
been completed. Mitigation lands for the clearing 
were purchased by the local sponsor in May 1985 and 
the Corps has reimbursed the local sponsor to cover 
the cost of these lands. Total Federal cost of this 
project is $1,800,000. 
12-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Authorized projects. Public Law 99-88, dated 
Aug. 15, 1985, authorized planning, design, engineering, 
and construction of a levee system in Slidell, LA, 
to protect 3,265 residential and commercial structures 
from floods in the West Pearl. Public Law 99-662, 
dated Nov. 17, 1986, authorized construction of Shoccoe 
Dam and various flood control measures for 
Carthage-Leake County, MS. 
Local cooperation. For the Jackson-East Jackson 
and vicinity of Jackson projects, the requirements are 
as prescribed in Section 3 of the Flood Control Act 
of 1936, as amended. This Act requires that a local 
sponsor provide the easements, and rights-of-way necessary 
for construction of the project; hold and save 
the United States free from damages due to construction 
of the project; and maintain and operate all works 
after completion in accordance with regulations prescribed 
by the Secretary of the Army. The Slidell 
levee project authorization required cost-sharing and 
new guidelines for local cooperation. A Local Cooperation 
Agreement consistent with Public Law 99-88 
was signed by the Slidell local sponsor and the 
Assistant Secretary of the Army for Civil Works on 
Jun. 30, 1986. The local sponsors are as follows: 
Jackson-East Jackson, Rankin-Hinds Pearl River 
Flood Control Drainage District; Vicinity of Jackson 
Project, Pearl River Basin Development District; 
Slidell Levee Project, St. Tammany Levee 
District. 
Condition as of Sep. 30. An overall basin study is 
essentially complete, except for alternative studies to 
Shoccoe Dry Dam as discussed below. Flood control 
feasibility studies for Jackson, MS, recommending 
Shoccoe Dam, and for Slidell, LA, recommending a 
15-mile levee system, have been completed. Detailed 
engineering and design studies are underway for the 
Slidell levee system. As a result of upstream opposition, 
Shoccoe Dam is not implementable. In response 
to a request by the local sponsor, the Pearl River 
Basin Development District, reconnaissance studies to 
evaluate alternatives to Shoccoe for flood damage 
reduction in the Jackson Metropolitan Area are 
underway. Studies of various flood control measures 
for Carthage-Leake County, Columbia and Picayune, 
MS; Bogalusa, LA, and the Bogue Chitto Subbasin 
have been completed. None were found ecenomically 
feasible. Navigation studies have been conducted on 
the East and West Pearl Rivers. Results of these studies 
indicate that maintenance necessary to reopen the 
existing West Pearl River navigation project is economically 
justified. Studies also indicate that the East 
Pearl River does not have sufficient existing flows to 
support a 7- to 9-foot-deep navigation channel. The 
navigation study for Port Bienville, MS, has been 
terminated due to withdrawal of the Hancock 
County Port and Harbor Commission as local sponsor. 
Reconnaissance studies of flow distribution 
between the West Pearl River and the East Pearl 
River (boundary between the States of Louisiana 
and Mississippi) in the Lower Basin are currently 
underway. These studies will identify problems 
and potential solutions and determine if detailed 
feasibility studies are warranted. 
11. PEARL RIVER, SLIDELL, 
ST. TAMMANY PARISH, LA 
Location. The project is located in the southeastern 
portion of the State of Louisiana and consists of the 
area bounded by the West Pearl River on the east, 
Interstate 10 on the west, and Lake Pontchartrain on 
the south. 
Authorized project. The project is broken into two 
segments of levees. The segment north of 1-10 consists 
of 4.5 miles of levee, a pumping station, a floodgate, 
and other minor drainage structures. This levee protects 
the Slidell area north of 1-10 from flooding associated 
with a 200-year hydrological event on the Pearl 
River. The segment south of 1-10 consists of 10.5 miles 
of levees, two pumping stations, floodgates, and other 
minor drainage structures. This levee protects the Slidell 
area south of 1-10 from flooding associated with 
a 200-year hydrological event on the Pearl River and 
provides the same level of protection against hurricane 
surges. These two levee segments total 15 miles 
of levee and would protect some 3,029 homes. 
Local cooperation. The project sponsor, St. Tammany 
Levee District, and the Assistant Secretary of 
the Army (Civil Works), in an agreement consistent 
with the Fiscal Year 1985 Supplemental Appropriation 
Act Public Law 99-88) and Senate Report 1567, 
signed the Local Cooperation Agreement Jun. 30. 
1986. 
Operations and results during fiscal year. Continued 
engineering studies in preparation of General 
Design Memorandum. 
Condition as of Sep. 30. Process of developing 
General Design Memorandum. No construction has 
taken place. 
12. PORTER BAYOU. MS 
Location. Porter Bayou is located in Bolivar and 
Sunflower Counties, MS. It lies approximately 25 
miles east of the Mississippi River, is approximately 
5 miles south of Cleveland, MS, and travels through 
the town of Shaw, MS. 
Existing project. The plan of improvement calls 
for selective snagging and clearing of Porter Bayou 
from mile 12.5 to mile 32.3. This plan provides a 
0.5-year frequency protection for the Porter Bayou 
area. All construction is being performed from one 
side of the stream, leaving the other side undisturbed. 
The total estimated Federal cost of the project is 
$860,000. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. The construction contract 
was completed Nov. 16, 1983. A separate contract was 
let to biologically remove alligatorweed at Shaw, MS, 
and follow-ip with herbicide has been added. 
12-6

VICKSBURG, MS, DISTRICT 
13. RED RIVER BELOW DENISON 
DAM (VICKSBURG DISTRICT) 
Location. On Red River and its tributaries below 
Denison Dam, in Oklahoma, Arkansas, Texas, and Louisiana. 
(Refer to Geological Survey State maps and 
folio "Maps of Red River" - 1958 edition.) 
Existing project. Flood Control Act of 1946 
approved general plan for flood control on Red River 
below Denison Dam, TX and OK, which provides for 
construction of six flood control reservoirs in combination 
with existing or authorized Federal and non- 
Federal levee improvements, modified as required, 
and channel stabilization at locations where levee setbacks 
are impossible or uneconomical. This act further 
authorized incorporation of several separate existing 
projects for flood damage prevention along Red 
River below Denison, above jurisdiction of the MRC, 
into this project. By Public Law 780, 83rd Cong., 2nd 
sess., as amended by Public Law 218, 84th Cong., 1st 
sess., and Public Law 645, 86th Cong., 1st sess., plan 
of improvement was amended to include additional 
projects as indicated in following lists of reservoirs 
and local protection works considered in general flood 
control plan for the Red River below Denison Dam, 
and existing flood control projects incorporated into 
project in Vicksburg District. (See Table 12-H for new 
projects and Table 12-I for incorporated projects.) 
Local cooperation. See individual reports herein. 
14. RED RIVER BELOW DENSION 
DAM, LEVEES AND BANK 
STABILIZATION 
(VICKSBURG DISTRICT) 
Location. Along the main stem of the Red River 
from the head of the levee system immediately above 
Index, AR, through the southwest corner of Arkansas 
to the vicinity of Boyce, LA, on the right bank, and 
Pineville, LA. on the left bank. 
Existing project. Raising and strengthening existing 
and authorized Red River levees to provide protection 
against flooding and bank protection works at 
locations where levee setbacks are impossible or uneconomical. 
The plan consists of raising and strengthening 
existing and authorized Red River levees to provide 
against a flood approximately 20 percent greater 
than the flood of 1945, the flood of record, as modified 
by authorized reservoirs. Bank protection works are 
to be constructed at locations where levee setbacks are 
impossible or uneconomical. Estimated cost for new 
work (October 1989) is $61,516,000 Federal and 
$1,560,000 non- Federal. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-10 of FY 1984 
Annual Report. 
Operations and results during fiscal year. Hired 
labor forces continued investigations, surveys, and 
preparation of plans and specifications. The Cash 
Bend Revetment Extension, river mile 287.5-R, was 
completed and the McKinney Bayou Replacement 
floodgate was initiated. 
Condition as of Sep. 30. Construction was initiated 
in February 1948 and the levees are complete and 
bank stabilization is 98 percent complete. 
15. RED RIVER WATERWAY 
SHREVEPORT, LA, TO 
INDEX, AR 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red River between 
Shreveport, LA, and Index, AR. 
Existing project. To provide for realigning the 
channels of Red River from Shreveport, LA, to the 
levee system near Index, AR, by means of dredging, 
cutoffs, and training works and for stabilizing its 
banks by means of revetments, dikes, and other methods. 
Facilities to provide opportunities for recreation 
and for fish and wildlife development are an integral 
part of the project. Estimated cost for new work (October 
1989) is $249,000,000 Federal and $29,073,000 
non-Federal. 
Local cooperation. Requirements and assurances 
of local cooperation are fully described on pages 12-10 
and 12-11 of Fiscal Year 1984 Annual Report. 
Operations and results during fiscal year. Hired 
labor forces continued reevaluation studies. 
Condition as of Sep. 30. Construction has not been 
initiated. Completion of a General Re-evaluation 
Study is currently scheduled for September 1990. The 
engineering and economic feasibility of constructing 
the authorized project must be reviewed in light of 
changed conditions within the project area. 
16. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was accomplished at 
a cost of $196,990 for the fiscal year. Total cost as of 
Sep. 30, 1989, is $2,475,653. 
No activity during the period. 
Emergency bank protection (Sec. 14 of 1956 
Flood Control Act, Public Law 780, 83rd Cong.). 
Total FY 89 costs for emergency bank protection 
work was $169,279. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Detailed studies were completed on Canal 43, 
Desha and Lincoln Counties, AR, at a cost of $53,819; 
Chauvin Bayou, LA, $626,765; Youngs Bayou, LA, 
$207,028. 
Detailed studies continued on Pearl-Flowood, MS, 
at a cost of $1,200; Boggy Bayou, LA, $42,316; Smackover, 
MS, $51,201; Bawcomville, $265,208; Cooley 
12-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Creek, Minden, LA, $1,273; and Gin Bayou, Itta Bena. 
$7,257. 
During FY 89 detailed studies were terminated on 
Sherwood, AR, $1,950. 
17. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities--repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecedent legislation.) 
Disaster preparedness, FY costs for the period 
were $215,853. 
Advance measures - $1,420,011. 
Total Public Law 99 cost during FY 89 was 
$635,864. 
Snagging and clearing of navigable streams 
and tributaries in the interest of flood control (Sec. 
208 of 1954 Flood Control Act, Public Law 780, 
83rd Cong.) 
No activity during the period. 
12-8

TABLE 12-A 
VICKSBURG, MS, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Ouachita and Black 
Rivers below Camden, 
AR (6.5-foot 
navigation project) 
Ouachita and Black 
Rivers below Camden, 
AR (9-foot 
navigation project) 
2. Red River 
Emergency Bank 
Protection 
(Contrib. Funds) 
3. Red River 
Waterway 
Mississippi 
River to Shreveport, 
LA 
(Contrib. Funds) 
5. Bayou Bartholomew 
and Tributaries, 
AR and LA 
6. Bayou Bodcau 
and Tributaries, 
AR and LA 
7. Lead Bayou, 
MS 
8. Ouachita River 
Levees, LA 
10. Pearl River 
Vicinity of 
Jackson 
11. Pearl River, 
Slidell, St. Tammany 
Parish, LA 
12. Porter Bayou, 
MS 
Total Funds to 
Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 5,391 
6,098,000 
7,064,032 
3,248,900 
3,495,900 
1,270,000 
3,073,870 
91,585,000 
65,955,521 
1,580,000 
2,251,500 
154,936 
153,230 
0 
187,980 
0 
2,428 
21,217 
40,000 
52,533 
7,814,000 
8,537,018 
5,235,000 
5,033,649 
2,355,000 
3,497,107 
68,000,000 
77,210,592 
1,121,100 
1,117,843 
-116,000 
72,417 
631,000 
14,000 
69,619 
176,000 
175,956 
97,500 
116,973 
413,000 
232,288 
2,876,000 
4,791,420 
4,427,500 
4,387,192 
4,348,000 
3,439,358 
103,690,000 
98,126,979 
2,739,000 
2,674,606 
281,000 
254,000 
372,065 
230,000 
49,000 
134,000 
99,158 
14,891 
497,000 
563,676 
414 
1,033,000 
2,009,983 
4,854,300 
4,953,458 
5,571,000 
4,175,110 
118,000,000 
121,938,473 
3,686,697 
3,642,852 
647,000 
212,000 
-92,596 
89,560 
292,000 
265,208 
3,530 
0 
116,973 
585,000 
644,866 
12-9 
5,248,6191 
5,248,619' 
228,345,524 
227,579,721 
83,655,267 
83,438,863 
29,236,000 
25,883,688 
6,825 
6,825 
620,414,000 
594,529,168 
12,113,297 
11,516,646 
2,740,000 
2,275,0008 
974,000 
974,000 
1,038,000 
1,037,952 
631,000 
372,065 
1,961,089 
1,961,089 
3,108,000 
3,046,366 
2,084,530 
2,076,254 
97,500 
1,947,000 
1,890,000 
1,035,278 
1,029,671

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 12-A 
(CONTINUED) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
14. Red River below New Work 
Denison Dam, Approp. 957,000 963,000 1,000,000 1,300,000 60,944,000 
Levees and Bank Cost 2,286,507 185,772 718,800 835,640 59,149,640 
Stabilization 
(Vicksburg District) 
15. Red River Water- New Work 
way, Shreveport, Approp. - 520,000 350,000 - 1,010,000 
LA, to Index, AR Cost 13,684 344,324 355,688 - 855,4973 
1. Includes $674,068 for new work on previous rojects. 
2. Includes $3,312,000 PL 98-8 Jobs Bill. Excludes 
$47,854,000 previously allocated to New Orleans District. 
3. Excludes New Orleans District allocation and cost. 
12-10

VICKSBURG, MS, DISTRICT 
TABLE 12-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Jul. 14, 1960 
Dec. 31, 1970 
Aug. 13, 1968 
Aug. 13, 1968 
May 17, 1950 
Nov. 7, 1966 
Oct. 27, 1965 
Nov. 17, 1986 
Jun. 30, 1948, 
as amended 
Nov. 17, 1986 
OUACHITA AND BLACK RIVERS BELOW CAMDEN, 
AR (See Section 1 of Text) 
Modification of existing project to provide for 9-foot channel 
and deepening canal to Felsenthal, AR. 
Modification of 9-foot project to provide four new locks and 
dams and channel improvements. 
Migratory waterfowl refuges on Bayou D'Arbonne in 
connection with the pool of the Columbia Lock and Dam 
and in the pool of the Felsenthal Lock and Dam. 
RED RIVER EMERGENCY BANK PROTECTION (See 
Section 2 of Text) 
Realining the banks by dredging cut-offs and training works 
and stabilizing banks by means of revetments and dikes. 
RED RIVER WATERWAY-MISSISSIPPI RIVER TO 
SHREVEPORT, LA (See Section 3 of Text) 
Develop a 9 by 200 feet, approximately 236 miles long from 
Mississippi River at junction of Old River via Old River 
and Red River to Shreveport, LA, consisting of 
realinement, bank stabilization, and construction five locks 
and dams. 
BAYOU BARTHOLOMEW, AR AND LA (See Section 5 
of Text) 
Authorized channel improvements on Bayou and Tributaries 
(see above). 
Modified 1950 authorization to include 10 lakes in the west 
escarpment in Arkansas and 6 local levees in Louisiana, 
and acquisition of lands for mitigation of fish and wildlife 
losses. The previously authorized channel improvement was 
deferred until it is determined that the quality and 
quantity of water downstream will not be adversely 
affected. 
BAYOU BODCAU AND TRIBUTARIES, AR AND LA 
(See Section 6 of Text) 
Extend Cypress Bayou-Red Chute Bayou levee, construct 
stream closure landside drainage channel and three 
culverts on Red Chute Bayou, and clearing and snagging 
channel; extend Flat River-Loggy Bayou levee, close Flat 
River near junction with Cutoff Bayou, and construct 
control structures on Flat River near junction with Red 
Chute Bayou; and enlarge Flat River channel to 20 to 35 
feet, a distance of 11.6 miles. 
CANEY CREEK, MS 
Authorizes construction of such bank stabilization measures 
for Caney Creek in the vicinity of Jackson, MS, between 
McDowell Road and Raymond Road as the Secretary 
determines necessary for flood damage prevention and 
erosion control along approximately 3,000 feet of the creek. 
LEAD BAYOU, MS (See Section 7 of Text) 
Channel enlargement. 
MONROE AND WEST MONROE, LA, AND 
OUACHITA PARISH, LA 
Authorizes such structural and nonstructural measures as 
the Secretary deems feasible to prevent flood damage to 
the cities of Monroe and West Monroe, LA, and Ouachita 
Parish, LA. 
12-11 
S. Doc. 117, 81st Cong., 
1st sess. 
S. Doc. 112, 86th Cong., 
2d sess. 
Report of the Chief of 
Engineers dated Nov. 25, 
1970, and H. Doc. 92-109, 
92d Cong., 1st sess. 
H. Doc. 304, 90th Cong., 
2d sess. 
H. Doc. 304, 90th Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 
1st sess. 
H. Doc. 506, 98th Cong., 
2d sess. 
H. Doc. 203, 89th Cong., 
1st sess. 
Public Law 99-662, 99th 
Cong., 2d sess. 
Sec. 205 of the Flood 
Control Act of 1948, as 
amended. Authorized by 
Chief of Engineers Jun. 
10, 1980. 
Public Law 99-662, 99th 
Cong., 2d sess.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 12-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Jul. 14, 1960 
Jun. 13, 1983 
Jul. 29, 1983 
Aug. 15, 1985 
Nov. 17, 1986 
Nov. 17, 1986 
Nov. 17, 1986 
Jun. 30, 1948, 
as amended 
Nov. 17, 1986 
OUACHITA RIVER AND TRIBUTARIES, AR AND LA 
(See Section 9 of Text) 
Authorized DeGray Lake; Murfreesboro Lake; extension of 
floodwall at Monroe to partially close the existing gap; 
local protection at Bawcomville, LA (subsequently 
constructed under Sec. 6, Act of May 15, 1928, with local 
interests contributing one third of cost); Bayou 
Bartholomew channel improvement, including Deep Bayou 
and Overflow Creek; Pine Bluff local protection; local 
protection at Calion, AR; and incorporation, into the 
Ouachita River and Tributaries project, of all existing 
projects and portions thereof in the basin above the lower 
end of the levees on the east bank of the Ouachita River. 
In addition, the Chief of Engineers authorized on Nov. 14, 
1966, additional work on the levees. 
PEARL RIVER, MS AND LA (See Section 10 of Text) 
Construction of levee system and channel rectification, Pearl 
River, vicinity of Jackson, MS 
Accomplish the clearing and channel improvements at Hwy 
25 bridge on the Pearl River in the vicinity of Jackson, MS. 
Design and construct protection to prevent flooding along 
the Pearl River in the vicinity of Jackson, MS 
Planning, design, engineering and construction of a levee 
system for Slidell, LA, pending binding cost-sharing 
arrangements acceptable to the Secretary of the Army or 
under terms and conditions provided in subsequent 
legislation when enacted into law. 
Water Resources Development Act of 1986 authorized flood 
control project at Shoccoe, MS, as outlined in Report of 
Chief of Engineers dated March 17, 1986, and also several 
project features which would provide flood control to the 
upstream areas of the Pearl River Basin in MS. 
PEARL RIVER, SLIDELL, ST. TAMMANY PARISH, 
LA (See Section 11 of Text) 
Authorizes flood control improvements for Pearl River 
Basin, St. Tammany, LA, subject to a favorable Chief's 
report and approval by the Secretary of the Army for Civil 
Works. 
PEARL RIVER BASIN, SHOCCOE DAM, MS 
Authorizes the Pearl River Basin, including Shoccoe, MS, 
for the construction of the Shoccoe Dam plus upstream 
flood control measures at east-central Leake County, south 
part of Carthage, MS, Highway 35 vicinity, upstream 
reservoirs on the Pearl River and upstream channels on the 
Pearl River and elsewhere in Leake County. 
PORTER BAYOU, MS (See Section 12 of Text) 
Selective snagging and clearing of Porter Bayou, MS from 
mile 12.5 to mile 32.3 
RED RIVER WATERWAY, LA 
Water Resources Development Act of 1986 authorized for 
construction the project for mitigation of wildlife losses, 
Red River Waterway, LA, which may include all or such 
portion of any land adjacent to the Loggy Bayou Wildlife 
Managemert Area. 
12-12 
S. Doc. 117, 81st Cong., 
1st sess. 
H. Doc. 441, 86th Cong., 
1st sess. 
S. Doc. 153, 98th Cong., 
1st sess. 
Public Law 98-63, 98th 
Cong., 1st sess. 
Public Law 99-88, 99th 
Cong., 2d sess. 
Public Law 99-662, 99th 
Cong., 2d sess. 
Public Law 99-662, 99th 
Cong., 2d sess. 
Public Law 99-662, 99th 
Cong., 2d sess. 
Sec. 205 of the Flood 
Control Act of 1948, as 
amended. Authorized by 
Chief of Engineers, Feb. 
18, 1982. 
Public Law 99-662, 99th 
Cong., 2d sess.

VICKSBURG, MS, DISTRICT 
TABLE 12-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
RED RIVER BELOW DENISON DAM LEVEES AND 
BANK STABILIZATION (VICKSBURG DIST.) (See 
Section 14 of Text) 
Jul. 24, 1946 Levee and bank stabilization. H. Doc. 602, 79th Cong., 
2d sess. 
Aug. 13, 1968 Deauthorization of Morringsport Dam and Reservoir on H. Doc. 304, 90th Cong., 
Cypress Creek: realining and stabilizing the banks of the 2d sess. 
Red River; and recreational facilities from the Mississippi 
River to Denison Dam, OK and TX. 
RED RIVER WATERWAY-SHREVEPORT, LA, TO 
INDEX, AR (See Section 15 of Text) 
Aug. 13, 1968 Provides for realinement of the channels of the Red River H. Doc. 304, 90th Cong., 
from Shreveport. LA, to Index, AR. 2d sess. 
12-13

TABLE 12-C OUACHITA AND BLACK RIVERS, AR AND LA 
(9-FOOT PROJECT), LOCKS AND DAMS 
(See Section 1 of Text) 
Min. 
Depth 
Greatest on 
Available Lower 
Miles Length Max. Elev. Miter 
Above Width for Full Lift Normal Sill at 
Miles Mouth of Width at Pool Normal Pre- Total 
from of Lock of Lock Low Surface Pool Character cent Estimated 
Nearest Black Chamber Chamber Water (feet Level or Kind of Type of Com- Project 
Location Town River (feet) (feet) (feet) msl) (feet) Foundation Dam Construction plete Cost 
Jonesville, LA 10 25 84 600 30 34 14 Piling Moving Tainter gated dam; 1002 $ 42,400,000 
bascule gated 
navigation pass; 
steel mitering lock 
gates 
Columbia, LA 5 117 84 600 18 52 13 do do Tainter gated dam; 952 44,000,000 
fixed crest 
navigation pass; 
steel mitering lock 
gates 
Felsenthal, AR 1 227 84 600 18 701 13 Earth do Tainter gated dam; 882 99,600,000 
navigation pass 
with inflatable 
dam on crest; steel 
mitering lock 
gates. 
Calion, AR 7 283 84 600 12 77 13 do do Tainter gated dam; 882 70,000,000 
(THh. atKch. er) hinged crest gated navigation pass; 
steel mitering lock 
gates. 
Estimated Federal Cost $256,000,000 
Estimated Non-Federal Cost 16,833,000 
Total Estimated Cost 272,833,000 
N-
1 
1. Fish and wildlife impoundment level. Navigation pool 
elevation .65. 
2. The percent complete reflects all work within the 
pool.

VICKSBURG, MS, DISTRICT 
TABLE 12-D OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1989 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For: Construction Maintenance Completed 
Bayou Bartholomew, LA and AR 1, 2, 3, 4 - 
Bayous D'Arbonne and Corney, LA1, 2, 4 - 
Big Black River, MS 1 , 4, 5- 
Big Sunflower River, MS 1, 4, 6, 7- 
Boeuf River, LA 1 , 3, 4, 7, 8, 9- 
Claiborne County Port, MSCypress 
Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA15 Complete 
Homochitto River, MS 4 - 
Lake Providence Harbor, LALittle 
Missouri River, AR1, 4, 5 - 
Little River, LA 1, 4, 5, 10- 
Little Tallahatchie River, MS 1, 7- 
Madison Parish Port, LA - 
Mouth of Yazoo River, MS 1, 7. 11- 
Ouachita and Black Rivers, AR and LA, 
Felsenthal Canal 
Overton-Red River Waterway, LAPearl 
River, MSRed 
River below Fulton, AR 1, 16, 17, 18- 
Red River Waterway 
LA, AR, OK, and TX 1' 17 18 
Red River Waterway, Shreveport, LA 
to Daingerfield, TX' 
Removing snags and wrecks from- 
Mississippi River below mouth of 
Missouri River and from 
Old and Atchafalaya Rivers1 1 
Rosedale Harbor, MSSaline 
River, AR 1 3. 4, 5- 
Tallahatchie and Coldwater 
Rivers, MS 1. 4. - 
Tensas River and Bayou 
Macon, LA1, 8, 12 
1931 
1941 
1895 
1942 
1949 
1985 
1971 
1910 
1985 
1873 
1890 
1913 
1985 
1953 
193712 
1985 
1985 
1978 
1969 
1976 
1948 
1985 
1931 
1939 
1949 
$ 45,874 
19,000 
15,000 
560,027 
30,000 
2,000,000 
202,817 
15,482 
208,537 
19,992 
1,500 
19,000 
656,000 
1,179,211 
8,562,908 
1,963,806 
$ 42,857 
37,804 
459,328 
103,737 
257,252 
452,611 
8,518 
3,521,524 
566,978 
455,151 
4,387,192 
2,424,844 
2,147,890 
1
1 
Dec. 1983 
Dec. 1914 
1 
Nov. 1963 
1
1
1 
Dec. 1980 
1
1
1 
1956 
1
1
1 150,800 
272,500 
2,493,617 
12,792 
173,066 
85,352 
2,000,000 
26,900 
43,481 
38,367 
Sep. 1978 
1 
12-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 12-D 
(CONTINUED) 
OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
Cost to Sep. 1989 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For: Construction Maintenance Completed 
Yalobusha River, MS 1, 4, 5 14 - 1937 7,000 15,936 1 
Yazoo River, MS - 1987 9,341,826 1,196,781 1 
64th 
sess. 
1. Status and Date unavailable. 
2. Abandonment recommended in H. Doc. 1962, 
Cong., 2d sess., and H. Doc. 467, 69th Cong., 1st 
3. Channels adequate for existing commerce. 
4. Inactive project. No commerce. 
5. Abandonment recommended in H. Doc. 467, 
69th Cong., 1st sess. 
6. Project curtailment recommended by elimination 
of work between Pentecost and mouth of Hushpuckena 
River. (Abandonment of entire project erroneously recommended 
in H. Doc. 467, 69th cong., 1st sess.) 
7. See report of Mississippi River Commission for 
operations in connection with Yazoo Basin. 
8. Report of New Orleans District, pp. 919-920 for 
Fiscal Year 1949. 
9. Project curtailment recommended by elimination 
of work above Girard, LA (Abandonment of entire project 
recommended erroneously in H. Doc. 467, 69th Cong., 1st 
sess.) 
10. Due to decline of traffic, local interests not 
sufficiently interested to provide rights-of-way and dumping 
privileges. 
11. No additional funds available under this project. 
Work is being carried on under appropriation flood control, 
Mississippi River and tributaries. 
12. Year authorized. 
13. Inactive. Channel adequate for commerce. 
14. See report of Mississippi River Commission for 
operations in connection with Yazoo Basin flood control 
pGrroejneacdt a including channel clearing and rectification and Lake on Yalobusha River. 
15. Excludes $50,000 contributed funds. 
16. Includes $1,553,878 for previous projects. 
17. Incorporated in the project "Red River Waterway- 
Mississippi River Shreveport, LA" Sept. 30, 1976. 
18. Emergency bank protection on this project is 
reported separately as "Red River Emergency Bank Protection." 
Two reaches, "Red River Waterway-Mississippi 
River to Shreveport, LA" and "Red River Waterway- 
Shreveport, LA, Daingerfield, TX," are also reported 
separately. 
12-16

VICKSBURG, MS, DISTRICT 
TABLE 12-E OUACHITA RIVER AND TRIBUTARIES: 
EXISTING PROJECT 
(See Section 9 of Text) 
For Last Estimated 
Full Report Federal 
See Annual New Work 
Project Report for: Cost 
Blakely Mt. Dam-Lake Ouachita, AR 1985 $ 44,100,000 
DeGray Lake, AR 1985 72,034,000 
Narrows Dam-Lake Greeson, AR 1985 20,900,000 
Calion. AR 1960 970,996 
Columbia, LA 1941 204,740 
Existing levees and extensions thereto from Bastrop, LA, to mouth of 
Boeuf River and at West Monroe, LA 1961 3,025,181' 
Little Missouri River below Murfreesboro, AR 1957 354,802 
Ozan Creek, AR 1957 57,742 
Terre Noire Creek, AR 1948 123,700 
Pine Bluff, AR, local protection 1954 172,582 
Monroe, LA, floodwall extension (Plan B) 1984 2,561,000 
Bayou Bartholomew and Tributaries. AR and LA (1) 44,800,000 
Ouachita River Levees (additional work) (1) 9,400,000 
Total $198,704,743 
1. See individual reports herein. 
2. Includes $5,800,000 for water supply, to be reimbursed 
by local interests. 
3. Actual cost of completed project. 
4. Excludes the authorized Murfreesboro Lake, AR, 
project, which is inactive. The latest estimated cost (1954) 
was $4,190,000. 
12-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 12-F RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): NEW PROJECTS 
(See Sec. 13 of Text) 
Drainage Conserva- Flood 
Area tion Control Estimated 
Project (square Storage (acre- Federal Stream miles) (acre-feet) feet) Cost 
Bayou Bodcau and tributaries, AR2 and LA - 1,158 - - $25,100,0003 
Bayou Nicholas-Coushatta, LA - - - - 70,7174 
Bayou Pierre in vicinity of Shreveport, LA5 - - - - 243,3368 
Caddo Lake, LA' Caddo Lake - - - 3,586,000 
Campti-Clarence Area in 
Natchitoches Parish, LA Red River - - - 1,950,0003 
Garland City, AR16 - - - - 1,450,0008 
Maniece Bayou, AR - - - - 970,0323 
McKinney Bayou, AR7,8 - - - - 5,610,0003 
Posten Bayou, AR and LA2 , 6,9 - - - - 560,000 
Red River below Denison Dam levees 
and bank stabilization, TX, AR and LA" 3 - - - - 59,650,0003 
Total 99,191,885 
1. Details presented in individual report herein. 
2. Construction on this project not started. 
3. In addition, non-Federal funds are: 
Bayou Bodcau and tributaries, AR and LA ......................................................... $5,300,000 
Bayou Pierre in vicinity of Shreveport, LA (cash contribution) ........................................ 89,047 
Caddo Lake, LA ...................................................................................... 28,000 
Campti-Clarence Area in Natchitoches Parish, LA .................................................... 480,000 
E ast Point .......................................................................................... 67,000 
Garland City, A R ..................................................................................... 6,000 
Maniece Bayou, AR (cash contribution) ................................................................. 18,000 
McKinney Bayou AR(cash contribution) ............................................................. 508,000 
Red River below benison Dam, levees and bank stabilization, TX, AR, and LA ...................... 1,560,000 
4. For last full report, see Annual Report for 1964. 
5. For last full report, see Annual Report for 1951. 
6. Inactive. 
7. Includes $4,330,200, Code 711, and $399,739 accelerated Public Work funds. 
8. Joint-use pool (sediment). 
9. Deauthorized by resolution Dec. 17, 1970, which also authorized new project "Posten Bayou, AR," under provision of 
Sec. 201 of Flood Control Act of 1965. 
12-18

VICKSBURG, MS, DISTRICT 
TABLE 12-G RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): INCORPORATED PROJECTS 
(See Sec. 13 of Text) 
For Last 
Flood Estimated Full Report 
Control Federal See Annual 
Project Type of Work Act Cost Report For 
Aloha-Rigolette Area, Grant and Rapides 
Parishes, LA Levee and appurtenances 1941 $ 1,653,2371 1956 
Bayou Bodcau Reservoir, LA2 Flood-control reservoir 1938 5,120,7401 4 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA Channel improvement 1941 319,2001 1948 
Bayou Pierre, LA Channel enlargement 1936 255,5291 4 
Black Bayou Lake, LA5 ' 6 Flood-control reservoir 1936 714,000 1945 
Colfax Grant Parish, LA Cutoff 1938 70,3481,7 1938 
Grant Parish, below Colfax, LA Levees 1938 38,8091 1941 
Hempstead County levee district 
No. 1, AR Levee enlargement 1938 88,0061 1941 
Natchitoches Parish, LA Levee and appurtenances 1936 1,529,9271, 8 1956 
Pineville, Red River, LA Levee and appurtenances 1941 232,4261 1953 
Red River in vicinity of 
Shreveport, LA Bank protection 1944 3,908,0001 1953 
Red River Parish, LA Levee enlargement 1936 149,4351 1939 
Saline Point, LA Cutoff 1936 124,1111 1945 
Wallace Lake, LA Flood-control reservoir 1936 1 ,2 19 ,3 7 1 1, 3 4 
Total $15,467,134 
1. Actual cost. 
2. Project transferred to Vicksburg District August, 
1982.
3. Includes amounts indicated for recreational facilities 
under Code 711, Bayou Bodcau Reservoir, LA, $1,027,000; 
Wallace Lake, LA, $17,164. 
4. Included in this report. 
5. Work not started. 
6. Inactive. 
7. Completed under provisions of Sec. 7 of Flood Control 
Act of 1928, as amended by Sec. 9 of Flood Control Act of 
1936, and included in 1939 Annual Report of President, 
Mississippi River Commission, p. 2214. 
8. In addition, $25,000 was expended from contributed 
funds. 
12-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 12-H OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 1989 
Mo. and Yr. Full Report Operation Mo. and Yr. 
If See Annual and If 
Project Deauthorized Report For: Construction Maintenance Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA' 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA1 
Bayou Bodcau Reservoir, LA 
Bayou Pierre, LA 
Bayou Pierre in vicinity of 
Shreveport, LA' 2 
Big Black River, MS3 
Big Choctaw Bayou, LA3. 4 
Black Bayou Reservoir, LA" 5. 6 
Blakely Mt. Dam - Lake 
Ouachita, Ouachita River, AK 
Buffalo River, MS 7 
Caddo Lake Dam, LA 
Campti-Clarence Area in 
Natchitoches Parish, LA 
Colfax, Grant Parishes, LA" 8 
DeGray Lake 
Caddo River, AR 
East Point, LA 
Garland City, AR 
Grant Parish below Colfax, LA 1. 3 
Hempstead County Levee District 
No. 1, AR1 .3 
Homochitto River, MS 3 
Maniece Bayou, AR" 2 
McKinney Bayou Finn Bayou 
Segment, AR 
Monroe Floodwall, LA 
Murfreesboro Dam and Lake4 
Narrows Dam-Lake Greeson, 
Little Missouri River, AK 
Natchez Port Area, MS 3 . 4 
Natchitoches Parish, LA1. 2 
Pearl River, Jackson-East 
Jackson, MS 
Pineville, Red River, LA3 , 4 
Posten Bayou, AR'0 
Poverty Point, LA 
Red River Parish, LA1 3 
Nov. 1986 
Aug. 1977 
1956 
1948 
1985 
1985 
1951 
1956 
1966 
1945 
1985 
1940 
1986 
1978 
1938 
1985 
1969 
1976 
1941 
1941 
1956 
1970 
19639 
1984 
1951 
1985 
1969 
1956 
1986 
1953 
1973 
1986 
1939 
$ 1,653,189 $ - 
319,200 
243,3362 
910,185 
248,823 
34,023,108 
3,214,406 
241,130 
670,750 
Apr. 1955 
Jan. 1948 
Apr. 1961 
FY 1939 
Jun. 1939 
3
3 
54,647,790 Oct. 1955 
865,382 
1,655,700 
70,348 
72,033,992 
286,069 
1,335,841 
38,809 
88,006 
205,000 
970,9322 
2,560,000 
16,516,689 
538,000 
1,529,478 
290,000 
232,426 
250,000 
149,435 
- Jul. 1978 
37,267,153 Dec. 1971 
144,650 
Aug. 1968 
Jul. 1974 
Aug3. 1969 
Aug. 1969 
38,195,165 May 1950 
Aug. 1955 
Dec. 1951 
Oct. 1985 
12-20

TABLE 12-H 
(CONTINUED) 
VICKSBURG, MS, DISTRICT 
OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 1989 
Mo. and Yr. Full Report Operation Mo. and Yr. 
If See Annual and If 
Project Deauthorized Report For: Construction Maintenance Completed 
Red River in vicinity of 
Shreveport, LA - 1953 3,908,000 - Mar. 1953 
Saline Point, LA" -3 1945 124,111 - 
Twelvemile Bayou, LA4 
- 1966 335,433 - May 1965 
Wallace Lake, LA - 1985 - 785,216 Dec. 1946 
1. Authorized under project "Red River Below Denison 
Dam." 
2. In addition, the following was expended from contributed 
funds: 
Amite River and tributaries ........... $ 430 
Bayou Pierre in vicinity of 
Shreveport, LA ................... 89,047 
Choctaw Bayou and Tributaries, LA .... 170,799 
Harvey Canal, Bayou Barataria Levee, 
LA ............................... 425,209 
Maniece Bayou, AR ................... 39,293 
Natchitoches Parish, LA .............. 250,000 
3. Completion Date Unavailable. 
4. Authorized by Chief of Engineers under authority 
of Sec. 205 Flood Control Act of 1948, as amended. 
5. Construction not initiated. 
6. Inactive. 
7. Deauthorized by Sec. 1002, Water Resources Development 
Act of 1986. 
8. Completed under provisions of Sec. 7 Flood Control 
Act of 1928, as amended by Sec. 9, Flood Control Act 1936 
and included in 1939 Annual Report of President, Mississippi 
River Commission, p. 2214. 
9. Date authorized. 
10. Posten Bayou Project, authorized by Senate and 
House Resolutions Dec. 17 and 15, 1970, deleted the plan 
authorized by the flood control Act dated Aug. 3, 1955. 
12-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 12-I ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 89 Categories 
SURVEYS (Category 100) 
NAVIGATION (110) 
Lower Pearl Flow Distribution, MS. -12547 $ 88,174 
Flood Control Studies (120) 
Ouachita River Basin, AR and LA -12046 31,288 
Pearl River Basin, MS and LA -12234 169,124 
Hot Springs, Garland Co., AR -12737 193,631 
Jackson Metro Area, MS -12742 234,574 
Subtotal 628,617 
Comprehensive Studies (150) 
Red River Comprehensive (153) -15399 269,880 
Miscellaneous Activities (170) 
Special Investigations (171) -17250 21,222 
Interagency Water Resources (173) -14713 26,941 
Subtotal 48,163 
Coordination Studies with Other Agencies (180) 
Department of Agriculture, Soil Conservation Service (181) -51840 1,571 
Planning Assistance to States, MS (186) -14828 35,888 
Planning Assistance to States, AR (186) -14805 6,740 
Subtotal 44,199 
TOTAL (Category 100) 1,079,033 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 174,506 
Hydrologic Studies (260) 
Hydrologic Studies (260) -53820 13,088 
Subtotal 187,594 
TOTAL (Category 200) 187,594 
CONTINUATION OF PLANNING & ENGINEERING (Category 400) 
Flood Control Projects (450) 
Pearl River, Slidell, LA (451) -12442 15 
Pearl River, Shoccoe Dam, MS (452) -12444 63 
Subtotal 78 
TOTAL (Category 400) 78 
ADVANCE E&D (Category 600) 
Flood Control Projects (650) 
Local Protection, Red River Waterway, 
Shreveport to Index (651) -75023 75,793 
Local Protection, Pearl River Vicinity 
of Jackson, MS (651) -75426 822 
Reservoirs Pearl River Shoccoe Dam, MS (652) -12444 113,038 
Subtotal 482,055 
TOTAL (Category 600) 482,055 
GRAND TOTAL GENERAL INVESTIGATIONS $1,748,760 
12-22

MEMPHIS, TN, DISTRICT *
This district comprises a portion of southeastern 
Missouri and southern Illinois, western portions of 
Kentucky and Tennessee, a small portion of northern 
Mississippi, and the northeastern portion of Arkansas; 
includes area embraced in drainage basins of eastern 
tributaries of the Mississippi River south of Ohio 
River Basin to Nonconnah and Horn Lake Creeks, 
inclusive, and those of western tributaries south of 
Little River diversion channel and Commerce, MO, 
including St. Francis River Basin and White River 
and tributaries below Peach Orchard Bluff, AR, on 
the right bank and below Augusta, AR, on the left 
bank; also includes left bank Mississippi River levee 
from vicinity of Memphis south to about mile 620, and 
right bank levees from Cade Girardeau, MO, to about 
mile 605. 
IMPROVEMENTS 
Navigation 
1. Navigation work under special 
authorization ........................ 
Flood Control 
2. Humbolt, TN ......................... 
3. Inspection of completed flood control 
projects ............................. 
4. Flood control work under special 
authorization ........................ 
Page Tables 
13-1 
13-1 
13-2 
13-2 
Table 13-A 
Table 13-B 
Table 13-C 
Table 13-D 
Table 13-E 
Cost and Financial 
Statement .................. 
Authorizing Legislation ...... 
Other Authorized Navigation 
Projects................ 
Other Authorized Flood 
Control Projects ............ 
Active General 
Investigations .............. 
Navigation 
1. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
During this period $8,244 was expended on reconnaissance 
studies on Cairo Harbor, IL. 
Flood Control 
2. HUMBOLDT, TN 
Location. Humboldt is located in Gibson County, 
TN. 
Existing project. Authorized July 23, 1984, under 
the authority of Section 205 of the 1948 Flood Control 
Act, as amended. The project consists of clearing 
and snagging approximately 2,200 feet of existing 
channel and the construction of 2,600 feet of enlarged 
channel. The project will provide a 10-year level of protection 
for area residents and is expected to reduce 
average annual flood damages by 64 percent. The construction 
cost for the project is $1,368,000. The project 
assurances of local cooperation have been furnished. 
The construction contract for required channel 
improvement was awarded in July 1986. It has been 
determined that no adverse environmental impacts 
will result from construction of the project. 
Local cooperation. Requirements of local cooperation 
are fully described on page 13-4 of FY 1984 
Annual Report. 
Condition as of Sep. 30. Channel work was completed 
Dec. 18, 1987. A contract for construction of a 
railroad drainage structure was awarded on June 2, 
1987. The work was completed in April 1988. 
13-1 
Page 
13-3 
13-3 
13-4 
13-5 
13-6

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
3. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspected completed projects at a cost of $115,991 
in the period. Total cost as of Sep. 30, 1988, was 
$1,510,315. This included in-depth inspection of 
projects. 
4. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
During this period $116,203 was expended to complete 
a reconnaissance study and prepare a detailed 
project report on Big Creek, Millington, TN and $799 
was used to initiate a reconnaissance study for Obion, 
TN. 
Emergency bank stabilization activities pursuant 
to Sec. 14, Public Law 526, 79th Cong., as 
amended. 
During FY 1989, $259,385 was expended on Perkins 
Street Bridge, Nonconnah Creek, Memphis, TN; 
$10,898 on Quince Road Bridge, Nonconnah Creek 
lateral, Memphis, TN; $14,982 on Fletcher Creek Stabilization, 
Memphis, TN; $11,544 on Harrington 
Creek Stabilization, Memphis, TN; $4,019 on Wolf 
River at U.S. Highway 51, Memphis, TN; $7,516 on 
Plainview Road Bridge over South Forked Deer 
River, Chester Co., TN; and $301,978 on Wolf River 
at Second Street, Memphis, TN. Monies on the Perkins 
Street and North Second Street projects were 
used for construction of these projects. Monies on the 
Harrington Creek, Wolf River at U.S. Highway 51, 
Plainview Road, and Fletcher Creek projects were 
used to continue reconnaissance studies and negotiate 
local cooperation agreements. Monies on the Quince 
Road project were used to complete reconnaissance 
studies and initiate preparation of construction plans 
and specifications for the project. 
Emergency flood control activities, Public Law 
99, 84th Cong. 
Federal cost was $191,877 for disaster preparedness 
in FY 89. Also, $8,657 was spent on flood 
fight activities, $57,058 for drought assistance, and 
$74,335 for private levee rehabilitation. 
Flood control activities pursuant to Sec. 208, Public 
Law 780, 83rd Cong., as amended. 
No work was accomplished this period under this 
authority. 
13-2

MEMPHIS, TN, DISTRICT 
TABLE 13-A COST AND FINANCIAL STATEMENT 
See 
iSne cTtieoxnt Project Funding Total Funds to FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
2. Humboldt, TN New Work 
Approp. $333,333 $707,000 $175,000 0 $1,370,333 
Cost 349,736 510,151 368,778 4,968 1,369,322 
TABLE 13-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
HUMBOLDT, TN (See Sec. 2 of Text) 
Jun. 30, 1948, Channel improvement within the city of Humboldt. Approved Jul. 23, 1984' 
as amended 
1. Authorized under authority of Sec. 205 of the 1948 Flood control Act, as amended. 
13-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 13-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1989 
Full Report Operation 
Project DMeoa. utahnodr izYerd. See Annual and Mo. and Yr. Report For: Construction Maintenance Completed 
Caruthersville Harbor, MO - 1984 $768,992 $ 2,621,754 Dec 80 
Forked Deer River, TN, including South 
Fork1,2 - 1912 25,000 425,857 - 
Helena Harbor, AR - 1984 90,847 5,280,925 Sep 63 
Elvis Stahr Harbor, KY - 1984 149,827 4,873,153 Jan 63 
New Madrid Harbor, MO - 1984 196,373 385,509 Oct 70 
Obion River, TN",3 - 1911 28,716 -- 
Osceola Harbor, AR - 1984 269,115 6,307,388 Nov 74 
Removing snags and wrecks from 
Mississippi River below mouth of Missouri 
River and from Old and Atchafalaya 
Rivers4'5 - 1948 - 318,8334 
St. Francis and L'Anguille Rivers and 
Blackfish Bayou, AR"2 - 1942 92,000 300,449- 
White River, AR (below Newport) - 1984 169,994 22,456,705- 
Wolf River (Memphis Harbor), TN - 1984 586,500 10,845,364 1959 
1. No commerce. 4. Completion date not available. 
2. Existing project is for maintenance only. 5. No funrds available under this project. Work being 
3. Recommended for abandonment in H. Doc. 467, 69th carried on under "Appropriation, Flood Control, Mississippi 
Cong., 1st sess. River and Tributaries." 
13-4

MEMPHIS, TN, DISTRICT 
OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
Project 
Big Creek Canal, Millington, TN 
Big Creek and L'Anguille River, White 
River Basin, AR' 
Bradford, TN 
Clarendon to Laconia Circle, 
White River Basin, AR' 
Cottonwood Slough pumping plant. IL 
Drinkwater Sewer. MO 
Dyersburg, TN" 
Dyersburg, TN (SW) 
Grays Creek Canal 
Shelby Co., TN 
Hatchie River, Alcorn Co., MS 
Huntingdon. TN 
Long Lake Area 
Helena. AR 
Memphis. Wolf River, and 
Nonconnah Creek. TN 
Mounds and Mound City, 
Ohio River Basin. IL 4 
Nixon Creek. TN2' 
Nonconnah Blvd., 
Nonconnah Creek. TN 
Nonconnah Creek, 
Interceptor Sewer, 
Memphis, TN 
N. Second St., Memphis, TN 
(Wolf River Bridge) 
Sandy Creek 
Jackson, TN 
St. Francis River 
Highway No. 90 AR 
Treasure Island, MO 
Turner Creek, Corinth, MS 
US Hwy 51, Nonconnah Creek, TN 
W. Hickman, Area, Hickman, KY 
For Last Cost to Sep. 1989 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Deauthorized Report For: Construction Maintenance Completed 
- 1977 $ 70,363 $ - 
6 May 81 
6 May 81 
Sep 1980 
Jul 1983 
1937 
1984 
1964 
1984 
1962 
1981 
1985 
1987 
1983 
1983 
1960 
1955 
1952 
1983 
1987 
1983 
1985 
1985 
1981 
1987 
1984 
1983 
95,061 
147,000 
1,494,828 
229,649 
1,820,869 
155,280 
85,200 
2,900,281 
Dec 1983 
Feb 
Jun 
Jun 
Oct 
Aug 
1964 
1980 
1962 
1976 
1985 
Feb 1986 
61,281 
11,141,199 
1,132,704 
62,821 
249,999 
259,000 
249,999 
238,000 
161,000 
861,528 
100,600 
369,200 
1,674,180 
May 1959 
Oct 19595 
Dec 1951 
Nov 1981 
Dec 1986 
Sep 1980 
Dec 1984 
Sep 1985 
Mar 1978 
Mar 1987 
Mar 1983 
Oct 1976 
1. Inactive, awaiting local cooperation. 
2. Authorized b Chief of Engineers under small project 
authority, Sec. 205, Flood Control Act of 1948, as amended. 
3. Includes $21,863 contributed funds. 
4. Work being completed under Mississippi River and 
Tributaries project. 
5. Exclusive of Cache River Pumping Station. 
13-5 
TABLE 13-D 
-

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 13-E ACTIVE GENERAL INVESTIGATIONS 
(96x3121) 
Federal Cost Totals by 
Item and CWIS Number FY 89 Categories 
SURVEYS (Category 100) 
Miscellaneous Activities (170) 
Special Investigations (171) -17250 $ 20,754 
Dam Safety Criteria Studies (173) 4,265 
25,019 
Coordination Studies with Other 
Agencies (180) 
Planning Assistance to States (186) 17,214 
TOTAL (Category (100) $ 42,233 
COLLECTIONS AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 232,345 
TOTAL (Category 200) $232,345 
GRAND TOTAL GENERAL INVESTIGATIONS $274,578 
13-6

ST. LOUIS, MO, DISTRICT *
This district comprises those portions of southwestern 
Illinois and eastern Missouri embraced in drainage 
basin of Mississippi River and its western tributaries, 
exclusive of the Missouri River, from the 
mouth of the Ohio River to mile 300, and of its eastern 
tributaries to Hamburg Bay at mile 261 on left bank, 
exclusive of tributary basin of Illinois Waterway 
upstream of new La Grange Lock and Dam at mile 
80.15 above confluence of the Illinois and Mississippi 
Rivers. District also includes drainage basin in Missouri 
tributary to the Little River diversion channel. 
Report on the Mississippi River between the Missouri 
River and mile 300 is included in separate report on 
the Mississippi River between the Missouri River and 
Minneapolis, MN. Report on the portion of the Illinois 
River downstream of new La Grange Lock and Dam 
is included in report of the Chicago District on the Illinois 
Waterway, Illinois and Indiana. 
IMPROVEMENTS 
Navigation 
1. Illinois Waterway, IL 
(St. Louis Dist.) .................. 
2. Kaskaskia Riyer, IL.............. 
3. Mississippi River between 
Missouri and Minneapolis, MN 
(St. Louis Dist.) (Includes Melvin 
Price Locks & Dam) ............. 
4. Mississippi River between Ohio 
and Missouri Rivers, 
MO and IL...................... 
5. Southeast Missouri Port, MO ...... 
Flood Control 
6. East St. Louis and vicinity, IL .... 
7. Kaskaskia Island Drainage and 
Levee District, IL ................ 
8. Mauvaise Terre Drainage 
and Levee District, IL ........... 
9. Meramec River Basin, MO ....... 
9A. Pine Ford Lake, MO .............. 
10. McGee Creek Drainage and Levee 
D istrict, IL ...................... 
11. Nutwood Drainage and Levee 
District, IL ...................... 
12. Rend Lake, Big Muddy 
R iver, IL ......................... 
13. Wood River Drainage and 
Levee District, IL ................. 
Page Flood Control (cont.) 
14-2 
14-2 
14-2 
Page 
14. Inspection of completed flood 
control projects.................... 
15. Navigation work under 
special authorization ............... 
16. Flood control work under 
special authorization ............... 
Multiple-Purpose Project 
14-2 Including Power 
14-3 17. Clarence Cannon Dam and Mark 
Twain Salt River, MO............. 
18. Upper Mississippi River 
Environmental Management 
14-3 Program .......................... 
14-4 
14-4 
14-4 
14-4 
14-5 
14-5 
14-5 
14-5 
Tables 
Table 14-A 
Table 14-B 
Table 14-C 
Table 14-D 
Table 14-E 
Table 14-F 
Cost and Financial 
Statement................. 
Authorizing Legislation ..... 
Other Authorized 
Navigation Projects......... 
Lakes, Levees, and 
Recreational Facilities...... 
Other Authorized Flood 
Control Projects ........... 
Active General 
Investigations (96X3121) .... 
14-6 
14-7 
14-8 
14-10 
14-13 
14-13 
14-14 
14-16 
14-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. ILLINOIS WATERWAY, IL 
(ST. LOUIS DIST.) 
See report on Illinois Waterway, IL and IN, under 
Rock Island District. 
2. KASKASKIA RIVER, IL 
Location. The river rises in Champaign County, IL, 
about 5 miles northwest of Urbana, in east-central 
part of state. It flows southwesterly about 325 miles 
and empties into Mississippi River about 8 miles 
above Chester, IL, or about 118 miles above mouth of 
Ohio River. (See Cincinnati sheet of maps of United 
States published by Army Map Service, scale 
1:500,000.) 
Previous project. For details see Annual Report 
for 1896, page 171. 
Existing project. Improvement for navigation provides 
a channel 9 feet deep and 225 feet wide from 
mouth to Fayetteville, IL. Improvement consists of 
enlarging present channel where required, making 
overbank cutoffs to eliminate sharp bends, and construction 
of a dam at mile 0.8 with a single lock 84 
feet wide and 600 feet long, at an estimated total Federal 
project cost (1984) of $145,060,000. Non-Federal 
project cost is $7,665,000, of which $1,500,000 is local 
contribution. 
Local cooperation. State of Illinois passed legislation 
authorizing Illinois Department of Public Works 
and Buildings to enter into assurances of local cooperation 
with the United States. These assurances have 
been furnished and were accepted on behalf of the 
United States on Sep. 10, 1965; these assurances were 
supplemented on Aug. 7, 1972, to incorporate the provisions 
of Public Law 91-646. 
Operations and results during fiscal year. The 
project is physically complete. Hired labor performed 
operation and maintenance of the project. 
3. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN (ST. LOUIS 
DIST.) (INCLUDES MELVIN 
PRICE LOCKS & DAM) 
See separate section entitled "Mississippi River be 
tween Missouri River and Minneapolis, MN," printed 
in the Annual Report of the Chief of Engineers. 
4. MISSISSIPPI RIVER BETWEEN 
OHIO AND MISSOURI RIVERS, 
MO AND IL 
Location. Mississippi River rises in Lake Itasca, 
MN, and from that lake flows southerly about 2,340 
miles and empties into the Gulf of Mexico. Portion 
included in this report embraces the 195-mile section 
known as middle Mississippi, between tributary Ohio 
and Missouri Rivers about 974 to 1,169 miles from the 
gulf. See folder by Corps of Engineers of Navigation 
Charts, Middle and Upper Mississippi River, Cairo, 
IL, to Minneapolis, MN. 
Previous projects. For details see page 1879 of 
Annual Report for 1915, and page 1014 of Annual 
Report for 1938. 
Existing project. The existing project provides for 
obtaining and maintaining a minimum channel depth 
of not less than 9 feet, a minimum width of not less 
than 300 feet at low water, with additional widths in 
bends from mouth of Ohio River (about 974 miles 
from gulf) to northern boundary of city of St. Louis, 
mile 191, thence 200 feet wide, with additional width 
in bends to mouth of Missouri River, mile 195; to be 
obtained: (1) by regulating works, for closing secondary 
channels, contracting river by building new banks 
where river width is excessive and protecting new and 
old banks from erosion where necessary to secure permanency 
at an estimated total Federal cost (1989) of 
$199,000,000; (2) by dredging to maintain project channels; 
(3) by construction of works authorized for Chain 
of Rocks reach in 1945 River and Harbor Act, which 
approved a comprehensive plan for development of 
the river at Chain of Rocks to provide for construction 
of a lateral canal at a cost of $59,720,600; and (4) by 
construction of a fixed-crest rock-fill dam about 900 
feet below Chain of Rocks Bridge, authorized by 1958 
River and Harbor Act, at cost of $4,353,000, excluding 
$7,000 costs to Coast Guard for aids to navigation. 
Estimated total Federal project cost (1986) is 
$245,073,600. A small boat harbor opposite Chester, 
IL, was deauthorized and excluded from foregoing 
cost estimate. See H. Doc. 669 (76th Cong., 3rd sess.) 
for report of Chief of Engineers dated Feb. 27, 1940, 
containing a general plan for improvement of Mississippi 
River between Coon Rapids Dam and mouth of 
Ohio River for purposes of navigation, power development, 
flood control, and needs of irrigation. 
Local cooperation. None required. 
Terminal facilities. Existing facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Regulating 
Works: contract was continued on stone dike 
and revetment construction as was engineering and 
design and supervision and administration. Construction 
on existing project began in 1881 and project has 
been in beneficial use practically from its inception. 
Projects on Dam 27 and Chain of Rocks are complete. 
Work on the project is about 77 percent complete. 
Channel as a whole has been greatly improved by the 
work completed to date. Dredging is required at low 
stages to remove temporary shoals and maintain 
required channel depths. River is generally above 
10-foot stage, St. Louis gage, from latter part of February 
to the latter part of August, during which time 
project channel depths generally prevail without 
dredging. During FY 1988 and FY 1989 low water 
14-2

ST. LOUIS, MO, DISTRICT 
conditions (drought) have increased maintenance 
dredging. To improve navigation depths a rock 
removal contract began Oct. 1988 through FY 1989 
(81% of original contract). 
Maintenance. Work consisted of 8,725 feet of dike 
and 47,935 feet of revetment repair. U.S. plant and 
hired labor plus contract dredging performed channel 
dredging removing 6,079,800 cubic yards of material 
from main channel. Condition and operation studies, 
recreation planning, engineering and design, and operation 
and maintenance of Lock and Dam 27 continued. 
5. SOUTHEAST MISSOURI PORT, 
MISSOURI 
Location. The project is located on the right bank 
of the Mississippi River at river mile 30 above the 
Ohio River in the counties of Scott and Cape Girardeau 
in Southeast Missouri. 
Existing project. Pursuant to Sec. 107, Public Law 
86-645, as amended, a slackwater channel, 2,000 feet 
long, 230 feet wide, and 9 feet deep is being constructed. 
This project will provide a navigation channel 
for development of a port and related facilities 
at this location. Total estimated cost is $5,410,000 
(2,149,000 non-Federal). 
Location cooperation. On May 22, 1987, a Local 
Cooperation Agreement was signed between the Port 
District and the St. Louis District, Corps of 
Engineers. 
Results during fiscal year. Construction of the 
channel was completed in early Fiscal Year 1988. 
Soon thereafter, a large slide occurred on the south 
bank of the harbor at the location where Southeast Missouri 
Port Authority has undertaken construction of 
a dock. Repair of this slide was done in early Fiscal 
Year 1989, with repair costs shared in accordance 
with the local cooperation agreement. 
Flood Control 
6. EAST ST. LOUIS AND 
VICINITY, IL 
Location. Project is in St. Clair and Madison Counties, 
IL, on the left bank of the Mississippi River 
between river miles 175 and 195 above the Ohio River. 
Project includes all bottom lands between bluffs on the 
east and Mississippi River and Chain of Rocks Canal 
on the west, and extends from Cahokia diversion channel 
on the north to Prairie du Pont Creek on the south. 
(See Corps of Engineers Navigation Charts, Middle 
and Upper Mississippi River, Cairo, IL, to 
Minneapolis, MN.) 
Existing project. The 1936 Flood Control Act 
authorized raising and enlarging existing levee systems 
by construction or reconstruction of 19.8 miles of 
levee, including 3.1 miles of floodwall, together with 
necessary appurtenant works consisting of gravity 
drainage structures, highway and railroad closure 
structures, alterations and reconstruction of existing 
pumping plants, alterations to railroad bridges and 
approaches at levee crossings, service roads on levee 
crown, and seepage control measures. Work under 
this authorization provides the area protection against 
a flood of about 200-year frequency. The completed 10 
miles of levee along Chain of Rocks Canal and Lock 
27 provide flood protection on the landward side integral 
with and to the same degree as the East St. Louis 
levee. Final cost of work under this authorization is 
$22,550,100. The Flood Control Act of 1965 modified 
existing project to provide for channel improvements, 
diversion ditches, flood plain detention areas, a reservoir 
on Little Canteen Creek, and a pumping plant to 
considerably reduce damages resulting from interior 
flooding. This act also authorized reconstruction of a 
channel stabilization dam in Cahokia Creek diversion 
channel to provide protection to adjacent levees and 
bridges from scour and eventual loss. Postauthorization 
studies have indicated that flood plain detention 
areas, the reservoir on Little Canteen Creek and 
other related flood control measures in the Cahokia- 
Harding Ditch Area are not economically feasible. 
Also, further studies of the channel stabilization dam 
in Cahokia Creek diversion channel have been 
deferred due to lack of support from the local sponsor 
of the project. Estimated total Federal project cost of 
work under this authorization is $33,600,000 (1985), 
$22,020,000 for Cahokia-Harding Ditch Area, and 
$11,580,000 for Blue Waters Ditch. Non-Federal cost 
is $20,770,000. The 1988 Energy and Water Development 
Appropriations Act authorized repair and rehabilitation 
of pump stations and appurtenant works, 
channels and bridge structures. The estimated total 
cost of this work, as shown in the Committee Report, 
is $25,000,000. (The unapproved estimated total cost, 
Oct. 84 price level, is $42,620,000.) 
Local cooperation. Local interests have fully complied 
with the requirements of local cooperation for 
work under the 1936 authorization. For work authorized 
by Flood Control Act of 1965 requirements of 
local cooperation are fully described on page 14-4 of 
Fiscal Year 1980 Annual Report. Formal assurances 
were accepted on the Blue Waters Ditch area on Jun. 
25, 1981. For work under the 1988 authorization, local 
interests have provided a letter of intent and a Local 
Cooperation Agreement is currently being processed 
for the first item of construction. 
Operations and results during fiscal year. 
Scheduled construction of project modifications 
authorized by Flood Control Act of 1965 is complete. 
This work included ditching contracts and the Blue 
Waters Ditch pumping station. Work authorized by 
Flood Control Act of 1936 is also complete. The East 
St. Louis pumping station, constructed under the 
authority of the Flood Control Act of 1936, sustained 
damage during an October 1986 flood event and 
major repairs were accomplished with non-Corps of 
Engineers funds. 
14-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
7. KASKASKIA ISLAND DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. In Randolph County, IL, on the right 
bank of the Mississippi River between miles 111 and 
116 above the mouth of the Ohio River. (See Paducah, 
KY, IL, MO, IN, map published by Army Map Service, 
scale 1:250,000.) 
Previous project. For details, see page 1375 of 
Annual Report for 1950. 
Existing project. Project area contains about 9,460 
acres only partially protected against flood stage of 
38.5 feet on the Chester, IL, gage. Flooding occurs 
about once in every 7.3 years with an average duration 
of 26 days, causing substantial damage. The 1962 
Flood Control Act (H. Doc. 519, 87th Cong., 2nd sess.) 
provides for enlarging and raising the existing levee 
about 8 feet to provide protection against a flood 
having a frequency of once in 50 years. Estimated 
total Federal project cost (1986) is $14,100,000. Non- 
Federal cost is $2,100,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-6 of Fiscal Year 
1980 Annual Report. Formal assurances from the Kaskaskia 
Island Drainage and Levee District were 
accepted on behalf of the United States on Jan. 23, 
1980. 
Operations and results during fiscal year. Preconstruction 
planning is complete. All construction of 
gravity drains, levee embankment and installation of 
wildlife plantings is complete (1989). 
8. MAUVAISE TERRE DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Scott County, IL, 
on the left bank of the Illinois River between miles 
63.5 and 67.0 above the Mississippi River. (See 
Quincy, IL-MO, sheet of maps of the United States, 
published by Army Map Service, scale 1:250,000). 
Existing project. Project provides for raising a portion 
of the existing levee and construction of two railroad 
closure structures. Project will provide protection 
to 5,700 acres of land against a flood of 100-year 
frequency. Based on cost sharing requirements prior 
to enactment of Public Law 99-662, the estimated total 
Federal project cost (1987) is $1,840,000. Non-Federal 
cost is $185,000. Project was authorized by the Energy 
and Water Development Appropriation Act of 1985, 
Public Law 98-360, 98th Cong., 2nd sess. 
Local cooperation. The village of Naples, IL, 
signed a letter of intent, dated Mar. 13, 1985, indicating 
a willingness to comply with the terms of local 
cooperation including provisions of the Uniform Relocations 
and Real Property Acquisition Policy Act of 
1970 (Public Law 91-646) and Section 221 of the Flood 
Control Act of 1970 (Public Law 91-611). Local cooperation 
requirements are: furnish without cost to the 
United States all lands, easements, and rights-of-way 
necessary and accomplish all relocations necessary for 
the construction of the project; hold and save the 
United States free from damages due to the construction 
works, save and except damages due to the fault 
or negligence of the United States or its contractor; 
and maintain and operate all the works after completion 
in accordance with regulations prescribed by the 
Secretary of the Army. It has been determined that 
cost sharing must be in accordance with the provisions 
of Public Law 99-662, which requires a substantial 
increase in cost of local cooperation. The village 
of Naples has determined that they are unable to 
assume responsibility for cost sharing as required by 
Public Law 99-662. Therefore, construction of the project 
cannot be undertaken. 
Operations and results during fiscal year. It was 
determined that local interests will not be able to cost 
share on this project. Construction of the project has 
been deferred. 
9. MERAMEC RIVER BASIN, MO 
Location. The basin lies within the State of Missouri 
and comprises 3,980 square miles. The river is 
a west bank tributary of the Mississippi River at mile 
161 above mouth of Ohio River. Major streams in the 
basin include the Meramec, Big, and Bourbeuse Rivers. 
The basin extends about 100 miles southwesterly 
from St. Louis into the Ozark Highlands. (See St. 
Louis, MO, and Rolla sheets of maps of the United 
States, published by Army Map Service, scale 
1:250,000.) 
Existing project. The project provides for the construction 
of Meramec Park and Union Lakes, authorized 
by the 1938 Flood Control Act; and Pine Ford, 
Irondale, and 1-38 Lake projects, and 19 angler-use 
sites, authorized by the 1966 Flood Control Act. 
Under the plan, Irondale and 1-38 Lakes will reduce 
flood damages in the upper Big and Bourbeuse Rivers. 
Meramec Park, Union, and Pine Ford Lakes will 
substantially reduce flooding in the lower basin area 
and will lower flood crests on the Mississippi River. 
Project will also provide water supply, water quality 
control, recreation, and fish and wildlife conservation. 
Public Law 97-128 authorized structural and nonstructural 
flood control measures along the lower 
Meramec River in Jefferson and St. Louis Counties, 
Missouri. Subsequent studies determined that a local 
flood protection project for Valley Park, Missouri, was 
justified at an estimated total cost of $11.8 million. 
(October 1984 price level). (See Table 14-D for additional 
data on this comprehensive project.) 
9A. PINE FORD LAKE, MO 
Location. Proposed dam is on Big River at mile 
43.8, about 45 miles southwest of St. Louis. The Big 
River is a tributary of the Meramec. Lake would 
extend about 34 miles up Big River. (See St. Louis, 
MO, sheet of maps of the United States, published by 
Army Map Service, scale 1:250,000.) 
14-4

ST. LOUIS, MO, DISTRICT 
Existing project. Project provides for construction 
of a compacted earth-fill dam with a concrete chute 
spillway. Dam will be 141 feet high and 2,070 feet 
long. Construction of new roads, improvements of existing 
roads, alterations to pipeline, power and telephone 
lines, and construction of recreational facilities are 
included. Maximum storage capacity will be 285,000 
acre-feet. Estimated total project cost (1984) is 
$147,000,000, of which $8,173,200 and $22,900,000 are 
local reimbursements for water supply and recreation 
and fish and wildlife respectively. 
Local cooperation. Local interests must contribute 
toward cost of project for storage allocation to water 
supply in accordance with the Water Supply Act of 
1958. 
Operations and results during fiscal year. Preconstruction 
planning previously funded but not 
completed. 
10. McGEE CREEK DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. The levee district is in Brown and Pike 
Counties, IL, on the right bank of Illinois River 
between miles 67.2 and 75.1 above the Mississippi 
River. (See Kansas City sheet of maps of United 
States, published by Army Map Service, scale 
1:500,000.) 
Existing project. Project provides for reconstruction 
of 14.7 miles of levee, construction of a new pumping 
plant, closure structure, and seepage control measures. 
Project will provide protection to about 12,080 
acres of agricultural land against a flood of about 
50-year frequency. Estimated total Federal project 
cost (1983) is $25,500,000. Non-Federal cost is 
$930,000. Project was authorized by 1962 Flood Control 
Act (H. Doc. 472, 87th Cong., 2nd sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-9 of Fiscal Year 
1980 Annual Report. Local interests have executed 
assurances in compliance with Public Law 91-611 and 
Public Law 91-646. 
Operations and results during fiscal year. The 
project is complete. 
11. NUTWOOD DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The levee district is in Greene and Jersey 
Counties, IL, on the left bank of the Illinois River 
between miles 15.2 and 23.7 above the Mississippi 
River. (See Quincy, IL-MO, sheet of maps of the 
United States, published by Army Map Service, scale 
1:250,000.) 
Existing project. Project provides for raising and 
enlarging 11.4 miles of levee, construction of 1.0 mile 
of new levee, altering discharge line of pumping station, 
and construction of seepage control measures. 
Project will provide protection to 10,360 acres of land, 
9,635 of which are highly productive agricultural 
lands against a flood of 50-year frequency. Estimated 
total Federal project cost (1986) is $6,510,000. Non- 
Federal cost is $450,000. Project was authorized by 
the 1962 Flood Control Act (H. Doc. 472, 87th Cong., 
2nd sess.). 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-11 of Fiscal Year 
1980 Annual Report. Local interests have indicated a 
willingness to meet the terms of local cooperation. 
Operations and results during fiscal year. Due 
to a lack of economic justification the project has been 
recommended for deferral. 
12. REND LAKE, BIG MUDDY 
RIVER, IL 
Location. The lake is in Franklin and Jefferson 
Counties in southern Illinois. The dam is on Big 
Muddy River, 103.7 miles upstream from its confluence 
with the Mississippi River, and about 3 miles 
northwest of Benton, IL. (See Belleville sheet of maps 
of United States, published by Army Map Service, 
scale 1:250,000, and Geological Survey quadrangle 
maps, 1:62,500.) 
Existing project. The project provides for construction 
of an earth dam, ungated concrete spillway, relocation 
of roads and utilities, recreational facilities, 
access roads, and service facilities. In addition, two 
subimpoundment dams were constructed on upper 
arms of reservoir to enhance fish and wildlife value 
of project. Reservoir has an area of 24,800 acres, and 
a storage capacity of 294,000 acre-feet. Project provides 
flood control, water supply, low-flow regulations, 
conservation of fish and wildlife, recreation, and area 
development. Estimated total Federal project cost 
(1983) is $43,100,900, of which $12,197,700 is for lands 
and damages. Non-Federal local contribution for 
water supply is $9,941,300. Federal cost for code 711 
recreation facilities is $1,060,900. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-12 of Fiscal Year 
1980 Annual Report. Assurance of local cooperation 
and water supply contract have been executed and 
approved by the Secretary of the Army. 
Operations and results during fiscal year. Real 
estate activities in connection with project completion 
were performed. Lands acquired to date are 39,819 
acres in fee and 906 acres in easements. Project is 
essentially complete. 
Maintenance. Hired labor forces performed operation 
and maintenance of Rend Lake Reservoir. 
13. WOOD RIVER DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. In Madison County, IL, on left bank of 
Mississippi River between river miles 195 and 203 
above Ohio River. District includes bottom lands 
14-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FQR FY 1989 
between river and bluffs and extends from Cahokia 
diversion channel on the south to opposite Lock and 
Dam 26 at Alton, IL, on the north. Small industrial 
cities of Hartford, Wood River, Roxana, and East 
Alton and part of Alton riverfront, lie within the district. 
(See Corps of Engineers Navigation Charts, 
Middle and Upper Mississippi River, Cairo, IL, to 
Minneapolis, MN.) 
Existing project. The 1938 Flood Control Act 
authorized raising, enlarging, and extending existing 
levee system to provide 20.8 miles of levees and construction 
of appurtenant works consisting of gravity 
drainage structures, highway and railroad closure 
structures, alterations to existing or construction of 
new pumping plants; surfacing service road on levee 
crown, making necessary alterations to railroad 
tracks and bridges at levee crossings, seepage corrective 
measures and construction of a low-water dam at 
mouth of Wood River. Project will afford protection 
to this district against a flood of about 200-year frequency. 
Estimated total construction cost (1982) is 
$18,600,000 (excluding $23,000 contributed funds). 
Flood Control Act of 1965 modified 1938 Flood Control 
Act to provide for construction of a pumping station 
with collector ditches and necessary appurtenant 
facilities for removal of water impounded by existing 
levee. This portion of the project has been declared 
inactive. 
Local cooperation. Fully complied with for work 
authorized by 1938 Flood Control Act. 
Operation and results during fiscal year. Work 
authorized by the 1938 Flood Control Act is complete. 
The remaining closure will be made as part of the 
Lock and Dam 26 project and will be in conjunction 
with removal of railroad bridge. 
14. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was accomplished at 
a cost of $340,125 for the fiscal year. Total cost as of 
end of fiscal year is $6,829,045. 
15. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
No activity during this fiscal year. 
16. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Preauthorization study costs for fiscal year were 
$20,049 for St. Peters, MO; and $29,266 for Boise 
Brule Levee and Drainage District, MO; $6,862 for 
Lower Salt River, Pike County, MO; $6,037 for Mississippi 
Levee System, Monroe; E. Cape Girardeau Main 
Ditch, IL, $2,443; and Modoc Levee and Drainage District, 
Prairie, IL, $7,304. 
The Water Resources Development Act of 1986 
authorized construction of a levee approximately onefifth 
of a mile long to be built in Meredosia, IL, at 
a total cost of $80,000. This work was accomplished 
by local interests. 
Emergency flood control activities--repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation). 
Federal costs for the fiscal year were $180,731 for 
disaster preparedness, and $82,282 for rehabilitation. 
Multiple-Purpose Project 
Including Power 
17. CLARENCE CANNON DAM AND 
RESERVOIR, SALT RIVER, MO 
Location. Salt River rises in Schuyler County, 
about 12 miles south of Missouri-Iowa State line. It 
flows southeasterly about 192 miles and empties into 
Mississippi River about 2 miles above Louisiana, MO, 
or about 284 miles above mouth of Ohio River. (See 
Kansas City and Quincy sheets of maps of United 
States published by Army Map Service, scale 
1:500,000, and Geological Survey quadrangle maps, 
1:250,000.) 
Previous project. For details, see page 645 of 
Annual Report for 1968. 
Existing project. Project provides for construction 
of a multiple-purpose reservoir, including power, 
flood control, water supply, navigation storage, pollution 
abatement, fish and wildlife conservation, and recreation. 
Dam consists of a compacted earth embankment 
with a concrete spillway controlled by tainter 
gates. Dam and spillway are about 1,700 feet long. 
Spillway structure consists of an ogee overflow section 
surmounted by four 50- by 30-foot tainter gates. Reservoir 
will have a storage capacity of 1,428,000 acrefeet 
for use of flood control, future domestic 
and industrial water supply, sediment storage, and 
power generation. Project plan provides for installation 
of one 27,000 KW conventional unit and one 
31,000 KW reversible unit for pumped storage operations. 
Total Federal project cost estimate (1984) is 
$330,000,000 of which $22,420,000 is for lands and 
damages; $14,300,000 for water supply; $76,000,000 
for hydropower. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-13 of Fiscal Year 
1980 Annual Report. Assurances have been received 
from the State of Missouri and approved by the Chief 
of Engineers. 
14-6

ST. LOUIS, MO, DISTRICT 
Operations and results during fiscal year. Work 
is complete on all major items. Lands acquired to date 
are 55,277 acres in fee and 10,068 acres in easements. 
Project is essentially complete. 
18. UPPER MISSISSIPPI RIVER 
ENVIRONMENTAL MANAGEMENT 
PROGRAM 
Location. The portion of the Upper Mississippi 
River within the boundaries of the St. Louis District 
extends from the mouth of the Ohio River (river 
mile 0) to river mile 300, downstream of Lock and 
Dam 22. 
Existing project. The project is composed of five 
elements: Habitat Rehabilitation and Enhancement, 
Long-term Resource Monitoring, Recreation, Studies 
of Recreation Impacts and Navigation Traffic Monitoring. 
The overall program, involving five states, three 
Engineer Districts and two Corps of Engineers Divisions, 
is administered by the North Central Division. 
For the St. Louis District's part of the program, 
16 habitat rehabilitation projects have been proposed, 
of which one (1) is under construction with 9 
others funded for planning & preliminary engineering 
(DPR's) in FY 89. Through Fiscal Year 1989, funds 
allocated to the St. Louis District have amounted to 
$1,442,000. The authorization limit for the overall program, 
projected over a 10-year period, is $191,415,000. 
Local cooperation. The terms of local cooperation, 
as established by Public Law 99-662, will vary 
according to the nature of the project, land ownership 
and pre-existing management responsibilities. A 
Local Cooperation Agreement has been executed 
between the Missouri Department of Conservation 
and the Assistant Secretary of the Army for the 
Clarksville Refuge project, the first scheduled construction 
project for this program within the St. Louis 
District. 
Operations and results during the fiscal year. 
One (1) construction contract was awarded; one (1) 
detailed project report (DPR) was completed with 4 
DPR's initiated on other projects. Mapping & preliminary 
data collection for DPR's has begun on 
4 additional projects. 
14-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 14-A 
See 
Section 
in Text Project 
2. Kaskaskia River 
IL (Regular 
Funds) 
(Contrib. Funds) 
4. Mississippi River 
Between Ohio and 
Missouri Rivers 
(Includes Chain 
of Rocks) 
5. Southeast Missouri 
Port, MO 
(Contrib. Funds) 
6. East St. Louis and 
Vicinity, IL 
(Contrib. Funds) 
7. Kaskaskia Island 
Drainage & Levee 
District, IL 
8. Mauvaise Terre 
Drainage & Levee 
District, IL 
9A. Pine Ford 
Lake, MO 
10. McGee Creek 
Drainage & 
Levee District, 
IL 
11. Nutwood Drainage 
& Levee 
District, IL 
COST AND FINANCIAL STATEMENT 
Total Funds to 
Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
$14,300,000 
14,204,126 
1,372,000 
1,177,658 
18,626
0 
3,541,000 
3,415,685 
9,545,000 
9,771,652
00 
00 
1,890,000 
2,446,626 
119,000 
516,340 
957,000 
1,626,323
0 
337,089 
-36,000 
721
0 
136,924 
$ 15,000 
192,628 
1,134,000 
1,346,290
0
0 
4,594,000 
4,667,633 
12,262,000 
12,566,762 
660,000 
480,601
00 
-112,000 
134,522
0 
99,176 
3,951,000 
4,073,697 
-15,000 
49,575
0 
341 
130,000 
75,145 
$ -28,000 
205,202 
1,625,000 
1,531,119
00 
18,455,000 
2,437,584 
13,527,000 
13,415,950 
1,380,000 
1,574,510 
1,425,210 
1,424,467
0 
213,660
00 
4,030,000 
3,515,195 
4,000 
52,889
00 
-7,000 
161,063
00 
$ 0
8 
1,191,500 
1,322,007
0
0 
3,948,000 
17,569,473 
22,520,500 
22,533,237 
1,180,000 
1,155,537 
178,894 
241,387 
150,000 
596,594
00 
-500,000 
143,107
00 
00 
0 
15 
14-8 
$147,387,0001 
147,387,0001 
15,681,756 
15,684,662 
1,158,356 
1,118,160 
201,501,6002 
198,941,8352 
263,265,6333 
262,976,8913 
3,220,000 
3,210,648 
1,604,104 
1,665,854 
16,997,3264 
17,351,170b 
961,750 
961,750 
16,188,000 
16,179,667 
589,000 
589,000 
3,644,001 
3,644,001 
25,043,300 
25,043,255 
670,000 
670,000

ST. LOUIS, MO, DISTRICT 
TABLE 14-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total Funds to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
12. Rend Lake, Big New Work 
Muddy, IL Approp. 0 0 0 0 43,700,900 
(Regular Funds) Cost 17,224 19,926 9,188 0 43,700,900 
Maint. 
Approp. 2,759,600 2,558,822 3,082,000 3,065,000 34,722,6228 
Cost 2,812,138 2,620,317 2,972,608 3,106,641 34,457,5928 
Code 711 Funds New Work 
Approp. 0 0 0 0 1,060,900 
Cost 0 0 0 0 1,060,900 
(Contrib. Funds) New Work 
Contrib. 0 0 0 0 9,941,2789 
Cost 0 0 0 0 9,941,2789 
Maint. 
Contrib. 300,000 532,627 490,556 347,131 4,856,617 
Cost 247,328 582,664 375,860 469,993 4,856,564 
13. Wood River New Work 
Drainage & Levee Approp. 118,000 500,000 -44,000 0 17,163,821 o 
District, IL Cost 416,517 463,192 33,367 0 17,163,8210 
17. Clarence Cannon New Work 
SDaalmt R ainvder ,R MesOer voir, Approp. 820,000 673,000 0 0 312,692,0281 Cost 1,795,702 1,625,900 678,367 325,533 312,293,70411 
Maint. 
Approp. 3,929,600 4,077,322 4,733,000 4,727,000 29,909,982 
Cost 3,633,059 4,340,515 4,496,082 5,126,986 29,843,676 
1. Excludes $10,461 expended on previous project. 
2. Excludes previous project cost of $1,416,620. 
3. In addition $3,109 was expended for rehabilitation. 
4. Includes $8,072,326 for work authorized by Flood 
Control Act of 1965. 
5. Includes $7,921,939 for work authorized by Flood 
Control Act of 1965. 
6. Includes $200,000 for definite project under 1938 
Flood Control Act. 
7. Excludes $6,800,700 for previous project. 
8. Excludes $550,000 Area Development Administration 
Funds allotted to the State of Illinois for increased 
construction costs of Interstate Highway 57 to meet project 
requirements, and excludes $449,093 Area Redevelopment 
Administration Funds allotted to the Corps. 
9. Includes $6,103,711 credit to State of Illinois for 
work in kind. 
10. Funds are for work authorized by Flood Control 
Act of 1938. 
11. Includes $216,628 for definite project study under 
1938 Flood Control Act. 
14-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 14-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 19071 
Mar. 3, 19051 
Jun. 25, 1910 
Jan. 21, 1927 
Jul. 3, 1930 
Mar. 2, 1945 
Sep. 3, 19543 
Jul. 3, 19584 
Oct. 21, 1978 
Dec. 29, 1981 
Aug. 15, 1985 
and Nov. 17, 
1986 
1960 River and 
Harbor Act as 
amended, 
Section 107 
Nov. 17, 1986 
Jun. 22, 1936 
Oct. 27, 1965 
Oct. 22, 1976 
KASKASKIA RIVER, IL (See Section 2 of Text) 
Construct canal, lock, and dam to provide a 9-foot navigation 
channel from mouth to Fayetteville, IL. 
MISSISSIPPI RIVER BETWEEN OHIO AND MISSOURI 
RIVERS (See Section 4 of Text) 
Project for regulating works in 1881. (To obtain a minimum 
depth of 8 feet.) 
Dredging introduced as part of the project. 
These acts practically abrogated that part of project for middle 
Mississippi which proposed regulating works. 
Regulating works restored to project and appropriations begun 
with a view to completion of improvement between Ohio and 
Missouri Rivers within 12 years at an estimated cost of $21 
million, exclusive of amounts previously expended. 
For 9 feet deep and 300 feet wide from Ohio River to northern 
Rivers and Harbors boundary of city of St. Louis. 
Project between northern boundary of St. Louis and Grafton 
(mouth of Illinois River) modified to provide a channel 9 feet 
deep and generally 200 feet wide with additional width around 
bends. 
Modified to provide construction of a lateral canal with lock at 
Chain of Rocks. 
Modified to provide construction of a small-boat harbor opposite 
Chester, IL. 
Modified to provide construction of a fixed crest rockfill dam 
900 feet below Chain of Rocks Bridge. 
MELVIN PRICE LOCKS & DAM (FORMERLY LOCK 
AND DAM NO.26 (REPLACEMENT)) 
Construct new Dam and a 1,200 Foot Lock approximately two 
miles downstream of the existing structure. 
Change name from "Lock and Dam No. 26" to "Melvin Price 
Lock and Dam" upon termination of service in U.S. Congress. 
Construct a second lock, 600 feet long at the Lock and Dam No. 
26. (Replacement) Project. 
SOUTHEAST MISSOURI PORT, MO (See Section 5 of Text) 
Construct harbor channel with adjacent landfill. 
CAPE GIRARDEAU, JACKSON METROPOLITAN 
AREA, MO 
As outlined in the Report of the Chief of Engineers dated Dec. 8, 
1984, the Water Resources Development Act of 1986 authorizes 
flood control and related recreational improvements in the 
Cape La Croix Creek Watershed. 
EAST ST. LOUIS AND VICINITY, IL (See Section 6 of Text) 
Raise and enlarge existing levee. 
Construct pumping plant and other modifications to reduce 
interior flooding. 
Construct Blue Waters Ditch as independent section. 
Repair and rehabilitate pump stations and appurtenant works, 
channels and bridges. 
S. Doc. 44, 87th Cong., 1st 
sess. 
Annual Report, 1881, p. 
1536. 
Committee Doc. 9, 69th 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 12, 70th 
Cong., 1st sess. 
H. Doc. 231, 76th Cong., 1st 
sess. 
H. Doc. 230, 83d Cong., 1st 
sess. 
Public Law 95-502, 95th 
Cong. 
Public Law 97-118, 97th 
Congress. 
Public Law 99-88 and 
Public Law 99-662, 99th 
Cong. 
Public Law 99-662, 99th 
Cong., 2d Sess. 
Special report on record in 
OCE. 
H. Doc. 329, 88th Cong., 2d 
sess. 
Public Law 94-587, 94th 
Cong. 
Public Law 100-202, 100th 
Cong. 
14-10

ST. LOUIS, MO, DISTRICT 
TABLE 14-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 17, 1986 
Jul. 14, 1984 
Jun. 28, 1938 
Nov. 7, 1966 
Dec. 29, 1981 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 17, 1986 
ELDRED AND SPANKEY DRAINAGE AND LEVEE 
DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
HARTWELL DRAINAGE AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
HILLVIEW DRAINAGE AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
KASKASKIA ISLAND DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 7 of Text) 
Raise and enlarge existing levee. 
MALINE CREEK, MISSOURI 
As outlined in the Report of the Chief of Engineers dated Nov. 2, 
1982, the Water Resources Development Act of 1986 authorizes 
flood control, recreation and environmental improvements. 
MAUVAISE TERRE DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 8 of Text) 
Raise and enlarge existing levee and other modifications. 
MERAMEC RIVER BASIN, MO (See Section 9 of Text) 
Construct reservoirs and local protection project. 
Construct Pine Ford, Irondale, and 1-38 dams and 19 Angler-use 
sites. 
Undertake structural & nonstructural flood control measures. 
MCGEE CREEK DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 10 of Text) 
Reconstruct existing levee and construct pumping plant to 
reduce flooding. 
MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE 
AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
NUTWOOD DRAINAGE AND LEVEE DISTRICT, IL (See 
Section 11 of Text) 
Raise and enlarge existing levee and other modifications. 
REND LAKE, BIG MUDDY RIVER, IL (See Section 12 of 
Text) 
Construct dam at Benton, Ill., and subimpoundment dams on 
upper arms of reservoir. 
STE. GENEVIEVE, MO 
As outlined in the Report of the Board of Engineers for Rivers 
and Harbors dated Apr. 16, 1985, the Water Resources 
Development Act of 1986 authorizes construction of a levee and 
a pumping plant to protect the city from Mississippi River and 
Gabouri Creek floods. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 519, 87th Cong., 2d 
sess. 
Public Law 99-662, 99th 
Cong., 2d Sess. 
Energy and Water 
Development Approp. 
Act of 1985, 98th 'Cong., 2nd 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
H. Doc. 525, 89th Cong., 2d 
sess. 
Public Law 97-128, 97th 
Cong. Amended Section 
1128, Public Law 99-662, 
99th Cong. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 472, 87th Cong., 2d 
sess. 
H. Doc. 541, 87th Cong., 2d 
sess. 
Public Law 99-662, 99th 
Cong., 2d Sess. 
14-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 14-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
WOOD RIVER DRAINAGE AND LEVEE DISTRICT, IL 
(See Section 13 of Text) 
Jun. 28, 1938 Construct reservoirs and local protection projects. Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
CLARENCE CANNON DAM AND RESERVOIR, SALT 
RIVER, MO (See Section 17 of Text) 
Oct. 23, 1962 Modified act of Jun. 28, 1938 by deleting the reservoir therefrom and H. Doc. 507, 87th Cong., 2d 
reauthorizing it as a separate multiple-purpose project. sess. 
Oct. 27, 1965 Changes name of project from Joanna Dam to present Public Law 89-298, 89th 
designation. Cong. 
1. Also joint resolution, Jun. 29, 1906. 
2. Contains latest published map. 
3. Inactive. 
4. All work completed. 
5. Authorized under provision of Sec. 201 of the Flood 
Control Act of 1965. 
14-12

ST. LOUIS, MO, DISTRICT 
TABLE 14-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 1989 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Cuivre River, MO1 - 1883 $ 12,000 $ - 
Grafton Small Boat Harbor, IL Nov. 1977 19622 - 
Mississippi River at Alton, IL 
Small Boat Harbor Nov. 1977 19582 - - 
Moccasin Springs, MO - 1969 76,4363 - 
Small Boat Harbor opposite Chester, IL Nov. 1977 19542 - - 
Small Boat Harbor opposite Hamburg, IL Nov. 1977 19502 - - 
Wabash Railroad Bridges, Illinois River, 
Meredosia, and Valley City, IL - 1961 2,653,194 1961 
1. Inactive. River declared nonnavigable by act of Mar. 2. Year authorized. 
23, 1900. 3. Excludes $56,605 contributed funds. 
TABLE 14-D LAKES, LEVEES, AND 
RECREATIONAL FACILITIES 
Estimated 
See Required Total Estimated 
Sine cTtieoxnt Project Estimated Non-Federal Cost (Date to Name Federal Cost Cost Revision) 
11. Meramec River Basin, MO Lakes: 
Union2 101,305,000 11,695,000 113,000,000 (1982) 
Pine Ford' 115,926,800 31,073,200 147,000,000 (1984) 
Irondalea 8,744,370 66,700,000 (1982) 
I-382 27,294,000 2,306,000 29,600,000 (1982) 
1. Separate reports are included herein. 
2. See 1979 Annual Report for details. 
14-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 14-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1989 
For Last 
Full Report Operation 
Mo. and Yr. See Annual and Mo. and Yr. 
Project Deauthorized Report For: Construction Maintenance Completed 
Angler-use sites, Meramec Basin, MO Oct. 1986 1967 $ - $ - 
Big Swan Drainage and Levee District, 
Illinois River, IL' Oct. 1986 - - 
Cache River Diversion, IL - 1953 2,837,114 - 1953 
Cape Girardeau, MO, 
reaches Nos. 1, 3, and 4 Oct. 1978 1959 22,000- 
Cape Girardeau, MO, No. 2 - 1965 5,157,805 - 1964 
Carlyle Lake, IL - 1981 46,013,699 45,612,023 Oct. 1976 
Chouteau, Nameoki, and Venice Drainage 
and Levee District, IL- 1955 185,700 - 1955 
Clear Creek Drainage and 
Levee District, IL2- 1964 4,984,500 - 1963 
Columbia Drainage and Levee 
District No. 3, IL - 1981 2,818,000 - Aug. 1981 
Degognia and Fountain Bluff Levee and 
Drainage District, IL - 1959 5,889,500 - 1959 
Dively Drainage & Levee District, IL - 1976 1,720,000 - 1976 
East Cape Girardeau and Clear Creek 
Drainage District, IL - 1963 1,920,600 - 1963 
Eldred, IL Nov. 1979 19623 - - - 
Emergency bank protection for certain 
highway and railroad facilities at Price 
Landing, MO (see Flood Control 
Act of 1944) - 1950 55,415 Emergency - Oct. 1949 repairs to levees on Mississippi, 
Illinois, and Kaskaskia Rivers and flood 
fighting and rescue work (Sec. 5, Flood 
Control Act of 1941, as amended)4 - 1953 - 1,033,279 1951 
Emergency protection for certain highway 
and railroad facilities at Chester, I 
bridge (Sec. 12, Flood Control Act of 1944) - 1952 50,000 - Jan. 1952 
Emergency protection for Illinois approach, 
Chain of Rocks Bridge (Sec. 12, Flood 
Control Act of 1944) - 1946 25,000 - Aug. 1945 
Fort Chartres and Ivy Landing Drainage 
District No. 5, IL- 1970 1,154,800 -1958 
Fort Chartres and Ivy Landing Drainage 
District No. 5 and Stringtown Drainage 
and Levee District No. 4, IL Oct. 1986 1971- 
Grand Tower Drainage and 
Levee District, IL - 1959 4,677,900 -1959 
Harrisonville Levee and 
Drainage District IL - 1981 5,829,000 - Mar. 1981 Indian Creek Area, Illinois River, IL' Nov. 1981 - - 
Kaskaskia Island Drainage and 
Levee District, IL - 1959 297,460 - 1949 
Keach Drainage and Levee District, IL' Oct. 1986 ... 
Lake Shelbyville, IL - 1981 47,927,562 45,704,661 Sep. 1978 
Levee Districts between Carlyle and 
New Athens, IL, Nos. 2, 5, 6, and 7 Nov. 1979 1979 
Levee Districts between Carlyle and 
New Athens, IL, Nos. 3, 4, 8, 10, and 13 Nov. 1979 1979 
Levee Districts between Cowden 
and Vandalia, IL Oct. 1978 1978 496,000 
Meramec Park Lake, MO - 1987 30,552,023 4,659,362 
14-14

ST. LOUIS, MO, DISTRICT 
TABLE 14-E 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1989 
For Last 
Full Report Operation 
Project DMeoa.u tahnodr izYerd. See Annual and Mo. and Yr. Report For: Construction Maintenance Completed 
Meredosia Lake and Willow Creek Drainage 
and Levee District, IL - 1944 249,738 - 1944 
Miller Pond Drainage District, IL - 1955 164,183 - 1955 
Mississippi River Agricultural - 1987 2,137,000 - - 
Area 8, MO 
Mississippi River at St. Louis, MO - 1980 79,265,166 - Jan. 1980 
Mississippi River Agricultural Area 
No. 10, MO Nov. 1979 1967 
Mississippi River Agricultural Area 
No. 12, MO -1967 
Mississippi River, Alton to Gale, IL, 
underseepage measures - - 85,422 - Oct. 1962 
North Alexander Drainage and 
Levee District, IL -1957 939,569 - 1957 
Perry County Drainage and Levee 
District Nos. 1, 2 and 3, MO - 1987 7,968,700 - - 
Prairie du Pont Levee and 
Sanitary District, IL5 - 1970 6,005,127 - 1970 
Prairie du Rocher and vicinity, IL - 1959 3,882,600 - 1959 
Preston Drainage and Levee District, IL - 1959 1,866,910 - 1959 
Richland Creek, IL - 1969 401,000 - - 
Riverland Levee District, MO Aug. 1977 19363 - - 
Scott County Drainage and Levee District, 
Illinois River, IL' Oct. 1986 -- 
Ste. Genevieve County Drainage and 
Levee District No. 1, MO Nov. 1977 19363 - 
St. Louis County Drainage and 
Levee District No. 1, MO Nov. 1977 19363 - - - 
SLtrainngdtionng,, Ft. Chartres and Ivy - 1957 2,123,700 - Aug. 1956 IL 
Union Lake, MO 6 - 1979 4,918,203 4,335 - 
Urban areas at Alton, IL - 1960 192,000 - - 
Village of New Athens, IL - 1981 1,983,000 - Sep. 1981 
Valley City Drainage & Levee District, IL7 - 1967 91,952 - 1967 
Wiedmer Chemical Drainage and Levee 
District, MO Nov. 1977 19363 
1. Projects authorized or modified by Flood Control Act 
of Oct. 23,1962 (see H. Doc. 472, 87th Cong., 2d sess., for details). 
2. Completed except for seepage control measures, which 
are inactive. 
3. Year authorized. 
4. Work complete, now performed under Public Law 99. 
5. Includes $5,235,927 for previous project. 
6. Includes $183,638 for definite project study under 1938 
Flood Control Act. Includes Highway 185 funds. 
7. Authorized by Chief of Engineers (Sec. 205, 1948 Flood 
Control Act, as amended). 
14-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 14-F ACTIVE GENERAL INVESTIGATIONS 
(96X3121) 
Federal Cost Totals by 
Item and CWIS Number FY 89 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Culvre River, MO -12744 
St. Louis Metropolitan Area, MO & IL -55040 
Meramec R. Basin Missouri Study, MO. -14056 
West Frankfort & Vicinity, IL -12643 
Sub-total 
Review of Authorized Projects (160) 
Miscellaneous Activities (170) 
Special Investigations -17250 
Review of FERC Licenses -53857 
Dam Safety Criteria Studies 
Sub-total 
Coordination Studies with Other Agencies (180) 
Dept. of Agric. - Soil Cons. Service -51840 
Plan Assist to State of IL -14817 
Plan Assist to State of MO -14829 
Sub-total 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) -82030, and -82040 
Hydrology Studies (260) -53820 
TOTAL (Category 200) 
CONTINUATION OF PLANNING & ENGINEERING (Category 400) 
River Des Peres, MO -12638 
TOTAL (Category 400) 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
Cape Girardeau - Jackson -12356 
Maline Creek, MO -12297 
Meramec River Basin, MO -75412 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
$ 9,739 
82,031 
1,572 
160,427 
253,770 
20,737 
247 
3,999 
24,983 
5,247 
8,326 
10,350 
23,923 
206,013 
9,739 
303,729 
1,179,636 
203,874 
6,245 
$ 302,676 
$ 215,752 
$ 303,729 
$ 1,389,755 
$ 2,211,912 
14-16

NASHVILLE, TN, DISTRICT * 
This district comprises portions of southern Kentucky, 
southwestern Virginia, western North Carolina, 
northern Georgia and Alabama, northeastern 
Mississippi and practically all of Tennessee except 
western portion, and embraces drainage basins of 
Tennessee and Cumberland Rivers and their tributaries. 
IMPROVEMENTS 
Page General Investigations 
1. Cumberland River, TN and KY ........ 15-2 
2. Tennessee River, TN, AL and KY ...... 15-3 
3. Tennessee-Tombigbee Waterway, AL 
and M S ............................ 15-4 
4. Navigation Work Under Special 
Authorization ...................... 15-4 
Alteration of Bridges 
5. Authorized Alteration of Bridges ...... 15-4 
Flood Control 
6. Big South Fork National River and 
Recreation Area, KY and TN ......... 15-4 
7. Martins Fork Lake, KY .............. 15-5 
8. Middlesboro, Cumberland River 
Basin, KY .......................... 15-5 
9. Tug and Levisa Forks of the Big Sandy 
River and Cumberland River, W VA, 
VA and KY ........................ 15-5 
10. Ohio River Basin (Nashville Dist.) .... 15-6 
11. Inspection of completed flood 
control projects .................... 15-6 
12. Flood control work under special 
authorization ...................... 15-6 
Multiple-Purpose Projects, Including Power 
13. Center Hill Lake, Ohio River 
Basin, TN .......................... 15-6 
14. Dale Hollow Lake, Ohio River Basin, 
TN and KY ........................ 15-6 
15. J. Percy Priest Dam and Reservoir, 
Ohio River Basin, TN ............... 15-7 
16. Laurel River Lake, Ohio River 
Basin, KY ......................... 15-7 
17. Wolf Creek Dam-Lake Cumberland, 
Ohio River Basin, KY ............... 15-8 
Page 
18. Surveys ......................... 15-8 
19. Collection and study of basic data ...... 15-8 
Tables 
Table 15-A Cost & Financial Statement ..... 15-9 
Table 15-B Authorizing Legislation ........ 15-11 
Table 15-C Other Authorized Navigation 
Projects ..................... 15-13 
Table 15-D Not Applicable 
Table 15-E 
Table 15-F 
Other Authorized Flood Control 
Projects ..................... 15-13 
Other Authorized Multiple- 
Purpose Projects, Including 
Pow er ....................... 15-14 
Table 15-G Deauthorized Projects .......... 15-14 
Table 15-H 
Table 15-I 
Table 15-J 
Table 15-K 
Cumberland River, TN & KY, 
Principle Features ............. 15-15 
Tennessee River Lock 
Dimensions .................. 
Tennessee River Total Cost of 
Existing Project .............. 
Ohio River Basin (Nashville 
District) Local Protection ...... 
15-17 
15-518 
15-18 
Table 15-L Reservoirs ................. 15-18 
Table 15-M 
Table 15-N 
Inspection of Completed Flood 
Control Projects ............... 15-19 
Flood Control Work Under 
Special Authorization .......... 15-19 
15-1 
Navigation 
r

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
Navigation 
1. CUMBERLAND RIVER, TN AND KY 
Location. Formed by junction of Poor and Clover 
Forks in Harlan County, Ky., about 694.2 miles above 
its mouth, and flows west to Burnside, Ky., from 
whence it makes a loop southwestward into Tennessee, 
passes Nashville, and returns northwestward to 
Kentucky, emptying into Ohio River near Smithland, 
Ky. (See Geological Survey base maps of Tennessee 
and Kentucky.) 
Previous projects. For details see pages 1898 and 
1901 of Annual Report for 1915, and page 1208 of 
Annual Report for 1938, and pages 1069 and 1070 of 
Annual Report for 1962. 
Existing project. Below Nashville: Improvement of 
Cumberland River between mouth and Nashville was 
authorized for 9-foot navigation; increased project 
depth to be obtained by construction of three moderate 
height dams with lockage facilities, designated as 
Kuttawa (Eureka), Dover, and Cheatham, to replace 
existing locks A to F inclusive below Nashville and 
lock 1 above Nashville. (See table 15-B for authorizing 
legislation.) Subsequent authorities provided for 
construction of hydroelectric power-generating facilities 
at Cheatham Dam, river mile 148.7, and modification 
of project for navigation on Cumberland River, 
Tenn. and Ky., to provide, in lieu of previously authorized 
works at Kuttawa, mile 32.2, and Dover, mile 
100.1, for construction of a multiple-purpose improvement 
consisting of a dam, lock, and powerplant near 
mile 30.6 on lower Cumberland River and a canal for 
navigation and other purposes connecting this reservoir 
with reservoir formed by Kentucky Dam on the 
Tennessee River. The project is known as Barkley 
Dam and Lake Barkley. Provision of interconnecting 
canal, involving excavation of a channel through narrow 
watershed divide about 2.5 miles upstream from 
damsite, permits alternative routes available for navigation 
between either Cumberland or Tennessee 
Rivers and Ohio River, and affords integrated operation 
of Barkley and Kentucky Reservoirs through 
diversion of flows in interests of flood control and 
power production. Cost of modified project for 9-foot 
navigation and multiple-purpose development is 
$178,181,406 Federal funds and $102,966 non-Federal 
funds for recreation facilities under the completed 
projects program. (See table 15-H for listing of principal 
features.) 
Under flood conditions as regulated by upstream 
reservoirs, extreme fluctuation in stage of river below 
Nashville, Tenn., varies at different localities from 
about 16 to 55 feet above minimum pool levels. Ordinary 
fluctuations vary with power flows from as 
much as the allowable 3-foot drawdown below normal 
pool elevation 385 at Cheatham Lock and Dam to a 
range of about 7 feet at Nashville. Seasonal variation 
in normal headwater levels at Lake Barkley is 5 feet, 
which in combination with power flows produces 
fluctuations up to 10 feet below Cheatham Lock and 
Dam. 
Above Nashville: See pages 1693 thru 1696 of 
Annual Report for 1950 for information including 
statistical data on locks and dams 1 to 17 and 21. 
Completion information is shown on pages 1454 of the 
report for 1951. See Table 15-B for Authorizing Legislation. 
Construction of Old Hickory, Carthage, and 
Celina Dams above Nashville was also authorized for 
navigation and power. The dam and reservoir authorized 
for construction on Cumberland River near 
Carthage, Tenn., has been redesignated as Cordell 
Hull Dam and Reservoir. Cost of Old Hickory and 
Cordell Hull projects, including locks, is $132,140,900. 
Estimated cost of Celina Dam (1985) is $213,000,000. 
(See table 15-H at end of chapter for listing of principal 
features.) 
Under flood conditions as presently regulated, including 
effect of surcharge operation of Old Hickory 
project, extreme fluctuations of stage in this section 
of river vary from a range of 35 feet at Nashville 
(mile 191) to a maximum of 46 feet immediately below 
Old Hickory Dam (mile 216.2), and from an 
8-foot variation in headwater at dam to 36 feet in 
vicinity of Carthage, Tenn., (mile 313.5), present 
head of navigation; with variations up to 35 feet at 
Celina, Tenn. (mile 380.8) and 29 feet in tailwater at 
Wolf Creek Dam (mile 460.9). Maximum fluctuations 
under ordinary conditions from power flows vary 
from about 7 feet at Nashville to 14 and 3 feet, respectively, 
in tailwater and headwater of Old Hickory 
Dam, and at other key points as follows: 13 feet at 
Carthage; 18 feet at Celina; and 19 feet at Wolf Creek 
Dam. 
Further details on project authorization for river 
sections below and above Nashville are shown on 
Table 15-B. 
Local cooperation. Under modified project for 9- 
foot navigation and multiple-purpose development, 
recreation features of reservoir components are subject 
to certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 1965. 
Terminal facilities. There are 41 terminals on the 
Cumberland River (3 municipally owned and open for 
public use; 4 government owned facilities and 34 privately 
owned facilities). A total of 21 terminals have 
15-2

NASHVILLE, TN, DISTRICT 
railroad connections. Principal commodities handled 
are petroleum products, stone, sand, gravel, coal, coke, 
iron, steel, chemicals, and grain. Facilities considered 
adequate for existing commerce. For further information 
see page 695 of Annual Report for 1969. 
Operations during fiscal year. New work: None. 
Maintenance: Barkley, Cheatham, Cordell Hull, and 
Old Hickory locks and dams were operated as required. 
Operation and Maintenance improvements 
included completion of bendway dredging above Barkley, 
and continuation of rock removal at five sites on 
the Lower Cumberland. Contracts were awarded to 
revise lock lighting and purchase quoin and miter 
blocks at Barkley; repair dam and spillway gates and 
replace storage building for power plant at Cheatham; 
repair service base building and replace generator 
leads at Old Hickory. 
Total net energy generated at Barkley Dam 
(780,960,935 kw-hr) was made available through Department 
of the Interior to the Tennessee Valley Authority, 
Southern Illinois power Cooperative, Big 
Rivers Rural Electric Cooperative Corporation, and 
Indiana Statewide Rural Electric Cooperative, Inc., 
Hoosier Energy Division. Total net energy generated 
at Cheatham Dam (173,427,427 kw-hr), Cordell Hull 
(480,859,171 kw-hr), and Old Hickory (603,448,570 
kw-hr) was made available for distribution. Activities 
under reservoir management program comprising 
malaria control, shoreline sanitation, land management 
and disposal, and maintenance of public-use facilities 
continued. 
2. TENNESSEE RIVER, TN, AL AND KY 
Location. Formed by junction of French Broad and 
Holston Rivers in eastern Tennessee, 4.4 miles above 
Gay Street Bridge at Knoxville, flows southwest into 
northern Alabama, thence in a generally westerly 
course across north Alabama, to northeast boundary 
of Mississippi, thence nearly due north across Tennessee 
and Kentucky, entering Ohio River at Paducah, 
652.1 miles from junction of French Broad and Holston 
Rivers. (See Geological survey base map of Tennessee 
River Basin.) 
Previous projects. For details see pages 1902-1906, 
Annual Report for 1915; pages 1190-1194, 1196-1216, 
and 1220-1222, Annual Report for 1929; and page 
1216, Annual Report for 1938. 
Existing project. Originally provided for permanent 
improvement of river for a navigable depth of 9 feet 
at low water from mouth about 650 miles to Knoxville, 
Tenn. Only work performed by the Corps was construction 
of lock at General Joe Wheeler Dam and 
miscellaneous appurtenant improvements at a new 
work cost of $2,244,236. Tennessee Valley Authority 
program provided for obtaining authorized 9-foot 
project by construction of high dams and locks and 
utilization of certain locks and dams previously constructed 
under jurisdiction of the Corps. (See Table 
15-B for Authorizing Legislation.) Subsequent construction 
by that agency of Melton Hill Dam extends 
navigable channel of Tennessee River system up the 
Clinch River about 38 miles above damsite (mile 23.1) 
to vicinity of Clinton, Tenn. (See table 15-I on Tennessee 
River.) 
In accordance with general navigation laws placing 
control and supervision over navigable waters under 
direction of Secretary of the Army, the Corps of 
Engineers operates and maintains all locks, and maintains 
navigation channels and safety harbors by performing 
all necessary maintenance dredging and 
snagging operations. For information concerning 
other functions of the Corps under division of responsibilities 
for Tennessee River since adoption of Tennessee 
Valley Authority Act of 1933, see page 1084 of 
Annual Report for 1962. 
Local cooperation. Authorization requires no local 
cooperation in construction of alternate system of low 
dams. It does, however, provide that if high dams are 
built before the United States builds projected locks 
and low dams which are to be replaced, the United 
States shall contribute to cost of substituted structures 
an amount equal to estimated cost of works of 
navigation for which substitution is made. 
Terminal facilities. There are 150 terminals on the 
Tennessee River (10 municipally owned, 16 government 
owned facilities and 124 privately owned facilities). 
A total of 81 terminals have railroad connections. 
Principal commodities handled are petroleum products, 
stone, sand, gravel, coal, coke, grain, chemicals, 
iron, and steel. Facilities considered adequate for 
existing commerce. A list of terminals is revised annually 
and can be obtained from Division Engineer, 
Ohio River Division, Corps of Engineers, Cincinnati, 
Ohio. For further information see page 698 of Annual 
Report for 1969. 
Operations during fiscal year. Channel work by government 
plant and hired labor consisted of dredging 
and snagging at various locations, and maintenance 
of mooring facilities and safety harbors. Cost of channel 
maintenance was $536,777. Maintenance: All locks 
were operated and lock appurtenances and standby 
plant maintained as required. Major repairs continued 
at Wilson Auxiliary Lock including structural repairs 
to middle and lower gates, excavating and shotcreting 
the bluff above the lower guide wall and widening 
lower guide wall. Work was begun to renovate the 
lock operation building and paint the main lock. 
15-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
The Guntersville Main Lock was unwatered and 
repaired and new quoin and miter block were purchased, 
gear speed reducers were overhauled and lock 
gate stops repaired. Lock lighting revisions were completed 
at Watts Bar and Fort Loudoun. Fort Loudoun 
was unwatered and repaired, and new miter blocks 
and quoin purchased. Culvert valves were repaired 
and painted at Watts Bar. At Kentucky Lock contracts 
were awarded to replace handrails and machinery 
gear reducers. Floating boom was repaired at Pickwick, 
and lock gate stops repaired at Nickajack. 
3. TENNESSEE-TOMBIGBEE 
WATERWAY, AL AND MS 
Location. West Central Alabama and Northeastern 
Mississippi; in Marengo, Sumter, Greene and Pickens 
Counties, Alabama, and Noxubee, Lowndes, Clay, 
Monroe, Itawamba, Prentiss and Tishomingo Counties, 
Mississippi. 
Existing project. Provides for a waterway 234 miles 
in length, connecting the Tombigbee and Tennessee 
Rivers by way of the East Fork of Tombigbee River, 
Mackeys and Yellow Creeks, affording a channel not 
less than 9 feet deep and 280 feet in bottom width, 
with 10 locks each having clear chamber dimensions 
of 110x600 feet. Construction of the divide section, 
including Bay Springs lock and dam, is assigned to 
the Nashville District; whereas, the prosecution of 
work on the river and canal sections is under the jurisdiction 
of the Mobile District. Only activities of the 
Nashville District are reported hereon. Estimated 
Federal cost of new work under jurisdiction of the 
Nashville District is $750,000,000. (See 15-B for authorizing 
legislation.) 
Local cooperation. Authorization requires local interests 
to construct, maintain and operate all highway 
bridges, construct and maintain all highway relocations 
or alterations, make and maintain alterations as 
required to sewer, water supply and drainage facilities, 
assume cost of operation and maintenance of 
utility crossings, provide and maintain as required 
suitable and adequate river and canal terminals in 
accordance with plans approved by the Secretary of 
the Army and the Chief of Engineers. 
Operations during fiscal year. At the Piney Grove 
Recreation Site, work to provide campsites and trails 
was completed, and a contract for a beach and picnic 
area continued. The project is 99% complete. Navigation 
features are 100% complete. 
4. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
During the period $22,864 was expended for a study 
of Centre South Riverport, Hamilton Co., TN., and 
$27,175 for study and planning for an access channel 
to Port of Florence, AL. Construction of a channel at 
Morgan County Port was begun with expenditures in 
FY 89 of $1,383,202 federal funds and $771,967 contributed 
funds. 
Alteration of Bridges 
5. AUTHORIZED ALTERATION OF 
BRIDGES 
Work on Woodland Street bridge, under Truman- 
Hobbs Act, was initiated in 1965 and completed in 
1966. Costs were $987,632. For details see page 922 of 
Annual Report for 1967. 
Flood Control 
6. BIG SOUTH FORK NATIONAL RIVER 
AND RECREATION AREA, KY AND TN 
Location. The proposed project is located in Northeastern 
Tennessee and Southeastern Kentucky along 
the Big South Fork River and its tributaries in Pickett, 
Scott, Fentress, and Morgan Counties, Tennessee, and 
McCreary County, Kentucky. 
Existing project. A National Recreation Area was 
established in accordance with the concept included 
in the interagency report prepared pursuant to section 
208 of Flood Control Act of 1968. Total acreage is not 
to exceed 125,000 acres. The act specifically establishes 
the National Area for the purpose of preserving 
and interpreting the scenic, biological, archaeological 
and historical resources of the river gorge area and 
developing the natural recreational potential of the 
area. The area is divided into two categories, gorge 
and adjacent areas, with no construction permitted 
except limited clearing for establishment of day-use 
facilities, historical sites, primitive campgrounds and 
access roads. Lodges and other facilities will be provided 
in the adjacent areas. The project was authorized 
by the Water Resources Development Act of 1974, 
1976 and Water Resources Development Act of 1986. 
(See table 15-B for authorizing legislation.) The 
present authorized cost (ceiling) for the project is 
$156,122,000. The National Park Service operates and 
maintains the useable units of the area upon completion 
of land acquisition and construction by The Corps 
of Engineers. The first construction contract was 
awarded in June 1981. The project is 68% complete. 
15-4

NASHVILLE, TN, DISTRICT 
Local cooperation. None required. 
Operations during fiscal year. Engineering and design 
continued. Acquired 713.24 acres fee. Stabilization 
of a slide on Blue Heron Road was completed. 
Swimming facilities were completed at the Bandy 
Creek campground and recreation area, and a service 
area and maintenance building for the National Park 
Service Maintenance Staff was completed. 
7. MARTINS FORK LAKE, KY 
Location. Dam located at mile 15.6 on Martins Fork 
of Clover Fork, Cumberland River, about 10 miles 
southeast of city of Harlan, with reservoir extending 
about 6 miles upstream within Harlan County, southeastern 
Kentucky. 
Existing project. Multiple-purpose improvement 
combining flood control with water quality control 
and recreation development adopted by 1965 Flood 
Control Act (H. Doc. 244, 89th Cong.), in general 
accordance with recommendations. Dam will be concrete 
type, about 504 feet long and rising 97 feet above 
streambed. Outlet works provide for release of water 
from reservoir at varying levels. Drainage area above 
damsite is 55.7 square miles. At full pool level, spillway 
crest at elevation 1341 above mean sea level, 
reservoir will cover 578 acres and contain 21,120 acrefeet 
of storage capacity. Provision is made for 17,450 
acre-feet of reservoir capacity between elevations 
1341 and 1300 for control of floods in winter and 
spring season, and 14,360 acre-feet (El. 1341-1310) 
during summer and fall, in conjunction with which 
storage of 3,090 acre-feet would be available on a 
seasonal basis to meet streamflow requirements for 
water quality control and fish life below the dam. A 
minimum permanent pool of 3,670 acre-feet, 274 acres 
in extent, will thus be provided during potential flood 
seasons; and during late spring and summer when 
flood storage can be reduced, the lake is to be operated 
generally at a higher level (El. 1310) to maintain a 
larger surface area of 340 acres for recreation and to 
provide the required seasonal storage for releases of 
water during critical low-flow periods. Project will 
prevent major portion of average annual flood losses 
at Harlan and result in significant stage reductions 
with related benefits along rural reaches and at other 
urban areas downstream. Actual cost of project including 
$95,000 code 710 funds is $20,479,91L First 
construction contract awarded in December 1972. 
Project completed for beneficial use in September 
1978. 
Local cooperation. Federal Water Project Recreation 
Act of 1965 (P.L. 89-72) applies in regard to 
non-Federal participation in recreation development, 
in addition to which local interests are to provide certain 
safeguards to ensure functioning of reservoir as 
intended. In May 1981 a final recreation cost-sharing 
contract with Harlan County was approved and certain 
recreation facilities have been jointly developed 
by the Corps and the County. These facilities, consisting 
of a swimming beach and a picnic area are 
now operated and maintained by Harlan County. 
Recreation investment to date (Corps and Local) is 
about $100,000. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures operated 
as required. 
8. MIDDLESBORO, CUMBERLAND 
RIVER BASIN, KY 
Location. At Middlesboro, Ky., on Yellow Creek, a 
tributary entering Cumberland River about 660 miles 
above its mouth. 
Existing project. A system of canals and levees 
around one side of town, arranged so as to divert most 
headwaters of Yellow Creek away from present channel 
through heart of city. Protection is thus afforded 
in large measure to life and property within business 
district and a large part of residential section. For 
project details, see page 1088 of Annual Report for 
1962. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Work 
on levees, canals, and appurtenances was accomplished 
by hired labor. 
9. TUG AND LEVISA FORKS OF THE 
BIG SANDY RIVER AND UPPER 
CUMBERLAND, WV, VA AND KY 
Location. The project is located in the State of 
West Virginia and the Commonwealths of Kentucky 
and Virginia. The Cumberland portion consists of 
the Upper Cumberland River Basin, above Cumberland 
Falls, Ky. The basin is approximately 100 miles 
in length, averaging 30 miles in width at the lower 
portion and 10 miles in width upstream at Harlan, 
Ky. The Big Sandy Basin is within the Huntington 
District and the Cumberland within the Nashville 
District. 
Existing project. Provides for flood control measures 
for communities in the Tug and Levisa Forks 
and Upper Cumberland River Basins. The Cumberland 
portion has been assigned to the Nashville District. 
Only activities of the Nashville District are 
15-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
reported hereon. Estimated Federal cost of new work 
under jurisdiction of the Nashville District is 
$261,000,000. The project was authorized by the 
Energy and Water Development Appropriation Act of 
1981, Section 202 of PL 96-367. 
Local cooperation. Authorizing legislation requires 
that non-federal interests shall hold and save the 
United States free from damages due to construction 
works and maintain and operate all such works after 
their completion in accordance with regulations by 
the Secretary of the Army. 
Operations during fiscal year. Engineering and design 
continued. Acquired 41.04 acres fee, and 7.00 
acres easement. Construction of the Floodwall/Highway 
contract at Pineville, and Phase II of the Wallsend 
Levee continued. Design continued on the Harlan 
structural project and the levee at Barbourville. A 
contract was awarded for diversion tunnels at Harlan. 
Nonstructural excavations continued at Harlan, Barbourville 
and Pineville, and the first floodproofing 
contract was completed at Pineville. 
10. OHIO RIVER BASIN 
(NASHVILLE DISTRICT) 
Location. A series of levees, floodwalls, channel 
improvements, and reservoirs in Ohio River Basin 
within Nashville District. 
Existing project. The general comprehensive plans 
approved for flood control and other purposes in Ohio 
River Basin is set forth in legislation listed in Table 
15-B. Individual projects, local protection projects 
and lakes, considered in comprehensive plan within 
Nashville District are listed in Table 15-K. 
11. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts, requires local interests furnish assurances they 
will maintain and operate certain local protection 
projects after completion in accordance with regulations 
prescribed by Secretary of the Army. District 
Engineers are responsible for administration of these 
regulations within their respective districts. Maintenance 
inspections were made during fiscal year of 
completed protective works in localities transferred to 
local interests for maintenance and operation. Local 
interests were advised, as necessary, of measures required 
to maintain projects in accordance with standards 
prescribed by regulations. Fiscal year cost was 
$17,236. Total cost to September 30, 1989 was $323,335. 
For project inspection data see table 15-M. 
12. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control and coastal emergencies (Public Law 
99, 84th Cong., and antecedent legislation). 
Actual Federal cost for the fiscal year was $208,404 
for disaster preparedness. 
Multiple-Purpose Projects, Including Power 
13. CENTER HILL LAKE, OHIO RIVER 
BASIN, TN 
Location. Dam is on Caney Fork River, 26.6 miles 
above its confluence with Cumberland River (mile 
309.2) at Carthage, Tenn. It is in DeKalb County, 
Tenn., about 55 miles east of Nashville, and 14 miles 
southeast of Carthage, Tenn. Reservoir extends about 
64 miles up main stream and about 10 miles up Falling 
Water River and lies within DeKalb, Putnam, 
White, and Warren Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and 
power production, with a permanent pool for public 
use and conservation purposes. In addition to main 
dam structure, provision was made for a rolled-earth 
dike to close a saddle in reservoir rim near damsite. 
For further details, see page 1099 of 1962 Annual Report. 
Actual cost of project including $8,940,642 code 
710 funds is $53,412,022. 
Local cooperation. None required on completed 
project. Recreation development subject to certain 
conditions of non-Federal cost-sharing under Federal 
Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structure and its 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy generated 
(159,154,300 kw-hr) was made available through 
Department of the Interior to Tennessee Valley Authority 
for distribution. Activities under reservoir 
management involved land management, public relations, 
and maintenance of public use facilities. 
14. DALE HOLLOW LAKE, OHIO RIVER 
BASIN, TN AND KY 
Location. Dam is on Obey River, 7.3 miles above its 
confluence with Cumberland River (mile 380.9) at 
Celina, Tenn. It is in Clay County, Tenn., and about 
15-6

NASHVILLE, TN, DISTRICT 
80 miles northeast of Nashville, Tenn., 28 miles north 
of Cookeville, Tenn., and 3 miles east of Celina, Tenn. 
Reservoir extends about 51 miles up main stream, 10 
miles up East Fork, and 6 miles up West Fork of Obey 
River, and lies within Cumberland and Clinton Counties, 
Ky., and Clay, Pickett, Overton, and Fentress 
Counties, Tenn. 
Existing project. A concrete gravity-type dam, hy-. 
droelectric powerplant, and reservoir for primary 
purposes of flood control and power production with 
a permanent pool for public use and conservation purposes. 
See page 1096 of 1962 Annual Report for 
project details. Cost of project including $2,195,600 
code 710 funds and $150,000 non-Federal funds for 
recreation facilities under the completed projects program 
is $28,317,746. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy generated 
(156,755,670 kw-hr) was made available through 
Department of the Interior to Tennessee Valley Authority 
for distribution. Activities under reservoir 
management program involved public relations, land 
management, and maintenance of public-use facilities. 
Major accomplishment was the replacement of two 
generator ACB's. 
15. J. PERCY PRIEST DAM AND 
RESERVOIR, OHIO RIVER BASIN, TN 
Location. Damsite is on Stones River, 6.8 miles 
above its confluence with Cumberland River (mile 
205.9); in Davidson County, Tenn.; and about 7 miles 
east of Nashville, Tenn. Reservoir extends southeasterly 
from dam about 32 miles along main stream, 10 
miles up East Fork, 6.5 miles up West Fork, and for 
shorter distances up other tributaries of Stones River; 
and lies within Davidson, Rutherford, and Wilson 
Counties, Tenn. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control, power 
production and recreation. For further details see 
page 703 of 1969 Annual Report. Cost of project including 
$3,260,400 under code 710 funds and $46,000 
non-Federal funds for recreation facilities under the 
completed projects program is $56,914,039. 
Local cooperation. Recreation development subject 
to certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Total net 
energy generated (127,221,600 kw-hr) was made available 
through Department of the Interior to Tennessee 
Valley Authority for distribution. Activities under 
reservoir management program involved public relations, 
fish and wildlife management, and maintenance 
of public-use facilities. Water quality mixing pumps 
were installed upstream of the generator to provide 
better water quality downstream. 
16. LAUREL RIVER LAKE, OHIO RIVER 
BASIN, KY 
Location. Damsite is at mile 2.3 on Laurel River, a 
tributary of Cumberland River, in southcentral Kentucky. 
The two streams meet about 9 miles below 
Cumberland Falls, a prominent physiographic feature 
at head of Lake Cumberland which is formed by Wolf 
Creek Dam. Reservoir extends 19.2 miles upstream to 
site of Corbin, Ky. water-supply dam and lies within 
Laurel and Whitley Counties. 
Existing project. Project approved in general accordance 
with recommendations of House Document 
413, 86th Congress, by 1960 Flood Control Act, as 
amended by Public Law 88-253, was designed for 
purposes of flood control, power, and recreation as an 
integral unit of a coordinated plan for development of 
water resources of Cumberland River Basin. With the 
view of a net gain in power potential on a system 
basis, the plan of improvement incorporated appropriate 
flood control storage in the proposed project 
and corresponding adjustment in operations of Wolf 
Creek Dam-Lake Cumberland for flood control and 
power, which in effect constituted a transfer of reservoir 
capacity without entailing a change in flood 
control benefits. Further detailed study giving full 
consideration to power capabilities and marketing arrangements 
indicated the advantage of maintaining 
present storage allocation at Wolf Creek and use of 
all available storage capacity of Laurel River Lake 
for power. The power plant is complete. Recreation 
was completed in FY 1986. Total cost is $56,741,232. 
Local cooperation. None required. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
15-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
appurtenances maintained as required. Total net 
energy generated (69,971,000 kw-hr) was made available 
through Department of the Interior for distribution. 
Installation of power plant remote control 
instruments was accomplished in FY 89. 
17. WOLF CREEK DAM-LAKE 
CUMBERLAND, OHIO RIVER 
BASIN, KY 
Location. Wolf Creek Dam is on Cumberland River 
at mile 460.9 (above mouth) in Russell County, Ky., 
about 10 miles southwest of Jamestown and 12 miles 
north of Albany, Ky. Lake Cumberland extends 101 
miles up main stream, 48 miles up South Fork of 
Cumberland River, in Russell, Clinton, Wayne, 
Pulaski, McCreary, Laurel, and Whitley Counties, Ky. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and 
power production, with a permanent pool for publicuse 
and conservation purposes. See page 1094 of 1962 
Annual Report for project details. Cost of project is 
$188,267,195. This cost includes $3,259,872 code 710 
funds, $880,000 non-Federal funds for recreation facilities 
under the completed program, and $104,999,237 
for major rehabilitation. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: Activity 
involving the integrity of the structure began in 1968 
when a leak or seepage developed in the embankment. 
The major rehab embankment contract was physically 
completed in September 1982. Maintenance: Dam 
was operated and structures and appurtenances maintained 
as required. Operation of powerplant was continuous 
except for normal interruptions and necessary 
shutdowns for inspection and maintenance purposes. 
Major maintenance work items included installing 
revenue meters, instrumentation automation, supplying 
utility water to Dam site, and erosion control 
work at the Kendall site. Total net energy generated 
(1,226,510,000 kw-hr) was made available through 
Department of the Interior for distribution. Activities 
under reservoir management program involved land 
management activities, public relations, and maintenance 
of public-use facilities. 
General Investigations 
18. SURVEYS 
Costs for this period were $1,422,199 for which 
$1,029,240 was for navigation, $270,167 for flood 
damage prevention studies, $70,054 for special investigations, 
$32,738 for coordination studies with 
other agencies, and $20,000 for interagency water 
resource development. 
19. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for this period were $54,201 for technical 
services to others, and $44,237 for flood plain management 
services, totalling $98,438. 
15-8

NASHVILLE, TN, DISTRICT 
TABLE 15-A 
See 
Section 
in Text Project 
1. Cumberland River, 
TN and KY 
2. Tennessee River, 
TN, AL and KY 
3. Tenn.-Tombigbee 
Waterway, AL and MS 
5. Big South Fork National 
River and Rec. Area, 
KY and TN 
6. Martins Fork Lake, KY 
7. Middlesboro, Cumberland 
River Basin, KY 
8. Tug & Levisa Forks of the 
Big Sandy & Cumberland 
River, WV, VA and KY 
11. Cumberland, KY 
12. Center Hill Lake, 
Ohio River Basin, TN 
13. Dale Hollow Lake 
Ohio River Basin, 
TN and KY 
14. J. Percy Priest Dam and 
Reservoir, Ohio River 
Basin, TN 
15. Laurel River Lake, 
Ohio River Basin, KY 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total to 
FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
538 
18,496,000 
18,461,695 
16,900,000 
16,908,385 
- 
11,405,000 
6,844,558 
10,231,765 
10,105,683 
- 6,765 
- 6,765 
480,000 
507,448 
27,000 
28,020 
11,840,000 
12,317,354 
2,820,000 
2,853,975 
- 
3,007,000 
3,101,316 
2,353,000 
2,497,915 
58,000 
141,682 
886,000 
883,590 
75,587 
16,388,500 
16,532,247 
13,763,000 
13,527,412 
1,435,000 
2,954,077 
8,648,000 
5,883,134 
676,000 
658,851 
64,000 
63,990 
23,263,000 
17,204,246 
3,341,000 
3,277,917 
3,108,000 
3,087,685 
2,740,000 
2,646,484 
850,000 
817,325 
20,608,000 
20,422,397 
17,122,000 
16,991,895 
3,000,000 
3,600,796 
3,916,000 
6,273,184 
616,000 
613,142 
57,000 
57,141 
16,685,000 
16,207,412 
3,818,000 
3,758,934 
3,380,000 
3,375,737 
2,949,000 
2,907,243 
1,005,000 
1,036,364 
23,167,200 
23,648,733 
17,036,700 
17,383,402 
300,000 
2,030,026 
7,969,000 
6,158,684 
598,500 
619,139 
66,000 
61,772 
12,312,000 
17,561,180 
3,615,200 
3,750,028 
3,850,100 
8,418,865 
3,324,800 
3,341,459 
1,406,100 
1,422,959 
320,252,240 1.2s, 
320,252,240 1,2,8 
240,649,376 4 
240,104,677 s 
16,251,428 6 
16,251,428 6 
166,309,651 ' 
165,935,917 8 
400,000 
400,000 
740,895,050 
738,887,431 
111,823,920 9 
108,661,209 o10 
20,479,911 
20,479,911 
5,120,500 
5,106,211 
817,830 11 
817,830 11 
1,909,844 
1,898,376 
94,754,000 12 
92,075,750 1o 
66,642 
66,642 
53,412,022 1# 
53,412,022 .1 
50,792,167 16 
50,722,787 17 
28,317,746 18 
28,317,746 19 
48,869,907 2so 
48,768,128 21 
56,914,039 22 
56,914,089 '3 
34,129,386 24 
33,915,118 5 
56,741,282 
56,741,282 
9,804,100 26 
9,279,900 6 
15-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
TABLE 15.A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
16. Wolf Creek Dam and New Work 
Lake Cumberland, Approp. - - - - 83,267,958 s7 
Ohio River Basin, KY Cost 9,190 - - - 83,267,958 27 
Maint. 
Approp. 4,847,000 5,361,000 4,434,000 5,085,400 70,226,841 28 
Cost 5,055,966 5,272,882 4,460,508 5,271,224 70,158,209 29 
Rehab. 
Approp. - - - - 104,999,237 so 
Cost - - - - 104,999,237 so 
1. Includes $9,707,354 for abandoned and/or replaced works 
under the old Cumberland River system. (Amount includes 
$826,253 for new work and $3,266,706 for maintenance on previous 
projects.) 
2. Includes $61,733 public works acceleration funds, and 
$102,966 contributed by the State of Kentucky and $6,750 contributed 
by Metropolitan Nashville, TN. 
3. Includes $298,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
4. Includes $955,889 for special recreation use fees, and 
$1,938,157 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Act (PL 
98-8) of 1983. 
5. Includes $955,889 for special recreation use fees and 
$1,938,157 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Act (PL 
98-8) of 1983. 
6. Includes $14,007,193 for new work and $4,005,175 for 
maintenance on previous projects. 
7. Includes $495,763 for maintenance and operation of dams 
and other improvements of navigable waters, and $764,000 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
8. Includes $495,763 for maintenance and operation of dams 
and other improvements of navigable waters, and $764,000 
funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
9. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
10. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
11. Includes $33,876 Emergency Relief Funds. 
12. Includes $12,312,000 contributed by the State of Kentucky. 
13. Includes $17,561,130 contributed by the State of Kentucky. 
14. Includes $35,896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
15. Includes $35,896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
16. Includes $292,280 funds for special recreation use fees, 
and $393,578 for maintenance and operation of dams and other 
improvements of navigable waters, and $91,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
17. Includes $292,280 funds for special recreation use fees, 
and $393,578 for maintenance and operation of dams and other 
improvements of navigable waters, and $91,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
18. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
19. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
20. Includes $339,480 funds for special recreation use fees, 
and $393,578 for maintenance and operation of dams and other 
improvements of navigable waters, and $482,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
21. Includes $339,480 funds for special recreation use fees, 
and $393,578 for maintenance and operation of dams and other 
improvements of navigable waters, and $482,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
22. Includes $46,000 contributed by the Metropolitan Government, 
Nashville, TN. 
23. Includes $46,000 contributed by the Metropolitan Government, 
Nashville, TN. 
24. Includes $260,680 for special recreation use fees, and 
$337,078 for maintenance and operations of dams and other 
improvements of navigable waters, and $40,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
25. Includes $260,680 for special recreation use fees, and 
$337,078 for maintenance and operations of dams and other 
improvements of navigable waters, and $40,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
26. Includes $66,678 for maintenance and operations of 
dams and other improvements of navigable waters. 
27. Includes $96,920 public works acceleration funds, and 
$880,000 contributed by the State of Kentucky. 
28. Includes $82,048 public works acceleration funds, and 
$198,578 for maintenance and operation of dams and other improvements 
of navigable waters, and $278,780 funds for special 
recreation use fees, and $293,000 funds provided from the 
Productive Employment Appropriation Act (PL 98-8) of 1983. 
29. Includes $82,048 public works acceleration funds, and 
$198,578 for maintenance and operation of dams and other improvements 
of navigable waters, and $278,780 funds for special 
recreation use fees, and $293,000 funds provided from the 
Productive Employment Appropriation Act (PL 98-8) of 1983. 
30. Includes $203,757 for claim paid on initial construction 
of switchyard. 
15-10

NASHVILLE, TN, DISTRICT 
TABLE 15-B 
See Section 
in Text A 
AUTHORIZING LEGISLATION 
Date of 
uthorized Act Project and Work Authorized 
1. 
Jul 13, 1892 
Jun 25, 1910 
Aug 30, 1935 
Jul 24, 1946 
Jun 19, 1952 
Sep 3, 1954 
Jul 14, 1960 
Aug 5, 1886 
Mar 2, 1907 
Mar 2, 1919 
Jun 5, 1920 
Jul 3, 1930 
Jun 26, 1934 2 
Jul 24, 1946 
Oct 1, 1980 
2. 
Jul 3, 1930 
May 18, 1933 
CUMBERLAND RIVER BELOW NASHVILLE 
Provision made for lock A 
Provision made for locks B to F, and for dredging below 
lock F. 
Repairing dams A to F, inclusive, and surmounting same 
with movable crests. 
Provision of 9-foot channel by the construction of 3 
moderate height dams below Nashville; via, Kuttawa 
(Eureka), Dover, and Cheatham. 
Provision for hydroelectric power production as a function 
of Cheatham Dam. 
Construction of Barkley (Lower Cumberland) dam and 
reservoir project for navigation, flood control, hydroelectric 
power, and related purposes in lieu of Kuttawa 
and Dover navigation-only structures. 
Authorized change in alignment of Illinois Central Railroad. 
CUMBERLAND RIVER ABOVE NASHVILLE 
Provision made for locks and dams; the Secretary of War 
to determine the final plan of improvement. 
Dimensions of the locks fixed in accordance with reports 
of Mar. 30, 1&87, and Nov. 25, 1890. 
Adoption of the report of the Board of Engineers, dated 
Feb. 26, 1906, limiting the lock and dam construction to 
locks and dams 1 to 7, and 21. 
Provision made for locks and dams 8 to 17. 
Authorizes work to proceed in Tennessee without waiting 
for action of local interests in Kentucky. 
Raising dam 1, 3 feet. 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers 
and harbors. 
Construction of Old Hickory, Cordell Hull (Carthage), and 
Celina Dams above Nashville for navigation and the 
development of power resources. 
Design and construct flood control measures for communities 
in the Upper Cumberland River basins. 
TENNESSEE RIVER 
Authorized navigable depth of 9 feet from mouth about 
650 miles to Knoxville, Tennessee to be obtained by 
construction of low dams. 
Authorized TVA to construct such dams in the Tennessee 
River as will provide a 9 foot channel. 
Annual Report, 1890, p. 
2151 
H. Does. 758, 60th Cong., 
1st sess.; and 1481, 60th 
Cong., 2d seas. 1 
H. Doc. 38, 73d Cong., 1st 
sess. 
H. Doc. 761, 79th Cong., 
2d sess. 
S. Doc. 81, 83d Cong., 2d 
sess. 
H. Doc. 56, 86th Cong., 2d 
sess. 
Annual Report 1884, p. 
1663. 
Annual Report 1888, p. 
1622, and Annual Report 
1892, p. 1933. 
H. Doc. 699, 59th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 10, 63d 
Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 26, 70th 
Cong., 2d sess. 
H. Doc. 761, 79th Cong., 
2d sess. 
Sec. 202, PL 96-367 
H. Doc. 328, 71st Cong., 
2d sess. 
15-11 
Documents

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
TABLE 15-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Section Date of 
in Text Authorized Act Project and Work Authorized Documents 
9. OHIO RIVER BASIN, NASHVILLE DISTRICT 
Aug 28, 1937 
Jun 28, 1938 
Aug 18, 1941 
Dec 22, 1944 
Jul 24, 1946 
May 17, 1950 
Dec 30, 1963 
Jun 18, 1965 
Aug 13, 1968 
Jun 19, 1970 
Mar 7, 1974 Authorized establishing Big South Fork National River and 
Recreation Area, KY and TN. Total area not to exceed 
125,000 acres. 
Mar 7, 1974 Additional $120 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
TENNESSEE-TOMBIGBEE WATERWAY 
Jul 24, 1946 Construction of waterway to connect above rivers and 
provide a 9 foot channel and minimum bottom width 
of 170 feet in river and canal sections and 150 feet in 
the divide cut, with locks 110 by 600 feet clear inside 
dimensions. 
Subsequent studies determined most practical plan consists 
of channel with bottom width of 300 feet (280 feet in 
divide cut), fewer locks with higher lifts resulted in 
reducing number of lifts from 18 to 10 and reduced 
length from 260 to 253 miles. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st 
sess. 
Construct levees, floodwalls, and drainage structures for 
protection of cities and towns in Ohio River Basin. 
Project to be selected by Chief of Engineers with 
approval of Secretary of War at a cost not to exceed 
$24,877,000 for construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable 
at discretion of Secretary of War and Chief of Engineers, 
and for initiation and partial accomplishment of plan, 
authorized $75 million for reservoirs and $50,300, for 
local flood protection works. 
Additional $45 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $70 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $125 million for further prosecution of 
comprehensive plan. 
Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $150 million for further prosecution of 
comprehensive plan for flood control and other purposes 
in Ohio River Basin. 
Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $69 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
H. Doc. 6755, 89th Cong., 
1st sess. 
S. 3710, 90th Cong., 2d 
sess. 
H. R. 15166 91st Cong., 
2d sess. 
H. R. 10203 93rd Cong. 
Water Resources Develop. 
Act of 1974 Amended by 
PL 94-587, 94th Cong. 
H. R. 10203 93rd Cong. 
River Basin Monetary 
Authorization Act of 
1974. 
H. Doc. 486, 79th Cong., 
2d sess. 
Page 1343, Part I, FY 
1968 House Hearings. 
1. Contains latest published maps. Included in Public 
Works Administration program Sept. 6, 1933. 
2. Permanent Appropriation Repeal Act. 
15-12 
H. Doc. 762, 77th Cong., 
2d sess. 
H. Doc. 506, 78th Cong., 
1st sess.

NASHVILLE, TN, DISTRICT 
TABLE 15-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(All Projects not Specifically Identified in Text) 
For last Full Cost to Sep 30, 1989 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Caney Fork River, TN abandoned 1895 $ 27,828 - 
Clinch River, TN and VA abandoned 1923 53,949 $ 7,873 
Duck River, TN abandoned 1887 13,000 - 
Elk River, AL and TN abandoned 1904 4,000 
French Broad and Little Pigeon Rivers, TN abandoned 1931 249,605 33,554 
Holston River, TN abandoned 1911 5,714 - 
Little Tennessee River, TN abandoned 1888 5,510 - 
Obey River, TN abandoned 1887 11,500 - 
Red River, TN abandoned 1884 5,000 - 
South Fork of Cumberland River, KY abandoned 1892 11,967 - 
TABLE 15-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects not Specifically Identified in Text) 
For last Full Cost to Sep 30, 1989 
Project Report see Operation and Status Annual Report Construction Maintenance 
Barbourville, KY completed 1963 $2,088,147 
Coal Creek and Tributaries (Lake City), TN completed 1962 460,134 - 
Corbin (Lynn Camp Creek), KY completed 1969 567,703 - 
Middlesboro (Yellow Creek), KY completed 1949 26,309 - 
Paint Rock River, AL completed 1967 544,178 - 
Pineville, KY completed 1963 1,679,126 - 1 
1. Includes $9,950 contributed funds. 
15-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS 
TABLE 15-F INCLUDING POWER 
Project Status 
Barkley Dam and Lake Barkley, KY and TN beneficial use 
Celina Dam, KY active 
Cheatham Lock and Dam, TN beneficial use 
Cordell Hull Lock and Dam, TN beneficial use 
Old Hickory Lock and Dam, TN beneficial use 
1. Details given under "Cumberland River, TN and KY." See Table 15-H. 
TABLE 15-G 
Project 
Three Islands Reservoir, Ohio 
River Basin, TN 
Middlesboro, Yellow Creek 
Bell County, KY 
Cumberland River above 
Nashville, TN 
For last Full 
Report see 
Annual Report 
-... 
DEAUTHORIZED PROJECTS 
For last Full 
Report see 
Annual Report for 
1970 
Hiwassee River, Polk and 
Bradley Counties, TN 
1923 
Rossview Lake, Tennessee 
and Kentucky 
Date and Authority 
Authorized: FC Act 1938, PL 761, 75 
Cong., 3rd sess.; FC Act 1946, PL 525, 
79th Cong., 2d sess. 
Deauthorized: 5 Aug 1977. 
Authorized: FC Act, Dec 22, 1944, 
PL 534, 78th Congress. 
Deauthorized: 17 Oct 1986. 
Water Resources Development Act of 
1986, PL 99-662, 99th Cong., 2d sess. 
Authorized: River & Harbor Act, 
Aug 5, 1886. 
Deauthorized: 17 Oct 1986. 
Water Resources Development Act of 
1986, PL 99-662, 99th Cong., 2d sess. 
Authorized: River & Harbor Act, 
Aug 14, 1876. 
Deauthorized: 17 Oct 1986. 
Water Resources Development Act of 
1986, PL 99-662, 99th Cong., 2d sess. 
Authorized: FC Act, Jun 28, 1938, 
PL 761, 75th Congress. 
Deauthorized: 17 Oct 1986. 
Water Resources Development Act of 
1986, PL 99-662, 99th Cong., 2d sess. 
Cost to Sep 30, 1989 
Operation and 
Construction Maintenancee 
$146,498,644 $77,576,8841 
222,575 -_ 1 
31,682,762 57,050,1211 
79,874,492 37,705,8671 
52,266,412 67,771,8551 
Federal Contributed 
Funds Funds 
Expended Expended 
$111,855 - 
123,065 - 
6,779 - 
15-14 
, . 
._...__

NASHVILLE, TN, DISTRICT 
TABLE 15-H CUMBERLAND RIVER, TN AND KY: PRINCIPLE FEATURES 
(See Section 1 of Text) 
Dam and Reservoir Barkley Cheatham Old Hickory Cordell Hull Celina 
Nearest town 
Miles above mouth of river 
Lock dimensions (feet)1 
Lift at normal pool levels (feet) 
Depths on guardsills at 
minimum pool levels (feet) 
Character of foundation 
Dam: 
Type 
Height 
Length, exclusive of lock section 
(feet) 
Spillway: 
Gross length (feet) 
Net length opening (feet) 
Crest gates: 
Type 
Number 
Size (feet) 
Operating levels at dam 
(feet, mean sea level) : 
Maximum regulated 
Normal operation: 
Full pool 
Minimum pool 
Minimum pool in advance of floods 
Reservoir area (acres) 
Reservoir capacity (acre-feet): 
Flood control 
Power drawdown 
Dead storage 
Total 
Canal: 
Length (miles) 
Bottom width (feet) 
Depth at minimum pool level (feet) 
Power development: 
Number of units 
Generator rating (kilowatts) 
Total installation (kilowatts) 
Kuttawa, KY, 
11 miles. 
30.6 
110 by 800 
57 
11, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
157 
9,959 
804 
660 
Tainter 
12 
55 by 50 
Ashland City, 
TN, 9 miles. 
148.7 
110 by 800 
26 
14, upper; 
17, lower 
Rock 
Concrete 
gravity 
75 
800 
480 
420 
Tainter 
7
60 by 27 
375 
359 
354 
346 
93,430 
1,213,000 8,4 
259,000 
610,000 
2,082,000 
385 
382 
7,450 
19,800 7 
84,200 
104,000 
Old Hickory, 
TN, 3 miles. 
216.2 
84 by 400 
60 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
98 
3,605 2 
325 
270 
Tainter 
6
45 by 41 
450 
442 
27,450 
125,000 5 
63,000 
357,000 
545,000 
Carthage, TN, 
5 miles. 
313.5 
84 by 400 
59 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
93 
1,138 2 
291 
225 
Tainter 
5
45 by 41 
508 8 
508 
501 
499 
13,920 
85,600 s,6 
20,500 
204,800 
310,900 
1.75 
400 
11 
4
32,500 
130,000 
3
12,000 
36,000 
4
25,000 
100,000 
3
33,333 
100,000 
15-15 
Celina, TN, 
5 miles. 
385.4 
Rock 
Concrete 
gravity and 
earthfill 
86 
2,298 
290 
250 
Tainter 
5
50 by 37 
564 8 
560 
559 
559 
16,960 
55,950 5 
14,700 
287,300 
357,950 
3
36,000 
~" 108,000 " -. ,,,_,_

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
TABLE 15-H 
(Continued) 
CUMBERLAND RIVER, 
(See 
TN AND KY: PRINCIPLE 
Section 1 of Text) 
Dam and Reservoir Barkley Celina Cheatham Cordell Hull Old Hickory 
Percent of project completion s - 8 8 8 
Year opened to navigation 1964 - 1952 1973 1954 
Cost 9 $146,500,000 $213,000,000 $31,700,000 $79,874,500 $52,266,400 
1. Clear width and length available for full width. 
2. Exclusive of lock section. 
3. Surcharge. 
4. Normal operation (elev. 375-359) during nonflood season; 
flood control allowance to be increased to 1,472,000 acrefeet 
(elev. 375-354) during season of major floodflows. 
5. Surcharge storage. 
6. During flood season (elev. 508-501); minimum 51,800 
acre-feet (elev. 508-504) with normal operation during nonflood 
season. 
7. Daily pondage allowance; run-of-river project. 
8. Completed for full beneficial use. 
9. Includes recreation facility costs. 
15-16 
FEATURES

TABLE 15-I TENNESSEE RIVER 
(See Section 2 of Text) 
Project 1 
Kentucky 
Pickwick Landing: 
Auxiliary lock 
Main lock 
Wilson: 
Auxiliary lock 
Main lock 
General Joe Wheeler: 
Auxiliary lock 
Main lock 
Guntersville: 
Auxiliary lock 
Main lock 
Nickajack: 
Auxiliary lock 
Main lock 
Chickamauga 
Watts Bar 
Fort Loudon 
Melton Hill 
(Clinch R.) 
.t 
I-s 
C71 
1' 
Lock Dimensions 
Length Minimum Depth 
Width Avail- Lift on Guard Sills 
of able for 
Cham- Full Nor- Maxiher 
Width mal mum Lower Upper 
(feet) (feet) (feet) (feet) (feet) (feet) o 
110 600 56 73.3 12.7 11.0 
Miles 
Above Miles from 
Mouth Nearest Town 
22.4 0.5 above Gilbertsville, 
KY 
206.7 4.4 above Hamburg, 
TN 
206.7 4.4 above Hamburg 
TN 
259.4 2.9 above Florence, 
AL 
259.4 2.9 above Florence, 
AL 
274.9 18.4 above Florence 
AL 
274.9 18.4 above Florence, 
AL 
349.0 9.1 below Guntersville, 
AL 
349.0 9.1 below Guntersville, 
AL 
424.7 39.4 below Chattanooga, 
TN 
424.7 39.4 below Chattanooga, 
TN 
471.0 6.9 above Chattanooga, 
TN 
529.9 6.8 above Breedenton, 
TN 
602.3 1.3 above Lenoir City, 
TN 
23.1 22.1 above Kingston, 
TN 
110 
110 
60 
60 
60 
75 
600 
800 
360 
360 
360 
400 
39 41.0 
39 41.0 
49 53.0 
58 70.0 
72 80.0 
54 60.0 
O 
Character 
f Foundation 
Limestone 
12.8 10.0 Limestone 
12.8 10.0 Limestone 
11.0 4 11.2 Limestone 
13.0 13.0 Limestone 
13.2 14.7 Limestone 
13.0 13.0 Limestone 
11.8 13.0 Limestone 
12.7 18.0 Limestone 
13.0 13.0 Limestone 
13.0 13.0 Limestone 
13.0 10.0 Limestone 
11.8 12.0 Shale 
11.8 12.0 Limestone 
13.0 13.0 Limestone 
Year 
)pened 
Navi- Kind Type of 
gation of Dam Construction 
1942 Fixed Concrete and 
earthfill 
1937 Fixed Concrete and 
earthfil 
1984 Fixed Concrete and 
earthfll 
1927 Fixed Concrete and 
earthfill 
1959 - - 
110 600 55 63.0 
110 1000 55 63.0 
60 292 94 100.0 
300 
110 600 94 100.0 
60 400 48 51.5 
110 600 48 51.5 
60 360 39 45.0 
110 600 39 45.0 
Concrete and 
earthfill 
Concrete and 
earthfill 
Concrete and 
earthfill 
Concrete 
Concrete 
Concrete and 
earthfill 
Concrete and 
earthfill 
Concrete 
Cost of 
Each Lock 
and Dam 
a
3 
$46,973,540 s 
7 
1,796,2956 m 
3&7 
7 y 
7 n 
3 &7 
3 
1. H. Doc. 328, 71st Cong., 2d sess., contains table, pp. 98 
and 99, giving pertinent information concerning low dams contemplated 
under 1930 project. Annual Report for 1938, pp. 1218 
and 1219, contains similar information pertaining to low dams 
in addition to existing locks and dams, including those constructed 
or under construction by Tennessee Valley Authority. 
2. Lock and dam constructed by Tennessee Valley Authority. 
3. Lock and dam constructed by Tennessee Valley Authority. 
Design for lock prepared with Corps forces and funds. 
4. Tailwater in canal; flight of 2 locks. 
5. Constructed by the Corps under authority of sec. 124, 
National Defense Act of June 3, 1916 (H. Doc. 1262, 64th 
Cong., 1st sess.). Actual cost of lock and dam. 
6. Actual cost of lock only as constructed by the Corps; 
dams constructed by Tennessee Valley Authority. 
7. Constructed by Tennessee Valley Authority. 
1934 Fixed 
1963 Fixed 
1937 Fixed 
1965 Fixed 
1967 Fixed 
Fixed 
1939 Fixed 
1941 Fixed 
1943 Fixed 
1963 Fixed

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1989 
TABLE 15-J TENNESSEE RIVER, TN, AL, AND KY 
TOTAL COST OF EXISTING PROJECTS TO 
(See Section 2 of Text) 
SEP 30, 1988 
Channel Operation & 
Funds New Work Maintenance Maintenance Total 
Regular $2,244,236 $8,963,124 $152,955,948 $164,163,308 1.2 
Maintenance - - 11,665 11,665 
Increase of compensation, - 5 - 5 
rivers and harbors, 1919 
(certified claims) 
Total $2,244,236 $8,963,129 $152,967,613 $164,174,9781,2s 
1. In addition, surplus property value at $54,336 was tion and care of works of improvement under provisions of 
transferred from the project without reimbursement. Excludes appropriation for such purposes. 
$4,005,175 expended between 1890 and June 30, 1935, on opera- 2. Excludes $14,007,192 previous construction cost. 
TABLE 15-K OHIO RIVER BASIN (NASHVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS
Estimated Cost 
Type of 
Location Protection Federal Non-Federal Total 
Cumberland, KY Channel 520,000 240,000 760,0001 
Improvement 
1. Deferred. 
TABLE 15-L RESERVOIRS 
Total 
Federal 
Tributary Basin and Reservoir Stream Cost 
Center Hill Lake, TN Caney Fork River $58,412,022 1 
Dale Hollow Lake, TN and KY Obey River 28,167,7461 
J. Percy Priest Dam & Reservoir, TN Stones River 56,868,039 1,2 
Laurel River Lake, KY Laurel River 56,741,232 a 
Martins Fork Lake, KY Martins Fork 20,479,911 
1. Details of this project are in individual report. 
2. Formerly Stewarts Ferry Reservoir. 
3. See "Other authorized multiple-purpose projects." 
15-18

NASHVILLE, TN, DISTRICT 
TABLE 15-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 10 of Text) 
Project Date of Inspection 
Barbourville, KY 
Corbin, KY 
Lake City, TN 
Middlesboro, KY (Yellow Creek) 
Middlesboro, KY (Diversion Canal) 
Paint Rock River, AL 
Pineville, KY 
Spring City, TN 
Sunbright, TN (Whiteoak Creek) 
May 1989 
May 1989 
May 1989 and Sep 1989 
May 1989 and Sep 1989 
May 1989 and Sep 1989 
Oct. 1989 
May 1989 and Sep 1989 
May 1989 and Oct. 1989 
May 1989 and Sep 1989 
TABLE 15.N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205 
P.L. 858, 80th Congress, as amended 
Project FY 89 Cost 
Browns Creek, Nashville, TN 
Dry Creek, Goodlettsville, TN 
Lytle Creek, Murfreesboro, TN 
Little Limestone Creek, TN 
Whites & Ewing Creeks, TN 
Gibson Creek, TN 
Trace Creek, Waverly Park, TN 
Doe & Watanga River, Elizabethtown, TN 
Little Harpeth River, Brentwood, TN 
Beaver Dam Creek, Damascus, VA 
Brush Creek, Johnson City, TN 
Clinch River, Tazwell Co., VA 
Hickory Creek, Warren Co., TN 
$ 50,488 
247,274 
58,903 
21,152 
16,690 
16,720 
44,704 
57,579 
5,734 
2,651 
40,801 
5,101 
27,198 
Emergency Bank Protection (Section 14 of the 1946 
Flood Control Act, P.L. 526, 79th Congress) 
Project FY 89 Cost 
Lake Guntersville, AL $286,027 
Sheffield Water Intake, AL 24,167 
Duck River, Hickman Co., TN 183,340 
Pond Creek, Cheatham Co., TN 4,276 
15-19 
--

LOUISVILLE, KY. DISTRICT * 
This district comprises a portion of southwestern Ohio, 
west central Kentucky, a small portion of north central 
Tennessee, Indiana except northern part, and 
southeastern Illinois except Cairo-Mounds-Mound City 
area, all included in drainage basin of Ohio River and its 
tributaries (exclusive of Tennessee and Cumberland 
Rivers) from mile 438 (below Pittsburgh) immediately 
upstream from Foster, KY. to mouth. 
All cost and financial statements for projects are listed 
at the end of this chapter. All other tables are referenced 
in text and also appear at the end of this chapter. 
IMPROVEMENTS 
Navigation - Locks and Dams Page 
1. Construction of Locks and Dams, 
Ohio River.............................16-2 
2. Green and Barren Rivers, KY............. 16-2 
3. Kentucky River, KY..................... 16-2 
4. Open Channel Work, Ohio River........... 16-3 
5. Other Authorized Navigation 
Projects ............................... 16-3 
6. Navigation Work Under Special 
Authorization ......................... . 16-3 
Flood Control - Local Protection 
7. 
8. 
9. 
Evansville, IN .......................... 16-3 
Mill Creek, OH.........................16-3 
Southwestern Jefferson 
County, KY............................16-4 
Flood Control - Reservoirs 
10. Barren River Lake, KY...................16-4 
11. Brookville Lake, IN......................16-5 
12. Buckhorn Lake, KY.....................16-5 
13. Caesar Creek Lake, OH................... 16-5 
14. Cagles Mill Lake, IN.....................16-6 
15. Carr Fork Lake, KY....................16-6 
16. Cave Run Lake, KY...................... 16-6 
17. Cecil M. Harden Lake, IN.................16-6 
18. Clarence J. Brown Dam 
& Reservoir, OH......................... 16-7 
19. Green River Lake, KY.................... 16-7 
20. Huntington Lake, IN.....................16-7 
21. Mississinewa Lake, IN....................16-8 
22. Monroe Lake, IN........................16-8 
23. Nolin Lake, KY........................16-9 
24. Ohio River Basin 
(Louisville Dist.)......................... 16-9 
25. Patoka Lake, IN........................16-9 
26. Rough River Lake and Channel 
Improvement, KY.......................16-9 
27. Salamonie Lake, IN.................... 16-10 
28. Taylorsville Lake, KY...................16-10 
Page 
29. Wabash River Basin....................16-11 
30. West Fork of Mill Creek Lake, OH........16-11 
31. William H. Harsha Lake, OH.............16-11 
32. Inspection of Completed Flood 
Control Projects........................ 16-12 
33. Other Authorized Flood Control 
Projects ............................... 16-12 
34. Flood Control Works Under 
Special Authorization....................16-12 
General Investigations 
35. 
36. 
37. 
Surveys..............................16-12 
Collection and Study of Basic Data........ 16-12 
Preconstruction Engineering and 
Design ............................... 16-12 
Tables 
Table 16-A Cost and Financial 
Statement......................16-13 
Table 16-B Authorizing Legislation..........16-17 
Table 16-C Other Authorized Navigation 
Projects........................16-18 
Table 16-D Not Applicable 
Table 16-E Other Authorized Flood 
Control Projects................. 16-19 
Table 16-F Not Applicable 
Table 16-G Deauthorized Projects............ 16-21 
Table 16-H Principal Features of Green 
and Barren Rivers and Kentucky 
River Navigation Systems........16-23 
Table 16-I Ohio River Basin - Total 
Cost of Basin Plan............... 16-24 
Table 16-J Wabash River Basin - Total 
Cost of Basin Plan..............16-28 
Table 16-K Inspection of Completed 
Flood Control Projects...........16-29 
Table 16-L Flood Control Work Under 
Special Authorization............16-31 
16-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation - Locks and Dams 
1. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
For report on this improvement, see the heading under 
Ohio River. 
2. GREEN AND BARREN RIVERS, 
KY. 
Location. Green River rises in Casey County, KY, 
flows northwesterly 370 miles, and empties into Ohio 
River about 8 miles above Evansville, IN. Barren River 
rises in Monroe County, KY, flows northwesterly 130 
miles, and empties into Green River 1/2 mile above Lock 
4 and 149.5 miles above mouth of Green River. 
Existing project. Six locks and dams on Green River 
and one on Barren River to give, with channel work in 
pools of dams, a navigable depth of 9 feet and width of 
200 feet from Ohio River to mile 103 Green River, 3.2 
miles upstream from Paradise, KY; a navigable depth of 
5.5 feet from mile 103 Green River to Mammoth Cave, 
KY, mile 197.8 Green River, and from mouth of Barren 
River mile 149.5 Green River, to Bowling Green, KY, mile 
30.1, Barren River. 
Fluctuations in stage vary considerably at different 
locks. At Lock 3, Green River, ordinary high stages are 
from 12 to 15 feet above pool level, and at Lock 1, Barren 
River, from 7 to 10 feet above pool. Maximum stages of 
record are 34 feet above normal pool stage at Lock 3, 
Green River, and 29 feet at Lock 1, Barren River, obtained 
during floods of 1937 and 1913, respectively. (See Table 
16-B for authorizing legislation and Table 16-H for principal 
features of the locks and dams.) 
Local cooperation. Fully complied with. 
Terminal facilities. Coal handling facilities located 
on the Green River between miles 81.5 and 108.1 near 
South Carrollton, Rockport, Paradise and gochester, 
Kentucky, are considered adequate for existing 
commerce. 
Operations during fiscal year. Consisted of operation 
and maintenance of Locks and Dams 1 and 2, Green 
River, and removal of shoals, snags, and slides as required 
to maintain adequate channel for existing traffic between 
mouth of Green River and Dam 3 at mile 108.5 Green 
River. Maintenance: Contracts were awarded for cell 
removal on Green River and construction of access road 
and repair of concrete esplanade pavement at Lock and 
Dam 6. Routine maintenance was performed. 
Locks and Dams 1 and 2, Green River, are in good condition. 
Lock and Dam 3, Green River, and Lock and Dam 
1, Barren River are in fair condition, and Lock 4, Green 
River, is in poor condition. Dam 4, Green River, failed 
May 24, 1965, when 120 feet washed out. Breach later 
widened, and repairs were deferred pending completion 
of survey report for navigation on Green River. Pool of 
Dam 1, Barren River, is maintained for local small boat 
use, but navigation through lock is suspended because of 
loss of lower pool. Operation activity was discontinued at 
Lock 4 Green River and Lock and Dam 1 Barren River 
in January 1974 and at Lock 3, Green River in September 
1981. The residences and associated buildings and 
certain real estate at Lock 4 Green River and Lock and 
Dam 1 Barren River were disposed of in January 1975. 
Operation of Locks 5 and 6, Green River, was discontinued 
August 1951, as they were no longer used by river 
traffic. Controlling project depth in lower 103 miles of 
Green River is 9 feet; controlling depth from mile 103 to 
Bowling Green, KY, is 5.5 feet. Under permit issued by 
District Engineer on August 20, 1963, private interests 
dredged channel of Green River to extend 9-foot depth to 
coal loading teminal at mile 105.7. Channel of Green 
River above Lock 3 is no longer maintained. 
3. KENTUCKY RIVER, KY 
Location. Formed by confluence of its North and Middle 
Forks about 4 miles east of Beattyville in east central 
Kentucky, (South Fork joins the main stream at that 
location), flows northwesterly and empties into Ohio River 
at Carrollton, KY, mile 545.8 below Pittsburgh, PA. 
Existing project. Provides for 14 locks and fixed dams 
to give, in connection with improvement of Ohio River, 
slack water navigation of 6 feet minimum depth from 
Ohio River to places on the three forks that are short 
distances above Beattyville, KY. Length of 6-foot-depth 
project on main stem of Kentucky River is 258.6 miles 
to confluence of Middle and North Forks. Cost of completed 
new work is $4,176,749. River frequently rises to 
35 feet or higher. Extreme height at Lock 1 due to flood 
backwater from Ohio River is 60.3 feet, while extreme 
floods reach height of 47.6 feet at Lock 4, and 35.5 feet 
at Lock 14. At some intermediate locks extreme height 
of floods exceeds 40 feet. All flood heights refer to upper 
pool gages. Existing project was adopted by 1879 River 
and Harbor Act (H. Ex. Doc. 47, 45th Cong., 3d Sess., and 
Annual Report, 1879, p. 1398). Operation and care of locks 
and dams were included in project July 1, 1935, under 
provision of Permanent Appropriations Repeal Act of 
June 26, 1934. (See Table 16-H for principal features of 
the locks and dams.) 
On December 19, 1976 the lock operation schedules for 
commercial traffic and recreational craft on the Kentucky 
River System were reduced from continuous 24-hour yearround 
operation to two shift year-round operation of Locks 
1 through 4, intermittent daily operation of Locks 5 
through 10, and intermittent operation five days weekly 
of Locks 11 through 14. Since that time the hours for 
operation of Locks 5 through 14 have been reduced in 
several increments. On 1 October 1981 Locks 5 through 
14 were closed to traffic and placed in caretaker status. 
Locks 5, 6, 8, 9, and 10 were in operation for 15 weekends 
during fiscal year 1982 and was again closed at the end 
of this period. Locks 5 through 14 were leased to the State 
of Kentucky on 21 May 1985. The State of Kentucky 
operated these locks on weekends during the summer 
boating seasons through the Fiscal Year. The lease is due 
to expire on 15 October 1989 and Locks 5 through 14 will 
be closed to traffic and placed in caretaker status. During 
the fiscal year Locks 1 through 4 continued a two shift, 
16-2

LOUISVILLE, KY. DISTRICT 
year-round operation. 
Licenses. Federal Regulatory Commission License 
No. 539, to Kentucky Utilities Co., at Dam 7, Kentucky 
River, Annual charge, $4,400; total collections through 
September 30, 1989, $284,405. 
Terminal facilities. Facilities for bulk commodities 
and gasoline are considered adequate for existing traffic. 
Operations during fiscal year. Consisted of operation 
and maintenance of Locks and Dams 1 through 4 and 
removal of shoals, snags, and slides as required to maintain 
an adequate channel for existing traffic between 
mouth of river and Dam 5 at mile 82.2 Kentucky River. 
Maintenance: Contract was awarded for upper lock guide 
wall replacement and routine maintenance was 
performed. 
Existing project was completed in 1917. Work 
accomplished was rehabilitation of the five old State locks 
and dams and construction of new Locks and Dams 6 to 
14 inclusive. Repairs have been made to deteriorated 
locks and dams as required to keep locks in operation and 
maintain pool levels above dams except in extreme dry 
weather, when some pools fall below normal levels, details 
in Annual Reports for 1963, 1964 and 1965. Channel work 
was performed as required to provide for existing river 
traffic. Controlling navigable depth in length of river 
covered by existing project was 6 feet at end of fiscal year. 
4. OPEN CHANNEL WORK, 
OHIO RIVER 
For report on this improvement, see this heading under 
Ohio River. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 16-C. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
None. 
Flood Control - Local Protection 
7. EVANSVILLE, IN 
Location. In Vanderburgh County, IN, on right bank 
of Ohio River, 792.2 miles below Pittsburgh, PA. (See U.S. 
Geological Survey map of Evansville-South, IN.) 
Existing project. Construction of a system of levees 
and concrete floodwalls, together with pumping plants for 
disposal of interior drainage, at Evansville. For further 
details, see Annual Report for 1962, page 1127. Project 
will provide protection for City of Evansville, IN, against 
Ohio River floods equal to 1937 flood (maximum of record), 
with a 3-foot freeboard. Estimated total cost of new work 
(1989) is $51,100,000 Federal, and $5,500,000 non- 
Federal. Existing project selected for construction under 
general authorization for Ohio River Basin in 1937 Flood 
Control Act. Howell Section, Unit 2, was reclassified from 
the "active" category to the "inactive" category July 7, 
1977 based on current studies that indicated this part of 
the project is not economically justified. 
Local cooperation. Section 3 of Flood Control Act of 
June 22, 1936, as amended, applies. Fully complied with 
for Howell Unit 1 and Knight Township sections. 
Assurances for Pigeon Creek Section, Unit 1, were executed 
February 11, 1963. Authorizations-of-entry for 
Pigeon Creek Section, Unit 2, Parts 1 and 2 have been 
furnished. 
Operations during fiscal year. Engineering and 
design studies continued. Plans and specifications for US 
Highway 41W Pump Plant were completed and construction 
contract was awarded in September 1989. Contracts 
for Diamond Avenue, North 1st Avenue, and Stringtown 
Road pumping plants and associated levee, floodwall, and 
power service were awarded in December 1988 and 
January 1989, respectively. Pumping Plants and Levee 
advanced to 14 percent completion. Levee Unit 2, Part 
3 construction contract was awarded in November 1988 
and is 88 percent completed. 
Knight Township, Howell, Unit 1 and Pigeon Creek, 
Unit 1 Sections are complete. Howell Section, Unit 2, is 
in the "inactive" category. Construction of Pigeon Creek 
Section, Unit 2, was started in April 1974 and is about 
89 percent complete. Project is about 66 percent complete 
overall. 
8. MILL CREEK, OH 
Location. Project is located along the 18-mile length 
of Mill Creek and three-fourths mile length of East Fork 
in Hamilton County, OH. Lower Mill Creek is in the commercial 
and industrial heart of the Cincinnati 
metropolitan area in the southwestern portion of the 
State. 
Existing project. Eighteen miles of channel improvement, 
2 miles of levees, two pumping plants, modification 
of 29 bridges, and the addition of two pumping units 
at the present Mill Creek Barrier Dam, located near the 
Ohio River, are included in the project. Acquisition and 
development with appropriate landscaping of 620 acres 
along the creek will be provided for high-density urban 
oriented recreational use. Estimated cost of new work 
(1989) is $202,087,000, of which $42,087,000 is 
non-Federal. 
Local cooperation. Section 3, Flood Control Act of 
1936 as amended, applies. In addition, local interests 
must provide without cost to the United States all 
modifications and relocations of buildings, utilities, street 
and foot bridges, sewers, and related and special facilities 
as necessary for construction of project; prevent encroachment 
on improved channels and on ponding areas which 
would impair capacities; at least annually inform interests 
affected as to degree of protection afforded by project, 
and provide guidance and leadership in preventing 
unwise and uneconomical development of flood plain 
areas by encouraging prudent use of floodproofing, land 
regulation planning, or other flood plain management 
16-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
techniques to reduce flood losses. Further, with respect 
to the recreational aspects of the project, local interests 
are required to furnish assurances that they will, if 
necessary, pay or contribute in kind, a portion of the cost 
of recreational facilities which, when added to the cost 
of recreation land, would amount to at least 50 percent 
of the total first cost of the recreation land and recreational 
facilities, and assure access to the recreation 
facilities to all on equal terms. An assurance agreement 
covering local cooperation requirements for the project 
consistent with Section 221 of the 1970 Flood Control Act 
and the Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970 was executed by the 
Millcreek Valley Conservancy District February 6, 1975, 
and for the Secretary of the Army March 28, 1975. A 
recreation cost sharing contract was executed by the 
Conservancy District February 25, 1975, and approved 
by the Secretary of the Army May 28, 1975. 
Operations during fiscal year. Engineering studies 
continued. Construction Contracts for: Section 8 (Barrier 
Dam) advanced to 44 percent completion; Levee Section 
2- Slide Repair advanced to 83 percent completion; Channel 
Section 4A advanced to 99 percent completion; and 
Channel Sections 2 & 3 Fencing advanced to completion. 
Construction contract for Channel Section 1 was awarded 
in August 1989. Flood damages estimated at 
$1,110,000 were prevented during the 1989 flood season. 
Design Memoranda, Hydrology & Hydraulics, Concrete 
Aggregate and Stone Protection Sources, and Railroad 
Relocations, General Design Memoranda, Phase I and 
Phase II, Design of Channel - Sections 5 and 7 are complete. 
Construction of channel and levee - Sections 2, 3 
and 7A, Phase I, are complete. Project is about 44 percent 
complete overall. 
9. SOUTHWESTERN JEFFERSON 
COUNTY, KY 
Location. In Jefferson County, KY, on left bank of 
Ohio River from mile 616 to 628.6. 
Existing project. Construction of 68,500 feet of levee, 
1,550 feet of concrete wall, four pumping plants, and other 
necessary appurtenances. Project provides protection for 
24,100 acres against Ohio River floods equal to 1937 flood 
of record with 3-foot freeboard. Estimated cost of new 
work (1989) is $66,585,000, of which $56,668,000 is 
Federal, and $9,917,000 is non-Federal. Project was 
authorized under Flood Control Act of August 1968. 
Recreation as a project purpose has been deferred until 
such time as a water quality problem on Pond Creek is 
corrected. 
Local cooperation. Section 3 Flood Control Act of 
1936 as amended applies. In addition, local interests must 
agree to administer project land and water areas for 
recreation and fish and wildlife enhancement; and to pay, 
contribute in kind or repay (which may be through user 
fees) with interest, one-half of the separable first cost of 
the project allocated to recreation and fish and wildlife 
enhancement; and bear all costs of operation, 
maintenance and replacement of lands and facilities for 
recreation and fish and wildlife enhancement. Jefferson 
County Fiscal Court expressed intent to fulfill requirement 
by resolution dated April 4, 1967. Formal 
assurances of local cooperation for the flood protection portion 
of the project was executed by resolution of Jefferson 
County Fiscal Court, adopted September 17, 1971, and 
assurances for the recreation portion of the project were 
executed by similar resolution, adopted September 14, 
1971. Authorization-of-entry for levee and floodwall sections 
1, 2, 3, 4, 4A, 5 and Pond Creek Pump Plant have 
been furnished. 
Operations during fiscal year. Engineering studies 
continued. Contract for Pond Creek Pumps and Motors, 
awarded in May 1985, was advanced to completion. Contract 
for Levee Section 5 and Pond Creek Pumping Station 
awarded in September 1985 was advanced to completion. 
Contract for Remedial Work for Railroad Closure 
at Levee Section 5 was awarded in September 1986 and 
advanced to completion. Construction contract for repairs 
to Sections 1, 2, 3, 4 & 4A was awarded in September 
1989. 
Engineering studies are about 99 percent complete. 
Construction of levee and floodwall Sections 1, 2, 3,4 and 
4A; railroad closure at Section 4; electric service for 
gatewells; Riverport and Upper and Lower Mill Creek 
pumping plants; rehabilitation of pump stations; and 
relocation of Texas Gas pipeline are complete. Project is 
98 percent complete overall. Project was transferred to 
local interest on 8 September 1989. 
Flood Control - Reservoirs 
10. BARREN RIVER LAKE, KY 
Location. Dam is on Barren River, 79.5 miles above 
its confluence with Green River and 10 miles northeast 
of Scottsville, KY. At flood control pool reservoir extends 
upstream about 40 miles in Barren and Allen Counties, 
KY. (See U.S. Geological Survey map of Lucas, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rolled earth and rockfill, 146 feet 
high and 3,970 feet long, with gate-controlled outlet works 
and uncontrolled open-cut spillway. Total storage capacity 
is 815,200 acre-feet (768,000 for flood control and 46,600 
for water supply storage). For further details, see page 
1125 of Annual Report for 1962. Cost of the completed 
project is $27,479,717 including $2,335,055 Federal funds 
and $108,418 non-Federal funds for construction of recreation 
facilities under the completed projects program. Project 
was authorized by Flood Control Act of 1938. 
Local cooperation. None required by authorizing act. 
Under provision of Water Supply Act of 1958, contract 
with City of Glasgow for water supply storage was 
approved by Secretary of Army on October 4, 1965. Terms 
require City to pay $23,433, which is project cost allocated 
to water storage plus capitalized prepayment of proportionate 
share of operation, maintenance, and major 
replacement costs. A contract, with the Commonwealth 
of Kentucky for development of additional campsites, 
shoreline protection and breakwater extension at Barren 
16-4

LOUISVILLE, KY. DISTRICT 
River Lake State Park under the cost-sharing category 
of the completed projects program was approved by the 
Secretary of the Army November 4, 1977. 
Operations during fiscal year. New work: None. 
Maintenance: Contracts for control tower maintenance 
and bulkhead modification and roof replacement were 
completed. Routine maintenance was performed. Operation 
for flood control during the 1989 flood season 
prevented damages of $7,883,000. 
Construction started in March 1960 and all major construction 
and relocation items were completed in October 
1964. Project was placed in operation in March 1964. 
Land acquisition is complete. 
11. BROOKVILLE LAKE, IN 
Location. Damsite is on East Fork of Whitewater 
River, 2.4 miles above confluence with West Fork, and 
about 1-1/2 miles north of Brookville, Indiana. The reservoir 
lies in Franklin and Union Counties, Indiana. (See 
U.S. Geological Survey map of Brookville, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earthfill, 182 feet high and 3,004 
feet long, with gate-controlled outlet works, and uncontrolled 
open spillway. Total storage capacity is 359,600 
acre-feet (214,700 for flood control, 89,300 for water supply, 
and 35,500 for conservation). A minimum pool of 
20,100 acre-feet is maihtained. Estimated cost of new 
work (1989) is $45,416,380 of which $37,918,888 is 
Federal cost and $7,497,492 is non-Federal contribution 
for water supply storage. Project was authorized by 1938 
Flood Control Act. 
Local cooperation. None required by authorizing act. 
Contract with State of Indiana for water supply storage 
under provisions of Water Supply Act of 1958 was 
approved by Secretary of Army, August 5, 1965. Under 
terms of contract, State paid initial costs allocated to 
water supply feature of project plus capitalized prepayment 
of proportionate share of operation and maintenance 
costs. 
Operation during fiscal year. New work: None. 
Maintenance: Installation of hydropower unit is complete 
but is not in operation pending finalization of contract 
with Southeastern Power Administration for purchase of 
surplus power. Operation for flood control during 1989 
flood season prevented damages of $376,000. Routine 
maintenance was performed. 
Construction was started in November 1965 and project 
was placed in operation January 1974. Construction 
and land acquisition are complete. 
12. BUCKHORN LAKE, KY 
Location. Dam is on Middle Fork of Kentucky River, 
43.4 miles above mouth, and 0.5 mile upstream from 
Buckhorn, Perry County, KY. Reservoir extends 
upstream about 34 miles and lies in Leslie and Perry 
Counties, Kentucky. (See U.S. Geological Survey map of 
Buckhorn, KY.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill type, with gate controlled 
outlet works. Total storage capacity is 168,000 
acre-feet, of which 157,600 is for flood control. For further 
details, see page 1120 of Annual Report for 1962. 
Cost of completed new work is $11,766,206 including 
$386,707 for construction of recreation facilities under the 
completed projects program. Existing project was 
authorized by general authorization for Ohio River Basin 
in 1938 Flood Control Act. 
Local cooperation. Department of Parks of the Commonwealth 
of Kentucky has undertaken management of 
lands and recreational facilities in accordance with license 
granted by Secretary of the Army on June 29, 1962. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during 1989 flood season 
prevented damages of $1,463,000. 
Construction started in September 1956 and project was 
placed in operation in August 1960. All construction and 
land acquisition is complete. 
13. CAESAR CREEK LAKE, OH 
Location. Damsite is on Caesar Creek, about 3.0 
miles above its confluence with Little Miami River, in 
Warren County, OH, about 3.5 miles southeast of 
Waynesville, OH, and 10.5 miles northeast of Lebanon, 
OH. Reservoir lies in Warren, Clinton, and Green 
Counties, OH. (See U.S. Geological Survey map of 
Oregonia, OH.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earth and rockfill dam, four saddle dams, outlet works 
and an uncontrolled saddle spillway. Total storage capacity 
of reservoir is 242,200 acre-feet, of which 148,500 acrefeet 
is reserved for flood control storage. Estimated cost 
of new work (1989) is $62,893,882 and $5,037,000 non- 
Federal reimbursement for water supply storage. Existing 
project was authorized by general authorization for Ohio 
River Basin in 1983 Flood Control Act. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of storage 
for future municipal and industrial water supply uses. 
Contract with State of Ohio for water supply storage 
under provisions of Water Supply Act of 1958, as amended, 
was approved by Secretary of the Army, May 20, 1970. 
Under terms of contract, State will reimburse the Federal 
Government for costs allocated to water supply storage 
over a period not to exceed 50 years after use of this 
storage is initiated plus estimated annual amount for cost 
of operation, maintenance and major capital replacements 
required for the water supply facilities. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. Flood 
damages estimated at $2,462,000 were prevented during 
the 1989 flood season. 
Construction was started in January 1968 and the project 
was placed in operation January 1978. Land acquisition 
is complete. All relocation and construction features 
are complete. Project is about 99 percent complete overall. 
16-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
14. CAGLES MILL LAKE, IN 
Location. Dam is on Mill Creek, 2.8 miles above its 
confluence with Eel River, in Putnam County, IN, and 
about 25 miles east of Terre Haute, IN. Reservoir extends 
upstream about 11 miles and is in Putnam and Owen 
Counties, IN. (See U.S. Geological Survey map of Poland, 
IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill embankment. Total 
storage capacity is 228,100 acre-feet, of which 201,000 
acre-feet are for flood control. For details see Annual 
Report for 1962, page 1136. Cost of completed new work 
is $4,376,278 including $155,416 Federal funds, $113,094 
contributed funds and $106,813 non-Federal funds for construction 
of recreation facilities under the completed projects 
program. Existing project was selected for construction 
under general authorization for Ohio River Basin in 
1938 Flood Control Act. 
Local cooperation, None required. State of Indiana 
has undertaken development and management of recreation 
facilities for use of the public in reservoir area in accordance 
with license granted by Secretary cf the Army 
on January 17, 1952. A contract with the Indiana Department 
of Natural Resources for expanding the boat ramp 
and parking area at Site 3, Lieber State Park, under the 
cost sharing category of the completed projects program 
was signed by the State of Indiana on August 26, 1981 
and approved by the Deputy Chief of Engineers on 
March 26, 1982. 
Operations during fiscal year. New Work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1989 flood season 
prevented damages of $3,944,000. 
Construction started in July 1948 and completed in 
June 1953. 
15. CARR FORK LAKE, KY 
Location. Damsite is 8.8 miles above mouth of Carr 
Fork, a tributary of North Fork of Kentucky River, 16 
miles upstream from Hazard, KY. The reservoir lies entirely 
within Knott County. (See U.S. Geological Survey 
maps of Carrie and Vicco, KY.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. Dam is rock and 
earth fill with impervious core, 720 feet long and 130 feet 
high, with uncontrolled open cut spillway through left 
abutment. Outlet works has two control gates and 8-foot 
diameter conduit to stilling basin. Total storage capacity 
is 47,700 acre-feet (31,600 for flood control and 4,300 
for water quality control). A higher level seasonal pool 
for recreation is provided. Estimated Federal cost of new 
work (1989) is $50,854,826 including $76,724 for recreation 
facilities under the completed projects program. Project 
was authorized by the 1962 Flood Control Act. 
Local cooperation. None required for reservoir 
project. Division of Flood Control and Water Usage of 
Commonwealth of Kentucky gave assurance that encroachments 
on downstream channel capacity will be 
prevented. 
Operations during fiscal year. New work: Real 
estate administrative action required for condemnation 
of remaining tracts was continued. Maintenance: Routine 
maintenance was performed. Operation for flood control 
during the 1989 flood season prevented damages of 
$3,450,000. 
Condition at end of fiscal year. Project was placed 
in operation January 1976. Construction started in 
January 1966 is complete. All land required for the project 
has been acquired; however, several acquisition actions 
remain unsettled. 
16. CAVE RUN LAKE, KY 
Location. Damsite is on Licking River, about 4 miles 
upstream from U. S. Highway 60 near Farmers, KY, and 
7 miles southwest of Morehead, KY. Reservoir will be in 
Rowan, Bath, Morgan, and Menifee Counties, KY. (See 
U.S. Geological Survey maps of Salt Lick and Morehead, 
KY.) 
Existing project. Plan provides for construction of a 
reservoir for flood control and allied purposes. Dam is rolled 
earthfill, with gate controlled outlet works and uncontrolled 
open spillway. Total storage capacity is 614,700 
acre-feet (438,500 for flood control and 28,300 for water 
quality control). Estimated Federal cost of new work 
(1989) is $114,826,300 of which $35,213,000 is U. S. Forest 
Service cost. Project was authorized by Flood Control Acts 
of June 22, 1936 and June 28, 1938. 
Local cooperation. None required. 
Operations during fiscal year. New work: None. 
Real estate administrative action required for acquisition 
of remaining tracts was completed. Maintenance: Routine 
maintenance was performed. Operation for flood control 
during the 1989 flood season prevented damages of 
$12,992,000. 
Project has been in operation since February 1974. 
Construction was started in June 1965 and is about 95 
percent complete overall. Land acquisition is complete. 
All relocation and construction features are complete 
except recreation facilities. 
17. CECIL M. HARDEN LAKE, IN 
Location. Dam is on Raccoon Creek, 32.4 miles above 
its confluence with Wabash River, and 25 miles northeast 
of Terre Haute, IN. At flood control pool, reservoir extends 
upstream about 15 miles in Parke and Putnam Counties, 
Indiana. (See U. S. Geological Survey Map of Mansfield, 
IN.) 
Existing project. A rolled earth dam and reservoir, 
for flood control and allied purposes. Total storage 
capacity is 132,800 acre-feet of which 116,600 acre-feet 
are for flood control. For details, see Annual Report for 
1962, page 1132. Cost of completed new work is 
$6,987,807 made up of $6,260,134 for the initial project 
and $373,678 Federal cost and $353,995 non-Federal 
contribution in kind for recreation facilities under the 
completed projects program. Project was selected for construction 
under general authorization for Ohio River 
16-6

LOUISVILLE, KY. DISTRICT 
Basin in 1938 Flood Control Act. Project name was changed 
from Mansfield Lake to Cecil M. Harden Lake by 
Public Law 93-521, December 14, 1974. 
Local cooperation. State of Indiana has undertaken 
management of lands and recreational facilities in 
accordance with license granted by Secretary of the Army 
on April 19, 1961. A contract with the Indiana Department 
of Natural Resources, approved by the Secretary of 
the Army in May 1974, provided for that agency to design 
and construct certain additional recreation facilities at 
Cecil M. Harden, Huntington, Mississinewa, Monroe and 
Salamonie Lakes under the cost sharing category of the 
completed projects program. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. Flood 
damages of $5,651,000 were prevented during the 1989 
flood season. 
Construction started in October 1956 and all major 
items of work were completed December 1961. Land acquisition 
is complete. Project has been in operation since 
August 1960. Cost shared recreation facilities constructed 
by the State of Indiana under the completed projects program 
are completed. 
18. CLARENCE J. BROWN DAM & 
RESERVOIR, OH 
Location. Damsite is just east of Springfield, Clark 
County, OH, at mile 7.3 of Buck Creek, a tributary of Mad 
River. (See U. S. Geological Survey maps of New 
Moorefield and Springfield, OH.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, 6,620 feet 
long and 72 feet high, with gated outlet works and open 
cut spillway with concrete chute through right abutment. 
Total storage capacity of reservoir is 63,700 acre-feet 
(32,900 for flood control and 20,800 for water quality control). 
Federal cost of completed project is $22,083,660. Project 
was authorized by 1962 Flood Control Act. Project 
name was changed from Buck Creek Dam and Reservoir 
to Clarence J. Brown Dam and Reservoir by Public Law 
90-46, July 4, 1967. 
Local cooperation. Assurances from City of 
Springfield, Springfield Conservancy District, and Clark 
County, Ohio, covering protection against detrimental 
channel encroachment below dam to mouth of Buck 
Creek, were accepted March 5, 1964. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. Flood 
damages of $10,000 were prevented during the 1989 flood 
season. 
Construction started in September 1966. Land acquisition 
and all major project features were completed in 
November 1973. The project was placed in operation in 
January 1974. 
19. GREEN RIVER LAKE, KY 
Location. Damsite is 305.7 miles above mouth of 
Green River in Taylor County, KY, about 8 miles south 
of Campbellsville. Reservoir lies in Taylor and Adair 
Counties. (See U. S. Geological Survey map of Cane 
Valley, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth and rock-fill, 141 feet high 
and 2,350 feet long. Outlet works is slide gate-controlled 
and spillway open and uncontrolled. Total storage 
capacity is 723,200 acre-feet (560,600 for flood control and 
64,500 for low-flow augmentation). Cost of completed new 
work is $33,462,330, including $317,145 Federal funds 
and $183,732 non-Federal funds for construction of recreation 
facilities under the completed projects program. 
Existing project was authorized under general authorization 
for Ohio River Basin in 1938 Flood Control Act. 
Local cooperation. None required by authorizing act. 
Taylor County, by lease approved by Secretary of Army 
February 15, 1968, undertook operation and maintenance 
of Smith Ridge public access area. In May 1980, the lease 
was amended to turn back responsibility for maintenance, 
and operation of 99 percent of the site to the Corps, with 
the County retaining responsibility for the marina area. 
Under provision of Water Supply Act of 1958, contract 
with City of Campbellsville for water supply storage was 
approved by Secretary of Army April 23, 1969. Terms require 
city to repay, with interest and annual charges for 
operation, maintenance and major replacement, the investment 
cost of $85,765 allocated to its water supply 
storage space. Total payments received through fiscal 
year 1984 was $21,504. The Department of Parks of the 
Commonwealth of Kentucky, by lease approved by 
Secretary of Army, October 4, 1971, has undertaken the 
management of the Lone Valley public access area. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages estimated 
at $5,052,000 during the 1989 flood season. 
Construction began in August 1965 and all major construction 
and relocation items were completed in 1972. 
Project has been in operation since February 1969. Project 
including all land acquisition complete in 1973. 
Construction of sanitary dump station for boats at Dam 
Site in conformance with EPA and State standards and 
rehabilitation of sewage treatment facilities, washhouses 
and restrooms at Smith Ridge site is complete. 
20. HUNTINGTON LAKE, IN 
Location. Damsite is on Wabash River, about 2 miles 
from Huntington, IN, and 411.4 miles above mouth. 
Reservoir is in Huntington and Wells Counties, IN. (See 
U. S. Geological Survey maps of Majenica and Mt. Etna, 
IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam consiste of a rolled earth embankment 
4,700 feet long and 89 feet high, a concrete spillway and 
outlet section 155 feet long, and a concrete gravity section 
310 feet long. Spillway is controlled by three gates, 
16-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
and outlet works by six sluices. Project also provides local 
flood protection for Markle, IN. Total storage capacity of 
reservoir is 153,100 acre-feet, of which 149,000 acre-feet 
is reserved for flood control storage. Estimated cost for 
new work (1989) is $19,622,509 made up of $19,273,252 
Federal cost for the initial project and $193,903 non- 
Federal contributed funds for low flow augmentation 
storage, and $155,354 non-Federal contribution in kind 
for recreation facilities under the completed projects program. 
Project was authorized by Flood Control Act of 
1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana has met this obligation. Contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army May 17, 1974, provided 
for that agency to design and construct certain 
additional recreational facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost shared category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Repairs to the Operating Tower were completed. 
Routine maintenance was performed. Operation 
for flood control prevented damages estimated at 
$1,484,000 during the 1989 flood control season. 
Land acquisition and all major construction complete. 
Project was placed in operation January 9, 1969. Cost 
shared recreation facilities constructed by the State of 
Indiana under the completed projects program are 
complete. 
21. MISSISSINEWA LAKE, IN 
Location. Damsite is 7.1 miles above mouth of 
Mississinewa River, which flows into Wabash River about 
2 miles upstream from Peru, IN. At flood control pool 
level, reservoir extends upstream about 28 miles, in 
Wabash, Grant, and Miami Counties, IN. (See U.S. 
Geological Survey map of Peoria, IN.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earthfill dam 137 feet high and 8,100 feet long, gatecontrolled 
outlet works, and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 368,400 acre-feet, of which 345,100 acrefeet 
are reserved for flood control storage. Cost for completed 
new work is $24,381,129 made up of $23,793,145 
Federal cost for the initial project, $239,200 non-Federal 
contributed funds for low flow augmentation storage, 
$174,392 Federal cost and $174,392 non-Federal contribution 
in kind for recreation facilities under the completed 
projects program. Project was authorized by the Flood 
Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to 1 percent of project first cost. 
State of Indiana assumed this obligation. A contract with 
the Indiana Department of Natural Resources, approved 
by the Secretary of the Army in May 1974, provided for 
that agency to design and construct certain additional 
recreation facilities at Cecil M. Harden, Huntington, 
Mississinewa, Monroe and Salamonie Lakes under the 
cost sharing category of the completed projects program. 
Operations during fiscal year. New work: None 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages of 
$4,739,000 during 1989 flood season. 
Construction and land acquisition is complete. Project 
was placed in operation in May 1968. Cost shared recreation 
facilities cconstructed by the State of Indiana under 
the completed projects program are complete. 
22. MONROE LAKE, IN 
Location. Dam is on Salt Creek, a tributary of White 
River, 25.9 miles above mouth, and 2 miles each of 
Harrodsburg, Monroe County, IN. At flood control pool 
level, reservoir will extend upstream 44 miles in Monroe, 
Brown, and Jackson Counties. (See U.S. Geological 
Survey map of Clear Creek, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth core and rock shell, with 
gate-controlled outlet works and uncontrolled open 
spillway. Total storage capacity is 441,000 acre-feet 
(258,800 for flood control and 159,900 for low flow 
augmentation.) Cost of completed new work is 
$16,569,589 made up of $7,033,669 Federal cost for the 
initial project and $7,797,604 non-Federal contributed 
funds for low-flow regulation storage and $869,158 
Federal cost and $869,158 non-Federal contribution in 
kind for recreation facilities under the completed projects 
program. Project was authorized by 1958 Flood Control 
Act, modifying comprehensive plan for Ohio River Basin. 
Local cooperation. Section 3, 1944 Flood Control Act 
applies. Local interests must contribute 54.1 percent of 
project cost, this being the proportion allocated to low-flow 
regulation feature, plus a capitalized amount 
representing that part of average annual maintenance 
and operation cost allocated to low-flow regulation. State 
of Indiana assumed this cost sharing obligation. A contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 1974, provided 
for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages of 
$1,634,000 during 1989 flood season. 
Project is complete and was placed in operation in 
February 1965. Cost shared recreation facilities constructed 
by the State of Indiana under the completed 
projects program are complete. 
23. NOLIN LAKE, KY 
Location. Dam is on Nolin River 7.8 miles above its 
16-8

LOUISVILLE, KY. DISTRICT 
confluence with Green River, about 70 air miles 
southwest of Louisville, KY. Reservoir extends upstream 
about 57 miles and is in Edmonson, Grayson, Hart, and 
Hardin Counties, KY. (See U.S. Geological Survey maps 
of Nolin Reservoir and Dickeys Mill, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rockfill-earth core type with gatecontrolled 
outlet works, and uncontrolled open spillway. 
Total storage capacity is 609,400 acre-feet, of which 
545,600 acre-feet.is for flood control. For further details 
of project see Annual Report for 1962, page 1124. 
Estimated Federal cost of new work (1989) is $17,193,381 
including $2,594,377 for construction of recreation 
facilities. Project was selected for construction under 
general authorization for Ohio River Basin in 1938 Flood 
Control Act. 
Local cooperation. None required for authorized 
project. State of Kentucky contributed $18,195 for 
increased width of dam for public road. 
Operations during fiscal year. New work: None. 
Maintenance: Contracts for control tower maintenance, 
bulkhead modification, and ramp improvements were 
completed, and Stilling Basin repairs continued. Rountine 
maintenance was performed. Operation for flood control 
during the 1989 flood season prevented damages 
estimated at $4,794,000. 
Construction started in January 1959. Project was completed 
and placed in operation in March 1963. 
24. OHIO RIVER BASIN 
(Louisville District) 
Location. Works covered by this project are a series 
of levees, floodwalls, channel improvements, and reservoirs 
in Ohio River Basin within Louisville District. 
Existing project. Individual projects considered in 
comprehensive plan within the Louisville District. (See 
Table 16-B for authorizing leglsiation, and Table 16-I for 
cost and listing of projects in the basin plan.) 
Operations during fiscal year. No costs were 
incurred except for these projects for which individual 
reports are given. 
25. PATOKA LAKE, IN 
Location. Damsite is in Dubois County, IN, 118.3 
miles above mouth of Patoka River, and 50 miles westnorthwest 
of New Albany, IN. Reservoir extends into 
Dubois, Orange and Crawford Counties. (See Geological 
Survey map of Cuzco, IN.) 
Existing project. Reservoir for flood control and allied 
purposes. Dam is earth and rock fill, 1,550 feet long and 
85 feet high, with gate-controlled outlet works and uncontrolled 
open spillway. Total storage capacity is 301,600 
acre-feet (121,000 for flood control and 167,500 for water 
supply and water quality control). Estimated cost of new 
work (1989) is $73,664,159 of which $53,095,790 is 
Federal cost for other construction, and $20,568,369 is 
non-Federal contribution for water supply storage and 
recreation facilities. Project was authorized by 1965 Flood 
Control Act, and emergency measures and snagging and 
clearing the Patoka River downstream of Patoka Lake 
to insure effective operation of the project for flood control 
was directed by 1981 Appropriation Act for Energy 
and Water Development. 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated to 
water supply storage over a period not to exceed 50 years 
after use of this storage is initiated, presently estimated 
at 29.316 percent of the joint-use facilities cost, exclusive 
of interests, plus $287,000 for the cost of operating and 
maintaining water supply storage for a period of 50 years, 
plus $42,000 for the cost of major capital replacements 
required for water supply storage space for a period of 50 
years. Local interests are also required to pay, contribute 
in kind, or repay (which may be through user fees) with 
interest, one-half of the separable first cost of the project 
allocated to recreation. Present laws of the State of 
Indiana require that agency to make cash contributions 
during construction of the project. Local interests must 
also agree to prevent encroachments on channel of Patoka 
River from dam to mouth, and to pay allocated initial and 
annual maintenance and operation costs for water supply 
storage. Formal assurances of local cooperation, executed 
by the Indiana Natural Resources Commission, were 
accepted August 27, 1970. Contracts with State of Indiana 
for water supply and recreation were approved by the 
Secretary of the Army November 2, 1970. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1989 flood season 
prevented damage estimated at $1,894,000. 
Construction was started in July 1972. Engineering 
studies are complete. Land acquisition is about 99 percent 
complete. All major features are complete. Permanent 
impoundment was started in February 1978 and the 
project was placed in operation about August 1980. The 
project is about 99 percent complete overall. 
26. ROUGH RIVER LAKE AND 
CHANNEL IMPROVEMENT, KY 
Location. Dam is on Rough River, 89.3 miles above 
its confluence with Green River 160.3 miles above Ohio 
River, and about 60 miles southwest of Louisville, KY. 
Reservoir extends upstream about 30 miles and is in 
Breckinridge, Hardin, and Grayson Counties, KY. Channel 
improvement work is on Rough River, Barnett Creek, 
and West Fork of Barnett Creek. (See U.S. Geological 
Survey maps of McDaniels and Falls of Rough, KY.) 
Existing project. Reservoir is for flood control and 
allied purposes. Dam is rolled earthfill type, with gatecontrolled 
outlet works. Storage capacity is 334,380 acrefeet, 
of which 314,210 acre-feet is for flood control. Project 
also includes channel clearing of lower Rough River, and 
channel improvement on Barnett Creek, a tributary of 
Rough River. For further details see page 1126 of Annual 
16-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Report for 1962. Cost of completed new work is 
$10,643,001 including $890,008 Federal funds and 
$22,612 non-Federal funds for construction of recreation 
facilities under the completed projects program. Existing 
project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. Modification of previousli approved plan to include 
channel improvement items was authorized by the 
1944 Flood Control Act. 
Local cooperation. None required for construction of 
reservoir unit. Provisions of Section 3, Flood Control Act 
of 1936, are applicable to channel improvements. 
Assurances were obtained from Ohio County for channel 
improvement. Department of Parks, Commonwealth of 
Kentucky, has undertaken management of certain lands 
and recreation facilities in accordance with license 
granted by Secretary of the Army on August 18, 1961. 
A contract with the Commonwealth of Kentucky to improve 
and pave road at the Below Dam Area - State Park 
under the cost sharing category of the completed projects 
program was approved by the Secretary of the Army 
November 4, 1977. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1989 flood season 
prevented damages estimated at $6,565,000. 
Construction started in November 1955 and reservoir 
was placed in operation in June 1959. Land acquisition 
and all major items of construction and relocation are 
complete. 
27. SALAMONIE LAKE, IN 
Location. Damsite is 3.1 miles above mouth of 
Salamonie River which enters Wabash River about 6 
miles upstream from Wabash, IN. Reservoir extends 
upstream about 27 miles at flood control pool and lies in 
Wabash and Huntington Counties, IN. (See U. S. 
Geological Survey maps of Lagro and Majenica, IN.) 
Existing project. Provides for construction of a reservoir 
for flood control and allied purposes. It includes an 
earthfill dam with a maximum height of 133 feet and and 
length of 6,100 feet, gate-controlled outlet works with a 
16-foot diameter conduit and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 263,600 acre-feet, of which 250,500 acrefeet 
is for flood control storage. Estimated project cost for 
new work (1989) is $17,046,151 made up of $16,244,356 
Federal cost for the initial project and $170,697 non- 
Federal contributed funds for low-flow augmentation 
storage and $315,549 Federal cost and $315,549 non- 
Federal contribution in kind for recreation facilities under 
the completed projects program. Project was authorized 
by Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana assumed this obligation. A contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 1974, provided 
for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe, and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. During 
the 1989 flood season, operation for flood control 
prevented damages of $2,906,000. 
Land acquisition and all major construction and relocation 
contracts are complete. Reservoir was placed in 
operation in spring 1967. Cost shared recreation facilities 
constructed by the State of Indiana under the completed 
projects program are complete. 
28. TAYLORSVILLE LAKE, KY 
Location. Damsite is in Spencer County, KY, 60.0 
miles above the confluence of Salt River and Ohio River, 
4 river miles above Taylorsville and 36.9 river miles 
above Shepherdsville, KY. (See U. S. Geological Survey 
map of Taylorsville, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam will be an earth and rock fill structure, 
164 feet high and 1,280 feet long. Outlet works will 
be slide gate controlled and spillway will be uncontrolled 
open cut. Total storage capacity will be 291,670 acre-feet 
(211,230 for flood control, winter months), and 52,245 for 
water quality and fish and wildlife. Estimated cost of new 
work (1989) is $122,084,000 made up of $92,977,000 
Federal cost for the initial project and $17,017,000 non- 
Federal contributed funds for initial recreation facilities 
and $6,045,000 Federal cost and $6,045,000 non-Federal 
contributed funds for recreation facilities under the completed 
projects program. Project was authorized by 1966 
Flood Control Act. 
Local cooperation. Local interests must agree to administer 
project land and water areas for recreation; pay, 
contribute in kind, or repay (which may be through user 
fees) with interest one-half of the separable first costs of 
the project allocated to recreation; bear all costs of operation, 
maintenance, and replacement of recreation lands 
and facilities. Local interests must also agree to prevent 
encroachments on flow-carrying capacities of stream 
channels below the reservoir to the extent needed to provide 
reasonably effective reservoir operation. Commonwealth 
of Kentucky has indicated intent to fulfill requirements 
for recreation cost sharing and has assumed 
responsibility for channel encroachments and pollution 
control. The Commonwealth furnished assurance 
agreements covering prevention of encroachment on 
capacity of stream channels in April and May 1973 and 
executed the recreation cost sharing contract in April 
1973. On April 2, 1980 the U. S. District Court for the 
Western District of Kentucky ruled that the 1973 recreation 
cost sharing contract between the Commonwealth 
and the United States that provded for repayment after 
completion was invalid under the Kentucky Constitution 
which prohibits one General Assembly from obligating 
future appropriations that would be binding on a subsequent 
legislature. In response to the Court's ruling, the 
Commonwealth and the United States entered into a new 
16-10

LOUISVILLE, KY. DISTRICT 
contract providing for cash contributions. Contract was 
approved by the Secretary of the Army June 11, 1980. The 
contract was found to be valid and enforceable by the 
Court July 14, 1980. 
Operations during fiscal year. New work: Engineering 
and design studies and land acquisition continued. 
Contracts for Possum Ridge Roads, Campground Utilities, 
Telephone Line relocations, and Power service were completed. 
Contracts for Power Service advanced to 80 percent 
completion. Contracts were awarded for Possum 
Ridge Sewage Treatment Plant and Force Main Outfall 
and advanced to 47 percent completion. Routine 
maintenance was performed. During the 1989 flood 
season operation for flood control prevented damages of 
$2,502,000. 
Engineering and design studies are about 93 percent 
complete and land acquisition is about 97 percent complete. 
Construction was started in June 1974. All major 
construction items are complete except recreation 
facilities. The dam gates were closed in January 1983 for 
permanent impoundment. Dedication ceremony was May 
28, 1983. The project is about 90 percent complete overall. 
29. WABASH RIVER BASIN 
Location. Works covered by this project are located 
in the Wabash River Basin, a drainage area of 33,100 
square miles, covering parts of Indiana, Illinois and Ohio. 
Existing project. One local protection project and five 
reservoir projects were authorized for this basin plan. (See 
Table 16-B for authorizing legislation and Table 16-J for 
project list and total cost of basin plan.) 
30. WEST FORK OF MILL 
CREEK LAKE, OH 
Location. Dam is on West Fork of Mill Creek 6.5 
miles above its junction with Mill Creek and 2 miles 
northeast of Mount Health, OH, and 10 miles north of 
downtown Cincinnati. Reservoir extends upstream about 
3 miles and is in Hamilton County, OH. (See U. S. 
Geological Survey map of Glendale, OH.) 
Existing project. An earth embankment dam and a 
reservoir for flood control, recreation, and reduction of 
pumping requirements at Mill Creek barrier dam in 
Cincinnati. Total storage capacity of reservoir is 11,300 
acre-feet, of which 9,850 acre-feet is for flood control. For 
further details see page 1119 of Annual Report for 1962. 
Cost of completed new work is $4,722,463 made up of 
$3,092,941 Federal cost for the initial project, $520,800 
non-Federal cost for sewer relocation and dam, $50,000 
non-Federal contributed funds in fulfillment of project 
authorization and $529,361 Federal cost and $529,361 
non-Federal contribution in kind for recreation facilities 
under the completed projects program. Existing project 
selected for construction under additional authorization 
for Ohio River Basin in 1946 Flood Control Act. 
Local cooperation. Local interests were to release 
necessary land under their control and give assurance 
that future channel encroachment below damsite would 
be prevented. For enlargement of reservoir to include a 
conservation pool, local interests would contribute onehalf 
additional cost of such pool, including one-half cost 
of relocation of sanitary sewer, and agree to hold the 
United States free from damages resulting from its provision. 
Board of County Commissioners of Hamilton 
County, Ohio, adopted a resolution October 8, 1947, signifying 
willingness to fulfill requirements including provision 
of conservation pool. Assurances were executed on 
same date. A contract with the United States for relocation 
of sanitary sewer outside reservoir area in order to 
include conservation pool in project was accepted by 
Hamilton County, in which the United States paid onehalf 
cost of such relocation work. Hamilton County 
Commissioners furnished $50,000, required as a local contribution 
toward additional cost of providing conservation 
pool. Hamilton County Park District has undertaken 
development and management of recreation facilities in 
reservoir area for use of the public in accordance with the 
license granted by Secretary of the Army on October 31, 
1951. Contract for cost shared recreation development 
under the completed works program was executed by the 
Board of Park Commissioners, Hamilton County Park 
District, Ohio, in September 1975 and approved by the 
Chief of Engineers in December 1975. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during 1989 flood season 
prevented damages estimated at $10.000. 
Construction started in March 1949 and reservoir was 
placed in operation in December 1952. Project is complete. 
Cost shared recreation development under the completed 
projects program is complete. 
31. WILLIAM H. HARSHA LAKE, OH 
Location. Damsite is on East Fork of Little Miami 
River between Batavia and Williamsburg, OH, about 6.0 
miles above Batavia and 32.6 miles above mouth of the 
Little Miami River. Entire project lies in Clermont 
County, OH. (See U. S. Geological Survey map of Batavia, 
OH.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, outlet works, 
an uncontrolled saddle spillway, and a dike to close a saddle 
north of spillway. Total storage capacity of reservoir 
is 294,800 acre-feet, of which 210,600 acre-feet is reserved 
for flood control storage. Estimated cost of new work 
(1989) is $55,230,000 and $3,485,840 non-Federal reimbursement 
for water supply storage. Existing project was 
authorized by general authorization for Ohio River Basin 
in 1938 Flood Control Act. Project name was changed 
from East Fork Lake to William H. Harsha Lake effective 
January 4, 1981 by Public Law 96-383, October 6, 
1980. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of storage 
for future municipal and industrial water supply uses. 
Contract with State of Ohio for water supply storage 
under provisions of Water Supply Act of 1958, as amend- 
16-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
ed, was approved by Secretary of the Army, May 20, 1970. 
Under terms of contract, State will reimburse the Federal 
Government for costs allocated to water supply storage 
over a period not to exceed 50 years after use of this 
storage is initiated plus estimated annual amount for cost 
of operation, maintenance and major capital replacements 
required for the water supply facilities. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during 1989 flood season 
prevented damages estimated at $4,140,000. 
Construction was started in May 1970. Engineering 
studies are 94 percent complete. All land required for 
project has been acquired. Major relocation and construction 
features are complete, except one recreation item. 
Project is about 94 percent complete overall and reservoir 
was placed in operation in February 1978. 
32. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent acts 
require local interests to maintain and operate local 
protection projects in accordance with regulations 
prescribed by Secretary of the Army. Inspections were 
made to determine extent of compliance and to advise interests 
as necessary to measures required to correct deficiencies. 
(See Table 16-K for local protection projects and 
channel improvements inspected.) 
Fiscal year costs were $117,984. Total costs to 
September 30, 1989 were $3,130,001 
33. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 16-E. 
34. FLOOD CONTROL WORKS UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities pursuant to Public 
Law 99, 84th Congress, and antecedent legislation. Costs 
for fiscal year were $234,827 for disaster preparedness. 
No funds were expended for emergency operations or 
repair work on local protection projects. 
Flood control activities pursuant to Section 205, 1948 
Flood Control Act, Public Law 858, 80th Congress, as 
amended. Costs for fiscal year were $187,462 for preparation 
of Reconnaissance Studies, Summary Fact Sheets, 
and Detailed Project Reports on 8 projects, and $10,385 
for Plans and Specifications on one project and construction 
on one project. 
See Table 16-L. 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (Section 208, 1954 
Flood Control Act, Public Law 780, 83rd Congress). Costs 
for fiscal year were $8,607 for Plans and Specifications 
on one project. 
See Table 16-L. 
Emergency bank protection (Section 14, 1946 Flood Control 
Act, Public Law 526, 79th Congress). Costs for fiscal 
year were $20,416 for preparation of Reconnaissance 
Studies on 4 projects, $99,723 for start of Plans and 
Specifications on 5 projects, and $42,839 for construction 
of one project. 
See Table 16-L. 
Streambank demonstration project (Section 603, 1986 
Water Resource Development Act, Public Law 662, 99th 
Congress). Cost for fiscal year were $28,349 for a study 
report at Ohio River, Gallatin County, IL. 
General Investigations 
35. SURVEYS. 
Fiscal year costs were $2,406,561 consisting of 
$1,602,881 for three flood damage prevention studies and 
the Ohio River Main Stem Study; $320,611 for navigation 
study; $221,532 for the Wabash River Comprehensive 
Middle Reaches Interim, $75,059 for Special Investigations, 
$29,160 for review of Federal Energy 
Regulatory Commission licenses, $20,946 for Dam Safety 
criteria studies, and $136,373 for planning assistance 
to states. 
36. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $222,562 for flood plain management 
services. 
37. PRECONSTRUCTION 
ENGINEERING AND DESIGN 
Fiscal year costs were $3,658,216 for continuation of 
detailed planning and engineering studies for Olmsted 
Locks & Dam. Fiscal year costs were $482,251 for 
Preconstruction Engineering and Design (PED) studies 
on Holes Creek, West Carrollton, Ohio; Miami River, 
Pleasant Run, Ohio; South Frankfort, Kentucky Local 
Proteciton Projects; and the Louisville Waterfront Park 
study. 
16-12

LOUISVILLE, KY. DISTRICT 
TABLE 16-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1986 1987 1988 1989 Sep 30, 1989 
Navigation - Locks and Dams 
2 Green and Barren New Work 
Rivers, KY Approp. 
Cost 
Maint. 
Approp. 
Cost 
3 Kentucky River, KY New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Flood Control - Local Protection 
7 Evansville, IN New Work 
Approp. 
Cost 
8 Mill Creek, OH 
9 Southwestern 
Jefferson County, 
KY 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Flood Control - Reservoirs 
10 Barren River Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
11 Brookville Lake, IN 
12 Buckhorn Lake, KY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
> - 9 - 9 - e - 
1,238,500 1,254,300 1,062,900 1,440,900 
1,267,516 1,206,604 1,067,343 1,297,228 
$13,808,2221 
13,808,2221 
31,860,212' 3 
31,659,207 
- - - - 4,176,749 
- - - - 4,176,749 
2,505,800 1,744,500 994,200 1,565,200 53,259,4894 s 
2,493,699 1,735,988 947,928 1,479,695 53,095,373^ * 
- - - - 556,956 
- - - - 556,956 
-89,000 363,000 598,000 5,065,187 34,403,0436 
300,448 410,957 579,623 2,864,214 32,095,146' 
9,614,000 12,463,000 15,153,000 
10,064,391 10,592,245 13,791,850 
10,865,000 
6,350,916 
78,852,742 
69,969,271 
3,484,000 6,422,000 6,153,000 1,777,000 56,697,183 
4,731,054 5,664,866 7,058,291 1,739,587 55,755,163 
1,189,000 
1,167,073 
95 
420,000 
410,678 
1,740,100 
1,658,886 
1,466,900 
1,403,868 
-13,805 
1,196,700 
1,351,926 
27,479,7178 
27,479,7178 
17,893,126 1o 11 
17,837,5709 10 11 
- 45,416,38012 
- 45,402,56512 
416,500 468,400 533,100 5,239,189 
400,067 451,075 567,567 5,224,492 
- - - - 11,766,20613 
- - - - 11,766,20613 
791,500 660,400 651,300 675,100 10,853,71014 
801,081 648,737 601,512 724,265 10,822,99714 
16-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1989 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1986 1987 1988 1989 Sep 30, 1989 
Flood Control - Reservoirs 
13 Caesar Creek Lake, OH 
14 Cagles Mill Lake, IN 
15 Carr Fork Lake, KY 
16 Cave Run Lake, KY 
17 Cecil M. Harden Lake, 
IN 
18 Clarence J. Brown 
Dam & Reservoir, 
OH 
19 Green River Lake, KY 
20 Huntington Lake, IN 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$ - 
162,680 
631,000 
601,671 
228 
346,000 
371,968 
1,845 
747,000 
784,850 
786,628 
485,000 
501,921 
$ - 
11,388 
792,100 
771,070 
$ - 
32,958 
743,200 
760,749 
404,600 419,700 
386,493 399,204 
27,269 
855,900 
814,628 
400,000 
615,829 
478,300 
470,412 
7,000 
802,400 
819,487 
17,497 
513,000 
502,958 
-3,725 
650,900 
666,348 
343,900 
377,443 
772 
882,400 
915,926 
17,417 
517,800 
515,762 
$62,893,882 
62,884,788 
6,038,663 
6,005,862 
4,376,27815 
4,376,27816 
6,100,706 
6,091,412 
50,854,82617 
50,852,17317 
9,182,60018 
9,162,14318 
74,262,282 
74,199,983 
5,864,646 
5,834,070 
- - - - 6,987,80719 
- - - - 6,987,80719 
518,400 474,000 652,700 683,800 7,407,996 
500,086 472,566 615,395 706,592 7,368,398 
- - - - 22,083,660 
- - - - 22,083,660 
379,000 420,900 431,100 425,400 4,913,747 
372,932 412,987 411,888 449,834 4,897,584 
1,124,000 941,000 
1,143,281 945,408 
- - 33,462,33020 
- - 33,462,33020 
943,800 889,397 14,592,94621 
900,784 945,736 14,559,95121 
- - - - 19,622,5092 
- - - - 19,621,764$ 
483,000 464,900 1,000,300 453,100 6,613,312 
458,903 431,702 1,000,638 495,401 6,593,446 
16-14

LOUISVILLE, KY. DISTRICT 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding 1986 1987 1988 1989 Sep 30, 1989 
Flood Control - Reservoirs 
21 Mississinewa Lake, IN 
22 Monroe Lake, IN 
23 Nolin Lake, KY 
24 Ohio River Basin, 
Louisville District 
25 Patoka Lake, IN 
26 Rough River Lake & 
Channel Improvement, 
KY 
27 Salamonie Lake, IN 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$ 3,003 
411,000 
494,721 
411,200 418,700 
397,788 423,085 
$ - 
446,700 
456,896 
$24,381,12924 
24,379,80025 
5,755,705 
5,743,848 
- - - - 16,569,58926 
- - - - 16,569,58926 
459,600 434,800 572,100 629,700 6,639,02527 
467,832 413,156 591,033 624,204 6,620,58327 
- - -970 
1,413,000 2,011,400 2,208,900 
1,424,694 1,958,358 2,265,061 
- 17,193,38128 
- 17,191,44129 
1,291,100 20,944,3150 
1,297,261 20,870,60430 
- 1,526,142 
- 1,526,142 
8,114 
379,000 
385,206 
20,863 
412,700 
408,563 
15,000 
13,837 
386,200 
377,388 
2,480 
431,600 
432,867 
73,664,15931 
73,316,74432 
3,645,631 
3,620,544 
- - - - 10,643,00133 
- - - - 10,643,00133 
1,095,000 1,304,500 1,007,600 1,575,300 19,402,21034 
1,104,891 1,241,626 997,292 1,602,455 19,312,07134 
444,000 411,700 435,400 
418,578 394,597 452,523 
408,768 
421,912 
17,046,15135 
17,039,32136 
5,843,181 
5,825,496 
16-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1986 1987 1988 1989 Sep 30, 1989 
Flood Control - Reservoirs 
28 Taylorsville Lake, KY New Work 
Approp. $ - $305,000 $481,000 $486,000 $86,097,309" 
Cost 516,124 285,296 756,351 904,636 84,990,47438 
Maint. 
Approp. 528,000 548,900 537,000 626,800 3,377,700 
Cost 535,625 541,164 515,309 626,165 3,339,135 
30 West Fork of Mill New Work 
Creek Lake, OH Approp. - - - - 4,722,46339 
Cost - - - - 4,722,46339 
Maint. 
Approp. 285,000 296,200 392,600 280,000 4,727,689 
Cost 286,138 282,997 367,143 305,440 4,711,217 
31 William H. Harsha New Work 
Lake, OH Approp. - - - - 52,023,15740 
Cost 116,209 8,270 5,378 885 52,023,15740 
Maint. 
Approp. 481,200 444,900 442,300 453,335 4,520,101 
Cost 482,245 443,723 423,889 473,034 4,501,762 
1 Includes $85,000 public works funds. 
2 Includes $2,000 emergency relief funds, $204,444 
"maintenance and operation of dams and other improvements 
of navigable waters" and $3,842,667 expended from 1888 to 
30 June 1936, for operation and care from permanent indefinite 
appropriation. 
$ Includes $725,715 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
4 Includes $316,871 under "maintenance and operation of 
dams and other improvements of navigable waters," and 
$6,405,372 expended between July 5, 1885 and June 30, 1937 
on operation and care from permanent indefinite appropriation. 
a Includes $149,700 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
Includes $11,812 emergency relief funds and $63,187 contributed 
funds. 
' Includes $1,518 contributed funds. 
8 Includes $2,224,948 Code 711 funds, $110,107 Code 713 
Federal funds and $108,418 Code 713 non-Federal funds. 
9 Includes $100,000 Supplemental funds. 
1o Includes $326,900 Special Recreation Use Fees. 
11 Includes $214,675 "maintenance and operation of dams and 
other improvements of navigable water." 
12 Includes $7,497,492 contributed funds and $100,706 Code 
711 funds. 
18 Includes $61,451 public work acceleration executive 1963 
funds, $143,088 Code 711 funds, and $243,619 Code 712 funds. 
14 Includes $52,240 Special Recreation Use Fees. 
15 Includes $35,814 Code 711 funds, $119,602 Code 713 funds, 
and $113,094 contributed funds. 
16 Includes $35,814 Code 711 funds, $119,602 Code 713 funds, 
and $106,813 contributed funds. 
17 Includes $76,724 Code 711 funds. 
18 Includes $51,854 Special Recreation Use Fees. 
19 Includes $19,683 Code 711 funds, $353,995 Code 713 funds, 
and $353,995 non-Federal contributions in kind for recreation 
facilities. 
2 Includes $133,413 Code 711 funds, $183,732 Code 713 funds, 
and $40,001 contributed funds. 
21 Includes $114,280 Special Recreation Use Fees and 
$214,675 under "maintenance and operation of dams and other 
improvements of navigable water." 
SIncludes $155,354 Code 713 funds and $193,903 contributed 
funds. 
Includes $155,354 Code 713 funds and $193,812 contributed 
funds. 
Includes $215,000 Code 711 funds, $174,392 Code 713 funds, 
$239,200 contributed funds and $174,392 non-Federal contribution 
in kind for recreation facilities. 
25 Includes $215,000 Code 711 funds, $174,392 Code 713 funds, 
$237,871 contributed funds, and $174,392 non-Federal contribution 
in kind for recreation facilities. 
26 Includes $1,185 Code 711 funds, $869,158 Code 713 funds, 
$7,797,604 contributed funds and $869,158 non-Federal contribution 
in kind for recreation facilities. 
27 Includes $54,460 from Productive Employment Appropriation 
Act (PL 98-8) of 1983. 
28 Includes $21,897 public works acceleration executive 1963 
funds and $2,594,377 Code 711 funds. 
29 Includes $21,897 public works acceleration executive 1963 
funds and $2,592,438 Code 711 funds. 
30 Includes $204,920 Special Recreation Use Fees, $52,000 
Supplemental Funds, and $141,675 "maintenance and operation 
of dams and other improvements of navigable water." 
1 Includes $20,568,369 contributed funds. 
32 Includes $20,221,129 contributed funds. 
SIncludes $196,306 public works acceleration executive 1963 
funds, $867,396 Code 711 funds, $22,612 Code 713 funds, and 
$22,612 contributed funds. 
4 Includes $236,640 Special Recreation Use Fees and 
$214,675 under "maintenance and operation of dams and other 
improvements of navigable water." 
* Includes $315,549 Code 713 funds, $170,697 contributed 
funds and $315,549 non-Federal contribution in kind for recreation 
facilities. 
36 Includes $315,549 Code 713 funds, $163,867 contributed 
funds and $315,549 non-Federal contribution in kind for recreation 
facilities. 
27 Includes $3,528,831 contributed funds. 
8 Includes $2,928,803 contributed funds. 
39 Includes $529,361 Code 713 funds, $50,000 contributed 
funds, $529,361 non-Federal contribution in kind for recreation 
facilities, and $520,800 non-Federal cost for sewer relocation and 
dam. 
40 Includes $58,571 for preconstruction planning, engineering 
and design completed before FY 1953. 
16-16

LOUISVILLE, KY. DISTRICT 
TABLE 16-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
GREEN AND BARREN RIVERS, KY (See Section 2 of Text) 
Purchase of original improvement 
Construction of Lock 2, Green River 
Construction of Lock 5, Green River 
Construction of Lock 6, Green River 
Appropriated $5,000 for continuing improvements of Green 
River above mouth of Big Barren River, with provision "That the 
Secretary of War may, in his discretion, expend such portion of 
said amount as may be necessary for removal of snags in 
Nolin River" 
Construct new Lock 1 and new Lock and Dam 2, Green River 
Construct new locks at Dam 5, Green River and Dam 1, 
Barren River; modification of Dam 5, Green River, 
widens bends in Bear Creek, KY 
Operation and care of locks and dams with War Department 
Appropriations for rivers and harbors 
Improvement of Nolin River 
Channel enlargement of lower 103 miles of Green River 
Recovation of authorities for improvement of 
Bear Creek and Nolin River 
OHIO RIVER BASIN (Louisville Dist.) (See Section 24 of Text) 
Aug 28, 1937 Construct levee, floodwalls, and drainage structures for protection 
of cities and towns in Ohio River Basin, projects to be selected 
by Chief of Engineers with approval of Secretary of War, at a cost 
not to exceed $24,877,000 for construction 
Jun 28, 1938 Approved general comprehensive plan for flood control and other 
purposes in Ohio River Basin as may be advisable in discretion 
of Secretary of War and Chief of Engineers, and for initiation 
and partial accomplishment of plan, authorized $75 million for 
reservoirs and $50.3 million for local protection works, individual 
projects to be selected and approved by Chief of Engineers subject 
to provision that authorization shall include diversion of Cache River 
above Cairo, Illinois, and protection of area north of Cairo 
drainage district by levees at an estimated cost of $2 million 
Aug 18, 1941 Additional $45 million for further prosecution of comprehensive 
plan for Ohio River Basin 
Dec 22, 1944 Additional $70 million for further prosecution of comprehensive 
plan for Ohio River Basin, including plan of improvement for 
flood control and other purposes in Kentucky River Basin 
Flood protection works at Taylorsville, Kentucky at an 
estimated cost of $129,350 
Channel improvement of lower Rough River and Barnett Creek 
at an estimated cost of $360,000 
Jul 24, 1946 Additional $125 million for further prosecution of comprehensive 
plan, including plan of improvement for flood control in 
Wabash River Basin, Illinois and Indiana, at an estimated cost 
of $9,629,000 
Also, West Fork of Mill Creek at an estimated cost of $1,527,000. 
May 17, 1950 Additional $100 million for prosecution of comprehensive plan 
for Ohio River Basin, including necessary bank stabilization 
measures at New Harmony Bridge, Indiana, at an estimated 
cost of $500,000 
Jul 3, 1958 Flood control Act of 1958 modified comprehensive plan to provide 
for Monroe Reservoir on Salt Creek, White River Basin, Indiana, 
at an estimated cost to the United States of $4,350,000; cost to 
local interests, $5,141,000 
Oct 23, 1962 Flood Control Act of 1962 deleted Jessamine Creek Reservoir 
on Kentucky River, Kentucky, from comprehensive plan for 
Ohio River Basin 
Dec 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Jun 18, 1965 Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin 
May 12, 1967 Additional $38 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Aug 13, 1968 Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Aug 11, 1888 
Mar 3, 18931 
Jul 13, 1892 
Jul 13, 1902 
Mar 3, 19052 
Mar 3, 1909 
Jul 3, 19302 
Jun 26, 1934$ 
Aug 30, 19352 
Sep 3, 1954 
16-17 
H. Ex. Doc 111, 49th Cong., 
2d Sess., Annual Report 
1887, p. 1903 
Annual Report, 1891, p. 2 4 3 9 
Annual Report, 1891, p. 2 4 7 8 
S. Doc. 82, 83d Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 2, 71st Cong., 1st Session, 
and H. Doc. 685, 69th Cong., 
2d Session 
H.D. 480, 72d Congress, 2d Sess. 
S.D. 82, 83d Congress, 2d Sess. 
Flood Control Committee 
Document 1, 75th Congress., 
1st Session 
Flood Control Committee 
Document 1, 75th Cong., 
1st Session 
H. Doc. 504, 78th Congress, 
2d Session 
S.D. 105, 78th Congress, 
1st Session 
H. D. 535, 78th Congress, 
2d Session 
H. D. 197, 80th Congress, 
1st Session 
H.D.198, 80th Congress, 1st Sess 
H. D. 192, 85th Congress, 
1st Session 
H. D. 423, 87th Congress, 
2d Session 
Public Law 88-253, 88th Cong., 
1st Session 
Public Law 8942, 89th Cong. 
1st Session 
Public Law 90-17, 90th Cong., 
1st Session 
Public Law 90-483, 90th Cong., 
2d Session

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-B 
CONTINUED 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
OHIO RIVER BASIN (Louisville Dist.) (Cont'd.) 
Jun 19, 1970 Additional $69 million for further prosecution of comprehen- Public Law 91-282, 91st Congress, 
sive plan for Ohio River Basin 2d Session 
Mar 7, 1974 Additional $120 million for further prosecution of comprehen- Public Law 93-251, 93rd Congress, 
sive plan for Ohio River Basin 2d Session 
Mar 7, 1974 Fifty-four local protection projects and one reservoir project in Public Law 93-251, 93rd Congress, 
comprehensive plan for Ohio River Basin were deauthorized 2d Session 
August 5, 1977, under Section 12, Water Resources 
Development Act of 1974 
Two additional local protection projects in comprehensive 
plan for Ohio River Basin were deauthorized November 6, 
1977, under Section 12, Water Resources Development 
Act of 1974 
WABASH RIVER BASIN (See Section 29 of Text) 
Aug 13, 1968 Construction of five multiple purpose reservoirs and one S.D. 96, 90th Congress, 2d Session 
local protection project in Wabash River Basin, IL & IN, with 
proviso that construction of Big Walnut Lake, IN, project 
must be approved by the President. Authorization of $50 
million for initiation and partial accomplishment of project. 
Dec 29, 1981 Two multiple purpose reservoirs in Wabash River Basin were Public Law 97-128, 97th Congress, 
deauthorized 2d Session 
MIAMI RIVER BASIN, PLEASANT RUN, VICINITY 
FAIRFIELD, OH. 
Nov 17, 1986 Three dry bed reservoirs and a Channel Improvement Public Law 97-128, 97th Congress, 
was authorized in Section 401 of The Water Resource 2nd Session 
Development Act of 1986. 
HAZARD; KENTUCKY 
Nov 17, 1988 Approximately 6 miles of Channel Improvement Public Law 100-676, 100th 
was authorized in Section 3 of the Water Resources Congress, 2nd Session 
Development Act of 1988. 
1 Deficiency act. 
2 Authorization for Nolin River and Bear Creek revoked by Act 
of Sep. 3, 1954. 
a Permanent Appropriations Repeal Act. 
TABLE 16-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost to Sep 30, 1989 
Full Report 
See Annual Operation and 
Name of Project Status Report Construction Maintenance 
Licking River 
Rough River, KY 
Tradewater River, KY 
White River, IN 
Completed 
Completed 
Completed 
Completed 
1901 
1951 
1858 
1909 
$ 13,045 
105,500 
18,568 
119,312 
$ 
101,196 
33,331 
16-18

TABLE 16-E 
LOUISVILLE, KY. DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report 
See Annual 
Project and Status Report For 
Cost to Sep 30, 1989 
Construction 
Operation and 
Maintenance 
Local Protection: 
Completed: 
Boone County, KY (Ohio River, Rabbit Hash) 
Brevoort Levee, IN (Wabash River) 
Brookport, IL 
Cannelton, IN 
Canoe Creek, Henderson, KY2 
Chaplin River, Perryville, KY2 
Cincinnati, OH 
Covington, KY 
Dayton, KY 
Delphi, IN (Wabash River) 
England Pond Levee, IL (Wabash River) 
English, IN (Little Blue Rivera 
Frankfort, KY (North Frankfort) (Kentucky River 8 
Gill Township Levee, IN (Wabash River) 
Golconda, IL 
Grassy Creek, Jackson County, IN 
(Muscatatuck River) 
Harrisburg, IL 
Hawesville, KY 
Indianapolis, IN (Fall Creek Section) 
(White River) 
Indian Creek, Corydon, IN2 
Jackson, KY (Kentucky River) 
Jeffersonville-Clarksville, IN 
Lawrenceburg, IN 
Lebanon Junction, KY (Salt River)a 
Levee Unit No. 5, Wabash River, IN 
Levee Unit 8, IN (White River) 
Louisville, KY4 
Lyford Levee Unit, IN (Wabash River) 
Mason J. Niblack Levee, IN (Wabash Rivers 
Mill Creek, Jefferson County, KY2 
Mount Carmel, IL (Wabash River) 
Muncie, IN (White River) 
Neon-Fleming, KY (Kentucky River) 
New Albany, IN 
New Harmony Bridge, IL & IN (Wabash River) ' 
Newburgh, IN (Ohio River)6 
Newport, KY 
Paducah, KY 
Panther Creek, KY (Green River)a 
Portland, IN (Salamonie River)a 
Reevesville, IL (Cache River) 
Rochester & McCleary's Bluff Levee, IL 
(Wabash River) 
Rosiclare, IL 
Saline River & Tribs, IL 
Shawneetown, IL7 
Sturgis, KY 
Taylorsville, KY (Salt River) 
Tell City, IN 
Terre Haute (Conover Levee), IN (Wabash River)7 
Town Creek, Harrodsburg, KY2 
Triplett Creek, Morehead, KY (Licking Rivers 
Uniontown, KY 
Vincennes, IN (Wabash River)7 
West Terre Haute, IN (Wabash River) 
Active: 
Frankfort, KY (South Frankfort) (Kentucky River)3 * 
Grayville, IL 
Hazard, KY 
Holes Creek, West Carrollton, Ohio9 (Great Miami River) 
Louisville, KY 
Miami River Basin, Pleasant Run, Vicinity Fairfield, OH 
(Great Miami River) 
Russell & Allison Levee, IL (Wabash River) 
Salyersville, KY (Licking River) 
1977 
1954 
1958 
1959 
1957 
1965 
1987 
1953 
1972 
1965 
1979 
1948 
1960 
1953 
1952 
1955 
1953 
1964 
1957 
1959 
1953 
1967 
1987 
1952 
1975 
1944 
1987 
1973 
1972 
1956 
1963 
1957 
1959 
1974 
1959 
1959 
1970 
1962 
1954 
1972 
1954 
1981 
1972 
1952 
1956 
1965 
1967 
1972 
1956 
1964 
1977 
1979 
1946 
$ 392,443 
1,240,299 
597,493 
2,068,391 
1,206,852 
832,700 
10,150,935 
7,862,937 
13,177,345 
144,563 
734,498 
372,353 
2,960,970 
561,200 
565,333 
70,304 
870,015 
969,318 
1,788,840 
300,143 
130,952 
4,226,361 
2,473,414 
130,417 
7,440,987 
700,534 
26,721,438 
267,391 
5,892,329 
292,710 
1,980,675 
887,835 
86,532 
5,375,471 
297,624 
52,061 
7,512,987 
4,761,551 
254,031 
237,657 
600,300 
1,079,236 
622,544 
7,826,219 
91,000 
1,826,778 
378,050 
932,229 
14,913 
56,505 
893,094 
1,070,926 
3,308,941 
1,095,704 
52,088 
272,750 
16-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-E 
CONTINUED 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1989 
Full Report 
See Annual Operation and 
Project and Status' Report For Construction Maintenance 
Inactive: 
Frankfort, KY (Benson Creek) (Kentucky River) 1979 - - 
Greenfield Bayou Levee, IN (Wabash River) 1979 157,935 - 
Indianapolis, IN (Warfleigh Section) 
(White River) 1976 153,410 - 
Island Levee, IN (Wabash River) 1979 355,963 - 
Lewisport, KY - - - 
New Harmony Bridge, IL & IN (Wabash River)' 1959 - - 
Newport-Wilder, KY - - - 
Owensboro, KY - - - 
Salyersville, KY (Licking River) 1946 12,000 - 
Smithland, KY - - - 
Vincennes, IL (Wabash River) 1964 - - 
West Point, KY - 4,490 - 
Reservoirs: 
Active: 
Camp Ground Lake, KY (Salt River) 1983 235,615- 
Inactive: 
Big Pine Lake, IN (Wabash River) 1977 1,270,590 - 
Big Walnut Lake, IN (Wabash River) 1980 1,009,188 - 
Booneville Lake, KY (Kentucky River) 1976 1,038,595 - 
Downeyville Lake, IN (Wabash River) - - - 
Eagle Creek Lake, KY 1975 702,471 - 
Falmouth Lake, KY (Licking River) 1981 944,386 - 
Lafayette Lake, IN (Wabash River) 1977 1,200,920 - 
Louisville Lake, IL (Wabash River) 1983 2,355,395 - 
Mining City Lake, KY (Green River) - 350,474 - 
Red River Lake, KY (Kentucky River) 1976 1,794,308 - 
1 All projects are on Ohio River unless otherwise noted. 
2 Authorized by Chief of Engineers under Section 205, 1948 
Flood Control Act, as amended. 
g Cost includes $161,098 cash contribution consisting of 
$105,118 from the City of Frankfort, KY and $55,980 from the 
Commonwealth of Kentucky. 
' Cost includes $1,716,301 cash contribution from City of 
Louisville, KY. 
a Cost shown are for Levee and pump plants. 
6 The Water Resources Development Act of 1974 modified the 
Newburgh Locks & Dam project to include the bank protection 
works at Newburgh, IN. 
Partially completed to form a useful unit. Remaining portion 
of project deauthorized. 
8 Partially completed to form a useful unit. Remaining portions 
of project are active and inactive. 
' Advance Engineering and Design funded with General 
Investigations Appropriation. 
16-20

LOUISVILLE, KY. DISTRICT 
TABLE 16-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Flood Control - Local Protection 
Adams Levee, IN (Wabash River) - 1978 $ -- 
Alton, IN - 1977-- 
Anderson, IN (White River) 1940 1986 5,724- 
Aurora, IN - 1977 35,420- 
Bellevue KY- 1977 19,023- 
Bonpas Creek, IL (Wabash River) - 1981 - - 
Bromley, KY - 1977-- 
California (Cincinnati) OH - 1977 16,465- 
Carrollton, KY - 1977 9,713- 
Caseyville, KY - 1986 - - 
Cave-in-Rock, IL - 1977 - - 
Cincinnati, OH (Unit 2) - 1977 - - 
Cincinnati, OH (Unit 4) - 1977 - - 
Cleves, OH - 1977 6,343- 
Clinton, IN - 1977 6,848- 
Cloverport, KY - 1986 - - 
Concordia, KY - 1986 - - 
Deer Creek, Prairie, Levee, IN - 1977 - - 
Derby, IN - 1977 - - 
Elizabethtown,, IL - 1977 - - 
Fletcher & Sunshine Gardens Levee, IN - 1977 3,361- 
Grandview, IN - 1977 8,497- 
Honey Creek Levee, IN - 1977 - - 
Leavenworth, IN - 1977 - - 
Levee Unit 1, Eel River, IN - 1977 - - 
Levee Unit 2, Eel River, IN - 1977 - - 
Levee Unit 2, East Fork White River, IN - 1977 - - 
Levee Unit 3, East Fork White River, IN 1938 1977 275- 
Levee Unit 1, IL (Wabash River) 1973 1986 60,000- 
Levee Unit 1, Little Wabash River, IL - 1977 - - 
Levee Unit 2, Little Wabash River, IL - 1977 - - 
Levee Unit 2, Wabash River, IL - 1977 - - 
Levee Units 3 and 4, Wabash River, IL 1938 1977 216- 
Levee Unit 6, Wabash River, IL - 1977 9,922- 
Levee Unit 17, Wabash River Basin, IN - 1977 - - 
Levee Unit 1, White River, IN - 1977 - - 
Levee Unit 7, White River, IN - 1977 - - 
Levee Unit 9, White River, IN - 1977 - - 
Levee Unit 10, White River, IN - 1977 - - 
Louisville, KY (Partial) - 1986 - - 
Ludlow, KY - 1977 14,503- 
Madison, IN - 1977 - - 
Mauckport, IN - 1977 - - 
Marion, IN (Wabash River) 1979 1986 209,975- 
McGinnis Levee, IN 1950 1977 71,049- 
Metropolis, IL - 1986 10,575- 
Milton, KY -1977 - - 
Moscow, OH - 1977 
New Amsterdam, IN - 1977 
New Harmony, IN - 1977 
New Richmond, OH - 1977 7,104 
Orleans, IN 1972 1977 13,158 
Patriot, IN - 1977 
Prestonville , KY - 1977 
Raccoon Creek Levee, IN - 1977 
Rising Sun, IN - 1977 
Rockport, IN - 1977 
Rome, IN - 1977 
Shawneetown, IL - 1986 25,367 
Shoals, IN (East Fork White River) 1938 1977 
Shufflebarger Levee, IN 1950 1977 64,487- 
Sugar Creek Levee, IN 1961 1977 28,061- 
Terre Haute, IN - 1977 - - 
Tolu, KY - 1986 - - 
Tri Pond Levee, IL 1972 1977 65,510- 
Troy, IN 1977 - - 
16-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-G 
CONTINUED 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Flood Control- Local Protection 
Utica, IN 
Vevay, IN 
Vincennes, IN (Partial) 
Westport, KY 
Flood Control- Reservoirs 
Big Blue Lake, IN 
Clifty Creek Lake, IN 
Helm Lake, IL 
Lincoln Lake, IL 
Metamora Lake, IN 
1964 
1980 
1979 
1976 
1979 
1978 
1977 
1986 
1977 
1981 
1981 
1981 
1981 
1977 
1,079,867 
1,016,358 
41,616 
1,331,844 
16-22

TABLE 16-H NAVIGATION LOCKS AND DAMS 
PRINCIPAL FEATURES - GREEN & BARREN RIVERS 
AND KENTUCKY RIVER NAVIGATION SYSTEMS 
Lock Dimensions 
Miles Greatest Length 
Lock above Available Upper Depth of Year 
and Mouth of Distance from Width of For Full Normal Pool Miter Sills Character of Percent Opened to Cost of 
Dam River Nearest Town Chamber Width Lift Elevation Upper Lower Foundation Complete Navigation Lock and Dam 
(feet) (feet) (feet msl) (feet) (feet) 
CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER - For report on this improvement see this heading under Ohio River. 
GREEN AND BARREN RIVERS, KY (See Section 2 of Text) 
Green 
River 
New 1 9.1 Spottsville, KY 84.0 600.0 11.8' 349.1 12.1 11.3 Shale and Coal 100 1956' $5,101,978' 
New 2 63.1 0.3 miles below 84.0 600.0 14.3 363.4 15.0 11.7 Shale 100 1956' 4,799,271 
Calhoun, KY 
3 108.5 0.3 miles below 35.8 137.5 17.0 380.4 7.3 5.6 Rock 100 1836' 121,377 
Rochester, KY 
4 149.0 Woodbury, KY 35.8 138.0 16.4 396.8 7.1 6.5 Rock 100 1839' 125,718 
5 168.1 0.3 miles below 56.0 360.0 15.2 412.0' 12.0 9.3 Piles and Rock 100 1905' 1,020,868" 
Glenmore, KY 
6 181.7 2.8 miles above 36.0 145.0 9.2 421.1 8.0 8.8 Gravel 100 1905' 168,415 
Brownsville, KY 
Barren Barren 
River River 
1 15.0" 0.3 miles above 56.0 360.0 15.2 412.0 12.0 9.3 100 1934 871,565" 
Greencastle, KY 
KENTUCKY RIVER, KY (See Section 3 of Text) Kentucky 
River 
Kentucky 
River 
1 4.0 3.8 miles above 38.0 145.0 8.2 430.0 8.2" 14.8 Rock and Clay 100 1839" 
Carrollton, KY 
2 31.0 Lockport, KY 38.0 145.0 13.9 443.9 7.6 6.1 Rock 100 1839" . 
3 42.0 Gest, KY 38.0 145.0 13.2 457.1 8.6 6.5 Rock 100 1844" 1,350,385" 
4 65.0 1.0 mile below 38.0 145.0 13.2 470.3 6.4 7.4 Rock 100 1844" 
Frankfort, KY 
5 82.2 2.8 miles below 38.0 145.0 15.0 485.3 10.0 6.5 Rock 100 1844" - 
Tyrone, KY 
6 96.2 21.6 miles below 52.0 147.0 14.0 499.3 9.4 6.4 Rock and Piles 100 1894" 314,847 
High Bridge, KY 
7 117.0 0.8 mile below 52.0 147.0 15.3 514.6 9.1 6.9 Rock 100 1897" 290,788 
High Bridge, KY 
8 139.9 4.7 miles above 52.0 146.0 18.7 533.6 10.6 6.0 Rock 100 1900" 275,463 
Camp Nelson, KY 
9 157.5 Valley View, KY 52.0 148.0 17.3 550.6 10.0 6.6 Rock 100 1907" 237,646 
10 176.4 1.0 mile below 52.0 148.0 17.0 567.6 9.0 6.0 Rock 100 1907" 221,500 
Ford, KY 
11 201.0 17.2 miles below 52.0 148.0 18.0 585.6 10.0 6.0 Rock 100 1906" 296,593 
Irvine, KY 
12 220.0 Ravenna, KY 52.0 148.0 17.0 602.6 9.6 6.0 Rock 100 1910" 425,693 
13 239.9 2.2 miles below 52.0 148.0 18.0 620.6 9.6 6.0 Rock 100 1915" 461,476 
Willow, KY 
14 249.0 Heidelberg, KY 52.0 148.0 17.0 637.6 8.6 6.0 Rock 100 1917" 392,902 
' At normal pool Dam 48, Ohio River, Elev. 337.3, Green 
River datum (Elev. 338.0 Ohio River datum). 
' New Lock 1 placed in operation May 25, 1956; old Dam 
1, completed 1835-40, replaced with new cellular concrete 
masonry dam constructed 1970 71 with O&M General funds at 
cost of $822,000. 
SDoes not include $179,110 cost of old Lock and Dam 1. 
SNew Lock and Dam 2, placed in operation June 18, 1956. 
s Does not include $295,696 cost of old Lock and Dam 2. 
* Operation discontinued September 30, 1981. 
' Breaching of dam on May 24, 1965, stopped through traf 
fic to Bowling Green, KY. 
SWith movable A frame crest 3 feet high. 
SOperation discontinued Aug. 1, 1951. 
O Does not include $179,434 cost of old Lock and Dam 5. 
n Distance from mouth of Green River is 164.5 miles. Lock 
closed to navigation as the result of loss of pool at Green River 
Lock and Dam 4 on May 24, 1965. 
1 Includes $729,269 for new large lock completed in 1934. 
" At normal pool McAlpine Dam, Ohio River elev. 421.8 Kentucky 
River datum (Elev. 420 Ohio River datum). 
" Reconstruction completed by United States in 1882. 
' Built by State of Kentucky. Cost given is for repairs by 
United States to Locks and Dams 1 through 5. Original construction 
costs to State were: L&D 1, $220,300; L&D 2, $151,983; 
L&D 3, $135,857; L&D 4, $131,607; and L&D 5, $137,436. 
* Lock was closed to traffic and placed in caretaker status 
in September 1982.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-I OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section 24 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost" 
Project and Status1 Construction Federal Non-Federal Total 
Completed: 
Barnett Creek, KY (Rough River)8 " 
Brookport, IL5 6 
Cannelton, IN5 7 
Cincinnati, OH 5 8 
Covington, KY 5 9 
Dayton, KY 
Delphi, IN (Wabash River)5 
1o 
England Pond Levee, IL (Wabash River)11 
Frankfort, KY (Kentucky River)5 
North Frankfort 5 
Golconda, IL5 12 
Harrisburg, IL5 10 
Hawesville, KY 5 13 
Jackson, KY (Kentucky River)5 8 
Jeffersonville-Clarksville, IN 7 
Lawrenceburg, IN5 
Louisville, KY5 
14 
Mason J. Niblack Levee, IN 
(Wabash River)4 5 
New. Albany, IN 5 8 
New Harmony Bridge, IL and IN 
(Wabash River)5 7 
Newport, KY5 ' 
Paducah, KY5 7 
Reevesville, IL (Cache River)" 15 
Rochester and McCleary's Bluff Levee, IL 
(Wabash River)11 
Rough River, KY3 4 
Sturgis, KY (Tradewater River)11 
Taylorsville, KY (Salt River)5 
16 
Tell City, IN5 14 
Uniontown, KY5 
17 
Vincennes, IN (Wabash River)5 
(completed portion) 
West Terre Haute, IN (Wabash River) 
'Active: 
Evansville, IN 4 
Frankfort, KY (Kentucky River)5 
South Frankfort 5 
Russell & Allison Levee, IL 
(Wabash River)9 
Inactive: 
Frankfort, KY (Kentucky River)a 
Benson Creek5 
Greenfield Bayou Levee, IN (Wabash River)5 
Island Levee, IN (Wabash Rivera) 
Lewisport, KY 5 
New Harmony Bridge, IL and IN 
(Wabash River) ' 
Owensboro, KY5 
Smithland, KY5 
Wilders, KY 
Channel improvement 
Wall and levee 
Wall and levee 
Wall and barrier dam 
Wall and levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Cutoff channel 
Wall and levee 
Wall and levee 
Wall and levee 
Levee and pump plants 
Wall and levee 
Bank Protection 
Wall and levee 
Wall and levee 
Levee 
Levee 
Channel improvement 
Levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Wall 
Levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Bank protection 
Wall and levee 
Wall and levee 
Wall and levee 
597,493 
2,068,391 
10,150,935 
7,862,937 
13,117,345 
144,563 
734,498 
2,960,970 
565,333 
870,015 
969,318 
130,952 
4,226,361 
2,473,414 
25,005,137 
4,337,617 
5,375,471 
297,624 
7,512,987 
4,761,551 
600,300 
1,079,236 
1,826,778 
378,050 
932,229 
1,070,926 
3,308,941 
1,095,704 
8,500 
29,105 
1,309,146 
1,051,102 
2,013,000 
17,164 
107,000 
272,100 
10,900 
20,000 
42,593 
3,000 
590,888 
284,725 
1,716,301 
p 
605,993 
2,097,496 
11,460,081 
8,914,039 
15,130,345 
161,727 
841,498 
3,233,070 
576,233 
890,015 
1,011,911 
133,952 
4,817,249 
2,758,139 
26,721,438 
109,200 4,446,817 
740,000 6,115,471 
298,506 
232,000 
40,000 
100,000 
x93,000 
63,309 
32,707 
72,153 
285,000 
297,624 
7,811,493 
4,993,551 
640,300 
1,179,236 
1,919,778 
441,359 
964,936 
1,143,079 
3,593,941 
150,000 1,245,704 
51,100,000 5,500,000 56,600,00029 
6,122,000 2,041,000 8,163,00018 
19,400,000 2,340,000 21,740,00021 
3,340,000 
4,600,000 
4,630,000 
610,000 
664,376 
886,000 
864,000 
10,800,000 
1,150,000 
1,087,000 
528,000 
243,000 
99,000 
195,000 
414,000 
959,000 
4,490,00022 
5,687,00023 
5,158,00023 
853,00024 
763,37625 
1,081,000 
1,278,000 
11,759,00026 
16-24

LOUISVILLE, KY. DISTRICT 
TABLE 16-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 24 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost' 
Project and Status' Construction Federal Non-Federal Total 
Deauthorized August 5, 1977 under 
Section 12, Water Resources Development 
Act of 1971 (Public Law 93-251): 
Alton, IN 
Bellevue, KY 
Bromley, KY 
Carrollton, KY 
Cave-in-Rock, IL 
Cincinnati, OH (Unit 2) 
Cincinnati, OH (Unit 4) 
Cleves, OH 
Clinton, IN (Wabash River) 
Deer Creek Prairie Levee, IN 
(Wabash River) 
Derby, IN 
Elizabethtown, IL 
Fletcher and Sunshine Gardens Levee, 
IN (Wabash River) 
Grandview, IN 
Honey Creek Levee, IN 
Leavenworth, IN 
Levee Unit 1, Eel River, IN 
Levee Unit 2, Eel River, IN 
Levee Unit 1, Little Wabash River, IL 
Levee Unit 2, Little Wabash River, IL 
Levee Unit 6, Wabash River, IL 
Levee Unit 17, IN 
Levee Unit 1, White River, IN 
Levee Unit 2, White River, IN 
Levee Unit 7, White River, IN 
Ludlow, KY 
Madison, IN 
Mauckport, IN 
McGinnis Levee, IN (Wabash River) 
Milton, KY 
Moscow, OH 
New Amsterdam, IN 
New Harmony, IN (Wabash River) 
New Richmond, OH 
Patriot, IN 
Prestonville, KY 
Raccoon Levee, IN (Wabash River) 
Rising Sun, IN 
Rockport, IN 
Rome, IN 
Shufflebarger Levee, IN 
(Wabash River) 
Sugar Creek Levee, IN 
(Wabash River) 
Tri-Pond Levee, IL (Wabash River) 
Troy, IN 
Vevay, IN 
Westport, KY 
Levee 
Wall and Levee 
Wall and Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall 
Levee 
Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Wall 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Levee 
Wall and Levee 
Wall and Levee 
Levee 
Levee 
Levee 
Levee 
Wall and Levee 
Levee 
Wall 
$ 255,000 
1,570,000 
1,250,000 
2,220,000 
661,000 
16,800,000 
14,900,000 
1,240,000 
77,000 
213,000 
553,000 
559,000 
548,000 
580,000 
653,000 
1,470,000 
204,000 
2,090,000 
2,850,000 
3,410,000 
1,160,000 
1,580,000 
2,180,000 
724,000 
1,490,000 
2,540,000 
3,820,000 
506,000 
1,820,000 
2,480,000 
1,170,000 
476,000 
616,000 
3,200,000 
753,000 
1,710,000 
426,000 
896,000 
466,000 
359,000 
2,380,000 
418,000 
2,050,000 
502,000 
1,170,000 
1,610,000 
$ 40,000 
400,000 
925,000 
97,000 
125,000 
2,900,000 
621,000 
67,000 
9,000 
10,000 
67,000 
153,000 
26,000 
133,000 
32,000 
266,000 
40,000 
715,000 
164,000 
136,000 
56,000 
118,000 
116,000 
73,000 
88,000 
745,000 
360,000 
105,000 
104,000 
41,000 
372,000 
13,000 
25,000 
720,000 
372,000 
55,000 
37,000 
280,000 
133,000 
67,000 
90,000 
29,000 
191,000 
133,000 
146,000 
41,000 
$ 295,000 
1,970,000 
2,175,000 
2,317,000 
786,000 
19,700,000 
15,521,000 
1,307,000 
86,000 
223,000"4 
620,000 
712,000 
574,000" 
713,000 
685,000 
1,736,000 
244,000 
2,805,000 
3,014,000' 7 
3,546,0002" 
1,216,000 
1,698,00028 
2,296,00027 
797,000' 
1,578,00027 
3,285,000 
4,180,000 
611,000 
1,924,000 
2,521,000 
1,542,000 
489,000 
641,000 
3,920,000 
1,125,000 
1,765,000 
463,000"4 
1,176,000 
599,000 
426,000 
2,470,000 
447,000" 
2,241,0002" 
635,000 
1,316,000 
1,651,000 
16-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FY 1989 
TABLE 16-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL !COST OF. BASIN PLAN 
(FLOOD CONTROL) 
(See Section 24 of Text) 
LOCAL PROTECTION 
Type of Estimated Cost' 
Project and Status Construction Federal Non-Federal Total 
Deauthorized November 6, 1977 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Aurora, IN Wall and Levee $4,300,000 $1,190,000 $5,490,000 
California (Cincinnati), OH Wall and Levee 1,750,000 720,000 2,470,000 
Deauthorized October 3, 1978 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Adams Levee, IN (Wabash River). Levee 292,000 14,000 306,00027 
Utica, IN5 Levee 1,570,000 120,000 1,690,000 
Deauthorized May 6, 1981 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Bonpas Creek, IL (Wabash River : Channel 1,080,000 630,000 1,710,00028 
improvement 
Deauthorized November 17, 1986 under 
Section 12, Water Resources Development 
Act of 1974 (Public Law 93-251) 
Caseyville, KY5 Levee 396,000 35,000 431,000 
Cloverport, KY5 Wall and Levee 728,000 193,000 921,000 
Concordia, KY5 Levee 590,000 55,000 645,000 
Metropolis, IL5 Wall and Levee 3,070,000 431,000 3,501,000 
Shawneetown, IL5 Wall and Levee 1,810,000 361,000 2,171,000 
Tolu, KY5 Levee 303,000 35,000 338,000 
Vincennes, IN (Wabash River)5 Wall and Levee 3,340,000 - 3,340,00028 
(Uncompleted Portion) 
West Point, KY5 Wall and Levee 3,283,000 400,000 3,683,000" 
1 All projects are on an Ohio River unless otherwise noted. 
2 Latest cost estimate revision 1954 unless otherwise noted. 
* Part of Rough River Reservoir and.Channel Improvement 
Project, KY. 
4 Details of this project are in individual report. 
5 Also see "Other authorized flood control projects." 
6 See Annual Report for 1958 for details. 
r See Annual Report for 1959 for details. 
8 See Annual Report for 1957 for details. 
s See Annual Report for 1965 for details. 
1o See Annual Report for 1953 for details. 
n See Annual Report for 1972 for details. 
12 See Annual Report for 1960 for details. 
13 See Annual Report for 1955 for details. 
14 See Annual Report for 1962 for details. 
15 Substitute project for Belknap, Karnak, and Ullin, IL, complete. 
See Annual Report for 1954 for details: 
16 See Annual Report for 1952 for details. 
17 See Annual Report for 1956 for details. 
18 
19 
20 
21 
22 
23 
24 
25 
26 
27 
28 
29 
Latest cost estimate revision 1988. 
Latest cost estimate revision 1986. 
Latest cost estimate revision 1984. 
Latest cost estimate revision 1983. 
Latest cost estimate revision 1976. 
Latest cost estimate revision 1978. 
Latest cost estimate revision 1960. 
Latest cost estimate revision 1971. 
Latest cost estimate revision 1977. 
Latest cost estimate revision 1961. 
Latest cost estimate revision 1973. 
Latest cost estimate revision 1989. 
16-26

LOUISVILLE, KY. DISTRICT 
TABLE 16-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 24 of Text) 
RESERVOIRS 
Tributary Basin Estimated Cost' 
Reservoirs Status Stream Federal Non-Federal Total 
Great Miami River: 
Brookville Lake, IN' 
Metamora Lake, IN 
Green River: 
Barren River Lake, KY1 
Green River Lake, KY2 
Mining City Lake, KY 
Nolin Lake, KY2 
Rough River Kentucky2 
Kentucky River 
Booneville Lake, KY 
Buckhorn Lake, KY2 
Carr Fork Lake, KY2 
Licking River 
Cave Run Lake, KY2 
Falmouth Lake, KY 
Little Miami River: 
Caesar Creek Lake, OH2 
William H. Harsha 
Lake, OH2 
Mill Creek: 
West Fork of 
Mill Creek Lake, OH2 
Wabash River: 
Cagles Mill Lake, IN 2 
Cecil M. Harden Lake, IN 2 
Monroe Lake, IN2 
Patoka Lake, IN2 
Complete 
Deauthorized 
Complete 
Complete 
Inactive 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
East Fork of Whitewater 
River 
West Fork of Whitewater 
River 
Barren River 
Green River 
Green River 
Nolin River 
Rough River 
South Fork of Kentucky 
River 
Middle Fork of Kentucky 
River 
North Fork of Kentucky 
River 
Licking River 
Licking River 
Caesar Creek 
East Fork of Little Miami 
River 
West Fork of Mill Creek 
Mill Creek 
Raccoon Creek 
Salt Creek 
Patoka River 
$37,918,888 
35,300,000 
27,371,299 
33,238,597 
69,100,000 
17,193,381 
10,620,389 
60,700,000 
11,766,206 
50,854,826 
114,826,300 
125,000,000 
$7,497,492$ 
108,418' 
223,7331$ 
22,612' 
$ 45,416,380 
35,300,0004 
27,479,717 
33,462,330 
69,100,0004 
17,193,381 
10,643,001 
60,700,000' 
11,766,206 
50,854,826 
114,826,3007 
125,000,000' 
62,893,882 5,037,000' 67,930,882 
55,230,000 3,485,840' 58,715,840 
3,622,302 1,100,16110 4,722,463 
4,263,184 
6,633,812 
7,902,827 
113,094' 
353,9955 
8,666,76211 
53,095,790 20,568,369 
4,376,278 
6,987,807 
16,569,589 
73,664,159 
Latest cost estimate revision 1989 unless otherwise noted. 
Details of this project given in individual report. 
Cash contributions for water supply storage. 
Latest cost estimate revision 1954. 
For Code 713 recreation development. 
Latest cost estimate revision 1975. 
Includes $35,213,000 United States Forest Service cost. 
Latest cost estimate revision 1979. 
Reimbursement for water supply storage. 
1o Includes $520,800 for non-Federal cost for sewer relocation 
and dam, $50,000 for contributed funds in fulfillment of project 
authorization, and $529,361 for Code 713 recreation 
development. 
1 Includes $7,797,604 cash contribution for storage for low-flow 
regulation and $869,158 for Code 713 recreation development. 
1i Includes $14,180,677 cash contribution for water supply 
storage, and $6,387,692 for initial recreation development. 
13 For $183,732 Code 713 recreation development and $40,001 
contributed funds. 
16-27 
Ti--~--~----.~1 l.-I----I-------. .-:i. r. --;T

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-J WABASH RIVER BASIN 
TOTAL COST OF BASIN PLAN: 
(FLOOD CONTROL) 
(See Section 29 of Text) 
Type of 
Construction Estimated Cost 
Project or Stream Status Federal Non-Federal Total 
LOCAL PROTECTION 
Marion, IN Wall and Levee Inactive $ 3,900,000 $ 854,000 $ 4,754,000' 
RESERVOIRS 
Big Blue Lake, IN Big Blue River Deauthorized 87,200,000 53,846,0008 141,046,0004 
Big Walnut Lake, IN Big Walnut Creek Inactive 81,800,000 45,069,000' 126,869,0004 
Downeyville Lake, IN Flatrock and Little 
Flatrock Rivers Inactive 74,200,000 64,448,000 138,648,000' 
Helm Lake, IN Skillet Fork Deauthorized 25,171,000 14,829,000' 40,000,0008 
Louisville, Lake, IL Little Wabash River Inactive 113,000,000 14,435,000' 127,435,00010 
i Latest cost revision 1984 unless otherwise noted. 
9 Latest cost estimate revision 1977. 
8 Includes $38,190,000 reimbursable by non-Federal interests 
for water supply and $15,656,000 reimbursable for initial recreation 
facilities. 
' Latest cost estimate revision 1979. 
a Includes $26,663,000 reimbursable by non-Federal interests 
for water supply and $18,406,000 reimbursable for initial recreation 
facilities. 
* Includes $53,084,000 reimbursable by non-Federal interests 
for water supply, $8,749,000 reimbursable for initial recreation 
facilities. 
' Includes $12,696,000 reimbursable by non-Federal interests 
for water supply and $2,133,000 for recreation facilities. 
8 Latest cost estimate revision 1975. 
* Includes $8,402,000 reimbursable by non-Federal interests 
for water supply and $6,033,000 reimbursable for initial recreation 
facilities. 
10 Latest cost estimate revision 1982. 
16-28

LOUISVILLE, KY. DISTRICT 
TABLE 16-K INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 32 of Text) 
Date of 
Local Protection Projects Inspection 
Brevoort Levee, IL May 1989 
Brookport, IL Nov 1988 
Cache River Levee, IL Nov 1988 
Cannelton, IN Nov 1988 
Cincinnati, OH May 1989 
Covington, KY Nov 1988 
Dayton, KY May 1989 
Delphi, IN Mar 1989 
England Pond Levee, IL May 1989 
Evansville, IN Jul 1989 
Frankfort, KY, North Frankfort Mar 1989 
Gill Township Levee, IN Mar 1989 
Golconda, IL Oct 1988 
Harrisburg, IL Oct 1988 
Hawesville, KY Nov 1988 
Indianapolis, IN Mar 1989 
Jeffersonville-Clarksville, IN Mar 1989 
Lawrenceburg, IN May 1989 
Lebanon Junction, KY Mar 1989 
Levee Unit No. 5, Wabash River, IN Sep 1989 
Levee Unit No. 8, Wabash River, IN Mar 1989 
Louisville, KY Aug 1989 
Lyford Levee, IN Apr 1989 
Mason J. Niblack Levee, IN May 1989 
Mt. Carmel, IL Sep 1989 
Muncie, IN Mar 1989 
Perryville, KY Aug 1989 
New Albany, IN Mar 1989 
Newport, KY Nov 1988 
Paducah, KY Nov 1988 
Reevesville, IL Nov 1988 
Rochester-McCleary's Bluff Levee, IL Sep 1989 
Rosiclare, IL Oct 1988 
Shawneetown, IL Oct 1988 
Sturgis, KY May 1989 
Taylorsville, KY Mar 1989 
Tell City, IN Nov 1988 
Terre Haute (Conover Levee), IN Apr 1989 
Uniontown, KY May 1989 
Vincennes, IN May 1989 
West Terre Haute, IN Apr 1989 
16-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 16-K INSPECTION OF COMPLETED 
CONTINUED FLOOD CONTROL PROJECTS 
(See Section 32 of Text) 
Dates of 
Channel Improvements Inspection 
Canoe Creek, Henderson, KY May 1989 
Cypress Creek, McLean County, KY Jul 1989 
Eel River, Brazil Waterworks, IN Apr 1989 
English, IN (Little Blue River) Jun 1989 
Grassy Creek, Jackson County, IN Sep 1985 
Harrodsburg, KY (Town Creek) Aug 1989 
Indian Creek, Corydon, IN Jul 1989 
Jackson, KY (North Fork Kentucky River) Jun 1989 
Lick Creek, Hartford City (Blackford County), IN Aug 1989 
Mill Creek, Jefferson County, KY Jul 1988 
Muscatatuck River, Crothersville, IN Sep 1986 
Neon-Fleming, KY (North Fork Kentucky River) Jun 1989 
Nicholasville (Town Fork) Vicinity, KY Aug 1989 
Panther Creek, Curdsville, KY Jul 1989 
Plum Creek, Spencer County, KY Aug 1986 
Portland, IN (Salamonie River) Mar 1989 
Rough River, Hartford, Ohio County, KY Jul 1989 
Salamonie River, Wells County, IN Mar 1989 
Saline River and Tributaries, IL Oct 1988 
Triplett Creek, Morehead, KY Jun 1989 
Troublesome Creek, Hindman, KY Jun 1989 
Wabash River, Adams County, IN Mar 1989 
Whitesburg, KY (North Fork Kentucky River) Jun 1989 
Bank Revetments 
East Fork White River, Brownstown (Jackson County) IN Mar 1989 
Eighteen Mile Island, Oldham Co., KY Jul 1988 
Great Miami River, Sidney, OH Mar 1988 
Green River, Calhoun, KY Jul 1989 
Licking River, Butler, KY Nov 1988 
Lusk Creek, Golconda, IL Oct 1988 
Little Miami River, Indian Hill, OH May 1989 
Little Miami River, Milford, OH May 1989 
Ohio River, Brandenburg, KY Jun 1989 
Ohio River, Cloverport, KY Jul 1989 
Ohio River, Daviess Co., KY Jul 1989 
Ohio River, Fort Massac State Park, IL Nov 1988 
Ohio River, Hawesville, KY Jul 1989 
Ohio River, Lewisport, KY Jul 1989 
Ohio River, Madison, IN Aug 1989 
Ohio River, Moscow, OH Nov 1988 
Ohio River, Mount Vernon, IN May 1989 
Ohio River, Newburgh, IN Jul 1989 
Ohio River, Ohio Street, Evansville, IN Jul 1989 
Ohio River, Otter Creek Park, KY Aug 1989 
Ohio River, Rabbit Hash, Boone Co., KY May 1989 
Ohio River, Rockport Landing, IN May 1989 
Ohio River, Sellersburg, IN Sep 1986 
Ohio River, SR 66, Cannelton, IN Nov 1988 
Ohio River, Troy, IN May 1989 
Ohio River, Upper River Rd., Jefferson Co., KY Jul 1988 
Ohio River, Vanderburg Co., IN Jun 1989 
Patoka River at Jasper, IN Mar 1989 
Patoka River, Winslow, IN Apr 1988 
Stoner Creek, North Middletown, KY Jun 1989 
Wabash River near Merom, IN Mar 1989 
Wabash River, New Harmony, IN Sep 1989 
White River, Petersburg (Pike Co.), IN Mar 1989 
Whitewater River, Levee Rd., near Brookville, IN May 1989 
WTP, Great Miami River, Ross, OH May 1989 
16-30

LOUISVILLE, KY. DISTRICT 
TABLE 16-L FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 34 of Text) 
Fiscal Year Cost 
Total 
Flood Control (Section 205): 
Canoe Creek at Henderson, KY5 $ 398 
Duck Creek, Elwood, IN2 .11,607 
Feather Creek, Clinton, IN2 73,016 
Kentucky River, Hyden, KY' 7,461 
Licking River, Salyersville, KY2 15,764 
Little Beaver Creek, Kettering, OH2 549 
Raccoon Creek, D & L Townships, IL1 15,661 
Red River, Clay City, KY' 24,945 
Sugar Creek, Bellbrook, OH2 38,459 
Whitewater River, Hagerstown, IN3 9,987 
Snagging and Clearing for Flood Control (Section 208): 
Salamonie River, Montpelier, IN3 8,607 
Emergency Bank Protection (Section 14): 
Indian Creek, Burton Road, Morgan Co, IN3 23,009 
Little Turtle Creek, Sullivan Co., IN3 18,980 
Miami River, Lake Isabella Park, OH3 8,975 
Ohio River, Brandenburg, KY' -656 
Ohio River, Owensboro, KY5 42,839 
Ohio River, Utica Pike, Clark Co., IN1 6,072 
S.F. Wildcat Creek, Rd 7E, Tippecanoe Co., IN3 20,698 
Wabash River, Little Road, Vigo Co., IN3 19,906 
Wabash River, West Rd., Vigo Co., IN3 17,130 
Whitewater River, Adar Grove, IN' 6,025 
1 Reconnaissance Study 
2 Detail Project Report 
3 Plans and Specifications 
4 Construction Funds Received 
5 Construction Completed 
16-31

HUNTINGTON, WV, DISTRICT * 
All cost and financial statements for projects are 
listed at the end of this chapter. All other tables are 
referenced in the text and also appear at the end of this 
chapter. 
The Huntington District includes central and 
southeastern Ohio, all of West Virginia except the 
northern panhandle and northeastern portion, the 
eastern portion of Kentucky, a portion of midwestern 
Virginia, a very small portion of midwestern Virginia, a 
very small portion of northwestern North Carolina, 
embraced in the drainage basin of the Ohio River and its 
tributaries from approximate river mile 127 (below 
Pittsburgh, PA) to approximate river mile 438, 
immediately upstream from Foster, KY. The drainage 
area of the Huntington District is approximately 44,914 
square miles. 
IMPROVEMENTS 
Navigation 
1. Construction of Locks and 
Dams on Ohio River ..................................... 17-2 
2. Kanawha River, WV ..................................... 17-2 
3. Open Channel Work, Ohio River ................. 17-2 
4. Other Authorized 
Navigation Projects .................................. 17-2 
Flood Control 
5. Alum Creek Lake, OH .................... .. 17-2 
6. Beech Fork Lake, WV .................................. 17-3 
7. Bluestone Lake, Ohio 
River Basin, WV ..................................... 17-3 
8. Burnsville Lake, Ohio 
River Basin, WV ..................................... 17-3 
9. Deer Creek Lake, 
Ohio River Basin, OH ................................... 17-3 
10. Delaware Lake, Ohio 
River Basin, OH ..................................... 17-4 
11. Dewey Lake, Ohio 
River Basin, KY .................................... 17-4 
12. Dillon Lake, Ohio 
River Basin, OH ............................................... 17-4 
13. East Lynn Lake, 
Ohio River Basin, WV ................................... 17-5 
14. Fishtrap Lake, Ohio River Basin, KY ............ 17-5 
15. Grayson Lake, KY ............................................ 17-5 
16. John W. Flannagan Dam and 
Reservoir, Ohio River Basin,VA ...................... 17-5 
17. Levisa and Tug Forks of the 
Big Sandy River and Cumberland 
River, KY, WV and VA ................................. 17-6 
18. Massillon, OH ..................................... 17-6 
19. Muskingum River Lakes, OH .......................... 17-6 
20. Newark, OH ..................................... 17-7 
21. North Branch of Kokosing 
River Lake, OH .................................... 17-7 
22. North Fork of Pound River Lake, VA ........... 17-8 
23. Ohio River Basin (Huntington District) ...... 17-8 
24. Paint Creek Lake, Ohio 
River Basin, Ohio ............................................. 17-8 
25. Paintsville Lake, KY ........................................ 17-8 
26. R.D. Bailey Lake, WV ................................... 17-9 
27. Roseville, OH .................................................... 17-9 
28. Summersville Lake, Ohio 
River Basin, WV ..................................... 17-9 
29. Sutton Lake, Ohio River Basin, WV ............ 17-9 
30. Tom Jenkins Dam, Ohio 
River Basin, OH ..................................... 17-10 
31. Yatesville Lake, KY ....................................... 17-10 
32. Inspection of Completed 
Flood Control Projects ................................. 17-10 
33. Flood Control Work Under 
Special Authorization .................................. 17-10 
General Investigations 
34. Surveys ..................................... 17-11 
35. Collection and Study of Basic Data ............ 17-11 
Tables 
Table 
Table 
Table 
17-A 
17-B 
17-C 
Table 17-D 
Table 17-E 
Table 
Table 
Table 
17-F 
17-G 
17-H 
Cost & Financial Statement ........ 17-12 
Authorization Legislation ........... 17-17 
Other Authorized 
Navigation Projects ..................... 17-20 
Not Applicable 
Other Authorized Flood 
Control Projects ............................ 17-21 
Not Applicable 
-Deauthorized Projects .................. 17-22 
Inspection of Flood 
Control Projects ............................ 17-23 
17-1 
Page Page

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON THE OHIO RIVER 
See this heading under Chapter 19- Ohio River 
2. KANAWHA RIVER, WV 
Location. The Kanawha River is approximately 97 
miles in length and is formed by the junction of the New 
and Gauley Rivers, a short distance above Kanawha 
Falls, WV, and flows generally northwesterly to the 
confluence with the Ohio River at Point Pleasant, WV. 
Previous projects. For details of previous projects 
see the Annual Reports for 1875,1915 and 1938. 
Existing project. The existing project consists of 
three navigation structures on the Kanawha River. 
London Locks and Dam are located approximately 83 
miles above the mouth of the Kanawha River and 
approximately two miles downstream from Montgomery, 
WV. Marmet Locks and Dam are located approximately 
68 miles above the mouth of the Kanawha River at 
Marmet, WV. Winfield Locks and Dam are located 
approximately 31 miles above the mouth of the Kanawha 
River at Winfield, WV. Each structure has twin locks 
with usable dimensions of 56 feet by 360 feet. Another 
structure is located on the Ohio River at approximate 
river mile 279 and approximately nine miles below 
Gallipolis, OH. This structure has two parallel locks, the 
main lock is 110 feet by 360 feet. This system of locks and 
dams provides a navigable depth of nine feet from the 
mouth of the Kanawha River to a point approximately 91 
miles upstream. The existing project was completed at a 
cost of $23,403,201. Construction was initiated in 1931 
and completed in 1937. For further cost details see Table 
17-B, see also, Appendix C. Public Law 99-88 authorized 
the initiation of Engineering and Design and Real Estate 
Acquisition for Winfield Locks and Dam Replacement. 
Feasibility studies for modernization have been 
completed. The recommended plan includes construction 
of an additional lock chamber (800'x110') adjacent to the 
existing locks and continued use of the riverward lock 
chamber and the navigation dam. The full funding 
estimate for new work is $203,000,000. 
Local cooperation. None required. 
Terminal facilities. There are 79 terminals along 
the Kanawha River located from the mouth of the river 
to 30 miles east of Charleston, WV. These terminals are 
constructed principally of steel and wood mooring piles 
and steel pile mooring cells. Seventeen of these terminals 
have railroad connections. One terminal, a paved wharf, 
is owned by the City of Charleston, WV. The remaining 
terminals are privately owned. The principal 
commodities handled are coal, chemicals, acids, cement, 
gasoline and oil, and sand and gravel. For further details 
see the 1962 Annual Report. 
Operations during the fiscal year. The Locks and 
Dams were operated as required and necessary repairs 
and improvements were made to the locks and dams as 
well as to the appurtenant structures and grounds. 
Channel inspections were conducted periodically. 
3. OPEN CHANNEL WORK, 
OHIO RIVER 
See this heading under Chapter 19- Ohio River. 
4. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 17-C. 
5. ALUM CREEK LAKE, OH 
Location. The damsite is located in Delaware 
County, OH, on Alum Creek, a tributary of Big Walnut 
Creek, approximately 26 miles above the mouth of Alum 
Creek and 15 miles north of Columbus, OH, and 
approximately 157 miles above the mouth of the Scioto 
River. 
Existing project. The existing project consists of a 
rolled earthfill dam 93 feet in height and 10,000 feet in 
length with a gate controlled spillway located in the right 
abutment. The reservoir provides a total storage of 
134,800 acre-feet and controls a drainage area of 
approximately 123 square miles. See also Appendix A. 
Construction of the dam and appurtenant works was 
initiated in August 1970 and completed in July 1974. The 
405 tracts of land required for the project have been 
acquired. The Federal cost of the project was 
$56,267,422. The Sponsor will reimburse the 
Government an estimated $27,880,000, exclusive of 
interest, for cost allocated to water supply. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations and Maintenance. The entire project is 
complete. The project was operated for the benefit of flood 
control as required, and necessary repairs were made to 
the structure and appurtenances. During the fiscal year 
the project prevented flood damages estimated to be 
$984,000. To date, the project has prevented an 
estimated $45,071,000 in flood damages. 
17-2

HUNTINGTON WEST VIRGINIA DISTRICT 
6. BEECH FORK LAKE, WV 
Location. The damsite is located in Wayne County, 
WV., on Beech Fork Creek, a tributary of Twelvepole 
Creek, approximately four miles above the mouth of 
Beech Fork Creek and 20 miles above the confluence of 
Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of a 
rolled earth-fill dam 86 feet in height and 1,080 feet in 
length, an uncontrolled spillway landward of the left 
abutment of the dam with a control structure at the 
upstream end. The reservoir provides a total storage of 
37,540 acre-feet and controls a drainage area of 
approximately 78 square miles. Construction of the dam 
was initiated in December 1972 and completed in 
February 1977. See also Appendix A. A total of 485 tracts 
of land were acquired for the project. The total cost of the 
project was $41,987,500. 
Local cooperation. None required. 
Operations during the fiscal year. New Work: 
Engineering activities for remaining work items 
continued. The project is essentially complete, except for 
remaining recreation facilities, landscaping and 
cleanup. 
Operations and maintenance. The project was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood 
damages estimated to be $707,000. To date the project 
has prevented an estimated $3,666,000 in flood damages. 
7. BLUESTONE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located on the New River 
in Summers County, WV, approximately three miles 
above Hinton, WV and one mile from the confluence of 
the New and Greenbrier Rivers. The reservoir is located 
in Summers County, WV and Giles County, VA. 
Existing project. The existing project consists of a 
concrete gravity dam 180 feet in height and 2,048 feet in 
length. Appurtenant structures consist of a gated 
spillway 790 feet in length located in the channel section 
of the dam. The stilling pool is formed by a 23 foot 
highweir located 364 feet downstream of 16 gated sluices 
through the spillway section and discharging into the 
stilling pool. Penstocks were installed at the time of 
construction to permit the future installation of hydropower. 
The reservoir provides for a total storage of 
631,000 acre-feet. See also Appendix A. Construction of 
the dam was initiated in January 1942 and completed in 
April 1952. A total of 338 tracts of land was acquired for 
the project. The Federal cost of the project was 
$29,458,652, which includes expenditures under the 
recreation at completed projects program. For further 
details see the 1939 and 1962 Annual Reports. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. The entire project is complete. The 
reservoir was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $134,000. To 
date, the project has prevented an estimated 
$582,995,000 in flood damages. 
8. BURNSVILLE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located in Braxton County 
WV, on the LIttle Kanawha River, approximately two 
miles above Burnsville, WV, and 124 miles above the 
confluence of the Little Kanawha River and the Ohio 
River. 
Existing project. The existing project consists of an 
earth embankment dam 80 feet in height and 1,000 feet 
in length with a gated spillway in the left abutment. The 
outlet works is an integral part of the spillway, 
consisting of five sluice gates and one low flow sluice. The 
reservoir provides for a total storage of 65,400 acre-feet 
and controls a drainage area of approximately 165 
square miles. Construction of the dam was initiated in 
June 1973 and completed in February 1976. See also 
Appendix A. The 357 tracts of land required for the 
project have been acquired. The Federal cost of the 
project was $56,195,839. 
Local cooperation. None Required. 
Operations during the fiscal year. The project is 
completed. The project was operated for flood control as 
required and necessary repairs were made to the 
structure and appurtenances. During the fiscal year the 
project prevented flood damages estimated to be 
$4,161,000. To date, the project has prevented an 
estimated $26,860,000 in flood damage. 
9. DEER CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Pickaway 
County, approximately seven miles south of Mount 
Sterling, OH on Deer Creek, a tributary of the Scioto 
River, approximately 21 miles above the mouth of Deer 
Creek and approximately 106 miles above the mouth of 
the Scioto River. 
17-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
Existing project. The existing project consists of a 
rolled earth-filled dam 93 feet in height and 3,880 feet in 
length, a 741-foot concrete gravity channel section 
controlled by three tainter gates, an outlet works 
consisting of five gated sluices through a concrete 
spillway section discharging into a stilling basin and an 
earth dike 15 feet by 4,600 feet in a saddle located 
approximately four miles southwest of the damsite. The 
reservoir provides a total storage of 102,540 acre-feet and 
controls a drainage area of approximately 278 square 
miles. Construction of the dam was completed in May 
1968. The 138 tracts of land required for the project have 
been acquired. For further project details see the 1965 
Annual Report. See also Appendix A. The Federal cost of 
the project is $20,406,545, including expenditures under 
the recreation at completed projects program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$376,000 in flood damages during the fiscal year. To date, 
the project has prevented an estimated $18,059,000 in 
flood damages. 
10. DELAWARE LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located on the Olentangy 
River, approximately six miles above and north of 
Delaware, OH, and approximately 32 miles above the 
confluence of the Olentangy and Scioto Rivers at 
Columbus, OH. The reservoir is located in Delaware, 
Marion and Morrow Counties, OH. 
Existing project. The existing project consists of a 
rolled earth-fill dam with a gate controlled ogee type 
spillway and five outlet conduits in the channel. The dam 
is 18,600 feet in length and 92 feet in height. The project 
provides for storage of 132,800 acre-feet and controls a 
drainage area of approximately 381 square miles. 
Construction of the dam was initiated in April 1946 and 
completed in July 1948. For further details see the 1962 
Annual Report. See also Appendix A. Total real estate 
requirements of 7,703 acres of fee acquisition and 2,428 
acres of flowage easements have been completed. The 
Federal cost for the project was $7,631,821. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for the benefit of flood control 
as required, and necessary repairs were made to the 
structure and appurtenances. The project prevented an 
estimated $1,542,000 in flood damages during the fiscal 
year. To date, the project has prevented an estimated 
$60,223,000 in flood damages. 
11. DEWEY LAKE, 
OHIO RIVER BASIN, KY 
Location. The damsite is located on Johns Creek, 
approximately seven miles southeast of Paintsville, KY 
and approximately six miles above the confluence of 
Johns Creek and the Levisa Fork of the Big Sandy River. 
Existing project. The existing project consists of 
an earthfill dam 118 feet in height and 913 feet in length, 
a controlled outlet works discharging through a channel 
excavated in the left abutment, and a rolled earth-fill 
dike blocking a low divide to Brandykeg Creek and the 
Levisa Fork. The reservoir provides a total storage of 
93,300 acre-feet and controls a drainage area of 
approximately 207 square miles. Construction of the 
dam was initiated in March 1946 and completed in July 
1949. For further project detail see the 1965 Annual 
Report. See also Appendix A. Total real estate 
requirements for the project were 12,458 acres in fee and 
1,170 acres in flowage easements. The Federal cost of the 
project was $7,845,547, including expenditures for 
recreation under the completed project program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction activities are 
complete. The reservoir was operated for the benefit of 
flood control as required and necessary repairs were 
made to the structure and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $82,000. To date, the project has prevented an 
estimated $53,122,000 in flood damages. 
12. DILLON LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located on the Licking 
River, approximately six miles above the confluence of 
the Licking and Muskingum Rivers at Zanesville, Ohio. 
Existing project. The existing project consists of a 
rolled earth-fill dam 118 feet in height and 1,400 feet in 
length, a controlled outlet works discharging through a 
20-foot conduit in the right abutment, and an ungated 
280-foot spillway adjacent to the left abutment of the 
dam, and two rolled earthfill dikes. The reservoir 
provides for a total storage of 261,110 acre-feet and 
controls a drainage area of approximately 748 square 
miles. Construction of the dam was completed in July 
1959. For further project details see the 1962 Annual 
17-4

HUNTINGTON WEST VIRGINIA DISTRICT 
Report. See also Appendix A. Total real estate required 
for the project consists of 8,232 acre in fee and 5,380 acres 
of flowage easements. See also Appendix A. Federal cost 
of the project was $30,218,135. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated as required for flood control, 
and necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$5,206,000 in flood damages during the fiscal year. To 
date, the project has prevented an estimated 
$132,825,000 in flood damages. 
13. EAST LYNN LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located in Wayne County, 
WV approximately six miles southeast of Wayne, WV, 10 
miles above the mouth of East Fork and 42 miles above 
the confluence of Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of 
an earth-fill dam 113 feet in height and 638 feet in 
length, an uncontrolled spillway near the left abutment 
of the dam, and a 13-foot reinforced concrete tunnel in the 
right abutment with a control structure at the upstream 
end. The reservoir provides for a total storage of 82,500 
acre-feet and controls a drainage area of approximately 
133 square miles. The required 552 tracts of land have 
been acquired. See also Appendix A. The Federal costs of 
the project is $37,800,480. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $1,460,000. To 
date, the project has prevented an estimated $36,095,000 
in flood damages. 
14. FISHTRAP LAKE, 
OHIO RIVER BASIN, KY 
Location. The damsite is located in Pike County, 
KY, on the Levisa Fork of the Big Sandy River, 
approximately 15 miles upstream from Pikeville, KY, 
approximately three miles above the confluence of 
Levisa and Russell Forks and 103 miles above the mouth 
of the Levisa Fork. 
Existing project. The existing project consists of 
a rock-fill dam 195 feet in height and 1,100 feet in 
length, a controlled spillway containing four tainter 
gates located in the valley wall adjacent to the left 
abutment of the dam, the outlet works consists of an 
intake structure with three conduits controlled by slide 
gates and discharging into a horseshoe shaped tunnel. 
The reservoir provides for a total storage of 164,360 
acre-feet and controls a drainage area of approximately 
395 square miles. The dam was completed in February 
1969. The 1,301 tracts of land required for the project 
have been acquired. See also Appendix A. The Federal 
costs for the project was $54,670,126, which includes 
expenditures under the recreation at completed projects 
program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required, 
and necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $684,000. To 
date, the project has prevented an estimated 
$266,166,000 in flood damages. 
15. GRAYSON LAKE, KY 
Location. The damsite is located in Carter County, 
Kentucky on the Little Sandy River approximately 49 
miles above the confluence with the Ohio River, and 11 
miles upstream from Grayson, KY. 
Existing project. The existing project consists of a 
random earthfill dam 120 feet in height and 1,460 feet in 
length, a controlled outlet works discharging through a 
14-foot spillway beyond the left abutment. The reservoir 
provides for a total storage of 119,000 acre-feet and 
controls a drainage area of approximately 196 square 
miles. The dam was completed in January 1968. The 484 
tracts of land required for the project have been acquired. 
See also Appendix A. Federal costs for the project was 
$19,162,741, which includes expenditures for recreation 
facilities under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $7,645,000. To 
date, the project has prevented an estimated $39,173,000 
in flood damages. 
17-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
16. JOHN W. FLANNAGAN 
DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Location. The damsite is located in Dickenson 
County, VA, approximately four miles northwest of 
Haysi, VA, on the Pound River approximately two miles 
above the confluence of the Pound River and Russell Fork 
and approximately 150 miles above the mouth of the Big 
Sandy River. 
Existing project. The existing project consists of a 
rock-fill dam 252 feet in height and 970 feet in length, an 
outlet tunnel located near the left abutment of the dam 
with a control structure at the upstream end, a spillway 
controlled by six tainter gates located in a saddle just 
upstream from the damsite. The reservoir provides for a 
total storage of 145,700 acre-feet and controls a drainage 
area of approximately 222 square miles. The project was 
modified to include water quality control by adding 
control gates to the previously uncontrolled spillway, 
which increased the total storage capacity by 39,000 
acre-feet. The dam was completed in December 1963. The 
382 tracts of land required for the project have been 
acquired. See also Appendix A. The Federal cost for the 
project was $20,444,383, which includes expenditures for 
recreation under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $260,000. To 
date, the project has prevented an estimated 
$138,453,000 in flood damages. 
17. LEVISA AND TUG FORKS OF THE 
BIG SANDY AND CUMBERLAND 
RIVERS, WV, VA, AND KY 
Location. The Levisa and Tug Forks form the Big 
Sandy River at Louisa, KY. The Cumberland portion is 
the Upper Cumberland River Basin above Cumberland 
Falls, KY. The basin is approximately 100 miles in 
length and averages approximately 30 miles in width in 
the lower portion and approximately 10 miles in width 
above Harlan, KY. The Big Sandy Basin is within the 
Huntington District, and the Cumberland Basin is 
within the Nashville District. This report covers that 
portion of the project located in the Huntington District. 
Existing project. The authorization language 
directs the Corps of Engineers to design and construct, at 
full Federal expense, such flood control measures as are 
determined to be necesssary and advisable for the 
communities in the Tug and Levisa Forks and Upper 
Cumberland River basins. The authorization further 
states that such flood control measures would be located 
at or in the vicinity of Pikeville, KY; and Grundy, VA on 
the Levisa Fork; Pineville, KY, on the Cumberland 
River; and Williamson and Matewan on the Tug Fork, in 
order to afford the named communities and other flood 
damaged locations and their immediate environs a level 
of protection against flooding at least sufficient to 
prevent any future losses from the likelihood of flooding 
such as occurred in April 1977. The full funding estimate 
for the project is $763,300,000, which includes 
$41,600,000 non-Federal contributions. 
Local cooperation. None required. 
Operations during the fiscal year. Additional 
engineering studies are now underway to determine 
what is necessary and advisable to address the flooding 
problems in both the Levisa Fork Basin and in the Tug 
Fork tributary stream areas. The contract for 
construction of the Pump Station at West Williamson, 
WV was awarded in April 1983 and is complete. The 
contract for construction of the floodwall at West 
Williamson, WV, was awarded in July 1986 and is 
complete. The contract for the Williamson Area 
Clearing was awarded in September 1987 and is 
complete. The contract for the Williamson Housing 
Development, Valley View Site, was awarded in 
September 1987 and is 98% complete. The contract for 
the Floodwall and Pump Stations for the Williamson 
Central Business District was awarded in June 1988 
and is 58% complete. 
18. MASSILLON, OH 
Location. The project is located in Stark County, on 
the Tuscarawas River, approximately 200 miles above 
the mouth of the Muskingum River. 
Existing project. The existing project consists of 
channel improvement to the Tuscarawas River, 
combined with the construction of drainage facilities, 
levees and pump stations. For further details see the 
1962 Annual Report. Construction was initiated in July 
1940 and completed in October 1951. 
Local cooperation. None required. See the 1962 
Annual Report for details of local contribution of work 
beyond the scope of the project. 
Operations during the fiscal year. Routine 
inspections were conducted to determine that the 
improved channel was maintained in satisfactory 
condition. 
17-6

HUNTINGTON WEST VIRGINIA DISTRICT 
19. MUSKINGUM RIVER LAKES, OH 
Location. The Muskingum River lies in Southeast 
Ohio and including tributaries, drains approximately 
8,000 square miles. The headwaters rise about 25 miles 
south of Lake Erie and flow into the Ohio River at 
Marietta, OH, 172 miles below Pittsburgh, PA. 
Existing project. The existing project consists of 
the construction and operations and maintenance of 14 
reservoirs and appurtenant works in the Muskingum 
River Basin. The existing project originally authorized 
by the Public Works Administration in February 1934. 
Construction of the system was initiated in January 1935 
and completed in November 1938. The system was 
initially operated and maintained by the Muskingum 
Watershed Conservancy District of Ohio, the sponsoring 
agency, from July 1938 to August 1939 when operation 
and maintenance became the responsibility of the Corps 
of Engineers in accordance with the provisions of the 
1939 Flood Control Act. For further project details, see 
the 1962 Annual Report. See also Appendix A. The cost 
of the project was $41,247,815, which includes 
expenditures for recreation facilities under the 
completed project program. A significant Major 
Rehabilitation program was approved in December 1977 
in order to assure the integrity of the existing 14 
structures under the originally designed maximum pool 
conditions. Underseepage and abutment seepage 
problems are being corrected through the installation of 
downstream blankets and/or relief wells and grouting. 
The estimated full funding cost of the rehabilitation 
program is $39,100,000 in total, with $25,500,000 from 
the Construction, General Appropriation and 
$13,600,000 from the Operations and Maintenance, 
General Appropriation. A related but separate program 
entitled Dam Safety Assurance has been initiated. 
Under current hydrologic design standards, deficiencies 
exist in the spillways at all the 14 projects in the system. 
Corrective measures include widening present 
spillways, constructing new spillways and installing 
parapet walls on top the dams. The full funding estimate 
for the Dam Safety Assurance Program is $60,870,000. 
Local cooperation. All requirements for local 
cooperation have been met. For further details see the 
1942 Annual Report. 
Operations during the fiscal year. New Work. 
The Major Rehabilitation is continuing as scheduled. 
Thus far, twenty-one contracts have been awarded andthe 
program is 65% complete. The Dam Safety Assurance 
program was initiated during FY 1982. Thus far seven 
contracts have been awarded and the Dam Safety 
Assurance program is 39% complete. 
Operations and Maintenance. The reservoirs 
were operated for flood control as required, and the 
necessary repairs were made to the structures and 
appurtenances. The system prevented an estimated 
$43,836,000 in flood damages during the fiscal year. To 
date, the system has prevented an estimated 
$1,153,332,000 in flood damages. 
20. NEWARK, OHIO 
Location. The project is located in Licking County 
at the junction of the North and South Forks of the 
Licking River, approximately 29 miles above the 
confluence with the Muskingum River at Zanesville, OH. 
Existing project. For details of the existing project 
see the 1981 Annual Report. Construction of the existing 
project was initiated in July 1940 and completed in 
November 1941. As a result of the 1968 Flood Control Act 
the existing project was modified to include improvement 
of the interior drainage facilities, construction of Log 
Pond Run diversion channel and modification of the 
North Fork Channel. Construction of the Log Pond Run 
diversion channel was awarded in September 1980 and 
completed in December 1981. The full funding estimate 
for the project is $10,550,000 Federal cost and $4,215,000 
non-Federal. 
Local cooperation. For details of required and 
completed local cooperation see the 1981 Annual Report. 
Operations during the fiscal year. New Work: 
North Fork Channel - As a result of withdrawal of State 
support for the Utica Lake project (now inactive) and the 
interdependency of the operation of Utica with the North 
Fork Channel, the North Fork Channel portion of the 
project required re-formulation. A reanalysis is 
complete. Engineering studies continued. The contract 
for construction of North Fork Channel (Phase I) was 
awarded in September 1986 and is complete. The 
contract for construction of the remaining portion of 
North Fork Channel was awarded in February 1988 and 
is 98% complete. 
Operations and Maintenance: Routine inspections 
were conducted to determine that the improved channel 
was maintained in satisfactory condition. 
21. NORTH BRANCH OF KOKOSING 
RIVER LAKE, OH 
Location. The damsite is located in Knox County, 
OH, on the North Branch of Kokosing River, 
approximately nine miles above the confluence of the 
Kokosing and North Branch Rivers, and two miles 
northwest of Fredericktown, OH. 
Existing project. The existing project consists of a 
rolled-earth dam, 70 feet in height and 1,400 feet in 
17-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
length with an uncontrolled spillway adjacent to the 
right abutment, and an uncontrolled, reinforced concrete 
outlet work located in the right abutment of the dam. The 
reservoir provides for a total storage of 14,885 acre-feet 
and controls a drainage area of approximately 45 square 
miles. the 56 tracts of land required for the project have 
been acquired. Construction of the dam was completed in 
May 1972. See also Appendix A. The Federal cost for the 
project was $6,665,985, which includes expenditures 
under the recreation at completed projects program. 
Local cooperation. None required. 
22. NORTH FORK OF POUND 
RIVER LAKE, VA 
Location. The damsite is located in Wise County, 
VA, on the North Fork of Pound River, approximately 
one mile upstream from the confluence of the North and 
South Forks which form the Pound River and 
approximately three miles upstream from Pound, VA. 
Existing project. The existing project consists of a 
rockfill dam, 130 feet in height and 600 feet in length, an 
uncontrolled spillway in a saddle upstream from the 
dam, and an outlet tunnel in the right abutment with a 
control structure at the upstream end. The reservoir 
provides a total storage of 11,300 acre-feet and controls 
a drainage area of approximately 17 square miles. The 
127 tracts of land required for the project have been 
acquired. Construction of the dam was completed in 
January 1966. See also Appendix A. The Federal costs for 
the project was $6,186,901, which includes expenditures 
for recreation under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction is complete. The 
project was operated as required for flood control and the 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $30,000. To 
date, the project has prevented an estimated $4,710,000 
in flood damages. 
23. OHIO RIVER BASIN 
(HUNTINGTON DISTRICT) 
Location. The work covered by this project consists 
of a series of levees, floodwalls, channel improvements 
and dams and lakes in the Ohio River Basin within the 
Huntington District. 
Existing project. The existing project consists ofthe 
individual projects considered in the Ohio River Basin 
comprehensive plan within the Huntington District. 
Operations during the fiscal year. The 
completed local protection projects, which are operated 
and maintained by local interest, except for those local 
protection projects for which individual reports have 
been included. To date the project has prevented flood 
damages of an estimated cumulative total of 
$617,891,000. 
24. PAINT CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Ross County, 
Ohio, on Paint Creek, a tributary of the Scioto River, 
approximately 37 miles above the mouth of Paint Creek 
and 100 miles above the mouth of the Scioto River and 
approximately four miles east of New Parkersburg, OH. 
Existing project. The existing project consists of a 
rock and random earth fill dam, 118 feet in height and 
700 feet in length, a gale controlled spillway located near 
the right abutment, an outlet tunnel located in the right 
abutment with a control structure at the upstream end, 
and a random rockfill dike located at the right abutment 
of the spillway. The reservoir provides for a total storage 
of 145,000 arcre-feet and controls a drainage area of 
approximately 576 square miles. Construction of the 
dam was completed in July 1973. The 257 tracts of land 
required for the project have been acquired. See also 
Appendix A. Federal costs for the project was 
$26,969,962, which includes expenditures under the 
recreation at completed projects program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and the necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented an estimated $721,000 in flood damages. To 
date, the project has prevented flood damages estimated 
to be $38,794,000. 
25. PAINTSVILLE LAKE, KY 
Location. The damsite is located in Johnson 
County, KY, on Paint Creek, a tributary of the Levisa 
Fork of the Big Sandy River, approximately eight miles 
above the mouth of Paint Creek, and four miles west of 
Paintsville, KY. 
Existing project. The existing project consists of a 
rockfill dam 153 feet in height and 1,560 feet in length, 
an uncontrolled spillway located southwest of the right 
abutment of the dam, and an outlet tunnel in the right 
abutment with a control structure at the upstream end. 
17-8

HUNTINGTON WEST VIRGINIA DISTRICT 
The reservoir provides for a total storage of 76,642 acrefeet 
and controls a drainage area of approximately 93 
square miles. The 635 tracts of land required for the 
project have been acquired. Construction of the dam was 
initiated in September 1976 and was completed in 
September 1980. See also Appendix A. The full funding 
estimate for new work is $66,478,000, which includes 
$3,028,000 non-Federal Costs. The local sponsor has 
reimbursed the Government $377,000 for the cost 
sharing portion of recreation development. 
Operations during the fiscal year. New Work: 
Construction of the project is well advanced. The 
remaining work items include minor highway 
relocations, landscaping and final cleanup. The contract 
for Construction of Mine Fork Road was awarded in 
February 1989 and is 3% complete. 
Operations and Maintenance: The reservoir was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood 
damages estimated to be $3,000. To date, the project has 
prevented flood damages estimated to be $5,650,000. 
26. R. D. BAILEY LAKE, WV 
Existing project. The damsite is located in 
Wyoming County, WV, on the Guyandotte River 
approximately 108 miles above the confluence with the 
Ohio River and one mile east of Justice, WV. 
Existing project. The existing project consists of a 
rolled rockfill dam with a concrete face, 305 feet in height 
and 1,330 feet in length, an uncontrolled spillway located 
in a saddle in the right abutment of the dam, and an 
outlet tunnel in the left abutment with a control 
structure located at the upstream end. The reservoir 
provides for a total storage of 203,700 acre-feet and 
controls a drainage area of approximately 540 square 
miles. Construction of the dam was initiated in 
November 1973 and completed in December 1979. See 
also Appendix A. A total of 2,109 tracts of land were 
acquired for the project. The total cost of the project was 
$261,211,700. 
Local cooperation. None required. 
Operations and Maintenance. The reservoir was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood 
damages estimated to be $94,000. To date, the project has 
prevented flood damages estimated to be $58,790,000. 
27. ROSEVILLE, OH 
Location. The project is located in Muskingum and 
Perry Counties, on Moxahala Creek, approximately six 
miles the confluence with Jonathan Creek, a tributary of 
the Muskingum River. 
Existing project. The existing project consists of 
7,291 feet of channel improvement; 6,400 feet of levee and 
railroad embankment enlargements; and the necessary 
appurtenances for interior drainage. Total Federal cost 
of the project was $910,785. Construction was initiated 
in August 1959 and completed in October 1960. 
Local cooperation. All requirements for local 
cooperation have been completed. See also the 1962 
Annual Report. Total costs of local requirements were 
$62,000. 
Operations during the fiscal year. Routine 
inspections of the improved portion of the project were 
conducted to determine that the project was maintained 
in satisfactory condition. 
28. SUMMERSVILLE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located at Ruckers Bend 
in Nicholas County on the Gauley River approximately 
35 miles above the confluence of the Gauley and New 
River at Gauley Bridge, WV. 
Existing project. The existing project consists of a 
rockfill dam having a height of 357 feet and a length of 
2,280 feet, an outlet tunnel in the right abutment with 
a control structure located at the upstream end, an 
uncontrolled spillway located west of the right abutment 
and two earthfill dikes. The reservoir provides for a total 
storage of 413,800 acre-feet and controls a drainage area 
of 803 square miles. See also Appendix A. Construction 
of the dam was initiated in March 1960 and completed in 
March 1966. A total of 9,346 acres of land were acquired 
for the project. The Federal costs of the project was 
$48,375,884, which includes expenditures under the 
recreation at completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necesssary repairs were 
made to the structures and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $286,000. To date, the project has prevented an 
estimated $256,167,000 in flood damages. 
17-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
29. SUTTON LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located on the Elk River 
in Braxton County approximately one mile above Sutton, 
WV and 101 miles above the mouth of the Elk River. 
Existing project. The existing project consists of a 
concrete gravity dam having a height of 220 feet and a 
length of 1,178 feet, a gated spillway in the channel 
section of the dam, comprised of six tainter gates 
supported by piers, an outlet works comprised of five gate 
sluices through the spillway section. The reservoir 
provides for a storage of 265,300 acre-feet and controls a 
drainage area of 537 square miles. See also Local 
cooperation. None required. See the 1981 Annual 
Report for contributed funds. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necessary repairs were 
made to the structure and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $1,059,000. To date, the project has prevented an 
estimated $173,123,000 in flood damages. 
30. TOM JENKINS RESERVOIR, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Athens County, 
on the East Branch of Sunday Creek, a tributary of the 
Hocking River, approximately three miles north of 
Glouster, Ohio and 57 miles above the mouth of the 
Hocking River. 
Existing project. The existing project consists of a 
rolled-earth dam, 84 feet in height and 944 feet in length, 
a controlled works discharging through a tunnel in the 
left abutment, and an uncontrolled spillway in the ridge 
running south from the damsite. The reservoir, known as 
Burr Oak Lake, provides for a total storage of 26,900 
acre-feet and controls a drainage area of approximately 
33 square miles. See also Appendix A. Construction of 
the project was initiated in March 1948 and completed in 
February 1950. A total of 100 acres of land were acquired 
for the project. The Federal costs of the project were 
$2,086,503, which includes expenditure for recreation at 
completed project. 
Local cooperation. All requirements of local 
cooperation have been met, see also the 1962 Annual 
Report. Contributed funds in the amount of $575,000 
have been received from the State of Ohio. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necessary repairs were 
made to the structure and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $342,000. To date, the project has prevented an 
estimated $9,983,000 in flood damages. 
31. YATESVILLE LAKE, KY 
Location. The damsite is located in Lawrence 
County, on Blaine Creek, a tributary of the Big Sandy 
River, approximately five miles west of Louisa, KY and 
18 miles above the mouth of Blaine Creek. 
Existing project. The existing project provides for 
the construction of an earthfill dam, 104 feet in height 
and 770 feet in length, an uncontrolled spillway located 
approximately one-half mile east of the right abutment 
of the dam, and an outlet tunnel through the left 
abutment of the dam with a control structure at the 
upstream end. The reservoir will provide a total storage 
of 86,951 acre-feet and control a drainage area of 208 
square miles. The full funding estimate for new work is 
$106,000, which will be allocated and expended by the 
Federal Government. The sponsor will reimburse the 
Government an estimated $6,615,000 for the cost 
sharing portion of the recreation development. To date, 
618 of the required 778 real estate tracts have been 
acquired. A contract for construction of the dam was 
awarded in January 1977 and was terminated for the 
convenience of the Government in August 1977. 
Operations during the fiscal year. New Work: 
The contract for Construction of Dam and Appurtenant 
Works, Phase I, was awarded in March 1984 and is 
complete. Contracts with the Commonwealth and the 
County for relocation and/or abandonment of roads 
affected by the project are complete. The contract for 
construction of Dam and Appurtenances (Phase II) was 
awarded in April 1986 and is complete. The contract for 
Relocation of SR32-2 was awarded in February 1986 and 
is complete. The contract for Reservoir Clearing was 
awarded in June 1989 and is 49% complete. The contract 
for Relocating Remaining Highways was awarded in 
October 1988 and is 86% complete. The contract for 
Cemetery Relocation, Part III, was awarded in February 
1989 and is 72% complete. 
32. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The flood control act of June 22, 1936 and 
subsequent acts require local interest to furnish 
assurances that they will operate and maintain certain 
local protection projects after completion in accordance 
with regulations prescribed by the Secretary of the 
Army. District Engineers are responsible for the 
administration of these regulations within their 
respective districts. Maintenance inspections were made 
17-10

HUNTINGTON WEST VIRGINIA DISTRICT 
during the fiscal year of those completed units transferred 
to local interests for operation and maintenance. Local 
interests were advised, as necessary, of measures 
required to maintain the projects in accordance with the 
standards prescribed by regulations. Total costs for fiscal 
year 1989 were $83,890. Total cost to September 30, 
1989, were $1,529,232. The flood control works inspected 
and the dates of inspection are tabulated in Table H. 
33. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency bank protection activities pursuant to 
Section 14 of the 1946 Flood Control Act, Public Law 526, 
79th Congress are tabulated as follows: 
Location FY 1989 Cost 
Apple Creek, Apple Creek, OH 
Jardin Manor, Lick Creek, OH 
Kenova, WV 
Nimishillen Creek, East Sparta, OH 
Ohio River, Gallipolis, OH 
Ohio River, Williamstown, WV 
Ohio River, Village Middleport, OH 
Point Pleasant, WV, State Park 
Prices Creek, at Smithfield, WV 
Sistersville, WV, City Park 
Sistersville, WV, Storm & Sanitary Services 
St. Albans, WV, Kanawha River 
State Route 62, Buffalo, WV 
$ 3,767 
6,467 
50,070 
5,116 
10,875 
41,111 
20,981 
55,113 
19 
35,113 
49,681 
12,257 
32 
Flood control activities pursuant to Section 205 of 
the 1948 Flood Control Act, Public Law 853, 80th 
Congress are tabulated as follows: 
Location FY 1989 Cost 
Black Fork, Mohichan River, Shelby, OH 
Blacklick Creek, Franklin County, OH 
Elk River, at Addison, WV 
Hocking River, at Chauncey, OH 
Hughes Creek, Hugheston, WV 
Krouts Creek, Huntington, WV 
Muskingum River, Mansfield, OH 
Olentangy River, Galion, OH 
Spring Creek, Spencer, WV 
Wolf Creek, Barberton/Norton, OH 
$ 62 
81,234 
8,715 
12,627 
3,342 
673
6 
5,421 
4,665 
25,501 
Snagging and clearing activities pursuant to 
Section 208 of the 1954 Flood Control Act, Public Law 
780, 83rd Congress are tabulated as follows: 
Location FY 1989 Cost 
Hocking River, Rockbridge, OH 
Krouts Creek, Huntington, WV 
Lilly Park, WV 
Shope Creek, Ashland, KY 
Whitestone Creek, Mt. Giland, OH 
$11,294 
146 
39 
846 
819 
Work performed under special legislation pursuant 
to Water Resources Development Act of 1986 as follows: 
Location 
Bridges, Massillon, OH 
Kanawha River, Charleston, WV 
Kanawha River, St. Albans, WV 
FY 1989 Cost 
$ 5,778 
4,683 
13,112 
Flood control and coastal emergency activities 
pursuant to Public Law 99, 84th Congress were 
conducted as required during FY 1989 at a cost of 
$416,239. 
National emergency management activities were 
accomplished by the district as required. The costs for 
these activities during FY 1989 were $131,890. 
34. SURVEYS 
Fiscal year 1989 costs were $2,052,522 itemized as 
follows: 
Navigation Studies 
Flood Damage Prevention Studies 
Comprehensive Basin Studies 
Special Studies 
Miscellaneous Activities 
Coordination Studies 
Advance Engineering and Design 
35. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $189,902. 
$678,360 
583,231 
539,690 
9,519 
92,088 
149,634 
961,345 
17-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
TABLE 17-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
2. Kanawha River, 
.WV 
(Existing Project) 
Winfield L&D 
5. Alum Creek Lake, 
OH 
6. Beech Fork Lake, 
WV 
7. Bluestone Lake, 
Ohio River Basin, 
WV 
8. Burnsville Lake, 
Ohio River Basin, 
WV 
9. Deer Creek Lake, 
Ohio River Basin, 
OH 
10. Delaware Lake, 
Ohio River Basin, 
OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 27,853,6991 
- - - - 27,853,6991 
6,765,000 5,326,600 6,348,500 5,045,900 89,777,5842 
6,780,172 5,273,037 6,338,485 4,956,717 89,589,6872 
- - - - 130,9848 
- - - - 130,9848 
- 1,185,000 2,905,000 5,860,000 
- 788,585 3,049,510 5,257,766 
-45,933 
5,341 
600,200 
608,490 
186,000 
281,817 
608,000 
620,375 
578,800 484,500 
584,656 464,003 
77,021 
807,500 
800,170 
-40,000 
34,897 
754,000 
705,229 
730,200 831,300 966,500 
725,974 818,116 959,377 
-39,426 
12,722 
1,079,600 
1,063,503 
496,800 
492,537 
732,200 
748,714 
9,950,0004 
9,095,8614 
56,267,422 
56,267,422 
5,999,365 
5,955,532 
41,987,500 
41,987,500 
6,825,739 
6,778,872 
- 29,458,6526 
- 29,458,6526 
990,700 14,498,778 
1,027,535 14,489,019 
1,036,000 1,073,100 1,279,100 
1,051,479 1,022,355 1,225,891 
431,200 466,200 401,500 
454,619 454,016 404,277 
1,244,500 831,500 406,500 
1,255,843 804,290 429,605 
378,800 
362,294 
527,600 
527,210 
56,195,839 
56,195,839 
9,263,3056 
9,138,2986 
20,406,5457 
20,406,5457 
6,933,0258 
6,900,4588 
7,631,821 
7,631,821 
9,046,8199 
9,030,0699 
17-12

TABLE 17-A (cont'd) 
HUNTINGTON WEST VIRGINIA DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
11. Dewey Lake, 
Ohio River Basin, 
KY 
12. Dillon Lake, 
Ohio River Basin, 
OH 
13. East Lynn Lake, 
Ohio River Basin, 
WV 
14. Fishtrap Lake, 
Ohio River Basin, 
KY 
15. Grayson Lake, 
KY 
16. John W. Flannagan 
Dam & Reservoir, 
Ohio River Basin, 
VA 
17. Levisa & Tug Forks 
of the Big Sandy & 
Cumberland Rivers, 
KY, WV, & VA 
18. Massillon, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 7,845,54710 
- - - - 7,845,54710 
935,400 1,102,600 1,218,000 1,028,200 14,820,17611 
935,266 1,087,460 1,182,381 1,076,456 14,787,12111 
- - - - 30,218,135 
- - - - 30,218,135 
823,300 
809,990 
1,169,000 
1,201,498 
757,500 
777,145 
410,900 
405,026 
327,000 
299,855 
426,300 6,092,34312 
463,478 6,076,47712 
- - 775,000 
- - 774,512 
960,300 1,213,501 995,100 
945,656 1,106,056 1,123,898 
806,000 
803,962 
37,800,968 
37,806,480 
12,506,80718 
12,487,46818 
54,670,12614 
54,670,12614 
909,500 1,039,300 8,842,49815 
861,475 1,076,769 8,810,28216 
19,162,74116 
19,162,74116 
572,000 
598,334 
639,000 
631,346 
649,500 
617,469 
628,800 9,823,370 
639,720 9,784,232 
20,444,38317 
20,444,38317 
666,500 
674,436 
857,300 1,119,000 
844,377 1,058,688 
935,600 12,092,26218 
979,894 12,056,25718 
14,526,000 30,865,000 30,102,000 41,100,000 139,993,0001' 
15,005,640 20,547,722 36,253,188 43,081,654 136,831,11918 
13,300 
12,942 
-100 9,000 
8,575 
10,000 
9,587 
8,139,4060" 
8,139,406.' 
312,708 
311,611 
17-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
TABLE 17-A (cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
19. Muskingum River 
Dams & Lakes, 
OH 
20. Newark, OH 
(Previous Project) 
(Existing Project) 
21. North Branch of 
Kokosing River 
Lake, OH 
22. North Fork of 
Pound River Lake, 
Ohio River Basin, 
VA 
23. Ohio River Basin 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
(Rehab.) 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Dam Safety 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- - - - 41,247,81521 
- - - - 41,247,81521 
4,041,000 4,110,000 3,570,500 4,222,500 68,878,05022 
4,154,795 3,980,201 3,496,431 4,354,381 68,747,69022 
993,000 
1,139,211 
60,000 
308,507 
196,800 595,500 200,000 992,300 
195,560 577,093 209,502 982,155 
2,052,000 572,000 50,000 22,209,945 
1,915,129 349,014 375,383 22,077,845 
6,000,000 9,065,000 2,410,000 24,415,000 
4,473,692 7,914,562 3,921,597 23,137,625 
845,916 
845,916 
13,800 
13,737 
297,785 
198,296 
23,200 20,500 -900 758,742 
23,004 19,790 - 758,673 
265,000 4,087,000 550,000 10,674,512 
356,352 2,743,720 1,638,974 10,410,324 
58,600 158,300 
59,642 151,627 
199,000 297,400 
206,538 284,700 
154,000 
150,471 
252,500 
246,920 
154,000 
157,555 
6,665,9852" 
6,665,985" 
1,809,917 
1,800,586 
- 6,186,90125 
- 6,186,901" 
265,700 5,655,959" 
275,188 5,645,17726 
355,86127 
355,86127 
24. Paint Creek Lake, New Work 
Ohio River Basin, Approp. 
OH Cost 
Maint. 
Approp. 
Cost 
25. Paintsville Lake, 
KY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
464,000 706,700 
455,093 669,305 
548,500 
590,421 
84,359 620,000 322,000 
435,106 856,936 317,444 
844,500 685,600 596,500 
816,543 672,878 582,529 
- 26,969,962" 
- 26,969,962" 
504,700 6,406,856 
503,067 6,387,170 
635,000 59,444,147 
182,694 58,912,546 
626,600 4,668,700 
629,138 4,637,686 
17-14

TABLE 17-A (cont'd) 
HUNTINGTON WEST VIRGINIA DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
26. R. D. Bailey Lake, New Work 
WV Approp. - 45,250,000 -5,000 - 261,217,2335" 
Cost 271,600 45,222,538 36,623 - 261,217,23380 
Maint. 
Approp. 2,551,000 1,335,800 1,723,000 1,178,000 12,328,61451 
Cost 2,571,582 1,313,257 1,652,811 1,236,457 12,270,41881 
27. Roseville, OH New Work 
Approp. - - - - 910,785 
Cost - - - - 910,785 
Maint. 
Approp. 20,000 12,000 9,000 22,700 192,668 
Cost 19,961 12,004 8,665 - 169,596 
28. Summersville Lake, New Work 
Ohio River Basin, Approp. - - - - 48,375,88482 
WV Cost - - - - 48,375,88482 
Maint. 
Approp. 1,649,000 2,784,500 963,500 1,040,100 18,843,014" 
Cost 1,656,311 2,794,884 902,053 1,086,289 18,799,009" 
29. Sutton Lake, New Work 
Ohio River Basin, Approp. -5,376 - - - 37,029,585" 
WV Cost 12,805 - - - 37,029,585" 
Maint. 
Approp. 1,480,000 1,024,800 1,284,500 1,293,900 21,472,687" 
Cost 1,567,279 1,023,670 1,223,288 1,356,331 21,427,843" 
30. Tom Jenkins Dam, New Work 
OH Approp. - - - - 2,086,503" 
Cost - - - - 2,086,503" 
Maint. 
Approp. 371,000 234,400 227,000 242,500 4,341,375 
Cost 378,150 240,242 227,314 226,493 4,320,175 
31. Yatesville Lake, New Work 
KY Approp. 9,642,000 5,410,000 8,287,000 17,627,000 86,010,500 
Cost 10,201,760 15,907,584 16,007,404 18,798,052 84,011,836 
See page 17-16 for footnotes. 
17-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
1Includes $4,294,612 for new work for previous projects, 
$4,498,636 Emergency Relief funds, $9,004,800 Public Works 
funds and $686,317 Code 713 funds. 
2Includes $3,883,513 for maintenance of previous projects 
and $546,090 Maintenance and Operation funds. 
3 Public Works Acceleration funds. 
4Includes $4,975,000 Inland Waterways Trust funds. 
sIncludes $543,960 Emergency Relief funds, $9,698 Public 
Works Acceleration funds, $211,850 Code 711 funds and 
$75,000 Code 713 funds. 
6Includes $214,678 Maintenance and Operations Funds. 
7Excludes $225,090 contributed funds. Includes $590,000 
Code 711 funds. 
8Includes $130,000 provided by the Productive 
Employment Act of 1983. 
9Includes $240,000 provided by the Productive 
Employment Act of 1983. 
10Includes $23,087 Public Works Acceleration funds, 
$1,089,94 Code 711 funds and $231,105 Code 713 funds. 
11Includes $82,900 Special Recreation Use Fee Funds and 
$214,678 Maintenance and Operations Funds. 
12Includes $100,000 provided from the Productive 
Employment Act of 1983. 
1 lSncludes $209,918 Special Recreation Use Fee Funds and 
$214,678 Maintenance and Operations Funds. 
14Includes $362,649 Code 711 funds and $10,000 Code 712 
funds. 
15Includes $38,000 Special Recreation Use Fee Funds and 
$214,678 Maintenance and Operations Funds. 
16Includes $406,919 Code 711 funds and $2,317 Code 713 
funds. 
17Includes $422,983 Code 711 funds. 
lncludes $88,710 special recreation use fees. 
19Includes Cost from Ohio River Division/District. 
m2Includes $477,813 contributed funds. 
21Includes $27,190,000 National Industrial Recovery 
fundsand $528,288 Code 711 funds. 
2Includes $198,578 Maintenance and Operations funds. 
23Includes $61,945 Public Works Acceleration funds. 
2Includes $45,177 Code 711 funds. 
25Includes $64,233 Code 711 funds. 
26Includes $68,200 special recreation use fees. 
27Includes $10,920 Emergency Relief funds. 
28Includes $14,153 Code 711 funds. 
2Includes $31,496 special recreation use fee funds. 
30Includes $5,534 Consolidated Army funds. 
S31 ncludes $60,000 provided from the Productive 
Employment Act of 1983, and $66,678 Maintenance and 
Operations Funds. 
S32 ncludes $300,062 Code 711 funds. 
"Includes $214,112 special recreation use fee funds, 
$300,000 provided from the Productive Employment 
Appropriations Act of 1983, and $66,678 Maintenance and 
Operation Funds. 
3"Includes $1,837,337 Code 711 funds and $287,843 
Accelerated Public Works funds. Excludes $62,800 contributed 
funds. 
36Includes $267,634 special recreation use fee funds, 
$215,000 provided from the Productive Employment 
Appropriations Act of 1983, and $142,078 Maintenance and 
Operations Funds. 
36Includes $8,064 Code 711 funds and $30,000 Public 
Works Acceleration funds. Excludes $575,000 contributed 
funds. 
17-16

TABLE 17-B 
HUNTINGTON WEST VIRGINIA DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
2. Aug. 30, 1935 
Aug. 15,1985 
Oct. 23, 1962 
Oct. 23, 1962 
Jun. 28, 1938 
Dec. 22, 1944 
Jun. 28, 1938 
Dec. 22, 1944 
Jun. 28,1938 
Jun. 28,1938 
Dec. 22,1944 
Jun. 28, 1938 
Dec. 22, 1944 
Jun. 28,1938 
Dec. 22,1944 
KANAWHA RIVER LOCKS AND DAMS, WV 
Construction of three locks and dams on the Kanawha 
River and one on the Ohio River. 
Engineering and Design and Land Acquisition for 
Winfield Locks and Dam. 
ALUM CREEK LAKE, OH 
Construction of Flood Control Reservoir. 
BEECH FOfRK LAKE, WV 
Construction of Flood Control Reservoir. 
BLUESTONE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
Deleted Power 
BURNSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
DEER CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
DELAWARE LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DEWEY LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DILLON LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
17-17 
H. Doc. 31, 73rd Cong., 
1st Sess. 
P.L. 88, 99th Cong., 
1st Sess. 
H. Doc. 58'7, 87th Cong., 
2nd Sess. 
H. Doc. 520, 87th Cong., 
2nd Sess. 
H. Doc. 91, 74th Cong. 
2nd Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534 78th Cong., 
2nd. Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong. 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
5. 
6. 
10. 
11. 
12.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
TABLE 17-B (cont'd) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
13. Jun. 28, 1938 
Dec. 22, 1944 
14. Jun. 28, 1938 
Dec. 22, 1944 
15. Jul. 14, 1960 
16. Jun. 28, 1938 
Dec. 22, 1944 
17. Oct. 1, 1980 
18. Jun. 28, 1938 
19. Feb. 20, 1934 
Jun. 28, 1938 
Aug. 11, 1939 
20. Jun. 28, 1938 
Aug. 13,1968 
21. Oct. 23, 1962 
22. Jul. 14, 1960 
EAST LYNN LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
FISHTRAP LAKE, OHIO RIVER BASIN, KY 
Construction of Flood Control Reservoir. 
Added Recreation 
GRAYSON LAKE, KY 
Construction of Flood Control Reservoir. 
JOHN W. FLANNAGAN DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Construction of Flood Control Reservoir. 
Added Recreation 
LEVISA AND TUG FORKS OF THE BIG SANDY 
RIVER, AND CUMBERLAND RIVER, KY, WV 
Construction of such Flood Control Measures as deemed 
Necessary and Advisable. 
MASSILLON, OHIO 
Construction of Channel Improvement Project. 
MUSKINGUM RIVER LAKES, OH 
Construction of 14 Flood Control Reservoirs. 
Reimbursement to the Muskingum Conservancy District a 
sum not to exceed actual expenditures for project construction. 
Operations and Maintenance assigned to the Corps of Engineers. 
NEWARK, OHIO 
Construction of Channel Improvement Project. 
Modification to Existing Project and Additional Channel 
Improvement and Drainage Facilities. 
NORTH BRANCH OF KOKOSING RIVER LAKE, OH 
Construction of Flood Control Reservoir. 
NORTH FORK OF POUND RIVER LAKE, VA 
Construction of Flood Control Reservoir. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 440, 86th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Sect. 202, P.L. 367, 
96th Cong., 2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Public Works Admin. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 396, 76th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
H. Doc. 337, 90th Cong., 
2nd Sess. 
H. Doc. 220, 87th Cong., 
2nd Sess. 
H. Doc. 645, 86th Cong., 
2nd Sess. 
17-18

TABLE 17-B (cont'd) 
HUNTINGTON WEST VIRGINIA DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
24. Jun. 28, 1938 
Dec. 22,1944 
Oct. 27, 1965 
Oct. 23, 1962 
Jun. 28,1938 
Jun. 28,1938 
Dec. 22,1944 
Jun. 28, 1938 
Dec. 22,1944 
Dec. 22, 1944 
Oct. 27, 1965 
Jun. 22, 1936 
PAINT CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
PAINTSVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
R. D. BAILEY LAKE, WV 
Construction of Flood Control Reservoir. 
ROSEVILLE, OH 
Construction of Channel Improvement Project. 
SUMMERSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
SUTTON LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
TOM JENKINS DAM, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
YATESVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
INSPECTIONS OF COMPLETED FLOOD CONTROL 
PROJECTS 
Inspection of Local Maintenance of Federally 
Constructed Local Protection Projects. 
17-19 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 246, 89th Cong., 
1st Sess. 
H. Doc. 569, 87th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 762, 78th Cong., 
2nd Sess. 
H. Doc. 246, 89th Cong., 
2nd Sess. 
P.L. 738, 74th Cong., 
1st Sess. 
25. 
26. 
27. 
28. 
29. 
30. 
31. 
32.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
TABLE 17-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Big Sandy River 
WV and KY including 
Levisa and Tu Forks2 1952 1,586,236 1,569,8111 131,473 
Elk River, WV 1903 30,259 
Gauley River, WV4 1903 14,761 
Guyandotte River, WV5 1915 27,500 
Little Kanawha River, WVs 1960 470,536 1,023,854 
Muskingum River, OH7 1955 301,912 6,171,897 6,041 
New River, WA and VA5 1899 109,691 
Scioto River at Portsmouth, OH8 1953 10,951 16,593 
1In addition, $140,068 expended from funds transferred 
from Department of Commerce, under accelerated public 
works program, for repairs of eroded bank at lock 3 on Big 
Sandy River, at Louisa, KY. 
2Operation and Maintenance suspended June 30, 1952. 
SWork closed September 1902. Property transferred to 
Kanawha River improvements. 
4Work closed September 1902. Abandonment recommended 
in H. Doc. 467, 69th Congress. 
5Work suspended. 
6Operation and maintenance suspended June 30, 1951. 
7Collections from license non-Federal hydroelectric 
utilities for use of dams on Muskingum River for fiscal years 
1923-1953 were $79,154. 
8Private Law 954, August 31, 1954, authorized Secretary 
of Treasury to pay Portsmouth sand and Gravel Co. $75,000 in 
full settlement of claims against Government for damages resulting 
from change in Scioto River Channel. 
17-20

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Local Protection Projects 
Ashland, KY 1954 3,718,839 - - 
Athens, OH 1979 5,313,700 - - 
Cattletsburg, KY 1963 3,854,361 - - 
Ceredo-Kenova, WV 1955 2,753,551 - - 
Chillicothe, OH 1986 20,373,314 - - 
East Rainelle, WV 1962 614,598 - - 
Galax, VA 1953 480,536 - - 
Huntington, WV 1956 7,172,840 - - 
Ironton, OH 1952 2,604,646 - - 
Maysville, KY 1959 6,493,747 - - 
Parkersburg, WV 1955 6,652,827 - - 
Pt. Pleasant, WV 1955 2,919,578 - - 
Portsmouth-New Boston, OH 1956 9,806,424 - - 
Princeton, WV 1962 808,750 - - 
Russell, KY 1953 552,493 - - 
Williamson, WV 1964 1,056,166 - - 
Inactive Local Protection Projects 
Augusta, KY - 11,577 - - 
Burlington, OH - - - - 
Chesapeake, OH - - - - 
Coal Grove, OH - 3,389 - - 
Coal River, WV 1979 472,229 - - 
Dover, KY - - - - 
Fullerton, KY - - - - 
Greenup, KY - 4,962 - - 
Lower Guyandotte River Basin, WV - 17,721 - - 
Miller, OH - - - - 
Normal, KY - - - - 
Proctorville, OH - - - - 
Ravenswood, WV - - - - 
South Point, OH - - - - 
South Portsmouth, KY - - - - 
Vanceburg, KY - - - - 
Deferred Local Protection Projects 
Newark, OH (Interior Drainage) 1983 - - - 
Oceana, WV 1981 611,000 - - 
Inactive Reservoirs and Lakes 
Haysi, VA - 2,656 - - 
Leading Creek, WV 1974 272,880 - - 
Panther Creek, WV 1976 22,879 - - 
Salt Creek, OH 1975 1,089,943 - - 
Utica, OH 1975 757,550 - - 
West Fork, WV 1974 663,192 - - 
Deferred Reservoir and Lakes 
Birch, WV -.. 
Kehoe Lake, KY 1981 1,272,740 - - 
Logan, OH - 
Moores Ferry, WV - 
Active Authorized Projects with no current year expenditures. 
Martin, KY 1983 212,048 
17-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1989 
TABLE 17-G DEAUTHORIZED PROJECTS 
All projects listed in this table have been deauthorized in accordance with Section 12 of the Water Resources Development Act 
of 1974, P.L. 251, 93rd Congress. 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds 
Local Protection Projects Report For Date Expended Expended 
Aberdeen, OH - May 1981 1,334 - 
Athalia, OH - Aug 1977 - - 
Belpre, OH - Nov 1977 - - 
Brooklyn, WV - Nov 1979 - - 
Buena Vista, OH - Aug 1977 - - 
Chambersburg, OH - Aug 1977 - - 
Cheshire, OH Nov 1977 - - 
Chilo, OH - Aug 1977 - - 
Clifton, WV - Aug 1977 11,237 - 
Columbus, OH - Aug 1977 - - 
Friendly, WV - Aug 1977 - - 
Gallipoiis, OH - Aug 1977 - - 
Hanging Rock, OH - Aug 1977 - - 
Hartford, WV - Aug 1977 - - 
Henderson, WV - Aug 1977 - - 
Higginsport, OH - Oct 1978 - - 
Hockingport, OH - Aug 1977 - - 
Letart, WV - Aug 1977 - - 
Letart Falls, OH - Aug 1977 - - 
Manchester, OH - May 1981 - - 
Mapleshade, OH - Oct 1978 - - 
Marietta, OH - Nov 1981 - - 
Mason, WV - Aug 1977 - - 
Middleport, OH - May 1981 9,783 - 
Millwood, WV - Aug 1977 - - 
New Martinsville, WV - Nov 1979 - - 
New Matamoras, OH - Aug 1977 - - 
Newport, OH - Aug 1977 - - 
Pomeroy, OH - Aug 1977 - - 
Portland, OH - Aug 1977 - - 
Racine, OH - Aug 1977 - - 
Ripley, OH - Oct 1978 7,523 - 
Riverview, WV - Aug 1977 - - 
St. Mary's, WV - Aug 1977 - - 
Sardis, OH - Aug 1977 - - 
Sciotoville, OH - Aug 1977 - - 
Sistersville, OH - Aug 1977 - - 
Syracuse, OH - Aug 1977 - - 
Waverley, WV - Aug 1977 - - 
Williamstown, WV - Nov 1979 - - 
Zanesville, OH - May 1981 - - 
Reservoirs aid Lakes 
Big Bendc, WV - Aug 1977 - - 
Big Darby, OH 1969 Nov 1979 3,349,568 - 
Frazeysburg, OH - May 1981 5,000 - 
Millersburg, OH - May 1981 - - 
Mill Creek, OH 1981 Nov 1981 1,602,702 - 
Mud River, WV - Nov1979 - - 
Poca, WV - May 1981 - - 
Rocy Fork, OH 1950 Aug 1977 91,321 - 
White Oak Creek, OH - Nov 1981 - - 
17-22

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-H INSPECTION OF FLOOD CONTROL PROJECTS - See Section 33 of Text 
Flood Control Works Inspected Dates of Inspection 
Ashland, KY May 89 Sep 89 
Athens, OH May 89 
Bramwell, WV Oct 89 
Cairo, WV Oct 89 
Canton (Nimishillen), OH Aug 89 
Cattletsburg, KY Jun 89 Sep 89 
Ceredo-Kenova, WV May 89 Sep 89 
Chillicothe, OH Apr 89 Oct 89 
East Rainelle, WV Oct 89 
Fishing Creek, Pine Grove, WV Oct 89 
Fourpole Creek, WV Feb 89 
Galax, VA Nov 89 
Grahn, KY Sep 89 
Griffithsville-Yawkey, WV Dec 89 
Hutchins, KY 
Huntington, WV Apr 89 Sep 89 
Inez, KY Sep 89 
Ironton, OH Apr 89 Sep 89 
Jacksonsburg, Fishing Creek, WV Oct 89 
Maysville, KY May 89 Oct 89 
Montcalm, WV Nov 89 
Newark, OH Jul 89 Oct 89 
Olive Hill, KY Sep 89 
Paint Creek at Chillicothe, OH Dec 89 
Paint Creek at Washington Court House, OH Oct 89 
Parkersburg, WV May 89 Oct 89 
Pax, WV Nov 89 
Point Pleasant, WV May 89 Oct 89 
Portsmouth-New Boston, OH Jun 89 Oct 89 
Prestonsburg, KY Jul 89 
Princeton, WV Nov 89 
Richwood and Fenwick, WV Nov 89 
Right and Left Forks of Beaver Creek, KY Dec 89 
Ripley, WV Oct 89 
Roseville, OH Jul 89 Nov 89 
Russel, KY Jun 89 Sep 89 
Smithfield, WV Oct 89 
South Williamson, KY May 89 Sep 89 
Utica, OH Aug 89 
West Union, Middle Island, WV Oct 89 
Williamson, WV May 89 Sep 89 
17-23

PITTSBURGH, PA DISTRICT * 
This District comprises part of eastern Ohio, western Pennsylvania, 
southwestern New York, northern West Virginia, 
and northwestern Maryland embraced in drainage basin of 
Ohio River and Tributaries above mile 127 (below Pittsburgh), 
immediately upstream from New Martinsville, W. Va. 
IMPROVEMENTS 
Navigation - Locks and Dams Page 
1. Allegheny River, PA ........................... 18-2 
2. Construction of locks and dams, 
Ohio River ...................................... 18-2 
3. Monongahela River, PA and WV .................. 18-2 
4. Open-channel work, Ohio River ................ 18-3 
5. Tygart Lake, WV ................ ............. 18-3 
6. Other authorized navigation projects .............. 18-3 
Flood Control - Local Protection 
7. Chartiers Creek, PA .................. ....... 18-3 
8. Elkins, WV .................................... 18-3 
9. Johnstown, PA......... ...... ............ ... . 18-4 
10. Punxsutawney, Ohio River 
Basin, PA................. .. .. .............. 18-4 
11. Turtle Creek, PA .............................. 18-4 
Flood Control - Reservoirs 
12. Berlin Lake, Ohio River 
Basin, OH...................................... 18-4 
13. Conemaugh River Lake, 
Ohio River Basin, PA ........................... 18-5 
14. Crooked Creek Lake, 
Ohio River Basin, PA ............................ 18-5 
15. East Branch, Clarion River Lake, 
Ohio River Basin, PA ............................ 18-5 
16. Kinzua Dam and Allegheny Reservoir, 
Ohio River Basin, PA and NY .................. 18-5 
17. Loyalhanna Lake, Ohio River 
Basin, PA ............................... ..... 18-6 
18. Mahoning Creek Lake, 
Ohio River Basin, PA ............................ 18-6 
19. Michael J. Kirwan Dam and 
Reservoir, Ohio River Basin, OH .................. 18-6 
20. Mosquito Creek Lake, Ohio 
River Basin, OH ............................... 18-7 
21. Ohio River Basin (Pittsburgh 
District) ......................................... 18-7 
22. Shenango River Lake, Ohio 
River Basin, PA and OH ......................... 18-7 
23. Stonewall Jackson Lake, Ohio River 
Basin, WV..................................... 18-8 
24. Tionesta Lake, Ohio 
River Basin, PA ................................. 18-8 
25. Union City Dam, Ohio River 
Basin, PA ....................................... 18-8 
26. Woodcock Creek Lake, Ohio River 
Basin, PA ....................................... 18-9 
27. Youghiogheny River Lake, Ohio River 
Basin, PA and MD ............................... 18-9 
28. Inspection of completed flood control 
projects.......................................... 18-9 
29. Other authorized flood control projects. .......... 18-10 
30. Flood control work under special 
authorization ....................................... 18-10 
General Investigations 
31. Surveys....................................... 18-10 
32. Collection and study of basic data ................ 18-10 
33. Preconstruction, Engineering and Design......... 18-10 
34. Research and development. ................ .. 18-10 
Tables 
Table 18-A 
Table 18-B 
Table 18-C 
Table 18-D 
Table 18-E 
Table 18-F 
Table 18-G 
Table 18-H 
Table 18-I 
Table 184-J 
Table 18-K 
Table 18-L 
Table 18-M 
Cost & Financial Statement ............. 18-11 
Authorizing Legislation ................. 18-15 
Other Authorized Navigation Projects .... 18-20 
Not Applicable ......................... 
Other Authorized Flood Control 
Projects ................................ 18-21 
Not Applicable......... ................ 
Deauthorized Projects .................. 18-23 
Allegheny River Statistics ............ 18-24 
Monongahela River Statistics ............ 18-25 
Monongahela River Total Costs .......... 18-26 
Ohio River Basin Reservoirs ............. 18-26 
Inspection of Completed Flood Control 
Projects ................................ 18-27 
Flood Control Work Under Special 
Authorization.......................... 18-28 
18-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation - Locks and Dams 
1. ALLEGHENY RIVER, PA 
Location. The Allegheny River is 325 miles long. It rises in 
northern Pennsylvania, flows northwestward into New York, 
thence generally southwestward to Pittsburgh, PA, where it 
joins with Monongahela River to form the Ohio. (See Geological 
Survey Charts for western Pennsylvania and southwestern 
New York.) 
Existing project. The project consists of eight locks and 
dams to afford slack-water navigation for a length of 72 miles 
from Pittsburgh, PA to above East Brady, PA. Controlling 
depth through canalized portion is 9 feet at normal pool level. 
Channel width varies from a minimum of 200 feet to full width 
of river at mouth. Existing project is complete, the last lock, 
No. 9, was placed in service in 1938. All locks and dams are in 
fair condition. Navigation channel has been widened at certain 
points and, in general, maintained to project depth, thus affording 
adequate depth for passage of commercial tows. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Pittsburgh constructed a modern 
wharf for river freight. There are numerous privately 
maintained terminals and docks, consisting of tipples, various 
types of hoists, chutes, and pipelines for use in loading and 
unloading coal, stone, sand, gravel, petroleum products, steel 
products, and other commodities. Transshipment of freight between 
river and railroads is handled at privately owned riverto-
rail terminals. Existing private terminals are adequate for 
shipments and receipt in Pittsburgh District of type of commerce 
now in existence. 
Operations during fiscal year. Operations and Maintenance, 
General: Contract for tow haulage units at locks 2, 3, 4 
and 6, awarded in September, 1988 for $330,337 was 67% complete. 
Contracts completed during the fiscal year include erosion 
protection at L/D 7 for an estimated $4,302,885 and installation 
of exterior insulation and doors - L/D 6 and 7 for an 
estimated $151,464. Locks were operated as required and necessary 
repairs were made to structures to maintain them in a 
serviceable condition. 
2. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
See this heading under Ohio River portion. 
3. MONONGAHELA RIVER, PA AND 
WV 
Location. Formed by junction of Tygart and West Fork Rivers 
about 1 mile south of Fairmont, WV, and flows northerly 
for 128.7 miles to its junction with Allegheny River, forming 
Ohio River at Pittsburgh, PA (See Geological Survey Charts 
for southwestern Pennsylvania and northern West Virginia.) 
Previous project. For details see Annual Report for 1963, 
page 1070. 
Existing project. Provides for improvement of river by 9 
locks and dams to afford slack-water navigation for its entire 
length from Pittsburgh to above Fairmont, WV. Original locks 
and dams 7, 8 and 9 were replaced by new locks and dams 7 and 
8 in 1925. Increased traffic necessitated enlargement and improvement 
of locks and dams 1 to 6 between Pittsburgh and 
Rices Landing, PA, by building two parallel chambers and 
fixed concrete dams during 1905 and 1932. Locks and dam 1 
were eliminated in 1938 by raising Emsworth Dam, Ohio 
River. Reconstruction of lock 2 was completed in 1953 to provide 
two modern navigation chambers. The existing locks and 
dam 2 were originally completed in 1907; major modifications 
were made in 1923 and 1924, and in 1926 the upper guard and 
guide walls were extended. Construction of Maxwell locks and 
dam and the reconstruction of dam 4 have allowed for removal 
of obsolete locks and dams 5 and 6. Small and antiquated 
original locks and dams 10 to 15, inclusive, have been replaced 
by three modern structures. Morgantown lock and dam, initial 
step in replacement program, was completed in 1950 replacing 
locks and dams 10 and 11. Hildebrand lock and dam, next 
upstream, was completed in 1959 replacing locks and dams 12 
and 13. Raising crest of dam 8 was also completed in 1959 as 
part of upper river improvement and eliminates restricted 
depth in upper reach of pool. Opekiska lock and dam was completed 
in 1967 replacing locks and dams 14 and 15. Completion 
of this link in upper river replacement program provides for 
entire river length of minimum channel depth of 9 feet, varying 
in width from a minimum of 250 feet to practically full 
width at mouth. 
Locks and dam 3 showed advanced stages of deterioration 
and, because of its strategic location and its importance to 
industry throughout the Greater Pittsburgh area and the nation, 
emergency remedial work had to be done in 1977. Major 
rehabilitation of locks and dam 3 was completed on Oct. 27, 
1980. 
The Water Resources Development Act of 1986 authorized 
the replacement of Lock and Dam 7 with Grays Landing Lock 
and Dam and the construction of a new lock landward of the 
existing lock at Lock and Dam 8 (to be renamed Point Marion 
Lock and Dam). In accordance with the provisions of this act, 
50% of the total cost of construction for the Grays Landing and 
Point Marion projects will be derived from the Inland Waterways 
Trust Fund. 
Local cooperation. None required. 
Terminal facilities. City of Pittsburgh constructed a modern 
wharf for freight. Boat landings are maintained by some 
municipalities along the river. A large number of tipples at 
mines and various types of hoists at manufacturing plants and 
sand and gravel supply companies are maintained for private 
use in loading and unloading coal, coke, billets, steel products, 
sand, gravel, and other commodities. These terminals and 
docks are not available for general commerce. A number of 
docks and pipelines are also privately maintained for 
petroleum and acid products. Marine ways are maintained by 
some of the larger industries. These are also several terminals 
for rail-to-river and river-to-rail transfer. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year: New Work: A contract for 
right bank excavation, Grays Landing L/D, was awarded on 
May 26, 1988 for $12,058,580 and was 93% complete. All land 
has been acquired for the lock site. Work continued on cultural 
resources and the acquisition of real estate for the remainder 
of the project. The estimated total cost of the project, which is 
scheduled to be complete in August, 1995 is $168,000,000. A 
total of 193 acres in fee and easements is expected to be acquired 
for the project by the end of FY 90. The estimated total 
cost of the Pt. Marion project, which is scheduled to be complete 
in September 1993, is $96,400. 
Operations and Maintenance, General: Contracts physically 
completed during the fiscal year include: Dam rehabilitation 
- Pt. Marion L/D for an estimated $2,491,843; replace 
concrete slabs - esplanade, Opekiska L/D for an estimated 
$101,489; and esplanade repairs - Maxwell L/D for an estimated 
$92,092. Contracts financially completed during the fiscal 
year include: Painting service bridge and emergency bulkheads 
- Morgantown L/D and Hildebrand L/D for $183,340; 
18-2

PITTSBURGH, PA., DISTRICT 
emergency dredging - Hildebrand L/D for $260,103; removal of 
lower approach cells - L/D 3 for $137,170 and access road, 
parking lot and esplanade repaving for $53,475. Locks were 
operated as required and necessary repairs were made to structures 
to maintain them in a serviceable condition. 
4. OPEN-CHANNEL WORK, OHIO 
RIVER 
See this heading under Ohio River portion. 
5. TYGART LAKE, WV 
Location. Tygart Lake is located on the Tygart River in 
Taylor and Barbour Counties, northcentral WV. The lake is 
approximately 26 road miles due east of Clarksburg, WV and 
30 road miles south of Morgantown. The dam is situated 22.7 
river miles above the mouth of the Tygart River at Fairmont, 
or 2.25 miles upstream from Grafton, WV, and about 78 miles 
south of Pittsburgh, PA. (See Geological Survey Charts for 
Fairmont, Thornton, and Belington, WV.) 
Existing project. A reservoir for low water regulation and 
flood control. Dam is concrete gravity type with an uncontrolled 
center spillway flanked by abutment sections joining 
valley sides. Project was authorized by Public Works Administration 
January 11, 1934, and adopted by 1935 River and Harbor 
Act. For further project description see Annual Report for 
1962. Authorized project is complete. Reservoir is in operation 
for low water control in Monongahela River and for purpose of 
flood protection in Monongahela and Ohio Valleys. Construction 
of dam was started in 1935 and placed in operation in 
1938. Land acquired for project consists of 2,662.9 acres in fee, 
flowage easements over 1,216.9 acres and 1,731.9 acres of other 
easements. 
Local cooperation. The State of West Virginia has assumed 
responsibility for the development and operation of 
hunting and fishing areas as well as the Tygart Lake State 
Park. Controlled releases for downstream navigation and 
recreation are also coordinated with others to the extend feasible. 
No local cooperation is required at completed project; however, 
future recreational developments are subject to certain 
conditions of non-Federal cost-sharing under Federal Water 
Project Recreation Act of 1965. A cost-sharing agreement was 
executed with the West Virginia Department of Recreation in 
May 1981. 
Operations during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood control 
and low water regulation, as required, and project structures 
were operated and maintained in a serviceable condition 
throughout the year. Estimated flood control benefits achieved 
by this reservoir for this period were $17,140,000. Total flood 
control benefits for this reservoir through September 30, 1989 
are $545,845,000. Activities under reservoir management program 
comprising sanitation measures, conservation, land 
management, and operation and maintenance of public-use 
facilities continued. This work was limited in scope as State of 
West Virginia has jurisdiction over recreation in reservoir 
area. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 18-C on other authorized navigation projects. 
Flood Control - Local Protection 
7. CHARTIERS CREEK, PA 
Location. Within Washington and Allegheny Counties, 
southwestern Pennsylvania, a tributary of Ohio River. (See 
Geological Survey Chart for Carnegie, PA) 
Existing project. Provides for channel widening, deepening 
and realignment, construction of a major channel cutoff, and 
relocations in two separate and independent reaches. James G. 
Fulton project in Allegheny County would be about 13.4 miles 
long and Canonsburg-Houston reach in Washington County 
about 4.7 miles long. Completed improvements would contain 
within banks, all floods up to the 1912 maximum of record, but 
with some residual damage, and would greatly reduce flood 
stages and damages resulting from higher floods. James G. 
Fulton Flood Control Project-Construction of Unit 1 was 
started in July 1968, completed in September 1970, and turned 
over to local interests for operation and maintenance on 
June 25, 1971. Construction of Unit 2 was started in April 
1970, completed in April 1973, and turned over to local interests 
on November 22, 1974. Construction of Unit 3 was started 
in July 1971 and was completed in December 1974. Construction 
of Unit 5 was started in June 1972 and was Completed in 
December 1973. Construction of Unit 4 channel improvement 
was started in July 1978, completed in June 1981 and turned 
over to local interests on 18 November 1981. A contract for 
Environmental Improvement, Unit 4, James G. Fulton, was 
awarded in Sep 1981 and completed in Dec 1981. Canonsburg- 
Houston Reach-Construction of Unit 1 was started in December 
of 1968, completed in March 1970, and turned over to local 
interests for operation and maintenance on August 10, 1970. 
Construction of Unit 2A was started January 17, 1976, completed 
December 16, 1976, and turned over to local interests on 
June 9, 1977. Construction plans and specifications for Unit 
2B, the remaining unit of the reach, are 99% complete. Remaining 
work on project has been delayed due to the inability 
of local cooperating agency to provide the necessary rights-ofway. 
Project was authorized by Flood Control Act of 1965. 
Estimated cost for new work (1985) is $41,850,000 of which 
$32,750,000 is Federal cost and $9,100,000 non-Federal cost. 
Local cooperation. Requirements are described in full on 
page 26-3 of FY 1981 Annual Report. Local cooperating agency 
(Washington County) has been unable to provide the necessary 
rights-of-way for the remaining Unit 2B. Direct non-Federal 
contributions have been made in the amount of $4,225,188. 
Operations during fiscal year. Regular inspections were 
made at completed units. Estimated flood control benefits 
achieved by the Chartiers Creek project for this period were 
$3,000. Total benefits achieved through September 30, 1989 
were estimated to be $16,051,000. 
8. ELKINS, WV 
Location. On Tygart River in north-central Randolph 
County, WV, about 155 miles south of Pittsburgh, PA. It is at 
downstream end of a long, broad reach of upper Tygart Valley, 
about 75 miles above mouth of river. (See Geological Survey 
Chart for Elkins, WV) 
Existing project. Provides flood protection by diverting 
flood discharges from upstream arm of loop of natural river 
channel into an artificial cutoff channel, thereby bypassing 
City of Elkins. Improvement is designed to accommodate discharges 
equivalent to maximum flood of reasonable expectancy. 
Project construction was started in May 1946 and cornpleted 
in May 1949. Completed works, except that portion of 
18-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
channel maintained by Federal Government, has been operated 
and maintained by City of Elkins since March 31, 1949. 
Land acquired for project consists of 32.04 acres in fee and 
526.01 acres in easements. Project was authorized by 1938 
Flood Control Act. For further project description see Annual 
Report for 1962, page 1222. Federal cost of completed project 
was $1,772,627; estimated non-Federal cost for lands, easements, 
and rights-of-way was $40,000. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and maintenance, 
general: Routine investigations and inspections were 
made. Project was last inspected in June 1986. Cumulative 
total flood damages prevented to September 30, 1989, totaled 
$14,311,000. 
9. JOHNSTOWN, PA 
Location. Project is located in southwestern Cambria 
County, PA, about 58 miles east of Pittsburgh, PA. It is in a 
deep and comparatively narrow valley at junction of Stoney 
Creek and Little Conemaugh River, which unite to form Conemaugh 
River. (See Geological Survey Chart for Johnstown, 
PA.) 
Existing project. Provides for increased channel capacity 
by enlarging and realigning channels and protecting banks 
with concrete pavement. Improvement designed to accommodate 
discharges equivalent to those of March 1936 flood, maximum 
natural flow of record, minimum of overbank flow and to 
practically eliminate damages therefrom. Project construction 
began in August 1938 and was completed in November 1943. 
Footer protection for Unit 4 was completed in November 1949. 
Land acquired for project consists of easements over 192 acres. 
Project was authorized by Flood Control Acts of 1936 and 1937. 
For further project description see Annual Report for 1962, 
page 1215. 
Local cooperation. Section 2, Flood Control Act of June 28, 
1938, applies. 
Operations during fiscal year. Operations & maintenance, 
general: Contract for flood wall repairs, awarded in 
August 1989 for $85,000 was 30% complete. Contract for removal 
of bar deposits and cleaning weep holes was completed 
in FY 89 for $427,731. Cumulative flood damages prevented by 
project were estimated to be $417,940,000 to end of September, 
1989. 
10. PUNXSUTAWNEY, OHIO RIVER 
BASIN, PA 
Location. Borough of Punxsutawney is on Mahoning Creek 
in Jefferson County, PA, about 85 miles northeast of Pittsburgh, 
PA. It is on a comparatively wide, alluvial flood plain 
about 52 miles above mouth of stream and 30 miles above 
Mahoning Creek flood control dam. (See Geological Survey 
Charts for Punxsutawney and Smicksburg, PA.) 
Existing project. Provides flood protection by channel enlargement, 
dikes, and walls. Improvement is designed to accommodate 
discharges 20% greater than that of maximum 
flood of record. Project was accomplished by construction of 
four units. Construction started May 1946 and was completed 
June 1950. Land acquired for project consists of perpetual easements 
over 72.6 acres. Completed works, except that portion of 
channel maintained by the Federal Government have been 
operated and maintained by Borough of Punxsutawney since 
July 31, 1950. Project was authorized by 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1209. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and maintenance, 
general: Operation activities continued and routine investigations 
and inspections were made. Cumulative flood 
damages prevented by project were. estimated to be 
$28,913,000 to end of September 1989. 
11. TURTLE CREEK, PA 
Location. In Allegheny and Westmoreland Counties, adjacent 
to Pittsburgh, PA, along lower reaches of Turtle Creek 
and Thompson Run, a tributary of Turtle Creek. (See Geological 
Survey Chart for Pittsburgh, PA). 
Existing project. The existing channel improvement project 
was constructed during the period 1962-1967 and provided 
for flood protection by widening, deepening, and streamlining 
channel of lower Turtle Creek for about 6.3 miles and channel 
of Thompson Run for about 1 mile above its mouth. Appurtenant 
work consists of channel streambed and side slope protection 
where required, retaining walls, drop structures, 
floodgates, alteration, removal or reconstruction of restrictive 
structures and adjustments of affected utilities. Project was 
designed to accommodate a design flood corresponding to an 
estimated 100 year frequency. Project was authorized by Flood 
Control Act of 1958. Federal cost for completed project was 
$15,350,000; non-Federal cost was $1,840,000. The Fiscal Year 
1985 Supplemental Appropriations Act specified that the Secretary 
of the Army, acting through the Chief of Engineers, is 
authorized and directed to repair and restore the Turtle Creek, 
Pennsylvania, local protection project. Estimated Federal cost 
for repair and restoration work is $1,950,000; non-federal cost 
is $650,000. 
Local cooperation. The Turtle Creek Flood Control Authority 
was the local sponsor for the existing project. However, 
they are not financially able to sponsor the project restoration, 
nor to subsequently perform any required project maintenance. 
Consequently, the District has coordinated with other 
levels of Government, and in the process, has been advised by 
Allegheny County, Pennsylvania Board of Commissioners, 
that the County will sponsor the project. Preliminary confirmation 
by letter was received on 30 March 1988. 
Operations during fiscal year. New work: The proposed 
project consists of debris and sediment removal from the Turtle 
Creek and Thompson Run channels and debris basin; clearing 
trees and brush from channel side slopes, restoration of channel 
side slopes, repairs to concrete retaining walls, debris 
dams, trashracks, spalled concrete joints and drainage appurtenances; 
and removal of vegetative growth from weepholes. 
12. BERLIN LAKE, OHIO RIVER 
BASIN, OH 
Location. Dam is on Mahoning River about 73 miles above 
its confluence with Shenango River. It is about 10 miles above 
existing Milton Reservoir Dam and 35 miles upstream from 
Warren, Ohio. Reservoir is in Portage, Mahoning and Stark 
Counties, OH. (See Geological Survey charts for Warren, 
Ravenna, and Alliance, OH.) 
Existing project. A reservoir for flood control and water 
supply. Dam consists of a partially controlled, concrete gravity, 
center spillway flanked by rolled-earthfill abutment sections 
joining valley sides. Authorized project is complete and in operation 
for flood control and low water regulation purposes in 
industrialized Mahoning Valley below. Construction of dam 
was started January 1942 and completed in June 1943. Present 
project lands consists of 6,885.3 acres in fee and 1,098.7 acres 
18-4

PITTSBURGH, PA., DISTRICT 
in easements. For further project description, see Annual Report 
for 1962, page 1233. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject to certain 
conditions of non-Federal cost-sharing under Federal 
Water Project Recreation Act of 1965. 
Operations during fiscal year. Contract for construction 
of entrance road was completed for an estimated $97,904. 
Reservoir was operated as required and necessary repairs were 
made to structures and appurtenances. Estimated flood control 
benefits achieved by this reservoir for this period were 
$8,968,000; total benefits through September 30, 1989 are 
$232,059,000. Activities under reservoir management program 
comprising sanitation measures, conservation, land 
management, and operation and maintenance of public-use 
facilities continued. 
13. CONEMAUGH RIVER LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Conemaugh River in Indiana and 
Westmoreland Counties, PA, 7.5 miles above junction of Conemaugh 
River and Loyalhanna Creek, which form the head of 
the Kiskiminetas River. It is about 2 miles northeast of Tunnelton, 
PA, and about 42 miles east of Pittsburgh, PA. Reservoir 
is in Westmoreland and Indiana Counties, PA. (See Geological 
Survey Charts for Latrobe, New Florence, and Elders 
Ridge, PA.) 
Existing Project. A flood control reservoir dam of concrete 
gravity type with a gate-controlled center spillway flanked by 
abutment sections joining valley sides and an earth embankment 
ending in right abutment. Authorized project is complete. 
Reservoir system is designed for protection of Pittsburgh 
and reduction of flood heights in upper Ohio Valley, generally. 
Land acquired for dam, reservoir and railroad relocation consists 
of 7608.7 acres in fee and 522.8 acres in easements. Project 
authorized by Flood Control Acts of 1936 and 1938. For 
further project description see Annual Report for 1962, page 
1217. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and maintenance, 
general: Contract for drift and debris removal, awarded 
10 December 1987 for $35,000, was completed during the fiscal 
year. Reservoir was operated for benefit of flood control as 
required, and necessary repairs were made to structures and 
appurtenances. Estimated flood control benefits achieved by 
this reservoir for this fiscal year were $3,987,000; total flood 
control benefits through September 30, 1989 were 
$566,416,000. Activities under reservoir management program 
comprising sanitation measures, conservation, land 
management and operation and maintenance of public use facilities 
were continued. 
14. CROOKED CREEK LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Crooked Creek 6.7 miles above junction 
of creek with Allegheny River near Ford City, PA, and about 
32 miles northeast of Pittsburgh, PA. (See Geological Survey 
Charts for Freeport and Elders Ridge, PA.) 
Existing project. A flood control reservoir dam of earth-fill 
type with separate uncontrolled saddle spillway and tunnel 
outlet works. Authorized project is complete. Reservoir is in 
operation as a unit of a coordinated reservoir system designed 
for protection of Pittsburgh and reduction of flood heights in 
upper Ohio Valley, generally. Construction of dam was started 
in March 1938 and completed in October 1940. Present project 
lands consist of 2,563.6 acres in fee and 99.98 acres in easements. 
Project was authorized by Flood Control Acts of 1936 
and 1938. For further project description see Annual Report for 
1962, page 1213. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and maintenance, 
general: Contract for spillway repairs, awarded in September 
1988, was completed for $242,364. Reservoir was operated 
for benefit of flood control, as required, and necessary 
repairs were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir for this fiscal 
year were $840,000; total benefits achieved through September 
30, 1989 were $124,610,000. Activities under reservoir 
management program comprising sanitation measures, conservation, 
land management, and operation and maintenance 
of public-use facilities continued. 
15. EAST BRANCH, CLARION RIVER 
LAKE, OHIO RIVER BASIN, PA 
Location. Dam is in Elk County, PA on East Branch of 
Clarion River above Middle Fork, 7.3 miles above junction of 
East and West branches of Clarion River at Johnsonburg, PA, 
and about 105 miles northeast of Pittsburgh, PA. Reservoir is 
in Elk County, PA. (See Geological Survey Chart for Mount 
Jewett, PA.) 
Existing project. A reservoir for flood control and lowwater 
regulation. Dam is rolled-earthfill type with gatecontrolled 
concrete tunnel under right abutment and a paved 
uncontrolled spillway on left abutment slope. Authorized project 
is complete. Reservoir is in operation for low-water regulation 
purposes in Clarion River Valley below and for flood control 
as a unit of a coordinated reservoir system for protection of 
Pittsburgh and upper Ohio Valley, generally. Construction of 
dam was started in June 1947 and completed in July 1952. 
Present project lands consist of 287.2 acres in fee and 1,296.7 
acres in easements. Project was selected for construction under 
general authorization for Ohio River Basin in Flood Control 
Acts of 1938 and 1944. For further project description see Annual 
Report for 1962, page 1206. 
Local Cooperation. None required by law. 
Operations during fiscal year. Operations and maintenance, 
general: A contract for water supply systems revisions 
was completed for $30,750. Reservoir was operated for flood 
control and low-water regulation, as required; and necessary 
repairs were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir during this 
fiscal year were $334,000; total benefits through September 
30,1989 are $32,545,000. Some reservoir management activity 
was performed throughout the year comprising sanitation 
measures, conservation, land management and operation of 
public-use facilities. Work was limited in scope as bulk of 
reservoir lands are owned by Commonwealth of Pennsylvania. 
16. KINZUA DAM AND ALLEGHENY 
RESERVOIR, OHIO RIVER BASIN 
PA AND NY 
Location. Dam site is on Allegheny River 9 miles above 
Warren, PA, and 198 miles above mouth of river at Pittsburgh, 
PA. Reservoir is in Warren and McKean Counties, PA., and 
Cattaraugus County, NY. (See Geological Survey Charts for 
Warren and Kinzua, PA-NY, and Randolph and Salamanca, 
NY.) 
18-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. Reservoir provides flood control, low 
water regulation, and recreation. Dam consists of a combination 
concrete gravity structure and rolled earth embankment 
with gate-controlled spillway and discharge conduits controlled 
by slide-gates in gravity section. Construction of project, 
initiated in February 1960, is complete. Construction of 
dam was started in September 1960 and completed in December 
1965. Development of recreation area at Onoville under a 
cost-sharing agreement with Cattaragus County was completed 
in June 1978. Land acquired for project consists of 
2,646.6 acres in fee and easements over 22,420.4 acres. For 
further details see Annual Report for 1962, page 1202. Project 
was authorized by Flood Control Acts of 1936, 1938 and 1941. 
Local cooperation. None required by law. 
Licenses. The Federal Power Commission granted a license 
to Pennsylvania Electric Company and Cleveland Electric Illuminating 
Company on December 28, 1965, for the joint construction, 
operation and maintenance of a 325-megawatt 
pumped-storage installation (FPC Project No. 2280). The project 
is complete. 
Operation during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood control 
and low water regulation, as required, and necessary repairs 
were made to structures and appurtenances. Estimated 
flood control benefits achieved by this reservoir for this period 
were $2,309,000; total to end of this fiscal year, $335,385,000. 
Of 2,212 surface tracts authorized for acquisition, all have been 
acquired but are subject to a final audit. Activities under reservoir 
management program comprising sanitation measures, 
conservation, land management, and operation and maintenance 
of public-use facilities continued. 
17. LOYALHANNA LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Loyalhanna Creek, 4.5 miles above 
junction of creek with Conemaugh River at Saltsburg, PA, and 
about 29 miles east of Pittsburgh, PA. Reservoir is in Westmoreland 
County PA. (See Geological Survey Chart for Latrobe, 
PA). 
Existing project. A flood control reservoir dam of concrete 
gravity type with a gate-controlled center spillway flanked by 
abutment sections joining valley sides, and an earth embankment 
section ending in left abutment. Authorized project is 
complete. Reservoir is in operation as a unit of a coordinated 
reservoir system designed for protection of Pittsburgh and reduction 
of flood heights in upper Ohio Valley, generally. Construction 
of dam was started in October 1939 and completed in 
June 1942. Land acquired for project consists of 3,333.7 acres 
in fee and easements over 86.7 acres. Project was authorized by 
Flood Control Acts of 1936 and 1938. For further project description 
see Annual Report for 1962, page 1219. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood control, 
as required, and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this reservoir for ths fiscal year were $1,094,000; 
total benefits to September 30, 1989; $166,835,000. Activities 
under reservoir management program comprising sanitation 
measures, conservation, land management and operation and 
maintenance of public-use facilities continued. 
18. MAHONING CREEK LAKE, OHIO 
RIVER BASIN, PA 
Location. Dam is on Mahoning Creek in Armstrong 
County, PA, 21.6 miles above junction of creek with Allegheny 
River. It is about 6.50 miles southeast of New Bethlehem, PA, 
and about 51 miles northeast of Pittsburgh, PA. Reservoir is in 
Armstrong, Indiana, and Jefferson Counties, PA. (See Geological 
Survey Charts for Rural Valley and Smicksburg, PA). 
Existing project. A flood control reservoir dam of concrete 
gravity type with a gate-controlled center spillway flanked by 
abutment sections joining valley sides. Authorized project is 
complete. Reservoir is in operation as a unit of a coordinated 
reservoir system designed for protection of Pittsburgh and reduction 
of flood heights in upper Ohio Valley, generally. Construction 
of dam started in February 1939 and was completed 
in June 1941. Land acquired for projects consists of 2,519.36 
acres in fee and easements over 83.5 acres. Project was authorized 
by Flood Control Acts of 1936 and 1938. For further project 
description see Annual Report for 1962, page 1210. 
Local cooperation. None required at completed project. On 
November 4, 1977 a contract for Wildlife development at Mahoning 
Creek Lake was executed between the U.S. Government 
and the Pennsylvania Game Commission. Each party 
will pay or contribute in kind 50% of the first cost of initial 
wildlife development. Cost-sharing for construction of fishing 
access area awarded in September 1980 was completed in July 
1981 for $335,405.75. On June 7, 1979, a contract for fishing 
and boating development at Mahoning Creek Lake was executed 
between the U.S. Government and Pennsylvania Fish 
Commission. Each party will pay or contribute in kind 50% of 
the first costs of initial fishing and boating development. Costsharing 
contract for construction of hunting access areas 
awarded July 30, 1980 was completed on Nov 25, 1981 at a 
final cost of $44,540. On September 9, 1980, a contract for 
camping and day-use recreational development was executed 
between the U.S. Government and the County of Armstrong. 
Each party will pay or contribute in kind 50% of the first costs 
of initial camping and day-use recreational development and 
50% of the costs for future development. Cost-sharing contract 
for Construction of Milton Loop Recreation Area awarded July 
19, 1981 was completed on September 17, 1982 for $467,842. 
Each cooperation authority is responsible for operation, 
maintenance and replacement without cost to the Government 
of all facilities developed with their support. 
Operations and results during fiscal year. Operations 
and maintenance, general: Contract for concrete repairs, parapet 
walls and roadway, awarded on August 19, 1986 was completed 
for $470,891. Reservoir was operated for benefit of flood 
control as required, and necessary repairs were made to structures 
and appurtenances. Estimated flood damages prevented 
by this project for this fiscal year were $896,000; total benefits 
through Sept 30, 1989 were $156,256,000. Activities under 
reservoir management and maintenance for public-use facilities 
continued. 
19. MICHAEL J. KIRWAN DAM AND 
RESERVOIR, OH 
Location. Dam site is on West Branch of Mahoning River 
which joins Mahoning River at Newton Falls, OH. It is 11 
miles above mouth of branch and about 15 miles upstream 
from Warren, OH. Reservoir is in Portage County, OH. (See 
Geological Survey Charts for Ravenna, Garrettsville, Chagrin 
Falls, and Kent, OH.) 
Existing project. Reservoir provides flood control, lowwater 
regulation and recreation. Dam consists of a rolled-earth 
18-6

PITTSBURGH, PA., DISTRICT 
embankment structure with gate-controlled outlet works and 
an uncontrolled side-hill spillway through left abutment. Authorized 
project is completed and in operation for flood control 
and low water regulation purposes. Construction of dam and 
access road was started in May 1963 and completed in November 
1966. Land acquired for project consists of 6,298.9 acres fee 
and easements over 27.9 acres. For further description see 
Annual Report for 1962, page 1231 (West Branch Reservoir, 
Mahoning River, Ohio). Project was authorized by 1958 Flood 
Control Act (H. Doc. 191, 85th Cong. 1st sess.), with local 
contribution requirements modified by Flood Control Act of 
1960. Federal costs of completed project as $17,370,000. Local 
interests contributed $3,230,000 during period of construction 
bringing initial project cost to $20,600,000. 
Local cooperation. Local interests must contribute 
$5,200,000 for water pollution abatement and for municipal 
and industrial water supply purposes, of which $3,230,000 was 
paid in cash during construction. Unpaid balance at time project 
is placed in operation, $1,970,000, will be paid in cash at 
that time or on an annual basis. Of the unpaid balance of 
contributed funds due and payable, payment in full of Trumbull 
County's share in the amount of $663,040 has been received. 
Mahoning County elected to pay their share 
($1,306,960) in 50 annual installments of $50,323.32, including 
interest, and has paid $589,465.70 toward principal to date. 
Local interests have now contributed $4,482,505.70 towards 
total of $5,200,000 non-Federal costs. 
Operations during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood control 
and low-flow augmentation, as required, and necessary 
repairs were made to structures and appurtenances. Total 
flood control benefits for this reservoir through September 30, 
1989 are $84,127,000. Estimated flood control benefits 
achieved by this project for this fiscal year are $4,947,000. 
Activities under reservoir management program comprising 
sanitation measures, conservation, land management, and operation 
and maintenance of public-use facilities continued. 
20. MOSQUITO CREEK LAKE, OHIO 
RIVER BASIN, OH 
Location. Dam is on Mosquito Creek, 9 miles above junction 
of creek with Mahoning River at Niles, OH, and about 18 miles 
northwest of Youngstown, OH. (See Geological Survey Charts 
for Bristolville and Kinsman, OH, and Pennsylvania.) 
Existing project. A reservoir for flood control, low-water 
regulation and water supply storage. Dam is rolled-earthfill 
type with outlet facilities through dam, and an uncontrolled 
natural wasteway to discharge overflow from reservoir. Authorized 
project is complete and in operation for flood control 
and low-water regulation purposes in industrialized Mahoning 
and Beaver Valleys below. Construction of dam was started in 
July 1943 and was ready for beneficial use in January 1944. 
Land acquired for project consists of 11,180.6 acres in fees and 
easements over 276.0 acres. State of Ohio has a license from 
Secretary of the Army for development and operation of recreation 
facilities in reservoir area. Project was selected for construction 
under general authorization for Ohio River Basin in 
1938 Flood Control Act. For further project description see 
Annual Report for 1962, page 1228. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject to certain 
conditions of non-Federal cost-sharing under Federal 
Water Project Recreation Act of 1965. 
Operations during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of flood control 
and low-flow regulation as required, and necessary repairs 
were made to structures and appurtenances. Estimated flood 
control benefits achieved by this project for this fiscal year 
were $2,027,000. Total flood control benefits for this reservoir 
through September 30, 1989 were $64,042,000. Activities 
under reservoir management program comprising sanitation 
measures, conservation, land management and operation and 
maintenance of certain public-use facilities continued. This 
work was limited in scope as State of Ohio has jurisdiction over 
recreation in reservoir area. 
21. OHIO RIVER BASIN 
(PITTSBURGH DISTRICT) 
Location. A series of dikes, floodwalls, channel improvements, 
and reservoirs/lakes in Ohio River Basin within Pittsburgh 
District. 
Existing project. Individual projects considered in comprehensive 
plan within Pittsburgh District. (See Tables 18-B, 18- 
E and 18-K on Acts authorizing existing projects, local protection 
projects and reservoirs.) 
Operations during fiscal year. New work: None by the 
United States except as stated in individual projects. Completed 
local protection projects operated and maintained by 
local interests, including those projects for which individual 
reports have been included, prevented flood damages of an 
estimated $9,337,000 during this fiscal year. Total flood damages 
prevented through September 30, 1989 are $714,745,000. 
22. SHENANGO RIVER LAKE, OHIO 
RIVER BASIN, PA AND OH 
Location. Dam is on Shenango River about 0.8 mile above 
Sharpsville, PA, and about 33 miles above junction of river 
with Mahoning River, which unite near New Castle, PA, to 
form Beaver River. Reservoir is in Mercer County, PA and 
Trumbull County, Ohio. (See Geological Survey Chart for 
Kinsman, Ohio, and Shenango, PA.) 
Existing project. A reservoir for flood control, low-flow augmentation 
and recreation. Dam consists of a concrete gravity 
structure with gate-controlled outlet works and an uncontrolled 
center spillway section. Authorized project is complete. 
Reservoir is in operation for low-water regulation purposes in 
Shenango River valley below and for flood control as a unit of 
a coordinated reservoir system for protection of Shenango 
River valley and the Beaver and upper Ohio River Valley, 
generally. Construction of dam was started in March 1963 and 
completed in May 1965. Land acquired for project consists of 
14,482.8 acres in fee and easements over 197.7 acres. Future 
work consists of completion of project lands of any additional 
recreation facilities as required to serve the public needs. For 
further project description, see Annual Report for 1962, page 
1230. Project was authorized by 1938 Flood Control Act. 
Local cooperation. None required by law. 
Operations during fiscal year. Contract for maintenance 
building renovation, awarded in FY 88 for $139,500 was 98% 
complete. Contract for rehabilitation of Milligan Bridge was 
completed for $99,919. Reservoir was operated for benefit of 
flood control and low-flow augmentation, as required, and necessary 
repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved for FY 1989 were 
$1,670,000. Total benefits achieved by this project through 
September 30, 1989 were $21,053,000. Activities under reservoir 
management program comprising sanitation measures, 
conservation, land management and operation and maintenance 
continued. 
18-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
23. STONEWALL JACKSON LAKE, 
WV 
Location. In Lewis County, North Central West Virginia, 
on the West Fork River, which joins the Tygart River at Fairmont, 
West Virginia to form the Monongahela River. Damsite 
is located at Brownsville, West Virginia, about 4 miles south of 
Weston and 72 miles above mouth of West Fork River at Fairmont, 
WV. (See Geological Survey Charts for Weston and 
Crawford, WV.) 
Existing project. Provides for construction of a reservoir for 
flood control, water supply, water quality control, area redevelopment 
and recreation. Dam is concrete gravity type, 95 feet 
high and 620 feet long. Outlet works consist of five multi-level 
sluices, spillway is uncontrolled. Storage capacity is 74,650 
acre-feet controlling an area of 102 square miles. Project was 
authorized by 1966 Flood Control Act. Estimated initial Federal 
cost for new work (1989) is $231,000,000 (includes 
$29,160,000 reimbursement by non-Federal interests.) 
Local cooperation. Local interests are required to make 
arrangements for repayment, under the provisions of the 
Water Supply Act of 1958, as amended, of that part of the 
construction cost and annual operation, maintenance and replacement 
costs allocated to municipal and industrial water 
supply, an amount presently estimated at $4,350,000 for construction; 
and $15,000 annually for operations, maintenance 
and replacements. Also, in accordance with Federal Water 
Project Recreation Act, local interests are required to administer 
project land and water areas for recreation and fish and 
wildlife enhancement, pay, contribute in kind or repay (which 
may be through user fees) with interest, one-half of the separable 
first costs of the reservoir project allocated to recreation 
and fish and wildlife enhancement, an amount presently estimated 
at $24,810,000, bear all costs of operation, maintenance 
and replacement of recreation and fish and wildlife land and 
facilities, the amount involved being currently estimated on an 
average annual basis to be $457,000, exercise to the full extent 
of their legal capability, control against removal of streamflow 
made available for water quality control; and contribute to the 
control of pollution of streams subject to low-flow augmentation 
by adequate treatment or other methods of controlling 
wastes at their source. The requirements of Section 221 were 
amended in 1971 to exempt assurances for future demands for 
water supply pursuant to the Water Supply Act of 1958 from 
the contractual requirements of the Act. Accordingly, the city 
of Weston, West Virginia, has provided assurances that it will 
enter into a water supply contract with the Department of the 
Army within a period of time which will permit paying out the 
costs allocated to the water supply storage within the life of the 
project. A recreation cost-sharing contract, in accordance with 
the requirements of the Federal Water Project Recreation Act, 
P.L. 89-72, was executed by the State of West Virginia on 
March 27, 1977. Local cooperation assurances for recreation 
cost-sharing were executed by the Governor and Attorney General 
of West Virginia on May 29, 1973. In this connection, 
Section 8 ofP.L. 92-222 deleted the requirement that the State 
of West Virginia "hold and save the United States free from 
damages resulting from water rights claims due to construction 
and operation of the project." Legislation relieving 
Stonewall Jackson Lake, WV, project of the requirements of 
Section 221, P.L. 96-611 was contained in Water Resources 
Development Act of 1974 signed by the President on March 7, 
1974. 
Operations during fiscal year. New Work: Contract for 
Basic Park, Roanoke Bay recreation area, awarded in January, 
1988 for $11,036,089 was 90% complete. Contract for dam area 
facilities, awarded in June, 1988 for $2,758,130 was 70% complete. 
Contract for access road road repairs, awarded in January, 
1989 for $138,900 was 66% complete. 
Contracts awarded in September, 1989 included construction 
of Carrion Bay campground for $4,919,986 and design, 
furnish and install water temperature profile for $89,264. No 
physical work was accomplished on these contracts in FY 1989. 
Contracts completed during the fiscal year included: Carrion 
Bay recreation area for an estimated $1,370,435; Georgetown 
access area for $342,872; communication site, roads, trash 
boom and boat ramp for $497,844; Vandalia recreation area for 
$937,919; Jacksonville access area for $304,545; plugging oil 
and gas wells for $136,870; Glady Fork access area for 
$169,546; Carrion Bay - earthwork for $375,879 and plugging 
abandoned gas wells for $81,942. 
Surface land acquired for the project consists of 20,849 acres. 
Land acquisition, detailed engineering work and construction 
continued and all items of work were progressing on 
schedule. The overall completion date for the project is not 
scheduled pending agreement by the existing cost sharing 
partner to cost increases to the original agreed upon recreation 
program. Estimated flood control benefits achieved for this 
project for FY 89 were $9,454,000. Total flood control benefits 
for the reservoir through September 30, 1988 are $38,032,000. 
24. TIONESTA LAKE, OHIO RIVER 
BASIN, PA 
Location. Dam is on Tionesta Creek, 1.25 miles above junction 
of creek with Allegheny River at Tionesta, PA, and about 
78 miles northeast of Pittsburgh, PA. Reservoir is entirely in 
Forest County, PA. (See Geological Survey Charts for Tionesta, 
Tidioute and Sheffield, PA.) 
Existing project. A flood control reservoir dam of earthfill 
type with separate uncontrolled saddle spillway and tunnel 
outlet works. Authorized project is complete. Reservoir is in 
operation as a unit of a coordinated reservoir system designed 
for protection of Pittsburgh and reduction of flood heights in 
upper Ohio Valley, generally. Construction of dam was started 
in May 1938 and completed in January 1941. Land acquired for 
project consists of 2,797.3 acres in fee and easements over 13.1 
acres. Future work consists of provision on project lands of 
additional recreational facilities as required to serve public 
needs. Project was authorized by Flood Control Acts of 1936 
and 1938. For further project description see Annual Report for 
1962, page 1203. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and maintenance 
general: Contract for boat launch ramp and access road 
repairs, awarded for $473,526, was 98% complete. Reservoir 
was operated for benefit of flood control and low-flow augmentation, 
as required, and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this reservoir for this period were $1,270,000. 
Total flood control benefits for this reservoir through September 
30, 1989 were $173,273,000. Activities under reservoir 
management program comprising sanitation measures, conservation, 
land management and operation and maintenance 
of public-use facilities continued. 
25. UNION CITY DAM, PA 
Location. In Erie County, northwestern Pennsylvania, on 
French Creek, a tributary of Allegheny River. Damsite is 24 
miles upstream from Cambridge Springs, PA, and 41 miles 
upstream from Meadville, PA. (See Geological Survey Chart 
for Union City, PA - NY.) 
18-8

PITTSBURGH, PA., DISTRICT 
Existing project. A flood control reservoir dam of earth 
embankment nongated type with uncontrolled side-channel 
spillway. Outlet works consist of a lower outlet located in valley 
floor constructed of reinforced concrete conduit 8 feet by 4.5 
feet and an upper outlet consisting of an uncontrolled slot 9.5 
feet wide through the north end of the ogee weir in the spillway. 
Dam is 1,420 feet long at top rising 88 feet above 
streambed and provides gross capacity of 47,640 acre-feet from 
a drainage area of 222 square miles. Project authorization was 
modified to provide for a conservation pool and addition of 
recreation facilities. On November 5, 1974, a referendum proposal 
was defeated by the constituents of Erie County in regard 
to the cost-sharing for construction of recreation facilities. In 
view of the foregoing, all action toward implementation of the 
authorized project modification was discontinued. Reservoir is 
operated as one of a two-reservoir system for reduction of flood 
stages in French Creek Basin between damsite and mouth, 
Allegheny River from Franklin, PA, to Pittsburgh, PA, inclusive, 
and upper Ohio River Valley. Initial highway relocations 
were completed in October 1968 and remaining highway relocations 
were completed in May 1972. Construction of the dam 
was started in July 1968 and completed in September 1971. 
Land acquired for project consists of 161.4 acres in fee and 
easements over 2,410.3 acres. Existing project was authorized 
by 1962 Flood Control Act. 
Local cooperation. Local interests are required to inform 
affected interests in French Creek Basin at least annually, 
that the system of reservoirs of which Union City Dam is a 
part, will not provide protection against maximum floods. 
November 10, 1964 the Department of Forests and Waters of 
the Commonwealth of Pennsylvania furnished formal assurances 
of local cooperation in respect to notifying local interests 
at least annually that the system of reservoirs will not provide 
protection against maximum floods. A referendum on the ballot 
during the November 1974 election regarding the approval 
to cost-share the maintenance of a summer pool was defeated 
by the local voters. 
Operations during fiscal year. Operation and maintenance, 
general: Contract to install sluice gate intake structure 
was completed during the fiscal year for $42,198. Maintenance 
of the structure and appurtenances was performed as required. 
This dam acted as an uncontrolled detention type dam during 
the fiscal year. Estimated flood control benefits achieved by 
this reservoir for this period were $385,000. Total flood control 
benefits for this reservoir through September 30, 1989 were 
$14,875,000. 
26. WOODCOCK CREEK LAKE, PA 
Location. In Crawford County, northwestern Pennsylvania, 
on Woodcock Creek, a tributary of French Creek. Damsite is 
about 4.1 miles above mouth of Woodcock Creek and about 5 
miles northeast of Meadville, PA. (See Geological Survey 
Chart for Meadville, PA.) 
Existing project. A flood-control reservoir dam of rolledearth 
embankment type, gate-controlled outlet works with a 6 
foot-wide by 7.75 foot-high conduit and uncontrolled saddle 
spillway on the left abutment. Dam is 4,650 feet long at top 
rising 90 feet above streambed and provides for gross capacity 
of 20,000 acre-feet from a drainage area of 46 square miles. 
Reservoir is operated as one of a two-reservoir system for reduction 
of flood stages in French Creek Basin between damsite 
and mouth. Allegheny River from Franklin, PA, to Pittsburgh, 
PA, inclusive, and upper Ohio River Valley. Authorized project 
is complete. Construction of dam was started in July 1970 and 
completed in July 1973. Land acquired for project consists of 
1,731.5 acres in fee and easements over .56 acres. Project was 
authorized for flood control and recreation by 1962 Flood Control 
Act. Storage for water quality control was added to the 
project during the preconstruction planning stage. 
Local cooperation. Local interests must inform affected 
interests in French Creek Basin at least annually, in a manner 
satisfactory to District Engineer, that a system of reservoirs of 
which Woodcock Creek is a part, will not provide protection 
against maximum floods. Pennsylvania Department of Forests 
and Waters assumed responsibility of local cooperation for 
project. 
Operations during fiscal year. Operation and maintenance, 
general: Maintenance of the structure and appurtenances 
was performed as required. Contract for access road and 
pump station repairs was completed for $44,270. Estimated 
flood control benefits achieved by this project for FY 89 were 
$85,000. Total flood control benefits achieved by this reservoir 
through September 30, 1989 were $1,695.000. 
27. YOUGHIOGHENY RIVER LAKE 
OHIO RIVER BASIN, PA AND MD 
Location. Dam is on Youghiogheny River about 74.2 miles 
above its junction with Monongahela River at McKeesport, 
PA. It is 1.2 miles upstream from Confluence, PA, and about 57 
miles southeast of Pittsburgh, PA. Reservoir is in Fayette and 
Somerset Counties, PA, and Garrett County, MD. (See Geological 
Survey Charts for Confluence, PA, Accident, MD, West 
Virginia and Pennsylvania.) 
Existing project. Reservoir for flood control, low-flow augmentation, 
and pollution abatement purposes. Dam is rolledearthfill 
type with separate uncontrolled side channel spillway 
and tunnel outlet works. Authorized project is complete. For 
flood control, reservoir is operated as a unit of a coordinated 
reservoir system designed for protection of Pittsburgh and reduction 
of flood heights in upper Ohio Valley, generally. Construction 
of dam was started in June 1940 and completed May 
1944. Land acquired for project consists of 3,914.9 acres in fee 
and easements over 0.62 acre. A license was issued Commonwealth 
of Pennsylvania covering fish conservation and management 
in Pennsylvania portion of reservoir. Future work 
consists of provision on project lands of additional recreational 
and sanitary facilities as required to serve the public needs. 
Project was selected for construction under general authorization 
for Ohio River Basin in 1938 Flood Control Act. For further 
project description see Annual Report for 1962, page 1223. 
Local cooperation. None required. 
Operations during fiscal year. Contract for road/bridge 
improvements - Mill Run and Tub Run, awarded for $290,854 
was 98% complete at the end of the fiscal year. Contracts completed 
during the fiscal year include concrete repairs to air 
shaft and control tower for $585,641 and revisions to water 
system for $55,515. Reservoir was operated for benefit of flood 
control, as required, and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this reservoir for this period were $2,086,000. 
Total flood control benefits achieved by this project through 
September 30, 1989 were $153,897,000. Activities under reservoir 
management program comprising sanitation measures, 
conservation, land management and operation and maintenance 
of public use facilities continued. 
28. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent acts 
require local interests to furnish assurances that they will 
18-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
maintain and operate certain local protection projects after 
completion in accordance with regulations prescribed by Secretary 
of the Army. District Engineers are responsible for administration 
of these regulations within boundaries of their respective 
districts. Inspections were made of completed units 
transferred to local interests for maintenance and operation 
and local interests were advised, as necessary, of measures 
required to maintain these projects in accordance with standards 
prescribed by regulations. (See Table 18-L for dates of 
inspections.) 
Costs for this fiscal year, $69,018. Total cost to September 
30, 1989 was $1,143,620. 
29. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 18-E on other authorized flood control projects. 
30. FLOOD CONTROL WORKS UNDER 
SPECIAL AUTHORIZATION - 
For flood control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization) 
See Table 18-M. 
For emergency bank protection (Sec. 14 of 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
See Table 18-M. 
Flood control and coastal emergencies (Public Law 99, 
84th Cong., and antecedent legislation.) 
Corps Statutory Authorities $168,952 
Activities in Support of Others 12,567 
Facilities 5,478 
Inspections 13,202 
Total Cost for Fiscal Year: $200,199 
General Investigations 
31. SURVEYS 
Navigation studies 
Flood control studies 
Coordination with other agencies 
Review for Deauthorization 
Interagency Water Resource Development 
Special investigations 
Federal Energy Regulatory Commission 
Total cost for fiscal year 
$ 99,680 
1,378,008 
80,209 
87 
19,999 
112,023 
51,428 
$1,741,434 
32. COLLECTION AND STUDY OF 
BASIC DATA 
Costs this fiscal year were $233,947 for flood plain management 
services and $9,478 for related hydrologic studies. 
33. PRECONSTRUCTION 
ENGINEERING AND DESIGN 
Saw Mill Run, Pittsburgh, PA $176,612 
34. RESEARCH AND DEVELOPMENT 
None. 
18-10

PITTSBURGH, PA., DISTRICT 
TABLE 18-A COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 1989 
Navigation - Locks and Dams 
1. Allegheny River 
PA 
3. Monongahela 
River, PA and 
WV 
5. Tygart Lake, 
WV 
Flood Control - Local Protection 
7. Chartiers 
Creek, PA 
(Federal Funds) 
(Contributed 
Funds) 
8. Elkins, WV 
9. Johnstown, PA 
10. Punxsutawney, 
Ohio River 
Basin, PA 
11. Turtle Creek, 
PA 
Flood Control - Reservoirs 
12. Berlin Lake 
Ohio River 
Basin, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - - 18,157,8601 
S- - - 18,157,8601 
4,975,000 5,985,100 7,578,300 7,375,589 79,275,3512 
4,986,772 5,905,479 7,649,246 7,318,418 79,185,5622 
400,000 3,323,000 9,436,000 17,218,000 159,580,0853 
209,436 3,080,973 7,334,873 17,718,346 157,546,7134 
9,721,852 11,813,800 11,350,400 11,866,029 181,186,6355 
10,063,705 11,727,436 11,441,627 11,873,521 181,086,6346 
- - - 15,857,000 
7 221 - - 15,857,000 
- - - - 19,077,9327 
- - - - 19,077,9327 
726,400 873,300 711,000 699,244 11,046,7838 
741,774 846,746 750,871 688,409 11,024,3198 
5,134 
3,500 
2,838 
7,000 
7,098 
8,000 
8,346 
15,000 
14,951 
- - - 26,586,186 
- - - 26,560,187 
- - - 4,225,188 
- - -4,204,498 
- - 1,772,627 
- - - 1,772,627 
21,000 5,000 5,000 262,987 
10,372 16,083 3,704 260,958 
- - - 8,865,3889 
- - - 8,865,3889 
84,000 452,500 236,533 4,583,238 
50,417 483,915 211,155 4,555,492 
- - - 3,586,10710 
- - - 3,586,10710 
7,000 
2,679 
78,000 
22,239 
5,000 
9,254 
174,000 
34,901 
4,000 
1,247 
130,000 
254,486 
1,038,88811 
1,035,96011 
15,747,352 
15,676,92938 
- - - - 8,739,98712 
- - - - 8,739,98712 
1,366,700 1,204,900 1,688,900 1,517,900 19,300,68313 
1,397,114 1,238,771 1,668,230 1,498,246 19,227,53013 
18-11 
---- -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 1989 
13. Conemaugh 
River Lake, Ohio 
River Basin, PA 
14. Crooked Creek 
Lake, Ohio 
River Basin, PA 
15. East Branch, 
Clarion River 
Lake, Ohio 
River Basin, PA 
16. Kinzua Dam and 
Allegheny 
Reservoir, Ohio 
River Basin, PA 
and NY 
17. Loyalhanna 
Lake, Ohio River 
Basin, PA 
18. Mahoning Creek 
Lake, Ohio 
River Basin, PA 
19. Michael J. Kirwan 
Dam and 
Reservoir, Ohio 
River Basin, OH 
20. Mosquito Creek 
Lake, Ohio River 
Basin, OH 
21. Ohio River Basin 
Pittsburgh, PA 
District 
Consolidated 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
717,000 
880,435 
43,001 
- - - 46,012,41114 
- - - 46,012,41114 
900,000 973,675 868,671 10,008,250 
763,414 1,120,111 847,810 9,966,442 
- - - 4,474,52416 
- - - 4,431,523'15 
2,619,000 3,003,400 1,595,200 1,383,449 18,362,97016 
2,701,478 2,775,020 1,829,431 1,391,136 18,326,55516 
- - - - 9,539,58617 
- - - - 9,539,58617 
539,482 728,300 817,300 804,600 9,588,05718 
514,479 712,557 840,411 819,123 9,570,16918 
- - - - 109,309,07619 
- - - - 109,298,20519 
1,083,000 
1,115,419 
-100,000 
230,032 
1,137,900 
1,095,568 
-200,000 
8,928 
1,178,200 1,133,200 17,944,578 
1,235,576 1,111,672 17,915,762 
- - 2,940,000 
- 279 2,920,558 
- - - - 5,727,53120 
- - - - 5,727,53120 
953,700 1,120,000 968,300 880,449 13,241,00521 
999,266 1,047,093 1,054,219 872,417 13,215,16921 
.=- - -=.. 
- - 6,104 
650,200 909,000 715,100 
656,660 829,775 813,086 
0 7,144,97322 
55 7,144,97323 
720,708 9,723,324 
733,871 9,714,660 
- - - - 47,033 
- - - - 47,033 
- - - - 17,376,09724 
- - - - 17,376,09724 
655,500 596,100 577,700 735,300 8,894,39625 
652,378 605,411 575,593 710,880 8,856,33425 
- - - - 4,253,02926 
S- - - 4,253,02926 
683,000 795,900 758,900 824,400 8,824,064 
672,132 815,130 766,515 815,786 8,802,547 
- - - - 985,19727 
- - - - 985,19727 
18-12

PITTSBURGH, PA., DISTRICT 
TABLE 18-A COST AND FINANCIAL STATEMENT 
(Continued) 
See Total Cost to 
Section Sep 30, 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 1989 
22. Shenango River New Work 
Lake, Ohio River Approp. - - - - 40,227,20128 
Basin, PA Cost - - - - 40,209,89428 
Maint. 
Approp. 2,019,000 2,045,000 2,019,200 1,812,800 22,517,61729 
Cost 2,068,686 1,890,645 2,148,985 1,872,160 22,488,51829 
23. Stonewall Jackson New Work 
Lake, Ohio Approp. 24,106,000 16,913,000 23,259,000 2,428,000 202,316,200 
River Basin, WV Cost 25,450,413 15,713,411 13,372,446 12,400,043 200,641,199 
Maint. 
Approp. - 25,500 631,000 749,800 1,406,300 
Cost - - 643,529 758,230 1,401,759 
24. Tionesta Lake, New Work 
Ohio River Approp. -32,403 - 0 0 7,792,37830 
Basin, PA Cost - - 3,770 230 7,792,37981 
Maint. 
Approp. 1,060,000 1,010,500 1,263,800 1,308,979 14,847,23232 
Cost 1,074,808 951,589 1,320,359 1,316,393 14,815,18032 
25. Union City New Work 
Dam, Ohio Approp. - - - - 14,559,800 
River Basin, PA Cost - - - - 14,559,800 
Maint. 
Approp. 512,000 434,900 276,249 244,547 3,978,364 
Cost 528,818 451,946 264,569 262,236 3,971,444 
26. Woodcock Creek New Work 
Lake, Ohio Approp. 5,376 - - - 20,553,47433 
River Basin, PA Cost 137,846 6,497 - - 20,545,06534 
Maint. 
Approp. 749,000 621,800 626,298 775,600 7,201,96935 
Cost 751,253 622,437 654,790 769,170 7,185,71435 
27. Youghiogheny New Work 
River Lake Approp. -10,959 - - - 12,521,16736 
Ohio River Cost 2,334 - - - 12,521,16736 
Basin, PA and Maint. 
MD Approp. 2,602,000 1,722,600 1,426,978 2,271,800 21,953,76537 
Cost 2,409,684 1,837,361 1,506,348 2,287,890 21,907,54737 
1. Includes $2,453,737 from emergency relief funds and 
$1,250,049 from public works funds. 
2. Includes $64,365 public works acceleration, executive 
funds (1963) and $191,400 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
3. Includes $5,420,541 for new work for previous projects, 
$4,657,000 appropriated to date for Pt. Marion, L/D 8, PA 
($2,192,000 - CG funds, $2,465,000 from the Inland Waterways 
Trust Fund), and $25,720,000 appropriated to date for 
Grays Landing, L/D 7, PA ($12,397,000 - CG funds, 
$13,323,000 from the Inland Waterways Trust Fund). Also 
inclues AE & D costs from Gray's Landing ($803,000) and Pt. 
Marion ($618,758). 
4. Includes $423,301 expended to date on Point Marion, 
L/D 8, PA ($2,098,973 - CG Funds, $2,324,328 from the Inland 
Waterways Trust Fund), and $23,920,327 expended to 
date for Grays Landing, L/D 7, PA ($12,100,406 - CG funds, 
$11,819,921 from the Inland Waterways Trust Fund). Also 
includes AE & D costs for Gray's Landing ($803,000) and Pt. 
Marion ($618,758). 
5. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$582,000 provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds. 
6. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$464,508 provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds. 
7. Includes $1,999,995 emergency relief funds, 
$10,000,000 public work funds, $234,000 Code 711 funds and 
$412,088 Code 713 funds; excludes $409,622 contributed by 
local interest. 
8. Includes $89,000 provided from the Productive Employment 
Appropriations, Act (PL 98-8) 1983 funds. 
9. Includes $33,423 from emergency relief funds. 
10. Excludes $180,485 for new work expended from contributed 
funds. 
11. Includes $283,988 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
18-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18A-A COST AND FINANCIAL STATEMENT 
(Continued) 
12. Includes $1,542,500 Code 711 funds, $809,700 Code 
712 funds and $99,111 Code 713 funds; excludes $100,000 
contributed by local interest. 
13. Includes $40,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
14. Includes $5,351 from emergency relief funds and 
$328,000 Code 711 funds. 
15. Includes $63,788 from emergency relief funds and 
$269,635 Code 711 funds. 
16. Includes $45,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
17. Includes $156,812 Code 711 funds. 
18. Includes $322,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
19. Includes $2,791 from emergency relief funds, $14,622 
Code 711 funds and $568,265 Code 713 funds; excludes 
$389,370 contributed by local interest. 
20. Includes $7,339 from emergency relief funds and 
$274,669 Code 711 funds. 
21. Includes $256,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
22. Includes $25,671 emergency relief funds, $162,381 
Code 711 funds and $561,247 Code 713 funds; excludes 
$500,086 contributed by local interests. 
23. Includes $25,671 emergency relief funds, $162,381 
Code 711 funds and $561,247 Code 713 funds; excludes 
$456,611 contributed by local interests. 
24. Includes $74,900 Code 711 funds; excludes 
$4,482,505.70 for new work contributed by local interest. 
25. Includes $315,500 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
26. Includes $122,729 Code 711 funds and $94,900 Code 
713 funds. 
27. Includes $8,914 from emergency relief funds. 
28. Includes $1,730,100 Code 711 funds and $1,618,300 
Code 713 funds. 
29. Includes $152,000 provided from the Productive Employment 
Appropriations Act. (PL 98-8) 1983 funds. 
30. Includes $2,303,076 Code 711 funds ($256,760 provided 
from the Productive Employment Appropriations Act 
PL 98-8, 1983 funds), $275,900 Code 712 funds, and $24,201 
emergency relief funds. 
31. Includes $2,303,077 Code 711 funds, ($256,531 provided 
from the Productive Employment Appropriations Act 
PL 98-8, 1983 funds), $275,900 Code 712 funds, and $24,201 
emergency relief funds. 
32. Includes $203,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
33. Includes $1,679,774 Code 711 funds. 
34. Includes $1,671,366 Code 711 funds. 
35. Includes $85,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds). 
36. Includes $2,846,263 Code 711 funds ($293,000 provided 
from the productive Employment Appropriations Act. 
(PL 98-8) 1983 funds). 
37. Includes $591,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
38. Includes $15,350,352 original construction cost. 
18-14

PITTSBURGH, PA., DISTRICT 
TABLE 18-B AUTHORIZATION LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
Aug 5, 1886 
June 3, 1896 
July 25, 1912 
July 3, 1930 
Aug 30, 19351 
Aug 30, 19351 
June 26, 19342 
Mar 3, 1899 
June 13, 1902 
Mar 3, 1905 
Mar 3, 1905 
Mar 2, 1907 
Mar 4, 1913 
Sep 22, 1922 
July 3, 1930 
Jan 31, 19313 
June 26, 19342 
ALLEGHENY RIVER, PA. (See Section 1 of Text) 
For lock and dam 1. (Fixed dam contemplated. Sep 29, 1891 
Secretary of War authorized change to a movable dam.) 
For locks and dams 2 and 3. 
For locks and dams 4 to 8 inclusive. 
For a depth of 9 feet in the lower 61 miles. 
Replace lock and dam 1 by a dredged channel, 9 feet deep 
and 200 feet wide up to lock 2, and construct new locks 
and dams 2 and 3, to replace existing locks and dams 2 
and 3. 
Construct lock and dam 9, raising crest of dam 8, and dredging 
a navigable channel to head of pool 8. 
Operation and care of locks and dams provided for with funds 
from War Department appropriation for rivers and harbors. 
MONONGAHELA RIVER, PA AND WV 
Enlarge and improve lock and dam 6; additional works at 
lock 3; new repair steamer and new dredge boat with 
equipment; all at an estimated cost of $185,556. 
Rebuild lock and dam 2 at estimated cost of $655,961. 
(Estimate increased in 1910 to $698,961.) 
Acquisition of land and additional improvements at 5 and 6 
at a cost of $7,850. 
Rebuild lock and dam 3 at estimated cost of $589,196. 
Reconstruct lock and dam 5 at estimated cost of $756,042. 
Reconstruct lock and dam 6 at estimated cost of $356,400. 
(Estimate increased in 1916 to $418,860.) 
Additional improvements at estimated cost as follows: 
Guide walls and guard walls, 1 to 6, $1,255,130; 
Lengthen land chamber of lock 3 to 720 feet, $787,722; 
New chamber (360 feet long), lock 4, $699,786; 
Lock and dam 7, $1,161,241; Lock and dam 8, $1,165,758; 
Lock and dam 7 (second chamber), $419,126; 
Lock and dam 8 (second chamber), $504,465; 
Reconstruction dam 4, $397,211; Marine ways, repair 
plant, office and warehouse, $250,000, for a total of 
$6,640,439. 
Construct new locks and dam 2.5 miles below existing structure, 
at estimated cost of $2,175,000 in lieu of work authorized 
at old lock and dam 4. 
Chief of Engineers authorized to locate new locks and dam 4 
above existing structure and on such site as they may 
deem most desirable. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
18-15 
Annual Report 1886, 
p. 1545, 
Annual Report 1891, 
p. 2366 
H. Doc. 204, 54th Cong., 
1st Sess., and Annual 
Report 1896, p. 2212 
H. Doc. 540, 62d Cong., 
2d Sess. 
H. Doc. 356, 71st Cong., 
2d Sess. 
Rivers and Harbors 
Committee, Doc. 16, 
72d Cong., 1st Sess. 
H. Doc. 721, 71st Cong., 
3d Sess., and Rivers and 
Harbors Committee, Doc. 
27, 73d Cong., 2d Sess. 
Annual Report 1897, 
p. 2423 
Annual Report 1909, 
p. 1756 
Annual Report 1904, p. 460 
H. Doc. 209, 58th Cong., 
2d Sess. 
H. Doc. 209, 58th Cong., 
2d Sess. 
H. Doc., 1217, 62d Cong., 
3d Sess. 
H. Doc. 288, 67th Cong., 
2d Sess. 
Rivers and Harbors 
Committee, Doc. 22, 70th 
Cong., 
2d Sess. 
3.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-B AUTHORIZATION LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jan 11, 1934 
Aug 30, 1935 
Jun 28, 1938 
Jun 28, 1938 
Jun 28, 1938 
3. May 17, 1950 S. Doc. 100, 81st Cong., 
1st Sess. 
Modification of existing project as follows: 
Provide 2 new locks and dams similar to Morgantown lock 
and dam to replace existing locks and dams 12 to 15 inclusive. 
Provide a movable crest on existing dam 8 to raise existing 
pool-full elevation 4 feet. 
Provide a navigation channel of 300-foot minimum bottom 
width and a 9-foot project depth above lock and dam 8. 
Provide an extension of navigable channel of upper Monongahela 
River, into lower Tygart River for 2.1 miles at a 
maximum bottom width of 200 feet and a 9-foot project 
depth. 
Construct new lock and dam 7 (Grays Landing Lock and 
Dam) as follows: 
The Grays Landing Lock and Dam will be located 3.0 miles 
downriver from existing Lock and Dam 7. It will consist of 
a single lock chamber, 84 feet wide by 720 feet long, with a 
fixed crest dam 576 feet in length. The existing Maxwell 
Pool at elevation 763.0 will be shortened three miles and 
the existing Pool 7 at elevation 778.0 will be extended 
downriver to the new dam. There will be no change in pool 
elevation above existing Dam 7. Upon completion of the 
new replacement lock and dam, existing Lock and Dam 7 
will be removed. Total authorized cost is $123,000,000. 
Replace existing 56' x 360' lock chamber at Point Marion 
Lock and Dam (Lock and Dam 8) with new 84' x 720' 
chamber. Existing movable crest dam to remain; no change 
in pool elevations. Total authorized cost is $82,900,000. 
TYGART RIVER LAKE, WV 
Construction of a dam and reservoir for low water regulation 
and flood control 
ELKINS, WV 
For construction of local flood protection projects. 
JOHNSTOWN, PA 
For construction of local flood protection projects. 
PUNXSUTAWNEY, OHIO RIVER BASIN, PA 
For construction of local flood protection projects. 
18-16 
Supplemental Appropriations 
Act of 1985 for Engineering 
and Design 
and Land Acquisition 
and Water Resources Development 
Act of 1986; 
Public Law 99-662 Sec. 
301(a). 
Supplemental Appropriations 
Act of 1985 for Engineering 
and Design 
and Land Acquisition 
and Water Resources Development 
Act of 1986; 
Public Law 99-662 Sec. 
301(a). 
H. Doc. 1792, 64th Cong. 
2nd Sess. 
H. Doc. 106, 76th Cong. 
1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 306, 74th Cong. 1st 
Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Nov 17, 1986 
5. 
8. 
9. 
10.

PITTSBURGH, PA., DISTRICT 
TABLE 18-B 
(Continued) 
AUTHORIZATION LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
12. 
Jun 28, 1938 
13. 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
modified by 
Aug 18, 1941 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
BERLIN LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Construction, operation & maintenance of recreation facilities. 
CONEMAUGH RIVER LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
CROOKED CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
EAST BRANCH CLARION RIVER LAKE, 
OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Construction, operation & maintenance of recreation facilities. 
KINZUA DAM AND ALLEGHENY RESERVOIR, 
OHIO RIVER BASIN, PA AND NY 
Construction of a dam and reservoir for flood control and low 
water regulation and recreation. 
Construction of a dam and reservoir for flood control, pollution 
abatement, low water regulation and recreation. 
Construction, operation & maintenance of recreation facilities. 
LOYALHANNA LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
MAHONING CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
18-17 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 300, 76th Cong. 
1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
14. 
15. 
16. 
17. 
18.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-B 
(Continued) 
AUTHORIZATION LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
20. 
19. 
Jul 3, 1958 
Jul 14, 1960 
Jun 28, 1938 
Dec 22, 1944 
as amended, 
Aug 28, 1937 
Jun 28, 1938 
Aug 18, 1941 
Dec 22, 1944 
Jul 24, 1946 
May 17, 1950 
Dec 30, 1963 
Jun 18, 1965 
May 12, 1967 
Aug 13, 1968 
Jun 19, 1970 
Mar 7, 1974 
Oct 22, 1976 
18-18 
MICHAEL J. KIRWAN DAM AND RESERVOIR, OH 
Construction of a dam and reservoir for flood control, water 
supply, low water, regulation and recreation. 
To define cost-sharing arrangement for municipal & industrial 
water supply & water for pollution abatement purposes. 
MOSQUITO CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control, low 
water regulation and water supply storage. 
Construction, operation & maintenance of recreation facilities. 
OHIO RIVER BASIN - Pittsburgh District 
Construct levees, floodwalls, and drainage structures for protection 
of cities and towns in Ohio River Basin. Projects to 
be selected by Chief of Engineers with approval of Secretary 
of War at a cost not to exceed $24,877,000 for construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable in 
discretion of Secretary of War and Chief of Engineers, and 
for initiation and partial accomplishment of plan, authorized 
$75 million for reservoirs and $50,300,000 for local 
flood protection works. 
Additional $45 million for prosecution of comprehensive plan 
for Ohio River Basin. 
Additional $70 million for further prosecution of comprehensive 
plan for Ohio River Basin, including additional 
projects in tributary basins. 
Additional $125 million for further prosecution of comprehensive 
plan including additional projects in tributary 
basins. 
Additional $100 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $150 million for further prosecution of comprehensive 
plan for flood control and other purposes in Ohio 
River Basin. 
Additional $89 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $38 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $35 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $69 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $120 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Authorized phase I design memorandum stage of advanced 
engineering and design of the project for abatement of acid 
mine drainage in the Clarion River Basin, Pa. 
H. Doc. 191, 85th Cong. 
1st Sess. 
Pub. Law 86-645 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
Flood Control Committee, 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Committee, 
Doc. 1, 75th Cong., 
1st Sess. 
H. Doc. 300, 76th Cong. 
1st Sess. 
H. Doc. 762, 77th Cong. 
2d Sess. 
H. Doc. 506, 78th Cong. 
1st Sess. 
S. Doc. 20, 81st Cong. 
1st Sess. 
Public Law 88-253, 
88th Cong., 1st Sess. 
H. Doc. 6755, 89th Cong., 
90th Cong. 1st Sess. 
Public Law 90-17. 
90th Cong., 1st Sess. 
Public Law 90-483, 
90th Cong., 2d Sess. 
H. Doc. 15166, 91st Cong., 
2d Sess. 
H. Doc. 10203, 93rd Cong. 
River Basin Monetary 
Authorization Act of 
1974. 
Water Resources Development 
Act of 1976; Public 
Law 94-587, Sec. 101(a). 
21.

PITTSBURGH, PA., DISTRICT 
TABLE 18-B AUTHORIZATION LEGISLATION 
(Continued) 
See Date 
Seetlon Authorizing 
in Text Act Project and Work Authorized Documents 
22. SHENANGO RIVER LAKE, OHIO RIVER BASIN, PA AND OH 
Jun 28, 1938 Construction of a dam and reservoir for flood control, low H. Doc. 306, 74th Cong. 
water regulation and recreation. 1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facili- Sec. 4, Flood Control Act of 
as amended ties. 1944 
23. STONEWALL JACKSON LAKE, WV 
Nov 7, 1966 Construction of a dam and reservoir for flood control, water S. Doc. 109, 89th Cong. 
supply, water quality control, area redevelopment and 2nd Sess. 
recreation. 
24. TIONESTA LAKE, OHIO RIVER BASIN, PA 
Jun 22, 1936 Construction of a dam and reservoir for flood control and low H. Doc. 306, 74th Cong. 
amended by water regulation. 1st Sess. 
Jun 28, 1938 FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facili- Sec. 4, Flood Control Act of 
as amended ties. 1944 
25. UNION CITY DAM, PA 
Oct 23, 1962 Construction of a dam and reservoir for flood control. S. Doc. 95, 87th Cong. 
2nd Sess. 
26. WOODCOCK CREEK LAKE, PA 
Oct 23, 1962 Construction of a dam and reservoir for flood control, recre- S. Doc. 95, 87th Cong. 
ation and storage for water quality control. 2nd Sess. 
27. YOUGHIOGHENY RIVER LAKE, OHIO RIVER BASIN, 
PA AND MD 
Jun 28, 1938 Construction of a dam and reservoir for flood control, low- H. Doc. 306, 74th Cong. 
flow augmentation, and pollution abatement, purposes. 1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facili- Sec. 4, Flood Control Act of 
as amended ties. 1944 
1. Included in the Emergency Relief program 
April 8, 1935. 
2. Permanent Appropriations Repeal Act. 
3. Public Res. 117, 71st. Cong., 3d Sess. 
18-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6 of Text) 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allegheny River, PA, open-channel work Completed 1934 197,000 133,940 
Beaver and Mahoning Rivers, PA and 
OH1 4 Inactive 1938 - - 
Buckhannon River, WV2 3 Completed 1893 5,500 - 
Cheat River, WV2 3 Completed 1895 12,997 
Pittsburgh Harbor, PA Completed 1922 110,663 81,613 
1. January 23, 1939, Chief of Engineers recommended constructing 
a waterway from Ohio River through Beaver, Mahoning, 
and Grand River Valleys to Lake Erie (H. Doc. 178, 76th 
Cong., 1st Sess.) 
2. Abandonment recommended in H. Doc. 467, 69th Cong., 1st 
Sess. 
3. No Commerce reported. 
4. Eligible for deauthorization. 
18-20

PITTSBURGH, PA., DISTRICT 
TABLE 18-E 
Project and S 
Flood Protection 
Specifically Authorized Projects 
Completed: 
Bradford, PA 
Brookville, PA 
Buckhannon, WV 
Butler, PA 
DuBois, PA 
Elkins, WV6 
Girty's Run, Millvale, PA4 
Johnsonburg, PA 
Johnstown, PA6 
Kittanning, PA, Part I 
Latrobe, PA 
Latrobe, PA 
Olean, NY 
Portage, PA 
Portville, NY 
Punxsutawney, PA6 
Reynoldsville, PA 
Ridgeway, PA (Elk Creek) 
Root Creek, Bolivar, NY 
Salamanca, NY 
Turtle Creek, PA5 
Washington, PA 
Wellsville, OH, Section I 
Wellsville, OH, Section II 
Youngstown, OH 
Active: 
Saw Mill Run, PA 
Inactive: 
Uniontown, PA 1 
Deferred: 
Benwood, WV 
Authorized by Chief of Engineers 
Completed: 
Amsterdam, OH 
Big Run, PA 
Burgettstown, PA 
Friendsville, MD 
Granville, PA 
Leetonia, OH 
Oil City, PA 
Slovan, PA 
Sykesville, PA 
Tarentum, PA 
Tenmile Creek at Marianna, PA 
Wilmore, PA 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects Not Specifically Identified in Text) 
For Last Cost to September 30, 1989 
Full Report 
See Annual Construction Non-Federal Opel 
tatus Report For (Federal Cost) Cost MaJ 
1962 
1963 
1972 
1970 
1979 
1986 
1958 
1949 
1951 
1970 
1954 
1965 
1954 
1959 
1964 
1986 
1972 
1972 
1964 
1956 
1956 
1976 
1956 
1954 
1964 
1965
- 
1964 
1981 
7,601,763 
964,976 
1,568,661 
1,556,181 
4,465,200 
1,772,627 
2,659,263 
674,664 
8,865,388 
130,317 
207,659 
2,556,652 
3,217,531 
150,386 
2,070,484 
3,586,107 
385,494 
628,888 
1,591,436 
2,880,535 
15,676,979 
789,093 
483,910 
157,633 
3,621,134 
- 
40,000 
130,000 
2,000 
49,400 
597,000 
353,000 
180,485 
72,000 
113,000 
81,028 
183,072 
364,208 
83,129 
41,529 
75,908 
89,299 
43,595 
57,811 
184,246 
136,591 
1,554,428 
96,853 
18-21 
ration and 
intenance

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Construction Non-Federal Operation and 
Project and Status Report For (Federal Cost) Cost Maintenance 
Active: 
Ridgeway & Vicinity (on Clarion River)3 1979 132,464 - - 
Inactive: 
Black Fork at Hendricks, WV 1972 6,800 - - 
Oakdale, PA - 14,127 - - 
Rouseville, PA -1,642 - - 
Wallace, WV2 - 11,035 - - 
Weston Mills, Olean, NY - 50,100 - - 
Weston Mills, Portville, NY - 52,100 - - 
Reservoirs 
Inactive: 
Eagle Creek Reservoir, OH - 100,000 - - 
Other: 
Rowlesburg Lake, WV 1977 2,857,575 - - 
Eligible for deauthorization. 
Lacks local support. 
No longer economically justified. 
Excludes $701,722 contributed by local interests. 
Includes $15,350,352 original construction cost. 
Reported in detail in an individual report. 
18-22 
1. 
2. 
3. 
4. 
5. 
6.

PITTSBURGH, PA., DISTRICT 
TABLE 18-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Adena, OH (Short Creek) 
Allegany, NY Unit I (Allegheny River)1 
Allegany, NY Unit II (Five Mile Creek Area)1 
Bellaire, OH 
Brackenridge, Tarentum and Natrona, PA 1 
Brilliant, OH 
Brockway, PA (Allegheny River Basin) 
Clarington, OH 
Coraopolis, PA 
Dillonvale, OH (Short Creek) 
Empire-Stratton, OH1 
Follansbee, WV 
Freeport, PA (Allegheny River) 
Industry, PA 
Kittanning, PA, part II (Allegheny River) 
Lake Chautauqua and Chadakoin River, NY2 
Lake Erie-Ohio Canal, OH and PA - 1935 Act 
Leetsdale, PA1 
Martins Ferry, OH1 
McKees Rocks, PA 
Mingo Junction, OH 
Moundsville, WV' 
Muddy Creek Dam, PA' 
Neville Island, PA' 
New Cumberland, WV 
New Kensington and Parnassus, PA' 
Pittsburgh, PA (Golden Triangle) 
Pittsburgh, PA (North Side) 
Pittsburgh, PA (The Strip) 
Powhaten Point, OH 1 
Proctor, WV' 
Redbank Creek Lake, PA 
Rochester, PA' 
St. Marys, PA (Allegheny River Basin) 
Smith Ferry, PA 
Warwood, WV' 
Wellsburg, WV 
West Bridgewater, PA 
Wheeling, WV' 
Wheeling, WV (North Wheeling)' 
Wheeling, WV (Wheeling Island)' 
Wilcox, PA3 
Woodlands, WV1 
Youghiogheny River, PA and MD (Canalization)' 4 
1975
"- 
1965 
1972 
1941 
1977 
-
- 
1954 
1971 
Aug 5, 1977 
Nov 17, 1986 
Nov 17, 1986 
May 6, 1981 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Nov 6, 1977 
Mar 2, 1970 
May 6, 1981 
Nov 17, 1986 
Nov 17, 1986 
Oct 3, 1978 
Aug 5, 1977 
Nov 17, 1986 
Nov 17, 1986 
Nov 17, 1986 
Aug 5, 1977 
Nov 17, 1986 
Oct 3, 1978 
Oct 3, 1978 
Oct 3, 1978 
Nov 17, 1986 
Nov 17, 1986 
Aug 5, 1977 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Nov 17, 1986 
Nov 17, 1986 
Nov 17, 1986 
Mar 5, 1955 
Nov 17, 1986 
Nov 17, 1986 
1. Deauthorized under Water Resources Development Act of 
1986 (PL 99-662). 
2. Local Interests failed to meet requirements of cooperation, 
authority for project expired Mar. 2, 1970. 
3. Local interests failed to meet requirements of cooperation, 
authority for project expired Mar. 5, 1955. 
4. Includes $47,195 construction costs expended under previous 
project and $1,700 O&M costs expended under previous 
project. 
18-23 
13,452 
4,100 
64,851 
76,487 
194 
16,884 
33,031 
190,722 
1,342,000 
25,164 
402,459 
156,377 
13,529 
6,387 
189,067 
21,700 
16,761 
232,863 
-- 
-- 
II- 
"-

TABLE 18-H ALLEGHENY RIVER, PA.: LOCKS AND DAMS 
(See Section 1 of Text) 
Dimensions 
Upper Depths on 
Avail- Normal Miter Sills Character of Type of 
Width able Lift at Pool at Normal Foundation Construction Year 
of Length Normal Elevation Pool Level- Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above ber Width Level mean sea Lower Upper Kind of Com- Navi- 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actu 
2 6.7 Aspinwall, PA 56 360 11.0 721.0 12.0 10.9 Rock Rock Fixed Concrete Concrete 100 19342 $ 1, 
3 14.5 Cheswick, PA 56 360 13.5 734.5 10.8 11.8 Rock Pile-Rock Fixed Concrete Concrete 100 19342 $ 1, 
4 24.2 Natrona, PA 56 360 10.5 745.0 10.0 8.5 Rock Rock Fixed Concrete Concrete 100 1927 1, 
5 30.4 Freeport, PA 56 360 11.8 756.8 10.5 10.3 Piling Crib-Pile Fixed Concrete Concrete 100 1927 1, 
6 36.3 Clinton, PA 56 360 12.2 769.0 10.6 10.8 Rock Crib-Pile Fixed Concrete Concrete 100 1928 1, 
7 45.7 Kittanning, PA 56 360 13.1 782.1 9.8 10.9 Piling Steel Sheet Fixed Concrete Concrete 100 1930 1, 
Piling 
8 52.6 Templeton, PA 56 360 17.9 800.0 10.4 13.8 Rock Rock Fixed Concrete Concrete 100 1931 2, 
9 62.2 Rimer, PA 56 360 22.0 822.0 10.5 11.3 Rock Rock Fixed Concrete Concrete 100 1938 2, 
Total $15, 
Abandoned lock and dam 1 
Abandoned lock and dam 2 
Abandoned lock and dam 3 
Demolishing old dam 1 
Dredging channel 1, 
Total $18, 
1. All depths as shown are on guard sills and are controlling depth. 2. Dates shown represent replacement structures. 
0
q 
al Cost y 
763,485 
875,665 
707,690 
940,537 
523,959 
460,008 
848,920 
510,373 
630,637 
591,187 
544,929 
310,103 
26,001 
055,003 
157,860 4
Z
0
C

TABLE 18-I MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(See Section 3 of Text) 
Dimensions Upper Depths on 
Avail- Normal Miter Sills Character of Type of 
Width able Lift at Pool at Normal Foundation Construction Year 
of Length Normal Elevation Pool Level- Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above ber Width Level mean sea Lower Upper Kind of Com- Navi- 
No. Mouth Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Dam Lock Dam plete gation Actual Cost 
2 11.2 Braddock, PA 56 360 8.7 718.7 16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 19532 $ 17,872,21257 
110 720 
3 23.8 Elizabeth, PA 563 360 8.2 726.9 16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 19533 17,538,5365 8 
720 
4 41.5 Monessen, PA 563 360 16.6 743.5 10.7 20.0 Piles Piles Movable Concrete Concrete 100 19322 17,254,0715 6 
720 
- 61.2 Maxwell locks 843 720 19.5 763.0 15.0 20.5 Rock Rock Movable Concrete Concrete 100 1964 30,110,8895 
and dam, 
Maxwell, PA 
- 82.2 Grays Landing 84 720 15.0 778.0 15.0 26.0 Rock Rock Fixed Concrete Concrete - - 24,723,3279 
Lock and dam, 
Grays Landing, 
PA 
7 85.0 Greensboro, PA 56 360 15.0 778.0 10.0 10.5 Rock Rock Fixed Concrete Concrete 100 19252 2,639,8045 
8 90.8 Point Marion, PA 56 360 19.0 797.0 10.0 14.5 Rock Rock Movable Concrete Concrete 100 19252 10,450,5544 5 
- 102.0 Morgantown lock 84 600 17.0 814.0 14.5 17.8 Rock Rock Movable Concrete Concrete 100 1950 8,778,0005 
and dam, 
Morgantown, WV 
- 108.0 Hildebrand lock 84 600 21.0 835.0 15.0 14.0 Rock Rock Movable Concrete Concrete 100 1959 12,506,8295 
and dam, 6 
miles above 
Morgantown, WV 
- 115.4 Opekiska lock 84 600 22.0 857.0 14.0 17.75 Rock Rock Movable Concrete Concrete 100 1964 25,179,6225 
and dam, 13.4 
miles above 
Morgantown, WV 
Marine ways, etc 250,0005 
Abandoned lock and dam 1 1,019,9075 
Abandoned lock and dam 4 780,8165 
Abandoned lock and dam 5 1,074,8125 
Abandoned lock and dam 6 770,4495 
Abandoned lock and dam 7 213,7765 
Abandoned lock and dam 8 245,9005 
Abandoned lock and dam 9 191,0005 
Abandoned lock and dam 10 210,4455 
Abandoned lock and dam 11 227,6685 
Abandoned lock and dam 12 200,5505 
Abandoned lock and dam 13 190,6915 
Abandoned lock and dam 14 210,1275 
Abandoned lock and dam 15 175,8295 
Dredging 587,8995 
Total $173,403,7135 
1-r 
1. All depths as shown are on guard sills and are controlling depths. 
2. Dates shown for locks and dams No. 2 to 8 inclusive, represent reconstruction. 
3. 2 Chambers 
4. Includes $3,322,057 for raising crest of dam, (1958-9), $2,086,438 for original reconstruction 
(1923-1926) and $618,758 AE&D costs for replacement of lock, and $2,324,328 
expended from the Inland Waterways Trust Fund. 
5. Actual cost: may include estimated costs which have been footnoted as necessary. 
6. Includes $2,173,767 for original reconstruction (1931-2), and $15,080,304 for reconstruction 
of dam (1963-1967). 
7. Includes $16,967,114 for reconstruction of locks. 
8. Includes $15,857,000 for major rehabilitation. 
9. Includes AE&D costs for proposed lock ($803,000) and $11,819,921 expended from 
the Inland Waterways Trust Fund.

REPORT OF THE SECRETARY Off THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-J MONONGAHELA RIVER, PA AND WV: 
TOTAL COSTS OF EXISTING PROJECT TO END OF FISCAL YEAR 
(See Section 3 of Text) 
Operation and 
Maintenance, 
Funds New Work General Total 
Regular $167,983,17213 $160,164,1332 $328,147,3051 23 
Maintenance and operation . .. 452,623 452,623 
Public Works acceleration, executive (1963) - 22,549 22,549 
Total $167,983,17213 $160,639,3052 $328,622,477123 
1. Excludes $5,420,541 for new work for previous projects. 3. Includes $15,857,000 for major rehabilitation of LID 3, 
$23,920,327 for replacement of L/D 7 ($11,819,921 provided by 
2. Excludes $20,446,587 expended between July 7, 1897 and the Inland Waterways Trust Fund), and $4,423,301 for re- 
June 30, 1937, on operation and care of works of improvement placement of lock at Pt. Marion Lock and Dam ($2,324,328 
under provisions of permanent appropriation for such purposes provided by the Inland Waterways Trust Fund.) 
and excludes $742 for maintenance of previous projects. 
TABLE 18-K OHIO RIVER BASIN (PITTSBURGH DISTRICT): RESERVOIRS 
(See Section 21 of Text) 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Allegheny: 
Conemaugh River, PA' Conemaugh River $ 46,012,41113 
Crooked Creek, PA' Crooked Creek 4,431,52313 
East Branch Clarion River, PA' Clarion River 9,539,5861' 
Kinzua Dam and Allegheny Reservoir, PA and NY' Allegheny River 112,218,763136 
Loyalhanna, PA' Loyalhanna Creek 5,727,53113 
Mahoning Creek, PA' Mahoning Creek 7,144,97313 
Tionesta, PA' Tionesta Creek 7,792,3791 3 
Union City, PA' French Creek 14,559,80013 
Woodcock Creek, PA' Woodcock Creek 20,545,0651 3 
Beaver: 
Berlin, OH' Mahoning River 8,739,98713 
Eagle Creek, OH2 Eagle Creek 12,700,0002 4 7 
Michael J. Kirwan, OH' Mahoning River 17,376,09713 
Mosquito Creek, OH 1 Mosquito Creek 4,253,02913 
Shenango River, PA and OH' Shenango River 40,209,8941 3 
Monongahela: 
Stonewall Jackson Lake, WV' West Fork River $231,000,00015 
Youghiogheny River, PA and MD' Youghiogheny River 12,521,16713 
1. Reported in detail in an individual report. 
2. Eligible for deauthorization. 
3. Actual Cost. 
4. Latest cost estimate revision 1954. 
5. 
6. 
7. 
Latest cost estimate revision in 1989. 
Includes $2,920,558 actual cost for Dam Rehabilitation. 
Inactive. 
18-26

PITTSBURGH, PA., DISTRICT 
TABLE 18-L INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 28 of Text) 
Project Dates of Inspection Project Dates of Inspection 
Amsterdam, OH October 1988 Marianna, PA April 1988 
Big Run, PA May 1989 Millvale, PA June 1986 
Bolivar, NY September 1989 Oil City Ice Control 
Bradford, PA June 1989 Structure, Allegheny 
Brookville, PA May 1989 River, PA September 1989 
Buckhannon, WV September 1989 Oil City LPP-(Dike), PA September 1989 
Burgettstown-Slovan, PA September 1986 Olean, NY September 1989 
Butler, PA June y 19 Portage, PA September 1989 
Chartiers Creek, PA Portville, NY September 1989 
Cannonsburg-Houston Reach September 1989 Reynoldsville, PA May 1989 
James G. Fulton Reach September 1989 Ridgway, PA June 1988 
Colliers, WV September 1988 Salamanca, NY September 1989 
DuBois, PA May 1989 Stonewood-Nutter Fort, WV July 1983 
Eldred, PA April 1987 Sykesville, PA May 1989 
Etna, PA September 1989 Tarentum, PA November 1976 
Friendsville, MD April 1988 Turtle Creek, PA September 1987 
Granville, PA April 1988 Washington, PA September 1986 
Johnsonburg, PA April 1989 Wellsville, OH September 1988 
Kittaning, PA August 1983 Weston, WV September 1989 
Latrobe, PA September 1988 Wilmore, PA September 1988 
Leetonia, OH June 1989 Yonmgstown, PA July 1989 
18-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 18-M FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 30 of Text) 
Flood Control Activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization) 
Project/Study Identification Fiscal Year Costs 
Allegheny River, Oil City, PA (Complete) 909,940 
Girty's Run, Allegheny County, PA (Complete) 2,737 
Lick Run Creek, Baldwin, PA (Reconnaissance Report) 18,583 
Parsons, Hambleton, Hendricks, WV (Reconnaissance Report) 45,932 
Robinson Run, Oakdale, PA (Inactive) 29 
Sullivan Run, Butler, PA (Reconnaissance Report) 158,399 
Tygart River, Phillipi, WV (Reconnaissance Report) 11,609 
W. Little Pine Creek, Etna, PA (Complete) 4,523 
Total cost for current fiscal year: 1,151,752 
Emergency Bank Protection - Section 14 of the 
1846 Flood Control Act, Public Law 526, 79th Congress 
Project/Study Identification 
Airport, Glendale, WV (Detailed Project Report complete) 
Beaver River, Bridgewater, PA (complete) 
Brook County, Hooverson Heights, WV (complete) 
Brush Creek, Jeannette, PA (Detailed Project Report complete) 
Chadakoin River, Jamestown, NY (Detailed Project Report complete) 
Cox Run, Wellsburg, WV (Detailed Project Report underway) 
Crows Run, Conway, PA (To be terminated) 
Dry Brook Creek, Poland, NY (Detailed Project Report underway) 
Dutch Hollow, Ellery, NY (To be terminated) 
Elks Creek, Clarksburg, WV (complete) 
Green County, Route 88, PA (to be terminated) 
Kennedy Twp., McKees Rocks, PA (complete) 
Mahoning River, Warren Twp., OH (complete) 
Mahoning River, Warren, OH (Detailed Project Report underway) 
Main Street, Wellsburg, WV (Detailed Project Report underway) 
Middle School, Wellsburg, WV (Detailed Project Report underway) 
Mill Run, Sinclairville, NY (Detailed Project Report complete) 
Monongahela River, Granville, WV. (complete) 
N. Scenic Road, Buffalo Twp., PA (to be terminated) 
Neshannock Creek, New Castle, PA (Detailed Project Report underway) 
Ohio River, McMechen, WV (to be terminated) 
Ohio River, River Ave., Chester, WV (to be terminated) 
Orange Road, Mercer County, PA (Detailed Project Report underway) 
Plum Creek, Oakmont, PA (Detailed Project Report underway) 
S. Scenic Road, Buffalo Twp., PA (to be terminated) 
Salamanca (Power Trans. Tower), NY (Detailed Project Report underway) 
Saw Mill Run Rd., Salamanca, NY (Detailed Project Report underway) 
Sewer Outfall, Glendale, WV (Plans & Specs underway) 
Shupe Run, Mt. Pleasant, PA (Detailed Project Report complete) 
Turkey Run, Shenango Twp., PA (to be terminated) 
Unnamed Tributary to Pymatuning (to be terminated) 
Walnut Bottom Run, Beaver Falls, PA (Detailed Project Report underway) 
Water Works, Park & Pool, Wellsburg, WV (Detailed Project Report underway) 
West Run, Munhall, PA (Plans & Specs complete) 
Total cost for current fiscal year 
Fiscal Year Costs 
7,362 
60 
254 
13,623 
8,885 
17,052
4 
9,424 
36 
82 
62 
55 
28 
18,982 
15,447 
17,025 
6,404 
104 
2,246 
7,260 
72 
872 
6,417 
19,487 
15 
10,052 
6,299 
4,418 
321
2 
1,148 
7,665 
12,677 
21,539 
215,379 
18-28

OHIO RIVER 
For actual construction of locks and dams, and operation 
and care of completed stuctures, river is divided into 
three sections under immediate supervision and direction 
of District Engineers at Pittsburgh, Huntington and 
Louisville. Pittsburgh section extends 127 miles from 
head of river at Pittsburgh, Pa., to a point immediately 
upstream from New Martinsville, W. Va., and includes 
Emsworth, Dashields, Montgomery, New Cumberland, 
Pike Island and Hannibal locks and dam. Huntington 
section extends 311 miles from mile 127 to 438 
immediately upstream from Foster, Ky., and includes 
Willow Island, Belleville, Racine, Gallipolis, Greenup and 
Captain Anthony Meldahl locks and dams. Louisville section 
extends 543 miles from mile 438 to mouth of river, 
and includes Markland and McAlpine locks and dams 
(with Louisville and Portland Canal) Cannelton, 
Newburgh, Uniontown, and Smithland locks and dams 
and Locks and Dams 52 and 53. 
IMPROVEMENTS 
Navigation 
1. Construction of locks and dams on Ohio 
River ............................... 19-1 
2. Open channel work, Ohio River............ 19-3 
Tables 
Table 19-A Cost and Financial Statement...... 19-5 
Table 19-B Authorizing Legislation............19-6 
Table 19-C Not Applicable 
Table 19-D Not Applicable 
Table 19-E Not Applicable 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON OHIO RIVER 
Location. Ohio River is formed by junction of 
Allegheny and Monongahela rivers at Pittsburgh, Pa., 
and flows generally southwesterly for 981 miles to join 
Mississippi River near Cairo, Ill. For description of river 
see page 1227, 1932 Annual Report. 
Previous projects. For details see page 1907 of Annual 
Report for 1915. 
Existing project. Provides for improvement of entire 
river by construction of locks and dams to provide a 
channel depth of 9 feet and for widening Louisville and 
Portland Canal at Louisville, Ky. Project provides for a 
lock with usable dimensions of 110 by 600 feet at each 
of the dams and, in addition, an auxiliary lock 56 by 360 
feet is available at Emsworth, Dashields, Montgomery, 
and McAlpine locks and dams with an auxiliary lock at 
Gallipolis being 110 by 360 feet. Dashields is a fixed dam, 
while Emsworth, Montgomery, and Gallipolis are fixed 
dams with movable crests. Remaining dams are movable 
Table 19-F Not Applicable 
Table 19-G Not Applicable 
Table 19-H Construction of Locks and Dams on 
Ohio River, Total Cost of Existing 
Project .......................... 19-6 
Table 19-I Federal Energy Regulatory 
Commission Licenses of Locks 
and Dams, Ohio River............. 19-6 
Table 19-J Ohio River Locks and Dams 
Statistics ............... ....... 19-7 
type, with navigable pass varying in width from 600 to 
1,248 feet. In addition to navigable pass, movable-type 
dams are also provided with one or more regulating weirs. 
At McAlpine Locks and Dam, a canal (Louisville and 
Portland) extends along left bank for 2 miles, with locks 
at lower end. Modifications to existing project under purview 
of Section 6, March 3, 1909 Act, provide for fixed 
dams with movable crests with two locks (110 by 1200 
feet and 110 by 600 feet) at New Cumberland, Pike Island, 
Hannibal, Willow Island, Belleville, Racine, Greenup, 
Captain Anthony Meldahl, Markland, Cannelton, 
Newburgh, and Uniontown; two locks 110 by 1200 feet 
at Smithland; 110 by 1,200 foot temporary locks in addition 
to the existing locks at Locks and Dams 52 and 53, 
and reconstruction to provide a 110 by 1200-foot lock in 
addition to existing locks and a fixed dam with two sections 
of movable crest at McAlpine Locks and Dam; 
widening Louisville and Portland Canal to 500 feet. Auxiliary 
lock 56 by 360 feet at McAlpine Locks and Dam 
has been inoperative since failure of downstream lock 
gates in December 1972. Rehabilitation of existing Locks 
and Dams 52 and 53 was started in September 1979 under 
the purview of Section 6, March 1909 Act. Mound City 
19-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
was also considered authorized under purview of 1909 
Act, and preconstruction planning was performed in the 
period 1965 to 1972. The ruling of the U.S. District Court, 
District of Columbia, on September 6, 1974, with 
reference to Lock and Dam 26, Mississippi River, would 
also apply to this project. Consequently, it is no longer 
considered authorized. Operation and care of locks and 
dams were included in project July 1, 1935, under provisions 
of Permanent Appropriations Repeal Act of June 26, 
1934. Estimated Federal cost of new work (existing project, 
1983), exclusive of Gallipolis Locks and Dam reported 
under Kanawha River project is $1,778,840,999, 
estimated non-Federal cost is $14,999,000. Foregoing 
estimate does not include expenditures on previous projects. 
Various items previously included in this project are 
considered inactive or unnecessary and are excluded from 
foregoing cost estimate. See page 693, Annual Report, 
1968 for items and estimated'cost. Under authority of 
1910 River and Harbor Act, Louisville and Portland 
Canal was widened to 200 feet; Locks and Dams 40 and 
42 eliminated; Locks and Dams 1 and 2 replaced by 
Emsworth Locks and Dam; Lock and Dam 3 replaced by 
Dashields Locks and Dam; and Locks and Dams 4, 5, and 
6 replaced by Montgomery Locks and Dam. Locks and 
Dams 24, 25, and 26 were replaced by Gallipolis Locks 
and Dam authorized by August 30, 1935 Act, and constructed 
under project for improving lower Kanawha 
River. Locks and Dams 7, 8, and 9 were replaced by New 
Cumberland Locks and Dam; Locks and Dams 10 and 11 
were replaced by Pike Island Locks and Dam; Locks and 
Dams 12, 13, and 14 were replaced by Hannibal Locks 
and Dam; Locks and Dams 15, 16, and 17 were replaced 
by Willow Island Locks and Dam; Locks and Dams 18, 
19, and 20 were replaced by Belleville Locks and Dam; 
Locks and Dams 21, 22, and 23 were replaced by Racine 
Locks and Dam; Locks and Dams 27, 28, 29, and 30 were 
replaced by Greenup Locks and Dam; Locks and Dams 
31, 32, 33, and 34 were replaced by Captain Anthony 
Meldahl Locks and Dam; Locks and Dams 35, 36, 37, 38, 
and 39 were replaced by Markland Locks and Dam; the 
Louisville and Portland Canal at McAlpine Locks and 
Dam was widened to 500 feet. Locks and Dams 43, 44, 
and 45 were replaced by Cannelton Locks and Dam; Locks 
and Dams 46 and 47 were replaced by Newburgh Locks 
and Dam; Locks and Dams 48 and 49 were replaced by 
Uniontown Locks and Dam, presently under construction; 
and Locks and Dams 50 and 51 were replaced by 
Smithland Locks and Dam, presently under construction, 
as modifications to existing project under purview of 
Section 6, March 3, 1909 Act, reducing total number of 
structures to 20. The Water Resources Development Act 
of 1974 combined the Newburgh Bank Protection Works 
project with the Newburgh Locks and Dam project. A 
December 1981 Act established the Falls of the Ohio 
National Wildlife Conservation Area near McAlpine 
Locks and Dam to protect and preserve existing fossilized 
coral and a diversity of wildlife. Table 19-J contains data 
relative to various features of locks and dams included 
in existing projects. For list of principal towns and cities 
along Ohio River with their mileage below Pittsburgh, 
PA, see page 1060, 1962 Annual Report. See Table 19-I 
for licenses. 
Navigation system of 21 locks and dams is in operation 
and 9-foot navigation throughout length of river is 
generally available at all times. At certain unstable bars 
project depth is maintained by dredging, supplemented 
by contraction works. (See "Open Channel Work, Ohio 
River.") Table 19-J shows cost and year completion of 
locks and dams now in operation. Existing project does 
not provide adequate facilities for present day navigation 
due to obsolescence of structures. Since repair and modernization 
of these facilities would be extremely costly, 
replacement and reconstruction is being accomplished as 
rapidly as funds are made available for the purpose. Construction 
of lock and dam replacement program was 
initiated in fiscal year 1955. New Cumberland, Pike 
Island, Hannibal, Willow Island, Belleville, Racine, 
Greenup, Captain Anthony Meldahl, Markland, 
McAlpine, Cannelton, Newburgh, Uniontown, and 
Smithland replacement locks and dams are in operation, 
replacing 39 old low-lift locks and dams. For total cost of 
existing project, see Table 19-H. 
Terminal facilities. Modern public terminals, with 
warehouses, equipped with operating machinery for 
transferring materials, have been constructed by private 
interests at some of the larger cities and towns. A list of 
terminals on Ohio River is revised annually and can be 
obtained from Division Engineer, U.S. Army Engineer 
Division, Ohio River, Cincinnati, Ohio. 
Operations during fiscal year. New work by contract 
and hired labor: 
Emsworth Locks and Dam (Rehabilitation): Major 
rehabilitation work was completed on November 9, 1984 
and included placing stone erosion protection downstream 
of both the back channel and the main channel, structurally 
rehabilitating all 14 dam gates, painting of the 
service bridge on the main channel dam and painting dam 
gates on the back channel. Lock work included rehabilitation 
of the river chamber and land chamber including all 
lock machinery. Expenditures during FY 1989 for construction 
completion of the remaining rehabilitation project 
was $1,768. 
Montgomery Locks and Dam (Rehabilitation): Contracts 
completed include: Fabrication of lock miter gates, 
110-foot chamber for $1,049,132; upper guard wall cells 
for $856,468; emergency dam bulkheads for $329,631; 
fabrication of 56-foot lock miter gates for $344,519. Contract 
for installation of 56-foot lock miter gates and major 
rehabilitation of locks and dam, awarded on July 29, 
1985 for $22,193,960 was completed for estimated amount 
of $24,004,667. Installation of 110-foot lock miter gates 
was completed by hired labor. Expenditures during FY 
1989 for real estate coordination, construction, engineering 
and design of rehabilitation project was $446,971. 
Willow Island Locks and Dam: Construction was initiated 
in January 1967. All work is complete. 
Belleville Locks and Dam: Construction was initiated 
in May 1962. All work is complete. 
Racine Locks and Dam: Construction initiated in June 
1964 is complete. 
19-2

OHIO RIVER 
Gallipolis Lock and Dam: The existing project, constructed 
under project for improving lower Kanawha 
River, was placed in operation in August 1937. The 
dimensions of the existing locks chambers and poor approach 
conditions, particularly to downstream traffic, 
have created a higher than normal accident rate to the 
structure with corresponding hazards and delays to traffic. 
The Water Resources Development Act of 1976 
authorized Phase I studies for a single 1200-foot lock in 
a bypass canal. These studies are complete. 
Initial Construction, General funds for the continuation 
of Engineering activities were received in September 
1985. During the fiscal year real estate acquisition continued. 
Plans and Specifications were completed. The project 
was advertised and bids were opened in September 
1987. The contract was awarded in October 1987 and is 
38% complete. The total estimated cost of the project is 
$345,000,000, which is 50 percent federal cost and 50 percent 
inland waterways trust fund cost. 
Greenup Locks and Dam: Construction was initiated in 
October 1954. All work is complete. 
Captain Anthony Meldahl Locks and Dam: Construction 
work complete. 
Markland Locks and Dam: Project is complete including 
a public highway bridge across the navigation structure, 
as authorized by the Federal-Aid Highway Act of 1970 
(Public Law 91-606). For details of bridge see page 22-3 
of Annual Report for 1978. 
Falls of the Ohio National Wildlife Conservation Area 
was authorized by Public Law 97-137 on December 29, 
1981. The Conservation Area will protect 1,000 acres 
which consists of birdlife and other wildlife. Planning, 
consisted in efforts to locate a Non-Federal sponsor to help 
cost share project accomplishments. Real Estates activities 
consisted of acquisition proceedings against 48 
triacts needed for the projects. $903,140. 
McAlpine Locks and Dam: Project is complete except 
for alteration of lift section of railroad bridge that spans 
the upper end of the Louisville and Portland Canal which 
work is presently deferred. 
Cannelton Locks and Dam: Project is complete except 
for financially closing out the project. $20,371. 
Newburgh Locks and Dam: Construction initiated in 
October 1962 is complete except for financially closing out 
the project. $3,210. 
Uniontown Locks and Dam: Project is complete except 
for continuing action on Declarations of Taking on one 
tract. $6,446. 
Smithland Locks and Dam: All major construction 
features are complete and the project was advanced to 99 
percent completion. Land acquisition is complete except 
for outstanding condemnation actions and acquisition of 
one recreation site. One relocation contract for electric 
lines is being delayed for rights-of-way problems. 
Contracts to construct a recreational site at Lusk Creek, 
IL and to provide electric service to same were completed. 
Engineering and Design on remaining project features 
was continued. $75,778. 
Locks and Dam No. 52 (New Lock): Construction initiated 
in December 1967 is complete. 
Locks and Dam No. 53 (Temporary Lock): Construction 
initiated in December 1972 is complete. 
Locks and Dam No. 52 (Rehabilitation): Construction 
initiated in June 1979 is complete. 
Locks and Dam No. 53 (Rehabilitation): Construction 
initiated in June 1979 is complete. 
Operation and maintenance, general. Locks and dams 
operated as required and necessary repairs and improvements 
made thereto and to operator's quarters, 
grounds and esplanades. Costs were $9,000,963 for Pittsburgh 
District, $11,464,341 for Huntington District and 
$13,638,220 for Louisville District. 
Dashields Locks and Dam (Rehabilitation): Major 
Rehabilitation work includes new mechanical and electrical 
systems, structural repairs, lock wall stabilization, 
new land and middle wall buildings, repairs to existing 
land wall, service and river wall buildings and new access 
road. Contract for Rehabilitation of Locks and Dam 
was awarded on September 17, 1987 for $25,918,504 and 
is 94 percent complete. Overall scheduled completion date 
is December 1990. Expenditures during FY 1989 for construction 
and engineering and design for rehabilitation 
project was $14,103,507. 
2. OPEN CHANNEL WORK, OHIO RIVER 
Location. Under jurisdiction of district engineer in 
whose district the work is located. Portion of river included 
in project extends 974.7 miles from head of river at 
Pittsburgh, PA, to mouth of Cache River (Mound City, 
IL). Open channel improvement from mouth of Cache 
River to mouth of Ohio River is under jurisdiction of 
Mississippi River Commission. 
Existing projects. Before completion of canalization 
project, no project depth had been fixed by Congress under 
project for open channel work, but in order to properly 
aid packet and barge navigation it was necessary to 
secure a low-water channel with a minimum depth of 
4 to 6 feet, and a width, depending upon difficulty 
of running channel, of 400-600 feet; also to permit 
movemment of large coal tows, which movement occurred 
at stages of water exceeding 10 feet, it was necessary 
to remove points of projecting bars which formed at 
various locations along river. Accomplishment of this purpose 
involved concentration of current by closing back 
channels at islands with low dams, contraction and 
straightening wide open channels by low dikes, dredging 
bars and shoals, and removal of snags and wrecks. 
Incidental to direct improvement of Ohio River is construction 
and maintenance of ice piers as required for protection 
of river craft. Stage of extreme high water on Ohio 
River varies from 46 feet at Pittsburgh, Pa., to 80 feet 
at Cincinnati, Ohio, with 57.2 feet at Louisville, Ky. (head 
of falls), 53.8 feet at Evansville, Ind., and 59.5 feet at 
Cairo, Ill. (mouth of river). Estimated cost of new work 
(1960) is $16,160,000, exclusive of following items which 
are considered inactive: Ice piers authorized by 1927 River 
and Harbor Act; reforestation of sloughs on Kentucky 
19-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Peninsula near Evansville, Ind., authorized by 1930 River 
and Harbor Act; dredging to widen channel at certain 
points; and placing revetment at various points. 
Estimated cost of these items (1954) is $6,565,000. Operation 
of snag boats on Ohio River below Pennsylvania 
State line was included in project July 1, 1935, under provisions 
of Permanent Appropriations Repeal Act of 
June 26, 1934. See Table 19-B for authorizing legislation. 
New work under this project is substantially complete, 
since it is not anticipated that work on inactive portion 
of project will be accomplished. In addition to dredging, 
local stabilization of channel has been effected at various 
points by construction of dikes and revetment. Work 
which remains consists of dredging to widen channels at 
certain points to project depth. 
Local cooperation. River and Harbor Act of 
January 21, 1927 authorizing construction of ice piers for 
general open channel work, imposes condition that before 
work is begun on any pier, local interests convey to the 
United States free of cost such riparian rights as may be 
deemed necessary in connection with the improvements 
at locality (HI. Doc. 187, 67th Congr., 2nd sess.). Existing 
ice piers are adequate for present purposes and local 
cooperation is not needed since no additional construction 
is under consideration. River and Harbor Act of July 3, 
1930, provides for reforestation of sloughs of Kentucky 
Peninsula and bank protection and that no expense shall 
be incurred by the United States for acquiring lands 
required for purpose of this improvement (H. Doc. 409, 
69th Cong. 1st sess.). However, since no serious overbank 
erosion has occurred since bank revetment in 1933-34, 
reforestation is not considered justifiable at this time and 
no local cooperation is required. 
Operations during fiscal year. Operation and 
maintenance, general: Dredging was done where required 
to provide an adequate and dependable channel of project 
depth at minimum pool conditions. Dikes and 
revetments were maintained and routine work of maintaining 
navigation aids, removing snags, making channel 
studies, hydrographic surveys and mapping was performed 
as required. Channel soundings, hydrographic surveys, 
stream gaging operations, channel inspections and aids 
to navigation, and miscellaneous inspections and reports 
cost $978,308. There was no dredging by hired labor on 
the Ohio River in FY 89. Dredging by contract: Huntington 
District 645,881 cubic yards at $1,475,964 and 
Louisville District 1,033,966 cubic yards at $2,092,935. 
19-4

OHIO RIVER 
TABLE 19-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
1. Construction of New Work 
Locks and Dams Approp. $7,065,000 $5,479,000 $52,787,000 $43,833,000 $1,492,818,7721 3 5 10 17 21 
on Ohio River Cost 6,639,783 4,974,653 45,381,646 48,444,774 1,488,152,8151 3 6 11 12 15 16 18 22 
Maint. 
Approp. 32,293,874 33,309,500 34,400,000 34,279,987 691,632,3212 4 19 
Cost 32,804,809 32,780,076 34,640,914 34,103,524 690,611,1482 13 14 1920 
Rehab. 
Approp. 10,151,000 12,486,000 2,720,000 275,000 82,996,572 
Cost 12,571,165 9,965,508 5,845,792 448,866 82,898,626 
Rehab.(O&M) 
Approp. 1,267,100 1,784,400 12,890,200 14,129,500 30,071,200 
Cost 1,166,100 1,578,959 13,155,802 14,103,501 30,004,362 
2. Open Channel New Work 
Work, Ohio River Approp. - - - - 15,962,2608 
Cost - - - - 15,962,2608 
Maint. 
Approp. 4,508,800 3,860,500 4,429,600 4,394,700 121,302,0267 9 
Cost 4,555,393 3,854,324 4,250,322 4,547,207 121,246,6857 9 
Rehab. 
Approp. - - - - 944,649 
Cost - - - - 944,649 
1 Includes $17,003,761 for previous 6-foot canalization 
project. 
2 Includes $36,943,217 expended from 1885 to 1937 on operation 
and care of work of improvement under provisions of permanent 
indefinite appropriations for such purposes. 
3 Includes $215,812 public works acceleration, executive 
1963. 
4 Includes $38,766 public works acceleration, executive 1963. 
5 Excludes $251,769 contributed funds for new work. 
6 Excludes $250,102 contributed funds for new work. 
7 Excludes $1,621,349 expended in operation of snag boats 
under provisions of permanent indefinite appropriation for such 
purposes, and $267 transferred to project without 
reimbursement. 
8 Includes $1,040,236 Public Works funds. 
9 Includes $1,000 for removal of obstructions in Licking River 
under authority of Section 3, R&H Act of 1930. 
10 Includes $100,000 placed in FY 1971 Budget Reserve. 
1 Excludes $3,899 transferred from project without 
reimbursement. 
12 Surplus property valued at $3,553 transferred to project 
without reimbursement. 
13 Excludes $2,140 transferred to project without 
reimbursement. 
14 Excludes surplus property valued at $73,832 transferred 
to project without reimbursement. 
15 Includes $87,724,158 prior construction cost. 
16 Excludes surplus property valued at $297,385 transferred 
to project without reimbursement. 
17 Includes $549,392 Code 710 Funds, $572,162 Code 711 
Funds, $532,677 Code 712 Funds and $1,759,812 Code 713 
Funds. 
18 Includes $549,392 Code 710 Funds, $342,162 Code 711 
Funds, $532,677 Code 712 Funds and $1,989,812 Code 713 
Funds. 
19 Includes $2,158,073 Funds provided from The Productive 
Employment Appropriations Act of 1983 (PL 98-8). 
20 Includes $920,945 cost for operations and care of previous 
projects. 
21 Includes $52,249,000 Inland Waterways Trust Funds. 
22 Includes $49,629,000 Inland Waterways Trust Funds. 
19-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 19-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
2. Open Channel Work, Ohio River 
March 3, 1827 Project adopted by this act originally covered entire 
length of Ohio River from its mouth near Cairo to 
Pittsburgh, a distance of 981 miles. It provided for 
removal of all obstructions which tend to endanger 
steamboat navigation. 
January 21, 1927 Construct ice piers as a part of project, with funds H. Doc. 187, 67th Cong., 2nd sess. 
allotted from appropriations for general open 
channel work. 
July 3, 1930 Reforestation of sloughs on Kentucky Peninsula near H. Doc., 409, 69th Cong., 1st sess. 
Evansville, Ind., and a 200-foot strip along bank 
and for bank protection, at an estimated cost of 
$200,000. 
July 3, 1958 Act of March 3, 1827 modified to include maintenance H. Doc., 434, 84th Cong., 2nd sess. 
of existing Licking River Channel within lower 
3-mile limit of River slack water, at an estimated 
increase of $1,000 in cost of average annual 
maintenance. 
Locks and Dams, Ohio River 
December 29, 1981 Act of December 29, 1981 established the 1,000 H.R. 2241, PL 97-137, Title II, 
acre Falls of the Ohio National Wildlife Conser- 95 Stat. 1710 
vation Area, at a cost not to exceed $300,000. 
November 17, 1988 Olmsted Locks and Dam PL 100-676, 100th Cong., 2nd Sess. 
CONSTRUCTION OF LOCKS AND DAMS ON OHIO RIVER 
TOTAL COST OF EXISTING PROJECT TO SEPTEMBER 30, 1989 
TABLE 19-H (See Section 1 of Text) 
Operations and 
Maintenance 
Funds New Work General Rehabilitation Total 
Regular $1,395,755,640 $649,649,431 $112,902,988 $2,158,308,059 
Public Works 3,258,368 0 0 3,258,368 
Emergency Relief 1,198,837 19,000 - 1,217,837 
Maintenance & Operation - 3,039,789 3,039,789 
Public Works Acceleration 215,812 38,766 254,578 
Executive 1963 $0 
Total $1,400,428,6573 $652,746,9861 2 $112,902,9884 $2,166,078,631 
1 Excludes $36,943,217 expended from 1885 to 1937 under 4 Includes $30,004,362 cost for O&M 
permanent indefinite appropriation. Rehabilitation. 
2 Excludes $920,945 cost for operation and care of previous 
projects. Note: All other cost variations are listed in the Footnotes 
3 Excludes $87,724,158 prior construction cost. of Table 19-A. 
FEDERAL ENERGY REGULATORY COMMISSION LICENSES 
TABLE 19-I AT LOCKS AND DAMS, OHIO RIVER 
Markland Dam McAlpine Dam Racine Dam Greenup Dam Hannibal Dam 
F.E.R.C. License 2,211 289:1,000 2,570 2,614 3,206 
License Public Service Co. Louisville Gas and Ohio Power Co. City of Vanceburg, City of New 
of Indiana Electric Co. Kentucky Martinsville,WV 
Annual Charge $ 45,950.00 $ 95,000.00 $ 64,232.00 $ 261,103.00 
Collections to end of 
Fiscal Year 1988 $1,054,961.64 $8,340,353.84 $478,369.00 $1,774,678.00 
19-6

TABLE 19-J4 OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
Replaced 
Emsworth Locks and Dam, 
Emsworth, PA 
Replaced 
Replaced 
Dashields Locks and Dam 
1.6 miles below 
Sewickley, PA 
Replaced 
Replaced 
Replaced 
Montgomery Locks and Dam, 
1.4 miles above 
Industry, PA 
Replaced 
Replaced 
New Cumberland Locks and 
Dam, Stratton, OH 
Replaced 
Replaced 
Replaced 
Pike Island Locks and Dam, 
2 miles upstream from 
Warwood, WV 
Replaced 
Replaced 
Replaced 
Hannibal Locks and Dam, 
1.6 miles upstream from 
New Martinsville, WV 
Replaced 
Replaced 
Willow Island Locks and 
Dam, 2.7 miles above 
Waverly, WV 
110 
56 
600 
360 
110 600 
56 360 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
600 
360 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
18.0 710.0 17.0' " 12.9' Rock 
15.5' s 12.93 
10.0 692.0 13.41 17.53 Rock 
Rock and piles 100 
Rock and piles 100 
- $ 870,034 
1921 43,347,634" 
- 976,767 
- - 1,144,588 
Rock 100 1929 33,537,438"** 
- - 1,071,472 
- - 1,080,132 
- - 1,123,442 
17.5 682.0 16.0' 14.6s Rock and piles Rock and piles 100 
20.5 664.5 7.0' 14.8s Rock 
21.0 644.0 17.0' 18.0' Rock 
Rock 
1936 37,680,796"* 
- - 1,075,000 
- - 1,167,456 
100 1959 39,099,688 
- - 1,177,100 
- - 1,138,000 
- - 1,162,165 
Rock 100 1968 56,623,946 
- - 1,166,104 
- - 1,222,389 
- - 1,133,371 
21.0 623.0 38.0 17.0 Rock Rock 99 1972 87,649,818 
- - 1,180,478 
- - 1,275,532 
20.0 602.0 35.0 15.0 Rock and piles Rock 100 1972 76,520,876 
1 -
6.2 
13.3 
31.7 
7 - 
8 - 
54.4 
9 
10 
11 
12 
13 
14 
15 
16 
84.3 
126.4 
161.7

TABLE 19-J4 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
103.9 Belleville Locks and Dam, 
0.3 mile below 
Reedsville, OH 
- Replaced 
- Replaced 
- Replaced 
237.5 Racine Locks and Dam, 
1.5 miles below 
Letart Falls, OH 
- Replaced 
- Replaced 
- Replaced 
279.2 Gallipolis Locks and Dam, 
0.7 mile below 
Hogsett, WV 
Gallipolis Modernization 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
341.0 Greenup Locks and Dam, 
4.9 miles below 
Greenup, KY 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
436.2 Captain Anthony Meldahl 
Locks and Dam, 2.2 miles 
above Foster, KY 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
1,200 
600 
1,200 
600 
17 
18 
19 
20 
21 
22 
23 
24 
25 
26 
27 
28 
29 
30 
31 
32 
33 
34 
- - $ 1,362,591 
- - 927,091 
- - 1,213,848 
- - 936,696 
22.0 582.0 37.0 15.0 Rock and piles Rock 100 1968 
- - 1,484,562 
- - 1,218,798 
- - 1,851,488 
22.0 560.0 18.0 15.0 Rock and piles 
23.0 538.0 18.0 15.0 Rock 
23.0 538.0 18.0 15.0 - 
30.0 515.0 18.0' 13.0 Rock 
30.0 485.0 18.0' 15.0 Rock 
Rock 
Rock 
Rock 
Rock 
100 1971 
100 1937 
100 1959 
- - 1,359,231 
- - 2,951,216 
- - 1,937,166 
- - 3,437,057 
100 1962 74,188,216 
600 
360 
1,200 
600 
1,200 
600 
1,200 
600 
62,591,255 
ri
0
0
Li 
0
ITi 
r-3' 
0
0
ITJ 
d 
0
O
'TI 
C0 
r
0
C
Cl 
0 
d 
co 
64,922,680 
1,187,542 
1,925,205 
1,307,241 
3,452,066 
100,505,8021" 
1,063,133 
1,088,802 
1,579,618 
57,464,191

TABLE 19-J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cast 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
35 - Replaced 
36 - Replaced 
37 - Replaced 
38 - Replaced 
531.5 Markland Locks and Dam, 
1 mile above Markland, IN 
39 - Replaced 
40 - Eliminated 
41 - - 
Falls of the Ohio, 1 mile 
above McAlpine 
604.0 McAlpine Locks and Dam 
(Reconstruction of Locks 
and Dam 41) 
42 - Eliminated 
43 - Replaced 
44 - Replaced 
45 - Replaced 
720.7 Cannelton Locks and Dam 
3 miles above 
Cannelton, IN 
46 - Replaced 
776.1 Newburgh Locks and Dam, 
16 miles above 
Evansville, IN 
47 - Replaced 
48 - Replaced 
49 - Replaced 
846.0 Uniontown Locks and Dam, 
3.5 miles below 
Uniontown, KY 
50 - Replaced 
51 - Replaced 
918.5 Smithland Locks and Dam, 
2 miles above 
Smithland, KY 
110 
110 
N/A 
110 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
1,200 
600 35.0 455.0 50.0 15.0 Rock 
N/A N/A N/A N/A N/A N/A 
1,200 49.0 12.0 
600 37.0 420.0 19.0 11.0 Rock 
360 19.0 11.0 
1,200 25.0 383.0 38.0 13.0 Rock 
600 
1,200 
600 16.0 358.0 32.0 16.0 Rock 
1,200 
600 22.0 342.0 34.0 12.0 Rock 
1,200 
1,200 22.0 324.0 34.0 12.0 Rock 
Piles 
N/A 
Rock 
Rock 
100 
0 
1963 
N/A 
$ 1,894,942 
3,704,535 
1,297,924 
2,857,040 
63,019,403 
2,222,448 
7,658,134' 
1,470,959 
100$ 1961 45,726,189' 
99 1972 
2,592,242 
2,819,930 
3,202,890 
99,028,570'� 
- - - 3,129,028 
Pile 99 1975 104,484,465 
- - - 4,415,526 
- - - 3,062,710 
- - - 3,325,964 
Rock 99 1975 100,307,642 
- - - 3,751,762 
- - - 4,370,566 
Rock 99 1980 273,689,085 
0
('") 
N 
CD

TABLE 19-J 
(Continued) 
OHIO RIVER LOCKS AND DAMS 
(See Section 1 of Text) 
Lock Dimensions Upper 
Normal 
Greatest Pool 
Length Elevation Depth on 
Width Available (feet, Miter Sills Actual Cost 
Lock Miles of For Full mean Year to Date of 
and Below Distance From Chamber Width Lift sea Upper Lower Character of Foundation Percent Opened to Each Lock 
Dam Pittsburgh Nearest Town (feet) (feet) (feet) level) (feet) (feet) Lock Dam Complete Navigation and Dam 
52 938.9 1.4 miles below Brookport, IL 110 000 12.0 302.0 15.4 11.0 Pile Pile 100 1928 13,337,747" 
938.9 1.4 miles below Brookport, Il 110 1,200 12.0 302.0 15.4 11.0 Pile Pile 100 1969 10,197,516 
(New lock) 
53 962.6 10.8 miles above 110 600 13.4 290.0 15.4 9.6' Pile Pile 100 1929 10,004,240" 
Mound City, IL 
962.6 10.8 miles above 110 1,200 13.4 290.0 15.4 9.6 Pile -100 1982 38,570,920 
-Mound City, IL (New lock) 
974.2 Mound City Lock and Dam - - - - - - - - 1,539,470 
I mile below Mound City, IL 
TOTAL $1,594,061,568" 
' Depths are on emergency dan foundation and are controlling depths. 
: Change from fixed dam to lift-gate dam completed in 1938. 
' Depths are on poiree dam foundation and are controlling depths. 
* Land chamber. 
s River chamber. 
s Roller-gate dam. Cost not included in total. Constructed under project for 
improving lower Kanawha River. 
Lock and Dam 41 completed with 110- by 600-foot lock in 1921. Completed 
with new dam and raised canal and lock wall in 1928. Auxiliary 56- by 360-foot 
lock constructed in 1929-30. Reconstr-uction and modernization began 1956, 
renamed McAlpine Locks and Dam in 1960. Operation of auxiliary lock 
suspended in 1971. 
* Completed except for deferred alteration of railroad bridge. 
9 Dam below not yet constructed. Depth on lower miter sill at lower water. 
1o Excludes $2,219,975 payment for settlement of damage to dam caused by 
barge accident in April 1978. 
" Includes $8,876,000 for major rehabilitation project initiated in FY 1979. 
" Includes $4,593,572 for major rehabilitation project initiated in FY 1979. 
13 For preconstruction planning 1965 to 1972. No longer considered authorized. 
See Section 1 of text. 
" Includes $37,485,869 for major rehabilitation initiated in FY 1980. 
14* Includes $31,943,185 for major rehabilitation initiated in FY 1983. 
" 4 
**Includes $30,004,362 for major rehabilitation initiated in FY 1986 
(O&M funds). 
s Includes $46,629,000 Inland Waterways Trust Funds. 
" Exclusive of $6,994,235 details below. 
Additional Features Entering into Cost of Project 
Louisville and Portland Canal and Indiana chute $ 
(under previous project) 
Examinations, survey contingencies, plants and miscellaneous 
Recreation facilities, pool area, Gallipolis Locks and Dam 
TOTAL 
5,359,203 
966,232 
668,800 
6,994,235 
GRAND TOTAL $1,601,055,803

BUFFALO, N.Y., DISTRICT * 
The district comprises Ohio, northwestern Pennsylvania 
and western and northern New York, embracing U.S. waters 
of Lake Erie exclusive of small portion of western end, Lake 
Ontario, and St. Lawrence River, with their tributary 
drainage basins from boundary between the states of Ohio 
and Michigan to international boundary line east of Frontier, 
New York. 
IMPROVEMENTS 
Navigation 
1. Ashtabula Harbor, Ohio ...................... 
2. Barcelona Harbor, N Y .... ,.................... 
3. Black Rock Channel and 
Tonawanda Harbor, N Y ...................... 
4. Buffalo Harbor, N Y .......................... 
5. Cattaraugus Harbor, N Y .................... 
6. Cleveland Harbor, Ohio ............. ....... 
7. Conneaut Harbor, Ohio ........................ 
8. Dunkirk Harbor, N Y ........................ 
9. Erie Harbor, Pa. .............................. 
10. Fairport Harbor, Ohio ....................... 
11. Huron Harbor, N Y ........................... 
12. Irondequoit Bay, N Y ..................... 
13. Lorain Harbor, Ohio .......................... 
14. New York State Barge Canal ................... 
15. Oak Orchard Harbor, N Y ..................... 
16. Olcott Harbor, N Y ........................... 
17. Port Ontario Harbor, N Y ..................... 
18. Rochester Harbor, N Y ......................... 
19. Rocky River, Ohio ........................... 
20. Sandusky Harbor, Ohio ...................... 
21. Toledo Harbor, Ohio ......................... 
22. Vermilion Harbor, Ohio ................... 
23. West Harbor, Ohio .......................... 
24. Wilson Harbor, N Y .......................... 
25. Reconnaissance and condition surveys ......... 
26. Other authorized navigation projects ........... 
27. Navigation work under special authorization .. . 
Page 
20-1 
20-2 
20-2 
20-2 
20-3 
20-3 
20-4 
20-4 
20-4 
20-5 
20-5 
20-5 
20-6 
20-6 
20-6 
20-6 
20-7 
20-7 
20-7 
20-8 
20-8 
20-8 
20-8 
20-9 
20-9 
20-9 
20-9 
Navigation 
1. ASHTABULA HARBOR, OHIO 
Location. On the south shore of Lake Erie, at mouth of 
Ashtabula River, 59 miles easterly from Cleveland, Ohio. 
(See NOAA Nautical Chart 14836.) 
Previous projects. For details see page 1963 of Annual 
Report for 1915, and page 1593 of Annual Report for 1938. 
Existing project. For description see pages 1297-99 of 
Annual Report for 1966. Federal cost of completed project is 
$12,240,147. Non-Federal costs of $5,743,000, including 
contribution of $47,000, were for construction of access roads, 
docks, storage and handling facilities and dockside dredging. 
Beach Erosion Control Page 
28. Maumee Bay State Park, Ohio ................. 20-9 
29. Presque Isle Peninsula, Erie, Pa .............. 20-10 
30. Other authorized beach erosion 
control projects ........................... 20-11 
31. Beach erosion work under 
special authorization .......................... 20-11 
Flood Control 
32. Ellicott Creek, N Y ....................... 20-11 
33. Mount Morris Lake, N Y 
Genesee River ..................................... 20-11 
34. Ottawa, Ohio .............................. 20-12 
35. Point Place, Toledo, Ohio .................... 20-12 
36. Reno Beach-Howard Farms Area, Ohio ........ 20-12 
37. Inspection of completed flood 
control projects .............................. 20-12 
38. National Emergency Preparedness ............. 20-12 
39. Other authorized flood control projects ........ 20-13 
40. Flood control work under 
special authorization ........................ 20-13 
Deauthorized projects 
41. Deauthorized Projects ....................... 20-13 
General Investigations 
42. Surveys ...................................... 
43. Collection and study of basic data .............. 
44. Advance Engineering & Design ................. 
45. Continuation of Planning and Engineering .... 
20-13 
20-13 
20-13 
20-13 
See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $47,000 for work authorized by 1936 and 1970 
acts. 
Terminal facilities. There are 16 piers and wharves. One 
facility is owned by Coast Guard. Ten facilities are along 
banks of Ashtabula River and six are on southside of outer 
harbor. Eleven terminals have railroad connections and six 
have mechanical handling facilities. Facilities are considered 
adequate for existing commerce. (See Port Series No. 42, 
revised 1972, Corps of Engineers.) 
20-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations and results during fiscal year, Maintenance: 
Real estate activities, condition sediment surveys and reformulation 
and economic analysis regarding dredging of toxic 
materials from upper River by Government plant and hired 
labor cost $81,705. Environmental testing, by contract, and 
supervision and review of that contract cost $32,431. Repairs 
to 25 l.f. of the east and west breakwater by U.S. derrickboat 
McCauley cost $107,777. Removal of 87,000 cubic yards 
shoaled material from outer harbor, by contract, cost $447,912. 
Engineering and design cost $148,530. Supervision and 
administration cost $82,327. 
2. BARCELONA HARBOR, N Y 
Location. On south shore of Lake Erie about 17 miles 
southwesterly of Dunkirk, N Y, and 29 miles northeasterly of 
Erie, Pa. (See NOAA Nautical Chart 14823.) 
Previous projects. Adopted by July 4, 1936, River and 
Harbor Act. Only information available is in index to report 
of Chief of Engineers under title "Portland Harbor, N.Y." 
Existing Project. For description of existing project see 
page 1506 of Annual Report for 1961. Actual costs for new 
work for completed project were $1,124,286. Non-Federal 
costs of $60,000 were incurred by local interests. Of this 
amount, $7,500 was a cash contribution and remainder was 
for providing necessary lands and construction of public 
wharf. Existing project was authorized by the 1945 River and 
Harbor Act (H. Doc. 446, 78th Cong., 2nd sess.). 
Local cooperation. Fully complied with. Local interest 
contributed $7500 for existing project. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, condition sediment surveys 
and real estate activities by Government plant and hired 
labor cost $2,718. 
3. BLACK ROCK CHANNEL AND 
TONAWANDA HARBOR, NY 
Location. Improvement is essentially that of upper 13.5 
miles of Niagara River from its head at Lake Erie, Buffalo, N 
Y, to and including Tonawanda Harbor, N.Y. It comprises 
improvements formerly designated by three titles; viz, Lake 
Erie entrance to Black Rock Harbor and Erie Basin, N Y, 
Black Rock Harbor and Channel, N Y and Tonawanda 
Harbor and Niagara River, N Y (See NOAA Nautical Chart 
14832.) 
Previous projects. For details see item 5 and 7, page 19700f 
Annual Report for 1915, and page 1612 of Annual Report for 
1938. 
Existing project. For description of existing project and 
Federally owned Black Rock ship lock, see page 1548 of 
Annual Report for 1962. Improvement of guide pier at Black 
Rock Lock, as authorized by 1935 act was deauthorized by 
Congress in August 1977. Cost for completed portion of new 
work is $10,457,093. Enlarging of existing 21-foot turning 
basin and deepening lower 1,500 feet of Tonawanda inner 
harbor from 16 to 21 feet, authorized by the 1954 act, was 
deauthorized by Congress in May 1981, and is excluded from 
foregoing cost. Estimated cost, (1961) of this portion is 
$339,000. Non-Federal costs are estimated at $1,540,000 for 
costs incurred by New York State for construction of Erie 
Basin and protecting breakwater, and construction and 
extension of Bird Island Pier, and by other local interest for 
relocation of utilities. See Table 20-B for authorizing 
legislation. 
Local cooperation. Fully complied with for existing 
project. Contract for cost-shared recreation development at 
completed projects (Code 713 program) was executed by the 
New York State Department of Environmental Conservation, 
Albany, N.Y. on April 16, 1985, and was approved by the 
Assistant Secretary of the Army and Chief of Engineers on 
May 3, 1985. 
Terminal facilities. Two facilities are along upstream end 
of channel. Below Black Rock Lock and at Tonawanda 
Harbor there are 13 privately owned terminals. There are two 
State-owned barge canal terminals at Tonawanda, N Y, and 
several marine service and supply docks for recreational and 
other small craft. The Corps owns a wharf adjacent to Black 
Rock Lock which is private. Ten terminals have railroad 
connections and six mechanical-handling facilities. Facilities 
considered adequate for existing commerce. (Port Series No. 
41, revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. Operation and 
care (Black Rock Lock): Lock was in operation 274 days and 
closed for underwater cleaning and repairs from January 6, 
1989 through April 9, 1989. Ordinary maintenance and repair 
of structures and grounds was accomplished throughout the 
year by Government plant and hired labor. Total costs of 
$734,621 were distributed as follows: Operation and care: 
operation of lock, ordinary maintenance and repair $551,530; 
maintenance of grounds $108,811; periodic inspection, real 
estate activities, condition sediment surveys, Commercial 
Activities study and support of Water Control Center $162,862. 
A/E contract for stability analyses of lockwall continued at 
cost of $74,470. Lockwall maintenance by hired labor cost 
$9,868. Rehab/widening of west lockwall, by contract, was 
completed at cost of $136,837. Testing of cable for potential 
voltage, by contract, cost $7,732. Payment from Canada for a 
portion of costs to remove sunken vessel from abutment of 
Peace Bridge within Black Rock Channel resulted in credit 
for snagging and clearing in amount of $499,821. Finalization 
of FY85 contract for repairs at Bird Island Pier by 
settlement of outstanding claim cost $25,437 Federal and 
$150 non-Federal. Engineering and design cost $108,781. 
Supervision and administration cost $48,114. 
4. BUFFALO HARBOR, N Y 
Location. At eastern end of Lake Erie, at head of Niagara 
River, 176 miles easterly from Cleveland, Ohio. (See NOAA 
Nautical Charts 14820 and 14833.) 
Previous projects. For details see page 1967 of Annual 
Report for 1915 and page 1606 of Annual Report for 1938. 
Existing project. For description see page 1368 of Annual 
Report for 1963. In addition, on December 15, 1980, OCE 
authorized the removal of bridge abutments of South 
Michigan Avenue Bridge. New work for completed project 
cost $18,837,601. Estimated non-Federal costs were $9,188,000 
for deepening, widening, and improving Buffalo River and 
ship canal, constructing piers, retaining walls, and dikes and 
performing dockside dredging. See Table 20-B for authorizing 
20-2

BUFFALO, N.Y., DISTRICT 
legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 45 wharves and piers of 
which 4 piers, owned by Niagara Frontier Port Authority, 
and 9 privately owned and operated facilities are on outer 
harbor and along sides of Lackawanna and Union ship 
canal, 4 along banks of Buffalo ship canal, and 26 along 
Buffalo River. Coast Guard facilities are at mouth of Buffalo 
River along left bank. City of Buffalo owns a slip on right 
bank of Buffalo River just north of Michigan Avenue Bridge 
for mooring city fireboat. Thirty-four terminals have railroad 
connections and 29 mechanical-handling facilities. Facilities 
considered adequate for existing commerce. (See Port Series 
No. 41, revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, condition sediment surveys 
by Government plant and hired labor, water control 
management, and real estate activities cost $149,193. Fish and 
plant life study at Times Beach, by contract, cost $58,267. 
Engineering study regarding design deficiency at Times 
Beach dike cost $45,645. Repairs to about 175 l.f. of South and 
Old breakwaters by U.S. derrickboat McCauley cost $159,763. 
Finalization of FY88 dredging contract and settlement of 
claim from FY87 dredging contract cost $60,546. Snagging 
and clearing by Government plant and hired labor cost 
$46,571. Maintenance at Dike 4 and emergency repairs at 
Times Beach disposal area cost $27,102. Engineering and 
design effort cost $19,852. Supervision and administration 
cost $204,984. 
5. CATTARAUGUS HARBOR, N Y 
Location. At mouth of Cattaraugus Creek on south shore 
of Lake Erie about 12 miles northeasterly from Dunkirk 
Harbor, N Y and 24 miles southwesterly from Buffalo 
Harbor, N Y (See NOAA Nautical Chart 14823.) 
Existing project. For details of the existing project, see 
page 32-4 of Annual Report for 1983. Construction was 
completed in January 1983. Total Federal cost for new work 
was $4,804,060. Total non-Federal cost for new work was 
$2,566,529, excluding $20,000 for lands. Existing project was 
authorized by 1968 River and Harbor Act (H. Doc. 97, 90th 
Cong., 1st sess.) 
Local cooperation. See page 32-5 of Annual Report for 
1976 for details of requirements of local cooperation. The 
cash contribution paid was $2,566,529. The State of New 
York executed local cooperation agreement in July 1981. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys and real estate activities 
cost $37,698. Biological testing, by contract, and supervision 
and review of contract cost $4,184. 
6. CLEVELAND HARBOR, OHIO 
Location. On south shore of Lake Erie, at mouth of 
Cuyahoga River, 176 miles westerly from Buffalo, N.Y. (See 
NOAA Nautical Chart 14839). 
Previous projects. For details see page 1962. Annual 
Report for 1915, and page 1585, Annual Report for 1938. 
Existing Project. For description of existing project, as 
authorized through the 1967. Further improvements through 
the 1966 modification, see page 1269 of Annual Report for 
1967. Further improvements in the interest of commercial 
navigation and recreational navigation were authorized in 
the 1985 Supplemental Appropriations Act (PL 99-88), at a 
cost not to exceed $36,000,000. The commercial navigation 
portion of the overall project consists of: (a) enlarging and 
deepening to 31 feet LWD the east entrance channel; (b) 
deepening the east basin channel to 27 feet LWD; and (c) 
expanding the capacity of Dike Site 14 to contain the 
polluted dredged material resulting from the project. This 
portion of the project is currently on hold as the local sponsor 
has assigned this aspect a lower priority. The recreational 
navigation portion of the overall project consists of: an 
entrance channel 100 feet by 540 feet in length dredged to 8 
feet below Low Water Datum (LWD) and the associated 375 
feet of bulkheading along the west side of Pier 34; a 386 foot 
west breakwater with a 20 foot top width, shore arm 
connection to Pier 32 and associated 406 feet of bulkheading; 
a 485 foot north breakwater including 635 feet of bulkheading 
along the north end of Pier 34 extending to and 
along the west end of Pier 36 and 1.8 acres of fill between Pier 
34 and Pier 36; and, a combined 6.4 acre turning basin, 
anchorage area, and harbor-of-refuge with a dredged depth 
varying between 7 and 8 feet below LWD and the 1,223 feet of 
bulkheading around the combined area; 2,093 feet of walkway 
4 feet wide along the north breakwater bulkheading and the 
anchorage area; and 2,593 linear feet of suitable handrail for 
safety along the north and west breakwaters and the 
anchorage area. The basis for these recreational features is a 
report titled "North Coast Harbor/Pier 34, Cleveland 
Harbor, Ohio" prepared by CENCB in December 1988. A 
portion of the recreational navigation project has been 
completed by the Ohio Department of Natural Resources. 
The recreational navigation project was also authorized by 
the Water Resources Development Act of 1986 (PL 99-662) 
and the FY88 Energy and Water Appropriations Act (PL 
100-202). These acts also authorized additional undefined 
improvements to Cleveland Harbor. Estimated total Federal 
cost of the existing project is $40,084,100 (Oct. 1988) exclusive 
of undefined, inactive and deferred portions of the project. 
The amount of $29,315,100 is for completed work and the 
balance of $10,769,000 is for new work. Estimated non- 
Federal cost is $15,157,000 (Oct. 1988) of which $9,203,000 is 
actual cost for completed work and the balance of $5,954,000 
is required for work authorized by PL 99-88, PL 99-662, and 
PL 100-202. Remaining work authorized by 1946 River and 
Harbor Act, consisting of widening and deepening the right 
bank of Cuyahoga River at the downstream end of Cut 4, is 
considered inactive and excluded from foregoing cost 
estimate. Estimated Federal cost (1966) of this portion is 
$85,600 and non-Federal cost (1966) $5,000,000. Remaining 
work authorized by 1958 R&H Act, consisting of planning 
and replacement of bridges number 19 (E.L.R.R.) and 32 
(B.&O.R.R.) and widening Cuyahoga and Old River 
channels, and remaining work authorized by the 1960 RScH 
Act, consisting of deepening the remainder of Cuyahoga 
River from bridge number 1 to and including the Old River 
to a depth of 27 feet, has been classified as deferred and is also 
excluded from foregoing cost estimate. Estimated Federal 
cost (Oct. 1976) of this portion is $18,033,300 and estimated 
non-Federal cost (Oct. 1976) is $21,251,000. See Table 20-B for 
20-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
authorizing legislation. 
Local cooperation. For details of local cooperation, see 
page 32-4 of FY 87 Annual Report. 
Terminal facilities. There are 65 piers and wharves. 
Fourteen are located in the outer harbor, 11 on banks of Old 
River, 40 along the deep-draft section of Cuyahoga River. 
Forty-one terminals have both railroad connections and 
mechanical-handling facilities. The Corps owns a wharf at 
the foot of East 9th Street. Facilities are considered adequate 
for existing commerce. (See Port Series No. 43, revised 1981, 
Corps of Engineers). 
Operations and results during fiscal year. New Work: 
Coordination with local interests, completion of the report 
entitled "North Cost Harbor/Pier 34, Cleveland Harbor, 
OH," a draft PL 100-202 Agreement and draft Local 
Cooperation Agreement for the recreational navigation 
portion of the authorized project were provided at a cost of 
$127,579. Maintenance: Miscellaneous inspection services, 
condition sediment surveys, letter report on new confined 
disposal facility and associated testing, and real estate 
activities cost. $296,926. Environmental testing, by contract, 
and supervision and review of that contract cost $82,602. 
Repairs to 225 l.f. of east and west arrowhead breakwaters 
and east breakwater by U.S. derrickboat Simonsen cost 
$791,739. Removal of approximately 21,636 cubic yards of 
shoaled material from Cuyahoga River, by contract, cost 
$308,119. Repairs to east breakwater, by contract, were 
continued at cost of $1,123,948. Botulism control for confined 
disposal facility cost $4,716. Engineering and design costs 
were $310,449. Supervision and administration cost $522,155. 
7. CONNEAUT HARBOR, OHIO 
Location. On the south shore of Lake Erie, at mouth of 
Conneaut River, 73 miles easterly from Cleveland, Ohio (See 
NOAA Nautical Chart 14824.) 
Previous projects. For details see page 1964, Annual 
Report for 1915. 
Existing projects. For description see page 1274 of Annual 
Report for 1967. Actual costs for new work for completed 
portion of the project were $7,541,369. See page 1274, Annual 
Report for 1967, for complete description of project modification 
authorized by 1966 R&H Act. Estimated cost (1970) of 
this modification is $717,000. For completed work non- 
Federal costs were $200,000 for dockside dredging and 
removal of existing dolphins. Estimated non-Federal cost of 
$2,877,000 (1970) includes cash contribution of $717,000 and 
the remainder is for the construction of service facilities for 
the 1966 project modification. See Table 20-B for authorizing 
legislation. 
Local cooperation. Fully complied with for completed 
portion of project. See page 32-6 of Annual Report for 1971 
for requirements of local cooperation for project modification 
as authorized by the River and Harbor Act of 1966. 
Terminal facilities. There are seven piers and wharves. Six 
are privately owned and operated and located in inner 
harbor. Remaining facility is city owned on the south side of 
outer harbor. Six terminals have railroad connections and 
four mechanical-handling facilities. (See Port Series No. 42, 
revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and condition sediment 
surveys were done by Government plant and hired labor and 
cost $26,322. Finalization of FY88 dredging contract resulted 
in cost of $68,885. Engineering and design effort cost $1,329. 
Supervision and administration cost $41,334. 
8. DUNKIRK HARBOR, N Y 
Location. On south shore of Lake Erie, 37 miles southwesterly 
from Buffalo, N Y (See NOAA Nautical Chart 
14823.) 
Previous projects. For details see page 1966 of Annual 
Report for 1915, and page 1604 of Annual Report for 1938. 
Existing project. For description of completed portion of 
existing project see page 32-8 of Annual Report for 1976. For 
description of small boat harbor project as authorized under 
Section 201 of Flood Control Act of 1965, see page 32-8 of 
Annual Report for 1978. Actual costs for completed work are 
$3,010,024. Actual non-Federal costs are $1,961,000. See Table 
20-B for authorizing legislation. 
Local cooperation. Fully complied with 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys and deficiency study by 
Government plant and hired labor cost $14,693. U.S. derrickboat 
McCauley repaired 1001.f. of the U.S. breakwater at cost 
of $148,751. Supervision and administration cost $3,217. 
9. ERIE HARBOR, PA 
Location. On southerly side of bay formed by Presque Isle 
Peninsula, on south shore of Lake Erie, 78 Miles westerly 
from Buffalo, N Y (See NOAA Nautical Chart 14835.) 
Previous projects. For details see page 1965 of Annual 
Report for 1915 and page 1600 of Annual Report for 1938. 
Existing projects. For description see pages 1363-64 of 
Annual Report for 1963. Entire project modification 
authorized by 1945 River and Harbor Act, providing for 
deepening channel and basin, both 23 feet deep, to Penn 
Central Company coal docks at westerly end of harbor, was 
deauthorized by Congress in August 1977. Actual costs for 
new work for completed portion of project were $2,860,906. 
Extension of north pier portion, authorized by 1899 act was 
deauthorized in November 1981. Estimated cost (1955) of this 
portion is $1,071,000. A portion of work authorized by 1960 
act, deepening strips adjacent to north and south piers, was 
deauthorized in August 1982. Estimated cost (July 1962) of 
this portion is $78,000. Non-Federal costs for completed 
work were $51,000 for providing ore dock and dredging slip 
adjacent thereto. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Sixteen piers and wharves, of which 12 
are privately owned and operated. Erie International Marine 
Terminal No. 1 owned by Port Commission, city of Erie, is 
along main waterfront on south side of Presque Isle Bay and 
Coast Guard facilities are on north side. Two offshore oil 
docks are on Lake Erie. Eight terminals have railroad 
connections and six mechanical-handling facilities. Facilities. 
20-4

BUFFALO, N.Y., DISTRICT 
are considered adequate for existing commerce. (See port 
Series No. 42, revised 1972, Corps of Engineers.) 
Operations and result during fiscal year. Maintenance: 
Miscellaneous inspection services, condition sediment 
surveys, and real estate activities by Government plant and 
hired labor cost $28,295. Contract for repair of north pier by 
placing stone along the toe, cost $266,500. Realignment and 
strapping of steel sheetpiling at north pier by Government 
plant and hired labor cost $35,462. Engineering and design 
efforts cost $50,795. Supervision and administration cost 
$23,301. 
10. FAIRPORT HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of Grand 
River, 33 miles easterly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14837.) 
Previous projects. For details see page 1963 of Annual 
Report for 1915, and page 1590 of Annual Report for 1938. 
Existing project. For description of existing project as 
authorized through the 1960 modifications, see page 1526 of 
Annual Report for 1962; for description of small boat harbor 
as authorized by Sec. 201 of 1965 Flood Control Act, see page 
32-10 of Annual Report for 1977. Estimated total Federal cost 
of new work is $4,931,000 (Oct. 1980) of which $2,591,000 is 
actual cost for completed portion of project and the balance 
of $2,340,000 is for proposed work authorized by Sec. 201 of 
1965 FC Act which is deferred. Entire project modification 
authorized by 1960 River and Harbor Act, providing for 
deepening lake approach channel, 800-foot wide channel 
through outer harbor and channel in Grand River, and 
enlargement of turning basin, is classified inactive and is 
excluded from foregoing cost. Estimated cost of this 
modification is $3,170,000 (1963). Estimated non-Federal cost 
is $4,991,000 of which $101,000 were for bulkheads and 
dockside dredging for completed portion of project and 
$2,560, 000 which includes cash contribution of $2,330,000, is 
for work authorized by Sec. 201 of 1965 FC Act. For the 
inactive 1960 project modification, estimated non-Federal 
cost of $3,821,000 (1963) is for lands, relocations, utility 
changes, dock dredging and dock and bulkhead modifications. 
See Table 20-B for authorizing legislation. 
Local cooperation. See page 32-11 of 1976 Annual Report 
regarding assurances of local cooperation for work authorized 
by R&H Acts of 1927 and 1960 and page 32-11 of 1977 Annual 
Report for requirements of local cooperation for work 
authorized by Sec. 201 of 1965 Flood Control Act. 
Terminal facilities. Sixteen piers and wharves, all along 
banks of Grand River. One facility is owned by Coast Guard. 
Nine terminals have railroad connections and ten mechanical-
handling facilities. Facilities considered adequate for 
existing commerce. (See Port Series No. 42, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, real estate activities, and 
condition sediment surveys by Government plant and hired 
labor, cost $28,315. U.S. derrickboat McCauley repaired 130 
1.f. of outer breakwaters at cost of $115,350. Dredging, by 
contract, removed 131,845 cubic yards of shoaled material, 
and cost $654,019. Engineering and design effort cost $18,869. 
Supervision and administration cost $78,853. 
11. HURON HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of Huron 
River, 47 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chapit 14843.) 
Previous project. For details, see page 1961 of Annual 
Report for 1915, and page 1576 of Annual Report for 1938. 
Existing project. For description, see page 1347 of Annual 
Report for 1963 and page 32-12 of Annual Report for 1978. 
Cost of completed portion of existing project was $4,834,006. 
Construction of detached breakwater as authorized by 1962 
R&H Act is deferred. Estimated cost of construction of 
breakwater is $12,970,000 (July 1972). Non-Federal costs of 
$163,000 were incurred by local interests in 1963 for dockside 
dredging of areas between Federal improvement and terminal 
facilities. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Six privately owned wharves and 
docks, one along left bank of Huron River and remainder 
along right bank. Four terminals have railroad connections 
and four mechanical-handling facilities. Facilities are 
regarded as adequate for existing commerce. (See Port Series 
No. 42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and condition sediment 
surveys by Government plant and hired labor cost $22,146. 
Finalization of FY87 dredging contract resulted in credit of 
$31,714. Engineering and design costs were $8,499. Supervision 
and administration cost $31,693. 
12. IRONDEQUOIT BAY, N Y 
Location. On south shore of Lake Ontario, 4 miles east of 
Rochester, N Y at mouth of Irondequoit Creek, Monroe 
County, N Y (See NOAA Nautical Charts 14804 and 14815). 
Existing project. For details of existing project, see page 
32-7 of Annual Report for FY 87. Total estimated project cost 
is $15,363,000 (Oct. 1984) including $3,582,000 Federal (which 
includes the CoE $3,536,000 and the USCG $46,000) and 
$11,781,000 non-Federal, including a cash contribution of 
$2,661,000, lands and damages $290,000 and the cost of a 
movable highway bridge $8,830,000. Existing project was 
authorized by 1958 River and Harbor Act (H. Doc 332, 84th 
Cong., 2d sess.) 
Local cooperation. The Buffalo District has a properly 
executed Local Cooperation Agreement with New York 
State, executed April 20, 1983. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. New Work: 
Project is physically complete, including upland recreation 
features. FY89 Non-Federal contract cost including supervision 
and administration was $62,683. Federal cost were $96. 
Construction of the recreational facilities was completed in 
August 1987. Maintenance: Miscellaneous inspection services, 
real estate activities and condition sediment surveys by 
Government plant and hired labor cost $3,901. Finalization 
of FY88 dredging contract cost $7,006. Engineering and 
design effort cost $4,323. Supervision and administration 
cost $9,529. 
20-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
13. LORAIN HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of Black 
River, 25 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14841.) 
Previous projects. For details, see page 1961 of Annual 
Report for 1915, and page 1580 of Annual Report for 1938. 
Existing project. For description see pages 1319-22 of 
Annual Report for 1966. Estimated Federal cost of new work 
is $26,246,000 (Oct. 1976). Deepening and widening remainder 
of Black River Channel at Cut 1 and construction of bank 
stabilization as authorized by 1960 act and modified by 1965 
act is classified deferred. The estimated cost of $5,317,000 for 
this work is included in the above estimate. A portion of work 
authorized by 1960 act, dredging of 15-to-25 foot wide strips 
adjacent to the U.S. East and West piers is also deferred and 
estimated cost of $60,200 (July 1966) is excluded from 
foregoing cost estimate. Total non-Federal cost estimate is 
$8,853,000 (Oct. 1976) including $3,000 contributed by local 
interests toward construction of west shorearm. For work 
authorized by 1960 act, including deferred portion, non- 
Federal costs are estimated to be $8,805,000 for lands, 
relocations of utilities, modifications of existing docks and 
bulkheads, construction of new bulkheads and dockside 
dredging. For work authorized by 1965 act, classified as 
deferred, local interests must make a cash contribution 
presently estimated to be $45,000. See Table 20-B for 
authorizing legislation. The Water Resources Development 
Act (WRDA) of 1986 (PL 99-662) authorized construction of 
commercial navigation improvements consisting of two 
bend cuts on the Black River to widen and straighten the 
channel between the Norfolk and Western Railroad Bridge 
and the 21st Street Bridge. These cuts are to be excavated to 
the existing channel depth of 27 feet. The authorized plan 
also includes widening the Upper Turning Basin at the 
existing depth of 21 feet. Estimated costs for this work are 
$3,750,000 Federal and $2,110,000 non-Federal (Oct. 1988). 
On March 12, 1986 the Chief of Engineers under authority of 
Section 107 of the 1960 River and Harbors Act, as amended 
authorized construction of a small boat harbor which was 
completed in July 1987. The project consists of a 225-foot 
detached rubblemound breakwater and an 800-foot long 
rubblemound breakwater attached to the east breakwater 
shorearm in the east basin of the outer harbor. Construction 
costs for this project, including supervision and administration, 
were $775,025 Federal and $775,025 non-Federal. 
Local cooperation. For completed work, local interests 
contributed $3,000. Work authorized by 1960 act (and modified 
by 1965 act) is deferred. All other conditions fully complied 
with. On March 25, 1986, the city of Lorain, Ohio signed the 
local cooperation agreement, for the Section 107 project. For 
details see page 32-7 of Annual Report for 1986. For details of 
local cooperation agreement for project authorized by the 
1986 WRDA, see page 32-9 of Annual Report for FY87. 
Terminal facilities. There are 23 piers and wharves, of 
which three are on outer harbor and remainder are along 
banks of Black River. Two are owned by the city. Eight 
terminals have railroad connections and 15 mechanicalhandling 
facilities. Facilities are considerd adequate for 
existing commerce. (See Port Series No. 42, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. New Work: 
Federal advance engineering and design (Preconstruction 
Engineering and Design) funds in the amount of $281,336 
were expended on in-house engineering effort for project 
authorized by the 1986 WRDA. This includes $104,917 for a 
vessel simulation model study (Phase II) conducted at the 
Waterways Experiment Station, Vicksburg, Mississippi. Maintenance: 
Miscellaneous inspection services, real estate activities, 
and condition sediment surveys by Government plant 
and hired labor cost $42,788. Repairs to 150 l.f. of east 
breakwater and diked disposal area by the U.S. derrickboat 
Simonsen cost $394,868. Engineering and design effort cost 
$21,514. Supervision and administration cost $80,182. 
14. NEW YORK STATE BARGE CANAL 
Location. Erie, Niagara, Orleans, Monroe, Wayne, 
Seneca, Cayuga, Onondaga, Oswego, Oneida and Herkimer 
Counties, N Y (within the Buffalo District). 
Existing project. The NY State Barge Canal system has 57 
locks, 524 miles of canals, over 100 dams and numerous 
roads, bridges, buildings and other structures. The Barge 
Canal was built and is owned by New York State. Existing 
project was authorized by PL 99-662, the Water Resources 
Development Act of 1986. 
Local cooperation. There is no cooperative agreement as 
yet on this project. 
Operations and results during fiscal year: Maintenance: 
Coordination between NY State and Department of Army 
cost $9,493. 
15. OAK ORCHARD HARBOR, N Y 
Location. On south shore of Lake Ontario at mouth of 
Oak Orchard Creek, 33 miles westerly of Rochester, N Y (See 
NOAA Nautical Chart 14805.) 
Previous project. For details see page 628 of Annual Report 
for 1905. 
Existing project. For description of completed existing 
project see page 32-14 of 1975 Annual Report. Actual Federal 
cost for completed project was $1,613,500. Estimated non- 
Federal cost is $270,000 (July 1971) including cash contribution 
of $170,700 and $54,002 for recreational facilities and 
remainder for lands and construction of wharf. Existing 
project was authorized by the 1945 River and Harbor Act (H. 
Doc. 446, 78th Cong., 2d sess.) 
Local cooperation. Fully complied with. Local interests 
contributed $224,702. 
Terminal facilities. There is no commercial navigation at 
Oak Orchard Harbor. Terminal facilities consist of private 
docks for recreational craft. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys, real estate activities and 
economic evaluation cost $10,440. 
16, OLCOTT HARBOR, N Y 
Location. On south shore of Lake Ontario at mouth of 
Eighteen Mile Creek about 18 miles east of mouth of Niagara 
River and 63 miles by water west of Rochester, N Y (See 
NOAA Nautical Chart 14806.) 
20-6

BUFFALO, N.Y., DISTRICT 
Previous project. For details see page 1971 of Annual 
Report for 1915 and page 1621 of Annual Report for 1938. 
Existing project. For description, see page 1555 of Annual 
Report for 1962. Cost of new work for completed project was 
$1,500 exclusive of amounts expended on previous projects, 
all of which was contributed by local interests. See Table 20-B 
for authorizing legislation. The authorized modification to 
the existing project consists of breakwaters to provide 
optimum harbor protection, channel dredging, a stone jetty 
and recreational fishing facilities including a foot bridge, 
walkways and guardrails, access facilities, sanitary facilities 
and parking areas. The estimated cost of the authorized 
modifications is $13,280,000 (October 1988) of which 
$6,680,000 is Federal (80,000 USCG) and $6,600,000 is non- 
Federal. Modification of the existing project was authorized 
by the 1986 Water Resources Development Act (WRDA) (PL 
99-662). 
Local cooperation. Fully complied with for completed 
project. Local interests contributed $1,500. Modifications 
authorized by the 1986 WRDA will require local interests to 
pay 50% of project cost including lands, easements, rights-ofway 
and dredge disposal areas. They are also responsible for 
construction of necessary docks and berthing spaces, construction 
of launching ramp, parking areas, sanitary facilities, 
and necessary access roads. After construction, non-Federal 
responsibilities would include fishing facility maintenance, 
except for the aids to navigation. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. New Work: Inhouse 
engineering effort for Advance Engineering and 
Design Preconstruction Engineering and Design for FY89 
was $494,360. Maintenance: Project condition sediment 
surveys, real estate activities and update of Environmental 
Impact Statement cost $16,374. 
17. PORT ONTARIO HARBOR, N Y 
Location. On southeasterly end of Lake Ontario, 19 miles 
northeasterly of Oswego, N Y and 32 miles southerly of 
Sackets Harbor, N Y (See NOAA Nautical Chart 14803.) 
Previous projects. Adopted by the River and Harbor Act 
July 4, 1836. Only information available is the index to the 
report of the Chief of Engineers. 
Existing project. As modified by Phase I and II General 
Design Memorandum, provides for: (a) two shore connected 
rubblemound breakwaters in Lake Ontario at mouth of 
Salmon River, south breakwater about 1,350 feet and north 
breakwater about 350 feet long; (b) entrance channel between 
breakwaters, 100 feet wide and 8 feet deep, from deep water in 
lake to a limit about 1,200 feet from 8-foot depth contour in 
lake; (c) river channel 85 feet wide and 6 feet deep from inner 
limit of entrance channel for a distance upstream of about 
450 feet. Estimated Federal cost for project is $2,350,000 (Oct. 
1987). Estimated non-Federal cost for new work is $1,670,000 
(Oct. 1987) including cash contribution of $1,350,000. 
Existing project was authorized by the River and Harbor Act 
of March 2, 1945 (H. Doc. 446, 78th Cong., 2d sess.). 
Local cooperation. See page 32-16 of Annual Report for 
1976 for details of requirements of local cooperation. Assurances 
have been received from the New York State Office 
of Parks, Recreation and Historic Preservation. The LCA 
was executed on June 24, 1986. 
Terminal facilities. The only commercial navigation at 
Port Ontario is charter boat fishing. Terminal facilities 
consist of private docks for recreational craft. 
Operations and results during fiscal year. New Work: 
Actual construction of the project was completed in October 
1987. Federal in-house engineering effort cost $14,818. 
Contract supervision and administration cost $1,332. Non- 
Federal costs for in-house engineering effort were $556. 
Maintenance: Condition sediment surveys and real estate 
activities cost $4,893. 
18. ROCHESTER HARBOR, N Y 
Location. On south shore of Lake Ontario, at mouth of 
Genesee River, 59 miles westerly from Oswego, N,Y. (See 
NOAA Nautical Chart 14815.) 
Previous project. For details see page 1471 of Annual 
Report for 1915, and page 1623 of Annual Report for 1938. 
Existing project. For description see page 1556 of Annual 
Report for 1962. Actual cost for new work for completed 
project is $2,191,514. Non-Federal costs are estimated at 
$2,260,000, all for 1960 Act, for lands, relocation of submarine 
cable crossing, relocations of small docks and boathouses, 
dockside dredging, structure modifications, and replacement 
of Baltimore & Ohio coal loader. See Table 20-B for 
authorizing legislation. 
Local cooperation. Complied with except provision for 
replacement of coal loading facility as required by River and 
Harbor Act of July 14, 1960. 
Terminal facilities. One terminal facility at mouth of 
Genesee River has been leased to the Great Lakes Division of 
Pittston Stevedoring Corp. Facilities also consist of private 
docks for recreational craft and privately owned servicing 
and storage handling facilities for recreational and other 
small craft. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, real estate activities, and 
condition and sediment surveys by Government plant and 
hired labor cost $29,317. Finalization of FY88 structure repair 
contract resulted in credit of $9,265. Finalization of FY88 
dredging contract resulted in credit of $20,666. Engineering 
and design effort cost $27,215. Supervision and administration 
cost $50,535. 
19. ROCKY RIVER HARBOR, OHIO 
Location. At mouth of Rocky River which empties into 
Lake Erie 7 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14826.) 
Existing project. For description see page 1329 of Annual 
Report for 1966. Federal cost for completed project was 
$343,494 and non-Federal cost was a cash contribution of 
$249,346. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $249,346 for new work. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately-owned servicing and storage 
20-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and project condition 
sediment surveys by Government plant and hired labor cost 
$18,301. 
20. SANDUSKY HARBOR, OHIO 
Location. On south shore of Lake Erie, in southeasterly 
portion of Sandusky Bay, 50 miles westerly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14845.) 
Previous projects. For details see page 1960 of Annual 
Report for 1915, and page 1574 of Annual Report for 1938. 
Existing project. For description see pages 1511-12 of 
Annual Report for 1962. Actual costs for new work for 
completed project were $6,250,121, excluding $325,000 
contributed by local interests. Non-Federal costs for completed 
project are estimated at $675,000, including $325,000 
cash contribution and the remaining $350,000 is for dockside 
dredging adjacent to deepened channels authorized by 1960 
Act. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $325,000 for new work. 
Terminal facilites. Fourteen piers and wharves, three at 
west end of harbor and remainder along dock channel. One is 
a base for State-owned fish research and patrol boats. One 
publicly owned and six privately owned are used for mooring 
fishing boats and recreational craft and for ferry service. Five 
terminals have railroad connections and five mechanicalhandling 
facilities. Facilities are considered adequate for 
existing commerce. (See Port Series No. 42, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and condition sediment 
surveys by Government plant and hired labor cost $67,062. 
Removal of 46,976 cubic yards shoaled material, by contract, 
cost $240,158. Supervision and administration cost $103,889. 
Engineering and design effort cost $25,976. Finalization of 
dredging contract resulted in a net credit of $4,554 to the 
non-Federal account. 
21. TOLEDO HARBOR, OHIO 
Location. Comprises lower 7 miles of Maumee River and 
channel through Maumee Bay to Lake Erie. Maumee River 
has its source in northern Indiana and empties into Lake 
Erie. Harbor is at westerly end of Lake Erie, 99 miles westerly 
from Cleveland, Ohio. (See NOAA Nautical Chart 14847.) 
Previous projects. For details see page 1959 of Annual 
Report for 1915, and page 1565 of Annual Report for 1938. 
Existing project. For description of existing project see 
pages 32-18 and -19 of Annual Report for 1978. Cost of 
completed existing project was $15,567,147. See Table 20-B 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Maumee River through city of Toledo 
has been developed extensively for deep-draft navigation. 
Detailed information on actual port and harbor facilities are 
in Port Series No. 44 (revised 1972) prepared and published as 
Part 2, by board of Engineers for Rivers and Harbors. 
Information on port administration and Federal services, 
port and terminal services and charges, and steamship 
services is prepared and published as Part 1 by the Port 
Development Staff, U.S. Department of Commerce. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition sediment surveys, economic and environmental 
studies, and real estate activities cost $257,620. Environmental 
testing, by contract, cost $12,000; supervision and 
review of that contract cost $5,632. In-house study to develop 
additional uses for dredged material cost $48,430. A/E 
contract to study alternative methods of moving dredged 
material from site cost $40,715. A/E contract for Maumee Bay 
Bottom Sedimentation/Characterization Study to determine 
more and better areas for dumping dredged material was 
completed at a cost of $49,915; supervision and review of that 
contract cost $20,096. Contract for obstruction removal from 
FY88 was finalized at cost of $15,384. Removal of estimated 
480,000 cubic yards of shoaled material from Bay Channel 
and Maumee River Channel, by contract, cost $1,820,032. 
Repairs to confined disposal facility by hired labor cost 
$48,030. Engineering and design cost $226,594. Supervision 
and administration cost $234,600. 
22. VERMILION HARBOR, OHIO 
Location. On south shore of Lake Erie at mouth of 
Vermilion River, 37 miles westerly from Cleveland, Ohio, 
(See NOAA Nautical Chart 14826.) 
Existing project. For description of existing project see 
pages 32-17 and 32-18 of Annual Report for 1975. Actual 
Federal cost for the completed existing project was $1,156,118. 
Estimated non-Federal cost for new work is $754,679 
including cash contribution of $740,679 and remainder for 
relocation of submarine cable and construction of public 
wharf. See Table 20. B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $740,679. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous studies, condition sediment surveys and real 
estate activities by Government plant and hired labor cost 
$25,951. Supervision and administration cost $5,990. 
23. WEST HARBOR, OHIO 
Location. On southwest shore of Lake Erie, 13 miles 
northeast of Port Clinton, Ohio. (See NOAA Nautical Chart 
14847.) 
Existing project. For description of existing project, see 
page 32-10 of Annual Report for 1983. Total Federal cost for 
new work was $3,303,898. Total non-Federal cost for new 
work was $3,922,000 including cash contribution of 
$3,795,000. Existing project was authorized by 1965 River 
and Harbor Act (H. Doc. 245, 88th Cong., 2d sess.) 
Local cooperation. See page 32-20of 1978 Annual Report 
for requirement of local cooperation. By letter dated January 
31, 1978, State of Ohio stated its intent to furnish assurances 
of local cooperation, and executed LCA was received on 
March 9, 1981. 
20-8

BUFFALO, N.Y., DISTRICT 
Terminal facilities. Commerce at the harbor presently 
consists of recreational boating and affiliated activities. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous reports and condition sediment surveys cost 
$35,696. Maintenance dredging, by contract, cost $407,420, 
and removed approximately 70,389 cubic yards of shoaled 
material. Engineering and design costs were $221. Supervision 
and administration costs were $44,091. 
24. WILSON HARBOR, N Y 
Location. At mouth of east branch of Twelve Mile Creek, 
which enters Lake Ontario 12 miles easterly of mouth of 
Niagara River, and 67 miles westerly of Rochester Harbor, 
N Y (See NOAA Nautical Chart 14806). 
Previous project. For details see page 2395 of Annual 
Report for 1889, and page 628 of Annual Report for 1905. 
Existing project. For description see page 32-18 of Annual 
Report for 1975. Actual Federal cost for the completed 
existing project was $477,904. Estimated non-Federal costs 
are $774,000 which includes cost of $16,000 for previously 
completed work. Remainder of non-Federal costs are for 
work required for 1968 R&cH Act including cash contribution 
of $166,988. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous studies, condition sediment surveys and real 
estate activities cost $16,176. Supervision and administration 
cost $6,415. 
25. RECONNAISSANCE AND 
CONDITION SURVEYS 
Condition surveys were performed by the Buffalo District 
at a cost of $20,808. Environmental Impact Statement update 
cost $18,977. Real estate activities, to include utilization 
inspections, cost $8,748. Supervision and administration, to 
include program management for activities, cost $6,220. 
Project Date of Survey 
Niagara River, NY Sept 1989 
Little Sodus, NY Aug 1989 
Great Sodus, NY Aug 1989 
Pt. Clinton, OH July 1989 
26. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 20-C. 
27. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 20-G. 
STURGEON POINT, EVANS, NY 
Location. On south shore of Lake Erie, 17 miles southwest 
of Buffalo, NY and 22 miles northeast of Dunkirk, NY. (See 
Geological Survey map for Angola, NY). 
Existing project. Project was authorized for construction 
by the Chief of Engineers pursuant to Section 107 of the 1960 
River and Harbors Act, as amended, on October 21, 1987. The 
project provides for rehabilitation of the existing breakwater 
with a rubblemound facing and raised concrete walkway, 
construction of a rubblemound west breakwater extension, 
construction of a rubblemound east breakwater, a shore 
revetment, and dredging. The project will provide needed 
access to Lake Erie between Buffalo and Dunkirk, NY. The 
marina will provide mooring for 210-230 boats, provide 
protection and access to the lake for the trailered boat launch 
ramp and provide fishing access for non-boaters. The non- 
Federal sponsor (Town of Evans, NY) is required to provide 
approximately 50% of the cost of the general navigation 
features, provide the lands, easements and rights of way, 
relocations, dredging into the mooring area, docking 
facilities, and upland improvements. Estimated Federal 
project cost is $1,460,000 (October 1987). Estimated non- 
Federal project cost is $1,475,000 (October 1987). In addition, 
the local sponsor is required to provide associated costs 
estimated at $1,000,000. 
Local cooperation. The Buffalo District has a properly 
executed Local Cooperation Agreement with the Town of 
Evans, NY, signed October 26, 1987. 
Operations and results during fiscal year. New Work: 
Project construction was 100% complete in December 1988. 
Balancing of Federal and non-Federal shares resulted in a net 
Federal credit to the contract of $183,172, including supervision 
and administration, and a net credit of $85,786 for 
in-house engineering effort. Additional Federal in-house 
engineering effort cost $125,041. Non-Federal contract cost, 
including supervision and administration was $866,941. Inhouse 
engineering effort cost $81,743. 
Investigation and removal of sunken vessels and other 
obstructions to navigation under authority of Section 19 of 
the River and Harbor Act of 1899. 
Billing from NAVSEACOM for removal of sunken Barge 
No. 45, pinned against the upstream face of Peace Bridge pier 
4, on the Niagara River was continued at a cost of $378,921. 
Navigation work pursuant to Section 111, Public Law 
90-483. 
Fairport Harbor, OH - Costs of $40 were incurred for 
preauthorization studies. 
Lorain Harbor, OH - Costs of $9,298 were incurred for 
preauthorization studies. 
Sandusky Harbor, OH - Costs of $4,315 were incurred for 
preauthorization studies. 
West Harbor, Ottawa, OH - Costs of $3,995 were incurred 
for preauthorization studies. 
Navigation work pursuant to Section 208, Public Law 
83-780. 
Unnamed Tributary of Lake Erie, Blasdell - Costs of $3,149 
for preauthorization studies. 
Beach Erosion Control 
28. MAUMEE BAY STATE PARK, OHIO 
Location. Maumee Bay State Park is located in Lucas 
County, OH approximately 5 miles east of Toledo. The 1,855 
20-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
acre park has 11,000 feet of shoreline along the southerly end 
of Maumee Bay (Lake Erie). (See U.S. Geological Survey 
Map, Oregon, OH). 
Existing project. The study for Maumee Bay was conducted 
under the Western Lake Erie Shore Study authorized by the 
Committee on Public Works of the House of Representatives 
on April 11I, 1974. The project was authorized for construction 
by the 1986 Water Resources Development Act (PL 99-662), 
November 17, 1986. The recommended plan as described in 
the General Design Memorandum (May 1988) consists of a 
2500 ft. long protective sand beach stabilized by rubblemound 
breakwaters and jetties, in addition to a 2700 ft. long 
rubblemound revetment along the west half (5,200 ft.) of park 
shoreline. The authorized plan also included a rubblemound 
revetment along the easterly half of the park shoreline. 
However, in July 1986, the Ohio Department of Natural 
Resources initiated advance construction of the rubblemound 
revetment and work was completed in February 1987. This 
has reduced the estimated cost of the project to $10,290,000 
(Oct. 1988) of which $2,870,000 is Federal cost and $7,420,000 
is non-Federal cost including lands, utilities and other 
recreation facilities. 
Local cooperation. For details of local cooperation, see 
page 32-14 of FY 87 Annual Report. 
Operations and results during fiscal year. New Work: 
Plans and Specifications for the project were completed in 
September 1989. In-house engineering effort cost $27,250 
under Advance Engineering and Design, Preconstruction 
Engineering and Design and $109,566 under the Construction 
General Appropriation. 
29. PRESQUE ISLE PENINSULA, ERIE, PA 
Location. At Erie, Pa., on south shore of Lake Erie, 78 
miles southwest of Buffalo, N Y and 102 miles eastnortheast 
of Cleveland, Ohio. (See NOAA Nautical Charts 14824 and 
14835). 
Existing project. For description of completed portion of 
existing project see page 1393 of Annual Report for 1963. For 
details of project authorized by the 1974 Water Resources 
Development Act (WRDA), 1976 WRDA and 1986 WRDA, 
see page 32-14 of Annual Report for FY 87. Estimated Federal 
cost for the authorized project modifications (Oct. 1988) is 
$16,379,000 which includes $5,646,000 for completed work 
authorized by the 1954 and 1960 R&H Acts and 1974 WRD Act 
and $10,773,000 for completed work authorized by the 1976 
WRD Act. Estimated non-Federal cost for the authorized 
project and modifications (Oct. 1988) is $8,579,000 which 
includes $3,983,000 for completed work authorized by 1954 
and 1960 R&H Acts and 1974 WRD Act and $4,596,000 for 
completed work authorized by the 1976 WRD Act. The 
estimated Federal cost (Oct. 1988) for the 58 breakwater 
project is $16,700,000. The estimated non-Federal cost (Oct 
1988) for the breakwater project is also $16,700,000. See Table 
20-B for authorizing legislation. 
Local cooperation. Fully complied with for completed 
project as authorized by 1954 and 1960 R&8cH Acts and 1974 
WRD Act. An agreement between the United States of 
America and the Commonwealth of Pennsylvania, acting 
through the Department of Environmental Resources was 
entered into on February 21, 1979 for the annual nourishment 
which was extended by the 1976 WRD Act. A Local 
Cooperation Agreement between the United States of 
America and the local sponsor for construction of the 58 
breakwater project was executed by the Secretary of the Army 
on June 22, 1989. The local sponsor, namely the Department 
of Environmental Resources of the Commonwealth of 
Pennsylvania, agreed to provide without cost to the United 
States all lands, easements, and rights-of-way, including 
suitable borrow and dredge disposal areas for excavated 
material as determined by the Chief of Engineers and 
necessary for implementation and for annual nourishment 
of the project; provide a cash contribution based on the 
appropriate percentage of final construction cost, exclusive 
of lands, easements, and rights-of-way, the percentage to be 
in accordance with existing law based on shore ownership 
and use existing at time of construction, which contribution 
is presently estimated at $13,800,000 or 50% based on this 
being a recreational project. Pay 50% of the cost for annual 
beach redistribution and nourishment work for the project; 
hold and save the United States free from damages due to 
construction works, except for damages due to fault or 
negligence of Government or its Contractors; maintain and 
operate all the works, including breakwaters and annual 
sand nourishment and redistribution as needed, after 
completion in accordance with regulations prescribed by the 
Secretary of the Army; and assure continued public ownership 
and continued public use without cost to the United States of 
appropriate access and facilities including parking and 
sanitation, necessary for realization of public benefits upon 
which Federal participation is based, and administer and 
maintain beach for continued public use during life of 
project. 
Operations and results during fiscal year. New Work: 
Beach nourishment as authorized by the 1976 WRD Act was 
continued. One contract for providing beach nourishment in 
1989 and 1990 was awarded. A total off 268,718 tons of sand 
were placed on the beaches. The 1989 nourishment program 
included placement of approximately 234,004 tons of upland 
sand at a unit price of $4.72 per ton on beaches 4, 5, 6, 8, and 
Duck Pond Crossover. In addition, approximately 34,714 
tons of fine off-shore sand at a unit price of $8.27 per ton was 
used in the top dressing layer on beaches 6, 8 and 10 and on 
Duck Pond Crossover. During the year a total of $1,599,864 
($1,115,058 Federal and $484,806 non-Federal) was expended 
for beach nourishment operations. Of this total, contract 
costs were $1,014,669 Federal, including supervision and 
administration and chemical testing and aerial photography 
architect/engineering contracts and $461,042 non-Federal. 
In-house engineering effort cost $100,389 Federal and $23,764 
non-Federal. The Commonwealth of Pennsylvania contributed 
$456,429 for their share of the FY 89 nourishment 
operations. The cumulative non-Federal total project share 
through FY 89 is $8,364,529. The Final Phase I General 
Design Memorandum was submitted to the Secretary of the 
Army in October 1981 for his review and transmittal to 
Congress. In FY 89 a total of $8,952 was expended for real 
estate activities and $29 for in-house engineering effort for 
the permanent project under Continuation of Planning and 
Engineering Preconstruction Engineering and Design. The 
Phase II General Design Memorandum which presents the 
detailed final design of the project recommended in the 
Phase I General Design Memorandum was approved on July 
27, 1988. The contract plans and specifications for construction 
of the 58-breakwater project, under the Construction 
20-10

BUFFALO, N.Y., DISTRICT 
General appropriation were approved on August 3, 1988. A 
Local Cooperation Agrement between the United States of 
America and the Commonwealth of Pennsylvania was 
executed by the Secretary of the Army on June 22, 1989. One 
contract for construction of the breakwater project was 
awarded. During the year, a total of $258,339 ($149,223 
Federal and $109,116 non-Federal) was expended to initiate 
construction of the breakwater project. Of this total, contract 
costs were $30,000 Federal and $25,120 non-Federal, including 
construction management. In-house engineering 
effort cost $119,223 Federal and $81,996 non-Federal. The 
Commonwealth of Pennsylvania contributed $2,500,000 in 
FY 89 toward this project. 
30. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See Table 20-D. 
31. BEACH EROSION WORK 
UNDER SPECIAL AUTHORIZATION 
LAKESHORE PARK 
ASHTABULA, OHIO 
Location. Lakeshore Park is located in Ashtabula, Ashtabula 
County, Ohio about 40 miles southwest of Erie, 
Pennsylvania, and about 50 miles northeast of Cleveland, 
Ohio. (See U.S. Geological Survey Map, Ashtabula North, 
OH). 
Existing project. For description of existing project, see 
page 32-12 of Annual Report for 1983. Construction was 
completed in July 1983. 
Local cooperation. For details of local cooperation requirements, 
see page 32-12 of Annual Report for 1983. 
Operation and results during fiscal year. New Work: FY 89 
Federal cost was $25,289 for beach nourishment contract. 
In-house engineering effort cost $4,258. 
Beach erosion activity pursuant to Section 103, Public Law 
87-874 (preauthorization studies). 
Century Park, Lorain, OH - Costs of $12,106 were incurred 
for preauthorization studies. 
Geneva State Park, OH - Costs of $2,844 were incurred for 
preauthorization studies. 
Simms Park, Euclid, OH - Costs of $3,915 were incurred for 
preauthorization studies. 
Flood Control 
32. ELLICOTT CREEK, N Y 
Location. The channel improvement is located on the 
downstream portion of Ellicott Creek in the towns of Amherst 
and Tonawanda, Erie County. (See Geological Survey 
maps of Tonawanda East and Buffalo Northeast, N Y) 
Existing project. For detailed description of the original 
project as authorized by Section 201 of the 1970 Flood Control 
Act, see page 32-24 of Annual Report for 1973. The basic 
authorization, as modified by the Water Resources Development 
Act of 1974, provides authority to undertake flood 
control measures to alleviate flooding that is compatible 
with authorized project and any alternatives currently under 
restudy pursuant to Flood Control Act of 1970. As a result of 
restudy of alternatives, the project provides for: (a) widening, 
straightening and deepening about 2.5 miles of existing creek 
channel including the existing bypass channel in Ellicott 
Creek Park; (b) construction of a diversion channel about 
5,850 feet long between Maple Road and Millersport 
Highway; (c) construction of a diversion channel about 1,950 
feet long through Pfohl Park; (d) construction of a diversion 
channel about 9,150 feet long from Niagara Falls Boulevard 
upstream to about Pfohl Park; (e) construction of 3 highway 
bridges; (f) modification of culverts at Tonawanda Creek 
Road; (g) modification of utilities and drainage outlets; and 
(h) recreation facilities consisting of a bike and hike path 
about 5.4 miles long, with open space park areas. The 
estimated Federal cost of existing project is $11,312,000 (Oct. 
1988). The estimated non-Federal cost is $9,235,000 (Oct. 
1988). Completion of preconstruction planning and construction 
was authorized Dec. 29, 1981, under Section 5, PL 
97-128. 
Local cooperation. For details of local cooperation see 
page 32-22 of Annual Report for 1976. On October 25, 1976, 
the New York State Department of Environmental Conservation 
furnished a letter of intent to cooperate toward construction 
of project. On June 22, 1983, a formal Local 
Cooperation Agreement was requested from N Y State. On 
January 20, 1984, this agreement was fully executed. 
Operations and results during fiscal year. New Work: In 
August 1987 a contract was awarded and construction 
initiated on Stage 2. A third and final contract, Stage 2A, 
which will complete the project, was awarded in May 1988. 
Construction on Stages 2 and 2A was completed in Spring 
1989 and the project was accepted by the sponsor in July 1989. 
Minor site restoration remains to be completed in spring 
1990. Federal costs for FY 89 were $830,246 for the contract, 
including supervision and administration and $157,000 for 
in-house engineering effort. Non-Federal costs were $238,554 
for construction contract, including supervision and 
administration. 
33. MT. MORRIS LAKE, N Y 
GENESEE RIVER 
Location. Dam is on Genesee River 66.9 miles above river 
mouth and about 32 miles southwesterly of Rochester, N. Y. 
Reservoir is in Livingston and Wyoming Counties, N Y (See 
Geological Survey maps of Nunda and Portage, N Y). 
Existing project. For description of existing project as 
authorized by 1944 Flood Control Act see page 1575 of 
Annual Report for 1962. New work for completed project 
cost $23,365,559. In addition $5,000 contributed funds were 
expended for new work. 
Local cooperation. None required. Local interests contributed 
$5,000 for new work. 
Operations and results during fiscal year. Maintenance: 
Operation and ordinary maintenance of dam, reservoir and 
service facilities, condition and operation studies, real estate 
activities and miscellaneous reports, to include stability 
analysis, periodic inspection and dam failure emergency 
planning, were accomplished by hired labor at a cost of 
$568,831. Co-Operative Stream Gaging Program accomplished 
by U.S. Geological Survey and National Weather 
Service reporting and hydroclimatic network cost $81,228. 
Operation of the Water Control Center cost $162,602. Finali- 
20-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
zation of FY88 debris removal contract cost $4,922. Installation 
of emergency lighting system within confines of dam, by 
hired labor, cost $4,636. Installation of intercommunication 
system throughout dam by hired labor cost $8,669. Rehab of 
existing elevator, to include replacement of guide rails, door 
tracks, hangers, ladders and cables, by contract, cost $74,985. 
Engineering and design costs for maintenance were $127,996. 
Supervision and administration cost $58,512. 
34. OTTAWA, OHIO 
Location. Ottawa is located on the Blanchard River, about 
22 miles upstream from its confluence with the Auglaize 
River. The Blanchard River drains about 765 square miles of 
the extreme sourtheastern corner of the Maumee River Basin 
which covers about 6,586 square miles in northwestern Ohio, 
northeastern Indiana and southeastern Michigan (See U.S. 
Geological Survey map for Ottawa, OH.) 
Existing project. The local protection project, authorized 
by Section 203 of the 1966 Flood Control Act (Public Law 
89-789), provides for construction of levees, floodwalls 
combined with channel improvement, bridge change, and 
construction of new bridges. The reformulated project 
consists of improving the floodway by clearing and snagging 
the Blanchard River, removing abandoned railroad and 
highway embankments, relocating a power line, clearing a 
floodway and doing some selected filling on the riverbanks. 
The non-structural component of the selected plan consists 
of automating one gage at Ottawa, OH, to provide an early 
warning system to residents. Estimated Federal cost of the 
project (Oct., 87) is $990,000. Estimated non-Federal cost is 
$440,000 (Oct., 87) including a cash contribution of $73,000. 
The project was reclassified from active to deferred for 
restudy in March 1988. 
Local cooperation. The local sponsor, Maumee Watershed 
Conservancy District, will, prior to construction, enter into a 
bindipg written agreement which addresses project construction 
and satisfies the requirements of Section 221 of 
Public Law 91-611. For details of local cooperation, see page 
32-15 of Annual Report for FY85. By letter dated September 
10, 1987, the Conservancy District informed the Buffalo 
District that it cannot provide a Letter of Intent because the 
Village of Ottawa is unable to provide any funds to meet the 
non-Federal funding requirements for this project. 
Operations and results during fiscal year. New Work: Inhouse 
engineering effort for Advance Engineering and 
Design Preconstruction Engineering and Design cost $1,153. 
35. POINT PLACE, TOLEDO, OHIO 
Location. Point Place is located on a peninsula in 
northeast portion of city of Toledo, Ohio. Its shores are 
bounded on the east by Maumee Bay of Lake Erie and on the 
west by Ottawa River. The peninsula extends in a northeasterly 
direction immediately north of mouth of Maumee 
River. 
Existing project. The project provides for: (a) combination 
of protective structures consisting of 5,700 linear feet of steel 
sheet pile wall and 18,700 feet of levee; (b) three new pumping 
stations; and (c) 5,500 linear feet of new storm sewer facilities, 
including 2,400 linear feet of gravity outfalls. The estimated 
project costs are $9,916,000 Federal and $4,220,897 non- 
Federal including a cash contribution of $1,865,800. Existing 
project was authorized by 1965 Flood Control Act (H.D. 363, 
92nd Cong., 2d sess). 
Local cooperation. For details of local cooperation see 
pages 32-24 and -25 of Annual Report for 1978. The Local 
Cooperation Agreement was executed by city of Toledo on 
January 27, 1982. 
Operations and results during fiscal year. New Work: The 
entire project was completed in June 1986. Balancing of 
Federal and non-federal shares resulted in a Federal net credit 
of $30,000 for in-house engineering effort. Non-Federal inhouse 
engineering effort cost $32,978. 
36. RENO BEACHHOWARD 
FARMS AREA, OHIO 
Location. Area is located in Lucas Country, on the south 
shore of Lake Erie about 15 miles east of Toledo, Ohio. (See 
U.S. Geological Survey map for Reno Beach and Metzger 
Marsh, OH). 
Existing project. The local protection project, as authorized, 
provides for construction of 8,200 feet of roadway 
seawall, consisting of an earth dike, faced on the lakeward 
side with a quarry-run stone fill; and a steel sheet pile 
floodwall connecting the easterly end of this seawall at Wards 
Canal to the existing inland dike paralleling the canal. 
Estimated Federal cost of new work consisting of reconstructing 
to a permanent project the "Operation Foresight" 
work which was completed in 1973, is $5,560,000 (Oct. 
1988). Non-Federal cost estimate of $1,850,000 (Oct. 1988) 
includes cash contribution of $520,000 toward first cost of 
construction plus all lands, easements, and rights-of-ways. 
Project was authorized under Section 203 of the Flood 
Control Act of 1948 (H.D. 554, 80th Cong. 2d sess.) 
Local cooperation. See pages 32-16 of 1982 Annual Report 
for full requirements of local cooperation. A local Cooperation 
Agreement (LCA) was executed with the local 
Sponsor on July 22, 1988 and by the Assistant Secretary of the 
Army for Civil Works on September 30, 1988. 
Operations and results during fiscal year. New Work: FY 
89 continued coordination with local sponsors, the State of 
Ohio and Congressional Representatives, in an effort to 
resolve problems in acquiring the necessary lands, easements 
and Rights-of-way (LER). Availability of LER is uncertain. 
In-house engineering effort cost $123 under Advance Engineering 
and Design Preconstruction Engineering and 
Design, and $163,230 under the Construction General 
Appropriation. 
37. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed flood control works for compliance 
with Federal requirements were made during the 
period at a cost of $242,177. This includes updating the 
hydraulics and hydrology of various local flood control 
projects. Total cost to Sept. 30, 1989 was $1,322,426. 
38. NATIONAL EMERGENCY 
PREPAREDNESS 
FY 89 costs were $139,664. 
20-12

BUFFALO, N.Y., DISTRICT 
39. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 20-E. 
40. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 20-H. 
CONESUS LAKE, LIVONIA, N Y 
Location. Conesus Lake is situated in western New York 
State about 25 miles south of the city of Rochester. (See U.S. 
Geological Survey Map, Livonia, N Y). 
Existing project. Project was authorized for construction 
by the Chief of Engineers pursuant to Section 205 of the 
Flood Control Act of 1948, as amended, on July 22, 1985. For 
description of existing project, see page 32-19 of the Annual 
Report for FY87. Total Federal cost of the project is 
$1,445,000 (June 1988). Total non-Federal cost is $300,000 
(June 1988). 
Local cooperation. On September 25, 1985, the New York 
State Department of Environmental Conservation signed the 
Local Cooperation Agreement. For details see page 32-16 of 
Annual Report for FY 86. 
Operations and results during fiscal year. New Work: 
Project construction is 100% complete as of June 1988. 
Balancing of Federal and non-Federal shares resulted in a 
Federal net credit to the construction contract of $14,638. 
Supervision and administration of the contract cost $4,547. 
In-house engineering effort for flow tests, and to modify the 
operating plan for the outlet control structure cost $57,601. 
Non-Federal contract costs wer $1,000. 
EUCLID CREEK, CLEVELAND, OH 
Location. Euclid Creek has a drainage area of approximately 
25 square miles and is located east of Cleveland 
in Cuyahoga County and a small portion in Lake County, 
Ohio. (See U.S. Geological Survey Map, East Cleveland, 
OH). 
Existing project. For details of existing project, see page 
32-14 of the Annual Report for 1983. Initial construction of 
project was completed in 1986. Repairs to failed bank were 
completed in May 1988. 
Local cooperation. For details of local cooperation requirements, 
see page 32-13 of Annual Report for 1984. 
Operations and results during fiscal year. New Work: 
Federal contract costs, including supervision and administration 
were $1,000. In-house engineering effort cost $11,462. 
Flood Control and Coastal Emergencies (Public Law 99, 
84th Congress, as amended by Sec. 206 of Flood Control Act 
of 1962). 
FY 89 costs for Disaster Preparedness were $859,706. 
Federal costs for Advance Measures were $54,470 and non- 
Federal costs were $18,606. The Advance Measures project at 
Wightman's Grove, Sandusky County, Ohio provides for 
construction of 5,600 feet of clay and rubblemound dikes and 
was completed in late FY88. Balancing of Federal and non- 
Federal shares resulted in a Federal net credit for the contract, 
including supervision and administration of $1,374 and a 
credit to in-house engineering effort of $7,607. Non-Federal 
contract costs, including supervision and administration 
were $10,999. In-house engineering effort cost $7,607. The 
Advance Measures Self-Help Program initiated in FY87 was 
terminated in June 1988. FY89 in-house costs were $63,451. 
Government furnished materials which remained unused at 
the end of the program are being redistributed to six Corps 
Districts for use during future flood events. 
41. DEAUTHORIZED PROJECTS 
See Table 20-I. 
General Investigations 
42. SURVEYS 
During FY 1989 costs of $925,793 were incurred as shown 
below: 
Navigation Studies ............................. 
Flood Damage Prevention Studies .............. 
Shoreline Protection Studies ................. 
Special Studies ............................... 
Miscellaneous Investigations ................... 
Coordination Studies ........................... 
Phase I GDM Studies ..................... 
Comprehensive Studies .......................... 
Review of Authorized Projects ................ 
$ 49,827 
611,810 
107,323
0 
69,844 
82,242
0 
4,747
0 
43. COLLECTION AND STUDY 
OF BASIC DATA 
During the period, costs of $247,467 were incurred in 
connection with International Water Studies under the 
General Investigations appropriation and $520,367 incurred 
under the Operations and Maintenance appropriation for a 
total cost of $767,834. Flood plain management services were 
performed during the year at a cost of $291,708. During the 
year, flood hazard evaluation studies were essentially 
completed for the towns of Grove, NY and Pioneer, OH. The 
results of these studies will enable local officials to encourage 
and enforce prudent use of the identified flood plains. Also 
hundreds of technical assistance requests regarding flood 
plain matters were completed during the year responding to 
individuals, corporations, real estate companies, insurance 
agents, engineering firms and local agencies. Costs for 
General Hydrologic Studies were $1,932. 
44. ADVANCE ENGINEERING 
AND DESIGN 
Costs during the period were $804,222 for Preconstruction 
Engineering and Design Advance Engineering and Design 
projects. For details of individual projects, see sections 13, 16, 
28, 34 and 36 in text. 
45. CONTINUATION OF PLANNING 
AND ENGINEERING 
Costs during the period were $8,981 for Preconstruction 
Engineering and Design Continuation of Planning and 
Engineering. For details of individual project, see section 29 
in text. 
20-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
1. Ashtabula Harbor, OH 
2. Barcelona Harbor, NY 
(Federal Funds) 
(Contrib. Funds) 
3. Black Rock Channel 
and Tonawanda 
Harbor, NY 
(Federal Funds) 
(Contrib. Funds) 
4. Buffalo Harbor, NY 
5. Cattaraugus 
Harbor, NY 
(Federal Funds) 
(Contrib. Funds) 
6. Cleveland Harbor, OH 
7. Conneaut Harbor, OH 
8. Dunkirk Harbor, NY 
(Federal Funds) 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
- - - - 12,805,339' 
- - - - 12,805,339' 
304,500 781,500 577,000 898,500 12,112,446 
325,492 750,105 608,844 900,683 12,095,103 
- - - - 6,077,000 
- - - - 6,077,000 
554 
554 
1,110 
1,110 
1,861,755 2,122,000 57 
1,985,726 2,007,904 73
2,718 
2,718 
1,185,853 2 
1,185,853 2 
1,930,177 
1,930,177 
174,000 
174,000 
- 11,135,120 3 
- 11,135,120 3 
4,896 38,293,861 4 
4,621 38,270,1494 
- 620,000 
150 620,000 
- 23,115,187 5 
- 23,115,187 s 
8,000 55,381,515 6 
1,923 55,311,6076 
- 295,457 
- 295,457 
33,864 
41,882 
12 
2,98 
3,44 
4,804,060 
4,804,060 
144,169 
119,959 
2,566,529 
2,566,529 
- 32,146, 299 
7,579 32,126, 663 7 
6,000 151,648,485 8 
0,654 151,240,164 8 
- 16,404,903 
- 16, 404,903 
- 8,346,6419 
- 8,346,641 9 
6,000 9,705,602 to 
7,871 9,704,527 to 
- 651,850 
- 651,850 
- 3,010,024 " 
- 3,010,024 " 
9,460 2,105,334 
6,661 2,105,065 
4,608 
4,608 
310,000 
310,000 
2,869,826 
2,718,745 
15,998 209,852 
1,610,000 1,806,000 1,708,000 76 
1,764,633 1,536,751 2,000,059 77 
.- 
157 
93,141 
49,039 
178,000 
193,000 
3,050,000 
3,088,149 
2,895,000 
3,646,340 
651,000 
633,847 
35,095 
34,406 
5,547 
17,397 
50,000 
49,794 
3,509,000 
3,450,536 
300,000 
136,368 
9,236 
9,260 
250,000 
102,991 
5,807,000 
5,071,289 
218,182 
14,000 441,500 12 
31,314 428,606 13 
33,000 240,004 11 
30,914 195,346 16 
20-14

BUFFALO, N.Y., DISTRICT 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
(Contrib. Funds) 
9. Erie Harbor, PA 
10. Fairport Harbor, NY 
11. Huron Harbor, OH 
(Federal Funds) 
(Contrib. Funds) 
12. Irondequoit Bay, NY 
(Federal Funds) 
(Contrib. Funds) 
13. Lorain Harbor, OH 
(Federal Funds) 
(Contrib. Funds) 
14. New York State 
Barge Canal 
15. Oak Orchard 
Harbor, NY 
16. Olcott Harbor, NY 
Funding 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
- - - - 1,950,000 12 
- - - - 1,950,000 12 
353,185 185,006 1,162,001 400,512 
296,835 111,071 1,287,977 404,352 
267,000 111,000 725,000 843,000 
263,177 116,277 663,810 895,406 
600,000 792,000 615,000 -22,000 
598,849 754,196 617,197 30,624 
3,597,873 13 
3,597,873 13 
16,594,274 14 
16,593,842 '4 
1,154 
1,154 
2,959,611 1 
2,959,611 15 
14,716,672 
14,707,333 
5,103,795 16 
5,103,795 16 
16,211,926 
16,210,842 
247,030 
247,030 
63,079 
63,079 
3,535,800 
3,535,710 
390,704 
390,704 
2,720,186 
2,720,039 
22,217,073 17 
22,196, 467 17 
25,503,429 
25,493,738 
845,551 
845,551 
12,500 
12,500 
1,586,996 18 
1,586,996 18 
248,541 
248,541 
890,210 19 
812,703 19 
578,052 20 
578,052 20 
14,477 2' 
14,47721 
25,000 - 
-166,925 198,565 
- 105,000 
- 1,850 
1,389,500 71,340 
1,589,224 262,725 
575,000 577,000 
263,456 788,111 
1,124,000 1,087,000 
1,093,955 1,059,216 
660,000 203,000 
14,198 696,038 
38 
267,500 
364,095 
9,402 
36,515 
70,607 
635,000 
703,157 
-17,449 
135,315 
- 12,500 
- 3,007 
44
-25,717 
85,297 
..- 
-12,464 
-4,679 
22 
5,005 1,578 
4,757 1,826 
- 350,000 
- 178,133 
3,336 12,094 
3,269 12,161 
96 
18,204 
24,760 
59,346 
62,683 
208,000 
281,336 
545,000 
539,352 
9,493 
10,440 
10,440 
400,000 
494,360 
16,374 
16,374 
20-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
17. Port Ontario 
Harbor, NY 
(Federal Funds) 
(Contrib. Funds) 
18. Rochester Harbor, NY 
19. Rocky River 
Harbor, NY 
20. Sandusky Harbor, OH 
(Federal Funds) 
(Contrib. Funds) 
21. Toledo Harbor, OH 
22. Vermilion Harbor, OH 
23. West Harbor, OH 
(Federal Funds) 
(Contrib. Funds) 
24. Wilson Harbor, NY 
27. Lake Erie, 
Sturgeon Pt., NY 
(Federal Funds) 
(Contrib. Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
160,000 920,000 500,000 
59,808 1,028,304 460,136 
- - 359 
- - 359 
270,000 560,000 520,000 
- 824,358 510,677 
1,828,000 627,000 1,285,000 
1,734,843 721,364 1,266,283 
3,951 
245,580 
- 3,270 
59 3,270 
- 2,400,00022 
16,150 2,374,39822 
4,893 5,252 
4,893 5,252 
- 1,350,000 
556 1,335,591 
- 2,439,308 23 
- 2,439,308 23 
38,000 18,592,816 24 
77,136 18,592,79924 
18,301 
18,301 
343,494 
343,494 
2,252,607 
2,252,607 
- - - - 6,727,270 25 
- - - - 6,727,27025 
813,000 639,000 165,000 446,000 14,935,439 
813,049 624,082 157,030 437,085 14,903,530 
- - - - 675,606 
- - - - 675,606 
- 20,000 - - 20,000 
- 19,999 - -4,554 15,445 
- - - - 17,191,842 26 
- - - - 17,191,842 26 
3,320,000 3,741,500 2,958,000 2,894,800 83,401,353 27 
3,367,229 2,001,213 4,710,343 2,779,048 83,262,543 27 
-23,903 
17,639 
48,744 
48,744 
3,695 
4,994 
92,000 
96,898 
52,597 
52,597 
14,083 
14,083 
31,941 
31,941 
45,472 688,700 210,275 
26,296 430,722 487,428 
3,377 38,786 
3,377 38,786 
173,000 1,460,000 
167,117 1,451,120 
- 1,464,858 
- 404,395 
22,591 
22,591 
-15,000 
-143,915 
-108,000 
948,684 
1,156,118 28 
1, 156, 118 28 
2,026,840 
2,026,840 
139,775 
139,775 
3,303,898 
3,303,898 
1,028,294 
1,028,294 
3,795,000 
3,795,000 
535,246 29 
535,246 29 
554,005 30 
554,005 30 
1,786,90031 
1,635,854 31 
1,356,858 
1,353,079 
20-16

TABLE 20-A (Continued) 
BUFFALO, N.Y., DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
28. Maumee Bay State 
Park, OH 
29. Presque Isle 
Peninsula, Erie, PA 
(Federal Funds) 
(Contrib. Funds) 
31. Lakeshore Park, 
Ashtabula, OH 
(Federal Funds) 
(Contrib. Funds) 
32. Ellicott Creek, NY 
(Federal Funds) 
(Contrib. Funds) 
33. Mt. Morris Lake, NY 
Genesee River 
34. Ottawa, OH 
35. Point Place, 
Toledo, OH 
(Federal Funds) 
(Contrib. Funds) 
36. Reno Beach-Howard 
Farms Area, OH 
40. Conesus Lake, 
Livonia, NY 
(Federal Funds) 
(Contrib. Funds) 
40. Euclid Creek, OH 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
- 250,000 113,000 
- - 229,777 
15,000 
136,816 
378,000 
366,593 
1,085,000 1,163,000 1,297,000 3,608,000 18,738,562 
1,101,511 1,163,404 1,277,795 1,264,281 16,382,393 
- - - - 4,978 
- - - - 4,978 
497,143 486,429 464,143 2,956,429 9,712,713 
529,863 508,126 440,157 593,922 7,321,733 
85,000 
13,739 73,045 
20,000 30,000 
16,108 29,547 
865,000 2,474,000 4,878,000 
505,283 2,819,385 4,906,278 
- - 400,000 
- - 399,900 
990,000 931,000 
1,004,820 951,801 
- 135,000 
142,821 98,091 
117,000 
109,421 
45,320 
57,021 
3,000 
17,702 
448,000 
134,255 
35,000 
90,000 
108,791 
10,501 
90,480 
58,164 
880,000 
857,780 
-11,000 
26,822 
8,74 
1,081,000 
987,246 
253,000 
238,554 
1,23 
1,09 
9 -3 
[4 
921,844 
916,475 
249,707 
249,707 
11,193,000 
11,097,039 
653,000 
638,454 
- 23,365,559 32 
- 23,365,559 32 
$3,500 13,935,809 
)2,381 13,756,431 
- 374,000 
1,153 374,000 
- 9,916,000 
30,000 9,866,000 
5,831 1,871,631 
32,978 1,871,203 
25,000 200,000 335,000 
12,159 210,486 163,353 
953,000 
1,084,884 
14,964 
85,000 
36,532 
88,000 
235,462 
19,000 
119,000 
184,825 
38,400 
47,510 
1,000 
12,462 
1,170,467 
996,230 
2,069,400 
2,031,849 
35,000 
34,964 
3,456,000 
3,455,904 
1. Includes $565,192 for previous projects. Excludes $47,000 
contributed funds. 
2. Includes $56,616 for previous projects. Excludes $7,500 
contributed funds. 
3. Includes $58,027 for previous projects. 
4. Includes $4,922 emergency relief authority administrative 
costs transferred for new work to maintenance upon conversion to 
programming and budgeting system July 1, 1953, by direction of 
Office, Chief of Engineers. Also includes appropriations and costs 
under appropriation titles 96x3123 Operation and Maintenance 
and 96x5125 Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. 
5. Includes $4,277,586 for previous projects. Excludes expenditures 
of $239,305 for work authorized by Section 107. 
6. Includes 1,883,647 for previous projects. Excludes $446,805 
contributed funds. 
7. Includes $1,564,154 for previous project and appropriations 
and costs of $16,596 for modification authorized for 
construction under authority of Sec. 107,1960 RcH Act. 
8. Includes appropriations and costs under appropriation 
titles 96x3123 Operations and Maintenance and 96x5125 Maintenance 
and Operation of Dams and Other Improvements of 
Navigable Waters. Excludes $201,960 contributed funds. 
9. Includes $805,272 for previous projects. 
10. Includes $39,784 for previous projects. 
11. Includes $811,250 for previous projects. Excludes $11,000 
contributed funds. 
12. Includes $176,520 for previous projects. 
13. Includes $736,967 for previous projects. 
14. Includes $104,900 for previous projects. Excludes $154,500 
contributed funds. 
15. Includes $368,940 for previous projects. 
16. Includes $269,789 for previous projects. 
17. Includes $292,203 for new work for previous projects. 
Excludes $3,000 contributed funds. Also excludes appropriation 
and cost of $29,570 under authority of Section 107, 1960 R8cH Act. 
18. Excludes $224,702 contributed funds. 
20-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
19. Includes $140,210 for previous projects. Excludes $1,500 
contributed funds. 
20. Includes $38,959 for previous projects. Excludes $5,000 
contributed funds. 
21. Excludes $186,000 Public Works Acceleration Act. 
22. Includes $50,000 for previous projects. 
23. Includes $247,794 for previous projects. 
24. Includes $617,529 for previous projects and $478 emergency 
relief authority administration costs transferred from new work to 
maintenance upon conversion to programming and budgeting 
system, July 1, 1953, by direction of Office, Chief of Engineers. 
25. Includes $477,149 for previous projects. Excludes $325,000 
contributed funds. 
26. Includes $1,624,695 for previous projects. 
27. Includes $16,914 for previous projects. 
28. Excludes $740,679 contributed funds. 
29. Includes $57,342 for previous projects. Excludes $166,998 
contributed funds. 
30. Includes $16,914 for previous projects. 
31. Includes $341,900 study funds under authority Section 107, 
1960 R8cH Act. 
32. Excludes $5,000 contributed funds. 
TABLE 20-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ASHTABULA HARBOR, OHIO (See Section 1 of Text) 
Construction of breakwater. 
Enlarge outer harbor by extending west breakwater and constructing 
new east breakwater pierheads on lakeward ends of breakwaters; 
and remove part of old east breakwater. 
Extend west breakwater to shore; dredge outer harbor to a depth of 20 
feet. 
Remove portion of east breakwater, extend breakwaters to present 
project dimensions and dredging restrictions in portion of west 
basin. 
Dredge channel through outer harbor, channel of approach to Penn 
Central Co. slip, channel Ashtabula River, to and in turning basin 
all to present project dimensions; remove portion of old east inner 
breakwater and maintenance to 24-foot depth of portion of outer 
harbor. 
Extend river channel to present project limit. 
Dredging approach channel and turning basin in east outer harbor to 
25-foot depth. 
A depth of 29 feet in soft and 30 feet in hard material in entrance 
Channel to just inside outer ends of breakwaters, thence 28 feet in 
soft and 29 feet in hard material in a channel to inner breakwater, 
thence 27 feet in soft and 28 feet in hard materials in a channel 
extending to Penn Central Co. slip and extending 2000 feet up 
Ashtabula River, 22 feet in hard material in turning area; and 28 
feet in soft and 29 feet in hard material in areas adjacent to 250-foot 
section of inner breakwater when that section is removed as now 
authorized. 
Dredging approach, channel and turning basin in east outer harbor 
to 28 feet in soft material and 29 feet in hard material. 
BARCELONA HARBOR, NY (See Section 2 of Text) 
Harbor of refuge. 
BLACK ROCK CHANNEL AND TONAWANDA HARBOR, N Y 
(See Section 3 of Text). 
Dredging channel through horseshoe reef at outlet of Lake Erie and 
Tonawanda Inner Harbor to 16 feet. 
Deepening Tonawanda Creek to 16 feet. 
Dredging channel from Buffalo outer harbor to foot of Maryland St., 
Buffalo, to 21 feet. 
Dredging channel from foot of Maryland St., Buffalo, to natural 
deepwater pool upstream from Tonawanda Harbor to 21 feet; 
construction of ship lock and bridge; and repair of Bird Island pier 
and towpath wall. 
Annual Report, 1895, p. 2132 
H. Doc. 654, 61st Cong., 2d sess. 
H. Doc. 997, 64th Cong., 1st 
sess. 
H. Doc. 43, 73rd Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 78, 74th Cong., 2d sess. 
H. Doc. 321, 77th Cong., 1st 
sess. 
H. Doc. 
sess. 
H. Doc. 
sess. 
486, 83rd Cong., 2d 
148, 86th Cong., 1st 
H. Doc. 269, 89th Cong., 1st 
sess. 
4 
H. Doc. 446, 78th Cong., 2nd 
sess. 
H. Doc. 446, 78th Cong., 2nd 
sess. 
H. Ex. Doc. 83, 50th Cong., 1st 
sess. Annual Report, 1888, 
p. 2066, and Annual Report, 
1897, pp. 3116-3120. 
H. Doc. 143, 56th Cong., 1st 
sess., and Annual Report, 
1900 p. 4152. 
H. Doc. 125, 56th Cong., 2d 
sess., and Annual Report, 
1901, p. 3343. 
H. Doc. 428, 58th Cong., 2d 
sess. 
20-18 
TABLE 20-A (Continued) COST AND FINANCIAL STATEMENT 
June 3, 1896 
Mar. 3, 1905 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 27, 1965 
Mar. 2, 1945 
Aug. 11, 1888 
June 3, 1896 
June 13, 1902 
June 13, 1902 
Aug. 8, 1917 
Mar. 3, 1905

BUFFALO N.Y., DISTRICT 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 27, 1916 
Mar. 2, 1919 
Mar. 2, 1945 
Sept. 22, 1922 
Mar. 3, 1925 
June 26, 1934s 
Aug. 30, 19356 
Mar. 2, 1945 
Sept. 3, 1954 
May 20, 1826 
June 23, 1866 
June 23, 1874 
June 3, 1896 
Mar. 3, 1899 
Mar. 3, 1909 
June 6, 1900 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 1907:o 
June 25, 1910 
July 25, 1912 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 194511 
July 14, 1960 
Dredging channel along Tonawanda Island, with turning basin at its 
downstream end at the foot of the Island, to 21 feet. 
Dredging triangular area at junction with Buffalo north entrance 
channel. 
Widening channel at foot of Maryland St., Buffalo. 
Widening canal south of International Bridge and removal of 
westerly end of Rattlesnake Island shoal. 
Operation and care of improvements provided for with funds from 
War Department appropriations for rivers and harbors. 
Removal of rock shoals in Lake Erie entrance to canal, and in canal 
south of Ferry Street Bridge, to 22 feet; enlargement of North 
Tonawanda turning basin; extension of Bird Island pier, improvement 
of guide pier at the lock; and elimination of upper 150 feet of 
Tonawanda Creek channel from the project.7 
Widening Lake Erie entrance to canal. 
Deepen lower 1,500 feet of Tonawanda inner harbor and enlarge 
turning basin. 
BUFFALO HARBOR, N Y (See Section 4 of Text). 
Construction of south pier (extended in 1868)9. 
Construction of old breakwater.9 
Extension of old breakwater. 9 
Stony Point and south breakwater.9 
North breakwater. 9 
Deepening entrance channel to inner harbor and removing rock 
shoal therein. 
Dredging at entrance to canals at South Buffalo in outer harbor.' 
South entrance breakwater. 9 
Extension of Federal project to Commercial St. and removal of 
Watson elevator site. 9 
Deepening areas A, B, and D in outer harbor to 21 feet, and area C in 
north entrance to 23 feet. 
Deepening areas F and G in outer harbor to 21 feet. 
Removal of shoal between entrance channel to Buffalo River and Erie 
Basin to 21 feet. 
Deepening areas H, I, and K in outer harbor to 21 feet. 
Extension of south entrance and south breakwaters, deepening outer 
harbor to present project dimensions, and removal of shoals on 
approach to south entrance. 
Maintenance of channels in Buffalo River and Buffalo ship canal to 
21 feet in cooperation with city of Buffalo. 
Deepening North and Buffalo River entrance channels, and deepening 
and maintaining Buffalo River and Buffalo ship canal to present 
project dimensions. 
Deepening approach to south entrance channel to 30 feet; deepen to 
30 feet in outer area and 29 feet in inner area of south entrance 
channel; and deepen to 28 feet southerly part of outer harbor. 
H. Doc. 658, 63d Cong., 2d sess. 
H. Doc. 1004, 65th Cong., 2d 
sess. and H. Doc. 92, 79th 
Cong., 1st sess. 
H. Doc. 981, 66th Cong. 2d sess. 
H. Doc. 289, 68th Cong., 1st 
sess. 
H. Doc. 28, 73d Cong., 1st sess. 
H. Doc. 92, 79th Cong., 1st 
sess.
4 
H. Doc. 423, 83d Cong., 2d 
sess. 4, 8 
Annual Report 1868, pp. 222 
and 232. 
Annual Report, 1868, pp. 232 
and 236. 
Annual Report, 1876, pt. 2, pp. 
569 and 573. 
Annual Report, 1895, p. 3153. 
H. Doc. 72. 55th Cong., 1st 
sess., and Annual Report, 
1897, p. 3245. 
Specified in acts. 
Specified in act. 
H. Doc. 240, 59th Cong., 1st 
sess. 
H. Doc. 298, Rivers and Harbors 
Committee Doc. 2, 61st 
Cong., 2d sess. 
H. Doc. 550, 62d Cong., 2d sess. 
H. Doc. 1139, 64th Cong., 1st 
sess. 
H. Doc. 481, 68th Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 1, 71st Cong., 1st sess. 
H. Doc. 46, 73d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 54, 74th Cong., 1st sess. 
H. Doc. 352, 78th Cong., 1st 
sess. 
H. Doc. 151, 86th Cong., 1st 
sess. 
20-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Mar. 3, 1875 
Aug. 5, 1886 
Aug. 11, 1888 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1907 
June 25, 1910 
July 27, 1916 
Aug. 8, 1917 
Aug. 29, 1937 
Aug. 30, 193512 
Aug. 30, 1935" 
Mar. 2, 194514 
July 24, 1946 
July 3, 1958 
July 14, 1960 
as amended 
Nov. 17, 1986 
Aug. 13, 1968 
Deepening portion of outer harbor to 27 feet over a width of 500 feet 
for 2,500 feet northward from 28-foot project area, widening 
within 1,700 feet to limits within 150 feet of breakwater axis and 75 
feet from harbor line and continuing within these limits for 7,000 
feet. Elimination of 25-foot wide strip between presently authorized 
and proposed easterly dredging limits. Elimination of easterly 
50-foot wide undredged strip in existing 23-foot depth project 
area, extending northerly from 27-foot depth to Buffalo River 
entrance channel. Previously authorized but uncompleted portions 
of work authorized by 1935 act, combined with this act as a single 
improvement. 
Removal of abandoned abutments of South Michigan bridge. 
Replace dike at the Small Boat Harbor. 
CATTARAUGUS HARBOR, N Y (See Section 5 of Text). 
Construction of arrowhead breakwaters at mouth of Creek; entrance 
channel 200 feet wide at lakeward end, 100 feet wide and eight feet 
deep from that depth in lake to point 1,575 feet upstream; channel 
100 feet wide, six feet deep an additional 3,425 feet upstream; and 
recreational fishing facilities at mouth. 
CLEVELAND HARBOR, OHIO (See Section 6 of Text). 
West breakwater. 
Part of east breakwater. 9. 
Extension of east breakwater. 
Reconstruction of piers.9 
Dredging channel between piers and outer harbor to depth of 19 feet; 
dredging to depth of 23 feet in any portion of harbor in discretion 
of Secretary of War. 
Arrowhead breakwater and extension of east breakwater. 
Removal of deflecting arm of old east breakwater and closure of gap 
between old and new east breakwaters. 
Pierhead at easterly end of east breakwater. 
Maintenance and improvement of channels in Cuyahoga and Old 
Rivers to a depth of 21 feet to a point 2,000 feet upstream from 
Clark Ave. viaduct and 18-foot turning basin. 
Deepening outer harbor and channel between piers to present project 
dimensions, construction of 400-foot spur breakwater at gap in 
shore arm of west breakwater, removal of easterly 150 feet of west 
main breakwater, elimination from project of a 298-foot southerly 
extension of west pier, and abandonment of inner 932 feet of shore 
arm of west breakwater. 
Maintenance dredging in Cuyahoga and Old Rivers for 1 year as an 
emergency measure. 
Maintenance of extension of Cuyahoga River channel. 
Extension, maintenance, and improvement to a depth of 21 feet of 
Cuyahoga River channel to present project limit. 15,'6 
Improvement of Cuyahoga and Old Rivers to a depth of 23 feet and 
replacement or pier construction of 7 railroad bridges. 2 
Deepening channel 25 feet through east basin of outer harbor; 
replacement of Erie-Lackawanna Railroad bridge over Cuyahoga 
River at mile 4.1 and widening of channel at that point, with 
elimination of reconstruction of east pier of bridge as previously 
authorized; and replacement of Baltimore SOc hio Railroad Bridge 
over Old River near its mouth and Willow Avenue Highway 
Bridge about 800 feet above mouth and widening channel at four 
locations along lower, 2,000 feet of river. 3 
20-20 
H. Doc. 451, 87th Cong., 2d 
sess. 
Sec. 107, PL 86-645. Authorized 
by Chief of Engineers Dec. 
15, 1980. 
Sec. 601, PL 99-662 
H. Doc. 97, 90th Cong., 1st sess. 
Annual Report, 1876, p. 558. 
H. Ex. Doc. 116, 48th Cong., 2d 
sess., and Annual Report, 
1886, p. 1865. 
H. Ex. Doc. 189, 50th Cong., 2d 
sess., and Annual Report, 
1888, p. 2005. 
H. Doc. 326, 54th Cong., 1st 
sess., and Annual Report, 
1896, p. 2949. 
H. Doc. 156, 55th Cong., 2d 
sess., and Annual Report, 
1899, pp. 3075 and 3078. 
H. Doc. 118, 56th Cong. 2d sess. 
No printed report. 
H. Doc. 891, 63th Cong., 2d 
sess. 
H. Doc. 707, 63d Cong., 2d 
sess., and Rivers and Harbors 
Committee Doc. 84, 74th 
Cong., 2d sess. 
H. Doc. 477, 72d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 39, 74th Cong., 1st sess. 
Specified in act. 
H. Doc. 95, 79th Cong., 1st sess. 
H. Doc. 629, 79th Cong., 2d 
sess. 
H. Doc. 107, 85th Cong., 1st 
sess.

TABLE 20-B (Continued) 
BUFFALO N.Y., DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 14, 1960 
Mar. 2, 1827 
Mar. 2, 1867 
June 3, 1896 
June 25, 1910 
June 30, 1948 
Oct. 23, 1962 
Depth of 29 feet in lake approach to main entrance; 28 feet in entrance 
channel to lakeward ends of piers at mouth of Cuyahoga River; 27 
feet in river to a point just above its junction with Old River, and 
in Old River to upstream limit of present 23-foot project; 28 feet in 
west basin within existing project limits as modified to eliminate a 
triangular area at west end and to extend limits to a line parallel to 
and 75 feet from harbor line; and 28 feet in westerly 800 feet of east 
basin. 24 
An area in east basin 27 feet deep extending about 3,800 feet easterly of 
28-foot area with project limits 380 feet from east breakwater and 
on landward side generally by a line 75 feet lakeward of and 
parallel to harbor line. A dock channel to Nicholson Cleveland 
Terminal Co. pier, at easterly end of east basin, from 25-foot 
contour to a limit 75 feet north of pierhead line, 400 feet wide at 
shoreward end and flared toward the lake. 
Deepening upper end of Old River channel from 21 to 27 feet. 
Preparation of Phase I design memorandum for improvements 
consisting of removal of portions of entrance breakwater; construction 
of breakwater extension of east entrance; deepening approach 
and entrance channels; construction of diked disposal area; and, 
installation of recreational fishing facilities on west breakwater. 
Bulkheading and other necessary repairs at pier 34 and approach 
channels and necessary protective structures for mooring basins 
for transient vessels in the area south of pier 34. 
CONNEAUT HARBOR, OHIO (See Section 7 of Text). 
Extension of east breakwater, construction of new west breakwater, 
removal of portion of old west breakwater, and dredging of outer 
harbor to 19 feet. 
Realinement of west breakwater, removal of remainder of old west 
breakwater, and deepening outer harbor to 20 feet. 
Removal of Bessemer & Lake Erie R.R. Co. of inner 635 feet of west 
pair. 
Removal of a portion of west breakwater, extension of breakwaters to 
present project dimensions, construction of pierheads on outer 
ends of breakwaters, deepening outer harbor to present project 
dimensions; removal of portions of river pier, and elimination 
from project of a 255-foot shoreward extension of west breakwater. 
Deepening easterly part of outer harbor to 28 feet in soft material and 
29 feet in hard material; deepening remaining triangular area of 
outer harbor to 22 feet in soft material and 23 feet in hard material; 
deepening inner harbor for 2,450 feet upstream of outer end of west 
pier to 27 feet in soft material and 28 feet in hard material; removal 
of east pier, extension of east break water to shore; and an access 
channel 8 feet deep in outer harbor to city dock. Previously 
authorized but uncompleted portion of work authorized by 1917 
and 1935 acts combined with this act for accomplishment as a 
single improvement. 
Recreational small-boat harbor provided by: a stone dike about 2,200 
feet long: access channels 6 feet deep, 2,800 feet long and 100 feet 
wide; closing of 100-foot gap in existing west breakwater; and 
personnel guard rail on west breakwater. 
DUNKIRK HARBOR, N Y (See Section 8 of Text) 
Construction of west pier. 9,1 8 
Breakwater and excavation of entrance channel to 13 feet 9 
Deepening of entrance channel and harbor basin to a depth suitable 
for vessels of 16-foot draft. 
Removal of rock reef bordering the inner entrance channel. 
Deepening outer entrance channel to present project depths; removal 
of rock shoal on the west side of the entrance channel to a depth of 
17 feet, and changed limits of the inner entrance channel and basin 
to present project dimensions. 
H. Doc. 
sess. 
983, 64th Cong., 1st 
H. Doc. 48, 73d Cong., 1st sess. 
H. Doc. 
sess. 
415, 87th Cong., 2d 
H. Doc. 484, 89th Cong., 2d 
sess. 4 
S. Ex. Doc. 42, 35th Cong., 1st 
sess., and Annual Report 
1866 pt. IV, p. 155. 
Annual Report, 1871, p. 214 
H. Doc. 63, 54th Cong., 1st sess. 
H. Doc. 720, 61st Cong., 2d 
sess. 4 
H. Doc. 632, 80th Cong., 2d 
sess. 
20-21 
H. Doc. 152, 86th Cong., 1st 
sess. 
H. Doc. 527, 87th Cong., 2d 
sess. 4 
Sec. 107, PL 86-645. Authorized 
by chief of Engineers Dec. 6, 
1966. 
Sec. 202, PL 99-662. 
H. Doc. 653, 61th Cong., 2d 
sess. 
July 14, 1960 
as amended 
Oct. 22, 1976 
(Sec. 175) 
Nov. 17, 1986 
June 25, 1910 
Aug. 8, 1917 
17 
Aug. 30, 193511 
Oct. 23, 1962 
Nov. 7, 19668

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Dec. 15, 1970 
(House Public Works Comm.) 
June 22, 1971 
(Senate Public Works Comm.) 
Sec. 201 of F.C. Act of 1965 
Nov. 17, 1986 
May 26, 1824 
Mar. 3, 1899 
June 15, 1910 
Nov. 28, 192020 
Aug. 30, 1935 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 23, 1962 
Mar. 3, 182521 
June 3, 1896 
Mar. 3, 1905 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193522 
Aug. 26, 1937 
July 24, 1946 
July 14, 196027 
Construction of small-boat harbor. 
Dredging and maintenance of eastern inner harbor. 
ERIE HARBOR, PA (See Section 9 of Text). 
Breakwaters and piers; dredging entrance channel; and brushwood 
protection of beach of Presque Isle Peninsula.9 
Deepening channel and harbor basin to 18 feet; repair and extension 
of piers; and plant growth and emergency protection work on 
peninsula. 
Deepening channel and part of harbor to 20 feet. 
Reconveyed Presque Isle Peninsula to the State of Pennsylvania for 
park purposes. 
Deepening, widening, and straightening entrance channel, dredging 
channel at easterly end of harbor basin, deepening a portion of 
harbor basin, all to present project dimensions; elimination of 
north breakwater from project; and limitation of south breakwater 
to a length of 1,200 feet. 
Protection of the peninsula south of the waterworks settling basin. 
Widen 25-foot deep approach channel to ore dock. 
Depth of 29 feet in the entrance channel to a point opposite the inner 
end of the north pier, thence 28 feet in soft and 29 feet in hard 
material in the remainder of the entrance channel, within the 
general limits of the 25-foot basin and inner channel opposite the 
ore dock except as modified to eliminate from the project a 
triangular area along the easterly side;and a depth of 28 feet over a 
300-foot westward extension of the 25-foot basin. 26 
Depth of 27 feet in soft material and 28 feet in hard material in 
approach area to Duquesne Marine Terminal. Previously authorized 
but uncompleted portion of work authorized by 1935 act is 
combined with this act as a single improvement. 
FAIRPORT HARBOR, OHIO (See Section 10 of Text) 
Construction of piers. 
Breakwaters and dredging outer harbor to a depth of 18 feet. 
1,400-foot extension of east breakwater, present project dimension of 
east pier, and deepening of harbor to 19 feet. 
4,000-foot extension of east breakwater at limit of cost to the United 
States of $715,000. 
Deepening of outer harbor and entrance channel to present project 
dimensions; extending the west breakwater to present project 
dimensions with pierhead at its outer end; removal of west pier, 
and construction of bulkhead on west side of river channel. 
Dredging of 21- and 24-foot river channels and turning basin in 
Grand River to present project dimensions. 
Dredging of 8-foot river channel. 
Depth of 29 feet in the approach channel from the lake; a depth of 28 
feet over a width of 800 feet in outer harbor; a depth of 27 feet in soft 
and 28 feet in hard material in Grand River, over a width of 200 feet 
to the upstream limit of the turning basin, with suitable widening 
at the bends, thence over widths reducing from 200 to 100 feet to the 
upstream limit of the existing Federal project, except in the 8-foot 
channel; enlargement of the turning basin, including deepening 
of the entire basin to 21 feet; and minor modification of the 
existing project limits in the outer harbor. 
H. Doc. 91-423, 91st Cong., 2d 
sess. 
Sec. 848, PL 99- 662. 
Annual Report, 1915, p. 1965. 
H. Doc. 70, 55th Cong., 1st sess. 
and Annual Report, 1896, p. 
3237.19 
Rivers and Harbors Committee 
Doc. 26, 61st Cong., 2d sess. 
H. Doc. 52, 73d Cong., 1st sess. 
Specified in act. 
H. Doc. 345, 83d Cong., 2d sess. 
H. Doc. 199, 86th Cong., 1st 
sess. 
H. Doc. 340, 87th Cong., 2d 
sess. 
4 
Annual Report, 1889, pp. 
2147-2153. 
H. Doc. 347, 54th Cong., 1st 
sess. and Annual Reports, 
1896, p. 2956; 1903, p. 2084; 
1905, p. 2349. 
H. Doc. 206, 63d Cong., 1st sess. 
H. Doc. 592, 69th Cong., 2d 
sess., Rivers and Harbors 
Committee Doc. 13, 70th 
Cong., 1st sess. 
H. Doc. 472, 72d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 79, 74th Cong., 2d sess. 4 
H. Doc 706, 79th Cong., 2d 
seSS. 4 
H. Doc. 347, 86th Cong., 2d 
sess. 4 
20-22

BUFFALO N.Y., DISTRICT 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 10, 1977 
(House Public Works Comm.) 
Oct. 1, 1976 
(Senate Public Works Comm.) 
Sec. 201 of F.C. Act of 1965 
Mar. 2, 1905 
Mar. 2, 1919 
Aug. 30, 193522 
Oct. 23, 1962 
July 3, 1958 
Mar. 3, 1899 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Mar. 2, 1945 
Construction of small boat harbor. 
HURON HARBOR, OHIO (See Section 11 of Text) 
Extension of west pier, construction of east breakwater, removal of 
part of old east pier; deepening of channel to 19 feet; and dredging 
of sheltered area. 
Widening river to 200 feet; removal of remainder of old east pier, 
construction of new spur pier, enlargement of sheltered area; and 
closure of breach at shore end of west pier. 
Extension of west pier with pierhead at its outer end; removal of outer 
end of east breakwater and constructing pierhead on new outer 
end; widening and deepening channel to present project dimensions; 
enlargement of turning basin at head of channel; shore 
protection west of west pier, and elimination from project 
construction of spur pier and dredging sheltered area outside 
channel limits. 
Depths of 29 feet in approach channel, 28 feet in entrance channel, 27 
feet in river channel, 21 feet in turning basin a detached 
breakwater, 1,575 feet long 2,000 feet lakeward of outer end of 
existing west pier; and abandonment of lakeward end of existing 
approach channel.2 8 
IRONDEQUOIT BAY, NY (See Section 12 of Text). 
Construction of entrance channel 9 feet deep and 100 feet wide, 
extending from 9-foot depth in Lake Ontario to junction with 
inner bay channels, a distance of about 1,300 feet; inner channel, 8 
feet deep and 100 feet wide, from entrance channel to deep water in 
bay, a distance of about 3,035 feet; access channel 8 feet deep, 100 
feet wide, and 500 feet in length from the inner bay channel to the 
west; two stone rubblemound structures 1,350 feet and 750 feet in 
length at the natural entrance; and recreational facilities. 
LORAIN HARBOR, OHIO (See Section 13 of Text). 
Breakwaters and extensions of piers to present dimensions. 
Extend 18-foot channel from inner end of piers to Erie Avenue Bridge. 
Extend breakwaters and dredge to depth of 19 feet in outer harbor. 
Extend breakwaters to present project dimensions. 
Deepen outer harbor and river channel to Erie Avenue Bridge to 20 
feet. 
Extend 20-foot channel to American Shipbuilding Co. drydock. 
Widen 2 bends in river and enlarge turning basin opposite National 
Tube Co. dock. 12 
Approach channel to municipal pier. 
Deepen outer harbor and river channel to American Shipbuilding 
Co. drydock 2 to present project dimensions and extension of river 
channel to upper end of National Tube Co. dock with turning 
basin opposite that dock. Maintenance dredging in Black River 
from American Shipbuilding Co. drydock 2. Upper end of 
National Tube Co. dock was authorized Apr. 7, 1934, by Public 
Works Administration. 
Enlarging turning basin opposite National Tube Co. dock to present 
project dimensions. 
Turning basin in bend of Black River immediately upstream from 
Baltimore & Ohio RR coal dock. 
H. Doc. 627, 94th Cong., 2d 
sess. 
H. Doc. 122, 58th Cong., 2d 
sess. 
H. Doc. 5, 63d Cong., 1st sess. 
H. Doc. 478, 72d Cong., 2d sess. 
H. Doc. 165, 87th Cong., 1st 
sess. 4 
H. Doc. 332, 84th Cong., 2d 
sess. 
H. Doc. 131, 55th Cong., 2d 
sess., and Annual Report 
1898, p. 2718. 
H. Doc. 560, 60th Cong., 1st 
sess. 
H. Doc. 644, 61st Cong., 2d sess. 
H. Doc. 980, 64th Cong., 1st 
sess. 
H. Doc. 985, 64th Cong., 1st 
sess. 
H. Doc. 587, 69th Cong., 2d 
sess. 
H. Doc. 469, 72d Cong., 2d sess. 
Senate Committee print, 73d 
Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 51, 74th Cong., 1st sess. 
Specified in act. 
H. Doc. 161, 77th Cong., 1st 
sess. 
20-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 14, 1960 
Mar. 2, 1945 
Mar. 2, 1867 
Mar. 4, 1913 
Nov. 17, 1986 
Mar. 2, 1945 
Nov. 17, 1986 
Mar. 2, 1829 
Aug. 2, 1882 
June 25, 1910 
Aug. 30, 19356 
Mar. 2, 1945 
July 14, 1960 
H. Doc. 166, 86th Cong., 1st 
sess. 
4 
PL 89-298. 
Sec. 107, PL 86-645. Authorized 
by Chief of Engineers Mar. 
12, 1986. 
Sec. 202, PL 99-662. 
Oct. 2, 1965 
July 14, 1960 
as amended 
Nov. 17, 1986 
Replace Norfolk and Western Railway swing bridge with a vertical 
lift bridge; construct two detached arrowhead breakwaters lakeward 
of existing breakwaters; construct extension of east breakwater, to 
shore; remove 300 feet of lakeward end of west breakwater; remove 
outer 1,100 feet of east pier; deepen lake approach to 29 feet, 
800-foot wide outer harbor channel to 27 feet; widen river channel 
at bends; and construct a new turning basin 21 feet deep near 
upstream limit of existing project. 29 
Construct bank of stabilization works at cut numbered 1 along left 
bank of river channel above Erie Avenue Bridge.8 
Construction of a 225 foot detached rubblemound breakwater and an 
800 foot long rubblemound breakwater attached to the east 
breakwater shorearm in the east basin of the outer harbor. 
Two bend cuts on Black River between the Norfolk and Western 
Railroad Bridge and 21st Street Bridge, excavated to existing 
channel depth of 27 feet. Widening Upper Turning Basin at 
existing authorized depth of 21 feet. 
NEW YORK STATE BARGE CANAL (See Section 14 of Text) 
Reimbursement to State of New York for 50 percent of the cost of 
operating, maintaining and rehabilitating the New York Barge 
Canal. The Federal contribution to rehabilitation costs shall be 
limited in any fiscal year to $5,000,000, or 5 percent of the 
expenditures in that fiscal year whichever is the lesser. 
OAK ORCHARD HARBOR, NY (See Section 15 of Text) 
Harbor of refuge. 
OLCOTT HARBOR, NY (See Section 16 of Text) 
Dredging a channel 11 feet deep between parallel piers. 9 
Deepening channel to 12 feet and maintenance of west pier. 
Construct the project for Navigation, Report of the Chief of 
Engineers dated June 11, 1980. 
PORT ONTARIO, NY (See Section 17 of Text) 
Construct harbor of refuge. 
Maintain harbor of refuge. 
ROCHESTER, HARBOR, N Y (See Section 18 of Text) 
Construction of piers.9 
Extension of piers to 15 foot contour in the lake. 
Concrete superstructure on piers.9 
Deepening channel to 20 feet. 
Dredging of the entrance channel and turning basin, and the 
elimination of the inner ends of the east and west piers, all to 
present project dimensions. 
Maintenance of existing channel upstream of the Penn Central Co. 
bridge. 
Depth of 24 feet in the channel from the lake to the west pier, a depth 
of 23 feet between the piers and in the lower river to the Penn 
Central Co. bridge, including the existing turning basin; a depth 
of 21 feet from the bridge to the upstream project limit, with 
suitable widening at the bends; and, upstream turning basin 21 
feet deep and 650 feet wide adjacent to the improved channel, with 
two mooring dolphins. 
ROCKY RIVER HARBOR, OHIO (See Section 19 of Text) 
East pier and dredging of channel. 
Extension of east pier and deepening channel to present project 
dimensions. 
Realign and extend channel and construct an anchorage basin. 
Annual Report, 1871, p. 211. 
H. Doc. 70, 75th Cong., 1st sess. 
H. Doc. 352, 88th Cong., 2d 
sess. 
4 
20-24 
Sec. 1105, PL 99-662 
H. Doc. 446, 78th Cong., 2d 
sess. 
Annual Report, 1866 pt. III, p. 
15 and pt. IV, p. 158. 
H. Doc. 780, 62d Cong., 2d 
sess. 
4 
Sec. 601, PL 99-662 
H. Doc. 446, 78th Cong., 2d 
sess. 
Sec. 615, PL 99-662. 
Annual Report, 1874, p. 247. 
Annual Report, 1881, p. 2437. 
Annual Report, 1905, p. 2383. 
H. Doc. 342, 61st Cong., 
2d sess. 
H. Doc. 484, 72d Cong., 2d sess. 
H. Doc. 139, 76th Cong., 1st 
sess. 
H. Doc. 409, 86th Cong., 2d 
sess. 4 
Nov. 17, 1986 
June 10, 1872 
Aug. 26, 1937 
Oct. 27, 1965

BUFFALO N.Y., DISTRICT 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1919 
Jan. 21, 1927 
Aug. 30, 193525 
Mar. 2, 1945 
July 14, 1960 
SANDUSKY HARBOR, OHIO (See Section 20 of Text) 
Construction of channel protection works. 
Widening of Straight and Dock channels and deepening to 19 feet. 
Extension of east jetty to total length of 6,000 feet, with pierhead on 
outer end; deepening of the outer, straight, and easterly portion of 
Dock channels to 21 feet, and westerly portion of Dock channel to 
20 feet. 
Deepening of Dock Channel to 22 feet. 
Enlargement of turning basin and construction of rock dike. 
Maintenance of Bay Channel to 22 feet; and elimination from project 
of portion of turning basin and rock dike. 
Extending Moseley Channel and deepening that channel and the 
outer end of Straight channel to 26 feet, from deep water in the lake 
to the vicinity of Cedar Point dock; widening the bend at the 
junction of the Moseley and Straight channels and deepening to 26 
feet; deepening the Straight channel to 25 feet from the vicinity of 
Cedar Point dock to junction with Bay channel; deepening the 
Bay channel from the junction with the Straight channel to the 
outer end of the Pennsylvania Coal dock No. 3 to 25 feet, thence 
from outer end of the coal dock to the turning basin to 24 feet in 
soft material and 25 in hard, with no Federal dredging within 50 
feet of the dock; and enlarging the turning basin, including 
removal of approximately 300 feet of the rock dike, and deepening 
to 24 feet in soft material and 25 feet in hard. 
H. Doc. 362, 55th Cong., 2d 
sess., and Annual Report 
1898, p. 2708 
H. Doc. 120, 56th Cong., 2d 
sess. 
H. Doc. 982, 64th Cong., 1st 
sess. 
H. Doc. 584, 69th Cong., 2d 
sess. 
Rivers and Harbors Committee 
Doc. 2, 73d Cong., 1st sess. 
H. Doc. 328, 76th Cong., 1st 
sess. 
H. Doc. 144, 86th Cong., 1st 
sess. 
4 
TOLEDO HARBOR, OHIO (See Section 21 of Text). 
Mar. 3, 1899 A channel 400 feet wide and 21 feet deep from 25-foot contour in 
Maumee Bay to Fassett Street Bridge, 200 feet wide and 19 feet deep 
above that point and a 500-foot turning basin at Upper End. A 
stone revetted earth dike in Maumee Bay Channel. 
June 25, 1910 Act 1899 modified to insure a navigable channel to 21 feet from Fassett 
Street Bridge to Lake. 
Aug. 30, 1935 Channel 25 feet deep and 500 feet wide from 25-foot contour to mouth 
of Maumee River (300 feet wide on each side of center dike in Bay 
Channel), thence 400 feet wide to Fassett Street Bridge, 200 feet 
wide above that point and a turning basin at Upper end 18 feet 
deep. 
May 17, 1950 Widening at bend of mouth of River opposite Chesapeake and Ohio 
Railway Dock. 
Sept. 3, 1954 Removal of center dike in Maumee Bay Channel. 
July 3, 1958 Enlarge widening at bend opposite Chesapeake and Ohio dock and 
turning basin opposite American Shipbuilding Co. dock. 
July 14, 1960 Deepen Bay Channel including widenings to 28 feet, deepen River 
channels to New York Central Railroad Bridge to 27 feet and 
construct new turning basin below Anthony Wayne Brige.30. 
VERMILION HARBOR OHIO (See Section 22 of Text). 
Parallel piers and dredging channel to 8 feet deep. 
Deepening of channel to 12 feet. 
Reconstruction of piers. 
New entrance formed by two overlapping arrowhead breakwaters 
and extension of existing river channel upstream to Liberty St. 
Bridge. 
WEST HARBOR, OHIO (See Section 23 of Text). 
Construction of arrowhead breakwaters, entrance channel, and access 
channel. 
WILSON HARBOR, N Y (See Section 24 of Text). 
Entrance channel 80 feet wide and 8 feet deep; and restore east and 
west piers. 
Extend existing channel 300 feet; and construct new channel 3,800 
feet long through Tuscarora Bay. 
H. Doc. 198, 55th Cong., 2d 
sess. and Annual Report 
1898, p. 2693. 
H. Doc. 865, 60th Cong., 1st 
sess. 
Rivers and Harbors Committee 
Doc. 21, 72d Cong., 1st sess. 
H. Doc. 189, 81st Cong., 1st 
sess. 
H. Doc. 620, 81st Cong., 2d sess. 
H. Doc. 436, 84th Cong., 2d 
sess. 
H. Doc. 153, 86th Cong., 1st 
sess. 4 
Annual Report, 1880 
Annual Report, 1874, p. 219. 
H. Doc. 252, 58th Cong., 2d 
sess. 
H. Doc. 231, 85th Cong., 1st 
sess. 
H. Doc. 245, 88th Cong., 2d 
sess. 
H. Doc. 679, 76th Cong., 3d 
sess. 
H. Doc. 112, 90th Cong., 1st 
sess. 
20-25 
July 4, 1836 
Mar. 3, 1875 
Mar. 3, 1905 
July 3, 1958 
Oct. 27, 1965 
Mar. 2, 1945 
Aug. 13, 1968

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
STURGEON POINT, EVANS, N Y (See Section 27 of Text). 
Rehabilitate existing breakwater, construct rubblemound west 
breakwater extension, construct rubblemound east breakwater, a 
shore revetment, and dredging. 
MAUMEE BAY STATE PARK, OHIO (See Section 28 of Text). 
Protective sand beach stabilized by rubblemound offshore breakwaters 
and jetties along the west half of park shoreline and rubblemound 
revetment at the east end of the park. 
PRESQUE ISLE PENINSULA, ERIE, PA (See Section 29 of Text). 
Sept. 3, 1954 Construction of groin system, seawall, bulkhead, placement of beach 
material at waterworks reservation and along remainder of 
peninsula; removal of portions of existing structures. 
July 14, 1960 Periodic nourishment of shores for a 10-year period. 
Mar. 7, 1974 Periodic nourishment of shore for a 5-year period. 
Oct. 22, 1976 Preparation of Phase I design memorandum for improvements 
(Sec. 101) consisting of construction of five sections of spaced offshore 
breakwaters and replenishment of beach area with sandfill. 
Nov. 17, 1986 Construct offshore breakwaters and restore beaches. 
LAKESHORE PARK, ASHTABULA, OHIO (See Section 31 of 
Text). 
Construction of offshore breakwaters, restoration of an 800-foot long 
beach, and subsequent periodic nourishment as necessary. 
ELLICOTT CREEK, NY (See Section 32 of Text). 
Widening, straightening and deepening channel in Ellicott Creek 
Park; construct diversion channels; construct 3 highway bridges; 
modify culverts; modify utilities and drainage outlets; and 
construct recreation facilities. 
MT. MORRIS LAKE, GENESEE RIVER, N Y, (See Section 33 of 
Text). 
Construction of a concrete gravity dam and reservoir. 
OTTAWA, OHIO (See Section 34 of Text). 
Construction of leeves, floodwalls, combined with channel improvement, 
bridge change, and construction of new bridges. 
POINT PLACE, TOLEDO, OHIO (See Section 35 of Text). 
Construction of steel sheet pile wall, levees, pumping stations, storm 
sewer facilities, and gravity outfalls. 
RENO BEACH - HOWARD FARMS AREA OHIO (See Section 36 
of Text). 
Construction of dike and levees. 
CONESUS LAKE, LIVONIA, NY (See Section 40 of Text). 
Construction of sheetpiling, concrete control structure, outlet 
channel, and creek channelization. 
EUCLID CREEK, CLEVELAND, OHIO (See Section 40 of Text). 
Construction of diversion channel, levees, and creek channelization. 
Sec. 107, PL 86-645. Authorized 
by Chief of Engineers Oct. 
21, 1987. 
Sec. 501, PL 99-662. 
H. Doc. 231, 81st Cong., 1st 
sess. 
H. Doc. 397, 86th Cong., 2d 
sess. 
H. Doc. 796, 93d Cong., 2d Sess. 
Sec. 501, PL 99-662. 
Sec. 103, PL 87-874. Authorized 
by Chief of Engineers April 
26, 1982. 
Sec. 201, PL 91-611 
Sec. 14, PL 93-251 
H. Doc. 615, 78th Cong., 2d 
sess. 
H. Doc. 485, 89th Cong. 
H. Doc. 363, 92d Cong., 2d sess. 
H. Doc. 554, 8th Cong., 2d sess. 
Sec. 205, PL 858. Authorized by 
Chief of Engineers July 22, 
1985. 
Sec. 205, PL 858. Authorized by 
Chief of Engineers Oct. 9, 
1981 
1. Authorized by Public Works Administration, Sept. 6, 1933. 
2. Widening Cuyahoga River downstream at end of Cut 4 
classified inactive. 
3. Replacement of bridges 19 and 32, widening Cuyahoga and 
Old River Channels, classified deferred. 
4. Contains latest published map. 
5. Permanent Appropriations Repeal Act. 
6. Authorized May 28, 1935 by Emergency Relief Administration 
Act of 1935. 
7. Improvement of guide pier at Black Rock Lock was 
deauthorized by Congress in August 1977. 
8. Classified deferred. 
9. Completed under previous projects. 
10. Also Sundry Civil Act of Mar. 3, 1905. 
11. Authorized in part by Public Works Administration, Sept.6, 
1933. 
12. Authorized by Public Works Administration Sept. 6, 1933. 
13. Previously authorized by Public Works Administration. 
14. First Deficiency Appropriations Act approved April 1, 1944. 
15. Authorized by Defense Plant Corp., May 19, 1942. 
20-26 
July 14, 1960 
Nov. 17, 1986 
Oct. 23, 1962 
as amended 
Dec. 31, 1970 
Mar. 7, 1974 
Dec. 22, 1944 
Nov. 7, 1966 
Oct. 27, 1965 
June 30, 1948 
June 30, 1948, 
as amended 
June 30, 1948, 
as amended.

BUFFALO N.Y., DISTRICT 
TABLE 20-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
16. Deepening left half of channel extension was eliminated 24. Deepening remainder of Cuyahoga River from bridge 1 to 
from project by 1962 R&H Act. and including Old River, classified deferred. 
17. Permit of Secretary of War, Aug. 5, 1927. 25. Included in Public Works Administration program, Nov. 
18. Modified 1828 and 1852. 15, 1933. 
19. Extension of north pier portion of this modification was 26. Deepening strips adjacent to north and south piers was 
deauthorized Nov. 1981. deauthorized Aug. 1982. 
20. Public Law 366. 27. Modification classified inactive. 
21. Modified 1830, 1881, and 1890. New work completed under 28. Construction of breakwater classified deferred. 
previous projects. 29. Deepening and widening remainder of Black River channel 
22. Partly included in Public Works Administration program, at Cut 1 classified deferred. 
Nov. 15, 1933. 30. The 27-foot project extended 2,800 feet and turning basin 
23. First Supplemental National Defense Appropriation Act, relocated under authority of Chief of Engineers. 
1944 approved Dec. 23, 1943. 
TABLE 20-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 26 of Text) 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Big (Cunningham) Creek, Ohio' Completed _2 $ 19,763 3 
Black River Harbor, N Y4 
- - 2 42,401 
Cape Vincent Harbor, N Y Completed 1962 275,082 $1,563,727 
Cattaraugus Creek, N Y5 
-_ _2 57,410 - 
Elk Creek Harbor, Pa. Active 1978 101,500 
Geneva-on-the-Lake, Ohio Completed 1988 3,681,563 16 60 
Grasse River (Massena), N Y4,6 - 1891 9,000 3 - 
Great Sodus Bay Harbor, N Y Completed 1988 610,959 7 2,470,590 18 
Hamlin Beach Harbor, N Y Deferred 1973 72,052 
Kelleys Island, Ohio Active 1974 12 129,874 
Little River at Cayuga Island, N Y Completed 1969 46,804 7 42,393 
Little Sodus Bay Harbor, N Y Completed 1988 301,394 19 3,101,290 20 
Morristown Harbor, N Y Completed 1949 6,221 9,694 
Niagara Remedial Works, N Y8 Completed 1966 6,069,395 510,819 
Niagara River, N Y13 Completed 1964 559,457 9 144,569 
Ogdensburg Harbor, N Y Completed 1987 1,720,466 14 1,357,007 15 
Oswego Harbor, N Y Completed 1988 8,430,016 21 6,637,325 22 
Ottawa River Harbor, Michigan and Ohio Inactive 1977 12 99,000 - 
Port Bay, N Y Active - - - 
Port Clinton Harbor, Ohio Completed 1985 71,950 928,608 
Pultneyville Harbor, N Y" - 1934 68,219 20,087 
Put in Bay, Ohio Completed 1951 12 51,609 13,046 
Sackets Harbor, Ohio Completed 1982 25,010 25,298 
Sandusky River, Ohio 4 - 1894 58,0003 557 
1. No commerce reported. 
2. Only information available is in index to reports of Chief of 
Engineers. 
3. Amount includes maintenance; not separable. 
4. Abandonment recommended in H. Doc. 467, 69th Cong., 
1st sess. 
5. Abandonment recommended inEx. Doc. 16, 35th Cong., 1st 
sess. 
6. Channel improved by local interests. 
7. Includes local interests contribution of $25,742. 
8. Costs of operation and maintenance of this project will be 
settled directly by concerned power agencies. No further appropriations 
will be made to this project. 
9. Includes local interests contribution of $27,563. 
10. Includes local interests contribution of $5,000. 
11. Abandonment recommended in H. Doc. 375, 64th Cong., 
1st sess. 
12. Annual Report for Detroit District. 
13. Construction of compensating works as authorized by 1930 
R&H Act was deauthorized by Congress in August 1977. 
14. Includes $271,380 for previous projects. Excludes $57,000 
contributed funds. 
15. Includes $130,512 for previous projects. 
16. Excludes $3,236,062 for previous projects. 
17. Includes $361,772 for previous projects. 
18. Excludes $713,544 for Rehab. 
19. Includes $232,328 for previous projects. 
20. Excludes $742,822 for Rehab. 
21. Includes $1,187,977 for previous projects. 
22. Includes $945,684 for previous projects. Excludes $307,590 
Rehab. 
20-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-D OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
(See Section 30 of Text) 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Cleveland and Lakewood, Ohio: 
Edgewater Park' Deferred - - - 
White City Park' Deferred - - - 
Fair Haven Beach State Park, 
Lake Ontario2 Deferred - - - 
Fort Niagara State Park, N Y3 Active - - - 
Hamlin Beach State Park, N Y Completed 1976 $1,769,600 - 
Lakeview Park, Lorain, OH Completed 1987 1,741,125 S 
Selkirk Shore State Park, Lake Ontario, N Y4 Deferred 1963 58,978 $2,946 
1. Project authorized by River and Harbor Act of September 3, 4. Federal participation was limited to one-third of first cost 
1954 is classified as deferred. when project was authorized by 1954 River and Harbor Act. Federal 
2. Project authorized by River and Harbor Act of July 3, 1958 participation was changed from one-third to 70 percent of remaining 
is classified as deferred. work under Public Law 87-874. Uncompleted portion of project is 
3. Project authorized under provision of Section 201, 1965 classified as deferred. 
Flood Control Act as been reclassified as active. 5. Does not include $739,700 contributed funds. 
TABLE 20-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 39 of Text) 
Cost to September 30, 1989 
For Last 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Auburn, N Y Owasco Outlet' Completed 1962 $ 371,9856 - 
Batavia and vicinity, Tonawanda Creek, N Y' Completed 1957 335,385 - 
Caledonia, Genesee River, N Y Deferred 1950 - - 
Camp Perry, Ohio' Completed 1967 " 275,000 '0 
Cayuga Creek, Cheektowaga, N Y',5 Completed 1984 1,404,500 - 
Chittenango Creek and tributaries, N y2,3 Inactive 1948 12,464 - 
Cuyahoga River Basin, Ohio Active 1985 1,117,000 - 
Dansville and vicinity, Canaseraga Creek, N Y Active 1985 490,300 - 
East Lake, Ohio, Chagrin River 3 Inactive 1976 506,344 - 
Fremont, Ohio, Sandusky River' Completed 1976 8,589,824 9 - 
Ithaca, N Y, Cayuga Inlet, N Y' Completed 1978 3,929,330 2 - 
Lackawanna, N Y Smokes Creek' Completed 1971 3,542,068 7 
Lancaster, Cayuga Creek, N Y' Completed 1954 797,300 - 
Marsh Creek, Geneva, N Y5 Completed - 226,429 - 
Montour Falls, Oswego River Basin, N Y' Completed 1954 1,681,785 - 
Onondaga Creek, Nedrow, N Y ',5 Completed 1964 330,231 - 
Owasco Inlet and Outlet, Montville and 
Dry Creek, State Ditch and Crane Brook, N Y4 Inactive/Deferred 1950 281,559 - 
Scajaquada Creek, N Y' Completed 1985 4,944,852 - 
Syracuse, Oswego River Basin, N Y' Completed 1954 3,349,248 - 
Warsaw, N Y Oatka Creek', 5 Completed 1969 558,317 8 
Wellsville, N Y Genesee River' Completed 1978 3,145,303 '3 
1. Completed. 
2. Local interest required to contribute $25,000. 
3. Project is not considered economically justified and is 
inactive. 
4. Inactive portion of work for State Ditch has been done by 
local interest and work on Crane Brook has been deferred at the 
request of local interests. 
5. Project authorized by Chief of Engineers. 
6. Excludes costs of $188,732 under Public Law 84-99, Flood 
Control and Coastal Emergencies Appropriation, incurred for 
project rehabilitation as a result of damages due to storm Agnes, 
June 1972. 
7. Includes local interest contribution of $50,000. 
8. Excludes costs of $26,807 under Public Law 84-99, Flood 
Control and Coastal Emergencies Appropriation, incurred for 
project rehabilitation as a result of damages due to storm Agnes, 
20-28

BUFFALO N.Y., DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 39 of Text) 
June 1972. 
9. Includes local interests contribution of $6,944. Excludes 
cost of $383,786 under Public Law 84-99, Flood Control and Coastal 
Emergencies Appropriation, for emergency restoration of levees 
damaged during 1973. 
10. Includes local interest contribution of $125,000. 
11. Annual Report for Detroit District. 
12. Includes local interests contribution of $99,000. Excludes 
TABLE 20-G 
costs of $104,005 under Public Law 84-99, Flood Control and 
Coastal Emergencies Appropriation, incurred for project rehabilitation 
as a result of damages due to storm Agnes, June 1972. 
13. Includes local interests contribution of $50,000. Excludes 
costs of $374,042 under Public Law 84-99, Flood Control and 
Coastal Emergencies Appropriation, incurred for project rehabilitation 
as a result of damages due to storms. 
Study Identification Fiscal Year Cost 
East Harbor State Park, OH $30,758 
Lake Erie, Sheffield, OH 877 
North Sandy Pond, Oswego Co., NY 40,032 
Seneca Lake, Geneva, NY 43,581 
Toussaint River, Carrol Twsp., OH 36,302 
TABLE 20-H FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 40 of Text) 
Flood Control Activities pursuant to Sec. 205 
Public Law 858, 80th Congress as amended (preauthorization) 
Study Identification 
Andover, Dyke Creek, NY 
Buffalo River, West Seneca, NY 
Butternut Creek, DeWitt, NY 
Canadaway Creek, Fredonia, NY 
Canandiagua Lake, NY 
Cattaraugus Creek, Arcade, NY 
Cazenovia Creek, Buffalo, NY 
Chagrin River, Eastlake, OH 
Cross Lake, NY 
Honeoye Lake, NY 
Keuka Lake Outlet, NY 
Limestone Creek, Fayetteville, NY 
Maumee River, Grand Rapids, OH 
Oneida Lake, NY 
Owasco Inlet, Groton, NY 
Scajaquada Creek, Depew, NY 
Silver Creek, Silver Creek, NY 
Swan Creek, Toledo, OH 
Temple Creek, Elk Creek, PA 
Village of Malone, NY 
W. Br. Limestone Creek, Manlius, NY 
Fiscal Year Cost 
$34,614 
3,337 
217 
11,210 
7,372 
1,746 
13,863 
13,552 
15,691 
38,430 
31,260 
31,957 
195 
4,444 
17,259 
39,882 
3,483 
11,783 
4,569 
308 
38,585 
20-29 
TABLE 20-E 
(Continued) 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 27 of Text) 
Navigation Activities Pursuant to Section 107, Public Law 86-645 
(Preauthorization)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 20-H (Continued) 
FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(See Section 40 of Text) 
Emergency bank protection (Sec. 14 of 1946 Flood Control Act, 
Public Law 526, 79th Cong.) 
Study Identification 
Butternut Creek, E. Syracuse, NY 
Canadaway Creek, Fredonia, NY 
Chagrin River, Solon Rd., OH 
Chagrin River, East Branch, Sperry Rd., OH 
Chagrin River, East Branch, Wisner Rd., OH 
Clear Creek, Bray Rd., Freedom, NY 
Clear Creek, Rt. 98, Freedom, NY 
Cuyahoga River, Akron Peninsula Rd., OH 
Cuyahoga River, Brecksville Rd., OH 
Cuyahoga River, North Portage Path, Akron, OH 
Cuyahoga River, Riverview Rd., Northampton, OH 
Keshequa Creek, Nunda, NY 
Lake Erie, Lakeshore Blvd, Willowick, OH 
Lake Erie, Eastlake, OH 
Lake Erie, Fredonia, NY 
Lake Erie, Linwood Park, Vermilion, OH 
Lake Erie, Mentor-on-the-Lake, OH 
Lake Erie, Middle Bass Island, Deist Rd., OH 
Lake Erie, North Point Dr., Avon Lake, OH 
Lake Erie, St. Joseph Christian Life Center, OH 
Lake Erie State Park, Brocton, NY 
Maumee River, Providence Metropark, OH 
Mill Creek, Warrenville Twsp, OH 
Sandusky River Ream Rd., Sandusky, OH 
Sandusky River, Twsp. Rd. 234, Sandusky Twsp., OH 
Fiscal Year Cost 
$ 9,964 
1,225 
14,957 
4,126 
1,424 
2,266 
4,011 
5,811 
10,425 
296,649 
115,574 2 
4,146 
2,951 
50 
8,737 
3,742 
500 
665 4 
2,003 
14,929 
6,513 5 
1,638 
7,787 
3,751 
6,354 
1. Does not include $94,411 in contributed funds. 4. Does not include $131 in contributed funds. 
2. Does not include $26,281 in contributed funds. 5. Does not include $3,648 in contributed funds. 
3. Does not include $10,395 in contributed funds. 
TABLE 20-I DEAUTHORIZED PROJECTS 
(See Section 41 of Text) 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Black Rock Channel and 
Tonawanda Harbor, NY 1935 R&H Act' 
Black Rock Channel and Tonawanda Harbor, NY 
1954 R&cH Act 
Cape Vincent Harbor, NY 1945 R&H Act 
Crane Creek State Park, OH 1962 R&H Act 
Erie Harbor, PA 1945 R&H Act 
Erie Harbor, PA 1899 R&H Act 
Erie Harbor, PA 1960 R&H Act 
Grandview Bay Harbor, NY 1945 R&H Act 
Great Sodus Bay Harbor, NY 1962 R&H 
Hammondsport, Oswego River Basin, NY 1941 FC Act 
Ithaca, NY-Cascadilla Creek 1941 FC Act 
Ithaca, NY-Fall Creek 1941 FC Act 
Maumee River, above Toledo, OH 1872 Act 
1962 
1962 
1962 
1968 3 
1963 
1963 
1963 
1948 
1963 
1951 
1950 
1950 
1971 3 
Aug 1977 
May 1981 
Nov 1986 
Nov 1979 
Aug 1977 
Nov 1981 
Aug 1982 
Aug 1977 
Aug 1977 
Nov 1983 
Aug 1977 
Aug 1977 
Nov 1977 
-
-
-
-
- 
$1,524 
29,000 
8,159 
12,300 
12,000 
20-30

TABLE 20-I (Continued) 
BUFFALO, N.Y., DISTRICT 
DEAUTHORIZED PROJECTS 
(See Section 41 of Text) 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Niagara River, Compensating Works, NY 
1930 R&H Act 1964 Aug 1977 - - 
Ogdensburg Harbor, NY 1935 R&H Act 1986 Nov 1986 - - 
Oswego Harbor, NY 1940 R&H Act2 1963 May 1981 -- 
Red Creek, NY 1966 FC Act 1975 Nov 1986 361,241 - 
Sackets Harbor, NY 1945 R&H Act 1948 May 1981 19,010 - 
Sheffield Lake Community Park, OH 1962 R&H Act - Aug 1977 - - 
Watkins Glen, NY 1941 FC Act 1958 Aug 1977 43,182 - 
1. Extension of guide pier only; other improvements 
completed. 
2. Deepening of west outer harbor, other improvements 
completed. 
3. Annual Report for Detroit District. 
20-31

DETROIT, MI DISTRICT * 
The district is composed of the upper and lower peninsulas 
of Michigan and portions of Indiana, Wisconsin and Minnesota, 
which border the lakes. It includes U.S. waters of Lakes 
Superior, Michigan, Huron, St. Clair and western Lake Erie. 
Unless otherwise indicated, all depths stated in this 
report are referred to low water datum as follows: Lake Superior, 
600 feet; Lake Michigan-Huron, 576.8 feet; Lake Erie, 
568.6 feet; and Lake St. Clair, 571.7 feet. Elevations in feet are 
above mean water level at Father Point, Quebec (International 
Great Lakes Datum - 1955). 
IMPROVEMENTS 
Navigation Page 
1. Algoma Harbor, WI ........................ 21-2 
2. Arcadia Harbor, MI .......................... 21-2 
3. Ashland Harbor, WI ......................... 21-2 
4. Au Sable Harbor, MI ....................... 21-2 
5. Bayport Harbor, MI ......................... 21-3 
6. Big Suamico River, WI ....................... 21-3 
7. Black River, (P.H.) MI ....................... 21-3 
8. Black River Harbor, (U.P.) MI ................ 21-4 
9. Bolles Harbor, MI .. ........................ 21-4 
10. Charlevoix Harbor, MI ........................ 21-4 
11. Clinton River, MI ..... ..................... 21-5 
12. Detour Harbor, MI .................. ...... 21-5 
13. Detroit River, M I ............. ............... 21-5 
14. Duluth-Superior Harbor, MN and WI ........... 21-6 
15. Eagle Harbor, MI ... ....................... 21-7 
16. Fox River, WI ............................ 21-7 
17. Frankfort Harbor, MI ......................... 21-7 
18. Grand Haven Harbor and Grand River, MI ....... 21-8 
19. Grand Marais Harbor, MI ..................... 21-8 
20. Grand Marais Harbor, MN .................. 21-9 
21. Grand Traverse Bay Harbor, MI .............. 21-9 
22. Green Bay Harbor, WI ........................ 21-9 
23. Harbor Beach Harbor, MI ................... .21-10 
24. Hearding Island Inlet, Duluth Harbor, MN ...... 21-10 
25. Holland Harbor, MI ......................... 21-10 
26. The Inland Route, MI :.......................21-10 
27. Kenosha Harbor, WI ........................ 21-11 
28. Kewaunee Harbor, WI ....................... 21-11 
29. Keweenaw Waterway, MI .................... 21-12 
30. Lac LaBelle Harbor, MI ..................... 21-12 
31. Lake St. Clair, MI Channels ................... 21-12 
32. Leland Harbor, MI ......................... 21-13 
33. Lexington Harbor, MI ........................ 21-13 
34. Little Lake Harbor, MI ................... .. .21-13 
35. Ludington Harbor, MI ....................... 21-13 
36. Mackinac Island Harbor, MI .................. 21-14 
Navigation (cont.) Page 
37. Manistee Harbor, MI ........................ 21-14 
38. Manistique Harbor, MI ....................... 21-14 
39. Manitowoc Harbor, WI ..................... 21-15 
40. Marquette Harbor, MI ...................... 21-15 
41. Menominee Harbor and River, MI and WI ...... 21-15 
42. Milwaukee Harbor, WI ....................... 21-16 
43. Monroe Harbor, MI ........................ 21-16 
44. Muskegon Harbor, MI ....................... 21-17 
45. New Buffalo Harbor, MI .................... 21-17 
46. Ontonagon Harbor, MI .................... 21-18 
47. Pentwater Harbor, MI ........................ 21-18 
48. Pointe Lookout Harbor, (Au Gres River) MI . .21-18 
49. Portage Lake Harbor, MI ..................... 21-19 
50. Port Austin Harbor, MI ...................... 21-19 
51. Port Sanilac Harbor, MI .................... 21-19 
52. Port Washington Harbor, WI ................. 21-19 
53. Port Wing Harbor, WI ..................... 21-20 
54. Rouge River, MI .......................... .21-20 
55. Saginaw River, MI ............ ............. 21-20 
56. St. Clair River, MI .......................... 21-21 
57. St. Joseph Harbor, MI ....................... 21-21 
58. St. Marys River, MI ......................... 21-22 
59. Saugatuck Harbor and Kalamazoo River, MI . .21-23 
60. Saxon Harbor, WI ......................... 21-23 
61. Sebewaing River, MI ........................ 21-24 
62. Sheboygan Harbor, WI ..................... 21-24 
63. South Haven Harbor, MI ................... 21-24 
64. Sturgeon Bay & Lake Michigan Ship Canal, WI . .21-24 
65. Two Harbors, MN .......................... 21-25 
66. Two Rivers Harbor, WI ...................... 21-25 
67. Whitefish Point Harbor, MI .................. 21-25 
68. White Lake Harbor, MI ..................... 21-26 
69. Reconnaissance and Condition Surveys ......... 21-26 
70. Other Authorized Navigation Projects .......... 21-26 
71. Navigation Work Under Special Authorization ... 21-26 
21-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Beach Erosion Control Page 
72. Authorized Beach Erosion Control Projects ... .21-26 
73. Emergency Shore Protection ................. .21-26 
74. Beach Erosion Work Under Special 
Authorization .............................. 21-27 
75. Mitigation of Shore Damages ............... .21-27 
Flood Control 
76. Paw Paw Lake, MI ........................ 2. 1-27 
77. Saginaw River, MI .......................... 21-27 
78. Sebewaing, Sebewaing River, MI .............. 21-28 
79. Inspection of Completed Flood Control Projects 21-28 
80. Other Authorized Flood Control Projects ...... 21-28 
81. Flood Control Under Special Authorization ... .21-28 
82. Surveillance of Northern Boundary Waters ..... 21-29 
83. Surveys .................. .............. . 21-31 
General Investigations Page 
84. Preconstruction Engineering and Design ........ 21-31 
85. Collection and Study of Basic Data ............ 21-31 
Tables 
Table 21-A Cost & Financial Statement ............ 21-33 
Table 21-B Authorizing Legislation ............... .21-46 
Table 21-C Other Authorized Navigation Projects ... 21-58 
Table 21-D Not Applicable ............................ 
Table 21-E Other Authorized Flood Control Projects 21-59 
Table 21-F Multiple Purpose Projects, including Power 
St. Marys River, MI: Existing Project ... .21-59 
Table 21-G Deauthorized Projects ................ .21-60 
Table 21-H Features of Existing Project ............ 21-61 
Table 21-I Fox River, WI: Locks & Dams .......... 21-62 
Table 21-J Reconnaissance & Condition Surveys ..... 21-63 
Navigation 
1. ALGOMA HARBOR, WI 
Location. On west shore of Lake Michigan, about 68 miles 
from Green Bay via Sturgeon Bay Canal and about 115 miles 
northerly from Milwaukee (See NOAA Nautical Chart No. 
14910). 
Previous project. For details see page 1199 of Annual 
Report for 1958. 
Existing project. Provides for (a) a north pier 1102 feet long; 
(b) a south breakwater 1530 feet long; (c) an entrance channel 
14 feet deep and 200 feet wide from that depth in Lake Michigan 
and extending 800 feet landward; (d) a channel 14 feet deep 
in the Ahnapee River 80 to 175 feet wide for 1200 feet up to the 
Second Street Bridge; (e) an outer basin 14 feet, 600 feet long 
and 100 to 500 feet wide. For a more detailed description see 
page 1200 of Annual Report for 1958. 
Section 52 (c) of the Water Resources Development Act 
(W.R.D.A.) of 1988 deauthorized the outer harbor basin feature 
of the navigation project. (See Table 21-B for legislation.) 
2. ARCADIA HARBOR, MI 
Location. On east shore of Lake Michigan, 193 miles northeasterly 
from Chicago, IL, and 15 miles northerly from Manistee, 
MI. (See NOAA Nautical Chart No. 14907). 
Existing project. Provided for maintenance dredging of the 
existing harbor built by private interests for a period of five 
years. The five years covered by this project were the calendar 
years 1905 to 1909, inclusive. Funds were also appropriated 
and maintenance was performed in calendar years 1911, 1912, 
1913 and 1915, inclusive. There is at present no approved project 
for the improvement of this harbor. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Dock facilities are considered adequate 
for existing recreational traffic. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, and miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $60,384. A contract was awarded and completed 
for repairs to the North and South Pier and Revetment at a cost 
of $1,956,296. Engineering and design during construction 
cost $2,198. A contract was also awarded and completed for 
maintenance dredging at a cost of $32,552 removing approximately 
5,224 cubic yards of shoal material by hydraulic 
dredge. Engineering, design, surveys, real estate, supervision 
and administration cost $106,777. 
Existing project was completed in 1909. Varying depths of 5- 
12 feet exist in the channel at present. Future maintenance of 
the harbor will be based on providing a 9-foot depth. Piers and 
revetments are in good condition with some sections in need of 
major repair. Total cost for existing project to end of FY was 
$4,083,366. 
3. ASHLAND HARBOR, WI 
Location. At head of Chequamegon Bay, on south shore of 
Lake Superior, about 65 miles east of Duluth, MN. (See 
NOAA Nautical Chart 14974.) 
Existing project. A west channel 20 and 21 feet deep and an 
east basin 25 and 27 feet deep, both all protected by an 8,000- 
foot breakwater. For additional details see page 1008 of 
Annual Report for 1965. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Ashland owns 4,150 feet of 
waterfront for future public needs. Wharves for handling coal, 
ore, limestone, logs and pulpwood are served by railroads. 
Facilities are considered adequate for existing commerce. Handling 
of ore and logs has been discontinued for the present. 
Operations during fiscal year. Maintenance: Condition surveys, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $24,006. Breakwater repairs 
were performed by the derrickbarge COLEMAN at a cost of 
$57,357. Supervision and administration cost $1,589. 
Work authorized prior to 1960 Act was completed in 1950. 
Work authorized by 1960 Act was completed in November 
1962. Total cost for existing project to end of FY was 
$4,763,421, of which $1,695,645 was for new work and 
$3,067,776 for maintenance. 
4. AU SABLE HARBOR AT AU SABLE 
RIVER (OSCODA), MI 
Location. The Au Sable River and Village of Oscoda, MI 
are on west shore of Lake Huron, 8 miles north of Au Sable 
21-2

DETROIT, MI DISTRICT 
Point, northeast limit of Saginaw Bay. (See NOAA Nautical 
Chart 14863.) 
Previous project. For details see pages 336 and 2453 of 
Annual Report for 1892. 
Existing project. Riprapping outer 200 feet of north pier at 
mouth of Au Sable River, dredging an entrance channel 12 feet 
deep and dredging between piers and upstream to State highway 
bridge 10 feet deep. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small timber pile wharfs used primarily 
by commercial fishermen and pleasure craft operators; 
also a private marina basin east of U.S. Highway 23 Bridge. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys 
and miscellaneous inspections and reports were performed 
by Government forces at a cost of $10,437. The contract 
awarded last FY for repair of Breakwater Cell Caps was 
completed at a cost of $41,481. Engineering and design during 
construction, surveys, supervision and administration cost 
$9,415. 
Existing project was completed in 1962. Total cost for existing 
project to the end of FY was $2,781,341, of which $209,776 
was for new work (includes $16,400 contributed funds) and 
$2,571,565 for maintenance. 
5. BAY PORT HARBOR, MI 
Location. On Wild Fowl Bay on east shore of Saginaw Bay 
about 10 miles south of Caseville, Mich. (See NOAA Nautical 
Chart No. 14863.) 
Existing project. Provides for a channel 6 feet deep and 50 
feet wide extending 5,750 feet from 6-foot contour in Saginaw 
Bay to intersection of private service channels to be dredged by 
local interests. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small wharves used primarily by 
commercial fishermen. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys 
and environmental studies were performed by Government 
forces at a cost of $24,609. Engineering and design for a 
maintenance dredging contract to be awarded next FY cost 
$24,737. 
Existing project was completed in 1967. Total cost for existing 
project to end of FY was $215,672, of which $93,597 was 
for new work and $122,075 for maintenance. 
6. BIG SUAMICO RIVER, WI 
Location. A small stream which flows easterly into Green 
Bay, an arm of Lake Michigan. Mouth of the river is about 8 
miles north of Green Bay Harbor, and about 44 miles southwesterly 
from Menominee Harbor, MI and WI. (See NOAA 
Nautical Chart No. 14910.) 
Existing project. An entrance channel 8 feet deep which 
extends from that depth in Green Bay to 1,800 feet above the 
river mouth, with widths of 100 feet in bay and 60 feet in river; 
total length of channel is about 3,700 feet. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Small private wharves along lower 1.5 
miles of river, used by local fishing interests. Ample space is 
available for additional fishing wharves when required. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$13,040. The contract for maintenance dredging awarded last 
FY was completed at a cost of $379,601. Cost incurred 
included Confined Disposal Site Construction and Preparation 
and removing 32,635 cubic yards of material. Surveys, 
supervision and administration cost $57,344. 
Existing project was completed in 1938. Dredging channel 
was started in September 1938 and completed in November 
1938. Total cost for existing project to end of FY was $790,429 
of which $20,243 was for new work and $770,186 for maintenance. 
7. BLACK RIVER (PORT HURON), MI 
Location. This river has its source in the northern part of 
Sanilac County, MI, is about 60 miles long, and flows in a 
southeasterly direction into the St. Clair River. (See NOAA 
Nautical Chart 14852.) 
Previous project. For details see page 1441 of Annual 
Report for 1916, and page 1554 of Annual Report for 1938. 
Existing project. Provides for a channel 20 feet deep from 
deep water in St. Clair River to the Grand Trunk Western Railroad 
Bridge, 160 feet wide at the mouth, decreasing to 100 feet, 
about 800 feet from the mouth, thence 100 feet wide for 2,600 
feet, decreasing to 75 feet for a distance of 4,800 feet; widening 
two bends to 100 feet, one at the foot of 12th Street, and the 
other below the Grand Trunk Western Railroad Bridge; for a 
settling basin 75 feet wide and 20 feet deep, beginning at the 
Grand Trunk Western Railroad Bridge in Port Huron and 
extending upstream a distance of about 2,300 feet; and then 
for a distance of 2.6 miles as a 100-foot wide river channel, 8 
feet deep to the I-94 bridge where it decreases to 6 feet deep and 
continues to the vicinity of the Black River Drainage Canal 
with suitable widening where required at bends in the channel. 
The project modification authorized by the Act of August 30, 
1935, is considered to be inactive and is excluded from the foregoing 
cost for new work. The cost of this modification was last 
revised in 1954 and was estimated to be $194,000 exclusive of 
$194,000 to be contributed by local interests. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are docks on both sides of Black 
River, near its mouth, and between these docks and the upper 
limit of improvement there are 5 other docks varying in length 
from 100 to 500 feet. All docks are privately owned and are 
restricted to the use of the owners. The facilities are considered 
adequate for existing commerce. Public recreational boating 
facilities constructed by the State and local agencies are available, 
as are privately owned and operated marinas. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$27,980. Engineering and design for maintenance dredging to 
be performed by contract next FY cost $38,891. Supervision 
and administration and real estate cost $2,235. 
21-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
All work, except that authorized by Act of August 30, 1935, 
and the latest modification, has been completed. Total cost for 
existing project to end of FY was $1,430,125, of which 
$830,165 was for new work (includes $349,921 contributed 
funds) and $599,960 for maintenance. 
8. BLACK RIVER HARBOR 
(UPPER PENINSULA), MI 
Location. At mouth of Black River on south shore of Lake 
Superior 39 miles westerly from Ontonagon, MI, and 47 miles 
easterly from Ashland, WI. (See NOAA Nautical Chart 
14965.) 
Existing project. Two converging breakwaters, an entrance 
channel between breakwaters, an inner channel, and an irregular 
harbor basin. For additional details see page 1092 of 
Annual Report for 1966. Project depths are 12 feet in the 
approach channel and 8 feet in the river channel and basin. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. Local interests furnished 
easements on 0.85 acre of land. 
Terminal facilities. Wharves constructed on both sides of 
river. Wharf on east bank has frontage of 400 feet; on west 
bank, a frontage of 750 feet. 
Operations during fiscal year. Maintenance: Condition surveys 
and environmental studies were performed by Government 
forces at a cost of $5,318. An adjustment of -$17,055 and 
-5,046 cubic yards was made to the maintenance dredging contract 
completed last FY. Supervision and administration cost 
$9,257. 
Project was completed in June 1958. A triangular-shaped 
rock shoal 50 feet wide at easterly end extends along southerly 
side of channel. Total cost for existing project to end of FY was 
$1,094,743, of which $383,350 was for new work and $711,393 
for maintenance. 
9. BOLLES HARBOR, MI 
Location. On west shore of Lake Erie at mouth of La Plaisance 
Creek, 7 miles southwest of Monroe, MI. (See NOAA 
Nautical Chart 14846.) 
Existing project. Provides for an entrance channel in Lake 
Erie, 8 feet deep and 80 feet wide from deep water to a point 
opposite the outer end of existing jetty, thence widening to 100 
feet at creek mouth; an access channel in La Plaisance Creek, 6 
feet deep and 100 feet wide at the mouth widening to 120 feet 
and extending to the first bend, thence narrowing to 50 feet 
wide and continuing at that width to the La Plaisance Road 
bridge; a steel sheet pile revetment, about 200 feet long, located 
along Michigan State Conservation Department property on 
west side of channel at creek mouth. Project also provides for 
inclusion of existing 400-foot long steel sheet pile jetty constructed 
by Michigan State Waterways Commission at the 
mouth of La Plaisance Creek. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. The Monroe Boat Club and three 
marinas provide facilities adequate for existing recreational 
boat traffic. There is also a public launching ramp and parking 
area at Conservation Department fishing site at creek mouth. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$24,673. An adjustment of -$16,383 was made to the FY 87 
maintenance dredging contract terminated for default in FY 
88. The contract for maintenance dredging awarded last FY 
was completed removing 13,837 cubic yards of material at a 
cost of $119,941. Surveys, supervision and administration cost 
$13,401. 
The existing project was completed in 1970 (Adequate 
depths exist over the project length except for the upstream 800 
feet). Total cost for existing project to the end of FY was 
$3,286,723, of which $426,413 was for new work (includes 
$255,000 contributed funds) and $2,860,310 for maintenance. 
10. CHARLEVOIX HARBOR, MI 
Location. On east shore of Lake Michigan, 276 miles northeasterly 
from Chicago, IL, and 75 miles northerly from Frankfort, 
MI. (See NOAA Nautical Chart 14942.) 
Existing project. A channel 24 feet deep in Lake Michigan 
and a river channel 23 feet deep in the lower and upper channels 
connecting Lake Michigan with Lake Charlevoix via 
Round Lake. The channels are protected where needed by 
piers and revetments. For additional details see page 1476 of 
Annual Report for 1962. (See Table 21-B for authorizing legislation.) 
Section 25 of the Water Resources Development Act of 
1988 provides authorization pertaining to the South Pier to 
Charlevoix Harbor. It states, "The Secretary shall take such 
action as may be necessary to restore recreational uses established 
prior to May 1, 1988, or provide comparable recreational 
uses at the South Pier to Charlevoix Harbor project, 
Charlevoix, Michigan, in order to mitigate any adverse impact 
on recreational uses resulting from reconstruction of the South 
Pier.. ." 
Local cooperation. None required except the latest project 
modification is subject to the following: Provide without cost 
to the United States, all lands, easements, and rights-of-way 
required for construction and subsequent maintenance of the 
modified project upon the request of the Chief of Engineers, 
including suitable areas determined by the Chief of Engineers 
to be required in the general public interest for initial and subsequent 
disposal of excavated materials and any necessary 
retaining dikes, bulkheads, and embankments, therefor, or the 
cost of such retaining works; hold and save the United States 
free from damages due to the construction and maintenance of 
the modified project, except for damages due to the fault or 
negligence of the United States or its contractors; provide and 
maintain without cost to the United States depths in berthing 
areas and local access channels serving the terminals commensurate 
with the depths provided in the related project areas; 
accomplish, without cost to the United States, such alterations 
of submarine utility crossing as are required by the modified 
project; establish regulations prohibiting discharge of pollutants 
into the waters of the harbor by users thereof which regulations 
shall be in accordance with applicable laws or regulations 
of Federal, State and local authorities responsible for 
pollution prevention and control; if acquiring lands, easements 
and rights-of-way for construction of the project, local 
interests will comply with the applicable provisions of the Uniform 
Relocation Assistance and Real Property Acquisition 
Policies Act of 1970; Public Law 91-646, approved January 2, 
1971; contribute all costs in excess of $1,000,000 should the 
total cost of construction of the general navigation facilities 
exceed that amount, in accordance with provisions of Section 
107 of the 1960 River and Harbor Act, as amended. The total 
first cost of construction (1975) is estimated at $652,000. 
21-4

DETROIT, MI DISTRICT 
Terminal facilities. Several small landing places in Round Lake 
at Charlevoix for handling fish and miscellaneous commodities, 
a wharf for petroleum products at west end of Lake 
Charlevoix, and coal wharves at Advance and Boyne City. 
Charlevoix, Boyne City, and East Jordan provide public docks 
for small craft. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed at a cost of $95,833. The U.S. Cranebarge 
MANITOWOC performed removal of obstructions 
along channel limits at a cost of $53,891. Repairs to safety features 
were performed by hired labor at a cost of $2,647. The 
contract awarded last FY for repair of the South Pier and 
Revetment, Sections A & F, was completed at a cost of 
$1,265,491. Engineering and design during construction, surveys, 
real estate, supervision and administration cost 
$110,199. 
Existing project was completed in 1939 except for the latest 
modification. A controlling depth of 18 feet is available 
throughout the entire project, except for minor shoaling along 
the channel limits. Total cost for existing project to the end of 
FY was $9,218,882, of which $180,623 was for new work, 
$7,908,863 for maintenance (Bank Stabilization $46,352) and 
$1,129,396 for rehabilitation. 
11. CLINTON RIVER, MI 
Location. Has its source in Oakland County, MI, flows easterly 
about 60 miles and empties into Anchor Bay in northwestern 
part of Lake St. Clair. (See NOAA Nautical Chart 14850). 
Previous project. For details see page 1958 of Annual 
Report for 1915, and page 1556 of Annual Report for 1938. 
Existing project. An entrance channel in Anchor Bay 8 feet 
deep, 300 feet wide at 8-foot depth contour in the bay, gradually 
decreasing to 50 feet wide at about 1,000 feet upstream 
from mouth of Clinton River, a length of about 4,600 feet; a 
channel 8 feet deep and 50 feet wide in the river about 38,700 
feet long from entrance channel upstream to Mt. Clemens at 
Cass Avenue; closing old channel and making a cutoff at Shoemakers 
Bend; closing Catfish Channel; construction of revetments 
as needed in the river; and a harbor basin, 5 feet deep 
and 11 acres in area at entrance along bay channel, protected 
by breakwaters on north and south sides. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. River is used exclusively by recreational 
craft. There are numerous public and private piers and 
wharves along the river below the city. They are considered 
adequate. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$57,968. Maintenance of disposal area was performed by hired 
labor at a cost of $277. Engineering and design for a maintenance 
dredging contract deferred to perform more critical 
work cost $44,651. Engineering and design for construction of 
off-loading platform to be performed by contract next FY cost 
$23,232. Supervision and administration cost $431. The contract 
for construction of a confined disposal facility was completed 
at a cost this FY of $852,698. Surveys and layouts, engineering 
and design during construction cost $18,488. 
Supervision and administration for Dike Disposal cost 
$238,191. 
Existing project was completed in 1966. Total cost for existing 
project to end of FY was $5,703,081, of which $549,798 
was for new work (includes $289,752 contributed funds) and 
$5,153,283 for maintenance. 
12. DETOUR HARBOR, MI 
Location. On the west side of DeTour Passage, about 2 miles 
upstream from Lake Huron. The passage forms the mouth of 
the St. Marys River which connects Lakes Huron and Superior. 
(See NOAA Nautical Chart 14882.) 
Existing project. Provides for small boat harbor and harbor 
of refuge by dredging a 10-foot deep entrance channel and providing 
an 8-foot deep access channel protected by a 1,305-foot 
breakwater. The total estimated (October 1981) project cost is 
$2,650,000; the Federal cost is $1,400,000 and the non-Federal 
cost is $1,250,000, which is a cash contribution. (See Table 21- 
B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Public docking, landing, parking and 
sanitary facilities are being provided by the State of Michigan. 
Operations during fiscal year. Maintenance: Condition surveys 
and miscellaneous inspections and reports were performed 
by Government forces at a cost of $9,245. An adjustment 
of $381 was made to the contract completed last FY for 
repair of the Breakwater. Supervision and administration cost 
$90. 
Existing project is complete. Total cost for existing project 
to end of FY was $2,695,606, of which $2,559,346 was for new 
work and $136,260 for maintenance. 
13. DETROIT RIVER, MI 
Location. One of the Great Lakes connecting channels, 31 
miles long, flows south from Lake St. Clair to Lake Erie. (See 
NOAA Nautical Chart 14848.) 
Previous project. For details see page 1958 of Annual 
Report for 1915, and page 1541 of Annual Report for 1938. 
Existing project. Improving Detroit River main channels to 
provide 25.5-foot draft navigation; improving certain auxiliary 
and side channels; and construction of various water level 
and crosscurrent control structures. Details are in accompanying 
Table 21-H. Project depths are referred to local low water 
datum planes which correspond to low water datums for Lakes 
St. Clair and Erie, 571.7 and 568.6 feet above mean water level 
at Father Point, Quebec (International Great Lakes Datum - 
1955.) (See Table 21-B for authorizing legislation.) 
Estimated 1978 Federal cost of new work, exclusive of 
amounts expended on previous projects, is $159,300,000. 
Local cooperation. Fully complied with. No local cooperation 
is required for modifications authorized by Acts of July 
1946 and March 1956. The Trenton Channel modification 
approved August 13, 1968, is considered inactive. 
Terminal facilities. Numerous commercial installations used 
for handling coal, iron ore, limestone, steel products, petroleum 
products, and other items such as overseas general cargo. 
Detail on actual port and harbor facilities is in Port Series No. 
45 (revised 1984) prepared and published by the Water 
Resources Support Center. Facilities are considered adequate 
for existing commerce. 
21-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations during fiscal year. Maintenance: Condition surveys, 
Hi-Fix surveys, real estate, environmental studies, support 
of water control center, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$1,244,961. Maintenance of disposal area was performed by 
hired labor at a cost of $90,170. Location and removal of 
obstructions cost $1,647,907. An adjustment of -$5,167 was 
made to the contract for repair of the diked disposal facility at 
Pte. Mouillee completed last FY. A maintenance dredging contract 
at Pte. Mouillee Access Channel was awarded and completed 
this FY removing approximately 49,000 cubic yards of 
material at a cost of $645,399. Engineering, design and surveys 
cost $41,691. Engineering and design for maintenance dredging 
East Outer and Lower Livingstone channels to be performed 
by contract next FY cost $23,161. Supervision and 
administration cost $20,926. Under the Dike Disposal Program 
an adjustment of $764,999 was made to the FY 78 Pointe 
Mouillee Disposal Site Phase II contract. Supervision and 
administration for dike disposal was $571. 
Latest modification of connecting channels project in the 
Detroit River is complete except for compensating works. Pertinent 
data concerning channels covered by project at end of 
FY are set forth in Table 21-H. Total cost for existing project to 
end of FY was $202,336,328, of which $76,877,357 was for 
new work ($75,346,669 regular funds and $1,530,688 Public 
Works Funds) and $125,458,971 (includes $361,235 Section 
150 contributed funds) for maintenance. 
14. DULUTH-SUPERIOR HARBOR, 
MN AND WI 
Location. At extreme western end of Lake Superior. Cities 
of Duluth, MN, and Superior, WI, are on north and south 
sides, respectively. (See NOAA Nautical Chart 14975.) 
Previous projects. See page 1246 of Annual Report for 1962. 
Existing project. Provides for rebuilding canal piers at 
Duluth entry, replacement or construction of piers and breakwater 
at Superior entry and dredging approaches and channels 
within harbor, St. Louis Bay, and St. Louis River. Channels 
vary in depth from 32 to 28 feet in entrances, are 27 feet deep in 
iron-ore route channels, and are from 20 to 23 feet in inner 
channels. (See Table 21-B for authorizing legislation.) 
For details of authorized channel dimensions and dimensions 
of structures, see pages 1246 and 1247 of Annual Report 
for 1962 and page 1011 of Annual Report for 1965. Portion of 
project for deepening Twenty-first Avenue West channel is 
inactive. Estimated cost (1967) of this portion was $577,000. 
The Water Resources Development Act (W.R.D.A.) of 1986 
authorized modifications to the project to deepen the western 
portions of North and South Channels, the entire Upper Channel, 
and the Minnesota Channel to 27 feet LWD; widen the 
Cross Channel to provide a minimum turning basin of 1,500 
feet; widen the bend at the Arrowhead Bascule Bridge to 600 
feet; and construct an upland confined disposal facility. Estimated 
cost (Oct. 88) is $13,180,000; which includes $7,068,000 
Federal and $6,112,000 non-Federal. 
Local cooperation. Fully complied with for completed portion 
of project. Local cooperation items for the newly authorized 
project in the W.R.D.A. of 1986 (P.L. 99-662), are as 
described in House Document 150, 86th Congress, 1st Session, 
and also includes, as a result of P.L. 99-662, construction cost 
sharing as follows: 
a. Contribute in cash 25 percent of the total cost of construction 
of general navigation facilities, exclusive of aids to navigation, 
a contribution presently estimated at $2,350,000. The 
estimated cash contribution of $2,350,000 to be paid in lump 
sum prior to initiation of construction, or in annual installments 
during the construction period at a rate proportionate to 
the proposed or scheduled expenditure of Federal funds as 
required by the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final apportionment 
of cost to be made after actual costs have been determined; 
and 
b. Repay, with interest, over a period of up to 30 years following 
project completion, 10 percent of the total cost of construction 
of general navigation facilities, an amount presently 
estimated at $940,000. The Secretary of the Army may count 
against all or part of the 10 percent repayment, the amount of 
the local contribution for lands, easements, rights-of-way, 
dredged/demolition material disposal sites and relocations. In 
no case are these costs to count against the cash payment during 
construction, and in no case would the amount waived 
exceed 10 percent of project cost. 
Terminal facilities. There are 113 docks or terminals including 
some 54 major ones; all but one are privately owned. Facilities 
for handling iron ore, coal, limestone, petroleum, steel and 
scrap iron, cement, general cargo, and grain are believed adequate 
for most existing commerce. 
Operations during fiscal year. Rehabilitation: Miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $6,053. Engineering and design, supervision and 
inspection for the rehabilitation of North and South Piers Sections 
0, N-1, N and M contract completed last FY cost $12,277. 
Maintenance: Condition surveys, master plan, environmental 
studies, support of water control center, miscellaneous inspections 
and reports were performed by Government forces at a 
cost of $630,709. Operation and maintenance of the museum 
was performed by Government forces at a cost of $348,231. 
Operation and maintenance of service facilities and pier was 
performed at a cost of $93,981. A Commercial Activities Program 
study for the Visitor's Center cost $23,954. Repairs to 
Superior entry breakwater and seawalls were performed by the 
Derrickbarge COLEMAN at a cost of $170,728. Safety maintenance 
was performed by hired labor at a cost of $13,446. An 
adjustment of $55,584 and 9,373 cubic yards was made to a 
maintenance dredging contract awarded in FY 87 and completed 
last FY. The contract for maintenance dredging 
awarded last FY was completed with approximately 126,499 
cubic yards removed this FY at a cost of $925,491. A contract 
for maintenance dredging of contaminated materials was 
awarded this FY in the amount of $1,395,200. The contract is 
approximately 13% complete at a cost of $181,999. Cost 
incurred this FY was for mobilization, site preparation at Erie 
Pier and removing approximately 17,927 cubic yards of material. 
Engineering, design, surveys, supervision and administration 
cost $240,827. 
Work authorized prior to 1960 Act was completed in June 
1956. Under the 1960 Act, work on the outer harbor, included 
in House Document 150, was completed in June 1965. Work in 
the inner harbor, included in House Document 196, started in 
May 1963, was completed in November 1968 except for 21st 
Avenue West channel portion which is inactive. 
The United States owns 34.90 acres of land in fee in Minnesota 
and Wisconsin of which 2.15 acres are used for a vessel 
yard. Total cost for existing project to end of FY was 
$72,550,767, of which $16,109,258 was for new work, 
$45,490,636 for maintenance, and $10,950,873 for rehabilitation. 
21-6

DETROIT, MI DISTRICT 
15. EAGLE HARBOR, MI 
Location. On the south shore of Lake Superior on the North 
Face of Keweenaw Point, 31 miles northeasterly from the 
Upper Entrance to Keweenaw Waterway. (See NOAA Nautical 
Chart 14964.) 
Existing project. Provides for a short entrance channel, a 
guide pier marking the entrance on the west side, and a harbor 
basin. Project depths are 14 feet in the entrance channel and 12 
feet in the harbor basin. For additional details see page 1182 of 
Annual Report for 1959. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. An old Lshaped timber wharf is available 
but is in poor condition. A dock and launching ramp constructed 
by the State is located on the north side of the Harbor 
Basin. 
Operations during fiscal year. Maintenance: Condition surveys 
were performed by Government forces at a cost of $1,711. 
Minor repairs to navigation structures were performed by 
hired labor at a cost of $237. 
The original project was completed in 1879. The modification 
for a small boat harbor was completed in 1959. Total cost 
for existing project to end of FY was $293,058, of which 
$205,164 was for new work and $87,894 for maintenance. 
16. FOX RIVER, WI 
Location. Rises in Columbia County, WI, and flows about 
176 miles northerly into Green Bay. Wolf River, physically a 
main river but by designation a tributary of Fox River, rises in 
central part of Fort County, WI, and flows southerly. (See 
NOAA Nautical Chart 14916 for Lake Winnebago and lower 
Fox River.) 
Previous projects. See page 1368 of Annual Report for 1962. 
Existing project. Deepening and widening channel of Fox 
River from De Pere 7 miles above mouth to confluence of Wolf 
River, a total length of 59 miles, to 6 feet, with 9.6 feet in rock 
cut below De Pere lock and 7 feet in other rock cuts on lower 
river below Menasha lock; construction and reconstruction of 
19 locks and 9 dams; a concrete retaining wall at Kaukauna; 
construction and maintenance of harbors having depths of 6 
feet on Lake Winnebago; widening Neenah Channel to 100 
feet, with a 6-foot depth for about 1 mile; and dredging, snagging, 
and otherwise improving Wolf River 47 miles from its 
mouth to New London, depth to be 4 feet. 
Cost of completed portion of project is $513,424 for the 
lower river exclusive of previous projects. River and Harbor 
Act of 1925 portion of project is considered inactive and 
excluded from cost estimate. Estimated cost (1924) of this portion 
is $2,886,000. (See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Wharf and landing facilities are, in general, 
adequate for existing needs. (See Table 21-I on locks and 
dams, Fox River, WI.) 
Operations during fiscal year. Maintenance: Condition surveys, 
miscellaneous inspections and reports, safety training 
and plans for flood emergencies were performed at a cost of 
$44,956. Federal canal banks at various locations were 
repaired at a cost of $33,215. Pier repairs were performed at 
De Pere Dam at a cost of $70,324. Scour protection stone was 
placed below Menasha Dam at a cost of $42,200. Sediment 
sampling was performed at random sites at a cost of $30,104. 
An archaeological study for disposal was undertaken, totaling 
$36,913. The operation and maintenance of nine (9) dams and 
ten (10) overflow weirs and caretaker status maintenance of 
seventeen (17) locks and two (2) guard locks totaled $567,857. 
Retroactive pay in the amount of $53,950 was paid to cover 
lock and dam employees who were, from FY 1980 - FY 1988, 
paid at a lower pay scale than laws required. Fox River 
O.S.H.A. Program and major miscellaneous items of supply 
totaled $4,580. Water control studies, monitoring and regulation 
of water levels were performed at a cost of $228,280. Engineering 
and design costs were $28,073. Supervision and administration 
costs were $215,102. 
Existing project is complete except for the inactive portion. 
Nineteen original locks and nine original dams have been 
rebuilt. (See Table 21-I for year of completion of each). Structures 
and dredging in pools have increased original depths generally 
about 2 feet. Work remaining to complete project consists 
of dredging in upper portion of Wolf River, and rock 
removal and deepening of Neenah Channel on lower Fox 
River, which are no longer considered necessary. Existing locks 
and dams are generally in fair to good condition. Total cost for 
existing project to end of FY was $44,780,449, of which 
$3,753,334 was for new work and $41,027,115 for operation 
and maintenance. Funds in the amount of $3,706,187 were 
expended between July 5, 1884, and June 30, 1935, on operation 
and care of works of improvement under provisions of 
permanent indefinite appropriation for such purposes. 
17. FRANKFORT HARBOR, MI 
Location. On east shore of Lake Michigan, 204 miles northeasterly 
from Chicago, IL, and 28 miles northerly from Manistee, 
MI. (See NOAA Nautical Chart 14907). 
Existing project. Provides for constructing an exterior basin 
in Lake Michigan formed by two breakwaters, 450 feet apart at 
the outer ends, diverging at an angle of about 90 degrees, the 
main arm and shore connection on north breakwater are 972 
and 1,000 feet long, respectively, and the main arm and shore 
connection of south breakwater 1,188 and 1,400 feet long, 
respectively; for removing 801 feet of north and 1,172 feet of 
south pier; dredging basin 20 feet deep and 800 feet wide at 
entrance, decreasing toward new pier heads to 600 feet wide, 
dredging approach and entrance channel through outer basin 
to a depth of 24 feet from deep water in Lake Michigan to a 
point 500 feet landward of opening between breakwaters, over 
the entire width outside the breakwaters and to a maximum 
width of 500 feet inside the breakwaters; thence to 23 feet deep 
through inner portion of outer basin to outer end of north pier, 
over widths decreasing from 500 to 160 feet; and thence to 22 
feet deep between the piers to the inner basin in Lake Betsie; 
dredging an 18-foot deep interior basin in Lake Betsie from 
within 50 feet of existing structures on the west and extending 
eastward about 1,550 feet to easterly boundary and from 
within 50 feet of existing structures on the north and extending 
southward 800 feet to the southerly boundary; dredging a recreational 
craft anchorage area 10 feet deep and 300 feet wide, 
extending 600 feet eastward of the east limit of the interior 
basin, with its north side in line with the north limit of the 
basin. Breakwaters and shore connections are built of concrete 
caissons and piling capped with concrete. Inner piers and revetments 
are built of stonefilled timber cribs and piling, all capped 
with concrete, except for 476 feet of south revetment which 
consists of steel sheet piling. (See Table 21-B for authorizing 
legislation.) 
21-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Fully complied with. 
Terminal facilities. Two car ferry slips on south shore and 
several docks along north shore of Lake Betsie. The City and 
State provide a recreational docking facility on north side of 
Lake Betsie which is open to all on equal terms. There is also a 
marine railway capable of handling small craft. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, and miscellaneous inspections and reports 
were performed by Government forces at a cost of $26,889. 
Repairs to North and South Breakwater, Sections A, B, C and 
D, and South Revetment, Sections O and P were performed 
using the Cranebarge MANITOWOC at a cost of $48,699. 
Supervision and administration cost $4,772. 
Existing project was completed in 1939, with exception of 
the latest modification which was completed in 1969. Navigation 
structures are in good condition and programmed for 
major repair on an as needed basis. For additional details on 
completion of existing project see page 1474 of Annual Report 
for 1962. Total cost for existing project to end of FY was 
$9,962,726, of which $1,955,159 (includes $31,709 contributed 
funds) was for new work, $7,732,791 for maintenance, and 
$274,776 for rehabilitation. 
18. GRAND HAVEN HARBOR 
AND GRAND RIVER, MI 
Location. Harbor is on east shore of Lake Michigan. 108 
miles northeasterly from Chicago, IL, and 23 miles northerly 
from Holland, MI. River rises in Jackson County, MI, and 
flows 260 miles westerly into Lake Michigan. (See NOAA Nautical 
Chart 14933, and Geological Survey Grand Rapids quadrangle). 
Previous project. For details see page 1949 of Annual 
Report for 1915, and page 1481 of Annual Report for 1938. 
Existing project. An entrance channel protected by parallel 
piers and revetments at mouth of Grand River, a deep draft 
channel in river extending to Spring Lake, a turning basin, and 
a shallow draft channel in river extending 14.5 miles upstream 
to Bass River. Project depths are 23 feet in entrance channel, 21 
feet in river to turning basin, 18 feet in turning basin and channel 
to Spring Lake, and 8 feet in upper Grand River channel. 
For additional details see page 1461 of Annual Report for 
1962. Dredging on northerly side of inner channel is considered 
inactive. Estimated cost of this portion (1954) is $38,600. The 
Water Resources Development Act (W.R.D.A.) of 1986 authorized 
modifications to deepen the harbor entrance and river 
channels to 29 and 27 feet, respectively; and provides for a new 
and larger turning basin. Estimated cost (Oct. 88) is 
$18,700,000, which includes $10,950,000 Federal and 
$7,750,000 non-Federal. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed portions 
of project. Local cooperation items for the newly authorized 
project in the W.R.D.A. of 1986 (P.L. 99-662), are as 
described in House Document 661, 76th Congress, 3d Session, 
and also includes, as a result of P.L. 99-662, construction cost 
sharing requirements as follows: 
a. Contribute in cash 25 percent of the total cost of construction 
of general navigation facilities, exclusive of aids to navigation, 
a contribution presently estimated at $3,650,000. The 
estimated cash contribution of $3,650,000 to be paid in lump 
sum, prior to initiation of construction, or in annual installments 
during the construction period at a rate proportionate to 
the proposed or scheduled expenditure of Federal funds as 
required by the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final apportionment 
of cost to be made after actual costs have been determined; 
and 
b. Repay, with interest, over a period of up to 30 years following 
project completion, 10 percent of the total cost of construction 
of general navigation facilities, an amount presently 
estimated at $1,460,000. The Secretary of the Army may count 
against all or part of the 10 percent repayment, the amount of 
the local contribution of lands, easements, rights-of way, 
dredged/demolition material disposal sites and relocations. In 
no case are these costs to count against the cash payment during 
construction, and in no case would the amount waived 
exceed 10 percent of project cost. 
Terminal facilities. Several wharves exist for handling coal, 
limestone, sand and gravel, petroleum products, fish and miscellaneous 
commodities. There is also a car ferry slip which is 
inactive. The State and local agencies provide recreational 
boating facilities which are open to all on equal terms. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $240,918. The U.S. Cranebarge MANITOWOC 
performed repairs to the South Pier, Sections K, J, J-1, and I at 
a cost of $101,481. Minor repairs to navigation structures by 
hired labor cost $4,221. The contract awarded last FY for 
maintenance dredging of the inner harbor was completed at a 
cost of $393,297, removing approximately 104,909 cubic yards 
of dredged material. A contract was awarded and completed 
this FY for maintenance dredging at a cost of $107,136. 
Approximately 15,359 cubic yards of shoal material was 
removed from the outer harbor. This contract was also for 
beach nourishment. Engineering, design, surveys, real estate, 
supervision and administration cost $146,849. Environmental 
studies in connection with Section 111 of P.L. 90-483 were performed 
at a cost of $18,947. Beach nourishment in conjunction 
with above maintenance dredging contract cost $39,626. 
Supervision and administration cost for Section 111 was 
$1,806. 
Existing project was substantially completed in 1949. For 
additional details on completion of existing project see page 
1463 of Annual Report for 1982. Structures are generally in 
good condition; repairs are made on an as needed basis. Total 
cost for existing project to end of FY was $27,703,415, of 
which $1,458,469 was for new work, $25,431,333 for maintenance, 
and $813,613 for rehabilitation. 
19. GRAND MARAIS HARBOR, MI 
Location. On south shore of Lake Superior, 93 miles west of 
Sault Ste. Marie, MI. (See NOAA Nautical Chart 14962.) 
Existing project. Provides for a channel protected by parallel 
piers and for closing natural entrance channel with a pile 
dike. Project depths are 18 feet between piers and 20 feet in 
lake approach. For additional details see page 1449 of Annual 
Report for 1962. (See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small piers, a Coast Guard Station, 
and a small boat pier and launching ramp built by the 
State of Michigan provide facilities adequate for present traffic. 
21-8

DETROIT, MI DISTRICT 
Operations during fiscal year. Maintenance: Condition surveys 
and miscellaneous inspections and reports were performed 
by Government forces at a cost of $5,643. 
Existing project is complete except for widening a portion of 
channel from 250 to 300 feet. Project now being maintained to 
19 and 15 feet below I.G.L.D. in lieu of 20 and 18 feet which is 
adequate for current usage. Total cost for existing project to 
end of FY was $2,774,534, of which $1,055,871 was for new 
work and $1,718,663 for maintenance. 
20. GRAND MARAIS HARBOR, MN 
Location. On north shore of Lake Superior, 106 miles northeasterly 
from Duluth, MN. (See NOAA Nautical Chart 
14967.) 
Existing project. Provides breakwater piers to narrow the 
entrance; concrete seawalls across ledge at southeast corner of 
harbor; an anchorage area and a small-boat basin protected by 
a rubblemound breakwater. Project depths are 16 feet in 
anchorage area increasing to 20 feet near entrance and 8 feet in 
small-boat basin. For additional details see page 1014 of 
Annual Report for 1965. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two inactive pulpwood wharves and several 
fish wharves, all privately owned. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys 
were performed by Government forces at a cost of 
$10,909. 
Existing project is complete. Total cost for existing project 
to end of FY was $3,672,924, of which $450,972 was for new 
work, $1,991,952 for maintenance, and $1,230,000 for rehabilitation. 
21. GRAND TRAVERSE BAY HARBOR, MI 
Location. At mouth of Traverse River on eastern shore of 
Keweenaw Peninsula about 20 miles northeasterly from Portage 
entry to Keweenaw Waterway. (See NOAA Nautical Chart 
14964.) 
Existing project. Provides two parallel piers, an entrance 
channel between piers and a harbor basin. Project depths are 
12 feet between piers and 10 feet in basin. Project area 
extended 200 feet upstream in 1966. For additional details see 
page 1015 of Annual Report for 1965. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. Local interests furnished 
easements on 5.1 acres of land. 
Terminal facilities. Several privately owned fishing wharves. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $7,688. Repairs to N. Breakwater 
Section A were performed by the Cranebarge MARKUS 
at a cost of $22,068. 
Existing project was completed in 1950 except for extension 
of north pier completed in 1964. Steel cells and piers are in 
good condition. Total cost of existing project to end of FY was 
$1,995,690, of which $266,037 was for new work and 
$1,729,653 for maintenance. 
22. GREEN BAY HARBOR, WI 
Location. At mouth of Fox River, at head of Green Bay, 
about 180 miles from Milwaukee, WI, via Sturgeon Bay 
Canal, and about 49 miles southwest of Menominee Harbor, 
MI, and WI. (See NOAA Nautical Chart 14918.) 
Previous projects. See page 1366 of Annual Report for 1962. 
Existing project. See Chicago District 1979 Annual Report, 
Table 30-C, p. 30-30. 
For more detailed description of project see page 1216 of 
Annual Report for 1963. 
Cost of completed portion of project is $9,335,000 Federal, 
and non-Federal cost is $490,000 including $100,000 contributed 
funds. Local interests requested that the inactive portion 
of the 1962 River and Harbor Act, consisting of dredging the 
reach from 150 feet downstream of the C.&N.W. Railway 
Bridge to 1,700 feet upstream of this bridge, be reactivated and 
the authorization modified to include deepening the adjacent 
turning basin and modifying the C.&N.W. Railway Bridge to 
provide increased horizontal clearance. Estimated cost of this 
portion (1988) is $5,560,000; $3,614,000 Federal and 
$1,946,000 non-Federal which includes $1,390,000 local contribution. 
Section 601c of the Water Resources Development 
Act (W.R.D.A.) of 1986 authorized deepening the Fox River 
Channel, Green Bay, WI, to 27 feet. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for existing project. 
Terminal facilities. There are 16 wharves for handling coal, 
petroleum products, cement, limestone, general overseas 
cargo and miscellaneous commodities. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$458,885. Minor maintenance of the disposal area was performed 
by hired labor at a cost of $910. The contract for maintenance 
dredging the Outer Bay Portion awarded in FY 87 was 
completed removing 44,865 cubic yards of material at a cost 
this FY of $1,026,225. The contract for maintenance dredging 
the Fox River and Outer Channel awarded last FY was completed 
at a cost of $959,319. Cost incurred this FY included 
clearing of trees at Bayport Disposal Area and removing 
105,544 cubic yards of material. A contract was awarded this 
FY for maintenance dredging Inner Channel with Disposal in 
Bayport in the amount of $597,690. No work was performed 
this FY. Engineering, design, surveys, supervision and administration 
cost $358,596. Engineering and design for construction 
of a confined disposal facility cost $402. 
Existing project is complete. The 1962 modification was 
started in November 1966 and completed in September 1973, 
except for dredging the reach from 150 feet downstream of the 
C.&N.W. Railway Bridge to 1,700 feet upstream of this bridge. 
Dredging of the turning basin above Chicago & Northwestern 
Railway Bridge was commenced in August 1938. The turning 
basin was enlarged under authority of Section 5 of the River 
and Harbor Act of March 4, 1915, in order to provide sufficient 
area for the large ships that use it. The work was performed 
as part of a maintenance dredging contract in September 
and October 1973. East revetment at Grassy Island was 
entirely removed in July 1935. Dredging Fox River and 
21-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
entrance channel to Tail Point Light was completed in September 
1967. Total cost of the existing project to end of FY was 
$39,349,237, of which $38,408,437 were regular funds and 
$940,800 Public Works funds; $9,946,395 for new work and 
$29,402,842 for maintenance. The new work cost does not 
include $100,000 contributed funds. 
23. HARBOR BEACH HARBOR, MI 
Location. On west shore of Lake Huron about 60 miles 
north of Port Huron, MI. (See NOAA Nautical Chart 14862.) 
Existing project. Harbor of refuge protected by three breakwaters; 
a main entrance 23 feet deep; and an anchorage area 21 
feet deep. For additional details see page 1485 of Annual 
Report for 1962. (See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Coal and limestone are received at a private 
wharf. In addition, there is a public recreational craft pier, 
a Coast Guard pier, and several small installations engaged in 
docking and servicing light-draft commercial and recreational 
vessels. These facilities satisfy current commerce and traffic 
requirements. 
Operations during fiscal year. Maintenance: Condition surveys, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $19,714. The contract awarded 
in FY87 for repair of the Main Breakwater, Phase I, was completed 
at a cost of $252,995. Engineering and design for the second 
phase of repairing the Main Breakwater continued at a 
cost of $62,993. Real estate and supervision and administration 
cost $27,358. 
Existing project was completed in 1928. For additional 
details on completion of existing project see page 1485 of 
Annual Report for 1962. Total cost for existing project to end 
of FY was $10,952,873, of which $1,200,598 was for new 
work, $9,557,771 for maintenance, and $194,504 for rehabilitation. 
24. HEARDING ISLAND INLET, 
DULUTH, MN 
Location. In Duluth Harbor, which is at the extreme western 
end of Lake Superior. The city of Duluth, MN is on the north 
side. (See NOAA Nautical Chart 14975.) 
Existing Project. Hearding Island was formed by placement 
of dredged material in 1934 while deepening the Duluth-Superior 
Harbor. The Hearding Island Inlet is within the existing 
harbor line; however, it is outside of the Congressionally 
authorized Federal project at Duluth. Hearding Island Inlet is 
a 750-foot channel, 75 feet wide and 5 feet deep below Low 
Water Datum. Section 22 of the Water Resources Development 
Act of 1988 authorized dredging the Inlet to increase water circulation 
and reduce stagnant water conditions, at a total cost 
of $500,000. (See Table 21-B for authorizing legislation.) 
25. HOLLAND HARBOR, MI 
Location. On east shore of Lake Michigan 95 miles northeasterly 
from Chicago, IL, and 23 miles southerly from Grand 
Haven, MI. (See NOAA Nautical Chart 14932.) 
Previous project. For details see page 1948 of Annual 
Report for 1915 and page 1478 of Annual Report for 1938. 
Existing project. An outer breakwater protected approach 
channel in Lake Michigan, an entrance channel to Lake Macatawa 
protected by piers and revetments, a channel through 
Lake Macatawa into Black River, and a turning basin. Project 
depths are 23 feet in outer portion of approach channel 
decreasing to 21 feet at outer end of inner piers, 21 feet to upper 
end of project, and 18 feet in turning basin. For additional 
details see page 1458 of Annual Report for 1962. 
Widening bend of entrance channel into Lake Macatawa is 
in an active category as a result of a reclassification recommendation 
approved by the Office of the Chief of Engineers on 
August 20, 1981. Estimated cost of this portion (1988) is 
$2,517,000, Federal and $1,355,000 non-Federal which 
includes $1,248,000 local contribution. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with for completed portions 
of project. Work authorized by Act of 1954 is subject to 
condition that work on either or both proposed modifications 
may be undertaken by the United States provided local interests 
furnish all lands except 1.5 acres of Federal lands, easements, 
rights-of-way, and suitable spoil disposal areas for initial 
work and future maintenance; remove buildings and other 
structures, except existing revetments, from lands to be furnished; 
and hold the United States free from damages. 
Terminal facilities. Wharves are at inner end of Lake Macatawa, 
and used for handling coal, building materials, petroleum 
products, and miscellaneous commodities. Two shipbuilding 
yards are on south shore of the lake. Holland provides 
a public wharf for small craft. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $191,559. Minor repairs to navigation structures by 
hired labor cost $14,634. The contract awarded last FY for 
repair of South Revetment, Sections J thru P, was completed at 
a cost of $2,870,137. Engineering and design during construction 
cost $24,565. A contract for maintenance dredging the 
inner harbor was awarded in the amount of $890,765. The contract 
is approximately 46.6% complete at a cost of $414,633, 
removing approximately 34,625 cubic yards of shoal material 
from the inner harbor. Another contract was awarded for 
maintenance dredging of the outer harbor and was completed 
at a cost of $86,970 removing approximately 16,100 cubic 
yards of dredge material. Engineering and design for major 
repairs to the remaining portion of South Revetment, Section 
P, was performed at a cost of $29,557. Engineering and design 
for major repairs to North and South Connector, Section Q, 
cost $48,157. Engineering, design, real estate, surveys, supervision 
and administration cost $281,313. Condition surveys, 
environmental studies and real estate in connection with Section 
111 of P.L. 90-483 were performed at a cost of $19,829. 
Existing project, with exception of widening bend in revetted 
entrance channel authorized by Act of September 3, 1954, 
was completed in 1957. For additional details on completion of 
existing project, see page 1460 of Annual Report for 1962. 
Total cost of existing project to end of FY was $23,077,390, of 
which $1,392,827 was for new work ($1,180,502 regular funds, 
$176,620 for previous project and $35,705 contributed funds), 
$21,182,111 for maintenance, and $502,452 for rehabilitation. 
26. THE INLAND ROUTE, MI 
Location. A series of interconnected lakes and streams 
stretching across northern tip of Lower Peninsula of Michigan, 
and extends from Conway near Lake Michigan to Cheboygan 
on Lake Huron; a distance of 35 miles. Crooked and 
Indian Rivers are connecting channels in the waterway. (See 
NOAA Nautical Chart 14886.) 
21-10

DETROIT, MI DISTRICT 
Existing project. Provides for a channel 30 feet wide and 5 
feet deep, with necessary widening at bends, through Crooked 
and Indian Rivers, and Crooked, Burt, and Mullett Lakes, and 
from Conway (west end of Crooked Lake) to navigation lock 
at Cheboygan; in Pickerel Channel from Pickerel Lake to 
Crooked Lake. It also provides for suitable jetties at head of 
Indian River. The addition of a lock and dam was approved by 
the Chief of Engineers on September 2, 1964, to correct a 
design deficiency. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None exist for commercial cargo-handling 
along the Crooked and Indian Rivers. Numerous small 
privately owned timber piers and wharves, some equipped with 
covered boat wells for serving and storing recreational craft, 
have been constructed. Landings maintained by hotel and 
resort operators are open to the public for transfer of passengers. 
Public docks are at Conway and Oden on Crooked Lake; 
the Village of Indian River, Topinabee, and Mullett Lake Village 
on Mullett Lake; and at Cheboygan. About 30 highways 
dead end at the water's edge, permitting public access for various 
marine activities. Dock facilities are considered adequate 
for existing traffic. 
Operations during fiscal year. Maintenance: The navigation 
lock was operated and maintained by the Village of Alanson at 
a cost of $46,721. In 1989, the lock was operated from April 17 
through April 28 from 8:00 a.m. to 4:00 p.m.; from April 29 
through May 12 from 9:00 a.m. to 5:00 p.m.; and, from May 
13 through September 30 it was open from 6:00 a.m. to 10:00 
p.m. Adjustments of $8,677 were made in cost to FY87 and 
FY88 navigation lock operations for repair services performed 
by the Village of Alanson. Condition surveys and miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $8,463. 
The existing project was completed in 1958. The lock and 
dam was completed in FY 1968. For additional details see page 
1382 of Annual Report for 1960. Total cost for existing project 
to end of FY was $3,733,794, of which $918,222 was for new 
work (includes $148,000 contributed funds) and $2,815,572 
for maintenance. 
27. KENOSHA HARBOR, WI 
Location. On west shore of Lake Michigan about 35 miles 
south of Milwaukee and about 54 miles north of Chicago. (See 
NOAA Nautical Chart 14904.) 
Previous project. See page 1390 of Annual Report for 1962. 
Existing project. For detailed description see page 1237, 
Annual Report for 1963. Estimated (1986) Federal cost is 
$455,000 exclusive of amounts expended on previous projects 
and $195,000 non-Federal which includes $155,000 local contribution. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves used for miscellaneous 
foreign overseas commodities and autos, and also several fishing 
wharves. While these facilities are considered generally 
adequate for existing commerce, more efficient use of existing 
terminals and utilization of available frontage for development 
of additional terminals should be made. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$47,197. Repairs to S. Revetment, Section E and Confined 
Disposal Facility, Sections 2 and 3 were performed by the 
Cranebarge MANITOWOC at a cost of $67,739. Engineering 
and design for repairs to Detached Breakwater - Section H to 
be performed by contract next FY continued at a cost of 
$96,699. Engineering and design for repair to confined disposal 
facility cost $4,231. Supervision and administration cost 
$16,968. 
Existing project is complete except for dredging 25-foot 
strips adjacent to the north and south piers which will be completed 
after rehabilitation of the piers. The north and south 
piers were completed in 1900 and the breakwater in 1909. The 
north pier is in excellent condition. The south pier and breakwater 
are in generally good condition. Total cost of the existing 
project to end of FY was $11,348,891, of which $11,321,233 
were regular funds and $27,658 Emergency Relief funds; 
$988,969 being for new work, $9,089,647 for maintenance, 
and $1,270,275 for rehabilitation. The new cost does not 
include $3,000 contributed funds. 
28. KEWAUNEE HARBOR, WI 
Location. On west shore of Lake Michigan, about 105 miles 
north of Milwaukee, WI, and about 78 miles from Green Bay, 
via Sturgeon Bay Canal. Harbor is at mouth of Kewaunee 
River. (See NOAA Nautical Chart 14908.) 
Previous projects. See page 1375 of Annual Report for 1962. 
Existing project. See Chicago District 1979 Annual Report, 
Table 30-C, p. 30-31. 
Costs of completed project are $603,021, Federal, and 
$9,000 non-Federal, exclusive of amount expended on previous 
projects. Uncompleted portion (estimated $200,000-July 
1965) of 1935 River and Harbor Act is considered inactive, and 
excluded from present cost estimate. The portion authorized 
by the 1960 River and Harbor Act was deauthorized in 1977. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car-ferry slips, a petroleum tank 
farm, a Corps of Engineers project office, and several fishing 
wharves. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$134,456. Repairs to navigation structures were performed by 
hired labor at a cost of $1,625. Repair to diked disposal area 
was performed by hired labor at a cost of $1,751. An adjustment 
of $199 was made to the FY 87 contract completed last 
FY for repair of the N. Stub Pier, Section A. A contract for 
Emergency Maintenance dredging was awarded and completed 
this FY at a cost of $136,624. Cost incurred this FY 
included revising the disposal area and removing 6,819 cubic 
yards of material. A contract for Maintenance dredging the 
entire channel was awarded and completed this FY at a cost of 
$180,977 removing 53,679 cubic yards of material. Engineering, 
design, surveys, supervision and administration were performed 
at a cost of $106,446. 
Active portion of existing project is complete. The north 
pier was completed in 1897 and the remaining portion is in generally 
good condition. Rehabilitation of the south pier was 
completed in June 1967. Construction of north breakwater 
and shore connection, except for a gap of 150 feet about 830 
21-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
feet from shoreward end, and removal of outer 706.5 linear 
feet of north pier was commenced in September 1935 and completed 
in June 1937. Removed 500 linear feet of north pier in 
April/May 1963 and widened and deepened the adjacent channel 
in 1965. Outer end of the north pier was struck and severely 
damaged by car ferry vessel in October 1973 and a 24-foot section 
at outlet end was subsequently removed, thus reducing the 
structure to a length of 626 feet. Dredging entrance channel in 
interior basin to existing project depth was commenced in 
April and completed in October 1938. Kewaunee River is navigable 
to about 6.5 miles above mouth for craft drawing not 
more than 4 feet. Total cost of existing project to end of FY was 
$9,556,321, of which $758,333 was for new work ($338,333 
regular and $420,000 Emergency Relief funds) $8,180,688 regular 
funds for maintenance and $617,300 regular funds for 
rehabilitation. 
29. KEWEENAW WATERWAY, MI 
Location. In Lake Superior across Keweenaw Peninsula in 
upper peninsula of Michigan. The west entrance is 169 miles 
east of Duluth, MN. (See NOAA Nautical Chart 14972.) 
Existing project. A navigable channel, minimum width 300 
feet, 25 miles long, partially natural and partially artificial, 
across Keweenaw Peninsula via Portage Lake. For details see 
page 1121 of Annual Report for 1963. (See Table 21-B for 
authorizing legislation.) 
The uncompleted portion of the project for navigation at 
Keweenaw Waterway, Houghton County, MI, authorized by 
the River and Harbor Act of Aug. 30, 1935, Public Law 409, 
73rd Congress, which consists of extending the lower entrance 
breakwater by 2,000 feet, including the necessary alteration or 
replacement of structures due to channel deepening, was 
deauthorized by the Water Resources Development Act of 
1986; Public Law 99-662-Nov. 17, 1986, 99th Congress, Title 
X.
Local cooperation. None required. 
Terminal facilities. Six coal docks, a petroleum dock, and 
several general merchandise and miscellaneous wharves, all 
privately owned. Facilities are considered adequate for existing 
commerce. Also present is a government constructed recreational 
area with facilities to include a picnic area and small boat 
landing range. 
Operations during the fiscal year. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$85,353. The Derrickbarge COLEMAN performed breakwater 
repair at a cost of $216,729. The contract for major 
repair of Section F, North Revetment is approximately 77%7 
complete at a cost this FY of $4,022,000. A contract was 
awarded for maintenance dredging in the amount of $653,300. 
No work was performed this FY. Engineering and design during 
construction for major repair of Section F, North Revetment 
cost $17,893. Engineering and design for maintenance 
dredging cost $35,824. Supervision and administration cost 
$186,939. An adjustment of $21,382 was made to the contract 
for construction of a confined disposal facility completed last 
FY. Preparation of O&M Manual, supervision and administration 
for Dike Disposal cost $8,767. 
Active portion of the project is complete. The flared revetment 
at the upper entry should be modified to restrict wave 
action from the stilling basin entrance. Total cost for existing 
project to end of FY was $26,992,296, of which $5,974,141 was 
for new work, and $21,018,155 for maintenance. 
30. LAC LA BELLE HARBOR, MI 
Location. On south shore of Lake Superior on eastern shore 
of Keweenaw Peninsula, 41 miles northeasterly from Portage 
entry to Keweenaw Waterway. Lac La Belle, Bete Grise Bay, 
and Mendota Ship Canal combine to form the harbor. (See 
NOAA Nautical Chart 14964.) 
Existing project. Provides for construction of two parallel 
piers at the entrance having lengths of 584 and 682 feet for 
north and south piers, respectively; for an entrance channel 
between the piers 50 feet wide and 12 feet deep, about 820 feet 
long with a flared approach; and for an inner canal 50 feet wide 
and 10 feet deep, about 730 feet long. For additional details see 
page 1039, Annual Report for 1964. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small, privately owned wharves 
are available in the harbor for use of small craft engaged in 
fishing and recreational activities. A state owned dock for 
small craft is located at northwest corner of Lac La Belle Bay. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$22,797. Engineering and design for maintenance dredging 
cost $6,273. Removal of obstructions was performed by the 
Cranebarge MARKUS at a cost of $43,930. 
The existing project was completed in 1960. Controlling 
depths are about 11 feet in the approach channel and 10 feet in 
the inner channel. Total cost for existing project to end of FY 
was $824,264, of which $269,270 was for new work and 
$554,994 for maintenance. 
31. LAKE ST. CLAIR, MI CHANNELS 
Location. Lake St. Clair, a section of Great Lakes connecting 
channels, is an expansive shallow basin having a vessel 
track length of about 15 miles from mouth of St. Clair River to 
head of Detroit River. (See NOAA Nautical Chart 14850.) 
Previous project. For details see page 2882, Annual Report 
for 1896; pages 1957-58, Annual Report for 1915; and page 
1539, Annual Report for 1938. 
Existing project. An improved channel through Lake St. 
Clair 800 feet wide, 27.5 feet deep, and about 14.5 miles long; 
extending from mouth of Southeast Bend cutoff channel at 
lower end of St. Clair River to head of Detroit River Channel. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. None 
Operations during fiscal year. Maintenance: Condition surveys, 
Hi-Fix surveys, support of Water Control Center, environmental 
studies, miscellaneous inspections and reports were 
performed by Government forces at a cost of $99,126. Maintenance 
of disposal area was performed by hired labor at a cost 
of $1,118. 
Total cost for existing project to end of FY was $20,361,921, 
of which $7,675,357 was for new work ($6,666,762 regular 
funds and $1,008,595 Public Works Funds) and $12,686,564 
for maintenance. 
21-12

DETROIT, MI DISTRICT 
32. LELAND HARBOR, MI 
Location. A light-draft harbor on eastern shore of Lake 
Michigan at mouth of Carp River, about 40 miles north of 
Frankfort, MI, and 40 miles southwest of Charlevoix, MI. (See 
NOAA Nautical Chart 14912.) 
Existing project. Provides for a harbor of refuge consisting 
of a breakwater about 1,200 feet long, a protected anchorage 
and maneuver area about 3 acres in extent and 10 feet deep, a 
12-foot deep flared approach channel decreasing in width to 90 
feet, an existing south pier 440 feet long, a 35-foot long cellular 
extension to south pier, an entrance channel 6 feet deep and 40 
feet wide extending to mouth of Carp River, and for elimination 
of existing north pier. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned wharves on each side of 
river below the dam which is 400 feet above the river mouth. 
These wharves serve the local fishing interests and recreational 
craft. Public facilities are operated by the State and local agencies. 
All available dockage space is utilized. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, and miscellaneous inspections 
and reports were performed by Government forces at a cost of 
$21,344. A contract was awarded and completed for maintenance 
dredging removing approximately 16,417 cubic yards of 
shoal material at a cost of $86,268. Engineering, design, surveys, 
supervision and administration cost $20,867. 
The existing project was completed in 1932 except for the 
1962 authorization which was completed in 1967. Total cost for 
existing project to end of FY was $2,977,575, of which 
$1,027,089 was for new work, $1,879,808 for maintenance and 
$70,678 for rehabilitation. 
33. LEXINGTON HARBOR, MI 
Location. On southwest shore of Lake Huron, 20 miles 
north of Port Huron, MI. (See NOAA Nautical Chart 14862.) 
Existing project. Provides for two offshore breakwaters 
opening to the southeast and totaling about 2,400 feet long 
with provisions for recreational fishing on the main breakwater; 
an anchorage and maneuver area of about 5 acres, 8 feet 
deep; and a flared approach channel 10 feet deep, decreasing 
to 160 feet in width through the breakwaters. Project also provides 
for recreational fishing facilities. Estimated (1979) Federal 
cost for new work is $1,647,306 excluding $1,088,888 to be 
contributed by local interests. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Assurances of local cooperation were 
furnished by Michigan Department of Natural Resources to 
the Secretary of the Army. The cash contribution was 
$1,088,888. 
Terminal facilities. An existing public fishing pier of open 
pile construction is not adequate for existing and prospective 
commerce. Complete boating facilities are planned by State 
and local agencies in connection with the harbor construction. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$18,783. Safety maintenance cost $1,172. Monitoring and 
environmental studies under Section 111 mitigation were performed 
at a cost of $20,450. The Beach nourishment contract 
awarded last FY was completed at a cost this FY of $347,174. 
Engineering, design, surveys, supervision and administration 
under Section 11l cost $8,193. 
The existing project was completed during FY 1977. Total 
cost for existing project to end of FY was $4,694,020, of which 
$3,107,192 (includes $1,088,888 contributed funds) was for 
new work and $1,586,828 for maintenance. 
34. LITTLE LAKE HARBOR, MI 
Location. On south shore of Lake Superior 21 miles west of 
Whitefish Point and 30 miles east of Grand Marais, MI. (See 
NOAA Nautical Chart 14962.) 
Existing project. Provides for a small-craft harbor of refuge 
by dredging an entrance channel 12 feet deep from Lake Superior 
into Little Lake, suitably protected by breakwaters and 
revetments. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Only terminal facility at project site consists 
of a public dock built by State of Michigan for light-draft 
craft. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, and miscellaneous inspections 
and reports were performed by Government forces at a cost of 
$38,706. Design deficiency study continued at a cost of 
$16,929. A maintenance dredging contract was awarded and 
completed at a cost of $88,210, removing approximately 
19,812 cubic yards of shoal material. Engineering, design, and 
supervision and administration cost $19,257. 
This project is considered complete; however, because of 
shifting sand, the harbor entrance shoals rapidly with the result 
that full project depth is not usually available. An analysis for 
the Deficiency Report was submitted to North Central Division 
in March 1978 and approved. The design deficiency letter 
report and Environmental Assessment, drafted in FY 87, were 
reviewed by NCD. A biological assessment on the Piping 
Plover was prepared, and we are presently awaiting comments 
from the Fish and Wildlife Service. Total cost for existing project 
to end of FY was $3,911,768, of which $600,478 was for 
new work and $3,311,290 for maintenance. 
35. LUDINGTON HARBOR, MI 
Location. On east shore of Lake Michigan, 156 miles northeasterly 
from Chicago, IL, and 67 miles northerly from Grand 
Haven, MI. (See NOAA Nautical Chart 14937.) 
Previous project. For details see page 1951 of Annual 
Report for 1915, page 1491 of Annual Report for 1938, and 
page 1307 of Annual Report for 1963. 
Existing project. Provides for an exterior basin in Lake 
Michigan protected by north and south breakwaters, north 
breakwater is 1,800 feet long and south breakwater 1,700 feet 
long, 550 feet apart at outer ends, diverging at an angle of 90 
degrees, with shore connections, 1,103 and 2,004 feet long, 
respectively; for dredging exterior basin to 18 feet deep with a 
maximum width of 1,500 feet; for a channel with a depth of 29 
feet from deep water in Lake Michigan decreasing to 27 feet at 
the west end of the north pier, over a maximum width of 600 
feet; thence a channel with a depth of 27 feet, over a minimum 
width of 230 feet with necessary widening at Pere Marquette 
21-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Lake; and for inner piers and revetments, 1,649 feet long on 
north and sufficiently long on the south for turn at Pere Marquette 
Lake. The estimated (1977) Federal cost for new work is 
$8,250,000. Estimated total costs for local interests is 
$147,000. (See Table 21-B for authorizing legislation.) 
Local cooperation. Has been complied with. 
Terminal facilities. In addition to main terminal of Chesapeake 
& Ohio Railway Co., consisting of three car ferry slips, a 
wharf, and warehouses, there are several wharves which handle 
coal, limestone, and miscellaneous commodities. Facilities 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, and miscellaneous inspections 
and reports were performed by hired labor at a cost of $62,606. 
An adjustment of $40,426 was made in cost to the repair of the 
North Breakwater, Sections A, B, and C, and South Breakwater 
performed last FY using the Cranebarge MANITOWOC. 
Maintenance of safety features was performed at a cost 
of $2,426. A contract was awarded in the amount of $388,800, 
for maintenance dredging. No work was performed this FY. 
Engineering, design, supervision and administration cost 
$26,725. Under the Section 111 program, surveys and monitoring, 
cost $2,769. 
Existing project was completed in 1918. For additional 
details on completion of existing project see page 1469 of 
Annual Report for 1962. Total cost for existing project to end 
of FY was $20,446,484, of which $8,532,202 was for new 
work, $11,556,369 for maintenance, and $357,913 for rehabilitation. 
36. MACKINAC ISLAND HARBOR, MI 
Location. On the southeast side of Mackinac Island which 
lies just east of the Straits of Mackinac, the connecting waterway 
between Lakes Michigan and Huron. (See NOAA Nautical 
Chart 14881.) 
Existing project. Provides for the construction of two 
breakwaters 910 and 950 feet long from Mission and Biddle 
Points, respectively. The breakwaters are of rubblemound construction. 
Estimated (1969) Federal cost for new work is 
$230,000, excluding $105,000 to be contributed by local interest. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Consists of private piers used by small 
commercial vessels and light-draft passenger ferry boats. 
Facilities for recreational craft are provided by the State dock 
which is open to all on equal terms. These facilities satisfy current 
traffic requirements, however, they are usually hard 
pressed during the annual Chicago to Mackinac-Port Huron to 
Mackinac sailboat races. 
Operations during fiscal year. Maintenance: Miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $1,652. Close-out of the contract completed last FY 
for repair of Rubblemound, East Breakwater cost $622. 
The existing project was completed in 1967. Total cost for 
existing project to end of FY was $2,146,133, of which 
$334,089 (includes $105,004 contributed funds) was for new 
work and $1,812,044 for maintenance. 
37. MANISTEE HARBOR, MI 
Location. On east shore of Lake Michigan, 179 miles northeasterly 
from Chicago, IL, and 26 miles northerly from 
Ludington, MI (See NOAA Nautical Chart 14938.) 
Previous project. For details see page 1952 of Annual 
Report for 1915, and page 1493 of Annual Report for 1938. 
Existing project. An entrance channel in Lake Michigan 
protected by a breakwater, piers, and revetment; a channel in 
Manistee River to Manistee Lake; and Federal participation in 
cost of replacing Maple Street Bridge. Project depths are 25 
feet in entrance channel and 23 feet in river channel. For additional 
details see page 1470 of Annual Report for 1962. (See 
Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Installations are on both sides of river 
and on Manistee Lake. Commerce handled includes coal, 
sand, salt, and general cargo. In addition, there is a Government 
wharf and a State and City owned recreational craft pier 
which is open to the public. These facilities satisfy current commerce 
requirements. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, miscellaneous inspections and reports were 
performed by hired labor at a cost of $38,491. Repairs to the 
North Breakwater, Sections A and S and the South Breakwater, 
Sections B and B-1, were performed by the U.S. Cranebarge 
MANITOWOC at a cost of $91,893. Repairs to safety 
features cost $40. A contract was awarded and completed for 
maintenance dredging at a cost of $262,919 removing approximately 
72,292 cubic yards of material. Engineering and design 
for repair of the South Breakwater Sections M, N, O, 0-1 was 
completed at a cost of $3,509. Engineering, design, surveys, 
real estate and supervision and administration cost $61,350. 
Existing project was completed in August 1967. For additional 
details on completion of existing project see page 1470 of 
Annual Report for 1962. Total cost for existing project to end 
of FY was $10,753,744, of which $2,696,522 was for new 
work, $6,683,058 for maintenance, and $1,374,164 for rehabilitation. 
38. MANISTIQUE HARBOR, MI 
Location. On the north shore of Lake Michigan, 135 miles 
northeasterly from Green Bay Harbor, WI, and 220 miles 
northerly from Milwaukee, WI. (See NOAA Nautical Chart 
14908.) 
Previous project. For details see page 1933 of Annual 
Report for 1915, and page 1422 of Annual Report for 1938. 
Existing project. A breakwater protected entrance channel 
in Lake Michigan, a channel in Manistique River, and a pier at 
river mouth. Project depths are 19 feet in outer portion of 
entrance channel, 18 feet in inner portion of entrance channel, 
and 18 feet in river channel. For additional details see page 
1451 of Annual Report for 1962. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A car ferry slip, two coal and building 
material wharves, two fishing wharves, and numerous lumberyard 
slips. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, and miscellaneous inspections 
and reports were performed at a cost of $18,197. Repairs to 
East Breakwater, Sections A and B and West Breakwater, Sections 
A, B, C, and D were performed by the U.S. Cranebarge 
MARKUS at a cost of $145,960. Repairs to safety features cost 
$1,006. Supervision and administration cost $3,803. 
21-14

DETROIT, MI DISTRICT 
Total cost for existing project to end of FY was $3,694,883, 
of which $1,299,355 was for new work, $2,079,195 for maintenance 
and $316,333 for rehabilitation. 
39. MANITOWOC HARBOR, WI 
Location. On west shore of Lake Michigan about 79 miles 
north of Milwaukee and about 106 miles from Green Bay via 
Sturgeon Bay Canal. (See NOAA Nautical Chart 14922.) 
Previous projects. See page 1379 of Annual Report for 1962. 
Existing project. The total estimated (Oct. 1981) project cost 
is $3,080,000; the Federal Cost is $1,085,000 and non-Federal 
cost is $1,995,000, which is a cash contribution. See Chicago 
District Annual Report for 1979, Table 30-C. 
For detailed description see page 1228 of Annual Report for 
1963. Estimated costs (1970) of new work for 1968 modification 
are $81,000 Federal and $30,000 non-Federal which 
includes a cash contribution of $18,000. Work on the 1968 
modification was postponed until 1982. The portion authorized 
by the 1962 River and Harbor Act is inactive and estimated 
(1970) at $1,150,000 Federal, and $105,000 non-Federal. 
(See Table 21-B for authorizing legislation.) 
Construction of a small boat harbor within the existing harbor 
was authorized by the Chief of Engineers, June 26, 1979, 
and 720-foot channel extension reaffirmed in July 1982, under 
authority of Section 107, 1960 River and Harbor Act, as 
amended. 
Local cooperation. Fully complied with for completed modifications. 
For 1968 modification local interests must make an 
annual cash contribution equivalent to 50�%/ of the annual 
costs associated with construction and maintenance of the 
channel extension until such time that a second user utilizes the 
channel extension. Such a contribution is presently estimated 
at $14,200; provide without cost to the United States all lands, 
easements, and rights-of-way required for construction and 
subsequent maintenance, including suitable areas determined 
by the Chief of Engineers to be required in the general public 
interest for initial and subsequent disposal of dredged materials, 
and the necessary retaining dikes, bulkheads, and embankments 
therefor or the costs of such retaining works; hold and 
save the United States free from damages due to the construction 
works and subsequent use, operation, and maintenance of 
the project, not including damages due to the fault or negligence 
of the United States or its contractors; provide and maintain 
without cost to the United States adequate berthing areas 
at the docks adjacent to the improvement; accomplish at no 
cost to the United States all relocations and alterations of utilities 
necessary for the project; assume full responsibility for all 
project first costs in excess of the Federal cost limitation of 
$2,000,000; and comply with the Uniform Relocation Assistance 
and Real Property Acquisition Policies Act of 1970. 
Terminal facilities. Three car-ferry slips, a grain elevator, 
one shipbuilding yard, and three other wharves used for handling 
coal, building materials, cement, and miscellaneous commodities. 
While these facilities are considered adequate for 
existing commerce, it is believed the city should provide a suitable 
wharf with warehouse and railway connection open to the 
general public. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$40,546. Repairs to confined disposal facility - Sections J and 
K and N. Breakwater Section C were performed by the Cranebarge 
MANITOWOC at a cost of $76,624. Supervision and 
administration were performed at a cost of $17,328. 
Existing project is completed except for the 1962 and 1968 
modifications. The 1962 modification is inactive. Work on the 
1968 modification was essentially completed in FY 83. The 
Federal modification, adopted July 15, 1985, included the 
expansion of the new entrance channel to the Section 107 project 
and extension of the rubblemound breakwater. The breakwater, 
completed in 1910, is in generally fair condition. Dredging 
a channel through the outer basin to existing project depth 
and removal of a portion of old north stub pier at the river 
entrance were completed in December 1937. Dredging river 
channel was completed in July 1942. Cost for existing project 
to end of FY was $12,595,054, of which $3,960,044 was for 
new work (includes $1,911,130 contributed funds) and 
$8,635,010 for maintenance. 
40. MARQUETTE HARBOR, MI 
Location. In Marquette Bay on south shore of Lake Superior, 
160 miles west of Sault Ste. Marie, MI, and 265 miles east 
from Duluth, MN. (See NOAA Nautical Chart 14970.) 
Existing project. Provides for a breakwater, and a harbor 
basin 26.5 feet deep, giving a protected area of 350 acres. Project 
was modified in 1960 to provide a 27-foot depth in harbor 
area. (See Table 21-B for authorizing legislation.) 
Local cooperation. None required for earlier authorizations. 
Fully complied with for the 1960 Act. 
Terminal facilities. One ore dock, unused at present; two 
coal docks; one petroleum dock; and three other unused 
docks. There are also several small fish wharves without railroad 
connections. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys were performed by Government forces at a 
cost of $7,810. 
Total cost for existing project to end of FY was $3,756,506, 
of which $1,282,893 was for new work, $2,007,856 for maintenance 
and $465,757 for rehabilitation. 
41. MENOMINEE HARBOR AND RIVER, 
MI AND WI 
Location. On Lake Michigan at the mouth of the Menominee 
River on the western shore of Green Bay, 16 miles northwest 
of the mouth of Sturgeon Bay, and 49 miles northeast of 
Green Bay Harbor, about 155 miles from Milwaukee via Sturgeon 
Bay Canal. The river forms the boundary between the 
commercial harbors at Marinette, WI, and Menominee, MI. 
(See NOAA Nautical Chart 14917.) 
Previous projects. See page 1361 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report 1979, 
Table 30-C, page 30-26. 
For detailed description see page 1214, Annual Report for 
1963. The portion authorized by 1960 River and Harbor Act is 
inactive and estimated (1964) at $442,000 Federal, and 
$105,000 non-Federal. Costs of completed new work exclusive 
of inactive work and amount expended on previous projects 
are $221,053 Federal and $50,762 non-Federal, which includes 
a cash contribution of $36,762. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with for completed 
work. 
21-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Terminal facilities. There are 9 wharves for handling coal, 
limestone, pulp and miscellaneous commodities. City of Marinette, 
WI, provided a public wharf. Facilities are considered 
fairly adequate for existing commerce, except that there is need 
for a public wharf owned by City of Menominee, with warehouse 
and railway connection. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$33,027. Repairs to S. Pier Sections A, B, C, D, E, F were performed 
by the Cranebarge MANITOWOC at a cost of 
$60,018. Supervision and inspection cost $11,831. Engineering 
and design for site selection of a confined disposal facility cost 
$10,245. 
The project is effect prior to the modification of March 2, 
1945, was completed in 1938. No additional work was necessary 
under the modification of March 2, 1945, to provide a 
depth of 12 feet in the extension of the channel to the vicinity of 
the Marinette Yacht Club, as project depth or more was available. 
The entrance piers were completed in 1884, were rehabilitated 
(1954-1964) and are in excellent condition. Dredging of 
the channel below the Marinette municipal wharf, together 
with enlarging the turning basin to existing project depth, was 
commenced in May 1938. Modification of the project authorized 
by the 1960 River and Harbor Act is inactive. Construction 
for the 1967 modifications was started August 17, 1968, 
and completed in October 1968. The cost of the existing project 
to end of FY was $4,584,840, of which $570,238 was for 
new work (includes $36,762 contributed funds), $2,662,750 for 
maintenance and $1,351,852 for rehabilitation. 
42. MILWAUKEE HARBOR, WI 
Location. On west shore of Lake Michigan about 85 miles 
north of Chicago, IL, and about 83 miles west of Grand 
Haven, MI. (See NOAA Nautical Chart 14924.) 
Previous projects. See page 1385 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 
1979, Table 30-C, page 30-26. For detailed description see page 
1232 of Annual Report for 1963. 
Completed new work costs are $6,937,804 Federal and 
$478,000 non-Federal, exclusive of amount expended on previous 
projects. The uncompleted portion authorized by the 
1935 River and Harbor Act was placed in the inactive category 
in June 1973. Estimated costs are $119,000 (July 1972) Federal 
and $1,170,000 (July 1972) non-Federal for this portion. 
Uncompleted portion 1945 River and Harbor Act was 
deauthorized in 1977. (See Table 21-B for authorizing legislation.) 
Local cooperation. Complied with for Acts of March 2, 
1945, October 23, 1962, and July 14, 1960, except inactive portion 
of 1945 Act. Act of August 30, 1935, provided that original 
dredging of outer harbor area be done by city of Milwaukee 
and city of Milwaukee be reimbursed at actual cost but not to 
exceed 10 cents per cubic yard, place measurement, for original 
dredging done subsequent to authorization of work by Congress. 
Agreement covering dredging was executed by Secretary 
of War, February 23, 1934, after this work was originally 
authorized as part of public works program. City was reimbursed 
for 10 percent of dredging. 
Terminal facilities. Four car-ferry slips, and 57 other 
wharves, private and municipal, used for handling coal, grain, 
building materials, cement, petroleum products, and miscellaneous 
commodities. As facilities in inner harbor were inadequate 
for existing commerce, Milwaukee Harbor Commission 
has constructed nine docks in the outer harbor for handling 
general cargo. 
Operations during fiscal year. Rehabilitation: An adjustment 
of $10,002 was made to the FY 85 contract for major 
rehabilitation of the North Pier and North Breakwater completed 
last FY. An adjustment of -$6,398 was made to the FY 
87 contract for major rehabilitation Phase II of the North 
Breakwater completed last FY. The contract awarded last FY 
for major rehabilitation Phase III of the North Breakwater 
was completed this FY at a cost of $781,987. Engineering, 
design, supervision, and administration was performed at a 
cost of $101,759. Engineering and design for construction of a 
walkway on the outer end of the N. Breakwater to be performed 
by contract next FY cost $14,516. Maintenance: Condition 
surveys, environmental studies, miscellaneous inspections 
and reports were performed by Government forces at a 
cost of $189,773. Repairs to diked disposal facility Sections B, 
D, G, and F were performed by the Cranebarge MANITOWOC 
at a cost of $153,079. Engineering and design for CDF 
expansion cost $32,296. Engineering and design for emergency 
maintenance dredging of the Kinnickinnic River to be performed 
by contract next FY cost $20,011. Supervision and 
administration cost $31,640. 
Existing project is complete except for inactive portions. 
The 1962 modification was completed in July 1967. North 
breakwater and shore connection, 9,954 feet long, was completed 
in August 1925. North pier was completed in 1905 and 
construction of south pier was completed in November 1910. 
Construction of south breakwater and shore connection was 
completed in October 1929. Before modification of August 30, 
1935, City of Milwaukee also dredged most of the area in the 
outer harbor south of inner entrance piers and lakeward of 
pierhead line to more than 21 feet below datum without cost to 
the United States. City of Milwaukee also dredged a portion of 
the area of the outer harbor north of inner entrance piers to 
provide an approach channel to the passenger and auto pier 
opposite East Claybourn Street. Work on the 1945 modification 
was completed in August 1957, except for inactive portion 
which consists of dredging the Milwaukee River from Buffalo 
Street to upper limit of the project at Humboldt Avenue. Total 
cost for existing project to end of FY was $55,643,135, of 
which $8,231,024 was for new work, $34,721,465 for maintenance, 
and $12,690,646 for rehabilitation. 
43. MONROE HARBOR, MI 
Location. On lower reach of River Raisin, which empties 
into Lake Erie and is 36 miles south of Detroit, MI. (See 
NOAA Nautical Chart 14830.) 
Existing project. Provides for a channel in Lake Erie and 
River Raisin to City of Monroe, for a turning basin, and for 
riprapping protecting dikes at river mouth. Project depths are 
21 feet to turning basin, 18 feet in turning basin, and 9 feet to 
upstream end of project. For additional details see page 1490 
of Annual Report for 1962. Project feature for riprapping protecting 
dikes is considered inactive. Estimated cost of this feature 
(1954) is $90,000. (See Table 21-B for authorizing legislation.) 
21-16

DETROIT, MI DISTRICT 
The Water Resources Development Act (W.R.D.A.) of 1986 
authorized modifications to deepen the River Raisin portion of 
the existing 200 foot navigation channel from 21 to 27 feet 
between the existing turning basin and the river's mouth; 
deepen the lake channel from 21 to 28 feet, and widen the channel 
from 200 to 500 feet, for a distance of approximately 
47,000 feet from the river's mouth to the Maumee Bay 
Entrance Channel; dredge a new turning basin 24 feet deep, 
with a diameter of at least 1,600 feet, at the river's mouth; and 
construct a 190 acre confined disposal area in Plum Creek Bay 
behind which would enable the creation of a 700 acre marsh. 
Estimated total cost (Oct. 88) is $150,200,000; $59,000,000 
Federal and $91,200,000 non-Federal, which includes a cash 
contribution of $19,650,000. 
Local cooperation. Fully complied with for completed portion 
of project. Local cooperation items for the newly authorized 
project in the W.R.D.A. for 1986 (P.L. 99-662), are as 
described in the Rivers and Harbors Committee Document 22, 
71st Congress, 1st Session; R & H Comm. Doc. 12, 72d Congress, 
1st Session, and 45, 75th Congress, 1st Session, and also 
includes, as a result of P.L. 99-662, construction cost sharing as 
follows: 
a. Contribute in cash 25 percent of the total cost of construction 
of general navigation facilities, exclusive of aids to navigation, 
a contribution presently estimated at $19,650,000. The 
estimated cash contribution of $19,650,000 to be paid in lump 
sum prior to initiation of construction, or in annual installments 
during the construction period at a rate proportionate to 
the proposed or scheduled expenditure of Federal funds as 
required by the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final apportionment 
of cost to be made after actual costs have been determined; 
and 
b. Repay, with interest, over a period of up to 30 years following 
project completion, 10 percent of the total cost of construction 
of general navigation facilities, an amount presently 
estimated at $7,860,000. The Secretary of the Army may count 
against all or part of the 10 percent repayment, the amount of 
the local contribution for lands, easements, rights-of-way, 
dredged/demolition material disposal sites and relocations. In 
no case are these costs to count against the cash payment during 
construction, and in no case would the amount waived 
exceed 10 percent of project cost. 
c. The confined dike area construction is a non-Federal 
responsibility and is estimated to cost $70,156,000. 
Terminal facilities. Several privately owned docks and a 
municipal terminal. Port of Monroe Authority built a steel and 
concrete wharf on southeast side of turning basin for commercial 
use. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$90,146. Maintenance of the disposal facility was performed 
by hired labor at a cost of $12,153. The maintenance dredging 
contract awarded last FY was completed with 126,671 cubic 
yards removed this FY at a cost of $598,419. An adjustment of 
-$39,714 was made to the contract for repair of confined disposal 
facility Cell #1 completed last FY. Engineering, design, 
surveys, supervision and administration cost $38,858. 
Total cost for existing project to end of FY was $55,839,721, 
of which $987,340 was for new work (includes $300,000 contributed 
by the Port Commission of Monroe) and $54,852,381 
for maintenance (includes $166,667 contributed funds, 
$125,000 by Consolidated Paper Company and $41,667 by 
River Raisin Company). 
44. MUSKEGON HARBOR, MI 
Location. On east shore of Lake Michigan, 114 miles northeasterly 
from Chicago, IL, and 80 miles easterly from Milwaukee, 
WI (See NOAA Nautical Chart 14934.) 
Previous project. For details see page 1950 of Annual 
Report for 1915; page 1399, Annual Report for 1924; and page 
1484, Annual Report for 1938. 
Existing project. A breakwater protected outer basin in 
Lake Michigan and an entrance channel from Lake Michigan 
to Muskegon Lake protected by piers and revetments. Project 
depths vary from 29 feet in the lakeward portion of the outer 
basin to 27 feet in the channel between the inner piers to 
Muskegon Lake. For additional details see page 1303 of 
Annual Report for 1963. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned wharves primarily 
for commercial use. Details on actual port and harbor facilities 
are in Port Series, No. 48 (revised 1981) prepared and published 
by the Water Resources Support Center. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Rehabilitation: An adjustment 
of $804 was made to the cost of engineering and design 
for major rehabilitation of the North and South Revetment. 
Maintenance: Condition and structure surveys, environmental 
studies, miscellaneous inspections and reports were performed 
by Government forces at a cost of $86,940. Repair to safety 
features by hired labor cost $13,621. Repairs to South Pier, 
Sections N, O, P and North Breakwater, Sections A & B were 
performed by the U.S. Cranebarge MANITOWOC at a cost of 
$128,236. An adjustment of -$10,517 and 25,785 cubic yards 
was made to the maintenance dredging contract completed last 
FY. Engineering, design, surveys, real estate, and supervision 
and administration cost $23,916. Environmental monitoring 
was performed in conjunction with the authorized Section 111 
project at a cost of $25,747. The contract awarded last FY for 
Beach Nourishment was completed at a cost of $293,755. Real 
estate, supervision and administration cost $18,470. 
Existing project, including latest project modification, was 
completed in 1965. For additional details on completion of 
existing project see page 1465 of Annual Report for 1962. Total 
cost for existing project to end of FY was $25,453,749, of 
which $3,017,110 was for new work, $8,612,339 for maintenance, 
and $13,824,300 for rehabilitation. 
45. NEW BUFFALO HARBOR, MI 
Location. At mouth of Galien River on southeast shore of 
Lake Michigan in Berrien County, about 45 miles easterly from 
Chicago, IL. (See NOAA Nautical Chart 14905.) 
Existing project. Provides for an entrance channel 10 feet 
deep by 80 feet wide and 850 feet long, to mouth of Galien 
River; new north and south breakwaters 1,305 and 740 feet 
long, respectively, and deepening inner channel to Galien River 
to 8 feet and 80 feet wide and 1,250 feet long. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
21-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Terminal facilities. One village owned boat ramp and three 
privately operated marinas, and a private boat club facility. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, and miscellaneous inspections 
and reports were performed at a cost of $59,488. The U.S. 
Cranebarge MANITOWOC performed repairs to North 
Breakwater, Section A and South Breakwater, Section B at a 
cost of $48,868. Repairs to safety features cost $38. An adjustment 
of $71 was made to the contract completed last FY for 
beach nourishment. Supervision and administration cost 
$12,710. 
Existing project is complete. Total cost for existing project 
to end of FY was $5,961,802, of which $2,472,183 was for new 
work (includes $1,186,467 contributed funds) and $3,489,619 
for maintenance. 
46. ONTONAGON HARBOR, MI 
Location. On south shore of Lake Superior. It consists of 
improvement of mouth of Ontonagon River. (See NOAA Nautical 
Chart 14965.) 
Previous project. For details see page 1931 of Annual 
Report for 1915, and page 1406 of Annual Report for 1938. 
Existing project. Provides for approach channel 16 feet 
deep, a channel between piers with 17 and 15-foot depths, an 
inner basin 12 feet deep, and maintenance of channels, basin, 
and entrance piers. Completed project cost $19,619. See page 
1100 of Annual Report for 1966 for details. A modification 
authorized by 1962 River and Harbor Act provides for increasing 
depths of channels, construction of an inner basin and a 
sedimentation basin. (See Table 21-B for authorizing legislation.) 
The turning basin feature of the project for navigation at 
Ontonagon Harbor, Ontonagon County, MI, authorized by 
the River and Harbor Act of 1962, was deauthorized by the 
Water Resources Development Act of 1986; Public Law 99-662 
- Nov. 17, 1986, 99th Congress, Title X. 
Local cooperation. None required. 
Terminal facilities. There are no publicly owned wharves. 
There are three coal wharves, an oil receiving facility, and a few 
small fish wharves. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. New Work: The Definite Project 
Report for Ontonagon, terminated due to lack of local 
sponsorship, cost $18,525 in FY 89. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed 
by Government forces at a cost of $21,568. Repairs to 
the East and West Breakwaters were performed by the Derrickbarge 
COLEMAN at a cost of $294,389. A contract for maintenance 
dredging was awarded and completed this FY at a cost 
of $261,164 removing 39,005 cubic yards of material. Engineering 
and design for Repair to the West Revetment Section E 
to be performed by contract next FY cost $68,019. Engineering 
and design for maintenance dredging to be performed by contract 
next FY cost $13,044. Other engineering, design, surveys, 
supervision and administration cost $43,805. 
All work authorized under previous Acts was completed in 
1938. Total cost for existing project to end of FY was 
$10,327,657, of which $952,170 was for new work and 
$9,375,487 for maintenance. 
47. PENTWATER HARBOR, MI 
Location. On east shore of Lake Michigan, 146 miles northeasterly 
from Chicago, IL, and 14 miles southerly from 
Ludington, MI. (See NOAA Nautical Chart 14907.) 
Existing project. Provides for widening old entrance channel 
to 150 feet between parallel piers and revetments, channel 
to extend from Lake Michigan to Pentwater Lake, with a 
depth of 16 feet. Piers and revetments are built of stonefilled 
timber cribs and piling and capped with concrete. The 200-foot 
extension to south pier portion of project is considered inactive. 
Estimated cost (1954) of this portion is $65,100. (See Table 
21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small privately owned wharves 
on west end of Pentwater Lake. The City and Michigan Waterways 
Commission jointly constructed a dock on northwest side 
of Pentwater Lake for public use. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, and miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $31,673. Repairs to North Pier Sections B, B-1, C, 
C-1, G and H, and South Revetment Sections F and J were performed 
by hired labor using the U.S. Cranebarge MANITOWOC 
at a cost of $77,649. Repairs to safety features cost $29. 
A maintenance dredging contract was awarded and completed 
removing approximately 19,100 cubic yards of shoal material 
at a cost of $106,700. Engineering and design for repairs to 
South Revetment and South Pier Sections, A, M, M-1 and N 
was performed at a cost of $27,790. Engineering, design, surveys, 
real estate, and supervision and administration cost 
$24,920. 
Existing project was completed in 1959 except for a 200-foot 
extension to the south pier which is not considered necessary 
under present conditions. For additional details see page 1468 
of Annual Report for 1962. Total cost for existing project to 
end of FY was $3,974,263, of which $179,899 was for new 
work, and $3,794,364 for maintenance. 
48. POINTE LOOKOUT HARBOR (AU GRES 
RIVER), MI 
Location. At Au Gres River on westerly shore of Lake 
Huron at entrance to Saginaw Bay, about 17 miles northeast of 
mouth of Saginaw River. (See NOAA Nautical Chart 14863.) 
Existing project. Provides for construction of a small boat 
harbor having a 12-foot deep, 100-foot wide, 2,800-foot long 
outer entrance channel; a 5,600-foot long, 100-foot wide inner 
entrance channel having a 10-foot depth; an 8,270-foot long, 
6-foot deep river channel ending just downstream from U.S. 
23 highway bridge and having a width of 60 feet; a 4,000-foot 
long north breakwater and a 3,800-foot long south breakwater. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small boat marina facilities are under 
construction by the State of Michigan. 
Operations during fiscal year. Maintenance: Condition surveys 
and miscellaneous inspections and reports were performed 
by Government forces at a cost of $26,855. Minor 
structure repairs were performed by hired labor at a cost of 
$8,414. An adjustment of -$3,688 and -546 cubic yards was 
made to the maintenance dredging contract completed last FY. 
Engineering, design, and supervision and administration cost 
$8,661. 
21-18

DETROIT, MI DISTRICT 
Existing project was completed in 1974. Total cost for existing 
project to end of FY was $6,042,602, of which $2,642,584 
was for new work and $3,400,018 for maintenance. 
49. PORTAGE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan about 186 miles 
northeasterly from Chicago, IL, and about 37 miles northerly 
from Ludington, MI. (See NOAA Nautical Chart 14939.) 
Existing project. Provides for a harbor of refuge with an 
entrance channel from Lake Michigan to Portage Lake protected 
by piers and revetments. Project depth is 18 feet. For 
additional details see page 1297 of Annual Report for 1958. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. There are landing places and marinas at 
inner end of Portage Lake. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, and miscellaneous inspections and reports 
were performed by Government forces at a cost of $19,113. 
Repairs to North and South Revetment, Sections D, F, G, H, 
and J, North and South Pier, Sections A, B, and F were performed 
by the U.S. MANITOWOC at a cost of $163,940. A 
contract for maintenance dredging was awarded in the amount 
of $82,500. No work was performed this FY. Engineering, 
design, real estate, surveys, and supervision and administration 
cost $43,233. 
Existing project was substantially completed in 1912. For 
additional details on completion of existing project see page 
1298 of Annual Report for 1958. The structures are generally 
in fair condition. Total cost for existing project to end of FY 
was $2,053,892, of which $256,129 was for new work and 
$1,797,763 for maintenance. 
50. PORT AUSTIN HARBOR, MI 
Location. On west shore of Lake Huron at extreme southeastern 
limit of Saginaw Bay, and 29 miles south of Au Sable 
River (Oscoda). (See NOAA Nautical Chart 14863.) 
Existing project. A harbor of refuge at the mouth of Bird 
Creek, consisting of a harbor basin dredged to a depth of 10 
feet protected by a breakwater structure, and for dredging an 
entrance channel to the harbor basin to a depth of 12 feet. (See 
Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of docks near mouth of Bird 
Creek and a State-owned dock inside breakwater. Facilities 
accommodate recreational craft and are considered adequate 
for existing traffic. 
Operations during fiscal year. New Work: A contract was 
awarded this FY in the amount of $1,673,300 for additional 
breakwater. The contract is approximately 65% complete at a 
cost of $1,078,603. Engineering and design, supervision and 
administration cost $193,583. Maintenance: Condition surveys, 
and miscellaneous inspections and reports were performed 
by Government forces at a cost of $14,682. The contract 
awarded last FY for repair of the Breakwater Cell Cap 
was completed at a cost of $96,573. Engineering and design 
during construction cost $323. Supervision and administration 
cost $28,823. 
Total cost for existing project to end of FY was $4,439,025, 
of which $2,538,469 was for new work (includes $172,100 contributed 
funds) and $1,900,556 for maintenance. 
51. PORT SANILAC HARBOR, MI 
Location. On southwest shore of Lake Huron, 30 miles 
north of Port Huron, MI. (See NOAA Nautical Chart 14862.) 
Existing project. Provides for a harbor of refuge protected 
by breakwater structures extending to 12-foot depth contour in 
lake; for dredging a harbor basin 10 feet deep; for dredging an 
entrance channel 12 feet deep; a 70-foot extension of the south 
breakwater; a 300-foot arm added to the north breakwater; 
and riprap placed at the lakeward side of the breakwater additions. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one privately owned dock used 
principally as a fishing terminal by owner and a municipally 
owned pier for recreational craft. Facilities are considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, and miscellaneous inspections 
and reports were performed by Government forces at a cost of 
$4,616. Safety maintenance performed by hired labor cost 
$7,575. An adjustment of $67,808 was made in cost to the 
Breakwater Cell Cap Repairs contract completed last FY. An 
adjustment of $1,972 was made to the dredging contract completed 
last FY. Engineering, design, surveys, and supervision 
and administration cost $10,746. Environmental studies under 
Section 111 Mitigation were performed at a cost of $8,931. An 
adjustment of $2,614 was made in cost to beach nourishment 
work in conjunction with the above maintenance dredging 
contract. 
The project was completed in 1951 except for latest modification 
which was completed in FY 76. The breakwaters are in 
good condition. Total cost for existing project to end of FY was 
$4,832,797, of which $1,733,071 was for new work (includes 
$487,108 contributed funds) and $3,099,726 for maintenance 
(includes $115,000 contributed funds). 
52. PORT WASHINGTON HARBOR, WI 
Location. On the west shore of Lake Michigan, about 53 
miles south of Manitowoc and about 29 miles north of Milwaukee, 
WI. (See NOAA Nautical Chart 14904.) 
Previous project. For details, see page 1938 of Annual 
Report for 1915, page 1459 of Annual Report for 1938, and 
page 30-14 of Chicago District Annual Report for 1975. 
Existing project. See Chicago District Annual Report for 
1979, Table 30-C, page 30-27. 
Construction of a small boat harbor within the existing harbor 
was authorized by the Chief of Engineers, June 12, 1975, 
under authority of Section 107, 1960 River and Harbor Act, as 
amended. 
Local cooperation. Fully complied with. 
Terminal facilities. There is one coal wharf, a petroleum 
tank farm and several fishing wharves. City provided a wharf 
which is open to public use. Facilities considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$11,134. Repair to N. Stub Pier Section G was performed by 
21-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
the Cranebarge MANITOWOC at a cost of $86,357. Supervision 
and administration cost $9,015. 
The existing project was completed in 1936. The 1958 modification 
was deauthorized in 1977. Total cost for existing project 
to end of FY was $6,780,946, of which $4,206,204 was for 
new work (includes $1,624,000 contributed funds) and 
$2,574,742 for maintenance. 
53. PORT WING HARBOR, WI 
Location. On south shore of Lake Superior, 34 miles easterly 
from Duluth, MN. (See NOAA Nautical Chart 14966.) 
Existing project. Provides for two parallel piers at entrance, 
835 and 1,017 feet long, respectively, 200 feet apart; an 
entrance channel between piers 150 feet wide with 15-foot 
depth; an irregular-shaped turning basin 15 feet deep at inner 
end of piers from which two inner channels with 8-foot depth 
extend. One of these is 60 feet wide extending southerly for 340 
feet and one 70 feet wide extending easterly 1,170 feet. 
Portion of dredging of entrance channel to complete project 
width and depth is considered unnecessary to meet present 
navigation requirements. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are four privately owned fishing 
wharves which are considered adequate for existing conditions. 
Operations during fiscal year. Maintenance: Condition surveys 
were performed by Government forces at a cost of $3,905. 
Minor repairs to navigation structures cost $235. 
Existing project is complete, except channel between piers, 
and has been dredged to only a 100-foot width. Widening the 
channel an additional 50 feet was considered unnecessary to 
meet present navigation requirements. That work was classified 
inactive and deauthorized on August 5, 1977, under Section 
12 of Public Law 93-251. Piers are in good condition. At 
the end of FY controlling depth was 12 feet in lake approach, 
10 feet between piers in northerly portion of turning basin, and 
8 feet in easterly inner channel. Land owned by the United 
States totals 7.80 acres. Total cost for existing project to end of 
FY was $940,334, of which $63,393 was for new work and 
$876,941 for maintenance. 
54. ROUGE RIVER, MI 
Location. Rises in Oakland and Washtenaw Counties, MI, 
30 miles long, flows southeasterly through Wayne County, and 
joins Detroit River at westerly limit of City of Detroit. (See 
NOAA Nautical Chart 14854.) 
Previous project. For details see page 1530 of Annual 
Report for 1932, and page 1558 of Annual Report for 1938. 
Existing project. Provides for: (a) Main channel from 
Detroit River through Short Cut Canal extending to upstream 
limit of the project, a distance of 3.5 miles. Project depths are 
25 and 21 feet in navigation channel, 21 feet in turning basin, 
and 13 feet in upper reach of project. (b) Old Channel from 
Detroit River extending to junction of Old Channel with Short 
Cut Canal. Project depths are 25, 18, 17, and 21 feet. For additional 
details see page 1324 of Annual Report for 1963. In 
1973, work authorized by the 1962 River and Harbor Act was 
reclassified from the active to inactive category. Estimated cost 
(1972) of this work is $880,000. Except for dredging 25-foot 
channel 1,150 feet upstream from mouth of Old Channel, 
work authorized in Act of August 30, 1935, is considered inactive. 
Estimated cost (1958) of inactive portion is $255,000. 
Work authorized by Act of July 3, 1958, is considered inactive. 
Estimated cost (1960) of this work is $210,000. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. Act of October 23, 1962, requires local 
interests to provide lands and rights-of-way for construction 
upon request of the Chief of Engineers; hold the United States 
free from damages; provide terminal facilities to accommodate 
prospective commerce considered in report of District 
Engineer; dredge and maintain areas between the Federal 
improvement and terminal facilities to depths commensurate 
with improved Federal channel; make alterations in docks, 
bulkheads and other structures, and take such other measures 
as may be necessary to assure stability of banks adjacent to 
channel; and provide bridge protection. The assurances of 
local cooperation for the River and Harbor Act of 1962 were 
furnished by the Michigan State Waterways Commission and 
accepted on January 7, 1965. Fulfillment of all items of local 
cooperation has not been accomplished. 
Terminal facilities. Numerous large commercial docks for 
handling various type cargo. Details on actual port and harbor 
facilities are contained in the Port Series No. 45 (revised 1984) 
prepared and published by the Water Resources Support Center. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys 
and environmental studies were performed by Government 
forces at a cost of $154,369. An adjustment of -$6,542 
was made to the FY 86 contract for repairs to the confined disposal 
facility at Grassy Island. An adjustment of -$1,631 was 
made to the contract for repair of the diked disposal facility at 
Pte. Mouillee completed last FY. A maintenance dredging contract 
was awarded and completed this FY at a cost of $604,499 
removing approximately 63,000 cubic yards of material. Engineering, 
design, surveys, supervision and administration cost 
$76,381. Under the Dike Disposal Program an adjustment of 
$234,999 was made to the FY 78 Pointe Mouillee Disposal Site 
Phase II Contract. Supervision and administration for Dike 
Disposal cost $11,609. 
Work authorized before 1962 modification is complete or 
deauthorized. For additional details on completion of existing 
project see Annual Report for 1962. Total cost for existing project 
to end of FY was $34,605,353, of which $675,251 was for 
new work and $33,930,102 for maintenance. In addition, 
$29,563 was expended for new work from Emergency Relief 
Act Funds. 
55. SAGINAW RIVER, MI 
Location. Formed by union of Tittabawassee and Shiawassee 
Rivers, 22 miles long, and flows northerly into extreme 
inner end of Saginaw Bay, Lake Huron. Cities of Saginaw and 
Bay City are on the river. (See NOAA Nautical Chart 14867.) 
Previous project. For details, see page 1957 of Annual 
Report for 1915, and page 1550 of Annual Report for 1938. 
Existing project. Provides for an entrance channel 27 feet 
deep and 350 feet wide from 27-foot contour in Saginaw Bay to 
river mouth; thence a channel 26 feet deep and 200 feet wide to 
New York Central Railroad Bridge at Bay City; thence 22 feet 
deep and 200 feet wide to C&O Railroad Bridge in Saginaw; 
thence 16.5 feet deep and 200 feet wide to upstream limit at 
Green Point. Project also provides for five turning basins; one 
25 feet deep at Essexville, 600 feet wide with a maximum length 
of 1,850 feet; one 22 feet deep on east side of channel about 1 
21-20

DETROIT, MI DISTRICT 
mile upstream from Cass Avenue in Bay City, 650 feet wide and 
1,000 feet long; one 20 feet deep at Carrollton, 100 to 300 feet 
wide and 900 feet long; one 20 feet deep just downstream from 
C&O Bridge in Saginaw, 650 feet wide and 1,000 feet long; and 
one 15 feet deep between Bristol Street Bridge and New York 
Central Railroad Bridge in Saginaw. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Numerous large commercial docks for 
handling a great variety of cargo. Details on actual port and 
harbor facilities are in Port Series No. 45 (revised 1984) prepared 
and published by the Water Resources Support Center. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
Hi-Fix surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $410,418. The contract awarded last FY for maintenance 
dredging was completed at a cost of $1,107,392, removing 
approximately 183,925 cubic yards of shoal material. A 
contract was awarded this FY in the amount of $1,447,280 for 
maintenance dredging. No work was performed this FY. An 
adjustment of $9,010 was made to the cost of the FY 87 Diked 
Disposal Facility repair contract completed last FY. Maintenance 
of disposal area cost $7,015. Engineering, design, real 
estate, supervision and administration cost $100,709. Engineering, 
design, and real estate for construction of a diked disposal 
area for upper Saginaw was continued at a cost of 
$198,388. 
Existing project is complete except for small part of the 
work authorized by the Act of October 23, 1962. Section D 
(Sixth Street Turning Basin) of the 1962 Act is complete except 
for the channel portion, which is pending modification. Total 
cost for existing project to end of FY was $73,358,585, of 
which $14,930,727 was for new work and $58,427,858 for 
maintenance. 
56. ST. CLAIR RIVER, MI 
Location. A 40 mile long section of Great Lakes connecting 
channels which flows southerly from Lake Huron and discharges 
into Lake St. Clair. (See NOAA Nautical Chart 
14852.) 
Existing project. Provides for channels through St. Clair 
River, which, at lower water datum, are suitable for vessels 
drawing 25.5 feet. Project also provides for improvement of 
North Channel outlet, 100 feet wide and 10 feet deep, for recreational 
craft. Project depths are referred to low water datums 
for Lakes Huron and St. Clair, 576.8 and 571.7 feet above 
mean water level at Father Point, Quebec; International Great 
Lakes Datum 1955. (See Tables 21-B and 21-H for authorizing 
legislation and features of existing project.) Act of July 24, 
1946, provides for widening and deepening of southeast bend 
and improvement of outlet of north channel at an estimated 
cost (1986) of $870,000; $435,000 Federal and $435,000 non- 
Federal. On June 16, 1969, the Director of Civil Works 
approved substitution of the Middle Channel of the St. Clair 
River for the authorized north channel. Subsequently, however, 
the work authorized by the River and Harbor Act of July 
24, 1946, was deauthorized by the Water Resources Development 
Act of 1986; Public Law 99-662 - Nov. 17, 1986, 99th 
Congress, Title X. 
Local cooperation. None required. 
Terminal facilities. This improvement serves through commerce, 
between upper and lower Great Lakes, and has not 
materially influenced terminal facilities along its route. A 
number of privately owned piers and wharves are at Port 
Huron, Marysville, St. Clair, and Marine City, MI, which handle 
coal, limestone, petroleum products, woodpulp, salt and 
general cargo. These installations satisfy present commerce 
requirements. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, support of water control center, 
miscellaneous inspections and reports were performed by Government 
forces at a cost of $198,952. Location and removal of 
obstructions cost $369,339. Engineering and design for maintenance 
dredging Pte. Edwards, Blue Water and Lower River 
to be performed by contract next FY cost $36,752. Supervision 
and administration cost $694. 
Existing project is complete. Total cost for existing project 
to end of FY was $38,018,618, of which $19,213,246 was for 
new work and $18,805,372 for maintenance. 
57. ST. JOSEPH HARBOR, MI 
Location. On east shore of Lake Michigan, 60 miles easterly 
from Chicago, IL, and 24 miles southerly from South Haven, 
MI (See NOAA Nautical Chart 14930.) 
Previous project. For details see page 1945 of Annual 
Report for 1915, and page 1470 of Annual Report for 1938. 
Existing project. Provides for protecting mouth of St. 
Joseph River by two piers, 250 to 325 feet apart at their inner 
and outer ends, respectively, having lengths of 2,758 feet on 
north side and 2,603 feet on south side; for a channel 21 feet 
deep from Lake Michigan to mouth of Benton Harbor Canal, 
a length of about 6,900 feet with widths of 265 feet at outer end 
of piers, 190 feet at inner end of piers and revetments, thence 
generally 215 feet to lower end of turning basin, increasing to 
250 feet above the turning basin to mouth of Paw Paw River, 
thence generally 110 feet in Paw Paw River to mouth of Benton 
Harbor Canal; for dredging channel in Benton Harbor Canal 
up to west line of Riverview Drive extended northerly, to 18 
feet deep and 80 feet wide; and a turning basin 18 feet deep on 
north side of channel above mouth of Morrison Channel and a 
turning basin 18 feet deep near mouth of Paw Paw River. Public 
Law 88-88th Congress declared a portion of Benton Harbor 
Canal a non-navigable stream. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several commercial wharves for handling 
coal, building materials, petroleum products, and miscellaneous 
commodities. A package freight terminal and a public 
docking facility is also available. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $169,405. Repairs to North Revetment, Sections C, 
D, and E, and Obstruction Removal were performed using the 
Cranebarge MANITOWOC at a cost of $62,762. Hired labor 
cost for maintenance of disposal area and safety features was 
$5,304. The structure repair contract awarded last FY for 
repair of North Pier, Section A, South Pier, Sections H and N, 
and North Revetment, Section B was completed at a cost of 
$94,209. Engineering and design during construction cost 
$473. An adjustment of -$17,966 was made in cost to the contract 
for maintenance dredging of the Outer Channel com- 
21-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
pleted last FY. A contract was awarded and completed this FY 
for maintenance dredging the Outer Channel. Approximately 
18,745 cubic yards of material was removed at a cost of 
$106,362. This contract was also for beach nourishment. Engineering 
and design for a Wave Deflection Wall in Section E of 
the North Revetment cost $1,545. Engineering, design, surveys, 
real estate, and supervision and administration cost 
$106,850. Engineering and design for disposal area for polluted 
dredged material was continued at a cost of $104,921. 
Under the Section 111 Program, $255,150 was expended to 
complete a contract awarded last FY to place dredged material 
on the beach. Beach nourishment in conjunction with above 
maintenance dredging contract cost $41,363. Monitoring, surveys, 
engineering, and supervision and administration cost 
$35,475. 
Existing project was completed in 1956. The structures are in 
generally good condition. For additional details on completion 
of existing project see page 1454 of Annual Report for 1962. 
Total cost for existing project to end of FY was $20,435,643, of 
which $1,804,485 was for new work, $17,668,942 for maintenance 
and $962,216 for rehabilitation. 
58. ST. MARYS RIVER, MI 
Location. A Great Lakes connecting channel about 63 miles 
long, flows southeasterly between State of Michigan and Province 
of Ontario, Canada, from eastern end of Lake Superior 
into northern end of Lake Huron. (See NOAA Nautical Charts 
14882, 14883, and 14884.) At Sault Ste. Marie, MI, about 14 
miles downstream from Lake Superior, there are four parallel 
locks and a hydroelectric powerplant. 
Previous project. For details see page 1955, Annual Report 
for 1915; and page 1529, Annual Report for 1938. 
Existing project. Channels permitting 25.5-foot draft navigation 
in St. Marys River and Lake Superior and Lake Huron 
approaches thereto; constructing and operating four locks and 
two canals; constructing an electric plant of 14,000 kilowatt 
capacity (45,000 kilowatt ultimate capacity) constructing 
anchorage areas in river above and below locks; and constructing 
various other works in conjunction with project. Subsequently, 
in 1932, the Unit 10 powerhouse was installed raising 
the capacity to 18,400 kilowatts (45,000 ultimate capacity). 
Original State locks were operated and maintained under permanent 
indefinite appropriation from June 9, 1881, to 
November 2, 1886, after which they were destroyed by excavation 
for the Poe Lock in 1896. Weitzel Lock destroyed in 1942 
by excavation for MacArthur Lock, was operated and maintained 
under the same appropriation from September 1, 1881, 
to June 30, 1935. Poe Lock was operated and maintained 
under the same appropriation from August 3, 1896, Davis 
Lock from October 21, 1914, and Sabin Lock from September 
18, 1919, to end of FY 1935. The 1,200 foot by 110 foot new 
Poe Lock was authorized in 1962 and put into operation in 
1968. Details of existing project are set forth in Table 21-F. 
Project depths are referred to low water datum corresponding 
to sloping surface of river as follows: Above locks: When 
water surface of Lake Superior is at elevation 600 feet and at 
upstream side of locks is 599.5 feet above mean water level at 
Father Point, Quebec (International Great Lakes Datum 
1955). Below locks: When water surface at downstream side of 
locks is at elevation 577.8 feet and Lake Huron is 576.8 feet 
above mean water level at Father Point, Quebec (International 
Great Lakes Datum 1955). Estimated (1974) cost for new work 
is $163,087,000. (See Table 21-B for authorizing legislation.) 
The Water Resources Development Act (W.R.D.A.) of 1986 
authorized construction of a second lock 1,294 feet in length, 
115 feet in width, and 32 feet in depth, adjacent to the existing 
lock. The replacement lock is to be located in the North Canal 
of the St. Marys Falls Canal at Sault Ste. Marie, MI, on the site 
of the existing Davis and Sabin Locks. Material removed during 
construction of the replacement lock will be placed on the 
Northwest Pier to serve as a windbreak for downbound vessels 
approaching the lock. Estimated cost (Oct. 88) is $159,900,000 
Federal and $86,100,000 non-Federal. 
Local cooperation. Fully complied with for completed portion 
of project. Local cooperation items for the newly authorized 
project in the W.R.D.A. of 1986 (P.L. 99-662), are as follows: 
a) Provide without cost to the United States all lands, easements, 
and rights-of-way necessary for implementation and 
later maintenance of the proposed project, and for aids to navigation 
upon the request of the Chief of Engineers, including 
suitable areas determined by the Chief of Engineers to be 
required in the general public interest for initial and later disposal 
of dredged/demolition material and including necessary 
retaining dikes, bulkheads, and embankments therefor, or the 
costs of such retaining works; 
b) Hold and save the United States free from damages due to 
the implementation and maintenance of the project, not 
including damages due to the fault or negligence of the United 
States or its contractors; 
c) Accomplish without cost to the United States such alterations 
and relocations of pipelines, powerlines, cables, sewer, 
water supply, drainage, and other utilities, structures, and 
improvements made necessary by the project (Any such costs 
of the items on Federal property at the locks, would be part of 
the total construction cost and not separable local sponsor 
cost.); 
d) Contribute in cash 25 percent of the total cost of construction 
of general navigation facilities, exclusive of aids to navigation, 
a contribution presently estimated at $61,500,000. The 
estimated cash contribution of $61,500,000 to be paid in lump 
sum prior to initiation of construction, or in annual installments 
during the construction period at a rate proportionate to 
the proposed or scheduled expenditure of Federal funds as 
required by the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final apportionment 
of cost to be made after actual costs have been determined; 
and 
e) Repay, with interest, over a period of up to 30 years following 
project completion, 10 percent of the total cost of construction 
of general navigation facilities, an amount presently 
estimated at $24,600,000. The Secretary of the Army may 
count against all or part of the 10 percent repayment, the 
amount of the local contribution for lands, easements, rightsof-
way, dredged/demolition material disposal sites and relocations. 
In no case are these costs to count against the cash payment 
during construction, and in no case would the amount 
waived exceed 10 percent of project cost. 
f) Any construction needed to prevent/mitigate for erosion 
or shoaling attributed to the lock would be cost shared in the 
same proportion as the project. 
Terminal facilities. This improvement serves through commerce 
between Lake Superior and lower lakes and has not 
materially influenced terminal facilities at localities along its 
route. Three piers at Sault Ste. Marie receive coal and petro- 
21-22

DETROIT, MI DISTRICT 
leum products. Limestone is shipped from a pier at Drummond 
Island. Vessel refueling stations are at Lime Island and 
Village of Detour; they receive coal and petroleum products. 
Present terminals satisfy current traffic requirements. 
Operations during fiscal year. Operations, maintenance, 
and care of locks: Two canals and three locks were operated 
(the third lock, Davis, was out of service) as required. Necessary 
repairs and improvements were made thereto and to 
appurtenant structures and equipment. Canals were open to 
navigation 300 days (from 1 October 1988 through 30 September 
1989). During that period, a total of 13,660 vessels, aggregating 
89,517,470 short tons of freight and 319,291 passengers 
passed through the MacArthur, Poe, and Sabin Locks. Cost 
for operation, maintenance, and care of the locks for this FY 
was $5,756,085, which included $282,858 for extended season 
operation and maintenance, $50,257 for operation and maintenance 
of the Gatelifter PAUL BUNYAN and $21,573 retroactive 
backpay (FY 1980 - FY 1988) for lock and dam operators 
who had been paid at the wrong pay scale. 
Powerhouse and equipment: Two hydroelectric powerhouses 
were operated and maintained at a cost of $879,150 
during the FY which includes a deduction of $39,008 for interdepartmental 
electricity sold but not paid for. The contract 
awarded in FY 87 for emergency repair to hydro generator 
Unit 10 accrued expenditures in the amount of $27,500. 
Other operation and care items: Building and grounds were 
operated and maintained, condition surveys, operations studies, 
real estate, environmental studies, miscellaneous inspections 
and reports were performed at a cost of $1,388,574 which 
includes a custodial, snow removal, and grounds upkeep contract 
for $275,644. Security measures were performed at a cost 
of $349,747 which included a service contract for $341,760. 
The survey and mapping contract awarded last FY accrued 
cost in the amount of $5,223. A study on winter and extended 
navigation season, ice measurements, and weather monitoring 
was performed at a cost of $264,473. Hired labor repairs to the 
Soo Harbor ice boom cost $38,114. Work was done on the 
Compensating Gates at a cost of $53,414. 
Channels and canals: St. Marys River channels and canal 
approach depths were surveyed by sweeping. Removal of 
shoals in the St. Marys River channels and canal approaches 
was accomplished by hired labor with U.S. Derrickboats 
NICOLET and HARVEY at a cost of $1,357,614. 
Other miscellaneous items: The FY 87 repair contract for the 
Davis Lock Dewatering Gates was completed this FY at a cost 
of $51,081. Supervision and Administration of the Dewatering 
Gates Contract cost $14,206. Engineering and design for the 
master plan for the facility was performed at a cost of $20,319. 
Other miscellaneous engineering and design, supervision and 
administration cost $65,050. 
Recreational facilities: Information center, comfort stations, 
park fountain, observation and overlook platforms were 
maintained at a cost of $123,557 which included a janitorial 
contract for the Information Center at a cost of $21,717. A 
commercial activity study was performed for the Visitor Center 
at a cost of $19,191. A contract was awarded and completed 
this FY for the expansion of the Visitor Center parking lot at a 
cost of $86,477. Visitors entering the Soo Locks Information 
Center numbered 614,156. Visitors to the observation platforms 
overlooking the locks numbered 540,411. Total number 
of visitors to the Soo Locks park was 734,915. A grand total of 
1,054,206 people visited the Soo Locks. 
Total project costs in FY 89 amounted to $10,499,775. 
Project in effect prior to modification of March 21, 1956, is 
complete and work authorized by 1956 modification to provide 
a safe draft of 25.5 feet for both upbound and downbound 
traffic is also complete. Public Works Acceleration 
Funds used for maintenance were $118,000. Total cost for 
existing project to end of FY was $371,462,047, of which 
$160,657,070 was for new work and $210,804,977 for maintenance. 
59. SAUGATUCK HARBOR 
AND KALAMAZOO RIVER, MI 
Location. Harbor is on east shore of Lake Michigan, 90 
miles northeasterly from Chicago, IL, and 22 miles northerly 
from South Haven, MI. (See NOAA Nautical Chart 14906.) 
Previous project. For details see page 1947 of Annual 
Report for 1915, and page 1475 of Annual Report for 1938. 
Existing project. Entrance channel protected by parallel 
piers at mouth of Kalamazoo River and a river channel to Village 
of Saugatuck, MI. Project depths: 16 feet in entrance 
channel, 14 feet in river channel. Additional details on page 
1456, 1962 Annual Report. (See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. At Village of Saugatuck, MI, there are 
several landing places for recreational craft and one for small 
commercial vessels. At Village of Douglas, MI, there is a landing 
pier. Facilities are considered adequate for present traffic. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, and miscellaneous inspections and reports 
were performed by Government forces at a cost of $50,412. 
Repairs to safety features by hired labor cost $3,721. A contract 
in the amount of $49,320 was awarded for maintenance 
dredging. No work was performed this FY. Engineering, 
design, surveys, supervision, and administration cost $34,399. 
Existing project was completed in 1903. Total cost for existing 
project to end of FY was $3,634,047, of which $364,527 
was for new work and $3,269,520 for maintenance. 
60. SAXON HARBOR, WI 
Location. On south shore of Lake Superior in Wisconsin at 
mouth of Oronto Creek, 27 miles southeast of harbor at Bayfield, 
WI, and 21 miles westerly of harbor at Black River, MI; 
99 miles east of Duluth-Superior Harbor and 60 miles west of 
Ontonagon Harbor, MI. (See NOAA Nautical Chart 14965.) 
Previous project. For details see page 1254 of Annual 
Report for 1962. 
Existing project. Provides for east and west breakwaters, an 
outer channel 10 feet deep, an inner basin and side channel 8 
feet deep, and diversion of Oronto Creek to Parkers Creek by 
three short reaches of channel excavation and a levee. For 
detailed dimensions of features see page 1025 of Annual 
Report for 1965. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One wharf 300 feet long on east side of 
present harbor basin constructed by local interests. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$30,034. Repairs to E. Breakwater Outer Cell Cap were per- 
21-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
formed by the Cranebarge MARKUS at a cost of $43,983. 
Engineering and design for repairs to the East and West Breakwater 
cost $24,136. Engineering and design for maintenance 
dredging cost $34,665. A contract was awarded this FY for 
maintenance dredging in the amount of $91,760. No work was 
performed this FY. Supervision and administration cost 
$2,673. 
The project was completed in March 1968. A reconnaissance 
report was completed in August 1971 concerning erosion of the 
shoreline west of the harbor. Plans and specifications for mitigation 
of shoreline damages were completed and a construction 
contract was awarded in August 1989. Total cost for existing 
project to end of FY was $1,707,670, of which $1,094,377 
was for new work (includes $50,193 contributed funds) and 
$613,293 for maintenance. 
61. SEBEWAING RIVER, MI 
Location. At mouth of Sebewaing River on south shore of 
Saginaw Bay about 10 miles south of Bay Port, MI. (See 
NOAA Nautical Chart 14863.) 
Previous project. For details see page 1007 of Annual 
Report for 1912. 
Existing project. Provides for an entrance channel 8 feet 
deep, 100 feet wide, and about 15,000 feet long in Saginaw 
Bay. (See Table 21-B for authorizing legislation.) 
Terminal facilities. A number of small wharves used by fishing 
vessels and other light-draft craft are along the river. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, and miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $28,329. The maintenance dredging contract 
awarded last FY was completed at a cost of $586,031, removing 
approximately 82,898 cubic yards of dredged material. 
Engineering, design, real estate, surveys, and supervision and 
administration cost $56,300. 
Existing project was completed in 1903. Total cost for existing 
project to end of FY was $3,473,295, of which $35,573 was 
for new work and $3,437,722 for maintenance. 
62. SHEBOYGAN HARBOR, WI 
Location. On west shore of Lake Michigan about 26 miles 
south of Manitowoc and about 55 miles north of Milwaukee, 
WI. (See NOAA Nautical Chart 14922.) 
Previous project. See page 1381 of Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 
1979, Table 30-C, page 30-27. 
For detailed description see page 1230, Annual Report for 
1963. New Work for project as completed cost $648,271, exclusive 
of amounts expended on previous projects. (See Table 21- 
B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves for handling coal, petroleum 
products and miscellaneous commodities. City provided 
a public wharf. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $30,426. Minor repairs to navigation 
structures were performed by hired labor at a cost of 
$815. Engineering, design, surveys, supervision and 
administration for a maintenance dredging contract cancelled 
due to lack of shoaling cost $23,003. Engineering and design 
for dike disposal site selection continued at a cost of $6,868. 
Existing project was completed in 1904. Construction of 
north breakwater was commenced in October 1913 and completed 
in October 1915. Dredging entrance channel to existing 
project depth was commenced in June and completed in July 
1938. Work on 1954 modification was completed in December 
1956. Piers and breakwaters are in generally good condition. 
Inner 260 feet of south pier was replaced with a revetment by 
private interests under permit granted July 16., 1931, by the 
Secretary of War. Piers, therefore, are maintained only for a 
length of about 2,490 feet. Sheboygan River is navigable about 
2.4 miles above its mouth for craft drawing not more than 2 
feet. Total cost for existing project to end of FY was 
$8,043,208, of which $1,136,088 was for new work, 
$6,298,092 for maintenance and $609,028 for rehabilitation. 
63. SOUTH HAVEN HARBOR, MI 
Location. On east shore of Lake Michigan, 77 miles northeasterly 
from Chicago, IL, and 24 miles northerly from St. 
Joseph, MI. (See NOAA Nautical Chart 14906.) 
Previous project. For details see page 1947 of Annual 
Report for 1915, and page 1473 of Annual Report for 1938. 
Existing project. An entrance channel protected by parallel 
piers and revetments at mouth of Black River, a river channel 
and a turning basin. Project depths are 21 feet in entrance 
channel and 19 feet in river channel and turning basin. For 
additional details see page 1455 of Annual Report for 1962. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves for handling coal, building 
materials, woodpulp, fish, and miscellaneous commodities 
will have warehouses. Facilities satisfy current commerce 
requirements. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, and miscellaneous inspections and reports 
were performed by Government forces at a cost of $20,485. 
The U.S. Cranebarge MANITOWOC performed repairs to 
North Revetment, Section G and South Pier, Sections H, J, 
and K at a cost of $41,340. Hired labor cost for maintenance of 
safety features was $5,697. Engineering and design for major 
repairs to the South Pier and Revetment Sections A, M, M-1, 
and N continued at a cost of $38,692. Real estate and supervision 
and administration cost $10,587. Environmental studies 
and monitoring in connection with Section 111 was performed 
at a cost of $13,725. 
Existing project was completed in 1960. Project now being 
maintained to 14-foot and 12-foot depths, respectively (in lieu 
of the 21 feet and 19 feet authorized), which is adequate for 
current usage. For additional details on completion of existing 
project see page 1456 of Annual Report for 1962. Total cost for 
existing project to end of FY was $7,676,048, of which 
$984,426 was for new work, $5,059,546 for maintenance and 
$1,632,076 for rehabilitation. 
64. STURGEON BAY AND LAKE MICHIGAN 
SHIP CANAL, WI 
Location. On west shore of Lake Michigan about 52 miles 
northeast of Green Bay and about 128 miles north of Milwaukee, 
WI. (See NOAA Nautical Chart 14919.) 
Previous projects. See page 1373 of Annual Report for 1962. 
21-24

DETROIT, MI DISTRICT 
Existing project. See Chicago District Annual Report for 
1979, Table 31-C, page 30-27. For detailed description, see 
page 1223, Annual Report for 1963. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. As the canal and connecting channel is a 
through waterway, only terminal facilities are in City of Sturgeon 
Bay, 4 miles from west end of revetted portion of canal. 
These facilities consist of two wharves for handling coal, 
petroleum products and miscellaneous commodities and four 
shipbuilding yards. City of Sturgeon Bay provided a public 
wharf about 5 miles northwesterly from City of Sturgeon Bay. 
Two major shipyards are located in Sturgeon Bay where repair 
facilities are available including dry docks, marine railways 
and hoists. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$77,453. Repairs to N. Revetment Sections M, J, L, and S. 
Revetment Sections K and N were performed by the Cranebarge 
MANITOWOC at a cost of $96,692. Engineering, 
design, miscellaneous inspections and reports for construction 
of offloading disposal facility to be performed by contract next 
FY cost $75,853. Other engineering and design, supervision 
and administration cost $21,431. 
Total cost for existing project to end of FY was $10,008,501, 
of which $1,059,722 was for new work, $8,063,880 for maintenance 
and $884,899 for rehabilitation. In addition, $235,940 
was expended between April 25, 1893, and June 30, 1917, on 
operating and care of works of improvements under provision 
of permanent indefinite appropriations for such purposes. 
65. TWO HARBORS, MN 
Location. Harbor is on north shore of Lake Superior, 27 
miles northeasterly from Duluth, MN. (See NOAA Nautical 
Chart 14966.) 
Existing project. Narrowing natural entrance by construction 
of two breakwaters, 1,628 and 900 feet long, from eastern 
and western points of bay, respectively; and dredging a maneuvering 
area on north side of harbor to 28 and 30 feet deep. A 
walkway on east breakwater is provided for public recreational 
use. For details see page 1026 of Annual Report for 1965. 
Dredging to deepen areas along easterly and northerly edges of 
channel was completed in 1980. This portion of project was 
reclassified from the "inactive" to "active" category in 1973. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. A section 221 local 
cooperation agreement was entered into with the city of Two 
Harbors on August 14, 1978. 
Terminal facilities. No publicly owned wharves. Three ore 
docks, tug wharf, an unused coal dock, and merchandise 
wharf are privately owned. Facilities considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $26,289. Engineering and 
design for repair to W. Pier - Section C to be performed by contract 
next FY cost $175,554. Supervision and administration 
cost $2,117. 
The existing project is complete. Total cost for existing project 
to end of FY was $6,413,694, of which $4,170,710 was for 
new work and $2,242,984 for maintenance. 
66. TWO RIVERS HARBOR, WI 
Location. On west shore of Lake Michigan about 82 miles 
north of Milwaukee and about 101 miles from Green Bay, WI, 
via Sturgeon Bay Canal. (See NOAA Nautical Chart 14903.) 
Previous projects. See page 1377, Annual Report for 1962. 
Existing project. See Chicago District Annual Report for 
1979, Table 30-C, page 30-28. 
For detailed description see page 1226 of Annual Report for 
1963. Completed project cost $147,463, exclusive of the 
amount expended on previous projects. The 1935 River and 
Harbor Act portion of project is considered inactive. Estimated 
cost of this portion (1954) is $14,000. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A coal wharf and several fishing 
wharves. City provided a wharf for receipt of petroleum products 
and public use. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Condition surveys, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$30,445. Repairs to South Breakwater Sections C and D were 
performed by the Cranebarge MANITOWOC at a cost of 
$45,434. A contract was awarded for maintenance dredging in 
the amount of $207,840. No work was performed. Engineering, 
design, supervision and administration cost $58,702. 
Existing project is complete except for inactive portion of 
project which consists of dredging a 10-foot width along east 
side of lakeward portion entrance channel between the piers. 
This dredging was omitted to avoid removal of necessary riprap 
along entrance piers. Present width of channel is considered 
adequate for present and reasonably prospective commerce. 
South pier was completed in 1883 and is in generally 
good condition. North pier was completed in 1908. North 
revetment, completed in 1917, was rebuilt in May to August 
1962. Dredging entrance channel and inner basin to existing 
project depth was commenced in March and substantially 
completed in May 1937. Total cost for existing project to end of 
FY was $7,156,497, of which $360,320 was for new work, 
$6,738,120 for maintenance, and $58,057 for minor rehabilitation. 
67. WHITEFISH POINT HARBOR, MI 
Location. On south shore of Lake Superior 40 miles northwesterly 
from Sault Ste. Marie, MI, and 53 miles easterly from 
Grand Marais, MI. (See NOAA Nautical Chart No. 14962.) 
Existing project. Provides for a harbor or refuge protected 
by two breakwater structures and for dredging a harbor basin 
and entrance channel, 12 feet deep. The addition of a 270-foot 
wave absorbing breakwater inside the harbor was approved by 
the Chief of Engineers on August 17, 1967, to correct a design 
deficiency. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one privately owned fishing 
wharf and a small-boat pier and launching ramp built by the 
State of Michigan. Facilities are considered adequate for existing 
commerce. 
21-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations during fiscal year. Maintenance: Condition surveys 
and environmental studies were performed by Government 
forces at a cost of $10,833. Engineering and design for a 
maintenance dredging contract to be awarded next FY cost 
$3,939. 
Existing project was completed in 1960. The interior breakwater 
and repairs to the shoal connection were accomplished 
by contract during FY 1969. Remaining structures are in generally 
good condition. Total cost for existing project to end of FY 
was $1,023,747, of which $771,639 was for new work and 
$252,108 for maintenance. 
68. WHITE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan 120 miles northeasterly 
from Chicago, IL, and 45 miles southerly from 
Ludington, MI. (See NOAA Nautical Chart 14935.) 
Existing project. Parallel piers, revetments, and a channel 16 
feet deep, 200 feet wide, 1,950 feet long, extending from Lake 
Michigan to White Lake. For additional details see page 1465 
of Annual Report for 1962. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. A privately owned chemical shipping 
dock on north side of lake about 3 miles from inner end of 
revetted entrance channel. Across lake, at Village of Whitehall, 
there are several installations serving light draft vessels. 
These terminals satisfy present recreational and commercial 
traffic requirements. 
Operations during fiscal year. Maintenance: Condition and 
structure surveys, environmental studies, and miscellaneous 
inspections and reports were performed by Government forces 
at a cost of $27,188. Repairs to the North Revetment Sections 
A, G, and H and Scuth Pier, Sections A, B, C, D, and E were 
performed by hired labor using the Cranebarge MANITOWOC 
at a cost of $62,330. Minor safety maintenance performed 
by hired labor cost $2,474. Engineering and design for 
repairs to North and South Piers Sections A and B continued at 
a cost of $69,331. Real estate and supervision and administration 
cost $9,470. Condition surveys, monitoring, real estate, 
and engineering and design in connection with Section 111 of 
P.L. 90-483 were performed at a cost of $23,587. 
Existing project was completed in 1908. Stone was placed on 
the north and south revetments in FY 1972. The structures are 
in generally good condition. Project now being maintained to 
14-foot depth authorized, which is adequate for current usage. 
Total cost for existing project to end of FY was $3,745,781, of 
which $457,562 was for new work and $3,288,219 for maintenance. 
69. RECONNAISSANCE AND 
CONDITION SURVEYS 
See Table 21-3. 
70. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 21-C. 
71. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107. Public Law 
86-645 (pre-authorization.) None. 
Beach Erosion Control 
72. AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
A beach erosion control project is authorized at the Shore of 
Manitowoc County, WI. For last full report see Annual Report 
for 1963 (Berrien County). The project is in the inactive category. 
The project for beach erosion control, Berrien County, MI 
(St. Joseph Shore), authorized by the Flood Control Act of 
1958, was deauthorized by the Water Resources Development 
Act of 1986; Public Law 99-662 - Nov. 17, 1986, 99th Congress, 
Title X. (See Table 21-G for list of deauthorized projects.) 
73. EMERGENCY SHORE PROTECTION 
Authority for emergency streambank and shoreline protection 
of public works and non-profit public services. (Section 14 
Flood Control Act of 1946, as amended.) 
Bar Lake, MI - A contract for construction of a stone 
revetment to protect 600 feet of Lake Michigan shoreline adjacent 
to Lakeshore Road was awarded on August 3, 1989, and 
work commenced on September 22, 1989, at a cost of $18,844. 
Baraga County, MI - Plans and specifications for protection 
of 400 feet of Lake Superior shoreline adjacent to U.S. 
Highway 41 were continued at a cost of $3,862. 
Charlevoix County, East Jordan River, MI - The plans and 
specifications for protection of 800 feet of shoreline adjacent 
to the M-32 bridge abutment embankments were completed at 
a cost of $4,343. The Local Cooperation Agreement for construction 
of the project was executed on July 13, 1989, and the 
required cash contribution and rights-of-entry were provided 
on September 7, and August 19, 1989, respectively. 
City of South Haven, MI - Termination and financial 
closeout of the unfavorable reconnaissance report study was 
completed at a cost of $4,000. 
Fair Haven, MI- Plans and specifications for protection of 
850 feet of the Anchor Bay shoreline adjacent to State Highway 
M-29 were continued at a cost of $8,851. 
Harbor Springs, MI - Subsequent to approval of the project 
for construction, by the Assistant Secretary of the Army, in 
FY 1988, the project sponsor withdrew its support of the project 
due to real estate problems and the project was therefore 
terminated on February 9, 1989. FY 1989 costs were $5,910. 
Lake Michigan Shoreline, Muskegon, MI - A contract for 
construction of a stone revetment to protect 600 feet of Lake 
Michigan shoreline adjacent to the city's water filtration plant 
was awarded on March 30, 1989, and all work was substantially 
completed on July 26, 1989, at a cost of $205,306. 
Lake Michigan Shoreline, South Milwaukee, WI - A 
reconnaissance study, to determine if there is a Federal interest 
in providing shoreline erosion protection to the outfall pipe of 
the city's Wastewater Treatment Plant, was completed, and is 
currently under review by higher authority. No funds were 
expended in FY 1989. 
Ludington, MI - Termination and financial closeout of the 
unfavorable reconnaissance report study was completed at a 
cost of $2,390. 
Manistee River, Manistee, MI - Termination and financial 
closeout of the unfavorable reconnaissance report study was 
completed at a cost of $4,000. 
21-26

DETROIT, MI DISTRICT 
Marysville, St. Clair River, MI - A contract for shoreline 
erosion protection of 2,000 feet of the St. Clair River shoreline 
adjacent to River Road was awarded on June 30, 1989, and 
work commenced on August 8, 1989, at a cost of $113,544. 
Memorial Drive, McKinley Park, WI - Review and 
approval of the completed Detailed Pr oject Report, which recommended 
the construction of the stone revetment to protect 
500 feet of the Lake Michigan shoreline adjacent to Lincoln 
Memorial Drive, was continued at a cost of $850. 
Memorial Drive, Muskegon, MI - A reconnaissance study, 
to determine if there is a Federal interest in providing shoreline 
erosion protection to 800 feet of Scenic Drive at Memorial 
Drive, was continued at a cost of $2,936. 
Milwaukee South Shore Park, WI - Review and approval 
of the completed Detailed Project Report, which recommended 
the construction of a stone revetment to protect the 
pavilion/bathhouse and its parking lot, was continued. There 
were no costs incurred during FY 89. 
Scenic Drive, Duck Lake, MI - A contract for construction 
of a stone revetment to protect 1,500 feet of Lake Michigan 
shoreline adjacent to Scenic Drive was awarded on August 9, 
1989. However subsequent to contract award, a significant 
error in estimated bedding stone quantities was detected and 
the contract was terminated on September 8, 1989, for convenience 
of the Government. Design alternatives were developed 
and will be coordinated with the project sponsor prior to readvertisement 
of the work in FY 90. FY 89 costs were $15,856. 
Sheboygan, WI - Completed the preparation of an unfavorable 
Detailed Project Report for the city's sanitary pump 
station, and a favorable Detailed Project Report to provide 
shoreline erosion protection to the city's 60-inch sanitary sewer 
line. FY 89 costs were $2,592. 
74. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion activities pursuant to Section 103 of the 1962 
River and Harbor Act. None. 
75. MITIGATION OF SHORE DAMAGES 
Mitigation of Shore Damages pursuant to Section 111 of the 
River and Harbor Act of 1968. Plans and specifications for 
mitigation of shoreline damages adjacent to County Highway 
A west of Saxon Harbor, WI, were completed and a construction 
contract was awarded to Saginaw Construction, Inc., on 
August 3, 1989. Construction initiation scheduled for October 
1989. FY 89 costs were $30,526. 
Flood Control 
76. PAW PAW LAKE, MI 
Location. Approximately 10 miles north of St. Joseph/Benton 
Harbor on the Paw Paw River, in Berrien County. 
Existing Project. Accomplished under the authority of Section 
205 of the 1948 Flood Control Act, the project provides 
for: a gated control structure at the Paw Paw Lake outlet to the 
Paw Paw River; a 1,722 foot long, 72-inch reinforced concrete 
drainage from the southeast corner of the lake to the Paw Paw 
River; entrance and exit structures to improve hydraulic efficiency 
and provide protection to the pipe from floating debris; 
and two small levees to alleviate induced downstream damages. 
The project was completed in February 1987. (See Table 
21-B for authorizing legislation.) 
Local Cooperation. Fully complied with. 
Operations during fiscal year. New Work: Financial closeout 
of the project authority cost $1,358. 
Total costs to end of FY were $3,589,000. 
77. SAGINAW RIVER, MI 
Location. Saginaw River Basin including its tributaries, Tittabawasee, 
Shiawassee, Flint and Cass Rivers, drains an area 
of 6,260 square miles in the east central part of Michigan and 
empties into Saginaw Bay, an arm of Lake Huron. Bay City, 
near mouth of river, and Saginaw, 22 miles upstream from 
mouth, are on Federally improved deep-draft Saginaw River 
navigation channel (See Saginaw and Flint Geological quadrangles 
and NOAA Nautical Chart 14867). 
Existing project. Provides for improvements in Saginaw 
River Basin for flood control and other purposes: (a) at Sanilac 
Flats, MI, Middle Branch and South Branch, Cass River, to 
provide for major drainage improvements by channel 
improvements on Middle and South Branches, including a 
short reach of East Branch. This feature of the project for 
flood control, Saginaw River, MI, authorized by the Flood 
Control Act of 1958, was deauthorized by the Water Resources 
Development Act of 1986; Public Law 99-662 - Nov. 17, 1986, 
99th Congress, Title X; (b) at Vassar on Cass River, to provide 
for flood protection of areas on north and south sides of river 
by channel improvement, levee construction floodwalls, modifications 
of Moore Drain, and related work at an estimated 
U.S. cost (Oct. 1984) of $8,620,000 and non-Federal cost of 
$579,000 for construction; (c) at Frankenmuth on Cass River, 
to provide for flood protection of areas on north side of river 
by channel improvement, levee construction, and related 
work, at an estimated U.S. cost (July 1974) of $410,900 for 
construction; (d) at Flint on Flint River, to provide for flood 
protection of areas on both sides of main stem of Flint River 
and its tributaries, Swartz and Thread Creeks by channel 
improvement, bridge alterations, floodwall and levee construction, 
and related work, at an estimated U.S. cost (Oct. 
1984) of $18,251,600 and non-Federal cost of $2,580,000 for 
construction; provided local interests contribute in cash 1 percent 
of first cost of project, exclusive of costs of rights-ofways; 
(e) at Corunna on Shiawassee River, to provide for flood 
protection by channel improvement, levee construction, and 
related work. This feature of the project for flood control, 
Saginaw River, MI, authorized by the Flood Control Act of 
1958, was deauthorized by the Water Resources Development 
Act of 1986; Public Law 99-662 - Nov. 17, 1986, 99th Congress, 
Title X; (f) at Owosso on Shiawassee River, to provide 
for flood protection by channel improvement. This feature of 
the project for flood control, Saginaw River, MI, authorized 
by the Flood Control Act of 1958, was deauthorized by the 
Water Resources Development Act of 1986; Public Law 99-662 
- Nov. 17, 1986, 99th Congress, Title X; (g) at Midland on Tittabawassee 
River, to provide for flood protection through 
non-structural (permanent evacuation) measures at an estimated 
U.S. cost (Apr. 1982) of $5,125,000 and non-Federal 
cost of $1,611,500 for implementation; however, project was 
reclassified to the "inactive" category on December 15, 1982; 
(h) at Shiawassee Flats along lower reaches of the four principal 
tributaries of Saginaw River, to provide for flood protection, 
including fish and wildlife areas; by channel improvement, 
levees, lateral reservoirs with control structures and 
related work at an estimated U.S. cost (Oct. 1984) of 
21-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
$23,417,500 Federal, and a non-Federal cost of $2,705,000 
which includes a cash contribution of $1,237,000; provided 
local interests contribute in cash 5 percent of cost of rights-ofway 
for flood control and other work required as local cooperation, 
and furnish one-half of land required for fish and wildlife 
areas; provided that the Federal allocation for 
conservation does not exceed amount obtained by taking 28 
percent of project cost for Shiawassee Flats unit and subtracting 
therefrom one-half cost of lands for conservation; and provided 
further that before starting works for flood control to 
Shiawassee Flats, Chief of Engineers and Director, Fish and 
Wildlife Service, prepare a plan mutually acceptable to Secretary 
of the Army and Secretary of the Interior for operation of 
fish and wildlife areas to required degree of controlled storage 
of flood-waters while preserving the maximum fish and wildlife 
benefits. Total estimated cost for new work, for active portion 
(1984) is $50,700,000 Federal and $1,421,000 to be contributed 
by local interests. Total estimated cost (1984) to local 
interests is $5,870,000. 
Local cooperation. Responsible local interests must make 
cash contributions as called for above; furnish lands, and 
rights-of-way, including removal of buildings, for construction; 
hold the United States free from damage; maintain and 
operate all works after completion; establish and enforce regulations 
designed to prevent encroachments in improved channels; 
and bear expense of constructing highway relocations and 
highway bridges, alter bridge approaches and existing highway 
bridge approaches and existing highway bridges (except underpinning 
and bridge raising), and alter utilities. Required assurances 
for Flint River at Flint were furnished by city of Flint and 
accepted by the United States on November 23, 1962. Estimated 
required cash contribution for Flint ($56,000) was furnished 
February 20, 1963. An additional $117,000 was furnished 
by the City to cover increased construction costs. 
Required assurances for Cass River at Frankenmuth were 
accepted on September 8, 1964. All necessary lands, easements, 
and rights-of-way have been provided. The Midland 
City Council adopted a resolution on June 7, 1982, declaring 
its intent not to sponsor the Flood Control project on the Tittabawassee 
River at Midland. The Vassar City Council, in a letter 
dated January 26, 1982, indicated a willingness and capability 
to provide the assurances of local cooperation for the Vassar 
Flood Control Project. Saginaw County, in a resolution dated 
August 11, 1982, indicated a willingness and capability to provide 
the assurances of local cooperation for the Shiawassee 
Flats Flood Control Project. 
Operations during fiscal year. New Work: Flint: Investigations 
of claims for contract completed in FY 80 were continued 
in FY 89 at a cost of $148,628. 
The Frankenmuth and Flint portions of the project are complete. 
78. SEBEWAING, SEBEWAING RIVER, MI 
Location. Sebewaing River drains an area of 105 square 
miles in Huron and Tuscola Counties on the westerly side of 
Thumb area of Lower Peninsula of Michigan and discharges 
into Saginaw Bay, an arm of Lake Huron, 20 miles northeast 
from mouth of Saginaw River. Village of Sebewaing is near 
mouth of River. (See NOAA Nautical Chart 14863.) 
Existing project. Enlarging present channel of Sebewaing 
River through Village of Sebewaing, MI, to a capacity of 7,500 
cubic feet per second from junction of Columbia and State 
drains to a point 4,500 feet lakeward from railroad bridge near 
mouth; altering railroad bridge and three highway bridges to 
permit free passage of ice; and removal of present dike on 
south side of channel lakeward from railroad bridge. Project is 
designed to provide protection for Village of Sebewaing from 
floods with a frequency of once in 15 years and with a magnitude 
greater than the maximum flood of record. (See Table 21- 
B for authorizing legislation.) 
Local cooperation. Complied with except for furnishing 
easements and rights-of-way for removal of remaining portion 
of dike on south side of channel lakeward from railroad 
bridge. 
Operations during fiscal year. Maintenance: Condition surveys 
were performed by Government forces at a cost of $7,243. 
Total costs to the end of the FY were $773,529. 
79. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Name of Project Date of Inspection 
Battle Creek, Kalamazoo River, MI September 1989 
Burr Oak, Prairie River, MI September 1989 
Frankenmuth, Cass River, MI August 1989 
Mount Clemens Spillway and Cutoff 
Canal, Clinton River, MI May 1989 
Red Run, Clinton River, MI May 1989 
FY 89 costs were $115,223. Total costs to end of FY were 
$1,612,392. 
80. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 21-E. 
81. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency Flood Control Activities, Flood Fighting (Public 
Law 84-99 and P.L. 93-288 and Antecedent Legislation). 
Fiscal Year Costs 
Project and Location to September 30, 1989 
Disaster Preparedness $ 330,015 
Emergency Operations $ 19,724 
Rehabilitation $ -0- 
Advance Measures $ 165,799 
Advance Measures (Contributed Funds) $ 100,918 
Flood Control activities pursuant to Section 205 of the 1948 
Flood Control Act. The Draft Definite Project Report for the 
Ontonagon, MI project was terminated due to lack of local 
sponsorship ($18,525). The preparation of Reconnaissance 
Reports continued for Cedar Creek, Auburn, IN ($22,061); 
Grand Pointe, Eaton County, MI ($4,749); LaPorte, Pine 
Lake, IN ($27,873); Lincoln Creek, Milwaukee, WI ($38,928); 
Menominee River, Milwaukee, WI ($14,103); and Root River, 
Milwaukee, WI ($34,548). Financial physical closeout of study 
authorities were completed on the terminated Wilson Park, 
Milwaukee, WI project ($2,182) and the Judy Creek, IN project 
($43). New Reconnaissance Report efforts were initiated 
for the city of Monroe, MI ($297) and Oconto River, WI 
($1,291). A Reconnaissance Report addressing alternatives for 
reducing the O&M cost of the completed Kawkawlin River 
project was initiated and completed at a cost of $18,050. 
Flood Control activities pursuant to Section 208 of the 1954 
Flood Control Act. Physical and financial closeout of the 
21-28

DETROIT, MI DISTRICT 
study authority was accomplished on the terminated study for 
North Fond du Lac, WI ($368). 
Aquatic Plant Control activities pursuant to Section 302 of 
the River and Harbor Act of 1965 (PL 89-298). None. 
82. SURVEILLANCE OF NORTHERN 
BOUNDARY WATERS 
Field Operations. The following field operations, which 
were complemented by office activities, were conducted during 
the report period. In support of District modeling activities, 
flow distribution measurements were conducted in the St. 
Clair River delta. In support of the International Niagara 
Board of Control, the District conducted discharge measurements 
on the Niagara River. These measurements are part of 
programs to verify the stage-discharge relationships for the 
Ashland Avenue, American Falls, Buffalo and Fort Erie gages, 
and to support mathematical modeling activities. These programs 
are essential to maintaining an accurate estimate of flow 
over Niagara Falls, to satisfy the Niagara Treaty, and to verify 
stage-discharge relationships developed for the International 
Joint Commission Reference Study. In support of the International 
Lake Superior Board of Control, discharge measurements 
were conducted in the lower St. Marys Rapids for the 
calibration of the Sault Ste. Marie Compensating Works. 
Additional field measurements are scheduled on the St. Marys, 
St. Clair, Niagara, and St. Lawrence Rivers during FY 90. 
During the winter months, the District monitors the presence 
and intensity of ice in the St. Marys, St. Clair, and Detroit 
Rivers as an ongoing mission. Water levels are monitored continuously 
at key gages in these rivers for automated updating 
of hydrographs used for detecting possible ice jams and the 
associated potential for flooding. This information can be 
used to provide advance warning to area residents and to trigger 
emergency actions by the Corps and other governmental 
agencies (in support of respective Flood Alert Plans). Currently, 
data can be obtained from water level gages via direct 
communication with the gages or from a satellite downlink station 
using portable lap-top personal computers. This provides 
water level data from critical sites to the District office within 
minutes of data collection. 
International Activities. The following activities were conducted 
specifically for the International Joint Commission 
(IJC) Boards and Committees: 
Members of the Detroit District staff attended the spring 
semi-annual appearances of the International Great Lakes 
Boards before the Commission in Washington, D.C. 
As a result of the record high Great Lakes levels in 1985-86, 
and the prospects of even higher levels in 1987, the governments 
of the United States and Canada issued the IJC a Reference, 
on August 1, 1986, requesting a new water level study. 
Under this study, the IJC was asked to examine and report 
upon methods of alleviating the adverse consequences of fluctuating 
water levels in the Great Lakes-St. Lawrence River 
basin. As previously indicated, the water levels of the lakes 
were at or near recorded highs for this century. This led to an 
initial emphasis on high water levels and interim emergency 
actions which could be taken to aid interests harmed or threatened. 
This led to the creation of an interim task force, which 
was charged with completing a study within one year. Personnel 
from the Great Lakes Hydraulics and Hydrology Branch of 
the Detroit District headed several of these tasks and were 
involved in preparing many of the group findings and recommendations. 
Although water levels descended dramatically in 
1987, the main study commenced. In addressing potential 
measures for alleviating the adverse effects of water level fluctuations, 
the study groups will identify and provide advice on 
crisis intervention, intermediate measures and long-term considerations, 
building on, as appropriate, the work of the Commission's 
task groups. Once the study is completed the governments 
should be in a better position to make a determination 
regarding management of the Great Lakes. 
Because of the complexity of the issues being addressed during 
the Reference Study, the bulk of the work, which is 
expected to require several years of effort, has been assigned to 
functional study groups, each with a responsibility to play a 
lead role with respect to a group of related tasks. The work 
activities of each group, in turn, frequently requires integration 
and close collaboration with work activities of the other 
groups. The magnitude of this study requires that it be 
addressed in two phases. Phase I, which was completed in May 
1989, identified the major types of measures, which address 
the problems brought on by lake level fluctuations, and developed 
a comprehensive framework for the systematic evaluation 
of these measures. The IJC reviewed the work of the functional 
groups and issued their Phase I progress report in July 
1989. This report was titled, "Living With the Lakes: Challenges 
and Opportunities" In FY 89, the Detroit District continued 
to be heavily involved in providing support to several of 
the study groups under Phase I, in particular, Functional 
Group 1 - Hydraulics, Hydrology and Climate. Phase II, with 
a final report to the IJC due in September 1991, will apply the 
evaluation procedure in detail to specific selected measures 
identified in Phase I. Although this effort has not yet started, it 
is expected that it will be formulated and staffed before the end 
of FY 90. 
a. International Lake Superior Board of Control. The 
Detroit District Engineer is the United States Regulation Representative 
of the Board of Control. In support of the U.S. 
Section of the Board, the District provided monthly Lake 
Superior outflow recommendations based upon a review of the 
hydrologic factors which influence the future regulation of 
Lake Superior. These recommendations were based on the use 
of probability forecasts of water supplies routed through the 
lakes, rendering outflows under Plan 1977, the currently 
approved operating rule. 
The Board has sought to update the current regulation plan 
to include such things as: an additional decade of water level 
data; an increase in outflow capacity following construction of 
a new powerhouse by Great Lakes Power Limited, Canada; 
and the additional knowledge gained since Plan 1977 has been 
in effect. The Board submitted to the IJC for approval an 
updated and revised edition of Plan 1977 in October 1989. It is 
expected that further Plan modification will be explored by the 
Detroit District under its association with the IJC's Reference 
Study. 
During FY 89, a series of discharge measurements were 
made at the St. Marys River Compensating Works as part of a 
program to verify the existing gate rating equations or to establish 
new ones. A second series of measurements at the Compensating 
Works is scheduled for FY 90. Further measurements 
may be required in order to obtain adequate data. 
21-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
b. International Niagara Board of Control and International 
Niagara Working Committee. The Chief of the Great 
Lakes Hydraulics and Hydrology Branch is on the U.S. Section 
of the Working Committee. Under the auspices of the 
International Niagara Committee, the Detroit District computes, 
coordinates and publishes, with Canada, the monthly 
flows in the Niagara River. The District also provides direct 
technical support and consulting engineering services to the 
Board and Committee. During FY 89, a series of discharge 
measurements were made at the International Bridge Section 
for verification of Lake Erie outflow equations. Additional 
measurements are planned at this section in FY 90 and 91. Due 
to the dynamic nature of the Niagara River, the District is 
involved with the periodic verification of the rating curves for 
the Ashland Avenue and American Falls gages. The Ashland 
Avenue relationship measures the flow over the falls to ensure 
that the Board operates within the terms of the Niagara Treaty. 
The American Channel relationship provides a measure of the 
flow over only the American Falls. As part of the ongoing programs 
to periodically verify the stage-discharge relationships 
for these gages, discharge measurements were made in FY 89. 
c. International St. Lawrence River Board of Control. 
When requested, the Detroit District supported the Buffalo 
District in its activities. In FY 87 and 88, the Detroit District 
conducted an intensive flow measurement program in the 
Copeland Cut reach of the St. Lawrence River to collect data 
to be used for development of a mathematical model of critical 
sections in the river, and also for proposed physical models. In 
FY 90, the Detroit District will perform an additional drogue 
study in the river. In FY 92 and FY 93, further flow distribution 
measurements will be made to calibrate the existing mathematical 
model of the river. During FY 89, personnel from the 
Detroit District were requested to review specific aspects of 
Plan 1958-D, the present outflow regulation plan for Lake 
Ontario, and look at ways of optimizing the outlet conditions 
employed in the Plan. 
d. International Great Lakes Diversions and Consumptive 
Uses Study Board. The IJC submitted its recommendations, 
based on the Board's report and subsequent public hearings, to 
the governments of the United States and Canada, in a report 
dated January 1985. A former Detroit District Engineer was 
Chairman of the U.S. Section of the Working Committee. 
Until such time as the Board is either dissolved or continued, 
certain personnel within the District continue to hold membership 
on the Diversions and Environmental Evaluation Subcommittees 
and on the Public Involvement Ad Hoc Group. In 
an action related to the efforts of this Board, a cooperative 
study, by the Council of Great Lakes Governors Water 
Resources Management Committee and the U.S. Geological 
Survey (USGS), was conducted to investigate, evaluate and 
compare water-use data in the Great Lakes basin. Personnel 
from the Detroit District were contacted for consultation services 
with respect to Great Lakes computer models. A report 
was produced by the USGS in 1986. In matters related to the 
IJC Reference Study, in FY 89, the USGS provided District 
personnel with updated Great Lakes consumptive uses data. 
Throughout the Reference Study the District is expected to 
continue with its support relating to the evaluation of consumptive 
uses. 
e. International Great Lakes Technical Information Network 
Board. Although the Board is inactive at this time, the 
Chief of the Great Lakes Hydraulics and Hydrology Branch 
remains the Secretary to the U.S. Section, as well as a member 
of the Hydraulics and Hydrology Committees. The Board 
completed its study and provided a report of its findings and 
recommendations to the Commission in December 1984. In 
January 1985, the IJC informed the governments of the United 
States and Canada of the findings of the Board. One of the recommendations 
of this Board, to create a modeling group, has 
been adopted by the Coordinating Committee and is described 
below. 
Coordinating Committee on Great Lakes Basic Hydraulic 
and Hydrologic Data. The Chief of the Great Lakes Hydraulics 
and Hydrology Branch is the U.S. Secretary to this Committee, 
as well as a member of its several subcommittees. A 
new subcommittee was created in FY 89, the Hydrometeorology 
and Modeling Subcommittee. The first efforts of this subcommittee 
are to update the Great Lakes Hydrometeorological 
Station Directory and to prepare a models inventory. The 
directory update is expected to be completed in FY 90. Committee 
operations continued pertaining to the coordination of 
basic hydraulic and hydrologic data with Canada. In FY 89, 
efforts were begun to more closely coordinate the format of 
the U.S. and Canadian water level bulletins, in order to avoid 
confusion and to better inform the public. Suggested changes 
are being considered and reviewed by this Committee. Work 
continues on a report which will document all the discharge 
measurements (U.S. and Canadian) made on the Great Lakes 
Connecting Channels and St. Lawrence River during the period 
1860 to present. Through the auspices of the Coordinating 
Committee, the Corps of Engineers, by 1983, had provided 
funds to Canada, in the amount of $215,000, to aid in completion 
of precise leveling in the International Section of the St. 
Lawrence River. This survey, as well as similar surveys conducted 
in the U.S. by NOAA, are part of a program to update 
the International Great Lakes Datum (IGLD). The new IGLD 
will evolve around the epoch year 1985 and is expected to be 
published in early FY 91. 
NCD Master Plan for the Water Control Data System. During 
FY 89, the District continued to implement the Great Lakes 
Water Control Data System, using a Harris-800 minicomputer 
and an extensive system of automated gaging stations. The 
computer collects data from the District's data collection platforms 
(DCP's), from dedicated lines to the National Weather 
Service's telecommunication network, and from NOAA/NOS 
and Canadian water level computer systems. The District has 
29 active DCP's and plans to install as many as three additional 
DCP's in the near future. 
Great Lakes Information Management. The District, in FY 
89, continued development of computer mapping capabilities 
centered around dedicated computer hardware and software 
for processing satellite and aerial photography and encoded 
mapped information into a Geographic Information System 
(GIS) for the U.S. portion of the Great Lakes. The GIS is being 
generated to contain multiple information layers on the physiographic, 
economic, sociologic, environmental, and hydrologic 
characteristics of the Great Lakes region. The GIS is 
designed to create a "corporate data base" to support various 
District operations and studies, including improved monitoring 
of hydrometeorologic conditions over the basin. 
Hydraulics and Hydrology of the Great Lakes. Studies to 
improve the existing Great Lakes water level forecasting system, 
including investigation into the factors affecting the 
Great Lakes water balance relationship (i.e., runoff, over 
water precipitation, evaporation, ice retardation, etc.) and use 
of real-time hydrologic data, were continued by Great Lakes 
21-30

DETROIT, MI DISTRICT 
Hydraulics and Hydrology Branch staff members. Hydrologically 
based computer models are being calibrated and tested 
for each of the Great Lakes for possible use in simulating water 
supply conditions, forecasting water levels and regulating the 
outflows from Lakes Superior and Ontario. District personnel, 
in cooperation with National Weather Service personnel, 
are continuing to assess water supply conditions over both 
Lakes Superior and Ontario, through use of airborne snow 
and soil moisture surveys, and processed satellite imagery. 
Levels of the Great Lakes. The Great Lakes Hydraulics and 
Hydrology Branch provided technical information and expertise 
regarding recorded lake levels and still water lake level 
forecasts to many interested parties, such as Congressmen, 
state and local officials, news media, navigation and power 
interests, concerned property owners and recreational boaters. 
Upon request, water level information was supplied to the 
public in the form of direct answers to numerous inquiries, 
addresses to various civic groups, and interviews with the news 
media. Currently, daily reports on present water levels, precipitation 
and significant events on the Great Lakes basin, are 
being made available on the District's Harris-800. Historical 
water level data is also available on this system. Those agencies 
and individuals interested can retrieve this information at any 
time via a telecommunication device. The publication of an 
internationally coordinated (U.S. and Canada) forecast of 
Great Lakes water levels, under the auspices of the Coordinating 
Committee on Great Lakes Basic Hydraulic and Hydrologic 
Data, was continued during the period. The circulation in 
the U.S. alone is about 13,000 copies. 
Total costs under Surveillance of Northern Boundary 
Waters for FY 89 were $1,458,207. 
General Investigations 
83. SURVEYS 
Fiscal year costs were $12,377 for the navigation study on 
the Great Lakes Connecting Channels and Harbors 
(GLCC&H). Pre-construction Engineering and Design work 
activities were outlined and are scheduled to be initiated in FY 
90, and completed in FY 92. Preparation of the Chief of Engineers 
report continued. The city of Superior, WI, elected to not 
provide a willingness to sponsor the Superior Harbor portion 
of the project. Flood Damage Prevention studies cost 
$834,370. Funds in the amount of $13,083 were expended on 
coordinating the Ecorse Creek Basin, Wayne County, Flood 
Protection Study. In addition, $2,461 were spent in coordinating 
work efforts on a Summary Report dealing with the overall 
study authority for the Great Lakes, particularly Lake Ontario 
and Lake Erie, of which Ecorse Creek is an Interim study. 
Funds in the amount of $120,361 were used to prepare a 
Reconnaissance Report for Southern Wayne County, MI. 
Continuation of the Saginaw River, MI, Basin Study was 
accomplished at a cost of $531,142. The St. Joseph River, MI, 
Basin Study continued at a cost this FY of $167,323. 
Coordination Studies with Other Agencies includes: 
Special Investigations, $88,347 (includes $74,347 for engineering 
and technical assistance given to local citizens because 
of fluctuating lake levels of the Great Lakes; F.E.R.C., $2,000; 
Interagency Water Resources Development, $12,000). Soil 
Conservation Service, $2,000; and Planning Assistance to 
States (Section 22), $136,700 (includes $75,000- MN, $59,700- 
MI). 
Funds in the amount of $91,701 for Fox River, WI, and 
$41,317 for the Inland Route, MI, were expended to continue 
the restudy of Federal interest under Section 216. 
84. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
MONROE HARBOR, MI: 
A Final Survey Report recommending structural modifications 
was completed in February 1980. The report recommendations 
are: to deepen the River Raisin portion of the project to 
27 feet; to widen to 500 feet and deepen to 28 feet the entrance 
channel from Lake Erie; to provide a new turning basin able to 
accommodate 1,000 foot vessels; and to construct a confined 
disposal facility that would create a 700 acre marsh and provide 
shoreline protection behind the disposal facility. 
The Monroe Harbor Study was included in the FY 1984, 
1985, and 1986 budgets under the category "Continuation of 
Planning and Engineering" for the purpose of collecting 
updated and detailed project data, reevaluating project channel 
dimensions and dredged material disposal requirements, 
reaffirming project economic and environmental feasibility, 
and preparing preliminary project design. A reevaluation 
report was completed in FY 89, and is under review at North 
Central Division. The report proposes a reduction in the recommended 
channel width and depth, and proposes open water 
disposal of the dredged materials. FY 89 costs for continuing 
preconstruction engineering and design for Monroe Harbor, 
MI, were $122,458. 
DULUTH-SUPERIOR HARBOR, MN-WI: 
A Final Survey Report recommending a commercial navigation 
project at Duluth-Superior Harbor, MN-WI, was completed 
in November 1982. The report recommends deepening 
approximately 4.0 miles of navigation channels (North, South, 
Upper, and Minnesota Channels) in the St. Louis River to a 27 
foot project depth, widening the Cross Channel turning basin 
to 1,500 feet, widening the bend at the site where the Arrowhead 
Bridge was removed to 600 feet and disposing the dredged 
material in an upland confined disposal site located on a 120- 
acre tract of land in the Superior Forest. 
FY 1989 costs for continuing the General Design Memorandum 
for Duluth-Superior Harbor, MN-WI, were $280,662. 
FORT WAYNE, IN 
The Final Feasibility Report (FFR) and Final Environmental 
Impact Statement (FEIS) were completed by the District in 
August 1987 and revised in April 1988. The Recommended 
Plan provides for upgrading, to a 100-year level of protection, 
approximately 35,000 feet of existing levees and floodwalls. 
On September 14, 1988, the FFR/FEIS, BERH Report was 
forwarded to the Chiefs office. The Chief of Engineers Report 
was forwarded to the Secretary of the Army on May 1, 1989. 
The FY 89 cost for Fort Wayne, IN, was $575,691. 
85. COLLECTION AND STUDY OF 
BASIC DATA 
FY 89 costs for International Water Studies were $25,000, 
and $233,938 for Flood Plain Management Services. 
Flood Insurance Studies. Six Flood Insurance Studies were 
completed in FY 89 for Sheboygan County, WI; and the Michigan 
communities of Ann Arbor City, Washtenaw County; 
Hersey Village, Osceola County; Lincoln Township, Newaygo 
County; Kalamazoo City, Kalamazoo County; and Wyoming 
City, Kent County. The studies were completed at a total cost 
of $190.313. The FY 89 costs for the six studies were $129, $1, 
21-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
$15,036, $14,801, $34,616, and $33,232, respectively. Michigan 
Flood Insurance Studies for Georgetown Township, 
Ottawa County; Lapeer City, Lapeer County; and Thomas 
Township, Saginaw County will be completed in FY 90. The 
FY 89 costs associated with these studies were $30,205, $8,613, 
and $6,234, respectively. FY 89 coordination costs for the 
Michigan communities of Adrian Township, Lenawee 
County; City of Three Rivers, St. Joseph County; Manistee 
Township, Manistee County, and Northfield Township, 
Washtenaw County, were $923, $195, $283, and $340, respectively. 
Final coordination meetings were held on completed 
Flood Insurance Studies for Allen County, IN; and the Michigan 
communities of Armada City, Macomb County; Clare 
City, Clare County; Holland City, Ottawa County; Lapeer 
Township, Lapeer County; and Mayfield Township, Lapeer 
County. The FY 89 costs for these activities were $975, $2,180, 
$73, $28, $465, $214, and $387, respectively. 
Costs in FY 89 in support of the Federal Emergency Management 
Agency's Community Assistance Program, limited 
map maintenance program, and a special study on Great Lakes 
wave runup methodology were $29,088, $34,721, and $73,993, 
respectively. 
A Dam Break Analysis for Bloomer Dam, WI, was completed 
for the St. Paul District at a cost of $12,233. 
21-32

DETROIT, MI DISTRICT 
TABLE 21-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
2. Arcadia Harbor, New Work 
MI Approp. 0 - - - 0 
Cost 0 - - - 0 
Maint. 
Approp. 117,000 433,000 272,000 2,134,000 4,094,362 
Cost 144,618 387,088 283,253 2,158,207 4,083,366 
3. Ashland Harbor, New Work 
WI Approp. - - - - 1,695,645 
Cost - - - - 1,695,645 
Maint. 
Approp. 115,000 364,948 9,528 87,254 3,072,078 
Cost 129,603 360,246 14,231 82,952 3,067,776 
4. Au Sable Harbor, New Work 
MI Approp. - - - - 209,776' 
Cost - - - - 209,776' 
Maint. 
Approp. - - 89,697 7,000 2,571,565 
Cost - - 35,364 61,333 2,571,565 
5. Bayport Harbor, New Work 
MI Approp. - - - - 93,597 
Cost - - - - 93,597 
Maint. 
Approp. - - - 49,346 121,283 
Cost - - - 49,346 121,283 
Diked 
Disposal 
Approp. - - - - 792 
Cost - - - - 792 
6. Big Suamico River, New Work 
WI Approp. - - - - 20,243 
Cost - - - - 20,243 
Maint. 
Approp. 8,757 16,557 128,974 449,293 770,186 
Cost 8,757 16,557 128,282 449,985 770,186 
7. Black River (P.H.) New Work 
MI Approp. - - - - 830,1652 
Cost - - - - 830,1652 
Maint. 
Approp. - - 22,071 66,435 600,9473 
Cost - - 18,414 69,106 599,961P 
8. Black River Harbor, New Work 
MI (U.P.) Approp. - - - - 383,350 
Cost - - - - 383,350 
Maint. 
Approp. (6,000) - 147,000 (14,000) 711,423 
Cost 8,645 1,410 135,450 (2,480) 711,393 
9. Bolles Harbor, New Work 
MI Approp. - - - - 426,413^ 
Cost - - - - 426,413' 
Maint. 
Approp. 167,964 222,422 377,499 (1,000) 1,669,762 
Cost 153,415 143,902 335,703 141,632 1,669,760 
Diked 
Disposal 
Approp. - - - - 1,190,550 
Cost - - - - 1,190,550 
21-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
10. Charlevoix Harbor, New Work 
MI Approp. - - - - 180,623 
Cost - - - - 180,623 
Maint. 
Approp. 182,000 253,000 1,080,000 1,523,000 7,909,900 
Cost 154,568 251,394 1,115,167 1,528,061 7,908,863 
Rehab. 
Approp. 0 - - - 1,129,396 
Cost 0 - - - 1,129,396 
11. Clinton River, New Work 
MI Approp. - - - - 549,798' 
Cost - - - - 549,798' 
Maint. 
Approp. 8,662 89,661 19,248 122,935 1,255,303 
Cost 8,662 89,661 14,342 126,559 1,254,021 
Diked 
Disposal 
Approp. 71,000 261,000 2,219,000 966,100 3,907,300 
Cost 72,663 237,122 2,098,062 1,109,377 3,899,262 
12. Detour Harbor, New Work 
MI Approp. - - - - 1,354,910 
Cost - - - - 1,354,910 
Contributed Funds New Work 
Approp. - - - - 1,204,436 
Cost - - - - 1,204,436 
Maint. 
Approp. 3,752 22,320 99,664 4,500 136,260 
Cost 4,118 12,331 104,437 9,716 136,260 
13. Detroit River, New Work 
MI Approp. - - - - 76,877,3576 
Cost - - - - 76,877,357' 
Maint. 
Approp. 3,446,800 4,017,500 2,714,000 3,680,100 83,005,424 
Cost 4,109,489 4,030,841 2,673,764 3,709,048 82,934,502 
Diked 
Disposal 
Approp. 0 - - 768,600 42,169,294 
Cost 1,383 54 - 765,570 42,163,234 
Contributed Funds Maint. 
Approp. 242,280 72,612 46,343 - 361,235 
Cost 203,000 89,344 68,891 - 361,235 
14. Duluth-Superior Harbor, New Work 
MI and WI Approp. - - - - 16,109,258' 
Cost - - - - 16,109,258' 
Maint. 
Approp. 1,973,700 2,219,700 3,694,400 2,665,000 43,961,370 
Cost 1,945,302 2,304,284 3,699,515 2,684,950 43,934,387 
Diked 
Disposal 
Approp. - - - - 1,556,249 
Cost - - - - 1,556,249 
Rehab. 
Approp. 4,830,000 3,773,000 (55,000) - 10,958,000 
Cost 4,773,781 3,930,167 (63,083) 18,330 10,950,873 
15. Eagle Harbor, New Work 
MI Approp. - - - - 205,164 
Cost - - - - 205,164 
Maint. 
Approp. - - - 2,000 87,946 
Cost - - - 1,948 87,894 
21-34

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
16. Fox River, WI 
17. Frankfort Harbor, 
MI 
18. Grand Haven Harbor, 
MI 
Section 111 
Section 111 
Contributed Funds 
19. Grand Marais Harbor, 
MI 
20. Grand Marias Harbor, 
MN 
21. Grand Traverse Bay 
Harbor, MI 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,063,000 1,246,100 1,545,000 1,383,000 
1,064,843 1,251,433 1,565,066 1,355,554 
45,000 150,999 25,000 74,449 
49,296 150,723 21,193 80,360 
615,700 673,200 672,100 979,000 
615,944 670,055 654,999 993,902 
1,181,500 91,000 69,000 65,000 
1,204,587 92,608 67,261 60,379 
- - - 27,936 
- - -5,643 
1,079,000 (16,000) (17,336) 
1,071,033 (3,820) 18,064 
0 89,000 43,000 
0 87,584 37,660 
10,409 
10,909 
23,000 
29,756 
21-35 
3,753,3343 
3,753,3343 
41,069,773' 
41,027,115' 
1,955,1590 
1,955,15910 
6,529,345 
6,528,291 
274,776 
274,776 
1,204,500 
1,204,500 
1,283,469" 
1,283,469" 
175,000 
175,000 
22,708,455" 
22,699,614 '2 
813,613 
813,613 
780,400 
780,400 
1,958,684 
1,951,319 
27,200 
15,585 
1,055,871 
1,055,871 
1,740,956 
1,718,663 
450,972 
450,972 
1,991,952 
1,991,952 
1,230,000 
1,230,000 
266,037 
266,037 
1,729,653 
1,729,653

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
22. Green Bay 
Harbor, WI 
23. Harbor Beach 
Harbor, MI 
25. Holland Harbor, 
MI 
Section 111 
Section 111 
26. Inland Route, 
MI 
27. Kenosha Harbor, 
WI 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Total Cost 
to 
FY86 FY87 FY88 FY89 Sept. 30, 1989 
- - - - 9,946,395' "' 
- - - - 9,946,395'"' 
1,761,000 1,299,000 2,562,000 2,796,200 
1,604,864 1,384,841 2,630,676 2,803,935 
290,000 205,000 25,000 
310,913 205,760 23,982 
0 
402 
313,949 295,641 2,651,100 330,900 
310,694 252,600 2,671,991 363,060 
507,000 
484,876 
694,000 
828.919 
86,000 
60,666 
454,000 
472,285 
80,000 
74.093 
1,137,600 
1,096,765 
49,500 
58.655 
3,915,000 
3,961,525 
22,000 
19,829 
64,000 74,000 46,000 
85,167 60,411 63,861 
22,620,435" 
22,593,934'" 
6,813,807 
6,808,908 
1,200,598 
1,200,598 
9,316,980 
9,314,671 
194,504 
194,504 
243,100 
243,100 
771,827 " ' 7 
771,827'"67 
621,000 
621,000 
17,913,312 
17,910,881 
1,611,700 
1,607,930 
502,452 
502,452 
1,663,300 
1,663,300 
918,222'" 
918,222'1 
2,415,888 
2,411,272 
404,300 
404,300 
8,077 
208,000 
168,916 
1,072 
1,182,600 
1,206,019 
352,000 216,200 
351,863 232,834 
988,969 
' 19.2 
988,96919.20 
4,711,6682' 
4,711,0472' 
1,270,275 
1,270,275 
4,378,600 
4,378,600 
21-36

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
28. Kewaunee Harbor, 
WI 
29. Keweenaw 
Waterway, MI 
30. Lac Labelle Harbor, 
MI 
31. Lake St. Clair, 
MI, Channels 
32. Leland Harbor, 
MI 
33. Lexington 
Harbor, MI 
Contributed Funds 
Section 111 
Section 111 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
243,000 172,000 954,200 559,500 
225,007 159,073 962,764 562,078 
681,000 2,822,000 584,000 4,588,700 
668,439 2,777,736 631,023 4,564,738 
241,000 855,000 162,500 
220,193 875,855 150,762 
15,000 
30,149 
- - - 73,000 
- - - 73,000 
262,600 103,000 256,000 54,100 
260,663 105,926 225,803 100,244 
100,000 105,000 135,000 129,500 
104,735 100,159 138,200 128,479 
- 49,000 
- 22,997 
260,000 88,000 
407,397 92,307 
194,000 
210,048 
115,000 
32,489 
10,000 
19,955 
294,000 
375,817 
21-37 
758,33322 
758,33322 
5,239,291" 
5,219,22723 
617,300 
617,300 
2,961,461 
2,961,461 
5,974,141 
5,974,141 
19,546,38324 
19,494,65524 
1,523,500 
1,523,500 
269,270 
269,270 
554,994 
554,994 
7,675,35725 
7,675,35725 
7,568,18426 
7,566,76426 
5,119,800 
5,119,800 
1,027,08927 
1,027,08927 
1,883,011 
1,879,808 
70,678 
70,678 
1,646,304 
1,646,304 
1,088,888 
1,088,888 
372,000 
372,000 
377,044 
377,044 
1,211,000 
1,209,784

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
34. Little Lake 
Harbor, MI 
35. Ludington Harbor, 
MI 
Section 111 
Section 111 
36. Mackinac Island 
Harbor, MI 
Contributed Funds 
37. Manistee Harbor, 
MI 
38. Manistique Harbor, 
MI 
39. Manitowoc 
Harbor, WI 
Contributed Funds 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
263,000 165,600 216,000 162,500 
279,129 166,243 221,928 163,102 
329,000 1,743,000 566,000 150,500 
337,698 1,764,395 565,357 132,183 
(64,000) 41,800 11,000 
(46,931) 40,390 13,086 
22,274 136,000 1,580,300 
22,023 59,616 1,656,661 
10,000 
2,769 
2,000 
2,274 
816,000 777,000 299,000 454,000 
791,534 784,446 313,522 458,202 
- - 39,436 172,400 
- - 39,435 168,966 
296,000 283,000 213,000 134,000 
300,389 297,160 220,309 134,498 
21-38 
600,4782" 
600,4782" 
3,312,615 
3,311,290 
7,912,2022"9 
7,912,20229 
620,000 
620,000 
10,866,066"' 
10,839,260' 
357,913 
357,913 
724,340 
717,109 
229,085 
229,085 
105,004 
105,004 
1,812,044 
1,812,044 
2,696,522"' 
2,696,522"' 
6,684,73332 
6,683,0582 
1,374,164 
1,374,164 
1,299,355" 
1,299,355" 
2,082,630 
2,079,195 
316,333 
316,333 
2,048,91434 
2,048,9143" 
1,911,130 
1,911,130 
5,557,515" 
5,553,254" 
3,081,756 
3,081,756

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
40. Marquette 
Harbor, MI 
41. Menominee 
Harbor & River, 
MI & WI 
Contributed Funds 
42. Milwaukee 
Harbor, WI 
43. Monroe Harbor, 
MI 
Contributed Funds 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Diked- 
Disposal 
Approp. 
Cost 
204,384 184,646 9,188 
204,324 185,349 8,369 
6,741 
7,810 
104,000 149,886 26,000 114,500 
109,403 149,204 29,387 115,121 
1,282,893 
1,282,893 
2,007,856 
2,007,856 
465,757 
465,757 
533,476" 
533,4763 
2,074,840 s: 
2,071,73637 
1,351,852 
1,351,852 
(10,000) 
2,288 
440,000 
399,452 
3,205,000 
3,189,537 
593,660 
591,014 
36,762 
36,762 
2,783,000 
2,753,156 
1,235,000 
1,229,552 
540,300 
608,059 
3,592,400 
3,537,129 
442,400 
426,799 
784,000 
901,866 
1,640,900 1,576,000 1,289,500 514,800 
1,700,939 1,577,775 1,133,479 699,862 
(17,000) 
(23,493) 
(1,000) (6,500) 
34,881 (1,077) 
8,231,02438 
8,231,02438 
28,361,9753' 
28,340,54039 
12,718,210 
12,690,646 
6,380,925 
6,380,925 
987,340" 
987,340� 
16,158,420" 
16,154,808� 
- (1,818) 
- 5,442 
0 38,614,400 
0 38,614,391 
83,182 
83,182 
21-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
44. Muskegon Harbor 
MI 
Section 111 
Section 111 
45. New Buffalo 
Harbor, MI 
Contributed Funds 
46. Ontonagon Harbor, 
MI 
47. Pentwater Harbor, 
MI 
48. Point Lookout 
Harbor, MI 
Contributed Funds 
49. Portage Lake 
Harbor, MI 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
86,000 
89,926 
1,593,000 
1,602,842 
1,337,300 
1,468,604 
526,000 
664,118 
83,000 
77,669 
916,000 
919,158 
80,000 532,000 245,000 
77,241 533,537 242,196 
45,000 70,000 305,700 
58,390 29,843 337,972 
60,000 
84,085 7,832 
0 
804 
5,000 398,371 109,800 
10,057 386,063 121,175 
56,000 
48,354 
443,600 
420,997 
3,000 
10,824 
573,700 
563,053 
8,000 
18,525 
691,000 
701,989 
194,666 221,000 288,000 261,500 
194,467 222,504 283,769 268,761 
1,701,100 33,991 266,980 
1,882,296 35,484 259,915 
(2,743) 
606 
120,385 
125,487 
21-40 
30,000 
40,242 
13,854 9,292 249,400 
14,664 6,406 226,286 
2,912,110"' 
2,912,110 ' 
105,000 
105,000 
6,301,11542 
6,295,52412 
2,324,700 
2,316,815 
13,824,300 
13,824,300 
1,285,716 
1,285,716 
1,186,467 
1,186,467 
3,311,324 
3,308,119 
953,90343 
952,170^5 
9,388,853" 
9,354,487" 
181,500 
181,500 
21,000 
21,000 
179,899 
179,899 
3,795,755 
3,794,364 
2,642,584 
2,642,584 
3,269,161 
3,269,161 
121,600 
121,600 
9,257 
9,257 
256,129 
256,129 
1,823,763 
1,797,763

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
50. Port Austin 
Harbor, MI 
51. Port Sanilac 
Harbor, MI 
Contributed Funds 
Section 111 
Contributed Funds 
Section 111 
52. Port Washington 
Harbor, WI 
Contributed Funds 
53. Port Wing Harbor, 
WI 
54. Rouge River, 
MI 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
52,000 50,000 100,000 1,245,000 
50,753 5 87,191 1,272,186 
60,613 (62,502) 106,867 79,824 
544,368 (55,855) 38,044 140,401 
1,772 177,000 128,101 
8,676 51,263 242,404 
87,000 
92,717 
- 207,000 6,000 (1,000) 
185,852 45,478 157,407 11,545 
- - - 106,506 
- - - 106,506 
- 78,935 
- 78,216 
3,598 
4,140 
711,700 2,685,000 ,(82,000) 817,500 
694,589 2,673,425 (50,114) 827,076 
329 
- - 247,000 
12 174 246,608 
21-41 
2,575,334" 
2,538,469'5 
1,749,822 
1,741,556 
159,000 
159,000 
909,963 
909,963 
487,108 
487,108 
336,000 
336,000 
1,967,286 
1,961,568 
115,000 
115,000 
9,158 
9,158 
1,014,000 
1,014,000 
2,582,204" 
2,582,204" 
2,564,12147 
2,564,121" 
10,621 
10,621 
1,624,000 
1,624,000 
63,393 
63,393 
877,118 
876,941 
675,251" 
675,251" 
19,168,103" 
19,166,277" 
14,770,823 
14,763,825

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
55. Saginaw River, 
MI 
(Federal Funds) 
(Contributed Funds) 
56. St. Clair River, 
MI 
57. St. Joseph 
Harbor, MI 
Section 111 
Section 111 
58. St. Marys 
River, MI 
59. Saugatuck 
Harbor, MI 
and Kalamazoo 
River, MI 
60. Saxon Harbor, 
WI 
Section 111 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
626,200 2,548,000 1,937,000 
680,370 2,422,846 2,052,297 
1,642,100 
1,634,544 
182,500 126,000 80,000 188,000 
207,953 149,558 71,832 198,388 
816,100 1,527,000 1,927,100 573,500 
863,958 1,519,667 1,874,080 605,737 
611,000 647,000 3,406,700 527,100 
591,221 670,265 3,301,795 633,865 
- - (5,700) 
14,595 868 (5,700) 
730,000 387,000 465,000 
632,995 520,434 244,935 
00 
74,800 
331,988 
- 160,657,071l" 
- 160,657,070"' 
9,704,800 9,934,400 14,288,300 
9,761,729 9,497,511 14,783,035 
10,527,500 
10,499,775 
78,559 29,270 156,161 134,973 
95,146 26,250 152,608 88,532 
(1,130) - - - 
477 - - - 
2,237 
25,098 
21-42 
15,191 50,000 158,500 
2,434 59,766 135,491 
14,917,1275 
14,917,127" 
13,600 
13,600 
38,876,394 
38,848,145 
19,579,900" 
19,579,713"5 
19,213,24652 
19,213,24652 
18,848,513 
18,805,372 
976,485 
976,485 
828,000 
828,000 
12,765,264 
12,758,766 
962,216 
962,216 
638,076 
638,076 
4,272,100 
4,272,100 
211,317,308 
210,791,877 
13,100 
13,100 
364,5275" 
364,527" 
3,322,690" 
3,269,520" 
426,507" 
426,507" 
667,870 
667,870 
639,293 
613,293

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
61. Sebewaing River, 
MI 
62. Sheboygan 
Harbor, WI 
63. South Haven 
Harbor, MI 
Section 111 
Section 111 
64. Sturgeon Bay, WI 
& Lake Michigan 
Ship Canal, WI 
65. Two Harbors, 
MN 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 230,400 396,176 522,051 
- 111,517 366,111 670,660 
327,000 301,000 217,000 61,500 
363,502 251,568 267,383 61,112 
(15,000) 
9,231 64 
87,000 197,335 65,000 116,500 
84,580 194,378 85,519 116,801 
312,000 
669,316 3,198 3,584 
13,000 
13,725 
176,000 141,300 269,500 246,000 
346,931 121,157 266,195 271,429 
11,953 1 - 
- 24,521 157,000 160,722 
- 13,315 120,516 203,960 
21-43 
35,573 
35,573 
3,438,060 
3,437,722 
1,136,08857 
1,136,0885' 
5,390,892" 
5,390,300" 
609,028 
609,028 
907,792 
907,792 
452,42659 
452,426" 
532,000 
532,000 
3,863,301" 
3,863,001 
1,632,076 
1,632,076 
42,381 
42,381 
1,157,000 
1,154,164 
1,059,722" 
1,059,7226' 
7,755,41562 
7,752,76162 
311,119 
311,119 
884,899 
884,899 
4,170,710'3 
4,170,71063 
2,247,436 
2,242,984

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
66. Two Rivers 
Harbor, WI 
67. Whitefish Point 
Harbor, MI 
68. White Lake 
Harbor, MI 
Section 111 
Section 111 
76. Paw Paw Lake, MI 
77. Saginaw River, 
MI 
(Federal Funds) 
(Contributed Funds) 
78. Sebewaing River, 
MI 
82. Surveillance Of 
North Boundary 
Waters 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Diked 
Disposal 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
21,978 
21,017 
23,416 7,174 159,992 
15,445 26,713 134,581 
- - - 14,772 
- - - 14,772 
98,000 95,000 139,000 166,900 
98,248 91,872 141,570 170,793 
389,000 
429,111 
49,000 11,000 23,000 
53,483 8,936 23,587 
2,900,000 125,000 (3,000) 
2,777,125 263,233 10,599 
57,336 
9,000 
16,224 
- 260,000 
44,928 19,298 
5,000 4,000 
8,000 4,000 
0 
1,358
0 
148,628 
7,500 
7,243 
1,330,000 1,230,000 1,435,000 1,440,000 
1,308,778 1,278,991 1,372,820 1,458,207 
360,320" 
360,320" 
5,576,648"' 
5,550,648"' 
1,187,472 
1,187,472 
58,057 
58,057 
771,639 
771,639 
251,027 
251,027 
1,081 
1,081 
207,862 
207,862 
249,700 
249,700 
2,559,363 
2,559,063 
734,000 
729,156 
3,589,000 
3,589,000 
24,813,359 
24,715,090 
173,000 
172,997 
365,642" 
365,642" 
408,144 
407,887
0
0 
44,329,3346" 
44,252,216"7 
21-44

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
'Includes $114,786 for previous projects. 
2 Includes $85,849 for previous projects. 
Includes $12,008 for maintenance of previous projects. 
'Includes $255,000 contributed funds. 
SIncludes $25,500 for previous projects and $289,752 contributed 
funds for existing projects. 
' Includes $2,097,254 for previous projects. 
' Includes $1,547,195 for new work for previous projects. 
" Includes $3,239,910 for previous projects. 
Includes $89,309 for previous projects. 
'O Includes $31,709 contributed funds. 
" Includes $311,329 for previous projects. 
'2 Includes $13,437 for previous projects. 
'-In cludes $396,974 for previous projects. 
" Includes $109,463 for previous projects. 
"sIn cludes $8,918 for previous projects. 
'"In cludes $176,620 for new work, $127,598 for maintenance. 
" Includes $35,705 contributed funds. 
" Includes $148,000 contributed funds for existing project. 
" Includes $453,839 for previous projects. 
20 Excludes $3,000 contributed funds. 
21 Includes $21,818 for previous projects. 
2 Includes $149,312 for previous projects. 
2 Includes $88,364 for previous projects. 
24 Includes $402,242 for previous projects. 
2" Includes $656,000 for previous projects. 
26 Includes $235,346 for previous projects. 
2" Includes $354,139 contributed funds. 
'" Includes $57,670 contributed funds. 
29 Includes $491,416 for previous projects. 
3� Excludes $136,286 contributed funds. 
3' Includes $354,999 for previous projects. 
32 Includes $150,910 for previous projects. 
"3 Includes $3,955 for previous projects. 
3' Includes $400,126 for previous projects. 
3' Includes $54,288 for previous projects. 
Includes $312,423 for previous projects. 
"' Includes $36,194 for previous projects. 
" Includes $1,293,220 for previous projects. 
3' Includes $459,305 for previous projects. 
4' Includes contributed funds of $300,000 for new work and 
$166,667 for maintenance contributed by: Port Commission 
of Monroe, $300,000; Consolidated Paper Co., $125,000 and 
River Raisin Co., $41,667. 
" Includes $613,408 for previous projects. 
" Includes $446,183 for previous projects. 
'' Includes $284,802 for previous projects. 
" Includes $113,326 for previous projects. 
' Includes $172,100 contributed funds. 
3' Includes $188,495 for previous projects. 
" Includes $15,123 for previous projects. 
' Includes $50,084 for previous projects. 
' Includes $56,608 for previous projects. 
" Includes $962,556 for previous projects. 
" Includes $1,671,660 Public Works Funds and $49,419 emergency 
relief funds. 
' Includes $503,113 for previous projects. 
'" Includes $2,904,807 for previous projects. 
" Includes $90,232 for previous projects. 
" Includes $117,554 for previous projects. 
" Excludes $50,193 contributed funds. 
" Includes $487,817 for previous projects. 
" Includes $87,131 for previous projects. 
" Includes $187,233 for previous projects. 
60 Includes $131,239 for previous projects. 
"' Includes $323,419 for previous projects. 
02 Includes $219,730 for previous projects. 
�' Includes $48,404 national recovery act for new work funds. 
" Includes $212,857 for previous projects. 
" Includes $33,113 for previous projects. 
" Includes $15,000 for previous projects. 
" Includes $3,973,897 for previous projects. 
21-45

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1871 
Nov. 17, 1988 
Mar. 3, 1905 
Aug. 5, 1886 
Aug. 11, 1888 
Mar. 3, 1899 
Jun. 6, 1900 
Aug. 8, 1917 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Mar. 2, 1945 
May 20, 1965 
Aug. 26, 1937 
Sep. 19, 1890 
Jul. 13, 1892 
Sep. 22, 1922 
Jul. 3, 1930 
Aug. 30, 1935 
Apr. 23, 1970 
Mar. 2, 1945 
Jul. 6, 1965 
Aug. 14, 1876 
Aug. 2, 1882 
Jun. 13, 1902 
Jun. 20, 1938 
ALGOMA HARBOR, WI (See Section 1 of Text) 
Outer basin enclosed by a north pier 1,102 feet long and a south breakwater 
1,530 feet long, a 2,100 foot entrance channel and outer basin. 
Deauthorization of the outer harbor basin feature of the navigation project. 
ARCADIA HARBOR, MI (See Section 2 of Text) 
Maintenance of existing 12-foot channel. 
ASHLAND HARBOR, WI. (See Section 3 of Text) 
Breakwater 7,900 feet long and dredging to remove a shoal. 
Appropriation of $60,000 for 'Continuing improvements on enlarged project: 
(On completion of Poe Lock in 1896, with available depth of 20 feet, 
dredging at Ashland Harbor was carried to a similar depth.) 
Detached breakwater extending 4,700 feet out from shore at a point 2,600 
feet east of main breakwater (prolonged) and parallel thereto. 
Project modified by omitting detached breakwater and defining depth and 
extent of channel to be dredged. 
Widening part of present channel for entrance channel and for basin in 
eastern part of harbor. 
Deepening east basin to 25 feet and west channel, as far as 8th Ave. West 
extended to 21 feet. 
Widening west channel to 750 feet at its westerly end. 
Deepening portions of East Basin and West Channel to 27 and 21 feet, 
respectively. 
AU SABLE HARBOR AT AU SABLE RIVER (OSCODA), MI 
(See Section 4 of Text) 
Dredging channels 12 and 10 feet deep and riprapping North Pier. 
BAY PORT HARBOR, MICHIGAN (See Section 5 of Text) 
Channel 6 feet deep and 50 feet wide. 
BIG SUAMICO RIVER, WI (See Section 6 of Text) 
Channel from Green Bay to 1,800 feet above the river mouth. 
BLACK RIVER (PORT HURON), MI (See Section 7 of Text) 
Channel from mouth of Grand Trunk R.R. Bridge. 
Channel from Grand Trunk R.R. Bridge to Washington Ave. 
Consolidation of projects for Black River at Port Huron and Mouth of 
Black River. 
Settling Basin. 
Deepening channel and settling basin to 20 feet, and widening to 100 feet 2 
bends; 1 at the foot of 12th St., the other below the Grand Trunk R.R. 
Bridge. 
Extension of existing channel. 
BLACK RIVER HARBOR, MI (UPPER PENINSULA) 
(See Section 8 of Text) 
Two converging breakwaters, an entrance channel between breakwaters, 
an inner channel, and an irregular harbor basin. Project depths 12 feet in 
approach channel and 8 feet in the river channel and basin. 
BOLLES HARBOR, MI (See Section 9 of Text) 
Entrance channel in Lake Erie, Access channel in LaPlaisance Creek, Steel 
sheet pile revetment. 
CHARLEVOIX HARBOR, MI (See Section 10 of Text) 
Channel from Lake Michigan to Round Lake protected where needed by 
piers and revetments. 
Channel from Round Lake to Lake Charlevoix. 
Project depth increased to 15 feet. 
Project depth increased to 18 feet. 
River and Harbor Act 
H. Doc. 1098, 100th Cong. 2d Sess., 
Sec. 52(c) of the Water Resources 
Development Act (W.R.D.A.) of 
1988 
H. Doc. 194, 58th Cong., 2d Sess. 
H.Ex. Doc. 89, 48th Cong., 2d Sess. 
Annual Reports, 1886, p. 1674; and 
1887, p. 1966. 
H. Doc. 1698, 64th Cong., 2d Sess. 
S. Doc. 133, 71st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
46, 82d Cong., 1st Sess. 
H. Doc. 337, 77th Cong., 1st Sess. 
H. Doc. 165, 86th Cong., 1st Sess.' 
H. Doc. 446, 78th Cong., 2d Sess.' 
Section 107, 1960 River and Harbor 
Act. 
H. Doc 498, 74th, Cong., 2d Sess.' 
Annual Report 1889, p. 2291 
No Printed Report 
H. Doc. 436, 64th Cong., 1st Sess. 
H. Doc. 162, 71st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
54, 72d Cong., 2d Sess. 
Section 107, 1960 River and Harbor 
Act. 
H. Doc. 446, 78th Cong., 2d Sess.' 
Section 107, 1960 River and Harbor 
Act. 
S. Ex. Doc. 16, 44th Cong., Ist Sess., 
and Annual Report 1876, p. 523 
No Prior Survey of Estimates. 
No Prior Survey of Estimates. 
S. Doc. 163, 75th Cong., 3rd Sess.' 
21-46

TABLE 21-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 17, 1988 
Mar. 29, 1977 
Aug. 5, 1886 
Jul. 19, 1963 
Jun. 3, 1969 
Jun. 13, 1902 
Mar. 3, 1905 
Jun. 25, 1910 
Mar. 4, 1913 
Mar. 2, 1907 
Jun. 25, 1910 
Mar. 2, 1910 
Jul. 3, 1930 
Aug. 30, 19353 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 19504 
Mar. 21, 1956 
Jul. 14, 1960 
Aug. 13, 1968 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 1907 
May 28, 1908s 
Jul. 27, 1916 
Mar. 2, 1919 
Restore recreational uses or provide comparable recreational uses at the 
South Pier. 
Project depth increased to 24 and 23 feet, and construction of revetment 
upstream of Highway Bridge. 
CLINTON RIVER, MI (See Section 11 of Text) 
Channel in River and Lake St. Clair, Pile Dike, Closing channels and making 
Cutoff, and revetments as needed. 
Widening entrance channel and constructing protected harbor basin. 
DETOUR HARBOR, MI (See Section 12 of Text) 
Small boat harbor and harbor of refuge, 10-foot channel, 8-foot deep 
access channel protected by 1,000-foot breakwater. 
DETROIT RIVER, MI (See Section 13 of Text) 
Amherstburg Channel and removal of Grosse Ile shoal. 
Fighting Island Channel. 
Livingstone Channel. 
Channel Depths of 26 and 25 feet. 
Channel to Wyandotte 21 feet deep and 300 feet wide through Middle 
Ground opposite Head of Fighting Island. 
Trenton Channel and Turning Basin (West of Grosse Ile). 
American Channel North of Belle Isle between Windmill Point and Fairway 
Slip, Detroit. 
Deepen Westerly 300 feet of Amherstburg Channel and Ballards Reef 
Channel below Livingstone Channel to 27 feet to provide depths adequate 
for 24-foot draft navigation when governing Lakes are at Datum, 
with necessary widening at approaches and bends and construction of 
necessary compensating works, Detroit River. 
Extend Turning Basin in Trenton Channel 600 feet. Dredge through East 
Draw of lower Grosse Ile Bridge and extend 300-foot width of Channel 
North of lower Grosse Ile Bridge. 
Channel Depth of 28.5 feet throughout downbound and Two-Way Channels, 
except in upper (27.7-foot depth) and lower, (29-foot depth) Livingstone 
Channel, and in upbound Channel; 27-foot depth in Ballards Reef 
Channel below junction with Livingstone Channel. 27.5-foot depth in 
westerly 300-foot width of Limekiln Crossing and Amherstburg 
Reaches, and 28.5-foot depth in westerly 300-foot width of Hackett 
Beach, with necessary compensation works. Also 28.5-foot depth in 
Lake Erie from Detroit River to Pelee Passage Shoal. Inclusive. 
Trenton Channel; Deepen to 27 feet, where necessary, Wyandotte Reach 
from Detroit River to Upper Grosse Ile Bridge, about 5.5 miles, deepen 
to 28 feet and widen to 300 feet below Upper Grosse Ile Bridge to and 
including a Turning Basin 28 feet deep and 15 across in area outside project 
limits. 
Trenton Channel: Deepen to 28 feet and widen to 300 feet from the Upper 
Turning Basin at Trenton to Gibraltar, about 20,500 feet downstream: 
Construct a Turning Basin at Gibraltar at a depth of 28 feet, width of 830 
feet, and length of 1,500 feet: Build compensating works to maintain 
water levels. 
DULUTH-SUPERIOR HARBOR, MN AND WI 
(See Section 14 of Text) 
Dredging. 
Rebuilding piers at Superior Entry. 
Enlarge plan for Superior Entry and additional dredging near draw span of 
Burlington Northern railway bridge. 
Dredging additional area for basin inside Duluth entrance to 22-foot 
depth. 
Enlarging Superior Harbor Basin. 
Removal of shoal point at southerly end of East Gate Basin. 
H. Doc. 1098, 100th Cong. 2d Sess., 
Sec. 25 of the W.R.D.A. of 1988 
Section 107, 1960 River and Harbor 
Act. 
S. Doc. 199, 46th Cong., 2d Sess. 
Annual Report 1880, p. 2062 and H. 
Doc. 210, 44th Cong., 2d Sess. and 
Annual Report 1886, p. 219 
Section 107, 1960 River and Harbor 
Act. 
Section 107, 1960 River and Harbor 
Act. 
H. Doc. 712, 56th Cong., 1st Sess. 
and 40, 58th Cong., 3rd Sess. 
H. Doc. 17, 62d Cong., 1st Sess. 
H. Doc. 266, 59th Cong., 2d Sess. 
676, 61st Cong., 2d Sess., and 32, 
65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
1, 72nd Cong., 1st Sess.' 
H. Doc. 205, 75th Cong., 1st Sess. 
H. Doc. 734, 79th Cong., 2d Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 30, 81st Cong., 1st Sess.' 
S. Doc. 71, 84th Cong., 1st Sess.' 
H. Doc. 319, 86th Cong., 2d Sess.' 
H. Doc. 338, 90th Cong., 2d Sess.' 
H. Ex. Doc. 59, 53rd Cong., 3d Sess. 
and Annual Report, 1895, p. 2538. 
H. Doc. 82, 59th Cong., 2d Sess. 
H. Doc. 221, 60th Cong., 1st Sess. 
H. Doc. 651, 64th Cong., 1st Sess. 
H. Doc. 1018, 64th Cong., 1st Sess. 
21-47

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jan. 21, 1927 
Jul. 30, 19303 
Aug. 30, 19303 
Jul. 16, 19526 
Jul. 14, 1960' 
Oct. 4, 1961 
Nov. 17, 1986 
Mar. 2, 1867 
Mar. 2, 1945 
Aug. 5, 1886 
Sep. 19, 1890 
Jun. 3, 1896 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 3, 1925' 
Jun. 26, 1934' 
Jul. 3, 1958 ' 
Jun. 23, 1866" 
Mar. 3, 1925 
Aug. 26, 1937 
Oct. 27, 1965 
Jun. 23, 1866 
Jun. 14, 1880 
Sep. 19, 1890 
Jul. 13, 1892 
Jul. 3, 1930 
Aug. 26, 1937 
Mar. 2, 1945 
Nov. 17, 1986 
Howards Bay Channel, 20 feet deep. 
Deepening and widening channels and basins. 
Deepen Superior Front Channel and a portion of East Gate Basin to 25 
feet. 
Present project dimensions of channels and basin. 
Abandons northerly portion of 21st Avenue West Channel. 
Deepen portions of the North and South Channels, the entire Upper Channel 
and Minnesota Channel to 27 feet; widen the Cross Channel turning 
basin to 1,500 feet; widen the bend at the Arrowhead Bascule Bridge to 
600 feet, and construct an upland CDE 
EAGLE HARBOR, MI (See Section 15 of Text) 
Breakwater and dredging of entrance channel 130 feet wide to depth of 14 
feet. 
Project modified by reduction of channel width from 130 feet to 80 feet. 
Project modified by increasing width of breakwater from 20 feet to 30 feet 
and increasing the channel from 80 to 130 feet. 
Project modified by omitting breakwater and constructing guide piers. 
Inner harbor basin and breakwaters and removal of east guide pier. 
FOX RIVER, WI (See Section 16 of Text) 
Improvement of Fox River. 
Dredging Fond du Lac Harbor on Lake Winnebago. 
Improvement of Wolf River 
Improvement of Stockbridge, of Calumet and Miller Bay, and of Brothertown 
Harbor, on Lake Winnebago. 
Increased depth in rock cuts on lower river, widen Neenah Channel, and a 
concrete retaining wall at Kaukauna. 
Operation and care of locks and dams provided for with funds from War 
Department appropriations for rivers and harbors. 
Sec. 108, that Federal project structure, appurtenances, and real property 
of Upper Fox River, WI, be disposed of to State of Wisconsin. 
FRANKFORT HARBOR, MI (See Section 17 of Text) 
A New Outlet 12 feet deep protected by Piers and Revetments. 
Exterior Breakwaters, removal of portions of Piers, Project Dimensions 
of Outer Basin. 
Dredge the area in Lake Betsie. 
Deepen approach and entrance Channels. Extend Inner Basin and Dredge 
recreational anchorage area. 
GRAND HAVEN HARBOR, MI (See Section 18 of Text) 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Present Project dimensions of Harbor channel to Grand Trunk Car Ferry 
Slip and River Channel. Eliminating all of that portion of Grand River 
above Bass River, Consolidation of Projects for Harbor and River. 
Channel to Spring Lake 
Present Project Dimensions of Harbor Channel from Car Ferry Slip to 
Grand Trunk Railway Bridge and Turning Basin. 
Deepen the harbor entrance channel and harbor river channel to 29 and 27 
feet, respectively; provide a new and larger turning basin, trapezoidal in 
shape, 1,200 feet long at the channel, 300 feet long at the shore, 800 feet 
at a right angle to the channel and 18 feet deep. 
H. Doc. 145, 69th Cong., 1st Sess. 
and Rivers and Harbors Committee, 
Doc. 32, 71st Cong., 2d Sess. 
H. Doc. 482, 72d Cong., 2d Sess. 
H. Doc. 374, 82d Cong., 2d Sess. 
H. Doc. 150, 86th Cong., 1st Sess., H. 
Doc. 196, 86th Cong., 1st Sess. 
H. Doc. 204, 99th Cong., 2d Sess. 
Sec. 202a of Water Resources Development 
Act of 1986 
Annual Report for 1868, p. 89. 
Annual Report for 1874, pp. 36, 135 
and 136. 
Annual Report for 1877, p. 98. 
H. Doc. 446, 78th Cong., 2d Sess.' 
Annual Report, 1885, pp. 2041-2045 
(plan of a board approach Dec. 10, 
1884, as modified by Corps of Engineers, 
May 14, 1886). 
H. Ex. Doc. 24, 51st Cong. 1st Sess. 
Annual Report, 1890, p. 2390. 
No prior survey or estimates. 
No prior survey or estimates. 
No prior survey or estimates. 
H. Doc. 294, 68th Cong., 1st Sess.' 
S. Bill 3910, 85th Cong., 2d Sess. 
H. Doc. 482, 5th Cong., 2d Sess. 
H. Doc. 208, 68th Cong., 1st Sess. 
H. Doc. 511, 74th Cong., 2d Sess., S. 
Doc. 16, 89th Cong., 1st Sess.' 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Doc. 88, 71st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
1, 75th Cong., 3d Sess.' 
H. Doc. 661, 76th Cong., 3d Sess.' 
H. Doc. 227, 98th Cong., 2d Sess. 
Sec. 202a of W.R.D.A. of 1986 
21-48

TABLE 21-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 14, 1880 
Jun. 14, 1880 
May 17, 1950 
Mar. 3, 1879 
Aug. 30, 1935 
May 17, 1950 
Mar. 2, 1945 
Jun. 23, 1866 
Jul. 13, 1892 
Jun. 26, 1910 
Aug. 8, 1917 
Mar. 3, 1925 
Aug. 30, 19352 
Aug. 26, 1937 
Mar. 2, 1945 
Oct. 23, 1962 
Nov. 17, 1986 
Mar. 3, 1871 
Jan. 21, 1927 
Jul. 16, 1984 
Nov. 17, 1988 
Aug. 30, 1852 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 3, 1905 
Jul. 3, 1930 
Aug. 30, 1935 
Sep. 3, 1954 
Sep. 3, 1954 
Sep. 2, 1964 
GRAND MARAIS HARBOR, MI (See Section 19 of Text) 
Existing Project, except for pile dike. 
For Pile Dike. 
800-Foot Extension of West Pier. 
GRAND MARAIS HARBOR, MN (See Section 20 of Text) 
Breakwaters and dredging of anchorage area of 26 acres to 16 feet. 
Seawalls across ledge in southeast corner of harbor, enlarging anchorage 
basin and deepening of entrance. 
Small-boat basin with breakwater. 
GRAND TRAVERSE BAY HARBOR, MI 
(See Section 21 of Text) 
Two Parallel piers, and entrance channel between piers and a harbor basin. 
Project depths are 12 feet between piers and 10 feet in basin. Project area 
extended 200 feet upstream in 1966. 
GREEN BAY HARBOR, WI (See Section 22 of Text) 
Outer Channel and revetment at Grassy Islands.' 2 
Inner channel."2 
Turning basin at De Pere. 
Maintenance of turning basin at De Pere. 
Increasing depth of inner channel and turning basin to 18 feet. 
Deepen outer channel to 22 feet with widening and straightening inside of 
Tail Point Bend, widen channel in Fox River through city of Green Bay to 
22 feet. 
Turning basin above Chicago & North Western Ry. Bridge. 
Turning basin at mouth of East River. 
Deepen and widen 9 miles of entrance channel to 26 by 500 feet; 3.6 miles 
of entrance channel to 24 by 300 feet; and 3.2 miles of existing Fox River 
to 24 feet deep. 
Deepen the Fox River channel at Green Bay, WI, to 27 feet. 
HARBOR BEACH, LAKE HURON, MI 
(See Section 23 of Text) 
Adopted Site and made provision for harbor. Closing North Entrance and 
dredging Main Entrance and Anchorage Area. 
Removal of portion of Breakwater in interest of sanitation. 
Deepen the waterway within the Marina facility. 
HEARDING ISLAND INLET, DULUTH, MN 
(See Section 24 of Text) 
Dredging of the Inlet to increase water circulation and reduce stagnant 
water conditions. 
HOLLAND HARBOR, MI (See Section 25 of Text) 
Artificial channel between Lakes Macatawa and Michigan.' 2 
Piers and Revetments.' 2 
Extending Inner Piers. 
Converging Breakwater. 
Channel to Holland and Turning Basin at Holland 
Present Project Dimensions of Channels at Turning Basin. 
Widen Bend in Reveted Entrance Channel into Lake Macatawa, Dredge 
Channel in Black River, and Widen and Extend Turning Basin. 
THE INLAND ROUTE, MI (See Section 26 of Text) 
Channel 30 feet wide and 5 feet deep through Lakes and Rivers with suitable 
jetties. 
Lock and Dam. 
Specified in Act. Annual Report 
1881, p. 2050. 
Annual Report 1895, p. 351. 
H. Doc. 751, 80th Cong., 2d Sess. 
H. Ex. Doc., 75, 43d Cong., 2d Sess. 
Annual Report, 1875, p. 184. 
Rivers and Harbors Committee Doc. 
22, 72d Cong., 1st Sess. 
H. Doc. 187, 81st Cong., 1st Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report, 1867, p. 70. 
Unpublished report approved Aug. 3, 
1892. 
H. Doc. 222, 61st Cong., 2d Sess. 
H. Doc. 1017, 64th Cong., 1st Sess. 
H. Doc. 294, 68th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
40, 72d Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
73, 74th Cong., 2d Sess. 
H. Doc. 95, 76th Cong., 1st Sess. 
H. Doc. 470, 87th Cong., 2d Sess.' 
H.R.6 (formerly S. 1567), 99th 
Cong., 2d Sess. (W.R.D.A. of 1986, 
Sec. 601c) 
Annual Report 1873, p. 292, H. Doc. 
1700, 64th Cong., 2d Sess. 
H.R. 5653, 98th Cong., 2d Sess., P.L. 
98-360 (98 Stat. 405) Sec. 105. 
H. Doc. 1098, 100th Cong., 2d Sess., 
Sec. 22 of the W.R.D.A. of 1988 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
Annual Report 1866, p. 106. 
H. Doc. 272, 51st Cong., 2d Sess., 
and Annual Report 1887, p. 2950 
Annual Report 1905, p. 2176. H. 
Doc. 588, 69th Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
48, 74th Cong., Ist Sess. 
H. Doc. 282, 83rd Cong., 2d Sess. 
H. Doc. 142, 82nd Cong., 1st Sess.' 
Chief of Engineers. 
21-49

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1899 
Mar. 2, 1907 
Aug. 30, 19352 
May 17, 1950 
Oct. 23, 1962 
Mar. 3, 1881 
Jun. 25, 1910 
Aug. 30, 1935214 
Jul. 14, 1960 
Sep. 19, 1890 
Jun. 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935's 
Nov. 17, 1986 
Mar. 2, 1945 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Mar. 2, 1919 
Jul. 3, 1930 
Aug. 30, 19333 
Mar. 21, 1956 
Aug. 30, 1935 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
KENOSHA HARBOR, WI (See Section 27 of Text) 
Parallel piers and 600 feet of breakwater.'2 
Extending Breakwater 200 feet. 
Present project dimensions of entrance channel and basin. 
Channel northwesterly from basin. 
Deepen lake approach channel to 27 feet and 800 feet wide; deepen 
approach channel to 26 feet, entrance channel and inner basin to 25 feet. 
KEWAUNEE HARBOR, WI (See Section 28 of Text) 
Entrance piers. 
Turning basin. 
North breakwater, remove old north pier, widen and deepen entrance 
channel and turning basin to 20 feet and remove outer south shoal. 
Enlarge existing turning basin, extend existing project into north basin, 
and increase depth of north basin to 20 feet at a maximum width of 500 
feet and eliminate removal of outer shoal. 
KEWEENAW WATERWAY, MI (See Section 29 of Text) 
Acquisition of waterway; for a 16-foot channel of 70-foot bottom width, 
renew canal revetments, reconstruct and extend piers at upper entrance 
to 30-foot depth of water, and at proper time for increase of channel 
depth to 20 feet with bottom width of not less than 120 feet (increase in 
width and depth of channel approved Mar. 15, 1898). 
Anchorage basin just within lower entrance about one-half mile long, 800 
feet wide; a mooring pier on its westerly side 2,000 feet in length, and for 
purchase of necessary land. 
Princess Point Cutoff channel. 
General deepening, widening and straightening of channels and basins to 
provide 25-foot depth with additional overdepth at entrances, extend 
lower entrance breakwater, and necessary alteration or replacement of 
structures due to deepening channels. 
Deauthorization of the uncompleted portion of the project authorized by 
the 1935 River and Harbor Act. 
LAC LA BELLE HARBOR, MI (See Section 30 of Text) 
Two parallel piers at the entrance, 584 and 682 feet; an entrance channel 
between the piers 50 feet wide and 12 feet deep, 820 feet long with a flared 
approach and inner canal 50 feet wide and 10 feet deep and 730 feet long. 
LAKE ST. CLAIR, MI, CHANNELS (See Section 31 of Text) 
Two Dikes. 
Deepening Canal and dredging Channel at Grosse Pointe. 
Second Canal for downbound vessels. 
21-foot depth in Grosse Pointe Channel for about 5.25 miles. 
25-foot depth through Canals and Channel through Lake St. Clair. 
Removal of Center Dike and widening Channel to 700 feet. 
Deepening Channel to 27.5 feet and abandonment of Channel above 
mouth of Southeast bend cutoff Channel. 
LELAND HARBOR, MI (See Section 32 of Text) 
Entrance Channel protected by Piers. 
Outer Breakwater, Anchorage Area. Approach Channel and removal of 
North Pier. 
LEXINGTON HARBOR, MI (See Section 33 of Text) 
Approach Channel and Maneuver Area Protected by Breakwaters.' 
LITTLE LAKE HARBOR, MI (See Section 34 of Text) 
12-Foot Deep Channel from Lake Superior into Little Lake Breakwaters 
and Revetments. 
H. Doc. 328, 54th Cong., 2d Sess. 
Annual Report 1897, p. 2772, H. 
Doc. 164, 55th Cong., 3d Sess. 
Annual Report, 1899, p. 1817. 
H. Doc. 62, 59th Cong., 2d Sess. and 
Rivers and Harbors Committee Doc. 
3, 59th Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
19, 74th Cong., 1st Sess. 
H. Doc. 750, 80th Cong., 2d Sess. 
H. Doc. 496, 87th Cong., 2d Sess.' 
Annual Report, 1881, p. 2082 
H. Doc. 324, 60th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
43, 72d Cong., 1st Sess. 
S. Doc. 19, 86th Cong., 1st Sess.' 
H. Ex. Doc. 105 49th Cong., 2d Sess. 
and Annual Report 1887, p. 1977. 
H. Doc. 325, 60th Cong., 1st Sess. 
H. Doc. 835, 63rd Cong., 2d Sess. 
H. Doc. 55, 73rd Cong., 1st Sess.' 
H.R.6 (formerly S. 1567) 99th Cong., 
2d Sess. (W.R.D.A. of 1986) 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report, 1961, p. 1039. 
Annual Report 1885, p. 2150. 
H. Doc. 297, 51st Cong., 2d Sess. 
H. Doc. 234, 56th Cong., 2d Sess. 
H. Doc. 188, 65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
3, 72nd Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess.' 
Rivers and Harbors Committee Doc. 
23, 74th Con., 1st Sess. 
H. Doc. 413, 87th Cong., 2d Sess. 
H. Doc. 301, 88th Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 2d Sess.' 
21-50

TABLE 21-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 2, 1907 
Dec. 31, 1970 
Jun. 25, 1910 
Aug. 17, 1966 
Mar. 2, 1867 
Sep. 19, 1890 
Jul. 25, 1912 
Jul. 3, 1920 
Mar. 2, 1945 
Jul, 14, 1960 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 2, 1907 
Aug. 30, 1935" 
Aug. 26, 1937 
Oct. 23, 1962 
Dec. 31, 1968 
(Sec. 107 of 
1960 R & H) 
Jun. 26, 1979 
Mar. 2, 1867 
Aug. 11, 1888 
Jun. 25, 1910 
Aug. 30, 1935' 
Jul. 11, 1960 
LUDINGTON HARBOR, MI (See Section 35 of Text) 
Entrance Piers. 
Pier Extension. Reconstruction and Repairs to Existing Structures and 
Present Project Dimensions of Channel. 
Breakwaters, Shore Connections, and Removal of Outer Ends of the Two 
Inner Piers. 
Deepen Channels and Widen Opening between Breakwaters. 
MACKINAC ISLAND HARBOR, MI (See Section 36 of Text) 
Original Breakwater.' 
500-foot extension to East Breakwater. 
MANISTEE HARBOR, MI (See Section 37 of Text) 
Entrance Piers. 
Extending Channel 8,000 feet to connect with Manistee Lake, and further 
Pier extension. 
Depth of 20 feet in Outer Harbor 570 feet wide to Outer end of South Pier 
18 feet deep in river, South Breakwater with shore connection, and 
extend North Pier if required. 
23-foot depths in entrance channel and 21-foot depths in River Channel. 
Remove old South Revetment, Construct new South Pier and Revetment, 
and widen river entrance Channel. 
Present Project dimensions of Channel through Outer Basin and River, 
and Federal participation in cost of replacing Maple Street Bridge. 
MANISTIQUE HARBOR, MI (See Section 38 of Text) 
Breakwaters and Outer Harbor. 
Present Location of West Breakwater and Pier at River Mouth. 
MANITOWOC HARBOR, WI (See Section 39 of Text) 
Breakwaters. 
Present project dimensions of channel through outer basin, removal of old 
north stub pier, and approach channel to a proposed city terminal south 
of shore end of south breakwater. 
Channel in river. 
Deepen Lake approach to 25 feet by 800 feet wide, deepen outer harbor to 
25 feet, river channel to 23 feet to 8th St., and Upper River Channel to 22 
feet to Soo Line R.R. 
Dredge River Channel to 12 feet from Soo Line R.R. 720 feet upstream. 
Construct 765-foot long stone Breakwater, and rubblemound bulkhead; 
construct 360-foot long entrance Breakwater; dredge 16,500 cubic yards 
for entrance channel. 
MARQUETTE HARBOR, MI (See Section 40 of Text) 
Breakwaters, 2,000 feet long. 
Extending the breakwater 1,000 feet. 
Additional 1,500-foot extension to breakwater and removing a shoal in 
northerly part of harbor. 
Deepening harbor to 25 feet. 
Deepening harbor to 27 feet. 
Annual Report 1867, p. 114 '6 
H. Doc. 273, 54th Cong., 2d Sess. and 
Annual Report 1897, p. 2951 
H. Doc. 62, 59th Cong., 1st Sess. and 
Rivers and Harbors Committee Doc. 
3, 59th Cong., 2d Sess.'" 
H. Doc. 342, 91st Cong., 2d Sess.' 
H. Doc. 646, 56th Cong., 1st Sess. 
Section 107, 1960 River and Harbor 
Act. 
Annual Report 1867, p. 115 
Annual Report 1891, p. 2678 
H. Doc. 599, 62nd Cong., 2d Sess. 
S. Doc. 131, 71st Cong., 2d Sess. 
H. Doc. 380, 77th Cong., 1st Sess. 
H. Doc. 358, 86th Cong., 2d Sess. 
H. Doc. 429, 58th Cong., 2d Sess. 
Annual Report 1908, p. 648, and 
Unpublished Report of Mar. 13, 
1908. Approved by Secretary of War, 
Apr. 3, 1908. 
H. Doc. 62, 59th Cong., 1st Sess., as 
modified by Rivers and Harbors 
Committee Doc. 3, 59th Cong., 2d 
Sess. 
Rivers and Harbors Committee Doc. 
39, 73d Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
80, 74th Cong., 2d Sess. 
H. Doc. 479, 87th Cong., 2d Sess. 
Jun. 1967 Detailed Project Report; 
Apr. 1982 Supplement.' 
Sec. 107, 1960 River and Harbor Act. 
H. Ex. Doc. 56, 39th Cong., 2d Sess. 
pts. 1 and 2, and Annual Report, 
1866, pp. 8 and 77. 
Annual Report 1889, pp. 272 and 
2021. 
H. Doc. 573, 61st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
20, 72d Cong., 1st Sess. 
H. Doc. 154, 86th Cong., Ist Sess.' 
21-51

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1871 
Jun. 13, 1902 
Mar. 4, 1913 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Jun. 27, 1967 
Sec. 107 
Aug. 30, 1852 
Mar. 3, 1883 
Mar. 2, 1907 
Sep. 22, 1922 
Aug. 30, 1935 
Mar. 2, 1945 's 
Jul. 14, 1960 
Oct. 23, 1962 
Feb. 24, 1835 '9 
Jul. 3, 1930 
Jul. 14, 193221 
Nov. 17, 1986 
Jun. 13, 1902 
Mar. 3, 1925 
Aug. 30, 1935 
Oct. 23, 1962 
Oct. 23, 1962 
MENOMINEE HARBOR AND RIVER, MI AND WI 
(See Section 41 of Text) 
Entrance piers. 
Consolidation of project for harbor and river, and a channel 18 feet deep. 
Partial restoration of work above bridge which had been eliminated by Act 
of May 3, 1905. 
20-foot depth in channel and 18-foot depth in turning basin. 
21-foot depth in channel and turning basin and enlarge turning basin. 
Extend channel 12 feet deep to vicinity of Marinette Yacht Club. 
Deepen existing approach channel to 26 feet, entrance and river channels 
to 24 feet and enlarge turning basin. 
Deepen 1,100 feet of river channel generally north of Marinette Corp. 
facilities to 19 feet. 
MILWAUKEE HARBOR, WI (See Section 42 of Text) 
North Pier." 
Inner 7,600 feet of breakwater.'" 
South pier. Extending north breakwater 1,000 feet. 
Extend north breakwater; a south breakwater; present project dimensions 
of inner entrance channel. 
Dredging a portion of outer harbor to 21-foot depth. 
Dredging river channels to 21-foot depth. 
Deepen South Menominee and Burnham Canals to 21 feet. 
Deepen an approach channel to 30 feet by 800 feet wide and 300 feet wide 
through breakwater; deepen entrance channel 28 feet through piers, 
outer harbor to 28 feet south of entrance channel, and a channel to 27 feet 
in Milwaukee River to Buffalo St., and in Kinnickinnic River to Chicago 
& North Western Ry. bridges. 
MONROE HARBOR, MI (See Section 43 of Text) 
9-foot channel, protecting Revetments and Piers. 
21-foot channel, dikes and Turning Basin.2' 
Modified Conditions of Local Cooperation imposed by Act of Jul. 3, 
1930. 
Deepen portion of existing navigation channel to 27 feet; deepen lake 
channel to 28 feet; widen the channel from 200 to 500 feet; dredge a new 
turning basin 24 feet deep, 1,600 feet wide at river's mouth; and construct 
a 190 acre CDF in Plum Creek Bay to enable creation of a 700 acre marsh 
behind the CDF. 
MUSKEGON HARBOR, MI (See Section 44 of Text) 
Piers and Revetments. 
Breakwaters. 
Repairing Revetments around Car Ferry Slip. 
Channel deepening and present project dimensions of channel. Piers and 
Revetments. 
NEW BUFFALO HARBOR, MI (See Section 45 of Text) 
Entrance channel 10 feet deep by 80 to 180 feet wide and 850 feet long to 
mouth of Galien River, new no. and so. breakwaters 1,305 and 740 feet, 
respectively, deepening inner channel to Galien River to 8 feet and 80 feet 
wide and 1,250 feet long. 
Annual Report, 1867, p. 132. 
H. Doc. 419, 56th Cong., Ist Sess. 
H. Doc. 171, 70th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
28, 73rd Cong., 2d Sess. 
H. Doc. 228, 76th Cong., 1st Sess. 
H. Doc. 112, 86th Cong., 1st Sess. 
Detailed Project Report Dec. 1960.' 
S. Doc. 175, 25th Cong., 2d Sess. 
Annual Report 1881, p. 2122 
Annual Report 1906, p. 1752. (No 
prior survey or estimate affecting 
breakwater extensions.) 
H. Doc. 804, 66th Cong., 2d Sess. 
H. Doc. 289, 72d Cong., 1st Sess. 
S. Doc. 29, 76th Cong., 1st Sess. 
H. Doc. 285, 86th Cong., 2d Sess. 
H. Doc. 134, 87th Cong., 1st Sess.' 
Annual Report 1872, p. 237 
Rivers and Harbors Comm. Doc. 22, 
71st Cong., 1st Sess. 
Rivers and Harbors Comm. Doc. 12, 
72d Cong., 1st Sess., 45, 75th Cong., 
1st Sess.' 
H.R.6 (formerly S. 1567), 99th 
Cong., 2d Sess. (W.R.D.A. of 1986) 
H. Doc. 104, 56th Cong., 2d Sess. 
H. Doc. 494, 67th Cong., 4th Sess. 
Rivers and Harbors Comm. Doc. 64, 
75th Cong., 1st Sess.' 
H. Doc. 474, 87th Cong., 2d Sess.' 
H. Doc. 474, 87th Cong., 2d Sess. 
21-52

TABLE 21-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 25, 1910 
Aug. 26, 1937 
Oct. 23, 1962 
Nov. 17, 1986 
Mar. 2, 1867 
Mar. 3, 1873 
Jul. 5, 1881 
Jul. 13, 1892 
Mar. 25, 1907 
Mar. 2, 1945 
Mar. 3, 1879 
Mar. 2, 1945 
Jul. 16, 1984 
Jul. 11, 1987 
Mar. 2, 1945 
Jul. 11, 1870 
Aug. 14, 1876 
Aug. 30, 193529 
Jul. 3, 195830 
Jun. 13, 1902 
Jun. 30, 1948 
Aug. 5, 1977 
Aug. 8, 1917 
Aug. 30, 19352' 
25 
Jul. 3, 19582 
Oct. 23, 19622 
Jun. 25, 1910 
Jul. 3, 1930 
Aug. 26, 1937 
ONTONAGON HARBOR, MI (See Section 46 of Text) 
Channel 17 feet deep and 150 wide through bar and 15 feet deep and 100 
feet wide between piers, and pier maintenance. 
Modified project widths and provide inner basin. 
Enlarging and deepening the existing harbor basin. 
Deauthorization of the turning basin feature of the project authorized by 
the 1962 River and Harbor Act. 
PENTWATER HARBOR, MI (See Section 47 of Text) 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Present project depth of channel. 
POINTE LOOKOUT HARBOR (AU GRES RIVER), MI 
(See Section 48 of Text) 
Breakwater, Anchorage Area, Channel Dredging. 
PORTAGE LAKE HARBOR, MI (See Section 49 of Text) 
Entrance Channel 18 feet deep protected by Piers and Revetments. 
PORT AUSTIN HARBOR, MI (See Section 50 of Text) 
Breakwater, Anchorage Basin, Channel Dredging. 
Construct a breakwater access for recreation purposes. 
Breakwater 
PORT SANILAC HARBOR, MI (See Section 51 of Text) 
Entrance Channel 12 feet deep, Anchorage Basin, Breakwater. 
PORT WASHINGTON HARBOR, WI (See Section 52 of Text) 
North pier and south basin.' 2 
North basin. 
North breakwater, removal of 650 feet of north pier, outer turning basin, 
present project dimensions of channel and basin and extension of south 
breakwater. 
Extending and raising of north breakwater and placing rubble along sides; 
removing 456 feet of south breakwater and dredging in outer basin. 
PORT WING HARBOR, WI (See Section 53 of Text) 
Construction of parallel piers and dredging. 
Dredging inner channels and abandonment of certain revetments and 
channels. 
Deauthorization of 50 feet of entrance channel widening. 
ROUGE RIVER, MI (See Section 54 of Text) 
21-foot channel via the Shortcut Canal. 
25-foot channel at mouth of Old Channel, 1,425 feet long and adjacent to 
latter, and 21-foot channel extending from junction of Old Channel and 
Shortcut Canal into Old Channel to Detroit, Toledo & Ironton R.R. 
Bridge. 
Old Channel; 100 feet wide from Peerless Cement Corp. to Junction with 
Shortcut Canal widened to 150 feet at 2 bends. 
25-foot channel over modified limits from Detroit River to Jefferson Ave. 
(via Shortcut Canal). 
SAGINAW RIVER, MI (See Section 55 of Text) 
Channel 200 feet wide, with depth of 18.5 feet in Bay and 16.5 feet in River. 
Project Depth of 18.5 feet extended up River to Saginaw. 
Turning Basin. 
H. Doc. 602, 61st Cong., 2d Sess. 
S. Committee print, 74th Cong., 2d 
Sess. 
H. Doc. 287, 87th Cong., 2d Sess. 
H.R.6 (formerly S. 1567) 99th Cong., 
2d Sess. (W.R.D.A. of 1986) 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Doc. 181, 39th Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report 1879, p. 163422 
H. Doc. 446, 78th Cong., 2d Sess. 
H.R. 5653, 98th Cong., 2d Sess., P.L. 
98-360 (98 Stat. 405) Sec. 106. 
P.L. 100-71 
H. Doc. 446, 78th Cong., 2d Sess. 
H. Ex. Doc. 28, 41st Cong., 2d Sess. 
and Annual Report, 1879, p. 119. 
Annual Report, 1876, pt. 2, p. 379 
H. Doc. 168, 72d Cong., 1st Sess. and 
Rivers and Harbors Committee Doc. 
41, 74th Cong., 1st Sess. 
H. Doc. 446, 83d Cong., 2d Sess.' 
H. Doc. 114, 56th Cong., 1st Sess. 
H. Doc. 668, 80th Cong., 2d Sess. 
H. Doc. 1063, 64th Cong., 2d Sess. 
H. Doc. 125, 85th Cong., 1st Sess. 
H. Doc. 509, 87th Cong., 2d Sess.' 
H. Doc. 740, 61st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
30, 71st Cong., 2d Sess. 
Rivers and Harbors Comm. Doc. 21, 
75th Cong., 1st Sess. 
21-53

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts 
Jun. 20, 1938 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 13, 1892 
Jul. 8, 1930 
Mar. 2, 1945 
Jul. 24, 1946 
Mar. 21, 1956 
Nov. 17, 1986 
Mar. 3, 1875 
Jun. 14, 1880 
Mar. 3, 1899 
Aug. 30, 1935 
Jun. 2, 1937 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 11, 1870 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Jun. 13, 1902 
Mar. 3, 1907 
Mar. 3, 1909 
Jul. 25, 1912 
Mar. 4, 1915 
Sep. 22, 1922 
Jan. 21, 1927 
Work Authorized 
Present Project Channel Dimensions from Bay to Sixth Street Bridge in 
Saginaw. 
New Channel in Bay, 350 feet wide and 24 feet deep from 24-foot contour 
to River Mouth, Project Depth of 24 feet in River Channel up to Detroit 
& Mackinac Railway Bridge, Project Depth of 22 feet in River Channel 
up to Sixth Street Bridge, Turning Basins at Essexville and Carrollton, 
and elimination of present Channel in Bay. 
Deepen Bay Channel, Deepen River Channel to Detroit & Mackinac 
Bridge, Extend 22-foot Project above 6th St. Bridge, Deepen Essexville 
Turning Basin, and Construct 2 new Turning Basins.' 
Deepen River Channel to 25 feet, from Detroit & Mackinac Bridge to New 
York Central Railroad Bridge. 
ST. CLAIR RIVER, MI (See Section 56 of Text) 
20-foot Channel in the River 
Deepen Channel to 25 and 26 feet, and Compensating Works. 
Widening Channel at Southeast Bend to 700 feet. 
Widen and deepen Southeast Bend and improve Outlet of North Channel, 
St. Clair River. 
Deepen and further improve Channels in St. Clair River between limits of 
27.1 to 30 feet to provide safe navigation by vessels with drafts of 25.5 
feet. A cutoff Channel in Canada at Southeast Bend and abandon old 
Southeast Bend Channels. 
Deauthorization of the work authorized by the River and Harbor Act of 
Jul. 24, 1946. 
ST. JOSEPH HARBOR, MI (See Section 57 of Text) 
Interior Revetments. 26 
Benton Harbor Canal. 26 
Present Project dimensions of Piers and a Turning Basin. 
Present project dimensions of Paw Paw River. 
Abandon easterly 1,000 feet of Channel above West Line of 9th St. 
Thrning Basin above mouth of Morrison Channel and eliminate Turning 
Basin near mouth of Paw Paw River. 
Maintenance of Turning Basin near mouth of Paw Paw River. 
ST. MARYS RIVER, MI (See Section 58 of Text) 
Weitzel Lock (Replaced in 1943 by MacArthur Lock), widen and deepen 
existing State Channel.26 
Poe Lock.' 
Dredging through shoals above falls and shoals below falls between lower 
end of Canal and upper entrance Channel into Lake Nicolet (formerly 
Hay Lake). 
Enlarging the Old Channel. 
Lake Nicolet and Neebish Channels work in that section of River below 
Locks. 
Davis Lock Second Canal, and Emergency Dam. 
Lease of Waterpower at Falls. Lease entered into with Michigan Northern 
Power Co. provided for construction of remedial and compensating 
works. 
Fourth Lock (Renamed 'Sabin' Lock in 1943). 
Deepen Tailrace of Power Plant. 
Widen upper approach to Canals through Vidal Shoals, extend anchorage 
and maneuver area below Locks. 
Remove Round Island, middle ground extension of Northwest Canal Pier, 
and widen Channels Middle Neebish Route. 
Documents 
H. Doc. 576, 75th Cong., 3d Sess. 
H. Doc. 500, 83rd Cong., 2d Sess. 
H. Doc. 554, 87th Cong., 2d Sess. 
H. Doc. 240, 89th Cong., 1st Sess.' 
H. Doc. 207, 51st Cong., 2d Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
H. Doc. 309, 77th Cong., 1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess. 
H.R.6 (Formerly S. 1567), 99th 
Cong., 2d Sess. (W.R.D.A. of 1986) 
H. Ex. Doc. 160, 43rd Cong., 2d 
Sess., and Annual Report 1875, pt. 1, 
p. 162 
Annual Report 1880, pp. 2030, 2031 
and 2049, 2055. 
H. Doc. 307, 55th Cong., 2d Sess., 
and Annual Report 1898, p. 2496. 
Rivers and Harbors Comm. Doc. 52, 
74th Cong., 1st Sess. 
H. Doc. 129, 76th Cong., 1st Sess. 
S. Doc. 95, 84th Cong., 2d Sess.' 
Report by Maj. O. M. Poe, Corps of 
Engineers, not published. 
H. Ex. Doc. 72, 49th Cong., 2d Sess. 
H. Ex. Doc. 207, 51st Cong., 2d Sess. 
and Annual Report 1891, p. 2810 
H. Doc. 138, 56th Cong., 2d Sess., 
and 215, 58th Cong., 3d Sess. 
H. Doc. 128, 56th Cong., 2d Sess. 
H. Doc. 333, 59th Cong., 2d Sess. 
(Plan 3) 
H. Doc. 65, 62d Cong., 1st Sess. 
District Engineer Report, Oct. 29, 
1920. 
H. Doc. 270, 69th Cong., 1st Sess. 
21-54

TABLE 21-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 3, 1930 
Jun. 26, 1934' 
Aug. 30, 1935 
Mar. 7, 1942 
Jun. 15, 1943 
Mar. 2, 1945 
Jul. 24, 1946 
Mar. 21, 1956 
Jul. 9, 1956 
Nov. 17, 1986 
Jun. 3, 1896 
Mar. 2, 1907 
Jun. 25, 1910 
Jul. 3, 1958 
Jun. 3, 1896 
Mar. 2, 1907 
Jan. 21, 1927 
Aug. 30, 1935 
Sep. 3, 1954 
Aug. 11, 1888 
Mar. 3, 1905 
Aug. 30, 1935 
Deepen Channels throughout downbound Route. 
Operation and Care of Canal and Locks provided from War Department 
Appropriations for Rivers and Harbors. 
Widen Brush Point Turn and Channel from Brush Point to Point Louise. 
Construct new (MacArthur) Lock on site of former Weitzel Lock, deepen 
approach Channels to 27 feet, and reconstruct approach Piers. 
Name 'MacArthur' Lock and changed name of 'Fourth' Lock to 'Sabin' 
Lock. 
Remove Bridge Island and construct new Hydroelectric Power Plant. 
Replace Poe Lock at St. Marys Falls Canal with a new structure 800 feet 
long, 100 feet wide and 32 feet deep with necessary construction of Nose 
and Center Piers, and widen and deepen Channel across Point Iroquois 
Shoals and in Lake Nicolet to provide wider anchorage and maneuver 
areas in St. Marys River. 
Deepen to provide a Project Safe Draft of 25.5 feet over full width to 
downbound and 2-way Channels (including anchorage areas) and over 
Westerly 300-foot width of upbound Middle Neebish Channel, when levels 
of Lakes Superior and Huron are at their respective low-water 
datums. 
Repeal Authorization of Bridge as a part of Project, authorize alteration 
with cost to be apportioned by Sec. 6, Truman Hobbs Act, June 21, 1940. 
Construct a second large lock 1,294 feet in length, 115 feet in width, and 32 
feet in depth, adjacent to the existing lock. The replacement lock is to be 
located in the North Canal of the St. Marys Falls Canal at Sault Ste. 
Marie, MI, on the site of the existing Davis and Sabin Locks. 
SAUGATUCK HARBOR AND KALAMAZOO RIVER, MI 
(See Section 59 of Text) 
Entrance Channel, Piers and Revetments. 
Deepening entrance to 16 feet. 
Deepening Channel in River to 14 feet. 
SAXON HARBOR, WI (See Section 60 of Text) 
Provides for east and west breakwaters, an outer channel 10 feet deep, an 
inner basin and side channel 8 feet deep, and diversion of Oronto Creek 
to Parkers Creek by three short reaches of channel excavation and a 
levee. 
SEBEWAING RIVER, MI (See Section 61 of Text) 
Entrance Channel 8 feet deep, 100 feet wide and 15,000 feet long in 
Saginaw Bay. 
SHEBOYGAN HARBOR, WI (See Section 62 of Text) 
North breakwater. 
Preserving south pier as part of project, providing turning basin, and elimination 
of proposed south breakwaters. 
Present project dimensions of channel. 
Widen and deepen outer harbor entrance channel to 450 feet, widen and 
deepen river channel from present project limit to north side of Jefferson 
Ave. 
SOUTH HAVEN HARBOR, MI (See Section 63 of Text) 
Channel from Inner End of Piers to Highway Bridge.' 2 
Present dimensions of Piers and for a Thrning Basin. 
Present Project dimensions of Channel and Thrning Basin. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Comm. Doc. 53, 
74th Cong., 1st Sess. 
H. Doc. 218, 77th Cong., 1st Sess. 
H. Doc. 679, 78th Cong., 2d Sess. and 
H. Doc. 339, 77th Cong., 1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess.' 
None 
H.R.6 (formerly S. 1567), 99th 
Cong., 2d Sess. (W.R.D.A. of 1986) 
H. Doc. 912, 54th Cong., 1st Sess. 
Annual Report 1896, Vol. 2. Pt. 5, p. 
2739 
Annual Report 1907, p. 6416 
H. Doc. 635, 61st Cong., 2d Sess. 
River and Harbor Act, H. Doc. 169, 
85th Cong., 1st Sess.,' Annual Report 
for 1965, p. 1025. 
H. Doc. 71, 54th Cong., 1st Sess. 
H. Doc. 62, 59th Cong., 1st Sess. 
H. Doc. 475, 68th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 47, 74th Cong., 1st Sess. 
H. Doc. 554, 82d Cong., 2d Sess.' 
No Prior Survey or Estimate. 
H. Doc. 119, 58th Cong., 2d Sess. 
Rivers and Harbors Comm. Doc. 9, 
73d Cong., 1st Sess.' and unpublished 
review Report of Chief of Engineers, 
Dated Dec. 21, 1934. 
21-55

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 3, 1873 
Jul. 13, 1892 
Jun. 13, 1902 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 5, 1886 
Aug. 5, 1886 
Aug. 30, 1935 
Nov. 7, 1945 
Jul. 14, 1960 
Mar. 3, 1871 
Mar. 2, 1907 
Aug. 30, 1935 
Jul. 3, 1958 
Mar. 2, 1945 
Aug. 17, 1967 
Mar. 2, 1867 
Mar. 3, 1873 
Jul. 5, 1884 
Jul. 13, 1892 
Mar. 2, 1907 
Jul. 23, 1985 
Jul. 3, 1958 
Aug. 18, 1941 
STURGEON BAY AND LAKE MICHIGAN SHIP CANAL, WI 
(See Section 64 of Text) 
Breakwaters. '2 
Acquisition of the canal. 
Canal revetments and consolidation of canal and harbor works. 
Present project dimensions of channels and elimination of turning basin 
immediately west of revetted canal. 
Turning basin between city and Bushman wharves. 
TWO HARBORS, MN (See Section 65 of Text) 
Breakwater and dredging. 
Construction of two breakwater piers. 
Shore connection to east breakwater and dredging maneuvering area. 
Construct new east breakwater and enlargement of maneuvering basin. 
Deepen harbor project depths from 26 and 28 feet to 28 and 30 feet, respectively. 
TWO RIVERS HARBOR, WI (See Section 66 of Text) 
South pier, 750 feet of north pier, and about 44 feet of north revetment.' 2 
Remainder of north pier and stilling basin. 
Deepening entrance channel and inner basin to 18 feet. 
Extend existing project in West Twin River to 18 feet deep and in East Twin 
River to 10 feet deep to 22d Street Bridge. 
WHITEFISH POINT HARBOR, MICH. (See Section 67 of Text) 
Breakwaters, Entrance Channel, Anchorage Basin. 
Breakwater Inside Harbor. 
WHITE LAKE HARBOR, MI (See Section 68 of Text) 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
Present Project Depth of Channel. 
PAW PAW LAKE, MI (See Section 76 of Text) 
Construct a gated control structure at the Paw Paw Lake outlet; a 1,722 
foot long, 72-inch reinforced concrete drainage from the Lake to Paw 
Paw River; entrance and exit structures to improve efficiency and provide 
protection; and two small levees. 
SAGINAW RIVER, MI FLOOD CONTROL 
(See Section 77 of Text) 
Flood Control improvements to Saginaw River and its tributaries including 
Tittabawassee, Shiawassee, Flint, and Cass Rivers. 
SEBEWAING, SEBEWAING RIVER, MI 
(See Section 78 of Text) 
Enlarging present Channel of Sebewaing River, altering Railroad and 
Highway Bridges, removal of Dike. 
H. Ex. Doc. 34, 42d Cong., 2d Sess. 
Annual Report, 1872, p. 171. 
H. Ex. Doc. 106, 49th Cong., 2d Sess. 
H. Doc. 117, 56th Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
9, 74th Cong., 1st Sess. 
H. Doc. 421, 78th Cong., 2d Sess. 
H. Ex. Doc. 94, 48th Cong., 2d Sess. 
Annual Report for 1887, p. 1952 
Rivers and Harbors Comm. Doc. 17. 
72d Cong., 1st Sess. 
H. Doc. 805, 78th Cong., 2d Sess. 
H. Doc. 146, 86th Cong., 1st Sess.' 
Annual Report, 1871, p. 123 (as modified 
by Chief of Engineers, Feb. 27, 
1897). 
H. Doc. 730, 59th Cong., 1st Sess. 
Modification of Plan A. 
Rivers and Harbors Committee Doc. 
25, 73d Cong., 2d Sess. 
H. Doc. 362, 84th Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
Chief of Engineers. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
No Prior Survey or Estimate. 2" 
Section 205, 1948 Flood Control Act 
H. Doc. 346, 84th Cong., 2d Sess.' 
H. Doc. 286, 76th Cong., 1st Sess.' 
21-56

TABLE 21-B (Continued) 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
'Contains latest published map. 
'Including Emergency Relief Administration Work authorized 
May 28, 1935. 
3Included in Public Works Administration Program September 
6, 1933. 
'This modification deauthorized August 5, 1977, under Section 
12, Public Law 93-251. 
SAdministrative Act, Section 4. 
'Public Law 568, 82d Congress. 
'Public Law 388, 87th Congress. 
'This portion inactive. 
'Permanent Appropriations Repeal Act. 
"Transfer completed June 1962. 
"Amended 1868, 1879, 1892. 
"Completed under previous project. 
"'Included in Public Works Administration Program January 3, 
1934. 
"Inactive portion; removal of 200 linear feet of north pier, widening 
inner 200 feet of channel through outer basin, and closing 
gap in north shore connection of breakwater. 
'SLatest published map is in Annual Report 1914, p. 2974. 
"Latest published map in Annual Report 1914, p. 2914. 
"Superceded by Act of October 23, 1962. 
"Uncompleted portion was deauthorized in 1977 (dredging Milwaukee 
River from Buffalo St. Bridge to North Humboldt 
Ave. Bridge). 
"Modified by Act of June 10, 1872. 
'"Riprapping of protecting dikes portion of project is inactive. 
2"War Department Appropriations Act. 22Latest published map is in House Document 588, 64th Cong., 
1st Sess. 
"Contains latest published maps. See also map with Rivers and 
Harbors Committee Doc. 19, 72d Cong., 1st Sess. 
UExcept for dredging 25-foot channel to 1,150 feet upstream of 
mouth in old channel, work authorized in this Act is considered 
inactive. 
"This modification deauthorized August 5, 1977, under Section 
12, Public Law 93-251. 
26Completed under previous projects. Public Law 130, 75th 
Cong., 1st Sess. 
"Latest published map is in H. Doc. 2053, 64th Cong., 2d Sess. 
"Project complete except for Work Authorized by River and 
Harbor Act of 1950. 
"Work recommended in H. Doc. 588, 64th Cong., 1st Sess. 
3"Deauthorized in 1977. 
21-57

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation & 
Project Status Report for Construction Maintenance 
Alpena Harbor, MI Completed 1985 337,394' 943,697 
Algoma Harbor, MI Completed 1981 205,0102 937,883 
Bayfield Harbor, WI Completed 1979 183,855 89,585 
Belle River, MI Completed 1980 24,301 78,516 
Beaver Bay, MN Active 1982 293,000 2,818 
Big Bay Harbor, MI Completed 1988 390,433' 1,208,384 
Black River (Alcona Co), MI Inactive 1907 0 0 
Caseville Harbor, MI Completed 1988 587,314 361,007 
Cedar River Harbor, MI Active 1982 215,000 0 
Chnls. in the Straits of Mackinac, MI Completed 1984 2,832,629 223,354 
Cheboygan Harbor, MI Completed 1988 504,236 895,263 
Chippewa Harbor, Isle Royale, MI Completed 1959 125,629 13,528 
Cornucopia Harbor, WI Completed 1988 462,653 865,151 
Cross Village, MI Active 1983 364,000 0 
Grays Reef Passage, MI Completed 1970 190,521 709,571 
Greilickville Harbor, MI Completed 1976 366,579 139,513 
(Formerly Traverse City Harbor, MI) 
Hammond Bay Harbor, MI Completed 1988 1,092,366 494,587 
Harrisville Harbor, MI Completed 1988 2,639,392 1,061,193 
Kawkawlin River, MI Completed 1986 0 241,700 
Knife River Harbor, MN Active 1986 412,945 288,478 
La Pointe Harbor, WI Completed 1986 139,874 94,966 
Les Cheneaux Islands Channels, MI Completed 1980 399,478 324,036 
Little Bay DeNoc, Gladstone Harbor, MI Completed 1966 332,832 98,455 
Lutsen Harbor, MN Active 1982 357,000 0 
Mackinaw City Harbor, MI Completed 1986 136,286' 85,684 
Northport Harbor, MI Inactive - 0 0 
Oconto Harbor, WI Completed 1985 130,7545 1,152,5516 
Pensaukee Harbor WI Completed 1986 0 28,182 
Petoskey Harbor, MI Completed 1986 123,839 551,052 
Pine River, MI Completed 1980 13,649 40,646 
Presque Isle Harbor, MI Completed 1988 1,252,192 998,665 
St. James, Beaver Island, MI Completed 1957 49,1717 65,842 
St. Joseph River, MI ' Completed 1975 54,555 19,185 
Tawas Bay Harbor, MI Completed 1986 1,955,745" 25,288 
Washington Island, WI Completed 1950 62,838 71,708 
'Includes $18,899 for previous projects. 
I2ncludes $92,774 for previous projects. 
3Excludes $56,500 Contributed Funds. 
'Excludes $136,286 for Contributed Funds. 
Slncludes $84,569 for previous projects. 
'Includes $8,161 for previous projects. 
'Excludes contributed funds of $7,500. 
8Includes $834,677 Contributed Funds. 
21-58

TABLE 21-E 
DETROIT, MI DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation & 
Project Status Report for Construction Maintenance 
Kalamazoo River (Battle Creek) MI'.' Deferred 1975 4,471,235 - 
Kalamazoo River (Kalamazoo) MI2 Active 1975 421,466 - 
Mount Clemens, Clinton River, MI Completed 1953 1,136,0083 - 
Upper River Rouge, MI4 Inactive 1968 7,935 
River Rouge, MI Completed 1981 31,960,332 
'Includes $108,335 Contributed Funds. 3Includes $202,996 Contributed Funds. 
2Scheduled for deauthorization on Dec. 31, 1989, in accordance 4Planning indefinitely suspended due to lack of local cooperawith 
Section 1001 of the W.R.D.A. of 1986 (P.L. 99-662). tion. 
TABLE 21-F MULTIPLE PURPOSE PROJECTS, INCLUDING POWER 
ST. MARYS RIVER, MI: EXISTING PROJECT 
(SEE SECTION 58 OF TEXT) 
Lock Davis Sabin MacArthur New Poe 
Miles Above Mouth 47 47 47 47 
Clear Width of Chamber Feet 80 80 80 110 
Length Between Gate Quoins Feet 1,350 1,350 800 1,200 
Lifts Feet 21.7 21.7 21.7 21.7 
Depth Over Upper Breast Walls' Feet 24.3 24.3 31 32 
Depth Over Lower Breast Walls' Feet 23.1 23.1 31 32 
Foundation Rock Rock Rock Rock 
Type of Construction Concrete Concrete Concrete Concrete 
Estimated Cost $6,200,0002 $3,275,000 $12,909,440 $39,000,000 
Actual Cost $2,200,000' $1,750,0006 $12,718,8064., $34,813,066 
Completed (Open to Commerce) Oct. 21, 1914 Sep. 18, 1919 Jul. 11, 1943 Jun. 26, 1969 
Emergency Dam for South Canal North Canal 
Miles Above Mouth 47 47 
Estimated Cost 9- $300,000 
Type Steel Stoplogs Recessed Steel Stoplogs Recessed 
Into Lock Masonry Into Lock Masonry 
Cost Completed _' $169,224' 
Year Completed 1943 1922 (Modified 1963) 
'At low water datum 599.5 above and 577.8 below. 
'Includes Cost of North Canal. 
3Includes cost of canal excavations to provide necessary 
approaches to lock, canal walls, piers and emergency dam, 
$662,919. 
4Excludes cost of deepening and enlarging South Canal, 
$1,653,378. 
'Excludes cost of North Canal, $2,572,611. 
Note: Limiting draft to locks is determined by depth over breast walls. 
6Excludes cost of canal excavations to provide necessary 
approaches to lock, canal walls, piers, and emergency dam, 
$662,919. 
'Excluding cost of lower guard gates which were never 
installed. 
'Including engineering office, and inspection. 
9Not separate from cost of locks. 
21-59

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Berrien County, MI 1963 Nov. 1986 0 0 
(St. Joseph Shore) beach erosion control 
(1958 Flood Control Act) 
Black River Harbor, MI 1976 Nov. 1977 0 0 
(Aug. 30, 1935 R&H Act) 
Detroit River, Trenton Chnl., MI 1976 Aug. 1977 0 0 
(May 17, 1950 R&H Act) 
Forestville Harbor, MI 1969 Nov. 1986 0 0 
(1968 R&H Act) 
Grand Haven Harbor, MI 1976 Nov. 1977 0 0 
(Mar. 2, 1945 R&H Act) 
Grand River at Grandville, MI 1966 Nov. 1977 0 0 
(Oct. 27, 1965 Flood Control Act) 
Kewaunee River, WI 1976 Aug. 1977 0 0 
(1960 R&H Act) 
Lansing (Grand River), MI 1971 Jun. 1981 7,000 0 
(Jul. 3, 1958 Flood Control Act) 
Pentwater Harbor, MI 1976 Nov. 1977 0 0 
(Jul. 13, 1892 R&H Act) 
Racine Harbor, WI 1963 May 1986 9,441,554 0 
(Mar. 2, 1907; Aug. 26, 1937; Mar. 2, 1945, R&H Acts 
and Section 107 of the 1960 R&H Act) 
Red Run Drain, Lower Clinton River, MI 1983 Nov. 1986 3,823,000 0 
(1970 Flood Control Act) 
Rogers City Harbor, MI 1926 Aug. 1977 5,892 0 
(Jun. 25, 1910 R&H Act) 
Rouge River, MI 1976 Aug. 1977 22,000 0 
(Oct. 23, 1962 R&H Act) 
Rouge River, MI 1976 Aug. 1977 12,000 0 
(Jul. 3, 1958 R&H Act) 
Rouge River, MI 1976 Aug. 1977 0 0 
(Aug. 30, 1935 R&H Act) 
St. Clair River Compensating Works, MI 1976 Aug. 1977 0 0 
(Jul. 3, 1930 R&H Act) 
South Milwaukee Harbor, WI 1906 Aug. 1977 0 0 
(1836 Flood Control Act) 
St. Marys River (MacArthur Lock Guard Gates), MI 1977 Oct. 1978 0 0 
(Mar. 7, 1942 R&H Act) 
21-60

DETROIT, MI DISTRICT 
FEATURES OF EXISTING PROJECT 
Project 
Datum Planes 
Length Miles Used by Above Mean 
of from Upbound Water Level 
Channel Mouth or Down- Project Project at Father 
of bound Width Depth Point, Quebec Year 
Name of Channel (Feet) River Vessels (Feet) (Feet) (Feet) Complete 
DETROIT RIVER, MI (SEE SECTION 13 OF TEXT) 
Channel North of Belle Isle' 2 
Channel at Head of Detroit River 
Miscellaneous Shoals and Obstructions 
Belle Isle to Fighting Island Channel 
Fighting Island Channel 
Ballards Reef Channel North of Junction 
with Livingstone Channel 
Livingstone Channel Upper 
Livingstone Channel Lower: 
CS 260 + 00 to 368 + 87 
CS 368 + 87 to 492 + 00 
East Outer Channel 
Misc., Shoals and Obstructions, 
Detroit River to Pelee Passage 
Pelee Passage Shoal 
Amherstberg Channel: 
Upper Section, Ballards Reef Channel 
Middle Section 
Lower Section, Hackett Range 
West Outer Channel 
Trenton Channel: 
Wyandotte Reach 
Trenton Reach (Upper) 
Trenton Reach (Lower) 
Grosse Ile Shoal 
30 
38,800 32 
44,500 25 
Both 
Both 
Both 
24,800 17 Both 
12,200 12 Both 
26,000 10 Down 
10,887 
12,313 
42,000 
5 Down 
Both 
Both 
- - Both 
- - Both 
6,500 
12,000 
24,000 
21,000 
31,500 
5,100 
600 
600 
10 
17 
14 
14 
Up 
Up 
Up 
Down 
Local 
Local 
Local 
Local 
200 
800 
800 
600 
450 
450,800 
800-1,200 
1,200 
21.0 571.3 
28.5 571.5-570.9 
28.5 570.9-570.3 
28.5 
28.5 
569.8 
569.8 
27.7 569.8-568.6 1964 
29.0 
29.0 
28.5 
568.6 
568.6 
568.6 
- 28.5-29.53 568.6 
- 29.5 568.6 
600 
600 
6,000 
800 
300 
300 
250-300 
27.5 
21.27.5� 
21.28.5" 
22.0 
27.0 
28.0 
28.0 
20.0 
569.8-569.5 
569.5-568.9 
568.9-568.6 
568.6 
569.7-569.6 
569.6-568.8 
569.8 
ST. CLAIR RIVER, MI (SEE SECTION 56 OF TEXT) 
Channel at Foot of Lake Huron 
Channel North of Blue Water Bridge 
Port Huron to Stag Island 
Widening at Upper and Lower 
Ends of Stag Island 
St. Clair to Russell Island 
Russell Island to Southeast Bend 
Southeast Bend CS 324 + 00 to 250 + 00 
Cutoff Channel 
North Channel 
26,500 44 
4,100 39 
38,000 
37,600 
77,000 
20,600 
7,400 
30,300 
8,000 
39 
31 
24 
11
5 
Both 
Both 
Both 
Both 
Both 
Both 
Both 
Both 
Small 
Craft 
800 
800 
800 
900-1,000 
1,000 
700-1,000 
700 
700 
100 
30.0 576.8-576.5 1961 
30.0 576.4-576.1 1962 
30.0 
27.4 
27.3 
17.2 
27.1 
27.1 
10.0 
576.4-576.1 
574.9-573.8 
573.8-572.4 
572.4-572.1 
573.1-572.0 
572.1-571.7 
571.7 
1961 
1962 
1962 
1962 
1962 
1962 
1962 
'This is a Side Channel 
2Extends from Deep Water Near Windmill Point to a Point 
Opposite Fairview Slip, about 3,000 Feet. 
3Project Depth 29.5 feet over Rock Shoals and 28.5 feet over 
other than Rock Shoals. 
4Project Depth 21 feet in Easterly 300-foot width of Channel 
and 27.5 feet in Westerly 300-foot width. 
"Project Depth 21 feet in Easterly 300-foot width of Channel 
and 28.5 feet in Westerly 300-foot width. 
6Project Complete Except for Work Authorized by River and 
Harbor Act of 1950. 
21-61 
TABLE 21-H 
1964 
1964 
1964 
1962 
1963 
1961 
1961 
1964 
1962 
1964 
1960 
1960 
1960 
1929 
19646 
1964 
1941 
1904

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 21-I FOX RIVER, WI: LOCKS AND DAMS 
(SEE SECTION 16 OF TEXT) 
Depth At 
Normal Pool 
Miles Avail-' Lower 
from Dis- Clear able Breast Miter Character Kind Year 
Green Nearest tance Width Length Lift Wall' Sill of of Type of Com- 
Name of Lock and Dam Bay Town (miles) (feet) (feet) (feet) (feet) (feet) Foundation Dam Construction plete 
De Pere lock] 7.1 De Pere - 36.0 146.0 8.9 10.3 12.0 Rock - Concrete 1936 
De Pere dam 7.2 De Pere - - - - - - Rock Fixed. Concrete 1929 
Little Kaukauna lock2 13.0 De Pere 6 36.0 146.0 7.2 8.0 9.5 Clay - Concrete 1938 
Little Kaukauna dam 2 13.1 De Pere 6 . - . -..- - - Clay and gravel Fixed Piers and concrete 1926 
Rapide Croche lock 19.2 Wrightstown 2 36.0 146.0 8.3 8.8 9.3 Rock - Concrete 1934 
Rapide Croche Dam 19.3 Wrightstown 2 - - - - - Rock Fixed" Concrete 1930 
Kaukauna fifth lock 22.8 Kaukauna - 35.6 144.0 9.1 6.7 9.3 Rock - Composite 1898 
Kaukauna fourth lock 23.1 Kaukauna - 36.6 144.1 10.2 6.9 6.0 Rock - Stone masonry 1879 
Kaukauna third lock 23.3 Kaukauna - 30.6 144.0 10.2 6.9 6.3 Rock - Stone masonry 1879 
Kaukauna second lock2 23.4 Kaukauna - 35.0 144.0 9.6 6.0 6.0 Rock - Stone masonry 1903 
Kaukauna first lock 23.6 Kaukauna - 35.1 144.4 11.0 6.9 6.0 Rock - Stone masonry 1883 
Kaukauna Dam2 24.0 Kaukauna - - - - - - Rock Fixed. Concrete 1931 
Kaukauna guard lock 24.0 Kaukauna - 40.0 - - 9.4 - Rock - Stone masonry 1891 
Little Chute combined lock: 
Lower 24.4 Little Chute 1 35.4 146.5 10.9 6.0 8.6 Rock - Stone masonry 1879 
Upper 25.4 Little Chute 1 36.3 144.1 10.6 7.6 6.0 Hardpan - Stone masonry 1879 
Little Chute second lock 26.4 Little Chute - 35.0 144.2 13.8 8.0 6.1 Rock - Stone masonry 1881 
Little Chute first (guard) lock' 26.5 Little Chute - 35.4 - - 6.6 - Rock - Stone masonry 1904 
Little Chute Dam 26.6 Little Chute - - - - - - Rock Fixed3' Concrete 1932 
Cedars lock 27.3 Little Chute 1 35.0 144.0 9.8 6.8 7.3 Rock - Stone masonry 1888 
Cedars Dam 27.4 Little Chute 1 - - - - - Rock Fixed. Concrete 1933 
Appleton fourth lock 30.7 Appleton 1 35.0 144.0 7.6 8.1 7.9 Rock - Stone masonry 1907 
Appleton lower dam 30.9 Appleton 1 - - - - - Rock Fixed3' Concrete 1934 
Appleton third lock 31.3 Appleton - 35.0 144.0 8.7 6.0 8.6 Rock - Stone masonry 1900 
Appleton second lock 31.6 Appleton - 35.1 144.6 9.6 6.9 6.0 Clay - Stone masonry 1901 
Appleton first lock 31.9 Appleton - 35.0 144.7 10.0 6.6 6.0 Rock - Stone masonry 1884 
Appleton upper dam 32.2 Appleton - - - - - - Rock. Fixed3 Concrete 1940 
Menasha lock 37.0 Menasha - 35.4 144.0 8.5 7.2 8.0 Clay - Composite 1899 
Menasha Dam 37.8 Menasha - - - - - - Hardpan Fixed Concrete 1937 
'Depth shown is on breast wall, which is controlling depth for 
upper pool. 
2Original structure built prior to assumption of control by 
United States on Sep. 18, 1872. 
'Provided with sluices. 
'Flash boards used. 
sPartially rebuilt. 
21-62 
Actual 
Cost 
$229,308 
209,536 
362,427 
179,398 
228,738 
118,975 
13,310' 
37,536 
39,948 
24,313 
38,704 
123,763 
12,630 
102.304 
48,555 
7,817 s 
82,554 
34,972 
84,973 
40.893 
73,903 
32.238 
22,940 
36,004 
151,558 
19,326 s 
84,686

TABLE 21-J 
DETROIT, MI DISTRICT 
RECONNAISSANCE & CONDITION SURVEYS 
Name of Project Date Survey Conducted 
ALGOMA HARBOR, WI 
ALPENA HARBOR, MI 
BAYFIELD HARBOR, WI 
BELLE RIVER HARBOR, MI 
BIG BAY HARBOR, MI 
CASEVILLE HARBOR, MI 
CHANNELS IN STRAITS OF MACKINAC, MI 
CHEBOYGAN HARBOR, MI 
CORNUCOPIA HARBOR, WI 
GRAYS REEF PASSAGE, MI 
GREILICKVILLE HARBOR, MI 
HAMMOND BAY HARBOR, MI 
HARRISVILLE HARBOR, MI 
KNIFE RIVER, MN 
LAPOINTE HARBOR, WI 
LES CHENEAUX ISLAND CHANNELS, MI 
LITTLE BAY DENOC, MI 
MACKINAW CITY HARBOR, MI 
OCONTO HARBOR, WI 
PENSAUKEE HARBOR, WI 
PETOSKEY HARBOR, MI 
PINE RIVER HARBOR, MI 
PORT WING HARBOR, WI 
PRESQUE ISLE HARBOR, MI 
ST. JAMES HARBOR, MI 
TAWAS BAY HARBOR, MI 
NOVEMBER 1988 
SEPTEMBER 1989 
JULY 1989 
JUNE 1989 
AUGUST 1989 
APRIL 1989 
JUNE 1989 
MAY 1989 
JULY 1989 
AUGUST 1989 
APRIL 1989 
MAY 1989 
JUNE 1989 
JULY 1989 
JULY 1989 
SEPTEMBER 1989 
JULY 1989 
MAY 1989 
OCTOBER 1988 
FEBRUARY 1989 
OCTOBER 1988 
JUNE 1989 
JULY 1989 
AUGUST 1989 
JUNE 1989 
JUNE 1989 
21-63

CHICAGO, ILLINOIS, DISTRICT * 
This district comprises Cook, McHenry, Lake, Kane, DuPage Indiana, including a portion of LaPorte County along Lake Michiand 
Will Counties in Illinois, and Lake and Porter Counties in gan. 
IMPROVEMENTS 
Page 
22-2 
22-2 
22-2-3 
22-3 
22-3 
22-4 
22-4 
22-4 
22-4-5 
22-5 
Navigation 
1. Burns Waterway Harbor, IN 
2. Burns Waterway SBH, IN 
3. Calumet Harbor and Rv. IL and IN 
4. Chicago Harbor, IL 
5. Chicago River, IL 
6. Indiana Harbor, IN 
7. Michigan City Harbor, IN 
8. Waukegan Harbor, IL 
9. Reconnaissance and Cond. Surveys 
10. National Emergency Preparedness 
Alteration of Bridges 
11. Other Authorized Bridge Alteration 
Beach Erosion Control 
12. Indiana Dunes National Lakeshore 
(Beverly Shores, IN) 
13. Indiana Shoreline, IN 
14. Other Authorized Beach Erosion 
15. Beach Erosion Control Under 
Special Authorization 
Flood Control 
16. Chicago River, IL (North Branch) 
17. Lake Michigan, Edgewater/Rogers 
Park Communities, Chicago, IL 
18. Little Calumet River, IN 
19. McCook and Thornton Reservoirs, IL 
20. North Branch Chicago River, IL 
21. O'Hare Reservoir, IL 
22. Other Auth. Flood Control Projects 
23. Flood Control Work Under Special 
Authorization 
General Investigation 
22-5 24. Surveys 
25. Collection and Study of Basic Data 
26. Continuation of Planning and 
22-5 
22-5 
22-5 
22-5 
27. 
28. 
TITLE 
Cost and Financial Statement ............... ................. 
Authorizing Legislation....................................... 
Existing Projects .......................................... 
Other Authorized Bridge Alteration .............................. 
Other Authorized Beach Eros. Projects ........................... 
Other Authorized Flood Control Projects ........................... 
Deauthorized Projects ................. .................... 
Engineering 
Advance Engineering and Design 
Miscellaneous 
TABLES 
22-A 
22-B 
22-C 
22-D 
22-E 
22-F 
22-G 
Page 
22-5 
22-6 
22-6 
22-6-7 
22-7 
22-7 
22-7 
22-7-8 
22-8 
22-8 
22-8 
22-8 
22-8 
PAGES 
22-9-11 
22-12-14 
22-15 
22-16 
22-16 
22-16 
22-16 
22-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. BURNS WATERWAY HARBOR, IN 
Location. Northwestern Indiana on the southern shore of Lake 
Michigan in Porter County, 28 miles southeast of Chicago Harbor. 
(see NOAA Nautical Charts Numbers 14905 and 14926). 
Existing Projects. Provides for (a) rubble mound north breakwater 
5,830 feet long; (b) a rubble mound west bulkhead 1,200 
feet long; (c) a stone filled steel sheet pile cell, west bulkhead 
shore connection 2,400 feet long; (d) an approach channel 30 
feet deep and 400 feet wide; (e) an outer harbor 28 feet deep; 
(f) an east harbor arm 27 feet deep and 620 feet wide; (g) a west 
harbor arm 27 feet deep and 620 feet wide. The project was authorized 
by the River and Harbor Act of 27 October 1965 (Public 
Law 89-298; House Document Number 160, 88th Congress, 
1st Session). The authorizing act also provided the Secretary of 
the Army to reimburse The State of Indiana for expenditure of 
funds used to construct such portions of the project as approved 
by the Chief of Engineers and constructed under supervision of 
the Chief of Engineers. See Table 22-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Seven berths and docks are available, 
three on the west harbor arm, one on the harbor basin, and three 
on the east harbor arm. One dock on the west harbor arm is used 
for shipment and receipt of steel products. One dock on the east 
harbor arm is used for receipt of iron ore pellets and limestone 
and shipment of steel products. Five facilities are administered 
by the Indiana Port Commission and are used for handling general 
cargo. 
Operations and results during period. 
Maintenance: Operations studies, surveys and reports were performed 
by hired labor at a cost of $39,499, by other COE at a 
cost of $12,041, and by contract cost of $27,867. E&D for the 
placement along the north breakwater was performed by hired 
labor at a cost of $2,746. Placement of the stone was performed 
by contract at a cost of $937,490. Project management and real 
estate costs were $43,512 and $7,255, respectively. Supervision 
and administration was performed by hired labor at a cost of 
$102,414. 
Condition at end of fiscal year. The existing project is complete. 
Total costs of existing project to September 30, 1989 were 
$18,975,953 of which $13,599,900, was for New Work 
($13,584,000 federal and $15,900 non-federal), and $5,376,053 
for maintenance. 
2. BURNS WATERWAY SBH, IN 
Location. Northwestern Indiana on the southeast shore of Lake 
Michigan in Porter County, at the mouth of the Burns Ditch, approx. 
35 miles southeast of Chicago. (See NOAA Nautical Chart 
Numbers 14905 and 14926). 
Previous Projects. None 
Existing Projects. Provides for (a) a rubble mound west 
breakwater 1,003 feet long; (b) a rubble mound north breakwater 
678 feet long; (c) channel improvement 5,200 linear feet, 
145,000 cubic yard dredged and used for beach nourishment. 
Local Cooperation. Fully complied with. 
Terminal Facility. There are several marinas located at Burns 
Ditch. The commodities handled at this harbor are fresh fish. 
Operations and results during period. 
Maintenance: Beach monitoring analysis and surveys were performed 
by hired labor at a cost of $51,768, and by contract at 
a cost of $46,840. Equipment and labor costs to remove and restack 
stones on the north breakwater by Detroit District were 
$35,097. Field sampling and lab analysis of wave data were performed 
by CERL at a cost of $15,000. Project management and 
program management costs were $21,606 and $2,971, respectively. 
Condition at the end of the fiscal year. Total cost of existing 
project to September 30, 1989 was $3,972,676 of which 
$3,766,593 was for New Work, ($1,999,921 federal and 
$1,766,672 non-federal), and $206,083 for maintenance. 
3. CALUMET HARBOR AND RIVER, 
IL and IN 
Location. Northeastern Illinois, on the southwest shore of Lake 
Michigan in Cook County, 15 miles south of Chicago Harbor, 
within corporate limits of the city of Chicago, except for breakwaters, 
an approach channel and an anchorage area which are 
in Illinois and Indiana (see NOAA Nautical Charts Numbers 
14926 and 14929). 
Previous Projects. For details see page 1400 of Annual Report 
for 1962. 
Existing Projects. Provides for (a) stone filled timber crib 
breakwater 6,714 feet long; (b) a stone filled double row steel 
sheet pile detached breakwater 5,007 feet long; (c) a north pier 
2,450 feet long; (d) an approach channel 29 feet deep and 3,200 
feet wide; (e) an outer harbor anchorage area 28 feet deep and 
3,000 feet wide; (f) an entrance channel 27 feet deep and 230 
to 290 to feet wide; (g) a channel in the Calumet River 27 feet 
deep and at least 200 feet wide to the north side of 130th Street; 
(h) three turning basins designated as numbers 1, 3, and 5; (i) 
a channel extending into Lake Calumet at a width of about 1,000 
feet. The project was authorized by the River and Harbor Act 
of 3 March 1899, 13 June 1902, 30 August 1935, 14 July 1960, 
23 October 1962, and 27 October 1965. See Table 22-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Thirty six docks, wharves, and terminals 
are available. The Chicago Regional Port District owns four 
wharves, two grain elevators, one dock, and one terminal. The 
United States Government owns one stone dock. The most important 
cargoes handled are iron ores and concentrates, coal, and 
lignite. 
Operations and results during period. 
Maintenance: Water quality activities were continued by contract 
at a cost of $99,400, and by hired labor at a cost of $62,749. 
Operation studies and reports were performed by hired labor at 
a cost of $10,460. Installation and retrieval of wave gauges were 
performed by WES at a cost of $12,853, by contract at a cost 
of $14,243 and by hired labor at a cost of $40,838. Field sampling 
and lab analysis of the wave data was performed by CERL 
at a cost of $75,664. Plans and specifications for the Coast Guard 
light and foundation were continued by hired labor at a cost of 
$33,822. Maintenance Dredging of 100,000 cubic yds of the outer 
harbor was performed by contract at a cost of $858,028. Conract 
administration was performed by hired labor at a cost of 
$8,595. E&D was performed by hired labor at a cost of $102,023. 
Project management and real estate management were performed 
by hired labor at a cost of $132,925 and $6,942, respectively. 
22-2

CHICAGO, IL, DISTRICT 
Under the major rehabilitation project, placement of stone on 
Reach A of the breakwater was performed by contract at a cost 
of $3,262,269. Engineering and design during construction was 
performed by hired labor at a cost of $91,762. Supervision and 
administration costs were $226,371. Project and real estate management 
were performed by hired labor at a cost of $30,192 and 
$2,383, respectively. 
Condition at end of fiscal year. The existing project is 79 % 
complete. Work remaining to be accomplished consists of widening 
and straightening the Calumet River in the vicinity of 106th 
Street and the inactive portion which consists of closing the gap 
between the breakwaters, and dredging minor shoals in the outer 
harbor. Total costs of existing project to September 30, 1989 
were $54,570,793 of which $22,578,567 was for new work 
($19,541,964 regular funds and $3,036,603 public work funds), 
$25,867,531 regular funds for maintenance, $836,667 non-federal 
funds for maintenance, and $5,288,028 regular funds for rehabilitation. 
4. CHICAGO HARBOR, IL 
Location. Northeastern Illinois on the southwest shore of Lake 
Michigan in Cook County, within the corporate limits of the City 
of Chicago, (see NOAA Nautical Charts Numbers 14926, 14927, 
and 14928). 
Previous Projects. See page 1396 of Annual Report for 1962. 
Existing Project. Provides for (a) a stone filled timber crib 
shore arm extension breakwater 2,250 feet long; (b) a stone filled 
timber crib exterior breakwater 5,421 feet long; (c) a rubble 
mound and stone filled concrete caisson southerly extension to 
the exterior breakwater 4,944 feet long, exclusive of 582 foot 
entrance gap enclosing an outer basin of about 970 acres; (d) a 
stone filled timber crib north pier 960 feet long; (e) a stone filled 
timber crib north inner breakwater 4,034 feet long with a 304 
foot shore return, and a 754 foot gap; (f) a stone filled timber 
crib south inner breakwater 2,544 feet long enclosing an inner 
basin of approximately 224 acres; (g) a lake approach channel 
29 feet deep and 800 feet wide; (h) a channel and maneuver area 
inside the exterior breakwater and exterior breakwater southerly 
extension 28 feet deep with a maximum width of 1,300 feet; (i) 
an inner basin 21 feet deep; (j) an entrance channel of 21 feet 
deep. The project was authorized by the River and Harbor Acts 
of 11 July 1870, 14 June 1880, 3 March 1899, 25 July 1912, 
2 March 1919 and 23 October 1962. See table 22-C. 
The Chicago Lock was constructed in 1938 by the Metropolitan 
Water Reclamation District of Greater Chicago. The deep 
draft lock is 600 feet long, 80 feet wide, and 23 feet deep and 
uses a steel cellular design. Operation and maintenance responsibilities 
in the interests of navigation were transferred to the Federal 
Government pursuant to Public Law 90-63 approved 30 July 
1983, Section 107 of the Public Law 97-88, and Memorandum 
of Agreement between the Department of Army and the Metropolitan 
Water Reclamation District of Greater Chicago. 
Local Cooperation. Fully complied with. 
Terminal Facilities. There are three docks, two for passenger 
excursion boats and one for cargo. The most important cargoes 
handled are sugar and non-metallic minerals. 
Operations and results during period. 
Maintenance: The lock operations contract was continued with 
International Research and Development, Inc. at a cost of 
$514,562. Other support for operations of the lock amount to 
$31,579. Surveys and soundings were performed by contract at 
a cost of $83,654 and by hired labor at a cost of $42,407. A wave 
gauge retrieval system was installed by other COE at a cost of 
$22,464. E&D for the rehabilitation of the lock was performed 
at a cost of $73,673. Rehabilitation of the lock was performed 
by contract at a cost of $365,856. Real estate costs were $19,959. 
Project management and contract administration cost were 
$137,079 and $42,711, respectively. 
Condition at end of fiscal year. The existing project is complete. 
Total costs of existing project to September 30, 1989 were 
$19,199,086 of which $4,342,822 was for new work, 
$13,529,664 for maintenance, and $1,326,600 for rehabilitation. 
5. CHICAGO RIVER, IL 
Location. Northeastern Illinois, in Cook County within the 
corporate limits of the City of Chicago. (See NOAA Nautical 
Charts Numbers 14926, 14927 and 14928.) 
Previous Projects. See page 1394 of Annual Report for 1962. 
Existing Project. Provides for (a) a channel 21 feet deep in 
the main river from its mouth at Rush Street to the junction of 
the North and South Branches (0.7 miles); (b) a channel 21 feet 
deep in the North Branch from the junction to North Avenue (2.22 
miles); (c) a channel 21 feet deep in the North Branch Canal (1.04 
miles); (d) a 21 foot deep North Branch Turning Basin just south 
of North Avenue; (e) a channel 9 feet deep in the North Branch 
from North Avenue to Addison Street. All dredging to within 
20 feet of existing docks. The project was authorized by the River 
and Harbor Acts of 3 March 1899, 13 June 1902, 2 March 
1907, and 24 July 1946. Portion of project authorized by River 
and Harbor Act of 1946 is in deferred-for-restudy category. See 
table 22-C. 
Local Cooperation. Fully complied with for completed modifications. 
River and Harbor Act of 24 July 1946 which provided 
improvement of channel is subject to condition that local 
interests furnish assurances they will hold the United States free 
from damages which may result from construction and maintenance 
of improvement. Requirement has not been complied with. 
Terminal Facilities. Six docks are available. The most important 
cargoes handled are sand, gravel and crushed rock. 
Operations and results during period. 
Maintenance: An environmental impact statement associated 
with the Confined Disposal Facility was continued by hired labor 
at a cost of $138,498. Data collection for water control and water 
quality activities was performed by hired labor at a cost of 
$494,166, by other federal agency at a cost of $430,576, by contract 
at a cost of $75,236 and by other COE at at cost of $22,784. 
Real estate and project management were performed by hired labor 
at a cost of $11,968 and $73,869, respectively. 
Condition at end of fiscal year. The project is complete except 
for dredging the channel between North Avenue and Addison 
Street as authorized by 1946 River and Harbor Act. Head of navigation 
for deep draft vessels are North Avenue, 5.97 miles from 
deauthorized Michigan Avenue Bridge. Under Section 1142, PL 
99-662, the Corps assumes responsibility for monitoring of the 
Diversion of Lake Michigan water into the Illinois waterway. 
The Corps assumes full diversion accounting responsibility in 
FY88. 
Total costs of existing project to September 30, 1989 were 
$12,780,125 of which $1,500,565 was for new work and 
$11.279.560 was for maintenance. 
22-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
6. INDIANA HARBOR, IN 
Location. Northwestern Indiana, on the southwest shore 
of Lake Michigan in Lake County, 19 miles southeast of Chicago 
Harbor. (See NOAA Nautical Charts Numbers 14926 and 
14929). 
Previous Projects. For details see page 1943 of Annual Report 
for 1915, and page 1520 of Annual Report for 1938. 
Existing Projects. Provides for (a) northerly rubble-mound 
breakwater 1,120 feet long; (b) an easterly concrete capped concrete 
caisson breakwater 201 feet long with a rubble mound extension 
2,324 feet long; (c) a lake approach channel 29 feet deep 
and 800 feet wide; (d) an anchorage and maneuver basin 28 feet 
deep; (e) a canal entrance channel 27 feet deep and 280 feet wide; 
(f) a main canal 22 feet deep; (g) a turning basin 22 feet deep; 
(h) the Forks Turning Basin 22 feet deep; (i) the Lake George 
Branch 22 feet deep; (j) the Calumet River Branch 22 feet deep. 
The project was authorized by the River and Harbor Acts of 4 
March 1913, 2 March 1919, 20 March 1922, 3 July 1930, 30 
August 1935, 26 August 1937, and 4 July 1960. See table 22-C. 
Local Cooperation. Substantially complied with. See the FY 
1986 Annual Report for full requirements. 
Terminal Facilities. Fifteen docks and wharves are available. 
Six docks for handling iron ore and limestone. Six docks for handling 
petroleum products. Three docks for handling gypsum, scrap 
metal and steel, and bulk products. 
Operations and results during period. 
Maintenance: Environmental studies and surveys were conducted 
by hired labor at a cost of $572,794, by contract at a cost of 
$151,477 and by other COE at a cost of $6,419. Project management 
and real estate costs were $8,842 and $5,923, respectively. 
Condition at end of fiscal year. The existing project is complete. 
Total cost of existing project to September 30, 1989 was 
$14,535,098, of which $4,909,648 was for new work and 
$9,625,450 was for maintenance. 
7. MICHIGAN CITY HARBOR, IN 
Location. Northwestern Indiana, on the southeast shore of Lake 
Michigan in LaPorte County, 38 miles southeast of Chicago Harbor. 
(See NOAA Nautical Charts Numbers 14905 and 14926.) 
Previous Projects. See page 1407 of Annual Report for 1962. 
Existing Project. Provides for (a) a stone filled timber crib 
detached breakwater 1,304 feet long; (b) a pile and steel sheeting 
west pier 835 feet long; (c) a stone filled timber crib, pile 
and steel sheeting east pier 2,276 feet long; (d) a stone filled timber 
crib east breakwater 1,000 feet long; (e) an entrance channel 
18 feet deep and 425 feet wide; (f) a turning basin 18 feet deep; 
(g) a channel in Trail Creek 18 feet deep; (h) a turning basin 18 
feet deep; (i) an outer basin 12 feet deep; (j) an outer basin 8 
feet deep; (k) a channel in Trail Creek 6 feet deep and 50 feet 
wide. The project was authorized by the River and Harbor Acts 
of 3 March 1889, 3 March 1905, 21 January 1927, 30 August 
1935, and Section 107 of 14 July 1960 approved on 30 September 
1966. See table 22-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. There are several marinas in the lower 
mile of Trail Creek. The commodity handled at this harbor is 
fresh fish. 
Operations and results during period. 
Maintenance: Sediment surveys and studies of the east and 
west pier were conducted by hired labor at a cost of $65,945 and 
by contract at a cost of $23,450. Plans and specifications for the 
capping of the Confined Disposal Facility and for resurfacing the 
concrete cap on the east pier were performed by hired labor at 
a cost of $87,322 and $82,180, respectively. Core sampling of 
the east pier was performed by contract at a cost of $2,803. Real 
Estate costs were $5,315. Program management for these activities 
was performed by hired labor at a cost of $8,920. 
Condition at end of fiscal year. The existing project is complete. 
Total costs of existing project to September 30, 1989 were 
$9,239,264 of which $1,287,057 was for new work ($1,256,257 
federal and $30,800 non-federal funds), $6,333,537 for maintenance, 
and $1,618,670 for rehabilitation. 
8. WAUKEGAN HARBOR, IL 
Location. Northeastern Illinois, on the Southwest shore of Lake 
Michigan in Lake County, 38 miles north of Chicago Harbor. 
(See NOAA Nautical Charts Numbers 14904 and 14905). 
Previous Projects. See page 1392 of Annual Reprot for 1962. 
Existing Projects. Provides for (a) northerly stone filled timber 
crib breakwater 588 feet long; (b) a stone filled reinforced concrete 
caisson shore connection 270 feet long; (c) a stone filled 
double row steel sheeting shore connection 640 feet long; (d) a 
single row steel sheeting shore connection 398 feet long; (e) a 
stone filled timber crib north pier 998 feet long; (f) a single row 
steel sheet piling north pier 444 feet long; (g) a steel piling revetment 
632 feet long; (h) a stone fille timber crib pier 1,399 
feet long; (i) a stone filled double row pile and sheeting south 
pier 1,712 feet long; (j) an entrance channel 22 feet deep and 
390 feet wide; (k) a channel between the piers 18 feet deep and 
200 feet wide; (1) an inner basin 13 feet deep; (m) an anchorage 
area in the southwest corner of the inner basin 8 feet deep. The 
project was authorized by the River and Harbor Acts of 13 June 
1902, 3 July 1930, and 2 March 1945. See table 22-C. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Four docks are available. The commodities 
handled at this harbor are gypsum and building cement. 
Operations and results during period. 
Maintenance: Enviromental studies and monitoring activites 
were performed by hired labor at a cost of $72,116, by other 
COE at a cost of $3,200, by contract at a cost of $17,930, and 
by other Federal Agency at a cost of $9,549. A wave guage retrieval 
system was installed by other COE at a cost of $25,000. 
FY 1988 dredging contract was completed at a cost of $3,884. 
Engineering and design costs were $6,273. E&D costs associated 
with the construction of the Confined Disposal Facility were 
$3,865. Real estate costs were $7,310. Project management and 
contract administration for the above project were $16,972 and 
$7,741, respectively. 
Condition at end of fiscal year. The existing project is complete 
except for the 1970 modification which is inactive. Total 
costs of existing project to September 30, 1989 were $7,979,627, 
of which $823,026 was for new work and $7,156,601 was for 
maintenance. 
9. RECONNAISSANCE AND CONDITION 
SURVEYS 
Condition surveys and aerial photos were performed at a cost 
22-4

CHICAGO, IL, DISTRICT 
of $9,168. Water quality studies were performed by hired labor 
at a cost of $1,202. Project management was performed by hired 
labor at a cost of $114,193. 
10. NATIONAL EMERGENCY 
PREPAREDNESS 
Fiscal Year costs of $141,486 were for: 
Training and Exercises $ 7,157 
Management and Mobilization Planning $134,329 
Alteration of Bridges 
11. OTHER AUTHORIZED BRIDGE 
ALTERATION 
See table 22-D. 
Beach Erosion 
12. INDIANA DUNES NATIONAL LAKE 
SHORE BANK PROTECTION, 
BEVERLY SHORES, IN 
Location. Northwestern Indiana, on the southeast shore of Lake 
Michigan in Porter County, approximately 35 miles southeast of 
Chicago Harbor. (See NOAA Nautical Charts Numbers 14095 
and 14926.) 
Existing Projects. Provides for 13,000 feet of stone revetment 
and periodic repair of rip rap to maintain the full length of beach 
front at Beverly Shores, Indiana. The current project was authorized 
by Public Law 97-88 and Public law 98-63. 
Local Cooperation. Fully complied with. 
Operations and results during period. 
Project management cost associated with closing FY 1988 contract 
for emergency repairs of the existing revetment was $1,679. 
Condition at end of fiscal year. Total costs of existing project 
to September 30, 1989 were $1,086,585 of which $660,000 
is for new work and $426,585 is for maintenance. 
13. INDIANA SHORELINE, IN 
Location. On the south end of Lake Michigan along a twomile 
reach of shore west of Michigan City Harbor, Indiana. 
Existing Project. The project consists of beach nourishment 
of approximately two miles of beach between Michigan City Harbor 
and Beverly Shores, Indiana, requiring placement of 400,000 
cubic yards of sand. Periodic replenishment averaging about 
70,000 cubic yards of sand at five year intervals would be required 
throughout the life of the project. The project was authorized 
for construction by Section 501 of the Water Resources Development 
Act of 1986. Estimated Federal Cost (1987) for new 
work is $8,340,000. 
Local Cooperation. Sections 101 and 103 of the Water Resources 
Development Act of 1986 applies. In letter dated March 
27, 1984, the City of Michigan City stated its willingness to act 
as local sponsor in the event that a local sponsor may be required 
at a future date. 
Operations and results during period. 
New work: Advance Engineering and Design was continued 
at a cost of $49,092. 
Condition at the end of the fiscal year. Preconstruction planning 
and engineering was initiated in fiscal year 1984. Total cost 
of the existing project to September 30, 1989 is $222,000 for 
new work. 
14. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See table 22-E. 
15. BEACH EROSION CONTROL UNDER 
SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 103 of the 
River and Harbor Act of 1962, as amended. 
Project and Location 
North Chicago, IL 
Sunrise Park, Lake Bluff, IL 
Fiscal Year Costs 
to September 30, 1989 
$1,395 
$-7,184 
Flood Control 
16. CHICAGO RIVER, IL (NORTH 
BRANCH) 
Location. Northern Illinois, in Cook and Lake Counties. 
Existing Project. Provides for clearing the channel of the North 
Branch of the Chicago River, Illinois, of fallen trees, roots, and 
other debris and objects which contribute to the flooding, unsightliness, 
and pollution of the river. The project extends from 
Wolf Point in Chicago, Illinois, to its source just south of Rockland 
Road east of Libertyville, Illinois. The project was authorized 
by the River and Harbor Act of 31 December 1970 (Section 
116) and amended by the River and Harbor Act of 7 March 1974. 
Local Cooperation. The 1970 Act provided that local interests 
furnish without cost to the United States all lands, easements, 
rights-of-way, and disposal areas necessary for construction 
of the project; hold and save the United States free from 
damages due to construction; maintain and operate all works after 
completion without cost to the United States; and agree to bear 
all costs in excess of $200,000 for completing construction. Assurance 
of local cooperation for this act was approved on 31 July 
1972. The 1974 Act provided that the United States will maintain 
the channel free of trees, roots, debris and objects at a cost 
not to exceed $150,000 per year with non-Federal interests paying 
25 percent of the cost of maintenance. 
Operations and results during period. 
Maintenance: Engineering and design for FY 87 Debris Removal 
project was continued by hired labor at a cost of $12,420 
and by contract at a cost of $26,865. Contract administration costs 
were $1,042. 
Condtion at end of fical year. Total cost of existing project 
to September 30, 1989 was $2,331,075 of which $231,884 
was for new work ($191,884 regular funds and $40,000 contributed 
funds), and $2,099,191 was for maintenance ($1,617,702 
Federal funds and $481,489 contributed funds). 
22-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
17. LAKE MICHIGAN, 
EDGEWATER/ROGERS PARK 
COMMUNITIES, CHICAGO, IL 
Location. On the Illinois Shore of Lake Michigan in City of 
Chicago (Cook County) from Hollywood-Ardmore Beach to 
Chicago-Evanston border. 
Existing Project. The project includes construction of a series 
of rubble mound revetments at the following street ends: Granville, 
Rosemont, and North Shore Avenues (approximate total 
of 340 linear feet); offshore breakwaters, 100 feet long each, at 
Thorndale, Jarvis and Fargo Avenues; a 40 foot seawall extension 
at Glenlake Avenue; and placement of 450 linear feet of rubble 
mound revetment at Berger Park. Planned construction activities 
at Devon Avenue and Hartigan Park and Beach were deleted 
at the local sponsor's request and at Sherwin Avenue due 
to lack of economic justification as determined by the value engineering 
study. Beach nourishment placement at Rogers Park 
and Beach was deleted due to the local sponsor's disagreement 
with the Local Cooperation Agreement requirement which holds 
the local sponsor responsible for future project maintenance. The 
project was authorized by PL-99-190 Section 123 and amended 
by PL99-591. 
Local Cooperation. The local sponsor is required to provide 
all lands, easements and rights of way, provide all required relocations, 
hold and save the United States from any damages due 
to construction or operation of the project, and contribute a minimum 
of twenty-five percent of the total project costs. The local 
sponsorship for Phase I (the completed activities) was shared by 
the City of Chicago and the Chicago Park District. 
Operations and results during period. 
New Work: Construction contract for the first phase; which included 
breakwaters at Thorndale, Jarvis and Fargo Avenues, rubble 
mound revetments at Granville, Rosemont, and North Shore 
Avenues and the seawall extension at Glenlake Avenue was fiscally 
completed. During the year a total of $348 was expended 
for Phase I for project management. Administrative close-out of 
the construction contract for the rubble mound revetment at Berger 
Park was completed. Construction contract costs were $16,502 
($15,716 Federal and $786 Non-Federal). Operation and maintenance 
manual was completed for $8,658 ($7,114 Federal and 
$1,544 Non-Federal). Plans and specifications were completed 
for Phase II which includes beach nourishment at Rogers Park 
and Beach at a cost of $2,001 for hired labor and $2,069 for real 
estate management services. A summary of total Federal costs 
by locations is as follows: 
Fiscal Year Cost 
Project and Location September 30, 1989 
Phase I - Completed Construction 
Lake Michigan-Granville Ave., Chicago, IL $ 59 
Lake Michigan-Thorndale Ave., Chicago, IL 97 
Lake Michigan-Rosemont Ave., Chicago, IL 39 
Lake Michigan-North Shore Ave., Chicago, IL 94 
Lake Michigan-Fargo Ave., Chicago, IL 20 
Lake Michigan-Jarvis Ave., Chicago, IL 39 
Lake Michigan-Berger Park, Chicago, IL 22,830 
Phase II 
Lake Michigan, Edgewater/Rogers Park $ 4,071 
(Hartigan Park), Chicago, IL 
Condition at the end of the fiscal year. The existing project 
is 100 percent complete. Total costs of existing project to September 
30, 1989 were $2,062,347 for new work ($1,685,700 
Federal and $376,647 contributed funds). 
18. LITTLE CALUMET RIVER, IN 
Location. Little Calumet River is located in northwest Indiana 
between the Illinois-Indiana state line and the Conrail Railroad 
in east Gary, Indiana. 
Existing Project. The project consists of replacing 22 miles 
of levees between the Illinois-Indiana state line and Cline Avenue; 
construction of 12 miles of levees in Gary; a diversion structure 
at Hart Ditch; permanent evacuation of 29 structures in the 
Black Oak area of Gary; flood proofing 38 residential structures 
in Gary; modifying 7 miles of channel; modifying 4 highway 
bridges; construction of 17 miles of hiking trails and accompanying 
recreation support facilities, and preservation of 788 acres 
of wetlands with wildlife mitigation measures. Estimated Federal 
cost (1988) for new work is $50,700,000 and $17,300,000 
to be contributed by local intests. Project was authorized by Section 
401 of the Water Resources Development Act of 1986. 
Local Cooperation. Section 103 Water Resources Development 
Act of 1986 applies. By letter dated June 22, 1981, the Little 
Calumet River Basin Development Commission forwarded a 
resolution passed by the Commission affirming its understanding 
of the general items of local cooperation and indicating tentative 
willingness to act as local sponsor. By letter dated May 
2, 1986, the Commission expressed its willingness to meet the 
non-Federal project sponsor requirements. The Commission is 
aware of the PL99-662 cost-sharing requirements. The District 
Engineer believes that the Commission would have the ability to 
provide the local cooperation requirements for this project. 
Operations and results during period. 
New work: Advance engineering and design was continued at 
a cost of $329,053. 
Conditions at the end of the fiscal year. Preconstruction planning 
is in progress. Total costs of existing project to September 
30, 1989 were $2,004,000 for new work. 
19. McCOOK AND THORNTON 
RESERVIORS, IL 
Location. The McCook Reservoir will be located in within the 
communities of McCook and Hodgkins, Illinois, at the existing 
McCook Quarry. The Thornton Reservoir will be located in the 
community of Thornton, Illinois at the existing Thornton Quarry. 
Existing Project. The project consists of converting two quarries 
into flood storage reservoirs. The McCook reservoir will have 
a storage volume of 32,100 acre-feet (9.8 billion gallons), the 
Thornton reservoir will have a volume of 14,600 acre-feet (4.8 
billion gallons). The reservoirs will store floodwater from tunnels 
constructed or under construction by the U.S. Environmental 
Protection Agency and the Metropolitan Water Reclamation 
District of Greater Chicago as part of the Tunnel and Reservoir 
Project (TARP). Estimated project cost (1986) is $436,000,000 
including Federal cost for new work of $327,000,000 and 
$109,000,000 to be contributed by non-Federal interests. Project 
was authorized by Section 3 of the Water Resrouces Development 
Act of 1988. 
Local Cooperation. By letter dated 13 November 1986, the 
Metropolitan Water Reclamation District of Greater Chicago indicated 
that it would be the local sponsor and provide the re- 
22-6

CHICAGO, IL, DISTRICT 
quired local cooperation. 
Operations and results during period. 
New work: Continuation of planning and engineering was continued 
at a cost of $599,850. 
Condition at end of the fiscal year. Pre-construction planning 
is in progress. Total costs to the existing project to September 
30, 1989 were $654,615 for new work. 
20. NORTH BRANCH, 
CHICAGO RIVER, IL 
Location. The North Branch Chicago River Basin is located 
north of the City of Chicago in suburban Cook and Lake Counties. 
Existing Project. The project consists fo constructing two excavated 
floodwater storage reservoirs on the West Fork and one 
excavated reservoir on the Middle Fork. The Water Resources 
Development Act of 1986, Section 401, also includes authorization 
to reimburse non-Federal interests 50 percent of the costs 
of planning and construction for three existing reservoirs on the 
West Fork, known as Techny reservoirs, and the existing Mid 
Fork reservoir on the Middle Fork. Reservoir 27 in the Village 
of Brannockburn, the first reservoir to be constructed, will be 
built on the West Fork 12.7 miles above its confluence with the 
North Branch Chicago River. It will have a floodwater storage 
capacity of 525 acre-feet. Excavation for the reservoir will be 
approximately 48 feet deep. Approximately 700 feet of the West 
Fork channel will be improved and relocated for construction of 
the diversion structure. The second reservoir to be constructed, 
Reservoir 29A, will be built 9.6 miles above the mouth of the 
West Fork and 3.1 miles south of Reservoir 27. The reservoir 
flood water storage capacity is 575 acre-feet. Site 29A is located 
near the Village of Deerfield in unincorporated Cook County. 
Two project features, the channel relocation and construction of 
two bridges, will be accomplished by private or local governmental 
interests prior to construction of the reservoir at 29A. The 
last reservoir to be constructed, Reservoir 15, will be located 
near the City of Green Oaks on the Middle Fork, 22.1 miles above 
its confluence with the North Branch Chicago River. The design 
floodwater storage capacity is 500 acre-feet. The excavated reservoir 
will be approximately 42 feet deep except in the sedimentation 
pool area which will be about 15 feet deeper. Channel 
improvements and relocation of about 800 feet of the channel 
will be required for construction of the diversion structure at the 
north end of the reservoir. Estimated Federal cost (Oct. 1988) 
for new work is $18,400,000. An additional $9,600,000 will be 
contributed by local interests. Project was authorized by the Water 
Resources Development Act of 1986 (H. Doc. 100-72 100th 
Congress, 1st session). 
Local Cooperation. By letter dated August 2, 1983, the Director 
of the Illinois Division of Water Resources has indicated 
that the State of Illinois will provide the lands required for the 
project. The Director also stated that the Lake County Forest Preserve 
District and the Village of Deerfield will operate and maintain 
the reservoirs. The Director has stated in conversations with 
the Chicago District that the State will be willing to participate 
in the cost sharing plan required by Section 103 of the Water 
Resources Development Act of 1986. The local cooperation 
agreement for Reservoir 27 was executed on 27 April, 1988. 
Operations and results during period. 
New work: Construction of Reservoir 27 was continued at a cost 
of $3,093,121 ($2,922,869 Federal and $170,252 non-Federal). 
Engineering and design costs associated with Reservoir 27 were 
$113,810 ($104,490 Federal and $9,320 non-Federal) and construction 
managment costs were $233,948 hired labor ($228,403 
Federal and $5,546 non-Federal), and $1,304 Federal costs for 
soil testing. Plans and specifications for Reservoir 29A were completed 
at cost of $615,264. Plans and specifications for Reservoir 
15 were initiated at a cost of $168,828. Audit of the costs 
for Techny and Mid Fork Reservoirs and pumping stations were 
completed. Audit costs by other COE were $21,028 and project 
management costs were $31,851. 
Condition at the end of the fiscal year. The existing project 
is 56 percent complete. Construction of Reservoir 27 was initiated 
in August 1988. Total costs of the existing project to September 
30, 1989 were $6,362,462 for new work of which 
$6,177,344 was Federal funds and $185,118 non-Federal Funds. 
21. O'HARE RESERVOIR, IL 
Location. The reservoir will be located in an unincorporated 
portion of Elk Grove Township in northwestern Cook County, 
Illinois about 1 mile northwest of Chicago O'Hare International 
Airport. 
Existing Project. The project consists of a 1,050 acre-foot capacity 
reservoir, excavated to a depth of 80 feet. The reservoir 
would be constructed at the terminus of the existing system of 
6.6 miles of deep tunnels, recently constructed under the U.S. 
Environmental Protection Agency and the Metropolitan Water 
Reclamation District of Greater Chicago Tunnel and Reservoir 
Project (TARP). Estimated project cost (Oct. 1988) is 
$18,500,000 including Federal cost for new work of $13,500,000 
and $5,000,000 to be contributed by local interests. Project was 
authorized by Section 401 of the Water Resources Development 
Act of 1986. 
Local Cooperation. Sec. 103 of the Water Resources Development 
Act of 1986 applies. By letter dated 12 April 1984, the 
Metropolitan Water Reclamation District of Greater Chicago stated 
it would be the local project sponsor and provide the required 
local cooperation. 
Operations and results during period. 
New work: Advance Engineering and Design was continued at 
a cost of $545,928. 
Condition at the end of the fiscal year. Preconstruction planning 
is in progress. Total costs to the existing project to September 
30, 1989 were $1,078,000 for new work. 
22. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 22-F. 
23. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting and 
rescue work (Public Law 99, 84th Cong. and antecedent legislation). 
Program 
Disaster Preparedness 
Emergency Operations 
Advance Measures 
Fiscal Year Costs 
to September 30, 1989 
$136,675 
34,413 
565,474 
22-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Emergency Water Supplies/Drought 46,191 
Emergency bank protection (Sec. 14 of the 1946 Flood Control 
Act Public Law 526. 79th Congress). 
Fiscal Year Costs 
Project and Location to September 30, 1989 
Batavia, IL $ 16,247 
Dune Acres, IN 98,311 
Duneland Beach, LaPorte Co., IN 215,735 
Lake Michigan, Temple Emanuel, IL 216,740 
Meigs Field, IL 2,500 
Flood control activities pursuant to Section 205 of Flood Control 
Act of 1845, as amended. 
Project and Location 
Fox River, McHenry County, IL 
Northfield, IL 
Libertyville Estates, IL 
Wilmington, IL 
McCook Levee, IL 
Monticello Ave., IL 
Fiscal Year Costs 
to September 30, 1989 
$ 6,000 
17,385 
6,563 
10,050 
7,716 
4,887 
General Investigations 
24. SURVEYS 
Fiscal year costs were $731,967 itemized as follows: 
Navigation Studies $ 0 
Flood Damage Prevention Studies 375,960 
Shoreline Protection Studies 268,223 
Special Studies 12,784 
Special Investigations 45,000 
Coordination Studies 19,000 
Supplemental Pre-authorization 0 
25. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs of $157,000 were for: 
Flood Plain Management Services 
Hydrologic Studies 
26. CONTINUATION OF PLANNING 
AND ENGINEERING 
Costs during the period were $599,850. Costs were incurred 
on the McCook and Thornton Reservoir projects. See section 19 
for details. 
27. ADVANCE ENGINEERING 
AND DESIGN 
Costs during the period were $924,073. For details see sections 
13, 18, and 21. 
Miscellaneous 
28. LAKE GEORGE, HOBART, IN 
Location. Lake George in Hobart, Indiana and the Deep River 
watershed upstream of the lake through Lake Station, Indiana. 
Existing Project. The project consists of the removal of approximately 
900,000 cubic yards of silt, aquatic growth and other 
material and the construction of silt traps or other devices to prevent 
and abate the deposition of sediment. Estimated cost (1988) 
for new work is $3,750,000 Federal and $1,250,000 is to be contributed 
by local interests. Project was authorized by Section 602 
of the Water Resources Development Act of 1986. 
Local Cooperation. Section 602(b), Water Resources Development 
Act of 1986 applies. 
Operations and results during period. 
None. 
Condition at the end of the fiscal year. No work has been 
initiated. 
$157,000 
$ 0
22-8

CHICAGO, IL, DISTRICT 
TABLE 22-A COST AND FINANCIAL STATEMENT 
See Total To 
Section September 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 30, 1989 
1. Burns Waterway New Work: 
Harbor, IN 
(Federal Funds) 
(Contributed 
Funds) 
2. Burns Waterway 
Small Boat 
Harbor, IN 
(Federal Funds) 
Contributed 
Funds) 
3. Calumet Harbor 
and River, IL 
and IN 
(Federal Funds) 
(Contributed 
Funds) 
4. Chicago Harbor, 
IL 
(Federal Funds) 
5. Chicago River, IL 
Indiana Harbor, 
6. IN 
(Contributed 
Funds) 
7. Michigan City 
Harbor, IN 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib.. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
150,000 
169,592 
80,000 
58,181 
13,584,000 
13,584,000 
350,000 1,041,000 5,425,793 
190,357 1,172,824 5,376,053 
15,900 
15,900 
270,000 
107,727 
135,000 
603,227 
985,000 
1,399,456 
1,507,000 
1,488,154 
970,000 
941,516 
-0- 
239,573 
30,000 
2,101 
89,172 
251,805 
368,500 
337,350 
350,000 
237,488 
13,000 
18,633 
20,000 
30,700 
3,886 
-0- 
1,305,000 
244,567 
2,204,000 
748,562 
185,000 
173.282 
446,500 
1,458,542 
2,185,000 
3,612,977 
2,000,000 
1,999,921 
235,000 
206,083 
1,770,558 
1,766,672 
22,578,5671 
22,578,5671 
25,985,7742 
25,867,5312 
5,428,0013 
5,288,0283 
836,667 
836,667 
4,788,8274 
4,788,8274 
905,000 1,260,000 1,327,000 13,772,286 
957,037 1,053,456 1,333,944 13,529,664 
1,326,600 
1,326,600 
1,500,5655 
1,500,5655 
738,000 
694,096 
946,000 1,076,000 11,395,7376 
694,064 1,347,097 11,279,5606 
4,897,1487 
4,897,1487 
12,500 
12,500 
981,000 
1,224,393 
395,000 
293,094 
380,000 
372,199 
611,000 9,655,7788 
745,455 9,625,4508 
43,6469 
1,543,6469 
25,000 1,292,000 
22,484 1,115,432 
124,000 
279,174 
270,000 6,351,512 
275,935 6,333,537 
1,618,670 
1,618,670 
22-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 22-A (Cont'd) COST AND FINANCIAL STATEMENT 
See Total To 
Section September 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 30, 1989 
(Contributed 
Funds) 
8. Waukegan 
Harbor, IL 
12. Indiana Dunes 
Nat'l. Lakeshore 
Beverly Shores, 
IN 
13. Indiana Shore- 
Line, IN 
16. Chicago River, IL 
(North Branch) 
(Federal Funds) 
(Contributed 
Funds) 
17. Lake Michigan- 
Edgewater/ 
Rogers Park 
Communities, 
Chicago, IL 
(Federal Funds) 
(Contributed 
Funds) 
18. Little Calumet 
River, IN 
19. McCook and 
Thornton 
Reservoirs, 
(CUP) IL 
20. North Branch 
Chicago River, IL 
(Federal Funds) 
(Contributed 
Funds) 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
30,800 
30,800 
823,02610 
823,02610 
380,000 
753,002 
-0- 
-0- 
-0- 
-0- 
-0- 
9,999 
66,000 
137,171 
96,898 
26,458 
121,000 
113,972 
360,000 
466,267 
-0- 
-0- 
-0- 
379,000 
390,216 
300,000 
158,224 
-0- 
-0- 
467,500 
395,208 
-0- 
-1,016 
20,000 
31,687 
-0- 
-0- 
1,621,200 
1,506,101 
380,000 
364,739 
288,000 
243,404 
-0- 
-0- 
315,000 
309,626 
956,000 
1,066,704 
-0- 
-0- 
-30,000 
29,698 
108,000 
74,925 
285,000 
239,476 
8,400 
80,925 
-0- 
38,379 
-0- 
9,578 
350,000 
396,662 
201,000 7,224,980" 
173,840 7,156,601" 
-0- 
-0- 
-10,000 
1,679 
15,000 
49,092 
660,000 
660,000 
427,500 
426,585 
230,000 
230,000 
33,000 1,681,000 
40,327 1,617,702 
-0- 
11,575 
40,000 
40,000 
-56,500 1,685,700 
27,248 1,685,700 
-0- 
2,330 
380,000 
376,647 
337,000 2,012,000 
329,053 2,004,000 
150,000 1,107,000 1,257,000 
54,765 599,850 654,615 
3,800,000 
907,753 
255,000 
-0- 
1,476,500 
4,094,037 
183,000 
185,118 
6,460,000 
6,177,344 
438,000 
185,188 
22-10

CHICAGO, IL, DISTRICT 
TABLE 22-A (Cont'd) COST AND FINANCIAL STATEMENT 
See Total To 
Section September 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 30, 1989 
21. O'Hare Reservoir, New Work: 
Chicago, IL Approp. 85,000 500,000 493,000 1,078,000 
Cost 39,587 492,485 545,928 1,078,000 
1. Includes $855,973 for previous projects. 
2. Exludes contributed funds in settlement pursuant 
to decree (No. 54-C-1608) regarding removal of flue dust 
and includes $45,230 for previous projects. 
3. Includes $689,001 in settlement pursuant to decree 
regarding removal of flue-dust. 
4. Includes $446,005 for previous projects. 
5. Includes $955,886 for previous projects. 
6. Includes $109,463 for previous projects. 
7. Includes $60,668 for previous projects. 
8. Includes $2,509 for previous projects. 
9. Excludes $287,389 for previous projects. 
10. Excludes $218,233 on previous projects. 
11. Includes $15,711 on previous projects. 
22-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 22-B AUTHORIZING LEGISLATION 
Acts 
Oct. 27, 1965 
Mar. 3, 1899 
June 13, 1902 
Mar. 3, 1905 
June 25, 1910 
Sept. 22, 1922 
Aug. 30, 19351 2 
Aug. 30, 1935' 2 
Mar. 2, 19453 
July 14, 1960 
Oct. 23, 1962 
Oct. 27, 1965 
July 11, 1870 
June 14, 1880 
Mar. 3, 1899 
July 25, 1912 
Mar. 2, 1919 
Mar. 3, 1931 
Mar. 2, 1945 
Oct. 23, 1962 
Dec. 4, 1981 
July 30, 1983 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 1919 
July 24, 1946 
Work Authorized 
BURNS WATERWAY HARBOR, IN 
(See Section 1 of Text) 
Provides for breakwater and channel to present dimensions and depths; 
North Breakwater, West Bulkhead, Approach Channel and Outer Harbor, 
East and West Harbor Arms. 
CALUMET HARBOR AND RIVER, IL AND IN 
(See Section 3 of Text) 
Outer Harbor protected by breakwaters. 
Five turning basins. 
Provided for shape and dimensions of turning basins. 
Consolidated the 2 projects for Calumet Harbor and Calumet River. 
Detached breakwater, dredging outer harbor to existing project depth and 
dimensions; deepen river-entrance channel and river to existing project 
depths; widen and straighten river channel; 5 turning basins to same depth 
as adjacent channel. 
Dredging area A and B in south end of Lake Calumet and an entrance 
channel 300 feet wide and 21 feet deep. 
An approach channel to harbor 3,200 feet wide and 28 feet deep through 
shoals outside breakwater and closing existing gap between breakwaters. 
Depth of 29 feet in lake approach to 28 feet in outer harbor, and 27 feet in 
river entrance up to E.J. & E. Ry. Bridge. 
Deepen, widen, and straighten channel in Calumet River from E.J. and E. 
Ry. Bridge, to and including turning basin 5, to a depth of 27 feet in 
earth and 28 feet in rock; deepen turning basins 1, 3 and 5 to 27 feet; enlarge 
turning basins 3 and 5; a channel into Lake Calumet to 27 feet deep 
for 3,000 feet and a width of 1,000 feet; and eliminate turning basins 2 
and 4 from project. 
Modification of Act of Oct. 23, 1962. Protection for Elgin, Joliet and Eastern 
Railway Bridge over the Calumet River, to permit dredging to full 
width of the south draw to depth of 27 feet, and temporary protection for 
center pier and south abutment of the New York, Chicago, and St. Louis 
Railroad Bridge (Nickle Plate) to permit dredging of full width of south 
bridge draw to depth of 27 feet prior to its replacement. 
CHICAGO HARBOR, IL 
(See Section 4 of Text) 
Inner breakwaters and inner basin. 
Exterior Breakwater. 
Present project depth in basin, and entrance to Chicago River. 
Shore-arm and southerly extension of exterior breakwater. 
Modification of area to be dredged in inner basin. 
Shore-arm extension of exterior breakwater transferred to Lincoln Park 
Commissioners. 
Resumption of jurisdiction over shore-arm extension breakwater and over 
certain navigable waters in Lake Michigan which lie in northwestern part 
of outer harbor. 
Deepen a lake approach channel to 29 by 800 feet wide for 6,600 feet; and 
deepen a channel and maneuver area inside harbor entrance to 28 by 
1,300 feet wide. 
Provides for lock operations and maintenance responsibilities in the interests 
of navigation. 
CHICAGO RIVER, IL 
(See Section 5 of Text) 
For project depth of 21 feet in lieu of that fixed by act of June 3, 1896. 
Turning basins. 
Interpreted by Chief of Engineers, April 11, 1908 as adopting new work of 
the then existing project for 21-foot depth. 
Eliminated all work except maintenance of main river. 
Dredging channel 9 feet deep to within 30 feet of existing bulkheads and 
river banks from North Ave. to Belmont Ave., thence 9 feet deep and 50 
feet wide to Addison St. 
Documents 
Public Law, 89-298, H. Doc. 160, 
88th Cong., 1st sess. 
Annual Report, 1896, pp. 2584 et 
Seq. and H. Doc. 277, H. 
54th Cong., 1st sess. 
H. Doc. 172, 54th Cong., 2d sess. 
H. Doc. 349, 60th Cong., 1st sess. 
H. Doc. 494, 72d Cong., 2nd sess. 
H. Doc. 180, 73rd Cong., 2d sess. 
H. Doc. 233, 76th Cong., 1st sess. 
H. Doc. 149, 86th Cong., 1st sess. 
H. Doc. 581, 87th Cong., 2d sess. 
H. Report No. 973, 89th Cong., 
1st sess. 
H. Ex. Doc. 114, 41st Cong., 2d 
sess., and Annual Report 1879, pp. 
1562-1567 
Annual Report, 1870, pp. 1562-1567 
Annual Report 1897, pp. 2790-2791 
H. Doec. 710, Cong., 2d sess. 
H. Doc. 1303, 64th Cong., 1st sess. 
Public Law 797, 71st Cong. 
Public Law 14, 79th Cong. 
H. Doc. 485, 87th Cong., 2d sess. 
Section 107 of Public Law 97-88 
Public Law 98-63 
Specified in act. 
Specified in act. 
H. Doe. 95, 56th Cong., 1st sess. 
(Annual Report, 1900, p. 3863 and 
Annual Report, 1909, p. 709). 
H. Doe. 1294, 64th Cong., 1st sess. 
H. Doc. 767, 78th Cong., 2d sess.6 7 
22-12

CHICAGO, IL, DISTRICT 
TABLE 22-B (Cont'd) AUTHORIZING LEGISLATION 
Acts 
Nov. 17, 1986 
June 25, 1910 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 20, 1922 
Mar. 3, 1925 
Mar. 2, 1929 
July 3, 193010 
July 30, 1932 
Aug. 30, 193511 
Aug. 28, 1937 
July 14, 1960 
Oct. 27, 196512 
Mar. 3, 1889 
Mar. 3, 1905 
Jan. 21, 1927 
Aug. 30, 1935 
Sept. 30, 1966 
Sec. 107 
June 14, 1880 
Aug. 3, 1882 
June 13, 1902 
July 3, 1930 
Mar. 2, 1945 
22-13 
Work Authorized 
Responsible for monitoring of Lake Michigan Diversion 
INDIANA HARBOR, IN 
(See Section 6 of Text) 
Maintenance of outer harbor. Maintenance of inner harbor channel when 
deeded free of cost to and accepted by the United States. 
Breakwaters. 
Lighthouse crib, present length and alignment easterly and northerly 
breakwaters. 
Reduce length of channel to be maintained in extension to Lake George. 
Authorized Secretary of War to modify project so far as relates to length 
and alignment of breakwaters and to sell Youngstown Sheet and Tube Co. 
about 1,180 linear feet of shoreward end of existing north breakwater. 
Accept 2.3 acres of land for construction of the Forks Turning Basin. 
Existing project channel width and depth in Lake George Branch and 
turning basin at the Forks. 
Authorized Secretary of War to sell Inland Steel Co., about 1,903 linear feet 
of southerly end of existing east breakwater. 
Extended easterly breakwater, dredge entrance channel and outer harbor, 
deepen channel between bulkhead fills, widen main stem of canal and 
portion of Calumet River Branch to 141st St. 
Modified conditions of local cooperation required before enlargement of 
Indiana Harbor Canal is undertaken by United States. 
Increase authorized depths of 29 feet in outer harbor entrance channel; 28 
feet in outer harbor, and 27 feet in canal entrance channel to first E.J. & 
E. Ry. Bridge. 
Deepen main canal from landward end of canal entrance channel to a point 
lakeward of Dickey Place Bridge over a modified channel width of 190 
feet, except through bridge openings. 
MICHIGAN CITY HARBOR, IN 
(See Section 7 of Text) 
East breakwater and old east pier inclosing the outer basin. 
Extension of east pier. 
Extend east pier and construct detached breakwater. 
Lower turning basin. 
Rebuild west pier as at present located. 
Present project dimensions of entrance channel. 
Existing project depth in channel, and in lower and middle turning basins, 
eliminated improvement of Trail Creek above middle turning basin and 
uncompleted portion of detached breakwater, abandonment of old east 
breakwater and old east pier inclosing outer basin. 
Restore and repair westerly 1,000 feet of east breakwater, dredging outer 
basin, and enlarging entrance to basin through east pier. 
Dredge river channel 50 feet wide and 6 feet deep from upper turning basin 
to E Street bridge. 
WAUKEGAN HARBOR, IL 
(See Section 8 of Text) 
Parallel piers and basins. 9 
Modified location of harbor entrance. 
Detached breakwater, extend piers, increase width of harbor at inner end of 
north pier, and dredge channel and basin to depth of 20 feet. 
Extension of breakwater to shore, dredging near outer end of north piers 
and enlarging inner basin. 
Dredge an entrance channel to existing project dimensions from outer end of 
north pier to project depth in lake, and dredge an anchorage area in 
southwest corner of inner basin to existing project depth. Abandonment of 
dredging triangular area in southwest corner of inner basin to 18 feet 
deep. 
Documents 
Section 1142, Water Resources 
Development Act of 1986 
H. Doc. 1113, 60th Cong., 2d sess. 
H. Doc. 690, 62d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 6, 65th Cong., 2d sess. 
Public Law 176, 67th Cong. 
Rivers and Harbors Committee 
Doc. 21, 71st Cong., 2d sess. 
Public Law 219, 72d Cong. 
Rivers and Harbors Committee 
Doc. 29, 72d Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 13, 75th Cong., 1st sess. 
H. Doc. 195, 86th Cong., 1st sess. 
H. Doc. 227, 89th Cong., 1st sess. 
Recommendations of a Board of Engineers, 
Annual Report 1870, p. 
123 
Reports of Boards of Engineers, 
Annual Report 1851, pp. 
2187-2189; Annual Report 1882, 
p. 2264-2266. 
Annual Report 1897, pp. 2903-2904. 
Joint Resolution of Congress approved 
May 13, 1908. 
Public Law 23. 
H. Doc. 279, 69th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 34, 74th Cong., 1st sess. 
Detailed Project Report June 19658 
Annual Report, 1880, p. 142 
Annual Report, 1882, pp. 277, 2162 
H. Doc. 343, 56th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 27, 71st Cong., 2d sess. 
H. Doc. 116, 77th Cong., 1st sess.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 22-B (Cont'd) AUTHORIZING LEGISLATION 
Acts 
Dec. 17, 1970 
Sec. 201 
Oct. 27, 1965 
Dec. 4, 1981 
July 30, 1983 
Nov. 17, 1986 
Dec. 15, 1985 
Nov. 17, 1986 
Nov. 17, 1986 
Dec. 31, 1970 
Nov. 17, 1986 
Nov. 17, 1986 
Nov. 17, 1988 
Work Authorized 
Provides for deepening the existing entrance channel in the outer harbor to 
25 feet and extending it to the depth in Lake Michigan, at widths varying 
from 380 feet to 500 feet; deepening the channel between piers to a depth 
of 23 feet at a width of 180 feet, and deepening the inner basin to 23 feet 
and extending its limits approximately 275 feet northward. 
INDIANA DUNES NATIONAL LAKESHORE, IN 
BEVERLY SHORES, IN 
(See Section 12 of Text) 
Provides for emergency shore protection repairs to stone revetment initially 
constructed in 1973. 
Provides for operations and maintenance of the shore protection measures. 
INDIANA SHORELINE, IN 
(See Section 13 of Text) 
Provides for beach nourishment along a two-mile reach of shore west of 
Michigan City Harbor, Indiana. 
LAKE MICHIGAN-EDGEWATER/ROGERS PARK 
COMMUNITIES, CHICAGO, IL 
(See Section 17 of Text) 
Provides for emergency bank stabilization, shore protection and flood 
control work. 
LITTLE CALUMET RIVER, IN 
(See Section 18 of Text) 
Provides for levee construction, a diversion control structure at the mouth of 
Hart Ditch, permanent evacuation of a portion of the Black Oak area of 
Gary and non-structural flood proofing measures in Gary. 
NORTH BRANCH CHICAGO RIVER, IL 
(See Sections 16 and 20 of Text) 
Construction of three reservoirs and reimbursement to locals for 50 percent 
of the costs for Techny and Mid-Fork reservoirs. 
Clearing fallen trees, roots and other debris and objects which contribute to 
flooding. 
O'HARE RESERVOIR, CHICAGO, IL 
(See Section 21 of Text) 
Provides for a 1,050 acre-foot excavated reservior. 
LAKE GEORGE, HOBART, IN 
(See Section 28 of Text) 
Provides for removal of silt, aquatic growth and construction of silt traps. 
McCOOK AND THORNTON RESERVOIR 
(See Section 19 of Text) 
Provides for construction of two floodwater storage reservoirs in the 
quarries of the same name. 
Documents 
H. Doc. 368, 90th Cong., 2d sess. 
Public Law 97-88 
Public Law 98-63 
Sec. 501, Water Resources 
Development Act of 1986. 
Public Law 99-190 amended 
Sec. 401, Water Resources 
Development Act of 1986. 
H. Doc. 100-72, 100th Cong. 
1st sess., Sec. 401, Water Resources 
Development Act of 1986 
River and Harbor Act. (Sec. 116) 
Sec. 401, Water Resources 
Development Act of 1986. 
Sec. 602, Water Resources 
Development Act of 1986. 
Sec. 3, Water Resources Development 
Act of 1988. 
1. Included in Public Works Administrative Program September 
6, 1943, and Dec. 16, 1933. 
2. Uncompleted portion was deauthorized in 1977 (dredging 
in front of U.S. Steel Corp.). 
3. Uncompleted portion was deauthorized in 1977 (breakwater 
closure). 
4. Contains latest map of harbor. Uncompleted portion is 
inactive. 
5. Contains latest map of river. 
6. Latest published map is an Annual Report for 1914, opposite 
p. 2928. 
7. Contains latest published map of North Branch above 
North Ave. 
8. Contains latest published map. 
9. Completed under previous project. 
10. Uncompleted portion was deauthorized in 1977 (widen and 
deepen Lake George Branch). 
11. Included in Public Works Administration Program Sept. 6, 
1933, and July 25, 1934. Uncompleted portion was deauthorized in 
1977 (widen and deepen main canal and Calumet River Branch). 
12. Project deauthorized in 1977. 
22-14

CHICAGO, II, DISTRICT 
TABLE 22-C EXISTING PROJECTS 
See 
Section Length Width Depth 
in Text Project Item (feet) (feet) (feet) 
i. Burns Waterway 
Harbor, IN 
2. Burns Waterway 
SBH, IN 
3. Calumet Harbor 
and River, IL 
and IN 
4. Chicago Harbor, 
IL 
5. Chicago River, 
IL 
6. Indiana Harbor, 
IN 
7. Michigan City 
Harbor, IN 
8. Waukegan Harbor, 
IL 
North Breakwater 
Outer West Bulkhead 
Approach Channel 
Outer Harbor 
East Harbor Arm 
West Harbor Arm 
North Breakwater 
West Breakwater 
Approach Channel 
Burns Ditch 
Northerly Crib Breakwater 
Southerly Steel Breakwater 
North Pier 
Chicago Confined Disposal Facility 
Approach Channel 
Outer Harbor 
River Entrance 
Elgin, Joliet & Eastern Railway Bridge 
to turning basin No. 3 
Turning Basin No. 3 to Turning Basin No. 5 
Approach into Lake Calumet 
Extension in Lake Calumet 
Turning Basins 1,3,and 5 
Shore arm extension 
Exterior breakwater 
Exterior breakwater southerly ext. 
North inner breakwater 
South inner breakwater 
North Pier 
Approach Channel 
Channel and maneuver 
Lock 
Inner Basin 
Entrance Channel 
Main branch of Chicago River 
North Branch of Chicago River 
North Branch Canal 
North Branch Turning Basin 
Northerly Breakwater 
Easterly Breakwater 
Approach Channel 
Outer Harbor 
Entrance Channel 
Main Channel 
Turning Basin 
Lake George Branch 
Calumet River Branch 
Detached Breakwater 
West Pier 
East Pier 
East Breakwater 
Entrance Channel 
Main Channel 
Outer Basin 
Trail Creek 
Trail Creek 
North Breakwater and Shore Connection 
North Pier and North Revetment 
South Pier 
Entrance Channel 
Channel to Inner Basin 
Inner Basin 
Anchorage Area 
'Area of about 6 acres. 
22-15 
5 Ran 
3,600 
2,200 
3,700 
2,100 
3,800 
678 
1,043 
1,200 
5,593 
6,714 
5,007 
2,450 
2,979 
9,700 
10,500 
3,000 
21,100 
8,000 
4,000 
3,000 
2,250 
5,421 
4,944 
4,034 
2,544 
960 
6,600 
2,200 
600 
1,270 
7,300 
3,800 
11,100 
5,500 
1,120 
2,525 
7,200 
4,200 
3,600 
7,400 
3,700 
2,500 
1,304 
835 
2,276 
1,000 
1,900 
2,400 
900 
3,000 
2,300 
1,896 
2,074 
3,111 
3,250 
1,700 
1,650 
_1 
400 
Varies 
620 
620 
200 
100 
3,200 
2,000 
290 
200 
and variable 
Variable 
400 
1,000 
800 
1,300 
80 
740 
190-470 
190-390 
91-390 
56-210 
800 
Varies 
65-280 
61-210 
64-160 
160-260 
150-425 
120-150 
900 
50-100 
50 
390 
200 
375-500 
801 
30 
28 
27 
27 
11
9 
29 
28 
27 
27 
earth
28 
rock
27 
27 
27 
27 
29 
28 
23 
21 
21 
21 
21 
21 
21 
29 
28 
27 
22 
22 
22 
22 
18 
18 
8-12
8
6 
22 
18 
18
8

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 22-D OTHER AUTHORIZED BRIDGE ALTERATION 
(See Section 11 of Text) 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Calumet River Bridges 1967 1,625,068 - 
1Transferred to Department of Transportation in accordance with Section 6(g) of the Act of October 16, 1966, P.L. 89-670. 
TABLE 22-E OTHER AUTHORIZED BEACH EROSION PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Casino Beach, Chicago, IL 1987 - 
Mt. Baldy, Indiana Dunes National 
Lakeshore, IN 1984 $1,500,000 
Hollywood-Ardmore Beach, Chicago, IL 1982 237,271 
Evanston, IL 1979 766,052 - 
Lake Michigan-Lake Bluff, IL 1976 244,889 - 
Lake Michigan-Lake Forest, IL' 1975 65,611 
1Authorized by River and Harbor Act of 1954. 
TABLE 22-F OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Little Calumet River, IL 1984 583,000 
Little Calumet River Basin 
(Cady Marsh Ditch), IN 1987 - 
TABLE 22-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
KANKAKEE RIVER, IL AND IN 
Levee between Shelby Bridge and 
Baum's Bridge in IN 1938 Nov. 17, 1986 - 
LITTLE CALUMET RIVER, IL AND IN 
Little Calumet River and Tributaries, 
IL and IN 1968 Nov. 17. 1986 53,136 - 
22-16

ROCK ISLAND, IL, DISTRICT* 
This district comprises most of the northern half of 
Illinois, portions of southern Wisconsin, southern and 
southwestern Minnesota, eastern and central Iowa, and 
northeastern Missouri, embraced in drainage basin of 
Mississippi River and its eastern and western tributaries 
between mile 330 (above mouth of Ohio River) and 614, and 
of its eastern tributaries only, between Hamburg Bay, at 
mile 261 and 300. This district also includes the Illinois 
Waterway above mile 80 with its tributaries and drainage 
basins. The section of the Mississippi River between river 
miles 300 and 614 is included in the report on Mississippi 
River between Missouri River and Minneapolis, MN. 
IMPROVEMENTS 
Navigation Page 
1. Illinois and Mississippi Canal, IL............... 23-2 
2. Illinois Waterway, IL and IN.................. 23-2 
3. Mississippi River between Missouri River 
and Minneapolis, MN........................ 23-3 
4. Upper Mississippi River System Environmental 
Management Program, IL, IA, MN, Mo, WI.....23-3 
5. Other Authorized Navigation Projects.......... 23-3 
Flood Control 
6. Coralville Lake, IA.......................... 23-4 
7. Des Moines Recreational River and 
Greenbelt, IA ............................... 23-4 
8. Farm Creek, IL ........................... 23-4 
9. Hannibal, M O .............................. 23-4 
10. Red Rock Dam and Lake Red Rock, IA......... 23-5 
11. Rockford, IL. ............................. 23-5 
12. Saylorville Lake, IA.......................... 23-5 
13. South Quincy Drainage and Levee District, IL .... 23-6 
14. Inspection of Completed Flood 
Control Projects ...... ...................... 23-6 
15. Other Authorized Flood Control Projects. ....... 23-6 
16. Flood Control Work Under Special 
Authorization ............................... 23-6 
General Investigations 
17. Surveys .................................... 23-6 
18. Collection and Study of Basic Data............. 23-6 
19. Advance Engineering and Design ............... 23-6 
Tables Page 
Table 23-A Cost and Financial Statement.......... 23-7 
Table 23-B Authorizing Legislation.............. 23-9 
Table 23-C Other Authorized Navigation 
Projects .......................... 23-12 
Table 23-D Not Applicable 
Table 23-E Other Authorized Flood 
Control Projects................... 23-12 
Table 23-F Not Applicable 
Table 23-G Deauthorized Projects. .............. 23-14 
Table 23-H Inspection of Completed Flood 
Control Projects................... 23-15 
Table 23-I Flood Control Work Under Special 
Authorization ...................... 23-16 
Table 23-J Illinois Waterway: Existing 
Locks and Dams................... 23-18 
Table 23-K Illinois Waterway: Lock and Dam 
Construction, Foundations, Cost ..... 23-18 
Table 23-L Illinois Waterway: Additional 
Features Entering into Cost .......... 23-19 
Table 23-M Illinois Waterway: Existing Project.... 23-20 
Table 23-N Illinois Waterway: Total Cost of 
Existing Project.................... 23-21 
23-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. ILLINOIS AND MISSISSIPPI 
CANAL, IL 
Location. This canal extends for 75 miles from the 
Illinois River near LaSalle, IL, to the Mississippi River at 
Rock Island, IL. A feeder canal, 29 miles in length, extends 
from the summit level of the canal to the Rock River at 
Rock Falls, IL. 
Existing project. See pages 1306-1308 of Annual Report 
for 1962 for details regarding project. The canal was constructed 
in the period 1892-1918. The canal has not been 
operated for navigation since June 1951 in accordance with 
Corps policy to discontinue operation of waterways affording 
little or no benefit to navigation. The River and Harbor 
Act of 1958 authorized the appropriation of $2,000,000 for 
the purpose of placing the canal in proper condition for 
public recreational use and to convey and transfer the canal 
to the State of Illinois as part of the State park system. 
The repair and modification program was initiated in 
1961, and a number of canal features have been repaired or 
modified. In connection with this program, fee title to 1,062 
acres and recreational flowage easements over 309 acres of 
land in Rock River at Rock Falls, formerly under navigation 
flowage easement, have been acquired. The State of Illinois 
accepted title to the canal as of August 1, 1970. The River 
and Harbor Act of 1970 authorized the additional appropriation 
of $6,528,000 to be expended for the repair, 
modification, and maintenance of bridges, title transfer, 
modification or rehabilitation of hydraulic structures, fencing, 
clearing auxiliary ditches, and for the repair and 
modification of other canal property appurtenances. 
The repair and modification work was underway until a 
suit was filed by three Illinois counties and their Commissioners 
of Highway against the Federal Government and the 
State in 1974 over maintenance of highway bridges crossing 
the canal. After the lawsuit was filed, further rehabilitation 
work by the Federal Government on the canal was suspended.
On 4 November 1981, the Corp of Engineers deposited 
$3,722,572 with the Clerk of the U.S. District Court in 
Chicago in full satisfaction of the Court's judgment. These 
funds are currently being used by the counties to complete 
bridge rehabilitation work as directed in the court order. 
Rehabilitation work by the Federal Government in coordination 
with the state was resumed in 1984 with the remaining 
authorization expended in 1987. 
The Water Resources Development Act of 1986 authorized 
an additional appropriation of $8,472,000 to accomplish 
the work described in the 1970 River and Harbor Act. 
The State of Illinois filed a lawsuit against the United 
States on July 6, 1987 in the U.S. Claims Court in the 
amount of $8,472,572. The suit consisted of two parts: (1) a 
claim for reimbursement of previously expended State funds 
for bridge repair and (2) that the federal funds ($3,722,572) 
used by the Government to satisfy the judgment in the Commission 
of Highway vs. United States be restored to the remaining 
authorization. Litigation of this suit will continue 
in FY90. 
Local cooperation. A revised agreement listing Federal 
remaining work items and the State desired priority of remaining 
work items is being developed in FY90. 
Operations during fiscal year. Engineering and Design 
work: (1) Performed hydraulic assessment of east end of 
canal, (2) Developed list of remaining federal work items; 
(3) Developed draft of revised agreement; and Initiated environmental 
coordination for remaining federal work at a 
cost of $105,286 during FY 1989. 
2. ILLINOIS WATERWAY, IL AND IN 
Location. Illinois River (entirely within State of 
Illinois), formed by confluence of Kankakee and Des 
Plaines River, flows southwesterly and enters Mississippi at 
Grafton, IL, about 38 miles above St. Louis. Illinois Waterway 
comprises Illinois River from its mouth to confluence 
of Kankakee and Des Plaines Rivers (273 miles), Des Plaines 
River to Lockport (18.1 miles) and Chicago Sanitary and 
Ship Canal and South Branch of Chicago River to Lake 
Street, Chicago (34.5 miles). Also from a point 12.4 miles 
above Lockport, IL, waterway comprises Calumet-Sag 
Channel and Little Calumet and Calumet Rivers to turning 
basin 5, near entrance to Lake Calumet (23.8 miles); and 
Grand Calumet River from junction to 141st Street, deep 
(lake) draft navigation (9 miles) and to Clark Street, Gary, 
IN (4.2 miles). 
Previous projects. For details, see page 1945 of Annual 
Report for 1915 and page 1172 of Annual Report for 1932. 
Existing project. See table 23-K and page 1255 of Annual 
Report for 1963. Cost of new work was $124,041,436 
and includes $445,000 for Recreation Facilities under Code 
711. Calument-Sag Modification, Part III, placed in the 
deferred-for-restudy category in March 1972, cost of 
$33,000,000 (July 1971) Federal and $20,700,000 (July 1971) 
non-Federal; and widen Marseilles Canal to 300 feet, a protion 
of work authorized by River and Harbor Act of 1935, 
placed in the deferred category, cost of $1,859,300 (July 
1971) Federal, are all exluded from present cost estimate. 
See Table 23-B for authorizing legislation. 
(See tables 23-J through 23-N on existing locks and dams; 
lock and dam construction, foundations, cost; additional 
features entering into cost of project; existing project and 
total cost of existing project.) 
Local cooperation. Complied with for completed 
modifications and Part I of Calument-Sag Modification. 
All pools above Alton Pool: 
Maintenance: Channel dredging by the Government 
cutterhead pipeline Dredge WILLIAM A. THOMPSON 
was performed in the LaGrange pool at a cost of $529,700 
with a total of 263,063 cubic yards of material being remov- 
23-2

ROCK ISLAND, IL, DISTRICT 
ed. Dredging inspection and reports were completed at a 
cost of $55,400. Strike removal and snagging and clearing 
was accomplished in various locations by hired labor at a 
cost of $121,600. Maintenance of the Lucas-Berg Disposal 
Facility cost $10,000 and contractor completed construction 
mitigation at a cost of $8,700. Structural repairs to locks 
and dams were performed by hired labor at a cost of 
$1,679,200. Contractor substantially completed repairs to 
the upstream lock gates at Lockport Lock at a cost of 
$6,700. Repairs to upstream guard cell at Lockport Lock 
were completed by contract at a cost of $24,200. Contractor 
initiated construction of lock chamber bulkhead slots and 
repairs to the riverwall at Lockport Lock at a cost of 
$742,900. Contract for replacement of lock lighting at 
Peoria and LaGrange Locks and Dams was performed at a 
cost of $228,200. Contract repairs to the Visitor's Center at 
Starved Rock Lock and Dam cost $23,700. Dredged 
material disposal activities and other environmental concerns 
in connection with dredging cost $29,400. Real estate 
support of maintenance activities cost $41,200. Buildings, 
grounds, and utility maintenance at locks and dams and Illinois 
Waterway Project Office at Peoria totaled $36,900. 
Permanent operating equipment costs were $173,700. 
Engineering and design work, including preparation of 
design memorandums cost $214,500, and supervision, administration 
and inspection for the maintenance features 
totaled $231,500. Total maintenance costs were $4,157,500 
Net credits to the project were $3,700. 
Operation and Care: Operation of the locks and dams 
and routine maintenance and minor repairs thereto were 
made at a cost of $6,369,400. Illinois Waterway Project Office 
at Peoria was continued at a cost of $822,900. Real 
estate management services were provided at a cost of 
$27,700 Visitor's Center at Starved Rock Lock and Dam 
was operated at a cost of $208,200. OSHA inspections and 
medical examinations were accomplished at a cost of 
$9,600. Contract law enforcement was provided at a cost of 
$900. Surveys, studies, and other inspections were performed 
at a cost of $850,400; natural and cultural resource activities 
cost $33,100; and water control management costs 
were $555,900. Supervision and administration for the 
operation features totaled $207,000. Total operation costs 
were $9,085,100. 
Total operation and maintenance costs were $13,242,600 
for all pools above Alton Pool. 
Rehabilitation: Rehabilitation work at LaGrange, 
Peoria, Marseilles, Brandon Road, and Lockport Lock 
Locks and Dams was in progress. Costs at LaGrange were 
$4,841,517; at Brandon Road, $86,147; at Lockport, 
-$1,516; at Marseilles, $996,654; and at Peoria, 
$5,534,868; for a total of $11,457,670. 
Alton Pool Operation: Costs by hired labor for condition 
and operation studies were $120,042; water control 
management $73,004; and supervision and administration 
$12,197. 
Alton Pool Maintenance: Costs for the year were 
$168,122 for dredging and $5,801 for supervision and administration. 
Total cost for work in Alton Pool was $379,166. 
Total operation and maintenance costs for all pools above 
Alton Pool were $13,242,600. Alton Pool operation and 
maintenance costs were $379,166; for a total operation and 
maintenance cost of $13,621,766. 
3. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement, see chapter on "Mississippi 
River between Missouri River and Minneapolis, 
MN." 
4. UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM, IL, IA, MN, MO, WI 
Location. The project is located in the Mississippi River 
Basin encompassing a 5-state area including IL, IA, MN, 
MO, and WI. 
Existing project. The project represents the initial implementation 
of the master plan prepared by the Upper 
Mississippi River Basin Association (report dated January 
1982). Project features include long-term resources monitoring, 
habitat rehabilitation and enhancement, a study of 
economic impacts of recreation, traffic monitoring, and 
recreation improvements (currently unfunded). The project 
was initiated in FY 1986 utilizing funds provided by FY 1985 
Supplemental Appropriation Act. The execution of the project 
will be closely coordinated with the Upper Mississippi 
River Basin Association, other Federal agencies, affected 
States, and local communities. See Table 23-B for authorizing 
legislation. 
Local cooperation. Local cooperation agreements will 
be sought as required. 
Operations during fiscal year. Costs during the year 
totaled $6,300,372. The majority of funds were expended on 
two program elements: habitat projects and continuation of 
long term resource monitoring. Design was initiated on 13 
projects, continued on 14: construction was initiated on 
four and continued on one. Funds were also used for the 
economic impacts of recreation study, the traffic monitoring 
program, and the general plan. 
5. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 23-C 
23-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Flood Control 
6. CORALVILLE LAKE, IA 
Location. Coralville Lake is formed by the Coralville 
Dam on the Iowa River, several miles upstream from Iowa 
City, Johnson County, IA, about 83 miles above the confluence 
of the Iowa River with the Mississippi River. 
Existing project. See page 28-4, Annual Report for 
1981, for project details. Construction began in July 1949 
and the project has been in operation since February 1958. 
About 24,406 acres of land were acquired in fee, and 
flowage easements obtained for 9,494 acres. The project was 
modified to provide for construction of a highway bridge 
crossing the lake at the Mehaffey site, which was begun in 
June 1964 and completed in October 1966. See Table 23-B 
for authorizing legislation. 
Local cooperation. None required, except in connection 
with the Mehaffey Bridge which has been fully complied 
with. 
Operations during fiscal year. New work: Additional 
land acquisition to provide for the present plan of reservoir 
operation performed at a cost of $180,546. Maintenance: 
Routine maintenance activities continued at a cost of 
$2,990,552. Reservoir maintenance and operation funds FY 
cost of $68,000. Expenditures from return of recreation use 
fees were $125,192. 
7. DES MOINES RECREATIONAL 
RIVER AND GREENBELT, IA 
Location. The greenbelt area is located along both 
banks of the Des Moines River in central IA and extends 
from a point at which relocated U.S. Highway 92 crosses the 
Des Moines River near Harvey, upstream approximately 169 
river miles to U.S. Highway 20 at Fort Dodge, IA. It includes 
the Corps' operated Lake Red Rock and Saylorville 
Lake projects. 
Existing project. The project will include, but not be 
limited to: (1) the construction, operation, and maintenance 
of recreational facilities and streambank stabilization structures; 
(2) the operation and maintenance of all structures 
constructed before the date of authorization of this project 
(other than any such structure operated and maintained by 
any person under a permit or agreement with the Secretary); 
(3) such tree plantings, trails, vegetation, and wildlife protection 
and development and other activities as will enhance 
the natural environment for recreational purposes; and (4) 
the prohibition or limitation by the Secretary of the killing, 
wounding, or capturing at any time of any wild bird or 
animal in such areas as may be directed by the Secretary. In 
carrying out the project, the Secretary may acquire by purchase, 
donation, exchange, or otherwise, land and interests 
therein, as the Secretary determines are necessary to carry 
out such project. 
The authorization requires that an Advisory Committee 
will be established for consultation with the Department of 
the Army consisting of three Corps of Engineers appointees, 
one person from the city of Des Moines, and one from each 
other incorporated municipality within the greenbelt, two 
from each of eight counties in the greenbelt, and five from 
the State of Iowa. See Table 23-B for authorizing legislation. 
Local cooperation. Letters of Assurance for the overall 
project have been furnished by Polk County, (28 Oct. 85) 
City of Johnson (11 Nov. 85), Iowa Department of Natural 
Resources (6 Dec. 85), City of Ft. Dodge (5 Dec. 85), City of 
Swan (7 Dec. 85), Marion County (16 Dec. 85), Jasper 
County (16 Dec. 85), Boone County (18 Dec. 85), Webster 
County (14 Jan. 86), City of Des Moines (7 Apr. 86), City of 
West Des Moines (28 May 87), City of Dayton (20 May 87), 
Hamilton County (1 Sep. 87), City of Stratford (12 Jan. 88), 
Polk City (12 Mar. 87), and the Town of Lehigh (13 Mar. 
86). 
Operations during fiscal year. Coordination was maintained 
with the Advisory Committee in accordance with 
Public Law 99-88. Feature Design Memoranda were completed 
for Jester Park Campground improvements 
(February 1989) and Multi-Purpose Trail, Red Rock, Segment 
I,( May 1989). The construction contract was awarded 
for the Jester Park Campground Improvements project. 
Costs incurred were $371,106. 
8. FARM CREEK, IL 
Location. Farm Creek watershed in Tazewell County, 
IL, is 60 square miles in extent. Stream empties into Illinois 
Waterway at mile 162 above mouth. 
Existing project. See page 28-5, Annual Report for 1983 
for description of project. See Table 23-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Routine 
maintenance activities were continued at a cost of $148,814. 
9. HANNIBAL, MO 
Location. Hannibal is located on the right bank of the 
Mississippi River between river miles 309 and 310 in Marion 
County. The area to be protected contains about 50 acres, 
which have been extensively developed for light industrial, 
commercial, public, and residential purposes. 
Existing project. The project provides a 500-year level 
of protection for Hannibal by construction of levees and 
floodwalls along Front and Collier Street. The proposed 
project is approximately 0.7 of a mile long, with an average 
levee height of 12.5 feet. Concrete floodwalls would be used 
in confined areas. There are four street closure structures 
and six gatewells. Provisions for interior drainage includes a 
new 3,000 foot interceptor sewer, together with a 1.0 acre 
23-4

ROCK ISLAND, IL, DISTRICT 
ponding area and a 40,000 GPM station. The area to be protected 
includes 19 blocks of the city's downtown area, including 
the historic Mark Twain District. The estimated cost 
is $6,770,000 which includes $1,690,000, non-federal costs. 
See Table 23-B for authorizing legislation. 
Local cooperation. Local cooperation agreement for the 
project was executed on 27 December 1988. 
Operations during fiscal year. Continued planning, 
engineering and design effort at a cost of $303,889. 
10. RED ROCK DAM AND LAKE RED 
ROCK, IA 
Location. The site of this project is on the Des Moines 
River, chiefly in Marion County, but extending into Jasper, 
Warren, and Folk Counties. The dam is 142.9 miles above 
the mouth of the Des Moines River, which empties into the 
Mississippi River at mile 361.4 above the mouth of the Ohio 
River. The city of Des Moines lies northwesterly from the 
site, about 60 miles upstream. 
Existing project. See page 28-6, Annual Report for 1981 
for description of the project. Construction began in May 
1960, and the dam was placed in beneficial use for storage of 
flood water in January 1969. Land acquired for the project 
consisted of 47,615 acres in fee and 29,057 acres in flowage 
easement. Landowner complaints, that lake operations have 
flooded their lands more frequently than what they were 
told to expect when flowage easements were initially acquired, 
led Congress to modify the project authorization. 
Language in PL 99-190 authorizes acquisition from willing 
sellers fee simple title in real property, which is subject to 
periodic flooding inconnection with the operation of the 
project. Potentially, there are approximately 1,000 tracts 
consisting of about 30,000 acres involved. Estimated 
Federal cost is $33,600,000. See Table 23-B for authorizing 
legislation. 
Local cooperation. None required. 
Operations during fiscal year: New Work: Land Acquisition 
costs were $227,006. The REDM (#5W) was approved 
February 1988. Preparation of second REDM (#5X) 
was initiated. Maintenance: Routine maintenance activities 
were continued at a cost of $2,475,492. Flood control reservoir 
maintenance and operation funds FY cost $68,000. Expenditures 
from the return of recreation use fees were 
$143,003. 
11. ROCKFORD, IL 
Location. The city of Rockford is located along both 
banks of the Rock River, in Winnebago County, IL. Kent 
Creek is a small stream, tributary to the Rock River, which 
flows through the right-bank portion of the city. 
Existing project. The project provides flood protection 
for the right-bank portion of the city from floods on Kent 
Creek. It consists of a rolled earth dam with outlet works 
and spillway on North Branch Kent Creek in Page Park; 
12,000 feet of channel cleanout and straightening on North 
Branch Kent Creek; raise of Levings Lake Dam on South 
Branch Kent Creek and construction of spillway and diversion 
channel; 10,800 feet of channel cleanout and 
straightening on South Branch Kent Creek; and relocations. 
Construction was initiated in October 1978. The estimated 
project cost is $17,001,736, including $6,430,000 for land 
and relocations. See Table 23-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New Work: Construction 
of the project was continued at a cost of $47,007. The project 
is now complete. 
12. SAYLORVILLE LAKE, IA 
Location. The project site is chiefly in Polk County, IA, 
but portions extend into Dallas and Boone Counties. The 
dam is about 213.7 miles above the mouth of the Des 
Moines River and about 5 miles upstream from the city of 
Des Moines, IA. 
Existing project. The dam is an earth embankment 
6,750 feet long at crest with a height of 120 feet. Outlet 
works are a single circular concrete conduit, 22 feet in 
diameter, located at the toe of the west bluff. Control structure 
is at upstream end of conduit and houses three gates. A 
stilling basin is provided to dissipate energy of discharge 
from outlet conduit. Spillway is in west bluff, weir 430 feet 
long. Water flowing over the spillway weir discharges into a 
paved chute and thence into an excavated earth channel to 
the Des Moines River. Top of spillway is about 31 feet below 
top of earth embankment section, and flow over weir is uncontrolled 
when water in reservoir reaches its crest. Watershed 
area above dam site is 5,823 square miles. With pool at 
spillway crest elevation, lake area is 16,700 acres and contains 
about 676,000 acre-feet of water at that height 
(602,000 for flood control and 74,000 for a conservation 
pool to maintain minimum flows at downstream points). 
Lake supplements capacity of downstream Lake Red Rock 
at river mile 142.9. The two lakes provide a high degree of 
flood protection to the lower Des Moines River Valley. 
Reaches along the Mississippi River downstream from the 
mouth of the Des Moines River are also benefited. 
A project modification plan to minimize the adverse environmental 
effects at Ledges State Park, located upstream 
from the dam, was authorized in 1976. The project 
modification includes relocation of affected park facilities, 
acquisition of additional park land, and the development of 
a floodway corridor, with recreational facilities, from the 
dam downstream to Sixth Avenue in Des Moines. Improvements 
to Highway 415 the main access road to existing 
facilities on the east side of the reservoir, were added to the 
project by Congress in 1984. 
Construction began in June 1965, and the dam ws placed 
in operation for the storage of flood water in April 1977. 
23-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Remedial work in Big Creek Valley, consisting of a diversion 
dam and channel and a barrier dam, for the protection 
of the town of Polk City was completed in December 1974. 
The land acquisition program involved 26,526 acres acquired 
in fee, flowage easements for 1,925 acres. The 
estimated project cost is $16,580,000 including $2,820,000 
non-Federal costs from the State of Iowa and the City of 
Des Moines, Iowa toward recreational development. See 
Table 23-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: The principal 
work item was the construction of recreational facilities and 
spillway modifications. New work costs were $1,448,816. 
Maintenance: Routine maintenance activities were continued 
at a cost of $4,594,994. Reservoir maintenance and 
operation funds FY costs of $68,000. Expenditures from 
return of recreation use fees were $200,116. The project is 
about 96 percent completed, excluding deferred work. 
13. SOUTH QUINCY DRAINAGE AND 
LEVEE DISTRICT, IL 
Location. The South Quincy Drainage and Levee 
District, in Adams County, is located on the left bank of the 
Mississippi River between river miles 318.5 and 325.5 just 
south of Quincy, Illinois. It is bounded by the Mississippi 
River on the west, the river bluffs on the east, Curtis Creek 
on north, and Mill Creek on the south. 
Existing project. About 8.8 miles of earth levee and a 
pumping station constructed by local interests and imporved 
by the Federal Government in 1967 was designed and built 
to provide protection against a flood having a 2 percent 
chance of being equaled or exceeded in any one year. Increasing 
the level of protection to a 500-year change of occurrence 
includes raising the existing levee approximately 
3.5 feet in height and adding .4 mile of levees and floodwall. 
Associated features of the proposed plan include raising and 
resurfacing existing road ramps, and a railroad closure 
structure. See Table 23-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Completed construction 
of Stage I, Levees and Floodwalls. Initiated construction of 
Stage II, Levees, and Stage III, Levees. Costs for FY 89 
were $2,623,855 
14. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Federal flood control regulations (part 208 of title 33, 
Code of Federal Regulations) provide that the structures 
and facilities constructed by the United States for local 
flood protection shall be continuously maintained in such a 
manner and operated at such times and for such periods as 
may be necessary to obtain the maximum benefits. Costs 
during the period for inspections of projects turned over to 
local interests to ascertain compliance with Federal requirements 
were $97,428. (See Table 23-H for list of completed 
flood control projects inspected.) 
15. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 23-E. 
16. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities, Section 205, Public Law 
84-685. See Table 23-I. 
Snagging and Clearing of Navigable Streams and 
Tributaries in Interest of Flood Control, Section 208, Public 
Law 83-780. See Table 23-I. 
Emergency Bank Protection (Section 14 of the 1946 Flood 
Control Act, Public Law 526.) See Table 23-I. 
Emergency Flood Control Activities, Public Law 99, 84th 
Congress. See Table 23-I. 
General Investigations 
17. SURVEYS 
The flood control study in progress during FY 89 was the 
South Fork, Sangamon River, Illinois at a cost of $129,523. 
Special investigations, FERC review, Dam Safety Criteria 
Studies. Inventory of Dams, SCS Coordination, and Planning 
Assistance to States efforts totaled $166,166. Total cost 
of surveys was $295,689. 
18. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management services cost $195,449. 
Hydrologic studies, including general studies, sedimentation 
studies, streamflow studies, and rainfall studies cost 
$195,508. Total cost for collection and study of basic data 
was $390,957. 
19. ADVANCE ENGINEERING AND 
DESIGN 
The Loves Park, IL, project, authorized by the Water 
Resources Development Act of 1986, lies in Winnebago 
County, IL, on the northeast boundary of the city of 
Rockford, 17 miles south of the IL-WI State line. The project 
would provide local flood protection (100-year level) for 
the city of Loves Park, IL, against flooding of Loves Park 
Creek (formerly called the Large Unnamed Creek). Protection 
measures would consist of 17,350 feet of channel improvements, 
a 75,000 GPM pump plant, and ponding. 
Completed the General Design Memorandum and initiated 
plans and specifications for Stage I in FY 89. Total cost of 
advance engineering and design was $227,046. See Table 
23-B for authorizing Legislation. 
23-6

ROCK ISLAND, IL, DISTRICT 
Located in Muscatine and Louisa Counties, Muscatine 
Island Levee District and Muscatine-Louisa County 
Drainage District No. 13, together with the city of 
Muscatine, Iowa form a joint drainage and flood protection 
area for 30,700 acres of bottom land. The project was 
authorized by the Water Resources Development Act of 
1986 subject to a favorable Chief's Report and approved by 
the Secretary of the Army. The project will provide flood 
protection by increasing the height of the existing main stem 
levee and flank levee. Work continued on the General 
Design Memorandum in FY 89 at a cost of $68,127. See 
Table 23-B for authorizing legislation. 
TABLE 23-A COST AND FINAN 
The West Des Moines - Des Moines, Iowa project is 
located in Polk County in central Iowa. The recommended 
project of levees and flood walls will provide flood protection 
from the Raccoon River, Walnut Creek, and Jordan 
Creek for approximately 927 urban acres. The project was 
authorized by the Water Resources Development Act of 
1986. FY 89 funds were used to complete work on the 
General Reevaluation Report (GRR) and initiate work on 
the General Design Memorandum (GDM). Preconstruction 
planning for FY 89 was $273,269. See Table 23-B for 
authorizing legislation. 
Total cost for advance engineering and design was 
$532,442. 
CIAL STATEMENT 
See 
Section 
in Text Project 
1. Illinois and 
Mississippi Canal, 
IL 
2. Illinois Waterway, 
IL and IN 
4. Upper Mississippi 
River System Enviornmental 
Management 
Program, IL, IA, MN, 
MO, WI 
6. Coralville Lake, IA 
7. Des Moines 
Recreational River 
and Greenbelt, IA 
8. Farm Creek, IL 
9. Hannibal, MO 
Funding 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Contibuted Funds 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Total Cost to 
FY 86 FY 87 FY 88 FY 89 September 1989 
- - - - 7,605,143' 
- - - - 7,605,143' 
695,000 
359,615 
42,558 
377,489 5,639 
115,000 
105,286 
18,048,3682 
18,032,6022 
- 126,707,751' 
- 126,706,419' 
10,847,351 
10,797,875 
13,841,000 
16,528,634 
12,491,000 15,938,200 12,730,200 
12,748,599 15,775,768 13,238,903 
29,671,000 18,153,200 10,865,000 
30,572,350 18,003,459 11,457,670 
814,000 1,683,000 5,911,000 7,364,000 
442,750 1,571,225 4,601,786 6,300,372 
507,889 
2,290,600 
2,045,866 
238,000 
163,997 
31,900 
132,327 72,339 
100,000 
180,546 
2,048,522 2,599,400 2,774,000 
2,225,575 2,566,631 2,990,552 
371,000 240,000 480,000 
404,519 199,368 371,106 
4,150 
25,986 8,632 
145,984 
4,916 
266,908,147' 
264,076,151' 
134,239,825 
132,889,368 
15,802,000 
12,916,133 
30,069,488' 
29,963,521' 
30,833,027 
28,780,075 
1,344,000 
1,138,990 
182,034 
39,534 
- 9,859,0206 
- 9,859,0206 
60,000 
79,811 
124,000 
117,693 
89,000 
93,074 
184,000 
119,421 
138,500 
100,069 
84,000 
154,746 
115,600 
148,814 
395,000 
303,889 
3,028,332 
2,920,082 
1,307,993 
1,216,682 
23-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 23-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 September 1989 
10. Red Rock Dam and New Work: 
Lake Red Rock, IA Approp. - - 500,000 1,057,000 96,860,484 
Cost - - 90,566 227,006 95,621,056 
Maint: 
Approp. 3,004,600 2,638,322 2,647,700 2,531,000 32,664,345 
Cost 2,638,830 2,801,950 2,914,375 2,475,492 30,210,627 
11. Rockford, IL New Work: 
Approp. 309,000 1,086,000 773,000 - 10,827,273 
Cost 564,537 159,867 1,654,337 47,007 10,006,497 
Contributed Funds 
Approp. - - 259,750 5,079 514,190 
Cost 48 - 237,736 - 481,944 
12. Saylorville Lake New Work: 
IA Approp. 7,107,000 961,000 1,500,000 1,522,000 113,809,887 
Cost 3,631,688 4,740,366 1,511,897 1,448,816 112,393,145' 
Maint: 
Approp. 3,116,600 3,823,422 3,542,400 4,568,800 34,296,665 
Cost 3,032,005 3,362,400 3,870,708 4,594,994 30,990,912 
Contributed Funds: 
Approp. 141,989 143,489 136,454 168,033 2,752,806 
Cost 141,745 245,111 166,102 44,640 2,407,254 
13. South Quincy, IL New Work: 
Approp. 209,000 230,000 2,574,000 2,570,000 5,733,000 
Cost 218,160 231,040 2,363,592 2,623,855 5,575,113 
Contributed Funds: 
Approp. - - 480,000 1,180,000 1,660,000 
Cost - - 401,083 966,423 1,367,506 
19. Loves Park, IL New Work: 
Approp. 311,000 430,000 275,000 193,000 1,409,000 
Cost 303,507 297,233 339,749 227,046 1,355,179 
Muscatine Island, IA New Work: 
Approp. - 100,000 225,000 150,000 475,000 
Cost - 25,843 238,497 68,127 332,467 
West Des Moines, IA New Work: 
Approp. - 75,000 250,000 250,000 575,000 
Cost - - 247,658 273,269 520,927 
1. Includes $25,000 Emergency Relief Funds. 
2. Includes $4,143,282 for Operating and Care under the 
"Permanent Indefinite Appropriation." 
3. Includes $2,569,102 for previous projects. 
4. Includes $1,028,468 for previous projects. 
5. Includes cost of Mehaffey Bridge, $1,365,074 (excluding 
$100,000 contributed funds). 
6. Excludes $161,813 contributed funds. 
7. Excludes $950,000 non-Federal cost. 
23-8

ROCK ISLAND, IL, DISTRICT 
TABLE 23-B 
See 
Section 
in Text 
AUTHORIZING LEGISLATION 
Date 
Authorizing 
Act Project and Work Authorized 
2. January 21, 1927 
July 3, 1930 
June 26, 1934' 
August 30, 1935 
August 30, 1935" 
June 14, 1937 
June 20, 1938 
October 23, 1943 
March 2, 1945 
Rivers and Harbors 
Committee Doc. 69th Cong., 
1st sess., and S. Doc. 130, 
69th Cong., 1st sess. 
S. Doc. 126, 71st Cong., 
2nd sess. 
ILLINOIS WATERWAY, IL AND IN 
Channel 9 feet deep and 200 feet wide from mouth 
of Illinois River to Utica, 231 miles, modification 
of 2 U.S. locks and dams, removal of 2 State 
dams. (Act authorized appropriation of not to exceed 
$3,500,000 for carrying on work.) 
Channel 9 feet deep from Utica, IL, to heads of 
present Federal projects on Chicago and Calumet 
Rivers 94.6 miles to Lake Street, and 96.3 miles to 
turning basin 5, respectively, to be secured by means 
of completed dams, locks, lateral canals, and dredging 
begun by State of Illinois in general accordance with 
present plans of State for that work. Act adopting 
project authorized appropriation of not to exceed 
$7,500,000 for carrying on work. 
Operation and care of locks and dams provided for 
with funds from War Department appropriation for 
rivers and harbors. 
Construct modern locks and dams at LaGrange and 
Peoria and a channel 9 feet deep and 300 feet wide 
below Lockport, exact location and details of design 
of all structures to be left to discretion of Chief of 
Engineers, and, for time being, that no change be 
made in water authorized for navigation of Illinois 
River by act of July 3, 1930. 
Also provides for 3 passing places along Sag 
Channel and authorized channel in Calumet-Sag 
route to turning basin 5, and dredging at entrance of 
Lake Calumet. 
Realign portion of Calumet River and abandonment 
of bypassed section of Calumet River. 
Modifies local cooperation requirements in 1935 act. 
Pay damages to levee and drainage districts due to 
seepage and other factors, not to exceed $503,500. 
Enlarge Calumet-Sag Channel to 160 feet wide and 
a usable depth of 9 feet. Dredge a barge channel 160 
feet wide with a usable depth of 9 feet in Grand 
Calumet and Little Calumet River Branch of Indiana 
Harbor Canal to deep (lake) draft through 141st St., 
East Chicago, IN. Construct in Little Calumet River 
a lock of suitable dimensions for large navigation. 
Rebuild or otherwise alter at Federal expense all 
obstructive railroad bridges across Calumet-Sag 
Channel, Little Calumet River, Calumet River, Grand 
Calumet River, and Indiana Harbor Canal, so as to 
provide suitable clearance, except that no Federal 
Iunl(s shall he expended lfor removal or alteration 
of Illinois Central RR. bridge at mile 11.20 of Little 
Calumet River. 
H. Doc. 711, 77th Cong., 
2nd sess. 
H. Doc. 145, 76th Cong., 
1st sess. 
23-9 
H. Doc. 184, 73rd Cong., 
2nd sess. 2 
H. Doc. 180, 73rd Cong., 
2nd sess. 
Rivers and Ilarbors Couniit tee 
Doc. 19, 75th Cong., 1st sess. 
Documents 
_ _ _

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 23-B (Continued) AUTHORIZING LEGISLATION 
See D)ate 
Section Authorizing 
in 'T'ext Act Project and Work Authorized Documents 
July 24, 1946 
July 24, 1946 
July 17, 1953 
July 3, 1958 
August 18, 1968 
November 17, 1986 
Substitute following work for that authorized by act 
of March 2, 1945; replace emergency dam in Chicago 
Sanitary and Ship Canal: enlargement of that canal 
thence to Sag ,Junction and of Caltimet -Sag Channel 
to afford channels 225 feet wide and usable depth of 
9 feet; construct along general route depth of 9 feet 
to 225 feet wide between Little Calumet River and 
junction with Indiana Harbor Canal and 160 feet wide 
thence to Clark St., Gary, IN, with a turning basin at 
Clark St.., enlarge Indiana Harbor Canal to 225 feet 
wide and usable depth of 9 feet between Grand 
Calumet River and vicinity of 141st St., inclusive; 
remove Blue Island lock and construct a lock and control 
works in Calumet River near its head, and 
similar structures in proposed Grand Calumet 
Channel west of Indiana Iharbor Canal; alter or eliminate 
railroad bridges across three channels lakeward 
of Chicago Sanitary and Ship Canal, or construct 
new railroad bridges to provide suitable 
clearance. 
A small-boat harbor in vicinity of Peoria, IL,b,y 
construction of a basin 510 by 250 feet, dredged to 
7 feet deep. 
$48,933 to reimburse Nutwood Drainage and Levee 
District for additional pumping operation; supplementing 
$58,750 authorized in October 1943 act. 
Federal participation in alteration of highway 
bridges, Calumet-Sag Modification, Part I, which 
constitute unreasonable obstructions to navigation, in 
accordance with Public Law 647, 76th Cong., as 
amended. 
Federal participation in alteration of highway 
bridges, Calumet-Sag Modification, Part II, which 
constitute unreasonable obstructions to navigation, 
in accordance with Public Law 647, 76th Cong., as 
amended. 
Illinois River at Peoria, IL modification of navigation 
project to include an adjacent downstream water 
area. 
UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM, IL, IA, MN, MO, WI 
Provide for a 10-year environmental program to 
include habitat rehabilitation and enhancement; longterm 
resource monitoring with computerized( inventory 
and analysis; recreational development; assessment 
of economic benefits from recreational activities; 
and navigation system traffic monitoring. 
23-10 
II. Doc. 677, 79th Cong., 
2nd sess. 
H. Doc. 698, 79th Cong., 
2nd sess. 
II. I)oc. 144, 81st Cong., 
1st sess. 
II. Doc. 45, 85th Cong., 
1st sess.4 
Specified in Act. Also 
II. I)oc. 45, 85th Cong., 
1st sess. 
Sec. 857, II.R.6, Water 
Resources Development 
Act of 1986. 
11. Doc. 2577, 99th Cong., 
1st sess. 
August 15, 1985 
(P.L. 99-88)

ROCK ISLAND, IL, DISTRICT 
TABLE 23-B (Continued) AUTHORIZING LEGISLATION 
l)nte 
Authorizing 
Act Project and Work Authorized Documents 
November 17, 1986 
June 28, 1938 
July 14, 1960 
August 15, 1985 
(P.L. 99-88) 
November 17, 1986 
8. 1944 Flood Control 
Act 
9. October 23, 1962 
10. June 28, 1938 
December 19, 1985 
11. October 23, 1962 
12. July 3, 1958 
October 22, 1976 
13. Novembcer 17, 1986 
19. November 17, 1986 
Approves 1982 Upper Mississippi River Master Plan, 
authorizes interstate agreements between Upper 
Mississippi River states, directs Secretary to implement 
GREAT II recommendations for disposal of 
dredged material and facilitate the productive use of 
dredge material, directs and interagency agreement 
with the Department of Interior for its participation in 
the plan, authorizes second lock at Lock and Dam No. 6. 
CORALVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Highway bridge across Coralville Lake at or near 
the Mehaffey site. 
DES MOINES RECREATIONAL RIVER AND 
GREENBELT, IA 
Recreational development; environmental enhancement; 
and related streambank stabilization. 
Defines area of work. 
FARM CREEK, IL 
Two flood detention dams and channel 
improvements. 
HANNIBAL, MO 
Levee, floodwall, closure structures, and pumping 
plant for flood control. 
RED ROCK DAM AND LAKE RED ROCK, IA 
Reservoir for flood control and recreation. 
Land Acquisition 
ROCKFORD, IL 
Channel enlargement and realignment, levees, and 
appurtenant works for flood control. 
SAYLORVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Modification to minimize adverse project impact on 
Ledges State Park. 
SOUTH QUINCY I)RAINAGE ANI) LEVEE 
I)ISTRIICT, IL 
Raise existing levee, construct levees and Iloodwalls 
raise road ramps and construct railroad closure. 
LOVES PARK, IL 
Improved channel, pumping plant and pond storage. 
Sec. 1103, H.R.6, Water 
Resources Development 
Act of 1986. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
None 
IH. i)oc. 2577, 99th Cong., 
1st sess. 
Sec. 604, 1H.R.6, Water 
Resources I)evelopment 
Act of 1986. 
H. Doc. 802, 78th Cong., 
2nd sess. 
II. Doc. 564, 87th Cong., 
2nd sess. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
PL 99-190 
S. Doc. 142, 87th Cong., 
2nd sess. 
S. Doc. 9, 85th Cong., 
1st sess. 
H. Doc. 487, 94th Cong., 
2nd sess. 
Sec. 401, II.l1.6, Water 
Resources I)evelopment 
Act of 1986. 
Sec. 401, H.R.6, Water 
Resources Development 
Act of 1986. 
23-11 
See 
in 'l'cxt 
6. 
7. 
__

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 23-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
MUSCATINE ISLAND LEVEE DISTRICT 
AND MUSCATINE-LOUISA COUNTY 
DRAINAGE DISTRICT, NO. 13, IA 
19. November 17, 1986 Raise existing levees. Sec. 401, H.R.6, Water 
Resources Development 
Act of 1986. 
WEST DES MOINES, IA 
19. November 17, 1986 Construct levees and floodwall. Sec. 401, H.R.6, Water 
Resources Development 
Act of 1986. 
1. Permanent Appropriations Repeal Act. 3. Included, in part, in Public Works Administration Program 
2. Contains latest published map of Illinois and Des Plaines October 31, 1934, and February 28, 1935. 
Rivers. 4. Contains latest published maps of Calumet-Sag portion. 
TABLE 23-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 5 of Text) 
For Last Cost To September 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Hannibal SBH, MO Completed 1958 108,7004 58,000 
Squaw Chute at Quincy, IL Completed 1967 70,979' 9,345 
Muscooten Bay, Illinois River, IL Completed 1985 265,499 ' 167,504 
Quincy, IL, Harbor Access Channel Completed 1970 35,4772 37,700 
Muscatine Harbor, IA Completed 1964 353,000 85,999 
1. Excludes $25,851 contributed funds. 3. Excludes $137,869 contributed funds. 
2. Excludes $35,350 contributed funds. 4. Excludes $20,300 contributed funds. 
TABLE 23-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 15 of Text)
Cost To September 30, 1989 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Projects 
Banner Special Drainage and Levee Districts, IL 
Bear Creek Dam (City of Hannibal, MO) 
Bettendorf, IA 
Big Lake Drainage and Levee District, IL 
Canton, MO' 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
Des Moines and Mississippi Levee District 
No. 1, MO 
Des Moines, IA 
Drury Drainage District, IL 
Dubuque, IA 
East Liverpool Drainage and Levee District, IL 
1943 
1962 
1987 
1943 
1964 
1981 
1954 
1941 
1969 
1972 
1964 
1974 
1941 
247,822 
1,679,056 
14,827,293 
144,910 
1,496,555 
26,001,996 
1,923,145 
68,898 
1,492,016 
4,993,224 
1,144,875 
10,861,170 
207,826 
-
- 
228,073 
761,050 
23,323 
145,415 
23-12

ROCK ISLAND, IL, DISTRICT 
TABLE 23-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) (See Section 15 of Text)
Cost To September 30, 1989 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Projects 
East Moline, IL 1984 9,692,097 - - 
East Peoria Drainage and Levee District, IL 1946 279,963 - - 
Elkport, IA 1951 34,200 - - 
Evansdale, IA 1983 4,409,088 - - 
Fabius River Drainage District, MO 1941 60,500 - - 
Fabius River Drainage District, MO 1963 1,621,841 - - 
Farmers Levee and Drainage District, IL 1942 155,562 - - 
Fulton, IL 1984 18,017,200 - - 
Galena, IL 1952 844,100 - 118,000 
Green Bay Levee and Drainage District No. 2, IA 1949 299,000 - - 
Green Bay Levee and Drainage District No. 2, IA 1967 1,727,711 - - 
Gregory Drainage District, MO 1940 77,100 - - 
Gregory Drainage District, MO 1972 1,538,963 - 20,626 
Henderson County Drainage District No. 1, IL 1968 1,453,217 - - 
Henderson County Drainage District No. 2, IL 1968 1,043,902 - - 
Henderson County Drainage District No. 3, IL 1949 42,700 - - 
Hennepin Drainage and Levee District, IL 1940 109,593 - - 
Hunt Drainage District and Lima Lake Drainage 
District, IL 1972 4,772,498 - - 
Indian Grave Drainage District, IL 1972 3,551,961 - - 
Iowa River-Flint Creek Levee District No. 16, IA 1972 6,044,693 - - 
Kishwaukee River at DeKalb, IL' 1957 123,300 - - 
Lacey Langellier, West Mantanzas and Kerton 
Valley Drainage and Levee District, IL 1954 1,290,000 - - 
Liverpool Drainage and Levee District, IL 1943 117,731 - - 
Lost Creek Drainage and Levee District, IL 1938 152,000 - - 
Marengo, IA' 1981 2,447,001 - - 
Marion County Drainage District, MO 1967 873,748 - - 
Marshalltown, IA 1978 8,437,511 - 252,136 
Mason and Menard Drainage District, IL 1940 93,808 - - 
Meredosia Levee and Drainage District, IL' 1977 1,995,322 - 269,739 
Milan, IL 1988 13,430,596 - 213,554 
Muscatine, Mad Creek, IA' 1983 1,129,800 - - 
Muscatine Island Levee District and Muscatine- 
Lousia County Drainage District No. 13, IA 1970 3,293,276 - 220,000 
Near Springfield on Sangamon River, IL 1941 - - - 
Oakford Special Drainage District, IL 1940 38,417 - - 
Okabena Creek at Worthington, MN' 1957 72,432 - - 
Ottumwa, IA 1977 233,145 - - 
Pekin and La Marsh Drainage and Levee 
District, IL 1955 158,383 - - 
Penny Slough, Rock River, IL 1940 85,800 - - 
Rock Island, IL 1979 7,582,373 - - 
Rocky Ford Drainage and Levee District, IL 1941 108,797 - - 
Sabula, IA 1958 411,915 - - 
Sagamon River (Mouth), IL 1980 1,048,990 272,848 15,122 
Seahorn Drainage and Levee District, IL 1945 32,281 - - 
Sid Simpson Project, IL 1968 5,789,800 - - 
Sny Basin, IL 1972 14,003,560 - - 
Sny Island Levee Drainage District, IL 1942 61,400 - - 
Sny Island Levee Drainage District, IL 1968 4,956,749 - - 
23-13

TABLE 23-E 
(Continued) 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 15 of Text) 
Cost To September 30, 1989 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
South Beardstown and Valley Drainage and 
Levee District, IL 1942 220,729 -- 
South Beardstown Drainage and Levee District, IL 1942 171,839 - - 
South Quincy Drainage and Levee District, IL 1940 61,200 -- 
South Quincy Drainage and Levee District, IL 1968 1,231,243 - - 
South River Drainage District, MO 1941 55,300 -- 
South River Drainage District, MO 1966 1,106,056 - - 
Spring Lake Drainage and Levee District, IL 1941 185,980 -- 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1,IL 1967 3,306,695 - - 
Union Township Drainage District, MO 1947 116,576 - - 
Van Meter, IA' 1965 113,842 -- 
Authorized Projects Not Constructed 
Ames Dam and Reservoir, Skunk River, IA 1987 1,400,800 - - 
Davenport, IA 1987 - - 
Moline, IL2 1987 - - - 
Peoria, IL 1973 534,580 - - 
Rock River Agricultural Levees, IL 1984 858,000 -- 
Waterloo, IA (Bridges) 1987 - - 
1. Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act). 
2. FY 89 funds of $5,639 were expended to close out project. 
TABLE 23-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For i)cauthorized Expended Expended 
Cal.-Sag Channel, Part II 
Illinois Waterway, IL and IN 
Campbells Island 
Mississippi River, IL 
Carroll County Levee 
and Drainage District, IL 
Central City Lake, 
Wapsipinicon River, IA 
Farmers Drainage and Levee 
District (Sangamon River), IL 
Freeport, IL 
Green Island Levee and 
Drainage District, IA 
1-Henderson River, ILI 
Illinois Waterway, IL and IN 
Duplicate Locks 
Illinois Waterway 
Navigation Project (Pekin, IL) 
Janesville and Indian 
Ford Dams, WI 
1986 
1969 
1938 
1970 
1942 
1979 
1938 
1964 
1982 
1986 
1938 
1986 
1979 
1977 
1977 
1986 
1986 
1977 
1977 
1981 
1986 
1977 
$ 76,664 
55,664 
286,000 
102,310 
23-14

ROCK ISLAND, IL, DISTRICT 
'TABLE 23-G (Continued) DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Keithsburg Drainage 
District, IL 1938 1977 
Pecatonica River at 
Darlington, WI - 1977 
Rochester Lake, 
Cedar River, IA - 1977 - 
South Beloit, IL 1979 1986 270,000 
William L. Springer Lake 
Decatur, IL 1979 1986 - - 
TABLE 23-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 14 of Text) 
Date 
Project Inspected 
Alpine Dam and Page Park Dam, Rockford, IL 
Banner Special Drainage and Levee District, IL 
Bear Creek Reservoir, Hannibal, MO 
Bettendorf, IA 
Big Lake Drainage and Levee District, IL 
Burlington, IA 
Canton, MO 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
DeKalb, IL 
Des Moines, IA 
Des Moines and Mississippi Levee District No. 1, MO 
Drury Drainage District, IL 
Dubuque, IA 
East Liverpool Drainage and Levee District, IL 
East Moline, IL 
East Peoria Drainage and Levee District, IL 
East Peoria Sanitary District, IL 
Elkport, IA 
Evansdale, IA 
Fabius River Drainage District, MO 
Farmers Drainage and Levee District, IL 
Fulton, IL 
Galena, IL 
Green Bay Levee and Drainage District, No. 2, IA 
Gregory Drainage District, MO 
Henderson County Drainage District No. 1, IL 
Henderson County Drainage District No. 2, IL 
Hennepin Drainage and Levee District, IL 
Hergot Drainage and Levee District, IL 
Hunt Drainage District & Lima Lake Drainage District, IL 
Indian Grave Drainage District, IL 
September 1988 
December 1988 
January 1989 
October 1988 
December 1988 
December 1988 
March 1989 
September 1988 
April 1989 
February 1989 
September 1988 
October 1988 
April 1989 
December 1988 
September 1988 
January 1989 
October 1988 
December 1988 
March 1989 
September 1988 
November 1988 
April 1989 
February 1989 
September 1988 
September 1988 
November 1988 
January 1989 
November 1988 
November 1988 
January 1989 
January 1989 
January 1989 
January 1989 
23-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 23-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(Continued) (See Section 14 of Text) 
Date 
Project Inspected 
Iowa River-Flint Creek Levee District No. 16, IA 
Kerton Valley Drainage and Levee District, IL 
Lacey Drainage and Levee District, IL 
Langellier Darinage and Levee District, IL 
Liverpool Drainage and Levee District, IL 
Lost Creek Drainage and Levee District, IL 
Mad Creek, Muscatine, IA 
Marengo, IA 
Mason and Menard Drainage District, IL 
Marion County Drainage District, MO 
Marshalltown, IA 
Meredosia Levee and Drainage District, IL 
Milan, IL 
Muscatine Island, L&DD, &Louisa DD No. 13, IA 
Oakford Special Drainage and Levee District, IL 
Pekin-LaMarsh Drainage and Levee District, IL 
Penny Slough Drainage and Levee District, IL 
Rock Island, IL 
Sabula, IA 
Sanitary District of Beardstown, IL 
Seahorn Drainage and Levee District, IL 
Sny Island Levee Drainage District, IL 
South Beardstown Drainage and Levee District, IL 
South River Drainage District, MO 
Spring Lake Drainage and Levee District, IL 
Subdistrict No. 1 of Drainage Union No. I 
and Bay Island Levee and Drainage District No. 1, IL 
The Sny Basin, IL 
Valley Drainage and Levee District IL 
Van Meter, IA 
Volga, IA 
Waterloo, IA 
West Matanzas Drainage and Levee District, IL 
Worthington, MN 
December 1988 
March 1989 
March 1989 
March 1989 
February 1989 
December 1988 
December 1988 
November 1988 
January 1989 
May 1989 
November 1988 
October 1988 
October1988 
December 1988 
January 1989 
March 1989 
September 1988 
October 1988 
September 1988 
March 1989 
December 1988 
March 1989 
March 1989 
May 1989 
March 1989 
December 1988 
March 1989 
March 1989 
October 1988 
September 1988 
November 1988 
March 1989 
December 1988 
TABLE 23-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 
858, 80th Congress, as Amended (Preauthorization) 
(See Section 16 of Text) 
Study Identification 
Cedar Falls, Cedar River, IA 
DeKalb, Kishwaukee River, IL 
Des Moines River, IA 
East Peoria, IL 
Gale Creek, Oregon, IL 
Village of Hull, IL 
Illinois, and Michigan Canal, IL 
Fiscal Year Costs 
$ 3,473 
241 
18,654 
28,297 
54,716 
8,275 
21,264 
23-16 
a

ROCK ISLAND, IL, DISTRICT 
TABLE 23-I 
(Continued) 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 
858, 80th Congress, as Amended (Preauthorization) 
(See Section 16 of Text) 
Study Identification Fiscal Year Costs 
Illinois River, Liverpool, IL 
Iroquois River, Sugar Creek, Watseka, IL 
North River, Marion County, MO 
No Name Creek, Waterloo, IA 
Oelwein, Fayette County, IA 
Ottawa, IL 
Panther Creek, Sangamon River, Chandlerville, IL 
Raccoon River, Des Moines, IA 
Sabula, IA 
Sink Creek, Waterloo, IA 
Tama, IA 
Vermilion River, Pontiac, IL 
Walnut Creek, Clive, IA 
Willow Creek, Mason City, IA 
$15,398 
7,035 
34,060 
14,000 
17,610 
9,683 
5,968 
43,625 
3,242 
9,917 
4,575 
2,029 
8,813 
37,426 
TABLE 23-I Snagging and Clearing Navigable Streams and 
Tributaries in the Interest of Flood Control (Preauthorization) 
(Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress) 
(See Section 16 of Text) 
Project and Location Fiscal Year Costs 
Carbon Cliff, Sec 3 & 4, RIE, IL $12,909 
Kickapoo Creek, DeWitt Co., IL 15,000 
TABLE 23-I Emergency Bank Protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
(See Section 16 of Text) 
Project and Location Fiscal Year Costs 
Buena Vista, IA $25,633 
Des Moines River, Bridge 32527, MN 14,300 
Eldon, IA 10,534 
Farmington, Des Moines River, IA 8,685 
Iowa River, Louisa Co., IA 9,611 
Iowa River, Wapello, IA 12,092 
Monroe County, IA 6,656 
North River, Klien Bridge, MO 9,565 
Oquawka, Mississippi River, IL 3,054 
Oxford Junction, Wapsi River, IA 30 
Sangamon River, Riverton, IL 24,626 
Stuart, IL 14,485 
Van Buren Co., IA 8,605 
Wapello County, IA 4,490 
Whitetie River, Grundy County, IL 8,235 
23-17

TABLE 23-I 
(Continued) 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Emergency Flood Control Activities - Repair, Flood Fighting, and 
Rescue Work (Public Law 99, 84th Congress and Antecedent Legislation) 
(See Section 16 of Text) 
Project and Location Federal Cost 
Advance Preparation $376,975 
Rehabilitation: 
Sny Island D.D., IL 280,860 
Emer Water Supply & Drought Assistance: 
Blandinsville, IL 66,801 
Packard, IA 3,600 
Papineau, IL 68,129 
TABLE 23-J ILLINOIS WATERWAY: 
EXISTING LOCKS AND DAMS 
(See Section 2 of Text) 
Depth on 
D)imensions Miter Sills 
at Low Water 
Available Lift at 
Miles Width of length for Low 
Above Chamber Full Width Water' Lower Upper 
Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) 
LaGrange Lock 80.2 7.8 below leardstown, IL 110 600 10.0 13.0 15.5 
Peoria Lock 157.7 4.1 below Peoria, IL 110 600 11.0 12.0 15.5 
Starved Rock Lock 231.0 Utica, IL 110 600 18.5 14.0 16.8 
Marseilles Lock 244.6 Marseilles, IL 110 600 24.45 14.0 18.6 
Dresden Island Lock 271.5 8 above Morris, IL 110 600 21.75 12.25 16.85 
Brandon Road Lock 286.0 Joliet, IL 110 600 34.0 13.8 17.85 
Lockport Lock 291.1 Lockport, IL 110 600 30.5-39.52 15.0 11.0-20.0' 
T.J. O'Brien Lock 326.5 Chicago, IL 110 1,000 - 14.0 14.0 
1. Lifts and depth on miter sills are those obtained with 2. Variation in lift and depth on upper miter sill at 
flat pools. Loclkport is (Itde to Iluctuation of water surface in the sanitary 
district canal. 
TABLE 23-K ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 2 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Illinois River, $ 2,733,499' 
mouth to Utica; 
channel improvement 
by dredging 
in Illinois River 
below Starved Rock 
modification of two 
U.S. locks and 
dams, and removal 
of two State dams. 
23-18

ROCK ISLAND, IL, DISTRICT 
TABLE 23-K 
(Continued) 
ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 2 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Concrete Piles in sand 
Concrete Piles in sand 
Starved Rock 
Marseilles 
Dresden Island 
Brandon Road 
I ockport 
T.J. O'Brien 
Lock and damn 
equipment 
'l'ota I locks 
and dams 
1. Actual cost. 
TABLE 23-L 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Concrete 
and sheet 
piling 
Piles in clay Fixed 
ILLINOIS WATERWAY, IL AND IN 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 2 of Text) 
Dredging: 
Little Calumet and Calumet Rivers 
Calumet-Sag, 3 passing places 
Starved Rock to Lockport 
Starved Rock to Grafton 
Calumet-Sag Channel 
Peoria small boat harbor 
$ 2,135,358' 
813,418' 
3,650,635 
2,917,607 
19,238,200 
24,937' 
23-19 
LaGrange 
Peoria 
Movable 
(wicket 
with Aframe-
crest) 
Movable 
(wicket 
type) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Movable 
(Bear trap) 
(Bear trap) 
Concrete 
and timber 
Concrete 
and timber 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Concrete 
anI 
structural 
steel 
Concrete 
a nd 
structural 
steel 
Concrete 
an(l sheet 
piling 
Piles in sand 
Piles in sand 
Rock 
Rock 
Rock 
Rock 
Rock 
Piles in clay 
1939 
1939 
1933 
1933 
1933 
1.933 
1933 
1960 
2,744,592' 
3,381,030' 
885,315' 
1,853,725' 
$ 2,503,376' 
2,031,683' 
133,608' 
6,954,700' 
1,250,304' 
$ 24,471,832

TABLE 23-L 
(Continued) 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
ILLINOIS WATERWAY, IL AND IN 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 2 of Text) 
Protection piers at all locks 
Calumet-Sag modification engineering and design 
Calumet-Sag modification, supervision and administration 
Rebuild highway bridges 
Rebuild railway bridges: 
Calumet-Sag Channel 
Little Calumet and Calumet Rivers 
Recreation Facilities, Code 711 
Removal of Blue Island lock 
Grand Calumet River controlling works2 
St. Louis District 
Total additional features 
Total existing project 
1. Actual cost. 
TABLE 23-M 
77,613' 
5,141,474 
5,466,804 
19,327,850 
20,828,435' 
18,362,041' 
445,000 
288,600' 
3,375,704' 
$100,442,142 
$124,913,974 
2. Placed in inactive status November 19, 1974. 
EXISTING PROJECT 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
2. Illinois Waterway, Nine locks and six dams - - 
IL and IN 
Grafton to Lockport, IL 291.1 miles 300 9 
Lockport to controlling works 2.0 miles 200-300 9 
Controlling works to junction with 10.0 miles 225 9 
Calumet-Sag Channel 
Calumet-Sag Channel to lock in Blue 16.0 miles 225 9 
Island 
Calumet and l,ittle Calumet Channel, 7.7 miles 300 9 
from Blue Island to turning basin 5 
Grand Calumet River Channel from 9.0 miles 9 
junction with Little Calumet River 
to and in Indiana Harbor Canal to 
141st, East Chicago, IN 
Also, Grand Calumet River Channel 4.2 miles 160 9 
from junction of Indiana Harbor 
Canal and Grand Calumet River to 
Clark St. in Gary, IN, with a turning 
basin at Clark St. 
A channel in Chicago Sanitary and 22.1 miles 175-300 9 
Ship Canal and South Branch 
Chicago River from Sag-Junction to 
Lake St. in Chicago, IL 
23-20

ROCK ISLAND, IL, DISTRICT 
TABLE 23-N ILLINOIS WATERWAY, IL AND IN 
TOTAL COST OF EXISTING PROJECT 
TO SEPTEMBER 30, 1989 
(See Section 2 of Text) 
New Work Maintenance Rehabilitation Total 
Regular Funds $120,886,748 $264,076,151 $132,889,368 $517,852,267 
Public Works Funds 3,960,735 - - 3,960,735 
Emergency Relief Funds 1,858,936 - - 1,858,936 
Total $126,706,419 $264,076,151 $132,889,368 $523,671,938' 
1. Includes $1,735,890 expended between 1927 and 1936 on the visions of the permanent indefinite appropriation for such purposes. 
operation and care of the works of improvement under the pro- 
23-21

ST. PAUL, MN DISTRICT * 
District comprises western Wisconsin, major portion of 
Minnesota, northern and eastern North Dakota, and small portions 
of northeastern South Dakota and northern and northeastern 
Iowa embracing drainage basins of Mississippi River and 
tributaries from its source to mile 614 above mouth of Ohio 
River; Red River of the North and tributaries; those streams 
north of Missouri River Basin in North Dakota; and U.S. waters 
of Lake of the Woods and its tributaries. That section of 
Mississippi River above mile 614 is included in report on 
Mississippi River between Missouri River and Minneapolis, 
Minnesota. 
IMPROVEMENTS 
Navigation Page 
1. Minnesota River, MN .......................................... 24-2 
2. Mississippi River between Missouri River and 
Minneapolis, MN ..................................... 24-2 
3. Reservoirs at Headwaters of Mississippi River, MN. 24-2 
4. St. Croix River, MN & WI .................................. 24-3 
5. Warroad Harbor and River, MN ........................... 24-3 
6. Zippel Bay, Lake of the Woods County, MN .......... 24-3 
Flood Control 
7. Bassett Creek, MN .................................. 24-4 
8. Big Stone Lake and Whetstone River, MN and SD. 24-4 
9. Cannon River at Faribault, MN ............................ 24-4 
10. Chaska, MN ..................................... 24-5 
11. Devils Lake, ND ..................................... 24-5 
12. Eau Galle River, WI ..................................... 24-5 
13. Emerson, Manitoba-Noyes, MN ........................ 24-6 
14. Enderlin, Maple River, ND .................................. 24-6 
15. Grafton Pumping Station, ND .............................. 24-6 
16. Homme Lake and Dam, ND ................................ 24-6 
17. Houston, MN ...................................... 24-7 
18. Lac qui Parle Lakes, Minnesota River, MN ............ 24-7 
19. La Farge Lake and Channel Improvement, WI ....... 24-7 
20. Lake Andrusia, Mississippi River, MN ................ 24-8 
21. Lake Ashtabula and Baldhill Dam, Sheyenne 
River, ND ..................................... 24-8 
22. Lake Pulaski, Wright County, MN ....................... 24-8 
23. Lake Traverse and Bois de Sioux River, SD 
and MN ..................................... 24-9 
24. Mankato and North Mankato, MN .......................... 24-9 
25. Marshall, MN ..................................... 24-9 
26. Middle River at Argyle, MN ............................... 24-10 
27. Minnesota River at Henderson, MN ....................... 24-10 
28. Pettibone Park, La Crosse, WI ................................ 24-10 
29. Portage, WI ....................................... 24-10 
30. Prairie du Chien, WI .................................... 24-11 
31. Red Lake River, MN including Clearwater River, 
MN ..................................... 24-11 
32. Red Lake River, Gentilly, MN ............................ 24-11 
33. Red River of the North at Argusville, ND ........... 24-12 
34. Red River of the North at Breckenridge, MN ......... 24-12 
35. Red River of the North drainage basin, MN, SD 
and N D ................................................................ 24-12 
Page 
36. Rochester, M N .................................................... 24-13 
37. Roseau River, MN ..................................... 24-13 
38. Sheyenne River, ND ..................................... 24-14 
39. Souris River Basin, ND ........................................ 24-14 
40. State Road and Ebner Coulees, WI ...................... 24-15 
41. St. Paul, M N ........................................................ 24-15 
42. Wild Rice River, South Branch and Felton 
Ditch, M N .......................................................... 24-15 
43. W inona, M N ...................................................... 24-16 
44. Zumbro River at Jarrett and Millville, MN ............. 24-16 
45. Inspection of completed flood control projects ....... 24-16 
Miscellaneous 
46. Other work under special authority ..................... 24-17 
General Investigations 
47. Surveys ..................................... 24-17 
48. Collection and study of basic data ....................... 24-17 
49. Advance engineering and design ......................... 24-17 
Tables 
Table 24-A Cost & Financial Statement .................. 24-18 
Table 24-B Authorizing Legislation ......................... 24-22 
Table 24-C Other Authorized Navigation Projects ....... 24-23 
Table 24-D Not Applicable 
Table 24-E Other Authorized Flood Control Projects .. 24-24 
Table 24-F Not Applicable 
Table 24-G Deauthorized Projects ............................ 24-26 
Table 24-H Reservoirs at Headwaters of 
Mississippi River ...................................... 24-27 
Table 24-I Red River of the North Drainage Basin: 
Active Units in Comprehensive Basin 
Plan .................................. 24-28 
Table 24-J Inspection of Completed Flood Control 
Projects ..................................... 24-29 
Table 24-K Flood Control Work Under Special 
Authorization ..................................... 24-30 
Table 24-L General Investigations ........................... 24-31 
24-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. MINNESOTA RIVER, MN 
Location. Rises in Big Stone Lake, MN and SD, and flows 
southeasterly about 224 miles to Mankato, MN, thence northeasterly 
about 106 miles to join the Mississippi River opposite 
St. Paul, MN. (For general location see Geological Survey map 
of Minnesota.) 
Previous projects. For details see page 1890 of Annual 
Report for 1915, and page 1105 of Annual Report for 1938. 
Existing project. Provides 9-foot depth below flat pool 
level of Mississippi River lock and dam 2 from mouth to mile 
14.7, one-half mile above the railway bridge at Savage, MN, and 
4-foot depth from mile 14.7 to 25.6 at Shakopee, MN. For 
details see page 1018 of Annual Report for 1965. (See table 24- 
B for authorizing legislation.) 
Local cooperation. Fully complied with. See also page 
1074 of Annual Report for 1967. 
Terminal facilities. There are privately-owned terminals at 
miles 9, 13.1, 14.5, and two at mile 14.7. 
Operations and results during fiscal year. Maintenance: 
Dredging by hired labor cost $77,736. Snagging and clearing 
cost $24,409 by hired labor. Engineering and administrative 
costs amounted to $9,554. 
Condition at end of fiscal year: Work on project for 4-foot 
depth was completed in 1931. The United States owns 10 acres 
of land in fee 2 miles east of Savage, MN, and easements on 
123.08 acres of land. 46.20 acres have been transferred from the 
Department of the Army and Department of the Air Force to the 
project. Navigation from mouth to Shakopee was practicable for 
drafts not in excess of 3 feet. A contract for work under 1958 
authorization for a 9-foot channel started in May 1966 and was 
terminated in January 1967 when 56 percent complete. A 
channel dredging contract awarded in June 1967 was completed 
in August 1968. Total costs for existing project to September 30, 
1989, were $4,648,311, of which $1,940,180 was for new work 
and $2,708,131 for maintenance. In addition, cost from contributed 
funds was $139,671 for dredging to 9-foot depth under 
provisions of section 4, River and Harbor Act of 1915, and 
$219,531 for work done for the State of Minnesota relative to 
modification of the project. 
2. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement see chapter on Mississippi 
River between Missouri River and Minneapolis, Minnesota. 
3. RESERVOIRS AT HEAD WATERS OF 
MISSISSIPPI RIVER, MN 
Location. Reservoirs are on the Mississippi River and 
several of its tributaries in Itasca, Beltrami, Hubbard, Aitkin, 
Cass and Crow Wing Counties, MN. (See table 24-H on reservoirs.) 
Previous projects. For details see page 1888 of Annual 
Report for 1915,and page 1098 of Annual Report for 1938. 
Existing project. Provides for reconstruction from timber to 
concrete at Winnibigoshish, Leech Lake, Pokegama, Sandy 
Lake and Pine River Dams, and construction of a concrete dam 
at Gull Lake. Pokegama was built on bedrock and the others on 
pile foundations. A portion of Leech Lake Dam from piers 26 to 
39 was replaced with an earth fill. Constructed three dikes at 
Winnibigoshish, four at Pokegama, two at Sandy Lake, and 16 
at Pine River. Sandy Lake Dam includes a lock 160 feet long, 
30 feet wide, with a maximum lift of 9.5 feet and a depth of 2.5 
feet on lower sill at low water which was converted to use as a 
spillway. (See table 24-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None. 
Operations and results during fiscal year. Maintenance: 
Reservoirs were operated as required, recreation facilities and 
equipment maintained, and surveys, repairs, and reports were 
made by hired labor at a cost of $1,243,462. Reservoirs were 
operated by contract at a cost of $126,191 and by U.S. Geological 
Survey for $30,265. Physical security cost $3,195 by hired 
labor. Periodic inspection and dam safety costs were $89,728 by 
hired labor, $14,815 by contract and $30,477 by other Corps. 
Cultural resource investigation cost $9,293 by contract, $37,832 
by hired labor and $-3,800 by other Corps. Land acquisition 
analysis and survey cost $14,234 by hired labor. Environmental 
review and drought planning cost $13,485 by hired labor and 
$5,999 by other Corps. Data collection, water analysis, structural 
inventory for drought planning and maintenance of stream 
gauging cost $209,442 by hired labor, $5,283 by contract, 
$4,470 by other Corps, and $38,480 by U.S. Geological Survey. 
Miscellaneous engineering and design cost $212,257 by hired 
labor, and $78,841 by contract. Real estate was managed at a 
cost of $23,740. Lands and damages cost $31,358. Supervision 
and administration and other miscellaneous costs were $319,313. 
Condition at end of fiscal year: Existing project was completed 
in 1937. Flowage rights were acquired on all lands 
affected by construction, maintenance, and operation of reservoirs. 
A total of 1,672.26 acres in fee are owned by the United 
States. The United States has easements, flowage rights, and 
24-2

ST. PAUL, MINNESOTA DISTRICT 
other rights of use on another 296,334.44 acres. Structures are 
in fair condition. Recreation facilities for public use are being 
constructed intermittently at all reservoir areas. (See table 24- 
H for capacities and costs by reservoir.) 
4. ST. CROIX RIVER, MN & WI 
Location. From source in northwestern Wisconsin, flows 
southwesterly and then southerly about 164 miles to Mississippi 
River at Prescott, WI, about 41.7 miles below lower Burlington 
Northern railway bridge, Minneapolis, MN. For its greater part, 
forms boundary between Minnesota and Wisconsin. (See Geological 
Survey map of Minnesota.) 
Existing project. Provides for maintenance of a channel, 9 
feet in depth and of suitable width from mouth to Stillwater, MN, 
24.5 miles, created by improvement of upper Mississippi River; 
a channel 3 feet deep at mean low water between Stillwater and 
Taylors Falls (27.3 miles); improvement of harbor and waterfront 
at Stillwater; and a small-boat harbor at Hudson, WI, which 
was deauthorized on November 17, 1986 under Section 1002 of 
the 1986 Water Resources Development Act. (See table 27-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. At Stillwater there is a concrete paved 
levee and a piling-and-timber trestle wharf on right bank. At 
other points along river, landing may be made on banks. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Channel dredging by Government pipeline dredge WILLIAM 
A. THOMPSON cost $65,500. 
Condition at end of fiscal year: All new work was completed 
in 1930. The United States owns 2.75 acres of land in fee at 
Taylors Falls and has easements over 7.57 acres of land at 
Bayport, MN. Extension to provide a 9-foot channel from 
mouth to Stillwater was completed August 12, 1938, when full 
pool at dam 3 of Mississippi River canalization project was 
reached. Minimum draft from Stillwater to Taylors Falls is 
about 1 foot at extreme low water, and from mouth to Stillwater, 
9 feet. Maintenance of the 3-foot channel is limited to requests 
by the National Park Service which manages this reach under the 
Wild and Scenic Waterways classification. 
5. WARROAD HARBOR AND 
RIVER, MN 
Location. At southwestern extremity of Lake of the Woods, 
36 miles west of mouth of Rainy River. (See NOAA Nautical 
chart 14999.) 
Existing project. Provides for a channel 8 feet deep from 
landing at Warroad to deep water in lake, channel being 9,200 
feet long, 200 feet wide within harbor, and 300 feet wide out in 
lake; for a turning basin 500 by 900 feet to a depth of 8 feet; and 
for a pile-brush stone jetty on north side of channel extending 
from shore 700 feet into the lake. For additional details see page 
1027 of Annual Report of 1965. Portion of dredging of entrance 
channel and turning basin to complete project width and depth 
was considered unnecessary to meet present navigation requirements, 
and classified inactive was deauthorized on August 5, 
1977, under Section 12 of Public Law 93-251. (See table 27-B 
for authorization legislation.) 
Local cooperation. None required. 
Terminal facilities. There is one publicly owned wharf. 
There are two commercial fish wharves, one of which is served 
by a spur track, and a number of minor wharves, all privately 
owned. Facilities are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design cost $10,614. Administrative costs 
were $1,496. 
Condition at end of fiscal year: Project is complete. Prospective 
jetty completed in 1910 and reconstructed as a rubble 
mound in 1929 is in good condition. Turning basin at Warroad 
wharves was completed in 1911, and a channel 200 feet wide and 
8 feet deep in 1915. Controlling depth in river channel and lake 
approach channel was 6 feet below low-water datum for a 
minimum width of 100 feet. A walkway on the jetty is provided 
for public use. A revetment wall, constructed under Section 2 of 
Public Law 269, 69th Congress, in accordance with Article VIII 
of the Lake of the Woods Treaty, has deteriorated and will 
require future maintenance. 
6. ZIPPEL BAY, LAKE OF THE WOODS 
COUNTY, MN 
Location. Zippel Bay is a natural harbor located in northwestern 
Minnesota on the south shore of Lake of the Woods near 
Williams, Minnesota. The navigation project is located in 
Zippel Bay State Park. 
Existing project. Boats based at a state park, resort, marina, 
and a number of private residences use Zippel Bay to provide 
access to the lake. However, the natural channel between the 
bay and Lake of the Woods varied in depth and width and 
restricted navigation. The plan of improvement provides a 
small-boat access channel 50-70 feet wide and approximately 
1,800 feet long between Zippel Bay and Lake of the Woods. 
Jetties have been constructed on both sides of the channel to 
minimize the amount of maintenance dredging. The project was 
approved by the Chief of Engineers for construction in October 
1985 under the authority contained in Section 107 of the River 
and Harbor Act of 1960, as amended. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New Work: An 
adjustment of $59,030 was made based on an audit of final 
project costs. 
24-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Condition at end of fiscal year: Construction of the small 
boat navigation project is completed. Responsibility for the 
project was transferred to the local sponsor, the State of Minnesota 
Department of Natural Resources, in July 1988. 
Flood Control 
7. BASSETT CREEK, MN 
Location. In Hennepin County and Minneapolis, Minnesota, 
on Bassett Creek, a tributary of the Mississippi River. (For 
general location, see Geological Survey map of Minnesota.) 
Existing project. The proposed project consists of nonstructural 
and structural flood control measures. Nonstructural 
measures include continuation of existing floodplain regulations, 
flood insurance and forecasting, and flood warning. Principal 
structural measures consist of six small control structures 
in the upper watershed to temporarily impound floodwaters and 
a new tunnel (part of which is being constructed on a cooperative 
basis with the Minnesota Department of Transportation) in a 
highly urbanized area of Minneapolis to replace the existing 
tunnel outletting Bassett Creek to the Mississippi River. Also 
included in the plan are a limited reach of channel widening, 
bridge removals, culvert replacements, a weir structure, a flood 
storage area, and a railroad bridge replacement. Estimated 
Federal cost (1989) for new work is $28,100,000 and $4,494,000 
is to be contributed by local interests. Project was authorized by 
the 1976 Water Resources Development Act. 
Local cooperation. See Annual Report for 1977 for requirements. 
Under current cost sharing policies, when the costs of 
lands, easements, and rights-of-way are less than 20 percent of 
total project costs, local interests are required to furnish the 
standard local cooperation requirements plus a cash contribution, 
the total of the two to amount to a minimum of 25 percent 
of the total project costs. On June 27, 1986, the City of 
Minneapolis entered into a local cooperation agreement with the 
Department of the Army. 
Operations and results during fiscal year. New Work: 
Miscellaneous lands and damages cost $20,922. A Stage 3 
construction contract cost $1,732,721. Engineering and design 
cost $299,116 by contract, and $591,893 by hired labor. Supervision 
and administration and other miscellaneous costs were 
$238,558. 
Condition at end of fiscal year: Construction of the first 
control structures is complete. The Minnesota Department of 
Transportation (MnDOT) has completed construction of the 
downstream portion of the tunnel including the last 4,800 feet 
and outlet to the Mississippi River. The amount of $3,642,888 
was reimbursed to MnDOT for the Federal share of the work. 
Construction work is currently underway on the tunnel segment 
located in sandstone (Stage 3). 
8. BIG STONE LAKE AND WHETSTONE 
RIVER, MN AND SD 
Location. On Minnesota River near Ortonville and Odessa, 
MN, and Big Stone City, SD, at the outlet of Big Stone Lake and 
in Big Stone and Lac qui Parle Counties, MN, and Grant County, 
SD. (For general location, see Geological Survey map of 
Minnesota.) 
Existing project. Provides for a dam and reservoir on 
Minnesota River above U.S. Highway 75, modification of Big 
Stone Lake outlet dam and silt barrier, bank stabilization along 
lower reach of Whetstone River, channel improvement on 
Minnesota River for 3 miles below outlet control dam at Big 
Stone Lake along with necessary relocations and acquisition of 
lands. These improvements would be made for wildlife conservation 
and development, flood control, and recreation. For 
additional details see Annual Report for 1970. Project was 
authorized by 1965 Flood Control Act (H. Doc. 579, 87th Cong., 
2d sess., contains latest map; and H. Dec. 193, 88th Cong., 2d 
sess.). 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Structure was operated and maintained and inspections and 
evaluations performed at a cost of $77,466 by hired labor and 
$8,000 by other Corps. Data collection and water control 
analysis cost $25,166 and $18,134, respectively. Data collection 
by other government agencies cost $22,400. Real estate 
management by the North Central Division cost $513. Engineering 
and design and supervision and administration cost 
$3,549 and $40,687, respectively. 
Condition at end of fiscal year: Construction of the project 
is complete. A general plan between the Secretary of the Army 
and the Secretary of the Interior for administrating the use of 
waters, land, or interests therein has been consummated, and a 
cooperative agreement between the Corps of Engineers and the 
U.S. Fish and Wildlife Service was approved. On March 31, 
1975, the Secretary of the Army transferred lands in the project 
not required for Corps of Engineers operation and maintenance 
to the Department of Interior. The transfer of property was 
accepted by the Department of the Interior on May 21, 1975. 
The project was transferred to the Upper Minnesota River 
Watershed District for operation and maintenance. 
9. CANNON RIVER AT FARIBAULT, MN 
Location. The project site is located along the left bank of 
the Cannon River, about 5 miles north of Faribault, Minnesota, 
in southeastern Minnesota. 
Existing project. The plan consists of protecting approximately 
440 feet of shoreline with riprap and clearing fallen trees 
from the channel at the erosion site. A minimum of 8 feet would 
be maintained between the edge of the road surface and the edge 
of the riverbank. The bank would be shaped and filled with 
pervious fill to a 1 vertical on 2.5 horizontal slope. The bank 
would be protected with 12 inches of riprap and 6 inches of 
bedding above the water level. A guardrail would be installed as 
an additional measure to protect the public safety. 
The project was approved for construction by the Chief of 
Engineers on August 19, 1988. The project is being constructed 
24-4

ST. PAUL, MINNESOTA DISTRICT 
under the authority of Section 14 of the 1946 Flood Control Act, 
as amended. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local cooperation agreement was signed by Rice 
County, Minnesota in August 1988. 
Operation and results during fiscal year. New work: A 
construction contract cost $42,959. Engineering and design and 
supervision and administration cost $624 and $2,561, respectively. 
Condition at end of fiscal year: Construction was completed 
in the summer of 1989. 
10. CHASKA, MN 
Location. In Carver County in south-central Minnesota on 
the Minnesota River. (For general location, see Geological 
Survey map of Minnesota.) 
Existing project. The plan of improvement consists of a 
levee and interior drainage works along the Minnesota River, 
flood diversion channels on Chaska Creek and East Creek, and 
appropriate floodplain regulation measures. Principal project 
features include: approximately 1.1 miles of upgraded levee, 
1.5 miles of new levee, and one pumping station on the Minnesota 
River; 1.1 miles of diversion channel on Chaska Creek; and 
0.6 mile of diversion channel and 0.3 mile of channel improvement 
on East Creek. Approximately 2.9 miles of paved recreation 
trails on top of the levee and around Courthouse Lake are 
also included in the proposed plan. Estimated Federal cost 
(1989) for new work is $21,400,000 and $2,637,000 is to be 
contributed by local interests. Project was authorized by the 
1976 Water Resources Development Act. (H. Doc. 644, 94th 
Congress, 2d sess., contains latest published map.) 
Local cooperation. See Annual Report for 1977 for requirements. 
A local cooperation agreement was executed on September 
12, 1988. The agreement included cost sharing provisions in 
accordance with the 1986 Water Resources Development Act. 
Operations and results during fiscal year. New Work: 
Real Estate cost $14,096. Stage 1 construction contract cost 
$3,500. Engineering and design cost $2,565 by contract and 
$762,688 by hired labor. Supervision and administration cost 
$108,663. 
Condition at end of fiscal year: A contract for Stage 2 of the 
flood control project was awarded in September, 1989. Stage 1 
construction is complete. 
11. DEVILS LAKE, ND 
Location. In Ramsey County in north central North Dakota 
about 80 miles west of Grand Forks, North Dakota. (For general 
location, see Geological Survey map of North Dakota.) 
Existing project. Involves a system of levees and interior 
flood control facilities at the head of Creel Bay. The main 
embankment across Creel Bay is 1,810 feet long and varies from 
0 to 27 feet high. The south Creel Bay tieback embankment is 
1,030 feet long and varies from 0 to 3 feet high. The north Creel 
Bay tieback embankment is 2,400 feet long and varies from 0 to 
8.5 feet high. The south embankment is 3,100 feet long and 
varies from 0 to 9.5 feet high. 
The interior flood control system consists of temporary 
stormwater retention ponds immediately north and south of the 
city's sewage lagoons, a 16,000 gallon per minute pumping 
station and a system of ditches and culverts linking the ponds to 
the pumping station. 
The project was approved by the Chief of Engineers for 
construction August 15, 1983, under the authority contained in 
Section 205 of the 1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1983 for requirements. 
A local assurance agreement required by Public Law 91- 
611 was adopted by the city of Devils Lake in August 1983. 
Operations and results during fiscal year. New Work: 
Construction contracts cost $954. Engineering and design cost 
$30,821 by hired labor. Supervision and administration costs 
were $7,128. 
Condition at end of fiscal year. Construction work on the 
project is substantially complete. 
12. EAU GALLE RIVER, WI 
Location. At and in vicinity of Spring Valley, WI, on Eau 
Galle River 30 miles above its mouth at Chippewa River, and its 
tributary, Mines Creek, which flows through the village. Spring 
Valley is about 45 miles east of St. Paul, MN, and 36 miles west 
of Eau Claire, WI. (See Geological Survey map for Wisconsin 
for general location.) 
Existing project. Authorized plan of improvement as 
modified by further studies includes a retarding dam and reservoir 
on Eau Galle River immediately upstream from Spring 
Valley, and remedial works on Mines Creek including channel 
enlargement, a low levee, and a drop structure. Project provides 
for earth and rock-fill dam, an uncontrolled outlet and an uncontrolled 
spillway emerging above Mines Creek. See page 1030 of 
Annual Report for 1965 for further details. Proposed improvements 
on Burghardt Creek were eliminated. Improvements 
provide complete protection near Spring Valley for standard 
project flood, and below that point in decreasing value in 
proportion to distance from reservoir. Permanent conservation 
pool will serve a local need for a recreational area. Project was 
authorized by 1958 Flood Control Act (S. Doc. 52, 84th Cong., 
1st sess., contains latest published map.) 
Local cooperation. Fully complied with. See page 1083 of 
Annual Report for 1967. 
Operations and results during fiscal year. Maintenance: 
Structure and recreation facilities were operated and maintained, 
and inspections, investigations and evaluations were 
performed at a cost of $267,848 by hired labor and $65,347 by 
contract. Real estate management cost $2,121. Data collection 
cost $3,456 by hired labor and $8,500 by other government 
24-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
agencies. Water control analysis and water quality by other 
Corps of Engineer districts cost $7,985 and $138,249, respectively. 
Administrative and other miscellaneous costs were 
$98,138. 
Condition at end of fiscal year: Mines Creek improvements 
were substantially completed in 1964; minor work was accomplished 
in 1966. A contract for dam, spillway, and discharge 
channel, started July 1, 1965, was completed in October 1968. 
Recreational facilities have been provided. Remedial work to 
repair eroded gutters and road ditches was completed in September 
1973. Repair of failing discharge conduit by installing a 
steel liner was completed in April 1982. 
13. EMERSON, MANITOBA-NOYES, MN 
Location. The unincorporated village of Noyes is located in 
Kittson County in extreme northwestern Minnesota about 80 
miles north of Grand Forks, North Dakota. Noyes is situated on 
the right overbank of the Red River of the North, approximately 
one-half mile from the channel. 
Existing project. The project will consist of a "ring" levee 
which will protect both Noyes and the city of Emerson, Manitoba, 
Canada. The project will have three basic components: 
upgrading the existing Emerson, Manitoba, emergency levee to 
provide 100-year flood protection; constructing a 3,800-footlong 
levee at Noyes, Minnesota, to provide 100-year flood 
protection; and constructing a 2,000-foot-long International 
levee in Minnesota which will run parallel to the International 
boundary. The levees will provide a complete and continuous 
levee system around the two communities. The levees will have 
a 10-foot top width, side slopes of 1 vertical on 3 horizontal, and 
vary in height from 7 to 12 feet. The interior flood control 
facilities consist of one ponding area and two gravity outlets. 
The project was approved by the Chief of Engineers for construction 
on July 26, 1988, under the authority contained in 
Section 205 of the 1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local cooperation agreement was signed by St. Vincent 
Township, Minnesota, the local sponsor, in August 1988. 
Operations and results during fiscal year. New Work: A 
construction contract cost $313,001. Engineering and design 
cost $7,050. Supervision and administration cost $16,020. 
Condition at end of fiscal year: The contract for construction 
of the flood control project at Noyes was 95 percent complete in 
September 1989. 
14. ENDERLIN, MAPLE RIVER, ND 
Location. In Ransom County in southeastern North Dakota 
on the Maple River about 45 miles southwest of Fargo, North 
Dakota. (For general location, see Geological Survey map of 
North Dakota.) 
Existing project. The project at Enderlin involves a system 
of levees along the right bank of the main stem and the left bank 
of the South Branch of the Maple River. The total levee system 
would be about 1.2 miles long and would have an average height 
of about 8 feet. Other features of the project include channel 
improvements on the south branch, replacement of the Soo Line 
railroad bridge, and interior drainage facilities consisting of 
three ponding areas with gated outlet conduits. To prevent 
failure of the channel and levee by erosion, rip-rapping is 
provided in selected reaches. 
The project was approved by the Chief of Engineers for 
construction August 11, 1982, under the authority contained in 
Section 205 of the 1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1982 for requirements. 
Alocal assurance agreement required by Public Law 91- 
611 was adopted by the city of Enderlin in July 1982. 
Operations and results during fiscal year. New Work: 
Engineering and design by hired labor cost $9,208. Supervision, 
administration and other miscellaneous costs were $751. 
Condition at end of fiscal year: Construction of the project 
is substantially complete. 
15. GRAFTON PUMPING STATION, ND 
Location. The project site is located in an unincorporated 
area of Walsh County, North Dakota. The erosion site is on the 
left bank of the Red River of the North immediately downstream 
of the County Highway 17 bridge which is 10 miles east of 
Grafton. 
Existing project. The project to protect the streambank 
from erosion that is threatening the City of Grafton's water 
supply intake facility was authorized under Section 14 of the 
1946 Flood Control Act, as amended. The initial appraisal 
report was dated January 1988. The recommended plan consists 
of reshaping the existing bank and placing 1,200 cubic yards of 
riprap along approximately 250 feet of the riverbank to protect 
the city's pumping station from further erosion. The project was 
approved for construction by the Chief of Engineers on August 
18, 1988. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local cooperation agreement was signed by the City of 
Grafton, North Dakota in August 1988. 
Operations and results during fiscal year. New Work: A 
construction contract cost $56,729. Engineering and design cost 
$1,003. Supervision and administration costs were $2,473. 
Condition at end of fiscal year: A construction contract for 
slope protection was awarded on September 29, 1988. 
16. HOMME LAKE AND DAM, ND 
Location. Dam is on South Branch of Park River about 4 
miles upstream from Park River, ND, and 62.1 miles above 
mouth of Park River. South, Middle, and North Branches, 
headwater streams of Park River, rise in Cavalier County in 
northeastern North Dakota and flow easterly to an almost 
common confluence near Grafton, ND, forming main stream 
which flows easterly 35 miles to join Red River of the North 
24-6

ST. PAUL, MINNESOTA DISTRICT 
about 35 miles south of the international boundary. (For general 
location, see Geological Survey map of North Dakota.) 
Existing project. See Annual Report for 1962. Project was 
authorized as Park River Reservoir by 1944 Flood Control Act 
(S. Doc. 194, 78th Cong., 2d sess.), and redesignated Homme 
Reservoir and Dam by Public Law 435, 80th Congress, 2d 
session. Latest published map is in project document. 
Local cooperation. Fully complied with. Total costs for all 
requirements of local cooperation under terms of project authorization, 
including required non-Federal contributions, were 
$62,800. In addition, local interests contributed $16,220 for 
construction of a water supply outlet through dam and incurred 
other costs of $19,600. 
Operations and results during fiscal year. Maintenance: 
Structure was operated and maintained, and inspections and 
evaluations performed at a cost of $82,812. 
Condition at end of fiscal year: Project completed in June 
1956 except for additional recreational facilities which have 
been done intermittently since that time. Construction began in 
April 1948 and major structures completed in May 1951. Structures 
are in good condition. Government has acquired 395 acres 
of land in fee and easements over 7.8 acres of land for project. 
An additional 6.3 acres of land have been donated for recreational 
development and 3.75 acres have been acquired due to 
bank erosion bordering the project. 
17. HOUSTON, MN 
Location. In Houston County in southeastern Minnesota on 
the Root River in the city of Houston, Minnesota. 
Existing project. The plan of protection provides levee 
flood protection together with appropriate floodplain regulation 
measures. Main features of the project include 3.1 miles of 
levee, 0.2 miles of road raise, an interior drainage pumping 
station, and road and rail closures. Estimated Federal cost 
(1989) for new work is $5,620,000 and $1,772,000 is to be 
contributed by local interests. The project was approved for 
construction by the 1986 Water Resources Development Act 
(Public Law 99-662) and is being reevaluated based on changes 
since the 1975 Feasibility Report. 
Local cooperation. See Annual Report for 1988 for requirements. 
During reevaluation of the project, the items of local 
cooperation will be modified to reflect current cost sharing 
requirements. 
Operations and results during fiscal year. New Work: 
Preconstruction planning continued at a cost of $222,100. 
Condition at end of fiscal year: General Reevaluation study 
was initiated in January 1987 to reevaluate the feasibility of the 
authorized project based on changes in existing conditions, 
public views, and design criteria since completion of the feasibility 
report in 1975. In coordination with the city of Houston, 
the state of Minnesota Department of Natural Resources and the 
Department of Transportation, a flood control plan has been 
identified and a report is being prepared recommending the plan 
for design studies. 
18. LAC QUI PARLE LAKES, 
MINNESOTA RIVER, MN 
Location. Works covered by this project lie along Marsh 
Lake and Lac qui Parle and the Minnesota River between head 
of Marsh Lake and Granite Falls, MN. (For general location, see 
Geological Survey map of Minnesota.) 
Existing project. See Annual Report for 1962. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Project was operated and maintained, and inspections and evaluations 
were performed at a cost of $178,371 by hired labor, 
$30,607 by contract, and $-549 by other Corps districts. Dam 
failure planning cost $2,227 by hired labor. Reservoir operations 
planning evaluation cost $25,116 by hired labor. Data 
collection cost $8,605 by hired labor and $47,340 by U.S. 
Geological Survey. Water control analysis cost $42,002. Real 
estate cost $7,491. Water control operating equipment cost 
$49,860 and for the U.S. Geological Survey $17,420. Engineering 
and design and supervision and administration cost $33,361 
and $78,862, respectively. 
Condition at end of fiscal year: Project has been operated by 
the Government since transfer from State of Minnesota to the 
United States in September 1950. The United States owns fee 
title to 517.62 acres of land and easements on 19,859.47 acres of 
land. In 1957, 60.1 acres were withdrawn from public lands for 
use by the Department of the Army. Land acquisition is 
complete. Construction under present plan of improvement was 
started in September 1941 and completed in December 1951 
except for recreational facilities. All structures are in good 
condition. 
19. LA FARGE LAKE AND CHANNEL 
IMPROVEMENT, WI 
Location. On the Kickapoo River which rises in Monroe 
County in southwestern Wisconsin and flows south and southwest 
through Vernon, Richland, and Crawford Counties emptying 
into Wisconsin River about 16 miles above junction of latter 
stream with Mississippi River. (For general location see Geological 
Survey map of Wisconsin.) 
Existing project. Provides for a dam and impoundment of 
the Kickapoo River about 1 mile upstream from village of La 
Farge, operated for flood control, fish and wildlife conservation, 
general recreation, and a reduction ofaggradation downstream 
from the dam, and supplemental protection at Soldiers Grove 
and at Gays Mills by means of levees, supplementary channel 
improvement, and interior drainage facilities. See Annual 
Report for 1975 for details. 
Estimated Federal cost (1976) for new work is $55,400,000. 
Project was authorized by 1962 Flood Control Act (H. Doc. 557, 
87th Cong., 2d sess., contains latest published map.) 
Local cooperation. None required for construction of La 
Farge Lake. See Annual Report for 1967 for requirements for 
24-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
local protection works. Local interests have not been requested 
to furnish assurances. 
Operations and results during fiscal year. Maintenance: 
Project was operated and maintained at a cost of $16,300. 
Condition at end of fiscal year: General and Real Estate 
design memorandums and detailed plans for the La Farge Dam 
and spillway and for relocations have been completed. Land 
acquisition negotiations began in December 1968. The first land 
payment was made on January 15,1969, and the land acquisition 
program is 80 percent complete. Contracts for excavation of the 
left abutment, for test wells, and for construction of the outlet 
works and right abutment have been completed. A study of 
alternatives has been completed. All further construction has 
been indefinitely suspended. Work has been accomplished to 
provide for completion of relocation work left partially completed 
when construction was suspended. Soldiers Grove has relocated 
out of the floodplain area after receiving funds from 
other agencies. A study of a modified dry dam was completed 
in early FY 1985. On the basis of the study results, it was 
recommended that no further work be done to establish the 
economic feasibility of a dry or wet dam at La Farge and that the 
La Farge Lake and channel improvement project be deauthorized. 
20. LAKE ANDRUSIA, MISSISSIPPI RIVER, 
MN 
Location. On the left bank of the Mississippi River, between 
Andrusia Lake and Allen's Bay of Cass Lake, about 5 miles 
north of the city of Cass Lake, in the southeastern corner of 
Beltrami County, which is in north-central Minnesota. 
Existing project. The project to protect the streambank 
from erosion that is destroying a prehistoric cemetery and a 
historic and prehistoric habitation site was authorized under 
Section 14 of the 1946 Flood Control Act, as amended. The 
initial appraisal report, dated June 1986, recommended placing 
a 2-foot-thick blanket of random fill to protect the burial site 
from construction activities, placing granular fill and shaping 
520 feet of the riverbank to a 1 vertical on 2.5 horizontal slope, 
and protecting the area with 9 inches of bedding and 18 inches 
of graded riprap. The project was approved for construction by 
the Chief of Engineers on October 26, 1987. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local cooperation agreement was signed by the 
Beltrami Soil and Water Conservation District in November 
1987. 
Operations and results during fiscal year. New Work: An 
adjustment of $-1,668 was made based on an audit of final 
project costs. 
Condition at end of fiscal year: Construction was complete 
and final contract payment made in July 1988. Project was 
transferred to Beltrami Soil and Water Conservation District by 
letter dated February 15, 1989. 
21. LAKE ASHTABULA AND BALDHILL 
DAM, SHEYENNE RIVER, ND 
Location. Baldhill Dam is on the Sheyenne River, 16 miles 
upstream from Valley City, ND, and about 271 miles above 
mouth. Sheyenne River rises in central North Dakota and flows 
500 miles generally southeast to enter Red River of the North 
about 10 miles north of Fargo, ND. (For general location see 
Geological Survey map of North Dakota.) 
Existing project. See Annual Report for 1962. Project was 
authorized by Flood Control Act of 1944 (S. Doc. 193, 78th 
Cong., 2d sess., contains latest published map). Reservoir above 
Baldhill Dam was designated as Lake Ashtabula by Public Law 
772, 81st Congress, 2d session. 
Local cooperation. See Annual Report for 1962. Complied 
with except for construction of Fargo diversion dam and ditch 
for which assurances furnished by city of Fargo were approved 
by the Secretary of War on June 26, 1947. Necessity for this 
feature will be reviewed. 
Operations and results during fiscal year. Dam Safety: 
Cultural resources costs by hired labor were $1,640. Engineering 
and design cost $121,270 by contract, $352,070 by hired 
labor, and $54,974 for a Waterways Experiment Station model 
study. Administrative costs were $24,717. Maintenance: Project 
was operated and maintained, and inspections, investigations, 
monitoring and evaluations were performed at a cost of 
$429,366 by hired labor and $8,863 by contract. Real estate 
management cost $22,594. Data collection cost $6,513 by hired 
labor and $73,541 by other government agencies. Water control 
analysis by hired labor cost $16,566. Dam safety engineering 
and design cost $14,037 by hired labor, and $475 by Fish and 
Wildlife Service. A privy and shower cost $44,357 by hired 
labor and $29,918 by contract. Administrative and engineering 
and design costs were $112,605 and $3,163, respectively. 
Condition at end of fiscal year: Project completed in March 
1956 except construction of recreational facilities which is 
being accomplished intermittently. United States owns 7,816.5 
acres of land in fee and easements on 666.2 acres. Construction 
initiated in July 1947 and major features completed in November 
1950. Dam was placed in permanent operation in spring of 
1951. Structures are in good condition. Baldhill Dam has been 
classified as a large, high hazard dam under the National 
Program for the inspection of dams. A risk assessment report 
prepared in June 1986 indicated a serious spillway discharge capacity 
deficiency. A General Design Memorandum which 
recommended increasing the spillway capacity was approved by 
OCE in July 1987. 
22. LAKE PULASKI, WRIGHT COUNTY, 
MN 
Location. Lake Pulaski is approximately 45 miles northwest 
of the Twin Cities of Minneapolis and St. Paul, Minnesota. 
24-8

ST. PAUL, MINNESOTA DISTRICT 
It lies within three local political jurisdictions (City of Buffalo, 
Wright County and Buffalo Township). 
Existing project. Lake Pulaski has no natural outlet. Prior 
to construction of this project, the lake had been rising, inundating 
a number of houses or summer residences. A combination 
of a pumped pipeline and gravity-flow storm sewers to convey 
excess water through the city of Buffalo from Lake Pulaski to 
Buffalo Lake was constructed to stabilize the lake. Included in 
this project was a storm sewer upgrade which was constructed by 
the city of Buffalo. The lake will be maintained at elevation 
966.0 feet mean sea level. This is the lowest level permitted for 
an artificial outlet under State of Minnesota rules governing 
landlocked lakes. The project was approved by the Chief of 
Engineers for construction in March 1985 under the authority 
contained in Section 205 of the 1948 Flood Control Act, as 
amended. 
Local cooperation. See Annual Report for 1986 for requirements. 
A local assurance agreement was adopted by the Lake 
Pulaski Improvement District, the local sponsor, in August 
1986. 
Operations and results during fiscal year. New Work: A 
construction contract cost $15,753. Supervision and administration 
costs were $9. 
Condition at end of fiscal year: Construction is essentially 
complete. 
23. LAKE TRAVERSE AND BOIS DE 
SIOUX RIVER, SD AND MN 
Location. Works covered by this project lie along Lake 
Traverse and Bois de Sioux River between upper end of Lake 
Traverse at Browns Valley, MN, and the mouth of Bois de Sioux 
River at Breckenridge, MN. Lake drains through river to Red 
River of the North, and two waters form a portion of boundary 
between State of Minnesota and States of North and South 
Dakota. (For general location, see Geological Survey map of 
Minnesota.) 
Existing project. See Annual Report for 1962. Existing 
project was authorized by Flood Control Act of June 22, 1936. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Project and related facilities were operated and maintained, and 
inspections and evaluations performed at a cost of $348,094. 
Condition at end of fiscal year: Existing project was completed 
in June 1948, except for minor recreational facilities. Fee 
title to 1,144.13 acres and easements on 6,172.25 acres of land 
have been acquired. White Rock Dam and Reservation control 
structures are in operation, and structures and appurtenances are 
in good condition. Remedial work for repair of apron at White 
Rock Dam was completed in November 1968. Roadways across 
structure are open to public travel. 
24. MANKATO AND NORTH MANKATO, MN 
Location. Along Minnesota River between miles 103.5 and 
109.5 near Mankato, North Mankato, and Le Hillier, in southcentral 
Minnesota. (For general location see Geological Survey 
map of Minnesota.) 
Existing project. As modified as a result of severe 1965 
flood, provides for protection of communities of Mankato, 
North Mankato, and Le Hillier by means of levees and floodwalls 
with pumping plants and interior drainage facilities. See page 
1090 of Annual Report for 1967 for further details. Additional 
channel improvement, levees, pumping, and interior drainage 
features have been included in the Mankato unit of the project 
for protection from the high flows of Indian Creek. Expansion 
of Indian Creek improvements were made during detailed studies 
as a result of updated hydrologic data. Highway bridge 
relocations made necessary by the project have been authorized 
at Federal expense. Project was authorized by 1958 Flood 
Control Act (H. Doc. 437, 84th Cong., 2d sess., contains latest 
published map.) Project was modified by 1965 Flood Control 
Act, and by the Water Resources Development Acts of 1974 and 
1976. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Construction of 
the T.H. 169 Bridge relocations was completed. Construction 
costs for improvements at Mankato were $1,133,524, at North 
Mankato were $12,590 and at Le Hillier were $958,108. Engineering 
and design by contract cost $95,356 and by hired labor 
cost $19,689. Real Estate cost $-218,455. Supervision and 
administration cost $70,215 by hired labor and $65,690 by 
contract. Other miscellaneous costs were $2,858. 
Condition at end of fiscal year: Construction of the project 
is complete. 
25. MARSHALL, MN 
Location. In Lyon County in southwestern Minnesota along 
the Redwood River about 68 miles above its confluence with the 
Minnesota River at the city of Marshall, Minnesota. (For 
general location see Geological Survey map for Minnesota.) 
Existing project. See page 1059 of Annual Report for 1964 
for completed channel improvement project authorized by 1960 
Flood Control Act. Federal costs amounted to $1,802,866. The 
existing flood control project was completed in 1963. In 
response to a need for additional flood control, a feasibility study 
was completed in 1979. The project recommended in the 
feasibility report was authorized by the Water Resources Development 
Act of 1986, Public Law 99-662, Section 401(a). Improvements 
include 4.7 miles of additional levees, 3.8 miles of 
bank protection, 0.3 mile of new high-flow diversion channel, an 
interbasin overflow structure, modifications to the existing diversion 
and drop structures, and a recreation plan. The recrea- 
24-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
tion plan consists of 2.5 miles of biking/walking trail, five miles 
of cross-country skiing/hiking trail, and related picnic and rest 
area facilities. The project would provide protection against a 
flood having an occurrence interval of about once in 115 years. 
Estimated Federal cost (1989) for new work is $5,150,000 and 
$1,065,000 is to be contributed by local interests. 
Local cooperation. Fully complied with for completed 
work. Project was transferred to local interests on December 23, 
1963. 
For new work, see Annual Report for 1985 for requirements. 
By letter dated November 19, 1986, the city of Marshall indicated 
its willingness to participate financially in construction of 
a project consistent with the cost sharing and financing concepts 
reflected in the 1986 Water Resources Development Act. 
Operations and results during fiscal year. New Work: 
Preconstruction planning was continued at a cost of $33,569. 
Condition at end of fiscal year: Construction of completed 
work was initiated August 1962 and completed December 1963. 
Preconstruction planning for the new work is in progress. 
26. MIDDLE RIVER AT ARGYLE, MN 
Location. In Marshall County in northwestern Minnesota 
on the Middle River within the city limits of Argyle, Minnesota. 
Existing project. The plan of protection includes a system 
of levees, road raises along with interior drainage facilities to 
provide main developed parts of the city of Argyle with one 
percent chance flood protection. Also included is the evacuation 
of 12 residences which are located outside of the line of flood 
barrier protection. The project was approved for construction on 
August 1, 1985 by the Chief of Engineers. The project is being 
constructed under the authority of Section 205 of the 1948 Flood 
Control Act, as amended. 
Local cooperation. See Annual Report for 1985 for requirements. 
A local assurance agreement required by Public Law 91- 
611 was adopted by the city of Argyle in August 1985. 
Operations and results during fiscal year. New Work: 
Real estate costs were $1,489 by hired labor. Engineering and 
design cost $60,836 by hired labor. Supervision and administration 
costs were $15,425. 
Condition at end of fiscal year: Construction contract for 
Stage I is complete. A Stage II construction contract was 
awarded in September 1989. The evacuation of the 12 residences 
is complete. 
27. MINNESOTA RIVER AT 
HENDERSON, MN 
Location. In Sibley County in southeastern Minnesota 
about 50 miles southwest of Minneapolis, Minnesota. (For 
general location, see Geological Survey map of Minnesota.) 
Existing project. The project at Henderson involves a 
system of levees to protect the flood prone areas of the city from 
floods on the Minnesota River. The proposed levee is about 1.6 
miles long and has an average height of 15 feet. Appurtenant 
interior flood control facilities include a system of interceptor 
stormsewers and ditches, and two ponding areas each with a 
gravity outlet and a pumping station designed to discharge 
impounded storm water during flood periods when exterior 
flood levels would require the gravity outlets to be closed. 
Provisions for the temporary closure of two state highways and 
a county highway are also included as project features. Total 
Federal cost (1989) of the project is estimated at about $1,500,000. 
The project was approved by the Chief of Engineers for construction 
June 26, 1987, under the authority contained in Section 
205 of the 1948 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local assurance agreement was adopted by the City of 
Henderson, the local sponsor, in May 1988. 
Operations and results during fiscal year. New Work: 
Construction by contract cost $626,057. Engineering and design, 
supervision and administration and other associated costs 
were $85,959. 
Condition at end of fiscal year: Construction of the project 
was about 80 percent complete at the end of the fiscal year. 
28. PETTIBONE PARK, LA CROSSE, WI 
Location. The project site is located along Pettibone Park 
which is on Barron Island, a large island in the Mississippi River 
which forms the right bank of the main channel, directly across 
the river from La Crosse, which is located in La Crosse County, 
in southwestern Wisconsin. 
Existing project. The project to protect the streambank 
from erosion that threatened the access road to Pettibone Park 
was authorized under Section 14 of the 1946 Flood Control Act, 
as amended. The initial appraisal report was dated June 1988. 
The recommended plan consisted of placing 4,500 tons of rockfill 
along 1250 feet of the riverbank to protect the park access 
road from further erosion. The project was approved for 
construction by the Chief of Engineers on August 19, 1988. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local cooperation agreement was signed by the City of 
La Crosse, Wisconsin, in August 1988. 
Operations and results during fiscal year. New Work: A 
construction contract cost $44,680. Engineering, design and 
supervision and administration cost $2,251 and $450, respectively. 
Condition at end of fiscal year: A construction contract for 
slope protection was awarded on September 27, 1988. Construction 
was completed in November 1988 and the project was 
formally transferred to the City of La Crosse on June 22, 1989. 
29. PORTAGE, WI 
Location. In Columbia County in central Wisconsin along 
the Wisconsin River about 35 miles north of Madison, Wiscon- 
24-10

ST. PAUL, MINNESOTA DISTRICT 
sin. (For general location see Geological Survey map for 
Wisconsin.) 
Existing project. The recommended plan provides for 
improvement to the existing levee system along the left bank of 
the Wisconsin River at Portage. The plan includes 2.9 miles of 
existing levee improvement; 550 feet of flood wall; rehabilitation 
of the Portage lock gate as a flood barrier while retaining its 
intrinsic historic value; interior flood control facilities; and 
recreational and aesthetic facilities. The project would protect 
against a flood having an occurrence interval of about once in 
500 years. Estimated Federal cost (1989) for new work is 
$5,330,000 and $1,222,000 is to be contributed by local interests. 
Project was authorized by the Water Resources Development 
Act of 1986 (Public Law 99-662). 
Local cooperation. Local interests are required to provide 
the entire cost of lands, easements, and rights-of-way necessary 
for construction of the project and make a cash contribution to 
increase their share to 25 percent of total project costs for flood 
control. In addition, local interests are to provide the necessary 
lands for recreation development, subject to the condition that, 
where the appraised value of those lands is less than 50 percent 
of the total first cost of recreation development, a cash contribution 
will be made to bring the non-Federal share to at least 50 
percent of the total first cost of recreation development. By 
letter dated July 14, 1988, the city of Portage indicated a 
willingness and intention to meet the requirements of local 
cooperation for flood control and recreation. Formal assurances 
will be requested prior to initiation of construction. 
Operations and results during fiscal year. New Work: 
Preconstruction planning was continued at a cost of $280,668. 
Condition at end of fiscal year: Preconstruction planning is 
in progress. 
30. PRAIRIE DU CHIEN, WI 
Location. In Crawford County in southwestern Wisconsin 
on the left bank of the Mississippi River. (For general location, 
see Geological Survey map of Wisconsin.) 
Existing project. Combines total evacuation with flood 
proofing and land use control measures to provide the reduction 
of potential flood damages within design limits. Evacuation was 
accomplished by purchase and relocation of structures in lowest 
portions of the floodplain. Project was authorized by Water 
Resources Development Act of 1974. 
Local cooperation. See Annual Report for 1974 for requirements. 
A local assurance agreement in accordance with Section 
221 of the Flood Control Act of 1970 was entered into with the 
city of Prairie du Chien on May 2, 1978, and signed by the Chief 
of Engineers on September 11, 1978. 
Operations and results during fiscal year. New Work: 
Adjustment in project costs was made for $-69,891. 
Condition at end of fiscal year: Project was completed in 
September 1984. 
31. RED LAKE RIVER, MN, INCLUDING 
CLEARWATER RIVER, MN 
Location. Works covered by this project lie along upper 
reach of Red Lake River and also along Clearwater River, a 
tributary of Red Lake River, between a point near Plummer, 
MN, and a point just above the mouth of Ruffy Brook. Red Lake 
River, principal tributary of the Red River of the North, has its 
source at the outlet of Lower Red Lake in northwestern portion 
of Minnesota and flows westerly about 196 miles to its junction 
with Red River of the North at East Grand Forks, MN. Clearwater 
River has a general westerly course from its source near Ebro, 
MN, about 205 miles to its junction with Red Lake River at Red 
Lake Falls, MN. (For general location, see Geological Survey 
map of Minnesota.) 
Existing project. See Annual Report for 1962. Project was 
authorized by 1944 Flood Control Act (H. Doc. 345, 78th Cong., 
1st sess., contains latest published map.) 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Structures were operated and maintained and inspections and 
evaluations performed at a cost of $154,746. 
Condition at end of fiscal year: Construction of major 
improvements on Red Lake River and the Clearwater River 
were completed in June 1956. Replacement of rock and brush 
dam on Red Lake River at Indian boundary with a concrete 
structure and appurtenant work was completed in June 1959 to 
restore marshes in the area to better wildlife conditions. Construction 
of a bridge on Clearwater Road was completed by the 
Indian Service in July 1965. A contract for improvements on 
Red Lake River was completed in November 1966, and a 
contract for restoration of water levels in Red Lake River 
marshes was completed in November 1968. Operation of Red 
Lake Dam was assumed by the Corps on April 1, 1951. Channels 
are in good condition and indicate effectiveness of project as a 
flood control measure. 
32. RED LAKE RIVER AT GENTILLY, MN 
Location. The project site is located on the left bank of the 
Red Lake River in northwestern Minnesota about 1.5 miles west 
of Gentilly and 6 miles east of Crookston, the county seat of Polk 
County. 
Existing project. The project to protect the streambank 
from erosion that is threatening Polk County State Aid Highway 
11 and bridge was authorized under Section 603 of the Water 
Resources Development Act of 1986 (Public Law 99-662). The 
plan of improvement recommended in the project report dated 
May 1989 consists of stabilizing approximately 1200 feet of 
riverbank by slope reshaping and the placement of riprap. Based 
on the recommendation contained in the report, the project was 
approved for construction by the Chief of Engineers on August 
22, 1989. 
24-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. A local cooperation agreement between 
the Department of the Army and the Red Lake Watershed 
District, the local sponsor of the project was fully executed on 
September 5, 1989. In accordance with the agreement, the local 
sponsor is required to provide during the period of construction, 
a cash contribution of at least 5 percent of total project costs and 
any additional funds needed to make its total contribution, 
including the value of all required local responsibilities, equal to 
25 percent of the total project costs; provide without cost to the 
United States all lands, easements, and rights-of-way, including 
suitable borrow and dredged material disposal areas necessary 
for construction, operation and maintenance of the project; 
perform all relocations and alterations of buildings, utilities 
(other than those portions which pass under or through the 
project structures), highways, railroads, bridges (other than 
railroad bridges and approaches thereto), sewers and related and 
special facilities determined by the Government to be necessary 
for construction of the project; pay all costs in excess of the 
Federal statutory limitation of $500,000; hold and save the 
United States free from all damages arising from construction, 
operation and maintenance of the completed project, except for 
damages due to the fault or negligence of the Government or its 
contractors; comply with the provisions of the Uniform Relocation 
Assistance and Real Property Acquisition Policies Act of 
1970, Public Law 91-646, approved January 2, 1971, in acquiring 
lands, easements, and rights-of-way for construction and 
subsequent operation of maintenance of the project, and inform 
all affected persons of applicable benefits, policies, and procedures 
in connection with said Act; operate, maintain, replace, 
and rehabilitate the project upon completion in accordance with 
regulations or directions prescribed by the Government; give the 
Government a right to enter, at reasonable times and in a 
reasonable manner, upon land which it owns or controls for 
access to the project for the purpose of inspection, and, if 
necessary, for the purpose of completing, operating, maintaining, 
repairing, rehabilitating, or replacing the project; and comply 
with all applicable Federal and state laws and regulations, 
including section 601 of Title VI of the Civil Rights Act of 1964 
(Public law 88-352) and Department of Defense Directive 
5500.11 issued pursuant thereto and published in Part 300 of 
Title 32, Code of Federal Regulations, as well as Army Regulation 
600-7, entitled "Nondiscrimination of the Basis of Handicap 
in Programs and Activities Assisted or conducted by the 
Department of the Army." 
Operations and results during fiscal year. New Work: 
Engineering and design costs were $84,216. 
Condition at end of fiscal year: A construction contract for 
the project was awarded on September 28, 1989. 
33. RED RIVER OF THE NORTH AT 
ARGUSVILLE, ND 
Location. In Cass County in eastern North Dakota near the 
confluence of the Red River of the North and the Sheyenne River 
about 15 miles northwest of Fargo, North Dakota. (For general 
location, see Geological Survey map of Minnesota.) 
Existing project. The project involves a levee encircling the 
city of Argusville with associated interior flood control facilities. 
The total levee system is about 1.9 miles long and has an 
average height of about 8 feet. Interior flood control facilities 
consist of interceptor ditches and pipes, two temporary ponding 
areas and a pumping station to periodically discharge impounded 
water. The project was approved by the Chief of 
Engineers for construction July 5, 1985, under the authority 
contained in Section 205 of the 1948 Flood Control Act, as 
amended. 
Local cooperation. See Annual Report for 1985 for requirements. 
A local assurance agreement was adopted by the city of 
Argusville, the local sponsor, in July 1985. 
Operations at end of fiscal year. New Work: Construction 
contract cost $2,236. Engineering and design cost $12,192 by 
hired labor. Supervision and administration costs were $2,810. 
Condition at end of fiscal year: A construction contract for 
Stage 1 involving the west levee was completed in July 1986. A 
construction contract for Stage 2 involving the remainder of the 
project was awarded in August 1986 and was substantially complete 
at the end of the fiscal year. 
34. RED RIVER OF THE NORTH AT 
BRECKENRIDGE, MN 
Location. In Wilkin County in west central Minnesota on 
the Red River of the North, approximately 200 miles northwest 
of Minneapolis-St. Paul. 
Existing project. Provide for erosion control along the east 
bank of the Red River of the North adjacent to the St. Francis 
Nursing Home, a city owned facility. The project involves 
excavation and the placement of granular fill, bedding material 
and riprap along an approximate 300-foot reach of eroding riverbank. 
The project was approved by the Chief of Engineers for 
construction in September 1988 under the authority contained in 
Section 14 of the 1946 Flood Control Act, as amended. 
Local cooperation. See Annual Report for 1988 for requirements. 
A local assurance agreement was adopted by the city of 
Breckenridge, the local sponsor, in September, 1988. 
Operations and results during fiscal year. New Work: A 
construction contract cost $56,171. Engineering and design 
costs were $1,917. Supervision and administration costs were 
$1,118. 
Condition at end of fiscal year: A contract for the erosion 
control project at Breckenridge was awarded in September 
1988. Construction of the project was substantially complete at 
the end of the fiscal year. 
35. RED RIVER OF THE NORTH DRAINAGE 
BASIN, MN, SD & ND 
Location. Red River of the North Basin, within the United 
States, includes northeastern corner of South Dakota and much 
24-12

ST. PAUL, MINNESOTA DISTRICT 
of eastern North Dakota and northwestern Minnesota. Red 
River of the North, formed by confluence of Otter Tail and Bois 
de Sioux Rivers, flows northward through this region, forming 
boundary between North Dakota and Minnesota. (For general 
location of basin, see Geological Survey maps of Minnesota and 
South Dakota.) 
Previous project. See Annual Report for 1962 for navigation 
and flood control projects in the basin, not part of this 
project. 
Existing project. Project includes improvements for local 
protection in interests of flood control and major drainage 
accomplished by channel improvement, levees, etc., in addition 
to construction of a multiple purpose reservoir on Otter Tail 
River to control floods and, in conjunction with previously 
authorized Federal reservoir project at Baldhill site of Sheyenne 
River and at Red Lake, to increase low flows for water supply 
and pollution abatement. (See table 24-I for active units in 
comprehensive basin plan.) 
Project was authorized by Flood Control Acts of 1948 and 
1950. Public Works Authorization Act, 1957, authorized Chief 
of Engineers to acquire such lands as were beyond legal authority 
of the city of Grand Forks to acquire. Section 205 of the Flood 
Control Act of 1970 provided for extension of the expiration 
date for the East Grand Forks project. Authorization of the 
Sheyenne River (Kindred Lake) project by the 1970 Flood 
Control Act provided for the deletion of channel improvement 
on the lower 48.8 miles of the Sheyenne River authorized under 
the Flood Control Acts of 1948 and 1950. Latest published map 
is in House Document 185, 81st Congress, 1st session. 
Local cooperation. See Annual Report for 1965. Following 
the flood of 1965, the city of East Grand Forks requested 
reactivation of the project and furnished a resolution adopted 
May 11, 1965, indicating its willingness to meet the requirements 
of local cooperation. Expiration date for the East Grand 
Forks project was extended to April 17, 1975, permitting local 
interests additional time to furnish assurances of local cooperation. 
A local assurance agreement was passed by the city on 
March 27, 1975, and accepted by the acting Director of Real 
Estate, OCE for the Secretary of the Army on April 9, 1975. In 
a July 9, 1986 letter, the city of East Grand Forks withdrew 
support for the project presented in the General Design Memorandum. 
Operations and results during fiscal year. Maintenance: 
Orwell Lake and Dam were operated as required and miscellaneous 
inspections, reports, and repairs were made at a cost of 
$106,396 by hired labor and $21,693 by contract. Real estate 
management cost $4,459. Miscellaneous lands and damages 
costs were $2,735. Data collection cost $7,230 by hired labor 
and $16,610 by U.S. Geological Survey. Water control and 
water quality cost $15,932 and $7,718, respectively. Engineering 
and design cost $173,968 by hired labor and $46,601 by 
contract. Supervision and administration and other miscellaneous 
costs were $60,089 and $-2,311, respectively. 
Condition at end of fiscal year: Major construction for all 
active units except for East Grand Forks, MN, is complete. The 
East Grand Forks project was reclassified from active to inactive 
status on August 19, 1988. A total of 1,985 acres of land for 
Orwell Lake and Dam is owned in fee by the United States. See 
page 1281 of Annual Report for 1962 for periods of completion 
at active units of project other than Fargo. Work at Fargo, ND, 
started in May 1959, was completed in July 1963. (See table 24- 
I at end of chapter for total costs of new work to date.) 
36. ROCHESTER, MN 
Location. In Olmsted County in southeastern Minnesota on 
the South Fork of the Zumbro River. (For general location, see 
Geological Survey map of Minnesota.) 
Existing project. Provides for stream channel modifications 
and levees functioning in combination with a system of 
seven headwaters reservoirs. Principal features, in addition to 
the reservoirs, include 0.5 mile of grass-sloped channels, 6.1 
miles of riprapped or gabion-lined channels, 0.9 mile of architecturally-
treated concrete channels, 0.5 mile of dredged channel, 
six drop structures, 2.4 miles of levee, and hiking and biking 
trails. Estimated cost (1989) to the United States for new work 
is $60,700,000 and $7,418,000 is to be contributed by local 
interests. Project was authorized by the Water Resources 
Development Act of 1986 (H. Doc. 156, 93rd Cong., 1st sess., 
contains latest published map.) 
Local cooperation. See Annual Report for 1974 for requirements. 
A local cooperation agreement was signed August 27, 
1987 by the city of Rochester. 
Operations and results during fiscal year. New Work: 
Construction contracts for Stage 1A2B, 1A1, and 1B1 were 
$1,390,521, $1,207,034 and $400,392, respectively. Engineering 
and design cost $1,746,062 by contract, $1,268,835 by hired 
labor, and $19,932 by other Corps. Real estate activities cost 
$48,008. Supervision and administration cost $380,364. 
Condition at end of fiscal year: Construction continued on 
Stages 1A2B and 1A1. A construction contract was awarded for 
Stage 1B1 in May 1989. 
37. ROSEAU RIVER, MN 
Location. In Roseau County on the Roseau River in northwestern 
Minnesota near the city of Duxby. (For general location 
see Geological Survey map of Minnesota.) 
Existing project. See Annual Report for 1988 for description 
of project as authorized by the Flood Control Act of 1965. 
The project, as modified by the Water Resources Development 
Act of 1988, provided for construction of about 6 miles of flood 
control levee approximately 3 feet high in the vicinity of Duxby, 
Minnesota. Estimated cost (1989) to the United States for new 
work on the modified project is $270,000 and $90,000 is to be 
contributed by local interests. 
Local cooperation. See Annual Report for 1968 for requirements 
of project as authorized by the Flood Control Act of 1965. 
For the modified project, local interests are required to provide 
the entire cost of lands, easements, and rights-of-way necessary 
for construction of the project and make a cash contribution to 
24-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
increase their share to 25 percent of total project costs for flood 
control. Local interests have formed the Roseau River Watershed 
District to provide local cooperation requirements and 
acquire rights-of-way. 
Operations and results during fiscal year. New Work: 
Preconstruction planning was continued at a cost of $9,193. 
Condition at end of fiscal year: Preconstruction planning is 
underway for the Duxby levee project. 
38. SHEYENNE RIVER, ND 
Location. The Sheyenne River Basin is included in 16 
counties in the southeastern portion of North Dakota and drains 
an area of 7,140 square miles into the Red River of the North near 
Fargo, North Dakota. The principal area of flood damages in the 
basin is located at the lower end within Cass County and the city 
of West Fargo. (For general location, see Geological Survey 
map of North Dakota.) 
Existing project. The project as authorized by the 1986 
Water Resources Development Act consists of three major 
components for Federal implementation: 1) 11.9 miles of levee 
and a 6.7 mile flood diversion channel at West Fargo; 2) 7.5 
miles of flood diversion channel from Horace to West Fargo; 
and 3) a five-foot raise of the Baldhill Dam flood control pool. 
The Water Resources Development Act of 1986 stipulated that 
the project shall also include a dam and reservoir of approximately 
35,000 acre-feet of storage for the purpose of flood 
protection on the Maple River. There are several items of local 
cooperation required to implement the plan, and several components 
identified for non-Federal implementation which would 
supplement the recommended plan. Estimated cost (1989) to 
the United States for new work is $40,500,000 and $3,045,000 
is to be contributed by local interests. 
Local cooperation. See Annual Report for 1988 for requirements. 
Project consists of four separable components requiring 
four Local Cooperation Agreements. The Southeast Cass Water 
Resource District will serve as the local sponsor for the West 
Fargo Unit and the Horace to West Fargo Unit. The Local 
Cooperation Agreement for the West Fargo Unit was executed 
on July 25, 1988. By letter dated April 4, 1989, the Southeast 
Cass Water Resources District indicated that it fully agrees with 
the Horace to West Fargo Unit of the project and that it has the 
financial capability to cover the local share. The State Water 
Commission will serve as the quasi-sponsor for the other components 
until a formal sponsorship is determined by benefiting 
entities. 
Operations and results during fiscal year. New Work: 
Preconstruction planning was continued at a cost of $759,579. 
Condition at end of fiscal year: Plans and specifications for 
the West Fargo and Horace to West Fargo Units are under way. 
An economic evaluation study for the Maple River Unit is in 
progress. 
39. SOURIS RIVER BASIN, ND 
Location. On the Souris River in Ward, Renville, McHenry, 
and Bottineau Counties in northwestern North Dakota. The 
existing Lake Darling Dam is located about 20 miles northwest 
of Minot, North Dakota. The project also includes features at the 
communities of Sawyer and Velva and at various locations along 
the 358-mile U.S. portion of the Souris River. (For general 
location see Geological Survey map of North Dakota.) 
Existing project. The current plan of improvement authorized 
by the Water Resources Development Act of 1986 is the 
one-time purchase of 400,000 acre-feet of flood storage in 
Rafferty and Alameda Dams in Saskatchewan, Canada and the 
operation and maintenance of Rafferty Dam, Alameda Dam and 
the existing Boundary Dam in conjunction with the existing 
Lake Darling Dam to provide 100-year flood protection at 
Minot, North Dakota. The Act also authorizes those flood 
control measures upstream and downstream of the dam which 
are necessary for effective operation of the project. The 4-foot 
raise of the Lake Darling design pool (authorized by Section III 
of the Energy and Water Development Appropriations Act, 
1982, PL 97-88) and the the construction of Burlington Dam 
(authorized by PL 91-611) will no longer be authorized upon 
completion of the structure(s) in Canada. An International 
Agreement between Canada and the United States was signed in 
October 1989. 
The work under the current plan authorized by PL 99-662, 
consists of either one or two reservoirs in Saskatchewan, Canada 
(known as the Rafferty and Alameda projects); a modified 
outflow structure at Lake Darling Dam; a downstream flood 
warning system from the Canadian border; levee improvements 
at Sawyer, Renville County Park, and six subdivisions from 
Burlington to Minot, flood proofing of about 90 rural homes in 
the basin and the purchase of flowage easements; modifications 
to dams 87 and 96 in the Upper Souris National Wildlife Refuge; 
and modifications to dams 320, 326, 332, 341 and 357 in the J. 
Clark Salyer National Wildlife Refuge. Estimated Federal cost 
(1989) for new work is $80,900,000 and $5,042,000 is to be 
contributed by local interests. 
Local cooperation. See Annual Report for 1983 for requirements. 
Representatives of the water resource districts from 
Ward, Renville, McHenry, and Bottineau Counties area agreed 
to become members of a Souris River Joint Board for flood 
control, which would serve as local sponsor for the project. A 
local cooperation agreement for construction at Velva was 
signed in November 1984. A local cooperation agreement for 
the remainder of the project as authorized by the Water Resources 
Development Act of 1986 was signed in October 1989. 
Operations and results during fiscal year. New Work: 
Preconstruction planning for the Souris River basin reservoir 
continued at a cost of $1,891,625. An adjustment of construction 
contract costs for improvements at Velva was made for $- 
60,173. Engineering and design and supervision and administration 
costs for Velva were $48,049. 
24-14

ST. PAUL, MINNESOTA DISTRICT 
Condition at end of fiscal year: Construction of the channel 
and levee improvement work at Velva is complete. Preconstruction 
engineering and design are in progress for the remainder 
of the project. 
40. STATE ROAD AND EBNER COULEES, WI 
Location. In La Crosse County in west-central Wisconsin, 
on the south side of the City of La Crosse. (For general location, 
see Geological Survey map of Wisconsin.) 
Existing project. The plan of improvement for local protection 
(flood control) consists of channel deepening and enlarging 
downstream from Hagen Bridge to the mouth of Pammel Creek 
and includes 13,600 feet of concrete-lined rectangular channel, 
a drop chute inlet structure, a side channel inlet structure, a 
stilling basin, a terminus structure, and three new street bridges. 
The upper 4,000 feet of rectangular channel is designed for 
supercritical flow and the remaining 9,600 feet of channel is 
designed for subcritical flow. When completed, the project will 
provide Standard Project Flood (SPF) protection. The city 
replaced a fourth bridge in 1980 that was previously included in 
the authorized plan. The city also replaced a railroad bridge in 
1985 that was also included in the authorized plan. In 1986, the 
city constructed 450 feet of rectangular channel in the downstream 
reach to SPF protection. Estimated cost (1989) to the 
United States for new work, exclusive of the Ebner Coulee 
portion of the project which was deleted due to lack of economic 
feasibility, is $25,000,000 and $8,300,000 is to be contributed 
by local interests including a credit of $1,000,000 for advance 
construction work. Project was authorized by 1968 Flood 
Control Act (H. Doc. 360, 90th Cong., 2d sess., contains published 
map.) 
Local cooperation. See Annual Report for 1969 for requirements. 
The local sponsor withdrew support for the project in 
1976 citing increased non-Federal costs and lack of agreement 
on local cost sharing between three local units of government 
located within the project area. The project was reclassified as 
inactive on April 7, 1977, but was reactivated on November 8, 
1978, after the La Crosse County Board of Supervisors, the La 
Crosse City Council, and the Town of Shelby passed separate 
resolutions on September 17, 1978, July 13, 1978, and July 10, 
1978, respectively, which requested continuance of the project. 
A Local Cooperation Agreement between the Department of the 
Army and the City of La Crosse, Wisconsin, for the construction 
of the State Road flood control project was entered into August 
11, 1988. 
Operations and results during fiscal year. New Work: A 
Stage 1 construction contract cost $4,924,577. Real estate costs 
were $10,636. Cultural resources cost $19,774 by hired labor 
and $21,000 by contract. Engineering and design cost $225,164 
by contract and $172,909 by hired labor. Supervision and administration 
costs were $159,355. Other miscellaneous costs 
were $10,332. 
Condition at end of fiscal year: A construction contract for 
Stage 1 (outlet structure to Broadview Place) was awarded in 
September 1988. Plans and specifications for Stage 2 have been 
initiated. Ebner Coulee was classified to "inactive" in 1981 due 
to lack of economic feasibility. Construction is continuing. 
41. ST. PAUL, MN 
Location. In Ramsey County at St. Paul, Minnesota, on the 
Mississippi River. (For general location see Geological Survey 
map of Minnesota.) 
Previous project. For details see page 27-20 of Annual 
Report for 1974. 
Existing project. Since completion of the St. Pauland South 
St. Paul flood control project in 1964, the protected area has 
experienced two floods greater than the previous flood of record. 
The plan of protection provides for a 4-foot barrier raise along 
the existing project alignment. Estimated cost (1988) to the 
United States for new work is $7,160,000 and $2,390,000 is to 
be contributed by local interests. Project was authorized by the 
Water Resources Development Act of 1986 (Public Law 99- 
662). 
Local cooperation. See Annual Report for 1988 for requirements. 
During the preparation of the General Design Memorandum, 
the items of local cooperation will be modified to reflect 
cost sharing requirements of the Water Resources Development 
Act of 1986. Meetings on December 10, 1987 and January 14, 
1988 with local officials from the city of St. Paul reaffirmed the 
local sponsor's support of the project and its willingness to 
assume non-Federal cost sharing responsibilities. 
Operations and results during fiscal year. New Work: 
Preconstruction planning continued at a cost of $479,221. 
Condition at end of fiscal year: Preconstruction planning is 
continuing. 
42. WILD RICE RIVER--SOUTH BRANCH 
AND FELTON DITCH, MN 
Location. In Clay and Norman Counties in west-central 
Minnesota northeast of the city of Moorhead, MN. The South 
Branch of the Wild Rice River and Felton Ditch drain areas of 
253 and 122 square miles and enter the Wild Rice River at points 
29.5 and 20.5 miles, respectively, above its confluence with the 
Red River of the North. (For general locations, see Geological 
Survey map of Minnesota.) 
Existing project. Provided for increasing the capacities of 
the South Branch and Felton Ditch channels by widening the 
existing channels through the floodplain. Debris removal was 
accomplished in the lower reaches of both streams. In addition, 
short reaches of low dikes were constructed on both banks of 
Felton Ditch near the upper limit of improvement. The plan also 
included bridge and culvert structure alterations, new bridges, 
multi-plate pipe arches, side ditch inlet and lateral ditch entry 
modifications; and a drop inlet structure. The project provides 
flood protection in both watersheds for a 6-percent chance flood 
and outlets necessary for removal of crop-damaging surface 
24-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
waters from lateral and on-farm drainage systems. Project was 
authorized by 1968 Flood Control Act (H. Doc. 98, 90th Cong., 
1st sess., contains latest published map.) 
Local cooperation. See Annual Report for 1969 for requirements. 
A local assurance agreement in accordance with Section 
221 of the Flood Control Act of 1970 was executed by the Wild 
Rice Watershed District on October 18, 1978. 
Operations and results during fiscal year. New Work: A 
construction contract cost $7,849. Engineering and design cost 
$9,408 by hired labor and supervision and administration cost 
$11,921. 
Condition at end of fiscal year. The original flood control 
project was completed in 1983. After assuming responsibility 
for its operation and maintenance, the local sponsor reported a 
problem associated with certain types of inlets that had been 
installed. It was determined that the problems resulted from a 
design deficiency. A contract was awarded in September 1987 
to correct this deficiency by realigning/relocating the outlets of 
102 culvert inlets. The work is complete. 
43. WINONA, MN 
Location. At Winona County in southeastern Minnesota on 
the right bank of the Mississippi River about 725 miles above 
mouth of the Ohio River. (For general location see Geological 
Survey map of Minnesota.) 
Existing project. See Annual Report for 1968 for completed 
upstream improvements authorized by the Flood Control 
Act of 1958 providing for a continuous flood barrier about 6.1 
miles long with related pumping and interior drainage facilities. 
Federal costs amounted to $2,147,131 of which $111,500 was 
expended for the portion then deferred for restudy and $17,316 
was contributed by local interests. 
Improvement authorized in 1971 under Section 201 of the 
Flood Control Act of 1965 (H. Doc. 152, 92d Cong., 1st sess., 
contains latest published map) provides for levee and floodwall 
protection with necessary interior drainage works for the riverfront 
and the Lake Winona closure reaches, as well as a sound 
floodplain management program to prevent unwise development 
of the bordered by U.S. Highway 61 and Burns Valley and 
Pleasant Valley Creeks. The plan would also provide the 
downstream flood barrier needed to prevent Mississippi River 
backup flows from entering Lake Winona and inundating the 
area now only partially protected by the completed segment of 
the project authorized by the 1958 Flood Control Act. The plan 
would also provide control of Burns Valley Creek by means of 
channel improvement, raising and extending the existing levee 
system, a drop structure, an erosion control structure, alteration 
of two highway bridges, and a sewer line modification. Earth 
levees averaging 10 feet in height total approximately 3.1 miles 
in length. Concrete floodwalls, also averaging about 10 feet in 
height, total about 2,025 feet in length. Resolutions authorizing 
the project were adopted by the Public Works Committees of the 
House on July 29, 1971, and the Senate on November 18, 1971. 
Local cooperation. Fully complied with for completed 
work. See Annual Report for 1968 for requirements. 
For improvements authorized in 1971 see Annual Report of 
1972 for requirements. A local cooperation agreement required 
under Section 221 of the 1970 Flood Control Act was executed 
by the City of Winona on October 6, 1978. 
Operations and results during fiscal year. New Work: A 
construction contract for dredge fill cost $55,513. Engineering 
and design cost $3,043 by hired labor. Supervision and administration 
and other miscellaneous costs were $175. 
Condition at end of fiscal year: The upstream improvement 
except for a portion of the project raising and extending the 
existing levee downstream from the Lake Winona outlet was 
completed in August 1967. Work authorized in 1971 is complete. 
Project was formally dedicated by the city on October 13, 
1985. By letter dated September 7, 1988, responsibility for the 
completed project was transferred to the city of Winona. 
44. ZUMBRO RIVER AT JARRETT AND 
MILLVILLE, MN 
Location. The project sites are located on the left bank of the 
Zumbro River. The first site is about 1/2 mile downstream from 
Jarrett, Minnesota, and the second is about 1 1/4 miles downstream 
from Millville, Minnesota. The sites are about 16 miles 
northeast of Rochester, Minnesota, in south-central Wabasha 
County, in southeastern Minnesota. 
Existing project. The project to protect the streambank 
from erosion that is threatening County State Aid Highway 11 
was authorized under Section 14 of the 1946 Flood Control Act, 
as amended. The initial appraisal reports were dated June 1986 
and March 1987 for Millville and for Jarrett, respectively. The 
recommended plan consists of placing 2,200 tons of rockfill 
along 700 feet of the riverbank to protect the road from further 
erosion at the Millville site, and minor excavation and placing 
11,450 tons of rockfill along 1130 feet of the riverbank to protect 
the road from further erosion at the Jarrett site. The project was 
approved for construction by the Chief of Engineers on July 22, 
1988. 
Local cooperation. See Annual Report for 1988 for requirements. 
Local cooperation agreements for the projects were 
signed by Wabasha County, Minnesota in July 1988. 
Operations and results during fiscal year. New Work: A 
construction contract cost $88,983. Engineering and design cost 
$2,226. Real estate studies cost $157. Supervision and administration 
cost $1,819. 
Condition at end of fiscal year: A construction contract for 
slope protection was awarded on September 19, 1988. Construction 
is complete. Project was turned over to local interests 
by letter dated October 2, 1989. 
45. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood control projects turned over to local interests were 
inspected to determine that project channels are kept clean and 
24-16

ST. PAUL, MINNESOTA DISTRICT 
unobstructed, dikes and revetments are in good condition, and 
structures are in good repair and operable. Deficiencies, if any, 
were minor unless noted. (See table 24-J on inspection of completed 
flood control projects.) 
Cost for the period was $56,816. Total cost to September 30, 
1989, is $1,006,346. 
Miscellaneous 
46. OTHER WORK UNDER SPECIAL 
AUTHORITY 
In the Aquatic Plant Control program (Section 302, Public 
Law 298, 89th Congress) coordination with the state of Minnesota 
cost $46,183 and coordination with the state of Wisconsin, 
cost $12,166. A contract for aquatic plant control operations at 
Buffalo Lake, Wisconsin cost $27,000. Work in Minnesota by 
other Corps offices cost $19,790. 
Condition/operation studies for removal of silt and aquatic 
growth in Sauk Lake, Minnesota (Section 602, Water Resources 
Development Act of 1986) cost $404 by contract with the Fish 
and Wildlife Service, $80,300 by agreement with the United 
States Geological Survey, $12,500 by agreement with the Department 
of Agriculture, $4,001 by agreement with the Waterways 
Experiment Station, and $81,809 by hired labor. 
General Investigations 
47. SURVEYS 
Fiscal year cost was $1,076,853 which included five flood 
damage prevention studies, one restudy of deferred projects 
study, miscellaneous activities, and coordination with both 
Federal and non-Federal agencies. Table 24-L provides a 
specific list and respective fiscal year expenditures. 
48. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year cost was $314,633 which included the items 
concerning international water studies, flood plain management 
services and hydrologic studies. Table 24-L provides a specific 
list and respective fiscal year expenditures. 
49. ADVANCE ENGINEERING AND DESIGN 
Fiscal year cost was $1,775,138 which included six local 
protection projects. Table 24-L provides a specific list and 
respective fiscal year expenditures. For details of the individual 
projects see sections 17, 25, 29, 38 and 41. 
24-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-A COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project Funding FY86 FY87 FY88 FY89 1989 
1. Minnesota River, MN 
3. Reservoirs at 
Headwaters of 
Mississippi 
River, MN 
4. St. Croix River, 
MN and WI 
5. Warroad Harbor 
and River, MN 
6. Zippel Bay, 
Lake of the 
Woods County, MN 
7. Bassett Creek, MN 
8. Big Stone Lake 
and Whetstone 
River, MN and 
SD 
9. Cannon River at 
Faribault, MN 
10. Chaska, MN 
11. Devils Lake, ND 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maj. Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
2,057,7221 
2,057,7221 
- 48,300 
7,585 
283,000 
282,907 
35,546 
35,639 
115,700 2 2,712,132 
114,4992 2,710,931 
- - - - 4,398,6283 
- - - - 4,398,628 3 
2,263,000 1,643,200 2,305,600 2,413,600 30,184,0464 
2,040,208 1,964,106 2,153,201 2,538,360 30,094,5644 
- - - - 425,000 
- - - - 425,000 
- - - - 150,410 
- - - - 150,410 
100 
100 
69,700 5 1,178,055 
69,700 s 1,178,055 
86,105 
86,105 
34,600 
38,947 
331,000 
87,146 
24,000 
24,569 
215,046 
415,000 5,522,000 
323,387 5,159,893 
130,000 
221,445 
107,000 
173,867 
1.5,000 
52,066 
90,124 
- 
104,960 
181,300 
177,527 
14,500 
7,500 
1,347 
100,000 
75,701 
68,187 
63,332 
6,600 
12,111 
- - 115,000 
11,035 - 59,318 
1,219,787 
1,219,787 
515,000 
515,0006 
3,131,000 1,051,000 11,834,000 
1,598,739 2,883,210 11,662,8117 
- - 12,175,000 
- - 12,174,9148 
133,800 
150,131 
57,750 
6,988 
217,000 
209,888 
107,000 
152,113 
197,300 
195,915 
46,144 
901,000 
891,512 
25,000 
38,903 
2,623,600 
2,621,683 
72,250 
60,632' 
2,961,000 
2,943,89610 
2,702,000 
2,690,864 
24-18

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-A COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30 
In Text Project Funding FY86 FY87 FY88 FY89 1989 
12. Eau Galle River, WI 
13. Emerson, Manitoba- 
Noyes, MN 
14. Enderlin, Maple 
River, ND 
15. Grafton Pumping 
Station, ND 
16. Homme Lake and 
Dam, ND 
17. Houston, MN 
18. Lac qui Parle 
Lakes, MN 
19. La Farge Lake 
and Channel 
Imp., WI 
20. Lake Andrusia, 
Mississippi River, 
MN 
21. Lake Ashtabula 
and Baldhill 
Dam, Sheyenne 
River, ND 
22. Lake Pulaski, 
Wright County, MN 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Dam Safety: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
606,000 
472,034 
25,000 
6,351 
361,669 
68,000 
83,257 
384,500 
931,793 
78,000 
68,208 
934,000 
1,082,717 
325,000 
106,728 
488,500 
663,301 
15,000 
35,793 
20,057 
10,000 
10,000 
64,600 
65,211 
250,000 
152,000 
476,600 
478,975 
45,600 
68,774 
17,500 
8,057 
420,500 
512,070 
350,000 
68 
27,584 
139,000 
38,592 
84,600 
79,641 
229,000 
190,852 
478,200 
495,181 
34,200 
36,774 
54,000 
54,437 
836,000 1,165,900 
1,084,350 1,121,528 
- 1,080,000 
- 456,218 
760,000 
981,973 
20,000 
2,997 
24-19 
9,039,250 
9,039,250 
597,200 
591,644 
336,071 
9,959 
60,205 
77,500 
82,812 
180,000 
222,100 
- 
462,200 
520,713 
16,300 
16,300 
- 1,168 
724,600 
761,998 
401,000 
554,671 
15,762 
6,467,305 
6,449,839 
425,000 
390,96011 
4,000,000 
3,999,82412 
149,000 
108,797 13 
1,396,097 
1,396,097 
2,430,121 
2,429,113 
659,000 
564,952 
964,873 
964,873 
6,411,663 
6,404,237 
18,642,000 
18,642,000 
277,100 
276,499 
71,500 
61,326 15 
3,325,638 
3,325,63816 
15,634,652 
15,622,007 
1,481,000 
1,010,889 
1,187,500 
1,183,72417

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-A COST AND FINANCIAL STATEMENT (cont) 
See Total Cost to 
Section September 30 
In Text Project Funding FY86 FY87 FY88 FY89 1989 
23. Lake T raverse 
and Bois de Sioux 
River, SD 
and MN 
24. Mankato and North 
Mankato, MN 
25. Marshall, MN 
26. Middle River at 
Argyle, MN 
27. Minnesota River 
at Henderson, MN 
28. Pettibone Park, 
LaCrosse, WI 
29. Portage, WI 
30. Prairie du Chien, 
WI 
31. Red Lake River,MN, 
including 
Clearwater 
River, MN 
32. Red Lake River, 
Gentilly, MN 
33. Red River of the 
North at 
Argusviiie, ND 
34. Red River of the 
North at 
Breckenridge, MN 
35. Red River of the 
North Drainage 
Basin, MN, 
SD and ND 
36. Rochester, MN 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,339,727 
1,339,727 
265,000 
277,289 
400,900 
399,078 
516,900 
504,140 
331,900 
348,094 
10,875,000 10,035,000 9,200,000 1,298,000 
10,276,105 10,550,414 9,008,612 2,139,575 
75,000 
133,624 
345,000 
448,055 
40,000 
4,568 
-
- 
- 70,000 
- 87,787 
100,500 
142,367 
190,000 
94,958 
200,000 
196,334 
18,000 
161,205 
100,000 
94,983 
215,000 1,020,000 
234,728 475,312 
- 77,000 
- 19,883 
12,374 
65,200 
68,424 
535,000 570,000 
233,838 803,174 
- 7,500 
- 7,500 
331,000 214,000 
365,679 185,313 
42,051 
84,700 
78,031 
100,000 
24,445 
- 50,000 
145,050 
67,500 
6,971 
- 35,000 
1,250 
385,000 358,400 324,700 
367,879 413,858 294,219 
244,000 
229,894 
25,000 
33,569 
990,000 
77,750 
350,000 
712,016 
42,879 
300,000 
280,668 
- 69,891 
- 69,891 
140,400 
154,746 
140,000 
84,216 
17,238 
59,206 
428,900 
461,120 
673,000 3,489,000 5,514,000 
563,018 1,510,876 6,461,148 
4,362,319 
4,347,272 
97,378,500 
96,940,538 18 
2,495,866 
2,495,024 19 
2,015,000 
1,077,118 
1,747,500 
1,544,549 20 
77,000 
62,762 21 
300,000 
280,668 
3,685,000 
3,528,347 
3,120,079 
3,120,079 22 
1,231,602 
1,231,512 
247,500 
116,161 
1,534,000 
1,522,688 
75,000 
73,677 23 
8,138,984 
8,138,984 24 
4,496,534 
4,476,966 
12,800,000 25 
11,617,880 
24-20

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-A COST AND FINANCIAL STATEMENT (cont) 
See Total Cost to 
Section September 30 
In Text Project Funding FY86 FY87 FY88 FY89 1989 
37. Roseau River, MN New Work: 
Approp. - - - 2,128,000 
Cost 9,748 23,548 14,775 9,193 1,957,854 
38. Sheyenne River, New Work: 
ND Approp. 711,000 845,000 522,000 780,000 4,413,000 
Cost 733,305 688,070 687,427 759.579 4,389,928 26 
39. Souris River New Work: 
Basin, ND Approp. 3,257,000 2,057,000 2.450,000 1,500,000 10,572,000 
Cost 2,359,516 2,388,438 2,404,279 1,879,501 10,339y734 27 
40. State Road & New Work: 
Ebner Coulees, Approp. 15,000 - 1,265,000 4,582,000 7,409.000 
WI Cost 20,953 14,134 231,633 5,543,747 7,337,380 "8 
41. St. Paul, MN New Work: 
Approp. - - 400,000 475,000 875,000 
Cost - - 389.808 479,221 869,029 
42. Wild Rice River, New Work: 
South Branch and Approp. - 946.000 200,000 - 60.000 5,620.700 
Felton Ditch, MN Cost - 120,973 935,849 29.178 5,620,700 
43. Winona, MN New Work: 
Approp. - 165,000 - - 32,741,131 
Cost 186,137 86,877 98,537 58.731 32,741,131 "9 
44. Zumbro River New Work: 
at Jarrett and Approp. - 44,500 141,000 - 10,000 175.500 
Millville, MN Cost - 17,345 39,043 93,185 149,573 0o 
1 Includes $117,542 for new work for previous project. 
Excludes $359,202 contributed funds. 
2 Includes $2,800 for condition surveys. 
3 Includes $681,805 for new work for previous projects. 
4 Includes $100,857 for maintenance for previous projects. 
s Includes $4,200 for condition surveys. 
6 Excludes $307,556 contributed funds. 
' Excludes $218,940 contributed funds. 
8 Excludes $152,223 contributed funds. In addition, $486,313 
in other contributed funds have been expended for work under 
Government contract paid for by the Ottertail Power Company. 
9 Excludes $14,841 contributed funds. 
10 Excludes $229,327 contributed funds. 
ix Excludes $46,439 contributed funds. 
12 Excludes $131,459 contributed funds. 
13 Excludes $18,014 contributed funds. 
14 Excludes $56,220 contributed funds. 
15 Excludes $20,441 contributed funds. 
16 Excludes $208,000 contributed funds. 
17 Excludes $33,902 contributed funds. 
18 Excludes $79,537 contributed funds. 
19 Includes $1,802,866 for new work for previous project. 
20 Excludes $144,160 contributed funds. 
21 Excludes $20,920 contributed funds. 
22 Excludes $30,020 contributed funds. 
23 Excludes $20,327 contributed funds. 
24 Includes cost of the Wahpeton-Breckenridge unit,$11,239, 
which is classed as "deferred" and the units on which authorization 
has expired: Maple River, $1,241; Moorhead, $27,700; Sheyenne, 
$37,956. In addition, $203,874 special deposit funds and $146,160 
in other contributed funds have been expended for work under Government 
contract paid for by local interests. 
25 Excludes $554,350 contributed funds. 
26 Excludes $1,150,000 sunk costs for deauthorized Kindred 
Lake unit (see Table 24-G). 
27 Excludes $4,919,000 sunk costs for deferred Lake Darling 
Dam unit (see Table 24-E). 
28 Excludes $225,000 sunk costs for inactive Ebner Coulee unit 
(see Table 24-E) and $209,083 contributed funds. 
29 Excludes $589,316 contributed funds. In addition, $717,809 
in other contributed funds have been expended for work under Government 
contract paid for by local interests. 
30 Excludes $29,845 contributed funds. 
24-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-B AUTHORIZING LEGISLATION 
See Date of 
Sec. Authorizing 
in Text Act Project and Work Authorized Documents 
MINNESOTA RIVER, MN 
1. July 13, 1892 Open-channel improvement from mouth to Shakopee to obtain a 
channel of 4-foot depth to accommodate vessels with 3-foot draft. 
July 3, 1958 Dredging to provide channel of 9-foot depth from mouth to mile 14.7 
RESERVOIRS AT HEADWATERS OF MISSISSIPPI 
RIVER, MN 
3. Mar. 3, 1899 Reconstruct 4 of the 5 original dams and surveys to determine 
extent of lands overflowed by reservoirs. 
Mar. 2, 1907 Reconstruct Sandy Lake Dam and construct Gull Lake Reservoir. 
June 25, 1910 Construct an equalizing canal between Winnibigoshish and Leech 
Lake Reservoirs (no work was done and this part of the project 
abandoned in Act of Mar. 4, 1915.) 
July 27, 1916 Abandonment of ditches connecting Long Lake, Round Lake, and 
Gull Lake. 
June 26, 1934 2 Operation and maintenance provided for with funds from War 
Department appropriations for rivers and harbors. 
Annual Report 1891. 
p. 2209 
S. Doc. 144. 84th Cong., 
2d sess. 1 
H. Doc. 363, 61st Cong., 
2d sess. 
H. Doc. 413, 64th Cong., 
1st sess. 1 
4. June 18, 1878 
June 3, 1896 
Jan. 21, 1927 
Aug. 30, 1935 
May 17, 1950 
ST. CROIX RIVER, MN AND WI 
Dredging, etc., for a 3-foot channel between mouth and 
Taylors Falls. 
Harbor and waterfront at Stillwater. 
A 6-foot channel to Stillwater. 
The 9-foot channel from mouth to Stillwater. 
Small-boat harbor at Hudson. 6 
WARROAD HARBOR AND RIVER, MN 
5. Mar. 3, 1899 Dredging bar at mouth of Warroad River. 
June 6, 1900 Entrance channel 300 feet wide and 7 feet deep. 
June 13, 1902 3 
Mar. 3, 1905 
June 25, 1910 
July 25, 1912 
Aug. 5, 1977 
Enlarging turning basin. 
Deepening to 8 feet. 
Deauthorized portion of entrance channel and turning basin to 
complete project width and depth. 
H. Ex. Doc. 75, pt. 6, 43rd 
Cong., 2d Sess;4 Annual 
Report 1875, p. 372. 
H. Doc. 378, 69th Cong., 
1st sess. 4 
H. Doc. 183, 72nd Cong., 
1st sess. 4 
H. Doc. 184, 81st Cong., 
1st sess. 4 
Specified in Act. 
H. Doc. 92, 56th Cong., 
2d sess. s 
H. Doc. 703, 61st Cong., 
2d sess. 5 
Public Law 93-251 
1Contains latest published map. 
2 Permanent Appropriations Repeal Act. 
3 Appropriation 
4 See H. Doc. 462, 71st Congress, 2d sess., for latest published 
map. 
5 Latest published map is oppositep. 1984 in Annual Report for 1911. 
6 Deauthorized by 1986 WRDA (see Table 24-G). 
24-22

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30. 1989 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Baudette Harbor, MN Completed 1961 $36,415 $57,768 
Black River, WI 1 1950 67,585 - 
Lake Traverse, MN and SD 3, 4 1921 92 - 
Mississippi and Leech Rivers, MN Completed 3 1929 277,615 40,251 
Mississippi River between Brainerd and Grand 5 1925 47,794 3,891 
Rapids, MN 
Pine Creek, Angle Inlet, MN Completed 1978 38,700 102,196 
Red Lake and Red Lake River, MN Completed 3 1923 9,070 - 
Red River of the North, MN and ND 3, 6 1921 293,344 76,209 
Wisconsin River, WI 2, 3 1888 - - 
Zippel Bay Harbor, MN Inactive 5 1928 27,941 11,139 
1 Existing channel adequate for commerce (see table 24-G for 
deauthorized portion of project). 
2 Originally included in project 'Fox and Wisconsin Rivers, WI' 
Abandonment of improvement of Wisconsin River by 
channel contraction works recommended in 1886 and 1887 
(H.Doc.65,49th Cong., 2d sess.). Expenditures included under 
Fox and Wisconsin Rivers, WI'. No breakdown available. 
3 No commerce reported. 
4 Abandonment recommended in 1915 (H. Doc. 439, 64th 
Cong., 1st sess.) and June 24, 1926 (H. Doc. 467, 69th Cong.,lst sess.). 
s Abandonment recommended June 24, 1926 (H. Doc. 467,69th 
Cong. 1st sess.). 
6 Abandonment recommended in 1915 (H. Doc. 1666, 63d 
Cong., 3d sess.). 
24-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30. 1989 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Black Bear and Miller Lakes, Crow Wing County, MN 
Bonnes Coulee, Velva, ND s 5 
Burlington Dam, Souris River, ND 
Dry Run, IA 
Elk River, MN 
Grafton, ND 
Guttenberg, IA 
Hanover, Hennepin County, MN 5 
Irving Township, Jackson County, WI5 
Irving Township at Nicols Road, 
Jackson County, WI s 
Kickapoo River, Gays Mills, WI s 
Lake Darling Dam, ND 
Lost River, MN 
Lower Branch Rush River, ND 8 
Minnesota River at LeSueur, MN s 
Minneota, MN s 
Minot, ND 
Mississippi River near Aitkin, MN 
Pembina River, ND 
Pembina River Lake, ND 
Red Lake River at Huot, MN 5 
Red Lake River at Red Lake Falls, MN s 
Red River of the North at Breckenridge, MN s 
Red River of the North at Halstad, MN 8 
Red River of the North at Oslo, MN 8 
Red River of the North at Pembina, ND 8 
Redwood River below Marshall, MN a 
Rushford, MN 
Shepard Road, Mississippi River, St. Paul, MN 
Sheyenne River, Valley City, ND S 
Souris River, Velva, ND S 
St. Paul and South St. Paul, MN 
State Road & Ebner Coulees, WI 
(Ebner Coulee Unit) 
Tongue River Lake, ND 
Twin Valley, MN 
Upper Iowa River, IA 
Velva, ND 8 
Vermillion River, Hastings, MN 8 
Veteran's Memorial Levee, Mississippi River, 
Hastings, MN s 
Warner Road, Mississippi River, St. Paul, MN s 
Zumbro River, MN 
1 Advance engineering and design costs only. Project deferred with 
authorization of Lake Darling project. Additional authorization required 
for implementation of recommended plan. The Senate Report 
97-256 states that the Corps is to take no further action to construct 
Burlington Dam until directed to do so by Congress. 
2 Excludes $42,766 contributed funds. 
3 In addition $87,878 was expended from Public Law 99 funds in 
the spring of 1969 for emergency protection and incorporation into the 
permanent project. 
4 Preconstruction planning has not started. Phase I completed under 
General Investigations. 
24-24 
Completed 
Completed 
Deferred 
Completed 
Completed 
Active 4 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Active 4 
Inactive 12 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Inactive 12 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1988 
1985 
1983 
1966 
1970 
1983 
1974 
1988 
1984 
1986 
1987 
1987 
1967 
1974 
1986 
1963 
1983 
1957 
1983 
1950 
1984 
1984 
1986 
1984 
1979 
1960 
1980 
1985 
1988 
1988 
1974 
1987 
1950 
1988 
1964 
1970 
1980 
1985 
1987 
1975 
$471,000 
58,500 
5,568,6001 
1,790,759 2 
259,700 3 
2,361,915 
259,500 
189,600 
158,500 
33,000 
4,919,0006 
517,519 7 
1,000,000 9 
250,00010 
161,545 
21,479,50011 
1,675,835 
50,000 
64,500 
131,000 
27,500 
2,012,000 
1,960,200 
2,000,000 
202,400 
3,192,333 
250,00013 
111,000 
137,500 
8,476,01214 
225,000 
23,695 
2,115,700 
888,445 
334,628 
999,900 
182,000 
250,000 
1,284,100

ST. PAUL, MINNESOTA DISTRICT 
5 Project authorized by Chief of Engineers under small project 
authority, Section 14, Flood Control Act of 1946, as amended. 
6Advance engineering and design costs only. Project deferred with 
authorization of Souris River Basin Project (see Section 39 and Table 
24-A for costs for active project). 
7 Excludes $46,034 for the Ruffy Brook unit for which authorization 
expired in April 1966 (see Table 24-G). Excludes $246,911 contributed 
funds. 
8 Project authorized by Chief of Engineers under small project 
authority, Section 205, 1948 Flood Control Act, as amended. 
9 Excludes $35,000 contributed funds. 
1o Excludes $130,300 contributed funds. 
11 Excludes $4,167 contributed funds. 
12 Further work deferred pending review of project document (inactive). 
13 Excludes $62,620 contributed funds. 
14 Excludes $545,637 contributed funds for new work and $38,000 
expended by South St. Paul for work in lieu of required cash contribution. 
Excludes an additional, $206,629 expended for work done at 
request of local interests. 
24-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Black River, WI 1 1950 Aug. 5, 1977 - - 
Black River Lake, WI 1950 Aug. 5, 1977 - - 
Hudson Harbor, WI 2 1986 Nov. 17, 1986 - - 
Kindred Lake, ND 3 1987 Nov. 17, 1986 $1,150,000 - 
La Crosse, WI 1983 Nov. 17, 1986 - - 
Maple River, ND 4 1981 Oct. 6, 1961 1,241 - 
Moorhead, MN 4 1981 Oct. 30, 1961 27,700 - 
Ruffy Brook, MN 1967 Apr. 1966 46,034 - 
Sheyenne River, ND 4 1981 Dec. 31, 1970 37,956 - 
Warroad River and Bulldog Creek, MN 1974 Nov. 17, 1986 182,000 
Warroad Harbor and River, MN s 1981 Aug. 5, 1977 - - 
1Portion of project for removal of obstructions at various points 
outside the dredged area to clear channel to full project width (see Table 
24-C for costs for completed portion of project). 
2 Part of the St. Croix River, Minnesota and Wisconsin project (see 
Section 4 in text). 
3 Previously part of Sheyenne River, ND project (see Section 38 and 
Table 24-A for costs for active project). 
4 Part of Red River of the North Drainage Basin (see Section 35 in text 
and Table 24-I for costs for active units of the project). 
S Portion of dredging of entrance channel and turning basin to 
complete project width and depth (see Table 24-A for costs for 
completed portion of project). 
24-26

TABLE 24-H RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER 
(See Section 3 of Text) 
Outlet Watershed Area (square miles) Capacity Previous Projects Existing Proiects 
at 
Minimum Above Watershed Maximum 
Stages St. Paul (square Original Stage Total 
Reservoir (feet) 1 River (miles) miles) Lake Reservoir (acre-feet) Completed Cost Completed Cost Cost 
Winnibigoshish 6 Mississippi 408 1,442 117 179.4 967,930 1884 $214,000 1900 $173,470 $387,470 
Leech Lake 0 Leech 410 1,163 173 205.9 743,320 1884 171,805 1902 84,380 256,185 
Pokegama 6 Mississippi 344 6602 24 35.0 120,750 1884 85,000 1904 126,030 211,030 
Sandy Lake 7 Sandy 267 421 8 16.6 72,500 1895 114,000 1909 117,020 231,020 
Pine River 9 Pine 199 562 18 23.7 177,520 1886 97,000 1907 133,320 230,320 
Gull Lake 5 Gull 168 287 20 20.5 70,820 - - 1913 86,826 86,826 
Surveys and flowage rights - - - - 160,939 160,939 
Recreational facilities - - - - 2,834,838 2,834,838 
Total new work - - 681,805 - 3,716,823 4,398,628 
Total operating and care - - 100,857 - 29,026,508 29,127,365 
Permanent indefinite - - - - 967,197 967,197 
appropriation for operation 
and care, Feb. 1, 1895 to end of 
fiscal year 1936 
Rehabilitation - - - - 425,000 425,000 
Total 2,152,840 - $782,662 - $34,135,528 $34,918,190 
'Lower operating limits by regulations approved February 4, 1936, as modified December 29, 1944. 
2 Exclusive of area controlled by Winnibigoshish and Leech Lake Dams. 
i
)
3
3
)
) 
ycJ 
r
zz 
0
dd 
y

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-I RED RIVER OF THE NORTH DRAINAGE BASIN: 
ACTIVE UNITS IN COMPREHENSIVE BASIN PLAN 
(See Section 35 of Text) 
Total 
Cost to Estimated 
Name of Unit State Type September 30, 1989 Federal Cost 
Orwell Reservoir (Otter Tail River) Minnesota Reservoir $1,916,753 $1,916,7001 
Wild Rice and Marsh Rivers Minnesota Channel improvement 405,056 405,100 
Rush River North Dakota Channel improvement 287,686 287,700 
Sand Hill River Minnesota Channel improvement 548,778 548,800 
Mustinka River Minnesota Channel improvement 440,788 440,800 
Otter Tail River Minnesota Channel improvement 174,768 174,800 
Red River at Grand Forks North Dakota Levees and floodwall 948,895 948,900 
Red River at East Grand Forks Minnesota Levees, floodwall, 1,698,200 17,500,000 2 
pumping plants 
Red River at Fargo North Dakota Channel improvement, 1,639,924 1,639,9003 
levees 
Total cost to date 8,060,8484 
Total estimated cost 23,862,000 5 
1 Includes $181,713 for lands and $25,045 for recreation 
facilities. 
2 The East Grand Forks unit was reclassified from active 
to inactive on August 19, 1988. The cost of this unit was last 
revised in 1987. 
3 Includes $67,900 for lands. 
4 Costs of $11,239 for the Wahpeton-Breckenridge 
deferred unit not included. Authorization of the Sheyenne River, 
Moorhead, and Maple River units has expired. Cost of these units 
also not included total $66,897. 
5 The Wahpeton-Breckenridge unit of the project is 
classed as 'deferred' and is excluded from the estimate. The cost of 
this unit, last revised in 1955, was estimated to be $666,000. The 
Flood Control Act approved December 31, 1970 (H. Doc. 330-91-2) 
provided for deletion of the Sheyenne River unit, an authorization of 
the Maple River and Moorhead units expired at the end of the 5-year 
period within which local interests were required to furnish assurances 
of local cooperation. Authorization of these units, not 
included, expired on the dates indicated in Table 24-G. In FY 89, 
the Wahpeton-Breckenridge unit was included as part of the General 
Investigation program under Restudy of Deferred projects. 
24-28

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-J INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 45 of Text) 
Project Date Inspected 
Breckenridge, MIN ................................................. August 1989 
Eau Galle River, W I (M ines Creek Improvements) .......................................................................................................... September 1989 
Elk R iver, M N ...................................................................................................................... .. ... ...... ...................... A ugust 1989 
Enderlin, M aple River, ND ....................................... .. ....... .. ..... ..... .......... .............. August 1989 
Hanover, MN....................... .. . .......... ...... ...... . ................... ................ August 1989 
Maple River, ND........................... .................................... ............................................... August 1989 
Sheyenne River, ND......................................... .... . .......................... August 1989 
24-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 24-K FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public Law 858, 
80th Congress, as amended (preauthorization) 
Study/Project and Location Fiscal Year Costs 
Anoka, M N ............................................. .............. .............. $18,489 
Avoca, WI ........................................................................... .............. 10,554 
Beaver Lake, Stearns County, MN ......................................... ............................... 13,789 
Beebe Lake, Frankfort, MN ...................................... . ....... ........................... 18,211 
Cochrane, M ississippi River, W I ........................................................................... 138,253 
Gilmore Creek, M N ........................................................................... 12,586 
Granite Falls, M N ........................................................... ............... 10,778 
Kickapoo River, Viola, W I .................................................. ... ............... 429 
Lac qui Parle, MN ...................................................... 445 
Lake Charlotte, MN .............. .......... ............................................................. 17,835 
Lisbon, ND ........................................................................................................................... 21,274 
O w en, W I ............................................................................................................................................... ............ 18,433 
Pelican Lake, Frankfort, MN ........................................ ..................... 20,330 
Red River, Perley, MN ..................................... ................. 3,000 
Sanders Creek, Boscobel, W I ...................................................................................................... .................. 79,600 
Shell Lake, W I ......................................... .................... 2,703 
Sheyenne River, Harwood, ND......................................................... 360 
Snake River, A lvarado, M N ............................................... ....................................................... ....................... 52,722 
Trempealeau River, Arcadia, WI ....................................................................... 4,253 
Vermillion River, Farmington, MN ........................... . 423 
Emergency bank protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
Study/Project and Location Fiscal Year Costs 
County Hwy. 41 No.-MN R.-Mankato, MN ......................................................................................................... $5,766 
Grand Mound-St. Historical Site, MN ............................................................... 9,999 
H okah, M N ................................................................................................................................. .. .................... 20,727 
Wabasha, Mississippi River, MN ................................................................................................................... 6,850 
Warner Road at Sibley-St. Paul, MN ................................................................................................................ 19,179 
Zumbro River at Genoa, MN ............................................................ 3,371 
24-30

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-L GENERAL INVESTIGATIONS 
(See Sections 47, 48 and 49 of Text) 
Study Identification Fiscal Year Costs 
SURVEYS 
Flood Damage Prevention Studies 
Crookston, M N .............................................................. $14,955 
La C rosse, W I ........................................................................................................ . ................ 210,063 
M innesota River Basin, M N ................................................................................. ...................... 142,158 
Rainy River Basin, M N ......................... ........................................... 188,399 
Red River of the North, M N and ND ........................................................................... ............... 18,000 
Review of Authorized Projects 
Wahpeton-Breckenridge, MN ............................................ 92,168 
Miscellaneous Activities 
Special Investigations ....................................................................................................................... 47,914 
FERC Licensing Activities ......................................................................................... 1,610 
Intra Agency Water Resources Development ........................................................ 11,601 
Coordination with Other Agencies 
Soil Conservation Services .......................................................... 2,191 
B ureau of R eclam ation ............................................................................................................... 4,445 
Planning Assistance to States-M N .............................................................................. ................ 135,779 
Planning Assistance to States-ND .............................................................. 159,770 
Planning Assistance to States-W I.................................................................................. .................... 47,801 
TOTAL SURVEYS ....................................................... ...................... $1,076,853 
COLLECTION AND STUDY OF BASIC DATA 
International W ater Studies ......................................................................................... ................... 54,5841 
Flood Plain Management Services 
Flood Plain Management Services Unit .................................................... 116,215 
Technical Services, General ................................................................. 44,092 
Special Studies ............................................ ............... 50,152 
Hydrologic Studies 
Sedimentation Studies .................. ................................ ... ................... 46,000 
Stream Flow Data ...................... .................................................. 3,589 
TOTAL COLLECTION AND STUDY OF BASIC DATA ......................... ........................ $314,632 
ADVANCE ENGINEERING AND DESIGN 
Houston, M N ........................................ .............. ........ .............. 222,100 
M arshall, MN ................................................ ..... ........ ..................... 33,569 
Portage, W I ......................... ... ...... ........................................... ......................... ....................... 280,668 
Sheyenne River, N D ............................................................................................. ....................... 759,579 
St. Paul, MN ............................................. 479,221 
TOTAL ADVANCE ENGINEERING AND DESIGN ........................ ............................. $1,775,137 
Includes $45,804 for International Water Studies under O&M Appropriation. 
24-31

MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND MINNEAPOLIS, MN * 
Section of river covered in this report is divided into three 
reaches, under supervision and direction of District Engineers 
at St. Louis, Rock Island, and St. Paul. Section in St. Louis 
District extends 105 miles from Mouth of Missouri River to 
Location. Mississippi River rises in northern part of 
Minnesota, flows about 2,360 miles southerly and empties 
into Gulf of Mexico. Portion included in this report extends 
about 663 miles from mouth of Missouri River to Soo Line 
Railroad bridge, Minneapolis. Latest map and profile showing 
this section of river is in House Document 669, 76th 
Congress, 3d session. A map showing Lake Pepin is in 
House Document 511, 79th Congress, 2d session. A map of 
section Minneapolis to Dubuque is in House Document 515, 
79th Congress, 2d session. A map showing location of 
drainage districts (Bellevue, Iowa, to Missouri River ) is in 
River and Harbors Committee Document 34, 75th Congress, 
1st session. 
Previous projects. See page 1199 of Annual Report for 
1963. 
Existing project. Provides for a channel of 9-foot depth 
and adequate width between mouth of Missouri river (1,179 
miles from the gulf) and Soo Line Railroad at Minneapolis, 
by construction of a system of locks and dams, supplemented 
by dredging. Project also provides for further improvements 
at St. Paul to provide a basin extending 
downstream from Robert Street Bridge of 2.7 miles, and at 
Minneapolis to provide adequate terminal facilities, and for 
other harbor improvements and miscellaneous work. Pertinent 
data on locks and dams, harbor improvements, additional 
features entering into cost of project, and authorizing 
legislation are given in Tables 25-C, 25-D, 25-E and 25-G. 
All dams are concrete. Three dams (Upper St. Anthony 
Falls, 1 and 19) are fixed, remainder are movable. See 
House Document 669, 76th Congress, 3d session, for a 
report of Chief of Engineers Dated February 27, 1940, containing 
a general plan for improvement of Mississippi River 
between Coon Rapids Dam and mouth of Ohio River for 
purposes of navigation, power development, flood control, 
and irrigation needs. 
Local cooperation. Small-boat harbors authorized in the 
River and Harbor Act of 1962 are subject to conditions that 
local interests make a cash contribution toward cost of construction 
(except in case of Quincy Harbor which involves 
maintenance only of an existing harbor); furnish lands and 
rights-of-way for construction and future maintenance; 
hold the United States free from damages; provide and 
maintain mooring facilities and utilities; reserve accommodations 
for transient small boats; accomplish all 
Upper Mississippi River mile 300 above Ohio River; Rock 
Island District extends about 314 miles from mile 300 to 614; 
and St. Paul District extends about 244 miles from mile 614 
to Soo Line Railroad bridge, Minneapolis (mile 857.6). 
necessary relocations and alterations; and establish public 
bodies empowered to regulate use, growth and development 
of the harbors. 
Rectification of seepage damages to privately owned 
lands in the Sny Island Levee Drainage District, IL, is subject 
to the conditions that local interests acquire all lands, 
easements, and rights-of-way necessary for construction and 
maintenance of the project; comply with applicable provisions 
of the Uniform Relocation Assistance and Real Property 
Acquisition Policies Act of 1970; accept, operate, and 
maintain the project upon its completion; and hold and save 
the United States free from damages arising from the construction 
and operation of the completed project; provided 
further that the local public entity shall be reimbursed by the 
Government in the amounts actually expended by it in the 
acquisition of real estate and for payments required under 
Public Law 91-646 if said amounts have been previously 
submitted to and approved by the Government. 
Local cooperation requirements have been complied with 
for improvement of commercial harbor at Dubuque, IA; for 
improvement of Beaver Slough at Clinton, IA, for navigation; 
and for general navigation facilities at small-boat harbors 
at Rock Island, IL; Hannibal, MO; Fort Madison, IA; 
Davenport (Lindsay Park), IA; Muscatine, IA (including 
freight terminal approach channel); Andalusia, IL; Warsaw, 
IL; Moline, IL; Clinton, IA; and Savanna, IL. 
Licenses. Federal Energy Regulatory Commission collects 
from non-Federal licensees annually to recompensate 
the United States for use of government dams for generation 
of hydroelectric power. Amounts collected are returned to 
U.S. Treasury. (See table at end of chapter for license fees 
collected through the end of the fiscal year.) 
St. Paul District. New Work: Studies were continued 
under Section 107, small navigation project authority, for 
establishment of a small boat harbor at Guttenberg, Iowa at 
a cost of $224. 
Maintenance: Channel dredging to remove shoal areas 
was performed. Government pipeline dredge WILLIAM A. 
THOMPSON removed 2,796,406 cubic yards of material at 
38 locations at a cost of $888,663. Government derrick 
barge HAUSER/WADE removed 10,000 cubic yards of 
material at 1 location for $30,148. Government pipeline 
25-1

REPORT OF THE SECRETARY OF THE ARMY FOR CIVIL WORKS ACTIVITIES FOR FY 1989 
dredge DUBUQUE removed 30,337 cubic yards of material 
at 2 locations at a cost of $210,320. Mechanical dredging 
contractors removed 195,197 cubic yards of material at 16 
locations at a cost of $2,029,944. Dredging surveys cost 
$377,711. Other dredging and snagging cost $285,033. 
Water quality testing for dredging cost $77,365. 
Painting at locks and dams cost $504,899. Contracts for 
boundary surveys, general dam maintenance and general 
lock maintenance cost $32,162, $12,505 and $15,722, 
respectively. A contract to raise the service bridge at Lock 
and Dam 2 cost $2,617,442. Contracts for asbestos removal 
at all locks and dams for installation of lock machinery at 
Lock and Dam 2, and for scour repair at Lock and Dam 10 
cost $24,206, $139,100 and $1,822, respectively. A contract 
for rehabilitation of Blackhawk Park cost $386,349. Supply 
and equipment contracts for chains at Locks and Dams 
2,4,and 5 for gear reducers, for roller gate chains, for hoist 
machinery, for major maintenance supplies, and for lock 
operating machinery cost $206,661, $32,985, $262,838, 
$49,900, $520,962, and $78,690, respectively. Contracts for 
modification of tainter valves at Lock and Dam 1 for purchase 
of spare parts for locks, for a service bridge crane at 
Lock and Dam 2, for equipment replacement, for installation 
of septic and drain field at Locks and Dams 5 and 5A, 
for installation of a well at Lock and Dam 10 cost $17,427, 
$35,000, $90,893, $115,815, $36,611, and $30,351, respectively. 
Engineering work and miscellaneous surveys, 
reports, and other work were carried on by hired labor for 
$2,195,102 and by contract for $950,699. Other 
miscellaneous hired labor, supplies, and equipment cost 
$2,836,721. The total cost of maintenance was $15,094,046. 
Rehabilitation: A lock supply contract for Locks and 
Dams 3 and 5A-9, an electrical supply contract for Lock and 
Dam 6, and a supply contract for roller gate chains cost 
$37,845, $16,630, and $360,780 respectively. A contract to 
install lock machinery at Lock and Dam 3 cost $1,056,965. 
Engineering, administration, and other work were carried 
on by hired labor for $499,599 and by contract for $129,813. 
Total rehabilitation costs were $2,101,632. 
Operating and care: Locks and dams were operated as required, 
and necessary repairs were made to those and appurtenant 
structures. Other studies, reports, and 
miscellaneous engineering work were also accomplished. 
Total cost of operating and care was $9,765,674. 
Cost to St. Paul District were $224 for new work; 
$24,859,720 for operation and maintenance; and $2,101,632 
for rehabilitation, for a total of $26,961,576. 
Rock Island District. New Work: Work continued on 
Stage II, Rock Excavation, in Pool 15 with 78,685 cubic 
yards of rock and overburden being removed by contract at 
a cost of $611,700. 
Maintenance: Channel dredging by Government cutterhead 
pipeline dredge WILLIAM A. THOMPSON was 
performed at various locations in Pools 11, 16, 20 and 21 at 
a cost of $1,215,000 with 508,996 cubic yards of material being 
removed. Dredging inspection and reports were completed 
at a cost of $63,500. Snagging, clearing, and excavation 
was performed by hired labor at various locations at a 
cost of $284,700. Dredged material disposal activities and 
other environmental concerns in connection with dredging 
and channel maintenance activities cost $71,500. Repair of 
channel regulating works structures was performed at a cost 
of $1,955,500. Structural repairs, including sandblasting 
and painting, were performed by hired labor at locks and 
dams at a cost of $536,400. A strong-back to lift roller gate 
bulkheads for Locks and Dam 15 was constructed at a cost 
of $381,800. Repairs to spillways and dikes cost $91,400. 
Riprap repairs to the nonoverflow dike at Lock and Dam 12 
were completed at a cost of $464,800. Construction was 
completed on a new mooring cell upstream of Lock and 
Dam 12 at a cost of $5,800. Construction of bulkheads at 
Lock 13 was initiated at a cost of $283,800. The LeClaire 
Base Storage Yard was raised above the 50-year flood level 
and security improved at a cost of $154,700. Resurfacing of 
the access road to Lock and Dam 13 and Thompson 
Causeway cost $19,100 and $37,800 respectively.The Stage I 
contract for major maintenance to the dams at Locks and 
Dams 17 and 18 was continued at a cost of $3,110,600. The 
work includes repairs to the structural components of the 
dams, placement of additional rock fill upstream and 
downstream of the gated sections of the dam, repairs to the 
spillways, and removal of silt from the auxiliary lock bays. 
The Stage II major maintenance contract for electrical / 
mechanical system replacement at Lock 17 was initiated at 
$852,600. Shady Creek Public Use Area improvements included 
resurfacing of roads and relocating a sanitary dump 
station at a cost of $87,000. Repairs to boat ramps at Big 
Slough and Kilpeck Landing Public Use Areas were accomplished 
at a cost of $40,100. Camp pads were 
rehabilitated to Class A standards in Thompson Causeway 
Recreation Area at a cost of $38,500. Maintenance of roads 
and bridges, and of buildings, grounds and utilities cost 
$64,700. Maintenance of public use areas was performed at 
a cost of $671,500, and maintenance and purchase of permanent 
operating equipment cost $329,800. Maintenance of 
levees cost $74,400. Real estate activities relating to 
maintenance cost $123,600. Engineering and design work 
was performed at a cost of $1,137,900. Supervision administration 
and inspection for maintenance features cost 
$823,700. Total maintenance costs were $12,920,200. Net 
credits to the project were $1,311,000, primarily as a result 
of collection of damages from towboat companies to lock 
and dam structures. 
Operating and care: Operation of locks and dams and 
routine maintenance and minor repairs thereto were performed 
at a cost of $9,623,000. Real estate management services 
were performed at a cost of $191,400. Natural and 
cultural resource activities cost $248,200. Public use areas 
and Mississippi River Visitors Center were operated at a cost 
of $1,334,600 with contract law enforcement provided at a 
25-2

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
cost of $77,800. OSHA inspections and medical examinations 
were accomplished at a cost of $26,900. Surveys, 
various condition and operation studies, and structural inspections 
cost $1,778,000. Water control management costs 
were $707,000 and the amount of $600 was expended on 
Master Plans. Supervision and administration for operations 
features cost $295,000. Total operation costs were 
$14,282,500. 
Total operation and maintenance costs were $27,202,700. 
Rehabilitation: Rehabilitation continued at Locks and 
Dams 20, 21, and 22 at a cost of $7,110,567, $6,871,189, 
and $8,835,269, respectively. Total rehabilitation costs were 
$22,817,025. 
Costs to Rock Island District were $611,700 for new 
work; $27,202,700; for operations and maintenance; and 
$22,817,025 for major rehabilitation for a total of 
$50,631,425. 
St. Louis District. New work: Costs incurred for Melvin 
Price Locks and Dam, formerly Lock and Dam 26 replacement 
were $974,631 for real estate acquisition, $14,240,204 
for relocations, $310,930 for reservoir, $6,382,139 for the 
dam, $11,289,629 for the lock, $259,999 for channels, 
$694,035 for levees and floodwalls, $460,640 for buildings 
and utilities, $2,060,754 for permanent operating equipment, 
$2,910,552 for engineering, and $5,085,578 for supervision 
and administration. Costs incurred for 2nd lock were 
$41,295 for the lock, $2,068,513 for engineering and 
$207,831 for supervision and administration. Total cost of 
new work was $46,986,730. 
Operating and care: The locks and dams were operated as 
required, and necessary repairs were made thereto and to 
appurtenant structures at a cost of $3,586,031. 
Costs to St. Louis District were $46,986,730 for new work 
and $9,337,090 for operation and maintenance for a total of 
$56,323,820. 
Condition at end of fiscal year: For information pertaining 
to locks, dams, and harbors, see tables at end of chapter. 
St. Paul District. Work completed: Locks and Dams at 
St. Anthony Falls and 1 to 10, inclusive, except for relatively 
minor appurtenant work; major improvements of channels 
and harbors at St. Paul and Minneapolis; commercial harbors 
at Lake City, Red Wing, and Winona, MN; and Prairie 
du Chien, WI; small-boat harbors at St. Paul, Hastings, 
Red Wing, Wabasha, Lake City and Winona, MN; Lansing, 
IA; and Bay City, Pepin, and Prairie du Chien, WI; a 
remedial drainage ditch at Cochrane, WI; miscellaneous 
channel dredging and realignment; channel markers; pool 
clearing; and construction of various facilities for recreation 
use. Seepage damages totaling $90,027 were paid to 210 
claimants. 
Status of land and flowage acquisition; Approximately 
50,293.54 acres of land in fee, including 47,305 acres used 
by the Department of the Interior in accordance with a 
cooperative agreement and general plans, and easements of 
15,549.63 acres of land are owned or controlled in pools 1 to 
10, inclusive, at end of fiscal year. In addition, fee title to 
12.46 acres and perpetual easements on 2.98 acres of land 
for St. Anthony Falls and perpetual easements over 244.39 
acres of land for harbors have been obtained and Department 
of the Army holds special rights over 62,954.74 acres 
owned by Department of the Interior in pool Nos. 3 to 10, 
inclusive. Land acquisition is complete. 
Work remaining to complete portion of project in St. 
Paul District: Construction of small boat harbor at St. Paul 
(Harriet Island), MN and construction of additional recreational 
facilities. 
Condition of channel at end of fiscal year was such that 
controlling depths of nine feet at low water and minimum 
widths for long-haul common carrier service were available 
in all pools. Structures are in good condition. 
Rock Island District. Work completed: Major construction 
items including all locks and dams, are completed and 
in operation. The following related work has also been completed: 
Construction of small-boat harbors at Rock Island, 
IL; Moline, IL; Andalusia, IL; Warsaw, IL; Fort Madison, 
IA; Davenport (Lindsay Park), IA; Muscatine, IA; Clinton, 
IA; and Hanibal, MO; improvement of Beaver Slough at 
Clinton,IA, for navigation; improvement of commercial 
harbor at Dubuque, IA; rehabilitation of old auxiliary lock 
at Lock and Dam 14; permanent closure of old Lock 19 and 
drydock; rock and conglomerate excavation in Pool 16; rectification 
of seepage damage in the Sny Island Levee 
Drainage District, IL; recreational facilities; and construction 
of visitor center at Lock 15. 
Status of land and flowage acquisition: Acquisition of 
land in Pools 11 to 22, inclusive consisting of 93,601 acres in 
fee and 10,541 acres in flowage easement, has been completed. 
Condition of the channel at end of fiscal year, was such 
that controlling depths of nine feet at low water and widths 
suitable for long-haul common carrier service were being 
maintained in all pools. 
Work remaining to complete portion of project in Rock 
Island District: Construction of guidewall extension at 16, 
18, and 21; mooring facilities at 11, 12, 14, 15, 16, 17, and 
18; upper approach improvement at 19 and 20; rock and/or 
congolmerate excacation in Pools 14, 15, 18, and 21. Smallboat 
harbors at New Boston, IL, Bellevue, IA, Cassville, 
WI, Davenport (Credit Island), IA and Keokuk, IA are inactive, 
deferred or have been deauthorized. 
St. Louis District. Work completed: Locks and Dams 
24, 25, and Melvin Price Locks and Dam, except for 
guidewall extensions at Locks 24 and 25, have been completed 
as have recreation facilities at the three pools. 
Payments for rectification of damages have been completed. 
Other work remaining consists of construction guidewall ex- 
25-3

REPORT OF THE SECRETARY OF THE ARMY FOR CIVIL WORKS ACTIVITIES FOR FY 1989 
tensions at Locks 24 and 25. Melvin Price Locks and Darn 
are under construction. 
Status of land and flowage acquisition: Acquisitions of 
lands in Pools 24, 25, and 26, involving 4,448 acres of land 
in fee and flowage easements over 6,600 acres, is complete. 
A total of 3,561 acres has been acquired for the Melvin Price 
Locks and Dam project. 
Condition of channel at end of fiscal year was such that 
controlling depth of nine feet at low water and generally 
suitable widths for long-haul common carrier services were 
maintained in all pools and between Melvin Price Locks and 
Dam and Missouri River. 
Work remaining to complete portion of project in St. 
Louis District: Work remaining on the Melvin Price Locks 
TABLE 25-A COST AND FINANCI 
and Dam project includes completion of the second stage, 
(the 1200 foot lock and two half gatebays of the dam), and 
the third stage, (the 600 foot lock and 1 1/2 gatebays of the 
dam). Other work includes removal of the existing lock and 
dam, rerouting a railroad, and construction of the administration/
maintenance building and Visitor Center. Approximately 
286 acres remains to be acquired, of which 
1,391 acreas are for mitigation purposes for terrestrial 
wildlife loses. 
Total Federal costs of existing project to end of fiscal year 
for the three Districts was $133,916,821 of which 
$47,598,654 was for new work, $61,399,510 regular funds 
for operation and maintenance and $24,918,657 regular 
funds for rehabilitation. 
AL STATEMENT 
Total Cost to 
Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
Mississippi River New Work' 
between Missouri River Approp. 2 $84,345,770 $102,998,100 $72,364,918 $36,641,700 $863,211,621 
and Minneapolis, Cost' 86,217,056 83,924,837 72,366,650 47,598,654 855,576,703 
Minnesota (Federal Maint. 4 
Funds) Approp. 56,548,589 59,089,429 59,310,934 57,726,400 899,878,388 
Cost 52,049,293 50,351,678 56,948,760 61,399,510 879,216,649 
Rehab. 
Approp. 1,240,000 12,950,000 15,902,500 24,729,200 112,354,887 
Cost. 1,185,900 12,283,403 16,248,598 24,918,657 112,169,755 
(Contributed Funds) New Work 
Approp. 0 0 0 0 2,041,140 
Cost 0 0 0 0 2,041,140 
1. Includes $56,945,518 for new work on previous projects. 
2. Includes Melvin Price Locks and Dam funds $643,182,000. 
3. Includes Melvin Price Locks and Dam funds $621,038,461. 
4. Includes $8,504,026 for maintenance on previous project. 
TOTAL COSTS OF EXISTING PROJECT 
TABLE 25-B TO SEPTEMBER 30, 1989 
Regular Public Work Emergency 
District Cost Funds Funds Relief Funds Total 
St. Paul New Work' $ 60,145,9912 24,210,071 $ 9,071,214 $93,427,276 
Maintenance3 371,516,443 - - 371,516,443 
Rehabilitation 51,105,616 - - 51,105,616 
Total 482,768,050 24,210,071 9,071,214 516,049,335 
Rock New Work4 70,947,945' 17,403,322 11,338,865 99,690,132 
Island Maintenance6 321,743,133 - - 321,743,133 
Rehabilitation 61,064,139 - 61,064,139 
Total 453,755,217 17,403,322 11,338,865 482,497,404 
St. Louis New Work' 650,142,679' 10,282,566 2,440,266 662,865,511 
Maintenance 195,189,902 - - 195,189,902 
Total 845,332,581 10,282,566 2,440,266 858,055,413 
1. Excludes $2,041,140 contributed funds. Includes $7,673 expended in 
pool No. 11. 
2. Includes $159,359 transferred from Rock Island District covering pro 
rata share of cost of derrick boat Hercules. 
3. Includes $762,196 expended between 1930 and 1936 on operating and 
care of works of improvement under provisions of permanent indefinite 
appropriation for such purposes. Excludes $797,670 contributed funds. 
4. Excludes $58,999 contributed funds. 
5. $687,709 was transferred to St. Louis District in fiscal year 1958. Excludes 
$201,167 transferred to St. Paul and St. Louis Districts covering 
their pro rata share of cost of derrick boat Hercules. 
6. Costs subsequent to FY 1953 included with operating and care. 
Includes the sum of $395,442, expended between 1930 and 1934 on the 
operating and care of the works of improvement under the provisions of 
the permanent indefinite appropriation for such purposes. 
7. Includes $47,800 transferred from Rock Island District covering pro 
rata cost of derrick boat Hercules and $687,709 transferred from Rock 
Island District. 
8. Includes $621,038,461 for Melvin Price Locks and Dam. 
25-4

TABLE 25-C LOCKS AND DAMS 
Lock Dimensions 
Greatest Depth on Character of Foundation Percent 
Width Length Upper Miter Sill Complete 
Miles of Available Normal Locks, Year Estimated Cost of 
Above Chain- for Full Pool Dams, and Opened Each Lock and 
Ohio Miles from ber Width Lift Eleva- Upper Lower Work in to Navi- Dam Including 
Lock and Dam River Nearest Town (feet) (feet) (feet) tion' (feet) (feet) Lock Dam Pool gation Work in Pool 
St. Anthony 853.9 In city of 56 400 49.2 799.2 15.7 13.7 Some lime- Limestone. 100 - $ 18,203,000 
Falls, upper 
Lock 
St. Anthony 
Falls, lower 
Lock and dam 
Lock and dam 
1 
Lock and dam 
2 
Lock and dam 
3 
Lock and dam 
4 
Lock and dam 
5 
Lock and dam 
0 5A 
S Lock and dam 
6 
Lock and dam 
7 
Lock and dam 
8 
Lock and dam 
9 
Lock and dam 
10 
Lock and dam 
11 
Lock and dam 
12 
Lock and dam 
13 
Lock and dam 
14 
Le Claire Lock 
(Canal) 
Lock and dam 
15 
Lock and dam 
16 
Minneapolis, 
MN 
853.3 In city of 
Minneapolis, 
MN 
847.6 Minneapolis- 
St. Paul 
815.2 1.3 above 
Hastings, MN 
796.9 6.1 above Red 
Wing, MN 
752.8 Alma, WI 
738.1 Minneiska, MN 
728.5 3 above 
Winona, MN 
714.3 Trempealeau, 
WI 
702.5 Dresbach, MN 
679.2 Genoa, WI 
647.9 3.3 below 
Lynxville, WI 
615.1 Guttenberg, IA 
583.0 3.7 above 
Dubuque, IA 
556.7 Bellevue, IA 
522.5 4.3 above 
Clinton, IA 
493.3 3.7 below 
Le Claire, IA 
493.1 3.9 below 
Le Claire, IA 
482.9 Foot of Arsenal 
Island Rock 
Island. IL 
457.2 1.8 above 
Muscatine, IA 
stone, mainly 
sandstone. 
No piles. 
56 400 26.9' 750.0 13.7 10.3 Sandstone. No 
piles. 
56 400 35.9' 725.1 13.5' 10.1 Rock and piles 
56 400 35.9 - 12.5' 7.6 in gravel. 
110 500 12.2 - 16.0 15.1 Piles in sand, 
1108 6008 12.2 687.2 22.2 13.0 silt and clay. 
110 600 8.0 675.0 17.0 14.0 Piles in sand, 
silt and clay. 
110 600 7.0 667.0 17.0 13.0 Piles in sand 
and gravel. 
110 600 9.0 660.0 18.0 12.0 Piles in sand 
and gravel. 
110 600 5.5 651.0 18.0 12.5 Piles in sand. 
110 600 6.5 645.5 17.0 12.5 Piles in sand, 
gravel and 
silt. 
110 600 8.0 639.0 18.0 12.0 Piles in sand 
and gravel. 
110 600 11.0 631.0 22.0 14.0 Piles in sand, 
gravel and 
broken rock. 
110 600 9.0 620.0 16.0 13.0 Piles in sand. 
110 600 8.0 611.0 15.0 12.0 Piles in sand. 
110 600 11.0 603.0 18.5 12.5 Piles in sand, 
gravel and 
silt. 
110 600 9.0 592.0 17.0 13.0 Piles in sand 
and gravel. 
110 600 11.0 583.0 19.0 13.0 Piles in sand, 
clay and 
gravel. 
110 600 11.0 527.0 20.5 13.5 Rock. 
80 320 11.0 - 17.6 10.9 Rock. 
110 600 16.0 561.0 24.011 11.0 Rock. 
110 360 16.0 - 17.011 11.0 
110 600 9.0 545.0 17.0 12.0 Piles in sand 
Sandstone. 
Piles in gravel. 
Piles in sand, 
silt and clay. 
Piles in sand. 
Piles in sand 
and gravel. 
Piles in sand. 
Piles in sand. 
Piles in sand 
and clay. 
Piles in sand. 
Piles in sand 
and gravel. 
Piles in sand. 
Piles in sand. 
Piles in sand. 
Piles in sand 
and gravel. 
Piles in sand 
and gravel. 
Rock. 
Rock. 
Rock. 
Piles in sand 
and gravel, and gravel. 
100 1959 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
99 
99 
100 
92 
100 
96 
1917 
1930 
1948 
1938 
1935 
1935 
1936 
1936 
1937 
1937 
1938 
1936 
1937 
1938 
1938 
1939 
1922 
1934 
98 1937 
Cl) 
Cl) 
Cl) 
Cl) 
Cl) 0l 
0 
12,382,000' 
2,358,000' 
6,492,000' 
5,596,000 
4,865,000 
5,081,000 
4,549,000 
4,874,000 
5,574,000 
6,061,000 
6,539,000 
4,750,000 
7,428,000 
5,580,000 
7,502,000 
6,284,000 
10 
13,589,000 
9,788,000

TABLE 25-C (Cont'd) LOCKS AND DAMS 
Lock Dimensions 
Greatest Depth on Character of Foundation Percent 
Width Length Upper Miter Sill Complete 
Miles of Available Normal Locks, Year Estimated Cost o 
Above Cham- for Full Pool Dams, and Opened Each Lock and 
Ohio Miles from ber Width Lift Eleva. Upper Lower Work in to Navi Dam Including 
Lock and Dam River Nearest Town (feet) (feet) (feet) tion (feet) (feet) Lock Dam Pool gation Work in Pool 
Lock and dam 437.1 4.2 above New 110 600 8.0 536.0 16.0 13.0 Piles in sand Piles in sand. 99 1939 $ 5,843.000 
17 Boston. IL 
Lock and dam 410.5 6.5 above 
18 Burlington, 
IA 
Lock and dam 364.2 Keokuk, IA 
19 
343.2 0.9 above 
Canton, MO 
324.9 2.1 below 
Quincy, IL 
301.2 1.5 below 
Saverton. MO 
273.4 Clarksville. MO 
241.4 Cap Au Gris. 
MO 
202.9 Alton, IL 
200.8 Alton, IL 
200.8 Alton, IL 
Lock and dam 
20 
Lock and dam 
21 
Lock and dam 
22 
Lock and dam 
24 
Lock and dam 
N 25 
Lock and dam 
26 (Henry T. 
Rainey Dam) 
Melvin Price 
Locks and Dam 
Melvin Price 
Locks and Dam 
(2nd Lock) 
Total, Locks 
and dams 
110 600 
110 358 
110 1,200 
9.8 
and gravel. 
528.0 16.5 13.7 Piles in sand. Piles in sand. 
38.2 518.2 4.5 9.2 Rock. 
5.0 13.0 
Rock. 
110 600 10.0 480.0 15.0 12.0 Rock. Rock and 
piles in 
sand and 
gravel. 
110 600 10.5 470.0 16.5 12.0 Piles in sand Piles in sand 
and gravel, and gravel. 
110 600 10.2 459.5 18.0 13.8 Rock. Rock. 
110 600 15.0 449.0 19.0 12.0 Rock and piles. Piles in sand. 
110 600 15.0 434.0 19.0 12.0 Piles in sand Piles in sand 
and gravel, and gravel. 
110 600 24.0 419.0 19.0 10.0 Piles in sand. Piles and 
110 360 24.0 - 16.0 10.0 sand. 
110 1,200 24.0 419.0 23.0 18.0 Piles to 
bedrock. 
110 600 24.0 419.0 42.0 18.0 Piles to 
bedrock. 
Piles to 
bedrock. 
Piles to 
bedrock. 
90 
100 
99 
97 
95 
99 
1937 
1913 
1957 
1936 
1938 
1938 
9914 1940 
9914 1939 
100 1938 
81 - 
7 - 
f 
10,308.000 
bb 0
y
0 
14,813,00012 
6,281.000 v
I- 
8,065.000 ; 
5,275.000 O 
10,337.000 x 
13,694.000 ' 
12,824.000 
0
z 
746,010,000 
230,000,000 
$ 1,200,945,000 
1. Elevation of pools 1 to 22 and at St. Anthony Falls are mean sea level 9. In addition, $1,965,300 expended from previous projects. 
1912 adjustment: pools 24, 26 are mean sea level 1929 adjustment. 10. Existing Le Claire Canal lock is used as auxiliary to lock 14; previous 
2. Includes existing dam, owned by Northern States Power Co. project cost $540,000. 
3. Includes dredging above upper lock. (Federal cost only.) 11. Depth over upper poiree sill. Depth over upper miter sill is 27 feet, at 
4. Based on pool elevation 723.1 in pool 1 which is crest of dam. Pool is nor- lock 15. 
mally maintained at elevation 725.1 by flashboards. 12. $640,868 for first lock was reported by Mississippi River Power Company, 
5. Includes lower approach dredging and dredging between upper and lower transferred to Government free in lieu of improvements destroyed. (Annual 
rock. (Federal cost only.) Report, 1928, pp. 1118-1119.) Present estimate includes $13,132,600 for main 
6. In addition 81.948,000 expended from previous projects and 81,349,600 lock and appurtenant work. 
from O & C appropriation for first of twin locks. Excludes lock and dam 13. Includes cash contribution of $3,950,000. 
rehabilitation program. 14. Complete except for guidewall extensions. 
7. Old upper guard sill. 
8. Landward lock. 
0
r
O
cr 
yC12 
O
7d 0
pt 
o

TABLE 25-D HARBOR IMPROVEMENTS 
Miles above Project Approximate size (feet) Actual or 
Name Ohio River Location Type depth Percent Estimated 
(feet) Width Length Complete Cost 
Harriet Island Harbor, 
St. Paul, MN 
St. Paul Harbor, MN 
Hastings Harbor, MN 
Red Wing Harbor, MN 
Red Wing Harbor, MN 
Bay City Harbor, WI 
Lake City Harbor, MN 
Pepin Harbor, WI 
Wabasha Harbor, MN 
Alma Harbor, WI 
Winona Harbors, MN 
0J Lansing Harbor, IA 
Prairie du Chien 
Harbor, WI 
Cassville Harbor, WI 
Dubuque Harbor, IA 
Savanna Harbor, IL 
Clinton Harbor, IA 
Moline Harbor, IL 
Davenport Harbor, IA 
(Lindsay Park) 
Rock Island Harbor, IL 
Andalusia Harbor, IL 
Muscatine Harbor, IA 
New Boston Harbor, IL 
Fort Madison Harbor, 
IA 
840.2 In city of St. Paul, MN 
836.5-839.2 In city of St. Paul, MN 
839.7 Channel improvement, 
Small-boat harbor and 
channel enlargement. 
813.2 Lower end of city of 
Hastings, MN 
791.4 In city of Red Wing, MN 
791.1 In city of Red Wing, MN 
785.9 Upper end of Bay City, 
WI 
773.0 In city of Lake City, MN 
767.1 In city of Pepin, WI 
760.0 Upper end of city of 
Wabasha, MN 
751.3 Upper end of Alma, WI 
726.0 In city of Winona, MN 
Latsch Island 
726.2 Crooked Slough 
663.3 Upper end of city of 
Lansing, IA 
635.5 Upper end of city of 
Prairie du Chien, WI 
635.0 In Marais de St. Friol 
East Channel below 
Hwy bridges. 
606.6 At Cassville, WI 
579.4 At Dubuque, IA 
537.3 At Savanna, IL 
519.0 At Clinton, IA 
488.0 At Moline, IL 
484.2 At Lindsay Park 
479.8 
473.0 
455.5 
455.6 
433.1 
383.7 
At Rock Island, IL 
Andalusia Slough 
At Muscatine, IA 
In Boston Bay 
At Fort Madison, IA 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Commercial' 
Small-boat' 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Entrance channel 
small-boat harbor 
Small-boat 
Small-boat 
Freight terminal 
approach channel 
Small-boat 
Small-boat 
70 
9 400-1,000 
5 300 
200 
300 
450 
50-100 
400 
500 
500 
50 
175-400 
300 
200 
200 
170 
400 
925 0 $ 306,000' 
2.7(mile) 
400 
100 
100 
500 100 
1,200 
800 
5,990 
600 
1,000 
850 
600 
800 
500 
1,000 
6,000 
500 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
800 100 
1,000 
frontage 
5 
12
5555 
120 
340 
280 
400 
230 
200 
100 
40 
150 
200 
90-135 
250 
565 
1,500 
910 
1,400 
660 
1,150 
1,100 
435 
950 
1,890 
600 
900 
100
0 
100
0 
78 
100 
100 
100 
100 
100
0 
100 
217,100 
230,200 
74,300 
146,800' 
8,700 
39,400 , 
93,500 9 
1,077,000' a 
205,500' 
41,700 pa 
56,300 - 
89,800 
84,700 z 
95,300 
rJ) 
85,500 0 
93,100 
z 
178,000 
55,200 z 
310,000 Z 
101,912 
110,328 's 
262,100 
31,000 g
z 
21,000 
353,000 
23,000 
184,200

TABLE 25-D (Cont,d) HARBOR IMPROVEMENTS 
Project Approximate size (feet) Actual or 
Name Mies aboRive Location Type depth Percent Estimated 
(feet) Width Length Complete Cost 
Keokuk Harbor, IA 363.5 At Keokuk, IA Small-boat 5 100-600 1,015 0 394,00 
Warsaw Harbor, IL 359.1 At Warsaw, IL Small-boat 5 100 600 100 73,0C 
Quincy Harbor, IL 327.3 In Quincy Bay, IL Small-boat 5 200-300 9,000 0 
Hannibal Harbor, MO 308.8 At Hannibal, MO Small-boat 5 180-260 600 100 129.0( 
Total $5,170,64 
I. In addition, local interests will contribute $306,000. 
2. In addition, local interests contributed $3,455. 
3. In addition, local interests contributed $9,533. 
4. Commercial harbor converted to small-boat harbor under authority 
of Section 107 of 1960 River and Harbor Act, as amended. Primary use 
is small-boat, although some commercial activity exists. 
5. In addition, local interests contributed $812,599. 
6. In addition, local interests contributed $32,344. 
7. Maintenance only, estimated at $5,000 annually. 
3O 
)0 
I0 
1,, 
00 
00 
5a 
b
O
-l 
O
0
r
y
31 
m
$1, 
C, 
0
y
m 
O
z
r
O
C) 
H
r' 
O 
o

TABLE 25-E 
MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
ADDITIONAL FEATURES ENTERING INTO 
COST OF PROJECT 
Facilities for public use, convenience and safety 
Rectification of damages caused by seepage and backwater 
Regulating works between Melvin Price Locks and Dam and Missouri River 
Improvement of Beaver Slough at Clinton, Iowa, for navigation 
Miscellaneous 
Total additional features 
Total existing project (new work) 
$ 9,172,700 
8,366,400' 
545,000 
193,600 
3,624,9002 
18,705,900' 
516,183,512 
1. Includes a lump-sum payment of $2,146,800 (O&M appropriation) paid 
to the Sny Island Levee Drainage District, IL, for rectification of seepage 
damages. Also includes $140,000 Construction General funds for project 
studies, evaluation, and report preparation. 
2. Includes $686,500 for repairs to Stone Arch Bridge, Minneapolis, MN. 
(FY 1969) 
3. Excludes $227,000 (1965) for inactive remedial measures at Sandy 
Slough, MO. 
LICENSE FEES COLLECTED 
TABLE 25-F THROUGH FISCAL YEAR 1989
Annual Collections to 
Dam Licensee Charge Sept. 30, 1989 
St. Anthony Falls Lower Northern States Power $ 3,300 $ 89,977 
Lock and Dam Co. (No. 2056) 
Lock and Dam No. 1 Ford Motor Co. 95,400 6,107,640 
Total project (No. 362) 6,197,617 
25-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 25-G AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sep. 22, 1922 
July 3, 1930 as 
amended by P.R. 
No. 10, Feb. 24, 
1932 
June 26, 1934 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 30, 1935 
Aug. 2(, 1937 
l)cc. 22, 1944 
Mar. 2, 1915 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
None 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
M ay 17, 1950 
May 17, 1950 
Sep. 3, 1954 
Sep. 3, 1954 
July 3, 1958 
July 3, 1958 
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND 
MINNEAPOLIS, MN 
Dredging channels to landing places. 
Project adopted from Illinois River to Minneapolis; Chief of 
Engineers granted discretionary authority to make such 
modification in plan as may be deemed advisable.4 
Operation of snag boats and operation and care of locks and dams 
to be provided for with funds from Department of the Army 
appropriations for rivers and harbors. 
Missouri River established as lower limit of project. 
Extension of 9-foot channel above St. Anthony Falls, MN, 
including adequate terminal facilities for Minneapolis, MN 
St. Paul, MN harbor. 
I)etermine damages to drainage and levee districts caused by 
seepage and backwater, and cost of making rectification thereof. 
Public park and recreational facilities. 
Red Wing, MN harbor. 
Remedial works to correct damages caused by seepage and 
backwater at Cochrane, WI 
Such changes or additions to payments, remedial works, or land 
acquisitions authorized by River and Harbor Act of Aug. 26, 
1937 (River and Harbor Committee Doc. 34, 75th Cong., 1st 
sess.), as Chief of Engineers deems advisable. 
St. Paul, MN channel enlargements, small boat harbor, and 
roadway. 
Vertical bridge clearance at Minneapolis to 26 feet above 
estimated stage for discharge of 40,000 c.fs. 
Winona, MN basin. 
Future mnodifiication of lock and dam No. 2 for power 
development. 
Provides for cash contribution by local interests in lieu of 
alteration of privately owned bridges and utilities for St. 
Anthony Falls prject. 
Lake City, MN harbor. 
Wabasha, MN harbor. 
Payment of damages caused by backwater and seepage, pools 3 
to 11. 
Hastings, MN harbor. 
Lansing, IA harbor. 
Fort Madison, IA harbor. 
Payment of damages caused by pool No. 14 at Clinton, IA. 
Davenport, IA harbor. 
Muscatine, IA harbor. 
Alma, WI harbor. 
Hannibal, MO harbor. 
Prairie du Chien, WI harbors. 
Opposite llnmburg, IL harbor.' 
Permits such change in location of Winona, MN small boat basin 
authorized by River and Harbor Act of Mar. 2, 1945 (1I. Doc. 
263, 77th Cong., 1st sess.), as Chief of Engineers deems advisable. 
Construction of Crooked Slough Harbor at Winona, MN, in lieu 
of previously authorized commercial harbor. 
Payment of damages caused by pool No. 24 at Louisiana, MO. 
Permits modification of vertical bridge clearances and authorizes 
completion of St. Anthony Falls project. 
Small boat and commercial harbors at Alton, IL.' 
None 
H. Doc. 290, 71st Cong., 2d sess. 
None 
H. Doc. 137, 72nd Cong., 1st sess. 
H. Doc. 137, 72nd Cong. let 
sess. 
Rivers and Harbors Committee 
Doc. 44, 74th Cong., 1st sess. 
Rivers and larbors Commnittee 
Doc. 34, 75th Cong., 1st sess. 
None 
II. I)oc. 103, 7(ith (ong., lt 
sess. 
H. Doc. 137, 76th Cong., 1st 
sess. 
None 
H. Doc. 547, 76th Cong., 3rd 
sess. 
S. Doc. 54, 77th Cong., 1st sess. 
H. Doc. 263, 77th Cong., 1st 
Bess. 
II. I)oc. 4:12, 77th Cong., Ist 
sess. 
H. Doc. 449, 78th Cong., 2d sess. 
H. Doc. 511, 79th Cong., 2d1 seas. 
H. Doec. 514, 79th Cong., 2d1s ess. 
H. Doc. 515, 79th Cong., 2d sess. 
H. Doc. 559, 79th Cong., 2d sess. 
S. Doc. 192, 79th Cong., 2d seas. 
H. Doc. 661, 80th Cong. 2d seas. 
S. Doc. 197, 80th Cong., 2(1 sess. 
H. Doc. 642, 80th Cong., 2d sess. 
H. Doc. 733, 80th Cong., 2d seas. 
H. Doc. 66, 81st Cong., 1st seas. 
H. Doc. 67, 81st Cong., 1st seas. 
HI. Doc. 71, 81st Cong., 1 st sess. 
II. D)oc. 254, 81st Cong., Ist sess. 
None 
H. Doc. 347, 83rd Cong., 2d 
sess. 
H. Doc. 251, 82nd Cong., 1st 
seas. 
H. Doc. 33, 85th Cong., 1st sess. 
H. Doc. 136, 84th Cong., Ist sess. 
25-10

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
T ABLE 25-G (Cont'd) AUTHORIZING LEGISLATION 
Acts 
July 3, 1958 
July 3, 1958 
Mar. 3, 1959 
.July 14, 1960 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 7, 1966 
Oct. 21, 1978 
Dec. 29, 1981 
Work Authorized 
Payment of lump sum amounts for damages to drainage and levee 
districts caused by operation of navigation pools. 
Improvement and maintenance of Beaver Slough at Clinton, IA. 
Reconstruction of structures as may be necessary to provide 
adequate facilities for existing navigation. 
Construction of Industrial Harbor at Red Wing, MN. 
Construction of small-boat harbors at Savanna, Moline, 
Andalusia, New Boston,' Warsaw, Quincy, and Grafton, IL; 
Bellevue,' Clinton, Davenport, and Keokuk, IA; St. Paul 
(Harriet Island), MN; and Bay City, Pepin, and Cassville,' WI. 
Payment of damages caused by pool 24 at Clarksville, MO. 
Remedial works at Sandy Slough, MO. 
Repair of Stone Arch Bridge at Minneapolis, MN. 
Replacement of Lock and Dam 26 
Change name of Lock and Dam 26 to Melvin Price Locks and Dam 
effective on the date of Melvin Price's death. (Apr. 22, 1988 - date of death) 
Documents 
H. Doc. 135, 84th Cong., 1st 
sess. 
H. Doc. 345, 84th Cong., 2d sess. 
None 
H. Doc. 32, 86th Cong., 1st sess. 
H. Doc. 513, 87th Cong., 2d sess. 
H. Doc. 552, 87th Cong., 2d sess. 
H. Doc. 419, 87th Cong., 2(1 scss. 
None 
Public Law 95-502 
Public Law 97-118 
1. Deferred. 
2. Inactive. 
3. Deauthorized FY 87 (WRDA of 1986). 
4. Guidewalls at Locks 3, 4, 5, 5A, 7, 8, 9, and 10 deauthorized FY 87 (WRDA of 1986). 
25-11

OMAHA, NE, DISTRICT * 
This district comprises portions of Montana, Wyoming, 
North Dakota, South Dakota, Minnesota, Colorado, 
Nebraska, Iowa, and Missouri, all embraced in 
drainage basin of Missouri River along main stem and 
tributraries to Rulo, NE. 
IMPROVEMENTS 
Navigation Page 
1. Missouri River, Sioux City, IA 
to Rulo, NE ................................. 26-2 
2. Navigation Work Under Special 
Authorization .............................. 26-2 
Flood Control 
3. Bear Creek Lake, CO .................... 26-2 
4. Bowman-Haley Lake, ND .................... 26-2 
5. Chatfield Lake, CO ........................ 26-2 
6. Cherry Creek Lake, CO ..................... 26-3 
7. Fall River Basin, SD ....................... 26-3 
8. Great Falls, MT ................ ..... 2.....6-3 
9. Little Sioux River, IA ....................... 26-3 
10. Lost Creek at Columbus, NE ................. 26-4 
11. Lower Heart River, Mandan, ND .......... 26-4 
12. Missouri National Recreational 
River, NE and SD ........................... 26-4 
13. Missouri River, Kenslers Bend, 
NE to Sioux City, IA ........................ 26-4 
14. Missouri River Levee System, 
Sioux City, IA to Rulo, NE .................. 26-4 
15. Papillion Creek and Tributaries 
Lakes, NE .................................. 26-5 
16. Pebble Creek, Scribner, NE ................. 26-5 
17. Pick-Sloan Missouri River Basin 
Program (Omaha Dist) ....................... 26-5 
18. Pipestem Lake, ND .......................... 26-5 
19. Salt Creek & Tributaries, NE ................ 26-5 
20. South Platte River Basin, CO................. 26-6 
21. Inspection of Completed Flood 
Control Works ......................... 26-6 
22. Scheduling Flood Control 
Resrvoir Operations ......................... 26-6 
23. Flood Control Activities Under 
Special Authorization ........................ 26-6 
Multiple Purpose Projects Including Power Page 
24. Big Bend Dam-Lake Sharpe, 
Missouri River Basin, SD ................ 26-6 
25. Fort Peck Lake, MT .................... 26-6 
26. Fort Randall Dam-Lake Francis Case, 
Missouri River Basin, SD ................ 26-7 
27. Garrison Dam-Lake Sakakawea, 
Missouri River Basin, ND ................... 26-7 
28. Gavins Point Dam-Lewis and Clark Lake, 
Missouri River Basin, NE and SD............26-7 
29. Oahe Dam-Lake Oahe, Missouri 
River Basin, SD and ND ................... 26-7 
Miscellaneous 
30. National Emergency Preparedness ............ 26-8 
General Investigations 
31. See Table 26-K ............................ 26-8 
Tables 
26-A Cost and Financial Statement ............. 26-9 
26-B Authorizing Legislation ................ 26-12 
26-C Other Authorized Navigation Projects ...... 26-15 
26-D Not Applicable 
26-E Other Authorized Flood Control Projects...26-15 
26-F Other Multiple Purpose Projects 
Including Power ......................... 26-17 
26-G Deauthorized Projects .................... 26-17 
26-H Missouri River Levee System, 
Sioux City, IA to Rulo, NE .............. 26-18 
26-I Pick-Sloan Missouri Basin Program.......26-18 
26-J Inspection of Completed Local 
Protection Projects ....................... 26-18 
26-K Active General Investigations ........... 26-21 
26-L Flood Control Activities 
Under Special Authorization .............. 26-22 
26-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA 
TO MOUTH (SIOUX CITY, IA 
TO RULO, NE) 
Location. Channel of the Missouri River extending 
from Sioux City, IA to Rulo, NE. 
Previous projects. For details see page 1893, Annual 
Report for 1915, and page 1175, Annual Report for 1938. 
Existing project. Provides for a navigation channel of 
9-foot depth and width not less than 300 feet, obtained by 
revetment of banks, rock dikes to contract and stabilize 
waterway, cutoffs to eliminate long bends, closing minor 
channels, and removal of snags and dredging as required. 
Construction was initiated on this section of the project 
(Sioux City to Rulo) in fiscal year 1928, the bank stabilization 
work was completed in April 1979, and the navigation 
feature was completed in September 1980. A reliable 
channel suitable for navigation is available through this 
section. Controlling depth at ordinary stages of the river is 
9 feet, with additional depths available during high stages. 
Commercial navigation was inaugurated on this section in 
May 1939, and common carrier transportation service 
was inaugurated in October 1946. Seven riverside recreation 
sites are complete and in operation. Total cost of new 
work Sioux City, IA to Rulo, NE is $189,226,000 (1989), 
of which $187,639,000 is the Federal cost of construction 
and $1,587,000 is the non-Federal cost, exclusive of 
amounts expended on previous projects. 
Local cooperation. Requirements are described in full 
on page 26-2 of fiscal year 1988 Annual Report. 
Terminal facilities. Terminal facilities for loading and 
unloading grain, liquids and dry bulk products are maintained 
by private interests at various locations on this 
section of the river. A complete list of terminal facilities 
are included in the Missouri River. Navigation Maps and 
can be obtained from the Omaha District for a small fee. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Local interests 
operate and maintain the recreation sites. 
2. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Small Navigation Projects Not Specifically Authorized 
by Congress (Sec. 107 of the River and Harbor Act of 
1960, as amended, Public Law 645, 86th Congress). 
No work during the period. 
Flood Control 
3. BEAR CREEK LAKE, CO 
Location. Damsite is on Bear Creek in Jefferson 
County, CO about 8 miles above the confluence of Bear 
Creek with the South Platte River at Denver. 
Existing project. Earthfill dam 180 feet high, with a 
crest length of about 5,300 feet, and a supplementary 
earthfill dike with a height of 65 feet and a crest length of 
2,100 feet, to the south of the main dam, and an uncontrolled 
earth and rock-cut emergency spillway. The lake 
provides storage capacity of 28,831 acre-feet for flood 
control and 1,979 acre-feet for sediment and recreation. 
Construction of the project was initiated in October 1973 
and was completed in September 1982, exclusive of recreation 
facilities. The total cost of construction was 
$61,503,600. Recreation facilities were developed utilizing 
cost sharing funds at an additional cost of $500,000. 
Local cooperation. Requirements are described in full 
on page 21-3 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Initiated investigation of 
contractor claim. Maintenance: Continued routine operation 
and maintenance activities. Annual project visitation 
hours were estimated at 460,300. 
4. BOWMAN-HALEY LAKE, ND 
Location. Damsite is on North Fork of Grand River in 
southwestern North Dakota, about 6 miles above Haley, 
ND. 
Existing project. A dam 79 feet high, with a crest length 
of 5,730 feet, and reservoir with a storage capacity of 
about 19,780 acre-feet for sediment storage, fish and wildlife 
conservation, recreation, and future water supply for 
communities of Bowman, Reeder, Scranton, and Gascoyne, 
ND. Construction was initiated in July 1964, and 
the project was completed in 1970. (See Table 26-A for 
total cost of construction.) 
Local cooperation. Requirements are described in full 
on page 26-2 of fiscal year 1988 Annual Report. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Annual project 
visitation hours were estimated at 126,600. 
5. CHATFIELD LAKE, CO 
Location. On the South Platte River, just below the 
mouth of Plum Creek, about eight miles upstream from 
Denver, CO. 
Existing project. Consists of rolled earth-fill dam with a 
maximum height of 148 feet, a crest length of 12,500 feet, 
and a reservoir with flood control capacity of 204,737 
acre-feet and sediment capacity of 26,692 acre-feet, which 
will be used for recreation, and an enlarged channel from 
the dam downstream to Denver to accommodate reservoir 
flood releases. 
The Corps is participating with local interests in acquisition 
of lands and development of recreation facilities 
immediately downstream of the Chatfield Dam in lieu of a 
portion of the channel improvement. Construction of the 
project was initiated in August 1967 and is 99 percent 
complete, with a scheduled completion date in FY 1990. 
Construction is essentially complete at the project with 
the exception of the downstream channel improvement, 
associated recreation facilities and fish and wildlife mitigation 
measures. Estimated cost through construction of 
the project is $104,700,000 (1989) of which $95,400,000 is 
the Federal cost for construction, $6,400,000 local cost in 
connection with the downstream channel improvement, 
and $2,900,000 is the local cost for acquisition of water for 
the recreation pool. 
26-2

OMAHA, NE, DISTRICT 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies to the downstream channel improvement. 
The Colorado Water Conservation Board 
provided assurances of local cooperation for the downstream 
improvement on December 13, 1967. Local interests 
must provide water for filling the sediment reserve 
pool for recreation use which the state agreed to on April 
_25, 1967. 
Operations during fiscal year. Continued design by 
hired labor. Continued work on O&M manuals. Continue 
downstream channel recreation facilities. Maintenance: 
Continued routine operation and maintenance activities. 
Annual project visitation hours were estimated at 
3,801,700. 
6. CHERRY CREEK LAKE, CO 
Location. Damsite is on Cherry Creek in Arapahoe 
County, CO, approximately 6 miles southeast of Denver, 
CO just outside of city limits. Cherry Creek joins South 
Platte River within city limits of Denver. 
Existing project. A rolled earth-fill dam with maximum 
height of 141 feet above streambed and 14,300 feet long. 
Project includes a reinforced concrete outlet works and an 
uncontrolled side channel spillway canal discharging into 
adjacent Toll Gate Creek. Cherry Creek project provides 
reservoir storage capacity of 93,920 acre-feet below spillway 
canal invert and, in addition, a surcharge storage of 
134,470 acre-feet. Plan of operation in ultimate development 
for multiple-purpose uses includes 13,960 acre-feet 
for sediment storage and 79,960 acre-feet for conservation 
purposes. Construction began in fiscal year 1946 and was 
completed in June 1961, exclusive of recreation facilities. 
Federal cost of the project was $15,220,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Annual project 
visitation hours were estimated at 6,060,300. 
7. FALL RIVER BASIN, SD 
Location. In Custer and Fall River Counties, in and 
near the town of Hot Springs, SD. Hot Springs unit is in 
the town of Hot Springs, immediately south of the junction 
of Cold Brook and Hot Brook which combine to 
form the Fall River. Cold Brook Lake unit is approximately 
1.25 miles north of the town of Hot Springs on 
Cold Brook; and Cottonwood Springs Lake unit is approximately 
4.5 miles west of the town of Hot Springs on 
Cottonwood Springs Creek, one-half mile upstream from 
its confluence with Hot Brook. 
Existing project. The general plan of improvement 
provides flood protection for Hot Springs, SD. The Hot 
Springs channel improvement unit consisted of widening, 
deepening and straightening 6,000 feet of channel of Fall 
River. The Cold Brook Lake unit, an earth-fill dam with 
appurtenant structures, controls an area of 70.5 square 
miles. The Cottonwood Springs Lake unit consists of an 
earth-fill dam with appurtenant structures and controls an 
area of 26 square miles. Construction of Hot Springs unit 
was completed during fiscal year 1951. Construction of 
Cold Brook unit dam and appurtenances was completed 
in fiscal year 1953 with exception of a road and parking 
area which were completed in fiscal year 1955. Construction 
of the Cottonwood Springs unit dam was completed 
in fiscal year 1970, with the exception of the recreation 
facilities which were completed in fiscal year 1972. (See 
Table 26-A for total cost of construction.) For last funding 
see FY 1981 Annual Report. 
Local cooperation. Local cooperation requirements 
have been fully complied with. 
Operations during fiscal year. Maintenance: Routine 
operation and maintenance activities were continued on 
the Cottonwood Springs and Cold Brook Dams and structures. 
Annual project visitation hours were estimated at 
449,100. 
8. GREAT FALLS, MT 
Location. In Great Falls, Cascade County, MT at confluence 
of the Sun and Missouri Rivers. 
Existing project. Provides for levees along the left bank 
of the Sun River and an interceptor ditch and closed conduit 
to collect and convey side-hill runoff to the Sun 
River. Estimated cost through construction of the project 
is $13,962,000 of which $11,912,000 is the Federal cost of 
construction and $2,050,000 is the local cost for lands, 
relocations and a cash contribution for replacement of a 
storm sewer conduit desired by local interests. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. In addition, local interests must 
zone the unleveed portion of the flood channel through 
the damage area to preserve its capacity and to prevent 
further encroachments and contribute in cash $179,000 
representing the estimated cost of replaced storm drainage 
facilities which will be incorporated into the closed conduit 
of the Watson Coulee Interceptor. West Great Falls 
Flood Control and Drainage District provided assurances 
on January 17, 1968, State Supreme Court decision on 
assessments required a change in state law, which was 
enacted in 1973. The final court ruling on compliance was 
made April 1, 1981, and the local sponsor was instructed 
to proceed toward project construction. 
Operations during fiscal year. Work continued on the 
O&M manuals. 
9. LITTLE SIOUX RIVER, IA 
Location. The project is located in the lower portion of 
the Little Sioux River Basin in Harrison and Monona 
Counties, IA, near the confluence of the Little Sioux and 
Missouri River. 
Previous project. For details see page 646, Annual Report 
for 1970. 
Existing project. Construction of the original project 
was completed in June 1966. Sill No. 4 was identified as a 
design deficiency in a June 17, 1981 report by the Omaha 
District, approved by OCE. Based on that report, design 
studies for a permanent solution to the problem were 
completed. Estimated cost through construction of the 
project is $23,630,000 (1989) of which $20,630,000 is the 
26-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Federal cost of construction, and $3,000,000 is the local 
cost for lands, relocations, and associated E&D. 
Local cooperation. The Little Sioux Inter-County 
Drainage District was sponsor of that portion of the original 
project where the remedial work is being accomplished. 
Remedial work was 100 percent Federally funded. 
Operations during fiscal year. Work continued on 
O&M manuals. 
10. LOST CREEK AT COLUMBUS, NE 
Location. On Lost Creek just north of the City of 
Columbus in Platte County, NE. 
Existing project. This project provides levee and channel 
improvements on the north side of Columbus and 
provides protection to commercial and residential areas. 
The estimated cost of the construction is $4,480,000 
(1989) of which $3,620,000 is the Federal cost, and 
$860,000 is non-Federal contributed funds - other, that 
provides for all necessary right of way, utility, and bridge 
relocations. 
Local cooperation. A contract with the City of Columbus 
to sponsor the project was approved on February 18, 
1982. 
Operations during fiscal year. Requested funds for use 
in analyzing contractor claim and to prepare O&M manuals 
for the project. 
11. LOWER HEART RIVER, MANDAN, ND 
Location. Mandan, North Dakota, is located just upstream 
from the confluence of the Missouri and Heart 
Rivers in Morton County, adjacent to Bismarck, North 
Dakota. The Heart River is a right-bank tributary to the 
Missouri River. 
Existing project. The plan includes raising a 7,150-foot 
reach of the Mandan Unit of the existing levee an additional 
1-1/2 to 2 feet to provide a full three feet of freeboard 
above the 100-year ice-affected event; raising a 
12,300-foot reach of the Lower Unit four to five feet to 
provide three feet of freeboard above the SPF ice-affected 
event; and continued zoning and flood insurance for the 
unprotected portions of the Lower Unit. 
Local cooperation. The Lower Heart River Water Resources 
District (LHRWRD) is the non-Federal sponsor 
of the project. The LHRWRD has obtained cost-sharing 
assistance from the North Dakota State Water Commission. 
Operations during fiscal year. Construction was completed 
in September 1989. The total estimated cost of the 
project is $1,568,100. The non-Federal portion of this cost 
is $333,000 which includes $69,300 for lands, easements 
and rights-of-way. 
12. MISSOURI NATIONAL RECREATIONAL 
RIVER, NE AND SD 
Location. NE and SD. The Missouri River between 
Gavins Point Dam and Ponca State Park, NE. This includes 
Cedar and Dixon Counties in Nebraska, and Yankton, 
Clay, and Union Counties in South Dakota. 
Existing project. The designation as a National Recreational 
River will preserve outstanding and important 
scenic values and will provide additional opportunities for 
river access and recreation use. Erosion control, consisting 
of bank stabilization and river management techniques 
designed to preserve the existing environment, will 
at the same time preserve high bank flood plain lands. 
Estimated total cost of construction is $21,633,000 (1989) 
of which $21,000,000 is the Federal cost of construction 
and $633,000 is the non-Federal contributed funds - 
other costs. 
Local cooperation. All construction on this project will 
be done in accordance with the cost sharing and financing 
concepts reflected in the Water Resources Development 
Act of 1986. A cost-sharing contract with the State of 
South Dakota for the Myron Grove access site was signed 
on June 24, 1986 and the Yankton-Riverside Park Section 
215 Agreement was signed on April 24, 1989. 
Operations during fiscal year. Efforts to protect Federally 
listed threatened and endangered species continued. 
13. MISSOURI RIVER, KENSLERS 
BEND, NE, TO SIOUX CITY, IA 
Location. Project is along Missouri River between 
Ponca Bend, NE, and combination bridge at Sioux City, 
IA.
Existing project. Construction of dikes, revetments and 
channel improvement along Missouri River from Miners 
Bend and vicinity, SD and NE, to Sioux City, IA. Project 
was started in June 1946 and completed in June 1961. (See 
Table 26-A for total costs.) 
14. MISSOURI RIVER LEVEE SYSTEM, 
IOWA, NEBRASKA, KANSAS AND 
MISSOURI (SIOUX CITY, IA 
TO RULO, NE) 
Location. On both banks of the Missouri River from 
Sioux City, IA to St. Louis, MO. Active portion of the 
project in Omaha District extends from Council Bluffs, 
IA to Rulo, NE. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from 
Sioux City, IA, to mouth, for protection of agricultural 
lands and small communities against floods. Construction 
was initiated June 1948. (See Table 26-H for status of 
active units). Cost estimate for active portion of project 
from Council Bluffs, IA to Rulo, NE is $42,549,000 (1988) 
of which $37,931,000 is Federal cost for construction and 
$4,618,000 local costs for lands and damages. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. Fully complied with for all completed 
units. Local interests have furnished assurances of 
their willingness and ability to fulfill local cooperation 
requirements for the remaining active units. 
Operations during fiscal year. Completed construction 
on Levee Unit L-611-614. Continued work on O&M 
manuals for Levee Unit L-611-614. 
26-4

OMAHA, NE, DISTRICT 
15. PAPILLION CREEK AND 
TRIBUTARIES LAKES, NE 
Location. The Papillion Creek basin is located in Washington, 
Douglas, and Sarpy Counties, NE. Big Papillion 
Creek rises west of Blair, flows southeasterly through 
metropolitan Omaha area where it is joined by the Little 
Papillion Creek just above Offutt AFB, forming Papillion 
Creek. The combined creek flows along the side of Offutt 
AFB to its confluence with the Missouri River. 
Existing project. The active project consists of a series 
of four dams and reservoirs, channel improvement and a 
flood warning system on tributaries of Papillion Creek. 
Construction was initiated in FY 1972. Completed projects 
include Standing Bear Lake (Site 16) December 1978 
and Glenn Cunningham Lake (Site 11) December 1979. 
Construction of the dam portions of Ed Zorinsky Lake 
(Site 18) and Wehrspann Lake (Site 20) are complete. 
Remaining work includes construction of recreational 
facilities at both sites, effluent storage facility at Site 18, 
and channel improvement on the Big Papio Channel. Estimated 
total costs for the project are $59,500,000 Federal 
funds with $3,879,000 non-Federal reimbursement, and 
$2,711,000 other and cash contributions. 
Local cooperation. Requirements are described in full 
on page 21-6 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Revise GDM and complete 
plans and specifications for Big Papio Channel. 
Start construction Recreation Facilities Stage I and Effluent 
Storage Facility; complete Stage IV Recreation Facilities, 
initiate and complete landscaping and handicapped 
fishing pier, Site 20. Maintenance: Routine operations 
and maintenance activities continued at all four dam sites. 
Annual project visitation hours were estimated at 
8,897,395. 
16. PEBBLE CREEK, SCRIBNER, NE 
Location. Scribner, Nebraska, is located in Dodge 
County about 47 miles northwest of Omaha, Nebraska. 
Pebble Creek is a right-bank tributary to the Elkhorn 
River. 
Existing project. The plan includes a 3.6-mile-long 
levee with an average height of about eight feet providing 
100-year flood protection plus 3 feet of freeboard from 
Pebble Creek, a closure structure at U.S. Highway 275 at 
the northern edge of Scribner, four road ramps over the 
levee, an automated flood warning system, and appropriate 
land use zoning and continued flood insurance for 
unprotected areas. In the process of providing FEMA the 
necessary date to revise the flood insurance rate maps to 
reflect the Pebble Creek levee, it was determined that 
Scribner is subject to greater residual flooding from the 
Elkhorn River than was previously determined. An additional 
segment needs to be added to the project which will 
essentially result in a ring levee that would provide complete 
flood protection for the city. 
Local cooperation. The city of Scribner is the non- 
Federal sponsor of the project. The city has obtained costsharing 
assistance from the Nebraska Natural Resources 
Commission and the Lower Elkhorn Natural Resources 
District. 
Operations during fiscal year. Construction on the 
Pebble Creek levee continued during the year and is scheduled 
for completion in October 1989. Work began on the 
plans and specifications for the additional segment of the 
project along the Elkhorn River. The total estimated cost 
of the project is $2,604,997. The non-Federal portion of 
this estimate is $533,000 which includes $225,000 for 
lands, easements and rights-of-way. 
17. PICK-SLOAN MISSOURI BASIN 
PROGRAM (OMAHA DISTRICT) 
Location. Flood control improvements in this project 
are along Missouri River and several of its principal tributaries 
and in states comprising Missouri River Basin. 
Existing project. A general comprehensive plan for 
flood control and other purposes in Missouri River Basin 
provides for levees along Missouri River between Sioux 
City, IA, and mouth and reservoirs on main stem of Missouri 
River and tributaries. See individual reports and 
Table 26-I for projects in the Omaha District included in 
the program. 
18. PIPESTEM LAKE, ND 
Location. On Pipestem Creek in Stutsman County, 
ND, 3 miles upstream from where Pipestem Creek joins 
the James River at Jamestown, ND. 
Existing project. The project consists of a rolled earthfill 
dam approximately 108 feet high with a crest length of 
4,000 feet and outlet works of a gated reinforced concrete 
conduit. The reservoir provides 146,880 acre-feet of storage. 
The miltipurpose pool provides space for silt storage 
and 885 acres of water surface for fish, wildlife and recreation 
needs. Construction of the project was initiated in FY 
1970 and completed in FY 1977. (See Table 26-A for total 
construction costs.) 
Local cooperation. Requirements are described in full 
on page 26-6 of fiscal year 1988 Annual Report. 
Operations during fiscal year. Routine operation and 
maintenance activities continued. Annual project visitation 
hours were estimated at 307,045. 
19. SALT CREEK AND TRIBUTARIES, NE 
Location. Salt Creek Basin comprises an area of about 
1,627 square miles in and around Lincoln in southeastern 
Nebraska. 
Existing project. The authorized project consists of a 
system of 10 dams and reservoirs, channel clearing, enlarging 
and realignment, levees and necessary bridge alterations. 
Pursuant to Senate Resolution adopted August 7, 
1964, which authorized a review of Salt Creek survey report, 
remaining units were placed in "inactive" classification. 
Construction of the project began in the spring of 
1962. All work under the active portion of the project, 
consisting of the 10 dams and reservoirs and the channel 
improvements and levees through Lincoln, was completed 
in 1969. Funds were transferred to the project in FY 1980 
with concurrence of Congressional Committees. These 
funds were used to determine an effective method of correction 
for the dispersive clay problem in the completed 
26-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
downstream levees through Lincoln. (See Table 26-A for 
total construction costs.) 
Local cooperation. Requirements are described in full 
on page 26-6 of fiscal year 1988 Annual Report. 
Operations during fiscal year. Maintenance: Routine 
operation and maintenance activities continued. Annual 
visitation hours to the system of dams were estimated at 
16,057,962. 
20. SOUTH PLATTE RIVER BASIN, CO 
Location. Flood control improvements in this project 
are along the South Platte River and its tributaries in 
Colorado. 
Existing project. General plan for flood control and 
other purposes provides for construction of Chatfield 
Lake on the South Platte River, Bear Creek Lake on Bear 
Creek, and levee and channel improvements on the South 
Platte River. (See individual reports and Table 26-B 
for authorizing legislation). 
21. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to furnish assurances that they 
will maintain and operate certain local protection projects 
after completion, in accordance with regulations prescribed 
by Secretary of the Army. District Engineers are 
responsible for administration of these regulations within 
the boundaries of their respective districts. 
Inspections of completed local protection projects 
which have beer turned over to local interests for maintenance 
and operation during the fiscal year are set forth 
in Table 26-J, Inspections of Completed Local Protection 
Projects. Fiscal year costs were $183,728. 
22. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, Flood Control Act of December 
22, 1944, Corps of Engineers is responsible for detailed 
scheduling of operations involving storage capacity 
reserved for or assigned to flood control in reservoirs constructed 
by Bureau of Reclamation as well as those constructed 
by Corps of Engineers. Costs for FY 1989 were 
$274,342 and total costs to September 30, 1989 were 
$5,655,864. 
23. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th Cong., 
and antecedent legislation.) 
Federal costs for FY 1989 were $449,963 for disaster 
preparedness and emergency operations, $293 for repair 
and restoration and $20,575 for emergency water supply 
and drought assistance. 
Small Flood Control Projects Not Specifically Authorized 
by Congress (Sec. 205, 1948 Flood Control Act 
as amended, Public Law 858, 80th Cong., June 30, 1948). 
Initiated preparation of O&M manuals and analysis of 
contractor claim on Lost Creek at Columbus, NE. Plans 
and specifications are currently being done on Sidney, 
NE. The following studies were initiated in FY 1989. 
Beaver Creek, Brush, CO; Big Dry Creek, Littleton, CO; 
Dutch Creek, Columbine Valley, CO; Elkhorn River, 
West Point, NE; and Wet Spottedtail Creek, Mitchell, 
NE. Three negative Initial Appraisal Studies were submitted 
during FY 89 at a cost of $10,686. 
Emergency Bank Protection (Sec. 14, 1946 Flood Control 
Act, Public Law 526, 79th Cong., July 24, 1946.) 
Operations under this heading were as follows: Construction 
was completed on four projects: Keg Creek, 
Minden, IA, completed 8 May 1989; Soldier River, Ute, 
IA, completed 20 June 1989; Milk River, Malta, MT, 
completed 11 September 1989; James River, Yankton, 
SD, completed 18 May 1989. Plans and specifications are 
currently being prepared on the following projects: South 
Platte River, Ft. Lupton, CO; West Nishnabotna River, 
Malvern, IA; East Bow Creek, Cedar County, NE; 
Powder River, Sheridan, WY; White River, Trip County, 
SD; Elkhorn River, Cuming County, NE; South Table 
Creek, Nebraska City, NE; Elkhorn River, Norfolk, NE; 
South Fork Elkhorn River, Holt County, NE; and Knife 
River, Mercer County, ND. The following studies were 
initiated in FY 1989: South Platte River, Commerce City, 
CO; Little Sioux River, Spencer, IA; Gallatin River, Gallatin 
County, MT; Shields River, Livingston, MT; Plum 
Creek, Brown County, NE; and Sand Draw Creek, Brown 
County, NE. 
Multiple-Purpose Projects Including Power 
24. BIG BEND DAM-LAKE SHARPE, 
MISSOURI RIVER BASIN, SD 
Location. On Missouri River, 987.4 miles above 
mouth, near Fort Thompson, SD, and approximately 20 
miles upstream from Chamberlain, SD. Dam is located in 
the upstream reach of Fort Randall Reservoir. Big Bend 
Reservoir extends upstream to Pierre, SD. 
Existing project. A rolled earth-fill dam 95 feet high, 
with a crest length of 10,570 feet, a hydroelectric generating 
plant consisting of eight 58,500 kilowatt units, and a 
chute-type gated spillway. Reservoir provides gross storage 
of 1,883,000 acre-feet. Federal cost of the project was 
$107,498,000. Construction began in September 1959 and 
was completed in September 1977, except for Code 710 
recreation facilities. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, power production and other 
multiple uses. Normal operation and maintenance procedures 
were accomplished during the fiscal year. During 
the period, 885,287,000 net kilowatt-hours of electricity 
were produced. Annual project visitation hours were estimated 
at 4,119,900. 
25. FORT PECK LAKE, MT 
Location. Reservoir is in Missouri River Valley in Mc- 
26-6

OMAHA, NE, DISTRICT 
Cone, Valley, Garfield, Phillips, Petroleum, and Fergus 
Counties, MT. Dam is approximately 1,771.6 miles above 
mouth of Missouri River. Nearest towns are Glasgow, 17 
miles northwest, and Nashua, 9 miles north. 
Existing project. A hydraulic earthfill dam with a maximum 
height of 251 feet, with a crest length of 21,026 feet, 
and a reservoir for flood control, irrigation, navigation, 
hydroelectric power, and other purposes, with a gross 
storage capacity of 18,909,000 acre-feet at maximum operating 
pool. Work started on original project in October 
1933 and on second power plant in August 1956. The 
project was completed in 1965. The power installations at 
the project were uprated in FY 1979. The 5 generators 
have a total output of 185,250 KW, 2 generators at 40,000 
KW each, 2 generators at 43,500 KW each and 1 generator 
at 18,250 KW. See page 818 of 1965 Annual Report 
and page 905 of 1958 Annual Report for project details. 
Federal cost of the project was $158,428,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, power production, 
and other multi-purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 978,105,000 
net kilowatt hours of electricity. Annual project visitation 
hours were estimated at 1,783,000. 
26. FORT RANDALL DAM-LAKE FRANCIS 
CASE, MISSOURI RIVER BASIN, SD 
Location. On Missouri River in Charles Mix and 
Gregory Counties, SD, about 82 miles above Yankton, 
SD. Site is 880 miles above mouth of Missouri River and 
148 miles above Sioux City, IA. 
Existing project. A rolled earth-fill dam with a maximun 
height of 165 feet, a crest length of 10,700 feet, and a 
reservoir for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage 
capacity of 5,574,000 acre-feet at maximum operating 
pool. The power installation consists of eight units rated 
at 40,000 kilowatts each. Construction began in May 1946 
and was completed in 1969, except for Code 710 recreation 
facilities. Federal cost of the project was 
$199,066,000. Non-Federal contribution for constructing 
approaches to the Platte-Winner Bridge was $720,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple uses. Normal operation and 
maintenance procedures were accomplished during the 
fiscal year. Generating facilities produced 1,648,711,000 
net kilowatt-hours of electricity. Annual project visitation 
hours were estimated at 7,383,400. 
27. GARRISON DAM-LAKE SAKAKAWEA, 
MISSOURI RIVER BASIN, ND 
Location. On Missouri River in McLean and Mercer 
Counties, ND, about 11 miles south of Garrison, ND, and 
9 miles west of Coleharbor, ND. 1,389.9 miles above 
mouth of river and 75 miles above Bismarck, ND. 
Existing project. A rolled earth-fill dam 11,300 feet 
long with a maximum height of 210 feet and a reservoir 
for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage capacity 
of 24,137,000 acre-feet. It provides five power units, three 
units rated at 80,000 kilowatts each, and two units rated at 
95,000 kilowatts each, three flood control tunnels and a 
gated spillway. Federal cost of the project was 
$299,938,000 including $4,208,000 for major rehabilitation. 
Non-Federal contribution in connection with widening 
Snake Creek Embankment was $687,000. Construction 
of the project was initiated in April 1946 and 
completed in 1966, except for recreational development 
using Code 710 funds. 
Local cooperation. None required except cost-sharing 
with the State of North Dakota for widening the Snake 
Creek Embankment and recreation cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 
1,818,415,000 net kilowatt-hours of electricity. Annual 
project visitation hours were estimated at 10,801,800. 
28. GAVINS POINT DAM-LEWIS AND 
CLARK LAKE, MISSOURI RIVER 
BASIN, NE AND SD 
Location. On Missouri River in Yankton County, SD, 
and Knox County, NE, about 4 miles upstream from 
Yankton, SD, and 811.1 miles above mouth of river. 
Existing project. A concrete and rolled earth-fill dam 
with a maximum height of 74 feet and a reservoir for 
flood control, irrigation, navigation, hydroelectric power, 
and other purposes with a gross storage capacity of 
504,000 acre-feet at maximum operating pool. The power 
installation consists of three units rated at 33,333 kilowatts 
each. Federal cost of the project was $49,617,000. 
Construction of original project was initiated in March 
1952 and was completed in 1964. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 696,248,000 
net kilowatt-hours of electricity during fiscal year. Annual 
project visitation hours were estimated at 9,336,400. 
29. OAHE DAM-LAKE OAHE, MISSOURI 
RIVER BASIN, SD AND ND 
Location. Dam is on Missouri River in hughes and 
Stanley Counties, SD, about 6 miles northwest of Pierre, 
26-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
SD, and 1,072.3 miles above mouith of river. 
Existing project. A rolled earth-fill dam with maximum 
height of 245 feet, a crest length of 9,300 feet, and reservoir 
for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage 
capacity of 23,337,000 acre-feet at maximum operating 
pool. It contains seven power units rated at 85,000 kilowatts 
each. Federal cost of the project was $346,521,000. 
Construction was initiated August 1948 and project 
placed in operation June 1963. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 
2,227,673,000 net kilowatt-hours of electricity. Annual 
project visitation hours were estimated at 16,124,979. 
Miscellaneous 
30. NATIONAL EMERGENCY 
PREPAREDNESS 
The total fiscal year cost for this category amounted to 
$190,895. 
31. GENERAL INVESTIGATIONS 
Fiscal Year 1989 costs totaled $2,208,558 for all 
General Investigation activities. See Table 26-K which 
covers Surveys, Collection and Study of Basic Data, Research 
and Development, Preconstruction Engineering 
and Design (projects not fully authorized), Planning and 
Engineering under Proposed Program Legislation, and 
Preconstruction Engineering and Design (fully authorized 
projects). 
26-8

OMAHA, NE, DISTRICT 
TABLE 26-A COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
I. Missouri River, 
Sioux City, IA 
to Rulo, NE 
2. Sioux City Marina 
3. Bear Creek Lake, 
CO 
4. Bowman-Haley 
Lake, ND 
5. Chatfield Lake, 
CO 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
6. Cherry Creek 
Lake, CO 
7. Fall River 
Basin, SD 
8. Great Falls, MT 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
9. Little Sioux River 
and Tributaries, IA 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
1,792,000 
1,814,990 
100,000 
100,000 
17 
227,000 
225,407 
127,000 
126,115 
2,584,000 
1,892,138 
561,000 
154,129 
3,145,000 
2,046,267 
748,000 
752,420 
-53,000 
55,464 
404,000 
402,689 
287,000 
288,506 
825,000 
563,139 
825,000 
563,139 
176,247 
176,247 
2,475,000 
2,464,261 
-20,000 
--21,364 
268,000 
275,403 
175,000 
174,940 
600,000 
1,369,780 
3,941 
96,498 
603,941 
1,466,278 
474,000 
471,710 
-65,000 
567,000 
566,993 
266,000 
254,829 
-80,000 
118,213 
-80,000 
118,213 
100,000 
26,511 
6,329 
106,329 
26,511 
2,406,000 
2,412,217 
9,000 
10,080 
243,000 
243,329 
276,000 
275,668 
361,000 
449,983 
444,539 
361,000 
894,522 
503,000 
497,720 
4,115 
833,000 
756,453 
312,000 
317,400 
-25,000 
31,283 
-25,000 
31,283 
30,000 
93,556 
2,051 
8,380 
32,051 
101,936 
- 189,225,9911 
189,225,9911 
1,926,284 110,730,702 
1,927,227 110,722,466 
284 
40,000 
11,538 
244,000 
244,269 
177,000 
176,890 
360,000 
341,698 
360,000 
341,698 
502,000 
500,802 
425,000 
501,292 
288,000 
291,312 
8.930 
8,930 
16,782 
16,782 
88,716 
88,716 
62,043,600 
62,015,138 
2,347,000 
2,346,197 
4,372,174 
4,372,174 
2,298,043 
2,296,202 
94,503,700 
94,455,891 
1,246,171 
1,187,914 
95,749,871 
95,643,805 
4,528,800 
4,515,061 
15,220,364 
15,220,364 
7,251,511 
7,247,785 
5,538,432 
5,538,432 
3,931,141 
3,927,822 
11,912,1124 
11,904,6104 
308,600 
308,600 
12,220,7124 
12,213,2104 
20,629,920 
20,621,900 
8,380 
8,380 
20,638,300 
20,630,280 
26-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
10. Lost Creek, New Work: 
Columbus, NE Approp. 294,000 -15,000 150,000 3,619,518 
Cost 547,369 -50,000 20,542 67,625 3,467,187 
(Required New Work: 
Contributed Approp. 147,300 
Funds) Cost 125,069 - - 147,300 
(Consolidated New Work: 
Summary) Approp. 294,000 -15,000 - 150,000 3,766,818 
Cost 547,369 74,232 20,542 67,625 3,614,487 
11. Lower Heart River New Work: 
Mandan, ND Approp. 88,000 73,000 211,000 703,000 1,235,100 
Cost 70,283 24,575 223,950 613,121 1,087,208 
(Required New Work: 
Contributed Approp. - - 263,700 263,700 
Funds) Cost - - 224,689 224,689 
(Consolidated New Work: 
Summary) Approp. 88,000 73,000 474,700 703,000 1,498,800 
Cost 70,283 24,575 223,950 837,810 1,311,897 
12. Missouri National New Work: 
Recreational River Approp. 136,000 25,000 70,000 68,000 919,800 
NE & SD Cost 95,984 57,516 88,586 71,561 914,446 
Maint. 
Approp. 352,000 200,000 200,000 952,000 
Cost 511,978 5,533 45,780 345,793 941,158 
13. Missouri River New Work: 
Kenslers Bend, Approp. - - - - 11,294,414 
NE, to Sioux Cost - - 11,294,414 
City, IA Maint. 
Approp. 39,000 52,000 45,000 41,000 4,528,069 
Cost 38,585 51,304 45,828 41,318 4,527,469 
14. Missouri River New Work: 
Levees, IA Approp. 287,000 120,000 250,000 37,931,1776 
NE, KS & MO Cost 218,155 166,202 99,087 178,349 37,882,1436 
(Required New Work: 
Contributed Approp. - - - - 38,810 
Funds) Cost - - - 38,810 
(Consolidated New Work: 
Summary) Approp. 287,000 120,000 250,000 - 40,198,198 
Cost 218,155 166,202 99,087 178,349 40,149,164 
15. Papillion Creek New Work: 
and Tributaries Approp. 1,627,000 2,270,000 2,868,000 1,671,000 50,426,7625 
Lakes, NE Cost 1,610,484 2,129,384 3,008,487 1,511,524 50,221,5305 
Maint. 
Approp. 473,000 514,000 594,000 710,000 3,767,000 
Cost 469,039 513,416 585,395 721,885 3,757,369 
16. Pebble Creek New Work: 
Scribner, NE Approp. 71,000 109,000 140,000 1,067,000 1,763,997 
Cost 85,307 114,703 45,607 1,071,987 1,674,441 
(Required New Work: 
Contributed Approp. - - 205,000 - 205,000 
Funds) Cost - - - 179,559 179,559 
(Consolidated New Work: 
Summary) Approp. 71,000 109,000 345,000 1,067,000 1,968,997 
Cost 85,307 114,703 45,607 1,251,546 1,854,000 
18. Pipestem Lake, New Work: 
ND Approp. - - - - 9,277,545 
Cost - - - - 9,277,545 
Maint. 
Approp. 271,000 351,000 534,000 267,000 3,795,000 
Cost 269,506 352,918 532,078 268,752 3,794,350 
26-10

OMAHA, NE, DISTRICT 
TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
19. Salt Creek and 
Tributaries, NE 
21. Inspections of 
Completed Local 
Protection Projects 
22. Scheduling Flood 
Control Reservoir 
Operations 
24. Big Bend Dam- 
Lake Sharpe, 
Missouri River 
Basin, SD 
25. Fort Peck Lake 
MT 
26. Fort Randall 
Dam-Lake Francis 
Case, Missouri 
River Basin, SD 
27. Garrison Dam- 
Lake Sakakawea, 
Missouri River 
Basin, ND 
(Federal Funds) 
(Contributed 
Funds) 
28. Gavins Point 
Dam-Lewis & 
Clark Lake, 
Missouri River 
Basin, SD 
and NE 
29. Oahe Dam-Lake 
Oahe, Missouri 
River Basin, 
SD & ND 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
Major Rehab 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
213 
390,000 
387,776 
278,000 
277,285 
274,000 
273,069 
-25,000 
-24,979 
3,667,000 
3,642,938 
4,200 
3,399,000 
3,461,784 
946,000 
946,653 
209,000 
209,511 
279,000 
278,567 
4,861,200 
4,868,068 
2,555,400 
2,535,237 
820,000 
821,892 
140,000 
140,060 
292,000 
293,188 
4,322,000 
4,319,764 
2,862,000 
2,852,583 
311 
6,957,000 
6,925,109 
7,148,000 
7,144,937 
78,000 
78,000 
4,246,000 
4,311,714 
-2,892 
7,149,000 
7,283,549 
1. Includes $18,325,581 National Industrial Recovery Act 
funds, $8,625,718 Emergency Relief Funds, and $1,181,125 for previous 
project. 
2. Includes $123,000 of government cost applicable to that 
portion of the project which is currently being carried in a deferred 
status. 
6,418,100 
6,525,664 
8,332,700 
8,366,465 
5,307,300 
5,306,454 
7,452,300 
7,395,467 
7,088,000 
7,040,950 
7,492,000 
7,500,354 
4,819,000 
4,685,741 
8,322,300 
8,295,810 
749,000 
690,683 
184,000 
183,728 
274,000 
274,342 
4,770,000 
4,729,117 
12,197,6212 
12,197,6212 
9,221,475 
9,161,496 
3,112,348 
3,111,929 
5,655,976 
5,655,864 
107,497,597 
107,497,597 
56,531,1743 
56,441,1733 
158,428,080 
158,428,080 
4,087,000 62,323,9543 
3,936,406 62,113,8213 
199,065,883 
199,065,883 
7,032,000 101,015,9523 
6,786,599 100,678,8683 
295,729,613 
295,729,613 
6,620,000 114,366,4003 
6,465,668 114,161,2213 
4,208,310 
- 4,208,310 
-- 686,961 
686,961 
- 49,617,239 
- 49,617,239 
4,753,000 74,159,4503 
4,791,142 74,035,6623 
- 346,520,603 
- 346,517,696 
7,945,000 106,759,7453 
7,929,133 106,596,5293 
3. Includes Special Recreation Use Fees. 
4. Includes $110,000 transferred to inactive portion for 
planning cost. 
5. Does not include $1,854,338 cost of inactive sites. 
6. Does not include $2,228,211.50 cost of inactive sites. 
26-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 26-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
Jan 12, 1927 
July 3, 1930 
Aug 30, 1935 
Mar 2, 1945 
Aug 13, 1968 
Flood Control 
Act of 1962 
Flood control 
Act of 1950 
Water Resources 
Development Act 
of 1986 
Aug 18, 1941 
Dec 22, 1944 
Dec 22, 1944 
Aug 18, 1941 
Flood Control 
Acts of 1955, 1965 
Flood Control 
Act of 1954 
June 30, 1948 
June 30, 1948 
National Parks 
and Recreation 
Act of 1978 
1. 
LOST CREEK AT COLUMBUS, NE 
Levee and channel improvement for local 
protection - Section 205. 
LOWER HEART RIVER, MANDAN, ND 
Levee and channel improvement for local 
protection - Section 205. 
MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE 
Appropriation of $12 million authorized for 
securing a 6 foot depth from Quindaro Bend 
(Kansas City, MO to Sioux City, IA). 
Appropriation of $15 million additional allotments 
totaling $29,153,108 made by Public Works 
Administration under provisions of National 
Industrial Recovery Act of 1933, and $9,669,791 
alloted under provisions of Emergency Relief 
Appropriations Act of 1935. 
For completion of project from mouth to Sioux City, IA. 
For a channel of 9-foot depth and 300-foot width. 
BEAR CREEK LAKE, CO 
A flood control reservoir for protection of 
metropolitan Denver, CO. 
BOWMAN-HALEY LAKE, ND 
Flood control reservoir and water supply. 
CHATFIELD LAKE, CO 
Flood control reservoir and channel improvements 
to provide downstream protection for Denver, CO. 
Modified 1950 Flood Control Act to operate dam 
and other Federal improvements to achieve 
authorized level of protection, beginning at dam 
and ending 82 miles downstream. Reassigns a 
portion of the storage space in the lake project to 
joint flood control-conservation purposes. Modified 
1974 WRDA to exemp prohibition of encroachments 
for Mineral Ave/ Ken Caryl Rd. ext & 
transmission line. 
CHERRY CREEK LAKE, CO 
Initiation and partial accomplishment of project. 
Completion of plan approved in Act of Aug 18, 1941. 
General comprehensive plan, Missouri River Basin. 
FALL RIVER BASIN, SD 
Provide flood control to the town of Hot Springs, SD. 
GREAT FALLS, MT 
Levees and channel improvement for local protection. 
PL 858, 80th Cong. 
PL 858, 80th Cong. 
MISSOURI NATIONAL RECREATIONAL RIVER, NE AND SD 
Preservation and enhancement of the Missouri PL 95-625 
River between the reaches from Gavins Point 
Dam, NE & SD to Ponca State Park, NE. 
26-12 
H. Doc. 1120, 60th Cong. 
PL 70-560 
PL 71-520 
PL 73-67 
H. Doc 238, 73rd Cong. 
PL 74-409 
H. Doc. 214, 76th Cong. 
PL 79-14 
S. Doc. 87, 90th Cong. 
PL 90-483 
H. Doc. 574, 87th Cong. 
PL 87-874 
H. Doc. 669, 80th Cong. 
PL 81-516 
H. Doc. 1013, 99th Cong. 
PL 99-662 
H. Doc. 426, 76th Cong. 
PL 77-228 
H. Doc. 426, 76th Cong. 
PL 78-534 
H. Doc. 475, and S. Docs. 
191 and 247, 78th Cong. 
PL 78-534 
H. Doc. 655, 76th Cong. 
PL 77-228 
H. Doc. 343, 85th Cong. 
PL 85-500 
PL 89-298 
5. 
6. 
7. 
9. 
10. 
11. 
12. 
LITTLE SIOUX RIVER, IA 
Correction of design deficiency. PL 341, 80th Cong. 
PL 83-780

OMAHA, NE, DISTRICT 
TABLE 26-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
13. 
14. 
June 28, 1938 
Aug 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sep 3, 1954 
Sep 3, 1954 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec 30, 1963 
June 18, 1965 
May 12, 1967 
MISSOURI RIVER, KENSLERS BEND, NE TO SIOUX CITY, IA 
Construction of dike, revetments. H. Doc. 821, 76th Cong. 
PL 77-228 
PL 80-858 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, AND MO. 
Levees along both sides of river from Sioux City, IA to H. Doc. 821, 76th Cong. 
Kansas City, MO. PL 77-228 
Extended project from Kansas City, MO to mouth H. Doc. 475, 78th Cong. 
and provided for increased protection. PL 78-534 
S. Does. 191 and 247, 78th 
Cong. 
PAPILLION CREEK AND TRIBUTARIES LAKES, NE 
Series of flood control reservoirs, providing protection H. Doc. 349, 90th Cong. 
for the metropolitan areas of Omaha, NE. PL 90-485 
Authorized additional $4.8 million for channel H. Doc. 1013, 99th Cong. 
improvement on Big Papillion Creek, and to PL 99-662 
Union Pacific RR bridge, rec trail and flood 
warning system. 
PEBBLE CREEK, SCRIBNER, NE 
Levee and channel improvement for local PL 858, 80th Cong. 
protection - Section 205. 
PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DIST.) 
Adopted general comprehensive plan for Missouri 
River basin and authorized $9 million for 
initiation and partial accomplishment. 
Modified general comprehensive plan to include 
Harlan County Dam and Reservoir on Republican 
River, NE and authorized additional $7 million. 
Expanded general comprehensive plan for Missouri River 
Basin and authorized additional $200 million. 
Authorized additional $150 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $250 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional $217,710,000 
Authorized $5,384,014 to compensate Sioux Indians for 
reservation lands required for Oahe, South Dakota project. 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of 
construction of Wilson Dam and Reservoir, KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional $200 million. 
Authorized additional $207 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $80 million for prosecution of 
general comprehensive plan for Missouri River 
Basin and modified the plan to include work protection 
and rectification works below Garrison Dam. 
Authorized additional $116 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $20 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Flood Control Committee 
Doc. 1, 75th Cong. 
PL 75-761 
H. Doc. 842, 76th Cong. 
PL 77-228 
H. Doc. 475, and S. Does. 191 
and 247, 78th Cong. 
PL 78-534 
PL 79-526 
PL 81-516 
H. Does. 549 and 642, 81st 
Cong. PL 83-780 
PL 83-776 
PL 84-505 
H. Doc. 409, 84th Cong. 
PL 85-500 
PL 86-645 
PL 88-253 
PL 89-042 
PL 90-17 
26-13 
Aug 18, 1941 
June 30, 1948 
Aug 18, 1941 
Dec 22, 1944 
Flood Control 
Act of 1968 
Water Resources 
Development Act 
of 1986 
June 30, 1948 
15. 
16. 
17.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 26-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
Aug 13, 1968 
June 19, 1970 
Dec 24, 1970 
Dec 31, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Flood Control 
Act of 27 Oct 1965 
July 3, 1958 
May 17, 1950 
May 12, 1967 
Aug 13, 1968 
June 19, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Dec 22, 1944 
June 16, 1933 
Aug 30, 1935 
May 18, 1938 
Dec 22, 1944 
June 3, 1948 
Authorized additional $38 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $109 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Changed comprehensive plan name to Pick-Sloan 
Missouri Basin Program. 
Oahe Dam and Reservoir, ND. 
Authorized additional $101 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $72 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $85 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $59 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
PIPESTEM LAKE, ND 
Provide flood control for Jamestown, ND and 
downstream areas. 
SALT CREEK AND TRIBUTARIES, NE 
Series of dams and channel improvements for flood 
control around Lincoln, NE. 
SOUTH PLATTE RIVER BASIN, CO 
Adopted plan of improvement for South Platte 
River Basin and authorized $26.3 million for 
initiation and partial accomplishment. 
Authorized additional $2 million for prosecution of plan. 
Authorized additional $12 million for prosecution of plan. 
Authorized additional $21 million for prosecution of plan. 
Authorized additional $37 million for prosecution of plan. 
Authorized additional $15 million for prosecution of plan. 
Authorized additional $22 million for prosecution of plan. 
Authorized additional $3 million for prosecution of plan. 
BIG BEND DAM - LAKE SHARPE, SD 
Expanded general comprehensive plan for flood control 
and other purposes in the Missouri River Basin 
FORT PECK LAKE, MT 
Construction of earth dam, as recommended by Chief of 
Engineers Sep 30, 1933, was approved by Executive Order by 
the President and included in Public Works Administration 
program, Oct 14, 1933 as authorized by the National Industrial 
Recovery Act of 1933 and adopted by the River and Harbor 
Act of 1935 (PL 74-409). 
Completion, maintenance, and operation of a hydroelectric 
power plant, subject to certain provisions in act respecting 
transmission and sale of electric energy. Also authorizes 
installation of additional power-generating facilities by 
Secretary of War when deemed necessary in judgment of 
Bureau of Reclamation. 
Modified authorization to provide for full multiple purpose 
operation. 
Payments to be made to school districts serving project as 
reimbursement for educational facilities (including transportation 
to and from school) for pupils who are dependents 
of persons engaged in construction, operation, and maintenance 
of projects. 
PL 90-483 
H. Doc. 91-748 and 
S. Doc. 91-895 
PL 91-282 
S. Doc. 91-1100, 91st Cong. 
PL 91-576 
H. Doc. 91-23 and 
PL 91-611 
PL 92-222 
PL 93-251 
PL 94-347 
PL 95-189 
H. Doc. 266, 89th Cong. 
PL 89-298 
H. Doc. 396, 84th Cong. 
PL 85-500 
H. Doc. 669, 80th Cong. 
PL 81-516 
PL 90-17 
PL 90-843 
PL 91-282 
PL 92-222 
PL 93-251 
PL 94-347 
PL 95-189 
H. Doc. 475, S. Doc. 247, 
78th Cong. PL 78-534 
H. Doc. 238, 73rd Cong. 
PL 74-409 
PL 75-529 
H. Doc. 475 and S. Docs. 191 
and 247, 78th Cong. 
PL 78-534 
PL 80-586 
26-14 
18. 
19. 
20. 
24. 
25.

OMAHA, NE, DISTRICT 
TABLE 26-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
Water Resources Modified authorization to include recreation as a H. Doc. 1013, 99th Cong. 
Development Act project purpose. PL 99-662 
of 1986 
26. FORT RANDALL DAM - LAKE FRANCIS CASE, SD 
Dec 22, 1944 Expanded general comprehensive plan for flood control H. Doc. 475 and S. Does. 191 
and other purposes in the Missouri River Basin. and 247, 78th Cong. 
PL 78-534 
27. GARRISON DAM - LAKE SAKAKAWEA, ND 
Dec 22, 1944 Expanded general comprehensive plan for flood control H. Doc. 475, S. Doc. 247, 
PWA 1968 and other purposes in the Missouri River Basin. 78th Cong. PL 78-534 
28. GAVINS POINT DAM - LEWIS AND CLARK LAKE, NE & SD 
Dec 22, 1944 Expanded general comprehensive plan for flood control H. Doc. 475, S. Doc. 247, 
and other purposes in the Missouri River Basin. 78th Cong. PL 78-534 
29. OAHE DAM - LAKE OAHE, SD & ND 
Dec 22, 1944 Expanded general comprehensive plan for flood control H. Doc. 475 and S. Does. 191 
and other purposes in the Missouri River Basin. and 247, 78th Cong. 
PL 78-534 
TABLE 26-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Missouri River, Sioux City, IA to 
Fort Benton, MT Complete 1948 3,123,141 644,863 
Small Navigation Project at 
Sioux City, IA Complete 1970 43,582 88,716 
TABLE 26-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Belle Fourche, Cheyenne River, SDI Complete 1940 37,410 
Big Sioux River at Sioux City, IA Complete 1982 7,458,934 - 
Blackbird Creek Near Macy, NE2 Complete 1970 262,479 - 
Buffalo Creek, 
Meadow Grove, NE2 Complete 1974 293,016 - 
Buffalo Creek, Scranton, ND2 Complete 1960 102,980 - 
Cedar Canyon Dam, Rapid City, SD Complete 1960 120,482 - 
City of Aurora, 
Westerly Creek, CO Complete 1955 150,000 
Clarkson, NE, Maple Creek Complete 1967 191,282 
Council Bluffs, IA (Act of 1936) Complete 1939 - 
Council Bluffs, IA (Act of 1944) Complete 1954 2,557,680 
26-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 26-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Deadman's Gulch, Sturgis, SD2 Complete 1981 3,000,000 - 
Dry Creek, Hawarden, IA Complete 1964 400,000 
Eagle Bay and Fort Yates 
Highway Bridges, ND Active 1978 616,639 
Floyd River, Sioux City, IA Complete 1970 11,556,667 
Forsyth, MT Complete 1950 255,177 - 
Frazer-Wolf Point, MT Complete 1982 435,000 
Gering Valley, NE Complete 1971 5,989,663 
Glasgow, MT Complete 1939 16,832 
Greybull, WY Complete 1960 248,507 
Havre, MT Complete 1958 1,825,881 
Herreid, Spring Creek, SD Complete 1954 50,216 
Hooper, NE2 Complete 1968 326,667 
Ida Grove, IA 2 Complete 1972 522,344 
Jamestown Reservoir, ND Complete 1950 - - 
Linton, ND2 Inactive 1973 
Little Papillion Creek, NE Complete 1976 3,643,111 
Loup River, Columbus, NE2 Complete 1973 1,000,000 
Lower Big Sioux River, IA and SD Inactive 1966 
Lower Heart River, ND Complete 1964 1,961,173 
Madison, NE, ,nion and 
Taylor Creeks" Complete 1967 234,839 
Mandan, Heart River, ND Complete 1960 676,916 
Marmarth, ND Complete 1960 169,498 - 
McCook Lake, SD Complete 1958 147,627 
Miles City, MT Inactive 1956 
Missouri River, Aten, NE Complete 1951 578,791 
Missouri River, Niobrara, NE Complete 1945 99,370 5,633 
Mott, ND Deferred - 
Mud Creek, Broken Bow, NE2 Complete 1976 1,000,000 - 
Nishnabotna River at 
Hamburg, IA Complete 1948 236,000 
Norfolk, NE Complete 1971 3,400,504 
Omaha, NE Complete 1954 5,903,640 
Pierce, NE Complete 1967 296,597 
Platte River Near Schuyler, NE2 Complete 1948 74,940 
Platte River and Lost Creek, 
Schuyler, NE Complete 1971 257,398 
Platte River and Tributaries, NE Inactive - 1,538,269 
Rapid Creek, Rapid City, SD Complete 1980 1,004,000 - 
Saco, MT Complete 1958 67,793 
Sacred Heart Hospital, 
Yankton, SD Complete 1978 184,380 
Sheridan, WY3 Complete 1976 2,618,809 
Shields River, 
Near Clyde Park, MT2 Complete 1951 25,747 
Sioux Falls, SD Complete 1966 5,288,707 
South Platte River Levees and 
Channel Improvements, Chatfield 
Lake to Ft. Morgan, CO Inactive 1957 
Vaughn, MT, Sun River2 Complete 1971 457,582 
Waterloo, NE Complete 1970 237,883 - 
West Point, NE Complete 1966 149,596 
Yellowstone River, 
W. Glendive, MT Complete 1960 230,294 
1. Completed as a Public Works Administration project. 
2. Authorized by Chief of Engineers. 
3. Includes inactive segment. 
26-16

OMAHA, NE, DISTRICT 
TABLE 26-F OTHER MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
For Last 
Full Report Cost to September 30, 1989 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Gavins Point Dam-Lewis and Clark Lake, 
Relocation of Niobrara, NE Complete 1980 13,516,459 
Springfield, SD Water Intake Active 
Williston, ND Water Intake Complete 1981 988,583 
TABLE 26-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Authority Federal Contributed 
See Annual and Funds Funds 
Project Report For Date Expended Expended 
Billings, MT 
Boulder, CO 
Buffalo, Johnson County 
Diversion Channel, WY 
Castlewood Lake, 
Douglas County, CO 
Davids Creek Lake, IA 
Dayton, WY 
Giles Creek, Elkhorn, NE 
Indian Creek Lake, IA 
Little Nemaha River, 
Nemaha County, NE 
Morrison, Bear Creek, CO 
Redwater River and 
Hay Creek, Bell Fourche, SD 
Shell Creek, NE 
1976 
1976 
1961 
1943 
1972 
1956 
1952 
1969 
1973 
1950 
1966 
1962 
Vermillion River and Tribs, SD 1968 
Sec. 201, FC Act 1950 
23 Mar 81 
FC Act 1950 
WRDA of 1986 
17 Oct 86 
FC Act 1950 
WRDA of 1986 
17 Oct 86 
PL 77-228 
WRDA of 1986 
17 Oct 86 
Sec. 203, PL 90-483 
WRDA of 1986 
17 Oct 86 
Sec. 12, PL 93-251 
WRDA of 1974 
5 Aug 77 
Sec. 12, PL 93-251 
WRDA of 1974 
6 Nov 77 
Sec. 12, PL 93-251 
WRDA of 1974 
4 Jan 74 
Sec. 204, PL 89-298 
WRDA of 1986 
17 Oct 86 
Sec. 12, PL 93-251 
WRDA of 1974 
5 Aug 77 
Sec. 12, PL 93-251 
WRDA of 1974 
4 Jan 74 
Sec. 12, PL 93-251 
WRDA of 1974 
3 Oct 78 
Sec. 12, PL 93-251 
WRDA of 1974 
4 Jan 74 
The following investigations for flood control called for by Flood Control Acts and committee resolutions were deauthorized by WRDA of 
1986, 17 Oct 86: Aowa & South Creek, NE; Bow Creek, NE; Cannonball River, ND; James River, ND & SD; Judith River Basin, MT; 
Niobrara River Basin, NE, SD & WY; Omaha Creek, NE; South Dakota Lakes, SD; Weeping Water Creek, NE; Windpower at Ft. Peck 
Lake, MT; Yellowstone River below Billings, MT. 
26-17 
75,000 
142,666 
135,000 
30,000 
1,000 
71,000 
208,000

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
MISSOURI RIVER LEVEE SYSTEM, SIOUX CITY, IA TO RULO, NE 
TABLE 26-H (See Section 14 of Text) 
Miles of 
Unit Levee Status 
L627-624 Mosquito Creek Levee 14.2 Complete 1950 
L601 Watkins-Waubonsie Ditch Levees 15.0 Complete 1966 
L594 Pleasant Valley Levee 11.4 Complete 1964 
R580 Nebraska City Levee 0.2 Complete 1950 
L575 Thurman-Hamburg Levee 45.8 Complete 1950 
R573 Otto County Drainage District No. 2 5.9 Complete 1950 
R562 Peru Dike 7.6 Complete 1950 
L561-550 Atchison County Levee District No. 1 41.3 Complete 1952 
R548 Brownville-Nemaha Levee 19.5 Complete 1952 
L536 Mill Creek Levee 13.6 Complete 1952 
R520 Richardson County Drainage Dist. No. 8 6.3 Complete 1960 
R613 Papillion Creek-Platte River Levee 14.0 Complete 1971 
R616 Bellevue-Papillion Creek Levees 4.5 Complete 1987 
L611-614 Mosquito-Keg Creek Levees 22.0 Complete 1988 
LL566217-, 5LL5660222447,,, Remedial Studies on Completed Units Studies Complete 
Comprehensive Restudy of Levee System Started Mar 1988 
PICK-SLOAN MISSOURI BASIN PROGRAM 
TABLE 26-I (See Section 17 of Text) 
Estimated Estimated 
Project Federal Cost Non-Federal Cost 
Fort Peck Lake, MT1,2 158,428,000 1,103,000 
Garrison Dam, Lake Sakakawea, ND1 ,2 299,938,000 1,516,000 
Missouri River Levee System, 14, NE, KS and MO 
(Sioux City, IA to Rulo, NE) , 37,931,000 4,618,000 
Oahe Dam-Lake Oahe, SD and ND 1,2 346,521,000 2,320,000 
Big Bend Dam-Lake Sharpe, SD1,2 107,498,000 302,000 
Fort Randall Dam, Lake Francis Case, SD1,2 199,066,000 1,609,000 
Gavins Point Dam, Lewis & Clark Lake, SD & NE1, 2 49,617,000 137,000 
Gavins Point Dam, Lewis & Clark bake, SD 
& NE-Relocation of Niobrara, NEz 13,516,000 
Omaha, NE2 5,904,000 362,000 
Council Bluffs, IA2 2,558,000 146,000 
Missouri River, Garrison Dam to Lake Oahe, ND2 9,413,000 270,000 
Cherry Creek Lake, CO1 ,2 15,220,000 285,000 
1Details presented on individual report. 2Completed. 3 Active portion of project. 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (See Section 21 of Text) 
Location Month Inspected 
Montana 
Glasgow, Milk River Nov 87 
Saco, Beaver Creek Aug 87 
Havre, Milk River Aug 87 
Havre, Scott Coulee-Bull Hook Dam Aug 87 
Clyde Park, Shields River Nov 86 
Three Forks, Lower Madison River Sep 88 
Forsythe, Yellowstone River May 89 
West Glendive, Yellowstone River Nov 86 
Vaughn, Sun River Sep 88 
*Yellowsatone River, Water Plant, Livingston May 89 
Sun River, Great Falls Sep 88 
26-18

OMAHA, NE, DISTRICT 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (Continued) (See Section 21 of Text) 
Location Month Inspected 
*Yellowstone River, Reedpoint Bridge May 89 
*Yellowstone River, Greycliff Bridge May 89 
*Yellowstone River, Springdale Bridge Inactive 
*Yellowstone River, Near Miles City 
Water Intake & Sewage Lagoon Inactive 
*Yellowstone River, Bank Protection, Billings Inactive 
*Yellowstone River, Yellowstone County Bridge, Near Billings Feb 88 
*Yellowstone River, Voges Bridge, Near Big Timber May 89 
*Jefferson River, Willow Creek Bridge, Near Three Forks Apr 88 
*Jefferson River, Bank Protection, Near Waterloo Apr 88 
*Big Hole River, Pennington Bridge, Near Twin Bridges Aug 89 
*Ruby River, Wheatly Bridge, Near Twin Bridges Aug 89 
*Big Horn River, Two Leggin Bridge, Near Hardin Inactive 
*Missouri River, Bank Stabilization, Fort Benton Sep 88 
*Yellowstone River, Glendive Nov 87 
Wyoming 
Greybull, Big Horn River May 89 
Sheridan, Big and Little Goose Creeks May 89 
*Shoshone River, Bank Protection, Lovell May 89 
*Shoshone River, Byron May 89 
North Dakota 
Mandan, Lower Heart River Aug 89 
Marmarth, Little Missouri River Aug 89 
Scranton, Buffalo Aug 89 
South Dakota 
Big Sioux River, Union County Jul 89 
Big Sioux River, North Sioux City Jul 89 
Sioux Falls, Big Sioux River May 89 
Belle Fourche, Belle Fourche River Sep 89 
Rapid City, Cedar Canyon Dam Sep 89 
Hot Springs, Fall River Channel Jul 89 
Herreid, Spring Creek Sep 85 
*Missouri River, Bank Protection, Greenwood Jun 88 
*Bad River, Bank Protection, Fort Pierre Jun 85 
*Big Sioux River, Schofield Bridge, Near Flandreau Jun 89 
*Big Sioux River, Fink Bridge, Near Flandreau Jun 89 
Rapid Creek, Rapid City Sep 89 
Sacred Heart Hospital, Yankton Jun 89 
*Vermillion River, Vermillion Jun 89 
*Big Sioux River, Harrisburgh Jun 89 
*Big Sioux River, Jefferson Jun 89 
Deadman Gulch, Sturgis Sep 88 
*Big Sioux River, Plymouth County Jun 89 
*Marne Creek, Yankton Jun 89 
Colorado 
Aurora, Westerly Creek-Kelley Road Dam Aug 88 
*Plum Creek, Bank Stabilization, Aurora Jul 86 
*Cache La Poudre River, Windsor Jul 86 
*South Platte River, Kersey Jul 86 
*South Platte River, Merino Jul 86 
*South Platte River, Iliff Jul 86 
*South Platte River, Platteville Jul 86 
*Big Thompson River, Johnstown Jul 86 
Cache La Poudre River, Ft. Collins (Water Treatment Plant) Jul 86 
South Platte River, Adams County, No. Washington St. 
Water and Sanitary District Jul 86 
26-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (Continued) (See Section 21 of Text) 
Location Month Inspected 
Nebraska 
Blackbird Creek, Decatur Jul 89 
Omaha, Missouri River Aug 89 
Waterloo, Elkhorn River Sep 89 
West Point, Elkhorn River May 89 
Pierce, Elkhorn River Aug 89 
Clarkson, Middle Fork, Maple Creek Jul 89 
Hooper, Elkhorn River Jul 89 
Norfolk, North Fork, Elkhorn River Jun 89 
Madison, Union & Taylor Creeks Aug 89 
*Platte River, M.U.D. Protection, Cedar Island Feb 89 
*Platte River, Bank Protection, Louisville Feb 89 
*Elkhorn River, Q Street Bridge, Near Gretna Sep 89 
*Elkhorn River, Ray Bridge, Near Norfolk Jul 89 
*North Platte River, Bank Stabilization, Minatare Sep 89 
*Logan Creek, Bank Protection, Near Bancroft May 89 
*Battle Creek, Bank Protection, Battle Creek Jun 89 
Schuyler, Lost Creek & Platte River Sep 89 
Little Papillion, Little Papillion Creek Jul 89 
Gering Valley, Gering Drain & Tributaries Sep 89 
Macy, Blackbird Creek Jul 89 
Lincoln, Salt Creek & Tributaries Mar 89 
Meadow Grove, Buffalo Creek May 89 
Columbus, Loup River Aug 89 
Broken Bow, Mud Creek Sep 89 
*Tangeman, Little Nemaha River Feb 89 
*Julian, Rock Creek Inactive 
*Muddy Creek Near Syracuse Feb 89 
*Platte River, Hansen-Chris Lakes, Bellevue Feb 89 
*Platte River, Brady Sep 89 
*Elm Creek, Decatur Apr 89 
*Wiggle Creek, Homer Jun 89 
*Elk Creek, Jackson Jun 89 
*South Creek, Martinburg Jun 89 
*Elk Creek, Willis Jun 89 
Columbus Flood Control Project, Lost Creek, Columbus Aug 89 
*Shell Creek, County Road Near Columbus Jun 89 
*Middle Pebble Creek, Snyder Jun 89 
*Elm Creek, Burt County Apr 89 
*Redbird Creek, O'Neill Sep 89 
*Salt Creek Sewage Treatment Plant, Lincoln Mar 89 
*Platte River, Ashland Jul 89 
*West Branch Papillion Creek, Omaha, NE Sep 89 
Iowa 
Council Bluffs, Missouri River Sep 89 
Ida Grove, Maple River-Odebolt Creek Aug 89 
Sioux City, Floyd River Sep 89 
Hawarden, Dry Creek Aug 89 
Hamburg L575, Nishnabotna River May 89 
Intercounty D.D., Little Sioux River Sep 89 
Nagel D.D., Little Sioux River Sep 89 
Bennett-McDonald-Smithland D.D., Little Sioux River Sep 89 
*West Nishnabotna River, Mills County Bridge, Near Malvern Feb 89 
*West Nishnabotna River, Mills County Bridge, Near Hastings Feb 89 
*East Nishnabotna River, Page County Bridge, Near Essex Feb 89 
*Missouri River, Marina, Sioux City Sep 89 
*West Nishnabotna River, Near Hancock Feb 89 
*East Nishnabotna River, Near Griswold Feb 89 
East Nishnabotna River, Red Oak Mar 89 
Big Sioux River, Sioux City Jul 89 
*Mucky Creek, Mapleton, IA Jun 89 
26-20

OMAHA, NE, DISTRICT 
INSPECTION 
TABLE 26-J (Continued) 
Location 
Emerson, Indian Creek, Mills County 
*East Fork of Boyer River, Near Vail 
Monona-Harrison Ditch Control, Monona County 
*Little Sioux River, Anthon 
*Big Sioux River, Plymouth County 
Missouri River Levees 
L624 & L627, Mosquito Creek & Sieck Levees 
L601, Watkins Levee District 
L601, Miller-Sturgeon Levee District 
L601, Missouri River Levee District #1 
L594, Waubansie Drainage District 
L594, Pleasant Valley Levee District 
L575, Benton-Washington Levee District 
L575, Northwest Atchison Levee District 
L575, McKissock Island Levee District 
L575, Buchannan Levee District 
L561, L550, L536, Atchison County Levee District 
L611-614, M & P Missouri River Levee District 
R613, Papio Natural Resources District 
R562, Peru Levee District 
R548, Brownville-Nemaha Levee District 
R548, Little Nemaha Levee District 
R520, Richardosn Co. Levee Dist. #8 
R573, Otoe County Drainage Dist. #2 
R616, Sarpy County Papio Natural Resources District 
OF COMPLETED LOCAL PROTECTION PROJECTS 
(See Section 21 of Text) 
Month Inspected 
Mar 89 
Mar 89 
Sep 89 
Jun 89 
Jun 89 
Sep 89 
Jun 89 
Jun 89 
Jun 89 
Jun 89 
Jun 89 
Mar 89 
May 89 
May 89 
May 89 
Mar 89 
May 89 
Aug 89 
Apr 89 
Apr 89 
Apr 89 
Apr 89 
Apr 89 
Aug 89 
*Denotes Section 14 Projects 
ACTIVE GENERAL INVESTIGATIONS 
TABLE 26-K (See Section 21 of Text)
Federal Cost Totals By 
Item FY 89 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Antelope Creek, Lincoln, NE 49,962 
Big Sioux River, Sioux Falls, SD 22,997 
Box Elder Creek Basin, CO 94,996 
Thurman to Hamburg, IA 31,708 
Platte River Basin, CO 6,950 
Eastern SD and Upper Big Sioux River, SD, IA 18,361 
James River Basin, SD 127,198 
Watertown and Vicinity, SD 138,219 
Missouri River, SD, NE, ND, MT 32,596 
Wood River, Grand Island, NE 65,593 
Subtotal 588,580 
Special Studies (140) 
Elm Creek, Decatur, NE 37,006 
Platte River Bank Stabilization Project, NE 245,278 
Subtotal 282,284 
Review of Authorized Projects (160) 
Deauthorization Review Program 1,898 
Subtotal 1,898 
26-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 26-K (Continued) 
ACTIVE GENERAL INVESTIGATIONS 
(See Section 31 of Text)
Federal Cost Totals By 
Item FY 89 Categories 
Miscellaneous Activities (170) 
Special Investigations 128,051 
FERC Licensing 1,916 
Interagency Water Resources Development 3,526 
Subtotal 133,493 
Coordination Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) 226 
Bureau of Reclamation, Dept. Interior (182) 5,121 
Planning Assistance to States (186) 633,599 
Subtotal 638,946 
TOTAL (Category 100) 1,645,201 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 248,326 
Hydrologic Studies (260) 35,780 
TOTAL (Category 200) 284,106 
RESEARCH AND DEVELOPMENT (Category 300) 
None 
PRECONSTRUCTION ENGINEERING AND DESIGN - 
PROJECTS NOT FULLY AUTHORIZED (Category 400) 
None 
PLANNING AND ENGINEERING UNDER PROPOSED 
LEGISLATION (Category 500) 
None 
PRECONSTRUCTION ENGINEERING AND DESIGN - 
FULLY AUTHORIZED PROJECTS (Category 600) 
Peity Creek, IA (650) 279,251 
TOTAL (Category 600) 279,251 
GRAND TOTAL GENERAL INVESTIGATIONS 2,208,558 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 26-L (See Section 23 of Text) 
Fiscal Year 
Project Name Stage Cost 
Flood Control and Coastal Emergencies 
Disaster Preparedness - 449,963 
Flood Flight and Rescue Operations - - 
Rehabilitation - 293 
Emergency Water Supply & Drought Assistance 20,575 
Advance Measures 
Section 205: 
Beaver Creek, Brush, CO R 23,935 
Carter Lake, NE R 85 
Knife River, Hazen, ND R 24 
Boyer River, Missouri Valley, IA R 27,071 
Cache La Poudre River, Greeley, CO R 1,985 
Elkhorn River, West Point, NE F 5,990 
Dutch Creek, Columbine Valley, CO R 14,606 
Elkhorn River, Crowell, NE R 24,049 
26-22

OMAHA, NE, DISTRICT 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 26-L (Continued) (See Section 23 of Text) 
Fiscal Year 
Project Name Stage Cost 
Little Sioux River, Spencer, IA R 2,379 
Lodge Creek, Chinook, MT R 25,210 
Logan Creek, Wakefield, NE R 2,180 
Lost Creek at Columbus, NE C 67,625 
Lower Heart River, Mandan, ND C 613,121 
Milk River, Malta, MT R 24,331 
Nowood River, Manderson, WY R 24,308 
Pebble Creek, Scribner, NE C 1,071,987 
Platte River, Cedar Creek, NE R 8,717 
Sidney, NE P 207,134 
Thirty Mile Creek, Harlem, MT R 24,956 
Van Bibber Creek, Arvada, CO F 15,067 
West Nishnabotna River, Atlantic, IA 68 
Wet Spottedtail Creek, Mitchell, NE R 46,085 
Yellowstone River, Glendive, MT R 28,086 
3 Negative Appraisals 10,688 
Total (Sectin 205's) 2,269,686 
Section 14: 
Battle Creek, Blaine, CO (Unruh Bridge) - 105 
Beaver Creek, Platte County, NE R 5,156 
Big Sioux River, 4-Plymouth, IA - 20 
Cannonball River, Shields, ND R 5,361 
Cedar River, Spaulding, NE R 5,093 
Clearwater, NE - 38 
East Bow Creek, Cedar County, NE P 6,799 
Elk Creek, Willis, NE - 34 
Elkhorn River, Beemer, NE P 2,428 
Elkhorn River, Norfolk, NE P 1,464 
Fort Lupton, CO (Lagoon) P 11,928 
Gallatin River, Gallatin County, MT R 4,136 
Hauser Lake, MT 65 
Heart River, Ft. Abe Lincoln Park, ND 79 
James River, Yankton, SD C 21,389 
Keg Creek, Minden, IA (WW Lagoon) C 54,737 
Knife River, Stanton, ND P 1,230 
Logan Creek, Bancroft, NE C 480 
Lovell, WY (Sewage Lagoon) P 6,550 
Madison River, Madison County, MT (State hwy 287) C 7,263 
Medicine Bow River, Elk Mountain, WY - 18 
Medora, ND (Sewage Lagoon) C 6,719 
Milk River, Blaine County, MT (Finley Bridge) C 5,064 
Milk River, Malta, MT (Sewerline) C 81,860 
Milk River, Nashua (Sewage Lagoon), MT 83 
Muckey Creek, Mapleton, IA - 3,111 
Muddy Creek, Syracuse, NE - 95 
Nine Mile Drain, Scottsbluff, NE R 3,966 
Niobrara River, NE (Carnes Bridge) - 1,747 
Oakland, IA P 609 
Platte River, Cass County, (YMCA), NE - 36 
Platte River, Camp Ashland, NE - 59 
Platte River, Douglas County, NE 
(Ginger Cove Sewage Lagoon) C 5,614 
Platte River, North Band, NE C 38,463 
Plum Creek, Norden Dam Access Road, NE R 5,419 
Powder River, Arvada, WY P 5,797 
Sand Creek, Rosebud, MT 66 
Shields River, Park County, MT (US 89) R 1304 
Snyder, NE (WW Treatment Plant) - 69 
Soldier River, Ute, IA C 18,578 
South Creek, Martinsburg, NE - 57 
South Fork, Ewing, NE P 6,045 
26-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 26-L (Continued) (See Section 23 of Text) 
Fiscal Year 
Project Name Stage Cost 
South Platte River, Commerce City, CO 
South Platte River, Commerce City, CO (1-270) 
South Platte River, Commerce City, CO (1-76) 
South Platte River, Commerce City, CO (State Hwy 244) 
South Platte River, Ft. Lupton, CO 
South Table Creek, Nebraska City, NE 
Spring Creek, Zap (Water & Sewer) 
Vermillion River, SD 
Waterman Creek, O'Brien County, IA 
West Nishnabotna, River, Malvern, IA 
West Papillion Creek, Douglas County, NE 
White River, Tripp County, SD 
Yellowstone River, Livingston, MT 
5 Negative Appraisals 
Total (Section 14's) 
Total Flood Control Activities 
R = Recon 
P = Plans & Specs 
C = Construction 
F = Feasibility 
- Does Not Apply 
26-24 
RRRPP 
CP 
P
C 
594 
5,316 
711 
249 
307 
3,997 
37 
126 
27,787 
5,258 
1,885 
7,418 
4,562 
6,879 
384,260 
2,653,946

KANSAS CITY, MO., DISTRICT * 
The district comprises a portion of southwestern Iowa; 
northwestern, central, and western Missouri; northern Kansas; 
southern Nebraska; and a portion of northeastern 
Colorado embraced in drainage basin of the Missouri River 
and tributaries from Rulo, Nebraska, to the mouth. Report 
on navigation project for section of Missouri River from 
Sioux City, Iowa, to Rulo, Nebraska, is in report of Omaha 
District. 
IMPROVEMENTS 
Navigation Page 
1. Missouri River, Sioux City, IA to 
Mouth (Rulo, NE, to Mouth).................27-2 
Flood Control 
2. Blue River Channel, Kansas City, MO ........ 27-2 
3. Brush Creek, Kansas City, MO............... 27-2 
4. Clinton Lake, Wakarusa River, KS ........... 27-2 
5. Harlan County Lake, Republican 
River, NE .............................. 27-3 
6. Hillsdale Lake, Big Bull Creek, KS ........... 27-3 
7. Kanopolis Lake, Smoky Hill River, KS ........ 27-3 
8. Little Blue River Channel Improvement, 
Little Blue River, MO ...................... 27-3 
9. Little Blue River Lakes, MO .............. 27-4 
10. Long Branch Lake, Little Chariton 
River, MO ............................ 27-4 
11. Melvern Lake, Marais des Cygnes 
(Osage) River, KS ......................... 27-4 
12. Milford Lake, Republican River, KS .......... 27-5 
13. Missouri River Levee System, IA, NE, 
KS, and MO (Rulo, NE to Mouth)............27-5 
14. Perry Lake, Delaware River, KS ............. 27-5 
15. Pick-Sloan Missouri Basin Program 
(Kansas City Dist.) ........................ 27-5 
16. Pomme de Terre Lake, Pomme de Terre 
River, MO ................................ 27-6 
17. Pomona Lake, One Hundred Ten Mile 
Creek, KS ................................ 27-6 
18. Rathbun Lake, Chariton River, IA ............ 27-6 
19. Smithville Lake, Little Platte River, MO ...... 27-6 
20. ITttle Creek Lake, Big Blue River, KS ........ 27-6 
21. Wilson Lake, Saline River, KS ............. 27-7 
Flood Control (cont.) Page 
22. Scheduling of Flood Control 
Reservoir Operations ....................... 27-7 
23. Inspection of Completed Flood 
Control Projects ........................... 27-7 
24. Disaster Preparedness Program-Inspections . .27-7 
25. Flood Control Activities Under Special 
Authorization ......................... 27-7 
Multiple Purpose Projects Including Power 
26. Harry S. Truman Dam and Reservoir, 
Osage River, MO ........................ 27-8 
27. Stockton Lake, Sac River, MO .............. 27-8 
General Investigations 
28. General Investigations ...................... 27-9 
Tables 
Table 27-A Cost & Financial Statement .......... 27-10 
Table 27-B Authorizing Legislation ............. 27-13 
Table 27-C Other Authorized Navigation 
Projects .......................... 27-16 
Table 27-D Not Applicable 
Table 27-E Other Authorized Flood Control 
Projects .......................... 27-17 
Table 27-F Not Applicable 
Table 27-G Deauthorized Projects ............... 27-18 
Table 27-H Missouri River Levee System ........ 27-19 
Table 27-I Kansas City District Projects 
Included in Pick-Sloan Missouri 
Basin Program ..................... 27-20 
Table 27-J Inspection of Completed Flood 
Control Projects .................... 27-20 
Table 27-K Active General Investigations ........ 27-21 
Table 27-L Flood Control Activities Under 
Special Authorization ............... 27-22 
27-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA, 
TO MOUTH (RULO, NE, TO MOUTH) 
Location. Jefferson, Madison, and Gallatin Rivers conjoin 
at Three Forks, Montana, to form the Missouri River, 
which flows southeasterly 2,315 miles (1960 mileage) across 
or along seven states to the Mississippi River, 17 miles above 
St. Louis. For description see page 1149, Annual Report 
for 1932. The river is commercially navigable from Sioux 
City, Iowa, to the mouth, a distance of 732 miles. The portion 
of project in Kansas City District extends from Rulo, 
Nebraska, to the mouth, a distance of 498 miles. 
Previous Projects. For details see page 1891 of Annual 
Report for 1915, and pages 1153 and 1175 of Annual Report 
for 1938. 
Existing Project. A channel of 9-foot depth and width 
not less than 300 feet, obtained by revetment of banks, construction 
of permeable dikes to contract and stabilize the 
channel, cutoffs to eliminate long bends, closing minor channels, 
removal of snags, and dredging as required. The 
improved reach within the Kansas City District extends 
from the mouth to Rulo, Nebraska, a distance of 498.4 miles. 
The Bank Stabilization and Navigation features of the 
project were completed in September 1980. For the reach 
from Rulo, Nebraska, to the mouth, the total construction 
cost was $237,942,190 including $8,665,594 for previous 
project. River access sites have been completed at 11 locations. 
Ordinary and extreme stage fluctuations are 16 and 
38 feet, respectively. 
Local cooperation. Cooperation from benefited localities 
may be required where any improvement may confer special 
benefit. The receipt of contributions from private parties 
are to be expended along with Government funds upon 
authorized work where such work would be in the interest 
of navigation, as authorized by 1915 Rivers and Harbors 
Act. Secretary of the Army approved general principle of 
cooperative construction on Missouri River below Kansas 
City on basis that 25 percent of cost of any special installation 
shall be paid by the United States and 75 percent by 
local interests. Total contributed by local interests in 
cooperation with the United States from 1918 to June 30, 
1964, was $675,663, of which $8,647 was returned to contributors. 
Local interests must share in cost of recreation 
facilities in accordance with provisions of the Federal Water 
Project Recreation Act of 1965. Local interests have contributed 
$171,816 for cost sharing on construction of recreation 
in addition to constructing portions of the facilities. 
'lerminfaalc ilities. A listing of terminal facilities are included 
in Missouri River Navigation Charts and can be obtained 
from Kansas City District Engineer for a small fee. 
Operations during fiscal year. The 1974 Base Line 
Study of the reach of the Missouri River in the Kansas City 
District estimated recreation use on the river at 1,250,000 
recreation days annually. The projected tonnage on the river 
for FY 1989 was approximately 2.3 million, excluding sand, 
gravel, and waterway improvement materials. Maintenance: 
Repair of dikes and revetments by contract. In addition, 
following work was accomplished by hired labor: Construction 
of environmental gaps, dike and revetment repair, 
channel maintenance dredging, real estate management, 
channel reconnaissance, condition studies, surveys and mapping, 
stream gauging, engineering and design, surveys and 
layout of construction, and supervision and administration. 
Flood Control 
2. BLUE RIVER CHANNEL, 
KANSAS CITY, MO 
Location. Along the Blue River and tributaries in 
Jackson County, Missouri. 
Existing project. Preliminary plans consist of 12.5 miles 
of improved channel along the Blue River within Kansas 
City, Missouri. Estimated Federal cost through construction 
of the project (1989) is $175,000,000, and estimated 
non-Federal cost of lands, damages and relocations is 
$22,800,000. 
Local cooperation. Section 2, Flood Control Act of 
June 22, 1936 applies. The city of Kansas City, Missouri, 
passed a resolution of intent on December 9, 1975 to provide 
the required assurances of local cooperation when 
requested. The Section 221 agreement was signed by the 
Kansas City District Engineer on September 8, 1983. 
Operations during fiscal year. Preconstruction planning 
is complete and final designs are underway. The first and 
second channel contracts are complete. A contract for pile 
stabilization is complete. Relocation contracts with four 
railroad companies are nearing completion. A contract for 
removal of contaminated sediments is underway. 
3. BRUSH CREEK, KANSAS CITY, MO 
Location. A major tributary of the Blue River in westcentral 
Kansas City and extending into Johnson County, 
Kansas, draining a highly urbanized 29-square-mile area in 
the two states. 
Existing project. Preliminary plans consist of improving 
about 7,500 feet of the channel from near Roanoke 
Parkway downstream to near Troost Avenue in Kansas City. 
Estimated Federal cost of the project (1989) is $16,090,000, 
and estimated non-Federal cost of lands, damages, and 
relocations is $10,110,000. 
Local cooperation. The city of Kansas City provided a 
letter of assurance, dated June 20, 1986, officially stating 
its intent and ability to cost share the project. 
Operations during fiscal year. Preconstruction engineering 
and design continues with activity in the Kansas 
City District and at the Waterways Experiment Station 
where model studies undertaken to confirm design calculations 
were completed. A Post Authorization Change 
Report was prepared which documented changes in the 
design and cost of the project. That report was submitted 
as the basis for further authorization by Congress to raise 
the maximum cost of the project, in accordance with Section 
902 of the Water Resources Development Act of 1986. 
The report is undergoing Washington-level review. 
4. CLINTON LAKE, WAKARUSA 
RIVER, KS 
Location. Damsite is on Wakarusa River about 4 miles 
southwest of Lawrence, Kansas, in Douglas County. Lake 
extends into Shawnee and Osage Counties, Kansas. 
27-2

KANSAS CITY, MO., DISTRICT 
Existing project. An earthfill dam about 9,250 feet long 
constructed to a height of about 114 feet with an uncontrolled 
spillway in left abutment. Total reservoir storage 
capacity 397,200 acre-feet (258,300 for flood control, 28,500 
for sediment reserve, and 110,400 of multipurpose storage 
for municipal and industrial waste supply and recreation). 
Cost of constructing the completed project was $57,415,433. 
Construction was initiated in January 1972, and the project 
was placed in operation in November 1977. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Reimbursement in the estimated 
amount of $6,768,000 is required for water supply storage 
in accordance with Water Supply Act of 1958. A contract 
was signed by the State on September 6, 1978 and was approved 
by the Secretary of the Army on October 30, 1978. 
Utilization of storage was initiated in December 1979. 
Repayment also began at that time. 
Operations during fiscal year. Visitation for FY 1989 
was 4,002,819 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
5. HARLAN COUNTY LAKE, 
REPUBLICAN RIVER, NE 
Location. Dam is on main stem of Republican River 
about 235 miles above confluence of stream with Smoky 
Hill River. Site is in Harlan County, 1/2 miles south of 
Republican City and 13 miles west of Franklin, Nebraska. 
Existing project. An earthfill dam about 107 feet above 
streambed with a total length of 11,827 feet, including a 
gate-controlled, concrete, gravity-type spillway section near 
center of dam. Reservoir provides storage capacity of 
850,000 acre-feet (500,000 for flood control and 350,000 for 
irrigation and sedimentation allowance). Initial cost of constructing 
the project was $45,279,532. Total Federal cost 
of project, including $1,017,623 for major rehabilitation 
work and $1,832,394 supplemental recreation development 
(Code 710), is $48,129,549. Construction of the project was 
initiated in August 1946. Project was placed in operation 
in December 1952. Major rehabilitation work was completed 
in FY 1968. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 2,550,920 visitor hours. Maintenance: Activities included 
sediment resurvey and ordinary operation and 
maintenance. 
6. HILLSDALE LAKE, BIG BULL 
CREEK, KS 
Location. The project is located approximately 12 miles 
above the mouth of Big Bull Creek, a tributary of the Marais 
des Cygnes River and about 15 miles southwest of the Kansas 
City metropolitan area in Miami County, Kansas. 
Existing project. An earthfill embankment about 11,600 
fe'et long (including approximately 3,300 feet of dike section) 
about 75 feet above rising valley flood plain. The 
spillway is gravity type uncontrolled and the outlet works 
are controlled. The total reservoir storage capacity is 
160,000 acre-feet (81,000 for flood control, 11,000 for sediment 
reserve, and 68,000 for multipurpose storage for water 
supply, water quality control, and recreation). Construction 
was initiated in December 1974 and project was placed in 
operation in October 1981. Federal cost of construction is 
$64,161,400. 
Local cooperation. Section 2, Flood Control Act 1938, 
applies. Local interests must make reimbursement of 
$23,342,756 for water supply storage in accordance with 
Water Supply Act of 1958. The Kansas Water Resources 
Board signed a contract in January 1974, approved by the 
Secretary of the Army in April 1974, for the entire 53,000 
acre-feet of water supply storage. Local interests have 
shown no interest in sponsoring recreational development 
at this time. Therefore, only minimum recreational facilities 
have been built. 
Operations during fiscal year. Visitation for FY 1989 
was 409,683 visitor hours. Maintenance: Activities consisted 
of upstream riprap repair and ordinary operation and 
maintenance. 
7. KANOPOLIS LAKE, SMOKY 
HILL RIVER, KS 
Location. Dam is on Smoky Hill River about 19 miles 
west and 16 miles south of Salina, Kansas, and about 205 
river miles above mouth of stream. 
Existing project. An earthfill dam about 131 feet above 
streambed, having a total length of 15,360 feet, including 
4,070 feet of dike section on the left abutment and 2,550 
feet of dike section on right abutment. The reservoir provides 
storage capacity of 450,000 acre-feet, (400,000 for 
flood control and 50,000 for recreation and streamflow 
regulation). Outlet works and spillway are in right abutment. 
Initial cost of constructing the project was $12,327,735. 
Total Federal cost of project, including $249,492, supplemental 
recreational development (Code 710), is $12,577,227. 
Construction was initiated in June 1940 and project was 
placed in operation in May 1948. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 1,835,804 visitor hours. Maintenance: Activities included 
completion of upstream riprap repair, drain installation, 
replacing collector system, and ordinary operation and 
maintenance. 
8. LITTLE BLUE RIVER CHANNEL 
IMPROVEMENT, LITTLE BLUE 
RIVER, MO 
Location. The project is located along the Little Blue 
River and extends 22 miles upstream from the head of 
Missouri River Levee Unit R 351 to the vicinity of Wildwood 
Creek in Jackson County, Missouri. 
Existing project. The improvements consist of 
straightening and enlarging the Little Blue River channel 
from the head of Missouri River Levee Unit R 351, near 
Blue Mills Road, upstream to the vicinity of Wildwood 
Creek, reducing the length of this section from 20.4 to about 
15 miles. Alteration of six highway bridges and construction 
of five new highway bridges and one railroad bridge 
27-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
were required. Improvements in the vicinity of Lake City 
Army Ammunition Plant consist of diversion of West Fire 
Prairie Creek into the Little Blue River and construction 
of a levee. Federal cost through construction of the project 
(1989) is $25,530,083 and non-Federal cost is $3,390,000. 
Construction was initiated in December 1974, and project 
was placed in operation in September 1986. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies to the Little Blue River channel improvement 
works. Jackson County, Missouri, passed a bond 
issue for sponsorship of the project. Assurances of local 
cooperation were furnished July 31, 1973. 
Operations during fiscal year. Project is complete. 
9. LITTLE BLUE RIVER LAKES, MO 
Location. This project consists of two lakes in Jackson 
County, Missouri, located in Kansas City, Missouri, and 
suburban communities. The Blue Springs Lake site is on 
the East Fork of the Little Blue River about one-half mile 
south of U.S. Highway 40 and the Longview Lake site is 
on the main stem at approximately 109th Street. 
Existing project. The Blue Springs dam is an earthfill 
embankment about 2,500 feet long and rising about 78 feet 
above the streambed, with an uncontrolled service spillway 
and uncontrolled outlet conduit. The total reservoir storage 
capacity is 26,600 acre-feet (15,700 for flood control, 10,600 
for multipurpose storage for water quality and recreation, 
and 300 for sedimentation). 
The Longview dam is an earthfill embankment about 
1,900 feet long and rising about 120 feet above the streambed, 
with an uncontrolled service spillway and an uncontrolled 
outlet conduit. The total reservoir storage capacity 
is 46,900 acre-feet (24,300 for flood control and 20,600 for 
multipurpose storage for water quality and recreation, and 
2,000 for sedimentation). Estimated Federal cost (1989) for 
both lakes through construction of the project is 
$140,750,000. Construction was initiated in September 
1977. 
Local cooperation. Section 2 of the Flood Control Act 
of June 28, 1938 applies. Local interests must share in 
separable cost allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. The Jackson 
County Legislature approved a recreation cost-sharing contract 
on July 5, 1974 which was approved by the Secretary 
of the Army on June 24, 1976. A supplemental agreement, 
signed by Jackson County officials on June 5, 1978, and 
approved by the Secretary of the Army January 10, 1979, 
revised the existing contract to include additional costs 
involved in raising the multipurpose pool elevation at the 
Blue Springs Lake. Estimated reimbursement for recreation 
is $14,564,000 of which $450,000 will be accomplished 
during construction by local interests. 
Operations during fiscal year. Longview Lake is essentially 
complete except for emergency rock stockpiles. Blue 
Springs Lake is complete except for road across dam, 
emergency rock stockpiles, recreation facilities, and interpretive 
exhibits. Project is 99 percent complete. Land 
acquisition is complete. Visitation for FY 1989 was 
3,813,569 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
10. LONG BRANCH LAKE, LITTLE 
CHARITON RIVER, MO 
Location. Damsite is on East Fork of Little Chariton 
River in north-central Missouri about 1 mile west of Macon 
in Macon County. 
Existing project. An earthfill dam about 3,800 feet long 
and about 71 feet high with an uncontrolled outlet conduit 
and an uncontrolled service spillway in right abutment. Total 
reservoir storage capacity is 65,000 acre-feet (29,000 for 
flood control, 4,000 for sediment reserve, and 32,000 of 
multipurpose storage for water supply, water quality control, 
fish and wildlife, and recreation). Estimated Federal 
cost (1989) is $19,454,000, and estimated non-Federal cost 
is $2,801,000. Construction was initiated in March 1973. 
Project was placed in useful operation for flood control on 
September 1, 1980. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Local interests must make reimbursement 
of $5,567,000 for water supply storage in accordance 
with Water Supply Act of 1958 and share in separable 
cost of $2,801,000 allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. On 
September 15, 1972 the Secretary of the Army approved 
a contract signed by the City of Macon, Missouri, for water 
supply and recreation development. Missouri state agencies 
indicated their intent to sponsor future water supply and 
signed a contract on June 17, 1977 to sponsor recreational 
development in lieu of City of Macon. After review by the 
Office of the Secretary of the Army, the state signed the 
contract in December 1979, and it was approved by the 
Secretary of the Army on April 18, 1980. 
Operations during fiscal year. Visitation for FY 1989 
was 1,229,265 visitor hours. Project is 99 percent complete 
on scheduled work. The remaining work is construction of 
recreation facilities. Maintenance: Activities consisted of 
ordinary operation and maintenance. 
11. MELVERN LAKE, MARAIS DES 
CYGNES (OSAGE) RIVER, KS 
Location. Damsite is on Marais des Cygnes (Osage) River 
in Osage County, Kansas, about 2 miles west of Melvern, 
Kansas. 
Existing project. An earthfill dam about 9,700 feet long 
and about 98 feet high with an uncontrolled chute-type 
spillway in left abutment. Total reservoir storage capacity 
is 363,000 acre-feet (200,000 for flood control, 26,000 for 
sediment reserve, and 137,000 of multipurpose storage for 
water quality control, and recreation). Cost of constructing 
the completed project was $37,436,530. Construction was 
initiated in July 1967, and the project was placed in operation 
in August 1972. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 5,494,562 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
27-4

KANSAS CITY, MO., DISTRICT 
12. MILFORD LAKE, REPUBLICAN 
RIVER, KS 
Location. Damsite is on Republican River near village 
of Alida and about 8 miles downstream from Milford, Geary 
County, Kansas, and about 10 miles above confluence of 
Republican and Smoky Hill Rivers which form Kansas River 
near Junction City, Kansas. 
Existing project. An earthfill dam about 6,300 feet long 
and 126 feet high with an uncontrolled service-chute 
spillway in a saddle on right abutment. Total reservoir 
storage capacity is 1,160,000 acre-feet (700,000 for flood 
control, 160,000 for sediment reserve and 300,000 of 
multipurpose storage for water supply, water quality control, 
and recreation). Water supply storage is included in 
project at request of Governor of Kansas under provisions 
of Federal Water Supply Act of 1958. Initial cost of constructing 
the completed project was $48,268,843. Total 
Federal cost of project, including $1,297,649 supplemental 
recreational development (Code 710), is $49,566,492. Construction 
was initiated in July 1961. Project was placed in 
operation in June 1965. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must make reimbursement of 
$13,045,576 for water supply storage in accordance with 
Water Supply Act of 1958. Utilization of storage has not 
been initiated. Reimbursement was initiated, at the option 
of the State, in September 1976. 
Operations during fiscal year. Visitation for FY 1989 
was 5,529,347 visitor hours. Maintenance: Activities included 
replacing relief wells and ordinary operation and 
maintenance. 
13. MISSOURI RIVER LEVEE 
SYSTEM, IA, NE, KS, AND MO 
(RULO, NE, TO MOUTH) 
Location. On both banks of Missouri River from Sioux 
City, Iowa, about 760 miles to mouth near St. Louis, 
Missouri. Portion of project in Kansas City District 
extends from Rulo, Nebraska, 498 miles to mouth. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from 
Sioux City, Iowa, to the mouth, for protection of agricultural 
lands and small communities against floods. 
Estimated cost (1989) for the active portion of the project 
from Rulo, Nebraska, to mouth is $81,696,000, including 
$76,485,000 Federal and $5,211,000 non-Federal contributions. 
Costs of $7,949,000 for lands and damages are to be 
borne by local interests. Remaining portion of project consists 
of units on which planning and construction are being 
delayed pending completion of restudy to assure that 
additional levee construction is economically justified. Cost 
estimate for deferred, inactive, and deauthorized portion of 
project Rulo, Nebraska, to mouth is $432,354,000 (1964, 
1986, and 1987 price levels), of which $393,956,000 is 
Federal cost for construction and $38,398,000 for lands and 
damages to be borne by local interests. Construction of the 
project was initiated in June 1948. 
Local cooperation. Section 3, Flood Control Act of 1936 
applies. Fully complied with for all completed units and 
units under construction. Local sponsors provide all operation 
and maintenance. 
Operations during fiscal year. Status of individual units 
of active portion of project at end of fiscal year is shown 
in Table 27-H on Missouri River Levee System. Planning 
on remaining active unit continued. 
14. PERRY LAKE, DELAWARE 
RIVER, KS 
Location. Damsite is on Delaware River about 5 miles 
above mouth in Jefferson County, Kansas, about 3 miles 
north of Perry, Kansas 
Existing project. An earthfill dam about 7,750 feet long 
constructed to an elevation about 95 feet above valley floor 
with gated-outlet works and an uncontrolled spillway in left 
abutment. Total reservoir storage capacity is 770,000 acrefeet 
(480,000 for flood control, including 140,000 for sediment 
reserve and 150,000 of multipurpose storage for water 
supply, water quality control, and recreation). Water supply 
storage is included in project plan at request of State 
of Kansas under provisions of Federal Water Supply Act 
of 1958. Initial cost of constructing the completed project 
was $48,371,706. Total Federal cost of project, including 
$724,212 supplemental recreational development (Code 
710), is $49,095,918. Construction was initiated in March 
1964, and the project was placed in operation in January 
1969. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must make reimbursement of 
$9,208,342 for water supply storage in accordance with 
Water Supply Act of 1958. Utilization of storage has not 
been initiated. Reimbursement was initiated at the option 
of the State in September 1978. 
Operations during fiscal year. Visitation for FY 1989 
was 4,681,905 visitor hours. Maintenance: Activities included 
painting gates and frames, renovating and stabilizing 
relief wells, and ordinary operation and maintenance. 
15. PICK-SLOAN MISSOURI BASIN 
PROGRAM (KANSAS CITY DIST.) 
Location. Flood control improvements included in this 
project are on and along the Missouri River and several of 
its principle tributaries, in states comprising the Missouri 
River Basin. 
Existing project. The Pick-Sloan Missouri Basin program 
for flood control and other purposes in Missouri River 
Basin provides for levees along Missouri River between 
Sioux City, Iowa, and the mouth, flood-protection works at 
certain municipalities, and reservoirs on main stem of 
Missouri River and on tributaries for control of flooding. 
(See Table 27-B for authorizing legislation and Table 27-I 
on Kansas City District projects included in Pick-Sloan 
Missouri Basin program.) See individual project reports. 
27-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
16. POMME DE TERRE LAKE 
POMME DE TERRE RIVER, MO 
Location. Dam is on main stem of Pomme de Terre River, 
about 44 miles above mouth of stream in Hickory County, 
Missouri. The lake extending upstream into Polk County, 
Missouri. Site is about 3 miles south of Hermitage, Missouri, 
and 20 miles north of Bolivar, Missouri. 
Existing project. An earth and rockfill dam about 4,630 
feet long constructed to about 155 feet above riverbed and 
a dike section on left abutment about 2,790 feet long, providing 
storage capacity of 650,000 acre-feet (407,000 for 
flood control and 243,000 for sedimentation and multipurpose). 
Initial cost of constructing the completed project 
was $14,946,784. Total Federal cost of project, including 
$329,140 area redevelopment and $2,089,529 supplemental 
recreational development (Code 710), is $17,365,453. 
Construction was initiated in January 1957, and the project 
was placed in useful operation in October 1961. 
Operations during fiscal year. Visitation for FY 1989 
was 7,645,745 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
17. POMONA LAKE, ONE HUNDRED 
TEN MILE CREEK, KS 
Location. Dam is on One Hundred Ten Mile Creek, a 
tributary of Marais des Cygnes (Osage) River, 7 miles above 
mouth of stream in Osage County, Kansas, about 7 miles 
northwest of Pomona, Kansas, and 34 miles upstream from 
Ottawa, Kansas. 
Existing project. An earthfill dam 7,750 feet long constructed 
to an average height of about 85 feet above 
streambed, with gated-outlet workes and an ungated chutetype 
spillway near left abutment. Total reservoir storage 
capacity is 230,000 acre-feet (160,000 for flood control, 
14,000 for sediment reserve, and 56,000 of multipurpose 
storage for water quality control, and recreation). Initial 
cost of constructing the completed project was $13,272,108. 
Total Federal cost of project, including supplemental recreational 
development $731,130 (Code 710), is $14,003,238. 
Construction began in July 1959, and the project was placed 
in operation in October 1963. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Pomona has water supply reimbursement under 
Water Supply Act of 1958 totaling $71,018. 
Operations during fiscal year. Visitation for FY 1989 
was 5,038,082 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
18. RATHBUN LAKE, CHARITON 
RIVER, IA 
Location. Damsite is on Chariton River about 7 miles 
north of Centerville and 1 mile north of Rathbun, Appanoose 
County, Iowa. 
Existing project. An earthfill dam 10,600 feet long constructed 
to an elevation about 86 feet above valley floor, with 
gated-outlet works and an uncontrolled service chute with 
paved sill spillway about a mile upstream from left abutment. 
Total reservoir storage capacity is 552,000 acre-feet 
(339,000 for flood control, 24,000 for sediment reserve and 
189,000 of multipurpose storage for navigation, water 
quality control, and recreation). Initial cost of constructing 
the project was $27,033,210. Total Federal cost of project, 
including $588,948 supplemental recreation development 
(Code 710), is $27,622,158. Construction of the project was 
initiated in September 1964 and completed in November 
1969. The operating plan for this project was revised to 
reduce flood control releases during critical times of the 
year to allow local farmers better access during planting 
and harvesting and to facilitate field drainage and drying 
out. The revised plan has resulted in more frequent high 
pool elevations than anticipated, which has inundated roads 
and recreation facilities. A shoreline erosion study was 
accomplished; and a supplement to the master plan was 
approved, which resulted in relocation of recreation facilities 
and bank stabilization work to compensate for the higher 
lake levels. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 3,233,589 visitor hours. Maintenance: Activities included 
ordinary operation and maintenance. 
19. SMITHVILLE LAKE, LITTLE 
PLATTE RIVER, MO 
Location. Damsite is on Little Platte River about 1 mile 
northeast of Smithville and about 5 miles north of Kansas 
City, in Clay and Clinton Counties, Missouri. 
Existing project. Earthfill dam about 4,200 feet long and 
95 feet high with an uncontrolled service spillway. A dike 
about 2,400 feet long crosses a saddle in left abutment. Total 
reservoir storage capacity is 246,500 acre-feet (92,000 for 
flood control, 52,300 for sediment reserve, and 102,200 of 
multipurpose storage for water supply, water quality control, 
and recreation). Cost of constructing the project was 
$87,685,314. Construction was initiated in November 1973, 
and the project was placed in operation in March 1982. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Reimbursement of $24,000,000 will 
be required for water supply storage in accordance with 
Water Supply Act of 1958, and reimbursement of $7,500,000 
will be required for recreation development in accordance 
with Federal Water Project Recreation Act of 1965. Additional 
non-Federal contribution for recreation amounts to 
$737,000. All contracts for local cooperation were approved 
by the Secretary of the Army on November 27, 1972. 
Operations during fiscal year. Visitation for FY 1989 
was 5,023,366 visitor hours. Maintenance: Activities consisted 
of sediment resurvey, resurfacing road across dam 
and to Litton Visitor Center, and ordinary operation and 
maintenance. 
20. TUTTLE CREEK LAKE, BIG 
BLUE RIVER, KS 
Location. Dam is on main stem of Big Blue River, 
about 12 miles above the mouth of stream in Riley and 
Pottawatomie Counties, Kansas. Site is about 12 miles 
northwest of Manhattan, Kansas. 
27-6

KANSAS CITY, MO., DISTRICT 
Existing project. An earth and rock dam 7,500 feet long 
and 157 feet high. Total reservoir storage capacity is 
2,346,000 acre-feet (1,933,000 for flood control, 228,000 for 
sediment reserve and 185,000 for multipurpose storage, for 
low-flow regulation, navigation, and recreation). Initial cost 
of constructing the completed project was $80,051,031. bTotal 
Federal cost of project, including $533,048 supplemental 
recreational development (Code 710), is $80,584,079. Construction 
began in October 1952. Project was placed in 
operation in July 1962. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 3,585,458 visitor hours. Maintenance: Activities included 
seismic reevaluation, modification and enlargement 
of administration building, and ordinary operation and 
maintenance. 
21. WILSON LAKE, SALINE RIVER, KS 
Location. Dam is on Saline River about 130 miles above 
its mouth, near eastern edge of Russell County, Kansas, 
about 50 miles west of Salina, 10 miles north of Wilson, and 
20 miles east of Russell, Kansas. 
Existing project. An earthfill dam about 5,600 feet long 
and 160 feet high with a gated-outlet works, chute spillway, 
storage capacity is 776,000 acre-feet (511,000 for flood control, 
40,000 for sediment reserve and 225,000 multipurpose 
storage for irrigation, navigation, and low flow regulation). 
Initial cost of constructing the project was $20,015,023. 
Tobtal Federal cost of project, including $448,344 supplemental 
recreational development (Code 710), is $20,463,367. 
Construction began in April 1961 and the project was placed 
in operation in December 1964. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 4,647,773 visitor hours. Maintenance: Activity consisted 
of ordinary operation and maintenance. 
22. SCHEDULING OF FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, 1944 Flood Control Act, the Corps 
is responsible for detailed scheduling of operations concerning 
storage capacity reserved for or assigned to flood control 
in reservoirs constructed by Bureau of Reclamation as 
well as those constructed by the Corps. 
23. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, P.L. 738, and subsequent 
acts require local interests to furnish assurances 
that they will maintain and operate certain local protection 
projects after completion in accordance with regulations 
prescribed by the Secretary of the Army. District Engineers 
are responsible for administration of these regulations 
within boundaries of their respective district. (See Table 
27-J on inspection of completed flood control projects.) 
24. DISASTER PREPAREDNESS 
PROGRAM-INSPECTIONS 
Non-Federal flood protection works constructed or 
rehabilitated under P.L. 84-99 must be inspected by the 
Corps of Engineers to assure compliance with local cooperation 
agreements. 
25. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
Antecedent Legislation). 
Operations for period October 1, 1988 thru September 30, 
1989 were as follows: 
Disaster Preparedness Program includes planning, 
training, inspection, supplies and equipment and personnel. 
Inspections of both non-Federal farm levees and Federal 
authorized levees to assure compliance with eligibility and 
maintenance requirements were performed during FY 
1990. 
Drought Assistance emergency hauling of potable water 
to eight drought-distressed communities in Iowa was undertaken 
during the fourth quarter of FY 1989. This assistance 
will continue in FY 1991. 
(See Table 27-L for costs.) 
Small Flood Control Projects Not Specifically 
Authorized by Congress (Sec. 205, 1948 Flood Control 
Act, Public Law 858, 80th Cong., June 30, 1948, as 
amended). 
Each project selected must be complete in itself, 
economically and environmentally justified, and limited to 
a Federal cost of not more than $5 million. The local sponsoring 
agency must agree to provide without cost to the 
Department of the Army, all lands, easements, and rightsof-
way, including highway, highway bridge, and utility relocations 
and alterations; hold and save the Department of the 
Army free from damages; maintain and operate the project 
after completion; assume all project costs in excess of 
the Federal cost limit; and prevent future encroachments 
on improved channels. 
The Water Resources Development Act of 1986 requires 
the non-Federal sponsors of Section 205 projects to pay 50 
percent of the cost of the feasibility study. For structural 
flood control projects, the sponsor must pay in cash during 
the construction at least 5 percent of the construction cost. 
The sponsor's cash and other contributions must equal 25 
percent of the total construction cost, but will not be required 
to exceed 50 percent. 
There were no Section 205 projects under construction 
in Fiscal Year 1989. 
See Table L for expenditures under Section 205 during 
Fiscal Year 1989. 
Emergency Streambank Protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Cong., July 24, 
1946) as amended. 
Each project selected must be complete in itself, engineeringly 
feasible, economically justifiable, environmentally 
acceptable, and limited to a Federal statutory cost of 
27-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
not more than $500,000. The local sponsoring entity must 
agree to provide without cost to the Department of the 
Army, all lands, easements, and rights-of-way, including 
highway, highway bridge, and utility relocations and alterations 
required for project construction; provide over the 
period of construction, an amount equal to not less than 
25 percent or more than 50 percent of total project cost, 
at least 5 percent of which will be cash; operate, maintain, 
repair, replace, and rehabilitate the project upon completion; 
hold and save the Department of the Army free from 
damages arising from the construction, operation, and 
maintenance of the completed project; and assume all 
project costs in excess of the Federal statutory cost limit. 
Projects that were physically complete in FY 89, but will 
be financially completed in FY 90 are as follows: 
Little Blue River, Clay County, NE, Weyenberg Bridge 
- Construction was completed in February 1989 on this 
project to protect the county road and bridge from floodcaused 
erosion. The project consists of a concrete rubble 
fill revetment along both the right and left streambanks to 
protect the bridge abutments. 
Little Blue River, Nuckolls County, NE, Bridge 4525 - 
Construction was completed in March 1989 on this project 
to protect the county road and bridge. The project consists 
of concrete rubble streambank paving with a reinforced toe 
along the left streambank and a concrete rubble fill revetment 
along the right streambank to protect the bridge 
abutments. 
Chariton River, Schuyler County, MO, Eason Bridge - 
Construction was completed in July 1989 on this project 
to protect the county road and bridge. The project consists 
of a stone fill revetment with baffle dikes along the left 
streambank. 
West Fork Grand River, Ringgold County, IA, Parker 
Bridge - Construction was completed in September 1989 
on this project to protect the county road and bridge. The 
project consists of stone streambank paving with a 
reinforced toe along the left streambank. 
West Fork Grand River, Ringgold County, IA, Redding 
Bridge - Construction was completed in September 1989 
on this project to protect the county road and bridge. The 
project consists of stone streambank paving with a 
reinforced toe along both the right and left streambanks. 
See Table L for Emergency Streambank Protection 
expenditures during Fiscal Year 1989. 
Multiple Pupose Projects 
Including Power 
26. HARRY S. TRUMAN DAM AND 
RESERVOIR, OSAGE RIVER, MO 
Location. Damsite is on main stem of Osage River about 
1.5 miles northwest of Warsaw, Benton County, Missouri. 
Reservoir extends into Bates, Henry, Hickory, St. Clair, and 
Vernon Counties, Missouri. 
Existing project. An earthfill dam about 5,000 feet long 
constructed to an average height of about 96 feet above 
streambed, including a gate-controlled overfall spillway section 
and a power installation consisting of six inclined pumpgenerating 
units with total capacity of 160,000 kilowatts. 
Total reservoir storage capacity is 5,202,000 acre-feet 
(3,918,000 for flood control, 244,000 for sediment reserve, 
and 1,040,000 multipurpose storage for power, low-flow 
regulation, and recreation). Public Law 91-267, approved 
May 26, 1970, authorized a change in project name from 
Kaysinger Bluff Dam and Reservoir, Osage River Basin, 
Missouri, to the Harry S. Truman Dam and Reservoir. 
Estimated cost (1989) through construction of the project 
is $549 million. Construction of relocation of Missouri 
Highway M-13 was initiated September 1964 and completed 
May 1966. Construction of the dam and reservoir was initiated 
in October 1964. The embankment has been completed 
including paving the top of the dam roadway. The 
spillway was completed in October 1979. The Southwestern 
Power Administration powerline needed for final testing 
and commercial operation of the generators was completed 
in December 1979. The first power unit was placed on line 
on December 22, 1979. Subsequent problems with the turbine 
bearing required remedial design on the bearing. 
Restricted commercial power production began in April 
1982. Through September 1989, power generation totaled 
2,631,813,800 kilowatt hours. Of the gross income from the 
sale of power by Southwestern Power Administration, 
$43,642,662 was allocated to the Corps of Engineers for 
project power operating costs, interest, and investment 
recovery. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operation during fiscal year. Visitation for FY 1989 was 
11,269,544 visitor hours. Work was continued on acquisition 
of land and rights-of-way and construction of the 
powerplant. Project is 97 percent complete. During FY 
1989, 148,237,000 kilowatt-hours of electrical power were 
generated. Maintenance: Activities consisted of continuation 
of contract for repair of turbine blade, painting gates, 
road repair, and ordinary operation and maintenance. 
27. STOCKTON LAKE, SAC RIVER, MO 
Location. Damsite is on Sac River about 49.5 miles above 
its confluence with Osage River, and about 2 miles east of 
Stockton, Cedar County, Missouri, lake extending into Dade 
and Polk Counties. 
Existing project. A rock-shell dam with impervious core 
about 5,100 feet long constructed to an average height of 
about 128 feet, with a gated overfall spillway and a 
45,200-kilowatt power installation. Ibtal reservoir storage 
capacity is 1,674,000 acre-feet (774,000 for flood control, 
25,000 for sediment reserve and 875,000 multipurpose 
storage for power and recreation). Initial cost of constructing 
the completed project was $75,715,300. Estimated cost 
of the project, including $3,758,000 for downstream channel 
work and $502,057 for supplemental recreational 
development (Code 710), is $79,975,357 (1988). Construction 
was initiated in October 1963, and the project was 
placed in operation in December 1969. Power operation 
problems were encountered with the initial operation in 
March 1973 because the downstream channel did not have 
the capacity which earlier observations and computations 
indicated. As a result, it has been necessary to restrict the 
power operation to about the 30,000 kilowatt level. Rightof-
way for construction of a channel cutoff and bridge at 
Horseshoe Bend has been acquired, and construction has 
been completed. Sloughing easements downstream to Caplinger 
Mills have been acquired. Completion assured 
27-8

KANSAS CITY, MO., DISTRICT 
downstream channel capacity to Caplinger Mills of 8,000 
c.f.s. for powerplant operation. Discharge in this range will 
accommodate power operations at a 39,500-kilowatt level. 
Through September 1989, power generation totaled 
991,699,800 kilowatt-hours. Of the gross income from the 
sale of power by Southwestern Power Administration, 
$19,379,635 was allocated to the Corps of Engineers for 
project operating costs, interest, and investment recovery. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1989 
was 6,933,586 visitor hours. The project is complete and in 
operational status. The net amount of power marketed 
with Southwestern Power Administration was 46,619,000 
kilowatt-hours. Maintenance: Activities consisted of installation 
of microwave communication system and ordinary 
operation and maintenance. 
General Investigations 
28. GENERAL INVESTIGATIONS 
Fiscal year 1989 costs totaled $1,041,744 for all General 
Investigations activities. See Table 27-K which covers 
Surveys, Collection and Study of Basic Data, and 
Preconstruction Engineering and Design. 
27-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
Missouri River, 
Sioux City, IA 
to Mouth (Rulo, 
Nebr., to Mouth) 
(Federal Funds) 
(Contributed 
Funds) 
(Consolidated 
Summary) 
2. Blue River Channel 
Kansas City, 
MO 
3. Brush Creek, 
Kansas City, 
MO 
4. Clinton Lake, 
Wakarusa 
River, KS 
5. Harlan County 
Lake, Republican 
River, NE 
6. Hillsdale Lake, 
Big Bull 
Creek, KS 
7. Kanopolis Lake, 
Smoky Hill 
River, KS 
8. Little Blue River 
Channel Improvement, 
Little Blue 
River, MO 
9. Little Blue River 
Lakes, Little Blue 
River, MO 
1. 
FY 86 FY 87 FY 88 FY89 Sept. 30, 1989 
I 
Funding 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
6,452,000 
6,489,931 
6,452,000 
6,489,931 
6,052,000 
6,123,287 
325,000 
301,712 
1,237,000 
1,237,034 
5,312,600 
5,312,600 
5,312,600 
5,312,600 
5,750,000 
3,029,536 
488,000 
510,235 
1,193,100 
1,188,950 
4,731,500 
4,731,500 
4,731,500 
4,731,500 
4,370,000 
4,108,250 
752,000 
748,429 
1,554,100 
1,556,750 
1,249,000 1,024,500 1,113,800 1,203,000 
1,230,196 1,039,936 1,115,994 1,202,000 
140,000 
140,000 
611,000 
611,096 
1,696,000 
1,723,084 
55,000 
128,044 
589,300 
587,500 
1,663,400 
1,658,450 
52,007 
6,371,000 4,152,000 
7,060,777 4,165,726 
- 271,600 
- 271,600 
652,900 807,000 
644,700 817,000 
1,541,200 
1,546,150 
25,000 
25,801 
3,997,000 
3,476,930 
646,100 
646,099 
2,222,000 
2,222,000 
9,026 
1,742,000 
642,178 
838,000 
837,970 
27-10 
5,424,000 
5,274,000 
5,424,000 
5,274,000 
7,031,000 
9,982,519 
255,000 
259,530 
1,300,000 
1,301,490 
237,942,1901 
237,942,1901 
285,414,3142 
285,264,3142 
816,190 
816,190 
22,642 
22,642 
238,758,3801 
238,758,3801 
285,436,9562 
285,286,956 
34,951,171 
34,915,2903 
1,820,000 
1,819,906 
57,415,433 
57,415,4334 
11,530,500 
11,530,490 
47,111,926 
47,111,9266 
20,552,761 
20,550,511 
1,017,623 
1,017,623 
64,161,400 
64,161,400 
4,709,700 
4,709,700 
12,577,227 
12,577,2276 
19,404,610 
19,404,610 
25,530,083 
25,530,083 
140,750,200 
139,090,5277 
1,755,700 
1,755,669

KANSAS CITY, MO., DISTRICT 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
10. Long Branch Lake 
Little Chariton 
River, MO 
(Contributed 
Funds) 
(Consolidated 
Summary) 
11. Melvern Lake 
Osage (Marais des 
Cygnes) River, KS 
12. Milford Lake, 
Republican River, 
KS 
13. Missouri River 
Levee System 
IA, NE, KS 
and MO 
14. Perry Lake, 
Delaware River, KS 
16. Pomme de Terre 
Lake, Pomme de 
Terre River, MO 
17. Pomona Lake, One 
Hundred Ten Mile 
Creek, KS 
18. Rathbun Lake, 
Chariton River, 
IA 
19. Smithville Lake, 
Little Platte 
River, MO 
Total Cost to 
Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
480,000 
374,529 
685,100 
680,100 
-5,803 
224,016 
474,197 
598,545 
1,046,000 1,213,200 
1,046,062 1,213,200 
1,273,000 1,557,400 
1,273,091 1,555,900 
583,000 2,129,000 
583,031 742,202 
1,533,000 
1,576,795 
1,453,000 
1,454,098 
1,058,000 
1,058,022 
1,609,500 
1,627,595 
-33,000 
370,426 
987,000 
990,924 
1,503,200 
1,502,000 
1,277,400 
1,277,400 
1,165,900 
1,163,088 
1,321,300 
1,331,082 
67,000 
35,559 
801,100 
801,050 
20,675 
562,100 
567,100 
146,717 
167,392 
15,371 
627,000 
627,000 
15,371 
1,400,400 1,292,000 
1,400,400 1,292,000 
1,939,600 
1,942,100 
904,000 
2,137,188 
1,427,300 
1,426,000 
1,453,700 
1,452,200 
1,177,900 
1,168,483 
1,565,900 
1,575,400 
37,136 
862,500 
862,550 
1,631,000 
1,630,995 
655,000 
809,164 
48,721 
503,000 
503,029 
484,612 
59,520 
484,612 
108,241 
- 49,095,918 
- 49,095,918 
1,651,000 22,224,984 
1,630,496 22,201,980 
- 17,365,452 
- 17,365,452 
1,346,000 20,665,612 
1,347,500 20,665,612 
- 14,003,238 
- 14,003,238 
1,262,000 17,582,133 
1,274,229 17,582,133 
- 27,622,159 
- 27,622,159 
1,535,000 20,589,918 
1,535,500 20,589,918 
- 87,685,315 
- 87,685,315 
1,246,000 8,006,600 
1,246,000 8,006,600 
27-11 
18,286,177 
18,215,319 
4,827,700 
4,827,700 
1,119,3318 
1,004,324 
19,405,5089 
19,219,643 
37,436,530 
37,436,530 
15,262,360 
15,262,360 
49,566,492 
49,566,492 
20,669,524 
20,669,519 
60,573,851 
60,573,802

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
20. Tuttle Creek Lake New Work: 
Big Blue Approp. - - - - 80,584,079 
River, KS Cost- - - 80,584,079 
Maint. 
Approp. 1,375,000 2,036,400 2,860,100 1,666,000 22,301,279 
Cost 1,376,718 2,022,437 2,867,463 1,672,600 22,304,279 
21. Wilson Lake, New Work: 
Saline River, Approp. - - - - 20,463,367 
KS Cost - - - 20,463,367 
Maint. 
Approp. 1,458,000 1,671,900 974,900 1,234,000 15,705,846 
Cost 1,239,997 1,889,950 974,900 1,209,540 15,681,386 
22. Scheduling Flood Maint. 
Control Reservoir Approp. 195,160 164,000 177,000 180,000 54,535,483 
Operations Cost 195,160 164,000 177,000 180,000 54,535,483 
23. Inspection of Maint. 
Completed Flood Approp. 350,340 287,400 366,000 338,000 4,984,815 
Control Projects Cost 350,490 287,400 366,000 338,000 4,984,815 
24. Disaster Prepared- Maint. 
ness Program- Approp. 138,000 39,000 132,000 200,2501� 830,250 
Inspections Cost 138,546 39,000 132,000 200,241 830,241 
26. Harry S. Truman New Work: 
Dam & Reservoir Approp. 3,093,000 3,507,000 4,868,000 2,660,000 535,617,900 
Osage River, MO Cost 3,563,417 3,412,650 4,244,971 2,359,661 534,555,484 
Maint. 
Approp. 5,136,000 6,444,100 6,997,600 6,012,500 45,307,400 
Cost 5,133,990 6,438,198 6,993,112 6,026,000 45,307,400 
27. Stockton Lake, New Work: 
Sac River, MO Approp. 73,000 201,000 43,000 - 79,975,357 
Cost 451,361 220,675 37,772 9,756 79,968,442 
Maint. 
Approp. 1,830,000 2,217,200 2,394,500 2,777,500 28,557,500 
Cost 1,839,804 2,220,270 2,394,560 2,775,794 28,555,794 
1. Includes $8,665,594 costs of new work for previous _ 6. Excludes cost of materials furnished without charge 
project. 
2. Includes $738,109 for maintenance of previous 
project. 
3. Excludes $35,296 non-Federal contribution not required 
for authorized project (Blue River Channel Mobay Chemical 
1984-1987). 
4. Excludes $118,805 non-Federal contribution not required 
for authorized project (1973-1979). 
5. Excludes cost of materials furnished without charge 
in the amount of $24,198. 
in the amount of $7,885. 
7. Excludes $2,727,401 thru FY 1989 non-Federal contributions 
not required for authorized project. 
8. Correct total is $1,095,596, which includes $43,074 
interest during construction. Correction pending. 
9. Correct amount is $19,381,773. 
10. After FY 1988 inspections of non-Federal levees 
previously funded under O&M are funded under FC&CE, 
96X3125 (910-140) Disaster Preparedness Program- 
Inspections which had a carryover into FY 1989 of $250. 
27-12

KANSAS CITY, MO., DISTRICT 
TABLE 27-B AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
Jul. 25, 1912 
Aug. 8, 1917 
Mar. 3, 1925 
Jan. 12, 1927 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Dec. 31, 1970 
Nov. 17, 1986 
Oct. 23, 1962 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Sep. 3, 1954 
Jun. 28, 1938 
MISSOURI RIVER, SIOUX CITY, IA, TO 
MOUTH (RULO, NE, TO MOUTH) 
Project adopted for securing a permanent navigable 
channel of 6-foot depth from Kansas City, MO to 
mouth. 
Fixed upstream limit of improvement at upper end of 
Quindaro Bend (374.8 miles from mouth) and provided 
for dredging. 
For a mimimum width of 200 feet and depth of 6 feet, 
with a reasonable additional width around bends, 
mouth to upper end of Quindaro Bend, Kansas City, 
MO. 
Appropriation of $12 million authorized for securing a 
6-foot channel depth between Kansas City, MO, 
Quindaro bend, and Sioux City, IA. 
Appropriation of $15 million additional authorized; 
additional allotments totaling $29,153,108 were made 
by Public Works Administration under provisions of 
National Industrial Recovery Act of 1933, and 
$9,669,791 allotted under provisions of Emergency 
Relief Appropriation Act of 1935. 
Completion of improvement from mouth to Sioux City, 
IA.. 
Securing a navigable channel of 9-foot depth and a 
minimum width of 300 feet. 
BLUE RIVER CHANNEL, KANSAS CITY, MO 
Adopted plan for Blue River Basin and authorized 
$40,000,000 for initiation and partial accomplishment. 
BRUSH CREEK, KANSAS CITY, MO 
Project for flood control on Brush Creek, a tributary of 
the Blue River, Kansas City, MO, authorized at 
estimated total cost of $16,100,000. 
CLINTON LAKE, WAKARUSA RIVER, KS 
The project for the Kansas River, KS, NE, and CO is 
authorized at an estimated cost of $88,070,000. 
HARLAN COUNTY LAKE, REPUBLICAN 
RIVER, NE 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure 
HILLSDALE LAKE, BIG BULL CREEK, KS 
The comprehensive plan for the Missouri River Basin, 
approved by the Act of June 28, 1938, and as 
amended and supplemented is further modified to 
include the project for flood protection on the 
Kansas River and tributaries. It is further modified 
to include the project for flood protection on the 
Osage River and tributaries. 
KANOPOLIS LAKE, SMOKY HILL RIVER, KS 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
H. Doc. 1287, 61st Cong., 
(contains latest published 
map). P.L. 241-62. 
H. Doc. 463, 64th Cong., 
(contains latest published 
map). 
P.L. 585-68. 
H. Doc. 1120, 60th Cong., 
P.L. 560-70. 
P.L. 67-73 
H.R.11781 
P.L. 520-71 
H. Doc. 238, 73d Cong., 
(contains latest published 
map). P.L. 409-73 
H. Doc. 214, 76th Cong., 
(contains latest published 
map). P.L. 14-79. 
H. Doc. 91-332, 91st Cong. 
Sec. 401, Water Resources 
Development Act of 1986, 
P.L. 99-662 
1962 Flood Control Act 
S Doc 122, H. Doc. 578, 
87th Cong., P.L. 87-874. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
H. Doc. 842, 76th Cong.; 
P.L. 77-228. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong., 
P.L. 534. 
P.L. 780, 83rd Cong., H. Doc. 
549, 81st Cong. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
27-13 
2. 
3. 
4. 
5. 
6. 
7.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
8. 
9. 
Aug. 18, 1941 
Dec. 22, 1944 
Aug. 13, 1968 
Aug. 13, 1968 
Oct. 27, 1965 
Sep. 3, 1954 
Sep. 3, 1954 
Aug. 18, 1941 
Dec. 22, 1944 
Sep. 3, 1954 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946 
May 17, 1950 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
LITTLE BLUE RIVER CHANNEL 
Additional $38,000,000 for prosecution of general comprehensive 
plan for Missouri River Basin. 
LITTLE BLUE RIVER LAKES, MO 
Additional $38,000,000 for prosecution of general comprehensive 
plan for Missouri River Basin. 
LONG BRANCH LAKE, LITTLE CHARITON 
RIVER, MO 
The project for flood protection on the Chariton and 
Little Chariton Rivers and tributaries, IA and MO, 
is authorized at an estimated cost of $9,167,000. 
MELVERN LAKE, MARAIS DES CYGNES 
(OSAGE) RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
MILFORD LAKE, REPUBLICAN RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, 
AND MO 
Levees along both sides of river from Sioux City to 
Kansas City. 
Extended project from Kansas City to the mouth and 
provided for increased protection. 
PERRY LAKE, DELAWARE RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(KANSAS CITY DIST.) 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure 
Additional expenditure of $150 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Additional expenditure of $250 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
27-14 
H. Doc. 842, 76th Cong.; 
P.L. 77-228. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong., 
P.L. 534. 
P.L. 90-483 (H. Doc. 169, 
90th Cong. 
P.L. 90-483 (H. Doc. 169, 
90th Cong. 
1965 Flood Control Act, P.L. 
89-298, (H. Doc. 238, 89th 
Cong. 
H. Docs. 642, 5491, and 561, 
83rd Cong., P.L. 780 
H. Doc. 5491 83rd Cong., 
P.L. 780 
H. Doc. 821, 76th Cong. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong. 
H. Docs. 642, 5491 and 561, 
83rd Cong., P.L. 780. 
Flood Control Committee 
Doc. 1, 75th Cong. 
H. Doc. 842, 76th Cong.; 
P.L. 77-228 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong. 
10. 
11. 
12. 
13. 
14. 
15.

KANSAS CITY, MO., DISTRICT 
TABLE 27-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
Sep. 3, 1954 
May 2, 1956 
Jul 3, 1958 
Jul 14, 1960 
Dec 30, 1963 
Jun. 18, 1965 
May 12, 1967 
Aug. 13, 1968 
Dec 24, 1970 
Dec. 23, 1971 
Mar. 7, 1974 
Jun. 28, 1938 
Dec. 22, 1944 
Sep. 3, 1954 
Sep. 3, 1954 
Sep. 3, 1954 
Oct. 27, 1965 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of construction 
of Wilson Dam and Reservoir KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $207 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Additional expenditure of $80 million for prosecution 
of general comprehensive plan for Missouri River 
Basin and modified plan to include bank protection 
or rectification works below Garrison Dam. 
Additional $116 million for prosecution on general 
comprehensive plan for Missouri River Basin. 
Additional $20 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $38,000,000 for prosecution of general comprehensive 
plan for Missouri River Basin. 
Change comprehensive plan name to Pick-Sloan 
Missouri River Basin program. 
Additional $101,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri Basin 
Program. 
Additional $72,000,000 for prosecution of general comprehensive 
plan for Pick-Sloan Missouri Basin Program. 
POMME DE TERRE LAKE, POMME DE TERRE 
RIVER, MO 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,000,000 additional 
expenditure. 
POMONA LAKE, ONE HUNDRED TEN MILE 
CREEK, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
RATHBUN LAKE, CHARITON RIVER, IA 
Expanded general comprehenssive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
SMITHVILLE LAKE, LITTLE PLATTE 
RIVER, MO 
The project for flood protection on the Platte River 
and tributaries, MO and IA, is authorized at an 
estimated cost of $26,889,000. 
H. Docs. 642 and 5491, 83rd 
Cong. 
H. Doc. 409, 84th Cong. 
S. Doc. 91-1100, 91st Cong. 
S. Doc. 92-222, 92nd Cong. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
H. Doc. 475 and S. Docs. 
191 and 247, 78th Cong., 
P.L. 534. 
H. Docs. 642, 5491 and 561, 
83rd Cong., P.L. 780. 
H. Doc. 5491', 561, 83rd 
Cong., P.L. 780. 
H. Doc. 561, 83rd Cong., 
P.L. 780. 
1965 Flood Control Act, 
P.L. 89-298 (H. Doc. 262, 
89th Cong.) 
27-15 
16. 
17. 
18. 
19.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
TUTTLE CREEK LAKE, BIG BLUE RIVER, KS 
20. Jun. 28, 1938 Adopted general comprehensive plan for Missouri Flood Control Committee 
River Basin and authorized $9 million for initiatiion Doc. 1, 75th Cong., 
and partial accomplishment. P.L. 761. 
Aug. 18, 1941 Modified general comprehensive plan to include Harlan H. Doc. 842, 76th Cong.; 
County Dam and Reservoir on Republican River, P.L. 77-228. 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Docs. 
River Basin and authorized $200 million additional 191 & 247, 78th Cong., 
expenditure. P.L. 534. 
WILSON LAKE, SALINE RIVER, KS 
21. Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Docs. 
River Basin and authorized $200 million additional 191 & 247, 78th Cong., 
expenditure P.L. 534. 
Jul. 14, 19602 Additional expenditure of $207 million for prosecution S. Doc. 96, 86th Cong., 
of general comprehensive plan for Missouri River P.L. 645. 
Basin. 
HARRY S. TRUMAN DAM AND RESERVOIR, 
OSAGE RIVER, MO 
26. Sep. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 5491, 83rd Cong., 
River Basin and authorized $217,710,000 additional P.L. 780. 
expenditure. 
Oct. 23, 1962 The Kaysinger Bluff Reservoir is hereby modified in 1962 Flood Control Act, 
accordance with recommendations of the Chief of H. Doc. 578, 87th Cong., 
Engineers in H. Doc. 578, 87th Cong., at an P.L. 87-874. 
estimated additional cost of $43,245,000; provided, 
that nothing in this Act shall be construed as 
authorizing the acquisition of additional lands for 
the establishment of a national wildlife refuge at the 
reservoir. 
STOCKTON LAKE, SAC RIVER, MO 
27. Sep. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 5491, 83rd Cong., 
River Basin and authorized $217,710,000 additional P.L. 780. 
expenditure 
1. Contains latest published maps of Missouri River. 2. Report of Chief of Engineers on justification of Wilson Dam 
and Reservoir, submitted in compliance with Public Law 505, 
84th Congress, published as Senate Document 96, 86th Congress, 
was approved July 14, 1960 (Public Law 645). 
TABLE 27-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Fort Leavenworth Bridge removal Complete 1965 270,393 - 
Gasconade River, MO 1, 2 Complete 1931 139,003 85,077 
Osage River, MO, lock and dam3 Complete 1952 658,076 850,495 
1. Improvement adequate for existing needs. Project for 
maintenance only. 
2. Curtailment of project in H. Doc. 467, 69th Cong. 
3. Operation of lock and dam placed in standby status. 
27-16

KANSAS CITY, MO., DISTRICT 
TABLE 27-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Abilene, KS Completed 1965 1,099,350 - 
Atchison, KS Completed 1973 4,099,590 - 
Barnard, KS' Completed - 127,860 - 
Bartley, NE Completed 1953 118,269 - 
Bedford, East Fork, 102 River, IA' Completed 1974 652,414 - 
Big Blue River, Seward, NE' Completed - 126,887 - 
Big Stranger Creek, KS' Completed - 337,131 - 
Braymer Lake, Shoal Creek, MO Inactive 1966 - - 
Brookfield Lake, Yellow Creek, MO Inactive 1976 451,400 - 
Chariton-Little Chariton Basin, MO (1965 Act)2 1977 692,706 - 
Chariton River, MO (1944 Act) Completed 1973 8,052,990 - 
Dry Fork and East Fork Lakes, 
Fishing River, MO Deferred 1974 51,989 - 
East Muddy Creek, MO Inactive 1966 - - 
Elk Creek, Clyde, KS' Completed 1984 989,015 - 
Fairbury, Little Blue River, NE Completed 1973 726,966 - 
Fort Scott Lake, Marmaton River, KS Active 1976 757,500 - 
Frankfort, Black Vermillion River, KS Completed 1966 1,271,025 - 
Gypsum, Gypsum Creek, KS' Completed 1984 2,782,793 - 
Harry S. Truman Dam and Reservoir, MO 
(Downstream Fish and Wildlife Mitigation) Inactive - - - 
Indianola, NE Completed 1950 67,275 - 
Kansas City, Kansas River, KS (62 Mod) Completed 1984 25,010,500 - 
Kansas Citys on MO and KS Rivers, 
MO and KS3 1980 42,434,197 - 
Lawrence, Kansas River, KS4 Completed 1985 8,773,488 - 
Lower Grand River, MO Inactive 1966 - - 
Manhattan, Kansas River, KS Completed 1967 2,488,585 - 
Melvern Lake and Pomona Lake 
(Road Improvements) KS (1974 Act) Inactive - - - 
Mercer Lake, Weldon River, MO Inactive 1976 432,245 - 
Missouri River at New Haven, MO 
(Sec 212, 1950 Act) Completed - 139,883 - 
Missouri River Fish and Wildlife Mitigation Active - - - 
Osawatomie, Pottawatomie Creek, KS Completed 1973 2,036,624 - 
Ottawa, Osage (Marais des Cygnes) River, KS Completed 1966 4,462,661 - 
Pattonsburg Lake, Grand River, MO Inactive 1976 - - 
Pattonsburg Lake, Grand River, MO 
(Advance Highway Relocation) Inactive 1976 393,623 
Pattonsburg Lake, Grand River, MO 
(Advance Town Relocation) Inactive 1976 91,929 - 
Perry Lake Area (Road Improvements), KS Completed 1982 5,315,168 - 
Platte River, MO, Channel Improvement Deferred 1973 222,193 - 
Rathbun Lake Fish Hatchery Completed 1975 700,000 - 
Salina, Smoky Hill River, KS Completed 1967 3,878,668 - 
Seward, NE' Completed - 126,887 - 
Smithville Channel, Little Platte River, MO Deferred 1973 6,896 - 
Smithville Lake, Trimble Wildlife Area Active - - - 
Stonehouse Creek, Jefferson Co., KS' Completed 1972 246,995 - 
Topeka, Kansas River, KS Completed 1974 21,174,593 - 
Trenton Lake, Thompson River, MO Inactive 1966 - - 
Tuttle Creek Lake, KS 
Road and Bridge (1976 Act) Inactive - - - 
Upper Grand River, MO Inactive 1966 - - 
1. Authorized by the Chief of Engineers under Section 205, 3. Includes $619,787 non-Federal contributions for work 
Public Law 858, 80th Congress, as amended, desired by local interests, but not required under the project. 
2. Little Chariton River (East and Middle Fork) and The project as a whole is complete except for Turkey Creek 
Mussell Fork classified inactive. Construction cost includes facilities in Central Industrial District Unit. 
$481,106 cost of completed Shoal Creek Unit and $211,600 cost 4. Includes $153,377 non-Federal contributions. 
for inactive units, Little Chariton River and Mussell Fork. 
27-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-G DEAUTHORIZED PROJECTS 
Project 
Arlington Lake, MO 
For Last 
Full Report 
See Annual 
Re] 
Beatrice, Big Blue River, NE 
Garnett Lake, Pottawatomie 
Creek, KS 
Grove Lake, Soldier Creek, KS 
Hackleman Corners Lake, 
Cedar Creek, MO 
Hays, Big Creek, KS 1 
Indian Lake, Blue River, KS 
Kansas River Navigation 
Marysville, KS 
Merriam, Turkey Creek, KS 
Mill Lake, Blue River, MO 
Missouri River Levee System, 
KS, Units R402; R393-395; 
and R414 
Onaga Lake, Vermillion Creek, 
Pioneer Lake, KS 
Richland Lake, MO 
Tomahawk Lake, 
Blue River, KS 
Tuttle Creek Lake, KS (Road 
Improvement- 1974 Mod.) 
Wolf-Coffee Lake, Blue River, 
KS 
Contributed 
Funds 
Expended 
-T 
Date 
Deauthorized 
Aug. 5, 1977 
port For Date and Authority 
1948 Flood Control Act approved 
June 28, 1938, as modified by 
Flood Control Act approved 
August 18, 1941, and expanded 
by Flood Control Act approved 
December 22, 1944 
1965 Flood Control Act approved 
September 3, 1954 
1973 Flood Control Act approved 
September 3, 1954 
1977 1962 Flood Control Act (S. Doc. 
122, 87th Cong. 2d sess.) 
- Authorized by Flood Control Act 
approved September 3, 1954 
1974 Flood Control Act of 1965 approved 
October 27, 1965 
1976 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.) 
1980 1965 Flood Control Act, 
P.L. 89-298, Sec. 201 
- Flood Control Act of September 3, 
1954 
1970 Flood Control Act approved 
September 3, 1954 
1971 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.) 
- Flood Control Act of August 18, 
1941, P.L. 228, 77th Cong. 
1982 Flood Control Act of 1962, 
October 23, 1962 (P.L. 87-874) 
1952 Flood Control Act approved 
June 28, 1938, as modified by 
Flood Control Act of August 18, 
1941, and expanded by Flood 
Control Act approved 
December 22, 1944 
1948 Flood Control Act approved 
June 28, 1938, as modified by 
Flood Control Act approved 
August 18, 1941, and expanded 
by Flood Conotrol Act approved 
December 2, 1944 
1976 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.) 
1977 Sec. 18 of Water Resources 
Development Act of 1974 
1976 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.) 
1. A study of water supply and flood problems at Hays, 
KS, is being studied under Section 205, Public Law 858, 80th 
Congress, as amended. 
27-18 
I 
Federal 
Funds 
Expended 
$8,651 
16,317 
71,466 
1,754,019 
499,200 
127,297 
259,900 
133,682 
39,708 
57,500 
2,178,261 
95,692 
8,548 
77,189 
3,000 
1,095,020 
- May 6, 1981 
- Nov. 17, 1986 
- Nov. 17, 1986 
- Aug. 5, 1977 
- Jan. 18, 1978 
- Nov. 17, 1986 
Nov. 17, 1986 
- Jan. 1967 
- Nov. 27, 1973 
Nov. 17, 1986 
- Nov. 17, 1986 
- Nov. 17, 1986 
- Aug. 5, 1977 
Aug. 5, 1977 
- Nov. 17, 1986 
- Nov. 17, 1986 
- Nov. 17, 1986

TABLE 27-H 
KANSAS CITY, MO., DISTRICT 
MISSOURI RIVER LEVEE SYSTEM 
(See Section 13 of Text) 
Unit 
R 512-513 Richardson Co. D. D. #7 
R 500 Iowa Point D. D. #4 
Kimsey Holly Creek 
L 497 Forest City L. D. 
L488 Holt Co. D. D. #7 
R 482 Burr Oak D. D. #3 
L 476 Amazonia L. D. 
R 460-471 Elwood-Gladden L. D. 
L 455 S. St. Joseph L. D. 
L 443-448 Halls L. D. 
R 440 Atchison & Doniphan Co. D. D. 
L 408 Farley-Beverly D. D. 
L 400 Waldron L. D. 
L 385 Riverside-Quindaro D. D. 
R 351 Atherton L. D. 
L 330-345 Orrick L. D. 
L 319-325 Henrietta-Crooked River D. D. 
L 246 Brunswick-Dalton D. D. 
L 15 North County L. D. 
Remaining units 
Miles of 
Levee 
19.1 
4.1 
4.4 
16.0 
11.5 
8.2 
10.8 
13.8 
15.6 
17.3 
10.7 
12.2 
7.6 
6.5 
15.9 
43.4 
35.0 
20.0 
40.0 
Status 
Complete- 1958 
Complete-1954 
Complete-1970 
Complete- 1962 
Complete-1955 
Complete- 1954 
Complete- 1956 
Complete- 1968 
Complete- 1967 
Complete-1957 
Complete-1959 
Complete (Levee raise modification)-1972 
Complete-1957 
Planning underway 
Complete- 1966 
Inactive 
Inactive 
Complete- 1983 
Inactive 
Detailed planning not initiated 
27-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-I KANSAS CITY DISTRICT PROJECTS INCLUDED IN 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 15 of Text)
Estimated Estimated 
Project Federal Non-Federal 
Cost Cost 
Abilene, Smoky Hill River, KS $ 1,099,350 $ 287,000 
Bartley, Republican River, NE 118,269 9,500 
Fort Scott Lake, Marmaton River, KS 90,500,000 44,800,000 
Garnett Lake, Pottawatomie Creek, KS1 71,4662 
Harlan County Lake, Republican River, NE 48,129,549 - 
Harry S. Truman Dam and Reservoir, Osage River, MO 549,000,000 138,688,000 
Hillsdale Lake, Big Bull Creek, KS 64,161,400 23,342,756 
Indianola, Republican River, NE 67,275 7,592 
Kanopolis Lake, Smoky Hill River, KS 12,577,227 - 
Lawrence, Kansas River, KS 8,620,111 2,130,000 
Manhattan, Kansas River, KS 2,488,585 265,000 
Melvern Lake, Osage (Marais des Cygnes) River, KS 37,436,530 
Melvern Lake and Pomona Lake (Road Improvement), 
KS (1974 Authorization)8 500,000 214,300 
Milford Lake, Republican River, KS 49,566,492 - 
Missouri River Levee System, Rulo to the Mouth4 76,485,000 13,160,000 
Osawatomie, Osage (Marais des Cygnes) River, KS 2,036,624 348,300 
Ottawa, Osage (Marais des Cygnes) River, KS 4,462,661 876,000 
Perry Lake, Delaware River, KS 49,095,918 - 
Pomme de Terre Lake, Pomme de Terre River, MO 17,365,453 - 
Pomona Lake, Osage River Basin, KS 14,003,238 - 
Salina, Smoky Hill River, KS 3,878,668 1,960,000 
Stockton Lake, Sac River, MO 79,975,357 17,458,000 
Topeka, Kansas River, KS 21,174,593 10,383,492 
Tuttle Creek Lake, Big Blue River, KS 80,584,079 - 
Tuttle Creek Lake, KS-Road and Bridge (1976 Act)8 630,000 610,000 
Tuttle Creek Lake (Road Improvement), KS (1974 Modification) 1 500,000 214,300 
Wilson Lake, Saline River, KS 20,463,367 - 
1. Deauthorized by Water Resources Development Act of 4. Active portion of project. Deferred portion of project is 
1986, P.L. 99-662. currently estimated to cost (1989) $46,753,000 Federal and 
2. Total Federal funds expended. $4,336,000 non-Federal. Inactive portion of project is current- 
3. Inactive. ly estimated to cost (1989) $347,146,000 Federal and 
$34,062,000 non-Federal. Actual cost of deauthorized units was 
$57,000 Federal. 
TABLE 27-J INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 23 of Text) 
Location Month Inspected 
Missouri River Main Stem 
Missouri River Levees: R 512-513, R 500, Kimsey Holly Creek, L 497, L 488, 
R 482, L 476, R 460-471, L 455, L 443-448, R 440, L 408, L 400 and R 351, L 246 
Kansas Citys, Missouri and Kansas: Argentine, Armourdale, 
Birmingham, CID (Mo & Kans), East Bottoms, Fairfax-Jersey 
Creek, North Kansas City Units, and GSA Federal Complex 
Osage River, Kansas and Missouri 
Ottawa, Kansas 
Osawatomie, Kansas 
Kansas River and Minor Tributaries 
Topeka, Kansas; Auburndale, North Topeka, Oakland, Soldier 
Creek, South Topeka, and Waterworks Units 
Republican River. Nebraska and Kansas 
Bartley, Nebraska 
Smoky Hill. Saline, and Solomon Rivers 
Abilene, Kansas 
Mar/Sep 89 
Mar/Sep 89 
Apr 89/Oct 89 
Apr 89/Oct 89 
Apr 89/Oct 89 
May/Oct 89 
May 89/Oct 89 
27-20

TABLE 27-K 
KANSAS CITY, MO., DISTRICT 
ACTIVE GENERAL INVESTIGATIONS 
(See Section 28 of Text) 
Item and CWIS Number 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Blue River Basin, Overland Park, KS - 12562 
Blue River Basin, Kansas City, MO - 12563 
Grand River Basin, MO & IA - 12432 
Kansas and Osage Rivers, KS - 12204 
Osage River above Harry S. Truman Dam - 14063 
Turkey Creek Basin, KS & MO - 12381 
Subtotal 
Miscellaneous Activities (170) 
Special Investigations -17250 
Interagency Water Res Dev - 14713 
Subtotal 
Coordination Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) - 51840 
Bureau of Reclamation, Dept. Interior (182) - 51820 
Regional Planning (183) - 53847 
Planning Assistance to States (186) - 14820 
Subtotal 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) - 82030/40 
Hydrologic Studies (260) - 53820 
TOTAL (Category 200) 
PRECONSTRUCTION ENGINEERING AND DESIGN 
(Category 600) 
Brush Creek, Kansas City, MO (650) - 12319 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
Federal Cost 
FY 89 
27-21 
Totals By 
Categories 
$21,727 
149,036 
166,929 
6,500 
986 
90,633 
$435,811 
$90,000 
4,998 
$94,998 
$ 9,000 
17,000 
5,000 
35,416 
$66,416 
$597,225 
$173,886 
11,103 
$184,989 
$259,530 
$259,530 
$1,041,744

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 27-L FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
(See Section 25 of Text) 
Fiscal 
Year 
Study Status' Cost 
Flood Control Activities Pursuant to Section 205, Public Law 858, 
80th Congress, as Amended 
Hays, Lincoln Draw, KS F $35,129 
Rossville, Cross Creek, KS F 52,077 
Bedford, East Fork 102 River, IA F 13,637 
DeWitt, Big Blue River & Turkey Creek, NE R 42,361 
TOTAL FOR 4 ACTIVE PROJECTS: $143,204 
4 Section 205 studies were terminated in FY 1989, total $61,121 
TOTAL ALL PROJECTS $204,325 
Emergency Streambank Protection - Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Congress 
July 24, 1946, as Amended 
Little Blue River, Clay County, NE, Weyenberg Bridge O $16,076 
Little Blue River, Nuckolls County, NE, Bridge #4525 O 12,521 
Chariton River, Schuyler County, MO, Eason Bridge O 12,700 
West Fork Grand River, Ringgold County, IA, Parker Bridge O 29,846 
West Fork Grand River, Ringgold County, IA, Redding Bridge O 43,967 
Little Blue River, Washington County, KS, Spence Bridge P 16,285 
Little Blue River, Washington County, KS, County Road P 18,942 
Gregg Creek, Brown County, KS, Granada Bridge P 14,805 
Middle Fork Wolf River, Brown County, KS, Avenue Road Bridge P 3,713 
Tributary of Kill Creek, DeSoto, KS, Sewage Treatment Plant P 13,839 
Little Blue River, Thayer County, NE, Gilead North Bridge P 5,781 
Big Blue River, Blue Springs, NE, Sewerline and Road P 9,254 
Thompson River, Union County, IA, H17 Bridge P 10,773 
Middle Nodaway River, Adair County, IA, Bridge #56240 P 11,037 
Marais des Cygnes River, Osawatomie, KS, Water Supply Facilities P 1,646 
102 River, Nodaway County, MO, South Pickering Bridge P 7,885 
Republican River, Clifton, KS, Sewage Lagoons P 11,479 
TOTAL FOR 17 ACTIVE PROJECTS IN FY 89: $240,549 
13 studies were terminated in FY 89, total $51,999 
TOTAL ALL PROJECTS $292,548 
Emergency Flood Control Activities - Repair, Flood 
Fighting, and Rescue Work - Public Law 99 
84th Congress and Antecedent Legislation 
Disaster Preparedness Program 
Corps Statutory Activities $161,548 
Activities in Support of Others 33,999 
Facilities 79,049 
Inspections 200,241 
Total Disaster Preparedness Program $474,837 
Emergency Water Supply and Drought Assistance 46,314 
TOTAL ALL ACTIVITIES $521,151 
1. Status: R = Recon; F = Feasibility; P = P&S; C = Construction; O = Operational 
27-22

LITTLE ROCK, ARKANSAS DISTRICT * 
The civil works portion of this District covers an area of 
approximately 36,414 square miles in northern, western, and 
southwestern Arkansas and a portion of Missouri within the 
Arkansas, Little, and White River Basins. The District's 
responsibilities include those areas embraced in the drainage 
basin of the Arkansas River and its tributaries above and 
exclusive of Pine Bluff, AR, and below the mouth of the 
Poteau River, near Fort Smith, AR. The District has 
responsibility for planning, design, construction and operation 
and maintenance of the navigation portion of the 
McClellan-Kerr Arkansas River Navigation System in the 
State of Arkansas (including that portion below Pine Bluff). 
The District's responsibilities in the Little River Basin covers 
those portions of the drainage basin of the Arkansas portion 
of Little River and its tributaries above its mouth near 
Fulton, AR. The District's responsibilities in the White River 
Basin cover those portions in southern Missouri and northern 
and eastern Arkansas embraced in the White River drainage 
basin and its tributaries above Peach Orchard Bluff, AR. The 
Memphis District is responsible for navigation maintenance 
on the White River below Newport, AR, to the mouth of 
Wild Goose Bayou, in Arkansas County, AR. The White 
River downstream from the mouth of Wild Goose Bayou is 
part of the McClellan-Kerr Arkansas River Navigation 
System. 
IMPROVEMENTS 
Navigation Eag 
1. AR River Basin, AR, OK, & KS ....................... 28-2 
2. Arthur V. Ormond Lock & Dam (No.9), AR ................ 28-2 
3. Bank Stabilization & Channel Rectification, AR........... 28-2 
4. David D. Terry Lock & Dam (No.6), AR ................... 28-3 
5. James W. Trimble Lock & Dam (No.13) ................... ; 28-3 
6. Lock No.2 & Wilbur D. Mills Dam (No.2), AR ............ 28-3 
7. Lock & Dam No.3, AR ............................... 28-3 
8. Lock & Dam No.4, AR ................................ 28-3 
9. Lock & Dam No.5, AR ................................ 28-3 
10. Maintenance & Repair Fleet & Marine 
Terminals, AR .................................. 28-3 
11. Murray Lock & Dam (No.7), AR ...................... 28-4 
12. Navigation Work Under Special Authorization ............. 28-4 
13. Norrell Lock & Dam (No.l) & Entrance 
Channel, AR ................................... 28-4 
14. Other Authorized Navigation Projects ................. 28-4 
15. Toad Suck Lock & Dam (No.8), AR .................... 28-4 
Flood Control 
16. Black River, Wayne County, MO ...................... 28-4 
17. Blue Mountain Lake, AR ............................. 28-4 
18. Clearwater Lake, MO ................................. 28-5 
19. DeQueen Lake, AR ................................... 28-5 
20. Dierks Lake, AR .....................................- 28-5 
21. Flood Control Work Under Special 
Authorization ................................. 28-5 
22. Fourche Bayou Basin, Little Rock, AR .................... 28-6 
23. Gillham Lake, AR ..................................... 28-6 
24. Inspection of Completed Flood 
Control Projects ................................. 28-6 
25. Little Red River & Tributaries, 
Clinton, AR .................................... 28-6 
26. Little River Basin, AR .................................. 28-6 
27. Mill Creek, Fort Smith, AR ............................. 28-7 
28. Millwood Lake, AR .................................. 28-7 
29. Nimrod Lake, AR .................................... 28-7 
30. Other Authorized Flood Control Projects ................. 28-7 
31. White River Basin (Little Rock 
District), AR & MO ........................... 28-7 
32. White River, Batesville, AR ........................ . 28-8 
33. White River, Newport, AR ........................... 28-8 
34. White River, St. Paul, AR ............................. 28-8 
Multiple Purpose Proects Including Power 
35. Beaver Lake, AR ................................. 28-8 
36. Bull Shoals Lake, AR .............................. 28-9 
37. Dardanelle Lock & Dam (No.10), AR .................. 28-9 
38. Greers Ferry Lake, AR .............................. 28-9 
39. Norfork Lake, AR ............................ ..... 28-10 
40. Ozark-Jeta Taylor Lock & Dam (No.132), 
AR ........................................ 28-10 
41. Table Rock Lake, MO ................................... 28-10 
General Investigations 
42. Surveys .......................................... 28-10 
43. Collection and Study of Basic Data .................... 28-11 
44. Continuation of Planning and Engineering ............. 28-11 
45. Advance Engineering and Design ..................... 28-11 
Iables 
Table 28-A Cost & Financial Statement .................... 28-12 
Table 28-B Authorizing Legislation ....................... 28-16 
Table 28-C Other Authorized Navigation 
Projects ...................................... 28-19 
Table 28-E Other Authorized Flood Control 
Projects ..................................... 28-20 
Table 28-G Deauthorized Projects ......................... 28-21 
Table 28-H AR, OK,& KS: Navigation .................... 28-22 
Table 28-I AR, OK, & KS: Lakes ......................... 28-26 
Table 28-J Little River Basin, AR: Lakes.................. 28-27 
Table 28-K White River Basin, AR & MO: Lakes ............ 28-28 
28-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. ARKANSAS RIVER BASIN, AR, OK, AND KS 
Location. Arkansas River rises in Rocky Mountains near 
Leadville, CO, and flows southeastward 1,396 miles through 
Colorado, Kansas, Oklahoma, and Arkansas to join 
Mississippi River 599 Miles above Head of Passes, LA. (See 
Geological Survey state maps, 1:24,000, and flood control and 
navigation maps of Mississippi River, Cairo, IL, to Gulf of 
Mexico, 1970 edition scale 1:62,500.) 
Previous projects. For details see page 1066, Annual 
Report for 1932, and pages 744, 864, and 881, Annual Report 
for 1943. 
Existing project. Provides for improvement of Arkansas 
River Basin by construction of coordinated developments for 
navigation, hydroelectric power, flood control, water supply, 
sediment control, recreation, and fish and wildlife 
propagation. McClellan-Kerr Arkansas River Navigation 
System provides a channel 9 feet deep and 444.8 miles long, 
beginning at mouth of White River, which enters Mississippi 
River 599 miles above Head of Passes, LA, thence 9.8 miles 
upstream to mouth of Wild Goose Bayou; thence 9.2 miles by 
a land cut, designated as Arkansas Post Canal to mile 42 
(1943 survey) on Arkansas River; thence 376.0 miles along 
channel of latter stream to mouth of Verdigris River at 
navigation mile 395.0; thence 49.8 miles up Verdigris River to 
head of navigation at Catoosa, OK. The waterway is canalized 
throughout its length by 17 locks and dams with total lift of 
420 feet. Dardanelle, Ozark-Jeta Taylor, Robert S. Kerr, and 
Webbers Falls are multiple-purpose projects including power. 
Lock chambers are 110 by 600 feet. A minimum channel 
width of 150 feet is provided for Verdigris River, 225 feet for 
San Bois Creek, 250 feet for Arkansas River, and 300 feet for 
Arkansas Post Canal and White River. Other coordinated 
developments consist of 15 lakes, of which 13 are in Tulsa 
District, Kansas and Oklahoma, and two in Little Rock 
District. Pertinent data and estimated Federal costs are 
summarized in Tables 28-H and 28-I, and Arkansas River 
Basin; AR, OK, and KS: Navigation Lakes. For 
authorization see Table 28-B, Authorizing Legislation. 
Local cooperation. For McClellan-Kerr Arkansas River 
Navigation System, local interests must provide adequate 
terminal and transfer facilities and bear increased cost of 
maintenance and operation of all altered rail and highway 
routes, including bridges and appurtenances, utilities, and 
other existing improvements, other than federally owned. For 
lakes see requirements for each individual lake. 
Terminal facilities. Public port facilities are in operation 
at Pine Bluff (Jefferson County), Little Rock, and Fort Smith, 
AR, and Muskogee and Catoosa (Tulsa-Rogers County), OK. 
Port authorities have been organized to develop public 
facilities at North Little Rock, Dardanelle-Russellville, 
Morrilton, Clarksville, Ozark and Van Buren, AR, and 
Sallisaw, OK. Terminal facilities are in operation or being 
built at 35 locations in Arkansas and at 25 locations in 
Oklahoma along the improved waterways. 
Operations and results during fiscal year. Continued 
operation and maintenance. (See Tables 28-H and 28-I for 
navigation and lake listings.) For details of McClellan-Kerr 
Arkansas River Navigation System and lakes in Oklahoma 
and Kansas, see the Tulsa District report. Details of 
McClellan-Kerr Arkansas River Navigation System and lakes 
in Arkansas are shown on the following pages. 
Condition at end of fiscal year. See Tables 28-H and 28-I, 
Arkansas River Basin; AR, OK, and KS: Navigation/Lakes 
for status for individual items, navigation project, lakes, and 
basin plan. The overall project is 96 percent complete. 
Construction of the Holla Bend Closure (Arthur V. Ormond 
Lock and Dam) was completed in September 1987. Work 
continues on the Arkansas River project in this District 
including construction of meander cutoff levee between the 
Arkansas and White Rivers, land acquisition studies, continue 
detailed engineering studies to modify Wilbur D. Mills Dam 
No.2 to improve navigation at the Entrance Channel, and 
raise the existing North Little Rock floodwall and levee. 
Planning and engineering studies continue on the low-stage 
problem on the White River at Montgomery Point. 
2. ARTHUR V. ORMOND LOCK & DAM 
(NO. 9), AR 
Location, existing project, local coopertion, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Continued 
operation and maintenance. Non-Federal hydropower is being 
developed at the project under the authority provided by the 
Federal Energy Regulatory Commission. 
Condition at end of fiscal year. Construction began in April 
1965 and lock and dam was placed in operation in July 1969. 
Construction of Holla Bend closure structure (fish and 
wildlife mitigation) began in July 1986. Holla Bend Closure 
was completed in September 1987. 
3. BANK STABILIZATION & CHANNEL 
RECTIFICATION, AR 
Location. Several bank stabilization and channel 
rectification projects are laid out in various reaches extending 
from fixed point to fixed point on Arkansas River from 33.7 
to 362 miles above mouth and across the Arkansas-White 
cutoff, a 4- to 5-mile natural channel joining Arkansas and 
White Rivers about 18 and 12 miles above their respective 
mouths. 
28-2

LITTLE ROCK, AR DISTRICT 
Existing project. Bank stabilization and channel 
rectification is a part of McClellan-Kerr Arkansas River 
Navigation System. For a complete description of reach and 
location of each bank stabilization and channel rectification 
project, see the Annual Report FY 81. Total Federal cost to 
date is $119,300,184 for existing project in Little Rock 
District. For authorization see Table 28-B, Authorizing 
Legislation. 
4. DAVID D. TERRY LOCK AND DAM 
(NO. 6), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Condition at end of fiscal year. Construction began in 
January 1965 and lock and dam was placed in operation in 
August 1968. 
5. JAMES W. TRIMBLE LOCK AND DAM 
(NO. 13), AR 
Location, existing project, local cooperation, and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Operation and 
maintenance continued. Construction of a non-Federal 
hydropower facility has been completed at the project under 
the authority provided by the Federal Energy Regulatory 
Commission. 
Condition at end of fiscal year. Construction began in 
October 1965 and lock and dam was placed in operation in 
April 1969. Bridge across dam was completed in July 1968. 
6. LOCK NO.2 AND WILBUR D. MILLS DAM 
(NO.2), AR 
Location, existing project, local cooperation, and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began in May 
1963. Lock was placed in operation in March 1968. 
Emergency repairs to the scour protection features and 
tainter gates at the dam that resulted from the barge accident 
in December 1982 were completed in FY 85. The barges that 
clogged the dam gates during the December 1982 flood 
revealed that, with a certain set of circumstances (higher than 
normal head combined with the clogged gates resulted in 
high, current velocity that caused both upstream and 
downstream scouring), the structure could fail. This condition 
exists primarily because the structure was constructed on 
piling and designed for all of the gates to operate in unison. 
A model study by the Waterways Experiment Station 
determined the most feasible solution to this problem is to 
extend the stilling basin downstream. Plans and specifications 
for extending the stilling basin are currently being prepared, 
with a construction start planned for the summer of 1990 
contingent upon approval and funding. 
7. LOCK AND DAM NO. 3, AR 
Location, existing project, local cooperation, and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began in May 
1963 and lock and dam were placed in operation in 
December 1968. 
8. LOCK AND DAM NO. 4, AR 
Location, existing project, local cooperation and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began in May 
1964 and lock and dam was placed in operation in December 
1968. The Arkansas State Highway and Transportation 
Department (ASHTD) and the Federal Highway 
Administration (FHWA) have jointly requested that the 
Corps of Engineers design and construct a highway bridge 
crossing Lock and Dam No. 4 on the Arkansas River near 
Pine Bluff, AR with 100 percent funding by ASHTD and 
FHWA. Design will be by A-E contract. Negotiations for an 
A-E design contract were initiated in 15 June 1989. 
9. LOCK AND DAM NO. 5, AR 
Location, existing project, local cooperation and terminal 
facilities. See Section 1. 
Operation and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began in 
November 1964 and lock and dam was placed in operation in 
December 1968. 
10. MAINTENANCE AND REPAIR FLEET AND 
MARINE TERMINALS, AR 
Location, existing project, local cooperation, and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction of Pine Bluff 
Marine Terminal began March 1968 and it was placed in 
operation in April 1969. Construction of Dardanelle Marine 
28-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Terminal began June 1968 and it was placed in operation in 
November 1969. 
Location, existing project, local cooperation and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began in 
November 1964 and lock and dam was placed in operation in 
December 1968. 
11. MURRAY LOCK AND DAM (NO. 7), AR 
Location, existing project, local cooperation, and 
terminal facilities. See Section 1. 
Operations and results during fiscal year. Excavation of 
the high rock in Pool 7 was completed 19 January 1989. 
Recreation facilities are complete except for cost sharing 
items under the 710 program. Operation and maintenance 
continued. 
Condition at end of fiscal year. Construction began in 
November 1964 and lock and dam was placed in operation in 
October 1969. Construction of a non-Federal hydropower 
facility was completed at the project under the authority 
provided by the Federal Energy Regulatory Commission. 
12. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Preauthorization studies under the small project 
continuing authorities program, navigation activities, Section 
107, Public Law 86-6456, as amended. No activity during this 
fiscal year. 
13. NORRELL LOCK AND DAM (NO.1) 
AND ENTRANCE CHANNEL, AR 
Location, existing project, local cooperation, and terminal 
facilities. See Section 1. 
Recommended modification. The Waterways Experiment 
Station (WES), Vicksburg, MS, is conducting a test model of 
an additional lock and dam in the White River Entrance 
Channel. This alternative is being tested to relieve restrictions 
on the navigation system during low flows. WES has 
determined that the other alternatives tested would not solve 
the low-flow problem. 
Operations and results during fiscal year. Operation and 
maintenance continued. 
Condition at end of fiscal year. Construction began in 
May 1963 and lock and dam was placed in operation in June 
1967. 
14. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 28-C, Other Authorized Navigation Projects. 
15. TOAD SUCK FERRY LOCK AND DAM 
(NO. 8), AR 
Location, existing project, local cooperation, and terminal 
facilities. See Section 1. 
Operations and results during fiscal year. Continued 
operation and maintenance. 
Condition at end of fiscal year. Construction began in July 
1965 and lock and dam was placed in operation in November 
1969. Conway water supply project was completed and 
transferred to that city for operation and maintenance in July 
1983. 
Flood Control 
16. BLACK RIVER, WAYNE COUNTY, MO 
Location. On Black River at Missouri Highway HH Wayne 
Couty, Missouri. Highway HH is a major access route to 
Clearwater project and to Piedmont, located approximately 4 
miles to the northeast. 
Existing project. The Definite Project Report, 
recommending a plan of improvement under Section 14 of 
the 1946 Flood Control Act, as amended, was approved in 
February 1988. The plan of improvement recommended 
construction of approximately 750 feet of quarry-run 
revetment. 
Local cooperation. Section 3, Flood Control Act of June 
22, 1936, applies. 
Operations during fiscal year. Construction was completed. 
17. BLUE MOUNTAIN LAKE, AR 
Location. See Table 28-1, Arkansas River Basin, AR, OK, 
and KS: Lakes. 
Existing project. Estimated cost is $5,069,974. For further 
information see pages 906 and 907 of 1962 Annual Report. 
For authorization see Table 28-B. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Operation and 
maintenance of project continued. Estimated monetary 
benefits at end of fiscal year attributed to Blue Mountain 
Lake for prevention of flood damages were $1,011,000 for a 
total of $20,481,000 through September 30, 1989. 
28-4

LITTLE ROCK, AR DISTRICT 
Condition at end of fiscal year. Project is complete except 
for additional recreation sanitary facilities. Construction of 
project began in May 1940, and was placed in operation in 
March 1947. In FY 89, the Corps carried out a fall-andwinter 
drawdown, recommended by the AR Game and Fish 
Commission (AGFC), on Blue Mountain Lake. The purpose 
was fishery management, with water quality improvement a 
secondary purpose. As the water level decresed, the AGFC 
seeded the exposed bottom with a sorghum-sudan 
combination which effectively cleared up the water column. 
18. CLEARWATER LAKE, MO 
Location. See Table 28-K. White River Basin, AR & MO. 
Existing project. Estimated cost is $11,395,000. For 
further information see pages 897 and 898 of 1962 Annual 
Report. For authorization see Table 28-B, Authorizing 
Legislation. 
Project modification. A contract was awarded in July 1987 
to construct a seepage berm on the upstream face of the dam, 
a grout curtain on the right abutment, and a parapet wall 
along the dam. An additional 9 acres of land has been 
acquired to widen the spillway from 190 feet to 370 feet. The 
parapet wall and the widened spillway will pass about 90 
percent of the probable maximum flood. The estimated 
project cost is $11,000,000. Construction was essentially 
completed in September 1989. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Operation and 
maintenance of project continued. Flood damages prevented 
during FY 89 are estimated at $1,780,000; total cumulative 
damages prevented through September 1989 are estimated 
at $77,793,000. Releases made from lake during low-water 
periods were sufficient to supply municipal water for Poplar 
Bluff and other usages. 
Condition at end of fiscal year. Project is complete except 
for addition and improvement existing sanitary recreational 
facilities. Construction of project began in June 1940 and was 
ready for beneficial use in March 1948. 
19. DEQUEEN LAKE, AR 
Location. On Rolling Fork River, river mile 22.8, a 
tributary of Little River, in Sevier County, about 4 miles 
northwest of DeQueen, AR. (See Geological Survey map for 
Chapel Hill, AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,360 feet long, 
constructed to 160 feet above streambed. An uncontrolled 
spillway, 200 feet wide, is about 1,400 feet east of main 
embankment. Outlet works consist of a gated conduit, 12 feet 
in diameter. The lake controls 169 square miles of drainage 
area and provides a total storage of 136,100 acre-feet 
(101,200 for flood control storage and 34,900 for 
conservation and sedimentation reserve). Federal cost of 
project is $19,623,752. (See Table 28-B for authorizing 
legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938, 
and Section 301, Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Estimated monetary 
benefits attributed to DeQueen Lake for prevention of flood 
damages were $212,000 for a total of $4,952,000 through 
September 30, 1989. 
Condition at end of fiscal year. Construction began April 
1966 and project placed in useful operation in August, 1977. 
20. DIERKS LAKE, AR 
Location. On Saline River, river mile 56.6, a tributary of 
Little River, about 5 miles northwest of Dierks, Howard 
County, AR. (See Geological Survey map for Dierks Dam, 
AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,760 feet long, about 
153 feet above streambed. An uncontrolled spillway 800 feet 
wide is in a saddle at west end of dam. Outlet works 
consisting of a gated 6- by 9-foot oblong conduit, one 24-inch 
low-flow pipe, and one 30-inch water supply pipe are 
provided. The lake controls a drainage area of 114 square 
miles and provides for storage of 67,100 acre-feet for flood 
control and 29,700 acre-feet for water supply, conservation, 
and sedimentation reserve, a total of 96,800 acre-feet. Federal 
cost of project is $16,002,781. (See Table 28-B for authorizing 
legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938, 
and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented 
during FY 89 are estimated at $405,000; total cumulative 
flood damages prevented are estimated at $3,252,000. During 
the year, 254 acre-feet of water supply storage were 
withdrawn by Tri-Lakes Water District. 
Condition at end of fiscal year. Construction began in June 
1968. The embankment closure was made on May 8, 1975 
and the project placed in useful operation. 
21. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
(1) Emergency bank protection, Section 14, Public Law 
79-526. Fiscal year costs were: Black River Highway HH, 
Wayne County, MO, $38,079; White River, Newport, AR, 
$93,930. 
28-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
(2) Flood control activities, Section 205, Public Law 
80-858. Fiscal year costs were $258,044 (for more 
information, see Table 28-L). 
(3) Snagging and clearing of navigable streams and 
tributaries in interest of flood control, Section 208, Public 
Law 73-780. Fiscal year costs were $1,106, White River, St. 
Paul, AR, project. 
22. FOURCHE BAYOU BASIN, LITTLE ROCK, 
AR 
Location. On Fourche, Rock and Grassy Flat Creeks in 
vicinity of Little Rock, Pulaski County, AR. 
Existing project. The flood damage reduction channel 
project consists of widening, clearing and snagging with 
alteration of highway and railroad bridges. The project was 
authorized by the Water Resources Development Act of 1986 
(PL 99-662). The estimated project cost is $29,000,000; 
$19,100,000 Federal, $9,900,000 non-Federal. 
Local cooperation. The city of Little Rock, the project 
sponsor, signed the local cooperation agreement on August 
20, 1987. 
Operations during the fiscal year. Funds were provided 
to prepare plans and specifications for future contracts and 
continue construction. The first channel construction 
contract was completed. The second channel construction 
contract was awarded April 16, 1989. Sponsor has continued 
relocations and acquisition of real estate. 
23. GILLHAM LAKE, AR 
Location. Damsite is on Cossatot River, river mile 49.0, in 
Howard County, about 5 miles northeast of Gillham, Sevier 
County, AR. (See Geological Survey quadrangle map for 
Gillham Dam, AR, scale 1:24,000.) 
Existing project. For description of completed 
improvement see Page 19-12 of Annual Report for 1977 
(Tulsa District). Federal cost of project is $17,826,703. (See 
Table 28-H for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938, 
and Water Supply Act of 1958, as amended, apply. Tri-Lakes 
Water District furnished a resolution of intent to repay costs 
allocated to water supply storage. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 89 are estimated at $838,000; total cumulative flood 
damages prevented are estimated at $5,908,000. During the 
year, 627 acre-feet of water supply storage were withdrawn by 
Tri-Lakes Water District. 
Condition at end of fiscal year. Construction began in 
June 1968. The embankment closure was made on May 8, 
1975 and the project placed in useful operation. 
24. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Approved regulations for operation and maintenance of flood 
control works, Part 208 of Title 33, Code of Federal 
Regulations, provide for periodic inspection of completed 
projects transferred to local interests for operation and 
maintenance. Inspections of local flood protection projects 
were made to determine extent of compliance with approved 
regulations for maintenance and operation of these projects. 
Responsible officials of improvement districts concerned were 
advised of inadequacies in maintenance and operation of 
local flood protection works under their jurisdiction where 
appropriate. Costs for fiscal year were $81,247. Total cost 
through September 30, 1989, are $1,258,398. 
25. LITTLE RED RIVER AND TRIBUTARIES, 
CLINTON, AR 
Location. In Clinton, Van Buren County, AR, along the 
tributaries of the Little Red River. The city lies between the 
tributaries of Archey Fork and South Fork and is bisected by 
Town Branch. 
Existing project. The flood damage reduction project 
consists of 100-foot bottom-width channel for 1.35 miles on 
Archey Fork Creek and a 300-foot bottom-width channel for 
1.99 miles on South Fork, Little Red River. 
Local cooperation. Fully complied with. 
Operations and results during the fiscal year. Mitigation 
measures to compensate for damages to the walleye pike 
fishery are being coordinated with the U.S. Fish and Wildlife 
Service and the Arkansas Game and Fish Commission. 
Condition at end of fiscal year. Construction of the project 
began in 1985 and was transferred to the city of Clinton in 
August 1986 for operation and maintenance. An O&M 
manual was furnished the city of Clinton. 
26. LITTLE RIVER BASIN, AR 
Location. Improvements are on Little River and tributaries, 
Arkansas. More definite location of individual items is shown 
in Table 28-J, Little River Basin. 
Existing project. Part of a six-lake system for flood control 
and other purposes in the Little River Basin. The system 
consists of four lakes in Arkansas: Millwood on the main 
stem, Dierks on the Saline River, DeQueen on the Rolling 
Fork River, and Gillham on the Cossatot River, and two 
lakes in Oklahoma: Broken Bow on the Mountain Fork River 
and Pine Creek on the Little River. Under a District 
boundary change, effective in October 1980, the four projects 
in this system in Arkansas were reassigned from the Tulsa 
District to the Little Rock District. 
28-6

LITTLE ROCK, AR DISTRICT 
Local cooperation. Section 2, Flood Control Act of 1938, 
and Section 301, Water Supply Act of 1958, as amended, 
apply. Tri-Lakes Water District (DeQueen, Gillham, and 
Dierks) furnished a resolution of intent to repay costs 
allocated to water supply storage. The Southwwest Arkansas 
Water District is currently repaying costs allocated to water 
supply storage at Millwood Lake. 
Operations and results during fiscal year. Operation and 
maintenance of projects continued. See individual projects for 
details. 
Condition at end of fiscal year. Millwood, DeQueen, 
Gillham, and Dierks Lakes are complete and in operation. 
27. MILL CREEK, FORT SMITH, AR 
Location. In southwest Fort Smith, Sebastian County, AR. 
Existing project. The detailed project report was approved 
December 5, 1975. The plan involves improvements on 3.9 
miles of the Mill Creek channel and modifications on three 
bridges. The estimated project cost is $6,177,000: $3,617,000, 
Federal; $2,560,000, non-Federal. The study, which began 
under the General Investigations Program, was changed to 
the Continuing Authority Program due to the size of the 
project. 
Local cooperation. Section 3, Flood Control Act of June 
22, 1936, applies. 
Operations during the fiscal year. Plans and specifications 
are complete except for the utilities under and through the 
project's structure. 
28. MILLWOOD LAKE, AR 
Location. On Little River, river mile 16.0, approximately 7 
miles east of Ashdown, Little River County, AR, and about 
2 miles northeast of Millwood, Little River County, AR. (See 
Geological Survey quadrangle map for Red Bluff, AR, scale 
1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report for 1969 
(Tulsa District). Federal cost of project is $46,100,082. (See 
Table 28-B for authorizing legislation.) 
Local cooperation. Completed as required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 54,187 
acre-feet of water was released from the lake for water supply 
to Southwest Arkansas Water District. Estimated monetary 
benefits attributed to Millwood Lake for prevention of flood 
damages for the fiscal year were $574,000, for a total of 
$7,270,000 through September 30, 1989. 
Condition at end of fiscal year. Construction began in 
September 1961 and the project was placed in full-flood 
control operation in August 1966. Work required to complete 
project consists of additional recreational facilities under the 
cost sharing program. 
29. NIMROD LAKE, AR 
Location. See Table 28-I, Arkansas River Basin, AR, OK, 
and KS: Lakes. 
Existing project. Estimated cost is $4,005,627. For further 
information see pages 908 and 909 of 1962 Annual Report. 
For authorization see Table 28-B. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Operation and 
maintenance of project continued. Addition and 
improvement to existing recreation sanitary facilities 
continued. Flooding was prevented on an average of 1,978 
acres of improved land during fiscal year. 
Estimated monetary benefits at end of fiscal year attributed 
to Nimrod Lake for prevention of flood damages were 
$701,000, for a total of $12,726,000 through September 1989. 
Eighty-seven acre-feet of water were withdrawn by the city of 
Plainview, AR. 
Condition at end of fiscal year. Project is complete except 
for addition and improvement to existing sanitary recreation 
facilities. Construction of project began in January 1940 and 
was ready for beneficial use in January 1942. 
30. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
See Table 28-E, Other Authorized Flood Control Projects. 
31. WHITE RIVER BASIN 
(LITTLE ROCK DISTRICT), 
AR&MO 
Location. Improvements are on White River and tributaries, 
Arkansas and Missouri. More definite location of individual 
items is shown in Table 28-K, White River Basin. 
Existing project. A general comprehensive plan for flood 
control and other purposes in White River Basin. Plan 
includes seven lakes, of which two are flood-control only 
projects and five are multiple-purpose projects. Beaver, Table 
Rock, Bull Shoals, Norfork, Clearwater, Greers Ferry and 
Bell Foley lakes were selected and approved for construction 
by Chief of Engineers, and individual reports on six of these 
seven lakes are presented on subsequent pages. Bell Foley 
lake project was reclassified to inactive in June 1977; 
reviewed for the purpose of deauthorization and placed in a 
28-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
deferred status in May 1985; funded for update of economic 
data in FY 89. Lakes in plan are listed in Table 28-K, White 
River Basin. For authorization see Table 28-B. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies, Water Supply Act of 1958, as amended, applies to 
Beaver, Greers Ferry, and Norfork. 
Operations and results during fiscal year. Operation and 
maintenance of projects continued. Estimated monetary flood 
control benefits attributed to Beaver, Table Rock, Bull 
Shoals, Norfork, Greers Ferry, and Clearwater lakes for FY 
89 totaled $8,258,000. A cumulative total of flood damages 
prevented by the lakes through September 30, 1989, is 
estimated at $297,418,000. 
Electric energy delivered to Southwestern Power 
Administration for marketing during the fiscal year totaled 
1,802,532,500 kilowatt-hours. 
Water releases for fish hatcheries were: 28,960 acre-feet 
from Norfork Lake for Fish and Wildlife Service trout 
hatchery, 14,480 acre-feet from Table Rock Lake for Missouri 
Conservation Commission trout hatchery, and 14,480 
acre-feet from Greers Ferry Lake for U.S. Fish and Wildlife 
Service trout hatchery. 
Withdrawals for water supply purposes were: Beaver Water 
District, 34,084 acre-feet from Beaver Lake; Water and Sewer 
Improvement District No. 3 of Mountain Home, AR, 2,624 
acre-feet from Norfork Lake; the Community Water System, 
Cleburne County, AR, and the city of Clinton, AR, 6,870 
acre-feet from Greers Ferry Lake. 
Condition at end of fiscal year. Beaver, Table Rock, Bull 
Shoals, Norfork, Clearwater, and Greers Ferry lakes are 
complete and in operation. Progress on these lakes is in 
individual reports. Bell Foley lake project has been placed in 
a deferred status. Water Valley and Lone Rock lakes have 
been deauthorized. 
32. WHITE RIVER, BATESVILLE, AR 
Location. On White River, within the city of Batesville, 
Independence County, AR. 
Existing project. The Definite Project Report, 
recommending construction of a levee and floodwall to 
protect the industrial area, under Section 205 of the 1948 
Flood Control Act, as amended, was approved June 30, 1988. 
Local cooperation. Section 3, Flood Control Act of June 
22, 1936, applies. 
Operations during the fiscal year. Funds were used for 
plans and specifications, coordination with the local sponsor 
on real estate acquisition and the local cooperation 
agreement. 
33. WHITE RIVER, NEWPORT, AR 
Location. On White River, approximately 200 feet 
downstream of the Highway 367 bridge. Newport, Jackson 
County, AR. 
Existing project. Approximately 362 feet of emergency bank 
protection work along the White River bank was constructed 
to protect a Federally constructed concrete floodwall. Total 
project cost was $140,200: Federal, $105,100; non-Federal, 
$35,100. 
Local cooperation. Section 3, Flood Control Act of June 30, 
1988. The local cooperation agreement was signed by the 
local sponsor and the city of Newport on October 1, 1988. 
Operations during the fiscal year. Initial construction began 
in November 1988; however, work was delayed due to high 
water. A slope failure occurred in December 1988 which 
required a revised plan. The contractor resumed work in 
January 1989. Construction of the project was considered 
complete and acceptable by the local sponsor in May 1989. 
34. WHITE RIVER, ST. PAUL, AR 
Location. Along the right bank of the White River, St. Paul, 
Madison County, AR. 
Existing project. A plan of improvement, under Sec 208 of 
the 1954 Flood control Act, as amended, was approved in 
February 1988, to snag and clear 2,800 feet by 30 feet along 
the White River bank. Construction of the project, approved 
in August 1988, was delayed until the city could acquire the 
necessary land. Total cost of the project is estimated at 
$31,800: $22,700, Federal; $7,600, non-Federal. 
Location cooperation. Section 3, Flood Control Act of June 
22, 1936, applies. The local cooperation agreement was signed 
by the local sponsor, the city of St. Paul, AR, on August 24, 
1989. 
Operations during the fiscal year. The local cooperation 
agreement was negotiated and the city acquired the necessary 
lands. 
Multiple-Purpose Projects Including Power 
35. BEAVER LAKE, AR 
Location. See Table 28-K. White River Basin. 
Existing project. Estimated cost is $50,797,000. For further 
information see pages 788 and 789 of 1966 Annual Report. 
For authorization see Table 28-B. 
Local Cooperation. Section 2, Flood Control Act of 1938 
and Water Supply Act of 1958, as amended, apply. 
28-8

LITTLE ROCK, AR DISTRICT 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 89 are estimated at $498,000; total cumulative flood 
damages prevented are estimated at $21,401,000. During the 
year, 159,942,500 kilowatt-hours of electrical energy were 
delivered to the Southwestern Power Administration for 
marketing. Water supply storage withdrawn during the year 
was 34,084 acre-feet. 
Condition at end of fiscal year. Project is complete except 
for modifications to existing recreation and sanitary facilities. 
Alterations to existing parks to enhance fee collections, 
improve efficiency, reduce maintenance effort or rehabilitate 
20-year old park operation funded by O&M and SRUF, as 
appropriate. Construction of project began in October 1959 
and was placed in operation for flood control in December 
1963, hydroelectric power generation with both units in May 
1965, and water supply in January 1966. Since the dam was 
constructed there has been a seepage problem below Dike 
No. 1. Based on detailed investigation, it was determined that 
the limestone foundation under Dike No. 1 and 200 feet of 
the north end of the main dam embankment is the main 
problem. The plan of improvement is a concrete seepage 
cutoff in Dike No. 1 and the north end of the main dam. A 
request for proposals to construct a concrete cutoff wall was 
issued in September 1988. After evaluation a contract was 
awarded in June 1989, but a protest (which was denied) 
delayed the notice to proceed, which was issued in October 
1989. The contract period is estimated to be 760 days. 
36. BULL SHOALS LAKE, AR 
Location. See Table 28-K, White River Basin, AR & MO. 
Existing project. Estimated cost with eight generating units 
is $96,356,000. For further information see pages 725 and 726 
of 1965 Annual Report. For authorization see Table 28-B. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 89 are estimated at $2,959,000; total cumulative flood 
damages prevented are estimated at $91,646,000. During the 
year, 706,294,000 kilowatt-hours of electrical energy were 
delivered to Southwestern Power Administration for 
marketing. 
Condition at end of fiscal year. Project is complete except 
for modifications to existing recreation and sanitary facilities. 
Alterations to existing parks to enhance fee collections, 
improve efficiency, reduce maintenance effort or rehabilitate 
35-year-old park facilities funded by O&M or SRUF, as 
appropriate. Planning Division and Construction Operation 
Division, (LRD) and Arkansas Game & Fish Commission 
and Arkansas Department of Parks and Tourism worked 
together to provide environmentally sensitive bank 
stabilization along the White River at Bull Shoals State Park. 
Gravel excavation was conducted so as to avoid brown trout 
spawning sites. Environmental damages were offset with the 
placement of large boulders which serve as habitat for 
juvenile and adult trout. The boulders also provide excellent 
angling opportunities for this world class fishery. Construction 
of project began in April 1946 and was ready for beneficial 
use for flood control in June 1951 and generation of 
electrical energy in September 1952. Units 1 through 8 were 
placed in operation September 1952, December 1952, June 
1953, January 1962, February 1962, August 1963, and 
September 1963, respectively. 
37. DARDANELLE LOCK AND DAM (NO. 10), 
AR 
Location. See Table 28-H, Arkansas River Basin; AR, OK, 
and KS: Navigation. 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,683 feet long 
and 68 feet high. It has a spillway with 20 tainter gates 50 feet 
long and 39 feet high. Navigation lock is 110 by 600 feet with 
a lift of 54 feet. Powerhouse contains four 31,000 kilowatt 
generators. Lake has a storage capacity of 486,200 acre-feet. 
Estimated cost is $86,507,000. (See Table 28-B for 
authorizing legislation.) 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Continued 
operation and maintenance. Pool fluctuated within 2-foot 
power pondage, elevation 336.0 to 338.0. Power generation 
continued. During FY 89, 703,762,900 kilowatt-hours of 
electrical energy were delivered to the Southwestern Power 
Administration for marketing. 
Condition at end of fiscal year. Project is complete except 
for addition and improvement to existing recreation sanitary 
facilities. Construction began June 1957. Power units were 
placed on line April, May, and September 1965, and January 
1966. Lock was placed in operation in December 1969. The 
visitor center and resident office were completed in May 
1985. 
38. GREERS FERRY LAKE, AR 
Location. See Table 28-K, White River, AR & MO. 
Existing project. Estimated cost is $55,125,000. For further 
information see page 740 of 1964 Annual Report. (See Table 
28-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938 
and Water Supply Act of 1988, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 89 are estimated at $1,588,000; total cumulative flood 
damages prevented are estimated at $19,394,000. During the 
year, 216,618,000 kilowatt-hours of electrical energy were 
28-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
delivered to the Southwestern Power Administration for 
marketing. Water supply storage withdrawn during the year 
was 1,870 acre-feet. 
Condition at end of fiscal year. Project is complete except 
for addition and improvement to existing recreation sanitary 
facilities. Construction of project began in June 1957, was 
ready for beneficial use for flood control in January 1962, 
and power units 1 and 2 were placed in operation in March 
and May 1964, and water supply was placed in operation in 
April 1971. The visitors center was completed in June 1983 
at a cost of $813,000. 
39. NORFORK LAKE, AR 
Location. See Table 28-K, White River Basin, AR & MO. 
Existing project. Total estimated cost is $111,624,000, 
including $38,700,000 for addition of power units 3 and 4, 
and $40,000,000 for highway bridge construction. For further 
information see page 896 of 1962 Annual Report. (See Table 
28-H for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938 
and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 89 are estimated at $264,000; total cumulative flood 
damages prevented are estimated at $31,796,000. During the 
year, 240,547,000 kilowatt-hours of electrical energy were 
delivered to the Southwestern Power Administration for 
marketing. Water supply withdrawn by city at Mountain 
Home, AR, totaled 2,624 acre-feet. 
Condition at end of fiscal year. Project is complete except 
for addition and improvement to existing recreation sanitary 
facilities, and addition of power units 3 and 4. Construction 
of project began in October 1940, ready for beneficial use for 
flood control in June 1943, and for generation of electrical 
energy with one unit in June 1944. Second unit was added in 
February 1950. Water supply was added as a purpose in 
December 1969. Construction of two highway bridges over 
Norfork Lake to replace ferries was completed in November 
1982. The bridges were transferred to the Arkansas Highway 
and Transportation Department for operation and 
maintenance in July 1984. 
40. OZARK-JETA TAYLOR LOCK AND DAM 
(NO. 12), AR 
Location. See Table 28-H, Arkansas River Basin, AR, OK, 
and KS: Navigation. 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,480 feet long 
and 58 feet above streambed. It has a spillway with 15 tainter 
gates 50 feet long and 46 feet high. Navigation lock is 110 by 
600 feet with a lift of 34 feet. Powerhouse contains five 
20,000 kilowatt generators. Lake has a storage capacity of 
148,400 acre-feet. In addition, 1 foot of power pondage is 
provided in Pool No.13 between elevations 391.0 and 392.0. 
Estimated cost is $86,167,000. For authorization see Table 
28-B. 
Local cooperation. See Section 1. 
Operations and results during fiscal year. Delivered 
407,841,000 kilowatt-hours of electrical energy to 
Southwestern Power Administration for marketing. 
Continued operation and maintenance. 
Condition at end of fiscal year. Construction began in 
December 1964. Project is complete except for addition and 
improvement to existing recreation sanitary facilities. Lock 
and dam was placed in operation in November 1969. Power 
units were placed on line as follows: unit 1, November 1972; 
unit 2, August 1973; unit 3, October 1973; unit 4, December 
1973, and unit 5, May 1974. Work remaining consists 
principally of modifications to powerplant. 
41. TABLE ROCK LAKE, MO 
Location. See Table 28-K, White River Basin, AR & MO. 
Existing project. Estimated cost is $71,233,000. For further 
information see page 893 of 1962 Annual Report. For 
authorization see Table 28-B. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 89 are estimated at $1,169,000; total cumulative flood 
damages prevented are estimated at $55,388,000. During the 
year, 497,131,000 kilowatt hours of electrical energy were 
delivered to the Southwestern Power Administration for 
marketing. The District and the Waterways Experiment 
station are investigating the possibilities of improving the 
quality of Table Rock releases with a hypolimnetic 
oxygenation system. 
Condition at end of fiscal year. Project is complete except 
for addition and improvement to existing recreation sanitary 
facilities. Construction of project began in October 1954, was 
ready for beneficial use for flood control in November 1958, 
and for generation of electrical energy with units i and 2 in 
May 1959. Units 3 and 4 were added in April and June 1961. 
General Investigations 
42. SURVEYS 
Total fiscal year expenditures were $970,854: navigation 
studies, $409,422; flood damage prevention studies, $464,470; 
review of authorized projects, $4,232; special investigations, 
$35,000; review of FERC licenses, $2,000; interagency water 
28-10

LITTLE ROCK, AR DISTRICT 
resource development, $16,978; and, coordination studies 
with other agencies, $38,752. 
43. COLLECTION AND STUDY OF BASIC DATA 
Flood plain management services (FPMS). The authority 
for the FPMS program is Section 206 of the 1960 Flood 
Control Act, PL 86-645, as amended. Through technical 
services and planning guidance, the program encourages 
comprehensive flood plain management planning at all levels 
to reduce the potential for losses to life and property from 
floods. Federal and non-Federal agencies and the private 
sector are assisted with planning and development 
information for flood hazard areas. This assistance is in the 
form of local flood plain regulations, Federal Insurance 
Program requirements, and Executive Order 11988 
guidelines. Such assistance may include factual flood 
information (available or determined) and interpretation on 
flood frequencies, extent of flooding, flood-water velocity, 
duration of flooding and floodway limits. Services 
accomplished during fiscal year: Technical services and 
planning guidance responses furnished during FY 89 totaled 
15,900. This total included services to Federal and 
non-Federal agencies, individuals, realtors, corporations, 
lending institutions, engineers, architects, and others. Costs 
for providing these services during FY 89 totaled $290,277. 
Hydrologic studies. During the fiscal year, 141 stations were 
operated; 73 cooperatively with USGS and 41 by the Corps. 
The total cost for streamflow and some sediment data from 
all sources of funding for FY 89 was $562,050, of which 
$398,340 was transferred to USGS. The District also 
participated in a cooperative program with National Weather 
Service for rainfall and/or river reporting stations for use in 
forecasting streamflow for flood warning and operation of 
lake projects. Records were also collected at certain 
hydroclimate rainfall stations under a cooperative program 
between the two agencies. For these services, $41,490 was 
transferred to the National Weather Service. 
44. CONTINUATION OF PLANNING AND 
ENGINEERING 
During this fiscal year, a total of $124,683 was expended on 
North Little Rock (Dark Hollow), AR. 
45. ADVANCE ENGINEERING AND DESIGN 
During the fiscal year, a total of $734,777 was expended on 
Little River, Horatio, AR ($10,000); Beaver Lake Water 
Quality, AR ($596,790); Dardanelle Lock and Dam, Cane 
Creek Bridge, AR, $94,482; Village Creek, Jackson and 
Lawrence Counties, AR, ($8,506); Bell Foley Lake, AR, 
($25,000). 
28-11

TABLE 28-A 
LITLE ROCK, AR. DISTRICT 
COST AND FINANCIAL STATEMENT2 
See Total Cost 
Section to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Se.30,'89 2 
1. Arkansas River 
Basin, Ark., 
Okla. & Kans. 
3. Bank Stabilization 
& Channel 
Rectification, 
AR 
2,4-5, Navigation 
6,9,11, Locks & Dams, 
13,15 AR 
16. Black River 
Wayne Co., MO 
17. Blue Mountain 
Lake, AR 
New Work 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Maint. 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Special Funds 
Cost 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
$ 971,000 $ 3,346,000 $4,852,926 $7,481,000 $1,476,886,053 
150,318,533 
971,000 3,346,000 4,852,926 7,481,000 1,326,567,520 
1,072,738 4,400,979 4,352,714 4,256,220 1,472,472,641 
150,279,504 
1,072,038 4,400,979 4,352,714 4,256,220 1,322,198,137 
51,802,900 
11,478,700 
40,324,200 
56,383,991 
12,196,588 
44,187,403 
53,820,069 
11,386,703 
42,433,366 
54,463,823 
11,676,676 
42,792,147 
73,193,568 
12,883,200 
60,310,368 
69,730,438 
12,211,917 
57,518,521 
68,731,146 
13,230,308 
51,500,838 
20,319,918 
13,699,711 
56,620,207 
791,729,5622 
170,356,501 
621,373,061 
796,104,0712 
170,094,241 
626,209,830 
291,106 
291,106 
1,609,842 
1,609,842 
19,926,755 
19,926,755 
531,336 
531,336 
119,300,184 
119,300,184 
4,561,666 
4,561,666 
493,000 
785,392 
12,237,000 
15,261,530 
3,154,000 4,852,926 
3,614,165 4,288,918 
18,739,150 
18,913,983 
7,481,000 437,510,399 
4,256,220 433,576,551 
25,388,560 19,445,670 250,777,1822 
24,612,255 20,251,719 253,346,1342 
161,481 
21,256 
1,134,866 
984,823 
531,336 
531,336 
39,400 
38,079 
13,650 
11,913 
39,4003 
38,0793 
13,650 
11,913 
5,069,974 
5,069,974 
28-12

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 28-A 
(Continued) 
COST AND FINANCIAL STATEMENT' 
See Total Cost 
Section to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept..30,'89 1,2 
Blue Mountain 
Lake, AR 
(cont.) 
18. Clearwater 
Lake, MO 
19. DeQueen Lake, 
Little River 
Basin, AR 
20. Dierks Lake, 
Little River 
Basin, AR 
22. Fourche Bayou 
Basin, 
Little Rock, AR 
23. Gillham Lake, 
Little River 
Basin, AR 
25. Little Red River 
& Tributaries, 
Clinton, AR 
26. Little River 
Basin, (Little 
Rock Dist.) 
27. Mill Creek, Fort 
Smith, AR 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
624,000 
636,896 
701,722 
693,553 
1762,003022 
769,708 
620,000 
620,000 
1,419,000 
1,391,455 
1,540,922 1,546,000 
1,555,704 1,482,319 
_ 348,000 6,119,000 
_ 347,823 6,096,046 
747,000 12,061,0162 
750,782 12,027,2202 
_ 11,073,403 
11,060,204 
1,590,000 25,214,4441 
1,654,115 25,210,2811 
3,660,000 10,127,000 
3,674,652 10,118,519 
19,629,753 
19,623,752 
809,000 
805,368 
691,400 
713,943 
823,000 
813,849 
834,000 7,456,4302 
823,816 7,431,5982 
_ 16,002,904 
16,002,781 
624,000 
649,813 
300,000 
297,042 
697,300 
707,478 
798,000 
746,097 
360,000 2,225,000 
343,750 2,200,119 
_ 108,000 
__ 64,750 
816,000 
841,872 
2,550,000 
2,815,619 
766,722 
814,460 
88,000 
62,864 
328,578 
371,828 
819,000 
816,034 
12,131 
881,000 7,857,0032 
919,005 7,842,8222 
2,252,000 6,508,0003 
1,313,562 5,472,1043 
166,900 
61,900 
603,478 
498,478 
_ 17,827,111 
17,826,703 
847,360 7,053,5672 
847,710 7,046,9282 
3,999,5003 
3,761,2933 
_ 99,959,850 
1,127 99,544,384 
3,336,000 
3,632,464 
162,000 
99,493 
3,865,144 3,902,000 
3,945,354 3,749,058 
90,000 
122,848 
20,000 
37,177 
4,129,360 46,232,7842 
4,210,494 46,076,9432 
119,000 391,0003 
60,955 320,4733 
68,400 
30,254 
68,400 
30,254 
28-13

TABLE 28-A 
(Continued) 
LI TLE ROCK, AR DISTRICT 
COST AND FINANCIAL STATEMENT 1, 
See Total Cost 
Section to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept30,'89 1,2 
28. Millwood Lake, 
Little River 
Basin, AR 
29. Nimrod Lake, 
AR 
31. White River 
Basin (Little 
Rock District) 
32. White River 
Batesville, AR 
33. White River 
Newport, AR 
34. White River 
St. Paul, AR 
35 Beaver Lake, 
AR 
36. Bull Shoals 
Lake, Ar 
37. Dardanelle Lock 
& Dam (No. 10) 
AR 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
46,087,3822 
1,127 46,091,2482 
1,323,600 1,709,722 
1,335,411 1,712,473 
922,000 
914,350 
160,297 
916,722 
909,774 
9,005 
1,462,000 
1,373,078 
1,567,000 23,602,3842 
1,619,963 23,758,5952 
4,092,826 
4,005,627 
1,103,000 
1,076,793 
620,000 
620,000 
1,085,000 14,573,4602 
1,122,310 14,559,5912 
335,651,873 
335,378,666 
15,961,000 20,126,632 26,134,860 23,919,340 305,447,3112 
18,584,487 20,196,826 25,588,775 24,188,550 307,517,8572 
41,467 5,0004 
6,5004 
3,2004 
104,200 150,6671 
101,698 101,6981 
98,600 105,1004 
93,929 93,9294 
29,500 
27,900 
1,000 
1,105 
1,500 
29,500 
27,900 
4,2004 
1,1054 
1,500
0 
46,183,033 
46,112,072 
3,043,600 
3,082,886 
3,416,922 
3,382,140 
3,626,100 3,000,640 41,218,0912 
3,544,464 3,070,175 41,131,4192 
88,858,711 
88,858,707 
4,754,600 4,435,922 
4,754,193 4,430,634 
7,146,900 6,227,200 67,719,3752 
6,970,679 6,219,379 72,040,2302 
84,270,124 
84,261,240 
28-14

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 28-A 
(Continued) 
COST AND FINANCIAL STATEMENT 1 2 
See Total Cost 
Section to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept30,'891 , 
Dardanelle Maint. 3,751,000 4,284,300 4,558,000 4,736,000 57,082,1692 
(cont.) Approp. 3,633,834 4,425,056 4,338,146 4,862,558 56,886,8882 
Cost 
38. Greers Ferry New Work 
Lake, AR Approp. - - 48,865,512 
Cost - - 48,865,512 
Maint. 
Approp. 3,745,600 3,832,922 4,461,340 4,743,000 55,695,4002 
Cost 3,716,466 3,886,414 4,318,096 4,789,616 55,529,3952 
39. Norfork Lake, New Work 
AR Approp. 378 70,997,929 
Cost 159,899 378 70,716,087 
Maint. 
Approp. 2,423,600 2,537,022 3,250,860 3,229,000 48,355,073 
Cost 2,442,185 2,547,120 3,211,880 3,268,163 48,218,064 
40. Ozark-Jeta Taylor New Work 
Lock & Dam Approp. - 85,629,412 
(No.12), AR Cost 85,629,412 
Maint. 
Approp. 2,295,000 3,526,400 3,376,000 4,675,000 47,168,878 
Cost 2,322,962 3,525,398 3,344,691 4,688,530 47,125,441 
41. Table Rock New Work 
Lake, MO Approp. - - 67,224,000 
Cost - 67,224,000 
Maint. 
Approp. 3,229,600 4,362,922 4,446,000 5,129,500 63,751,788 
Cost 3,197,302 4,394,814 4,283,388 5,187,102 63,597,640 
1. For more details on project funds see text for individual projects. 
2. Beginning data shown in Table 28-A includes special recreation use fees. 
3. Includes funds for plans and specifications. 
4. Unexpended study funds used to initiate plans and specifications. 
28-15

LIT'LE ROCK, AR. DISTRICT 
TABLE 28-B AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
ARKANSAS RIVER BASIN, AR, OK, & KS 
(See Section 1 of text) 
Approved General comprehensive plan: 
Mannford Reservoir, OK 
Oologah Lake, OK 
Canton Lake, OK 
Tenkiller Ferry Lake, OK 
Wister Lake, OK 
Blue Mountain Lake, AR 
Nimrod Lake, AR 
Modified comprehensive plan to include reservoirs in 
Grand (Neosho) River Basin, OK, and Mo, and in 
Verdigris River Basin: 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Pensacola Reservoir Lake O' The Cherokees, OK 
Fall River Lake, KS 
Elk City Lake, KS 
Toronto Lake, KS 
Neodosha Lake, KS 
Authorized Chief of Engineers to provide in the Canton 
Lake 69,000 acre-feet of irrigation storage, subject to 
certain conditions. 
Approved multiple-purpose plan: 
Oologah Lake, OK 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Blackburn Reservoir, OK 
Mannford Reservoir, OK 
Taft Reservoir, OK 
Bank stabilization 
Dardanelle Lock and Dam, AR 
Eufaula Lake, OK 
Navigation locks and dams 
Ozark Lock and Dam, AR 
Short Mountain Lock and Dam, OK 
Webbers Falls Lock and Dam, OK 
Tenkiller Ferry Lake, OK 
Flood Control Com. 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 107 and 440, 
76th Cong. 1st sess. 
H. Doc 758, 79th Cong., 
2d sess. 
June 30, 1948 
May 17, 1950 
Modified Arkansas River navigation comprehensive plan to 
include bank protection works at Bradens Bend, OK. 
Modified comprehensive plan authorized in 1938 Flood 
Control Act and multiple-purpose plan authorized in 
River and Harbor Act of 1946 to provide for substituting 
Keystone Lake for Mannford, Blackburn and Taft 
Reservoirs. 
S. Doc 107, 81st Cong., 
1st sess. 
28-16 
June 28, 1938 
August 18, 1941 
July 24, 1946 
July 24, 1946

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 28-B 
(Continued) AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
July 14, 1960 Authorized incorporation of River and Harbor and Flood 
Control plans into a single plan of development and made 
all pervious authorizations applicable to combined 
plan of development. 
November 17, 1986 
June 10, 1948 
July 24, 1946 
July 3, 1958 
Fourche Bayou Basin, Little Rock, AR 
(See Section 22 of text.) 
Mill Creek, Fort Smith, AR 
(See Section 27 of text.) 
RED RIVER BELOW DENISON DAM INCLUDING 
LITLE RIVER BASIN, OK AND AR 
(See Section 26 of text) 
Construct Boswell, Hugo, and Millwood Lakes, and Bank 
Stabilization. 
Modified Millwood: Construct Pine Creek, Lukfata, 
Broken Bow, DeQueen, Gillham, Dierks Lakes 
Water Resources 
Development Act of 
1986, P.L. 99-662, 
Sec. 401 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers 
H. Doc. 602, 79th Cong., 
2d sess. 
H. Doc. 170, 85th Cong., 
1st sess. 
WHITE RIVER BASIN 
(L'TLE ROCK DISTRICT) 
(See Section 31 of text) 
June 28, 1938 
August 18, 1941 
September 3, 1954 
October 23, 1962 
March 1, 1974 
June 30, 1948 
Approved comprehensive plan for White River Basin: 
Lone Rock Lake, AR, Norfork Lake, AR, 
Clearwater Lake, MO, Water Valley Lake, AR, 
Bell Foley Lake, AR, Greers Ferry Lake, AR, 
and White River emergency. 
Modified comprehensive plan to include Bull Shoals 
Lake, AR, and MO, Table Rock Lake, MO, and 
AR, and Norfork Lake, AR, and MO (power). 
Authorized power in Greers Ferry Reservoir and added 
Beaver Lake to the plan. 
Authorizing clearing and straightening of channel for 
Village Creek, Jackson and Lawrence Counties. 
Authorizing highway bridge construction across 
Norfork Lake. 
Little Red River and Tributaries, 
Clinton, AR (See Section 25 of text.) 
Flood Control Comn. 
Doc 1, 75th Cong., 
1st sess. 
H. Doc. 917, 76th Cong., 
3d sess. 
H. Doc. 290, 77th Cong., 
1st sess. 
H. Doc. 499, 83d Cong., 
2d sess. 
H. Doc 352, 87th Cong., 
2d sess. 
Flood Control Comn. 
Doc. 1, 75th Cong., 
1st sess. 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers. 
28-17

LITTLE ROCK, AR. DISTRICT 
TABLE 28-B 
(Continued) AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
October 22, 1976 
July 24, 1946 
June 30, 1948 
July 24, 1946 
August 28, 1937 
White River Fish Hatchery, Arkansas provides for 
trout production facilities downstream from 
Beaver Dam. 
Black River, Wayne County, Mo. 
(See Section 16 of text.) 
White River, Batesville, AR. 
(See Section 32 of text.) 
White River, Newport, AR. 
(See Section 33 
of text.) 
White River, St. Paul, AR. 
(See Section 34 of text.) 
Water Resources 
Development Act of 
1976, P.L. 94-587, 
Sec. 105 
Section 14 P.L. 79-526. 
Authorized by Chief of 
Engineers 
Section 205, P.L. 80-858. 
Authorized by Chief of 
Engineers 
Section 14 P.L. 79-526. 
Authorized by Chief of 
Engineers 
Section 208, P.L. 75-406. 
Authorized by Chief of 
Engineers 
28-18

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 28-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Federal Cost to Sept. 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arkansas River, Little Rock Slackwater Harbor, AR 1 1988 $736,869 
Black River, AR and MO 3 1950 80,000 $ 930,324 
Current River, AR and MO 3 1964 17,0004 132,178 
Upper White River, AR 2 5 1952 813,197 1,788,374 
White River, AR (above Peach Orchard Bluff) 3 6 1950 _ 785,666 
White River, Jacksonport, AR 2 1984 43,110 
1. Authorized by Chief of Engineers under authority 
of Sec. 107, P.L. 86-6456. 
2. Completed. 
3. Channel adequate for existing commerce. completion 
not contemplated. 
4. Includes $7,000 for previous project. 
5. Federal operation and maintenance terminated 
June 30, 1952, due to lack of commerce. Facilitates at 
Locks and Dams Nos. 1,2, and 3 disposed of in accordance 
with authority in Public Law 996, 84th Cong. 
6. Responsibility for maintenance of project 
downstreamdownbstream downstream from Newport, AR transferred 
to Memphis District in FY 62. 
28-19

LrITLE ROCK, AR. DISTRICT 
TABLE 28-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept 30, 1989 
Full Report 
See Annual Operations and 
Project Status Report For Construction Maintenance 
Bell Foley Lake, White River, AR 
Black River, Butler County Road 607, MO 
Black River, Poplar Bluff, MO, to 
Knobel, AR 
Butler County Drainage District 3, MO 
Carden's Bottom Drainage District No. 2, 
Arkansas River, AR 
Clarksville, AR 
Conway County Drainage and Levee District 
No. 1, Arkansas River, Ar 
Conway County Levee Districts Nos. 1, 
2, and 8, Arkansas River, AR 
Conway County Levee District No. 6, 
Arkansas River, AR 
Crawford County Levee District, AR 
Crawford County Levee District, Arkansas 
River, AR 
Curia Creek Drainage District, Independence 
County, AR 
East Poplar Bluff and Poplar Bluff, MO 
Faulkner County Levee District No. 1, 
Arkansas River, AR 
Fort Smith, Arkansas River, AR 
From North Little Rock to Gillett, AR 
(above Plum Bayou) 
Fourche Creek, Little Rock, AR 
Jackson Couinty Levee District 2, White River, 
AR 
Little Massard Creek, Fort Smith, AR 
Little Red River District 1, AR 
Little Red River, White County Road Bridge, 
Judsonia, AR 
Little Rock Levee, AR, East End 
Fourche Bayou 
McLean Bottom Levee District No. 3, 
Arkansas River, AR 
Near Dardanelle, Arkansas River, AR 
Newport, White River, AR 
North Little Rock, Arkansas River, AR 
Otter Creek and Tributaries, 
Shannon Hills, AR 
Petit Jean River, AR 
Pine Mountain Lake, AR 
Point Remove Levee and Drainage District, 
Conway County, AR 
Roland Drainage District, Arkansas River, 
AR 
Rolling Fork River, Sevier Coiunty, AR 
Skaggs Ferry, Black River, AR 
South Bank Arkansas River (Head Fourche 
Island to Pennington Bayou), AR 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Cancelled 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
1975 
1985 
1958 
1983 
1951 
1962 
1959 
1952 
1952 
1983 
1954 
1983 
1958 
1941 
1951 
1954 
1973 
1983 
1988 
1983 
1983 
1975 
1950 
1953 
1941 
1958 
1987 
1966 
1985 
1983 
1950 
1983 
1941 
1964 
$1,407,116 
44,500 
84,315 
42,172 
919,955 
271,717 
187,440 
1,018,840 
390,952 
53,506 
2,001,820 
117,898 
304,699 
99,511 
1,077,546 
845,300 
22,890 
131,699 
198,096 
28,968 
63,355 
1,901,899 
422,549 
198,069 
314,276 
512,001 
162,204 
84,350 
1,432,331 
86,943 
269,907 
64,500 
81,023 
1,404,852 
28-20

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACIVITIES FOR FY 1989 
TABLE 28-E 
(Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept. 30, 1989 
Full Report 
See Annual Operations and 
Project Status Report For Construction Maintenance 
South Bank, Arkansas River, Little Rock to 
Pine Bluff, AR, Tucker Lakes Completed 1961 409,115 - 
Swan Creek Bank Stab., Taney County, MO Completed 1986 76,800 - 
Van Buren, Arkansas River, AR Completed 1952 438,222 - 
Village Creek, White River, and Mayberry 
Levee Districts, AR Completed 1972 1,567,156 
Village Creek, Jackson and 
Lawrence Counties, AR Inactive 1977 510,217 
West of Morrilton, Arkansas River, AR Completed 1962 1,269,959 
White River, at Hwy 14, 1/4 mile east 
of Oil Trough, AR Completed 1981 214,308 
White River Bank Stab., Batesville, AR Completed 1986 101,100 
White River, Jacksonport, AR Completed 1987 277,600 _ 
1. Reclassified as inactive in Jun '77; reviewed & deferred in 5. RecLassified as inactive in Jul '85. 
May '85. 6. See H Doc 577, 87th Cong., 2d sess., for description of 
2. Recommended for deauthorization in Sep '86. project. 
3. Construction of project cancelled because Local interests 7. Reclassified in Jun '77; inabi ity of Local interests to meet 
fai led to provide right-of-way for construction and maintenance. Local cooperation requirements. 
4. Authorized by Chief of Engineers. 
TABLE 28-G DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Federal Contributed 
Project Report For Authority Deauthorized Funds Funds 
Arkansas River, Russellville, 
Morrilton, AR HRI1 May 77 1988 - 
Black River Basin, MO & AR _ HR10 QOct 74 1988 - 
Crooked Creek Lake 
& Levee, AR 1969 1968 FCA 1988 - 
Lone Rock, Buffalo 
River, AR 1959 1938 FCA 1977 $130,653 
Ozark Natl Rec Area, 
Bell Foley & Greers Ferry SR14 May 73 1988 70,000 
Prosperity Lake, MO PL93-251 1988 864,000 
Water Valley, Eleven 
Point River, AR & MO 1959 1963 FCA 1977 414,011 
White River Basin above 
Beaver Lake, AR SR26, Oct 72 1988 - 
28-21

TABLE 28-H ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Depth on Char- Year 
Up- Upper Miter Sill actcr Opened 
stream Lock Pool of to Total 
from Miles to Dimension Lift (feet, Upper Lower Foun- Kind of Type of Naviga- Estimat 
Feature Mouth Nearest Town (feet) (feet) MSL) (feet) (feet) dation Dam Construction tion Cost 
LITTLE ROCK 
DISTRICT 
Norrell L&D No. 1 
Lock No. 2 
Wilbur D. Mills Dam 
(No. 2) 
L&D No. 3 
10.3 8 east of Arkansas 
Post, AR 
13.3 6 east of Arkansas 
Post, AR 
40.5 3 southeast Arkansas 
Post, AR 
50.2 5 north of Grady, AR 
110 by 600 30 max 
110 by 600 20nom 
28 max 
142 
162 
16 15 Piles in Fixed 
sand overflow 
18 14 Piles in 
sand 
Concrete 1967 $34,265,000 
1967 43,869,000 
Piles in Movable Gated concrete 1968 
sand spillway with 
embankment 
ends 
110 by 600 20 182 18 14 Piles in 
sand 
Movable Gated concrete 1968 
spillway with 
embankment 
ends 
33,791,000 
L&D No. 4 
L&D No. 5 
David D. Terry 
L&D (No. 6) 
66.0 7 east of Pine Bluff, 
AR 
86.3 4 southeast of 
Redfield, AR 
108.1 12 southeast of Little 
Rock, AR 
110 by 600 14 196 
110 by 600 17 213 
110 by 600 18 231 
18 14 Piles in Movable Gated concrete 1968 
sand spillway with 
embankment 
ends 
18 14 Clay Movable Gated concrete 1968 
spillway with 
embankment 
ends 
18 14 Piles in Movable Gated concrete 1968 
sand spillway with 
embankment 
ends 
40,831,000 
29,568,000 
62,585,000
dl

TABLE 28-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Depth on Char- Year 
Up- Upper Miter Sill acter Opened 
stream Lock Pool of to Total 
form Miles to Dimension Lift (feet, Upper Lower Foun- Kind of Type of Naviga- Estimate 
Feature Mouth Nearest Town (feet) (feet) MSL) (feet) (feet) dation Dam Construction tion Cost 
d1 
Murray L&D (No.7) 
Toad Suck Ferry 
L&D (No. 8) 
Arthur V. Ormond 
L&D (No. 9) 
Dardanelle 
L&D (No. 10) 
L&D No. 11 
Ozark-Jeta Taylor 
L&D (No. 12) 
James W. Trimble 
L&D (No. 13) 
TULSA DISTRICT3 
James W. Trimble 
L&D (No. 13)(part) 
125.4 6 northwest of Little 
Rock, AR 
155.9 6 west of Conway, AR 
176.9 3 southwest of 
Morrilton, AR 
205.5 2 northwest of 
Dardanelle, AR 
110 by 600 
110 by 600 
18 249 
16 265 
110 by 600 19 284 
110 by 600 54 338 
18 14 Shale Movable Gated concrete 1969 
spillway with 
embankment 
ends 
18 14 Shale Movable Gated concrete 1969 
spillway with 
embankment 
ends 
18 14 Shale Movable Gated concrete 1969 
spillway with 
embankment 
ends 
18 14 Sand- Movable Gated concrete 1969 
stone spillway with 
embankment 
ends 
Deleted 
256.8 1 east of Ozark, AR 
292.8 7 east of Fort Smith, 
AR 
110 by 600 
110 by 600 
34 372 
20 392 
18 15 Sandstone 
and 
shale 
18 14 Sandstone 
and 
shale 
Movable Gated concrete 1969 
spillway with 
embankment 
ends 
Movable Gated concrete 1969 
spillway with 
embankment 
ends 
1970 6,858,(00) 
$37,492,000 
56,912,000 
34,357,000 
84,270,124 
85,629,412 
46,187,000

TABLE 28-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Depth on Char- Year 
Up- Upper Miter Sill acler Opened 
stream Lock Pool of to Total 
form Miles to Dimension Lift (feet, Upper Lower Foun- Kind of Type of Naviga- Eslimat 
Feature Mouth Nearest Town (feet) (feet) MSL) (feet) (feet) dation Dam Construction tion Cost 
W.D. Mayo 
L&D (No. 14) 
Robert S. Kerr 
L&D (No. 15) 
Webbers Falls 
L&D (No. 16) 
Chouteau L&D 
(No. 17) 
Newt Graham 
L&D (No. 18) 
319.6 4 east of Redland, 
OK 
336.2 1 north of Cowlington, 
OK 
366.6 1 northwest of Gore, 
OK 
401.4 4 northwest of Okay, 
OK 
421.6 8 southwest of Inola, 
OK 
110 by 600 20 412 
110 by 600 48 460 
110 by 600 30 490 
110 by 600 21 
110 by 600 21 532 
14 15 Rock Movable Gated concrete 1970 
spillway with 
embankment 
ends 
18 14 Rock Movable Gated concrete 1970 
spillway with 
embankment 
ends 
19 16 Rock Movable Gated concrete 1970 
spillway with 
embankment 
ends 
511 15 14 Rock Movable Gated concrete 1970 
spillway with 
embankment 
ends 
15 14 Rock Movable Gated concrete 1970 
spillway with 
embankment 
ends 
$32,655,000 
94,578,237 
83,738,277 
31,619,000 
44,355,000 
eci

TABLE 28-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Additional features entering into cost of project 
Little Rock District: 
Bank stabilization and channel rectification, mile 33.7 to 362 and 
Arkansas-White Cutoff, 100 per cent complete ........... $119,300,184 
Maintenance and repair fleet and marine terminals, 
99 percent complete ..................................... 7,500,000 
Total, Little Rock District ....................... 716,556,720 
Navigation aids (U.S. Coast Guard) ........................... 2,268,000 
Tulsa District: 
Bank stabilization and channel rectification, Short Mountain 
to Fort Smith, complete ................................. 12,700,038 
Maintenance and repair fleet and marine terminals, 
complete ............................................... 2,750,000 
Subtotal ....................................... $309,253,552 
Upstream Lakes:3 
Oologah, 90.2 miles upstream from mouth, Verdigris River 
complete ................. .......................... $ 46,772,329 
Keystone, 638.8 miles upstream from mouth, Arkansas River, 
complete....................... .............. 123,171,17 
Eufaula, 27 miles upstream from mouth, Canadian River, 
complete ........................................... 123,350,74 
Subtotal......................................... 293,294,24 
Total, Tulsa District .............................. 602,547,80 
Total Project Cost 96 percent complete .......... $1,319,104,52 
1. Navigation miLeage from mouth of White River except Dam No. 2 is 40.5 mites 
above mouth of Arkansas River. 
2. Includes cost of entrance channel. 
3. Details in TuLsa District report. 
O
0
O
cn C'1 
~t1 
0
z
rr 
0
C2 
x
C. 
O
00 
0
00

ARKANSAS RIVER BASIN; AR, OK, AND KS: LAKES 
(See Section 1 of Text) 
Lake and State 
Miles 
Above 
River Mouth Nearest Town 
Drainage 
Area 
(sq mi) 
Height 
of Dam 
(feet) 1pe 
Reservoir 
Capacity 
(acre-feet) 
Power 
Development 
(kilowatts) 
Blue Mountain, AR 
Canton, OK 
Elk City, KS 
(Table Mound) 
Eufaula, OK 1 2 
Fall River, KS 
Fort Gibson, OK 1 
Keystone, OK 1 2 3 
Markham Ferry, OK1 
Neodesha, KS5 
Nimrod, AR 
Oologah, OK2 
Pensacola, OK 1 6 
Tenkiller Ferry, OK 1 
Toronto, KS 
Wister, OK 
Petit Jean 
North Canadian 
Elk 
Canadian 
Fall 
Grand (Neosho) 
Arkansas 
4 Grand (Neosho) 
Verdigris 
Fourche La Fave 
Verdigris 
Grand (Neosho) 
3 Illinois 
Verdigris 
Poteau 
74.4 
384.3 
8.7 
27.0 
54.2 
7.7 
538.8 
47.4 
222.8 
62.6 
90.2 
77.0 
12.8 
271.5 
60.9 
Paris, AR 
Canton, OK 
Independence, KS 
Eufaula, OK 
Fall River, KS 
Fort Gibson, OK 
Sand Springs, OK 
Pryor, OK 
Neodesha, KS 
Plainview, AR 
Claremore, OK 
Disney, OK 
Gore, OK 
Toronto, KS 
Wister, OK 
488 
12,483 
634 
47,522 
585 
12,492 
74,506 
11,533 
1,152 
680 
4,339 
10,298 
1,610 
730 
993 
115 Earthfill 
68 Earthfill 
107 Earthfill 
114 
94 
110 
121 
90 
74 
103 
137 
147 
197 
90 
99 
Earthfill 
Earthfill 
Concrete-gravity 
Earthfill 
Earthfill 
Earthfill 
Concrete-gravity 
Earthfill 
Concrete arch 
Earthfill 
Earthfill 
Earthfill 
257,900 
383,300 
284,300 
3,798,000 
256,40() 
1,284,400 
1,836,500 
444,500 
90,000 
336,010 
1,519,0(X) 
2,197,000 
1.230,800 
199,700 
427,900 
90,000 
45,000 
70,000 
100,000 
86,400 
34,000 
1947 
1948 
1966 
1964 
1949 
1953 
1964 
1968 
0 
1942 
1974 
1940 
1953 
1960 
1949 
$ 5,069,974 
11,209,834 
19,052,990 
123,350,791 
10,550,873 
42,591,298 
123,171,173 
6,908,756 
97,910 
4,092,826 
46,722,329 
52,126 
24,017,724 
13,896,324 
10,501,226 
Subtotal, exclusive of Eufaula, Keystone, and Oologah, 93 percent complete. 
Arkansas River Basin; AR, OK and KS: Navigation (Table 28-H) 
Total, Arkansas River Basin, 98 percent complete 
1. Project includes facilities for production of hydroelectric 
power. 
2. Cost included in navigation project. 
3. Details in Tulsa District report. 
4. Constructed by State of Oklahoma under the name of 
Robert S. Kerr Dam (Lake Hudson). Estimate shown is for 
Federal participation. 
5. Inactive. Estimate is based on 1954 price levels. 
6. Constructed by State of Oklahoma under the name 
Grand River Dam (Lake O'The Cherokees). Estimate shown is 
for Federal participation. 
Table 28-I 
Year or 
Percent 
Complete 
Total 
Estimated 
Cost 
148,041,86 
1,319,104,52 
1,467,146,38 
_ ~_ 
~

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 28-J LIT'LE RIVER BASIN, AR: LAKES 
(See Section 26 of Text) 
Project River Site1 Nearest Town 
DeQueen Lake1 Rolling Fork River 22.8 DeQueen, AR 
Gillham Lake1 Cossatot River 49.0 Gillham, AR 
Dierks Lake1 Saline River 56.6 Dierks, AR 
Millwood Lake1 Little River 16.0 Millwood, AR 
1. Project is reported separately herein. 
28-27

WHIT'E RIVER BASIN; AR, AND MO: LAKES 
TABLE 28-K (See Section 33 of text) 
Miles Drainage Reservoir Power Total 
Above Area Hleight of Dam Above Streambed Capacity Development Estimate 
Lake River Mouth Nearest Town (sq mi) and Type (acre-feet) (kilowatts) Cost1 
Beaver2 White 609.0 Eureka Springs, AR 1,186 228 feet concrete-gravity and earthfill 1,952,000 112,000 $ 50,797, 
Bell Foley3 Strawberry 27.2 Poughkeepsie, AR 519 136 feet concrete-gravity and earthfill 518,000 93,700, 
Bull Shoals2 White 418.6 Mountain Home, AR 6,036 258 feet concrete-gravity 5,408,000 340,000 96,356, 
Clearwater2 Black 257.4 Piedmont, MO 898 154 feet earthfill 413,000 11,395,( 
Greers Ferry2 Little Red 79.0 Heber Springs, AR 1,146 243 feet concrete-gravity 1,844,000 96,000 55,125,( 
Norfork2 North Fork 4.8 Norfork, AR 1,806 216 feet concrete-gravity 1,983,000 80,550 111,624,( 
Table Rock2 While 523.8 Branson, MO 4,020 252 feet concrete-gravity and earthfill 3,462,000 200,000 71,233,( 
Total 15,580,000 828,550 490,230,( 
1. Current FY price levels unless otherwise noted. 3. Inactive--placed in a deferred status in May 1985. 
2. For details see individual reports. Estimate based on 1983 price Levels. 
000 
000 
000 
000 
00 
000 
000 
)00 
00

TULSA, OKLAHOMA, DISTRICT * 
The civil works portion of this District covers an area of 
approximately 160,000 square miles which includes Oklahoma 
and parts of Kansas and Texas within the Arkansas 
and Red River Basins. The District's responsibilities within 
the Arkansas River Basin cover southern Kansas, 
northern Oklahoma, and the Texas Panhandle. These 
areas are embraced in the drainage basin of the Arkansas 
River and its tributaries above the mouth of the Poteau 
River, extending to the Kansas-Colorado State line, 
exclusive of that portion of the South Canadian River 
Basin and its tributaries west of the Texas-New Mexico 
State line. The District's responsibilities within the Red 
River Basin cover the northern portion of Texas, and the 
southern portion of Oklahoma. These areas are embraced 
in the drainage basin of the Red River and its tributaries 
above Fulton, AR. 
IMPROVEMENTS 
Navigation Page 
1. McClellan-Kerr Arkansas River 
Navigation System, OK ................ 29-2 
2. Other Authorized Navigation Projects .... 29-2 
Flood Control 
Arcadia Lake, OK .................... 29-2 
Arkansas-Red River Basins Chloride Control 
Projects, KS, OK, and TX ............. 29-2 
Area V, Estelline Springs .............. 29-3 
Area VIII ............................ 29-3 
Birch Lake, OK ....................... 29-3 
Candy Lake, OK ......... ........ 29-3 
Canton Lake, OK ..................... 29-4 
Copan Lake, OK ...................... 29-4 
Council Grove Lake, KS .............. 29-4 
El Dorado Lake, KS .................. 29-4 
Elk City Lake, KS .................... 29-4 
Fall River Lake, KS ................... 29-4 
Fort Supply Lake, OK ................. 29-4 
Great Bend, KS ...................... 29-4 
Great Salt Plains Lake, OK ............ 29-5 
Halstead, KS ......................... 29-5 
Heyburn Lake and Polecat Creek, OK .. 29-5 
Hugo Lake, OK ................... 29-5 
Hulah Lake, OK ...................... 29-5 
John Redmond Dam and Reservoir, KS . 29-5 
Kaw Lake, OK ....................... 29-5 
Lake Kemp, TX ...................... 29-6 
Lake Wichita, Holliday Creek, TX ...... 29-6 
Marion Lake, KS ..................... 29-6 
Mingo Creek, OK ..................... 29-6 
Oologah Lake, OK .................... 29-6 
Optima Lake, OK ..................... 29-6 
Parker Lake, OK ...................... 29-7 
Page 
29. Pat Mayse Lake, TX .................. 29-7 
30. Pearson-Skubitz Big Hill Lake, KS ..... 29-7 
31. Pine Creek Lake, OK ................. 29-7 
32. Sardis Lake, OK ...................... 29-7 
33. Skiatook Lake, OK . ................. 29-7 
34. Toronto Lake, KS .................... 29-7 
35. Waurika Lake, OK . ................. 29-8 
36. Wister Lake, OK ..................... 29-8 
37. Other Authorized Flood 
Control Projects ....................... 29-8 
38. Inspection of Completed Local Flood 
Protection Projects .................... 29-8 
39. Scheduling Flood Control Reservoir 
Operations ............................. 29-8 
40. Emergency Flood Control Activities ..... 29-8 
41. Flood Control Work Under Special 
Authorization ......................... 29-8 
Multiple -Purpose Projects Including Power 
42. Broken Bow Lake, OK ................ 29-8 
43. Eufaula Lake, OK .................... 29-8 
44. Fort Gibson Lake, OK ................ 29-8 
45. Keystone Lake, OK ................... 29-9 
46. Lake Texoma (Denison Dam), OK 
and TX .............................. 29-9 
47. Robert S. Kerr Lock and Dam 
and Reservoir, OK .................... 29-9 
48. Tenkiller Ferry Lake, OK ............. 29-9 
49. Webbers Falls Lock and Dam, OK ..... 29-9 
29-1 
3. 
4. 
4a. 
4b. 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
19. 
20. 
21. 
22. 
23. 
24. 
25. 
26. 
27. 
28.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Genera 
50. 
51. 
52. 
Tables 
29-A 
29-B 
29-C 
29-D 
d Investigations Page 
Surveys .......... ...... .......... 29-10 
Collection and Study of Basic Data ... 29-10 
Preconstruction 
Engineering and Design .............. 29-10 
Cost and Financial Statement ......... 
Authorizing Legislation ............... 
Other Authorized Navigation Projects .. 
Not Applicable 
29-11 
29-16 
29-18 
Navigation 
1. McCLELLAN-KERR ARKANSAS 
RIVER NAVIGATION SYSTEM 
(Tulsa District Portion), OK. 
Location. The Tulsa District portion of the McClellan-Kerr 
Arkansas River Navigation System provides a navigation route 
up the Arkansas River from the Oklahoma-Arkansas State line 
to the head of navigation at Catoosa, OK, near Tulsa, OK. The 
total length of the Tulsa District portion of the system is 137 
navigation miles. Descriptions and costs for the entire navigation 
system can be found in Little Rock District's entry in this Annual 
Report. 
Existing projects. The McClellan-Kerr Arkansas River 
navigation project is a component of the multiple-purpose plan 
for the Arkansas River Basin which provides for the 
improvement of the basin through the construction of 
coordinated developments for navigation, hydroelectric power, 
flood control, water supply, water quality control, sediment 
control, recreation, and fish and wildlife propagation. The 
McClellan-Kerr project consists of bank stabilization, channel 
straightening, and cutoffs as required. The navigation channel 
has a minimum depth of 9 feet and minimum widths of 250 
feet on the Arkansas River and 150 feet on the Verdigris River. 
The Tulsa District portion of the navigation system consists of 
Arkansas River Bank Stabilization and Channel Rectification, 
Chouteau Lock and Dam, Newt Graham Lock and Dam, Robert 
S. Kerr Lock and Dam and Reservoir, Robert S. Kerr Marine 
Terminal, Sans Bois Navigation Channel, W.D. Mayo Lock and 
Dam, Webbers Falls Lock and Dam, and the pool in Oklahoma 
which was created by Lock and Dam 13 in Arkansas. The other 
parts of the multiple-purpose plan for the Arkansas River Basin 
are listed in Table 29-H. 
Local cooperation. Fully complied with. 
Terminal facilities. Public port facilities are in operation at 
Muskogee and Catoosa, OK, and at Fort Smith, AR. At Sallisaw, 
OK, a port authority has been active in seeking development of 
public facilities at that location. Other private commercial port 
facilities are complete and in operation at eight Oklahoma 
locations. 
Operations during fiscal year. Routine operation and 
maintenance continued. 
Page 
29-E Other Authorized Flood 
Control Projects ..................... 29-19 
29-F Not Applicable 
29-G Deauthorized Projects ................ 29-19 
29-H Arkansas River Basin Multiple- 
Purpose Plan ....................... 29-20 
29-I Inspection of Completed Local Flood 
Protection Projects ................... 29-20 
29-J Flood Control Work Under Special 
Authorization ........................ 29-21 
29-K General Investigations ................ 29-22 
2. OTHER AUTHORIZED NAVIGATION 
PROJECTS. 
See Table 29-C. 
Flood Control 
3. ARCADIA LAKE, OK. 
Location. On the Deep Fork River at river mile 218.3 in 
the metropolitan area of Oklahoma City and Edmond, OK, about 
1.5 miles west of Arcadia, in Oklahoma County, OK. (See 
Arcadia, OK, Geological Survey map, scale 1:24,000.) 
Existing project. The plan of improvement provides for 
flood control, water supply, and recreation by construction of an 
earthfill dam approximately 102 feet high and 5,250 feet long 
with a high-level uncontrolled spillway. Outlet works consist of 
a gated tower and conduit. The lake has a total capacity of 
92,000 acre-feet (27,380 for conservation, 64,430 for flood 
control, and 190 for sedimentation reserve) and controls a 
105-square-mile drainage area. Construction began in October 
1980 and the project became operational for flood control in 
November 1986. 
Local cooperation. Section 2 of the Flood Control Act of 
1938, the Water Supply Act of 1958, the Federal Water Project 
Recreation Act of 1965, and Section 221 of the Flood Control 
Act of 1970 apply. 
Operations and results during fiscal year. The project 
is 99 percent complete. Estimated cost is $90,400,000 (October 
1989 price level base). Funds of $768,000 were transferred from 
the project in FY 89. Remaining work in recreation is 
unscheduled pending settlement of lawsuit filed against the city 
of Edmond for payment of completed recreation work. Litigation 
is now in Western District Court, OK. Court date is tentatively 
scheduled for November 1990. The city of Edmond has signed 
an interim lease to assure parks will remain open. 
4. ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL PROJECTS, 
KS, OK, AND TX. 
Location. On certain tributary streams of the Arkansas and 
Red Rivers in the western half of the Tulsa District. 
Existing project. Provided for studies involving the control 
of water pollution caused by 15 natural salt sources identified 
29-2

TULSA, OKLAHOMA, DISTRICT 
in 1957 by the U.S. Public Health Service. The Arkansas and 
the Red Rivers represent major national and regional water 
resources severely limited due to poor water quality primarily 
caused by the natural pollutant, sodium chloride. The Arkansas 
River is polluted by five naturally occurring salt sources located 
in northwestern Oklahoma and southwestern Kansas. The Red 
River Basin is polluted by ten naturally occurring salt sources 
located in northwestern Texas and southwestern Oklahoma. 
These studies included the construction and subsequent 
maintenance of an ifection well and a ring dike used for data 
collection. Preauthorization studies completed in 1966 and 1970 
recommended construction of project features at 13 of the 15 
sites. For a detailed discussion of the chloride control projects, 
see the page 19-4 of the Annual Report for 1983. The Water 
Resources Development Act of 1986 (PL 99-662) authorized the 
Red River Basin and the Arkansas River Basin as separate projects 
with separate authority under Section 203 of the Flood 
Control Act of 1966. The Arkansas River portion of the project 
was deferred in 1982 (not economically justified). Preconstruction 
engineering and design is compl te on the Red River portion of 
the project. It is available for initiation of construction. 
4a. AREA V, ESTELLINE SPRINGS. 
Location. Chloride Control Area V is located about 0.5 mile 
east of Estelline, TX, on the Prairie Dog Town Fork of the Red 
River. 
Existing project. For a description of the completed 
improvement, see the Annual Report for 1987. Construction 
started in 1963 and the structure was completed in 1964. 
Local cooperation. Descriptive text concerning local cooperation 
requirements is given on page 19-5 of the Annual Report 
for 1983. 
4b. AREA VIII. 
Location. Chloride Control Area VIII is located at river mile 
74.9 of the South Fork of the Wichita River in King County, 
TX, about 5 miles east of Guthrie, TX. 
Existing project. The plan of improvement consists of two 
low-flow collection dams with attendant pumping stations and 
pipeline facilities. These two dams (the Bateman Low Flow Dam 
and the Ross Ranch Low Flow Dam) would be equipped with 
an inflatable fabric-type weir located in the spillway section 
which would be deflated to pass relatively good quality high 
flows. The collected brines would be pumped to the storage reservoir 
behind the Truscott Brine Dam. This brine dam, located 
at river mile 3.6 on Bluff Creek (a tributary of the North Fork 
of the Wichita River) about 3 miles northwest of Trusctt, TX, 
would contain the collected brines from this area as well as 
ftuture collections from Area X. Construction was initiated at 
Area VIII and Truscdt Brine Dam in 1976. The first of the 
two low-flow dams was completed and put into full operation 
in May 1987. The second was to be constructed after initial 
operation of the first to determine the effectiveness of the 
operation. 
Local cooperation. Descriptive text concerning local cooperation 
requirements is given on page 19-5 of the Annual Report 
for 1983. 
Operations and results during fiscal year. The Water 
Resources Development Act of 1986 authorized construction of 
the remaining areas of the Red River Chloride Control project 
pending transmittal of a report of a favorable finding of the 
effectiveness of the operation of Area VIII. Public Law 99-662 
established a panel to assess the improvement in water quality 
downstream of Area VIII as a measure of its effectiveness. A 
favorable report was submitted by the panel to the Secretary of 
the Army (CW) and to the Public Works Committees of the 
House and Senate in August 1988. 
5. BIRCH LAKE, OK. 
Location. On Birch Creek at river mile 0.8, about 1.5 miles 
south of Barnsdall in Osage County, OK. (See Barnsdall, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see the Annual Report for 1979. Construction 
began in November 1973 and the project was placed in useful 
operation in March 1977. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
6. CANDY LAKE, OK. 
Location. On Candy Creek, a tributary of Bird Creek in the 
Verdigris River Basin, at river mile 1.9. The damsite is about 
1.5 miles northeast of Avant in Osage County, OK. (See Avant, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. The plan of improvement provides for an 
earthfill dam about 4,200 feet long, including an uncontrolled 
concrete spillway, with a maximum height of 103 feet above 
streambed. Outlet works will consist of a gated intake structure, 
a 10- by 11.25-foot conduit, and a stilling basin. An 18- by 
24-inch low-flow pipe and an 18-inch water supply pipe will be 
provided. The lake will have a total capacity of 75,420 acre-feet 
(44,160 for conservation and sediment reserve and 31,260 for 
flood control). The drainage area above the damsite is 43 square 
miles. Candy Lake will be operated as a unit of a seven-lake 
system for flood control in the Verdigris River Basin in Oklahoma. 
Construction began in September 1976. 
Local cooperation. Section 2 of the Flood Control Act of 
1938, the Water Supply Act of 1958, and Section 221 of the 
Food Control Act of 1970 apply. 
Operations and results during fiscal year. The project 
was about 13 percent complete when construction was delayed 
because the U.S. Justice Department decided to withdraw 
condemnation proceedings to acquire mineral rights. Estimated 
cost of the project was $38,300,000 (October 1984 price level). 
The project was deferred in January 1984. Project land has been 
made available for low intensity recreation use. Routine operation 
and maintenance continued. 
29-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
7. CANTON LAKE, OK. 
Location. On the North Canadian River at river mile 394, 
about 2 miles north of Canton in Blaine County, OK. (See 
Canton, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 590 of the Annual Report for 1969. 
Construction began in December 1940 and the project was 
placed in useful operation in April 1948. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
8. COPAN LAKE, OK. 
Location. On the Little Caney River, a tributary of the 
Caney River in the Verdigris River Basin, at river mile 7.4, about 
2 miles west of Copan in Washington County, OK. (See Copan, 
KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-7 of the Annual Report for 1983. 
Copan Lake is operated as a unit of a seven-lake system for 
flood control in the Verdigris River Basin in Oklahoma. Construction 
began in November 1972 and the project was placed 
in useful operation in April 1983. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Work on the 
recreation contract was completed and the lake is physically 
complete. 
9. COUNCIL GROVE LAKE, KS. 
Location. On the Grand (Neosho) River at river mile 450, 
about 1.5 miles northwest of Council Grove in Morris County, 
KS. (See Council Grove Lake, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 519 of the Annual Report for 1969. 
Construction began in June 1959 and the project was placed in 
useful operation in July 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
10. EL DORADO LAKE, KS. 
Location. On the Walnut River, a tributary dof the Arkansas 
River, at river mile 100.2, about 4 miles northeast of El Dorado 
in Butler County, KS. (See El Dorado, KS, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a descripion of the completed 
improvement, see page 19-7 at the Annual Report for 1983. El 
Dorado Lake was authorized as a unit of a three-lake system 
for flood control in the Walnut River Basin. Construction began 
in October 1973, and impoundment began in June 1981. Project 
completion is scheduled for July 1989. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. The 12th 
Street bridge and road resurfacing were completed. Routine 
operation and maintenance continued. 
11. ELK CITY LAKE, KS. 
Location. On the Elk River at river mile 8.7, about 7 miles 
northwest of Independence in Montgomery County, KS. (See 
Table Mound, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 593 of the Annual Report for 1969. 
Construction began in February 1962 and the project was placed 
in useful operation in March 1966. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
12. FALL RIVER LAKE, KS. 
Location. On the Fall River at river mile 54.2, about 4 miles 
northwest of Fall River in Greenwood County, KS. (See Severy, 
KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a descririon of the completed 
improvement, see page 953 of the Annual Report for 1969. 
Construction began in May 1946 and the project was placed in 
full operation in April 1949. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
13. FORT SUPPLY LAKE, OK. 
Location. On Wolf Creek, a tributary of the North Canadian 
River, at river mile 5.5, about 12 miles northwest of Woodward 
in Woodward County, OK. (See Fort Supply, OK, Geological 
Survey Map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 594 of the Annual Report for 1969. 
Construction began in October 1938 and the project was placed 
in full flood control operation in May 1942. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
14. GREAT BEND, KS. 
Location. In Barton County, KS, on the north bank of the 
Arkansas River about 4.5 miles above its confluence with Walnut 
Creek. (See Great Bend, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. The plan, authorized by the Flood Control 
Act of 1965, provides for 6.2 miles of leveed channel to divert 
Walnut Creek flood flow around Great Bend into the Arkansas 
River upstream from the city; a 1.5-mile leveed channel to divert 
Little Walnut Creek flood flow into the Walnut Creek diversion 
levees along the Arkansas; a tie-back levee 4.3 miles long on 
the Arkansas left bank upstream from the junction of the Walnut 
diversion channel; and appurtenant facilities. 
29-4

TULSA, OKLAHOMA, DISTRICT 
Local cooperation. In accordance with the cost sharing and 
financing concepts reflected in the Water Resources Development 
Act of 1986, the city of Great Bend, KS, agreed to participate 
in project construction. 
Operations and results during fiscal year. Estimated 
cost of the project is $39,500,000 (October 1988 price level). The 
contract for Phase II-A was awarded 14 July 1989. Funds of 
$1,000,000 were reprogrammed from the project in FY 89. 
15. GREAT SALT PLAINS LAKE, OK. 
Location. On the Salt Fork of the Arkansas River at river 
mile 103.3, about 12 miles east of Cherokee in Alfalfa County, 
OK. (See Jet, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 594 of the Annual Report for 1969. 
Construction of the project began in September 1938 and was 
completed in July 1941. The project was placed in full flood 
control operation in May 1941. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
16. HALSTEAD, KS. 
Location. In the city of Halstead in Harvey County, KS, 
along the Arkansas River. (See Halstead, KS, Geological Survey 
Map, scale 1:24,000.) 
Existing project. Provides for channel modification and 
construction of about 4 miles of levee in combination with 
clearing and snagging and straightening and widening approximately 
3.6 miles of the Little Arkansas River channel to a 60- 
foot-bottom width in the vicinity of Halstead. Channel modification 
will be restricted to one side of the channel except in 
transition areas. Tree planting and revegetation will be done and 
ten pool riffle areas will be established to minimize environmental 
impacts. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Funds 
provided in FY 89 were used to complete the Design Memorandum 
and to coordinate the Local Cooperation Agreement 
(LCA). The LCA was signed in October 1989. Estimated project 
cost is $8,800,000 (October 1989 price level base). 
17. HEYBURN LAKE AND 
POLECAT CREEK, OK. 
Location. On Polecat Creek, a minor tributary of the 
Arkansas River, at river mile 48.6, about 11 miles west of 
Sapulpa in Creek County, OK. (See Lake Heyburn, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 599 of the Annual Report for 1969. 
Construction started in March 1948 and the project was placed 
in useful operation in October 1950. Channel improvements 
below the lake were completed in September 1952. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. The dam 
and reservoir, which is federally maintained and operated, is in 
good condition and performs as intended. Routine operation and 
maintenance continued. 
18. HUGO LAKE, OK. 
Location. On the Kiamichi River at river mile 17.6, about 
7 miles east of Hugo in Choctaw County, OK. (See Hugo Dam, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-12 of the Annual Report for 1977. 
Construction began in October 1967 and the project was placed 
in useful operation in January 1974. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
19. HULAH LAKE, OK. 
Location. On the Caney River at river mile 96.2, about 15 
miles northwest of Bartlesville, near Hulah, in Osage County, 
OK. (See Bowring, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 595 of the Annual Report for 1969. 
Construction began in May 1946 and was completed in June 
1950. The project was placed in full flood control operation in 
September 1951. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
20. JOHN REDMOND DAM AND 
RESERVOIR, KS. 
Location. The dam is located on the Grand (Neosho) River 
at river mile 343.7, about 2 miles northwest of Burlington in 
Coffey County, KS. (See John Redmond Dam, KS, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 581 of the Annual Report for 1970. 
Construction was initiated in July 1959 and was completed in 
December 1965. The project was placed in flood control 
operation in July 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
21. KAW LAKE, OK. 
Location. On the Arkansas River at river mile 653.7, about 
8 miles east of Ponca City in Kay County, OK. (See Charley 
Creek West, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-13 of the Annual Report for 1977. 
Construction began in June 1966 and the project was placed in 
operation in May 1976. 
29-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
22. LAKE KEMP, TX. 
Location. On the Wichita River at river mile 126.7, about 
40 miles southwest of Wichita Falls, TX. (See Northeast Lake 
Kemp, TX, Geological Survey Map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-14 of the Annual Report for 1977. 
Construction began in May 1970 and the project was placed in 
useful operation in October 1972. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
23. LAKE WICHITA, HOLLIDAY 
CREEK, TX. 
Location. The project is located in Wichita and Archer 
Counties, TX. The Lake Wichita dam and the Holliday Creek 
channel are located in the city of Wichita Falls, TX. (See Wichita 
Falls, TX, Geological Survey Map, scale 1:24,000.) 
Existing project. The proposed plan includes the 
replacement of the existing Lake Wichita dam with an earthen 
dam approximately 16,000 feet long, a concrete spillway, an 
auxiliary spillway, and low-flow outlet works. The plan also 
includes channel improvements along Holliday Creek from the 
new spillway to the Wichita River, a distance of 9.3 miles. 
Local cooperation. The city has removed one bridge, 
initiated construction of a portion of the channelization, initiated 
acquisition of real estate necessary for construction of the project, 
and initiated engineering and design for the relocation of utilities, 
streets, and highway bridges. 
Operations and results during fiscal year. The construction 
of Phase II channels is approximately 27 percent complete 
and will continue in FY 90 along with engineering and design 
and supervision and admenistration. Estimated project cost is 
$45,200,000 (October 1989 price level base). 
24. MARION LAKE, KS. 
Location. On the Cottonwood River at river mile 126.7, 
about 3 miles northwest of Marion in Marion County, KS. (See 
Pilson, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 597 of the Annual Report for 1969. 
Construction began in June 1964 and the project was placed in 
flood control operation in February 1968. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
25. MINGO CREEK, OK. 
Location. On the right-bank tributary of Bird Creek in 
Tulsa County, OK. (See Tulsa, OK, Geological Survey Map, 
Scale 1:24,000.) 
Existing project. The recommended plan will consist of 23 
detention sites which would capture peak flows and hold them 
temporarily until downstream flows subside. There would be 
about 9.4 miles of channelization in selected locations on the 
tributaries and main stem of Mingo Creek. This plan will 
provide a minimum of 65-year protection in the major damage 
area. 
Local cooperation. In accordance with the cost sharing and 
financing concepts reflected in the Water Resources Development 
Act of 1986, the non-Federal sponsor must provide lands, 
easements, rights-of-way, and dredged material disposal areas; 
modify or relocate buildings, utilities, roads, bridges (except 
railroad bridges), and other facilities where necessary in the 
construction of the project; pay five percent of the costs allocated 
to flood control; and bear all costs of operation, maintenance, 
and replacement of flood control facilities. The non-Federal 
sponsor has also agreed to make all required payments 
concurrently with project construction. The local sponsor is the 
city of Tulsa, OK. On August 26, 1983, the city of Tulsa 
adopted a Resolution of Assurance to provide a minimum share 
equal to 35 percent or the traditional lands, easements, and 
rights-of-way, whichever is greater, and will be required to assist 
in the actual financing of construction. The city has constructed 
4.75 miles of channel and placed two excavated detention 
facilities into flood control operation. 
Operations and results during fiscal year. Two 
contracts were awarded during FY 89 - main stem Phase I-A 
in September 1989 for $2,000,000, and Audubon in May 1989 
for $3,079,000. Estimated project cost is $167,800,000 (October 
1989 price level base). 
26. OOLOGAH LAKE, OK. 
Location. On the Verdigris River at river mile 90.2, about 
2 miles southeast of Oologah in Rogers County, OK. (See 
Oologah, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-15 of the Annual Report for 1972. 
Construction began in July 1950 but the project was placed in 
standby status in October 1951. Construction resumed in 
December 1955 and was completed in May 1963 for initial development. 
Construction for ultimate (second stage) development 
was initiated in July 1967 and was completed in 1974. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
27. OPTIMA LAKE, OK. 
Location. On the North Canadian River at river mile 623.2, 
about 4.5 miles northeast of Hardesty in Texas County, OK. 
(See Optima Dam, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the existing 
improvement, see page 19-16 of the Annual Report for 1979. 
29-6

TULSA, OKLAHOMA, DISTRICT 
Construction began in March 1966 and impoundment began in 
October 1978. Construction was completed in 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
28. PARKER LAKE, OK. 
Location. On Muddy Boggy Creek, a tributary of the Red 
River, about 23 miles east of Ada in Coal County, OK. (See 
Parker, OK, Geological Survey map, scale 1:24,000.) 
Existing project. Parker Lake is a multipurpose element in 
a plan of improvement for the Upper Muddy Boggy Creek Basin, 
OK. The project consists of an earthfill dam about 2,100 feet 
long, a gated outlet works for flood control and water supply, 
and a 600-foot-wide spillway. The lake created would have a 
total storage capacity of 237,000 acre-feet and would yield 42 
million gallons per day for municipal and industrial water supply. 
The project was authorized by the Water Resources Development 
Act of 1986. 
Local cooperation. The Oklahoma Water Resources Board, 
the local sponsor, has agreed to provide 5 percent of the costs 
allocated to flood control upfront and to reimburse the costs 
allocated to water supply over a 30-year period. 
Operation and results during fiscal year. Work in FY 
89 included a design memorandum for an access road and 
project building. Plans and specifications for the access road and 
project building were approved by Southwestern Division in 
January 1989. Estimated project cost is $62,500,000 (October 
1989 price level base). 
29. PAT MAYSE LAKE, TX. 
Location. On Sanders Creek, a tributary of the Red River, 
at river mile 4.6, about 12 miles north of Paris in Lamar County, 
TX. (See Grant, TX, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the complded 
improvement, see page 584 of the Annual Report for 1970. 
Construction began in March 1965 and the project was placed 
in full flood control operation in September 1967. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
30. PEARSON- SKUBITZ BIG HILL 
LAKE, KS. 
Location. On Big Hill Creek at river mile 33.3, about 4.5 
miles east of Cherryvale, KS. (See Dennis, KS, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-11 of the Annual Report for 1983. 
Construction began in April 1974 and impoundment began in 
March 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
31. PINE CREEK LAKE, OK. 
Location. On the Little River at river mile 145.3, about 5 
miles northwest of Wright City in McCurtain County, OK. (See 
Wright City, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 584 of the Annual Report for 1970. 
Construction began in February 1963 and the project was placed 
in useful operation in June 1969. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
32. SARDIS LAKE, OK. 
Location. On Jackfork Creek, a tributary of the Kiamichi 
River, at river mile 2.8, about 2.5 miles north of Clayton in 
Pushmataha County, OK. (See Yanush, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-11 of the Annual Report for 1983. 
Sardis Lake will be operated as a unit of a three-lake system 
for flood control in the Kiamichi River Basin. (The three-lake 
system includes Hugo and Tuskahoma Lakes.) Construction 
began in August 1975 and the project became operational in 
January 1983. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. The project 
is about 99 percent complete. Remaining work is on the Daisy 
Road Stage II-B. Stage II-B is about 86 percent complete; repair 
of Stage I is complete. Funds of $1,350,000 were transferred 
into the project in FY 89. Estimated cost of the project is 
$67,893,000 (October 1989 price level). 
33. SKIATOOK LAKE, OK. 
Location. On Hominy Creek, a tributary of Bird Creek in 
the Verdigris River Basin, at river mile 14.3, about 5 miles west 
of Skiatook in Osage County, OK. (See Avant S.E., OK, 
Geological Survey map, scale 1;24,000.) 
Existing project. For a description of the completed 
improvement, see Page 19-8 of the Annual Report for 1987. 
Construction began in January 1974, impoundment began in 
October 1984, and the project became operational in November 
1984. 
Local cooperation: Fully complied with. 
Operations and results during fiscal year. The project 
is 97 percent complete. Estimated cost of the project is 
$121,500,000 (October 1989 price level base). 
34. TORONTO LAKE, KS. 
Location. On the Verdigris River at river mile 271.5, about 
4 miles southeast of Toronto in Woodson County, KS. (See 
Fredonia, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 600 of the Annual Report for 1969. 
Construction began in November 1954 and the project was 
29-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
placed in full operation in March 1960. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
35. WAURIKA LAKE, OK. 
Location. On Beaver Creek, a tributary of the Red River, 
at river mile 27.0, about 6 miles northwest of Waurika in 
Jefferson County, OK. (See Hastings, OK- TX, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-12 of the Annual Report for 1983. 
Waurika Lake is operated as a unit of a coordinated lake system 
for flood control in the Red River Basin. Construction began in 
July 1971 and impoundment began in August 1977. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operations and maintenance continued. 
36. WISTER LAKE, OK. 
Location. On the Poteau River at river mile 60.9, about 2 
miles south of Wister in LeFlore County, OK. (See Wister, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 601 of the Annual Report for 1969. 
Construction began in April 1946 and was completed in May 
1949. The project was placed in full flood control operation in 
October 1949. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. A contract 
for Phase I of major rehabilitation was awarded June 5, 1989, 
in the amount of $3,919,000. The contract for Phase II will be 
awarded upon resolution of a protest. Estimated major rehabilitation 
cost is $11,300,000 (October 1989 price level base) 
37. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS. 
See Table 29-E. 
38. INSPECTION OF COMPLETED 
LOCAL FLOOD PROTECTION 
PROJECTS. 
Inspections of completed, Federally constructed local flood 
protection projects which are owned, operated, and maintained 
by local interests are made to determine the extent of compliance 
with approved regulations for operations and maintenance. The 
inspections assist the Corps of Engineers in determining if the 
project provides the flood protection for which it was constructed. 
See Table 29-I for a list of projects inspected in FY 89. Fiscal 
year cost was $103,025. 
39. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS. 
The Tulsa District, Corps of Engineers is responsible for flood 
control operations at 12 non-Corps projects. These include nine 
Bureau of Reclamation lakes, two Grand River Dam Authority 
lakes, and one city-county owned lake. All of these projects were 
constructed wholly or in part with Federal funds. No unusual 
problems were experienced at any of these projects during FY 
89. Fiscal year cost for scheduling flood control reservoir 
operations toaled $677,029. 
40. EMERGENCY FLOOD CONTROL 
ACTIVITIES. 
Fiscal year cost for national emergency preparedness was 
$75,790 and for advance measures was $77,097. 
41. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION. 
See Table 29-J for FY 89 expenditures for Small Flood 
Control Projects Not Specifically Authorized by Congress (Section 
205); Emergency Streambank and Shoreline Projects (Section 
14); Snagging and Clearing; and Flood Control and Coastal 
Emergencies, Rehabilitation Projects. 
Multiple -Purpose Projects 
Including Power 
42. BROKEN BOW LAKE, OK. 
Location. On the Mountain Fork River at river mile 20.3, 
about 9 miles northeast of Broken Bow in McCurtain County, 
OK. (See Broken Bow, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvements, see page 29-17 of the Annual Report for 1971. 
Construction began in November 1961 and the project was 
placed in useful operation in October 1969. Power units 1 and 
2 were placed in operation in January and June 1970, 
respectively. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
43. EUFAULA LAKE, OK. 
Location. On the Canadian River at river mile 27.0, about 
12 miles east of Eufaula in McIntosh County, OK. (See Porum, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 588 of the Annual Report for 1970. 
Construction began in December 1956 and the project was 
placed in full flood control operation in February 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
44. FORT GIBSON LAKE, OK. 
Location. On the Grand (Neosho) River at river mile 7.7, 
about 5 miles north of Fort Gibson in Muskogee County, OK. 
(See Fort Gibson Dam, OK, Geological Survey map, scale 
1:24,000.) 
29-8

TULSA, OKLAHOMA, DISTRICT 
Existing project. For a description of the complted 
improvement, see page 604 of the Annual Report for 1969. 
Construction began in March 1942 but was held in abeyance 
during World War II. Construction resumed in May 1946 and 
was completed in June 1950. The fourth generator was installed 
and the project placed in full operation in September 1953. The 
Water Resources Development Act of 1986 authorized the 
construction of hydropower units 5 and 6. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
45. KEYSTONE LAKE, OK. 
Location. On the Arkansas River at river mile 538.8, near 
Sand Springs, OK, and about 15 miles west of Tulsa, OK. (See 
Keystone Dam, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 589 of the Annual Report for 1970. 
Construction began in January 1957 and the project was placed 
in flood control operation in September 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
46. LAKE TEXOMA (DENISON DAM), 
OK AND TX. 
Location. On the Red River at river mile 725.9, about 5 
miles northwest of Denison, TX. (See Denison Dam, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 603 of the Annual Report for 1969. Lake 
Texoma is operated as a unit of a coordinated lake system for 
flood control in the Red River Basin. Construction started in 
August 1939 and was completed in February 1944. Commercial 
power generation was started in March 1945. Authorized work 
is complete except for installation of the third, fourth, and fifth 
power units. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
47. ROBERT S. KERR LOCK AND DAM 
AND RESERVOIR, OK. 
Location. On the Arkansas River at navigation mile 336.2, 
about 8 miles south of Sallisaw in eFlore County, OK. 
(See Robert S. Kerr, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-21 of the Annual Report for 1972. 
The Robert S. Kerr Lock and Dam and Reservoir is a unit of 
the McClellan-Kerr Arkansas River Navigation System. Construction 
began in April 1964 and closure was completed in 
October 1970. The lock and dam became operational for 
navigation in December 1970. Generating units 1, 2, 3, and 4 
were placed in operation in October, July, September, and 
November 1971, respectively. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Five sites have been developed for 
handling coal, grain, construction aggregrates, and miscellaneous 
cargo. The facilities are considered adequate for present traffic. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
48. TENKILLER FERRY LAKE, OK. 
Location. On the Illinois River at river mile 12.8, 7 miles 
northeast of Gore in Sequoyah County, OK. (See Gore, OK, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a descriiion of the completed 
improvement, see page 606 of the Annual Report for 1969. 
Construction began in June 1947 and was completed in July 
1953. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
49. WEBBERS FALLS LOCK AND 
DAM, OK. 
Location. On the Arkansas River at navigation mile 366.6, 
about 5 miles northwest of Webbers Falls in Muskogee County, 
OK. (See Webbers Falls, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-23 of the Annual Report for 1977. 
The Webbers Falls Lock and Dam is a unit of the 
McClellan-Kerr Arkansas River Navigation System. Construction 
began in January 1965, and the project was placed in useful 
operation in November 1970. The lock and dam became 
operational for navigation in December 1970. Generating units 
1, 2, and 3 were placed in operation in August, September, and 
November 1973, respectively. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Facilities at the Port of Muskogee 
include: A cargo pier, mooring dolphins, warehouse, terminal 
building, and fuel facility built by the Muskogee City-County Port 
Authority; a liquid cargo loading facility and a steel unloading 
facility built by Frontier Steel Company; grain holding facilities 
built by Conagra, Inc.; and a general-purpose private dock built 
by the Fort Howard Paper Company. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
29-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
General Investigations 
50. SURVEYS. 
Fiscal year cost was $2,429,186 which included 11 flood 
damage prevention studies; 2 comprehensive studies; 2 restudies 
of deferred projects; inventory of dams - special investigations and 
review of FERC licenses, and coordination with her Federal 
agencies, States and intragency water resources development; 
and non-Federal interests. Table 29-K provides a specific list and 
respective fiscal year expenditures. 
51. COLLECTION AND STUDY OF 
BASIC DATA. 
Fiscal year cost was $311,399 which includes flood plain 
management services and hydrologic studies. Table 29-K 
provides a specific list and respective fiscal year expenditures. 
52. PRECONSTRUCTION 
ENGINEERING AND DESIGN. 
Fiscal year cost was $1,003,858 which includes two flood 
control reservoirs and four local protection projects. Table 29-K 
provides a specific list and respective fiscal year expenditures.
29-10

TULSA, OKLAHOMA, DISTRICT 
Table 29-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 19891 
1. McClellan-Kerr Arkansas 
River Navigation System, 
OK, (Tulsa District 
Portion) 
3. Arcadia Lake, OK 
4. Arkansas-Red River Basins 
Chloride Control, KS, OK, 
and TX 
4a. Area V, Estelline Springs, TX 
4b. Area VIII, TX 
5. Birch Lake, OK 
6. Candy Lake, OK 
7. Canton Lake, OK 
- - - - 130,936,6382 
S- - - 130,936,6382 
8,635,900 7,778,050 10,166,800 4,207,100 132,507,061 
9,120,610 7,895,973 9,367,272 4,224,784 127,376,720 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
3,146 
4,410 
6,000 
5,882 
943,000 
601,912 
127,300 
127,232 
595,000 
611,520 
8,285 
-222 
-222 
435 
1,660 
330,844 
459,500 
457,269 
615,400 
611,826 
47,590 
1,500,000 
815,940 
294,600 
304,715 
768,000 
1,323,780 
417,500 
392,488 
376 
5,700 
5,048 
28,300 
26,232 
341,291 
693,500 
654,204 
709,800 
687,249 
-22,000 
8,272 
24,100 
14,338 
3,635 
4,288 
3,300 
5,288 
115,936 
770,300 
802,076 
759,972 
771,336 
19,000 
19,242 
1,188,500 1,146,922 1,585,400 1,403,400 
1,297,427 1,142,413 1,481,886 1,508,298 
29-11 
82,108,289 
81,657,964 
880,900 
839,724 
25,705,208 
25,705,068 
3,533,506 
3,646,832 
300,028 
300,028 
169,111 
183,699 
46,493,000 
46,418,486 
2,050,600 
2,040,781 
13,549,170 
13,549,296 
6,968,573 
10,253,240 
4,927,922 
4,927,714 
43,100 
33,580 
11,209,834 
10,918,727 
19,899,594 
19,971,579 
1t T 7 
6,646,000 6,300,000 
11,417,121 6,092,367 
100 168,700 
-315 142,836 
182 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Table 29-A 
(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 19891 
8. Copan Lake, OK 
9. Council Grove Lake, KS 
10. El Dorado Lake, KS 
11. Elk City Lake, KS 
12. Fall River Lake, KS 
13. Fort Supply Lake, OK 
14. Great Bend, KS 
15. Great Salt Plains Lake, OK 
16. Halstead, KS 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
3,092,000 
1,050,879 
491,000 
501,204 
450,000 
725,909 
587,100 
609,896 
2,127,911 
729,800 
674,358 
353,133 
903,200 
875,777 
88,676,999 
91,987,703 
3,751,000 
3,653,202 
- 11,810,509 
- 11,810,509 
856,000 1,420,122 
876,525 1,444,285 
1,412,317 
319,800 
338,798 
870,500 
917,213 
453,181 
329,100 
328,807 
654,300 
686,243 
818,300 
803,059 
1,930,000 
2,064,749 
416,500 
391,983 
843,900 
864,027 
131,000 
318,066 
536,208 
539,477 
777,400 1,005,708 
745,711 1,026,682 
11,821,944 
11,793,246 
92,432,468 
92,265,049 
2,927,908 
2,901,292 
19,052,990 
19,052,990 
10,770,814 
10,723,259 
- 10,550,873 
- 10,550,873 
835,800 
1,091,136 
671,000 
687,903 
696,600 
703,723 
622,800 
619,807 
888,200 1,054,600 
801,319 1,132,283 
942,600 1,024,500 
889,571 970,456 
220,000 1,140,000 1,500,000 
126,531 1,031,858 1,247,994 
485,200 
636,153 
370,600 
366,615 
250,000 
156,920 
507,200 1,033,200 
427,519 1,119,370 
375,000 
454,756 
200,000 
203,551 
11,185,995 
11,339,542 
7,724,134 
7,723,127 
10,753,973 
10,616,384 
2,860,000 
2,406,383 
4,626,270 
4,626,270 
7,082,307 
7,072,602 
825,000 
815,227 
29-12

TULSA, OKLAHOMA, DISTRICT 
Table 29-A 
(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 19891 
17. Heyburn Lake and 
Polecat Creek, OK 
18. Hugo Lake, OK 
19. Hulah Lake, OK 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Minor Rehab 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
20. John Redmond Dam 
and Reservoir, KS 
21. Kaw Lake, OK 
22. Lake Kemp, TX 
23. Lake Wichita, 
Holliday Creek, TX 
24. Marion Lake, KS 
25. Mingo Creek, OK 
495,200 
531,820 
610,400 
564,381 
693,200 
681,398 
826,000 
787,096 
- 1,868 974 4,023 
1,217,600 2,712,122 2,398,900 1,328,700 
1,264,286 2,597,490 2,462,384 1,343,855 
291,600 
497,400 
642,100 
648,068 
721,000 
681,541 
595,300 
597,517 
1,380,600 1,009,622 1,212,200 1,546,200 
1,563,663 892,125 1,284,003 1,562,032 
143,616 5,264 3,102 -390 
1,714,200 2,118,422 2,430,300 1,772,700 
2,080,047 2,139,648 2,202,005 1,884,007 
138,000 
172,196 
118,300 
120,895 
169,700 
160,954 
150,680 
158,216 
805,000 1,704,000 6,755,000 
677,910 1,275,692 6,826,669 
719,300 
789,868 
831,500 
830,572 
906,600 
797,669 
889,800 
910,507 
- 2,087,000 4,884,000 
446,418 2,268,007 
29-13 
2,560,572 
2,560,572 
8,796,923 
8,794,842 
37,759,742 
37,432,108 
16,746,850 
16,568,047 
11,388,150 
11,182,433 
11,095,279 
11,008,195 
135,718 
135,718 
28,151,515 
28,151,515 
18,801,677 
18,847,092 
109,430,750 
109,429,274 
19,323,090 
19,153,295 
7,637,702 
7,637,702 
1,986,914 
1,984,348 
9,264,000 
8,780,271 
13,420,817 
13,420,817 
12,010,346 
11,889,997 
6,971,000 
2,714,425

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Table 29-A 
(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 19891 
26. Oologah Lake, OK 
27. Optima Lake, OK 
28. Parker Lake, OK 
29. Pat Mayse Lake, TX 
30. Pearson-Skubitz 
Big Hill Lake, KS 
31. Pine Creek Lake, OK 
32. Sardis Lake, OK 
33. Skiatook Lake, OK 
34. Toronto Lake, KS 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
1,179,000 1,252,522 1,295,700 1,135,100 
1,306,646 1,246,801 1,309,601 1,143,974 
485,500 
490,736 
451,500 
448,801 
961,000 
55,496 
542,900 
525,318 
200,000 
288,951 
561,000 
578,602 
-654,000 
119,194 
46,722,3293 
46,721,5563 
19,351,426 
19,331,602 
47,173,438 
47,273,438 
4,758,422 
4,788,614 
522,000 
463,641 
- 9,310,661 
- 9,310,661 
930,000 
1,018,712 
692,800 
689,368 
927,400 
870,590 
805,100 
869,122 
40 
797,600 
825,038 
45,998 
924,900 
1,065,137 
7,453,000 
1,055,291 
673,700 
671,787 
- 230,000 
1,041,357 
578,600 
524,973 
301,000 
292,120 
767,300 1,007,300 1,025,700 
786,870 961,795 1,066,793 
22,313 
780,800 
768,370 
572,000 
3,607,419 
665,350 
690,076 
509,874 
609,700 
639,033 
400,500 
410,820 
849,500 
883,439 
-202 
1,008,600 
999,405 
5,215,000 1,350,000 
4,138,635 4,273,156 
823,900 
812,244 
2,000,000 
279,972 
795,900 
712,124 
313,200 
291,831 
888,800 
887,629 
433,000 
2,189,460 
987,700 
1,002,919 
211,900 
233,835 
11,158,609 
11,144,569 
16,879,166 
16,879,165 
5,701,200 
5,697,978 
20,628,049 
20,627,847 
11,056,658 
11,000,442 
67,893,479 
65,760,353 
4,202,850 
4,177,311 
106,181,282 
106,138,089 
3,190,300 
3,081,202 
13,896,324 
13,896,324 
5,286,103 
5,283,938 
29-14

TULSA, OKLAHOMA, DISTRICT 
Table 29-A 
(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 19891 
35. Waurika Lake, OK 
36. Wister Lake, OK 
42. Broken Bow Lake, OK 
43. Eufaula Lake, OK 
44. Fort Gibson Lake, OK 
45. Keystone Lake, OK 
46. Lake Texoma (Denison Dam), 
OK and TX 
47. Robert S. Kerr Lock and 
Dam and Reservoir, OK 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Major Rehab 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Minor Rehab 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
24,340 
938,200 
958,274 
29,910 
73,000 
192,927 -8,034 
901,922 1,121,600 1,209,100 
899,739 1,083,398 1,212,261 
67,153,050 
67,142,501 
8,833,966 
7,784,634 
- 10,501,226 
- 10,501,226 
718,400 
777,134 
774,500 
758,208 
852,100 
836,200 
802,800 
805,894 
940,000 
922,683 
1,274,100 1,334,022 1,677,900 1,626,200 
1,393,509 1,342,585 1,501,749 1,779,734 
478,000 
287,346 
3,137,400 
3,319,004 
192,000 
786,814 
3,771,922 
3,751,284 
63,796 
4,725,100 
4,488,574 
17,617 
3,666,000 
3,403,633 
2,898,800 3,239,622 3,300,400 3,230,500 
3,187,330 3,144,482 3,138,033 3,354,424 
2,681,300 3,081,022 3,666,600 2,902,200 
2,844,576 3,033,653 3,491,838 3,024,825 
5,070,800 4,593,222 5,668,500 5,350,600 
5,433,240 4,534,606 5,592,446 5,473,749 
10,863,860 
10,828,281 
940,000 
922,683 
41,222,692 
41,222,692 
18,516,541 
18,473,541 
123,350,7474 
123,012,7624 
50,880,366 
47,373,436 
42,591,298 s 
43,497,791 s 
45,569,188 
46,778,635 
123,171,1736 
123,170,6756 
39,777,652 
39,743,799 
68,168,9607 
68,019,1097 
81,801,170 
81,705,441 
46,237 
46,237 
- - - 94,578,237 
- - 94,578,237 
2,452,000 2,413,300 4,273,100 4,592,584 42,578,820 
2,510,997 2,531,516 4,037,108 4,781,357 42,126,223 
29-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Table 29-A 
(Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 19891 
48. Tenkiller Ferry Lake, OK New Work 
Approp - - 24,017,7208 
Cost - - 24,057,7188 
Maint 
Approp 2,927,600 3,115,037 3,291,800 2,739,000 39,201,614 
Cost 3,081,392 3,178,124 3,061,753 2,831,687 39,043,115 
49. Webbers Falls Lock New Work 
& Dam, OK Approp - - - - 83,738,277 
Cost - - - - 83,738,701 
Maint 
Approp 3,561,800 2,341,900 2,860,500 2,433,300 39,754,764 
Cost 3,867,890 2,368,464 2,529,036 2,728,735 39,821,131 
1. Includes $2,077,900 expended by the Jobs Act (P.L. 98-8, 6. Excludes $5,366,231 special funds. 
dated March 24, 1983) for projects listed in Table 29-M of the 7. Includes $433,539 Emergency Relief funds. Exchange 
FY 85 Annual Report. $1,256,068 from special contributed funds. 
2. Includes $12,700,038 for Bank Stabilization and Channel 8. Excludes $946 contributed funds. Includes $39,999 Public 
Rectification. Works acceleration funds. 
3. Excludes $81,460 contributed funds and $1,348,816 special 9. The cost for Grand Lake 0' the Cherokees has been added 
funds. to amount reported in paragraph 40, Scheduling Reservoir 
4. Excludes $299,803 contributed funds and $13,211,728 Operations. 
special funds. 
5. Excludes $134,919 contributed funds. Includes $49,581 
Public Works acceleration funds. 
Table 29-B AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
July 24, 1946 
October 22, 1976 
November 17, 1986 
December 31, 1970 
October 22, 1976 
4. 
4a. October 23, 1962 
4b. November 7, 1966 
December 31, 1970 
November 17, 1986 
McCLELLAN-KERR ARKANSAS 
RIVER NAVIGATION SYSTEM 
Big and Little Sallisaw 
Creeks Navigation Project 
W.D. Mayo Hydropwer 
ARCADIA LAKE 
Changed water quality to water supply 
ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL 
Authorized Area V (Estelline Springs) 
Authorized Areas VII, VIII, and X 
Authorized Areas I, II-III, VI, IX, XIII, XIV, and XV 
Authorized the Red River Basin 
and the Arkansas River Basin as 
separate projects with separate authority. 
HD 79-758, 
PL 79-525 
PL 94-587 
PL 99-662 
HD 91-299 
PL 94-587 
SD 87-107 
PL 89-789, SD 110 
PL 91-611 
PL 99-662 
29-16 
1.

TULSA, OKLAHOMA, DISTRICT 
Table 29-B 
(Continued) AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
5. October 23, 1962 
6. October 23, 1962 
7. June 28, 1938 
July 24, 1946 
June 30, 1948 
8. October 23, 1962 
9. May 17, 1950 
10. October 27, 1965 
11. August 18, 1941 
12. August 18, 1941 
13. June 22, 1936 
14. November 17, 1986 
15. June 22, 1936 
16. November 17, 1986 
17. July 24, 1946 
18. July 24, 1946 
19. June 22, 1936 
20. May 17, 1950 
February 15, 1958 
21. October 23, 1962 
22. October 23, 1962 
23. November 17, 1986 
24. May 17, 1950 
25. November 17, 1986 
26. June 28, 1938 
27. June 22, 1936 
28. November 17, 1986 
29. October 23, 1962 
30. October 23, 1962 
November 10, 1978 
31. July 3, 1958 
32. October 23, 1962 
December 4, 1981 
33. October 23, 1962 
34. August 18, 1941 
35. December 30, 1963 
HD 
HD 
HD 
BIRCH LAKE 
CANDY LAKE 
CANTON LAKE 
Approved Irrigation Storage 
Approved Water Supply Storage 
COPAN LAKE 
COUNCIL GROVE LAKE 
EL DORADO LAKE 
ELK CITY LAKE 
FALL RIVER LAKE 
FORT SUPPLY LAKE 
GREAT BEND 
GREAT SALT PLAINS LAKE 
HALSTEAD 
HEYBURN LAKE AND POLECAT CREEK 
HUGO LAKE 
HULAH LAKE 
JOHN REDMOND DAM AND RESERVOIR 
Authorized name change 
KAW LAKE 
LAKE KEMP 
LAKE WICHITA, HOLLIDAY CREEK 
MARION LAKE 
MINGO CREEK 
OOLOGAH LAKE 
OPTIMA LAKE 
PARKER LAKE 
PAT MAYSE LAKE 
PEARSON-SKUBITZ BIG HILL LAKE 
Authorized name change 
PINE CREEK LAKE 
SARDIS LAKE 
Authorized name change 
SKIATOOK LAKE 
TORONTO LAKE 
WAURIKA LAKE 
87-563 
87-563 
75-569 
HD 87-563 
HD 80-442 
HD 89-232 
HD 76-440 
HD 76-440 
HD 74-308 
PL 99-662 
HD 74-308 
PL 99-662 
HD 80-290 
HD 79-602 
HD 74-308 
HD 80-442 
PL 85-327 
HD 87-143 
HD 87-144 
PL 99-662 
HD 80-442 
PL 99-662 
Committee Doc. 
No. 1, 75th 
Cong., 1st Session 
HD 74-308 
PL 99-662 
HD 88-71 
HD 87-472 
PL 95-265 
HD 85-170 
SD 87-145 
PL 97-88 
HD 87-563 
HD 76-440 
PL 77-228 
SD 88-33 
PL 88-253 
29-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Table 29-B 
(Continued) AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
36. June 28, 1938 WISTER LAKE Committee Doc. 
No. 1, 75th 
Cong., 1st Session 
July 30, 1983 Changed conservation pool PL 98-63 
elevation 
42. July 3, 1958 BROKEN BOW LAKE HD 85-170 
October 23, 1962 SD 87-137 
43. July 24, 1946 EUFAULA LAKE HD 79-758 
44. August 18, 1941 FORT GIBSON LAKE HD 76-107 
July 24, 1946 Incorporated into the PL 76-228 
multiple-purpose plan for 
the Arkansas River Basin 
November 17, 1986 Added hydropower units 5 & 6 PL 99-662 
45. May 17, 1950 KEYSTONE LAKE SD 81-07 
46. LAKE TEXOMA (Denison Dam) 
June 28, 1938 Flood control and power HD 75-541 
October 17, 1940 Navigation and regulating flows PL 76-868 
Sepember 30, 1944 Authorized name PL 78-454 
August 14, 1953 Water supply PL 83-273 
November 17, 1986 Recreation PL 99-662 
47. July 24, 1946 ROBERT S. KERR LOCK AND HD 79-758 
DAM AND RESERVOIR 
July 8, 1963 Authorized name change PL 88-62 
48. June 28, 1938 TENKILLER FERRY LAKE Committee Doc. 
No. 1, 75th 
Cong., 1st Session 
June 24, 1946 Power HD 79-758 
49. July 24, 1946 WEBBERS FALLS LOCK AND DAM HD 79-758 
Table 29-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Big and Little Sallisaw Navigation Project Inactive - 
Poteau River Navigation Project, OK and AR Complete 1983 536,952 
Red River from Fulton, AR, to Mouth of Washita River Complete 1924 378,574 182,157 
29-18

TULSA, OKLAHOMA, DISTRICT 
TABLE 29-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Augusta LPP, KS"' 2 1938 84,217 
Big Pine Lake, TX3 1984 1,701,670 
Boswell Lake, OK3 1952 
Cherry and Red Fork Creeks LPP, OK2 1970 261,448 
Crutcho Creek LPP, OK3 1972 213,016 
Dodge City LPP, KS2 
Enid LPP, OK2 1963 743,612 14,599 
Flat Rock and Valley View Creeks LPP, Tulsa, OK2' 4 1975 1,741,000 
Florence LPP, KS2 1965 369,782 
Hutchinson LPP, KS2 1956 3,497,718 
Iola LPP, KS2 1939 22,290 
Jenks LPP, OK2 1950 344,797 
Joe Creek LPP, OK2 308,041 
Lamed LPP, KS2 
Lukfata Lake, OK3 1983 1,424,685 
Marion, KS2 1988 5,488,190 
McGrath Creek, Wichita Falls, TX5 
Oklahoma City LPP, OK2 1960 8,047,512 
Red River Bank Stabilization Below Denison, OK and TX2 1953 222,105 
Sand Creek LPP, KS2 1968 545,996 
Sand Lake, OK' 1963 
Shidler Lake, OK3 1983 568,191 
Tulsa and West Tulsa LPP, OK2 1954 2,785,070 
Turtle Creek LPP, Yukon, OK3 1975 144,853 
Tuskahoma Lake, OK' 1963 
West Branch Chisholm Creek LPP, KS2 1965 364,200 
Wichita and Valley Center LPP, KS2 1960 12,247,379 
Winfield LPP, KS1' 2 1937 
LPP - Local Protection Project. 
1. Completed by Kansas Works Progress Administration. 
2. Complete. 
3. Deferred. 
4. Federal cost limited to $1,000,000. 
5. Active with no current year expenditures. 
TABLE 29-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Cedar Point Lake, KS 1980 November 17, 1986 0 0 
Public Law 99-662 
Cow Creek, Hutchinson, KS 1971 November 17, 1986 363,720 0 
Public Law 99-662 
El Dorado, West Branch, 1977 November 17, 1986 92,319 0 
Walnut River, KS Public Law 99-662 
Neodesha Lake, KS 1952 November 17, 1986 97,910 0 
Public Law 99-662 
Towanda Lake, KS 1981 November 17, 1986 392,361 0 
Public Law 99-662 
29-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 29-H ARKANSAS RIVER BASIN MULTIPLE-PURPOSE PLAN 
(See Section 1 of Text) 
Feature River River Mile 1 Nearest Town 
LAKES 
Canton North Canadian 394.3 Canton, OK 
Elk City Elk River 8.7 Elk City, KS 
Eufaula Canadian 27.0 Eufaula, OK 
Fall River Fall River 54.2 Fall River, KS 
Fort Gibson Grand (Neosho) 7.7 Fort Gibson, OK 
Grand Lake 0' the Cherokees Grand (Neosho) 77.0 Disney, OK 
Keystone Arkansas 538.8 Sand Springs, OK 
Lake Hudson (Markham Ferry) Grand (Neosho) 47.4 Locust Grove, OK 
Neodesha Verdigris 222.8 Neodesha, KS 
Oologah Verdigris 90.2 Oologah, OK 
Tenkiller Ferry Illinois 12.8 Gore, OK 
Toronto Verdigris 271.5 Toronto, KS 
Wister Poteau 60.9 Wister, OK 
McCLELLAN-KERR ARKANSAS RIVER NAVIGATION SYSTEM, OK 
(Tulsa District Portion) 
Bank Stabilization and Channel Rectification Verdigris and Arkansas N/A2 Fort Smith, AR, to Catoosa, OK 
Chouteau Lock and Dam (17), OK Verdigris 401.5 Okay, OK 
Lock and Dam 13, AR Arkansas 292.8 Fort Smith, AR 
Newt Graham Lock and Dam (18), OK Verdigris 421.6 Inola, OK 
Robert S. Kerr Lock and Dam (15), OK Arkansas 339.0 Sallisaw, OK 
Robert S. Kerr Marine Terminal, OK Arkansas 336.2 Cowlington, OK 
Sans Bois Navigation Channel, OK Sans Bois Creek 341.0 Keota, OK 
W.D. Mayo Lock and Dam (14), OK Arkansas 319.6 Redland, OK 
Webbers Falls Lock and Dam (16), OK Arkansas 366.6 Gore, OK 
1. On the McClellan-Kerr Arkansas River Navigation System, these are navigation miles. 
2. As required for a channel 9 feet deep. 
TABLE 29-I INSPECTION OF COMPLETED LOCAL FLOOD 
PROTECTION PROJECTS 
(See Section 38 of Text) 
Projects Inspected in Fiscal Year Inspection Date 
Hutchinson, KS May 1989 
Park City, KS June 1989 
Wichita and Valley Center, KS May 1989 
29-20

TULSA, OKLAHOMA, DISTRICT 
TABLE 29-J FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 41 of Text) 
Fiscal Year 
Study Identification/Name Cost 
SMALL FLOOD CONTROL PROJECTS NOT SPECIFICALLY 
AUTHORIZED BY CONGRESS (Section 205) 
Blackboy Creek, Tulsa County, OK 
Caney River (Kennilworth Addition), Bartlesville, OK 
Coal Creek, Henryetta, OK 
Coweta Creek, Coweta, OK 
Dog Creek, Waynoka, OK 
East Plum Creek, Wichita Falls, TX 
Haikey Creek, Tulsa County, OK 
Joe Creek, Tulsa, OK 
Merkle Creek, Norman, OK 
Muskogee, OK 
North Canadian River Wastewater Plant, Oklahoma City, OK 
Pauls Valley, OK 
Rock Creek, Burlington, KS 
Tahlequah Creek 
Walnut Creek, Purcell, OK 
Washita River, OK 
Whiskey and Rock Creeks, Independence, KS 
Whitewater and Walnut River, Augusta, KS 
Wichita Falls, TX 
TOTAL SMALL FLOOD CONTROL PROJECTS 
EMERGENCY STREAMBANK AND SHORELINE PROTECTION (Section 14) 
Chikaskia River, Blackwell, OK 
City Dam, Little Caney River, KS 
County Road (Sec. 2), Deer Creek, KS 
County Road (Sec. 6), Deer Creek, KS 
County Road, Verdigris River, KS 
County Road, Tner Creek, Adair County 
County Road, Washita River, Carter County 
Dam and Bridge, Neosho River, KS 
Fort Cobb Sewage Lagoon, OK 
Lee Creek, Adair County, OK 
Levee, Arkansas River, Tulsa 
Murray County Bridge, OK 
North Canadian River (11th Street Bridge), Yukon, OK 
North Canadian River, Okfuskee County, OK 
Sewage Lagoons, North Canadian River 
State Highway 156, Kay County, OK 
Verdigris River City Dam, Independence, KS 
Walnut River, Cowley County, KS 
Washita River, Anadarko, OK 
TOTAL EMERGENCY STREAMBANK AND SHORELINE PROTECTION 
SNAGGING AND CLEARING 
Elk River, Elk County, KS 
Minnehaha Creek, Canton, OK 
South Deer Creek, Shawnee, OK 
Unnamed Trib., Tecumseh, OK 
Walnut Creek, Purcell, OK 
TOTAL SNAGGING AND CLEARING 
FLOOD CONTROL AND COASTAL EMERGENCIES, REHABILITATION 
Tulsa/West Tulsa Levee 
TOTAL FLOOD CONTROL AND COASTAL EMERGENCIES, REHABILITATION 
29-21 
67,005 
2,664 
6,417 
4,142 
37,435 
19,827 
6,459 
16,312 
36,878 
46,453 
819,387 
600 
34,637 
52,458 
26,636 
47,366 
4,800 
377 
46,406 
1,266,258 
33,859 
8,200 
3,515 
3,625 
7,696 
2,855 
5,012 
1,952 
4,455 
543 
8,369 
521 
94 
-338 
3,359 
2,164 
229,333 
3,304 
95 
318,614 
3,031 
10,000 
7,868 
11,096 
4,154 
36,149 
-702 
-702

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 29-K GENERAL INVESTIGATIONS 
(See Sections 50, 51, and 52 of Text) 
Fiscal Year 
Study Identification/Name Cost 
SURVEYS 
Flood Damage Prevention Studies 
Arkansas River, Great Bend, KS, to Tulsa, OK 309,864 
Arkansas River Basin, AR and OK 331,239 
Canadian River Basin, OK, TX, and NM 10,576 
Crutcho Creek, OK 124,708 
Grand (Neosho) River, KS and OK 2,226 
Keystone Dam to Tulsa, Ark River 210,065 
Lake Texoma, OK and TX 362,481 
Miami and Vicinity, OK 243,283 
North Canadian River Above Lake Overholser 62,732 
Verdigris River Basin 243 
Verdigris River Basin, KS and OK, Caney 9,873 
Comprehensive Studies 
Arkansas River and Tributaries, South Central-Southeast Areas, OK 206,079 
Red River Basin, AR, TX, LA, and OK CM 223,687 
Review of Authorized Projects 
Restudy of Deferred Projects 
Lukfata Lake, OK 43,929 
Winfield, KS 1,427 
Inventory of Dams 
Special Investigations 40,981 
Review of FERC Licenses 2,411 
Intragency Water Resources Development 16,434 
Coordination with Other Federal Agencies, States, and Non-Federal Interests 
Soil Conservation Service 3,992 
Bureau of Reclamation 6,050 
Planning Assistance to States - Texas 0 
Planning Assistance to States - Kansas 65,195 
Planning Assistance to States - Oklahoma 151,719 
TOTAL SURVEYS 2,429,186 
COLLECTION AND STUDY OF BASIC DATA 
Flood Plain Management Services 
Flood Plain Management Services 120,396 
Ponca City, OK, Flood Forecast Map 2,792 
Technical Services General 174,418 
Tulsa Forecast Maps 13,495 
Hydrologic Studies 
Storm Studies 298 
TOTAL COLLECTION AND STUDY OF BASIC DATA 311,399 
PRECONSTRUCTION ENGINEERING AND DESIGN 
Flood Control Reservoirs 
Douglass Lake, KS 1,645 
Parker Lake, OK 4,110 
Local Protection 
Arkansas City, KS 136,771 
Fry Creeks, Bixby, OK 519,614 
Mingo Creek, OK 315 
Upper Little Arkansas River Watershed, KS 341,402 
TOTAL PRECONSTRUCTION ENGINEERING AND DESIGN 1,003,858 
29-22

FORT WORTH, TX, DISTRICT *
District includes that portion of Texas south of Red 
River drainage basin exclusive of drainage basin of Rio 
Grande and its tributaries above and including Pecos 
River; exclusive of drainage basins to all short streams 
arising in coastal plain of Texas and flowing into the 
Gulf of Mexico, including entire basins of Buffalo 
Bayou, San Jacinto, San Bernard, Lavaca, Navidad, 
Mission, and Arkansas Rivers; exclusive of lower basins 
of major streams flowing into the gulf as 
follows: Sabine River, Texas and Louisiana, downstream 
from U.S. Highway 190 crossing at Bon Wier, 
Texas; Neches River downstream from Town Bluff 
gaging station; Trinity River downstream from Texas 
State Highway 45 crossing at Riverside, Texas; Brazos 
River downstream from confluence with Navasota 
River; Colorado River downstream from gaging station 
at Austin; Guadalupe River downstream from 
confluence with San Marcos River; San Antonio River 
downstream from confluence with Escondido Creek; 
Nueces River downstream from confluence with Frio 
and Atascosa Rivers; and exclusive of Agua Dulce, San 
Fernando, and Olmos Creek basins draining into Baffin 
Bay; coastal area south thereof to Rio Grande and 
south to the northern boundaries of Newton, Jasper, 
Tyler, Polk, Trinity, Walker, Waller, Austin, Fayette, 
Gonzales, Karnes, Live Oak, Jim Hogg, Zapata; the 
northern and western boundaries of McMullan; and the 
western boundaries of Montgomery and Duval Counties, 
Texas. District also includes those portions of the 
Sulphur River and Cypress Creek Watershed located in 
the State of Texas; that portion of western Louisiana in 
Sabine River drainage basin upstream from U.S. 
Highway 190 crossing at Bon Wier, Texas. 
30-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
IMPROVEMENTS 
Navigation l 
1. Trinity River Project, TX ............... 
Flood Control 
2. Aquilla Lake, TX ..................... 
3. Bardwell Lake, TX .................... 
4. Belton Lake, TX ...................... 
5. Benbrook Lake, TX .................... 
6. Boggy Creek, TX ...................... 
7. Canyon Lake, TX .................... .. 
8. Cooper Lake and Channels, TX .......... 
9. Ferrells Bridge Dam- 
Lake O' The Pines, TX ................. 
10. Grand Prairie, TX (Meyers Road) ......... 
11. Grapevine Lake, TX ................... 
12. Hords Creek Lake, TX ................. 
13. Joe Pool Lake, TX .................... 
14. Lavon Lake, TX ...................... 
15. Lavon Lake Modification and East Fork 
Channel Improvement, TX .............. 
16. Lewisville Dam, TX ................... 
17. Navarro Mills Lake, TX ................ 
18. O.C. Fisher Dam and Lake, TX .......... 
19. Proctor Lake, TX ..................... 
20. Ray Roberts Lake, TX ................. 
21. San Antonio Channel Improvement, TX ... 
22. San Gabriel River, TX ................ 
23. Somerville Lake, TX .................. 
24. Stillhouse Hollow Dam, TX ............ 
25. Waco Lake, TX ...................... 
Page Flood Control (Cont) Page 
30-2 26. Wright Patman Dam and Lake, TX ...... 30-11 
27. Inspection of Completed Flood Control 
Projects ............................ 30-11 
30-3 28. Scheduling Flood Control Reservoir 
30-3 Operations ......................... 30-12 
30-4 29. Other Authorized Flood Control Projects .. 30-12 
30-4 30. Flood Control Work Under Special 
3n_A Authorization ....................... 30-12 
30-5 
30-5 
30-6 
30-6 
30-6 
30-7 
30-7 
30-7 
30-8 
30-8 
30-8 
30-9 
30-9 
30-9 
30-9 
30-10 
30-10 
30-11 
30-11 
Multiple-Purpose Projects Including Power 
31. Robert Douglas Willis Hydropower, TX ... 
32. Sam Rayburn Dam and Reservoir, TX .... 
33. Town Bluff Dam- 
B.A. Steinhagen Lake, TX ............. 
34. Whitney Lake, TX ................... 
General Investigations 
35. Surveys ............................ 
36. Collection and Study of Basic Data ...... 
30-12 
30-12 
30-13 
30-13 
30-13 
30-13 
Tables 
Table 30-A Cost and Financial Statement .. 30-15 
Table 30-B Authorizing Legislation ........ 30-19 
Table 30-C Other Authorized Flood Control 
Projects ..................... 30-22 
Table 30-D Inspection of Completed Flood 
Control Projects .............. 30-22 
Table 30-E Flood Control Work Under 
Special Authorization .......... 30-23 
Navigation 
1. TRINITY RIVER PROJECT, TX 
The project authorized by the River and Harbor Act 
of 1965 (H. Doc 276, 89th Cong., 1st Sess.) consists of 
five major components: Multiple-Purpose Channel, 
Tennessee Colony Lake, Dallas Floodway Extension, 
West Fork Floodway, and Water Conveyance Facilities. 
For the last full report on the project as authorized, see 
Annual Report of 1978. The project information 
present herein is based on the tentatively selected 
project plan presented in the Draft General Design 
Memorandum. The plan consists of three structural 
components: Dallas Floodway Extension, Tennessee 
Colony Lake, and Channel to Liberty in the lower 
basin. The estimated cost of the improvements is 
$1,235,000 including $107,000,000 non-Federal cost for 
land acquisition and relocation required for the local 
protection features (Oct. 1, 1987, base price). 
Operations during fiscal year. The authorized 
projects have been dormant for several years due to 
lack of local support. 
CHANNEL TO LIBERTY: 
Location. The Channel to Liberty begins at the 
Houston Ship Channel, crosses the bay area in an 
easterly direction to intersect the existing Double 
Bayou Channel turns northward along the coastline to 
Wallisville Lake and then continues northward 
through the lake area along the course of the Trinity 
River to River Mile 45 above Liberty, Texas. 
Existing project. The navigation portion of the 
channel will have a width of 200 feet with a depth of 12 
feet and will extend from the Houston Ship Channel in 
Galveston Bay to the port of Liberty, Texas. The flood 
control portion of the channel will have a bottom width 
of 200 feet with a depth of 30 feet, and will extend from 
Wallisville Lake to River Mile 45 above Liberty, Texas. 
Estimated Federal cost of the improvements is 
$147,000,000 and estimated non-Federal cost is 
$44,000,000 for a total estimated cost of $191,000,000 
(Oct. 1, 1987, base price). 
Local cooperation. Local interests are required to: 
(a) provide, without cost to the Federal Government, all 
lands, easements and rights-of-way required for construction, 
operation and maintenance of the project, 
30-2

FORT WORTH, TEXAS DISTRICT 
(b) accomplish, without cost to the Federal Government, 
all relocations and alterations to existing 
improvements, other than highway bridges over new 
land cuts and railroad bridges required for the 
construction of the project, (c) maintain and operate the 
flood control portion of the channel upstream of 
Liberty, Texas, and (d) reimburse the Federal Government 
for one-half of the separable costs allocated to 
recreation and fish and wildlife enhancement. This 
reimbursement is presently estimated at $34,000, 
exclusive of interest. 
TENNESSEE COLONY LAKE: 
Location. The Tennessee Colony dam site is 
located at River Mile 341.7 on the Trinity River about 
22 miles west of Palestine, Texas. The lake would 
extend into Freestone, Anderson, Henderson, and 
Navarro Counties, and would control a drainage area of 
12,302 square miles. 
Existing project. The plan of improvement provides 
for the construction of an earthfilled dam with a 
maximum height of 123 feet above the streambed and a 
total embankment length of 42,350 feet with a gated 
concrete spillway. The lake will have a total controlled 
storage of 3,455,000 acre-feet and a water surface area 
of 114,400 acres at the top of the flood control pool and 
68,100 acres at the top of the conservation pool. The 
total storage includes 2,269,500 acre-feet for flood 
control, 1,040,000 acre-feet for conservation, and 
145,500 acre-feet for sediment reserve. Estimated 
Federal cost of the improvement is $913,000,000 (Oct. 1, 
1983, base price). 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated 
to water supply storage and one-half of the separable 
cost allocated to recreation and fish and wildlife 
enhancement. This reimbursement is presently estimated 
at $461,754,000 for water supply and $9,533,000 
for recreation (excluding future recreation facilities), 
for a total cost of $471,287,000, exclusive of interest. 
DALLAS FLOODWAY EXTENSION: 
Location. Dallas Floodway Extension is located on 
the Trinity River in the City of Dallas, Dallas County, 
Texas. 
Existing project. The plan of improvement provides 
for extending the existing Floodway downstream 
about 9 miles to the confluence of the Trinity River and 
Five Mile Creek. The plan consists of a leveed floodway 
and flood conveyance improvement (channel) along the 
main stem, Five Mile Creek and White Rock Creek. 
Maintained free of encroachments, the levees and 
channels would provide Standard Project Flood protection 
for approximately 7,300 acres of urban lands 
currently subject to flooding. The estimated Federal 
cost is $68,000,000 and estimated non-Federal cost is 
$63,000,000 for a total estimated cost of $131,000,000 
for the improvement (Oct. 1, 1983, base price). 
Local cooperation. Local interests are required to: 
(a) provide, without cost to the Federal Government, all 
lands, easements and rights-of-way necessary for construction, 
maintenance and operation of the project, (b) 
accomplish, without cost to the Federal Government, 
all alterations to existing improvements, other than 
railroad bridges required for the construction of the 
project, (c) maintain and operate the project after 
completion, and (d) reimburse the Federal Government 
for one-half of the separable costs allocated to recreation 
and fish and wildlife enhancement. This reimbursement 
is presently estimated at $1,878,000 (excluding 
future recreation) exclusive of interest. 
Flood Control 
2. AQUILLA LAKE, TX 
Location. On Aquilla Creek in Hill County, Texas, 
with the dam at River Mile 23.3, about 6.8 miles 
southwest of Hillsboro, Texas, and about 24.0 miles 
north of Waco, Texas. 
Existing project. For description of completed 
improvements and authorizing Acts see Annual Report 
for 1984. Construction was started March 1977, and 
project was ready for beneficial use April 29, 1983. 
Estimated cost is $46,100,000. 
Local cooperation. The Water Supply Act of 1958, 
as amended, and the Federal Water Project Recreation 
Act of 1965 and Section 221, Flood Control Act of 1970 
apply. A contract with the Brazos River Authority for 
water supply storage was approved by the Secretary of 
the Army, June 29, 1976. To date, the Authority has 
paid $141,283 toward principal and $17,008 to operation 
and maintenance. 
Benefits accrued to Aquilla project: Accumulated 
flood damages prevented through FY 1989 were 
$1,919,000. 
Operations during fiscal year. Routine operation 
and maintenance continue. 
3. BARDWELL LAKE, TX 
Location. Dam is on Waxahachie Creek, 5 river 
miles upstream from its confluence with Chambers 
Creek, a tributary of the Trinity River, and about 5 
miles south of Ennis, Ellis County, Texas. 
Existing project. For a description of completed 
improvement and authorizing act see Annual Report of 
1969. Construction of project was started August 1963 
and completed for beneficial use in November 1965. 
Estimated cost of project is $12,941,000. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs allocated to 
increased water supply storage under the terms of the 
Water Supply Act of 1958. A Contract was approved by 
the Secretary of the Army on June 24, 1963, and the 
Trinity River Authority, a State agency, agreed to 
fulfill all requirements of local cooperation. To date the 
authority his paid $588,565 toward principal and 
$747,951 toward annual cost of operation and maintenance 
of project, including cost of operating 10-foot 
conduit. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
30-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Benefits accrued to Bardwell project: Accumulated 
flood damages prevented through FY 1989 were 
$9,137,800. 
4. BELTON LAKE, TX 
Location. Dam is on Leon River about 16.7 miles 
above confluence of Leon and Lampasas Rivers and 
about 3 miles north of Belton, Texas. 
Existing project. For a description of completed 
improvement and authorizing acts see Annual Report 
of 1962. Construction started June 1949 and project 
was ready for beneficial use in March 1954. Raising 
water supply pool: Construction started in July 1970 
and the pool raise is complete. Estimated cost of project 
is $18,410,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with Brazos River Authority, 
a State agency, for remaining water supply storage in 
reservoir was approved by Secretary of the Army on 
January 15, 1958, at an estimated cost of $1,602,822. To 
date $1,186,817 has been paid. Under the contract 
Brazos River Authority must also pay annually 11.2 
percent of actual annual cost of operation and maintenance. 
To date $1,323,854 has been paid. An interim 
contract with Brazos River Authority for emergency 
use of water supply storage in project was approved by 
Secretary of the Army on January 2, 1957. Amount of 
$331,410 paid by authority on March 21, 1957 for use of 
these facilities was credited to interest and principal 
payable under formal water supply contract. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Belton project: Accumulated 
flood damages prevented through FY 1989 were 
$118,806,600. 
5. BENBROOK LAKE, TX 
Location. Dam is in Tarrant County, Texas, on 
Clear Fork of Trinity River 15 river miles upstream 
from its confluence with West Fork of Trinity River 
about 10 miles southwest of downtown Fort Worth, 
Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Construction of project was started May 1947 
and ready for beneficial use in September 1952. 
Estimated cost of project is $14,544,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. No water supply storage is included in 
project. In 1956, Congress passed legislation enabling 
the city of Fort Worth to purchase conservation storage 
space in Benbrook lake. Contracts have been negotiated 
with the city of Fort Worth and the Benbrook Water 
and Sewer Authority for the use of portions of the 
navigation storage for water supply purposes until such 
storage is required for Trinity River Navigation. To 
date $166,851 has been paid by the city of Fort Worth 
and $123,522 by Benbrook Water and Sewer Authority. 
A cost sharing contract with the city of Benbrook for 
Recreation Development was approved by the Secretary 
of the Army May 20, 1977. To date, $18,321 has 
been paid. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to system consisting of Benbrook 
Lake, Clear Fork and West Fork Floodways: Accumulated 
flood damages prevented through FY 1989 are 
estimated at $60,658,800. 
6. BOGGY CREEK, AUSTIN, TX 
Location. The project is located on Boggy Creek in 
southeast portion of the city of Austin, Texas. 
Existing project. The Boggy Creek Channel Improvement 
Project will consist of approximately 2 miles 
of concrete and gabion lined channel beginning just 
upstream of Webberville Road and extending downstream 
almost to Jain Lane. From there the Channel is 
about 1.0 mile of grasslined trapezoidal channel to Ed 
Bluestein (Highway 183) where it transitions back into 
the natural channel. The project will include a 54 acre 
tract near the lower end of the project which will serve 
as a mitigation and environmental quality enhancement 
area. Approximately 1.0 mile of nature trail will 
be included in the mitigation/enhancement area. The 
project will require the replacement or modification of 
four bridges. It will also include the replacement of two 
railroad bridges with one bridge. Estimated Federal 
cost is $16,700,000 and $8,500,000 non-Federal cost 
(Oct. 1, 1989, base price). 
The proposed flood control channel will provide 
capacities for the 100 year flood. Design will provide for 
containment of flows within the banks of the improved 
channels. Bottom widths for the concrete channel will 
vary from 60 feet to 90 feet, and top widths from 80 feet 
to 120 feet. 
Local cooperation. In accordance with the cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, the City of Austin 
is required to provide lands, easements, rights-of-way, 
and material disposal areas, presently estimated at 
$2,129,000; modify or relocate buildings, utilities, roads 
and other facilities except railroad bridges, where 
necessary in the construction of the project presently 
estimated at $4,719,000; pay one-half of the separable 
costs allocated to recreation, presently estimated at 
$231,000; and bear all costs of operation, maintenance, 
and replacement of recreation facilities, presently 
estimated at $32,000 annually; pay five percent of cost 
allocated to flood control, presently estimated at 
$1,227,000 and bear all cost of operation, maintenance, 
and replacement of flood control facilities presently 
estimated at $43,000 annually; pay 33 percent of the 
first costs allocated to environmental quality enhancement, 
presently estimated at $64,000; pay 37 percent of 
the separable first cost allocated to fish and wildlife 
mitigation, presently estimated at $130,000 and bear 
all costs of operation, maintenance, and replacement of 
fish and wildlife facilities presently estimated at 
$5,000. The city will also be required to hold and save 
30-4

FORT WORTH, TEXAS DISTRICT 
the United States free from damages due to the 
construction work, operate and maintain all works 
after completion, prevent any obstruction or encroachment 
that would reduce the flow capacity of the project, 
provide and maintain adequate lateral drains and 
channels, publicize flood plain information for all 
streams in the watershed and adopt and enforce 
regulations to minimize damages to future developments 
within the 100-year flood plain, and administer 
and assure access to the recreational facilities and 
lands to all on an equal basis. 
Operations during fiscal year. Specific authorization 
for construction of Boggy Creek is found in FY 
1985 Supplemental Act. In FY 1989 work continued on 
the Channel Improvement Part I; contracts were 
awarded on Relocation of the Railroad Bridge and the 
Channel Improvement Part II. Project completion is 
scheduled for FY 1991. 
7. CANYON LAKE, TX 
Location. Dam is on Guadalupe River, 303 miles 
above its mouth, and about 12 miles northwest of New 
Braunfels, Comal County, Texas. 
Existing project. For a description of completed 
improvement and authorizing act see Annual Report of 
1969. Construction started April 1958 and project 
completed for beneficial use June 1964. Estimated cost 
of project is $21,732,000, including $1,400,000 contributed 
by local interests. 
Local cooperation. Local interests (Guadalupe- 
Blanco River Authority) will utilize water impounded 
for water supply and streamflow regulation for development 
of electric power. In a formal contract approved 
by Chief of Engineers on October 24, 1957, Guadalupe- 
Blanco River Authority agreed to fulfill all requirements 
of local cooperation. Required contribution of 
$1,400,000 was made in full by Guadalupe-Blanco River 
Authority. The estimated cost of the water storage 
contract is about $9,000,000. To date $1,770,654 has 
been paid. In addition, $22,848 was contributed for 
installation and operation of reservoir leakage gages. 
Under the contract the authority must pay 34.8 percent 
of actual annual cost of operation and maintenance. To 
date $1,069,561 has been paid. 
Operations during fiscal year. Regular funds: 
Routine operation and maintenance continued. Recreation 
facilities under Code 710 remain. 
Benefits accrued to Canyon project: Accumulated 
flood damages prevented through FY 1989 were 
$58,878,300. 
8. COOPER LAKE AND CHANNELS, 
TX 
Location. Cooper Dam is located in northeast 
Texas about 4 miles southeast of Cooper, 13.0 miles 
north of Sulphur Springs, and is at river mile 23.2 on 
the South Sulphur River. The South Sulphur River 
rises in Fannin County, Texas, and flows generally east 
for about 80 miles to its confluence with the North 
Sulphur River to form the Sulphur River. 
Existing project. The authorized plan of improvement 
consists of a multipurpose reservoir with levee 
and channel improvements on the Sulphur River. The 
reservoir consists of a rolled earthfill dam with a 
maximum height of about 73 feet, 28,070 feet long at its 
crest, a single conduit 10.5 feet in diameter, 530 feet 
long, two 10.5 foot by 4.75 foot sluices, and a 700 foot 
wide uncontrolled concrete spillway. The reservoir 
surface area will be 22,740 acres at the top of the flood 
control pool, 19,305 acres at the top of the water supply 
pool, and 5,084 acres at the top of the sediment pool. 
The reservoir will contain 131,400 acre-feet of flood 
control storage, 273,000 acre-feet of municipal and 
industrial water supply storage, and 37,000 acre-feet of 
sediment storage. 
Construction of the project began in July 1958 and, 
to date, approximately 66 percent of the lands required 
for project construction have been acquired and 98 
percent of the levees and 100 percent of the channel 
work have been completed. Approximately 14.8 miles of 
the South Sulphur River and 6.3 miles of the Middle 
Sulphur River channels have been excavated. Approximately 
3.4 miles of levee embankment on the South 
Sulphur River and 7.3 miles on the Middle Sulphur 
River have been constructed upstream of the Cooper 
Lake. About 10.5 miles of levee on the North Sulphur 
River, 8.2 miles of levee on the Sulphur River, 14 miles 
of levee on Cuthand Creek, and 4.2 miles of levee on 
Brushy Creek were strengthened; 0.5 mile of levee on 
Kickapoo Creek was enlarged; and 15.3 miles of new 
channel in Cuthand Creek, 0.8 mile of new channel in 
Brushy Creek, and 0.2 mile of cutoff channel in 
Kickapoo Creek were excavated; all downstream from 
Cooper Lake. 
Lack of funds and spending limitations prevented 
construction of the levees and channel work between 
April 1964 and February 1971. Construction was 
started again, however, in May 1971. The Texas 
Committee on Natural Resources, et. al., secured an 
injunction to halt construction on the project pending 
preparation of an Environmental Impact Statement 
(EIS), required by the National Environmental Policy 
Act of 1969. A statement was prepared and filed on 
June 24, 1977. The plan recommended, in the Final 
EIS, minimized further construction of the authorized 
channels and provided for construction of the lake and 
downstream levees. The sufficiency of the Final EIS 
was challenged in the court and in December 1978 the 
U.S. District Court for the Eastern District of Texas 
ruled the statement inadequate, citing five deficiencies 
and halting all further construction. A Supplemental 
EIS to comply with the court's decision was prepared 
and filed with the Environmental Protection Agency in 
March 1981. The recommended plan of improvement 
consists of the multipurpose lake, 0.9 mile of levee, and 
the acquisition of 25,500 acres of wildlife mitigation 
lands. All remaining channel and levee work was 
deleted from the recommended plan. The Supplemental 
EIS was filed with the court in July 1981 and numerous 
motions, documents, affidavits, and briefs were subsequently 
filed. After the Supplemental EIS was filed in 
July 1981, numerous motions, documents, affidavits, 
30-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
and briefs were filed through October 1982. On 
December 30, 1982, the U.S. District Court issued a 
95-page order continuing the permanent injunction. On 
March 22, 1983, the order was revised and Judge 
William Wayne Justice issued an Amended Memorandum 
Opinion and a Permanent Injunction against the 
construction of Cooper Lake. The Government filed a 
Notice of Appeal with the court in May 1983. On July 
16, 1984, litigation was resolved and the injunction was 
released. The project was transferred to the Fort Worth 
District at the end of FY 1979. Public Law 101-101, 
H.R. 101-235, approved September 29, 1989, authorized 
$5 million for additional recreation. Estimated Federal 
cost (Oct. 1, 1989 base price) is $134,400,000, non- 
Federal cost for land for the levees is $227,000 and in 
addition $51,200,000 is to be reimbursed by water 
supply users over a 50-year period. 
Local cooperation. Except for Cooper Lake, local 
interest must furnish lands and rights-of-way and alter 
and relocate highways and related facilities and 
utilities, except railroads, for construction; hold and 
save the United States free from damages; maintain 
and operate all works after completion, and preserve 
channel capacities by preventing encroachment. Local 
agencies furnished rights-of-way for the first two 
phases of work on the levees and channel downstream 
from Cooper Dam. Rights-of-way acquisition for the 
second phase was also essentially complete when 
construction was halted. 
Assuring agencies are the following counties in 
Texas: Franklin, Hopkins, Titus, and Red River. Basic 
assurances have been received. 
Operations during fiscal year. Contract awarded 
during FY 1989 include the following: Fencing Part III, 
awarded 25 April 1989. Through FY 1989 the following 
is approximately complete: Levees and Channels, 98 
percent; Real Estate, 66 percent; Embankments, Spillway 
and Outlets, 30 percent. Land Acquisition and 
Engineering and Design continues. Deliberate Impoundment 
is scheduled for September 1991 and 
project completion is scheduled June 1994. 
9. FERRELLS BRIDGE DAMLAKE 
O' THE PINES, TX 
Location. Dam is on Cypress Creek in Marion, 
Harrison, Upshur, Morris, Camp, and Titus Counties, 
Texas, 8 miles west of Jefferson, Texas. 
Existing project. An earth-fill dam 10,600 feet 
long and 77 feet high includes a 200-foot spillway with 
a capacity of 68,200 cubic feet per second. Reservoir 
controls runoff from 850 square miles of drainage area, 
and has a gross storage capacity of 842,100 acre-feet, 
including 587,200 acre-feet flood control storage, 3,800 
acre-feet conservation storage, and 251,000 acre-feet for 
municipal and industrial water supply. Reservoir 
extends 28 miles upstream. Project affords substantial 
flood protection of Cypress Creek Valley from damsite 
to confluence with Red River and, together with 
operation of other reservoirs proposed in Red River 
Basin, will provide flood protection along main stem of 
Red River below Denison Dam. Construction commenced 
in January 1955 and was completed June 1960. 
Estimated Federal cost of project is $17,231,700 (Oct. 1, 
1983, base price), including $4,349,200 for Code 711 and 
$399,739 accelerated Public Works fund. This project 
transferred to the Fort Worth District as of the end of 
FY 1979. 
Local cooperation. None required. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Ferrells Bridge Dam-Lake O' 
The Pines project: Accumulated flood damages prevented 
through FY 1989 were $6,636,600. 
10. GRAND PRAIRIE, TX, STREAMBANK 
EROSION AT MEYERS 
ROAD 
Location. The project is located at a bend of the 
West Fork of the Trinity River approximately 6.1 miles 
upstream of the confluence of the West Fork and Elm 
Fork of the Trinity River. This bend in the river is 
adjacent to Meyers Road which lies within Dallas 
County and is located in northeast Grand Prairie. More 
specifically, Meyers Road is north of Interstate Highway 
30 and west of the city's sanitary landfill. 
Existing project. For description of completed 
improvements and authorizing acts see Annual Report 
for 1985. Construction was started in January 1984 and 
completed in 1985. The total Federal and non-Federal 
estimated cost of the project is $300,000. 
Local cooperation. In accordance with Section 14 
of the Flood Control Act of 1946 as amended, the city of 
Grand Prairie is required to assume full responsibility 
for all project costs in excess of the Federal cost 
limitation of $250,000. In addition, the city is required 
to provide without cost to the United States, all lands, 
easements, and rights-of-way necessary for construction 
and maintenance; bear the cost of all alteration and 
relocations of utilities, storm drains, roads, highway 
bridges, and community services; hold and save the 
United States free from damages due to construction 
work; operate and maintain all works after completion 
and prevent any obstruction or encroachment that 
would reduce the flow capacity of the project; publicize 
and notify all interested parties that the project will 
not provide protection from the occurrence of storms 
greater than the project design flood; comply with 
Public Law 91-646, approved January 2, 1971, and with 
the requirements of Section 221, Public Law 91-611, 
approved December 31, 1970, as amended. 
11. GRAPEVINE LAKE, TX 
Location. Dam is in Tarrant County, Texas, on 
Denton Creek, 11.7 river miles upstream from its 
confluence with Elm Fork of Trinity River and about 
20 miles northwest of City of Dallas, Texas. 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1962. Construction of project was started December 
1947 and ready for beneficial use in July 1952. 
30-6

FORT WORTH, TEXAS DISTRICT 
Estimated cost of project is $18,896,000, including 
$2,040,000 contributed by local interests. 
Local cooperation. A contract with Dallas County 
Park Cities Water Control and Improvement District 
No. 2 for 50,000 acre-feet of water supply storage was 
approved by Secretary of the Army on March 21, 1955. 
Park Cities paid the required $607,000. A contract with 
City of Dallas for 85,000 acre-feet of water supply 
storage was approved by Secretary of the Army on 
March 17, 1954. Dallas paid the required $1,433,026. A 
contract with City of Grapevine, Texas, for 1,250 
acre-feet of water supply storage was approved by 
Secretary of the Army on September 14, 1953, at an 
estimated cost of $22,654. A contract for Interim Use of 
Navigation Storage with city of Grapevine was approved 
by Secretary of the Army on February 27, 1981, 
at an estimated cost of $684,000. To date, $117,411 has 
been paid. Above contracts include payment of operation 
and maintenance costs as follows: Dallas County 
Park Cities Water Control and Improvement District 
No. 2, a pro rata part of the actual annual cost, which 
part is to be not less than $2,000 nor more than $3,000; 
Dallas, 9.2 percent of actual annual cost; and Grapevine, 
its pro rata part of actual annual cost (estimated 
at $79.55 annually and included in total annual 
payment). Following operation and maintenance payments 
have been made: Park Cities $109,231, Dallas 
$535,002, and Grapevine $145,434. 
Operations during fiscal year. A contract for 
modification of Embankment and Spillway was 
awarded September 30, 1983 and continues. The 
proposed plan of improvement provides for spillway 
modification by construction of spillway chute and 
stilling basin and a berm on the downstream side of the 
main embankment and completion in FY 1987. Recreation 
facilities under Code 710 remain. 
Benefits accrued to system comprised of Lewisville 
Lake, Grapevine Lake and Dallas Floodway: Accumulated 
flood damages prevented through FY 1989 were 
$964,580,100. 
12. HORDS CREEK LAKE, TX 
Location. On Hords Creek, a tributary of Pecan 
Bayou, about 13.5 miles west of Coleman, Texas, and 
about 27.8 miles upstream from mouth of Hords Creek. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Construction of project was started January 
1947 and completed for beneficial use in April 1948. 
Estimated cost of project is $4,337,000 including 
$105,000 contributed by local interests. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Hords Creek project: Accumulated 
flood damages prevented through FY 1989 were 
$937,200. 
13. JOE POOL LAKE, TX 
Location. Dam site is located at River Mile 11.2 on 
Mountain Creek, a right bank tributary of the West 
Fork of the Trinity River, and is adjacent to the city 
limits of Grand Prairie, Dallas County, Texas, which is 
one of the rapid growing cities in the Dallas-Fort Worth 
Metropolitan area. 
Existing project. The project provides for construction 
of an earthfill dam with a maximum height of 
108.5 feet above the streambed and a total length of 
22,360 feet, including 50-foot type spillway, which will 
control 232 square miles of drainage area. The 
reservoir will have a total controlled storage of 304,000 
acre-feet and a water surface area of 10,940 acres at the 
top of the flood control pool and 7,470 acres at the top 
of the conservation pool. The total storage includes 
123,100 acre-feet for flood control, 142,900 acre-feet for 
conservation and 38,000 acre-feet for sediment reserve. 
Estimated cost of the project is $198,900,000 (Oct. 1, 
1989, base price) including $10,600,000 non-Federal 
first cost. Project is a unit in the general comprehensive 
plan for development and control of the water 
resources of the Trinity River Basin. 
Local cooperation. The Water Supply Act of 1958 
as amended, and the Federal Water Project Recreation 
Act of 1965 apply. Contracts for water supply storage 
and recreation with the Trinity River Authority were 
approved by the Acting Secretary of the Army, June 
15, 1977. The recreation contract with Trinity Valley 
Authority was modified March 28, 1979, to allow the 
Corps to participate with the State of Texas and 
approved by the Assistant Secretary of the Army 
March 21, 1980. Recreation development contract with 
the State of Texas was approved by the Assistant 
Secretary of the Army March 21, 1980. Reimbursement 
is currently estimated at $48,600,000 for water supply 
and $19,400,000 for recreation (excluding future recreation 
facilities) for a total of $68,000,000 exclusive of 
interest. To date $35,503 has been paid. Of the actual 
annual cost of operation and maintenance, $464 has 
been paid. 
Operations during fiscal year. The project has 
been under construction since FY 1975 and through FY 
1989 is approximately ,99 percent complete overall. 
Contracts awarded during FY 1989 included the 
following: Embankment Skinslide Repair, awarded 
February 15, 1989; Stabilization and Restoration of 
Penn Site, awarded May 25, 1989. Deliberate Impoundment 
was January 1986. Project completion is scheduled 
for May 1993. Land Acquisition and Engineering 
and Design continue. Public Law 97-400, H.R. 7377, 
97th Congress, effective December 31, 1982, changed 
the name of Lakeview Lake to Joe Pool Lake. Benefits 
accrued to Joe Pool Lake project: Accumulated flood 
damages prevented through FY 1989 were $3,086,100. 
14. LAVON LAKE, TX 
Location. Dam is in Collin County, Texas, on East 
Fork of Trinity River 55.9 miles above its confluence 
with Trinity River and about 22 miles northeast of 
Dallas, Texas. 
30-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Construction of project was started January 
1948 and ready for beneficial use in September 1953. 
Project is complete. See following section for Lavon 
Lake Modification and East Fork Channel Improvement 
authorized by Flood Control Act of 1962. 
Estimated cost of project is $15,470,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with North Texas Municipal 
Water District for water supply storage, including cost 
of intake structure, was approved by Secretary of the 
Army July 8, 1954, at an estimated cost of $1,405,753. 
Contract was revised in 1973 and final revised contract 
amount is $1,445,261.67. To date North Texas Municipal 
Water District has paid $2,654,348. Under the 
contract North Texas Municipal Water District must 
pay annually 13.6 percent of actual annual cost of 
operation and maintenance, and to date has paid 
$640,785. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Lavon project: Accumulated 
flood damages prevented through FY 1989 were 
$96,677,100. 
15. LAVON LAKE MODIFICATION 
AND EAST FORK CHANNEL 
IMPROVEMENT, TX 
Location. Existing dam is in Collin County, Texas, 
on East Fork of Trinity River, 55.9 miles above its 
confluence with Trinity River and about 22.0 miles 
northeast of Dallas, Texas. Channel improvement of 
East Fork extends from its mouth to River Mile 31.8. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1988. Construction of project was initiated in May 
1970 and ready for beneficial use in December 1975. 
Estimated Federal cost of the modification and improvement 
is $69,750,000 and $220,000 local interests, 
a total of $69,970,000. Project is complete. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs allocated to 
increased water supply storage under the terms of the 
Water Supply Act of 1958. The North Texas Municipal 
Water District has contracted for 43 percent of the 
water supply (approved September 22, 1967, by the 
Secretary of the Army) and to date $2,997,006 has been 
paid. North Texas Municipal Water Supply District has 
submitted assurance to contract for 57 percent of 
future water supply. Reimbursement is currently 
estimated at $37,787,324. 
Levee Districts 4 and 5, which comprise the lower 
10 miles of the East Fork Channel, entered into 
agreements as required by Section 221 of the Flood 
Control Act of 1970 on January 28, 1972 and have 
furnished all necessary construction easements. 
Levee Districts 6, 8, 10, 13, and 15, which comprise 
the upper 15 miles of the East Fork Channel, have 
declined to provide the necessary assurances. On 
December 8, 1972, this portion of the project was 
reclassified from "active" to "inactive" category. 
Operations during fiscal year. Improvement of 
the lower ten miles of the East Fork Channel and 
Levees and total project are 100 percent complete. 
16. LEWISVILLE DAM, TX 
Location. Dam is in Denton County, Texas, on Elm 
Fork of Trinity River 30 river miles above its 
confluence with Trinity River and about 22 miles 
northwest of City of Dallas, Texas at a site downstream 
from old Garza Dam. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Construction of project was started November 
1948 and ready for beneficial use in November 1954. 
Estimated cost of project is $25,902,000, including 
$3,677,000 contributed by local interests. 
Local cooperation. A contract with City of Dallas 
for 415,000 acre-feet of water supply storage land rights 
and interests to Garza Dam and Reservoir was 
approved by the Secretary of the Army on July 16, 
1953. Local contributions have been made in full. A 
contract with city of Denton, Texas, for remaining 
21,000 acre-feet of water supply storage was approved 
by the Secretary of the Army on May 20, 1954, with an 
estimated cost of $250,064. Local contributions have 
been paid in full. Under above contracts, cities of 
Dallas and Denison must pay annually 21.9 and 1 
percent, respectively, of actual annual cost of operation 
and maintenance. To date Dallas has paid $3,121,543 
and Denison $135,178. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to system comprised of Lewisville 
Lake, Grapevine Lake, and Dallas Floodway: Accumulated 
flood damages prevented through FY 1989 were 
$964,580,100. 
17. NAVARRO MILLS LAKE, TX 
Location. Dam is in Navarro County, Texas, at 
River Mile 63.9 on Richland Creek, a tributary of 
Trinity River, about 16.0 miles southwest of Corsicana, 
Texas. 
Existing project. For description of completed 
improvement and authorization acts see Annual Report 
for 1965. Construction started December 1959 and 
project completed for beneficial use March 1963. 
Estimated cost of project is $13,154,000, including 
$300,000 contributed by local interests. 
Local cooperation. The Water Supply Act of 1958, 
as amended applies. A formal contract with the Trinity 
River Authority was approved March 3, 1966, by the 
Secretary of the Army at an estimated cost of 
$2,260,800. To date the Authority has paid $855,612 for 
water supply and $882,568 for operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
30-8

FORT WORTH, TEXAS DISTRICT 
Benefits accrued to Navarro Mills project: Accumulated 
flood damages prevented through FY 1989 were 
$27,837,900. 
18. O.C. FISHER DAM AND LAKE, TX 
Location. Dam is on North Concho River, a 
tributary of Concho River, about 6.6 miles above mouth 
of North Concho River near city of San Angelo, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Name was changed from San Angelo Dam and 
Reservoir to O.C. Fisher Dam and Lake January 3, 
1975 by Public Law 93-634. Construction of project was 
started May 1947 and ready for beneficial use February 
1952. Estimated cost of project is $17,111,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A water-supply contract with Upper 
Colorado River Authority for water-supply storage in 
reservoir was approved by Secretary of the Army on 
October 11, 1948. The Authority has contributed 
$860,444 toward cost of project and $64,336 toward 
operation and maintenance for a 50-year period. The 
Authority must pay additional contributions of $1 a 
year for useful life of project, beginning January 1, 
1965. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to O.C. Fisher Dam and Lake 
project: Accumulated flood damages prevented through 
FY 1989 were $2,375,600. 
19. PROCTOR LAKE, TX 
Location. Dam is at River Mile 238.9 on Leon 
River, a tributary of Brazos River, about 8.0 miles 
northeast of Comanche in Comanche County, Texas. 
Existing project. For description of completed 
improvement and authorization act see Annual Report 
of 1969. Construction of project was started July 1960 
and completed for beneficial use 1963. Estimated cost of 
project is $16,249,000. 
Local cooperation. The Water Supply Act of 1958 
applies. A formal contract with the Brazos River 
Authority, a State agency, was approved by Secretary 
of the Army, July 1, 1960, and was modified and 
approved May 9, 1966, at an estimated cost of 
$1,707,900. To date the Authority has paid $390,024 for 
water supply and $344,000 for operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance were continued. Recreation facilities 
under Code 710 remain. 
Benefits accrued to Proctor project: Accumulated 
flood damages prevented through FY 1989 were 
$9,300,800. 
20. RAY ROBERTS LAKE, TX 
Location. Damsite is located at River Mile 60.0 on 
the Elm Fork of the Trinity River, Denton County, 
between Sanger and Aubrey, Texas and 30 miles 
upstream from Lewisville Dam. 
Existing project. The plan of improvement provides 
for construction of an earthfilled dam with a 
maximum height of 141 feet above the streambed, a 
length of 15,250 feet including an uncontrolled 
broadcrested spillway 100 feet long, controlling 682 
square miles of drainage area. The lake will have a 
total controlled storage of 1,064,600 acre-feet, with a 
water surface area of 36,900 acres. The total storage 
includes 260,800 acre-feet for flood control, 749,200 
acre-feet for water supply, and 54,600 acre-feet for 
sediment reserve. Estimated Federal cost of the project 
is $291,000,000 (Oct. 1, 1989, base price). Public Law 
96-384, 96th Congress, H.R. 8094, effective January 4, 
1981, changed the name of Aubrey Lake to Ray Roberts 
Lake. 
Local cooperation. The Water Supply Act of 1958 
as amended and the Federal Water Project Recreation 
Act of 1965 and Section 221, Flood Control Act of 1970 
apply. Contracts with the cities of Dallas and Denton, 
Texas, for water supply storage and recreation were 
approved by the Secretary of the Army September 16, 
1980. To date the city of Dallas has paid $3,878,934 and 
the city of Denton has paid $1,362,867 toward principal. 
Dallas has paid $35,441 and Denton has paid $12,452 
toward annual cost of operation and maintenance of 
project. 
Operations during fiscal year. The project is 
about 89 percent complete overall. Acquisition of real 
estate continues. FY 1989 funds were used to award the 
following contracts: Alternative Recreation Facilities, 
Part III, awarded May 12, 1989; Boundary Delineation 
Part VII, awarded April 14, 1989; Recreation Facilities 
Part II and Part III, awarded July 17, 1989. Engineering 
and Design continues. Deliberate Impoundment 
was June 30, 1987. Project completion is scheduled for 
June 1992. At the request of the City of Denton and the 
approval of the Secretary of the Army, the penstock 
was added to the embankment as a minimum facility 
for future hydropower. 
21. SAN ANTONIO CHANNEL 
IMPROVEMENT, TX 
Location. Floodway is in city of San Antonio, 
Bexar County, Texas, on San Antonio River and San 
Pedro, Apache, Alazan, Martinez Creeks, and Espada 
Aqueduct located in vicinity of Six Mile Creek. 
Existing project. The project consists of 34.9 miles 
of channel and associated improvements on six separate 
streams of which about 84 percent has been 
completed. Completion of detailed engineering and 
design studies revealed that the least costly alternative 
for the remaining channel improvements would consist 
of two tunnels. The San Pedro Creek tunnel would be 
6,040 feet in length and the San Antonio River tunnel 
would be 16,360 feet in length, and construction and 
alteration of railroad bridges. Estimated Federal cost of 
these modifications is $114,000,000 (Oct. 1, 1989, base 
price), and estimated cost to local interests is 
$93,000,000 which includes $3,000,000 cash contributions 
and $90,000,000 for lands, damages, and construction, 
a total of $207,000,000. Existing project was 
30-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
authorized by 1954 Flood Control Act. The Water 
Resources Act of 1976 added authorization to the 
existing project for construction of flood control 
measures needed to preserve and protect the Espada 
Aqueduct located in the vicinity of Six Mile Creek. 
Construction was started in October 1957 and the 
project is about 84 percent complete. Project completion 
is scheduled for July 1992. 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction, including 
purchase and removal of buildings, relocation or 
reconstruction of bridges (exclusive of railway bridges), 
channel dams where applicable, and utility lines; hold 
the United States free from damages; maintain and 
operate all works after completion; and provide a cash 
contribution for enhancement benefits of 2.65 percent 
of actual Federal construction cost. San Antonio River 
Authority furnished assurances that it will comply 
with all requirements of local cooperation. These 
assurances were accepted by the District Engineer on 
April 15, 1957. To date $1,764,210 has been contributed 
by San Antonio River Authority. In addition, $30,000 
has been contributed and accepted, under the authority 
of Civil Functions Appropriations Act of 1958, for 
vehicular crossings over the San Antonio Channel. 
Operations during fiscal year. FY 1989 funds 
were used to continue construction and engineering 
and design studies. 
Benefits accrued to San Antonio project: Accumulated 
damages prevented through FY 1989 were 
$117,514,900. 
22. SAN GABRIEL RIVER, TX 
Location. Project is a system of three reservoirs in 
Williamson County in the central portion of Brazos 
River Basin, which consists of Granger Dam at River 
Mile 31.9 on San Gabriel River, about 7.0 miles east of 
Granger, Texas; North San Gabriel Dam at River Mile 
4.3 on North Fork of San Gabriel River, about 3.5 miles 
northwest of Georgetown, Texas; and South Fork Dam 
at River Mile 4.7 on South Fork of San Gabriel River, 
about 3.0 miles southwest of Georgetown, Texas. 
Existing project. Granger Lake was authorized by 
1954 Flood Control Act, and North (North San Gabriel 
Dam and Lake Georgetown) and South Fork Lakes 
were authorized by 1962 Flood Control Act. Estimated 
total Federal cost of project is $181,400,000 (Oct 1, 1986, 
base price) and estimated non-Federal cost of 
$90,600,000 for a project total of $272,000,000. Plan of 
improvement provides for the following: Granger: An 
earthfilled dam 16,320 feet long, including spillway 
with maximum height of 115 feet above streambed, 
which controls 709 square miles of drainage area. 
Reservoir provides a total storage capacity of 244,200 
acre-feet, of which 162,200 acre-feet are for flood 
control, 37,900 acre-feet for water supply storage, and 
44,100 acre-feet for sediment reserve. Estimated cost of 
project is $62,062,000. North San Gabriel Dam: A 
rockfill dam 6,700 feet long, including spillway with 
maximum height of 164 feet above streambed, which 
controls 246 square miles of drainage area. Reservoir 
provides a total storage capacity of 130,800 acre-feet of 
which 87,600 acre-feet are for flood control, 29,200 
acre-feet for water supply storage, and 14,000 acre-feet 
for sediment reserve. Estimated cost of project is 
$38,765,000. South Fork: A rockfill dam 5,620 feet long, 
including spillway with maximum height of 152 feet 
above streambed, which controls 123 square miles of 
drainage area. Reservoir provides a total storage 
capacity of 82,600 acre-feet (45,700 for flood control, 
28,900 for water supply storage, and 8,000 for sediment 
reserve). Estimated cost of project is $171,173,000. 
Public Law 96-575, 96th Congress, H.R. 4941 effective 
January 4, 1981, changed the name of North Fork Lake 
to North San Gabriel Dam and Lake Georgetown. 
Local cooperation. Construction is subject to 
condition that local interests reimburse the Federal 
Government for costs allocated to water supply at 
Granger, Lake Georgetown, and South Fork Lakes. 
Reimbursement currently estimated at $13,315,000 for 
Granger, $6,295,000 for Lake Georgetown, and 
$50,563,000 for South Fork, for a total of $70,172,000 
exclusive of interest. Brazos River Authority, a State 
agency, is the local interests' sponsor of project, and by 
letter dated April 18, 1966, indicated its acceptance of 
the proposed plan of development and its willingness to 
pay for the costs allocated to water supply in each 
reservoir in the ultimate plan. Such water supply 
assurances for Granger and Lake Georgetown Lakes 
were approved May 24, 1968 as satisfactory in accordance 
with requirements of the Water Supply Act of 
1958, as amended. Contract negotiations for South Fork 
Lake will be deferred until the need for water supply 
develops and the reservoir is scheduled for construction.
Operations during fiscal year. Through 1983 all 
work has been completed. Deliberate impoundment of 
water commenced at Granger and Lake Georgetown 
Lakes on January 21, 1980 and March 3, 1980, 
respectively. In FY 1982, studies on South Fork Lake 
were resumed in preparation of General Design 
Memorandum to provide reaffirmation prior to construction. 
A Draft Reevaluation Report on South Fork 
Lake was submitted to headquarters in October 1986. 
The report recommended no Federal action and defer 
further studies indefinitely. Future water supply needs 
of the area would be addressed by reallocating storage 
at Granger Lake. The South Fork Lake project was 
placed on inactive status and would be eligible for 
deauthorization in FY 1997 if no funds are obligated by 
then. 
Benefits accrued to project consisting of Granger 
and Lake Georgetown: Accumulated flood damages 
prevented through FY 1989 were $19,094,400. 
23. SOMERVILLE LAKE, TX 
Location. Dam is on Yegua Creek 20 miles 
upstream from its confluence with Brazos River and 
about 2 miles south of Somerville, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report 
of 1969. Construction started in June 1962 and project 
30-10

FORT WORTH, TEXAS DISTRICT 
was ready for beneficial use in January 1967. Estimated 
cost of project is $30,227,000. 
Local cooperation. The Water Supply Act of 1958, 
as amended, applies. A contract with the Brazos River 
Authority, a State agency, for water supply storage 
approved May 10, 1962, by the Secretary of the Army, 
has paid $1,348,117 to date. Also under the contract, 
the authority must pay annually 28.655 percent of the 
actual annual cost of operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Somerville project: Accumulated 
flood damages prevented through FY 1989 were 
$32,976,900. 
24. STILLHOUSE HOLLOW DAM, TX 
Location. Dam is on Lampasas River 16 miles 
upstream from its confluence with Little River, a 
tributary of the Brazos River, and about 5 miles 
southwest of Belton, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report 
of 1969. Construction was initiated in July 1962 and 
the project was ready for beneficial use in February 
1968. Estimated cost of project is $23,670,000. 
Local cooperation. The Water Supply Act of 1958 
applies. A contract with the Brazos River Authority, a 
State agency, for water supply storage was approved 
April 13, 1962, by the Secretary of the Army, at an 
estimated cost of $6,912,430. To date the Authority has 
paid $1,664,692. Also under the contract the Authority 
must pay annually 27.748 percent of the actual annual 
cost of operation and maintenance. To date the 
Authority has paid $718,917. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Stillhouse Hollow Project: 
Accumulated estimate of flood damages prevented 
through FY 1989 is $28,027,300. 
25. WACO LAKE, TX 
Location. Dam is on Bosque River, 4.6 river miles 
above its confluence with Brazos River, at City of Waco, 
McLennan County, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report 
of 1969. Estimated cost of project is $50,853,000 
including $250,000 contributed by local interests and 
$2,500,000 other non-Federal cost. Construction was 
started in July 1958, and project was ready for 
beneficial use in February 1965. 
Local cooperation. Section G of the Flood Control 
Act of December 1944 applies. A contract with the 
Brazos River Authority, a State agency, for water 
supply storage and the contract with the City of Waco 
transferring the existing Lake Waco to the Government 
for their water storage, was approved by the 
Secretary of the Army on April 15, 1958. To date, the 
Authority for their portion of the water supply storage 
has paid $1,904,735. Also under the contract the 
Authority and the City must pay 14.706 and 2.087 
percent respectively of the actual cost of operation and 
maintenance. To date the Authority has paid $902,247 
and the City has paid $140,818. A contract with the 
Brazos River Authority, for additional storage for 
municipal and industrial water supply, was approved 
by the Acting Assistant Secretary of the Army, 
September 28, 1984. 
Operations during fiscal year. Routine operations 
and maintenance continued. Recreation facilities 
under Code 710 remain. 
Benefits accrued to Waco project: Accumulated 
flood damages prevented through FY 1989 were 
$66,633,100. 
26. WRIGHT PATMAN DAM AND 
LAKE, TX 
Location. Dam is on Sulphur River in Cass and 
Bowie Counties, Texas. Dam is 45 miles above mouth of 
Sulphur River, and about 8 miles southwest of 
Texarkana, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report 
of 1984. Estimated cost of project is $51,945,000 which 
includes $5,449,100 Code 711, $399,939 accelerated 
public works funds, and $13,138,004 to be reimbursed 
by local interests, over a period not to exceed 50 years, 
for water supply storage, and including $2,092,040 for 
pro rata share of original reservoir cost. Construction 
was initiated in August 1948 and completed in March 
1962, except real estate activities, construction under 
Code 711, and conversion of 120,000 acre-feet to water 
supply storage after completion of Cooper Reservoir. 
This project transferred to the Fort Worth District as of 
the end of FY 1979. 
Local cooperation. A contract with the city of 
Texarkana, Texas, for reserving water supply storage 
space was approved by the Secretary of the Army 
December 17, 1968. To date, the City has paid $488,614. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Wright Patman project: Accumulated 
flood damages prevented through FY 1989 
were $13,859,400. 
27. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed local flood protection 
projects is made periodically in compliance with 
Section 208.10, of Title 33, Code of Federal Regulations, 
which contains regulations for operation and maintenance 
of local flood-protection works approved by 
Secretary of the Army in accordance with authority in 
Section 3, Flood Control Act of June 22, 1936. See Table 
30-D for inspections made this fiscal year. 
Inspection costs for FY from regular funds for 
maintenance were $42,053. Total costs to September 30, 
1989 were $815,945. 
30-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
28. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with Flood Control Act of 1944, 
expenditures were made for scheduling flood control 
reservoir operations and preparation of reservoir 
regulation manual for Marshall Ford Dam, on the 
Colorado River, near City of Austin, Texas, and for 
preparation of reservoir regulation manual for Twin 
Buttes Dam, on Middle and South Concho Rivers near 
City of San Angelo, Texas. Marshall Ford Dam was 
authorized by 1937 River and Harbor Act. Project was 
constructed jointly by Bureau of Reclamation and 
Lower Colorado River Authority and was completed 
during FY 1942. Twin Buttes Reservoir was authorized 
for construction by Department of Interior by Public 
Law 152, 85th Congress. Construction was initiated in 
June 1960; closure of dam started in June 1962; 
deliberate impoundment was started January 23, 1963. 
Accumulated damages prevented by Marshall Ford 
Reservoir through FY 1989 were $191,937,800 and by 
Twin Buttes through FY 1989 were $418,000. Twin 
Buttes Reservoir consists of two separate pools, one on 
South Concho River and the other on Middle Concho 
River and Spring Creek. Equalizing channel between 
these two pools is at elevation 1925.0. Costs for fiscal 
year from regular funds for operation of both reservoirs 
were $109,395. 
29. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 30-C.) 
30. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
(See Table 30-E.) 
Flood control activities pursuant to Section 205, 
Public Law 585, 80th Congress, as amended (preauthorization); 
emergency streambank protection under 
Section 14, Public Law 526, 79th Congress, as amended. 
Emergency flood control, hurricane-flood, and 
shore protection activities (Public Law 99, 84th Congress, 
and antecedent legislation). 
Fiscal year costs were $206,257 for disaster preparedness; 
no levee repair. 
Multi-Purpose Projects Including Power 
31. ROBERT DOUGLAS WILLIS 
HYDROPOWER, TX 
Location. For location of completed dam see Town 
Bluff Dam-B.A. Steinhagen Lake, Texas in this chapter. 
Existing project. Installation of hydroelectric 
power generating facilities at Town Bluff Dam was 
authorized by the River and Harbor Act of 1945 (Public 
Law 79-14), March 2, 1945, but deferred in the original 
construction. Town Bluff Dam was completed and 
placed in operation in 1951. A Design Analysis Report 
completed in April 1982 and a Feasibility Report was 
approved September 9, 1983 indicated that installing 
hydropower at this project is now economically feasible. 
The hydropower facilities will include a 6,000 kilowatt 
power plan (two units at 3,000 kilowatts each), intake 
and outlet facilities, and necessary switchgear equipment 
to be located in the main embankment at the old 
diversion channel and will be operated remotely from 
the Sam Rayburn project. The installation and operation 
of hydropower facilities will not result in the 
altering of the existing operation at Town Bluff. The 
project will produce an estimated 35,900 megawatt 
hours of energy per year. There is no Federal cost on 
this project. It is completely funded by non-Federal 
funds. The estimated non-Federal cost is $18,900,000. 
101st Congress House Report 923, effective February 7, 
1989, changed the name of Town Bluff Hydropower to 
Robert Douglas Willis Hydropower. 
Local cooperation. A contract with the Sam 
Rayburn Municipal Power Authority was approved by 
Secretary of the Army, June 28, 1985, relative to 
financing, escrow agreement, and power sales agreement. 
Operation during fiscal year. Plans and specifications 
were completed and construction on the 
turbine-generator was initiated in FY 1986. Construction 
on the powerhouse was initiated in FY 1987. 
Project completion date is scheduled for 1990. 
32. SAM RAYBURN DAM AND 
RESERVOIR, TX 
Location. Dam is on Angelina River 25.2 miles 
upstream from its confluence with Neches River and 
about 10.0 miles northwest of Jasper, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report 
1969. Construction was started August 1956 and project 
was ready for beneficial use in March 1965. Estimated 
cost of project is $68,683,000 including $3,000,000 
contributed by local interests. 
Local cooperation. A contract with the Lower 
Neches Valley Authority, a State agency, to contribute 
$3,000,000 toward the first cost and an additional 
$200,000 annually for 50 years after completion of the 
project was approved by the Secretary of the Army on 
January 22, 1957: Contribution of $3,000,000 was made 
in full and annual payments to date of $4,000,000 have 
been made by the Authority. 
A contract with the City of Lufkin for water supply 
storage was approved May 27, 1969 by the Secretary of 
the Army at an estimated cost of $525,600. To date the 
City has paid $143,830. Also under the contract the 
City of Lufkin must pay annually 0.692 percent of the 
annual cost of operation and maintenance. To date the 
City has paid $131,217. 
Operations during fiscal year. Continued routine 
operation and maintenance. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Sam Rayburn project: Accumulated 
flood damages prevented through FY 1989 were 
$208,792,200. 
30-12

FORT WORTH, TEXAS DISTRICT 
33. TOWN BLUFF DAMB.
A. STEINHAGEN LAKE, TX 
Location. Dam is on Neches River about 12.4 miles 
below mouth of Angelina River, one-half mile north of 
Town Bluff, Texas, and 93.0 river miles north of 
Beaumont, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Construction started March 1947 and project 
was ready for beneficial use in April 1951. Estimated 
cost of project is $9,888,000, including $2,000,000 
contribution by local interests. 
Local cooperation. Completed as required. 
Operations during fiscal year. Routine operation 
and maintenance continued. Recreation facilities under 
Code 710 remain. 
34. WHITNEY LAKE, TX 
Location. Dam is on Brazos River, about 442 miles 
above mouth of river, 5.5 miles southwest of Whitney, 
Texas, and about 38 miles upstream from City of Waco, 
Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report 
for 1962. Construction of project was started June 1946 
and ready for flood control use in December 1951. First 
power was placed on-the-line in June 1953. Raise power 
pool is complete. Estimated cost of project is 
$46,306,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with the Brazos River 
Authority, a State agency, for water supply storage was 
approved by the Secretary of the Army November 3, 
1982. To date, the authority has paid $235,251. 
Operations during fiscal year. Continued routine 
operation and maintenance. Recreation facilities under 
Code 710 remain. 
Benefits accrued to Whitney project: Accumulated 
flood damages prevented through FY 1989 were 
$160,030,900. 
General Investigations 
35. SURVEYS 
Fiscal year costs were $1,062,950 for flood damage 
prevention studies; $84,192 for coordination with other 
agencies; $78,777 for review of authorized projects; 
$77,832 for miscellaneous activities; and $0 for 
preauthorization studies Phase I for a total of 
$1,225,919. 
36. COLLECTION AND STUDY OF 
BASIC DATA 
Work was continued under the Flood Plain Management 
Services on the compilation of information on 
floods and potential flood damages, including identification 
of those areas subject to inundation. Fiscal year 
expenditures for these activities totaled $320,519. 
Fiscal year costs were $18,468 for hydrologic studies. 
30-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
This page intentionally left blank. 
30-14

FORT WORTH, TEXAS DISTRICT 
TABLE 30-A 
See 
Section 
in Text Project 
1. Trinity River Project, TX 
Includes Channel to 
Liberty, Tennessee 
Colony Lake, and Dallas 
Floodway Extension 
2. Aquilla Lake, TX 
3. Bardwell Lake, TX 
4. Belton Lake, TX 
5. Benbrook Lake, TX 
6. Boggy Creek, TX 
(Federal Costs) 
(Contributed Funds) 
7. Canyon Lake, TX 
8. Cooper Lake and 
Channels, TX 
(Contributed Funds) 
9. Ferrells Bridge Dam 
Lake O' The Pines, TX 
10. Grand Prairie, TX 
Meyers Road 
(Contributed Funds) 
11. Grapevine Lake, TX 
COST AND FINANCIAL STATEMENT 
Total Cost To 
Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989'7 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
(-)81,000 275,000 
161,064 235,826 
7,683 
412,000 
400,259 
1,124,800 
1,116,537 
(-)9,000 
(-)2,557 
1,622,600 
1,640,448 
1,112,000 
1,140,186 
295,000 
215,950 
1,087,000 
1,068,610 
3,301,000 
3,181,603 
1,660,200 
1,697,636 
39,227 
- 22,574,865 
- 22,574,865 
- - - 45,506,300 
13,509 1,324 - 45,506,300 
506,300 436,800 532,500 2,601,600 
519,866 441,685 529,579 2,581,648 
- - - 10,934,505 
- - - 10,934,505 
954,122 1,148,400 1,194,800 14,662,20918 
963,614 1,174,518 1,183,423 13,475,18818 
- - - 16,960,549 
- - - 16,960,5491 
1,488,622 1,993,300 1,716,300 20,518,76418 
1,481,234 2,010,129 1,761,276 20,395,28918 
- - - 13,130,463 
- - - 13,069,9912 
1,100,522 1,398,100 1,245,400 20,076,43818 
1,105,422 1,261,787 1,376,992 19,913,58118 
1,045,000 3,100,000 4,205,000 9,370,000 
1,102,585 2,158,645 2,769,539 6,959,521 
16,500 922,968 35,132 974,400 
- 357,601 281,160 638,661 
- - - 19,088,5243 
- - - 19,088,524 
1,094,522 1,266,600 1,186,900 15,245,02618 
1,095,387 1,248,993 1,169,578 14,939,47918 
6,055,000 17,200,000 20,534,000 71,710,000 
6,082,525 8,082,802 24,757,172 66,463,742 
- - - 227 
- - - 227 
- - - 14,175,1974 
- - - 14,175,1975 6 
1,860,122 2,096,400 1,680,700 25,452,05318 
1,854,337 2,077,743 1,721,149 25,434,01118 
- -1,729 - 248,271 
- 223 - 248,271 
- - -40,000 
1,511 (-)9,551 - 
250,000 
462,395 2,801 7,030 6,050 
21,317,790 
21,317,278 
30-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 30-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project 
12. Hords Creek Lake, TX 
13. Joe Pool Lake, TX 
14. Lavon Lake, TX 
15. Lavon Lake Modification 
& East Fork Channel 
Improvement, TX 
16. Lewisville Dam, TX 
17. Navarro Mills Lake, TX 
18. O.C. Fisher Dam and 
Lake, TX 
19. Proctor Lake, TX 
20. Ray Roberts Lake, TX 
31. Robert Douglas Willis 
Hydropower, TX 
(Contributed Funds) 
32. Sam Rayburn Dam and 
Reservoir, TX 
Funding 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989" 
1,450,600 1,571,122 2,001,400 1,912,100 23,857,39018 
1,504,755 1,572,836 1,975,327 1,903,328 23,783,14918 
-- - - 2,731,0898 
1,924 - - - 2,731,089 
928,181 658,300 713,900 769,600 11,374,469 
980,194 650,938 709,692 772,873 11,289,82118 
1,951,000 11,100,000 9,100,000 5,182,000 185,171,000 
7,404,030 5,739,280 8,404,244 10,379,003 183,800,503 
108,000 355,800 448,300 529,900 1,442,000 
105,918 354,030 428,177 532,438 1,420,563 
- - - - 12,864,796 
- - - - 12,864,796 
1,904,600 2,148,322 2,352,400 1,841,300 24,957,64018 
1,945,384 2,152,944 2,327,877 1,850,509 24,885,90018 
- - - - 69,796,862 
- 184 - - 69,796,862 
(-)184,000 - - - 25,333,988 
3,529 - - - 25,333,9889 
2,054,600 3,899,822 2,230,600 2,108,300 33,590,22510 
1,876,603 3,929,412 2,140,815 2,133,211 is
31,044,63010 
18 
- - - - 9,846,759 
- - - - 9,846,75911 
843,000 1,095,422 1,257,900 1,311,800 14,621,80018 
888,742 1,080,767 1,244,267 1,286,746 14,541,94918 
- - - - 16,027,467 
- - - - 16,027,467 
601,000 685,900 1,026,660 867,400 13,034,89018 
603,677 646,518 1,052,790 851,790 12,966,80518 
- - - - 14,469,585 
14,409 - - - 14,469,585 
1,081,000 938,022 1,228,100 1,401,800 14,522,65418 
1,085,535 942,557 1,193,209 1,413,347 14,284,32118 
44,118,000 39,000,000 10,534,000 15,583,000 262,829,700 
46,428,681 33,801,189 13,117,540 13,682,191 256,336,826 
- 36,300 319,500 449,600 805,400 
- 25,754 309,453 456,846 792,053 
1,761,000 4,541,000 8,758,000 3,458,000 18,518,000 
1,313,111 4,417,320 9,229,935 3,385,422 18,345,788 
- - - - 60,670,957 
- - - - 60,670,95612 
30-16

FORT WORTH, TEXAS DISTRICT 
TABLE 30-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 ' 7 
21. San Antonio Channel 
Improvement, TX 
(Federal Funds) 
(Contributed Funds) 
22. San Gabriel River, TX 
Granger 
Lake Georgetown 
23. Somerville Lake, TX 
24. Stillhouse Hollow Dam, 
TX 
33. Town Bluff Dam- 
B.A. Steinhagen Lake, TX 
25. Waco Lake, TX 
34. Whitney Lake, TX 
26. Wright Patman Dam and 
Lake, TX 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,441,6( 
2,455,3E 
2,114,0( 
2,119,8 
191,0( 
181,7E 
1,208,0( 
1,202,6 
964,0( 
980,6 
3,5( 
1,563,6( 
1,586,6(
)0 2,455,322 
88 2,451,539 
)0 10,859,000 
55 5,985,903 
- 353,935 
00 23,000 
84 36,593 
00 834,722 
57 839,763 
)0 1,044,822 
79 1,004,730 
2,724,400 
2,734,448 
17,800,000 
11,285,198 
602,750 
956,685 
2,305,100 
2,288,354 
19,891,000 
17,605,602 
39,603,03618 
39,220,51618 
88,765,048 
74,803,714 
- 1,956,210 
- 1,956,210 
- 101,796,100 
- 101,796,100 
1,220,600 1,116,200 
1,179,792 1,130,161 
1,465,000 
1,485,058 
1,181,000 
1,180,248 
9,298,27818 
9,243,90618 
8,750,55418 
8,717,83018 
- 27,790,438 
- 27,790,436 
2,190,122 2,071,900 1,590,400 
2,183,967 2,030,709 1,637,136 
23,766,35818 
21,232,10718 
- 19,594,97113 
- 20,522,084 
841,000 921,122 1,529,700 1,405,000 
900,650 886,513 1,495,401 1,452,494 
14,105,04818 
14,040,46618 
- - - - 6,602,737 
- - - - 6,602,73714 
859,000 747,400 750,500 1,158,000 14,135,46818 
848,855 757,622 734,887 1,191,374 14,048,84918 
- - - - 49,521,12115 
- - - - 49,521,121 
1,838,800 1,772,722 2,040,625 1,694,700 22,294,10518 
1,891,769 1,800,333 2,019,545 1,681,788 22,141,99818 
- - - - 42,952,938 
- - - - 42,952,93816 
2,484,600 2,428,122 2,686,800 2,717,800 37,280,60218 
2,471,637 2,490,316 2,653,768 2,713,466 36,859,92518 
- - - - 35,731,626 
- - - - 35,731,626 
1,541,600 2,023,322 1,658,402 1,743,100 26,129,51418 
1,534,545 1,945,964 1,731,222 1,751,522 26,070,06418 
1 Excludes $47,309 receipts from reconveyance of 
land deposited to miscellaneous receipts. 
2 Excludes $322,346 receipts from reconveyance of 
land deposited to miscellaneous receipts. 
* Excludes $1,422,848 expended for new work from 
contributed funds, including $22,848 "Contributed Funds 
Other" for installation and operation of gages for leakage 
study. 
4 Includes $1,378,486 for Code 711, $52,808 for Code 
713, and $399,739 accelerated Public Works Act funds. 
Excludes $1,711,200 contributed funds. 
6 Includes $1,376,322 for Code 711, $52,808 for Code 
713, and $399,739 accelerated Public Works Act funds. 
Excludes $4,137 reimbursed in Fiscal Year 1973. 
6 Claim Northeast Texas Municipal Water District 
$16,546. Three payments of $12,410 less real estate charges of 
$1,325, making a total of $2,811 reimbursed in Fiscal Year 
1972, Fiscal Year 1973, and Fiscal Year 1974. 
7 Excludes $146,795 receipts from reconveyance of 
land deposited to miscellaneous receipts, and $2,040,026 for 
new work expended from contributed funds. 
30-17 
68 
3O 
33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 30-A COST AND FINANCIAL STATEMENT 
s Excludes $105,079 expended from contributed 
funds. 
9 Excludes receipts from reconveyance Q A ,,",mC of land of n,, L... L - -,,-.,, - - -1-� , - , - -- -�- �1 1 - �--, --= �-- funds. 
14 Excludes $2,000,000 contributed funds expended. 
15 Excludes $2,750,000 expended for contributed 
426,Ub whicn were aeposited to miscellaneous receipts, and 16 Excludes $188,282 receipts from reconveyance of $3,676,661 for new work expended from contributed funds. 
10 Includes $130,000 under appropriation 96X5125. lands deposited to miscellaneous receipts. 
11 Excludes $300,000 expended from contributed 17 Includes funds provided by the Jobs Act (PL 98-8, 
funds. dated March 24, 1983). 
12 Excludes $3,000,000 expended from contributed 18 Beginning Fiscal Year 1985 data shown on Table 
funds. A includes Special Recreation Use Fees. Data for previous 
13 Includes receipts from disposals and revocation of fiscal years have been changed to conform to the new 
funds related thereto. procedure. 
30-18

FORT WORTH, TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 13, 1968 
Mar. 31, 1960 
Jul. 24, 1946 
Sep. 3, 1954 
Mar. 2, 1945 
Jun. 22, 1936 
Mar. 2, 1945 
Sep. 3, 1954 
8. Aug. 3, 1955 
9. Jul. 24, 1946 
10. Jul. 24, 1946 
11. Mar. 2, 1945 
12. Aug. 18, 1941 
2. S. Doc. 52, 90th Cong., 
1st Sess. 
H. Doc. 424, 82nd Cong., 2nd 
Sess. 
H. Doc. 88, 81st Cong., 
1st Sess. 
H. Doc 535. 81st Cong., 2nd 
Sess. 
H. Doc. 403, 77th Cong., 1st 
Sess. 
Flood Control Act of 1936 
(PL 738) 
AQUILLA LAKE, TX 
Construction of a dam on Aquilla Creek, about 6.8 miles 
southwest of Hillsboro, Texas and about 24 miles north 
of Waco, Texas. 
BARDWELL LAKE, TX 
Construction of a dam on Waxahachie Creek about 5 miles 
south of Ennis, Texas. 
BELTON LAKE, TX 
Construction of a dam on the Leon River about 3 miles 
north of Belton, Texas. 
Modification of the dam to provide for generation of 
hydroelectric power. 
BENBROOK LAKE, TX 
Construction of a dam on the Clear Fork of the Trinity 
River about 10 miles southwest of Fort Worth, Texas. 
BOGGY CREEK, TX 
Construction of a concrete trapezoidal channel on Boggy 
Creek beginning just above Webberville Road and 
extending downstream about 2.2 miles to just below 
Bolm Road. From there, a grass lined channel would 
extend further downstream and transition with the 
natural channel at Ed Bluestein Boulevard, a distance 
of about 1.7 miles. 
CANYON LAKE, TX 
Construction of a dam on the Guadalupe River about 12 
miles northwest of New Braunfels, Texas. 
COOPER LAKE AND CHANNELS, TX 
Construction of earth-fill dam and reservoir area; channel 
clearing, realignment, and enlargement; enlargement 
and extension of existing levees; construction of appurtenant 
drainage works along main stem of Sulphur 
River above mile 126; channel clearing, realignment, 
and enlargement and levee enlargement and modification 
of appurtenant drainage works on Cuthand Creek 
below mile 24, on Sulphur River below mile 70, except 
in proposed Cooper Reservoir, miles 29 to 42, and on 
Middle Sulphur River below mile 8; channel clearing 
and realignment of Brushy Creek below mile 5; and 
levee enlargement on North Sulphur River between 
miles 1 and 5. 
FERRELLS BRIDGE DAM-LAKE O' THE 
PINES, TX 
Provides for construction of an earth-fill dam and reservoir 
area. 
GRAND PRAIRIE, MEYERS RD, TX 
Slope Restoration with riprap side slopes along 
streambank of West Fork Trinity River, adjacent to 
Meyers Road. 
GRAPEVINE LAKE, TX 
Construction of a dam on Denton Creek, a tributary of the 
Trinity River, about 20 miles northwest of Dallas, 
Texas. 
HORDS CREEK LAKE, TX 
Construction of a dam on Hords Creek, a tributary of 
Pecan Bayou, near the city of Coleman, Texas. 
76th Cong., 1st 
H. Doc. 488, 83rd Cong., 
2nd Sess. 
H. Doc. 602, 79th Cong., 
2nd Sess. 
Flood Control Act of 1946 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 370, 76th Cong., 
1st Sess. 
30-19 
TABLE 30-B 
H. Doc. 247, 
Sess. 
5. 
7.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 30-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
13. Oct. 27, 1965 
14. Mar. 2, 1945 
15. Oct. 23, 1962 
Mar. 7, 1974 
16. Mar. 2, 1945 
17. Sep. 3, 1954 
Dec. 31, 1970 
18. Aug. 18, 1941 
19. Sep. 3, 1954 
20. Oct. 27, 1965 
32. Mar. 2, 1945 
21. Sep. 3, 1954 
22. Sep. 3, 1954 
Jan. 3, 1975 
23. Sep. 3, 1954 
24. Sep. 3, 1954 
33. Mar. 2, 1945 
JOE POOL LAKE, TX 
Construction of a dam on Mountain Creek, adjacent to the 
city limits of Grand Prairie, Texas, about 3 miles above 
the existing Mountain Creek Dam. 
LAVON LAKE, TX 
Construction of a dam on the East Fork of the Trinity 
River about 22 miles northeast of Dallas, Texas. 
LAVON LAKE MODIFICATION AND EAST 
FORK CHANNEL IMPROVEMENT, TX 
Enlarge Lavon Dam and enlargement and realignment of 
the lower 25 miles of the East Fork of the Trinity River, 
including rehabilitation of existing levees. 
Improvement of Collin County Road 115. 
LEWISVILLE DAM, TX 
Construction of a dam on the Elm Fork of the Trinity 
River near the city of Lewisville, Texas. 
NAVARRO MILLS LAKE, TX 
Construction of a dam on Richland Creek, a tributary of 
the Trinity River, about 16 miles southwest of 
Corsicana, Texas. 
Alteration of FM Highway 3164 in Wolf Creek Park. 
O.C. FISHER DAM AND LAKE, TX 
Construction of a dam on the North Concho River just 
above San Angelo, Texas. 
PROCTOR LAKE, TX 
Construction of a dam on the Leon River about 8 miles 
northeast of Comanche, Texas. 
RAY ROBERTS LAKE, TX 
Construction of a dam on the Elm Fork of the Trinity 
River between Sanger and Aubrey, Texas, about 30 
miles upstream from the existing Lewisville Dam. 
SAM RAYBURN DAM AND RESERVOIR, TX 
Construction of a dam on the Angelina River about 10 
miles northwest of Jasper, Texas. 
SAN ANTONIO CHANNEL IMPROVEMENT, 
TX 
Channel improvement of the San Antonio River and 
tributaries in and near the city of San Antonio, Texas. 
SAN GABRIEL RIVER PROJECT, TX 
Construction of: (1) a dam (Granger Dam and Lake) on 
the San Gabriel River about 7 miles east of Granger, 
Texas, (2) a dam (North Fork Lake) on the north Fork of 
the San Gabriel River about 3.5 miles northwest of 
Georgetown, Texas and (3) a dam (South Fork Lake) on 
the South Fork of the San Gabriel River about 3 miles 
southwest of Georgetown, Texas. 
SOMERVILLE LAKE, TX 
Construction of a dam on Yegua Creek about 2 miles south 
of Somerville, Texas. 
STILLHOUSE HOLLOW DAM, TX 
Construction of a dam on the Lampasas River about 5 
miles southwest of Belton, Texas. 
TOWN BLUFF DAM-B. A. STEINHAGEN 
LAKE, TX 
Construction of a dam on the Neches River near Jasper, 
Texas. 
H. Doc. 276, 89th Cong., 
1st Sess. 
H. Doc. 533, 78th Cong., 
2nd Sess. 
H. Doc. 554, 87th Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 498, 83rd Cong., 
2nd Sess. 
H. Doc. 315, 76th Cong., 
1st Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
H. Doc. 344, 83rd Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess., and 
H. Doc. 591, 87th Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
30-20

FORT WORTH, TEXAS DISTRICT 
TABLE 30-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
ROBERT DOUGLAS WILLIS HYDROPOWER, 
TX 
31. Mar. 2, 1945 Construction of two units at 3,000 kilowatts each of S. Doc. 98, 76th Cong., 
hydroelectric power generating facilities connected with 1st Sess. 
Town Bluff Dam-B.A. Steinhagen Lake, Texas. 
TRINITY RIVER PROJECT, TX 
1. Oct. 27, 1965 Construction of Tennessee Colony Dam located at river H. Doc. 276, 89th Cong., 
mile 339.2 on the Trinity River about 16 miles west of 1st Sess., and 
Palestine, Texas; a multiple purpose channel from the H. Doc. 364, 90th Cong., 
Houston, Texas ship channel to Fort Worth, Texas; a 2nd Sess. 
distance of approximately 363 miles, an extension of the 
existing Dallas, Texas, Floodway downstream approximately 
9.0 miles; a realignment and enlargement of the 
West Fork of the Trinity River from the mouth of the 
West Fork to the existing Fort Worth, Texas, Floodway, 
a distance of approximately 31 miles; and water 
conveyance facilities involving construction of about 98 
miles of pipeline from Tennessee Colony Lake to the 
existing Benbrook Lake. 
WACO LAKE, TX 
25. Sep. 3, 1954 Construction of a dam on the northwest edge of Waco, H. Doc. 535, 81st Cong., 
Texas, below the confluence of the North, South, and 2nd Sess. 
Middle Bosque Rivers. 
WHITNEY LAKE, TX 
34. Aug. 18, 1941 Construction of a dam on the Brazos River, about 19 miles H. Doc. 390, 76th Cong., 
southwest of Hillsboro, Texas. 1st Sess. 
Raise the power pool 13.0 feet. 
WRIGHT PATMAN DAM AND LAKE, TX 
26. Jul. 24, 1946 Construction of an earth-fill dam and reservoir. H. Doc. 602, 79th Cong., 
2nd Sess. 
30-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 30-C 
OTHER AUTHORIZED FLOOD CONTROL 
(See Section 29 of Text) 
PROJECTS 
For Last Full Cost to September 30, 1989 
Report See 
Annual Report Operation and 
Project For Construction Maintenance 
Belton Lake Modification, TX7 1988 - - 
Big Fossil Creek, TX3 1969 - - 
Big Sandy Lake, TX2 1986 - 
Big Spring, TX2 1979 - 
Brownwood Channel Improvement, TX5 - - 
Carl L. Estes Dam and Lake, TX2 1979 - - 
Dam "A" Lake, TX6 1987 - 
Duck Creek Channel Improvement, TX4 1983 - 
Elm Fork Floodway, TX 1987 - 
Fort Worth Floodway (Clear Fork), TX3 1971 - - 
Fort Worth Floodway (West Fork), TX3 1971 - 
Grand Prairie, TX (Landfill)3 1987 - 
Greenville, TX3 1983 - 
Lake Brownwood Modification, TX4 1983 - 
Lake Fork Lake, Sabine River, TX5 - - 
Millican, TX2 1988 - 
Navasota Lake, Navasota River, TX4 
Plainview Local Flood Protection Project, TX4 1979 - - 
Roanoak Lake, TX2 1979 - - 
Rockland Lake, TX6 1988 - 
Rutledge Hollow Creek Channel Improvement, Poteet, TX3 1969 - - 
Zacate Creek Channel, TX3 1983 - 
Calloway Branch, Hurst, TX3 1986 - - 
1Deauthorized 1 Nov 81. 5 Deauthorized Nov 86. 
2Inactive. 6Deauthorized Oct 88. 
"Completed. 7Deferred. 
4Recommended for deauthorization, H.R. 3678, August 
23, 1983, 98th Congress, 1st Session. 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
TABLE 30-D (See Section 27 of Text) 
Location Dates of Inspection 
Big Fossil Creek .................................. ..... ............. ... ....... Dec.15,1988 
Calloway Branch, Hurst .................................................. .......... Jul. 12, 1989 
Dallas Floodway .................................................... ........ Nov. 17,1988 
East Fork ................ ................................................. Nov.7, 1989 
Fort Worth Floodway ......... .................................................... Sep. 21, 1989 
Grand Prairie Landfill ................................................................ Jul. 19, 1989 
Grand Prairie Meyers Road ............................................... .......... Jul. 19, 1989 
Greenville...................................... ................................ Oct.19,1989 
Irving Floodway .................. .................. .................. Jul. 28, 1986 
Munday ............................................................. ................. Nov. 9, 1988 
Pleasanton ............................................................ ......... May 22, 1989 
Poteet ....................................................... ........... M ay 22, 1989 
San Antonio Floodway ................... ........................................ May 23, 1989 
Sulphur River Levees ............................. ............................... Aug. 23, 1985 
Wheeler Creek ......... ............................................. ........... Apr. 4, 1989 
Zacate Creek .................. May 24, 1989 
30-22

FORT WORTH, TEXAS DISTRICT 
TABLE 30-E
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Project 
Blockhouse Creek, Cedar Park, TX ..... 
Bunker Hills Creek, Watauga, TX ...... 
Burton Creek, Bryan, TX ........... 
California Creek, Hamlin, TX ......... 
Calloway Branch, Hurst, TX .......... 
Carrizo Creek, Carrizo Spring, TX ...... 
Chacon Creek, Laredo, TX ........... 
Chambers Creek, Everman, TX ........ 
Delaware Creek, Dallas, TX .......... 
Dry Branch Creek, Grand Prairie, TX .. . 
Elm Fork, Gainesville, TX............ 
Farmers Branch, White Settlement, TX. . 
Grassy Branch, Millsap, TX .......... 
Johnson Creek, Grand Prairie, TX ...... 
Little Walnut Creek, Austin, TX ....... 
Lorean Branch, Hurst, TX ........... 
Lower Walnut Creek, Austin, TX....... 
Pecan Creek, Gainesville, TX ......... 
Rush Creek, Arlington, TX ........... 
Singing Hills Creek, Watauga, TX ...... 
South Mesquite, Mesquite, TX ......... 
Spanish Oak Creek, Cedar Park, TX .. . 
Sulphur Branch, Euless, TX .......... 
Ten Mile Creek, De Soto, TX.......... 
Ten Mile Creek, Duncanville, TX ....... 
Ten Mile Creek, Lancaster, TX ........ 
Timber Creek, Double Oak, TX ........ 
Town Branch Creek, Lockhart, TX...... 
Upper Zacate Creek, Laredo, TX ....... 
Valley View Branch, Hurst, TX........ 
Walnut Creek, Hood County, TX ....... 
Walnut Creek, Sequin, TX ........... 
Walnut Creek Tribs, Austin, TX ....... 
Whitney Creek, Whitney, TX ......... 
Zacate Creek, Laredo, TX ............ 
Zarzamdra Creek, San Antonio, TX ..... 
(See Section 30 of Text) 
Cost 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
. . 
30-23 
. . 
. . 
. . 
. . 
. . 
$ 00 
193
00 
51,472 
1,580 
923 
22,303 
61,333
0 
75,892
0 
94,404 
5,065 
1,462,740
00 
29,765 
24,657 
77
0 
47,080 
51,589 
22,871
00 
14,190 
27,840 
22,476 
51,795 
35,923 
12 
1,722
0 
14,929 
. . . . . . . . . . 
. . . . . . . . . . 
. . . . . . . . . . 
. . . . . . . . . . 
. . . . . . . . . . 
. . 
. . . . . . . . . . 
. . . . . . . . . . 
. . . . . . . . . . 
. . . . . . . . . .

GALVESTON, TEXAS, DISTRICT * 
Galveston District comprises drainage basins of all 
short streams arising in coastal plain of Texas and 
flowing into the Gulf of Mexico, including the entire 
basin of Buffalo Bayou, San Jacinto, San Bernard, 
Lavaca, Navidad, Mission, and Aransas Rivers. It 
embraces Agua Dulce, San Fernando, and Olmos Creek 
Basins draining into Baffin Bay, and coastal area south 
thereof to the Rio Grande and east of western 
Boundary of Starr County, Texas. It includes lower 
basins of major streams flowing into the Gulf of 
Mexico: Sabine River, Texas and Louisiana, downstream 
from U.S. Highway 190 crossing at Bon Wier, 
Texas; Neches River downstream from Town Bluff 
gaging station; Trinity River downstream from Texas 
State Highway 19 crossing at Riverside, Texas; Brazos 
River downstream from confluence with Navasota 
River; Colorado River downstream from northern 
boundary of Fayette County; Guadalupe River downstream 
from confluence with San Marcos River; San 
Antonio River downstream from confluence with 
Escondido Creek; Nueces River downstream from 
confluence with Frio and Atascosa River. 
31-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
IMPROVEMENTS 
Navigation Page Flood Control (cont.) 
1. Aquatic Plant Control (Southwestern 
Division) ........................... 
2. Brazos Island Harbor, TX ............. 
3. Cedar Bayou, TX .................... 
4. Corpus Christi Ship Channel, TX ....... 
5. Freeport Harbor, TX ................. 
6. Galveston Harbor and Channel, TX ..... 
7. Gulf Intracoastal Waterway between 
Apalachee Bay, FL, and the Mexican 
Border ............................ 
8. Houston Ship Channel, TX ............ 
9. Matagorda Ship Channel, TX ......... 
10. Sabine-Neches Waterway, TX .......... 
11. Texas City Channel, TX ............... 
12. Trinity River and Tributaries, TX ....... 
12A. Anahuac Channel, TX ................ 
12B. Channel to Liberty, TX ............... 
12C. Wallisville Lake, TX ................. 
13. Reconnaissance and Condition Surveys .. 
14. Navigation Work Under Special 
Authorization ...................... 
31-2 
31-2 
31-3 
31-3 
31-4 
31-5 
31-5 
31-7 
31-7 
31-7 
31-8 
31-9 
31-9 
31-9 
31-9 
31-10 31. Surveys .......................... 
32. Planning and Engineering ............ 
31-10 33. Collection and Study of Basic Data ..... 
Tables 
31-A Cost and Financial Statement. 31-17 thru 
31-B Authorizing Legislation ..... 31-20 thru 
31-C Other Authorized Navigation Projects .. 
31-D Other Authorized Flood Control Projects. 
31-E Total Cost of Existing Projects ........ 
31-F Channel Dimensions ........ 31-36 thru 
31-G Channel Dimensions, GIWW 
Tributary Channels ........ 31-39 thru 
31-H Dredging Operations ........ 31-41 thru 
31-11 
31-11 
31-12 
31-12 
31-12 
31-12 
22. Port Arthur and Vicinity, TX 
Hurricane-Flood Protection ........... 
23. Sims Bayou, TX .................... 
24. Taylors Bayou, TX .................. 
25. Texas City and Vicinity, TX 
Hurricane-Flood Protection ........... 
26. Upper White Oak Bayou, TX ......... 
27. Vince and Little Vince Bayous, TX ..... 
28. Inspection of Completed Flood Control 
W orks ........................... 
29. Flood Control Work Under Special 
Authorization ...................... 
30. Emergency Stream Bank and Shoreline 
Erosion Work and Snagging and Clearing 
Under Special Authorization .......... 
General Investigations 
Beach Erosion Control 
15. Corpus Christi Beach, TX ............ 31-10 
Flood Control 
16. Buffalo Bayou and Tributaries, TX ..... 
17. Clear Creek, TX .................... 
18. Cypress Creek, TX .................. 
19. Falfurrias, TX ..................... 
20. Kirbyville, TX ..................... 
21. Lower Rio Grande Basin, TX .......... 
Navigation 
1. AQUATIC PLANT CONTROL 
(SOUTHWESTERN DIVISION) 1965 
ACT 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in Texas 
and the Sabine River Watershed of Louisiana. 
Previous project. For details see page 699 of 
Annual Report for 1963. 
Existing project. A comprehensive project to 
provide for control and progressive eradication of 
water-hyacinth, alligatorweed, Eurasian watermilfoil, 
hydrilla, and other obnoxious aquatic plant growths, 
from navigable waters, tributary streams, connecting 
channels, and other allied waters in Texas in the 
combined interest of navigation, flood control, drainage, 
agriculture, fish and wildlife conservation, public 
health, and related purposes, including continued 
research for development of the most effective and 
economic control measures. Control of hydrilla, water 
hyacinth and alligator weed continues in the Nueces 
River Basin, North Coastal Area, Guadalupe River 
Basin, Sabine River Basin, Trinity River Basin, Cypress 
Creek Basin, Neches River Basin, South Coastal Area, 
San Jacinto River Basin, Rio Grande Basin, Colorado 
River Basin and Brazos River Basin. 
Local cooperation. Sec. 302, 1965 River and 
Harbor Act, amended by Water Resources Development 
Act of 1986, applies. 
Operations during fiscal year. Control work by 
the State of Texas continued. Coordination of a 
Cooperative Agreement with the State for operations 
was continued. Monitoring of the biological control 
nursery areas was continued during the year. Expansion 
of the program to additional sites was approved. 
2. BRAZOS ISLAND HARBOR, TX 
Location. At extreme south end of coast of Texas, 
about 7 miles north of mouth of Rio Grande and about 
5 miles east of Brownsville, Texas. (See National Ocean 
Survey Chart 11301.) 
31-2 
Page 
31-13 
31-13 
31-13 
31-14 
31-14 
31-14 
31-15 
31-15 
31-15 
31-15 
31-15 
31-16 
31-19 
31-33 
31-34 
31-34 
31-35 
31-38 
31-40 
31-42

GALVESTON, TEXAS, DISTRICT 
Previous project. For details see page 1017 of 
Annual Report for 1932. 
Existing project. Provides for channel dimensions 
in various sections of the waterway as shown in Table 
15F.
Project also provides for dual jetties at the gulf 
entrance, a north jetty 6,330 feet long, a south jetty 
5,092 feet long, and 1,000-foot extension to existing 
north jetty and for maintenance of 3rd fishing harbor 
constructed by local interests. Under ordinary conditions, 
mean tidal range is about 1.5 feet, and extreme 
range is about 2 feet. All depths refer to mean low tide. 
To some extent, height of tides is dependent on the 
wind, and during strong "northers" in winter season, 
water surface in southern end of Laguna Madre may be 
raised 4 feet or more above mean low tide in the gulf. 
Estimated cost for new work is: Federal (Corps) 
$32,581,647, exclusive of amount expended on previous 
projects, and non-Federal $16,056,258, including 
$8,697,258 contributed funds, $438,000 lands, 
$2,064,000 relocations, and $4,857,000 other costs, 
exclusive of amount expended on previous projects. 
(October 1, 1989 base price). 
Widening Brownsville Channel from Goose Island 
to Brownsville turning basin and deepening southeast 
corner of Brownsville turning basin to 36 feet was 
completed in April 1980. The 1,000-foot extension to 
existing north jetty was deauthorized under Section 
1001 of the Water Resources Development Act of 1986. 
Work remaining consists of enlarging 14.8 miles of the 
existing Brownsville Channel from 36 feet by 200 feet 
to 42 feet by 300 feet and by enlarging 2.5 miles of the 
entrance channel from 38 feet by 300 feet to 44 feet by 
400 feet. The turning basin would be enlarged to 1,200 
feet at a depth of 36 feet. (See Table 31-E for total cost 
of existing project to September 30, 1989.) 
Local cooperation. Complied with for the completed 
work. For the 42 foot project authorized by the 
Water Resources Development Act of 1986, local 
interests are required to provide lands, easements, 
rights-of-way, and material disposal areas; levees and 
spillways for disposal areas; modify or relocate utilities, 
roads, and other facilities, except railroad bridges; pay 
one-half of the separable and joint costs allocated to 
recreation; and pay 25 percent of the costs allocated to 
deep-draft navigation, during construction, and pay an 
additional 10 percent of the costs allocated to navigation 
within a period of 30 years following completion if 
not offset by credit allowed for lands, easements, 
rights-of-way, relocations and dredged material disposal 
areas. 
Terminal facilities. Numerous terminal facilities 
for bulk and liquid cargo are available. (See Port Series 
No. 26, revised 1980.) Facilities are adequate for 
existing commerce. 
Operations during fiscal year. New Work: See 
Section 32, Planning and Engineering. 
Maintenance: Routine maintenance. (See Table 
31-H for dredging operations.) 
3. CEDAR BAYOU, TX 
Location. The bayou is about 30 miles long. It 
flows to the south and empties into northwest corner of 
upper Galveston Bay, about 1.5 miles below mouth of 
San Jacinto River and about 28.5 miles north of 
Galveston, Texas. (See National Ocean Survey Chart 
11326.) 
Previous project. For details see Annual Report 
for 1938. 
Existing project. Project provides for a channel 10 
feet by 100 feet from Houston Ship Channel to Bayou 
Mile 11.0. Channel was completed from Houston Ship 
Channel to first bend in Cedar Bayou above the mouth 
in 1931. Channel from Mile -0.1 to Mile 3.0 was 
completed in March 1975. Channel from Mile 3.0 to 
Mile 11.0 was deauthorized under Sec. 12 of Public Law 
93-251. Project also includes jetties at mouth of bayou 
provided for under previous project. 
Under ordinary conditions, mean tidal range is 
about 0.6 feet and extreme range 1.2 feet. Height of 
tides is dependent largely on the wind, and during 
strong "northers" in the winter season water surface 
may be depressed 2 feet below mean low tide. (See 
Table 15-E for total cost of existing project to 
September 30, 1989.) 
Local cooperation. Fully complied with. 
Terminal facilities. U.S. Steel Company has a 
barge dock at bayou mile 2.8, and there are a few small 
wharves, privately owned, for local use at various 
places along Cedar Bayou. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Routine maintenance. (See Table 31-H for dredging 
operations.) 
4. CORPUS CHRISTI SHIP 
CHANNEL, TX 
Location. This project, formerly known as the Port 
Aransas-Corpus Christi Waterway, Texas, was changed 
to Corpus Christi Ship Channel, Texas, by 1968 River 
and Harbor Act. This is a consolidation of old 
improvements of Port Aransas, Texas, and channel 
from Aransas Pass to Corpus Christi, Texas. Aransas 
Pass is on southern portion of Texas Coast, 180 miles 
southwest of Galveston and 132 miles north of mouth of 
Rio Grande. Aransas Pass connects Corpus Christi Bay 
with the gulf. Waterway extends from deep water in 
the gulf through Aransas Pass jettied entrance, thence 
westerly 20.75 miles to and including a turning basin at 
Corpus Christi, thence westerly 1.75 miles through 
Industrial Canal to and including turning basin at 
Avery Point, thence westerly 4.25 miles to and 
including a turning basin near Tule Lake, thence 
northwesterly 1.8 miles to and including a turning 
basin at Viola, Texas. (See National Ocean Survey 
Charts 11308, 11309, 11311, and 11314.) 
Previous project. For details see page 1861 of 
Annual Report for 1915. 
31-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Existing project. (See Table 31-F for existing 
project dimensions provided for in various channels 
and basins comprising this waterway.) 
Project also provides for two rubblestone jetties at 
Aransas Pass entrance, extending into the gulf from St. 
Joseph and Mustang Islands, project lengths of which 
are 11,190 and 8,610 feet, respectively. Project further 
provides for a stone dike on St. Joseph Island about 
20,991 feet long, connecting with north jetty and 
extending up this island to prevent a channel being cut 
around jetty. Project also provides for a breakwater at 
the entrance to the harbor area at Port Aransas, and 
for the realignment of the existing 12-foot by 100-foot 
project channel to Port Aransas. The breakwater 
consists of two overlapping sections. The one on the 
east side of the realigned entrance channel has a length 
of 830 feet and the second, located on the west side of 
the entrance channel, has a length of 1,290 feet. The 
channel to Port Aransas was relocated in the 300-foot 
clear distance between the overlapping sections. The 
portion of the channel remaining inside the breakwaters 
was widened to 150 feet. Under ordinary conditions, 
mean tidal range at Aransas Pass is about 1.1 
feet and extreme range about 2 feet, and at Corpus 
Christi mean range about 1 foot and extreme about 1.5 
feet. Heights of tides are dependent largely on strength 
and directions of winds, and during strong "northers" 
in the winter season water surface may be depressed as 
much as 3 feet below mean low tide. Estimated cost for 
new work is: Federal (Corps) $74,938,515, including 
$456,515 for Port Aransas Breakwaters and exclusive 
of amount expended on previous projects: and non- 
Federal $18,977,431 (includes $768 for Port Aransas 
Breakwaters) including $7,644,435 contributed funds 
and value of useful work performed, $3,320,228 lands, 
$6,027,000 relocations and $1,985,000 other cost. (October 
1, 1989 base price.) 
The Port Aransas-Corpus Christi 40-foot project 
was completed in 1966. The Jewel Fulton Canal was 
completed in 1963. The Port Aransas Breakwaters were 
completed in July 1973. Work remaining consists of 
deepening deep-draft channels to 45 feet from Tule 
Lake Turning Basin through Viola Turning Basin, and 
constructing a mooring area at Port Ingleside with 
dolphins. Entrance and jetty channels have been 
dredged to project depth and width, and dredging of 
channel from Harbor Island to and through the 
Chemical Turning Basin at 45-foot depth has been 
completed. Initial mooring dolphins were completed in 
May 1979. Disposal area levees, Area 1 and Rincon 
were completed in August 1984. First stage disposal 
area levees, South Shore, were completed in September 
1984. (See Table 31-E for total cost of existing project to 
September 30, 1989.) 
Local cooperation. Fully complied with. 
Terminal facilities. Terminal facilities on Harbor 
Island at head of Aransas Pass, Ingleside, Corpus 
Christi, La Quinta, Avery Point, and Viola, are 
considered adequate for existing commerce. (See Port 
Series, No. 25, revised 1979, Corps of Engineers.) 
Operations during fiscal year. New Work: Construction 
of retaining works at Suntide was completed 
at a fiscal year cost of $130,961. Contract for dredging 
Tule Lake to and including Viola Turning Basin was 
completed at a fiscal year cost of $7,116,237. Contracts 
for the alteration of a 6" oil pipeline, an 8" pipeline and 
a 4" fiber optic cable in the Suntide area are completed 
at a fiscal year cost of $44,535, $39,913 and $33,003 
respectively. Construction of the effluent ditch for the 
Suntide Disposal Area was awarded in July 1989. 
Fiscal year cost was $250,031. (See Table 31-H for 
dredging operations.) 
Maintenance: Routine maintenance. (See Table 
31-H for dredging operations.) 
5. FREEPORT HARBOR, TX 
Location. Formed by improvement of Brazos 
River, Texas, from mouth to about 6 miles upstream to 
Freeport, Texas. (See National Ocean Survey Charts 
11321 and 11322.) 
Previous projects. For details see page 1860 of 
Annual Report for 1915, and page 872 of Annual 
Report for 1938. 
Existing project. Existing project dimensions for 
various channels and basins are shown in Table 31-F on 
channel dimensions at end of chapter. 
Existing project also provides for: Dual jetties and a 
diversion canal for the Brazos River, including a dam, a 
lock in the dam and necessary auxiliary equipment. 
Also provides for rehabilitation of southwest jetty and 
the relocation of the northeast jetty (about 640 feet to 
the northeast); realignment of the channel between the 
Jetty Channel and Brazosport Turning Basin; realignment 
of the channel between Brazosport Turning Basin 
and Upper Turning Basin; relocation of Upper Turning 
Basin; and public use facilities adjacent to the Freeport 
Jetties. The 30-foot channel from Upper Turning Basin 
to Stauffer Chemical Plant, including the turning 
basin, was deauthorized by Sec. 12 of PL 93-251. 
Construction of lock in diversion dam at local expense 
is considered inactive. 
The 38-36 foot project was completed in 1962. Work 
remaining consists of realigning, deepening and widening 
the Outer Bar and Jetty Channels; relocating the 
northeast jetty; rehabilitating the southwest jetty; 
realigning and deepening the harbor channel between 
the jetty channel and the Upper Turning Basin; 
relocating and enlarging the Upper Turning Basin; 
constructing a turning point near the northwesterly 
end of the jetty channel; enlarging Brazosport Turning 
Basin; deepening Brazos Harbor Channel; and enlarging 
and deepening Brazos Harbor Turning Basin, as 
authorized by the R&H Act of 1970. The initial contract 
for the 45 foot project, construction of 3,700 feet of the 
North Jetty, was awarded in May 1987. (See Table 31-E 
for total cost of existing project to September 30, 1989.) 
Under ordinary conditions mean tidal range is 
about 1.5 feet and extreme range is about 2.5 feet. 
Except under extreme conditions, rises on river and in 
diversion channel do not cause greater variations in 
water surface than those caused by tidal action. 
31-4

GALVESTON, TEXAS, DISTRICT 
Estimated cost of new work is: $63,627,000 Federal 
(Corps); and $31,666,000 non-Federal, including 
$21,158,303 contributed funds, $360,249 contributed 
work, $6,587,448 lands, $2,990,000 levees and spillways, 
and $570,000 relocations. (October 1, 1989 base price.) 
Local cooperation. Fully complied with except for 
Section 101 of River and Harbor Act of 1970, modified 
by the Water Resources Development Act of 1986. The 
Local Cooperation Agreement, executed 26 June 1986, 
requires that local interest provide lands, easements, 
rights-of-way, including land for recreation, and 
dredged material disposal areas, presently estimated at 
$9,260,000, modify or relocate utilities, roads, and other 
facilities, except railroad bridges, where necessary for 
construction of the project, presently estimated at 
$570,000, contribute in cash one-half of the separable 
and joint costs allocated to recreation, presently 
estimated at $390,000; and, during construction, pay 25 
percent of the construction costs allocated to deep-draft 
navigation, presently estimated at $20,010,000. 
Terminal facilities. Small privately owned 
wharves, two oil docks, one acid dock, two shell 
unloading docks and one caustic dock. Brazos River 
Navigation District has one large dock with four transit 
sheds over rail facilities permitting all-weather work. 
Facilities considered adequate for existing commerce. 
(See Port Series No. 26, revised 1980, for additional 
facilities.) 
Operations during fiscal year. New Work: Construction 
of 3,700 feet of the North Jetty continued at a 
fiscal year cost of $3,565,080. 
Maintenance: Routine maintenance. (See Table 
31-H for dredging operations.) 
6. GALVESTON HARBOR AND 
CHANNEL, TX 
Location. A consolidation of authorized improvements 
at Galveston, Texas, which includes projects 
formerly identified as Galveston Harbor, Texas; 
Galveston Channel, Texas; and Galveston seawall 
extension. Entrance to Galveston Harbor is on Gulf of 
Mexico on the northern portion of the Texas Coast. 
Galveston Channel extends from a point in Galveston 
Harbor between Bolivar Peninsula and Fort Point to 
and along wharf front Galveston, Texas, and is about 5 
miles long and 1,200 feet wide. (See National Ocean 
Survey Chart 11324/5.) 
Previous projects. For details see page 1854 of 
Annual Report for 1915. 
Existing project. Provides for channel dimensions 
in sections of the waterway shown in Table 31-F. 
Also provided are: two rubble-mound jetties, the 
south one extending from Galveston Island and the 
north one extending from Bolivar Peninsula, for 
distances of 35,900 feet and 25,907 feet, respectively, 
into the Gulf of Mexico; a concrete seawall from the 
angle at Sixth Street and Broadway, in the city of 
Galveston, to the south jetty, and a 16,300-foot 
extension of the concrete seawall in a southwesterly 
direction from 61st Street; for 11 groins along the gulf 
shore between 12th Street and 61st Street; and for 
maintenance of seawall from the angle at 6th Street 
and Broadway to the south jetty. Under ordinary 
conditions, mean tidal range in Galveston Harbor is 1.6 
feet on outer bar and 1.4 feet on inner bar with extreme 
ranges of 2.3 and 2.1 feet, respectively. Mean range in 
Galveston channel is about 1.3 feet and extreme range 
about 2 feet under ordinary conditions. Height of tides 
in both Galveston harbor and channel is dependent 
largely on the wind, and during strong "northers" 
water surface may be depressed 2 feet below mean low 
tide.
Existing project is complete. Dredging of Galveston 
channel to 36 foot depth was completed in November 
1966. Dredging of the realigned entrance and Outer 
Bar Channel was completed in October 1967. Rehabilitation 
of the Beach Front Groins was completed June 
1970. Dredging of Galveston channel to 40 feet was 
completed in March 1976. See Section 12. TEXAS CITY 
CHANNEL, TX regarding work authorized by Water 
Resources Development Act of 1986. (See Table 31-E for 
total cost of existing project to September 30, 1989.) 
Local cooperation. Complied with. 
Terminal facilities. None on Galveston Harbor, 
which is entrance channel leading to terminal facilities 
on Galveston, Texas City, and Houston Ship Channels. 
Galveston Channel terminal facilities are mostly on 
south side of channel. Principal wharves, owned by the 
city of Galveston, extend from 10th to 41st Street (see 
Port Series No. 23, revised 1979). A containership 
terminal equipped with a crane capable of stacking 
containers three units high on the deck of any normal 
containership has been completed and placed into 
operation by the city of Galveston at Piers 10 and 11, 
on the south side of Galveston Channel. The city of 
Galveston has also placed into operation a barge 
terminal equipped with two 35-ton and one 5-ton cranes 
for loading and unloading barges on Lash and Seabee 
ships at Pier 35 and a docking and holding area for 
Lash and Seabee barges on Pelican Island, directly 
across the channel from Piers 35 and 36. Present 
facilities are considered adequate for existing commerce. 
Operations during fiscal year. Routine maintenance 
including mosquito control spraying. (See Table 
31-H for dredging operations.) 
7. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FL, AND 
MEXICAN BORDER 
Location. Extends from a point on Sabine River 
about 3 miles below Orange, Texas, to Brownsville, 
Texas, about 421 miles; a navigation channel, about 7 
miles long, in Colorado River, extending from 
Matagorda, Texas, to Gulf of Mexico; a tributary 
channel in San Bernard River, extending from 
Intracoastal Waterway crossing to State highway 
bridge some 30 miles above crossing; a tributary 
channel in Colorado River extending from Intracoastal 
Waterway upstream 15.5 miles; a tributary channel 
extending about 14 miles from Intracoastal Waterway 
31-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
to Palacios, Texas; a tributary channel extending about 
2 miles from Intracoastal Waterway to Rockport, 
Texas; a tributary channel extending about 6 miles 
from Intracoastal Waterway near Port Aransas, Texas, 
to town of Aransas Pass, Texas; a tributary channel 
about one-fourth mile long extending from Intracoastal 
Waterway near Port O'Connor, Texas, into Barroom 
Bay; a tributary channel extending about 38.8 miles 
from Intracoastal Waterway via Seadrift to a point in 
Guadalupe River 5.5 miles below Victoria, Texas; a 
harbor of refuge for small craft at Seadrift; a channel 
extending from gulf to Port Mansfield, Texas, about 11 
miles; and a tributary channel in Arroyo, Colorado 
extending from Intracoastal Waterway to a point near 
Harlingen, Texas, about 31 miles; side channels in 
vicinity of Port Isabel, Texas, and a small boat basin at 
Port Isabel, Texas, and a tributary channel extending 
from Intracoastal Waterway main channel at a point in 
West Galveston Bay into Offatts Bayou about 2.2 miles 
with a west turnout (wye connection) 12 feet deep and 
125 feet wide between Offatts Bayou Channel and the 
Gulf Intracoastal Waterway. (See National Ocean 
Survey Charts 11302, 11303, 11305, 11306, 11308, 
11309, 11314, 11315, 11317, 11319, 11322, 11326, and 
11331.) 
Previous project. For details see page 1859 of 
Annual Report for 1915. (West Galveston Bay and 
Brazos River Canal, Texas.) 
Existing project. Existing project dimensions provided 
for in main channel of waterway: A channel 12 
feet deep (below mean low tide) and 125 feet wide from 
the Sabine River to Brownsville, Texas. Relocation of 
channel 12 feet deep by 125 feet wide in Matagorda 
Bay, miles 454.3 to 471.3, relocation of channel 12 feet 
deep by 125 feet wide in Corpus Christi Bay, miles 539.4 
to 549.7 (mileage is west of Harvey Lock, Louisiana); 
and alternate channel, 12 feet deep (below mean low 
tide) and 125 feet wide via Galveston Channel and 
Galveston Bay to the Galveston causeway; maintenance 
of existing channel 12 feet deep by 125 feet wide 
through Lydia Ann Channel, between Aransas Bay and 
Aransas Pass; provisions of such passing places, 
widening of bends, locks and guard locks, railway 
bridges over artificial cuts as are necessary, and the 
tributary channels shown in tabulation. The authorized 
channel 16 feet deep and 125 feet wide from Sabine 
River to Houston Ship Channel is inactive. (See Table 
31-G on existing project dimensions provided for in 
tributary channels.) 
Removal of the railroad bridge across the canal at 
Mud Bayou was completed and operation and care of 
the facility was discontinued on April 14, 1969. 
Deepening the existing 6 foot by 60 foot side channels 
at Port Isabel to 12 feet was completed February 22, 
1972, Offatts Bayou channel was completed January 
1974. Relocation of main channel across Corpus Christi 
Bay was completed in September 1976. The 14 foot by 
175 foot Channel to Aransas Pass was completed in 
April 1979. Dredging Chocolate Bayou Channel was 
completed in January 1981. Construction of a saltwater 
barrier in Chocolate Bayou was completed in February 
1981. The 12 foot by 125 foot channel relocation route 
in Matagorda Bay has been deauthorized. The Harbor 
of Refuge at Seadrift, Texas, has been placed in the 
inactive category. Construction of jetties at mouth of 
Colorado River was completed in 1986. Active authorized 
work remaining consists of the following: (1) 
Mouth of Colorado River, dredging a navigation 
channel from gulf to the GIWW; construction of an 
impoundment basin; constructing a turning basin at 
Matagorda, Texas; construction of a diversion dam and 
channel; construction of a dam at Tiger Island Cut; 
construction of an oyster cultch; and recreation facilities; 
(2) Work authorized by the Water Resources 
Development Act of 1988 for enlarging the existing 
Channel to Victoria from a depth of 9 feet and width of 
100 feet to a depth of 12 feet and width of 125 feet. (See 
Table 31-E for total cost of existing project to 
September 30, 1989.) 
Mean tidal variation is 0.5 foot at Orange, 1 foot at 
Port Arthur, 1.3 feet in Galveston Bay, 1.5 feet at 
Freeport, 1 foot in Matagorda Bay, 1 foot in San 
Antonio Bay, 1 foot at Corpus Christi, 1.5 feet at Port 
Isabel, and 1.5 feet at Brownsville. Extreme ranges of 
tide under ordinary conditions are 1 foot at Orange, 1.5 
feet at Port Arthur, 2 feet in Galveston Bay, 2 feet at 
Freeport, 1.5 feet in Matagorda and San Antonio Bays, 
1.5 feet at Corpus Christi, 2 feet at Port Isabel, and 1.5 
feet at Brownsville. Height of tides is dependent largely 
on wind. Strong north winds have depressed water 
surface as much as 2 feet below mean low tide. 
Estimated cost for new work is: $91,764,000 (excluding 
$164,000 Department of Transportation cost for Channel 
to Victoria) Federal (Corps), including $8,414 for 
Port Isabel Side Channel, $46,559 for Port Isabel Small 
Boat Basin, $356,466 for Offatts Bayou, and $658,573 
for Channel to Aransas Pass and excluding expenditures 
on previous projects; non-Federal $25,025,174 
($395,000 voluntarily expended on Gulf Intracoastal 
Waterway, $46,559 contributed funds for Port Isabel, 
$49,665 contributed funds for Offatts Bayou, $347,950 
contributed funds for channel to Aransas Pass, 
$3,530,000 contributed funds for Mouth of Colorado 
River, $1,680,000 contributed funds for Channel to 
Victoria, $7,155,000 lands for Gulf Intracoastal Waterway, 
$11,000 lands for Port Isabel, $4,242,000 relocations 
for Gulf Intracoastal Waterway, and $7,568,000 
other costs for Gulf Intracoastal Waterway). (October 1, 
1989 base prices.) 
Local cooperation. Fully complied with except for 
provisions of Section 101, 1968 River and Harbor Act 
and Water Resources Development Act of 1988. 
Non-Federal contributions are $395,000 for Gulf 
Intracoastal Waterway, $46,559 for Port Isabel, Texas, 
$49,665 for Offatts Bayou, Texas, $347,950 for Channel 
to Aransas Pass, Texas, and $3,530,000 for Mouth of 
Colorado River, Texas, and $1,680,000 for Channel to 
Victoria. 
Terminal facilities. There are terminal facilities 
at Aransas Pass, Port Arthur, Galveston, Port Isabel, 
and Brownsville. See Port Series No. 22 (revised 1981), 
Port Series No. 23 (revised 1979), Port Series No. 25 
(revised 1979) and Port Series No. 26 (revised 1980), 
31-6

GALVESTON, TEXAS, DISTRICT 
Corps of Engineers. Local interests constructed terminal 
facilities at Port Mansfield and Port Harlingen. 
There are numerous privately owned piers and 
wharves along the waterway. A 330-foot navigation 
district owned general cargo dock, a 770-foot private 
dock and a 760-foot private timber trestle have recently 
been completed at the upper end of the Channel to 
Victoria. Facilities are adequate for existing commerce. 
Operations during fiscal year. New work: Contract 
for dredging the harbor and turning basin was 
completed at a fiscal year cost of $727,110. Contract for 
the diversion channel and levees continued at a fiscal 
year cost of $2,866,010. Channel to Victoria New Work: 
See Section 32, Planning and Engineering. 
Maintenance: The Brazos River Floodgates were 
operated and maintained at a cost of $917,042 including 
engineering and design, supervision and administration, 
and real estate activities. The Colorado River 
Locks were operated and maintained at a cost of 
$2,481,125 including engineering and design and supervision 
and administration. (See Table 31-H for dredging 
operations.) 
8. HOUSTON SHIP CHANNEL, TX 
Location. Connects Galveston Harbor, at a point 
opposite Port Bolivar, with city of Houston, Texas, 
extending 50 miles northwesterly across Galveston Bay 
through San Jacinto River and Buffalo Bayou to a 
turning basin at head of Long Reach with light-draft 
channel 5 miles long from turning basin to Jenson 
Drive, Houston. (See National Ocean Survey Charts 
11324/5, 11327, 11328, and 11329.) 
Previous project. For details see page 1856 of 
Annual Report for 1915. 
Existing project. Provides for channel dimensions 
in sections of the waterway shown in Table 31-F. 
Also provides for certain cut-offs, for easing sharp 
bends, an earthen dam across the upper end of Turkey 
Bend, and for off-channel silting basins as deemed 
necessary by the Chief of Engineers. Construction of 
26,000 linear feet of pile dike to protect the channel in 
upper Galveston Bay was deauthorized by Sec. 12 of PL 
93-251. The 40-foot project was completed in March 
1966. Dredging a channel in Greens Bayou to Mile 1.57 
was completed in 1970. Dredging Greens Bayou, Mile 
1.57 to Mile 2.73, has been deauthorized. (See Table 
31-E for total cost of existing project to September 30, 
1989.) 
Mean tidal range under ordinary conditions is 0.6 
foot to 1.3 feet in lower part of Galveston Bay; 0.6 foot 
to 1.3 feet in upper bay; and 0.5 to 1 foot in San Jacinto 
River and Buffalo Bayou. Extreme ranges under 
ordinary conditions are about 2 feet, 1.2 feet and 1 foot, 
respectively. Freshets caused rises of over 12 feet in 
Buffalo Bayou; however, this condition has not occurred 
since completion of Addicks and Barker Dams 
for flood control on upper watershed of Buffalo Bayou. 
Height of tides is dependent largely on the wind, and 
during strong "'northers" in winter season the water 
surface may be depressed 2 feet below mean low tide. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Houston and Port of 
Houston Authority operate modern terminals which 
supplement privately owned wharves, piers, and docks, 
as described in Port Series No. 24 (revised 1980), Corps 
of Engineers. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Rehabilitation of 
House and Stimson Tracts disposal areas fiscal year 
cost was $3,054,999. Rehabilitation of Peggy Lake 
disposal area fiscal year cost was $197,946. Routine 
maintenance, including mosquito control spraying. (See 
Table 31-H for dredging operations.) 
9. MATAGORDA SHIP CHANNEL, 
TX 
Location. This is a consolidation of shallow draft 
channel improvements of "Channel from Pass Cavallo 
to Port Lavaca, Texas," and deep draft channel 
improvements authorized under "Matagorda Ship 
Channel, Texas." Bar at Pass Cavallo is 125 miles 
southwest of Galveston entrance and 54 miles north of 
Aransas Pass. It connects Matagorda Bay with the gulf. 
Project extends across Matagorda Bay and Lavaca Bay 
to towns of Port Lavaca and Point Comfort. These two 
towns are on opposite sides of Lavaca Bay and both are 
about 26 miles northwest from Pass Cavallo. (See 
National Ocean Survey Chart 11316.) 
Existing project. Existing project dimensions provided 
for in various channels and basins are listed in 
Table 31-F on channel dimensions. 
Project also provides for dual jetties at entrance, 
south jetty extending 6,000 feet to 24-foot depth in the 
gulf and north jetty extending 5,900 feet to 24-foot 
depth. Under ordinary conditions mean tidal range is 
about 1 foot and extreme range about 2 feet. Height of 
tide is dependent largely on the wind, and during 
strong "northers" in winter season the water surface 
may be depressed 2 feet below mean low tide. 
Estimated cost for new work is: $18,058,777 Federal 
(Corps), and $12,859,000 non-Federal, including 
$12,259,619 contributed funds, $182,000 for lands, 
$220,000 for relocations, and $196,581 other costs. The 
project was completed in March 1967. 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned facilities at 
Port Lavaca, municipally owned facilities at mouth of 
Lynn bayou, privately owned and publicly owned 
facilities at Point Comfort, Texas. These facilities are 
considered adequate for present commerce. Facilities at 
Point Comfort consist of a channel, turning basin with 
wharfs, oil dock and loading equipment, all owned by 
Aluminum Company of America; and a wharf built by 
local interest at Point Comfort turning basin. 
Operations during fiscal year. Routine maintenance. 
(See Table 31-H for dredging operations.) 
10. SABINE-NECHES WATERWAY, TX 
Location. This is a consolidation of old improvements 
of "Harbor at Sabine Pass and Port Arthur 
Canal" and "Sabine-Neches Canal, including Sabine 
River to Orange and Neches River to Beaumont, 
31-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Texas." Sabine Pass is on Gulf of Mexico about 58 miles 
east of Galveston and 280 miles west of Southwest Pass, 
Mississippi River. It connects Sabine Lake with gulf. 
Port Arthur canal extends 7 miles from near upper end 
of Sabine Pass to Port Arthur docks at mouth of 
Taylors Bayou. Near its upper end, Sabine-Neches 
canal joins and extends to mouths of Neches and 
Sabine Rivers. Waterway next extends up Neches River 
to Beaumont and up Sabine River to Orange. (See 
National Ocean Survey Charts 11341, 11342, and 
11343.) 
Previous projects. For details see page 1863 of 
Annual Report for 1915, page 985 of Annual Report for 
1916, and page 873 of Annual Report for 1926. 
Existing project. Existing project dimensions provided 
for in various channels and basins are set forth in 
Table 31-F on channel dimensions. Project also provides 
for two stone jetties at Sabine Pass entrance from 
the gulf, western jetty to be 21,905 feet long and 
eastern jetty 25,310 feet long. Project further provides 
for removal of guard lock in Sabine-Neches Canal, 
construction of suitable permanent protective works 
along Sabine Lake frontage owned by city of Port 
Arthur to prevent dredged material from entering 
Sabine Lake and to prevent erosion of material 
deposited, reconstruction of Port Arthur Bridge, and 
relocation of Port Arthur field office. Mean tidal 
variation at entrance is about 1.5 feet, at Port Arthur 
about 1 foot, and at Orange and Beaumont about 0.5 
foot. Prolonged north winds during winter season have 
depressed water surface as much as 3.4 feet below 
mean low tide while tropical disturbances have caused 
heights as much as 8 feet above mean low tide. 
Existing project is complete. Removal of obstructive 
bridge at Port Arthur was completed May 1969. The 
high level fixed bridge across Sabine-Neches Canal was 
completed October 1970. Deepening project to 40 feet 
was completed April 1972. (See Table 31-E for total cost 
of existing project to September 30, 1989.) 
Local cooperation. Complied with. 
Terminal facilities. See volume 2, Port Series No. 
22 (revised 1981), Corps of Engineers. Facilities are 
considered adequate for present commerce. 
Operations during fiscal year. Routine maintenance 
including mosquito control spraying. A contract 
for dredging Lower Reach-Neches River Channel was 
initiated in August 1989 and incurred $19,000 for 
mobilization costs this fiscal year. (See Table 31-H for 
dredging operations.) 
11. TEXAS CITY CHANNEL, TX 
Location. Texas City is on the mainland of Texas 
on west side of Galveston Bay, about 10 miles 
northwest of city of Galveston. (See National Ocean 
Survey Charts 11324/5.) 
Previous projects. For details see page 1856 of 
Annual Report for 1915. 
Existing project. Provides for channel 40 feet 
deep, 400 feet wide and about 6.75 miles long, from 
Bolivar Roads to a turning basin at Texas City, 40 feet 
deep, 1,000 feet to 1,200 feet wide and 4,253 feet long; 
and an Industrial Canal, 40 feet deep and 300-400 feet 
wide extending a distance of 1.7 miles southwestward 
from the south end of Texas City Turning Basin, and a 
turning basin, 40 feet deep, 1,000 feet wide and 1,150 
feet long. 
Project also provides for easing the approach to the 
turning basin; a pile dike 28,200 feet long, parallel to 
and north of the channel; and a rubble-mound dike, 
27,600 feet long, along the southerly side of the pile 
dike.
The 40-foot channel was completed in June 1967. 
Widening the Texas City Turning Basin; realigning the 
Texas City Turning Basin to a location 85 feet easterly 
from its present position; and enlargement through 
widening and deepening of the Industrial Canal and 
basins was initiated in July 1980 and completed in 
June 1982. The only work remaining is deferred 
construction consisting of widening the Industrial 
Canal from 250 feet to 300 feet at 40 foot depth. 
Work authorized by Water Resources Development 
Act of 1986 would modify the project by providing for 
deepening the Texas City Turning Basin to 50 feet, 
enlarging the 6.7-mile long Texas City Channel to 50 
feet by 600 feet, deepening the existing 800-foot wide 
Bolivar Roads Channel and Inner Bar Channel to 50 
feet, deepening the existing 800-foot wide Outer Bar 
and Galveston Entrance Channel to a 52-foot depth for 
4.1 miles at a width of 800 feet and an additional reach 
at a width of 600 feet to the 52 foot contour in the Gulf 
of Mexico. Establishment of 600 acres of wetland and 
development of water-oriented recreational facilities on 
a 90-acre enlargement of the Texas City Dike are also 
proposed. At the request of local sponsor, City of Texas 
City, the project has been placed in the "deferred" 
category. (See Table 31-E for total cost of existing 
project to September 30, 1989.) 
Under ordinary conditions mean tidal range is 
about 1.3 feet and extreme range is about 2 feet. Height 
of tide is dependent largely on the wind and during 
strong "northers" water surface may be depressed 2 
feet below mean low tide. Estimated cost for new work 
is $123,300,000 Federal (Corps), excluding expenditures 
on previous projects, and $74,393,700 non-Federal, 
including $62,027,741 contributed funds, $248,000 work 
contribution, $427,959 lands, $10,737,000 levees and 
spillways, $6,000 for removal of barge mooring facilities 
from Snake Island, $561,000 for berthing areas, and 
$386,000 relocations. 
Local cooperation. Fully complied with for completed 
work. For work authorized by the Water 
Resources Development Act of 1986, local interests are 
required to provide levees for disposal areas and 
wetlands; relocate utilities, roads, and other facilities, 
except railroad bridges; provide berthing areas; pay 
one-half of the separable and joint costs allocated to 
recreation; and bear all costs of operation, maintenance 
and replacement of recreation facilities, and, during 
construction, pay 25 percent of the costs allocated to 
deep-draft navigation to a depth of 45 feet plus 50 
percent of the costs allocated to deep-draft navigation 
deeper than 45 feet; pay an additional 10 percent of the 
31-8

GALVESTON, TEXAS, DISTRICT 
costs allocated to deep-draft navigation within a period 
of 30 years following completion if not offset by credit 
allowed for lands, easements, rights-of-way, relocations 
and disposal areas; and pay 50 percent of the costs 
incurred for operation and maintenance below the 
45-foot depth. 
Terminal facilities. Privately owned terminal 
facilities are on the mainland at inner end of this 
channel and are considered adequate for existing 
commerce. A deep-draft channel and turning basin 
extend about 1.9 miles southwestward from south end 
of Texas City Turning Basin have been constructed by 
local interests. See Port Series No. 23 (revised 1979), 
Corps of Engineers. 
Operations during fiscal year. New Work: See 
Section 32, Planning and Engineering. 
Maintenance: Routine maintenance. (See Table 
31-H for dredging operations.) 
12. TRINITY RIVER AND 
TRIBUTARIES, TX 
Location. The main stem of the Trinity River is 
formed at Dallas by the confluence of the West Fork 
and the Elm Fork at river mile 505.5. The mouth of the 
Trinity is about one-half mile west of Anahuac, Texas. 
(See Geological Survey base map, Texas, scale 
1:500,000.) 
Previous project. For details of abandoned locks 
and dam construction see page 986 of Annual Report 
for 1932. 
Existing project. See individual detailed reports 
on Anahuac Channel, Channel to Liberty and 
Wallisville Lake. Project includes the existing Federal 
project designated as "Mouth of Trinity River, Texas," 
which was completed in 1907 at a cost of $80,000 (no 
cost to local interest). Project is not being maintained. 
(See Table 31-E for total cost of existing project to 
September 30, 1989.) 
Local cooperation. See individual detailed reports 
on Channel to Liberty and Wallisville Lake. There is no 
local cooperation required for Anahuac Channel. 
Terminal facilities. Privately owned wharves and 
piers at Anahuac, Moss Bluff, Wallisville, and Liberty, 
Texas, are adequate for existing commerce. 
12A. ANAHUAC CHANNEL, TX 
Location: Extends from 6-foot depth in Galveston 
Bay to Anahuac, Texas, opposite mouth of Trinity 
River 38 miles north of Galveston, Texas. (See National 
Ocean Survey Chart 11323.) 
Existing project. No project dimensions authorized 
by 1905 River and Harbor Act. A 6- by 80-foot 
channel, 16,000 feet long was dredged in 1905. At 
present a 6- by 100-foot channel is maintained. Under 
ordinary conditions tidal range is 0.6 to 1.2 feet. Height 
of tide is dependent largely on wind. Strong north 
winds depress water surface 1.5 feet below mean sea 
level. Latest published map is in House Document 440, 
56th Congress, 1st Session. Project was completed in 
1911. 
Local cooperation. None required. 
Terminal facilities. Privately owned wharves and 
piers are the only terminal facilities at Anahuac. 
Operations during fiscal year. Routine maintenance. 
12B. CHANNEL TO LIBERTY, TX 
Location. Improvement is located in Galveston 
Bay and tidal reach of lower Trinity River. (See 
Geological Survey Maps for Anahuac, Cove, Moss Bluff, 
and Liberty, Texas.) 
Previous projects. For details see page 986 of 
Annual Report for 1932. 
Existing project. Provides for a 6-foot channel 
from Anahuac to Liberty which was completed in 1925. 
A navigable channel from the Houston Ship Channel 
near Red Fish Bar in Galveston Bay to Liberty, Texas, 
with depth of 9 feet and width of 150 feet, extending 
along the east shore of Trinity Bay to the mouth of the 
Trinity River at Anahuac, thence in the river channel 
to a turning basin at Liberty, Texas, and a protective 
embankment along the west side of the channel in 
Trinity Bay. 
The 6-foot Channel to Liberty was completed in 
1925. The 9-foot Channel to Liberty has been dredged 
from junction with Houston Ship Channel to a point 
one mile below Anahuac, Texas. Work remaining 
consists of dredging a 9- by 150-foot channel from one 
mile below Anahuac, Texas to Liberty, Texas. 
Local cooperation. Fully complied with for portion 
of "Channel to Liberty" between Houston Ship 
Channel and 1 mile below Anahuac, Texas, as required 
by 1946 River and Harbor Act (H. Doc. 634, 79th Cong., 
2nd Sess.), but not complied with for remaining portion 
of "Channel to Liberty" as required by River and 
Harbor Act of 1945 (H. Doc. 403, 77th Cong., 1st Sess.) 
at an estimated total cost of $550,000, of which 
$460,000 is for lands and rights-of-way and $90,000 for 
pipeline relocations for 9- by 150-foot channel. 
Terminal facilities. Privately owned wharves and 
docks at Anahuac, Wallisville, Texas Gulf Sulphur Co.'s 
slip, Moss Bluff and Liberty, Texas, are adequate for 
existing commerce. 
Operations during fiscal year. Routine maintenance 
including mosquito control spraying. (See Table 
31-H for dredging operations.) 
12C. WALLISVILLE LAKE, TX 
Location. Dam is at river mile 3.9, about 4 miles 
northwest of Anahuac, Texas. (See National Ocean 
Survey Chart 11323.) 
Existing project. Provides for construction of a 
dam and overflow spillway approximately 8 miles long 
to prevent salinity intrusion and create a 5,600-acre 
reservoir. The maximum pool elevation will be 4 feet 
above National Geodetic Vertical Datum. Project 
provides for an 84 foot by 600-foot navigation lock to 
facilitate navigation on Channel to Liberty. The sill has 
a depth of minus 16 feet below National Geodetic 
31-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Vertical Datum. Project also provides for two recreational 
areas. Dam controls a drainage area of 1,262 
square miles below Livingston Dam (non-Federal 
project at channel mile 99.2) and has a storage capacity 
of 58,000 acre-feet. Under ordinary conditions mean 
tidal range in bay is from 0.6 foot to 1.2 feet. Height of 
tide is dependent largely on wind. Strong northerly 
winds depress water surface 1.5 feet below mean sea 
level. Total estimated cost of authorized project is 
$71,100,000 Federal (Corps). (October 1, 1989 base 
price.) 
A contract for construction of access road, Big Hog 
intake structure, intake canal and access bridge was 
completed in October 1968. Work started in July 1970 
on construction of the lock and dam, roads, diversion 
channel, and navigation channel. Work was suspended 
in February 1973 because of an injunction halting 
construction. Protective work on the lock and dam was 
permitted and was completed in April 1973. An 
exception to the injunction was granted for plugging oil 
wells which was completed in August 1973. Notice of 
appeal to the Court of Appeals for the Fifth Circuit was 
filed in April 1973. In August 1974, the Court of 
Appeals reversed the judgment and remanded the case 
with directions that a revised or supplemental statement 
be prepared and judged anew. Final supplement 
to the Environmental Impact Statement for the 
modified project authorized in the Supplemental Appropriations 
Act, 1983 (PL 98-63) was submitted to the 
Environmental Protection Agency on September 21, 
1983. 
In March 1986, the Court rendered it Memorandum 
of order continuing the injunction and directing the 
Corps to re-commence the administrative process at the 
time when the first departure from standard NEPA 
procedures occurred prior to the 1983 legislative action. 
The Corps and local sponsors perfected an appeal to the 
U.S. Court of Appeals and on May 11, 1987, the Court 
of Appeals ruled in favor of the Corps and dismissed the 
suit in its entirety. 
Local cooperation. Local interest must contribute 
an amount equal to cost allocated to water supply, 
one-half of cost allocated to salinity control and cost 
allocated to recreation less cost of basic facilities and 
less 15 percent of total project cost. Local interest 
reimbursement is estimated at $9,818,000. 
Operations during fiscal year. New Work: Plans 
and specifications for the non-overflow dam, Interstate 
10 to the Lock site, were approved in May 1986. 
Further work has been deferred pending receipt of 
construction funds. 
Maintenance: Ranger surveillance, administration 
of project, and administration of duck blind permit 
program was conducted. 
13. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and Condition Surveys were conducted 
on the following projects: 
Project 
Channel to Port 
Bolivar 
Houston Ship 
Channel 
Cedar Bayou 
Freeport Harbor 
Gulf 
Intracoastal 
Waterway 
Texas City 
Channel 
Brazos Island 
Harbor 
Date of Survey 
Oct 1988 
Jan-Mar 1989 
Jan 1989 
May-Aug 1989 
Jul-Aug 1989 
Jul-Sep 1989 
Aug-Sep 1989 
Fiscal 
Year 
Cost 
$ 18 
2,358 
302 
13,497 
1,135 
7,760 
54,223 
$79,293 
14. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 
Public Law 86-645 (preauthorization). 
107, 
Reconnaissance studies of navigation channel improvements 
on the Sabine River Channel at Orange, 
Texas were completed at a fiscal year cost of $553. 
Studies have been terminated. 
Reconnaissance studies of navigation channel improvements 
on Cedar Bayou at Baytown, Texas were 
continued at a fiscal year cost of $54,674. 
Beach Erosion Control 
15. CORPUS CHRISTI BEACH, TX 
(RESTORATION PROJECT) 
Location. Corpus Christi Beach, a shore area 
having a length of about 2 miles, is located on the west 
side of Corpus Christi Bay in Nueces County at Corpus 
Christi, Texas. (See National Ocean Survey Charts 
11309 and 11311.) 
Existing project. The plan of improvement provided 
for initial restoration of eroded areas of Corpus 
Christi Beach, over a shore length of 1.4 miles, located 
on the easterly side of Rincon Peninsula, with periodic 
nourishment as required. Construction was completed 
in March 1978. Periodic nourishment and construction 
of sand retention groin was completed in November 
1985. Estimated cost of new work is $2,150,000 Federal 
(Corps) and $2,265,000 non-Federal consisting of 
$2,150,000 Contributed funds, $43,000 relocations, and 
$72,000 lands. (October 1, 1987 base price.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Section 934 of 
Water Resources Development Act of 1986 provides for 
extension of nourishment period to 50 years for beach 
nourishment projects. A study is underway to determine 
the appropriateness of such an extended nourishment 
period for the Federal beach nourishment project. 
31-10

GALVESTON, TEXAS, DISTRICT 
Flood Control 
16. BUFFALO BAYOU AND 
TRIBUTARIES, TX 
Location. Improvements are on Buffalo Bayou 
watershed, a part of San Jacinto River watershed, in 
Harris County, west and northwest of city of Houston, 
Texas. (See Geological Survey quadrangle sheets for 
Harris County.) 
Existing project. Provides for improvement of 
Buffalo Bayou and its tributaries above turning basin 
of Houston Ship Channel to control floods for protection 
of city of Houston, and prevent deposition of silt in 
turning basin of ship channel by construction of 
detention reservoirs, enlargement and rectification of 
channels and construction of control works. Estimated 
cost of new work is $150,114,000 Federal (Corps) 
including $11,900,000 for recreational facilities at 
completed projects (Code 713 funds) and $11,214,000 for 
Dam Safety Assurance, and $98,791,000 non-Federal, 
consisting of $86,891,000 for lands and relocations, and 
$11,900,000 contributions for recreational facilities. 
(October 1, 1989 base price.) 
Construction of Barker Dam was completed in 
February 1945. Construction of Addicks Dam and 7.4 
miles of channel rectification downstream from 
Addicks and Barker Dams was completed in October 
1948. Modification of Barker and Addicks Dams 
consisting of gating of two uncontrolled conduits in 
each dam, was completed in 1969. Channel rectification 
on Brays Bayou with an improved channel length of 
25.4 miles was completed in March 1971. Channel 
rectification on White Oak Bayou was completed in 
1976. Major rehabilitation of Addicks and Barker Dams 
to prevent seepage through the embankment was 
completed in 1982. Work remaining consists of rectification 
of approximately 22 miles of main stem of 
Buffalo Bayou. Work under the Dam Safety Assurance 
program was initiated in Fiscal Year 1986. Work to be 
accomplished includes raising approximately 32,400 
feet of Addicks Dam 1 to 3 feet and raising approximately 
57,600 feet of Barker Dam 3 to 5 feet and 
armor-plating low ends of both dams. A contract with 
the city of Houston for cost-sharing in the construction 
of recreation facilities at Cullen Park was entered into 
in November 1981. The lease for approximately 10,534 
acres of land and- water areas was approved in 
February 1983. 
Local cooperation. Section 203, 1954 Flood Control 
Act applies. Local interests have accomplished all 
required local cooperation on Brays Bayou and White 
Oak Bayou. On Buffalo Bayou, local interests purchased 
interests that the United States had in 7 miles 
of rectified channel below Barker and Addicks Dams 
for $256,651. Of the remaining required rights-of-way 
on Buffalo Bayou, local interests have acquired about 
40 percent. About 53 percent of required bridge 
relocations and 3 percent of the required utility 
relocations have been accomplished. Advance of 
$4,400,000 by the Harris County Flood Control District 
was refunded in September 1956. Public Law 86-53 
authorized reimbursement of $38,726 to Galveston, 
Houston and Henderson Railroad Company for bridge 
alterations at Brays Bayou. Non-Federal contributions 
totaled $63,661 for project betterments. Recreation 
development is subject to conditions of non-Federal 
cost-sharing under Federal Water Project Recreation 
Act of 1965. 
Operations during fiscal year. Recreation: Community 
Park West (Phase IB) and the velodrome were 
completed in November 1986. Grading and clearing for 
an archery range was performed by the City of Houston 
in March and April 1987. Work has been initiated on a 
construction contract, awarded for Community Park 
West (Phase 2) in 1988. Harris County Precinct 3, 
Cullen Barker Park, completed Community Park 2 
which includes soccer fields and parking lots. 
Dam Safety Assurance: Raising Main Dam, Barker 
Dam, awarded in June 1986, was financially completed 
with a decrease in cost of $69,361. Contract for armor 
plating the ends of the dams, awarded in May 1987, 
continued at a fiscal year cost of $335,270. Contract for 
construction of concrete T-wall at Outlet, Addicks Dam 
was awarded in December 1988 and continued at a cost 
of $151,820. The contract for raising the Main Dam, 
Barker Dam, awarded in July 1986, was physically 
completed in August 1987, but remains financially 
incomplete due to a pending claim. No cost was 
incurred for this fiscal year. 
Maintenance: Routine operations and maintenance 
at Addicks and Barker Dams. 
17. CLEAR CREEK, TX 
Location. The project is located about midway 
between the two metropolitan centers of Houston, 
Texas, on the north and Galveston-Texas City on the 
south in Harris and Galveston Counties above and 
below existing Clear Lake. 
Existing Project. The authorized plan of improvement 
consists of an improved channel from Mile 3.8 to 
Mile 34.8 to contain within its banks all flood flows up 
to and including that of a 100-year flood. The selected 
plan provides channel enlargement and easing of bends 
within the existing stream from Mile 3.8 to Mile 26.05 
to contain at least the 10-year frequency storm, and 
additional outlet with gated structure from Clear Lake 
to Galveston Bay, restriction of development in the 
residual 100-year flood plain and measures to mitigate 
environmental effects. In 1986, at the request of 
Brazoria County Drainage District No. 4, that portion 
of the project upstream of the Brazoria/Galveston 
County line, approximate improved Mile 18.5, was 
placed in the "inactive" category. Estimated cost for 
new work, excluding "inactive" portion, is $49,900,000 
Federal (Corps) and $41,780,000 non-Federal consisting 
of $4,580,000 cash contributions, $17,100,000 for lands, 
and $20,100,000 for relocations (October 1, 1989 base 
price). 
Local Cooperation. Local sponsors for the project 
are Galveston and Harris counties. The Local Cooperation 
Agreement, executed 30 June 1986, requires local 
interests to provide lands, easements, rights-of-way, 
31-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
and material disposal areas; modify or relocate building, 
pipelines, utilities, roads and other facilities, 
except railroad bridges, where necessary in the construction 
of the project; make a cash contribution for 
mitigation measures consistent with the non-Federal 
share of total project costs without mitigation measures; 
pay five percent of the total costs allocated to 
flood control; and bear all costs of operation and 
maintenance of flood control facilities. 
Operations during fiscal year. Engineering and 
Design is underway. A contract for relocation of the 
Galveston, Houston and Henderson Railroad bridge at 
mile 6.79 was awarded in March 1988. Fiscal year cost 
was $1,222,322. Construction of a second outlet-gated 
structure was initiated in May 1989. Fiscal year cost 
was $287,231. 
18. CYPRESS CREEK, TX 
Location. The project is located north of Houston, 
Texas in Harris County. 
Existing project. The authorized plan of improvement 
consists of enlargement of the lower 29.4 miles of 
the Cypress Creek Channel, incorporating grassed side 
slopes and channel bottom and appropriate erosion 
control measures; application of floodplain management 
techniques in the residual floodplain; construction 
of project-oriented recreation features, including 
11.5 miles of hike-and-bike trails and related facilities 
for health, safety, and public access; and habitat 
management measures on 844 acres of Harris County 
Parkway land, creation of wooded and brush habitat 
along 70 acres of the project right-of-way, acquisition of 
329 acres of wildlife habitat along the creek, and 
creation of 64 acres of ponds and marshes. Estimated 
cost for new work is $89,300,000 Federal (Corps) and 
$30,800,000 non-Federal consisting of $10,600,000 cash 
contribution, $14,500,000 for lands, and $5,700,000 for 
relocations (October 1, 1989 base price). 
Local cooperation. Local sponsor for the project is 
Harris County. Local sponsor is required to provide 
lands, easements, and rights-of-way; modify or relocate 
buildings, pipelines, utilities, roads and other facilities, 
except railroad bridges; provide a cash contribution 
presently estimated at $10,600,000; and bear all costs of 
operation, maintenance, and replacement of flood 
control and recreation facilities. 
Operations during fiscal year. Project is awaiting 
Planning and Engineering funds. 
19. FALFURRIAS, TX 
Location. The city of Falfurrias is located near the 
confluence of Palo Blanco and Cibolo Creeks, intermittent 
streams that drain a 600-square-mile area in south 
Texas. 
Existing project. The authorized plan of improvement 
consists of a 5.6 mile long diversion levee; a 1.8 
mile long pilot channel; a flowage easement of 11,000 
acres of land subject to overflows from the pilot 
channel; and a 0.8 mile long ring levee around the 
sewage treatment plant. Estimated cost for new work is 
$16,600,000 Federal (Corps) and $16,600,000 non- 
Federal consisting of $1,660,000 cash contribution, 
$14,200,000 for lands, and $740,000 for relocations 
(October 1, 1989 base price). 
Local cooperation. The local sponsor would be 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipeline, utilities, roads 
and other facilities, except railroad bridges; provide a 
cash contribution presently estimated at $1,660,000 
and bear all costs of operation, maintenance and 
replacement of flood control facilities. 
Operations during fiscal year. Project is awaiting 
Planning and Engineering funds. 
20. KIRBYVILLE, TX 
Location. The project is located in Southeast Texas 
in the Sabine River basin on Trout Creek and Pin Oak 
Creek in the vicinity of Kirbyville, Texas, about 45 
miles north of Beaumont, Texas. 
Existing project. The plan of improvement is a 
combination channelization and floodplain management 
plan for Trout and Pin Oak Creeks. The 
structural element consists of a slightly enlarged 
channel and clearing and straightening of Trout Creek. 
The non-structural part consists of controls on future 
development in the residual 100-year floodplains along 
Trout and Pin Oak Creeks. Channel improvements in 
Trout Creek begin about 0.8 mile downstream from the 
Jasper-Newton County line and end about 0.4 mile 
upstream from the U.S. Highway 96 bridge. The 
improved, grass-lined channel will be 2.7 miles long, 
and generally follow the existing alignment of Trout 
Creek. A steel sheet pile and riprap drop structure will 
be constructed on Pin Oak Creek near its confluence 
with Trout Creek. Drainage culverts will be constructed 
along the improved channel on Trout Creek to 
facilitate lateral drainage and control erosion. Work 
includes some alterations to a Santa Fe Railroad bridge 
to accommodate the project and a new roadway bridge 
providing approximately 2,000 square feet of opening 
for passage of floodwaters. Estimated cost for new work 
is $1,458,000 Federal (Corps) and $785,000 non-Federal 
consisting of $90,000 cash contribution, $695,000 for 
lands and relocations. (1 October 1989 base prices) 
Local cooperation. Local sponsor for the project is 
the City of Kirbyville, Texas. A Local Cooperation 
Agreement was signed by the sponsor in August 1987. 
Operations during fiscal year. A contract for 
channelization, awarded in August 1989, cost $106,195. 
21. LOWER RIO GRANDE BASIN, TX 
Location. The project is located in Willacy, 
Hidalgo and Cameron Counties. The basin is bounded 
on the east by the Gulf of Mexico, on the south by the 
Rio Grande which forms the international boundary 
between the United States and Mexico, on the west by 
Starr County, and on the north by Brooks and Kenedy 
Counties. 
Existing project. The authorized plan of improvement 
consists of channel improvements to: (1) provide 
drainage protection for the area in Hidalgo and Willacy 
31-12

GALVESTON, TEXAS, DISTRICT 
Counties north of U.S. Highway 83, and for the area 
between U.S. Highway 83 and the Rio Grande in 
Hidalgo County; and (2) provide flood protection for the 
cities of McAllen, Edinburg, Raymondville, Edcouch, 
La Villa, and Lyford. Estimated cost for new work is 
$136,200,000 Federal (Corps) and $76,700,000 non- 
Federal consisting of $14,900,000 cash contribution, 
$32,300,000 for lands, and $29,500,000 for relocations 
(October 1, 1989 base price). 
Local cooperation. Local sponsors for the project 
are Hidalgo County Drainage District No. 1 and 
Willacy County Drainage District No. 1. In accordance 
with the cost-sharing and financing concepts of the 
Water Resources Development Act of 1986, local 
interests are required to provide lands, easements, and 
rights-of-way; modify or relocate buildings, pipelines, 
utilities, roads and other facilities, except railroad 
bridges; provide a cash contribution presently estimated 
at $14,900,000, and bear all costs of operation, 
maintenance, and replacement of flood control facilities.
Operations during fiscal year. Phase I General 
Design Memorandum was approved by the Board of 
Rivers and Harbors in April 1983. Project is awaiting 
Planning and Engineering funds. 
22. PORT ARTHUR AND VICINITY, 
TX (HURRICANE-FLOOD 
PROTECTION) 
Location. Port Arthur is on west shore of Sabine 
Lake in extreme southeast part of Texas, about 14 
miles from the gulf. Area under consideration is 
comprised of about 38,500 acres, and includes cities of 
Port Arthur and Groves, towns of Griffin Park, Pearl 
Ridge, and Lakeview, and adjacent industrial areas. 
Existing project. Authorized plan provides for 
raising and reconstructing 6.3 miles of existing concrete 
and steel sheet-pile seawall; constructing 0.3 mile 
of new concrete and sheet-pile seawall; raising and 
improving 3.0 miles of existing earth levees; constructing 
20.3 miles of new earth levees and constructing five 
interior drainage pumping plants. Raising and 
strengthening of levees surrounding Gulf Oil 
Company's fresh water reservoir was placed in the 
"inactive" category in December 1980. The project was 
initiated in March 1966 and the active portion of the 
project was completed in 1984. Estimated cost for new 
work, excluding "'inactive" portion, is $59,703,000 
Federal (Corps) and $26,036,000 non-Federal consisting 
of $16,016,000 cash contributions, $3,403,000 for lands, 
$6,168,000 for relocations, and $449,000 for pumping 
station betterments and levee realignment betterments. 
Local cooperation. Fully complied with. 
Operation during fiscal year. A severe settlement 
problem exists in the Chevron Sabine Road Tank 
Farm area. The Galveston District continued to 
conduct investigations and monitoring of the settlement 
to help determine appropriate corrective actions 
of Federal interest. 
23. SIMS BAYOU, TX 
Location. The project is located in Harris County, 
in the southern portion of Houston, Texas. 
Existing project. The authorized plan of improvement 
provides for enlargement and rectification, with 
appropriate erosion control measures, of 19.31 miles of 
Sims Bayou to provide 25-year flood protection; environmental 
measures and riparian habitat improvement 
along the entire alignment; and recreational development 
to include 27 miles of hike and bike trails 
connecting to existing public parks, together with 
picnic, playground, and other leisure facilities. Estimated 
cost for new work is $163,700,000 Federal 
(Corps) and $79,600,000 non-Federal consisting of 
$14,120,000 cash contributions, $32,995,000 for lands, 
$30,214,000 for relocations and $2,271,000 other cost 
(October 1, 1989 base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. In accordance 
with the cost-sharing and financing concepts reflected 
in the Water Resources Development Act of 1986, local 
interests are required to provide lands, easements, and 
rights-of-way; modify or relocate buildings, pipelines, 
utilities, roads, and other facilities, except railroad 
bridges, where necessary for the construction of the 
project; pay one-half of the separable and joint costs 
allocated to recreation; and bear all costs of operation, 
maintenance and replacement of recreation facilities; 
and pay 12 percent of the costs allocated to flood 
control to bring the total non-Federal share of flood 
control costs to 25 percent; and bear all costs of 
operation, maintenance and replacement of flood 
control facilities. 
Operations during fiscal year. See Section 32, 
Planning and Engineering. 
24. TAYLORS BAYOU, TX 
Location. Watershed of Taylors Bayou is in 
extreme southeast corner of Texas adjoining basins of 
Neches River and Sabine Lake on the east. City of Port 
Arthur is about 8 miles from the main stream of 
Taylors Bayou. 
Existing project. Improvement consists of enlarging 
and rectifying approximately 53 miles of natural 
and artificial channels on Taylors Bayou and tributary 
water courses. Phase I consists of constructing a gated 
structure to prevent saltwater intrusion and 2.9 miles 
of new diversion channel and enlarging 1.8 miles of 
Gulf Intracoastal Waterway and a 1.9 mile section of 
the Outfall Canal. Phase II consists of enlarging 6.0 
miles of Taylors Bayou, 14.3 miles of Hillebrandt 
Bayou, 1.5 miles of Pivotot Bayou, 2.3 miles of Bayou 
Din, and 3.5 miles of Willow Marsh Bayou. Phase III 
consists of enlarging 7.0 miles of North Fork Taylors 
Bayou, 7.8 miles of South Fork Taylors Bayou and 4.4 
miles of Mayhaw Bayou. The Phase III portion of the 
project was placed in the "inactive" category in 
November 1980. Initial contract on the "active" portion 
31-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
of the project was awarded in August 1982. Estimated 
cost for new work, excluding inactive portion, is 
$40,800,000 Federal (Corps) and $22,300,000 non- 
Federal, including $14,000,000 cash contribution, 
$4,400,000 lands, and $3,900,000 for relocations. (October 
1, 1989 base price.) 
Local cooperation. Section 204, 1965 Flood Control 
Act, applies. 
Operation during fiscal year. Contract for channel 
rectification, Hillebrandt Bayou Sta. 4+07.12 to 
Sta. 86+30, awarded in September 1988, had a fiscal 
year cost of $1,086,363. Installation of a cathodic 
protection system for the salt water barrier was 
completed at a fiscal year cost of $82,200. Construction 
of the water control structure at Star Lake was 
initiated in December 1988 and continued at a cost of 
$201,033. Channel rectification of Hillebrandt Bayou 
Sta. 97 + 90 to Sta. 224+00 was initiated in June 1989 
and continued at a cost of $870,480. In July 1989 a 
contract for channel rectification of Hillebrandt Bayou 
Sta. 224 + 00 to Sta. 350 + 00 was awarded and continued 
for a fiscal year cost of $236,000. 
25. TEXAS CITY AND VICINITY, TX 
(HURRICANE-FLOOD 
PROTECTION) 
Location. On the west and southwest shore of 
Galveston Bay, about 9 miles northwest of Galveston, 
Texas. Project fronts on the west side of Galveston Bay 
and protects a land area of about 36 square miles. 
Existing project. Plan provides for construction of 
improvements for control of storm tides. Improvements 
consist of 15.9 miles of new levees, 1.3 miles of concrete 
floodwall, related drainage and stoplog structures, one 
tide control structure, and two pumping plants. The 
project was initiated in 1962, and physically completed 
in 1987; however, remedial measures are required to 
approximately 1.7 miles of levee toe to avoid further 
erosion. Estimated cost for new work is $40,300,000 
Federal (Corps) and $17,600,000 non-Federal, including 
$15,180,000 cash contribution, $1,071,000 work contribution, 
and $1,349,000 for lands, and $256,000 for 
ramps in lieu of closure structures and increased low 
flow pumping capacity for La Marque Pumping Plant. 
Local cooperation. Fully complied with. 
Operations during fiscal year. No work was 
performed. 
26. UPPER WHITE OAK BAYOU, TX 
Location. The project is located in Harris County, 
in the northwest portion of Houston, Texas. 
Existing project. The authorized plan of improvement 
provides for channel improvements in White Oak 
Bayou from Mile 10.7 to Mile 19.9; on Cole Creek from 
its mouth to Mile 4.9; and on Vogel Creek from its 
mouth to Mile 4.5. In addition, the project includes 
regulation of the residual 100-year flood plains along 
these streams and recreational development on project 
lands along White Oak Bayou, between Mile 14.6 and 
Mile 18.3. Estimated cost for new work is $70,200,000 
Federal (Corps) and $23,900,000 non-Federal consisting 
of $13,100,000 cash contribution, $6,920,000 for lands, 
and $3,880,000 for relocations (October 1, 1987 base 
price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. In accordance 
with the cost-sharing and financing concepts reflected 
in the Water Resources Development Act of 1986, local 
interests are required to provide lands, easements, and 
rights-of-way; modify or relocate buildings, pipelines, 
utilities, roads, and other facilities, except railroad 
bridges; make a cash contribution, which when combined 
with lands required for recreation equals one-half 
of the separable and joint costs allocated to recreation; 
and during construction, pay 13 percent of the costs 
allocated to flood control to bring the total non-Federal 
share of flood control costs to 25 percent. 
Operation during fiscal year. See Section 32, 
Planning and Engineering. 
27. VINCE AND LITTLE VINCE 
BAYOUS, TX 
Location. Watershed of Vince Bayou and tributary, 
Little Vince Bayou, has an area of about 17 
square miles and lies entirely within Harris County. 
Vince Bayou is a minor tributary of Buffalo Bayou in 
San Jacinto River Basin on upper gulf coast of Texas. 
Existing project. Project provides for enlarging 
and rectifying channel of Vince Bayou from mouth to a 
point about 7.3 miles upstream and Little Vince Bayou 
from mouth to a point about 4.2 miles upstream, a total 
distance in both streams of about 11.5 miles. The 
project was initiated in 1968. All work on Vince Bayou 
is complete. Estimated cost for new work is $19,347,000 
Federal (Corps) and $17,300,000 non-Federal, consisting 
of $5,100,000 for lands and $12,200,000 for relocations. 
(October 1, 1989 base price.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Contract for 
channel rectification on Little Vince Bayou was 
awarded in October 1988. Fiscal year cost was $216,270. 
31-14

GALVESTON, TEXAS, DISTRICT 
28. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Inspections of completed projects operated and 
maintained by local interests were made on the 
following projects. Fiscal year cost was $152,603. 
Date of 
Project 
Lavaca River Flood Protection, 
Halletsville, TX Oc 
Port Arthur Hurricane Flood 
Protection Project, TX NovE 
Vince Bayou - Flood Control 
Project, TX DecE 
GIWW - Chocolate Bayou Salt Water 
Barrier, TX Jai 
Freeport Hurricane-Flood Protection 
Project, TX 
Three Rivers Local Flood Protection, TX 
Corpus Christi Beach-Beach Protection, TX 
Mooring Dolphins Vicinity of 
Port Ingleside, TX 
Texas City Hurricane Flood Protection 
Project, TX 
Galveston Seawall, TX 
Brays Bayou Channel Rectification 
Project, TX 
Taylors Bayou Salt Water Barrier, TX A 
Big Hog Bayou, Wallisville, TX Sept( 
White Oak Bayou Channel 
Rectification Project, TX Sept( 
Inspection 
ctober 1988 
ember 1988 
ember 1988 
Emergency flood control - repair, flood fighting, and 
rescue work (Public Law 99, 84th Congress and 
antecedent legislation): 
Cost was $280,222 for disaster preparedness and 
$29,541 for emergency operations. 
Rehabilitation work for Brays and White Oak 
Floodways cost was reduced by $7,780. 
30. EMERGENCY STREAM BANK 
AND SHORELINE EROSION 
WORK AND SNAGGING AND 
CLEARING ACTIVITIES UNDER 
SPECIAL AUTHORIZATION 
Stream bank and shoreline erosion activities pursunuary 
1989 ant to Section 14 of the 1946 Flood Control Act, Public 
Law 525, as amended: 
April 1989 Feasibility studies of shoreline erosion control for 
May 1989 State Highway 111 at Lake Texana, Texas continued at 
May 1989 a fiscal year cost of $8,744. 
May 1989 Feasibility studies of streambank protection at U.S. 
Highway 190 Bridge near Merryville, Louisiana were 
M laa Q initiated at a fiscal year cost of $19,776. 
July 1989 
July 
august 
ember 
1989 
1989 
1989 
ember 1989 
29. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205 of 
1970 Flood Control Act, Public Law 858, 80th Congress, 
as amended: 
Construction of a flood control project at Kirbyville, 
Texas was initiated at a fiscal year cost of $123,921. 
Feasibility studies of a flood control project on West 
Gum Bayou at Dickinson, Texas were completed at a 
fiscal year cost of $13,790. 
Reconnaissance studies of flood control projects on 
the Lower Guadalupe River at Victoria, Texas, and on 
Tranquitas Creek at Kingsville, Texas were completed 
at fiscal year costs of $3,930 and $34,447 respectively. 
Both studies have been terminated. 
Reconnaissance studies of flood control projects on 
the Lower Guadalupe River at Victoria, Texas and on 
Petronila Creek at Discoll, Texas were continued at 
fiscal year costs of $18,566 and $48,160 respectively. 
Initial reconnaissance studies of flood control 
projects on the Arroyo Colorado at Rio Hondo, Texas, 
on Oso Creek, Texas, and on the Guadalupe River, 
Texas (Railroad Bridges) were completed at fiscal year 
costs of $7,218, $9,164, and $10,000 respectively. All 
studies have been terminated. 
Initial reconnaissance studies at Crystal Beach, 
Texas, were initiated at a fiscal year cost of $11,777. 
Snagging and clearing activities for flood control 
pursuant to Section 208 of the Flood Control Act of 
1954, Public Law 780, as amended: 
No studies of clearing and snagging for flood 
control purposes were conducted this fiscal year. 
General Investigations 
31. SURVEYS 
Fiscal year costs were $1,742,573 of which $491,154 
was for navigation studies, $860,490 was for flood 
damage prevention studies, $249,083 was for Review of 
Completed Projects, $5,843 was for coordination with 
other agencies, $50,839 was for Special Investigations, 
$17,000 for Interagency Water Resources, and $68,165 
was for Planning Assistance to States, also, $234,633 
was expended from contributed funds for the Cameron 
County flood damage prevention study. Local sponsor's 
in-kind services for Cameron County study were 
$263,950 for fiscal year 1988 and $233,680 for fiscal 
year 1989. 
32. PLANNING AND ENGINEERING 
Brazos Island Harbor, Texas (42-Foot Project) - The 
project will provide for enlargement of the entrance 
channel from deep water in the Gulf of Mexico to the 
Laguna Madre to a depth of 44 feet and a width of 400 
feet; enlargement of the Turning Basin Extension to a 
point 800 feet beyond the grain elevator to a depth of 
42 feet at widths varying from 325 to 400 feet; removal 
of Brownsville Navigation District Wharves 5, 6, and 9 
to permit widening of the adjacent portion of the 
Turning Basin to 1,200 feet at a depth of 36 feet. 
Estimated planning and engineering estimate is 
$2,050,000. Planning and engineering studies were 
initiated in Fiscal Year 1987. Fiscal year costs were 
$376,918. 
31-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Channel to Victoria, Texas - The project will 
provide for enlarging the existing Channel to Victoria 
from a depth of 9 feet and width of 100 feet to a depth 
of 12 feet and a width of 125 feet, the same dimensions 
as the Gulf Intracoastal Waterway, with disposal of the 
dredged materials in upland areas. In addition, the 
project includes a 60-acre confined disposal area in San 
Antonio Bay which would be developed as a bird 
rookery, and creation of additional marsh along the 
landlocked reach of the channel. Estimated planning 
and engineering estimate is $650,000. Planning and 
engineering studies were initiated in Fiscal Year 1989. 
Fiscal year costs were $184,380. 
Sims Bayou at Houston, Texas - The project will 
provide for enlargement and rectification, with appropriate 
erosion control measures, of 19.31 miles of Sims 
Bayou to provide flood protection, environmental 
measures and riparian habitat improvement along the 
entire alignment; and recreational development consisting 
of hike-and-bike trails connecting public parks, 
as well as picnic and other day-use facilities. Estimated 
planning and engineering estimate is $2,300,000. 
Planning and engineering studies were initiated in 
Fiscal Year 1986. Fiscal year costs were $728,079. 
Texas City Channel, Texas (50-foot Project) - The 
project will provide for enlargement of Texas City 
Channel to 50 feet deep and 600 feet wide over its 6.7 
mile length and enlargement of Galveston Harbor 
Channel to 50-52 feet deep and 800 feet wide over the 
10.5 mile length. The Galveston Entrance Channel 
would be extended 12.5 miles to the 52-foot bottom in 
the Gulf of Mexico. A 50-year dredged material disposal 
plan will be provided by a combination of containment 
of dredged material on Snake Island, establishment of 
600 acres of wetland, enlargement of Texas City Dike, 
and deposition of dredged material in the Gulf. Ninety 
acres of water-oriented recreational facilities on the 
Texas City Dike are included as a part of the proposed 
project. At the request of local sponsor, City of Texas 
City, the project has been placed in the "deferred" 
category. Estimated planning and engineering estimate 
is $2,000,000. Planning and engineering studies were 
initiated in Fiscal Year 1986. Fiscal year costs were 
$193,258. 
Upper White Oak Bayou and Tributaries, vicinity 
of Houston, Texas - The project will provide for 
channel improvements on White Oak Bayou from Mile 
10.7 to Mile 19.9; on Cole Creek from Mile 0 to Mile 4.9; 
and on Vogel Creek from Mile 0 to Mile 4.5, for a total 
of 18.6 miles. Project also provides for flood plain 
zoning and regulation on the residual 100-year flood 
plains on White Oak Bayou from Mile 19.9 to near Mile 
25.5; on Cole Creek from Mile 4.9 to near Mile 6.9; and 
on Vogel Creek from Mile 4.5 to near Mile 6.5; and 
includes recreational development along White Oak 
Bayou from near Mile 14.6 to near Mile 18.3. Harris 
County Flood Control District, sponsor, is proceeding 
with a schedule for construction of the project that is 
far in advance of the schedule for the Federal project. 
As a result of their schedule, the Federal project would 
be about 75 percent complete before scheduled construction 
by the Government could commence. Therefore, 
the project has been placed in the "inactive" 
category. Estimated planning and engineering estimate 
is $3,900,000. Planning and engineering studies were 
initiated in 1982. Fiscal year costs were $10,757. 
33. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management and technical services 
were performed at a cost of $37,601 and $106,154, 
respectively. 
Hydrologic studies cost $19,555. 
31-16

GALVESTON, TEXAS, DISTRICT 
TABLE 31-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
1. Aquatic Plant Control 
(Southwestern Division) 
1965 Act 
2. Brazos Island Harbor, 
TX 
3. Cedar Bayou, TX 
4. Corpus Christi Ship 
Channel, TX 
(Regular Funds) 
(Contributed Funds) 
5. Freeport Harbor, TX 
6. Galveston Harbor and 
Channel, TX 
7. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL and 
the Mexican Border 
(Galveston District) 
8. Houston Ship Channel, 
TX 
(Regular Funds) 
Total Cost To 
FY 86 FY 87 FY 88 FY 89 Sep. 30, 198927 
350,000 410,000 
423,289 218,283 
- 263,000 
- 201,963 
862,876 4,324,300 
807,209 4,384,707 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Minor Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
Minor Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
280,000 
362,827 
330,000 
337,341 
489,000 
376,459 
- 50,000 
- 43,758 
5,186,000 6,370,000 
5,820,870 5,197,915 
1,500,800 1,045,780 
1,501,507 1,025,178 
900,000 789,000 
966,167 737,743 
1,400,000 6,664,000 
1,312,905 5,822,023 
1,774,100 2,725,000 
1,752,328 2,744,490 
280,00 
377,07 
500,00 
376,91 
1,598,70 
1,711,33 
670,50 
676,44 
6,441,00 
7,018,98 
2,692,30 
2,704,98 
948,00 
858,21 
9,758,0C 
3,556,54 
3,400,40 
3,403,67 
2,151,100 256,800 4,520,000 2,515,0( 
2,168,744 252,486 4,494,522 2,540,95 
1,445,000 
1,407,010 
14,157,400 
13,885,258 
600,000 
601,461 
11,807,893 
12,291,328 
2,531,000 
2,299,493 
13,404,000 
13,179,818 
5,339,0( 
4,953,4 
15,842,6( 
15,954,3E
)0 2,918,1001 
'5 2,836,9031 
)0 12,950,5022 
.8 12,773,7252 
)0 42,126,3613 
16 42,126,3553 
- 2,170,080 
- 2,170,080 
- 681,2634 
- 681,2634 
)0 2,809,8165 
14 2,809,5185 
)0 76,635,3596 
34 75,624,3736 
)0 88,473,6587 
34 88,463,999' 
- 3,576,684 
- 3,576,684 
)0 6,279,088 
L5 5,892,972 
)0 20,834,1528 
[1 13,694,5278 
)0 50,138,7159 
77 50,136,9539 
- 8,935 
- 8,935 
- 29,096,39210 
- 29,096,39210 
)0 83,103,72311 
i3 83,090,80511 
- 7,969,329 
- 7,969,329 
)0 69,723,30312 
38 68,994,90812 
)0 236,458,64813 
54 236,229,83814 
- 434,638 
- 434,638 
- 835,873 
- 835,873 
- 35,760,38215 
- 35,760,38215 
31-17 
5,186,000 
4,433,754 
3,958,900 
4,158,250 
200,000 
63,401 
55,000 
143,688 
790,100 
801,255

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
8. (Continued) 
9. Matagorda, Ship 
Channel, TX 
(Regular Funds) 
10. Sabine-Neches 
Waterway, TX 
(Regular Funds) 
11. Texas City Channel, TX 
12. Trinity River and 
Tributaries, TX 
(Includes Wallisville) 
15. Corpus Christi Beach, 
TX (Restoration Project) 
(Contributed Funds) 
16. Buffalo Bayou and 
Tributaries, TX 
17. Clear Creek, TX 
(Contributed Funds) 
22. Port Arthur and 
Vicinity, TX Hurricane- 
Flood Protection 
(Regular Funds) 
(Contributed Funds) 
Funding 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Recreation: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
Dam Safety: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Total Cost To 
FY 86 FY 87 FY 88 FY 89 Sep. 30, 198927 
1,517 
31-18 
- 4,787 22,256 
16,291,97525 
16,264,68725 
3,303,100 4,573,100 5,370,000 5,807,400 113,926,12316 
3,269,155 4,625,738 4,839,291 6,258,038 113,833,16516 
- - - - 18,058,77717 
- - - - 18,058,77717 
3,110,545 1,898,700 1,315,000 2,668,600 42,351,888 
3,056,503 1,954,301 1,280,648 2,691,027 42,334,010 
- - - - 56,136,81518 
- - - - 56,136,81518 
4,859,500 8,801,900 5,766,000 2,191,200 146,659,62019 
4,930,766 8,830,303 5,736,919 2,215,722 146,652,69019 
287,000 800,000 550,000 169,500 15,131,97220 
266,519 789,006 552,610 193,258 15,126,86520 
1,955,900 756,300 1,624,000 25,900 23,614,46121 
1,963,470 755,245 1,611,594 38,062 23,613,09321 
- - - - 726,158 
- - - - 726,158 
196,000 96,000 - 78,000 29,279,67622 
182,708 49,190 43,479 26,757 29,160,70622 
1,930,800 856,800 626,500 426,400 11,686,30323 
2,001,202 811,757 666,001 395,234 11,629,66823 
(-)120,000 - 90,000 - 2,120,641 
264,506 9,337 14,621 79,360 2,099,727 
(-)60,000 - - - 2,038,345 
280,045 9,444 309 - 2,009,710 
- - - - 57,206,32424 
- - - - 57,206,32424 
- - - - 377,804 
98,400 86,703 (-)200 (-)12,151 358,185 
1,452,700 1,166,600 1,250,000 1,291,000 20,946,413 
1,442,566 1,196,542 1,201,080 1,288,343 20,858,885 
- - - - 12,475,000 
- - - - 12,475,000 
1,471,000 5,210,000 2,696,000 1,587,000 10,964,000 
623,544 2,902,172 5,477,640 725,846 9,729,202 
350,000 579,000 2,740,000 1,700,000 8,220,361 
331,139 572,718 1,031,961 2,394,973 7,158,453 
- 300,000 100,000 100,000 500,000 
- 200,000 110,000 28,723 338,723 
- - 50,000 150,000 59,902,509 
(-)2,599 26 13,514 67,473 59,763,053

GALVESTON, TEXAS, DISTRICT 
TABLE 31-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 198927 
23. Sims Bayou, TX New Work: 
Approp. 383,000 552,000 850,000 605,000 2,390,000 
Cost 300,776 508,887 809,881 728,079 2,347,623 
24. Taylors Bayou, TX New Work: 
(Regular Funds) Approp. 3,594,000 4,700,000 2,730,000 2,763,000 24,730,198 
Cost 3,749,224 4,767,108 1,794,939 2,712,071 23,534,298 
(Contributed Funds) New Work: 
Contrib. 1,200,000 1,500,000 1,000,000 735,000 7,034,000 
Cost 1,138,507 1,745,394 294,303 870,703 6,429,646 
25. Texas City and Vicin- New Work: 
ity, TX Hurricane-Flood Approp. 300,000 - - 70,000 38,052,400 
Protection Cost 639,007 138,296 4,693 65,512 38,018,805 
(Regular Funds) 
(Contributed Funds) New Work: 
Contrib. 175,000 15,000 - 26,000 14,251,10026 
Cost 354,683 137,455 1,851 21,455 14,242,58026 
26. Upper White Oak New Work: 
Bayou, TX Approp. 253,000 539,000 625,000 (-)444,700 972,300 
Cost 237,984 441,756 281,803 10,757 972,300 
27. Vince and Little Vince New Work: 
Bayous, TX Approp. 3,145,000 2,800,000 1,333,000 61,000 19,347,100 
Cost 3,203,495 2,464,974 1,744,821 288,880 19,263,328 
1 Excludes $810,144 credit for contributed work. 
2 Includes $675,855 for previous projects. In addition, 
$1,806,619 expended from contributed funds, of which 
$123,361 was for previous projects. 
3 In addition, $14,692 expended from contributed 
funds. 
4 Includes $39,087 for previous projects. In addition 
$25,000 expended from contributed funds. 
5 Includes $69,784 for previous projects. 
6 Includes $1,372,534 for previous projects. Includes 
$456,515 for Sec. 107 project for Port Aransas Breakwaters. 
In addition $768 expended from contributed funds for Port 
Aransas Breakwaters. 
v Includes $62,452 for previous projects. In addition, 
$445,269 expended from contributed funds. 8Includes $147,098 for previous projects. In addition, 
$4,271,003 expended from contributed funds. ($389,825 on 45' 
project.) 
9In addition, $229,311 expended from contributed 
funds. 
1�Includes $8,421,996 for previous projects. In addition, 
$3,648,932 expended from contributed funds. 
11Includes $86,126 for previous projects. In addition, 
$2,116,719 expended from contributed funds. 
12Includes $706,709 for previous projects. Includes 
Sec. 107 projects for Port Isabel Small Boat Basin ($46,559); 
Port Isabel Side Channel ($8,414); Offatts Bayou ($356,466); 
and Channel to Aransas Pass ($658,573). In addition contributed 
funds expended for Port Isabel Small Boat Basin 
($46,559); Offatts Bayou ($49,665); Channel to Aransas Pass 
($347,950); Chocolate Bayou ($658,310); and Mouth of Colorado 
River ($2,719,106). 
13Includes $1,526,564 for previous projects. In addition 
$22,672 expended from contributed funds. Includes 
following amounts for tributary channels separately funded 
starting in fiscal year 1987: Channel to Victoria $3,565,100. 
Channel to Aransas Pass $2,600. Chocolate Bayou Channel 
$1,091,500. Includes following amounts for tributary channels 
separately funded starting in fiscal year 1989: Channel to 
Harlingen $743,200. Channel to Port Mansfield $513,300. 
14Includes $1,526,564 for previous projects. In addition 
$22,672 expended from contributed funds. Includes 
following amounts for tributary channels separately funded 
starting in fiscal year 1987: Channel to Victoria $3,525,887, 
Channel to Aransas Pass $2,600, Chocolate Bayou Channel 
$1,091,500. In addition $566,875 was expended from contributed 
funds for Chocolate Bayou Channel. Also includes 
amounts for tributary channels separately funded starting in 
fiscal year 1989: Channel to Harlingen $733,847. Channel to 
Port Mansfield $507,955. 
'sIncludes $4,105,157 for previous projects. In addition, 
$2,591,939 expended from contributed funds, of which 
$1,209,179 was for previous projects. 
'6Includes $1,213,142 for previous projects. In addition, 
$534,641 expended from contributed funds, of which 
$200,000 was for previous projects. 
1In addition, $12,259,619 expended from contributed 
funds and $182,800 for contributed lands. 
iSIncludes $5,180,832 for previous projects. In addition, 
$2,680,942 expended from contributed funds, of which 
$577,507 was for previous projects. 
'Includes $2,379,677 for previous projects. In addition, 
$2,910,974 expended from contributed funds. 
20Includes $366,823 for previous projects. In addition, 
$1,023,819 expended from contributed funds, of which $99,000 
was for mitigation measures. 
21Includes $195,083 for previous projects. 
22Includes $1,966,306 for previous projects. In addition, 
$66 000 expended from contributed funds. 
3Includes $543,662 for previous projects. 24Includes $4,400,000 of advanced funds repaid to 
Harris County Flood Control District. In addition, $63,661 
contributed funds expended for Brays Bayou and $12,900 
Federal funds and $19,104 contributed funds expended for 
enlargement of Clodine Ditch. 
25Excludes $3,402,588 estimated value of contributed 
lands, $6,168,360 for relocations, and $217,000 credit given 
local sponsor for work-in-kind. 
26Excludes $1,349,069 estimated value of contributed 
lands and $1,070,959 credit given local sponsor for workin-
kind. 
27Includes funds ($12,544,400) provided by the Jobs 
Act (P.L. 98-8, dated March 24, 1983) for projects listed in 
Table 15-I of Annual Report for 1985. 
31-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. Oct. 27, 1965 
Nov. 17, 1986 
Jun. 3, 1930 
May 24, 1934 
(PWA) 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 1950 
Jul. 14, 1960 
Nov. 17, 1986 
2. 
31-20 
AQUATIC PLANT CONTROL 
Provides for control of progressive eradication of aquatic 
plant growth from the navigable waters and streams in 
the U.S. 
Amended cost sharing requirements to provide for 50 
percent Federal and 50 percent non-Federal participation 
in control operations. 
BRAZOS ISLAND HARBOR, TX 
Jetties and jetty channel, inside channels and basins. 
Local cooperation requirement modified to provide contribution 
of funds to cover cost of original dredging of all 
inside channels and basins. 
Deepen jetty channel to 31 feet and inner channels and 
Brownsville and Port Isabel turning basins to 28 feet. 
Enlarge Port Isabel turning basin. 
Deepen entrance channel to 35 feet; deepen to 33 feet 
channel across Laguna Madre; deepen to 32 feet 
channels from Laguna Madre to turning basins at 
Brownsville and Port Isabel; widen turning basins; and 
dredging present shallow-draft channel south of Port 
Isabel from railroad bridge to Laguna Madre and 
connecting channel to Port Isabel turning basin. 
Additional connecting channel between Port Isabel and 
Brownsville channels; and transfer shallow-draft channels 
at Port Isabel to GIWW. 
Deepen to 38 feet in outer bar channels and 36 feet in all 
other authorized channels and basins; extend existing 
turning basins at Brownsville and Port Isabel; and 
construct small-boat basin with a connecting channel 
next to Brownsville ship channel. 
Widen Brownsville Channel to 300 feet at a depth of 36 
feet from former Goose Island passing basin to turning 
basin extension, thence at a width of 500 feet and same 
depth to turning basin proper, deepen to 36 feet in area 
in southeast corner of turning basin, maintain two 
existing basins of fishing harbor, and a connecting 
channel, and construct a third basin, with necessary 
connecting channel and extend Brazos Island Harbor 
north jetty seaward 1,000 feet.27 
Enlargement of the entrance channel from deep water in 
the Gulf of Mexico to the Laguna Madre to a depth of 44 
feet and a width of 400 feet; enlargement of the Turning 
Basin Extension to a point 800 feet beyond the grain 
elevator to a depth of 42 feet at widths varying from 325 
to 400 feet; removal of Brownsville Navigation District 
Wharves 5, 6, and 9 to permit widening of the adjacent 
portion of the Turning Basin to 1,200 feet at a depth of 
36 feet; construction of asphalt walkways with handrails 
on the crown of the North and South Jetties, and 
construction of park-type public use facilities at the 
inner end of the North Jetty. 
H. Doc. 251, 89th Cong., 
1st Sess. 
Sec. 103(c), PL 99-662 
Rivers and Harbors 
Committee Doc. 16, 
71st Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 10, 
71st Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 32, 
75th Cong., 1st Sess. 
H. Doc. 335, 76th Cong., 
1st Sess. 
H. Doc. 347, 77th Cong., 
1st Sess. 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 192, 81st Cong., 
1st Sess. 
H. Doc., 428 86th Cong., 
2nd Sess.i 
Sec. 201, PL 99-662

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
3. Jul. 3, 1930 
4. Mar. 3, 1899 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 19132 
Sep. 23, 1922 
Jul. 3, 19303 
Jul. 3, 1930 
Aug. 30, 19354 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Jun. 20, 1938 
Mar. 2, 1945 
CEDAR BAYOU, TX 
Channel 10 feet deep and 100 feet wide from Houston Ship 
Channel to a point on bayou 11 miles above mouth.9 
CORPUS CHRISTI SHIP CHANNEL, TX 
Acquisition of old curvey portion of north jetty previously 
constructed by private parties. 
Complete north jetty in accordance with builder's plans. 
Complete north jetty in accordance with builder's plans. 
Connect old curve to St. Joseph Island, and construct south 
jetty. 
Dredge roadstead in Harbor Island Basin to 20 feet deep 
and construct 10,000 linear feet of stone dike on St. 
Joseph Island. 
Channel between jetties and Harbor Island Basin to 25 feet 
deep, extend jetties seaward, extend dike on St. Joseph 
Island 9,100 feet, and dredge approach channel 12 feet 
deep to town of Port Aransas. 
Dredging channel from Aransas Pass to Corpus Christi, 25 
feet deep, 200 feet bottom width. 
Deepen entrance channel from gulf to Harbor Island and 
provide an inner basin at Harbor Island of reduced area 
but greater depth. 
Channel from Aransas Pass to Corpus Christi Channel 
with depth 30 feet. 
Enlarge all channels from gulf to western end of basin 
dredge by Humble Oil and Refining Co., at its docks on 
Harbor Island. 
Maintain channel and maneuvering basin between breakwater 
and western shoreline of Corpus Christi Bay. 
Maintain 30-foot depth of approach channel, turning basin 
at Corpus Christi, Industrial Canal and turning basin at 
Avery Point. 
Maintain and deepen to 32 feet channel from deep water 
at Port Aransas to and including turning basin at 
Corpus Christi. 
Extend main turning basin at Corpus Christi westward 
2,500 feet at its present width and depth, deepen 
existing Industrial Canal and turning basin to 32 feet 
and extend this canal at a depth of 32 feet and general 
width of 150 feet, westward along Nueces Bay shore to a 
turning basin 32 feet by 900 feet, and 1,000 feet long 
near Tule Lake. 
Provide depth of 34 feet in all project channels and basins 
from Port Aransas to and including Tule Lake turning 
basin, for a width of 250 feet from Port Aransas to 
breakwater at Corpus Christi, for a width of 200 feet in 
Industrial Canal and in channel between Avery Point 
and Tule Lake turning basins, and widen Avery Point 
turning basin to 1,000 feet. 
31-21 
TABLE 31-B 
S. Doc 107, 71st Cong., 
2nd Sess.x 
Specified in Act. 
Specified in Act. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 5, 
59th Cong., 2nd Sess. 
H. Doc. 1094, 61st Cong., 
3rd Sess. 
H. Doc. 1125, 62nd Cong., 
3rd Sess. 
H. Doc. 321, 67th Cong., 
2nd Sess. 
H. Doc. 214, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 9, 
71st Cong., 1st Sess. 
Committee Does. 35, 72nd 
Cong., 1st Sess., and 40, 
73rd Cong., 2nd Sess. 
H. Doc. 130, 72nd Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 13, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 63, 
74th Cong., 1st Sess. 
H. Doc. 574, 75th Cong., 
3rd Sess. 
H. Doc. 544, 78th Cong., 
2nd Sess.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun. 30, 1948 
Sep. 3, 1954 
Sep. 3, 19545 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 14, 1960 
(As amended by 
Dec. 31, 1970) 
Aug. 13, 1968 
Oct. 22, 1976 
Deepen entrance channel to 38 feet from gulf to outer end 
of jetty; 38 feet decreasing to 36 feet thence to station 90 
north jetty; and 36 feet in all other deep water channels 
and basins except 2,000-foot undredged part of inner 
basin at Harbor Island, and a width of 400 feet in 
channel from Port Aransas to Maneuvering basin at 
Corpus Christi. 
An anchorage basin 12 feet deep, from 300 to 400 feet 
wide, and 900 feet long in Turtle Cove at Port Aransas, 
Texas. 
Branch channel 32 feet by 150 feet, extending northerly 
from main channel in vicinity of Port Ingleside, along 
north shore of Corpus Christi Bay to Reynolds Metals 
Co. plant and turning basin 32 feet deep and 800 feet 
square near plant in general vicinity of LaQuinta, 
Texas. 
An entrance channel 36 by 400 feet on a tangent 
alignment from 400-foot channel in Corpus Christi Bay, 
near Corpus Christi breakwater to flared approach 
channel to Corpus Christi turning basin. 
Deepen and widen LaQuinta Channel to 36 by 200 feet; 
enlarge LaQuinta turning basin to 36 by 800 by 1,000 
feet; a flared entrance to channel; and widening at 
curves. 
Deepen entrance channel to 42 feet from gulf to outer end 
of jetty; 40 feet in all other deep-water channels and 
basins except undredged northward extension to inner 
basin at Harbor Island and branch channel to 
LaQuinta; and widen Industrial Channel to 400 feet 
with flared entrances to Corpus Christi and Avery Point 
turning basins. 
Channel 40 by 200 feet extending 2.2 miles from Tule Lake 
turning basin to a turning basin 40 feet deep, 700 to 900 
feet wide, 1,000 feet long at Viola, Texas. 
Depth of 12 feet and a width of 100 feet in locally dredged 
Jewel Fulton Canal from LaQuinta Channel to a 
turning basin 12 by 200 by 400 feet, and assumption of 
maintenance by United States. 
Construction of a breakwater at entrance to harbor area at 
Port Aransas, and realignment of existing 12-foot by 
100-foot project channel. 
Provides for a project depth of 45 feet in the existing 
deep-draft channels and basins, for construction of a 
new deep-draft turning point, for construction of a deep 
draft mooring area and mooring facilities and for 
widening of the channels and basins at certain 
locations. The Act also deauthorized the undredged 
northward extension of Inner Basin at Harbor Island 
and the undredged west turnout (Wye connection) 
between the LaQuinta Channel and the main channel 
of the waterway. 
Modified local cooperation requirements for 1968 Act. 
Shifted responsibility for cost of disposal areas and 
confinement works from sponsor to joint 75 percent 
Federal and 25 percent non-Federal responsibility. 
H. Doc. 560, 80th Cong., 
2nd Sess. 
H. Doc. 654, 81st Cong., 
1st Sess. 
H. Doc. 89, 83rd Cong., 
1st Sess. 
H. Doc. 487, 83rd Cong., 
2nd Sess. 
S. Doc. 33, 85th Cong., 
1st Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
Sec. 107, PL 86-645 
S. Doc. 99, 90th Cong., 
2nd Sess.' 
Sec. 124, PL 94-587 
31-22

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
5. Mar. 3, 1899 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 1913 
Aug. 8, 1917 
Mar. 3, 19256 
Jul. 3, 1930 
Aug. 30, 19357 
Aug. 30, 1935 
May 17, 1950 
Jul. 3, 1958 
Oct. 5, 1961 
Dec. 31, 1970 
Nov. 17, 1986 
Aug. 5, 1886 
Jun. 13, 1902 
Mar. 3, 1905 
FREEPORT HARBOR, TX 
Dredging and other work necessary in judgment of 
Secretary of War for improving harbor; for taking over 
jetties and privately built works at mouth of river. 
Examination authorized. Work later confined to maintenance 
of jetties. 
Repairs to jetties and dredging. 
Construct seagoing hopper dredge. 
Purchase of one 15-inch pipeline dredge and equipment, its 
operation of 3 years, operation of seagoing dredge 
one-half time for 3 years, and repairs to jetties. 
Diversion dam, diversion channel, and necessary auxiliary 
works. 
Maintenance of diversion channel at expense of local 
interest. 
Deepening channels and basins. 
Maintenance of present project dimensions of channels 
and basins at Federal expense. 
Deepen outer bar channel to 38 feet from gulf to a point 
within jetties, thence 36 feet in authorized channels to 
and including upper turning basin. 
Relocate outer bar channel on straight alignment with 
jetty channel and maintain Brazos Harbor entrance 
channel and turning basin (constructed by local interests). 
Modification of HD 1469. Revoking certain provisions of 
local cooperation. 
Relocation of entrance channel and deepen to 47 feet; 
enlargement to a depth of 45 feet and relocation of jetty 
channel and inside main channel; deepening to 45 feet 
of channel to Brazosport; enlargement of the widened 
area of Quintana Point to provide a depth of 45 feet 
with a 750-foot diameter turning area; Brazosport 
turning basin to 45 feet deep with a 1,000 foot turning 
area; a new turning basin with a 1,200 foot diameter 
turning area and 45 feet deep; deepening Brazosport 
channel to 36 by 750 feet diameter; flared approaches 
from Brazos Harbor Channel; relocation of north jetty 
and rehabilitation of south jetty. 
Modified local cooperation requirements for the 1970 Act. 
GALVESTON HARBOR AND CHANNEL, TX 
Construct 2 rubblestone jetties at entrance to Galveston 
Harbor. 
A channel 1,200 by 30 feet from Bolivar Roads (outer end 
of old inner bar near Fort Point) at 51st Street.s 
Purchase or construct hydraulic pipeline dredge. 
31-23 
TABLE 31-B 
Specified in Act. 
H. Doc. 1087, 60th Cong., 
2nd Sess. 
Specified in Act. 
Specified in Act. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 10, 
68th Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 18, 
70th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 15, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Docs. 15, 72nd 
Cong., 1st Sess., and 29, 
73rd Cong., 2nd Sess. 
H. Doc. 195, 81st Cong., 
1st Sess. 
H. Doc. 433, 84th Cong., 
2nd Sess. 
PL 394, 87th Cong. 
H. Doc. 289, 93rd Cong., 
2nd Sess.2 
Sec. 101, PL 99-662 
H. Doc. 85, 49th Cong., 
1st Sess., and Annual 
Report, 1886, p. 1311. 
H. Doc. 264, 56th Cong., 
2nd Sess. 
Specified in Act.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1907 
Mar. 2, 1907 
Jun. 25, 19109 
Jul. 27, 1916 
Jul. 18, 1918 
Sep. 22, 1922 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Apr. 4, 1938 
Jun. 30, 1948 
May 17, 1950 
Jul. 3, 1958 
Jun. 23, 1971 
(House Res.) 
Nov. 18, 1971 
(Senate Res.) 
Mar. 2, 1907 
Extension of jetties to present project length and construction 
and operation of a dredge. 
Extension of Galveston Channel from 51st to 57th Sts., 
with depth of 30 feet and width of 700 feet. 
Conditional extension of Galveston Channel between 51st 
and 57th Sts., 30 feet deep and 1,000 feet wide. 
Extend seawall at Galveston from angle at 6th St., and 
Broadway to vicinity of Fort San Jacinto. 
Deepen harbor channel to 35 feet and widen to 800 feet. 
Further extension of seawall at Galveston to a junction 
with south jetty; and repairing seawall in front of Fort 
Crockett reservation. 
Deepen Galveston Channel to 32 feet; and maintain 
Galveston Harbor channels to dimensions of 800 feet 
wide, 35 feet deep on outer bar and 34 feet deep in inner 
bar.' � 
Maintain State Highway Ferry Landing Channels to 
dimensions of 12 by 100 feet. 
Construct 13 groins along gulf shore from 12th to 61st Sts. 
in city of Galveston at a limited cost of $234,000 (10 
groins constructed). 
Deepen Galveston Channel to 34 feet (Bolivar Roads to 
43rd St.). 
Deepen Galveston entrance channel to 36 feet. 
Completion of project for construction of 13 groins. 
Deepen Galveston Harbor to 38 feet from gulf to a point 2 
miles west of seaward end of north jetty; thence 36 feet 
to Bolivar Roads; revoking authority for maintenance of 
ferry channels; and Galveston channel to 36 feet deep 
from Bolivar Roads to 43rd Street. 
Deepen outer bar channel to 38 feet from gulf to a point 
within jetties, thence 36 feet in authorized channels to 
and including upper turning basin. 
Relocate outer bar channel on straight alignment with 
jetty channel and maintain Brazos Harbor entrance 
channel and turning basin (constructed by local interests). 
Deepen Galveston Channel to 40 feet from Bolivar to 43rd 
Street. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL AND MEXICAN BORDER12 
Channel 4 by 100 feet from West Galveston Bay across 
Chocolate Bay to 4 feet of water in Chocolate Bay. 
H. Doc. 340, 59th Cong., 2nd 
Sess., and Rivers and 
Harbors Committee Doc. 
11, 59th Cong., 2nd Sess. 
H. Doc. 768, 59th Cong., 
2nd Sess. 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1390, 62nd Cong., 
3rd Sess. 
H. Doc 758, 65th Cong., 
2nd Sess. 
H. Doc. 693, 66th Cong., 
2nd Sess. 
H. Doc. 307, 69th Cong., 
1st Sess. 
River and Harbors 
Committee Doc. 31, 
72nd Cong., 1st Sess. 
H. Doc. 400, 73rd Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 61, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 57, 
74th Cong., 1st Sess. 
PL 463, 75th Cong. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 195, 81st Cong., 
1st Sess. 
H. Doc. 433, 84th Cong., 
2nd Sess. 
H. Doc. 121, 92nd Cong. 
H. Doc. 445, 56th Cong., 
1st Sess. 
31-24

TABLE 
See 
Section 
in Text 
Mar. 2, 
Mar. 2, 
Mar. 2, 
Mar. 2, 
Mar. 2, 
1945 
19459 
1945 
1945 
194514 
Jul. 24, 1946 
Jul. 24, 1946 
May 17, 1950 
May 17, 1950 
May 17, 1950 
GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
31-25 
31-B 
Date 
Authorizing 
Act 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 26, 1937 
Jun. 20, 193813 
Jun. 20, 1938 
Jun. 20, 1938 
June 20, 1938 
Jun. 20, 1938 
Mar. 23, 1939 
Jul. 23, 1942 
Project and Work Authorized -- 
Channel 9 by 100 feet, Sabine River to Galveston Bay, and 
a 20-inch pipeline dredge. Such passing places, widening 
at bends, locks or guard locks and railway bridges over 
artificial cuts as are necessary. 
Channel 9 by 100 feet, Galveston Bay to Corpus Christi. 
Maintenance of a flood-discharge channel in Colorado 
River. 
Channel 9 by 100 feet in San Bernard River, Texas. 
Channel in Colorado River, 9 by 100 feet, with basin. 
Channel 9 by 100 feet from Palacios through Trepalacios 
and Matagorda Bays. 
Channel 9 by 200 feet from main channel to harbor at 
Rockport and improve harbor to 9-foot depth. 
Channel 6 by 100 feet from main channel to Aransas Pass, 
Texas. 
Enlarge waterway to depth of 12 feet and a width of 125 
feet from Sabine River to Corpus Christi. 
Enlarge waterway from Corpus Christi to vicinity of 
Mexican border to provide a depth of 12 feet and width 
of 125 feet throughout. 
Channel 6 by 60 feet from GIWW to a point in Chocolate 
Bayou near Liverpool. 
Channel 6 feet deep and 60 feet wide from main channel 
near Port O'Connor, Texas, in Barroom Bay. 
Enlarge channel from main channel to Aransas Pass, 
Texas, providing a depth of 9 feet and width of 100 feet. 
Channel 12 by 125 feet from main channel to Red Fish 
Landing, Texas, with basin. 
Channel 12 feet deep and 125 feet wide from main channel 
to vicinity of Ilarlingen, Texas, via Arroyo Colorado 
with basin. 
Fill a portion of shallow-draft channel adjacent to Port 
Isabel Turning Basin, construct a channel to connect 
shallow-draft channel with main channel near shoreline 
of Laguna Madre, and enlarge shallow-draft 
channel west of this connection, all to 12-foot depth and 
bottom width of 125 feet. 
Reroute main channel to north shore of Red Fish Bay 
between Aransas Bay and Corpus Christi Bay; deepen 
tributary channel from Port Aransas to Aransas Pass, 
Texas, 12 feet and extended basin at same depth. 
Deauthorized 6 by 60 foot channel in Chocolate Bayou and 
reauthorized the 4 by 100-foot channel. 
Alternate channel across South Galveston Bay between 
Port Bolivar and Galveston causeway. 
"Red Fish Landing" changed to "Port Mansfield, Texas." 
Documents 
H. Doc. 238, 68th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
S. Committee print, 
75th Cong., 1st Sess. 
H. Doc. 640, 75th Cong., 
3rd Sess. 
H. Doc. 642, 75th Cong., 
3rd Sess. 
H. Doc. 564, 75th Cong., 
3rd Sess. 
H. Doc. 641, 75th Cong., 3rd 
Sess. 
H. Doc. 643, 75th Cong., 
3rd Sess. 
H. Doc. 230, 76th Cong., 
1st Sess. 
PL 675, 77th Cong. 
H. Doc. 337, 76th Cong., 
1st Sess. 
H. Doc. 428, 76th Cong., 
1st Sess. 
H. Doc. 383, 77th Cong., 
1st Sess. 
S. Doc 248, 78th Cong., 
2nd Sess. 
H. Doc. 402, 77th Cong., 
1st Sess. (See PL 14, 
79th Cong.) 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 700, 79th Cong., 
2nd Sess. 
H. Doc. 768, 80th Cong., 
2nd Sess. 
H. Doc. 196, 81st Cong., 
1st Sess. 
PL 516, 81st Cong.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 12, 1952 
Sep. 3, 195415 
Sep. 3, 1954 
Sep. 9, 1959 
Jul. 14, 1960 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Oct. 23, 196216 
Oct. 23, 1962 
Oct. 23, 1962 
Incorporate as part of Intracoastal Waterway a channel 9 
by 100 feet from main channel via Seadrift to point on 
Guadalupe River 3 miles above Victoria, Texas, authorized 
by River and Harbor Act of 1945. 
Small craft harbor 9 by 200 by 1,000 feet at Seadrift with 
an entrance channel 9 by 100 feet. 
Widen tributary channel between Port Aransas and 
Aransas Pass, Texas, to 125 feet; straighten and widen 
to 125 feet connecting channel to Conn Brown Harbor, 
and maintain Conn Brown Harbor at Federal expense, 
all to 12 feet deep. 
Improve channels and basins comprising channel to Port 
Mansfield constructed in part by Federal Government 
and in part by local interest; constructing turnout 
curves at Gulf Intracoastal Waterway intersection and 
bend easing at entrance to turning basin; construct 
parallel jetties at gulf entrance; maintenance of locally 
dredged jetty channel 16 by 250 feet; and maintenance 
of small craft basin. 
Entrance channel 7 feet deep by 75 feet wide from main 
channel to Gulf of Mexico to inside shoreline at Port 
Isabel, Texas, an inner channel 6 feet deep by 50 feet 
wide from entrance channel to East Harbor Basin, and 
an irregular-shaped harbor basin 6 feet deep having a 
surface area of about 7 acres. 
Deepen the existing 6-foot channel at Port Isabel to 12 feet 
and removing the submerged bars at each end of the 
island to a depth of -12 feet MLT. 
Deepening the existing channel to 12 by 125 feet, and 
extend southeasterly from the Gulf Intracoastal Waterway 
main channel in West Galveston Bay, into Offatts 
Bayou, a distance of 2.2 miles, and a west turnout 12 by 
125 feet between the proposed Offatts Bayou Channel 
and the Gulf Intracoastal Waterway. 
Deepening Aransas Pass tributary channel to 14 feet from 
mile 0 at Harbor Island to mile 6.1 at the city of 
Aransas Pass; widening to 175 feet between miles 3.5 
and 4.6; and deepening Conn Brown Harbor, turning 
basin and connecting channel between Conn Brown 
Harbor and turning basin. 
Improve main channel 16 feet deep and 150 feet wide from 
Sabine River to Houston Ship Channel; with two 
relocations; relocate main channel in Matagorda Bay 
and Corpus Christi Bay; and maintaining existing Lydia 
Ann Channel. 
Deepen and widen channel to Palacios; construct two 
protective breakwaters; maintain and deepen existing 
basins; and deepen, enlarge and maintain existing 
approach channel to basin No. 2. 
Eliminates requirement of local interest to construct 
bridge at mile 29.2 turning basin at Victoria, and 
maintain turning basins at Victoria and Seadrift; 
provide: Federal construction of vertical-lift railroad 
bridge at Missouri-Pacific Railroad mainline crossing, 
mile 29.2; construction and future maintenance of basin 
near Victoria, Texas, and maintenance of basin constructed 
by local interests at Seadrift, Texas. 
PL 527, 82nd Cong., 
2nd Sess. 
H. Doc. 478, 81st Cong., 
2nd Sess. 
H. Doc. 376, 83rd Cong., 
2nd Sess. 
S. Doc. 11, 86th Cong., 
1st Sess. 
Sec. 107, PL 645, 86th Cong. 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
H. Doc. 556, 87th Cong., 
2nd Sess. 
H. Doc. 504, 87th Cong., 
2nd Sess. 
H. Doc. 288, 87th Cong., 
2nd Sess. 
31-26

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 27, 196517 
Aug. 13, 1968 
Nov. 17, 1986 
Nov. 17, 1988 
Mar. 5, 1905 
Mar. 2, 1919 
Mar. 3, 1925 
Jul. 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Jun. 30, 1948 
Jul. 3, 195820 
Modify existing Federal navigation project to provide a 
channel extending from Gulf Intracoastal Waterway 
through Chocolate Bay and Chocolate Bayou to project 
channel mile 8.2, thence to a turning basin near 
channel mile 13.2 and for salt water barrier in 
Chocolate Bayou about 3.7 miles upstream from basin 
(channel mile 16.9). 
Entrance channel 15 feet deep and 200 feet wide at the 
mouth of Colorado River Channel protected by an east 
jetty 3,500 feet long extending to 12-foot depth and a 
west jetty 2,900 feet long extending to 5-foot contour; 
make channel 12 feet by 100 feet from gulf shore to 
Matagorda, including recreation facility, a turning 
basin 12 feet by 300 feet wide and 1,450 feet long, and a 
new diversion channel 250 feet wide and varying in 
depth from 20 to 23 feet including a closure dam across 
the present river channel. 
Modified 1968 authorization to provide that diversion 
features be constructed at Federal expense and operation 
and maintenance be shared 75 percent Federal and 
25 percent non-Federal. 
Enlarge existing Channel to Victoria from a depth of 9 feet 
and width of 100 feet to a depth of 12 feet and width of 
125 feet. 
HOUSTON SHIP CHANNEL, TX 
Easing or cutting off sharp bends and construction of a pile 
dike.' s 
A channel 30 feet deep, widen bend at Manchester and 
enlarge turning basin. 
A light-draft extension of channel to mouth of White Oak 
Bayou.' 9 
Widen channel through Morgan Point and to a point 4,000 
feet above Baytown and widen certain bends. 
Deepen to 32 feet in main channel and turning basin, and 
a 400-foot width through Galveston Bay. 
Deepen to 34 feet in main channel and widen from Morgan 
Point to turning basin. 
Branch channel 10 by 60 feet behind Brady Island. 
Widen channel from Morgan Point to lower end of Fidelity 
Island with turning points at mouth of Hunting Bayou 
and lower end of Brady Island. 
Widen channel from lower end of Fidelity Island to 
Houston turning basin and dredge off-channel silting 
basins. 
Dieepen to 36 feet from Bolivar Roads to and including 
main turning basin at Houston, Texas, including 
turning points at Hunting Bayou and Brady Island. 
Deepen to 40 feet from Bolivar Roads to Brady Island, 
construct Clinton Island turning basin, a channel 8 by 
125 feet at Five Mile Cut, and improve shallow-draft 
channel at Turkey Bend. 
H. Doc. 217, 89th Cong., 
1st Sess. 
S. Doc. 102, 90th Cong., 
2nd Sess. 
Sec. 812, PL 99-662 
Sec. 3, PL 100-676 
Rivers and Harbors 
Committee Doc. 35, 
61st Cong., 2nd Sess. 
H. Doc. 1632, 65th Cong., 
3rd Sess. 
H. Doc. 93, 67th Cong., 
1st Sess. 
H. Doc. 13, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 28, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 58, 
74th Cong., 1st Sess. 
H. Doc. 226, 76th Cong., 
1st Sess. 
H. Doc. 226, 76th Cong., 
1st Sess. 
H. Doc. 737, 79th Cong., 
2nd Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 350, 85th Cong., 
2nd Sess.' 
31-27 
TABLE 31-B 
8.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 14, 1960 
Oct. 27, 1965 
Nov. 17, 1986 
9. Jun. 25, 1910 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 3, 1958 
10. Jul. 25, 1912 
Sep. 22, 1922 
Sep. 22, 1922 
Mar. 3, 1925 
Jan. 21, 1927 
Barbour Terminal at Morgan Point. 
Restoring existing locally dredged channel from mile 0 to 
0.34 to 36 feet deep and dredging a 15-12 ft. channel 
from mile 0.34 to 2.81, in Greens Bayou.2 1 
Maintenance of Greens Bayou, Barbour Terminal Channel, 
and Bayport Ship Channel to forty-foot depths at 
Federal expense. 
MATAGORDA SHIP CHANNEL, TX 
Channel to Port Lavaca, Texas 7 feet deep and 89 feet 
bottom width. 
Extend 7-foot channel to shoreline of Lavaca Bay at mouth 
of Lynns Bayou. 
Deepen and widen channel to present project dimensions. 
Extend channel 6 by 100 feet from Port Lavaca via Lavaca 
Bay, Lavaca and Navidad Rivers to Red Bluff, a 
distance of 20 miles. 
A harbor of refuge 9 feet deep near Port Lavaca and an 
approach channel 100 feet wide and equal depth. 
Deepen to 12 feet and widen to 125 feet Port Lavaca 
Channel and approach channel to harbor of refuge; 
deepen to 12 feet Port Lavaca turning basin and basins 
at harbor of refuge. 
An entrance channel 38 by 300 feet, a channel 36 by 200 
feet, 22 miles long across Matagorda and Lavaca Bays 
to Point Comfort, Texas, a turning basin 36 feet deep 
and 1,000 feet square at Point Comfort, and dual jetties 
at entrance from gulf. 
SABINE-NECHES WATERWAY, TX 
Existing project dimensions of jetties, a 26-foot channel 
through Sabine Pass, Port Arthur Canal and Port 
Arthur turning basin; and a 26-foot turning basin at 
Port Arthur. A depth of 25-feet in Sabine-Neches Canal, 
Neches River to Beaumont and Sabine River to Orange, 
including cutoffs and widening channels. 
Deepen channels to 30 feet from gulf to Beaumont, with 
increased widths and an anchorage basin in Sabine 
Pass. 
Deepen Port Arthur east and west turning basins and 
approach channel to 30 feet. Take over and deepen to 30 
feet channel connecting west turning basin with 
Taylors Bayou turning basin. For a 30-foot depth in 
channel from mouth of Neches River to cutoff in Sabine 
River near Orange. 
Removal of guard lock in Sabine-Neches Canal. 
Widen Sabine Pass and jetty channel, Port Arthur Canal, 
and Sabine-Neches Canal. For dredging 2 passing places 
in Sabine-Neches Canal, easing of bends, removal and 
reconstructing Port Arthur field office, extending 
Beaumont turning basin upstream 200 feet above new 
city wharves, and an anchorage basin in Sabine Pass. 
Sec. 107, PL 86-645 
R. Doc. 257, 89th Cong., 
1st Sess. 
Sec. 819, PL 99-662 
H. Doc. 1082, 60th Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 28, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
75th Cong., 1st Sess. 
H. Doc. 314, 76th Cong., 
1st Sess. 
H. Doc. 731, 79th Cong., 
2nd Sess. 
H. Doc. 131, 84th Cong., 
1st Sess. 
H. Doc. 388, 84th Cong., 
2nd Sess. 
H. Doc. 773, 61st Cong., 
2nd Sess. 
H. Doc. 975, 66th Cong., 
3rd Sess. 
S. Doc. 152, 67th Cong., 
2nd Sess. 
H. Doc. 234, 68th Cong., 
1st Sess. 
H. Doc 287, 69th Cong., 
1st Sess. 
31-28

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, 193511 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Jun. 20, 193822 
Oct. 17, 1940 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 194623 
Jul. 24, 194624 
Jul. 24, 1946 
May 17, 1950 
A depth of 32 feet in channels from gulf to Beaumont 
turning basin, including all turning basins at Port 
Arthur. 
Deepen channels to 34 feet with increased widths from 
gulf to Beaumont turning basin. 
Construct suitable permanent protective works along 
Sabine Lake. Maintain Taylors Bayou turning basin. 
Maintain channel from Sabine River to Orange Municipal 
wharf. 
Dredging 500 feet from eastern end of Harbor Island and 
abandonment of channel south and west of Harbor 
Island. 
Increased widths of channels from gulf to Beaumont 
turning basin and channel connecting Port Arthur west 
turning basin and Taylors Bayou turning basin, deepen 
Beaumont turning basin and Beaumont turning extension 
to 34 feet; and dredge a new cutoff from Smith's 
Bluff cutoff to McFadden Bend. 
Abandon Orange turning basin; dredge a channel 25 by 
150 feet, suitably widened on bends to highway bridge, 
and dredge a cutoff channel opposite Orange. 
Extend Beaumont turning basin upstream 300 feet. 
Widen Port Arthur west turning basin to 600 feet. 
Dredge a channel from Beaumont turning basin to vicinity 
of Pennsylvania Shipyard. 
Deepen Sabine Pass outer bar channel to 37 feet, Sabine 
Pass jetty channel to 36 feet at inner end, deepen to 36 
feet Sabine Pass Channel, Port Arthur Canal, Port 
Arthur east and west turning basins, Taylors Bayou 
turning basin and channel from Port Arthur west 
turning basin to Taylors Bayou turning basin, deepen to 
36 feet and widen toA00 feet Sabine-Neches Canal from 
Port Arthur Canal to mouth of Neches River except 
through Port Arthur Bridge; deepen Neches River 
channel from mouth to Beaumont turning basin to 36 
feet widening to 350 feet from Smith's Bluff to 
Beaumont turning basin; deepen junction area on 
Neches River at Beaumont turning basin to 36 feet; and 
widen Sabine-Neches Canal between Neches and Sabine 
Rivers to 150 feet. 
Improve Cow Bayou, Texas, by construction of a channel 
100 feet wide and 13 feet deep extending from 
navigation channel in Sabine River to a point 0.5 mile 
above county bridge at Orangefield, Texas, with a 
turning basin. 
Improve Adams Bayou, Texas, to provide a channel 12 feet 
deep and 100 feet wide extending from 12-foot depth in 
Sabine River to first county highway bridge across 
bayou. 
Deepen to 36 feet and widen to 400 feet the Sabine-Neches 
Canal near Port Arthur bridge; reconstruct Port Arthur 
Bridge and relocate Port Arthur field office. 
Rivers and Harbors 
Committee Doc. 27, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 12, 
74th Cong., 1st Sess. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 3, 
75th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 20, 
75th Cong., 1st Sess. 
H. Doc. 581, 75th Cong., 
3rd Sess. 
S. Doc 14, 77th Cong., 
1st Sess. 
H. Doc. 685, 76th Cong., 
3rd Sess. 
S. Doc 60, 77th Cong., 
1st Sess. 
S. Doc 158, 77th Cong. 
2nd Sess. 
H. Doc. 571, 79th Cong., 
2nd Sess. 
H. Doc. 702, 79th Cong., 
2nd Sess. 
H. Doc. 626, 79th Cong., 
2nd Sess. 
H. Doc. 174, 81st Cong., 
1st Sess. 
31-29 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 3, 195425 
Oct. 23, 196226 
11. Mar. 4, 1913 
Jul. 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Jun. 30, 1948 
Jul. 14, 1960 
Oct. 12, 1972 
(Senate Res.) 
Oct. 12, 1972 
(House Res.) 
Rectification of certain reaches of existing Sabine Pass 
Channel, Sabine-Neches Canal, and Neches River and 
Sabine River Channel; widen to 350 feet entrance 
channel to Port Arthur turning basins; widen curve at 
junction of Port Arthur and Sabine-Neches Canals; 
relocate and enlarge Sabine Pass anchorage basin to 34 
by 1,500 by 3,000 feet; widen to 200 feet Sabine-Neches 
Canal from mouth of Neches River to mouth of Sabine 
River and Sabine River Channel to upper end of 
existing project at Orange, except for channel around 
Harbor Island at Orange; deepen to 30 feet Sabine River 
Channel from cutoff near Orange municipal slip to 
upper end of project, except around Harbor Island; and 
enlarge area at entrance to Orange municipal slip to 
provide a maneuvering basin. 
Improve outer bar channel to 42 and 40 feet for all inland 
channels to Port Arthur and Beaumont; width of 500 
feet in Port Arthur Canal and 400 feet in Neches River 
Channel to Beaumont with three turning points in 
Neches River; a channel, 12 by 125 feet, extending in 
Sabine River to Echo; and replace an obstructive bridge 
at Port Arthur, Texas. Deauthorization of uncompleted 
portion of channel between Port Arthur west turning 
basin and Taylors Bayou turning basin and enlargement 
of entrance channel to Port Arthur turning 
basins. 
TEXAS CITY CHANNEL, TX 
A channel 300 by 30 feet and construct a pile dike 28,200 
feet long north to channel. 
A harbor 800 by 30 feet at Texas City, and construct a 
rubblemound dike. 
Extension of rubblemound dike to shoreline. 
Deepen channel and harbor to 32 feet. 
Deepen channel and harbor to 34 feet. 
Extend harbor 1,000 feet southward, 800 by 34 feet. 
Deepen channel and harbor to 36 feet, widen channel to 
400 feet and harbor to 1,000 feet and changing name of 
project to "TEXAS CITY CHANNEL, TEXAS." 
Deepen channel and turning basin to 40 feet and construct 
16-foot Industrial Barge Canal. 
Widen the existing main turning basin to 1,200 feet 
including relocation of the basin 85 feet to the east; 
providing a 40-foot deep channel in the Industrial Canal 
at widths of 300-400 feet, with a turning basin at the 
head of the canal 40 feet deep, 1,150 feet long, and 1,000 
Sfeet wide, and easing of the bend at the entrance to the 
canal, and deauthorization of shallow-draft Industrial 
Barge Canal not incorporated in the plan of improvement 
above. 
S. Doc. 80, 83rd Cong., 
2nd Sess. 
H. Doc. 553, 87th Cong., 
2nd Sess. 1 
H. Doc. 1390, 62nd Cong., 
3rd Sess. 
H. Doc. 107, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
73rd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 46, 
73rd Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 62, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 47, 
75th Cong., 1st Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess.1 
H. Doc. 427, 86th Cong., 
2nd Sess. 
H. Doc. 199, 92nd Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
31-30

GALVESTON, TEXAS, DISTRICT 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Nov. 17, 1986 
12. Mar. 3, 1905 
Jul. 25, 1912 
Sep. 22, 1922 
Mar. 2, 1945 
Jul. 24, 1946 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 30, 1983 
15. Dec. 15, 1970 
(House Res.) 
Dec. 17, 1970 
(Senate Res.) 
16. Jun. 20, 1938 
Sep. 3, 1954 
Oct. 27, 1965 
Deepening the Texas City Turning Basin to 50 feet, 
enlarging the 6.7 mile long Texas City Channel to 50 
feet by 600 feet; deepening the existing 800-foot wide 
Bolivar Roads Channel and Inner Bar Channel to 50 
feet; deepening the existing 800-foot wide Outer Bar 
and Galveston Entrance Channels to 52 feet; extending 
the Galveston Entrance Channel to a 52 foot depth for 
4.1 miles at a width of 800 feet and an additional reach 
at a width of 600 feet to the 52 foot contour in the Gulf 
of Mexico; and establishment of 600 acres of wetland 
and development of water-oriented recreational facilities 
on a 90-acre enlargement of the Texas City Dike. 
TRINITY RIVER AND TRIBUTARIES, TX 
Anahuac Channel. 
Six-foot channel to Liberty. 
Abandon improvements above Liberty and terminate all 
improvements by lock and dam, leaving a 6-foot 
channel from Liberty to mouth. 
Provides for a navigable channel from the Houston Ship 
Channel near Red Fish Bar in Galveston and Trinity 
Bays to the mouth of Trinity River and 9 feet deep and 
150 feet wide in the river section, with a turning basin 
at Liberty. 
Modification of the project to provide for a channel 9 feet 
deep and 150 feet wide from the Houston Ship Channel 
near Red Fish Bar in Galveston Bay extending along 
the east shore of Trinity Bay to the mouth of the Trinity 
River at Anahuac, including protective spoil embankment 
on the bay side of the channel in lieu of the 9 by 
200-foot channel in Galveston and Trinity Bays. 
Provides for the multiple-purpose Wallisville Reservoir, 
including a navigation lock in the Wallisville Dam at 
Channel Mile 28.30 and advancement of the Channel to 
Liberty from one mile below Anahuac (Mile 23.2) to the 
Texas Gulf Sulphur Company's slip at Channel Mile 
35.8, and incorporation into existing project Anahuac 
Channel and mouth of Trinity River projects. 
Reevaluation of navigation benefits. 
Modified Wallisville Reservoir by reducing the size to 
5,600 acres and confining the reservoir to east side of 
Trinity River. 
CORPUS CHRISTI BEACH, TX (RESTORATION 
PROJECT) 
Restoration and periodic nourishment of 1.4 miles of 
beach. 
BUFFALO BAYOU AND TRIBUTARIES, TX 
Barker and Addicks Reservoirs, Texas. 
Clearing, straightening, enlarging and lining of Buffalo, 
Brays, and White Oak Bayous. 
Extend upper limits of White Oak Bayou upstream about 
2.1 miles from BRI RR bridge to mouth of Cole Creek. 
Sec. 201, PL 99-662 
H. Doc. 989, 66th Cong., 
3rd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 634, 79th Cong., 
2nd Sess. 
H. Doc. 215, 87th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
PL 98-63 
H. Doc. 415, 91st Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
H. Doc. 456, 75th Cong., 
2nd Sess. 
H. Doc. 250, 83rd Cong., 
2nd Sess.1 
H. Doc. 169, 89th Cong., 
1st Sess. 
31-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
17. Aug. 13, 1968 
Nov. 17, 1986 
18. Nov. 17, 1988 
19. Nov. 17, 1988 
21. Nov. 17, 1986 
22. Oct. 23, 1962 
23. Nov. 17, 1986 
24. Oct. 27, 1965 
25. Jul. 3, 1958 
26. Nov. 17, 1986 
27. Oct. 23, 1962 
CLEAR CREEK, TX 
Channel enlargement and rectification from upper end of 
Clear Lake at Mile 3.8 to improved channel Mile 34.8.30 
Modified local cooperation requirements of the 1968 
authorization. 
CYPRESS CREEK, TX 
Enlargement and rectification of lower 29.4 miles of 
Cypress Creek channel and recreational development. 
FALFURRIAS, TX 
Construction of a 5.6-mile long diversion levee west of 
Falfurrias; a 1.8-mile long pilot channel west of 
Falfurrias; a flowage easement; and a 0.8-mile long ring 
levee around the sewage treatment plant. 
LOWER RIO GRANDE BASIN, TX 
Channel improvements to provide drainage protection for 
the area in Hidalgo and Willacy Counties north of U.S. 
Highway 83, and for the area between U.S. Highway 83 
and the Rio Grande in Hidalgo County; and to provide 
flood protection for the cities of McAllen, Edinburg, 
Raymondville, Edcouch, La Villa, and Lyford. 
PORT ARTHUR AND VICINITY, TX (HURRICANEFLOOD 
PROTECTION) 
Raising and reconstructing 6.3 miles of existing seawall; 
constructing 0.3 mile of new seawall, 20.3 miles new 
levees and five pumping plants; and raising and 
improving 7.5 miles of existing levees. 28 
SIMS BAYOU, TX 
Enlargement and rectification, with appropriate erosion 
control measures of 19.31 miles of Sims Bayou; 
environmental measures and riparian habitat along 
entire alignment, and recreational development. 
TAYLORS BAYOU, TX 
Enlarging and rectifying channels; construction of diversion 
channel; a salt water gate; enlargement of GIWW 
1.3 miles and alteration of State Highway 87 bridge. 29 
TEXAS CITY AND VICINITY, TX (HURRICANEFLOOD 
PROTECTION) 
Construction of improvements for control of storm tides, 
consisting of new and enlarged levees and floodwalls 
approximately 14.1 and 2.1 miles in length; related 
drainage and stoplog structures; a navigation opening 
and pumping plants. 
UPPER WHITE OAK BAYOU, TX 
Channel improvements in White Oak Bayou from Mile 
10.7 to Mile 19.9; on Cole Creek from its mouth to Mile 
4.9; and on Vogel Creek from its mouth to Mile 4.5; and 
recreational development on project lands along White 
Oak Bayou, between Mile 14.6 and Mile 18.3. 
VINCE AND LITTLE VINCE BAYOUS, TX 
Enlarging and rectifying channel of Vince Bayou and 
Little Vince Bayou upstream for a total of 11.5 miles for 
both streams. 
H. Doc. 351, 90th Cong., 
2nd Sess. 
Sec. 1001, PL 99-662 
Sec. 3, PL 100-676 
Sec. 3, PL 100-676 
Sec. 401, PL 99-662 
H. Doc. 505, 87th Cong., 
2nd Sess.1 
Sec. 401, PL 99-662 
H. Doc. 206 89th Cong., 
1st Sess. 
H. Doc. 347, 85th Cong., 
2nd Sess.1 
Sec. 401, PL 99-662 
H. Doc. 441, 87th Cong., 
2nd Sess.' 
1 Contains latest published maps. 4 Included in Public Works Administration program 
2 Extension of north jetty 1,950 feet and south jetty September 6, 1933 and February 16, 1935. 
1,265 feet considered inactive. 5 West leg of Wye junction with main channel 
ddreeadugtihnogcri2z,0e0d0. 
3 Dredging 2,000 by 650-foot northerly extension of 6 Construction of lock in diversion dam at local 
inner basin deauthorized. expense considered inactive. 
31-32

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
7 Dredging upper .5 mile of channel to vicinity of 
Stauffer Chemical plant was deauthorized under Sec. 12 of PL 
93-251. Included in Public Works Administration program 
September 6, 1933. 
8 Dredging 43rd to 51st Streets was deauthorized 
under Sec. 12 of PL 93-251. 
9 Deauthorized under Sec. 12 of PL 93-251. 
10 Deepening 43rd to 57th Streets was deauthorized 
under Sec. 12 of PL 93-251. 
11 Previously authorized September 6, 1933 by 
Public Works Administration. 
12 H. Doc. 230, 76th Cong., 1st Sess. and project 
documents contain latest published maps. 
13 Dredging upper 3.5 miles was deauthorized under 
Sec. 12 of PL 93-251. 
14 Dredging upper 5 miles was deauthorized under 
Sec. 1001 of PL 99-662. 
15 Inactive. 
16 Portion of 16-foot by 150-foot channel from Sabine 
River to Houston Ship Channel is inactive. Relocation of 
channel in Matagorda Bay deauthorized under Sec. 12 of PL 
93-251. 
17 The 9 feet by 100 feet channel from Mile 8.2 to 
Mile 13.2 in Chocolate Bayou was deauthorized under Sec. 
1001 of PL 99-662. 
18 Construction of pile dike was deauthorized under 
Sec. 12 of PL 93-251. 
19 Hill Street Bridge to mouth of White Oak Bayou 
was deauthorized under Sec. 12 of PL 93-251. 
20 Deepening channel to 40 feet from Southern 
Pacific Slip to Brady Island was deauthorized under Sec. 12 of 
PL 93-251. 
21 The 12-foot channel from mile 1.65 to mile 2.81 
deauthorized under Sec. 12 of PL 93-251. 
22 Complete widening of channel between Port 
Arthur west turning basin and Taylors Bayou turning basin 
deauthorized by 1962 R&H Act. 
23 Complete deepening of channel between Port 
Arthur west turning basin and Taylors Bayou turning basin 
deauthorized by 1962 R&H Act. 
24 Channel extension above Cow Bayou turning 
basin near Orangefield was deauthorized under Sec. 12 of PL 
93-251. 
25 Widening to 350 feet entrance channel to Port 
Arthur turning basin deauthorized by 1962 R&H Act. 
26 The 12-foot channel in Sabine River from Orange 
to Echo, Texas deauthorized under Sec. 12 of PL 93-251. 
27 Jetty extension was deauthorized under Sec. 1001 
of PL 99-662. 
28 Raising and strengthening of levees surrounding 
Gulf Oil Company's fresh water reservoir is inactive. 
29 Enlarging 7.0 miles of North Fork Taylors Bayou, 
7.8 miles of South Fork Taylors Bayou and 4.4 miles of 
Mayhaw Bayou are inactive. 
30 Portion of project upstream of Brazoria/Galveston 
County line, approximately mile 18.5, in inactive category. 
31 Turning basin was deauthorized under Sec. 1001 
of PL 99-662. 
31-33 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to September 30, 1989 
Report See 
Annual Report Operation and 
Project For Construction Maintenance 
Aquatic Plant Control (1958 and 1962 River and Harbor 
Acts)6 1967 38,2521 - 
Bastrop Bayou, TX2 1931 9,920 27,129 
Brazos River, TX, Velasco to Old Washington3 1924 216,9894 223,010 
Channel to Port Bolivar, TX 1987 133,9248 1,173,8929 
Clear Creek and Clear Lake, TX 1982 66,934 537,139 
Corpus Christi, TX, Channel to Navy Seaplane Base Encinal 
Peninsula 1968 1,194,344 26,467 
Dickinson Bayou, TX 1954 33,942 57,553 
Double Bayou, TX 1987 226,558 1,412,07810 
East Bay (Hanna Reef), TX5 1922 2,476 847 
Johnson Bayou LA6 1933 2,261 54,042 
Little Bay, TX 1979 - 252,728 
Neches River and Trib., Salt Water Barrier at Beaumont, 
TX (Advance Engineering & Design) 1984 1,503,843 - 
Oyster Creek, TX 1922 6,942 7,556 
Sabine River and Tributaries, TX (Echo to Morgan Bluff)3 1971 - 
1 Excludes $1,672 work contribution. 7 Aransas County Navigation District, Rockport, TX, 
2 Widening from 60 feet to 100 feet at 4-foot depth constructed project as authorized by 1950 River and Harbor 
was deauthorized under Sec. 12 of PL 93-251. Act (H. Doc. 114, 81st Cong., 1st Sess.) in 1955 under 
3 Deauthorized under Sec. 1001 of PL 99-662. Department of Army permit. 
4 Includes $123,676 for previous projects. Includes $46,101 for previous projects. 
In inactive category for maintenance. 'o n addition, $102,325 expended from contributed 
6 Channel adequate for existing commerce. funds. 
TABLE 31-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to September 30, 1989 
Report See 
Annual Report Operation and 
Project For Construction Maintenance 
Arroyo Colorado, Rio Hondo, Texas 1986 201,300 - 
Baytown, Texas 1980 245,400 - 
Colorado River, Matagorda, Texas2 1963 273,757 - 
Freeport and Vicinity, Texas, Hurricane-Flood Protection2 1984 29,285,0423 - 
Guadalupe River (Remove Log Jams), Texas2 1978 505,749 - 
Highland Bayou, Texas2 1984 12,254,390 - 
Lavaca-Navidad River, Texas: 
Hallettsville Project 1961 256,043 - 
General channel project 1952 21,086 - 
Liberty Local Protection Project, Texas6 1971 98,517 - 
Mill Creek, Texas' 1952 24,753 - 
Peyton Creek, Texas4 1975 66,377 - 
San Diego Creek, Alice, Texas2 1963 135,175 - 
Tranquitas Creek, Kingsville, Texas2 1956 130,239 - 
Three Rivers, Texas5 5,835,927 - 
1 Inactive. 4 Deauthorized under Sec. 12 of PL 93-251. 
2 Completed. 5 See Annual Report for 1983, Fort Worth District, 
" In addition, $8,695,438 expended from contributed page 16-12 
funds, $1,126,905 estimated value of contributed lands, and pag 
$2,726,446 for relocations by local interests. 6 Deauthorized under Sec. 1001 of PL 99-662. 
31-34

GALVESTON, TEXAS, DISTRICT 
TABLE 31-E TOTAL COST OF EXISTING PROJECTS 
See 
Section 
in Text Project Funds New Work Maintenance Rehabilitation 
2. Brazos Island 
Harbor, TX 
3. Cedar Bayou, TX 
4. Corpus Christi Ship 
Channel, TX 
5. Freeport Harbor, 
TX 
6. Galveston Harbor 
and Channel, TX 
7. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL 
and the Mexican 
Border 
8. Houston Ship 
Channel, TX 
10. Sabine-Neches 
Waterway, TX 
11. Texas City Channel, 
TX 
12. Trinity River and 
Tributaries, TX 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Total cost of project 
Regular 
Channel 
Seawall 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
9,249,310 
2,848,560 
1,683,258 
13,781,128 
642,176 
25,000 
667,176 
73,927,552 
324,287 
5,893,740 
80,145,579 
1,716,695 
276,720 
82,138,994 
13,430,854 
116,575 
4,271,003 
17,818,432 
360,249 
18,178,681 
11,920,187 
8,754,209 
3,648,932 
24,323,328 
67,821,722 
466,477 
3,821,590 
72,109,789 
395,000 
139,776 
72,644,565 
29,042,293 
2,612,932 
1,382,760 
33,037,985 
49,592,331 
1,363,652 
2,103,435 
53,059,418 
32,000 
116,760 
53,208,178 
14,623,746 
136,296 
1,023,819 
15,783,861 
27,194,400 
66,000 
27,260,400 
42,126,355 
14,692 
42,141,047 
2,739,734 
2,739,734 
88,401,547 
445,269 
88,846,816 
88,846,816 
50,136,953 
229,311 
50,366,264 
50,366,264 
82,479,395 
512,163 
13,121 
2,116,719 
85,121,398 
234,703,274 
22,672 
234,725,946 
234,725,946 
112,620,023 
334,641 
112,954,664 
144,273,013 
2,910,974 
147,183,987 
147,183,987 
23,418,010 
23,418,010 
11,086,006 
11,086,006 
2,170,080 
2,170,080 
3,576,684 
3,576,684 
3,576,684 
8,935 
8,935 
8,935 
7,373,356 
595,973 
7,969,329 
1,270,511 
1,270,511 
1,270,511 
726,158 
726,158 
8,35 
Total 
53,545,745 
2,848,560 
1,697,950 
58,092,255 
3,381,910 
25,000 
3,406,910 
165,905,783 
324,287 
6,339,009 
172,569,079 
1,716,695 
276,720 
174,562,494 
63,576,742 
116,575 
4,500,314 
68,193,631 
360,249 
68,553,880 
101,772,938 
9,862,345 
13,121 
5,765,651 
117,414,055 
303,795,507 
466,477 
3,844,262 
308,106,246 
395,000 
139,776 
308,641,022 
141,662,316 
2,612,932 
1,717,401 
145,992,649 
193,865,344 
1,363,652 
5,014,409 
200,243,405 
32,000 
116,760 
200,392,165 
38,767,914 
136,296 
1,023,819 
39,928,029 
38,280,406 
66,000 
38,346,406 
31-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-F CHANNEL DIMENSIONS 
See 
Section 
in Text 
2. 
Project 
Brazos Island 
Harbor, TX 
4. Corpus Christi 
Ship Channel, 
TX 
5. Freeport 
Harbor, TX 
Adopted Project 
Dimensions 
Depth in 
Feet 
(Below 
Mean Low Bottom 
Tide) Width (Feet) 
44-42 400 
42 300 
42 300 
42 300 
42 500 
36 1,000 
36 200 
36 200 
36 1,000 
15 370-305 
15 370-305 
15 370 
15 270 
15 100 
Section of Waterway 
Outer Bar and Jetty Channel 
Padre Island to Long Island 
Long Island to Goose Island 
Goose Island to Turning 
Basin Extension 
Turning Basin Extension 
Brownsville Turning Basin 
Port Isabel Channel via East 
Turnout 
West Wye, from Brownsville 
Channel 
Port Isabel Turning Basin 
Fishing Boat Harbor: 
West Basin 
Middle Basin 
East Basin 
Connecting Channel 
Entrance Channel 
Aransas Pass Outer Bar 
Channel 
Aransas Pass Jetty Channel 
Inner Basin at Harbor Island 
Channel to Port Aransas 
Port Aransas Turning Basin 
Anchorage Basin at Port 
Aransas 
Inner Basin to Mile 8.5 
Mile 8.5 to LaQuinta 
Junction 
LaQuinta Junction to Corpus 
Christi Turning Basin 
Corpus Christi Turning Basir 
Industrial Canal 
Avery Point Turning Basin 
Channel to Chemical 
Turning Basin 
Chemical Turning Basin 
Tule Lake Channel 
Tule Lake Turning Basin 
Viola Channel 
Viola Turning Basin 
Channel to LaQuinta 
LaQuinta Turning Basin 
Turning Point at LaQuinta 
Channel Junction 
Jewel Fulton Canal 
Jewel Fulton Turning Basin 
Mooring Area at Ingleside: 
Mooring Area (a) 
Mooring Area (b) 
Outer Bar Channel 
Jetty Channel 
Quintana Turning Basin 
Channel to Brazosport 
Turning Basin 
Brazosport Turning Basin 
Channel to Upper Turning 
Basin 
Upper Turning Basin 
Channel to Stauffer Chemica 
Plant 
Stauffer Turning Basin 
Brazos Harbor Channel 
700 
600-730 
730-1,720 
100-150 
200-4002 
300-400 
600-500 
500 
400 
800 
400 
975 
400 
1,200' 
300 
1,200 
300-350 
1,200 
300-400 
1,200 
1,250 s 
100 
200 
150 
150 
400 
400 
7504 
400 
1,0004 
375 
1,2004 
200 
500 
200 
Improved Project Dimensions 
Depth in 
Feet 
(Below Bottom 
Mean Low ,Width Length 
Tide) (Feet) Feet Miles 
38-36 300 2.5 
36 200 2.1 
36 200 9.6 
36 200 3.2 
36 500 1.3 
36 1,000 2,670 0.5 
36 200 1.4 
36 200 0.8 
36 1,000 1,300 0.2 
15 370-305 1,470 0.3 
15 370-305 1,200 0.2 
15 370 1,470 0.3 
15 265 1,230 0.2 
15 100 770 0.1 
47 
45 
45 
12 
12 
12 
45 
45 
40-45 
45 
45 
45 
45 
45 
40 
40 
40 
40 
45 
45 
45 
12 
45 
38 
36 
36 
36 
36 
36 
30 
25 
30 
700 
600 
Irregular 
100 
2002 
300-400 
600-500 
500 
400 
1,000 
400 
1,000 
350 
1,050' 
200 
900 
200-250 
700-900 
300-400 
1,200 
1,250* 
100 
200 
150 
300 
200 
200-350 
744-800 
350-375 
600 
200 
500 
200 
1,550 
200 
900 
5,423 
1,150 
1,690 
1,000 
1,000 
800 
1,250 
400 
1.8 
1.0 
0.1 
0.2 
8.5 
3.6 
8.6 
1.0 
1.1 
0.2 
0.6 
0.3 
3.1 
0.2 
1.8 
0.2 
5.6 
0.1 
0.2 
0.8 
0.1 
0.8 
- 
3.0 
0.8 
47 
45 
45 
12 
12 
12 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
12 
45 
45 
47 
45 
45 
45 
45 
45 
45 
30 
30 
36 
31-36 
- 1.2 
667 0.1 
- 1.4 
600 0.1 
- 1.1 
500 0.1 
- 0.5
1 
' 
3
3
3 
L

TABLE 31-F 
Adopted Project 
Dimensions Improved Project Dimensions 
Uepth in Depth in 
Feet Feet 
See (Below (Below Bottom 
Section Mean Low Bottom Mean Low Width Length 
in Text Project 
5. (Continued) 
6. Galveston 
Harbor and 
Channel, TX 
8. Houston Ship 
Channel, TX 
9. Matagorda Ship 
Channel, TX 
10. Sabine-Neches 
Waterway, TX 
Tide) Width (Feet) Tide) (Feet) Feet iles 
7504 
800 
800 
800 
2,8751 
800 
1,125 
Section of Waterway 
Brazos Harbor Turning 
Basin 
Entrance Channel 
Outer Bar Channel 
Inner Bar Channel 
Anchorage Basin 
Bolivar Roads Channel 
Bolivar Roads Channel to 
43rd St. 
Bolivar Roads to Morgan 
Point 
Morgan Point to Boggy 
Bayou 
Boggy Bayou to Greens 
Bayou 
Greens Bayou to Sims Bayou 
Hunting Bayou Turning 
Point 
Clinton Island Turning 
Basin 
Sims Bayou to Southern 
Pacific Slip 
Southern Pacific Slip to 
Houston Turning Basin 
Houston Turning Basin 
Upper Turning Basin 
Brady Island Channel 
Barbour Terminal Channel 
Turning Basin 
Bayport Ship Channel 
Turning Basin 
Anchorage Area 
Five-Mile Cut Channel 
Light-Draft Channel: 
Upper Turning Basin to 
Jensen Drive 
Turkey Bend Channel 
Greens Bayou Channel: 
Mile 0 to Mile 0.36 
Mile 0.36 to Mile 1.57 
Outer Bar and Jetty Channel 
Channel to Point Comfort 
Approach Channel to 
Turning Basin 
Turning Basin 
Channel to Port Lavaca 
Lynn Bayou Turning Basin 
Channel to Harbor of Refuge 
North-South Basin 
East-West Basin 
Channel to Red Bluff 
Sabine Bank Channel 
Sabine Pass Outer Bar 
Channel 
Sabine Pass Jetty Channel 
Sabine Pass Anchorage 
Basin 
Sabine Pass Channel 
Port Arthur Canal 
Entrance to Port Arthur 
Turning Basins 
Port Arthur East Turning 
Basin 
36 
52 
52 
50 
36 
50 
40 
40 
40 
40 
40 
40 
40 
40 
36 
36 
36 
10 
40 
40 
40 
40 
40
8 
10 
10 
40 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12
6 
42 
42 
40 
40 
40 
40 
40 
40 
525-675 
800 
800 
800 
2,875 
800 
1,125 
400 
400 
300 
300 
900-1,0009 
8009 
300 
300 
400-1,000 
150 
60 
300 
2,000 
300 
1,600 
150 
125 
60 
60 
175 
100 
300 
300-2008 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
800 
800 
800-500 
1,500 
500 
500 
275-678 
420 
6;75 0.1 
- 4.7 
- 1.7 
- 3.2 
- 1.81 
- 1.0 
- 3.9 
- 26.2 
- 12.8 
OA 
30 
42 
42 
40 
36 
40 
40 
40 
40 
40 
40 
40 
40 
40 
36 
36 
36 
10 
40 
40 
40 
40 
40
8 
10 
10 
40 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12
6 
42 
42 
40 
40 
40 
40 
40 
40 
400 
400 
300 
300 
948-1,0009 
965-1,0709 
300 
300 
400-1,000 
150 
60 
300 
2,000 
300 
1,600 
150 
125 
60 
60 
175 
100 
300 
300-2006 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
800 
800 
800-500 
1,500 
500 
500 
275-678 
370-547 
- 4.1 
- , 0.8 
- 0.3 
- 1.3 
- 3.2 
- 20.9 
- 1.1 
00 0.2 
- 4.1 
32 0.1 
- 1.9 
82 0.3 
'50 0.3 
- 20.2 
- 14.7 
- 3.4 
- 4.1 
)00 
65 
- 
5.6 
6.2 
0.3 
0.3 
1,0
5 
1,6 
1,7 
3,0 
1,7 
31-37 
GALVESTON, TEXAS, DISTRICT 
CHANNEL DIMENSIONS 
- 5.3 
1,375 - 
1,592 - 
- 0.6 
- 2.9 
3,100 0.6 
1,000 0.2 
- 0.9 
- 3.1 
2,000 0.4 
- 3.8 
1,000 0.3 
- 1.9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-F CHANNEL DIMENSIONS 
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Depth in 
Feet Feet 
See (Below (Below Bottom 
Section Mean Low Bottom Mean Low Width Length 
in Text Project Section of Waterway Tide) Width (Feet) Tide) (Feet) Feet Miles 
10. (Continued) Port Arthur West Turning 
Basin 40 600 40 350-550 1,610 0.3 
Channel connecting Port 
Arthur West and Taylors 
Bayou Turning Basins 40 200-250 40 200-250 - 0.6 
Taylors Bayou Turning Basin 40 150-1,000 40 90-1,233 3,470 0.7 
Sabine-Neches Canal, Port 
Arthur Canal to Neches 
River 40 400 40 400 - 11.2 
Turning Point at Mile 19.5 40 9004 40 9004 - 8 
Neches River, Mouth to 
Maneuvering Area Beaumont 
Turning Basin 40 400 40 400 - 18.3 
Turning Point, Mile 31.1 40 1,0004 40 1,000 700 8 
Turning Point, Mile 36.6 40 1,0004 40 1,000 930 8 
Turning Point, Mile 40.3 40 1,0004 40 1,300 1,530 8 
Channel Extension, Mile 
40.3 36 350 36 350 1,265 0.2 
Maneuvering Area at 
Beaumont Turning Basin 40 Irregular 40 Irregular 1,300 0.2 
Beaumont Turning Basin 34 500 34 160-535 1,500 0.3 
Beaumont Turning Basin 
Extension 34 350 34 300 - 0.4 
Beaumont Turning Basin 
Extension to End of Project 
Channel Vicinity 
Bethlehem Steel Company 30 200 30 200 - 0.7 
Sabine-Neches Canal, Neches 
River to Sabine River 30 200 30 200 - 4.4 
Sabine River Channel, Mouth 
to Foot of Green Ave. 30 200 30 200 - 9.5 
Orange Turning Basin 30 Irregular 30 Irregular 1,550 0.3 
Orange Municipal Slip 30 200 30 150-200 2,435 0.5 
Old Channel Around Harbor 
Island 25 150-200 25 150-200 - 2.4 
Channel to Echo7 12 125 - - - - 
Adams Bayou 12 100 12 100 - 1.7 
Cow Bayou 13 100 13 100 - 7.0 
Orangefield Turning Basin 13 300 13 300 500 0.1 
1 Average. 
2 Includes 100-foot channel width. 
4 Includes 450-foot channel to Corpus Christi. 
4 Diameter. 
6 Includes 350-foot channel width. 
6 300-foot width through Matagorda Peninsula. 
7 Deauthorized. 
8 Included in channel length. 
* Includes 300-foot channel width. 
31-38

GALVESTON, TEXAS, DISTRICT 
TABLE 31-G 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Tributary Channel 
Offats Bayou 
Main Channel 
West Wye 
Chocolate Bayou Channel 1 
12-Foot Channel via 
East Turnout 2 
West Turnout 3 
9-Foot Channel 4 
Turning Basin 
San Bernard River Channel 5 
Colorado River Channel 6 
Turning Basin 
Silting Basin 
Mouth of Colorado River 
Navigation Channel, GIWW to Gulf 
Turning Basin at Matagorda 
Channel to Palacios 
Turning Basin No. 1 
Turning Basin No. 2 
Connecting Channel 
Channel to Barroom Bay 
Channel to Victoria Main Channel via 
East Turnout 
Turning Basin 
West Turnout Channel 
Channel to Seadrift via South Turnout 
Turning Basin 
North Turnout Channel 
Harbor of Refuge at Seadrift Channel 
Basin 
Channel to Rockport 
Turning Basin 
Channel to Aransas Pass 
Turning Basin 
Channel to Conn Brown Harbor 
Conn Brown Harbor 
Channel to Port Mansfield to 
Entrance Channel 
Approach Channel to Hopper Dredge 
Turning Basin 
Hopper Dredge Turning Basin 
Channel Across Padre Island and 
Laguna Madre 
Turnout Channels, East Side of Main 
Channel, GIWW 
North Turnout 
South Turnout 
Channel West Side of Main Channel, 
GIWW, to P.T. of Turnout Channels 
Turnout Channels, West Side of Main 
Channel, GIWW 
North Turnout 
South Turnout 
Channel from P.T. of Turnout Channels to 
Approach 
Channel to Main Turning Basin 
Approach Channel to Main Turning 
Basin 
Main Turning Basin 
Turning Basin Extension 
Small Craft Basin 
Shrimp Basin 
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Uepth in 
Feet (Below Bottom Feet (Below 
Mean Low Width Mean Low Bottom Length 
Tide) (Feet) Tide) Width (Feet) Feet Miles 
12 
12 
12 
12
999999 
15-12 
12 
12 
12 
12 
12 
12 
12 
12
9999
9999 
14 
14 
14 
14 
16 
16 
16 
14 
12 
12 
14 
12 
12 
14 
14 
14 
14
8 
12 
125 
125 
125 
125 
100 
600 
100 
100 
400 
150 
200-100 
350 
125 
200 
300 
150-480 
60 
100 
600(AVG) 
100 
100 
250 
100 
100 
200 
200 
475 
175 
300 
125 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
125 
200 
400 
1,000 
160 
350 
12 
12 
12 
12
9999 
12 
12 
12 
12
999999 
99 
14 
14 
14 
14 
16 
16 
16 
14 
12 
12 
14 
12 
12 
14 
14 
14 
14
8 
12 
125 
125 
125 
125 
100 
100 
400 
150 
125 
200 
300 
130-400 
100 
500(AVG) 
100 
100 
200 
100 
200 
342(AVG) 
125-175 
300
0.2 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
125 
200 
400 
1,000 
160 
350 
2,200 
500 
635 
1,130 
80 
23 
1,22 
2,21 
12 
1,80 
3C 
2.3 
0.4 
8.2 
0.8 
26.0 
15.5 
0.1 
1.0 
16.1 
0.1 
0.2 
0.1 
- 34.8 
)0(AVG) 0.1 
- 0.8 
- 2.0 
30 - 
- 0.5 
- 2.1 
5 0.2 
- 6.1 
.2 0.4 
5 - 
)0 0.3 
- 0.8 
- 0.4 
)0 0.1 
- 7.7 
- 0.6 
- 0.6 
- 0.6 
- 0.6 
- 0.6 
- 0.6 
- 0.3 
1,250 0.2 
580 0.1 
860 0.2 
1,450 0.3 
31-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 31-G 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Depth in 
Feet (Below Bottom Feet (Below 
Mean Low Width Mean Low Bottom Length 
Tributary Channel Tide) (Feet) Tide) Width (Feet) Feet Miles 
Channel to Harlingen via South Turnout 
from Main Channel, GIWW 12 125 12 12511 - 25.812 
Turning Basin near Rio Hondo 12 400 12 400 500 0.1 
North Turnout from Main Channel 12 200 12 200 - 0.7 
Port Isabel Side Channels 
Main Channel 12 125 12 125-90 - 0.6 
Main Channel 12 233-60 12 233-60 - 0.4 
South Leg 12 125 12 125 - 0.2 
Port Isabel Small Boat Harbor 
Entrance Channel 7 75 7 75 - 1.4 
Harbor Channel 6 50 6 50 - 0.3 
Boat Basin 6 Variable 6 72-501 1,308 0.2 
1 Includes the construction of a salt water barrier at 
Mile 16.9. 
2 Constructed 10 feet deep by 100 feet wide by local 
interests. East turnout channel constructed 150 feet wide. 
3 Constructed by local interests. 
4 Authorized to mile 13.2. Mile 8.2 to Mile 13.2 was 
deauthorized. 
5 Authorized to Mile 31 above mouth (channel mile 
29.41). Upper 3.4 miles was deauthorized under Section 12 of 
PL 93-251. 
6 Includes a discharge channel from Matagorda, 
Texas, to the gulf which was dredged by local interests in 
1939. (Maintenance will be discontinued upon completion of 
improvements authorized by R&H Act of 1968.) 
7 Authorized by R&H Act of 1968. Also provides for 
a dam across the present discharge channel, a new 250-foot 
wide by 20 to 23-feet deep discharge channel into Matagorda 
Bay, and a 15-foot by 200-foot wide entrance channel with 
parallel jetties from the gulf shoreline into the Gulf of 
Mexico. East jetty to be 3,500 feet long and west jetty 2,900 
feet long.
8 Includes two protective breakwaters at entrance to 
turning basins. 
9 In the inactive category for maintenance. 
1o Also provides for two stone jetties at the gulf 
entrance about 1,000 feet apart. (North jetty constructed 
2,300 feet long and south jetty constructed 2,270 feet long.) 
11 South turnout is 200 feet wide. 
12 Authorized to mile 31. Mile 25.8 to Mile 31 was 
deauthorized. 
31-40

GALVESTON, TEXAS, DISTRICT 
TABLE 31-H DREDGING OPERATIONS 


Brazos Island Harbor, 
TX (Maintenance) 

Dredging Brazos Island 
Harbor Entrance
Channel 

November 30, 1988 to 
January 16, 1989

731,545 

$1,404,354

Cedar Bayou, TX 
(Maintenance) 

Dredging Cedar Bayou 
Channel 

January 16, 1989 to 
April 10, 1989 

633,636 

$642,328

Corpus Christi Ship 
Channel, TX 
(Maintenance) 

Dredging Light Beacon 
82 thru Main Turning 
Basin 

September 7, 1988 to 
December 12, 1988

606,141 

$469,147

Dredging Corpus Christi 
Entrance Channel 
(Hopper Dredge 
WHEELER) 

October 5, 1988 to 
October 29, 1988 

261,343 

$1,440,000 

Dredging Corpus Christi 
Jetty Channel (Hopper 
Dredge WHEELER) 

September 6, 1989 to 
September 7, 1989

4,972  

$97,500 

Dredging Inner Basin

April 3, 1989 to 
April 12, 1989 

201,671

$271,420

Freeport Harbor, TX 
(Maintenance) 

Dredging Outer Bar and 
Jetty Channels 

August 1, 1988 to 
September 4, 1988

61,480

$79,925 

Dredging Outer Bar and 
Jetty Channels (Hopper 
Dredge WHEELER) 

August 5, 1989 to 
September 24, 1989 

999,961 

$3,217,500 

Galveston Harbor and 
Channel, TX 
(Maintenance)
 
Dredging Bolivar Roads 
to Pier "B" 

April 12, 1989 to 
September 30, 1989

2,528,948 

$1,756,162

Dredging Entrance, 
Outer and Inner Bar 
Channels (Hopper 
Dredge WHEELER)

September 2, 1989 to 
September 30, 1989 

58,938

$336,200 

Gulf Intracoastal 
Waterway Between 
Apalachee Bay, FL and 
Mexican Border 
- Galveston District 
(Maintenance) 

Dredging Channel to 
Victoria and Removal of 
Broken Concrete Chutes

October 1, 1988 to 
January 27, 1989 

692,862

$611,940 
 
Dredging Galveston 
Causeway to Cow Bayou 

October 1, 1988 to 
January 1, 1989

1,381,845

$403,748 

Dredging Main Channel 
in Matagorda Bay 

October 2, 1988 to 
October 25, 1988 

197,056

$250,233

Emergency Dredging 
Vicinity FM 457 

October 7, 1988 to 
October 10, 1988

22,360 

$168,322

Dredging Chocolate 
Bayou Channel 
 
October 12, 1988 to 
February 4, 1989 

1,460,058 

$913,752

Dredging Channel to 
Palacios 

October 26, 1988 to 
December 13, 1988 

1,284,247

$497,329 

Emergency Dredging 
Channel to Port 
Mansfield

November 13, 1988 to 
December 7, 1988 

169,585

$345,000 
 
Dredging South Bird 
Island to Mud Flats 

January 5, 1989 to 
September 30, 1989 

1,821,099 

$1,913,790

Dredging Port Isabel to 
Mud Flats and Port 
Isabel Small Boat 
Harbor 

January 22, 1989 to 
September 30, 1989 

1,238,601

$1,470,220

Dredging Main Channel 
GIWW, Channel to 
Victoria and Channel to 
Seadrift 

July 8, 1989 to 
September 11, 1989

1,724,800  

$1,086,400

Dredging Turnstake 
Island to Live Oak Point

July 6, 1989 to 
August 10, 1989  

1,327,691

$690,000 

Dredging Vicinity 
Rollover Pass and Port 
Bolivar 

August 7, 1989 to 
September 30, 1989

587,522

$500,000 

31-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 

Gulf Intracoastal 
Waterway Between 
Apalachee Bay, FL and 
Mexican Border 
- Galveston District 
(Maintenance) 

Dredging Freeport 
Harbor to Vicinity FM
457

September 10, 1989 to 
September 30, 1989 

263,798 

$385,970 

Dredging Main Channel 
in Matagorda Bay 

September 13, 1989 to September 30, 1989 

227,279 

$282,520 


Houston Ship Channel,  
TX (Maintenance) 

Dredging Light Draft 
Channel
 
October 1, 1988 to October 8, 1988

12,811

$166,258

 
Dredging Morgan Point 
to Carpenter Bayou 

October 1, 1988 to January 16, 1989 

2,112,775 

$1,554,086 

Matagorda Ship 
Channel, TX 
(Maintenance) 

Dredging Matagorda 
Peninsula to Point 
Comfort 

January 10, 1989 to March 24, 1989 

3,787,107 

$1,264,003 

Dredging Entrance 
Channel 

January 30, 1989 to February 20, 1989

498,040 

$877,256  

Dredging Channel to 
Port Lavaca and 
Channel to Harbor of 
Refuge 

March 29, 1989 to April 16, 1989 

1,069,665 

$245,466 

Sabine-Neches  
Waterway, TX  
(Maintenance) 

Dredging Sabine Pass
Outer Bar Channel

September 4, 1988 to October 16, 1988 

1,045,159

$937,203 

Dredging Port Arthur 
Turning Basins and 
Junction Area 

August 31, 1989 to September 30, 1989

434,829 

$500,000  


31-42 


ALBUQUERQUE, NM, DISTRICT* 
The district comprises the watershed of the Canadian 
River and its tributaries and the watershed of Arkansas 
River and its tributaries in Colorado including Colorado 
and New Mexico; the watershed of Rio Grande and its 
tributaries including the Pecos River and its tributaries 
upstream of Amistad Lake; and the watershed of the 
Mimbres River and its tributaries in New Mexico. 
Note: The district watershed boundaries were revised in 
June 1986 to include the portion of New Mexico west of 
the Continental Divide. 
IMPROVEMENTS 
Flood Control 
1. Acequias Irrigation System, NM ...... 
2. Albuquerque Diversion Channels, NM ... 
3. Conchas Lake, NM ................ 
4. El Paso, TX ..................... 
5. Fountain Creek, Pueblo, CO ......... 
6. John Martin Reservoir, CO .......... 
7. Puerco River, Gallup, NM ........... 
8. Rio Grande Basin, NM ............. 
8A. Abiquiu Dam, NM ................ 
8B. Cochiti Lake, NM ................. 
8C. Galisteo Dam, NM ................ 
8D. Jemez Canyon Dam, NM ........... 
8E. Rio Grande Floodway, NM .......... 
8F. Truth or Consequences Unit, NM ...... 
9. Santa Rosa Dam and Lake, NM ....... 
Page 
32-1 
32-2 
32-2 
32-3 
32-3 
32-4 
32-4 
32-4 
32-5 
32-5 
32-6 
32-6 
32-6 
32-7 
32-7 
Flood Control (Continued) 
10. Trinidad Lake, CO ................. 
11. Two Rivers Dam, NM ............... 
12. Inspection of completed flood 
control projects .................. 
13. Scheduling flood control 
reservoir operations ................ 
14. Other authorized flood 
control projects .................. 
15. Flood Control work under 
special authorizations .............. 
General Investigations 
16. Surveys ........................ 
17. Collection and study of basic data ...... 
18. Continuation of Planning and Engineering 
19. Advance Engineering and Design ....... 
Flood Control 
1. ACEQUIAS IRRIGATION SYSTEM, 
NM 
Location. There are about one thousand acequias 
throughout the state of New Mexico, most of which are 
located in north-central New Mexico. 
Proposed project. Authorized by the Water Resources 
Development Act of 1986, Section 1113, the 
project consists of about one thousand acequias throughout 
the state of New Mexico. These community ditch 
systems provide irrigation water to about 160,000 acres 
on an estimated 12,000 farms. Acequias have been in 
existence since the early Spanish Colonization period of 
the 17th and 18th Centuries and represent one of the 
oldest forms of cooperative institutions in the United 
States. They are an integral part of the culture and 
heritage of New Mexico. Diversion structures, many of 
which are constructed of available materials such as rock 
and brush, are frequently destroyed by flows greater than 
normal resulting from spring runoff or summer thunderstorms. 
Usually disruption of the ditches occurs during 
peak irrigation season and severely impacts crop production. 
The Water Resources Development Act of 1986 
directs the U.S. Army Corps of Engineers to undertake 
measures, without regard to economic analysis, as are 
necessary to protect and restore the river diversion 
structures and associated canals. 
*All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at 
the end of this chapter. 
32-1 
Page 
32-8 
32-8 
32-9 
32-9 
32-10 
32-10 
32-10 
32-10 
32-10 
32-10

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local Cooperation. The local sponsor, the State of 
New Mexico, has a law whereby the State of New 
Mexico provides 17.5% of the project costs and low 
interest loans to the local Acequias for the remaining 
7.5%. The State of New Mexico has appropriated, and 
will appropriate on an annual basis, the funds necessary 
to meet the requirements of local sponsorship. 
Operation and results during fiscal year. Funds 
to initiate construction were received in Fiscal Year 
1988. Construction contracts were awarded in FY 1988 
and FY 1989. 
Condition at end of fiscal year. Construction was 
completed on structures for seven projects in FY 1989: 
Farmers Mutual Ditch, Heading Structure and Sluice; 
Upper Clyde Ditch, Diversion Structure; Tecolotito 
(upper Anton Chico) Ditch, Flume; Cinco Acequias, 
Diversion Structure; Ortiz Ditch, Heading Structure; 
Acequia Madre del Sur, Diversion Structure and Eledge 
Mill Ditch, Heading Structure. 
2. ALBUQUERQUE DIVERSION 
CHANNELS, NM 
Location. The project is located in an area which 
comprises watersheds of ephemeral streams entering a 
15-mile reach of the Rio Grande from the east at 
Albuquerque, NM, and vicinity. Combined drainage 
area of the tributaries is about 276 square miles. The 
Sandia range of the Rocky Mountains, which is about 12 
miles east of the Rio Grande, forms the eastern border 
of the watersheds. The crest of this mountain range 
rises more than a mile over the river to an elevation of 
10,692 feet above mean sea level. (See Geological 
Survey Map, Albuquerque, NM, quadrangle, scale 
1:62,500.). 
Existing project. Improvements consist of north and 
south diversion channels on high ground east of and 
parallel to the valley. Channels are designed to carry 
floods equal in magnitude to standard project flood from 
all tributaries. For a description of the complete improvement 
and authorizing legislation see page 17-15 of 
Annual Report for FY 1973. 
Local cooperation. Section 2 Flood Control Act of 
1938 applies. For details of local cooperation requirements 
see page 17-2 of Annual Report for FY 1973. 
Operations and results during fiscal year. The 
North Diversion Channels prevented $2,505,600 in flood 
damages during FY 1989. The estimated total accumulated 
flood damages prevented were $80,279,500. Peak 
flood flows recorded during FY 1989 were: North Diversion 
Channel near Alameda 3,510 c.f.s.; South Diversion 
Channel 712 c.f.s.. 
Condition at end of fiscal year. Construction of the 
North and South Diversion Channels began in March 
1965, and was completed in March 1972. The South 
Diversion Channel is in good condition and well maintained 
by the local interests. The North Diversion 
Channel has experienced severe arching and cracking of 
the concrete lined portion. Construction to correct this 
problem was initiated and completed in FY 1987. 
3. CONCHAS LAKE, NM 
Location. The dam is in San Miguel County, NM, on 
the Canadian River, about one-fourth mile downstream 
from the confluence of the Canadian and Conchas Rivers. 
(See Geological Survey State map of New Mexico, scale 
1:500,000, and Geological Survey topographic map. 
Tucumcari quadrangle, scale 1:250,000.) 
Existing project. A concrete gravity main dam section 
1,250 feet long with a maximum height of 200 feet above 
streambed located in the Canadian River Canyon together 
with earth dikes on each side have an overall length of 
about 3.7 miles. The main section contains conduits in its 
base for the release of water to maintain low flows and 
for drainage of the reservoir, and an overflow, ungated 
spillway 300 feet long. The earth dikes vary in height up 
to 100 feet and the north dike contains a concrete ogeetype 
emergency spillway 3,000 feet long. The reservoir 
has a gross storage capacity of 529,000 acre-feet (198,900 
for flood control, 259,600 for water conservation and 
irrigation, and 70,500 dead storage). The dam controls 
7,409 square miles of drainage area. (See page 17-16 of 
Annual Report of 1973 for authorizing legislation.) 
Local cooperation. None Required. 
Operations and results during fiscal year. 
Operation of the reservoir continued. The reservoir was 
operated for storage of floodwater and releases for 
irrigation purposes. $78,400 in sediment damages were 
prevented during FY 1989 while no flood damages were 
prevented. Estimated total accumulated flood and 
sediment damages prevented by the project through FY 
1989 were $3,142,500. Estimated irrigation benefits for 
FY 1989 were $165,000. Estimated total accumulated 
irrigation benefits through FY 1989 were $9,457,400. The 
pool elevation at the start of FY 1989 was 4,190.11 feet 
with corresponding storage of 224,154 acre-feet. Total 
releases for this reporting period were 75,194 acre-feet. 
Releases of 71,708 acre-feet were made to Arch Hurley 
Conservancy District and 3,415 acre-feet to Bell Ranch. 
The pool elevation on September 30, 1989 was 4,190.11 
32-2

ALBUQUERQUE, NM, DISTRICT 
feet with corresponding storage of 224,154 acre-feet. 
Sediment deposition during the fiscal year was 700 acrefeet. 
Condition at end of fiscal year. The existing 
project was essentially complete in 1940. Reservoir and 
appurtenances are in good condition and in operation. 
Irrigation of some lands downstream from the project 
was begun in November 1945. A cost sharing agreement 
between the Government and the State of New 
Mexico for additional Recreation Development at 
Conchas Lake was completed in August 1977. Costs of 
the facilities are 50 percent State of New Mexico and 50 
percent Federal. Construction of recreation facilities was 
initiated in FY 1978 and completed in FY 1983. 
4. EL PASO, TX 
Location. The project is located at El Paso, El Paso 
County, TX, which is on the left bank of the Rio Grande 
in the reach that forms part of international boundary 
between United States and the Republic of Mexico. 
(Geological Survey map for El Paso, TX; New Mexico 
quadrangle, scale 1:250,000.) 
Existing project. This project consists of a singlepurpose 
flood control system of detention dams, 
diversion dikes, conduits and channels to collect, regulate 
and discharge arroyo runoff into the Rio Grande. 
Runoff from the tributary arroyos on the eastern, 
southern, and western slopes of the adjacent Franklin 
Mountains often inundates sections of the city and its 
outlying suburban developments. The project is divided 
into three independent elements: Northwest area, 
Central area, and Southeast area. The project plan 
satisfies the 1933 U.S. and Mexico agreement on limited 
tributary discharge into the Rio Grande in El Paso, 
Texas. (See Table 32-B for authorizing legislation.) 
Local cooperation. Section 2 of the Flood Control 
Act of June 28, 1938 applied for the Northwest and 
Central areas. The Local Cooperation Agreement for the 
Southeast area reflects the cost sharing requirements 
contained in the Water Resources Development Act of 
1986. 
Operations and results during fiscal year. Flood 
control dams in operation during FY 1989 and dates of 
completion of construction are as follows: Northgate and 
Range Dams (February 1973); Sunrise and Mountain 
Park Dams (October 1974); and Pershing Dam (March 
1977); Fort Bliss Diversion Channel (November 1978); 
Oxidation Pond and Buena Vista Diversion and 
Oxidation Pond Outlet Conduit (November 1980); 
Mulberry and Thorn Drive Dams (June 1982); Mesa Dam 
(September 1982); McKelligon Canyon Dam (October 
1982); Keystone Dam (September 1983); Keystone Outlet 
Conduit (March 1984); Highway Diversion Channel (May 
1985); Dam Safety Assurance Program to the existing 
Range and Northgate Dams (May 1986); and Borderland 
Diversion Channel (September 1986). During FY 1989 
flood flows and flood control storage were minimal, 
however, damages which would have resulted from these 
flows were prevented. The estimated total flood damages 
prevented since completion of Northgate and Range Dams 
in 1973 through FY 1989 were $22,700. 
Condition at end of fiscal year. Construction has 
temporarily ended in the Central Area. The only remaining 
work is the Pershing Dam, Dam Safety Assurance. 
The Northwest Area of the project for all practical 
purposes is 100 percent complete. 
The General Design Memorandum for the Southeast 
Area was completed in September 1987 and construction 
was initiated in October 1988 on the Phelps Dodge Basin. 
5. FOUNTAIN CREEK, PUEBLO, CO 
Location. The project is located on Fountain Creek 
approximately 1 mile above the confluence of the 
Arkansas River and Fountain Creek in the city of Pueblo 
in southeastern Colorado. Pueblo is approximately 30 
miles east of the Wet Mountains of the Rocky Mountains. 
(See Geological Survey Map, Northeast Pueblo, CO 
quadrangle, scale 1:24,000.) 
Proposed project. Authorized by the Water Resources 
Development Act of 1986, PL 99-662, the project 
comprises 11,500 feet of channel modification and 9,700 
feet of levee which will provide a 200-year level of protection 
at an estimated first cost of $8,880,000 ($6,410,000 
Federal and $2,470,000 non-Federal). (See Table 32-B for 
authorizing legislation.) 
Local cooperation. The Water Resources Development 
Act of 1986 applies. 
Operations and results during fiscal year. Funds 
for initiation of construction were initially received in 
fiscal year 1987. A construction contract for recreation 
was awarded in September 1987. The remaining 
construction contract for levees and channel work was 
awarded 21 June 1988. 
Condition at end of year. Construction on the levees 
and channel began in July 1988 and the entire project is 
scheduled for completion in March 1990. 
32-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
6. JOHN MARTIN RESERVOIR, CO 
Location. The project is located on the Arkansas 
River, 1,159 miles upstream from its mouth, 300 miles 
downstream from its source, in Bent County, about 18 
miles upstream from the city of Lamar, CO. (See 
Geological Survey maps for Lamar and Las Animas, CO 
quadrangles, scale 1:125,000.) 
Existing project. The project consists of a concrete 
and earthfill structure about 2.6 miles long with a maximum 
height of 106 feet above streambed and an 
overflow, gated spillway 1,174 feet long. Total capacity 
of the reservoir at the spillway crest is 615,500 acre-feet 
(270,200 for flood control and 345,300 for conservation 
and recreation storage). This reservoir controls a 
contributing drainage area of 18,130 square miles and is 
operated as a unit of the coordinated reservoir system 
for flood control in the Arkansas River Basin. Public 
Law 89-298 modified the act of June 22, 1936 (49 Stat. 
1570) to authorize 10,000 acre-feet of reservoir flood 
control storage space for fish and wildlife and recreation 
purposes. For details of the completed improvement and 
authorizing legislation see page 17-16 of Annual Report 
for FY 1973. 
Local cooperation. Section 3 of the Flood Control 
Act of June 22, 1936, applies. 
Operations and results during fiscal year. 
Routine maintenance and operation continued. Regulation 
of conservation storage continued under rules and 
regulations of the Arkansas River Compact. $136,200 in 
sediment damages were prevented during FY 1989. 
Estimated total flood and sediment damages prevented 
by this project through FY 1989 were $91,822,100. 
Estimated irrigation benefits for FY 1989 were $351,700. 
Estimated total accumulative irrigation benefits were 
$24,463,200. Maximum pool elevation of 3,826.58 feet 
with corresponding storage of 125,286 acre-feet occurred 
on March 24, 1989. Total releases for FY 1989 were 
162,845 acre-feet. Releases attributed to irrigation 
benefits amounted to 89,501 acre-feet. Sediment deposition 
was 1,216 acre-feet in FY 1989. 
Condition at end of fiscal year. Storage and 
operation of the reservoir for irrigation began in March 
1943. The reservoir and appurtenances are in good 
condition and in operation. 
7. PUERCO RIVER, GALLUP, NM 
Location. The project is located on the Puerco River 
in the city of Gallup in northwestern New Mexico in 
McKinley County. 
Proposed project. This project was authorized by the 
Water Resources Development Act of 1986, PL 99-662 and 
the Energy and Water Development Appropriations Act of 
1988. The project consists of improvement of existing 
levees, construction of new levees and limited channel 
rectification. The project will provide the 100-year level 
of protection at an estimated first cost of $6,670,000 
($5,000,000 Federal and $1,670,000 non-Federal) 1 October 
1989 price levels. (See Table 32-B for authorizing 
legislation.) 
Local cooperation. The Water Resources Development 
Act of 1986 applies. 
Operation and results during fiscal year. Funds 
to initiate construction were received in Fiscal Year 1988. 
A construction contract for the I-40 Auxiliary Levee was 
awarded in September 1988. The remaining construction 
contracts for the construction of the levees and channel 
improvement were awarded in June 1989. The entire 
project is scheduled for completion in May 1991. 
Condition at end of year. Finalized Construction 
Cost-Sharing Agreement, prepared Plans and Specifications 
and awarded construction contracts. 
8. RIO GRANDE BASIN, NM 
Location. Improvements are on the Rio Grande and 
tributaries in New Mexico. More definite locations and 
descriptions of individual projects are in following paragraphs 
and individual reports by projects. 
Existing project. The Flood Control Act of 1948 
authorized the flood control phase of the comprehensive 
plan of development of water resources of the Rio Grande 
basin in New Mexico (H. Doc 243, 81st Cong., 1st sess.) 
with the exception of Chiflo Dam and Reservoir and 
spillway gate structure at Chamita Dam. Although recommended, 
Chiflo Dam and Reservoir was deleted from the 
authorized plan. It was excluded without prejudice to 
future consideration by Congress. It was requested at 
that time, by the States of Colorado and Texas, that the 
project be deferred for restudy regarding required storage 
and methods of operation. By the same act, Congress also 
authorized for the construction irrigation phase of the 
comprehensive plan as recommended by Bureau of 
Reclamation (H. Doc. 653, 81st Cong., 2nd sess.). The act 
also stipulated that work should be prosecuted in 
accordance with a joint agreement approved by the 
Secretary of the Army and Acting Secretary of the Interior 
on November 21, 1957. In addition, under that agreement 
the Bureau of Reclamation was given responsibility for 
construction, operation, and maintenance of channel 
rectification, and drainage rehabilitation and extension 
32-4

ALBUQUERQUE, NM, DISTRICT 
phases of the unified plan of improvement. Authority 
for the Chamita Dam and Reservoir was abrogated when 
Cochiti Dam and Reservoir was authorized. (See Table 
32-B for authorizing legislation and Table 32-C for 
existing projects.) 
All operations and costs for projects contained in the 
authorized plan are reflected in individual reports on the 
following pages. 
8A. ABIQUIU DAM, NM 
Location. The project is one unit of the flood control 
phase of the comprehensive plan for the Rio Grande and 
tributaries, New Mexico. Abiquiu Dam is on the Rio 
Chama near the town of Abiquiu, NM, about 32 miles 
upstream from the confluence of Rio Chama and Rio 
Grande. (See Geological Survey Map for plan and 
profile of Rio Chama, NM, from mouth to mile 103, 
sheet 1, and Army Map Service, Aztec, NM; Colorado 
NJ 13-1, scale 1:250,000.) 
Existing project. This project consists of an earthfill 
dam 1,540 feet long, 325 feet high, with a 12-foot 
diameter controlled outlet, and an uncontrolled spillway 
in a natural saddle about one mile north of the left 
abutment. The reservoir provides 565,000 acre-feet of 
flood control and sediment storage. Total capacity at the 
spillway crest is 1,212,000 acre-feet. For a detail 
description of the completed improvements and authorizing 
legislation see Annual Report of 1973. A major 
rehabilitation project was completed in September, 1980 
and the recreation facilities were completed in FY 1981. 
Local cooperation. None required. 
Operations and results during fiscal year. 
Routine maintenance and operation continued. Storage 
and flows were regulated in accordance with Section 203, 
Flood Control Act of 1960. On October 1, 1988, the pool 
elevation was 6,218.74 feet. The maximum pool 
(6,221.69 feet) and storage (198,338 acre-feet) occurred 
on March 13, 1989. On September 30, 1989, the pool 
elevation was 6,211.20 feet with a corresponding storage 
of 156,589 acre-feet. There was 1,205 acre-feet of 
sediment deposition during FY 1989. 
There were $28,100 in flood damages prevented during 
FY 1989. 
Sediment damages prevented were $135,000. Accumulated 
flood and sediment damages prevented by the 
project since completion were $232,743,600 through FY 
1989. 
Condition at end of fiscal year. Project was placed 
in operation in February 1963. Project structures are in 
good condition and in operation. On 22 February 1989 a 
contract was awarded for construction of two drainage 
adits to alleviate seepage problems in the north and south 
abutments. Construction of the adits is scheduled to be 
completed in February 1990. 
Emergency gates were not installed in the outlet conduit 
of Abiquiu Dam during its construction. A plan for the 
Abiquiu Dam emergency gates has been prepared in 
accordance with Section 1112 of the Water Resources 
Development Act of 1986. Construction of the emergency 
gates is necessary to increase safety and enhance flood 
and sediment control. 
8B. COCHITI LAKE, NM 
Location. The dam is at river mile 340 on the Rio 
Grande (river mile 0 being at intersection of New Mexico- 
Texas State line with international boundary at El Paso, 
TX), near Pueblo de Cochiti, which is about 50 miles 
upstream from Albuquerque, NM. (See Geological Survey 
Maps, Cochiti Dam, NM, quadrangle and Santo Domingo 
Pueblo, NM, quadrangle, scale 1:24,000.) 
Existing project. This project consists of an earthfill 
dam about 5.4 miles long with a maximum height of 251 
feet above streambed. The project extends generally in 
an east-west line across the Rio Grande to a point about 
2 miles east of the Rio Grande and then southward across 
the Santa Fe River. An uncontrolled spillway with a 460- 
foot-long ogee-weir and a 160-foot notch 10.5 feet deep in 
the center is at the embankment on the south side of the 
Santa Fe River. Operational releases for flood control and 
irrigation are made through a 3-barrel gated conduit in 
the left abutment on the Rio Grande. The reservoir has 
a storage capacity of 492,500 acre-feet for flood control, 
103,800 acre-feet for sediment and 50,130 acre-feet for 
recreation within the sediment space, for a total of 
596,300 acre-feet. The project controls flood waters from 
a 11,695 square mile drainage area. For more 
improvement details see page 17-7 of Annual Report for 
1980. See page 17-14 of fiscal year 1981 Annual Report 
for authorizing legislation. 
Local cooperation. None required. 
Operations and results during fiscal year. The 
project was completed in June 1975. On October 1, 1988, 
the pool elevation was 5,332.41 feet with a corresponding 
storage of 50,312 acre-feet. The maximum pool elevation 
was 5,340.40 feet with a storage of 60,939 acre-feet on 
March 20, 1989. On September 30, 1989 the pool 
32-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
elevation was 5,332.72 feet with a corresponding storage 
of 50,692 acre-feet. There was 738 acre-feet of sediment 
deposition during FY 1989. There were no flood 
damages prevented during FY 1989. Sediment damages 
prevented were $82,700. Accumulated total damages 
prevented are $252,005,600. 
Conditions at end of fiscal year. The dam and 
appurtenances were placed in operation in 1975. The 
Cochiti Recreation area was completed in 1976, with the 
Visitors Center completed in 1977. The Tetilla Peak 
recreation area was completed in 1981. Project 
structures are in good condition and in operation. 
8C. GALISTEO DAM, NM 
Location. The dam is at river mile 12 on Galisteo 
Creek, a tributary of Rio Grande. The reservoir will 
extend upstream from the dam for about 4 miles, near 
the village of Waldo, NM (See Geological Survey Map,. 
San Pedro 1, NM quadrangle, scale 1:24,000.) 
Existing project. This project consists of an earthfill 
dam 2,820 feet long with a maximum height of 158 feet 
above the streambed. The outlet works consist of a 10- 
foot diameter uncontrolled outlet with a discharge 
capacity of 4,980 cubic feet per second with a pool at the 
spillway crest elevation. The spillway is a broad crested 
weir 250 feet long in the right abutment. The flood 
control storage is 89,000 acre-feet. For more details of 
completed improvements and authorizing legislation see 
page 17-17 of Annual Report for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Operation of 
the project began on October 11, 1970. The reservoir 
was empty on October 1, 1988. No storage occurred 
during FY 1989. Peak inflow was 625 c.f.s. and maximum 
outflow was 625 c.f.s. There was 37 acre-feet of 
sediment deposition during the year and the reservoir 
was empty on September 30, 1989. Sediment damages 
prevented during the FY were $4,100 totaling $123,000 
through FY 1989. 
Condition at end of fiscal year. The project was 
placed in operation in October 1970. The project structures 
are in good condition and in operation. 
8D. JEMEZ CANYON DAM, NM 
Location. The project is located in Sandoval County, 
NM, on the Jemez River about 2 miles upstream from 
the confluence of the Jemez River and the Rio Grande, 
about 5 miles northwest of Bernalillo, NM (See Geological 
Survey map for Bernalillo quadrangle, scale 1:125,000.) 
Existing project. This project consists of an earthfill 
dam 780 feet long with maximum height of 135 feet above 
streambed, and off-channel uncontrolled saddle spillway 
400 feet wide, and a 13-foot diameter gated outlet in the 
left abutment with discharge capacity of 8,340 cubic feet 
per second with a pool at spillway crest elevation. The 
dam was raised 14.1 feet and the spillway widened 28 feet 
in 1986 and 1987 to provide adequate discharge capability 
and freeboard allowance to accommodate the revised 
probable maximum flood. The reservoir has a capacity of 
106,100 acre-feet (73,000 acre-feet for flood control and 
33,100 acre-feet for sediment control). For more detailed 
description of completed improvements and authorizing 
legislation see page 17-17 of Annual Report for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. On 
October 1, 1988, the pool elevation was 5,194.77 feet with 
a corresponding storage of 26,753 acre-feet. The 
maximum pool elevation was 5,198.88 feet with a storage 
of 32,465 acre-feet on May 10, 1989. On September 30 
1989 the pool elevation was 5,191.88 feet with a corresponding 
storage of 23,086 acre-feet. The reservoir was 
regulated for sediment control during FY 1989. Sediment 
deposition during FY 1989 was 428 acre-feet. There were 
no flood damages prevented during FY 1989. Sediment 
benefits during FY 1989 were $47,900. Estimated total 
accumulated flood and sediment damages prevented by the 
project through FY 1989 were $11,931,300. 
Condition at end of fiscal year. The project was 
placed in operation in October 1953. The project structures 
are in good condition and in operation. 
8E. RIO GRANDE FLOODWAY, NM 
Location. This project is one unit of the flood control 
phase of the comprehensive plan of improvement for the 
Rio Grande Basin in New Mexico. It is on the Rio 
Grande and covers a section of the river commencing near 
Truth or Consequences (formerly Hot Springs) at about 
river mile 123 and extends upstream to Espanola, NM, 
about river mile 394. (See table 32-D on Rio Grande 
Floodway.) 
Existing project. This project consists of flood 
protection and major drainage improvements by channel 
rectification, levee enlargement and construction, and bank 
stabilization work where needed to protect the levees. 
Construction of the project is a joint undertaking by the 
32-6

ALBUQUERQUE, NM, DISTRICT 
Bureau of Reclamation and the Corps. Portions to be 
done by the Corps will consist of levee enlargement, 
construction, and bank protection work, with channelrectification 
and drainage-rehabilitation work being the 
responsibility of Bureau of Reclamation. Levees constructed 
by local interests exist throughout the reach of 
the river involved, but are not uniform as to grade, 
section, or standard of construction, and in many places 
are threatened by the meandering river. (See Table 32- 
D on existing project and Table 32-B for authorizing 
legislation.) 
Local cooperation. In addition to the usual requirements, 
local interests are responsible for all highway, 
bridge, and public utility relocations or replacements 
required in construction of the project. Local interests 
will also be required to comply with requirements of 
Section 221, 1970 Flood Control Act and PL 91-646 
Uniform Relocation Assistance Act of 1970. Total costs 
for all requirements for the completed Albuquerque unit 
under terms of project authorization were $75,000. 
There were no non-Federal costs in connection with the 
construction of the Cochiti to Rio Puerco unit of 
floodway. The Espanola Valley unit is in the deferred 
category. Neither the city of Espanola nor Santa Clara 
Pueblo have given any indication that they plan any 
positive action to solve the flooding problem. For more 
details see page 17-8 of Annual Report for 1980. 
Operations and results during fiscal year. There 
were no flood damages prevented by the completed 
floodway project during FY 1989. Estimated total accumulated 
flood damages prevented by the floodway project 
through FY 1989 amounted to $44,011,400. The peak 
flow of the Rio Grande through the middle valley was 
3,770 c.f.s. at Albuquerque on April 22, 1989. The peak 
at San Acacia was 3,500 c.f.s. on April 29, 1989. 
Condition at end of fiscal year. Construction of 
the Albuquerque unit of the Rio Grande Floodway 
project is complete. The General Design Memorandum 
for the Bernalillo to Belen unit was completed in June 
1986. The San Acacia to Bosque del Apache unit was 
reclassified to the active category in July 1985. 
Construction was initiated on the Truth or 
Consequences Unit in fiscal year 1989. The Espanola 
Valley unit was reclassified to deferred category on 17 
October 1973. 
8F. TRUTH OR CONSEQUENCES UNIT, 
NM 
Location. This project is located on Cuchillo Negro 
Creek in the vicinity of the city of Truth or 
Consequences, New Mexico. 
Proposed project. The project is authorized by the 
Flood Control Act of 1948 and 1950, modified by the 
Water Resources Development Act of 1986, to provide that 
the Secretary is authorized to construct a flood control 
dam on Cuchillo Negro Creek, a tributary of the Rio 
Grande in lieu of the authorized floodway. The project 
will be constructed at an estimated total cost of 
$13,600,000 ($10,200,000 Federal and $3,400,000 Non- 
Federal) 1 October 1989 price levels. (See Table 32-B for 
authorizing legislation.) 
Local cooperation. Water Resources Development 
Act of 1986 applies. 
Operations and results during fiscal year. A 
contract for the construction of the dam was awarded on 
22 September 1989. 
9. SANTA ROSA DAM AND LAKE, NM 
Location. The project is located on a lake in 
Guadalupe County, on Pecos River, at river mile 766.4 
approximately 7 miles north of Santa Rosa, NM (See U.S. 
Geological Survey map, Corazon, NM, sheet, scale 
1:125,000.) 
Existing project. Operation of the project began in 
November 1979. It consists of an earth and rock fill dam 
1,950 feet long and 212 feet maximum height above the 
streambed. The purposes of the project are flood control, 
irrigation and sediment retention. An unlined, open rock 
cut about 1,000 feet back from the left abutment serves as 
an uncontrolled spillway. The outlet works, located in the 
left abutment, consists of a control tower, intake structure 
with gates, and a 10-foot diameter concrete lined tunnel 
with a terminal flip bucket energy dissipator. Storage 
capacity at the spillway crest is 447,100 acre-feet which 
includes 80,100 acre-feet sediment reserve, 200,000 acrefeet 
irrigation and 167,000 acre-feet flood control storage. 
The surface area of the reservoir at the spillway crest is 
10,685 acres. The contributing drainage area at the dam 
site is 2,434 square miles. 
For a more detailed report of the authorized project 
including the modification to existing Summer Lake see 
page 17-8 of fiscal year 1981 Annual Report. For 
authorizing legislation see page 17-14 of fiscal year 1981 
Annual Report. 
Local cooperation. In addition to first costs, operation 
and maintenance of both reservoirs is the 
responsibility of the Federal Government; however, the 
Carlsbad Irrigation District is required to contribute to 
operation and maintenance costs an equal amount to what 
they now pay toward Sumner Lake. The Carlsbad 
32-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Irrigation District also agreed to use Sumner Lake for 
flood control. Because they realize equivalent benefits 
from storage capacity in Santa Rosa Dam and Lake, they 
will continue to fulfill their repayment obligation. The 
New Mexico Division of Parks manages the recreation 
facilities. Activities include camping, picnicking, boating 
and hiking. 
For more requirements and details on final approval in 
1974 for transfer of irrigation storage from Sumner Lake 
to Santa Rosa Dam and Lake (formerly Los Esteros 
Lake) see page 17-5 of Annual Report for 1980. 
Operations and results during fiscal year. The 
project was completed in late 1979 and reservoir 
operation for irrigation was started in March 1980. Pool 
elevation at the start of the fiscal year was 4,738.25 feet 
with storage of 78,884 acre-feet. Total releases for the 
fiscal year were 85,823 acre-feet. Pool elevation on 
September 30, 1989 was 4,711.99 acre-feet with a 
storage of 22,920 acre-feet. The maximum elevation was 
4,740.87 feet with a storage of 87,396 acre-feet on April 
8, 1989. There was 270 acre-feet of sediment deposition 
during the fiscal year. $6,500 in flood damages were 
presented in FY 1989. Sediment damages prevented 
during the fiscal year were $30,200. Releases attributed 
to irrigation benefits were 78,515 acre-feet. Irrigation 
benefits for the fiscal year were $274,800 with an 
accumulative total of $1,594,900 through FY 1989. 
Condition at end of fiscal year. Construction 
contract for the recreation area was awarded in 
September 1979 and completed in October 1980. Design 
studies for spillway modification were initiated in FY 
1979 and construction was completed in FY 1982. 
10. TRINIDAD LAKE, CO 
Location. This project is located on the Purgatoire 
River about 161 miles above its junction with the Arkansas 
River. The Project is about 4 miles upstream from 
the city of Trinidad, CO. (See Geological Survey map, 
Trinidad, CO, quadrangle, scale 1:24,000.) 
Existing project. The project consists of an earthfill 
dam 6,610 feet long with a maximum height of 200 feet 
above the streambed, an uncontrolled spillway 1,000 feet 
wide in the left abutment, and a 10-foot diameter, gatecontrolled 
conduit in the right abutment with discharge 
capacity of 5,870 c.f.s. with a water surface at top of the 
flood control pool. In 1985, a 3-foot high parapet wall 
on top of the upstream face of the dam and a supplemental 
700-foot wide rock cut emergency spillway 
located on the right abutment were constructed to 
provide adequate discharge capability and freeboard 
allowance to accommodate the revised probable maximum 
flood. The reservoir provides for storage of 60,000 acrefeet 
for flood control, 39,000 acre-feet for sediment, 20,000 
acre-feet irrigation, and 4,500 acre-feet for recreation, a 
total of 123,500 acre-feet. The reservoir controls a 
drainage area of 671 square miles and is operated for 
flood and sediment control, irrigation, and recreation 
purposes. For authorizing legislation see page 17-14 of 
fiscal year 1981 Annual Report. 
Local cooperation. Assurances of local cooperation 
received from City of Trinidad and Purgatoire River Water 
Conservancy District were formally accepted May 11, 1967, 
after execution of irrigation repayment contract. For 
complete details of requirements and costs pertaining to 
the execution of the irrigation repayment contract and the 
addition of permanent storage for recreation facilities see 
page 17-9 of fiscal year 1980 Annual Report. 
Operations and results during fiscal year. The 
reservoir was operated for flood control and irrigation 
releases during the fiscal year. On October 1, 1988 the 
pool elevation was 6,173.73 feet with a corresponding 
storage of 17,751 acre-feet. The maximum pool elevation 
was 6,185.91 feet with a corresponding storage of 26,041 
acre-feet on April 17, 1989. On September 30, 1989 the 
pool elevation was 6,147.35 feet with a corresponding 
storage of 5,753 acre-feet. Sediment deposition during FY 
1989 was 194 acre-feet. Sediment damages prevented 
during FY 1989 was $46,200. Accrued sediment benefits 
are $2,109,900. Irrigation benefits for FY 1989 were 
$90,100. Accrued irrigation benefits through FY 1989 
were $1,316,800. Irrigation releases for the year were 
22,933 acre-feet. 
Conditions at end of fiscal year. The project was 
placed in operation in 1977. The recreation facilities were 
completed in 1980. The Dam Safety Assurance Contract 
was awarded in September 1982 and was completed in 
1Vay rrujc ILeatures are in guuuoo couiiiu iLuIu a in 
operation. 
11. TWO RIVERS DAM, NM 
Location. The project is located about 14 miles 
southwest of Roswell, NM on the Rio Hondo and the 
Rocky Arroyo. The Rio Hondo is formed at the confluence 
of the Rio Ruidoso and the Rio Bonito, near the 
village of Hondo, NM, in the foothills region of Sierra 
Blanca in the southeastern part of Lincoln County, NM, 
and flows generally easterly to its confluence with the 
Pecos River near Roswell, NM (See Geological Survey 
map, Hondo Reservoir quadrangle, scale 1:24,000.) 
32-8

ALBUQUERQUE, NM, DISTRICT 
Existing project. The Diamond "A" Dam is an 
earthfill structure, 4,885 feet long and 98 feet high, with 
a gated outlet. The Rocky Dam is an earthfill structure 
2,940 feet long and 118 feet high with an uncontrolled 
outlet. No provision is made for water storage except 
for flood control. Flood releases will be controlled so 
that flows through Roswell will not exceed the Rio 
Hondo channel capacity which is about 1,000 c.f.s. The 
capacity of the Two Rivers Reservoir at its spillway crest 
is 168,000 acre-feet, of which 18,000 acre-feet are 
provided for sediment reserve. Together these dams 
regulate runoff from 1,027 square miles of drainage area. 
For details of completed improvement and authorizing 
legislation see page 17-18 of Annual Report for 1973. 
Local cooperation. Section 2 Flood Control Act of 
1938 applies and compliance is satisfactory. 
Operations and results during fiscal year. Routine 
maintenance and operation continued. The 
reservoir was empty on October 1, 1988. There were 
$215,000 flood damages prevented during 1989. 
Sediment damages prevented were $28,200. Estimated 
total accumulated flood and sediment damages prevented 
through FY 1989 were $7,997,800. There were 252 acrefeet 
of sediment deposition during FY 1989. The 
accrued sediment benefits through FY 1989 are 
$920,900. 
Condition at end of fiscal year. The project is 
complete and was placed in operation July 1963. The 
project features are in good condition and in operation. 
12. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Included under this heading is inspection of completed 
flood control projects transferred to local interests for 
operation and maintenance. The projects in Texas, 
Colorado, and New Mexico were inspected. Federal 
costs for fiscal year 1989 were $92,321. 
13. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Pursuant to Section 7, Flood Control Act of 1944, five 
projects are operated by others for flood control. These 
projects are Platoro, Pueblo, Sumner, Navajo, and 
Brantley Dams. 
Platoro Dam on the Conejos River above the town of 
Platoro, Conejos County, CO controls runoff from 40 
square miles of high mountain area. The authorized 
purposes are irrigation storage and flood control. Total 
storage is 60,000 acre-feet with the top 6,000 acre-feet for 
flood control. The 54,000 acre-feet is joint use storage 
with flood control on a forecast basis during spring runoff. 
Platoro Dam was authorized by the Interior Appropriation 
Act of 1941. (see H Doc 693, 76th Cong., 3rd Sess.) 
Construction of this project was completed by the Bureau 
of Reclamation in 1952. 
On October 1, 1988 storage in Platoro Reservoir was 
29,182 acre-feet at elevation 9,997.4 feet. Maximum 
storage of 33,913 acre-feet at elevation 10,004.05 feet 
occurred on May 9, 1989. On September 30, 1989, 
storage was 19,430 acre-feet at elevation 9,991.94 feet. 
Peak flow at Mogote gage was 1,470 c.f.s. on May 30, 
1989. There were no flood damages prevented by the 
project during FY 1989. Total flood damages prevented to 
date are at $4,507,500. Total cost for activity, by the 
Corps of Engineers during FY 1989 was $13,549. 
Pueblo Dam is part of the Fryingpan-Arkansas project 
which was authorized under Public Law 87-590, 87th 
Congress, HR 2206 on August 16, 1962. The project was 
completed in August 1975. Pueblo is operated by the 
Bureau of Reclamation and is located at river mile 1,293.7 
on the Arkansas River in Pueblo County, Colorado. 
Pueblo Reservoir has 27,000 acre-feet exclusive flood space 
and 66,000 acre-feet joint use space. 
Operation of Pueblo Reservoir began on February 10, 
1974. Storage on October 1, 1988 was 150,685 acre-feet, 
elevation 4,851.21 feet. Maximum storage during the year 
was 203,429 acre-feet at elevation 4,866.14 feet on April 5, 
1989. Storage on September 30, 1989 was 113,489 acrefeet 
at elevation 4,838.55 feet. There were no flood 
damages prevented in FY 1989. Total cost for FY 1989 
activity, by the Corps of Engineers, was $13,281. Total 
flood damages prevented to date are $2,852,100. 
Sumner Dam is located on the Pecos River at river mile 
710.8 in DeBaca County, New Mexico. Sumner Dam was 
authorized as Alamogordo Dam by the Secretary of the 
Interior under a Finding of Feasibility approved by the 
President of the USA on 6 November 1935, under the 
Federal Reclamation laws. The original project was 
completed in 1937. Modification work of raising the dam 
16 feet, adding a spillway and limiting the service spillway 
floor to 56,000 c.f.s. was completed in 1957. A twentyfour 
inch bypass line was installed in 1977 to pass flows 
less than 100 c.f.s. Storage on October 1, 1988 was 
19,168 acre-feet at elevation 4,248.7 feet. Maximum 
storage for FY 1989 was 34,600 acre-feet at elevation 
4,255.0 feet on March 14, 1989. Storage on September 30, 
1989 was 15,981 acre-feet at elevation 4,243.3 feet. Total 
cost for FY 1989 activity, by the Corps of Engineers, was 
$12,124. 
32-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navajo Dam and Reservoir is located on the San Juan 
River at river mile 298.6 in San Juan County, New 
Mexico. Navajo Dam was authorized as part of a 
Colorado River Storage Project by an act of 84th 
Congress, 11 April 1956 (PL 485). The Bureau of 
Reclamation constructed and is responsible for operation 
of the project. Construction was initiated in June 1958 
and the project was completed and placed in operation 
in March 1963. Storage on October 1, 1988 was 
1,214,973 acre-feet, elevation 6,049.40 feet. Maximum 
storage for FY 1989 was 1,406,160 acre-feet, elevation 
6,064.81 feet on June 20, 1988. Storage on 30 
September 1989 was 1,309,989 acre-feet, elevation 
6,057.30 feet. Total Corps of Engineers cost for FY 1989 
activity was $13,646. 
Brantley Dam on the Pecos River above the town of 
Carlsbad in Eddy County, NM controls runoff from 
13,208 square miles of uncontrolled area. The 
authorized purposes are irrigation, flood control, Fish 
and Wildlife and Recreation and for the elimination of 
the hazards of failure of the McMillan and the Avalon 
Dams. The total storage is 348,544 acre-feet with 
189,000 acre-feet for flood control. The Brantley Dam 
was authorized for construction on 20 October 1972 by 
Public Law 92-514 with the cost ceiling raised for the 
project in October 1980 by Public Law 96-375. On 
September 6, 1988 the conduits were closed and 
Brantley Dam started its initial filling. On September 
30, 1989, the storage was 10,086 acre-feet at elevation 
3,238.9 feet. 
14. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 32-E. 
15. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 858, 80th Congress, as amended (preauthorization). 
Costs during FY 1989 were: Tellbrook Arroyo, Dona 
Ana County, NM $7,950; Willow Creek Floodway, 
Creede, CO $38,291; Zuni River at Zuni, NM $41,257 
and Templeton Gap Floodway, Colorado Springs, CO 
$4,850. 
Emergency flood control activities; repair, flood 
fighting, and rescue work. (Public Law 99, 84th 
Cong., and antecedent legislation.) 
Federal costs for fiscal year 1989 were $169,599 for 
advance preparation, none for flood emergency operations, 
and there were no repair and restoration costs. 
Emergency bank protection (Sec. 14, 1946 Flodd 
Control Act, Public Law 526, 79th Cong.) 
Federal costs during FY 1989 were: San Vicente 
Arroyo, Silver City, NM $12,929; Pinon Bridge, Fountain 
Creek, CO $162,235; Stratmoor Hills, CO $94,718; 
Alameda Street, Santa Fe, NM $18,356; Willow Creek 
(Sewage Lagoons) Creede, CO $5,865; Pueblo State Rec 
Area, Pueblo, CO $2,250; Hampton Arroyo at SH550, 
Aztec, NM $9,607 and Dona Ana Drain, Dona Ana 
County, NM $9,668. 
Snagging and Clearing for Flood Control (Section 
208 of the 1954 Flood Control Act, 83rd Cong.) 
Costs during FY 1989 were: Gallinas River, City of Las 
Vegas, NM $6,489. 
General Investigations 
16. SURVEYS 
Costs for the fiscal year were $839,234 for flood damage 
prevention studies, $67,733 for special studies 
(coordination studies with other agencies), and $576 for 
preauthorization studies. 
17. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $154,546 for flood plain management 
and technical services. 
Hydrologic studies involving collection and study of basic 
dtLG, such as stream flow ata coLllecV#tion of suspndeLJ d 
sediment samples, recording rain gage data, special study 
for Pikes Peak flood warning systems, hydrometeorological 
studies, and sedimentation studies continued. 
Costs during the fiscal year were $31,873. 
18. CONTINUATION OF PLANNING AND 
ENGINEERING 
There was no cost associated with the Continuation of 
Planning and Engineering in FY 1989. 
19. ADVANCE ENGINEERING AND 
DESIGN 
32-10

ALBUQUERQUE, NM, DISTRICT 
Advance Engineering and Design Costs for FY 1989 
were $412,292 for the following flood Control Projects: 
Alamogordo, NM ($2,521); Rio Grande Bernalillo to 
Belen, NM ($49,099); Puerco River and Tribs, Gallup, 
TABLE 32-A COST AND FINA 
NM ($111); Rio Grande Floodway, San Acacia to Bosque 
del Apache, NM ($361,274) and Rio Grande Floodway 
TorC Unit, NM (-$713). 
N CIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
1. Aceauias Irrigation New Work 
System, NM 
2. Albuquerque 
Diversion Channels 
Project, NM 
(Federal Funds) 
(Contributed Funds) 
(Other Contributed 
Funds) 
3. Conchas Lake, NM 
4. El Paso, TX 
5. Fountain Creek 
Pueblo, CO 
6. John Martin 
Reservoir 
7. Puerco River, 
Gallup, NM 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
301,000 
277,737 
1,678,000 
479,263 
23,263 
2,000,000 
1,142,950 
3,678,0005 
1,622,2135 
17,569,450 
17,569,450 
518,356 
518,356 
854,644 
854,644 
13,821,4991 
13,821,4991 
941,000 
905,216 
3,538,000 
3,743,565 
679,322 
725,985 
910,800 
886,032 
598,000 1,729,000 
715,687 792,511 
300,000 2,878,000 
256,135 1,072,391 
955,000 1,085,222 1,501,300 
976,245 1,081,879 1,346,719 
249,000 
249,000 
25,000 
25,000 
275,000 
268,826 
903,300 15,059,794 
942,571 15,034,744 
3,206,000 63,550,294 
3,056,377 62,354,482 
3,032,000 
4,673,143 
6,210,000 
5,998,669 
15,555,3582 
15,555,3582 
2,010,500 19,134,522 
2,176,195 19,119,472 
2,792,000 
396,592 
3,042,0005" 
640,5305.8 
32-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 32-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
8. Rio Grande Basin, NM 
8A. Abiquiu Dam, NM I 
8B. Cochiti Lake, NM I
r
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
26,745,028 
14,318 26,745,028 
1,958,000 3,925,122 1,564,400 
2,032,253 3,682,277 1,788,361 
3,864,200 22,628,528 
3,974,747 22,623,301 
97,084,559 
97,084,559 
1,010,000 1,217,022 1,192,200 
996,402 1,208,537 1,049,950 
1,266,200 13,399,122 
1,454,062 13,397,164 
8C. Galisteo Dam, NM 
8D. Jemez Canyon 
Dam, NM 
8E. Rio Grande Floodway 
8F. Rio Grande Floodway 
T or C Unit, NM 
9. Santa Rosa Dam 
& Lake, NM 
10. Trinidad Lake, CO 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
88,000 
97,215 
1,457,000 
1,457,797 
198,000 
201,545 
367,000 
276,605 
20,833 
491,000 
489,720 
20,746 
459,000 
425,597 
141,000 
135,193 
610,000 
601,864 
233,000 
195,877 
254,000 
366,766 
5,621 
621,000 
627,678 
23,344 
441,000 
485,188 
136,900 
140,391 
9,339 
267,500 
310,108 
393,000 
386,718 
23,277 
601,400 
615,688 
175 
476,100 
475,952 
211,600 
215,037 
371,800 
370,477 
3,422,000 
772,829 
-660 
731,600 
750,828 
363,500 
374,903 
14,275,053 
14,275,053 
1,977,977 
1,976,333 
6,293,972 
6,293,972 
6,195,351 
6,193,729 
4,794,8683 
4,794,8683 
5,183,0004 
2,512,6354' 
41,041,562 
41,039,056 
5,106,200 
5,106,020 
55,774,758 
55,774,758 
5,144,100 
5,141,942 
32-12

ALBUQUERQUE, NM, DISTRICT 
TABLE 32-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sept. 30, 1989 
11. Two Rivers Dam, NM New Work 
Approp. - - - - 4,847,244 
Cost - - - - 4,847,244 
Maint. 
Approp. 209,000 242,000 294,300 280,300 2,984,312 
Cost 214,225 240,312 291,180 290,782 2,983,217 
Includes $3,492,696 maintenance and improvement costs and of Reclamation under memorandum of agreement between that agency 
$869,978 for emergency relief, excludes $2,279,326, cost of initiating and the Corps. 
project under the authority of Emergency Relief Appropriation Act 
of 1935 and $222,669, the cost for work performed with funds 4Starting in FY 1982, AE&D programs are funded through GI 
transferred to the Corps under Public Works acceleration Act of 1962. appropriations. 
2Excludes $59,977 emergency relief funds for new work. Includes 5 Reflects PED funding appropriations beginning in FY 1986. 
$30,000 for Code 710. 
6FY 1986 PED funds were appropriated to and expended by Los 
3Includes funds for preconstruction planning of Espanola Valley Angeles District. 
unit. Excludes $1,000,011 appropriated funds transferred to Bureau 
TABLE 32-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act 
1. Nov. 17, 1986 
4. Oct. 27, 1965 
5. Nov. 17, 1986 
7. Nov. 17, 1986 
Project and Work Authorized 
ACEQUIAS IRRIGATION SYSTEM 
An Irrigation System dating back to the eighteenth century with 
significant engineering works in the settlement and development 
of the western portion of the United States. Restoration and 
preservation of this system has cultural and historic values to 
the region. Measures are necessary to restore and protect the 
river division structures and associated canales. 
EL PASO, TX 
A single-purpose flood control system of detention dams, diversion 
dikes and channels to collect, regulate and discharge arroyo 
runoff in the Rio Grande. Consists of four independent units 
(NW Area, Central Area, and two units, Copper System and 
Bluff Channel of the SE Area.) 
FOUNTAIN CREEK, PUEBLO, CO 
Channel improvements and levee construction on both sides of 
Fountain Creek approximately 1 mile above the confluence of 
the Arkansas River and Fountain Creek. 
PUERCO RIVER, GALLUP, NM 
Channel rectifications, improvement of existing levees and 
construction of new levees on both sides of Rio Puerco in the 
city of Gallup, NM. 
Documents 
Public Law 662, 
99th Cong. 2nd 
sess. (Sec. 1113) 
H. Doc. 207, 89th 
Cong., 1st 
sess. 
Public Law 662, 
99th Cong. 2nd 
sess. 
Public Law 662, 
99th Cong., 2nd 
sess. 
32-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 32-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act 
8. June 30, 1948 
May 17,1950 
July 14, 1960 
November 17, 
1986 
8E. June 30, 1948 
and 
May 17, 1950 
8F. June 30, 1948 
May 17, 1950 
November 17, 
1986 
IContains latest published maps. 
32-14 
-- 
Project and Work Authorized 
RIO GRANDE BASIN, NM 
Authorized to be appropriated $3,500,000 to be expended by the 
Dept. of the Army for partial accomplishment of approved 
general comprehensive plan for the Rio Grande Basin in NM 
and Colorado. 
Authorized to be appropriated an additional $39,000,000 for 
Department of the Army for prosecution of comprehensive plan 
for the Rio Grande Basin. 
Authorized Cochiti Dam on Rio Grande and Galisteo Dam on 
Galisteo Creek as additions to authorized comprehensive plan 
for Rio Grande Basin (Cochiti Dam was authorized in lieu of 
Low Chamita Dam of Chamita Reservoir Project on Rio Chama 
under "substitute plan"). Also authorized to be appropriated 
an additional $58,300,000 for Dept. of the Army for this 
addition to comprehensive plan for the Rio Grande Basin. 
Authorized installation of the Abiquiu Dam Emergency Gates by 
the Water Resources Development Act of 1986 (PL 99-662) 
RIO GRANDE FLOODWAY, NM 
Channel rectification, levee enlargement and construction, and 
bank stabilization on Rio Grande between river mile 123 and 
394 (San Acacia to Bosque Del Apache Unit.) 
TRUTH OR CONSEQUENCES UNIT, NM 
Approved comprehensive plan for Rio Grande Basin is set forth 
in the Report of the Chief of Engineers dated April 15, 1948, 
for flood control of Rio Grande Basin. 
In addition to previous authorizations, the completion of the plan 
approved in the Flood Control Act of 1948, for the Rio Grande 
Basin, at an estimated cost of $39,000,000. 
Modify previous authorizations to provide that the Secretary is 
authorized to construct a flood control dam on Cuchillo Negro 
Creek in lieu of the authorized floodway. 
Documents 
H. Doc. 243, 81st 
Cong.,lst sess. 
Public Law 516, 
81st Cong., 2nd 
sess. 
S. Doc. 94, 86th 
Cong. 
Public Law 662 
99th Cong., 2nd 
sess. 
Cong., 1st sess.' 
and Public Law 
516, 81st Cong., 
2nd sess. 
H. Doc. 243, 81st 
Cong., 1st sess. 
H. Doc. 243, 81st 
Cong., 1st sess. 
Public Law 662, 
99th Cong., 2nd 
sess. (Sec 871)

ALBUQUERQUE, NM, DISTRICT 
TABLE 32-C 
RIO GRANDE BASIN, NM 
RIO GRANDE BASIN, NM: EXISTING PROJECT 
(See Section 8 of Text) 
Miles Drainage Total 
Above Nearest Area (square Estimated 
Project River Mouth Town mile) Description Cost 
Abiquiu Dam Rio Chama 32 Espanola, 2,147 Earthfill 325 feet high, 30,397,096 
NM 1,212,000 acre feet capacity 
Jemez Canyon Jemez 2 Bernalillo, 1,034 Earthfill 136 feet high, 106,100 4,217,206 
Dam NM acre-feet capacity 
Rio Grande Rio Grande 123 - - Channel rectification, levee 25,744,000 
Floodway to 3941 enlargement and construction 
Cochiti Lake Rio Grande 3401 Cochiti, NM 11,695 Earthfill 251 feet high, 596,300 96,900,000 
acre-feet capacity 
Galisteo Dam Galisteo Creek 8 Waldo, NM 596 Earthfill 158 feet high, 89,000 14,340,280 
acre-feet capacity 
River mile 0 is at intersection of New Mexico-Texas State Line with international boundary at El Paso, Texas. 
2Does not include non-Federal costs. 
3Includes $5,383,000 major rehabilitation, $138,900 for recreation facilities and $3,600,000 for emergency gates. 
TABLE 32-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Alamogordo Diversion Channel, Tularosa (closed) Basin, New Mexico 1966 189,356 
Alpine, Texas3 1977 130,488 
Cibolo Creek, Texas1 1983 829,500 
Colorado Springs, Fountain cue Bouille River, Colorado 
(Templeton Gap Floodway) 1959 881,262 
Creede, Willow Creek, Colorado (floodway)1 1952 219,789 
Highway 12, Colorado1 1985 120,500 
Holly, Colorado' 1985 2,021,400 
Las Animas, Colorado2 1980 4,956,000 
Las Cruces, New Mexico2 1980 4,815,236 
Pecos, Texas3 1977 480,273 
Pinon Canyon Dam, Trinidad, Colorado (Sec.212)1 130,678 
Pueblo, Arkansas River, Colorado (floodway levee extension)' 1954 201,958 
Santa Fe River and Arroyo Mascaras, New Mexico3 1983 1,123,900 
Smith Creek, Colorado' 1985 219,000 
Socorro Diversion Channel, Tributaries of Rio Grande, New Mexico1 1965 2,259,328 
ICompleted. hResponsibility of local interests. Inactive. 'Deferred. 
32-15

LOS ANGELES, CA, DISTRICT * 
This district (total area, about 230,000 square miles) 
comprises those drainage basins tributary to the Pacific 
Ocean that are in California between the Mexican 
boundary and Cape San Martin (about 265 miles north 
of entrance to Los Angeles Harbor); lower Colorado 
River drainage (below Lee Ferry, AZ), which is in 
southeastern California, southeastern Nevada, southwestern 
Utah, and all of Arizona, except the northeastern 
corner; that part of the Great Basin that is in southern 
Nevada and southeastern California; and the United 
States parts of those small drainage basins in southern 
Arizona that drain southward into Mexico. 
IMPROVEMENTS 
Navigation Page 
1. Channel Islands Harbor, CA ........... 33-2 
2. Oceanside Harbor, CA ................ 33-2 
3. Redondo Beach Harbor 
(King Harbor), CA .................. 33-2 
4. San Diego Harbor, CA ............... 33-2 
5. Santa Barbara Harbor, CA ............. 33-3 
6. Ventura Harbor, CA ................. 33-3 
7. Reconnaissance and condition surveys ..... 33-3 
Flood Control 
8. Alamo Lake, Bill Williams River, AZ ..... 33-3 
9. Gila River Basin, AZ: ................ . 33-3 
9A. Painted Rock Dam (Gila River), AZ . . .. 33-3 
9B. Phoenix, AZ, and vicinity 
(including New River) ............. 33-3 
9C. Whitlow Ranch Dam, Queen 
Creek, AZ ...................... 33-4 
10. Los Angeles County drainage 
area, CA ......................... 33-4 
11. Mojave River Dam, Mojave River 
Basin, CA ........................ 33-5 
12. Pine and Mathews Canyons Dams, 
Colorado River Basin, NV ............ 33-5 
13. San Luis Rey River, San Luis Rey 
River Basin, CA .................... 33-5 
14. Santa Ana River Basin (and Orange 
County), CA........................ 33-5 
15. Sweetwater River, Sweetwater River 
Basin, CA ........................ 33-5 
16. Telegraph Canyon Creek, Chula 
Vista, CA........................ 33-6 
17. Whitewater River, San Bernardino and 
Riverside Counties, CA ............... 33-6 
18. Inspection of completed flood control 
projects .......................... 33-6 
19. Scheduling flood control reservoir 
operations ....... .................... 33-6 
Flood Control (Cont'd) Page 
20. Flood control work under special 
authorization ...................... 33-6 
General Investigations 
21. Surveys ......................... 33-7 
22. Collection and study of basic data ..... 33-7 
23. Research and development ........... 33-7 
24. Preconstruction engineering and design: .. 33-7 
24A. Little Colorado River at Holbrook, CA... 33-7 
24B. Redondo Beach Harbor (King 
Harbor), CA .................... 33-7 
24C. Rillito River in the vicinity of Tucson, 
Gila River and tributaries, AZ ......... 33-7 
24D. Santa Ana River mainstem, including 
Santiago Creek, Santa Ana River 
Basin, CA 
Tables 
Table 33-A 
Table 33-B 
Table 33-C 
Table 33-D 
Table 33-E 
Table 
Table 
Table 
33-F 
33-G 
33-H 
Table 33-I 
Table 33-J 
...................... 33-7 
Page 
Cost and financial 
statement .............. 33-9 
Authorizing 
legislation .............. . 33-13 
Other authorized 
navigation projects ........ 33-17 
Other authorized beach 
erosion control projects ..... .33-19 
Other authorized flood 
control projects .......... 33-20 
Not applicable 
Deauthorized projects ...... 33-22 
Reconnaissance and 
condition surveys .......... 33-23 
Inspection of completed flood 
control projects........... 33-23 
Flood control work under 
special authorization ....... 33-24 
33-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
Navigation 
1. CHANNEL ISLANDS HARBOR, CA 
Location. On coast of southern California about a 
mile northwest of existing harbor of Port Hueneme, 65 
miles northwest of Los Angeles Harbor, and 345 miles 
south of San Francisco. (See Coast and Geodetic Survey 
Charts 5007 and 5202.) 
Existing project. For details, see page 33-2 of Annual 
Report for 1981. 
Local cooperation. Fully complied with. 
Terminal facilities. Two thousand and six 
hundred boat slips in 9 marinas, with restroom and 
shower facilities; dry storage area for 300 boats with 
3-ton and 1-ton hoist facilities; 2 marine construction 
and repair yards with 5-ton travel lift and 35-ton hoist 
to 70-ton boatway haulout capacities; a fuel dock 
facility; a sport-fishing complex; 6 restaurants; 2 coffee 
shops; 800 waterfront apartments-many with adjoining 
slips; 300 motel units; 4 yacht club buildings; 3 public 
convenience docks; a 66-slip guest boat complex; a 
harbor administration building/harbor patrol office and 
dock complex; a marine emporium complex, housing a 
chandlery store, a sail loft, a delicatessen, a fishing 
tackel shop, yacht sales, an underwater repair service, 
and an adjacent dock complex; a 7-lane free access 
public launch ramp, with paved pay parking for cars and 
trailers; a boaters' convenience center; a commercial 
fishing pier and hoist; 2 large public parks; a fire station; 
and a U.S. Coast Guard station. Waterway-connected 
and north of the harbor is Mandalay Bay, a private 
keys-type waterfront homes development with an area 
for about 500 homes and connected dockage for boats. 
Transition from harbor to Mandalay Bay is restricted by 
a 4-lane high-rise bridge with a clearance height of 29 
feet at high tide. 
Operations during fiscal year. Completed contract 
payment for maintenance dredging of sand trap 
and entrance channel at a cost of $2,789,640 regular 
funds and $713,405 Navy funds. 
2. OCEANSIDE HARBOR, CA 
Location. On coast of southern California at 
Oceanside, about 30 miles north of City of San Diego. 
(See Coast and Geodetic Survey Chart 5101.) 
Existing project. For details, see page 33-4 of Annual 
Report for 1981. 
Local cooperation. Fully complied with for maintenance 
to date. 
Terminal facilities. Berthing for 957 boats (783 
single-tie slips, 38 double-tie slips, and 136 side-ties, of 
which 54 are visitors slips); 12 dry storage spaces at 
Oceanside Marine Center; a fuel dock; a boat hoist; a 
launching ramp, which can accommodate 4 launchings 
at the same time; parking for 1,732 cars, with temporary 
parking for about 141 boat trailers; a boat-repair 
facility; a pump-out facility; a Coast Guard cutter; 
restaurants; retail stores; yacht brokers; a boatel/motel; 
condominiums; and a sport-fishing facility. 
Operations during fiscal year. Completed 
contract payment for maintenance dredging at a cost of 
$40,575 regular funds. Completed second construction 
contract for experimental sand bypass system, pump 
facilities and power system, in June 1989 at a cost of 
$307,077 regular funds. 
3. REDONDO BEACH HARBOR 
(KING HARBOR), CA 
Location. On coast of southern California in 
southern (downcoast) part of Santa Monica Bay about 
18 miles northwest of Los Angeles and Long Beach 
Harbors and about 417 miles southeast of San Francisco 
Bay. (See Coast and Geodetic Survey Charts 5101 and 
5144). 
Existing project. For details, see page 33-4 of Annual 
Report for 1981. 
Local cooperation. Fully complied with. 
Terminal facilities. Consist of 3 boat basins 
containing 1,500 small boat slips; outer harbor 
containing 120 moorings; fuel docks; sewage pump-out 
station; 2 boat hoists; launching ramp for hand carried 
boats; boat repair facilities; marine hardware stores; 
sport-fishing pier, with facilities for the on- and 
off-loading of passengers from vessels for hire; and a 
commercial/recreational/fishing pier adjacent to the 
harbor facilities. 
Operations during fiscal year. Completed contract 
payment for maintenance repair of north breakwater 
at a cost of $200,435 regular funds. 
4. SAN DIEGO HARBOR, CA 
Location. On coast of southern California just 
north of United States-Mexico boundary line, about 
109 miles southeast of Los Angeles and Long Beach 
Harbors. (See Coast and Geodetic Survey Chart 5107.) 
Previous projects. For details, see page 1976 of 
Annual Report for 1915 and page 1642 of Annual Report 
for 1938. 
Existing project. For details, see page 33-4 of Annual 
Report for 1980. 
Local cooperation. Requirements are described in 
full on Page 33-5 of Annual Report for 1980. 
Terminal facilities. Consist of 45,070 feet of 
wharves, exclusive of Government-owned wharves, of 
which 21,070 feet are Port District owned and 24,000 
feet are privately owned. Government-owned wharves 
at North Island are restricted to military use only. 
Operations during fiscal year. Initiated and 
completed maintenance dredging in February 1989 at a 
cost of $598,528 regular funds. 
33-2

LOS ANGELES, CA, DISTRICT 
5. SANTA BARBARA HARBOR, CA 
Location. On coast of southern California 90 miles 
northwest of Los Angeles Harbor and 320 miles 
southeast of San Francisco Harbor. (See Coast and 
Geodetic Survey Chart 5261.) 
Existing project. For details, see page 33-4 of 
Annual Report for 1983. 
Local cooperation. See page 1015 of Annual 
Report for 1969 for items of local cooperation under 
1962 authorized modification of existing project. 
Terminal facilities. A wharf 2,000 feet long; a pier 
325 feet long in harbor for tie-up mooring for Coast 
Guard cutter; a landing float; an open mooring and slip 
anchorage for small craft; and a launching ramp for 
small craft. 
Operations during fiscal year. Completed 
maintenance dredging in September 1989 at a cost of 
$372,010 regular funds. 
6. VENTURA HARBOR, CA 
Location. On coast of southern California about 65 
miles northwest of the City of Los Angeles, about 70 
miles northwest of Los Angeles and Long Beach 
Harbors, and about 6 miles northwest of Channel 
Islands Harbor. 
Existing project. For details, see page 33-5 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Terminal facilities. Two fuel docks; guest berthing 
docks; 3 boat-repair facilities, 1 full service with a 
60-ton travelift, 1 full service with a 150-ton marine 
elevator, and 1 do-it-yourself boatyard with a 20-ton 
travelift; Fisherman's Pier, with 3 50-ton jib cranes for 
off-loading commercial fishing vessels; flake ice 
manufacturing and distribution system; 3 wholesale fish 
buying stations; a retail fish market and seafood 
restaurant; 1,800 boat slips; a mast up dry storage area 
for 112 trailerable boats; a 6-lane deluxe launch ramp; 
2 yacht clubs; restaurants; cocktail lounges; 
sport-fishing facilities; harbor and offshore islands 
excursion boats; 3 yacht sales; marine communications 
sales and services; 3 marine chandleries; 2 public 
restroom buildings; a harbor administration 
building/harbor master's office; a headquarters/visitors 
center for Channel Islands National Park; marine 
related ancillary businesses, including a convenience 
grocery store, a marine bookstore, a dive shop, gift 
shops, and a jewelry store; and a 230-room resort and 
time-share hotel. 
Operations during fiscal year. Completed 
contract payment for maintenance dredging of entrance 
channel and sand trap at a cost of $544,486 regular 
funds. 
7. RECONNAISSANCE AND 
CONDITION SURVEYS 
See table 33-H. 
Flood Control 
8. ALAMO LAKE, BILL WILLIAMS 
RIVER, AZ 
Location. About 70 miles southeast of Kingman, 
AZ, in a narrow gorge at river mile 39 on Bill Williams 
River, AZ, a tributary of Colorado River. 
Existing project. For details, see page 33-7 of Annual 
Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
Initiated preparation of water control manual. 
9. GILA RIVER BASIN, AZ 
9A. PAINTED ROCK DAM (GILA 
RIVER), AZ 
Location. On Gila River (mile 126) about 20 miles 
downstream from Gila Bend, AZ, in Gila River Basin, 
which is a part of Colorado River Basin. 
Existing project. For details, see page 33-9 of Annual 
Report for 1981. 
Local cooperation. Requirements are described in 
full on page 33-9 of Annual Report for 1981. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
9B. PHOENIX, AZ, AND VICINITY 
(INCLUDING NEW RIVER) 
Location. On Cave Creek, Skunk Creek, Dreamy 
Draw, New River, and Agua Fria River in and adjacent 
to metropolitan Phoenix, AZ. 
Existing project. Plan as modified by Division Engineer, 
South Pacific Division, in July 1977, provides for 
four dams and detention basins, one each on Dreamy 
Draw, Cave Creek, Skunk Creek, and New River; Arizona 
Canal diversion channel; channel improvements 
on Cave Creek, Skunk Creek, and New River; flowage 
easements along Skunk Creek and New and Agua Fria 
Rivers; flood plain management along Dreamy Draw, 
Cave Creek, Skunk Creek, and New River; and recreational 
facilities. Approved estimated (1989) first cost for 
modified project is $446,512,000 (full funding estimate 
and includes allowance for estimated inflation through 
construction period), comprising $254,009,000 Federal 
and $192,503,000 non-Federal. Map of modified plan 
is in "Design Memorandum No. 3, General Design Memorandum-
Phase I, Plan Formulation for New River 
and Phoenix City Streams, Arizona," prepared by Los 
Angeles District in March 1976. 
33-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
Local cooperation. Requirements are described in 
full on page 33-9 of Annual Report for 1981. 
Operations during fiscal year. Completed 
construction of Agua Fria River levees in April 1989. 
Continued construction of Arizona Canal diversion 
channel, reach 2B, 47th Drive to 29th Avenue, which is 
about 99 percent complete. Initiated construction of 
Arizona Canal diversion channel, reach 2C, 29th 
Avenue to Cave Creek, Cave Creek channel and 
sediment basin, and recreation, which is about 82 
percent complete. Initiated construction of New River 
bank stabilization and channelization, which is about 77 
percent complete. Completed preparation of plans and 
specifications for recreational facilities, Arizona Canal 
diversion channel, reach 1, Cactus Road to Skunk 
Creek. Completed preparation of plans and specifications 
for Arizona Canal diversion channel, reach 3, 
Cave Creek to Dreamy Draw; and awarded contract in 
July 1989. Continued preparation of plans and 
specifications for Arizona Canal division channel, reach 
4, Dreamy Draw to Cudia City Wash. Administered 
rights-of-way acquisition continued by local interests. 
Costs for construction of channels were $20,583,596 
regular funds, $476,155 required contributed funds, 
and $1,751,340 other contributed funds. Costs for 
construction of levees were $664,230 regular funds, 
$15,636 required contributed funds, and $33,858 other 
contributed funds. Costs for construction of bank 
stabilization were $3,438,502 regular funds and 
$80,947 required contributed funds. Costs for 
relocations were $135,354 regular funds and 450,000 
other contributed funds. Cost for recreational facilities 
was $257,614 required contributed funds. 
9C. WHITLOW RANCH DAM, 
QUEEN CREEK, AZ 
Location. On Queen Creek, AZ, a tributary of Gila 
River, about 10 miles west of Superior, AZ. 
Existing project. For details, see page 33-10 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dam in 
good operating condition; and administered real estate. 
10. LOS ANGELES COUNTY 
DRAINAGE AREA, CA 
Location. Along Los Angeles and San Gabriel Rivers, 
Rio Hondo, and Ballona Creek, and tributaries 
thereof in Los Angeles County, CA. 
Previous project. For details, see pages 1768 to 
1772 of Annual Report for 1941; page 1602 of Annual 
Report for 1942; and page 1535 of Annual Report for 
1943. 
Existing project. Flood control improvements in 
four stream basins in Los Angeles County, CA, as 
follows: Los Angeles River Basin, San Gabriel River 
Basin, Rio Hondo Basin, and Ballona Creek Basin. 
Protection of about 325,000 acres in densely populated 
Los Angeles County, including areas in Los Angeles, 
Pasadena, Glendale, Burbank, and other cities. Five 
flood control dams (Hansen, Lopez, Santa Fe, 
Sepulveda, and Whittier Narrows); debris basins at 
mouths of 22 canyons; channel improvements along 
101.3 miles of Los Angeles River, San Gabriel River, 
Rio Hondo, and Ballona Creek; and channel 
improvements along 192.89 miles of tributary channels. 
For details on units, see Annual Report for 1962. For 
other pertinent information, see table 33-G, 
"Deauthorized Projects." 
A rehabilitation plan was approved in May 1984. 
Deteriorated portions of the Los Angeles River channel 
along a 23.5-mile reach from Lankershim Boulevard to 
Stewart and Gray Road were restored; and the Los 
Angeles River channel along a 1-mile reach upstream 
from Sepulveda Dam in the vicinity of Balboa Boulevard 
was repaired and improved. Federal first cost for 
rehabilitation was $33,780,311. A map of the 
rehabilitation plan is in "General Design Memorandum, 
Los Angeles River Rehabilitation under the Major 
Rehabilitation Program," dated January 1984 and 
revised in March 1984. 
Removal and sale of dredged material from Hansen 
flood control basin for purposes of facilitating flood 
control, recreation, and water conservation were 
authorized as a modification of existing project in 1986. 
Maintenance dreding at mouth of the Los Angeles River 
for the purpose of maintaining the flood control basin 
and navigation safety was authorized as a further 
modification of existing project in 1988. 
Local cooperation. Requirements are described in 
full on page 33-11 of Annual Report for 1981. 
Operations during fiscal year. Operations for 
units in Los Angeles River Basin: (a) Compton Creek: 
Maintained channel in good operating condition from 
Alameda Street to Hooper Avenue storm drain. (b) 
Haines Canyon: Maintained debris basin and channel 
upstream from Plainview Avenue in good operating 
condition and administered real estate. (c) Hansen 
Dam: Maintained dam in good operating condition and 
administered real estate. Continued preparation of 
water control manual. (d) Lopez Dam: Maintained 
dam in good operating condition and administered real 
estate. (e) Los Angeles River channel, Lankershim 
Boulevard to Stewart and Gray Road: Administered real 
estate. Completed construction of twelfth rehabilitation 
contract, main channel invert overlay (Dayton Ave. to 
Soto St.), in December 1988. Initiated and completed 
construction of thirteenth rehabilitation contract, 
expansion joints (Los Feliz to Soto St.), in March 1989. 
Cost for construction of channels was $3,040,646 
regular funds. (f) Sepulveda Dam: Maintained dam in 
good operating condition and administered real estate. 
Operations for units in San Gabriel River Basin: (a) 
Santa Fe Dam: Maintained dam in good operating 
condition and administr'ed real estate. Continued 
preparation of water control manual. (b) San Gabriel 
River channel, San Gabriel Canyon to Santa Fe Dam, 
Approach channel to Santa Fe Dam (remedial work): 
Maintained channel in good operating condition. (c) 
Whittier Narrows Dam: Maintained dam in good 
operating condition and administered real estate. 
33-4

LOS ANGELES, CA, DISTRICT 
Operations for unit in Rio Hondo Basin: Alhambra 
Wash: Maintained channel upstream from Valley 
Boulevard in good operating condition. 
Operations for unit in Ballona Creek Basin: Ballona 
Creek channel and jetties: Maintained channel 
downstream from Washington Boulevard to La Salle 
Avenue and downstream from Los Angeles city 
boundary to ocean; jetties; and Pacific Avenue bridge in 
good operating condition. 
11. MOJAVE RIVER DAM, MOJAVE 
RIVER BASIN, CA 
Location. On Mojave River at the Forks site, just 
downstream from mouth of Deep Creek and about 14 
miles upstream from Victorville, in Mojave River Basin, 
CA. 
Existing project. For details, see page 33-8 of Annual 
Report for 1983. 
Local cooperation. Requirements are described in 
full on page 33-13 of Annual Report for 1981. 
Operations during fiscal year. Maintained dam in 
good operating condition and administered real estate. 
12. PINE AND MATHEWS CANYONS 
DAMS, COLORADO RIVER 
BASIN, NV 
Location. In Lincoln County, NV, about 100 miles 
north of Hoover Dam and about 17 and 20 miles, respectively, 
east of Caliente, NV. 
Existing project. For details, see page 33-13 of 
Annual Report for 1981. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintained dams 
in good operating condition and administered real estate. 
13. SAN LUIS REY RIVER, SAN 
LUIS REY RIVER BASIN, CA 
Location. Lower San Luis Rey River Valley along 
San Luis Rey River from Murray Road (river mile 7.2) 
to Pacific Ocean, San Diego County, CA. 
Existing project. Plan as modified provides for 
about 5.4 miles of double levee; stone-protected 
channel with soft bottom invert; 1,300 feet of parapet 
walls; and 6 interior drainage ponds. Plan also provides 
for recreation features. Approved estimated (1989) first 
cost for project is $44,100,000 (includes allowance for 
estimated inflation through construction period), 
comprising $33,000,000 Federal and $11,100,000 
non-Federal. Map of modified plan is in "Supplement 
to the Phase II General Design Memorandum for the 
San Luis Rey River Flood Control Project (Murray Road 
to Pacific Ocean), Encompassing Pilgrim Creek to 
Pacific Ocean, San Diego County, California," 
prepared by the Los Angeles District in December 1987 
and approved in March 1988. 
Local cooperation. Requirements are described in 
full on page 33-7 of Annual Report for 1987. 
Operations during fiscal year. Completed first 
construction contract, Pacific Ocean to Priory Road, in 
May 1989. Costs for levees were $4,577,108 regular 
funds, $128,762 required contributed funds, and 
-$7,090 other contributed funds. Cost for relocations 
was $84,286 other contributed funds. 
14. SANTA ANA RIVER BASIN (AND 
ORANGE COUNTY), CA 
Location. On Santa Ana River and tributaries and 
on other streams in Orange, Riverside, and San Bernardino 
Counties, CA. 
General plan of improvement. For details, see 
page 33-14 of Annual Report for 1981. 
Existing project. For details on units, see Annual 
Report for 1968. For other pertinent information, see 
table 33-G, "Deauthorized Projects." 
Local cooperation. Fully complied with. 
Operations during fiscal year. (a) Brea Dam: 
Continued preparation of water control manual. 
Maintained dam in good operating condition and 
administered real estate. (b) Carbon Canyon Dam and 
channel: Initiated preparation of water control manual. 
Maintained project in good operating condition and 
administered real estate. (c) Fullerton Dam: Completed 
preparation of water control manual. Maintained dam 
in good operating condition and administered real 
estate. (d) Prado Dam: Maintained dam in good 
operating condition and administered real estate. 
Continued preparation of water control manual. (e) San 
Antonio Dam: Maintained dam in good operating 
condition and administered real estate. Continued 
preparation of water control manual. (f) San Antonio 
and Chino Creeks channel: Maintained project in good 
operating condition and administered real estate. 
15. SWEETWATER RIVER, 
SWEETWATER RIVER 
BASIN, CA 
Location. Lower Sweetwater River Valley, along 
Sweetwater River from Interstate Freeway 805 to San 
Diego Bay, San Diego County, CA. 
Existing project. Plan as modified provides for 
about 3.2 miles of improved trapezoidal channel along 
Sweetwater River from Interstate Freeway 805 to San 
Diego Bay as part of a combined flood control and 
highway project; recreation features; and mitigation 
measures. Approved estimated (1989) first cost for 
project is $53,440,000 (includes allowance for 
estimated inflation through construction period), 
comprising $29,800,000 Federal and $23,640,000 
non-Federal. Map of modified plan is in "General 
Design Memorandum No. 1 for Sweetwater River Flood 
Control Channel, San Diego County, California," 
33-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
prepared by Los Angeles District in March 1982 and 
revised in May 1984. 
Local cooperation. Requirements are described in 
full on page 33-16 of Annual Report for 1981. 
Operations during fiscal year. Completed stage 3 
construction in June 1989. California State Department 
of Transportation awarded contract for and initiated 
creation of marshland, which is about 15 percent 
complete. Initiated preparation of plans and specifications 
for channel excavation west of Interstate 5. 
16. TELEGRAPH CANYON CREEK, 
CHULA VISTA, CA 
Location. In and near the City of Chula Vista, San 
Diego County, CA. 
Existing project. A 0.5-mile-long rectangular 
concrete channel from about 550 feet upstream from 
4th Avenue to 450 feet upstream from Broadway 
Boulevard; two boxes varying from 10 to 12 feet wide 
and 10 to 13 feet high, totaling 0.4 mile in length, that 
would connect the rectangular concrete channel to 
existing 0.2-mile-long culvert, which is incorporated 
into project; a 0.3-mile-long trapezoidal concrete 
channel downstream from Interstate 5; a 0.1-mile-long 
trapezoidal earth-bottom channel leading into San 
Diego Bay; and beautification. Approved estimated 
(1989) first cost for project is $9,618,000 ($5,000,000 
Federal and $4,618,000 non-Federal). 
Local cooperation. Requirements are described in 
full on page 33-9 of Annual Report for 1985. 
Operations during fiscal year. Completed 
construction in July 1989 at a cost of $816,090 regular 
funds and $2,624,155 required contributed funds. 
17. WHITEWATER RIVER, 
SAN BERNARDINO AND 
RIVERSIDE COUNTIES, CA 
Location. In San Bernardino and Riverside 
Counties, CA, from the City of Banning to the Salton 
Sea, and about 100 miles from the City of Los Angeles, 
CA. 
Existing project. Plan provides for an eventreporting 
network of remote precipitation and stream 
gauges in the upstream watersheds, consisting of 19 rain 
gauges,; 3 combination rain and snow gauges; 3 rain, 
snow, and temperature gauges; 13 stream and rain 
gauges; 4 repeaters; and 1 weather station. Latest 
approved estimated (1986) first cost for project is 
$300,000 ($225,000 Federal and $75,000 non-Federal).
Local cooperation. Provide lands, easements, and 
rights-of-way; maintain and operate works after completion; 
and develop, maintain, and implement emergency 
evacuation plans. 
Operations during fiscal year. Continued 
preparation of project plan, which is about 99 percent 
complete. 
18. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection costs for fiscal year from regular funds 
for maintenance were $623,697. (See table 33-I on inspection 
of completed flood control projects.) 
19. SCHEDULING FLOOD 
CONTROL RESERVOIR 
OPERATIONS 
In accordance with section 7, Flood Control Act of 
1944, studies of reservoir operations for flood control 
were conducted; and preparation of regulations for the 
use of storage allocated for flood control was continued 
for the following Bureau of Reclamation projects: 
Hoover Dam and Twitchell Dam. Costs for fiscal year 
from regular funds for maintenance were $56,429. 
20. FLOOD CONTROL WORK 
UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 80-858, as amended (preauthorization) 
See table 33-J on flood control work under special 
authorization. 
Emergency bank protection (sec. 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong.) 
Federal cost for fiscal year was $225,309 for Gila 
River, Pima Bridge, Safford, Graham County, AZ; 
$39,428 for Walnut Canyon, Anaheim, Orange County, 
CA; $16,196 for Arroyo Conejo Creek, Camarillo, 
Ventura County, CA; and $7,661 for Chino Canyon, 
Palm Springs, and $1,161 for Heacock Channel, 
Sunnymead, both in Riverside County, CA. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation) 
Federal cost for fiscal year was $520,591, of which 
$455,429 were for advance preparation and $65,162 
were for rehabilitation. 
Snagging and clearing of navigable streams and 
tributaries in interest of flood control (sec. 208, 1954 
Flood Control Act, Public Law 780, 83d Cong.) 
Federal cost for fiscal year was $4,351 for 
McDonald Canyon, Ventura County, CA. 
Flood insurance activities (sections 1301-1377, 
1968 Housing and Urban Development Act, Public 
Law 90-448, as amended) 
33-6

LOS ANGELES, CA, DISTRICT 
In coordination with flood control activities, flood 
insurance studies were continued in accordance with 
Inter-Agency Agreements at fiscal year cost of $6,118 
under Housing and Urban Development reimbursable 
order. 
General Investigations 
21. SURVEYS 
Fiscal year cost was $5,743,404 regular funds, of 
which $1,154,673 were for navigation studies; $23,313 
were for beach erosion control studies; $2,790,977 were 
for flood control studies; $1,218,537 were for surveys; 
$131,493 were for special studies involving coordination 
with other agencies; $250,638 were for review of 
authorized projects; $173,409 were for miscellaneous 
activities; and $364 were for supplemental 
preauthorization studies, phase I. 
22. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $250,064 for technical 
services, including $13,792 for Sierra Vista, Coches 
County, AZ; $5,295 for Las Vegas Wash, Clark 
County, NV; and $213 for Kershaw Ryan State Park, 
Lincoln County, NV; and $45,320 for flood plain 
management. 
23. RESEARCH AND 
DEVELOPMENT 
Fiscal year costs were $2,816 for hydrologic studies; 
and $3,995 for coastal data collection. 
24. PRECONSTRUCTION 
ENGINEERING AND 
DESIGN 
24A. LITTLE COLORADO RIVER 
AT HOLBROOK, AZ 
Holbrook, Navajo County, AZ, is along the Little 
Colorado River about 150 miles northeast of Phoenix, 
AZ. Project was authorized by Water Resources 
Development Act of 1986, Public Law 99-662, dated 
November 17, 1986. 
Plan of improvement provides for raising and 
extending existing levee along the north bank of the 
Little Colorado River at Holbrook; and adding a south 
bank levee, a low flow channel, recreational facilities, 
and mitigation features. 
Continued preparation of project plan during fiscal 
year. Estimated preconstruction planning cost is 
1,967,000. Total costs during fiscal year were 
$645,259. 
24B. REDONDO BEACH HARBOR 
(KING HARBOR), CA 
Redondo Beach Harbor (King Harbor) is a 
small-craft harbor at the southern end of Santa Monica 
Bay in the City of Redondo Beach, Los Angeles County, 
CA, which is about 17 miles southwest of the business 
center of the City of Los Angeles, CA. Project 
modification was authorized by Water Resources 
Development Act of 1986, Public Law 99-662, dated 
Nobember 17, 1986; and further modification was 
authorized by Water Resources Development Act of 
1988, Public Law 100-676, dated November 17, 1988. 
Plan of improvement to modify existing project 
provides for raising 1,300 feet at the south end of the 
north breakwater to 20 feet, raising 150 feet at the 
shoreward end of the south breakwater to 16 feet, and 
extending the seaward end of the south breakwater 150 
feet.
Continued preparation of project plan during fiscal 
year. Estimated preconstruction planning cost is 
$785,000. Total costs during fiscal year were $576,083. 
24C. RILLITO RIVER IN THE 
VICINITY OF TUCSON, GILA 
RIVER AND TRIBUTARIES, AZ 
Rillito River and associated streams are in the north 
and east parts of the Tucson metropolitan area, Pima 
County, AZ. Project was authorized by Water 
Resources Development Act of 1986, Public Law 
99-662, dated November 17, 1986. 
Plan of improvement provides for bank stabilization 
and grade control structures to prevent degradation; 
landscaping; and recreational features. 
Continued preparation of project plan during fiscal 
year. Estimated preconstruction planning cost is 
$1,900,000. Total costs during fiscal year were 
$340,880. 
24D. SANTA ANA RIVER 
MAINSTEM, INCLUDING 
SANTIAGO CREEK, SANTA 
ANA RIVER BASIN, CA 
Santa Ana River mainstem, including Santiago 
Creek, Santa Ana River Basin, CA, is on Santa Ana 
River and tributaries and on other streams in Orange, 
Riverside, and San Bernardino Counties, CA. Project 
was authorized by Water Resources Development Act of 
1986, Public Law 99-662, dated November 17, 1986; 
and Energy and Water Development Appropriations 
Act of 1988, Public Law 100-202, dated December 22, 
1987. 
Plan of improvement provides for construction of 
Seven Oaks Dam in the San Bernardino Mountains 
north of Redlands, San Bernardino County; 
management of flood plain between Seven Oaks Dam 
and Prado Reservoir; raising Mill Creek levee near 
Redlands; improvement of Oak Street Drain in Corona, 
Riverside County; enlargement of existing Prado Dam 
33-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
and reservoir, Riverside and San Bernardino Counties; 
improvement of lower Santa Ana River channel from 
Prado Dam to Pacific Ocean; improvement of lower 
reach of Santiago Creek channel in Orange County; and 
improvement of San Timoteo Creek channel from 
mouth of San Timoteo Canyon to Santa Ana River; 
recreational development along project length; 
purchase of 8 acres of salt marsh for mitigation of 
project effects; and purchase of 84 acres of wetlands at 
mouth of Santa Ana River for preservation of 
endangered least tern habitat. 
Completed preparation of project plan, phase II, 
during fiscal year. Estimated preconstruction planning 
cost is $28,643,000. Total costs during fiscal year were 
$7,655,186. 
33-8

LOS ANGELES, CA, DISTRICT 
TABLE 33-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
1. Channel Islands 
Harbor, CA 
2. Oceanside 
Harbor, CA 
(Regular Funds) 
Other Contrib. 
Funds) 
3. Redondo Beach 
Harbor (King 
Harbor), CA 
4. San Diego 
Harbor, CA 
(Regular Funds) 
(Required 
Contrib. Funds) 
(Other Contrib. 
Funds) 
5. Santa Barbara 
Harbor, CA 
(Regular Funds) 
6. Ventura 
Harbor, CA 
8. Alamo Lake, 
Bill Williams 
River, AZ 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
- $5,123,345 1 
- 5,123,345 1 
$261,415 $3,203,174 
273,870 3,198,140 
$103,427 $3,053,480 
79,131 3,085,944 
27,850,802 2 
27,847,504 2 
5,019,575 2,518,915 1,940,549 1,137,731 19,844,809 3 
5,192,340 2,301,884 1,619,552 1,392,867 19,406,954 3 
- - - - 491,286 4 
- - - - 491,286 4 
- - - - 1,200,000 
- - - - 1,187,500 
- - - - 4,766,898 5 
- - - - 4,766,898 5 
326,000 
184,273 
143,000 2,535,000 -18,890 4,281,506 6 
293,167 2,289,955 226,299 4,281,506 6 
- 40 
112,300 1,248,243 
113,854 1,224,701 
720,700 
686,790 
1,238 
324,859 
340,156 
- 28,094,095 7 
1 28,093,478 7 
873,000 
880,854 
4,838,867 8 
4,832,237 8 
717,910 
715,215 
1,926,563 9 
1,900,063 9 
- - - 172,000 10 
- - - 172,000 10 
787,000 905,000 158,806 11,159,625 11 
823,733 522,705 541,898 11,158,896 11 
- - - - 1,711,539 12 
- - - - 1,711,539 12 
1,823,920 1,659,500 1,586,000 921,364 19,919,221 13 
1,836,388 1,644,746 1,587,940 936,799 19,918,641 13 
-56 
697,000 
684,246 
581 
777,000 
741,897 
- - 16,934,060 14 
- - 16,934,060 14 
664,000 750,312 7,317,111 
679,831 754,272 7,262,192 
33-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
9A. Gila River Basin, 
AZ, Painted 
Rock Dam 
(Gila River) 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
- 19,980,564 15 
- 19,980,564 15 
651,000 
616,553 
805,000 725,000 681,019 10,396,167 
803,109 732,669 717,117 10,362,754 
9B. Gila River Basin, New Work: 
AZ, Phoenix, Approp. 
AZ, and vicinity Cost 
(including New River) 
(Regular Funds) 
(Required New Work: 
Contrib. Funds) Contrib. 
Cost 
(Other Contrib. New Work: 
Funds) Contrib. 
Cost 
16,539,000 
15,556,495 
34,500,000 18,000,000 25,200,000 
8,925,957 29,663,604 30,548,322 
333,500 745,000 
275,076 251,052 
- 1,730,000 
740,297 282,212 
1,659,600 
564,923 
6,366,620 
2,288,661 
2,551,000 
1,130,390 
1,144,000 
2,351,602 
162,594,297 
152,278,649 
7,624,314 
3,749,050 
11,475,320 
6,069,503 
9C. Gila River Basin, 
AZ, Whitlow 
Ranch Dam, 
Queen Creek 
10. Los Angeles 
County drainage 
area, CA 
(Regular Funds) 
(Required 
Contrib. Funds) 
(Other Contrib. 
Funds) 
11. Mojave River 
Dam, Mojave 
River Basin, CA 
(Regular Funds) 
(Other Contrib. 
Funds) 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Rehab.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
42,000 
39,914 
-
-1,199 
3,444,000 
4,423,901 
6,869,000 
3,929,743 
659 
352,572 
-
- 
161,187 
241,091 
-, 
116,000 
180,500 
- - - 1,867,963 18 
- - - 1,867,963 18 
58,000 74,000 54,000 1,129,413 
52,423 79,631 50,702 1,123,061 
-
4,647 
3,649,400 
2,911,406 
11,121,000 
4,566,377 
366 
107,413 
4,611,040 
5,162,625 
5,124,000 
10,469,266 
200,000 
171,198 
6,880,590 
6,702,794 
-78,000 
3,539,763 
320 - 
377,226,885 17 18 20 
377,194,526 17 19 21 
70,765,050 17 22 
70,120,822 17 23 
34,556,000 
33,780,311 
13,933,341 24 
13,891,552 25 
- 516,000 28 
- 459,985 27 
- 36,644,865 28 
- 36,639,888 28 
- 300,000 179,800 1,148,994 29 
116,365 224,700 255,376 1,117,851 30 
- - - 17,838,198 
- - - 17,838,198 
134,000 151,000 183,000 3,612,548 
115,710 113,743 206,282 3,579,629 
- - - 286,300 
- - - 284,501 
33-10

LOS ANGELES, CA, DISTRICT 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
12. Pine and Mathews 
Canyons Dams, 
Colorado River 
Basin, NV 
13. San Luis Rey 
River, San Luis 
Rey River Basin, 
CA (Regular 
Funds) 
(Required 
Contrib. Funds) 
(Other Contrib. 
Funds) 
14. Santa Ana River 
Basin (and Orange 
County), CA 
(Regular Funds) 
(Required 
Contrib. Funds) 
15. Sweetwater River, 
Sweetwater River 
Basin, CA 
16. Telegraph Canyon 
Creek, Chula 
Vista, CA 
(Regular Funds) 
Required 
Contrib. Funds) 
(Other Contrib. 
Funds) 
17. Whitewater River, 
San Bernardino 
and Riverside 
Counties, CA 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
105,000 
108,416 
301 
436 
1,886,600 
1,982,194 
4,132 
- - - 1,401,248 
- - - 1,401,248 
107,000 56,000 105,000 1,372,356 
106,915 57,637 98,228 1,364,705 
250,000 2,800,000 4,653,000 9,142,000 
223,717 609,990 6,284,196 8,556,178 
2,211 
1,728,000 
1,670,993 
-38,322 
-38,322 
67,555 
130,000 
78,000 
1,589,000 
1,506,188 
100 
6,242,000 6,919,000 600,000 
6,295,436 4,164,487 2,215,062 
68,000 
64,073 
128,762 
77,196 
130,000 
128,762 
78,000 
77,196 
- 47,994,738 31 32 33 
47,994,738 31 32 33 
1,940,061 29,414,471 31 34 35 
2,034,762 29,287,446 31 34 35 
- 3,065,000 38 
- 3,065,000 38 
- 75,000 37 
- 67,655 38 
- 20,885,503 
-364,149 19,358,679 
- 3,400,000 750,000 5,000,000 
3,846 3,134,380 1,018,273 4,997,385 
500,000 2,000,000 1,823,000 4,323,000 
- 1,482,038 2,739,776 4,221,814 
105,000 - - 105,000 
104,941 10 3 104,954 
150,000 250,000 
90,893 50,038 
400,000 
140,931 
1. Excludes $1,361,668 Navy funds; Coast Guard 
costs; and $210,748 other contributed funds. 
2. Includes $55,194 for reconnaissance and condition 
surveys. Excludes $6,337,536 for maintenance 
accomplished with Navy funds. 
3. Includes $76,268 for reconnaissance and condition 
surveys. Excludes $5,807,410 for maintenance 
accomplished with Navy funds. 
33-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
4. For jetty and groin extensions desired by local 
interests. 
5. Excludes Coast Guard costs. 
6. Includes $20,517 for reconnaissance and condition 
survey costs since FY 1958. 
7. Includes $154,704 for new work for previous 
project; $86,352 public works funds; and $1,226,793 
emergency relief funds. Excludes $254,795 Navy funds 
for dredging entrance channel in FY 1961 to depth of 
-42 feet mean lower low water (or 2 feet below project 
depth); and Coast Guard costs. 
8. Includes $59,904 for maintenance for previous 
project and $221,831 for reconnaissance and condition 
surveys since FY 1958. In addition, includes $144 for 
retroactive pay increase shown in "cost" figure only, as 
reported in 1958 Annual Report, page 1430. Excludes 
$270,696 for maintenance accomplished with Navy 
funds. 
9. Includes $4,441 for betterments desired by local 
interests prior to modification by 1986 River and Harbor 
Act. 
10. Excludes Coast Guard costs. 
11. Includes $29,198 public works funds; $11,000 
working funds for work performed in addition to existing 
project; and $19,741 for reconnaissance and condition 
surveys. Excludes $462,986 other contributed 
funds spent by the Corps for maintenance-dredging 
betterments desired by local interests. 
12. Excludes $1,708,836 required contributed funds 
and Coast Guard costs. 
13. Includes $89,819 for reconnaissance and condition 
surveys. Excludes $10,000 other contributed funds. 
14. Includes $57,000 Code 710 funds since FY 1975. 
15. Includes $357,469 Code 710 funds since FY 
1962. 
16. Includes $3,758 Code 710 funds since FY 1962. 
17. Includes $11,008,935 emergency relief funds for 
new work. Excludes $16,726,888 emergency relief 
funds spent by Corps in connection with emergency 
relief (previous) project and $107,939 for minor rehabilitation. 
18. Includes $23,763,900 Code 710 funds since FY 
1974 ($1,226,100 for Sepulveda Dam; $6,290,000 for 
Whittier Narrows Dam; $22,000 for LACDA prototype; 
$535,000 for Hansen Dam; $10,422,100 for Santa Fe 
Dam; $215,000 for Tujunga Wash channel; $8,500 for 
Lopez Dam; $3,562,200 for Los Angeles River and Rio 
Hondo channels; and $1,483,000 for Ballona Creek 
channel). 
19. Includes $23,760,342 Code 710 funds since FY 
1974 ($1,223,226 for Sepulveda Dam; $6,289,734 for 
Whittier Narrows Dam; $22,000 for LACDA prototype; 
$535,000 for Hansen Dam; $10,421,682 for Santa Fe 
Dam; $215,000 for Tujunga Wash channel; $8,500 for 
Lopez Dam; $3,562,200 for Los Angeles River and Rio 
Hondo channels; and $1,483,000 for Ballona Creek 
channel). 
20. Includes $200,000 for Hansen Dam modification 
since FY 1989. 
21. Includes $171,198 for Hansen Dam modification 
since FY 1989. 
22. Includes $8,679,940 for recreational facilities 
since FY 1985 ($8,154,940 for Sepulveda Dam and 
$525,000 for Los Angeles River and Rio Hondo channels). 
23. Includes $8,363,741 for recreational facilities 
since FY 1985 ($7,838,741 for Sepulveda Dam and 
$525,000 for Los Angeles River and Rio Hondo channels). 
24. Includes $13,933,341 Code 710 funds since FY 
1974 ($992,650 for Sepulveda Dam; $6,797,556 for 
Whittier Narrows Dam; $199,541 for Tujunga Wash 
channel; $460,500 for Hansen Dam; $2,824,056 for 
Los Angeles River and Rio Hondo channels; 
$1,467,538 for Santa Fe Dam; and $1,191,500 for 
Ballona Creek channel). 
25. Includes $13,891,552 Code 710 funds since FY 
1974 ($992,650 for Sepulveda Dam; $6,755,767 for 
Whittier Narrows Dam; $199,541 for Tujunga Wash 
channel; $460,500 for Hansen Dam; $2,824,056 for 
Los Angeles River and Rio Hondo channels; 
$1,467,538 for Santa Fe Dam; and $1,191,500 for 
Ballona Creek channel). 
26. Includes $516,000 for recreational facilities since 
FY 1985 ($516,000 for Los Angeles River and Rio 
Hondo channels). 
27. Includes $459,985 for recreational facilities since 
FY 1986 ($459,985 for Los Angeles River and Rio 
Hondo channels). 
28. Non-Federal funds spent by the Federal Government 
to September 30, 1989, for replacements required 
as part of local cooperation and betterments desired by 
local interests. Excludes $4,238,000 other contributed 
funds spent by the Corps in connection with emergency 
relief (previous) project. 
29. Includes $1,148,994 for recreational facilities 
since FY 1984 ($299,194 for Santa Fe Dam; $370,000 
for Los Angeles River and Rio Hondo channels; and 
$479,800 for Sepulveda Dam). 
30. Includes $1,117,851 for recreational facilities 
since FY 1984 ($299,194 for Santa Fe Dam; $338,857 
for Los Angeles River and Rio Hondo channels; and 
$479,800 for Sepulveda Dam). 
31. Comprises funds for Brea, Fullerton, Prado, and 
San Antontio Dams, Carbon Canyon Dam and channel, 
Lytle and Cajon Creek channel improvements, and San 
Antonio and Chino Creeks channel. 
32. Includes $5,000 working funds for San Antonio 
Dam; $67,361 for San Juan Dam (deauthorized unit) 
(also reported under "Deauthorized Projects"); and 
$85,310 undistributed funds. Excludes other contributed 
funds spent by the Corps, as follows: $124,105 for 
water conservation betterments desired by local interests 
at Prado Dam; $8,500 for betterments desired by 
local interests at San Antonio Dam; $234,709 for betterments 
desired by local interests on San Antonio and 
Chino Creeks channel; and $601,762 for required items 
of local cooperation on Lytle and Cajon Creeks channel 
improvements. Excludes $290,000 spent direct by local 
interests on San Antonio and Chino Creeks channel for 
local cooperation items not required. 
33-12

LOS ANGELES, CA, DISTRICT 
TABLE 33-A (Cont'd) COST AND FINANCIAL STATEMENT 
33. Includes $5,920,831 Code 710 funds since FY 
1974 ($1,058,731 for Carbon Canyon Dam and channel; 
$1,264,300 for Fullerton Dam; and $3,597,800 for 
Prado Dam). 
34. Includes $114,000 for recreational facilities since 
FY 1985 ($114,000 for Carbon Canyon Dam and 
channel). 
35. Excludes maintenance for Lytle and Cajon 
Creeks channel improvements, which are operated and 
maintained by local interests. 
TABLE 33-B AUTHORIZING 
36. Includes $3,065,000 Code 710 funds since FY 
1974 ($1,388,651 for Carbon Canyon Dam and channel; 
$1,250,349 for Fullerton Dam; and $426,000 for 
Prado Dam). 
37. Includes $75,000 for recreational facilities since 
FY 1985 ($75,000 for Carbon Canyon Dam and channel). 
38. Includes $67,655 for recreational facilities since 
FY 1986 ($67,555 for Carbon Canyon Dam and channel). 
LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. Sep. 3, 1954 
2. Oct. 27, 1965 
3. May 17, 1950 
4. Mar. 3, 1875 
Sep. 19, 1890 
June 25, 1910 
Mar. 4, 1913 
July 27, 1916 
Aug. 8, 1917 
Aug. 8, 1917 
Sep. 22, 1922 
Mar. 3, 1925 
CHANNEL ISLANDS HARBOR, CA 
Harbor for light-draft vessels and shore protection 
works. 
OCEANSIDE HARBOR, CA 
Maintenance of general navigation features of 
Del Mar Boat Basin and of Oceanside Harbor. 
REDONDO BEACH HARBOR 
(KING HARBOR), CA 
Reconstruction of part of original breakwater and 
construction of extension; construction of south 
breakwater; and maintenance of breakwaters. 
SAN DIEGO HARBOR, CA 
Diversion dike. 
Jetty on Zuniga Shoal. 
Dredge channel through outer bar 30 feet deep 
and 600 feet wide, and a channel through 
middle ground to 30 feet deep. 
Dredge channel through outer bar 570 feet wide 
and 35 feet deep, and a channel through 
middle ground 32 feet deep. 
Widen approach (area B) to San Diego municipal 
pier by dredging area C (north of area B). 
Dredging area A (south of area B). 
Dredge 35-foot channel through middle ground. 
Dredging areas D and E. 
Widen approach (area C) to San Diego municipal 
pier 1 by dredging a portion of area F (north 
of area C). 
H. Doc. 362, 83d Cong., 
2d sess. 
H. Doc. 76, 89th Cong., 
1st sess. 
H. Doc. 303, 81st Cong., 
1st sess. 
Annual Report, 1873; 
p. 1142 
H. Ex. Doc. 177, 50th 
Cong., 1st sess. (Annual 
Report, 1888; p. 2114) 
H. Doc. 961, 60th Cong., 
1st sess. 
H. Doc. 1309, 62d 
Cong., 3d sess. 
H. Doc. 648, 64th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 8, 64th 
Cong., 2d sess. 
H. Doc. 140, 65th Cong., 
1st sess. 
H. Doc. 1000, 66th 
Cong., 3d sess. 
River and Harbors 
Committee Doc. 2, 68th 
33-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
July 3, 1930 
Aug. 30, 1935 1 
Aug. 26, 1937 
Oct. 17, 1940 
Mar. 2, 1945 
Aug. 13, 1968 
5. Aug. 30, 1935 
Mar. 2, 1945 
Oct. 23, 1962 
Dec. 31, 1970 
6. Aug. 13, 1968 
8. Dec. 22, 1944 
9A. May 17, 1950 
Deepen to 40 feet channel through outer bar; along 
south and north banks, main channel; dredge 
turning basin, widen area H, and dredge a 
channel to National City and Chula Vista. 
Widen bay channel to 2,200 feet with depth 
of 35 feet from the vicinity of Whalers Bight 
in lower bay to navel air station opposite 
turning basin. 
Dredging areas Q, Q-1, M, N, and O. 
Dredge a seaplane basin (area S) of about 
3,000 acres, 10 feet deep, and fill an area 
of about 110 acres adjacent to southern end 
of basin. 
Dredge triangular approaches to 26- and 35- 
foot anchorages, area M. 
Deepen and extend existing navigation channels, 
delete uncompleted parts, and extend 
maintenance. 
SANTA BARBARA HARBOR, CA 
Maintenance dredging present depths into harbor 
formed by breakwater constructed by local 
interests. 
Permits maintenance by means of a fixed sandintercepting 
plant to be provided and operated 
by and at expense of local interests. United 
States to contribute to operating expense an 
amount not to exceed $30,000 annually, 
whenever funds are allotted therefor; funds 
thus contributed to be reduced by actual cost 
of harbor maintenance if and when intercepting 
plant has been installed. 
Modification of existing project. 
Dredging and maintenance by United States. 
VENTURA HARBOR, CA 
Adoption and maintenance of existing general 
navigation features of harbor, excluding 
interior basins; construction of an offshore 
breakwater; dredging a sand trap in lee of 
breakwater; repairing existing north and middle 
jetties; and construction of recreational fishing 
facilities on jetty crests. 
ALAMO LAKE, BILL WILLIAMS 
RIVER, AZ 
Multiple-purpose dam and reservoir. 
PAINTED ROCK DAM (GILA RIVER), 
GILA RIVER BASIN, AZ 
Dam and flood control basin. 
S. Doc. 81, 71st Cong., 
2d sess. 
H. Doc. 223, 73d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 89, 
74th Cong., 2d sess. 
H. Doc. 844, 76th Cong., 
3d sess. 
H. Doc. 390, 77th Cong., 
1st sess. 
H. Doc. 365, 90th Cong., 
2d sess. 2 
S. Committee Print, 73d 
Cong., 2d sess. 
H. Doc. 348, 77th Cong., 
1st sess. 
H. Doc. 518, 87th Cong., 
2d sess. 2 
None 
H. Doc. 356, 90th Cong., 
2d sess. 
H. Doc. 625, 78th Cong., 
2d sess. 
H. Doc 331, 81st Cong., 
1st sess. 
33-14

LOS ANGELES, CA, DISTRICT 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
9B. Oct. 27, 1965 
9C. July 24, 1946 
10. June 22, 1936 
May 15, 1937 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sep. 3, 1954 
July 3, 1958 
July 14, 1960 
Oct. 23, 1962 
Dec. 30, 1963 
PHOENIX, AZ, AND VICINITY 
(INCLUDING NEW RIVER), 
GILA RIVER BASIN 
Detention basins, diversion channels, and 
channel improvements. 
WHITLOW RANCH DAM, QUEEN 
CREEK, GILA RIVER BASIN, AZ 
Dam and flood control basin. 
LOS ANGELES COUNTY DRAINAGE 
AREA, CA 
Reservoirs and flood channels for flood control 
and related purposes at an estimated construction 
cost not to exceed $70 million. 
Added flood channels on Ballona Creek and 
tributaries to project. 
Provision of lands, easements, and rights-of-way 
and relocations by Federal Government instead 
of by local interests. (Resultant additional cost 
to the United States, $12,541,000.) 
Project extended to include additional flood control 
reservoirs, flood control channels, and debris 
basins for flood control and related purposes. 
Also authorized to be appropriated $25 million 
for further accomplishment of plan. 
Authorized to be appropriated an additional $25 
million for prosecution of comprehensive plan 
approved in Flood Control Act of Aug. 18, 1941. 
Authorized to be appropriated an additional $25 
million for further prosecution of comprehensive 
plan. 
Rio Hondo channel improvement, Whittier Narrows 
Reservoir to Los Angeles River (in lieu of enlarging 
channel and bridges on San Gabriel River 
downstream from reservoir). Also authorized 
to be appropriated an additional $40 million 
for further prosecution of comprehensive plan. 
Authorized to be appropriated an additional 
$12,500,000 for further prosecution of 
comprehensive plan. 
Authorized to be appropriated an additional 
$44 million for further prosecution of comprehensive 
plan. 
Authorized to be appropriated an additional 
$32 million for further prosecution of comprehensive 
plan. 
Authorized to be appropriated an additional 
$3,700,000 for further prosecution of 
comprehensive plan. 
Authorized to be appropriated an additional 
$30 million for further prosecution of comprehensive 
plan. 
H. Doc. 216, 89th Cong., 
1st sess. 
H. Doc. 220, 80th Cong., 
1st sess. 
None 
None 
None 
H. Doc. 838, 76th Cong., 
3d sess. 
None 
None 
None 
None 
None 
None 
None 
None 
33-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 18, 1965 
Nov. 17, 1986 
Nov. 17, 1988 
11. July 14, 1960 
12. May 17, 1950 
13. Dec. 17, 1970 3 
Nov. 17, 1986 
14. June 22, 1936 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 3, 1958 
In addition to all previous authorizations, completion 
of improvements under the comprehensive 
plan for flood control in the Los Angeles River 
Basin at a presently estimated cost of $31 million 
for completion. 
Authorized modification of Hansen Dam by removing 
and selling dredged material to 
facilitate flood control, recreation, and water 
conservation. 
Authorized modification of Los Angeles River by 
dredging at mouth of river to maintain flood 
control basin and navigation safety. 
MOJAVE RIVER DAM, MOJAVE 
RIVER BASIN, CA 
Dam and reservoir, and an earthfill dike. 
PINE AND MATHEWS CANYONS DAMS, 
COLORADO RIVER BASIN, NV 
Dams and flood control basins. 
SAN LUIS REY RIVER, SAN LUIS REY 
RIVER BASIN, CA 
Channel and levee, and beautification features. 
Authorized non-Federal project cost sharing at a 
minimum of 25 percent and a maximum of 50 
percent. 
SANTA ANA RIVER BASIN (AND 
ORANGE COUNTY), CA 
Reservoirs and flood channels for flood control 
and related purposes for protection of metropolitan 
area of Orange County, at an estimated 
construction cost not to exceed $13 million. 
San Antonio and Chino Creeks channel portion 
of improvement. Authorized to be appropriated 
$6,500,000 for initiation and partial accomplishment 
of plans for those creeks. Rescinded provisions 
of Flood Control Act of 1936, providing 
that local interests pay for relocations, lands, 
easements, and rights-of-way. (Estimated 
resultant additional cost to United States, 
$3,500,000). 
Authorized to be appropriated an additional 
$2,500,000 for prosecution of projects 
approved in above flood control acts. 
Authorized to be appropriated an additional 
$10 million for prosecution of projects adopted 
in above-mentioned flood control acts, including 
projects on Lytle and Cajon Creeks for local 
flood protection at San Bernardino and 
Colton, CA. 
Authorized to be appropriated an additional $8 
million for prosecution of projects approved in 
above-mentioned flood control acts. 
None 
None 
None 
H. Doc. 164, 86th Cong., 
1st sess. 
H. Doc. 530, 81st Cong., 
2d sess. 
S. Doc. 91-106, 91st 
Cong., 2d sess. 
None 
None 
H. Doc. 688, 75th Cong., 
3d sess. 
None 
H. Doc. 534, 78th Cong., 
2d sess. 2 
None 
33-16

LOS ANGELES, CA, DISTRICT 
TABLE 33-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
15. Aug. 13, 1968 
16. Feb. 7, 1985 4 
17. Nov. 17, 1986 5 
SWEETWATER RIVER, SWEETWATER 
RIVER BASIN, CA 
Channel improvement, as part of a combined flood 
control and highway project. 
TELEGRAPH CANYON CREEK, 
CHULA VISTA, CA 
Channel improvements and beautification. 
WHITEWATER RIVER, SAN BERNARDINO 
AND RIVERSIDE COUNTIES, CA 
Flood warning system. 
H. Doc. 148, 90th Cong., 
1st sess. 
None 
None 
1. Included in the emergency relief program, 
May 28, 1935. 
2. Contains latest published map. 
3. Final date of approval by House and Senate 
Public Works Committees resolution under provisions of 
section 201, Public Law 89-298. 
TABLE 33-C OTHER AUTHORIZE 
4. Date approved by Chief of Engineers under 
provisions of section 205, Public Law 80-858, as 
amended. 
5. Date approved by Water Resources Development 
Act of 1986, Public Law 99-662, under provisions 
of section 205, Public Law 80-858, as amended. 
D NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Dana Point Harbor, CA 
Harbor office at Morro Bay, CA 
Los Angeles and Long Beach 
Harbors, CA 
Los Angeles and Long Beach 
Harbors, San Pedro Bay, CA 
Marina del Rey, Los Angeles 
County, CA 
Morro Bay Harbor, CA 
Newport Bay Harbor, CA 
Port Hueneme, CA 
Port San Luis, CA 
Completed 
3 
Completed 
Completed 
Completed 
Inactive & 
Active (mod)3 
Completed 
Completed & 
Active (mod) 
1984 
1988 
1988 
1988 
1982 
1988 
1984 
$4,737,550 1 
64,710,518 4 
4,238,752 6 
2,612,093 8 
796,897 10 
2,051,422 12 
1,457,929 14 
$555,147 2 
17,462,276 s 
2,440,268 7 
12,523,928 9 
622,252 11 
1,293,606 13 
1,062,173 16 
33-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-C (Cont'd) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
San Diego River and 
Mission Bay, CA Completed 1988 11,972,422 18 5,497,316 17 
Sunset Harbor (Bolsa Chica 
Bay), CA 3- -- 
1. Excludes $4,777,000 required contributed 
funds and Coast Guard costs. 
2. Includes $59,187 for reconnaissance and 
condition surveys. 
3. Authorized by Water Resources Development 
Act of 1986, Public Law 99-662, November 17, 1986, 
subject to favorable report. 
4. Includes $2,187,047 for new work for previous 
project; $1,593,667 public works funds; a credit of 
$33,050 for transfer land at Reservation Point; and 
$996,792 of emergency relief funds. Excludes Federal 
funds spent by the Navy for new work on middle 
breakwater; $1,219,655 required contributed funds; 
$37,104,234 other contributed funds, including 
$1,672,575 for new work betterments desired by local 
interests prior to 1976 modification; and Coast Guard 
costs.
5. Includes $139,347 for maintenance for previous 
project, and $205,479 for reconnaissance and 
condition survey costs since FY 1958. Excludes 
$87,120 for maintenance betterments desired by local 
interests prior to 1976 modification. 
6. Excludes $4,238,752 required contributed 
funds; $1,843,146 other contributed funds; and Coast 
Guard costs. 
7. Includes $105,526 for reconnaissance and 
condition surveys. Excludes $114,000 required 
contributed funds; and $75,109 other contributed 
funds. 
8. Navy funds. Excludes $2,128,411 for rehabilitation. 
9. Includes $431,926 for reconnaissance and 
condition surveys since FY 1958 and $307,945 Navy 
funds. Excludes $124,578 other contributed funds. 
10. Public Works administration funds. Excludes 
$796,897 required contributed funds and $1,100 
preauthorization costs. 
11. Includes $168,329 for reconnaissance and 
condition survey costs since FY 1958. Excludes $7,000 
other contributed funds. 
12. Excludes $813,878 other contributed funds. 
13. Includes $93,606 for reconnaissance and 
condition surveys. 
14. Includes $568,417 for new work prior to 
modification by 1965 River and Harbor Act. Excludes 
Coast Guard costs. Includes $344 expended in FY 
1989. 
15. Includes $54,715 for maintenance for project 
prior to modification by 1965 River and Harbor Act and 
$18,958 for reconnaissance and condition surveys. 
16. Excludes $557,832 other contributed funds. 
Includes $2,610,000 regular funds and excludes 
$2,910,000 required contributed funds, both for new 
work on flood control project, "San Diego River Basin, 
Calif." 
17. Includes $103,116 for reconnaissance and 
condition surveys. 
33-18

LOS ANGELES, CA, DISTRICT 
TABLE 33-D OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
*For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Anaheim Bay Harbor, 
Orange County, CA 1 Completed 1967 $89,119 
Bird Rock area, La Jolla, 
San Diego County, CA 2 Completed 1967 25,881 3 
Coast of California, Point Mugu 
to San Pedro breakwater, CA Completed 1972 1,253,594 4 
Doheny Beach State Park (Doheny 
State Beach), CA Completed 1968 587,717 s 
Imperial Beach, CA Active 1986 2,283,932 8 
Las Tunas Beach Park, San Diego 
County, CA Active 1976 107,484 
Ocean Beach, San Diego 
County, CA 7 Completed 1960 7,912 - 
Oceanside, San Diego County, CA Completed 1982 4,367,442 8 - 
San Diego (Sunset Cliffs), CA Active 1979 365,000 s - 
San Gabriel River to Newport Bay 
(Surfside-Sunset and Newport 
Beach), Orange County, CA Active 1985 10,257,465 10 
Ventura-Pierpoint area, CA Completed (part) 1969 715,819 11 
& Deferred (part) 
1. The project authorized by the Act of Congress 
of October 23, 1962, H. Doc. 602, 87th Cong., 2d sess., 
in lieu of part of the original Anaheim Bay Harbor 
project is covered under San Gabriel River to Newport 
Bay (Surfside-Sunset and Newport Beach), Orange 
County, CA. 
2. Authorized by Chief of Engineers under 
authority of section 103, Public Law 87-874. 
3. Excludes $75,614 required contributed funds. 
4. Excludes $1,238,418 required contributed 
funds. 
5. Excludes $431,260 required contributed funds. 
6. Excludes $1,464,677 required contributed 
funds; $66,124 other contributed funds; and Coast 
Guard costs. Includes $227,433 expended in FY 1989. 
7. Plant in service. 
8. Excludes $604,817 other contributed funds. 
9. Excludes $184,336 required contributed funds. 
10. Excludes $4,627,903 required contributed 
funds. Includes $535,365 expended in FY 1989. 
11. Excludes $117,406 other contributed funds for 
beach-nourishment betterments and $618,949 required 
contributed funds. 
33-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allenville, AZ 1 
City Creek levee, San Bernardino 
County, CA 1 
Cucamonga Creek, Santa Ana 
River Basin, CA 
Gila River Basin, AZ: 
Camelsback Dam (Gila River) 
Gila and Salt Rivers levee and 
channel improvements 
Indian Bend Wash 
Lower Gila River levee and 
channel improvements (Gila 
River and tributaries downstream 
from Painted Rock Dam) 
Middle Gila River channel 
improvements, upper end of 
Safford Valley to Buttes 
damsite (Camelsback damsite 
to Salt River) 
Pinal Creek channel improvements 
(Globe) 
Santa Rosa Wash (Tat 
Momolikot Dam and 
Lake St. Clair) 
Tucson diversion channel 
Goleta, CA, and vicinity 
Holbrook levee, Little 
Colorado River, Colorado 
River Basin, AZ 
Los Coches Creek, San Diego 
County, CA 1 
Lytle and Warm Creeks, Santa 
Ana River Basin, CA 
Mission Zanja Creek, 
Redlands, CA 11 
Needles, San Bernardino 
County, CA I 
Oro Grande Wash channel 
improvements, Mojave River 
Basin, CA I 
Quail Wash levee, Joshua Tree, 
San Bernardino County, CA ' 
Ridgecrest, Kern County, CA ' 
Rose Creek channel improvements, 
San Diego, CA 1 
San Diego River (Mission Valley), 
San Diego River Basin, CA 
Santa Ana River Basin, CA: 
Devil, East Twin, and Warm 
Creeks channel improvements 
and Lytle Creek levee 
Mill Creek levees 
Riverside levees 
San Jacinto River levee and 
Bautista Creek channel 
Santa Clara River levee improvement, 
Santa Clara River 
Basin, CA 
Completed 
Completed 
Completed 
Deferred 
Active (part) 
& Deferred (part) 
Completed 
Inactive 
Active 
Deferred 
Completed 
Completed 
Active 
Completed 
Completed 
Completed 
Active 
Completed 
Completed 
Completed 
Terminated 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
1984 
1987 
1963 
1966 
1985 
1975 
1970 
1968 
1982 
1986 
1982 
1950 
1988 
1987 
1988 
1973 
I A 
1973 
1972 
1978 
1962 
1961 
1959 
1985 
1961 
$3,000,000 2 
400,000 3 
93,339,911 4 
73,201 5 
32,459,294 6 
2,413,051 
402,867 
121,509 5 
17,009,754 7 
6,922,631 8 
500,000 
335,000 
3,973,741 s 
37,973,202 10 
1,352,294 
1,000,000 12 
1,000,000 13 
212,745 
195,194 
982,432 14 
1,708,437 
7,753,937 15 
617,890 18 
2,104,478 
9,258,207 17 
2,126,672 
33-20

LOS ANGELES, CA, DISTRICT 
TABLE 33-E (Cont'd) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Santa Maria Valley levees, Santa 
Maria River Basin, CA Completed 1984 10,079,976 18 - 
Santa Paula Creek channel 
and debris basins (including 
Mud Creek), Santa Clara 
River Basin, CA Active 1983 4,790,960 19 - 
Sespe Creek at Fillmore, 
Ventura County, CA 1 Completed 1984 4,000,000 20 
South Fork of the Santa 
Clara River, Santa 
Clarita Valley, CA 1 Active 1985 632,158 - 
Tijuana River Basin, CA Completed 1979 1,703,031 21 - 
Ventura River Basin, CA: 
Stewart Canyon debris basin 
and channel Completed 1964 939,908 22 _ 
Ventura River levee Completed 1950 1,349,638 23 - 
Whitewater River Basin, CA: 
Banning levee-San Gorgonio 
River, Riverside County 1 Completed 1966 97,868 
Chino Canyon improvements, 
Palm Springs 1 Completed 1973 819,878 25 
Tahchevah Creek detention basin 
and channel improvements Completed 1967 1,420,552 26 - 
Tahquitz Creek Inactive 1974 1,063,600 - 
Winslow (tributaries of Little 
Colorado River), Little 
Colorado River Basin, AZ Completed (part) 1973 1,831,300 - 
& Deferred (part) 
West Magnesia Canyon channel, 
Rancho Mirage, CA Completed 1988 4,000,000 24 - 
1. Authorized by Chief of 
authority of section 205, Public 
amended. 
Engineers under 
Law 80-858, as 
2. Excludes $187,965 required contributed 
funds.
3. Excludes $371,058 other contributed funds. 
4. Excludes $584,068 required contributed funds 
and $9,332,327 other contributed funds. Includes 
$6,435 expended in FY 1989. 
5. Advance planning only. 
6. Excludes $304,720 required contributed funds 
and $3,130,762 other contributed funds. Includes 
$650,000 expended in FY 1989. 
7. Includes $6,790,854 expended since FY 1988 
to comply with Tohono O'odham Tat Momolikot Dam 
Settlement Act of October 14, 1986, Public Law 
99-469. Includes $63,048 expended in FY 1989. 
8. Includes $1,158,006 Code 710 funds since FY 
1977. Excludes $749,072 required contributed funds 
and $394,364 other contributed funds. 
9. Excludes $6,319,349 required contributed 
funds. 
10. Excludes $5,499,193 other contributed funds. 
Includes $14,689 expended in FY 1989. 
11. Authorized by Water Resources Development 
Act of 1986, Public Law 99-662, November 17, 1986. 
12. Excludes $619,912 required contributed funds 
and $91,160 other contributed funds. 
13. Excludes $514,806 required contributed funds 
and $176,295 other contributed funds. 
14. Excludes $251,000 required contributed funds 
and $154,733 other contributed funds. 
15. Excludes $200,000 required contributed funds 
and $1,641,668 other contributed funds. 
16. Excludes $35,830 other contributed funds. 
17. Excludes $712,000 other contributed funds. 
18. Excludes $106,364 other contributed funds. 
Includes $49 expended in FY 1989. 
19. Excludes non-Federal costs of $295,000 for 
local cooperation items not required and $49,458 other 
contributed funds. Includes $787 expended in FY 
1989. 
20. Excludes $559,525 required contributed funds. 
21. International Boundary and Water Commission 
funds. 
22. Excludes $179,148 other contributed funds. 
33-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
23. Includes $6,000 Code 710 funds since FY 
1977. Excludes $17,006 other contributed funds. 
24. Excludes $2,324,206 required contributed 
funds. 
TABLE 33-G DEAUTHORI 
25. Excludes $8,718 required contributed funds 
and $53,470 other contributed funds. 
26. Excludes $74,718 required contributed funds. 
[ZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Hodges Dam, San Dieguito 
River Basin, CA 
Las Vegas Wash tributaries, 
Colorado River Basin, NV 
Santa Ana River Basin 
(and Orange County), CA: 
Aliso Creek Dam 
San Juan Dam 
1958 
1964 
1950 
Trabuco Dam 
Villa Park Dam 
Sierra Madre Wash channel, 
Los Angeles County drainage 
area, CA 
University Wash and Spring 
Brook, Riverside, CA 
1986 
1975 
1978 
Sec. 12, Public 
Law 93-251 
1977 
Sec. 12, Public 
Law 93-251 
1986 
Sec. 1002, Public 
Law 99-662 
1986 
Sec. 1002, Public 
Law 99-662 
1986 
Sec. 1002, Public 
Law 99-662 
1978 
Sec. 12, Public 
Law 93-251 
1986 
Sec. 1002, Public 
Law 99-662 
1986 
Sec. 1002, Public 
Law 99-662 
33-22 
TABLE 33-E (Cont'd) 
$295,191 
67,361 
213,313 
-

LOS ANGELES, CA, DISTRICT 
TABLE 33-H RECONNAISSANCE AND CONDITION SURVEYS 
(See Section 7 of Text) 
Project Date 
Dana Point Harbor, CA October 1988 
Morro Bay Harbor, CA September 1989 
Newport Bay Harbor, CA October 1988 
Port Hueneme, CA June 1989 
TABLE 33-I INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 18 of Text) 
Project Date 
Alamo Lake, Bill Williams River, AZ 
Banning levee-San Gorgonio River, Whitewater River Basin, CA 
Brea Dam, Santa Ana River Basin (and Orange County), CA 
Carbon Canyon Dam and channel, Santa Ana River Basin 
(and Orange County), CA 
Chino Canyon improvements, Palm Springs, Whitewater River Basin, CA 
City Creek levee, San Bernardino County, CA 
Devil, East Twin, and Warm Creeks channel improvements and Lytle 
Creek levee, Santa Ana River Basin, CA 
Fullerton Dam, Santa Ana River Basin (and Orange County), CA 
Hansen Dam, Los Angeles County drainage area, CA 
Holbrook levee, Little Colorado River, AZ 
Indian Bend Wash, Gila River Basin, AZ 
Lopez Dam, Los Angeles County drainage area, CA 
Los Angeles County drainage area channels, CA 
Lytle and Cajon Creeks channel improvements, Santa Ana 
River Basin (and Orange County), CA 
Lytle and Warm Creeks, Santa Ana River Basin, CA 
Mathews Canyon Dam, Colorado River Basin, NV 
Mill Creek levees, Santa Ana River Basin, CA 
Needles, San Bernardino County, CA 
Oro Grande Wash channel improvements, Mojave River Basin, CA 
Painted Rock Dam (Gila River), Gila River Basin, AZ 
Pine Canyon Dam, Colorado River Basin, NV 
Prado Dam, Santa Ana River Basin (and Orange County), CA 
Quail Wash levee, Joshua Tree, San Bernardino County, CA 
Riverside levees, Santa Ana River Basin, CA 
January 
May 
April 
April 
May 
May 
1989 
1989 
1989 
1989 
1989 
1989 
May 1989 
April 1989 
June 1989 
January 1989 
January 1989 
November 1988 
November 1988, 
June and July 1989 
May 
May 
June 
May 
January 
May 
January 
June 
May 
May 
May 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
33-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 89 
TABLE 33-I (Cont'd) INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 18 of Text) 
Project 
Rose Creek channel improvements, San Diego, CA 
San Antonio and Chino Creeks channel, Santa Ana River Basin 
(and Orange County), CA 
San Antonio Dam, Santa Ana River Basin (and Orange County), CA 
San Diego River channel and levees, San Diego River Basin, CA 
San Jacinto River levee and Bautista Creek channel, Santa Ana 
River Basin, CA 
Santa Fe Dam, Los Angeles County drainage area, CA 
Santa Rosa Wash (Tat Momolikot Dam and Lake St. Clair), AZ 
Sepulveda Dam, Los Angeles County drainage area, CA 
Tahchevah Creek detention basin and channel improvements, 
Whitewater River Basin, CA 
Tucson diversion channel, Gila River Basin, AZ 
Whitlow Ranch Dam, Queen Creek, Gila River Basin, AZ 
Winslow (tributaries of Little Colorado River), Little Colorado 
River Basin, AZ (part) 
June 1989 
May 
May 
June 
May 
June 
February 
June 
May 
February 
January 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
1989 
January 1989 
TABLE 33-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to 
Section 205, Public Law 80-858, 
As Amended (Preauthorization) 
(See Section 20 of Text) 
Project Fiscal Year Costs 
Lake Elsinore, Riverside County, CA $280,412 
Rialto Channel, Rialto, CA 26,750 
Santa Clara River, Fillmore, CA 2,112 
Tanque Verde Creek, Tucson, AZ 80,468 
33-24 
Date

SAN FRANCISCO, CA, DISTRICT * 
This district comprises the Klamath River Basin in 
southern Oregon and portions of northern and western 
California consisting of drainage basins tributary to the 
Pacific Ocean from the Oregon-California State line on 
the north to Cape San Martin, CA, on the south, except 
for basins tributary to the San Francisco Bay system 
which lie east of the Benicia-Martinez Bridge. 
IMPROVEMENTS 
Navigation Page 
1. Oakland Harbor, CA ................ 34-1 
2. Richmond Harbor (Deepening), CA ...... 34-2 
3. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels) ..................... 34-2 
4. San Francisco Bay and Delta Model, CA. . . 34-3 
5. Reconnaissance and Condition Surveys .... 34-3 
6. Navigation Work under Special 
Authorization ....................... 34-3 
7. Beach Erosion Control Work under Special 
Authorization ...................... 34-3 
Flood Control 
8. Inspection of Completed Flood 
Control Projects .................... 34-4 
9. Flood Control Work under Special 
Authorization ................. ... . 34-4 
10. Surveys .......................... 34-4 
Navigation 
1. OAKLAND HARBOR, CA 
Location. Oakland Harbor is located in the City of 
Oakland, California, on the eastern shore of central San 
Francisco Bay immediately south of San 
Francisco-Oakland Bay Bridge. 
Existing project. Adopted by Acts of June 23, 
1874, June 25, 1910, September 22, 1922, January 21, 
1927, April 28, 1928, July 3, 1930, March 2, 1945 and 
October 23, 1962. The project was completed February 
1975, except for deepening the tidal canal to 35 feet 
from Fortman Basin to Park Street, and to 25 feet above 
Park Street which was deauthorized November 1977. 
Reconstruction of the Fruitvale Avenue Highway Bridge 
was completed in December 1973 and turned over to 
local interests for operation and maintenance. Project 
consists of entrance channel to Oakland Outer Harbor, 
35 feet deep from deep water in San Francisco Bay and 
800 feet wide across the shoal southeast of Yerba Buena 
Island, narrowing to 600 feet at Oakland Mole; thence, 
a channel and turning basin 35 feet deep and from 600 
to 950 feet wide in outer harbor to the Army Base. 
Project also provides entrance channel to Oakland 
Inner Harbor, 35 feet deep and 600 feet wide to west 
end of Government Island, with additional widening to 
General Investigations 
11. Collection and Study of Basic Data .... 
12. Preconstruction Engineering and Design . 
Tables 
Table 34-A 
Table 34-B 
Table 34-C 
Table 34-D 
Table 
Table 
Table 
Table 
34-E 
34-F 
34-G 
34-H 
Page 
. 34-4 
. . 34-4 
Cost and Financial 
Statement ................ 34-5 
Authorizing 
Legislation ................ 34-9 
Other Authorized 
Navigation Projects ........ 34-11 
Other Authorized Beach 
Erosion Control Projects ..... 34-11 
Not Applicable 
Not Applicable 
Deauthorized Projects ...... 34-12 
Inspection of Completed Flood 
Control Projects........... 34-12 
within 75 feet of the pierhead line in front of Grove and 
Market Street (formerly municipal) piers and along the 
south side of the channel from Harrison Street eastward 
to harbor line point 119 in Brooklyn Basin; a channel 35 
feet deep and 500 feet wide through Brooklyn Basin; for 
a triangular area 35 feet deep about 2,700 feet long and 
maximum width of 300 feet at western end of Brooklyn 
Basin; a channel along north side of Brooklyn Basin 
which is 35 feet deep and 300 feet wide for 1,300 feet, 
thence 25 feet deep and 300 feet wide for 3,700 feet to a 
turning basin at east end of Brooklyn Basin which is 35 
feet deep, 500 feet wide, and 1,200 feet long; a channel 
in the tidal canal 35 feet deep and 275 feet wide from 
Brooklyn Basin to Park Street, thence 18 feet deep to 
San Leandro Bay; a total channel length of 8-1/2 miles 
from San Francisco Bay to San Leandro Bay. Project 
also includes parallel rubblemound jetties at entrance to 
inner harbor, north jetty 9,500 feet long and south jetty 
12,000 feet long; three highway bridges across the tidal 
canal, two of which (at Park Street and High Street) 
have been replaced by local interests and the Fruitvale 
Avenue Bridge constructed by Federal Government has 
been transferred to Alameda County. The railroad 
bridge has been transferred to the County for operation 
and maintenance. The Federal Government will 
reimburse the County for the cost of operating and 
maintaining the railroad bridges. 
34-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
WRDA of 1986 authorized deepening the 4 mile 
Inner and 3.4 mile Outer Harbors channels to 42 feet 
deep and widening the entrance channel to 1,000 feet; 
relocation of the Outer Harbor turning basin 3,000 feet 
westward; and widening the turning basin to 1,800 feet 
and constructing a 1,200 foot turning basin in the Inner 
Harbor, 42 feet deep, at mile 3.7. Present estimated 
total cost for the authorized improvements is 
$72,580,000. The non-Federal cost is $25,500,000. 
Local cooperation. By letter dated June 2, 1987, the 
Port of Oakland has indicated its intent to sign the Local 
Cooperation Agreement satisfying the requirements of 
the Water Resources Development Act of 1986, PL 
99-662. The local sponsor must comply with the 
following requirements: (1) provide lands, easements, 
rights-of-way, and dredged material disposal areas; (2) 
pay 25 percent of the costs allocated to deep draft 
navigation during construction; and (3) pay additional 
10 percent plus interests of the costs allocated to deep 
draft navigation within a period of 30 years following 
completion of construction. 
Terminal facilities. The port occupies 19 miles on 
the mainland shore of San Francisco Bay. There are 
550 acres of marine terminal facilities, 28 deepwater 
berths and 25 container cranes, including 5 of the post 
Panamax type. On-dock covered storage space 
exceeds 600,000 square feet. Three major railroads, 
Santa Fe, Southern Pacific and Union Pacific serve the 
port. 
Operations during fiscal year. New Work. Sediment 
testing, ocean site baseline and intitial monitoring 
studies, preparation of SEIS draft and GDM draft. 
2. RICHMOND HARBOR 
(DEEPENING), CA 
Location. Richmond Harbor is located in central 
San Francisco Bay, in Contra Costa County in the City 
of Richmond. 
Existing project. The existing navigation channel 
extends from deep water in San Francisco Bay to the 
Port of Richmond. The channel is maintained at a depth 
of -45 feet MLLW (Southhampton Shoal Channel and 
Long Wharf Maneuvering Area), -35 feet MLLW 
(Entrance Channel, Potrero Reach Channel, Potrero 
Sharp Turn, Inner Harbor and about half of the Santa 
Fe Channel), and -30 feet MLLW (remainder of the 
Santa Fe Channel). The width of the navigation channel 
is 600 feet for most of its length to Point Richmond with 
two maneuvering areas: one in front of the Long Wharf 
and the other at Point Richmond. At Potrero Reach, the 
channel 500 foot width flares to about 600 feet at Point 
Potrero with a turn at the point, 1,150 feet wide and 35 
feet deep except for a depth of 30 feet at the southerly 
apex of the bend. Thence, the channel continues into 
the inner harbor at a width of 850 feet in a northerly 
direction to the entrance of the Santa Fe Channel. The 
Santa Fe Channel extends northwesterly at a width of 
200 feet into the upper basin terminus. A turning basin 
is provided at Point Richmond, and a rubble-mound 
training wall extending 10,000 feet westerly from 
Brooks Island is also provided in the Potrero Reach. For 
details, see page 1977 of Annual Report for 1915 and 
page 1646 of Annual Report for 1938. 
Proposed improvements consists of a two-phased 
construction plan extending four and a half miles 
through the Santa Fe Channel. Phase I would deepen 
the existing 35-foot channel to -38 feet for bulk 
carriers, and provide a turning basin of 1,200 feet 
diameter near Point Potrero. Approximately 1,500,000 
cubic yards of sediment are to be dredged and 
transported to an upland and/or aquatic disposal site. In 
addition, 2,600 cubic yards of rock are to be excavated 
and disposed of at the Port-owned land disposal site. 
The estimated cost of Phase I is $16,050,000 of which 
$12,550,000 is Federal cost (includes $50,000 Coast 
Guard costs) and $3,500,000 is non-Federal cost. 
Phase II has been deferred and is reclassified to the 
inactive category. 
The existing project was authorized on October 27, 
1965. Previous projects were authorized by Acts 
adopted in 1917, 1930, 1935, 1938, 1945 and 1954. 
The proposed improvements are authorized by the 
Water Resources Development Act of 1986, PL 
99-662. 
Local cooperation. In accordance with the cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, the local sponsor 
must comply with the following requirements: (1) pay 10 
percent of the costs to 20 feet below mean lower low 
water and 25 percent of costs between 20 and 45 feet 
below mean lower low water and (2) reimburse an 
additional 10 percent of the costs of the general 
navigation feature of the project within a period of 30 
years following completion of construction; and (3) 
provide all lands, easements, rights-of-way, relocation 
and dredged material disposal (LERRD) areas 
necessary for the projects. The value of LERRD can be 
credited toward the payment required under item (2) 
above. The agreement is scheduled to be executed in 
September 1994. 
Terminal activities. The Port of Richmond encompasses 
nine privately-owned terminals and seven terminals 
owned by the Port. 
Operations during fiscal year. New Work. 
Continued preconstruction planning and engineering. 
3. SAN FRANCISCO BAY TO STOCKTON, 
CA (JOHN F. BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. John F. Baldwin Ship Channel. 
Navigation channels extending from entrance to San 
Francisco Bay to Suisun Bay near Martinez through San 
Francisco, Marin, Contra Costa, and Solano Counties. 
(See National Ocean Service Charts 18649, 18654 and 
18656 for respective areas.) 
34-2

SAN FRANCISCO, CA, DISTRICT 
Existing project. Project provides for modification 
of the existing San Francisco Harbor, Richmond 
Harbor, San Pablo Bay and Suisun Bay Channels to the 
vicinity of Martinez to provide depths of 55 feet for San 
Francisco Bar Channel, 45 feet (currently 35 feet) for 
main internal bay channels upstream to the vicinity of 
Martinez; enlargement and deepening to 45 feet 
(currently 35 feet) of maneuvering areas adjacent to 
major petroleum refinery terminals along the channel 
route. San Francisco Harbor Main Channel was 
completed in February 1974. The South Hampton 
Shoal Channel and the Richmond Long Wharf 
manevering area was completed in December 1986. For 
the approved cost estimate (1989) of Federal cost 
(Corps), see Sacramento District Annual Report. 
Existing project was adopted by 1965 River and Harbor 
Act (H. Doc. 208, 89th Cong., 1st sess., contains latest 
published map). 
Local cooperation. See Sacramento District Annual 
Report. The local sponsor, Contra Costa County, 
supports the project. 
Terminal facilities. See Port Series No. 30, revised 
1983, No. 31, revised 1982, and No. 32, revised 1986, 
titled respectively: "The Ports of San Francisco, 
Redwood City, and Humboldt Bay, Calif."; "The Ports 
of Oakland, Alameda, Richmond, and the Ports on 
Carquinez Strait, Calif."; and "The Ports of 
Sacramento, Stockton, Pittsburg, and Antioch, Calif." 
Facilities are considered adequate for existing 
commerce and will be adequate for future commerce 
upon completion of new terminal facilities. 
Operations during fiscal year. New Work: 
Continued planning engineering and design activities. 
4. SAN FRANCISCO BAY AND DELTA 
MODEL, CA 
Location. The model, including a regional visitor 
center, is located in Sausalito, CA, adjacent to San 
Francisco Bay about two miles north of the Golden Gate 
Bridge. 
Existing project. The San Francisco Bay/Delta 
Model, which covers 17 miles of the Pacific Ocean beyond 
the Golden Gate, all of San Francisco Bay proper, 
San Pablo Bay, Suisun Bay, and all of the Sacramento- 
San Joaquin Delta east of Suisun Bay to the cities of 
Sacramento on the northeast and Stockton and Tracy 
on the south, was constructed in a rehabilitated warehouse 
at Sausalito, CA, as a part of the San Francisco 
Bay and Tributaries, CA, Study authorized by the River 
and Harbor Act of May 17, 1950 (PL 81- 516, Section 
110). The model was authorized as an operation and 
maintenance project in the Water Resources Development 
Act of 1974 (PL 93-251, Section 8). The model 
successfully reproduces to the proper scale the rise and 
fall of the tide, flow and currents of water, salinity intrusion, 
and trends in disposition of sediments. It is a useful 
tool to examine forces existing in the bay and estuarine 
system and to predict results of proposed changes. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Operation and maintenance of the model continues. 
Extensive exhibit upgrade for the Visitor Center and 
development of Cooperative Association completed 
September 30, 1989. 
Historical summary. Original model construction 
was initiated 1956 and completed 1957. The addition of 
the Sacramento-San Joaquin Delta to the original 
model was initiated 1966 and completed 1969. The 
central exhibits were completed in December 1981. 
Continued testing of proposals affecting the environmental 
quality of the region including, but not limited 
to: salinity intrusion, dispersion of pollutants, water 
quality, improvements for navigation, dredging, bay fill, 
physical structures, other shoreline changes. Total cost 
of regional visitor exhibits and model as of September 
30, 1989, was $16,643,770, of which $6,410,630 was 
for the regional visitor center, $1,288,219 for exhibits, 
and $8,944,921 for maintenance. 
5. RECONNAISSANCE AND CONDITION 
SURVEYS 
Reconnaissance and condition surveys of channels to 
be dredged in years other than FY 89 and jetty structures 
were conducted on the following projects: Bodega 
Bay; Crescent City Harbor; Fisherman's Wharf; Moss 
Landing; Noyo River and Harbor; Petaluma River; Redwood 
City Harbor; Richardson Bay Channel; San Bruno 
Shoal; San Francisco Harbor; San Leandro Marina; 
San Pablo-Mare Island Straits; San Rafael Creek; Suisun 
Bay Channel; and Suisun Channel, all in California. 
Fiscal year costs were $341,479 of which $70,786 was 
for jetty condition surveys and $270,693 for project 
condition surveys. 
6. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
Fiscal year total costs for preauthorization studies 
were $75,305 of which $59,044 was for Crescent City 
Harbor, Del Norte County, CA; and $16,261 for Larkspur 
Ferry, Marin County, CA. 
7. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to 
Section 103, Public Law 87-874 (preauthorization). 
Fiscal year cost for preauthorization studies was 
$61,622 for Emeryville, Alameda County, CA. 
Mitigation of shore damages activities pursuant to 
Section 111, Public Law 90-483 (preauthorization). 
Fiscal year cost for preauthorization studies was 
$14,312 for Moss Landing Harbor, CA. 
34-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
8. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Section 3, Flood Control Act of June 22, 1936, as 
amended and supplemented, included a requirement 
that local interests maintain and operate completed 
flood control works in accordance with regulations 
prescribed by the Secretary of War. Inspections made 
throughout the year to determine effectiveness of 
operation and maintenance by local interests of 
completed local protection projects and works 
constructed under emergency and special authorities of 
Sections 205 and 208 of the 1948 Flood Control Act, 
Section 14 of the 1946 Flood Control Act, and Public 
Law 99, 84th Congress. Fiscal year cost was $82,371. 
Total cost to September 30, 1989 was $2,120,090. See 
Table 34-H for inspections made this fiscal year. 
9. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
(preauthorization). 
Fiscal year costs were $306,595 for preauthorization 
studies of which $15,367 for Felton Grove, Santa Cruz 
County, CA; $62,604 for Gold Gulch, Santa Cruz 
County, CA; $67,327 for Haciena Carmel, Carmel 
River, CA; $8,682 for Las Gallianas Creek, Marin 
County, CA; $10,946 for Pescadero and Butano 
Creeks, CA; $50,311 for Petaluma River, Sonoma 
County, CA; $14,030 for Rohner Creek, Fortuna, CA; 
$1,779 for San Felipe Lake, San Benito County, CA; 
$2,298 for Salt and Eel River, Humboldt County, CA; 
$70,537 for San Pedro Creek, Pacifica, CA; and $2,714 
for Soquel Creek, Santa Cruz County, CA. 
Emergency flood control activities-repair, flood 
fighting and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Fiscal year costs of $642,401 were incurred for 
disaster preparedness of emergency flood control 
activities. 
Emergency bank protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Congress). 
Fiscal year cost was $62,151 for San Pablo Creek, 
CA. 
General Investigations 
10. SURVEYS 
Fiscal year costs for surveys were $1,683,151, of 
which $312,337 was for navigation studies; $1,288,787 
for flood damage prevention; and $82,027 for inventory 
of dams. 
11. COLLECTION AND STUDY OF BASIC 
DATA 
Fiscal year total costs of $76,354 were incurred, of 
which $74,354 was for flood plain management service 
program and $2,000 for hydrologic studies. 
12. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
NOYO RIVER AND HARBOR, CA 
Noyo River rises in the Coast Range, flows westerly, 
and empties into Noyo Harbor. Noyo Harbor is a cove 
on the California Coast about 87 miles south of 
Humboldt Bay and 135 miles northwest of San 
Francisco. The 1962 Rivers and Harbors Act, modified 
by the 1976 Water Resources Development Act, 
authorized up to two breakwaters as necessary to 
provide protection. The 1976 WRDA authorized 
construction of additional channel improvements. 
Recommended plans of improvement for the breakwater 
and channel improvement were previously considered 
as a single project. Due to significant differences in 
the time required for planning and construction, each 
part is now reported separately. 
The plan of improvement for Noyo River and Harbor 
(Breakwater), CA provides for one breakwater west of 
the entrance channel in Noyo Harbor. Estimated 
preconstruction planning cost is $1,560,000. Total 
costs during the fiscal year were $427,507 with General 
Investigation funds. Planning is about 65 percent 
complete. Model studies, using a physical model to test 
alternative plan, were run intermittently from FY 84-FY 
86, with additional tests conducted in FY 88 and FY 89. 
The plan of improvement for Noyo River and Harbor 
(Channel Extension), CA provides for a 60-foot wide 
channel, 7 feet deep, for a distance of about 3,000 feet 
upstream from the end of the existing Federal project to 
the Dolphin Isle Marina. Estimated preconstruction 
planning cost is $580,000. Total costs during the fiscal 
year were $46,940 with General Investigation funds. 
34-4

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
Bodega Bay, CA New Work 
Approp. - - - - $1,226,765 1 2 40 
Cost - - - - 1,226,765 1 3 40 
Maint. 
Approp. $67,210 $39,374 $34,257 $34,358 1,190,514 4 40 
Cost 82,427 42,542 40,520 34,362 1,190,514 4 40 
Major rehab. 
Approp. - - - - 397,779 5 
Cost - - - - 397,779 5 
Crescent City New Work 
Harbor, CA Approp. - - - - 9,454,972 6 36 
Cost 1,993 - - - 9,454,972 6 36 
Maint. 
Approp 5,110,486 777,000 1,606,614 1,213,875 22,085,227 7 36 
Cost 5,004,776 850,714 1,633,938 1,210,973 22,057,628 7 36 
Major rehab. 
Approp. - - - - 525,000 8 
Cost - - - - 525,000 8 
Fisherman's Wharf New Work 
Areas, San Francisco Approp. 5,265,000 -116,000 - - 9,199,000 41 48 50 
Harbor, CA Cost 7,151,353 28,014 -763 2,057 9,199,000 41 49 50 
Maint. 
Approp. - - - 7,894 7,894 51 
Cost - - - 7,894 7,894 51 
Halfmoon Bay, CA New Work 
Approp. - - - - 6,697,396 43 44 
Cost - - - - 6,697,396 43 44 
Maint. 
Approp. 10,000 -3,700 12,827 - 2,097,194 44 45 
Cost 36,818 -1,244 12,827 - 2,097,194 44 45 
Humboldt Harbor New Work 
and Bay, CA Approp. - - - - 9,847,299 9 40 
Cost - - - - 9,847,299 9 40 
Maint. 
Approp. 4,236,000 2,369,000 2,628,700 853,000 59,784,641 10 40 
Cost 4,414,387 2,342,236 2,680,296 814,563 59,746,321 10 40 
Moss Landing New Work 
Harbor, CA Approp. - - 15,000 - 353,215 11 40 
Cost - - - 14,312 352,527 11 40 
Maint. 
Approp. 36,570 465,000 15,000 59,018 4,505,802 12 40 
Cost 52,051 467,211 21,258 65,968 4,505,802 12 40 
Napa River, CA New Work 
Approp. - - - - 1,021,274 13 40 
Cost - - - - 1,021,274 13 40 
Maint. 
Approp. 26,583 6,412 724,000 1,321,300 3,891,932 13 14 40 
Cost 26,583 6,412 722,384 1,291,094 3,860,110 13 14 40 
Noyo River and New Work 
Harbor, CA Approp. - - 580,000 141,000 2,242,482 15 16 40 
Cost 12,423 829 232,814 474,448 2,228,744 15 17 40 
Maint. 
Approp. 598,000 422,000 363,000 53,875 7,092,529 18 19 40 
Cost 534,352 445,886 387,248 65,482 7,082,210 18 19 40 
Minor rehab. 
Approp. - - - - 222,810 20 40 
Cost - - - - 222,810 20 40 
34-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
1. Oakland Harbor, 
CA 
Petaluma River, CA l 
Redwood City l 
Harbor, CA 
2. Richmond Harbor, 
CA 
3. San Francisco Bay 
to Stockton, CA 
(John F. Baldwin 
and Stockton Ship 
Channels) 
4. San Francisco Bay 
and Delta Model, 
CA 
San Francisco 
Harbor, CA 
San Francisco 
Harbor and Bay, CA 
(Removal of Drift) 
San Leandro 
Marina, CA 
San Pablo Bay 
and Mare Island 
Strait, CA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
535,700 915,000 
315,449 984,397 
1,075,000 2,620,200 
1,060,589 2,582,782 
3,400,000 
2,573,759 
1,917,900 
1,913,913 
1,976,000 
2,836,782 
2,009,000 
2,053,312 
16,778,684 21 40 
16,649,384 21 40 
35,264,346 22 40 
35,239,117 22 40 
297,146 23 40 
297,146 23 40 
-168,185 755,000 1,129,000 736,454 10,434,107 24 40 
-115,226 729,877 1,032,148 857,991 10,431,970 24 40 
S- - - 1,672,722 25 40 
S- - - 1,672,722 25 40 
14,674 59,010 77,260 448,576 7,925,474 26 40 
14,674 59,010 77,260 444,208 7,921,106 26 40 
848,300 561,000 779,532 437,000 5,627,527 27 28 
760,681 662,879 237,782 975,507 5,618,521 27 28 
1,074,000 1,811,300 610,300 2,589,440 21,583,382 29 40 
1,097,818 1,803,232 593,290 2,596,465 21,554,678 29 40 
- - - - 164,689 
- - - - 164,689 
5,166,000 1,937,000 1,600,000 1,186,000 29,011,200 
5,877,031 2,216,315 1,157,869 1,759,997 28,928,467 
1,100,000 
1,067,138 
980,000 1,050,000 1,880,000 16,792,700 
1,077,118 1,043,711 1,820,403 16,643,772 
- - - 2,689,356 28 30 40 
- - - 2,689,356 28 30 40 
1,566,340 1,593,036 2,615,833 1,282,785 27,977,515 31 40 
1,726,548 1,595,213 2,432,154 1,438,119 27,930,774 31 40 
930,000 1,305,000 1,570,000 1,317,000 25,168,182 40 
1,047,460 1,109,605 1,698,448 1,426,004 25,069,771 40 
44,171 
66,284 
38,337 34,105 815,663 2,134,008 32 
38,337 34,105 815,127 2,133,472 32 
- - - 1,369,372 28 33 40 
- - - 1,369,372 28 33 40 
34-6

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
Maint. 
Approp. 1,939,000 1,898,935 891,543 994,034 36,092,213 34 40 
Cost 1,978,259 1,848,904 806,132 1,120,892 36,085,640 34 40 
San Rafael, CA New Work 
Approp. - - - - 32,359 40 47 
Cost - - - - 32,359 40 47 
Maint. 
Approp. 970,994 626,591 202,007 - 3,816,962 40 46 
Cost 932,781 629,727 231,575 4,026 3,815,479 40 46 
Santa Cruz New Work 
Harbor, CA Approp. 2,134,000 - 20,468 - 4,126,808 51 
(Federal Funds) Cost 1,960,377 198,922 19,715 755 4,126,808 52 
(Contrib. Funds) New Work 
Contrib. - - - - 160,000 35 
Cost - - - - 160,000 35 
Maint. 
Approp. 994,500 64,000 62,000 - 9,600,660 40 
Cost 1,035,571 59,497 67,328 8,808 9,600,660 40 
Suisun Bay New Work 
Channel, CA Approp. - - - - - 36 
Cost - - - - - 36 
Maint. 
Approp. 1,797 174,000 296,700 250,717 3,483,277 37 40 
Cost 8,568 160,402 309,816 253,884 3,483,076 37 40 
Suisun Channel, CA New Work 
Approp. - - - - 217,677 38 
Cost - - - - 217,677 38 
Maint. 
Approp. 51,594 92,312 95,498 88,765 1,679,907 39 
Cost 51,594 92,312 95,498 88,765 1,679,907 39 
1. Include $641,800 for jetties, bulkheads, main 
Bodega Bay Channel and turning basin completed in 
1943. 
2. Includes $585,000 for Preconstruction Planning 
($456,000 Construction, General funds and 
$129,000 General Investigation funds). 
3. Includes $584,563 Preconstruction Planning 
costs ($455,563 Construction General costs and 
$129,000 General Investigation costs). 
4. Includes $255,964 for reconnaissance and 
condition surveys, FY 1956-1989. 
5. Excludes contribution funds of $2,000. 
6. Excludes contributed funds of $271,116 and 
$2,138 surplus material from Corps military activities. 
7. Excludes contributed funds of $44,340. 
Includes $80,284 for reconnaissance and condition 
surveys, FY 1956-1989. 
8. Excludes $2,000 contributed funds in lieu of 
royalty-free rock. 
9. Includes $2,261,371 for previous project. 
Excludes $95,000 contributed funds for existing 
project. 
10. Includes $98,206 for previous project and 
$1,710 for reconnaissance and condition surveys, FY 
1956-1989. 
11. Excludes $5,337 previous project costs. 
12. Excludes $8,539 surplus material from Corps' 
military activities. Includes $126,283 for reconnaissance 
and condition surveys, FY 1956-1989. Excludes 
contributed funds of $180,200. 
13. Excludes previous project costs. Excludes 
$492,788 contributed funds. 
14. Includes $274,508 for reconnaissance and 
condition surveys, FY 1956-1989. 
15. Includes $11,985 for previous project. 
Excludes $7,180 contributed funds for previous project. 
16. Includes $1,944,000 for Preconstruction Planning 
($1,364,000 for Breakwater of which $500,000 
allocated under Construction, General and $864,000 
under General Investigations); ($580,000 for Channel 
Extension of which $165,000 allocated under Construction, 
General and $415,000 under General Investigations). 
17. Includes $1,930,262 Preconstruction cost 
($1,350,262 for Breakwater of which $500,000 was 
under Construction, General and $850,262 under 
General Investigations); ($580,000 for Channel Extension 
of which $165,000 was under Construction, 
General and $415,000 under General Investigations). 
18. Includes $32,097 for previous project and 
$19,311 for reconnaissance and condition surveys, FY 
1956-1989. Excludes contributed funds of $820 for 
previous project. 
19. Excludes contributed funds of $4,000 in lieu of 
providing dike disposal areas on existing project. 
20. Excludes contributed funds of $1,700. 
34-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
21. Includes $2,899,232 for previous projects. 
Excludes $397,266 contributed funds on existing project.
22. Includes $684,028 for previous projects and 
$774 for reconnaissance and condition surveys, FY 
1956-1989. 
23. Includes $212,083 for previous project. Excludes 
contributed funds of $15,559 for previous project. 
Excludes $30,000 contributed funds. 
24. Includes $314,692 for previous project and 
$151,586 for reconnaissance and condition surveys, FY 
1956-1989. Excludes contributed funds of $192,424. 
25. Includes previous project costs $31,443. Excludes 
$119,572 contributed funds for existing project. 
26. Includes $277,214 for reconnaissance and 
condition surveys, FY 1956-1989. 
27. Excludes contributed funds of $524,778. Includes 
$105,000 Public Works Administration funds. 
28. Excludes modification authorized October 27, 
1965, under project "San Francisco Bay to Stockton, 
CA (John F. Baldwin and Stockton Ship Channels)." 
29. Excludes $34,800 contributed funds. Includes 
$3,364 for reconnaissance and condition surveys, FY 
1956-1989. 
30. Includes $1,030,399 for previous projects. Excludes 
$134,591 contributed funds for existing project. 
Includes $193,000 Public Works Administration funds. 
31. Includes $475,321 for previous projects and 
$107,313 for reconnaissance and condition surveys, FY 
1956-1989. 
32. Authorized by FC Act of 1965 (Sec. 201); 
Maintenance R&H Act of 1970 (Sec. 103). Includes 
$179,208 for reconnaissance and condition surveys FY 
1979-1989. See FY 1977 Annual Report for last full 
report. Excludes contributed funds of $859,947. 
33. Includes $1,086,703 for previous projects. 
34. Includes $1,359,380 for previous projects and 
$32,894 for reconnaissance and condition surveys, FY 
1956-1989. 
35. Excludes $810,046 contributed funds. 
36. See FY 1984 Annual Report for last full report. 
37. Project maintenance responsibility to Point 
Edith was transferred to San Francisco District January 
1, 1974. Excludes Sacramento District's portion. 
Includes $17,327 for reconnaissance and project condition 
surveys, FY 1976-1989. 
38. Project maintenance assigned to San Francisco 
District from Sacramento District January 1, 1974. See 
Sacramento District 1972 Annual Report for full report. 
39. Includes $372,398 for reconnaissance and 
condition surveys, FY 1978-1989. 
40. See FY 1981 Annual Report for last full report. 
41. Excludes Contributed Funds of $709,624. 
42. See Sacramento District FY 1985 Annual Report 
for full report. 
43. Excludes $100,000 contributed funds and 
$105,000 contributed in lieu of royalty-free rock. 
44. See FY 1979 Annual Report for last full report. 
45. Includes $30,394 for reconnaissance and condition 
surveys, FY 1970-1989. 
46. Includes $162,015 for reconnaissance and 
condition surveys, FY 1970-1989. 
47. Excludes $41,094 contributed funds. 
48. Includes $9,199,000 funds of which 
$8,499,000 was under Construction, General and 
$700,000 under General Investigations. Excludes Contributed 
Funds of $742,360. 
49. Includes $9,199,000 costs of which 
$8,499,000 was under Construction, General and 
$700,000 under General Investigations. Excludes Contributed 
Funds of $709,624. 
50. See FY 1987 Annual Report for last full report. 
51. Includes $7,894 for reconnaissance and condition 
surveys, FY 1989. 
52. See FY 1988 Annual Report for last full report. 
34-8

TABLE 34-B 
SAN FRANCISCO, CA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 23, 1874 
June 25, 1910 
Sep. 22, 1922 
Jan. 21, 1927 2 
Apr. 28, 1928 
July 3, 1930 
Mar. 2, 1945 
Mar. 2, 1945 
Oct. 23, 1962 3 
Nov. 17, 1986 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 4 
1. OAKLAND HARBOR, CA 
Jetties. 
North channel in Brooklyn Basin, 25 feet deep, 
and tidal canal to 18 feet. 
Channel across shoal southeast of Yerba Buena 
Island and thence to Webster St.; South 
channel in Brooklyn Basin; Turning Basin at 
east end of Brooklyn Basin; and channel in 
Tidal Canal from Brooklyn Basin to Park St., 
30 feet deep. 
Channel from Webster St. to Brooklyn Basin, 
maintain area to within 75 feet of pierhead 
line south of channel from Harrison St. to 
Harbor Line Point 119 in Brooklyn Basin; 
dredge a triangular strip about 2,700 feet long 
and maximum width of 300 feet at western 
end of Brooklyn Basin, 30 feet deep. 
Local cooperation requirements modified to 
provide alteration or replacement of bridges by 
local interests shall apply only to that feature of 
project covering deepening tidal canal to 25 feet. 
Drawbridges across Tidal Canal were required by 
1882 Decree of Court in condemnation proceedings 
whereby title was obtained to rightof-
way for tidal canal. 
Entrance channel to outer harbor, 800 to 600 
feet wide. 
Eliminated requirement that local interests contribute 
10 cents per cubic yard toward deepening 
tidal canal. 
Maintenance of 35-foot depth in channel to outer 
harbor and in outer harbor channel and turning 
basin. 
Deepen inner harbor 35-foot channels and lower 
1,300 feet of north channel in Brooklyn Basin 
to 35 feet. 
Deepen Inner and Outer Harbor channels to 42 
feet. Widen entrance channel to 1,000 feet; 
relocate Outer Harbor turning basin 3,000 feet 
westward and widen turning basin to 1800 feet. 
Construct 1,200 feet turning basin in Inner 
Harbor. 
RICHMOND HARBOR, CA 
Channel 24 feet deep and 600 feet wide from San 
Francisco Bay to Ellis Slough (Santa Fe Channel); 
a turning basin at Point Potrero; a training wall. 
A 30-foot channel with lessened widths; a turning 
basin at head of navigation. 
Increase project widths in inner harbor, maintenance 
of Santa Fe channel to 30 feet; approach areas 
in outer harbor to 32 feet. 
34-9 
Annual Report, Part II, 
1874, p. 378. 
H. Doc. 647, 61st Cong., 
2d sess. 
H. Doc. 144, 67th Cong., 
2d sess. 
H. Doc. 407, 69th Cong., 
1st sess. 1 
Public Res. 28, 
70th Cong. 
Rivers and Habors 
Committee Doc. 43, 
71st Cong., 2d sess. 
H. Doc. 466, 77d Cong., 
1st sess. 
Report on File in Office, 
Chief of Engineers 
H. Doc. 353, 87th Cong., 
2d sess. 1 
1986 WRDA, Public 
Law 99-662 
H. Doc. 515, 63rd Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 16, 
70th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 7, 
73d Cong., 1st sess., 
and 10, 74th Cong., 
1st sess. 
2.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 34-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 20, 1938 Widen channel at Point Potrero and north thereof; H. Doc 598, 75th Cong., 
enlarge and maintain to 30-foot depth turning 3d sess. 
basin at Terminal No. 1. 
Mar. 2, 1945 Channel 20 feet deep, 150 feet wide, in San Pablo H. Doc. 715, 76th Cong., 
Bay north of Point San Pablo. 3d sess. 
Sep. 3, 1954 Channel 35 feet deep and 600 feet wide adjacent H. Doc. 395, 83rd Cong., 
to Southampton Shoal; enlarge and deepen to 35 2d sess. 1 
feet approach area to Richmond Long Wharf; 
widen and deepen inner harbor and entrance 
channels; deepen turning basin at Point Richmond 
and southerly 2,000 feet of Santa Fe Channel. 
Eliminate restriction that widening north of 
Point Potrero will not be undertaken until local 
interests furnish assurances industries will avail 
themselves of improved navigation facilities. 
and reclamation of Reservation Point. 
Oct. 27, 1965 West Richmond channel 45 feet deep, 600 feet H. Doc. 208, 89th Cong., 
wide; enlarge and deepen to 45 feet maneuvering 1st sess. 1 
area at Richmond Long Wharf (Sacramento Dist. 
"San Francisco Bay to Stockton, Calif. (John 
F. Baldwin and Stockon Ship Channels)"). 
Nov. 17, 1986 Deepen channel to 38 feet between Richmond 1986 WRDA, Public Law 
Long Wharf and Santa Fe Channel. Construct 99-662 
1,200 feet turning basin. 
1. Contains latest published map. 
2. Included deepening of tidal canal above Park 
Street Bridge to 25 feet, which was deauthorized 
November 6, 1977. 
3. Reconstruction of Fruitvale Avenue Highway 
Bridge (S. Doc. 75, 87th Cong., 2d sess.) which was 
deauthorized November 6, 1977. 
4. Included in part in Public Works Administration 
Program, September 6, 1933. 
34-10

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Berkeley Harbor, CA 1 Completed 1966 $155,550 2 $6,120 s 
Berkeley Marina, CA 1 Completed 1979 505,201 3 
Lower San Francisco Bay, CA Inactive 1935 - - 
Monterey Harbor, CA Completed 1971 1,108,182 4 85,880 5 
San Francisco Harbor (Islais 
Creek), CA 1 Completed 1976 848,227 7 
San Francisco Marina (Gas 
House Cove), CA Completed 1974 180,472 - 
San Leandro Marina (Breakwater), 
CA 1 Completed 1976 210,390 8 
1. Authorized by Chief of Engineers (Sec. 107, 5. Includes $8,041 for reconnaissance and 
Public Law 86-645). condition survey for FY 1956-1989. 
2. Excludes $155,551 contributed funds. 6. Includes preauthorization costs $26,855 and 
3. Excludes $378,989 contributed funds. excludes contributed funds $153,618. 
4. Includes $207,800 Public Works Administra- 7. Includes $94,550 preauthorization costs. 
tion funds and breakwater modifications (1960 Act) 8. Includes $72,000 preauthorization costs and 
placed inactive 1974. The barrier groin and sandtrap excludes contributed funds $138,189. 
feature of the project was deauthorized November 17, 9. Includes $6,120 for jetty condition surveys for 
1986, by WRDA of 1986. FY 1987-1989. 
TABLE 34-D OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Humboldt Bay, CA Inactive 1958 $2,000 
Santa Cruz County, CA Inactive 1966 245,639 
34-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 34-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Knights Valley Lake, R.R. 
Basin, CA 1974 Aug. 5, 1977 - 
Oakland Harbor, CA (Deepen 
Tidal Canal) 1981 Nov. 6, 1977 - 
Oakland Harbor, CA (Fruitvale 
Avenue Bridge) 1981 Nov. 6, 1977 - 
San Lorenzo Creek, CA 
(Upper Portion) 1962 Nov. 6, 1977 - 
San Pablo Bay and Mare 
Island Strait, CA (Approaches 
to Vallejo and South Vallejo) 1982 Nov. 6, 1977 - 
TABLE 34-H INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 8 of Text) 
Location Dates of Inspection 
Alameda Creek 
Butte Creek 
Canyon Creek 
Corte Madera Creek 
Coffee Creek 
Coyote Creek 
Denny Rock Creek 
Dry Creek 
East Weaver Creek 
lri iRiver 
Eel River at Sandy Prairie 
Fishhole Creek 
Klamath River 
Mad River 
Mad River at Blue Lake 
Mad River Slough 
Meiss Lake 
Pajaro River 
Pinole Creek 
Redwood Creek 
Rheem Creek 
Rodeo Creek 
Russian River 
San Leandro Creek 
San Lorenzo Creek 
San Lorenzo River 
Mar 1989 
Aug 1989 
Sep 1989 
Apr 1989 
Sep 1989 
Apr 1989 
Sep 1989 
Nov 1988 and Mar 1989 
July 1989 
Sep 1989 
July 1989 
Sep 1989 
July 1989 and Sep 1989 
Sep 1989 
July 1989 
Sep 1989 
Aug 1989 
Nov 1988 and Jun 1989 
May 1989 
July 1989 and Sep 1989 
May 1989 
May 1989 
July 1989 
Mar 1989 
Mar 1989 
May 1989 
34-12

TABLE 34-H (Cont'd) 
SAN FRANCISCO, CA, DISTRICT 
INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 8 of Text) 
Location Dates of Inspection 
San Pablo Creek Oct 1988 
Scott River Aug 1989 
Sprague River Sep 1989 
Upper Klamath Lake Sep 1989 
Uvas Creek May 1989 
Wildcat Creek May 1989 
34-13

SACRAMENTO, CA, DISTRICT * 
This district comprises basins of Suisun Bay and San 
Joaquin and Sacramento Rivers in California; Goose 
Lake in Oregon; basins of the Great Salt Lake and 
Sevier Lake in Utah; an intervening portion of Great 
Basin in northern Nevada, northern California, and 
southeastern Idaho; and the upper Colorado River 
basin, which is in southwestern Wyoming, eastern Utah, 
northeastern Arizona, and western Colorado, west of 
the Continental Divide. 
IMPROVEMENTS 
Navigation Page 
1. Sacramento River, CA ............... 35-2 
2. Sacramento River Deep Water 
Ship Channel, CA ................... 35-3 
3. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels) .................... 35-3 
4. San Joaquin River, CA ................ 35-4 
Flood Control 
5. Buchanan Dam-H.V. Eastman Lake, 
Chowchilla River, CA ................ 35-5 
6. Cache Creek Settling Basin, CA ......... 35-5 
7. Calaveras River and Littlejohn Creek and 
tributaries, including New Hogan Lake and 
Farmington Dam, CA ................ 35-6 
8. Corte Madera Creek, CA .............. 35-7 
9. Fairfield Vicinity Streams, CA .......... 35-7 
10. Hidden Dam-Hensley Lake, Fresno 
River, CA ......................... 35-8 
11. Isabella Lake, Kern River, CA .......... 35-9 
12. Kaweah and Tule Rivers, including 
Terminus Dam and Success Lake, CA . . . . 35-10 
13. Little Dell Lake, UT................. 35-11 
14. Lower San Joaquin River, CA .......... 35-11 
15. Martis Creek Lake, Martis Creek, 
NV and CA ....................... 35-12 
16. Merced County Streams ............. 35-12 
17. Merced County Stream Group, CA ...... 35-13 
18. Pajaro River, CA .................... 35-13 
19. Pine Flat Lake and Kings River, CA ..... 35-14 
20. Redbank and Fancher Creeks, CA ...... 35-15 
21. Russian River Basin, including Dry Creek 
(Warm Springs Lake) and Lake 
Mendocino (Coyote Valley Dam), CA... 35-16 
22. Sacramento River and tributaries, CA 
from Collinsville to Shasta Dam ......... 35-17 
23. Walnut Creek, CA ................. 35-18 
24. Wildcat and San Pablo Creeks, CA ...... 35-19 
25. Inspection of Completed Flood 
Control Projects ................... 35-20 
Flood Control (Cont'd) Page 
26. Flood Control Work under Special 
Authorization ..................... 35-20 
27. Scheduling Flood Control 
Reservoir Operations ................ 35-20 
Multiple-Purpose Projects Including Power 
28. New Melones Lake, CA.............. 35-21 
General Investigations 
29. Surveys ......................... 35-22 
30. Collection and Study of Basic Data ...... 35-22 
31. Research and Development ........... 35-22 
32. Preconstruction Engineering and Design ... 35-22 
Tables 
Table 35-A 
Table 35-B 
Table 35-C 
Table 35-D 
Table 35-E 
Table 35-F 
Table 35-G 
Table 35-H 
Table 35-I 
Table 35-J 
Table 35-K 
Table 35-L 
Page 
Cost and Financial 
Statement ............... 35-24 
Authorizing 
Legislation .............. 35-32 
Other Authorized 
Navigation Projects ........ 35-34 
Not Applicable 
Other Authorized Flood 
Control Projects........... 35-35 
Not Applicable 
Deauthorized Projects ...... 35-37 
Sacramento River, CA: 
Tidal and Flood Conditions 
Prevailing ............... 35-37 
San Joaquin River, CA: 
Total Cost of New Work 
for Project ............... 35-38 
San Joaquin River, CA: 
Project Units (1950 Modification) 
Reclassified and Excluded from 
Project Cost .............. 35-38 
Merced County Stream Group, 
CA, Maximum Inflow, Storage, 
and Outflow for Projects ...... 35-39 
Russian River Basin, CA: 
Estimated Cost for New Work . .35-39 
35-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
IMPROVEMENTS (Cont'd) 
Page Tables 
Russian River Basin, CA: 
Project Features and 
Estimated Costs ............ 35-40 
Sacramento River and 
Tributaries, CA, Collinsville 
to Shasta Dam: Project Units 
Units Reclassified and 
Excluded from Cost Estimate . . 35-40 
Table 35-0 
Table 35-P 
Page 
Sacramento River and 
Tributaries, CA, from Collinsville 
to Shasta Dam: Construction 
Accomplished and Contract 
Costs .................... 35-41 
Flood Control Work Under 
Special Authorization Flood 
Control Activities Pursuant 
to Section 205, Public Law 
80-858, as Amended 
(Preauthorization) ......... 35-42 
Navigation 
1. SACRAMENTO RIVER, CA 
Location. Rises in Trinity Mountains in north-central 
California, flows generally southerly about 374 miles 
and empties into Suisun Bay, an arm of San Francisco 
Bay, at Collinsville, CA. (See Geological Survey 
topographic map of Sacramento Valley, CA.) 
Previous projects. For details see page 1985 of 
Annual Report for 1915 and page 1708 of Annual 
Report fcr 1938. 
Existing project. For description of Sacramento 
Deep Water Ship Channel, see Annual Report for 1969. 
Total first cost for completed portion was $43,932,558 
($39,560,558 Federal (Corps), $300,000 (Coast 
Guard), and $4,072,000 non-Federal for lands and 
damages, including relocations) and excludes local 
interests cost $10,741,000 (June 1963) for 30-foot 
deep water ship channel and 13-foot deep connecting 
canal basic terminal facilities required under terms of 
project authorization. Project also provided for a 
shallow-draft channel 10 feet deep at mean lower low 
water 150 to 200 feet bottom width, from Suisun Bay to 
Sacramento, CA, 60 miles; a depth of 6 feet at low water 
between Sacramento and Colusa, 85 miles; a depth of 5 
feet at low water between Colusa and Chico Landing, 50 
miles; and such depths as practicable between Chico 
Landing and Red Bluff, 53 miles, a total distance of 248 
miles. However, shallow-draft channel feature Colusa 
to Red Bluff (including Colusa to Chico Landing, 50 
miles and Chico Landing to Red Bluff, 53 miles) was 
deauthorized by 1986 Water Resources Development 
Act on November 17, 1986 (Public Law 99-662). (See 
table 35-H on tidal and flood conditions prevailing.) 
Local cooperation. Fully complied with for deep 
water ship channel project. None required on shallowdraft 
feature. 
Terminal facilities. Piers, wharves, and docks at 
Port of Sacramento for shallow-draft navigation are 
open-pile structures with timber decks, some of which 
are designed to meet extreme high waters of flood 
stages. All main wharves at Sacramento have rail connections. 
Three of above facilities are owned by city of 
Sacramento and remainder by private interests; all are 
privately operated. For full description see "Port and 
Terminal Facilities at the Ports of Sacramento, Stockton, 
Pittsburg and Antioch, Calif., 1986." Deep water 
terminal facilities comprise wharves and piers, administration 
and storage buildings, and belt railroad facilities. 
Majority of these facilities are owned and operated 
by Sacramento-Yolo Port District; remainder are privately 
owned and operated. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. New work, Deep 
Water Ship Channel: None. Maintenance: Shallow 
Draft Channel: Maintenance and operation activities 
continued in Sacramento River, Sacramento upstream 
to Colusa. Deep Water Ship Channel: Maintenance and 
operation activities continued. 
Historical summary. Construction of 7-foot 
shallow-draft channel below Sacramento was initiated 
in September 1899 and completed in 1904. Modified 
10-foot shallow-draft channel up to Sacramento was 
initiated in FY 1928 and completed in 1931. 
Shallow-draft channel above Sacramento was begun in 
April 1946 but new work was discontinued when about 
48 percent complete. In February 1974, remaining 
work for shallow-draft portion of project, provision of a 
5-foot depth between Colusa and Chico Landing (50 
miles), was reclassified as "deferred." Channel is 
navigable all year; however, there is no regular 
navigation above Colusa, 145 miles above river mouth. 
On November 17, 1986, remaining shallow-draft 
feature, Colusa to Red Bluff (including Colusa to Chico 
Landing, 50 miles and Chico Landing to Red Bluff, 53 
miles) was deauthorized by 1986 Water Resources 
Development Act (Public Law 99-662). Construction 
of 30-foot deep water ship channel was initiated in July 
35-2 
Tables 
Table 35-M 
Table 35-N

SACRAMENTO, CA, DISTRICT 
1949; improvement dredging by continuing contracts 
resulted in provision of an operational facility for 
oceangoing vessels during June 1963. Bascule bridge 
was completed in April 1960, barge lock in August 
1961, barge canal in November 1961, and entire deep 
water ship channel in June 1970. 
2. SACRAMENTO RIVER DEEP WATER 
SHIP CHANNEL, CA 
Location. On the Sacramento River between Collinsville 
and the Port of Sacramento, a distance of about 
43 miles, in the counties of Sacramento, Contra Costa, 
Solano, and Yolo, CA. 
Existing project. Project provides for deepening to 
35 feet the Suisun Bay and Sacramento River Deep 
Water Ship Channels from New York Slough to the Port 
of Sacramento, and the Avon to New York Slough reach 
to 35 feet which will be accomplished under the San 
Francisco Bay to Stockton (John F. Baldwin and Stockton 
Ship Channels) project, and widening the channel 
as necessary. 
Current selected plan also provides for a water quality 
monitoring program, and establishment of wetland habitat 
and upland habitat to mitigate for losses of such 
habitat. 
Project estimate (October 1989) is $43,400,000 (includes 
an allowance for estimated inflation through the 
construction period) comprising Federal cost (Corps) of 
$21,400,000; Federal cost (Coast Guard) for navigation 
aids $300,000; and non-Federal cost of $21,700,000 
for lands and damages, relocations, and spoil retention 
dikes, including the cash contribution ($7, 130,000) that 
local interests must pay. Existing project was adopted by 
Supplemental Appropriations Act of 1985, August 15, 
1985 (Public Law 99-88), 99th Cong., 1st sess. and 
modified by 1986 Water Resources Development Act, 
November 17, 1986 (Public Law 99-662) 99th Cong., 
2d sess. 
Local cooperation. Local interests, through a public 
body legally authorized and financially capable, must 
give assurances they will furnish lands, easements, 
rights-of-way, and dredged material disposal areas; 
modify or relocate buildings, utilities, roads, and other 
facilities where necessary in the construction of the 
project; and provide retention dikes for dredged 
material disposal area; and pay 25 percent of the costs 
allocated to deep draft navigation during construction, 
presently estimated at $7,240,000. Local interests have 
agreed to make all required payments concurrently with 
project construction. A Local Cooperation Agreement 
(LCA) (sec. 221) was executed June 27, 1986. An LCA 
modification necessitated by the Water Resources 
Development Act of 1986 was executed December 6, 
1988. 
Terminal facilities. All main wharves at Sacramento 
have rail connections. Three of above facilities are 
owned by city of Sacramento and remainder by private 
interests; all are privately operated. For full description 
see "Port and Terminal Facilities at the Ports of 
Sacramento, Stockton, Pittsburg and Antioch, Calif., 
1986." Deep water terminal facilities comprise wharves 
and piers, administration and storage buildings, and belt 
railroad facilities. Majority of these facilities are owned 
and operated by Sacramento-Yolo Port District; 
remainder are privately owned and operated. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Engineering 
was continued. First construction contract was 
awarded in February 1989. Work was initiated at 
contract fiscal year cost of $1,090,000. 
Historical summary. General Design Memorandum 
was approved and Record of Decision was signed in May 
1987. Local Cooperation Agreement (LCA) modification 
was approved and was signed by Port of Sacramento 
on August 19, 1987. LCA modification was executed 
December 6, 1988. First construction contract was 
awarded February 2, 1989 and work was initiated. 
3. SAN FRANCISCO BAY TO STOCKTON, 
CA, (JOHN F. BALDWIN AND 
STOCKTON SHIP CHANNELS) 
Location. On navigation channels extending from 
entrance to San Francisco Bay to Port of Stockton 
through San Francisco, Marin, Contra Costa, Solano, 
Sacramento, and San Joaquin Counties. (See Coast and 
Geodetic Charts 5527 and 5532-5534 for respective 
areas.) 
Existing project. Project provides for modification 
of existing San Francisco Harbor, Richmond Harbor, 
San Pablo Bay and Mare Island Strait, Suisun Bay 
Channel, and San Joaquin River navigation projects to 
provide depths of 55 feet for San Francisco Bar Channel, 
45 feet for main internal bay channels upstream to 
vicinity of Avon, and 35 feet from Avon to Stockton; 
enlargement and deepening to 45 feet of maneuvering 
areas adjacent to major petroleum refinery terminals 
along channel route; widening Suisun Bay Channel; 
reclaiming shoreline marshes and inundated or low-lying 
areas by spoil deposit for public recreation and for 
industrial use; providing basic recreation facilities on 
some of the reclaimed areas for public use; and placing 
additional rock revetment on waterside of levees bordering 
channels. 
Project estimate (October 1989) is $124,900,000 
(includes an allowance for estimated inflation through 
the construction period) comprising Federal cost 
(Corps) of $123,800,000, including basic recreation 
facilities; Federal cost (Coast Guard) for navigation aids 
$1,100,000; and non-Federal cost of $29,200,000 for 
lands and damages, relocations, berthing areas, and 
spoil retention dikes, including the cash contribution 
($20,000) that local interests must make for land enhancement 
at time of construction. Local interests must 
also pay, contribute in kind, or repay with interest 
one-half of separable cost of project allocated to recreation. 
Existing project was adopted by 1965 River and 
35-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Harbor Act (H. Doc. 208, 89th Cong., 1st sess., contains 
latest published map). 
Local cooperation. Local interests, through a public 
body legally authorized and financially capable, must 
give assurances they will furnish lands, easements, and 
rights-of-way for construction and future maintenance 
of the project and for aids to navigation, including 
spoil-disposal areas designated by the Chief of Engineers; 
provide necessary spoil retention dikes, bulkheads, 
and embankments except as applicable to spoildisposal 
areas designated as public recreation areas; 
make utility modifications and relocations required for 
construction, including new bridges or bridge alterations 
(except for railroad bridges), and absorb any increased 
annual maintenance and operation costs resulting there 
from; provide and maintain all necessary berthing areas, 
at a depth commensurate with project depth, at all 
terminals and wharves to be served by the deepened 
channels; and in recognition of the local land enhancement 
benefits to result from landfill during dredging, 
contribute to the United States 4 cents per cubic yard of 
all spoil material placed during initial construction for 
modification of Suisun Bay Channel project on areas 
not developed for public use. Local interests must also 
give satisfactory assurances, before starting construction 
of the affected units, that they will maintain and operate 
the Federally provided recreation areas and facilities, 
continue to maintain to adequate standards the levees 
altered, set back or provided revetment protection, and 
hold the U.S. Government free from damages due to 
deposition of spoil and construction of new levees or 
reconstruction of existing levees. Local interests, represented 
by Board of Supervisors of Contra Costa County 
and Stockton Port District, must, at time of construction, 
contribute $20,000 in cash for land enhancement; 
pay, contribute in kind, or repay with interest one-half 
of separable cost of project allocated to recreation; and 
maintain and operate basic recreation facilities after 
construction and install additional basic facilities required 
as demands on area expand. No work shall be 
undertaken on a modification of Suisun Bay Channel 
project unit to deepen the channel to more than 35 feet 
between Avon and a proposed refinery or manufacturing 
plant, until local interests furnish formal assurances 
and definite plans for such installation within the Avon- 
Chipps Island reach of channel. Also, no work shall be 
undertaken on modification of San Joaquin River navigation 
project unit, regarding access channels in vicinity 
of Antioch, until local interests furnish formal assurances 
and definite plans for Port of Antioch. Formal 
assurances for deepening and otherwise improving the 
Stockton Deep Water Ship Channel from Pittsburg to 
Stockton were furnished by Stockton Port District April 
9, 1970. The Stockton Port District, in August 1980, 
formally provided their intent to sponsor the Avon to 
Pittsburg reach (Suisun Bay Channel) and recreational 
development on Roberts Island. The Port of Stockton, 
by letter of October 20, 1981, stated that they would 
furnish the necessary assurances for fish and wildlife 
mitigation and enhancement, and on April 13, 1982, 
provided formal updated assurances for the Avon to 
Stockton portion. A sec. 221 agreement satisfying all 
requirements of local cooperation for Southampton 
Shoal and Richmond Long Wharf maneuvering area 
was obtained from Contra Costa County Board of 
Supervisors and signed by District Engineer July 31, 
1984. On May 3, 1988, Board passed a resolution of 
continued support for construction in West Richmond, 
Pinole Shoal, Carquinez Strait, and Suisun Bay Channels. 
A Memorandum of Agreement between the 
Department of the Army, San Francisco District and 
Contra Costa County to sample berthing areas of project 
was executed September 12, 1989. 
Terminal facilities. See Port Series No. 30, revised 
1983, and 31, revised 1982, titled respectively: "The 
Ports of San Francisco, Redwood City, and Humboldt 
Bay, Calif." and "The Ports of Oakland, Alameda, 
Richmond, and Ports on Carquinez Strait, Calif."; and 
Port Series No. 32, revised 1986, "The Ports of Sacramento, 
Stockton, Pittsburg and Antioch, Calif." Facilities 
are considered adequate for existing commerce and 
will be adequate for future commerce upon completion 
of new terminal facilities. 
Operations and results during fiscal year. New 
work: Sacramento District: Engineering continued. 
Channel improvement-dredging of various reaches between 
McDonald Tract and Avon was continued by 
Contract No. 4 at fiscal year contract cost of $647,055. 
San Francisco District: planning activities continued including 
completion of an overwater sediment sampling 
contract and initiation of a vessel simulation navigation 
study. 
Historical summary. Construction of project was 
initiated in June 1971 and is about 37 percent complete. 
4. SAN JOAQUIN RIVER, CA 
Location. Rises in east central California and flows 
westerly and northwesterly about 340 miles to its confluence 
with Sacramento River at head of Suisun Bay, 48 
miles northeast of San Francisco. Deep water channel in 
San Joaquin River extends 41 miles from its mouth in 
Suisun Bay at Pittsburg to city of Stockton. Waterborne 
access to city provided by Stockton Channel, an artificial 
cut extending from river about 2 miles into city. 
(See Coast and Geodetic Survey Sheet 5527.) 
Existing project. For description of completed improvement, 
modifications, and authorizing acts, see Annual 
Report for 1967. (See table 35-I for total cost of 
new work for project completed in May 1960.) 
Projects units (1950 modification) reclassifed and 
excluded from project cost are set forth in table 35-J. 
Modification of existing project is included as one 
unit of San Francisco Bay to Stockton, CA, (John F. 
Baldwin and Stockton Ship Channels) project, authorized 
by 1965 River and Harbor Act (H. Dec. 209, 89th 
Cong., 1st sess.); this modification is reported in detail 
under Sacramento District, Improvement No. 3. 
35-4

SACRAMENTO, CA, DISTRICT 
Local cooperation. Fully complied with for completed 
portion of project; for details of required cash 
contributions on completed, inactive and deferred portions 
of project, see Existing project paragraph, Annual 
Report for 1967. 
Terminal facilities. For description of harbor facilities 
at Port of Stockton, CA, see Port Series 32, "The 
Ports of Sacramento, Stockton, Pittsburg and Antioch, 
Calif.," revised 1986. Downstream from Stockton, traffic 
is accommodated by bank landings and sheds except 
at Antioch and near Pittsburg, where there are wharves 
for shallow- and deep-draft vessels. Terminal transfer 
facilities at public ocean terminal of Port of Stockton are 
adequate for present and immediate future. 
Operations and results during fiscal year. Maintenance: 
Condition studies and miscellaneous inspections 
and reports were accomplished by hired labor. (Repair 
or restoration of wavewash protection is required by 
legislation authorized by Improvement No. 3.) 
Historical Summary. Active portion of existing 
project was completed in May 1960. Construction of 
project was initiated in December 1877. 
Flood Control 
5. BUCHANAN DAM-H.V. EASTMAN 
LAKE, CHOWCHILLA RIVER, CA 
Location. On Chowchilla River about 36 miles above 
its mouth and about 16 miles northeast of city of 
Chowchilla, CA. (See Geological Survey quadrangles 
for area.) 
Existing project. Provides for construction of a 
205-foot high rockfill dam to create a reservoir with 
gross storage capacity of 150,000 acre-feet for flood 
control, irrigation, recreation, and fish and wildlife. In 
conjunction with dam, project plan provides for about 
12 miles of downstream levee and channel construction 
on Ash Slough to accommodate a project design flow of 
5,000 cubic feet per second within slough and 7 miles of 
levee and channel improvement on Berenda Slough. 
Operation and maintenance of dam and reservoir is the 
responsibility of the Federal Government. Total first 
cost for existing project is $28,919,597, of which 
$27,369,597 is Federal cost, including $4,580,000 for 
basic recreation facilities, and $1,550,000 non-Federal 
costs for lands and damages, including relocations for 
downstream levee and channel improvements. Local 
interests have contracted with the Bureau of Reclamation 
for irrigation service. For future non-Federal 
reimbursement, see Local cooperation paragraph. 
Local interests have also, over a period of years, 
expended about $500,000 for construction of low levees 
and clearing downstream channels to provide some local 
flood protection in project area. This work is inadequate 
during major floods. Existing project was adopted by 
1962 Flood Control Act (S. Doc. 98, 87th Cong., 2d 
sess., contains latest published map). Lake formed by 
Buchanan Dam on Chowchilla River was designated 
"H.V. Eastman Lake" by Public Law 93-217. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and operation 
activities were continued. Dam safety assurance studies 
were continued at a fiscal year cost of $8,842. Runoff of 
Chowchilla River above Buchanan Dam was below 
normal for the year. Maximum storage of 19,400 acrefeet 
occurred May 16, 1989. Maximum bihourly inflow 
to reservoir was 970 cubic feet per second on March 
26,1989. Maximum release of 220 cubic feet per second 
on June 27, 1989, was below maximum permissible 
flood release. During the year, a total of 7,700 acre-feet 
of water was released for irrigation and other purposes. 
Historical summary. Construction began in July 
1971 and was completed in May 1979. Construction of 
Buchanan and Hidden dam and appurtenances were 
combined under one contract. Project was completed in 
September 1983, except for installation of piezometers 
(now deferred indefinitely). Dam closure was in March 
1975; dam was completed in January 1976. Reservoir 
clearing and boundary marking were completed May 
1975. Bifurcation structure was completed in February 
1976. Channel improvement, Ash and Berenda 
Sloughs, was completed in March 1976. Recreation 
areas: Phase I was completed in January 1976; Phase II 
was completed in February 1978. Residences, administration 
building, and visitors center contract was completed 
in May 1978. Landscaping was completed in May 
1979 and erosion control was completed in April 1979. 
A resources interpretive display and road relocation 
were completed in FY 1982. Dam safety assurance 
studies were initiated in FY 1981. Solar heating was 
installed at Chowchilla recreation area in FY 1984. 
Final land audit was approved on December 3, 1985. 
6. CACHE CREEK BASIN, CA (CACHE 
CREEK SETTLING BASIN) 
Location. At the mouth of Cache Creek in Yolo 
County where it enters the Yolo Bypass about 2 miles 
east of city of Woodland and about 15 miles northwest 
of city of Sacramento, CA. 
Existing project. Provides for raising the perimeter 
levees of the existing settling basin an average of 12 feet, 
extending the levees upstream to County Road 102 to 
provide 50-year sediment storage capacity, enlarging 
and reconstructing the cobble weir, and degrading existing 
training levees and rebuilding them adjacent to 
western perimeter levee to provide 50 years of sediment 
storage capacity (340 acre-feet annually.). Estimated 
cost (October 1989) for existing project is $21,400,000 
(includes an allowance for estimated inflation through 
the construction period), of which $14,700,000 is Federal 
and $6,700,000 is non-Federal (which includes 
$1,070,000 cash contribution). For future non-Federal 
reimbursement, see Local cooperation paragraph. 
Existing project was adopted by Water Resources Development 
Act of 1986, Public Law 99-662, November 
35-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
17, 1986 (HD 98-134, 98th Cong., 1st sess., contains 
published map.) Project as authorized included development 
of a national wildlife refuge within the settling 
basin; however, the Department of the Army determined 
that such refuge would be more appropriately 
funded and developed by the U.S. Fish and Wildlife 
Service. Refuge feature was reclassified to deferred 
category on April 11, 1988. 
Local cooperation. Local interests are required to 
provide lands, easements, rights-of-way, and dredged 
material disposal areas; modify or relocate buildings, 
utilities, roads, bridges (except railroad bridges) and 
other facilities where necessary in construction of the 
project; pay 5 percent of cost allocated to flood control 
to bring total non-Federal share of flood control costs to 
25 percent of which $1,050,000 is cash contribution, 
and bear all costs of operation, maintenance and replacement 
of flood control facilities. Local interests 
have agreed to make all required payments concurrently 
with project construction. 
Operations and results during fiscal year. 
Engineering activities were continued. 
7. CALAVERAS RIVER AND LITTLEJOHN 
CREEK AND TRIBUTARIES, 
INCLUDING NEW HOGAN LAKE 
AND FARMINGTON DAM, CA 
Location. Streams comprising Calaveras River and 
Littlejohn Creek groups rise in Sierra Nevada and its 
foothills, flow easterly across flatlands of San Joaquin 
Valley and empty into San Joaquin River directly, or 
through various sloughs, in vicinity of Stockton, CA. 
Littlejohn Creek is in Calaveras, Stanislaus, and San 
Joaquin Counties. The three principal stream systems of 
the group are, from south to north, Lone Tree Creek, 
Littlejohn Creek, and Duck Creek. Calaveras River 
group is in Calaveras and San Joaquin Counties. The 
two principal streams of the groups are, from south to 
north, Calaveras River and Bear Creek. (See Geological 
Survey Valley Springs quadrangle for New Hogan reservoir 
area and Trigo and Bachelor Valley quadrangles for 
Farmington reservoir area.) 
Existing project. For description of completed 
improvements consisting of Farmington Dam, New 
Hogan Lake, and Bear Creek levee and channel improvement, 
and authorizing act, see Annual Report for 
1967. (a) Farmington: Total first cost (July 1955) for 
project was $3,995,684, of which $3,676,384 was Federal 
and $319,300 non-Federal for lands and damages 
including relocations. (b) New Hogan: Federal cost for 
project is $15,906,150, including $543,514 for basic 
recreation facilities. For future non-Federal reimbursement, 
see Local cooperation paragraph. Federal cost 
for recreation facilities funded from Code 710 appropriations 
is $897,742. (c) Bear Creek: Project cost is 
$6,485,734, of which $3,242,867 is Federal, including 
reimbursement ($488,096) to local interests of one-half 
of excess local interest cost of lands, rights-of-way, and 
relocations over estimated Federal construction cost in 
accordance with section 3, Public Law 738, 74th Congress. 
Non-Federal cost included in above amount is 
$3,242,867 for relocations and lands and damages, 
exclusive of above Federal reimbursement. 
Local cooperation. Fully complied with. New 
Hogan: Local interests must pay portion of first cost and 
annual operation and maintenance costs allocated to 
conservation functions of project. These costs are estimated 
at 36.2 percent of first cost and 38 percent of 
annual costs. In addition, local interests contributed 
land, the (July 1964) market value of which was. 
$556,000. For years 1961 through 1970, an interim 
contract between the Bureau of Reclamation and local 
water users provided for storage and payment of irrigation 
water; local interests paid $3,238,092 through 
December 31, 1988. A long-term contract between that 
agency and local water users was executed August 25, 
1970. A concessionaire at New Hogan Marina provided 
public use facilities in accordance with lease agreement 
with the Secretary of the Army at an estimated cost to 
date of $234,000. 
Operations and results during fiscal year. New 
work: New Hogan Lake, regular funds: None. Code 710 
funds: None. Bear Creek, San Joaquin County: None. 
Maintenance: Farmington Dam-Maintenance and operation 
activities continued; structures were maintained 
in serviceable condition. During rainflood season, Duck 
Creek Diversion and Littlejohn Creek at Farmington 
had no active storage. New Hogan Lake--Maintenance 
and operation activities continued. Dam safety assurance 
studies at New Hogan Dam were continued at a 
fiscal year cost of $14,317. Renovation of recreational 
area was continued at a fiscal year contract cost of 
$672,036. Structures were maintained in serviceable 
condition. Runoff of Calaveras River above New Hogan 
was below normal for the year. Maximum storage of 
41,400 acre-feet occurred April 30, 1989. Maximum 
bihourly inflow to reservoir was 1,500 cubic feet per 
second on March 25, 1989. Maximum release of 310 
cubic feet per second on June 1, 1989, was below maximum 
permissible flood release. During the year, 19,700 
acre-feet was released for irrigation and other purposes. 
Historical summary. Farmington Dam: Construction 
of Farmington project was initiated in July 1949 and 
completed for beneficial flood control operation in 
1952. Duck Creek channel improvement was completed 
in November 1951; and channel improvement on south 
Littlejohn Creek was completed in May 1955. There are 
no recreation facilities or public-use areas. All work 
completed. Dam safety assurance studies were initiated 
in FY 1982. New Hogan Lake: Construction was initiated 
May 1960, main dam closure November 1963, 
project completed for operational use in June 1964, and 
all work completed October 1973. Recreation facilities 
have been provided from Code 710 appropriations. 
Seepage measurement weir constructed in June 1980. 
Dam safety assurance studies were initiated in FY 1980. 
Bear Creek, San Joaquin County: Construction began in 
June 1963 and was completed in June 1967. Final cash 
contribution was made to local interests December 23, 
35-6

SACRAMENTO, CA, DISTRICT 
1970. Solar heating was installed at recreation facilities 
in FY 1984. A cultural resources survey was completed 
in FY 1984. 
8. CORTE MADERA CREEK, CA 
Location. Creek and tributaries drain an area of 28 
square miles in Marin County, CA, and flow into west 
side of San Francisco Bay about 9 miles north of Golden 
Gate. (See Geological Survey quadrangle San Rafael.) 
Existing project. Provides for about 11 miles of 
channel improvements, including realignment, enlargement, 
levees, riprapping, rectangular concrete sections, 
interior drainage facilities, bridge relocations, and debris 
removal on Corte Madera Creek and lower reaches 
of its tributaries, and a continuous channel rights-ofway 
to deep water in San Francisco Bay reserved to 
assure channel outlet in the event of future tideland 
reclamation. Water Resources Development Act of 
1986 modified existing project to direct construction of 
Unit 4 from Lagunitas Road Bridge to Sir Francis Drake 
Boulevard, and to include construction of floodproofing 
measures as necessary to individual properties and other 
necessary structural measures in vicinity of Lagunitas 
Road Bridge to insure proper functioning of completed 
portions of authorized project. Portion of project 
upstream of Sir Francis Drake Boulevard previously 
classified inactive was modified on November 17, 1986 
to eliminate any channel modification. Current project 
has 3 miles of channel enlargement and levees, about 
1.8 miles of rectangular concrete channel improvements, 
and 450,000 cubic yards of redredging on lower 
Corte Madera Creek. Approved estimated cost for new 
work (October 1989) is $29,500,000, of which 
$17,700,000 is Federal cost and $11,800,000 is non- 
Federal cost (includes $730,000 to be contributed by 
local interests.) (See table 34-B for authorizing legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way, including suitable areas for 
disposal of waste material, modify or relocate all bridges 
and utilities necessary for construction and maintenance; 
hold and save the United States free from 
damages due to the construction works; maintain and 
operate the project after completion in accordance with 
the regulations prescribed by the Secretary of the Army, 
and prevent encroachment on flood channels that 
would result in decreasing the effectiveness of project 
for flood control; adjust all claims regarding water rights 
that might be affected by the project; and contribute in 
cash 1.5 percent of Federal construction cost of Ross 
Valley unit and tidal areas, an estimated $730,000. 
Marin County Flood Control and Water Conservation 
District previously furnished resolution of local assurances 
dated March 29, 1966, March 28, 1967, August 
15, 1967, and July 8, 1969, and Marin County Board of 
Supervisors reaffirmed by letter dated September 28, 
1978. Project was authorized by the State of California 
by 1965 Statute, Chapter 1388. Board of Supervisors of 
Marin Connty Flood Control and Water Conservation 
District furnished assurances of willingness and ability to 
meet requirements for portion of project below Sir 
Francis Drake Boulevard. 
On December 13, 1983, Marin County Board of 
Supervisors reconfirmed assurances of local cooperation 
because a Superior Court Judgment ordered that 
county to take all steps required by law to complete 
channel downstream of Sir Francis Drake Boulevard 
(Unit 4) and maintain entire project as agreed. A Local 
Cooperation Agreement for redredging the lower reach 
of Corte Madera Creek was executed on June 29, 1985. 
Marin County also provided support for Ross Valley 
Unit 4 by resolution on March 24, 1987 and by the 
resolution on September 13, 1988. 
Operations and results during fiscal year. New 
work: Engineering continued. Landscaping restoration 
contract for Units 2 and 3 was continued at fiscal year 
cost of $152,697. Waterways Experiment Station 
published a sedimentation study in April 1989. Study 
concluded that existing concrete channel will not 
contain 100-year flows. 
Historical summary. Project responsibility was 
transferred from San Francisco District on April 1, 
1982. Project is about 77 percent complete considering 
the portion being held in abeyance upstream of Sir 
Frances Drake Boulevard. Work remaining: Design 
construction of the remaining 3,000 feet of channel 
downstream of Sir Francis Drake Boulevard and Ross 
Creek. In lieu of the authorized concrete channel, an 
alternative plan consisting of wing walls and individual 
house floodproofing is being recommended in the Significant 
Post-Authorization Change Report. The portion 
of Corte Madera Creek upstream of intersection of 
Sir Francis Drake Boulevard and Corte Madera Creek 
in Ross, near the city of San Anselmo, was classified as 
"inactive" on July 11, 1984, due to lack of local 
support. A Local Cooperation Agreement for redredging 
lower reach of Corte Madera Creek was executed 
June 29, 1985. Construction on Lower Corte Madera 
Creek Channel was completed and transferred to Marin 
County Flood Control and Water Conservation District 
by letter of May 28, 1987. San Francisco District will 
monitor maintenance and operation of the project. 
9. FAIRFIELD VICINITY STREAMS, CA 
Location. On five streams in vicinity of cities of 
Fairfield and Suisun, Solano County, CA. 
Existing project. Provides for channel improvement 
on Ledgewood, Laurel, and McCoy Creeks and diversion 
of three creeks upstream from Fairfield (Pennsylvania 
Avenue Creek into Ledgewood Creek, Union 
Avenue Creek into Laurel Creek, and Laurel Creek into 
McCoy Creek). Project related recreation facilities such 
as access roads, parking areas, a boat-launching ramp 
and hiking, bicycle, and horseback trails would also be 
constructed. Estimated cost (October 1989) for existing 
project is $36,300,000 (includes an allowance for estimated 
inflation through the construction period), of 
which $13,800,000 is Federal and $22,500,000 is non- 
35-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Federal (includes $290,000 cash contribution). For 
future non-Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted by sec. 
201, 1965 Flood Control Act (1970 Senate and House 
Public Works Committee resolutions) and Further Continuing 
Appropriations Act for FY 1986 (Public Law 
99-190), December 19, 1985. (HD 91-159, 91st 
Cong., 1st sess., contains published map). 
Local cooperation. Local interests are required to 
provide lands, easements, rights-of-way, and dredged 
material disposal areas, modify or relocate buildings, 
utilities, roads, and other facilities, except railroad 
bridges, where necessary in the construction of the 
project, pay one-half of the separable costs allocated to 
recreation, presently estimated at $475,000, of which 
$80,000 is for lands, $105,000 is credit for recreation 
facilities built by local interests per Public Law 100-71, 
July 11, 1987, which directs that project proceed under 
provisions of sec. 117, Public Law 99-190, and 
$290,000 is cash contribution; and bear all costs of 
operation, maintenance, and replacement of recreation 
facilities and flood control facilities. Ultimate non-Federal 
cost for flood control will be reduced by a Federal 
reimbursement of one-half of the non-Federal costs in 
excess of the Federal construction costs. Local interests 
have agreed to make all required payments concurrently 
with project construction. 
Project had been in "deferred" status since 
September 15, 1977, due to lack of local assurances. In 
April 1982, the cities of Fairfield and Suisun affirmed 
their support and intent to provide necessary assurances 
of local cooperation for a modified version of the 
authorized project from 200-year to 100-year flood 
protection. On June 23, 1982, project was reclassified 
from "deferred" to "active" status. The State of 
California Reclamation Board has provided a letter of 
intent to the Assistant Secretary of the Army, November 
8, 1982, to cooperate with the Federal Government to 
begin construction of the project. In accordance with 
FY 1985 Supplemental Appropriations Act (Public Law 
99-88) and sec. 117 of the Further Continuing 
Appropriations Act for FY 1986 (Public Law 99-190), 
a Local Cooperation Agreement for flood control and 
recreation (sec. 221) was executed June 3, 1986. 
Sec. 117 of Further Continuing Appropriations Act 
for FY 1986 contained the following authorization 
language which will be reflected in any future modified 
agreements: "The Secretary shall include as part of the 
non-Federal contribution of the project for flood 
control, Fairfield Vicinity Streams, California, 
authorized in accordance with sec. 201 of Flood Control 
Act of 1965, the cost of any work carried out by 
non-Federal interests on the project after December 
31, 1973, and before the date of the enactment of this 
joint resolution if the Secretary determines such work is 
reasonably compatible with the project. Costs and 
benefits resulting from such work shall continue to be 
included for purposes of determining economic 
feasibility of the project." Prior local expenditures of 
$6,800,000 have been reported by the sponsor. The 
Corps is evaluating costs and benefits of all completed 
works by non-Federal interests after December 31, 
1973. 
Operations and results during fiscal year. 
Construction contract for Laurel Creek Diversion 
Channel, Phase II, was physically completed at a fiscal 
year cost of $462,209. Construction contract for Laurel 
Creek and Union Avenue Diversion, Phase III, was 
initiated at a fiscal year cost of $3,204,904. 
Historical summary. Local Cooperation Agreement 
was executed on June 3, 1986. Construction was initiated 
in October 1986. Construction contract for enlarging 
McCoy Creek and constructing Laurel Creek Diversion 
Channel, Phase I, was completed and was transferred 
to local interests in July 1987 for maintenance. 
Construction contract for Laurel Creek Diversion 
Channel, Phase II, was physically completed. Construction 
contract for Laurel Creek and Union Avenue 
Diversion, Phase III, was initiated. 
10. HIDDEN DAM-HENSLEY LAKE, 
FRESNO RIVER, CA 
Location. On Fresno River about 50 miles above its 
mouth and about 15 miles northeast of Madera, CA 
(See Geological Survey quadrangles for area.) 
Existing project. Provides for construction of a 
163-foot high earthfill dam to create a reservoir with 
gross storage capacity of 90,000 acre-feet for flood 
control, irrigation, recreation and other purposes. In 
conjunction with the dam, the project provides for 
about 13 miles of downstream levee and channel 
improvements on Fresno River immediately upstream of 
Chowchilla Canal crossing to accommodate project 
design flow of 5,000 cubic feet per second. Operation 
and maintenance of dam and reservoir is the 
responsibility of the Federal Government. Total first 
cost for existing project is $31,785,426, of which 
$30,555,426 is Federal cost, including $3,564,168 for 
basic recreation facilities, and estimated $1,230,000 
non-Federal cost for lands and damages including 
relocations for downstream levee and channel improvements. 
Local interests have contracted with the Bureau 
of Reclamation for irrigation service. For future 
non-Federal reimbursement, see Local cooperation 
paragraph. Local interests have also, over a period of 
years, expended about $300,000 for construction of low 
levees and clearing downstream channels to provide 
some local flood protection in the project area. This 
work is inadequate during major floods. Existing project 
was adopted by 1962 Flood Control Act (S. Doc. 37, 
87th Cong., 1st sess., contains latest published map). 
Lake created by Hidden Reservoir project on Fresno 
River was designated "Hensley Lake" by Public Law 
93-603. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work. None. Maintenance: Maintenance and operation 
35-8

SACRAMENTO, CA, DISTRICT 
activities were continued. Dam safety assurance studies 
were continued at a fiscal year cost of $8,851. Runoff of 
Fresno River below Hidden Dam was below normal for 
the year. Maximum storage of 23,000 acre-feet 
occurred June 9, 1989. Maximum bihourly inflow to the 
reservoir was 490 cubic feet per second on March 3, 
1989. Maximum release of 230 cubic feet per second on 
July 7, 1989, was below maximum permissible flood 
release. During the year, 16,300 acre-feet of water was 
released for irrigation and other purposes. 
Historical summary. Construction began in July 
1971 and was completed in January 1979. Dam closure 
was in March 1975; dam was completed November 
1975. Instrumentation was completed in January 1976. 
Downstream channel improvement, Fresno River, was 
completed April 1976. Recreation areas: Phase I was 
completed in March 1976; Phase II was completed in 
June 1978. Residences, administration building, 
grounds, and utilities contract was completed in 
February 1978. Landscaping was completed in 
December 1978 and erosion control was completed in 
January 1979. Project was completed in September 
1980. Final land audit was approved February 5, 1980. 
Dam safety assurance studies were initiated in FY 1980. 
Piezometer installation was completed in September 
1982. Solar heating was installed at recreation areas in 
FY 1984. 
11. ISABELLA LAKE, KERN RIVER, CA 
Location. About 35 miles northeast of city of 
Bakersfield, CA, near confluence of north and south 
forks of Kern River; auxiliary dam is about one-half 
mile east of main dam. (See Geological Survey 
quadrangles of area.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1967. Federal cost for new work is $22,027,452. For 
future non-Federal reimbursement see Local cooperation 
and Licenses paragraphs. Federal cost funded 
from Code 710 appropriations is $2,199,085. Operation 
and maintenance of dam and reservoir is Federal 
responsibility. 
Local cooperation. California officially adopted 
project by chapter 1514 of statutes of 1945, State of 
California. Local interests, represented by North Kern, 
Buena Vista, and Tulare Lake Basin Water Storage 
Districts and La Hacienda Water District, were required 
to reimburse the Federal Government the portion of 
first cost and annual operation and maintenance costs 
allocated to irrigation functions of project. These costs, 
based on a cost allocation study completed in December 
1955, are $4,573,000 of first cost and 21.7 percent of 
annual operation and maintenance cost. For the years 
1956 through 1964, an interim contract between the 
Bureau of Reclamation and local water users provided 
for storage and payment of irrigation water. Under 
provisions of this interim contract, local interests paid 
$1,936,229 through December 31, 1964. A long-term 
contract between the Bureau and local water users was 
executed October 23, 1964. Balance due on allocated 
first cost of $4,573,000 was paid by the water users on 
March 31, 1965. Kern County assumed administration 
of recreation and development and maintenance of 
public use areas at project in accordance with a 25-year 
license February 15, 1955. The agreement with Kern 
County provided for joint operation and development 
by the Corps and Kern County including permits granted 
to concessionaires by the county to provide certain 
services. As of September 30, 1971, Kern County 
relinquished all administration of recreation and 
development and maintenance of public use areas at the 
project. A State law permitting the Department of 
Boating and Waterways (known as the Department of 
Navigation and Ocean Development prior to January 
1979) to participate in inland water development with 
Federal agencies was signed by the Governor on August 
11, 1972. All concessionaires will operate under permits 
granted by the Corps. Total cost to date of present 
recreation facilities developed by the county and the 
marina concessionaires is about $965,000; $235,000 of 
this was a grant from the California Wildlife 
Conservation Board and about $534,000 is investment 
by marina concessionaires. 
Licenses. In accordance with Federal Power Commission 
Docket No. E-6578, issued April 1, 1963, 
payment of $377,426 was made to the Federal Government 
by Pacific Gas and Electric Co. ($108,352) and 
Southern California Edison Co. ($269,074) for headwater 
benefits to downstream existing plants from 
Isabella Dam to cover benefits from April 15, 1954, to 
December 31, 1962. Between 1962 and 1982, the 
power companies have in the aggregate made annual 
payments of $44,650 for headwater benefits. That 
amount was to be paid each year until changes in 
operation, development, or costs indicated some modification 
to be advisable. Federal Power Commission 
Docket No. E-6578 was revised by Docket No. 
HB07-75-4-000 (order issued July 11, 1983 under 24 
FERC, paragraph 62052) which modified cumulative 
use charges after 1974, effective retroactively. Such 
charges will now vary each year. An adjustment (years 
1974 through 1984) was included in 1984 payment of 
$244,790. The 1985 payment was $52,747; 1986 payment 
was $51,905. No payment was received in 1987. 
The 1988 payment was $58,187. No payment was 
received in 1989. Cumulative use charges collected by 
the Federal Power Commission (known as the Federal 
Energy Regulatory Commission since January 9, 1978) 
and returned to the U. S. Treasury through period 
ending September 30, 1989, amounted to $1,767,355. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation continued. 
Structures were maintained in good condition. Runoff 
of Kern River above Isabella Dam was below normal for 
the year. Maximum storage of 184,800 acre-feet occurred 
June 1, 1989. Maximum bihourly inflow to the 
reservoir was 2,600 cubic feet per second on March 3, 
1989, and maximum outflow of 1,900 cubic feet per 
second occurred July 13, 1989. During the year, 
35-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
335,600 acre-feet was released for irrigation and other 
purposes. 
Historical summary. Construction began in March 
1948 and was completed in June 1968. Main dam, 
Borel Canal outlet works and appurtenances, and 
auxiliary dam were completed in April 1953. Storage 
impoundment began December 1952. Piezometer was 
installed in August 1982. Project is operating to provide 
flood protection and irrigation benefits for which it was 
designed. Recreation facilities were provided by Code 
710 funds. Dam safety assurance studies were initiated 
in FY 1979. A cultural resources survey was completed 
in FY 1984. 
12. KAWEAH AND TULE RIVERS, 
INCLUDING TERMINUS DAM 
AND SUCCESS LAKE, CA 
Location. Terminus Dam is on Kaweah River about 
20 miles east of Visalia, CA. Success Lake is on Tule 
River about 5 miles east of Porterville, CA. (See 
Geological Survey quadrangles of area.) 
Existing project. Terminus Dam: For description of 
completed improvement and authorizing act, see 
Annual Report for 1975. Federal cost of new work is 
$19,302,957, including $242,605 for basic recreation 
facilities and excluding spreading works constructed by 
local interests at an estimated (July 1957) cost of about 
$750,000. Spreading works portion of project has been 
deauthorized. The 90-day Congressional project review 
period, required by sec. 12, Public Law 93-251, as 
amended, ended August 5, 1977, and resulted in 
deauthorization of that portion of project. Federal cost 
of recreation facilities funded from Code 710 
appropriations is $700,004. Success Lake: For 
description of completion improvement and authorizing 
act, see Annual Report for 1975. Federal cost of new 
work for Success Lake is $14,247,221, including 
$253,697 for basic recreation facilities. Federal cost of 
recreation facilities funded from Code 710 appropriations 
is $747,048. For future non-Federal reimbursements, 
see Local cooperation paragraph. Operation 
and maintenance of reservoirs is Federal responsibility. 
Local cooperation. California officially adopted 
projects by chapter 1514 of statutes of 1945, State of 
California. Local interests for Terminus Dam are 
represented by Kaweah Delta Water Conservation 
District. Local interests for Success Lake are considered 
to be represented by the Vandalia, Porterville, and 
Lower Tule River Irrigation Districts, the Tulare Lake 
Basin Water Storage District, and Pioneer Water Co., 
which represent over 90 percent of irrigated land and 
water-right holders along Tule River below damsite. 
Local interests must reimburse the Federal Government 
the portion of first cost and annual operation and 
maintenance costs allocated to irrigation functions of 
projects. These costs are estimated at 14.1 percent of 
first and annual costs for Terminus and 9.5 percent of 
first and annual costs for Success. Local interests for 
Terminus stated they will continue to operate and 
maintain spreading works and downstream channel 
systems to provide required capacity for disposal of 
floodwaters. Local interests for Success stated they will 
continue to maintain downstream channel systems to 
provide required capacity for disposal of floodwaters. 
Repayment contracts between the Bureau of Reclamation 
and local water users for irrigation supply from 
Terminus and Success reservoirs were executed January 
11, 1965, and April 30, 1965, respectively. Reservoirs 
are being operated for irrigation storage as well as flood 
control and incidental recreation use. Tulare County 
acquired water for recreation pools at the projects. 
Local interests paid the following total amounts for 
irrigation services from the reservoirs through December 
31, 1988: Terminus, $1,801,206 and Success, 
$847,903. Tulare County was granted a 25-year license 
for planning, development, and management of public 
recreation areas at Success, July 10, 1960, and at 
Terminus, June 5, 1961. Basic public-use facilities 
constructed by Corps at the Success reservoir were 
transferred to jurisdiction of Tulare County on January 
18, 1962; facilities at Terminus were transferred June 
20, 1962. In March 1967, an amendment to the license 
agreements was approved by the Assistant Secretary of 
the Army. Under these amended licenses, Tulare 
County retained administration of only specified land 
areas and operation and maintenance of recreation 
facilities in these areas. In addition, they continued their 
program of water safety, boat inspection, and law 
enforcement at both reservoirs. The Corps took over the 
administration of the remainder of the project land 
areas and the operation and maintenance of recreation 
facilities in these areas. Calif. Department of Fish and 
Game expended funds to improve fishery resources of 
the Terminus reservoir. As of April 1, 1972, Tulare 
County relinquished all planning, development, and 
management of public recreation areas at Terminus 
Dam. Tulare County by expenditure of county funds 
and by a lease to a marina concessionaire has aided in 
the development of recreation facilities at an estimated 
cost of $199,000. Calif. Department of Fish and Game 
expended funds in conjunction with Tulare Sportsman's 
Council and developed a habitat for upland game birds 
at Success Lake. As of April 1, 1972, Tulare County 
relinquished all planning, development, and management 
of public recreation areas at Success Lake, except 
for the Bartlett Park recreation area. Tulare County has 
aided in development of recreation facilities. Total cost 
to date of present recreation facilities developed by the 
county ($360,000) and the marina concessionaires 
($373,000) is about $733,000. 
Operations and results during fiscal year. New 
work: Terminus Dam, regular funds: None. Code 710 
funds: None. 
Success Lake, regular funds: None. Code 710 funds: 
None. 
Maintenance: Terminus Dam: Maintenance and 
operation continued. Dam safety assurance studies were 
completed at a fiscal year cost of $138. Structures were 
maintained in serviceable condition. Runoff of Kaweah 
River above Terminus Dam was below normal for the 
35-10

SACRAMENTO, CA, DISTRICT 
year. Maximum storage of 129,000 acre-feet occurred 
on May 31, 1989. Maximum bihourly inflow to the 
reservoir on April 11, 1989, was about 1,600 cubic feet 
per second. Maximum outflow of 2,000 cubic feet per 
second occurred June 9, 1989. Water released for 
irrigation and spreading releases totaled 207,000 
acre-feet. Success Lake: Maintenance and operation 
continued. Dam safety assurance studies were completed 
at a fiscal year cost of $2,294. Structures were 
maintained in serviceable condition. Runoff of Tule 
River above Success Dam was below normal during the 
year. Maximum bihourly inflow to the reservoir was 
1,900 cubic feet per second on March 3, 1989, and 
maximum outflow of 470 cubic feet per second occurred 
on August 2, 1989. Maximum storage of 42,100 
acre-feet occurred on June 2, 1989. Water released for 
irrigation and spreading releases amounted to 49,700 
acre-feet. 
Historical summary. Terminus Dam: Construction 
of project began in July 1957 and was completed in June 
1968. Final land audit was approved on April 20, 1987. 
Construction of main dam and appurtenances, initiated 
in February 1959, was completed in June 1962. Dam 
has been operating since November 1961 to provide 
flood protection for which it was designed; conservation 
impoundment was commenced May 1962. Appurtenances 
are in good condition. Recreation facilities were 
provided by Code 710 funds. Dam safety assurance 
studies were initiated in FY 1979 and completed in FY 
1989. Piezometer installation and a cultural resources 
survey were completed in FY 1984. Success Lake: 
Construction of project began in November 1956, was 
completed in June 1968, and final audit of historical 
land record was approved December 17, 1979. 
Construction of main dam and appurtenances, initiated 
in October 1958, was completed in May 1961. Dam has 
been operating since October 1960 to provide flood 
protection for which it was designed; conservation 
impoundment was commenced March 1962. Recreation 
facilities were provided by Code 710 funds. Dam 
safety assurance studies were initiated in FY 1979 and 
completed in FY 1989. A cultural resources survey was 
completed in FY 1984. 
13. LITTLE DELL LAKE, UT 
Location. On Dell Creek, a tributary of Parleys 
Creek, about 8 miles east of Salt Lake City upstream of 
Mountain Dell Reservoir in Salt Lake County, UT. 
Existing Project. Project providing for construction 
of a dam about 253 feet high to create a reservoir with a 
gross capacity of 30,000 acre-feet for flood control, 
municipal and industrial water supply, recreation and 
fish and wildlife was authorized by the 1968 Flood 
Control Act (S. Doc. 53, 90th Cong., 1st sess., contains 
published map) as modified by sec. 170, Water 
Resources Development Act of 1976, Public Law 
94-587, October 22, 1976. Facility would be operated 
in conjunction with existing downstream 3,200 
acre-foot Mountain Dell Reservoir on Parleys Creek for 
flood control and water supply. 
Authorized project has been reexamined and scaled 
down to reflect local interests' ability to pay. Current 
plan of improvement includes only flood control and 
water supply purposes. Recreation was deferred as of 
May 30, 1986, and Emigration Creek Diversion was 
deleted and placed in an inactive status. Project will 
include an earthfill dam 224 feet high, a 20,500 
acre-foot reservoir, and 10,035 feet of pipeline to divert 
water from Parleys Creek. Estimated project cost 
(October 1989) is $56,800,000 (includes an allowance 
for estimated inflation through the construction period) 
of which $32,700,000 is Federal and $24,100,000 is 
non-Federal for lands and damages and includes a cash 
contribution of $17,500,000. Project is included in FY 
1985 Supplemental Appropriations Act (Public Law 
99-88) August 15, 1985. 
Local cooperation. Local interests are required to 
provide lands, easements, rights-of-way, and dredged 
material disposal areas; modify or relocate buildings, 
utilities, roads, bridges (except railroad bridges), and 
other facilities where necessary in the construction of 
the project; pay all costs allocated to municipal and 
industrial water supply; pay 13 percent of costs allocated 
to flood control to bring total non-Federal share of 
flood control costs to 25 percent, bear all costs of 
operation, maintenance, and replacement of flood 
control facilities; and pay a cash contribution presently 
estimated at $17,500,000. By letters of January 22, 
1986, and January 24, 1986, the Metropolitan Water 
District of Salt Lake City and Salt Lake County 
indicated their support and willingness to proceed with a 
reduced scale project based on their "ability to pay." A 
Local Cooperation Agreement (sec. 221) was executed 
on June 10, 1986. Water Revenue Bonds were issued 
August 27, 1986, and proceeds from the sale in the 
amount of $14,300,000 have been deposited in the 
Little Dell Construction Fund Account. 
Operations and results during fiscal year. 
Engineering activities continued. Construction of core 
trench and test fill was completed at a fiscal year 
contract cost of $198,950. Main dam and appurtenances 
contract was awarded in May 1989; construction 
was initiated at contract fiscal year cost of $1,920,367. 
Relocations were essentially completed by the State of 
Utah and several utility companies. Main dam and 
appurtenances contract was awarded in May 1989; 
construction was initiated at contract fiscal year cost of 
$1,920,367. 
Historical summary. A Local Cooperation 
Agreement (sec. 221) was executed June 10, 1986. 
Construction was initiated in April 1988. Construction 
of core trench and test fill was completed in February 
1989. Main dam and appurtenances contract was 
awarded May 12, 1989. 
14. LOWER SAN JOAQUIN RIVER, CA 
Location. On Lower San Joaquin River, CA, from 
city of Stockton, CA, extending about 225 miles 
upstream to Friant Dam (about 19 miles northeast of 
35-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Fresno) and along Kings River North for approximately 
25 miles upstream from Mendota Dam. 
Existing project. This project is a modification and 
extension of the previous Lower San Joaquin River and 
Tributaries project (see Annual Report for 1976) to 
provide clearing and snagging on San Joaquin River 
from Stockton, CA, upstream to Friant Dam. Estimated 
first cost (October 1989) is $29,776,000, of which 
$22,876,000 is Federal and $6,900,000 is non-Federal 
for lands and damages (includes an allowance for 
estimated inflation through the construction period as 
well as $12,976,000, Federal, and $5,000,000, 
non-Federal, for work completed by 1974). Existing 
project was included in the 1983 Supplemental 
Appropriations Act, Public Law 98-63, July 29, 1983, 
which states that project for flood protection on Lower 
San Joaquin River, CA, authorized by the Flood 
Control Act approved December 22, 1944, as 
amended, is modified to authorize the Secretary of the 
Army, acting through the Chief of Engineers, to perform 
clearing and snagging on San Joaquin River from 
Stockton, CA, to Friant Dam, at an estimated cost of 
$5,000,000. The Energy and Water Development 
Appropriation Act of 1988, Public Law 100-202, 
December 22, 1987 (H.J. Res. 395) modifies 
Supplemental Appropriations Act of 1983 to include: 
clearing and snagging in area of North Fork of Kings 
River in Mendota Pool from southerly boundary of 
James Reclamation District Number 1606 to Mendota 
Dam; fish and wildlife mitigation; and such riprapping in 
area of clearing and snagging on such rivers as may be 
necessary to prevent erosion from such clearing 
snagging; and increase estimated cost of clearing and 
snagging on Lower San Joaquin River, including 
activities above, from $5,000,000 to $8,000,000. 
Local cooperation. Prior to initiation of construction, 
a non-Federal entity shall furnish adequate 
assurance for providing all lands, easements, rights-ofway 
and dredged material disposal areas; modify or 
relocate buildings, utilities, roads, bridges (except 
railroad bridges), and other facilities, where necessary 
in construction of project at no expense to the Federal 
Government, execute a local cooperation agreement 
pursuant to sec. 221 Public Law 96-611; agree to 
operate and maintain the project works upon 
completion of construction in accordance with rules and 
regulations prescribed by the Department of the Army; 
and hold and save the United States free from damages 
due to construction, operation, and maintenance of the 
project, not including damages due to the fault or 
negligence of the United States or its contractors. 
Non-Federal sponsor, the California State Reclamation 
Board, has agreed to make all required payments 
concurrently with project construction. 
Operations and results during fiscal year. 
Coordination with local interests and pertinent agencies 
was continued. Lack of concensus of support by 
Federal, State and local entities led to recommendation 
to terminate project. 
Historical summary. A Plan of Action, February 
1984, has been prepared. Design Memorandum No. 5 
for Eastside Bypass at San Joaquin River was prepared 
in September 1984. First construction contract, 
dredging Eastside Bypass, was awarded October 12, 
1984 and completed in May 1985. 
15. MARTIS CREEK LAKE, MARTIS 
CREEK, NV AND CA 
Location. Reservoir is on Martis Creek a tributary of 
Truckee River, near Truckee, CA; intermittent channel 
improvements are on Truckee River in Reno, NV. (See 
Geological Survey quadrangles for areas.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1975. Federal cost for project was $8,503,789 
including $289,506 for basic recreation facilities. 
Federal cost of recreation facilities funded from Code 
710 appropriations was $1,200. Construction of 
recreation facilities under Code 710 was determined to 
be infeasible. Operation and maintenance of reservoir is 
Federal responsibility. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and operation 
of project, including recreation facilities, was continued. 
Structures were maintained in serviceable condition. 
Runoff above Martis Creek Dam was below normal for 
the year. Maximum storage of 900 acre-feet occurred 
on March 11, 1989. Maximum bihourly inflow to the 
reservoir was 350 cubic feet per second on March 11, 
1989, and maximum outflow of 250 cubic feet per 
second occurred March 11, 1989. 
Historical summary. Project construction began in 
August 1967; dam closure was in October 1971; dam 
completed in August 1972; basic recreation facilities 
were completed in December 1972; and project was 
completed in June 1974. Recreation facilities under 
Code 710 funding were considered infeasible. Dam 
safety assurance studies were initiated in FY 1981. 
16. MERCED COUNTY STREAMS, CA 
Location. In vicinity of city of Merced, CA, on 
streams draining from Mariposa County foothills of the 
Sierra Nevada into Merced County. Streams lie easterly 
of and drain into the San Joaquin River between 
Chowchilla River on the south and Merced River on the 
north. Drainage area represents about 1,000 square 
miles; nearly 700 square miles of foothills and 
mountains in Mariposa County and about 300 square 
miles of flood plain in Merced County. (See Geological 
Survey quadrangles for area.) 
Existing project. Project is a modification of 
Merced County Stream Group, Calif., Improvement 
No. 17, authorized by 1944 Flood Control Act (H. Doc. 
473, 78th Cong., 2d sess.) and completed in FY 1957. 
Existing project provides for construction of three new 
35-12

SACRAMENTO, CA, DISTRICT 
reservoirs-Castle, Haystack Mountain, and Marguerite 
on Canal, Black Rascal, and Deadman-Dutchman 
Creeks, respectively, and enlargement of four existing 
reservoirs-Burns, Bear, Owens, and Mariposa, providing 
a total capacity of 126,700 acre-feet for 
multipurpose storage; and about 52 miles of levee and 
channel improvements in lower reaches of Bear, Black 
Rascal, Mariposa, and Deadman Creeks, thereby tying 
the existing project channels into Eastside Bypass of San 
Joaquin River flood control system. Haystack Mountain, 
Bear, and Owens projects would provide flood 
control only; Castle and Burns projects, flood control 
and recreation; Marguerite project, flood control and 
irrigation; and Mariposa project, all three purposes. 
Existing project was adopted by 1970 Flood Control Act 
(Document not yet printed.) 
Current plan of improvement would defer enlargement 
of existing Burns reservoir, Mariposa reservoir, 
construction of Marguerite Dam, and the irrigation 
function associated with the latter two facilities, 
enlargement of existing Owens reservoir and about 32 
miles of levee and channel improvement on Owens, 
Mariposa, and Deadman-Dutchman Creeks. Estimated 
project cost (October 1989) is $100,900,000 (includes 
an allowance for estimated inflation through the 
construction period), of which $70,500,000 is Federal 
and $30,400,000 is non-Federal. 
Local cooperation. Local interests are required to 
provide lands, easements, and rights-of-way and 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, and other facilities, where 
necessary in the construction of the project; pay 
one-half of the separable and joint costs allocated to 
recreation, presently estimated at $230,000, of which 
$190,000 is a cash contribution and $40,000 is for 
lands; and bear all costs of operation, maintenance, and 
replacement of flood control facilities. Total non-Federal 
share of Castle Dam first cost is $3,000,000 and 
includes cash contribution of $470,000. 
The California Reclamation Board and the City of 
Merced are the local sponsors of the authorized project. 
The Reclamation Board will serve as sole sponsor for the 
Castle Dam Unit. Merced County Board of Supervisors 
reaffirmed their support for the project by letter of April 
4, 1986. City of Merced by letter of March 13, 1986, 
reaffirmed its support for and intent to furnish 
assurances for recreation aspects of the project. 
California Reclamation Board reaffirmed its support for 
total project by letter of April 9, 1986. A Local 
Cooperation Agreement (sec. 221) was executed for 
Castle Dam Unit on June 27, 1986. State of California 
legislation (AB3369) was enacted on September 14, 
1986 which enabled the Reclamation Board to 
financially participate in the project. A new Local 
Cooperation Agreement (LCA) was signed by the 
Assistant Secretary of the Army November 30, 1988, in 
accordance with the Water Resources Development Act 
of 1986. 
Operations and results during fiscal year. 
Engineering activities continued with completion of 
plans and specifications for Castle Dam. 
17. MERCED COUNTY STREAM 
GROUP, CA 
Location. Reservoirs and channel improvements are 
on Bear, Burns, Mariposa, and Owens Creeks, in 
foothills of Sierra Nevada about 15 to 20 miles east of 
city of Merced, CA. (See Geological Survey Haystack 
Mountain quadrangle for Burns and Indian Gulch 
quadrangle for Bear, Owens, and Mariposa areas.) 
Existing project. For description of completed 
improvements and authorizing act, see Annual Report 
for 1962. Improvements consist of reservoirs at 
Mariposa, Owens, Burns and Bear Creeks and 
diversions from Black Rascal Creek to Bear Creek and 
from Creek to Mariposa Creek. Total first cost for 
project was $3,899,259, of which $2,751,259 was 
Federal and $1,148,000 non-Federal for lands 
including relocations and channel improvement. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Ordinary maintenance and operation of 
the four completed reservoirs continued. Structures 
were maintained in a serviceable condition. Runoff from 
drainage areas above Merced County stream group 
reservoirs was below normal for the year. See Table 
35-K for maximum inflow storage and outflow for the 
projects. Outflows were less than channel capacity rates 
in the project streams. 
Historical summary. Construction was initiated 
March 1948, with construction of Mariposa project, 
which was completed in November 1948. Construction 
of Owens project, initiated in March, was completed in 
October 1949; Burns project, initiated in July 1949, was 
completed in January 1950; and Bear project initiated 
in April, was completed in December 1954. Black 
Rascal and Owens Creek diversion channels and 
stream-gaging stations were completed in April 1956. 
Local interests completed channel enlargement and 
restoration of channel capacities of Miles, Burns, 
Owens, and Mariposa Creeks in 1956 at their expense. 
Improvement of Bear Creek and Black Rascal Slough, 
below their confluence, was deferred pending possible 
improvements downstream, outside limits of project. 
18. PAJARO RIVER, CA 
Location. In the Uvas-Carnadero and Llagas Creeks 
watersheds of the upper Pajaro River Basin in south 
Santa Clara County in vicinity of the city of Gilroy about 
75 miles south of San Francisco, CA. 
Existing project. Provides for construction of a 
2-mile levee along the north side of Uvas Creek from a 
point about 2,000 feet downstream of Thomas Road to 
about 3,500 feet upstream of Miller Avenue. Project 
will also include a bikeway and hiking trail. Estimated 
35-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
cost (October 1989) for existing project is $14,790,000 
(includes an allowance for estimated inflation through 
the construction period), of which $5,395,000 is 
Federal and $7,395,000 is non-Federal (which includes 
$795,000 cash contribution). For future non-Federal 
reimbursement, see Local cooperation paragraph. 
Existing project was adopted by Flood Control Act of 
1944, December 21, 1944 (HD 505-78, 78th Cong., 2d 
sess., contains published map.) 
Local cooperation. Local interests are required to 
provide lands, easements, right-of-way, and dredged 
material disposal areas; modify or relocate buildings, 
utilities, roads, bridges (except railroad bridges) and 
other facilities where necessary in construction of 
project; pay one-half of separable costs allocated to 
recreation and bear all cost of operation, maintenance, 
and replacement of recreation facilities; and pay 5 
percent of cost allocated to flood control and bear all 
costs of operation, maintenance and replacement of 
flood control facilities. Local interests will receive an 
estimated Federal reimbursement of $6,228,000 for 
one half of non-Federal costs allocated to flood control 
in excess of Federal costs. Local interests have agreed to 
make all required payments concurrently with project 
construction. 
Operations and result during fiscal year. First 
construction contract (levee work and bike path 
upstream of Thomas Road Bridge) was completed at 
fiscal year cost of $2,320; second construction contract 
(levee work and hiking trails), continued at fiscal year 
cost of $69,227; and the third and final construction 
contract (landscaping) was initiated at fiscal year cost of 
$106,504. 
Historical summary. Responsibility for remaining 
portions of advance engineering and design, plans and 
specifications, and construction was transferred to 
Sacramento District in April 1982. Local Cooperation 
Agreement (LCA) for flood control was executed with 
the Santa Clara Valley Water District on June 25, 1987, 
and LCA for recreation was executed with the City of 
Gilroy on July 27, 1987. Construction began in October 
1987. 
19. PINE FLAT LAKE AND KINGS 
RIVER, CA 
Location. Reservoir is on Kings River, about 25 miles 
east of Fresno, CA, and channel improvements are on 
Kings River downstream from Lemoore weir, about 25 
miles south of Fresno. (See Geological Survey 
quadrangles of area.) 
Existing project. Improvement is a unit in 
comprehensive plan for flood control and other related 
purposes for Sacramento-San Joaquin Basins. Project 
consists of a 429-foot high concrete gravity dam, 
including a gated overflow section with a maximum 
discharge capacity of 391,000 cubic feet per second, 
creating a reservoir with gross storage capacity of 1 
million acre-feet, for flood control, irrigation, and 
related purposes. Outlet provisions for future power 
development are included in dam, but Federal 
construction of power-generating facilities is not 
authorized. Improvement also includes levee and 
channel work on Kings River and its distributaries on 
valley floor about 25 miles south of Fresno. Channel 
improvement work will enlarge channel capacities and 
regulate flows in lower branches of the Kings River. 
There are nine public-use and recreation areas: One 
maintained by the Corps, four by the Forest Service, 
three jointly by the Corps and concession, and one by 
Fresno County. Also, five boat access-only areas are 
maintained by the Corps on the south side of the 
reservoir. Project cost is $42,072,330, of which 
$41,502,330 is Federal (including $13,700 for basic 
recreation facilities) and $570,000 non-Federal for 
rights-of-way for downstream channel improvements. 
For future non-Federal reimbursement, see Local 
cooperation paragraph. Federal cost of recreation 
facilities for Pine Flat Lake, funded from Code 710 
appropriations is $1,595,100 exclusive of recreation 
facilities previously provided at a cost of $13,700. In 
addition, Federal cost of recreation facilities for Pine 
Flat Lake, funded from Public Works Acceleration 
Executive Act of 1962 appropriations, was $239,235 
(July 1963). Operation and maintenance of dam and 
reservoir is Federal responsibility. Existing project was 
adopted by 1944 Flood Control Act (H. Doc. 630, 76th 
Cong., 3d sess., contains latest published map). 
Local cooperation. Local interests must reimburse 
the Federal Government for first costs allocated to 
irrigation functions of reservoir portion of project in 
accordance with reclamation law. Under provision of 
War Department Civil Appropriations Act of 1947, the 
Secretary of War, with concurrence of the Secretary of 
the Interior, determined allocation of cost to irrigation 
should be set at an amount not to exceed $14,250,000. 
In addition, local interests must pay 37.4 percent of 
annual maintenance, operation, and replacement costs 
of dam and reservoir allocated to irrigation function. 
Repayment contracts between the Bureau of Reclamation 
and the local water users for the irrigation use of the 
reservoir were executed December 23, 1963. The 
Bureau is administering the contracts in accordance 
with reclamation law as amended by the Reclamation 
Reform Act of October 12, 1982. That act generally 
exempts the limitations under the early reclamation laws 
as being applicable to projects constructed by the Corps 
with two exceptions; however, all existing contracts to 
share construction and maintenance costs remain in 
effect. Prior to execution of the final contracts, the 
Bureau provided conservation water to local interests 
under an interim contract. Irrigation interests paid 
$13,062,723 for irrigation services through December 
31, 1988. With respect to the downstream channel 
improvements, sec. 3, Flood Control Act of June 22, 
1936, applies. King River Conservation District 
represents local interests; assurances were acceptcd 
November 20, 1959. Local interests have furnished all 
requirements for construction rights-of-way for construction 
of channel improvements required to date, 
Three concessionaires each at Lakeridge Marina (Deer 
35-14

SACRAMENTO, CA, DISTRICT 
Creek), Pine Flat Marina and Trimmer Marina 
provided public-use facilities in accordance with lease 
agreements with the Secretary of the Army. Estimated 
cost to date of facilities installed by these concessionaires 
is $1,727,000. Fresno County developed publicuse 
facilities on an 85-acre tract immediately 
downstream from dam for picnicking, camping, 
swimming, and playground activities, at an estimated 
cost to date of $476,000 under provisions of a license 
agreement. The U.S. Forest Service developed and 
operates a picnic area at the upper end of reservoir. 
Cost of site development is about $37,500. Installation 
of a hydroelectric powerplant, located at the downstream 
toe of the Corps Pine Flat Dam, was completed 
in January 1984 by Kings River Conservation District. 
Project consists of an outdoor-type powerhouse 
containing three generating units with capacities of 55 
megawatts each for a total of 165 megawatts. 
Conservation District would make use of the three 
existing 13.5-foot diameter penstocks that were 
installed in Pine Flat Dam when constructed in 1954. 
Licenses. License No. 1988, effective April 1, 1955, 
was issued by Federal Power Commission to Pacific Gas 
and Electric Co. for hydroelectric power development 
of North Fork Kings River by the company upstream 
from the Pine Flat reservoir. Under interim Contract 
No. DA-04-167-eng-1182 with the Department of the 
Army, Pacific Gas and Electric Co. paid for storage of 
power water in the Pine Flat reservoir May 15, 1954, 
through March 31, 1955. Current Contract No. 
DA-04-167-eng-1328 with the Department of the 
Army provides for storage of power water at the rate of 
0.1375 per acre-foot; the contract covers April 1, 1955, 
through March 31, 2005. By an agreement of January 
1972, supplementing the December 1954 contract, 
Pacific Gas and Electric Co. transferred ownership of 
most of its Kings River system water to the Kings River 
Water Association. Accordingly, no further significant 
storage service to Pacific Gas and Electric Co. by the 
reservoir at Pine Flat is anticipated. Total payment 
under these contracts through June 30, 1972, (last year 
of payment), amounts to $2,478,798; these funds were 
paid to Sacramento District and deposited for return to 
the Treasury. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation activities 
continued. Structures were maintained in serviceable 
condition. Runoff of Kings River above Pine Flat Dam 
was below normal for the year. Maximum storage of 
386,200 acre-feet occurred on May 29, 1989. 
Maximum bihourly inflow to the reservoir was 5,080 
cubic feet per second on May 8, 1989, and maximum 
outflow of 6,700 cubic feet per second occurred on June 
12, 1989. During the year, 924,000 acre-feet was 
released for irrigation and spreading. 
Historical summary. Construction began in April 
1947 and project, including channel improvement, was 
completed in September 1977. Main dam was initiated 
in January 1950, completed in June 1954, and has been 
operating since February 1954 to provide flood 
protection for which it was designed. Total of 35.2 miles 
of new and reconstructed levees and 13.2 miles of 
channel clearing have been transferred to the Kings 
River Conservation District for maintenance. Recreation 
facilities for various recreation areas under Code 
710 appropriation are complete. Completed preliminary 
design and cost estimates for Pine Flat fish barrier were 
reviewed by the State, but the State was unable to 
provide necessary assurances of local cooperation. Dam 
safety assurance studies were initiated in FY 1982. A 
cultural resources survey was completed in FY 1984. 
20. REDBANK AND FANCHER 
CREEKS, CA 
Location. Northeast and adjacent to the Fresno- 
Clovis Metropolitan Area in Fresno County about 170 
miles southeast of Sacramento, CA. 
Existing project. Provides for flood control 
detention basins on Redbank Creek, Pup Creek, and 
Alluvial Drain; construction of a dam 45.5 feet high to 
create a reservoir with gross capacity of 10,300 
acre-feet for flood control on Fancher Creek; and 
enlargement of Big Dry Creek project to provide 
increased flood protection and recreational development. 
Since the local sponsor does not support 
recreational development at this time, the recreation 
feature of the project is considered to be inactive. The 
authorization Act states "measures determined appropriate 
by the Secretary of the Army to minimize benefits 
to groundwater recharge" shall be included in the 
project. Estimated cost (October 1989) for existing 
project is $67,200,000 (includes an allowance for 
estimated inflation through the construction period), of 
which $50,400,000 is Federal and $16,800,000 is 
non-Federal (which includes $5,138,000 cash contribution). 
For future non-Federal reimbursement, see 
Local cooperation paragraph. Existing project was 
adopted by sec. 401, Water Resources Development 
Act of 1986, Public Law 99-662, November 17, 1986. 
(HD 98-147, 98th Cong., 2d sess., contains published 
map.) 
Local cooperation. Local interests are required to 
provide lands, easements, rights-of-way, and dredged 
material disposal areas; modify or relocate buildings, 
utilities, roads, bridges (except railroad bridges) and 
other facilities where necessary in construction of the 
project; pay 5 percent of cost allocated to flood control 
to bring total non-Federal share of flood control costs to 
25 percent, of which $5,138,000 is cash contribution, 
and bear all costs of operation, maintenance and 
replacement of flood control facilities. Local interests 
have agreed to make all required payments concurrently 
with project construction. 
Operations and results during fiscal year. Engineering 
activities were continued. Construction contract 
was completed for Dry Creek Crossing at a fiscal year 
cost of $87,333 and was transferred to local interests for 
operation and maintenance on January 10, 1989. 
Cultural Resources Preservation contract was essentially 
35-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
completed. Construction contract for Redbank Creek 
Detention Basin was awarded September 14, 1989. 
Historical summary. Local Cooperation Agreement 
was executed on August 1, 1987. Project construction 
was begun in September 1987 with initiation of 
archaeological work on Cultural Resources Preservation. 
Construction contract for Dry Creek Crossing was 
completed and transferred to local interests for 
operation and maintenance on January 10, 1989. 
21. RUSSIAN RIVER BASIN, CA 
Location. Russian River rises in Coast Range in 
northwestern California, flows southerly for 87 miles, 
and then turns westerly to flow for 23 miles to Pacific 
Ocean at Jenner, 60 miles northwest of San Francisco, 
CA. (For general location see Geological Survey map 
for California.) 
Existing project. Active authorized project provides 
for construction of a dam on East Fork of Russian River 
at Coyote Valley to a height of 160 feet; a dam on Dry 
Creek at Warm Springs to a height of 319 feet; and 
channel stabilization works on Russian River between 
mouth and mile 98, on lower reaches of several 
tributaries, and on Dry Creek downstream from dam. 
Project also provides for expansion of fish hatchery 
capacity at Dry Creek, Warm Springs, to compensate 
for fish losses on Russian River attributed to operation of 
Coyote Dam component of project. Coyote Valley Dam 
(Lake Mendocino), completed in 1959, is operated and 
maintained by the United States. (See tables 35-L and 
35-M for latest approved estimated costs.) 
Local cooperation. Fully complied with for Coyote 
Valley Dam and channel improvements accomplished 
to date. For the Dry Creek portion, local interests are 
required by the authorizing act to comply with the usual 
a., b., c. requirements for channel improvements and, 
in addition, prevent any encroachment in the channel of 
Dry Creek which would interfere with proper 
functioning of the channel improvement works; adjust 
all claims concerning water rights arising from the 
construction and operation of the improvements, 
including acquisition of water rights needed for 
preservation of fish and wildlife resources affected by 
the project; and reimburse the United States in 
accordance with the Water Supply Act of 1958, as 
amended, for that part of the construction cost, (27.8% 
of total construction cost, currently estimated at 
$104,020,000) and the annual operation, maintenance, 
and replacement costs allocated to municipal and 
industrial water supply, tentatively estimated at 
$460,000. The estimated annual cost to local interests 
for maintenance of channel improvement works is 
$80,000. Sonoma County Water Agency (formerly 
Sonoma County Flood Control and Water Conservation 
District) provided assurances of willingness and ability 
to meet requirements by Resolutions No. DR 00793-1, 
September 25, 1961, No. DR 4770-1, December 17, 
1962, and No. DR 45759, August 5, 1974, for Dry 
Creek (Warm Springs) Lake and Channel. By letter 
dated March 7, 1967, Sonoma County Flood Control 
and Water Conservation District further indicated their 
interest in optimization of the Dry Creek (Warm 
Springs) damsite to provide additional water supply 
storage. Reimbursement to the United States for Dry 
Creek (Warm Springs) Lake and Channel costs 
allocated to 212,000 acre-feet of water supply storage is 
specified in a water supply contract with the local 
sponsor approved in October 1982. Local interests have 
expended approximately $1,000,000 to provide partial 
flood protection in project area and have constructed 
facilities at an approximate cost of $20,000,000 to 
distribute water from the completed Coyote Valley 
reservoir. 
Operations and results during fiscal year. New 
work: Coyote Valley Dam: None. Dry Creek (Warm 
Springs) Lake and Channel: Engineering activities 
continued. Major items of contract work included: 
Continuation of Rockpile Road Upgrade, $801,284; 
physical completion of Yorty Creek Beach, $236,771; 
initiation and physical completion of remedial work at 
Buzzard Rock (now known as Liberty Glen) camping 
area, $141,488; continuation of downstream channel 
improvements, Phase III, $209,444; and initiation of 
downstream recreation area, $138,894. Maintenance: 
Coyote Valley Dam: Operation and maintenance 
continued. Structures were maintained in serviceable 
condition. Runoff of East Fork Russian River at Coyote 
Dam was near normal for the year. Maximum storage of 
93,000 acre-feet occurred on March 18, 1989. 
Maximum bihourly inflow to reservoir was 4,900 cubic 
feet per second on March 18, 1989. Maximum release 
of 2,200 cubic feet per second occurred on March 6, 
1989. During the year, 113,800 acre-feet was released 
for flood control, and 96,000 acre-feet was released for 
irrigation and other purposes. Dry Creek (Warm 
Springs) Lake and Channel: Operation and maintenance 
continued. Structures were maintained in 
serviceable condition. Runoff of Dry Creek at Warm 
Springs Dam was below normal for the year. Maximum 
storage of 193,900 acre-feet occurred April 9, 1989. 
Maximum bihourly inflow to reservoir was 6,800 cubic 
feet per second on March 18, 1989. Maximum release 
of 400 cubic feet per second occurred October 5, 1988. 
During the year, 68,000 acre-feet was released for 
irrigation and other purposes. Project prevented 
$50,000 in damages from FY 1989 rainfloods. 
Historical summary. Entire project, exclusive of 
recreation facilities at completed project (Lake 
Mendocino), is about 96 percent complete. Coyote 
Valley Dam, initiated November 1958, was completed 
April 1959 (cost $17,550,000, of which $11,952,000 
was Federal; and $5,598,000 contributed). Work, 
including removal of slides resulting from storms in 
1958, was completed April 1959. Bank stabilization 
work on Russian River near Geyserville was completed 
in 1957 and channel improvements in remaining 
reaches on Russian River and East Fork of Russian River 
were completed in 1974 (cost $2,483,900). In April 
1982, responsibility was transferred to the Sacramento 
District. 
35-16

SACRAMENTO, CA, DISTRICT 
Warm Springs construction completions include fish 
hatchery in December 1980, reservoir clearing in July 
1981, project overlook in May 1981, downstream 
stabilization sills in October 1981, dam closure in 
October 1982, spillway repair at Warm Springs Dam in 
September 1985, and boat launching facilities, Phase I, 
in September 1985. Initial filling of Warm Springs 
reservoir was commenced on November 1, 1984. Major 
items of work remaining include completion of 
upgrading Rockpile Road, minimal recreation facilities, 
boat ramp facilities, and vegetation management 
program with remaining boundary fencing. Responsibility 
for construction was transferred to Sacramento 
District in August 1983. Dam safety assurance studies 
were initiated at Coyote Valley Dam in fiscal year 1984. 
22. SACRAMENTO RIVER AND 
TRIBUTARIES, CA, FROM 
COLLINSVILLE TO SHASTA DAM 
Location. Rises in Trinity Mountains in 
north-central California, flows generally southerly 
about 374 miles and empties into Suisun Bay, an arm of 
San Francisco Bay at Collinsville, CA. Works covered 
by this improvement are on Sacramento River and 
tributaries from Collinsville to Shasta Dam, about mile 
312. Drainage area above Rio Vista is 26,500 square 
miles (See Geological Survey quadrangles of area for 
Sacramento River and Upper Butte Basin; Flournoy and 
Fruto quadrangles for Black Butte Lake; and Tuscan 
Buttes, Tehama, Redding, and Hooker quadrangles for 
Table Mountain Lake.) 
Existing project. Improvement of Sacramento River 
and tributaries, from Collinsville to Shasta Dam was 
authorized as a unit of a comprehensive plan for flood 
control and other related purposes in Sacramento River 
Basin. (a) Sacramento River and major and minor 
tributaries, for flood control purposes: Enlargement of 
existing levees on Sacramento River between vicinity of 
Moulton weir and Ord Bend; construction of new levees 
from present levee terminus to vicinity of Chico 
Landing; construction of a weir near Chico Landing, 
extension of Moulton weir, and construction of a bypass 
through Upper Butte Basin; construction of new levees 
in Lower Butte Basin; enlargement of existing levees in 
Sutter, Tisdale, Sacramento, and Yolo Bypasses; and 
levee construction and/or channel enlargement on 
following minor tributaries of Sacramento River: 
Antelope Creek; Chico and Mud Creeks and Sandy 
Gulch; Butte and Little Chico Creeks; Cherokee Canal; 
Elder Creek; Deer Creek (Tehama County); Thomes 
Creek; and Willow Creek. Improvement provides for 
about 155 miles of channel improvement and about 294 
miles of levees with an average height of 12 feet and a 
freeboard of 3 feet. Improvement also provides for 
revetment as required for protection of bypass levee 
slopes against erosion. Total first cost for project is 
$18,300,000 (October 1988), of which $11,900,000 is 
Federal, and $6,400,000 non-Federal for lands and 
damages, including relocations. (See table 35-N on 
project units classified and excluded from cost 
estimate.) (b) Sacramento River, Chico Landing to Red 
Bluff, CA: An extension of the existing Sacramento 
River Flood Control project which provides for 
construction of bank protection works and minor 
channel improvements as required on Sacramento River 
between Chico Landing and Red Bluff for flood control 
purposes. Estimated first cost (October 1987) for 
project work in Tehama, Butte, and Glenn Counties is 
$31,000,000, of which $25,700,000 is Federal cost and 
$5,300,000 non-Federal cost for lands and damages 
including relocations and cash contribution of 
$3,435,000. (c) Sacramento River, CA, Bank Protection 
Project: Includes initial phase covering 430,000 
lineal feet of bank protection and a second phase 
covering 405,000 lineal feet of bank protection under a 
long range program of bank protection, erosion control 
works, and setback levees at critical locations within 
limits of authorized or existing levees included in the 
Sacramento River Flood Control project to protect 
integrity of levee system for flood control purposes. 
Total estimated (October 1989) first cost for project is 
$140,800,000, (includes an allowance for estimated 
inflation through the construction period) of which 
$98,600,000 is Federal (including $2,460,000 for 
recreation facilities) and $42,200,000 non-Federal 
comprising for lands and damages including relocations 
and $24,660,000 required cash contribution toward first 
cost. Construction in (a), (b), and (c) above 
supplements program of levee improvements as 
accomplished pursuant to 1917 Flood Control Act, as 
amended by subsequent acts, including 1941 Flood 
Control Act, and which are reported by California 
Debris Commission under Sacramento River, CA, flood 
control. (d) Authorization also provided for Black Butte 
Lake. For description of completed project see Annual 
Report for 1975. Federal first cost for project is 
$14,508,820, including $475,507 for basic recreation 
facilities. For future non-Federal reimbursement, see 
Local cooperation paragraph. Federal cost for 
recreation facilities funded from Code 710 appropriations 
is $1,000,162. A concessionaire at Black Butte 
Marina provided public use facilities in accordance with 
lease agreement with the Secretary of the Army at an 
estimated cost to date of $87,000. (e) Authorization 
also provided for construction of Table Mountain (Iron 
Canyon) project, an earthfill dam on Sacramento River 
about 3 miles north of Red Bluff, CA. This project unit 
was deauthorized August 5, 1977. For details, see 
Annual Report for 1978. 
Local cooperation. (a) Sacramento River and major 
and minor tributaries: Sec. 3, Flood Control Act of June 
22, 1936, applies. Fully complied with for all work 
completed or under contract, and local interests 
indicated they will be able to fulfill requirements for 
remaining work as scheduled. Levee construction (107 
miles) total requirement for the "active" project has 
been completed, transferred to, and accepted by the 
State. (b) Sacramento River, Chico Landing to Red 
Bluff: Sec. 3, Flood Control Act of June 22, 1936, 
applies; local interests must also assume responsibility 
for flood plain zoning. Fully complied with for portions 
completed in Tehama, Butte, and Glenn Counties; 
35-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
completed work, bank protection at 36 sites, was 
transferred to and accepted by the State. (c) 
Sacramento River Bank Protection Project: Sec. 3, 
Flood Control Act of June 22, 1936, applies. Local 
interests must also contribute an amount in cash that, 
when added to costs of lands, easements, rights-of-way 
and utility modifications, equals one-third of cost of 
each unit of remedial work; this contribution is 
estimated (October 1989) at $24,660,000. Local 
interests fully complied with requirements for all work 
completed or under contract, and indicated they will be 
able to fulfill requirements for remaining work as 
scheduled. In addition, for reaches where local interests 
request bank stabilization in lieu of more feasible levee 
setbacks, local interests will contribute costs over and 
above costs of setbacks, and provide local contribution 
indicated above. Completed units transferred to and 
accepted by the State. (d) Black Butte Lake: None 
required for construction. Local interests must pay the 
portion of first cost and annual operation and 
maintenance costs allocated to the conservation 
functions of the project; these costs are estimated at 
39.9 percent of first cost and 40.2 percent of annual 
costs. From March 2, 1960, to October 22, 1970, 
contract between the Bureau of Reclamation and the 
State of California provided for repayment of irrigation 
storage costs; Bureau administered contract in accordance 
with reclamation law. Local interests paid a total 
of $77,205 for irrigation services during this period. 
Public Law 502, 91st Cong., 2d sess., October 23, 1970, 
provided that Black Butte project be financially 
integrated with the Central Valley project, coordinated 
operationally with other Central Valley project storage 
units by the Bureau under the Secretary of the Interior, 
and that dam and reservoir at Black Butte be physically 
operated and maintained by the Corps in a manner 
compatible with recreational use of the reservoir. 
Operations and results during fiscal year. New 
work: (a) Sacramento River and major and minor 
tributaries-Engineering activities continued. (b) Sacramento 
River Bank Protection Project-Engineering and 
design activities continued. (See table 35-0 for 
construction accomplished and contract costs.) (c) 
Sacramento River, Chico Landing to Red Bluff. 
Engineering activities continued. (d) Black Butte Lake, 
regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation activities 
continued. Structures were maintained in serviceable 
condition. Runoff above Black Butte Dam was below 
normal for the year. Maximum storage of 117,500 
acre-feet occurred May 1, 1989. Maximum bihourly 
inflow to Black Butte reservoir was 4,100 cubic feet per 
second on March 24, 1989, and maximum outflow of 
880 cubic feet per second occurred on May 12, 1989. 
During the year, 6,300 acre-feet was released for flood 
control and 121,200 acre-feet was released for 
irrigation and other purposes. (e) Table Mountain (Iron 
Canyon) Lake: None. 
Historical summary. (a) Sacramento River and 
major and minor tributaries (active portions): Construction 
was initiated in May 1949 on Deer Creek and Butte 
Creek units; Cherokee Canal, Elder Creek, Chico and 
Mud Creeks, and Sandy Gulch units have been 
completed. Active portion of this improvement is about 
99 percent complete. Work remaining is bypass levee 
revetment as required. (b) Sacramento River Bank 
Protection Project: Construction of first unit was 
initiated in June 1963; initial phase of project was 
completed in November 1974. Phase II is underway, 
and overall project is about 90 percent complete. (c) 
Sacramento River, Chico Landing to Red Bluff: Active 
portion of project, bank protection in Tehama County, 
was initiated in June 1963 and completed in March 
1964. Project was reopened in June 1968 to place 
additional necessary bank protection. Work at 36 sites 
was completed in Tehama, Butte, and Glenn Counties 
as of September 1985 and transferred to State for 
maintenance. Bank protection on Sacramento River, 
Tehama County-one site, mile 215, (Unit 5), was 
completed November 1982, two sites, mile 209.5 and 
mile 217.5, (Unit 6), were completed in November 
1983, and four sites, 241.0, 237.9, 237.7, and 237.5 
(Unit 7) were completed in February 1985. (d) Black 
Butte Lake: Construction began in March 1960 and 
project is complete. Final land acquisition was 
completed in December 1966. Construction of main 
dam was initiated in June 1960 and completed in 
December 1963. Dam has been operating since 
November 1962 to provide the flood protection for 
which it was designed. Final cost allocation approved 
May 3, 1977. Dam safety assurance studies were 
initiated in FY 1980 and completed in FY 1986. 
Piezometer installation and slope for protection at the 
dam were completed in FY 1983. A cultural resources 
survey was completed in FY 1984. (e) Table Mountain 
(Iron Canyon) Lake: Project unit deauthorized as of 
August 5, 1977. 
23. WALNUT CREEK, CA 
Location. Project is on Walnut Creek and lower 
reaches of its principal tributaries, Pacheco, Grayson, 
San Ramon, Las Trampas, Galindo, and Pine Creeks in 
Contra Costa County, CA. Improvement will extend 
from Suisun Bay to head of project about 1 mile above 
southern limits of city of Walnut Creek. City of Walnut 
Creek is about 10 miles south of Suisun Bay. (See 
Geological Survey quadrangles for area.)Lower San 
Luis Rey River Valley along San Luis Rey. 
Existing project. Comprises extension of existing 
levees, construction of new levees and concrete 
channels, channel rectification and enlargement, and 
utilization of improvements constructed or planned by 
local interests. Plan provides for about 21.8 miles of 
channel improvement, two reinforced-concrete drop 
structures, two stilling basins, and 13.8 miles of levees. 
Cost estimate (October 1989) is $94,100,000 (includes 
an allowance for estimated inflation through the 
construction period), of which $67,900,000 is Federal 
cost and $26,200,000 is non-Federal cost (includes 
$20,625,000 for lands and damages and relocations 
except railroad facilities, and $5,575,000 required cash 
contribution for land enhancement benefits provided by 
the project). Local interests have expended about $3 
35-18

SACRAMENTO, CA, DISTRICT 
million for flood control in the project area during the 
period 1955-1965, including the concrete conduits 
constructed through the city of Walnut Creek at an 
estimated cost of $1,000,000 considered a preproject 
condition to be incorporated in the Corps project. In 
addition, local developers have made channel improvements 
for Upper Pine Creek valued at $5,050,000. The 
cost thereof is not included in above costs of local 
cooperation. Improvement adopted by 1960 Flood 
Control Act (H. Doc. 76, 86th Cong., 1st sess., contains 
latest published map). 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936, applies, except that relocation of 
railroad facilities is a Federal responsibility. In addition, 
local interests must make a cash contribution to the 
United States, in amount of 7.4 percent of cost of 
construction for land enhancement benefits provided by 
project. Cash contribution is estimated (October 1989) 
at $5,575,000. Local interests are represented by 
Contra Costa County Flood Control and Water 
Conservation District; formal assurances, including 
evidence of financial and legal ability to fulfill 
requirement for the cash contribution, were accepted by 
the Sacramento District Engineer on November 15, 
1963. The Flood Control District furnished all 
rights-of-way required to date and indicated that it will 
furnish all requirements as needed for future 
construction. The Flood Control District will arrange for 
highway bridge modifications and utility relocations 
before start of work by the Corps contractor. Payment 
of required contributed funds will be made in 
installments in amounts equal to 7.4 percent of the 
estimated construction expenditure for each fiscal year. 
Flood Control District and city of Walnut Creek have 
requested that recreation be added as a project purpose 
and will share costs in accordance with Water Resources 
Development Act of 1986. To date, $4,755,081 has 
been furnished. 
Operations and results during fiscal year. New 
work: Engineering and design for the uncompleted 
portions of Walnut and San Ramon Creeks and upper 
Pine Creek is continuing. Construction on San Ramon 
Bypass Channel has been split into three contracts. 
Contract No. 1 had no costs in fiscal year 1989 due to 
review of contractor (Lionsgate) claims and court 
action. Claims were heard before Board of Contract 
Appeals. Final decision is pending. Contract No. 2 was 
continued at fiscal year contract cost of $1,108,578. 
Contract No. 3 was awarded on September 27, 1989. 
Construction on Upper Pine Channel was continued at a 
fiscal year contract cost of 645,736. 
Historical summary. Construction was initiated 
June 1964; project is about 90 percent complete. Total 
of 16.7 miles of channel improvement, 9.2 miles of 
levee construction, part of channel improvement 
landscaping, and Drop Structures No. 1 and 2 have 
been transferred to local interests for operation and 
muaintenance. Planning and design continued on 
rmaining reaches. Work remaining consists of channel 
improvement on Walnut Creek and San Ramon bypass 
(Ygnacio Valley Road to Rudgear Road along SPRR 
alignment) and upper Pine Creek. 
Construction responsibility was transferred from San 
Francisco District on April 1, 1982. 
24. WILDCAT AND SAN PABLO 
CREEKS, CA 
Location. Project is located in vicinity of San Pablo 
and Richmond, Contra Costa County, CA, about 20 
miles northeast of San Francisco, CA. 
Existing project. Current plan of improvement 
consists of 16,700 lineal feet of channel improvements 
on Wildcat Creek and 11,700 lineal feet of channel 
improvements on San Pablo Creek. Improvements 
include channel deepening, levees, stilling basins, and 
flow control weirs. Additionally, about 32 acres will be 
planted for mitigation of fish and wildlife. Approved 
estimated cost of new work (1989) is $41,700,000 
(includes an allowance for estimated inflation through 
the construction period), of which $25,400,000 is 
Federal cost, and $16,300,000 is non-Federal cost 
(includes $1,350,000 cash contribution). Improvements 
adopted by House and Senate Public Works 
Committee Resolutions June 9 and 15, 1976, 
respectively, under provisions of sec. 201 of Flood 
Control Act of 1965 (H. Doc. 511, 94th Cong., 2d 
sess., contains latest published map).For details on 
units, see Annual Report for 1968. 
Local cooperation. In accordance with cost sharing 
and financing concepts reflected in the Water Resources 
Development Act of 1986, local interests are required to 
provide lands, easements, rights of way, and dredged 
material disposal areas; modify or relocate buildings, 
utilities, roads, bridges (except railroad bridges), and 
other facilities, where necessary in the construction of 
project; pay one-half of the separable costs allocated to 
recreation and bear all costs of operation, maintenance, 
and replacement of recreation facilities; pay 5 percent 
of the costs allocated to flood control and bear all costs 
of operation, maintenance, and replacement of flood 
control facilities. Local interests have agreed to make 
all required payments concurrently with project 
construction. The Board of Supervisors of Contra Costa 
County by Resolution 73-466, June 25, 1973, agreed to 
assume obligations of local cooperation. On November 
9, 1976, the Board reaffirmed sponsorship by 
Resolution 76-960. Contra Costa County Flood Control 
and Water Conservation District Board of Supervisors 
formed an Assessment District, August 3, 1982, which 
assures availability of funds for local share of 
non-Federal portion of project costs for a modified plan 
of improvement. A flood control Local Cooperation 
Agreement satisfying all requirements of sec. 221, 
Flood Control Act of 1970 (Public Law 91-661) and 
consistent with the Water Resources Development Act 
of 1986 (Public Law 99-662), was executed on June 20, 
1986 between the Department of the Army and the 
Contra Costa County Flood Control and Water 
Conservation District. By Resolution No. 1985-12-351, 
adopted December 17, 1985, the East Bay Regional 
35-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Park and Recreation District stated support for 
development of trail and recreational improvements for 
the project and indicated its intent to share in 50 
percent of the cost of such improvements and perform 
operation and maintenance responsibility. A recreation 
Local Cooperation Agreement will be required prior to 
initiation of that construction. 
Operations and results during fiscal year. 
Construction on Reach 1, Contract 1, of channel 
improvement on Wildcat Creek was continued at a fiscal 
year contract cost of $1,831,558. Construction on 
Reach 1, Contract 2 was initiated at a fiscal year 
contract cost of $57,823. 
Historical summary. Local interests withdrew 
support of project in 1979. Project responsibility was 
transferred from San Francisco District on April 1, 
1982. After 1982-1983 floods, local interests again 
indicated support of the project, and in October 1983, 
project work was resumed by Sacramento District. A 
revised final environmental impact statement was filed 
March 28, 1986, and a General Design Memorandum 
was approved May 29, 1986. Flood Control Local 
Cooperation Agreement was executed June 20, 1986. 
Overall project is about 55 percent complete. 
25. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and maintenance 
of flood control works, part 208, title 33, Code of 
Federal Regulations, provide for inspection of completed 
projects transferred to local interests for 
operation and maintenance to determine status of 
project and insure compliance with regulations. During 
fiscal year, inspections were made of: Completed unit of 
Fairfield Vicinity Streams; completed units of Sacramento 
River and major and minor tributaries; 
completed units of Sacramento River, Chico Landing to 
Red Bluff; completed units of Sacramento River flood 
control project, Kings River Channel Improvement 
(Pine Flat Lake project), and Walnut Creek project; 
American River levees; Merced County Stream group; 
Middle Creek (Lake County); Chester, North Fork 
Feather River; levee and channel improvements on 
Chowchilla River (Buchanan project) and Fresno River 
(Hidden project); Duck Creek diversion, Green Valley 
Creek, Littlejohn Creek, Mormon Slough, Bear Creek, 
Kern River-California Aqueduct Intertie, and North 
Fork, Pit River at Alturas, all in California; Truckee 
River, CA and NV; completed units of lower San 
Joaquin River and tributaries, CA; completed units of 
Red Bank and Fancher Creeks including Big Dry Creek 
Dam and diversion, CA; Reese River, Battle Mountain, 
NV; Sevier River, Redmond and vicinity, Jordan River, 
Big Wash near Milford, and Kays Creek, all in Utah; 
various emergency flood control works under authority 
of sec. 208, Flood Control Act of June 30, 1948, and 
September 3, 1954; Public Law 99, June 28, 1955, and 
antecedent legislation; and sec. 14 of Flood Control Act 
of July 24, 1946. Maintenance inspections conducted 
indicate that existing agreements and regulations are 
being complied with on completed flood control works. 
Continuing effort is required to improve maintenance 
practices and active steps are being taken by responsible 
State and local agencies to achieve desired results. Local 
agencies were advised, as necessary, of measures 
required to maintain these projects in accordance with 
standards prescribed by regulations. Total cost of 
inspection for fiscal year of $1,422,785 included 
continuation of dam safety assurance program for 
Folsom Lake, CA ($664,119). 
26. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to sec. 205, 
Public Law 858, 80th Congress, as amended 
(Preauthorization). 
Costs for preauthorization studies for fiscal year were 
$218,558. See Table 35-P for list of studies. 
Emergency flood control activities-repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Cong., and antecedent legislation). 
Federal cost for fiscal year was $370,309, all of 
which was for disaster preparedness. 
Emergency bank protection (sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.). 
Federal cost for fiscal year was $37,293. Bank 
protection was continued on Duchesne River, UT 
($5,813) and on Spanish Creek, CA ($16,067) and was 
completed on Green River, Lincoln County, WY 
($2,120) and Spring Creek near Springville, UT 
($13,293). 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (sec. 208, 1954 
Flood Control Act, Public Law 780, 83d Cong.). 
No snagging and clearing activities this fiscal year. 
Flood insurance activities (sec. 1301-1377, 1968 
Housing and Urban Development Act, Public Law 
90-448 as amended). 
In coordination with flood control activities, five 
flood insurance studies were initiated, four flood 
insurance studies were continued, and five flood 
insurance studies were completed in accordance with 
the Inter-Agency Agreements EMW-E-2226, 2549, 
2768 and 2994, respectively, at a fiscal year cost of 
$157,676 under Federal Emergency Management 
Agency reimbursable order. 
27. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with sec. 7, Flood Control Act of 
1944, summaries of monthly reservoir operations at Big 
Dry Creek, Boca, Camanche, Del Valle, Folsom, Friant 
(Millerton Lake), Indian Valley, Los Banos Detention, 
35-20

SACRAMENTO, CA, DISTRICT 
New Bullards Bar, New Don Pedro, New Exchequer 
(Lake McClure), New Melones, Oroville, Prosser, 
Shasta, and Stampede, CA; East Canyon, Echo, Lost 
Creek, Pineview, Starvation, and Wanship, UT; and 
Blue Mesa, Lemon, Paonia, and Vallecito, CO, were 
prepared. Work was completed on Oroville, Starvation 
and McPhee water control manuals. Draft water control 
manual revisions were started and essentially completed 
on Don Pedro reservoir. Work was initiated on the new 
Ridgeway and Red Fleet reservoir manuals. Corps 
personnel provided advice as requested during flood 
control operations at all sec. 7 reservoirs. Fiscal year 
cost was $688,817. Total cost to September 30, 1989, 
was $4,329,783. 
Multiple-Purpose Projects including Power 
28. NEW MELONES LAKE, CA 
Location. On Stanislaus River about three-quarters 
mile downstream from existing Melones Dam and about 
35 miles northeast of city of Modesto. (See Geological 
Survey quadrangles of the area.). 
Existing project. Provides for construction of (a) an 
earth and rockfill dam about 625 feet high to create a 
reservoir with gross storage capacity of about 2,400,000 
acre-feet for flood control, irrigation, power, general 
recreation, fish and wildlife, and other purposes, and 
(b) a powerplant below the dam with an installed 
capacity of 300,000 kilowatts. Upon completion of 
construction of dam and powerplant by the Corps, the 
project became an integral part of Central Valley project 
and is being operated and maintained by the Secretary 
of the Interior pursuant to Federal reclamation laws, 
except that the flood control operation of the project 
shall be in accordance with rules and regulations 
prescribed by the Secretary of the Army. Maintenance 
of Stanislaus River channel from Goodwin Dam to San 
Joaquin River to a capacity of at least 8,000 cubic feet 
per second will also be Corps responsibility. Approved 
estimated (October 1989) Federal cost is $394,500,000 
(includes an allowance for estimated inflation through 
the construction period). For future non-Federal 
reimbursement, see Local cooperation paragraph. In 
addition, local interests expended $300,000 for levees 
along lower reaches of Stanislaus River. Existing project 
was adopted by 1962 Flood Control Act (H. Doc. 453, 
87th Cong., 2d sess., contains latest published map). 
This act modified original authorization adopted by 
1944 Flood Control Act. (H. Flood Control Committee 
Doc. 2, 78th Cong., 2d sess., contains latest published 
map.) The 1944 Flood Control act established $8 
million monetary limitation for partial accomplishment 
of project. Further monetary authorizations of $2.5 
million, $5 million, $13 million, $2 million, $17 million, 
$18 million, $44 million, $83 million, $46 million, $6 
million, and $61 million were provided for this project 
by Public Laws 235 and 780, 83d Cong., and 85-500, 
90-17, 90-483, 91-282, 92-222, 93-251, 94-397, 
95-104, and 95-189, making a total monetary 
authorization of $305,500,000 available for the basin 
plan comprising Lower San Joaquin River and 
tributaries, including Tuolumne and Stanislaus Rivers, 
CA. Since FY 1979, appropriations have not been 
subject to the river basin monetary limitation. 
Local cooperation. Based on approved preliminary 
cost allocation studies (July 1965) local interests will be 
required to pay 35.2 percent of first cost and 12.7 
percent of annual operation and maintenance costs 
allocated to irrigation. In addition, 31.1 percent of first 
cost and 62.5 percent of annual cost would be allocated 
to power. Local interests must also maintain existing 
private levees along Stanislaus River from Goodwin 
Dam to San Joaquin River and prevent encroachment 
on channel and floodway between levees to preserve 
safe carrying capacity throughout the reach of at least 
8,000 cubic feet per second. Recovery of costs allocated 
to irrigation and power will be the responsibility of the 
Bureau of Reclamation. Reimbursement of costs will be 
in accordance with Bureau policies and procedures for 
the Central Valley project. State of California officially 
adopted project by chapter 918 of statutes of 1963, and 
by chapter 1438 of those statutes authorized State 
Reclamation Board to furnish required assurances. The 
Board, by letter dated December 13, 1963, stated it 
would furnish required assurances when formally 
requested to do so. Assurances were requested by letter 
of December 30, 1977. On October 2, 1979, the Board 
reaffirmed its intent to furnish the required assurances. 
On January 6, 1983, the Board provided formal 
assurances of local cooperation. 
Operations and results during fiscal year. New 
work: Engineering activities continued. Fiscal year costs 
for major items of work included: Continuation of land 
acquisition activities, $258,075; continuation of Glory 
Hole recreation area sanitary system contract, 
$1,030,411, and of two-mile bar recreation contract, 
$59,436; completion of Knights Ferry Covered Bridge, 
$243,113; and initiation of Peoria Mountain revegetation 
contract, $18,836. Maintenance: Maintenance 
and operation activities continued on Lower Stanislaus 
River. 
Historical summary. Construction was initiated in 
August 1966. Main dam contract which was awarded in 
March 1974 has been completed; dam dedication 
ceremonies were held July 14, 1979. Cultural resources 
preservation, water intake facilities, flood control and 
irrigation tailrace modification, reservoir area clearing, 
Tuttletown Phase I recreation area, Oakdale recreation, 
Glory Hole Phase I and Phase II recreation area, and 
operations access road contracts have all been 
completed. Glory Hole minimal recreation facilities 
contract has been completed. A boundary fencing 
contract, Lower Stanislaus Phase I and Phase II minimal 
recreation facilities contract, Lower Stanislaus Corporation 
Yard contract, and Lower Stanislaus Administration 
Building contract have been completed. Tuttletown 
minimal recreation facilities contract, McHenry recreation 
area contract, Tuttletown wastewater treatment 
contract, Knights Ferry recreation area contract, and 
Knights Ferry Covered Bridge contract have been 
completed. Overall project is nearing completion 
except for Lower Stanislaus River recreation facilities. 
35-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Remaining recreation facilities were unscheduled 
pending development of cost sharing agreements and/or 
specific Congressional appropriation of funds. A 
Memorandum of Understanding between the Department 
of the Interior and the Department of the Army 
transferring the New Melones dam and reservoir from 
the Corps of Engineers to the Bureau of Reclamation 
was executed on November 20, 1979. Agreement 
provides that the Corps complete land acquisition 
actions and retain budgeting, design, and construction 
responsibility for reservoir clearing and recreation 
development; completion of cultural resources mitigation 
in project area was vested in the Department of the 
Interior. The California State Water Resources Control 
Board's Decision 1422 of April 1973 established 
conditions which impacted on the planned filling and 
operation of the project by the Department of the 
Interior. As a result, the Department of Interior brought 
suit against the State of California claiming State 
limitations on project operation were contrary to 
Congressional intent and authority. The case was heard 
before the U.S. District Court in Fresno, CA, and in 
early March 1981, a Federal judge ruled that the 
Federal Government could fill the New Melones 
reservoir for purpose of generating electrical power, but 
not for agricultural or other purposes. Both the 
Government and the California State Resources 
Control Board appealed this decision to the 9th Circuit 
Court of Appeals in San Francisco, CA. 
On December 20, 1982, the Court upheld all 25 
requirements placed on the Federal Government by the 
State Water Resources Control Board. The decision 
reversed the lower court's decision to permit filling of 
the reservoir for generating electrical power. The 
Bureau of Reclamation subsequently filed for a permit 
from the State Water Resources Control Board to fill the 
reservoir. Permit was approved. The Bureau had 
originally started generating power on a limited basis on 
July 1, 1979; however, after the filling of the reservoir in 
spring of 1983, full power generating benefits have been 
attained. Project is about 99 percent complete. 
General Investigations 
29. SURVEYS 
Total fiscal year costs were $4,197,387, of which 
$2,501,895 was for flood damage prevention studies (in 
addition, $1,347,487 was expended from required cost 
contributions for feasibility cost shared studies and 
$8,709 was expended from other non-Federal 
contributions); $5,000 for coordination with Soil 
Conservation Service; $14,000 for coordination with 
Bureau of Reclamation pertaining to projects under 
reclamation program (including PL 984); $116,000 for 
special investigations; $44,000 for Intragency Water 
Resources Development; $33,000 for review of FERC 
licenses; and $127,296 for planning assistance to states 
($41,500, CA; $24,692, UT; $60,104, CO; and 
$1,000, WY). 
30. COLLECTION AND STUDY OF 
BASIC DATA 
Technical assistance was performed for other Federal 
agencies as well as non-Federal agencies in connection 
with Flood Plain Management Services Program at fiscal 
year costs of $456,934. No Flood Plain Information 
Studies were prepared after FY 1980. 
Fiscal year costs for hydrologic studies were $7,000. 
31. RESEARCH AND DEVELOPMENT 
The Hydrologic Engineering Center was designated as 
a separate Field Operating Agency as of January 1, 
1979, in accordance with OCE permanent orders 1-1, 
January 10, 1979, but Sacramento District is continuing 
to provide advisory and administrative support services 
to HEC as specified in local support agreement 
DACW05-79-A-0038 of March 1979. Fiscal year costs 
were $1,276,374, of which $427 was for planning 
methodologies, $842,883 was for analytical techniques, 
$99,990 for Water Source Interrelationships, $45,623 
for risk assessment for Corps dams, $65,893 for earth 
resources satellites, $51,097 for planning assistance to 
states; $168,649 for hydrologic manual preparation, 
and $1,812 for Construction Productivity Advancement 
Research (CPAR) Program, all at the Hydrologic 
Engineering Center. 
32. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
CACHE CREEK BASIN, CA 
Project is located on eastern slope of the Coast 
Range. Clear Lake unit is about 110 miles north of San 
Francisco and Settling unit is about 15 miles northwest 
of Sacramento. 
Plan of improvement consists of two project units: 
Upper basin at Clear Lake (selected plan)--widening 
and/or deepening 4.5 miles of existing 5 mile long Clear 
Lake outlet channel to a capacity of 8,000 cubic feet per 
second, and nonstructural measures; and lower basin at 
the mouth of Cache Creek--enlarging existing 
perimeter levees of Cache Creek Settling Basin an 
average of 12 feet to provide 50 years of sediment 
storage capacity and enlarging existing project levees 
from settling basin mouth upstream to County Road 
102, reconstructing and enlarging existing Cobble weir, 
degrading the existing training levees and rebuilding 
them adjacent to the western perimeter levee to allow 
utilization of entire basin for sediment deposition, 
acquiring easements for 3,600 acres of existing settling 
basin and establishing a wildlife refuge; however, the 
refuge feature was reclassified to deferred category on 
April 11, 1988. The second project unit-Cache Creek 
Settling Basin-is reported under Improvement No. 6. 
General Design Memorandum for the Clear Lake 
Outlet Channel (Upper Basin) was continued at a fiscal 
35-22

SACRAMENTO, CA, DISTRICT 
year cost of $356,768. Preconstruction planning 
estimate for the Outlet Works is $2,330,000. 
COTTONWOOD CREEK, CA 
Project will be located on main stem and the North, 
South, and Middle Forks of Cottonwood Creek on 
eastern slope of the Coast Range and southern slope of 
Trinity Range between cities of Redding and Red Bluff, 
CA, and was authorized by the 1970 Flood Control Act 
(Document not yet printed). 
Plan of improvement provides for two multiple-purpose 
reservoirs, one at Dutch Gulch (capacity 900,000 
acre-feet) and one at Tehama (capacity 700,000 
acre-feet), and includes base facilities for future 
installation of hydropower generating equipment. 
Advance Engineering and Design activities were 
essentially discontinued in FY 1985 as by the letter of 
June 25, 1985, the State of California indicated they 
could not financially participate in the project at this 
time. Final documentation of record of the Advance 
Engineering and Design studies was continued at a fiscal 
year cost of $38,738. 
COYOTE CREEK, CA (KNOWN AS 
COYOTE AND BERRYESSA CREEKS) 
Project is located in the cities of San Jose and Milpitas 
immediately south of San Francisco Bay in Santa Clara 
County, CA. 
Plan of improvement on Coyote Creek consists of 
overflow channels and offset levees. Improvement on 
Berryessa Creek includes two sedimentation basins at 
the upstream end of the concrete lined trapezoidal 
channel and offset levees. Combined plan would 
provide flood protection from Coyote and Berryessa 
Creeks to cities of San Jose and Milpitas, which include 
large industrial complexes and some residential 
development. 
Feasibility report (prepared by San Francisco 
District) was approved by Board of Engineers for Rivers 
and Harbors on March 31, 1988. Preconstruction 
engineering and design studies were continued by 
Sacramento District. Plan of Action was submitted on 
September 12, 1988. General Design Conference was 
held on September 28-29, 1988 in Milpitas. General 
Design Memorandums were initiated on Coyote and 
Berryessa Creeks. Estimated preconstruction planning 
cost is $2,000,000. 
TRUCKEE MEADOWS, NV 
Project is located in metropolitan area of Reno and 
Sparks in Washoe County, NV. 
Plan of improvement consists of about 7 miles of 
levees, 5 miles of floodwalls, 6 bridge replacements 
along Truckee River and includes limited channel 
excavation, a 900-acre detention basin, and backwater 
levees along Steamboat Creek, Boynton Slough, and the 
North Truckee Drain just north of the Interstate 
Highway 80 crossing. Plan also includes recreation 
facilities with bicycle and pedestrian paths, river 
overlooks, and picnic sites; mitigation measures (31 
acres of riparian plantings to replace vegetation losses); 
and fish and wildlife features. Project will provide flood 
protection from Truckee River to cities of Reno and 
Sparks and Truckee Meadows urban areas. 
Record of Decision was signed by Assistant Secretary 
of the Army on December 6, 1987. General Design 
Conference was held on July 12-13, 1988. General 
Design Memorandum was continued. Estimated 
preconstruction planning cost is $4,300,000. 
GUADALUPE RIVER, CA 
Project is located in the downtown area of San Jose in 
Santa Clara County, CA. 
Current plan of improvement includes widening and 
deepening one or both sides of Guadalupe River for 2.5 
miles from Interstate Highway 280 to Interstate Highway 
880 in downtown San Jose, CA, and consists of channel 
modifications with provisions for fish and wildlife 
mitigation. Project features include a 2,023-foot 
underground conduit bypass, a 2,495-foot concrete 
lined channel, a 9,129-foot earth trapezoidal channel 
lined with riprap, a one-sided widened channel, and 
mitigation plantings on the widened channel. Project is 
to provide 100-year flood protection from Guadalupe 
River to downtown San Jose, including approximately 
600 commercial businesses, 1,500 private residences, 4 
major traffic arteries, and the San Jose International 
Airport. 
General Design Memorandum was continued. 
Estimated preconstruction planning cost is $2,450,000. 
NAPA RIVER, CA 
Project is located in city and county of Napa, CA. 
Current plan of improvement for Napa River from 
Edgerley Island to Trancas Street consists of channel 
widening and realignment, dredging, bank protection, 
construction of concrete step-walls through city of 
Napa, and fish and wildlife mitigation and recreation. 
Current plan of improvement for Napa Creek includes a 
series of 5 concrete box culverts and extends from Napa 
River to Jefferson Street, a distance of 2,500 feet. 
Project will provide high level flood protection from 
Napa River and Napa Creek to city of Napa. 
Local sponsors have expressed interest in developing 
a reduced scope plan more suitable to their financial 
capability. Preliminary evaluations indicate reduced 
scope plan would probably be economically justified. 
General Design Conference was held on January 12, 
1989. Supplemental General Design Memorandum was 
initiated. Preconstruction planning cost is $5,000,000. 
35-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 33-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
1. Sacramento River 
CA 
(Contrib. Funds, 
Other) 
2. Sacramento River 
Deep Water Ship 
Channel, CA 
(Required Contrib. 
Funds) 
3. San Francisco Bay 
to Stockton, CA 
(John F. Baldwin 
and Stockton Ship 
Channels) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
$1,807,800 
1,841,271 
800,000 
649,054 
12,513,000 
12,140,776 
$3,973,000 
3,914,755 
85,000 
- 
- - $40,331,192 1 
- - 40,331,192 1 
$249,000 $150,700 43,296,331 2 
267,263 188,435 43,277,483 3 
- - 85,000 4 
400,000 1,200,000 1,400,000 
450,454 996,359 1,520,808 
- - 750,000 
- - 600,803 
3,853,474 5 
3,611,618 
750,000 
600,803 
3,137,000 2,547,000 1,676,000 54,816,000 6 
4,354,831 1,750,433 2,635,686 54,545,653 7 
4. San Joaquin New Work 
River, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Buchanan Dam- New Work 
H.V. Eastman Lake, Approp. 
Chowchilla River, Cost 
CA (Federal Maint. 
Funds) Approp. 
Cost 
(Contrib. Funds, New Work 
Other) Contrib. 
Cost 
6. Cache Creek New Work 
Settling Basin, CA Approp. 
Cost 
7. Calaveras River New Work 
and Littlejohn Approp. 
Creek and Trib- Cost 
utaries including Maint. 
New Hogan Lake Approp. 
& Farmington Dam, Cost 
CA (Federal Funds) 
(Contrib. Funds, New Work 
Other) Contrib. 
Cost 
5,833,117 8 
5,833,117 8 
20,000 
80,224 
778,000 92,500 48,500 12,866,476 9 
764,102 92,763 54,591 12,856,262 9 
- - - - 27,369,597 
- - - - 27,369,597 
853,000 1,150,000 1,306,500 1,224,800 10,407,800 
870,983 1,062,828 1,298,349 1,238,494 10,269,556 
- - - - 111,187 
- - - - 111,187 
217,000 
21,396 195,375/ 
10 
10 
217,000 
216,771 
- - - - 23,723,144 
S- - - 23,723,144 
1,124,000 1,740,300 1,515,200 1,779,600 18,177,269 
1,132,703 1,641,032 1,629,933 1,715,926 18,000,364 
20,000 
26,468 
4,000 
6,780 
11 
11 
12 
12 
1,398,251 13 14 15 
144 1,398,251 13 14 15 
8. Corte Madera 
Creek, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
2,374,000 
1,602,532 
-50,000 
41,977 
1,325,000 1,223,000 
1,869,610 310,625 
- 20,000 
11,109 4,052 
-800,000 12,006,725 
414,832 11,903,516 
- 186,095 
7,888 171,507 
35-24 
16 
16 
17 18 
17 18

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
(Contrib. Funds, 
Other) 
9. Fairfield Vicinity 
Streams, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
10. Hidden Dam - 
Hensley Lake, 
Fresno River, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
11. Isabella Lake, Kern 
River, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
12. Kaweah and Tule 
Rivers including 
Terminus Dam and 
Success Lake, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
13. Little Dell 
Lake, UT 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
14. Lower San Joaquin 
River, CA 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
270,000 
121,420 
905,000 
285,206 
874,000 
897,340 
- -20,000 
103,880 - 
582,000 3,892,000 
998,510 2,264,005 
- 27,000 
- 9,618 
200,000 620,000 
- 608,438 
2,939,000 
4,260,133 
9,000 
13,115 
1,886,000 
961,970 
786,921 19 
762,222 20 
9,480,000 
8,954,183 
36,000 
22,733 
2,706,000 21 
1,570,408 22 
- - - 30,555,426 
- - - 30,555,426 
918,000 1,102,800 1,126,100 11,005,400 
893,031 1,129,940 1,096,138 10,922,659 
- - - 165,112 23 
- - - 165,112 23 
2,426,000 3,882,598 
2,519,690 3,863,211 
- 20,000 
- 10,320 
1,893,000 
1,918,526 
135,000 
80,405 
2,164,000 
2,076,605 
105,000 
114,581 
- - 24,450,537 24 
- - 24,450,537 24 
1,810,000 2,145,000 31,277,596 25 26 
1,794,140 2,027,598 31,007,666 25 26 
80,000 105,000 643,000 27 
69,885 109,422 627,627 28 
2,180,700 
2,314,446 
185,000 
184,483 
1,335,000 2,500,000 1,750,000 
1,274,320 1,443,225 2,482,603 
- - 660,000 
- - 496,240 
300,000 3,260,000 710,000 
- 2,250,170 1,983,921 
448,000 
415,547 
- 34,997,230 29 
- 34,997,230 29 
2,125,600 27,443,825 30 
2,053,516 27,283,692 30 
51,000 538,420 31 32 34 
107,190 532,443 31 32 35 
7,025,000 15,419,900 
4,213,530 12,070,861 
2,840,000 3,500,000 
1,762,627 2,258,867 
50,465 4,320,465 36 
25,546 4,259,636 37 
900,000 100,000 -49,000 4,049,000 
132,867 197,045 450,299 3,767,200 
35-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
15. Martis Creek Lake, 
Martis Creek, NV, 
and CA 
16. Merced County 
Streams, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
17. Merced County 
Stream Group, CA 
18. Pajaro River Basin, 
CA (Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
19. Pine Flat Lake and 
Kings River, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
20. Redbank and 
Fancher Creeks, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
21. Russian River Basin, 
CA, Coyote Valley 
Coyote Valley Dam 
(Lake Mendocino) 
and Channel 
Improvements 
(Federal Funds) 
(Contrib. Funds, 
Other) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
- - - - 8,504,989 38 
- - - - 8,504,989 38 
252,000 272,000 283,000 266,100 4,519,450 
359,725 282,598 285,589 273,026 4,495,667 
180,000 450,000 100,000 3,602,000 
121,269 319,218 121,958 333,016 
- - - 2,582,500 
- - - 615,811 
81,000 
109,537 
20,000 
10,396 
10,702,000 
7,245,461 
2,582,500 
615,811 
- - - 2,751,259 
- - - 2,751,259 
113,000 107,000 117,000 1,777,506 
118,837 104,771 122,833 1,762,468 
480,000 
101,162 
61,000 
650 
21,000 
1,622,000 
673,441 
549,000 
102,234 
16,250 
25,890 
2,713,000 
237,189 
127,268 
5,663 
39 
39 
40 
40 
7,084,968 41 
3,271,768 41 
610,000 
230,152 
37,250 42 
31,553 42 
- - - 43,356,265 43 44 45 
- - - 43,356,265 43 44 45 
1,492,000 1,395,000 2,054,500 1,387,000 23,084,785 46 
1,464,946 1,365,827 2,042,413 1,450,874 22,993,298 46 
- - - 110,000 47 
- - - 110,000 47 
820,000 
813,805 
685,000 
468,756 
10,000 
1,100,000 
908,733 
250,000 
138,073 
4,053,000 
1,101,483 
202,500 
124,396 
6,687,065 48 
3,292,766 48 
462,500 
262,469 
- - - 14,435,869 49 
S- - - 14,435,869 49 
2,542,000 3,467,102 1,778,000 1,646,600 29,580,777 50 51 
2,518,357 3,445,754 1,755,996 1,614,367 29,390,626 50 51 
78,411 
66,758 
5,000 
21,290 
5,000 
3,825 
2,000 
430 
245,411 52 
242,612 53 
35-26

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
Dry Creek (Warm 
Springs) Lake 
and Channel 
Improvements, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
22. Sacramento River 
and Tributaries, CA 
from Collinsville to 
Shasta Dam 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
23. Walnut Creek, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
24. Wildcat and San 
Pablo Creeks, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
28. Lower San 
Joaquin River 
and Tributaries, 
CA including 
and Stanislaus 
Tuolumne Rivers, 
CA, New Melones 
Lake, CA 
(Federal Funds) 
Contrib. Funds, 
Other) 
New Work. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
8,615,000 
8,878,305 
1,772,000 
1,758,290 
3,381 
4,042,500 
3,921,536 
941,000 
1,011,304 
1,600,000 
923,511 
90,000 
101,299 
4,591,000 
3,667,875 
710,000 
641,386 
-210,000 
-232,098 
12,670,000 
8,577,136 
1,962,000 
1,864,917 
55,000 
60,698 
7,574,000 
6,714,273 
2,058,000 
2,007,449 
400,000 
969,483 
100,000 
78,785 
7,700,000 
6,049,719 
1,026,834 
625,832 
2,323,166 
1,672,179 
526,000 2,800,000 
404,415 2,606,849 
160,000 15,158 
- 140,472 
150,000 265,000 
- 302,467 
5,719,000 
2,855,897 
550,200 
529,709 
6,830,000 
7,915,389 
593,000 
608,037 
6,600,000 
9,292,267 
2,307,000 
2,378,477 
73,000 
57,926 
9,216,000 
7,968,616 
1,123,500 
1,136,243 
2,476,000 
609,953 
40,000 
62,582 
3,935,000 
6,398,725 
130,000 
474,213 
3,674,950 
3,858,569 
4,661,000 
1,104,454 
575,000 
71,359 
260,000 
184,140 
4,664,000 
3,312,754 
637,000 
620,542 
8,099 
1,900,000 
2,701,746 
2,244,700 
2,254,939 
20,000 
31,714 
4,450,000 
5,634,386 
1,242,100 
1,183,415 
1,210,000 
1,921,720 
15,000 
17,604 
4,400,000 
2,544,540 
260,000 
238,792 
1,958,714 
1,513,579 
1,621,000 
2,515,019 
-190,000 
150,107 
465,000 
528,470 
2,500,000 
2,039,696 
602,400 
600,157 
314,619,645 54 
312,791,058 54 
13,714,700 5 
13,543,958 56 
208,000 57 
194,119 58 
113,883,008 s9 60 
112,599,522 so so60 
17,300,934 61 
17,135,881 61 
22,641,538 
21,285,013 
2,806,362 62 63 
2,806,324 62 63 64 
59,482,430 65 
57,142,620 66 
4,755,081 67 
4,584,949 68 
10,831,901 69 
9,833,556 69 
11,538,000 
8,413,485 
550,158 
361,939 
1,150,000 70 
1,015,077 71 
361,150,996 72 
356,950,762 73 
4,742,600 
4,687,815 
80,000 74 
12,585 76 
35-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
1. Includes the following amounts for new work: 
Regular funds: Previous project, $185,198; existing 
project, $585,436 for shallow-draft and $39,560,558 
for deep-draft. 
2. Includes the following funds for maintenance: 
Regular funds: Previous project, $553,720; existing 
project, $15,786,207 for shallow-draft and 
$26,886,404 for deep-draft; and deferred maintenance 
funds, $70,000 for shallow-draft. 
3. Includes the following costs for maintenance: 
Regular funds: Previous project, $553,720; existing 
project, $15,726,304 for shallow-draft and 
$26,927,459 for deep-draft; and deferred maintenance 
funds, $70,000 for shallow-draft. 
4. Includes $85,000 contributed funds, other, 
from Sacramento-Yolo Port District for clearing and 
grubbing on dredged material deposit areas to be used 
on ship channel maintenance dredging work. 
5. Includes unobligated carryover for continuation 
of planning and engineering (CP&E) funds as of 
September 30, 1985 ($33,474) for Sacramento River 
Deep Water Ship Channel to be included in project cost 
(for cost sharing) per TWX of September 9, 1985. 
6. Includes $25,804,800 funds for Sacramento 
District and $29,011,200 for San Francisco District. 
7. Includes $25,617,184 funds for Sacramento 
District and $28,928,468 for San Francisco District. 
8. Includes $1,158,348 public work funds, of 
which $207,198 was for work done along 30-foot 
channel in Suisun Bay Channel; excludes $19,000 
expended for engineering for inactive portion of 1950 
modification. In addition, $1,342,500 was expended 
from required contributed funds. 
9. In addition, $1,250 was expended from 
required contributed funds. 
10. Contributed funds, other, from State of 
California for design and construction of downstream 
channel improvements on Ash and Berenda Sloughs 
below Buchanan Dam. 
11. Includes Code 710 funds and costs for 
recreation facilities at New Hogan Lake: Total to date 
$897,742. 
12. Includes $99,000 special recreation use fees 
and costs at New Hogan Lake, and $195,000 
maintenance and operation of dam funds and costs 
(96X5125) at New Hogan Lake beginning in FY 1988. 
13. For miscellaneous construction under local 
cooperation requirements, primarily Bear Creek, San 
Joaquin County; includes $108,056 as related to Duck 
and Littlejohn Creeks channel improvements as part of 
Farmington Dam project unit. 
14. Includes $393,195 contributed funds, other, 
from California Department of Boating and Waterways 
for design and construction of boat launching and 
related facilities, and $30,000 for design and 
construction of a boarding float at North Shore 
recreation area at New Hogan Lake. 
15. Includes $104,000 contributed funds, other, 
from Calaveras County Water District for New Hogan 
hydropower studies. 
16. Includes $6,999,725 San Francisco District 
construction funds and costs for Corte Madera Creek. 
17. $8,695 contributed funds transferred to 
Sacramento District in FY 1983. 
18. Includes $97,400 San Francisco District 
required contributed funds and costs. 
19. Contributed funds, other, from Marin County 
including $536,921 for miscellaneous bridge and road 
relocations and $250,000 for additional expenses for 
disposal sites at Corte Madera Creek. 
20. Contributed funds, other, costs including 
$536,921 for miscellaneous bridge and road relocations 
and $225,300 for additional expenses for disposal sites 
at Corte Madera Creek. 
21. Includes $2,685,000 contributed funds, other, 
from State of California for relocations (automotive type 
bridges) at Laurel Creek Diversion near Fairfield, and 
$21,000 from City of Fairfield for Phase III contract for 
channel development on Laurel Creek. 
22. Includes $952,734 contributed funds, other, 
costs from State of California for relocations at Laurel 
Creek Diversion and $9,236 contributed funds, other, 
costs from City of Fairfield for Phase III contract. 
23. Contributed funds, other, from State of 
California for miscellaneous design and construction at 
Hidden Dam. 
24. Includes $2,199,085 Code 710 funds and costs 
for recreation facilities at Isabella Lake, and $224,000 
Code 713 funds and costs for improvement at Tillie 
Creek and Live Oak campgrounds. 
25. Includes $407,640 special recreation use fees 
and costs at Isabella Lake. 
26. Includes $131,900 maintenance and operation 
of dam funds and costs (96X5125) at Isabella Lake 
beginning in FY 1985. 
27. Includes $438,000 contributed funds, other, 
from California Department of Boating and Waterways 
for design and construction of boat launching and 
related facilities at Old Isabella Road and Isabella 
Peninsula and $205,000 for Isabella Dam hydropower 
studies. 
28. Includes $189,627 contributed funds, other, 
costs for Isabella Dam hydropower studies. 
29. Includes Code 710 funds and costs for 
recreation facilities: Success Lake: Total to date 
$747,048. Terminus Dam: Total to date $704,000. 
30. Includes $165,000 special recreation use fees 
and costs at Success Lake. 
31. Contributed funds, other, from the State of 
California Department of Boating and Waterways and 
costs for acquisition of a boarding float at Success Lake, 
$30,000 and at Terminus Dam, $12,420. 
32. Includes $346,000 contributed funds, other, 
from the Kaweah River Power Authority, Visalia, CA, 
for Terminus Dam hydropower studies. 
33. Includes $341,411 contributed funds, other, 
costs for Terminus Dam hydropower studies. 
34. Includes $150,000 contributed funds, other, 
from DITT Inc., Paris, France, for hydropower studies 
at Success Lake. 
35. Includes $148,612 contributed funds, other, 
costs for Success Lake hydropower studies. 
36. Includes $4,320,465 contributed funds, from 
the Metropolitan Water District of Salt Lake City for 
relocation of State Highway 65 at Little Dell Lake. 
35-28

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
37. Includes $4,259,636 contributed funds, other, 
costs for relocation of State Highway 65 at Little Dell 
Lake. 
38. Includes $1,200, initiation of the plans and 
specifications for Code 710 recreation facilities, for FY 
1978. Construction of recreation facilities at Martis 
Creek Lake under Code 710 was determined to be 
infeasible. 
39. Includes contributed funds, other, for lands, 
easements and rights-of-way for Castle Dam from State 
of California. 
40. In addition, $66,532 expended for new work 
from contributed funds, other, for miscellaneous 
construction under local cooperation requirements as 
related to acquisition of rights-of-way and utility 
alterations for Merced County Stream Group. 
41. Includes $1,949,968 San Francisco 
construction funds and costs and $260,000 Sacramento 
general investigation funds and costs for Pajaro River. 
42. Includes $37,250 contributed funds, other, 
from Santa Clara Valley Water District for bridge 
relocation at Pajaro River. 
43. Includes Code 710 funds and costs for 
recreation facilities at Pine Flat Lake: Total to date 
$1,595,100. 
44. Includes Public Works Acceleration, Executive 
(PL 87-658) (Transfer to Corps of Engineers, Civil) 
1963 funds and costs ($239,235) for recreation 
facilities. 
45. Includes $19,600 Code 713 funds and costs for 
Pine Flat fish barrier. 
46. Includes $158,300 special recreation use fees 
and costs at Pine Flat Lake, and $188,785 maintenance 
and operation of dam funds and costs at Pine Flat Dam. 
47. Miscellaneous construction and engineering 
and design services (non-project) accomplished at 
expense of State of California under local cooperation 
requirements in connection with acquisition of 
rights-of-way and utility alterations at Pine Flat Lake. 
48. Includes the unobligated carryover for 
continuation of planning and engineering (CP&E) funds 
as of September 30, 1985 ($29,065) and FY 1986 
allocation for Redbank and Fancher Creeks to be 
included in project costs (for cost sharing) per TWX of 
September 9, 1985. 
49. Excludes $5,598,000 contributed funds; 
$400,000 for recreation facilities at completed projects 
funded under Public Works Acceleration Program; and 
$1,628,411 for recreation facilities at completed 
projects funded under Code 711 at Coyote Valley Dam, 
Lake Mendocino. 
50. Includes $94,459 special recreation use fees 
and costs (FY 1982-1983), but excludes prior special 
recreation fees and costs for Coyote Valley Dam, Lake 
Mendocino. 
51. Includes $993,680 maintenance and operation 
of dam funds and costs at Coyote Valley Dam, Lake 
Mendocino for FY 1985, FY 1986, FY 1987, FY 1988, 
and FY 1989. 
52. Includes $245,411 contributed funds, other, 
from city of Ukiah for Coyote Valley Dam, Lake 
Mendocino, hydropower studies. 
53. Includes $242,612 contributed fund, other, 
costs for Coyote Valley Dam, Lake Mendocino, 
hydropower studies. 
54. Includes $253,421,793 San Francisco 
construction funds and costs through August 1983 for 
Dry Creek, Warm Springs Dam. 
55. Includes $964,114 San Francisco maintenance 
funds and costs through April 1982 for Dry Creek, 
Warm Springs Dam. 
56. Includes $75,400 maintenance and operation 
of dam funds and costs at Dry Creek, Warm Springs 
Dam. 
57. Includes $208,000 contributed funds, other, 
from Sonoma County for Dry Creek, Warm Springs, 
hydropower studies. 
58. Includes $194,119 contributed fund, other 
costs for Dry Creek, Warm Springs hydropower studies. 
59. Excludes $614,608 for Table Mountain (Iron 
Canyon) project, deauthorized August 5, 1977, and 
$531,000 for Sacramento River and Major and Minor 
Tributaries portions which are considered inactive and 
deferred. 
60. Includes Code 710 funds and costs for 
recreation facilities at Black Butte Lake: Total to date 
$1,000,162. 
61. Includes $104,100 special recreation use fees 
and costs at Black Butte Lake. 
62. Miscellaneous construction and engineering 
and design services (non-project) accomplished at 
expense of State of California under local cooperation 
requirements in connection with acquisition of 
rights-of-way and utility alterations (primarily for 
Sacramento River and Major and Minor tributaries 
project). Includes State Highway Commission payment, 
$789,008, for use of excess excavation from Chico and 
Mud Creeks and Sandy Gulch (Sacramento River and 
Major and Minor Tributaries) for freeway embankment 
through city of Chico. 
63. Includes $41,984, contributed funds, other, 
from State of California for required modification of 
existing private facilities, Sacramento River, Chico 
Landing to Red Bluff; $15,977 contributed funds, 
other, from State of California Department of Boating 
and Waterways for replacing a boarding float at Orland 
Buttes boat launching ramp at Black Butte Lake; and 
$330,000 contributed funds, other, from the city of 
Santa Clara for hydropower studies at Black Butte Lake. 
64. Includes $329,962 contributed funds, other, 
costs for Black Butte hydropower studies. 
65. Includes $8,849,825 San Francisco 
construction funds for Walnut Creek. 
66. Includes $9,049,609 San Francisco 
construction costs for Walnut Creek. 
67. Includes $450,268 San Francisco required 
contributed funds for Walnut Creek. 
68. Includes $525,846 San Francisco required 
contributed costs for Walnut Creek. 
69. Includes $400,348 San Francisco contributed 
funds, other, and contributed fund costs for Walnut 
Creek. 
35-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
70. Includes $1,150,000 contributed funds, other, 
from Contra Costa Flood Control and Water 
Conservation District for replacement of sewerline in 
Richmond for Wildcat and San Pablo Creeks project. 
71. Includes $1,105,077 contributed funds, other 
costs for replacement of sewerline in Richmond for 
Wildcat and San Pablo Creeks project. 
72. Excludes funds applicable to other units of this 
basin authorization (Lower San Joaquin River and 
Tributaries and Tuolomne River Basin, California). 
(See Table 35-E) 
73. Includes $110,000 utilized for preparation of 
1957 Economic Feasibility Report and of Revised 
Feasibility Report (FY 1960, 1961, and 1962) 
applicable to 1962 reauthorization of project. 
74. Includes $80,000 contributed funds, other, 
from the Bureau of Reclamation for visitors center at 
Mark Twain area, New Melones lake. 
75. Includes $12,585 contributed funds, other, 
costs from the Bureau of Reclamation for visitors center 
at Mark Twain area, New Melones Lake. 
35-30

SACRAMENTO, CA, DISTRICT 
TABLE 35-A COST AND FINANCIAL STATEMENT 
PRECONSTRUCTION ENGINEERING AND DESIGN 
See 
Section Total Cost to 
in Text Project Funding FY 85 FY 86 FY 87 FY 88 Sep 30, 1989 1 
Cache Creek Basin, New Work 
CA Approp. $574,000 $640,000 $280,000 293,000 $1,811,336 2 
Cost 375,436 514,136 502,475 356,775 1,748,668 
Cache Creek Sett- New Work 
ling Basin, CA Approp. - - - 486,000 486,000 
Cost - - - 99,032 99,032 
Caliente Creek, CA New Work 
Approp. - - - 60,000 60,000 
Cost - - - 58,303 58,303 
Cottonwood Creek, New Work 
Approp. -50,000 - - - 15,765,000 2 
Cost 17,510 4,979 -29,988 38,738 15,759,197 
Coyote and Berryessa New Work 
Creeks, CA Approp. - - 100,000 714,000 814,000 
Cost - - 64,285 357,290 421,575 
Dry Creek, New Work 
Roseville, CA Approp. - - - 59,000 59,000 
Cost - - - - - 
Guadalupe River, New Work 
CA Approp. 25,000 739,000 625,000 661,000 2,050,000 2 
Cost 16,822 435,345 821,612 717,234 1,991,013 
Napa River, CA New Work 
Approp. - - - 750,000 750,000 2 
Cost - - - 455,470 455,470 
Truckee Meadows, New Work 
NV Approp. - - 440,000 1,528,000 1,968,000 
Cost - - 180,377 1,105,270 1,285,648 
1. Beginning in FY 1982, Advance Engineering 
and Design (Preconstruction, Engineering and Design) 
programs are funded under General Investigations 
Appropriations. 
2. Includes FY 1985 unobligated carryover and 
FY 1986 allocation for CP&E funds and all AE&D 
funds to be included in project cost (for cost sharing) 
per TWX of September 9, 1985. 
3. Excludes $2,639,955 funds and costs for a 
previous flood control project. (See Table 35-E.) 
35-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
Mar. 3, 1899 
July 25, 1912 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
Nov. 17, 1987 
8. 
Oct. 23, 1962 
Nov. 7, 1966 
Nov. 17, 1986 
SACRAMENTO RIVER, CA 
A depth of 7 feet below Sacramento. H. Doc. 186, 55th Cong., 
works. 2d sess., and 48, 55th 
Cong., 3d sess. (Annual 
Report 1898, p. 2844 
and 1899, p. 3171). 
For work above Sacramento. H. Doc. 76, 62d Cong., 
1st sess. 1 
The 10-foot channel up to Sacramento. H. Doc. 123, 69th Cong., 
1st sess. 
A depth of 6 feet between Sacramento and Colusa Rivers and Harbors 
and 5 feet between Colusa and Chico Landing Committee Doc. 35, 
at a cost of $390,000 provided flow of rivers 73d Cong., 2d sess. 
is increased to minimum flow of 5,000 cubic 
feet per second after Shasta Reservoir is built. 
Authority for a special direct participation of Rivers and Harbors 
Federal Government of $12 million in cost Committee Doc. 35, 
of Shasta Reservoir. 73d Cong., 2d sess. 
Transfer of authority for expenditure of above $12 
million from Secretary of War to Secretary of the 
Interior. 
Modified existing navigation project for Sacramento S. Doc. 142, 79th Cong., 
River, CA, to provide for construction of a ship 2d sess. 
channel 30 feet deep and 200 to 300 feet wide 
from deep water in Suisun Bay to Washington Lake, 
including such works as may be necessary to compensate 
for or alleviate any detrimental salinity 
conditions resulting from ship channel; a triangular 
basin of equal depth, 2,400 by 2,000 by 3,400 feet 
at Washington Lake; and connecting channel 13 feet 
deep and 120 feet wide, with lock and drawbridge, 
thence to Sacramento River. 
Deauthorization of shallow-draft channel, Colusa Sec. 1002, 1986 WRDA 
to Red Bluff, feature of project for navigation, 
Sacramento River, California. 
CORTE MADERA CREEK, CA 
Levees and channel improvements, lower 11 miles H. Doc. 545, 87th Cong., 
of Corte Madera Creek and tributaries, as 2d sess. 
modified by Chief of Engineers. 
Local cooperation requirements modified to Sec. 204, 1966 Flood 
provide 1.5 percent cash contribution toward Control Act. 
cost of Ross Valley unit. 
Modify existing project to direct construction of Unit Sec. 823, 1986 WRDA 
4 from Lagunitas Road Bridge to Sir Francis Drake 
Boulevard, and to include construction of floodproofing 
measures in vicinity of Lagunitas Road 
Bridge to insure proper functioning of completed 
portions of authorized project. Further modify 
project to eliminate any channel modifications 
upstream of Sir Francis Drake Boulevard. 
RUSSIAN RIVER BASIN, CA 
Coyote Valley Dam (Lake Mendocino): Channel 
improvements on lower 98 miles of Russian River 
and lower reaches of tributaries. 
Increased appropriation authorization for initial 
stage of project development. 
H. Doc. 585, 
2d sess. 
81st Cong., 
PL 404, 84th Cong., 
2d sess. 
35-32 
21. 
May 17, 1950 
Feb. 10, 1956

TABLE 35-B (Cont'd) 
SACRAMENTO, CA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Dry Creek (Warm Springs) Lake; Channel 
Improvements on Dry Creek below dam. 
Dry Creek (Warm Springs) Lake and channel; 
compensate for fish losses on the Russian River 
which may be attributed to the operation of the 
Coyote Dam component of the project through 
measures such as possible expansion of the 
capacity of the fish hatchery at the Warm 
Springs Dam component of the project. 
H. Doc. 547, 87th Cong., 
2d sess. 
Sec. 95, 1974 WRDA 
May 
July 
17, 1950 
3, 1958 
July 3, 1958 
July 14, 1960 
May 12, 1967 
Mar. 7, 1974 
June 19, 1975 
SACRAMENTO RIVER AND TRIBUTARIES, 
CA, FROM COLLINSVILLE TO SHASTA 
DAM 
Modify Sacramento River Flood Control Project H. Doc. 649, 78th Cong., 
to provide for extensions in levees and other 2d sess. 2 
structures along Sacramento River and major 
and minor tributaries; construct Black Butte 
Dam and Reservoir; construct low-level Table 
Mountain Dam and Reservoir with power 
facilities; and provision of monetary authorization 
of $15 million for initiation of modification. 
Improvements for protection of Upper Butte Basin H. Doc. 367, 81st Cong., 
(included full monetary authorization). 1st sess. 2 
Extend existing Sacramento River Flood Control H. Doc. 272, 84th Cong., 
Project to Keswick Dam for purposes of zoning 2d sess. 2 
area below dam and modification of project by 
construction of bank protection and incidental 
channel improvements between Chico Landing 
and Red Bluff (included full monetary authorization). 
Additional authorization of $17 million for comprehensive 
plan approved in act of December 22, 
1944. 
Further modification of Sacramento River Flood S. Doc. 103, 80th Cong., 
Control Project by construction of initial 10- 
year phase of bank erosion control works and 
setback levees on Sacramento River and 
authorization of $14,240,000 for prosecution 
of modification. 
Additional authorization of $7 million for bank PL 90-17 
protection approved in act of July 14, 1960. 
Initiation of construction of second phase of bank PL 93-251 
erosion control works and setback levees on 
Sacramento River as approved in act of July 14, 
1960, and additional authorization of $16 
million for such purpose. 3 
Deauthorization of Table Mountain Dam and H. Doc. 94-192, 94th 
Reservoir. 4 Cong., 1st sess. 
1. Contains latest published map of section above 
Sacramento. For map of section below Sacramento, see 
H. Doc. 1123, 60th Cong., 2d sess. and S. Doc. 142, 
79th Cong., 2d sess. 
2. Contains latest published map. 
3. Total monetary authorization available, exclusive 
of preauthorization studies from general investigations 
appropriations, amounts to $72,740,000. 
4. The 90-day Congressional project review 
period, required by sec. 12, PL 93-251, as amended by 
sec. 157, PL 94-587, ended August 5, 1977, and 
resulted in deauthorization of project unit. 
35-33 
Oct. 23, 1962 
Mar. 7, 1974 
22. 
Dec. 22, 1944

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Feather River, CA 1951 - $ 5,7521 2 
Middle River and Connecting 
Channels, CA Completed 1974 $ 8,3543 93,4944 
Mokelumne River, CA Completed 1974 8,500 189,152 
Navajo Reservoir, NM Completed - 2,1325 6 - 
Old River, CA Completed 1970 23,185 7 631,128 
Stockton and Mormon 
Channels, CA Completed 1970 253,1518 218,854 
Suisun Bay Channel, CA Completed 1974 200,928 o1011 3,316,62212 13 
Suisun Channel, CA Completed 1973 217,677 733,48913 14 
Suisun Point Channel, CA Completed 1965 191,728 5 15 - 
1. Maintenance project, channels adequate for 
commerce. 
2. Includes $10 for maintenance for previous 
project. Excludes $6,160 for previous project and 
$3,840 for existing project for maintenance expended 
from contributed funds. 
3. Includes $1,600 for previous project. 
4. Includes $790 for previous project. 
5. Authorized by Chief of Engineers under 
authority of sec. 107, Public Law 86-645, as amended. 
6. All costs transferred from Los Angeles District 
in FY 1968. 
7. Estimated cost to local interests was $3,600 for 
lands, damages and public landings. Remaining portion 
of project, consisting of side channel at Orwood and 
completion of project channels from mouth of Old River 
to Lammers Ferry road and from Crocker Cut to Holly 
Sugar Factory was deauthorized November 17, 1986, by 
WRDA of 1986. 
8. Upon completion of Mormon Slough, 
Calaveras River, CA in February 1970, local interests 
accepted maintenance responsibility for Mormon 
Slough as well as for Stockton and Mormon Channels 
CA, and Federal maintenance was discontinued. No 
Federal maintenance costs have been incurred since FY 
1969.
9. Includes $58,901 for previous project. 
10. Excludes $59,551 expended from required 
contributed funds for previous project. 
11. Excludes work accomplished under existing 
project at a cost of $207,198 from Public Works 
Administration funds allotted to San Joaquin River, CA. 
12. Includes $59,817 for previous projects. 
Excludes $5,449 expended from required contributed 
funds for previous project. 
13. Maintenance responsibility transferred to San 
Francisco District, January 1, 1974. 
14. Includes reconnaissance and condition surveys 
of $5,496 and $483 for fiscal year 1963 and 1964, 
respectively. 
15. Estimated cost (July 1964) to local interests was 
$12,000 for lands, damages, and spoil retention dikes. 
35-34

SACRAMENTO, CA, DISTRICT 
TABLE 35-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Alameda Creek, CA Completed 
American River, CA Completed 
Aquatic Plant Control, CA Completed 
Big Cry Creek Dam and 
diversion, CA Completed 
Big Wash, Milford, Beaver 
County, UT Completed 
Burch Creek, Weber County, UT 
Chester, CA Active/no FY 89 
expenditure 
Coyote Creek, CA Completed 
Duck Creek, San Joaquin 
County, CA Completed 
East Weaver Creek, CA Completed 
Folsom Lake, American River, CA Completed 
Green Valley Creek, Solano 
County, CA Completed 
Kays Creek, UT Completed 
Kern River-California Adqueduct 
Intertie, CA Completed 
Klamath River, CA Completed 
Lake Camanche, CA Completed 
Lake Oroville, CA Completed 
Lakeport Lake, CA Active/no FY 89 
expenditure 
Lower San Joaquin River and 
Tributaries, including Tuolumne 
and Stanislaus Rivers, CA Completed 
Marysville Lake, CA Active/no FY 89 
expenditure 
Merced River, CA Completed 
Middle Creek, CA Completed 
Mormon Slough, CA Completed 
Napa River Basin, CA Active/no FY 89 
expenditure 
New Bullards Bar, CA Completed 
North Fork, Pit River at 
Alturas, CA Completed 
Pinole Creek, CA Completed 
Redwood Creek, Humboldt 
County, CA Completed 
Reese River, Battle Mountain, NV Completed 
Rheem Creek, CA Completed 
Rodeo Creek, CA Completed 
Salinas River, CA Inactive 
Salt Lake City, Jordan River, UT Completed 
San Leandro Creek, CA Completed 
San Lorenzo Creek, CA Completed 
San Lorenzo River, CA Completed 
Sevier River near Redmond, UT Completed 
Sonoma Creek, CA Inactive 
Truckee River and tributaries, Active/no FY 89 
CA and NV expenditure 
1978 
1959 
1967 
1955 
1961 
1964 
1981 
1968 
1967 
1965 
1957 
1963 
1973 
1977 
1972 
1976 
1981 
1976 
1976 
1980 
1976 
1967 
1976 
1979 
1972 
1974 
1968 
1970 
1969 
1962 
1966 
1952 
1961 
1973 
1962 
1966 
1952 
1973 
1968 
$26,995,350 
2,125,8 18 3 
1,000 
1,369,9314 
217,879s 6 
26,049 5 
3,570,000 7 
705,622 1 5 
664,825 8 
220,636 1 5 9 
63,014,810 10 
136,0265 11 
407,989 s 12 
1,503,073 s 13 
4,838,000 1 
10,252,950 14 
70,425,470 15 
2,353,003 18 
27,835,263 17 
- 18 
10,918,796 19 
2,643,499 20 
2,965,402 21 
2,639,955 1 22 
12,890,625 23 
904,278 6 24 26 
885,750 1 6 
4,620,070 1 28 
133,339 6 27 
400,000 1 5 28 
974,100 1 s 
94,213 1 29 
1,227,570 o 
1,000,000 1 31 
5,130,821 1 32 
4,314,406 133 
919,000 34 
781,500 1 36 
1,038,960 
35-35 
$54,778 1 2

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-E (Cont'd) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
1. Project responsibility transferred from San 
Francisco District to Sacramento District April 1, 1982. 
2. Scheduling of reservoir operations costs. 
3. Excludes $54,919 other contributed funds for 
miscellaneous construction for local interests pursuant to 
requirements of local cooperation were $951,000 
(1959) for lands and relocations. 
4. Excludes $44,008 other contributed funds for 
construction in connection with bridge construction 
pursuant to requirements of local cooperation. Total 
cost to local interests for all requirements of local 
cooperation was $370,000 (1959) for lands and 
relocations. 
5. Authorized by Chief of Engineers under 
authority of sec. 205, Public Law 80-858, as amended. 
6. Excludes $22,000 for preauthorization studies. 
7. Excludes $69,262 other contributed funds from 
State of California for two low water crossings and 
appurtenances at Chester. 
8. Excludes $50,000 for preauthorization studies. 
Estimated costs to local interests were $665,000 for 
lands and damages including relocations. 
9. Includes $174,938 Public Works Acceleration 
Program Funds. 
10. Transferred to Bureau of Reclamation in May 
1956 for operation and maintenance by that agency in 
conjunction with other units of Central Valley project. 
11. Excludes $20,000 for preauthorization studies. 
12. Includes $30,000 for preauthorization studies. 
Estimated costs (FY 1973) to local interests for all 
requirements of local cooperation were $150,117 for 
lands and damages including relocations. 
13. Includes $73,000 for preauthorization studies. 
Non-Federal (Kern County Water Agency) cost for 
road relocation was $18,260 (required contributed 
funds). 
14. Constructed by East Bay Municipal Utility 
District. Final Federal contribution of $51,202 made 
July 18, 1978 (total $10,111,684). Non-Federal costs 
$34,988,536. 
15. Constructed by State of California. Final 
Federal contribution of $64,186 was made on February 
9, 1981 (total $69,994,105) for flood control 
reservation. Project prevented $500,000 in damages 
from the FY 1989 rainfloods. 
16. Lakeport Lake was deauthorized November 17, 
1986, and was reauthorized November 17, 1988. 
17.Cherry Valley and New Don Pedro Reservoirs 
constructed by local interests. Federal contributions of 
$9,000,000 and $5,464,000, respectively, for flood 
control reservation. Final Federal contribution of 
$308,898 was made on January 18, 1972, for New Don 
Pedro. Excludes $3,004,946, contributed funds, other, 
for miscellaneous engineering and construction (nonproject) 
at local interest expense under local cooperation 
requirements for acquisition of rights-of-way for 
levee and channel improvements on Lower San Joaquin 
River and tributaries. 
18. Planning and any future development is 
uncertain awaiting State of California's position on 
support of Marysville project. 
19. Constructed by Merced Irrigation District, Final 
Federal contribution of $839 was made December 2, 
1975 (total $10,818,638) for flood control reservation. 
20. Estimated costs (FY 1967) to local interests for 
all requirements of local cooperation were $1,340,000 
for lands and damages including relocations. 
21. Non-Federal cost $2,965,402 (FY 1976) for 
lands and relocations. Federal contribution of $599,336 
made to State Reclamation Board. 
22. This project was reclassified as "active" on 
August 3, 1987. 
23. Constructed by Yuba County Water Agency. 
Final Federal contribution of $33,470 was made in FY 
1972 (total $12,759,127) for flood control reservation. 
24. Includes $41,800 for preauthorization studies. 
25. Excludes $146,000 other contributed funds for 
miscellaneous construction and engineering and design 
services under local cooperation requirements in 
connection with acquisition of rights-of-way, relocation, 
and utility alterations. 
26. Includes $107,000 costs for remedial work to 
drainage system completed in FY 1977. 
27. Includes $19,000 for preauthorization studies. 
28. Excludes $52,549 contributed funds. 
29. Cost includes engineering and design prior to 
June 30, 1952 and costs of $4,288 (FY 1962 - 1963) to 
determine if project classification to an active category 
was justified. 
30. Estimated costs to local interests for all 
requirements of local cooperation were $463,000 (July 
1962) for lands and damages including relocations. 
Project prevented $500,000 in damages from the 
May-July 1989 snowmelt runoff. 
31. Excludes $285,329 contributed funds. 
32. Excludes $200,000 estimated value of work 
performed in lieu of cash contribution. 
33. Excludes $421,182 contributed funds. 
34. Excludes $48,000 required contributed funds 
toward first cost. Cost to local interests for all 
requirements of local cooperation, including required 
contributions, were $118,000 (1951). 
35. Placed inactive 1974. 
35-36

TABLE 35-G 
SACRAMENTO, CA, DISTRICT 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Alhambra Creek, CA 1981 1986 $300,000 - 
Bear River, CA 1980 1986 - - 
Eel River, CA 1971 1986 1,272,816 - 
Gleason Creek, NV 1977 1986 215,826 - 
Humboldt River and 
Tributaries, NV 1982 1986 1,532,932 - 
Little Valley Wash, Magna, UT 1951 1977 - - 
Mad River Basin, CA 1973 1986 4,243,750 - 
Spanish Fork River, UT 1955 1977 20,000 - 
Weber River and Tributaries, UT 1974 1972 75,120 - 
(Morgan County) 
TABLE 35-H SACRAMENTO RIVER, CA: 
TIDAL AND FLOOD CONDITIONS PREVAILING 
(See Section 1 of Text) 
Range in Feet 
Miles from Mean Extreme Ordinary Extreme 
Mouth of Tidal 1 Tidal 2 Flood 3 Flood 4 
Place River 
Collinsville 0 4.3 7 8 10 
Sacramento 59 2.0 2 3 20 28 
Verona (Mouth of Feather River) 80 - Trace 22 30 
Colusa 144 - - 26 32 
Chico Landing 193 - - 20 25 
Red Bluff 248 - - 24 30 
1. Mean lower low water to mean higher high 
water. 
2. Tide at low water season only. 
3. Mean lower low water to flood stage. 
4. Extreme low water to indicated flood condition. 
35-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-I SAN JOAQUIN RIVER, CA: 
TOTAL COST OF NEW WORK FOR PROJECT 1 
(See Section 4 of Text) 
Federal Non-Federal 2 
Modification 
Corps of 
Engineers 
(Construction) 
Coast 
Guard 
(Construction) 
Required 
Cash 
Contribution 
Lands and 
Damages (including 
Relocations) 
Total Total 
Project 
Prior to 1950 
Modification $4,009,938 $80,000 $1,307,500 $1,042,000 $2,349,500 $6,439,438 
1950 Modification 1,823,179 - 35,000 135,000 170,000 1,993,170 
Total $5,833,117 $80,000 $1,342,500 $1,177,000 $2,519,500 $8,432,617 
1. Completed in May 1960. 
2. Excludes $5,865,000 (Feb. 1954) local interests 
costs for Stockton Deep Water Channel terminal 
facilities required under terms of project authorization. 
TABLE 35-J SAN JOAQUIN RIVER, CA: 
PROJECTS UNITS (1950 MODIFICATION) RECLASSIFIED AND 
EXCLUDED FROM PROJECT COST 
(See Section 4 of Text) 
Non-Federal 
Federal Required Lands and 
Corps of Cash Damages (includ- Total 
Unit Engineer Contribution ing Relocations) Total Project 
Settling Basin above head 
of Burns Cutoff 1 $1,073,000 $30,000 $200,000 $230,000 $1,303,000 
Burns Cutoff improvement; 
new turning basin; dredging 
Mormon Channel 2 5 7,882,0003 431,000 1,455,000 1,886,000 9,768,000 
Upper Stockton Channel 
enlargement 4 5 535,000 34,000 15,000 49,000 584,000 
1. July 1959 price index. 
1977. 
Deauthorized August 5, 
2. Deferred; July 1960 price index. 
3. For lands and construction. 
4. Deleted by 1965 River and Harbor Act 
authorization of San Francisco Bay to Stockton 
Channel, Sacramento District, Improvement No. 3. 
5. Deauthorized November 17, 1986. 
35-38

SACRAMENTO, CA, DISTRICT 
TABLE 35-K MERCED COUNTY STREAM GROUP, CA, 
MAXIMUM INFLOW, STORAGE, AND OUTFLOW FOR PROJECTS 
(See Section 16 of Text) 
Maximum 
Inflow Maximum Maximum 
(c.f.s.) Storage Outflow 
Stream (bihourly) (acre-feet) (c.f.s.) 
Burns 1,300 30 1,000 
Bear 630 90 530 
Owens 330 70 80 
Mariposa 1,140 570 400 
TABLE 35-L RUSSIAN RIVER BASIN, CA: ESTIMATED 
COST FOR NEW WORK 
(See Section 21 of Text) 
Estimated Cost 
Non-Federal 
Project Feature Federal Contribution Total 
Coyote Valley Dam (Lake Mendocino): 
Channel Improvements below Dam 
on lower 98 miles of Russian River $14,436,000 $5,598,000 $20,034,000 1 
Dry Creek (Warm Springs) Lake: 
Channel Improvements below Dam 257,600,000 104,020,000 361,620,000 
Total $272,036,000 $109,618,000 $381,654,000 
1. Exclusive of $1,628,000 for recreation facilities 
at completed projects. 
2. Reimbursement by local interests to Federal 
Government for costs allocated to water supply storage 
to be paid over a period not to exceed 50 years after use 
of storage is initiated and exclusive of lands and 
damages. 
35-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-M RUSSIAN RIVER BASIN, CA: PROJECT 
FEATURES AND ESTIMATED COSTS 
(See Section 21 of Text) 
Height of Reservoir 
Nearest City Distance Dam and Capacity Estimated 
Name (California) Above Mouth Type (Acre-Ft) Cost 
Coyote Valley Dam (Lake Ukiah Mile 0.8-East Fork 160 Feet- 122,500 $17,550,000 1 
Mendocino) of Russian River Earthfill 
Channel Improvements (East Ukiah Mile 0 to 0.8 East - - 2,484,000 
Fork) Fork 
below Coyote Valley Dam Guerneville Mile 0 to 98, Russian - - - 
and lower 98 miles of River 
Russian River) 
Dry Creek (Warm Springs) Healdsburg Mile 14.4 Dry Creek 319 Feet- 381,000 358,220,000 
Earthfill 
Channel Improvements (Dry Healdsburg Mile 1 to 14.4 Dry - - 3,400,000 
Creek) below Dry Creek Creek 
(Warm Springs Dam) 
1. Exclusive of $1,628,000 for recreation facilities 
at completed projects. 
TABLE 35-N SACRAMENTO RIVER AND TRIBUTARIES, CA, 
COLLINSVILLE TO SHASTA DAM: 
PROJECT UNITS RECLASSIFIED AND EXCLUDED FROM COST ESTIMATE 
(See Section 22 of Text) 
Current Estimated Cost 
Unit Classification Federal Non-Federal Total 
1944 Modification: 
Antelope Creek 2 Inactive $1,400,000 $340,000 $1,740,000 
Lower Butte Basin 3 Deferred 7,286,000 2,285,000 9,571,000 
Thomas Creek 2 Deferred 1,140,000 140,000 1,280,000 
Willow Creek 2 Inactive 1,290,000 120,000 1,410,000 
Bypass Levees 4 Deferred 7,100,000 940,000 8,040,000 
Bypass Levees 4 Inactive 3,010,000 - 3,010,000 
1950 Modification: 
Upper Butte Basin 2 Deferred 3,530,000 1,787,000 5,317,000 
1. For lands and damages, including relocations. 
2. July 1960 price level. 
3. Excludes work applicable to extension of 
Moulton weir (July 1954 price level). 
4. July 1961 price level. 
35-40

SACRAMENTO, CA, DISTRICT 
TABLE 35-0 SACRAMENTO RIVER AND TRIBUTARIES, CA, 
FROM COLLINSVILLE TO SHASTA DAM: 
CONSTRUCTION ACCOMPLISHED AND CONTRACT COSTS 
(See Section 22 of Text) 
Required 
Contract Federal Contributed Total 
Contract 40B continuation (Bank protection, 
selected sites, Sacramento River, 
miles 187.1-191.6) -$137,215 $795,377 $658,162 
Contract 41A (also known as 40C) 
completion (Bank protection, 
selected sites on Sacramento River, 
miles 19.2-23.2, and Sloughs) 20,736 2,828 23,564 
Contract 42 initiation (Bank protection, 
selected sites on Sacramento River, 
miles 23.6-56.7, and Georgiana, 
Steamboat and Sutter Sloughs) 1,650,518 387,629 2,038,147 
Contract 43 initiation (Bank protection, 
selected sites on Feather River, 
Colusa Basin Drain, and Sutter and 
Yolo Bypasses 1,829,875 515,007 2,344,882 
35-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 35-P FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, PUBLIC LAW 80-858, 
AS AMENDED (PREAUTHORIZATION) 
(See Section 26 of Text) 
Fiscal Year 
Study Stage Cost 
Ashley Creek near Vernal, UT 1 Reconnaissance $28,774 
Bitter Creek at Rock Springs, WY Reconnaissance 6,119 
Blacksmith Fork River, Logan, UT 1 Reconnaissance 19,825 
Burch and Jewett Creeks near Corning, CA Reconnaissance 1,635 
Carson River below Lahontan Dam, Fallon, NV Reconnaissance 5,892 
Colorado River at Grand Junction, CO Reconnaissance 11,793 
Colorado River at Riverside, CO Reconnaissance 431 
Elder and Unionhouse Creeks, CA Reconnaissance 6,400 
Henson Creek, Lake City, CO Reconnaissance 5,362 
Morrison Creek, Beach-Stone Lakes, CA 1 Reconnaissance 1,065 
Plateau Creek near Collbran, CO 1 Reconnaissance 8,037 
Price River, Price, UT 1 Reconnaissance 1,864 
Roaring Fork River near Basalt, CO 1 Reconnaissance 18,705 
Sacramento River near Hamilton City, CA Reconnaissance 20,671 
Sacramento River, Tehama, CA Reconnaissance 14,619 
Salado Creek near Patterson, CA Reconnaissance 14,992 
Weber River at Oakley, UT 1 Reconnaissance 24,841 
West Antioch Creek vicinity Antioch, CA Reconnaissance 184 
White River at Meeker, CO 1 Reconnaissance 27.4 19 
$218,628 
1. No further studies recommended. 
35-42

PACIFIC OCEAN DIVISION 
The Pacific Ocean Division is an operating division with 
both district and division functions. Its civil works responsibilities 
encompass the State of Hawaii, the Territory 
of Guam, the Territory of American Samoa, and the 
Commonwealth of the Northern Mariana Islands. The 
division is unique in that the area of responsibility is 
totally comprised of islands dispersed over an ocean 
environment exceeding 6 million square miles. 
IMPROVEMENTS 
Navigation 
1. Agat Harbor, Guam ........... ........ 
2. Barbers Point Harbor, Oahu, Hawaii ...... 
3. Kaulana Bay Boat Harbor, Hawaii, Hawaii . 
4. Kawaihae Small Boat Harbor, 
Hawaii, Hawaii ........................ 
5. Laupahoehoe Harbor, Hawaii, Hawaii ..... 
6. Maalaea Harbor, Maui, Hawaii ........... 
7. Reconnaissance and Condition Surveys .... 
8. Navigation Work Under Special 
Authorization ......................... 
Erosion Control 
9. Lepua Area, American Samoa ............ 
10. Masefau Bay, American Samoa ........... 
11. Sand Island Shore Protection 
Oahu, Hawaii ........................ 
12. Beach Erosion Work Under Special 
Authorization ......................... 
Flood Control 
13. Agana River, Guam ................. 
14. Alenaio Stream, Hawaii, Hawaii .......... 
15. Kahawainui Stream, Oahu, Hawaii ....... 
16. Kahoma Stream, Maui, Hawaii .......... 
17. Flood Control Work Under Special 
Authorization ......................... 
18. Inspection of Completed Flood 
Control Projects ...... ......... ...... 
Multiple-Purpose Projects, 
Including Power 
19. Nanpil River Hydropower, Pohnpei, 
Federated States of Micronesia .......... . 
Page 
36-2 
36-2 
36-2 
36-2 
36-2 
36-3 
36-3 
36-3 
36-3 
36-3 
36-3 
36-4 
36-4 
36-4 
36-4 
36-4 
36-5 
36-5 
General Investigations 
20. Surveys ............................ 
21. Collection and Study of Basic Data ........ 
22. Preconstruction Engineering and 
Design ............................... 
Page 
36-5 
36-5 
36-6 
Tables 
Table 36-A Cost and Financial Statement .... 36-7 
Table 36-B Authorizing Legislation ......... 36-9 
Table 36-C Other Authorized Navigation 
Projects ....................... 36-11 
Table 36-D Other Authorized Beach 
Erosion Control Projects ......... 36-12 
Table 36-E Other Authorized Flood 
Control Projects ................ 36-13 
Table 36-F Not Applicable 
Table 36-G Deauthorized Projects ........... 36-14 
Table 36-H Navigation Activities Pursuant 
to Section 107 ................. 36-15 
Table 36-I Emergency Streambank and 
Shoreline Protection Activities 
Pursuant to Section 14 .......... 36-15 
Table 36-J Beach Erosion Control Activities 
Pursuant to Section 103 ......... 36-15 
Table 36-K Flood Control Activities Pursuant 
to Section 205 .................. 36-16 
Table 36-L Flood Control Activities Pursuant 
to Section 208 .................. 36-16 
Table 36-M Inspection of Completed Flood 
Control Projects ................ 36-16 
36-5
36-1 
_ I_ I_ _I

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigation 
1. AGAT HARBOR, GUAM 
Location. On the southwestern coast of the island of 
Guam, about 3,318 miles west of Honolulu, Hawaii (See 
NOAA Chart 81408) 
Existing project. For a description of the existing 
project, see page 36-1 of the FY86 Annual Report. 
Local cooperation. Requirements are described in 
full on page 36-1 of the FY86 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. New Work: The 
construction contract was completed in February 1989 
and dedicated in March 1989. Negotiations for contractor 
claims are ongoing; financial completion pending. 
2. BARBERS POINT HARBOR, OAHU, 
HAWAII 
Location. On the west coast of Oahu, about 25 miles 
from metropolitan Honolulu. (See Coast and Geodetic 
Survey Charts 4110 and 4133) 
Existing project. For a description of the existing 
project, see page 36-1 of the FY84 Annual Report. Total 
project estimate is $63,600,000 of which Federal cost is 
$55,300,000 (including $372,500 in U.S. Coast Guard 
cost) and non-Federal cost is $8,300,000 including lands 
and rights-of-way and cash contribution of $2,500,000. 
(See Table 36-B for Authorizing Legislation) 
Local cooperation. Requirements are described in 
full on page 36-1 of the FY85 Annual Report. 
Terminal facilities. See page 36-2 of the FY84 
Annual Report. 
Operations during fiscal year. Plans and specifications 
for project beautification and revetment construction 
were completed in January 1989. A construction 
contract was awarded in May 1989 for $488,000 of which 
Federal cost is $67,000 and non-Federal cost is $421,000. 
Construction was not initiated as of September 1989. 
Completion is scheduled for January 1990. Maintenance: 
Annual operational cost for the Regional Visitor Center 
located at Fort DeRussy was $52,957. 
3. KAULANA BAY BOAT HARBOR, 
HAWAII, HAWAII 
Location. On the southern tip of the island of Hawaii 
in the Ka'u Judicial District about 80 road miles southwest 
of the city of Hilo. (See NOAA Chart 19320) 
Existing project. For a description of the existing 
project, see page 36-2 of the FY84 Annual Report. Total 
project cost estimate is $828,000 of which Federal cost is 
$751,000 and non-Federal cost is $77,000. 
Local cooperation. Requirements are described in full 
on page 36-3 of the FY82 Annual Report. 
Terminal facilities. There is an existingboat launching 
ramp owned by the State of Hawaii and open to the 
public on an equal basis. 
Operations during fiscal year. A construction 
contract is scheduled for award in December 1989 pending 
completion of a Memorandum of Agreement between 
the State of Hawaii and the Historic Preservation Office. 
Plans and specifications were updated and a revised 
environmental assessment is underway. 
4. KAWAIHAE SMALL BOAT HARBOR, 
HAWAII, HAWAII 
Location. Kawaihae Harbor is located on the west 
coast of the island of Hawaii, approximately 85 nautical 
miles northeast of Hilo, County of Hawaii. (See NOAA 
Chart 19320) 
Existing project. The authorized project consists of 
an 850-foot long, 120-foot wide, and 12-foot deep entrance 
channel; a 1.2 acre and 12-foot deep existing 
turning basin; a 640-foot long, 80-foot wide, and 8-foot 
deep access channel; a 1,225-foot long west protective 
revetment structure; a 1,050-foot long east protective 
revetted structure; a 400-foot long wave absorber; and a 
2.5 acre, 650-foot long revetted offshore island. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. A Local Cooperation Agreement 
(LCA) will be prepared during the plans and specifications 
phase. 
Terminal facilities. None. 
Operations during fiscal year. The estimated cost 
of preconstruction engineering and design (PED) is 
$328,000. Total costs incurred during the Fiscal Year 
were $149,759. PED was approximately 41% complete as 
of September 30, 1989. 
5. LAUPAHOEHOE HARBOR, HAWAII, 
HAWAII 
Location. Laupahoehoe is located on a peninsula on 
the northeast coast of the island of Hawaii, about 25 road 
miles northwest of Hilo. (See NOAA Chart 19320) 
Existing project. For a description of the existing 
project, see page 36-2 of the FY87 Annual Report. 
Local cooperation. Requirements are described in 
full on page 36-2 of the FY87 Annual Report. 
Terminal facilities. The current facility includes a 
single lane, concrete paved launch ramp, roadways and 
parking areas. 
36-2

PACIFIC OCEAN DIVISION 
Operations during fiscal year. A construction 
contract to improve navigation safety was awarded in 
September 1989 for $235,000 of which Federal cost is 
$210,600 and non-Federal cost is $24,400. Construction 
is scheduled for completion in December 1989. 
6. MAALAEA HARBOR, MAUI, HAWAII 
Location. Maalaea Bay is situated on the southwest 
coast of Maui, approximately 7 miles south of Wailuku, 
the county seat of Maui. (See NOAA Chart 19350) 
Existing project. The authorized plan consists of 
improvements to an existing State owned facility, initially 
constructed by the State of Hawaii in 1952 and 
includes a 620-foot long extension of the south breakwater, 
a new 610-foot long, 150 to 180-foot wide, 12- to 
15-foot deep entrance channel, a 1.7 acre and 12 foot deep 
turning basin and a 720-foot long, 80-foot wide and an 
8-foot deep access channel. (See Table 36-B for Authorizing 
Legislation) 
Local cooperation. A Local Cooperation Agreement 
(LCA) will be prepared during the plans and specifications 
phase. 
Terminal facilities. There is an existing 1,000-foot 
long south breakwater, a 870-foot long east breakwater, 
300-foot long wharf, 90-foot wide entrance channel, and 
a single lane launch ramp, all constructed by the State of 
Hawaii. 
Operations during fiscal year. The estimated cost 
of preconstruction engineering and design (PED) is 
$395,000. Total costs incurred during the Fiscal Year 
were $125,660. PED was approximately 57% complete as 
of September 30, 1989. 
7. RECONNAISSANCE AND CONDITION 
SURVEYS 
Condition surveys were conducted at Auasi Small Boat 
Harbor, American Samoa; Aunuu Small Boat Harbor, 
American Samoa; Kahului Deep Draft Harbor, Hawaii; 
Laupahoehoe Harbor, Hawaii; Ofu Small Boat Harbor, 
American Samoa; and Tau Small Boat Harbor, American 
Samoa, in March 1989 by the Portland Districtfor$49,924. 
8. NAVIGATION WORK UNDER SPEC IAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (Preauthorization). See Table 36-H. 
Beach Erosion Control 
9. LEPUA AREA, AMERICAN SAMOA 
Location. Lepua Village is located on the island of 
Tutuila, about two miles east of Pago Pago on the north 
side of the Pago Pago Harbor. (See Coast and Geodetic 
Survey Chart 4190, Manua Islands) 
Existing project. For a description of the existing 
project, see page 36-3 of the FY88 Annual Report. 
Local cooperation. Requirements are described in 
full on page 36-3 of the FY88 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. A Local Cooperation 
Agreement (LCA) was executed in October 1988. Bid 
opening was held in January 1989 with acceptable bids 
well in excess of the government estimate. Contractor's 
proposal was submitted for audit by the Defense Contract 
Audit Agency. Results were received in August 1989 and 
negotiations with the contractor were completed and a 
continuing contract was awarded in September 1989. 
Total amount of the contract is $1,459,640 of which 
$1,102,640 is Federal cost and $357,000 is non-Federal 
cost 
10. MASEFAU BAY, AMERICAN SAMOA 
Location. Masefau Village is located on the north 
coast of the island of Tutuila. (See Coast and Geodetic 
Survey Chart 4190, Manua Islands) 
Existing project. The proposed plan consists ofa 525 
foot long revetment fronting the coastal road and elementary 
school in Masefau. 
Local cooperation. Requirements are described in 
full on page 36-3 of the FY88 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. A Local Cooperation 
Agreement (LCA) was executed in October 1988. Bid 
opening was held in January 1989 with acceptable bids 
well in excess of the government estimate. Contractor's 
proposal was submitted for audit by the Defense Contract 
Audit Agency. Results were received in August 1989 and 
negotiations with the contractor were completed and a 
continuing contract was awarded in September 1989. 
Total amount of the contract is $329,525 in Federal costs. 
11. SAND ISLAND SHORE PROTECTION, 
OAHU, HAWAII 
Location. Sand Island is located on the southern 
coast of Oahu. Sand Island is approximately 520 acres in 
36-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
area and shelters Honolulu Harbor from the open sea. It 
is connected to the Kapalama peninsula by a bascule 
bridge at its western end. There is approximately 4,700 
feet of shoreline on the south side of the island adjacent to 
the State park. (See Coast and Geodetic Survey Chart 
4109) 
Existing project. The proposed plan provides for a 
revetment 1,350-feet long and an offshore breakwater 
520-feet long. The estimated project first cost is $3,000,000 
of which Federal cost is $1,500,000 and non-Federal cost 
is $1,500,000. 
Local cooperation. Requirements are described in 
full on page 36-4 of the FY88 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. Currently awaiting 
local permit clearances from the study sponsor. A 
construction contract is scheduled for award in January 
1990. 
12. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency streambank and shoreline protection activities 
pursuant to Section 14, Public Law 79-526 (Preauthorization). 
See Table 36-I. 
Beach Erosion control activities pursuant to Section 
103, Public Law 87-874 (Preauthorization). See Table 
36-J. 
Flood Control 
13. AGANA RIVER, GUAM 
Location. The Agana River basin and the City of 
Agana are located on the western end of the Island of 
Guam near the center of the Island. The Territory of 
Guam is located approximately 3,800 statute miles west 
of Honolulu. (See NOAA Chart 81048) 
Existing project. For a description of the project, see 
page 36-3 of the FY87 Annual Report. The estimated cost 
of the project is $5,280,000 of which Federal cost is 
$4,090,000 and non-Federal cost is $1,190,000. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. Requirements are described in 
full on page 36-3 of the FY87 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. New Work: Plans 
and specifications were initiated in October 1986 and is 
approximately 95% complete as of September 30, 1989. 
Execution of a Local Cooperation Agreement and construction 
has been postponed pending resolution of land 
issues and a financing plan by the Government of Guam. 
14. ALENAIO STREAM, HAWAII, HAWAII 
Location. The Alenaio watershed is located in the 
South Hilo District on the island of Hawaii. Hilo is the 
principal urban center in the South Hilo district and the 
County seat for the County of Hawaii. (See NOAA Chart 
81408) 
Existing project. The recommended project consists 
of approximately 1,640-feet of concrete-lined channel; 
relocating one public and six residential structures and 
incorporating floodplain management regulations for 
undeveloped areas. The flood control improvements will 
provide a 100-year level of protection. The estimated cost 
of preconstruction engineering and design is $750,000. 
(See Table 36-B for Authorizing Legislation) 
Local cooperation. A Local Cooperation Agreement 
(LCA) will be prepared during the plans and specifications 
phase. 
Terminal facilities. None 
Operations during fiscal year. The estimated cost 
of preconstruction engineering and design (PED) is 
$750,000. Total costs incurred during the Fiscal Year 
were $261,384. The General Design Memorandum phase 
of PED was approximately 60% complete through September 
30, 1989. 
15. KAHAWAINUI STREAM, OAHU, 
HAWAII 
Location. The Kahawainui Stream watershed is located 
on the northeastern coast of the island of Oahu. 
Laie is the principal urban center in the Kahawainui 
watershed. (See Coast and Geodetic Survey Chart 4110) 
Existing project. For a description of the existing 
project, see page 36-4 of the FY88 Annual Report. 
Local cooperation. Requirements are described in 
full on page 36-4 of the FY88 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. A construction 
contract was awarded in November 1988 for $3,781,000 of 
which Federal cost is $3,090,000 and non-Federal cost is 
$691,000. Construction completion is scheduled in March 
1990. Construction is approximately 69% complete as of 
September 30, 1989. 
16. KAHOMA STREAM, MAUI, HAWAII 
Location. The Kahoma Stream drainage basin is 
located in Lahaina, Maui. Lahaina is on the west coast of 
Maui, about 4 miles from Kaanapali. The drainage basin 
of Kahoma Stream totals 5.3 square miles. (See NOAA 
Chart 19348) 
36-4

PACIFIC OCEAN DIVISION 
Existing project. For a description of the existing 
project, see page 36-5 of the FY84 Annual Report. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. Requirements are described in 
full on page 36-4 of the FY86 Annual Report. 
Terminal Facilities. None. 
Operations during fiscal year. New Work: Local 
Cooperation Agreement was executed in June 1986. A 
construction contract was awarded in September 1986 for 
$12,180,999 with completion scheduled in March 1990. 
Construction is approximately 84% complete as of September 
30, 1989. 
17. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 80-858. (Preauthorization). See Table 36-K. 
Flood control activities pursuant to Section 208 Public 
Law 83-780. (Preauthorization). See Table 36-L. 
Emergency flood control activities pursuant to Public 
Law 84-99. 
Federal cost during the fiscal year for Flood Control and 
Coastal Emergencies appropriation was $2,593,024 of 
which $222,069 was for disaster preparedness and 
$2,370,955 for rehabilitation. 
18. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Federal costs incurred during the fiscal year total 
$21,454. For a listing of projects inspected, see Table 
36-M. 
Multiple-Purpose Projects Including 
Power 
19. NANPIL RIVER HYDROPOWER, 
POHNPEI, FEDERATED STATES OF 
MICRONESIA 
Location. Nanpil River is located on the island of 
Pohnpei in the Federated States ofMicronesia. (See State 
of Hawaii, the New Pacific map) 
Existing project. For a description of the existing 
project see page 36-4 of the FY85 Annual Report. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. Requirements are described in 
full on page 36-5 of the FY85 Annual Report. 
Terminal Facilities. None. 
Operations during fiscal year. A construction 
contract for $5,622,000 was completed in October 1987. A 
contract to provide training for the operation and maintenance 
of the project is underway and is scheduled to run 
through FY91. 
General Investigations 
20. SURVEYS 
Fiscal year costs were $698,225 of which $84,641 was 
for navigation studies, $5,513 for flood damage prevention 
studies, $65,039 for shoreline protection studies, 
$311,033 for comprehensive studies, $76,060 for miscellaneous 
activities, and $155,938 for coordination with other 
agencies. 
21. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain management services. Flood Plain 
Management Services Program comes under Section 206, 
PL 86-645, 1960 Flood Control Act, as amended. Through 
technical services and planning guidance, the program 
provides information on floods and flood related information 
to improve planning for the careful use of the nation's 
flood plains, thereby reducing the potential for losses to 
life and property from floods and wave actions. Federal 
and non-Federal agencies and the private sector are 
assisted with flood hazard evaluation and planning information 
for flood and coastal hazard areas. This assistance 
is in the form of local flood plain regulations, 
National Flood Insurance requirements, and Executive 
Order 11988 requirements for federal agencies. Such 
assistance may include flood information and timing, 
floodwater velocity, extent of flooding, duration of flooding, 
flood frequency and regulatory floodway limits. 
Services accomplished during fiscal year. Requests 
and responses for technical services and planning 
assistance totaled 1,330. Of this total, 169 were from 
other federal agencies, 840 from non-Federal agencies, 
and 321 from individuals, realtors, corporations, lending 
institutions, engineers, architects and others. Of the 
1,330 requests, assistance resulted in 2,129 site specific 
responses. Costs for providing Flood Plain Management 
services during the fiscal year were $277,389. 
Hydrologic Studies. Storm studies cost was $4,889. 
Total costs for collection and study of basic data during 
the fiscal year were $282,277. 
36-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
22. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
COCONUT POINT, NU'UULI, TUTUILA 
ISLAND, AMERICAN SAMOA 
Section 501 of the Water Resources Development Act of 
1986 authorized the construction of a revetment to protect 
communal lands and public facilities at Coconut 
Point, Tutuila Island, American Samoa. Funds were 
provided to initiate a limited scope reconnaissance study. 
Additional information indicated 20 to 30 structures in 
critical areas, about 10 to 20 feet from the eroding shoreline. 
Formulation of a smaller plan that addresses only 
critical reaches of shoreline rather than the wider reaches 
originally evaluated could result in sufficient benefits to 
justify the project. A letter report was completed in 
August 1989 and concluded that shore protection measures 
were not economically justified and the study was 
subsequently terminated. Total costs incurred during the 
Fiscal Year were $25,561. 
36-6

PACIFIC OCEAN DIVISION 
TABLE 36-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
In Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
1. Agat Harbor, Guam 
(Federal Funds) 
(Contributed 
Funds) 
2. Barbers Point 
Harbor, Oahu, HI 
(Federal Funds) 
(Contributed 
Funds) 
3. Kaulana Bay Boat 
Harbor, Hawaii, HI 
(Federal Funds) 
4. Kawaihae Small 
Boat Harbor, 
Hawaii, HI 
(Federal Funds) 
5. Laupahoehoe Harbor, 
Hawaii, HI 
(Federal Funds) 
(Contributed 
Funds) 
6. Maalaea Harbor 
Maui, HI 
(Federal Funds) 
9. Lepua Area, 
American Samoa 
(Federal Funds) 
10. Masefau Bay, 
American Samoa 
(Federal Funds) 
11. Sand Island Shore 
Protection, HI 
(Federal Funds) 
13. Agana River, Guam 
(Federal Funds) 
14. Alenaio Stream, 
Hawaii, HI 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
52,000 1,196,000 409,700 
52,808 52,808 1,209,680 
-4,155,000 -200,000 
1,485,293 -87,348 
58,485 110,159 
-35,600 
1,208 
10,698 
--- 1,093,987 207,854 
--- 790,293 175,605 
--- -154,000 
28,044 40,616 
--- 8,452 
--- 12,000 
--- 9,193 1,743 
--- 170,000 
--- 149,759 
68,000 22,000 3,195,000 
76,793 26,172 3,027,525 
--- --- 365,000 
--- --- 151,000 
-115,986 
181,416 181,416 
--- 200,000 
--- 125,660 
8,000 60,000 
23,067 24,966 
6,062 
31,050 
--- 25,000 
--- 21,679 
--- 25,000 
402 23,651 
--- 250,000 
--- 117,422 125,965 
--- 300,000 
--- 107,388 
15,000 
7,308 
8,000 
3,018 
177 
5,762 
96,000 
261,384 
36-7 
2,000,000 
1,998,827 
1,301,841 
965,898 
53,391,500 
53,307,319 
4,249,670 
2,391,892 
171,400 
170,336 
170,000 
149,759 
3,623,450 
3,336,226 
365,000 
332,416 
395,000 
320,660 
268,000 
256,323 
33,000 
24,697 
172,500 
171,328 
250,000 
249,149 
396,000 
368,772

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 36-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
In Text Project Funding FY86 FY87 FY88 FY89 Sept. 30, 1989 
15. Kahawainui Stream, New Work: 
Oahu, HI Approp. 160,000 30,000 --- 3,220,000 3,600,000 
(Federal Funds) Cost 119,520 65,805 7,700 2,122,548 2,500,223 
(Contributed Contrib. --- --- --- 510,000 510,000 
Funds) Cost --- --- --- 307,910 307,910 
16. Kahoma Stream, New Work: 
Maui, HI Approp. 87,000 5,800,000 2,087,000 1,607,000 10,350,000 
(Federal Funds) Cost 82,959 2,350,275 3,297,665 3,056,250 9,545,665 
(Contributed Contrib. --- 416,550 311,440 -209,164 518,826 
Funds) Cost --- 104,911 164,744 146,882 416,537 
19. Nanpil River New Work: 
Hydropower, Approp. 6,000,000 530,000 500,000 --- 7,204,000 
Pohnpei, FSM Cost 1,786,232 4,090,598 703,045 290,511 7,024,924 
(Federal Funds) 
36-8

PACIFIC OCEAN DIVISION 
TABLE 36-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. 
Oct. 27, 1965 
4. 
Oct. 27, 1965 
6. 
Aug. 3, 1968 
Nov. 17, 1986 
Nov. 17, 1986 
Oct. 22, 1976 
BARBERS POINT HARBOR, OAHU, HAWAII 
An entrance channel 42 feet deep, 450 feet wide, and 
3,100 feet long; an inshore basin of about 46 acres, 
28 feet deep, a breakwater on the north side of the 
entrance channel, if model study shows it to be necessary; 
spending beaches with wave absorbers within the harbor 
totaling 1,320 feet in length; and a main access channel 
12 feet deep, 80 feet wide, and 1,200 feet long to a smallboat 
harbor on the west side of the deep-draft harbor to 
be developed by local interests. 
KAWAIHAE SMALL BOAT HARBOR, HAWAII, HAWAII 
An 850-foot long, 120-foot wide, and 12-foot deep 
entrance channel; a 1.2 acre and 12-foot deep existing 
turning basin; a 640-foot long, 80-foot wide, and 8-foot 
deep access channel; a 1,225-foot long west protective revetstructure; 
a 1,050-foot long east protective revetted structure 
a 400-foot long wave absorber; and a 2.5 acre, 650-foot long 
revetted offshore island 
MAALAEA HARBOR, MAUI, HAWAII 
A 620-foot long extension of the south breakwater, 
a new 610-foot length, 150 to 180-foot width, 12 to 
15-foot depth entrance channel, a 1.7 acre and 12-foot 
depth turning basin and a 720-foot length, 80-foot 
width and an 8-foot deep access channel 
AGANA RIVER, GUAM 
A levee system and channel improvements 
extending seaward consisting of 1,300-feet of 
concrete-lined channel, 410-feet of riprap and unlined 
channel, 850-feet of earth levee, 1,700-feet of floodwall, 
interior drainage improvements, minor modifications 
to the Marine Drive Bridge and a new bridge at the 
Saylor Street crossing. 
ALENAIO STREAM, HAWAII, HAWAII 
Project consists of approximately 1,640-feet of 
concrete-lined channel; floodproofing five individual 
structures, relocation of one public and six residential 
structures and incorporating floodplain management 
regulations for undeveloped areas 
KAHOMA STREAM, MAUI, HAWAII 
A debris basin 100-feet wide and 700-feet long with a 
capacity of 22,000 cubic yards; a rock sill, a diversion 
levee which is 80-feet long to direct flows into the 
concrete channel; a concrete trapezoidal channel about 
5,280-feet long; three concrete bridges with clear span of 
50 feet; and revetted outlet extending 70 feet seaward of 
the stream mouth. 
H. Doc. 93, 89th Cong., 
1st sess. 
Sec 301, PL 89-298 
Cong., 1st sess. 
Sec 101, PL 90-438 
Cong., 2nd sess. 
Sec 401, PL 99-662 
Sec 401, PL 99-662 
H. Doc 94-488, 94th 
Cong.,2nd sess. 
36-9 
13. 
14. 
16.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 36-B (Cont'd) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
19. 
Mar. 20, 1980 
Dec. 8, 1983 
NANPIL RIVER HYDROPOWER, POHNPEI, FSM 
Construction of a hydroelectric power facility. 
Appropriation of funds for a feasibility study 
and construction of a hydroelectric project. 
Sec. 101, PL 96-205 
Sec. 2, PL 98-213 
36-10

PACIFIC OCEAN DIVISION 
TABLE 36-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Agana Small Boat Harbor, Guam 
Auasi Harbor, American Samoa 
Aunuu Harbor, American Samoa 
Haleiwa Small Boat Harbor, Oahu, Hawaii 
Heeia-Kea Small Boat Harbor, Oahu, Hawaii 
Hilo Harbor, Hawaii, Hawaii 
Honokohau Small Boat Harbor, Hawaii, Hawaii 
Honolulu Harbor, Oahu, Hawaii 
Kahului Beach Road, Maui, Hawaii 
Kahului Harbor, Maui, Hawaii 
Kailua Small Boat Harbor, Oahu, Hawaii 
Kalaupapa Harbor, Molokai, Hawaii 
Kaunakakai Harbor, Molokai, Hawaii 
Kawaihae Harbor, Hawaii, Hawaii 
Keehi Lagoon, Oahu, Hawaii 
Kikiaola Small Boat Harbor, Kauai, Hawaii 
Lahaina Small Boat Harbor, Maui, Hawaii 
Manele Bay Small Boat Harbor, Lanai, Hawaii 
Maunalua Bay Small Boat Harbor, Oahu, Hawaii 
Nawiliwili Harbor, Kauai, Hawaii 
Nawiliwili Small Boat Harbor, Kauai, Hawaii 
Ofu Small Boat Harbor, American Samoa 
Pohoiki Bay, Hawaii, Hawaii 
Port Allen Harbor, Kauai, Hawaii 
Reeds Bay Small Boat Harbor, Hawaii, Hawaii 
Rota Harbor, CNMI 
Saipan Small Boat Harbor, CNMI 
Tau Small Boat Harbor, American Samoa 
Waianae Small Boat Harbor, Oahu, Hawaii 
Welles Harbor, Midway Island 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Deferred 
Completed 
Completed 
Active 
Inactive 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Active 
Completed 
Active 
Completed 
Completed 
Completed 
1978 
1982 
1982 
1978 
1972 
1982 
1971 
1985 
1976 
1984 
1967 
1968 
1966 
1981 
1956 
1981 
1977 
1986 
1972 
1987 
1976 
1976 
1979 
1984 
1967 
1985 
1982 
1985 
1979 
1950 
$ 937,7981 
1,033,015 2 
1,783,129 3 
527,047 4 
1,481 
5,423,440 
781,036 5 
16,044,095 6 
751,867 
7,203,2218 
157,997 
138,188 
5,983,5019 
3,348,000 10 
193,000 
186,937 
372,00011 
30,378 
2,127,724 12 
584,51313 
980,01814 
432,523 7 
752,64515
16 
2,000,000 17 
194,000 
1,991,569 18 
1,940,011 19 
2,448,056 20 
$ 49,919 
163,987 
208,902 
--- 
3,681,053 
63,693 
2,087,112 
--- 
6,750,442 
--- 
3,127 
292,441 
61,800 
41,857 
--- 
423,622 
--- 
9,227,500 
30,707 
668,354 
--- 
884,833 
85,123 
--- 
65,000 
98,363 
2,111 
1Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $282,474 for Construction. 
2Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $86,563 for Construction. 
3Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $231,437 for Construction. 
4Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $410,077 for Construction and $84,388 for Operation and 
Maintenance. 
6In addition, Contributed Funds of $630,568 for Construction. 
6In addition, Contributed Funds of $201,282 for Construction. 
7Authorized by the Chief of Engineers. 
8In addition, Contributed Funds of $30,200 for Construction. 
9In addition, Contributed Funds of $62,102 for Construction. 
1�Abandonment authorized by R & H Act of 1965 (HD 98, 89th 
Congress, 1st Session). 
11In addition, Contributed Funds of $370,845 for Construction. 
12In addition, Contributed Funds of $223,261 for Construction. 
13Authorized by the Chief of Engineers and completed in November 
1974. In addition, Contributed Funds of $405,471 for Construction. 
1 4Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $61,953 for Construction. 
15In addition, Contributed Funds of $200,000 for Construction. 
'16Reclassified from deferred to active category on May 16, 1983. 
'7 Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $774,373 for Construction. 
"1Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $54,034 for Construction. 
19In addition, Contributed Funds of $1,791,068 for Construction. 
20 Completed in 1941 and Maintenance transferred to Department 
of Navy. 
36-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 36-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Afono Area and Aoa Area, American Samoa Completed 1978 $ 254,0151 $ ... 
Asquiroga Bay, Guam Completed 1986 227,1812 ... 
Haleiwa Beach, Oahu, Hawaii Completed 1967 240,148 3 --- 
Kaaawa Beach, Oahu, Hawaii Completed 1976 176,488 "--- 
Kapaa Town, Kauai, Hawaii Completed 1977 158,916 b -"- 
Kekaha Beach, Kauai, Hawaii Completed 1981 999,9966 - 
Kihei Beach, Maui, Hawaii Completed 1972 154,313' --- 
Kualoa Regional Park, Oahu, Hawaii Terminated 1982 355,472 8--- 
Matafao Shoreline, American Samoa Completed 1984 225,000 2 ... 
Ofu Airstrip, American Samoa Completed 1987 189,500 --- 
Pago Pago Airport, American Samoa Completed 1984 174,941 2 
Pago Pago to Nuuuli, American Samoa Deferred 1978 394,187 --- 
Poloa Area, American Samoa Completed 1978 136,04010 . 
Sand Island, Oahu, Hawaii Completed 1981 301,879 " --- 
Vatia Area, American Samoa Completed 1978 154,30912 . 
Waikiki Beach, Oahu, Hawaii Deferred 1979 729,087 13 93,000 
1Authorized by the Chief of Engineers. In addition, $209,549 in 
Contributed Funds. 
2Authorized by the Chief of Engineers. 
3In addition, $160,098 in Contributed Funds. 
4Authorized by the Chief of Engineers. In addition, $97,075 in 
Contributed Funds. 
"Authorized by the Chief of Engineers. In addition, $56,916 in 
Contributed Funds. 
6Authorized by the Chief of Engineers. In addition, $1,672,524 in 
Contributed funds. 
7Authorized by the Chief of Engineers. In addition, $1,672,524 in 
Contributed Funds. 
8Authorized by the Chief of Engineers and terminated in April 
1980 as a Circuit Court ruled sand mining to be illegal. In addition, 
$177,300 in Contributed Funds. 
9Authorized by the Chief of Engineers. In addition, $312,480 in 
Contributed Funds. 
1�Authorized by the Chief of Engineers. In addition, $101,547 in 
Contributed Funds. 
1"Authorized by the Chief of Engineers. In addition, $255,728 in 
Contributed Funds. 
12Authorized by the Chief of Engineers. In addition, $132,075 in 
Contributed Funds 
13In addition $82,000 in Advanced Funds and $17,640 in Contributed 
Funds. 
36-12

PACIFIC OCEAN DIVISION 
TABLE 36-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1989 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Asan Village, Guam Completed 1986 $ 1,275,500 $ --- 
Hanapepe River, Kauai, Hawaii Completed 1967 784,8671- 
Iao Stream, Maui, Hawaii Completed 1985 12,285,000 --- 
Kaneohe-Kailua Area, Oahu, Hawaii Completed 1985 25,552,400 2 
Kaunakakai Stream, Molokai, Hawaii Completed 1950 73,478 3 --- 
Kawainui Swamp, Oahu, Hawaii Completed 1967 1,265,567 --- 
Kuliouou Stream, Oahu, Hawaii Completed 1971 1,000,000 --- 
Namo River, Guam Completed 1982 2,416,314 3 --- 
Paauau Stream, Hawaii Completed 1985 1,978,514 --- 
Wailoa Stream and Tributaries, Hawaii, Hawaii Completed 1966 1,044,888 --- 
'In addition, $11,953 in Contributed Funds. 
2Includes Non-Federal reimbursement of recreation construction 
cost of $5,668,300. In addition, $8,175 in Contributed Funds. 
3Authorized by the Chief of Engineers. 
4Authorized by the Chief of Engineers. In addition, $540,335 in 
Contributed Funds. 
36-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 36-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report for: Authority Expended Expended 
Ala Wai Harbor, Oahu, Hawaii 1976 November 1986 $ 40,117 --- 
PL 99-662 
Hana Small Boat Harbor, Maui, Hawaii 1967 November 1977 
HD #94-413 
Hanalei Small Boat Harbor, Kauai, Hawaii 1967 November 1981 
HD #97-59 
Hanapepe Bay, Kauai, Hawaii 1965 November 1986 
PL 99-662 
Kaimu Black Sand Beach, Hawaii, Hawaii 1975 July 1981 86,235 
Director of 
Civil Works 
Kapaakea Homestead Flood Control, 1979 July 1981 221,500 
Molokai, Hawaii Director of 
Civil Works 
Kewalo Harbor, Oahu, Hawaii 1976 September 1975 98,800 
Director of 
Civil Works 
Talofofo Bay Shore Protection, Guam --- August 1981 80,764 
Director of 
Civil Works 
Waimea Beach, Kauai, Hawaii --- November 1986 --- 
PL 99-662 
Wake Island Harbor, Wake Island 1950 November 1986 --- 
PL 99-662 
36-14

TABLE 36-H 
PACIFIC OCEAN DIVISION 
NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645, AS AMENDED 
(PREAUTHORIZATION) 
Study Fiscal Year Costs 
Ewa Beach Landing, Oahu, Hawaii 15,030 
Kahului Small Boat Harbor, Maui, Hawaii 38,066 
Mahukona (North Kohala), Hawaii, Hawaii 15,312 
TOTAL $68,408 
TABLE 36-I EMERGENCY STREAMBANK AND SHORELINE 
PROTECTION ACTIVITIES 
PURSUANT TO SECTION 14, 
PUBLIC LAW 79-526, AS AMENDED 
(PREAUTHORIZATION) 
Study 
Aunuu Harbor Erosion Control, American Samoa 
Kihei Shoreline Protection, Maui, Hawaii 
Lauliifou Shoreline Protection, American Samoa 
Olosega Bridge Protection, American Samoa 
Poloa Seawall, American Samoa 
Saipan Beach Road, CNMI 
Waimea River, Kauai, Hawaii 
TOTAL 
TABLE 36-J 
Fiscal Year Costs 
$ 26 
803 
31,764 
27,088 
28,806 
29,215 
1,841 
$119,543 
BEACH EROSION CONTROL ACTIVITIES 
PURSUANT TO SECTION 103, 
PUBLIC LAW 87-874 
(PREAUTHORIZATION) 
Study Fiscal Year Costs 
Amouli-Tula, American Samoa 
Canneries to Breakers Point, American Samoa 
East Agana, Guam 
Lauliituai-Aumi, American Samoa 
Nua-Amaluia, American Samoa 
Tau-Faleasao, American Samoa 
TOTAL 
$67,359 
59,253 
20,812 
75,782 
60,834 
40,573 
$324,613 
36-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 36-K FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858, AS AMENDED 
(PREAUTHORIZATION) 
Study 
Garapan Area, CNMI 
Kawainui Marsh, Oahu, Hawaii 
Kihei Area, Maui, Hawaii 
Lake Susupe, CNMI 
Malaekahana Stream, Oahu, Hawaii 
Malaeloa Stream, American Samoa 
Vaipito Stream, American Samoa 
Waiawa Stream, Oahu, Hawaii 
Waikomo Stream, Kauai, Hawaii 
Fiscal Year Costs 
$74,458 
10 
6,903 
1,516 
20,000 
84,926 
50,711 
25,003 
42,868 
Total $306,395 
TABLE 36-L FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 208, 
PUBLIC LAW 83-780, AS AMENDED 
(PREAUTHORIZATION) 
Study 
Waimea River, Kauai, Hawaii 
Fiscal Year Costs 
$34,828 
Total $34,828 
TABLE 36-M INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Study Date Inspected 
Asan River, Guam 
Hanapepe River, Kauai, Hawaii 
Iao Stream, Maui, Hawaii 
Kaneohe-Kailua Dam, Oahu, Hawaii 
Kaunakakai Stream, Molokai, Hawaii 
Kawainui Swamp, Oahu, Hawaii 
Kuliouou Stream, Oahu, Hawaii 
Namo River, Guam 
Paauau Stream, Hawaii, Hawaii 
Wailoa Stream, Hawaii, Hawaii 
Waimea River, Kauai, Hawaii 
April 1989 
November 1988 
February 1989 
October 1988 
October 1988 
October 1988 
October 1988 
April 1989 
April 1989 
December 1988 
December 1988 
November 1988 
February 1989 
36-16

PORTLAND, OR DISTRICT * 
The territorial limits of the Portland District include the 
Pacific coastal drainage area of the State of Oregon, the 
portions of the States of Oregon and Washington which lie 
within the Columbia River watershed downstream of the 
Umatilla Bridge below McNary Dam, and south central 
Oregon west of the Malheur River and the Steens 
Mountains, but not including that part which drains into the 
Klamath Lake and River. 
IMPROVEMENTS 
Navigation Page 
1. Bonneville Navigation Lock, Bonneville Dam, 
OR and WA .......................... 37-2 
2. Chetco River, OR ......................... 37-2 
3. Columbia and Lower Willamette Rivers below 
Vancouver, WA, and Portland, OR ........... 37-2 
4. Columbia River at Baker Bay, WA ........... 37-3 
5. Columbia River between Chinook, WA and 
Head of Sand Island ....................... 37-4 
6. Columbia River at the Mouth, OR and WA ... 37-4 
7. Columbia River between Vancouver, 
WA and The Dalles, OR. ................... 37-4 
8. Coos Bay, OR ............................. 37-5 
9. Coos and Millicoma Rivers, OR .............. 37-6 
10. Coquille River, OR ................ ...... 37-6 
11. Depoe Bay, OR .......................... 37-6 
12. Elochoman Slough, WA ... .. ..... ..... 37-7 
13. Navigation Work Under Special Authorization . 37-7 
14. Port Orford, OR ........................ 37-7 
15. Project Condition Surveys .................. 37-7 
16. Rogue River Harbor at Gold Beach, OR ...... 37-7 
17. Siuslaw River, OR ......................... 37-8 
18. Skamokawa Creek, WA .................... 37-8 
19. Skipanon Channel, OR ..................... 37-8 
20. Tillamook Bay and Bar, OR ................. 37-9 
21. Tongue Point, OR ........................ 37-9 
22. Umpqua River, OR .................... 37-9 
23. Willamette River at Willamette Falls, OR .... 37-10 
24. Yaquina Bay and Harbor, OR ............. 37-10 
Flood Control 
25. Applegate Lake, Rogue River Basin, OR ..... 
26. Blue River Lake, OR ..................... 
27. Cottage Grove Lake, OR ................. 
28. Dorena Lake, OR ........................ 
29. Elk Creek Lake, Rogue River Basin, OR ..... 
30. Fall Creek Lake, OR ...................... 
31. Fern Ridge Lake, OR ..................... 
32. Flood Control Work Under 
Special Authorization ..................... 
37-11 
37-11 
37-12 
37-12 
37-12 
37-13 
37-13 
37-14 
33. Inspection of Completed Flood Control Projects37-14 
Page 
34. Inspection of Non-Federal Flood Projects .... 37-14 
35. Lower Columbia River Basin, OR and WA ... 37-14 
36. Lower Columbia River Basin Bank Protection, 
OR and WA. .......................... 37-15 
37. Mt. St. Helens & Vicinity, WA ............. 37-15 
38. Mt. St. Helens Sediment Control, 
Castle Rock, WA ...................... 37-15 
39. Scheduling Flood Control Reservoir Operations 37-16 
40. Willamette River Basin, OR ............... 37-16 
41. Willamette River Basin Bank Protection, OR . 37-16 
42. Willow Creek Lake, Heppner, OR .......... 37-17 
Multiple-Purpose Projects, Including Power 
43. Bonneville Lock and Dam -- 
Lake Bonneville, OR and WA. ............. 
44. Cougar Lake, OR ........................ 
45. Detroit Lake, OR ........................ 
46. Green Peter-Foster Lakes, OR ............ 
47. Hills Creek Lake, OR ..................... 
48. John Day Lock and Dam -- 
Lake Umatilla, OR and WA................ 
49. Lookout Point Lake, OR .................. 
50. Lost Creek Lake, Rogue River Basin, OR .... 
51. The Dalles Lock and Dam -- 
Lake Celilo, WA and OR .................. 
37-17 
37-18 
37-18 
37-19 
37-19 
37-20 
37-20 
37-21 
37-21 
General Investigations 
52. Surveys ................................ 37-22 
53. Collection and Study of Basic Data .......... 37-22 
Tables 
Table 37-A 
Table 37-B 
Table 37-C 
Table 37-D 
Table 37-E 
Table 37-F 
Cost & Financial Statement ....... 37-23 
Authorizing Legislation ........... 37-30 
Other Authorized Navigation Projects 37-37 
Not Applicable 
Other Authorized Flood 
Control Projects ................ 37-38 
Other Authorized Multiple Purpose 
37-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Projects, Including Power ......... 37-40 
Table 37-G Deauthorized Projects ............ 37-41 
Table 37-H Columbia and Lower Willamette River 
Below Vancouver, WA and 
Portland, OR ................... 37-42 
Table 37-I Navigation Activities Pursuant to 
Section 107, Public Law 86-645 .... 37-42 
Table 37-J Project Condition Surveys ......... 37-42 
Table 37-K Willamette River at Willamette Falls, 
OR, Principal Features of Existing 
Canal and Locks ................ 37-43 
Table 37-L Flood Control Activities Pursuant to 
Section 205, Public Law 80-858 .... 37-43 
Table 37-M Flood Control Reservoir Operations 37-43 
Table 37-N Lower Columbia River Basin, 
OR and WA, Levees and Improvements 
to Existing Works ................ 37-44 
Table 37-0 Willamette River Basin 
Comprehensive Plan ............. 37-45 
Table 37-P Principal Data Concerning Navigation 
Lock, Spillway Dam, and Powerplant 37-46 
Navigation 
1. BONNEVILLE NAVIGATION LOCK, 
BONNEVILLE DAM, OR AND WA 
Location. On Columbia River 40 miles east of Portland, 
OR about 146 miles above mouth of river. 
Existing project. The existing lock chamber is 76 feet wide 
and 500 feet long with 24.2 feet depth of water over the sill. 
Construction of a new navigation lock just south of the existing 
lock was authorized in the FY 1985 Supplemental Appropriations 
Act, Public Law 99-88, August 15, 1985. Inland 
Waterways Trust Fund will fund 50 percent of the project 
cost in accordance with the Water Resources Development 
Act of 1986, Public Law 99-662, November 17, 1986. The 
new lock chamber will be 86 feet wide and 675 feet long with 
19 feet depth of water over the sill. Estimated cost for construction 
of the new navigation lock is $328,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New Work: A contract for 
construction of the upstream guardwall was awarded in January 
1989. Design effort continued for the lock structure 
throughout fiscal year 1989. 
2. CHETCO RIVER, OR 
Location. Rises in Siskiyou Mountains of Coast Range at an 
elevation of 4,000 feet, flows for about 51 miles in a circuitous 
route, and empties into Pacific Ocean at Brookings, OR, 300 
miles south of entrance to Columbia River and 345 miles 
north of San Francisco Bay. (See National Oceanic and Atmospheric 
Administration Charts 18600 and 18203.) 
Existing project. Provides for two jetties at the mouth of 
the river. Modification of 1965 authorized an entrance channel 
120 feet wide by 14 feet deep; a barge turning basin about 
250 feet wide, 650 feet long, and 14 feet deep; and a small 
boat access channel 100 feet wide by 12 feet deep. Also 
authorized was a 450-foot extension of north jetty with an 
increase in elevation of existing portion and a protective dike 
about 1,800 feet long with a top elevation of 18 feet. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 6.9 feet 
and extreme is about 12 feet. Construction of jetties was 
completed December 1957. Removal of rock pinnacles and 
an abandoned bridge structure was accomplished in June 
1959. Under authorized modification of October 1965, two 
contracts were completed. Construction of entrance channel 
and extension of north jetty was completed in July 1969. 
Construction of a protective dike, turning basin and small 
boat access channel was completed in March 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. The Port of Brookings has developed 
tow large boat basins, one for commercial fishing boats and 
the other for sport boats, and a public boat launching ramp. 
There are four fish receiving docks and a sea-going barge 
dock for lumber loading and storage. There is also a privately 
owned marina and a Coast Guard Station. 
Operations during fiscal year. Maintenance: A total of 
20,041 cubic yards of material was removed by the contract 
hopper dredge Westport. The channel flusher Sandwick 
spent six days working at the project. 
3. COLUMBIA AND LOWER WILLAMETTE 
RIVERS BELOW VANCOUVER, WA, AND 
PORTLAND, OR 
Location. The Columbia River rises in British Columbia, 
through which it flows for 425 miles. It enters the United 
States in northeastern Washington, and empties into the 
Pacific Ocean 645 miles north of San Francisco Bay and 160 
miles south of Strait of Juan DeFuca. Total length of river is 
1,210 miles. (See NOAA Charts 18520, 1852i, 18522, 18523, 
18524, 18526, and 18531; also Geological Survey Map of 
Washington.) Willamette River rises in Cascade Range in 
western Oregon, flows northerly, and empties into Colombia 
River about 100 miles from the sea. Its length from source of 
Middle Fork is about 294 miles. Project embraces 103.5 miles 
of Columbia River below Vancouver, WA, and 14.6 miles of 
Willamette River below Portland, OR. (See NOAA Chart 
18526 and Geological Survey Map, State of Oregon.) 
Existing project. Provides for a channel 35 feet deep and 
500 feet wide from River Mile 106.5 to 105.5, the distance 
between existing highway and railroad bridges; a channel 40 
feet deep and 600 feet wide from Vancouver, WA, River Mile 
105.5 to mouth of Columbia River, River Mile 3; a turning 
basin at Vancouver, WA, 40 feet deep, 800 feet wide, and 
about 5,000 feet long; a turning basin at Longview, WA, 40 
37-2

PORTLAND, OREGON DISTRICT 
feet deep, average width of 1,200 feet, and about 6,000 feet 
long; and a channel 40 feet deep in the Willamette River with 
varying widths of 600 to 1,900 feet from the mouth (River 
Mile 0) to Broadway Bridge (River Mile 11.6) which encompasses 
Portland Harbor area, subject to provisions that channel 
from mouth of Willamette River to turning basin at Vancouver, 
WA, be limited to 500 feet in width until need for 
additional width is demonstrated by developed traffic. Existing 
project also provides for auxiliary channels 10 feet deep 
and 300 feet wide near Cathlamet, WA; 30 feet deep and 300 
feet wide in St. Helens, (Oregon); and 30 feet deep and 500 
feet wide connecting upper end of St. Helens Channel with 
main ship channel of Columbia; 24 feet deep and 200 feet 
wide along frontage of town of Rainier, OR, extended to its 
upper and lower ends to deep water in Columbia River, 8 feet 
deep and 150 feet wide from this depth in Columbia River 
through old mouth of Cowlitz River to a point about 3,000 
feet upstream from present terminus of harbor line; a channel 
from Longview Port dock downstream along pierhead 
line and past Weyerhaeuser Timber Co. plant at Longview to 
a connection with main ship channel below Mount Coffin, the 
downstream 2,400 feet of this channel to be 30 feet deep and 
300 feet wide and remainder to be.28 feet deep and 250 feet 
wide; construction of a small boat mooring basin at Astoria, 
OR, to include a sheet pile, sand-filled breakwater about 
2,400 feet long with a 30-foot roadway along its full length, 
and steel pile shore wings totaling about 1,460 feet long and 
for stone-and-pile dikes and revetments. Plane of reference 
in estuary from mouth of Harrington Point is mean lower low 
water; thence to Portland and Vancouver, adopted low water. 
Tidal range between mean lower low water and mean higher 
high water at mouth of Columbia is about 8 feet, and at 
Portland and Vancouver, about 3 feet at low stage of rivers. 
Extreme tidal ranges are about 13 and 3 feet, respectively. 
Annual freshets have little effect on stage of tide at mouth of 
Columbia; at Portland and Vancouver, they average about 12 
feet, while highest know reached a stage of 33 feet above 
water at Portland. 
Work on the 40-foot channel in Columbia River from 
Portland, OR, and Vancouver, WA, to the sea was completed 
in 1976 except for observation of channel to determine if 
additional control structures or dredging will be required. 
Auxiliary channel in vicinity of Longview was completed in 
1949, and improvement of mouth of Cowlitz River and small 
boat mooring basin at Astoria were completed in 1950. Project 
depths are maintained all year except for the period 
immediately following the annual freshet in May-June when 
shoaling occurs at several locations. Timing of vessel movement 
with tidal fluctuations permit maximum draft conditions. 
In Columbia and Willamette Rivers between mouth 
and Broadway Bridge at Portland a depth of 40 feet at low 
tide and 42 feet at high tide is practicable all year. In Columbia 
River between mouth of Willamette river and Vancouver, 
WA, depths of 40 and 42 feet at low and high tide, respectively, 
are practicable all year. (For details relating to previous 
project, see pages 1995 and 1998 of Annual Report for 
1915 and page 1746 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 37-3 of FY 1981 Annual Report. 
Terminal facilities. At Portland, OR, there are six Port of 
Portland terminals consisting of 43 berths equipped to handle 
general cargo, bulk cargo, lumber, automobiles, lift-on-liftoff 
and roll-on-roll-off containers, and breakbulk vessels. 
The Port of Portland owns and operates a major ship repair 
yard, which includes the West Coast's largest, and the world's 
third largest, floating dry dock. Also available in the harbor 
area are privately operated facilities for receiving, storing and 
outloading petroleum, wood chips, grain, logs, sand and 
gravel, cement, and steel products. 
At Astoria, OR, there is a terminal with facilities for receiving 
and handling all types of general cargo. 
At Vancouver, WA, there are municipal facilities capable 
of berthing five ships simultaneously. Each berth is completely 
outfitted with mechanical and lift facilities for receiving 
and handling all types of cargo. The port has a low dock to 
handle roll-on-roll-off and side-port discharging vessels. 
The grain terminal has a storage capacity of 4,500,000 bushels. 
Port of Longview has a public terminal on Columbia River 
and a privately owned grain elevator with a capacity of 
6,900,000 bushels. This port also has a heavy lift facility, with 
a capacity of 600 tons. 
Port of Kalama has two berthing areas, one port owned and 
one private. 
At other locations on Columbia River between Portland 
and Columbia River entrance there are sufficient private 
facilities to accommodate river vessels and fishing craft. 
These facilities, with planned extensions, are considered adequate 
for existing commerce. (For details, see Port Series 
Nos. 33 and 34, Corps of Engineers, published in 1974 and 
1975 respectively.) 
Operations during fiscal year. Maintenance: Regular 
maintenance continued through the year. A total of 
7,946,800 cubic yards of material was removed. The U.S. 
hopper dredge Essayons removed 2,918,700 cubic yards, and 
U.S. hopper dredge Yaquina removed 43,000 cubic yards. In 
addition, the pipeline dredge Oregon removed 3,699,700 cubic 
yards, the contract dredge Padre Island removed 163,500 
cubic yards, and the contract dredge Smith Rice Super Scoop 
removed 1,121,900 cubic yards. 
4. COLUMBIA RIVER AT BAKER BAY, WA 
Location. Baker Bay is a shallow body of water about 15 
square miles in extent on the north side of Columbia River 
near its mouth. The bay is separated from the river by Sand 
Island, a low-lying sand bar only a few feet above high tide 
level. (See NOAA Chart 18521.) 
Existing project. A mooring basin 10 and 12 feet deep, 
about 20 acres in extent with protecting breakwaters; and a 
west channel 16 feet deep and 200 feet wide for the first 2000 
feet, then 16 feet deep and 150 feet wide to the boat basin; a 
channel east of Sand Island to Port of Ilwaco, a distance of 
about 4 miles. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean higher 
high water is about 8 feet, and extreme about 13 feet. 
Channel extending through easterly passage of Sand Island 
was completed in 1934. This portion of authorized project is 
37-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
not passable and is not maintained at the present time. 
Dredging west channel to 8 feet was accomplished September 
1948. Deepening west channel to 10 feet, and boat basin 
and breakwater construction at Ilwaco, WA, was finished 
December 1957, and again, deepening of the west channel to 
16 feet completed in August 1985 under Section 107, finished 
the project. 
Local cooperation. Fully complied with. 
Terminal facilities. Wharves, floats, ramps, and berths, for 
fishing craft, barges and tow-boats. Small-boat basin and 
protecting breakwater provides moorings for numerous fishing 
and recreational craft all year. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: A total of 
73,400 cubic yards of material was removed. The U.S. hopper 
dredge Yaquina removed 10,000 cubic yards and the contract 
dredge Ross Island removed 63,400 cubic yards. 
5. COLUMBIA RIVER BETWEEN CHINOOK, 
WA, AND HEAD OF SAND ISLAND 
Location. At easterly end of Baker Bay, lying on north side 
of Columbia River near mouth. (See Coast and Geodetic 
Survey Chart 6151.) 
Existing Project. Channel 10 feet deep and 150 feet wide, 
extending from head of Sand Island to Chinook; a turning and 
mooring basin at upper end of channel, 10 feet deep, 660 feet 
long, and ranging from 275 to 500 feet wide; reconstruction of 
easterly 393 feet of existing breakwater; and extension of 
existing breakwater easterly and thence northerly to connect 
with shore in vicinity of Portland Street, Chinook, WA. Tidal 
range between mean lower low water and mean higher high 
water is about 8 feet and extreme about 13 feet. 
Project as originally authorized was completed in 1940. The 
10-foot channel depth modification was accomplished September 
1958. Rehabilitation of existing breakwater was completed 
September 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Chinook Packing Company owns a 
wharf for receiving fresh fish, and one additional fish buying 
company is located at Chinook. A portion of wharf is also 
used as a public landing. At upper end of channel there is a 
turning and mooring basin with facilities for mooring 350 
fishing and recreational craft. Adequate terminal and mooring 
facilities include a public launching ramp, hoist with 
10-ton capacity and suitable supply facilities. 
Operations during fiscal year. Maintenance: Contract 
clamshell dredge removed 117,600 cubic yards. 
6. COLUMBIA RIVER AT THE MOUTH, OR 
AND WA 
Location. The Columbia River entrance is 645 miles north 
of San Francisco Bay. Project is about 120 miles downstream 
of Portland, OR, and Vancouver, WA. For description of 
Columbia River see Section 4. 
Existing project. Provides for a one-half- mile-wide channel 
across a bar 55 feet deep (mean lower low water) for the 
northernmost 2,000 feet, and 48 feet deep (mean lower low 
water) along the southern 640 feet, to be secured by two 
rubblemound jetties, spur jetty "A" on the north shore and by 
dredging. The north jetty is about 2.5 miles long and the south 
jetty about 6.6 miles long, spur jetty "A" is about 0.3 miles 
long. Tidal range on bar between mean lower low water and 
mean higher high water is about 8 feet, and extreme about 13 
feet. 
The originally authorized project depth of 40 feet was completed 
in 1918; south jetty completed in 1914 and north jetty 
in 1917. A spur jetty (jetty "A") was completed in 1939 (repaired 
in 1961) for the purpose of channel stabilization. Spur 
jetty "B" currently is classified "inactive." Dredging of the 
48-foot bar channel started April 1956 was completed in 
September 1957. South jetty rehabilitation started June 1962 
was completed September 1964. North jetty rehabilitation 
started January 1965 was completed April 1965. Additional 
rehabilitation of the south jetty was initiated in May 1982 and 
completed in September 1982. Deepening bar channel to 55 
feet completed September 1984. Project dimensions were 
available at end of fiscal year. (For details relating to previous 
projects, see page 1999, Annual Report for 1915 and page 
1740 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Local interests 
contributed $500,000 toward construction of the north jetty 
which was completed in 1917. 
Operations during fiscal year. Maintenance: A total of 
4,672,200 cubic yards of material was removed. The U.S. 
hopper dredge Essayons removed 1,172,000 cubic yards of 
material, the contract dredge Padre Island removed 
2,764,100 cubic yards, and the contract dredge Newport removed 
736,100 cubic yards. 
7. COLUMBIA RIVER BETWEEN 
VANCOUVER, WA, AND THE DALLES, OR 
Location. On Columbia River, between Interstate Bridge 
at Vancouver, WA, 106.5 miles above mouth and The Dalles, 
OR, mile 191, a distance of 84.5 miles. For description of 
Columbia River, See Section 4, "Columbia and Lower Willamette 
Rivers Below Vancouver, WA, and Portland, OR." 
Existing project. Channel 27 feet deep at low water and 300 
feet wide between Vancouver, WA, and The Dalles, OR, 
84.5 miles; a channel 10 feet deep at low water and 200 feet 
wide at upstream entrance to Oregon Slough, OR; a suitable 
turning basin adjacent to site of port development in vicinity 
of Camas and Washougal, WA; a boat basin at Hood River, 
OR, 500 by 1,300 feet and 10 feet deep at normal Bonneville 
pool level, with a connecting channel of same depth to deepwater, 
and a protecting breakwater on easterly side; a barge 
channel to waterfront at Bingen, WA, 10 feet deep at normal 
Bonneville pool level, 200 feet wide and about 1 mile long, 
and an access channel 7 feet deep at normal Bonneville pool 
level, 100 feet wide and about 1,000 feet long, to a natural 
mooring basin for small boats near east end of channel; and 
construction of The Dalles small boat basin, to provide a 
breakwater and shear boom protected basin about 400 by 800 
feet in size with depth of 8 feet below a pool elevation of 72.5 
37-4

PORTLAND, OREGON DISTRICT 
feet at mean sea level. Tidal range between mean lower low 
water and mean higher high water at Vancouver is about 3 
feet and at Bonneville about 0.2 foot at low stages of the river. 
Extreme tidal ranges are about 4 feet and 0.4 foot, respectively. 
Existing project is complete. Construction of The Dalles 
small boat basin, was completed in 1949. Channel dredging at 
upper end of Oregon Slough was accomplished in 1957. Project 
depth of 27 feet between Bonneville and The Dalles, 
OR, was achieved April 1959. The 27-foot channel depth 
between Vancouver, WA, and Bonneville, OR, was completed 
May 1938. Improvement of lower entrance of Bonneville 
Dam lock was completed in May 1961. At the present 
time, the channel is maintained to a depth of 16 feet, which is 
adequate for using traffic. Construction of a boat basin at 
Hood River, OR, and of Camas-Washougal, WA, turning 
basin was accomplished February 1962. Construction of a 
barge channel in Columbia River near Bingen, WA, was 
completed September 1963. Small boat recreation channel 
100 feet wide 6 feet deep at South Channel Government 
Island completed 1985 under section 107. 
Local cooperation. Fully complied with. 
Terminal facilities. At Vancouver, WA, upstream of Interstate 
Highway bridge at River Mile 108.1 on site of former 
shipyard are numerous ship-building facilities equipped with 
railway and river moorage facilities. Also in this area are a 
paper-storage warehouse with barge slip, two boat building 
businesses, and a storage dock with gantry crane. Sites are 
available for development to suit lessee. 
At Camas, Wa, about 13.5 miles upstream from Vancouver, 
there is a private wharf used for transfer of papermill 
supplies and paper to and from barges, and facilities for 
discharging bulk oils from barges. 
At Port of The Dalles (mile 44 above Bonneville) there is a 
municipal wharf 125 by 1,100 feet for use by tugs and barges. 
There is a one-story timber and corrugated iron warehouse, 
94 by 461 feet, on this wharf. A private elevator with a capacity 
of 40,000 bushels and a public elevator of 1,113,800- 
bushel capacity for handling bulk grain to barges are also at 
The Dalles. Public elevator has rail, truck, and water connections. 
There is a port owned rail connection about threefourths 
mile below municipal wharf where certain types of 
cargo may be handled between railroad cars and barges. 
At numerous locations along the entire waterway there are 
facilities for transfer of logs to water from trucks and public 
and private boat basins. Facilities are considered adequate 
for present commerce. 
Operations during fiscal year. Maintenance: The U.S. 
hopper dredge Yaquina removed 11,780 cubic yards of material. 
8. COOS BAY, OR 
Location. On Oregon coast 200 miles south of mouth of 
Columbia River and 445 miles north of San Francisco Bay. It 
is about 13 miles long and 1 mile wide, with an area at high 
tide of about 15 square miles. (See NOAA Charts 18580 and 
18587.) 
Existing project. Two rubblemound, high- tide jetties at 
entrance; a channel across the outer bar 45 feet deep and 700 
feet wide, reducing gradually to 35 feet deep and 300 feet 
wide near River Mile 1 and continuing to about mile 9; thence 
a channel 35 feet deep and generally 400 feet wide to mile 15; 
an anchorage area 35 feet deep, 800 feet wide, and 1,000 feet 
long at Empire (River Mile 5.5); turning basins at North Bend 
(River Mile 12.5) and Coalbank (River Mile 14.7) 35 feet 
deep, 650 feet wide and 1,000 feet long; a channel 22 feet 
deep and 150 feet wide from Smith's Mill (River Mile 15) to 
Millington (River Mile 17); a small boat basin, about 500 by 
900 feet at Charleston, with a connecting channel, 16 feet 
deep, 150 feet wide and 6,200 feet long, to deep water in Coos 
Bay, and construction of a protecting breakwater and bulkhead. 
Plane of reference is mean lower low water. Tidal range 
between mean lower low water and mean higher high water is 
7 feet and extreme is about 11 feet at both the entrance and at 
Coos Bay. 
South jetty was completed in 1928, north jetty in 1929, and 
24-foot channel in 1937. The south jetty was restored in 1941 
and 1942 by construction of a concrete cap for full length of 
the jetty. Excavation of channel to 30 feet deep and generally 
300 feet wide from entrance of Isthmus Slough was completed 
in 1951. Dredging outer bar channel to a depth of 40 
feet, decreasing to 30 feet at Guano Rock was completed in 
1952. Construction of the Charleston Channel and smallboat 
basin was completed in September 1956. Rehabilitation 
of south jetty was started in June 1962 and completed December 
1963. Repair of north jetty was completed in August 
1989. Construction of the deeper and wider channel to mile 
15 was completed in 1979. Deepening of Charleston channel 
and turning basin completed in 1985 under Section 107. (For 
details relating to previous projects, see page 1987 to Annual 
Report for 1915 and page 1728 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 37-5 of FY 1981 Annual Report. 
Terminal facilities. At North Bend there is a municipal 
dock 649 feet long fronting on channel, about 2,380 feet of 
privately owned mill docks, and three oil receiving terminals 
in vicinity. 
At Coos Bay there is a privately owned dock with a frontage 
of 1,345 feet, open to the public on equal terms; several small 
landings for fishing and harbor craft; and three lumber docks 
with 1,300,576, and 500-foot frontages, respectively. 
In the North Spit industrial area, there is one woodchip 
loading facility having a frontage of 1200 feet and a smaller 
T-dock operated by the Port of Coos Bay. 
At Eastside, on Isthmus Slough, there is a 200-foot dock. 
At Empire there is a privately owned lumber dock with 
frontage of 510 feet, and an oil terminal, owned by Port of 
Coos Bay, for receipt of petroleum products by barge. A 
barge slip also owned by the Port was completed in 1986. 
At Charleston there are wharves, for receipt of fresh fish 
and shellfish and a large seafood receiving and processing 
plant. There are also two municipally owned small-boat ba- 
37-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
sins, open to all on equal terms, capable of mooring 250 
fishing and recreation craft. Servicing facilities for small craft 
are available at all facilities, and public launching ramps have 
been constructed in Charleston area by private interests. A 
privately owned floating moorage on Joe Ney Slough has 
facilities for mooring about 50 fishing vessels. 
At Jordan Cove area there is a dock, 248 feet long, for wood 
chip ships. 
These facilities are considered adequate for existing commerce. 
(For details see Port series No. 33, Corps of Engineers, 
published in 1975.) 
Operations during fiscal year. Maintenance: Total of 
811,460 cubic yards removed. U.S. hopper dredge Yaquina 
removed 334,550 cubic yards and the contract hopper dredge 
Westport removed 476,915 cubic yards of material. The 
sand-bypasser Sandwick displaced sand from shoal areas in 
Charleston entrance channel. Repair of the north jetty was 
completed in 1989. 
9. COOS AND MILLICOMA RIVERS, OR 
Location. South Fork and Millicoma Rivers rise in Coast 
Range in southern Oregon, flow generally westerly and join 
to make Coos River, 5.3 miles above mouth of Coos River in 
Coos Bay. (See NOAA Chart 18587, Allegany and Daniels 
Creek Quadrangle.) 
Existing project. Originally authorized project: A channel 
depth of 3 feet, generally, from mouth of Coos River and 1 
foot near head of navigation. Project as modified: Two channels 
5 feet deep and 50 feet wide from mouth of Coos River to 
Allegany on Millicoma River, mile 13.8 and to Dellwood on 
South Fork, mile 14, and thence a channel 3 feet deep and 50 
feet wide to mile 14.7 on South Fork, including stabilization 
works on Coos River. Mean lower low water is plane of 
reference. Tidal range between mean lower low water and 
mean higher high water at the mouth of Coos River is 7 feet 
and extreme about 11 feet. Tidal range at head of navigation 
in both forks is about 1 foot. Freshet stages usually reach a 
height of from 10 to 15 feet at Allegany, head of navigation on 
Millicoma River. 
Originally authorized project providing for a channel from 
mouth of Coos River to head of navigation in both forks, to 
provide a depth of 3 feet generally and 1 foot near head of 
navigation, was completed in 1899. In March 1966, construction 
of project was modified by 1948 River and Harbor Act 
was completed. 
Local cooperation. Fully complied with. 
Terminal facilities. Several small privately owned docks 
and landing places on the river are used by towboats and 
pleasure craft. There are no publicly owned docks. Present 
facilities are considered adequate for existing commerce. Major 
log processing yards are located at the head of navigation 
on both rivers. 
Operations during fiscal year. Maintenance: The contract 
pipeline dredge Karen removed 14,000 cubic yards. 
10. COQUILLE RIVER, OR 
Location. Rises in Coast Range, flows generally westerly 
for about 100 miles, and empties into Pacific Ocean at Bandon, 
OR, 225 miles south of mouth of Columbia River and 
420 miles north of San Francisco Bay. (See NOAA Charts 
18580 and 18186.) 
Existing project. Two rubblemound high- tide jetties at 
river mouth, south jetty 2,700 feet long and the north, 3,450 
feet long; and a channel 13 feet deep at mean lower low water 
and of suitable width from the sea to a point 1 mile above old 
Coquille River Lighthouse, and snagging to State highway 
bridge at city of Coquille. Mean lower low water is plane of 
reference. Tidal range between mean lower low water and 
mean higher high water at mouth is 7 feet and extreme about 
10 feet. 
Jetties were completed in 1908 and entrance channel in 
1933. North jetty was reconstructed in 1942 and a 750-foot 
extension to easterly end was constructed in 1951. South jetty 
was repaired in 1954 and north jetty in 1956. Coquille Lighthouse 
rehabilitation was completed June 21, 1976. Port of 
Bandon constructed boat basin facility in conjunction with 
protective breakwater and entrance channel construction in 
1985, under Section 107. (For details relating to previous 
projects, see page 1986 of Annual Report for 1915 and page 
1727 of Annual Report for 1938.) 
A plan to deepen the entrance channel of the Coquille 
River from 13 feet to 18 feet was approved in May 1988. 
Construction is planned to occur in 1991. 
Local cooperation. None required. However, restoration of 
lighthouse using Code 710, Recreation Facilities at Completed 
Projects, funding required 50 percent cost sharing with 
non-Federal sponsor (Oregon State Parks). 
Terminal facilities. At Bandon: A privately owned mill 
dock used exclusively for shipping lumber on coastwise vessels, 
a publicly owned wharf, and a small-boat basin open to 
all on equal terms. 
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 13,190 cubic yards of material from 
entrance channel. 
11. DEPOE BAY, OR 
Location. Harbor on Oregon coast 100 miles south of 
mouth of Columbia River. (See Coast and Geodetic Survey 
Chart 5902.) 
Existing project. Two breakwaters north of entrance; an 
entrance channel 8 feet deep and 50 feet wide; an inner basin 
750 feet long, 390 feet wide and 8 feet deep with retaining 
wall along easterly side; and a stone spending beach. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 8 feet 
and extreme is about 12 feet. Project as originally authorized 
was completed in 1939 and project modification, enlarging 
the basin and deepening to 8 feet, was accomplished in June 
1952 and August 1966. 
Local cooperation. Fully complied with. 
37-6

PORTLAND, OREGON DISTRICT 
Terminal facilities. Facilities, in inner basin, consist of 
landings and floats to accommodate operators of excursion 
and commercial fishing boats. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Contract 
pipeline dredge Karen removed 14,030 cubic yards of material 
from the boat basin, and contract clamshell Kaward removed 
1,000 cubic yards from sediment catch basin. 
12. ELOCHOMAN SLOUGH, WA 
Location. A side channel of Columbia River, about 3.5 
miles long, on Washington side about 75 miles below Portland, 
OR, (See Coast and Geodetic Survey Chart 6152.) 
Existing project. A channel 10 feet deep and 100 feet wide 
extending from that depth in Columbia River near easterly 
end of slough to existing terminals near mouth of Elochoman 
River, a distance of about 1.5 miles with suitable turning 
basin of same depth at inner end. Detailed project report on a 
small-boat basin at Cathlamet, WA, covering modification of 
project under Section 107 of the 1960 River and Harbor Act, 
as amended by Section 310 of the 1965 River and Harbor Act 
was approved February 9,1966 authorizing project for construction. 
Project provides for an entrance channel 50 feet 
wide and 6 feet deep, and a breakwater with a top width of 10 
feet and elevation of 12 feet. Low water is plane of reference. 
Average tidal range during low water conditions in Columbia 
River is about 5 feet. Federal costs of modified project is 
$177,769. Existing project authorized by 1937 River and Harbor 
Act (H. Doc.510, 74th Cong.,2nd sess. contains latest 
published map). 
Local cooperation. Fully complied with. Required local 
interests contribution of an estimated $19,600 is 11 percent of 
the Federal first cost of construction. An additional cash 
contribution of $67,031 was requested for accomplishment of 
local work consisting of dredging the mooring area by Federal 
contractor. 
Terminal facilities. Only terminals are privately owned 
wharves of Crown Willamette Paper Co., and International 
Wood Products Co. Present facilities are considered adequate 
for existing commerce 
Operations during fiscal year. Contract clamshell removed 
59,043 cubic yards of material. 
13. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public Law 
86-645 (preauthorization). See Table 37-I. 
Aquatic plant control (Section 302, Public Law 89-298): 
Sampling and identification of aquatic plant infestation in 
Columbia River and Willamette River Basins were accomplished. 
Total costs for fiscal year were $3,342. 
14. PORT ORFORD, OR 
Location. On Oregon coast 250 miles south of Columbia 
River entrance and 390 miles north of San Francisco Bay. 
(NOAA Chart 18203 and Geological Survey Quadrangle, 
Port Orford, OR) 
Existing project. Improvement of harbor by 55-foot extension 
of existing locally constructed breakwater and dredging 
of a turning basin, 340 feet long, 100 feet wide and 16 feet 
deep. Breakwater was completed October, 1968. Turning 
basin was completed September 1971. 
Local cooperation. Fully complied with. 
Terminal facilities. A dock which is a timber piling structure 
about 210 by 70 feet, equipped with hydraulic crane for 
lifting boats from the water to dock for repairs and/or storage 
and removing fish catches from boats. Expansion of the dock 
structure to 210 x 220 feet is 90% complete. The installation 
of the second hydraulic crane was completed in FY 1986. 
About 150 fishing and private boats use this dock each year. 
Operations during fiscal year. Maintenance: During the 
summer months, the sand-bypasser Sandwick displaced 
shoal areas to provide longer periods of channel depths for 
navigation traffic. A contract submersible pump dredge removed 
1,420 cubic yards of material which would provide 
users with adequate depths to utilize cranes during the winter 
months. 
15. PROJECT CONDITION SURVEYS 
Surveys were conducted during the fiscal year at a cost of 
$67,847; (See Table 37-J). 
16. ROGUE RIVER HARBOR AT GOLD 
BEACH, OR 
Location. Rises in Cascade Range in southwestern Oregon; 
flows westerly through Coast Range, and empties into Pacific 
Ocean 264 miles south of mouth of Columbia River and 381 
miles north of San Francisco Bay. (See NOAA Chart 18202.) 
Existing project. Two jetties at entrance, and a channel 13 
feet deep and 300 feet wide from ocean to a point immediately 
below State highway bridge, about 1 mile, including 
widening channel at a point about 0.25 mile below bridge to 
form a turning basin 13 feet deep, 500 feet wide, and 650 feet 
long. At request of local interests, turning basin was located 
in south portion of estuary downstream from a point 0.25 mile 
below bridge. This change was effected to permit adequate 
terminal facilities to be constructed adjacent to turning basin. 
Mean lower low water is plane of reference. Range of tide 
between mean lower low water nd mean higher high water is 
7 feet, and extreme about 14 feet. 
Project as authorized has been completed. Construction of 
two jetties at entrance was completed September 1960. 
Dredging river channel by contract and entrance bar by government 
plant was completed October 1961. North jetty rehabilitation 
along channel side was completed October 1966. 
Breakwater construction and dredging, under contract 
awarded in September 1964, was 17 percent accomplished 
when flood of December 1964 destroyed all completed 
works. Contract was terminated as further construction at 
that location was considered unfeasible. Bank protection 
work at Wedderburn location was completed in October 
1972. A breakwater, constructed by Port of Gold Beach, was 
37-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
completed during 1973. In 1985, three pile dikes, located on 
the south side of channel oceanward of the boat basin entrance, 
were completed. 
Local cooperation. Fully complied with. 
Terminal facilities. There are various landings for fishing 
and recreational craft. At Wedderburn, across river from 
Gold Beach, is a facility to accommodate excursion passengers 
and small freight items destined for various private landings 
between Wedderburn and Agness, OR. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: A total of 
90,140 cubic yards of material was removed. The contract 
hopper dredge Westport removed 60,000 cubic yards at the 
entrance bar. Contract pipeline dredge Karen removed 
30,410 cubic yards of material at Gold Beach boat basin 
channel. 
17. SIUSLAW RIVER, OR 
Location. Rises in coast range, flows about 110 miles westerly 
and empties into Pacific Ocean about 160 miles south of 
entrance of Columbia River and 485 miles north of San 
Francisco Bay, CA. (See NOAA Charts 19583 and 18580.) 
Existing project. Provides for 2 high- tide, rubblemound 
jetties 750 feet apart at the outer end, the north jetty 8,390 
feet long (600 feet unconstructed) and the south jetty 4,200 
feet long; an entrance channel 18 feet deep and 300 feet wide 
from deep water in ocean to a point 1,500 feet inside the 
outer end of existing north jetty; thence a channel 17 feet 
deep, 20C feet wide with additional widening at bends, and 
about 5 miles long, to a turning basin, 16 feet deep, 200 feet 
wide with additional widening at bends, and about 5 miles 
long, to a turning basin, 16 feet deep, 400 feet wide, and 600 
feet long, opposite Siuslaw dock at Florence; a channel 12 
feet deep, 150 feet wide from Florence to mile 16.5; and at 
River Mile 15.5 a turning basin 12 feet deep, 300 feet wide 
and 500 feet long. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean 
higher high water at mouth of river is 7 feet and extreme 
about 11 feet. During low stages of river, tidal effect extends 
to Mapleton, 20.5 miles above mouth. (For details relating to 
previous project, see page 1988 of Annual Report for 1915.) 
A modification to the existing project was authorized by 
Public Law 96-367, October 1, 1980. North and south jetty 
modifications were completed in FY 85. Modifications provide 
for extending the north and south jetties by 1,900 and 
2,300 feet respectively. The jetty extensions will terminate at 
approximately the minus 25-foot contour. Spur jetties were 
constructed on each jetty extension to reduce longshore currents 
from transporting material around the heads of the 
jetties. Each spur jetty is 400 feet long and originate approximately 
900 feet shoreward of the jetty head. The north jetty 
spur is oriented 45 degrees to the north of the existing jetty 
alignment and the south jetty spur 45 degrees to the south of 
the jetty alignment. Work on the extension of the north and 
south jetties was completed on 31 December 1986. 
Local cooperation. Fully complied with. 
Terminal facilities. Port dock at Florence, 150 feet wide 
and 350 feet long, is about 5.3 miles above river entrance and 
accommodates a fish-receiving station at east end of wharf 
which maintains a 2-ton capacity winch and supplies gasoline, 
oil and ice to fishermen. Other facilities at Florence consist of 
various floatways which provide docking facilities for fishing 
vessels and other small craft and a floating dock with accommodations 
for 75 commercial fishing vessels. Adjacent to 
commercial basin is mooring basin with accommodations for 
200 sport boats of all sizes. 
Modern docks for loading ocean-going barges with packaged 
lumber is maintained at Mapleton and owned by the 
Davison Lumber Company. 
There are also a number of private landings and log booms 
between Cushman and Mapleton to accommodate river traffic. 
These facilities are considered adequate for existing traffic.
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 116,800 cubic yards of material. 
18. SKAMOKAWA CREEK, WA 
Location. Rises in Wahkiakum County, in southwestern 
part of the State of Washington, flows southwesterly and 
southerly about ten miles, and empties into the Columbia 
River about 34 miles above the mouth (see NOAA Chart 
18523). 
Existing project. Provides for a channel 6.5 feet deep at low 
water and 75 feet wide, between Steamboat and Brooks 
Sloughs, about 1,600 feet long. Tidal range between mean 
lower low water and mean higher high water is about seven 
feet and maximum variation of water level due to tides or 
freshets is about 12 feet. During ordinary freshets a stage of 
12 feet is reached in creek at Skamokawa, WA. Project as 
authorized was completed in 1920. 
Local cooperation. None required. 
Terminal facilities. There are several privately owned 
docks on Skamokawa Creek, Steamboat Slough, and Brooks 
Slough for use of towboats, commercial fishing vessels, and 
pleasure craft. 
Operations during fiscal year. Maintenance: The sandbypasser 
SANDWICK displaced shoals in the channel. 
19. SKIPANON CHANNEL, OR 
Location. In tidal waterway extending south 2.7 miles from 
deep water in Columbia River. Channel enters Columbia 
about 10 miles above mouth and 4 miles below Astoria, OR. 
(See NOAA Chart 18523.) 
Existing project. Channel 30 feet deep and generally 200 
feet wide extending from deep water in Columbia River to 
railroad bridge at Warrenton, OR, distance of 1.8 miles, 
turning basin of same depth, mooring basin 12 feet deep at 
mean lower low water at Warrenton, OR, and channel 7 feet 
deep, generally 40 feet wide, with increased widths at log 
dumps and terminals, for 4,500 feet via cutoff channel above 
railroad bridge. Channel is maintained to 16 feet which is 
adequate for user traffic. Mean lower low water is plane of 
37-8

PORTLAND, OREGON DISTRICT 
reference. Tidal range between mean lower low water and 
mean higher high water is about 8 feet, extreme is about 13 
feet. 
Project as authorized is complete. Dredging river channel 
and turning basin was completed in 1939. Construction of 
small-boat mooring basin at Warrenton, OR, was completed 
October 1957, and fill stabilization work was accomplished in 
August 1958. 
Local cooperation. None required. 
Terminal facilities. City of Warrenton owns wharf with a 
300-foot frontage open to pubic on equal terms. One privately 
owned cannery wharf with a 300-foot frontage is used 
for unloading fish and handling fish nets. One privately 
owned boatyard has floats and moorage facilities for use by a 
maximum of 80 small boats. Small-boat basin has facilities 
for numerous fishing and recreation craft, and a privately 
owned lumber mill has a barge loading facility for chips and 
lumber. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: The U.S. hopper 
dredge Yaquina removed 23,400 cubic yards of material. 
20. TILLAMOOK BAY AND BAR, OR 
Location. Bay is on Oregon coast about 50 miles south of 
mouth of Columbia River. (See NOAA Charts 18520 and 
18558.) 
Existing project. Provides for a jetty about 5,700 feet long 
on north side of entrance and a jetty 8,000 feet long on south 
side; a channel through bar 18 feet deep and of such width as 
can be practically and economically obtained; for a channel 
200 feet wide and 18 feet deep from deep water in bay to 
Miami Cove; and for initial dredging to 12 feet deep of a 
small-boat basin and approach thereto at Garibaldi, OR. 
Project also provides for improvement of Bayocean Peninsula, 
OR, by construction of sand and rockfill dike 1.4 miles 
long, on alignment extending between Pitcher Point and 
town of Bayocean. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean 
higher high water is 8 feet, extreme is about 14 feet. Hobsonville 
Channel portion of project is inactive. 
Except for construction of Hobsonville Channel portion, 
classified inactive, channels were completed in 1927, north 
jetty in 1933, improvement of Bayocean Peninsula in 1956, 
and small-boat basin in 1958. Rehabilitation of north jetty 
was initiated April 1969 and was completed in September 
1979. 18 foot channel to Miami Cove is inactive due to mill 
closure. (For details relating to previous projects, see page 
1989 of Annual Report for 1915 and page 1474 of Annual 
Report for 1936.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 37-9 of FY 1981 Annual Report. 
Terminal facilities. At Garibaldi: A facility owned by the 
Port of Bay City, for shipping lumber and receiving logs, a 
public landing suitable for mooring fishing vessels, towboats, 
and other craft. Small-boat basin has adequate facilities for 
mooring fishing and recreational craft. A privately owned 
boat ramp and moorage is available for recreational craft. 
At Bay City: A privately owned wharf used exclusively for 
receipt of fresh fish and shellfish. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys, miscellaneous inspections and reports were performed. 
A reconnaissance report was initiated to evaluate 
deterioration of the north jetty. 
21. TONGUE POINT, OR 
Location. The northwest corner of Oregon at river mile 18 
on the Columbia River, five miles east of the city of Astoria, 
OR. 
Existing project. Tongue Point is located adjacent to the 
congressionally authorized Columbia River 40-foot deepdraft 
navigation channel. The harbor and port facilities were 
first developed in the 1930's as a U.S. navel base. After World 
War II the site served as a temporary berthing area. The 
improvements, however, have not been actively maintained 
for 25 years. The State of Oregon obtained the majority of the 
port development in 1980 from the Federal Government, 
including five finger piers. The remaining acres and three 
finger piers are still federally owned and used by the U.S. 
Department of Commerce as a Job Corps Center and the 
U.S. Coast Guard as a lifeboat station. Construction of a 
34-foot deep by 350-foot wide channel 1.75 miles long from 
the existing Columbia River channel to Tongue Point docks 
was authorized in July 1989 under section 107 of the 1960 
Rivers and harbors Act, as amended A 25-foot deep (mllw) 
by 1,050-foot wide turning basin is also being constructed and 
will be located near the piers. The estimated cost of the 
project is $4,328,259 of which $2,530,000 is federal costs and 
$1,798,259 non-federal. 
Local cooperation. The State of Oregon, acting through the 
Division of State Lands, is the non-federal sponsor. 
Terminal facilities. The State of Oregon owns five 30-foot 
wide concrete finger piers between 1,300 and 1,500 feet long. 
The site is served by a 12-inch water main, and electricity and 
sewage lines also exist at the site. Additional development of 
these existing port facilities, which will facilitate the movement 
of an estimated 225,000 automobiles annually, is the 
responsibility of the local sponsor. 
Operations during fiscal year. New Work: A contract for 
construction of this project was awarded on July 20, 1989 and 
is scheduled for completion in FY 1990. 
22. UMPQUA RIVER, OR 
Location. Rises in Cascade Range, flows westerly about 120 
miles, and empties into Pacific Ocean 180 miles south of 
Columbia River and 465 miles north of San Francisco Bay. 
(See NOAA Charts 18580 and 18584.) 
Existing project. A jetty on north side of entrance about 
8,000 feet long, a south jetty 4,200 feet long extending to a 
point 1,800 feet south of outer end of north jetty; dredging to 
provide a usable entrance channel 26 feet deep, and a river 
37-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
channel 22 feet deep and 200 feet wide, from mouth to 
Reedsport, a distance of about 12 miles with a turning basin at 
Reedsport 1,000 feet long, 600 feet wide, and 22 feet deep; 
deepening of channel at Winchester Bay to 16 feet deep by 
100 feet wide for 3,100 feet, then adding 16 feet deep by 100 
feet wide for 500 feet, and 12 feet deep by 75 feet wide for 950 
feet beyond boat basin making up the East Boat Channel. A 
new West Boat Channel was added 16 feet deep by 100 feet 
wide for 4,300 feet and completed in 1984. Project was modified 
in 1951 to provide a channel in Scholfield River, but this 
portion of the project is currently inactive. Mean lower low 
water is plane of reference. Tidal range between mean lower 
low water and mean higher high water at river mouth is 7 feet, 
and extreme range is about 11 feet. 
North jetty was completed in 1930. Extension to original 
south jetty was completed in 1938. Dredging a 22-foot channel 
from mouth of river to Reedsport was completed in 1941. 
Gardiner Channel and turning basin was completed in 1949 
and Winchester Bay Channel and mooring basin in 1956. 
Rehabilitation of south jetty was completed August, 1963. 
Extension of training jetty was completed October 9, 1980. 
Deepening Winchester Bay East Channel and new West 
Channel completed 1984 under Section 107. (For details 
relating to previous projects, see page 2967 of Annual Report 
for 1898 and page 1732 of Annual Report for 1938.) 
Local cooperation. None required. 
Terminal facilities. At Gardiner there is about 650 feet of 
wharf frontage. Also there is an oil unloading facility owned 
by International Paper Co. for exclusive use of tanker barges. 
Port of Umpqua owns one wharf with 456 feet of water 
frontage, of which 228 feet is usable for vessels and another 
with about 75 feet of water frontage which has not been used 
generally for commercial shipping. 
On Bolon Island across the river from Reedsport a wharf 
was constructed which has about 5 acres of open storage for 
lumber and available to all on equal terms. 
At Winchester Bay, 2 miles from river entrance there is a 
major sports and commercial fishing harbor. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 210,000 cubic yards of material. 
Contract clamshell Jamison DB Big John removed 30,950 
cubic yards from Winchester Bay access channels. 
23. WILLAMETTE RIVER AT WILLAMETTE 
FALLS, OR 
Location. Locks and dam covered by this project are at 
Willamette Falls, a rocky reef in Willamette River at Oregon 
City, OR, about 26 miles above mouth of river. 
Existing project. Canal and locks were originally constructed 
by private interest in 1873 and were purchased by the 
United States in April 1915 for $375,000. Final report on 
purchase and rehabilitation of canal and locks is in the Annual 
Report for 1923, when project was reported 98 percent 
complete. The project includes four locks a canal basin and 
an extra guard lock used to prevent flooding when river levels 
are high. The system acts as a fluid staircase between the 
upper and lower reaches of the Willamette River. Total 
length of existing canals and locks is about 3,500 feet. Principal 
features of existing canal and locks at Willamette Falls are 
set forth in Table 37-K. Ordinary fluctuation of stage of 
water above locks is 12 feet and extreme, due to flood conditions, 
20 feet. Below locks, ordinary fluctuation is 15 feet and 
extreme 50 feet. 
Until the 1940's, the gates were opened manually. Now, the 
gates are operated by hydraulic pumps controlled by switches 
in two control stations with the aid of closed-circuit television 
and radio communication. All the gates have been replaced 
under minor rehabilitation funds. Existing locks and grounds 
are in good condition and in continuous operation. New service 
building was completed in 1988 costing $523,000. The 
project was placed on the National Register of Historic 
Places in 1974. 
Local cooperation. Fully complied with. 
Terminal facilities. James River Paper has a timber wharf 
about 850 feet long, extending to and supported by a concrete 
division wall built in lock canal by the United States. This 
wharf is used for receiving mill supplies and shipping paper 
and paper products. 
Operations during fiscal year. Normal operation and maintenance 
performed. Traffic through lock totaled 1,206,563 
tons during the fiscal year. 
24. YAQUINA BAY AND HARBOR, OR 
Location. Yaquina Bay is on Oregon coast, 113 miles south 
of mouth of Columbia River. (See NOAA Charts 18580 and 
18581.) 
Existing project. Two high tide rubblemound jetties at entrance, 
north jetty 7,000 feet, and south jetty 8,600 feet long; 
a spur jetty on channel side of south jetty 4,700 feet from its 
sea end, 800 feet long; five groins channelward from south 
jetty; channel 40 feet deep for a general width of 400 feet 
across bar and at outer end of entrance channel; a channel 30 
feet deep and 300 feet wide to a turning basin of same depth, 
900 to 1,200 feet wide and 1,400 feet long, and a channel 18 
feet deep and 200 feet wide from 30-foot channel at about 
mile 2.4, thence upstream to abandoned railroad terminus at 
Yaquina, a distance of about 4.5 miles. Project also provides 
for two small boat mooring basins at Newport, OR. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 8 feet 
and extreme is about 12 feet. At mile 1.2 a 1,300 foot long 
breakwater protecting the Port of Newport South Beach 
Marina together with an entrance channel 8 feet long by 100 
feet wide for a distance of 2,035 feet. 
Project as originally authorized was completed in May 
1952. Restoration of jetties was completed in 1934 and extension 
of north jetty 1,000 feet seaward was completed in 1940. 
Construction of mooring basin at Newport and dredging of 
channel and turning basin to project dimensions were completed 
during fiscal year 1949. Restoration of north jetty was 
again accomplished in 1956. Under modification of July 3, 
1958, extension of north jetty was completed in September 
1966, dredging of 40-foot bar channel and 30-foot river chan- 
37-10

PORTLAND, OREGON DISTRICT 
nel was completed in October 1968, and extension of south 
jetty was completed in June 1972. The north jetty was rehabilitated 
in 1988. (For details relating to previous projects see 
Annual Report for 1893, part 4, page 3314, and Annul Report 
for 1938, page 1736.) 
Local cooperation. None required. 
Terminal facilities. At McLean Point, on north side of bay, 
about 2 miles from entrance, Port of Newport has two berths 
capable of serving ocean-going vessels, one 435 feet long, the 
second 520 feet long. At the time the second berth was 
dredged, a retaining wall and fill of 6 acres were constructed 
adjacent to deep water. There now is 40 acres of filled land 
adjacent to deep water, and of this total, 7 acres were constructed 
in 1956-57. This facility has necessary carriers and 
lift trucks for handling lumber cargoes, warehouse for covered 
cargo storage, and is open to all on equal terms. 
Port of Newport also has a public wharf with 300 feet of 
frontage for servicing fishing boats. In addition, Port of Newport 
maintains 510 berths for mooring commercial and sport 
fishing vessels. There are several seafood companies on the 
bay which have their own facilities for handling fresh fish and 
crab. Supplies and petroleum products are readily available 
for small vessels. On south side of bay about 1.2 miles above 
entrance, Port of Newport has constructed South Beach Marina 
which can handle approximately 600 pleasure craft and 
shallow draft fishing boats. Public facilities include public 
automobile and boat trailer parking, boat launching ramp, 
fuel dock, fishing pier, and picnic area. A dry boat moorage of 
120 boats, is completed. A swing hoist with 3- ton capacity is 
currently available and one with 60-ton capacity is planned. 
About 1.5 miles above entrance, Oregon Aqua Foods, subsidiary 
of Weyerhaeuser Company, maintains a commercial 
fish farm facility. 
About 2.0 miles above entrance, Oregon State University, 
in conjunction with the Marine Science Center on 52 acres, 
maintains a 220-foot pier for docking large and small research 
vessels and a 100-foot float for docking small boats. 
Docking facilities are restricted to research vessels and State 
of Oregon small boats. 
Operations during fiscal year. Maintenance: A total of 
333,810 cubic yards was removed. U.S. hopper dredge Yaquina 
removed 57,300 cubic yards and the contract hopper 
dredge Padre Island removed 276,510 cubic yards of material. 
25. APPLEGATE LAKE, ROGUE RIVER 
BASIN, OR 
Location. In Jackson County, OR, on Upper Applegate 
River, a tributary of Rogue River, at River Mile 46, about 23 
airline miles southwest of Medford, OR. 
Existing project. A gravel-fill embankment dam, 242 feet 
high from streambed to crest with an overall length of 1,300 
feet. A gate- controlled concrete chute-type spillway on the 
left abutment, and a regulating outlet conduit, and intake 
tower with multilevel intakes on the left side of valley floor. 
Lake, 5 miles long, provides 75,000 acre-feet of usable storage 
for flood control and water conservation utilization. Project 
controls runoff from a drainage area of 223 square miles. 
In addition to flood control, reservoir is operated to provide 
irrigation, fish and wildlife enhancement, water quality control, 
and recreation benefits. Recreation facilities were provided 
by the Corps of Engineers with operation and maintenance 
by the USFS under a memorandum of agreement. 
Project is complete and operating. 
Local cooperation. Authorizing act requires that State of 
Oregon insure maintenance of stream flow released for fishery. 
In addition, costs allocated to irrigation would have to be 
repaid in a manner and to an extent consistent with reclamation 
laws and policies. Oregon Department of Fish and Wildlife 
made filing May 31, 1962 with State Engineer for water 
rights for use of stored water and natural flows for fish habitat 
improvement in amounts and at times specified in project 
authorization. The U.S. Bureau of Reclamation has made a 
feasibility study of Applegate Irrigation Division. The results 
of the study indicate that at present there does not appear to 
be a feasible Federal irrigation project for the Applegate 
River valley. Local interests have furnished all local cooperation 
specified by the 1970 Flood Control Act. The assurances 
were approved by the Secretary of the Army on May 8, 1975. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance was performed. Freshets regulated 
by Applegate Lake on Applegate River and Rogue River are 
shown in Table 37-M. 
26. BLUE RIVER LAKE, OR 
Location. On Blue River, a major tributary of McKenzie 
River, 1.8 miles above confluence of the two streams at the 
confluence of Quartz Creek and Blue River and about 42 
miles easterly of Eugene, OR. 
Existing project. A gravel-fill embankmnent dam 1,329 feet 
long at crest including spillway and 319 feet above the lowest 
point of the general foundation. A concrete gravity chutetype 
spillway with two gates is located on left abutment. 
Outlet works are in left abutment. On left shore of reservoir 
an earth-and-gravel fill embankment, about 1,535 feet long 
and 70 feet high, closes a low saddle between Blue River and 
McKenzie River. Project controls runoff from drainage area 
of 88 square miles. Reservoir provides 85,000 acre-feet of 
usable flood control storage and is operated as a unit of 
coordinated reservoir system to protect Willamette River 
Valley and increase low waterflows for navigation and other 
purposes. Recreation facilities are provided by the U.S. Forest 
Service under a Memorandum of Agreement. Project is 
complete. Construction of dam and appurtenant works was 
initiated in May 1963 and operation for flood control was 
effective in October 1968. Settlement of claims was completed 
in May 1974. Eugene Water and Electric Board made 
an application on April 1982 for permit to install two small 
hydropower units at Blue River Lake project. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance work performed. Freshets regulated 
by Blue River Lake project on Blue River, a major 
tributary of McKenzie River, are shown in Table 37-M. 
37-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
27. COTTAGE GROVE LAKE, OR 
Location. ON Coast Fork of Willamette River, 29 miles 
from mouth. Coast Fork rises in Douglas County, OR, on 
western slope of Cascade Range and northern slope of 
Calapooia Range, flows north for 49 miles, and unites with 
Middle Fork to form main Willamette River. 
Existing project. An earthfill dam, 1,750 feet long at crest, 
114 feet high from lowest point of the general foundation, a 
concrete gravity free overflow spillway 264 feet long near the 
right abutment, and a concrete gravity non-overflow section 
96 feet long forming the right abutment. Total length of dam 
is 2,110 feet. Outlet works, consisting of three gate- controlled 
conduits, pass through spillway section. Reservoir 
provides 30,060 acre-feet of usable flood control storage and 
controls runoff of drainage area of 104 square miles. Project 
is operated as a unit of coordinated reservoir system to protect 
Willamette River Valley and increase low waterflow for 
navigation and for other purposes. Recreational development 
consists of day use and overnight facilities at five sites 
operated by the Corps of Engineers. Construction of project 
initiated August 1940 was completed April 1952. Dam and 
reservoir have been in continuous operation since September 
1942. 
Local cooperation. Development of additional recreation 
facilities will require a local sponsor willing to cost share and 
assume all operation and maintenance of park facilities. 
Operations during fiscal year. Maintenance: Contract for 
supervisory control and data acquisition equipment is in progress. 
Normal operation and maintenance work continued. 
Freshets regulated by Cottage Grove Lake on Coast Fork 
Willamette River are shown in Table 37-M. 
28. DORENA LAKE, OR 
Location. On Row River, OR, 7 miles from mouth. Row 
River rises in Lane County on western slope of Cascade 
Range, flows northwest for 19 miles, and enters Coast Fork of 
Willamette River 19.5 miles above mouth. 
Existing project. An earthfill embankment dam, 3,352 feet 
long at crest and 145 feet high from lowest point of the 
general foundation. Concrete gravity free-overflow spillway, 
200 feet long, forms right abutment. Outlet works on five 
slide-gate-controlled conduits pass through spillway section. 
Reservoir provides 70,500 acre-feet of usable flood control 
storage and controls runoff of 265 square miles. The Project 
is operated as a unit of coordinated reservoir system to protect 
Willamette River Valley and increase low waterflows for 
navigational and other purposes. Construction of project initiated 
June 1941 was completed October 1952 except for 
construction of additional recreation facilities that were 
funded under the Code 710 program. Future recreation facility 
construction will be accomplished in accordance with the 
cost-sharing contract with Lane County, OR. Dam and reservoir 
have been in continuous operation since November 
1949. 
Local cooperation. A multiple project cost sharing agreement 
has been in force with Lane County since Sept. 1976. It 
includes 4 projects and 14 parks. At Dorena Lake, 6 parks 
included in the agreement are managed by Lane County 
under a lease agreement. Future recreation development 
will require a supplement to the cost sharing agreement. 
Operations during fiscal year. Maintenance: Contract for 
supervisory control and data acquisition equipment is in progress. 
Normal operation and maintenance continued. Freshets 
regulated by Dorena Lake project on Row and Coast Fork 
Willamette Rivers are shown in Table 37-M. 
29. ELK CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Location. In Jackson County, OR at River Mile 1.7 on Elk 
Creek, a tributary of Rogue River, about 26.5 miles northerly 
from Medford, OR. 
Existing project. Construction work for the 249-foot high 
roller compacted concrete gravity dam, 2,600 feet long at the 
crest, with a gate controlled concrete chute spillway, regulating 
outlet conduits, power penstock and multiple use intake 
tower attached to the upstream face of the dam has been 
stopped due to a court injunction. The project would control 
runoff from a drainage area of 135 square miles, and provide 
future municipal and industrial water supply, irrigation, fish 
and wildlife enhancement, water quality control, and recreation 
benefits. 
Construction of the project was initiated in February 1971. 
Work completed to date includes construction of roads and 
the main dam structure and outlet works to elevation 1563 
(approximately 1/3 proposed height). All lands for the project 
have been acquired with the exception of the clearing of 
water rights for a seemingly abandoned irrigation canal which 
originates within the project boundaries. Environmental 
statements were filed with Council of Environmental Quality 
June 15, 1972 and Supplement No. 1 addressing water quality 
and social/demographic information was filed with EPA on 
December 24, 1980. Estimated cost of project is $168,000,000 
of which $164,400,000 is federal and $3,600,000 is non-federal. 
In October 1985, the Corps was advised by Oregon Natural 
Resources Council (ONRC) and environmental group, they 
intended to file suit against the government to halt construction 
of Elk Creek, on specific environmental issues. A hearing 
on the motion for a preliminary injunction was scheduled 
before Oregon Federal District Court 16, December 86. On 
that date, the Court refused to grant the injunction to halt 
construction and bids were opened and the contract subsequently 
awarded to Ohbayashi Corp. An appeal was filed by 
ONRC in March, 1986 and heard by the 9th Circuit Court in 
July, 1986. 
On 23 June 1987, the Circuit Court reversed the decision of 
the District Court and returned the case to the District Court 
for appropriate injunctive relief. The resulting District court 
order issued in August and September 1987 allowed construction 
of the dam to El. 1563 ft. (approximately 1/3 the 
height of the dam), backfilling of the foundation key trench, 
aggregate processing, quarry restoration, and other miscellaneous 
work. The construction of the main dam to elevation 
1563 was reached in mid-January 1988. The Department of 
37-12

PORTLAND, OREGON DISTRICT 
Justice petitioned the 9th Circuit Court for a rehearing. On 
December 10th 1987 the 9th Circuit Court rejected the petition 
for a rehearing, requiring the termination of the existing 
main dam, and reservoir clearing contracts. The Department 
of Justice petitioned with the U.S. Supreme Court for a 
review of the decisions made by the 9th Circuit Court. The 
hearing before the U.S. Supreme Court was held May 1, 
1989. The U.S. Supreme Court remanded the case back for 
injunctive relief. In September 1989, the District Court was 
requested by the Corps to remand the case back to the Corps 
for preparation of a supplemental EIS. 
To lift the injunction against the dam a Supplemental Environmental 
Impact Statement (EISS) is being prepared to 
address those issues. Additional studies are being conducted 
in water temperature and turbidity, and fish and wildlife. The 
Draft EISS is scheduled for public review at the end of calendar 
year 1990. 
Local cooperation. Authorizing act requires that State of 
Oregon take action prior to construction to insure maintenance 
in stream of flow to be released for fishery. In addition, 
costs allocated to irrigation would have to be repaid in a 
manner and to an extent consistent with the U.S. Bureau of 
Reclamation laws and policies. On February 24, 1966, State 
of Oregon Water Resources Board filed for withdrawal rights 
of 25 cubic feet per second to maintain a minimum flow for 
fish. Development of recreation facilities require a local 
sponsor willing to cost share in recreation development and 
assume all operations and maintenance of park facilities. 
Operations during fiscal year. Settling of contract claims, 
operation and maintenance during the construction phase of 
the project, and archeological investigations. 
30. FALL CREEK LAKE, OR 
Location. On Fall Creek, a tributary of Middle Fork Willamette 
River, about 7 miles above confluence of the streams 
and about 19 miles southeasterly of Eugene, OR. 
Existing project. An earth-and-gravel fill embankment 
about 5,100 feet long at crest and 193 feet high from lowest 
point of the general foundation. A gated concrete gravity 
spillway is in left abutment. Outlet is in right abutment. 
Reservoir provides 115,000 acre-feet of usable flood control 
storage and is operated as a unit of coordinated reservoir 
system to protect Willamette River Valley and increase low 
waterflows for navigation and other purposes. 
Construction of project began May 1962 and was essentially 
complete November 1965. Reservoir storage for flood 
control was effective October 1965. SKY Camp Lodge was 
completed October 1978. Future recreation facilities will be 
provided in accordance with the cost-sharing contract with 
Bethel School District. Bethel School District has a subagreement 
with the Springfield Kiwanis Club for management 
of this facility. The Corps manages one park at the 
project. 
Local cooperation. Fall Creek Lake is included in the Lane 
County multiple project cost sharing agreement. Two parks 
are managed by Lane County under lease agreement. Future 
development will require a supplement to the cost sharing 
agreement. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance work performed. Freshets regulated 
by Fall Creek Lake project on Fall Creek, a tributary of 
Middle Fork, Willamette River, are shown in Table 37-M. 
31. FERN RIDGE LAKE, OR 
Location. On Long Tom River, 23.6 miles from the mouth. 
Long Tom River rises in Lane county, OR, on eastern slope 
of Coast Range, flows north for 50 miles, and enters Willamette 
River 147 miles above its mouth. 
Existing project. A main dam 6,624 feet long at crest and 49 
feet high from lowest point of the general foundation and two 
auxiliary dikes, 915 and 3,929 feet long, along northeasterly 
boundary of lake. Main dam consists of an earthfill embankment 
dam 6,330 feet long, a concrete gravity spillway near left 
abutment with a non-overflow structure 46 feet long, containing 
outlet works, and an overflow structure, 248 feet long, 
controlled by six automatic gates. Project includes rectification 
of channel of Long Tom River downstream of dam. 
Reservoir provides 110,000 acre-feet of usable flood control 
storage and controls runoff of tributary drainage area of 275 
square miles. Reservoir protects Long Tom River Valley and 
is operated as a unit of coordinated reservoir system to protect 
Willamette River Valley generally and to increase low 
water-flows for navigation and other purposes. Dam was 
originally constructed in 1941 to height of 47 feet. Provision 
of additional storage for flood control was obtained in 1965 by 
raising embankments 2 feet to 49 feet above lowest point of 
the general foundation. 
Construction of project initiated April 1940 was completed 
August 1951, except for provision of additional storage for 
flood control authorized in 1962 and completed April 1965, 
and construction of additional recreation facilities funded 
through the Code 710 program. Dam and reservoir have been 
in continuous operation since December 1941. Development 
of future recreation facilities will be in accordance with the 
cost-sharing contract with Lane county, and requires a 50 
percent contribution by the county. Development is subject 
to availability of funds by the Government and the county. 
Local cooperation. Fern Ridge Lake is included in the Lane 
County multiple project cost sharing agreement. Three parks 
are managed by Lane County under lease agreements. Future 
development will require a supplement to the cost sharing 
agreement. The Oregon Department of Fish and Wildlife 
manages 5,000 acres of land and water for migratory water 
fowl under a lease agreement. 
Operations during fiscal year. Maintenance: Contract for 
supervisory control and data acquisition equipment is in progress. 
Rehabilitation of outlet works was completed. Normal 
operation and maintenance continued. Freshets regulated by 
Fern Ridge Lake project on Long Tom River are shown in 
Table 37-M. 
37-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
32. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public Law 
858, 80th Cong., as amended (preauthorization). See Table 
37-L. 
Emergency bank protection (Section 14 of 1946 Flood Control 
Act, Public Law 526, 79th Cong.). Fiscal year costs for 
completion of preauthorization studies on Little Butte 
Creek, Eagle Point, Oregon were $4,968 and initiation of a 
preauthorization study on Nehalem River, Sunset Drainage 
District, Oregon $520. Preparation of plans and specifications 
were continued for Mill Creek, Oregon $14,238 and 
Winchester Bay, Oregon $898. 
Snagging and clearing for flood control (Section 208, Flood 
Control Act of 1954, Public Law 780, 83rd Congress). Fiscal 
year costs for preauthorization study on Tutuilla Creek, Oregon 
were $10,000. 
Beach erosion control (Section 103, River and Harbor Act 
of 1962, Public Law 874, 87th Congress). Fiscal year costs for 
initiation of a preauthorization study at Cape Lookout State 
Park, Oregon were $6,446. 
Emergency flood control activities-repair, flood fighting 
and rescue work (Public Law 99, 84th Congress and antecedent 
legislation). Federal costs for fiscal year were: $213,104, 
disaster preparedness; $1,198, emergency operations. 
Mt. St. Helens Emergency Measures. The May 18, 1980 
eruption of Mt. St. Helens dramatically altered the hydraulic 
and hydrologic regimes of the Cowlitz and Toutle River valleys. 
Volcanic debris substantially reduced the river's hydraulic 
capacity to the point where major flooding could be expected 
even with normal runoff. 
A major recovery program for the Cowlitz and Toutle Rivers 
funded under advance measures was initiated a short time 
after the eruption and was essentially completed during FY 
1982. 
Total cost of Mt. St. Helens emergency measures, from 
initiation through FY 1989, with some contract modifications 
remaining to be negotiated, is $245,967,730. The authorized 
navigation channel on the Cowlitz between River Mile 0 and 
4.2 remains unusable due to continued sedimentation. 
33. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Funds appropriated for inspection of completed local flood 
protection works are used to determine maintenance condition 
of completed works and to ascertain whether those works 
are being properly maintained by local interests. A total of 65 
leveed areas and 264 bank protection works are inspected at 
various locations along both banks of Lower Columbia River 
below Bonneville Dam, along Oregon Coast, in eastern Oregon, 
in southern Oregon and in Willamette River Basin. 
Aerial inspection of revetments in Willamette River Basin 
are supplemented by an onsite inspection at locations requiring 
maintenance. A representative of sponsoring districts 
accompanied the Portland District representatives performing 
the levee inspections. Deficiencies in maintenance and 
need for repairs were discussed with sponsoring districts' 
representatives and a report was made to each sponsor with 
recommendations for improving maintenance. The program 
to improve maintenance of completed Federal projects initiated 
by House Appropriations Committee on Civil Functions 
was continued. Of the 65 leveed areas inspected during the 
fiscal year, four were reported deficient in maintenance. Fiscal 
year costs were $110,157. 
34. INSPECTION OF NON-FEDERAL FLOOD 
PROJECTS 
Annual inspections and evaluations are made of flood control 
works constructed by non- federal agencies. These evaluations 
are to determine eligibility for assistance under PL 
84-99, of damages by flooding. This evaluation consists of an 
engineering study to determine degree of flood protection 
being provided, a tabulation of improvements within the protected 
area for cost-benefit studies and an inspection to 
determine compliance with maintenance agreements executed 
by the project sponsor and the Government. These 
inspections also serve a valuable disaster preparedness function 
in terms of explaining to local sponsors there preparedness 
responsibilities. All local sponsors are advised of the 
result of these evaluations and inspections. Fiscal year costs 
were $3,811. This function was transfered to the Flood Control 
and Coastal Emergencies appropriations this fiscal year. 
35. LOWER COLUMBIA RIVER BASIN, OR 
AND WA 
Location. On Columbia River and minor tributaries, chant 
nels, and sloughs, between Sandy River, OR, about 15 miles 
east of Vancouver, WA, and mouth of Columbia River. 
Existing project. Plan for bank protection work, improvements 
to existing projects, and construction of flood control 
works in Lower Columbia River Basin provides for new construction 
and supplementing and extending projects constructed 
in Lower Columbia River Basin under authority of 
1936 Flood Control Act: (a) Lower Columbia River Bank 
Protection, OR and WA provides for bank protection works 
at 96 locations on Columbia River and tributaries between 
Sandy River and mouth of Columbia River, totaling about 
224,000 linear feet. Estimated total Federal cost is 
$25,100,000 and non-Federal cost is $1,720,000; (b) See Table 
37-N on Levees and Improvements to Existing works; (c) 
Lower Columbia River Basin levees at new locations, Oregon 
and Washington, provides for construction of flood control 
works at: Washougal area, Clark County, WA, about 5.5 
miles of levee and appurtenant works at a Federal cost of 
$1,803,488, and non-federal cost at $98,000; and Vancouver 
Lake area in vicinity of Vancouver, WA, about 18 miles of 
levee and appurtenant works at an estimated Federal cost 
(1980) of $19,500,000 and non-Federal cost at $900,000. This 
portion, Vancouver Lake, WA, has been reclassified "deferred". 
Total estimated Federal costs (1980) for both areas 
of work are $21,303,488 and non-Federal costs $998,000. 
Federal cost for all work under project, Lower Columbia 
River Basin, OR, and WA, is $67,531,776. 
Construction of improvement to existing project in Sandy 
Drainage District, OR, was completed by local interests at no 
37-14

PORTLAND, OREGON DISTRICT 
construction cost to the Government. Improvements of levees 
have been accomplished by contract at the following 
locations: Multnomah County Drainage District, No. 1, OR, 
June 1962; Suvie Island Drainage District, OR, October 
1972; Woodson Drainage District, OR, December 1963; 
Rainier Drainage District, OR, June 1964; Cowlitz County 
Diking Improvement Districts, OR, April 1967; Cowlitz 
County Consolidated Diking Improvement District, No 2, 
Wa, June 1974; Beaver Drainage District, Or, June 1978; 
Wahkiakum County consolidated Diking District #1, WA, 
October 1979; and Scappoose Drainage District, OR, September 
1980. Washougal Area, WA (new location) levee 
construction has been completed. Under authorization for 
Lower Columbia River Basin bank protection works, construction 
has been completed at numerous locations. (See 
Section 34 for additional information). 
Local cooperation. Flood Control Act of 1950 provides 
local interests furnish lands and rights-of-way; make necessary 
highway, highway bridge, and utility alterations; hold the 
United States free from damages; and maintain and operate 
completed works. Under Section 103 of the Water Resources 
Development Act of 1986, local interest will be required to 
make a cash contribution for construction of each project. 
Total non-Federal cost for all work is $6,488,000. For details 
of status or requirements of local cooperation, see individual 
project reports. 
Operations during fiscal year. See individual projects. 
36. LOWER COLUMBIA RIVER BASIN BANK 
PROTECTION, OR AND WA 
Location. On Columbia River and tributaries between 
Sandy River, OR, and mouth of Columbia River. 
Existing project. Provides for construction of 224,000 linear 
feet of bank protection works at 96 locations along Lower 
Columbia River below River Mile 125 and along principal 
tributaries in this reach, to protect existing improvements 
such as levees and developed industrial lands from further 
erosion. Existing project is a unit of general comprehensive 
plan for flood control, navigation, and other purposes in 
Columbia River Basin. Construction of project began in July 
1961 and is 88 percent complete. .A total of 191,000 linear 
feet of bank protection work at 84 locations has been completed. 
Estimated Federal cost is $24,900,000. 
Local cooperation. Flood Control Act of 1950 provides 
local interests furnish lands and rights-of-way; make necessary 
highway, highway bridge, and utility alterations; hold the 
United States free from damages; and maintain and operate 
completed works. Under Section 103 of the Water Resources 
Development Act of 1986, Local Interests will also be required 
to make a cash contribution for construction of each 
site. Estimated costs for all requirements of local cooperation 
are $1,400,000. 
Operations during fiscal year. Work consisted of coordination 
with sponsors and evaluation of local erosion problems 
continued. 
37. MOUNT ST. HELENS & VICINITY, WA 
Location. Along the Cowlitz and Toutle rivers from Spirit 
Lake at the base of Mt. St. Helens to the confluence of the 
Cowlitz with the Columbia River (River Mile 68) approximately 
55 miles downstream from Portland, OR. 
Existing project. The May 18, 1980 eruption of Mt. St. 
Helens dramatically altered the hydraulic and hydrologic regimes 
of the Cowlitz and Toutle River valleys. Mudflows 
triggered by the eruption carried large volumes of sediment 
from the debris avalanche into these river valleys, reducing 
hydraulic capacity to the point where major flooding could be 
expected even with normal runoff. Storm runoff and surface 
drainage continue to deliver sediment from the debris avalanche 
into the rivers. Funds allocated under Public Law 
84-99 were used for major recovery work on the Cowlitz and 
Toutle rivers. 
In late FY 1983, interim flood control measures were implemented 
under the authority of Public Law 98-63 to assure 
100-year flood protection to developed areas along the 
Cowlitz River. Measures implemented are primarily dredging 
on the Cowlitz and Toutle rivers temporary levee improvements 
on the Cowlitz River, and a monitoring program. 
Local cooperation. Local sponsors are responsible for obtaining 
any additional lands easements and rights-of-way. 
The State of Washington has agreed to act as the local sponsor. 
State funds have been appropriated for acquisition of 
lands and related expenses for Mt. St. Helens recovery operations. 
The State of Washington has spent over $4,500,000 to 
procure disposal sites for dredged material. 
Operations during fiscal year. The settlement of contract 
claims was the only activity in the fiscal year. 
38. MT. ST. HELENS SEDIMENT CONTROL, 
WA
Location. On the North Fork Toutle River, 2 miles upstream 
from its confluence with the Green River, in Cowlitz 
County, southwest Washington. The river systems impacted 
by the project include Toutle, Cowlitz and Columbia Rivers. 
Most of the population affected by the problems reside in the 
communities of Longview, Kelso, Lexington, and Castle 
Rock, Washington. 
Existing project. The project was authorized by the Supplement 
Appropriations Act, 1985 (Public Law 88, 99th Congress, 
August 15, 1985). The Act includes authorization "... to 
construct, operate and maintain a sediment retention structure 
near the confluence of the Tout!e and Green River, 
Washington, with such design features and associated downstream 
actions as are necessary, in accordance with the Feasibility 
Report of the Chief of Engineers dated December 
1984." The project will provide a permanent solution to potential 
flooding on the Cowlitz River from sedimentation 
problems created by the eruption of Mt. St. Helens. The 
Decision document recommended construction of a single 
sediment retention structure (SRS) with a 125- foot high 
spillway at the Green River site on the North Fork Toutle 
River, improvements to the levee system at Kelso, Washington, 
and dredging downstream from the SRS. 
37-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Local interests are responsible for provision 
of all lands, easements, and rights-of-way for the sediment 
retention structure, dredging disposal areas, and levee 
improvements. Local interests are also responsible for all 
alterations and relocations of buildings, roads, bridges and 
other structures or utilities made necessary by implementation 
of the project. In addition, operation and maintenance of 
fish facilities, the levee system at Kelso and dredged material 
disposal sites will be the responsibility of local interests. Nonfederal 
cash contribution is $3,600,000 and the estimated 
non-federal land, easements, right-of-ways, and relocations 
costs are $21,000,000. 
Operations during fiscal year. Work on the Sediment Retention 
Structure continued and is scheduled for completion 
in FY 1990. Work on the fish collection facility contract 
continued and is scheduled for completion in FY 1990. Fish 
collection began in February 1989 at a partially completed 
facility. Contracts were awarded in August 1989 for dredging 
in the Cowlitz River and approximately 3,900,000 cubic yards 
of material was removed. The Kelso Levee improvement 
contract was completed. 
39. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Corps of Engineers monitored flood control operations at 
five Bureau of Reclamation projects (Prineville, Ochoco, 
Emigrant, Scoggins, and Galesville) and one municipal power 
project operated by Tacoma City Light (Mossyrock). The 
Bureau of Reclamation projects were partially constructed 
with flood control funds, thereby subjecting project operation 
to monitoring by the Corps of Engineers under section 7, 
Flood Control Act of 1944. Monitoring of Mossyrock flood 
control operation is assigned to the Corps by the Federal 
Energy Regulatory Commission as the Mossyrock license 
calls for specific flood control regulation. 
The five Bureau of Reclamation projects and Mossyrock 
project were operated during 1989 within the flood control 
regulations specified for each project. A water control manual 
for Scoggins Dam was completed in 1989. A water control 
manual for Galesville Dam is scheduled for completion in 
November of 1990. Total cost of monitoring the six projects 
during the fiscal year was $4,073. 
40. WILLAMETTE RIVER BASIN, OR 
Location. Willamette River, formed by Coast and Middle 
forks which join a few miles above Eugene, OR, flows north 
189 miles, and enters Columbia River 101.5 miles above its 
mouth. The basin has an area of 11,200 square miles and lies 
between Cascade Range on the east and Coast Range on the 
west. Major tributaries of Willamette River rise in Cascade 
Mountains and consist of Coast and Middle Forks and 
McKenzie, Calapooia, Santiam, Molalla, and Clackamas Rivers. 
Important tributaries that head in the Coast Range are 
Luckiamute, Yamhill, and Tualatin Rivers. Minor tributaries, 
all of which enter the main stream from the west, are 
Long Tom River, Marys River, and Rickreall Creek. 
Existing project. Flood Control Act of 1938 approved general 
comprehensive plan for flood control, navigation, and 
other purposes in Willamette River Basin and authorized 
funds for initiation and partial accomplishment of plan recommended 
for initial accomplishment of plan recommended 
for initial development; the reservoirs and related works to 
be selected by Chief of Engineers. Subsequent Flood Control 
Acts, 1941 through 1974, authorized additional flood control 
and other works and increased monetary authority. 
Following projects were completed as authorized and are in 
continuous operation: Fern Ridge Lake, August 1951; Cottage 
Grove Lake, April 1952; Dorena Lake, October 1952; 
Detroit Lake, December 1960; Lookout Point Lake, June 
1961; Hills Creek Lake, June 1963; Cougar Lake, March 
1964; Fall Creek Lake, November 1965; Green Peter-Foster 
Lakes, June-December 1967 respectively; and Blue River 
Lake, October 1968. Under the authorization for construction 
of recreation facilities at completed projects, work has 
been accomplished at Fern Ridge, Cottage Grove, Dorena, 
Lookout Point, and Fall Creek Lakes. Under the memoranda 
of agreements with the U.S. Forest Service, recreation facilities 
also have been constructed at Detroit, Lookout Point, 
Cougar, Blue River, and Hills Creek Lakes, Recreational 
facilities were constructed at Green Peter-Foster Lakes with 
initial construction funds. Details of operation, construction, 
and financial status of projects are in individual reports. 
During low-water season, July-September, supplemental 
water releases are made from Willamette River Basin Reservoirs. 
Uses which benefit from increased downstream flows 
include irrigation, navigation, power, fisheries, pollution 
abatement, and recreation. Although optimum regulation 
cannot be provided for every purpose, water released from 
reservoirs during the low-water season for a particular purpose 
will usually provide benefits to other uses as well. Basic 
policy is to provide most beneficial overall regulation, consistent 
with established water-use priorities. (See Table 37-0 
on Willamette River Basin comprehensive plan.) 
Local cooperation. Section 2, Flood Control Act of June 
28, 1938 applies. Local cooperation for other projects is in 
individual reports for those projects. 
Operations during fiscal year. See individual reports. 
41. WILLAMETTE RIVER BASIN BANK 
PROTECTION, OR 
Location. On Willamette River and tributaries, between 
Cascade Range and Coast Range, from a point south of 
Eugene to Portland, OR. 
Existing project. Provides for clearing, sloping, and reveting 
riverbanks; construction of pile and timber bulkheads and 
drift barriers; minor channel improvements; and maintenance 
of existing works for control of floods and prevention 
of erosion at various locations along Willamette River and its 
tributaries. The current scope of the project is a total of 
510,000 linear feet of bank protection at 236 locations. Estimated 
Federal cost is $29,400,000. 
Construction of project began in 1938 and is 96 percent 
complete. A total of 489,795 linear feet of bank protection 
work at 230 locations consisting of revetment of riverbanks, 
pile and timber bulkheads, drift barriers, and channel improvements, 
have been completed on Willamette River and 
tributaries. 
37-16

PORTLAND, OREGON DISTRICT 
Local cooperation. Section 3, Flood Control Act of 1936 
and Section 103, Water Resources Development Act of 1986 
applies. Estimated costs for all requirements of local cooperation 
under terms of project authorization were 
$2,200,000. 
Operations during fiscal year. Coordination and evaluation 
of local erosion problems continued. 
42. WILLOW CREEK LAKE, HEPPNER, OR 
Location. On Willow Creek immediately upstream from 
Heppner and just downstream from junction of Balm Fork 
and Willow Creek in Section 35, Township 2 South, Range 26 
East, Willamette Meridian. 
Existing project. Project provides flood protection to the 
city of Heppner and downstream area by controlling runoff 
from a drainage area of 96 square miles. The dam is a roller 
compacted concrete structure 160 feet high at crest elevation 
2,130. Ancillary features include a center uncontrolled spillway 
with a maximum flood capacity of 93,300 cfs (cubic feet 
per second), an outlet works with a capacity of 500 cfs, a 
minor flow works and diversion works. Gross storage capacity 
of the project is 13,250 acre-feet, consisting of 7,750 acrefeet 
for exclusive flood control, 1,750 acre-feet for joint flood 
control and irrigation, 1,750 acre- feet exclusive irrigation, 
and 2,000 acre-feet dead storage for fish, wildlife, recreation, 
sediment accumulation, and aesthetics. Limited recreation 
facilities are being provided. 
Willow Creek Parks and Recreation District has leased 
recreation facilities at Willow Creek Lake. A courtesy handling 
dock was constructed by the Recreation District utilizing 
Oregon State Marine Board funds. A playfield area below 
the dam has been leased to the City of Heppner. 
The final Environmental Impact Statement was filed with 
the Environmental Protection Agency on December 20, 
1979. The provisions of the Clear Water Act were met by a 
Section 404(b)(1) Evaluation and a public notice issued January 
12, 1980, and a section 401 certification from the State of 
Oregon on February 15, 1980. Land acquisition is about 99 
percent complete. 
Local cooperation. None required. Development of recreation 
facilities will require cost sharing with a non-federal 
local sponsor. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance performed. 
Multiple-Purpose Projects, Including Power 
43. BONNEVILLE LOCK AND DAM - LAKE 
BONNEVILLE, OR AND WA 
Location. Project is on Columbia River, 40 miles east of 
Portland, OR, about 146 miles above mouth of river. For 
description of Columbia River, see Section 4. 
Existing project. A dam, powerplant, and lock for power 
and navigation. Spillway dam extends across main channel 
from Cascade island shore to Bradford Island. Overflow crest 
at 24 feet above mean sea level is surmounted by 18 verticallift 
steel gates, 10 with remote control hoists placed between 
piers which extend to elevation 99 feet where a service roadway 
provides access, and two 350-ton gantry cranes for regulating 
gates. Powerhouse No. 1 extending across Bradford 
Slough to the Oregon shore has an installation of 10 units, 
consisting of one unit of 48,000 kilowatts, one unit of 59,500 
kilowatts, and eight units of 60,000 kilowatts each, totaling 
587,500 kilowatts. Ordinary and extreme fluctuations of river 
at lower lock gate are about 21 and 47 feet respectively. 
Project includes fish ladders to serve both main channel, 
Bradford Slough Channel, and Powerhouse II channel. Navigation 
lock and powerhouses are founded on andesite, and 
main dam rests on solidified sedimentary rock of volcanic 
origin. The pool created by dam provides a navigable channel 
27 feet deep between Bonneville and The Dalles Dams, a 
distance of 47 river miles. Principal data concerning navigation 
lock spillway dam, and powerplant are set forth in Table 
37-P. 
Dam, navigation lock, 10-unit power generating installation, 
fishways, and attendant buildings and grounds cost 
$83,239,395, of which $6,072,480 is for navigation facilities, 
$39,350,824 for power facilities and $37,816,091 for joint 
facilities, consisting of dam, fishways, buildings and grounds, 
and headwall section of power units 0 to 6, cost of which 
$2,106,000 is allocated to dam and lake facilities. 
In response to flow regulations and peakings from upstream 
plants operating under conditions of Canadian storage 
and Pacific Northwest-Southwest Intertie, two modifications 
were undertaken at the Bonneville project. The 
modification for peaking project was undertaken to minimize 
adverse environmental effects under rapidly changing flow 
conditions from upstream dams. The project was completed 
in 1978 at a cost of $27,195,000. The second modification 
provided for increased power installation by building a second 
powerhouse located on the Washington shore adjacent 
to the end of the existing spillway. The new powerhouse 
contains eight units of 66,500 kilowatts each and two fish 
attraction turbine generator units of 13,100 kilowatts each for 
a combined capacity of 558,200 kilowatts, bringing the entire 
Bonneville capacity to 1,145.7 megawatts. Additional fish 
facilities consist of the powerhouse collection system, second 
fish ladder on the Washington shore, transportation channel 
connecting the Cascade Island fish ladder with new exit control 
section, and fingerling bypass facilities which include fish 
screens in both the powerhouses. To provide for the anticipated 
increased visitor use, onsite visitor facilities are included. 
Under authority of the Bonneville Project Act 
(August 20, 1937), a letter from Bonneville Power Administration 
to North Pacific Division dated January 21, 1965, 
requested construction of a second powerhouse. 
Construction of project started October 1933, was completed 
February 1943. Modification of powerhouse control 
equipment started March 1957, was completed September 
1958. First two power units were placed in operation during 
fiscal year 1938. Powerhouse with complete installation of 10 
units, was in operation December 1943. 
Construction of modification for peaking work commenced 
in September 1970 and was completed in September 1978. 
37-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Construction of second powerhouse is near completion. 
Final environmental impact statement was filed with Council 
on Environmental Quality in April 1972. In response to increasing 
visitation which now exceeds 800,000 a year at the 
dam site itself and 1,500,000 project wide, a visitor center 
with windows into the fish ladders, a 60-seat theatre, exhibits 
and displays was completed in 1975. Units 11 through 18 were 
on-line by October, 1982. The visitor facility for the new 
powerhouse (which does not require cost-sharing) is an integral 
part of that structure. The total cost for construction of 
the second powerhouse is $679,000,000. 
The first powerhouse, spillway, navigation lock and associated 
facilities have been designated as a National Historic 
District. 
A cost sharing agreement between The Corps and 
Skamania County has been finalized. Development of recreation 
facilities at Home Valley was completed this fiscal 
year. 
Through September 1989, power generation totaled 205.4 
billion kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, $351,399,213 
was reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. None required, except for non-Federal 
cost-sharing for development of recreational facilities. 
Operations during fiscal year. New work: Research continued 
to find a solution for correction of deficiencies of fish 
guidance efficiency at the Second Powerhouse to reduce fingerling 
mortality incurred during annual downstream migration. 
Maintenance: The First Powerhouse modernization program 
continues to be implemented. Normal operation and 
maintenance was performed during period. During the fiscal 
year 5,073,605,000 kilowatt-hours of electrical power energy 
were generated, of which 5,046,417,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Traffic through the navigation lock consisting of 
rafted logs, petroleum products, grains, and miscellaneous 
cargo. Fiscal year traffic through lock is estimated to total 
11,594,772 tons. 
44. COUGAR LAKE, OR 
Location. At mile 4.4 on South Fork McKenzie River which 
joins McKenzie River about 56.5 miles above its confluence 
with Willamette River. Project is about 42 miles east of 
Eugene, OR. 
Existing project. A rockfill dam with an impervious earth 
core, about 1,738 feet long at crest and 445 feet high above 
the streambed. Reservoir is 6 miles long with storage capacity 
at full pool of 219,000 acre-feet and controls runoff of tributary 
drainage area of 210 square miles. Spillway is on right 
abutment and outlet and power tunnels in left abutment. 
Outlet tunnel is provided with a chute and stilling basin. 
Powerplant consists of two 12,500 kilowatt units with minimum 
provisions for installing a third unit of 35,000 kilowatts 
for future peaking capacity. Improvement functions as a unit 
in coordinated system of reservoirs for multiple-purpose development 
of water resources in Willamette River Basin. 
Recreation facilities are provided by the U.S. Forest Service. 
Also authorized (but unconstructed) is a reregulating dam, 
Strube Lake, below Cougar Lake, which would permit Cougar 
to operate as a peaking powerplant. The Strube dam 
would contain two units totalling 4,600 kilowatts. 
Construction of project initiated June 1956 is complete, 
excluding Strube Lake and Cougar Additional Unit for which 
planning is essentially complete. Also, plans and specifications 
for the first construction contract (relocations) have 
been completed. Generating units 1 and 2 were placed in 
commercial operation March 23 and February 4, 1964, respectively. 
Physical in-service date for flood control was November 
29, 1963. Through September 1989 power generation 
totaled 3.4 billion kilowatt-hours. Of the gross income from 
sale of this power by Bonneville power Administration, 
$17,967,962 was reimbursed to the U.S. Treasury to recover 
Corps of Engineers project investment and operating costs. 
Estimated Federal cost of Strube lake and Cougar Additional 
Unit is $114,000,000. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance continued. During fiscal year, 
178,123,000 kilowatt-hours of electrical energy were generated 
at project, of which 177,358,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Cougar Lake on South 
Fork McKenzie River are shown on Table 37-M. 
45. DETROIT LAKE - BIG CLIFF, OR 
Location. On North Santiam River with dam 50 miles from 
mouth 40 miles southeast of Salem, OR. North Santiam 
River flows north and west for 85 miles, and unites with South 
Santiam River to form Santiam River, which 10 miles downstream 
enters Willamette River 108 miles above its mouth. 
Existing project. Main dam and a reregulating dam, both 
with power-generating facilities. Detroit Dam is a concrete 
gravity structure about 1,522 feet long and 454 feet high from 
lowest point of the general foundation to roadway deck. Spillway 
is a gate-controlled overflow section, and outlet works 
are gate- controlled conduits through dam. Powerhouse with 
two units having a capacity of 50,000 kilowatts each is in right 
abutment immediately below dam. Reservoir has a storage 
capacity at full pool of 454,900 acre-feet and controls runoff 
of tributary drainage area of 438 square miles. It is being 
operated as a unit in coordinated reservoir system to protect 
Willamette Valley from floods, to increase low water flows in 
interest of navigation and irrigation, to generate power, and 
for other purposes. Reregulating dam 3 miles downstream at 
Big Cliff site is concrete gravity type, about 191 feet high from 
lowest point of the general foundation to roadway deck. 
Power installation consists of one unit with a capacity of 
18,000 kilowatts. Reservoir has a storage capacity of 5,930 
acre-feet at full pool. Project is a unit of comprehensive plan 
for flood control and other purposes in Willamette Basin. 
Recreation facilities are provided by the U.S. Forest Service, 
Oregon State Park System and the town of Detroit. 
37-18

PORTLAND, OREGON DISTRICT 
Construction of project begun in May 1947 was completed 
December 1960. The two powerhouse generating units were 
placed in commercial operation June and October 1953. At 
Big Cliff powerhouse, single generating unit was placed online 
June 1954. Use of Big Cliff Dam for reregulating fluctuating 
flow from Detroit units was effected October 1953. 
Through September 1989 power generation totaled 17.7 billion 
kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, $58,602,684 was 
reimbursed to the U.S. Treasury to recover Corps of Engineers 
project investment and operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance continued. During fiscal year 
395,292,000 kilowatt-hours of electrical energy were generated 
at project of which 392,613,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by the Detroit Lake project on 
North Santiam River are shown in Table 37-M. 
46. GREEN PETER-FOSTER LAKES, OR 
Location. At approximate mile 5.5 on Middle Santiam 
River which joins South Santiam River about 56.8 miles 
above its confluence with Willamette River. Dam is about 30 
miles southeast of Albany in Linn County, OR. 
Existing project. Main dam and a reregulating dam, both 
with power-generating facilities. Green Peter Dam is a concrete 
gravity structure, 1,400 feet long and 385 feet high 
above the lowest point of the general foundation with a gatecontrolled 
spillway. Outlet works consist of two conduits 
through spillway, discharging into a stilling basin. 
Powerplant, on right bank adjacent to spillway stilling basin, 
consists of two units with an installed capacity of 80,000 
kilowatts. Reservoir provides storage capacity at full pool of 
430,000 acre-feet, extending 6.5 miles up Quartzville Creek 
and some 7.5 miles up Middle Santiam River above creek 
junction, forming a Y- shaped pool. Reservoir controls 
runoff of tributary drainage area of 277 square miles. 
Foster Dam, 7 miles downstream from Green Peter Dam is 
located on South Santiam River about 38 miles above its 
confluence with Santiam River and 1.5 miles below its confluence 
with Middle Santiam River. Foster Dam consists of an 
earth, gravel, and rock-filled embankment, 146 feet high 
from lowest point of the general foundation and a concrete 
gravity gate controlled spillway and stilling basin for a total 
length of 4,800 feet. Power installation consists of two units 
with capacity of 20,000 kilowatts. Foster Lake has a storage 
capacity, at full pool, of 61,000 acre-feet. Project functions as 
a unit in coordinated system of reservoirs for multiple-purpose 
development of water resources in Willamette River 
Basin. 
All construction on Green Peter-Foster Lakes project initiated 
June 1961 is completed. Green Peter Lake was placed 
in operation for useful flood control June 1967 as a unit of 
coordinated reservoir system for protection of the Willamette 
River Basin. First power- generation unit was placed 
on the line June 9, 1967 and second, June 28, 1967. Use of 
Foster Lake for reregulating fluctuating flows from Green 
Peter units was effective December 1967. First power generation 
unit was placed on-line August 22, 1968 and second, 
September 6, 1968. Through September 1989 power generation 
totaled 7.6 billion kilowatt-hours. Of the gross income 
from sale of this power by Bonneville Power Administration, 
$43,611,534 was reimbursed to the U.S. Treasury to recover 
Corps of Engineers project investment and operating costs. 
Local cooperation. Future recreation development at Foster 
or Green Peter will require cost sharing. Recreation facilities 
at Foster Lake includes 4 parks and 2 parks at Green 
Peter Lake. Five of these parks were developed by the Corps 
and are operated by Linn county under lease agreement. One 
park is operated by the Corps. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance continued. During the fiscal year 
353,348,000 kilowatt-hours of electrical energy were generated 
at project of which 351,141,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Green Peter Lake project 
on Middle Santiam River are shown in Table 37-M. 
47. HILLS CREEK LAKE, OR 
Location. On the Middle Fork, Willamette River, 47.8 
miles from mouth and 26.5 miles upstream from Lookout 
Point Dam. Middle Fork, Willamette River rises on west 
slope of Cascade Range and flows northwesterly to its junction 
with Coast Fork, Willamette River. Dam is about 45 
miles southeast from Eugene, OR. 
Existing project. An earth-and-gravel-fill dam about 
2,150 feet long at the crest and 338 feet above lowest point of 
the general foundation. A gate-controlled concrete gravity 
chute-type spillway is in right abutment. Diversion tunnel, 
outlet tunnel and power tunnel are in same abutment. Powerhouse 
with two 15,000 kilowatt units is located next to 
spillway. Hills Creek Lake is about 8.5 miles long and provides 
storage capacity at full pool of 356,000 acre-feet. Project 
controls runoff of drainage area of 389 square miles and 
is an integral unit of comprehensive plan for development of 
water resources of Willamette River Basin. Hills Creek Lake 
and Lookout Point Lake are operated as a unit for control of 
floods and generation of power on Middle Fork Willamette 
River. These projects, in conjunction with Dexter reregulating 
dam and Fall Creek Lake flood control system, will effectively 
control floods on Middle Fork and provide maximum 
efficient generation of hydroelectric power. Recreation facilities 
are provided by the U.S. Forest Service. Hills Creek 
power units are remote controlled from Lookout Point. 
Construction of project, initiated May 1956, was completed 
June 1963. The project was placed in service for useful flood 
control in November 1961. On May 2, 1962, the two power 
units were placed on-line. Through September 1989, power 
generation totaled 4.4 billion kilowatt-hours. Of the gross 
income from sale of this power by Bonneville Power Administration, 
$18,172,346 was reimbursed to the U.S. Treasury to 
recover Corps of Engineers project investment and operating 
costs. 
Local cooperation. None required. 
37-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance continued. During fiscal year, 
190,240,000 kilowatt-hours of electrical energy were generated 
at project, of which 189,759,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Hills Creek Lake on Middle 
Fork Willamette River are shown in Table 37-M. 
48. JOHN DAY LOCK AND DAM - LAKE 
UMATILLA, OR AND WA 
Location. On Columbia River about 3 miles downstream 
from mouth of John Day River and about 215 miles above 
mouth of Columbia River. 
Existing project. A dam, powerplant, navigation lock, fish 
ladders, and appurtenant facilities with a slack-water lake 
about 75 miles long extending to McNary Lock and Dam. 
Included is relocation of railroads, highways, utilities, and 
communities affected by the impoundment. The project as 
originally authorized would have provided 2,000,000 acrefeet 
of flood control storage. As modified, the project provides 
500,000 acre-feet of flood control storage between 
elevations 257 and 268. The structure is 5,900 feet in length 
and stands about 161 feet above streambed. Powerhouse has 
space for 20 generating units of 135,000 kilowatts each; 16 
units have been installed for a present capacity of 2,160,000 
kilowatts. Principal project data are set forth in Table 37-P. 
A detailed description of project as authorized and modified 
is on pages 1992 and 1993 of Annual Report for 1962 
under the Walla Walla District. 
Construction began July 1958 and the project was opened 
to navigation April 1968. The main dam contract is complete. 
Lock rehabilitation work begun in FY 1980 was completed in 
FY 1986. Entire project is estimated to be 99 percent complete. 
Through September 1989 power generation totaled 
217.7 billion kilowatt-hour. Of the gross income from sale of 
this power by Bonneville Power Administration, 
$283,028,949 was reimbursed to the U.S. Treasury to recover 
Corps of Engineers project investment and operating costs. 
Estimated Federal cost of new work is $512,523,000, consisting 
of $512,190,000 Corps of Engineers and $333,000 for 
Coast Guard navigation aids. 
Local cooperation. Recreation facilities at 5 parks are operated 
and maintained by local agencies under lease agreement 
with the Corps. Six developed recreation areas are operated 
and maintained by the Corps of Engineers. Any future recreation 
development will require cost sharing. 
Operations during fiscal year. New work: Engineering and 
design activities on modifications to the fish bypass system 
and construction of the intake gantry crane continued. 
Maintenance: Normal operation and maintenance continued. 
During fiscal year 9,827,200,000 kilowatt-hours of electrical 
power were generated by the 16 generating units of 
which 9,809,843,000 kilowatt-hours were delivered to Bonneville 
Power Administration, the marketing agency. Traffic 
through the navigation lock, consisting of petroleum products, 
grains, and miscellaneous cargo. During the fiscal year 
traffic through the locks is estimated to total 7,682,755 tons. 
Rehabilitation: Refurbishment of one generator winding 
and rebuilding (to strengthen) one turbine was completed. 
Work on the next scheduled unit was initiated. Work continued 
on installation of the new control system to increase 
reliability and ease of operation of the powerhouse. Work 
continued for the FY 1990 completion of station service 
improvement contract which will allow black start up of the 
powerhouse. 
49. LOOKOUT POINT - DEXTER LAKES, OR 
Location. On Middle Fork, Willamette River at Meridian 
site, 21.3 miles from mouth. Middle Fork, Willamette River, 
rises in Lane County on western slope of Cascade Range and 
flows northwesterly to its junction with Coast Fork, which is 
head of mainstem Willamette River. Dam is about 22 miles 
southeast from Eugene, OR. 
Existing project. A main dam at Meridian site and a 
reregulating dam 3 miles downstream at Dexter site. Both 
dams are earth-and-gravel- fills with concrete spillways and 
have power generating facilities. Main dam is 258 feet high 
from lowest point of the general foundation to deck and is 
3,381 feet long at crest forming a reservoir 14.2 miles long 
providing storage of 456,000 acre-feet at full-pool level. 
Reservoir controls runoff of tributary drainage area of 991 
square miles. Spillway, 274 feet long, is a gate-controlled 
overflow type, forming right abutment. Outlet works consisting 
of slide- gate-controlled conduits pass through spillway 
section. Powerhouse has three main generating units with a 
capacity of 120,000 kilowatts. Dexter reregulating dam has a 
maximum height of 107 feet above lowest point of the general 
foundation and is 2,765 feet long at crest, forming a full pool 
of 27,500 acre-feet extending upstream to main dam and 
providing pondage to regulate Lookout Point powerhouse 
water releases to a uniform discharge. Spillway consists of a 
gate-controlled overflow section 509 feet long forming right 
abutment. 
Flow regulation is accomplished by use of spillway gates 
and releases through powerhouse, which contains one 
15,000-kilowatt unit. Lookout Point and Dexter Lakes are 
operated as a single unit of a coordinated system of reservoirs 
to protect Willamette River Valley against floods, to provide 
needed hydroelectric power, and to increase low water flows 
for navigation, irrigation, and other purposes. Existing project 
authorized as a unit of comprehensive plan for flood 
control and other purposes in Willamette River Basin. 
Construction of project initiated May 1947 was completed 
June 1961, except for construction of additional recreation 
facilities funded through the Code 710 program. Future recreation 
facilities will be provided in accordance with the costsharing 
contract with Lane County and will require a 50 
percent contribution by Lane County and is subject to funding 
availability by the Government and the County. At Lookout 
Point powerhouse, generating units 1,2, and 3 were 
placed in commercial operation December 1954, February 
1955, and April 1955, respectively. At Dexter powerhouse 
the single unit was placed on- line May 1955. Dexter was 
placed in operation for reregulation in December 1954. 
37-20

PORTLAND, OREGON DISTRICT 
Through September 1989 power generation totaled 14.1 billion 
kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, $62,874,898 was 
reimbursed to the U.S. Treasury to recover Corps of Engineers 
project investment and operating costs. 
Local cooperation. A multiple project cost sharing agreement 
has been in force with Lane County since September 
1976. It includes 4 projects and 13 parks. All these parks are 
managed by Lane County under lease agreement. Recreation 
opportunities are provided at 2 parks on Dexter Lake which 
are operated by Lane County via the multi-project cost-sharing 
agreement and lease instruments. The north shore of 
Lookout Point Lake is also leased to Lane County for recreation 
purposes; there is essentially no development. Future 
development will require a supplement to the cost sharing 
agreement. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance continued. During fiscal year, 
439,206,000 kilowatt-hours of electrical power energy were 
generated at project of which 437,361,000 kilowatt-hours 
were delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Lookout Point Lake 
project on Middle Fork Willamette River are shown in Table 
37-M. 
50. LOST CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Location. On Upper Rogue River at mile 153.6 about 30 
miles northeasterly from Medford, OR. 
Existing project. A rock and gravel-fill embankment dam 
about 327 feet high from streambed to crest, with an overall 
length of 3,750 feet with an impervious earth core and a 
gate-controlled concrete spillway. Powerhouse is on right 
abutment and houses two Francis-type turbines with installed 
capacity of 24,500 kilowatts each. Regulating outlet 
facility was provisions for temperature regulation for releases 
in interest of fishery enhancement is also on right bank. 
Reservoir 10 miles long provides 315,000 acre-feet of usable 
storage. Project provides control of runoff of drainage area of 
674 square miles. In addition to hydroelectric power generation, 
project provides flood control; irrigation, future municipal 
and industrial (M&I) water supply, fish and wildlife enhancement, 
water quality control and recreation benefits. 
Construction of project initiated July 1967 is complete. 
Generating units 1 and 2 were placed in commercial operation 
July 6 and July 13, 1977, respectively. Physical in-service 
date for flood control was February 18, 1977. Final environmental 
statement was filed with Council on Environmental 
Quality in June 1972. Recreation opportunities are provided 
by 4 parks at the project. The State of Oregon operates 2 
parks, including a 200 unit campground, part of Stewart State 
Park. Through September 1989, power generation totaled 
3.5 billion kilowatt- hours. Of the gross income from sale of 
this power by Bonneville Power Administration, $18,985,976 
was reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. Authorizing act required that local 
agencies furnish assurances prior to construction that demands 
will be made for future use of water supply storage 
within a period that will permit repayment of costs, including 
interest, allocated to water supply within life of the project; 
that State of Oregon take action, prior to construction to 
insure maintenance in stream of flows to be released for 
fishery; in addition, costs allocated to irrigation would have to 
be repaid in manner and to an extent consistent with reclamation 
laws and policies; and costs allocated to power will be 
repaid on a system basis by revenue from sales of power in 
Pacific Northwest Federal system by Bonneville Power Administration. 
A survey in September, 1980 of M&I water 
supply needs showed nine communities with water supply 
needs. A contract for M&I supply has been completed with 
one of the communities. Assurances for municipal and industrial 
water supply were obtained from six communities in 
Rogue River Valley. On February 26, 1966 Oregon State 
Department of Fish and Wildlife agreed to operate Cole M. 
Rivers Fish Hatchery, the largest in Oregon, for mitigation 
and enhancement of fish. The Corps provides full funding for 
the operation and maintenance of the hatchery. The hatchery 
became operational in 1972. 
Operations during fiscal year. Maintenance: Normal operation 
and maintenance continued. During fiscal year 
302,517,000 kilowatt-hours of electrical power energy were 
generated by project of which 299,737,000 kilowatt-hours 
were delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Lost Creek Lake on 
Rogue River are shown in Table 37-M. 
51. THE DALLES LOCK AND DAM - LAKE 
CELILO, WA AND OR 
Location. On Columbia River at head of pool behind Bonneville 
Dam, about 192 miles above mouth of river and 88 
miles east of Portland, OR. 
Existing project. A dam, powerplant, navigation lock, and 
appurtenant facilities. Improvement provides for navigation 
and hydroelectric power generation. Dam is designed for a 
normal pool at elevation 160 feet at mean sea level. Normal 
pool forms a reservoir extending upstream about 23 miles 
providing slackwater to John Day Dam site. The Dalles Dam 
is 8,700 feet long and consists of a rock, gravel, and sand river 
closure section from Oregon shore connecting to a nonoverflow 
section which in turn joins powerhouse, then concrete 
nonoverflow sections connecting spillway with powerhouse 
and spillway with navigation lock at right abutment on Washington 
shore. Fish-passing facilities including two ladders 
and a fish lock are provided. Powerhouse was constructed for 
14 units initially with substructure for eight additional units, 
an ultimate total of 22 units. Initial installation, excluding two 
13,500 kilowatt fish-water units, is 1,092,000 kilowatts. With 
eight units installed for a capacity of 687,800 kilowatts. The 
total generating capacity is 1,806,800 kilowatts. Structures 
are founded on Columbia River basalt. Principal data concerning 
lock, spillway, and powerhouse are set forth in Table 
37-P. 
Major construction of project initiated February 1952, was 
completed October 1960 when unit No. 14 was placed in 
37-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
commercial operation. Initial contract for additional units 
15-22 was awarded in September 1967. Additional 8-unit 
phase was completed when unit 22 was placed in commercial 
operation in November 1973. Basic recreation facilities were 
developed with construction funds at 4 parks on Lake Celilo. 
These parks were further expanded with code 710 funds in 
the late 60's and early 70's. Two parks are operated by Washington 
State Park Commission under a lease agreement. 
Studies for adding power generation facilities to the North 
Shore Fish Ladder Auxiliary Water supply System were initiated 
in October 1979 and completed in December 1980. 
These facilities would provide baseload generation (3.5 
megawatts) and would not impact the present operation of 
the North Fish Ladder. However, it was determined that it 
was not within the Chief of Engineer's authority to add these 
power facilities. A local interest, North Wasco County Public 
Utility Distric pursued the construction of these power facilities 
through the FERC license processes and awarded a construction 
contract in September 1989. Power-on-line is 
scheduled for August 1991. Seufert Visitor Center was completed 
in September 1980. Through September 1989, power 
generation totaled 225.4 billion kilowatt- hours. Of the gross 
income from sale of this power by Bonneville Power Administration, 
$286,944,155 was reimbursed to the U.S. Treasury 
to recover Corps of Engineers project investment and operating 
costs. 
Local cooperation. Further recreation development will 
require cost sharing and assumption of operation and maintenance 
by local, non-federal sponsor. 
Operations during fiscal year. New work: Engineering and 
design activities associated with preparation of a general design 
memorandum for juvenile fish bypass facilities were 
initiated. 
Maintenance: Unit 5 failed on 6 February 1989 and a 
contract was awarded to replace windings. Normal operation 
and maintenance continued. During fiscal year 7,642,608,000 
kilowat-hours of electrical power energy were generated at 
project of which 7,623,175,000 kilowatt-hours were delivered 
to Bonneville Power Administration, the marketing agency. 
Traffic through the navigation lock consisted of petroleum 
products, grains and miscellaneous cargo. During the fiscal 
year traffic through the locks is estimated to total 7,947,786 
tons. 
General Investigations 
52. SURVEYS 
Fiscal year costs were $632,399 of which $123,245 was for 
navigation studies, $24 for flood damage prevention studies, 
$279,392 for comprehensive studies, $103,024 for miscellaneous 
activities, and $126,714 for coordination with other 
agencies. 
53. COLLECTION AND STUDY OF BASIC 
DATA 
International water studies. The Columbia River Treaty 
between Canada and the United States of America relating 
to cooperative Development of the Water Resources of the 
Columbia River Basin was signed at Washington, D.C., on 
January 17, 1961, and the exchange of ramifications took 
place on September 16, 1964. 
Implementations of the Treaty by the United States and 
Canada entities under the guidance of the Permanent Engineering 
Board has continued. The two permanent committees 
established by the entities, the Operating Committee 
and the Hydrometeorological Committee, continue to function. 
Costs for support of both committee activities were $14,080 
for the fiscal year. 
Flood plain management services. Flood Plan Management 
Services Program comes under Section 206 of the 1960 
Flood Control Act, PL 86-645, as amended. Through technical 
services and planning guidance, the program encourages 
comprehensive flood plain management planning at all levels 
to reduce the potential for losses to life and property from 
floods. Federal and non- Federal agencies and the private 
sector are assisted with planning and development information 
for flood hazard areas. This assistance is in the form of 
local flood plain regulations, Federal Insurance Program requirements, 
and Executive Order 11988 guidelines. Such 
assistance may include factual flood information (available or 
determined) and interpretation on flood frequencies, extent 
of flooding, flood-water velocity, duration of flooding and 
floodway limits. 
Services accomplished during fiscal year: Technical services 
and planning guidance responses furnished totaled 755. 
Of this total, 68 were from other Federal agencies; 122 from 
non-Federal agencies; and 565 from private sector realtors, 
corporations, lending institutions, engineers, architects, and 
others. Cost for providing these services during the fiscal year 
totaled $130,802. 
A preliminary evaluation of flood protection measures was 
developed and furnished to the city of Stanfield, OR. Subsequently, 
the city of Stanfield is developing a preliminary 
implementation plan incorporating street and utility rehabilitation/
upgrading plans into the flood protection plan and 
obtaining citizen input. The final flood control plan will be 
completed in FY 1990. Costs during the fiscal year totaled 
$28,914. 
37-22

PORTLAND, OREGON DISTRICT 
TABLE 37-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY 86 FY 87 FY 88 FY 89 to 
In Text Sep.30, 1989 
1. Bonneville Navigation New Work 
Lock, Bonneville Dam, 
OR and WA 
(Federal Funds) 
(Inland Waterway 
Trust Fund) 
2. Chetco River, OR 
3. Columbia and Lower 
Willamette Rivers 
Below Vancouver, 
WA and Portland, OR 
(Federal Funds) 
(Contributed Funds) 
4. Columbia River at 
Baker Bay, WA 
5. Columbia River 
Between Chinook, 
WA, and Head of 
Sand Island 
6. Columbia River at 
The Mouth, OR and 
WA 
7. Columbia River 
Between Vancouver, 
WA and The Dalles 
OR 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
6,451,000 8,340,000 19,607,000 24,150,000 
6,420,377 8,360,936 19,581,238 14,050,665 
- 14,959,000 19,593,000 24,150,000 
- 14,570,957 19,560,249 12,732,518 
552,000 300,200 631,000 132,000 
554,702 296,243 634,978 129,856 
11,459,400 10,932,230 
11,430,195 10,861,438 
438,000 311,000 
438,112 252,899 
13,201,000 12,630,000 
12,867,766 13,065,333 
19,000 515,000 
75,829 516,034 
594,000 501,000 659,000 554,000 
605,577 505,301 582,990 631,348 
347,900 
352,944 
8,911,415 6,302,400 7,953,000 8,201,000 
8,818,651 6,385,156 7,963,652 8,207,278 
429,000 441,000 239,000 201,000 
438,416 428,767 246,672 201,199 
37-23 
58,702,30751 
48,413,21651 
58,702,000 
46,863,724 
2,043,7131 
2,043,7131 
5,882,626 
5,879,812 
28,349,3042 
28,349,3042 
272,910,7563 
272,882,728 3 
665,9544 
665,9544 
941,252 
941,252 
3,880,185 
3,879,944 
220,2835 
220,2835 
5,357,813 
5,357,772 
24,913,6616 
24,913,6616 
106,747,4997 
106,735,5057 
7,322,878 
7,322,878 
5,989,5098 
5,989,5098 
12,147,9489 
12,142,2989

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY 86 FY 87 FY 88 FY89 to 
In Text Sep.30, 1989 
8. Coos Bay, OR New Work 
(Federal Funds) 
(Contributed Funds) 
9. Coos and Millicoma 
Rivers, OR 
10. Coquille River, OR 
11. Depoe Bay, OR 
12. Elochoman Slough, WA 
14. Port Orford, OR 
16. Rogue River Harbor 
At Gold Beach, OR 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work 
Contrib 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp 
Cost 
Major Rehab 
Approp. 
Cost 
3,041,000 
3,085,466 
3,933,300 3,740,000 10,584,000 
3,886,842 3,787,393 10,573,892 
170,000 51,600 144,000 144,000 
175,970 50,373 137,266 152,741 
333,000 339,000 198,000 114,000 
341,125 336,007 184,652 129,841 
27,000 45,000 
29,397 43,260 
140,000 
134,729 
59,000 
57,942 
208,000 295,000 247,000 189,000 
210,184 293,510 248,451 188,579 
354,000 917,800 614,000 705,000 
368,738 824,626 704,787 708,632 
37-24 
TABLE 37-A 
(Continued) 
29,750,09210 
29,750,09210 
77,481,95211 
77,448,59011 
2,335,966 
2,335,966 
486,680 
486,680 
350,23812 
350,23812 
2,033,610 
2,033,475 
693,36613 
693,36613 
5,694,94414 
5,694,05014 
367,364 
367,364 
932,876 
925,316 
18,64152 
18,64152 
75,648 
74,590 
758,692 15 
758,69215 
3,135,329 
3,134,175 
4,156,25216 
4,156,25216 
10,565,52017 
10,565,01917 
635,783 
635,783

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY 86 FY 87 FY 88 FY 89 to 
In Text Sep.30, 1989 
17. Siuslaw River, OR New Work 
(Federal Funds) 
(Contributed Funds) 
18. Skamokawa Creek, WA 
19. Skipanon Channel, 
OR 
20. Tillamook Bay and 
Bar, OR 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp 
Cost 
2,081,000 62,000 -25,000 
1,821,733 315,633 -15,013 
581,000 689,000 473,000 353,000 
584,714 687,256 453,180 374,215 
45,000 45,000 
45,000 24,127 
1,394 
-8,921 
11,953 
- 31,000 
- 30,103 
292,000 294,000 
291,905 284,590 
59,000 20,000 
68,044 20,691 
897 
10,000 224,000 
19,783 224,676 
28,000 
27,333 
57,500 
59,942 
29,502,21218 
29,502,21218 
11,999,09919 
11,997,14819 
879,285 
879,285 
493,611 
493,611 
2,400 
2,400 
414,782 
414,782 
280,854 
280,854 
3,357,014 
3,356,869 
22,434,82720 
22,434,82720 
3,023,29021 
3,022,83621 
2,839,799 
2,839,799 
21. Tongue Point, OR 
(Federal Funds) 
(Contributed Funds) 
22. Umpqua River, OR 
New Work 
Approp. 
Cost 
New Work 
Contrib.. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
956,000 
965,341 
32,500 219,000 
25,934 121,926 
89,500 
1,723,900 1,141,000 
1,665,197 1,211,354 
37-25 . 
2,030,000 
2,123,166 
1,779,100 
261,787 
2,281,500 
2,271,026 
1,868,600 
261,787 
661,000 
662,499 
17,718,87722 
17,718,87722 
24,933,889 
24,932,990 
2,500,677 
2,500,677

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY 86 FY 87 FY 88 FY 89 to 
In Text Sep.30, 1989 
23. Willamette River at New Work 
Willamette Falls, OR 
24. Yaquina Bay and 
Harbor, OR 
25. Applegate Lake, 
Rogue River Basin 
OR 
26. Blue River Lake, OR 
27. Cottage Grove Lake, 
OR 
28. Dorena Lake, OR 
29. Elk Creek Lake, 
Rogue River Basin, 
OR 
30. Fall Creek Lake, OR 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
-- Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
496,000 748,000 1,160,000 610,000 
510,761 746,399 1,163,445 619,085 
493,000 1,834,400 7,399,000 686,000 
523,138 1,817,346 7,395,427 713,859 
9,300 
47,546 
550,000 
556,380 
996 6,767 11,238 
625,000 399,000 437,000 
605,461 396,186 460,286 
213,000 284,000 163,000 135,000 
219,165 267,968 178,769 135,957 
708,000 896,000 635,000 663,000 
730,380 854,918 641,975 690,448 
382,000 619,000 472,000 705,115 
405,563 544,805 520,149 711,406 
32,226,000 9,100,000 30,437,000 5,911,000 
20,345,020 26,012,598 29,918,249 6,361,434 
255,000 341,000 398,000 361,000 
258,853 337,548 387,439 359,851 
520,00523 
520,00523 
16,476,82324 
16,474,91524 
234,794 
234,794 
19,242,04625 
19,242,04625 
28,594,70226 
28,594,44326 
12,005 
12,005 
91,642,489 
91,642,489 
4,217,70049 
4,216,23449 
32,038,22527 
32,038,22527 
2,495,991 
2,495,228 
4,013,12328 
4,013,12328 
10,172,67829 
10,149,09529 
14,568,26230 
14,568,26230 
6,216,289 
6,193,894 
99,540,579 
99,240,776 
22,118,2643' 
22,118,264*' 
5,146,415 
5,130,097 
37-26

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY 86 FY 87 FY 88 FY 89 to 
In Text Sep.30, 1989 
31. Fern Ridge Lake, OR New Work 
36. Lower Columbia River 
Basin Bank Protection 
OR & WA 
37. Mt. St. Helens 
and Vicinity, WA 
38. Mt. St. Helens 
Sediment Control, 
Castle Rock, WA 
(Federal Funds) 
(Contributed Funds) 
41. Willamette River 
Basin Bank Protection, 
OR 
42. Willow Creek Lake, OR 
43. Bonneville Lock and 
Dam - Lake Bonneville 
OR and WA 
44. Cougar Lake, OR 
45. Detroit Lake, OR 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab 
Approp 
Cost 
847,000 2,332,000 760,000 747,000 
856,543 2,289,234 778,941 755,964 
2,850,000 216,000 
2,840,161 224,638 
6,280,000 3,740,000 
6,347,141 3,647,394 
5,000 
8,357 
76,000 
74,921 
10,000 -80,000 
163,122 -89,264 
1,400,000 29,265,000 55,468,000 12,195,000 
1,365,665 28,825,326 38,873,805 27,743,424 
- 3,500,000 
343,000 389,000 
300,794 458,945 
96,000 70,200 
95,917 60,544 
- 149,240 
- 3,500,000 
55,000 
62,498 
80,000 
84,524 
30,000 
25,308 
65,000 
62,717 
(See Walla Walla, WA District) 
382,000 403,000 501,000 687,000 
405,626 399,378 496,680 685,094 
14,826,000 6,850,000 4,098,000 1,152,000 
14,958,973 5,472,560 4,102,274 2,405,289 
12,994,000 11,512,000 10,754,000 10,727,000 
12,979,585 11,118,185 10,944,639 10,813,072 
34 
1,141,000 1,260,000 696,000 786,000 
1,153,266 1,245,605 679,113 818,440 
1,456,000 1,557,000 1,294,000 1,539,000 
1,435,467 1,554,727 1,320,145 1,530,767 
8,526,93532 
8,526,93532 
14,003,63433 
13,984,29733 
20,871,745 
20,869,865 
42,158,000 
42,125,370 
98,328,000 
96,808,220 
3,649,240 
3,500,000 
24,782,81634 
24,778,12034 
3,756,744 
3,748,772 
2,557,000 
2,537,691 
765,396,60435 
765,189,84235 
163,263,10136 
162,877,58836 
58,636,39337 
58,636,39337 
12,272,81650 
12,272,45550 
62,729,698 
62,729,698 
28,250,77248 
28,225,75848 
363,086 
363,086 
37-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY 86 FY 87 FY 88 FY 89 to 
In Text Sep.30, 1989 
46. Green Peter-Foster New Work 
Lakes, OR 
47. Hills Creek Lake, OR 
48. John Day Lock and 
Dam - Lake Umatilla, 
OR and WA 
49. Lookout Point 
Lake, OR 
50. Lost Creek Lake, 
Rogue River 
Basin, OR 
51. The Dalles Lock and 
Dam - Lake Celilo, 
WA and OR 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,688,000 1,925,000 
1,667,370 1,887,327 
1,824,000 1,773,000 
1,823,898 1,822,417 
446,000 658,000 518,000 595,000 
457,531 643,258 532,759 592,142 
8,685,000 1,930,000 350,000 
8,665,982 1,941,379 280,217 
39,000 
55,598 
6,125,000 8,103,000 7,248,000 8,019,500 
6,257,535 8,037,902 7,230,856 7,983,895 
4,450,000 3,800,000 3,940,000 2,725,000 
4,418,339 3,766,284 3,861,592 2,702,857 
2,194,000 2,520,000 2,321,000 3,085,000 
2,156,310 2,461,925 2,343,553 3,144,995 
4,700 
7,270 132 8,652 7,688 
2,420,000 2,636,000 2,586,000 2,657,000 
2,466,125 2,627,487 2,536,371 2,646,763 
1,210,000 
488,415 
8,927,000 7,095,000 7,731,000 7,695,000 
9,027,285 6,866,803 7,747,465 7,721,519 
1. Excludes $17,742 contributed funds for new work. 
2. Includes $1,529,413 for previous project. 
3. Includes $150,955 allotted from deferred maintenance funds, 
Code 700, $62,296 for public works accelerated program repair, 
and $1,214,865 for previous project. Excludes $24,320 expended 
from contributed funds prior to 1964. . 
4. Excludes $31,636 contributed by city of Astoria and Bumble Bee 
Sea Foods, Astoria, OR (not part of regular project). Includes 
$223,026 expended from contributed funds prior to 1964 and 
$428,136 contributed by Port of Portland and $14,792 by Port of 
Vancouver. 
5. Includes $84,930 rehabilitation funds. 
6. Includes $1,986,253 for previous project and $608,111 allotted 
and expended under Code 710, recreation facilities at completed 
project. Excludes $500,000 contributed funds. 
7. Includes $2,186,000 for previous project and $1,188,625 under 
deferred maintenance, Code 700. 
8. Includes funds under Code 721 (small authorized projects) 
$30,393. Entrance to Oregon slough; $161,897, Camas-Washougal 
Turning Basin; $227,908, Hood River Small Boat Basin; $157,470, 
Bingen, WA, Barge Channel; and $140,619, The Dalles Small 
Boat Basin. 
9. Includes $2,033,408 under code 700 (Deferred Maintenance). 
10. Includes $802,096 for previous project, Excludes contributed 
funds. 
11.Includes $178,801 for previous project and $1,444,640 under 
Code 700, Deferred Maintenance. Excludes $8,387 contributed 
funds. 
37-28 
TABLE 37-A 
(Continued) 
84,005,78838 
84,005,78838 
25,575,13239 
25,558,55939 
45,700,619 
45,700,619 
8,790,26740 
8,784,03140 
512,255,24641 
512,112,92241 
113,744,65942 
113,478,42642 
22,208,000 
22,042,072 
88,238,39543 
88,238,39543 
41,840,60544 
41,785,12444 
136,408,150 
136,408,150 
24,742,80045 
24,620,17145 
302,274,28846 
301,552,70346 
105,491,00847 
105,211,23847

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
12. Excludes $80,000 (other funds) contributed for new work by 
Port of Coos Bay to cover additional cost of disposing of dredge 
spoils in Coos Bay, OR; includes $8,000 for previous project. 
13. Includes $340,726 for previous project. Excludes $72,891 
contributed funds. includes $36,00 under Code 711. 
14. Includes $41,467 for previous project and $78,500 under Code 
700, Deferred Maintenance. 
15. Excludes $9,900 contributed funds. 
16. Excludes $13,779 (other funds) contributed for additional 
landfill and extension of drainage lines. 
17. Includes $21,000, Wedderburn Study Funds. 
18. Includes $1,159,357 for previous project. 
19. Includes $10,611 for previous project and $188,000 under code 
700, Deferred Maintenance. 
20. Includes $77,209 for previous project and $57,767 under Code 
720 (Small Authorized Projects) Garibaldi Boat Basin. Excludes 
$592,622 contributed funds and $300,000 channel dredging by local 
interest. 
21. Includes $71,498 for previous project. Excludes $6,450 
expended from contributed funds. 
22. Includes $39,242 for previous project. Excludes $6,450 
expended from contributed funds. 
23. Excludes $300,000 contributed funds. 
24. Includes $452,110 on operation and care from permanent 
indefinite appropriation and $150,000 under maintenance and 
operation of dams and other improvements of navigable waters. 
25. Includes $707,313 for previous project and $170,000 
appropriated from public works acceleration program for north 
jetty rehabilitation. 
26. Includes $6,026 for previous project. 
27. Includes $96,000 pro rata share of site selection costs in lieu of 
Quartz Creek Lake. 
28. Includes $1,639,828 allotted and expended under Code 710, 
recreation facilities at completed project. 
29. Includes $167,878 special recreation use fees. Includes $66,678 
under maintenance and operation of dams and other 
improvements to navigable waters. 
30. Includes $1,038,790 allotted and expended under Code 710, 
recreation facilities at completed project. 
31. Includes $1,026,264 allotted and expended under Code 710, 
recreation facilities at completed project. 
32. Includes $3,894,673 allotted and expended under Code 710, 
recreation facilities at completed project and $136,482 allotted 
under 721 (small authorized project) reservoir modification. 
Excludes $2,100 (other funds contributed). 
33. Includes $9,750 allotted under Code 700, deferred 
maintenance. Includes $66,678 under maintenance and operation 
of dams and other improvements to navigable waters. 
34. Excludes $93,733 contributed funds. 
35. Includes $12,200,000 Public Works Administration funds, 
$20,240,700 National Recover Act Funds, $27,195,400 modification 
for peaking funds, $136,457 Code 710, recreation facilities at 
completed project funds and $627,593,352 allotted and 
$642,322,501 expended second powerhouse funds, $6,000 allotted, 
$6,000 expended power units funds. 
36. Includes $540,000 deferred maintenance funds, Code 700 and 
$1,692,148 maintenance and operation of dams and other 
improvements of navigable waters. 
37. Includes $96,000 pro rata share of site selection costs in lieu of 
Quartz Creek Lake. Includes $1,789,988 allotted and $1,789,954 
expended for Strube Lake and Cougar Additional Unit. 
38. Includes $113,000 pro rata share of site selection costs in lieu 
of Quartz Creek Lake. 
39. Includes $288,578 under maintenance and operation of dams 
and other improvements of navigable waters. 
40. Includes $75,400 under maintenance and operation of dams 
and other improvements of navigable waters. 
41. Includes $25,984 allotted and expended under 710, recreation 
facilities at completed projects. 
42. Includes $1,361,900 for O&M and fish evaluation of Spring 
Creek Hatchery (funds revoked and paid to USFWS at OCE level, 
but a cost to project); includes $423,800 special recreation use fees. 
Includes $933,438 under maintenance and operation of dams and 
other improvements of navigable waters. 
43. Includes $457,611 allotted and expended under 710, recreation 
facilities at completed projects. 
44. Includes $293,578 under maintenance and operation of dams 
and other improvements of navigable waters. 
45. Includes $288,578 under maintenance and operation of dams 
and other improvements of navigable waters. 
46. Includes $1,140,747 allotted and expended under 710, 
recreation facilities at completed projects, and $52,997,220 allotted 
and expended additional units 15 - 22 funds. 
47. Includes $721,490 under maintenance and operation of dams 
and other improvements of navigable waters. 
48. Includes $237,078 under maintenance and operation of dams 
and other improvements of navigable waters. 
49. Includes $66,678 under maintenance and operation of dams 
and other improvements of navigable waters. 
50. Includes $161,678 under maintenance and operation of dams 
and other improvements of navigable waters. 
51. Includes $24,307 under code 422 General Investigation. 
52. Exculdes $86,586 contributed funds. 
37-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
TABLE 37-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. BONNEVILLE NAVIGATION LOCK, BONNEVILLE DAM, OR AND WA 
Aug 15, 1985 
Nov 17, 1986 
Mar 02 , 1945 
Oct 27, 1965 
Dec 04, 1981 
3. 
Feb 27, 1911 
Jul 25, 1912 
Jul 27, 1916 
Aug 08, 1917 
Sep 22, 1922 
Mar 04, 1923 2 
Mar 03, 1925 
Mar 03, 1927 
Jul 03, 1930 
Sep 06, 19333 
Aug 30, 1935 
Aug 30, 1935 
Aug 30, 1935 
Aug 26, 1937 
Aug 26, 1937 
Mar 02, 1945 
Mar 02, 1945 
Jul 24, 1946 
Construction of a new navigation lock just south P. L 99-88 
of existing lock. 
Construction to be funded 50% from fuel taxes paid P.L 99-662 
into Inland Waterways Trust Fund. 
CHETCO RIVER, OR 
To provide for the stabilization of the channel, 
by constructing jetties and dredging. 
Modification of channel entrance and channel 
improvements. 
Deepen channel 2 feet to 16 feet, extend the existing 
jetty system 750 feet for the North, and 1,250 feet 
for the South jetty. 
COLUMBIA AND LOWER WILLAMETTE RIVERS BELOW 
VANCOUVER, WA AND PORTLAND, OR 
2 pipeline dredges and accessories. 
Increasing main channel to 30 feet. 
Consolidating improvement below Portland, OR and 
between Vancouver, WA and mouth of Willamette. 
For the Cathlamet channel. 
Construct an additional dredge (dredge was not built) 
and accessories for better maintenance, and 
construct contraction works. 
Channel from deep water in Willamette Slough to 
deep water in Columbia River. 
Depth of 25 feet and width of 300 feet from mouth of 
Willamette River to Vancouver, WA 
Closing east channel at Swan Island in Willamette River 
on condition that main channel to be opened to project 
dimensions on west side of island by Port of Portland 
For a 35-foot channel 500 feet wide from Portland to 
the sea. 
A channel 28 feet deep and 300 feet wide from mouth of 
Willamette River to Vancouver, with 2 turning 
basins, each generally 28 feet deep by 800 feet wide by 
2,000 feet long. 
A channel in Columbia River from mouth of Willamette 
to interstate highway bridge at Vancouver, WA, 
30 feet deep and 300 feet wide, with 2 turning 
basins at Vancouver. 
Maintenance of not to exceed 35 foot depth at low water 
in Portland Harbor and Willamette River between its 
mouth and Broadway Bridge at Portland. 
Auxiliary channels, 30 feet deep, 300 feet and 500 
feet at St. Helens. 
Extension of lower turning basin at Vancouver, WA, 
1,000 feet downstream. 
An auxiliary channel 24 feet deep and 200 feet wide 
along waterfront at Rainier, OR. 
Improvement of old mouth of Cowlitz River. 
An auxiliary channel in vicinity of Longview, WA. 
A small-boat mooring basin at Astoria, OR. 
H. Doc. 817, 77th Cong., 2d Sess 
S. Doc. 21, 89th Cong., 1st Sess. 
S. Doc. 10, 96th Cong., 1st Sess. 
H. Doc. 1278, 61st Cong., 3d Sess. 1 
H. Doc. 1278, 61st Cong., 3d Sess. 1 
No Prior Report 
H. Doc. 120, 63d Cong., 1st Sess.1 
H. Doc. 1009, 66th Cong., 3d Sess. 
H. Doc. 156, 67th Cong., 2d Sess. 
H. Doc 126, 68th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 10 
69th Cong., 2d Sess. 
H. Doc. 195, 70th Cong., 
1st Sess. and Rivers and Harbors 
Committee Doc. 8, 71st Cong., 
1st Sess. 1 
H. Doe. 249, 72d Cong., 2d Sess. 1 
Rivers and Harbors 
Committee Doc. 1, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 6, 
73d Cong., 1st Sess. 1 
H. Doc. 235, 72d Cong., 1st Sess.' 
Rivers and Harbors 
Committee Doc. 81, 
74th Cong., 2d Sess. 1 
H. Doc. 203, 75th Cong., 1st Sess.1 
H. Doc. 341, 77th Cong., 1st. Sess.' 
H. Doc. 630. 77th Cong., 2d Sess. 1 
H. Doc. 692, 79th Cong.,2d Sess. 
37-30

PORTLAND, OREGON DISTRICT 
TABLE 37-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
A channel 35 feet deep and 500 feet wide from mouth 
of Willamette River to interstate highway bridge at 
Vancouver, WA, with 2 turning basins of same depth. 
A channel 40 feet deep and 600 feet wide from Vancouver, 
WA, to mouth of Columbia River; a turning basin at 
Vancouver, WA, a turning basin at Longview, WA, and a 
channel 40 feet deep in Willamette River from mouth to 
Broadway Bridge which encompasses Portland Harbor area. 
H. Doe. 203, 87th Cong., 1st Sess. 
H. Doc. 452, 87th Cong., 2d Sess. 1 
Oct 23, 1962 
Oct 23, 1962 
Dec 11, 1933 
Aug 30, 1935 
Mar 02, 1945 
May 17, 1950 
Jun 20, 1938 
Sep 03, 1954 
Mar 03, 1905 
Dec 22, 1944 
Sep 03, 1954 
Jul 30, 1983 
Aug 26, 1937 
Mar 02, 1945 
Jul 24, 1946 
Jul 24, 1946 
Jul 24, 1946 
Jul 24, 1946 
Jun 25, 1910 
Mar 02, 1919 
Sep 22, 1922 
Jan 21, 1927 
Jul 03, 1930 
COLUMBIA RIVER AT THE MOUTH, OR AND WA 
Extend South Jetty and construct North Jetty and dredging. 
Construction, operation, and maintenance of recreation 
facilities 
Bar channel of 48-foot depth and spur jetty on north 
shore.9 
Deepening the northernmost 2,000 feet of the channel 
cross section to 55 feet. 
H. Doc. 94, 56th Cong., 1st Sess. 
Sec. 4, Flood Control 
Act of 1944 as amended 
H. Doc. 249, 83d Cong., 2d Sess. 1 
P.L 98-63 
COLUMBIA RIVER BETWEEN VANCOUVER, WA, AND THE DALLES, OR 
Construct a channel 27 feet deep by 300 feet from H. Committee D 
Vancouver, WA, to Bonneville, OR. 74th Cong., 2d S 
Construct Camas-Washougal turning basin. H. Doc. 218, 76t 
Construct a channel 27 feet deep by 300 feet wide H. Doc. 704, 79t 
from Bonneville, OR, to The Dalles, OR. 
Construct a boat basin at Hood River, OR, 10 feet deep, H. Doc. 704, 79t 
500 feet wide, by 1,300 feet long. 
Construct a barge channel at Bingen, WA, 10 feet deep, H. Doc. 704, 79t] 
200 feet wide, by 1 mile long, and an access channel 
7 feet deep, 100 feet wide, by 1,000 feet long to natural 
mooring basin. 
Construct The Dalles Harbor 8 feet deep, 400 feet wide S. Doc. 89, 79th 
by 800 feet long. 
COOS BAY, OR 
Dredging the Ocean Bar Channel. H. Doec. 958, 60tl 
A channel 22 feet deep to Smith's Mill. H. Doc. 325, 65t1 
Restore North Jetty 9,600 feet long, construct a South Jetty H. Doc. 150, 67t 
about 3,900 feet long, extend 22-foot bay channel from 
Smith's Mill to Millington. 
Extend jetties to such lengths as may be practicable H. Doc. 320, 69t1 
within estimate of total cost of jetties, $3,250,000 
given in H. Doc. 150, 67th Cong. 
A channel 24 feet deep and 300 feet wide, through H. Doc. 110, 70t 
Pigeon Point Reef, following a location along westerly side of bay. 
)oc. 94, 
;ess.1 
h Cong., 1st Sess. 
h Cong., 2d Sess. 
h Cong., 2d Sess. 
h Cong., 2d Sess. 
Cong., 1st Sess.1 
h Cong.,lst Sess. 
h Cong., 1st Sess. 
h Cong., 2d Sess. 
h Cong., 1st Sess. 
h Cong., 1st Sess.1 
37-31 
Documents 
5. 
COLUMBIA RIVER AT BAKER BAY, WA 
East Channel Public Works Administration 
Main channel H. Doc. 44, 73d Cong., 1st Sess. 
West channel 8 feet deep. H. Doc. 443, 76th Cong., 1st Sess. 
West channel 10 feet deep and mooring basin with S. Doc. 95, 81st Cong., 1st Sess. 
protecting breakwaters. 
COLUMBIA RIVER BETWEEN CHINOOK, WA AND HEAD OF SAND ISLAND 
Channel 8 feet deep. Rivers and Harbors Committee 
Doc. 50,75th Cong., 2d Sess. 
Channel 10 feet deep and mooring basin. S. Doc. 8, 83d Cong., 1st Sess.1

REPORT OF THE SECRETARY OFTHE ARMY ON-CIVIL WORKS FOR FY 1989 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug 30, 1935 
Jul 24, 1946 
Jun 30, 1948 
Dec 31, 1970 
For 24-foot channel from Pigeon Point Reef to 
Smith's Mill and a turning basin above Marshfield. 
Increased dimensions of channel across bar and to 
Isthmus Slough and turning basin opposite Coalbank 
Slough and at city of North Bend; anchorage basins at 
mile 3.5 and near mile 7. 
A mooring basin and connecting channel at Charleston. 
Increase dimensions to provide for bar channel 45 feet deep, 
inner channel 35 feet deep to mile 15, and deepening 
and widening existing turning basins and anchorage area. 
COOS AND MILLICOMA RIVERS, OR 
Dredging channel from mouth to head of navigation. 
For a 5 ft depth from mouth to head of navigation on the 
Millicoma River and South Fork. Except on South Fork 
above M. 14 where 3 ft will suffice. 
COQUILLE RIVER, OR 
Dredging shoals between mouth and Riverton, and 
removing obstruction between mouth of North Fork 
and Bandon. 
For a 13-foot channel from ocean to Bandon. 
Deepen channel to 16 feet between sea and eastern end 
of North Jetty. 
Present project depth between sea and eastern end of 
North Jetty. 
Construction, operation, and maintenance of 
recreation facilities. 
For 13-foot depth from sea to a point 1 mile above Coquille 
River Lighthouse and snagging to State Highway Bridge. 
DEPOE BAY, OR 
Construction of an inner basin 375 feet long, 125 feet wide H. Doc. 202, 75th Cong. 
and 5 feet deep, with entrance channel of same depth and 1st Sess. 
50 feet wide. 
Construction of inner basin 750 feet long, 390 feet wide and H. Doc. 350, 77th Cong. 
8 feet deep, with entrance channel at same depth and 30 feet 1st Sess. 
wide. 
ELOCHOMAN SLOUGH, WA 
A channel 10 feet deep and 100 feet wide extending from that H. Doc. 510, 74th Cong. 
depth in Columbia River near easterly end of slough to 2nd Sess. 
existing terminals near mouth of Elochoman River, a distance 
of about 1.5 miles, with suitable turning basin of same depth at 
inner end. 
PORT ORFORD, OR 
Extension of existing breakwater by 550 feet. 
Dredging of turning basin 340 feet long, 100 feet wide, 
16 feet deep. 
ROGUE RIVER HARBOR AT GOLD BEACH, OR 
Two jetties at entrance and improvement of channel. 
SIUSLAW RIVER, OR 
Build two high-tide stone jetties. 
Extends North Jetty 3,700 feet from old work constructed 
under previous project and provides for 4,200 foot south jetty. 
12-foot deep channel. 
S. Doc. 62, 88th Cong., 2d Sess 
H. Doc 151, 91st Cong., 2d Sess. 
S. Doe. 83, 83d Cong. 2d Sess. 
H. Doe. 71, 51st Cong., 1st Sess. 
H. Doe. 648, 61st Cong., 2d Sess. 
S. Committee Print, 
Serial, 68th Cong., 1st Sess. 
37-32 
S. Committee Print, 
73d Cong., 2d Sess.1 
S. Doc. 253, 79th Cong., 2d Sess. 
H. Doc 646, 80th Cong., 2nd Sess. 
H. Doe. 151, 91st Cong., 2d Sess. 
H. Doc. 237, 53d Cong., 3d Sess. 
S. Doc. 124, 80th Cong., 2d Sess. 
H. Doc. 673, 61st Cong., 2d Sess. 
H. doc. 207, 65th Cong., 1st Sess. ' 
H. Doc. 186, 70th Cong., 1st Sess. 
S. Committee Print, 
74th Cong., 1st Sess. 
Sec. 4, Food Control 
Act of 1944 as amended 
H. Doc. 672, 76th Cong., 2d Sess.1 
Jun 03, 1896 
Jun 30, 1948 
10. 
Jun 25, 1910 
Mar 02, 1919 
Jul 03, 1930 
Aug 30, 1935 
Dec 22, 1944 
Mar 02, 1945 
Aug. 26, 1937 
Mar. 2, 1945 
Aug. 26 1937 
11. 
12. 
14. 
16. 
17. 
Oct 27, 1965 
Dec 31, 1970 
Sep 03, 1954 
Sep 19, 1890 
Jun 25, 1910 
Mar 03, 1925

TABLE 37-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
18-foot bar channel and 16-foot river channel and a 600-foot 
extension of north Jetty. (600-foot extension classified 
deferred.) 
Phase I advance engineering and design for north 
and south jetty extensions. 
Extending north and south jetties about 2,000 and 
2,500 feet, respectively. 
SKAMOKAWA CREEK, WA 
Channel 6.5 feet deep and 75 feet wide, at low water 
between Steamboat and Brooks Slough. 
SKIPANON CHANNEL, OR 
Channel from deep water in Columbia River to railroad 
bridge, 30 feet deep. 
Channel extending upstream from railroad bridge a 
distance of 4,500 feet. 
Mooring basin 12 feet deep at Warrenton. 
H. Doc. 204, 85th Cong.,lst Sess.1 
Final Report of Chief 
of Engineers 
P.L 96-367 
H. Doe. 3, 63rd Cong.,lst Sess. 
H. Doc. 278, 70th Cong., 1st Sess.' 
H. Doc. 201, 75th Cong., 1st Sess. 
S. Doec. 93, 80th Cong., 1st Sess. ' 
18. 
19. 
37-33 
Documents 
Jul 03, 1958 
Oct 22, 1976 
Oct 01, 1980 
Mar 02, 1919 
Jul 03, 1930 
Aug 26, 1937 
Jun 30, 1948 
Jul 26, 1912 
Mar 04, 1913 
Mar 02, 1919 
Mar 03, 1925 
Mar 02, 1945 
Jun 30, 1948 
Sep 03, 1954 
Oct 27, 1965 
Jul. 18, 1989 
Sep 22, 1922 
Jan 21, 1927 
Jul 03, 1930 
Aug 30, 1935 
Jun 20, 1938 
Mar 02, 1945 
Mar 02, 1945 
Jun 30, 1948 
Sep 03, 1954 
20. TILLAMOOK BAY AND BAR, OR 
Construct North Jetty 5,700 feet long and dredging H. Doc. 349, 62d Cong., 2d Sess. 
channel 16 feet deep, 200 feet wide, to Bay City. 
Abandon that portion of project above Bay city. H. Doc. 760, 65th Cong., 2d Sess 
Abandon Bay City Channel and present project dimension H. Doc. 562, 68th Cong., 2d Sess. 
of channels and turning basins with regulating works as needed. 
Repair damage and check erosion on Bayocean Peninsula S. Doec. 35, 79th Cong., 1st Sess.4 
caused by storm Jan. 1939. 
Dredging small-boat basin and approach at Garibaldi, OR, H. Doc. 650, 80th Cong., 1st Sess. 
to depth of 12 feet. 
Closure of breach in Bayocean Peninsula S. Doc. 128, 83d Cong., 2d Sess.1 
Construct South Jetty, 80,000 feet long. S. Doc. 43, 89th Cong., 1st Sess. 1 
TONGUE POINT, OR 
Channel 34 feet deep and 350 feet wide from Columbia Section 107 of the 1960 River and 
River channel to Tongue Point docks, and a turning basin Harbor Act, as amended. 
located near the piers. 
UMPQUA RIVER, OR 
North Jetty, 7,500 feet long H. Doc. 913, 65th Cong., 2d Sess. 
Present project dimensions of North Jetty and dredging H. Doc. 320, 69th Cong., 1st Sess. 
ocean bar. 
A short south jetty H. Doc. 317, 70th Cong., 1st Sess.1 
A full length south jetty and maintenance dredging Rivers and Harbors Committee 
to a 26-foot depth. Doc. 9, 72d Cong., 1st Sess. 
Channel 22 feet deep and 200 feet wide from mouth S. Doc. 158, 75th Cong., 3d Sess. ' 
to Reedsport. 
Channel 22 feet deep and 200 feet wide from river channel S. Doc. 86, 76th Cong., 1st Sess.1 
to Gardiner, and turning basin 22 feet deep, 500 feet wide and 
800 feet long. 
Channel 10 feet deep and 100 feet wide from river channel to S. Doc. 191, 77th Cong., 2d Sess.' 
dock in Winchester Bay with mooring and turning basin 10 feet 
deep, 175 feet wide, and 300 feet long at inner end. 
Channel 12 feet deep and 100 feet wide from river channel to S. Doec. 154, 80th Cong., 2d Sess.1 
dock in Winchester Bay with mooring and turning basin 
12 feet deep, 175 feet wide, and 300 feet long at inner end. 
Channel 12 feet deep, Scholfield River. s S. Doc. 133, 81st Cong., 2d Sess.1 
21. 
22. 
1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
23. 
Jun 25, 1910 
Aug 08, 1917 
Jun 26, 19346 
Mar 02, 1945 
Mar 02, 1919 
Aug 26, 1937 
Mar 02, 1945 
Jul 24, 1946 
Jul 03, 1958 
Jul 14, 1960 
Oct 23, 1962 
Mar 07, 1974 
May 17, 1950 
Nov 17, 1986 
Jun 28, 1938 
Dec 22, 1944 
Jun 28, 1938 
Dec 22, 1944 
Oct 23, 1962 
Oct 07, 1970 
May 17, 1950 
Dec 22, 1944 
Jun 28, 1938 
Dec 22, 1944 
Oct 23, 1962 
WILLAMETTE RIVER AT WILIAMETTE FALLS, OR 
For purchase and rehabilitation of system and 
construction of concrete division wall. 
Deepening of locks. 
Operation and care of canal and locks provided for with funds 
from War Department appropriations for Rivers and Harbors. 
Construction of New Willamette Falls Locks. * 
YAQUINA BAY AND HARBOR, OR 
Restoration and extension of jetties constructed under 
previous projects, rock removal at entrance, and 
dredging in bay up to railroad terminus at Yaquina. 
Extension of north jetty seaward 1,000 feet. 
26-foot channel of suitable width across entrance bar, 
as far as rock bottom will allow, a 20-foot channel 300 feet 
wide along south side of bay to and including a turning basin 
22 feet deep, 1,000 feet wide and 1,200 feet long. 
Construct a small-boat mooring basin at Newport, OR. 
40-foot bar channel and 30-foot river channel 
extension of jetties at entrance. 
A small boat basin, south shore. 
APPLEGATE LAKE, ROGUE RIVER BASIN, OR 
Authorizes a rockfill embankment dam. 
Authorizes construction of project but no operation for 
irrigation until local interests agree to repay cost allocated. 
BLUE RIVER LAKE, OR 
Authorizes gravel-filled embankment dam. 
Authorizes Construction of hydroelectric power facilities 
COTTAGE GROVE LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
DORENA LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
ELK CREEK LAKE, ROGUE RIVER BASIN, OR 
Roller compacted concrete dam. 
Authorized construction but not operation for irrigation 
until local interests agree to repay cost allocated. 
FALL CREEK LAKE, OR 
Earth and gravel fill embankment dam. 
Construction, operation, and maintenance of recreation 
facilities. 
FERN RIDGE LAKE, OR 
Earthfill embankment dam 
Construction, operation, and maintenance of recreation 
facilities. 
Raise height of dam to obtain additional storage. 
24. 
37-34 
TABLE 37-B 
(Continued) 
H. Doc. 202, 56th Cong., 1st Sess. 
and Annual Report, 1900, P. 4374 
H. Doc. 1060, 62d Cong., 3d Sess. 1 
H. Doc. 544, 75th Cong., 3d Sess. 
H. Doc. 109, 65th Cong., 
1st Sess. 
S. Committee Print, 75th Cong., 
1st Sess. 
S. Doc. 119, 77th Cong., 1st Sess. 1 
S. Doc. 246, 79th Cong., 2d Sess. 
S. Doc. 8, 85th Cong., 1st Sess. 1 
Section 107, P.L 86-645 
Authorized by Chief of Engineers, 
Mar. 4, 1977 
H. Doc. 566, 87th Cong., 2d Sess. 
P.L 93-251 
H. Doc. 531, 81st Cong., 2d Sess. 
P.L 99-662 
H. Doc. 544, 75th Cong., 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc. 544, 75th Cong., 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc. 566, 87th Cong., 2d Sess. 
P.L 91-439 
H. Doc. 531, 81st Cong., 2d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doe. 544, 75th Cong. 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc 403, 87th Cong. 2d Sess. 
25. 
26. 
27. 
28. 
29. 
30. 
31.

TABLE 37-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
LOWER COLUMBIA RIVER BASIN, OR AND WA 
Bank protection work, improvements to existing 
projects, and construction of flood control works 
in Lower Columbia River Basin. 
H. Doc. 531, 81st Cong., 2d Sess. 
LOWER COLUMBIA RIVER BASIN BANK PROTECTION, OR AND WA 
Provides bank protection on Columbia River below H. Doc. 531, 81st Cong., 2d Sess. 
river mile 125 and along principal tributaries. 
MT. ST. HELENS & VICINITY, WA 
Implement and maintain flood control measures on Cowlitz P.L. 98-63 
and Toutle Rivers to assure flood protection for developed 
areas in the vicinity of such rivers against a one-hundred-year 
flood and to reduce sedimentation flow and the chance of 
blockage on the Columbia River. 
MT. ST. HELENS SEDIMENT CONTROL, CASTLE ROCK, WA 
Authorized construction of sediment and retention structures. P.L 99-88 
May 17, 1950 
May 17, 1950 
Jul 30, 1983 
Aug 15, 1985 
Jun 28, 1938 
May 17, 1950 
Jun 22, 1936 
Jun 28, 1938 
May 17, 1950 
Oct 27, 1965 
Completion, maintenance, and operation of Bonneville project 
under direction of Secretary of War and supervision of 
Chief of Engineers, subject to certain provisions herein relating 
to powers and duties of Bonneville Power Administrator. 
Construction, operation, and maintenance of recreation 
facilities 
Authorizes relocation of town of North Bonneville 
to new town site. 
Acquisition of Steigerwald Lake wetland area 
COUGAR LAKE, OR 
Rockfill dam. 
Addition of power 
Strube Lake reregulating dam. 
DETROIT LAKE, OR 
Authorizes concrete gravity structure. 
Addition of power and regulating Big Cliff Dam with power. 
GREEN PETER-FOSTER LAKES, OR 
Authorized Green Peter Dam in lieu of originally 
authorized Sweet Home Lake (1938) 
Addition of power at Green Peter and White Bridge 
Reregulating Dam. 
H. Doc. 544, 75th Cong., 3d Sess. 
H. Doc. 531, 81st Cong., 2d Sess. 
F.C. Act 1936 
H. Doc. 544, 75th Cong., 3d Sess. 
H. Doc. 531, 81st Cong., 2d Sess. 
H. Doc. 233, 89th Cong., 1st Sess. 
)R AND WA 
S. Committee Print, 73d Cong., 
2d Sess., (Report of Chief of 
Engineers dated Aug 21, 1933) 
Sec 4, Flood Control Act of 1944, 
as amended 
P.L 93-251 
P.L 98-396 
H. Doc. 531, 81st Cong., 2d Sess. 
P.L 83-780 
P.L 87-874 
H. Doc. 544, 75th Cong.,3d Sess. 
P.L 858, 80th Cong. 2d Sess. 
H. Doc. 531, 81st Cong., 2d Sess. 
P.L 83-780 F. C. Act 1954 
37-35 
35. 
36. 
37. 
Documents 
38. 
40. WILLAMETTE RIVER BASIN, OR 
Comprehensive plan for flood control, navigation and other 
purposes in Willamette River basin. 
General improvements 
WILLAMETTE RIVER BASIN BANK PROTECTION, OR 
Bank protection works, with channel clearing. 
Provide additional protection against flooding. 
Addition of 77 locations to scope of projects. 
WILLOW CREEK LAKE, HEPPNER, OR 
Storage project for flood control, recreation, and fish 
and wildlife. 
BONNEVILLE LOCK AND DAM - LAKE BONNEVILLE, C 
Existing project was originally authorized Sep. 30, 1933, by 
Federal Emergengy Administration of Public Works. 
Existing project authorized by congress 
41. 
42. 
43. 
44. 
Aug 30, 1935 
Aug 20, 1937 
Dec 22, 1944 
Mar 07, 1974 
Aug 22, 1984 
May 17, 1950 
Sep 03, 1954 
Oct 23, 1962 
June 28, 1938 
Jun 30, 1948 
May 17, 1950 
Sep 03, 1954 
45. 
46.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul 14, 1960 Changes location of reregulating dam from White S. Doc. 104, 86th Cong., 2d Sess. 
Bridge location to Foster. 
47. HILLS CREEK LAKE, OR 
May 17, 1950 Earth and gravel fill dam. H. Doc. 531, 81st Cong., 2d Sess. 
48. JOHN DAY LOCK AND DAM - LAKE UMATILLA, OR AND WA 
May 17, 1950 Multiple-purpose dam, flood control, navigation and power. H. Doc. 531, 81st Cong., 2d Sess. 
Dec 22, 1944 Construction, operation, and maintenance of recreation Sec 4, Flood Control Act of 1944, 
facilities, as amended 
Mar 24, 1965 John Day waterfowl management area. S. Doc. 28, 89th Cong., 1st Sess. 
49. LOOKOUT POINT LAKE, OR 
Jun 28, 1938 Earth-and-gravel filled dam. H. Doc. 544, 75th Cong., 3d Sess. 
Dec 22, 1944 Construction, operation, and maintenance of recreation Sec 4, Flood Control Act of 1944, 
facilities, as amended 
May 17, 1950 Addition of power and authorization of Dexter Lake H. Doc. 531, 81st Cong., 2d Sess. 
as reregulating dam, 
50. LOST CREEK LAKE, ROGUE RIVER BASIN, OR 
Sep 21, 1962 Rock and gravel fill embankment dam, including power. H. Doc. 566, 87th Cong., 2d Sess. 
Oct 15, 1966 Authorizes construction of project but not operation for P.L 89-689, Public Works 
irrigation until local interests agree to repay cost allocated. Approp. Act, 1967 
51. THE DALLES LOCK AND DAM - LAKE CELILO, WA AND OR 
May 17, 1950 Multiple-purpose dam, flood control, navigation and power. H. Doc. 531, 81st Cong., 2d Sess. 
Dec 22, 1944 Construction, operation, and maintenance of recreation Sec 4, Flood Control Act of 1944, 
facilities, as amended 
1. Contains latest published maps. 
2. Public Resolution 105, 67th Cong. 
3. Public Works Administration 
4. Includes following work, classified inactive. A channel to 
Hobsonville 200 feet wide and 16 feet deep, with a turning basin 
500 feet wide at Hobsonville, and regulating works as needed. 
5. Inactive. 
6. Permanent appropriations Repeal Act. 
7. Flood Control Act 
8. Classified Deferred 
9. Spur Jetty "B" classified inactive. 
37-36

PORTLAND, OREGON DISTRICT 
TABLE 37-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30. 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Alsea River, OR 
AstoriaTurning Basin, OR 1 
Bandon Small Boat Basin, Coquille, OR 1 
Bridges, Columbia River, Cascade Locks 
and Hood River, OR (Alteration) 
Cathlamet, WA 1 
Charleston Channel, Coos Bay, OR 1 
Clatskanie River, OR 2 
Columbia River, Illwaco, WA 1 
Cowlitz River, WA 
Cushman-Mapleton Channels 
(Siuslaw River), OR 1 
Deep River, WA 2 
Depoe Bay, OR 1 
Grays River, WA 2 
Hammonds Small Boat Basin, OR 1 
Interstate Bridge, Columbia River, 
Portland, OR to Vancouver WA (Alteration) 
Interstate Highway Bridge(Barge Channel), OR 1 
Kalama Turning Basin, Kalama, WA 1 
Lake River, WA 
Lewis River, WA 
Long Tom River, OR 
Mooring for Battleship Oregon, OR 
Multnomah Channel, OR 2 
Nehalem Bay, OR 
Nestucca River, OR 
Oregon Slough, (North Portland Harbor), OR 2 
Salmon River, OR 2 
Smith River, OR 2 
South Channel, Government Island, OR 1 
South Slough (Charleston), OR 1 
The Cascades Canal, Columbia River, Or 12 
The Dalles-Celilo Canal, Or and WA13 
Umatilla Harbor, OR14 
Westport Slough, OR 2 
Willamette River above Portland and 
Yamhill River, OR 
Winchester Bay, Umpqua River, OR 1 
Yaquina Bay and Harbor Small Boat Basin, Or 1 
Yaquina River, OR 1 
Yaquina River, OR 
Youngs and Claskanie River, Or 
Youngs Bay and Youngs River, OR 2 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completedm 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Abandoned 
Abandoned 
Abandoned 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1977 
1985 
1944 
1971 
1985 
1969 
1986 
1985 
1975 
1963 
1971 
1941 
1977 
1961 
1963 
1986 
1983 
1985 
1982 
1987 
1963 
1949 
1974 
1985 
1970 
1939 
1957 
1952 
1966 
1985 
1985 
1979 
1971 
1984 
1979 
2,000 
870,139 
1,173,524 
1,081,806 
171,467 
1,197,300 
19,2403 
1,589,231 
277,4368 
329,423 
15,384 
145,5885 
2,500 
519,0907 
1,154,1628 
15,281 
302,000 
2,700 
58,132 
437,669 9 
302,00610 
16,881 
2,145 
143,120 
119,80011 
26,821 
3,903,780 
4,716,205 
16,276 
862,918 
1,616,369 
891,69515 
195,31318 
28,800 
2,000 
9,348 
26,237 
16,648 
194,8964 
1,474,036 
32,768 
35,670 
58,127 
685,677 
4,000 
25,000 
55,195 
6,000 
90,514 
205,130 
559,858 
2,833,888 
171,909 
17,900,293 
749,69417 
34,449 
1. Authorized by Chief of Engineers (sec. 107). 
2. Channel adequate for present commerce. 
3. Includes $15,537 for previous project 
4. Includes $23,489 for previous project. 
5. Excludes $42,000 contributed funds. 
6. Includes $239,529 for Sec. 107 project. 
7. Excludes $75,000 contributed funds. 
8. Non-Federal funds, $1,204,100. 
9. Includes $419,557 for Sec. 107 project. 
10. Excludes $304,826 contributed funds. 
11. Excludes $102,000 contributed funds. 
12. Project abondoned due to flooding by Bonneville Dam pool. 
13. Project abandoned due to flooding by The Dalles Dam pool 
14. Project transferred to Portland Distnct from Walla Walla 
District FY 1974 and abandoned due to flooding by the John Day 
Dam pool. 
15. Excludes $969,342 contributed funds. 
16. Excludes $50,565 contributed funds 
17. Excludes $3,000 contributed funds. 
37-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
TABLE 37-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Se. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
COLUMBIA RIVER BASIN 
Blind Slough Diking District, Clatsop County, OR Completed 1939 163,397 
Consolidated Diking and Improvement District 1, 
Cowlitz County, WA Completed 1941 163,291 
Deep River Area, Wahkiakum County, WA Completed 1942 69,724 
Deer Island Area, Columbia County, OR Completed 1943 574,123 
Diking District 2, Clatsop County, OR Completed 1940 25,609 
Diking District 5, Clatsop County, OR Completed 1940 25,609 
Diking and Improvement District 5, 
Cowlitz County, WA Completed 1940 161,381 
Diking District 1 and 3 (Puget Island) and 
Little Island, Wahkiakum County, WA Completed 1941 258,795 
Diking Improvement District 1, Pacific County WA Completed 1941 26,810 
Diking and Improvement District 4, 
Wahkiakum County, OR Completed 1951 169,542 
Drainage District 1, Clatsop County, OR Completed 1939 240,939 
John Day River Area, Clatsop County, OR Completed 1942 33,080 
Karlson Island, Clatsop County, OR Completed 1941 25,773 
Knappa Area, Clatsop County, OR Completed 1942 18,789 
Lewis and Clark River Area, Clatsop County, OR Completed 1942 158,419 
Lower Cowlitz River Area, Clatsop County, OR Completed 1961 91,652 
Magruder Drainage District, Columbia County, OR Completed 1940 61,186 
Marshland Drainage District, 
Columbia County, OR Completed 1940 39,475 
Midland Drainage District Columbia County, OR Completed 1939 77,7743 
Multnomah Drainage District 1, OR Completed 1951 593,0344 
Peninsula Drainage District 1, Multnomah County, OR Completed 1942 241,148 
Port of Kalama, WA 1 Completed 99,844 
Rainier Drainage District, Columbia county, OR Completed 1942 47,662 
Sauvie Island Areas A and B, Multnomah County, OR Completed 1951 1,623,505 
Scappoose Drainage District, OR Completed 1984 3,991,558 
Skamokawa Creek Area, Wahkiakum County, WA Completed 1946 178,885 
Wahkiakum County Consolidated 
Diking District No. 1, WA Completed 1985 5,289,833 
Tenasillahe Island, Clatsop County, OR Completed 1939 133,778 
Upper Grays River Area, WA Completed 1947 61,263 
State Hwy 101 & 401, Columbia River, WA1 Completed 1985 504,64213 
Walluski River, Clatsop County, OR Completed 1942 66,932 
Warrenton Diking District, 1, Clatsop County, OR Completed 1940 69,503 
Warrenton Diking District 2, Clatsop County, OR Completed 1940 74,596 
Webb District Improvement Co.,Columbia County, OR Completed 1940 84,592 
Westland District Improvement Co., 
Columbia County, OR Completed 1940 205,531 
Westport Distric, Columbia and Clatsop Counties, OR Completed 1943 40,658 
Woodson Drainage District, Columbia County, OR Completed 1940 22,797 
Youngs River Dikes, Clatsop County, OR Completed 1942 248,802 
Total Columbia River Basin 16,399,775 
LEWIS RIVER BASIN 
Diking and Improvement District 11, 
Cowlitz County, WA Completed 1943 172,521 
COWLITZ RIVER BASIN 
Cowlitz County Drainage Improvement District 1, WA Completed 1939 42,978 
Diking Improvement District 13, Cowlitz County, WA Completed 1939 28,592 
Huntington Avenue, Castle Rock, Wa1 Completed 1985 250,000 
Total Cowlitz River Basin 442,735 
37-38

PORTLAND, OREGON DISTRICT 
TABLE 37-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
LOWER COLUMBIA RIVER BASIN 
Beaver Drainage District, OR Completed 1984 3,131,944 
Cowlitz County Consolidated Diking Improvement 
District No. 2, WA Completed 1977 1,661,367 
Cowlitz County Diking Improvement District 2, WA Completed 1967 363,000 
Cowlitz County Diking Improvement District 13, WA Completed 1967 65,345 
Cowlitz County Diking Improvement District 15, WA Completed 1967 304,794 
Cowlitz River, Hopkins Creek, WA1 Completed 236,860 
Hayden Island, OR Inactive 
Midland Drainage District, OR Completed 1971 304,511 
Multnomah County Drainage District 1, OR Completed 1964 1,499,186 
Peninsula Drainage District 2, OR Active 1961 35,265 
Rainier Drainage District, OR Completed 1967 593,945 
Sandy Drainage District, OR Completed 1954 154,0126 
Sauvie Island Drainage District, OR Completed 1966 674,137 
Vancouver Lake Area, WA Deferred 1981 889,391 
Wahkiakum Co. Diking District 4, WA Inactive 1971 48,619 
Washougal Area Levees, Clark County, OR Completed 1973 1,803,488 
Woodson Drainage District, OR Completed 1964 162,500 
Total Lower Columbia River Basin 11,928,364 
WILLAMETTE RIVER BASIN 
Amazon Creek, OR Completed 1960 1,214,3006 
Cascadia Lake, OR Deferred 1976 1,066,1147 
Gate Creek Lake, OR Deferred 1972 840,0008 
Holley Lake, OR Deferred 1963 241,992 
Sandy River and Sleepy Hollow, OR1 Completed 276,700 
Whelton Ditch, OR Inactive 1967 39,624 
Willamette River Basin Channel Clearing 
and Snagging Inactive 
Total Willamette River Basin 3,678,731 
ALL OTHER FLOOD CONTROL 
Arlington, Alkali Canyon, OR9 Abandoned 1950 23,439 
Bear Creek, Medford, OR 1 Completed 23,050 
Beaver Creek Near Tillamook, OR2 Completed 1967 106,198 
Castle Rock, Cowlitz River, WA Completed 1957 104,921 
Catching Inlet Drainage District Coos River, OR2 Completed 1959 182,655 
Chewaucan River, Paisley, OR1 Completed 42,761 
Clackamas River at Dixon Farm Location, OR Completed 1952 70,84510 
Days Creek Lake, OR (Phase I) Deferred 1982 1,307,216 
Depoe Bay, Lincoln County, OR1 Completed 22,963 
Deschutes River, Bend, OR 2 Completed 1988 106,25016 
John Day River (West), OR 1 Completed 1986 127,800 
Johnson Creek, OR Active 1981 170,245 
McDonald Dike Road, Nehalem River, OR1 Completed 1985 29,500 
McKenzie River Near Walterville, OR2 Completed 1966 148,358 
Miami River, OR' Completed 15,321 
Mill Four Drainage District, Yaquina River, OR Completed 1948 118,433 
Molalla River at Milk Creek Location, OR2 Completed 1955 55,007 
Molalla River at Ressel Location, OR2 Completed 1952 55,189 
Nestucca River, Condor Road, OR1 Completed 11,690 
Nestucca River, Vicinity Pacific City, OR1 Completed 16,000 
Pendleton Levees, Umatilla River, OR 11 
(a) Riverside Area Units Deferred 1960 9,100 
37-39

TABLE 37-E 
(Continued) 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep, 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
(b) State Hospital and City Areas (Zone 1) Completed 1959 267,748 
(c) State Hospital and City Areas (Zone 2)2 Completed 1960 161,540 
Pendleton, Umatilla River, OR10 Completed 1939 143,263 
Reedsport Levees, Umpqua River, OR2 Completed 1971 968,71612 
Rogue River, OR1 Completed 86,230 
Salmon Creek at Oakridge, OR2 Completed 1960 288,447 
Salmon Creek Near Vancouver, WA 1 Completed 1985 435,00014 
Siuslaw River, Lane County, OR 1 Completed 215,939 
Stillwell Drainage District, Tillamook Bay, OR2 Completed 1961 176,351 
Sumner Parker Airport, OR1 Completed 92,500 
Trask River, Tillamook County, OR 1 Completed 1984 121,273 
Tualatin, OR Completed 1985 1,803,094 
Umatilla River, Stanfield, OR Completed 33,835 
Umatilla River, Thorn Hollow, OR1 Completed 1985 154,600 
Umpqua River and Tributaries, OR1 Completed 1952 428,881 
Vicinity of Nehalem, Nehalem River, OR Completed 1952 45,677 
West Makinster Rd., Wilson River, OR 1 Completed 1986 176,000 
Wilson River, Vicinity Highway 101, OR1 Completed 30,000 
Total All Other Flood Control 7,965,985 
1. Authorized by Chief of Engineers (Sec. 14). 9. Project transferred from Walla Walla District FY 1974 and 
2. Authorized by Chief of Engineers (Sec. 205). abandoned due to flooding by the John Day Dam pool. Includes 
3. Includes $26,241, Emergency Relief Act Funds $3,328 FY 1960 preauthorization costs, Sec. 205, P.L 80-85. See 
4. Excludes $25,000 contributed funds FY 1960 Annual Report, page 1887 
5. Previous completed project, $138,956; $15,056 engineering costs 10. Excludes $2,520 contributed funds 
project coistructed by local interests. 11. Reported by Walla Walla District prior to 1974 
6. Excludes $154,751 contributed funds. 12. Excludes $230,070 contributed funds for new work and $31,284 
7. Includes $112,000 pro rata share of site selection in lieu of Government furnished sheet steel pile. 
Sweet Home. 13. Includes $254,642 contributed funds. 
8. Includes $95,000 pro rata share of site selection in lieu of 14. Includes $185,000 contributed funds. 
Quartz Creek Lake. 15. Excludes $5,822 contributed funds. 
TABLE 37-F OTHER AUTHORIZED MULTIPLE PURPOSE PROJECTS, 
INCLUDING POWER
For Last Cost to Sep., 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Restoration of Indian Fishing Grounds, Bonneville, OR Completed 1969 185,000 
37-40

PORTLAND, OREGON DISTRICT 
TABLE 37-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Area East of Albany, OR 1977 
Bachelor Island, WA 1977 
Bear Creek, Long Tom River, OR 1966 1971 4,559 
Calapooya River, OR 1959 1965 11,595 
Cascadia Lake, OR 1987 954,114 1 
Clatskanie River Area, Columbia County, OR 1960 1965 268 
Clatskanie Drainage Dist. 1, OR 1964 1978 18,543 
Clatsop County Drainage District 1, OR 1960 1974 4,472 
Clatsop County Diking District 3, OR 1938 1961 258 
Clatsop County Diking District 4, OR 1978 
Clatsop County Diking District 6, OR 1961 1978 8,824 
Columbia Drainage District No. 1, OR 1987 
Columbia Slough, OR 1953 1978 21,352 
Coquille River, OR 1948 1953 908 
Cowlitz County Consolidate Diking Improvement District 1, OR 1977 
Cowlitz River at Randle, WA 1962 1977 11,095 
Coyote and Spencer Creek, Long Tom River, Or 1960 1970 6,819 
Deer Island Drainage District, OR 1987 
East Muddy and Lake Creek, OR 1959 1970 6,465 
Ferguson Creek Long Tom River, Or 1978 
Flat Creek, Long Tom River, OR 1977 
Floodwall and Levees at Portland, OR 1977 
Gate Creek Lake, OR 1987 745,0012 
Holley Lake, OR 1963 1987 241,9923 
John Drainage District, OR 1961 1979 23,754 
John Day river, OR 1974 1974 210,220 
Kalama River (South Area) Levee, Cowlitz County, WA 1969 1978 55,594 
Lake River Delta Area, WA 1977 
Lewis River Area, WA 1978 
Magruder Drainage District, OR 1940 1974 774 
Mud and Basket Slough Rickreall Creek, OR 1977 
Pendleton Levees, Riverside Area, OR 1987 9,000 
Peninsula Drainage District 1, OR 1942 1977 43,292 
Pilot Rock, Birch Creek, OR 1963 1968 4,558 
Prescott Area, Columbia County, OR 1941 1978 125 
Prineville Area, Crooked River and Ochoco Creek, OR 1962 1977 11,318 
Pudding River, OR 1950 1979 5,000 
Shelton Ditch, Marion County, Or 1967 1987 39,624 
Skamokawa (Steamboat Slough), WA 1939 1979 
Soap Creek, WA 1977 
Turner Prairie, Mill Creek, OR 1978 
Umatilla River (Echo), OR 1960 1964 24,145 
Umpqua River-Scholfield River, OR 1987 4,000 
Waldo Lake Tunnel, OR 1958 
West Muddy Creek and Mary's River, OR 1962 1970 4,056 
Westport Slough, OR (Modification for 32-foot chanrnel) 1966 1977 
Wiley Creek Lake, OR 1960 112,000 
Willamette River above Portland and 
Yamhill River, OR (uncompleted portions) 1987 
Willamette Falls Fishladder, OR 1961 
Willamette River at Willamette Falls, OR 1948 1987 142,883 
1. Excludes Pro-rata share of $112,000 for Sweet Home Reservoir. 
2. Excludes Pro-rata share of $95,000 for Quartz Creek Reservoir 
3. Excludes $100,000 preauthorization study costs. 
37-41

TABLE 37-H 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
COLUMBIA AND LOWER WILLAMETTE RIVER 
BELOW VANCOUVER, WA, AND PORTLAND, OR 
TOTAL COST OF EXISTING PROJECT TO SEP. 30, 1989 
(SEE SECTION 3 OF TEXT) 
Funds New Work Maintenance Total 
Regular 28,349,304 272,882,728 301,232,032 
Public Works 446,296 14,414 460,710 
Emergency Relief Administration 138,449 98,668 237,117 
Total U.S. 28,934,049 272,995,810 301,929,859 
Contributed Prior to 1964 223,026 24,320 247,346 
Contributed (1975) 35 to 40-foot Channel 442,928 442,928 
Total Contributed 665,954 24,320 690,274 
Total All Funds 29,600,003 273,020,130 302,620,133 
TABLE 37-I NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1989) 
Charleston Channel, OR 31,792 
Columbia River, Henrici Bar, WA 76 
Columbia River, Kalama, WA 302 
Columbia River, Longview, WA 7,374 
Columbia River, Vancouver, WA 2,356 
Coos Bay, OR 42,531 
Coquille River, Bandon, OR 61,829 
Port of Morrow, Morrow, OR 3,440 
Westport, OR 6,242 
Wind River, WA 9,854 
Yaquina Bay and Bar, OR -85 
TOTAL $ 165,711 
TABLE 37-J PROJECT CONDITION SURVEYS 
Project Date Survey Conducted 
Elochoman Slough, WA December 1989 
Skamokawa Creek, WA November 1989 
Tillamook, OR October 1989 
Youngs Bay, OR January 1989 
37-42

PORTLAND, OREGON DISTRICT 
TABLE 37-K WILLAMETTE RIVER AT WILLAMETTE FALLS, OR 
PRINCIPAL FEATURES OF EXISTING CANAL AND LOCKS 
(See Section 23 of Text) 
Usable Lock Dimensions Series of 4 locks, each 175 feet by 37 feet 1 
Lift of each lock Lock 1 (Lower), 22,5 feet; Lock 2, 8.7 feet; Lock 3, 10.9 feet and 
Lock 4 (Upper), 8.1 feet 2 
Depth of Miter Sills at Lower Water Lower Lock, 8.4 feet; Upper Lock, 6 feet 
Character of foundation Rock 
Kind of Dam Fixed3 
Type of Construction Concrete 
Year of Completion 1873; Purchased by United States Apr. 26, 1915 
Cost Unknown; purchase price $375,000 
1. A guard lock 210 by 40 feet, which is used only at higher states powerplants operated by Crown Zellerbach Corp., and Portland 
of water, is at upper end of canal basin. Ry., Light & Power Co., which is now being operated by Portland 
2. A concrete division wall, 1,227 feet long, extending from Lock 4 General Electric Co. 
to Guard Lock, separates upper basin of canal from head race, 3. The dam is owned by private parties. 
which formerly led directly from basin and supplied water for 
TABLE 37-L FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858 
(PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1989) 
D River, Lincoln City, OR 8,406 
Depoe Bay, OR 6,713 
Libby Dike, Coal Bank Slough, OR 1,324 
Peninsula Drainage District No. 1, OR 25,231 
Rivergate, OR 11,412 
Salmon Creek Levee, Oakridge, OR 2,146 
Schooner Cr., Lincoln City, OR 5,309 
Tutuilla Creek, OR 20 
Waldport, OR 50,293 
Warrenton Diking District No. 1, OR 6,099 
Willamette River, Keizer, OR 2,049 
TOTAL $119,002 
TABLE 37-M FLOOD CONTROL RESERVOIR OPERATIONS 
See Section Date of Peak Inflow Storage Used 
in Text Project Peak Inflow Cu. Ft./Sec. Acre/feet 
25. Applegate Lake, OR March 9, 1989 2,550 12,000 
26. Blue River Lake, OR January 11, 1989 7,250 13,530 
27. Cottage Grove Lake, OR January 10, 1989 1,640 5,260 
44. Cougar Lake, OR January 10, 1989 5,600 15,100 
45. Detroit Lake, OR January 10, 1989 9,000 23,620 
28. Dorena Lake, OR January 10, 1989 10,250 18,910 
30. Fall Creek Lake, OR January 10, 1989 8,500 11,380 
31. Fern Ridge Lake, OR January 11, 1989 4,100 6,830 
46. Foster Lake, OR January 10, 1989 11,200 6,730 
46. Green Peter Lake, OR January 10, 1989 12,300 48,140 
47. Hills Creek Lake, Or January 10, 1989 8,700 18,630 
49. Lookout Point Lake, OR January 10, 1989 16,700 39,240 
50. Lost Creek Lake, Or March 21, 1989 5,500 8,000 
37-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
TABLE 37-N LOWER COLUMBIA RIVER BASIN, OR AND WA 
LEVEES AND IMPROVEMENTS TO EXISTING WORKS 
(See Section 35 of Text) 
Estimated Cost 
of Work 
Location Approved 1989 
Beaver Drainage District, OR $ 2,857,366 
Cowlitz County Diking Improvement District 2, WA 363,000 
Cowlitz County Diking Improvement District 13, WA 65,345 
Cowlitz County Diking Improvement Distict 15, WA 304,794 
Cowlitz County Consolidated Diking Improvement District 2, WA 1,661,367 
Midland Drainage District, OR 304,511 
Multnomah County Drainage District 1, OR 1,499,186 
Peninsula Drainage District No. 2, OR 3,770,000 
Rainier Drainage District, OR 593,945 
Sandy Drainage District, OR 15,0561 
Sauvie Island Drainage District, OR 674,137 
Scappoose Drainage District, OR 3,567,248 
Wahkiakum County Consolidated Diking District 1, WA 5,289,833 
Woodson Drainage District, OR 162,500 
Total Estimated Cost, Federal Funds 21,128,288 
Estimated Non-Federal Cost 3,770,000 
Locations deauthorized or reclassified inactive and excluded from above cost estimate: 
Bachelor Island, WA (Deauthorized - 1977) 
Clatskanie Drainage District, OR (Deauthorized - 1978) 
Clatskanie River Area, OR (Deauthorized - 1965) 
Clatsop County Drainage District 1, OR (Deauthorized - 1974) 
Clatsop County Diking District 4, OR (Deauthorized - 1978) 
Clatsop County Diking District 6, OR (Deauthorized - 1978) 
Columbia Drainage District 1, OR (Deauthorized - 1987) 
Cowlitz County Consolidated Diking Improvement District 1, WA (Deauthorized - 1977) 
Deer Island Drainage District, OR (Deauthorized - 1987) 
Hayden Island, OR (Inactive) 
John Drainage District, OR (Deauthorized - 1979) 
Kalama River Levee, WA (Deauthorized - 1978) 
Lake River Delta Area, WA (Deauthorized - 1977) 
Lewis River Area, WA (Deauthorized - 1977) 
Magruder Drainage District, OR (Deauthorized - 1977) 
Wahkiakum County Diking District 4, WA (Inactive) 
1. Cost is for engineering only. Project was constructed by local interests. 
37-44

PORTLAND, OREGON DISTRICT 
TABLE 37-0 WILLAMETTE RIVER BASIN COMPREHENSIVE PLAN 
(See Section 40 of Text) 
Estimated 
Federal 
Project Authorized Act Cost (1989) 
Blue River Lake, McKenzie Basin I 3 
Cascadia Lake, South Santiam River4 5 11 
Channel Clearing and Snagging on Willamette River and Major Tributaries8 
Channel Improvements for Flood control 
Tributary to Willamette River1 8 
Cottage Grove Lake, Coast Fork1 
Major Drainage on 16 Streams 
Cougar Lake, South Fork McKenzie1 3 
Detroit Lake, Including Big Cliff Lake, 
North Santiam River 1 
Dorena Lake, Row River 1 
Fall Creek Lake, Middle Fork 1 
Fern Ridge Lake, Long Tom River 1 
Gate Creek Lake, McKenzie Basin3 5 11 
Green Peter-Foster Lakes, Middle Santiam1 4 
Hills Creek Lake, Middle Fork1 
Holley Lake, Calapooya Rivers 11 
Lookout Point Lake, Including Dexter Lake, Middle Fork 1 
Strube Lake & Cougar Additional Unit, (South Fork McKenzie) 
(Modification to Cougar Lake) 
Waldo Lake Tunnel and Reregulating Works North Fork, Middle Fork 
Willamette River 
Willamette River Bank Protection 1 
May 17, 1950, H. Doc. 531 
81st Cong., 2d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. Doc. 531 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc 544, 
75th Cong., 3d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. and 
Sep 3, 1954, S. Doc 131, 83d 
Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. and 
June 30, 1948, Public Law 
858, 80th Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 3d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2d Sess. 
May 17, 1950, H. doc., 531 
81st Cong., 2d Sess. and 
Sep. 3, 1954, S. Doc 131, 
83d Cong., 2d Sess. and 
Jul y 14, 1960, S. Doc. 104 
86th Cong., 2d Sess. 
May 17, 1950, H. Doc. 531 
81st Cong., 2d Sess. 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
June 28, 1938, H. Doc. 544, 
75th Cong., 2d Sess. and 
May 17, 1950, H. Doc. 531, 
81st Cong., 2d Sess. 
Oct. 23, 1962, H. Doc. 403, 
87th Cong., 2nd Sess 
May 17, 1950, H. Doc. 5318, 
81st Cong., 2d Sess. 
June 22, 1936, Special Report 
Division Engr., June 28 
1938, H. Doc. 544, 75th Cong. 
3d Sess., and May 17, 1950, 
H. Doc. 531, 81st Cong., 2d Sess. 
$ 32,038,2252 
104,000,000 
(1975) 
3,005,000 
(1960) 
1,214,3003 
4,013,1232 9 
56,750,4052 1 
62,729,6982 
14,568,2622 
22,118,2642 1 
8,526,9352 9 
127,000,000 
(1980) 
84,005,7882 
45,700,6192 
13,300,000 
88,238,3952 9 
106,000,000 
29,200,000 
(1987) 
1. See individual report for details of the project. 
2. Actual cost 
3. For construction in lieu of originally authorized Quartz Creek 
Lake. 
4. For construction in lieu of originally authorized Sweet Home 
Lake. 
5. Project classified deferred. 
6. Project classified inactive. 
7. Does not include Reclassified Locations. 
8. Authorization rescinded August 28, 1958, Public Law 85-820. 
9. Includes cost of Recreation Facilities at Completed Projects, 
(710) 
10. Does not include $96,000 pro rata share of site selection costs 
in lieu of Quartz Creek Lake and Strube Lake and Cougar 
Additional Units. 
11. Authorization rescinded November 17, 1986, Public Law 99- 
662. 
37-45

TABLE 37-P 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
Bonneville Lock and Dam 
OR and WA -- 
Lake Bonneville 
(See Section 43 of Text) 
John Day Lock and Dam, 
OR and WA - 
Lake Umatilla 
(See Section 48 of Text) 
NAVIGATION LOCK 
Dimensions: 
Clear Width of Chamber 
Greatest Length Available for Full Width 
Lift (Vertical): 
At Extreme Low Water and Normal Pool Level 
At Normal River Stage 
At Extreme High Water 
Depth Over Miter Sills at Adopted Low Water 
Character of Foundation 
Open to Navigation 
SPILLWAY DAM 
Type of construction 
Completed 
Capacity 
Elevation of Gate Sills on Crest of Spillway 
Height above Lowest Foundation 
Length of Dam Proper 
Length of Dam Overall 
Width at Base 
Gate Openings 
Crest Overflow (Above Mean Sea Level) 
Elevation(NormalXAbove Mean Sea Level) 
POWERPLANT 
Length (First Powerhouse) 
Length (Second Powerhouse) 
Width (First Powerhouse) 
Width (Second Powerhouse) 
Height (Roof to Bedrock) (First Powerhouse) 
Height (Roof to BedrockXSecond Powerhouse) 
Generator (Station Unit) 
Generators (First Powerhouse) 
Generators (Second Powerhouse) 
Fishwater Supply Units (Second Powerhouse) 
Total Rated Capacity 
Speed 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
76 Feet 
500 Feet 
66 Feet 
59 Feet 
About 30 Feet 
24.2 Feet 
Andesite 
January 1938 
Concrete Gravity 
1938 
1,600,000 CFS 
23.3 Feet 
About 170 Feet 
1,090 Feet 
1,230 Feet 
200 Feet 
18 
24 Feet Pool 
72 Feet 
1,027 Feet 
953 Feet 
190 Feet 
235 Feet 
190 Feet 
200 Feet 
1 @ 5,000 kw 
1@ 48,000 kw 
1@ 59,500 kw 
8 @ 60,000 kw each 
8 @ 66,500 kw each 
2 @ 13,100 kw each 
1,145,700 kw 
75 Revolutions per Minute 
86 Feet 
669 feet 
97 Feet 
105 Feet 
113 Feet 
15 Feet 
April 1968 
Concrete Gravity 
March 1968 
2,250,000 cfs 
210 Feet 
Tainter 
50 ft. by 58.5 Ft. 
20 
37-46

PORTLAND, OREGON DISTRICT 
TABLE 37-P 
(continued) 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
The Dalles Lock and 
Dam, OR and WA -- 
Lake Celilo 
(See Section 51 of Text) 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Installed Capacity 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area At Elevation 268 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Type 
Lift Normal 
Net Clear Length 
Net clear Width 
Normal Depth Over Upper Sill 
Minimum Depth Over Lower Sill 
Opened To Navigation 
SPILLWAY DAM 
Type 
Elevation of Crest 
Top of Crest Gates 
Number of Gates 
Size of Gates 
Height (Foundation to Crest) 
Design Flood 
POWERPLANT 
Powerhouse Dimensions 
Generators Main Units 
Fishwater Supply Units 
Total Rated Capacity 
Station Service Units 
1,975 Feet 
243 Feet 
16 
4
135,000 kw 
2,160,000 kw 
2,700,000 kw 
235 Feet 
July 1968 
268-257 Feet 
276 Feet 
500,000 Ac.-ft. 
76.4 Miles 
55,000 Acres 
15 Ft. by 250 Ft. 
200 miles 
Single Lift 
87.5 Feet 
675 Feet 
86 Feet 
20 Feet 
15 Feet 
March 17, 1957 
Controlled 
121 Ft. msl 
162 Ft. msl 
23 
50 by 43 Feet 
120 Feet 
2,290,000 cfs 
240 by 2,150 feet 
14 @ 78,000 kw each 
8 @ 86,000 kw each 
2 @ 13,500 kw each 
1,807,000 kw 
2 @ 3,000 kw each 
37-47

SEATTILE, WA, DISTRICT 
This District comprises Washington State except southern 
and southeastern portions, northern Idaho, and northwestern 
Montana, embraced in drainage basins tributary to Pacific 
Ocean south of international boundary to Cape Disappointment, 
and to the Columbia River above Yakima River, inclusively. 
IMPROVEMENTS 
Navigation 
1. Anacortes Harbor, WA ................... 38-1 
2. Bellingham Harbor, WA ................... 38-2 
3. Ediz Hook, WA ....................... 38-2 
4. Everett Harbor and Snohomish River, WA .... 38-2 
5. Friday Harbor, WA ..................... 38-3 
6. Grays Harbor and Chehalis River, WA ........ 38-3 
7. Lake Crockett, WA ....................... 38-4 
8. Lake Washington Ship Canal, WA ........... 38-4 
9. Navigation Work under Special Authorization .. 38-4 
10. Olympia Harbor, WA ..................... 38-4 
11. Project Condition Surveys ................. 38-5 
12. Puget Sound and its Tributary Waters, WA .... 38-5 
13. Quillayute River, WA. .................... 38-5 
14. Seattle Harbor, WA ...................... 38-6 
15. Swinomish Channel, WA ................... 38-6 
16. Willapa River and Harbor and Naselle River, WA38-6 
Beach Erosion Control 
17.Beach Erosion Work under 
Special Authorization ................... 38-7 
18. Lincoln Park Beach, Seattle, WA ............ 38-7 
Flood Control 
19. Bitterroot River, Florence, MT ......... ... 38-7 
20. Elwha Klallam Reservation, Elwha, WA ...... 38-7 
21. Flood Control Work under Special Authorization 38-8 
22. Howard A. Hanson Dam, WA ............... 38-8 
23. Inspection of Completed Flood Control Projects 38-8 
24. Inspection of Completed PL-99 Works ....... 38-8 
25. Little Quilcene River, near Quilcene, WA ..... 38-8 
26. Mud Mountain Dam, WA ................. 38-9 
27. Sauk River, Skagit County, WA .............. 38-9 
28. Scheduling Flood Control Reservoir Operations 38-9 
29. Spokane River, Spokane, WA............... 38-9 
30. Stillaguamish River, WA .................. 38-9 
31. Tacoma, Puyallup River, WA ............... 38-10 
32. Wynoochee Lake, WA .................... 38-10 
Multiple-Purpose Projects, Including Power 
33. Albeni Falls Dam, ID ................... 
34. Chief Joseph Dam - Rufus Woods Lake, WA. 
35. Libby Dam - Lake Koocanusa, MT .......... 
General Investigations 
36. Surveys ................................. 
37. Collection and Study of Basic Data .......... 
38. Preconstruction Engineering and Design ..... 
38-10 
38-11 
38-11 
38-12 
38-12 
38-12 
Tables 
Table 38-A Cost & Financial Statement ....... 38-14 
Table 38-B Authorizing Legislation ........... 38-20 
Table 38-C Other Authorized Navigation Projects 38-25 
Table 38-D Not Applicable 
Table 38-E Other Authorized 
Flood Control Projects ........... 38-26 
Table 38-F Other Authorized Multiple Purpose 
Projects, Including Power ......... 38-29 
Table 38-G Deauthorized Projects ............ 38-29 
Table 38-H Lake Washington Ship Canal, WA 
Principle Features of Double Lock 
and Dam ....................... 38-29 
Table 38-I Project Conditions Surveys ........ 38-30 
Table 38-J Flood Control Activities Pursuant to 
Section 205, Public Law 80-858 .... 38-30 
Table 38-K Not Applicable 
Navigation 
1. ANACORTES HARBOR, WA 
Location. On northern point of Fidalgo Island in Puget 
Sound, 17 miles south of Bellingham, WA, and 64 miles north 
of Seattle. The main harbor is on Guemes Channel. (See 
NOAA Survey Chart 18427.) 
Existing project. Channel in Capsante Waterway, 12 feet 
deep and 150 to 250 feet wide, between east side of Q Avenue 
and deep water in Fidalgo Bay, a distance of 2,850 feet; and 
mooring basin 12 feet deep, 570 feet wide, and 960 feet long 
adjacent to north side of Capsante Waterway, protected by 
38-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
two pile breakwaters, each 470 feet long, east and southeast 
of basin. Plane of reference is mean lower low water. Range 
between mean lower low water and mean higher high water is 
8.2 feet. Extreme range is about 15.5 feet. Project was completed 
in July 1957. (For further details, see Annual Report 
for 1958.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 piers and wharves in the 
Port of Anacortes; 15 on Guemes Channel, 3 on Capsante 
Waterway, and 7 on Fidalgo Bay. Three wharves on Guemes 
Channel are open for public use; of these, one is publicly 
owned and operated and used for handling general cargo in 
foreign and domestic trade. In addition, two wharves are used 
for ferries plying to the San Juan Islands and to Vancouver 
Island, British Columbia. Both are publicly owned and operated. 
Two of the wharves on Capsante Waterway and basin 
are publicly owned and operated and used for receiving petroleum 
products, and as a moorage for fishing and pleasure 
craft. All other wharves are used for general industrial purposes. 
In addition, there are two oil-refinery wharves located 
to the south of Capsante Waterway that are privately owned 
and operated and used for handling petroleum products in 
foreign and domestic trade. These facilities are considered 
adequate for existing commerce. (See Port Series No. 37 - 
Ports of Port Angeles, Port Townsend, Everett, Anacortes, 
and Bellingham, WA, revised 1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Conducted channel condition surveys and completed new 
photo base maps for the project features. 
2. BELLINGHAM HARBOR, WA 
Location. Part of Bellingham Bay, an arm of Puget Sound, 
at Bellingham, in northwestern Washington. (See NOAA 
Survey Chart 18424.) 
Existing project. Channel 30 feet deep in Whatcom Creek 
Waterway from deep water to head of harbor, 363.2 feet wide 
to 750 feet from inner end, thence 18 feet deep for inner 750 
feet; Squalicum Creek Waterway, including dredging an entrance 
channel 200 feet wide and 26 feet deep from deep 
water in the bay to main pierhead line, and maintenance of 
southerly half and westerly end of Squalicum Creek basin to 
26 feet deep, provided that no dredging can be done within 75 
feet of wharves, piers, or similar structures; and small-boat 
basin adjacent to Squalicum Creek Waterway by construction 
and maintenance of two sections of rubblemound breakwater 
with combined length of 5,400 feet, including maintenance of 
minimum depths of 12 feet in entrance to basin. Plane of 
reference is mean lower low water. Range between mean 
lower low water and mean higher high water is 8.6 feet. 
Extreme range is about 16 feet. Project was completed in 
February 1961. (For further details see Annual Report for 
1961. For details relating to previous project see page 797 of 
Annual Report for 1907.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-2 of FY 1980 Annual Report. 
Terminal facilities. Of the forty wharves and piers in Bellingham 
Harbor, 9 are on Whatcom Creek Waterway; 3 on 
Squalicum Creek Waterway; 3 on I&J Street Waterway; and 9 
on Bellingham Bay. Two wharves on Whatcom Creek Waterway 
serve general cargo terminals. One is publicly owned and 
operated and is suitable for use by ocean-going vessels; the 
other one is privately owned and operated. There is one 
publicly owned terminal and small-boat harbor with 11 
wharves handling private craft and fishing boats. (See Port 
Series No. 37 - Ports of Port Angeles, Port Townsend, 
Everett, Anacortes, and Bellingham, WA, revised 1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Conducted channel condition surveys and completed new 
photo base maps for the project features. 
3. EDIZ HOOK, WA 
Location. Ediz Hook and the city of Port Angeles are on the 
Strait of Juan de Fuca in Clallam County, WA, about 100 
miles northwest of Seattle. (See NOAA Survey Chart 18468.) 
Existing project. Provides for about 13,300 linear feet of 
rock revetment and 3,100 linear feet of rock blanketing, together 
with initial beach replenishment and annual nourishment. 
Project was completed in October 1978. (For further 
details, see Annual Report for 1979.) 
Local cooperation. Fully complied with. 
Terminal facilities. Of the 27 waterfront facilities at Port 
Angeles Harbor, 3 are located along the inner side of Ediz 
Hook. Functional uses of the piers include placing logs into 
water from trucks for shipment by rafting; mooring harbor 
pilot boats; mooring U. S. Coast Guard vessels, Naval Reserve 
vessels, and occasionally, oceanographic research vessels; 
and fueling government vessels. (See Port Series No. 37 
- Ports of Port Angeles, Port Townsend, Everett, Anacortes, 
and Bellingham, WA, revised 1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Annual inspection and coordination with local sponsor. 
4. EVERETT HARBOR AND SNOHOMISH 
RIVER, WA 
Location. On Port Gardner Bay, at northern end of Possession 
Sound, an arm of Puget Sound at Everett, in northwestern 
Washington; and Snohomish River for 6.3 miles above 
mouth. (See NOAA Survey Chart 18443.) 
Existing project. Training dike extending from a point opposite 
23d Street northward 12,550 feet to outlet of 
Snohomish River, with spur dike extending 400 feet to pierhead 
line from north end of main dike; spur dike extending 
1,410 feet westward from Preston Point; removal of a section 
Sof training dike north of Snohomish River outlet; channel 150 
to 425 feet wide and 15 feet deep from deep water in Port 
Gardner Bay to 14th Street dock; thence a settling basin 700 
feet wide, 1,200 feet long, and 20 feet deep, thence a channel 
150 feet wide and 8 feet deep upriver to head of Steamboat 
Slough, a total distance of about 6.3 miles; settling basin 
within upper channel reach about 1 mile long with a capacity 
of 1 million cubic yards and maintaining East Waterway to 30 
feet deep. The 1968 modification included raising the southerly 
4,100 feet of existing training dike, extending the training 
38-2

SEATTLE, WASHINGTON DISTRICT * 
dike 1,500 feet farther south, and constructing a breakwater 
along the south and west sides of the existing small boat basin. 
Plane of reference is mean lower low water. Range between 
mean lower low water and mean higher high water is 11.1 
feet. Extreme tidal range is about 19 feet. The boat basin 
breakwater has been deleted at the request of the local sponsor, 
and the remainder of the 1968 modification has been 
deferred indefinitely. Project was completed in April 1963, 
excluding the deleted and deferred portions. (For further 
details, see page 1683 of Annual Report for 1963. For details 
relating to previous projects, see page 704 of Annual Report 
for 1905, page 2005 of Annual Report for 1915, and page 
1883 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-3 of FY 1981 Annual Report. 
Terminal facilities. There are 42 piers and wharves in the 
Port of Everett, 17 in Port Gardner and 25 on the Snohomish 
River. These include: 19 publicly owned terminals with four 
berths handling ocean-going vessels and 1 publicly owned 
terminal and small-boat basin handling fishing and pleasure 
craft. (See Port Series No. 37 - Ports of Port Angeles, Port 
Townsend, Everett, Anacortes, and Bellingham, WA, revised 
1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Channel condition surveys were conducted throughout the 
year. Puget Sound Dredged Disposal Analysis study costs 
resulted in an expenditure of $570,746. 
Maintenance, contract: A maintenance dredging contract 
for the Lower Snohomish River channel and downstream 
settling basin was awarded in August 1989, in the amount of 
$632,700. 281,000 cubic yards of material are expected to be 
removed, with completion in December 1989. 
5. FRIDAY HARBOR MARINA, WA 
Location. Friday Harbor is located on the eastern shore of 
San Juan Island on the inland waters of nothwestern Washington, 
about 28 nautical miles east of Victoria, British Columbia, 
and 60 nautical miles north of Seattle, WA. San Juan 
Island is one of over 170 islands in the San Juan Archipelago. 
Friday Harbor is the San Juan Island County seat and a 
United States Customs Port of Entry. (See NOAA Survey 
Chart 18425.) 
Existing project. 1,600-foot concrete breakwater to protect 
the existing port facilities and to allow the Port of Friday 
Harbor to provide 294 additional permanent moorage spaces 
and 44 additional transient spaces. Construction was completed 
in March 1984. 
Local cooperation. Fully compiled with. Requirements are 
described in full on page 38-4 of FY 1981 Annual Report. 
Operations during the fiscal year, Maintenance, hired labor: 
Conducted annual/after storm inspection of the breakwater 
structure. Coordinated the design and installation of 
two Government-furnished signs at the project. 
6. GRAYS HARBOR AND CHEHALIS RIVER, 
WA
Location. Harbor lies at mouth of Chehalis River, in southwestern 
part of Washington, 45 miles north of entrance to 
Columbia River. Inner portion comprises two main channels, 
the south and the north, connecting harbor proper with 
Chehalis River at Aberdeen. Chehalis River rises in southwestern 
part of Washington about 40 miles east of Pacific 
Ocean, flows generally northwesterly and empties into eastern 
part of Grays Harbor. (See NOAA Survey Chart 18502.) 
Existing project. Provides for an entrance channel across 
the bar 600 feet wide and 30 feet deep, to be secured by a 
south jetty 13,734 feet long and a north jetty 17,200 feet long, 
both at an elevation of 16 feet, and by dredging; maintenance 
of channel 30 feet deep and 350 feet wide from deep water in 
Grays Harbor 14 miles to Cow Point; thence 30 feet deep and 
200 feet wide, suitably widened at bends, to a point 13,700 
feet upstream from Union Pacific Railroad bridge at Aberdeen, 
a distance of 4.125 miles; a turning basin 30 feet deep, 
550 feet wide, and 1,000 feet long at upstream end of 30-foot 
channel near Cosmopolis; a channel 14 feet deep and 100 
feet wide in South Bay to Bay City; three breakwaters at, and 
maintenance of entrance channel to Westhaven Cove; and 
protection of Point Chehalis for an exposed length of about 
7,500 feet. Plane of reference is mean lower low water. Tidal 
range between mean lower low water and mean higher high 
water is 8.9 feet at Point Chehalis, 10.1 feet at Aberdeen, and 
8.1 feet at Montesano. Extreme range is 17.5 feet at Point 
Chehalis, 17.8 feet at Aberdeen, and 23.8 feet at Montesano 
(river flood of 1935). Project was completed in March 1965 
excluding deferred and inactive portions. Rehabilitation of 
4,000 feet of the south jetty was completed in October 1966. 
(For further details, see Annual Report for 1967. For details 
relating to previous projects, see pages 2002-03 of Annual 
Report for 1915 and page 1863 of Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 23 waterfront facilities 
(piers, wharves, and docks), exclusive of those available to 
recreational craft, at Grays Harbor, of which five are publicly 
owned. In foreign and domestic trade they serve various purposes 
which include the receipt and/or shipment of: logs and 
lumber, woodchips, conventional and containerized general 
cargo, seafood and fishing supplies, sand and gravel, and 
construction materials. Other uses include: mooring and 
icing fishing boats, mooring small vessels for outfitting and 
repair, and mooring company-owned tugs. Those piers operated 
by the U.S. Coast Guard moor government-owned vessels. 
(See Port Series No. 35, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Channel condition surveys were conducted throughout the 
year. The Corps hopper dredge Yaquina dredged in Crossover 
Reach Channel in October/November 1988, removing 
79,320 cubic yards of material at a cost of $684,527. 
Maintenance, contract: Maintenance dredging of the inner 
and outer harbors was completed in August 1989, at a cost of 
$1,529,300 with 1,126,700 cubic yards of material being removed. 
38-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
7. LAKE CROCKETT, WA 
Location. The harbor is on the west side of Whidbey Island, 
about 35 nautical miles north of Seattle, WA. The lake lies 
parallel to Admiralty Bay and is separated from it by a narrow 
strip of gravel beach. (See NOAA Survey Chart 18441.) 
Existing project. Provides for a basin in Lake Crockett with 
an area of about 6 acres and 18 feet deep at mean lower low 
water, connected with Admiralty Bay by a channel of the 
same depth and 150 feet wide, protected by a breakwater. 
The diurnal tidal range in Admiralty Bay is 8.4 feet and the 
extreme range is about 16.5 feet. Project was completed in 
January 1948. (For further details, see Annual Report for 
1948.) Recreational facilities at project under cost-sharing 
agreement with Washington State Parks and Recreation 
Commission include the following construction and improvements: 
construct a 35-unit camping loop and restroom, new 
boat ramp handling facility, breakwater, a restroom in the 
day-use area and porto-potti dumps for boats; and expand 
day-use facility and add riprap at the construction site. 
Local cooperation. None required. 
Terminal facilities. One publicly owned and privately 
owned passenger and automobile ferry landing within the 
dredged basin is open for public use, and is adequate for 
existing commercial traffic. The basin contains two publicly 
owned boat ramps open for public use. The ramps are adequate 
for recreational craft. 
Operations during fiscal year. Maintenance, hired labor: 
Scheduled work was fiscally completed.. 
8. LAKE WASHINGTON SHIP CANAL, WA 
Location. Entirely within city of Seattle and extends from 
Puget Sound through Shilshole Bay, Salmon Bay, Lake Union, 
Portage Bay, and Union Bay to deep water in Lake 
Washington. (See NOAA Survey Chart 18447.) 
Existing project. Provides for a double lock and fixed dam 
from gated spillway and necessary accessory works, including 
fishladder, at the Narrows at entrance to Salmon Bay, about 
1.25 miles from deep water in Puget Sound; for a channel 34 
feet deep and 300 feet wide from Puget Sound to Burlington 
Northern Railway bridge, about 5,500 feet, with a passing 
basin 34 feet deep and log basin 8 feet deep at turn below 
railway bridge; then 34 feet deep and 150 feet to 200 feet wide 
to locks, about 900 feet; and a guide pier 600 feet long; for 
revetment of canal banks between locks and Lake Union and 
between Lakes Union and Washington; and for a channel 30 
feet deep with a width of 100 feet from locks to Lake Union, 
200 feet thence to Portage Cut, 100 feet through Portage 
Cut, and thence 200 feet wide through Union Bay to Lake 
Washington. Section included in project is about 10 miles 
long. Plane of reference is mean lower low water. Extreme 
tidal range is 19.3 feet. Range between mean lower low water 
and mean higher high water is 11.3 feet, and between mean 
lower low water and extreme low water is 4.6 feet. Ordinary 
fluctuation in upper pool is about 22 inches; extreme fluctuation 
has been 3.6 feet. Principal features of double lock and 
dam (structures are at Seattle, WA) are set forth in Table 
38-H. Project was completed in 1934. (For further details, 
see Annual Report for 1935. For details relating to previous 
projects, see page 2003 of Annual Report for 1915, and page 
1880 of Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. The eight waterfront facilities at Lake 
Washington Ship Canal are used for fuel oil, seafood, marine 
repair, drydocking, outfitting, mooring fishing vessels and 
repairs to the locks' equipment. Project is a part of Seattle 
Harbor's inner harbor. (See Port Series No. 36, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Locks were operated and maintained all year, passing 18.792 
commercial and 61,326 pleasure vessels, and 2,131,600 tons 
of commerce. Fishladder passed more than 500,000 fish and 
there were more than 1,000,000 project visitors. The Washington 
Department of Wildlife, National Marine Fisheries, 
and Army Corps of Engineers cooperatively relocated sea 
lions to the south coast of Washington State. 
9. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public Law 
86-645 (preauthorization). 
Fiscal year costs for preauthorization studies were: 
Coupeville, Whidbey Island, WA, $1,169 (terminated); Fisherman 
Bay, Lopez Island, WA, $1,300 (terminated); Gooseberry 
Point Small Boat Harbor, Hale Passage, WA, $153,682; 
Keystone Harbor, Admiralty Inlet, WA, $7,336; Port 
Townsend, WA, $14,819; and Sandy Point Harbor, Whatcom 
County, WA, $27 (terminated). 
Aquatic plant control (Section 302, Public Law 89-298). 
The program consists of control measures for selected 
water bodies currently infested with Eurasian watermilfoil 
and measures to prevent its spread into uninfested waters. 
Operations under the cost-share program included mechanical 
harvesting of 52 acres, maintaining 6 acres of fiberglass 
bottom screens at Lake Washington, Lake Union and Lake 
Sammamish, WA; rotovating 100 acres at Pend Oreille River, 
WA; and, chemically treating (with the aquatic herbicide 
fluridon) 240 acres at Swofford Pond in Cowlitz River drainage, 
WA. The FY 1989 work also included treatment effectiveness 
and carryover studies, cooperation with the University 
of Washington on a grass carp study, aquatic plant 
surveys, and public information efforts. Total costs for the 
fiscal year were $290,392. 
10. OLYMPIA HARBOR, WA 
Location. Near southern end of Puget Sound at head of 
Budd Inlet, about 45 miles southwest of Tacoma. (See Coast 
and Geodetic Survey Chart 6462.) 
Existing project. Provides for a channel between deep 
water in Budd Inlet and port terminal, 30 feet deep at mean 
lower low water and 500 feet wide, with suitable additional 
width at bend, and a turning basin adjacent to port terminal 
30 feet deep, 3,350 feet long, and 500 to 960 feet wide. 
38-4

SEATTLE, WASHINGTON DISTRICT 
Extreme tidal range is 22.5 feet. Range between mean lower 
low water and mean higher high water is 14.4 feet. Existing 
project was completed in 1939. Entrance channel and turning 
basin authorized by 1945 River and Harbor Act have been 
deferred. (For details relating to previous projects, see page 
1369 of Annual Report for 1934 and page 1873 of Annual 
Report for 1938.) 
Local cooperation. Modification authorized by River and 
Harbor Act of March 2, 1945, requires that local interests 
furnish suitably bulkheaded areas for retention of dredged 
materials, when and as required. The Port of Olympia advised 
on January 25, 1949, that it could not comply with requirements 
at that time, but would do so on earliest possible date. 
Terminal facilities. Five port facilities are located in Olympia 
at Budd Inlet, exclusive of the numerous waterfront facilities 
in the ports used by recreational craft. The industrial 
docks are used for conventional general cargo, logs, timber 
products and miscellaneous mooring. (See Port Series No. 
35, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Maintained project coordination. 
11. PROJECT CONDITION SURVEYS 
Preliminary and detailed surveys to determine navigation 
conditions at boat basins, small navigation projects, channels, 
and tributaries of major rivers not within major project 
boundaries. Soundings and visual inspections in subject areas 
are conducted in order to evaluate shoaling conditions. Channel 
centerline markers are inspected for visibility and proper 
operation in applicable areas frequented by boating traffic 
consisting mostly of recreationalists. In addition, all subject 
areas are inspected to insure that they are clean of snags and 
obstructions. Costs for the fiscal year were $277,646. Total 
costs to date are $2,649,686. (See Table 38-I.) 
12. PUGET SOUND AND ITS TRIBUTARY 
WATERS, WA 
Location. Puget Sound is in the western part of Washington. 
Cities of Seattle, Tacoma, Olympia, Everett, Bellingham, 
and many small towns are on its bays and inlets. (See 
NOAA Survey Charts 18400, 18441, and 18448.) 
Existing project. Maintenance of Puget Sound and its 
tributary waters by snagging and dredging; and removal, in 
cooperation with city of Seattle, of floating debris from the 
Seattle Harbor area. Work consists of collecting large pieces 
of drift, waterlogged pilings, logs and other debris considered 
hazardous to navigation from Puget Sound and Federally 
authorized channels. (For details relating to previous projects, 
see page 2003 of Annual Report for 1915 and page 1869 
of Annual Report for 1938.) 
Local cooperation. None required. City of Seattle is cooperating 
in a program for control of floating debris in Seattle 
Harbor. 
Terminal facilities. Terminal facilities at numerous localities 
on Puget Sound and its tributary waters are, in general, 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired labor: 
The debris vessel Puget operated continuously throughout 
Puget Sound and its tributary waters and removed approximately 
2,500 tons of floating debris and hazards to navigation. 
Debris was disposed of locally or loaded aboard barges and 
disposed of by contract. Snagging operations were accomplished 
at Blaine Harbor, Bellingham Harbor, Swinomish 
Channel, Skagit River, Everett Harbor, Snohomish River 
(upstream to town of Snohomish), Lake Washington Ship 
Canal, Lake Washington, Tacoma Harbor, Olympia Harbor, 
Duwamish River, and Elliott Bay. 
Maintenance, contract: 1,596 tons of harbor debris were 
disposed of at a cost of $67,504. Contractor recycled some of 
the debris and placed the remainder in a demolition landfill. 
13. QUILLAYUTE RIVER, WA 
Location. River is formed by junction of Soleduck and 
Bogachiel Rivers, in northwestern Washington, and flows 
westerly 5 miles to Pacific Ocean at La Push, about 30 miles 
south of Cape Flattery. (See NOAA Survey Chart 18480.) 
Existing project. Provides for: (a) jetty 15 feet high on 
easterly side of river mouth, and a dike on westerly side, with 
a view of stabilizing entrance; (b) channel 10 feet deep and 
100 feet wide extending 2,000 feet upstream from deep 
water; (c) basin 10 feet deep, 300 to 425 feet wide, and 2,400 
feet long upstream of channel; and (d) maintenance of an 
ocean spit. Plane of reference is mean lower low water. 
Range between mean lower low water and mean higher high 
water at La Push is 8.3 feet. Extreme range is about 15 feet. 
The spit was nourished in conjunction with channel dredging 
contracts completed in 1973 and in 1977. The spit was rehabilitated 
with quarry rock in 1974, in 1979-80, and in 1982. In 
addition, a 500-foot breakwater section paralleling the channel 
and extending the spit was constructed. Project was completed 
in February 1960; however, the channel upstream of 
the boat basin has been classified as inactive. (For further 
details, see Annual Report for 1963.) 
Local cooperation. Complied with except that the requirement 
to provide a public landing open to all on equal terms in 
the boat basin was not complied with between May and July 
1981, due to the closure of the Quileute Indian Reservation 
to the landing of salmon by sport and charter fishermen. 
Project sponsorship was transferred from the Port of Port 
Angeles to the Quileute Tribe Port Authority in 1983. 
Terminal facilities. There are 6 privately-owned docks at 
La Push, near the mouth of the Quillayute River. In addition, 
there is a protected boat basin owned by the Quileute Tribe 
Port Authority which is used by fishing boats, pleasure craft, 
and the Coast Guard, which has a separate pier. 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys were made of the river channel during the 
year. Completed plans and specifications for maintenance 
dredging and supervised the dredging and training wall contract. 
Maintenance, contract: Emergency repairs of the timber 
and rock training wall were completed in February after 
being undermined by a change in the thalweg of the adjacent 
river. A 128-foot section of timber wall was replaced and 
38-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
8,400 cubic yards of rock was placed along the toe, all at a cost 
of $402,000. Maintenance dredging of 60,448 cubic yards 
from the entrance channel and boat basin was completed in 
March at a contract cost of $312,079. 
14. SEATTLE HARBOR, WA 
Location. Harbor at Seattle, WA, includes all waterways 
within city limits. Chief anchorage basin is Elliott Bay, an arm 
of Puget Sound. (See NOAA Survey Chart 18450.) 
Existing project. Maintenance of East and West Waterways, 
34 feet deep and 750 feet wide for 6,500 and 5,200 feet, 
respectively, from pierhead line in Elliott Bay; maintenance 
of East Waterway between upper end of 750-foot section and 
Spokane Street, 34 feet deep, 700 feet long, and 400 feet 
wide, and a turning basin, including head of East Waterway at 
junction of waterways south of Chicago, Milwaukee, St. Paul 
& Pacific Railroad bridge, to 30 feet deep, after these sections 
of waterway are dredged by local interests to full project 
dimensions; and dredging Duwamish Waterway 200 feet wide 
and 30 feet deep between West Waterway and First Avenue 
South, 150 by 20 feet between First and Eighth Avenues 
South, thence 150 feet by 15 feet to a point about 1.4 miles 
above 14th Avenue South Bridge, with turning basin 600 by 
350 feet and 20 feet deep just south of First Avenue South 
Bridge, and turning basin 500 by 250 feet and 15 feet deep, 
and settling basin of about 100,000 cubic yards-capacity at 
upper end of waterway, a distance of 5.12 miles. Total length 
of waterways included in project is about 7.5 miles. Plane of 
reference is mean lower low water. Range between mean 
lower low water and mean higher high water is 11.3 feet. 
Extreme tidal range is 19.3 feet. Project was completed in 
1931, excluding the settling basin at upstream end which is 
classified inactive and East Waterway above the 750-foot 
section. (For further details, see Annual Report for 1932.) 
Local cooperation. Fully complied with. Local sponsor has 
no maintenance responsibility. 
Terminal facilities. There are 196 piers, wharves, and docks 
located on the inner and outer harbors at Seattle, WA. 
Salmon Bay, Lake Union, Portage Bay and Lake Washington 
form the inner harbor; Elliott Bay and East, West and 
Duwamish Waterways form the outer harbor. (Lake Washington 
Ship Canal, a part of the inner harbor, is a separate 
project in this report.) These terminals serve a variety of 
purposes which include cargo handling, bunkering vessels, 
ferry service (vehicular, passenger and rail car), marine repair/
outfitting/drydocking/conversion, shipbuilding, handling 
supplies and equipment, and mooring company-owned 
equipment, excursion vessels, fire boats, fishing vessels, government 
equipment, harbor craft/tugs, and oceanographic 
research vessels. The numerous waterfront facilities in the 
port used exclusively by recreational craft are not included. 
(See Port Series No. 36, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys made of channels. Sediment sampling and 
testing was performed to characterize sediments proposed 
for open water disposal. Puget Sound Dredged Disposal 
Analysis study costs resulted in an expenditure of $10,000. 
15. SWINOMISH CHANNEL, WA 
Location. An inland passage, 11 miles long, between 
Saratoga Passage and Padilla Bay, in northwestern part of 
Washington, about 60 miles north of Seattle. (See NOAA 
Survey Charts 18400, 18427 and 18421.) 
Existing project. A channel 100 feet wide and 12 feet deep 
for 11 miles from deep water in Saratoga Passage to deep 
water in Padilla Bay, by dredging and dike construction where 
necessary; and removal of projecting rocky points of McGlinn 
and Fidalgo Islands obstructing navigation at "Hole-in-the- 
Wall". Plane of reference is mean lower low water. Range 
between mean lower low water and mean higher high water is 
11.5 feet at south end of channel, 8.4 feet at north end, and 10 
feet at La Conner. Extreme tidal range is about 19.5 feet at 
south end of channel and about 16 feet at north end. Project 
was completed in March 1965. (For further details, see Annual 
Report for 1965.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 wharves, docks, and piers 
on Swinomish Channel, all but 3 of which are privately 
owned. Of these, 1 is used for handling general cargo, 5 are 
used exclusively for moorage, unloading and servicing of fishing 
vessels; 2 are used for handling petroleum products; 3 
facilities are used for log dumps; and 2 for handling non-metallic 
minerals. Three publicly owned facilities for launching, 
mooring, and servicing small craft are within the city limits of 
La Conner. 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys were made of various reaches of the channel. 
Puget Sound Dredged Disposal Analysis study costs resulted 
in an expenditure of $21,405. 
16. WILLAPA RIVER AND HARBOR AND 
NASELLE RIVER, WA 
Location. Willapa Harbor consists of lower reaches of Willapa 
River and Bay, an inlet of Pacific Ocean about 30 miles 
north of mouth of Columbia River in Washington. Willapa 
River rises about 30 miles east of harbor, flows generally 
westerly, and empties into the bay. Naselle River enters the 
bay near its southerly end. (See NOAA Survey Chart 18504.) 
Existing project. Provides for: (a) channel over bar at 
mouth of Willapa Bay, 26 feet deep and at least 500 feet wide; 
(b) channel 24 feet deep and 200 feet wide from deep water in 
Willapa Bay to foot of Ferry Street at South Bend, thence 300 
feet wide to westerly end of narrows, thence 250 feet wide to 
forks of river at Raymond, including a cutoff channel 3,100 
feet long at narrows and a closing dike at Mailboat Slough; (c) 
channel 24 feet deep and 150 feet wide up south fork to deep 
basin above Cram Lumber Mill, and up north fork to 12th 
Street, with a turning basin 250 feet wide, 350 feet long, and 
24 feet deep at latter point; (d) channel 10 feet deep and 40 
feet wide from deep water in Palix River to Bay Center dock, 
with widening at shoreward end to provide a small mooring 
basin; (e) mooring basin 15 feet deep, 340 feet wide, and 540 
feet long adjacent to port wharf at Tokeland; (f) entrance 
channel at Nahcotta 10 feet deep and 200 feet wide, and 
mooring basin 10 feet deep, 500 feet wide, and 1,150 feet 
38-6

SEATTLE, WASHINGTON DISTRICT 
long, protected by a rubblemound breakwater about 1,500 
feet long; and (g) removal of snags, piles, and other obstructions 
in navigable channel of Naselle River between Naselle 
and mouth. Project includes about 26 miles of channel from 
entrance through Willapa River forks, 2,800 feet of Palix 
River-Bay Center channel, and 9 miles of Naselle River 
upstream of U.S. Highway 101 Bridge. Plane of reference is 
mean lower low water. Tidal range between mean lower low 
water and mean higher high water is 8.9 feet at Toke Point, 
9.9 feet at Raymond, 8.9 feet at Bay Center, and 10.8 feet 
near Naselle. Extreme range is 18 feet at Toke Point, 19.3 
feet at Raymond, 16 feet at Bay Center, and 18 feet near 
Naselle. Project was completed in November 1958. (For further 
details, see Annual Report for 1959. For details relating 
to previous projects, see page 968 of Annual Report for 1910, 
page 2001 of Annual Report for 1915, and page 1861 of 
Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 wharves on Willapa River 
and Harbor, including 5 in Willapa Bay, 4 in Bay Center, 12 in 
Raymond and South Bend, and 1 in Tokeland. Two of the 
wharves at Raymond and South Bend are suitable for use by 
ocean-going vessels. One of these is publicly owned and 
operated as a general cargo terminal, and one is located at a 
sawmill. The other wharves, including 3 that are publicly 
owned and operated, are used by shallow-draft vessels. 
These facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys were made of various segments of the 
project. 
Maintenance, contract: A clamshell maintenance dredging 
contract for the Bay Center channel was completed in August 
1989, at a cost of $209,289 with 33,159 cubic yards of shoal 
material removed. 
Beach Erosion 
Beach Erosion Control 
17. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 103, 
Public Law 87-874 (preauthorization). 
Fiscal year costs were: Coupeville, Whidbey Island, WA, 
$7,119. 
18. LINCOLN PARK BEACH, SEATTLE, WA 
Location. Project is located within the city of Seattle, at 
Williams Point, and adjacent to the East Passage of Puget 
Sound. 
Existing project. Beach nourishment consisting of the initial 
placement of 34,000 tons of sand, gravel, and cobble fill 
seaward of the existing seawall, a distance of 2,300' along the 
southwest beach. The fill extends horizontally 10' seaward of 
the wall, then slopes downward on a 1V to 5H gradient to 
intersect the existing groundline 65' seaward of the wall. 250' 
of rock revetment, at Williams Point, consisting of 2 layers of 
1,500- to 4,000-pound armor rock placed on a 2'-thick filter 
bed of quarry spalls, constructed with a 1V to 1.5H slope, a 
10'-top width, and a top elevation approximately 1' above the 
existing seawall. The revetment is fronted by 2,000 tons of 
gravel and cobble fill, with the same top elevation, slope and 
seaward extent as the beach nourishment on the southwest 
beach. Periodic beach nourishment, consisting of placement 
of beach material to replenish the erosion loss, is required 
approximately every 5 years. Monitoring of beach nourishment 
consists of initial and periodic profile surveys, estimate 
alongshore/offshore volumes of material, installation of wind 
gage at site, and periodic beach sediment sampling. Estimated 
construction cost is $780,000 ($508,000 Federal; 
$272,000 non-Federal). Initial construction was completed in 
December 1988. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (city of Seattle) provides 35% of 
total project cost. Local Cooperation Agreement was executed 
on June 15, 1988. 
Operations during fiscal year. New work, hired labor: 
Completed operation and maintenance manual and postconstruction 
monitoring. 
New work, contract: Completed initial construction contract. 
Awarded post-construction evaluation contract. 
Flood Control 
19. BITTERROOT RIVER, FLORENCE, MT 
Location. Project is located along the Bitterroot River in 
Ravalli County, 5.2 miles south of Florence, MT. 
Existing project. Plan of improvement provides for 900 
liinear feet or riprap protection consisting of a blanket 36" 
thick on a 1V to 2H slope and a 15-foot-wide, 4.5-foot-thick 
weighted riprap toe. Construction was completed in May 
1989, but final fiscal requirements remain to be completed. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (State of Montana) has provided 
25% of project cost. Local Cooperation Agreement was executed 
on December 16, 1988. 
Operations during the fiscal year. New work, hired labor: 
Completed plans and specifications. Avertised, awarded, and 
supervised construction contract. 
New work, contract: Construction of bank protection. 
20. ELWHA KLALLAM RESERVATION, 
ELWHA, WA 
Location. Within the Elwha River basin on the Olympic 
peninsula of Washington State, and approximately 6 miles 
west of the city of Port Angeles in Clallam County. 
Existing project. A setback levee, 7,640 feet long, averaging 
8 feet high with a 12-foot top width, to reduce flood 
damages along the lower Elwha River within the Klallam 
38-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
Tribal Reservation. The landward levee slope would be covered 
with soil and the riverward slope would be protected 
with quarry spalls. Both slopes would be planted with native 
grasses. Top of levee would be surfaced with gravel to provide 
a suitable road for inspection and maintenance. Interior 
runoff reaching the levee would be drained through gated 
culverts and a 1,000-foot-long drainage ditch which would 
parallel the downstream portion of the levee. Ramps would 
be built across the levee to provide access to property and the 
existing hatchery fish holding pond would be relocated behind 
the levee. Estimated construction cost is $1,196,000 
($897,000 Federal; $299,000 non-Federal). Construction is 
scheduled to be completed in November 1989. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (Lower Elwha Klallam Tribe) will 
provide 25% of project cost. Local Cooperation Agreement 
was executed on November 23, 1988. Local sponsor will also 
provide operation and maintenance of the completed project. 
Operations during fiscal year. New work, hired labor: 
Supervision and inspection of construction contract. 
New work, contract: Contract for project work was 
awarded in February 1989 in the amount of $859,332. 
21. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 14, Public Law 
526, 79th Congress, as amended (preauthorization). 
Fiscal year costs were: Half Moon Bay, WA, $2,087; Neah 
Bay, Clallam County, WA, $14,472; Redondo Beach, WA, 
$1,448. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization). 
See Table 38-J. 
Emergency flood-control activities - repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and antecedent 
legislation.) 
Fiscal year costs were: Disaster Preparedness Program, 
$449,499. 
22. HOWARD A. HANSON DAM, WA 
Location. Green River, in northwestern Washington, flows 
westerly for 40 miles to Auburn, thence northerly 32 miles to 
its mouth in Elliott Bay at Seattle. Dam is at river mile 64, 6 
miles southeast of Kanaskat, and 1 mile downstream from 
mouth of North Fork. (See Geological Survey topographic 
sheet, "Cedar Lake Quadrangle, WA.") 
Existing project. Rockfill dam about 235 feet high, with 
gated spillway having a concrete weir at elevation 1176 feet 
above mean sea level aind top of gates at elevation 1206, 
creating a reservoir with capacity of 106,000 acre-feet. Dam 
along crest is about 675 feet long. Improvement is designed to 
control flooding in Green River Valley to alleviate agricultural 
and urban flood damage, and make possible further 
expansion of Seattle industrial area. It also supplements 
Tacoma water supply which was included as a betterment. 
Project was completed in June 1963. (For further details, see 
Annual Report for 1963.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired labor: 
Operation continued all year. Routine maintenance was accomplished 
on roads, gages, debris booms, turbidimeter, 
ditches, powerline, and other project features. The outlet 
works and stilling basin were inspected. Work continued on 
water quality surveys, water storage studies, and channel 
capacity study. 
23. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections are made of Federally constructed local flood 
protection projects which are maintained by local interests; 
and agencies responsible for their operation and maintenance 
are advised of any needed repairs. During the fiscal 
year, inspections were made on Okanogan River at Omak and 
Oroville, Dungeness River at Sequim, Sammamish River, 
American Lake, Stillaguamish River and Yakima River, all in 
Washington State; Lightning Creek, Coeur d'Alene, and St. 
Maries projects in Idaho. Streambank vegetation evaluations 
were made at Omak and Oroville and on the Green River in 
Washington. Thirty Section 14 bank protection projects in 
WA, ID, and MT, were inspected in conjunction with flood 
control projects. Fiscal year costs were $68,417. Costs to date 
have been $887,328. 
24. INSPECTION OF COMPLETED PL-99 
WORKS 
Levee inspections and evaluations to determine future eligibility 
were made on approximately 70 miles of levees on the 
Nooksack, Yakima, Naches, St. Joe, and Coeur d'Alene Rivers 
in WA and ID. Stationing and levee profiles were completed 
on the Snoqualmie, Tolt and Raging Rivers in WA. 
Fiscal year costs were $2,137. Total costs to date have been 
$471,244. (Function moved to appropriation, Flood Control 
and Coastal Emergencies beginning Fiscal Year 1989.) 
25. LITTLE QUILCENE RIVER, NEAR 
QUILCENE, WA 
Location. Project is located in Jefferson County, 1 mile 
northeast of Quilcene, WA, in Mt. Walker Quadrangle SE 
1/4 sec 11, T. 27 N., R. 2W. 
Existing project. Approximately 200 linear feet of riprap 
bank protection was proposed to prevent further erosion of 
Wildwood Road which is adjacent to the Little Quilcene 
River. Protection would consist of a riprap blanket 36" thick 
on a 1V to 1.5H slope and a 12-foot-wide, 4-foot-thick 
weighted riprap toe. Estimated cost of the project was 
$48,500 ($36,375 Federal; $12,125 non-Federal). Project was 
cancelled due to an inability of local sponsor to provide all the 
real estate necessary for project construction. 
38-8

SEATTLE, WASHINGTON DISTRICT 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (Jefferson County) would have provided 
25% of project cost. 
Operations during fiscal year. New work, hired labor: 
Management funds expended to close out the project. 
26. MUD MOUNTAIN DAM, WA 
Location. On White River, principal tributary of Puyallup 
River, near Mud Mountain, 28 miles above its confluence 
with Puyallup River, and 38 miles above mouth of Puyallup 
River. Dam is 6 miles southeast of Enumclaw, in northwestern 
Washington, and 38 miles east of Tacoma. (See Geological 
Survey topographic sheet, "Cedar Lake Quadrangle, 
Washington.") 
Existing project. Rockfill dam, 700 feet long at crest elevation, 
rises 425 feet above bedrock. Reservoir has storage 
capacity of about 106,000 acre-feet. Outlet works are in right 
abutment and permit controlled discharge of 17,700 cubic 
feet per second through two concrete-lined tunnels with 
uncontrolled discharge over spillway having maximum capacity 
of 139,000 cubic feet per second. Improvement affords 
flood protection to White and Puyallup River Valleys and 
protects Tacoma industrial district in conjunction with Puyallup 
River project at Tacoma against floods about 50 percent 
greater than maximum discharge of record. Project was completed 
in June 1953, except for recreational facilities. (For 
further details, see Annual Report for 1953.) To date the 
Corps has constructed two vistas, a picnic area, and playground 
adjacent to the project office, a reservoir access point 
for hunters and fishermen, and a 1,760-foot trail leading to 
the lower vista area. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired labor: 
Project features were operated all year. Maintenance was 
accomplished on dam facilities, intake structure, gages, debris 
booms, power lines, roads, ditches, and fish facilities. 
Approximately 1,300 fish were transported from the fish 
collection facility. 
Dam Safety Assurance. New work, hired labor: A Feature 
Design Memorandum for correcting earthquake and debris 
blockage deficiencies in the outlet tower was completed. 
Major Rehabilitation. New work, hired labor: Supervision 
and inspection of construction contract. 
New work, contract: A contract for construction of a seepage 
control cutoff wall in the core of the dam was initiated. 
27. SAUK RIVER, SKAGIT COUNTY, WA 
Location. Project is located in Skagit County, WA, 50 miles 
northeast of Seattle, WA. Work is identified on the left bank 
of the Sauk River approximately 5.5 miles downstream from 
Darrington, WA. 
Existing project. Plan of improvement provides for 680 feet 
of riprap bank protection to prevent threatened erosion on 
State Route 530. Protection consists of a riprap blanket 42 
inches thick and a 15-foot-wide, 4.5-foot-thick weighted toe. 
Cost of the project was $152,400 ($119,600 Federal; $32,800 
non-Federal). Work was physically complete on September 
22, 1988. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (Washington State Department of 
Transportation) provided 25% of project cost. Local Cooperation 
Agreement was executed on July 11, 1988. 
Operations during fiscal year. New work, hired labor: 
Scheduled work was fiscally completed. 
28. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Flood control storage space was available in Hungry Horse 
Reservoir, MT, Flathead Lake, MT (controlled by Kerr 
Dam), Grand Coulee project, WA, Upper Baker and Ross 
Reservoirs, WA. Guidance forecasts were made during the 
flood control season, as required. No Lost Valley storage 
replacement was requested at Rocky Reach, Priest Rapids, 
and Wells Dams. Daily and/or hourly data were collected and 
tabulated as required to check compliance with operating 
criteria. Coordination necessary in preparation or revision of 
reservoir regulation manuals was carried on during the year 
with agencies responsible for the operation of these projects. 
Fiscal year costs were $116,145. Total costs to date have been 
$2,149,055. 
29. SPOKANE RIVER, SPOKANE, WA 
Location. Project is located on the right bank of the 
Spokane River at approximately River Mile 82.6, in the city of 
Spokane, WA, in Spokane NE Quadrangle NE 1/4 sec. 11, T. 
25 N., R. 43 E. 
Existing project. Approximately 600 linear feet of riprap 
bank protection to prevent further erosion of Upriver Drive, 
a city of Spokane arterial street. Protection consists of a 
riprap blanket 36" thick on a 1V to 2H slope and a 15-footwide, 
5-foot-thick weighted riprap toe. Total cost of the 
project was $154,400 ($115,800 Federal; $38,600 non-Federal). 
Construction was completed on December 7, 1987. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (City of Spokane) provided 25% of 
project cost. Local Cooperation Agreement was executed on 
October 23, 1987. Additional bank protection work was accomplished 
at the request of and funded by the local sponsor 
at a cost of $44,790. 
Operations during fiscal year. New work, hired labor: 
Scheduled work was fiscally completed. 
30. STILLAGUAMISH RIVER, WA 
Location. Formed by confluence of its north and south 
forks at Arlington, in northwestern Washington, Stillaguamish 
River flows westerly 22 miles to Puget Sound, 
entering Port Susan through Hat Slough and South Pass, and 
Skagit Bay through West Pass. (See NOAA Survey Chart 
18441, and Geological Survey Quadrangles Stanwood, 
Marysville, and Stillaguamish, WA.) 
Existing project. Works to reduce bank erosion and channel 
changes on Stillaguamish River 15 miles between Ar- 
38-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
lington and head of Hat Slough, and on Cook Slough, 3 miles 
long, as follows: Revetment at 26 places on river and Cook 
Slough; concrete weir (including a fishway) 275 feet long 
between steel-sheet-pile piers at head of Cook Slough to 
limit flow through slough; and two cutoff channels, each 
about 900 feet long, to eliminate sharp bends in Cook Slough. 
Tidal influence extends about 3 miles into improved section. 
Flood stages of 16 feet above low water at Cook Slough weir 
have been observed. Project was completed in July 1939. (For 
further details, see Annual Report for 1940.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired labor: 
Utilized in-house labor and equipment to replace rock riprap 
bank protection along 800 linear feet of segment #24. 
Maintenance, contract: Existing low water weir was modified 
by installing a fishway along the left bank caisson. Work 
was completed in October 1988. 
31. TACOMA, PUYALLUP RIVER, WA. 
Location. Puyallup River has its source in glaciers on western 
slopes of Mount Rainier, WA, flows northwesterly 50 
miles, and empties into Commencement Bay, an arm of 
Puget Sound, at Tacoma. Work covered by this project is on 
Puyallup River, within city limits of Tacoma. (See NOAA 
Survey Chart 18453.) 
Existing project. A channel with a capacity of 50,000 cubic 
feet per second between East 11th Street Bridge and lower 
end of inter-county improvement, a distance of about 2.2 
miles, by straightening channel, building levees, revetting 
channel and levees, and making necessary bridge changes. 
The 11th Street Bridge at lower end of project is 0.75 mile 
above mouth of Puyallup River. Diurnal tidal range at mouth 
of river is 11.8 feet and extreme range is 20 feet. Improvement 
was planned in conjunction with Mud Mountain Dam 
and affords protection against floods about 50 percent 
greater than maximum discharge of record. A real estate 
design memorandum, approved by Office of the Chief of 
Engineers on October 2, 1985, changed the project boundary 
to allow the Port of Tacoma to create a wetland adjacent to 
the project. This action resulted in the Corps acquiring approximately 
2,450 linear feet of setback levee in fee simple. 
Maintenance funds to cover the increased length of the project 
have been provided by the Port of Tacoma for the project 
life. Project was completed in May 1950. (For further details, 
see Annual Report for 1950.) 
Local cooperation. Fully complied with.. 
Operations during fiscal year. Maintenance, hired labor: 
Removed brush from the entire project along slopes of levee. 
32. WYNOOCHEE LAKE, WA 
Location. On Wynoochee River, a tributary of Chehalis 
River, about 28 miles north of Montesano, Grays Harbor 
County, WA. (See Geological Survey Quadrangles, Grisdale, 
Wynoochee Valley, and Montesano.) 
Existing project. Provides for a concrete and earthfill dam, 
177 feet high, and reservoir of 70,000 acre-feet of total storage 
for water supply, flood control, irrigation, and fish and 
wildlife. Upstream fish facilities were operational in the fall 
of 1970. The project was completed and became operational 
in December 1972. Installation of power-generating facilities 
was not authorized, pending a reexamination report by the 
Chief of Engineers. In February 1966, the Federal Power 
Commission asserted that power production as part of the 
Wynoochee project was not feasible at that time. (For further 
details, see Annual Report for 1972.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-12 of FY 1981 Annual Report. 
The Water Resources Development Act of 1988 authorized 
the Secretary of the Army to transfer the Operations, Maintenance, 
Repair and Rehabilitation (OMR&R) of the 
Wynoochee project to the city of Aberdeen. The dam was 
built on a cost-share basis with the city which pays approximately 
46% of the investment and O&M costs. The legislation 
relieves the city of the O&M payment when it assumes 
the OMR&R, to the extent the city personnel does the work. 
Operations during fiscal year. Maintenance, hired labor: 
Project facilities were operated all year. Maintenance was 
accomplished on dam and fish facilities, roads, ditches, culverts, 
and visitors' facilities. The project tank truck hauled 
upstream migrant fish past the dam. Study effort for orderly 
transfer of OMR&R of the project to the city of Aberdeen 
was initiated. 
Multiple-Purpose Projects, Including Power 
33. ALBENI FALLS DAM, ID 
Location. Dam is on Pend Oreille River about 25 miles 
west of Sandpoint, in northern Idaho, and 50 miles northeast 
of Spokane, WA. Dam is 838 and 90 miles upstream from 
mouths of Columbia and Pend Oreille Rivers, respectively. 
(See Geological Survey topographic sheets, Sandpoint, ID, 
and Newport, WA.) 
Existing project. Provides flood control, hydroelectric 
power, and related water uses on Pend Oreille River as a part 
of the multiple-purpose plan for development of Columbia 
River Basin, including recreation development. At the dam, 
channel was formerly divided by an island and a low waterfall 
of about 7 feet. Dam is a gated, gravity-structure spillway in 
left channel and a power-house having an installation of 
42,600 kilowatts in right channel, creating a reservoir with a 
usable storage capacity of 1,153,000 acre-feet. Project was 
completed in June 1957. (For further details, see Annual 
Report for 1957.) Recreational facilities for public use have 
been provided at Albeni Cove, Priest River, Riley Creek, 
Johnson Creek, Trestle Creek, Strongs Island, and Springy 
Point. (Strongs Island was closed in FY 1982 to reduce O&M 
costs.) (Refer to Albeni Falls Master Plan dated June 1981 
for further planned development.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired labor: 
Reservoir was operated through its annual cycle of storage 
and release. Routine structural, mechanical, and electrical 
38-10

SEATTLE, WASHINGTON DISTRICT 
maintenance was performed on spillways, dam, powerhouse, 
and equipment. 
Maintenance, contract: Work continued on the boundary 
monumentation. 
34. CHIEF JOSEPH DAM, RUFUS WOODS 
LAKE, WA 
Location. On Columbia River in north central Washington, 
at River Mile 545, just upstream from mouth of Foster Creek, 
1.5 miles upstream from Town of Bridgeport. (Geological 
Survey topographic sheet, Okanogan, WA, shows general 
locality.) 
Existing project. A concrete gravity structure which consists 
of a 19-gate spillway and a 27-unit powerhouse. The 
powerhouse has sixteen 88,274 kilowatt and eleven 95,000 
kilowatt generators with nameplate capacity of 2,457,384 
kilowatts. Additional work will be required to bring turbine 
efficiency for units 17-27 up to design standards. Uprating 
and plant modernization of units 1-16, and other miscellaneous 
project work, is essentially complete. Estimated cost of 
current construction project is $395,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New work, hired labor: Continued 
real estate acquisition. 
New work, contract: Contracts were awarded for data 
acquisition and control system, project final completion, station 
service governors, repaint powerhouse interior, and 
spillway spall repair. 
Contracts continuing through the fiscal year included generator 
stator rewind, transformers, main unit excitation system, 
powerhouse gallery drainage, project security, and turbine 
deficiency correction (units 17-27). Contracts 
completed during the fiscal year included installation and fire 
protection, project completion, station service system, and 
wildlife mitigation: mule deer study and mitigation evaluation. 
Maintenance, hired labor: Project was operated all year, 
and routine maintenance work was performed. 
Maintenance, contract: Major contracts awarded during 
the fiscal year included seal spillway pier cracks, install 
piezometers in right abutment, grout intake structure leaks, 
station service switchgear, and miscellaneous replacement 
orders. Contracts continuing through the fiscal year included 
repair and paint trashracks, paint generator tops and barrels, 
and irrigation outlet valve and trashrack. 
35. LIBBY DAM - LAKE KOOCANUSA, MT 
Location. On Kootenai River in Lincoln County, MT, 
about 17 miles upstream from Libby, and 219 miles upstream 
from confluence of Kootenai and Columbia Rivers. (See 
Geological Survey topographic sheet, Thompson Lakes, 
MT.) 
Existing project. Provides storage for local flood control 
protection in Montana and Idaho, and main stem flood control 
in Lower Columbia River, hydroelectric power generation 
at-site and at downstream plants through storage release. 
Project will be operated as a unit of comprehensive 
system for improvement of Columbia River basin for flood 
control, navigation, hydroelectric power, and other purposes. 
Local cooperation. Fully complied with. 
Libby Dam - Lake Koocanusa Project. Dam is a straight 
concrete gravity overflow type, 420 feet high, 3,055 feet long, 
with normal full pool at elevation 2459 feet above mean sea 
level. Powerhouse has an initial installed capacity of 420,000 
kilowatts from four hydroelectric generating units with provision 
for four additional units, one of which is currently under 
construction. Lake Koocanusa is 90 miles long, backing water 
42 miles into Canada and has a usable storage capacity of 
4,965,000 acre-feet at 50 percent drawdown. Construction of 
dam was in accordance with treaty between United States and 
Canada relating to international cooperation in water-resource 
development of the Columbia River basin. Construction 
is complete. 
Operations during fiscal year. Maintenance, hired labor: 
Reservoir was operated through its annual cycle of storage 
and release. Routine structural, mechanical, and electrical 
maintenance was performed on spillway, dam powerhouse, 
and equipment. 
Maintenance, contract: Work continued to upgrade and 
maintain the left abutment instrumentation. 
Libby Additional Units Project. Provides for installation of 
4 additional units at the Libby Dam powerhouse. Fabrication 
of generators for units 5 through 8 is complete; however, only 
the unit 5 generator was installed. Installation of the electrical 
equipment was limited to unit 5. Parts for units 6 through 
8 have been stored at the site. Project is complete. Units 6 
through 8 have been reclassified inactive. 
Operations during fiscal year. None. 
Libby Reregulating Dam Project. Provides for construction 
of a reregulating dam about 10 miles downstream of Libby 
Dam and associated relocation of about 9 miles of Burlington 
Northern Railroad, 7.5 miles of St. Regis log haul road, 0.5 
mile of Forest Development Road, and 7.5 miles of Montana 
State Highway. Funds were provided for a construction start 
in 1977; however, courts have found that Congress did not 
authorize construction of the reregulating dam. 
Operations during fiscal year. In FY 82, all work was terminated 
due to court direction. 
Libby Reregulating Dam - Power Units Project. Provides 
for installation of three hydroelectric generating units at the 
reregulating dam with 78,900 kilowatt installed capacity. A 
General Design Memorandum 1, Phase II, Preliminary Design 
Report was approved by the Office, Chief of Engineers 
on March 3, 1981. 
38-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989 
General Investigations 
36. SURVEYS 
Fiscal year costs were $279,641 for navigation studies, $452 
for flood damage prevention studies, $204 for comprehensive 
studies, $100,921 for review of authorized projects, $167,925 
for miscellaneous activities, and $50,247 for coordination 
with other agencies and non-Federal interests, a total of 
$599,390. 
37. COLLECTION AND STUDY OF BASIC 
DATA 
The work programmed for collection and study of basic 
data covers international water studies, flood plain management 
services, and hydrologic studies. Work on international 
water studies included checking Kootenay Lake storage computations 
to determine compliance of West Kootenay Power 
& Light Co. with orders of International Joint Commission, 
and coordination with International Kootenay Lake and 
Osoyoos Lake Boards of Control in enforcement of International 
Joint Commission orders. Coordination with the 
Osoyoos Lake Board of Control included technical assistance 
in review of operation plans for the recently constructed 
Osoyoos Lake control structure and Duck Lake. Technical 
assistance was provided other Federal and non-Federal 
agencies in flood hazard evaluation and related services as 
requested. Fiscal year costs were $2,690 for international 
water studies, $125,341 for flood plain management services, 
and $3,551 for hydrologic studies, a total of $131,582. 
38. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
Blair and Sitcum Waterways, Tacoma Harbor, WA 
Tacoma Harbor, Pierce County, is located in southern 
Puget Sound at Tacoma, WA, about 30 miles south of Seattle. 
The proposed plan of improvement provides for (a) modification 
of the existing Federal project for Blair Waterway to 
provide for the construction and maintenance of a 45-foot 
and a 41-foot channel including replacement of the East 11th 
Street Bridge and (b) Federal maintenance of the locally 
constructed Sitcum Waterway to depths of 40 and 35 feet. 
Work on the proposed project has ceased pending resolution 
of Indian land claims and possible elimination of replacement 
of the East 11th Street bridge. Legislation passed 
by Congress and signed by President Bush authorized full 
payment of $77,250,000. Washington State has authorized 
payment of its share. Remaining is the local community, Port 
of Tacoma and city of Tacoma. 
Estimated preconstruction engineering and design cost is 
$2,640,000. Fiscal year costs were $8,132. Total costs to date 
have been $1,310,000, including $300,000 appropriated and 
expended under Section 101(c). 
Centralia, WA 
The city of Centralia lies in west central Washington at the 
confluence of the Chehalis and Skookumchuck Rivers, about 
midway along the Chehalis River from its source in the Willapa 
Hills to its mouth at Aberdeen on Grays Harbor. 
The plan of improvement authorized in P.L. 99-662 would 
reduce flooding in the Skookumchuck River valley for the 22 
miles between Skookumchuck Dam and the river mouth and 
along the Chehalis River downstream from Centralia for 
about 20 miles to Oakville. The improvement, as recommended 
in the feasibility report, consists of structural modifications 
(flood control outlet tunnel and spillway gate) which 
would enable the existing, private water supply dam to provide 
flood control storage during winter months. The 
200-year flood on the Skookumchuck River at Centralia 
would be reduced from 13,300 cubic feet per second to 6,700 
cubic feet per second (about a current 4-year flow). The 
200-year flood plain would be reduced by 1,500 acres with 
water surface reductions of between 2 and 5 feet. 
Preconstruction Engineering and Design (PED) accomplished 
during the fiscal year included completion of the Plan 
of Action outlining preconstruction engineering and design 
studies, completion of the basic hydrologic analysis, initiation 
of coordination with the dam owner on appropriate flood 
control guide curves, initiation of comparative design analysis 
of dam modification options, and agreement by the city of 
Centralia to serve as local sponsor.. Estimated PED cost is 
$4,978,000. Fiscal year costs were $537,105. Total costs to 
date have been $736,964. 
Chehalis River at South Aberdeen and Cosmopolis, WA 
The cities of Aberdeen and Cosmopolis are located at the 
mouth of the Chehalis River in Grays Harbor County. The 
Chehalis River, about 125 miles in length, rises in the Willapa 
Hills in west central Washington. 
The plan of improvement, authorized in P.L. 99-662, as 
refined by the draft General Design Memorandum, would 
protect most of the left bank flood plain at the mouth of the 
Chehalis River in the cities of Aberdeen and Cosmopolis. 
The improvement would include segments of earthen embankment 
levee (2.2 miles) and steel sheetpile floodwall (0.9 
miles), joining areas of high ground (1.1 miles). The project 
roughly follows the left bank of the Chehalis River from 
Devonshire Slough to Cosmopolis. The levee would protect 
1,176 acres of the cities from inundation by the standard 
project flood. 
Accomplishments during the fiscal year included completion 
of the General Design Memorandum and Environmental 
Impact Statement. 
Estimated preconstruction engineering and design cost is 
$1,828,000. Fiscal year costs were $75,223. Total costs to date 
have been $1,321,935. 
Grays Harbor, Chehalis and Hoquiam Rivers, WA 
Grays Harbor is a large tidal estuary in southwestern Washington. 
The entrance is 45 miles north of the mouth of the 
Columbia River and 110 miles south of the Strait of Juan de 
Fuca. The estuary lies entirely within Grays Harbor County, 
State of Washington. 
The proposed plan of improvement consists of modifying 
the existing Federal project for Grays Harbor. The existing 
38-12

SEATTLE, WASHINGTON DISTRICT 
30-foot channel would be deepened to 46 feet across the 
ocean bar and widened in this reach from the existing 600 
feet to a 1,000-foot-wide channel; the entrance reach would 
be widened and deepened from the existing 350-foot-wide 
by 30-foot-deep channel to a channel tapering landward 
from 1,000 to 600 feet wide and 46 to 36 feet deep; the 
existing 350-foot-wide channel from South reach to Cow 
Point would be deepened from 30 feet deep to 36 feet deep; 
and the Aberdeen and South Aberdeen reaches would be 
widened and deepened from the existing 200-foot-wide by 
30-foot-deep channel to 250-300 feet wide by 36 feet deep. 
Two turning basins located at Aberdeen would be expanded 
and the existing railroad bridge would be modified to a horizontal 
clearance of 250 feet. Crab and fish mitigation are 
included in the project. 
During the fiscal year the General Design Memorandum 
(GDM) and Environmental Impact Statement Supplement 
(EISS) were completed. A contaminated sediments study was 
initiated in June 1989 to address concerns about Dioxin in the 
Grays Harbor sediments. Dredging from the ocean bar to 
Cow Point and construction of crab and fish mitigation are 
scheduled for Fiscal Year 1990. 
Estimated preconstruction engineering and design cost is 
$6,000,000. Fiscal year costs were $1,302,075. Total costs to 
date have been $5,597,382. 
38-13

REPORT OF THE SECRETARY OF THE AR1AY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
1. Anacortes Harbor, 
WA (Federal Funds) 
(Contrib. Funds) 
2. Bellingham Harbor, 
WA (Federal Funds) 
(Contrib. Funds) 
3. Ediz Hook, WA 
(Federal Funds) 
(Contrib. Funds) 
4. Everett Harbor and 
Snohomish River, 
WA (Federal Funds) 
(Contrib. Funds) 
5. Friday Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
6. Grays Harbor and 
Chehalis River, WA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work. 
Contrib. 
Cost 
Maint 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint,. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
185,000 167,000 258,000 
175,612 157,312 264,577 
- 188,000 
3,147 170,000 
-3,140 
6,679 
12,652 
68,000 
86,031 
-5 
7, 
13, 
12, 
7, 
16, 
-- 31,000 
-- 17,865 
-- 1,380 
690 -- 
291,000 492,000 910,500 970, 
294,189 489,763 793,615 1,083,E 
33 
-- 13,E 
-- 13, 
-9,600 
-- 222,345 
- 222,345 1 
;000 1,149,239 
472 1,149,212 
-- 59,524 
-- 59,524 
-- 5,000 
-- 5,000 
-- 1,566,839 
-- 1,566,839 2 
000 1,333,069 
859 1,332,918 3 
-- 29,421 
-- 29,421 
-- 9,103 
-- 9,103 
-- 5,878,740 
-- 5,878,740 
000 1,162,860 
773 1,159,498 
-- 385,850 
-- 385,850 
- 131,965 
-- 130,585 
-- 1,775,745 
-- 1,775,745 4 
600 9,435,178 
617 9,428,417 5 
-- 116,618 
-- 116,618 
-- 584,090 
-- 584,090 
-- 1,575,500 
-- 1,575,500 
800 13,800 
649 13,649 
-- 1,267,881 
-- 1,267,881 
-- 5,155,796 
38-14

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
( FRuirn2d s- (Yt6 - - -- 5155796 
(Contrib. Funds) 
7. Lake Crockett, WA 
8. Lake Washington 
Ship Canal, WA 
(Contrib. Funds) 
10. Olympia Harbor, WA 
12. Puget Sound and its 
Tributary Waters, WA 
13. Quillayute River, WA 
(Federal Funds) 
(Contrib. Funds) 
to vuava csa aa aa .spr 
3,927,140 
3,944,749 
3,278,700 
3,267,434 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
3,307,000 2,941,, 
3,316,169 2,889,2 
36,000 
40,915 
480 87,297,851 
250 87,240,713 7 
-- 9,592 
-- 9,592 8 
-- 4,606,145 
-- 4,606,145 
-- 35,834 
-- 35,834 
-- 55,889 
-- 55,889 
-6,800 
134 
377,990 
377,990 9 
697,640 
697,640 
-- -- -- -- 4,611,436 
-- -- -- -- 4,611,43610 
3,755,000 3,641,000 6,185,950 4,715,000 75,665,860 
3,778,291 3,640,034 6,079,426 4,627,269 75,365,50911 
-- -- -- -- 7,465,230 
133,987 10,373 -- -- 7,465,230 
-- -- -- -- 250,000 
-- -- -- -- 250,000 
100,000 114,000 
100,000 111,719 112 2,133 
617,000 597,000 565,000 560,000 
612,490 597,072 565,203 548,423 
17,000 456,050 
19,410 456,244 
-- 902,000 
5,415 901,651 
359,315 
359,31512 
739,377 
739,34113 
43,337 
43,337 
18,134,302 
18,111,27014 
521,850 
521,85015 
10,494,071 
10,493,647 
20,000 
20,000 
- 38-15 - 
-- 155,500 
-- 143,651

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
14. Seattle Harbor. WA New Work 
(Federal Funds) 
(Contrib. Funds) 
15. Swinomish Channel, WA 
(Federal Funds) 
(Contrib. Funds) 
16. Willapa River and Harbor 
and Naselle River, WA 
(Federal Funds) 
(Contrib. Funds) 
18. Lincoln Park Beach, 
Seattle, WA 
(Federal Funds) 
(Contrib. Funds) 
19. Bitterroot River, Florence 
MT. 
(Federal Funds) 
(Contrib. Funds) 
20. Elwha Klallam Reservation, 
Elwha River, WA 
(Contrib. Funds) 
22. Howard A. Hanson 
Dam, WA 
(Federal Funds) 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,001,000 393,000 
940,157 459,554 
61,000 144,900 
57,688 108,357 
353,000 376,000 523,000 
149,813 570,290 521,808 
-- 115,650 
4,953 113,884 
10,000 
24,422 
83,100 
91,253 
-- 361,100 
4,011 354,726 
-- 355,000 177,000 
1,464 115,101 358,921 
-- -- 269,500 
-- -- 12,965 199,303 
-- 11,500 176,250 
-- 10,902 163,488 
-- -- 59,750 
-- -- 56,302 
68,000 20,000 155,000 963,000 
70,712 19,091 154,383 860,712 
-- -- -- 120,142 
-- -- -- 95,315 
170,335 
170,335 
7,791,646 
7,750,033 
69,333 
69,333 
20,000 
20,000 
808,332 
808,33216 
6,850,040 
6,847,675 
32,000 
32,000 
1,386,955 
1,386,9557 
13,639,196 
13,632,167'1 
78,372 
78,372 
722.500 
664,511 
269,500 
212,628 
187,750 
174,390 
59,750 
56,302 
1,523,900 
1,418,369 
120,142 
95,315 
-- -- -- -- 37,048,061 
-- -- -- -- 37,048,061 
727,000 805,500 701,000 713,000 11,777,801 
616,769 918,895 721,875 597,463 11,655,39419 
38-16

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
(Contrib. Funds) 
-- 2,000,000 
-- 2,000,000 
25. Little Quilcene River, 
near Quilcene, WA 
26. Mud Mountain 
Dam, WA 
(Federal Funds) 
(Contrib. Funds) 
27. Sauk River, Skagit County, 
WA (Federal Funds) 
(Contrib. Funds) 
29. Spokane River, Spokane, 
WA (Federal Funds) 
(Contrib. Funds) 
30. Stillaguamish River, WA 
(Federal Funds) 
(Contrib. Funds) 
31. Tacoma, Puyallup River, 
WA 
(Federal Funds) 
(Contrib. Funds) 
32. Wynoochee Lake,WA 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
-- 9,000 
-- 7,981 
1,439,000 1,200,000 
1,326,358 1,196,536 
1,230,000 1,151,000 
1,272,504 1,152,114 
7,462 
2,285 
2,175,000 
2,256,885 
1,121,000 
1,031,680 
16,462 
6,196 16,462 
1,420,000 
1,429,669 
965,000 
990,238 
-- 520,000 1,500,000 13,400,000 
-- 515,530 1,479,084 13,366,684 
-- 7,500 118,700 
-- 5,311 34,873 
-- -- 39,500 
-- -- 4,073 
-- 9,000 113,138 
-- 8,891 112,289 
-- -- 79,311 
-- -- 78,827 
110,000 100,000 100,000 
110,406 96,786 97,881 
40,000 35,000 
40,851 32,177 
-- 54,405 
50,000 
52,358 
6,165 
-6,600 
79,416 
-6,722 
28,705 
958 
484 
97,600 
38,459 
30,( 
29,E 
1,032,000 1,382,000 1,295,000 1,646, 
1,020,809 1,405,109 1,298,569 1,615,. 
19,503,849 20 
19,479,29721 
21,427,476 
21,319,80022 
285,908 
285,908 
15,420,000 
15,361,297 
3,928 
3,928 
119,600 
119,600 
32,778 
32,778 
122,138 
122,138 
79,311 
79,311 
134,595 
134,59523 
1,872,447 
1,807,952 
21,000 
21,000 
-- 3,947,853 
-- 3,947,85324 
000 611,781 
686 610,539 
-- 54,405 
-- 6,165 
-- 23,494,445 
-- 23,494,44525 
000 15,232,446 
314 15,163,83626 
- 38-17 - 
New Work 
Contrib. 
Cost

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
33. Albeni Falls Dam, ID New Work 
Approp. - -- -- -- 31,741,561 
Cost -- -- -- -- 31,741,56127 
Maint. 
Approp. 2,974,000 2,743,000 3,478,400 3,524,200 38,219,406 
Cost 2,971,854 2,823,626 3,447,226 3,448,526 38,087,96328 
34. Chief Joseph Dam- New Work 
Rufus Woods Lake, WA Approp. '11,023,000 6,200,000 5,145,000 4,370,000 521,748,235 29 
Cost 10,091,596 7,151,901 5,161,387 4,344,812 521,710,51530 
Maint. 
Approp. 6,608,000 6,885,000 8,183,000 9,134,400 97,072,912 
Cost 6,525,685 7,054,829 8,068,534 8,840,800 96,632,06131 
Major Rehab. 
Approp. - - - -- 297,630 
Cost -- -- -- -- 297,630 
35. Libby Dam, Lake New Work 
Koocanusa,MT Approp. 630,000 -- -- -- 543,858,44032 
(Federal Funds) Cost 715,232 17,893 -- 791 543,856,97933 
Maint. 
Approp. 3,653,000 3,746,100 3,699,000 4,084,000 36,989,579 
Cost 3,654,719 3,782,076 3,615,043 4,100,378 36,859,72834 
(Contrib. Funds) New Work 
Contrib. - - - -- 1,458,252 
Cost -- -- -- -- 1,458,252*3 
1. Excludes $2,000 Coast Guard funds expended. 
2. Includes $56,582 appropriated and expended for previous 
project. Excludes $13,000 Coast Guard funds expended. 
3. Includes $1,092 appropriated and expended for previous project. 
4. Includes $418,209 appropriated and expended for previous 
project. Excludes $43,000 Coast Guard funds expended. 
5. Includes $5,869 appropriated and expended for previous project. 
6. Includes $124,945 for recreation facilities at completed project 
(Code 710) and $113,134 for previous project, appropriated and 
expended. Excludes $161,909 Navy funds, and $6,000 Coast Guard 
funds expended. 
7. Includes $37,415 appropriated and expended for previous 
projects. Excludes $409,660 Emergency Relief funds and $57,000 
Public Works Administration funds expended. 
8. Excludes $111,000 Public Works Acceleration Act funds 
expended. 
9. Includes $117,750 appropriated and expended for recreation 
facilities at completed project (Code 710). 
10. Includes $779,655 for recreation facilities at completed project 
(Code 710) and $485,002 for previous project, appropriated and 
expended. Excludes $246,567 expended by State of Washington, 
$742,071 expended by King County, and $192,516 Public Works 
Administration funds expended. 
11. Includes $1,631,195 (1916 to 1936) and $338,163 subsequently 
appropriated and expended under Maintenance and Operation of 
Dams and Other Improvements of Navigable Waters. 
12. Includes $183,257 for previous projects and $18,700 expended 
for restudy Fiscal Years 1968-1973, appropriated and expended. 
Excludes $105,467 Public Works Administration funds expended. 
13. Includes $14,418 appropriated and expended for previous 
projects. 
14. Includes $64,996 appropriated and expended for previous 
project. 
15. Excludes Navy funds expended on dredging river channel in 
1944 and Coast Guard funds expended for channel dredging in 
1948 and 1949. 
16. Excludes $1,000 Coast Guard funds expended. 
17. Includes $228,084 appropriated and expended for previous 
projects. Excludes $40,000 Coast Guard funds and $192,314 
Emergency Relief funds expended. 
18. Includes $309,177 appropriated and expended for previous 
projects. Excludes $78,532 Public Works Administration funds 
expended. 
19. Includes $66,678 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
20. Includes $87,785 appropriated for recreation facilities at 
completed project (Code 710) and $6,234,000 for Dam Safety 
Assurance. Excludes $26,000 Emergency Relief funds. 
21. Includes $87,785 expended for recreation facilities at 
completed project (Code 710) and $6,209,448 for Dam Safety 
Assurance. Excludes $26,000 Emergency Relief funds expended. 
22. Includes $198,578 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
23. Excludes $281,000 Works Progress Administration funds and 
$85,999 Emergency Relief funds expended. 
24. Includes $5,035 appropriated and expended for recreation 
facilities at completed project (Code 710). 
25. Includes $102,200 appropriated and expended for recreation 
facilities at completed project (Code 710). 
26. Includes $66,678 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
27. Includes $971,947 appropriated and expended for recreation 
facilities at completed project (Code 710). Excludes $136,736 
Public Works Acceleration Act funds expended for recreation 
facilities at completed project (Code 710). 
28. Includes $174,776 Special Recreation Use Fees, appropriated 
and expended. Includes $424,820 appropriated and expended 
under Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. 
29. Includes $144,338,252 appropriated for original project, 
$377,262,000 for additional units, and $147,983 for recreation 
facilities at completed project (Code 710). Excludes $58,000 Public 
Works Acceleration Act funds for recreation facilities at 
completed project (Code 710). 
30. Includes $144,338,252 expended for original project, 
38-18

SEATTLE, WASHINGTON DISTRICT 
$377,224,280 for additional units, and $147,983 for recreation 
facilities at completed project (Code 710). Excludes $58,000 Public 
Works Acceleration Act funds for recreation facilities at 
completed project (Code 710). 
31.Includes $774,561 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
32. Includes $484,753,143 appropriated for the original project, 
$42,221,634 for additional units, $16,276,363 for reregulating dam, 
$475,000 for power planning, and $132,300 for Kelley Flats 
Airport. 
33. Includes $484,753,143 appropriated for the original project, 
$42,220,173 for additional units, $16,276,363 for reregulating dam, 
$475,000 for power planning, and $132,300 for Kelley Flats 
Airport. 
34. Includes $611,224 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
35. Excludes $161,849 expended by Federal Aviation Agency, 
$32,000 expended by Lincoln County- City of Libby Joint Airport 
Board, $8000 expended by Bonneville Power Administration, and 
$379,555 expended by U.S. Forest Service. 
- 38-19-

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. ANACORTES HARBOR, WA 
Mar. 2, 1919 
Sep. 3, 1954 
June 25, 1910 
July 3, 1930 
Aug. 26, 1937 
Sep. 3, 1954 
July 3, 1958 
Mar. 7, 1974 
June 25, 1910 
July 3, 1930 
June 20, 1938 
Sep. 3, 1954 
July 14, 1960 
Aug. 13, 1968 
July 14, 1960 
as amended 
June 3, 1896 
Mar. 2, 1907 
Mar. 2, 1907 
June 25, 1910 
June 25, 1910 
Aug. 8, 1917 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Aug. 30, 1935 
Channel in Capsante Waterway. 
Mooring basin. 
BELLINGHAM HARBOR, WA 
Whatcom Creek Waterway 26- and 18-foot channels. 
Entrance channel in Squalicum Creek Waterway. 
Maintenance of southerly half and westerly end of 
Squalicum Creek Basin. 
Small-boat basin adjacent to Squalicum Creek Waterway. 
Whatcom Creek Waterway, 30-foot channel. 
EDIZ HOOK, WA 
Construction of 10,000 linear feet of rock revetment, 
together with initial beach replenishment and annual 
nourishment.Emergency interim measures necessary to 
prevent breaching of Ediz Hook prior to construction of 
authorized project. 
EVERETT HARBOR AND SNOHOMISH RIVER, WA 
Training dike 10,500 feet long extending across bar 
at outlet of old river channel. 
Raise 6,000 feet of training dike, extend spur dike, 
widen gap in dike as required, maintain East Waterway and 
channel to gap. 
Abandon project for Snohomish River and provide 
settling basin near 14th Street. 
Spur dike at Preston Point, remove training dike 
north of river outlet, enlarge channel to 14th Street, and 
deepen settling basin. 
Widen channel from settling basin to gap; extend 
channel to head of Steamboat Slough; and a settling basin 
within upper channel reach. 
Raise and extend existing training dike; and construct 
breakwater on westerly and southerly sides of 14th 
Street small-boat basin.1 
FRIDAY HARBOR MARINA, WA 
Construction of 1,600 feet of concrete floating breakwater 
GRAYS HARBOR AND CHEHALIS RIVER, WA 
South jetty. 
A north jetty 9,000 feet long. 
The 18-foot channel. 
Extend north jetty 7,000 feet; length of south jetty 
fixed at 13,734 feet. 
A 6-foot channel above Cosmopolis. 
Dredging in bar channel. 
Dredging in bar channel. 
16-foot channel from Cosmopolis to Montesano.2 
Reconstruct north and south jetties to an elevation of 
16 feet above mean lower low water. 
Maintain 26-foot channel below Aberdeen (as authorized 
by Public Works Administration Dec. 11, 1933) 
and combining projects for Grays Harbor and bar entrance 
and Grays Harbor, inner portion, and Chehalis River under 
a modified project for Grays Harbor and Chehalis River. 
H. Doc. 1117, 64th Cong., 1st Sess. 
S. Doec. 102, 83rd Cong., 2d Sess. 
H. Doc. 1161, 60th Cong., 2d Sess. 
H. Doc. 187, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 70, 74th Cong., 1st Sess. 
H. Doc. 558, 82d Cong., 2d Sess. 
S. Doc. 46, 85th Cong., 1st Sess. 
H. Doc. 101, 93d Cong., 1st Sess., 
P.L. 93-251 
H. Doec. 1108, 60th Cong., 2d Sess. 
H. Doec. 377, 71st Cong., 2d Sess. 
H. Doec. 546, 75th Cong., 3d Sess. 
H. Doe. 569, 81st Cong., 2d Sess. 
H. Doe. 348, 86th Cong., 2d Sess. 
H. Doe. 357, 90th Cong., 2d Sess. 
Sec. 107, P.L. 86-645. 
Authorized by Chief of Engineers, 
July 9, 1981 
Annual Report, 1895, pp. 3517-3533. 
Rivers and Harbors Committee 
Doec. 2, 59th Cong., 2d Sess. 
H. Doec. 507, 59th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doe. 29, 61st Cong., 2d Sess. 
H. Doe. 1125, 60th Cong., 2d Sess. 
H. Doec. 1729, 64th Cong., 2d Sess. 
H. Doec. 582, 69th Cong., 2d Sess. 
H. Doec. 315, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc.2, 74th Cong., 1st Sess. 
H. Doe. 53, 73rd Cong., 1st Sess.; 
Rivers and Harbors Committee 
Doe. 2, 74th Cong., 1st Sess. 
38-20

SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Construction, operation, and maintenance of recreation Sec. 4, Flood Control Act of 1944 
facilities. 
Maintain 30-foot depth in channel from deep water in Report in Office, Chief of Engineers 
Grays Harbor to Port of Grays Harbor Commission terminal 
which was deepened from 26 to 30 feet with Navy funds. 
June 30, 1948 
Sep. 3, 1954 
Sep. 3, 1954 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
June 25, 1910 
Mar. 4, 1913 
Aug. 8, 1917 
Sep. 22, 1922 
June 26, 19344 
Aug. 30, 19355 
Dec. 22, 1944 
as amended 
July 24, 1956 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
10. 
14-foot channel to Bay City; breakwater at Westhaven; 
protection of Point Chehalis; and maintenance of 
Westhaven entrance channel.3 
Dredging and maintenance of a 30-foot channel and 
turning basin from Aberdeen to Cosmopolis. 
Additional breakwater, 1,400 feet long, at Westhaven Cove. 
LAKE CROCKETT, WA 
Small-boat basin. 
Construction, operation, and maintenance of 
recreation facilities. 
H. Doc. 635, 80th Cong., 2d Sess. 
H. Doe. 412, 83d Cong., 2d Sess. 
H. Doc. 30, 84th Cong., 1st Sess. 
H. Doc. 303, 77th Cong., 1st Sess. 
Sec. 4, Flood Control Act of 1944 
LAKE WASHINGTON SHIP CANAL, WA 
For a double lock and fixed dam with gated spillway H. Doc. 953, 60th Cong., 1st Sess. 
and necessary accessory works at entrance to Salmon Bay; 
dredging a channel from locks to deep water in Puget Sound, 
and excavation by local interests of a channel from locks into 
Lake Washington. 
Dredging below locks and revetting canal banks. H. Doc. 800, 64th Cong., 1st Sess. 
Increased dimensions of channel between Puget Sound H. Doc. 324, 67th Cong., 2d Sess. 
and locks and a 600-foot extension of lower guide pier. 
Operating and care of locks and dam provided for with 
funds from War Department appropriations for Rivers and 
Harbors. 
Enlarge channel between locks and Lake Washington. H. Doc. 140, 72d Cong., 1st Sess. 
Construction, operation, and maintenance of Sec. 4, Flood Control Act of 1944 
recreation facilities. 
Government Locks to be known as P.L. 84-779 
Hiram M. Chittenden Locks. 
OLYMPIA HARBOR, WA 
Channel 22 feet deep and 150 feet wide. H. Doc. 244, 69th Cong. 1st Sess. 
Channels of 26-foot depth on east side of harbor. Rivers and Harbors Committee 
Doc. 5, 71st Cong., 1st Sess. 
Elimination from project of 12-foot channel on east Rivers and Harbors Committee 
and west sides of harbor, and for a channel 30 feet deep Doec. 21, 73rd Cong., 2d Sess. 
and 300 feet wide between Budd Inlet and port terminal, 
with turning basin of same depth. 
Widen outer portion of channel to 500 feet, and Rivers and Harbors Committee 
widen entrance to turning basin. Doc. 75, 74th Cong., 2d Sess. 
Entrance channel 500 feet wide to and including a H. Doc. 699, 76th Cong., 3d Sess. 
turning basin 3,350 feet long and generally 960 feet wide, all 
at a depth of 30 feet at mean lower low water3 
PUGET SOUND AND ITS TRIBUTARY WATERS, WA 
Maintenance of the rivers tributary to Puget Sound by 
snagging and dredging; and removal of floating debris from 
Seattle Harbor. 
QUILLAYUTE RIVER, WA 
Jetty (5 feet high) on easterly side of mouth, and a 
dike on westerly side, to stabilize entrance. 
Annual Report for 1893, page 3425 
H. Doec. 125, 71st Cong., 1st Sess. 
- 38-21 - 
TABLE 38-B 
(Continued) 
Dec. 22, 1944 
as amended 
Mar. 2, 1945 
12. 
July 13, 1892 
13. 
July 3, 1930

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
14. 
Maintenance dredging to provide a channel 6 feet H. Doc. 218, 78th Cong., 1st Sess. 
deep and of suitable width from ocean to within river mouth. 
Raising jetty to 15 feet; channel 10 by 100 feet, 2,000 feet H. Doc. 579, 81st Cong., 2d Sess 
long; moorage basin. 6 
SEATTLE HARBOR, WA 
Maintenance of East and West Waterways 750 feet wide S. Doc. 313, 65th Cong., 3d Sess. 
and 34 feet deep, and of Duwamish Waterway 20 feet deep 
and 150 feet wide as far south as Eighth Avenue South Bridge. 
Mar. 2, 1945 
Sep. 3, 1954 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 
July 13, 1892 
Aug. 30, 1935 
Oct. 23, 1962 
July 27, 1916 
Aug. 30, 19355 
Aug. 30, 19357 
Mar. 2, 1945 
Sep. 3, 1954 
Oct. 23, 1962 
as amended 
July 24, 1946 
as amended 
June 30, 1948 
as amended 
May 17, 1950 
Aug. 6, 1958 
July 24, 1946 
as amended 
June 22, 1936 
H. Doc. 108, 68th Cong., 1st Sess. 
H. Doc. 126, 71st Cong., 2d Sess. 
H. Doc. 211, 72d Cong., 1st Sess. 
H. Doc. 31, 52d Cong., 1st Sess. and 
Annual Report for 1892, p. 2752 
S. Committee Print, 73rd Cong., 
1st Sess. 
H. Doc. 499, 87th Cong., 2d Sess. 
WILLAPA RIVER AND HARBOR AND NASELLE RIVER, WA 
Channel 24 feet deep, 200 feet wide, in Willapa River, H. Doc. 706, 63d Cong., 2d Sess. 
and 150 feet wide in the forks. 
Maintenance of channel over bar to a depth of 26 feet Rivers and Harbors Committee 
and minimum width of 500 feet. Doc. 41, 72d Cong., 1st Sess. 
For cutoff channel at Narrows. Rivers and Harbors Committee 
Channel from deep water in Palix River to BayCenter dock. 
Widen Willapa River channel to 360 and 250 feet between 
South Bend and the forks; Tokeland and Nahcotta basins; 
and Naselle River clearance. 
LINCOLN PARK BEACH, SEATTLE, WA 
250-foot rock revetment and 2,550 feet of sand and 
gravel nourishment. Periodic monitoring and replenishing 
beach nourishment. 
Doc. 37, 73rd Cong., 2d Sess. 
H. Doc. 481, 76th Cong., 2d Sess. 
H. Doc. 425, 83d Cong., 2d Sess. 
Sec. 103, P.L. 87-874 
Authorized by Chief of Engineers, 
Oct. 18, 1983 
BITTERROOT RIVER, FLORENCE, MT 
Construction of riprap bank protection. Sec. 14, P.L. 79-526 
Authorized by Chief of Engineers, 
Feb. 10,1988 
ELWHA KLALLAM RESERVATION, ELWHA RIVER, WA 
7,640-foot long levee, 8 feet high with 12-foot Sec. 205, P.L. 80-858 
top width and bottom width of 45 feet. Authorized by Chief of Engineers, 
Sep. 1, 1987 
HOWARD A. HANSON DAM, WA 
Eagle Gorge flood control dam on Green River. H. Doc. 271, 81st Cong., 1st Sess. 
Redesignation of project as Howard A. Hanson Dam. P.L. 85-592 
LITTLE QUILCENE RIVER, NEAR QUILCENE, WA 
Construction of riprap bank protection. Sec. 14, P.L. 79-526 
Authorized by Chief of Engineers, 
May 21, 1987 
MUD MOUNTAIN DAM, WA 
Flood control dam on White River. S. Committee Print, 
Puyallup River, WA, 
74th Cong., 2d Sess. 
38-22 
Enlargement of Duwamish Waterway. 
Maintenance of East Waterway between 750-foot section 
and Spokane Street, and turning basin at junction of East 
and Duwamish Waterways. 
SWINOMISH CHANNEL, WA 
Channel 4 feet deep and 100 feet wide, and dike 
construction. 
Enlargement of channel to present project dimensions. 
Removal of navigation hazards at "Hole-in-the-Wall". 
15. 
16. 
18. 
19. 
20. 
22. 
25. 
26.

TABLE 38-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
Dec. 22, 1944 
as amended 
July 24, 1946 
as amended 
July 24, 1946 
as amended 
June 22, 1936 
June 28, 1938 
June 22, 1936 
Dec. 22, 1944 
as amended 
Oct. 23, 1962 
Dec. 22, 1944 
as amended 
Mar. 7, 1974 
Mar. 7, 1974 
May 17, 1950 
Dec 22, 1944 
as amended 
July 24, 1946 
June 30, 1948 
July 9, 1952 
Dec. 22, 1944 
as amended 
Oct. 22, 1976 
as amended on 
May 4, 1977 
May 17, 1950 
Nov. 7, 1966 
Jan. 2, 1968 
Aug. 13, 1968 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized Documents 
Construction, operation, and maintenance of Sec. 4, Flood Control Act of 1944 
recreation facilities. 
SAUK RIVER, SKAGIT COUNTY, WA 
Construction of riprap bank protection. Sec. 14, P.L. 79-526 
Authorized by Chief of Engineers, 
Mar. 2, 1987 
SPOKANE RIVER, SPOKANE, WA 
Construction of riprap bank protection. Sec. 14, P.L. 79-526 
Authorized by Chief of Engineers, 
Dec. 19, 1986 
STILLAGUAMISH RIVER, WA 
Improvement of flood channel by clearing and bank H. Doc. 657, 71st Cong., 3d Sess. 
revetment at 26 places; concrete weir at head of Cook Slough; 
and 2 cutoff channels in Cook Slough. 
Maintenance of improvements. P.L. 75-761 
TACOMA, PUYALLUP RIVER, WA 
Channel improvement to protect people and industrial S. Committee Print, Puyallup River, 
section of city of Tacoma. WA, 74th Cong., 2d Sess. 
Construction, operation, and maintenance of Sec 4, Flood Control Act of 1944 
recreation facilities. 
WYNOOCHEE LAKE, WA 
Dam and reservoir for water supply, flood control, 
irrigation, fish and wildlife, and recreation. 
Construction, operation, and maintenance of 
recreation facilities. 
Transfer to State of Washington as a part of project costs, 
$696,000 for construction of fish hatchery facilities. 
Amend contract between city of Aberdeen and United 
States for use of storage space, permitting deferral of the 
major portion of the first 10-year payments. 
ALBENI FALLS DAM, ID 
Multi-purpose dam with powerhouse. 
Construction, operation, and maintenance of 
recreation facilities. 
CHIEF JOSEPH DAM - RUFUS WOODS LAKE, WA 
Multi-purpose dam and powerhouse on Columbia 
River at Foster Creek. 
Redesignation of the project as Chief Joseph Dam. 
Designation of reservoir as Rufus Woods Lake. 
Construction, operation, and maintenance of 
recreation facilities. 
School facilities for education of dependents of 
construction personnel. 
H. Doc. 601, 87th Cong., 2d Sess. 
Sec. 4, Flood Control Act of 1944 
P.L. 93-251 
P.L. 93-251 
S. Doc. 9, 81st Cong., 1st Sess. 
Sec. 4, Flood Control Act of 1944 
H. Doc. 693, 79th Cong., 2d Sess. 
P.L. 858, 80th Cong., 2d Sess. 
P.L. 469, 82d Cong., 2d sess. 
Sec. 4, Flood Control Act of 1944 
P.L. 94-587 
P.L. 95-26 
LIBBY DAM - LAKE KOOCANUSA, MT 
Multi-purpose dam and powerhouse, and reregulating H. Doc. 531, 81st Cong., 2d Sess. 
facilities. 
School facilities for education of dependents of construction P.L. 89-789 
personnel, Libby project. 
Airport facility at Kelley Flats, MT. P.L 90-2398 
Design standards for relocation of Montana State P.L. 90-4839 
Highway 37 to be those adopted by State of Montana 
pursuant to provisions of Highway Safety Act of 1966. 
- 38-23 - 
27. 
29. 
30. 
31. 
32. 
33. 
34. 
35.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 19, 1970 Participation with State of Montana in construction, P.L. 91-28210 
operation and maintenance of fish hatchery facilities. 
Dec. 31, 1970 Designation of lake formed by the waters impounded P.L. 91-625 
by Libby Dam as Lake Koocanusa. 
Dec. 31, 1970 Design and construction of sewage collection and P.L. 91-611 
sewage treatment facility as part of relocation of municipal 
facilities of Rexford, MT; and compensation for railroad 
employees suffering long-term economic injury through 
reduction of income as result of the relocation of rail 
transportation facilities due to the construction of Libby Dam. 
Mar. 7, 1974 Phase I design memorandum stage for installation S. Doc. 29, 93d Cong., 1st Sess., 
of power generating facilities at Libby Reregulating Dam. P.L. 93-251 
Mar. 7, 1974 Construction of fish production measures to P.L. 93-251 
compensate for fish losses attributed to the project, and for 
acquisition of necessary real estate, construction of access 
roads and utilities (amends P.L. 91-282 by increasing 
limitation from $750,000 to $4,000,000). 
Mar. 7, 1974 Acquisition of land (not to exceed $2,000,000) for P.L. 93-251 
prevention of wildlife grazing losses caused by the project. 
Mar. 7, 1974 Reimbursement (not to exceed $350,000) to Boundary P.L. 93-251 
County, ID, for reconstruction of Deep Creek Bridge made 
necessary by duration of high flows during drawdown 
operations at Libby Dam. 
Mar. 7, 1974 Compensation (not to exceed $1,500,000) to Drainage P.L. 93-251 
Districts and owners of leveed and unleveed lands in 
Kootenai Flats, Boundary County, ID, for damages caused 
by duration of higher flows during drawdown operations at 
Libby Dam. 
1. Deferred. 
2. Inactive. 
3. A portion deferred. 
4. Permanent Appropriations Repeal Act. 
5. Included in Public Works Administration program. 
6. Maintenance of these items, as well as sandspit north of James 
Island, is included in this modification. 
7. Included in Emergency Relief program, May 28, 1935. 
8. Supplemental Appropriations Act of 1968, Section 502. 
9. Flood Control Act of 1968, Section 212. 
10. River Basin Monetary Authorization and Miscellaneous Civil 
Works Amendments Act of 1970, Section 7. 
38-24

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
PROJECT Status Report for Construction Maintenance 
Anacortes Navigation Channel, WA 1 Completed 1977 825,263 6 -- 
Bellingham Harbor, WA (I&J Street Waterway)1 Completed 1966 125,634 7 -- 
Blaine Harbor, WA Completed 1958 346,650 8 -- 
Columbia River, Wenatchee to Kettle Falls, WA Completed 1923 274,391 7,693 
East Bay Small Boat Basin, Olympia, WA1 Completed 1985 1,619,956 -- 
Edmonds Harbor, WA2 Completed 1987 -- 224,756 
Flathead River, MT Completed 1901 9,811 -- 
Hammersley Inlet, WA Completed 1950 9,000 10,683 
Hoquiam River, WA Completed 1950 18,92110 5,316 
Kenmore Navigation Channel, WA1 Completed 1987 946,000 437,000 
Kingston Harbor, WA Completed 1967 262,57011 5,00012 
Kootenai River, ID and MT Completed 1933 9,255 5,643 
Mats Mats Bay, WA1 Completed 1970 137,67913 -- 
Neah Bay, WA Completed 1982 2,057,266 1,854,058 
Okanogan and Pend Oreille Rivers, WA Abandoned 1913 63,879 7,634 
Poison Bay, Flathead Lake, MT Completed 1918 4,491 259 
Port Angeles Harbor, WA3 Completed 1960 470,873 -- 
Port Gamble Harbor, WA Completed 1953 11,91114 13,337 
Port Orchard Bay, WA4 Completed 1928 42,804 -- 
Port Townsend, WA Completed 1987 480,89915 78,787 
Prototype Breakwater Test Program, WA1 Completed 1985 1,461,590 -- 
Shilshole Bay, Seattle, WA Completed 1962 2,575,09118 -- 
Skagit River, WA Completed 1950 99,83016 38,75817 
Squalicum Small Boat Harbor, Bellingham, WA1 5 Completed 1981 1,744,02518 -- 
Tacoma Harbor, WA Completed 1987 2,383,89119 1,390,74520 
Waterway Connecting Port Townsend 
and Oak Bay, WA Completed 1987 73,322 378,378 
Westhaven Cove Small Boat Basin, WA 1 Completed 1981 2,000,00021 -- 
1. Authorized by Chief of Engineers under authority of Section 
107, Public Law 86-645. 
2. Constructed by local interests at a cost of $415,000. Excludes 
$1,000 Coast Guard funds expended for new work. Corps of 
Engineers is responsible for maintenance. 
3. Maintenance by Port of Port Angeles. 
4. No maintenance required. 
5. Displayed as Bellingham, Squalicum Small Boat Harbor, WA in 
last report. 
6. Excludes $457,200 contributed funds expended. 
7. Excludes $2,500 Coast Guard funds expended. 
8. Includes $8,005 appropriated and expended for previous project. 
9. Excludes $2,184,766 contributed funds expended. 
10. Excludes $32,373 Emergency Relief funds expended. 
11. Excludes $390,753 contributed funds and $3,000 Coast Guard 
funds expended. 
12. Mitigation of shore damages study. 
13. Excludes $28,288 contributed funds and $9,000 Coast Guard 
funds expended. 
14. Excludes $21,260 contributed funds expended. 
15. Excludes $92,423 contributed funds expended. 
16. Excludes $15,000 Coast Guard funds expended. 
17. Includes $2,500 appropriated and expended for previous 
project. 
18. Excludes $1,570,886 contributed funds expended. 
19. Includes $159,585 appropriated and expended for previous 
project. Excludes $1,147,208 contributed funds and $51,609 Public 
Works Administration funds expended. 
20. Includes $5,347 appropriated and expended for previous 
project. Excludes $222,500 contributed funds expended. 
21. Excludes $1,230,035 contributed funds expended. 
- 38-25 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30. 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
American Lake, Vicinity of Fort Lewis, WA1 Completed 1957 59,582 8 -- 
Bear Creek, Flathead CountyBridge, near Essex, MT2 Completed 1971 1,424 -- 
Blackfoot River, Matt Little Road, MT2 Completed 1964 17,836 -- 
Bogachiel River, Highway 101, near Forks, WA2 Completed 1981 156,000 -- 
Bogachiel River, Undie Road, Forks, WA2 Completed 1981 57,000 -- 
Cedar River, King County, WA3 Completed 1953 3,229 -- 
Cedar River, Renton, WA2 Completed 1949 32,264 -- 
Chehalis River, City of ChehalisRaw Water 
Pumphouse, WA2 Completed 1966 35,454 -- 
Chehalis River, Independence Road, 
Thurston County, WA2 Completed 1965 47,916 -- 
Chehalis River, Montesano, WA2 Completed 1977 140,080 -- 
Clallam Bay, Sekiu, WA2 Completed 1977 48,698 -- 
Clallam River, Highway 112, WA2 Completed 1981 43,500 -- 
Clark Fork River, Drummond, MT2 Completed 1978 18,660 -- 
Clark Fork River, Missoula, MT2 Completed 1978 31,548 -- 
Clark Fork River, Superior, MT2 Completed 1971 28,356 -- 
Clark Fork River, Vicinity of Plains, MT2 Completed 1950 27,947 -- 
Clearwater River, Jefferson County Road, WA2 Completed 1968 50,000 7-- 
Clearwater River, Queets River Bridge, WA2 Completed 1950 49,165 -- 
Coeur d'Alene, Spokane River, ID Completed 1941 152,872 -- 
Coeur d'Alene River, Springston, ID2 Completed 1950 25,452 -- 
Coffee Creek, WA 3 Completed 1966 15,000 -- 
Columbia River Basin, Local Protection Projects, 
ID, MT, and WA: 
Clark Fork River, Missoula, MT Completed 1983 384,862 8 -- 
Lightning Creek, Clark Fork, ID Completed 1959 42,726 -- 
Deschutes River, Gleason Road Bridge 
near Tumwater, WA2 Completed 1965 26,292 -- 
Deschutes River, Rich Road Bridge, 
near East Olympia, WA2 Completed 1967 22,956 -- 
Dungeness River, Area #5, WA2 Completed 1950 2,155 9 -- 
Dungeness River, Area #8, WA2 Completed 1950 2,895 -- 
Dungeness River, Clallam County, WA1 Completed 1964 52,04010 -- 
Dungeness River, Sequim, WA2 Completed 1981 99,000 -- 
Dungeness River, Clallam County, WA2 Completed 1986 47,500 -- 
Dungeness River, Taylor Cut-off Road, WA2 Completed 1961 14,093" -- 
Elwha River, Clallam County, WA2 Completed 1951 17,303 
Entiat River, WA3 Completed 1971 49,300 -- 
Entiat River, Chelan County, WA2 Completed 1978 38,000 -- 
Flathead River, MT2 Completed 1972 20,940 -- 
Flathead River, Bradley Channel Area, MT2 Completed 1955 26,265 -- 
Flathead River, near Kalispell, MT2 Completed 1948 33,347 -- 
Flathead River, near Kalispell, MT Deferred 1981 300,00012 -- 
Flathead River, Old Steel Bridge, near Kalispell, MT2 Completed 1964 13,438 -- 
Flower and Parmenter Creeks, MT 3 Completed 1950 2,320 
Foster Creek Road, Douglas County, WA2 Completed 1962 50,000 -- 
Green River between Kent and Auburn, WA 
and Allentown, WA2 Completed 1972 24,605 -- 
Green River, State Highway 181, WA2 Completed 1976 27,001 -- 
Henderson Bay, Purdy, WA2 Completed 1977 37,359 -- 
Hoh River, County Road 216, WA2 Completed 1980 143,000 -- 
Hoh River, U.S. Highway 101, WA2 Completed 1980 194,000 -- 
Hoh River Road, Jefferson County, WA (HO 1360)2 Completed 1956 22,082'3 -- 
Hoh River Road, Jefferson County, WA (HO 1361)2 Completed 1961 11,916 -- 
Hoh River Road, Jefferson County, WA (HO 1362)2 Completed 1964 41,622 -- 
Hoh River, near Forks, WA2 Completed 1983 173,000'14 -- 
38-26

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Hoko River, Sekiu, WA2 Completed 1977 21,083 -- 
Hood Canal, Hoodsport, WA2 Completed 1977 59,812 -- 
Hoquiam River, WA2 Completed 1977 52,600 -- 
Jackman Creek, Skagit River, WA 3 Completed 1962 24,000 -- 
Kootenai River, Bonners Ferry, ID2 Completed 1950 42,325 -- 
Kootenai River, Kootenai Flats Area, District #1, ID2 Completed 1965 14,885 -- 
La Conner, Swinomish Channel, WA2 Completed 1979 40,525 -- 
Methow River, WA (MET 1-74)2 Completed 1974 15,700 -- 
Methow River, WA (MET 2-74)2 Completed 1974 11,200 -- 
Methow River, WA (MET 3-74)2 Completed 1974 13,450 -- 
Methow River, Barclay Canal, WA2 Completed 1976 19,810 -- 
Methow River, State Highway No. 16 Bridge, 
Twisp, WA2 Completed 1949 31,783 -- 
Methow River, Twisp-Carlton Highway, 
Vicinity of Twisp, WA2 Completed 1951 33,30016 -- 
Methow River, Vicinity of Pateros, WA2 Completed 1951 11,7261' -- 
Middle Fork Nooksack River, Deming, WA2 Completed 1986 79,000 -- 
Mineral Creek, Lewis County, WA2 Completed 1972 11,836 -- 
Moclips River, Moclips, WA2 Completed 1977 17,608 -- 
Naches River, Naches, WA2 Completed 1982 59,000 -- 
Newaukum River, Lewis County, Hamilton, WA2 Completed 1972 24,792 -- 
Nisqually River, near Elbe, WA2 Completed 1948 37,636 -- 
Nisqually River, Thurston County, WA2 Completed 1960 26,790 -- 
Nisqually River, Vicinity of Elbe, WA2 Completed 1952 19,345 -- 
Nooksack River, WA 3 Completed 1948 24,006 -- 
Nooksack River, Acme, WA2 Completed 1985 77,300 -- 
Nooksack River, Guide Bridge Location, WA2 Completed 1950 6,07517 -- 
Nooksack River, above Highway 1Z Bridge, WA2 Completed 1960 10,807 -- 
North Fork Skykomish River, WA2 Completed 1981 222,500 -- 
Okanogan River, WA2 Completed 1974 10,100 -- 
Okanogan River at Outlet of Osoyoos Lake, WA3 Completed 1949 52,100 -- 
Okanogan River, Tonasket Creek and 
Osoyoo Lake, WA3 Completed 1953 7,987 -- 
Okanogan River, Omak, WA1 Completed 1981 2,231,030 -- 
Okanogan River, Oroville, WA1 Completed 1982 1,787,630 -- 
Pilchuck River, WA3 Completed 1948 25,401 -- 
Pilchuck River, WA2 Completed 1985 81,000 -- 
Pilchuck River, WA2 Completed 1971 10,713 -- 
Pilchuck River, Everett, WA2 Completed 1980 54,000 -- 
Pilchuck River, State Highway 92, Granite Falls, WA2 Completed 1971 30,973 -- 
Placer Creek, ID Completed 1986 5,865,000 -- 
Powell County High School, Deer Lodge, MT2 Completed 1964 11,291 -- 
Pysht River, Sekiu, WA2 Completed 1977 86,160 -- 
Queets River, Jefferson County Sewage Lagoon, WA2 Completed 1981 125,000 -- 
Quillayute River, Quileute Tribal Float 
and Bridge, WA2 Completed 1972 39,300 -- 
Quinalt River, Grays Harbor, WA2 Completed 1981 208,000 -- 
Quinalt River Road, Jefferson County, WA2 Completed 1961 15,9281" -- 
Rock Creek, Granite County, MT2 Completed 1974 49,657 -- 
Rock Creek, Missoula County, MT2 Completed 1973 31,565 -- 
Rock Creek Road, MT2 Completed 1980 50,000 -- 
Rye Creek, MT2 Completed 1973 22,819 -- 
St. Maries, St. Joe River, ID Completed 1942 357,698 -- 
St. Regis River, MT 3 Completed 1942 7,234 ' -- 
St. Regis River at St. Regis, MT 3 Completed 1951 2,983 -- 
Sammamish River, WA Completed 1967 2,582,53620 -- 
Sauk River, WA2 Completed 1974 20,860 -- 
- 38-27 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Sewage Treatment Plant, Missoula, MT2 
Shelton Creek, WA1 
Skagit River, WA (Avon Bypass) 
Skagit River, WA (Levee and Channel Improvements) 
Skagit River at Burlington Bend, WA2 
Skagit River, Cape Horn Road, WA2 
Skagit River, Deadman's Slough, WA2 
Skagit River, Pressentin Creek, WA2 
Skagit River, South Skagit Highway, WA2 
Skagit River, South Skagit Highway, WA (Job 66-1)2 
Skagit River, South Skagit Highway, WA (Job 67-1)2 
Snohomish River, Lowell-Snohomish River 
Road, WA2 
Snohomish River, Snohomish, WA2 
Snoqualmie River, West Snoqualmie, WA2 
Soleduck River Bridge, WA2 
Soleduck River, near Mora Road Bridge, WA2 
Startup, Skykomish and Wallace Rivers, WA 1 
Stillaguamish River, South Fork, Mountain 
Loop Highway, near Robe, WA2 
Stillwater River, MT2 
Stillwater and Whitefish Rivers, MT2 
Strong Creek, Hope, ID 2 
Taholah, WA2 
Upper Puyallup River, WA4 
Wenatchee Canyons 1 and 2, WA5 
West Fork Foster Creek, WA2 
Willapa River at Raymond, WA 
Wynoochee River, County Road 141, WA2 
Wynoochee River, near Montesano, WA2 
Wynoochee River, near Montesano, WA (WR-1-72)2 
Yakima, Yakima River, WA 
Yakima River, Cle Elum, WA2 
Yakima River, below mouth of Teanaway River, 
near Cle Elum, WA2 
Yakima River, West Richland, WA2 
Yakima River, Yakima WA2 
1. Authorized by Chief of Engineers under authority of Section 
205, Public Law 858, 80th Congress, as amended. 
2. Authorized by Chief of Engineers under authority of Section 
14, Public Law 526, 79th Congress, as amended. 
3. Authorized by Chief of Engineers under authority of Section 2, 
Public Law 406, 75th Congress, as amended. 
4. Authorized by Works Progress Administration Project No. OP 
65-93-917. 
5. Authorized by Secretary of Army under authority of Section 
201, Public Law 298, 89th congress, H. Doc. 91-370. 
6. Excludes $10,000 contributed funds expended. 
7. Excludes $24,728 contributed funds expended. 
8. Includes $7,850 appropriated and expended for recreation 
facilities at completed project (Code 710). Excludes $13,500 
contributed funds expended. 
9. Excludes $2,154 contributed funds expended. 
10. Excludes $340,066 Public Works Acceleration Act funds 
expended. 
11. Excludes $3,314 contributed funds expended. 
12. Preconstruction planning only. 
13. Excludes $21,807 contributed funds expended. 
14. Excludes $189,000 Federal Highway Administration funds 
expended. 
15. Excludes $6,786 contributed funds expended. 
16. Excludes $11,726 contributed funds expended. 
17 Excludes $6,075 contributed funds expended. 
18. Excludes $4,843 contributed funds expended. 
19. Excludes amount expended by Works Progress Administration 
which is not available. 
20. Excludes $696,923 contributed funds and $1,000 Coast Guard 
funds expended. 
21. Excludes $5,339 contributed funds expended. 
22. Excludes $24,488 contributed funds expended. 
23. Excludes $14,307 contributed funds expended. 
24. Excludes $1,960 contributed funds expended. 
25. Excludes $46,182 contributed funds expended. 
26. Emergency Relief funds, Works Progress Administration. 
Excludes $13,704 contributed funds expended. 
27. Includes $8,888 expended for restudy, FY 1967- 1972. 
28. Excludes $21,311 contributed funds expended. 
29. Excludes $17,988 Office of Emergency Preparedness funds 
expended. 
38-28 
Completed 
Completed 
Deferred 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1965 
1979 
1968 
1982 
1949 
1966 
1980 
1980 
1963 
1966 
1967 
1969 
1970 
1977 
1961 
1963 
1970 
1964 
1973 
1977 
1970 
1979 
1938 
1977 
1958 
1982 
1976 
1969 
1972 
1948 
1949 
1947 
1977 
1983 
50,00021 
872,021 
54,46812 
1,934,792 
50,000 
46,489 
93,000 
137,000 
40,753 
17,719 
50,00022 
44,227 
60,90023 
15,565 
16,43624 
11,433 
271,713 
50,00025 
17,457 
34,513 
8,442 
223,893 
71,49526 
544,331 
19,513 
508,13027 
111,072 
50,00028 
50,00029 
381,961 
8,047 
48,272 
36,768 
125,500

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-F OTHER AUTHORIZED MULTIPLE PURPOSE PROJECTS, 
INCLUDING POWER 
For Last Cost to Sep,. 30, 1989 
Full Report Operation 
See Annual and 
Project Report for Construction Maintenance 
Priest Rapids Dam, Columbia River, WA 1954 350,0001 
1. For partnership planning. Excludes funds expended for acquisition Wanapum Dams, in accordance with Public Law 544, 83d Congress. 
of lands under partnership arrangement for Priest Rapids and Project constructed by Grant County Public Utility District. 
TABLE 38-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Calispell Creek, WA 1 1968 1968 $25,000 6 
Columbia River Basin, Local Protection Projects, 
ID, MT, and WA: 
Crab and Wilson Creeks, WA 2 1958 1964 $ 9,000 8 -- 
Entiat River, WA 3 1958 1986 -- -- 
Methow River, WA 3 1958 1986 -- -- 
Okanagon River, WA 3 1958 1986 1,100 B -- 
St. Regis River, MT 4 1958 1978 1,400 6 -- 
Wenatchee River, WA 4 1958 1978 -- -- 
Yakima River at Ellensburg, WA 3 1980 1986 44,300 7 -- 
Hammersley Inlet, WA (Uncompleted Portion) ' 1950 1978 -- -- 
Hoquiam, Aberdeen, and Cosmopolis, Chehalis River, WA 5 1948 1952 83,631 8 -- 
Port Angeles Harbor, WA (Uncompleted Portion) 4 1960 1977 -- -- 
Port Gamble Harbor, WA (Uncompleted Portion) 4 1953 1977 -- -- 
Quillayute River, WA (Uncompleted Portion) 3 1986 1986 -- -- 
Seattle Harbor, WA (Uncompleted Portion) 3 1986 1986 -- -- 
Skagit River, WA (Uncompleted Portion) 4 1950 1978 -- -- 
Spokane River, Spokane, WA 3 1939 1986 2,9448 -- 
Stillaguamish River, WA 3 1946 1986 4,234 * -- 
1. Authority for project expired October 27,1968. March 7, 1974. 
2. Authority for project expired in July 1964. 5. Authority for project expired in October 1952. 
3. Deauthorized under authority of Section 1002, P.L. 99-662 dated 6. Preconstruction planning only. 
November 17, 1986. 7. Includes $14,300 expended for restudy, FY 1970. 
4. Deauthorized under authority of Section 12, P.L 93-251 dated 8. Economic study only. 
TABLE 38-H LAKE WASHINGTON SHIP CANAL, WA 
PRINCIPAL FEATURES OF DOUBLE LOCK AND DAM 
(SEE SECTION 8) 
Section Large Lock Small Lock 
Miles above mouth 11/4 11/4 
Clear width of chamber Feet 80 28 
Maximum available length Feet 760 123 
Lift Feet 26 26 
Depth on upper miter silli Feet 331/2 16 
Depth on intermediate miter sill2 Feet 29 -- 
Depth on lower miter sill2 Feet 29 16 
Character of foundation Clay Clay 
Kind of dam Fixed dam with Fixed dam with 
gated spillway. gated spillway. 
Type of construction Concrete Concrete 
Year completed 1916 1916 
Cost 3 3 
1. Low water in upper pool. 
2. Mean lower low water in Puget Sound. 
3. Cost of double lock and dam was $2,382,200 and the emergency 
gates, completed in 1923, $262,300. 
- 38-29 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACITVITIES FOR FY 1989 
TABLE 38-I PROJECT CONDITION SURVEYS 
(SEE SECTION 11) 
Name of Project Date Survey Conducted 
Washington: 
Anacortes Harbor, WA July 1989 
Bellingham Harbor, WA July 1989 
Port Townsend, WA November 1988 
Seattle Harbor, WA October 1988 
Water connecting Port Townsend and Oak Bay, WA July 1989 
TABLE 38-J FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, 
PUBLIC LAW 858, 80TH CONGRESS, AS AMENDED 
(PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1989) 
Cedar River, WA 164,719 ' 
Chehalis River, Salzer Creek, Wa 49,577 
China Creek, Centralia, WA' 132 
Clear & Clarks Creeks, Pierce County, WA2 36 
Lower Green River, King County, WA 15,462 
Newaukum River, WA 5,634 
Okanogan River, WA 35,789 
Snohomish River, Ebey Island, WA 33,434 
Snoqualmie River, WA 16,911 
Stillaguamish River, Snohomish County, WA 31,892 
Sultan, WA 35,094 
TOTAL $388,680 
1. Unfavorable report. 
2. Terminated. 
3. Excludes $78,428 contributed funds expended. 
38-30

WALLA WALLA, WA, DISTRICT * 
This District consists of all Columbia River drainage and 
tributaries thereto between the head of the McNary pool 
(River Mile 345.4) and the Umatilla Bridge (River Mile 
290.5) below McNary Dam, except the Yakima River Basin 
above the Van Giesen Street Bridge (River Mile 8.4) near 
Richland, WA. 
IMPROVEMENTS 
Navigation 
1. Navigation Work Under Special Authorization . 39-1 
Flood Control 
2. Columbia River Basin, Local Flood Protection 
Projects ................................ 39-1 
3. Catherine Creek, OR ..................... 39-2 
4. Clear & Burnt River, OR ................... 39-2 
5. Colfax, Palouse River, WA ................. 39-2 
6. Flood Control Work Under Special Authorization39-2 
7. Inspection of Completed Flood Control Projects 39-2 
8. Inspection of Completed PL-99 Works ....... 39-2 
9. Jackson Hole, WY ........................ 39-3 
10. Lucky Peak Lake, ID ....................... 39-3 
11. Mill Creek Lake, WA .................. ... 39-3 
12. Owyhee River, OR ........................ 39-4 
13. Scheduling Flood Control Reservoir Operations 39-4 
Multiple-Purpose Projects, Including Power 
14. Columbia River Juvenile Fish 
Mitigation Program ........................ 39-4 
15. Dworshak Dam and Reservoir, ID ............ 39-4 
16. Ice Harbor Lock and Dam - 
Lake Sacajawea, WA ....................... 39-5 
17. Lewiston-Clarkston Bridge, ID and WA ...... 39-5 
18. Little Goose Lock and Dam -- Lake Bryan, WA 39-6 
19. Lower Granite Lock and Dam, WA .......... 39-6 
20. Lower Monumental Lock and Dam - 
Lake Herbert G. West,WA ................. 39-7 
21. Lower Snake River Fish & Wildlife Compensation 
Plan, WA,OR, ID ........................ 39-7 
22. McNary Lock and Dam - Lake Wallula, 
OR and WA ............................ 39-7 
23. Snake River Downstream from Johnson Bar 
Landing, OR, WA and ID ................. 39-8 
General Investigations 
24. Surveys .................................. 
25. Collection and Study of Basic Data ........... 
26. Preconstruction, Engineering and Design ...... 
Tables 
Tables 39-A 
Tables 39-B 
Tables 39-C 
Tables 39-D 
Tables 39-E 
Tables 39-F 
Tables 39-G 
Tables 39-H 
Tables 39-I 
Tables 39-J 
Tables 39-K 
39-8 
39-9 
39-9 
Cost & Financial Statement ....... 39-10 
Authorizing Legislation ........... 39-12 
Other Authorized Navigation Projects 39-15 
Not Applicable 
Other Authorized Flood Control 
Projects ........................ 39-15 
Not Applicable 
Deauthorized Projects ............ 39-16 
Columbia River Basin, Local Flood 
Control Projects ............... 39-17 
Inspection of Completed Flood 
Control Projects ................ 39-17 
Principal Data Concerning Navigation 
Lock, Spillway Dam, Powerplant and 
Impoundment .................. 39-18 
Snake River Downstream from Johnson 
Bar Landing, OR, WA, and ID .... 39-22 
Flood Control 
1. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public Law 
86-645 (preauthorization). No costs in Fiscal Year 1989. 
2. COLUMBIA RIVER BASIN, LOCAL 
FLOOD PROTECTION PROJECTS. 
Location. Improvements included in this project are along 
Columbia River and its tributaries. 
Existing project. Flood Control Act of 1950 approved a 
general comprehensive plan for Columbia River Basin for 
-39-1- 
Navigation

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
flood control and other purposes based on plans in H. Doc. 
531, 81st Cong., 2d Sess., and authorized $75 million to be appropriated 
for partial accomplishment of certain projects. Of 
that authorization, an amount not to exceed $15 million was 
allotted for construction of local flood protection works 
throughout Columbia River Basin, subject to conditions that 
all work undertaken pursuant to authorization would be economically 
justified prior to construction, and local cooperation 
specified in 1936 Flood Control Act, as amended, should 
be required. (See Tables 39-B and 39-H for projects in Walla 
Walla District.) 
Local cooperation. Section 3, Flood Control Act of June 22, 
1936, applies. 
Operations during fiscal year. No projects were recommended 
for deauthorization during Fiscal Year 1989. 
3. CATHERINE CREEK, OR 
Location. Catherine Creek is a tributary to the Grande 
Ronde River located 8 miles east of the city of La Grande, 
Union County, Or. 
Existing project. Organic debris such as fallen trees, brush, 
and a select number of large cottonwood trees were removed 
from the creek to increase its capacity to convey future floods. 
The work was funded under authority of Section 208 of the 
Flood Control Act of 1954. 
Local cooperation. The Catherine Creek Corridor Improvement 
District sponsored the project and complied with 
requirements set forth in Section 3 of the Flood Control Act 
of 1936 plus additional requirements set forth in the project 
document. 
Operations during fiscal year. None. 
4. CLEAR & BURNT RIVER, OR 
Location. At the city of Huntington waste water lagoon, 
Malheur County, Oregon. 
Existing project. Place 800 feet of riprap along three cells 
of the lagoon system under authority of Section 14 of the 1946 
Flood Control Act. 
Local cooperation. City of Huntington sponsored the project 
and agreed to sponsorship requirements. 
Operations during fiscal year. None. 
5. COLFAX, PALOUSE RIVER, WA 
Location. On the main stem North and South Forks of the 
Palouse River and includes a portion of Spring Flat Creek, a 
tributary stream, all within the city of Colfax, WA. 
Existing project. Project consists of 3,740 feet of concretelined 
channel, 4,910 feet of revetted channel, and 2,330 feet 
of unrevetted channel and drainage structures. Authorization 
was provided under PL 78-534, Section 10, Flood Control 
Act of 1944. 
Local cooperation. The city of Colfax has provided the necessary 
right of way and other sponsorship requirements. 
Operations during fiscal year. None. 
6. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public Law 
858, 80th Congress, as amended. 
Fiscal year costs were $139,112 which included $121,193 
for feasibility studies and plans and specifications on the Malheur 
Lake project, OR and preauthorization studies of $78 
for the Oakley Westside Channel, ID; $6,395 for the 
groundwater study at Ririe, ID; and $11,446 for the Salmon 
River study at Salmon, ID. 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and antecedent 
legislation). 
Federal costs for fiscal year were $228,942 for disaster preparedness, 
and $271,747 for rehabilitation. 
Emergency Bank Protection (Section 14, 1946 Flood Control 
Act, Public Law 526, 79th Congress). 
Fiscal year costs were $2,116 for preauthorization studies 
for the Walla Walla River, Umatilla County, OR. 
Snagging and clearing of navigable streams and tributaries 
in interest of flood control (Section 208, 1954 Flood Control 
Act, Public Law 780, 83rd Congress). 
Fiscal year costs were $34,507 for preauthorization studies 
which included $5,161 Boise River, Canyon and Ada Counties, 
ID; $9,447 Malheur River, Vale, OR; $4,143 Palouse 
River, Colfax, WA; $6,464 Salmon River, Lemhi County, ID; 
$6,395 South Fork Boise River, Elmore County, ID; $1,906 
Esquatzel Coulee Connell, WA; and $991 Prairie Creek Enterprise, 
OR. 
7. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Federal law requires local interests to maintain and operate 
completed local protection projects in accordance with 
regulations prescribed by Secretary of Army. Inspections 
were made to determine extent of compliance and to advise 
local interests as necessary of measures required to correct 
deficiencies. Geological and seismological investigations at 
Ririe Dam are complete and the Waterways Experiment Station 
(WES) is finalizing all data and findings. The report and 
final recommendations will be distributed in FY 90. See Table 
39-I for inspections made during fiscal year. 
Fiscal year costs were $372,100. Total costs to September 
30, 1989 have been $2,474,974. 
8. INSPECTION OF COMPLETED PL-99 
WORKS 
Inspections are pursuant to Public Law 84-99 which directs 
the Corps to establish through inspection whether non- Federal 
flood control works will continue to provide the intended 
degree of flood protection and to determine if the maintenance 
program is adequate. FY 1989 costs for this program 
were $2,681. FY 1989 is the last year for expenditures on this 
- 39-2 -

WALLA WALLA, WASHINGTON DISTRICT 
program. The program will be carried under the Flood Control 
and Coastal Emergencies appropriations. 
9. JACKSON HOLE, WY 
Location. On both banks of the Snake River, Teton 
County, west of Jackson, Wyoming. 
Existing project. 23.5 miles of levees consisting of: Right 
bank - a levee with full riprap protection from 10 miles upstream 
of the Jackson-Wilson Highway Bridge, to 3.5 miles 
below, a total of 13.5 miles. Left bank - a levee with full 
riprap protection extending from 10 miles upstream of Jackson-
Wilson Highway Bridge to 5 miles upstream and tending 
1.5 miles immediately upstream from the same bridge to 3.5 
miles below the bridge, for a 10-mile total length. 
Project authorized by Public Law 516, Flood Control Act of 
1950 for flood control protection by channel improvements 
consisting of channel rectification, levees, and revetment 
along Snake River in the vicinity of Wilson, Wyoming. Public 
Law 99-662 modified the original Public Law 516 to provide 
that the operation, maintenance, modifications, and additions 
to the project become Federal responsibility. 
Local cooperation. Non-Federal sponsors shall pay the initial 
$35,000 in cash or materials of any such costs expended in 
any one year, plus inflation as of the date of enactment of the 
Water Resources Development Act of 1986.. 
Operations during fiscal year. An EIS scoping meeting was 
held to determine the physical, economic, and enironmental 
factors associated with operation and maintenance of the levees. 
The Fish and Wildlife Service provided a draft Coordination 
Act Report. A draft EIS was prepared. A Special Report 
was prepared for economic justification of Federal O&M of 
the levees. The O&M Decision Document was initiated. An 
In-Progress-Review was held on 4 May 1989 with Teton 
County Commissioners and Corps officials. 
10. LUCKY PEAK LAKE, ID 
Location. On Boise River in southwestern Idaho about 10 
miles southeast of city of Boise, ID. 
Existing project. The project includes a rolled-earthfill 
dam about 250 feet high above streambed and 1,700 feet long 
at crest, with a lake providing a total storage at upper operating 
lake level of 306,000 acre-feet. Project provides for flood 
control, irrigation, and recreation. (For details, see page 2000 
of Annual Report for 1962.) 
Construction of existing project was initiated November 
1949 and completed June 1961. Since 1961, $132,839,000 in 
potential flood damages have been prevented by the project. 
During the detailed investigation of outlet capacity and the 
potential for adding hydropower to the existing project, a 
need for an auxiliary outlet became apparent. Construction 
of an auxiliary outlet was authorized in the Water Resource 
Development Act of 1976. In FY 1978, an "Interim Feasibility 
Report on Modification of Lucky Peak Dam and Lake" 
(power facilities) was submitted to the Board of Engineers for 
Rivers and Harbors and approved. States, agencies, and the 
Chief of Engineers have commented on the report to the Secretary 
of the Army. The report was forwarded to the Office of 
Management and Budget in February 1982. 
A license to construct and operate power facilities at the 
project was issued by the Federal Energy Regulatory Commission 
(Project #2832) to the Boise Project Board of Control 
on June 10, 1980 and modified on October 9, 1980 and 1982. 
Construction of the auxiliary outlet facility began in May 1984 
and was completed in August 1986. Construction of modifications 
to the existing outlet tunnel and powerhouse excavation 
began in August 1986 and was completed January 1987. Powerhouse 
general contract construction began in April 1986. 
The project was completed and dedicated on October 7, 
1988. Power on line for all units was August 18, 1988. 
Local cooperation. None Required. 
Operations during fiscal year. Maintenance: Contract 
awarded to purchase intake bulkhead. Operation and Maintenance: 
Normal operation and maintenance continued, 
which included the dam structures and recreation areas. 
11. MILL CREEK LAKE, WA 
Location. In and upstream from Walla Walla, WA, on Mill 
Creek, a tributary of Walla Walla River. 
Existing project. The project includes an off-stream 
earthfill storage dam about 125 feet high above streambed 
and 3,200 feet long at the crest, two concrete-lined outlet 
channels, an earthfill diversion dam, and division structures. 
Project provides for flood control and recreation. Authorizing 
legislation to provide a channel through the City of Walla 
Walla was added to the project in 1941. Recreation was 
added to the project purposes through the Federal Water 
Project Recreation Act of 1965. 
Construction of the dam and appurtenant works was completed 
in 1942. Paving of the channel through City of Walla 
Walla was completed in 1948. Recreation facilities were completed 
in 1966. (For details, see page 2005 of Annual Report 
of 1962.) Since 1942, $7,518,000 in potential flood damages 
have been prevented by the combined storage and channel 
operation. 
The rehabilitation of the existing project was to correct the 
seepage and internal erosion by constructing a cutoff wall. 
The construction of the cutoff wall did not alleviate the seepage 
problem, thus requiring limited flood control use of the 
project. The seepage and internal erosion create ahigh vulnerability 
for dam failure. During FY 89, the reservoir was 
drained and will be filled only for flood control use. 
Local cooperation. Fully complied with. (For details, see 
page 2006 of Annual Report of 1962.) 
Operations during fiscal year. Maintenance: A contract 
was awarded for construction of sanitary facilities at Rooks 
Park. Operation and Maintenance: Normal operation and 
maintenance continued, which included regulation of water 
control structures and care of recreation areas. 
- 39-3 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
12. OWYHEE RIVER, OR 
Location. The lower 12 miles of the Owyhee River from the 
junction with the Snake River, upstream 23 miles to the 
Owyhee River diversion dam, Malheur County, OR. 
Existing project. Remove organicdebris and gravels from 
the lower 12 miles of the Owyhee River under the authority 
of Section 208 of the 1954 Flood Control Act. 
Local cooperation. The Owyhee River Water Control District 
sponsored the project and agreed to sponsorship requirements. 
Operations during fiscal year. None. 
13. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Functional regulation of non-Corps projects was accomplished 
under several authorities. Regulation of Palisades, 
Little Wood, and Anderson Ranch Reservoirs in Idaho, and 
Bully Creek, Warm Springs, Agency Valley, and Mason Reservoirs 
in Oregon, was accomplished as authorized under 
Section 7, Flood Control Act of 1944, and coordinated with 
the Bureau of Reclamation. 
Flood control operations at Jackson Lake, Arrowrock Reservoir, 
and Lake Lowell were in accordance with formal 
agreements with the Bureau of Reclamation. Regulation of 
American Falls, Owyhee, Magic, Mackay, Cascade, and 
Deadwood Reservoirs, Idaho, for flood control was accomplished 
under informal agreements. Brownlee, Oxbow, and 
Hells Canyon Reservoirs provided flood control regulation in 
accordance with provisions of the Federal Power Commission 
license to Idaho Power Company. 
Fiscal year costs were $290,017. 
Multiple-Purpose Projects, Including Power 
14. COLUMBIA RIVER JUVENILE FISH 
MITIGATION PROGRAM 
Location. At Lower Monumental, Little Goose, and Lower 
Granite on the Snake River in the states of Idaho and Washington 
and McNary on the Columbia River in the states of 
Oregon and Washington. 
Existing project. Congress passed and the President signed 
the FY 89 Energy & Water Development Act (P.L. 100-371) 
which mandated the expenditure of $8.7 million in FY 88 and 
$9.6 million in FY 89 for the design, testing, and construction 
of fish bypass facilities. Funds for FY 88 and 89 were expended 
on a project by project basis. However,the mitigation 
program starting in FY 91 will be considered one project and 
funds will be appropriated and expended as such. The program 
will consist of juvenile fish mitigation facilities which includes 
construction of juvenile fish passage facilities and a detailed 
mitigation study to be prepared in cooperation with 
regional interest, for juvenile fish losses at Corps dams on the 
Columbia and Snake Rivers. Completion of the bypass and 
transportation facilities will significantly increase the survival 
of migrating downstream juvenile fish. The mitigation study 
will determine the overall scope of the fish mitigation facilities 
for these Columbia and Snake River dams. 
The plan of improvement includes the following facilities: 
(a) Lower Monumental - submerged traveling fish screens, 
gate raise modification, gantry crane, collection bypass facility, 
and holding and loading facility (b) Little Goose - gantry 
crane, gate raise modification, submerged traveling fish 
screens, and holding and loading facilities Phase I and II (c) 
Lower Granite - deflectors, two fish transport barges, gate 
raise modification, fish support facility, wet separator, barge 
moorage facility expansion, and gantry crane (d) McNary - 
prototype screens, submerged traveling fish screens, gantry 
crane modifications, transport holding and loading facility, 
gate raise modification, and extended screen rehab facility. 
The total estimated Federal project cost is $139,000,000. 
Ice Harbor bypass facilities were not authorized for construction 
under the Columbia River Juvenile Fish Mitigation 
Program. However in FY 88, 89 and 90, Congress authorized 
expenditures up to $400,000 to proceed with design of a bypass 
system. A two year mitigation analysis commencing in 
FY 91 will determine future facilities at this project. 
Local cooperation. None required. 
Operations during fiscal year. New Work: Contract work 
continued for construction of two fish transport barges and 
contracts awarded for fixed deflectors at Lower Granite and 
holding and loading facilities Phase I and II at Little Goose. 
Engineering and design continues at Ice Harbor, Lower 
Monumental, Little Goose, Lower Granite, and McNary for 
design of submerged traveling screens, gate raise modifications, 
gantry cranes, collection bypass facilities, holding and 
loading facilities, and moorage facilities expansion.The fish 
mitigation program is approximately 11 percent complete. 
15. DWORSHAK DAM AND RESERVOIR, ID 
Location. Dam is on North Fork Clearwater River 1.9 miles 
above its junction with Clearwater River, near Orofino, ID, 
and about 35 miles east of Lewiston, ID. 
Existing project. The project includes a dam, powerplant, 
and appurtenant facilities. Project provides for flood control, 
navigation, hydroelectric power generation, recreation, and 
area redevelopment. The reservoir has a normal operating 
range between Elevations 1600 and 1445 Mean Sea Level 
(MSL). The reservoir has a gross storage capacity of 
3,453,000 acre-feet, of which 2,000,000 acre-feet are effective 
for both local and regional flood control and for at-site 
and downstream power generation. In addition, the reservoir, 
extending 53 miles into rugged and relatively inaccessible 
timberland, provides important trans- portation savings in 
connection with movements of marketable logs. The reservoir 
is habitat for elk, deer, and other wildlife. Dam structure 
is about 3,300 feet long and about 717 feet high above 
streambed. Fish passage is not feasible due to the height of 
the dam. A hatchery has been built below the dam to assure 
continuance of anadromous fish runs. Powerhouse has two 
90,000 kilowatt and one 220,000 kilowatt generating units in 
operation for a capacity of 400,000 kilowatts. Provisions have 
been made for three additional 220,000 kilowatt generating 
- 39-4 -

WALLA WALLA, WASHINGTON DISTRICT 
units for an ultimate installed capacity of 1,060,000 kilowatts. 
A reconnaissance report justifying the feasibility and cost 
benefits for the addition of a 200,000 kilowatt fourth generating 
unit was completed in FY 1978. Environmental and economic 
studies on additional generating units have been curtailed 
due to public opposition. Units 4,5,6 are now classified 
inactive and are eligible for deauthorization procedures. 
Principal project data are set forth in Table 39-J. 
Construction of the project started in April 1963 and was 
completed in 1986. Since the project became operational in 
June 1972, it has prevented about $737,000 of potential flood 
damages. Power generation through September 1989 has 
been 28.94 billion kilowatt hours. 
Eighty mini-recreation sites have been established along 
the reservoir shoreline. Each site includes at least a picnic table, 
U.S. Forest Service-type fireplace, and chemical toilet. 
Some of the sites have several picnic tables. Dent Acres and 
Freeman Creek recreation sites are open to the public. Facilities 
consist of a boat launching ramp, boat docks, cartrailer 
parking, comfort stations, and fully-developed overnight 
camping. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
continue for powerplant control. Operation and Maintenance: 
Wildlife habitat browse continued on project lands to 
provide winter browse for elk and deer. During fiscal year 
1.89 billion kilowatt hours of electrical power were generated 
by the three generating units. 
Dworshak National Fish Hatchery (DNFH) operations 
continued to be impaired by IHN virus. Steelhead eggs were 
transferred to Kooskia and Hagerman National Fish Hatcheries 
(KNFH and HNFH). After devastating losses at DNFH, 
enough fingerlings were returned from KNFH to allow a release 
of 1,391,999 smolts in the spring. With 450,000 smolts 
returned from HNFH, the total mitigaton release in the 
spring of 1989 was 1,850,000 steelhead smolts 750,000 less 
than in 1988. The total weight released was 265,942 pounds 
compared with 434,521 in 1988. DNFH also released 
1,653,252 spring chinook salmon (95,930 pounds). For the 
fourth successive year, rainbow trout (245,380 at 23,200 
pounds) reared at HNFH were released in Dworshak Reservoir, 
about 1/4 of the mitigaton goal. For the 1990 release, 
over 6,000 adult steelhead were spawned at DNFH, producing 
over 12 million eggs. Again, 4.3 million eggs were distributed 
to KNFH and HNFH. For the first time, IHN was found 
at KNFH, and 85 percent of the steelhead being reared there 
were lost. However, without IHN at HNFH, 1.6 million fingerlings 
were returned to DNFH in later summer 1989. The 
projected release of survivors at all three hatcheries for 1990 
will be very near the mitigation goal of 2.3 million. Approximately 
1.8 million spring chinook were on hand in September 
1989 for an expected release of 1.7 million in 1990. With near 
record runs of steelhead over Lower Granite Dam, over 
14,000 adult steelhead were expected to return to the Clearwater 
River in the winter of 1989-1990. 
16. ICE HARBOR LOCK AND DAM -- LAKE 
SACAJAWEA, WA 
Location. On Snake River, 9.7 miles above river mouth at 
head of Lake Wallula (McNary Reservoir) and 12 miles east 
of Pasco, WA. 
Existing project. The project includes a dam, powerplant, 
navigation lock, two fish ladders, and appurtenant facilities. 
Project provides for navigation, hydroelectric power generation, 
recreation, and incidental irrigation, The reservoir has a 
normal operating range between Elevations 440 and 435 
Mean Sea Level (MSL). Lake Sacajawea extends upstream 
about 31.9 miles and provides slack water to Lower Monumental 
Lock and Dam. Dam structure is about 2,790 feet long 
and about 130 feet high above streambed. Fish passage facilities 
include two fish ladders. Powerhouse has three 90,000 
kilowatt units and three 111,000 kilowatt generating units in 
operation for a capacity of 603,000 kilowatts. Spillway dam is 
610 feet long and overflow crest at Elevation 391 MSL is surmounted 
by 10 radial gates, 50 feet wide and 51 feet high, 
which provides the capacity to pass a design flood of 850,000 
cubic feet per second. Deck is at Elevation 453 MSL and provides 
a service road and track for a gantry crane. Navigation 
lock is single-lift type with clear plan dimensions of 86 by 675 
feet and 15-foot minimum depth over the sills. A navigation 
channel 250 feet wide and 14 feet deep is provided from the 
mouth of the Snake River to the dam and from the dam to 
Lower Monumental Lock and Dam. Principal data are set 
forth in Table 39-J. 
Construction of the original project started in December 
1955 and was completed in 1971. Construction of the additional 
generating units was started in 1971 and completed in 
1981. Power generation through September 1989 has been 
62.15 billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
continue for powerplant control. Contract awarded for emergency 
repair of the navigation lock gates and associated machinery. 
Operation and Maintenance: During fiscal year 2.36 
billion kilowatt hours of electrical power were generated by 
the 6 generating units. Traffic through the navigation lock, 
consisting of grains, petroleum products, fertilizer, wood 
products, and miscellaneous cargo, amounted to 4,949,054 
tons during calendar year 1988. 
17. LEWISTON-CLARKSTON BRIDGE, ID 
AND WA 
Location. On the Snake River, River Mile 141.3, 1.7 miles 
upstream of the existing interstate bridge connecting the 
towns of Lewiston, ID and Clarkston, WA. 
Existing Project. The project consists of a new fixed highlevel 
four-lane highway bridge and approaches on U.S. Highway 
12 across the Snake River constructed at a cost "not to 
exceed $21,000,000". In December 1981, Congress authorized 
an additional expenditure of $2,200,000 for construction 
of Lewiston's North Ramp. An approach roadway from the 
bridge to 16th Avenue in Clarkston, WA was authorized in 
July 1983 at an additional expenditure of $800,000. 
- 39-5 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Final Environmental Impact Statement Supplement was 
filed with the Council on Environmental Quality on July 16, 
1979. 
Local cooperation. Non-Federal interests have provided 
without cost to the United States all lands, easements, and 
rights-of-way necessary for the construction of the bridge 
and its approaches, and after construction have agreed to 
own, operate toll free, and maintain the bridge and approach 
facilities. The non-Federal costs for the land and relocation 
are $755,193. 
Operations during fiscal year. All work complete. 
18. LITTLE GOOSE LOCK AND DAM - 
LAKE BRYAN, WA 
Location. Dam is 70.3 miles above mouth of Snake River at 
head of Herbert G. West Lake (Lower Monumental Reservoir), 
about 40 airline miles northerly of Walla Walla, WA, 
and 50 miles westerly of Lewiston, ID. 
Existing project. The project includes a dam, powerplant, 
navigation lock, fish ladder, and appurtenant facilities. Project 
provides for navigation, hydroelectric power generation, 
recreation, and incidental irrigation. The reservoir has a normal 
operating range between Elevations 638 and 633 Mean 
Sea Level (MSL). Lake Bryan extends upstream about 37.2 
miles and provides slack water to Lower Granite Lock and 
Dam. Dam structure is 2,670 feet long and about 160 feet 
high above streambed. Fish passage facilities include one ladder 
with entrances on both shores with a fish channel through 
the spillway which connects to the powerhouse fish collection 
system and south shore ladder. Powerhouse has six 135,000 
kilowatt generating units in operation for a capacity of 
810,000 kilowatts. Spillway dam is 498 feet long and overflow 
crest at Elevation 581 MSL is surmounted by 8 radial gates, 
50 feet wide and 60 feet high, which provides the capacity to 
pass a design flood of 850,000 cubic feet per second. Navigation 
lock is single-lift type with clear plan dimensions of 86 
feet by 675 feet and 15-foot minimum depth over the sills. A 
navigation channel 250 feet wide and 14 feet deep is provided 
from the dam to Lower Granite Lock and Dam. Relocations 
along the lake included 32 miles of Camas Prairie Railroad, 
6.8 miles of county roads, 2.2 miles of state highways, and 
Central Ferry Bridge. Principal project data are set forth in 
Table 39-J. 
Construction of the original project started in 1963 and was 
completed in 1976. Construction of the additional generating 
units started in 1974 and was completed in 1984. Power generation 
through September 1989 has been 49.50 billion kilowatt 
hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
continue for powerplant control. Operation and Maintenance: 
During fiscal year 2.45 billion kilowatt hours of electrical 
power were generated by the 6 generating units. Traffic 
through the navigation lock, consisting of grains, petroleum 
products, fertilizer, wood products, and miscellaneous cargo, 
amounted to 4,056,396 tons during calendar year 1988. 
19. LOWER GRANITE LOCK AND DAM, WA 
Location. At River Mile 107.5 on Snake River at head of 
Lake Bryan (Little Goose Reservoir) and about 33 miles 
downstream from Lewiston, ID. 
Existing project. The project includes a dam, powerplant, 
navigation lock, fish ladder, appurtenant facilities, and required 
about 8 miles of backwater levees along the Snake and 
Clearwater Rivers at Lewiston, ID. Project provides for slackwater 
navigation, hydroelectric power generation, recreation, 
and incidental irrigation. The reservoir has a normal operating 
range between Elevations 738 and 733 Mean Sea 
Level (MSL) in Lewiston, ID-Clarkston, WA area. Lower 
Granite pool extends upstream about 38 miles and provides 
slackwater to the Confluence of the Snake and Clearwater 
Rivers. Dam structure is about 3,200 feet long and about 146 
feet high above streambed. Fish passage facilties include one 
ladder with entrances on both shores with a fish channel 
through the spillway which connects to the powerhouse fish 
collection system and south shore ladder. Powerhouse has six 
135,000 kilowatt generating units in operation for a capacity 
of 810,000 kilowatts. Spillway dam is 512 feet long and overflow 
crest at Elevation 581 MSL is surmounted by 8 radial 
gates, 60 feet wide and 60.5 feet high, which provides the capacity 
to pass a design flood of 850,000 cubic feet per second. 
Navigation lock is single-lift type with clear plan dimensions 
of 86 by 675 feet and 15-foot minimum depth over the sills. A 
navigation channel 250 feet wide and 14 feet deep is provided 
from the dam to the Confluence of the Snake and Clearwater 
Rivers. Principal data are set forth in Table 39-J. 
Construction of the original project started in July 1965 and 
was completed in 1984. Construction of the additional generating 
units was started in 1974 and completed in 1979. Power 
generation through September 1989 has been 40.60 billion 
kilowatt hours. Approximately $4,119,300 in potential flood 
damages have been prevented since the levees became functional. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
continue for powerplant control. Operation and Maintenance: 
During fiscal year 2.54 billion kilowatt hours of electrical 
power were generated by the 6 generating units. Traffic 
through the navigation lock consisting of grains, petroleum 
products, fertilizer, wood products, and miscellaneous cargo, 
amounted to 2,576,567 tons during calendar year 1988. 
As the first collection point on the Snake River, Lower 
Granite Dam is a primary component of the District's Juvenile 
Fish Transport Program. Transport began in the 1960's 
as a study of methods of bypassing juvenile steelhead and 
salmon around turbines of the Corps' Snake and Columbia 
River dams. Transport became a routine operation in 1980 
while other structural modifications, installation of screens, 
and development of bypass systems continue. 
For the transport program, the District has collection facilities 
at Lower Granite, Little Goose, and McNary Dams. Juvenile 
salmon and steelhead collected at these dams are 
hauled by specially designed trucks or barges to release sites 
below Bonneville Dam. From there, they can travel unob- 
- 39-6 -

WALLA WALLA, WASHINGTON DISTRICT 
structed to the sea. In 1989, over 20,000,000 juvenile fish 
were collected. Due to fishery agency and Indian tribal policy, 
over 4.5 million, primarily yearling chinook, were bypassed 
back to the river after being collected. Another million were 
bypassed at Lower Granite Dam because there was inadequate 
barge capacity to haul them. In all, over 15 million fish 
were transported. Increased hatchery production and improved 
collection facilities, especially at Little Goose Dam, 
should result in record numbers of fish being collected and 
transported in 1990. 
20. LOWER MONUMENTAL LOCK AND 
DAM - LAKE HERBERT G. WEST, WA. 
Location. On Snake River at head of Lake Sacajawea (Ice 
Harbor Reservoir), about 45 miles northeast of Pasco, WA, 
and 41.6 miles above river mouth. 
Existing project. The project includes a dam, powerplant, 
navigation lock, two fish ladders, and appurtenant facilities. 
Project provides for navigation, hydroelectric power generation, 
recreation, and incidental irrigation. The reservoir has a 
normal operating range between Elevations 540 and 537 
Mean Sea Level (MSL). Lake Herbert G. West extends upstream 
about 28.7 miles and provides slack water to Little 
Goose Lock and Dam. Dam structure is about 3,800 feet long 
and about 135 feet high above streambed. Fish passage facilities 
include two fish ladders, one at each end of the dam. Powerhouse 
has six 135,000 kilowatt generating units in operation 
for a capacity of 810,000 kilowatts. Spillway dam is 508 feet 
long and overflow crest at Elevation 483 MSL is surmounted 
by 8 radial gates, 50 feet wide and 61 feet high, which provide 
capacity to pass a design flood of 850,000 cubic feet per second. 
Deck is at Elevation 553 MSL and provides a service 
road and track for a gantry crane. Navigation lock is single-lift 
type with clear plan dimensions of 86 by 675 and 15-foot 
minimum depth over the sills. A navigation channel 250 feet 
wide and 14 feet deep is provided from the dam to Little 
Goose Lock and Dam. Relocations along the lake included 
railroads and highways. Principal data are set forth in Table 
39-J. 
Construction of the original project started in June 1961 
and was completed in 1976. Construction of the additional 
generating units started in 1975 and was completed in 1981. 
Power generation through September 1989 has been 63.20 
billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
continue for powerplant control and generating Unit 2 repair. 
Contract awarded for repair of navigation lock gate and 
associated machinery. Operation and Maintenance: During 
fiscal year 2.33 billion kilowatt hours of electrical power were 
generated by the 6 generating units. Traffic through the navigation 
lock, consisting of grains, petroleum products, fertilizer, 
wood products, and miscellaneous cargo, amounted to 
4,257,796 tons during calendar year 1988. 
21. LOWER SNAKE RIVER FISH AND 
WILDLIFE COMPENSATION PLAN, WA, OR, 
ID
Location. At various locations within the Columbia Snake 
River drainage in the States of Idaho, Oregon, and Washington. 
Existing project. The project consists of a series of fish 
hatcheries (all sites selected) and wildlife development areas 
at sites to be selected. The project will compensate for loss of 
wildlife habitat and anadromous and resident fishery inundated 
as a result of construction of four multiple-purpose 
dams and reservoirs on the Lower Snake River (Ice Harbor, 
Lower Monumental, Little Goose, Lower Granite). 
The Walla Walla District operates the Juvenile Fish Transportation 
Program for the Columbia-Snake system. Three 
primary collection points have been established at Lower 
Granite, Little Goose, and McNary Dams, with fish sorting 
and handling facilities. Smolts collected at these facilities are 
taken by specially-designed barges and trucks to an area 
downstream of Bonneville Dam and released to make the 
rest of their journey to the sea. In 1988 a total of just over 
20,000,000 juvenile fish were transported. Increased hatchery 
production and improved fish guiding efficiency (FGE) 
has resulted in increased numbers of fish to be transported. 
In 1980 the first release from the McCall, ID summer chinook 
hatchery was made, and the adult trapping facility which 
provides the fish egg supply of the McCall Hatchery became 
operational. 
The real estate design memorandum, and feature design 
memorandums on the McCall Hatchery, Hagerman Hatchery, 
Lookingglass Hatchery, Lyons Ferry Hatchery, Dworshak 
Hatchery Expansion, Irrigon Hatchery, Magic Valley 
Hatchery, Sawtooth Hatchery, Clearwater Hatchery, the offproject 
wildlife lands, and the site selection report have all 
been approved. A final Environmental Impact Statement was 
filed with Council on Environmental Quality on November 2, 
1977. The Dworshak National Fish Hatchery, the Irrigon 
Hatchery, Wallowa Satellite Hatchery, Hagerman Hatchery, 
Lyons Ferry Hatchery, Lookingglass Hatchery, McCall 
Hatchery, Sawtooth Hatchery and Magic Valley Hatchery are 
in operation. The compensation plan is 73 percent complete. 
Estimated Federal cost of the project is $198,000,000. 
Local cooperation. None required 
Operations during fiscal year. New work: Work was completed 
at Powell Satellite and non-hatchery sports fishing 
(McFarland). Contracts were awarded for Crooked River facility, 
and Red River completion contract. Wildlife compensation 
contracts were awarded for the game bird alternative 
agreement. 
22. McNARY LOCK AND DAM - LAKE 
WALLULA, OR AND WA 
Location. On Columbia River 292 miles above mouth, near 
Umatilla, OR, and 3 miles above mouth of Umatilla River. 
Existing project. The project includes a dam, powerplant, 
navigation lock, two fish ladders, appurtenant facilities, and a 
- 39-7 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
system of levees and pumping plants. Project provides for 
slackwater navigation, hydroelectric power generation, recreation, 
and incidental irrigation. The reservoir has a normal 
operating range between Elevations 340 and 335 Mean Sea 
Level (MSL). Lake Wallula extends upstream about 64 miles 
and provides slack water to Ice Harbor Lock and Dam. Dam 
structure is about 7,300 feet long and about 183 feet high 
above streambed. Fish passage facilities include two fish ladders. 
Powerhouse has fourteen 70,000 kilowatt generating 
units in operation for a capacity of 980,000 kilowatts. Spillway 
dam is 1,310 feet long and overflow crest at Elevation 291 
MSL is surmounted by 22 vertical lift gates, 50 feet wide and 
51 feet high, which provides the capacity to pass a design 
flood of 2,200,000 cubic feet per second. Navigation lock is 
single-lift type with clear plan dimensions of 86 by 675 feet 
and 15-foot minimum depth over the sills. A navigation channel 
250-feet wide and 14-feet deep is provided from the dam 
to the mouth of the Snake River. Relocations along the lake 
included railroad bridges over the Columbia and Snake Rivers 
in order to eliminate hazards to navigation. Principal project 
data are set forth in Table 39-J. 
Construction started May 1947 and was completed in 1982. 
Power generation through September 1989 has been 215.13 
billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
continue for powerplant control. Operation and Maintenance: 
During fiscal year 6.24 billion kilowatt hours of electrical 
power were generated by the 14 generating units. Traffic 
through the navigation lock, consisting of grains, petroleum 
products, fertilizer, wood products, and miscellaneous cargo, 
amounted to 8,199,337 tons during calendar year 1988. 
23. SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING, OR, WA, AND ID 
Location. On Snake River downstream from Johnson Bar 
Landing, River Mile 230 Snake River, which is largest tributary 
of Columbia River, rises in Yellowstone National Park in 
western part of Wyoming, flows generally westerly for about 
1,000 miles, and empties into Columbia River near Pasco, 
WA, 324 miles from Pacific Ocean. 
Existing project. The River and Harbor Act of 1945 authorized 
construction of dams as necessary for power incidental 
irrigation, and open channel improvements for purposes of 
providing slack-water navigation and irrigation between 
mouth of Snake River and "Lewiston, ID. That authorization 
modified previous authorizations only for the portion of improvement 
below Lewiston, ID. Acts of June 13, 1902, and 
August 30, 1935, as they pertain to open river improvement 
from Lewiston, ID, to Johnson Bar Landing, remain part of 
existing project. 
Improvements included in existing project are Ice Harbor 
Lock and Dam - Lake Sacajawea; Little Goose Lock and 
Dam - - Lake Bryan; Lower Granite Lock and Dam; Lower 
Monumental Lock and Dam - Lake Herbert G. West; and 
open-river improvement, Lewiston to Johnson Bar Landing. 
Each of the four locks and dams is described in an individual 
report, and cost and financial data for the entire project are 
shown on Table 39-A and 39-K. 
Ice Harbor, Lower Monumental, Little Goose, and Lower 
Granite are in full operation. (See individual reports for details.) 
(For further details see Annual Reports, page 2246 for 
1903; page 1986 for 1906; page 1991 for 1915; and page 1981 
for 1962.) 
Local cooperation. None required. 
Terminal facilities. On Snake River from the mouth to 
Johnson Bar Landing there are 18 privately-owned barge terminals 
in use for shipping grain, petroleum products, fertilizers, 
wood products, cement, and other general cargo. There 
are also 5 marinas and 28 small-boat launching ramps, all 
open to public use. The facilities serve slack-water navigation 
to Snake River Mile 140, the site of Lewiston, ID. That slackwater 
reaches the Lewiston, ID-Clarkston, WA area since 
the lake behind Lower Granite Dam was filled in February 
1975. 
Operations during fiscal year. See individual report for Ice 
Harbor, Lower Monumental, Little Goose, and Lower Granite 
Locks and Dams. On Snake River from Lewiston, ID, to 
Johnson Bar Landing, reconnaissance and condition surveys 
were conducted and survey markers were maintained. 
General Investigations 
24. SURVEYS 
The Upper Snake River and Tributaries is the principal ongoing 
survey. The area covered by the study extends from the 
headwaters of the Snake River in Wyoming down to and including 
the Weiser River in Idaho. Interim studies were continued 
on Galloway Dam located on the Weiser River, Snake 
River in the vicinity of Jackson Hole, WY,and Big Lost River. 
An interim study of the Owyhee River Basin was terminated 
in FY1989 because studies showed there was no economically 
feasible projects in that basin. 
A reconnaissance study of the Palouse River Basin was 
completed in FY 1989. Palouse River is a tributary of the 
Snake River that rises in the Moscow mountains in northwestern 
Idaho and drains an area of about 2,800 square miles, 
mostly in eastern Washington. The only economically feasible 
projects would primarily provide for supplemental muncipal 
water supplies for the cities of Moscow, ID and Pullman, 
WA. Therefore it was determined that there was no Federal 
interest in continuing the study. 
The Columbia River and Tributaries is a survey study directed 
by the North Pacific Division in which the Walla Walla 
District is participating. Work on the CR&T study involved 
completion of the Clearwater River Basin interim study. No 
feasibility projects were found in the Clearwater Basin. 
A reconnaissance study investigating the flooding problems 
in the vicinity of Mud Lake, ID was completed in FY 1989. 
The Mud Lake area is a closed basin located on Camas Creek, 
20 miles west and 50 miles north of Idaho Falls in Jefferson 
County, ID. The lake is formed by a 10-mile long dike constructed 
many years ago by local farmers. The dike allows the 
adjacent land to be farmed and provides a water elevation so 
- 39-8 -

WALLA WALLA, WASHINGTON DISTRICT 
that an irrigation canal can deliver water to farms. Above normal 
runoff in the basin threatens overtopping of the dike. 
The Corps' study investigated alternative measures (such as 
storage and diversion of flows) to alleviate the potential 
flooding that could occur with failure of the dike. Although 
some alternatives are feasible, local interests chose not to 
cost share the next study phase (feasibility) at this time. 
Total cost of surveys during fiscal year was $929,390. That 
sum was expended for: flood control studies, $658,979; special 
studies including Soil Conservation Service, Bureau of 
Reclamation, River Basin and Regional Planning Commissions, 
Cooperation with States, $32,261, Special Investigations 
and FERC Licensing Activities, $83,648, and restudy of 
deferred projects, $154,502. 
25. COLLECTION AND STUDY OF BASIC 
DATA 
During the fiscal year, flood hazard data for a number of 
locations in the District were collected and analyzed. Flood 
information was provided to several Federal agencies, to the 
States of Idaho, Oregon, and Washington, to various cities 
and counties in those states, and to some private organizations. 
Total cost of collection and study of basic data during fiscal 
year was $173,355 which was expended for flood plain management 
services $49,818, flood warning plan $42,103, and 
technical services, $80,234, and environmental data studies 
$1,200. 
26. PRECONSTRUCTION, ENGINEERING 
AND DESIGN 
McNary Lock and Dam (Second Powerhouse), OR and WA 
McNary Second Powerhouse is a proposed addition on the 
south shore of McNary Lock and Dam on the Columbia River 
near Umatilla, OR. The project will increase the present 
980,000 kilowatt generating capacity by an additional 774,000 
kilowatts. Provisions are included for compensation of negative 
impacts on fish and wildlife. The project is estimated to 
cost $667,000,000 at October 1, 1986 price levels. 
The General Design Memorandum Phase I was prepared 
under the Water Resource Development Act of 1976, Public 
Law 94- 587, and submitted to the Secretary of the Army on 
July 1, 1981. 
Studies were initiated in FY 1982 and continued through 
FY 1984 on the General Design Memorandum Phase II and 
the Powerhouse Preliminary Design Report. There has been 
no further design activity on the project. The project was 
authorized for construction in the Water Resources Development 
Act of 1986. 
Zintel Canyon Dam, WA 
The proposed project consists of a roller compacted concrete 
dam 90 feet high with uncontrolled spillway and a fixed 
maximum release outlet works that would create a detention 
reservoir of 1,260 acre-feet of capacity. The storage comprises 
860 acre-feet for flood control and 400 acre-feet for 
sediment. In addition, the project also includes a conduit with 
a capacity of 400 cfs and a dike and floodgate across the Union 
Pacific Railroad to protect downtown Kennewick, WA. The 
plan of improvement will provide protection against heavy 
rainfall, snowmelt, and thunderstorm floods to the city of 
Kennewick, WA. 
Reevaluation of the project economics due to hydrology 
modifications resulted in a revised General Design Memo 
No. 2. The GDM has been forwarded to the Washington 
Level Review Board for approval. Fiscal Year Costs were 
$159,360. 
The total estimated Federal and Non-Federal project cost 
is $9,300,000. The estimated Federal cost is $7,000,000. 
Local cooperation. Non-Federal sponsors shall pay 25 percent 
of the total project cost or an estimated $2,300,000 in 
cash or materials. 
- 39-9 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 39-A COST AND FINANCIAL STATEMENT 
See 
Section 
In Total to 
Text Project Funding FY 86 FY 87 FY 88 FY89 Sep. 30,1989 
3. Catherine Creek, OR New Work 
4. Clear & Burnt 
River, OR 
5. Colfax, Palouse 
River, ID 
9. Jackson Hole, WY 
10. Lucky Peak Lake, ID 
11. Mill Creek Lake, WA 
12. Owyhee River, OR 
15. Dworshak Dam & 
Reservoir, ID 
16. Ice Harbor Lock 
& Dam,WA 
17. Lewiston-Clarkston 
Bridge, ID & WA 
18. Little Goose Lock 
& Dam, WA 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
m--- 
12,932 
88,500 
63,974 
11,215 
-9,200 
265 
11,000 
35,526 
2,236 2,236 
115,000 
--- 96,159 
65,000 
52,958 
20,000 
50,833 
1,101,999 1,560,698 1,078,000 852,000 
1,136,570 1,492,378 855,418 1,068,450 
616,000 
613,230 
2,517,000 
2,517,177 
68,000 
35,014 
50,000 
559,901 
499,000 573,000 1,047,550 
494,044 575,148 1,046,431 
-90,000 
-89,857 
-6,184 
26,802 
1,250 
-1,023 1,974 
28,800 
28,800 
99,500 
99,500 
5,810,240 
5,810,240 
2,388,270 
2,388,270 
200,000 
200,000 
19,652,0811 
19,652,0811 
13,696,5512 
13,613,460 2 
2,258,495 3 
2,258,495 3 
8,637,443 
8,618,908 
17,705,607 
17,705,579 
69,316 
69,316 
13,689 
- 329,523,296 4 
399 329,523,296 4 
5,446,000 6,027,728 6,711,200 6,178,520 67,505,235 8 
5,499,554 5,985,953 6,436,396 6,507,158 67,371,512 * 
------ 690,000 167,930,757 6 
---- --- 248,487 167,489,244 8 
4,868,671 5,609,800 5,643,100 7,346,305 
5,183,795 5,290,932 5,342,425 7,876,699 
68,841,979 7 
68,715,326 7 
-- 22,957,664 
6,210 -- 22,957,664 
56,460 
--- 3,000,000 4,963,000 229,318,022 e 
--- --- 6,391,061 227,746,083 8 
3,921,401 5,298,710 4,882,100 3,704,800 
4,442,150 5,145,627 4,569,571 4,257,639 
53,316,405 * 
53,304,0058 
- 39-10 -

TABLE 39-A 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
In Total to 
Text Project Funding FY 86 FY 87 FY 88 FY89 Sep. 30,1989 
19. Lower Granite Lock New Work 
& Dam, WA Approp. --- - 5,661,000 -563,000 372,878,315 10 
Cost --- -- 19,405 3,781,755 371,581,473 10 
Maint. 
Approp. 8,890,205 8,493,700 8,654,100 7,770,300 70,002,602 1 
Cost 9,053,763 8,114,145 8,667,762 8,177,073 69,898,018 11 
Maint 
Contrib. -- 20,000 -- - 20,000 
Cost --- 20,000 -- - 20,000 
20. Lower Monumental New Work 
Lock & Dam, WA Approp. --- -- 20,000 2,140,000 238,533,732 12 
Cost --- -- -- 363,114 236,736,846 12 
Maint 
Approp. 4,037,830 5,556,200 6,514,800 5,837,300 52,693,532 13 
Cost 4,322,908 5,375,064 5,290,609 7,270,127 52,653,104 13 
21. Lower Snake Fish & Wildlife New work 
Compensation, ID, OR & WA Approp. 14,971,000 16,100,000 5,313,000 8,687,000 149,236,909 
Cost 15,096,848 16,303,537 5,391,184 8,567,973 149,068,986 
(Contributed Funds) New Work 
Contrib. --- -- --- -- 223,965 
Cost -- - -- -- 223,965 
22. McNary Lock & Dam, - New Work 
Lake Wallula, OR & WA Approp. -- -- 20,000 1,180,000 323,715,105 14 
Cost --- -- 18,801 1,022,277 323,556,183 14 
Maint. 
Approp 9,977,999 13,440,800 9,389,800 8,865,480 159,037,115 '5 
Cost 11,305,733 13,048,173 9,350,922 9,331,470 158,801,641 '1 
(Contributed Funds) Maint. 
Contrib. - -- - - 43,707 
Cost 43,707 --- -- --- 43,707 
23. Snake RiverDownstream New Work 
from Johnson Bar Landing Approp. - -- 8,681,000 7,230,000 1,009,095,589 16 
OR, WA & ID Cost -- - 19,405 10,784,417 1,003,988,409 16 
Maint. 
Approp. 21,725,107 24,958,410 25,694,100 24,662,405 245,423,093 17 
Cost 23,008,630 23,928,713 23,870,367 27,588,435 245,138,951 '7 
1. Includes $570,831 appropriated and expended for Code 710, 
Recreation Facilities at Completed Projects. 
2. Includes $66,700 allotted and expended under Maintenance and 
Operation of Dams and Other Improvements of Navigable 
Waters. 
3. Excludes $80,000 contributed funds, but includes $96,340 
appropriated and expended for Code 710, Recreation 
Facilities at Completed Projects. 
4. Includes $2,046,100 regular project construction 
funds appropriated for and expended by Department of Interior 
in Fiscal Years 1969 through 1972 for hatchery operations. 
Includes $655,000 appropriated and expended for additional unit. 
5.Includes $18,604,666 regular project operation and maintenance 
funds expended by Department of Interior starting FY 1972 for 
hatchery operations. FY 72-78 funds of $6,097,000 were charged 
to project as a cost, but not as an expenditure for accounting 
purposes. Includes $41,000 allotted and expended under Special 
Recreation Use Fees. Includes $120,000 allotted and expended 
under Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. 
6. Excludes $82,500 contributed for artificial spawning channel. 
Includes $36,748,021 appropriated and expended for additional 
Units 4 through 6. Includes $914,256 appropriated and expended 
for Code 710, Recreation Facilities at Completed Projects. 
Includes $690,000 appropriated and $248,487 expended for 
Columbia River Fish Mitigation Program. 
7. Includes $43,000 allotted and expended under Special 
Recreation Use Fees; $641,063 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
8. Includes $60,941,807 appropriated and expended for additional 
Units 4 through 6. Includes $7,963,000 appropriated and 
$6,391,061 expended for Columbia River Fish Mitigation Program. 
9. Includes $621,063 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
10. Includes $46,212,534 appropriated and expended for additional 
Units 4 through 6. Excludes $405,819 contributed funds on lock 
and dam project. Includes $63,800 appropriated and expended for 
Code 710, Recreation Facilities at completed projects. Includes 
$5,098,000 appropriated and $3,801,160 expended for Columbia 
River Fish Mitigation Program. 
11. Includes $338,163 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
- 39-11 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Navigable Waters. 
12. Includes $51,661,371 appropriated and expended for additional 
Units 4 through 6. Includes $2,160,000 appropriated and $363,114 
expended for Columbia River Fish Mitigation Program. 
13. Includes $372,376 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
14. Includes $1,976,586 appropriated and expended for Code 710, 
Recreation Facilities at Completed Projects. Includes $1,200,000 
appropriated and $1,041,078 expended for Columbia River Fish 
Mitigation Program. 
15. Includes $80,600 allotted and expended under Special 
Recreation Use Fees and $1,035,860 allotted and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
16. Includes $400,150 for new work on previous projects (Pasco to 
Lewiston), and $34,613 for new work appropriation used for 
maintenance prior to 1953. Excludes $167,500 contributed funds 
for new work consisting of $85,000 for new work on existing 
projects (Pasco to Riparia), plus $82,500 for new work on existing 
artificial spawning channel. 
17. Includes $186,570 appropriated and expended for maintenance 
of previous projects (Pasco to Lewiston) and $382,005 
appropriated and $381,928 expended open river Pasco to 
Lewiston and Lewiston to Johnson Bar Landing. 
- 39-12 -

WALLA WALLA, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. 
- 39-13 - 
TABLE 39-B 
May 17, 1950 
COLUMBIA RIVER BASIN, LOCAL FLOOD 
PROTECTION PROJECTS 
Blackfoot Area, Snake River, ID. Levee left bank. H. Doc 531, 81st Cong., 2nd Sess. 
Blackfoot River, ID. Levees, channel improvement, and 
rectification works. 
Boise Valley, Boise River, ID. Channel improvement and 
enlargement, levees, and revetments in Ada County. Canyon 
County unit was deauthorized April 18, 1967. Ada County 
unit was deauthorized in 1986. 
Camas Creek, ID. Channel deepening and rectification of a 
20-mile reach of Camas Creek. Deauthorized in 1965. 
Gooding Area, Little Wood River, ID. Channel improvement. 
Grande Ronde Valley, OR. Levees and channel clearing, 
straightening and realignment; would complement stream 
regulation by upstream storage projects. Deauthorized in 1986. 
Heise-Roberts Extension, Snake River, ID. Channel clearing 
and rectification, levees, and bank protection. Henrys Fork 
Unit deauthorized in 1986. 
Jackson Hole, Snake River, WY. Flood protection. 
Kendrick, Potlatch River, ID. Revetted levee. 
Little Wood River, ID. Flood protection in immediate area. 
Deauthorized in 1965. 
Malheur River, OR. Channel rectification, levees, and bank 
protection at Vale. Willow Creek unit was deauthorized 
October 14, 1969. 
Palouse River, WA. Flood protection for urban and rural 
areas at Garfield and near Malden. Deauthorized in 1986. 
Payette Valley, ID. Channel rectification, levees, and bank 
protection along 38 miles of Payette River below Black 
Canyon Dam. Payette Valley was deauthorized October 3, 1978. 
Portneuf River and Marsh Creek, ID. Concrete-lined channel 
through Pocatello. Inkom-Marsh Creek unit was deauthorized 
October 14, 1969. 
Shelley Area, Snake River, ID. Bank protection. 
South Fork Clearwater River, ID. Emergency construction of 
levees and revetments. Deauthorized in 1986. 
Teton River, ID. Flood protection. Deauthorized in 1986. 
Tomanovich-Salmon City, Salmon, ID. Channel improvement. 
Weiser River, Weiser Area, ID. Intermittent channel 
realignment and improvement, levees, and bank protection, 
lower river area. 
Whitebird Creek, ID. Flood protection. Deauthorized in 1986. 
CATHERINE CREEK, OR 
Organic debris removal along Catherine Creek. Sec 208, P.L 83-780 Authorized 
by Chief Engineers Sep. 3, 1985 
CLEAR & BURNT RIVER, OR 
Construction of riprap bank protection at city of Sec. 14, P.L 79-526 
Huntington Waste Water Lagoon. Authorized by Chief of Engineers 
Jul 10, 1985 
COLFAX, PALOUSE RIVER, WA 
Provides for flood control works in vicinity of and through Flood Control Act of 1944 
Colfax, WA, by channel enlargement and modification, H. Doc 888, 77th Cong., 2nd Sess. 
levees, floodwalls, revetments, and modification of railroad 
bridges. 
3. 
Sep 24, 1954 
Jul 24, 1946 
Dec 22, 1944 
5.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
10. LUCKY PEAK LAKE. ID 
Jul 24, 1946 
Oct 22, 1976 
Dec 22, 1944 
as amended 
Jun 28, 1938 
Aug 18, 1941 
Sep 24, 1954 
as amended 
Jul. 19, 1988 
Jul 3, 1958 
Oct 23, 1958 
Aug 15, 1963 
Mar 2, 1945 
Dec 22, 1944 
as amended 
Oct 22, 1976 
Dec 29, 1981 
Jul 30, 1983 
Mar 2, 1945 
Dec 31, 1970 
Mar 2, 1945 
Mar 2, 1945 
May 25, 1978 
Oct 22, 1976 
as ammended 
Nov. 17, 1986 
Dam for flood control, irrigation, and recreation. 
Second outlet for streamflow maintenance 
Construction, operation, and maintenance of recreation 
facilities. 
MILL CREEK LAKE, WALLA WALLA, WA 
Off-stream storage project upstream fromWalla Walla. 
Channel improvement through Walla Walla; concretelined 
channel. 
OWYHEE RIVER, OR 
Gravel, brush and small tree removal from 12 miles of 
Owyhee River. 
P.L 79-526, Chief of 
Engineers Report dated 
May 13, 1946 
P.L 94-587 
Sec. 4, Flood Control Act of 1944 
H. Doc. 578, 75th 
Cong., 3d Sess. 
H. Doc. 719, 76th 
Cong., 1st Sess. 
Sec. 208, P.L 83-780 
Authorized by Chief of Engineers 
Feb. 11, 1985. 
COLUMBIA RIVER JUVENILE FISH 
MITIGATION PROGRAM 
Design, test and construction of fish bypass facilities at P.L 100-371 
Lower Monumental, Little Goose, Lower Granite and 
McNary dams. 
(BRUCES EDDY) DWORSHAK DAM AND RESERVOIR, ID 
Preparation of detailed plans. S. Doc 51, 84th Cong., 1st Sess. 
Bruces Eddy dam and reservoir for flood control, H. Doc. 403, 87th 
navigation, power, recreation, and area redevelopment. Cong., 2nd Sess. 
Redesignation of project as Dworshak Dam and Reservoir. P.L 88-96 
ICE HARBOR LOCK AND DAM - LAKE SACAJAWEA, WA 
Unit 1 of 4, Lower Snake River project. Lock and dam for H. Doc. 704, 75th 
navigation, power, recreation, and incidental irrigation. Cong., 3rd Sess. 
Construction, operation, and maintenance of recreation Sec. 4, Flood Control of 1944 
facilities. 
LEWISTON-CLARKSTON BRIDGE, ID AND WA 
Four-lane highway bridge and approaches. P.L 94-587 
Increase of authorized amount to $23,200,000. P.L 97-140 
Approach roadway from bridge to Sixteenth Avenue in P.L 98-63 
Clarkston, WA. Increase of authorized amount to $24,000,000. 
LITTLE GOOSE LOCK AND DAM - LAKE BRYAN, WA 
Unit 3 of 4, Lower Snake River project. Lock and dam for H. Doc. 704, 75th Cong., 3rd Sess. 
navigation, power, recreation, and incidental irrigation. 
Designation of reservoir as Lake Bryan. P. L. 91-638 
LOWER GRANITE LOCK AND DAM, WA 
Unit 4 of 4, Lower Snake River project. Lock and H. Doc. 704, 75th Cong., 3rd Sess 
dam for navigation, power, recreation, and incidental irrigation. 
LOWER MONUMENTAL LOCK AND DAM - 
LAKE HERBERT G. WEST, WA 
Unit 2 of 4, Lower Snake River project. Lock and dam for H. Doc. 704, 75th Cong., 3rd Sess. 
navigation, power, recreation, and incidental irrigation. 
Designation of reservoir as Lake Herbert G. West. P. L 95-285 
LOWER SNAKE RIVER FISH & WILDLIFE 
COMPENSATION PLAN, WA, OR, AND ID 
Fish hatcheries and replacement of wildlife habitat. P.L 94-587 
Changes to land acquisition authority. H.R. 6-P.L99-662 
- 39-14 - 
TABLE 39-B 
(Continued) 
11. 
12. 
14. 
15. 
16. 
17. 
18. 
19. 
20. 
21.

TABLE 39-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
WALLA WALLA, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized Documents 
22. 
Mar 2, 1945 
Dec 22, 1944 
as amended 
Nov 17, 1986 
23. 
Jun 13, 1902 
Jun 25, 1910 
Aug 30, 1935 
Mar 2, 1945 
Table E Aug 18, 1941 
Table E Dec 22, 1944 
Table E Jul 11, 1956 
Table E Oct 23, 1962 
Table E Nov 7, 1966 
9. & Table E Nov 17, 1986 
McNARY LOCK AND DAM - 
LAKE WALLULA, OR AND WA 
Lock and dam for navigation, power, recreation, and 
irrigation 
Construction, operation, and maintenance of 
recreation facilities. 
Construction, operation and maintenance of a second 
powerhouse. 
SNAKE RIVER MOUTH TO JOHNSON BAR, OR, 
WA, AND ID 
Open-river navigation Riparia to Pittsburg Landing. 
Mouth to Riparia. 
Pittsburg Landing to Johnson Bar. 
H. Doc. 704., 75th Cong., 3rd Sess. 
Sec. 4, Flood Control Act of 1944 
H.R. 6 - P.L 99-662 
H. Doc. 127, 56th Cong., 2nd. Sess. 
H. Doc. 411, 55th Cong., 2nd Sess. 
Rivers and Harbors Committee 
Doc. 25, 72nd Cong., 1st Sess. 
Supercedes previous legislation mouth to Lewiston, ID only. H. Doc. 704, 75th 
See Ice Harbor, Lower Monumental, Little Goose, and Cong., 2d Sess. 
Lower Granite Locks and Dams. 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Dayton, Touchet River, WA. Flood protection. H. Doc. 662, 76th Cong., 3rd Sess. 
Milton-Freewater, Walla Walla River, OR.Flood Protection. H. Doc. 719, 76th Cong., 3rd Sess. 
Heise-Roberts Area, Snake River, ID. H. Doc 452, 77th Cong., 1st Sess. 
Channel improvement. 
Malheur Improvement District, Snake River, OR. 
Flood protection. 
Pullman, Palouse River, WA. Flood protection. 
Deauthorized in 1986. 
Esquatzel Coulee, Connell, WA. Levees and protective work P.L 84-685 
Lower Dry Creek, Lowden, WA. Channel improvement. 
Mission and Lapwai Creeks, ID. Construction of levee. 
Bear Creek, Kendrick, ID. Channel improvement. P.L 87-874 
Lapwai Creek Culdesac, ID. Construct left bank levee. 
Lyman Creek near Rexburg, ID. Channelization. 
Tucannon River, Camp Wooten, WA. Levee and channel work. 
Blackfoot Reservoir, Blackfoot River, ID. Modification to 
increase spillway capacity. Deauthorized in 1986. 
Ririe Lake, Willow Creek, ID. Storage for flood control. 
Grande Ronde Lake, OR. Flood control, irrigation, water P.L 89-298 
supply, anadromous fish, downstream and resident trout 
fishery, recreation and downstream power. Deauthorized 
in 1986. 
Zintel Canyon Dam, WA. Local protection reservoir to provide 
flood protection to portions of the city of Kennewick, WA. 
Cottonwood Creek Dam, ID. Protection to highly- P.L 89-789 
developed urban and suburban areas against flash floods. 
Deauthorized in 1986. 
Stuart Gulch Dam, ID. Protection to highly-developed urban 
and suburban areas against flash floods. Deauthorized 
in 1979. 
Jackson Hole, WY. Flood control protection by channel P.L 99-662 
improvement consisting of channel rectification, levees, 
and revetment along Snake River in vicinity of Wilson, 
Wyoming. Also operation, maintenance, modifications, and 
additions are Federal responsibility. 
Little Wood River, ID. Flood protection 
-39-15-

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 39-C OTHER AUTHORIZED 
NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Columbia River and Tributaries Completed 1968 1,851,195 -- 
above Celilo Falls to Kennewick, WA 1 
1. Obviated by The Dalles, John Day, and McNary projects. 
TABLE 39-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Asotin Creek, Asotin, ID 1 Completed 1951 12,019 
Bear Creek, Kendrick, ID 1 Completed 1970 133,518 
Big Wood River, ID5 Completed 1985 170,000 
Boise River, ID Completed 1985 236,500 - 
Catherine Creek Lake, OR Deferred 1978 1,552,000 - 
Connell, WA 1 Completed 1967 60,000 
Cottonwood Creek Community Church, Culdesac, ID2 Completed 1984 23,400 - 
Dayton, Touchet River, WA Completed 1966 380,617 - 
Dry Creek, WA1 Completed 1961 384,426 
Esquatzel Coulee, Connell, WA 1 Completed 1967 232,792 
Esquatzel Coulee, Mesa, WA1 Completed 1969 2,665 
Gooding Area, ID1 Completed 1954 59,167 
Graves Creek, ID' Completed 1953 75,469 - 
Heise-Roberts Area, Snake River, ID Completed 1955 1,575,838 - 
Jackson Hole, Snake River, WY Completed 1978 2,388,270 - 
Lapwai Creek, Culdesac, ID 1 Completed 1972 176,833 
Lava Hot Springs, Portneuf River, ID' Completed 1973 113,296 
Little Wood River, ID 6 Active 
Lower Dry Creek, Lowden, WA1 Completed 1972 17,592 
Lyman Creek, ID' Completed 1971 230,315 - 
Malheur Improvement District, Snake River, OR Completed 1957 55,894 - 
Milton-Freewater, Walla Walla River, OR3 Completed 1968 1,786,753 
Mission and Lapwai Creeks, ID1 Completed 1965 54,538 
Orofino Creek & Clearwater River, Orofino, ID2 Inactive 1949 23,050 
Rapid Creek, ID5 Completed 1985 19,500 
Pataha Creek, Pomeroy, WA2 Completed 1977 110,815 
Payette River, Emmett Sewage Lagoon, ID2 Completed 1967 39,172 
Riverside Area, Pasco, WA' Completed 1972 28,839 - 
Ririe Lake, ID Completed 1983 39,677,448 - 
Sewage Lagoon, Vale, OR2 Completed 1985 75,000 
Shobe Canyon, Heppner, OR' Completed 1970 5,000 
Snake River, Blackfoot, ID' Completed 1980 131,700 
Snake River, Heise Bridge Location, ID2 Completed 1952 8,501 
Snake River, Stevens, Blackfoot, ID1 Completed 1968 32,425 
South Fork, Boise River, ID5 Completed 1985 44,400 - 
South Fork Clearwater River, Kooskia-Stites, ID Completed 1973 61,055 - 
Tomanovich-Salmon City, ID' Completed 1955 128,635 
Touchet River, Waitsburg, WA' Completed 1973 72,140 
- 39-16 -

TABLE 39-E 
(continued) 
WALLA WALLA, WASHINGTON DISTRICT 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS
For Last Cost to Sep. 30. 1989 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Tucannon River, Wooten, WA 1 Completed 1971 73,932 
Umatilla River, OR 1 Completed 1961 161,540 
Wallowa River, Weaver Bridge, OR2 Completed 1960 16,118 
Weiser River, ID5 Completed 1985 106,900 
Willow Creek, ID1 Completed 1963 976 - 
Willow Creek Lake, OR Completed 1985 37,168,114 - 
Yakima River, West Richland, WA1 ,4 Completed 1964 238,890 
1. Authorized by Chief of Engineers pursuant to Section 205, PL 4. Includes $9,000 contributed funds. 
80-858. 5. Authorized by Chief of Engineers pursuant to Section 208, PL 
2. Authorized by Chief of Engineers pursuant to Section 14, PL 83-780. 
79-526. 6. Authorized by Chief of Engineers pursuant to PL99-662. No 
3. Exclusive of $6,300 contributed funds. funds authorized until FY90. 
TABLE 38-G DEAUTHORIZED PROJECT 
For Last 
Full report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Asotin Dam, Snake River, ID & WA 1964 1975 - 
Blackfoot Reservoir, ID 1980 1986 267,626 
Boise Valley, ID 
Ada County Unit 1963 1986 46,084 
Canyon County Unit 1963 1967 10,600 - 
Camas Creek, ID 1960 1965 9,080 
Cottonwood Creek Dam, Boise, ID 1972 1986 183,100 
Grande Ronde Lake, OR 1966 1986 - 
Grande Ronde Valley, OR 1958 1986 102,458 
Heise-Roberts Extension, ID 
Henrys Fork Unit 1968 1986 27,800 - 
Little Wood River, ID 1960 1965 21,334 - 
Lower Walla Walla River, WA 1953 1986 4,000 - 
Malheur River, OR 
Willow Creek Unit 1961 1969 13,000 - 
Mill Creek, WA 1958 1977 3,537 - 
Palouse River, WA 1958 1986 2,000 - 
Payette Valley, ID 1960 1978 23,178 - 
Portneuf River, Inkom-Marsh Creek, ID 1969 1969 - 
Pullman, Palouse River, WA 1964 1986 99,540 
S.Fork Clearwater River, ID 1973 1986 3,899 
Stuart Gulch Dam, Boise, ID 1974 1979 234,100 
Teton River, ID 1955 1986 10,387 - 
Touchet River, WA 1957 1977 11,198 - 
Whitebird Creek, Columbia River Basin, ID 1957 1986 1,896 
- 39-17 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 39-H COLUMBIA RIVER BASIN, LOCAL FLOOD PROTECTION 
PROJECTS (See Section 2 of Text) 
Estimated 
Federal Cost to 
Project Status Cost Sep. 30, 1989 
Blackfoot Area, Snake River, ID Completed - 42,796 
Blackfoot River, ID Completed - 391,143 
Heise-Roberts Extension, ID Snake River Unit Completed - 3,375,158 
Kendrick, Potlatch River, ID Completed - 59,942 
Malheur River, OR Vale Unit Completed - 325,581 
Mud Lake, ID Inactive 1,187,000 5,996 
Portneuf River and Marsh Creek, ID Pocatello Unit Completed - 6,456,0321 
Shelley Area, Snake River, ID Completed - 32,335 
Weiser River, ID Deferred 1,565,000 37,757 
Weiser River, ID Cambridge-Midvale Deferred - 75,000 
TOTAL 10,801,740 
1. Exclusive of $36,800 contributed funds. 
TABLE 39-I INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 7 of Text) 
Lyman Creek, ID August 1989 
Palouse River, ID May1989 
Payette River, ID May 1989 
Salmon River, ID January 1989 
Snake River, ID August 1989 
Snake River, WY August 1989 
Touchet River, WA April 1989 
Walla Walla River,WA January 1989 
- 39-18 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
Project 
Dworshak Dam and 
Reservoir, ID 
(See Section 15 of Text) 
Ice Harbor Lock and Dam, WA 
(See Section 16 of Text) 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Space for additional 
Rating, Each 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at Elevation 1600 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
Concrete Gravity 
September 1974 
150,500 cfs 
1613 feet 
Tainter 
50 ft. by 55 ft.
2 
428 feet
3 
2 @ 90,000 kw 
1 @ 220,000 kw 
400,000 kw
3 
3 @ 220,000 kw 
1,060,000 kw 
150 feet 
March 1973 
1600-1445 feet 
1605 feet 
2,000,000 ac.-ft. 
53 miles 
17,090 acres 
175 miles 
86 feet 
675 feet 
97 feet 
100 feet 
103 feet 
15 feet 
May 1962 
Concrete Gravity 
January 1962 
850,000 cfs 
391 feet 
Radial 
50 ft. by 51 ft. 
10 
671 feet
6 
3 @ 90,000 kw 
3 @ 111,000 kw 
603,000 kw 
226 feet 
December 1961 
- 39-19 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
Little Goose Lock and Dam, WA 
(See Section 18 of Text) 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 440 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
Lower Granite Lock and Dam, WA 
(See Section 19 of Text) 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
440-437 feet 
446 feet 
31.9 miles 
9,200 acres 
14 ft. by 250 ft. 
80 miles 
86 feet 
675 feet 
93 feet 
98 feet 
101 feet 
15 feet 
May 1970 
Concrete Gravity 
January 1970 
850,000 cfs 
581 feet 
Radial 
50 ft. by 60 ft.
8 
656 feet 
243 feet
6 
135,000 kw 
810,000 kw 
244 feet 
March 1970 
638-633 feet 
646.5 feet 
37.2 miles 
10,025 acres 
14 ft. by 250 Ft 
92 miles 
86 feet 
675 feet 
95 feet 
100 feet 
105 feet 
15 feet 
May 1975 
- 39-20 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
Concrete Gravity 
February 1975 
850,000 cfs 
581 feet 
Radial 
50 ft. by 60.5 ft.
8 
656 feet 
243 feet
6 
135,000 kw 
810,000 kw 
246 feet 
April 1975 
Lower Monumental Lock and 
Dam, WA (See Section 20 of Text) 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
738-733 feet 
746.5 feet 
38 miles 
8,900 acres 
14 ft. by 250 ft. 
91 miles 
86 feet 
675 feet 
97 feet 
98 feet 
103 feet 
15 feet 
April 1969 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
Concrete Gravity 
March 1969 
850,000 cfs 
483 feet 
Radial 
50 ft. by 61 ft. 
8 
656 feet 
243 feet
6 
135,000 kw 
810,000 kw 
242 feet 
May 1969 
- 39-21 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
McNary Lock and Dam, OR 
and WA (See Section 22 of Text) 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 540 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 340 
Acres Navigation Channel, Depth by Width 
Length of Shoreline 
540-537 feet 
548 feet 
28.7 miles 
6,590 acres 
14 ft. by 250 ft. 
78 miles 
86 feet 
675 feet 
67 feet 
75 feet 
83 feet 
15 feet 
November 1953 
Concrete Gravity 
October 1953 
2,200,000 cfs 
291 feet 
Vertical Lift 
50 ft. by 51 ft. 
22 
1,348 feet 
14 
70,000 kw 
980,000 kw 
193 feet 
November 1953 
340-335 feet 
356.5 feet 
64 miles 
38,800 
14 ft. by 250 ft. 
242 miles 
- 39-22 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-K SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING OR, WA, AND ID 
(See Section 23 of Text) 
Estimated 
Cost (Corps New Work Maintenance Percent 
of Engineers to Sep. 30 1989 to Sep. 30, 1989 Corn- Constr. 
Project Funds Only) Approp. Cost Approp. Cost pleted Started 
Ice Harbor Lock & Dam 
Initial Project 129,578,480 129,578,480 129,578,480 68,841,979 68,715,326 100 FY 57 
Code 710 Recreation Facilities 914,256 914,256 914,256 0 0 100 FY 57 
Power Units 4-6 36,748,021 36,748,021 36,748,021 0 0 100 FY 71 
Fish Bypass Program 789,0003 690.000 248,487 0 0 31 
Totals 168,029,757 167,930,757 167,489,244 68,841,979 68,715,326 99 
Little Goose Lock & Dam 
Initial Project 160,413,215 160,413,215 160,413,215 53,316,405 53,304,005 100 FY 63 
Power Units 4-6 60,941,807 60,941,807 60,941,807 0 0 100 FY 74 
Fish Bypass Program 25.500.0003 7.963.000 6.391.061 0 0 25 FY 89 
Totals 246,855,022 229,318,022 227,746,083 53,316,405 53,304,005 92 
Lower Granite Lock & Dam 
Initial Project 321,503,981 321,503,981 321,503,979 70,002,602 69,898,018 100 FY 65 
Code 710 Recreation Facilities 63,800 63,800 63,800 0 0 100 FY 84 
Power Units 4-6 46,212,534 46,212,534 46,212,534 0 0 100 FY 74 
Fish Bypass Program 23.300.000* 5.098.000 3.801.160 0 0 16 FY 88 
Totals 391,080,315 372,878,315 371,581,473 70,002,602 69,898,018 95 
Lower Monumental Lock & Dam 
Initial Project 184,712,361 184,712,361 184,712,361 52,693,532 52,653,104 100 FY 61 
Power Units 4-6 51,661,371 51,661,371 51,661,371 0 0 100 FY 75 
Fish Bypass Program 34,300,0003 2,160,000 363.114 0 0 1 
Totals 270,673,732 238,533,732 236,736,846 52,693,532 52,653,104 87 
Open River Lewiston to Johnson Bar 
Landing 34,613 34,613 ' 34,613 377,655 377,578 2 
Open River Pasco to Lewiston 0 0 0 4,350 4.350 
Totals Existing Project 1,076,673,439 1,008,659,439 1,003,588,259 245,236,523 244,952,381 100 
Previous Projects Pasco to Lewiston 400,150 400,150 400,150 186,570 186,570 
Totals Authorized Project 1,077,073,589 1,009,095,589 1,003,988,409 245,423,093 245,138,951 
1. New work appropriations used for maintenance prior to 1953. 
2. Includes $3,700 appropriated and $6,897 expended in FY 1989 
for project condition survey cost. 
3. Does not include mitigation analysis. 
- 39-23 -

ALASKA DISTRICT *
This District consists of the State of Alaska. 
IMPROVEMENTS 
Navigation 
1. Anchorage Harbor, AK ..................... 
2. Bar Point Harbor,Ketchikan, AK............. 
3. Bethel Small Boat Harbor, AK .............. 
4. Dillingham Harbor, AK .................... 
5. Homer Harbor, AK ...................... 
6. Kake Harbor, AK ........................ 
7. Metlakatla Harbor, AK ..................... 
8. Ninilchik Harbor, AK .................... 
9. Nome Harbor, AK ........................ 
10. Project Condition Surveys ................... 
11. St. George, AK .......................... 
12. St. Paul Island Harbor ..................... 
13. Thomas Basin, Ketchikan, AK ............... 
14. Wrangell Harbor, AK ...................... 
15. Wrangell Narrows, AK ..................... 
40-1 
40-1 
40-2 
40-2 
40-2 
40-2 
40-3 
40-3 
40-3 
40-4 
40-4 
40-4 
40-4 
40-5 
40-5 
Flood Control 
16. Chena River Lakes, AK ................ ... 40-5 
17. Flood Control Work Under 
Special Authorization ...................... 40-5 
18. Inspection of Completed Flood 
Control Projects .......................... 40-6 
Navigation 
1. ANCHORAGE HARBOR, AK 
Location. Anchorage is in southcentral Alaska on the 
southeast shore of Knik Arm, north of Turnagain Arm near 
its junction with Cook Inlet. (See NOAA Charts 16660 and 
16664.) 
Existing project. Provides for dredging along a 3,000-foot 
baseline adjacent to the Port of Anchorage dock to a depth of 
35 feet below mean lower low water. Tidal range between 
mean lower low water and mean higher high water is 29.0 feet 
and the extreme range is 42.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. The Port of Anchorage facility consists 
of a POL terminal at the southern end and three general 
cargo terminals northward. The northernmost terminal, 
completed during 1976 and 1977 was outside the Federal 
project limits. Extension of the limits from 2,070 feet northward 
to 3,000 feet was authorized by Public Law 94-587 and 
funded in FY 1978. 
Multiple-Purpose Projects, Including Power 
19. Snettisham, AK........................... 40-6 
General Investigations 
20. Survey .................................. 
21. Collection and Study of Basic Data ........... 
22. Preconstruction, Engineering and Design ...... 
Tables 
Table 40-A 
Table 40-B 
Table 40-C 
Table 40-D 
Table 40-E 
Table 40-F 
Table 40-G 
Table 40-H 
Table 40-I 
Table 40-J 
Table 40-K 
.40-6 
40-6 
40-6 
Cost & Financial Statement ........ 40-7 
Authorizing Legislation ........... 40-9 
Other Authorized Navigation Projects 40-11 
Not Applicable 
Other Authorized Flood 
Control Projects ................ 40-12 
Not Applicable 
Deauthorized Projects ............ 40-12 
Navigation Work Under Special 
Authorization ................... 40-12 
Project Condition Surveys ......... 40-13 
Not Applicable 
Not Applicable 
Operations during fiscal year. Maintenance: Dredging has 
been accomplished across the entire project during FY 1989. 
Controlling depth at the harbor was at a project depth of - 36 
feet MLLW. Regular maintenance dredging was accomplished 
by contract during July through August 1989. A total 
of 200,284 cubic yards of silt was removed. 
2. Bar Point Harbor, Ketchikan, AK 
Location. Bar Point Harbor is in the northwest part of 
Ketchikan, AK on the south coast of Revillagigedo Island, on 
the north shore of Tongass Narrows in southeastern Alaska. 
It is 760 miles southeast of Anchorage and 700 nautical miles 
north of Seattle, Washington, via the Inside Passage. (See 
NOAA Chart 17430.) 
Existing project. The maintenance of a small boat basin of 
17.91 acres in area, with depths of -10 and -15 feet mean 
lower low water; two rock breakwaters 700 and 1100 feet in 
length and two floating breakwaters, one 963 feet in length 
and two floating breakwaters, one 963 feet long and the other 
120 feet long. Tidal range between mean lower low water and 
mean higher high water is 12.0 feet and the extreme range is 
26.0 feet. 
- 40-1 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Local cooperation. Fully complied with. 
Terminal facilities. Provides public anchorage spaces and 
mooring facilities for commercial, local, transient and refuge 
seeking fishing vessels. Has boat launch ramp and tidal grid. 
Power, water and limited telephone service available. 
Operations during fiscal year. Draft Letter Report was 
prepared to study excessive harbor wave energy. 
3. Bethel Small Boat Harbor, AK 
Location. On the north bank of the Kushokwin River. Approximately 
53 miles upstream from Kuskokwin Bay, about 
400 miles west of Anchorage. (See NOAA Chart INT 500.) 
Existing project. A small boat basin of 12 acres providing 
moorage for 1,200 small riverboats. Provides for the dredging 
of a 31 foot wide access channel and a maneuvering and 
turning channel with a depth of -4 feet. 
Local cooperation. Awaiting reply from city of Bethel regarding 
proposed maintenance dredging disposal sites in order 
to proceed with dredging contract. 
Terminal facilities. None. 
Operations during fiscal year. Initiation of plans and specifications 
for a maintenance dredging contract. 
4. DILLINGHAM HARBOR, AK 
Location. At head of Nushagak Bay, an arm of Bristol Bay, 
on right bank of Nushagak River just below its confluence 
Wood River; about 470 miles northeasterly of Dutch Harbor 
and 300 miles southwest of Anchorage. (See NOAA/NOS 
Chart #16660) 
Existing project. A small-boat basin 230,000 square feet in 
area with a depth of 0 - 0 above mean lower low water along 
Scandinavian Creek; with entrance channel 1,100 feet long 
and 40 feet wide in Scandinavian Creek; and a sill across the 
basin. Tidal range between mean lower low water and mean 
higher high water is 19.8 feet. Extreme range is 30.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Four docks at the city of Dillingham; 
three privately owned, one owned by the city of Dillingham, 
and four publicly owned small boat floats in the project basin. 
Two docks are used by the city to unload barges which come 
into Dillingham. New floats for the harbor were installed in 
June 1982 and removed before fall freezeup. They are replaced 
each spring. Cargo and passengers from ocean vessels 
are unloaded at the docks or in the small-boat basin. Facilities 
are inadequate for number of boats using small boat 
harbor. 
Operations during fiscal year. Maintenance: Regular 
maintenance was accompliahed by dredging from the end of 
May to the middle of June 1989. A total of 79,940 cubic yards 
of material was removed. 
5. HOMER HARBOR, AK 
Location. In Kachemak Bay, on Kenai Peninsula, 152 miles 
by water southwest of Anchorage. Harbor site is land based 
near the extremity of Homer Spit which varies to one-quarter 
mile in width and extends 4.5 miles southeasterly from the 
mainland. (See NOAA/NOS Chart #16645) 
Existing project. Provides for sheltered small-boat harbor, 
relocated and based within Homer Spit about 50 acres in 
area. Project depth varies from 10 feet mean lower low water 
in the most western segment of the harbor to 20 feet below 
mean lower low water in the entrance channel and the most 
eastern segment of the harbor; a north entrance channel; 
protected by a main rock breakwater 1,018 feet long and 
secondary rock breakwater 238 feet long. Tidal range between 
mean lower low and mean higher high water is 18.1 
feet, with an extreme range of 30.4 feet. (For details relating 
to previous projects, see page 1593 of Annual Report for 
1964.) 
Local cooperation. Fully complied with. 
Terminal facilities. One publicly owned and operated 
wharf capable of handling oceangoing vessels serves for passengers 
and general cargo. small boat facilities in basin area 
include publicly owned mooring floats, a publicly owned 
wharf, and an industrial wharf. Construction has tripled size 
of the harbor. The city of Homer has tripled the size of its fish 
dock located at the southern end of the harbor. 
Operations during fiscal year. Maintenance: Regular 
maintenance dredging was accomplished by contract. A total 
of 22,369 cubic yards were removed during July and August 
1989. 
6. KAKE HARBOR, AK 
Location. Kake Harbor is located in the city of Kake on the 
northwest corner of Kupreanof Island in southeastern 
Alaska, 39 air miles west of Petersburg, AK, and 850 water 
miles northwesterly of Seattle, WA. (See Coast and Geodetic 
Chart 8201.) 
Existing project. The authorized project consists of a 
1,580- foot-long west breakwater and a 1,750-foot-long 
south breakwater. Tidal range between mean lower low water 
and mean higher high water is 14.0 feet with an extreme 
range of 22 feet. Estimated project cost is $13,417,000 (September 
1988), including $13,378,000 for general navigation 
facilities 22,000 for navigation aids and $17,000 for lands. 
Local interests will pay 10 percent of the costs initially plus 10 
percent during a period of up to 30 years. 
Local cooperation. A local cooperation agreement would 
be required with the city of Kake. 
Terminal facilities. At Kake, a publicly owned wharf with 
seaplane float equipped airplanes and shallow draft vessels is 
located within area of proposed basin. At cannery 1 mile from 
city, there are two privately owned deep draft piers; one for 
cargo, open to all local boat owners, the second for fuel, 
including a float for fuejing small boats. At Portage Cove, 2 
miles from the city, the existing float was expanded into a 
small boat facility by the state in 1982. It consists of 2 mooring 
- 40-2 -

ALASKA DISTRICT 
floats, a launch ramp, a grid and is protected by floating 
breakwater. Facilities are not considered adequate for present 
commerce due to the following deficiencies in small boat 
facilities: Shallow water at Portage Cove and its approaches; 
ice formation on the cove during the winter months causing 
major boat damage and limiting the use of the mooring float; 
and transportation problems between the city and present 
facility at Portage Cove. 
Operations during fiscal year. A temporary automatic 
meteorburst wind monitoring station was maintained to 
gather wind velocity and directional data more closely associated 
with the location of the project for comparison with data 
used in preparing the plans and specifications. Environmental 
data was gathered during 1983 and 1984 as 
preconstruction information to be compared with post-construction 
conditions. 
7. METLAKATLA HARBOR, AK 
Location. Metlakatla is located in the southern portion of 
Port Chester, a small bay on the northwest coast of Annette 
Island in southeastern Alaska, 18 miles south of Ketchikan. 
(See Coast and Geodetic Charts 8074, 8075, and 8102.) 
Existing project. Consists of two small boat basins. Existing 
basin is 2.18 acres in extent with a depth of 10 feet below 
mean lower low water, protected by a rubblemound breakwater 
900 feet long. New basin consists of two rubblemound 
breakwaters, 1,255 and 1,150 feet long, and an entrance channel 
and maneuvering area, 1,100 feet long, 100 feet wide, 
dredged to a depth of 15 feet below mean lower low water and 
a basin area of 6.25 acres dredged to a depth of 15 feet below 
mean lower low water. Tidal range between mean lower low 
water and mean higher high water is 14.7 feet, with an extreme 
range of 24 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Publicly owned facilities are one general 
cargo dock, one barge ramp, and a small boat float 
system in existing basin. Privately owned facilities are one oil 
pier and one industrial wharf. Facilities are not adequate for 
mooring the commercial fishing vessels operating from Metlakatla. 
Existing protected harbor area is fully utilized. 
Operations during fiscal year. Project complete. 
8. NINILCHIK HARBOR, AK 
Location. At mouth of Ninilchik River in Cook Inlet, at the 
community of Ninilchik, AK about 40 miles upcoast from 
Homer and 112 miles southwest of Anchorage. (See NOAA/ 
NOS Chart #16640.) 
Existing project. A small boat basin 320 feet long by 150 
feet wide dredged to elevation of 2 feet above mean lower low 
water, with an approach channel 400 feet long and 50 feet 
wide dredged to an elevation of 9 feet above mean lower low 
water; protected by a pile jetty 410 feet long. Project was 
modified in design stage to delete pile jetty and revise harbor 
dimensions to 400 feet long by 125 feet wide, and was completed 
in November 1961. Modification, including river channel 
diversion, two armor rock jetties, and beach protection, 
was accomplished 1967 and 1969. Range between mean 
lower low water and mean higher high water is 19.1 feet, with 
an extreme range of 29.3 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, limited to shallow-draft vessels 
and accessible from Cook Inlet only at half-tide or 
higher, are a cannery dock along Ninilchik River available for 
offloading fish, and small boat floats in project basin, provided 
by State of Alaska. Other supplies are landed on beach 
or brought by road from deep draft ports in the vicinity. 
Facilities are extremely inadequate for the number of boats 
presently using harbor. Expansion of facilities would require 
construction of additional protected harbor area. 
Operations during fiscal year. Maintenance: Dredging of 
the harbor and entrance channel was accomplished by contract 
with 6,749 cubic yards removed in 1989. 
9. NOME HARBOR, AK 
Location. At mouth of Snake River at the city of Nome, 
AK, on northerly shore of Norton Sound, an arm of Bering 
Sea. It is a shallow open roadstead, 581 nautical miles north 
of Dutch Harbor and 545 air miles northwest of Anchorage. 
(See NOAA/NOS Chart #16206.) 
Existing project. Provides for two jetties, the easterly 951 
and the westerly not exceeding 676 feet long, at mouth of 
Snake River; a channel 8 feet at mean lower low water, 75 
feet wide, from Norton Sound through Snake River to 
mouths of Bourbon and Dry Creeks, in city of Nome, ending 
in a turning basin of the same depth, 250 feet wide and 600 
feet long; revetting banks of rivers; and protecting all existing 
waterfront improvements on easterly beach by means of rock 
mount seawall 3,350 feet long extending easterly from east 
jetty. Project has been completed except extension of jetties 
beyond present 400 and 240 feet, which is classified inactive. 
Range between mean lower low water and mean higher high 
water is 1.6 feet and extreme tidal range is 7.5 feet, but water 
levels are influenced more by wind than tide. Levels of 5 feet 
below mean lower low water have been observed during 
offshore winds, and a level of 14 feet above mean lower low 
water has been observed during a southerly storm. 
Local cooperation. Fully complied with. 
Terminal facilities. Cargoes and passengers from ocean 
vessels are lightered to and from shore a distance of about 2 
miles. Traffic enters dredged channel and is handled over 
revetment, where lighterage company has transfer facilities 
which are open to the public. Facilities considered inadequate 
for existing commerce. In July 1984, the city of Nome 
received Department of Army authorization (permit) to construct 
a 3,600-foot gravel filled causeway. Construction of 
the causeway began in July 1985. Due to lack of complete 
funding the length of the causeway was shortened to 2,700 
feet. Construction was completed in May 1987. Use of this 
causeway for offloading petroleum products was delayed until 
the September 1987 arrival of a required berthing barge. 
Operations during fiscal year. Maintenance: Dredging by 
contract was accomplished throughout the ice-free season. 
In FY 1989 2,800 cubic yards were removed. 
- 40-3 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
10. PROJECT CONDITION SURVEYS 
Preliminary and detailed surveys to determine navigation 
conditions at boat basins, small navigation projects, channels 
and tributaries of major rivers not within major project 
boundaries. Total costs for fiscal year were $484,699. (See 
Table 40-I) 
11. ST. GEORGE, AK 
Location. The city of St. George is located on St. George 
Island, the southernmost island of the Pribilof Islands, near 
the edge of the southwest Bering Sea shelf. 
Existing project. Project was authorized in Section 107 of 
the River and Harbor act of 1960, PL 86-645, as amended. 
The work consists of dredging approximately 176,500 cubic 
yards of material in the maneuvering area from an average 
depth of + 3 feet mean lower low water to -18 feet mean 
lower low water and the entrance channel from an average 
depth of -14 feet mean lower low water to -20 feet below 
mean lower low water. 
Local cooperation. Fully complied with. 
Operation during the fiscal year. A contract was awarded in 
December 1988. Notice to proceed was acknowledged February 
24,1989 and the contractor mobilized to the island at the 
beginning of April 1989. As of October 1, 1989, the contractor 
was approximately 54 percent complete with the project. 
The contractor plans to remobilize in the spring of 1990 to 
complete the project. 
12. ST. PAUL ISLAND, AK 
Location. St. Paul Island Harbor is located on the shore of 
Village Cove on the southern side of St. Paul Island, the 
largest and most populated island of the Pribilof group in the 
central southeast Bering Sea. 
Existing Project. A St. Paul Harbor project was authorized 
by Congress in Section 202 of Public Law 99-662, based on a 
1982 Corps of Engineers feasibility report. Since that report 
was published, new wave and climatic information has been 
gained through field measurement and through a November 
1984 storm that severely damaged a city built breakwater at 
St. Paul. American vessels have also assumed control of the 
groundfish harvest in the area more rapidly than expected, 
while crab stocks and catches have declined markedly. St. 
Paul also constructed 750 feet of breakwater and a 200-foot 
dock at the harbor site. The recommended plan therefore 
differs from the authorized project. The city has proposed to 
construct the project under Section 204(e) of Public Law 
99-662. The recommended plan will add 1,050 feet of breakwater 
at the existing crest height, 37 feet MLLW. The plan 
will include an inner breakwater 1,000 feet long with a crest 
height of + 18 feet MLLW. The Natural depth of the channel 
(-25 to -30 feet MLLW) is sufficient to allow safe passage of 
the vessels for which the harbor is designed. A 6-acre mooring 
basin will provide a safe area for vessels during extreme 
wave conditions, although the vessels will be required to 
move away from the dock. The current estimated cost for the 
204(e) project is $30,330,000, of which $15,748,000 would be 
reimbursed to the city of St. Paul by the Corps of Engineers 
after completion of the general navigation features. 
Local Cooperation. St. Paul Island Harbor is to be constructed 
under provisions of Section 204 of the Water Resources 
Development Act of 1986 (Public Law 99-662). The 
city of St. Paul is authorized to construct the navigational 
improvements, and would be reimbursed by the Corps of 
Engineers after completion of the general navigation improvements. 
A 204(e) agreement was signed by Assistant 
Secretary of the Army (Civil Works) Page on 30 June 1988. 
Terminal facilities. The city of St. Paul has constructed a 
breakwater 750 ft. long and 37 ft. high at the site, with a 200- 
foot-long concrete caisson dock. The main breakwater will be 
an extension of the existing breakwater. The new dock would 
be an extension of the existing dock. Existing facilities are not 
considered adequate to fully protect vessels during storms, or 
to allow for economic development along the waterfront of 
St. Paul. 
Operations during Fiscal Year 1988. Two-dimensional and 
three-dimensional model studies of the breakwater and of 
the harbor layout were completed at the Waterways Experiment 
Station, resulting in lowering of the main breakwater 
crest height and in the addition of the inner breakwater to 
reduce wave heights in the inner harbor. An Environmental 
Assessment was completed, and a Finding of No Significant 
Impact (FONSI) was signed by the District Engineer. The 
General Design Memorandum was completed and approved. 
Plans and specifications were submitted by the local sponsor, 
and were approved after the appropriate modifications were 
made. The 204(e) agreement was signed by the local sponsor 
and by the Assistant Secretary of the Army (Civil Works). 
The local sponsor received bids for the project and selected a 
contractor. However, the contract was not awarded because 
of the local sponsor's inability to secure complete financing 
for the project, and the bid was eventually voided. The city of 
St. Paul investigated additional sources of funding. 
13. THOMAS BASIN, KETCHIKAN, AK 
Location. Thomas Basin is in the southeast part of 
Ketchikan, AK on the south coast of Revillagigedo Island on 
the north shore of Tongass Narrows in southeastern Alaska. 
It is 760 miles southeast of Anchorage and 700 nautical miles 
north of Seattle, WA, via the Inside Passage. (See NOAA 
Chart 17430.) 
Existing project. A small boat basin of 11.35 acres in area, 
with depth of -10 feet MLLW. It is protected by a 900 feet 
long rock breakwater with a concrete cap. The tidal range 
between mean lower low water and mean higher high water is 
12.0 feet and the extreme range is 26.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Sheltered moorage space is provided 
for 300 vessels. The harbor services commercial seiners, 
trollers, local, transient and refuge seeking fishing vessels. 
There is a tidal grid and a 2 ton jib boat crane. Power, water 
and limited telephone service is available. 
Operations during fiscal year. Maintenance: Initiation of 
the letter report was held in abayance pending the outcome 
- 40-4 -

ALASKA DISTRICT 
of the Wrangell Harbor breakwater repair, letter report, 
since the problems are very similar. No work was completed 
in FY-89. 
14. WRANGELL HARBOR, AK 
Location. Wrangell Harbor is located on the west side of 
the northern end of Wrangell Island, 824 miles from Seattle 
and 160 miles from Juneau. (See U.S. Coast and Geodetic 
Survey Charts Nos. 8164, 8161, and 8201.) 
Existing project. This provides for a rubblemound breakwater 
300 feet long to protect the southern portion of the 
outer harbor; dredging a mooring basin 600 feet long, 400 
feet wide, and 10 feet deep below mean lower low water 
within the protected area; an inner basin in the tide flat area 
east of Shakes Island, 325 feet wide and 550 feet long and a 
connecting channel 120 feet wide and approximately 530 feet 
long and a connecting channel 120 feet wide and approximately 
530 feet long from the outer mooring basin all at a 
depth of 10 feet at mean lower low water; and construction of 
a rock mound breakwater 320 feet long on the reef north of 
Shakes Island. The range between mean lower low water and 
mean higher high water is 15.7 feet. The extreme tidal range 
is 26 feet. Heavy swells, dangerous to small fishing boats, are 
caused by the wind, which causes an additional rise of about 1 
foot. 
Construction of the breakwater north of Shakes Island was 
placed on inactive status as material to be used from the inner 
basin was unsuitable and the breakwater considered unnecessary 
for safe moorage of vessels. The cost of this portion was 
last revised in 1956 and estimated to be $6,500. (See table 
40-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are eight wharves and floats in 
Wrangell Harbor. Two privately owned wharves serving general 
cargo and passenger terminals, one of which includes a 
cold storage facility, are open for public use. The remaining 
wharves serve various industrial purposes. One of the floats is 
publicly owned and is open for public use for mooring and 
servicing small craft, and two privately owned floats serve oil 
handling facilities. 
Operations during fiscal year. Maintenance: A letter report 
was completed in June 1989 for final Division review. It 
recommended removing the concrete parapet wall and replacing 
it with an armor rock overlay to the seaward face of 
the breakwater. Division comments were received in July 
1989 recommending additional analysis of the capability of 
the parapet wall to be patched. The life cycle cost analysis 
showed patching and armor overlay to be very close. All 
alternatives included repair of the breakwater head. No additional 
work was completed in FY-89. Study costs to date are 
$116,000. 
15. WRANGELL NARROWS, AK 
Location. Wrangell Narrows is a constricted channel located 
between Mitkof Island and Kupreanof Island. It is 
approximately 24 miles long with its northern terminus ending 
at the city of Petersburg, AK located 730 miles southeast 
of Anchorage, AK and 700 nautical miles north of Seattle, 
WA, via the Inside Passage. (See NOAA Chart 17375.) 
Existing project. The main channel has been excavated to a 
300 foot width and a depth of -24 mean lower low water 
throughout the length of the channel. Portions of the channel 
were surveyed in FY 88. 
Local cooperation. None required. 
Terminal facilities. This is a channel project and as such has 
no terminal facilities. 
Operations during fiscal year. Periodic surveys were conducted. 
The Corps of Engineers dredge Yaquina completed 
the maintenance dredging in FY89. 
Flood Control 
16. CHENA RIVER LAKES, AK 
Location. In the vicinity of Fairbanks, AK, and encompassing 
the Tanana River, Chena River, Little Chena River, and 
their tributaries. (See USGS map Fairbanks, C1, D1, D2, and 
big delta D6.) 
Local cooperation. Fully complied with. 
Existing project. Moose Creek Dam has been constructed 
17 miles east of Fairbanks with control works on Chena 
River. The dam itself extends from a bluff one mile north of 
the Chena River and south past the control works for approximately 
six miles to the Tanana River. The dam connects 
with a completed 22-mile levee system along the north 
boundary of the Tanana river to a point south and west of 
Fairbanks. Estimated Federal cost is $210,000,000, (excluding 
Little Chena Dam, presently deferred) and estimated 
non-Federal cost is $12,548,000. 
Operations during fiscal year. A construction contract for 
Moose Creek Dam gate modifications is currently underway. 
17. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities - repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and antecedent 
legislation). 
Federal costs for the fiscal year were $640,795 for disaster 
preparedness and emergency operations. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Cong, as amended (preauthorization). 
18. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections were made of flood control works at Gold 
Creek, Skagway River, Lowell Creek, Fairbanks, Galena, 
Bethel, Talkeetna River, and Klutina River during FY 1989. 
- 40-5 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Multiple-Purpose Projects, Including Power 
19. SNETTISHAM, AK 
Location. At mouth of Speel River, between Crater Lake 
to the west and Long Lake to the north, 29 nautical miles 
southeast of Juneau. (See Coast Geodetic Survey chart 8227.) 
Existing project. Snettisham is a multi-stage power project. 
The initial stage, which was completed in 1977, tapped 
Long Lake and included an underground powerhouse with 
two 23.4 megawatt units and a transmission line to Juneau, 
AK. The project was turned over to the Alaska Power Administration 
for operation and maintenance. The second 
stage, which is nearly complete, provided a tunnel to Crater 
Lake and added a third unit. The final phase will provide a 
dam on Long Lake to increase storage and the energy capability 
of Long Lake. The Long Lake Dam is currently unscheduled. 
The existing Long Lake (elevation 815 feet) water 
is transported through an approximately horizontal 13-foot 
diameter tunnel 8,400 feet long and a 1,400-foot penstock 
dropping at a 46 degree angle to the underground powerhouse 
at tidewater to drive two turbines with a combined 
generating capacity of 47,600 kilowatts. Power from two generators 
is supplied to Juneau by a 13.8 kilovolt overhead 
transmission line and a submarine cable traversing Taku Inlet. 
The Crater Lake stage of construction tapped Crater 
Lake (elevation 1,002 feet) to drive a third turbine installed in 
the existing underground powerhouse. An additional 
nameplated-rated generating capacity of 34,500 kilowatts 
was added. Estimated cost of Stage 1 and Stage 2 construction 
is $148,284,000. 
Local cooperation. None required. 
Operations during fiscal year. New Work: The remote 
supervisory control and data acquisition (SCADA) contract 
was awarded in September 1989. Crater Lake Additions 2 
(misc. powerhouse electrical improvements) and Transmission 
Line Improvements (overvoltage during switching) contracts 
are scheduled for award in May 1990. Crater Lake 
Additions 1 (trashrack design at Crater Lake tap opening) to 
be reevaluated when the lake is drawn down in April 1990. 
The study to determine economic viability of Long Lake Dam 
extension is complete. Conclusion to defer construction until 
Juneau power demand increases. Crater Lake Main Contract 
is essentially (complete. Successful lake tap occurred on October 
21, 1988. Power-on-line initially occurred in May 1989, 
but was shut down for repairs to the spherical valve. Power 
was restored on November 1, 1989. Field testing of generator 
is scheduled for May 1990. Results of turbine efficiency tests 
are currently being evaluated. Repairs to the spherical valve 
are scheduled to begin June 1990. 
General Investigations 
20. SURVEYS 
Fiscal year costs for surveys include $1,026,327 for flood 
control studies, $107,611 for coordination studies and 
$137,148 for miscellaneous activities. 
21. COLLECTION AND STUDY OF BASIC 
DATA 
Technical assistance, information, flood plain management 
guidance and other flood plain management services have 
been provided to military and nonmilitary Federal agencies, 
local communities, State agencies, Architectural/Engineering 
firms, lending institutions and private individuals at a 
fiscal year cost of $143,626. 
Fiscal year cost for Hydrologic Studies were $20,182. 
22. PRECONSTRUCTION, ENGINEERING 
AND DESIGN 
Kodiak Harbor, AK 
The port of Kodiak is located 242 and 175 nautical miles 
south of Anchorage and Seward, respectively, and approximately 
1,258 nautical miles northwest of Seattle. St. Herman 
Harbor is located at Near Island across Near Island Channel 
from Kodiak. 
The project authorized for construction consists of a 45 
acre mooring basin with moorage facilities protected by a 
1,900-foot rubblemound breakwater with a crest height of 
+ 18 feet MLLW. The 45 acres of mooring area would provide 
single berthing for approximately 475 vessels up to 80 
feet in length. The average depth of water in the mooring 
area is -45 feet MLLW. The authorized entrance channel is 
2,000 feet long, of which 930 feet would be dredged 150 feet 
wide to a depth of -20 feet MLLW. The recommended plan 
has a 1.865 foot rubblemound split breakwater with a crest 
elevation of + 22 feet MLLW. The main entrance channel is 
located in the split breakwater and has a design width of 200 
feet and design depth of -20 MLLW. Since the natural water 
depth at the main entrance channel is -55 feet MLLW, no 
dredging is required in this channel. A 100-foot rubblemound 
stub breakwater is recommended next to a secondary 
entrance channel at the north end of the harbor. this 
secondary entrance channel is to be 100-feet wide with a 
design depth of -12 feet MLLW, and will require 4.400 
square yards of rock excavation. 
The current estimated cost of $18,806,000, of which 
$16,925,000 would be the Federal first cost and $1,881,000 is 
the non-Federal first cost (cash and lands easements rights of 
way). Local interests will pay 10 percent initially plus 10 
percent during a period of up to 30 years, resulting in an 
ultimate non-Federal cost of $3,762,000. 
A Local Cooperation Agreement will be required with the 
city of Kodiak. 
Thirty-one piers, wharves, and docks are located in the port 
of Kodiak. Four are located in Womens Bay and two in 
Gibson Cove, west of the main part of the city. Twenty-four 
facilities are along the main waterfront of Kodiak, with thirteen 
on St. Paul Harbor and eleven on Kodiak Harbor, west 
and east of the Kodiak Small Boat Harbor, respectively. The 
remaining facility is the St. Herman Small boat harbor between 
Uski and Near Islands, directly south of the Kodiak 
Small Boat Harbor. Fiscal year costs were $528,250. 
- 40-6 -

ALASKA DISTRICT 
TABLE 40-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
1. Anchorage Harbor, AK New Work 
2. Bar Point Harbor, 
Ketchikan, AK 
3. Bethel Small Boat 
Harbor, AK 
4. Dillingham Harbor, AK 
(Contrib. Funds) 
5. Homer Harbor, AK 
(Contrib. Funds) 
6. Kake Harbor, AK 
7. Metlakatla Harbor, AK 
(Contrib. Funds) 
8. Ninilchik Harbor, AK 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,102,000 2,072,000 1,635,300 1,433,100 
1,250,458 2,008,806 1,415,805 1,479,384 
- 25,000 
-- 9,187 
--- 53,600 53,600 
24,075 
2.,55 
10,800 
28,222 
-- - - 95,934 
400,000 320,500 317,600 720,600 
339,533 1,159 318,768 714,936 
533,235 
533,235 
21,652,572 2 
21,413,469 
25,000 
12,142 
64,400 
52,297 
548,790 
548,790 
6,697,521 
6,686,635 
1,700 
1,700 
3,512,350 1 
3,512,350 1 
3,662,711 
3,662,698 
65,000 439,000 437,000 323,000 
63,991 435,194 431,274 333,942 
2,059 - - - 
15,000 
4,507 8,757 
-- 115,000 
67,698 75,668 
1,000 
84,161 
150,923 
20,000 
36,504 
550000 
20,000 
50,258 
200,000 222,000 134,100 229,200 
197,723 211,162 146,168 198,740 
67,974 
67,974 
8,316,460 
8,288,015 
870,700 
866,201 
5,077,470 
5,074,730 
148,520 
148,520 
830,644 
722,096 
428,720 
428,720 
3,905,776 
3,874,061 
- 40-7 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989, U.S. ARMY 1988 
TABLE 40-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep.30, 1989 
9. Nome Harbor, AK 
(Contrib. Funds) 
11. St. George, AK 
(Contrib. Funds) 
12. St. Paul Harbor, AK 
13. Thomas Basin, 
Ketchikan, AK 
14. Wrangell Harbor, AK 
15. Wrangell Narrows, AK 
16. Chena River Lakes, AK 
(Contrib. Funds) 
19. Snettisham, AK 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work Approp 
Cost 
New Work Approp. 
Cost 
Maint. Approp. 
Cost 
*New Work Approp. 
Cost 
New Work Approp. 
Cost 
Maint. Approp 
Cost 
New Work Approp. 
Cost 
1,195,045 479,000 353,400 236,700 
1,245,955 465,606 273,481 443,745 
2,500 
2,500 
2,500 
2,500 
2,500 
2,500 
2,500 
2,500 
53,400 160,000 3,710,000 
12,962 174,627 3,204,451 
- 4,000 633,828 
534,000 510,000 450,000 
530,857 509,055 248,714 
- --. 
- 75,000 
-- 45,319 
58,200 
21,792 
38,500 
49,023 
-30,000 
14 
52,500 
21,787 
- 231,200 1,263,800 
- 201,660 1,257,306 
3,478,000 
3,590,751 
13,500 
871,881 
7,200,000 
6,819,420 
887,000 
847,469 
.--- 
New Work Approp. 3,505,000 27,200,000 
Cost 3,561,846 17,964,165 
5,528,000 
3,009,031 
774,000 
759,085 
5,300,000 
12,809,549 
1,268,000 
3,477,192 
962,300 
962,828 
4,715,113 
6,782,000 
1. Includes $2,672 of Code 710 Rec. Funds and $1,509,678 for 
previous project. 
2. Includes only actual Funds retained and cost incurred. 
3. Includes $310,000 for previous project (Fairbanks). 
4. Includes $1,624 for previous project (Fairbanks). 
- 40-8 - 
1,348,240 
1,348,240 
9,219,052 
9,207,617 
167,500 
167,500 
4,000,000 
3,392,040 
637,828
0 
1,494,000 
1,288,626 
28,200 
21,806 
537,020 
537,020 
497,352 
447,481 
1,494,900 
1,458,966 
213,991,765 3 
213,270,157 3 
6,463,124 4 
6,352,178 4 
2,182,300 
2,145,929 
136,236,556 
132,423,306

ALASKA DISTRICT 
Table 40-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
July 3, 1958 
2. 
Oct. 22, 1976 
Sept 3, 1954 
July 14, 1960 
July 14, 1960 
July 14, 1960 
July 14, 1960 
(as amended) 
July 3, 1958 
3. 
July 2, 1958 
Aug. 19, 1964 
July 14, 1960 
Aug. 13, 1968 
ANCHORAGE HARBOR, AK 
Deep winter harbor, adjacent to docks, dredge to 35 feet 
below mean lower low water, protected by two jetties. 1 
Extension of project limits. 
BAR POINT HARBOR, KETCHIKAN, AK 
Dredge additional basin to 15 feet deep or to rock, and 
construct three breakwater 700, 1,100 and 450 feet long. 
Construct three breakwaters 1.208 feet, 165 feet, 
and 120 feet. 
Maintenance of 17.91 acre basin, two rock breakwaters 
and two floating breakwaters. 
H. Doc. 34, 85th Cong., 1st Sess.2 
P.L 94- 587 
H. Doc. 501, 82nd Cong., 2d Sess. 
Section 107, P.L 86- 645 
Approved June 29,1978 
Section 221, P.L 91- 611 
BETHEL SMALL BOAT HARBOR, AK 
Construct 7,700-foot-long small boat harbor and entrance Section 107, P.L 86- 645 
channel by deepening, widening, and straightening the upper Authorized by the Chief of Engineers 
6,800 feet of Brown's Slough. June 29,1978 
Dredge 31 foot wide access channel and maneuvering and Section 221, P.L 91- 611 
turning channel. 
DILLINGHAM HARBOR, AK 
Basin 230,000 square feet in area with depth of 2 feet 
above mean lower low water along Scandinavian Creek, 
with entrance channel 1,100 feet long and 40 feet wide. 
HOMER HARBOR, AK 
Basin 2.7 acres in area with depth of 12 feet below mean 
lower low water, and rock breakwater 1,260 feet long. 
Relocation and rehabilitation of project destroyed by 
March 27, 1964 earthquake, by construction of basin 10 
acre in area with 12-foot depth over 2.75 acres and 15-foot 
depth over 7.25 acres protected by rock breakwaters, 1,018 
feet and 238 feet long. 
Increased width and depth of entrance channel and an 
enlarged staging area. Basin enlarged from 16.5 to 50 acres. 
KAKE HARBOR, AK 
Basin 7-acre berthing area, 15 feet deep, inclosed by a 
1,580-foot west rock breakwater and a 900-foot south 
rock breakwater. 
H. Doc. 390, 84th Cong., 2d Sess.2 
H. Doc. 34, 85th Cong., 1st, Sess.2 
P.L 88- 451 
Section 107, P.L 86-645 
Authorized by Chief of Engineers, 
Nov. 13, 1981 
S. Doc. 70, 90th Cong., 2d Sess. 
METLAKATLA HARBOR, AK 
Dredging small boat basin 2.18 acre in extent to a depth H. Doc. 138, 76th Cong., 91st Sess. 
of 10 feet below plane of mean lower low water; construction 
of rubblemound breakwater 900 feet long. 
Entrance channel and two rubblemound breakwaters Section 201, P.L 89- 298 
inclosing a 7.0 acre basin. S. Doc. 92- 64, 92d Cong. 2d Sess. 2 
Authorized Oct. 12, 1972 
NINILCHIK HARBOR, AK 
Basin 320 feet long by 150 feet wide with depth of 2 feet H. Doc. 34, 85th Cong., 1st Sess. 2 
above mean lower low water, approach channel 400 feet 
long and 50 feet wide with depth of 9 feet above mean lower 
low water, protected by 410- foot jetty. 
- 40-9 - 
7. 
Mar. 2, 1945 
Oct. 27, 1965 
July 3, 1958 
8.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989, U.S. ARMY 1988 
AUTHORIZING LEGISLATION 
See Date 
Sect ion Authorizing 
in Text Act Project and Work Authorized Documents 
NOME HARBOR, AK 
Two jetties, easterly 335 feet and westerly 460 feet long H. Doec. 1932, 64th Cong., 2d Sess. 2 
revetment, channel and basin 200 feet wide and 250 feet long. 
Extension of the jetties and enlarging basin to 250 feet H. Doe. 404, 71st cong., 2d Sess., 
wide and 600 feet long. 3 and Rivers and Harbors Committee 
Doec. 38, 73d Cong., 2d Sess. 
Seawall Reports of Chief of Engineers 
dated March 8, 1948 
ST. GEORGE, AK 
Dredging the m,aneuvering ares from an average depth of Section 107 of The Rivers and 
+ 3 feet MLLW to 18 feet below MLLW and dredging the Harbors Act of 1960, Public Law 
entrance channel from an average depth of 14 feet MLLW 86-645, as amended and Water 
to 20 feet below MLLW. Resources Development Act of 1986, 
Public Law 99-662. 
ST. PAUL ISLAND, AK 
Add 1050 feet of breakwater at existing crest height, 
37 feet mean low low water and 1,000 feet long with a 
crest height of + 18 mean low low water. 
THOMAS BASIN, KETCHIKAN, AK 
Breakwater 940 feet long to protect 11.35 acre basin 
dredged to 10-foot depth. 
WRANGELL HARBOR, AK 
Breakwater 300 feet long to protect southern portion 
of harbor. 
Mooring basin 600 feet long, 400 feet wide, and 10 feet deep. 
Inner basin and connecting channel from the existing 
mooring basin, both 10 feet deep at mean lower low water, 
and breakwater 320 feet long on the reef north 
of Snakes Island. 
Section 202, PL 99-662 
H. Doec. 113, 70th Cong. 1st Sess.2 
H. Doec. 161, 67th Cong., 2d Sess. 
H. Doec. 202, 72nd Cong., 1st Sess. 
H. Doec. 284, 76th Cong., 1st Sess. 
WRANGELL NARROWS, AK 
Original channel 200 feet wide with depths of 21 feet in rock H. Doec. 179, 67th Cong. 2d Sess. 
and 27 feet at shoal No. 2. 
Enlargement of channel at shoat No. 1; easing curves for H. Doec. 647, 71st Cong., 3rd Sess 
300 foot channel, 24 feet deep. 
Channel 300 feet wide and 24 feet deep at mean lower low H. Doec. 260, 76th Cong., 1st Sess 
water, with improvement of existing alignment and an 
anchorage basin 500 yards wide, and 26 feet deep. 
CHENA RIVER LAKES, AK 
Dam and reservoir on the main Chena River, a dam and 
detention reservoir on the Little Chena River, and a levee 
along the north side of the Tanana River.4 
SNETTISHAM, AK 
Multi-purpose dam, with powerhouse and transmission 
facilities. 
S. Doe. 89, 90th Cong., 2d Sess.2 
H. Doec. 40, 87th cong., 1st Sess.2 
1. Purchase of dredge and deepwater jetties deauthorized 
November 6, 1977 under section 12, Public Law 93-251. 
2. Contains latest published map. 
3. Extension of jetties classified "inactive". 
4. Little Chena Dam classified "deferred". 
-40-10- 
Table 40-B 
(Continued) 
9. 
Aug. 8, 1917 
Aug. 30, 1935 
June 16, 1948 
Nov. 17, 1986 
11. 
12. 
13. 
14. 
Nov. 17, 1986 
July 3, 1930 
Sept. 22, 1922 
Aug. 30, 1935 
Mar. 2, 1945 
15. 
16. 
Mar. 3, 1925 
Aug. 30, 1935 
Mar. 2, 1945 
Aug. 13, 1968 
Oct. 23, 1962 
18. 
S. 
).

ALASKA DISTRICT 
TABLE 40-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Apoon Mouth of Yukon River, AK1 
Bar Point Harbor, AK2 
Bethel Small Boat Harbor, AK 
Cook Inlet Shoals, AK 
Cordova Harbor, AK 
Cordova, AK2 
Craig Harbor, AK 
Douglas Harbor, AK 
Dry Pass, AK 
Egegik River, AK 
Elfin Cove, AK 
Gastineau Channel, AK 
Haines Harbor, AK2 
Homer Harbor, AK2 
Hoonah Harbor, AK 
Humboldt Harbor, AK 
Iliuliuk Harbor, AK 
Juneau Harbor, AK 
Kasilof Harbor, AK2 
Ketchikan Harbor, AK 
Kodiak Harbor, AK 
Mekorykuk, AK 
Myers Chuck Harbor, AK 
Naknek River, AK 
Neva and Olga Straits, AK 
Old Harbor, Kodiak Island, AK2 
Pelican Harbor, AK 
Petersburg Harbor, AK 
Port Alexander, AK 
Port Lions, AK2 
Rocky Pass, AK 
St. Michael Canal, AK 
Seldovia Harbor, AK 
Sergius Whitestone, AK 
Seward Harbor, AK 
Sitka Harbor, AK 
Skagway Harbor, AK 
Valdez Harbor, AK 
Wrangell Narrows, AK 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
-Completed 
Completed 
Completed 
Completed 
Completed 
1920 
1983 
1985 
1977 
1978 
1986 
1983 
1963 
1983 
1972 
1959 
1964 
1977 
1987 
1983 
1977 
1941 
1974 
1975 
1979 
1973 
1986 
1970 
1961 
1960 
1972 
1964 
1972 
1949 
1986 
1960 
1916 
1974 
1973 
1973 
1973 
1972 
1968 
1979 
128,896 
2,000,0003 
1,520,272 
1,220,000 
843,534 
9,642,000 
1,033,5004 
282,019 
943,351 
4,441 
154,191 
789,461 
1,000,000 s 
2,000,000 
4,255,0006 
3,679,6837 
66,037 
1,381,150 
109,848 
1,602,417 
1,891,2128 
1,372,139 
9,700 
20,789 
155,009 
370,415 
369,683 
252,932 
17,000 
1,825,311 
337,668 
377,062 
1,051,8839 
1,798,010 
712,36910 
1,611,009 
133,180 
649,74011 
3,562,343 
2,154 
5,000 
488,156 
72,500 
23,466 
3,107 
102,701 
260,991 
331,256 
37,946 
132,946 
18,973 
26,800 
560 
5,518 
1,934 
219,789 
15,400 
32,665 
221,498 
309,260 
1. Abandonment recommended in H. Doc. 467, 69th Cong., 1st 
Sess. 
2. Authorized by Chief of Engineers (Sec. 107). 
3. In addition, $272,779 of State funds. 
4. Includes $656,240 for Sec. 107 project. 
5. In addition, $925,500 of State funds. 
6. In addition, $973,875 of State funds. 
7. In addition, $857,000 of State funds 
8. Includes $594,163 for rehabilitation. 
9. Includes $400,000 for rehabilitation. 
10. Includes $90,026 for rehabilitation and $2,528 Code 710. 
Recreation facilities at Completed projects. 
11. Includes $73,000 for rehabilitation and $2,713 Code 710, 
Recreation facilities at Completed projects. 
- 40-11 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1989, U.S. ARMY 1988 
TABLE 40-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30. 1989 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Bethel Bank, Kuskokwim River' Completed 1985 553,970 
Fairbanks, Tanana River & Chena Slough, AK Completed 1943 557,000 
Gold Creek, AK Completed 1975 876,006 2 4,301 
Klutina River, Cooper Center, AK a Completed 1973 260,681 
Lowell Creek, AK' Completed 1945 416,382 a 30,771 
Salmon River, AK Completed 1963 37,770 * ' 162,925 * 
Skagway River, AK Deferred * 1966 26,385 
Talkeetna River, AK Completed 1981 516,694 
1. Section 14 6. Includes $34,197 of PWA funds 
2. In addition, $25,000 expended from contributed funds. 7. In addition, $7,000 expended from contributed funds. 
3. Authorized by Chief of Engineers (Sec. 205). 8. In addition, $27,400 expended from contributed funds. 
4.During FY 88, $551,690 was expended from FC and CE. 9. Project eligible for deauthorization. 
5. In addition $25,000 expended from contributed funds. 
TABLE 40-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Anchorage Harbor, AK (Uncompleted Portion) 1967 1977 
Bradley Lake, AK 1983 1983 1982 46,701,000 
Ketchikan Harbor, AK (West Breakwater) 1979 1979 
Port Alexander, AK (Inner Harbor) 1949 1977 
Tolovana River, AK (Snagging) 1931 1977 
TABLE 40-H NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, PUBLIC LAW 86- 645 
(PREAUTHORIZATION) 
Study Identification Fiscal Year Costs 
Anchor Point, AK $ 88,565 
Chenega Bay, AK 3,516 
Chignik, AK 175,478 
Dillinghan, AK 95,934 
Fire Island, AK 7,500 
Kenai, AK 1,225 
Larsen Bay, AK 18,880 
Manley Hot Sprixigs, AK 1,380 
Mountain Point, AK 10,600 
Ouzinkie Small Boat Harbor, AK 26,629 
Pier III Shoal Removal Kodiak, AK 7,500 
Point Mackenzie, AK 2,478 
Port Graham, AK 985 
Puffin Island Shoal Removal Kodiak, AK 7,500 
Saxman, AK 46,524 
Seldovia, AK 6,345 
Whittier Small Boat Harbor, AK 14,605 
TOTAL 
- 40-12 -

ALASKA DISTRICT 
TABLE 40-I PROJECT CONDITION SURVEYS 
Name of Project Date Survey Conducted 
Craig Harbor March 1989 
Haines Harbor March 1989 
Ilivlivk Harbor August 1989 
King Cove Harbor June 1989 
Metlakatla Harbor January 1989 
Port Lions Harbor December 1988 
Sitka Harbor March 1989 
Skagway Harbor March 1989 
Seward Harbor September 1989 
- 40-13 -

BOARD OF ENGINEERS FOR RIVERS AND HARBORS 
The Board of Engineers for Rivers and Harbors is a 
continuing body created by Section 3 of the 1902 River 
and Harbor Act. The board is selected by the Chief of 
Engineers and consists of seven senior engineer officers. 
The Deputy Chief of Engineers normally serves as 
chairman. The seven members are division engineers with 
membership rotated among divisions having civil works 
missions. The civilian staff members consist of an Acting 
Resident Member and three senior advisors. The board 
generally meets quarterly or on call of the chairman. 
The board under the direction of the Chief of Engineers: 
* Conducts independent review of reports as requested 
by Acts of Congress or resolutions of Congressional 
Committees, or as directed by the Chief of Engineers, 
concerning proposed works for development of the 
water resources of the United States; prepares reports 
and recommendations thereon in compliance with 
study directives, with regard to formulation of project 
scope, suitability of engineering plans, adequacy of 
costs, economic justification, and requirements of local 
cooperation including cost sharing and propriety of 
proposed construction by the federal government. 
* Reviews reports and makes recommendations for major 
modification or reconstruction of existing navigation 
improvements to ensure conformity with existing 
authorized improvements and essentiality for efficient 
and economical maintenance and operation. 
* Provides independent evaluation and counsel with 
respect to the environmental quality aspects of water 
resources development. 
* Provides assistance, as required, to HQUSACE in the 
development of policy and related procedures for the 
uniform application of standards in the project formulation 
process. 
* Provides advice on potential issues related to ongoing 
planning studies, as discussed during feasibility phase 
Issue Resolution Conferences. 
Total membership of the board is fixed by law at seven. 
In December 1982, the Chief of Engineers instituted a 
mechanism for predesignating future members, based on 
their time of service as division engineers, geographical 
factors, and other criteria. This procedure achieves a 
wider involvement of division engineers and their staffs 
with the proceedings of the board. Members Designate 
attend and participate in the meetings of the board, but 
are not permitted to vote on board actions. This procedure 
achieves a wider involvement of division engineers 
and their staffs with the proceedings of the board. 
The membership ofthe board as of September 30, 1989 
was: 
Members: 
Major General Richard S. Kem, Deputy Chief of Engineers, 
Washington, DC 
Major General Robert M. Bunker, Division Engineer, 
South Atlantic, Atlanta, GA 
Brigadier General (P) John F. Sobke, Division Engineer, 
South Pacific, San Francisco, CA 
Brigadier General Arthur E. Williams, Division Engineer, 
Lower Mississippi Valley, Vicksburg, MS 
Brigadier General Robert H. Ryan, Division Engineer, 
Missouri River, Omaha, NE 
Brigadier General Theodore Vander Els, Division 
Engineer, North Central, Chicago, IL 
Brigadier General Robert C. Lee, Division Engineer, 
Southwestern, Dallas, TX 
Member Designate: 
Colonel (P) Paul W. Chinen, Division Engineer, Ohio 
River, Cincinnati, OH 
Official Board Actions. In compliance with resolutions 
of the Congress and instructions from the Chief of 
Engineers, the board approved three official report reviews 
during FY 1989. 
The favorable reports category includes favorable 
recommended projects for federal construction as well as 
projects for solving water resources problems for major 
metropolitan areas, even though they may not include 
recommendations for construction by any agency of the 
federal government. 
The board approved three projects at a estimated total 
first cost of $602,217,000, of which $341,933,000 is the 
first cost to the United States. A listing of the projects 
follows: 
Bayou La Batre, AL 
Buffalo Bayou and Tributaries, TX 
Miami Harbor Channel, FL 
Recommending Unfavorable forFederal Construction: 
During FY 1989, the board concurred in the unfavorable 
recommendations of the reporting officers for federal 
construction on 12 projects: 
Buffalo Harbor, NY 
Clearwater, FL (Spoil Disposal) 
Eastern South Dakota & Upper Sioux, SD and IA 
Flagler County, FL 
Genesee River Basin, NY 
Great Lakes, Lake Ontario, and Lake Erie 
Kansas and Osage Rivers, KS 
Little Pee Dee and Pee Dee Rivers, NC & SC 
Mexico Beach, FL 
Peoria Lake and La Grange Pool, Illinois River, Henry 
to Naples, IL 
St. Marys River Basin, FL and GA 
Wild Rice-Marsh Rivers, MN 
Since 1902, the board has acted on 8,824 reports, 
recommending favorably on 3,935 and unfavorably on 
4,889. 
41-1

MISSISSIPPI RIVER COMMISSION* 
The Mississippi River Commission (MRC) was created 
by an act of Congress on Jun. 28, 1879. The Flood 
Control Act of May 15, 1928, authorized the Flood Control, 
Mississippi River and Tributaries (MR&T) Project. 
The Commission consists of three officers of the 
Corps of Engineers, one from the former Coast and 
Geodetic Survey (presently the National Oceanic and 
Atmospheric Administration), and three civilians, two 
of whom must be civil engineers. All members are 
appointed by the President with the advice and consent 
of the Senate. 
During the fiscal year the Commissioners were: MG 
Thomas A. Sands, U.S. Army, President, appointed 
May 10, 1985, until his retirement in August 1989. BG 
Arthur E. Williams has served as Chairman since 
then. Mr. Sam E. Angel, appointed Sep. 25, 1979; Mr. 
R. D. James, civil engineer, appointed Dec. 1, 1981; 
Mr. Frank H. Walk, appointed Oct. 22, 1987; MG 
Charles E. Edgar III, appointed Oct. 22, 1987; RADM 
Wesley V. Hull, NOAA, appointed Jan. 4, 1988; COL 
Gerald E. Galloway, U.S. Army, appointed Oct. 28, 
1989: COL John P. Carey served as Secretary of the 
Commission. 
The MRC is charged, under direction of the Secretary 
of the Army and supervision of the Chief of Engineers. 
with prosecution of improvements for flood control 
of the Mississippi River and of its tributaries and 
outlets in its alluvial valley, so far as they are affected 
by Mississippi River backwater, between Head of 
Passes, LA (mile 0), and Cape Girardeau, MO (1,006 
miles AHP-Lower Mississippi mileage terminates at 
mile 954 AHP), and with prosecution of improvements 
in the interest of navigation between Cairo, IL (954 
miles AHP), and Baton Rouge, LA (234 miles AHP); 
and for stabilization of the lower 7 miles of the right 
bank of the Ohio River, to former mouth of Cache 
River. It also is charged with prosecution of certain 
flood control works on the Mississippi River and tributaries, 
as far as they are affected by backwater, 
between Cape Girardeau, MO, and Rock Island, IL 
(1,437 miles AHP), and with prosecution of improvements 
on designated tributaries and outlets below 
Cape Girardeau for flood control, navigation, major 
drainage, and related water uses. Authorized operations 
of the Commission below Cape Girardeau are conducted 
by District Engineers of New Orleans, Vicksburg, 
and Memphis Districts within the areas 
described below, in accordance with approved directives 
and programs and congressional appropriations 
therefor. 
New Orleans District: Mississippi River project levees 
and river channel stabilization as required from 
Head of Passes, mile 0 to 320 AHP, construction of 
four salinity-control structures for fish and wildlife 
enhancement in lower Mississippi River Delta region; 
Bonnet Carre' and Morganza Floodways; maintenance 
and improvements of Mississippi River navigation 
channel from Baton Rouge, LA (mile 234 AHP), to 
mile 320; Baton Rouge Harbor (Devils Swamp); navigation 
improvement of Atchafalaya and Old Rivers 
from Mississippi River to Morgan City; control of Old 
and Atchafalaya Rivers; Atchafalaya Basin Floodways; 
flood control and drainage improvements in 
Bayou Cocodrie and tributaries, in Bayou des Glaises, 
and in Upper Pointe Coupee Loop area; flood protection 
in eastern Rapides and south-central Avoyelles 
Parishes, LA; and freshwater distribution from Atchafalaya 
River to Teche-Vermilion Basins. 
Vicksburg District: Mississippi River project levees 
and river channel stabilization as required from 
upper limits of New Orleans District (mile 320 AHP) 
in vicinity of Black Hawk, LA, to Coahoma-Bolivar 
County line, MS (mile 620 AHP) on left bank, and 
to vicinity of mouth of White River, AR (mile 599 
AHP), on right bank including south bank Arkansas 
River levee to vicinity of Pine Bluff, AR, and north 
bank levee to vicinity of Tucker on left bank of Plum 
Bayou, AR; bank stabilization in lower 36.1 miles of 
Arkansas River; maintenance and improvement of 
Mississippi River navigation channel between miles 
320 and 599 AHP; Vicksburg and Greenville Harbors; 
specific fish and wildlife facilities in Tensas, 
Yazoo, and Big Sunflower Basins; a demonstration 
erosion control project in the Yazoo Basin; flood control 
and drainage improvements in Red River backwater 
area including leveed portions east and west 
of Black River and south of Red River; Jonesville, 
LA, Boeuf and Tensas Rivers, Bayou Macon Basins 
and tributaries, AR and LA, and Bayou Lafourche, 
LA; Yazoo River Basin, MS, including backwater 
area; Big and Little Sunflower Rivers, Deer Creek, 
and Steele Bayou, MS; and Grand Prairie Region 
and Bayou Meto Basin, AR, including provision for 
agricultural water supply. 
* Authorizing legislation (Tables 42-D and 42-E) is listed at the end of this chapter. All other tables are referenced in text and also appear at the end 
of this chapter. 
42-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
Memphis District: Mississippi River project levees 
and river channel stabilization as required, from 
upper limits of Vicksburg District to north bank 
of Little River diversion channel, MO (1,003 miles 
AHP), a few miles below Cape Girardeau, MO, on 
right bank, and to Cache River diversion channel (967 
miles AHP) above Cairo, IL, on left bank, including 
levees and revetment on right bank of Ohio River, in 
Mounds-Mound City area, IL; except operations above 
Cairo, IL, do not include channel stabilization on the 
Mississippi River. Maintenance and improvement of 
Mississippi River navigation channel between mile 
599 and 954 AHP and of Memphis Harbor, TN; specific 
fish and wildlife facilities in St. Francis Basin; 
levees in White River backwater area up to vicinity 
of Augusta, AR, and a pumping plant near mouth of 
White River; levees and pumping plants at De Valls 
Bluff and Des Arc, AR; channel improvements in 
Cache River Basin, AR; channel improvements in Big 
Creek and tributaries, AR; improvement works in St. 
Francis River Basin, MO and AR, including backwater 
area improvements in Belle Fountain Ditch and 
Drainage District No. 17, AR; Little River diversion 
channel, MO, and L'Anguille River, AR; Wolf River 
Basin, TN; Obion and Forked Deer River Basins, TN; 
Reelfoot Lake area, including channel improvement 
for Bayou du Chien and Lake No. 9, TN and KY; West 
Kentucky tributaries, KY; Mud Lake pumping station, 
TN; and pumping plants and outlet structures 
in the Cairo-Mounds-Mounds City area, IL. 
Field operations of the commission restricted to 
levee construction under Sec. 6, 1928 Flood Control 
Act (local interests contributing one-third of costs and 
furnishing rights-of-way) are conducted within the following 
limits by two districts reporting directly to the 
Commission on matters within their jurisdiction--St. 
Louis District: Mississippi River (Sec. 6) levees from 
upper limits of Memphis District to Clemens Station, 
MO (1,254 miles AHP), on right bank, and Hamburg 
Bay, IL (1,215 miles AHP), on left bank, and Illinois 
River from its mouth to mile 120 at Havana, IL. Rock 
Island District: Mississippi River (Sec. 6) levees from 
upper limits of St. Louis District to Rock Island, IL 
(1,437 miles AHP). For work accomplished see Table 
42-N. page 42-50, Annual Report for 1975. 
MISSISSIPPI RIVER AND 
ALLUVIAL VALLEY BELOW 
CAPE GIRARDEAU, MO 
Location and description. The Mississippi River 
rises in Lake Itasca, MN, and flows generally southerly 
for 2,340 miles through the central portion of 
United States to empty into the Gulf of Mexico 115 
miles below New Orleans. It is improved for barge navigation 
for 1,832 miles to Minneapolis, MN. The Mississippi 
River and its major tributaries, the Missouri, 
Ohio, St. Francis, White, Arkansas, Yazoo, and Red- 
Old Rivers, drain 1,245,000 square miles in all or part 
of 31 states between the Rocky and Appalachain 
Mountains and part of two Canadian provinces. Below 
Cape Girardeau, MO, 53 miles above Ohio River, river 
bottomlands widen abruptly into an alluvial valley of 
35,460 square miles which was originally subjected to 
flood overflow. A major part of the alluvial valley has 
been protected from floods by levees which confine 
floodflows within a floodplain having an average 
width of 5 miles. (See map of alluvial valley of Mississippi 
River, scale 1:500,000.) Observations made by 
Mississippi River Commission to Sep. 30, 1982, show 
approximate all-time maximum and minimum discharges 
between levees as follows: Cairo to White 
River, 2,000,000 and 70,000 cubic feet per second; 
thence to Red River, 2,150,000 and 90,000 cubic feet 
per second; thence to the Gulf of Mexico, 1,500,000 
and 50,000 cubic feet per second in Mississippi River 
and 660,000 and 11,000 cubic feet per second in Atchafalaya 
River. As the 1927 floodflow was not confined 
between levees, maximum discharges recorded do not 
include entire flow of the 1927 flood, maximum of record 
below White River. High water and flood stages 
usually occur in late winter or early spring, but great 
floods such as that of 1937 occurred as early as January. 
Low water stages generally prevail from August 
to December. Extreme all-time ranges in stages 
recorded at representative gages (rounded to nearest 
foot) are 60 feet at Cairo, 49 feet at Memphis, 57 feet 
at Red River Landing, and 21 feet at New Orleans 
(Carrollton). The river is nontidal above Red River 
Landing where tidal amplitude rarely exceeds 0.1 foot 
during extreme low water. 
Previous projects. For details see page 1944, 
Annual Report for 1932. 
Existing project. The Mississippi River and Tributaries 
Project in the alluvial valley between Head of 
Passes, LA, and Cape Girardeau, MO, provides protection 
from floods by means of levees, floodwalls, floodways, 
reservoirs (in Yazoo and St. Francis Basins), 
bank stabilization, and channel improvements in and 
along the river and its tributaries and outlets insofar 
as affected by backwater of Mississippi River, including 
levee work on the main stem between Cape 
Girardeau and Rock Island. When completed, 23,621 
square miles will be protected from the Mississippi 
River project flood. The project also provides for a 12- 
by 300-foot navigation channel between Baton Rouge, 
LA, and Cairo, IL; for salinity-control structures; and 
for channel realinement and improvement including 
bank stabilization and dikes to reduce flood heights, 
control natural tendency of river to lengthen by meandering, 
and protect levees from being destroyed by caving 
banks. Locations of major main stem Mississippi 
River improvements are shown in Table 42-A and 
those for off-main stem tributaries are shown in Table 
42-B. Pertinent data on dams and lakes are shown in 
Table 42-C. Authorizing and incorporating legislation 
are shown in Tables 42-D and 42-E. Summary of presently 
estimated Federal cost of authorized improvements 
is shown in Table 42-F. Construction of the existing 
project began in 1928 and has continued 
throughout ensuing years. Based on the estimated 
cost of $15,418,030,000 (cost projected through the 
42-2

MISSISSIPPI RIVER COMMISSION 
construction period), and actual expenditures through 
Sep. 30, 1989, of $4,708,611,338, the entire project is 
about 77.9 percent complete. 
Recommended modifications. None. 
Local cooperation. The Flood Control Act of 1928, 
as amended, applies. Such requirements have, in 
general, been complied with by local interests. 
Terminal facilities. See Port Series No. 21, 
1979/1982, for Ports of Baton Rouge and Lake Charles, 
LA; Port Series No. 20, 1981, for Port of New 
Orleans, LA; also folio of Flood Control and Navigation 
Maps of Mississippi River from Cairo, IL, to the 
Gulf of Mexico (56th edition), 1988. 
Project cost. Total allotted for flood control, excluding 
maintenance charges through Aug. 18, 
1941, chargeable under authorizations to Sep. 30, 
1989, was $4,759,777,837. (See Table 42-S.) (See also 
Tables 42-R, 42-T, and 42-U for additional financial 
statements. 
Operations and results during fiscal year. Commission 
activities: 
The 333rd Session was held Apr. 17-21, 1989, on 
board the Motor Vessel MISSISSIPPI enroute on the 
Mississippi River from Cairo, IL, to New Orleans, LA. 
Bank protection works, levees, and channel conditions 
were observed enroute. Public meetings were held at 
Cairo, IL; Memphis, TN; Vicksburg, MS; and New 
Orleans, LA, with approximately 190 people in attendance. 
This session adjourned at New Orleans, LA; at 
10:00 a.m., Apr. 21, 1989. 
The 334th Session was held Sep. 11-15, 1989, on 
board the Motor Vessel MISSISSIPPI enroute on the 
Mississippi River from Cairo, IL, to Morgan City, LA. 
Bank protection works, levees, and channel conditions 
were observed enroute. Public meetings were held at 
Cairo, IL; Memphis, TN; Greenville, MS; and Morgan 
City, LA, with approximately 190 people in attendance. 
This session adjourned at Morgan City, LA, at 
10:40 a.m. on Sep. 15, 1989. 
Records of Proceedings of all sessions of the Mississippi 
River Commission are on file in the office of the 
President. 
Alluvial Valley Mapping 
General. Contoured quadrangles and general maps 
of the alluvial valley are available for departmental 
use and public distribution under prescribed regulations. 
Preparation, revision, and publication of quadrangle 
maps (scale 1:62,500) continued. Roadmap-type 
information brochures of principal portions of the overall 
project were published along with pamphlets on 
the subject of flood control and navigation. Maps and 
supplemental data sheets for active works were 
updated and published as required. 
The 1988 (56th) edition of the folio of flood control 
and navigation maps (scale 1:62,500) covering 
the Mississippi River from Cairo, IL, to the Gulf of 
Mexico was revised and printed. The 1983-85 hydrographic 
survey of the Mississippi River (scale 1:20,000) 
was revised and reprinted. 
Approximately 5,046 flight-line miles of blackand-
white aerial photography (various scales); 1,450 
flight-line miles of color photography; and about 228 
hours of oblique photography were flown along the 
Mississippi River and tributaries in the New Orleans, 
Vicksburg, and Memphis Districts. 
Work accomplished in the Districts: New Orleans 
District--The revision of Bonnet Carre, LA; Lac Des 
Allemands, LA; Napoleonville, LA; St. Bernard, LA; 
White Castle, LA; and Ysclosey, LA, quandrangle 
maps, 1:62,500 scale, were completed and will be 
printed in 1989. The 1989 (2nd) edition folio of flood 
control and navigation maps (scale 1:24,000) covering 
the Atchafalaya River was printed. The 1986-88 hydrographic 
survey of the Atchafalaya River 1:10,000 scale 
was completed and printed. 
Memphis District--Series conversion of U.S. Geological 
Survey 1:24,000-scale to 1:62,500-scale quads of 
Dee, Melwood, Latour, Jonesboro, Vanndale, Wynne, 
Whitmore, Puxico, Park Place, Dyersburg, Halls, and 
Reelfoot Lake are complete. 
Vicksburg District--Series conversion of U.S. Geological 
Survey 1:24,000-scale quadrangles to 
1:62,500-scale quadrangles of McGehee, AR; Lake Village, 
AR; Eudora, AR; Wesson, AR; Potts Camp, MS; 
Denmark, MS; Bogalusa, LA; Sun, LA; Oden, AR; 
Athens, AR; Collinston, LA; Mangham, LA; Calvin, 
LA; Ashland, LA; Coushatta, LA; and Mansfield, LA; 
is in progress. Eva, LA; Monterey, LA; Jonesville, LA; 
Ferriday, LA; Harrisonburg, LA; Sicily Island, LA; 
Moreauville, LA; Marksville, LA; Colfax, LA; Jena, 
LA; Pollock, LA; Tullos, LA; Olla, LA; Fort Necessity, 
LA; Winnsboro, LA; Louann, AR; St. Joseph, LA-MS; 
Montgomery, LA; Provencal, LA; Campti, LA; Picayune, 
MS; Sumner, MS; Walthall, MS; and Pittsboro, 
MS were printed. 
Floods 
Streamflow observations during the fiscal year 
follow: 
Memphis District--Mississippi River crest stage of 
46.7 feet at Cairo gage on Feb. 25, 1989, and maximum 
discharge of 1,101,600 cubic feet per second, 
occurred on Feb. 26, 1989, at Hickman, KY and crest 
stage of 30.5 feet at Memphis on Mar. 1, 1989, with 
maximum discharge of 1,198,400 cubic feet per second 
on Mar. 1, 1989. 
Vicksburg District--Flooding was widespread 
from January through July in the Vicksburg District 
during FY 89. Peak stages and discharges on 
the Vicksburg District's reach of the Mississippi 
River were as follows: Arkansas City, 34.9 feet on 
Mar. 8, 1989, and maximum discharge of 1,380,000 
cubic feet per second; Vicksburg, 41.0 feet on Mar. 
9, 1989, and maximum discharge of 1,400,000 cubic 
feet per second; and Natchez, 48.0 feet on Mar. 10, 
1989, and maximum discharge of 1,400,000 cubic 
feet per second. 
42-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
New Orleans District--On the Mississippi River, the 
Red River Landing gage recorded a maximum stage 
of 52.20 feet NGVD on Mar. 11, 1989, and the New 
Orleans gage recorded a maximum stage of 14.77 feet 
NGVD on Mar. 13, 1989. On the Atchafalaya River, 
the Simmesport gage recorded a maximum stage of 
34.49 feet NGVD on Mar. 10, 1989. 
Studies and Investigations 
General investigations. Surveys and reports, authorized 
by laws and by Senate and House Public Works 
Committee resolutions, were made as required. Collection 
and study of basic data continued. No requests 
were received for modifications of the existing project, 
Mississippi River and Tributaries, authorized by the 
Flood Control Act of May 15, 1928, as amended (see 
Table 42-D). 
Reelfoot Lake, TN and KY, Reconnaissance Report 
including a negotiated cost sharing agreement and 
scope of feasibility studies was submitted to the Assistant 
Secretary of the Army (Civil Works) for certification 
on Aug. 17, 1988. The report identified three 
economically feasible plans of improvement which, to 
differing degrees, addressed flood control, sediment 
control, water quality, water supply, fish and wildlife 
preservation and enhancement, recreation, regional 
development, and allied concerns of the area. On 
December 20, 1988, the Office of the Chief of Engineers 
determined that further Corps participation in 
a cost-shared feasibility study was not advisable at 
this time. As a result, certification of the reconnaissance 
report was not received. 
Engineering studies. A research program was continued 
for development of materials and more effective 
and economical design of regulation features for 
placing and stabilizing the Mississippi River in a suitable 
alinement. 
Potamology investigations of river behavior continue 
to be made. Investigations into the major causeand-
effect relationships attributable to major changes 
in stage-discharge relationships on the Mississippi 
River as a result of both natural and man-made modifications 
are continuing. 
Mississippi River and Tributaries--Levees 
Operations and results during fiscal year. This 
feature consists of construction of new, and enlargement 
of existing, levees to approved grade and section; 
construction and restoration of levee berms; and construction, 
repair, and maintenance of roads on levees. 
Work accomplished is summarized in Table 42-N and 
further broken down as follows: 
New Orleans District--Enlarged 24.7 miles of levees 
and surfaced 9.2 miles of roads on levees in the Main 
Stem System. See Table 42-K. 
Vicksburg District--Completed 7.3 miles of berms 
and levees in the Main Stem System. See Table 42-L. 
Memphis District--Constructed 0.4 miles of levee 
extension, completed 0.8 miles of berms, and surfaced 
0.4 miles of roads on levees in the Main Stem System. 
See Table 42-M. 
Condition as of Sep. 30. (See Tables 42-K, 42-L, 
42-M, and 42-N.) There are 1,608.7 miles of levees 
authorized for the Mississippi River below Cape Girardeau, 
of which 1,601.9 are in place with 1,211.0 built 
to approved grade and section. The Main Stem Levee 
System consists of 2,201.5 miles, of which 2,195.7 are 
in place with 1,673.3 miles completed to approved 
grade and section. Included in this system are additional 
levees and structures along the south bank of 
Arkansas River (85.4 miles); along the south bank of 
Red River (59.2 miles, with 59.2 completed); and 449.2 
miles in the Atchafalaya River Basin, with 449.2 in 
place with 317.7 completed to grade and section (see 
Table 42-N). Of the authorized 671.9 miles of berms, 
515.3 are complete. Graveled or hard-surfaced roads 
have been constructed on 1,862.5 miles of these levees. 
There are an additional 1,608.2 miles of authorized 
tributary levees in the MR&T Project, of which 
1,120.0, are in place with 906.0 to approved grade and 
section. Berms have been completed on 9.8 miles and 
844.7 miles of graveled or hard-surfaced roads have 
been constructed on the levees. 
For last summary of levee work accomplished 
under Sec. 6, 1928 Flood Control Act, see Table 42-N, 
page 42-50, Annual Report for 1975. 
Mississippi River and Tributaries-- 
Channel Improvements 
Operations and results during fiscal year. 
Dredging: Mississippi River Main Stem--(See Table 
42-G.) Work included dredging 51,904,300 cubic yards 
for maintenance of channel and harbor improvements. 
Minimum channel depth of 9 feet was maintained. 
Dredging was done with the following plant: New 
Orleans District, channel maintenance was performed 
by Government-owned dustpan dredge Jadwin. 
Vicksburg District, channel maintenance was performed 
by Government-owned dustpan dredge 
Jadwin and contract dredge Lenel Bean. The MR&T 
harbors, in the Vicksburg District, maintained were 
Greenville and Vicksburg by leased cutterhead 
dredge Natchez. Memphis District channel maintenance 
dredging was performed by Government-owned 
dustpan dredge Burgess, and leased dustpan dredge 
Lenel Bean. 
The MR&T Harbor maintained was Memphis Harbor 
(McKeller Lake), by leased cutterhead dredges 
Natchez, Fritz Jahncke, and Missouri H. 
Bank revetment and dikes: (See Table 42-H, 42-I, 
and 42-J.) Construction of 21.84 miles of new bank 
revetment and 150,733 squares of concrete mattress, 
for maintenance, along the Mississippi River was completed 
by Government plant and hired labor. Also, 
4.42 miles of new dikes were constructed and 0 miles 
required for maintenance. 
The Ed Jones boat ramp was completed as a recreational 
facility on Obion-Tamm Revetment in Lauderdale 
County, Tennessee. The ramp was constructed of 
42-4

MISSISSIPPI RIVER COMMISSION 
articulated concrete mattress 40 feet wide and 310 
feet long. This project was cost-shared on a 50-50 basis 
with Tennessee Wildlife Resources Agency, the non- 
Federal project sponsor. 
No work was performed on tributaries. 
Other work performed in the interest of navigation, 
supplementing maintenance dredging on Mississippi 
River between Cairo, IL, and Baton Rouge, LA, 
included removal of snags, wrecks, and obstructions;. 
issuance of bulletins by the Vicksburg District providing 
information on available high-water velocities at 
selected locations; maintenance of bulletin boards 
showing daily gage readings at regular MRC gages; 
and contact pilot service furnishing navigation interests 
with latest information and advice on channel conditions 
and navigation interests. Cost of this work is 
given in Table 42-R. 
Condition as of Sep. 30. In carrying out authorized 
channel improvement program between Baton Rouge 
and Cairo, 16 cutoffs were developed between 1933 
and 1942. These, combined with chute channel development 
and alignment improvements, decreased channel 
length between these cities by about 170 miles. 
However, current velocities increased the attack on 
the banks and the river began to regain its length. As 
a result, the net shortening between 1933 and 1962 
was 114 miles of the theoretical 170-mile cutoff. 
There are now in place 920.99 miles of operative 
bank revetment and 227.60 miles of dikes on the lower 
Mississippi River. This amount of channel stabilization 
should prevent the river from regaining much 
more of its length due to meandering. A navigation 
channel 9 by 300 feet is being accomplished by revetment 
and dikes and maintained by dredging as 
required during the low- water season. Due to growing 
effectiveness of channel improvement program, 
average maintenance dredging requirements are 
steadily being reduced, and an increase in navigable 
depth is being obtained. Approximately 99.8 miles of 
foreshore protection have been constructed along the 
lower Mississippi River. 
There are 68.91 miles of revetment and 5.2 miles 
of dikes on tributary channels as listed in Tables 42-H, 
42-I, and 42-J. 
New Orleans District 
ATCHAFALAYA BASIN, LA 
Operations and results during fiscal year. New 
work by hired labor: Real estate activities and planning 
for construction were continued. 
New work by contract: Construction of floodside 
and landside berms and levee enlargement continued 
on the east and west protection levees. Two contracts 
on the west protection levee were completed over a distance 
of 6.0 miles with placement of 415,000 cubic 
yards; and on the east protection levee, one contract 
was completed over a distance of 6.2 miles with placement 
of 2,500,000 cubic yards. On the west protection 
levee one all-earth levee, totaling 6.7 miles, is under 
construction with placement of 580,000 cubic yards 
during this period. On the east protection levee 10.4 
miles of levee enlargement and floodside and landside 
berms are under construction with placement of 
1,730,000 cubic yards during this period. A contract 
for construction of the Blue Pointe Chute and American 
Pass channel training weirs was completed with 
placement of 120,000 tons of rock. 
Maintenance by hired labor: Operation and maintenance 
of Bayou Boeuf, Berwick, and Bayou Sorrel 
Locks, Morganza Control Structure, the West Atchafalaya 
Basin protection levee borrow pit, and numerous 
drainage structures as required, condition and 
operation studies, and water control management. 
Maintenance dredging was performed, resulting in 
the removal of 2,548,970 cubic yards by one leased cutterhead 
dredge from Berwick Bay harbor between 
March and August 1989; and removal of 117,212 cubic 
yards by leased cutterhead dredge from Three Rivers 
during August and September 1989. 
Conditions as of Sep. 30. Construction was 
initiated Aug. 7, 1929, with commencement of the 
west protection levee from Bordelonville to Hamburg, 
LA. The project is 85.5 percent complete. The current 
estimated Federal cost is $1,462,000,000 and non- 
Federal cost is $8,000,000. Of the 449.2 miles of levees 
and floodwalls authorized for the Atchafalaya system, 
317.7 miles are built to grade. See Table 42-K for 
status of levees. 
Major items remaining to be completed include completion 
of levees to grade and section, channel training 
works in the lower basin, realignment of the principal 
distributaries of the Atchafalaya River, and construction 
of two freshwater distribution structures. Approximately 
37.4 miles of bank stabilization have been 
placed as shown in Table 42-H. 
BATON ROUGE HARBOR 
(DEVILS SWAMP), LA 
Condition as of Sep. 30. Construction of the first 
2.5 miles of the proposed 5.0 miles of channel was 
initiated in January 1958 and completed in July 1959, 
with 7,458,086 cubic yards excavated. 
The project is 16 percent complete, based on the current 
estimated Federal cost of $699,200 and cash contributions 
of $650,000. Completion of the remaining 
2.5 miles is dependent on economic justification by 
developments on the initial channel. 
BAYOU COCODRIE AND TRIBUTARIES, LA 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of water control 
management. 
Condition as of Sep. 30. Construction was initiated 
in June 1946 and is 57 percent complete, based on the 
current estimated Federal cost of $20,400,000 and 
42-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
non-Federal cost of $323,000. See page 2031, Annual 
Report for 1961, for description of completed work. 
Work required to complete the project consists of 
enlargement of 13.5 miles of upper Bayou Boeuf, channel 
improvement of 25.3 miles of Bayou Cocodrie, 
enlargement of Bayou Courtableau from Washington, 
LA, to the west protection levee, and additional culverts 
through the west protection levee at 100 percent 
Federal cost in lieu of the previously authorized 
diversion channel from Washington to the Bayou 
Courtableau drainage structure. 
With the termination of the Eastern Rapides and 
South Central Avoyelles project, it has become necessary 
to provide an adequate outlet structure solely for 
the Bayou Cocodrie and Tributaries project. The economic 
effects of this change along with current benefits 
estimates have caused the benefit-cost ratio for 
the project to be less than unity. As a result, the project 
has now been classified as "inactive." If economic 
conditions change, the project could be reactivated. 
BONNET CARRE' SPILLWAY, LA 
Operations and results during fiscal year. Maintenance 
by hired labor: Condition and operation studies, 
water control management, and ordinary maintenance 
of the control structure and spillway 
continued. 
Condition as of Sep. 30. Construction of the 
spillway was initiated in Fiscal Year 1929. The 
control structure was completed in 1931, levees were 
completed in 1932, and utility crossings were completed 
in 1936. The cost of the completed work is 
$14,212,200. 
It was necessary to operate the structure to reduce 
flood stages in 1937, 1945, 1950, 1973, 1975, 1979, and 
1983. 
OLD RIVER, LA 
Operations and results during fiscal year. Maintenance 
by hired labor consisted of operation and maintenance 
of the lock and control structures as required, 
condition and operation studies, water control management, 
maintenance of cleared areas, levee shaping, 
operation of a picket boat at the inflow channels to the 
low-sill and auxiliary control structures, and engineering 
studies. 
Maintenance by contract: In September 1989, 
104.490 cubic yards of shoal were dredged from the 
lock forebay. 
Condition as of Sep. 30. Construction began September 
1955 and is complete at a Federal cost of 
$301,300,000. Principal items completed are as follows: 
Low-sill structure, June 1959; overbank structure, 
October 1959; auxiliary structure, September 
1986; levees and levee enlargements, October 1963; 
inflow and outflow channels for the low-sill structure, 
February 1961; inflow and outflow channels for the 
auxiliary structure, August 1987; navigation lock completed 
December 1962 and opened to navigation 
March 1963, at which time Old River was closed to 
navigation with a rock and earthfill dam; highway 
approaches and bridge over the lock completed March 
1965. Approximately 9.4 miles of bank protection 
have been constructed at the inflow and outflow channels. 
(See Table 42-H for details of bank protection.) 
Vicksburg District 
TENSAS BASIN, AR AND LA 
Operations and results during fiscal year. 
(a) Boeuf and Tensas Rivers, and Bayou Macon, 
AR and LA. Planning and design on project features 
are complete. The Lake Chicot Pumping Plant and 
related features are complete and in operation. The riverside 
gate repair contract awarded August 26, 1988, 
is continuing and a contract for the bulkhead gate 
repairs was awarded August 18, 1989. A third contract 
for pump repairs at the pumping plant is scheduled 
for award the first quarter of FY 90. 
(b) Red River backwater area. Planning and 
design continued on project features. All channel 
work required to get flows to the Tensas Cocodrie 
Pumping Plant and gravity structure is complete. The 
gravity structure and the pumping plant are complete 
and are being operated and maintained by contract. 
One mitigation item, the construction of two water control 
weirs, was completed in May 1988. Contracts for 
three additional mitigation features were awarded in 
December 1988 and February 1989. Planning and 
design continue on the two remaining mitigation features. 
Tensas-Cocodrie, Item 4-A, levee enlargement, 
6.3 miles in length, was completed in September 1988. 
Construction of Item 4-B was initiated Sep. 27, 1988, 
on 2.4 miles of levee enlargement and a contract for 
Item 2 is scheduled for July 1990. These contracts will 
complete the levee enlargement for the remaining 
12.7 miles of the levee system. 
Fool River Bayou Pumping Plant has been 
awarded to Fromherz Engineering. The FDM for this 
feature is scheduled to be complete September 1990. 
Work on the Below Red River Phase II GDM has been 
delayed pending economic justification. 
Condition as of Sep. 30. 
(a) Beouf and Tensas Rivers, and Bayou Macon, 
AR and LA. Channel improvement has been accomplished 
on 741.7 miles of project streams, providing 
major drainage outlets for the tributary areas. Additionally, 
61.0 miles of the Tensas River has been 
cleared and snagged. The GDM for the Tensas River 
Project, above mile 61, including Mill Bayou-Bayou 
Vidal is complete pending approval and resolution of 
review comments. 
(b) Red River backwater area. Levees in Tensas- 
Cocodrie area are complete except for levee raising of 
12.7 miles. The work comprised 93.1 miles of new 
levee, excluding 2.1 miles of high ground where no 
42-6

MISSISSIPPI RIVER COMMISSION 
levees are required, and 86.9 miles of gravel road on 
levees. Work is underway on an item of levee raising 
consisting of 2.4 miles. Construction of 63.4 miles of 
levee, Larto Lake to Jonesville levee system, has been 
completed. A levee grade reevaluation study for all 
levee systems in the Red River Backwater area was 
completed in Mar. 1985. Based on results of that 
study, work is underway to complete enlargement of 
the Tensas-Cocodrie levee system. Levee Item 4-A has 
been completed, and levee Item 4-B has been 
awarded. Levee work on Sicily Island area consists 
of 56 miles of new levee, 4 miles of which have been 
completed. 
LOWER ARKANSAS BASIN, AR 
Condition as of Sep. 30. Arkansas River levees. 
A total of 56.2 miles of the 61.5 miles of north bank 
levees and all of the 85.4 miles of south bank levees 
have been completed to approved grade and section. 
These levees above mile 36.1 are protected by bankprotection 
works constructed as a feature of project 
for Arkansas River and tributaries, AR and OK. For 
present status of this work, see report of Little Rock 
District. Below mile 36.1, needed bank protection is 
constructed with project maintenance funds. Big 
Bayou Meto gates and lifting mechanism were 
replaced during FY 88. 
YAZ00 BASIN, MS 
Operations and results during fiscal year. 
(a) Yazoo City and Belzoni protection works. 
Contract forces continued operation and maintenance 
of levees, drainage facilities, and pumping plant. 
(b) Greenwood protection works. Contract forces 
continued operation and maintenance of pumping 
plant, levees, and drainage facilities. 
(c) Main stem. Construction of the Bee Lake Drainage 
Structure is complete. Levee closure at Bee Lake 
is scheduled for award in FY 90. 
Contract forces continued operation and maintenance 
of channels, levees, and drainage facilities. 
(d) Big Sunflower River, etc. A contract was 
awarded Oct. 31, 1986, on Item 66-A, Steele Bayou 
Channel Improvement, Miles 63.0 to 68.7. The next 
item of work is scheduled for award in December 
1989. 
(e) Tributaries. Construction: (1) Levees. Levee 
work associated with the last item of work on 
Ascalmore-Tippo Project is complete. Levee work associated 
with Item 1 and Item 1-A Pelucia Creek is complete. 
Construction of the next item of work at Pelucia 
Creek, Item 2, is scheduled for award in February 
1990. 
(2) Channels. An award for construction of the 
Alligator-Catfish, Round Lake, Water Control Structure 
was awarded Mar. 31, 1989. Construction on 
the remaining channel work on the Ascalmore-Tippo 
Project is complete. 
Contract forces continued operation and maintenance 
of channels, levees, and drainage facilities. 
(f) Enid Lake. (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Rehabilitation of boat channels and snagging 
and clearing of tributary streams in the lake area continued. 
Maximum pool elevation in the lake was 
241.59 feet NGVD on Sep. 30, 1988, when storage in 
the flood control pool was 156,300 acre-feet. Peak 
24-hour inflow was 13,300 cubic feet per second on 
Jan. 19, 1988. On Sep. 30, 1988, pool elevation was 
241.59 feet NGVD and storage in the flood control 
pool was 156,300 acre-feet. 
(g) Grenada Lake. (See Table 42-C.) Construction 
of remaining public-use facilities has been deferred 
pending development of cost-sharing agreements with 
local interests for construction and non-Federal operation 
and maintenance, consistent with projects for 
which recreation facilities are being constructed 
under the provisions of the Federal Water Project Recreational 
Act of 1965 (Public Law 89-72), as amended. 
Maximum pool elevation in the lake was 205.40 feet 
NGVD on Sep. 25, 1988, when storage in the flood control 
pool was 273,100 acre-feet. Peak 24-hour inflow 
was 7,050 cubic feet per second on Jan. 20, 1988. On 
Sep. 30, 1988, the pool elevation was 205.32 feet 
NGVD and storage in the flood control pool was 
271,400 acre-feet. 
Construction of a levee to provide protection to the 
community of Coffeeville from high Grenada Lake 
stages was begun in FY 82. In addition to the levee, 
other features of Coffeeville project include: three 
drainage structures through the levee; portable 
pumps; area rehabilitation; and raising of a town 
street. Construction of the levee and two of the drainage 
structures was completed in FY 82. The remaining 
feature of the Coffeeville project was completed 
in early FY 84. 
(h) Sardis Lake (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Clearing of tributary streams in the lake area 
continued. Maximum pool elevation in the lake was 
252.46 feet NGVD on Sep. 26, 1988, when storage in 
the flood control pool was 395,300 acre-feet. Peak 
24-hour inflow was 16,300 cubic feet per second on 
Jan. 21, 1988. On Sep. 30, 1988, the pool elevation was 
251.98 feet NGVD and storage in the flood control 
pool was 383,300 acre-feet. An 8-mile reach of the Little 
Tallahatchie River from Sardis Dam to Highway 
51 was clogged with sediment restricting releases 
from the lake. This reach has been dredged to restore 
the design capacity of the river. Six disposal sites 
were selected, located in upland hill areas to reduce 
the adverse impact on prime agricultural lands along 
the river and still be in compliance with environmental 
laws and regulations. Dredging was completed 
in August 1982. Sardis Lower Lake Weir was 
awarded May 10, 1989, and is approximately 71 percent 
complete. 
(i) Arkabutla Lake. (See Table 42-C.) The dam 
and appurtenant structures were maintained and 
42-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
operated. Clearing of tributary streams in the lake 
area was continued. Maximum pool elevation in the 
lake was 241.03 feet NGVD on Jul. 5, 1989, and storage 
in flood control pool was 622,700 acre-feet. Peak 
24-hour inflow was 51,600 cubic feet per second on 
Jul. 2, 1989. On Sep. 30, 1989, the pool elevation was 
221.80 feet NGVD, and storage in the flood control 
pool was 146,200 acre-feet. 
(j) Yazoo Basin backwater. The Yazoo area backwater 
levees are complete, including the backwater 
levee from the Mississippi River levee to the west 
levee of the lower Auxiliary Channel, the Little Sunflower 
River drainage structure, and the connecting 
channel from the Steele Bayou drainage structure to 
the Big Sunflower River. A Phase I GDM was completed 
in FY 82 which addresses rural flooding from 
ponded runoff inside the backwater levee. A GDM for 
a pumping station of 17,500 cfs to reduce this ponding 
was approved Jul. 12, 1985. Later budgetary guidance 
reduced the pumping plant capacity to 10,000 cubic 
feet per second. A contract for portions of the inlet 
and outlet channel excavation for the pumping plant 
has been completed. A construction schedule for the 
remaining project features is dependent upon the 
local sponsor meeting the cost sharing requirements 
specified in the Water Resources Development Act of 
1986. 
The Satartia area backwater levee is complete. 
Rocky Bayou area levee Item IA was completed 
November 1987. Item lB was awarded in November 
1986. Completed backwater levees will require raising 
to provide the degree of protection intended based on 
the project design flow line developed for the Mississippi 
River following the 1973 flood. 
Four Greentree Reservoirs and pumping stations 
are now complete. A decision on construction of 
the remaining reservoirs will be made in the future 
after the U.S. Forest Service has had a substantial 
period of time to monitor the operation of the existing 
facilities. 
(k) Upper Yazoo Projects. The first eight items of 
channel improvement, approximately 56 miles, and 
two drainage structures have been completed. This 
work extends from Yazoo City, MS, to about 15 miles 
upstream of Belzoni, MS. 
A contract for the next item of work, levee and 
channel Item 3A-1, was awarded May 2, 1988. East 
Hollie Lake Drainage Structure located about 18 
miles north of Belzoni was awarded March 17, 1988. 
Mosquito Lake Drainage Structure, located about 11 
miles south of Greenwood, was awarded Apr. 20, 
1989. 
The Fort Pemberton Flood Control Structure is 
under construction and will be completed early FY 
90. Planning is continuing on upstream channel and 
levee work. 
(1) Streambank erosion control. Construction of 
the following projects has been completed: Tillatoba 
and Hunter Creeks, Items 1 and 2; Hunter Creek, 
Item IA; South Fork Tillatoba Creek, Items 5A and 
5B; North Fork Tillatoba Creek, Items A and 3A; Batupan 
Bogue, Items 4A, 4A-1, and 4A-2; Perry Creek, 
Items 6A and 6B; Johnson Creek, Items 9A, 9B, and 
vegetative treatment, Item 12; Goodwin Creek, Items 
8A, 8B, and 8C; and Hotopha Creek, Item 7. 
All construction under this feature is complete. and 
a final report was submitted to the Secretary of the 
Army Jan. 5, 1982. All work constructed has been 
turned over to the local sponsors for operation and 
maintenance except for the instrumented system on 
Goodwin Creek where the structures were retained 
for possible future studies. The Demonstration Erosion 
Control Project (DEC), a joint project with the 
USDA Soil Conservation Service was initiated by FY 
85 appropriations as a continuation on streambank erosion 
control efforts. The purpose of the project is to 
demonstrate the applicability of a systems approach 
to the design of erosion, sedimentation, and flood control 
works by applying this approach to six demonstration 
watersheds in the Yazoo Basin hill area. 
Condition as of Sep. 30. The first feature of Yazoo 
Basin project was started in 1936, and the total project 
is about 35 percent complete. A total of 50.9 miles 
of backwater levee has been completed to the interim 
grade. The ongoing Yazoo Basin Comprehensive 
Study will address other water resources problems 
and needs in the area to include urban and rural flood 
damage prevention, hydropower, and water supply. 
During FY 88, work continued in the DEC toward 
development of the systems plans and implementation 
of a monitoring program. The District completed the 
construction of 11 grade control structures; 32,500 linear 
feet of bank stabilization; and 4.1 miles of clearing, 
snagging, and debris removal. Construction was 
initiated on 2 grade control structures, 20 riser pipe 
grade control structures, and 0.3 mile of channel realignment 
and stone paving. 
LOWER RED RIVER--SOUTH BANK 
RED RIVER LEVEES, LA 
Operations and results during fiscal year. New 
work by hired labor consisted of engineering studies. 
Maintenance by hired labor consisted of water control 
management and economic studies. 
Condition as of Sep. 30. Construction was initiated 
in FY 29 and is complete. All of the 59.2 miles of levees 
authorized are completed to approved grade and 
section. 
Memphis District 
ST. FRANCIS BASIN, AR AND MO 
Operations and results during fiscal year. 
(a) Little River Drainage. Alteration of New Madrid 
County Route 282 for Ditch 281-9, awarded Apr. 
18, 1988, 95 percent complete. Channel cleanout, 
Ditches 293 and 281-9, awarded Jul. 15, 1988, 
42-8

MISSISSIPPI RIVER COMMISSION 
complete May 12, 1989. Channel cleanout, Castor 
River Item 2, Parcel 2 awarded Jul. 29, 1988, 80 percent 
complete. 
(b) Upper St. Francis River. Belle Fountain 
Ditch, alteration of Missouri State Highway NN 
Bridge awarded Jul. 16, 1986, 40 percent complete. 
State Line Ditch 29 alteration of Arkansas State Highway 
181 Bridge awarded Jul. 12, 1985, complete Feb. 
9, 1989. Upper Buffalo Creek alteration of Missouri 
State Highway 164 and N awarded Jun. 27, 1985, complete 
Jun. 17, 1988. Alteration to Arkansas State Highways 
77 and 119, Ditches 10 and 12 awarded Mar. 2, 
1987, 96 percent. Alteration of seven powerlines 
Ditches 10 and 12 awarded Feb. 24, 1987, 70 percent. 
Oak Donnick Floodway alteration of railroad bridges 
awarded Jun. 5, 1987, 95 percent complete. 
Riprap protection and Ditch 61 channel extension, 
awarded Sep. 7, 1988, 34 percent. Blackfish Bayou, 
Item 3, awarded Jun. 17, 1987, 95 percent complete. 
Highway 18-State Line, Drainage District No. 17, 
awarded Aug. 30, 1988, complete Nov. 24, 1988. 
Honey Cypress Township Bridge, Miles 8.92 and 
10.05, awarded Aug. 12, 1988, complete May 23, 1989. 
Main Ditch No. 9, County Bridge at Mile 0.79, 
awarded Aug. 29, 1988, complete May 12, 1989. 
Gravel surfacing below Highway 18, awarded Jul. 29, 
1988, complete Apr. 20, 1989. Channel enlargement, 
Ditch No. 12, awarded Apr. 25, 1988, complete Sep. 
29, 1988. Channel enlargement State Line Ditch 29 
awarded Mar. 17, 1988, completed May 5, 1989. 
Upper Buffalo Creek, Item 2, awarded Feb. 29, 1988, 
complete Oct. 26, 1988. Alteration of Missouri State 
Highway 164 Bridge, Main Ditch No. 9, awarded Jul. 
21, 1988, 70 percent complete. Belle Fountain, Channel 
Enlargement, awarded Jul. 28, 1989, 10 percent 
complete. Main Ditch 9, 2 County Bridges, Miles 2.91 
and 5.88, awarded May 30, 1989, 10 percent complete. 
Ditch 19 Extension, Bridge 33.19, awarded Oct. 31, 
1988, completed Jul. 28, 1989. 
(c) Lower St. Francis River. Ditch No. 60 at Highway 
63 channel maintenance, awarded Aug. 12, 1988, 
complete Nov. 18, 1988. Cleanout Ditch No. 251, 
awarded Mar. 24, 1988, complete Nov. 8, 1988. Repair 
work Big Lake Area Control Structure awarded Sep. 
28, 1987, complete Oct. 28, 1988. Blackfish Bayou, 
Item 3, awarded May 26, 1989, 27 percent complete. 
Below Marked Tree, Slope Restoration, Item 1, 
awarded Jun. 2, 1989, 52 percent complete. Channel 
Cleanout, Madison to Highway 64, awarded Sep. 30, 
1988, 42 percent complete. Alteration Bridge Route 
306, Blackfish Bayou, Item 3, awarded Sep. 5, 1989, 
3 percent complete. Honey Cypress Creek Channel 
Improvement, awarded May 26, 1989, 18 percent complete. 
Ditch 1, Highway 77 Scour Repairs, awarded 
Jan. 12, 1989, completed Aug. 2, 1989. 
Condition as of Sep. 30. 
(a) Little River Drainage. Project was initiated 
during 1938 and is 90 percent complete. 
(b) Upper and Lower St. Francis River and Tributaries. 
Project was initiated during 1937 and is 81 
percent complete. 
WHITE RIVER BACKWATER 
LEVEES 
Operations and results during fiscal year. 
Water service to Graham Burke Pumping Station, 
awarded Aug. 20, 1986, complete Sep. 30, 1988. Scour 
Repairs, Miles 37 and 39, awarded Apr. 17, 1989, and 
completed Aug. 10, 1989. 
LOWER WHITE RIVER 
Operations and results during fiscal year. 
(a) Augusta to Clarendon Levee. There were no 
contracts awarded or completed during the fiscal 
year. 
(b) Clarendon Levee. There were no contracts 
awarded or completed. 
Condition as of Sep. 30. 
(a) Augusta to Clarendon Levee. Project was 
initiated during 1946 and is 39 percent complete. 
(b) Clarendon Levee. Project was initiated during 
1972 and is 36 percent complete. 
CACHE BASIN, AR 
Operations and results during fiscal year. No 
contracts awarded or completed during the fiscal 
year. 
Condition as of Sep. 30. Project was initiated during 
1971 and is 4 percent complete. 
REELFOOT LAKE-LAKE NO. 9, 
TN AND KY 
Operations and results during fiscal year. Lake 
9, KY/TN, awarded May 23, 1989, 50 percent 
complete. 
Condition as of Sep. 30. Project was initiated during 
1974 and is 89 percent complete. 
WEST TENNESSEE TRIBUTARIES, TN 
Operations and results during fiscal year. 
(a) Obion River, TN. Obion Rivers channel 
improvement is 64 percent complete. 
(b) Forked Deer River, TN. Forked Deer River 
channel improvement is 85 percent complete. 
Condition as of Sep. 30. West Tennessee Tributaries 
Project is 41 percent complete. 
WEST KENTUCKY TRIBUTARIES, KY 
Operations and results during fiscal year. No contract 
awarded or completed during fiscal year. 
Condition as of Sep. 30. Project was initiated during 
1978 and is 4 percent complete. 
42-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
MISSISSIPPI RIVER LEVEES Madrid Bend, awarded Jun. 29, 1988, complete Dec. 
Operations and results during fiscal year. 20, 1988. 
R-0-5 Ac. Parcel 2, Cairo-Mound City, IL, awarded 
Dec. 18, 1987, complete Oct. 24, 1988. Levee work, CONSTRUCTION GENERAL 
Item No. L-859, Parcel No. 1, awarded Aug. 18, 
1988, 95 percent complete. Levee extension, L-895, Levee Roadway Resurfacing, L-661-R.M., awarded 
Jun. 16, 1989, completed Aug. 29, 1989. 
42-10

MISSISSIPPI RIVER COMMISSION 
TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
0-9571 Head of Passes, LA-Cairo, IL Dredging, revetment, and 
10-81 
11-25 
38 
45 
118 
81 
44-91 
81-96 
91-104 
96-279 
104-234 
127-129 
129-234 
235 
279-287 
287-303 
303-314 
314-572 
437 
437-721 
490 
537 
646 
605-666 
672-993 
The Jump-New Orleans, LA 
Baptiste Collette-Bayou Ostrica, 
LA 
Homeplace, LA 
Bohemia, LA 
Davis Pond, LA (formerly 
Myrtle Grove, LA) 
Caernarvon, LA 
Bohemia, LA-New Orleans, LA 
New Orleans, LA 
New Orleans, LA 
New Orleans-Morganza, LA 
New Orleans-Baton Rouge, LA 
Bonnet Carre' Floodway, LA 
Bonnet Carre' Baton Rouge, LA 
Baton Rouge Harbor 
Morganza Floodway, LA 
Morganza-Old River, LA 
Old River, LA control 
Old River-Cypress Creek, AR 
Vicksburg Harbor, MS 
Vicksburg-Lake View, MS 
Wilson Point, LA 
Greenville Harbor, MS 
Long Lake, Helena, AR 
Henrico-Helena, AR 
St. Francis River-Commerce, 
MO 3 
contract work 
Main line levee, right bank 
Local levees, left bank 
Salinity control structure, right 
bank 
Salinity control structure, left 
bank 
Salinity control structure, right 
bank 
Salinity control structure, left 
bank 
Main line levee and floodwall, 
left bank 
Main line levee, right bank 
Main line levee and floodwall, 
left bank 
Main line levee, right bank 
Main line levee, left bank 
Regulating spillway, left bank 
Main line levee, left bank 
Devils Swamp barge channel 
Regulating spillway, right bank 
Main line levee, right bank 
Levee closure and enlargement, 
low and high water spillway 
structures, navigation lock, and 
approach channels, right bank 
Main line levee, right bank 
Harbor extension and industrial 
fill 
Main line levee, left bank 
Pumping Plant and drainage 
structure, right bank 
Harbor improvements and port 
area 
Culvert and floodgate, right 
bank 
Main line levee and floodwall, 
right bank 
Main line levee, right bank 
by Public Law 
by Public Law 
Modified by Public Law 
87-874. 
Extends up south bank of 
Old River to Barbre 
Landing. 
Authorized by Public Law 
83-780. 
Joins Arkansas River, 
south bank levee. 
Authorized by Public Law 
70-391. Modified by 
Public Laws 79-526 and 
83-780. 
Unpublished Vicksburg 
District's MRC report 
approved Apr. 14, 1966.2 
Authorized by Public Law 
85-500. 
Authorized by Public Law 
79-526.2 
42-11 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Postauthorization change 
report, approved June 
1987. 
Authorized by Public Law 
89-298 (HD 308/74/1). 
Included in MS Delta 
Region, LA feature. 
Authorized 
81-516. 
Authorized 
81-516.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS 
(Continued) 
Mileage 
Above Head 
of Passes 
722-725 
721-734 
803-873 
857 
Locality 
Industrial levee (Ensley 
Bottoms) 
Memphis Harbor, TN 
Tiptonville-Obion River 
Near Mud Lake, TN 
Improvement 
Leve 
Closu 
indi 
chat 
Main 
exte 
Riv 
Pump 
chat 
890 - St. Johns Bayou, MO Draii 
clos 
890 New Madrid Floodway, MO Draii 
clos 
890-954 New Madrid-Birds Point, MO Flooc 
902-922 Slough Bend, Hickman, KY Main 
922 Hickman, KY Flooc 
946 Peafield, MO Draii 
9571 Cairo, Cairo drainage district Flooc 
9571 Cairo, Cairo drainage district, Flooc 
Mounds, Mound City, and plan 
vicinity 
Thebes-Rock Island, IL Leve 
Cape Girardeau, MO to Rock Leve 
Island, IL 
1. Cairo, IL, is on Ohio River about 3 miles above 
its mouth (Mississippi River mile 954 AHP). 
2. Also see Table 42-D, "Authorizing Legislation." 
e and pumping station 
ire of Tennessee Chute, 
istrial fill, levee, harbor 
nnels, etc. 
1 line levee, left bank, levee 
ension, and diversion Obion 
er 
pin g station and adjacent 
nnel improvements 
nage floodgate and levee 
ure 
nage floodgate and levee 
ure 
dway, right bank 
line levee, left bank 
dwall, left bank 
nage floodgate 
dwalls and levees 
dwalls, levees, and pumping 
nt 
es, both banks 
es 
Remarks 
Authorized by Public Law 
79-526. 
Modified by Acts of Jul. 
24, 1946 and Dec. 23, 
1971. 
Authorized Dec. 15 and 
17, 1970 under Sec. 201 
of Oct. 27, 1965 FC Act. 
Modified by Jul. 24, 1946 
Act. 
Modified by Sep. 3, 1954 
Act. 
Authorized by Sep. 3, 
1954 Act. 
Intermittent (Sec. 6). 
Intermittent (Sec. 6). 
3. Commerce, MO, is on Upper Mississippi River, 39 
miles above mouth of Ohio River. 
42-12

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
0-54 
27-54 
54-117 
20-27 
25-117 
27 
0-27 
31-57 
80 
53-117 
117 
117-129 
117-129 
105 
105-120 
115 
116 
5 
5-105 
29 
29 
40 
40 
40 
Floodway 
Floodway 
Floodway 
ATCHAFALAYA BASIN, LA' 
Atchafalaya Basin. Morga uza 
and West Atchafalaya 
Flood ways 
West Atchafalaya Floodway 
between Red River and 
Alabama Bayou 
Morganza Floodway between 
Mississippi River and Alabama 
Bayou 
Atchafalaya Basin Floodway 
between Alabama Bayou and 
Morgan City 
East protection le ee (Morganza 
and Atchafalaya Flood ways) 
Lacour-Red Cross 
Morganza-Morgan City 
Bayou Latenache 
Upper Pointe Coupee Loop area 
Bayou Fordoche-Ramah 
Bayou Sorrell 
Bayou Sorrel Lock-Morgan City 
Morgan City 
Below Morgan City 
Below Morgan City 
Atchafalaya Basin Flood way 
lower protection lep'ee 
Calumet 
Below Morgan City 
Berwick' 
Patterson 
West protection leee (Atchafalaya 
Basin and West Atchafalaya 
Flood ways) 
Simmesport-Hamburg 
Mansura to Wax Lake Outlet 
Coulee des Grues 
West Atchafalaya Floodway 
Morganza Floodway 
Bayou Darbonne 
West Atchafalaya Floodway 
Morganza Floodway 
Including lower Morganza 
Floodway guide levee. 
Through upper Morganza 
guide levee and enlargement 
of outlet channel. 
Enlargement of Bayou 
Latenache. Approved Jun. 
4, 1970. See Table 42-D. 
Levee landside borrow pit. 
Alternate route, Gulf 
Intracoastal Waterway 
Port Allen to Morgan City. 
Gulf Intracoastal Waterway 
utilizes levee west side 
borrow pit channel. 
Gulf Intracoastal 
Waterway. 
Bypass route for Gulf 
Intracoastal Waterway. 
East of lower river. 
Bayou Teche-Wax Lake 
Outlet. 
Inclosed area between Wax 
Lake Outlet and Berwick. 
Lower Atchafalaya River. 
Adjustment to provide fresh 
water. 
West Atchafalaya 
Floodway. 
Through West Atchafalaya 
protection levee. 
42-13 
Levee, upper Morganza guide 
Levee and Morgan City floodwall 
Drainage structure, Pointe Coupee, 
and channel enlargement 
Additional drainage facilities 
Drainage channel 
Lock 
Alternate navigation channel, Gulf 
Intracoastal Waterway 
Lock in Bayou Boeuf' 
Channel relocation 
Levee, floodwall 
Floodgate, east 
Levees, floodwall, drainage 
structures, and pumping plants 
Lock 
Water system 
Levee fuse plug 
Protection levee 
Levee enlargement and floodgate 
extension 
Railway 
Railway 
Gated drainage structures 
Highway 
Highway

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
41 Bayou Courtableau 
41 
41 
94 
94 
105 
105 
0-54 
5-6 
5-66 
28-30 
40-41 
54-117 
94-106 
Mileage 
Above 
Mouth 
0-8 
50-133 
96 
133 
0-17 
17-40 
40-51 
51-60 
17-42 
87-107 
40 
60 
West Atchafalaya Floodway 
Morganza Floodway 
Charenton 
Jaws-Lake Fausse Pointe 
Calumet 
Wax Lake Outlet 
Atchafalaya River 
Barbre Landing-Alabama Bayou 
Simmesport 
Simmesport-Bayou Garofier 
Melville 
Krotz Springs 
Below Alabama Bayou 
Mississippi River-Morgan City 
TECHE-VERMILION BASINS, 
LA 
Atchafalaya River to Teche- 
Vermilion Basins 
Courtableau Basin, LA, and 
outlets 
Charenton Canal 
West Atchafalaya protection levee 
borrow pit channel 
Bayou Courtableau spillway 
Bayou des Glaises 
BAYOU COCODRIE AND 
TRIBUTARIES 
Bayou Courtableau 
Bayou Cocodrie 
Bayous Cocodrie-Boeuf diversion 
Bayou Boeuf 
Bayous Boeuf-Rapides diversion 
Upper Cocodrie 
Bayou Boeuf 
Bayou Lamourie to Kincaid 
Structures 
Lecompte Control Structure 
Bayou Rapides Control Structure 
Gated drainage control structures 
and channels 
Railway 
Railway 
Floodgate and approach channels 
Outlet, Charenton drainage canal 
and protection levee. 
Floodgate, west 
Drainage canal-railway and 
highway bridges 
East bank, levee 
Levee, ring, and drainage structure 
West bank, levee 
Levee, ring 
Levee, ring 
Channel enlargement 
12- by 125-foot navigation channel 
Pumping station above Krotz 
Springs, conveyance channels, 
and appurtenant works 
Drainage channel 
Drainage channel 
Drainage control structure 
Diversion channel 
Enlargement and additional 
culverts 
Enlargement and realinement 
New channel 
New channel 
New channel 
Enlargement, clearing, and 
snagging 
Enlargement, realinement, 
clearing and snagging 
Fixed elevation weir 
Gated drainage structure 
42-14 
Borrow pit channel to 
Grand Lake through West 
Atchafalaya protection 
levee. 
Restoration of drainage 
west of West Atchafalaya 
Basin protection levee. 
Bayou Teche and Wax Lake 
Outlet. 
To lower flood heights. 
Increase channel capacities 
to decrease flood heights. 
Through Grand and Six 
Mile Lakes. 
Freshwater distribution 
from Atchafalaya River to 
Teche-Vermilion Basins. 
Outlet to gulf. 
Intercepting drainage 
channel. 
Washington to west 
protection levee.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
Bayou Lamourie Control 
Structure 
Various 
LAKE PONTCHARTRAIN, LA 
Lake Pontchartrain, Jefferson 
Parish, LA 
AMITE RIVER, LA 
Amite River, LA 
LOWER RED RIVER, SOUTH 
BANK, RED RIVER LEVEES, 
LA 
Moncla-Hotwells 
Red River-Moncla to Lake Long 
EASTERN RAPIDES AND 
SOUTH-CENTRAL 
AVOYELLES PARISHES, LA 
Eastern Rapides and southcentral 
Avoyelles Parishes, LA 
TENSAS BASIN, AR AND LA 
Red River backwater area 
Tensas-Cocodrie area 
Larto Lake-Jonesville 
Sicily Island area 
Below Red River area 
Black River, LA 
Six Mile Bayou area 
Jonesville, LA 
Ouachita River 
Boeuf and Tensas Rivers a lnd 
Bayou Macon, AR, and LA 
Bocuf River, AR, and LA 
Below Bayou La Fourche 
Bayou LaFourche 
Boeuf River, AR, and LA above 
Bayou LaFourche 
Canal 19 
Canal 19 extension 
Big and Colewa Creeks 
87 
(2, 3) 
Gated drainage structure 
Railway, highway, and local road 
bridges, and pipeline crossing 
Flood protection 
Bank protection 
Levee, south bank 
Levees 
Flood protection and drainage 
improvement 
Levees, drainage channels, 
structures, and pumping plant 
Levees, drainage channels, and 
structures 
Levees, drainage channels, 
structures, and pumping plants 
Levees, drainage channels, 
structures, and pumping plants 
Drainage structure and 
appurtenant channel works 
Levees, floodwall, pumping plant, 
and interior drainage 
Levees, drainage channels, and 
structures 
Clearing 
Channel improvement and 
realinement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
42-15 
Authorized by Public Law 
81-516. Eliminated by 
Public Law 89-298. 
Intermittent (Sec. 6). 
Authorized by Public Law 
91-611. 
(4) 
(4) 
(4) 
(4) 
Unpublished VXD-MRC 
Letter Report dated May 
31, 1977. MR&T 
authority. 2 
Portion of levee built under 
Sec. 6. Incorporated in 
MR&T by Public Law 
81-516.2 
Monroe to Sandy Bayou and 
Bawcomville (Sec. 6). 
(5) 
(5) 
Authorized by Public Laws 
78-534 and 79-526.2" ' 
(5) 
(") 
Authorized by Public Law 
78-534.; 
82-145 
3-56 
3-56 
5 
56 
0-32 
0-56 
151-235 
210-286 
286-296 
0-75

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
0-8 
0-7 
0-33 
0-10 
0-9 
0-14 
0-170 
0-34 
0-35 
Lake Chicot 
0-6 
0-165 
0-22 
0-0.2 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
To divert flows from Lake Chicot 
Tributaries of Boeuf River- 
Canal 19 
Fleschmans Bayou 
Caney Bayou 
Big Bayou 
Canal 18 
Kirsch Lake Canal 
Black Pond Slough 
Bayou Macon, AR, and LA 
Bayou Macon 
Canal 43 
Canal 81 
Pumping plant and drainage 
structure 
Tributa ry of Bay ou Macon 
Rush Bayou 
Tensas River, AR and LA 
Tensas River 
Tributa ryI of Tensas Ricer 
Mill and Vidal Bayous 
Gran t Ca na(11L,A 
Grant's Canal at Lake Providence 
LOWER ARKANSAS RIVER, 
AR 
Yancopin-Pine Bluff 
Fletcher Bend, AR to Pine Bluff 
North Little Rock to Gillett (below 
Plum Bayou) 
GRAND PRAIRIE-BAYOU 
METO, AR 
Grand Prairie Region and Bayou 
Meto Basin, AR 
YAZOO BASIN, MS 
Yazoo Backwater area 
Yazoo River System below 
Arkabutla Lake 
Yazoo River between Yazoo City 
and Prichard 
Yazoo River between Yazoo City 
and Askew 
Will M. Whittington Auxiliary 
Channel 
Yazoo City protection 
Rocky Bayou area 
Belzoni protection 
Greenwood protection 
Arkabutla Iake 
Channel improvement 
Channel improvement 
Filling canal 
(6) 
(6) 
(5) 
(") 
(6) 
(") 
See Table 42-E
(5) 
(5) 
Authorized by Public Law 
90-483. 
(6) 
Authorized by Public Law 
78-534. a 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
81-516. 
Levee, south bank 
Revetment 
Levee, north bank (5) 
Water supply and drainage 
improvements 
Levees and pumping plants 
Channel improvement 
Levees, right bank 
Levees, left bank 
Authorized by Public Law 
81-516. 
Including Tallahatchie and 
Coldwater Rivers. 
Intermittent. 
Intermittent. 
Floodway channel 
Levee, drainage structure, and 
pumping plant 
Channel clearing and enlargement 
Levee and floodwall 
Levees, channel improvement, 
drainage structures, and pumping 
plants 
Flood detention and conservation 
Improvement of 7.8 miles 
was approved Apr. 29, 
1970. 
See Table 42-C. 
42-16 
Clearing 
23-98 
35-98 
48-102 
0-75 
0-381 
75-366 
75-345 
45-109 
75 
127 
185 
381

TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River 
0-64 
64 
0-24 
0-26 
26 
0-13 
13 
0-88 
137-260 
75-381 
0-8.3 
0-23 
0-42 
275-290 
0-204 
0-8 
0-28 
0-81 
0-43 
0-4 
0-27 
153-160 
0-68 
13-55 
0-68 
99 
Locality 
Yalobusha River below Grenada 
Lake 
Grenada Lake 
Tallahatchie River-Little 
Tallahatchie River 
Little Tallahatchie River below 
Sardis Lake 
Sardis Lake 
Yocona River below Enid Lake 
Enid Lake 
Cassidy Bayou below Old 
Coldwater River 
Upper Yazoo Projects 
Area between main stem and hills 
including Bobo Bayou 
McKinney Bayou 
Alligator-Catfish Bayous 
Bear Creek 
Whiteoak Bayou 
Tallahatchie River, MS 
Big Sunflower Riter,f' etc. 
Big Sunflower River 
Hull Brake-Mill Creek Canal 
Hushpuckena River 
Quiver River 
Gin and Muddy Bayous, MS 
Bogue Phalia 
Ditchlow Bayou 
Little Sunflower River 
Deer Creek 
Steele Bayou 
Muddy Bayou 
LOWER WHITE RIVER AND 
BASIN, AR 
Laconia Circle-Old Town Lake 
Big Creek and tributaries 
Clarendon levee 
Improvement 
Channel improvement 
Flood detention and conservation 
Levees, Panola-Quitman Floodway 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Floodway channel 
Levees and channel improvement 
Channel improvement and 
enlargement of pumping plant 
Channel improvement 
Channel improvement 
Channel improvement 
Two road crossings of Panola- 
Quitman Floodway, MS and for 
protection of Sheley Bridge 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Water-control structure 
42-17 
Remarks 
See Table 42-C. 
See Table 42-C. 
See Table 42-C. 
Including Moores Bayou, 
Cutoff Bayou, Whiting 
Lake and outlet. 
Authorized by Public Law 
79-526. 
Authorized by Public Law 
79-526. 
Authorized by Public Law 
89-298. As modified in 
GDM in 1967. 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
90-147. 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
87-874. 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 
Authorized by Public Law 
78-534. 3 Modified in 
December 1970. See Table 
42-D. 
Approved Mar. 3, 1970. See 
Table 42-D. 
Mile 605-645 Mississippi 
River. 
(6) 
Authorized by Public Law 
89-298. 
Authorized by Public Law 
89-298. 
Levee, backwater including outlet 
Pumping plant 
Channel improvement and 
structures 
Levee and outlet structures

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
of Atchafalaya 
River Locality Improvement Remarks 
108-192 
122 
143 
0-196 
0-90 
260 
0-225 
225 
0-105 
86 
0-36 
0-29 
0-17 
0-12 
0-108 
0-25 
0-20 
0-15 
Augusta to Clarendon 
De Valls Bluff 
Des Arc, AR 
CACHE BASIN, AR 
Cache River, AR 
Bayou DeView, AR 
ST. FRANCIS RIVER AND 
BASIN, AR, AND MO 
Inter-River Drainage District in 
Missouri 
Mouth of St. Francis River- 
Wappapello Dam 
Wappapello Lake 
Little River Basin 
Marked Tree, AR 
Tyronza River 
Big Slough Ditch 
Mayo Ditch 
Cross County Ditch 
Belle Fountain Ditch 
Drainage District No. 17 
L'ANGUILLE RIVER, AR 
L'Anguille River and tributaries, 
Brushy and First Creeks 
WEST TENNESSEE 
TRIBUTARIES 
Wolf River and tributaries, TN 
Obion River and tributaries, 
North, South, Middle, and 
Rutherford Forks 
Forked Deer River and 
tributaries, North, Middle, and 
South Forks 
Mud Lake Pumping Station, TN 
Harris Fork Creek, TN and KY 
Porter Gap, TN 
REELFOOT LAKE-LAKE NO. 
9, TN AND KY 
Running Reelfoot Bayou, TN 
Bayou du Chien and Lake No. 9, 
KY and TN 
Levees, outlet structures 
Levee, outlet structure, and 
pumping station 
Levee, outlet structure, and 
pumping station 
Channel improvement and 
structures 
Channel improvement and 
structures 
Channel improvement and two 
outlet structures 
Floodway, levees, drainage 
channels, and structures 
Flood detention and conservation 
Floodway, levees, drainage 
channels, and structures 
Marked Tree Siphon 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement and 
pumping station 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Pumping plant 
Flood control improvements 
Construction to main-stem 
standards, levee and appurtanent 
structures for flood control 
Channel improvement 
Channel improvements and 
pumping station 
42-18 
(5) 
(5) 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Authorized by Public Law 
81-516. 
Authorized Dec. 16, 1975. 
See Table 42-D. 
See Table 42-C. 
Authorized by Public Law 
90-483. 
Authorized by Public Law 
90-483. 
Authorized by Public Law 
80-858. 
(6) 
Authorized by 1948 Flood 
Control Act. 
Authorized by 1948 Flood 
Control Act. 
Authorized by Resolutions 
Dec. 15 and 17, 1970.2 
Authorized by Water 
Resources Act of Oct. 22, 
1976.2 Section 102, 1976.2 
Section 183, 1976.2 
Authorized by Public Law 
83-780. 
Authorized in December 
1970, See Table 42-D.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
WEST KENTUCKY 
TRIBUTARIES, KY 
0-47 Obion Creek, KY Channel improvement Authorized by Public Law 
89-298. 
LITTLE RIVER DIVERSION 
CHANNEL, MO 
Delta to Ancell, MO Levees Mile 49 above Cairo. 
MISSOURI RIVER, MO 
0-28 Mouth to St. Charles, MO Levees Intermittent (Sec. 6). 
ILLINOIS RIVER, IL 
0-120 Mouth to Havana, IL Levees Intermittent (Sec. 6). 
OHIO RIVER, IL AND KY 
Cairo to Mound City and Mounds, Floodwall, levee, revetment, and 
IL pumping plant 
1. General data concerning Bayou Boeuf, Bayou Sorrel, 
and Berwick locks where Atchafalaya Basin protection levees 
cross Gulf Intracoastal Waterway, alternate route to Plaquemine, 
LA and lower Atchafalaya River (extension of Bayou 
Teche Waterway), respectively, are in report of New Orleans 
district. 
2. Also see Table 42-D, "Authorizing Legislation." 
3. Public Law 81-516 modified requirements of local 
cooperation. 
4. Authorized by Public Law 77-228. Modified by Public 
Law 89-298. 
5. Authorized or incorporated in MR&T by Public Law 
79-526.3 See Table 42-D. 
6. Authorized by Public Law 85-500. 
42-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-C MISSISSIPPI RIVER TRIBUTARY 
DAMS AND LAKES 
Grenada Enid Sardis Arkabutla Wappapello 
Name' Lake Lake Lake Lake Lake 
River Yalobusha Yocona Little Tallahatchie Coldwater St. Francis 
Nearest town to damsite Grenada Enid Sardis Arkabutla Wappapello 
Drainage area, square miles 1,320 560 1,545 1,000 1,310 
Conservation pool: 
Area, thousand acres 10 6 11 5 4 
Volume, thousand acre-feet 86 58 108 31 31 
Elevation, feet, NGVD 193 230 236.0 209.3 354.7 
Flood control pool: 
Area, thousand acres 65 28 58.5 33 23 
Volume, thousand acre-feet 1,252 602 1,462 494 582 
Runoff, inches 17.8 20.2 17.7 9.3 8.4 
Outlet gates: 
Number 3 2 4 3 3 
Size, feet 7.5 by 14 8 by 16 6 by 12 8.5 by 19 10 by 20 
Capacity, thousand cubic 
feet per second 10.7 9.4 10.0 10.0 18.0 
Spillway: 
Type, uncontrolled Chute Chute Chute Chute Gravity 
Length, feet 200 200 400 300 740 
Elevation, crest, feet, NGVD 231 268 281.4 238.3 394.7 
Discharge capacity, thousand 
cubic feet per second 52 50 132 89 229 
Surcharge pool: 
Area, thousand acres 106 41 90 63 32 
Volume, thousand acre-feet 1,385 554 1,447 858 521 
Runoff, inches 19.7 18.5 17.6 16.1 7.5 
Elevation, feet, NGVD 247.5 284.0 301.0 256.3 413.7 
Dam: 
Type, earthfill Rolled Rolled Hydraulic Rolled Rolled 
Length, thousand feet 13.9 8.4 15.3 11.5 2.7 
Elevation, crest, feet, NGVD 256.0 293.0 311.4 264.3 419.7 
1. Grenada, Enid, Sardis and Arkabutla Lakes are in 
Yazoo River Basin, MS; Wappapello Lake is in St. Francis 
River Basin, MO. 
42-20

TABLE 42-D 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
May 15, 1928 
Jun. 19, 1930 
Feb. 15, 1933 
Apr. 23, 1934 
Aug. 30, 1935 
Jun. 15, 1936 
Flood protection in alluvial valley of Mississippi River, revetment 
and contraction works and dredging to provide least channel 
depth of 9 feet and width of 300 feet below Cairo. 
Provided for allotment of the balance of emergency rescue funds 
to reimburse levee districts and others for expenditures in floodcontrol 
works during the 1927 and subsequent floods. 
Provided for ownership of lands in Bonnet Carrb Spillway and 
Floodway with proviso for granting rights-of-way, easements, 
and permits, in said lands 
Authorized payment for purchase of, or to reimburse states and 
local levee districts for the cost of, levee rights-of-way for flood 
control work in the Mississippi Valley, and for other purposes. 
Improvement of Wolf and Nonconnah Rivers, TN (Nonconnah 
Creek is correct title) 
Improvement of Wolf River (Memphis Harbor), TN 
Modification of the 1928 Act to provide for: 
Construction of a backwater levee at mouth of White River, AR 
Construction of Eudora floodway in lieu of Boeuf floodway; flood 
control, Yazoo River; construction of Morganza floodway; and 
an outlet to the Gulf of Mexico west of Berwick, LA, including a 
6-year program for the improvement and regularization of the 
Mississippi River between Arkansas and Red Rivers, and 
Atchafalaya River; and construction of roads on levees and 
drainage adjustments incident to floodway levees. 
Provided for construction of floodwalls, levees, and revetments 
along Wolf River and Nonconnah Creek for protection of 
Memphis, TN 
Modify the Yazoo River project to substitute a combined 
reservoir floodway and levee plan. 
Construction of Mounds to Mound City levee and control works 
along Cache River, IL 
Modification of previous act pertaining to floodways and outlets 
and lands therein; including program for the improvement and 
regularization of the Mississippi River, between Cairo and 
Arkansas River, extension of levee road system; strengthening 
of levees. 
Enlarge main line levees to offset abandonment of floodways 
between Arkansas and Red Rivers, flood control works in 
backwater areas of Yazoo and Red Rivers, and in Bayous 
Rapides, Boeuf, and Cocodrie, LA 
Navigation channel 12 feet deep and 300 feet wide between Baton 
Rouge and Cairo; flood protection of Yazoo River Backwater 
Area in vicinity of Satartia, MS 
Continue prosecution of channel improvement and stabilization 
program, $200 million. 
Flood control on the Big Sunflower, Little Sunflower, 
Hushpuckena, and Quiver Rivers and their tributaries, and on 
Hull Brake-Mill Creek Canal, Bogue Phalia, Ditchlow Bayou, 
Deer Creek, and Steele Bayou, MS' 
Improve Boeuf and Tensas Rivers and Bayou Macon, AR' 
Improve Bayou Lafourche, LA 
Improve Yazoo River tributaries. 
North bank, Arkansas River levees (below Plum Bayou).' 
Unpublished report on 
record in OCE. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 1st sess. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 1st sess. 
H. Doc. 359, 77th Cong., 1st 
sess. 
H. Doc. 509, 78th Cong., 2d 
sess. 
Public Law 534, 78th Cong., 
2d sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
S. Doc. 151, 78th Cong., 2d 
sess. 
S. Doc. 191, 79th Cong., 2d 
sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
H. Doc. 308, 74th Cong., 1st 
sess. 
42-21 
H. Doc. 90, 70th Cong., 1st 
sess. 
Public 395, 71st Cong., 2d 
sess. 
Public 351, 72d Cong. 
Public 171, 73d Cong. 
R&H Comm. Doc. 26, 72d 
Cong., 1st sess. 
R&H Comm. Doc. 45, 74th 
Cong., 1st sess. 
Unpublished report dated 
Apr. 2, 1925. 
H. Comm. on Flood Control, 
Doc. 1, 74th Cong., 1st sess. 
Aug. 28, 1937 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-D AUTHORIZING LEGISLATION 
(Continued) 
Actor 
Authorization Work Authorized 
Levees on White River (Augusta to Clarendon).' 
Bayou des Glaises diversion channel, LA' 
Modify local cooperation requirements in St. Francis and Yazoo 
Basins. 
Tiptonville-Obion levee and drainage improvements.' 
Improvement of St. Johns Bayou, MO 
Big Sunflower River, etc.' 
Tennessee Chute (Memphis Harbor), TN 
Continue prosecution of project for flood control and channel 
improvement, $100 million. 
Improve Mississippi River below Cape Girardeau, MO with 
respect to West Tennessee tributaries. 
Improve L'Anguille River, AR 
Baton Rouge Harbor (Devils Swamp), LA' 
Flood protection at Des Arc, AR 
Improve St. Francis River and Basin, AR and MO 
Improve Cache River and Bayou DeView, AR and MO 
Improve Grand Prairie Region and Bayou Meto Basin, AR 
Flood protection, Lake Pontchartrain, Jefferson Parish, LA' 
Filling Grant's Canal, Lake Providence, LA 
Additional protection to Red River Backwater Area. 
Extend Federal jurisdiction to cover levees in Orleans Parish, LA 
Bank protection, Amite River, LA 
Continue prosecution of project for flood control and channel 
improvement, $200 million. 
Jonesville, LA levee, retaining wall, and drainage structure.' 
Modify requirements for local cooperation in White River 
Backwater Area, AR 
Navigation improvement of Atchafalaya from Mississippi River 
to Morgan City, LA 
Modify project for Vicksburg-Yazoo Area (Harbor), MS 
Improve New Madrid Floodway, MO, including Peafield 
drainage floodgate. 
Control of Old and Atchafalaya Rivers and a lock for navigation. 
Improve Reelfoot Lake area, KY and TN 
Improve Greenville Harbor, MS 
42-22 
Jun. 30, 1948 
May 17, 1950 
Oct. 30, 1951 
Sep. 3, 1954 
Jul. 3, 1958 
Document 
H. Doc. 98, 76th Cong., 1st 
sess. 
H. Doc. 602, 79th Cong., 2d 
sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 757, 79th Cong., 2d 
sess. 
H. Doc. 138, 80th Cong., 1st 
sess. 
H. Doc. 516, 78th Cong., 2d 
sess. 
S. Doc. 51, 80th Cong., 1st 
sess. 
Public Law 526, 79th Cong., 
2d sess. 
H. Doc. 627, 80th Cong., 2d 
sess. 
H. Doc. 651, 80th Cong., 2d 
sess. 
H. Doc. 321, 80th Cong., 1st 
sess. 
H. Doc. 485, 81st Cong., 2d 
sess. 
H. Doc. 132, 81st Cong., 1st 
sess. 
S. Doc. 88, 81st Cong., 1st 
sess. 
H. Doc. 255, 81st Cong., 1st 
sess. 
S. Doc. 139, 81st Cong., 2d 
sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 1st 
sess. 
Public Law 237, 82d Cong., 
1st sess. 
S. Doc. 53, 82d Cong., 1st 
sess. 
H. Doc. 85, 83d Cong., 1st 
sess. 
H. Doc. 183, 83d Cong., Ist 
sess. 
H. Doc. 478, 83d Cong., 2d 
sess. 
S. Doc. 160, 83d Cong., 2d 
sess. 
S. Doc. 15, 86th Cong., Ist 
sess.

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Jul. 14, 1960 
Oct. 23, 1962 
Jun. 18, 1965 
Oct. 27, 1965 
Extensions to project for Boeuf and Tensas Rivers and Bayou 
Macon in Arkansas. 
White River backwater area pumping plant. 
Wolf River and tributaries for flood protection in Tennessee. 
Continue prosecution of project for channel improvement-$50 
million. 
Modification-Baton Rouge Harbor (Devils Swamp), LA 
Construct improvements in Gin and Muddy Bayous, Yazoo River 
Basin, MS 
Replace 2 bridges with adequate floodway over Boeuf River and 
Big Bayou in Boeuf Basin, AR 
Continue prosecution of project for flood control and channel 
improvement, $53 million. 
Modify and expand levees and channel improvement features of 
main stem project. 
Modify flood control improvements in following tributary areas 
and basins: Cairo-Mounds-Mounds City, St. Francis, Lower 
White, Boeuf-Tensas-Macon, Red River backwater, Yazoo 
headwater, Grand Prairie, and Bayou Meto. 
Acquire any modified easements required in New Madrid 
Floodway as provided by Sec. 4 of May 15, 1928 act. 
Operate and maintain pumping plant in Red River backwater 
area (Tensas-Cocodrie Pumping Plant). 
Provide improvements in West Kentucky tributaries. 
Provide fish and wildlife facilities in St. Francis and Big 
Sunflower Basins; Yazoo Headwater and Backwater Areas; and 
Mississippi Delta region. 
Deauthorize Amite River, LA project. 
Modify St. Francis River, MO and AR, project within District 
No. 7, Poinsett County, AR 
Provide pumping plant and drainage structure at Wilson Point, 
LA 
Construction of improvements to supplement freshwater supply 
in Teche-Vermilion Basins in Louisiana. 
Bank revetment for protection of existing industrial facilities 
along Mississippi River below Baton Rouge, LA 
Modification of West Tennessee tributaries feature to provide 
relocation of gas transmission lines at Federal expense. 
Continue emergency work, $87,135,000, which includes $100,000 
for road crossing of Panola-Quitman Floodway, MS, and $80,000 
for protection of Sheley Bridge, Tallahatchie River, MS 
Improvements in Boeuf and Tensas Rivers and Bayou Macon 
Basin to divert flows that would otherwise enter Lake Chicot, 
AR 
Improvements in the Belle Fountain ditch and tributaries, MO, 
and Drainage District No. 17, AR 
Provide pumping plants and other drainage facilities in Cairo, 
IL, and vicinity. 
Modification of Yazoo Headwater Project to include cleanout 
along David Bayou, MS 
Modify Yazoo Backwater feature to include a control structure in 
Muddy Bayou, MS 
42-23 
H. Doc. 108, 85th Cong., 1st 
sess. 
S. Doc. 26, 85th Cong., 1st 
sess. 
H. Doc. 76, 85th Cong., 1st 
sess. 
Public Law 86-645. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 87-874. 
Public Law 89-42. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
H. Doc. 308, 88th Cong., 2d 
sess. 
S. Doc. 57, 89th Cong., 1st 
sess. 
Unpublished Vicksburg 
District's MRC report 
Approved-Apr. 14, 1966. 
H. Doc. 524, 89th Cong., 2d 
sess. 
Public Law 89-789. 
Public Law 89-789. 
Public Law 90-147. 
H. Doc. 168, 90th Cong., 1st 
sess. 
H. Doc. 339, 90th Cong., 2d 
sess. 
Public Law 90-483. 
Unpublished MRC report 
dated May 8, 1968. 
Unpublished MRC report 
dated Feb. 2, 1970. 
Apr. 14, 19662 
Nov. 7, 1966 
Nov. 20, 1967 
Aug. 13, 1968 
Sep. 10, 1968; 
Mar. 3, 1970:

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
Apr. 29, 19703 
Jun. 4, 19703 
Dec. 31, 1970 
Senate and 
House Public 
Works 
Resolutions 
adopted Dec. 17 
and 15, 1970, 
respectively. 4 
River Basin 
Monetary Act 
of Dec. 23, 1971 
Jan. 19, 19732 
TITLE I Water 
Resources 
Development 
Act of 1974. 
Modification of Yazoo Headwater Project to include drainage 
structure and channel improvement on Rocky Bayou, MS 
Provide for enlargement of Bayou Latenache from Pointe Coupee 
drainage structure to Alabama Bayou, LA 
Modify and expand project to include flood protection within the 
area of eastern Rapides and south-central Avoyelles Parishes, 
LA, that are drained by Bayou des Glaises diversion channel and 
Lake Long, and their tributaries. 
Modify the project for West Kentucky tributaries (Obion Creek), 
KY, to provide for all relocations, at Federal expense, of all 
transmission lines required by the project. 
Report on Western Tennessee Tributaries, TN and KY, 
authorized: 
a. Modification of Reelfoot Lake feature to provide channel 
improvements on Bayou du Chien and Lake No. 9 in KY and 
b. Modification of Mississippi levee feature to include a 
pumping station near Mud Lake floodgate and adjacent 
channel improvements. 
Modification of Big Sunflower Basin feature to provide 
additional improvements in Steele Bayou Basin, MS 
Continue prosecution of project for the comprehensive 
development of the basin, $97 million. 
Modification of Tiptonville-Obion River levee feature to relieve 
local interests of all responsibility except that of providing 
maintenance. 
Modification of the Mississippi levee feature to provide additional 
drainage facilities in Long Lake area, vicinity of Helena, AR 
Projects recommended by four completed reports were 
authorized for accomplishment of Phase I design memorandum 
of advance engineering and design on: 
a. Greenville Harbor, Greenville, MS 
b. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Natchez area). 
c. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Vicksburg-Yazoo area). 
d. Bushley Bayou Area of Red River Backwater Area, LA 
Modification of West Tennessee tributaries feature (Obion and 
Forked Deer Rivers), TN, to acquire lands for fish and wildlife, 
recreation, and environmental purposes. 
Modification of the Yazoo Basin, MS, feature to provide for a 
streambank erosion control demonstration project for the delta 
and hill areas of basin. 
Modification of project to provide that the Secretary of the Army, 
acting through the Chief of Engineers, can substitute authorized 
mitigation lands, not yet acquired and no longer suitable, for 
like acreage in the same or adjacent subbasins of the project 
area. This section provides the authority to substitute authorized 
mitigation lands in: 
a. Tensas Basin, LA and AR, feature (Red River backwater). 
b. St. Francis Basin, AR and MO, feature. 
Modification of Bayou Cocodrie and tributaries, LA, feature, to 
provide for: enlargement of Bayou Courtableau from 
Washington to west protection levee; right-of-way and spoil 
disposal areas at Federal expense; and necessary additional 
culverts through west protection levee. 
Unpublished MRC report 
dated Mar. 6, 1970. 
Unpublished MRC report 
dated Sep. 22, 1969. 
S. Doc. 91-113, 2d sess. 
Public Law 91-611. 
H. Doc. 91-414, 2d sess. 
S. Doc. 91-74, 2d sess. 
Sec. 1, Public Law 92-222. 
Sec. 7, Public Law 92-222. 
Unpublished Memphis 
District's MRC report 
dated Oct. 4, 1972. 
Sec. 1, Public Law 93-251. 
Mar. 7, 1974. 
S. Doc. 93-38, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-157, 1st sess. 
Sec. 3, Public Law 93-251. 
Sec. 32, Public Law 93-251. 
Sec. 42, Public Law 93-251. 
Sec. 87, Public Law 93-251. 
42-24

TABLE 42-D 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Actor 
Authorization Work Authorized Document 
TITLE II River 
Basin 
Monetary 
Authorization 
Act of 1974 
River Basin 
Monetary Act 
of Oct. 2, 1975 
Dec. 16, 19752 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1977. 
Water Resources 
Development 
Act of 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1978. 
Modification of Cache River Basin, AR, feature to provide for: 
acquisition by fee easements of lands for fish and wildlife 
management, recreation, and environmental purposes. 
Continue prosecution of project for the comprehensive 
development of the basin, $211 million. 
Continue prosecution of project for the comprehensive 
development of the basin, $158,000,000. 
Modification of St. Francis Basin, AR and MO, feature to provide 
relief from ponding of interior runoff in the Inter-River 
Drainage District of Missouri. 
Continue prosecution of project for comprehensive development 
during period Jul. 1- Sep. 30, 1976, $60,300,000. 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $231,497,000. 
Sec. 101(a) authorized accomplishment of Phase I - Advanced 
Engineering and Design Memoranda - On: 
a. St. Johns Bayou and New Madrid Floodway, MO, project: 
Report of OCE - Sep. 26, 1975. 
b. Nonconnah Creek, TN" and MS, project: Report of OCE -Jun. 
23, 1976, and as an independent part of the project: 
Improvements for flood control and allied purposes on Horn 
Lake Creek and tributaries, including Cowpen Creek, TN 
and MS. 
Modification of West Tennessee Tributaries feature (Obion and 
Forked Deer Rivers), TN, to: 
a. (Sec. 102) - Provide project for flood control for Harris Fork 
Creek, TN and KY: (H.D. 94-221) except that highway bridge 
relocations and alterations shall be at Federal expense. 
b. (Sec. 183) - Provide for construction of a levee and 
appurtenant works from mouth of Obion diversion channel to 
vicinity Highway 88 and thence to vicinity of Porter Gap, TN 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $253,081,000. 
Sec. 99, Public Law 93-251. 
Sec. 201, Public Law 93-251. 
Mar. 7, 1974. 
Sec. 1, Public Law 94-101. 
Unpublished Memphis 
District's MRC report 
dated Nov. 11, 1975. 
Public Law 94-180, Dec. 26, 
1975. 
Public Law 94-355, Jul. 12, 
1976. 
Public Law 94-587, Oct. 22, 
1976. 
Public Law 95-96 Aug. 7, 
1977. 
42-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Dec. 9, 1977, 5th 
Ind. on VXD 
May 31, 1977, 
Letter Report.2 
Jun. 28, 1980 
Energy and 
Water 
Development 
Appropriation 
Act, 1981 
Supplemental 
Appropriations 
Bill for FY 
Ending Sep. 
30, 1985 (PL 
99-88), and the 
Water 
Resources 
Development 
Act of 1986 (PL 
99-662) 
Water 
Resources 
Development 
Act, 1986 
Modification of the Tensas Basin Project, Red River Backwater 
Area, to include a drainage structure and appurtenant channel 
works in the Six Mile Bayou area of Concordia Parish, LA 
The establishment of the Tensas River National Wildlife Refuge 
for the preservation and development of environmental 
resources and in lieu of mitigation acquisitions which 
otherwise would be required for certain water resources 
projects, within designated limits, in the basins of the Tensas, 
Boeuf, and Red Rivers in the State of Louisiana. 
For expenses necessary for prosecuting work of flood control 
projects, rescue work, repair, restoration or maintenance of 
flood control projects threatened or destroyed by flood, 
$232,519,000: Provided, That not less than $250,000 be 
available for control of bank erosion of streams in the Yazoo 
Basin, including the foothill area. Provided further, That funds 
for the Tensas Basin Red River Backwater Area, be used for 
flood control, etc. for Sicily Island and Below Red River 
including pumping stations. 
Authorizes and directs the Secretary of the Army acting 
through the Chief of Engineers to proceed with planning, 
design, engineering and construction of 41 water resources 
projects, including Atchafalaya Basin Floodway System. For 
the Atchafalaya Basin Floodway Systems project, cost-sharing 
is only required for the recreation feature of the project. The 
flood control and environmental features are Federal costs. 
Sec. 104(a), Authorization of Projects - Authorization of 
Construction: 
Incorporation of the project for flood control, Louisiana State 
Penitentiary levee, Mississippi River, LA: Report of the Chief 
of Engineers, dated Dec. 10, 1982, at a total cost of $23,400,000, 
with an estimated first Federal cost of $17,600,000 and an 
estimated first non-Federal cost of $5,800,000. No acquisition 
of land for or actual construction of the project may commence 
until appropriate non-Federal interests shall agree to 
undertake measures to minimize the loss of fish and wildlife 
habitat lands in the project area. 
a. Bushley Bayou, LA. Water Resources Development Act of 
1986 authorized the project for flood control, Bushley 
Bayou, LA. 
b. Eight Mile Creek, Paragould, AR. Project entails channel 
improvement along the creek with miniparks and hiking/ 
biking trails. 
c. Helena and Vicinity, AR. The Helena Basin is an urban 
basin containing approximately 3,500 acres which 
frequently and severely floods the city of Helena. A 
pumping station and sump with channel enlargement and a 
gated culvert was recommended. 
d. West Memphis and Vicinity, AR. Channel improvements 
along Ten Mile Bayou and Fifteen Mile Bayou for a total of 
23.86 miles, with limited revegetation of right-of-way to 
maintain environmental stability. 
e. St. Johns Bayou and New Madrid Floodway, MO. Flood 
control for urban and rural land. 
f. Nonconnah Creek and Johns Creek, TN and MS. Channel 
enlargement, recreation features with channel construction 
and environmental enhancement. 
Unpublished Vicksburg 
District report dated May 
31, 1977, on Cynthia and 
Six Mile Bayous, LA 
Public Law 96-285, Jun. 28, 
1980. 
Public Law 96-367, Oct. 1, 
1980. 
FY 1985 Supplemental 
Appropriations Bill (PL 
99-88), and Water 
Resources Development 
Act of 1986 (PL 99-662). 
Public Law 99-662, Nov. 17, 
1986. 
42-26

MISSISSIPPI RIVER COMMISSION 
TABLE 42-D AUTHORIZING LEGISLATION 
(Continued) 
Act or 
Authorization Work Authorized Document 
g. Horn Lake Creek and Tributaries, TN and MS. This is an 
urban flood control project located in extreme northwest 
Mississippi and southwest Tennessee. The plan of 
improvement consists of 3.5 miles of selective drift removal 
on lower Horn Lake Creek and 2.6 miles of vegetative 
clearing on Horn Lake Creek, 2.1 miles on Rocky Creek and 
0.6 miles of vegetative clearing and 1.8 miles of channel 
enlargement on Cow Pen Creek. Hike/bike trails are 
included along Rocky Creek and Cow Pen Creek. 
Sec. 601(a) Authorization of Projects. Authorization of 
Construction: 
a. Yazoo Backwater Area, MS. Authorized the project for 
mitigation of fish and wildlife losses at the Yazoo 
Backwater Project, MS. The project shall include 
acquisition of 40,000 acres for mitigation of project-induced 
fish and wildlife losses. 
b. Greenville Harbor, MS. Authorized the project for 
navigation, Greenville Harbor, MS, as contained in the 
reports of Chief of Engineers, Nov. 15, 1977 and Feb. 2, 
1982, at a total cost of $43,700,000 with an estimated first 
Federal cost of $28,000,000 and an estimated non-Federal 
cost of $15,700,000. 
c. Vicksburg, Harbor, MS. Authorized the project for 
navigation, Vicksburg Harbor, as contained in the report of 
the Chief of Engineers, Aug. 13, 1979, at a total estimated 
first Federal cost of $55,900,000 and an estimated non- 
Federal first cost of $23,300,000. 
d. Helena Harbor, Phillips County, AR. The recommended 
plan consists of dredging a navigation channel to provide 
access to 685 acres of landfill; construction of an overlook 
park; implementing landscaping and erosion control 
measures; and mitigation fish and wildlife losses. The 
project is scheduled to be constructed in two phases. 
e. White River Navigation to Batesville, AR. The plan of 
improvement recommmended in the Feasibility Report 
provides for construction and maintenance to provide a 200- 
foot wide, 9-foot deep channel available 95 percent of the 
time from mile 10 (Arkansas Post Canal) to mile 254, two 
scenic overlooks, a primitive camping area, and acquisition 
of about 1865 acres of woodlands for mitigation. However, 
section 52 of the Water Resources Development Act of 
1988 deauthorized this project. 
f. Obion Creek, KY. To prevent headwater flooding along 
tributary streams and backwater flooding of alluvial lands. 
g. Memphis Harbor, Memphis, TN. This is a navigation 
project in the vicinity of Memphis, TN, which would consist 
of dredging and maintaining a 4.9 mile long, 500-foot 
minimum width, 9-foot deep general navigation channel 
with additional dredging as required and strategic 
placement of dredged material to create and provide 
navigation access to 1,000 acres to be developed as a 
waterfront industrial complex. 
Sec. 806. Reelfoot Lake, KY. This project is modified to 
provide that the Federal share of the cost of operating the 
pumping plant feature of such project shall be 50 percent. 
Sec. 836. Mud Lake, Western Tennessee Tributaries. This 
project is modified to provide that the requirements of local 
cooperation shall be (1) 50 percent of the value of the lands, 
easements, and rights-of-way, (2) to hold and save the United 
States free from damages due to the construction works, and 
(3) to maintain and operate all the works after completion. 
42-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Jun. 4, 1987 Modification of Mississipppi Delta Region project to construct Unpublished New Orleans 
salinity control structure at Davis Pond (mile 118) rather than District report, Nov. 1, 
at Myrtle Grove (mile 59). 1984. 
1. Incorporated into Mississippi River and tributaries 
project as shown in Table 42-E. 
2. Date minor modification for blocked drainage was 
approved under delegated authority of the President, Mississippi 
River Commission, and in accordance with Sec. 10(p) 
of the 1946 Flood Control Act (Public Law 79-526). 
3. Date minor modification was approved under discretionary 
authority of Chief of Engineers contained in May 
15, 1928, Flood Control Act, as amended. 
4. Projects approved under the provisions of Sec. 201 
of Flood Control Act of Oct. 27, 1965. 
42-28

MISSISSIPPI RIVER COMMISSION 
TABLE 42-E INCORPORATING AND AUTHORIZING LEGISLATION 
For Last 
Public Full Report 
Act of Law Authorizing See Annual 
Incorporation No. Act Description Report for 
Jul. 24, 1946 79-526 Jun. 22, 1936 Tiptonville-Obion levee and drainage 1941, p. 943 
improvements, TN 
Jul. 24, 1946 79-526 Jun. 22, 1936 Bayou des Glaises diversion ditch, LA 1946, p. 1029 
Jul. 24, 1946 79-256 Jun. 22, 1936 From North Little Rock, AR, to Gillett, AR, on 1946, p. 1053 
north bank of Arkansas River (portion below 
Plum Bayou). 
Jul. 24, 1946 79-256 Aug. 18, 1941 White River levees, Augusta to Clarendon and De 1946, p. 1083 
Valls Bluff, AR 
Jul. 24, 1946 79-526 Dec. 22, 1944 Boeuf and Tensas Rivers and Bayou Macon, LA 1945, p. 982 
Jul. 24, 1946 79-526 Dec. 22, 1944 Big Sunflower River, etc. 1946, p. 1061 
Jun. 30, 1948 80-858 Jul. 24, 1946 Devils Swamp barge channel at Baton Rouge, LA 1948, p.1059 
(Baton Rouge Harbor) 
May 17, 1950 81-516 Jun. 22, 1936 Jonesville, LA 1953, p.773 
May 17, 1950 81-516 Jul. 24, 1946 Lake Pontchartrain-Jefferson Parish, LA 1953, p. 737 
42-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-F SUMMARY OF PRESENTLY ESTIMATED 
FEDERAL FIRST COST OF AUTHORIZED IMPROVEMENTS 
Estimated Cost' 
Project Title Fiscal Year 1989 
Completed features 2 
Mississippi River levees 
Mud Lake Pumping Station, TN 
Sec. 6 levees, 1928 Flood Control Act 
Channel improvement 
Atchafalaya Basin, LA 
Atchafalaya Basin Floodway System, LA 
Bayou Cocodrie and tributaries, LA 
Old River, LA 
Lower Red River- South Bank Red River levees, LA 
Eastern Rapides and South-Central Avoyelles Parishes, LA 
Mississippi Delta Region, LA 
Tensas Basin, AR and LA 
Lower Arkansas River, AR 
Grand Prairie-Bayou Meto, AR (Flood Control & Water Supply) 
Yazoo Basin, MS 
Lower White River, AR (All except Big Creek & Tribs.) 
Lower White River (Big Creek & Tribs.) 
Cache Basin, AR 
St. Francis Basin, AR and MO 
Eight Mile Creek, AR 
L'Anguille Basin, AR 
West Tennessee Tributaries, TN 
Harris Fork Creek, TN & KY 
Reelfoot Lake-Lake No. 9, TN & KY 
Reelfoot Lake, TN & KY (Completed) 
Reelfoot Lake-Lake No. 9, TN & KY 
West Kentucky Tributaries, KY 
Tensas River National Wildlife Refuge 
Sardis Dam (Dam Safety Assurance) 
St. Johns Bayou and New Madrid Floodway 
Nonconnah Creek 
Horn Lake Creek and Tributaries 
Greenville Harbor 
Memphis Harbor (Ensley Berm) 
Helena Harbor 
Helena AR and Vicinity 
West Memphis AR and Vicinity 
Vicksburg Harbor, MS 
Louisiana State Penitentiary Levee 
Teche Vermilion Basin 
Mississippi and Louisiana Estuarine Areas 
TOTAL 
$ 199,238,000 
1,310,000,000 
5,124,000,0003 
4,000,0003 
3,257,000,000 
1,470,000,000 
149,000,000 
20,400,0003 
301,300,000 
22,900,0003 
50,000,0003 
61,500,000 
489,000,000 
35,000,0003 
130,900,0003 
1,566,000,000 
16,802,0003 
45,090,0003 
137,000,000 
374,000,000 
13,206,000 
15,100,0003 
120,000,000 
14,964,0003 
(10,500,000)3 
440,000 
10,060,000 
24,000,0003 
40,000,0003 
29,300,000 
77,000,000a 
16,600,0004 
2,130,0004 
31,600,000' 4 
23,000,0004 
33,800,0004 
12,300,00034 
13,500,0004 
55,900,0004 
18,800,0004 
35,700,0004 
57,000,0005 
$15,407,530,000 
1. Inflation projected through the construction period. 
Harbors; Lake Pontchartrain; Wolf River; completed roads 
2. Includes Bonnet Carre', Morganza, and New Madrid 
Floodways; Memphis, Greenville, and Vicksburg on main 
stem levees; channel construction works; Atchafalaya River 
and Basin; Wax Lake Outlet; Charenton Canal; Bayou des 
Glaises diversion channel, Boeuf Basin levees; Grant's Canal; 
De Valls Bluff, Jonesville, and Des Arc protection works; 
Baton Rouge Harbor; and miscellaneous features; Teche- 
Vermilion Basins, LA. 
3. Incremental (not projected through the construction 
period.) 
4. Authorized by Water Resources Development Act 
of 1986, Public Law 99-662, Nov. 17, 1986. 
5. New start in FY 1991. 
42-30 
/ 1 I 
i i _ I ____ ~ I I j j

MISSISSIPPI RIVER COMMISSION 
TABLE 42-G MISSISSIPPI RIVER MAIN STEM 
CHANNEL IMPROVEMENTS
Operations in 1,000 Cubic Yards 
Location Fiscal Year 1989 
Mileage 
Above Head Channel 
District of Passes Construction Maintenance Total 
New Orleans 
Baton Rouge Harbor 
(Devils Swamp) 235 --- 
Main stem channel 234-320 - 3,840.0 3,840.0 
Vicksburg 
Main stem channel 322-600 - 3,431.1 3,431.1 
Vicksburg Harbor 437 - 249.1 249.1 
Greenville Harbor 537 - 336.3 336.3 
Memphis 
Main stem channel 600-954 - 40,955.1 40,955.1 
Memphis Harbor, 
McKellar Lake 725 - 3,092.7 3,092.7 
TOTAL - 51,904.3 51,904.3 
42-31

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction Nonop- O 
erative t 
Above New Work Since T 
Head Bank Exten- Prior I 
Location of R sion Lap Reinforcement FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (L 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) F
pera- 
Live 
'hru 
This 
FY 
inear 
'eet) 
MISSISSIPPI RIVER 
Standard revetment: 
Venice, LA .................. 
Lower Childress- 
Fort Jackson, LA ............ 
Buras, LA ................. 
Tropical Bend, LA ........ 
Bayou Lamoque, LA ........ 
Port Sulphur, LA ............ 
Point Michel, LA ............. 
Bohemia, LA ................ 
Diamond, LA .............. 
Gravolet, LA ................. 
Junior, LA .................. 
Harlem, LA ................ 
Myrtle Grove, LA ............ 
tr Monsecour, LA ............... 
.' Alliance, LA ............... 
S Belair, LA ................... 
Jesuit Bend, LA ............ 
Linwood, LA .............. 
Oak Point, LA ............... 
Scarsdale, LA ............... 
English Turn, LA .......... 
Poydras, LA ................. 
Cutoff, LA ................. 
Third district reach, LA ...... 
Algiers Point, LA ............ 
Gouldsboro Bend, LA ....... 
Gretna Bend, LA ........... 
Greenville Bend, LA ........ 
Carrollton Bend, LA ........ 
Avondale Bend, LA ........ 
Kenner, LA ................ 
Luling, LA ................. 
Good Hope, LA ............... 
Waterford, LA ............... 
Montz, LA ................... 
Lucy, LA ................. .. 
Reserve, LA .................. 
Willow Bend, LA ........... 
Angelina, LA .............. 
Vacherie, LA .............. 
Belmont, LA ............... 
12 
22 
25 
30 
33 
39 
44 
46 
49 
51 
54 
56 
59 
61 
62 
65 
68 
71 
72 
75 
78 
82 
88 
93 
95 
96 
97 
100 
104 
109 
114 
119 
126 
128 
132 
136 
138 
141 
145 
148 
152 
R
RRRL
RRL
RL
RL
RLRL
RLRL
RL
RL
RR
RRL
RL
RL
RL
RL
RL 
R
L 
1,387 
2,807 
2,671 
708 
7,380 
4,437 
2,033 
12,730 
56 
532 
25,852 
20,302 
8,120 
58,709 
1,037 
1,939 
2,212 
712 
3,323 
7,672 
14,203 
14,917 
3,455 
4,974 
9,746 
8,515 
3,727 
15,823 
7,962 
1,500 
14,157 
11,300 
4,624 
- 27,802 m 
- 15,430 
- 17,283 
- 25,012 y 
- 7,264 4 
- 36,995 b. 
- 21,932 0 
- 14,981 j 
- 11,600 - 
17,435 x 
- 23,599 m 
- 15,148 ' 
- 17,435 
- 11,571 
- 15,745 
- 26,111 0 
- 24,978 
- 10,638 
- 12,377 < 
13,852 r 
- 19,718 
- 45,864 0 
- 21,256 4 
- 27,167 
- 7,728 
- 4,960 > 
- 9,662 
- 22,045 
- 15,015 5 
- 28,409 4 
- 37,167 p 
- 36,288 
- 18,888 
16,732 O 
- 17,502 
- 17,826 
- 20,947 '� 
- 11,631 e 
- 31,727 
- 26,025 
- 25,575 
0
0

Rich Bend, LA ............... 
Romeville, LA ............... 
St. Alice, LA ................ 
Burnside, LA .............. 
Aben, LA .................. 
St. Elmo, LA ................ 
Smoke Bend, LA ............. 
Marchand, LA ............. 
Philadelphia Point, LA ....... 
New River Bend, LA ......... 
White Castle, LA ........... 
St. Gabriel, LA ............. 
Plaquemine Bend, LA ........ 
Manchac, LA ............. 
Missouri Bend, LA ........... 
Arlington, LA ............... 
Port Allen, LA .............. 
Allendale, LA ................ 
Springfield Bend, LA ......... 
Arboth, LA ................ 
Faulkner Lake, LA ........... 
Grand Bay, LA ............. 
Bayou Sara, LA .............. 
Red Store, LA ............... 
Arrow Bend, LA ............ 
Boies Point, LA .............. 
Morganza, LA ............. 
Iowa Point, LA .............. 
Brunette Point, LA ........... 
Greenwood Bend, LA ....... 
Hog Point, LA ............. 
Carr Point, LA ............. 
Above Old River, LA ......... 
Fort Adams, MS ........... 
Point Breeze, LA ........... 
Coochie, LA ................ 
Palmetto, MS .............. 
Subtotal 
New Orleans District, 
Mississippi River ....... 
Dikes: 
Profit Island Chute 
Closure, LA ............. 
OLD RIVER CONTROL 
Standard revetment: 
Inflow channel ............... 
Inflow channel ............... 
Outflow channel ............. 
Auxiliary inflow channel ....... 
Auxiliary outflow channel ...... 
Total standard revetment, 
Old River .............. 
157 
161 
165 
170 
172 
174 
177 
180 
183 
185 
193 
201 
209 
215 
222 
227 
231 
238 
244 
250 
253 
258 
265 
269 
272 
275 
279 
282 
285 
289 
296 
304 
305 
308 
313 
317 
322 
RL
RL
RL
RL
RL 
R
LRLRLRRLRLRLRLRRLRLRRRLRRL 
4,341 
4,404 
1,637 
6,292 
10,251 
5,382 
4,483 
3,496 
1,439 
4,800 
46 18,345 
54 15,948 
296 8,384 
75 33,016 
54 31,715 
208 24,324 
79 17,979 
62 19,898 
36 2,904 
- 12,796 
483 2,766 
17,202 
7,156 
6,038 
33,163 
25,966 
27,052 
29,304 
11,700 
10,240 
17,075 
16,436 
5,379 
43,665 
42,658 
31,292 
37,777 
38,976 
22,632 
12,244 
17,627 
25,502 
25,690 
13,190 
17,382 
7,090 
27,698 
11,315 
13,600 
16,094 
20,513 
11,375 
8,038 
14,987 
13,368 
8,600 
4,800 
17,219 
13,565 
17,150 
30,864 
2,297 
12,720 
7,818 
73,105 
(13.85 Miles) 
252 
315 
315 
315 
312 
312 
L
LR 
L&R 
L&R 
L&R 
1,498 298,292 17,279 
(3.27 Miles) 
85,798 92,774 1,570,546 
(297.45 Miles) 
4,315 
(.82 Mile) 
- - - - - - - 2,415 
- - - - - - - 4,365 
- - - - - - - 19,891 
- - - - - - - 17,200 
- - - - - - - 5,790 
49,661 
(9.41 Miles) 
-.

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction eNroantoivpe- 
Above New Work Since 
Head Bank Exten- Prior 
Location of R sion Lap Reinforcement FY 
Passes or (Linear (Linear (Linear Maintenance (Linear ( 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) 
)pera- a 
tive 1 
Thru 0 
This 
FY 
Linear 
Feet) y 
ATCHAFALAYA RIVER 
Standard revetment: 
Mile One, LA ............ 
Coville, Bayou, LA ........... 
Legonier, LA ................. 
Simmesport, LA .......... 
Kuhlman Bayou, LA ....... 
Odenburg, LA ........... 
Cason, LA ................... 
McCrea, LA ................ 
Woodside, LA .............. 
Provosty, LA ................ 
Crooked Bayou, LA ........... 
Mercier, LA ............... 
Barberton, LA ............. 
Evans Point, LA ............. 
Goudeau, LA ................ 
Morris Bayou, LA .......... 
Goodwood, LA ........... 
Red Cross, LA .............. 
Melville, LA ............... 
Cross Bayou, LA ............ 
Melville South, LA ........... 
Toles, LA ................... 
Petite Prairie, LA ............ 
Holloway Lake, LA ........... 
Bayou Sherman, LA ........ 
Krotz Springs, LA ........ 
Sherburne, LA ............. 
Bayou Big Graw, LA ......... 
Morgan City ............... 
Total standard revetment 
Below Confluence 
of Red and 
Atchafalaya 
Rivers 
1
34679 
12 
13 
14 
17 
18 
22 
23 
24 
26 
27 
28 
29 
30 
31 
33 
35 
36 
37 
38 
40 
43 
46 
115 
L
RL 
RL 
RRLRL 
RL 
RLRL 
RL 
RL 
RL 
RLL 
RRRL 
- - - - - - - 4,150 
- - - - - - - 6,550 
- - - - - - - 8,940 
- - - - - - - 10,636 
- - - - - - - 5,565 
- - - - - - - 5,375 
- - - 10,798 
- - - 5,027 
- - - 13,002 
- - - 7,768 
- - - 9,600 
- - - - - - - 10,478 
- - - 3,592 
- - - 4,898 
- - - 3,938 
- - - 3,800 
- - - 8,505 
- - - 8,065 
- - - 4,870 
- - - 3,815 
- - - 4,070 
- - - 6,355 
- - - 8,381 
- - - 7,085 
- - - 5,200 
- - - 7,925 
- - - 7,035 
- - - 8,394 
- - - 3,410 
- - - - - - 197,227 
(37.35 Miles) 
Dikes: 
None 
mC1 
0.^ 
O
mz 
C
0
CD 
C
00

LOWER RED RIVER 
Standard revetment: 
Long Lake, LA ............... 
Naples, LA ................ 
Turnbull Island, LA ........ 
Total standard revetment 
Below Confluence 
of Old River 
Outflow Channel 
and Red River 
10
79 
RRL 
- - 6,652 
- - 6,190 
- - 11,038 
- - - - - - - 23,880 
(4.52 Miles) 
Dikes: 
None 
1. Gross squares articulated concrete mattress (100 square feet). 
t 
CJ1

TABLE 42-I BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction Nonop- Op 
erative t 
Above New Work Since T 
Head Bank Exten- Prior I 
Location of R sion Lap Reinforcement FY i 
Passes or (Linear (Linear (Linear Maintenance (Linear (Li 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)L (Squares)' Feet) F 
erayve 
hru 
'his 
FY 
inear 
eet) 
MISSISSIPPI RIVER 
Standard revetment: 
Bougere Bend, LA ........... 
Dead Mans Bend, MS ......... 
Glasscock Cutoff,, MS-LA ..... 
Railroad Landing, MS ........ 
St. Catherine Bend, LA ....... 
Morville, LA ............... 
Natchez Island, MS .......... 
Carthage, MS.............. 
Vidalia Casting Field ......... 
Natchez Front, MS ......... 
Giles Cutoff, LA-MS ........ 
Gibson, LA ................. 
Ashland, LA-MS, TF ......... 
Kempe Bend, LA ............. 
Browns Field, LA ............ 
Goldbottom, MS .............. 
Hardscrabble, LA ............ 
Grand Gulf, MS ............ 
Point Pleasant, MS-LA ....... 
Togo Island, LA ............. 
Lake Karnac, LA-MS ....... 
Diamond Point, LA-MS ....... 
Reid-Bedford, LA .......... 
Racetrack, MS ........... 
Barge Line Terminal, MS ..... 
Vicksburg Harbor, MS ....... 
Delta Point, LA ............ 
King's Point-Opposite 
Delta Point, LA-MS ........ 
False Point, LA .............. 
Marshall-Brown's Point, 
LA-MS .................... 
Milliken Bend, LA ........ 
Belle Island, LA-MS ......... 
Goodrich, LA ................ 
Cottonwood Bar, MS, TF ..... 
Fitler-Cottonwood, MS ....... 
Hagaman, LA .............. 
Ben Lomond, MS ............. 
Baleshed Towhead-Stack 
Island, LA-MS ............. 
Lake Providence, LA ......... 
329 
335 
342 
346 
350 
356 
357 
361 
363 
364 
366 
371 
374 
383 
389 
392 
398 
403 
413 
415 
419 
423 
429 
433 
437 
437 
437 
439 
443 
446 
453 
460 
467 
470 
474 
481 
486 
488 
489 
RL
RLRRRLLL
RRL
RRL
RL
RRL
RRLLL 
R
L
R
L
RL
RRLRL 
R
R 
6,424 
4,900 
670 
3,195 
1,715 
- 23,465 
- 15,791 
- 3,588 
- 7,322 
- 3,233 
- - 
- - 
- - 
- - 
- - 
-
280 
408 
130 
2,254 
730 
1,935 
2,800 
6,529 
1,127 
1,042 
496 
8,484 
1,914 
730 3,613 
0
0
,.. .. 
- 26,055 n 
- 3,774 � 
- 6,865 
- 12,265 H 
- 28,093 * 
- 14,855 
- 2,180 
- 14,700 O 
- 2,670 
- 6,510 
- 3,195 
- 25,945 g 
- 27,092 m 
- 28,285 
- 9,280 4 
- 30,250 o 
- 22,530 Z 
- 53,948 n 
- 32,345 p 
- 7,064 
- 19,260 M 
- 12,125 4 
18,392 O 
13,935 
3,040 
- 7,350 , 
- 7,650 n 
- 19,330 , 
- 12,860 
- 19,580 
- 44,650 m 
- 24,160 0 
- 39,155 m 
- 21,360 i 
- 28,427 4 
- 37,756 - 
10,235 ? 
- 52,1242 
- 11,600

Mayersville, MS .............. 
Sarah Island-Opossum Point, 
LA-MS ............... 
Carolina, MS ............... 
Cracraft, AR ................ 
Worthington, MS-AR ........ 
Walnut Point Kentucky 
Bend, MS ............. 
American Cutoff, MS-AR ..... 
Sunnyside-Lakeport, AR...... 
Vancluse, AR .............. 
Island 84, AR, MS .......... 
Warfield Point, MS ......... 
Leland-LaGrange, AR-MS .... 
Spanish Moss, AR .......... 
Tarpley Island, MS ........... 
Miller Bend, MS ............. 
Island 82, AR .............. 
Ashbrook Island, MS ......... 
Arkansas City-Yellow 
Bend, AR ................ 
Huntington Point, MS ........ 
Pair O'Dice, AR ............ 
Eutaw-Mounds, MS ........ 
Cypress Bend, AR ......... 
Catfish Point, MS ........... 
Ozark, AR-MS ............. 
Prentiss, AR-MS ........... 
Rosedale Bend, AR ........... 
Riverton, MS ................ 
Klondike, AR .............. 
Victoria Bend-Terrene, MS .... 
Lake Concordia, MS ........ 
Big Island, AR ............... 
Smith Point, MS ........... 
Dennis, MS ................ 
Cessions, MS ............... 
Total revetment, 
Vicksburg District, 
Mississippi River ......... 
Dikes: 
Jackson Point, MS ............ 
Opposite Warnicott Ldg, MS 
Natchez Island, LA-MS ....... 
Waterproof Bar, LA ........ 
Spithead Towhead, MS ....... 
Browns Field, LA .......... 
Cottage Bend, LA-MS ........ 
Bondurant Towhead, LA ..... 
Coffee Point, LA ........... 
Yucatan, MS ................ 
Togo Island, LA .............. 
Below Racetrack, MS ......... 
Racetrack Towhead, MS ...... 
False Point, LA ............ 
Marshall Cutoff, LA.......... 
497 
503 
507 
511 
514 
519 
526 
530 
534 
535 
537 
538 
539 
542 
544 
546 
549 
553 
556 
561 
563 
568 
573 
578 
582 
585 
586 
588 
593 
596 
598 
601 
611 
615 
L
RL
RR 
LL
RRLLL
RRL
RR 
RL
RL
RL
RLLL
RLLRLLL 
34,992 
- 23,825 
- 11,080 
- 22,210 
- 8,350 
- 45,653 
- 2,980 
- 33,685 
- 4,300 
- 13,475 
- 4,320 
- 14,150 
- 4,580 
- 2,000 
- 29,360 
- 3,080 
- 3,455 
7,022 
- 
17,790 650 2,311 
1,700 
28,661 
(5.43 Miles) 
330 
352 
358 
379 
386 
388 
389 
394 
405 
410 
416 
430 
431 
441 
448 
LL
RRL
RL
RRRLL
RR 
R 
77,718 
5,196 
6,882 24,183 
(3) 
2,949 
5,388 
- 40,560 4 
- 17,067 - 
- 9,095 " 
- 40,188 
- 26,585 g 
- 20,075 ( 
- 22,015 P 
- 20,315 - 
- 4,820 E 
- 12,500 < 
- 23,400 m 
- 29,245 3 
- 8,340 C 
- 16,515 
- 18,185 
- 25,195 - 
- 10,910 
t1 
- 1,401,362 
(265.41 Miles) 
- 4,306 
- 5,351 
- 10,885 
- 14,321 
- 3,6614 
- 4,8354 
- 14,049 
- 4,421 
- 8,648 
- 9,010 
- 8,256 
- 11,7694 
- 1,752 
- 5,355 
- 5,1664 
C

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction eNroantiovpe- 
Above New Work Since 
Head Bank Exten- Prior 
Location of R sion Lap Reinforcement FY 
Passes or (Linear (Linear (Linear Maintenance (Linear ( 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Forest Home Towhead, LA .... 
Willow Cutoff, LA ......... 
Arcadia Point, MS ......... 
Point Lookout, LA ............ 
Ajax Bar, MS ............. 
Ben Lomond, MS ............ 
Balshed Ldg., MS .......... 
Wilson Point, LA ........... 
Corregidor, MS ............ 
Carolina, AR ................ 
Cracraft Lower, AR ........ 
Cracraft, AR ................ 
Leota, MS .............. 
Island, 86, AR ............. 
Seven Oaks, AR ............ 
Walnut Point, MS .......... 
Refuge, MS .............. 
Island 84, AR ................ 
Leland Bar, AR-MS .......... 
Leland Neck, AR-MS ......... 
Tarpley Cutoff, MS-AR ....... 
Island 82-Miller Bend, 
AR-MS .................. 
Ashbrook-Miller Bend, 
AR-MS .................... 
Ashbrook Cutoff, MS ....... 
Chicot Ldg., AR .............. 
Catfish Point, MS ......... 
Below Prentiss, MS .......... 
Malone Field, AR ......... 
Terrene, MS ............... 
White River Landing, AR ..... 
Montgomery Towhead, AR .... 
Victoria Bend, AR ......... 
Smith Point, MS ............. 
Island 70, MS .............. 
Total dikes, 
Vicksburg District, 
Mississippi River ....... 
449 
462 
470 
478 
482 
488 
493 
500 
505 
509 
510 
513 
514 
520 
523 
525 
528 
532 
538 
540 
540 
544 
547 
549 
564 
571 
580 
585 
590 
591 
592 
596 
600 
608 
L
RL 
RLLL 
RLL 
RRL 
RRLLL 
RL 
R 
1,970 
2,600 
- 
2,600 
Operative 
Thru 
This 
FY 
Linear 
Feet) 
0
0 
4,5744 c 
4,2754 
9,4634 
2,751 
24,319 
24,6674 
10,938 O 
3,592 
6,730 y 
2,897 
9,614 
3,809 
7,571 
14,433 
5,754 0 
4,725 
5,278 
4,580 
16,878 
4,315 - 
10,318 
O 
13,646 
13,015 
8,728 
17,451 n 
5,290 
7,813 
7,549 
7,921 m 
2,201 r 
6,071 O 
5,0334 0 
7,617 
14,949 
D 
410,550 e 
(77.76 Miles) 
R&L 
L&R 
L
RL 
RRL 
RRRLL 
12,907 
(2.44 Miles) 
00

ARKANSAS RIVERS 
Standard Revetment: 
Menard Bend, AR .......... 
Como, AR ..................... 
Morgan Bend, AR ............ 
Yancopin, AR ............... 
Total standard revetment, 
Arkansas River ........ 
Dikes: 
Hopedale Cutoff, AR ......... 
Morgan Bend, AR ......... 
Fletcher Bend, AR ........... 
Total dikes, Arkansas River .... 
RED RIVER6 
Standard revetment: 8 
Dupre, LA ................. 
Bringol, LA ................ 
Egg Bend, LA ............ 
Cologne Bend, LA ......... 
Roxana, LA ................ 
Ryland, LA .................. 
Whittington, LA ............. 
Smith, LA ................. 
Latanier, LA ................ 
Hudson, LA ................ 
Robert, LA ................. 
Alexandria Front, LA ........ 
Callahan, LA ................. 
Cotton, LA ................. 
Rapides, LA ................. 
Boyce, LA ............... 
Total standard revetment, 
Red River ............ ..... 
Dikes7 : 
Choctaw Bayou Bend, LA ..... 
Bringol (Egg Bend), LA ...... 
Egg Bend,LA ............. 
Cologne Bend, LA ......... 
Echo, LA .................. 
Richardson, LA ............ 
30 
36 
39 
69 
73 
75 
77 
83 
88 
89 
91 
93 
99 
102 
105 
110 
116 
119 
125 
71 
73 
75 
77 
78 
79 
RL 
R 
1,848 
3,658 
2,187 
7,693 
(1.46 Miles) 
RR
RRRRRRR 
R
R
RRRRR 
. -2,690 
. -4,000 
. -2,400 
. -650 
. -3,325 
. -3,925 
. -2,900 
. -2,700 
- - - - - - 2,460 
. -1,458 
. -5,500 
. -5,280 
. -4,000 
. -14,700 
. -1,030 
. -4,548 
. -61,566 
(11.66 Miles) 
RRRRRR 
2,000 
2,477 
900 
1,850 
1,900 
2,700 
Miles 
Above 
Mouth 
31 
34 
36 
24 
L
RL 
R 
tC 
11,770 
11,720 
5,250 
2,800 
31,540 
(5.97 Miles) 
CI) 
I) 
C) 
C,

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction Nonoperative 
Above New Work Since 
Head Bank Exten- Prior 
Location of R sion Lap Reinforcement FY 
Passes or (Linear (Linear (Linear Maintenance (Linear 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)l (Squares)' Feet) 
RED RIVER7 
continued 
Dikes': 
Alexandria, LA ............. 105 R - - - - - - (Rock groin) 
Bertrand, LA .............. 122 R - - - - - - 
Total dikes, Red River ......- - - - - - (3.7 
1. Gross squares articulated concrete mattress (100 square feet). 
2. Contains 7,814 linear feet of trenchfill revetment (stone). 
3. Linear feet of dike on which repairs were made. 
4. Changed to correct previous errors. 
0 
Operative 
Thru 
This 
FY 
(Linear 
Feet) 
270 
7,630 
19,727 
74 Miles) 
5. See report on Arkansas River and tributaries, AR and OK, under Little Rock District. 
6. Mileages based on 1967 hydrographic survey. 
7. Includes all types of dikes and retards.

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction Nonop- Op 
erative t 
Above New Work Since T 
Head Bank Exten- Prior T 
Location of R sion Lap Reinforcement FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Li 
(Miles) L Feet) Feet) (Squares)1 Feet) (Squares) (Squares1) Feet) F 
)eraive 
hru 
'his 
FY 
near 
eet) 
MISSISSIPPI RIVER 
Standard revetment: 
Big Island, AR ............. 
Scrubgrass Bend, AR ......... 
Henrico, AR ............ 
Cessions Towhead, AR ........ 
Knowlton, AR ............... 
Island 67, MS ............. 
Island 68 Bar, AR ............ 
Ludlow, AR ............... 
Rescue Landing, AR-MS ...... 
Fair Landing, AR........... 
Burke Landing, MS .......... 
Island 62, AR .............. 
Island 63, MS .............. 
Island 63 Bar, MS ............ 
Oldtown Bend, AR ........... 
Horseshoe, MS .............. 
Westover, AR .............. 
Delta-Friars Point, MS ....... 
Helena, AR ................. 
Trotters Landing, MS ....... 
Flower Lake, MS ............ 
St. Francis, AR ............. 
Harbert Point, MS ........... 
Walnut Bend, AR ............ 
Mhoon Bend, MS ............. 
Peters, AR ................. 
Commerce, MS .............. 
Porter Lake, AR ............ 
Pickett, MS-AR .............. 
Norfolk-Star, MS ............ 
Cow Island Bend, AR ......... 
Cow Island Bend (Upper), TN 
-Coahoma, TN ................ 
Ensley, TN ................ 
Dismal Point, AR .......... 
Bauxippi-Wyanoke, AR ....... 
Presidents Island, TN ...... 
Hopefield Point, AR, TN ...... 
Loosahatchie-Memphis, TN .... 
Loosahatchie Bar, TN ....... 
St. Clair, AR ................ 
Island 40, TN-AR ............ 
Brandywine, AR-TN ........ 
598 
600 
606 
615 
620 
621 
622 
626 
629 
632 
637 
638 
639 
639 
644 
647 
650 
655 
660 
665 
667 
672 
675 
680 
685 
692 
695 
700 
703 
709 
714 
716 
717 
723 
724 
730 
733 
736 
737 
740 
742 
744 
750 
RRRL 
RL 
RRL 
RL 
RLL 
RL 
RL 
RLL 
RL 
RL 
RL 
RRL 
RRLL 
RRL 
RL 
RRRR 
4,620 15,288 
- 
5,702 
12,709 
- 3,905 
- 7,315 
- 25,040 
- 10,615 
- 16,900 
- 8,735 
- 6,445 
- 10,390 
- 27,020 
- 25,690 
- 19,070 
- 9,030 
- 11,5192 
- 3,795 
- 26,860 
- 16,385 
- 12,730 
- 30,090 
- 36,460 
- 32,905 
- 16,385 
- 24,663 
- 9,065 
- 27,220 
- 35,828 
- 33,760 
- 29,085 
- 34,155 
- 12,575 
- 35,582 
- 22,274 
- 6,853 
- 9,270 
- 44,026 
- 7,200 
- 24,530 
- 12,755 
- 10,360 
- 31,293 
- 2,070 
- 2,9303 
- 30,750 
- 18,010

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction Nonoperative 
Above New Work Since 
Head Bank Exten- Prior 
Location of R sion Lap RenforcementFY 
Passes or (Linear (Linear (Linear Maintenance (Linear ( 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) 
MISSISSIPPI RIVER 
continued 
Standard Revetment: 
Shelby Forest, TN ............ 
Dean Island, AR ............. 
Cedar Point-Densford, TN .... 
Chute of Island 35, TN ........ 
Lookout Bar, TN ........... 
Lookout, TN ................. 
Sunrise Towhead, TN ........ 
Lower Bullerton, AR ......... 
Kate Aubrey Towhead- 
Island 30, TN ............ 
Osceola, AR ................ 
Osceola, AR ................ 
Ashport-Keyes Point, TN ..... 
Kate Aubrey, TN ......... 
Island 26, TN ............... 
Bend of Island 25, TN ........ 
Barfield, AR ............... 
Obion-Tamm, TN ......... 
Huffman-Hickman, AR-TN .... 
Heloise, TN ................ 
Island 18, MO .............. 
Linwood Bend, TN ........... 
Blaker Towhead, TN ......... 
Bells Point, MO ............ 
Gayoso-Caruthersville, MO .... 
Island 15, TN .............. 
Hathaway Landing, TN ...... 
Robinson Bayou, MO ......... 
Fritz Landing, TN ........... 
Lee Towhead, MO .......... 
Bend of Island 14, TN ........ 
Above Lee Towhead, TN ...... 
Little Cypress, MO ........... 
Merriwether-Cherokee, TN .... 
Linda, MO ................... 
Below Toney's Towhead, TN .... 
Toney's Towhead, KY-TN ..... 
Kentucky Point, KY ........ 
New Madrid Bar, KY ........ 
New Madrid Bend, MO ....... 
La Forge, MO .............. 
753 
756 
759 
764 
772 
774 
776 
782 
786 
786 
786 
791 
793 
798 
803 
808 
819 
826 
831 
836 
841 
845 
845 
848 
851 
852 
852 
857 
859 
859 
861 
864 
869 
876 
879 
882 
887 
888 
889 
892 
LRLRRRRR 
RP 
R
L
RRLRLRLRL 
L
RRLL
RLLLL
RL
RLLLRRR 
325 1175 
-
- 
6,890 
1,7306 
6,595 
3,870 
980 
7,184 
760 
3,656 
- 9,550 
- 7,555 
- 20,190 
- 29,190 
- 2,9903 
- 5,005 
- 14,615 
- 28,350 
- 30,808 
- 1,3504 
- 5,823 
- 44,232 
- 2,500 
- 15,690 
- 30,630 
- 50,965 
- 51,321 
- 26,984 
- 12,935 
- 22,170 
- 14,850 
- 17,087 
- 5,420 
- 25,600 
- 3,630 
- 1,000 
- 22,630 
- 15,670 
- 8,470 
- 12,050 
- 4,943 
- 34,090 
41,058 
- 11,950 
- 20,895 
- 12,600 
- 7,960 
- 16,825 
- 43,262 
- 22,380 
)perative 
Thru 
This 
FY 
Linear 
Feet) 
go 
0
0
0
so 
0
y
0M
C, 
0
M
y
x
c 
O
2
c
r 
O
c
y
C
y 
O 
d 
C
co 
0 
oo 
e

Slough Landing Neck, 
TN-KY .................... 
Winchester Towhead, MO ..... 
Island 9, KY-TN ........... 
Milton Bell, MO ............ 
Chute of Island 8, KY ....... 
Bend of Island 8, MO ......... 
Island 8, KY ............... 
Hickman-Reelfoot, KY ........ 
Beckwith Bend, MO .......... 
Williams, KY ................ 
Wolf Island, KY ............. 
Columbus, KY ............. 
Belmont, MO ................ 
Island 3 and 4, KY ......... 
Campbell, KY ............... 
Pritchard, MO ............. 
Mayfield Creek, KY .......... 
Wickliffe, KY ................ 
Cache-Cairo, IL (Ohio River) .... 
Total revetment, 
Memphis District, 
Mississippi River ....... 
,. Dikes: 
c Henrico, AR ................. Below Knowlton, AR ......... 
Island 67, MS ................ 
Below Ludlow, AR ......... 
Sunflower, AR ............. 
Island 64, AR ................ 
Island 62, AR .............. 
Island 63 Bar, MS ............ 
Island 63, MS .............. 
Kangaroo Point, AR ........ 
Friars Point, MS ........... 
Montezuma Bar, MS ....... 
Montezuma Towhead, AR ..... 
Prairie Point, AR .......... 
Flower Lake, MS ........... 
St. Francis Towhead, MS ..... 
Below Walnut Bend, AR ...... 
Bordeaux Point, MS ........ 
Peters, AR ................. 
Commerce, MS ............. 
Basket Bar, AR ............ 
Buck Island, MS ........... 
Porter Lake, AR ........... 
Pickett, MS .......... 
Seyppel, AR ................. 
Cat Island, AR .............. 
Coahoma, TN ................ 
Armstrong, AR-TN ........ 
899 
900 
905 
908 
913 
914 
914 
919 
924 
927 
934 
937 
938 
940 
943 
948 
949 
953 
958 
LRLRLRRL 
RL 
RL 
RRL 
RLL 
R 
5,255 
13,580 
(2.57 Miles) 
603 
616 
621 
624 
627 
630 
638 
639 
640 
649 
652 
657 
656 
668 
668 
671 
676 
681 
693 
694 
696 
700 
701 
704 
706 
710 
718 
720 
R
RLRL 
R
RLL 
RLL 
RRLL 
RL 
RL 
RL 
RL 
RR 
L
R 
5,485 
2,810 
350 
- 
11,578 
5,525 19,937 
85 1,015 
3,082 
3,804 
5,465 29,972 
(R) 
300 
1,620 200 
(9) 
6,340 
2,530 
300 
300 
- 37,520' 
- 5,540 
- 33,5857 
- 14,375 
- 12,620 
- 9,800 
- 18,515 
- 43,359 
- 14,588 
- 10,015 
- 19,205 
- 3,825 
- 5,785 
- 19,970 
- 6,865 
- 15,045 
- 8,935 
- 8,455 
- 26,152 
1,890,910 
(358.13 Miles) 
6,310 C 
15,718 e 
4,320 0 
5,040 O 
5,520 
7,330 E 
23,180 g 
2,600 c 
5,640 p 
5,730 Z 
6,870 
15,240 
3,450 
10,391 
11,060 
3,380 
6,4202 
4,920 
7,830 
8,810 
5,060 
4,705 
17,480 
7,180 
12,250 
15,590 
4,640 
18,690

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1989) 
Operations This FY 
Construction eNroantoivpe- O 
Above New Work Since 
Head Bank Exten-Reinforceme Prior 
Location of R sion Lap FY 
Passes or (Linear (Linear (Linear Maintenance (Linear ( 
(Miles) L Feet) Feet) (Squares)' Feet) (Squares)' (Squares)' Feet) 
MISSISSIPPI RIVER 
continued 
Dikes: 
Dismal Point, AR ......... 
Hopefield Point, AR ........ 
Robinson Crusoe, TN ......... 
Loosahatchie Bar, TN ........ 
Above Loosahatchie, TN ...... 
Redman Point, AR ........... 
Randolph Point, TN .......... 
Poker Point, AR .............. 
Corona Bar, TN-AR ........ 
Densford, TN .............. 
Cedar Point, TN ............ 
Below Richardson Landing, 
TN .......................... 
Lookout, TN-AR ............. 
Plum Point, TN ............. 
Lake Neark, AR ............ 
Island 30 ..................... 
Kate Aubrey, TN ........... 
Keyes Point, TN ............ 
Ashport-Goldust, TN-AR ..... 
Forked Deer, TN ............. 
Island 25, AR .............. 
Nebraska Point, TN ........ 
Below Tamm Bend, TN ....... 
Wrights Point, AR ........... 
Island 21, Chute, TN ....... 
Head of Island 21, TN ........ 
Island 20, MO-TN ......... 
Island 18, TN .............. 
Tennemo, TN ............ 
Blaker Towhead, TN ......... 
Caruthersville-Linwood 
Bend, MO ................ 
Sandy Hook, TN ........... 
Island 15, TN .............. 
Robinson Bayou, MO ......... 
Hathaway, TN ............. 
Island 15 Neck, TN........... 
Above Lee Towhead, TN ...... 
Below Cherokee, TN ........ 
Stewart Towhead, MO ........ 
724 
736 
738 
739 
742 
743 
747 
748 
755 
757 
759 
767 
771 
784 
786 
787 
791 
791 
795 
798 
804 
808 
813 
820 
824 
828 
831 
837 
842 
843 
844 
850 
851 
853 
854 
854 
859 
866 
871 
RRRRL 
RL 
RRLL 
L
RL 
RRRL 
RL 
RLL 
RLL 
RLLL 
RRL 
RLLLL 
R 
2,140 
150 
690 
150 
150 
14,,900700 
2,800 
4,590 
)perative 
Thru 
This 
FY 
Linear 
Feet) 
- 25,510 
- 1,330 
- 21,9391 
- 3,950 
- 8,990 
- 7,750 
- 16,740 
- 8,050 
- 8,430 
- 7,780 
- 2,890 
- 5,950 
- 5,538 
- 9,695 
- 2,5451 
- 3,010 
- 11,270 
- 19,775 
- 17,330 
- 8,5502 
- 5,450 
- 12,149 
- 8,300 
- 34,775 
- 3,170 
- 5,460 
- 18,139 
- 8,670 
- 4,390 
- 4,070 
222 
25,877 
2,350 
8,830 
10,768 
27,355 
21,100 
1,300 
6,230 
18,290 
bI

Ruddles Point, MO .......... 
Island 11, MO ................ 
New Madrid Bend, MO ....... 
Kentucky Point, KY .......... 
Morrison Towhead, MO ....... 
Hotchkiss Bend, MO .......... 
Below Island 9, TN ......... 
Donaldson Point, MO ......... 
Island 9, KY ............... 
Moore Island, KY-MO ........ 
Above Williams, KY .......... 
Campbell, KY ................ 
Pritchard, MO ............... 
Island 1, KY ............... 
Total dikes 
Memphis District, 
Mississippi River ......... 
874 
882 
887 
887 
890 
895 
901 
905 
906 
929 
930 
942 
944 
948 
R
R
RL 
R
RL
RLRLL
RL 
- - - - - - - 8,130 
- - - - - - - 8,039 
- - - - - - - 1,715 
- - - - - - - 11,550 
- - - - - - - 1,070 
- - - - - - - 6,583 
- - - - - - - 18,859 
- - - - - - - 8,320 
- - - - - - - 7,0109 
- - - - - - - 4,685 
- - - - - - - 1,1508 
- - - - - - - 2,610 
- - - - - - - 9,390 
- - - - - - - 15,260 
10,435 
(1.98 Miles) 
12,550 12,940 222 776,295 
(147.03) Miles 
Gross squares articulated concrete mattress (100 square feet). 
Changed to correct previous errors. 
Lumber mattress revetment. 
Rock Groins. 
Ed Jones boat ramp construction. 
6. Includes 140 feet not reported in FY 88. 
7. Stone in pile dike. 
8. Linear feet of dike on which repairs were made. 
9. Linear feet of triangular frame retards and pile dikes. 
1. 
2. 
3. 
4. 
5. 
-----

TABLE 42-K PROJECT LEVEES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1989) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
In Total System Corn- System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Corn- This This Corn- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MAIN STEM LEVEES 
Mississippi River Levees 
Fifth Louisiana Levee District ...... 
Levees ......................... 
Old River structures and levees ... 
Atchafalaya Basin Levee District ... 
Levees ....................... 
Morganza structure and levee .... 
Morganza forebay levee ......... 
Port Allen lock ................... 
Lafourche Basin Levee District Levees 
Plaquemines West Levee District Levees 
Buras Levee District ............... 
Levees ............................ 
Empire lock .................... 
Baton Rouge front levees ........... 
Pontchartrain Levee District ........ 
Levees ......................... 
Bonnet Carre' guide levees ....... 
Bonnet Carre' forebay levee ...... 
Bonnet Carre' structure .......... 
East Jefferson Levee District Levees . 
West Jefferson Levee District ....... 
Levees ......................... 
Floodwalls ..................... 
Harvey Canal Lock ............. 
Orleans Levee District .............. 
Left descending, east bank .......... 
Levees ................. ..... 
Floodwalls ......................... 
IHNC lock ....................... 
Right descending, west bank ........ 
Levees ............................ 
Algiers Canal lock ................ 
Lake Borgne Basin Levee District Levees 
Grand Prairie Levee District Levees 
Total Mississippi River ......... 
(16.8) 
15.5 
1.3 
(126.3) 
118.7 
0.8 
6.7 
0.1 
61.7 
37.9 
(34.1) 
34.0 
0.1 
2.1 
(124.9) 
110.8 
11.3 
1.3 
1.5 
11.6 
(20.0) 
19.8 
0.1 
0.1 
(27.2) 
(13.3) 
4.6 
8.6 
0.1 
(13.9) 
13.8 
0.1 
11.6 
37.4 
511.6 
(16.8) 
15.5 
1.3 
(126.3) 
118.7 
0.8 
6.7 
0.1 
61.7 
37.9 
(34.1) 
34.0 
0.1 
2.1 
(124.9) 
110.8 
11.3 
1.3 
1.5 
11.6 
(20.0) 
19.8 
0.1 
0.1 
(27.2) 
(13.3) 
4.6 
8.6 
0.1 
(13.9) 
13.8 
0.1 
11.6 
37.4 
511.6 
(-) 
(9.5) 
9.5 
0.2 
(-) 
(-) 
(-) 
(1.0) 
(1.0) 
1.0
(-) 
0.1 
4.7 
15.5 
(10.7) 
9.4 
1.3 
(94.9) 
87.3 
0.8 
6.7 
0.1 
24.1 
28.7 
(19.7) 
19.7 
0.9 
(91.1) 
77.0 
11.3 
1.3 
1.5 
10.8 
(9.1) 
8.9 
0.1 
0.1 
(21.0) 
(9.0) 
0.6 
8.3 
0.1 
(12.0) 
11.9 
0.1 
11.6 
28.4 
351.0 
(-) 
(5.3) 
5.3 
0.1 
(-) 
(4.7) 
4.7 
(-) 
(-) 
(-) 
(-) 
10.1 
(-) 
(-) 
(-) 
((--)) 
(-) 
- 
(-) 
(-) 
(-) 
(-) 
(-) (15.5) 
- 15.5 
(1.0) (118.7) 
1.0 118.7 
0.1 61.7 
- 37.9 
(-) (34.0) 
- 34.0 
- 2.1 
(-) (110.8) 
- 110.8 
- - 
- 11.6 
(-) (19.9) 
- 19.8 
- 0.1 
(-) (18.4) 
(-) (4.6) 
- 4.6 
(-) (13.8) 
- 13.8 
- 11.6 
- 37.4 
1.1 479.6 
N
O
N 
O
y 
>
c 
0
0
3y
0
0n
r 
O
y
�o 
co3 
(-) 
(-) 
(-) 
(-) 
- 
(-) 
(-) 
(-) 
(-) 
(15.5) 
15.5 
(118.7) 
118.7 
61.7 
37.9 
(34.0) 
34.0 
2.1 
(110.8) 
110.8 
11.6 
(19.9) 
19.8 
0.1 
(18.4) 
(4.6) 
4.6 
(13.8) 
13.8 
11.6 
37.4 
479.6

Other Levees Included in Mainstem 
Atchafalaya Basin 
Atchafalaya River and 
Bayou des Glaises ................ 
East bank Atchafalaya River ..... 
Bayou des Glaises .............. 
West bank Atchafalaya River ..... 
Simmesport Ring ............ 
Melville Ring ................... 
Krotz Springs Ring .............. 
Mansura Hills to Hamburg ....... 
West protection levee, Hamburg to Berwick 
drainage canal via Calumet .. . 
Levees west of Berwick, Berwick drainage 
canal to Charenton drainage canal 
Morganza upper guide levee ........ 
East protection levee, Morganza to Cutoff 
Bayou, including 19.5 miles of 
Morganza lower guide levee ........ 
Total Atchafalaya Basin ...... 
Total--Main Stem Levees ............. 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
Lake Pontchartrain, LA .............. 
Item A levees .................... 
Item B levees .................... 
Item C levees .................... 
Total Tributary Levees in MR&T Project 
GRAND TOTAL ............... 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(148.4) 
52.5 
7.9 
60.1 
1.6 
4.1 
1.7 
20.5 
(128.7) (128.7) 
(56.5) 
(8.9) 
(56.5) 
(8.9) 
(-) (143.9) 
- 52.5 
- 7.9 
- 55.6 
- 1.6 
- 4.1 
- 1.7 
- 20.5 
(3.1) (87.8) 
(-) 
(-) 
(9.6) 
(8.9) 
(-) (-) 
(-) (-) 
(-) 
(-) 
(-) 
(-) 
(-) (148.4) 
- 52.5 
- 7.9 
- 60.1 
- 1.6 
- 4.1 
- 1.7 
- 20.5 
(-) (43.9) 
20.2 
12.0 
11.7 
(-) (127.7) (3.1) (87.5) 
(-) 
(-) 
(56.5) 
(8.9) 
(-) 
(-) 
(-) 
(8.9) 
(106.7) (106.7) (6.1) (67.5) (-) (-) (-) (105.0) (6.1) (65.2) 
449.2 449.2 9.2 317.7 - - - 446.5 9.2 205.5 
960.8 960.8 24.7 668.7 10.1 - 1.1 926.1 9.2 685.1 
(17.4) (17.4) (-) (17.4) (-) (-) (-) (17.4) (-) (17.4) 
5.0 5.0 - 5.0 - - - 5.0 - 5.0 
10.1 10.1 - 10.1 - - - 10.1 - 10.1 
2.3 2.3 - 2.3 - - - 2.3 - 2.3 
17.4 17.4 - 17.4 - - - 17.4 - 17.4 
978.2 978.2 24.7 686.2 10.1 1.1 943.5 
1. Figures indicate landside seepage berms only. 
CI) 
CI) 
CI 
cl 
C. 
C
1 
9.2 702.5

TABLE 42-L PROJECT LEVEES: VICKSBURG DISTRICT 
(FISCAL YEAR 1989) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
Authorized In Total System Com- System plete Place Thru When Built plete When Built Thru 
for This This This Corn- This This Com- This This 
System FY FY FY2 pleted3 FY4 FY pleted FY FY 
MAIN STEM LEVEES 
Mississippi River Levees 
East bank in Mississippi ............. 178.35 178.3 - 109.1 156.9 2.8 114.0 168.4 - 168.4 
Greenville Harbor dikes .............. 7.8 7.8 - 7.8 - - - 
West bank in Arkansas ............... 75.6 75.6 2.5 50.1 54.0 4.5 51.5 75.4 - 75.4 
West bank in Louisiana 
(above Red River) . ................. 198.7 198.7 - 67.1 91.0 - 69.6 197.8 197.8 
Total Mississippi River Levees ...... 460.4 460.4 - 234.1 301.9 7.3 235.1 441.6 441.6 
Other Levees Included in 
Main Stem 
Lower Red River-South Bank 
Red River levees ................. (59.2) (59.2) (.1) (59.2) (-) (-) (-) (59.2) (-) (59.2) 
Hotwells to Moncla, LA, levees ...... 59.2 59.2 .1 59.2 - - - 59.2 - 59.2 
Arkansas River, South bank ....... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 
Total Other Levees Included in 
Main Stem ............... .... 144.6 144.6 - 144.6 24.7 - 24.7 143.3 - 140.3 
Total-Main Stem Levees .......... 605.0 605.0 2.4 378.7 326.6 7.3 259.8 584.9 - 581.9 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
Arkansas River, North bank .......... 61.57 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
Red River Backwater Levees ....... 263.6 160.5 - 141.58 - - - 249.0 - 141.9 
Yazoo River Basin . ................. (721.3) (356.5) (3.1) (157.0) - - - (717.3) (3.1) (323.6) 
Headwater ..................... 624.76 305.6 3.1 156.3 - - - 620.7 3.1 284.6 
Backwater ...................... 96.6 50.9 - 0.7 - - - 96.6 - 39.0 
Total Tributary Levess in MR&T Project ... 1,046.4 573.2 3.1 361.0 8.3 - 8.3 1,013.7 3.1 512.9 
GRAND TOTAL ..................... 1,651.4 1,178.2 3.1 739.7 334.9 7.3 268.1 1,598.6 3.1 1,094.8 
1. This tabulation does not include riverside berms which are 
considered an integral part of the levee section. Riverside berms will be 
constructed along with levee enlargements or seepage berm contracts. 
2. Levee that has adequate freeboard based on the refined 1973 
MR&T project flood flow line for the Mississippi River. Levees with 
more than 2 feet of freeboard are considered adequate. 
3. Subject to change as planning progresses. Does not include 
existing berms which need restudy. 
4. Based on refined 1973 MR&T project flood flow line. 
5. Includes 1.4 miles of concrete floodwall and 0.3 mile of levee on 
Vicksburg city front. 
6. Includes 36.9 miles of local protection works; 61.3 miles along 
Whittington Auxiliary Channel; 210 miles in Upper Yazoo Projects; 156.1 
miles along main stem; and 160.4 miles on tributaries. 
7. Includes 5.3 miles for Gillett new levee. 
8. Reflects results of 1985 flowline reanalysis. 
O
-3 
O
y 
d 
y
Ca 
O
y 
n
CC 
C
Ct 
O
cax 
ca

TABLE 42-M PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1989) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade andSection In In Com- 
In Total System Com- System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Com- This This 
System FY FY FY pleted' FY FY pleted FY FY 
MAIN STEM LEVEES 
Mississippi River 
Mounds, IL ....................... 
Mound City, IL ................... 
Cairo Drainage District ........... 
City of Cairo ..................... 
Little River Drainage District ....... 
Levee District No. 2, 
Scott County, MO .................. 
Levee District No. 3, 
Mississippi County, MO .......... 
St. Johns Levee and 
Drainage District ................ 
St. Francis Levee District of MO ... 
City of Hickman, KY ............. 
Board of Levee Commissioners 
Fulton County, KY ................ 
Reelfoot Levee District of Lake and 
Obion Counties, TN ................ 
Madrid Bend Levee District, 
Lake Co., TN .................... 
Lake County Levee and 
Drainage District .................. 
Dyer Count Levee and 
Drainage District No. 1 ............ 
Tipton-Obion levee extension ........ 
St. Francis Levee District of AR .... 
Helena Improvement District No. 1 
Cotton Belt Levee District No. 1 ... 
Laconia Drainage and Levee District 
Phillips County, AR ............... 
Laconia Levee District No. 1 of 
Desha County, AR ................. 
Laconia Circle Special Drainage 
District of Desha County, AR ...... 
Yazoo-Mississippi Delta Levee 
District ........................ 
3.9 
2.7 
13.82 
6.2 
19.3 
13.8 
3.9 
2.7 
13.8 
6.2 
19.3 
13.8 
26.0 26.0 
59.03 
55.7 
1.4 
16.7 
58.7 
55.7 
1.4 
16.7 
4.5 4.5 
5.2 5.2 
15.9 
21.3 
6.5 
156.7 
5.3 
23.9 
20.5 
18.1 
15.9 
21.3 
156.7 
5.3 
23.9 
20.5 
18.1 
6.6 6.6 
3.9 
2.7 
13.8 
6.2 
19.3 
13.8 
26.0 
58.2 
55.7 
1.4 
0.5 
2.5 
1.6 
4.4 
9.7 
4.2 
12.9 
9.2 
23.0 
0.8 
0.5 
2.5 
2.0 
4.9 
4.9 26.0 
12.0 
16.74 15.1 11.4 
4.54 
5.2 4 
15.9 
21.3 
153.24 
5.3 
23.9 
20.5 
18.14 
0.6 0.3 4.5 
9.1 
1.3 
84.7 
2.4 
18.8 
11.5 
12.6 
5.2 
4.5 15.9 
0.4 
81.8 
2.4 
18.8 
11.5 
9.2 16.5 
6.6 4 
93.6 93.6 - 93.6 87.3 
3.6 
1.1 
8.5 
4.0 
19.3 
13.8 
46.9 
55.1 
0.5 
16.3 
3.6 
1.1 
8.5 
3.5 
19.3 
13.8 
26.0 
46.1 
55.1 
0 
16.3 
4.3 
5.2 Z 
15.9 
21.3 
156.7 
4.2 
23.9 
20.5 
16.5 
21.3 
6.5 
156.7 
4.7 
23.9 
20.5 
87.3 93.6 -93.6

TABLE 42-M 
(Continued) 
PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1989) 
Levees and Floodwalls Berms (Miles)' Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Corn- 
In Total System Com- System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Com- This This 
System FY FY FY pleted' FY FY pleted FY FY 
Mississippi River Levees (continued) 
Madrid Bend L.D., 
Fulton Co., KY .................... 4.8 4.8 0.4 4.84 - - -4.8 0.4 4.8 
Birds Point-New Madrid 
setback levee ...................... 35.3 35.3 - 35.3 23.8 - - 35.3 - 35.3 
Total Mississippi River .......... 636.7 629.9 0.4 625.9 335.2 0.8 254.4 604.5 0.4 595.5 
TOTAL MAIN STEM LEVEES ... 636.7 629.9 0.4 625.9 335.2 0.8 254.4 604.5 0.4 595.5 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
St. Francis River .................. (308.2) (302.9) - (302.9) - - - (301.0) - (133.5) 
East bank ....................... 159.5 156.2 - 156.2 - - - 156.7 6.0 94.7 
West bank ...................... 148.7 146.7 - 146.7 - - - 144.3 - 38.8 
Little River ........ .............. (130.1) (130.1) - (130.1) - - - (128.9) (94.5) 
East bank (left) ................... 40.7 40.7 - 40.7 -40.7 27.0 40.1 
West bank ........................ 35.1 35. 1 35 - - - 35.1 - 23.7 
Elk Chute .......................... 39.9 39.9 - 39.9 - - - 39.7 - 17.3 
West Basin and middle valley ...... 14.4 14.4 - 14.4 - - - 13.4 - 13.4 
Lower White River ................. (95.6) (85.9) - (84.1) - - - (88.0) - (75.0) 
White River backwater levee . . 40.2 40.2 - 40.2 - - - 38.8 - 38.8 
Augusta to Clarendon .............. 49.2 39.5 - 39.5 - - - 49.2 - 36.2 
Clarendon levee .................... 6.2 6.2 - 4.4 - - - 
Memphis Harbor .................... 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 
Total Tributary Levees in 
MR&T Project .................... 544.4 529.4 - 527.6 7.0 - 1.5 528.4 33.0 313.5 
GRAND TOTAL ..................... 1,181.1 1,159.3 0.4 1,153.5 342.2 0.8 255.9 1,132.9 33.4 909.0 
1. Subject to change as planning progresses. 
2. Includes 5.1 miles of Cache River levee. This levee was enlarged to 
1928 grades with Federal funds, but since that time has been classified 
as a secondary levee. 
3. Includes 12.1 miles of Farrenburg levee. This levee was enlarged 
to 1928 grades with Federal funds, but since that time has been classified 
as a secondary levee. 
4. Authority: CEMRC-ED-GS (CELMM-ED-GT 18 FEB 87) 3rd END 
31 May 88.

TABLE 42-N 
RECAPITULATION 
PROJECT LEVEE TABLES 42-K, -L, AND -M 
(FISCAL YEAR 1989) 
Levees and Floodwalls Berms (Miles) Surfaced Roads on Levees 
(Miles) (Miles) 
Built to Approved Total 
Location Total Grade and Section In In Com- 
In Total System Com- System plete 
Authorized Place Thru When Built plete When Built Thru 
for This This This Com- This This Com- This This 
System FY FY FY pleted FY FY pleted FY FY 
MAIN STEM LEVEES 
Mississippi River 
New Orleans District, Table 42-K ... 511.6 511.6 .15.4 351.0 10.1 - 1.1 479.6 - 479.6 
Vicksburg District, Table 42-L ..... 460.4 460.4 - 234.1 301.9 -7.3 235.1 441.6 - 441.6 
Memphis District, Table 42-M ...... 636.7 629.9 0.4 625.9 335.2 0.8 254.4 604.5 0.4 595.5 
Total Mississippi River ........... 1,608.7 1,601.9 15.8 1,211.0 647.2 8.1 490.6 1,525.7 0.4 1,516.7 
Other Levees Included in Main Stem 
Atchafalaya Basin 
Floodway-NOD ................ 449.2 449.2 9.2 317.7 - - - 446.5 9.2 205.5 
Lower Red River- 
South Bank-VXD ............... 59.2 59.2 - 59.2 - - - 59.2 - 59.2 
Arkansas River-South Bank-VXD ... 85.4 85.4 - 85.4 24.7 - 24.7 84.1 - 81.1 
Total Other Levees Included 
in Main Stem . ................. 593.8 593.8 9.2 462.3 24.7 - 24.7 589.8 9.2 345.8 
Total Main Stem Levees ........ 2,202.5 2,195.7 25.0 1,673.3 671.9 8.1 515.3 2,115.5 9.6 1,862.5 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
Lake Pontchartrain, LA,-NOD ........ 17.4 17.4 - 17.4 - - - 17.4 - 17.4 
Yazoo River Basin-VXD ............. 721.3 356.5 3.1 157.0 - - - 717.3 - 320.5 
Arkansas River-North Bank-VXD ..... 61.5 56.2 - 56.2 8.3 - 8.3 47.4 - 47.4 
Red River Backwater-VXD .......... 263.6 160.5 - 147.8 - - - 249.0 - 145.9 
St. Francis River-MD ............... 308.2 302.9 - 302.9 - - - 301.0 6.0 133.5 
Little River-MD ................... 130.1 130.1 - 130.1 - - - 128.9 27.0 94.5 
Lower White River-MD .............. 95.6 85.9 - 84.1 - - - 88.0 - 75.0 
Memphis Harbor-MD ................ 10.5 10.5 - 10.5 7.0 - 1.5 10.5 - 10.5 
Total Tributary Levees in 
MR&T Project .................... 1,608.2 1,120.0 3.1 906.0 15.3 - 9.8 1,559.5 33.0 844.7 
Grand Total in Project ............ 3,810.7 3,315.7 28.1 2,579.3 687.2 8.1 525.1 3,675.0 42.6 2,707.2 
Cl2 
C12 
Mme 
Mai 
0C
0
z

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-0 CHANNEL IMPROVEMENTS: NEW ORLEANS 
(FISCAL YEAR 1989) 
DISTRICT 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Com- This This Percent 
ated pleted FY FY Complete 
(Miles) 
Bayou des Glaise diversion channel ............... 1938 6.0 - 6.0 100 
Bayous Rapides, Boeuf, and Cocodrie .............. 1946 92.6 - 63.4 75 
Charenton drainage and navigation canal ......... 1939 6.3 - 6.3 100 
Wax Lake Outlet ................................. 1938 15.7 - 15.7 100 
Atchafalaya Basin Floodway ..................... 1933 244.2 - 186.4 76 
Morganza Floodway ........................... 1941 3.3 - 3.3 100 
Old River outflow channel ...................... 1956 8.3 - 8.3 100 
Old River inflow channel ....................... 1960 2.3 - 2.3 100 
Old River lock approach channels ................ 1961 2.2 - 2.2 100 
Baton Rouge Harbor (Devils Swamp) ............. 1958 2.5 - 2.5 100 
Teche-Vermillion Water Supply ................... - 6.3 - 6.3 100 
42-52

MISSISSIPPI RIVER COMMISSION 
TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(FISCAL YEAR 1989) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Com- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BIG SUNFLOWER RIVER, ETC., MS 
Big Sunflower River ............................ 1947 199.1 - 199.1 100 
Quiver River ..................................... 1947 69.6 - 69.6 100 
Deer Creek ...................................... 1947 7.0 - 7.0 100 
Steele Bayou ..................................... 1947 54.9 - 54.9 100 
Steele Bayou' .................................... 1965 71.2 5.5 68.5 90 
Main Canal ...................................... 1959 21.1 - 21.1 100 
M ain Canal2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - 22.2 - - - 
Black Bayou ............. ....................... - 36.5 - - - 
Big Sunflower River tributaries .................. 1957 227.2 - 227.2 100 
Quiver River tributaries ......................... 1960 35.4 - 35.4 100 
YAZOO BACKWATER 
Yazoo Backwater ............................... 1960 39.9 - 39.9 100 
YAZOO BASIN HEADWATER, MS 
Upper Yazoo Project ............................ 1976 179.0 2.4 58.1 32 
Coldwater River ................................ 1941 54.6 - 54.6 100 
Arkabutla Canal ............................... 1948 0.4 - 0.4 100 
Tallahatchie Canal .............................. 1940 74.8 - 73.5 85 
Little Tallahatchie River and 
Panola-Quitman Floodway ...................... 1939 48.0 - 48.0 100 
Greenwood protection works ..................... 1971 2.9 - 2.9 100 
Yacona River .................................. 1952 1.8 - 1.8 100 
Bobo Bayou ..................................... 1944 16.1 - 16.1 100 
Cassidy Bayou .................................. 1934 69.0 - 69.0 100 
Cassidy Bayou 3 . . . . . . . . . . . . . . . .. . .. . . . .. . . . - 26.0 - - - 
Bear Creek Diversion ............................ - 4.8 - 
Lake Cormorant ................................. - 20.9 - 
Hurricane Bayou ................................ - 2.5 - 
Opossum Bayou .................................. - 20.8 - 
Abaica Creek ................................ - 7.7 - 
Chicopa Creek ................................... - 7.0 - 
Bear Creek ..................... .... ...... - 23.3 - 
Rocky Bayou ................................... - 7.8 - 
Whiteoak Bayou ................................. - 55.9 - 
Miscellaneous ditches ................. ....... - 12.3 - - - 
Yalobusha River ............ ................ 1939 46.0 - 46.0 100 
Yazoo River .................. ............... 1940 160.2 - 160.2 100 
Whittington Auxiliary Channel ................... 1956 30.8 - 30.8 100 
Tchula Lake ............... ..................... 1964 26.4 - 26.4 100 
David-Burrell Bayou ............................. 1957 40.4 - 40.4 100 
McKinney Bayou ......... ... .................. 1960 3.5 - 3.5 100 
Hillside Floodway ............................... 1964 11.0 - 11.0 100 
Yazoo City protection works ..................... 1953 1.6 - 1.6 100 
Ascalmore-Tippo Bayous ........................ 1975 30.2 - 15.1 50 
Alligator-Catfish Bayou .......................... 1973 8.3 - 8.2 99 
Pelucia Creek .................. . .......... 1975 13.7 - 5.6 40 
BOEUF & TENSAS RIVERS, ETC., 
LA AND AR 
Bayou Lafourche ............................... 1949 45.3 - 45.3 100 
Bayou Lafourche 4 ,7 . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 1972 43.0 - 4.4 10 
Big & Colewa Creeks ........................... 1947 81.4 - 81.4 100 
42-53

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-P CHANNEL IMPROVEMENTS: VICKSBURG DISTRICT 
(Continued) (FISCAL YEAR 1989) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Com- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BOEUF & TENSAS RIVERS, ETC., 
LA AND AR- continued 
Big & Colewa Creeks5' 7 . . . . . . . . . . . . . . . . . . . . . . . . . . 1965 86.8 - 51.5 60 
Tensas River ................................... 1947 96.5 - 96.5 100 
Tensas River ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1968 165.0 - 61.0 37 
Boeuf River, AR and LA ....................... 1953 103.9 - 103.9 100 
Fleschmans Bayou, AR .......................... 1963 6.6 - 6.6 100 
Caney Bayou, AR ............................... 1964 7.4 - 7.4 100 
Canal 18, AR .................................... 1963 10.3 - 10.3 100 
Big Bayou, AR ................................. 1952 33.3 - 33.3 100 
Black Pond Slough, AR ......................... 1962 14.3 - 14.3 100 
Bayou Macon, AR and LA 1959 150.8 - 150.8 100 
Rush Bayou, AR ............. ........ ....... 1964 6.7 - 6.7 100 
Canal 19, AR .................................... 1957 50.2 - 50.2 100 
Canal 43, AR .................................. 1956 34.5 - 34.5 100 
Canal 81, AR ................................... 1957 32.7 - 32.7 100 
Mill Bayou-Bayou Vidal-Bayou Vidal Cutoff ...... - 17.1 - - 
Kirsch Lake Canal ............................... - 9.3 - - 
Canal 19 Extension .............................. 1964 9.4 - 9.4 100 
Lake Chicot Pumping Plant ..................... - 2.5 - 2.5 100 
Mill Bayou .................................... 1955 4.8 - 4.8 100 
RED RIVER BACKWATER, LA 
Tensas-Cocodrie Pumping Plant .................. 1976 6.9 - 6.9 100 
Six Mile Bayou, LA ............................. - 1.5 - 1.5 100 
GRAND PRAIRIE, AR .......................... - 338.1 - - 
BAYOU METO, AR ............................ - 164.9 - - 
1. Includes further work on 54.9 miles and adds 16.3 6. Includes further work on 96.5 miles and adds 68.5 
miles of channel to the project. 
2. Includes further work on 21.1 miles and adds 1.1 
miles of channel to the project. 
3. Includes further work on 26.0 miles. 
4. Includes further work on 38.6 miles and adds 4.4 
miles of channel to the project. 
5. Includes further work on 75.3 miles and adds 11.5 
miles of channel to the project. 
additional miles of channel to the project. 
7. Further work on these items has been deferred 
due to local oppositions and withdrawal of sponsorship 
by the levee district. 
42-54

MISSISSIPPI RIVER COMMISSION 
TABLE 42-Q CHANNEL IMPROVEMENTS: MEMPHIS DISTRICT 
(FISCAL YEAR 1989) 
In Total 
System Complete 
Year When Built Thru 
Location Initi- Corn- This This Percent 
ated pleted FY FY Complete 
(Miles) 
BIRDS POINT-NEW MADRID 
FLOODWAY 
Birds Point-New Madrid Intercepting Ditch 
Enlargement, Samos and Vicinity, MO .......... 1952 9.6 9.5 100 
ST. FRANCIS BASIN 
Little River Drainage, MO. ....................... 1963 298.9 22.6 278.9 93 
St. Francis River, MO and AR ................... 1953 638.5 23.2 441.0 69 
West Memphis Drainage, AR ..................... 1951 19.8 - 19.8 100 
Big Slough and Mayo Ditch, AR ................. 1960 28.0 - 28.0 100 
Tyronza River, AR .............................. 1939 12.7 - 12.7 100 
L'Anguille River, AR ............................. (1) 95.0 - - - 
LOWER WHITE RIVER 
BASIN, AR 
Cache River Basin, AR .......................... 1972 231.5 - 7.2 3 
Big Creek and tributaries, AR .................... (1) 103.8 - - - 
WEST KENTUCKY TRIBUTARIES 
Obion Creek, KY ................................. (1) 41.7 
WEST TENNESSEE TRIBUTARIES 
MS River, Western TN tributaries 
(Backwater Areas) (1946 Act) ................... 1952 34.3 - 34.3 100 
Obion River Diversion Channel, 
TN (1946 Act) ................................. (1) 9.3 
Reelfoot Lake-Lake No. 9, KY 
and TN ........................................ 1974 15.8 - 3.0 19 
Running Reelfoot Bayou, TN ...................... 1955 19.7 - 19.7 100 
MS River Below Cape Girardeau; West 
TN tributaries. (1948 Act) ...................... 1961 225.0 - 89.8 41 
Wolf River and tributaries, TN ................... 1960 25.5 - 25.5 100 
1. Not started. 
42-55

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-R COSTS DURING FISCAL YEAR 1989 
Item Construction Maintenance Other 
FEDERAL FUNDS 
Flood control, Mississippi River and tributaries: 
St. Louis District: 
General investigations $ -- $ -- $ -- 
Advance engineering and design -- -- 
St. Francis Basin-Wappapello Lake -- 4,024,070 -- 
Subtotal 4,024,070 
Memphis District: 
General investigations -- -- 3,272,244 
Mississippi River levees 1,800,544 2,536,493 -- 
St. Francis Basin 11,260,082 7,914,325 -- 
Lower White River, Augusta to Clarendon 7,135 785,584 -- 
Clarendon Levee, Lower White, AR 8,759 -- -- 
White River Backwater -- 2,115,019 -- 
Cache Basin, Ark. 505,502 -- -- 
Channel improvement 20,223,122 22,146,133 -- 
West Tennessee tributaries 434,535 -- -- 
West Kentucky tributaries 6,885 -- -- 
Inspection of completed works -- 640,193 -- 
Mapping -- 251,118 -- 
Reelfoot Lake No. 9, TN-KY 2,939 -- -- 
Mud Lake, TN 37 -- -- 
Eight Mile Creek 229,396 -- -- 
Helena Harbor 832,121 --- 
L'Anguille River 46,203 -- -- 
Devalls Creek Pumping Station -- 2,951 -- 
Subtotal 35,357,258 35,606,232 3,272,244 
Vicksburg District: 
General investigations -- -- 1,205,936 
Advance engineering and design -- -- 
Mississippi River levees 2,845,769 956,554 -- 
Lower Arkansas River - 935,349 -- 
Tensas Basin 3,779,239 4,152,120 -- 
Yazoo Basin 21,237,930 21,955,964 - 
Channel improvement 28,462,509 12,122,331 -- 
Mapping -- 444,013 -- 
Inspection of completed works -- 165,600 -- 
Lower Red River--South Bank Red River Levee 496,303 36,496 -- 
Dam Safety Assurances 764,128 -- -- 
Subtotal 57,585,878 40,768,426 1,205,936 
New Orleans District: 
General investigations -- -- 807,868 
Advance engineering and design -- 
Mississippi River levees 10,606,523 5,159,462 - 
Mississippi Delta Region 5,584,995 -- -- 
Old River 1,872,804 5,054,804 - 
Bayou Cocodrie and tributaries -- 153,453 - 
Atchafalaya Basin 20,418,451 7,321,481 - 
Atchafalaya Basin Floodway System 6,675,942 -- -- 
Channel improvement 59,269,116 21,065,674 -- 
Inspection of completed works - 239,398 -- 
Mapping -- 193,855 -- 
Subtotal 
Total Federal Funds 
104,427,831 39,188,127 807,868 
197,370,967 119,586,856 5,286,048 
42-56

TABLE 42-R 
(Continued) 
MISSISSIPPI RIVER COMMISSION 
COSTS DURING FISCAL YEAR 1989 
Item Construction Maintenance Other 
CONTRIBUTED FUNDS 
Memphis District: 
Lauderdale County Boat Ramp 177,757 -- -- 
New Orleans District: 
Old River -- 64,994 -- 
Atchafalaya Basin -- -- 
Mississippi Delta Region 1,119,146 -- - 
Total Contributed Funds 1,296,903 64,994 -- 
Grand Total, Federal 
and Contributed Funds 198,667,870 119,651,849 5,286,048 
42-57

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-S STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1989 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1989 
ALLOTMENTS AND ACCRUED EXPENDITURES 
CHARGEABLE AGAINST FLOOD CONTROL 
ACT LIMITATIONS: 
COMPLETED WORKS: 
Waterways Experiment Station 
Office, Chief of Engineers 
Rock Island District: 
S. G. & O. prior to Aug. 18, 1941 
St. Louis District: 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Memphis District: 
Des Arc, Ark. 
Contraction works 
DeValls Bluff, Ark. 
Mapping 
Memphis Harbor 
New Madrid Floodway 
Wolf River and tributaries 
Roads on levees (Mississippi River levees) 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Vicksburg District: 
Boeuf Basin levees 
Channel realignment, Arkansas River 
Contraction works 
Eudora Floodway 
Vicksburg Harbor 
Greenville Harbor 
Grants Canal (Mississippi River levees) 
Mapping 
Jonesville, LA 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
New Orleans District: 
Baton Rouge Harbor, LA 
Atchafalaya River and Basin, LA 
Bonnet Carre' Spillway, LA 
Contraction works 
Mapping 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Wax Lake Outlet and Charenton Canal 
Morganza Floodway and structure 
Lake Pontchartrain 
Atchafalaya Basin, rights-of-way and flowage, 
Bayou des Glaises setback 
Subtotal 
All other completed items: 
Surveys under Sec. 10, Flood Control Act of 1928 
Impounded savings 
Plant transferred to revolving fund 
OCE (portion of allotment transferred to 
revolving fund, Washington Dist.) 
Subtotal 
TOTAL COMPLETED WORKS 
$ 874,000 
19,158 
14,010 
$ 874,000 
19,158 
14,010 
169,352 169,352 -- 
1,076,520 1,076,520 -- 
178,925 178,925 -- 
8,692,791 8,692,791 -- 
231,215 231,215 -- 
1,450,337 1,450,337 -- 
18,736,432 18,736,432 -- 
6,521,543 6,521,543 -- 
1,723,620 1,723,620 -- 
12,426 12,426 -- 
1,998,766 1,998,766 -- 
39,546,055 39,546,055 -- 
2,764,605 2,764,605 -- 
125,074 125,074 -- 
1,972,183 1,972,183 -- 
826,235 826,235 -- 
4,664,515 4,664,515 -- 
2,864,516 2,864,516 -- 
7,070 7,070 -- 
1,531,021 1,531,021 -- 
172,950 172,950 -- 
105,660 105,660 -- 
2,350,201 2,350,201 -- 
17,384,031 17,384,031 -- 
699,185 699,185 -- 
3,375,492 3,375,492 -- 
14,212,198 14,212,198 -- 
1,258,916 1,258,916 -- 
1,112,967 1,112,967 -- 
540,838 540,838 -- 
2,701,566 2,701,566 -- 
10,098,817 10,098,817 -- 
35,992,117 35,992,117 -- 
5,513,110 5,513,110 -- 
387,917 387,917 -- 
75,893,123 75,893,123 -- 
4,995,215 4,995,215 -- 
1,593,097 1,593,097 -- 
24,924,578 24,924,578 -- 
19,882 19,882 -- 
31,532,772 31,532,772 -- 
165,432,500 165,432,500 -- 
42-58

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1989 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1989 
UNCOMPLETED WORKS: 
Rock Island District: 
Levees under Sec. 6, Flood Control Act of 1928 
St. Louis District: 
Levees under Sec. 6, Flood Control Act of 1928 
Subtotal 
Memphis District: 
Mississippi River levees 
Mississippi River levees 
New Madrid 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Reelfoot Lake 
Reelfoot Lake, Lake No. 9, TN-KY 
St. Francis Basin: 
Wappapello Lake 
St. Francis River and tributaries 
Big Slough and Mayo ditch 
Little River drainage 
Lower White River: 
Clarendon Levee 
Augusta to Clarendon, AR 
White River backwater levee, AR 
Levees under Sec. 6, Flood Control Act of 1928 
West Tennessee tributaries 
Helena Harbor 
Cache Basin, AR 
West Kentucky tributaries 
Mud Lake Pumping Station, TN 
L'Anguille River 
Eight Mile Creek 
Subtotal 
Vicksburg District: 
Mississippi River levees (excludes Grants Canal, 
$7,070, shown under completed works) 
Section 6 Levees 
Lower Arkansas River: 
North Bank 
South Bank 
Tensas Basin: 
Lake Chicot pumping plant 
Tensas River 
Red River Backwater: 
Below Red River 
Red River backwater levee, LA 
Tensas, Cocodrie pumping plant 
Lower Red River South Bank Red River Levees 
Tensas National Wildlife Refuge, LA 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Levees under Sec. 6, Flood Control Act of 1928 
Yazoo Basin: 
Sardis Lake 
579,462 
1,897,980 
2,477,442 
173,989,354 
98,000 
347,865,307 
57,499,400 
135,666,000 
439,434 
7,895,000 
9,019,908 
215,975,682 
965,429 
50,977,592 
505,715 
1,788,846 
10,624,501 
108,651 
39,333,900 
4,562,000 
9,823,000 
1,440,000 
107,000 
196,000 
1,593,000 
1,070,473,720 
204,398,990 
9,000 
7,049,414 
15,676,286 
93,963,400 
41,507,200 
629,800 
60,960,646 
54,460,900 
785,400 
39,800,000 
403,602,065 
23,549,260 
99,932,040 
958,175 
26,502,400 
579,462 
1,897,980 
2,477,442 
173,766,072 
98,000 
347,812,324 
57,499,399 
133,865,904 
439,434 
7,881,074 
9,019,908 
214,393,994 
965,429 
50,955,445 
505,474 
1,786,981 
10,624,501 
108,651 
38,683,029 
1,418,769 
9,299,799 
1,424,635 
91,352 
118,162 
1,489,425 
1,062,247,764 
203,560,491 
9,000 
7,049,414 
15,676,286 
92,585,336 
41,480,091 
602,537 
57,028,319 
53,536,553 
756,281 
39,800,000 
402,473,991 
23,549,260 
99,264,287 
958,175 
26,502,400 
42-59 
223,282 
-- 
52,983
1 
1,042,810 
13,926 
-- 
1,581,687 
-- 
22,147 
241 
1,865 
650,871 
3,143,231 
523,201 
15,365 
15,648 
77,838 
103,575 
8,225,956 
835,499 
-- 
1,378,064 
27,110 
27,263 
3,932,326 
924,347 
29,119 
1,128,074 
667,753

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1989 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1989 
Yazoo Basin: (Continued) 
Enid Lake 
Arkabutla Lake 
Grenada Lake 
Greenwood 
Belzoni 
Yazoo City 
Will M. Whittington auxiliary channel 
Big Sunflower, etc. 
Main Stem 
Upper Yazoo Projects 
Yazoo Basin-Tributaries 
Tributaries (Except Ascal-Tippo-Opossum Bayous) 
Tributaries-Bank Stabilization 
Ascalmore-Tippo-Opossum Bayous 
Yazoo Basin Backwater 
Yazoo Backwater 
Rocky Bayou 
Yazoo Backwater Pumping Plant 
Muddy Bayou 
Steambank Erosion Control, Eval. and Demo. 
Demonstration Erosion Control 
Dam Safety Assurances-Sardis Dam 
Subtotal 
New Orleans District: 
Teche-Vermilion Basin Water Supply 
Bayou Cocodrie and Tributaries 
Channel improvement: 
Dredging 
Revetments 
Lower Red River (South Bank Levees) 
Levees Under Sec. 6, Flood Control Act of 1928 
Mississippi River Levees 
Mississippi Delta Region 
Atachafalaya Basin Floodway: 
Atachafalaya Basin 
Atachafalaya River Navigation 
Atachafalaya Basin Floodway System 
Old River 
Subtotal 
TOTAL UNCOMPLETED WORKS 
ADVANCE ENGINEERING AND DESIGN 
(CONSTRUCTION) 
Memphis District: 
L'Anguille River Basin, AR 
Reelfoot Lake, Lake No. 9 
Cache River 
Big Creek and Tributaries, Lower White River 
Clarendon Levee, Lower White River 
West Kentucky Tributaries 
Mud Lake Pumping Station, TN 
Harris Fork Creek, KY & TN 
Subtotal 
Vicksburg District: 
Yazoo Basin, Big Sunflower River, Steele Bayou 
Tensas - National Wildlife Refuge, LA 
Subtotal 
21,292,400 
16,000,700 
45,356,100 
11,543,000 
316,656 
2,205,611 
10,950,966 
42,451,000 
34,793,400 
75,949,806 
73,776,610 
612,484 
23,978,700 
56,444,200 
3,394,200 
11,302,200 
5,145,200 
14,767,000 
49,999,900 
6,181,000 
1,575,246,110 
33,806,000 
5,008,008 
35,945,266 
673,045,117 
18,056,600 
200,680 
244,615,000 
8,900,000 
611,829,537 
303,463 
8,656,000 
291,032,000 
1,931,397,671 
21,292,400 
16,000,700 
45,355,909 
11,543,000 
316,656 
2,205,611 
10,950,966 
39,942,894 
34,324,135 
72,100,638 
69,591,858 
612,484 
23,978,676 
56,158,992 
3,242,213 
9,027,925 
5,145,200 
14,767,000 
33,131,882 
5,449,359 
1,539,970,920 
33,806,000 
5,008,008 
35,945,266 
672,439,251 
18,056,600 
200,680 
243,066,742 
7,836,513 
608,467,437 
303,463 
7,627,146 
290,975,213 
1,923,732,318 
191 
2,508,106 
469,265 
3,849,168 
4,184,753 
24 
285,208 
151,987 
2,274,275 
11,868,018 
731,641 
35,275,190 
605,866 
1,548,258 
1,063,487 
3,362,100 
-- 
1,028,854 
56,787 
7,665,353 
4,579,594,942 4,528,428,443 51,166,499 
150,000 150,000 -- 
30,000 30,000 -- 
420,000 420,000 -- 
365,000 364,339 -- 
65,000 65,000 -- 
175,000 175,000 -- 
350,000 350,000 -- 
540,000 540,000 -- 
2,095,000 2,095,000 -- 
29,700 29,700 -- 
200,000 200,000 -- 
229,700 229,700 -- 
4:2-60

MISSISSIPPI RIVER COMMISSION 
TABLE 42-S 
(Continued) 
STATEMENTS OF ALLOTMENTS AND ACCRUED 
EXPENDITURES FOR FLOOD CONTROL, 
MISSISSIPPI RIVER AND TRIBUTARIES, 
FROM MAY 15, 1928, THROUGH SEP. 30, 1989 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30,1989 
New Orleans District: 
Mississippi Delta Region 69,753 69,753 -- 
Teche Vermilion Basin-Water Supply 1,109,000 1,109,000 -- 
East Rapides & S. Central Avoyelles Parishes 965,247 965,247 -- 
Subtotal 2,144,000 2,144,000 -- 
TOTAL ADVANCE ENGINEERING 
AND DESIGN 4,468,700 4,468,700 -- 
TOTAL COMPLETED WORKS, UNCOMPLETED 
WORKS AND ADVANCE ENGINEERING 
AND DESIGN 4,749,496,142 4,698,329,643 51,166,499 
RECREATION FACILITIES-COMPLETED 
PROJECTS 
Eight-Year Program Funds 
St. Louis District: 
Wappapello Lake, MO 2,405,300 2,404,890 410 
Wappapello Lake, MO, Rockwood Landing 203,286 203,286 -- 
Subtotal 2,608,586 2,608,176 410 
Vicksburg District: 
Sardis Lake 1,584,339 1,584,339 -- 
Enid Lake 2,268,209 2,268,209 -- 
Arkabutla Lake 2,189,280 2,189,280 -- 
Grenada Lake 1,631,281 1,631,281 -- 
Subtotal 7,673,109 7,673,109 -- 
Total Eight-Year Program Funds 10,281,695 10,281,285 410 
Total chargeable against Flood Control 
Act Limitations excluding flood 
control emergencies 4,759,777,837 4,708,611,338 51,166,499 
Total maintenance since Aug. 18, 1941 1,942,582,855 1,935,834,122 6,748,734 
Total rehabilitation 31,113,000 31,113,000 -- 
Total flood control emergencies 14,900,300 14,900,300 -- 
Total general investigations 76,120,881 74,773,617 1,347,264 
Total flood control, MR&T appropriations 6,824,494,873 6,765,232,377 59,262,497 
Appropriations in addition to flood control, MR&T 
Other appropriations itemized in footnote (1), 
pp. 2068-69, Annual Report for 1953 32,068,909 32,068,909 -- 
Grand total appropriated to Sep. 30, 1988 6,856,563,782 6,797,301,285 59,262,497 
Note: Preauthorization study costs chargeable to the MR&T authorization have been transferred to completed work. Costs not 
chargeable have been exluded from this report. 
42-61

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS' ACTIVITIES FOR FY 1989 
TABLE 42-T STATEMENTS OF EXPENDITURES FOR LEVEES 
BY STATE AND LOCAL ORGANIZATIONS 
THROUGH DEC. 31, 1988 
Engineer 
District 
St. Louis 
Memphis 
Vicksburg 
New Orleans 
Total 
Expenditures 
$ 79,366,859 
280,907,702 
136,549,432 
662,240,481 
$1,159,064,474 
42-62

MISSISSIPPI RIVER COMMISSION 
TABLE 42-U COST AND FINANCIAL STATEMENTi 
Total 
Project Funding FY 86 FY 87 FY 88 FY 89 Sep. 30, 1989 
Mississippi River General investigations: 
and tributaries Allotted 6,809,000 5,890,000 4,860,000 5,029,000 76,120,881 
(Regular Funds)1 Cost 5,955,532 6,296,443 4,961,997 5,286,048 74,773,617 
Construction (includes 
advance engineering 
and design): 
Allotted 194,438,000 192,260,000 191,020,000 210,139,000 4,579,594,942 
Cost 196,535,725 168,890,918 198,487,453 197,370,967 4,528,428,443 
Maintenance 
Allotted 100,480,000 112,403,000 120,874,000 121,878,000 1,942,582,855 
Cost 102,958,345 110,409,871 121,485,216 119,586,856 1,935,834,121 
Rehabilitations 
Allotted -- -- -- -- 31,113,000 
Cost -- -- -- -- 31,113,000 
Flood control 
emergencies 
(Maintenance): 
Allotted -- -- -- -- 14,885,992 
Cost -- -- -- -- 14,885,992 
(Contributed Funds) New Work: 
Contributed 20,000 124,692 1,590,000 2,028,507 13,323,970 
Cost 352,749 121,303 1,387,953 1,296,903 12,383,627 
Maintenance 
Contributed 169,279 101,108 79,126 83,164 2,598,412 
Cost 139,621 69,827 63,060 64,994 2,378,955 
1. Appropriations were as follows: 
Appropriations chargeable against Flood Control Act authorizations: 
Flood Control, MR&T except for emergencies (excludes Maintenance 
allotments Aug. 18, 1941, through Sep. 30, 1989): 
Net total allotted for works under Mississippi River Commission: $4,749,076,370 
Eight-Year Program Funds, Construction General: 10,281,695 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 4,995,215 
Transferred to revolving fund: 24,944,460 
Impounded savings: 1,593,097 $4,790,890,837 
Flood control emergencies: 
Net total allotted: 14,885,922 
Impounded savings: 14,378 14,900,300 
Additional funds not chargeable against Flood Control Act authorizations: 
Appropriations for Flood Control, MR&T, except for flood control emergencies: 
General investigations: 76,120,881 
Maintenance allotments Aug. 18, 1941, through Sep. 30, 1989 1,942,582,855 2,018,703,736 
Appropriations in addition to appropriations for Flood Control, MR&T 
(itemized in footnote (1), pp. 2068-69, Annual Report for 1953): 32,068,909 
Budgetary and OCE Reserves: 
Grand total: 6,856,563,782 
Reconciliation of appropriations and allotments: 
Total allotted to Sep. 30, 1989 6,825,016,632 
Transferred to revolving fund: 24,944,460 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 4,995,215 
Impounded savings withdrawn by Chief of Engineers: 1,607,475 
Total Appropriations to Sep. 30, 1989: 6,856,563,782 
Appropriations for past four reporting periods were as follows: 
FY 86: $301,727,000; FY 87: $310,553,000 
FY 88: $316,754,000; FY 89: $337,046,000. 
2. Totals for General Investigations include four projects transferred from Construction totals per DAEN-CWB-W, 
Aug. 4, 78, teletype. 
42-63

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
MISSISSIPPI RIVER AND TRIBUTARIES 
TABLE 42-V ACTIVE GENERAL INVESTIGATIONS 
(96x3112) 
Federal Cost Totals by 
Item and CWIS Number FY 89 Categories 
($) ($) 
SURVEYS (Category 100) 
Flood Damage Prevention (112) 
New Orleans District 
Atchafalaya Basin Water & Land Res - 12026 64,865 
Subtotal 64,865 
Vicksburg District 
Boeuf-Tensas Basin, AR & LA - 81273 530,725 
Natchez, MS- 12675 104,260 
Yazoo River Basin, MS - 12074 374,642 
Subtotal 1,009,627 
Memphis District 
Birds Point-New Madrid Alt Study - 12642 493,672 
Eastern AR Reg-Comprehensive Study - 81266 416,508 
Mayfield Creek -10850 21,058 
Reelfoot Lake, TN - 00086 7,487 
St. Francis River Below Wappapello (Whiteman's Creek) - 22000 124,330 
St. Francis River F&WL, AR&MO - 79690 7,895 
Tuscumbia River Study - 12408 1,441 
Subtotal 1,072,391 
TOTAL (Category 110) 2,146,883 
COLLECTION AND STUDY OF BASIC DATA (Category 120) 
Vicksburg District 138,164 
Memphis District 78,400 
TOTAL (Category 120) 216,564 
SUPPLEMENTAL PRE-AUTH STUDIES (Category 130) 
Flood Damage Prevention (132) 
Vicksburg District 
MS River East Bank Natchez - 76022 58,145 
TOTAL (Category 130) 58,145 
PRE-CONSTRUCTION ENGINEERING & DESIGN (Category 160) 
Flood Control Projects (162) 
New Orleans District 
MS-LA Estuarine Area ADVCPE - 12193 743,003 
Memphis District 
St. Johns Bayou & New Madrid Fdwy - 77005 439,087 
Nonconnah Creek, TN & MS - 12417 310,374 
Horn Lake Creek & Tribs/Cowpen Creek - 81282 151,286 
Helena AR & Vicinity - 81280 289,637 
L'Anguille River Basin - 00082 7,019 
Lower White River Big Creek & Trib - 12472 352,209 
West Memphis & Vicinity - 81281 571,852 
TOTAL (Category 160) 2,864,467 
GRAND TOTAL MR&T GENERAL INVESTIGATIONS 5,286,059 
42-64

U.S. ARMY CONSTRUCTION ENGINEERING RESEARCH LABORATORY 
The U.S. Army Construction Engineering 
Research Laboratory (USACERL) at Champaign, 
Illinois conducts research in the planning, 
design, construction, operation and 
maintenance and environmental quality of 
facilities and installations. 
During FY89, USACERL had four major 
research accomplishments related to the Civil 
Works program. 
(1) For the expert system for corrosion 
resident materials, a database of stainless steel 
properties was prepared, materials in water 
resource projects were identified and a selection 
guide was prepared. This selection guide can 
be used with a computerized knowledge-based 
shell to assist the design engineer in the 
selection of components. The advisor shell was 
used to produce an expert system for material 
selection and field comments were obtained on 
performance of the system. 
(2) A new repair compound was 
developed to rehabilitate corrosion damaged 
areas in steel structures such as gates, floating 
mooring stations and ramps. Currently used 
rehabilitation compounds are epoxy based and 
cracked within a year. Fiber-reinforced glass 
compounds (CERHAB) consists of calcium 
silicate fiber in a glassy matrix. CERHAB 
develops chemical bonds with a corroded 
substrate and the rust on the steel surface is 
dissolved by the glassy matrix. 
(3) The magnitude of microbiological 
corrosion at Truman Dam and Lock 53 on the 
Ohio River was evaluated. Tests on bacterial 
corrosion are continuing. The rate of corrosion 
at these sites has been reported to be 
accelerated because of bacterial action. The 
sulfate reducing bacteria produces acidic byproducts 
which are surrounded by gels and are 
not washed away. 
(4) The Civil Works guide specification 
draft addressing the use of metalized coatings 
on hydraulic structures was completed in FY89. 
The draft contains guidance on safety, surface 
preparation, materials application, inspection 
and quality control. In addition, thermal spray 
metalic coatings were evaluated for corrosion 
protection of dam gates and severely abrasive 
water. It is estimated that zinc or zinc 
aluminum alloy coatings will provide greatly 
lenghtened periods of corrosion protection. 
Approximately 500,000 square feet of steel on 
Ohio River hydraulic structures will benefit 
from the adoption of the technology. 
43-1

U.S. ARMY COLD REGIONS RESEARCH AND 
ENGINEERING LABORATORY 
BACKGROUND 
The U.S. Army Cold Regions Research and Engineering 
Laboratory (CRREL), located in Hanover, 
New Hampshire, was created in January 1961. 
It merged the Snow, Ice and Permafrost Research 
Establishment (created in 1949) and the Arctic 
Construction and Frost Effects Laboratory (created 
in 1953), both of which were outgrowths of the 
Army's World War II experience in Alaska, Iceland 
and Greenland. 
As the Army's center of expertise, CRREL conducts 
cold regions scientific and engineering research 
that addresses problems encountered by 
the Army and other DOD agencies wherever accomplishment 
of their mission is impacted by 
winter/cold regions effects. The major problem areas 
are: 
Ice-jam Floods 
Winter Navigation 
Remote Sensing for Civil Works 
Base Support 
Combat Operations 
Materiel Performance 
The total authorized strength of CRREL is 288 
(277 civilian and 11 military), and its budget for 
FY89 was $27.1 million. CRREL has six main 
buildings in Hanover (a total of 285,322 square feet 
on 31 acres of land), including the main laboratory, 
the Ice Engineering Facility, the logistics and supply 
building, the plant and equipment building, the 
equipment storage building and the Frost Effects 
Research Facility. 
The main laboratory contains 24 coldrooms that 
can be operated at temperatures as low as -50�F, a 
computer center, chemistry laboratories, a cleanroom 
complex, a soils laboratory, and a remote 
sensing analysis center. Specialized equipment includes 
low temperature materials testingmachines, 
mass spectrometers, a low-temperature electron 
microscope, a dual-gamma NDT device, a Hopkinson-
pressure-bar impact test device, and nuclear 
magnetic resonance equipment. 
The Ice Engineering Facility is one of the largest 
refrigerated hydraulics laboratories in the world. 
Within the IEF are a research area for large-scale 
refrigerated hydraulic models, arefrigeratedflume, 
a low temperature towing tank and a wind tunnel 
for simulating drifting snow. 
The Frost Effects Research Facility is a 29,000- 
square-foot refrigerated soils laboratory consisting 
of 12 test cells. Pavements, base and subbase 
courses, and buried utilities can be tested at full 
scale in the FERF. Six to eight natural freeze-thaw 
cycles can be simulated in a single year using 
refrigeration panels. 
The CRREL technical library is recognized as 
having the world's foremost collection of cold regions 
scientific and technical literature. More than 
2000 requests for information are filled each year. 
Additionally, the Bibliography on Cold Regions 
Science and Technology is prepared at the Library 
of Congress under the sponsorship of CRREL. It 
contains over 140,000 citations of world cold regions 
literature, including approximately 50,000 
Russian items. 
CRREL's basic and applied research covers a 
broad spectrum of cold regions studies. Basic research 
includes work in the physical, mechanical 
and chemical properties of snow and other forms of 
frozen precipitation, freshwater ice, sea ice and frozen 
ground. Basic research supports applied research 
in the major cold regions mission areas of 
Ice-jam Floods, Winter Navigation, Remote Sensing 
for Civil Works, Base Support, Combat Operations 
and Materiel Performance. Major Civil Works 
cold regions research topics include Ice Engineering, 
River Ice Management, Water Resources in 
Cold Regions, Remote Sensing, and Environmental 
Impact. 
CRREL has an international reputation and 
maintains close ties with the international research 
community and with Federal and State 
agencies, where it provides consulting services on 
a reimbursable basis. As the cold regions scientific 
and engineering expert for the Corps of Engineers, 
CRREL supports Corps districts and divisions by 
publishing field engineering reports, conducting 
demonstrations, sponsoring technical seminars for 
field engineers, making field visits to consult on 
engineering problems. 
OPERATIONS AND RESULTS 
DURING FY89 
In FY89 CRREL published and distributed 242 
scientific and engineering reports (CRREL Reports; 
Engineer Technical Letters; Special Reports; 
Technical Notes; Fact Sheets; videotapes; Informa- 
44-1

Report of the Secretary of the Army on Civil Works Activities for FY 1989 
tion Exchange Bulletins; journal articles; conference 
papers and abstracts; other Corps, DA and 
government publications; and books and nongovernment 
publications). 
This past year, CRREL has responded to 1082 
Installation Support requests (One-Stops). These 
requests span subjects from environmental quality 
for the Baltimore District to flood control and navigation 
at the Walla Walla District. 
In severe winters, ice jams are responsible for 
over $100 M in damages due to ice-induced flooding. 
Snowmelt runoff is necessary for river and 
ground water recharge but is also a source of spring 
flooding. Remote sensing technology is growing 
rapidly and provides the type ofinformation needed 
for many of the Corps engineering and operations 
missions. These are the major thrusts ofthe CRREL 
Civil Works R&D program. The Ice Engineering 
Program has developed the nation's principal guidance 
on winter navigation, river ice management 
and ice jam flood fighting. In the Water Resources 
in Cold Regions Program, distributed snowmelt 
routines are being developed along with in-situ 
sensors to monitor snowpack conditions. The Remote 
Sensing Program emphasizes the exploitation 
of real-time in-situ sensors, commercially available 
satellite imagery, and raster/vector data management 
capabilities. The program puts image-derived 
data to work driving models and assisting the 
Corps field offices in their day-to-day decisionmaking 
on water control operations and, when necessary, 
emergency operations. The CRREL code 
PRISM provides a small computer-based, advanced 
data management capability. It allows mixing of 
all types of data, raster- and vector-formatted information, 
and tailoring of mixed data sets to drive 
models or decision-making routines. The PRISM 
code uses parallel distributed processing (PDP) 
and neural networking to allow almost complete 
data flexibility, significant data compression and 
exceptional capabilities for desktop computers. 
During FY89 CRREL began a major technology 
transfer effort sponsored by HQ USACE and the 
Corps' Huntsville Division. This work is focused on 
revision of civil engineering and geotechnical criteria 
for design, construction and maintenance of 
roadways and airfields. This coordinated program 
involves CRREL, WES, and several Corps divisions. 
Principal topical areas for CRREL include 
pavement design and evaluation for seasonally frozen 
ground, structural design, and a reference 
handbook for pavements, foundations and drainage 
systems. 
ACCOMPLISHMENTS 
Ice Engineering 
Research has provided the design criteria for 
simple structures which prevent ice jam flooding. 
The newly constructed ice control structure on Oil 
Creek in Oil City, Pennsylvania, was one result of 
this work and received its best test this winter. The 
cold spell in December created a severe ice jam 
threat to the city. However, the new structure in 
conjunction with the ice boom on the Allegheny 
River controlled the ice and prevented the costly ice 
jam-related flooding. 
At Salmon, Idaho, a temporary ice boom was installed 
to confirm site selection. It appears one anchor 
may need to be moved to create an optimum 
ice retaining structure at that site. 
Construction of the castellated weir, laboratory 
tested and designed for Cazenovia Creek near Buffalo, 
New York, has been delayed due to cost sharing 
problems. This action emphasizes the need for 
additional research towards simpler, more cost efficient 
ice control structures. 
Consultation on ice problems is an ongoing effort 
primarily because there is little experience or 
expertise in Ice Engineering outside of CRREL. 
PC-based Data Retrieval Systems 
A PC-based automated system has been developed 
and implemented that provides critical data 
directly to the lock master for forecasting ice conditions. 
This will significantly reduce the time required 
to obtain the information needed to minimize 
the interruption of lock operations by adverse 
ice conditions. 
Inland Waterways Remote Sensing 
Demonstration Program 
The Rock Island District, in conjunction with 
CRREL, is conducting a demonstration of remote 
sensing technologies applicable to Corps water resources 
operations. The major objectives of this 
program are 1) to demonstrate the use of satellite 
and aerial images in water resources activities, including 
the comparison of information content, reliability, 
and cost of acquiring and analyzing such 
data; and 2) to demonstrate the operational use of 
state-of-the-art hydrometeorological and environmental 
sensors for the Geostationary Operational 
Environmental Satellite (GOES) and other data 
relay systems. 
The Rock Island Inland Waterways Remote Sensing 
Program began in 1985 and is in its final year. 
During the program a complete operational remote 
44-2

sensing GIS system was configured that will allow 
the water control data management and reservoir 
regulation groups to run real-time forecasting 
models in a workstation environment. The system 
will merge point, spatial and temporal data into a 
data storage system for use by the district field 
staff. In addition, four Engineer Technical Letters 
(ETLs), six reports, and four software programs 
were prepared which can also be used by all Corps 
districts in their day-to-day activities. Geotechnical 
instruments that will automate the data collection 
of many of the parameters required in the dam 
safety program have also been tested and recommendations 
made on the usefulness of the sensors 
to Corps projects. 
Major benefits to the Corps will be higher quality 
data at less cost and quicker reaction times for 
operations. The total cost of the six-year Remote 
Sensing Demonstration Program is approximately 
$1.55 million. The estimated annual cost savings 
will be $364,000 per year. The annual savings ofinhouse 
manpower requirements to the Rock Island 
District will be 4.0 work-years. 
Remote Sensing Program 
Snow, soil moisture, water quality and geotechnical 
sensors have been evaluated to obtain the 
highest quality data products for our models used 
in our water resources mission areas. These sensors 
provide real time information to the District 
offices allowing more effective forecasts of water 
conditions and the ability to regulate the reservoirs 
and navigable waterways to maximum efficiencies. 
The reduction in maintenance (sensor costs 
and manpower) of this data collection activity has 
reduced the costs at the rate of $1000 K/yr. It has 
also provided the data to reduce flooding and improve 
navigation at greatly reduced costs. 
A new data management package has been developed 
that allows rapid input of real-time in-situ 
sensor data and remotely sensed imagery to water 
control forecast models. The ability to rapidly integrate 
large volumes and varieties of data will be 
especially beneficial for reservoir regulation and 
emergency operations. The cost/benefit ofthis capability 
is now being established and is expected to be 
in the millions. 
Construction Productivity 
Advancement Research 
CRREL played a key role during 1989 in the development 
ofa new Civil Works research initiative 
to improve the productivity of the U.S. construction 
industry. Severe winter climates provide a significant 
challenge to construction. The Construction 
Productivity Advancement Research (CPAR) Program 
provides an excellent opportunity to combine 
the talents of the Laboratory with the experience of 
our civilian counterparts to mitigate the challenges 
presented by winter. CRREL has established three 
projects sharing the cost of research in cold regions 
pavements, concrete aggregates and landfill liners 
with industry and two state governments. Corps 
funding for these projects was $685,000 while our 
construction industry partners contributed about 
$4.5 million, making CRREL's efforts the most 
highly leveraged of all projects in the FY89 Corpswide 
program. 
Water Resources of Cold Regions 
Corps technology for the snowmelt component of 
flood forecasting is of 1950s vintage. A recent accomplishment 
is the application of the Corps Geographic 
Information System (GIS) to predicting 
the influence ofsnowmelt. This research also works 
toward calibrating existing flood forecast models to 
water temperature. Findings will be transmitted 
among the districts through publication of an ETL 
and updates to Engineering Manuals (i.e., Watershed 
Run-Off Analysis). Alaska, Rock Island, Baltimore 
and Detroit Districts have already participated 
in field tests or otherwise shown interest in 
the technology. 
Current research will determine the magnitude 
of bank erosion caused by interactive freeze-thaw 
processes, e.g., fluctuating surface waters and varying 
groundwater levels contribute to the erosion by 
providing a water source. Results from this program 
will be directly applicable to proposed work in 
assessing impacts of climate change. Improved 
techniques, models and sensors are the products to 
help measure and predict runoff, sediment transport, 
erosion, and water quality and their effects on 
hydrologic systems. GIS technology will be used to 
test snowmelt routines for applicability to COE 
flood forecasting operations. The utilization of new 
computer technology, especially GIS applications, 
in analyzing water resources engineering problems 
promises tremendous time-saving tools for 
being able to utilize spatial data bases that have 
not been feasible in the past. This added capability 
will improve the Corps' ability to make better hydrologic 
and water resources analyses. Estimated 
cost savings are $500,000 per year. 
44-3

U.S. ARMY ENGINEER WATERWAYS 
EXPERIMENT STATION 
Organization and functions. The Waterways Experiment 
Station (WES) is a field operating agency of the 
Chief of Engineers operating under the staff supervision 
of the Director, Research and Development. COL 
Larry B. Fulton, Corps of Engineers, is Commander 
and Director. Dr. Robert W. Whalin, PE, is Technical 
Director. Dr. Dennis R. Smith is Assistant Technical 
Director. 
WES, the Corps of Engineers largest laboratory 
complex for research, testing, and development, consists 
of six technical laboratories: Hydraulics, 
Geotechnical, Structures, Environmental, Coastal Engineering 
Research Center, and Information Technology 
Laboratory. The Hydraulics Laboratory, the largest 
laboratory of its kind in the world, uses a wide range 
of working models and computer-based numerical 
models for research and analysis of dams, levees, river 
and harbor projects, soil and streambank erosion, 
thermal pollution, etc. The Geotechnical Laboratory 
conducts research in soil mechanics, structural foundation 
design, embankment design and slope stability, 
seepage analysis, military pavements, engineering geology, 
rock mechanics, expedient surfacing, earthquake 
engineering, and mobility and trafficability. The Structures 
Laboratory uses theoretical, analytical, experimental, 
and modeling approaches to research the 
effects of nuclear and non-nuclear explosions, the 
response of structures to natural and explosive disturbances, 
and various construction materials with emphasis 
on concrete, especially the testing, repair, artd preservation 
of existing concrete structures. The 
Environmental Laboratory researches the problems 
caused by man's activities with respect to the environment. 
Research programs include Dredged Material, 
Aquatic Plant Control, Environmental and Water 
Quality Operational Studies, Environmental Impact, 
Wetlands, and the Natural Resources Research Program. 
These and other programs of the Environmental 
Laboratory range through waste management, environmental 
regulations, and military aspects of terrain and 
camouflage. The Coastal Engineering Research Center 
conceives, plans, and conducts research and data collection 
in coastal/ ocean engineering and nearshore 
oceanography to: provide a better understanding of 
waves, winds, water levels, tides, and currents; and 
provide scientific and engineering data and design 
criteria for materials as they apply to navigation 
improvements, flood storm protection, beach erosion 
control, recreation, and protection of structures in the 
coastal zone. The Information Technology Laboratory 
is responsible for all communications, mainframe computer 
functions for both technical and administrative 
applications, graphic presentations, and printed media 
at the station. 
WES Laboratories are engaged in research and engineering 
investigations in support of the civil and military 
missions of the Chief of Engineers. On a reimbursable 
basis, WES performs basic and applied research, 
develops state-of-the-art methods and techniques, tests 
materials and equipment, and provides consulting services. 
Subject to the approval of the Chief of Engineers, 
studies and investigations may be undertaken 
for agencies outside the Department of the Army. 
WES maintains an extensive scientific and engineering 
reference library to serve the specialized needs of 
the Corps of Engineers and issues publications of 
general interest; operates DoD Information Analysis 
Centers in the fields of Pavements and Soils Trafficability, 
Concrete Technology, Hydraulic Engineering, 
Soils Mechanics, and Coastal Engineering; and maintains 
the Corps of Engineers Engineering Computer 
Programs Library. 
During Fiscal Year 1989, 245 WES numbered 
reports of individual studies conducted at or for WES, 
3 instruction reports, 18 information exchange bulletins, 
4 video reports, and 108 various special purpose 
technical documents (conference reports, special study 
reports, etc.) for WES and other offices were printed 
and distributed to Corps offices and interested outside 
agencies. 
Operations and results during the period. Work 
accomplished at WES is, in general, initially financed 
by the Corps of Engineers Revolving Fund, with direct 
reimbursement from agencies requesting research investigations 
and related services. The Station's total program 
during Fiscal Year 1989 was $136,414,500 which 
included $29,847,000 performed by contract. Of the 
total program $78,545,600 was oriented toward the 
civil sector and $57,869,000 to military. The plant 
replacement and improvement program was 
$6,855,000 for this period. 
45-1

U.S. ARMY ENGINEER TOPOGRAPHIC LABORATORIES 
Organization and functions. The U.S. Army 
Engineer Topographic Laboratories (USAETL) 
began during World War I as a temporary Engineer 
Detachment formed to test aerial photographic 
mapping. Since that time, USAETL has grown to 
become a sophisticated, modern research and 
development complex. The laboratories perform 
research and development by applying the latest 
advances in electronics, information processing 
and related technologies in the environmental and 
topographic sciences to military and civil problems 
in mapping, surveying, land navigation and 
geographic information. USAETL is a field 
operating agency of the Corps of Engineers 
commanded by Colonel David F. Maune. 
USAETL is the only defense research and 
development laboratory that addresses the full range 
of developments in the topographic sciences, from 
basic research to a final product. Supportis provided 
to both Civil Works and Military elements of the 
Corps, the Army Materiel Command, Army Space 
Program Office, Defense Advanced Research 
Projects Agency and other federal Government 
organizations. To provide this support, USAETL is 
divided into six operational elements, three of 
which are developmental laboratories. The 
Geographic Sciences Laboratory performs research 
and development associated with the extraction 
and presentation of geographic data. The 
Topographic Developments Laboratory supports 
technology developments in surveying, map 
making, military geographic information systems 
and reproduction systems. The Space Programs 
Laboratory conducts research and development 
relating to the Army Space Program and acts as the 
Corps executive agent for space. The Research 
Institute performs most of the laboratories' basic 
and applied research. The Terrain Analysis Center 
prepares terrain studies needed by Army elements 
in the field. The Digital Concepts and Analysis 
Center serves as the primary point of contact to 
Army developers and users for digital topographic 
data.
In recent years, the emphasis of USAETL's 
research and development program has shifted 
from historic map making and surveying equipment 
and related techniques to new topographic data 
systems. These systems are required to support 
emerging weapons systems and military geographic 
information systems needed by field commanders 
for improved command, control, communications 
and intelligence. The new systems frequently use 
data acquired by remote sensing, and much of the 
work at USAETL involves this technology. 
Researchers atUSAETL are investigating the types 
of data acquired through sensors and the means to 
exploit that data. Studies showing the possibility of 
automating digital image interpretation are an 
important aspect of this work. Other work is to 
investigate digital processing of remotely sensed 
data and define remote sensing inputs required for 
Army terrain graphics and terrain data bases. 
Operations and results during FY90. The 
total program for USAETL in FY90 was $97.6 
million. This included work done for other agencies 
as well as for the Corps of Engineers. Of this total 
program, $62.3 million supported work performed 
by contract. Work in FY90 included $383,000 
charged to civil works funds 
Civil works efforts by USAETL in FY90 
included research to develop and demonstrate new 
equipment and techniques for the Surveying and 
Mapping Research, Dredging Research and Civil 
Works Guidance Update Programs. 
USAETL engineers continued development of 
the NAVSTAR Global Positioning System (GPS) 
for use by the Corps in a wide variety of engineering 
applications. Demonstration and consultation 
projects on GPS applications were completed in 12 
districts. These included projects for geodetic 
surveying and implementation of GPS on 
hydrographic survey vessels. One project was for 
emergency support to the San Francisco District 
following the earthquake. A study was completed 
examining data communication alternatives for 
Corps-wide implementation of GPS for 
hydrographic survey vessels and dredges. A study 
was also completed to investigate the use of GPS to 
determine tides and water level heights. 
A demonstration and evaluation of a new, full 
bottom coverage, hydrographic survey system was 
conducted. The system evaluated was judged not 
survey-ready for typical Corps activities. This 
evaluation will help prevent future contract disputes 
from arising over the use of this system. 
Guidance was provided to the field operating 
agencies on surveying and mapping standards in 
the form of one Engineer Technical Letter, one 
Engineer Manual and one Guide Specification. 
These were on hydrographic surveying and datum 
transformations. 
A software package was developed and 
distributed to the field operating agencies for the 
manipulation and transformation of survey data. 
This will allow more efficient use of personal 
computers and Computer Aided Design and 
Drafting workstations by the surveyors. 
46-1

THE WATER RESOURCES SUPPORT CENTER 
The Water Resources Support Center (WRSC), is a field 
operating agency under the staff supervision of the Director 
of Civil Works, Headquarters, U.S. Army Corps of 
Engineers. The Center consists of the Institute for Water 
Resources, the Navigation Data Center, the Washington 
Level Review Center and support elements. It is located 
at the Humphreys Engineer Center, Fort Belvoir, Virginia, 
with satellite elements at other locations, including 
the Hydrologic Engineering Center at Davis, California; 
and the Waterborne Commerce Statistics Center 
part of the Navigation Data Center in New Orleans, 
Louisiana. The accomplishments of WRSC during FY 
1989 are listed by Division. 
U.S. ARMY ENGINEER INSTITUTE FOR WATER RESOURCES (IWR) 
NAVIGATION DIVISION 
The IWR Navigation Division provides support to 
Corps field divisions and districts for project-specific and 
system studies of navigation improvements. It also provides 
support for the Inland Waterways Users Board and 
performs special studies as directed by the Office of the 
Chief of Engineers. The special studies address a variety 
of subjects where expertise in economic analysis is required, 
and range from assessment of transportation 
infrastructure to identification of economic impacts. 
Continuing Support Activities. The foundation for 
evaluation of navigation projects, both inland waterway 
and deep draft harbors, is the comparison of transportation 
costs with and without proposed improvements. The 
Division maintains and annually updates data on ocean 
and waterway vessel operating costs, the dimensions of 
those vessels, the distribution of ocean vessel sizes in the 
world fleet, and the configuration of barge tows on inland 
waterways. 
Coordination of Navigation Studies. The Inland 
Waterways Users Board, created by the Water Resources 
Development Act of 1986, is charged with advising 
Congress on priorities for improving inland waterways. 
To provide information desired by the Board and by the 
Corps, the Division produced an "Inland Waterway Review" 
in FY88 that provided a 10-year look ahead at 
waterway system traffic, problems, performance and 
investment requirements. In FY89, the Division routinely 
provided the Users Board with a series of analyses 
of the Inland Waterways Trust Fund and the adequacy of 
the Fund to support construction of authorized and 
potential improvements. 
Special Studies. The Division also produced a 
comprehensive review of inland waterway issues and 
problems in FY 89. This was provided to the U.S. 
Department of Transportation for incorporation in the 
National Strategic Transportation Planning Study requested 
by Congress. 
FUSION CENTER 
The mission of the Fusion Center is to provide leaders 
and managers multi-disciplinary, collaborative planning 
and creative problem-solving expertise. The Center 
services more than 20 Corps' offices, more than 20 non- 
Corps, DoD organizations, and 3 non-DoD agencies. The 
Center's facility is specially designed to support collaborative 
workshops, and is operated with attention to 
people's physical and psychological, as well as their 
information processing needs during workshops. A team 
of four professionals with a blend of engineering, psychology, 
information management and Administrative 
training with four years experience as a group provide 
customer service. 
The following is a list of planning groups facilitated by 
the Center: 
Task Forces 
* DoD Environmental Initiative (DoD) 
* LEAD Team (USACE) 
* Long Range Stationing Study (DCSOPS/OACE) 
* Engineer Force Modernization Task Force (USAES) 
* Human Resources 2000 (Dir HQ) 
Projects 
* Human Resource Management in the Corps 
* Leadership Education and Development 
* Fusion Center Consortium 
* Corps' Futures 
Project Assistance 
* Future Corps' Civil Works Strategies 
* Army Resource Management 2000 
* Corps' Senior Leadership Conferences 
* Outdoor Recreation (IWR) 
* Real Property Planning and Management 
(OACE, EHSC) 
Advice, consultation, facilitation, and workshop design 
* Internal Revenue Service 
* CERL 
* DoD Program Executive Offices 
47-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
RESEARCH DIVISION 
The Research Division responds to the water planning 
research needs of the fields, as well as one-of-a-kind 
projects assigned by the Office of the Chief of Engineers. 
At the same time, research assistance is given to Corps' 
field divisions and districts. Staff members of the Research 
Division apply specialized knowledge in fields 
such as economics, environmental science, sociology and 
engineering, to develop and conduct a broad range of 
research aimed at producing practical and effective planning 
tools. Research outputs are applied in Civil Works 
(CW) throughout the Corps, and, in several cases, to 
military problems as well. 
During FY 89, the Research Division was responsible 
for two long range research programs: Planning Methodology 
and Risk Assessment Planning. 
Planning Methodologies and Risk Assessment is focused 
on developing economic, financial, environmental 
and social evaluation techniques for planning flood control, 
navigation, and other water resources projects. 
Work includes developing economic evaluation manuals, 
microcomputer applications, regional analysis models, 
navigation project evaluation procedures, and flood control 
evaluation. Research Division also performs reimbursable 
research studies for HQUSACE and field offices. 
FY 89 accomplishments in this program include the 
completion of a manual providing guidance to Corps' 
economists on the computation of agricultural flood damages, 
and the initiation of work on a manual to provide a 
description of the economic evaluation of coastal shore 
protection projects. In addition, research to investigate 
the feasibility ofdevelopingapproaches for flood warning 
system benefit estimation was initiated. 
In FY 1989, the risk research program continued to 
identify critical components of risk and uncertainty in 
Corps' flood control and navigation planning. Research 
was also tasked to develop more effective methods for 
communicating information about risk in planning 
studies. A model for assessing the risk-cost of alternative 
dredge material disposal sites was developed. 
The Institute's training program provides a means for 
transferring research results and state-of-the-art planning 
techniques to various Corps' users. Courses on 
topics ranging in scope from Conflict Management to 
Economic Analysis for Water Resource Planning were 
conducted during the year. During FY 89, approximately 
500 persons attended 15 sessions of 8 training courses. 
POLICY STUDIES DIVISION 
In FY 89, the staff of the Policy Studies Division 
completed work on a number of important studies. A 
special report was completed on Corps' Activities in the 
1988 Drought. This document together with previous 
work on the 1986 and 1977 drought and several studies 
on reallocation opportunities, formed the basis ofa drought 
workshop in FY 89. Internal policy scoping in anticipation 
of a national water management during drought 
study was also begun. 
A significant amount of effort was also devoted to use 
of Alternative Dispute Resolution techniques in the new 
partnership planning environment as well as claims 
settlement. Work was also underway on a variety of 
topics including climate change, beneficial use ofdredged 
material, life cycle project management, Vision 21, 
groundwater flooding, and water resources planning for 
military bases. 
WASHINGTON LEVEL REVIEW CENTER (WLRC) 
The Washington Level Review Center (WLRC) was 
established in WRSC in December 1988 to accelerate the 
Civil Works project development process and add efficiencies, 
while maintaining quality and controlling 
schedules and costs. WLRC was assigned the mission of 
reviewing feasibility reports required by the Board of 
Engineers for Rivers and Harbors, Headquarters USACE, 
and the Assistant Secretary of the Army for Civil Works. 
Also, WLRC had responsibility for managing the Washington 
level review and processing of feasibility reports, 
WLRC reviews post authorization change reports, detailed 
project reports, general design memorandum, and 
other decision documents that the Director ofCivil Works 
may request. 
During FY 89, WLRC reviewed 78 documents. These 
consisted of 23 feasibility reports, 24 design memoranda, 
3 detailed project reports, 6 post authorization change 
reports, 17 documents for feasibility review conferences, 
and 5 special reports. 
47-2

HYDROLOGIC ENGINEERING CENTER 
The mission of the Hydrologic Engineering Center 
(HEC) is to increase the Corps technical capability in 
hydrologic engineering and planning and management. 
This is accomplished through research, training and 
technical assistance programs in hydrologic engineering 
and planning analysis, HEC maintains an awareness of 
the present needs and upcoming problems of the water 
resources community through continuous dialogue with 
Corps field offices and headquarters, universities, private 
industry, other Federal agencies and state and local 
governments. HEC bridges the gap between academic 
research and practical applications in the field. 
This year HEC made substantial commitments to 
move forward on several fronts: develop a new generation 
of hydrologic engineering computation products; 
document technical methods and guidance for field office 
reference; begin adapting HEC training courses to the 
reality of Corps-customer partnerships and life cycle 
project management; fine-tune and solidify our new 
program distribution policy; and continue to work closely 
with headquarters and field offices on high-priority 
projects. 
Substantial improvements have been made to the 
existing HEC-1, 2, 5, 6, and FDA packages. New releases 
of these programs for MS-DOS personal computers were 
made in late FY89 or are planned for early FY90. These 
packages include fully developed menu shell user interfaces 
and implementation of the data management and 
graphics display capabilities of the ItEC developed I)ata 
Storage System (DSS). Experiments were begun for 
program implementations on a UNIX PC operating 
system. An engineering workstation was ordered to let 
us work in that environment. The first major program to 
be developed employing software engineering techniques 
and designed specifically for the interactive PC environment 
is emerging from the design stage. The Interior 
Flood Hydrology program will be tested in mid-1990 and 
is planned for general release late in the year. 
Progress has been steady on products for the Corps 
guidance development project and cost-share partner 
communications. An ER establishing management principles 
for hydrologic engineering was completed and 
published. The new EM for river hydraulics is in the 
preliminary draft state. Sections of it have been used in 
training courses. Documents describing hydrologic 
performance of flood control projects, explaining flood 
risk, performing hydrologic frequency analysis, and 
documenting study guidelines for flood warning - preparedness 
programs were completed. Work began in 
earnest on several additional guidance products: 
catchment analysis EM hydrologic analysis by project 
purpose EM, degree-of-protection EP, and several ERs. 
Next FY HEC will continue increased emphasis on guidance 
development efforts. 
Seven PROSPECT courses were conducted for a total 
of 10 weeks of training. The courses covered a variety of 
hydrologic engineering and planning analysis topics. 
Attendance averaged about 30 students per course. The 
Hydrologic Engineering for Planning and Flood Loss 
Reduction Planning courses included presentations on 
the Corps two-phased planning process, partnership 
arrangements with local agencies, and life-cycle project 
management. Six workshops were also held comprising 
four weeks of sessions. Topics included flood damage 
analyses, reservoir simulation, and computer programs 
and methods in support of floodplain analysis. 
Reimbursable project work was undertaken for 18 
Corps offices including districts, divisions, headquarters, 
and R&D laboratories. The total reimbursable program 
was $900.000 with individual projects ranging 
from a few thousand dollars to over $100.000. Projects 
included watershed modeling, river hydraulics, water 
quality, flood frequency analysis, water control software 
development, and participation in start-up activities for 
the National Drought Study. Several projects were undertaken 
in support of realtime water control activities. 
The planned program for FY 1990 includes increased 
emphasis on development of technical guidance in support 
of HQUSACE initiatives and concentrated efforts to 
move HEC computational products to the emerging 
workstation environment. Training activities are expected 
to rebound from the low in FY 1989. Technical 
assistance will continue to be substantial. The anticipated 
increase in R&D funding for FY 1990 did not materialize. 
In fact a decrease occurred. This continues the erosion in 
R&I) funding that has taken place over the past 10 years. 
NAVIGATION DATA CENTER 
The Navigation Data Center's mission is to collect, 
process, manage, and distribute information regarding 
the characteristics of the U.S. Waterway System, including 
use, operation and physical aspects. This information 
consists of a variety of statistical data relating to 
foreign and domestic waterborne commerce, vessel, and 
port and lock facility inventory descriptions and lockage 
operations. The Center's 1989 theme was development of 
a strategic plan intended to strengthen internal data 
partnerships between Waterborne Commerce, Lock Performance 
Monitoring, and Port Facilities. To ensure 
user-oriented design of the new data base management 
systems, a series of workshops and meetings with both 
the Corps and user community was completed in FY 
1989. The implementation of each data area has begun, 
and each is at a different state of development. 
47-3

REPORT OF THE SECRETARY OF TIIE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
WATERBORNE COMMERCE STATISTICS CENTER 
The development of the new computer software is 
nearly complete and on schedule. Full implementation 
will begin in April 1990. WCSC now has the capability to 
provide statistics by state. Two new public domain data 
bases are now available. One data base contains originto-
destination commodity flows for major commodity 
groups among 26 geographic areas, and the other among 
the 50 states, Puerto Rico and the Virgin Islands. 
LOCK PERFORMANCE MONITORING SYSTEM (PMS) 
PMS continues the collection and archiving of data. 
Users meetings were initiated in FY 1989 to review PMS 
data requirements in conjunction with planning and 
operations personnel. These meetings have resulted in 
proposed changes and reduced data elements to be collected. 
The first set of changes regarding the shift log will 
be implemented in January 1990 and the second set will 
be implemented in January 1991. 
PORT FACILITIES 
Automated report preparation and port data base 
design are underway. Meetings held in FY 1989 with 
users, including Corps, other Federal agencies and the 
public, culminated in plans for data base management 
system and integration into the WCSC enforcement 
process. Port facility data for all reports, including over 
9,000 facilities, has been input to the Ports data base. In 
FY 1989, four reports were issued: 
Number 
12 
41 
43 
44 
Title 
Port of Houston, TX 
Port of Buffalo, Rochester, Oswego and 
Ogdenburg, NY 
Ports of Cleveland, OH 
Port of Toledo, OH 
47-4

PERMANENT INTERNATIONAL ASSOCIATION OF NAVIGATION CONGRESS 
(PIANC) 
The Permanent International Association of Navigation 
Congresses (PIANC) is an international organization 
consisting of approximately 40 national members, with 
headquarters in Brussels, Belgium. It is a clearinghouse 
where technology and experiences relating to ocean and 
inland navigation improvements are exchanged among 
engineers, scientists, port operators, and marina and 
vessel owners, to name a few. Its objective, broadly 
stated, is to promote the worldwide progress of inland 
and maritime navigation through the exchange of technical 
information on port and waterway development. 
The objective of the Association is met by holding International 
Congresses and by publishing quarterly technical 
bulletins and special reports. Special reports are 
published as a result of international research teams, 
called Working Groups, made up of those national 
members interested in the particular subject under study. 
Examples include methods of disposal of dredged material, 
an international survey of dry dock facilities and 
their characteristics, the beneficial use of dredged material, 
and other various topics relating to port and waterway 
development. The organization also serves as an excellent 
source of identifying individual and corporate expertise 
throughout the world on PIANC-related subjects. 
Personal interchange of ideas and information also is 
promulgated by members attending the International 
Congresses held once every four years. 
The affairs of the Association are managed by a Permanent 
International Commission (PIC), composed of delegates 
from each member government. It is in this way 
that member governments are represented in PIANC. 
The number of delegates is determined by the size of the 
national membership, but may not exceed ten per country. 
The United States has been a member of PIANC since 
1902 and has since provided an annual appropriation for 
the support and maintenance of the organization. This 
includes an annual subvention to PIANC International 
and payment of the travel expenses of properly accredited 
national delegates (Commissioners) of the United 
States to meetings of the International Commission and 
Congresses. Total appropriations for the U.S. Section, 
PIANC are currently $45,000 per year, including the 
annual subvention of approximately $10,000 to PIANC 
International. 
The United States Section is administered, by law, 
under the auspices of the Department of the Army (Corps 
of Engineers). The U.S. Section is composed of both 
individual and corporate members who pay their own 
membership dues. Membership of the U.S. Section on 
December 31, 1989, totaled 567, consisting of 480 individual 
members and 87 corporate members. 
Like all other member nations, the United States 
National Commission constitutes the governing body of 
the National Section. The ex-officio Offices of the U.S. 
National Commission are: Chairman (Assistant Secretary 
of the Army (CW)); Chairman Pro Tempore (Director of 
Civil Works); and Secretary (Mr. DuWayne A. Koch). 
During calendar year 1989, U.S. National Commissioners 
were: Mr. J. Ron Brinson, President and Chief 
Executive Officer, Port of New Orleans; Mr. Charles F. 
Connors, Director of Maritime Services, Mofatt & Nichol, 
Engineers; Dr. Tudor T. Davies, U.S. Environmental 
Protection Agency; Dr. G. Edward Dickey, Office of the 
Assistant Secretary of the Army (Civil Works); Mr. John 
M. Pisani, Maritime Administration, U.S. Department of 
Transportation; Mr. Charles R. Roberts, Director of Engineering, 
Port of Oakland; Mr. R. Erik Stromberg, 
President, American Association of Port Authorities; and 
Dr. Alan R. Thomas, National Oceanic and Atmospheric 
Administration. 
The U.S. Section representatives to the two Permanent 
Technical Committees (PTCs) and Working Groups of 
PTCs were as follows: 
Permanent Committee for Developing Countries - Dr. 
Anatoly B. Hochstein, LSU/GW Ports and Waterways 
Institute 
Permanent Technical Committee I (Inland Waterways 
and Ports) - Major General Robert F. Seedlock, USA 
(Ret.) 
Working Group 1, Economic Implications of Inland 
Waterway Development-George Antle, USACE IWR 
Working Group 2, Disposal of Dredged Materials - 
Charles C. Calhoun USACE WES 
Working Group 3, Consideration Or Risk in Determining 
Bank Protection - Alan D. Crowhurst, Maccaferri Gabions 
Working Group 4, Guidelines for the Design and Construction 
of Flexible Revetments Incorporating 
Geotextiles for Inland Waterways -Max Lamb, USACE 
LMVD 
Working Group 5, Container Transport with Inland 
Vessels - John M. Pisani, US DOT/MarAd 
Working Group 6, Problems Created by Salt Water 
Intrusion (from the sea or marine estruaries) in Inland 
Navigation - Christina E. Correale, USACE SAW 
Working Group 7, Management of Dredged Material 
from Inland Waterways - Charles C. Calhoun, USACE 
WES 
Working Group 8, Automatic Management ofCanalized 
Waterways and Its Hydraulic Problems- Jack R. Niemi, 
USACE LMS 
Working Group 9, Standardization of Inland Waterways' 
Dimensions, Dr. Anatoly B. Hochstein, LSU/GW 
Ports and Waterways Institute 
Working Group 10, Supervision and Control of Long 
Lateral Embankments - No U.S. Representative 
Working Group 11, Analysis of the Cost of Water 
Transportation and the Cost of Terminal Fees -George 
Antle, USACE IWR 
Working Group 12, Design, Installation and Maintenance 
of Natural Vegetation Bank Protections Utilizing 
Geotextile Reinforcement for Inland Waterways - Max 
Lamb, USACE LMVD 
48-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1988 
Permanent Technical Committee II (Maritime Ports 
and Seaways)- Dr. Ernst G. Frankel, Massachusetts 
Institute of Technology 
Working Group 1, Navigation in Muddy Areas - No 
U.S. Representative 
Working Group 2, Stability of Rubble Mound Breakwaters 
in Deeper Water - Eugene H. Harlow, Soros Associates 
Working Group 3, Ice Navigation - C. Allen Wortley, 
University Or Wisconsin 
Working Group 4, Dangerous Goods in Ports - No. 
U.S. Representative 
Working Group 5, Underkeel Clearance for Large Ships 
in Maritime Fairways with Hard Bottoms - Ronald C. 
Uhl in, Exxon International 
Working Group 6, Classification of Soils and Rocks to 
be Dredged - James W. Bean, C. F. Bean, Inc., New 
Orleans 
Working Group 7, Dimensions and Layout Or Channels 
- Leonard Van Houten, Greenwich, CT 
Working Group 8, The Damage Inflicted by Ships with 
Bulbous Bows on Underwater Structures - Wesley 
Allen, Jr., Georgia Ports Authority 
Working Group 9, Development of Modern Marine 
Terminals - Charles R. Roberts, Port of Oakland 
Working Group 10, Disposal of Dredged Material at 
Sea-Robert Engler, USACE WES 
WorkingGroup 11, Consequences ofNew Developments 
Or Car/Passenger Ferries - No U.S. Representative 
Working Group 12, Performance and Design Parameters 
of Rubble Mound Breakwaters - Robert Whalin, 
USACE WES 
Working Group 13, Floating Breakwaters ---John 
Oliver, USACE WES 
Working Group 14, Economic Methods of Channel 
Maintenance - DeWitt D. Barlow, Great Lakes Dredge 
and Dock Co. 
Working Group 15, Dry Docks - Michael Yachnis, 
Naval Facilities Engineering Command 
Working Group 16, Specification of Quantities and 
Related Risks on Maritime Transportation of Hazardous 
Chemicals and Wastes -Patrick Tobin, USEPA 
Working Group 17, Inspection, Maintenance and Repair 
of Maritime Structures Exposed to Material Degradation 
Caused by a Salt Water Environment - Charles 
F. Connors, Moffatt & Nichol, Engineers 
Working Group 18, Planning of (Commercial) Fishing 
Ports - No U.S. Representative 
Working Group 19, Beneficial Uses of Dredged Material 
- Jesse Pfeiffer, USACE CERD-C 
Working Group 20, Capacity Simulation Models for 
Approach Channels and Fairways in Harbors - Haruzo 
Eda, Stevens Institute of Technology 
Working Group 21, Flexible in the Marine Environment 
- Chatham, USACE WES 
Joint Subcommittee on Pleasure Navigation - John 
Moffatt & Nichol, Engineers 
Working Group 1, Ecological Conservation in Relation 
to Sport and Pleasure Navigation - Neil W. Ross, International 
Marina Institute 
Working Group 2, Wave Climate Criteria for the Design 
of Yacht Harbors and Marinas - Orson Smith, Clayton, 
NC
Working Group 3, Provision of Navigation Aids for 
Pleasure Craft - Austin E. Brant, Jr., TAMS 
Working Group 4, Chartering Services - Their Growth 
and Impact on Sport and Pleasure Navigation - Eugene 
H. Harlow, Soros Associates 
Working Group 5, Standards for Construction, Equipment 
and Operation of Yacht Harbors and Marinas -William 
A. Jansen, Illinois Department of Conservation. 
48-2

INTERNATIONAL BOUNDARY WATERS BOARDS 
In order to carry out United States obligations under 
international agreements, the Office of the Chief of 
Engineers and several Corps Divisions and districts with 
jurisdiction over areas bordering Canada have representation 
numerous international boards, committees, 
and other groups. The majority of these boards were 
established by the International Joint Commission (IJC) 
as empowered in accordance with the provisions of the 
Boundary Waters Treaty of 1909 between the United 
States and Great Britain (for Canada). IJC boards fall 
into two broad categories: boards of control, which are 
more or less permanent and supervise compliance over 
an IJC order; and engineering, technical, or study 
boards, which are usually dissolved after completing and 
reporting on an investigation assignment. In addition to 
boards created by the Commission, other international 
boards and committees are created by treaties or other 
arrangement in matters concerned with the water resources 
ofjoint interest, and the members report directly 
to the Governments or establishing agency. International 
boundary waters boards and committees having 
Corps of Engineer memberships during the fiscal year 
are listed in Table 49-1. For an explanation of the 
constitution of the various boards and committees, see 
the FY 77 and FY 80 annual reports. An innovative study 
organization, neither a board nor a committee, was 
established to conduct a study offluctuating Great Lakes 
levels pursuant to a Reference to the IJC from the 
Governments of Canada and the United States, dated 
August 1, 1986. A discussion of that study organization, 
which was established during FY 87, follows Table 49-1. 
TABLE 49-1 
IJC BOARDS OF CONTROL HAVING CE MEMBERS 
BOARD NAME 
YEAR 
ESTABLISHED UNITED STATES REPRESENTATION 
1. 
2. 
3. 
4. 
5. 
Int. Lake Superior 
Int. St. Croix River 
Int. Lake of the Woods 
Int. Lake Champlain 
Int. Kootenay Lake 
6. Int. Rainy Lake 
7. Int. Osoyoos Lake 
8. Int. Niagara 
9. Int. St. Lawrence River 
10. Int. Skagit River 
11. Int. Souris River 
12. Int. Souris-Red Rivers 
Engineer 
13. Int. Champlain-Richelieu 
14. Int. Great Lake Diversios 
and Consumptive 
Uses Study 
15. Int. Great Lakes Technical 
Information Network 
Board 
*Signifies U.S. Section Chairman. 
1914 
1915 
1925 
1937 
1938 
1941 
1943 
1953 
1953 
1967 
1959 
1948 
1975 
1977 
1979 
*Div. Engr., NCD 
*Div. Engr., NED 
*Dist. Engr., St. Paul 
*Dist. Engr., New York 
*1. Dist. Engr., Seattle 
2. Dept. of Interior, USGS, Boise, ID 
*Dist. Engr., St. Paul 
1. Dist. Engr., Seattle 
*2. Dept. of Interior, USGS, Tacoma, WA 
3. Washington State Parks & Recreation Commission, 
Olympia, WA 
* 1.'Div. Engr., NCD 
2. Dept. of Energy, FERC, Washington, D.C. 
*1. Div. Engr., NCD 
2. St. Lawrence-Eastern Ontario Commission, 
Waterton, NY 
3. NY Power Authority, Massena, NY 
*Dist. Engr., Seattle 
1. Dist. Engr., St. Paul 
*2. ND State Engr., Bismark, ND 
3. Dept. of Interior, USGS, Bismark, ND 
1. Dist. Engr., St. Paul 
*2. Dept. of Interior, BOR, Washington, D.C. 
3. Dept. of Interior, USGS, Reston, VA 
*1. New York Dept. Environ. Conser. 
2. Dist. Engr., New York 
3. Vermont Agency Environ. Conser. 
4. New England River Basins Commision, Staff Associate 
5. Dept. of Interior F&WS Boston, MA 
*1. Div. Engr., NCD 
2. Michigan Dept. Nat. Res. 
3. Illinois Dept. of Trans. 
4. Pennsylvania Dept. of Envir. Res. 
5. Dept. of Energy, FERC, New York, NY 
*1. CENCE-ED, Detroit, MI 
2. Great Lakes Environmental Research Lab., NOAA, 
Ann Arbor, MI 
3. USGS, Reston, VA 
49-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FORFY 1988 
OTHER INTERNATIONAL BOARDS OR GROUPS HAVING CE MEMBERS 
BOARD NAME 
16. Int. Lake Memphremagog 
17. Coordinating Committee 
on Great Lakes Basic 
Hydraulic and Hydrologic 
Data 
18. Int. Niagara Committee 
19. Columbia River Treaty 
Entities 
20. Columbia River Treaty 
Permanent Engineering 
*Signifies U.S. Section Chairman. 
YEAR 
ESTABLISHED 
1920 
1953 
1955 
1964 
1964 
Study of Fluctuating Great Lakes Levels Under the 
August 1, 1986, Reference. 
On August 1, 1986, the Government of Canada and the 
United States issued a reference to the IJC to study 
methods to alleviate the adverse consequences of fluctuating 
water levels in the Great Lakes-St. Lawrence 
River basin. The IJC was requested to address the 
immediate high lake level crisis and identify and evaluate 
intermediate and long-term potential measures, while 
considering such vital matters as domestic waste supply 
and sanitation, navigation, agriculture, shore property, 
flood control, wildlife and others. The IJC is to determine 
the full costs and benefits of any works or measures and 
indicate how the various interests on either side of the 
boundary would be affected. Compensatory works or 
measure to offset costs to the interests which may be 
adversely affected by any proposed regulatory measures 
also must be determined. 
The IJC proceeded with its reference responsibilities 
on three tracks. First, it submitted an initial report to the 
federal governments on November 14, 1986, listing immediate 
actions that could be taken to lessen damages 
from the then current high water levels. Second, the IJC 
formed a taskforce to evaluate measures which could be 
implemented within approximately one year to reduce 
high lake levels. The third track is the comprehensive 
study of long-term measures. 
The U.S. Department of State requested, by letter 
dated November 24, 1986, that the Corps of Engineers 
provide lead agency support to the IJC effort on this 
study. The IJC appointed a Steering Committee and a 
Project Management Team in April 1987. 
Study Level United State 
Governance Level All Three U.S 
Steering Committee Lead U.S. IJC 
Project Management Team *Div. Engr., N 
Lead IJC staf 
Chairperson c 
Functional Group No. 1 *Chief, CENC 
Functional Group No. 2 *Wisconsin D 
Functional Group No. 3 *Dr. Leonard 
Functional Group No. 4 *David LaRoc 
Functional Group No. 5 *Dr. Michael 
*Signifies U.S. Co-chairman. 4 
UNITED STATES REPRESENTATION 
*Dist. Engr., New York 
*1. Eng. Div., North Central Div. 
2. Dept. of Commerce, NOAA, Rockville, MD 
* Div. Engr., NCD 
1. Div. Engr., NPD 
*2. Bonneville Power Admin., Portland, OR 
*1. HQUSACE, CECW-ZB, Washington, D.C. 
2. Dept. of Energy, Tulsa, AR 
In the study for evaluating the long-term solutions to 
the problem of fluctuating lake levels, four distinct levels 
of study management are embodied in four different 
groups. They are made up of representatives from the 
IJC and Federal and state agencies, as well as individuals 
from universities and private sector enterprises. 
* Governance level - the six IJC Commissioners. 
* Steering Committee level - two lead IJC Commissioners 
and their lead staff and the two co-chairs of the 
Project Management Team. 
* Project Management Team level - the United States 
and Canadian co-chairs and the chairpersons of all the 
functional study groups following. 
* Functional study groups level - there are five functional 
study groups: 
Group No. 1. Hydraulic, Hydrologic and Climate 
Group; 
Group No. 2. Coastal Zone Ecology, Resources, Uses 
and Management Group; 
Group No. 3. Socio-economic and Environmental 
Impact Assessment Group; 
Group No. 4. Public Participation and Communication 
Group; and 
Group No. 5. System Synthesis and Analysis Group 
Key United States representation is presented in the 
following tabulation. In addition to the positions listed 
therein, Corps of Engineers personnel also serve as vital 
members of the various taskforce and functional work 
groups conducting different parts and different levels of 
the study. 
os Representation 
SIJC Commissioners 
Commissioner; Div. Engr., Corps of Engineers 
JCD 
)f the Functional Groups Listed Below 
ID-ED 
NR, Bureau of Water Resources and Zoning 
Shabman, Virginia Polytechnical Institute 
he, Secretary, U.S. Section, IJC 
Ben-Eli, the Cybernetic Consulting Group, Inc. 
9-2

INVESTIGATION OF PROJECTS UNDER FEDERAL POWER ACT 
The Federal Water Power Act of June 10, 1920, created 
the Federal Power Commission (in 1977 renamed 
the Federal Energy Regulatory Commission, FERC) 
composed of the Secretaries of War, Interior, and Agriculture, 
with authority to grant permits and licenses for 
hydroelectric development in all water over which Congress 
has jurisdiction. The act further required that 
work of the commission be performed by and through the 
Departments of War, Interior and Agriculture and their 
engineering, technical, and other personnel except as 
may be otherwise provided by law. By an act of June 23, 
1930, entitled "An Act to Reorganize the Federal Power 
Commission," Secs. 1 and 2 of the Federal Water Power 
Act of 1920 were amended. A commission was provided 
for, to be composed of five commissioners to be appointed 
by the President, by and with the advice and consent of 
the Senate. The necessity of performing work through 
the Department of War, Interior and Agriculture was 
removed and the commission was authorized to appoint 
such officers and employees as necessary in executing its 
function. By Title II, Public Utility Act of 1935, the 
original Federal Water Power Act was made Part I of the 
Federal Power Act, and Parts II and III were added to the 
Act. On October 1, 1977, pursuant to the provisions of 
the Department of Energy Organization Act (DOE Act), 
Public Law 59-91 Stat. (August 4, 1977) an Executive 
Order No. 12009, 42 Fed. Reg. 46267 (September 15, 
1977), the Federal Power Commission ceased to exist and 
its functions and regulatory responsibilities were transferred 
to the Secretary of Energy and the Federal Energy 
Commission (FERC) which, as an independent commission 
within the Department of Energy was activated on 
October 1,1977. 
Section 4(e) of the Federal Power Act provides that no 
water power license affecting navigable capacity of any 
navigable waters of the United States shall be issued 
until plans of the dam or other structures affecting 
navigation have been approved by the Chief of Engineers 
and Secretary of the Army. By an action, notice of which 
was published in the Federal Register Volume 40, Number 
74, dated April 16, 1975, the Secretary of the Army 
delegated to the Chief of Engineers his authority under 
Sec. 4(e) of the Federal Power Act. The Chief of Engineers 
on September 5, 1980 delegated to the Corps 
division engineers the authority for Section 4(e) approval 
of plans for non-Federal hydropower affecting navigation. 
The following work of an engineering nature was 
accomplished by the Corps division and district offices 
under the direction of the Chief of Engineers during the 
fiscal year: (1) 290 applications from non-Federal entities 
for planning, design, construction and operation of 
hydropower projects were reviewed and appropriate recommendations 
in the interest of flood control, navigation, 
and structural safety, and environmental impacts, 
relative to Corps projects, were furnished to the FERC. 
(2) 36 licensed power plants were in various stages of 
design review for addition of power at Corps dams, and 
(3) 16 Corps approved non-Federal power plants were in 
active construction stages by the end of the fiscal year. 
The Corps bills FERC licensees for the costs incurred 
by the Corps for reviewing and approving final design, 
plans and specifications for construction of power plants 
at Corps projects. In FY89, the total cost reimbursement 
to the Corps for this service was $803,986. Review of 
license applications is funded by the Corps as aline item 
in the General Investigation Account, in FY89, the cost of 
this activity was $469,063. This cost was reported to 
FERC for the Commission's assessment of annual charges 
to licensees. 
50-1

NATIONAL EMERGENCY PREPAREDNESS PROGRAM 
National Emergency Preparedness Activities 
Authority. Executive Order 12656, as amended, 
assigns responsibilities to executive departments and 
agencies to undertake national emergency planning and 
preparedness to ensure an effective national capability 
to meet essential civilian and defense needs during major 
domestic emergencies and national security emergencies. 
Status: During FY 1989, the Corps of Engineers 
continued its efforts to improve its readiness posture and 
ability to respond to various national emergencies including 
major natural disasters. Emphasis continued to 
be placed on program activities requiring a long term 
commitment of resources. The Command Readiness 
Program initiated in FY 1988 as a means to address 
mobilization requirements and resources was expanded 
to include seminars conducted at the regional level. In 
addition the focus of the Command Readiness Program 
was expanded to include issues related to other potential 
national emergencies. Work to refine the Corps of Engineers 
Readiness Evaluation System (CERES) also 
continued throughout FY 1989. Other activities within 
the National Emergency Preparedness Program included 
maintenance of and planning for the development of 
emergency facilities to support continuity of operations, 
and planning to meet the nation's water resource requirements 
in the event of a national emergency. Executive 
Order 12656 has tasked the Corps of Engineers to 
be the Executive Agency responsible for emergency water 
planning. 
Significant progress was made in the development of 
preparedness guidance and execution plans at all levels. 
While the efforts undertaken identified additional shortfalls 
or problems to be addressed, the Corps program 
continues to move towards the goal ofen suring a national 
engineering and construction capability that can respond 
to any national emergency. The Corps of Engineers 
Corrective Action Program (CECAP) continued to function 
effectively as a method for addressing the shortfalls 
or problems identified and implementing appropriate 
corrective actions. Despite limited resources, USACE 
participated in several major earthquake exercises including 
Response 89 sponsored by the Federal Emergency 
Management Agency and the South Pacific 
Division's Command Readiness Program and some funds 
were dedicated to developing and updatingthe earthquake 
plans. For fiscal year obligations and expenditures, see 
Table 51-C. 
STATUS OF THE PL 84-99 EMERGENCY FUND 
Fiscal Year 1989 
Unallocated Balance-30 Sep 87 ................. $20,292,354 
FY 89 Appropriation ................................. 20,000,000 
Revocation FY 89 ............................... . ..... 4,010,155 
Total Funds Available ................................. $43,302,504 
Allocations 
Disaster Preparedness ............................ $12,345,600 
Emergency Operations........................ 1,594,505 
Rehabilitation .................. ............ 787,843 
Emergency Water ......... ................... 490,344 
Hazard Mitigation .......................... 6,290 
Unallocated Balan ce-30 Sep 89 ............ $26,802,147 
TABLE 51-C 
NATIONAL EMERGENCY PREPAREDNESS 
Obligations 
Unobligated Balance-30 Sep 87 ............. $ 905,171 
Allotments ................ ............ ...... 7,986,519 
Total Funds Available ................. .......... 8,891,690 
Obligations................. ..... ....... 7,908,458 
Unobligated Balance-30 Sep 88 ........ $.. 983,232 
Expenditures 
Unexpended Balance-30 Sep 87 ............ $ 
A llotm ents......... ....... ......... 
1,562,668 
7,986,519 
Total Funds Available ............................. 9,549,187 
Expenditures .................................. 7,777,357 
Unexpended Balance-30 Sep 88 .......... $ 1,771,830 
51-1

NATURAL DISASTER PREPAREDNESS RESPONSE AND RECOVERY ACTIVITIES 
Activities. Disaster preparedness activities included 
the review and update of existing emergency response 
plans, training response personnel, continuation of the 
upgrading of emergency operation centers; procurement 
and maintenance of critical supplies and equipmentused 
during emergency response activities; coordination with 
Federal, State and local response agencies; and overall 
management of the preparedness, response and recovery 
program. 
Fiscal Year 1989 began just as Fiscal Year 1988 had 
ended with a continuation of drought problems across 
much of the country. USACE continued to provide emergency 
water assistance through the winter of 1988 and 
spring of 1989 to two communities in North Dakota and 
one in Illinois. As a result of the drought in Iowa, 
emergency water assistance was provided to nine communities 
in southern Iowa. The assistance started in late 
July and early August 1989 and continued into 1990. 
Also, in the fall, two communities in North Dakota were 
provided emergency water assistance, and assistance to 
one community continued into January 1990. During the 
winter and early spring, rains began to fall from eastern 
Texas across Arkansas and Missouri into the southern 
Ohio River Valley. The areas of most significant flooding 
occurred over southeast Missouri, eastern Arkansas, 
Tennessee, and Kentucky. USACE provided technical 
assistance to state and local flood fight efforts. Major 
flooding developed along the Red River of the North in 
Minnesota and North Dakota during April. In response 
to the near record flooding, USACE undertook construction 
of temporary levees and other measures to strengthen 
existing flood control projects which dramatically reduced 
flood damages. In response to localized flooding in 
early June over northwest Indiana, USACE assistance 
proved very effective. Through the month of June into 
July widespread heavy flooding occurred from east Texas 
through Arkansas, and Louisiana into northern Mississippi 
and most of the Ohio River Valley. While USACE 
provided significant technical assistance and flood fight 
materials to the areas of widespread flooding in southeast 
Texas, the long duration and record to near record 
flood levels minimized the effectiveness of state and local 
flood fight efforts. At the end ofJuly, Hurricane Chantal 
made landfall in the Galveston, Texas area. The direct 
impacts of Chantal were limited but it did exacerbate the 
problems over those parts of southeast Texas just beginning 
to recover from the earlier flooding. Three more 
tropical storms in the Atlantic Ocean became hurricanes 
during August and early September, but none impacted 
the United States. In mid September, Hurricane Hugo 
began marching through the islands in the eastern 
Caribbean leaving massive devastation in the Virgin 
Islands and Puerto Rico. Ultimately, the storm swept its 
fury into South and North Carolina. It caused few 
problems in the area of riverine flooding, however the 
storm surge caused massive damages along the South 
Carolina coast. Emergency assistance under USACE 
authority was limited. Our most significant mission was 
hauling drinkingto stricken areas in Puerto Rico. USACE 
was heavily involved in the massive recovery effort directed 
by FEMA in South Carolina and the Virgin Islands. 
USACE missions in South Carolina included debris 
clearance, removal of sunken vessels, emergency 
power generation, temporary ferry service, damage inspections, 
temporary beach dune restoration, and damage 
survey reports. In the Virgin Islands, USACE missions 
included damage survey reports, debris clearance, 
restoration of water supply, restoration ofpower systems, 
temporary repairs to homes, rehabilitation of public 
housing, and repairs to prisons. 
On top of all the flooding in the spring, came the Exxon 
Valdez catastrophic oil spill, 11 million gallons, in Alaska's 
Prince William Sound on March 24, 1989. USACE is a 
support agency to DOD under the National Contingency 
Plan. At the request of DOD to provide support to the oil 
spill recovery operations, USACE provided the hopper 
dredges Yaquina and Essayons. The dredges made a 
significant contribution to the oil spill recovery operations. 
The dredge Yaquina was used as a command post 
by the Coast Guard and Exxon. The dredge radar and 
communication equipment was used to coordinate oil 
recovery operations. The captain of the dredge provided 
technical and operational advice to the crew of the Soviet 
dredge that was also being used in the oil spill recovery 
operations. USACE R&D labs offered technical assistance 
on wind and wave data, oil containment and cleanup, and 
remote sensing and mapping. USACE also provided 
assistance in the oil spill recovery operations associated 
with the major oil spill in the Delaware River, near 
Philadelphia, PA, and the major oil spill in Galveston 
Bay, near Baytown, TX. 
52-1

CALIFORNIA DEBRIS COMMISSION 
This Commission, consisting of three Corps officers 
appointed by the President with the consent of the 
Senate, created by act of March 1, 1893 (27 Stat. L., p. 
507), was organized in San Francisco, CA, on June 8, 
1893, and has jurisdiction and duties extending over 
drainage area of Sacramento and San Joaquin Rivers, 
comprising great central valley of California and 
extending from crest of the Sierra Nevada on the east to 
that of the Coast Range on the west, and from Mount 
Shasta and Pit River Basin on the north to Tehachapi 
Mountains on the south. These rivers empty into head 
of Suisun Bay ultimately discharging into the Pacific 
Ocean through connecting bays and straits and the 
Golden Gate. Duties of the Commission comprise 
regulation of hydraulic mining in drainage area of 
Sacramento and San Joaquin Rivers, CA, so that debris 
will not be carried into navigable waters or otherwise 
cause damage; jurisdiction over construction and 
control of water storage facilities for domestic, 
irrigation, and power development purposes; and 
direction of improvements for control of floods on 
Sacramento River. On November 19, 1986, the 
Commission was abolished by the Water Resources 
Development Act of 1986 (PL 99-662) and all 
authorities, powers, functions, and duties were 
transferred to the Secretary of the Army. All acquired 
lands and other interests presently under jurisdiction of 
the Commission were authorized to be retained and 
administered under direction of the Secretary. 
IMPROVEMENTS 
Navigation Page 
1. Regulation of hydraulic mining and 
preparation of plans ................. 53-1 
2. Sacramento River and tributaries, CA 
(debris control) .................... 53-2 
3. Treatment of Yuba River debris 
situation-restraining barriers, CA ........ 53-2 
Flood Control 
4. Sacramento River, CA ................ 53-3 
Navigation 
1. REGULATION OF HYDRAULIC 
MINING AND PREPARATION 
OF PLANS 
Location. Operations largely limited to territory between 
Mount Lassen on the north and Yosemite Valley 
on the south, on western watershed of Sierra Nevada. 
(See Geological Survey sheets for the area, 25 in number.) 
Existing project. Provides for regulating hydraulic 
mining operations, planning improvement of conditions 
upon Sacramento and San Joaquin Rivers and their 
tributaries affected by such operations, and preparation 
of plans to enable hydraulic mining to be resumed in 
their drainage areas. In addition, the Secretary of the 
Army is authorized to enter into contracts to supply 
storage for water and use of outlet facilities from 
debris-storage reservoirs for domestic and irrigation 
purposes and power development upon such conditions 
of delivery, use, and payment as he may approve. 
Applications of prospective miners are fully investigated 
Tables 
Table 53-A Cost and Financial 
Table 53-B 
Table 53-C 
Page 
Statement ................ 53-5 
Authorizing 
Legislation ............... 53-7 
Sacramento River, CA: 
Total Cost of Existing Project . . 53-8 
by California Debris Commission and permits to operate 
are issued to those who provide satisfactory debris-restraining 
basins by construction of suitable dams where 
necessary or agree to make payment for storage in 
Government-constructed debris-restraining reservoirs 
constructed under act of June 19, 1934, as set forth 
below. For location and description of Governmentconstructed, 
debris-restraining reservoirs for general 
hydraulic mining, see Improvement 2. 
Local cooperation. Mineowners must bear all expenses 
incurred in complying with orders of the Commission 
for regulation of mining and restraint of debris. 
Operations and results during fiscal year. Minor 
administrative duties were accomplished. 
Administrative work overlaps that of improvements 2, 
3, and 4, hereunder, and that of Sacramento District. 
Historical summary. The Commission received 
1,292 applications for hydraulic mining licenses; 1 mine 
is licensed, but does not use storage behind Government 
debris dams. Work remaining is, in general, continuation 
of above or similar operations. 
53-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
2. SACRAMENTO RIVER AND 
TRIBUTARIES, CA (DEBRIS 
CONTROL) 
Location. Project reservoirs are to be constructed in 
watersheds of Yuba, Bear, and American Rivers, CA 
(See Geological Survey sheets for basin areas, seven in 
number.) 
Existing project. For description of completed 
North Fork and Harry L. Englebright projects and 
authorizing act, see Annual Report for 1975. Initial 
recreation facilities were provided in FY 1959. 
Recreation areas at Harry L. Englebright Dam are 
maintained by the Corps. Recreation areas at North 
Fork Dam are no longer maintained and operated by 
Auburn Recreation Park and Parkway District, but have 
been turned over to the Bureau of Reclamation (known 
as the Water and Power Resources Service between 
November 6, 1979, and May 18, 1981) on a permit 
basis. Total Federal cost of new work for construction of 
these reservoirs was $4,646,872, including $40,000 and 
$25,000, respectively, for basic recreation facilities at 
Englebright Dam and North Fork Dam. Reservoir 
project sites on Middle Fork of American River and on 
Bear River have been deauthorized and excluded from 
foregoing cost. The 90-day Congressional project 
review period, required by sec. 12, Public Law 93-251, 
as amended, ended August 5, 1977, and resulted in 
deauthorization of that portion of the project. Estimated 
cost of that portion is $1,820,000 (1935). 
Local cooperation. Fully complied with. 
Improvements made to facilities at North Fork Dam by 
Auburn Recreation Park and Parkway District under a 
lease agreement with the Secretary of the Army and 
Auburn Boat Clubs (concessionaire) at an estimated 
cost of $46,000 since September 1953. On March 1, 
1979, lands and waters at North Fork Dam were turned 
over to the Bureau of Reclamation on a 5-year 
renewable basis. On March 1, 1984, Permit No. 
DACWOS-4-79-527 was renewed for 5 years, was 
again renewed for 5 years on March 1, 1989, andwill be 
effective until February 28, 1994. Bureau will operate 
and maintain such use until Auburn project is 
completed, then a fee transfer will be made. Actual 
operation and maintenance of the recreation resource is 
being done by State of California by contract with the 
Bureau. 
Licenses. Under provisions of Contract No. 
W-1105-eng-2998 with Pacific Gas and Electric Co., 
payment is to be made to the Federal Government of 
$18,000 per year for the first 30 years (December 29, 
1942 through December 28, 1972) and $48,000 per 
year between December 29, 1972, and December 28, 
1992, in return for use of head at Englebright Dam and 
generation of hydroelectric power. Total payment 
through September 30, 1989, amounts to $1,326,393; 
these funds are paid to California Debris Commission 
and teposited for return to the Treasury. License No. 
2246, effective April 9, 1970 (date New Narrows 
powerplant was put in operation) was issued by Federal 
Power Commission (known as the Federal Energy Regulatory 
Commission since January 9, 1978) to Yuba 
County Water Agency for hydroelectric power development 
of Yuba River by the company upstream from 
Englebright Dam. Under provisions of Contract No. 
DA-04-167-CIVENG-66-95 with Yuba County Water 
Agency, payment is to be made to the Federal Government 
of $100,000 per year for no more than 50 years. 
First payment (partial) of $73,151 was made April 1, 
1971; total payment through September 30, 1989, 
amounts to $1,873,151. These funds are paid to Sacramento 
District and deposited for return to the Treasury. 
Operations and results during fiscal year. New 
work: Maintenance: Maintenance and operation 
activities continued at Harry L. Englebright Dam at a 
cost of $643,157, including recreation facilities. Dam 
safety assurance studies at Englebright Dam have been 
completed. 
Historical summary. Construction of dams was 
initiated in 1937; North Fork project was completed 
and in use at end of FY 1939, and Harry L. Englebright 
project was completed in January 1941. The two 
debris-control structures are in good condition. Public 
use of these reservoir recreation areas greatly overtaxes 
present capacities. Dam safety assurance studies were 
initiated at Englebright Dam in FY 1981 and were 
completed in FY 1987. 
3. TREATMENT OF YUBA RIVER DEBRIS 
SITUATION-RESTRAINING BARRIERS, 
CA 
Location. Works are on Yuba River between 
Marysville and where the river emerges from the 
foothills, near Hammonton, some 10 miles easterly 
from Marysville, or about 9 miles below the Narrows. 
(See Geological Survey Topographic map of 
Sacramento Valley, CA) 
Existing project. For description of completed project 
and authorizing act, see Annual Report for 1975. 
Total cost of new work was $723,259, of which 
$361,482 was U.S. funds and $361,777 required contributed 
funds by State of California. (For details of project 
in its original form, see Annual Report, 1917, p. 
1810.) In February 1963, center section of dam failed 
and major rehabilitation of structure was completed in 
December 1964. Total cost for required rehabilitation 
was $1,660,000, of which $830,000 was Federal cost 
and $830,000 required contribution by State of California 
toward rehabilitation cost. During the December 24, 
1964, floodflows on the Yuba River, the rehabilitated 
Daguerre Point Dam sustained considerable damage. 
(See 1965 Annual Report, p. 1647 "Operations and results 
during fiscal year.") The reconstructed portion of 
the dam completed earlier in December 1964 was undamaged 
by the flood. Permanent repair of Daguerre 
Point Dam abutment and fish facilities was completed in 
October 1965 at a cost of $447,808 with Federal and 
required State contributed funds on a matching basis. 
53-2

CALIFORNIA DEBRIS COMMISSION 
Local cooperation. Fully complied with for new 
work and major rehabilitation work. Total first cost to 
local interests for new work was $361,777 (required 
contribution by State of California). In addition, 
training walls were built on each bank below Daguerre 
Point for 11,250 feet and just above Daguerre Point, on 
the south bank, for 11,000 linear feet by two 
gold-dredging companies in connection with their 
dredging operations. To build these training walls would 
have cost the United States $450,000 (1902 estimate). 
Flood channels were also built by gold-dredging 
companies within confines of project works. Cost to the 
United States of equally effective works to restrain 
debris movement would have been more than $776,000 
(1926 estimate). Total costs to local interests for initial 
and permanent major rehabilitation works were 
$830,000 and $223,904, respectively, (required 
contribution by State of California). State of California 
must contribute annually an amount equal to the 
Federal allotment for maintenance. 
Operations and results during fiscal year. Maintenance: 
Operations included condition and operation 
studies by hired labor; and bank protection on Yuba 
River, consisting of a small rock groin at two locations 
upstream from Marysville completed by contract, 
$31,825. 
Historical summary. Construction of project works 
was initiated in November 1902. Construction of 
Daguerre Point Dam was completed in May 1906; 
diversion of river over dam was completed in 1910; 
training walls and dikes were completed in 1935. About 
149 million cubic yards of debris are held in lower 7 
miles of Yuba River between Marysville and 
downstream end of training walls. About 20 million 
cubic feet, are confined in river channel by Daguerre 
Point Dam. Additional millions of yards of loose 
material are in mine tailing fields adjacent to project 
training walls in upper 7-mile reach of project. Initial 
rehabilitation of Daguerre Point Dam begun in July 
1963 was completed in December 1964. Contract for 
permanent rehabilitation of structure was initiated in 
July and completed in October 1965. 
Flood Control 
4. SACRAMENTO RIVER, CA 
Location. Works- covered by this improvement are 
on Sacramento River and tributaries in north-central 
California from Collinsville to Ordbend, a distance of 
184 miles. 
Previous project. For details see page 1815 of 
Annual Report for 1917, page 1995 of Annual Report 
for 1938, and page 2262 of Annual Report for 1907. 
Existing project. Sacramento River flood control 
project is a comprehensive plan of flood control for 
Sacramento River and lower reaches of its principal 
tributaries. Improvement extends along Sacramento 
River from Ordbend in Glenn County, CA, 184 miles 
downstream to its mouth at Collinsville at upper end of 
Suisun Bay, and comprises a system of levees, overflow 
weirs, drainage pumping plants, and flood bypass channels 
or floodways designed to carry surplus floodwaters 
without inundation of valley lands. About 980 miles of 
levee construction, with an average height of 15 feet and 
98 miles of bank protection are involved in project. For 
further details, see Annual Report for 1962, page 2115. 
(See table 53-B for authorizing legislation.) 
Estimated (October 1987) cost for original project 
(exclusive of supplemental levee improvements), 
including new work and maintenance, is $163,925,000 
of which $68,925,000 is Federal cost and $95 million 
non-Federal ($90,050,562 for lands and damages and 
relocations and $4,949,438 required contributed funds 
for levee construction, bank protection works, and 
levee setbacks). Of this amount, $4,939,752 was for 
new work and $9,686 for maintenance. Estimated 
October 1989 total project cost is $180,045,000, of 
which $82,215,000 is Federal and $97,830,000 is 
non-Federal. Total estimate now includes remedial 
levee work for Yolo Bypass and Cache Slough (Unit 
109); Colusa Basin Drain (Unit 132); Knights Landing 
Ridge Cut (Unit 127) and Marysville/Yuba City Area 
levees (engineering and design only), but excludes 
Sacramento Urban Area Levee Reconstruction. In 
addition to project requirements, local interests 
constructed several pumping plants for drainage of 
agricultural and urban land protected by project levees. 
Some channel clearing work was accomplished by State 
of California and other local interests to supplement 
project levee construction. Dredging below Cache 
Slough and reconstruction of Cache Creek settling basin 
weir are considered deferred and excluded from 
foregoing cost estimate. Estimated cost (July 1962) of 
these project units is $2,560,000 and $520,000, 
respectively, a total of $3,080,000 plus U.S. costs, for 
construction. Operation and maintenance of completed 
project will be responsibility of local interests; as units of 
project are completed, they are transferred to agencies 
of State of California for operation and maintenance. 
Existing project was adopted by 1917 Flood Control Act 
(H. Doc 81, 62d Cong., 1st sess., as modified by Rivers 
and Harbors Committee Doc. 5, 63d Cong., 1st sess.), 
1928 Flood Control Act (S. Doc. 23, 69th Cong., 1st 
sess.), River and Harbor Act of 1937 (S. Committee 
print 75th Cong., 1st sess.), and 1941 Flood Control 
Act (H. Doc. 205, 77th Cong., 1st sess.). 
Phase I - Sacramento River Flood Control System 
Evaluation recommended reconstruction of 32 miles of 
Sacramento area levees. Report was approved and in 
March 1989, Sacramento Urban Area Levee Reconstruction 
project was established under authority of 
Sacramento River Flood Control Project. New project 
is located within boundaries of Sacramento River Flood 
Control System in highly urbanized area around city of 
Sacramento, near confluence of Sacramento and 
American Rivers. It includes Natomas area levees from 
Natomas Cross Canal Bypass through Reclamation 
District 900 and portions of the Yolo Bypass east levee 
in West Sacramento; and, in South Sacramento, the 
east bank of Sacramento River from Miller Park to town 
53-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
of Freeport. Estimated (October 1989) cost for 
Sacramento Urban project is $43,600,000 of which 
$21,800,000 is Federal and $21,800,000 is non-Federal 
(including a cash contribution of $2,180,000). 
Local cooperation. Local interests have fully complied 
with requirements for all work completed and 
indicated they will be able to fulfill requirements for 
remaining work. Local interest costs from required 
contributed funds for project work total $4,949,438 for 
levee construction, bank protection works, and levee 
setbacks, of which $4,939,752 was for new work and 
$9,686 for maintenance. 
Operations and results during fiscal year. Regular 
funds: Engineering continued. Levee stage construction 
on Yolo Bypass and Cache Slough (Unit 109) was 
initiated at fiscal year contract cost of $2,823,538. 
Historical summary. Construction of existing 
project began in FY 1918 and is about 99 percent 
complete. Channel improvement to date has produced a 
channel with a capacity of 579,000 cubic feet per 
second in Sacramento River below Cache Slough. In 
addition, discharges up to 21,000 cubic feet per second 
can be diverted from Sacramento River through 
Georgiana Slough. Completed major project items 
include about 977 miles of levees; five weirs with a 
combined discharge capacity of 602,000 cubic feet per 
second; two cutoff channels; two sets of outfall gates; 
channel improvement and clearing in Sacramento 
River, Butte Creek, Putah Creek, and Sutter and 
Tisdale Bypasses; construction of two main bypasses or 
floodways and secondary bypasses at Tisdale and 
Sacramento weirs and at Wadsworth Canal; construction 
of Knights Landing ridge cut and of Cache Creek 
settling basin; installation of gaging stations; and 
enlargement of Sacramento River below Cache Slough. 
Cutoffs at Collins Eddy and between Wild Irishman and 
Kinneys Bends were made in 1918 and 1919, 
respectively. Sacramento weir was completed in 1917, 
Fremont weir in 1924, Tisdale and Moulton weirs in 
1932, and Colusa weir in 1933. Outfall gates at Knights 
Landing were constructed in 1930 and at mouth of 
Butte Slough in 1936. Pumping plants on Sutter Bypass 
were completed in 1944. Work items with reference to 
clearing, snagging, rectification of channels, and bank 
protection on Sacramento River and tributaries in 
Tehama County and from Red Bluff southerly, provided 
for by 1941 Flood Control Act were accomplished in 
fiscal years 1947, 1948, 1949, and 1951. Work 
remaining comprises completion of levee stage construction, 
Yolo Bypass and Cache Slough (Unit 109) 
scheduled for completion in November 1989; Colusa 
Basin Drain (Unit 132); Knights Landing Ridge Cut 
(Unit 127); and Marysville/Yuba City Area levees. (See 
Table 53-C for total cost of existing project to 
September 30, 1989.) 
53-4

CALIFORNIA DEBRIS COMMISSION 
TABLE 53-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 86 FY 87 FY 88 FY 89 Sep 30, 1989 
1. Regulation of 
Hydraulic Mining 
and Preparation 
of Plans 
2. Sacramento River 
and Tributaries, 
CA (Debris 
Control) 
(Contributed 
Funds, Other) 
3. Treatment of 
Yuba River 
Debris Situation 
Restraining 
Barriers, CA 
(Federal Funds) 
(Required 
Contributed 
Funds) 
(Contributed 
Funds, Other) 
4. Sacramento 
River, CA 
including 
Sacramento River 
Flood Control 
Project and 
Sacramento Area 
Levee Reconstruction 
(Federal Funds) 
(Contributed 
Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
$821,325 
821,325 
5,093,999 1 2 
5,093,999 1 2 
695,000 
690,522 
633,000 634,800 706,300 9,136,143 3 
593,316 670,765 691,157 9,065,226 4 
- - - 12,420 s 
- - - 12,420 s 
361,482 
361,482 
24,000 
44,177 
37,000 
15,778 
85,000 20,000 1,812,6566 
65,648 36,360 1,780,833 6 
1,053,904 
1,053,904 
361,777 
361,777 
26,500 
41,476 
36,865 
14,901 
104,250 
54,096 
- 1,801,838 
43,163 1,769,059 
1,053,904 
1,053,904 
34,000 7 
34,000 7 
201,500 
165,245 
248,000 2,435,000 3,485,000 74,295,835 8 9 
159,929 158,963 3,536,455 71,921,019 8 
1,979,104 
1,979,104 
10,724,085 10 
10,724,085 10 
9,686 11 
9,686 11 
1. Exclusive of $644,503 appropriation and cost 
on inactive portion of project. 
2. Includes $477,127 for recreational facilities at 
North Fork ($32,473) and Harry L. Englebright 
($414,654), Code 710 appropriations and costs. 
3. Includes $7,864,061 from regular funds and 
$1,272,082 from Hydraulic Mining in California funds. 
4. Includes $7,793,144 from regular costs and 
$1,272,082 from Hydraulic Mining in California costs. 
53-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 53-A (Cont'd) COST AND FINANCIAL STATEMENT 
5. Funds from State of California Department of 
Navigation and Ocean Development for acquisition of a 
boarding float at Englebright Dam. 
6. Includes deferred maintenance funds in 
amount of $207,500. 
7. Miscellaneous engineering and construction 
accomplished at expense of local interests in connection 
with rehabilitation of Daguerre Point Dam necessitated 
by December 1964 floodflows. 
8. Includes appropriation and cost of $680,000 for 
new work for previous project and $1,486,469 public 
works funds for new work for existing project. 
9. Includes $1,200,000 Federal Funds for 
Sacramento Area Levee Reconstruction project 
(transferred from Sacramento River Flood Control 
project) in FY 1989. 
10. Includes $680,000 required contribution funds 
for previous project; $4,939,752 required contributed 
funds for existing project; and $310,801 voluntary 
contribution for bank protection for existing project. 
11. Includes $9,686 required contributed funds for 
existing project. 
53-6

TABLE 53-B 
CALIFORNIA DEBRIS COMMISSION 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
Ex. Doc. 267, 51st 
Cong., 2d sess., Ex. 
Doc. 98, 47th Cong., 
1st sess. 1 
(Amendment of sec. 13, 
Act of Mar. 1, 1893.)1 
Mar. 1, 1893 
Feb. 27, 1907 
53-7 
REGULATION OF HYDRAULIC MINING 
AND PREPARATION OF PLANS 
Created California Debris Commission and 
authorized: (a) Hydraulic mining under its 
regulation in drainage areas of Sacramento 
and San Joaquin Rivers, if possible without 
injury to navigability of these river systems or 
to lands adjacent thereto; and (b) preparation 
of plans by Commission for improvement 
of navigability of these river systems, and 
flood and debris-control therein. 
Authorized California Debris Commission to 
permit hydraulic mining without construction 
of impounding works, provided there is no 
injury to navigability of above river systems 
or lands adjacent thereto. 
Amended act of Mar. 1, 1893, which provides 
for construction of debris dams or other restraining 
works by California Debris Commission 
and collection of a 3-percent tax on 
gross proceeds of each mine using such 
facilities, so as to eliminate this tax and 
substitute an annual tax per cubic yard 
mined, obtained by dividing total capital 
cost of each dam, reservoir, and rightsof-
way, by total capacity of reservoir for 
restraint of debris; and authorized revocation 
of Commission orders permitting 
such mining, for failure to pay this annual 
tax within 30 days after its due date; and 
also authorized receipt of money advances, 
from mineowners to aid such construction, 
to be refunded later from annual payments 
of yardage taxes on material mined. 
Added at end of sec. 23 of above act, a provision 
that the Secretary of the Army is 
authorized to enter into contracts to supply 
storage for water and use of outlet facilities 
from debris-storage reservoirs for domestic 
and irrigation purposes and power development, 
upon such conditions of delivery, use, 
and payment as he may approve, these payments 
are to be deposited to credit of such 
reservoir project, reducing its capital cost to 
be repaid by tax on mining operations. 
Abolished the California Debris Commission 
and transferred all authorities, powers, 
functions, and duties to the Secretary of 
the Army. Authorized all acquired land 
and other interests presently under jurisdiction 
of the Commission to be retained 
and administered under direction of the 
Secretary. 
Sec. 1001, 1986 WRDA 
June 19, 1934 
June 25, 1938 
Nov. 17, 1986

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1989 
TABLE 53-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
4. SACRAMENTO RIVER, CA 
Dec. 22, 1944 Additional levee construction and reconstruction, H. Doc. 649, 78th Cong., 
and May 17, 1950 including levee protection of Upper Butte Basin, 2d sess., and 367, 81st 
and multipurpose reservoirs. 2 Cong., 1st sess. 
July 3, 1958 Bank protection and incidental channel improve- H. Doc. 272, 84th Cong., 
ments, Sacramento River from Chico Landing 2d sess. 
to Red Bluff, and local interests flood plain 
zoning above Chico Landing. 2 
July 14, 1960 Bank protection works at critical locations, S. Doc. 103, 86th Cong., 
Sacramento River. 2 2d sess. 
1. For latest published map, see Annual Report 
for 1913, p. 3170, and Rivers and Harbors Committee 
Document 50, 74th Cong., 1st sess. 
TABLE 53-C 
2. This supplemental work is reported in detail 
under Sacramento District, Improvement No. 22. 
Funds New Work Maintenance Total 
Regular $69,754,550 $1,979,104 $71,733,654 
Public Works 1,486,469 -- 1,486,469 
Total U.S. $71,241,019 $1,979,104 $73,220,123 
Contributed Project Work 4,939,752 9,686 4,949,438 
Contributed, Other 5,104,333 -- 5,104,333 
Total All Funds $81,285,104 $1,988,790 $83,273,894 
1. Includes $429,671 representing book value of 
plant purchased with previous project funds and 
transferred to existing project without reimbursement. 
53-8 
SACRAMENTO RIVER CA: TOTAL COST OF 
EXISTING PROJECT TO SEPTEMBER 30, 1989 
(See Section 4 of Text)

APPENDIX A 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
ALASKA 
Chena River Lakes 
ARIZONA 
Adobe 
Alamo 
Cave Buttes 
Dreamy Draw 
New River 
Painted Rock 
Tat Momolikot 
Whitlow Ranch 
ARKANSAS 
Blakely Mountain 
Dam 
Blue Mountain 
DeGray 
DeQueen 
Dierks 
Gillham 
Millwood 
Narrows Dam 
Nimrod 
CALIFORNIA 
Black Butte 
Brea 
Buchanan Dam- 
H.V. Eastman Lake 
Carbon Canyon 
Coyote Valley 
Dry Creek 
(Warm Springs) 
Lake and Channel 
Fannington 
Fullerton 
Hansen 
Narry L. Englebright 
Hidden Dam- 
Hensley Lake 
Isabella 
Lopez 
Martis Creek 
Merced County 
Stream Group: 
Bear 
Burns 
Mariposa 
Owens 
Mojave River 
New Hogan 
North Fork 
Pine Flat 
Prado 
San Antonio 
Santa Fe 
Sepulveda 
Yukon 
-Kuskokwim 
Gila 
Colorado 
Gila 
Gila 
Gila 
Gila 
Gila 
Gila 
Ouachita 
Arkansas 
Ouachita 
Red 
Red 
Red 
Red 
Ouachita 
Arkansas 
Sacramento 
Santa Ana 
San Joaquin 
Chena River 
Skunk Creek 
Bill Williams River 
Cave Creek 
Dreamy Draw 
New River 
Gila River 
Santa Rosa Wash 
Queen Creek 
Ouachita 
Petit Jean River 
Caddo 
Rolling Fork River 
Saline River 
Cossatot River 
Little River 
Little Missouri 
Fourche La Fave River 
Stony Creek 
Brea Creek 
Chowchilla River 
Santa Ana Carbon Canyon River 
Russian East Fork 
Russian River 
Russian 
San Joaquin 
Santa Ana 
Los Angeles 
Sacramento 
San Joaquin 
San Joaquin 
Los Angeles 
Sacramento 
San Joaquin 
San Joaquin 
San Joaquin 
San Joaquin 
Majave 
San Joaquin 
Sacramento 
San Joaquin 
Santa Ana 
Santa Ans 
SSan Gabriel 
Los Angeles 
Dry Creek 
Littlejohn Creek 
East Fullerton Creek 
Big Tujunga Wash 
Yuba River 
Fresno River 
Kern River 
Pacoima Wash 
Martis Creek 
Bear Creek 
Bums Creek 
Mariposa Creek 
Owens Creek 
Mojave 
Calaveras 
American River 
Kings River 
Santa Ana River 
San Antonio Creek 
San Gabriel River 
Los Angeles River 
Fairbanks 
Phoenix 
Wenden 
Phoenix 
Phoenix 
Phoenix 
GilaB end 
Casa Grande 
Superior 
Hot Springs 
Paris 
Arkadelphia 
DeQueen 
Dierks 
Gillham 
Ashdown 
Murfreesboro 
Plainview 
Orland 
Fullerton 
Chowchilla 
Brea 
Ukiah 
Healdsburg 
Farmington 
Fullerton 
Los Angeles 
Marysville 
Madera 
Bakersfield 
San
Fernanado 
Reno 
Merced 
Merced 
Merced 
Merced 
Victorville 
Valley 
Springs 
Auburn 
Piedra 
Corona 
Upland 
Duarte 
Van Nuys 
1981 2,000 NPP FR 
1982 18,350 
1968 1,046,310 
1979 46,600 
1973 320 
1985 43,520 
1959 2,476,340 
1974 198,550 
'960 34,500 
1955 2,768,500 
1947 257,900 
1971 881,900 
1977 136,100 
1975 96,800 
1975 221,800 
1966 1,854,930 
1949 407,900 
1942 336,010 
1963 160,000 
1942 4,010 
1975 150,000 
1961 6,610 
1959 122,500 
1983 381,000 
1952 52,000 
1941 760 
1940 25,450 
1941 69,000 
1975 90,000 
1953 570,000 
1954 440 
1971 20,400 
1954 7,700 
1950 7,000 
1948 15,000 
1949 3,600 
1971 89,670 
1963 325,000 
1939 14,700 
1954 1,000,000 
1941 196,240 
1956 7,700 
1948 22,110 
1941 17,430 
NPP FR 
560 FRWX 
NPP FRX 
NPP FRX 
NPP F 
NPP FRWX 
NPP GWX 
NPP FX 
20,900 FP 
2,910 FRWX 
6,400 FRZRS 
1,680 FSQRW 
1,360 FSRAW 
1,370 FSQW 
29,200 FSW 
2,500 FP 
3,550 FSWX 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
50 40,200 
109 2,275 
283 975 
109 2,275 
50 448 
104 2,320 
1281 4,780 
75.5 12,500 
149 637 
235 1,100 
Earth 115 2,800 
Earth 243 3,400 
Earth 160 2,360 
Earth & Rock 153 2,500 
Earth & Rock 160 1,750 
Earth 88 17,554 
Concrete 175 941 
Concrete 97 1,012 
770 FIRX Earth 156 2,970 
NPP FRX Earth 87 1,765 
470 FIRW Earth & Rock 205.5 1,800 
NPP FERX 
1,700 FRX 
500 FRSW 
NPP F 
NPP FRX 
120 FRWX 
400 DR 
5,000 FIRW 
1,850 FIRW 
NPP FX 
71 FSR 
NPP F 
NP F 
NPP F 
NPP F 
NPP FRWX 
715 FIRX 
280 DR 
NPP FIRX 
NPP FRX 
NPP FX 
NPP FRX 
NPP FRX 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
Concrete 
Concrete 
Earth 
Earth 
Earth 
Earth 
99 2,610 
160 3,500 
319 3,000 
60 7,800 
45 575 
97 10,475 
280 1,142 
163 5,730 
185 4,952 
50 1,300 
113 2,670 
92 1,830 
55 4,075 
88 1,330 
75 790 
200 2,200 
429 1,820 
155 620 
429 1,820 
106 2,280 
160 3,850 
92 23,800 
57 15,444

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
CALIFORNIA (Continued) 
San Joaquin Tule River 
San Joaquin Kaweah River 
San Gabriel San Gabriel River 
;and Rio Hondo 
Bear Creek 
South Platte River 
Cherry Creek 
Arkansas River 
Purgatoire River 
Branch Brook 
West Branch, 
Farmington River 
Hancock Brook 
Hop Brook 
Natchaug River 
Northfield Brook 
Naugatuck River 
Quinebaug River 
Columbia Boise River 
Kaskaskia River 
Farm Creek 
Fondulac Creek 
Kaskaskia River 
Big Muddy River 
East Fork of 
Whitewater River 
Mill Creek 
Raccoon Creek 
Wabash River 
Mississinewa 
Salt Creek 
Patoka River 
Salamonie 
Iowa River 
Des Moines River 
Chariton River 
Des Moines River 
Porterville 
Visalia 
El Monte 
Denver 
Denver 
Denver 
Lamar 
Trinidad 
Thomaston 
Riverton 
Plymouth 
Middlebury 
Willimantic 
Thomaston 
Thomaston 
Thompson 
Boise 
Carlyle 
East Peoria 
East Peoria 
Shelbyville 
Benton 
Brookville 
Tere Haute 
Rockville 
Huntington 
Peru 
Harrodsburg 
Ellsworth 
Wabash 
Iowa City 
Des Moines 
Centerville 
Des Moines 
Success 
Terminus 
Whittier Narrows 
COLORADO 
Bear Creek 
Chatfield 
Cherry Creek 
John Martin 
Trinidad 
CONNECTICUT 
Black Rock 
Colebrook River 
Hancock Brook 
Hop Brook 
Mansfield Hollow 
Northfield Brook 
Thomaston 
West Thompson 
IDAHO 
400 FIRX Earth 
345 FIRX Earth 
NPP FRWX Earth 
109 
1,412 
852 
1,844 
280 
20 
760 
40 
21 
450
8 
NPP 
200 
FRX 
FRX 
FRX 
FIR 
Earth 
Earth 
Earth 
Concrete 
& Earth 
FIRX Earth 
FR 
FRSX 
FRW 
FR 
FRW 
FRW 
F
FRW 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
1960 85,000 
'1961 150,000 
1967 35,150 
1978 30,810 
1974 231,429 
1950 93,920 
1943 615,500 
1977 123,500 
1970 8,700 
1969 97,700 
1960 4,030 
1968 6,970 
1952 52,000 
1965 2,430 
1960 42,000 
1965 26,800 
1956 306,000 
1967 983,000 
1951 15,500 
1951 3,780 
1970 684,000 
1970 294,000 
1974 359,600 
1952 228,120 
1960 132,800 
1969 153,100 
1967 368,400 
1964 441,000 
1978 301,600 
1966 263,600 
1958 492,000 
1969 1,830,000 
1969 552,000 
1975 602,000 
26,000 
NPP 
NPP 
11,100 
18,900 
2,250 
1,400 
1,100 
500 
1,100 
3,280 
2,010 
976 
1,820 
8,950 
11,000 
74,000 
FSNRWA Earth 
F Earth 
F Earth 
FSNRW Earth 
FQRSW Earth 
FRSW Earth& Rock 
FRX Earth 
FRX Earth 
FRW Earth 
FRW Earth 
FARS Earth 
FRSQW Earth & Rock 
FRW Earth 
FARW Earth 
FARWQ Earth 
FNRWXQ Earth 
FARWQ Earth 
A-2 
MissouriB 
Missouri 
Missouri 
Arkansas 
Aikansas 
Housatonic 
Connecticut 
Housatonic 
Housatonic 
Thames 
Thames 
Housatonic 
Thames 
Lucky Peak 2,850 FIR Earth 
ILLINOIS 
Carlyle 
Fanndale 
Fondulac 
Shelbyville 
Rend Lake 
INDIANA 
Brookville 
Cagles Mill 
Cecil M. Harden 
Huntington 
Mississinewa 
Monroe 
Patoka 
Salamonie 
Upper 
Mississippi 
Upper 
Mississippi 
Upper 
Mississippi 
Upper 
Mississippi 
Upper 
Mississippi 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
142 3,490 
250 2,375 
56 19,960 
180 5,300 
148 12,400 
141 14,300 
106 13,274 
200 6,610 
154 933 
223 1,300 
57 630 
97 520 
68 12,420 
118 810 
142 2,000 
70 2,550 
250 1,700 
67 6,570 
80 1,275 
67 1,000 
108 3,000 
54 10,600 
182 3,000 
150 950 
117 1,790 
91 5,332 
137 8,100 
93 1,400 
84 1,550 
133 6,100 
100 1,400 
110 5,676 
16 10,600 
125 6,750 
IOWA 
Coralville 
Red Rock 
Rathbum 
Saylorville 
Upper 
Mississippi 
Upper 
Mississippi 
Missouri 
Upper 
Mississippi

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
KANSAS 
Clinton 
Council Grove 
El Dorado 
Elk City 
Fall River 
Hillsdale 
John Redmond 
Kanopolis 
Marion 
Melvemrn 
Milford 
Pearson Skubitz 
Big Hill 
Perry 
Pomona 
Toronto 
Tuttle Creek 
Wilson 
KENTUCKY 
Barren River 
Buckhorn 
Carr Fork 
Cave Run 
Dewey 
Fishtrap 
Grayson 
Green River 
Martins Fork 
Paintsville 
Nolin 
Rough River 
Taylorsville 
Yatesville 
LOUISIANA 
Bayou Badcau 
Caddo Lake 
Wallace Lake 
MARYLAND 
Jennings Randolph 
Lake 
MASSACHUSETTS 
Barre Falls 
Birch Hill 
Buffumville 
Charles River Natural 
Valley Storage 
Conant Brook 
East Brimfield 
Hodges Village 
Knightville 
Littleville 
Missouri 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Missouri 
Arkansas 
Missouri 
Arkansas 
Missouri 
Mouri 
Arkansas 
Missouri 
Missouri 
Arkansas 
Missouri 
Missouri 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Cumberland 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Red 
Red 
Red 
Potomac 
Connecticut 
Connecticut 
Thames 
Charles 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Wakarusa River 
Grand (Neosho) 
Walnut River 
Elk River 
Fall River 
Big Bull Creek 
Grand (Neosho) 
Smoky Hill River 
Cottonwood River 
Marias des Cygnes 
Republican River 
Big Hill Creek 
Deleware River 
110 Mile Creek 
Verdigris River 
Big Blue River 
Saline River 
Barren River 
Middle Fork of 
Kentucky River 
Carr Fork 
Licking River 
Johns Creek 
Levisa Fork, 
Big Sandy River 
Little Sandy 
Green River 
Martins Fork 
Paint Creek 
Nolin River 
Rough River 
Salt River 
Blain Creek 
Bayou Bodcau 
Cypress Bayou 
Cypress Bayou 
North Branch 
Potomac River 
Ware River 
Millers River 
Little River 
Charles River 
Conant Brook 
Quinebaug River 
French River 
Westfield River 
Middle Branch, 
Westfield River 
Lawrence 
Council Grove 
El Dorado 
Independence 
Fall River 
Hillsdale 
Burlington 
Marquette 
Marion 
Melvem 
Junction 
Cherryvale 
Perry 
Pomona 
Toronto 
Manhattan 
Wilson 
Glasgow 
Buckhorn 
Hazard 
Farmers 
Paintsville 
Pikeville 
Grayson 
Campbells 
-ville 
Harlan 
Paintsville 
Kyrock 
Leitchfield 
Taylorsville 
Yatesville 
Shreveport 
Shreveport 
Shreveport 
Bamum 
Barre 
So. Roylaston 
Charlton 
Millis 
Monson 
Fiskdale 
Oxford 
Huntington 
Chester 
1977 397,200 
1964 112,882 
1981 236,200 
1966 287,300 
1949 256,400 
1981 160,000 
1964 628,540 
1948 450,000 
1968 141,770 
1972 363,000 
1965 1,160,000 
1981 39,740 
1969 770,000 
1963 230,000 
1960 200,800 
1962 2,346,000 
1964 776,000 
1964 815,200 
1960 168,000 
1976 47,700 
1974 614,100 
1949 93,000 
1968 164,360 
1967 118,990 
1969 723,200 
1978 21,00 
1983 73,500 
1963 609,400 
1958 334,400 
1983 291,670 
1988 86,951 
1949 357,300 
1971 175,000 
1946 96,100 
1981 130,900 
1958 24,000 
1941 49,900 
1958 12,700 
1983 35,000 
1966 3,740 
1960 30,000 
1959 12,800 
1941 49,000 
1965 32,400 
7,000 FSWAXR Earth 
3,310 FSQR Earth 
8,000 FSQR Earth 
4,122 FSQ Earth 
2,350 FSX Earth 
4,580 FSQR Earth 
9,710 FSQR Earth 
3,815 FRWX Earth 
6,210 FRQS Earth 
6,930 FRQWX Earth 
15,600 FRSXWQ Earth&Rock 
1,190 FSR Earth 
12,500 FRSXW Earth&Rock 
4,000 FRSWXQ Earth&Rock 
2,660 FX Earth 
15,800 FRWXQAN Earth&Rock 
9,000 FIRWXNA Earth&Rock 
4,340 FARS Earth 
550 FQRW Earth 
530 FQRW Earth & Rock 
6,790 FQRW Earth & Rock 
1,100 FARW Earth 
569 FARW Rock 
1,050 FQRW Earth & Rock 
5,070 FRSQW Earth & Rock 
578 FQ Concrete 
261 FQRW Earth & Rock 
2,890 FAR Earth & Rock 
2,180 FRX Earth & Rock 
1,625 FQRW Earth & Rock 
3,921 FQRW Earth & Rock 
NPP FRW 
32,700 NFRS 
2,300 FQRS 
Earth 
Concrete 
& Earth 
Earth 
114 9,250 
96 6,500 
99 20,930 
107 4,840 
94 6,015 
75 11,600 
86.5 21,790 
131 15,360 
67 8,375 
98 9.700 
126 6,300 
83 3,902 
96 7,750 
85 7,750 
90 4,712 
175 7,500 
160 5,600 
146 3,970 
162 1,020 
130 720 
148 2,740 
118 913 
195 1,100 
120 1,460 
142 2,350 
97 574 
160 1,600 
174 990 
124 1,530 
164 1,280 
105 760 
70 12,850 
3,700 
30 4,994 
952 FQRS Earth & Rock 296 2,130 
NPP FRW 
NPP FRW 
200 FRW 
NPP F 
NPP F 
360 FRW 
NPP FRW 
NPP FRW 
275 FRWS 
Earth & Rock 62 885 
Earth & Rock 56 1,400 
Earth & Rock 66 3,255 
Nonstructural -- -- 
Earth & Rock 85 1,050 
Earth & Rock 55 520 
Earth & Rock 55 2,140 
Earth & Rock 160 1,200 
Earth & Rock 1,164 1,360 
A-3

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
MASSACHUSETTS (Continued) 
Tully 
West Hill 
Westville 
MINNESOTA 
Big Stone Lake- 
Whetstone River 
Lac Qui Parle 
Chippewa River 
LacQui Parle 
Marsh Lake 
Orwell 
Red Lake 
MISSISSIPPI 
Arkabutla Lake 
Enid Lake 
Grenada Lake 
Okatibbee 
Sardis Lake 
MISSOURI 
Clearwater 
Long Branch 
Longview 
Pomme de Terre 
Smithville 
Wappapello 
NEBRASKA 
Harlan County 
Paipillion Creek 
and Tributaries 
Glenn Cunningham 
(Site 11) 
Standing Bear Lake 
(Site 16) 
Salt Creek & Tributaries 
Olive Creek (Site 2) 
Blue Stem (Site 4) 
Wagon Train (Site 8) 
Stagecoach Site (9) 
Yankee Hill (Site 10) 
Conestoga (Site 12) 
Town Lake (Site 13) 
Pawnee (Site 14) 
Holmees Park Lake 
(Site 17) 
Branched Oak (Site 18) 
Connecticut Tully River 
Blackstone West River 
Thames Quinebaug River 
Upper 
Mississippi 
Upper 
Mississippi 
Upper 
Mississippi 
Upper 
Mississippi 
Red River 
of the North 
Red River 
of the North 
Lower 
Mississippi 
Lower 
Mississippi 
Lower 
Mississippi 
Pascagoula 
Lower 
Mississippi 
White 
Grande 
Chariton 
Missouri 
Missouri 
Missouri 
Lower 
Mississippi 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
M:i;ssouri 
Misouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Minnesota River 
Chippewa River 
Minnesota River 
Minnesota River 
Otter Tail River 
Red Lake River 
Coldwater River 
Yocona River 
Yalobusha River 
Okatibbee Creek 
Little Tallahatchie 
River 
Black River 
Little Charlton 
Little Blue River 
Momme de Terre River 
Little Platte River 
St. Francis River 
Republican River 
Knight Creek 
Trib of Big Papillion 
Creek 
S. Trib. Olive Br. Creek 
N. Trib Olive Br. Creek 
N. Trib. Hickman Creek 
S. Trib. Hickman Creek 
Cardwell Creek 
Holmes Creek 
Middle Creek 
N. Middle Creek 
Antelope Creek 
Oak Creek 
Fryville 
Uxbridge 
Sturbridge 
Ortonville 
Montevideo 
Montevideo 
Montevideo 
Fergus Falls 
Red River 
Arkabutla 
Enid 
Grenada 
Meridian 
Sardis 
Piedmont 
Macon 
Kansas City 
Hermitage 
Smithville 
Wappapello 
1949 22,000 
1960 12,350 
1961 11,100 
1973 45,000 
1950 (2) 
1950 122,800 
1953 14,100 
1953 14,100 
1951 3,270,000 
1943 525,300 
1951 660,000 
1954 1,337,400 
1969 142,400 
1940 1,570,000 
1948 413,700 
1980 65,000 
1986 46,900 
1961 650,000 
1982 2456,500 
1941 613,200 
Republican City 1952 850,000 
Omaha 
Omaha 
Kramer 
Sprague 
Holland 
Hickman 
Denton 
Denton 
Pleasantdale 
Emerald 
Lincoln 
Raymond 
1975 17910 
1973 5,220 
1964 5,470 
1963 10,260 
1963 9,280 
1964 6,640 
1966 7,560 
1964 10,640 
1966 8,080 
1965 29,520 
1963 6,510 
1968 97,560 
300 FRW Earth & Rock 62 
NPP FRW Earth & Rock 51 
23 FRW Earth & Rock 78 
12,700 
NPP 
6,500 
210 
210 
279,000 
5,100 
6,100 
9,800 
1,280 
10,700 
1,630 
2,430 
930 
7,820 
7,190 
4,100 
FRW 
FRWX 
FRWX 
FARS 
FARS 
FARSX 
F
F
F
FQSR 
F
FRWX 
FRSQW 
FRWQ 
FRWX 
FSQRW 
FR 
Earth 25 
Earth & Rock 21 
Earth & Rock 21 
Earth & Rock 19.5 
Eaarth & Rock 47 
Earth & Rock 15.5 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth 
Earth & Rock 
Earth & Rock 
Earth 
Earth&Rock 
Earth&Rock 
Earth 
Earth & Rock 
81 
99 
102 
67 
117 
154 
71 
120 
155 
95 
109 
1,570 
2,400 
560 
13,700 
17,97 
4,100 
11,800 
1,355 
36,500 
11,500 
8,400 
13,900 
6,543 
15,300 
4,225 
3,800 
1,900 
4,630 
4,200 
2,700 
13,600 FIRWX Earth & Rock 107 11,827 
391 FQEX Earth 67 1,940 
137 FRX Earth 70 1.460 
174 
316 
303 
196 
208 
230 
255 
728 
100 
1,780 
FR 
FR 
FR 
FB 
FR 
FR 
FR 
FR 
FR 
FR 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
45 
57 
52 
48 
52 
63 
58 
65 
55 
70 
3,020 
2,760 
1,650 
2,250 
3,100 
3,000 
2,075 
5,000 
7,700 
5,200 
A-4

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
NEW HAMPSHIRE 
Blackwater 
Edward MacDowell 
Franklin Falls 
Hopkinton-Everett 
Otter Brook 
Surry Mountain 
NEVADA 
Mathews Canyon 
Pine Canyon 
NEW MEXICO 
AAbiquiu 
Conchiti 
Conchas 
Galisteo 
Jemnez Canyon 
Two Rivers: 
Diamond "A" Dam 
Rocky Dam 
Santa Rosa Dam & 
Reservoir 
NEW YORK 
Almond 
Arkport 
East Sidney 
Mount Morris 
Whitney Point 
NORTH CAROLINA 
B. Everett Jordan 
Falls 
W. Kerr Scott 
NORTH DAKOTA 
Baldhill 
Borman-Haley 
Homme 
Pipestem 
OHIO 
Alum Creek 
Berlin 
Caesar Creek 
Clarence J. Brown 
Deer Creek 
Delaware 
Dilon 
Merrimack 
Merrimack 
Merrimack 
Merrimack 
Merrimack 
Connecticut 
Connecticut 
Blackwater River 
Nubanusit Brook 
Pemigewasset River 
Contoocook River 
Piscataquog River 
Otter Brook 
Ashuelot River 
Colorado Mathews Canyon 
Colorado Pine Canyon 
Rio Grande 
Rio Grande 
Arkansas 
Rio Grrande 
Rio Grande 
Rio Grande 
Rio Grande 
Pecos 
Susquehanna 
Susquehanna 
Susquehanna 
Genesee 
Susquehanna 
Cape Fear 
Neuse 
Yadkin- 
Pee Dee 
Red River 
of the North 
Missouri 
Red River 
of the North 
James River 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Rio Charma 
Rio Grande 
Canadian River 
Galistco Creek 
Jemez River 
Rio Hondo 
Rocky Arroyoo 
Pecos 
Canacadea Creek 
Canisteo Creek 
Ouleout Creek 
Genesee River 
Otselic River 
New Hope 
Neuse 
Yadkin 
Sheyenne River 
Webster 
West 
Peterborough 
Feanklin 
West 
Hopkinton 
East Weare 
Keene 
Keene 
Caliente 
Caliente 
Abiquio 
Pena Blanca 
Tucumcari 
Albuquereque 
Bemailillo 
Roswell 
Santa Rosa 
Homell 
Arkport 
Franklin 
Mount Morris 
Whitney Point 
Durham 
Raleigh 
Wilkesboro 
Valley City 
North Fork, Grand River Haley 
South Branch of Park River 
Park River 
Pipestem Creek Jamestown 
Alum Creek 
Mahoning Creek 
Caesar Creek 
Buck Creek 
Deer Creek 
Licking River 
Licking River 
Africa 
Deerficld 
Wilmington 
Springfield 
New Holland 
Zanesville 
Zanesville 
1941 46,000 
1950 12,800 
1943 154,000 
1962 71,500 
1962 87,500 
1958 18,300 
1941 32,500 
NPP 
NPP 
NPP 
200 
120 
85 
265 
FRW 
FRW 
FRW 
FRW 
FRW 
FRW 
FRW 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
75 
67 
140 
76 
115 
133 
86 
1957 6,270 NPP FX Earth 
1957 7,750 NPP FX Earth 
1963 1,212,000 
1975 596,300 
1939 529,000 
1970 89,000 
1953 102,700 
1963 168,000 
1979 447,000 
1949 14,600 
1940 7,900 
1950 33,550 
1952 337,000 
1942 86,440 
1982 753,500 
1983 3374450 
1963 153,000 
1950 70,000 
1967 92,980 
1951 3,660 
1974 146,880 
1975 134,800 
1943 91,200 
1978 242,200 
1974 63,700 
1968 102,500 
1961 273,000 
1961 273,000 
NPP 
1,200 
3,000 
NPP 
NPP 
NPP 
FXS 
FRWX 
FI 
FX 
FX 
FX 
Earth 
Earth 
Concrete 
& Earth 
Earth 
Earth 
Earth 
NPP FIX Earth 
124 
NPP 
210 
170 
1,200 
14,300 
11,300 
1,470 
325 
1,750 
51 
885 
348 
240 
13,300 
1,010, 
727 
1,325 
1,325 
FRW 
F
FRW 
FR 
FRW 
Earth 
Earth 
Concrete & 
Earth 
Concrete 
Earth 
FQRSWX Earth 
FQRSWX Earth 
FARSX Earth 
FARS Earth 
FSRWK Earth 
FARS Earth 
FRWX Earth 
FRSW Concrete & 
Earth 
FARSWQ Concrete & 
Earth 
FRSQW Earth & Rock 
FQRW Earth & Rock 
FRW Earth 
FRWX Earth 
FRWX Earth 
1,150 
1,030 
1,740 
790 
2,000 
1,288 
1,670 
71 800 
92 884 
325 
241 
200 
156 
135 
96 
212 
212 
90 
113 
130 
210 
95 
112 
92 
148 
61 
79 
67 
108 
93 
96 
165 
72 
93 
118 
118 
1,540 
28,300 
19,400 
2,820 
760 
4,885 
2,940 
1,950 
1,260 
1,200 
2,010 
1,028 
4,900 
1,330 
1,915 
1,740 
1,650 
5,730 
865 
4,000 
10,000 
5,750 
2,750 
6,620 
3,880 
1,400 
1,400 
A-5

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
OHIO (Continued) 
Michael J. Kirwan 
Mosquito Creek 
Muskingum River 
Reservoirs: 
Atwood 
Beach City 
Bolivar 
Charles Mill 
Clendening 
Dover 
Leesville 
Mohawk 
Mohicanville 
Piedmont 
Pleasant Hill 
Senecaville 
Tappan 
Wills Creek 
North Branch, 
Kakosing River Lake 
Paint Creek 
Tom Jenkins 
West Fork Mill Creek 
William H. Harsha 
OKLAHOMA 
Arcadia 
Birch 
Canton 
Copan 
Fort Supply 
Great Salt Plains 
Heyburn 
Hugo 
Hulah 
Kaw 
Ooologah 
Optima 
Pine Creek 
Sardis 
Skiatook 
Waurika 
Wister 
OREGON 
Applegate 
Blue River 
Cottage Grove 
Dorena 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Red 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Red 
Red 
Arkansas 
Red 
Arkansas 
West Branch, 
Mahoning River 
Mosquito Creek 
Indian Fork 
Sugar Creek 
Sandy Creek 
Black Fork 
Brushy Fork 
Tuscarawas River 
McGuire Creek 
Walhondoing River 
Lake Fork 
Stillwater Creek 
Clear Fork 
Seneca Fork 
Little Stillwater Creek 
Wills Creek 
North Branch of 
Kakosing River 
Paint Creek 
East Branch, 
Sunday Creek 
Mill Creek 
Little Miami River 
Deep Fork River 
Birch Creek 
North Canadian River 
Little Caney River 
Wolf Creek 
Salt Fork, 
Arkansas River 
Polecat Creek 
Kiamichi River 
Caney River 
Arkansas River 
Verdigris River 
North Canadian River 
Little River 
Jackfork Creek 
Hominy Creek 
Beaver Creek 
Poteau River 
Rogue River Applegate River 
Columbia 
Columbia 
Columbia 
Blue River 
Coast Fork, 
Willamette River 
Row River 
Newton Falls 1966 78,700 
Cortland 1944 104,100 
New
Cumberland 
Beach City 
Bolivar 
Mufflin 
Tippecanoe 
Dover 
Leesville 
Nellie 
Mohicanville 
Piedmont 
Perrysville 
Senecaville 
Tappan 
Conesville 
Fredericktown 
New Petersburg 
Gloucester 
Mount Healthy 
Williamsburg 
Edmond 
Bamsdall 
Canton 
Copan 
Fort Supply 
Cherokee 
Sapulpa 
Hugo 
Bartlesville 
Ponca City 
Oologah 
Hardesty 
Wright City 
Clayton 
Skiatook 
Waurika 
Wister 
Medford 
Blue River 
Cottage Grove 
Cottage Grove 
1937 49,700 
1937 71,700 
1938 149,600 
1936 88,000 
1937 54,000 
1938 203,000 
1937 37,400 
1937 285,000 
1936 102,000 
1937 65,000 
1938 87,700 
1937 88,500 
1936 61,60-0 
1937 196,000 
1973 14,900 
1972 145,000 
1951 26,900 
1952 11,380 
1978 284,500 
1986 92,010 
1977 58,200 
1948 377,100 
1983 227,700 
1942 100,700 
1941 271,400 
1950 55,395 
1974 966,700 
1951 289,000 
1976 1,348,000 
1963 1,519,000 
1978 229,500 
1969 465,780 
1984 468,060 
1985 500,700 
1977 343,500 
1949 427,900 
580 
700 
1,540 
420 
NPP 
1,350 
1,800 
350 
1,000 
NPP 
NPP 
2,270 
850 
3,550 
2,350 
900 
98 
710 
394 
200 
18,760 
1,820 
1,137 
7,910 
4,850 
1,820 
8,690 
880 
13,250 
3,570 
17,040 
29,460 
5,340 
3,750 
13,610 
10,190 
10,100 
5,360 
FAQRSW Earth 
FARSWQ Earth 
FRX 
FRX 
FR 
FRX 
FRX 
FRX 
FRX 
FR 
FR 
FRX 
FRX 
FRSX 
FRX 
FRX 
FRW 
FRSQW 
FRSWX 
FRX 
FRSQW 
FSR 
FSQRW 
FSI 
FSQRW 
FSX 
FRWX 
FRWXS 
FSQRW 
FSAX 
FSQRW 
FSN 
FSRW 
FSQWR 
FSRW 
FSQRW 
FISQWR 
FSAX 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth & Rock 
Concrete 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
1981 82,000 988 AFIQRSW Gravel 
Embankment 
1968 85,000 975 FINR Earth 
1942 30,060 1,155 FINR Concrete & 
& Earth 
1949 70,500 1,885 FINR Concrete 
& Earth 
83 
47 
65 
64 
87 
48 
64 
83 
74 
111 
46 
56 
113 
45 
52 
87 
71 
118 
84 
100 
200 
104 5,250 
97 3,190 
68 15,140 
70 7,730 
85 111,865 
68 6,010 
89 2,920 
101 10,200 
94 5,200 
125 9,466 
137 4,000 
120 15,200 
124 7,712 
81 14,138 
143 3,590 
106 16,600 
99 5,700 
242 1,300 
319 1,329 
114 2,110 
145 3,352 
A-6 
9,900 
5,650 
3,700 
5,600 
6,300 
1,390 
950 
824 
1,694 
2,330 
1,220 
1,750 
775 
2,350 
1,550 
1,950 
1,400 
700 
944 
1,100 
1,450

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
OKLAHOMA (Continued) 
Fall Creek 
Fern Ridge 
Willow Creek 
PENNSYLVANIA 
Alvin R. Bush 
Ayleswerth Creek 
Beltzville 
Blue Marsh 
Conemaugh 
Cowanesque 
Crooked Creek 
Curwensville 
East Branch, 
Clarion River 
Foster Joseph Sayers 
Francis E. Walter 
(Bear Creek) 
Gen. Edgar Jadwin 
Indian Rock 
Kinzua 
Loyalhanna 
Mahoning Creek 
Prompton 
Raystown 
Shenanago 
Stillwater 
Tioga-Hammond 
Lakes 
Hammond Lakes 
Tionesta 
Union City 
Woodcock Creek 
Youghiogheny River 
SOUTH DAKOTA 
Cold Brook 
Cottonwoiod Springs 
Lake Traverse: 
Reservation Control 
Dam 
White Rock 
TEXAS 
Addicks 
Aquilla 
Bardwell 
Barker 
Columbia 
Columbia 
Columbia 
Susquehanna 
Susquehanna 
Delaware 
Delaware 
Ohio 
Susquehanna 
Ohio 
Susquehanna 
Ohio 
Susquehanna 
Delaware 
Delaware 
Susquehanna 
Ohio 
Ohio 
Ohio 
Delaware 
Susquehanna 
Ohio 
Susquehanna 
Susquehanna 
Susquehanna 
Ohio 
Ohio 
Ohio 
Ohio 
Missouri 
Missouri 
Red River 
of the North 
Red River 
of the North 
San Jacinto 
Brazos 
Trinity 
San Jacinto 
Middle Fork, 
Long Tom River 
Willow Creek 
Kettle Creek 
Aylesworth Creek 
Pohopco Creek 
Tulephoken Creek 
Conemaugh River 
Cowanesque River 
Crooked Creek 
West Branch, 
Susquehanna River 
East Branch, 
Clarion River 
Bald Eagle Creek 
Lehigh River 
Dyberry Creek 
Codorus Creek 
Allegheny River 
Loyalhanna Creek 
Mahoning Creek 
Lackawaxem River 
Raystown Branch, 
Juniata River 
Shenanago River 
Lackawanna River 
Tioga River 
Crooked Creek 
Tionesta Creek 
French Creek 
French Creek 
Youghiogheny River 
Cold Brook 
Cottonwood Springs 
Creek 
Bois de Sioux River 
Bois de Sioux River 
South Mayde Creek 
Aquilla Creek 
Waxahachie creek 
Buffalo Bayou 
Eugene 
Eugene 
Heppner 
Renovo 
Archbald 
Lehighton 
Reading 
Saltsburg 
Larenceville 
Ford City 
Curwensville 
Wilcox 
Blanchard 
White Haven 
Honesdale 
York 
Warren 
Saltsburg 
New Bethlehem 
Honesdale 
Huntingdon 
Sharpsville 
Uniondale 
Tioga 
Tioga 
Tionesta 
Union City 
Meadville 
Confluence 
Hot Springs 
Hot Springs 
Wheaton 
Wheaton 
Addicks 
Hillsboro 
Ennis 
Baker 
1965 115,000 
1941 110,000 
1983 13,250 
1962 75,000 
1970 1,700 
1971 68,250 
1978 50,010 
1952 274,000 
1980 89,000 
1940 93,900 
1965 124,200 
1952 84,300 
1969 99,000 
1961 110,700 
1960 24,500 
1942 28,000 
1965 "1,180,000 
1942 95,300 
1941 74,200 
1960 52,000 
1973 762,000 
1966 191,400 
1960 12,000 
1978 62,000 
1978 63,000 
1940 133,400 
1970 47,640 
1973 20,000 
1943 254,000 
19534 7,200 
1970 8,385 
1941 164,500 
1941 85,500 
1948 204,500 
1983 146,000 
1965 140,000 
1945 207,000 
1,865 
10,305 
96 
160 
NPP 
947 
960 
300 
410 
350 
790 
90 
1,730 
80 
NPP 
NPP 
1,900 
210 
170 
290 
8,300 
1,910 
85 
470 
680 
480 
NPP 
118 
450 
FINR 
FINR 
FRN 
Rockfill 
Rockfill 
& Concrete 
Roller 
Compacted 
Concrete 
FRW Earth & Rock 
F Earth & Rock 
FQRSW Earth & rock 
FAQRS Earth & Rock 
FW Concrete 
& Earth 
FR Earth & Rock 
FRW Earth 
FR Earth 
FARQW Earth 
FRW Earth 
FNRW Earth & rock 
F Earth 
FRW Earth 
PFAQRW Concrete 
& Earth 
FRW Concrete 
& Earth 
FRW Concrete 
FNRW Earth 
FRW Earth & Rock 
FAQRW Concrete 
FS Earth 
FR Earth & Rock 
FR Earth & Rock 
FRW Earth 
F Earth 
FQRA Earth 
FARWQ Earth 
36 FRWX Earth 
41 FRWX Earth 
10,925 
6,500 
FRX 
FRX 
Earth 
Earth 
NPP FX Earth 
3,280 FSX Earth 
3,570 FRSX Earth 
NPP FX Earth 
A-7 
193 
49 
160 
165 
90 
170 
98 
137 
151 
143 
131 
184 
100 
234 
112 
83 
1'77 
114 
162 
140 
225 
68 
77 
140 
122 
154 
88 
90 
184 
5,100 
6,624 
1,780 
1,350 
1,270 
4,300 
1,775 
1,265 
3,100 
1,480 
2,850 
1,725 
6,835 
3,000 
1,273 
1,000 
1,877 
960 
926 
1,230 
1,700 
720 
1,700 
2,710 
6,450 
1,050 
1,420 
4,650 
1,610 
127 925 
123 1,190 
14 
16 
9,100 
14,400 
49 61,166 
104.5 11,890 
82 15,400 
37 72,844

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
TEXAS (Continued) 
Belton 
Benbrook 
Canyon 
Ferrells Bridge Dam- 
Lake O' the Plains 
Granger Dam and Lake 
Grapevine 
Hords Creek 
Joe Pool 
Lake Kemp 
Lavon 
Lewisville 
Navarro Mills 
North San 
Gabriel Dam, 
Lake Georgetown 
O.C. Fisher 
Pat Mayse 
Proctor 
Ray Roberts 
Somerville 
Stillhouse Hollow 
Waco 
Wright Patman 
VERMONT 
Ball Mountain 
North Hartland 
North Springfield 
Townshend 
Union Village 
VIRGINIA 
John W. Flannagan 
Gathright Dam & 
Lake Moomaw 
North Fork of 
Pound River 
WASIIINGTON 
Howard A. Hanson 
Mill Creek 
Mud Mountain 
Wynoochee 
Brazos 
Trinity 
Guadalupe 
Red 
Brazos 
Trinity 
Colorado 
Trrinity 
Red 
Trinity 
Trinity 
Trinity 
Brazos 
Colorado 
Red 
Brazos 
Trinity 
Brazos 
Brazos 
Brazos 
Red 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Ohio 
James 
Chehalis 
Green 
Columbia 
Puyallup 
Chehalis 
Leon River 
Clear Fork, 
Trinity River 
Guadallupe River 
Cypress Creek 
San Gabriel River 
Denton Creek 
Hords Creek 
Mountain Creek 
Wichita River 
East Fork, 
Trinity River 
Elm Fork, 
Trinity River 
Richland Creek 
North Fork, 
San Gabriel River 
North Concho River 
Sanders Creek 
Leon River 
Elm Fork 
Yegua Creek 
Lampasas River 
Bosque River 
Sulphur River 
West River 
Ottauguechee River 
Black River 
West River 
Ompompanoosuc River 
Pound River 
Jackson 
Wynoochee River 
Green River 
Mill Creek 
White River 
Wynoochee River 
Belton 
Fort Worth 
New Braunfels 
Jefferson 
Granger 
Grapevine 
Coleman 
Grand Prairie 
Wichita Falls 
Fort Worth 
Lewisville 
Corsicana 
Georgetown 
San Angelo 
Paris 
Comanche 
Denton 
Somerville 
Belton 
Waco 
Texarkana 
Jamaica 
North Hartland 
Springfield 
Townshend 
Union Village 
Haysi 
Alleghany 
Montesano 
Kanaskat 
Walla Walla 
Enumclaw 
Montesano 
1954 1,097,600 
1952 258,600 
1964 366,400 
1959 842,100 
1980 244,200 
1952 425,500 
1948 25,310 
1966 304,000 
1972 502,900 
1953 748,200 
1954 989,700 
1962 212,200 
1980 130,800 
1952 396,400 
1967 189,100 
1963 374,200 
1987 1,064,000 
1967 507,500 
1968 630,400 
1965 726,400 
1957 2,654,300 
1961 54,600 
1960 71,420 
1960 51,067 
1961 33,700 
1950 38,000 
1963 145,700 
1979 123,739 
1972 70,000 
1961 106,000 
1942 8,300 
1953 106,000 
1972 70,000 
12,300 
3,770 
346,400 
18,700 
4,400 
7,280- 
510 
7,470 
15,590 
21,400 
23,280 
5,070 
1,310 
5,440 
5,993 
4,610 
29,350 
11,460 
6,430 
7,270 
20,300 
75 
220 
290 
100 
NPP 
310 
2,532 
1,150 
FIRSX 
FNRXA 
FRSX 
FRS 
FRSWX 
FNRSXA 
FARSX 
FRSX 
FX 
FRSW 
FRSX 
FRSX 
FRSWX 
FRSX 
FRSW 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRW 
FRW 
FRW 
FRW 
FRW 
FAWR 
FQR 
FSARI 
1,600 FAS 
225 FR 
NPP FR 
1,150 FSARI 
A-8 
192 5,524 
130 9,130 
224 4,410 
97 10,600 
115 16,320 
137 12,850 
91 6,800 
109 22,360 
115 8,890 
81 19,483 
125 32,888 
82 6,700 
164 6,700 
128 40,885 
96 7,080 
86 13,460 
109 14,965 
80 26,175 
200 15,624 
140 24,618 
100 18,500 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Rock 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
& Earth 
Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Earth & Rock 
Concrete 
& Earth 
Rock 
Earth 
Rock 
Concrete 
& Earth 
265 
185 
120 
133 
170 
250 
257 
177 
235 
145 
425 
177 
915 
1,520 
2,940 
1,700 
1,100 
960 
1,172 
1m700 
675 
3,200 
700 
1,700

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1989 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
WEST VIRGINIA 
Beech Fork 
Bluestone 
Bumsville 
East Lynn 
R. D. Bailey 
Summersville Lake 
Sutton 
Tygart River 
WISCONISIN 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Beech Fork 
New River 
Little Kanawha 
Twelve Pole Creek 
Guynabdot River 
Gauley River 
Elk River 
Tygart River 
Lavalette 
Hinton 
Burnsville 
East Lynn 
Justice 
Summersville 
Sutton 
Grafton 
1977 37,540 
1952 631,000 
1977 65,400 
1970 82,500 
1979 203,700 
1965 413,800 
1960 265,300 
1938 287,700 
450 FRW Earth 86 1,080 
1,800 FRWX Concrete 180 2,048 
550 FQRW Earth & Rock 89 1,400 
823 FQRW Earth & Rock 122 650 
440 FQRW Earth & Rock 310 1,397 
407 FANR Rock 390 2,280 
270 FNAR Concrete 220 1,921 
620 FNAR Concrete 230 1,921 
Chippewa Eau Galle Spring Valley 1969 43,600 
A-9 
Eau Galle 150 FR Earth 122 1,800

FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS: 
SEPTEMBER 30, 1989 
Pod Charatceristics of Dam 
Cal. Year Total (Ac eage) 
Community Placed in Strage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acae-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
CALIFORNIA 
Big Dry Creek 
Comanche2 
Cherry Valley3 
Del Valle 
Eaton Wash 
New Bullards Bar2 
New Don Pedro3 
New Exchequer2 
Oroville 2 
Tahchevah Creek 
COLORADO 
Pinon Canyon 
CONNECTICUT 
East Branch 
Hall Meadow Brook 
Mad River 
Sucker Brook 
San Joaquin Big Dry Creek 
San Joaquin Mokelumne River 
Tuolumne Cherry Creek 
Alameda Arroyo Del Valle 
Rio Hondo Eaton Wash 
Sacramento Yuba River 
San Joaquin Tuolomne River 
San Joaquin Merced River 
Sacramento Feather River 
Whitewater Tahchevah Creek 
Colorado Pinon Canyon Arroyo 
Housatonic East Branch, 
Naugatuck River 
Housatonic Hall Meadow Brook 
Connecticut Mad River 
Connecticut Sucker Brook 
Fresno 
Clements 
Sonora' 
Livermore 
Pasadena 
Marysville 
Modesto 
Merced 
Oroville 
Palm Springs 
Trinidad 
Torrington 
Torrington 
Winchester 
Winchester 
1948 16,250 NPP 
1963 431,500 NPP 
1956 268,000 475 
1968 77,000 200 
1937 960 NPP 
1968 960,00 1,910 
1970 2,030,000 3,520 
1966 1,026,000 1,900 
1964 3,539,000 5,838 
1965 960 NPP 
1964 4,350 NPP 
1964 4,350 NPP 
1962 8,620 NPP 
1963 9,700 10 
1970 1,480 NPP 
F Earth 40 20,038 
FRS Earth & Rcck 171 2,450 
FS Earth & Rock 315 2,500 
FRS Earth 223 880 
F Earth 82 1,795 
FIRPW Concrete 645 2.323 
FISP Earth & Rock 565 1,920 
FIR Rock 480 1,200 
FIRSW Earth 770 6,850 
F Earth 42 3,610 
FRW Earth 
FR 
F
FR 
F 
92 700 
Eart! 92 100 
Earth & Rock 73 1,200 
Earth 178 940 
Earth 68 1,160 
IDAHO 
Upper Snake Willow Crc 
Potomac 
Upper 
Mississippi 
Oswego 
Savage 
Bear Creek 
Onondaga Creek 
Red North Fork, Red 
Arkansas Grand (Neosho) River 
Arkansas Grand (Neosho) River 
Beaver Big Wash 
Winooski Jail Branch 
Winooski Waterbury 
Winooski North Branch, 
Idaho Falls 1979 100,500 364 
Western Port 1952 20,000 360 
Hannibal 1962 8,700 NPP 
Syracuse 1949 18,200 NPP 
Altus 1948 152,429 6,260 
Locust Grove 1964 444,500 10,0006 
Disney 
Milford 
East Barre 
Waterbury 
Wrightsville 
1941 2,197,000 46,5006 
1961 1,200 NPP 
1938 12,050 NPP 
1938 37,000 890 
1938 20,300 570 
FIR Earth 184 840 
FRS Earth & Rock 184 1,050 
F Earth 65 1,450 
F Earth 
FISR Concrete 
FRP Concrete 
& Earth 
FRP Concrete 
F Earth 
F Earth 
FRH Earth 
FR Earth 
67 1,782 
98 1,112 
147 4,494 
147 6,565 
34 2,814 
65 1,460 
158 1,800 
115 1,525 
A-10 
Ririe 
MARYLAND 
Savage River 
MISSOURI 
Bear Creek 
NEW YORK 
Onandaga 
OKLAHOMA 
Altus4 
Lake Hudson5 
Grand Lake O' 
the Cherokees 
UTAH 
Big Wash 
VERMONT 
East Barre 
Waterbury 
Wrightsville

FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS 
SEPTEMBER 30, 1989 (Continued) 
NOMENCLATURE FOR PROJECT FUNCTIONS 
A - Low Flow Augmentation 
D - Debris Control 
F - Flood Control 
I - Irrigation 
N - Navigation 
P - Power 
Q - Water Quality Control 
R - Public Recreation (Annual Attendance exceeding 5,000) 
S - Water Supply 
W - Fish and Wildlife (Federal or State) 
X - Water Conservation and Sedimentation 
1 Acres of Water surface at top of permanent pool 
2 Federal Government contributed for flood storage 
3 Cherry Valley Reservoir: Planned and constructed by local interests as initial phase; provided flood control on itnerim basis. Second and final phase,N ew Don Pedro Reservoir: 
Federal Government contributed for flood protection, construction and operation by City and County of San Fransisco, and Turlock and Modesto Irrigation Districts. 
4 Construction by Bureau of Reclamation. Participation by Department of the Army to finance flood control portion. 
5 Construction by Grand River Dam Authority. Participation by Department of the Army to finance flood control portion. 
6 Top of power pool. 
A-11

APPENDIX B 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Alton to Gale Levee System, Mississippi 
River, IL and MO.................... ...... 
Arcadia Lake, OK ................................... ........ 
Ardsley, NY ..................................... ........... 
Arkansas-Red Basins Chloride Control (Area VIII), 
Ok, TX, and KS (Stage I)............................................. 
Ascalmore-Tippo Items, MS ............................................ 
Atchafalaya Basin, LA ...................................... .... 
B. Everett Jordan Dam and Lake, NC............................... 
Bassetta Creek, MN.................................. ....... 
Big Blue River, Saline Co., NE, Tuxedo Park Road & 
Bridge (Sec 14)............................................................ 
Big South Fork National River & 
Recreation Area, KY and TN....................................... 
Big Wood River, ID (Sec 208)............................................ 
Bitterroot River, Florence, MT (Sec 14).............................. 
Black River, Butler County Road 607, MO (Sec 14) ......... 
Black River, Hwy HH, Wayne Co., MO............................. 
Blue River Channel, Kansas city, MO................................. 
Boggy Creek, TX .................................... ........ 
Boise River, ID (Sec 208) .................................. ........... 
Browns Creek, Nashville, TN.............................................. 
Brush Bayou, LA............................... ... ........... 
Buffalo Bayou and Tributaries, TX..................................... 
Buffalo Bayou and Tributaries, TX, Addicks and 
Barker, Dam Saftey Assurance.................................... 
Candy Lake, OK .................................... ........ 
Cannon River at Fairbault, MN (Sec 14) .......................... 
Canton Bridge, Trigg Co., KY.......................................... 
Catherine Creek, OR (Sec 208)......................................... 
Clear Creek, TX ....................................... ......... 
Central and Southern, FL.................................................... 
Chariton River, Schuyler Co., MO, Eason Br. (Sec 14)...... 
Chaska, MN................................... ............ 
Chena River Lakes, AK ........................................ 
Cooper Lake and Channels, TX ........................................ 
Copan Lake, OK .................................... ........ 
Corte Madera Creek, CA................................... .... 
County Line Road Bridge, Mantachie, MS (Sec 14)........... 
Cowanesque Lake, PA ..................................... .... 
Cuyahoga River, Riverview Rd, OH (Sec 14)...................... 
Dade County, FL .............................................................. 
Deleware Coast Protection, DE......................................... 
Demonstration Erosion Control, MS................................... 
1983 
1980 
1987 
1976 
1984 
1928 
1967 
1987 
1986 
1979 
1984 
1989 
1985 
1988 
1984 
1985 
1984 
1988 
1977 
1956 
1986 
1976 
1986 
1986 
1985 
1988 
1950 
1989 
1988 
1973 
1958 
1973 
1966 
1989 
1987 
1989 
1975 
1971 
1985 
1986 
1990 
1987 
(2) 
1982 
1986 
1985 
1989 
1989 
1989 
1981 
1983 
1990 
1992 
Indefinite4 
1989 
19883 
1987* 
2010 
1993 
1992 
1987 
1988 
1985 
1989 
1986 
1989 
1998 
1990 
1985 
1990 
1980 
Indefinite 
1990 
Deferred 
1989 
1987 
1986 
1995 
1997 
1989 
1994 
1989 
1994 
1989 
Indefinite 
1990 
1990 
1990 
2032 
2021 
Indefinite 
Local Protection 
Reservoir 
Local Protection 
Chloride Control 
Local Protection 
Floodway and Levees 
Reservoir 
Local Protection 
Streambank Protection 
National Recreation Area 
Snagging and Clearing 
Streambank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Snagging and Clearing 
Local Protection 
Local Protection 
Local Protection 
Dam Safety 
Reservoir 
S treambank Protection 
Streambank Protection 
Snagging and Clearing 
Local Protection 
Local protection 
Streambank Protection 
Local Protection 
Reservoirs and Levee 
Reservoir, channel 
improvement 
Reservoir 
Local Protection 
Streambank Protection 
Water Supply Modification 
Streambank Protection 
Shore Protection 
Local Protection 
Local Protection 
4 Remaining recreation unscheduled pending settlement of lawsuit filed against Edmond, OK for payment of completed recreation 
work. Public use areas, Stages III-B and III-C, are unscheduled pending resolution of repayments by the sponsor for completed 
facilities. 
3 Completion of Stage I (Truscott facilities) only. Stage II (Ross facilities) indefinate.

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Devils Lake, ND (Sec 205) ................................................. 
Dry Creek (Warm Springs) Lake & Channel.................... 
Dry Creek, Goodlettsville, TN.......................................... 
Dunbar (Sewage Facilities), WV (Sec 14)........................ 
East Branch, Cooper River, Pompion Hill Chapel 
near Huger, SC (Sec 14)........................................... 
East St. Louis and Vicinity, IL............................................ 
East St. Louis and Vicnity, IL - Rehabilitation.................... 
El Dorado Lake, KS ...................................... ...... 
El Paso, TX ..................................... ............ 
Elizabeth, NJ ..................................... ........... 
Elk Creek Lake, OR ...................................... ...... 
Elkhorn River, West Point, NE (Sec 205)............................ 
Ellicot Creek, NY ..................................... ........ 
Elwha Klallam Reservation, Elwha, WA (Sec 205) ........... 
Emerson, Manitoba-Noyes, MN (Sec 205)....................... 
Enslava Creek, Mobile, AIL(Sec 205) ................................ 
Evansville, IN................................. ............ 
Fairfield Vicinity Streams, CA ......................................... 
Falls Lake, NC.................................... ................ 
Fire Island Inlet to Montauk Point, NY............................... 
(Remainder) ..................................... .............. 
Fisher Ferry Road, MS (Sec 205) ..................................... 
Fountain Creek, Pueblo, CO ............................................ 
Four Rivers Basin, FL ..................................... ..... 
Fourche Bayou, Vicinity of Little Rock, AR ..................... 
Galena Emergency Bank Stabilization, AK........................ 
Grafton Pumping Station, ND (Sec 14) ............................ 
Great Bend,KS.............................. ............. 
Great Falls MT.................................. .......... 
Greenwood Bendway, Site 3, MS ..................................... 
Greenwood Bendway, Site 4, MS ..................................... 
Greenwood Bendway, Site 5, MS ..................................... 
Gulf Breeze, Santa Rosa Co., FL (Sec 14)........................... 
Guntersville Lake, Guntersville, AL ................................. 
Halstead,KS..................................... 
Hannibal, MO................................... ............ 
Hills Point Road, Dorchester Co., MD (Sec 14).................. 
Hintonville Road Bridge, Perry Co., MS (Sec 14)............... 
Humboldt, TN (Sec 205)........................................ 
Hurricane Creek , Prentiss Co., MS (Sec 14)....................... 
Isle ofWight Bay, Ocean City,MD (Sec 14)......................... 
Joe Pool Lake, TX ..................................................... 
Kahawainui Stream, Oahu, HI.............................................. 
Kahoma Stream, Maui, HI ............................................. 
Kaskaskia Island Drainage & Leeve Dist., IL..................... 
Kea Creek, Minden, IA (Sec 14).......................................... 
Lake Chicot Pumping Plant, AR ....................................... 
Lake Erie State Park, Brocton NY (Sec 14).................. 
Lake Michigan, Edgewater/Rogers Park, IL...................... 
Lake Pontchartrain, LA ................................................. 
Lake Pulaski, Wright County, MN (Sec 205) .................... 
1983 
1967 
1988 
1986 
1986 
1974 
1988 
1974 
1971 
1972 
1971 
1989 
1986 
1987 
1988 
1988 
1939 
1985 
1973 
1963 
1963 
1987 
1987 
1966 
1987 
1987 
1988 
1987 
1982 
1986 
1987 
1987 
1989 
1988 
1989 
1989 
1989 
1989 
1986 
1989 
1989 
1975 
1989 
1986 
1980 
1988 
1981 
1989 
1987 
1967 
1986 
1986 1989 
1983 Indefinite 
1990 
1987 
1987 1987 
1986 
1986 1995 
1981 1989 
1973 Indefinite 
Indefinite 
Indefinite 
1991 
1989 
1990 
1990 
1991 
1994 
1992 
1983 1994 
Indefinite 
Indefinite 
1990 
1990 
1986 Indefinite 
1991 
1988 1988 
1990 
1993 
1987 1987 
1988 
1988 
1988 
1989 
1989 
1993 
1992 
1989 1989 
1990 
1988 1988 
1990 
1990 
1986 1993 
1990 
1990 
1986 
1989 1989 
19914 
1990 
1988 
Indefinite 
1989 1989 
Local Protection 
Reservoir 
Local Protection 
S treambank Protection 
Streambank Protectio 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Local Protection 
S treambank Protection 
Local Protection 
Local Protection 
Local Protection 
Riverbank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Riverbank Protection 
Riverbank Protection 
Riverbank Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
Shoreline Protection 
Reservoir 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Shoreline Protection 
Shoreline Protection 
Local Protection 
Local Protection 
B-2

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Lake Wichita, Holliday Creek, TX ................................... 
Larose to Golden Meadow, LA......................................... 
Lead Bayou, MS (Sec 205)............................... .............. 
Lepua Area, Tutila Island, American Samoa........................ 
Levisa & Tug Forks of the Big Sandy River & 
Cumberland River, KY, WV & VA............................. 
Liberty State Park, Levee and Seawall, NJ (Sec 205)......... 
Little Blue, River, Adams Co., NE, Overy Bridge 
(Sec 14)......................................................................... 
Little Blue River, Adams Co., NE, Pauline Bridge 
(Sec 14)......................................................................... 
Little Blue River, Adams Co., NE, Pimpel 
Bridge (Sec 14) .......................................... ............... 
Little Blue River Channel, MO ......................................... 
Little Blue River Lakes, MO............................................... 
Little Dell Lake, UT.................................... ....... 
Little Kanawha River, Glenville, WV (Sec 14) .................. 
Little Red River, Clinton, AR (Sec 205)........................... 
Little River, Belfast, ME (Sec 14)....................................... 
Lincoln Park Beach, Seattle, WA......................................... 
Long Branch Lake, MO .................................... .... 
Los Coches Creek, San Diego County CA (Sec 205)......... 
Lower Columbia River Bank Protection, OR and WA....... 
Lower Heart River, Mandan, ND (Sec 205)..................... 
Lower San Joaquin River, CA (Snagging & Clearing)....... 
Madison River, Quake Lake,MT (Sec 14)............................ 
Magby Creek, Columbus, MS (Sec 205)............. ........... 
Mankato and N. Mankato, MN ......................................... 
Manistee, Bar Lake, MI (Sec 14)......................................... 
Marne Creek, Yankton, SD (Sec 14)................................... 
Martin Creek, Prentiss Co., MS ........................................ 
Marysville, MI (Sec 14)................................... ..... 
Masefau Bay, Tutuila Island, American Samoa................... 
Mauvaise Terre, IL................................ ......... 
McGee Creek Drainage and Levee Dist., IL ..................... 
Medicine Bow River, Elk, MT, WY (Sec 14)................... 
Merced County Streams, CA .............................................. 
Middle River at Argyle, MD (Sec 205)............................... 
Milan, IL ..................................... ............. 
Mill Creek, OH ................................................................... 
Minnesota River at Henderson, MN (Sec 205) ................. 
Mingo Creek, OK.................................... ......... 
Miss. River Channel Improvements (AR, IL, KY, LA, 
MI, MO & TN)............................................................. 
Miss. River Levees.............................................................. 
Missouri River Levee System, IA, NE, KS, and MO ......... 
Monongahela River, Granville, WV (Sec 14)................... 
MLt. St. Helens Sediment Control, WA................................ 
Mudline to Pineville, MS ............................................... 
Murder Creek, Brewton, AL (Sec 205)............ ........... 
Muskegon (Filtration Plant), MI (Sec 14)........................... 
1987 
1972 
1982 
1989 
1981 
1987 
1986 
1986 
1986 
1975 
1978 
1985 
1986 
1985 
1988 
1988 
1973 
1986 
1961 
1987 
1985 
1988 
1989 
1971 
1989 
1986 
1986 
1989 
1989 
1985 
1979 
1985 
1985 
1985 
1980 
1981 
1988 
1988 
1928 
1928 
1948 
1986 
1986 
1984 
1986 
1989 
1988 
1993 
1992 
1988 
1991 
Local Protection 
Local Protection 
Local Protection 
Shoreline Protection 
Indefinite Local Protection 
1988 Shore Protection 
1986 
1987 
1987 
1987 
1987 1987 
1988 
1990 
1991 
1987 
1986 1987 
1989 1989 
1989 
1980 Indefinite 
1987 1990 
Indefinite 
1989 1989 
1993 
1989 1989 
1990 
1989 
1989 1990 
1987 1988 
1987 
1989 1990 
1990 
1987 
1985 
1986 1987 
Indefinite 
1989 
1988 1988 
1999 
1990 
1995 
(4) 
(4) 
1985 
1989 
2010 
2008 
Indefinite 
1987 
1991 
1985 
1991 
1989 
S treambank Protection 
S treambank Protection 
Streambank Protection 
Local Protection 
Reservoir 
Reservoirs 
Streambank Protection 
Local Protection 
S treambank Protection 
Beach Nourishment 
Reservoir 
Local Protection 
Local Protection 
Local Protection 
Snagging and Clearing 
S treambank Protection 
Snagging and Clearing 
Local Protection 
Shoreline Protection 
Streambank Protection 
Streambank Protection 
Shoreline Protection 
Shoreline Protection 
Local Protection 
Local Protection 
Streambank Protection 
Reservoirs 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Channel Improvement 
Main Line Levees 
Local Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
Local Protection 
Shoreline Protection 
B-3

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Muskingham River Lakes, OH ........................................ 
Muskingum River Lakes, OH 
(Dam Safety Assurance)........................................... 
New Orleans to Venice, LA ............................................. 
Newark, OH ..................................... ........... 
North Branch Chicago River, IL....................................... 
North Portage Path, Akron, OH (Sec 14)............................. 
North Raccoon River, Ia State Hwy, 7 Bridge, 
Buena Vista, IA................................... ....... 
North River, Co. Route 116, Klein Bridge, 
Marion co., MO................................... ....... 
Oil Creek Ice Control Project, Oil City, PA ..................... 
Osage River, Miller Co., MO, Road HH (Sec 14).............. 
Otter Creek, Shannon Hills, AR (Sec 205) ....................... 
Owyhee River, OR (Sec 208) ........................................... 
Paintsville Lake, KY ...................................... ...... 
Pajano River, CA................................... ......... 
Panola-Quitman Item C, MS ............................................ 
Papillion Creek and Tributaries Lake, NE.......................... 
Passaic River Basin, NJ and NY (Sec 205)....................... 
Pearl River, MS ............................................. 
Pelucia Creek, Item 1, MS ............................................. 
Pelucia Creek, Item 1A, MS ............................................ 
Pennypack Creek, Hatboro, PA........................................... 
Perkins Street Bridge, TN (Sec 14)...................................... 
Perley Brook, Fort Kent, ME (Sec 14)................................. 
Perry County L & D Nos. 1, 2, 3, MO.............................. 
Pettibone Park, LaCrosse, WI (Sec 14)............................. 
Phoenix, AZ, and Vicinity (including New River) ............. 
Platte River, North Bend, NE (Sec 205)............................... 
Platte River, Ginger Cove, NE (Sec 14)............................... 
Poquessing Creek, Bucks Co., PA .................................... 
Porter Bayou, MS (Sec 205) ............................................ 
Portugues and Bucana Rivers, PR..................................... 
Presque Isle Peninusula, PA................................................ 
Proctor Creek, Atlanta, GA (Sec 205).................................. 
Pt. Leflore, MS ......................................... ......... 
Puerco River, Gallup, NM................................. ............ 
R. D. Bailey Lake, WV .............................................. 
Raccoon Creek, Baconton, GA (Sec 205)............................ 
Rapidan River, Orange, VA (Sec 14).................................. 
Raritan Bay and Sandy Hook Bay, NJ, Matawan 
and Union Beach Sections........................................ 
Ray Roberts Lake, TX.................................... ...... 
Redbank & Fancher Creeks, CA....................................... 
Red Lake River at Gentilly, MN.......................................... 
Red River Emergency Bank Protection ............................ 
Red River of the North at Breckenridge, MN (Sec 14)....... 
Red River of the North at Argusville, ND (Sec 205).......... 
Reserve Sewage Lagoon, NM (Sec 14) .............................. 
Rio Grande Floodway, Truth or Consequences, NM........... 
1976 
1982 
1969 
1976 
1988 
1989 
1987 
1987 
1987 
1986 
1984 
1986 
1973 
1987 
1984 
1972 
1987 
1984 
1985 
1987 
1988 
1987 
1989 
1977 
1988 
1980 
1988 
1988 
1987 
1982 
1975 
1975 
1989 
1985 
1988 
1967 
1989 
1983 
1965 
1975 
1987 
1989 
1971 
1988 
1985 
1986 
1989 
1989 
1989 
1986 
1984 
1983 
1974 
1989 
1989 
1985 
1989 
1989 
1989 
1988 
1975 
1986 
1988 
1995 
2013 
1989 
1991 
1990 
1989 
1989 
1989 
1987 
1986 
1987 
1991 
1988 
1986 
1991 
1988 
1985 
1987 
1987 
1989 
1990 
1989 
1985 
1989 
1992 
1989 
1989 
1988 
1988 
1993 
1989 
1990 
1986 
1990 
1988 
1990 
1987 
Indefinite 
1987 1992 
1993 
1990 
Indefinite 
1989 1989 
1987 1989 
1989 1987 
1991 
Major Rehabilitation 
Modernization of Dams 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
S treambank Protection 
Streambank Protection 
Local Protection 
S treambank Protection 
Local Protection 
Snagging and Clearing 
Reservoir 
Local Protection 
Local Protection 
Reservoirs 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
S treambank Protection 
Local Protection 
S treambank Protection 
Local Protection 
Streambank Protection 
S treambank Protection 
Local Protection 
Local Protection 
Local Protection 
Beach Replentishment 
Local Protection 
Streambank Protection 
Local Protection 
Reservoir 
Local Protection 
S treambank Erosion 
Local Protection 
Reservoir 
Reservoir 
StreambankProtection 
Streambank Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
Local Protection 
B-4

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Richmond, VA................................... 1989 
Rochester, MN ..................................... 1987 
Rockford, IL (Kent Creek)..................................... 1979 
Roosevelt Campobello International Park, Lubel, ME........ 1988 
Sabana Grande, PR (Sec 205) .............................. ......1.9.8.7. 
Sacramento River Bank Protection, CA ..............1.9.63.......... 
Sacramento River, Chico Landing to Red Bluff, CA ...... 1963 
Sacramento River Flood Control, CA.............................. 1918 
Sacramento River, Major and Minor Tributaries, CA ......19.4.9 
Saginaw River, MI ..................................... 1965 
San Antonio Channel Improvement, TX...............19.5.7............ 
Sangamon River, Sewage Treatment Facility 
Riverton, IL............... ................. 1987 
San Lui s Rey River, San Luis Rey River, Buoin, CA........ 1987 
San Vincente Arroyo, Silver Spring, NM ..............19.8.8........ 
Sardis Lake, OK ..................................... 1976 
Sauk River, Skagit County, WA (Sec 14).............1.98.8............. 
Savan Gut, VI (Sec 205) ..................................... 1987 
Saxon Harbor, WI (Sec 111)................................... 1989 
Saylorville Lake, IA..................................... 1965 
Scotts Creek, newberry, SC (Sec 205)............................. 1986 
Scottsville, VA (Sec 215)................................ 1986 
Sewer Line Protection, Valley, AL (Sec 14)....................... 1985 
Sicily Island, LA, Levee .........................19.8.3....................... 
Silver Creek, Rome, GA (Sec 205).................1.9.89................... 
Skiatook Lake, OK ..................................... 1974 
Smithville Lake, MO............................................. 1974 
Soldier River, Ute, IA (Sec 205)...................1.98.8..................... 
Sope Creek, Marietta, GA........................1.9.8.6..................... 
South Fork, Boise River, ID (Sec 208) ...............1.9.8.4.......... 
South Quincy, IL ..................................... 1987 
South Racoon River, 8" Water Supply Line, Stuart, IA....... 1987 
Southwestern Jefferson County, KY .................1.9.74................ 
Sowashee Creek, Meridian, MS.....................19.8.8................ 
Spring Brook Creek, Pittston Township, PA (Sec 14).....1.98.9.. 
State Road and Ebner coulees, WI...................19.8.8.............. 
Steele Bayou, MS ..................................... 1966 
St. Francis Basin .................................... 1938 
Stonewall Jackson Lake, WV .....................1.9.77................... 
Swan Creek, Taney County, MO (Sec 14)............1.9.8.4........... 
Sweetwater River, CA......................................... .......1.9.92... 
Tallahatchie River, Site 1, MS .....................1.98.8.................. 
Taylors Bayou, TX ......................................................... 1982 
Taylorsville Lake, KY .................................... 1974 
Telegraph Canyon Creek, Chula Vista, CA (Sec 205)......... 1988 
Tennessee River (Mile 650) Downtown Is. Airport, TN .... 1986 
Tensas Cocodrie Pumping Plant, LA 11 ..............1.9.8.3............ 
5 Project consists of Levee upgrade and enlargement. 
6 Durham Prong Diversion local support problem. 
1992 
1989 
1989 
1989 
1989 
1979 
1989 
1988 
1983 
1989 
1989 
1977 
1986 
1985 
1982 
1989 
1989 
1983 
(4) 
1986 
1983 
1989 
1993 
1995 
1989 
1989 
1990 
1994 
Indefinite 
1989 
1988 
1992 
1991 
1989 
1992 
1988 
1990 
1989 
1990 
1990 
1993 
1988 
1988 
1989 
20005 
1990 
1988 
1986 
1989 
1990 
1985 
1991 
1989 
1989 
1992 
1990 
1993 
2010 
1999 
1988 
1986 
1992 
1988 
1992 
1990 
1989 
1987 
Indefinite 6 
Local Protection 
Local Protection 
Local Protection 
Shoreline Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
Reservoir 
S treambank Protection 
Local Protection 
Shoreline Mitigation 
Reservoir 
Local Protection 
Local Protection 
Sewer Line Protection 
Local Protection 
Local Protection 
Reservoir 
Reservoir 
Streambank Protection 
Local Protection 
Snagging and Clearing 
Local Protection 
Streanbank Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local protection 
Local Protection 
Tributary levees & channels 
Reservoir 
Streambank Protection 
Local Protection 
Riverbank Protection 
Local Protection 
Reservoir 
Local Protection 
Streambank Protection 
Local Protection 
B-5

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Tensas Cocodrie, LA, Levee (5)........................................ 
Texas City and Vicinity, TX (1958 authorization) ............. 
Tombigbee River Tributaries, AL and MS ....................... 
Tunkhannock Creek, Tunkhannock Creek, PA (Sec 14)..... 
Tynes Branch, Houston School Road Bridge, Itawamba 
Co., MS ........................................................................ 
Upper Scioto River, Marion County, OH (Sec 205)........... 
Upper Yazoo Projects, MS............................................. 
U.S. Hwy. 11 Bridge, Fosters, AL (Sec 14)........................ 
U.S. Hwy. 82 Bridge, Columbus, MS (Sec 14) .................. 
U.S. Interstate 59 Bridges, Fosters, AL (Sec 14)................ 
Valley Creek, AL (Sec 14).................................................. 
Vince and Little Vince Bayous, TX.................................... 
Walnut Creek, CA .................................... ....... 
Warner Road, Mississippi River, St. Paul, MN (Sec 14)..... 
Waterman Creek, O'Brien County, IA (Sec 205)................. 
Westerly Creek, Colorado............................... ...... 
West Fork, Des Moines River, Petersburg Township 
Bridge 32527, Jackson Co., MN................................... 
West Little Pine Creek, Etna, PA...................................... 
West Tennessee Tributaries ........................................... 
Wheeler Creek, Gainesville, TX (Sec 205)......................... 
Wharton's Bend Road, Coosa River,AL (Sec 14)................ 
White River, Batesville, AR (Sec 14) ................................. 
White River, Jacksonport, AR (Sec 205).......................... 
White River, Newport, AR (Sec 14).................................... 
White River, St. Paul, AR (Sec 208).................................... 
Wildcat and San Pablo Creeks, CA..................................... 
Wilamette River Basin Bank Protection, OR...................... 
Winona, MN................................... ............ 
Wolf River at 2nd Street, Memphis, TN (Sec 14)................ 
Wood River Drainage and Levee District, IL ................... 
Wyoming Valley, PA................................... ...... 
Yatesville Lake, KY.................... ........ 
1974 
1962 
1965 
1989 
1986 
1986 
1976 
1985 
1985 
1985 
1985 
1968 
1964 
1986 
1988 
1988 
1986 
1986 
1960 
1983 
1989 
1984 
1984 
1988 
1988 
1980 
1938 
1979 
1988 
1953 
1983 
1964 
1987 
1986 
1986 
1986 
1986 
1989 
1988 
1987 
(4) 
1094 
1986 
1986 
1989 
1985 
1989 
1962 
1976 
19957 
1987 
Indefinite 
1990 
1987 
1987 
2013 
1986 
1986 
1987 
1986 
1988 
1900 
1987 
1989 
1991 
1989 
1987 
Indefinite 
1984 
1990 
1986 
1986 
1989 
1990 
Indefinite 
Indefinite 
1988 
1990 
1986 
1986 
1992 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Bridge Protection 
Local Protection 
Local Protection 
S treambank Protection 
Streambank Protection 
Streambank Protection 
Sewerline Protection 
Local Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
S treambank Protection 
Local Protection 
Tributary Channels 
Local Protection 
S treambank Protection 
Local Protection 
Local Protection 
Streambank Protection 
Snagging and Clearing 
Local Protection 
Local Protection 
Local Protectin 
Local Protection 
Local Protection 
Rehabilitation of levee system 
Reservoir 
B-6 
7 Item 2A temporarily deferred.

APPENDIX C 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
Alabama-Coosa Rivers, AL 
Claiborne Lock & Dam 
Millers Perry lock and 
Dam 
Jones Bluff Lock and Dam 
Aoleghny River, PA and NY 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
Lock and Dam No. 6 
Lock and Dam No. 7 
Lock and Dam No. 8 
Lock and Dam No. 9 
Apalachicola, Chattahoochee, 
and Flint Rivers, GA, AL 
and FL 
Jim Woodruff Lock 
and Dam 
George W. Andrews 
Lock and Dam 
Walter F. George 
Lock and Dam 
Atlantic Intracoastal 
Wastierway 
Albemarle and Chesapeake 
Canal Route: 
Great Bridge Lock 
Dismal Swamp Canal 
Route: 
Deep Creek Lock 
South Mills Lock 
Bayou Teche, LA 
Berwick Lock 
Keytoane Lock 
Black Rock Chantel and 
Tonawonda Harbor, NY 
Black Rock Lock 
Black Warrior, Warrior 
and Tombigbee Rivers, AL 
Coffeeville (Jackson) 
Lock and Dam 
Demopolis Lock and Dam 
Armstad I. Selden Lock 
and Dam 
WinmB. acon Oliver 
Lock andDam 
Holt Lock and Dam 
John Hilis Bankhead 
Lock and Dam (New Lock) 
Canaveral Harbor, FL 
Canaverl Lock 
Cape Pear River, NC 
Lock and Dam No. 1 
Lock and Dam No. 2 
William O. Huske 
Lock and Dam 
Central and Southmrn Florida 
S-61 Lock 
S-65 Lock 
S-65A Lock 
S-65B Lock 
S-65CLock 
81.82 Qaibone, AL 
142.32 Camden, AL 
254.42 Benton, AL 
6.7 Aspinwall, PA 
14.5 Cheswick, PA 
24.2 Natrona, PA 
30.4 Freeport, PA 
36.3 Cinton, PA 
45.7 Kittanning, PA 
52.6 Templeton, PA 
62.2 Rimer, PA 
107.64 Chattahoochoe, FL 
182.85 Columbia, GA 
182.85 Port Gaines, GA 
11.56 GOat Bridge, VA 
10.66 Deep Crk, VA 
33.26 South Mills, NC 
1.53 Berwick, LA 
72.53 New Iberia, LA 
0.0 Buffalo, NY 
116.610 Coffeeville, AL 
213.210 Demopolis, AL 
261.110 Eutaw, AL 
338.110 Tuscaloosa, AL 
347.010 Holt, AL 
365.1 Adger, AL 
2.7 Cocoa, FL 
67.0 Kings Bluff, NC 40 
99.0 Browns Landing, NC 40 
123.0 Tolars Landing, NC 40 
0.0 St. Cloud, FL 
56.0 Froatproof, FL 
46.0 Avon Park, FL 
32.0 Scbring, FL 
25.0 Sebring, FL 
30 
30 
30 
30 
30 
84 600 30 16 13 Movable 3,1603 1973 
84 600 45 16 13 Movable 9,9003 1969 
84 600 45 16 13 Movable 14,9623 1974 
56 
56 
56 
56 
56 
56 
56 
56 
360 
360 
360 
360 
360 
360 
360 
360 
11 
13 
10 
12 
12 
13 
18 
22 
11 
12
9 
10 
11 
11 
14 
11 
12 Fixed 
11 Fixed 
10 Pixed 
11 Fixed 
11 Fixed 
10 Fixed 
10 Fixed 
11 Fixed 
1,393 193420 
1,436 19342 
876 1927 
780 1927 
1,140 1928 
916 1930 
984 1931 
950 1938 
60.5 9 200 
103.1 9 200 
88.0 9 200 
7.8 9 
9.7 9 
6.2 9 
5.9 9 
9.4 9 
6.9 9 
9.6 9 
9.8 9 
200 
200 
200 
200 
200 
200 
200 
200 
82 450 33 14 14 Movable 5,924 1957 46.7 6 100 
82 450 25 19 13 Movable 620 1963 28.5 6 100 
82 450 88 18 13 Movable 13,371 1963 85.0 6 100 
72 530 3 167 16
7 None 
52 300 12 127 
52 300 12 127 
45 307 79 
36 162 9 
97
9 
12
7 
None 
127 None 
97 None 
8 Fixed 
68 625 5 21.6 21.6 None 
1932 12 90 
1940 6 50 
1941 6 
1950 
175 1913 
50 
8 80 
34.5 6 80 
1914 7.1 21 200 
110 600 33 13 13 Movable 1,185 1965 96.6 9 200 
110 600 40 13 13 Fixed 1,485 1962 47.9 9 200 
110 600 22 13 13 Movable 1,832 1962 77.0 9 200 
95 460 28 12 12 Fixed 700 1940 8.9 9 200 
110 600 64 19 13 Movable 1,138 1969 18.1 9 200 
110 600 68 13 13 Fixed 1,170 1975 42.7 9 200 
90 600 14 14 None 
200 11 9 9 Fixed 
200 9 12 12 Fixed 
300 
90 
90 
90 
90 
90 
9 9 Fixed 
6 Nane 
6 None 
6 Namc 
6 None 
6 None 
1965 12 125 
275 1915 32.0 8 100 
229 1917 24.0 8 100 
220 1935 20.0 8 100 
1963 
1964 
1967 
1965 
1965 
8 
28.0 3 
10.0 3 
14.0 3 
7.0 3 
20 
30 
30 
30 
30

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authorized Chansel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Type
1 
(feet) Opened (miles) (feet) (feet) 
Central and Southern Florida (continued) 
S-65D Lock 
S-65B Lock 
S-308B 
S-310 
Chicago Harbor, IL 
Chicago Lock 
Columbia River, OR and WA 
Bonaeville Lock and Dam 
The Dales Lock and Dam 
John Day Lock and Dam 
McNary Lock and Dam 
Cros-Florida Barge Canal 
Inglia Lock, Dam 
and Spillway 
Bureka Lock and Dam 
Harry H. Buckman Lock 
Cumberland River, KY 
and TN 
Barkley Dam 
Cheatham Lock and Dam 
Old Hickory Lock and Dam 
Cordell Hull Dam 
and Reservoir 
Fox River, WI 
DePee Lock 
DePre Dam 
Little Kaukauna Lock 
Little Kaukauna Dam 
Rapide Crochn Lock 
Rapids Croche Dam 
Kaukauna Fifth Lock 
Kaukauna Fourth Lock 
Kaukauna Third Lock 
Kaukauna Second Lock 
Kaukaunm First Lock 
Kaukauna Dam 
Kaukauna Guard Lock 
Little Chute canombineLdo ck 
Lower 
Upper 
Little Chute Second Lock 
Little Chute First 
(Guard) Lock 
Little Chute Dam 
Cedars Lock 
Cedars Dam 
Appleton Fourth Lock 
Appleton Lower Dam 
Appleton Third Lock 
Appleton Second Lock 
Appleton FPirsLt ock 
Appleton Upper Dam 
Menash Lock 
Menaha Dam 
Freshwater Bayou, LA 
Freshwater Bayou Lock 
Gaeon and Barren Rivers, KY 
Geen River. 
Lock and Dam No. 1 
Lock and Dam No. 2 
Gulf Intracoastal Waterway 
Inner Harbor Navigation 
Chamnel Lock 
Harvey Lock 
16.0 
12.0 
38.7 
0.0 
Oktechobee, FL 
Okeechobee, FL 
Port Mayaca, FL 
Gewistm, FL 
0.0 Chicago, IL 
146.0 Bonneville, OR 
190.0 The Dalles, OR 
215.0 Rufus, OR 
292.0 Umatilla, OR 
168.611 Inglis, FL 
20.0 Sparr, FL 
90.4 Palatka, FL 
30 
30 
56 
50 
90 
90 
400 
60 
80 600 
76 
86 
86 
86 
84 
84 
84 
30.6 Kuttawa, KY 110 
148.7 Ashland City, TN 110 
216.2 Old Hickory, TN 84 
313.5 Carthage, TN 84 
7.1 
7.2 
13.0 
13.1 
19.2 
19.3 
22.8 
23.1 
23.3 
23.4 
23.6 
24.0 
24.0 
25.4 
25.4 
26.4 
26.5 
26.6 
27.3 
27.4 
30.7 
30.9 
31.3 
31.6 
31.9 
32.2 
37.8 
37.8 
19.08 
DePe, WI 
DePe, WI 
DePere, WI 
DePeze, WI 
Wrightstown, WI 
Wrightatown, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Menasha, WI 
Menasha, WI 
Intracoastal City, LA 
9.1 Spottville, KY 
63.1 Calhoun, KY 
92.612 
98.312 
New Orleans, LA 
Harvey, LA 
36 
36 
36 
36 
37 
31 
35 
35 
40 
35 
36 
35 
35 
35 
35 
35 
35 
34 
34 
84 
500 
675 
675 
675 
600 
600 
600 
800 
800 
400 
65 
88 
110 
75 
28 
20 
20 
57 
26 
60 
6
6 
14 
13 
6
6 
14 
13 
None 
None 
Movable 
Movable 
23 23 None 
32 
15 
15 
15 
18 
14 
14 
11 
14 
14 
24 
15 
15 
20 
15 
15 
13 
12 
10 
Movable 
Movable 
Movable 
Movable 
1964 
1964 
1977 
1980 
9.0 3 
4.0 3 
5.0 8 
.5 6 
30 
30 
100 
50 
1939 .15 21 470 
2,680 1938 
8,735 1957 
5,900 1968 
7,365 1953 
Movable 5,100 1968 
Movable 3,830 1971 
None 1972 
Movable 9,959 1964 
Movable 801 1959 
Movable 3,605 1957 
47.5 27 
25,0 14 
76.0 14 
64.0 14 
300 
250 
250 
250 
11.0 12 150 
12 150 
21.2 12 150 
118.1 9 150 
67.5 9 150 
97.3 9 150 
400 59 14 13 Movable 1,138 1973 71.9 9 150 
146 
146 
146 
144 
144 
144 
144 
144 
147 
144 
144 
144 
144 
144 
145 
145 
144 
600 
9
7
8
9 
10 
10 
10 
11
9 
11 
11 
14 
7 
10
8
9 
10 
10
8 
10
8
9
7
7
7
6
7
6
8
8 
12 
10 
10 
9
66 
66 
7 7 
8 8 
6 9 
7 6 
7 6 
7 8 
16 16 None 
84 600 12 12 11 Fixed 
84 600 14 15 12 Fixed 
75 640 99 
75 425 109 
317 
12
7 
317 
12
7 
1936 
Movable 986 1929 
1938 
Movable 588 1926 
1934 
Movable 461 1930 
1898 
1879 
1879 
1903 
1883 
Movable 603 1931 
1891 
1879 
1879 
1881 
1904 
Movable 562 1932 
1888 
Movable 654 1933 
1907 
Movable 549 1934 
1900 
1901 
1884 
Movable 691 1940 
1899 
Movable 401 1937 
5.9 6 
6.2 6 
3.6 6 
0.3 6 
0.2 6 
0.1 6 
0.2 6 
0.4 6 
1.4 6 
100 
100 
100 
100 
100 
100 
100 
100 
100 
6 100 
6 100 
1.0 6 100 
0.7 6 
3.4 6 
0.6 6 
0.3 6 
0.3 6 
5.1 6 
28.3 6 
401 1968 
100 
100 
100 
100 
100 
100 
100 
12 125 
482 1956 54.0 9 200 
519 1956 45.4 9 200 
None 
None 
1923 
1935 
12 150 
12 125 
C-2

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Conmmunity of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typol (feet) Opened (miles) (feet) (feet) 
Gulf Intracoastal Waterway (continued) 
Algiers Lock 
Bayou Bouef Lock 
Bayou Sorrel Lock 
Part Allen Lock 
Calcasieu Lock 
Brazos River Floodgates 
Colorado River 
Bast Lock 
West Lock 
Hudson River, NY 
Troy Lock and Dam 
Illinois Waterway, IL 
LaGrange Lock and Dam 
Peoria Lock and Dam 
Starved Rock Lock 
and Dam 
Marseilles Lock 
Marseilles Dam 
DresdenI sland 
Lock and Dam 
Brandon Road Lock 
and Dam 
Lockpt Lock 
Thomas J. O'Brien 
Lock and Dam 
Inland Route, MI 
Crooked River 
Lock and Weir 
Kanawha River, WV 
Winfield Lock and Dam 
Marnwt Lock and Dam 
London Lock and Damrn 
Kaskaskia River, IL 
Kaskaskia Lock and Dam 
Kentucky River, KY 
Lock and Dam No. 1 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
Lock and Dam No. 62 
Lock and Dam No. 724 
Lock andDam No. 8 
Lock and Dam No. 9
2 4 
Lock and Dam No. 10 
Lock and Dam No. 11 
Lock and Dam No. 12 
Lock and Dam No. 13 
Lock and Dam No. 142 
Lake Washington Ship Canal 
Kiram M. Chittenden Lock 
Large Lock 
Small Lock 
McCellan-Kerr Arkansas 
River Navigation System, 
AR and OK 
Norell Lock and Dam 
Wilbur D. Mills, Lock No. 2 
Dam No. 2 
ss.o 
12 
88.012 
93.3 
131.013 
228.512 
238513 
404.113 
Algiers, LA 
Marpn City, LA 
Plaquemine, LA 
Port Allen, LA 
Leake Charles, LA 
Freeport, TX 
75 
75 
56 
84 
75 
75 
797 
1,158 
800 
1,198 
1,205 
109 
69 
109 
45 
69 
137 
137 
14 
137 
137 
157 
444.8 MatagordaT,X 75 1,200 59 
444.8 Matagorda,TX 75 1,200 59 
153.8 Troy, NY 
13 
13 
14 
14 
13 
15 
15 
15? 
Noane 
None 
NNaannao 
Nane 
None 
None 
None 
None 
16 
16 
12 
12 
16 
12 
1956 
1956 
1952 
1961 
1950 
1943 
1954 
1954 
45 493 17 16 13 Fixed 1,495 1917 
150 
150 
125 
125 
200 
125 
12 125 
12 125 
2.2 14 200 
80.2 Beardstown, IL 110 600 10 16 13 Movable 1,066 1939 77.5 9 300 
157.7 Peoria, IL 110 600 11 16 12 Movable 536 1939 73.3 9 300 
231.0 Uitca, IL 
244.6 Marseilles, IL 
247.0 Marseilles, IL 
271.5 Morris, IL 
286.0 Joliet, IL 
291.1 LockportIL, 
326.5 Chicago, IL 
30.0 Alansn, MI 
31.1 
67.8 
82.8 
Winfield, WV 
Mamet. WV 
London, WV 
110 600 19 17 14 Movable 1,280 1933 13.6 9 
110 600 24 19 14 1933 26.9 9 
Movable 819 1933 24.6 
300 
300 
110 600 22 17 12 Movable 1,616 1933 14.5 9 300 
110 600 34 18 14 Movable 2,373 1933 
110 600 40 12 15 None 1933 
110 1,000 2 14 14 Movable 257 1960 
17.8 66 1 6.9 7.9 SSP Weir 83 1967 
56 
56 
56 
360 
360 
360 
28 
24 
24 
18 
18 
18 
12 
12 
12 
Movable 834 1937 
Movable 707 1934 
Movable 707 1934 
5.1 9 300 
9 300 
6.9 9 300 
4.0 5 30 
36.7 9 300 
15.0 9 300 
7.8 9 300 
.8 Ellis Grove, IL 84 600 32 18 11 Movable 130 1973 35.0 9 225 
4.0 
31.0 
42.0 
65.0 
82.2 
96.2 
117.0 
139.9 
157.5 
176.4 
201.0 
220.9 
239.9 
249.0 
Carrlton, KY 
Lockport, KY 
Gest, KY 
Frankfort, KY 
Tyrone, KY 
High Bridge, KY 
High BridgeK,Y 
Camp Nelson, KY 
Valley View, KY 
Ford, KY 
Irvine, KY 
Raverma, KY 
Willow, KY 
Heidelberg, KY 
1.3 Seattle, WA 
13 Seattle, WA 
10.3 
13.3 
40.5 
Arkansas Post, AR 
Arkansas Post. AR 
Arkansas Post, AR 
38 
38 
38 
38 
38 
52 
52 
52 
52 
52 
52 
52 
52 
52 
145 
145 
145 
145 
145 
147 
147 
146 
148 
148 
148 
148 
148 
148 
8 
14 
13 
13 
15 
14 
15 
19 
17 
17 
18 
17 
18 
17 
8
8
96 
10
9
9 
11 
11 
9 
10 
10 
10 
9 
15 
6
7
6
6
6
7
6
7
6
6
6
6
6 
80 760 26 33.5 29 
28 123 26 16 16 
110 
110 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
424 1839 
400 1939 
465 1844 
534 1844 
556 1844 
413 1891 
350 1897 
257 1900 
362 1907 
472 1907 
208 1906 
240 1910 
248 1915 
248 1917 
Movable 235 1916 
600 30 16 15 Fixed *4,577 1967 
600 20 18 14 1967 
Movable *42,073 1968 
27.0 6 
11.0 6 
23.0 6 
17.2 6 
14.0 6 
20.8 6 
22.9 6 
17.6 6 
18.9 6 
24.6 6 
19.9 6 
19.0 6 
9.1 6 
9.6 6 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
17.0 34 150 
3.0 9 250 
36.9 9 250 
C-3

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authoried Chamnnel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (fet) Opened (miles) (feet) (fet) 
McQellan-Kerr Arkansas 
River Navigation System, 
AAR and IK (continued) 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
David D. Terry Lock 
and Dam 
Murray Lock and Dam 
Toad Suck Ferry Lock 
and Dam 
Lock and Damn No. 9 
Dardanelle Lock and Dam 
Ozark-Jetta Taylor Lock* 
and Dam 
Lock and DamnN o. 13 
W. D. Mayo Lock and Damn 
Robert S. Kerr Lock and 
Dam and Reservoir 
Webbers Falls Lock and 
Dam 
Chouteau Lock and Dam 
Newt Graham Lock 
and Dam 
Mississippi River 
Between Ohio and Missouri 
Rivers 
Lock and Dam No. 27 
Mississippi River Between 
Missouri River and 
Minneapolis MN 
Locak and Dam No. 26 
Lock and Dam No. 25 
Lock and Dam No. 24 
Lock and Dam No. 22 
Lock and Dam No. 21 
Lock and Dam No. 20 
Lock and Dam No. 19 
Lock and Dam No. 18 
Lock and Dam No. 17 
Lock and Dam No. 16 
Lock and Dam No. 15 
Lock and Dam No. 14 
Lock and Dam No. 13 
Lock and Dam No. 12 
Lock and Dam No. 11 
Lock and Dam No. 10 
Lock and Dam No. 9 
Lock and Dam No. 8 
Lock and Dam No. 7 
Lock and Dam No. 6 
Lock and Dam No. SA 
Lock and Dam No. 5 
Lock and Dam No. 4 
Lock and Dam No. 3 
Lock and Dam No. 2 
Lock and Dam No. 1 
St. Anthony Falls 
Lower Lock and Dam 
Upper Lock and Dam 
50.2 Grady, AR 
66.0 Pine Bluff, AR 
863 Redfield, AR 
108.1 Little Rock, AR 
125.4 Little Rock, AR 
155.9 Conway, AR 
176.9 Morriltom, AR 
205.5 Russellville, AR 
256.8 Ozark, AR 
292.8 Port Smith, AR 
319.6 Port Smith, AR 
336.2 SSallisawOK 
366.6 Webbers Palls, OK 
4014A Muskogee, OK 
4421.7 Inola. OK 
185.114 Granite City, IL 
202.915 Alton, IL 
241.4 
1 5 Cap Au Gris, MO 
273.415 Qarksville, MO 
301.215 Saverton, MO 
324.915 Quincy, IL 
343.215 Canton, MO 
364.215 Keokuk,IA 
410.515 Burlington, IA 
437.115 New Boston, IL 
457.215 Muscatine, IA 
482.915 Rock Island, IL 
493.115 IeClaize, IA 
493315 LeCIaire, IA 
522.515 5inton, IA 
556.715 Bellevue, IA 
583.015 Dubuque, IA 
615.115 Guttenberg, IA 
647.915 Lynxville, IA 
679.215 Genoa, WI 
702.515 Dresbach, MN 
714315 Trempealeau, WI 
728.515 Winona, MN 
738.115 Minneiska, MN 
752.815 Alma, WI 
796.915 Red Wing, MN 
815.215 Hastings, MN 
847.615 Minneapolis,, MN 
St. Paul 
853315 Minneapolis, MN 
853.915 Minneapolis, MN 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
600 20 18 
600 14 18 
600 17 18 
14 Movable *6,1110 
14 Movable 5,745 1968 
14 Movable *7,455 1968 
600 18 18 14 Movable *8,890 1968 
600 18 18 14 Movable (3,930 1969 
600 16 18 
600 19 18 
600 54 18 
600 34 18 
600 20 18 
600 20 14 
14 Movable *1,580 1969 
14 Movabe *1,505 1969 
14 Movable **1,815 1969 
15 Movable *12,480 1969 
14 Movable *4,725 1969 
15 Movable 7,400 1970 
110 600 48 18 14 Movable 7,230 1970 
110 600 30 19 
110 600 21 15 
16 Movable 4,370 1970 
14 Movable 11,690 1970 
110 600 21 15 14 Movable 11,630 1970 
1968 15.8 9 
20.3 9 250 
21.8 9 250 
17.3 9 250 
30.5 9 250 
21.0 9 250 
28.6 9 250 
51.3 9 250 
36.0 9 250 
26.8 9 250 
16.6 9 250 
30.4 9 250 
34.8 9 250 
20.2 9 150 
23.7 9 150 
110 1,200 21 16 15 Fixed 3,240 1953 17.8 9 200 
110 600 24 19 
360 24 16 
110 600 15 19 
110 600 15 19 
110 600 10 18 
110 600 10 17 
110 600 10 15 
110 1,200 38 15 
110 600 10 17 
100 600 8 16 
110 600 9 17 
110 600 16 27 
110 360 16 27 
80 320 11 18 
110 600 11 21 
110 600 11 19 
110 600 9 17 
110 600 11 19 
110 600 8 15 
110 600 9 16 
110 600 11 22 
110 600 8 18 
110 600 7 17 
110 600 6 18 
110 600 9 18 
110 600 7 17 
110 600 8 17 
110 600 12 22 
500 12 16 
56 400 38 13 
56 400 38 13 
56 
56 
10 Movable 1,725 1938 
10 
12 Movable 1,296 1939 
12 Movable 4,280 1940 
14 Movable 1,024 1938 
12 Movable 1,066 1938 
12 Movable 2,144 1936 
13 Fixed 4,434 1913 
14 Movable 1.350 1937 
13 Movable 921 1939 
12 Movable 1,099 1937 
11 Movable 1,203 1934 
11 
11 1922 
14 Movable 1,343 1939 
13 Movable 1,066 1939 
13 Movable 849 1938 
13 Movable 1,278 1937 
12 Movable 763 1937 
13 Movable 811 1937 
14 Movable 935 1937 
12 Movable 940 1937 
13 Movable 893 1936 
13 Movable 682 1936 
12 Movable 1,619 1935 
13 Movable 1,367 1935 
14 Movable 365 1938 
13 Movable 822 1930 
15 1948 
8 Fixed 574 1932 
10 1917 
400 25 14 10 Movable 188 1956 
400 49 16 14 Fixed 3,584 1963 
38.5 9 200 
32.0 9 200 
27.8 9 200 
23.7 9 NS 
18.3 9 NS 
21.0 9 NS 
46.3 9 NS 
26.6 9 NS 
20.1 9 NS 
25.7 9 NS 
10.4 9 NS 
29.2 9 NS 
34.2 9 NS 
26.3 9 NS 
32.1 9 NS 
32.8 9 NS 
31.3 9 NS 
23.3 9 NS 
11.8 9 NS 
14.2 9 NS 
9.6 9 NS 
14.7 9 NS 
44.1 9 NS 
18.3 9 NS 
32.4 9 NS 
5.7 9 NS 
0.6 9 100 
3.8 9 100 
C-4

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Canurnity of Length for Narmal Length Year Length Depth Width 
Poject Mouth in Vkicinity Chamber Width Pool Level Upper Lower Type1 (feet) Opened (miles) (foeet) (eeOt) 
Mosnoala River, PA 
and WV 
Locks and Dam No. 2 
Locks and DamNo. 3 
Locks and Dam No. 4 
Maxwell LIcks and Dam 
Locks and Dam No. 7 
Locks and Dam No. 8 
Morgantown Lock and Dam 
Hildebrand Lock and Dam 
Opekisks Lock and Dam 
Ohio River 
Locks and Dam No. 53 
Locks and Dam No. 52 
Smithland Locks and Dam 
Uniontown Locks and Dam 
Newburgh Locks and Dam 
Camelta Locks and Dam 
McAlpine Locks and Dam 
Markland Locks and Dam 
Captain Anthony Meldabl 
Locks and Dam 
Oreemnp Locks and Dam 
Gallipolis Locks and Dam 
Racine Locks andDam 
Belleville Locks and Dam 
Willow Island Locks 
and Dam 
Hannibal Locks and Dam 
Pike Iland Locks and Dam 
New Cumberland Locks 
and Dam 
Motgacnry Island Locks 
and Dam 
DashfildLso cks and Dam 
Emswoath Locks and Dam 
Okechoboo Waterway, FL 
St. Lucle Lock and Dam 
Moore Haven Lock 
Orta Lock and Dam 
W. P. Pranklin Lock and 
Coerol Stmructre 
Old River, LA 
Old River Lock 
11.2 Braddock, PA 
23.8 Blisabeth, PA 
41.5 Mmmsan, PA 
61.2 Maxwell, PA 
85.0 Oeensbaro, PA 
90.8 Pbit Marion, PA 
102.0 Margntown, WV 
108.0 Morantown, WV 
115.4 Margantown, WV 
184 Mound City, IL 
42.1 Brockport, L 
353 Smithland, KY 
135.0 Uniontown, KY 
204.9 Newbargh, IN 
2603 Cannelto, IN 
374.2 Louisville, KY 
4495 Markland, IN 
544.8 Chilo, OH 
640.0 GOeenup, KY 
701.8 Hogan, WV 
743.5 Ltat Falls, OH 
777.1 Rodsville, OH 
8193 Waverly, WV 
854.6 New Martinsvilo 
,WV 
896.7 Warwood, WV 
926.6 Stratton, OH 
9493 Industry, PA 
967.7 Olenwillard, PA 
974.8 Emswcrth, PA 
15.1 Stuat, FL 
78.0 Moore Havn, PL 
93.6 LaBell, PFL 
121A PoFtMyers,FL 
304.0 Simnmsport, LA 
56 
110 
56 
56 
56 
56 
84 
84 
56 
56 
84 
84 
84 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
56 
110 
56 
50 
50 
50 
56 
360 9 
720 9 
360 8 
720 8 
360 17 
720 17 
720 20 
720 20 
360 15 
360 19 
600 17 
600 21 
600 22 
600 12 
1,200 12 
600 12 
1,200 12 
1,200 22 
1,200 22 
1,200 22 
600 22 
1,200 16 
600 16 
1,200 25 
600 25 
1,200 37 
600 37 
360 37 
1,200 35 
600 35 
1,200 30 
600 30 
1,200 30 
600 30 
600 23 
360 23 
1,200 22 
600 22 
1,200 22 
600 22 
1,200 20 
600 20 
1,200 21 
600 21 
1,200 21 
600 21 
1,o00 21 
600 21 
600 18 
360 18 
600 10 
360 10 
600 18 
360 18 
250 13 
250 2 
250 11 
400 3 
16 
16 
12 
12 
20 
20 
21 
21 
11 
15 
18 
14 
18 
15 
15 
15 
15 
34 
34 
34 
34 
32 
32 
38 
38 
49 
19 
19 
50 
50 
45 
45 
45 
45 
18 
18 
37 
37 
37 
37 
35 
35 
38 
38 
17 
17 
17 
17 
16 
16 
13 
13 
17 
16 
14 
10 
12 
13 
16 Fixed 748 1951 
16 195321 
12 FPxed 670 1907 
12 19071 
11 Movable 535 1932 
11 193221 
15 Movable 460 1964 
15 1964 
10 Fixed 610 192521 
10 Movable 560 192521
/ 2 
2 
15 Movable 410 1950 
15 Movable 530 1959 
14 Movable366 1964 7.0 
10 Movable 3.978 1929 
10 Temporary Lock 1980 
11 Movable 3,073 1928 
11 Temporary Lock 1969 
12 Movable 3,560 1980 
12 
12 Movable 3,516 1975 
12 
16 Movable 2,272 1975 
16 
13 Movable 1,965 1972 
13 
12 Movable 8,627 1961 
11 1921 
11 1930 
15 Movable 1,395 1963 
15 1963 
15 Movable 1,756 1962 
15 1962 
15 Movable 1,287 1962 
15 
15 Movable 1,132 1937 
15 
15 Movable 1,202 1970 
15 
15 Movablel,206 1969 36.4 
15 
15 Movable 1,128 1973 
15 
17 Movable 1,098 1972 
17 
18 Movable 1.306 1965 
18 
15 Movable 1.315 1961 
15 
15 Movable 1379 1936 
15 
18 Fixed 1,585 1929 
18 
13 Movable 1.717 1921 
13 
12 Movable 170 1941 
11 Noas 1953 
11 Movable 104 1937 
- Movable 1,150 1965 
75 1.200 35 11 11 Nae 
12.6 9 300 
17.7 9 300 
19.7 9 300 
23.8 9 300 
5.8 9 300 
11.2 9 300 
6.0 9 300 
7.4 9 300 
9 300 
23.7 9 300 
35.8 9 300 
99.7 9 300 
69.9 9 300 
55.4 9 300 
116.3 9 400 
75.3 9 300 
95.3 9 300 
9 300 
95,2 9 300 
61.8 9 300 
41.7 9 300 
33.6 9 300 
9 300 
35.3 9 1,000 
36.0 9 300 
29.9 9 300 . 
22.7 9 300 
18.4 9 300 
7.1 9 300 
6.2 9 300 
15.1 8 80 
15.6 8 90 
15.6 8 90 
7.9 8 90 
1963 12 125 
C-5

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Type1 
l (feet) Opened (miles) (feet) (feet) 
Ouchita and Black Rivers, 
AR & LA 
Jonesville Lock and Dam 
(Black River) 
Columbia Lock and Dam 
(Ouachita River) 
Calion Lock 
(Ouachita River) 
Felsenthal Lock 
(Ouachita River) 
lParl River, MS and LA 
Lock 1 
Lock 2 
Lock 3 
Red River Watrway 
Lock 1 
Sacranento River, CA 
Barge Canal Lock 
25.0 Jonesville, LA 
117.2 Columbia, LA 
281.7 
226.8 
29.417 Iarl River, LA 
40.717 Bush, LA 
43.917 Sun, LA 
43.8 
42.8 West Sacramento, 86 
CA 
84 600 30 18 14 Movable 450 1972 
84 600 18 18 13 Fixed 
92.2 9 100 
400 1972 106.2 9 100 
84 600 12 18 13 Movable 350 1984 
84 600 13 18 13 Movable 350 1984 
65 
65 
65 
310 26.7 
310 15 
310 11 
10 
10 
10 
10 None 
10 None 
10 None 
84 685 38 22 13 Fixed 
600 13 13 None 
1951 
1951 
1951 
50.3 9 100 
55.2 9 100 
11.1 7 80 
3.2 7 80 
13.2 7 80 
550 1984 44.2 9 200 
1961 1.5 13 120 
Snake River, WA 
Ice Harbor Lock and Dam 
Little Goose Lock and Dam 
Lower Granite Lock and Dam 
Lower Monumental Lock and Dam 
St. Mary's River, MI 
South Canal: 
MacArthur Lock 
Poe Lock 
North Canal: 
Davis Lock 
Sabin Lock 
SavannahG, A 
New SavannahB luff Lock 
and Dam 
Tennessee River, TN, AL, 
MS, and KY18 
Kentucky Lock and Dam 
Pickwick Landing Lock 
and Dam 
Auxiliary Lock 
Main Lock 
Waterway Connecting 
Tombigbee andT ennessee 
Rivers, AL and MS 
Gainesville Lock and Dam 
Aliceville Lock and Dam 
Columbus Lock and Dam 
Aberdeen Lock and Dam 
Lock A and Spillway 
Lock B and Spillway 
Lock C and Spillway 
Lock D and Spillway 
Lock B and Spillway 
Bay SpringsL ock andD am 
Wilson Lock and Dam 
Main Lock 
Auxiliary Lock 
GeneraJl oe Wheeler Lock 
and Dam 
Main Lock 
Auxiliary Lock 
920 Pasco, WA 
703 Starbuck, WA 
1073 Pomeroy, WA 
41.6 Kahlotus, WA 
86 
86 
86 
86 
47.0 Sault Ste. Marie, 80 
MI 
47.0 Sault Ste. Marie, 110 
MI 
47.0 Sault Ste. Marie, 80 
MI 
47.0 Sault Ste. Marie, 80 
MI 
187.2 Augusta, GA 56 
22.4 Gilbertsville, KY 110 
206.7 Hamburg, TN 110 
206.7 Hamburg, TN 110 
49.1 Gainesville, AL 110 
89.8 Aliceville, AL 110 
117.6 Columbus, MS 110 
140.4 Aberdeen, MS 110 
154.1 Amory, MS 110 
1593 Smithville, AL 110 
174.0 Pulton, MS 110 
181.4 Fulton, MS 110 
189.7 Belmont, MS 110 
194.9 Tupelo, MS 110 
259.4 PlorenceA, L 110 
259.4 Florence, AL 60 
274.9 Plorence, AL 110 
274.9 Rorence, AL 60 
675 89 
675 93 
675 93 
675 94 
15 
15 
15 
15 
800 22 31 
1,200 22 32 
1,350 22 24 
1,350 22 24 
15 Movable 1961 14 
15 Movable 1970 14 
15 Movable 1975 14 
15 Movable 1969 14 
31 Nne 
32 None 
23 None 
23 None 
1943 
1968 
1914 
1919 
360 15 14 12 Movable 360 1936 
600 56 11 13 Taintcr 7,976 1944 
600 55 10 13 Bulkhead 7,385 1937 
1,000 55 10 13 Bulkhead 7,385 1984 
600 36 
600 27 
600 27 
600 27 
600 30 
600 25 
600 25 
600 30 
600 30 
600 84 
15 
15 
15 
15 
15 
18 
18 
18 
18 
18 
15 Movable 15,460 1978 
15 Movable 14,790 1979 
15 Movable 10,040 1981 
15 Movable 10,640 1984 
15 Movable - 1985 
18 Movable -- 1985 
18 Movable - 1985 
18 Movable - 1985 
18 Movable - 1985 
18 None 10,640 1985 
600 94 13 13 Bulkhead 3,728 1959 
292 94 11 11 Bulkhead 3,728 1927 
600 48 13 13 Bulkhead 5,738 1963 
400 48 15 13 Bulkhead 5,738 1962 
250 
250 
250 
250 
27 
16.2 9 90 
184.3 9 300 
52.7 9 300 
52.7 9 300 
49.1 9 300 
40.7 9 300 
27.8 9 300 
22.8 9 300 
13.7 9 300 
14.7 9 300 
7.4 9 300 
8.3 9 300 
5.2 9 300 
64.5 9 300 
15.5 9 300 
15.5 9 300 
74.1 9 300 
74.1 9 300 
C-6

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1989 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Month a Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
Waterway Connecting 
Tambighbee and Tennessee 
Rivers, AL and MS (continued) 
Guriterville Lock and Dam 
Main Lock 
Auxliary Lock 
Nickajack Lock and Dam 
Chickamaugsa Lock and Dam 
Watts Bar Lock and Dam 
Port Loudon Lock and Dam 
Melton Hill Lock and Dam 
(Cinch River) 
Willamette River at 
Willamutte Falls, OR 
Lock No. 1 
Lock No. 2 
Lock No. 3 
Lock No. 4 
Guard Lock 
349.0 Gunsmville, AL 
349.0 Guntersville, AL 
424.7 Ohttanooa, TN 
471.0 Catanooga, TN 
529.9 Bweederon. TN 
6023 Lenoir City, TN 
23.1 Kingston,TN 
600 39 13 
400 39 13 
600 39 13 
360 49 10 
360 58 12 
360 72 12 
75 400 54 13 
26.0 Oregon City, OR 40 210 20 
26.0 Oregon City, OR 40 210 10 
26.0 Oregon City, OR 40 210 10 
26.0 Oregon City, OR 40 210 10 
26.4 Oregon City, OR 40 210 10 
13 Tainter 3,837 1965 
12 Taintor 3,837 1939 
11 Tainter 3,763 1967 
14 Taintnr 5,654 1940 
12 Tainer 2,646 1942 
12 Tairter 3,687 1943 
13 Tainter 1,072 1963 
8 None 
8 None 
8 None 
8 None 
8 None 
1872 
1872 
1872 
1872 
1872 
75.7 9 300 
75.7 9 300 
46.3 9 300 
58.9 9 300 
72.4 9 300 
49.8 9 300 
38.2 9 30019 
6 150 
.4 
23.6 6 NS 
1 
Fixed; crest without gates or other facility to control streamflow. Movable; includes any type of crest gates, tainter gates, wickets, or others to control streamflow. 
2Above mouth of Mobile River. 
3 
includes length of earth dikes. 
4
From mouth of Apalachicola River. 
5
From mouth of Chattahoochee River. 
6
Above Norfolk, VA. 
7
With reference to mean low water, or low mean Gulf as case may be. 
8
From Gulf Intracoastal Waterway. 
9 
Average high and low water conditions, lift varying widely, depending on tides and river stages. 
10From foot of Government Street, Mobile, AL. 
1 1
From mouth of St. Johns River. 
12Above Head of Passes. 
From New Orleans, LA. 
1 4 
Salt water barrier in down position. Will clear 15-foot vessels in normal position. 
1 5
Above the Ohio River. 1 6 
Channel completed to depth of 6.5 feet. 
17From mouth of West Pearl River. 
18Temesse River locks operated by the Corps, dams operated by the Tennessee Valley Authority. 
1 9 
300-foot width from lock to mouth of Clinch River and 175-foot width upstream from lock to Clinton, TN. 
2 0
Dates shown represent replacement structures. 
21Dates shown represent reconstruction for locks and dams Nos. 2.8 inclusive. 
Da was rebuilt in 1959. 
Old 110 X 358 lock replaced in 1957. 
Inoperable, caretaker status September 7,1982. 
Inoperable, caretaker status October 1, 1981. 
* Includes length of left and right embankments 
** Includes length of left embankment 
C-7

APPENDIX D 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Agat Small Boat Harbor, Guam (Sec 107) ................... 
AIWW - Replacement of Federal Hwy Bridges in NC..... 
Baltimore Harbor (50 foot), MD & VA............................ 
Barnegat Inlet, NJ ........................................... 
Bonneville Navigation Lock, OR & WA......................... 
Brandon Road Lock and Dam, Illinois Waterway, IL ....... 
Calumet Harbor and River, IL and IN................................. 
Calumet-Sag. Mod., Illinois Waterway, IL and IN, Part 1. 
Channel to Newport News, VA (1965 Mod.) .................. 
Channel to Newport News, VA (1986 Mod.) ................... 
Charleston Harbor, SC ..................................... .... 
Corpus Christi Ship Channel, TX ..................................... 
Dashields L/D, Ohio River, PA........................................... 
Delaware River in the Vicinity of Camden, NJ ................ 
Emsworth Locks and Dams, Ohio River, PA ................... 
Falls of the Ohio National Wildlife Conservation Area, 
IN and KY ..................................... ... ........... 
Finney Creek at Wachapreague, VW.................................. 
Freeport Harbor, TX ...................................... ...... 
Gallipolis Locks and Dam, Ohio River............................... 
Grays Landing Lock & Dam (Lock & Dam 7) 
Monongahela River, PA........................................ 
Jonesport Harbor, ME .................................... ..... 
Kaskaskia River, IL.......................................................... 
Kill Van Kull - Newark Bay, NJ and NY ......................... 
Krebs Lake, M S (Sec 107)................................. ........... 
LaGrange Lock and Dam, Illinois Waterway, IL ............... 
Lake Erie, Sturgeon Point, Evans, NY (Sec 107) ............... 
Laupahoehoe Harbor, Hawaii, HI ..................................... 
Little Rock Slackwater Harbor, Little Rock, AR................ 
Lock and Dams 3, 5A, 6,7,8 and 9, MN, WI and IA .......... 
Lock and Dam 17, IL ...................................... ..... 
1987 
1974 
1987 
1985 
1985 
1983 
1988 
1955 
1967 
1987 
1988 
1972 
1986 
1987 
1980 
1984 
1988 
1987 
1985 
1986 
1987 
1966 
1986 
1983 
1986 
1988 
1988 
1987 
1989 
1989 
1989 Dredging and breakwater 
1986 1 Indefinite Streambank Protection 
1990 Deepdraft channel deepening 
1992 Jetty realignment and dredging 
1993 New larger lock 
1988 Major rehabilitation of lock and 
dam 
1989 1990 Major rehabilitation of 
breakwaters 
1968 Indefinite Channel improvements and 
relocation 
1968 Indefinite Deferred anchorage construction 
1989 1988 Dredge 50 ft. Channel 
1994 Dredging and channel 
wideningand deepening 
1990 Dredging 
1990 Major rehabilitation of ocks and 
dams 
1088 1988 Dredging 
1985 Major rehabilitation of lock and 
dam 
1988 
1974 
1983 
1988 
1987 
Indefinite Protection of a National Natural 
Landmark 
1988 Dredging 
1992 Dredging, jetty construction, and 
recreation 
1995 Replacement of existing locks 
and major rehabilitation of the 
dam 
1995 Construct new lock & dam to 
replace existing lock & dam 7 
1990 Breakwater, dredging of new 
channel and anchorage 
1986 Lock, dam and channel 
1989 Deepdraft channel - widening 
and deepening 
1984 Dredging, navigation channel 
1990 Major Rehabilitation of Lock and 
Dam 
1989 Breakwaters, dredging 
1988 Breakwater 
1988 Dredging, deepening, channel 
and turning basin 
2000 Major rehabilitation of 
electrical/mechanical systems 
1992 Major maintenance of lock and 
dam

APPENDIX D (Continued) 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Lock and Dam 18, IA................... ...... 
Lock and Dam 20, MO ....................................... 
Lock and Dam 21, IL ..................................... ...... 
Lock and Dam 22, MO ..................................... ..... 
Marseilles Dam, Illinois Waterway, IL............................... 
McClellan-Kerr Arkansas River Navigation System, AR .. 
Melvin Price Lock and Dam, MO..................................... 
Mississippi River between Ohio and Missouri Rivers 
IL and MO................. ................ 
Mississippi River, Gulf Outlet, LA ................................... 
Mississippi River, Ship Channel, Gulf to 
Baton Rouge, LA .................................................... 
Missouri River, Sioux City, IA to mouth .......................... 
Montgomery Locks & Dams, Ohio River, PA.................... 
Moriches Inlet, NY ...................................... ....... 
Mouth of Colorado River, TX (Gulf Intracoastal 
W aterway) ....................................... ................ 
Nawiliwili Harbor, Kauai, HI ........................................... 
New York Harbor, NY and NJ............................................ 
Newburgh Locks & Dam, Ohio River, IN and KY............. 
Norfolk Harbor Channel, VA (1965 Mod.)......................... 
Norfolk Harbor Channel, VA (1986 Mod) ....................... 
Norfolk Harbor, Thimble Shoal Channel, VA................... 
Oakland Harbor, CA ...................................... ...... 
1989 
1986 
1987 
1987 
1985 
1963 
1974 
1910 
1958 
1987 
1912 
1983 
1987 
1984 
1985 
1976 
1965 
1966 
1987 
1987 
1987 
Ocean City Harbor and Inlet, MD....................................... 1983 
Ouachita and Black River, AR and LA............................ 1964 
Norfolk Harbor Channel, VA (1986 mod) ........................ 
Peoria Lock and Dam, Illinois Waterway, IL ................... 
Port Everglades Harbor, FL ........................................... 
Port Hueneme, CA ........................................... 
Port Ontario Harbor, NY........................................ 
Portsmouth Harbor & Piscataqua River, ME and NH ........ 
Red River WW, Mississippi River to Shreveport, LA........ 
1987 
1986 
1979 
1970 
1987 
1989 
1974 
1989 
1968 
1990 
1993 Major maintenance of lock and 
daml 
1990 Major Rehabilitation of Lock and 
Dam 
1989 Major Rehabilitation of Lock and 
Dam 
1989 Major Rehabilitation of Lock and 
Dam 
1989 Major rehabilitation of lock and 
dam 
1989 Locks and dams 
1992 Replacement 
2000 Regulating works 
1984 Dredging and jetties 
1987 2 Indefinite 3 Dredging 55-foot channel 
1980 Indefinite Navigation and bank stabilization 
complete. Fish and Wildlife 
mitigation authorized by Sec 
601 of WRDA of 1986 (P.L. 
99-0662) 
1987 Major rehabilitation of locks & 
dams 
1989 Dredging and jetty repair 
1987 
Incremental 
1969 
1967 
1936 
1984 
1989 
1972 
19842 
1992 Breakwaters, dredging, and 
recreation 
1987 Breakwater repair 
Indefinite Collection and removal of drift 
1974 Replacement of locks and dams 
46 and 47 
Indefinite Deferred anchorage const. 
1988 Dredge 50 ft. channel 
1988 Dredge outbound element 
1994 Channel deepening and widening 
turning basin 
1985 Rehabilitation of south jetty 
1994 Replacement of six locks and 
dams, channel deepening to 9 
feet and realignment 
1989 Dredge 50 ft. outbound element 
1990 Major Rehabilitation of lock and 
dam 
1987 Dredging 
1987 Dredging 
1988 Breakwaters, channel excavation 
1992 Dredging (widening channel) 
Indefinite Lock and dam construction. 
Channel improvement and 
realignment 
D-2

APPENDIX D (Continued) 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1989 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Richmond Harbor, CA ..................................... .... 
Sacramento River Deep Water Ship Channel, CA.............. 
St. George, AK.................................. .......... 
St. Paul, AK ................. .................. 
San Diego River and Mission Bay, CA............................... 
San Francisco Bay to Stockton, VA (John F. Baldwin 
and Stockton Ship Channels)...................... ........... 
Savannah Harbor Widening, GA ...................................... 
Shallow Creek, MD (Sec 107) .......................................... 
Smith Island, M D (Sec 107) ............................... ........... 
Smithland Locks and Dam, IL, IN, and KY ..................... 
Tampa Harbor, FL (Main Channel) .................................. 
Thimble Shoal Channel, VA ............................................ 
Tenn River, Decatur Morgan County Port, AL.................. 
Tombigbee River, Columbus Port, MS (Sec 107) ............. 
1985 
1986 
1989 
1989 
1948 
1971 
1990 
1987 
1982 
1971 
1976 
1987 
1988 
1987 
Tongue Point, OR ............................................................... 1989 
Wallisville Lake, TX ..................................... 1967 
Zippel Bay, Lake of the Woods County, MN .................. 1986 
1982 
1980 
1989 
1987 
1994 Channel deepening and turning 
basin 
1994 Deep draft channel, widening and 
deepending 
1990 Dredging 
1990 Dredging and breakwater 
Indefinite Dredging and breakwater 
Indefinite Deep draft channel, widening, 
deepening and dredging 
1991 Widening channel 
1988 Dredging 
1983 Channel cut with breakwater 
1987 Replacement of existing locks 
and dams 50 and 51 
1987 Dredging 
1989 Dredge 50 ft. outbound element 
1989 Channel excavation 
1989 Navigation channels & turning 
basin 
1990 Dredging 
Indefinite Multipurpose lake (navigation, 
salinity control, water supply, 
fish & wildlife, & 
recreational) 
1988 Breakwaters and Jetties 
1 Walter Jones and Joseph P. Knapp completed; Core Creek has been funded for initiation of construction; Hobucken has been 
funded for initiation of design; Fairfield has not been funded 
2 Phase I, forty-five foot channel to New Orleans, LA. Forty-five foot channel to Mile 181 (Donaldsonville, LA) placed in 
useful operation in 1988. 
3 Awaiting further LCA's to extend project to Baton Rouge, LA, and to go deeper than 45 feet. 
4 Lock and Dam No. 1 placed in useful opeation in 1984. Construction is continuing on Lock and Dam Nos 2 and 3, and has not 
been initiatied on Lock & Dam Nos 4 and 5. 
D-3

APPENDIX E 
MULTIPURPOSE PROJECTS INCLUDING POWER 
OPERABLE SEPTEMBER 30, 1989 
FloodC ontrol 
and/or 
Total Nay. Feature 
Storage Placed Initial Existing Scheduled Ultima 
Conmunity Capability iauseful Power Installation Installation Installation Project cHeight Length 
Poject River inVicinity (acre-feot) OperationCY In FY (KW) (KW) (KW) Functions Type 
2 
(feet) (fret) 
Albeni Falls, ID Pend Oreille 
Allatoaom Lake,GA Etowah 
BarkleyDan & Cumberland 
Lake Barkeley, KY KY 
& TN 
Beaver Lake, AR Whit 
Big BaendD am (Lake 
Sharpel), SD Missouri 
Blakely Mountain Ouachita 
Dam-lala 
Ouachita, AR 
Bo neville L&D Columbia 
Lake Bonnoville, 
OR & WA 
Broken Bow Lake, Mountain Fork 
OK 
Buford Dam, Chattahoochee 
Lanier, GA 
Bull Shoals Lake White 
AR & MO 
COarene Cannon Salt 
Dam 
Carters Dam, GA Coosawatte 
Center Hill Lake, Caney Fork 
TN 
CLeatham L&D, TN Cumberland 
Chief Joseph Dam Columbia 
(Rufus Woods 
Lake),WA 
Clarks Hill Lake Savannah 
GA & SC 
Cooper River, Santee 
Charleston 
Harbor, SC 
Cordell Hull L&D, Cumberland 
TN 
Cougar Lake, OR S. Fork McKenzic 
Dale Hollow Lake, Obey 
TN & KY 
Dardanrlle L&D, Arkansas 
AR 
DeGray Lake, AR Caddo 
DenisonDamn(Lake Red 
Texamna), TX & 
OK 
Detroit Lake, OR, North Santiam 
including Big 
Cliff Lake, OR 
Dworshak Dam N. Fork, 
& Reservoir, Clearwaer 
ID 
Eufaula Lake, OK Canadian 
Fort Gibson Grand (Neosho) 
Lake 
Fort Peck Lake, Missouri 
MT 
Fort Randal Dam Missouri 
(Lake Francis 
Case), SD 
Garrison Dam Missouri 
(Lake 
Sakakawea), 
ND 
Gavis Point Damn Missouri 
(Lewis & Clark 
Lake), SD & NE 
Green Peter Middle Santiam 
Lakc,OR, including 
Foster Lake, OR 
Grees Ferry Little Red 
Lake, AR 
Harry S. Truman 'Osap 
Dam & Res. 
Hartwell Lake, Savannah 
GA & SC 
Hills Creek Lake, Middle Fork 
OR Wilamett 
IceH arbor L&D 
(Lake 
Sacajawea), WA 
Snake 
Newport,WA 1,153,000 1952 1955 42,600 
Caranville,GA 670,000 1950 1950 74,000 
Frand Rivers, 2,082,000 1964 1966 130,000 
Eureka Springs, 
ChanberlainSD 
Mt. Pine, AR 
1,952,000 
1,883,000 
2,768,000 
1963 1965 
1964 1965 
1953 1956 
42,600 NFPR C 90 1,055 
74,000 FPRW C 190 1,250 
130,000 NPFR CE 157 9,959 
112,000 FPSR CE 228 2,575 
468,000 FPRIW E 95 10,570 
75,000 FPRW E 235 1,100 
112,000 
468,000 
75,000 
Bonnevile,OR 537,000 1938 1938 1,145,700 
Broken Bow, 
OK 
Buford, GA 
MountainHome 
AR 
Perry, MO 
Carters, GA 
Lancaster,TN 
Ashland City, TN 
Bridgeport, WA 
1,368,230 
2,554,000 
5,408,000 
1,428,000 
472,756 
2,092,000 
104,000 
593,000 
1968 1970 
1956 1957 
1952 1953 
1983 1985 
1975 1975 
1948 1951 
1952 1958 
1955 1956 
100,000 
86,000 
340,000 
58,000 
500,000 
135,000 
36,000 
2,457,384 
Augusta, GA 2,900,000 1952 1953 280,000 
St. Stephen, SC 2,560,000 N/A 1985 84,000 
Carthage, TN 
Blue River, OR 
Celina, TN 
Dardanelle, AR 
Arkadelphia, AR 
Denison, TX 
310,900 
219,000 
1,706,000 
486,200 
831,900 
5,312,300 
1973 1974 
1963 1964 
1943 1949 
1969 1965 
1969 1972 
1944 1945 
100,000 
25,000 
54,000 
124,000 
68,000 
70,000 
Mill City, OR 461,000 1953 1954 118,000 
OrofrinoI,D 3,453,000 1972 1973 400,000 
Eufaula, OK 3,825,400 1964 1964 
Ft. Gibson, OK 1,284,400 1949 1953 
Glasglow, MT 18,909,000 1938 1944 
Lake Andes, SD 5,574,000 1953 1954 
Riverdale, ND 24,137,000 
Yanktan, SD 
90,000 
45,000 
185,250 
320,000 
1954 1956 430,000 
504,000 1956 1957 100,000 
Sweet Home, OR 491,000 
Heber Spings 
Warsaw, MO 
Hartwell, GA 
Oakridge, OR 
Pasco, WA 
2,844,000 
5,202,000 
2,842,700 
356,000 
1967 1967 100,000 
1962 1964 
1982 1982(4) 
1961 1962 
1961 1962 
96,000 
160,000 
344,000 
30,000 
417,000 1962 1962 603,000 
1,145,700 NPR C 122 2,690 
100,000 FPWSR E 225 2,750 
86,000 NFPW E 192 5,400 
340,000 FPR C 258 2,256 
58,000 FNPRSW CE 138 1,700 
500,000 FPRW ER 450 1,950 
135,000 FPR CE 250 2,160 
36,000 NPR C 75 801 
2,457,384 PIR C 230 5,998 
280,000 NFPRSW CE 200 5,680 
84,000 NPW CE 86 876 
100,000 NPR CE 93 1,306 
64,600 NFPRI ER 445 1,738 
54,000 FPR C 200 1,717 
124,000 NPR C 68 2,683 
108,000 FNPRS E 243 3,400 
175,000 FPRSN E 165 17,200 
118,000 NFPRI C 382 1,528 
1,060,000 PNFR C 717 3,300 
90,000 ENPS E 114 3,200 
67,500 FP CE 110 2,990 
185,250 NFPRIW E 251 21,026 
320,000 NFPRIW E 165 10,700 
430,000 NFPRIW E 210 11,300 
100,000 NFPRIW E 74 8,700 
100,000 PFNIR C 340 1,380 
96,000 FPRS C 243 1,704 
160,000 FPRW CE 96 5,000 
344,000 NFPRS (E 204 17,852 
30,000 NFPRI GE 304 2,150 
603,000 NPRI CE 130 2,790

APPENDIX E (Continued) 
MULTIPUROPSE PROJECTS INCLUDING POWER 
OPERABLE SEPTEMBER 30, 1989 
Flood Control 
andlar 
Total Nay. Featuze 
Storae Plaed Initial Existing Scheduled Ultimate 
Community Capability in useful Power Istallatimn Installation Installation Project Length Height 
Project River in Vicinity (ac-feet) 
1 
OperationCmY In FY (KW) (KW) (KW) Functions Type 
2 (feet) (bet) 
Gavim PointDam Missouri 
(Lewis & Clark 
Lake), SD & NE 
Green hter Middle Santiam 
Lake,OR, including 
Foster Lake, OR 
Greers Ferry Little Red 
Lake, AR 
Hany S. Truman Osag 
Dam & Res. 
Hartwell Lake, Savannah 
GA & SC 
Hills Creek Lake, Middle Fork 
OR Wilamte 
Ice Harbor L&D Snake 
(Lake 
Sacajawea), WA 
Jim WoodruffDam Appalachicola 
(Lake Seminole), 
FL, GA & AL 
John Day L&D Columbia 
(Lake Umatilla), 
OR &WA 
John H. Kerr Roanoke 
Dam & 
Reservoir, NC 
& VA 
Robert F. Henry Alalmm 
L&D, AL 
J. ercy Priest Stones 
Dam & 
Reservoir, TN 
Keystone Lake, Arkansas 
OK 
Lake Greeson, AR Little Missouri 
Laurel River, KY Laurel 
Libby DamnL, ake Kooteni 
Koocanusa, MT 
Little Goose L&D Snake 
(Lake Bryan), WA 
Lookout Pbint Middle Fork 
Lake including Wilamntte 
Dexter Lake, OR 
Lost Crck Lake, Rogue 
OR 
Lower Granite Snake 
L&D, WA 
Lower Snake 
Manumental 
L&D (Lake 
Herbert G. 
West), WA 
McNary L&D Columbia 
(Lake Wallula) 
OR & WA 
Millers Ferry Alabama 
L&D, AL 
Nanpil River Nanpil River 
Hydropower, 
FPolnpeiF, SM 
New Melons Stanislaus 
Lake, CA
6 
Norfork Lake, AR North Fork 
& MO 
Oahe Dam (Lake Missouri 
Oahe), SD & ND 
Old Hickory L&D, Cumberland 
TN 
Ozark-Jeta Arkansas 
Taylor L&D, AR 
Philpott Lake, VA Roanoke 
Robert S. Kerr Arkansas 
L&D and 
Reservoir, OK 
Sam Raybum Dam Angelimn 
& Reservoir, TX 
St. Mary's River, Gscat Lakes 
MI 
YanktanS,D 
Sweet HomneO, R 491,000 
Heber Spings 
Warsaw, MO 
Hartwell, GA 
Oakridge, OR 
Puco, WA 
Chattahoochee, FL 367,300 
Rufus, OR 
504,000 1956 1957 100,000 
1967 1967 100,000 
2,844,000 
5,202,000 
2,842,700 
356,000 
1962 1964 
1982 1982(4) 
1961 1962 
1961 1962 
96,000 
160,000 
344,000 
30,000 
417,000 1962 1962 603,000 
1957 1957 30,000 
2,500,000 1968 1969 2,160,000 
Boydton, VA 2,750,300 1952 1953 204,000 
Benton, AL 234,200 1972 1975 68,000 
Nashville, TN 652,000 1967 1970 28,000 
Tulsa, OK 1,737,600 
Murfreesboro,AR 407,900 
London, KY 435,600 
Libby, MT 5,809,000 
Starbuck, WA 565,000 
Lowell, OR 483,000 
Trail, OR 
1964 1968 
1950 1950 
1973 1978 
1972 1975 
1970 1970 
1954 1955 
70,000 
25,500 
61,000 
525,000 
810,000 
135,000 
465,000 1977 1977 49,000 
Pomnroy, WA 484,000 1975 1975 810,000 
Kahlotus, WA 376,000 1969 1969 810,000 
Umatilla, OR 1,550,000 1953 1954 980,000 
Camden, AL 
Pohnpei, FSM 
331,8090 1969 1979 
1 1987 1988 
100,000 NFPRIW E 74 8,700 
100,000 PFNIR C 340 1,380 
96,000 FPRS C 243 1,704 
160,000 FPRW CE 96 5,000 
344,000 NFPRS CE 204 17,852 
30,000 NFPRI GE 304 2,150 
603,000 NPRI CE 130 2,790 
30,000 NPRW CE 67 6,150 
2,700,000 NPRFI CE 161 5,900 
204,000 FPRW CE 144 22,285 
68,000 NPRW CE 101 14,962 
28,000 FPRW CE 147 2,716 
70,000 FNPWS E 121 4,600 
25,500 FPRW C 183.5 941 
61,000 FPRW R 282 1,420 
840,000 FPR C 420 3,055 
810,000 NPRI E 160 2,670 
135,000 NFPRI CE 243 3,381 
49,000 DFPISWR CE 345 3,600 
810,000 NPRIF CE 146 3,200 
810,000 NPRI E 135 3,800 
1,754,000 NPRI CE 183 7,300 
75,000 
2,000 
Oakdale, CA 2,400,000 1978 1979 300,000 
Norfolk, AR 
Pierre, SD 
Hendersonville, 
TN 
OzarkAR 
Bassett, VA 
Sallisaw, OK 
Jasper, TX 
Sault Ste. Marie 
MI 
1,983,000 
23,337,000 
545,000 
148,400 
318,500 
522,700 
1943 1944 
1959 1962 
1954 1957 
1969 1973 
1951 1954 
1970 1971 
3,997,600 1965 1966 
--- 1855 1952 
80,550 
595,000 
100,000 
100,000 
14,000 
110,000 
52,000 
18,400 
75,000 NPRW CE 
2,000 P C 
90 11,380 
17 70 
300,000 FIPRW ER 625 1,560 
163,000 FPRS C 216 2,624 
595,000 NFPRIW E 245 9,300 
100,000 NPR CE 98 3,605 
100,000 NPR C 58 2,480 
14,000 FPR C 220 892 
110,000 NPR E 75 7,230 
52,000 FPWR CE 120 19,430 
18,400 NP Cantrol Gate 
E-2

APPENDIX E (Continued). 
MULTIPUROPSE PROJECTS INCLUDING POWER 
OPERABLE SEPTEMBER 30, 1989 
Food Control 
and/r 
Total Nay. Feature 
Storage Placed Initial Existing Scheduled Ultimate 
Cormmunity Capability in useful Power Installation Installation Installation Project Length Height 
Poject River in Vicinity (acre-fet)
1 
Operation CY In FY (KW) (KW) (KW) Functions Type
2 
(feet) (feet) 
Sam Raybum Dam Angeli Jasper, TX 3,997,000 1965 1966 52,000 52,000 FPWR CE 120 19,430 
& Reservoir, TX 
Snettiham, AK
7 
Spedol Juneau, AK 352,400 1973 46,700 27,0008 73,700 P C
9 
18 338 
Stockton Lake, MO Sac Stocktm, MO 1,674,000 1969 45,200 45,200 FPRW CE 128 5,100 
Table Rock Whie Branson, MO 3,462,000 1958 1959 200,000 200,000 FPR Ce 252 6,423 
Lake, AR & MO 
Tenkiller Lake, Illinois Gore, OK 1,230,800 1952 1953 40,000 40,000 PP E 197 3,000 
OK 
The Dalles LAD Columbia The Dalles, OR 53,000 1957 1957 1,806,800 1,806,800 NPR CR 300 8,875 
(Lake Cello), 
WA & OR 
Walter PFG. eorge Chattahooche Fort Gaines, GA 934,000 1963 1963 130,000 130,000 NPRW CE 114 13,585 
L&D, GA & FL 
Webber PFalls Arkansas Wevbbers Falls, OK 170,100 1970 1973 60,000 60,000 NP E 84 4,370 
L&D, OK 
West Point Chattahooche West Point, GA 604,500 1975 1975 73,375 108,375 FPRW CE 97 7,250 
Lake, AL & GA 
Whitney Lake, TX Brazos Whitney, TX 1,999,500 1953 1954 30,000 30,000 FPR CE 159 17,695 
Wolf Qeek Dam Cumberland Jamestown, KY 6,089,000 1950 1952 270,000 270,000 FPR CE 258 5,736 
Cumberland), KY 
1
Total of all storage functions, including inactive and dead storage to normal full pool level 
2: gravel; R: rock; C: concrete; E: earth 
4All units ae synchronized-to-line and two units have passed the pumrpbactke st. 
However, due to damaging effects to fish, no further pumping will be doane for their testing or operation until a solution to the problem is found. 
6
Being operated for the Department of Interior by the Bureau of Reclamation 
7 
Being operated by the Alaska Power Administartion 
8
Cratr Lak Unit 
9
Weir for Long Lake 
10Pormerly larks Hill Lake 
11Single Purpose Power. Special Appropriation By Congress 
Nomnclature for Project Functions 
D--Debria Control P--Power 
F--Flood Control R--Public Recreation Annual Attendance exceeding 5,000 
I--Irrigation S-Water Supply 
N--Navigation W--Fish and Wildlife (Federal or State) 
E-3

APPENDIX F 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER 
UNDER CONSTRUCTION, SEPTEMBER 30, 1989 
Nameplate Capacity 
Fiscal Scheduled Scheduled 
Year for for Scheduled Ultimate 
Project Started Operation Completion Functions Installation Installation 
Bonneville Second Powerhouse, OR and WA ............................ 1974 1881 1991 PR 558,200 558,200 
Clarence Cannon Dam, Salt River, MO.................................. 1966 1985 1990 FNPRSW 58,000 58,000 
Harry S. Truman Dam and Reservoir, 
Osage River, MO ........................... 1965 19821 19921 FRPW 160,000 160,000 
New Melones Lake, CA2 ................. .. .. ... .. ... .. . . . . . . . .. . . .... 1966 1979 Indefinite DFIPRW 300,000 300,000 
Richard B. Russell Dam and Lake, Savannah 
River, GA and SC .................................. 1975 1985 1991 FRP 600,000 600,000 
Cooper River, Charleston Hbr, SC................................... 1977 1985 1986 NWDP 84,000 84,000 
Snettisham, AK................... .................... 1967 1989 1989 P 73,700 27,000 
KEY 
D - 
F . 
I - 
N - 
P - 
R - 
S - 
W . 
Redevelopment 
Flood Control 
Irrigation 
Navigation 
Power 
Recreation 
Water Supply 
Fish and Wildlife 
1 All units are synchronized-to-line and two units have passed the pumpback test. However, due to damaging effects to fish, no further 
pumping will be done for either testing or operation until a solution to the problem is found. 
2 New Melones Lake was turned over to the Bureau of Reclamation for operation onNovember 20, 1979. Corps retains responsibility for 
facilities along the lower Stanisalaus River. Remaining construction consists of recreation facilities and minor feature closeouts. 
F-1

MAJOR FLOOD AND DAMAGES SUFFERED DURING FISCAL YEAR 1989 
(In Millions of Dollars) 
Month Location 
Lives 
Lost 
Damages 
Suffered 
Jan 89 
Feb 89 
Apr 89 
May 89 
May 89 
Jun 89 
Jun 89 
Jun 89 
Jun 89 
Subtotals 
Totals (All floods in U.S.) 
Utah 
Ohio, Tennessee and 
Lower Mississippi Valleys 
Tennessee 
Texas 
Virginia, Maryland and 
District of Columbia 
Texas, Louisiana and 
Mississippi 
Eastern United States 
Texas, Louisiana 
Mid-Atlantic 
12
*
6 
Extensive 
Flash Floods 
20 
11
1 
11
7 
54 
10 
500
* 
More than 540 
72 1,100 
* Exact dollar amounts not known, but damages are in the millions 
OTHER MAJOR WEATHER EVENTS AND DAMAGES 
Lives 
Event Number Lost 
Tropical Cyclones 11 58 
Tornadoes 570 32 
Drought 1 
Blizzards - Winter Storms 2 20 
Totals 884 110 
G-1 
Damages 
Suffered 
9.6 
0.6 
0.1 
10.3

FISCAL YEAR 1989 
FLOOD DAMAGES PREVENTED BY 
U.S. ARMY CORPS OF ENGINEERS 
BY REGION 
FY 1980 FY 1981 FY 1982 FY 1983 FY 1984 FY 1985 FY 1986 FY 1987 FY 1988 FY 1989 10-Year FY 1990 Percent 
Average 
1980-89 
New England 
Mid-Atlanti c 
Gulf & S. Atlantic 
Ohio 
Tennessee 
Great Lakes 
Upper Mississippi 
Souris-Red-Rainy 
Missouri 
Arkan sas-Red-White 
Lower Mississippi 
Rio Grande 
Texas and Gulf 
Colorado 
Great Basin 
California 
Columbia N. Pacific 
Alaska 
Hawaii 
75,911 
16,740 
28,086 
289,655
0 
9,594
0
0 
2.243 
108,025 
4,087,675 
46,260 
14,910 
117,761
0 
1,981,428 
514,257 
2,117 
4,254 
53,661 239,970 9,496 839,029 625 665 463,321 0 250 168,293 63,094 
24,171 10,419 25,703 2,486,292 18,823 357,665 30,340 26,450 24,802 302,140 16,607 
2,499 24,398 49,384 27,756 21,301 41,774 219,938 11,438 30,014 45,659 57,057 
231,431 188,802 207,363 556,603 268,796 633,658 172,866 63,538 285,510 289,822 248,699 
0 0 0 0 45 570 4,376 0 16,176 2,117 3,082 
9,842 27,836 5,856 24,593 30,107 28,071 51,245 9,587 24,982 22,207 16,849 
11,622 96,150 251,594 66,209 57,941 113,777 430,592 1,576 6,761 103,622 516,506 
0 0 2,700 1,314 1,721 18,966 52,015 411 68,814 14,594 7,156 
89,862 370,993 435,296 1,077,828 32,555 860,513 1,504,538 2,669 176,066 455,256 250,873 
11,617 55,960 161,010 88,788 168,558 174,737 996,615 161,923 186,727 211,396 456,041 
3,067 552,850 20,386,036 10,294,428 9,820,704 9,336,140 666,758 1,453,371 5,970,206 6,257,124 10,820,837 
889 2,526 29,918 98,419 127,698 87,139 113,621 21,528 2,755 53,075 42,531 
83,436 441,874 17,537 8,513 28,840 208,168 190,914 6,026 535,689 153,591 4,105,103 
0 0 13,000 90,630 14,300 0 0 0 0 23,569 0 
0 800 15,015 18,600 2,200 16,300 0 0 500 6,062 500 
680 307,013 1,075,869 102,360 72,800 13,910,920 154,858 98 4,770 1,761,080 9,500 
633,016 1,939,909 547,510 979,308 94,350 1,521,659 125,995 296,159 918,874 757,104 962,433 
4,473 4,741 4,885 5,055 6,846 6,828 17,000 0 8,000 5,994 0 
220 800 624 0 0 220 220 8,540 82 1,496 1,085 
7,298,916 1,160,486 4,272,241 23,238,796 16,766,085 10,768,210 27,317,770 5,195,212 2,063,314 8,260,978 10,634,201 17,577,953 
Region 
Ct 
of the 
10-Year 
Average 
37 
125 
86 
146 
76 
498 
49 
216 
173 
80 
2,673
0
8
1 
127
0 
73 
Total

DISTRIBUTION BY DISTRICT 
FLOOD DAMAGES PREVENTED BY CORPS OF ENGINEERS 
(IN THOUSANDS OF DOLLARS) 
District 
Vicksburg 
Memphis 
New Orleans 
St. Louis 
Kansas City 
Omaha 
Baltimore 
New York 
Norfolk 
Philadelphia 
Buffalo 
Chicago 
Detroit 
Rock Island 
St. Paul 
New England 
Alaska 
Portland 
Seattle 
Walla Walla 
Huntington 
Louisville 
Nashville 
Pittsburgh. 
Pacific Ocean 
Charleston 
Jacksonville 
Mobile 
Savannah 
Wilmington 
Sacramento 
Los Angeles 
San Francisco 
Albuquerque 
Fort Worth 
Galveston 
Little Rock 
Tulsa 
Total 
FY 1988 
$000 
1,059,110 
229,113 
4,681,183
0 
157,726 
18,340 
2,674 
18,975 
1,930 
1,223 
21,328 
5,750 
3,654 
732 
69,093 
250 
8,000 
899,537 
2,035 
17,302 
78,884 
146,160 
16,176 
60,466 
82 
1,434 
456
0 
850 
27,274 
5,270
0
0 
2,755 
470,269 
65,420 
25,553 
161,174 
8,260,978 
G-3

DISTRIBUTION BY DISTRICT 
FLOOD DAMAGES PREVENTED BY CORPS OF ENGINEERS 
(IN THOUSANDS OF DOLLARS) 
Damages Prevented 
by Corps-Controlled 
State Projects 
Alabama 
Alaska 
Arizona 
Arkansas 
California 
Colorado 
Connecticut 
Delaware 
Florida 
Georgia 
Hawaii and Guam 
Idaho 
Illinois 
Indiana 
Iowa 
Kansas 
Kentucky 
Louisiana 
Maine 
Maryland and 
District of Columbia 
Massachusetts 
Michigan 
Minnesota' 
Mississippi 
Missouri 
Montana 
Nebraska 
Nevada 
New Hampshire 
New Jersey 
New Mexico 
New York 
North Carolina 
North Dakota 
Ohio 
Oklahoma 
Oregon 
Pennsylvania 
Rhode Island 
South Carolina 
South Dakota 
Tennessee 
Texas 
Utah 
Vermont 
Virginia 
Washington 
West Virginia 
Wisconsin 
Wyoming 
Puerto Rico and 
Virgin Islands 
Total 
0 
8,000
0 
401,796 
4,770
0 
1,892
0 
456 
850 
82 
14,900 
7,925 
56,145 
76 
105,716 
96,767 
5,007,949
0
3 
237 
3,654 
14,989 
549,885 
117,726 
27 
17,427
00 
3,336 
2,755 
39,507 
18,362 
30,808 
89,977 
123,272 
840,765 
27,845
0 
1,434 
457 
9,651 
537,403 
500 
2,298 
11,243 
62,403 
18,592
0 
751
0 
8,232,186 
Damages Prevented 
by Corps-Controlled 
Emergency 
Operations 
000 
435
000000000 
5,000
000000 
00 
7,006
0000000000 
16,323
0000000000000
00 
28
0 
28,792 
Total Flood 
Damages Prevented 
by the Corps 
of Engineers 
000 
401,700 
4,770
0 
1,892
0 
456 
850 
82 
14,900 
7,925 
61,145 
76 
105,716 
96,767 
5,007,949
03 
237 
3,654 
21,995 
549,885 
117,726 
27 
17,427
00 
3,336 
2,755 
39,507 
18,362 
47,131 
89,977 
123,272 
840,765 
27,845
0 
1,434 
457 
9,651 
537,403 
500 
2,298 
11,243 
62,403 
18,592
0 
779
0 
8,260,978 
G-4

FISCAL YEAR 1989 
FLOOD DAMAGES SUFFERED 
(IN THOUSANDS OF DOLLARS) 
Lives Property Agricultural 
Location Lost Damage Losses 
Alabama 0 178 ** 
Alaska 0 6,000 ** 
Arizona 2 32,020 616 
Arkansas 4 2,320 ** 
California 0 35,538 3,200 
Colorado 0 481 ** 
Connecticut 0 800 ** 
Delaware 3 1,800 ** 
Florida 0 2,100 ** 
Georgia 0 1,782 ** 
Hawaii and Guam 1 3,382 ** 
Idaho 0 178 ** 
Illinois 0 * 1,800 
Indiana 0 716 ** 
Iowa 0 3,731 3,555 
Kansas 2 907 2,487 
Kentucky 4 27,401 44 
Louisiana 2 122,118 200,000 
Maine 0 3,200 ** 
Maryland and 5 1,800 ** 
District of Columbia 
Massachusetts 0 * ** 
Michigan 0 178 2 
Minnesota 0 17,600 ** 
Mississippi 2 3,636 ** 
Missouri 1 16,067 ** 
Montana 1 2,000 19 
Nebraska 9 21,842 8,130 
Nevada 0 23 ** 
New Hampshire 0 * ** 
New Jersey 2 1,800 ** 
New Mexico 0 2,378 ** 
New York 0 22,109 18,162 
North Carolina 4 18,120 1,952 
North Dakota 0 16,000 ** 
Ohio 4 62,240 ** 
Oklahoma 1 2,121 ** 
Oregon 0 82 16 
Pennsylvania 1 7,106 ** 
Rhode Island 0 * ** 
South Carolina 0 370 ** 
South Dakota 0 16 ** 
Tennessee 9 11,466 14 
Texas 15 340,746 352 
Utah 0 15,387 16 
Vermont 0 50 ** 
Virginia 6 21,312 18,051 
Washington 0 320 ** 
West Virginia 0 1,010 ** 
Wisconsin 0 160 ** 
Wyoming 0 1,602 ** 
Puerto Rico and 0 * ** 
Virgin Islands 
Total 72 823,421 257,383 
Total Losses (Property and Agricultural 1.1 Billion 
This table summarizes estimated values for flood events. Damage totals for major floods, especially those that 
occurred at the end of fiscal year, are frequently not well-refined in time for inclusion in this report. Lesser 
floods are not always consistently reported. These data are representative of state-by-state distribution of total 
flood damages, but may not represent the final loss value for each state. 
* Property damage unavailable but flooding occurred 
**Agricultural losses unavailable 
G-5

FISCAL YEAR 1989 
TROPICAL CYCLONES 
($ MILLION) 
Name 
Hurricane Joan' 
Tropical Storm Keith 
Tropical Storm Allison 
Tropical Storm Barry 
Hurricane Chantal 
Hurricane Dean 
Hurricane Erin 
Hurricane Felix 
Hurricane Gabrielle 
Hurricane Hugo 
Tropical Storm Iris 
C 
Month and Year 
Oct 1988 
Nov 1988 
Jun 1989 
Jul 1989 
Jul/Aug 1989 
Jul/Aug 1989 
Aug 1989 
Aug/Sep 1989 
Aug/Sep 1989 
Sep 1989 
Sep 1989 
Location 
Caribbean 
Nicaragua 
Caribbean 
Florida 
Gulf of Mexico 
Texas/Louisiana 
Atlantic 
Gulf of Mexico 
Texas 
Atlantic 
Atlantic 
Atlantic 
Atlantic 
Atlantic 
Leeward Islands 
Virgin Islands 
Puerto Rico 
South Carolina 
Atlantic 
U.S. Deaths 
0 
112 
134 
86 
26' 
U.S. Damage 
$3 million 
S500 million3 
S100 millions 
$9,000 million8 
1. In the South Caribbean 216 daths, 270 serious injuries, 122 missing, 211,500 homeless, total damages estimated near S2 billion. 
2. All deaths by drowning due to heavy rains. 
3. Most damage due to agricultural lossses and property damage as a result of flooding. 
4. Includes 3 deaths by drowning on U.S. Mainland, 7 confirmed and 3 presumed dead due to capsized vessel being used in the 
evacuation of a Gulf of Mexico oil rig. 
5. Most damage due to agrucultural losses and property damage as result of flooding. 
6. All daths occurred in various states along the New England coast. 
7. Inlcudes: 2 deaths on Puerto Rico, 3 deaths on U.S. Virgin Islands, 21 deaths on U.S. Mainland; these are NHC statistics, Red 
Cross statistics; 22 deaths on Puerto Rico, 7 deaths on U.S. Virgin Islands, 49 deaths on U.S. Mainland for a total number of 78 
deaths for U.S. and its territories. 
8. Includes: $2 billion in damages for Puerto Rico and the U.S. Virgin Islands, $7 billion for U.S. Mainland. An additional %.5 
billion in damages occurred on other Caribbean Islands.

POTENTIAL FLOOD DAMAGES IN THE UNITED STATES 
1979 1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 
Fiscal Year 
L1 
D Flood damages suffered 
Flood damages prevented 
Potential flood damages in the United States since Fiscal Year 1979. The potential damages for each year is the sum of the damages 
suffered and the damages prevented. The 1979-88 average is shown for comparison. 
rJ) 
hA 
Erio 
O
S0 
� 
.1
0
0
0 
'I
Ft 
O� 
r 1

ANNUAL REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1989 
INDEX 
The following abbreviations are used in the index 
LMK 
LMM 
LMN 
LMS 
MR+T 
MRK 
MRO 
NAB 
NAN 
NAO 
NAP 
NCB 
NCC 
NCD 
NCE 
NCR 
NCS 
NED 
VICKSBURG, MISS., DISTRICT 
MEMPHIS, TENN., DISTRICT 
NEW ORLEANS, IA., DISTRICT 
ST. LOUIS, MO., DISTRICT 
MISSISSIPPI RIVER AND 
TRIBUTARIES PROJECT 
KANSAS CITY, MO., DISTRICT 
OMAHA, NEBR, DISTRICT 
BALTIMORE, MD., DISTRICT 
NEW YORK, N.Y. DISTRICT 
NORFOLK, VA., DISTRICT 
PHILADELPHIA, PA., DISTRICT 
BUFFALO, N.Y., DISTRICT 
CHICAGO, ILL, DISTRICT 
MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MINN. 
DETROIT, MICH., DISTRICT 
ROCK ISLAND, ILL., DISTRICT 
ST. PAUL, MINN., DISTRICT 
NEW ENGLAND DIVISION 
NPA ALASKA DISTRICT 
A 
Aberdeen, Ohio (ORH) 17-22 
Aberdeen Creek, Va. (NAO) 5-19 
Abilene, Kans. (MRK) 27-16, 27-19 
Abiquiu Dam, N. Mex. (SWA) 32-4, 32-11, 32-13 
Absecon Inlet, N.J. (NAP) 3-2, 3-15, 3-19, 3-24 
Accotink Creek, Va. (NAB) 4-36 
Adams, Hossic River Basin, Mass. (NAN) 2-36 
Adams Creek, S.C. (SAN) 7-14 
Adams Levee, Ind. (Wabash River) (ORL) 16-21, 
16-26 
Addison, N.Y. (NAB) 4-14, 4-27 
Additional Features Entering Into Cost of Project 
(NCD) 25-1 
Adena, Ohio (Short Creek) (ORP) 18-21 
Adkin Branch, N.C. (SAW) 6-28 
Afono Area and Aoa Area, American Samoa (POD) 
36-11 
NPP 
NPS 
NPW 
ORD 
ORH 
ORL 
ORN 
ORP 
POD 
SAJ 
SAM 
SAN 
SAS 
SAW 
SPK 
SPL 
SPN 
SWA 
SWF 
SWG 
SWL 
SWT 
PORTLAND, OREG., DISTRICT 
SEATTLE WASH., DISTRICT 
WALLA WALLA, WASH., DISTRICT 
OHIO RIVER DIVISION 
HUNTINGTON, W. VA. DISTRICT 
LOUISVILLE, KY., DISTRICT 
NASHVILLE, TENN., DISTRICT 
PITTSBURGH, PA., DISTRICT 
PACIFIC OCEAN DIVISION 
JACKSONVILLE, FLA., DISTRICT 
MOBILE, ALA., DISTRICT 
CHARLESTON, S.C., DISTRICT 
SAVANNAH, GA., DISTRICT 
WILMINGTON, N.C., DISTRICT 
SACRAMENTO, CALIF., DISTRICT 
LOS ANGELES, CALIF., DISTRICT 
SAN FRANCISCO, CALIF., DISTRICT 
ALBUQUERQUE, N. MEX., DISTRICT 
FORT WORTH, TEX., DISTRICT 
GALVESTON, TEX., DIVISION 
LITTLE ROCK, ARK., DISTRICT 
TULSA, OKLA., DISTRICT 
Agana River, Guam (POD) 36-2, 36-7, 36-9 
Agana Small Boat Harbor, Guam (POD) 36-2, 36-10 
Agat Harbor, Guam (POD) 36-7 
Aitkin, Minn. (NCS) 24-33 
AIWW-Mooring Basins, N.C. (SAW) 6-28 
AIWW, Norfolk-St. Johns River, Fla. (SAJ) 4-96 
AIWW-Peltier Creek (SAW) 6-28 
AIWW-Tidal Lock in Snows Cut, N.C. (SAW) 6-28 
Airport, Glendale, W.Va. (ORP) 18-26 
Ala Wai Small Boat Harbor, Hawaii (POD) 36-13 
Alabama River, Selma, Ala. (SAM) 10-49 
Alabama River at Montgomery, Ala. (SAM) 10-48 
Alabama Coosa Rivers, Ala. and Ga. (SAM) 10-20, 
10-35, 10-45, 10-50 
Alameda Creek, Calif. (SPK) 35-34 
Alamo Lake, Bill Williams River, Az. (SPL) 33-5, 
33-13, 33-20 
Alamogordo Diversion Channel, Tularosa (Closed) 
Basin, N. Mex. (SWA) 32-14 
I-1

Albemarle and Chesapeake Canal (NAO) 5-18 
Albeni Falls Dam, Idaho (NAS) 38-10, 38-17, 38-22 
Albuquerque Diversion Channels, N. Mex. (SWA) 
32-1, 32-10 
Albuquerque Unit (SWA) 32-14 
Alenaio System, Hawaii (POD) 36-6 
Alford, Green River, Mass. (NED) 1-23, 1-42, 1-50 
Algoma Harbor, Mich. (NCE) 21-55, 21-60 
Alhambra Creek, Calif. (SPK) 35-36 
Allatoona Dam, Coosa River Basin, Ga. (SAM) 10-23, 
10-35 
Allatoona Lake, Coosa River Basin, Ga. (SAM)10-46 
Allegany, N.Y. Unit I (Allegheny River) (ORP) 18-21 
Allegany, N.Y. Unit II (Five Mile Creek Area) (ORP) 
18-21 
Allegheny River, Pa. (ORP) 18-2, 18-11, 18-15, 
18-19, 18-25 
Allegheny River, Pa., Locks and Dams (ORP) 18-22 
Allegheny River, Oil City, Pa. (ORP) 18-26 
Allentown, Lehigh River, Pa. (NAP) 3-26 
Allenville, Ariz. (SPL) 33-25 
Alley Bay, Beals, Maine (NED) 1-42 
Alligator Creek Basin, CL, Fla. (SAJ) 9-54 
Alloway Creek, NJ. (NAP) 3-25 
Alluvial Valley Mapping (MR+T) 42-3 
Alma Harbor, Wis. (NCD) 25-7, 25-10 
Almond Lake, N.Y. (NAB) 4-14, 4-27 
Almond Village, N.Y. (NAB) 4-40 
Aloha-Rigolette Area, Grant and Rapides Parishes, 
La. (LMN) (LMK) 11-18, 12-19, 12-20 
Alpena Harbor, Mich. (NCE) 21-55, 21-60 
Alpine, Tex. (SWA) 32-14 
Alpine Dam and Page Park Dam, Rockford, Ill. (NCR) 
23-15 
Alsea River, Oreg. (NPP) 37-37 
Altamaha, Oconee, and Ocmulgee Rivers, Ga. (SAS) 
8-1, 8-11, 8-12 
Alton, Ind. (ORL) 16-21, 16-25 
Alum Creek Lake, Ohio (ORH) 17-2, 17-12, 17-17 
Alvin R. Bush Dam, Pa. (NAB) 4-19, 4-28 
Amazonia, Mace Creek, Mo. (MRK) 27-21 
American Lake, Vicinity of Fort Lewis, Wash. (NPS) 
38-25 
American River, Calif. (SPK) 35-34 
Ames Dam and Reservoir, Skunk River, Iowa (NCR) 
23-14 
Amesbury, Powwow River, Mass. (NED) 1-23, 1-42, 
1-51 
Amite River, La. (MR + T) 42-15 
Amite River and Bayou Manchac, La. (LMN) 11-16 
Amite River and Tributaries, La. (LMN) 11-18 
Amouli-Tula, Tutuila Island, American Samoa (POD) 
36-14 
Amsterdam, Ohio (ORP) 18-20, 18-25 
Anacortes Harbor, Wa. (NPS) 38-1, 38-14, 38-19, 
38-24 
Anacostia River and Flats (NAM) 4-37 
Anacostia River and Tributaries, Flood Protection and 
Navigation Improvements, D.C. and Md. (NAB) 
4-39 
Anacostia River and Tributaries, Prince Georges Co., 
Md. (NAB) 14-39 
Anacostia River Basin (NAB) 4-42 
Anaheim Bay Harbor, Orange Co., Ca. (SPL) 33-24 
Anahuac Channel, Tex. (SWE) 31-8 
Anchorage Harbor, Alas. (NPA) 40-1, 40-8, 40-10 
Anchorage Harbor, Alas. (Uncompleted Portion) 
(NPA) 40-13 
Anchorages (NAO) 5-17, 5-21 
Anclote River, Fla. (SAJ) 9-46, 9-47 
Andalusia Harbor, Ill. (NCD) 25-7 
Anderson, Ind. (White River) (ORL) 16-21 
Anderson Park (NAO) 5-20 
Andover, Dyke Creek, N.Y. (NCB) 20-39 
Andover Lake, Conn. (NED) 1-44 
Andrews River, Mass. (NED) 1-3, 1-25, 1-33 
Angler-use sites, Meramec Basin, Mo. (LMS) 14-14 
Annapolis Harbor, Md. (NAB) 4-34, 4-41 
Ansonia-Derby, Conn. (NED) 1-23, 1-42, 1-50 
Anthony Shoals, Ga. (SAS) 8-16 
Apalachee Bay, Fla. to New Orleans, La. (SAM) 
10-40 
Apalachicola Bay. Fla. (SAM) 10-3, 10-31, 10-37 
Apalachicola, Chattahoochee, and Flint Rivers, Ala., 
Ga., and Fla. (SAM) 10-23, 10-35, 10-46, 10-51 
Apalachicola River to St. Andrew Bay, Fla. (SAM) 
10-40 
Apoon Mouth of Yukon River, Alas. (NPA) 40-12 
Applegate Lake, Rogue River Basin, Ore. (NPP) 
37-10, 37-25, 37-34, 37-43 
Appomattox River, Va. (NAO) 5-19, 5-21 
Apponaug Cove, R.I. (NED) 1-38 
Appoquinimink River, Del. (NAP) 3-24, 3-27 
Approach Channel to Main Turning Basin (SWE) 
31-36 
Aquia Creek, Va. (NAB) 4-37 
I-2

INDEX 
Aquashicola Reservoir, Penn. (NAP) 3-27 
Aquatic Plant Control 
Charleston, S.C., Distr. (SAN) 7-1, 7-8, 7-10, 7-14 
Galveston, Tex., Distr. (SWG) 31-2, 31-15, 31-18, 
31-30 
Jacksonville, Fla., Distr. (SAJ) 9-2, 9-26, 9-32, 9-47 
Mobile, Ala., Distr. (SAM) 10-3, 10-31, 10-37 
New England Div. (NED) 1-3, 1-25, 1-33 
New Orleans Distr. (LMN) 11-16 
New York Distr. (NAN) 2-2, 2-22, 2-27 
Philadelphia, Penn. (NAP) 3-25 
Sacramento, Calif., Distr, (SPK) 35-34 
Savannah, Ga., Distr. (SAS) 8-2, 8-11, 8-15 
Wilmington, N.C., Distr. (SAW) 6-2, 6-18, 6-25 
Aquilla Lake, Tex. (SWF) 30-2, 30-15, 30-19 
Ararat River, Mount Airy, N.C. (SAW) 6-27 
Arcadia Harbor, Mich. (NCE) 21-2, 21-31, 21-43 
Arcadia Lake, Okla. (SWT) 29-2, 29-16 
Arch Creek, Dade County, Fla. (SAJ) 9-55 
Archers Creek, S.C. (SAN) 7-14 
Ardsley, N.Y. (NAN) 2-17, 2-25, 2-31 
Area V, Estelline Springs, Tex. (SWT) 29-11 
Area VIII, Tex. (SWT) 29-11 
Area East of Albany Oreg. (NPP) 37-41 
Arecibo Harbor, P.R. (SAJ) 9-2, 9-26, 9-32 
Arkport Dam, N.Y. (NAB) 4-15, 4-27 
Arkansas City, Kan. (SWT) 29-19 
Arkansas River Basin, Ark., Okla., and Kan. (SWL) 
28-2, 28-11, 28-14, 28-19, 28-20, 28-21, 28-22 
Arkansas River Basin Multiple Purpose Plan (SWT) 
29-20 
Arkansas River, Dikes, Levees, and Revetments 
(MR+T) 42-39 
Arkansas River, Russellville, Morrilton, Ark. (SWL) 
28-18 
Arkansas-Red River Basins, Kan., Okla., Tex. (SWT) 
29-2, 29-11, 29-16 
Arlington, Alkali Canyon, Oreg. (NPP) 37-39 
Arlington Lake, Mo. (MRK) 27-17 
Amrnolds Bay, Vt. (NAN) 2-39 
Armuchee Creek, Ga., (SAM) 10-48 
Aroostook River, Ft. Fairfield, Me. (NED) 1-47 
Arroyo, Colo., Rio Hondo, Tex. (SWG) 37-31 
Arthur V. Ormond Lock and Dam (No.9) (SWL) 28-2, 
28-19 
Asan River, Guam (POD) 36-15 
Asan Village, Guam (POD) 36-12 
Asbury Park to Manasquan, NJ. (NAN) 2-17 
Asharoken Beach, Huntington, N.Y. (NAN) 2-39 
Ashland, Ky. (ORH) 17-21, 17-23 
Ashland Harbor, Wis. (NCE) 21-2, 21-31, 21-43 
Ashley River, S.C. (SAN) 7-14 
Ashtabula Harbor, Ohio (NCB) 20-2, 20-17, 20-22 
Asotin Creek, Asotin, Ind. (NPW) 39-15 
Asotin Dam, Snake River, Ind. and Wash. (NPW) 
39-16 
Asquiroga Bay, Guam (POD) 36-11 
Assunpink Creek Basin, NJ. (NAP) 3-12 
Astoria Deep Draft Anchorages, Oreg. (NPP) 37-42 
Astoria Turning Basin, Oreg. (NPP) 37-37 
Atchafalaya Basin, La. (MR+T) 42-5, 42-13, 42-30 
Atchafalaya Basin Floodway System, La. (MR+T) 
42-30 
Atchafalaya Basin Floodway between Alabama Bayou 
and Morgan City (MR+T) 42-13 
Atchafalaya River Bayous Chene Boeuf, and Black, 
La. (LMN) 11-16 
Atchafalaya River, Morgan City to Gulf of Mexico 
(LMN) 11-16 
Atchison Co. Levee District No. 1 (MRO) 26-18 
Atchison, Kans. (MRK) 27-16 
Athalia, Ohio (ORH) 17-22 
Athens, Ohio (ORH) 17-21, 17-23 
Atlantic Beach Channels, N.C. (SAW) 6-25 
Atlantic City, N.J. (NAP) 3-26 
Atlantic Coast of Maryland and Assateague Island, 
Va. (NAB) 4-22 
Atlantic Coast of NJ. Sandy Hook to Barnegat Inlets 
(NAN) 2-36 
Atlantic Gulf Ship Canal, Fla. (SAJ) 9-47 
Atlantic Intracoastal Waterway between Norfolk, Va. 
and St. Johns River, Fla. (NAO) (SAW) (SAN) 
(SAS) (SAJ) 5-2, 5-11, 5-15, 5-18, 5-21, 6-3, 6-18, 
6-22, 7-2, 7-9, 7-10, 8-2, 8-11, 8-13, 9-2, 9-26, 9-32 
Atlantic Ocean Channel, Va. (NAO) 5-5, 5-12, 5-16 
Au Sable Harbor at Au Sable River (Oscoda), Mich. 
(NCE) 21-3, 21-31, 21-43 
Auasi Harbor, American Samoa (POD) 36-10 
Auburn, N.Y., Owasco Outlet (NCB) 20-37 
Auglaize River, Cemetary, Defiance, Ohio (NCB) 
20-39 
Augusta, Ga. (SAS) 8-16 
Augusta, Ky. (ORH) 17-21 
Augusta Levee, Kans. (SWT) 29-19 
Aunuu Harbor, American Samoa (POD) 36-10, 36-14 
Aurora, Ind. (ORL) 16-21, 16-26 
I-3

Aurora, Westerly Creek-Kelley Road Dam, Colo. 
(MRO) 26-19 
Authorized Bridge Alteration (NED) 1-10 
Avoca, N.Y. (NAB) 4-15, 4-27 
Avon Harbor, N.C. (SAW) 6-25 
Aylesworth Creek Lake, Pa. (NAB) 4-14, 4-26 
B 
B. Everett Jordan Dam and Lake, N.C. (Formerly 
New Hope Lake, N.C.) (SAW) 6-15, 6-20 
Bachelor Island, Wash. (NPP) 37-41, 37-44 
Back Creek, Md. (NAB) 4-37 
Bad River, Bank Protection, Fort Pierre, S. Dak. 
(MRO) 26-19 
Bagaduce River, Maine (NED) 1-38, 1-42, 1-44 
Bainbridge, N.Y. (NAB) 4-39, 4-42 
Baker Brook, Mass. (NED) 1-44 
Bakers Haulover Inlet, Fla. (SAJ) 9-3, 9-26, 9-32 
Ball Mountain Lake, Vt. (NED) 1-13, 1-23, 1-28, 
1-48, 
Baltimore Harbor, Md. Collection and Removal of 
Drift (NAB) 4-4, 4-24, 4-31 
Baltimore Harbor and Channels, Md. and Va. (NAB) 
4-3, 4-24, 4-30, 4-40 
Baltimore Harbor and Channels (Norfolk District) 
(NAO) 5-2, 5-11, 5-15, 5-25 
Bandon Small Boat Basin, Oreg. (NPP) 37-37 
Bank Revetments and Dikes: Memphis District 
(MR+T) 42-41 
Bank Revetments and Dikes: New Orleans District 
(MR+T) 42-34 
Bank Revetments and Dikes: Vicksburg District 
(MR+T) 42-36 
Bank Stabilization and Channel Rectification, Ark. 
(SWL) 28-2, 28-11 
Bank Stabilization and Channel Rectification, 
Arkansas River, Ark. and Okla. (SWT) 29-20 
Banner Special Drainage and Levee Districts (NCR) 
23-12, 23-15 
Baptiste Collette-Bayou Ostrica, La. (MR+T) 42-11 
Bar Harbor, Maine (NED) 1-44, 1-46 
Bar Lake, Mich. (NCE) 21-25 
Bar Point Harbor, Ketchikan, Alas. (NPA) 40-2, 40-8, 
40-10, 40-12 
Baraga Co., Mich. (NCE) 21-25 
Barataria Bay Waterway, La. (LMN) 11-16 
Barbers Point Harbor, Oahu, Hawaii (POD) 36-2, 
36-7, 36-9 
Barbourville, Ky. (ORN) 15-13, 15-19 
Barbre Landing-Alabama Bayou (MR+T) 42-14 
Barcelona Harbor, N.Y. (NCB) 20-35 
Bardwell Lake, Tex. (SWF) 30-3, 30-15, 30-19 
Barkley Dam and Lake Barkley, Ky. and Tenn. 
(ORN) 15-14 
Barnard, Kans. (MRK) 27-16 
Bamegat Inlet, NJ.(NAP) 3-2, 3-15, 3-19 
Bamegat Light, NJ. (NAP) 3-26 
Bamett Creek, Ky. (Rough River) (ORL) 16-24 
Baron Fork, Ok. (SWT) 29-21 
Barre Falls Dam, Mass. (NED) 1-13, 1-28, 1-48 
Barren River Lake, Ky. (ORL) 16-4, 16-13 
Bartley, Nebr. (MRK) 27-16, 27-19 
Bass Harbor, Maine (NED) 1-38, 1-46 
Bass Harbor Bar, Maine (NED) 1-38 
Bassett Creek, Minn. (NCS) 24-3, 24-22 
Bastrop Bayou, Tex. (SWG) 31-30 
Batavia and Vicinity to Nawanda Creek, N.Y. (NCB) 
20-37 
Batavia, Ill. (NCC) 22-8 
Bath, N.Y. (NAB) 4-39, 4-42 
Baton Rouge Harbor, segment between Mi. 2.5 and 
5.0, La. (LMN) 11-16 
Baton Rouge Harbor (MR+T) 42-11 
Baton Rouge Harbor (Devil's Swamp), La. (MR+T) 
42-5, 42-31 
Battle Creek, Bank Protection, Battle Creek, Nebr. 
(MRO) 26-20 
Battle Creek, Kalamazoo River, Mich. (NCE) 21-27 
Baudette Harbor, Minn. (NCS) 24-27 
Bay City Harbor, Wis. (NCD) 25-27 
Bay Ridge and Red Hook Channels, N.Y. (NAN) 2-2, 
2-22, 2-27, 2-33 
Bay River, N.C. (SAW) 6-25 
Bayard, W. Va. (NAB) 4-39, 4-42 
Bayfield Harbor, Wis. (NCE) 21-55, 21-60 
Bayou Bartholomew and Tributaries, Ark. and La. 
(LMK) 12-3, 12-9, 12-11, 12-15, 12-17 
Bayou Bodcau and Tributaries, Ark. and La. (LMK) 
12-4, 12-9, 12-11, 12-18 
Bayou Bodcau, Red Chute, and Loggy Bayou, La. 
(LMN) (LMK) 11-18, 12-19,12-20 
Bayou Bodcau Reservoir, La. (LMK) 12-19, 12-20 
Bayou Boniface, La. (LMN) 11-16 
I-4

INDEX 
Bayou Choupique, La. (LMN) 11-18 
Bayou Cocodrie and Tributaries, La. (MR+T) 42-5, 
42-14, 42-30 
Bayou Coden, Ala. (SAM) 10-3, 10-5, 10-31, 10-37 
Bayou Cumbest, Jackson Co., Miss. (SAM) 10-49 
Bayous D'Arbonne and Corney, La. (LMK) 11-15 
Bayou des Glaises diversion ditch, La. (MR+T) 42-29 
Bayou Dorcheat, Loggy Bayou, and Lake Bisteneau, 
La. (LMN) 11-16 
Bayou Dupre, La. (LMN) 11-16 
Bayou Galere, Miss. (SAM) 10-48 
Bayou Grosse Tete, La. (LMN) 11-16 
Bayou La Batre, Ala. (SAM) 10-4, 10-31, 10-37, 
10-50 
Bayou Lacombe, La. (LMN) 11-16 
Bayou Lafourche and Lafourche Jump Waterway, La. 
(LMN) 11-16 
Bayou La Lautre, St. Malo's, and Yscolskey, La. 
(LMN) 11-16 
Bayou Metro, Ark. (MR+T) 42-54 
Bayou Nicholas, Coushatta, La. (LMN) (LMK) 11-18, 
12-18 
Bayou Plaquemine Brule, La. (LMN) 11-16 
Bayou Pierre, La. (LMK) 12-19, 12-20 
Bayou Pierre in vicinity of Shreveport, La. (LMN) 
(LMK) 11-18, 12-18, 12-20 
Bayou Queue de Tortue, La. (LMN) 11-16 
Bayou Rapides, La. (LMN) 11-18 
Bayou Rigolette, La. (LMN) 11-14 
Bayou Segnette Waterway, La. (LMN) 11-16 
Bayou Teche, La. (LMN) 11-16 
Bayou Teche and Vermilion River, La. (LMN) 11-16 
Bayou Terrebonne, La. (LMN) 11-16 
Bayou Vermilion, La. (LMN) 11-16 
Bayport Harbor, Mich. (NCE) 21-55 
Bayport, Fla. (SAJ) 9-47 
Baytown, Tex. (SWG) 31-31 
Beals Harbor, Me. (NED) 1-23, 1-38 
Bear Creek, Adel, Ga. (SAJ) 9-54 
Bear Creek, Kendrick, Ind. (NPW) 39-14, 39-15 
Bear Creek, Medford, Oreg. (NPP) 37-39 
Bear Creek, Mt. (NPS) 38-25 
Bear Creek Dam (City of Hannibal, Mo.) (NCR) 
23-12, 23-15 
Bear Creek Lake, Col. (MRO) 26-2, 26-9, 26-12 
Bear Creek, Long Tom River, Oreg. (NPP) 37-41 
Bear River, Calif. (SPK) 35-36 
Bear River, Smiths Fork, Wyo. (SPK) 35-40 
Beards Brook Reservoir, N.H. (NED) 1-44 
Beatrice, Big Blue River, Nebr. (MRK) 27-17 
Beaufort Harbor, N.C. (SAW) 6-4, 6-18, 6-23 
Beaver and Mahoning Rivers, Pa. and Ohio (ORP) 
18-19 
Beaver Bay, Minn., (NCE) 21-55 
Beaver Brook, Keene, N.H. (NED) 1-13, 1-23, 1-28, 
1-36, 1-44, 1-49 
Beaver Brook, Londonderry, N.H. (NED) 1-47 
Beaver Creek, Montezuma, Ga. (SAM) 10-48 
Beaver Creek, Platte Co., Nebr. (MRO) 26-23 
Beaver Creek Near Tillamoor, Oreg. (NPP) 37-39 
Beaver Drainage District, Oreg. (NPP) 37-44 
Beaver Lake, Ark. (SWL) 28-8, 28-13, 28-24 
Beaver Lake, Steams Co., Minn. (NCS) 24-34 28-8, 
28-13 
Beaver River, Bridgewater, Penn. (ORP) 18-26 
Beaver River, Ohio (ORP) 18-25 
Bedford, East Fork, 102 River, Iowa (MRK) 27-16 
Beech Fork Lake, W.Va. (ORH) 17-3, 17-12, 17-17 
Belfast Harbor, Me. (NED) 1-24, 1-38 
Belford, N.J. (NAN) 2-38 
Belhaven Harbor, N.C. (SAW) 6-5, 6-18 
Bell Foley Lake, White River, Ark. (SWL) 28-17, 
28-24 
Bell Island, Norwalk, Conn. (NED) 1-47 
Bellaire, Ohio (ORP) 18-21 
Bellamy River, N.H. (NED) 1-38 
Belle Fourche, Belle Fourche River, S. Dak. (MRO) 
26-19 
Belle Fourche, Cheyenne River, S. Dak. (MRO) 26-15 
Belle Glade, Fla. (SAJ) 9-48 
Belle River, Mich. (NCE) 21-55, 21-60 
Belleville Locks and Dam, Ohio (ORD) 19-8 
Bellevue, Ky. (ORL) 16-21, 16-25 
Bellevue-Papillion Creek Levees (MRO) 26-18 
Bellingham Harbor, Wash. (NPS) 38-2, 38-14, 38-19, 
38-24 
Bellville Point, Ga. (SAS) 8-15 
Belpre, Ohio (ORH) 17-22 
Belton Lake Modification, Tex. (SWF) 30-11 
Beltzville Lake, Penn. (NAP) 3-11, 3-17, 3-22 
Belton Lake, Tex. (SWF) 30-3, 30-15, 30-19 
Benbrook Lake, Tex. (SWF) 30-3, 30-15, 30-19 
Benett-McDonald-Smithland D.D., Little Sioux River, 
Iowa (MRO) 26-20 
I-5

Bennington, Vt. (NAN) 2-36 
Bennington Reservoir, N.H. (NED) 1-44 
Benwood, W.Va. (ORP) 18-20, 18-24 
Berkeley Harbor, Calif. (SPN) 34-12 
Berkeley Marina, Calif. (SPN) 34-12 
Berlin Lake, Ohio River Basin, Ohio (ORP) 18-4, 
18-11, 18-16 
Berlin, Ohio (ORP) 18-25 
Berrien County, (St. Josephs Shore) Mich. (NCE) 
21-57 
Berwick Bay Bridge (LMN) 11-16 
Bethel Bank Stabilization (NPA) 40-9 
Bethel Harbor (NPA) 40-14 
Bethel Small Boat Harbor, Ark. (NPA) 40-2, 40-8, 
40-10 
Bethlehem, Lehigh River, Penn. (NAP) 3-26 
Bettendorf, Iowa (NCR) 23-12, 23-15 
Betterton Harbor, Md. (NAB) 4-37 
Beverly Harbor, Mass. (NED) 1-38 
Big Bay Harbor, Mich. (NCE) 21-3, 21-31, 21-43 
Big Bend Dam-Lake Sharpe, Missouri River Basin, 
S.D. (MRO) 26-7, 26-11, 26-14, 26-18 
Big Bend, W.Va. (ORH) 17-22 
Big Black River, Miss. (LMK) 12-15, 12-20 
Big Blue Lake, Ind. (ORL) 16-22, 16-28 
Big Blue River, Blue Springs, Nebr. (Sewerline and 
Rd) (MKK) 27-21 
Big Blue River, Seward, Nebr. (MRK) 27-16 
Big Brown Creek, Prentiss Co., Miss. (SAM) 16-48 
Big Choctaw Bayou, La. (LMK) 12-20 
Big Creek and L'Anguille River, White River Basin, 
Ark. (LMM) 13-5 
Big Creek Canal, Millington, Tenn. (LMM) 13-5 
Big (Cunningham) Creek, Ohio (NCB) 20-35 
Big Cry Creek Dam and Diversion, Calif. (SPK) 35-34 
Big Darby, Ohio (ORH) 17-22 
Big Fossil Creek, Tex. (SWF) 30-22 
Big Hole River, Pennington Bridge, Near Twin 
Bridges (MRO) 26-19 
Big Horn River, Two Leggin Bridge near Hardin 
(MRO) 26-19 
Big Lake Drainage and Levee District, Ill. (NCR) 
23-12, 23-15 
Big Pigeon and Little Pigeon Bayous, La. (LMN) 
11-16 
Big Pine Lake, Ind. (Walbash River) (ORL) 16-20 
Big Pine Lake, Tex. (SWT) 29-19 
Big Rapids, Mich. (NCE) 21-25 
Big River Basin, Vicinity of Kansas City (MRK) 
27-16 
Big River Reservoir, RI. (NED) 1-40 
Big Run, Penn. (ORP) 18-20, 18-25 
Big Sandy Lake, Tex. (SWF) 30-22 
Big Sandy River, W. Va. and Ky., including Levisa 
and Tug Forks (ORH) 17-20 
Big Sioux River at Sioux City, Iowa (MRO) 26-15 
Big Sioux River, Fink Bridge, near Flandreau, S. 
Dak. (MRO) 26-19 
Big Sioux River, Harrisburgh, S. Dak. (MRO) 26-19 
Big Sioux River, Jefferson, S. Dak. (MRO) 26-19 
Big Sioux River, North Sioux City, S. Dak. (MRO) 
26-19 
Big Sioux River, Plymouth Co, Iowa (MRO) 26-21 
Big Sioux River, Plymouth Co, S. Dak. (MRO) 26-19 
Big Sioux River, Schofield Bridge, near Flandreau, 
S. Dak. (MRO) 26-19 
Big Sioux River, Sioux City, Iowa (MRO) 26-2 
Big Sioux River, Union Co, S. Dak. (MRO) 26-19 
Big South Fork National River and Recreation Area, 
Ky. and Tenn. (ORN) 15-4, 15-9 
Big Spring, Tex. (SWF) 30-22 
Big Stone Lake and Whetstone River, Minn. and S. 
Dak. (NCS) 24-4, 24-22 
Big Stranger Creek, Kan. (MRK) 27-16 
Big Suamico River, Wis. (NCE) 21-3, 21-31, 21-43 
Big Sunflower River, Miss. (LMK) (MR+T) 12-5, 
42-17, 42-29, 42-53 
Big Swan Drainage and Levee District, Ill. (LMS) 
14-14 
Big Thompson River, Johnstown, Colo. (MRO) 26-19 
Big Timber Creek, NJ. (NAP) 3-24 
Big Walnut Lake. Ind. (ORL) 16-28 
Big Walnut Lake. Ind. (Wabash River) (ORL) 16-20 
Big Wash, Milford Beaver Co, Utah (SPK) 35-34 
Big Wood River, Idaho (NPW) 39-15, 39-17 
Billings, Mt. (MRO) 26-17 
Biloxi Harbor, Miss. (SAM) 10-4, 10-31, 10-38 
Biloxi River at Lorraine Road, Harrison County, 
Miss. (SAM) 10-48 
Binghamton, N.Y. (NAB) 4-15, 4-27 
Birch, W. Va. (ORH) 17-21 
Birch Hill Dam, Mass. (NED) 1-13, 1-23, 1-28, 1-48 
Birch Lake, Okla. (SWT) 29-3, 29-11, 29-17 
Bird Rock Area, La Jolla, Calif. (SPL) 33-24 
Birds Point-New Madrid Floodway, Mo. (MR+T) 
42-55 
I-6

INDEX 
Biscayne Bay, Fla., Hurricane Protection (SAJ) 9-54 
Bitter Creek at Rock Springs, Wyo. (SPK) 35-40 
Black Bayou-Pine Island Area, La. (LMN) 11-18 
Black Bayou Lake, La. (LMK) 12-19 
Black Bayou Reservoir, La. (LMN) (LMK) 11-18, 
12-20 
Black Bear and Miller Lakes, Minn. (NCS) 24-4, 
24-22 
Black Creek, Gadsden, Ala. (SAM) 10-48 
Black Fork at Hendricks, W. Va. (ORP) 18-20 
Black River (Alcona Co.), Mich. (NCE) 21-55 
Black River, La. (MR+T) 42-15 
Black River, N.C. (SAW) 6-25, 6-27 
Black River, Wayne Co, Mo. (SWL) 28-4, 28-11 
Black River, Wis. (NCS) 24-27, 24-30 
Black River at North Bend, Wis. (NCS) 24-33 
Black River Basin, Ark. and Mo. (SWL) 28-18 
Black River, Butler County Road 607, Mo. (SWL) 
28-17 
Black River Harbor, Mich. (NCE) 21-31, 21-57 
Black River Harbor, (Upper Penisula) Mich. (NCE) 
21-3, 21-31, 21-43 
Black River Harbor, N.Y. (NCB) (NCE) 20-35, 21-31 
Black River Lake, Wis. (NCS) 24-30 
Black River, Poplar Bluff, Mo., to Knobel, Ark. 
(SWL) 28-17 
Black River (Port Huron), Mich. (NCE) 21-3, 21-43 
Black Rock, Waterbury, Ct. (NED) 1-50 
Black Rock Channel and Tonawanda Harbor, N.Y. 
(NCB) 20-2, 20-17, 20-22, 20-40 
Black Rock Harbor, Conn. (NED) 1-3, 1-25, 1-33, 
1-44 
Black Rock Lake, Conn. (NED) 1-17, 1-29, 1-49 
Black Walnut Harbor, Md. (NAB) 4-37 
Black Walnut Point, Md. (NAB) 4-39 
Black Warrior and Tombigbee Rivers, Ala. (SAM) 
10-5, 10-31, 10-38, 10-52 
Black Warrior River, U.S. Hwy. 11 Bridge, Fosters, 
Ala. (SAM) 10-48 
Blackbird Creek, Decatur, Nebr. (MRO) 26-20 
Blackbird Creek near Macy, Nebr. (MRO) 26-15 
Blackboy Creek, Tulsa Co., Okla. (SWT) 29-21 
Blackfoot Area, Snake River, Idaho (NPW) 39-12, 
39-16 
Blackfoot Reservoir, Idaho (NPW) 39-14, 39-16, 
Blackfoot-River, Idaho (NPW) 39-12, 39-14, 39-16, 
39-17 
Blackfoot River, Mont. (NPS) 38-25 
Blacksmith Fork River, Logan, Utah (SPK) 35-40 
Blackstone, Mass. (NED) 1-23 
Blackstone River Basin, Mass. and R.I. (NED) 1-11, 
1-47 
Blackstone River, Millbury, Mass. (NED) 1-42, 1-48 
Blackwater Dam, N.H. (NED) 1-18, 1-30, 1-51 
Blackwater River, Fla. (SAM) 10-47, 10-50 
Blackwater River, Va. (NAO) 5-19 
Blaine, Maine (NED) 1-23 
Blaine Harbor, Wash. (NPS) 38-24 
Blair and Sitcum Waterways, Tacoma Harbor, Wash. 
(NPS) 38-11 
Blakely Mountain Dam-Lake Ouachita, Ark. (LMK) 
12-17, 12-20 
Blanchard River, Ottawa, Ohio (NCB) 20-39 
Blind Slough Diking District, Oreg. (NPP) 37-38 
Blockhouse Creek, Cedar Park, Tex. (SWF) 30-23 
Blue Marsh Lake, Pa. (NAP) 3-11, 3-17, 3-22 
Blue Mountain Lake, Ark. (SWL) 28-4, 28-11, 28-22 
Blue River Channel, Kansas City, Mo. (MRK) 27-2, 
27-9, 27-12 
Blue River Lake, Oreg. (NPP) 37-10, 37-26, 37-34, 
37-43, 37-45 
Bluestone Lake, W. Va. (ORH) 17-3, 17-12, 17-17 
Bluff Creek, Miss. (SAM) 10-47 
Board of Engineers for Rivers and Harbors, Members, 
Board Actions, Recommendations (BERH) 41-1, 
41-2 
Bodega Bay, Calif. (SPN) 34-6 
Bodie Island, N.C. (SAW) 6-28 
Boeuf and Tensas Rivers, Ark. and La. (MR+T) 42-6, 
42-53, 42-54 
Boeuf and Tensas Rivers and Bayou Macon, 
La. (MR+T) 42-29 
Boeuf River, La. ( LMN) 12-15 
Bogachiel River, Wash. (NPS) 38-25 
Boggy Bayou Shoreline, Valparaiso, Fla., (SAM) 
10-49 
Boggy Creek, Austin, Tex. (SWF) 30-3, 30-15, 30-19 
Boise River, Idaho (NPW) 39-15, 39-17 
Boise Valley, Idaho (NPW) 39-12, 39-16 
Boligee Canal, Boligee, Ala. (SAM) 10-48 
Bolivar, N.Y. (ORP) 18-25 
Bolles Harbor, Mich. (NCE) 21-4, 21-31, 21-43 
Bon Secour River, Ala. (SAM) 10-7, 10-31, 10-39, 
10-50 
I-7

Bonnes Coulee, Velva, N.D. (NCS) 24-28, 24-33 
Bonnet Carre, Baton Rouge (MR+T) 42-11 
Bonnet Carre, Floodway, La. (MR+T) 42-11 
Bonnet Carre Spillway, La. (MR+T) 42-6 
Bonneville Lock and Dam-Lake Bonneville, Oreg. & 
Wash (NPP)37-2, 37-16, 37-23, 37-27, 37-35, 37-46 
Bonpas Creek, Ill.(Wabash River) (ORL) 16-21, 16-26 
Bonum Creek, Va. (NAB) 4-37 
Boone County (Ohio River, Rabbit Hash), Ky. (ORL) 
16-19 
Booneville Lake, Ky. (Kentucky River) (ORL) 16-20 
Boothbay Harbor, Maine (NED) 1-38, 1-53 
Boston Harbor, Mass. (NED) 1-38, 1-52 
Boswell Lake, Okla. (SWT) 29-19 
Boulder, Colo. (MRO) 26-17 
Bound Brook, Scituate, Mass. (NED) 1-42 
Bowman-Haley Lake, N. Dak. (MRO) 26-2, 26-9, 
26-12 
Brackenridge, Tarentum and Natrona, Pa. (ORP) 
18-21 
Bradford, Pa. (ORP) 18-20, 18-25 
Bradford, Tenn. (LMM) 13-5 
Bradley Lake, Alaska (NPA) 40-13 
Bramwell, W. Va. (ORH) 17-23 
Branford Harbor, Conn. (NED) 1-38, 1-53 
Branson Cove, Va. (NAB) 4-37 
Brant Rock Beach, Marshfield, Mass. (NED) 1-44 
Braymer Lake, Shoal Creek, Mo. (MRK) 27-16 
Brazos Island Harbor, Tex. (SWG) 31-2, 31-15, 31-18, 
3f-32, 31-33 
Brazos River, Tex., Velasco to Old Washington 
(SWG) 31-30 
Breckenridge, Minn. (NCS) 24-33 
Breton Bay, Md. (NAB) 4-37 
Brevard County, Fla. (SAJ) 9-18, 19-30, 9-40 
Brevoort Levee, Ill. (Wabash River) (ORL) 16-19, 
16-29 
Bridge Alterations Authorized 
Chicago, Ill., District (NCC) 22-17 
Nashville, Tenn., District (ORN) 15-4 
Bridgeport, Mich. (NCE) 21-25 
Bridgeport Harbor, Conn. (NED) 1-23, 1-38, 1-44 
Bridges, Columbia River, Oreg. (NPP) 37-37 
Bridgewater, Va. (NAB) 4-42 
Brigantine Islnad (NAP) 3-26 
Brilliant, Ohio (ORP) 18-21 
Bristol Harbor, R.I. (NED) 1-38 
Broad Creek, Md. (NAB) 4-37, 4-41 
Broad Creek, N.C. (SAW) 6-27 
Broad Creek, Va. (NAO) 5-19 
Broad Creek River, Del. (NAB) 4-37 
Broadkill River, Del. (NAP) 3-24 
Broadwater Creek, Md. (NAB) 4-40 
Broadway Lake, S.C. (SAS) 8-11, 8-14 
Brockway, Pa. (Allegheny River Basin) (ORP) 18-21 
Brockway Lake, Vt. (NED) 1-44 
Broken Bow, Mud Creek, Nebr. (MRO) 26-20 
Broken Bow Lake, Okla. (SWT) 29-8, 29-15, 29-18 
Bromley, Ky. (ORL) 16-21, 16-25 
Bronx River, N.Y. (NAN) 2-34, 2-37 
Brook County, Hooverson Heights, W.Va. (ORP) 
18-26 
Brookfield Lake, Yellow Creek, Mo. (MRK) 27-16 
Brookgreen Gardens, S. C. (SAN) 7-14 
Brooklyn, W. Va. (ORH) 17-22 
Brookport, Ill. (ORL) 16-19, 16-24, 16-29 
Brookville, Pa. (ORP) 18-20, 18-25 
Brookville Lake, Ind. (ORL) 16-5, 16-13 
Broward County, Fla., Beach Erosion Control and 
Hillsboro Inlet, Fla., Navigation Project (SAJ) 9-19, 
9-30, 9-40 
Brown, Clarence J., Dam and Reservoir, Ohio (ORL) 
16-7, 16-14 
Brown Co, Gregg Creek, Kan., Granda Bridge (MRK) 
27-21 
Brown Co, West Fork Wolf River, Kan., Avenue Rd. 
Bridge (MRK) 27-21 
Browns Creek, N.Y. (NAN) 2-33, 2-34, 2-37 
Browns Creek, Nashville, Tenn. (ORN) 15-19 
Brownville-Nemaha Levee (MRO) 26-18 
Brownwood Channel Improvement, Tex. (SWF) 
30-22 
Brunswick County Beaches, N.C. (Cape Fear to 
North Carolina-South Carolina State Line) (SAW) 
6-27 
Brunswick Harbor, Ga. (SAS) 8-3, 8-11, 8-13 
Brush Creek, Jeannette, Pa. (ORP) 18-26 
Brush Creek, Kansas City, Mo. (MRK) 27-2, 27-9, 
27-12 
Buchanan Dam-H. V. Eastman Lake, Calif. (SPK) 
35-5, 35-24 
Buck Creek, N.C. and S.C. (SAN) 7-15 
Buckhannon, W. Va. (ORP) 18-19, 18-20, 18-25 
Buckhorn Creek, Campbellsville, Ky., (ORL) 16-31 
I-8

INDEX 
Buckhorn Lake, Ky. (ORL) 16-5, 16-13 
Bucks Harbor, Machiasport, Maine (NED) 1-38, 1-46, 
1-53 
Bucksport Harbor, Maine (NED) 1-38 
Buena Vista, Iowa (NCR) 23-17 
Buena Vista, Ohio (ORH) 17-22 
Buena Vista, Va. (NAO) 5-20 
Buffalo, Johnson Co., Diversion Channel, Wyo. 
(MRO) 26-17 
Buffalo Bayou and Tributaries, Tex. (SWG) 31-10, 
31-16, 31-28 
Buffalo Creek, Meadow Grove, Nebr. (MRO) 26-15 
Buffalo Creek, Scranton, N. Dak. (MRO) 26-15 
Buffalo Harbor, N.Y. (NCB) 20-3, 20-17, 20-23 
Buffalo River, Miss. (LMK) 12-20 
Buffalo River, West Seneca, N.Y. (NCB) 20-39 
Buffumville Lake, Mass. (NED) 1-21, 1-31, 1-52 
Buford Dam, Lake Sidney Lanier, Ga. (SAM) 10-24, 
10-35 
Bull Run, Pa. (NAB) 4-39 
Bull Shoals Lake, Ark. (SWL) 28-8, 28-13 
Bull Shoals, White River, Ark. (SWL) 28-24 
Bullock Neck, East Providence, R.I. (NED) 1-46 
Bullocks Point Cove, R.I. (NED) 1-38 
Bunker Harbor, Maine (NED) 1-38 
Bunker Hills Creek, Watauga, Tex., (SWF) 30-23 
Burch Creek, Weber County, Utah (SPK) 35-34 
Burgettstown-Slovan, Pa. (ORP) 18-20, 18-25 
Burial Hill Beach, Westport, Conn. (NED) 1-41 
Burketts Creek, Amory, Miss. (SAM) 10-48 
Burlington, Iowa (NCR) 23-15 
Burlington, Ohio (ORH) 17-21 
Burlington Dam, N. Dak. (NCS) 24-28 
Burlington Harbor, Vt. (NAN) 2-34 
Burns Harbor, Ind. (NCC) 22-17 
Bums Small Boat Harbor, Ind. (NCC) 22-10 
Bums Waterway Harbor, Ind. (NCC) 22-2, 22-10, 
22-12, 22-14 
Bumrns Waterway SBH, Ind. (NCC) 22-2, 22-16 
Bumsville Lake, Ohio River Basin, W. Va. (ORH) 
17-2, 17-12, 17-17 
Burr Oak, Prairie River, Mich. (NCE) 21-27 
Burton Creek, Bryan, Tex. (SWF) 30-23 
Bush, Alvin R., Dam, Pa. (NAB) 4-9, 4-28 
Butler, Pa. (ORP) 18-20, 18-25 
Butler Co. Drainage District 3, Mo. (SWL) 28-17 
Buttermilk Bay Channel, Mass. (NED) 1-38 
Buttermilk Channel, N.Y. (NAN) 2-2, 2-22, 2-27, 
2-33 
Butternut Creek, DeWitt, N.Y. (NCB) 20-39 
Byram River at Pemberwick, Conn. (NAN) 2-36 
C 
C-51 East End (SAJ) 9-52 
Cache Basin, Ark. (MR+T) 42-9, 42-18, 42-30 
Cache Creek Basin, Calif. (SPK) 35-30, 35-22 
Cache Creek Basin, Calif., (Cache Creek Settling 
Basin) (SPK) 35-5, 35-24 
Cache La Poudre River, Ft. Collins, Colo. (MRO) 
26-19 
Cache La Poudre River, Windsor, Colo. (MRO) 26-19 
Cache River, Heron Pond, Ill. (ORL) 16-31 
Cache River Diversion, Ill. (LMS) 14-14 
Cache River Levee, Ill. (ORL) 16-29 
Caddo Lake, La. (LMK) 12-18 
Caddo Lake Dam, La. (LMK) 12-20 
Cadet Bayou, Miss. (SAM) 10-47, 10-50 
Cadle Creek, Md. (NAB) 4-40 
Caemarvon, La. (MR+T) 42-11 
Caesar Creek Lake, Ohio (ORL) 16-5, 16-14 
Cagles Mill Lake, Ind. (ORL) 16-6, 16-14 
Cahaba River, Ala. (SAM) 10-47 
Cairo, Cairo Drainage Districts (MR+T) 42-12 
Cairo, Cairo Drainage District, Mounds, Mound City 
and Vicinity (MR+T) 42-12 
Cairo, W. Va. (ORH) 17-23 
Calabash Creek, N.C. (SAN) 7-14 
Calapooya River, Oreg. (NPP) 37-41 
Calaveras River and Little John Creek and 
Tributaries, including New Hogan Lake and 
Farmington Darn, Calif. (SPK) 35-6, 35-24 
Calcasieu River and Pass, La. (LMN) 11-16 
Calcasieu River at Coon Island, La. (LMN) 11-16 
Calcasieu River at Devil's Elbow, La. (LMN) 11-16 
Calcasieu River Salt Water Barrier, La. (LMN) 11-16 
Caledonia, Genesse River, N.Y. (NCB) 20-37 
Calf Pasture Beach Park, Conn. (NED) 1-41 
California (Cincinnati), Ohio (ORL) 16-21, 16-26 
California Debris Commission (CDC) 53-1 
Calion, Ark. (LMK) 12-14, 12-17 
Calloway Branch, Hurst, Tex. (SWF) 30-22, 30-23 
Cal.-Sag Channel, Pt. II, Illinois Waterway, Ill., & Ind. 
(NCR) 23-14 
I-9

Calumet (MR+T) 42-13, 42-14 
Calumet Harbor and River, Ill. and Ind. (NCC) 22-2, 
22-10, 22-12, 22-16 
Calumet River Bridges, Ill. (NCC) 22-17 
Camas Creek, Idaho (NPW) 39-12, 39-16 
Cambridge Harbor, Md. (NAB) 4-4, 4-24, 4-31 
Cambridgeport Lake, Vt. (NED) 1-44 
Camden Harbor, Me. (NED) 1-38 
Camp Branch/Lynches Lake, Lake City, S.C. (SAN) 
7-16 
Camp Ground Lake, Ky. (Salt River) (ORL) 16-20 
Camp Perry, Ohio (NCB) 20-37 
Campbells Island, Ill. (NCR) 23-14 
Campti-Clarence Area in Natchitoches Parish, La. 
(LMN) (LMK) 11-18, 12-18, 12-20 
Canadaigua Lake, N.Y. (NCB) 20-39 
Canadaway Creek, Fredonia, N.Y. (NCB) 20-39 
Canal Point, Fla. (SAJ) 9-48 
Canapitsit Channel, Mass. (NED) 1-38 
Canaveral Harbor, Fla. (SAJ) 9-3, 9-26, 9-32, 9-43 
Candy Lake, Okla. (SWT) 29-3, 29-11, 29-17 
Cane Creek State Park, Ohio (NCB) 20-40 
Cane River, La. (LMN) 11-16 
Caney Creek, Miss. (LMK) 12-11 
Caney Fork River, Tenn. (ORN) 15-13 
Caney River, Okla. (SWT) 29-21 
Canisteo, N.Y. (NAB) 4-16, 4-27 
Cannelton, Ind. (ORL) 16-19, 16-24, 16-29 
Cannelton Locks and Dam, Ind. (ORD) 19-9 
Cannon, Clarence, Dam and Reservoir, Mo. (LMS) 
14-6, 14-9, 14-12 
Cannon River at Fairbault, Minn. (NCS) 24-4, 24-22 
Cannonball River, Shields, Nebr. (MRO) 26-23 
Canoe Creek, Henderson, Ky. (ORL) 16-30, 16-31 
Canton, Mass. (NED) 1-23, 1-42 
Canton, Mo. (NCR) 23-12, 23-15 
Canton Lake, Okla. (SWL) (SWT) 28-22, 29-3, 29-11, 
29-17, 29-20 
Canton (Nimishillen), Ohio (ORH) 17-23 
Canyon Lake, Tex. (SWF) 30-4, 30-15, 30-19 
Cape Charles City Harbor, Va. (NAO) 5-3, 5-11, 5-15 
Cape Cod Canal, Mass. (NED) 1-3, 1-25, 1-33 
Cape Fear River, N.C., above Wilmington (SAW) 6-5, 
6-18 
Cape Fear River Basin, N.C. (SAW) 6-11, 6-30 
Cape Florida State Park, Fla. (SAJ) 9-48 
Cape Girardeau, Jackson Metropolitan Area, Mo. 
(LMS) 14-10 
Cape Girardeau, Mo., No. 2 (LMS) 14-14 
Cape Henry Channel, Va. (NAO) 5-2, 5-15 
Cape Lookout, N.C. (SAW) 6-28 
Cape May City, N.J. (NAP) 3-26 
Cape May Inlet, N.J. (NAP) 3-15 
Cape May Inlet to Lower Twp., NJ. (NAP) 3-3, 3-19 
Cape Porpoise Harbor, Maine (NED) 1-38 
Cape Vincent Harbor, N.Y. (NCB) 20-35, 20-40 
Captain Anthony Meldahl Locks and Dam, Ky. 
(ORD) 19-8 
Carbon Cliff, Ill. (NCR) 23-17 
Carden's Bottom Drainage District No. 2, Arkansas 
River, Ark. (SWL) 28-17 
Carl L. Estes Dam and Lakes, Tex. (SWF) 30-22 
Carlyle Lake, Ill. (LMS) 14-4 
Carolina Beach, N.C. (SAW) 6-31 
Carolina Beach and Vicinity, N.C. (SAW) 6-12, 6-20 
Carr Fork Lake, Ky. (ORL) 16-6, 6-14 
Carrabelle Bar and Harbor, Fla. (SAM) 10-47 
Carrabelle Harbor, Fla. (SAM) 10-50 
Carroll County Levee and Drainage District, Ill. 
(NCR) 23-14 
Carrollton, Ky. (ORL) 16-21, 16-25 
Carters Creek, Va. (NAO) 5-19 
Carters Dam and Reservoir, Ga. (SAM) 10-21, 10-35, 
10-45 
Caruthersville Harbor, Mo. (LMM) 13-4 
Carvers Harbor, Vinalhaven, Me. (NED) 1-38 
Carvins Creek, Roanoke, Va. (SAW) 6-31 
Cascades Canal, Oreg. (NPP) 37-37 
Cascadia Lake, Oreg. (NPP) 37-39, 37-41, 37-45 
Caseville Harbor, Mich. (NCE) 21-4, 21-31, 21-43 
Caseyville, Ky. (ORL) 16-21, 16-26 
Cashie River, N.C. (SAW) 6-25 
Casino Beach, Chicago, Ill. (NCC) 22-17 
Cassville Harbor, Wis. (NCD) 25-7 
Castine, Me. (NED) 1-23 
Castle Rock, Wash. (NPP) 37-39 
Castlewood Lake, Douglas Co., Colo. (MRO) 26-17 
Catching Inlet Drainage District, Oreg. (NPP) 37-39 
Cathance River, Me. (NED) 1-38 
Catherine Creek, Oreg. (NPW) 39-2, 39-9, 39-12 
Catherine Creek Lake, Oreg. (NPW) 39-15 
Cathlamet, Wash. (NPP) 37-37 
Cattaraugus Creek, N.Y. (NCB) 20-35 
Cattaraugus Harbor, N.Y. (NCB) 20-3, 20-17, 20-24 
Cattletsburg, Ky. (ORH) 17-21, 17-23 
Cave Run Lake, Ky. (ORL) 16-6, 16-14 
I-10

INDEX 
Cave-In-Rock, Ill. (ORL) 16-21, 16-25 
Cayuga Creek, Cheektowaga, N.Y. (NCB) 20-37 
Cazenovia Creek, Buffalo, N.Y. (NCB) 20-39 
Cecil M. Harden Lake, Ind. (ORL) 16-6, 16-14 
Cedar Bayou, Tex. (SWG) Cedar Bayou, Tex. (SWG) 
31-30 
Cedar Canyon Dam, Rapid City, S. Dak. (MRO) 
26-15 
Cedar Creek, Sussex City, Del. (NAP) 3-24 
Cedar Falls, Cedar River, Ia. (NCR) 23-16 
Cedar Keys Harbor, Fla. (SAJ) 9-46, 9-47 
Cedar Point, Ga. (SAS) 8-15 
Cedar Point Lake, Kan. (SWT) 29-19 
Cedar River, Wash. (NPS) 38-25, 38-29 
Cedar River Harbor, Mich. (NCE) 21-55 
Cedar River, Spaulding, Nebr. (MRO) 26-23 
Celina Dam, Ky. (ORN) 15-14 
Center Hill Lake, Ohio River Basin, Tenn. (ORN) 
15-6, 15-9, 15-18 
Central and Southern Florida (SAJ) 9-30, 9-41, 9-48, 
9-49, 9-50, 9-51, 9-52 
Central City Lake, Wapsipinicon River, Ia. (NCR) 
23-14 
Centralia, Wash. (NPS) 38-12 
Ceredo-Kenova, W. Va. (ORH) 17-21, 17-23 
Chadakoin River, Jamestown, N.Y. (ORP) 18-26 
Chagrin River, East Branch, Baldwin Rd., Ohio 
(NCB) 20-39 
Chagrin River, East Branch, Sperry Rd., Ohio (NCB) 
20-39 
Chagrin River, East Branch, SR 615, Ohio (NCB) 
20-39 
Chambersburg, Ohio (ORH) 17-22 
Chambers Creek, Hurst, Tex. (SWF) 30-23 
Channel between North and South Hero Island, 
Lake Champlain, Vt. (NAN) 2-34 
Channel Connecting Plain Dealing Creek and Oak 
Creek, Md. (NAB) 4-40 
Channel Connecting Thoroughfare Bay with Cedar 
Bay, N.C. (SAW) 6-25 
Channel Connecting York River, Va. with Back 
Creek to Slaights Wharf (NAO) 5-19 
Channel from Back Sound to Lookout Bight, N.C. 
(SAW) 6-5, 6-18 
Channel from Naples to Big Marco Pass, Fla. (SAJ) 
9-4, 9-26, 9-32 
Channel from Pamlico Sound to Rodanthe, N.C. 
(SAW) 6-25 
Channel from Phoebus, Va. to Deep Water in 
Hampton Roads (NAO) 5-19 
Channel from PT of Turnout Channels to Approach 
(SWG) 31-36 
Channel Improvements (MR+T) 42-30, 42-52, 42-53, 
42-55, 
Channel Islands Harbor, Calif. (SPL) 33-2, 33-11, 
33-17 
Channel to Aransas Pass (SWG) 31-36 
Channel to Barroom Bay (SWG) 31-36 
Channel to Conn Brown Harbor (SWG) 31-36 
Channel to Harlingen via South Turnabout from Main 
Channel (SWG) 31-36 
Channel to Liberty, Tex. (SWG) 31-8 
Channel to Main Turning Basin (SWG) 31-36 
Channel to Newport News, Va. (NAO) 5-5, 5-12, 
5-16, 5-19, 5-21 
Channel to Palacios (SWG) 31-36 
Channel to Port Bolivar, Tex. (SWG) 31-30 
Channel to Port Mansfield (SWG) 31-36 
Channel to Rockport (SWG) 31-36 
Channel to Victoria Main Channel via East Turnout 
(SWG) 31-36 
Channel West Side of Main Channel (SWG) 31-36 
Channels and Harbors (ORL) 16-31 
Channels in the Straits of MacKinac (NCE) 21-55, 
21-60 
Chaplin River, Perryville, Ky. (ORL) 16-19 
Charenton (MR+T) 42-14 
Chariton River, Mo. (1944 Act) (MRK) 27-16 
Chariton River, Schuyler Co., Miss., Eason Bridge 
(MRK) 27-21 
Chariton-Little Chariton Basin, Mo. (1965 Act) 
(MRK) 27-16 
Charles River Dam, Mass. (NED) 1-23, 1-42 
Charles River (Natural Valley Storage Areas), Mass. 
(NED) 1-11, 1-27, 1-36 
Charlestown, N.H. (NED) 1-23, 1-42, 1-49 
Charleston Channel, Oreg. (NPP) 37-37, 37-42 
Charleston Harbor, S.C. (SAN) 7-2, 7-8, 7-10, 7-14, 
7-17 
Charlevoix County, East Jordan River, Mich. (NCE) 
21-25 
Charlevoix Harbor, Mich. (NCE) 21-4, 21-31, 21-43 
Charlotte County, Fla. (SAJ) 9-40 
Charlotte Harbor, Fla. (SAJ) 9-4, 9-26, 9-32, 9-46 
Chartiers Creek, Pa. (ORP) 18-3, 18-11, 18-25 
Chaska, Minn. (NCS) 24-5, 24-22 
I-11

Chatfield Lake, Colo. (MRO) 26-2, 26-9, 26-12 
Chatham (Stage) Harbor, Mass. (NED)1-38, 1-53 
Chattahoochee River, Eufaula, Ala. (SAM) 10-14, 
10-33, 10-44 
Chattooga Dams and Lakes, Ga. and S.C. (SAS) 8-16 
Cheat River, W. Va. (ORP) 18-19 
Cheatham Lock and Dam, Tenn. (ORN) 15-14 
Cheboygan Harbor, Mich. (NCE) 21-5, 21-32, 21-44 
Cheesequake Creek, NJ. (NAN) 2-33, 2-37 
Chefuncte River and Bogue Falia, La. (LMN) 11-16 
Chehalis River, Wash. (NPS) 38-12, 38-25 
Chena River Lakes, Alaska (NPA) 40-4, 40-5, 40-11 
Cherry and Red Fork Creeks Channel Improvement, 
Okla. (SWT) 29-19, 29-20 
Cherry Creek Lake, Colo. (MRO) 26-3, 26-9, 26-12, 
26-18 
Cherryfield, Maine (NED) 1-23, 1-42 
Chesapeake, Ohio (ORH) 17-21 
Chesconessex Creek, Va. (NAO) 5-19 
Cheshire, Ohio (ORH) 17-22 
Chester, Calif. (SPK) 35-34 
Chester River, Md. (NAB) 4-5, 4-24, 4-31 
Chester River, Delaware County, Pa. (NAP) 3-27 
Chetco River, Oreg. (NPP) 37-2, 37-23, 37-30 
Chewaucan River, Oreg. (NPP) 37-39 
Chicago Harbor, Ill. (NCC) 22-3, 22-10, 22-12, 22-16 
Chicago River, Ill. (NCC) 22-3, 22-10, 22-12, 22-16 
Chicago River, Ill. (North Branch) (NCC) 22-6, 22-11 
Chickamauga Lock and Dam, Tenn. (ORN) 15-17 
Chickasaw Bogue Creek, U.S. Highway 43 Bridge, 
Linden, Ala. (SAM)10-48 
Chicopee, Mass. (NED) 1-23, 1-42, 1-44, 1-49 
Chicopee Falls, Mass. (NED) 1-42, 1-49 
Chief Joseph Dam-Rufus Woods Lake, Wash. (NPS) 
38-10, 38-17, 38-22 
Chignik, Alaska (NPA) 40-13 
Chikaskia River, Okla. (SWT) 29-21 
Chillicothe, Ohio (ORH) 17-21, 17-23 
Chilo, Ohio (ORH) 17-22 
Chincoteague Bay, Va. (NAO) 5-19, 5-21 
Chincoteague Harbor of Refuge, Va. (NAO) 5-19, 
5-21 
Chincoteague Inlet, Va. (NAO) 5-3, 5-11, 5-15, 5-21 
Chippewa Harbor, Isle Royale, Mich. (NCE) 21-55 
Chittenango Creek and Tributaries, N.Y. (NCB) 20-37 
Chittenango Creek, Sullivan, N.Y. (NCB) 20-39 
Chocolate Bayou Channel (SWG) 31-36 
Choctaw Bayou and Tributaries, La. (LMN) 11-18 
Choctawhatchee Bay to Pensacola Bay, Fla. (SAM) 
10-35 
Choctawhatchee Bay to West Bay, Fla. (SAM) 10-40 
Choctawhatchee River, Fla. and Ala. (SAM) 10-47 
Choptank River, Md. (NAB) 4-37 
Chouteau Lock and Dam, Okla. (SWL) (SWT) 28-20, 
29-20, 29-21 
Chouteau, Nameoki, and Venice Drainage and Levee 
District, Ill. (LMS) 14-14 
Chowan River, N.C. (NAO) 5-19 
Chowan River, N.C. (SAW) 6-25 
Christiansted Harbor, V.I. (SAJ) 9-47 
Chwa Creek, Wa. (NPS) 38-29 
Cibolo Creek, Tex. (SWA) 32-14 
Cincinnati, Ohio (ORL) 16-19, 16-24, 16-29 
Cincinnati, Ohio (Unit 2) (ORL) 16-21, 16-25 
Cincinnati, Ohio (Unit 4) (ORL) 16-21, 16-25 
Cincinnatus, N.Y. (NAB) 4-42 
City Creek Levee, San Bernardino Co., Calif. (SPL) 
33-25 
City Dam, Little Caney River, Kan. (SWT) 29-21 
City of Aurora, Westerly Creek, Colo. (MRO) 26-15 
Clackamas River at Dixon Farm Location, Oreg. 
(NPP) 37-39 
Claiborne County Port, Miss. (LMK) 12-15 
Claibome Lock and Dam, Ala. (SAM) 10-21, 10-35, 
10-45 
Clairborne Harbor, Md. (NAB) 4-37 
Clallam Bay, Wash. (NPS) 38-25 
Clallam River, Wash. (NPS) 38-25 
Clanton, Ala. (SAM) 10-48 
Claremont Lake, N.H. (NED) 1-44 
Clarence Cannon Dam and Reservoir, Mo. (LMS) 
14-6, 14-9, 14-12 
Clarence J. Brown Dam and Reservoir, Ohio (ORL) 
16-7, 16-14 
Clarendon to Laconia Circle, White River Basin, Ark. 
(LMM) 13-5 
Clarington, Ohio (ORP) 18-21 
Clark Fork River, Mont. (NPS) 38-25 
Clark Point Beach, New Bedford, Mass. (NED) 1-41 
Clarkson, Maple Creek, Nebr. (MRO) 26-15 
Clarkson, Middle Fork, Maple Creek, Nebr. (MRO) 
26-20 
Clarksville, Ark. (SWL) 28-17 
Clatskanie Drainage District 1, Oreg. (NPP) 37-41 
1-12

INDEX 
Clatskanie River, Oreg. (NPP) 37-37, 37-44 
Clatskanie River Area, Oreg. (NPP) 37-41, 37-42, 
37-44 
Clatsop County Diking District 3, Oreg. (NPP) 37-41 
Clatsop County Diking District 4, Oreg. (NPP) 37-41 
Clatsop County Diking District 6, Oreg. (NPP) 37-41 
Clatsop County Drainage District 1, Oreg. (NPP) 
37-41 
Clatsop Drainage Districts 2 and 5, Oreg. (NPP) 37-43 
Clear and Clarks Creeks, Wa. (NPS) 38-29 
Clear and Burnt River, Oreg. (NPW) 39-2, 39-9, 39-12 
Clear Creek, Tex. (SWG) 31-11, 31-16, 31-28 
Clear Creek and Clear Lake, Tex. (SWG) 31-30 
Clear Creek Drainage and Levee District, Ill. (LMS) 
14-14 
Clear River, Burrillville, R.I. (NED) 1-24, 1-42, 1-48 
Clearwater Lake, Mo. (SWL) 28-4, 28-11, 28-24 
Clearwater Pass, Fla. (SAJ) 9-46, 9-47 
Clearwater River, Idaho (NPW) 39-17 
Clearwater River, Wash. (NPS) 38-25 
Cleveland and Lakewood, Ohio (NCB) 20-36 
Cleveland Harbor, Ohio (NCB) 20-3, 20-17, 20-24 
Cleves, Ohio (ORL) 16-21, 16-25 
Clewiston, Fla. (SAJ) 9-48 
Cliff Walk, Newport, R.I. (NED) 1-41 
Clifton, W. Va. (ORH) 17-22 
Clifty Creek Lake, Ind. (ORL) 16-22 
Clinch River, Tenn. and Va. (ORN) 15-13 
Clinton, Ind. (ORL) 16-21 
Clinton, Ind. (Wabash River) (ORL) 16-25 
Clinton, Ia. (NCR) 23-15 
Clinton Harbor, Conn. (NED) 1-38, 1-53 
Clinton Harbor, Ill. (NCD) 25-7 
Clinton Harbor, Iowa (NCD) 23-12 
Clinton Lake, Wakarusa River, Kan. (MRK) 27-2, 
27-9, 27-11 
Clinton River, Mich. (NCE) 21-5, 21-32, 21-44 
Cloverport, Ky. (ORL) 16-21, 16-26 
Clyde, R.I. (NED) 1-44 
Clyde Park, Mont. (MRO) 26-18 
Coal Creek, Okla. (SWT) 29-21 
Coal Creek and Tributaries (Lake City), Tenn. 
(ORN) 15-13 
Coal Creek Drainage and Levee District, Ill. (NCR) 
23-12, 23-15 
Coal Grove, Ohio (ORH) 17-21 
Coal River, W. Va. (ORH) 17-21 
Coan River, Va. (NAB) 4-40 
Coast of California, Point Mugu to San Pedro 
Breakwater, Calif. (SPL) 33-24 
Coasters Island Harbor, R.I. (NED) 1-38 
Cobb Brook, Westminster, Vt. (NED) 1-47 
Cobscook Bay, Maine (NED) 1-38 
Cocheco River, N.H. (NED) 1-38, 1-42 
Cochiti Lake, N. Mex. (SWA) 32-5, 32-11, 32-13 
Cochitito Rio Puerco Unit (not including Albuquerque 
Unit) (SWA) 32-14 
Cochrane, Wis. (NCS) 24-33 
Cockrells Creek, Va. (NAO) 5-19 
Coconut Pt., Nu'uuli, Tutuila Island, American Samoa 
(POD) 36-6 
Coeur D'Alene, Idaho (NPS) 38-25 
Cohansey River, NJ. (NAP) 3-3, 3-15, 3-19 
Cohasset Harbor, Mass. (NED) 1-38 
Colchester, Conn. (NED) 1-23 
Cold Regions Research Engineering Laboratory 
(CRREL) 44-1 
Cold Spring Inlet, NJ. (NAP) 3-3, 3-15, 3-19 
Colebrook River Lake, Conn. (NED) 1-13, 1-23, 1-28, 
1-48 
Colfax, Grant Parish, La. (LMN) (LMK) 11-18, 12-19, 
12-20 
Colfax, Palouse River, Wash. (NPW) 39-2, 39-9, 
39-12 
Collection and Study of Basic Data 
Alaska District (NPA) 40-7 
Albuquerque, N. Mex., District (SWA) 32-10 
Baltimore, Md., District (NAB) 4-22 
Buffalo, N.Y., District (NCB) 20-16 
Chicago, Ill., District (NCC) 22-9 
Detroit, Mich., District (NCE) 21-30 
Fort Worth, Tex., District (SWF) 30-13 
Galveston, Tex., District (SWG) 31-14 
Huntington, W. Va., District (ORH) 17-11 
Jacksonville, Fla., District (SAJ) 9-25 
Kansas City, Mo., District (MRK) 27-20 
Little Rock, Ark., District (SWL) 28-10 
Los Angeles, Calif., District (SPL) 33-9 
Louisville, Ky., District (ORL) 16-12 
Memphis, Tenn., District (LMM) 13-6, 13-12 
Mississippi River and Tributaries Project (MR+T) 
42-64 
Mobile, Ala., District (SAM) 10-27 
Nashville, Tenn. District (ORN) 15-8 
I-13

New England Division (NED) 1-24 
New Orleans District (LMN) 11-20 
New York District (NAN) 2-21 
Norfolk, Va., District (NAO) 5-10, 5-14 
Omaha, Nebr., District (MRO) 26-22 
Pacific Ocean District (POD) 36-5 
Philadelphia, Pa., District (NAP) 3-14 
Pittsburgh, Pa., District (ORP) 18-10 
Portland, Oreg., District (NPP) 37-21 
Rock Island, Ill., District (NCR) 23-6 
Sacramento, Calif., District (SPK) 35-22 
San Francisco, Calif., District (SPN) 34-5 
Savannah, Ga., District (SAS) 8-9 
Seattle, Wash., District (NPS) 38-11 
St. Louis, Mo., District (LMS) 14-6, 14-16 
St. Paul, Minn., District (NCS) 24-21, 24-35 
Tulsa, Okla., District (SWT) 29-10, 29-22 
Vicksburg, Miss., District (LMK) 12-8, 12-22 
Walla Walla, Wash., District (NPW) 39-8 
Wilmington, N.C., District (SAW) 6-17 
Colliers, W. Va. (ORP) 18-25 
Collinsville, Ala. (SAM) 10-48 
Colonial Beach, Va. (NAB) 4-38 
Colorado River, Matagorda, Tex. (SWG) 31-31 
Colorado River at Grand Junction, Colo. (SPK) 35-40 
Colorado River Channel (SWG) 31-36 
Colorado Springs, Colo. (Templeton Gap Floodway) 
(SWA) 32-14 
Columbia, La. (LMK) 12-14, 12-17 
Columbia and Lower Willamette Rivers below 
Vancouver, Wash., and Portland, Oreg. (NPP) 37-2, 
37-23, 37-30, 37-38, 37-42 
Columbia Drainage and Levee District No. 3, Ill. 
(LMS) 14-14 
Columbia Drainage District 1, Oreg. (NPP) 37-41, 
37-44 
Columbia River, Wash. (NPP) 37-42 
Columbia River and Tributaries above Celilo Falls to 
Kennewick, Wash. (NPW) 39-14 
Columbia River at Baker Bay, Wash. (NPP) 37-23, 
37-31 
Columbia River at the Mouth, Oreg. and Wash. 
(NPP) 37-4, 37-23, 37-31 
Columbia River Basin, Local Flood Protection 
Projects (NPS) (NPW) 38-28, 39-1, 39-12, 39-16 
Columbia River Basin, Local Protection Projects, 
Idaho, Mont., and Wash. (NPS) 38-25, 38-30 
Columbia River between Chinook, Wash., and Head 
of Sand Island (NPP) 37-4, 37-23, 37-31 
Columbia River between Vancouver, Wash., and The 
Dalles, Oreg. (NPP) 37-4, 37-23, 37-31 
Columbia River Treaty Entities 49-2 
Columbia River Treaty Permanent Engineering Board 
49-2 
Columbia River, Wenatchee to Kettle Falls, Wash. 
(NPS) 38-24 
Columbia Slough, Oreg. (NPP) 37-41 
Columbus, Loop River, Nebr. (MRO) 26-20 
Columbus, Ohio (ORH) 17-22 
Columbus Flood Control Project, Lost Creek, Columbus, 
Nebr. (MRO) 26-20 
Compo Beach, Westport, Conn. (NED) 1-41 
Conant Brook Dam, Mass. (NED) 1-14, 1-28, 1-48 
Conchas Lake, N. Mex. (SWA) 32-2, 32-10 
Concordia, Ky. (ORL) 16-21, 16-26 
Conemaugh River Lake, Ohio River Basin, Pa. (ORP) 
18-4, 18-12, 18-16, 18-25 
Conesus Lake, Livonia, N.Y. (NCB) 20-15, 20-21, 
20-34 
Conetoe Creek, N.C. (SAW) 6-27 
Coney Island Channel, N.Y. (NAN) 2-34 
Coney Island Creek, N.Y. (NAN) 2-37 
Conklin-Kirkwood, N.Y. (NAB) 4-39, 4-42 
Conneaut Harbor, Ohio (NCB) 20-4, 20-17, 20-25 
Connecticut River, Comish, N.H. (NED) 1-23 
Connecticut River, Northampton, Mass. (NED) 1-47 
Connecticut River, North Stratford, N.H. (NED) 1-42 
Connecticut River, W. Stewartstown, NH (NED)1-42 
Connecticut River (above Hartford), Conn. (NED) 
1-24, 1-38 
Connecticut River Basin, Vt., N.H., Mass. and Conn. 
(NED) 1-12, 1-23, 1-48 
Connecticut River below Hartford, Conn. (NED) 1-4, 
1-24, 1-25, 1-33, 1-44, 1-53 
Connell, Wash. (NPW) 39-15 
Conoho Creek, N.C. (SAW) 6-28 
Consolidated Diking and Improvement District 1, 
Cowlitz County, Wash. (NPP) 37-38 
Construction Engineering Research Laboratory 
(CERL) 43-1 
Construction General (MR+T) 42-10 
Construction of Locks and Dams, Ohio River (ORD) 
(ORH) (ORL) (ORP) 16-2, 17-2, 18-2, 19-1, 19-5, 
19-6 
I-14

INDEX 
Contentnea Creek, N.C. (SAW) 6-25, 6-27, 6-28 
Conway County Drainage - Levee District 1, 
Arkansas River, Ark. (SWL) 28-17 
Conway County Levee District No. 6, Arkansas 
River, Ark. (SWL) 28-17 
Conway County Levee Districts Nos. 1, 2 and 8 
Arkansas River, Ark. (SWL) 28-17 
Cook Inlet Shoals, Alaska (NPA) 40-12 
Cooley Canal Lucas Co., Ohio (NCB) 20-38 
Cooper Lake and Channels, Tex. (LMN) (SWF) 
11-18, 30-4, 30-15, 30-19 
Cooper River, NJ. (NAP) 3-24 
Cooper River, Charleston Harbor, S.C. (SAN) 7-3, 
7-8, 7-11 
Cooper River, Pompion Hill Chapel, S.C. (SAN) 7-16 
Cooper River Seismic Modification, S.C. (SAN) 7-3, 
7-8, 7-11 
Coordinating Committee on Great Lakes Basic 
Hydraulic and Hydrologic Data Board (NCE) 
21-29, 49-2 
Coos and Millicoma Rivers, Oreg. (NPP) 37-6, 37-24, 
37-32 
Coos Bay, Oreg. (NPP) 37-5, 37-24, 37-31, 37-42 
Coosa River, Montgomery to Gadsden, Ala. (SAM) 
10-22, 10-35 
Copan Lake, Okla. (SWT) 29-4, 29-12, 29-17 
Copes Comer Lakes, N.Y. (NAB) 4-40 
Coquille River, Oreg. (NPP) 37-6, 37-24, 37-32, 
37-41, 37-42 
Coralville Lake, Iowa (NCR) 23-3, 23-7, 23-11 
Coraopolis, Pa. (ORP) 18-21 
Corbin (Lynn Camp Creek), Ky. (ORN) 15-13, 
15-19 
Cordell Hull Lock and Dam, Tenn. (ORN) 15-14 
Cordova Harbor, Alaska (NPA) 40-12, 40-14 
Core Creek, N.C. (SAW) 6-27 
Corea Harbor, Gouldsboro, Maine (NED) 1-38 
Coming, N.Y. (NAB) 4-16, 4-28 
Coming-Monkey Run, N.Y. (NAB) 4-42 
Comrnucopia Harbor, Wis. (NCE) 21-5, 21-32, 21-44 
Corpus Christi, Tex., Channel to Navy Seaplane 
Base, Encinal Peninsula (SWG) 31-30 
Corpus Christi Beach, Tex. (Restoration Project) 
(SWG) 31-9, 31-16, 31-28 
Corpus Christi Ship Channel, Tex. (SWG) 31-2, 
31-15, 31-18, 31-32, 31-33, 31-38 
Corsica River, Md. (NAB) 4-37 
Corson Inlet and Ludlam Beach, NJ. (NAP) 3-26 
Corte Madera Creek, Calif. (SPK) 35-7, 35-24, 
35-31 
Cortland, N.Y. (NAB) 4-39, 4-42 
Cottage Grove Lake, Oreg. (NPP) 37-11, 37-26, 
37-34, 37-43, 37-45 
Cottonwood Creek, Calif. (SPK) 35-23, 35-30 
Cottonwood Creek Community Church, Culdesac, 
Idaho (NPW) 39-15 
Cottonwood Creek Dam, Boise, Idaho (NPW) 39-14, 
39-16 
Cottonwood Slough Pumping Plant, Ill. (LMM) 13-5 
Cotuit Harbor, Mass. (NED) 1-44 
Cougar Lake, Oreg. (NPP) 37-17, 37-27, 37-35, 
37-43, 37-45 
Coulee des Gaues (MR+T) 42-13 
Council Bluffs, Iowa (MRO) 26-15, 26-18 
Council Bluffs, Missouri River, Iowa (MRO) 26-20 
Council Grove Lake, Kan. (SWT) 29-4, 29-12, 29-17 
County Line Rd. Branch, Mantachie, Miss. (SAM) 
10-49 
Courtenay Channel, Fla. (SAJ) 9-47 
Cove Island, Stamford, Conn. (NED) 1-41 
Covered Bridge, Housatonic River, Sheffield, Mass. 
(NED) 1-17, 1-24, 1-29, 1-36 
Covington, Ky. (ORL) 16-19, 16-24, 16-29 
Cow Castle Creek, S.C. (SAN) 7-15 
Cow Creek Channel Improvement, Kans. (SWT) 
29-19 
Cowanesque Lake, Pa. (NAB) 4-8, 4-28 
Coweta Creek, Okla. (SWT) 29-21 
Cowlitz County Consolidated Diking Improvement 
District 1, Wash. (NPP) 37-41, 37-44 
Cowlitz County Diking Improvement Districts 2, 13 
and 15, Wash. ; NPP) 37-44 
Cowlitz County Drainage Improvement District 1, 
Wash. (NPP) 37-44 
Cowlitz River, Wash. (NPP) 37-37, 37-38, 37-39 
Cowlitz River at Randle, Wash. (NPP) 37-41 
Cowpens Swamp, S.C. (SAN) 7-15 
Cox Run, Wellsburg, W.Va. (ORP) 18-26 
Coyote and Berryessa Creeks, Calif. (SPK) 35-23, 
35-30 
Coyote and Spencer Creeks, Oreg. (NPP) 37-41 
Coyote Creek, Calif. (SPK) 35-23, 35-30, 35-34, 
Coyote Valley Dam (Lake Mendocino) and Channel 
Improvements, Calif. (SPK) 35-38 
Crabtree Swamp, S.C. (SAN) 7-15 
Craig Harbor, Alaska (NPA) 40-12, 40-15 
I-15

Crane Creek, Melbourne, Fla. (SAJ) 9-54 
Crane Creek Drainage and Levee District (NCR) 
23-12, 23-15 
Cranes Creek, Va. (NAO) 5-19 
Crawford County Levee District, Ark. (SWL) 28-17 
Crawford County Levee District, Arkansas River, 
Ark. (SWL) 28-17 
Creede, Willow Creek, Colo. (Floodway) (SWA) 
32-14 
Crescent City Harbor, Calif. (SPN) 34-6 
Cribbs Mill Creek, Tuscaloosa, Ala. (SAM) 10-49 
Criehaven Harbor, Maine (NED) 1-38 
Crisfield Harbor Md. (NAB) 4-5, 4-24, 4-32, 4-38 
Crooked and Dry Jordan Creeks, Harrison, Ark. 
(SWL) 28-25 
Crooked Creek, Bennettsville, S.C. (SAN) 7-16 
Crooked Creek Lake, Ohio River Basin, Pa. (ORP) 
18-4, 18-12, 18-16, 18-25 
Crooked Creek Lake and Levee, Ark. (SWL) 28-18 
Croocked-Perkins Creeks, Paducah, Ky. (ORL) 16-31 
Cross Creek, Paducah, Ky. (ORL) 16-31 
Cross-Florida Barge Canal (SAJ) 9-4, 9-26, 9-32, 
9-43, 9-44 
Cross Lake, N.Y. (NCB) 20-39 
Cross Rip Shoals Nantucket Sound, Mass. (NED) 1-38 
Cross Village, Mich. (NCE) 21-55 
Crown Point, N.Y. (NAN) 2-39 
Crows Run, Conway, Pa. (ORP) 18-26 
Crutcho Creek Channel Improvement, Okla. (SWT) 
29-19 
Crystal River, Fla. (SAJ) 9-47 
Cucamonga Creek, Santa Ana River Basin, Calif. 
(SPL) 32-25 
Cuckold Creek, Md. (NAB) 4-40 
Cuivre River, Mo. (LMS) 14-13 
Cumberland, Ky. (ORN) 15-9, 15-18 
Cumberland, Md., and Ridgeley, W. Va. (NAB) 4-13, 
4-26, 4-35, 4-42 
Cumberland River above Nashville (ORN) 15-11, 
15-14 
Cumberland River below Nashville (ORN) 15-11 
Cumberland River, Tenn. and Ky. (ORN) 15-2, 15-9, 
15-15 
Cummings Park, Stamford, Conn. (NED) 1-41 
Cunninghill Cove, Md. (NAB) 4-40 
Curia Creek Drainage District, Independence County, 
Ark. (SWL) 28-17 
Current River, and Tributary A, Van Buren, Mo. 
(SWL) 28-25 
Curry Creek Dam and Lake, Ga. (SAS) 8-16 
Curtis Merritt Harbor (Formerly Chincoteague Harbor 
of Refuge), Va. (NAO) 5-21 
Curwensville Lake, Pa. (NAB) 4-1, 4-20, 4-28 
Cushman-Mapleton Channels, Oreg. (NPP) 37-37 
Cuttyhunk Harbor, Mass. (NED) 1-38 
Cuyahoga River, Akron Peninsula Rd., Ohio (NCB) 
20-39 
Cuyahoga River, Brecksville Rd., Ohio (NCB) 20-39 
Cuyahoga River, North Portage Path, Akron, Ohio 
(NCB) 20-39 
Cuyahoga River, Riverview Rd., Northampton, Ohio 
(NCB) 20-39 
Cuyahoga River Basin, Ohio (NCB) 20-37 
Cypress Bayou and Waterway between Jefferson, Tex. 
and Shreveport, La. (LMN) (LMK) 11-16, 12-15 
Cypress Creek, Ky. (ORL) 16-30 
Cypress Creek, Md. (NAB) 4-37 
D 
Dade County, Fla. (SAJ) 9-23, 9-30, 9-40 
Dade County, North of Haulover Beach, Fla. (SAJ) 
9-23, 9-30, 9-40 
Dale Hollow Lake, Ohio River Basin, Tenn. and Ky. 
(ORN) 15-7, 15-9, 15-18 
Dallas Floodway, Tex. (SWF) 30-22 
Dam "A" Lake, Tex. (SWF) 30-22 
Dam and Bridge, Neosho River, Kan. (SWT) 29-21 
Dam Safety Program, New York District (NAN) 2-21 
Damariscotta River, Maine (NED) 1-38 
Dams and Reservoirs (SAW) 6-30 
Dan River, Madison Wastewater Treatment Plant, 
N.C. (SAW) 6-12, 6-20 
Dana Point Harbor, Calif. (SPL) 33-23 
Danbury, Conn. (NED) 1-23, 1-42, 1-50 
Dansville and Vicinity, Canaseraga Creek, N.Y. 
(NCB) 20-37 
Dardanelle Lock - Dam (No. 10), Ark. (SWL) 28-9, 
28-13, 28-20 
Darien Harbor, Ga. (SAS) 8-16 
Dashields Locks and Dams, Pa. (ORD) 19-7 
Dauphin Island Bay, Ala. (SAM) 10-7, 10-32, 10-39 
Davenport, Iowa (NCR) 23-14 
I-16

INDEX 
Davenport Center Lake, N.Y. (NAB) 4-40 
Davenport Harbor, Iowa (Lindsay Park) (NCD) 25-7, 
25-10 
David D. Terry Lock and Dam (No. 6), Ark. (SWL) 
28-3, 28-19 
Davids Creek Lake, Iowa (MRO) 26-17 
Davis, N.C. (SAW) 6-28 
Davis Creek, Va. (NAO) 5-19, 5-21 
Davis Pond, La. (MR+T) 42-11 
Day, John, Lock and Dam-Lake Umatilla, Oreg. and 
Wash. (NPP) 37-19, 37-28, 37-35, 37-46 
Day, John, River, Oreg. (NPP) 37-38, 37-41 
Days Creek Lake, Oreg. (NPP) 37-39 
Dayton, Ky. (ORL) 16-19, 16-24, 16-29 
Dayton Touchet River, Wash. (NPW) 39-14, 39-15 
Dayton, Wyo. (MRO) 26-17 
Daytona Beach Side Channel, Fla. (SAJ) 9-46 
De Soto, Mississippi River, Wis. (NCS) 24-33 
De Witt, Big Blue River and Turkey Creek, Nebr. 
(MRK) 27-21 
Deadman's Gulch, Sturgis, S.D. (MRO) 26-16, 
26-19 
Deep Creek, Edgecombe County, N.C. (SAW) 6-27 
Deep Creek, Accomack Co., Va. (NAO) 5-19 
Deep Creek, Newport News, Va. (NAO) 5-19, 5-21 
Deep River, Wash. (NPP) 37-37 
Deep River Area, Wash. (NPP) 37-38 
Deer Creek, Oreg. (NPP) 37-43 
Deer Creek Lake, Ohio River Basin, Ohio (ORH) 
17-3 
Deer Creek Lake, Ohio River Basin, W.Va. (ORH) 
17-3, 17-12, 17-17 
Deer Creek Prairie Levee, Ind. (ORL) 16-21 
Deer Creek Prairie Levee, Ind. (Wabash River) (ORL) 
16-25 
Deer Island Area, Oreg. (NPP) 37-38 
Deer Island Drainage District, Oreg. (NPP) 37-41, 
37-44 
Deer Island Thoroughfare, Maine (NED) 1-38 
Degognia and Fountain Bluff Levee and Drainage 
District, Ill. (LMS) 4-14 
DeGray Lake, Ark. (LMK) 12-17, 12-20 
DeKalb, Ill. (NCR) 23-15 
DeKalb, Kishwaukee River, Ind. (NCR) 23-16 
Delaware Bay to Millville (fixed bridge to upper end 
of project) 3-24 
Delaware Coast Protection, Del. (NAP) 3-12, 3-17, 
3-22 
Delaware Creek, Dallas, Tex. (SWF) 30-23 
Delaware Lake, Ohio River Basin , Ohio (ORH) 17-4, 
17-12, 17-17 
Delaware River at Pennsville, NJ. (NAP) 3-24 
Delaware River between Philadelphia, Pa., and 
Trenton, NJ. (NAP) 3-4, 3-15, 3-19 
Delaware River in Vicinity of Camden, NJ. (NAP) 
3-5, 3-16, 3-20 
Deleware River, Mouth of Neversink (NAP) 3-27 
Delaware River, Pa., NJ. and Del., Philadelphia to the 
Sea (NAP) 3-4, 3-15, 3-20 
Delphi, Ind. (Wabash River) (ORL) 16-19, 16-24, 
16-29 
Dennis Creek, NJ. (NAP) 3-24 
Depoe Bay, Oreg. (NPP) 37-37, 37-39 
Dequeen Lake, Ark. (SWL) 28-5, 28-12, 28-23 
Derby, Conn. (NED) 1-23, 1-42, 1-50 
Derby, Ind. (ORL) 16-21, 16-25 
Des Moines, Iowa (NCR) 23-12, 23-15 
Des Moines and Mississippi Levee District No. 1, 
Mo. (NCR) 23-12, 23-15 
Des Moines Recreational River and Greenbelt, Iowa 
(NCR) 23-3, 23-7, 23-11 
Des Moines River, Iowa (NCR) 23-16 
Des Moines River,. Bridge 32527, Minn. (NCR) 23-17 
Deschutes River Bend, Oreg. (NPP) 37-11, 37-26, 
37-34 
Deschutes River, Wash. (NPS) 38-25 
Deshler, Snake, and Spring Creeks, Nebr. (MRK) 
27-21 
Detour Harbor, Mich. (NCE) 21-5, 21-32, 21-44 
Detroit Lake, Oreg. (NPP) 37-18, 37-27, 37-35, 37-43, 
37-45 
Detroit River, Mich. (NCE) 21-6, 21-32, 21-44, 21-57 
Detroit River, Channels and Shoals, Mich. (NCE) 
21-58 
Devils Lake, N. Dak. (NCS) 24-5, 24-22 
Devil's Swamp, barge channel at Baton Rouge, La. 
(MR+T) 42-29 
Dewey Lake, Ohio River Basin, Ky. (ORH) 17-4, 
17-13, 17-17 
Dickey Lake, Maine (NED) 1-44 
Dickinson Bayou, Tex. (SWG) 31-30 
Dierks Lake, Ark. (SWL) 28-5, 28-12, 28-23 
Diking and Improvement District 4, Wahkiakum 
County, Wash. (NPP) 37-38 
Diking and Improvement District 5, Cowlitz County, 
Wash. (NPP) 37-38 
I-17

Diking and Improvement District 11, Cowlitz 
County, Wash. (NPP) 37-38 
Diking Districts 1 and 3 (Puget Island) and Little 
Island, Wash. (NPP) 37-38 
Diking Districts 2, 3, and 5, Clatsop County, Oreg. 
(NPP) 37-38 
Diking Improvement District 1, Pacific County, 
Wash. (NPP) 37-38 
Dillingham Emergency Bank Stabilization, Alaska 
(NPA) 40-6, 40-9, 40-11 
Dillingham Harbor, Alaska (NPA) 40-2, 40-8, 40-10 
Dillingham Small Boat Harbor, Ark. (NPA) 40-13 
Dillon Lake, Ohio River Basin, Ohio (ORH) 17-4, 
17-13, 17-17 
Dillonvale, Ohio (Short Creek) (ORP) 18-21 
Disaster Preparedness Program (MRK) (SAM) 10-1, 
27-7, 27-21, 52-1 
Dismal Swamp Canal (Deep Creek), Va. (NAO) 5-18 
Dismal Swamp Canal (South Mills, N.C.) (NAO) 5-18 
Dively Drainage-Levee District, Ill. (LMS) 14-14 
Dodge City, Kans. (SWT) 29-19, 29-20 
Doe and Watanga River, Elizabethtown, Tenn. (ORN) 
15-19 
Dog and Fowl Rivers, Ala. (SAM) 10-7, 10-32, 10-40 
Dog Creek, Okla. (SWT) 29-21 
Doheny Beach State Park (Doheny State Beach), 
Calif. (SPL) 33-24 
Dorchester Bay and Neponset River, Mass. (NED) 
1-38 
Dorena Lake, Oreg. (NPP) 37-11, 37-26, 37-34, 
37-43, 37-45 
Double Bayou, Tex. (SWG) 31-30 
Double Creek, N.J. (NAP) 3-24 
Douglas Harbor, Alaska (NPA) 40-12 
Dover, Ky. (ORH) 17-21 
Downeyville Lake, Ind. (ORL) 16-28 
Downeyville Lake, Ind. (Wabash River) (ORL) 16-20 
Drainage District 1, Clatsop County, Oreg. (NPP) 
37-38 
Dredging Operations (SWG) 31-38 
Drinkwater Sewer, Mo. (LMM) 13-5 
Drum Inlet, N.C. (SAW) 6-25 
Drury Drainage District, Ill. (NCR) 23-12, 23-15 
Dry Branch, Irving, Tex. (SWF) 30-23 
Dry Branch, Salem, Va. (SWF) 6-31 
Dry Brook Creek, Poland, N.Y. (ORP) 18-26 
Dry Branch Creek, Grand Prairie, Tex. (SWF) 30-23 
Dry Creek, Goodlettsville, Tenn. (ORN) 15-19 
Dry Creek, Hawarden, Iowa (MRO) 26-16 
Dry Creek (Warm Springs), Calif. (SPK) 35-26, 35-38 
Dry Creek, Wash. (NPW) 39-15 
Dry Fork and East Fork Lakes, Fishing River, Mo. 
(MRK) 27-16 
Dry Pass, Alaska (NPA) 40-12 
Dry Run, Iowa (NCS) 24-28 
DuBois, Pa. (ORP) 18-20, 18-25 
Dubuque, Iowa (NCR) 23-12, 23-15 
Dubuque Harbor, Iowa (NCD) 25-7 
Duck Creek Channel Improvement, Tex. (SWF) 
30-22 
Duck Creek, Elwood, Ind. (ORL) 16-31 
Duck Creek, San Joaquin Co., Calif. (SPK) 35-34 
Duck Island Harbor, Conn. (NED) 1-38, 1-53 
Duck Point Cove, Md. (NAB) 4-37, 4-41 
Duck River, Tenn. (ORN) 15-13 
Duluth-Superior Harbor, Minn. and Wis. (NCE) 21-6, 
21-30, 21-32, 21-45 
Dune Acres, Ind. (NCC) 22-8 
Duneland Beach, LaPorte Co., Ind. (NCC) 22-8 
Dungeness River, Wash. (NPS) 38-25, 38-29 
Dunkirk Harbor, N.Y. (NCB) 20-3, 20-17, 20-26 
Dunn Branch, Woodbine, Camden County, Ga. 
(SAS) 8-16 
Duval County, Fla. (SAJ) 9-19, 9-30, 9-41 
Duxbury Harbor, Mass. (NED) 1-38 
Dworshak Dam and Reservoir, Idaho (NPW) 39-4, 
39-13, 39-18 
Dyersburg, Tenn. (LMM) 13-5 
Dyersburg, Tenn. (Southwest) (LMM) 13-5 
Dymers Creek, Va. (NAO) 5-19 
E 
Eagle Bay and Fort Yates Highway Bridges, N. Dak. 
(MRO) 26-16 
Eagle Creek, Ohio (ORP) 18-25 
Eagle Creek, S.C. (SAN) 7-15 
Eagle Creek Lake, Ky. (ORL) 16-20 
Eagle Creek Reservoir, Ohio (ORP) 18-20 
Eagle Harbor, Mich. (NCE) 21-55, 21-60 
East Barre Dam, Vt. (NAN) 2-36 
East Bay (Hanna Reef), Tex. (SWG) 31-30 
East Bay Small Boat Basin, Olympia, Wash. (NPS) 
38-24 
East Boothbay Harbor, Maine (NED) 1-38 
East Bow Creek, Cedar Co., Wyo. (MRO) 26-23 
I-18

INDEX 
East Branch, Clarion River Lake, Ohio River Basin, 
Pa. (ORP) 18-5, 18-12, 18-17, 18-25 
East Branch Dam, Conn. (NED) 1-23, 1-42, 1-50 
East Brimfield Lake, Mass. (NED) 1-21, 1-23, 1-31, 
1-52 
East Cape Girardeau and Clear Creek Drainage 
District, Ill. (LMS) 14-14 
East Chester Creek, N.Y. (NAN) 2-3, 2-22, 2-27, 2-34 
East Fork, Tex. (SWF) 30-22 
East Fork of Boyer River, Near Vail, Iowa (MRO) 
26-21 
East Fork White River, Brownstown, Jackson Co., 
Ind. (ORL) 16-30 
East Hartford, Conn. (NED) 1-23, 1-42, 1-49 
East Lake, Ohio, Chagun River (NCB) 20-37 
East Liverpool Drainage and Levee District (NCR) 
23-12, 23-15 
East Lynn Lake, Ohio River Basin, W. Va (ORH) 
17-5, 17-13, 17-18 
East Moline, Ill. (NCR) 23-13, 23-15 
East Molokai, Molokai, Hawaii (POD) 36-14 
East Muddy and Lake Creek, Oreg. (NPP) 37-41 
East Muddy Creek, Mo. (MRK) 27-16 
East Nishnabotna River, near Griswold, Iowa 
(MRO) 26-20 
East Nishnabotna River, Page Co. Bridge, near 
Essex, Iowa (MRO) 26-20 
East Nishnabotna River, Red Oak, Iowa (MRO) 26-2 
East Pass Channel from Gulf of Mexico into 
Choctawhatchee Bay, Fla. (SAM) 10-8, 10-32, 
10-40 
East Peoria, Ill. (NCR) 23-16 
East Peoria Drainage and Levee District (NCR) 23-12, 
23-15 
East Peoria Sanitary District, Ill. (NCR) 23-15 
East Point, La. (LMN) (LMK) 11-8, 12-20 
East Poplar Bluff-Poplar Bluff, Mo. (SWL) 28-17 
East Rainelle, W. Va. (ORH) 17-21, 17-23 
East River, N.Y. (NAN) 2-3, 2-22, 2-27, 2-33 
East Rockaway Inlet, N.Y. (NAN) 2-4, 2-22, 2-28, 
2-37 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, N.Y. (Part I) (NAN) 2-16, 2-25, 2-31 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, N.Y. (Part II) (NAN) 2-36 
East Sidney Lake, N.Y. (NAB) 4-16, 4-28 
East St. Louis and Vicinity, Ill. (LMS) 14-3, 14-8, 
14-10 
East Weaver Creek, Calif. (SPK) 35-34 
East, West, and Duwamish Waterways, Seattle 
Harbor, Wash. (NPS) 38-12 
Eastchester Creek, N.Y. (NAN) 2-33 
Eastern Branch, Va. (NAO ) 5-16 
Eastern Rapides and South-Central Avoyelles 
Parishes, La. (MR+T) 42-15, 42-30 
Eastport Harbor, Maine (NED) 1-44 
Eau Galle River, Wis. (NCS) 24-6, 24-22, 24-33 
Eau Gallie Harbor, Fla. (SAJ) 9-5, 9-26, 9-32 
Echo Bay Harbor, N.Y. (NAN) 2-34 
Edenton Harbor, N.C. (SAW) 6-25 
Edgar Jadwin, General, Dam and Reservoir, Pa. 
(NAP) 3-13, 3-17 
Edgartown Harbor, Mass. (NED) 1-38 
Edisto River, S.C. (SAN) 7-14, 7-15 
Edisto River, North Fork, S.C. (SAN) 7-15 
Edisto River, Vicinity Canadays Landing, S.C. (SAN) 
7-15 
Ediz Hook, Wash. (NPS) 38-2, 38-14, 38-19, 38-29 
Edgartown Harbor, Mass. (NED) 1-44 
Edmonds Harbor, Wash. (NPS) 38-24 
Edward MacDowell Lake, N.H. (NED) 1-18, 1-30, 
1-51 
Eel River, Calif. (SPK) 35-36 
Eel River, Ind. (ORL) 16-30 
Egegik River, Alaska (NPA) 40-12 
Eight Mile Creek, Ark. (MR+T) 42-30 
Eighteen Mile Island, Ky. (ORL) 16-30 
El Dorado Lake, Kan. (SWT) 29-4, 29-12, 29-17, 
29-19 
El Paso, Tex. (SWA) 32-2, 32-10, 32-12 
El Tuque Beach, Ponce, P.R. (SAJ) 9-48 
Elder and Unionhouse Creeks, Calif. (SPK) 35-40 
Eldred, Ill. (LMS 14-14 
Eldred, Pa. (ORP 18-25 
Eldred and Spankey Drainage and Levee District, Ill. 
(LMS) 14-10 
Elfin Cove, Alaska (NPA) 40-12 
Elizabeth, NJ. (NAN) 2-36, 2-37 
Elizabeth River, Hillside, N.J. (NAN) 2-18 
Elizabethtown, Ill. (ORL) 16-21, 16-25 
Elk and Little Elk Rivers, Md. (NAB) 4-37 
Elk City Lake, Kan. (SWL) (SWT) 28-22, 29-4, 
29-12, 29-17, 29-20 
Elk Creek, Clyde, Kan. (MRK) 27-16 
Elk Creek Harbor, Pa. (NCB) 20-35 
Elk Creek, Jackson, Nebr. (MRO) 26-20 
I-19

Elk Creek Lake, Oreg. (NPP) 37-11, 37-26, 37-34 
Elk Creek, Willis, Nebr. (MRO) 26-20 
Elk River, Ala. and Tenn. (ORN) 15-13 
Elk River, Minn. (NCS) 24-28, 24-33 
Elk River, W. Va (ORH) 17-20 
Elkhom River, Beemer, Nebr. (MRO) 26-23 
Elkhom River, Norfolk, Nebr. (MRO) 26-23 
Elkhorn River, Q Street Bridge, near Gretna, Nebr. 
(MRO) 26-20 
Elkhorn River, Ray Bridge, near Norfolk, Nebr. 
(MRO) 26-20 
Elkins, W. Va. (ORP) 18-3, 18-11, 18-16 
Elkins, W. Va. (Monongahela River Basin) (ORP) 
18-24 
Elkland, Pa. (NAB) 4-39, 4-42 
Elkport, Iowa (NCR) 23-13, 23-15 
Elks Creek, Clarksburg, W.Va. (ORP) 18-26 
Ellerbe Creek, Durham County, N.C. (SAW) 6-27 
Ellicott Creek, N.Y. (NCB) 20-13, 20-20, 20-33 
Ellicott Creek, Lehn Springs, N.Y. (NCB) 20-39 
Ellicotts Creek, Moundville, Ala. (SAM) 10-49 
Ellis Swamp, Gates County, N.C. (SAW) 6-27 
Elm Creek, Burt Co., Nebr. (MRO) 26-20 
Elm Fork Floodway, Tex. (SWF) 30-22, 30-23 
Elm River, Decatur, Nebr. (MRO) 26-20 
Elmira, N.Y. (NAB) 4-6, 4-28 
Elochoman Slough, Wash. (NPP) 37-37, 37-42, 
Elwha River, Wash. (NPS) 38-7, 38-16, 38-21, 38-25 
Emergency Bank Protection Activities 
Albuquerque, N. Mex., District (SWA) 32-10 
Buffalo, N.Y., District (NCB) 20-39 
Louisville, Ky., District (ORL) 16-31 
Nashville, Tenn., District (ORN) 15-19 
Omaha, Nebr., District (MRO) 26-7 
Philadelphia, Pa., District (NAP) 3-12 
Pittsburgh, Pa., District (ORP) 18-26 
Rock Island, Ill., District (NCR) 23-6, 23-17 
Sacramento, Calif., District (SPK) 35-20 
San Francisco, Calif., District (SPN) 34-4 
St. Louis, Mo., District (LMS) 14-14 
St. Paul, Minn., District (NCS) 24-34 
Vicksburg, Miss., District (LMK) 12-7, 12-9 
Emergency Bank Stabilization Activities (LMM) 13-2 
Emergency Flood Control Activities 
Albuquerque, N. Mex., District (SWA) 32-9 
Kansas City, Mo., District (MRK) 27-21 
Memphis, Tenn., District (LMM) 13-12 
New Orleans District (LMN) 11-10 
Norfolk, Va., District (NAO) 5-10, 5-14 
Rock Island, Ill., District (NCR) 23-6 
Sacramento, Calif., District (SPK) 35-20 
San Francisco, Calif., District (SPN) 34-4 
Seattle, Wash., District (NPS) 38-29 
St. Louis, Mo., District (LMS) 14-6 
St. Paul, Minn., District (NCS) 24-34 
Tulsa, Okla., District (SWT) 29-8 
Vicksburg, Miss., District (LMK) 12-8 
Emergency protection for certain highway and railroad 
facilities at Chester, Ill., bridge (LMS) 14-14 
Emergency protection for Illinois approach, Chain 
of Rocks Bridge (LMS) 14-14 
Emergency repairs to levees on Mississippi, Illinois, 
and Kaskaskia Rivers (LMS) 14-14 
Emergency Shore Protection (NCE) (MRK) 21-25, 
27-21 
Emergency Streambank and Shoreline Protection 
(Authorized and Special Authorization) 
Galveston, Tex., District (SWG) 31-13 
Kansas City, Mo., District (MRK) 27-7, 27-21 
New York, N.Y., District (NAN) 2-21 
Pacific Ocean Division (POD) 36-4, 36-14 
Savannah, Ga., District (SAS) 8-7 
Tulsa, Okla., District (SWT) 29-21 
Emerson, Indian Creek, Mills County, Iowa (MRO) 
26-21 
Emerson, Manitoba-Noyes, Minn. (NCS) 24-6, 24-22 
Empire-Stratton, Ohio (ORP) 18-21 
Emsworth Locks and Dams, Pa. (ORD) 19-7 
Enderlin, N. Dak. (NCS) 24-7, 24-22, 24-33 
Endicott-Johnson City and Vestal, N.Y. (NAB) 4-39, 
4-42 
Engineer Topographic Laboratories (ETL) 46-1 
Engineer Waterways Experiment Station 45-1 
Engineering and Design, Activities, Continuation of 
Planning, Planning, Preconstruction 
Alaska District (NPA) 40-7 
Baltimore, Md., District (NAB) 4-22 
Buffalo, N.Y., District (NCB) 20-16 
Charleston, S.C., District (SAN) 7-1 
Chicago, I1l., District (NCC) 22-9 
Detroit, Mich., District (NCE) 21-30 
Galveston, Tex., District (SWG) 31-14 
Jacksonville, Fla., District (SAJ) 9-46 
Kansas City, Mo., District (MRK) 27-20 
I-20

INDEX 
Little Rock, Ark., District (SWL) 28-10 
Los Angeles, Calif., District (SPL) 33-9 
Louisville, Ky., District (ORL) 16-12 
Mississippi River and Tributaries (MR+T) 42-60, 
42- 61, 42-64 
Mobile, Ala., District (SAM) 10-27, 10-28 
New England Division (NED) 1-24 
New Orleans District (LMM) 11-20 
Omaha, Nebr., District (MRO) 26-22 
Pacific Ocean District (POD) 36-6 
Rock Island, Ill., District (NCR) 23-6 
Sacramento, Calif., District (SPK) 35-22, 35-30 
San Francisco, Calif., District (SPN) 34-5 
Savannah, Ga., District (SAS) 8-9 
Seattle, Wash., District (NPS) 38-11 
St. Louis, Mo., District (LMS) 14-16 
St. Paul, Minn., District (NCS) 24-21, 24-35 
Tulsa, Okla., District (SWT) 29-10, 29-22, 29-33 
Vicksburg, Miss., District (LMK) 12-22 
Walla Walla, Wash., District (NPW) 39-8 
Wilmington, N. C., District (SAW) 6-17 
England Pond Levee, Ill. (Wabash River)(ORL) 
16-19, 16-24, 16-29 
English, Ind. (Little Blue River) (ORL) 16-19, 16-30 
English Coulee, Grand Forks, N. Dak. (NCS) 24-34 
Enid, Okla. (SWT) 29-19 
Entiat River, Wash. (NPS) 38-25 
Erie Harbor, Pa. (NCB) 20-5, 20-18, 20-26, 20-40 
Erosion, Beach (Authorized and under Special Authorization 
Baltimore, Md., District (NAB) 4-13, 4-38, 4-39 
Buffalo, N.Y., District (NCB) 20-13, 20-36 
Charleston, S.C., District (SAN) 7-6, 7-15 
Chicago, Ill., District (NCC) 22-6, 22-17 
Detroit, Mich., District (NCE) 21-25, 21-26 
Galveston, Tex., District (SWG) 31-10 
Jacksonville, Fla., District (SAJ) 9-21 
Los Angeles, Calif., District (SPL) 33-24 
Mobile, Ala., District (SAM) 10-14, 10-47, 10-49 
New England Division (NED) 1-11, 1-41, 1-46 
New Orleans District (LMN) 11-10 
New York District (NAN) 2-16, 2-17, 2-36 
Norfolk, Va., District (NAO) 5-8, 5-20 
Pacific Ocean District (POD) 36-4, 36-11, 36-14 
Philadelphia, Penn., District (NAP) 3-11, 3-12, 3-26 
San Francisco, Calif., District (SPN) 34-4, 34-12 
Savannah, Ga., District (SAS) 8-6 
Wilmington, N.C., District (SAW) 6-26 
Erosion, Streambank (SAN) 7-16 
Escambia and Conecuh Rivers, Fla. and Ala. (SAM) 
10-47 
Escambia Bay, Fla. (SAM) 10-50 
Eslava Creek, Mobile, Ala.(SAM) 10-14, 10-33, 10-44 
Espanola Valley Unit (SWA) 32-14 
Esquatzel Coulee, Wash. (NPW) 39-14 
Esquatzel Coulee, Connell, Wa. (NPW) 39-14, 39-15 
Esquatzel Coulee, Mesa, Wa. (NPW) 39-15 
Essex River, Mass. (NED) 1-38 
Estate Mon Bijou-St. Croix, V.I. (SAJ) 9-54 
Estes, Carl L., Dam and Lake, Tex. (SWF) 30-22 
Euclid Creek, Cleveland, Ohio (NCB) 20-15, 20-21, 
20-34 
Eufaula Lake, Okla. (SWL) (SWT) 28-22, 29-9, 
29-15, 29-18, 29-20 
Evansdale, Iowa (NCR) 23-13, 23-15 
Evanston, Ill. (NCC) 22-17 
Evansville, Ind. (ORL) 16-3, 16-13, 16-24, 16-29 
Everett Harbor and Snohomish River, Wash. (NPS) 
38-2, 38-14, 38-19 
Everett Jordan Dam and Lake, N.C. (SAW) 6-11, 6-15 
Everglades Harbor, Fla. (SAJ) 9-47 
Ewa Beach Landing, Oahu, Hawaii (POD) 36-14 
Exeter River, N.H. (NED) 1-38 
Existing levees and extensions from Bastrop, La. to 
mouth of Boeuf River and at Monroe, La. (LMK) 
12-7 
F 
Fabius River Drainage District, Mo. (NCR) 23-13, 
23-15 
Fair Haven, Mich. (NCE) 21-25 
Fair Haven Beach State Park, Lake Ontario, N.Y. 
(NCB) 20-36 
Fairbanks, Tanana River and Chena Slough, Alaska 
(NPA) 40-13 
Fairbury, Little Blue River, Nebr. (MRK) 27-16 
Fairfield Vicinity Streams, Calif. (SPK) 35-7, 35-25 
Fairport Harbor, Ohio (NCB) 20-5, 20-18, 20-27 
Fajardo Harbor, P.R; (SAJ) 9-47 
Fall Brook Lake, Pa. (NAB) 4-40 
Fall Creek Lake, Oreg. (NPP) 37-12, 37-26, 37-34, 
37-43, 37-45 
Fall River Basin, S. Dak. (MRO) 26-3, 26-9, 26-12 
1-21

Fall River Harbor, Mass. (NED) 1-38, 1-44 
Fall River Lake, Kan. (SWL) (SWT) 28-22, 29-4, 
29-12, 29-17, 29-20 
Falls Lake, N.C. (SAW) 6-13, 6-16, 6-20 
Falmouth Harbor, Mass. (NED) 1-38 
Falmouth Lake, Ky. (Licking River) (ORL)16-20 
Fancy Bluff Creek, Ga. (SAS) 8-15 
Far Creek, N.C. (SAW) 6-5, 6-18 
Farm Creek, Ill. (NCR) 23-4, 23-7, 23-11 
Farmers Levee and Drainage District (NCR) 23-13, 
23-15 
Farmers Levee and Drainage District (Sangamon 
River), Ill. (NCR) 23-14 
Farmington, Des Moines River, Iowa (NCR) 23-17 
Farmington, N.H. (NED) 1-23 
Farmington River, Conn. (NED) 1-24 
Faulkner County Levee District No. 1, Arkansas 
River, Ark. (SWL) 28-17 
Feather Creek, Clinton, Ind. (ORL) 16-31 
Feather River, Calif. (SPK) 35-33 
Features of Existing Project (NCE) 21-58 
Felsenthal, Ark. (LMK) 12-4 
Ferguson Creek, Oreg. (NPP) 37-41 
Fern Ridge Lake, Oreg. (NPP) 37-12, 37-26, 37-43, 
37-45 
Femandina Harbor, Fla. (SAJ) 9-5, 9-27, 9-33 
Ferrells Bridge Dam-Lake O' The Pines, Tex. 
(LMN) (SWF) 11-18, 30-5, 30-15, 30-19 
Filberts Creek, N.C. (SAW) 6-27 
Finney Creek at Wachapreague, Va. (NAO) 5-3, 5-11, 
5-15, 5-21 
Fire Island Inlet to Jones Inlet, N.Y. (NAN) 2-4, 2-22, 
2-28, 2-33, 2-36, 2-39 
Fire Island Inlet to Montauk Point, N.Y. (NAN) 2-36 
Fish River, Baldwin Co., Ala. (SAM) 10-49 
Fisher, O. C., Dam and Lake, Tex. (SWF) 30-8, 30-16, 
30-20 
Fisherman's Wharf Area, San Francisco Harbor, 
Halfmoon Bay, Calif. (SPN) 34-6 
Fishing Bay, Md. (NAB) 4-5, 4-24, 4-32 
Fishing Creek, Md. (NAB) 4-37 
Fishing Creek, N.C. (SAW) 6-25 
Fishing Creek, Pine Grove, W. Va. (ORH) 17-23 
Fishtrap Lake, Ohio River Basin, Ky. (ORH) 17-5, 
17-13, 17-18 
Fitchburg, Mass. (NED) 1-23, 1-42 
Five Mile, Brookside, Ala. (SAM) 10-49 
Fivemile River Harbor, Conn. (NED) 1-38, 1-44 
Flannagan, John W., Dam and Reservoir, Ohio River 
Basin, Va. (ORH) 17-5, 17-13, 17-18 
Flat Creek, Oreg. (NPP) 37-41 
Flat Rock and Valley View Creeks, Okla. (SWT) 
29-19, 29-20 
Flathead River, Mont. (NPS) 38-24, 38-25 
Fletcher and Sunshine Gardens Levee, Ind. (ORL) 
16-21, 16-25 
Flint, Flint River, Mich. (NCE) 21-27 
Flood Control, Allotments and Accrued Expenditures 
for Mississippi River and Tributaries (MR+T) 42-58 
Flood Control and Coastal Emergency Activities 
Mobile, Ala., District (SAM) 10-27 
Omaha, Nebr., District (MRO) 26-22 
Tulsa, Okla., District (SWT) 29-21 
Flood Control Work (Activity), Authorized and Under 
Special Authorization 
Alaska District (NPA) 40-13 
Baltimore, Md., District (NAB) 4-21 
Buffalo, N.Y., District (NCB) 2-37, 2-39 
Charleston, S.C., District (SAN) 7-7, 7-15, 7-16 
Chicago, Ill., District (NCC) 22-17 
Fort Worth, Tex., District (SWF) 30-11, 30-22, 
30-23 
Galveston, Tex., District (SWG) 31-31 
Huntington, W.Va., District (ORH) 17-10, 17-21 
Jacksonville, Fla., District (SAJ) 9-21, 9-25, 9-50, 
9-54 
Kansas City, Mo., District (MRK) 27-7, 27-16, 
27-21 
Little Rock, Ark., District (SWL) 28-5, 28-7, 28-18 
Los Angeles, Calif., District (SPL) 33-25 
Louisville, Ky., District (ORL) 16-12, 16-19, 16-20, 
16-25, 16-26, 16-31 
Memphis, Tenn., District (LMM) 13-2, 13-5 
Mobile, Ala., District (SAM) 10-20, 10-27, 10-48, 
10-49 
Nashville, Tenn., District (ORN) 15-6, 15-13, 15-19 
New England Division (NED) 1-24, 1-42, 1-47 
New Orleans District (LMN) 11-10, 11-18, 11-20 
New York District (NAN) 2-21 
Norfolk, Va., District (NAO) 5-10, 5-14, 5-20 
Omaha, Nebr., District (MRO) 26-15, 26-16, 26-23 
Pacific Ocean District (POD) 36-12, 36-15 
Philadelphia, Pa., District (NAP) 3-12, 3-26, 3-27 
Pittsburgh, Pa., District (ORP) 18-9, 18-20, 18-26 
I-22

INDEX 
Portland, Oreg., District (NPP) 37-38, 37-43 
Rock Island, Ill., District (NCR) 23-6, 23-12, 23-14, 
23-16, 23-17, 23-18 
Savannah, Ga., District (SAS) 8-7, 8-16 
Seattle, Wash., District 38-25, 38-29 
St. Louis, Mo., District (LMS) 14-3, 14-6, 14-14 
St. Paul, Minn., District (NCS) 24-28, 24-34 
Tulsa, Okla., District (SWT) 29-8, 29-19, 29-21 
Vicksburg, Miss., District (LMK) 12-7, 12-8, 12-20, 
12-22 
Walla Walla, Wash., District (NPW) 39-2, 39-15 
Wilmington, N.C., District (SAW) 6-14, 6-27, 6-31 
Flood Damage Prevention Studies 
Buffalo, N.Y., District (NCB) 20-16 
Charleston, S.C., District (SAN) 7-1, 7-14, 7-17 
Chicago, Ill., District (NCC) 22-8, 22-17 
Kansas City, Mo., District (MRK) 27-20 
Mississippi River (MR+T) 42-64 
Omaha, Nebr., District (MRO) 26-21 
St. Louis, Mo., District (LMS) 14-16 
St. Paul, Minn., District (NCS) 24-35 
Tulsa, Okla., District (SWT) 29-22 
Flood Hazard Information (SAM) 10-54 
Flood Insurance Activities 
Detroit, Mich., District (NCE) 21-30 
Mobile, Ala., District (SAM) 10-54 
Sacramento, Calif., District (SPK) 35-20 
Flood Insurance Studies and Flood Hazard 
Information Reports, Mobile, Ala., District (SAM) 
10-54 
Flood Plain Management (NAN) (SAN) 2-37, 7-17 
Floods (MR+T) 42-3 
Floodwall and Levees at Portland, Oreg. (NPP) 37-41 
Florence Levee, Kan. (SWT) 29-20 
Floyd River, Sioux City, Iowa (MRO) 26-16 
Flushing Bay and Creek, N.Y. (NAN) 2-5, 2-22, 2-28, 
2-33 
Fly Creek, Ala. (SAM) 10-8, 10-32, 10-40, 10-50 
Follansbee, W. Va. (ORP) 18-21 
Folly Brook, Wethersfield, Conn. (NED) 1-42, 1-49 
Folly River, S.C. (SAN) 7-8, 7-11, 7-19 
Folsom Lake, Calif. (SPK) 35-34 
Forest Heights, Md. (NAB) 4-39, 4-42 
Forest River, N. D. (NCS) 24-33 
Forestville, Mich. (NCE) 21-57 
Forked Deer River, Tenn., including South Fork 
(LMM) 13-4 
Forsyth, Mont. (MRO) 26-16 
Forsythe, Yellowstone River, Mont. (MRO) 26-18 
Fort Chartres and Ivy Landing Drainage District No. 
5 and Stringtown Drainage and Levee District No. 
4, 11. (LMS) 14-14 
Fort Clinch State Park, Fla. (SAJ) 9-54 
Fort Cobb Reservoir, Okla. (SWT) 29-21 
Fort Fisher and Vicinity, N.C. (SAW) 6-26 
Fort Gibson Lake, Okla. (SWL) (SWT) 28-22, 29-9, 
29-15, 29-18, 29-20 
Fort Kent, Maine (NED) 1-23, 1-42 
Fort Leavenworth, Kan., Bridge Removal (MRK) 
27-15 
Fort Loudon Lock and Dam, Tenn. (ORN) 15-17 
Fort Lupton, Lagoon (Co.) (MRO) 26-23 
Fort Macon State Park, N.C. (SAW) 6-26 
Fort Madison Harbor, Iowa (NCD) 25-7, 25-10 
Fort Myers Beach, Fla. (SAJ) 9-5, 9-27, 9-33, 9-46 
Fort Niagara State Park, N.Y. (NCB) 20-36 
Fort Peck Lake, Mont. (MRO) 26-7, 26-11, 26-14, 
26-18 
Fort Pierce, Fla. (SAJ) 9-27 
Fort Pierce Harbor, Fla. (SAJ) 9-6, 9-33 
Fort Randall Dam-Lake Francis Case, S. D. (MRO) 
26-7, 26-11, 26-15, 26-18 
Fort Scott Lake, Marmaton River, Kan. (MRK) 
27-16, 27-19 
Fort Smith, Arkansas River, Ark. (SWL) 28-17 
Fort Supply Lake, Okla. (SWT) 29-4, 29-12, 29-17 
Fort Toulouse, Ala. (SAM) 10-28, 10-46 
Fort Wayne, Ind. (NCE) 21-30 
Fort Wayne Mechanic St. Dike, St. Marys River, Ind. 
(NCE) 21-27 
Fort Worth Floodway (Clear Fork), Tex. (SWF) 30-22 
Fort Worth Floodway (West Fork), Tex. (SWF) 30-22 
Foster Creek Road, Wash. (NPS) 38-25 
Foster Joseph Sayers Dam, Pa. (NAB) 4-20, 4-28 
Foster Lake, Oreg. (NPP) 37-43 
Fountain Creek, Pueblo, Colo. (SWA) 32-3, 32-10, 
32-12 
Four River Basins, Fla. (SAJ) 9-24, 9-31, 9-42, 9-53 
Fourche Bayou Basin, Little Rock, Ark. (SWL) 28-5, 
28-12 
Fourche Creek, Little Rock, Ark. (SWL) 28-17 
Fourmile Run, Va. (NAB) 4-39, 4-42 
Fourpole Creek, W.Va. (ORH) 17-23 
Fourteen Slough, Stockton, Calif. (SPK) 35-40 
I-23

Fowl River, Ala. (SAM) 10-50 
Fox Point Hurricane Barrier, R.I. (NED) 1-23, 1-42 
Fox River, McHenry Co., ll. (NCC) 22-8 
Fox River, Wis. (NCE) 21-7, 21-32, 21-45, 21-59 
Fox River Locks and Dams, Wis. (NCE) 21-59 
Francis E. Walter Dam, Pa. (NAP) (NAB) 3-12, 3-17, 
3-22, 4-20, 4-22, 4-29, 4-36 
Frankenmuth, Cass River, Mich. (NCE) 21-27 
Frankfort, Black Vermillion River, Kan. (MRK) 
27-16 
Frankfort, Ky. (Benson Creek) (Kentucky River) 
(ORL) 16-20, 16-24 
Frankfort, (N. Frankfort) (Kentucky River), Ky. 
(ORL) 16-19, 16-24, 16-29 
Frankfort Harbor, Mich. (NCE) 21-7, 21-33, 21-45 
Franklin, W. P., Lock and Dam, Fla. (SAJ) 9-49 
Franklin Falls Dam, N.H. (NED) 1-8, 1-30, 1-51 
Frazer-Wolf Point, Mont. (MRO) 26-16 
Frazeysburg, Ohio (ORH) 17-22 
Freeport, Ill. (NCR) 23-14 
Freeport, Pa. (Allegheny River) (ORP) 18-21 
Freeport and Vicinity, Tex. Hurricane-Flood 
Protection (SWG) 31-31 
Freeport Harbor, Tex. (SWG) 31-3, 31-15, 31-20, 
31-32, 31-33, 31-38 
Fremont, Ohio, Sandusky River (NCB) 20-37 
French Broad and Little Pigeon Rivers, Tenn. 
(ORN)15-13 
Frenchboro Harbor, Maine (NED) 1-38 
Freshwater Bayou, La. (LMN) 11-16 
Friday Harbor Marina, Wash. (NPS) 38-24 
Friendly, W. Va. (ORH) 17-22 
Friendsville, Md. (ORP) 18-20, 18-25 
From North Little Rock, Ark. to Gillett, Ark. on north 
bank of Arkansas River (portion below Plum 
Bayou) (MR+T) 42-29 
From North Little Rock to Gillett, Ark. (above Plum 
Bayou) (SWL) 28-17 
Fry Creek, Okla. (SWT) 29-19 
Fullerton, Ky. (ORH) 17-21 
Fulton, Ill. (NCR) 23-13, 23-15 
G 
Galax, Va. (ORH) 17-21, 17-23 
Gale Creek, Oreg., Ill. (NCR) 23-16 
Galena, Ill. (NCR) 23-13, 23-15 
Galena Emergency Bank Stabilization, Alaska (NPA) 
40-6, 40-9, 40-11 
Galisteo Dam, N. Mex. (SWA) 32-5, 32-11, 32-13 
Gallipolis, Ohio (ORH) 17-22 
Gallipolis Locks and Dam, W. Va. (ORD) 19-8 
Galveston Harbor and Channel, Tex. (SWG) 31-4, 
31-15, 31-21, 31-32, 31-33, 31-38 
Gapway Swamp, N.C. and S.C. (SAN) (SAW) 6-27, 
7-15 
Garapan Area, CNMI (POD) 36-15 
Garden City, Tulsa, Okla. (SWT) 29-21 
Gardner, Mass. (NED) 1-23, 1-42, 1-49 
Gardners Creek, N.C. (SAW) 6-27 
Garland City, Ark. (LMN) (LMK) 11-18, 12-18, 
12-20 
Gamett Lake, Pottawatomie Creek, Kan. (MRK) 
27-17, 27-19 
Garrison Dam-Lake Sakakawea, N. Dak. (MRO) 26-8, 
26-11, 26-15, 26-18 
Gasconade River, Mo. (MRK) 27-15 
Gastineau Channel, Alaska (NPA) 40-12 
Gate Creek Lake, Oreg. (NPP) 37-39, 37-41, 37-45 
Gathright Dam and Lake Moomaw, Va. (NAO) 5-9, 
5-14, 5-17 
Gauley River, W. Va. (ORH) 17-20 
Gavins Point Dam-Lewis and Clark Lake, Nebr. and 
S. Dak. (MRO) 26-8, 26-11, 26-15, 26-17, 26-18 
Gaysville Lake, Vt. (NED) 1-44 
Genegantslet Lake, N.Y. (NAB) 4-40 
General Edgar Jadwin Dam and Reservoir, Pa. 
(NAP) 3-13, 3-17, 3-23 
General Joe Wheeler Dam (ORN) 15-17 
Geneva-On-The-Lake, Ohio (NCB) 20-5, 20-18, 
20-28 
Genoa Sewer Facility, Wayne County, N.C. (SAW) 
6-27 
Gentilly, Minn. (NCS) 24-28 
George, Walter F., Lock and Dam, Ala. and Ga. 
(SAM) 10-46 
George W. Andrews Lock and Dam, Ala. and Ga. 
(SAM) 10-25, 10-35, 10-41 
Georges River, Maine (NED) 1-38 
Georgetown Harbor, S.C. (SAN) 7-4, 7-8, 7-11 
Gering Valley, Gering Drain and Tribs., Nebr. (MRO) 
26-20 
Gering Valley, Nebr. (MRO) 26-16 
Gibson Creek, Tenn. (ORN) 15-19 
I-24

INDEX 
Gila River Basin, Ariz. (SPL) 33-5, 33-13, 33-25 
Giles Creek, Elkhorn, Nebr. (MRO) 26-17 
Gill Township Levee, (Wabash River), Ind. (ORL) 
16-19, 16-29 
Gillham Lake, Ark. (SWL) 28-6, 28-12, 28-23 
Gill's Creek, Lancaster, S.C. (SAN) 7-17 
Gilmore Creek, Winona, Minn. (NCS) 24-34 
Girty's Run (Allegheny Co.), Penn. (ORP) 18-26 
Girty's Run, Millvale, Pa. (ORP) 18-20 
GIWW; Apalachicola Bay to St. Marks River, Fla. 
(SAM) 10-48 
Glader Blvd., Minn. (NCS) 24-34 
Glasgow, Mont. (MRO) 26-16, 26-18 
Gleason Creek, Nev. (SPK) 35-36 
Glen Cove Creek, N.Y. (NAN) 2-33, 2-37 
Glen Cove Harbor, N.Y. (NAN) 2-34 
Gloucester Harbor and Annisquam River, Mass. 
(NED) 1-38, 1-46 
Goat Island, Ga. and S.C. (SAS) 8-16 
Golconda, Ill. (ORL) 16-19, 16-24, 16-29 
Gold Creek, Alaska (NPA) 40-13 
Goldsboro, Neuse River, N.C. (SAW) 6-27 
Goleta, Calif., and Vicinity (SPL) 33-9, 33-25 
Goodfood Creek, Chickasaw County, Miss. (SAM) 
10-15, 10-33, 10-44 
Gooding Area, Idaho (NPW) 39-15 
Gooding Area, Littlewood River, Ind. (NPW) 39-12 
Goose Creek, Md. (NAB) 4-37 
Gordons Creek, Hattiesburg, Miss. (SAM) 10-48 
Gordons Landing, Lake Champlain, Vt. (NAN) 2-34 
Goshen Creek, N.J. (NAP) 3-25 
Governor's Run, Md. (NAB) 4-40 
Gowanus Creek Channel, N.Y. (NAN) 2-34 
Grafton, N. Dak. (NCS) 24-28 
Grafton Pumping Station, N.Dak. (NCS) 24-7, 24-22 
Grafton Small Boat Harbor, Ill. (LMS) 4-13 
Grahn, Ky. (ORH) 17-23 
Grand Bayou Pass, La. (LMN) 11-16 
Grand Haven Harbor and Grand River, Mich. (NCE) 
21-8, 21-32, 21-45, 21-57 
Grand Isle and Vicinity, La. (LMN) 11-6, 11-11, 
11-14 
Grand Lake O' the Cherokees, Okla. (SWT) 29-20 
Grand Marais Harbor, Mich. (NCE) 21-8, 21-55, 
21-60 
Grand Marais Harbor, Minn. (NCE) 21-33, 21-46 
Grand Prairie, Ark. (MR+T) 42-54 
Grand Prairie, Tex., Sanitary Landfill (SWF) 30-22 
Grand Prairie, Tex., Streambank Erosion at Meyers 
Road (SWF) 30-5, 30-15, 30-19 
Grand Prairie-Bayou Meto, Ark., (Flood Control and 
Water Supply) (MR+T) 42-16, 42-30 
Grand River, Grandville, Mich. (NCE) 21-57 
Grand River, Union Co., Nebr. H17 Bridge (MRK) 
27-21 
Grand Tower Drainage and Levee Distnct, Ill. (LMS) 
14-14 
Grand Traverse Bay Harbor, Mich. (NCE) 21-9, 
21-33, 21-46 
Grande Ronde Lake, Oreg. (NPW) 39-14 
Grande Ronde Valley, Oreg. (NPW) 39-12, 39-16 
Grandview, Ind. (ORL) 16-21, 16-25 
Grandview Bay Harbor, N.Y. (NCB) 20-40 
Granite Falls, Minn. (NCS) 24-34 
Grant Parish, below Colfax, La. (LMN) (LMK) 11-18, 
12-19, 12-20 
Granville, Pa. (ORP) 18-20, 18-25 
Grapevine Lake, Tex. (SWF) 30-6, 30-16, 30-19 
Grasse River (Massena), N.Y. (NCB) 20-35 
Grassy Branch, Millsap, Tex. (SWF) 30-23 
Grassy Creek, Jackson County, Ind. (Muscatatuck 
River) (ORL) 16-19, 16-30 
Graves Creek, Idaho (NPW) 39-15 
Grays Creek Canal, Shelby Co., Tenn. (LMM) 13-5 
Grays Harbor and Chehalis River, Wash. (NPS) 38-3, 
38-12, 38-14, 38-19 
Grays Reef, Mich. (NCE) 21-60 
Grays Reef Passage, Mich. (NCE) 21-55 
Grays River, Wash. (NPP) 37-37 
Grayson Lake, Ky. (ORH) 17-5, 17-13, 17-18 
Grayville, Ill. (ORL) 16-19 
Great Bend, Kan. (SWT) 29-4, 29-12, 29-17 
Great Chazy River, N.Y. (NAN) 2-34, 2-39 
Great Coharie Creek, N.C. (SAW) 6-31 
Great Egg Harbor Inlet and Peck Beach, N J. (NAP) 
3-26 
Great Falls, Mont. (MRO) 26-3, 26-9, 26-12 
Great Kills Harbor, N.Y. (NAN) 2-34 
Great Lakes Information Management (NCE) 21-29 
Great Lakes to Hudson River Waterway, N.Y. (NAN) 
2-34 
Great Machipongo Inlet, Va. (NAO) 5-21 
Great Machipongo River, Va. (NAO) 5-21 
Great Miami River, Ind. (ORL) 16-27, 16-30, 16-31 
I-25

Great Pee Dee River, S.C. (SAN) 7-14 
Great Salt Plains Lake, Okla. (SWT) 29-5, 29-12, 
29-17 
Great Salt Pond, RI. (NED) 1-38, 1-44 
Great Sodus Bay Harbor, N.Y. (NCB) 20-6, 20-17, 
20-28, 20-40 
Great South Bay, N.Y. (NAN) 2-34 
Green and Barren Rivers, Ky. (ORL) 16-2, 16-13, 
16-17, 16-23 
Green Bay Harbor, Wis. (NCE) 21-9, 21-33, 21-46 
Green Bay Levee and Drainage District No. 2, Iowa 
(NCR) 23-13, 23-15 
Green Brook, Green Brook, N.J. (NAN) 2-39 
Green County, Route 88, Penn. (ORP) 18-26 
Green Harbor, Mass. (NED) 1-4, 1-25, 1-34, 1-46, 
1-53 
Green Island Levee and Drainage District, Iowa 
(NCR) 23-14 
Green Peter-Foster Lakes, Oreg. (NPP) 37-18, 
37-27, 37-35, 37-43, 37-45 
Green River, Ky. (ORL) 16-27 
Green River, Wash. (NPS) 38-25 
Green River Lake, Ky. (ORL) 16-7, 16-14, 16-30 
Green Valley Creek, Solano Co., Calif. (SPK) 35-34 
Greene, N.Y. (NAB) 4-39, 4-42 
Greenfield Bayou Levee, Ind. (Wabash River) (ORL) 
16-20, 16-24 
Greenport Harbor, N.Y. (NAN) 2-34 
Greens Creek, Petal, Miss. (SAW) 10-49 
Greenup, Ky. (ORH) 17-21 
Greenup Locks and Dam, Ky. (ORD) 19-6, 19-8 
Greenvale Creek, Va. (NAO) 5-19, 5-21 
Greenville, Tex. (SWF) 30-22 
Greenville Harbor, Miss. (MR+T) 42-30, 42-31 
Greenwich Bay, R.I. (NED) 1-38 
Greenwich Harbor, Conn. (NED) 1-38 
Greenwich Point Beach, Conn. (NED) 1-44 
Greers Ferry Lakes, Ark. (SWL) 28-9, 28-13, 28-24 
Greggs Creek, Glasgow, Mo., Sewage �Lift Station and 
Sewerline (MRK) 27-21 
Gregory Drainage Distnct, Mo. (NCR) 23-13, 23-15 
Greilickville Harbor, Mich. (Formerly Traverse City 
Harbor) (NCE) 21-55, 21-60 
Greybull, Wyo. (MRO) 26-16, 26-19 
Griffithsville-Yawkey, W.Va. (ORH) 17-23 
Grove Lake, Soldier Creek, Kan. (MRK) 27-17 
Guadalupe River, Calif. (SPK) 35-23, 35-30 
Guadalupe River (Remove Log Jams), Tex. (SWG) 
31-31 
Guayanes Harbor, P.R. (SAJ) 9-47 
Guilford Harbor, Conn. (NED) 1-38, 1-53 
Guilford Point Beach (Jacobs Beach), Guilford, 
Conn. (NED) 1-41 
Gulf Beach, Milford, Conn. (NED) 1-41 
Gulf Breeze, Fla. (SAM) 10-49 
Gulf Intracoastal Waterway between Apalachee Bay, 
Fla. and Mexican Border (SAM) 10-9, 10-31, 
10-32, 10-40 
Gulf Intracoastal Waterway between Apalachee Bay, 
Fla., and Mexican Border (Galveston, Tex., 
District) (SWG) 31-5, 31-15, 31-22, 31-32, 31-36, 
31-38 
Gulf Intracoastal Waterway between Apalachee Bay, 
Fla., and Mexican Border (New Orleans Dist.) 
(LMN) 11-16 
Gulf Intracostal Waterway, Coloosahat-Chee River to 
Anclote River, Fla. (SAJ) 9-27 
Gulf Intracoastal Waterway St. Marks to Tampa Bay, 
Fla. (SAJ) 9-47 
Gulf Street, Milford, Conn. (NED) 1-16, 1-24, 1-29, 
1-36 
Gulfport Harbor, Miss. (SAM) 10-9, 10-27, 10-32, 
10-40 
Gull Lake Reservoir, Minn. (NCS) 24-31 
Guntersville Lock, Ala. (ORN) 15-17 
Guttenberg, Iowa (NCS) 24-28 
Guyandotte River, W. Va. (ORH) 17-20 
Gypsum, Gypsum Creek, Kan. (MRK) 27-16 
H 
Hackensack River. N. Milford, N.J. (NAN) 2-39 
Hackleman Corners Lake, Cedar Creek, Mo. (MRK) 
27-17 
Haikey Creek, Okla. (SWT) 29-21 
Haines Harbor, Alaska (NPA) 40-12, 40-15 
Haistead, Kan. (SWT) 29-12 
Haleiwa Beach, Oahu, Hawaii (POD) 36-11 
Haleiwa Small Boat Harbor, Oahu, Hawaii (POD) 
36-10 
Hall Meadow Brook Dam, Conn. (NED) 1-23, 1-42, 
1-50 
Halstead, Kan. (SWT) 29-5, 29-17 
I-26

INDEX 
Hamburg L-575, Nishnabotna River, Iowa (MRO) 
26-20 
Hamlin Beach Harbor, N.Y. (NCB) 20-35 
Hamlin Beach State Park, N.Y. (NCB) 20-36 
Hammersley Inlet, Wash. (NPS) 38-24, 38-28 
Hammonassett Beach, Madison, Conn. (NED) 1-41 
Hammond Bay Harbor, Mich. (NCE) 21-9, 21-33, 
21-43 
Hammond Small Boat Basin, Oreg. (NPP) 37-37 
Hammondsport, Oswego River Basin, N.Y. (NCB) 
20-40 
Hampton Beach, Hampton, N.H. (NED) 1-41 
Hampton Creek, Va. (NAO) 5-19, 5-21 
Hampton Harbor, N.H. (NED) 1-5, 1-25, 1-34 
Hampton Institute, Va. (NAO) 5-20 
Hampton Roads and Harbors of Norfolk and 
Newport News, Va.- Collection and Removal of 
Drift (NAO) 5-4, 5-11, 5-15 
Hampton Roads Harbor, Supervision of (NAO) 5-13 
Hana Small Boat Harbor, Maui, Hawaii (POD) 36-13 
Hanalei Small Boat Harbor, Hawaii (POD) 36-12, 
36-13 
Hanapepe Bay, Kauai, Hawaii (POD) 36-13 
Hanapepe River, Kauai, Hawaii (POD) 36-12 
Hancock Brook Lake, Conn. (NED) 1-17, 1-30, 1-50 
Hanging Rock, Ohio (ORH) 17-22 
Hannibal, Mo. (NCR) 23-4, 23-7, 23-11 
Hannibal Harbor, Mo. (NCD) 25-8, 25-10 
Hannibal Locks and Dams, W. Va. (ORD) 19-6, 19-7 
Hannibal SBH, Mo. (NCR) 23-12 
Hanover, Hennepin Co., Minn. (NCS) 24-8, 24-23, 
24-33 
Hansen Dam, L.A. Co., D.D., Calif. (SPL) 33-25 
Hanson, Howard A., Dam, Wash. (NAS) 38-7, 38-16, 
38-21 
Harbor Beach Harbor, Mich. (NCE) 21-10, 21-34, 
21-46 
Harbor of Refuge, Block Island, R.I. (NED) 1-38, 
1-44 
Harbor of Refuge, Delaware Bay, Del. (NAP) 3-24 
Harbor of Refuge, N.C. (SAW) 6-28 
Harbor Office at Morro Bay, Calif. (SPL) 33-23 
Harbor Springs, Mich. (NCE) 21-25 
Harden, Cecil M., Lake, Ind. (ORL) 16-6, 16-14 
Harkers Island Harbor, N.C. (SAW) 6-29 
Harlan County Lake, Republican River, Nebr. (MRK) 
27-3, 27-9, 27-12, 27-19 
Harlem River, N.Y. (NAN) 2-34 
Harpers Ferry, W. Va. (NAB) 4-40 
Harpswell, Maine (NED) 1-23 
Harraseeket River, Maine (NED) 1-38 
Harriet Island Harbor, St. Paul, Minn. (NCD) 25-7 
Harris Fork Creek, Tenn. and Ky. (MR+T) 42-30 
Harrisburg, Ill. (ORL) 16-19, 16-24, 16-29 
Harrison County, Miss. (SAM) 10-47 
Harrisonville Levee and Drainage District, Ill. (LMS) 
14-14 
Harrisville Harbor, Mich. (NCE) 21-10, 21-34, 21-47 
Harrodsburg, Ky. (Town Creek) (ORL) 16-30 
Harry S. Truman Dam and Reservoir, Osage River, 
Mo. (MRK) 27-8, 27-11, 27-15, 27-16, 27-19 
Harsha, William H., Lake, Ohio (ORL) 16-11, 16-16, 
Hartford, Conn. (NED) 1-42, 1-49 
Hartford, Vt. (NED) 1-42, 1-49 
Hartford, W. Va. (ORH) 17-22 
Hartland, Maine (NED) 1-23 
Hartwell Drainage and Levee District, Ill. (LMS) 
14-11 
Hartwell Lake, Ga. and S.C. (SAS) 8-8, 8-12, 8-15, 
8-16 
Harvey Canal, Bayou Barataria Levee, La. (LMN) 
11-18 
Hastings Harbor, Minn. (NCD) 25-7, 25-10 
Hatchie River, Alcom Co., Miss. (LMM) 13-5 
Haverhill, Mass. (NED) 1-23 
Havre, Mont. (MRO) 26-16, 26-18 
Hawarden, Dry Creek, Iowa (MRO) 26-20 
Hawesville, Ky. (ORL) 16-19, 16-24, 16-29 
Hay Creek, Birdsboro, Pa. (NAP) 3-26 
Hay (West Harbor), Fisher's Island, N.Y. (NED) 1-38 
Hayden Island, Oreg. (NPP) 37-39 
Hays, Big Creek, Kan. (MRK) 27-17 
Hays, Lincoln Co., Kan. (MRK) 27-21 
Haysi, Va. (ORH) 17-21 
Hayward Creek, Mass. (NED) 1-23, 1-42 
Hazard, Ky. (ORL) 16-19 
Head of Passes, La.-Cairo, Ill. (MR+T) 42-11 
Heeia-Kea Small Boat Harbor, Hawaii (POD) 36-10 
Heise-Roberts Area, Snake River, Idaho (NPW) 
39-12, 39-14, 39-15 
Heise-Roberts Extension, Idaho (NPW) 39-16 
Helena, Ark. and Vicinity (MR+T) 42-30 
Helena Harbor, Ark. (LMN) 13-4 
Helena Harbor (MR+T) 42-30 
I-27

Hellens Creek, Md. (NAB) 4-40 
Helm Lake, Ill. (ORL) 16-22, 16-28 
Hemingway Creek, S.C. (SAN) 7-16 
Hempstead County Levee District No. 1, Ark. (LMN) 
(LMK) 11-18, 12-19, 12-20 
Hempstead Harbor, N.Y. (NAN) 2-6, 2-23, 2-28 
Henderson, W. Va. (ORH) 17-22 
Henderson Bay, Wash. (NPS) 38-25 
Henderson County Drainage Districts Nos. 1, 2 and 
3, Il. (NCR) 23-13, 23-15 
Henderson River, Ill. (NCR) 23-14 
Hendrick's Harbor, Maine (NED) 1-38 
Hennepin Drainage and Levee District, Il. (NCR) 
23-13, 23-15 
Henry, Robert F., Lock and Dam, Ala. (SAM) 10-35, 
10-45 
Herbert Hoover Dike Revetment (SAJ) 9-52 
Herefort Inlet (NAP) 3-26 
Hergot Drainage and Levee District (NCR) 23-15 
Herkimer, N.Y. (NAN) 2-36 
Herreid, Spring Creek, S. Dak. (MRO) 26-16, 26-19 
Herring Bay and Rockhold Creek, Md. (NAB) 4-6, 
4-24, 4-32 
Herring Creek, Md. (NAB) 4-6, 4-24, 4-32 
Herring River, Scituate, Mass. (NED) 1-24 
Heyburn Lake and Polecat Creek, Okla. (SWT) 29-5, 
29-13, 29-17 
Hickman, Ky. (MR+T) 42-12 
Hickman Harbor, Ky. (LMM) 13-4 
Hidden Dam-Hensley Lake, Fresno River, Calif. 
(SPK) 35-8, 35-25 
Higginsport, Ohio (ORH) 17-22 
Highland Bayou, Tex. (SWG) 31-31 
Highway 12, Colo. (SWA) 32-14 
Highway 39 Bridge, Gainesville, Ala. (SAM) 10-15, 
10-33, 10-44 
Hills Creek Lake, Oreg. (NPP) 37-19, 37-27, 37-43, 
37-45 
Hillsborough Bay, Fla. (SAJ) 9-54 
Hillsborough River, Fla. (SAJ) 9-39 
Hillsdale Lake, Big Bull Creek, Kan. (MRK) 27-3, 
27-9, 27-12, 27-19 
Hilo Harbor, Hawaii (POD) 36-10 
Hingham Harbor, Mass. (NED) 1-38 
Hintonville Rd. Bridge, Perry Co., Miss. (SAM) 10-49 
Hiwassee River, Tenn. (ORN) 15-14 
Hockingport, Ohio (ORH) 17-22 
Hodges Dam, San Dieguito River Basin, Calif. (SPL) 
33-27 
Hodges Village Dam, Mass. (NED) 1-21, 1-23, 1-31, 
1-52 
Hoh River, Wash. (NPS) 38-25 
Hoko River, Wash. (NPS) 38-25 
Holbrook Levee, Little Colorado River, Colorado 
River Basin, Ariz. (SPL) 33-25 
Holes Creek, West Carollton, Ohio (Great Miami 
River) (ORL) 16-19 
Holland Harbor, Mich. (NCE) 21-10, 21-34, 21-47 
Holley Lake, Oreg. (NPP) 37-39, 37-41, 37-45 
Holly, Colo. (SWA) 32-14 
Hollywood-Ardmore Beach along Lake Michigan, 
Ill. (NCC) 22-17 
Holmes Bay, Whiting, Maine (NED) 1-42 
Holmes Creek, Fla. (SAM) 10-47 
Holston River, Tenn. (ORN) 15-13 
Holyoke, Mass. (NED) 1-23, 1-42, 1-49 
Homeplace, La. (MR+T) 42-11 
Homer Harbor, Alaska (NPA) 40-2, 40-8, 40-10 
Hominy Swamp, N.C. (SAW) 6-28 
Homme Lake and Dam, N. Dak. (NCS) 24-8, 24-23 
Homochitto River, Miss. (LMK) 12-15, 12-20 
Homosassa River, Fla. (SAJ) 9-47 
Honey Creek Levee, Ind. (ORL) 16-21, 16-25 
Honey Hill Lake, N.H. (NED) 1-44 
Honga River and Tar Bay (Barren Island Gaps), Md. 
(NAB) 4-6, 4-24, 4-32 
Honokohau Small Boat Harbor, Hawaii (POD) 36-10 
Honolulu Harbor, Oahu, Hawaii (POD) 36-10 
Hood Canal, Wash. (NPS) 38-25 
Hoonah Harbor, Alaska (NPA) 40-12, 40-15 
Hooper, Elkhorn River, Nebr. (MRO) 26-20 
Hooper, Nebr. (MRO) 26-16 
Hooper Bay, Ark. (NPA) 40-13 
Hoosic Falls, Hoosic River Basin N.Y. (NAN) 2-36 
Hop Brook Lake, Conn. (NED) 1-17, 1-30, 1-50 
Hopkins Creek, S.C. (SAN) 7-16 
Hopkinton-Everett Lakes, N.H. (NED) 1-19, 1-30, 
1-51 
Hoquiam River, Wash. (NPS) 38-24, 38-25 
Hords Creek Lake, Tex. (SWF) 30-6, 30-16, 30-19 
Horn Harbor, Va. (NAO) 5-19 
Horn Lake Creek and Tributaries, (MR+T) 42-30 
Hornell, N.Y. (NAB) 4-17, 4-28 
Horseshoe Cove, Fla. (SAJ) 9-46, 9-47 
1-28

INDEX 
Hoskins Creek, Va. (NAO) 5-19, 5-21 
Hot Springs, Fall River Channel, S. Dak. (MRO) 
26-19 
Houlka Creek, Miss. (SAM) 10-48 
Houma Navigation Canal, La. (LMN) 11-16 
Housatonic River, Conn. (NED) 1-38, 1-44 
Housatonic River, Northampton, Mass. (NED) 1-47 
Housatonic River, Pittsfield, Mass. (NED) 1-42 
Housatonic River, Salisbury, Conn. (NED) 1-42 
Housatonic River, Sheffield, Mass. (NED) 1-24, 1-42 
Hausatonic River, Shelton, Conn. (NED) 1-47 
Housatonic River Basin, Conn. and Mass. (NED) 1-7, 
1-50 
Houston, Minn. (NCS) 24-8, 24-23 
Houston School Road Bridge, Itawamba County, 
Miss. (SAM) 10-15, 10-33, 10-44 
Houston Ship Channel, Tex. (SWG) 31-6, 31-15, 
31-24, 31-32, 31-34, 31-38 
Howard A. Hanson Dam, Wash. (NAS) 38-7, 38-16, 
38-21 
Howards Mill Lake, N.C. (SAW) 6-27 
Hudson Harbor, Wis. (NCS) 24-30 
Hudson River, Fla. (SAJ) 9-47 
Hudson River, N.Y. (NAN) 2-6, 2-23, 2-28, 2-32, 
2-33, 2-37 
Hudson River Channel, N.Y. (NAN) 2-33, 2-34 
Hugo Lake, Okla. (SWT) 29-5, 29-12, 29-17 
Hulah Lake, Okla. (SWT) 29-5, 29-12, 29-17 
Hull, Cordell, Lock and Dam, Tenn. (ORN) 15-14 
Humboldt, Tenn. (LMM) 13-1, 13-3 
Humboldt Bay, Calif. (SPN) 34-12 
Humboldt Harbor, Alaska (NPA) 40-12, 40-14 
Humboldt Harbor and Bay, Calif. (SPN) 34-6 
Humboldt River and Tributaries, Nev. (SPK) 35-36 
Hunt Drainage District and Lima Lake Drainage 
District, Ill. (NCR) 23-13, 23-15 
Hunting Island Beach, S.C. (SAN) 7-15 
Huntingdon, Tenn. (LMM) 13-5 
Huntington, Mass. (NED) 1-23, 1-42, 1-49 
Huntington, W. Va. (ORH) 17-21, 17-23 
Huntington Harbor, N.Y. (NAN) 2-34, 2-37 
Huntington Lake, Ind. (ORL) 16-7, 16-14 
Huot, Minn. (NCS) 24-33 
Huron Harbor, Ohio (NCB) 20-6, 20-17, 20-28 
Hurricane Barrier Operations, New England Division 
(NED) 1-23 
Hurricane Creek, Ashdown, Ark. (SWL) 28-25 
Hutchins, Ky. (ORH) 17-23 
Hutchinson Levee and Channel, Kan. (SWT) 29-19, 
29-20 
Hyannis Harbor, Mass. (NED) 1-38 
Hyde County Dike, N.C. (SAW) 6-28 
Hydraulics and Hydrology of the Great Lakes (NCE) 
21-29 
Hydrologic Engineenng Center (HEC) 47-1 
Hydrologic Studies (SAN) (LMK) (SWT) 7-17, 12-22, 
29-22 
I 
Iao Stream, Maui, Hawaii (POD) 36-12, 36-15 
Ice Harbor at Marcus Hook, Pa. (NAP) 3-25 
Ice Harbor at New Castle, Del. (NAP) 3-25 
Ice Harbor Lock and Dam-Lake Sacajawea, Wash. 
(NPW) 39-4, 39-9, 39-13, 39-18, 39-22 
Ida Grove, Iowa (MRO) 26-16 
Ida Grove, Maple River-Odebott Creek (MRO) 26-20 
Iliuliuk Harbor, Alaska (NPA) 40-12 
Illinois and Michigan Canal, Ill. (NCR) 23-16 
Illinois and Mississippi Canal, Ill. (NCR) 23-2, 23-7 
Illinois River, Ill. (MR+T) 42-19 
Illinois River, Liverpool, Ill. (NCR) 23-17 
Illinois Waterway, Ill. and Ind. (NCR) 23-2, 23-7, 
23-9, 23-14 
Illinois Waterway, Ill. and Ind., Additional Features 
Entering into Cost (NCR) 23-19, 23-20 
Illinois Waterway, Ill. and Ind., Duplicate Locks 
(NCR) 23-14 
Illinois Waterway. Ill.and Ind., Lock and Dam 
Construction, Foundations, Cost (NCR) 23-18 
Illinois Waterway. Ill. (St. Louis District) (LMS) 14-2 
Illinois Waterway Navigation Project (Perkin, Ill.) 
(NCR) 23-14 
Illinois Waterway: Existing Locks and Dams (NCR) 
23-18, 23-20 
Imperial Beach, Calif. (SPL) 33-24 
Indian Camp Creek and Tribs., Noxabee, Miss. (SAM) 
10-49 
Indian Creek, Corydon, Ind. (ORL) 16-19, 16-30 
Indian Creek Area, Illinois River, Ill. (LMS) 14-14 
Indian Creek Lake, Emerson, Iowa (MRO) 26-17 
Indian Grave Drainage District, Ill. (NCR) 23-13, 
23-15 
Indian Island, Maine (NED) 1-23 
I-29

Indian Lake, Blue River, Kan. (MRK) 27-17 
Indian River County, Fla. (SAJ) 9-19, 9-30, 9-41 
Indian River Inlet and Bay, Del. (NAP) 3-6, 3-16, 
3-20 
Indiana Dunes National Lakeshore Bank Protection, 
Beverly Shores, Ind. (NCC) 22-5, 22-14 
Indiana Dunes National Lakeshore Emergency Stone 
Repairs, Beverly Shores, Ind. (NCC) 22-11 
Indiana Harbor, Ind. (NCC) 22-4, 22-10, 22-13, 22-16 
Indiana Shoreline, Ind. (NCC) 22-5, 22-11, 22-14 
Indianapolis, Ind. (ORL) 16-29 
Indianapolis, Ind. (Fall Creek Section) (White River) 
(ORL) 16-19 
Indianapolis, Ind. (Warfleigh Section) (White River) 
(ORL) 16-19 
Indianola, Nebr. (MRK) 27-16 
Indianola, Republican River, Nebr. (MRK) 27-19 
Industrial Area, Waterbury, Conn. (NED) 1-47 
Industrial Levee (Ensley Bottoms) (MR+T) 42-12 
Industry, Pa. (ORP) 18-21 
Inez, Ky. (ORH) 17-23 
Inland Route, Mich. (NCE) 21-11, 21-34, 21-47 
Inland Waterway from Chincoteague Bay, Va., to 
Delaware Bay, Del. (NAP) 3-24 
Inland Waterway from Delaware River to Chesapeake 
Bay, Del. and Md. (NAP) 3-6, 3-16, 3-20 
Inland Waterway from Franklin to Mermentau River, 
La. (LMN) 11-16 
Inland Waterway, Rehoboth Bay to Delaware Bay, 
Del. (NAP) 3-24 
Inspection of Completed Beach Erosion Projects 
(NED) 1-11, 1-23 
Inspection of Completed Flood Control Projects 
Alaska District (NPA) 40-6 
Albuquerque, N. Mex., District (SWA) 32-8 
Baltimore, Md., District (NAB) 4-21 
Buffalo, N.Y., District (NCB) 20-15 
Charleston, S.C., District (SAN) 7-7 
Detroit, Mich., District (NCE) 21-27 
Fort Worth, Tex., District (SWF) 30-11, 30-22 
Galveston, Tex., District (SWG) 31-13 
Huntington, W. Va., District (ORH) 17-10, 17-19 
Jacksonville, Fla., District (SAJ) 9-25 
Kansas City, Mo., District (MRK) 27-7, 27-11, 
27-19 
Little Rock, Ark., District (SWL) 28-6 
Los Angeles, Calif., District (SPL) 33-8, 33-28 
Louisville, Ky., District (ORL) 16-12, 16-29, 16-30 
Memphis, Tenn., District (LMM) 13-2 
Mobile, Ala., District (SAM) 10-20 
Nashville, Tenn., District (ORN) 15-6, 15-9 
New Orleans District (LMN) 11-10 
New York District (NAN) 2-21 
Omaha, Neb., District (MRO) 26-6 
Pacific Ocean Division (POD) 36-5, 36-15 
Philadelphia, Penn., District (NAP) 3-13 
Pittsburgh, Penn., District (ORP) 18-9, 18-25 
Portland, Oreg., District (NPP) 37-13 
Rock Island, ill., District (NCR) 23-15, 23-16 
Sacramento, Calif., District (SPK) 35-20 
San Francisco, Calif., District (SPN) 34-4 
Savannah, Ga., District (SAS) 8-11 
Seattle, Wash., District (NPS) 38-8 
St. Louis, Mo., District (LMS) 14-6 
St. Paul, Minn., District (NCS) 24-20, 24-33 
Tulsa, Okla., District (SWT) 29-8, 29-20 
Vicksburg, Miss., District (LMK) 12-7 
Walla Walla, Wash., District (NPW) 39-2, 39-17 
Wilmington, N.C., District (SAW) 6-14 
Inspection of Completed Local Protection Projects 
(MRO) (NPP) 26-11, 26-18, 26-19, 37-13 
Inspection of Completed PL-99 Work, (NPW) (NPS) 
38-8, 39-2 
Inspection of Completed Projects (NAB) 4-42 
Inspection of Non-Federal Levees (NAP) (MRO) 
(MRK) 3-13, 26-11, 27-7, 27-11 
Institute for Water Resources 47-2 
Intercounty D. D., Little Sioux River, Ia. (MRO) 26-20 
International Boundary Waters Boards, 49-1 
Intemational Champlain-Richelieu Board 49-1 
International Great Lakes Diversions and 
Consumptive Uses Study Board (NCE) 21-29, 49-1 
International Great Lakes Technical Information 
Network Board (NCE) 21-29, 49-1 
International Joint Commission Board of Control 49-1 
International Kootenay Lake Board of Control 49-1 
International Lake Champlain Board of Control 49-1 
International Lake Memphremagog Board 49-2 
Intemational Lake of the Woods Control Board 49-1 
International Lake Superior Board of Control (NCE) 
21-28, 49-1 
International Niagara Board of Control and International 
Niagara Working Committee (NCE) 21-29, 
49-1 
International Niagara Committee 49-2 
International Osoyoos Lake Board of Control 49-1 
I-30

INDEX 
International Rainy Lake Board of Control 49-1 
International Skagit River Board of Control 49-1 
International Souris River Board of Control 49-1 
International Souris-Red Rivers Engineering Board 
49-1 
International St. Croix River Board of Control 49-1 
International St. Lawrence River Board of Control 
(NCE) 21-29,49-1 
Interstate Bridge, Portland, Oreg. (NPP) 37-37 
Interstate Highway Bridge (Barge Channel), Oreg. 
(NPP) 37-37 
Interstate 59 Bridges, Fosters, Ala. (SAM) 10-48 
Intracoastal Waterway, Caloosahatchee River to 
Anclote River, Fla. (SAJ) 9-6, 9-27, 9-33 
Intracoastal Waterway, Jacksonville to Miami, Fla. 
(SAJ) 9-7, 9-27, 9-33 
Intracoastal Waterway, Miami to Key West, Fla. 
(SAJ) 9-47 
Intracoastal Waterway, Mississippi River to Bayou 
Teche, La. (LMN) 11-16 
Investigations of Projects Under the Federal Power 
Act 50-1 
Iola Levee, Kans. (SWT) 29-19, 29-20 
Iowa Falls, River Road, Iowa (NCR) 23-17 
Iowa River-Flint Creek Levee District No. 16, Iowa 
(NCR) 23-13, 23-16 
Iowa River, Wapello, Iowa (NCR) 23-17 
Ipswich Harbor, Mass. (NED) 1-38 
Ipswich River, Mass. (NED) 1-44 
Iron'dale, Ala. (SAM) 10-49 
Irondequoit Bay, N.Y. (NCB) 20-6, 20-18, 20-29 
Ironton, Ohio (ORH) 17-21, 17-23 
Iroquois River, Sugar Creek, Watscka, Ill. (NCR) 
23-17 
Irving Floodway, Tex. (SWF) 30-22 
Irving Township at Nichols Rd., Jackson Co., Wis. 
(NCS) 24-28, 24-33 
Irving Township, Jackson Co., Wis. (NCS) 24-28, 
24-33 
Irvington Harbor, N.Y. (NAN) 2-37 
Isabella Lake, Kemrn River, Calif. (SPK) 35-9, 35-25 
Island Avenue, Quincy, Mass. (NED) 1-42 
Island Creek, Md. (NAB) 4-37 
Island Creek, St. Georges Island, Md. (NAB) 4-7, 
4-25, 4-32 
Island End River, Chelsea, Mass. (NED) 1-38 
Island Levee, Ind. (Wabash River) (ORL) 16-20, 
16-24 
Isle Au Haut Thoroughfare, Maine (NED) 1-38 
Isle of Shoals Harbor, Maine and N.H. (NED) 1-38 
Islesboro (The Narrows), Maine (NED) 1-23, 1-42 
Israel R., Lancaster, N.H. (NED) 1-49 
Issaquah Creek, Wash. (NPS) 38-29 
Ithaca, N.Y., Cascadilla Creek (NCB) 20-40 
Ithaca, N.Y., Cayuga Inlet (NCB) 20-37 
Ithaca, N.Y., Fall Creek (NCB) 20-40 
J 
J.C. Park, New Albany, Ind. (ORL) 16-31 
J.Percy Priest Dam and Reservoir, Ohio River 
Basin, Tenn. (ORN) 15-7, 15-9, 15-18 
J. Strom Thurmond Dam and Reservoir (formerly 
Clarks Hill Lake), Ga. and S.C. (SAS) 8-7, 8-12, 
8-14, 8-16 
Jackson, Ky. (Kentucky River) (ORL) 16-19, 16-24, 
16-30 
Jackson County Levee District 2, White River, Ark. 
(SWL) 28-17 
Jackson Creek, Va. (NAO) 5-19 
Jackson Hole, Snake River, Wyo. (NPW) 39-3, 39-9, 
39-12, 39-14, 39-15 
Jackson Port, Jackson, Ala. (SAM) 10-6, 10-31, 10-39 
Jacksonburg, Fishing Creek, W.Va. (ORH) 17-23 
Jacksonville Harbor, Fla. (SAJ) 9-7, 9-27, 9-34 
Jacksonville Harbor (Mill Cove), Fla. (SAJ) 9-8, 9-27, 
9-34 
Jacksonville Harbor, Fla., St. Johns River, Fla. 
opposite the City of Jacksonville (SAJ) 9-34 
Jadwin, General Edgar, Dam and Reservoir, Pa. 
(NAP) 3-13, 3-17 
Jamaica Bay, N.Y. (NAN) 2-7, 2-23, 2-28, 2-33, 2-34 
James River, Va. (NAO) 5-4, 5-11, 5-15, 5-21 
James River, Yankton, S. Dak. (MRO) 26-23 
James W. Trimble Lock and Dam (No. 13), Ark. 
(SWL) 28-3, 28-20 
Jamestown Reservoir, N. Dak. (MRO) 26-16 
Janesville and Indian Ford Damrns, Wis. (NCR) 23-14 
Jarvis Creek, Va. (NAO) 5-19 
Jaws-Lake Fousse Pointe (MR+T) 42-14 
Jefferson River, Bank Protection, near Waterlo, 
Mont. (MRO) 26-19 
Jefferson River, Willow Creek Bridge, near Three 
Forks, Mont. (MRO) 26-19 
Jeffersonville-Clarksville, Ind. (ORL) 16-19, 16-24, 
16-29 
1-31

Jemez Canyon Dam, N. Mex. (SWA) 32-5, 32-11, 
32-13 
Jenkins, Tom, Dam, Ohio (ORH) 17-19 
Jenkins, Tom, Reservoir, Ohio (ORH) 17-10, 17-14 
Jenks LLP, Okla. (SWT) 29-19, 29-20 
Jennings Beach, Fairfield, Conn. (NED) 1-41 
Jennings Randolph Lake, Md. and W. Va. (NAB) 
4-13, 4-27, 4-35 
Jeremy Creek, S.C. (SAN) 7-4, 7-8, 7-11 
Jim Woodruff Lock and Dam, Ga. and Fla. (SAM) 
10-25, 10-35, 10-46 
Joe Creek Channel Improvement, Okla. (SWT) 29-19, 
29-20, 29-21 
Joe Pool Lake (Lakeville Lake), Tex. (SWF) 30-6, 
30-16, 30-19 
John Day Lock and Dam-Lake Umatilla, Oreg. and 
Wash. (NPP) 37-19, 37-28, 37-35, 37-46 
John Day River, Oreg. (NPP) 37-38, 37-41 
John Drainage District, Oreg. (NPP) 37-41, 37-44 
John H. Kerr Dam and Reservoir, Va. and N.C. 
(SAW) 6-5, 6-16, 6-20 
John Martin Reservoir, Colo. (SWA) 32-3, 32-10 
John Redmond Dam and Reservoir, Kan. (SWT) 
29-5, 29-13, 29-17 
John W. Flannagan Dam and Reservoir, Ohio River 
Basin, Va. (ORH) 17-5, 17-13, 17-18 
Johns Pass, Fla. (SAJ) 9-9, 9-27, 9-34, 9-46 
Johnson Bay, Lubec, Maine (NED) 1-42 
Johnson Bayou, La. (SWG) 31-30 
Johnson Creek, Oreg. (NPP) 37-39 
Johnson Creek, Arlington, Tex. (SWF) 30-23 
Johnson Creek, Grand Prairie, Tex. (SWF) 30-23 
Johnsonburg, Pa. (ORP) 18-20, 18-25 
Johnsonburg, Penn. (Allegheny River Basin) (ORP) 
18-24 
Johnstown, Penn. (ORP) 18-4, 18-11, 18-16 
Johnstown, Penn. (Allegheny River Basin) (ORP) 
18-24 
Jones Bluff Lock and Dam, Ala. (SAM) 10-45 
Jones Inlet, N.Y. (NAN) 2-33, 2-34 
Jonesport Harbor, Maine (NED) 1-5, 1-26, 1-34 
Jonesville, La. (LMK) (MR+T) 12-14, 42-15, 42-29 
Jordan, B. Everett, Dam and Lake, N.C. (SAW) 16-20 
Josias River, Maine (NED) 1-39 
Joyce Creek, Camden County, N.C. (SAW) 6-27 
Julian, Rock Creek, Nebr. (MRO) 26-20 
Jump, The, New Orleans, La. (MR+T) 42-11 
Juneau (Aurora Harbor) (NPA) 40-14 
Juneau Harbor, Alaska (NPA) 40-12 
K 
Kaaawa Beach, Oahu, Hawaii (POD) 36-11 
Kahawainui Stream, Oahu, Hawaii (POD) 36-4, 36-7 
Kahoma Stream, Maui, Hawaii (POD) 36-5, 36-7, 
36-9 
Kahului Beach Road, Mauri, Hawaii (POD) 36-10 
Kahului Harbor, Mauri, Oahu, Hawaii (POD) 36-10, 
36-14 
Kailua Small Boat Harbor, Oahu, Hawaii (POD) 
36-10 
Kaimu Black Sand Beach, Hawaii, Hawaii (POD) 
36-13 
Kake Harbor, Alaska (NPA) 40-2, 40-8, 40-10 
Kalama River (South Area) Levee, Wash. (NPP) 
37-41, 37-44 
Kalamazoo River (Battle Creek), Mich.(NCE) 21-56 
Kalamazoo River (Kalamazoo), Mich. (NCE) 21-56 
Kalaupapa Harbor, Molokai, Hawaii (POD) 36-10 
Kanawha River, W. Va. (ORH) 17-2, 17-12, 17-17 
Kaneohe-Kailua Area, Oahu, Hawaii (POD) 36-12 
Kaneohe-Kailua Dam, Oahu, Hawaii (POD) 36-15 
Kankakee River, Ill. and Ind. (NCC) 22-17 
Kanopolis Lake, Smoky Hill River, Kan. (MRK) 
27-3, 27-9, 27-12, 27-19 
Kansas City, Kansas River, Kan. (1962 Mod.) (MRK) 
27-16 
Kansas Citys on Mo. and Kansas Rivers, Mo. and 
Kan. (MRK) 27-16 
Kansas River and Minor Tributaries (MRK) 27-19 
Kansas River Navigation, Kan. (MRK) 27-17 
Kapaa Town, Kauai, Hawaii (POD) 36-11 
Kapaakea Homestead Flood Control, Molokai, Hawaii 
(POD) 36-13 
Karlson Island, Oreg. (NPP) 37-38 
Kasilof Harbor, Alaska (NPA) 40-12 
Kaskaskia Island Drainage and Levee District, Ill. 
(LMS) 14-3, 14-8, 14-11, 14-14 
Kaskaskia River, Ill. (LMS) 14-2, 14-8, 14-10 
Kaulana Bay Boat Harbor Hawaii, Hawaii (POD) 
36-2, 36-7, 36-10 
Kaumalapau Harbor, Lanai, Hawaii (POD) 36-14 
Kaunakakai Harbor, Molokai, Hawaii (POD) 36-10 
I-32

INDEX 
Kaunakakai Stream, Molokai, Hawaii (POD) 36-12, 
36-15 
Kaw Lake, Okla. (SWT) 29-5, 29-13, 29-17 
Kawaihae Harbor, Hawaii, Hawaii (POD) 36-10 
Kawainui Marsh, Oahu, Hawaii (POD) 36-15 
Kawainui Swamp, Oahu, Hawaii (POD) 36-12, 36-15 
Kaweah and Tule Rivers, including Terminus Dam 
and Success Lake, Calif. (SPK) 35-10, 35-25 
Kawkawlin River, Mich. (NCE) 21-55 
Kawkawlin, Kawkawlin River, Mich. (NCE) 21-27 
Kays Creek, Utah (SPK) 35-34 
Keach Drainage and Levee District. Ill. (LMS) 14-14 
Keehi Lagoon, Oahu, Hawaii (POD) 36-10 
Keene, N.H. (NED) 1-23, 1-42, 1-49 
Kehoe Lake, Ky. (ORH) 17-21 
Keithsburg Drainage District, Ill. (NCR) 23-15 
Kekaha Beach, Kauai, Hawaii (POD) 36-11 
Kelly Creek, Monett, Ark. (SWL) 28-25 
Kelleys Island, Ohio (NCB) 20-35 
Kenai, Ark. (NPA) 40-13 
Kendrick, Potlatch River, Idaho (NPW) 39-12 
Kenmore Navigation Channel, Wash. (NPS) 38-24 
Kennebec River, Maine (NED) 1-24, 1-39, 1-44 
Kennebunk River, Maine (NED) 1-39 
Kennedy Twp. and McKees Rocks Borough, Penn. 
(ORP) 18-26 
Kenosha Harbor, Wis. (NCE) 21-11, 21-34, 21-47 
Kentucky Lock, Ky. (ORN) 15-17 
Kentucky River, Ky. (ORL) 16-2, 16-13, 16-27 
Kentucky River, Locks and Dams (ORL) 16-23 
Keokuk Harbor, Iowa (NCD) 25-8 
Kern River-California Aqueduct Intertie, Calif. 
(SPK) 35-34 
Kerr, John H., Dam and Reservoir, Va. and N.C. 
(SAW) 6-5, 6-16, 6-20 
Kerr, Robert S., Lock and Dam, Okla. (SWL) (SWT) 
28-20, 29-16, 29-18, 29-20 
Kerton Valley Drainage and Levee District, Ill. 
(NCC) 23-16 
Ketchikan Harbor, Alaska (NPA) 40-12, 40-13 
Kewalo Harbor, Oahu, Hawaii (POD) 36-13 
Kewaunee Harbor, Wis. (NCE) 21-11, 21-35 
Kewaunee River, Wis. (NCE) 21-47, 21-57 
Keweenaw, Eagle River, Mich. (NCR) 21-25 
Keweenaw Waterway, Mich. (NCE) 21-12, 21-35, 
21-47 
Key Creek, Minden (WW Lagoon), Iowa (MRO) 
26-23 
Key West, Fla. (SAJ) 9-48 
Key West Harbor, Fla. (SAJ) 9-47 
Keyport Harbor, NJ. (NAN) 2-33, 2-34, 2-38 
Keystone, Okla. (SWL) 28-22 
Keystone Lake, Okla. (SWT) 29-9, 29-15, 29-18 
29-20 
Kickapoo River, Gay Mills, Wis. (NCS) 24-28 
Kihei Beach, Mauri, Hawaii (POD) 36-11 
Kihei Shoreline Protection, Maui, Hawaii (POD)36-14 
Kikiaola Small Boat Harbor, Hawaii (POD) 36-10 
Kill Van Kull-Newark Bay Channel, NJ. and N.Y. 
(NAN) 2-8, 2-23, 2-29 
Kindred Lake, N. Dak. (NCS) 24-30 
Kings Creek, Va. (NAO) 5-19 
Kingston Harbor, Wash. (NPS) 38-24 
Kingston Harbor (North Plymouth), Mass. (NED) 
1-39 
Kingston-Edwardsville, Pa. (NAB) 4-39, 4-42 
Kingstree Branch, Williamsburg County, S.C. (SAN) 
7-15 
Kinley Creek, Lexington County, S.C. (SAN) 7-15 
Kinzua Dam and Allegheny Reservoir, Ohio River 
Basin, Pa. and N.Y. (ORP) 18-5, 18-12, 18-17, 
18-25 
Kirwan, Michael J., Dam and Reservoir, Ohio (ORP) 
18-6, 18-12, 18-17, 18-25 
Kishwaukee River at De Kalb, Ill. (NCR) 23-13 
Kissimmee River, Fla. (SAJ) 9-47 
Kittanning, Pa. (ORP) 18-25 
Kittanning, Pa. Part I (ORP) 18-20 
Kittanning, Pa. Part I (Allegheny River) (ORP) 18-24 
Kittanning, Pa. Part II (Allegheny River) (ORP) 18-21 
Kitzmiller, Md. (NAB) 4-39, 4-42 
Klamath River, Calif. (SPK) 35-34 
Klutina River, Copper Center, Alaska (NPA) 40-13 
Knappa Area, Oreg. (NPP) 37-38 
Knapps Narrows, Md. (NAB) 4-7, 4-25, 4-33 
Knife River, Minn. (NCE) 21-60 
Knife River, Stanton, N. Dak. (MRO) 26-23 
Knife River Harbor, Minn. (NCE) 21-55 
Knights Valley Lake, Calif. (SPN) 34-13 
Knightville Dam, Mass. (NED) 1-14, 1-23, 1-28, 1-48 
Knobb's Creek, N.C. (SAW) 6-25 
Kodiak Harbor, Alaska (NPA) 40-7, 40-12 
Kootenai River, Idaho and Mont. (NPS) 38-24, 38-26 
Krotz Springs (MR+T) 42-14 
Kualoa Regional Park, Hawaii (POD) 36-11 
Kuliouou Stream, Oahu, Hawaii (POD) 36-12, 36-15 
I-33

L 
L'Anguille Basin, Ark. (MR+T) 42-30 
L'Anguille River, Ark. (MR+T) 42-18 
La Conner, Wash. (NPS) 38-26 
La Crosse, Wis. (NCS) 24-30 
La Farge Lake and Channel Improvement, Wis. 
(NCS) 24-9, 24-23 
La Grange Bayou, Fla. (SAM) 10-47, 10-50 
La Grange Gut, Frederiksted, V.I. (SAJ) 5-54 
LaPlatte R. Shelbume Bay, Vt. (NAN) 2-38 
La Pointe Harbor, Wis. (NCE) 21-55 
La Trappe, Md. (NAB) 4-37 
Labette County Bridge, Kans. (SWT) 29-21 
Lac La Belle Harbor, Mich. (NCE) 21-55, 21-60 
Lac Qui Parle Lake, Minnesota River, Minn. (NCS) 
24-9, 24-23, 24-34 
Lacey Drainage and Levee District, Ill. (NCR) 23-16 
Lacey, Langellier, West Mantanzas and Kerton Valley 
Drainage and Levee District, Ill. (NCR) 23-13 
Lackawanna, N.Y. Smokes Creek (NCB) 20-37 
Lackawanna River Basin, Pa. (NAB) 4-13, 4-35 
Lacour-Red Cross (MR+T) 42-13 
Lafayette Lake, Ind. (Wabash River) (ORL) 16-20 
Lafayette River, Va. (NAO) 5-19 
Lago De Cerrillos, P.R. (SAJ) 9-42 
Lago De Portugues, P.R. (SAJ) 9-42 
Lagoon Pond, Martha's Vineyard, Mass. (NED) 1-39 
Lahaina Small Boat Harbor, Maui, Hawaii (POD) 
36-10 
Lake Andrusia, Mississippi River, Minn. (NCS) 24-9, 
24-23 
Lake Ashtabula and Baldhill Dam, Sheyenne 
River, N. Dak. (NCS) 24-10, 24-23 
Lake Borgne and Chef Menteur-Bulkheads 
Jetties (LMN) 11-16 
Lake Brownwood Modification, Tex. (SWF) 30-22 
Lake Camanche, Calif. (SPK) 35-34 
Lake Cantlin, Minn. (NCS) 24-34 
Lake Carnelian, Steamrns Co., Minn. (NCS) 24-34 
Lake Charles Deep Water Channel, La. (LMN) 11-13, 
11-16 
Lake Charlotte, Minn. (NCS) 24-34 
Lake Chautauqua and Chadakoin River, N.Y. (ORP) 
18-21 
Lake City, Tenn. (ORN) 15-19 
Lake City Harbor, Minn. (NCD) 25-7, 25-10 
Lake Crescent and Dunns Creek, Fla. (SAJ) 9-47 
Lake Crockett, Wash. (NPS) 38-3, 38-15, 38-20, 
38-29 
Lake Darling, N. Dak. (NCS) 24-28 
Lake Douglas, Ga. (SAM) 10-48 
Lake Elsinore, Riverside Co., Calif. (SPL) 33-28 
Lake Erie, Athol Springs, Hamburg, N.Y. (NCB) 
20-30 
Lake Erie, Domonakas Library, Sheffield Lake, Ohio 
(NCB) 20-93 
Lake Erie, Eastland, Ohio (NCB) 20-39 
Lake Erie, Fredonia, N.Y. (NCB) 20-39 
Lake Erie, Liwood Park, Vermilion, Ohio (NCB) 
20-39 
Lake Erie, Middle Bass Island, Deist Rd., Ohio (NCB) 
20-39 
Lake Erie-Ohio Canal, Ohio and Penn. (ORP) 18-21 
Lake Erie, Sheffield, Ohio (NCB) 20-38 
Lake Erie, State Park, Brocton, N.Y. (NCB) 20-3 
Lake Erie, Sturgeon Pt., Evans, N.Y. 28-209 
Lake Fork Lake, Sabine River, Tex. (SWF) 30-22 
Lake George, Hobart, Ind. (NCC) 22-9, 22-15 
Lake Gunterville, Ala. (ORN) 15-19 
Lake Harbor, Fla. (SAJ) 9-48 
Lake Hudson, Okla. (SWT) 29-20 
Lake Kemp, Tex. (SWT) 29-6, 29-13, 29-17 
Lake Lanier Reregulation Dam (SAS) 8-9 
Lake Massasecum, Bradford, N.H. (NED) 1-47 
Lake Michigan, Edgewater/Rogers Park Communities, 
Chicago, Ill. (NCC) 22-6, 22-11, 22-14 
Lake Michigan-Lake Bluff, Ill. (NCC) 22-17 
Lake Michigan-Lake Forest, Ill. (NCC) 22-17 
Lake Michigan, Lake Shore, Fullerton, Ill. (NCC) 
22-8 
Lake Michigan, Temple Emanuel, Ill. (NCC) 22-8 
Lake Michigan Shoreline, Cleveland, Wis. (NCB) 
21-25 
Lake Michigan Shoreline, Cudahy, Wis. (NCB) 21-25 
Lake Michigan Shoreline, Muskegon, Mich. (NCB) 
21-25 
Lake Michigan Shoreline, S. Milwaukee, Wis. (NCE) 
21-25 
Lake Michigan Shoreline, Whitefish Bay, Wis. (NCB) 
21-25 
Lake Montauk Harbor, N.Y. (NAN) 2-33, 2-34 
Lake Ogleton, Md. (NAB) 4-40 
Lake Ontario, Lake Rd., Webster, N.Y. (NCB) 20-39 
I-34

INDEX 
Lake Ontario, Rochester Harbor, N.Y. (NCB) 20-38 
Lake Oroville, Calif. (SPK) 35-34 
Lake Pontchartrain, La. (MR+T) 42-15 
Lake Pontchartrain-Jefferson Parish, La. (MR+T) 
42-29 
Lake Pontchartrain, North Shore, La. (LMN) 11-14 
Lake Pontchartrain and Vicinity, La., (Hurricane 
Protection) (LMN) 11-6, 11-11, 11-14 
Lake Providence Harbor, La. (LMK) 12-15 
Lake Pulaski, Wright Co., Minn. (NCS) 24-11, 24-23 
lake River, Wash. (NPP) 37-37, 37-42 
Lake River Delta Area, Wash. (NPP) 37-41, 37-44 
Lake Shelbyville, Ill. (LMS) 14-14 
Lake Sidney Lanier, Ga. (SAM) 10-46 
Lake St. Clair, Mich., Channels (NCE) 21-12, 21-35, 
21-48 
Lake Susupe, CNMI (POD) 36-15 
Lake Texoma, Tex. and Okla. (ORD) (SWT) 19-9, 
29-15, 29-18 
Lake Traverse, Minn. and S. Dak. (NCS) 24-27 
Lake Traverse and Bois De Sioux River, S. Dak. and 
Minn. (NCS) 24-11, 24-23 
Lake Washington Ship Canal, Wash. (NPS) 38-4, 
38-15, 38-20, 38-28 
Lake Wichita, Holliday Creek, Tex. (SWT) 29-6, 
29-13, 29-17 
Lakeport Lake, Calif. (SPK) 35-36 
Lakes, Levees, and Recreational Facilities (LMS) 
14-13 
Lakeshore Park, Ashtabula, Ohio (NCB) 20-20, 20-33 
Lakeview Park, Lorain, Ohio (NCB) 20-36 
Lamoille River, Vt. (NAN) 2-36, 2-37 
Lamprey River, N.H. (NED) 1-39 
Lancaster, Mass. (NED) 1-23 
Lancaster, N.Y. Cayuga Creek (NCB) 20-37 
Lancaster, Israel River, N.H. (NED) 1-42 
Langellier Drainage and Levee District, Ill. (NCC) 
23-16 
Lansing (Grand River), Mich. (NCE) 21-57 
Lansing Harbor, Iowa (NCD) 25-7, 25-10 
Lapwai Creek, Culdesac, Idaho (NPW) 39-14, 39-15 
Larchmont Harbor, N.Y. (NAN) 2-34 
Largo Sound Channel, Fla. (SAJ) 9-47 
Lamed, Kans. (SWT) 29-19, 29-20 
Larose to Golden Meadow, La. (Hurricane 
Protection) (LMN) 11-7, 11-11, 11-14 
Las Animas, Colo. (SWA) 32-14 
Las Cruces, N. Mex. (SWA) 32-14 
Las Tunas Beach, Calif. (SPL) 33-24 
Las Vegas Wash Tributaries, Nev. (SPL) 33-27 
Latrobe, Pa. (ORP) 18-20, 18-25 
Latrobe, Pa. (Allegheny River Basin) (ORP) 18-24 
Latta Brook Road, N.Y. (NAB) 4-39 
Lauliifou Shoreline Protection, American Samoa 
(POD) 36-16 
Lauliituai-Aumi, Tutuila Island American Samoa 
(POD) 36-14 
Laupahoehoe Harbor, Hawaii, Hawaii (POD) 36-2, 
36-7 
Laurel, Miss. (SAM) 10-49 
Laurel River Lake, Ohio River Basin, Ky. (ORN) 
15-7, 15-9, 15-18 
Lava Hot Springs, Portneuf River, Idaho (NPW) 39-15 
Lavaca-Navidad River, Tex. (SWG) 31-31 
Lavon Lake, Tex. (SWF) 30-7, 30-16, 30-19 
Lavon Lake Modification and East Fork Channel 
Improvement, Tex. (SWF) 30-7, 30-16, 30-20 
Lawrence, Kansas River, Kan. (MRK) 27-16, 27-19 
Lawrenceburg, Ind. (ORL) 16-19, 16-24, 16-29 
Lawyers Creek, Kamiah, Idaho (NPW) 39-17 
Lazer Creek Lake, Ga. (SAM) 10-48 
Lead Bayou, Miss. (LMK) 12-4, 12-9, 12-11 
Leading Creek, W. Va. (ORH) 17-21 
Leaf and Bowie Rivers, Hattiesburg, Miss. (SAM) 
10-15, 10-34, 10-44 
Leaf and Chickasawhay River, Miss. (SAM) 10-47 
Leaf River, County Rd. Bridge, Mahned, Miss. (SAM) 
10-48 
Leavenworth, Ind. (ORL) 16-21, 16-25 
Lebanon Junction. Ky. (Salt River) (ORL) 16-19, 
16-29 
Le Claire Lock (Canal), Iowa (NCD) 25-5 
LeSueur, Minn. (NCS) 24-33 
Lee County, Fla. (SAJ) 9-48 
Lee, Housatonic River, Mass. (NED) 1-23, 1-42 
Leech Lake Reservoir, Minn. (NCS) 24-31 
Leesville, Va., Roanoke River, Sec. 32, Demo. Project 
(SAW) 6-20 
Leetonia, Ohio (ORP) 18-20 
Leetsdale, Pa. (ORP) 18-21 
Leipsic River, Del. (NAP) 3-25 
Leith's Creek, N.C. (SAW) 6-27 
Leith's Creek, S.C. (SAN) 7-15 
Leland Bowman Lock, La. (formerly Vermilion Lock) 
(LMN) 11-16 
Leland Harbor, Mich. (NCE) 21-12, 21-35, 21-48 
I-35

Lemon Creek, N.Y. (NAN) 2-34 
Lepua Area, American Samoa (POD) 36-3, 36-7 
Les Cheneaux Islands, Channels, Mich. (NCE) 21-55, 
21-60 
Letart, W. Va. (ORH) 17-22 
Letart Falls, Ohio (ORH) 17-22 
Levee Districts between Carlyle and New Athens, Il. 
(No. 2,3,4,5,6,7,8,10,13) (LMS) 14-14 
Levee Districts between Cowden and Vandalia, Ill. 
(LMS) 14-14 
Levee Unit 1, Eel River, Ind. (ORL) 16-21, 16-25 
Levee Unit 2, Eel River, Ind. (ORL) 16-21, 16-25 
Levee Unit 2, East Fork White River, Ind. (ORL) 
16-21 
Levee Unit 3, East Fork White River, Ind. (ORL) 
16-21 
Levee Unit 1, Ill. (Wabash River) (ORL) 16-21 
Levee Unit 1, Little Wabash River, Ill. (ORL) 16-21, 
16-25 
Levee Unit 2, Little Wabash River, Ill. (ORL) 16-21, 
16-25 
Levee Unit 17, Ind. (ORL) 16-25 
Levee Unit 2, Wabash River, Ill. (ORL) 16-21 
Levee Units 3 and 4, Wabash River, Ill. (ORL) 16-21 
Levee Unit 6, Wabash River, Ill. (ORL) 16-21, 16-25 
Levee Unit 17, Wabash River Basin, Ind. (ORL) 
16-21 
Levee Unit 1, White River, Ind. (ORL) 16-21, 16-25 
Levee Unit 2, White River, Ind. (ORL) 16-25 
Levee Unit 7, White River, Ind. (ORL) 16-21, 16-25 
Levee Unit 9, White River, Ind. (ORL) 16-21 
Levee Unit 10, White River, Ind. (ORL) 16-21 
Levee Unit No. 5, Wabash River, Ind. (ORL) 16-19, 
16-29 
Levee Unit No. 8, Ind. (White River) (ORL) 16-9, 
16-29 
Levees (NAP) (MR+T) 3-13, 42-4, 42-10, 42-46 to 
42-51 
Levees, Missouri River (MRO) 26-21 
Levees Expenditures (MR+T) 42-62 
Levels of the Great Lakes (NCE) 21-29 
Levisa and Tug Forks of the Big Sandy River and 
Cumberland River, W. Va., Va., and Ky. (ORH) 
17-6, 17-13, 17-18 
Lewis and Clark River Area, Oreg. (NPP) 37-38 
Lewis River, Wash. (NPP) 37-37, 37-38, 37-42 
Lewis River Area, Wash. (NPP) 37-41, 37-44 
Lewisport, Ky. (ORL) 16-19, 16-24 
Lewiston-Clarkston Bridge, Idaho and Wash. 
(NPW) 39-5, 39-9, 39-13 
Lewisville Dam, Tex. (SWF) 30-7, 30-16, 30-20 
Lexington Harbor, Mich. (NCE) 21-12, 21-35, 21-48 
Libby Dam-Lake Koocanusa, Mont. (NAS) 38-10, 
38-18, 38-22 
Libby Dike, Coal Bank Slough, Oreg. (NPP) 37-43 
Liberty Local Protection Project, Tex. (SWG) 31-31 
Libertyville Estates, Ill. (NCC) 22-8 
License Fees Collected Through Fiscal Year 1988 
(NCD) 25-9 
Lick Creek, Hartford, City (Blackford Co.), Ind. 
(ORL) 16-30, 16-31 
Lick Run, Baldwin, Penn. (ORP) 18-26 
Lick Run, Roanoke, Va. (SAW) 6-27 
Licking River, Ky. (ORL) 16-18, 16-27, 16-30, 16-31 
Lido Key, Fla. (SAJ) 9-48 
Lighthouse Point Park, Conn. (NED) 1-41 
Limestone Creek, Fayettville, N.Y. (NCB) 20-39 
Lincoln, N.H. (NED) 1-23 
Lincoln lake, Ind. (ORL) 16-22 
Lincoln Park Beach, Wash. (NPS) 38-7, 38-16, 38-21 
Lincoln Salt Creek and Tribs., Nebr. (MRO) 26-20 
Linton, N. Dak. (MRO) 26-16 
Lisbon, N. Dak. (NCS) 24-34 
Lisle, N.Y. (NAB) 4-7, 4-28 
Little Bay, Tex. (SWG) 31-30 
Little Bay De Noc, Gladstone Harbor, Mich. (NCE) 
21-55 
Little Beaver Creek, Kettering, Ohio (ORL) 16-31 
Little Blue River, Clay Co., Nebr. (MRK) 27-21 
Little Blue River, Jefferson Co., Nebr., Rd. at Endicott 
(MRK) 27-21 
Little Blue River, Jefferson Co., Nebr., Crystal 
Springs Bridge at Fairbury (MRK) 27-21 
Little Blue River, Nuckolls Co., Nebr. (MRK) 27-21 
Little Blue River, Steele City, Nebr., Sewage Lagoons 
(MRK) 27-21 
Little Blue River, Thayer Co., Nebr., Gilead North 
Bridge (MRK) 27-21 
Little Blue River, Washington Co., Kan., County Rd. 
(MRK) 27-21 
Little Blue River, Washington Co., Kan., Spence Rd. 
(MRK) 27-21 
Little Blue River Channel Improvement, Little Blue 
River, Mo. (MRK) 27-3, 27-9 
I-36

INDEX 
Little Blue River Lakes, Little Blue River, Mo. 
(MRK) 27-4, 27-9, 27-13 
Little Caillou Bayou, La. (LMN) 11-16 
Little Calumet River, Ill. (NCC) 22-17 
Little Calumet River, Ind. (NCC) 22-7, 22-11, 22-14 
Little Calumet River Basin (Caddy Marsh Ditch), Ind. 
(NCC) 22-17 
Little Colorado River at Holbrook, Ariz. (SPL) 33-9 
Little Cove Creek, Glencoe, Ala. (SAM) 10-44, 10-48, 
10-49 
Little Creek, Kent Island, Md. (NAB) 4-37 
Little Dell Lake, Utah (SPK) 35-11, 35-25 
Little Egg Harbor, NJ. (NAP) 3-25 
Little Goose Lock and Dam-Lake Bryan, Wash. 
(NPW) 39-5, 39-9,39-13, 39-19, 39-22 
Little Harbor, N.H. (NED) 1-39 
Little Harbor, Woods Hole, Mass. (NED) 1-39 
Little Harpeth River, Brentwood, Tenn. (ORN) 15-19 
Little Kanawha River, W. Va. (ORH) 17-20 
Little Lake Harbor, Mich. (NCE) 21-13, 21-35, 21-48 
Little Machipongo River, Va. (NAO) 5-19 
Little Manatee River, Fla. (SAJ) 9-47 
Little Massard Creek, Fort Smith, Ark. (SWL) 28-6, 
28-12 
Little Miami River, Ohio (ORL) 16-27, 16-30 
Little Missouri River, Ark. (LMK) 12-15 
Little Missouri River below Murfreesboro, Ark. 
(LMK) 12-17 
Little Neck Bay, N.Y. (NAN) 2-34 
LittleNemaha River, Nemaha Co., Nebr. (MRO) 
26-17 
Little Papillion, Little Papillion Creek, Nebr. (MRO) 
26-20 
Little Papillion, Nebr. (MRO) 26-16 
Little Quilcene River, Wash. (NPS) 38-8, 38-16, 
38-21 
Little Red River District 1, Ark. (SWL) 28-17 
Little Red River and Tributaries, Clinton, Ark. (SWL) 
28-6, 28-12 
Little Red River, White County Road Bridge, 
Judsonia, Ark. (SWL) 28-17 
Little River, Del. (NAP) 3-24 
Little River, La. (LMK) 12-15 
Little River at Cayuga Island, N.Y. (NCB) 20-35 
Little River Basin (Little Rock District), Ark. (SWL) 
28-6, 28-12, 28-23 
Little River Belfast, Me. (NED) 1-19, 1-31, 1-36 
Little River (Creek), Va. (NAO) 5-19 
Little River Dike, Westfield, Mass. (NED)/1-42 
Little River Diversion Channel, Mo. (MR+T) 42-19 
Little River Inlet, N.C. and S.C. (SAN) 7-4, 7-8, 7-12 
Little Rock Levee, Ark. (East End Fourche Bayou) 
(SWL) 28-17 
Little Rock Slackwater Harbor, Arkansas River, Ark. 
(SWL) 28-3, 28-11 
Little Rockfish Creek, Hope Mills, N.C. (SAW) 6-27 
Little Sioux River, Anthon, Iowa (MRO) 26-21, 26-23 
Little Sioux River, Iowa (MRO) 26-4, 26-12 
Little Sioux River and Tributaries, Iowa (MRO) 26-9 
Little Sioux River at Spencer, Iowa (MRO) 26-33 
Little Sodus Bay Harbor, N.Y. (NCB) 20-7, 20-18, 
20-29 
Little Sugar Creek, Charlotte, N.C. (SAW) 6-27 
Little Tallahatchie River, Miss. (LMK) 12-15 
Little Tennessee River, Tenn. (ORN) 15-13 
Little Valley Wash, Magna, Utah (SPK) 35-36 
Little Wabash River, Wayne Co., Ill. (ORL) 16-31 
Little Walnut Creek, Austin, Tex. (SWF) 30-23 
Little Wicomico River, Va. (NAB) 4-37, 4-41 
Little Wood River, Idaho (NPW) 39-12, 39-16, 39-17 
Littleville Lake, Mass. (NED) 1-14, 1-23, 1-28, 1-48 
Liverpool Drainage and Levee District, Ill. (NCR) 
23-13, 23-16 
Local Protection Projects (NED) 1-48, 1-49, 1-50, 
1-51, 1-52 
Lock and Dam No. 1, Minn. (NCD) 25-5 
Lock and Dam No. 2, Ark. (SWL) 28-19 
Lock No. 2 and Wilbur D. Mill Dam (No.2), Ark. 
(SWL) 28-3 
Look and Dam No. 2, Minn. (NCD) 25-5 
Lock and Dam No. 3, Ark. (SWL) 28-3, 28-19 
Lock and Dam No. 3, Minn. (NCD) 25-5 
Lock and Dam No. 4, Ark. (SWL) 28-3, 28-19 
Lock and Dam No. 4, Wis. (NCD) 25-5 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
Lock and Dam No. 
5, Ark. (SWL) 28-3, 28-19 
5, Minn. (NCD) 25-5 
5A, Minn. (NCD) 25-5 
6, Wis. (NCD) 25-5 
7, Minn. (NCD) 25-5 
8, Wis. (NCD) 25-5 
9, Wis. (NCD) 25-5 
11, Ark. (SWL) 28-20 
11, Iowa (NCD) 25-5 
Lock and Dam No.-12, Iowa (NCD) 25-5 
I-37

Lock and Dam No. 13, Ark. (SWT) 29-20 
Lock and Dam No. 13, Iowa (NCD) 25-5 
Lock and Dam No. 14, Iowa (NCD) 25-5 
Lock and Dam No. 15, Ill. (NCD) 25-5 
Lock and Dam No. 16, Iowa (NCD) 25-5 
Lock and Dam No. 17, Ill. (NCD) 25-6 
Lock and Dam No. 18, Iowa (NCD) 25-6 
Lock and Dam No. 19, Iowa (NCD) 25-6 
Lock and Dam No. 21, Ill. (NCD) 25-6 
Lock and Dam No. 22, Mo. (NCD) 25-6 
Lock and Dam No. 24, Mo. (NCD) 25-6 
Lock and Dam No. 25, Mo. (NCD) 25-6 
Lock and Dam No. 26, Ill. (NCD) 25-6 
Lock and Dam No. 26 (Replacement) (LMS) 14-10 
Lock S-53, Fla. (SAJ) 9-49 
Lock S-55, Fla. (SAJ) 9-49 
Lock S-57, Fla. (SAJ) 9-49 
Lock S-58, Fla. (SAJ) 9-49 
Lock S-59, Fla. (SAJ) 9-49 
Lock S-60, Fla. (SAJ) 9-49 
Lock S-61, Fla. (SAJ) 9-49 
Lock S-62, Fla. (SAJ) 9-49 
Lock S-63, Fla. (SAJ) 9-49 
Lock S-63A, Fla. (SAJ) 9-49 
Lock S-65, Fla. (SAJ) 9-49 
Lock S-65A, Fla. (SAJ) 9-49 
Lock S-65B, Fla. (SAJ) 9-49 
Lock S-65C, Fla. (SAJ) 9-49 
Lock S-65D, Fla. (SAJ) 9-49 
Lock S-65E, Fla. (SAJ) 9-49 
Lock S-96, Fla. (SAJ) 9-49 
Lock S-96A, Fla. (SAJ) 9-49 
Lock S-157, Fla. (SAJ) 9-49 
Lock S-158, Fla. (SAJ) 9-49 
Lock S-193, Fla. (SAJ) 9-49 
Lock S-308B, Fla. (SAJ) 9-49 
Lock S-310, Fla. (SAJ) 9-49 
Lock Haven, Pa. (NAB) 4-22, 4-39 
Locklies Creek, Va. (NAO) 5-19 
Lockwoods Folly River, N.C. (SAW) 6-6, 6-18 
Lodge Creek, Chinook, Mont. (MRO) 26-23 
Logan, Ohio (ORH) 17-21 
Logan Creek, Bancroft, Nebr. (MRO) 26-23 
Logan Creek, Bank Protection, near Bancroft, Nebr. 
(MRO) 26-20 
Logan Creek, Wakefield, Nebr. (MRO) 26-23 
Lone Rock, Ark. (SWL) 28-18 
Long Beach Island, N.J. (NAP) 3-26 
Long Branch Lake, Little Carlton River, Mo. (MRK) 
27-4, 27-10, 27-13 
Long Island Intracoastal Waterway, N.Y. (NAN) 2-8, 
2-23, 2-29 
Long Lake Area, Helena, Ark. (LMM) 13-5 
Long Tom River, Oreg. (NPP) 37-37 
Longboat Pass, Fla. (SAJ) 9-9, 9-28, 9-34, 9-46 
Lookout Point Lake, Oreg. (NPP) 37-19, 37-28, 37-35, 
37-43, 37-45 
Lorain Harbor, Ohio (NCB) 20-7, 20-19, 20-29 
Lorean Branch, Hurst, Tex. (SWF) 30-23 
Los Angeles and Long Beach Harbors, Calif. (SPL) 
33-2, 33-11, 33-17, 33-23 
Los Angeles County Drainage Area, Calif. (SPL) 
33-5, 33-13, 33-20 
Los Coches Creek, Calif. (SPL) 33-6, 33-13, 33-21 
Lost Creek at Columbus, Nebr. (MRO) 26-4, 26-10, 
26-12, 26-23 
Lost Creek Drainage and Levee District, Ill. (NCR) 
23-13, 23-15 
Lost Creek Lake, Oreg. (NPP) 37-20, 37-28, 37-35, 
37-43 
Lost River, Minn. (NCS) 24-28, 24-33 
Louisiana State Penitentiary Levee (MR+T) 42-30 
Louisville, Ky. (ORL) 16-19, 16-21, 16-24, 16-29 
Louisville Lake, Ill. (ORL) 16-20, 16-28 
Loup River, Columbus, Nebr. (MRO) 26-16 
Lovell, (Sewage Lagoon) Wyo. (MRO) 26-23 
Loves Park, Ill. (NCR) 23-8, 23-11 
Lowell, Mass. (NED) 1-23, 1-42, 1-51 
Lowell Creek, Alaska (NPA) 40-13 
Lower Arkansas River, Ark. (MR+T) 42-16, 42-30 
Lower Arkansas River Basin, Ark. (MR+T) 42-7 
Lower Auchumpkee Creek, Ga. (SAM) 10-48 
Lower Big Sioux River, Iowa and S. Dak. (MRO) 
26-16 
Lower Branch Rush River, N. Dak. (NCS) 24-28 
Lower Columbia River Basin, Oreg. and Wash. 
(NPP) 37-13, 37-14, 37-26, 37-34, 37-39, 37-44 
Lower Cowlitz River, Wash. (NPP) 37-38 
Lower Creek, Lenoir, N.C. (SAW) 6-31 
Lower Dry Creek, Lowden, Wash. (NPW) 39-14, 
39-15 
Lower Grand River, Mo. (MRK) 27-16 
Lower Granite Lock and Dam, Wash. (NPW) 39-5, 
39-10, 39-13, 39-14, 39-19, 39-22 
Lower Green River, Wash. (NPS) 38-29 
Lower Guyandotte River Basin, W. Va. (ORH) 17-21 
I-38

INDEX 
Lower Heart River, N. Dak. (MRO) 26-10, 26-12, 
26-16 
Lower Heart River, Mandan, N. Dak. (MRO) 26-23 
Lower Machodoc Creek, Va. (NAB) 4-37 
Lower Monumental Lock and Dam, Lake Herbert G. 
West, Wash. (NPW) 39-6, 39-10, 39-13, 39-20, 
39-22 
Lower Red River-South Bank, Red River Levees, 
La. (MR+T) 42-30 
Lower Red River Standard Revetments (MR+T) 42-35 
Lower Rio Grande Basin, Tex. (SWG) 31-11, 31-28 
Lower San Francisco Bay, Calif. (SPN) 34-12 
Lower San Joaquin River, Calif. (SPK) 35-11, 35-25 
Lower San Joaquin River and Tributaries, including 
Tuolumne and Stanislaus Rivers, Calif. (SPK) 
35-27, 35-34 
Lower Snake River, Fish and Wildlife Compensation 
Plan, Wash., Oreg., Idaho (NPW) 39-6, 39-10, 39- 
13 
Lower Thorofare, Deal Island, Md. (NAB) 4-7, 4-25, 
4-33 
Lower Walla Walla River, Wash. (NPW) 39-16 
Lower Walnut Creek, Austin, Tex. (SWF) 30-23 
Lower White River (MT+T) 42-9 
Lower White River, Ark. (all except Big Creek and 
Tribs.) (MR+T) 42-30 
Lower White River (Big Creek and Tribs.) (MR+T) 
42-30 
Lower White River and Basin, Ark. (MR+T) 42-17, 
42-55 
Lower Woonsocket, R.I. (NED) 1-42, 1-48 
Lowes Wharf, Md. (NAB) 4-37 
Loyalhanna Lake, Ohio River Basin, Pa. (ORP) 18-6, 
18-12, 18-17, 18-25 
Lubec, Maine (NED) 1-23 
Lubec Channel, Maine (NED) 1-39 
Lucky Peak Lake, Idaho (NPW) 39-3, 39-9, 39-13 
Ludington Harbor, Mich. (NCE) 21-13, 21-26, 21-35, 
21-48 
Lyman Creek, Ind. (WPW) 39-15 
Ludlow, Ky. (ORL) 16-21, 16-25 
Ludlow Lake, Vt. (NED) 1-44 
Lukfata Lake, Okla. and Ark. (SWT) 29-19 
Lusk Creek, Ill. (ORL) 16-30 
Lyford Levee, Ind. (Wabash River) (ORL) 16-19, 
16-29, 16-31 
Lyman Creek near Lexburg, Idaho (NPW) 39-14 
Lynches River and Clark Creek, S.C. (SAN) 7-14 
Lynn Harbor, Mass. (NED) 1-39, 1-44 
Lynn-Nahant Beach, Mass. (NED) 1-41 
Lynnhaven Inlet, Va. (NAO) 5-19, 5-21 
Lytle and Warm Creeks, Santa Ana River Basin, Calif. 
(SPL) 33-25 
Lytle Creek, Murfreesboro, Tenn. (ORN) 15-19 
M 
Maalaea Small Boat Harbor, Maui, Hawaii (POD) 
36-10 
MacDowell, Edward, Lake, N.H. (NED) 1-18, 1-30, 
1-51 
Machias River, Me. (NED) 1-24, 1-39, 1-42 
Mackay Creek, N.C. (SAW) 6-25, 6-28 
Mackinac Island Harbor, Mich. (NCE) 21-13, 21-36, 
21-48 
Mackinaw City Harbor, Mich. (NCE) 21-55, 21-60 
Macon, Ga. (SAS) 8-16 
Macy, Blackbird Creek, Nebr. (MRO) 26-20 
Mad Creek, Muscatine, Iowa (NCR) 23-16 
Mad River, Conn. (NED) 1-23, 1-42, 1-48 
Mad River, Waterbury, Conn. (NED) 1-47 
Mad River Basin, Calif. (SPK) 35-36 
Madeline Island, Lake Superior, Wis. (NCE) 21-26 
Madison, Ind. (ORL) 16-21, 16-25 
Madison, Union and Taylor Creeks, Nebr. (MRO) 
26-16 
Madison Bay, Md. (NAB) 4-37 
Madison Parish Port, La. (LMK) 12-15 
Madison River, Madison Co., Mount.(State Hwy 287) 
(MRO) 26-23 
Madison, Union and Taylor Creeks, Nebr. (MRO) 
26-20 
Magby Creek, Columbus, Miss. (SAW) 10-49 
Magruder Drainage District, Oreg. (NPP) 37-38, 
37-41, 37-44 
Mahnomen, Minn. (NCS) 24-33 
Mahoning Creek, Penn. (ORP) 18-25 
Mahoning Creek Lake, Ohio River Basin, Penn. 
(ORP) 18-6, 18-12, 18-17 
Mahoning River, Warren Twp., Ohio (ORP) 18-26 
Maiden Creek Reservoir, Pa. (NAP) 3-27 
Main Street, Wellsburg, W. Va. (ORP) 18-26 
Main Turning Basin (SWG) 31-36 
I-39

Maintenance and Repair Fleet and Marine 
Terminals, Ark. (SWL) 28-3 
Malaeloa Stream, American Samoa (POD) 36-15 
Malden River, Mass. (NED) 1-39 
Malheur Improvement District, Snake River, Oreg. 
(NPW) 39-15 
Malheur River, Oreg. (NPW) 39-12, 39-14, 39-16, 
39-17 
Maline Creek, Mo. (LMS) 14-11 
Mamaroneck Harbor, N.Y. (NAN) 2-34 
Manasquan River, N.J. (NAP) 3-24 
Manatee County, Fla. (SAJ) 9-48 
Manatee Harbor, Fla. (SAJ) 9-9, 9-28, 9-34 
Manatee River, Fla. (SAJ) 9-47, 9-54 
Manchester, Ohio (ORH) 17-22 
Manchester Harbor, Mass. (NED) 1-44 
Mandan, N. Dak. (MRO) 26-16 
Mandan, Lower Heart River, N. Dak. (MRO) 26-19 
Manele Bay Small Boat Harbor, Lanai, Hawaii (POD) 
36-10 
Manet Beach, Quincy, Mass. (NED) 1-24 
Manhasset Bay, N.Y. (NAN) 2-34 
Manhattan, Kansas River, Kan. (MRK) 27-16, 27-19 
Maniece Bayou, Ark. (LMN) (LMK) 11-18, 12-8, 
12-20 
Manistee Harbor, Mich. (NCE) 21-14, 21-36, 21-48 
Manistique Harbor, Mich. (NCE) 21-14, 21-36, 21-48 
Manitowoc Harbor, Wis. (NCE) 21-14, 21-36, 21-49 
Mankato and North Mankato, Minn. (NCS) 24-11, 
24-23 
Mankato, North Mankato, and LeHillier, Minn. (NCS) 
24-33 
Mann's Harbor, N.C. (SAW) 6-28 
Manokin River, Md. (NAB) 4-37 
Mansfield Hollow Lake, Conn. (NED) 1-21, 1-23, 
1-31, 1-52 
Mansura to Wax Lake Outlet (MR+T) 42-13 
Manteo (Shallowbag) Bay, N.C. (SAW) 6-6, 6-19 
Mantua Creek, NJ. (NAP) 3-24 
Maple River, N. Dak. (NCS) 24-30, 24-33 
Maple Swamp, S.C. (SAN) 7-16 
Mapleshade, Ohio (ORH) 17-22 
Mapusagatuai Stream, American Samoa (POD) 36-15 
Marais Des Cygnes River, Osawatomie, Kan., Water 
Supply Facilities (MRK) 27-21 
Marblehead Harbor, Mass. (NED) 1-44 
Marengo, Iowa (NCR) 23-13, 23-16 
Marginal Way, Ogunquit, Maine (NED) 1-24, 1-42 
Markham Ferry, Okla. (SWL) 28-22 
Marietta, Ohio (ORH) 17-22 
Marina Del Rey, Calif. (SPL) 33-2, 33-11, 33-18 
Marion, Ind. (Wabash River) (ORL) 16-21, 16-28 
Marion, Kans. (SWT) 29-6, 29-17, 29-20 
Marion County Drainage District, Mo. (NCR) 23-13, 
23-15 
Marion Lake, Kan. (SWT) 29-6, 29-13, 29-17 
Markland Locks and Dam, Ind. (ORD) 19-6, 19-9 
Marmarth, N. Dak. (MRO) 26-16 
Marmarth, Little Missouri River, N. Dak. (MRO) 
26-19 
Marne Creek, Yankton, S. Dak. (MRO) 26-19, 26-23 
Marquette Harbor, Mich. (NCE) 21-15, 21-36 
Marsh Creek, Geneva, N.Y. (NCB) 20-37 
Marshall, Minn. (NCS) 24-11, 24-23 
Marshalltown, Iowa (NCR) 23-13, 23-15 
Marshland Drainage District, Oreg. (NPP) 37-38 
Martin, John, Reservoir, Colo. (SWA) 32-3, 32-10 
Martin, Ky. (ORH) 17-21 
Martin Creek Miss., Prentiss County (SAM) 10-16, 
10-34, 10-44 
Martins Ferry, Ohio (ORP) 18-21 
Martins Fork Lake, Ky. (ORN) 15-5, 15-9, 15-18 
Martis Creek Lake, Martis Creek, Nev. and Calif. 
(SPK) 35-12, 35-25 
Marysville, Kan. (MRK) 27-17 
Marysville Lake, Calif. (SPK) 35-34 
Marysville, St. Claire River, Mich. (NCB) 21-26 
Masefau Bay, American Samoa (POD) 36-3, 36-7 
Mason, W. Va. (ORH) 17-22 
Mason and Menard Drainage District, Ill. (NCR) 
23-13, 23-15 
Mason Creek, Va. (SAW) 6-31 
Mason J. Niblack Levee, Ind. (Wabash River) (ORL) 
16-19, 16-24, 16-29 
Massillon, Ohio (ORH) 17-6, 17-13, 17-18 
Matafao Shoreline, American Samoa (POD) 36-11 
Matagorda Ship Channel, Tex. (SWG) 31-6, 31-16, 
31-24, 31-34, 31-38 
Matawan Creek, NJ. (NAN) 2-33, 2-34 
Matinicus Harbor, Maine (NED) 1-39 
Mats Mats Bay, Wash. (NPS) 38-24 
Mattapoisett Harbor, Mass. (NED) 1-44 
Mattituck Harbor, N.Y. (NAN) 2-33, 2-34 
Mauckport, Ind. (ORL) 16-21, 16-25 
I-40

INDEX 
Maumee Bay, Oregon, Ohio (NCB) 20-39 
Maumee Bay State Park, Ohio (NCB) 20-12, 20-20, 
20-33 
Maumee River, above Toledo, Ohio (NCB) 20-40 
Maumee River, Defiance, Ohio (NCB) 20-39 
Maunalua Bay Small Boat Harbor, Oahu, Hawaii 
(POD) 36-10 
Maurice River, N.J. (NAP) 3-24, 3-25, 3-27 
Mauvaise Terre Drainage and Levee District, Ill. 
(LMS) 14-4, 14-8, 14-11 
Mayaguez Harbor, P.R. (SAJ) 9-10, 9-28, 9-34 
Mayo, W. D., Lock and Dam, Okla. (SWL) (SWT) 
28-20, 29-20 
Maysville, Ky. (ORH) 17-21, 17-23 
McAlpine Locks and Dam (ORD) 19-6, 19-9 
McClellan-Kerr Arkansas River Navigation System 
(SWT) 29-11, 29-16 
McCook Lake, S. Dak. (MRO) 26-16 
McDonald Dike Road, Oreg. (NPP) 37-39 
McCorkie Creek, Wash. (NPP) 37-43 
McGee Creek Drainage and Levee District, Ill. 
(LMS) 14-5, 14-8, 14-11 
McGinnis Levee, Ind. (ORL) 16-21, 16-25 
McKees Rocks, Pa. (ORP) 18-21 
McKenzie Creek, Piedmont, Mo. (SWL) 28-25 
McKenzie River near Walterville, Oreg. (NPP) 37-39 
McKinney Bayou, Finn Bayou Segment, Ark. (LMN) 
(LMK) 11-8, 12-18, 12-20 
McLean Bottom Levee District No. 3, Arkansas 
River, Ark. (SWL) 28-17 
McNary Lock and Dam-Lake Wallula-Oreg. and 
Wash. (NPW) 39-7, 39-8, 39-10, 39-13, 39-21 
Meadow Grove, Buffalo Creek, Nebr. (MRO) 26-20 
Medomak River, Maine (NED) 1-39 
Medora (Sewage Lagoon), N. Dak. (MRO) 26-23 
Meherrin River, N.C. (NAO) 5-19 
Melbourne Harbor, Fla. (SAJ) 9-10, 9-28, 9-34 
Meldahl, Captain Anthony, Locks and Dam, Ky. 
(ORD) 19-8 
Melton Hill Lock and Dam, Tenn. (ORN) 15-17 
Melvern Lake, Marais des Cygnes (Osage) River, 
Kans. (MRK) 27-4, 27-10, 27-13, 27-19 
Melvern Lake and Pomona Lake (Road 
Improvement), Kan. (MRK)27-16, 27-19 
Melville (MR+T) 42-14 
Melvin Price Locks and Dam, Ill. (NCD) 25-6 
Melvin Price Locks and Dam, (2nd lock) Ill. (NCD) 
25-6 
Memorial Drive, McKinley Park, Wis. (NCB) 21-26 
Memorial Drive, Muskegon, Mich. (NCB) 21-26 
Memphis District Bank Revetments and Dikes 
(MR+T) 42-41, 42-44 
Memphis District, Levees (MR+T) 42-49, 42-62 
Memphis District, Channel Improvements (FY 1988) 
42-55 
Memphis Harbor, Tenn. (MR+T) 42-12, 42-31 
Memphis Harbor (Ensley Berm) (MR+T) 42-30 
Memphis, Wolf River, and Nonconnah Creek, Tenn. 
(LMM) 13-5 
Menemsha Creek, Mass. (NED) 1-39 
Menominee Harbor and River, Mich. and Wis. (NCE) 
21-15, 21-36, 21-49 
Meramec Park Lake, Mo. (LMS) 14-14 
Meramec River Basin, Mo. (LMS) 14-4, 14-11, 14-13 
Merced County Stream Group, Calif. (SPK) 35-13, 
35-26 
Merced County Streams, Calif. (SPK) 35-12, 35-26 
Merced River, Calif. (SPK) 35-34 
Mercer Lake, Welden River, Mo. (MRK) 27-16 
Meredosia Lake and Willow Creek Drainage and 
Levee District, Ill. (LMS) 14-11, 14-15 
Meredosia Levee and Drainage District, Ill. (NCR) 
23-13, 23-16 
Merkie Creek, Okla. (SWT) 29-21 
Merizo Harbor, Guam (POD) 36-14 
Mermentau River, La. (LMN) 11-17 
Mermentau River, Bayou Nezpique, and Bay Des 
Cannes, La. (LMN) 11-17 
Merriam, Turkey Creek, Kan. (MRK) 27-17 
Merriconeag Sound, Harpswell, Maine (NED) 1-42 
Merrimack River, Mass. (NED) 1-39, 1-51 
Merrimack River Basin, N.H. and Mass. (NED) 1-18, 
1-23, 1-51 
Metamora Lake, Ind. (ORL) 16-22 
Methow River, Wash. (NAS) 38-26 
Metlakatla Harbor, Alaska (NPA) 40-3, 40-8, 40-10 
Metropolis, Ill. (ORL) 16-21, 16-26 
Miami Harbor, Fla. (SAJ) 9-10, 9-28, 9-34, 9-46 
Miami River, Fla. (SAJ) 9-46 
Miami River, Oreg. (NPP) 37-39 
Miami River Basin, Pleasant Run, Vicinity Fairfield, 
Ohio (ORL) 16-18, 16-19 
Mianus River, Conn. (NED) 1-39 
Michael J. Kirwan Dam and Reservoir, Ohio (ORP) 
18-6, 18-12, 18-17, 18-25 
I-41

Michigan City Harbor, Ind. (NCC) 22-4, 22-10, 22-13, 
22-16 
Middle Beach, Conn. (NED) 1-41 
Middle Creek, Calif. (SPK) 35-34 
Middle Fork Nooksack River, Deming, Wash. (NPS) 
38-26 
Middle Nodaway River, Adair Co., Iowa, Bridge No. 
56240 (MRK) 27-21 
Middle Pebble Creek, Snyder, Nebr. (MRO) 26-20 
Middle River, Adair Co., Iowa (NCR) 23-17 
Middle River and Connecting Channels, Calif. (SPK) 
35-33 
Middle River and Dark Head Creek, Md. (NAB) 4-37 
Middle River at Argyle, Minn. (NCS) 24-12, 24-23 
Middle School, Wellsburg, W. Va. (ORP) 18-26 
Middleport, Ohio (ORH) 17-22 
Middlesboro, Cumberland River Basin, Ky. (ORN) 
15-5, 15-9 
Middlesboro, Ky. (Diversion Canal) (ORN) 15-19 
Middlesboro, Ky. (Yellow Creek) (ORN) 15-13, 
15-14, 15-19 
Middleton Shoals, Ga. and S.C. (SAS) 8-16 
Midland Drainage District, Oreg. (NPP) 37-38, 37-39, 
37-44 
Milan, Ill. (NCR) 23-4, 23-7, 23-11, 23-16 
Miles City, Mont. (MRO) 26-16 
Milford Harbor, Conn. (NED) 1-5, 1-26, 1-34, 1-44, 
1-53 
Milford Lake, Republican River, Kan. (MRK) 27-5, 
27-10, 27-13, 27-19 
Milk River, Blaine Co., (Finley Bridge) Mont. (MRO) 
26-23 
Milk River, Malta, Mont. (MRO) 26-23 
Milk River, Malta (Sewerline), Mont. 26-23 
Mill Brook, Brownsville, Vt. (NED) 1-14, 1-24, 1-28, 
1-36, 1-49 
Mill Creek, Dalton, Ga. (SAM) 10-49 
Mill Creek, Fort Smith, Ark. (SWL) 28-6, 28-12 
Mill Creek, Jefferson County, Ky. (ORL) 16-19, 
16-30 
Mill Creek, Md. (NAB) 4-40 
Mill Creek, N.C. (SAW) 6-28 
Mill Creek, Ohio (ORL) 16-3, 16-13, 16-22, 16-27 
Mill Creek, Sumrall, Miss. (SAM) 10-49 
Mill Creek, Tex. (SWG) 31-31 
Mill Creek, Va. (NAO) 5-19 
Mill Creek, Warrenville Tswp, Ohio (NCB) 20-39 
Mill Creek, Wash. (NPW) 39-16 
Mill Creek Lake, Wash. (NPW) 39-3, 39-9, 39-13 
Mill Creek Levee (MRO) 26-18 
Mill Four Drainage District, Oreg. (NPP) 37-39 
Mill Lake, Blue River, Mo. (MRK) 27-17 
Mill Run, Sinclairsville, N.Y. (ORP) 18-26 
Millbury, Mass. (NED) 1-23 
Miller, Ohio (ORH) 17-21 
Miller Pond Drainage District, Ill. (LMS) 14-15 
Millers Ferry Lock and Dam, Ala. (SAM) 10-22, 
10-35, 10-45 
Millersburg, Ohio (ORH) 17-22 
Millford Haven, Va. (NAO) 5-19 
Millican Lake, Tex. (SWF) 30-8, 30-16, 30-20 
Mills, Wilbur D. Dam (SWL) 28-19 
Millwood, W. Va. (ORH) 17-22 
Millwood Lake, Ariz. (SWL) 28-7, 28-12 
Millwood Lake, Little River Basin, Ark. (SWL) 28-23 
Milton, Ky. (ORL) 16-21, 16-25 
Milton, Pa. (NAB) 4-42 
Milton-Freewater, Walla Walla River, Oreg. (NPW) 
39-14, 39-15 
Milton Harbor, N.Y. (NAN) 2-34 
Milwaukee Harbor, Wis. (NCE) 21-15, 21-37, 21-49 
Milwaukee South Shore Park, Wis. (NCE) 21-26 
Mineral Creek, Wash. (NPS) 38-26 
Mingo Creek, Okla. (SWT) 29-6, 29-14, 29-17 
Mingo Creek, S.C. (SAN) 7-14 
Mingo Junction, Ohio (ORP) 18-21 
Mining City Lake, Ky. (Green River) (ORL) 16-20 
Minneapolis, Minn. (NCR) (NCD) (NCS) 23-3, 24-2, 
25-1, 25-4, 25-10 
Minneota, Minn. (NCS) 24-22, 24-28 
Minnesota River, Minn. (NCS) 24-2, 24-22, 24-26 
Minnesota River at Henderson, Minn. (NCR) 24-12, 
24-23 
Minnesota River at Le Sueur, Minn. (NCS) 24-28 
Minnewawa River, Marlborough, N.H. (NED) 1-47 
Minot, N. Dak. (NCS) 24-28, 24-33 
Mispillion River, Del. (NAP) 3-7, 3-16, 3-20 
Misquamicut Beach, Westerly, R.I. (NED) 1-41 
Mission and Lapwai Creeks, Idaho (NPW) 39-14, 
39-15 
Mission Hills, Rock and Brush Creeks, Kan. (MRK) 
27-21 
Mission Zanja Creek, Redlands, Calif. (SPL) 33-6, 
33-14, 33-21 
Mississinewa Lake, Ind. (ORL) 16-8, 16-15 
Mississippi Delta Region, La. (MR+T) 42-30 
1-42

INDEX 
Mississippi River Agricultural Area No. 8, Mo. (LMS) 
14-15 
Mississippi River Agricultural Area No. 10, Mo. 
(LMS) 14-15 
Mississippi River Agricultural Area No. 12, Mo. 
(LMS) 14-15 
Mississippi River, Alma, Wis. (NCS) 24-34 
Mississippi River, Alton to Gale, Ill., Underseepage 
Measures (LMS) 14-15 
Mississippi River, Baton Rouge, La. (LMN) 11-2 
Mississippi River and Alluvial Valley below Cape 
Girardeau, Mo. (MR+T) 42-2 
Mississippi and Leech Rivers, Minn. (NCS) 24-27 
Mississippi River and Tributaries (MR+T) 42-63 
Mississippi River and Tributaries, Active General 
Investigations (MR+T) 42-46 
Mississippi River and Tributaries-Authorizing Legislation 
(MR+T) 42-21 to 42-28 
Mississippi River and Tributaries-Channel 
Improvements (MR+T) 42-4 
Mississippi River and Tributaries-Levees (MR+T) 
42-4 
Mississippi River and Tributaries-Statement of Allotments 
and Accrued Expenditures for Flood Control 
(MR+T) 42-58 
Mississippi River at Alton, Ill. (LMS) 14-13 
Mississippi River at St. Louis, Mo. (LMS) 14-15 
Mississippi River Bank Revetments and Dikes 
(MR+T) 42-6, 42-32, 42-38, 42-41, 42-44 
Mississippi River, Baton Rouge to Gulf of Mexico, 
La. (LMN) 11-2, 11-11, 11-13 
Mississippi River between Brainerd and Grand 
Rapids, Minn. (NCS) 24-27 
Mississippi River between Missouri River and Minneapolis, 
Minn. (NCR) (NCS) (NCD) 23-3, 24-2, 
25-1, 25-4, 25-10 
Mississippi River between Missouri River and Minneapolis, 
Minn. (St. Louis Dist.) (Includes L and D 
26 Replacement) (LMS) 14-2 
Mississippi River between Ohio and Missouri Rivers, 
Mo. and Ill. (LMS) 14-2, 14-8, 14-10 
Mississippi River Commission (MR+T) 42-1 
Mississippi River Delta at and below New Orleans, 
La., (New Orleans to Venice, La.; Hurricane 
Protection) (LMN) 11-2 
Mississippi River-Gulf Outlet, La. (LMN) 11-3, 
11-11, 11-13 
Mississippi River-Gulf Outlet, Michoud Canal, La. 
(LMN) 11-17 
Mississippi River Levees (MR+T) 42-10, 42-30, 
42-46 to 42-51 
Missouri River Levee System, Iowa, Nebr. Kan., and 
Mo. (MRK) 27-10, 27-13 
Mississippi River Main Stem Channel Improvements 
(MR+T) 42-3 
Mississippi River, Morgan City (MR+T) 42-14 
Mississippi River near Aitkin, Minn. (NCS) 24-28 
Mississippi River Outlets, Venice, La. (LMN) 11-17 
Mississippi River Project Levees (MR+T) 42-46, 
42-48, 42-49, 42-51 
Mississippi River Ship Channel, Gulf to Baton Rouge, 
La. (LMN) 11-4, 11-11, 11-13 
Mississippi River Tributary Dams and Lakes 
(MR+T) 42-20 
Missouri Fish and Wildlife Mitigation (MRK) 27-16 
Missouri National Recreational River, Nebr. and S. 
Dak. (MRO) 26-4, 26-10, 26-12 
Missouri River, Mo. (MR+T) 42-19 
Missouri River at New Haven, Mo. (MRK) 27-16 
Missouri River, Aten, Nebr. (MRO) 26-16 
Missouri River, Bank Protection, Greenwood, S. 
Dak. (MRO) 26-19 
Missouri River, Bank Stabilization, Fort Benton, 
Mont. (MRO) 26-19 
Missouri River, Cedar Co., Nebr. (MRO) 26-23 
Missouri River, Garrison Dam to Lake Oahe, N. Dak. 
(MRO) 26-18 
Missouri River, Kenslers Bend, Nebr. to Sioux City, 
Iowa (MRO) 26-5, 26-10, 26-13 
Missouri River, Levees (MRO) 26-21 
Missouri River Levee System (MRK) 27-18 
Missouri River Levee System, Iowa, Nebr., Kan., 
and Mo. (Rulo, Nebr. to Mouth) (MRK)(MRO) 
26-5, 26-10, 26-13, 26-18, 27-5, 27-19 
Missouri River Levee System, (Sioux City, Iowa, to 
Rulo, Nebr.) (MRO) 26-18 
Missouri River Levee System, Kan., Units R402, 
R393-395, and R414 (MRK) 27-17 
Missouri River Main Stem (MRK) 27-19 
Missouri River, Marina, Sioux City, Iowa (MRO) 
26-20 
Missouri River, Niobrara, Nebr. (MRO) 26-16 
Missouri River, Sioux City, Iowa, to Fort Benton, 
Mont. (MRO) 26-15 
I-43

Missouri River, Sioux City, Iowa, to Mouth (Rulo, 
Nebr. to Mouth) (MRK) (MRO) 26-2, 27-2, 27-9, 
27-12 
Missouri River, Sioux City, Iowa, to Rulo, Nebr. 
(MRO) 26-9, 26-12 
Mitigation of Shore Damages (NCE) 21-26 
Mixons Creek, Lamar Co., Miss. (SAW) 10-49 
Mobile Bay, Ala. to New Orleans, La. (SAM) 10-35 
Mobile Harbor, Ala. (SAM) 10-10, 10-32, 10-41 
Mocassin Swamp, N.C. (SAW) 6-28 
Moccasin Springs, Mo. (LMS) 14-13 
Moclips River, Wash. (NPS) 38-26 
Mojave River Dam, Calif. (SPL) 33-7, 33-14, 33-21 
Mokelumne River, Calif. (SPK) 35-33 
Molalla River at Milk Creek location, Oreg. (NPP) 
37-39 
Molalla River at Ressel location, Oreg. (NPP) 37-39 
Moline, Ill. (NCR) 23-14 
Moline Harbor, Ill. (NCD) 25-7 
Monona-Harrison Ditch Control, Monona County, 
Iowa (MRO) 26-21 
Monongahela River, Granville, W. Va. (ORP) 18-26 
Monongahela River, Penn. and W. Va. (ORP) 18-2, 
18-11, 18-15, 18-24, 18-25 
Monongahela River, Pa. and W. Va. Locks and Dams 
(ORP) 18-23 
Monoosnoc Brook, Mass. (NED) 1-44, 1-51 
Monoosnoc Lake, Mass. (NED) 1-44, 1-51 
Monroe, La., floodwall extension (LMK) 12-17 
Monroe and West Monroe, La. and Ouachita Parish, 
La. (LMK) 12-11 
Monroe Bay and Creek, Va. (NAB) 4-37 
Monroe County, Fla. (SAJ) 9-41 
Monroe Floodwall, La. (LMK) 12-20 
Monroe Harbor, Mich. (NCE) 21-6, 21-30, 21-37, 
21-50 
Monroe Lake, Ind. (ORL) 16-8, 16-15 
Montcalm, W. Va. (ORH) 17-23 
Monterey Harbor, Calif. (SPN) 34-12 
Montgomery Locks and Dams, Pa. (ORD) 19-7 
Montgomery to Gadsden, Coosa River Channel, Ala. 
(SAM) 10-28 
Montour Falls, Oswego River Basin, N.Y. (NCB) 
20-37 
Moore Haven Lock, Fla. (SAJ) 9-49 
Moorefield, W. Va. (NAB) 4-40 
Moores Ferry, W. Va. (ORH) 17-21 
Moorhead, Minn. (NCS) 24-30 
Mooring for Battleship Oregon, Oreg. (NPP) 37-37 
Moosabec Bar, Maine (NED) 1-39 
Morehead City Harbor, N.C. (SAW) 6-7, 6-19, 6-28 
Morgan City and Below (MR+T) 42-13 
Morgan City and Vicinity, La. (LMN) 11-8, 11-11, 
11-14 
Morganza Floodway, La. (MR+T) 42-1, 42-13, 42-14 
Morganza-Morgan City (MR+T) 42-13 
Morganza Floodway between Mississippi River and 
Alabama Bayou (MR+T) 42-13 
Morganza-Old River, La. (MR+T) 42-11 
Moriches Inlet, N.Y. (NAN) 2-9, 2-23, 2-29 
Mormon Slough, Calif. (SPK) 35-34 
Morrison, Bear Creek, Colo. (MRO) 26-17 
Morrison Creek Beach Stone Lakes, Calif. (SPK) 
35-20 
Morristown Harbor, N.Y. (NCB) 20-35 
Morro Bay Harbor, Calif. (SPL) 33-2, 33-11, 33-18 
Moscow, Ohio (ORL) 16-21, 16-25 
Mosquito Creek Lake, Ohio River Basin, Ohio (ORP) 
18-7, 18-12, 18-17, 18-25 
Mosquito Creek Levee (MRO) 26-18 
Mosquito Keg Creek Levee (MRO) 26-18 
Moss Bluff Lock, Fla. (SAJ) 9-53 
Moss Landing Harbor, Calif. (SPN) 34-6 
Mott, N. Dak. (MRO) 26-16 
Mouth of Colorado River (SWG) 31-36 
Mound City Locks and Dam, Ill. (ORD) 19-10 
Mound State Park, Ala. (SAM) 10-39 
Mounds and Mound City, Ohio River Basin, Ill. 
(LMM) 13-5 
Moundsville, W. Va. (ORP) 18-21 
Moundville, Ala. (SAM) 10-28 
Mount Baldy, Indiana Dunes Nat'l. Lake Shore, Ind. 
(NCC) 22-17 
Mount Carmel, Ill. (Wabash River) (ORL) 16-19, 
16-29 
Mount Clemens, Clinton River, Mich. (NCE) 21-56 
Mount Clemens Spillway and Cutoff Canal, Clinton 
River, Mich. (NCE) 21-27 
Mount St. Helens and Vicinity, Wash. (NPP) 37-14, 
37-26, 37-34 
Mount St. Helens Sediment Control, Wash. (NPP) 
37-15, 37-26, 37-34 
Mountain Brook Dam, N.H. (NED) 1-44 
Mountain Pt., Ark. (NPA) 40-13 
1-44

INDEX 
Mouth of Yazoo River, Miss. (LMK) 12-15 
Mouth to Riparia (NPW) 39-14 
Moyock Creek, N.C. (SAW) 6-28 
Mt. Holly, N.J. (NAP) 3-26 
Mt. Morris Lake, N.Y., Genesee River (NCB) 20-14, 
20-21, 20-33 
Muckey Creek, Mapleton, Iowa (MRO) 26-23 
Mud and Basket Slough, Rickreall Creek, Oreg. 
(NPP) 37-41 
Mud Creek, Broken Bow, Nebr. (MRO) 26-16 
Mud Lake, Idaho (NPW) 39-16 
Mud Lake Pumping Station, Tenn. (MR+T) 42-30 
Mud Mountain Dam, Wash. (NAS) 38-8, 38-16, 38-21 
Mud River, W. Va. (ORH) 17-22 
Muddy Creek Dam, Pa. (ORP) 18-21 
Muddy Creek, Evans, N.Y. (NCB) 20-39 
Muddy Creek near Syracuse, Nebr. (MRO) 26-20 
Muddy Hook and Tyler Coves, Md. (NAB) 4-37, 4-41 
Mulberry Creek, Va. (NAO) 5-19 
Mullet Key, Fla. (SAJ) 9-48 
Multiple Purpose Projects Including Power 
Alaska District (NPA) 40-6 
Detroit, Mich., District (NCE) 21-56 
Fort Worth, Tex., District (SWF) 30-11 
Kansas City, Mo., District (MRK) 27-8 
Little Rock, Ark., District (SWL) 28-8 
Mobile, Ala., District (SAM) 10-20, 10-45, 10-51 
Nashville, Tenn., District (ORN) 15-6, 15-14 
New England Division (NED) 1-43 
Omaha, Nebr., District (MRO) 26-17 
Philadelphia, Penn., District (NAP) 3-27 
Portland, Oreg., District (NPP) 37-16, 37-40 
Sacramento, Calif., District (SPK) 35-21 
Seattle, Wash., District (NPS) 38-10, 38-28 
St. Louis, Mo., District (LMS) 14-6 
Tulsa, Okla., District (SWT) 29-8 
Walla Walla, Wash., District (NPW) 29-4 
Wilmington, N.C., District (SAW) 6-14 
Multnomah Channel, Oreg. (NPP) 37-38, 37-44 
Multnomah Drainage District 1, Oreg. (NPP) 37-37, 
37-39 
Muncie, Ind. (ORL) 16-19, 16-29 
Munday Floodway, Tex. (SWF) 30-22 
Murder and Burnt Corn Creeks, Brewton, Ala. 
(SAM) 10-16, 10-34, 10-44, 10-48 
Murder Creek, East Brewton, Ala. (SAM) 10-48 
Murderkill River, Del. (NAP) 3-8, 3-16, 3-20, 3-24 
Murfreesboro Dam and Lake (LMK) 12-20 
Murray County Bridge, Okla. (SWT) 29-21 
Murray Lock and Dam No. 7, Ark. (SWL) 28-3, 28-19 
Murrells Inlet, S.C. (SAN) 7-5, 7-9, 7-12 
Muscatatuck River, Crothersville, Ind. (ORL) 16-30 
Muscatine, Iowa (Mad Creek) (NCR) 23-13 
Muscatine Harbor, Iowa (NCD) (NCR) 23-12, 25-7, 
25-10 
Muscatine Island, Iowa (NCR) 23-8 
Muscatine Island Levee District and Muscatine Louisa 
County Drainage District No. 13, Iowa (NCR) 
23-12, 23-13, 23-16 
Muscooten Bay, Ill. (NCR) 23-12 
Muskegon Harbor, Mich. (NCE) 21-17, 21-37, 21-50 
Muskingum River, Ohio (ORH) 17-20 
Muskingum River Dams and Lakes Ohio (ORH) 
17-14 
Muskingum River Lakes, Ohio (ORH) 17-6, 17-18 
Muskogee, Okla. (SWT) 29-21 
Mustinka River, Minn. (NCS) 24-32, 24-33 
Myers Chuck Harbor, Alaska (NPA) 40-12 
Myrtle Beach, S.C. (SAN) 7-17 
Mystic, Conn. (NED) 1-44 
Mystic River, Conn. (NED) 1-39, 1-44, 1-53 
Mystic River, Mass. (NED) 1-39 
N 
Naches River, Naches, Wash. (NPS) 38-26 
Nagel Drainage District, Little Sioux River, Iowa 
(MRO) 26-20 
Nags Head, N.C. (SAW) 6-31 
Nahunta Swamp, N.C. (SAW) 6-28 
Naknek River, Alaska (NPA) 40-12 
Namo River, Guam (POD) 36-12, 36-15 
Nan Cove, Md. (NAB) 4-37 
Nandua Creek, Va. (NAO) 5-19 
Nanpil River Hydropower, Pohnpei, Trust Territory 
of the Pacific Islands (POD) 36-5, 36-8, 36-9 
Nansemond River, Va. (NAO) 5-19, 5-21 
Nantasket Beach, Mass. (NED) 1-41 
Nanticoke River, Md. (NAB) 4-37 
Nanticoke River at Bivalve, Md. (NAB) 4-37 
Nanticoke River (including Northwest Fork), Del. 
and Md. (NAB) 4-37 
Nantucket (Harbor of Refuge), Mass. (NED) 1-39, 
1-44 
Nantucket Inner Harbor-Polpis, Mass. (NED) 1-46 
I-45

Napa River, Calif. (SPN) 34-6 
Napa River Basin, Calif. (SPK) 35-34 
Napatree Beach, R.I. (NED) 1-44 
Naquako River, P.R. (SAJ) 9-54 
Narragansett Pier, R.I. (NED) 1-44 
Narraguagus River, Maine (NED) 1-39 
Narrows Dam-Lake Greeson, Ark. (LMK) 12-17, 
12-20 
Narrows of Lake Champlain, N.Y. and Vt. (NAN) 2-9, 
2-23, 2-29, 2-33 
Nashua, N.H. (NED) 1-23, 1-42, 1-51 
Nasketucket Harbor, Fairhaven, Mass., (NED) 1-46 
Natchez Port Area, Miss. (LMK) 12-20 
Natchitoches Parish, La. (LMN) (LMK) 11-18, 12-19, 
12-20 
Nation Levee, Kan. (SWT) 29-21 
National Emergency Preparedness Activities (NAP) 
(NCB) (NCC) (NCE) (MRO) (SAM) (SWG) 3-14, 
10-27, 20-15, 21-9, 22-5, 26-8, 31-14, 51-1, 51-2 
Natural Disaster Preparedness, Response and 
Recovery Activities 52-1, 52-2 
Navajo Reservoir, N. Mex. (SPK) 35-33 
Navarro Mills Lake, Tex. (SWF) 30-8, 30-16, 30-20 
Navasota Lake, Tex. (SWF) 30-22 
Navigation Activities (NED) 1-47 
Navigation Data Center 47-1 
Navigation Locks and Dams, Ark. (SWL) 28-11 
Navigation Studies (NCB) 20-16 
Navigation Work Under Special Authorization 
Alaska District (NPA) 40-13 
Baltimore, Md., District (NAB) 4-12 
Buffalo, N.Y., District (NCB) 20-11, 20-38 
Charleston, S.C., District (SAN) 7-6, 7-14 
Detroit, Mich., District (NCE) 21-25 
Jacksonville, Fla., District (SAJ) 9-18 
Little Rock, Ark., District (SWL) 28-4 
Louisville, Ky., District (ORL) 16-3 
Memphis, Tenn., District (LMM) 13-1 
Mobile, Ala., District (SAM) 10-14, 10-49 
Nashville, Tenn., District (ORN) 15-4 
New Orleans District (LMN) 11-5, 11-17 
New York District (NAN) 2-16 
Norfolk, Va., District (NAO) 5-7, 5-13 
Pacific Ocean Division (POD) 36-3 
Philadelphia, Penn., District (NAP) 3-8 
Portland, Oreg., District (NPP) 37-6 
Savannah, Ga., District (SAS) 8-6 
Seattle, Wash., District (NPS) 38-4 
St. Louis, Mo., District (LMS) 14-6 
Vicksburg, Miss., District (LMK) 12-3 
Walla Walla, Wash., District (NPW) 39-1, 39-14 
Wilmington, N.C., District (SAW) 6-29 
Nawiliwili Harbor, Kauai, Hawaii (POD) 36-10 
Nawiliwili Small Boat Harbor, Kauai, Hawaii (POD) 
36-10 
NCD Master Plan for Water Control Data System 
(NCE) 21-29 
Neabsco Creek, Md. (NAB) 4-37 
Neah Bay, Wash. (NPS) 38-24 
Neale Sound, Md. (NAB) 4-7, 4-25, 4-33 
Near Dardanelle, Arkansas River, Ark. (SWL) 18-27 
Near Island Channel (NPA) 40-14 
Near Mud Lake, Tenn. (MR+T) 42-12 
Near Springfield on Sangamon River, Ill. (NCR) 
23-13 
Neavitt Harbor, Md. (NAB) 4-37 
Nebraska City Levee (MRO) 26-18 
Neches River and Tributaries, Salt Water Barrier at 
Beaumont, Tex. (SWG) 31-30 
Needles, San Bernardino, Co., Calif. (SPL) 33-25 
Nehalem Bay, Oreg. (NPP) 37-37, 37-42 
Neodesha Lake, Kan. (SWL) (SWT) 28-22, 29-19, 
29-20 
Neon-Fleming, Ky. (Kentucky River) (ORL) 16-19, 
16-30 
Neshaminy State Park Harbor, Pa. (NAP) 3-24 
Neshannock Creek, New Castle, Penn. (ORP) 18-26 
Nestucca River, Oreg. (NPP) 37-37, 37-39 
Neuse River, N.C. (SAW) 6-12, 6-25, 6-28 
Neuse River Barrier, N.C. (SAW) 6-28, 6-30 
Neuse River, 300 foot-wide channel in front of New 
Bern, N.C. (SAW) 6-28 
Neuse River, Oriental, N.C. (SAW) 6-31 
Neva and Olga Straits, Alaska (NPA) 40-12 
Neville Island, Pa. (ORP) 18-21 
New Albany, Ind. (ORL) 16-19, 16-24, 16-29 
New Amsterdam, Ind. (ORL) 16-21, 16-25 
New Bedford and Fairhaven Harbors, Mass. (NED) 
1-39, 1-44 
New Bedford, Fairhaven, and Acusmhnet, Mass. 
(NED) 1-19, 1-30, 1-36 
New Bedford-Fairhaven Hunicane Barrier, Mass. 
(NED) 1-23 
New Boston Harbor, Ill. (NCD) 25-7 
I-46

INDEX 
New Buffalo Harbor, Mich. (NCE) 21-17, 21-37, 
21-50 
New Bullards Bar, Calif. (SPK) 35-34 
New Cumberland, W. Va. (ORP) 18-21 
New Cumberland Locks and Dam, Stratton, Ohio 
(ORD) 19-7 
New Fairfield, Conn. (NED) 1-23 
New Harbor, Maine (NED) 1-39 
New Harmony, Ind. (ORL) 16-21 
New Harmony Bridge, Ill. and Ind. (Wabash River) 
(ORL) 16-19, 16-20, 16-24, 16-25 
New Haven Breakwater, Conn. (NED) 1-39 
New Haven Harbor, Conn. (NED) 1-5, 1-26, 1-34, 
1-44 
New Jersey Intracoastal Waterway (NAP) 3-8, 3-16, 
3-20 
New Kensington and Parnassus, Pa. (ORP) 18-21 
New London, Conn. (NED) 1-19, 1-23, 1-31, 1-36 
New London Harbor, Conn. (NED) 1-39, 1-46 
New London Hurricane Barrier (NED) 1-23 
New Madrid-Birds Pt., Mo. (MR+T) 42-12 
New Madrid Floodway, Mo. (MR+T) 42-12 
New Madrid Harbor, Mo. (LMM) 13-4 
New Martinsville, W. Va. (ORH) 17-22 
New Matamoras, Ohio (ORH) 17-22 
New Melones Lake, Calif. (SPK) 35-21 
New Orleans, La. (MR+T) 42-11, 42-31 
New Orleans-Baton Rouge, La. (MR+T) 42-11 
New Orleans District, Bank Revetments and Dikes, 
Atchafalaya River (MR+T) 42-34 
New Orleans District, Bank Revetments and Dikes, 
Mississippi River (MR+T) 42-32 
New Orleans District, Levees (MR+T) 42-46, 42-62 
New Orleans District, Channel Improvements (MR+T) 
42-52 
New Orleans-Morganza, La. (MR+T) 42-11 
New Orleans to Venice, La., Hurricane Protection 
(LMN) 11-8, 11-14, 
New Pass, Sarasota, Fla. (SAJ) 9-11, 9-28, 9-35, 9-46 
New Richmond, Ohio (ORL) 16-21, 16-25 
New River, Fla. (SAJ) 9-47 
New River, N.C. (SAW) 6-27 
New River, Va. and W. Va. (ORH) 17-20 
New River Inlet, N.C. (SAW) 6-29 
New Rochelle Harbor, N.Y. (NAN) 2-34 
New York and New Jersey Channels, (NAN) 2-10, 
2-24, 2-30, 2-33, 2-38 
New York Harbor, N.Y. (NAN) 2-33 
New York Harbor-Collection and Removal of Drift 
(NAN) 2-11, 2-24, 2-30 
New York Harbor-Entrance Channels and 
Anchorage Areas (NAN) 2-12, 2-24, 2-30 
New York State Barge Canal (NAN) (NCB) 2-13, 
20-8, 20-19, 20-30 
Newark, Ohio (ORH) 17-5, 17-14, 17-18, 17-21, 
17-23 
Newark Bay, Hackensack and Passaic Rivers, N.J. 
(NAN) 2-10, 2-24, 2-29, 2-33, 2-37 
Newaukum River, Wash. (NPS) 38-26 
Newbegun Creek, N.C. (SAW) 6-25 
Newburgh, Ind. (Ohio River) (ORL) 16-19 
Newburgh Locks and Dam, Ind. (ORD) 19-9 
Newbury Neck, Surry, Me. (NED) 1-24 
Newburyport Harbor, Mass. (NED) 1-6, 1-26, 1-34, 
1-44 
Newmarket Creek, Va. (NAO) 5-20 
Newport, White River, Ark. (SWL) 28-17 
Newport, Ky. (ORL) 16-19, 16-24, 16-29 
Newport-Wilder, Ky. (ORL) 16-20 
Newport, Ohio (ORH) 17-22 
Newport Bay Harbor, Calif. (SPL) 33-23, 33-28 
Newport Harbor, R.I. (NED) 1-39 
Newport News, Va. (NAO) 5-20 
Newport News Creek, Va. (NAO) 5-19, 5-21 
Newport-Wider, Ky. (ORL) 16-20 
Newry-Old Pickens Dam and Lake, S.C. (SAS) 8-16 
Newt Graham Lock and Dam, Okla. (SWL) (SWT) 
28-21, 29-20 
Newtown Creek, N.Y. (NAN) 2-33, 2-34 
Niagara Remedial Works, N.Y. (NCB) 20-35 
Niagara River, N.Y. (NCB) 20-35 
Niagara River, Compensating Works, N.Y. (NCB) 
20-40 
Niantic Bay and Harbor, Conn. (NED) 1-39 
Niblack, Mason J., Levee, Wabash River, Ind. (ORL) 
16-19, 16-29 
Nicholasville, (Townfork) Vicinity, Ky. (ORL) 16-30 
Nichols, N.Y. (NAB) 4-39, 4-42 
Nickajack Lock, Tenn. (ORN) 15-17 
Nimrod Lake, Ark. (SWL) 28-7, 28-12, 28-22 
Ninilchik Harbor, Alaska (NPA) 40-3, 40-8, 40-10 
Niobrara River, (Carnes Bridge) Nebr. (MRO) 26-23 
Nishnabotna River at Hamburg, Iowa (MRO) 26-16 
Nisqually River, Wash. (NPS) 38-26 
I-47

Nixon Creek, Tenn. (LMM) 13-5 
Noank Harbor, Groton, Conn. (NED) 1-46 
Nolin Lake, Ky. (ORL) 16-9, 16-15 
Nome Harbor, Alaska (NPA) 40-3, 40-8, 40-11 
Nomini Bay and Creek, Va. (NAB) 4-37 
Nonconnah Blvd., Nonconnah Creek, Tenn. (LMM) 
13-5 
Nonconnah Creek (MR+T) 42-30 
Nonconnah Creek, Interceptor Sewer, Memphis, 
Tenn. (LMM) 13-5 
Nonewaug River, Conn. (NED) 1-42 
Nookagee Lake, Mass. (NED) 1-44 
Nooksack River, Wash. (NPS) 38-26, 38-29 
Norfolk, Nebr. (MRO) 26-16 
Norfolk Floodwall, Va. (NAO) 5-20 
Norfolk Harbor, Va. (NAO) 5-12, 5-16, 5-21 
Norfolk Harbor and Channels (Deepening) (NAO) 
5-4, 5-12, 5-16 
Norfolk Harbor Channels, Va. (NAO) 5-5 
Norfolk, North Fork, Elkhorn River, Nebr. (MRO) 
26-20 
Norfork Lake, Ark. (SWL) 28-9, 28-13, 28-24 
Normal, Ky. (ORH) 17-21 
Norrell Lock and Dam (No. 1) - Entrance Channel, 
Ark. (SWL) 28-4, 28-19 
North Adams, Hoosic River Basin, Mass. (NAN) 
2-36 
North Alexander Drainage and Levee District, Ill. 
(LMS) 14-15 
North Andover and Lawrence, Mass. (NED) 1-44 
North Branch, Chicago River, Ill. (NCC) 22-7, 22-14 
North Branch of Kokosing River Lake, Ohio (ORH) 
17-7, 17-14, 17-18 
North Branch Reservoir Chicago River, Ind. (NCC) 
22-11 
North Canaan, Conn. (NED) 1-23, 1-42, 1-50 
North Canadian River, Okla. (SWT) 29-21 
North Chicago, Ill. (NCC) 22-6 
North Edisto River, S.C. (SAN) 7-14 
North Ellenville, N.Y. (NAN) 2-36 
North Fork Gunnison River, Paonia, Co. (SPK) 35-40 
North Fork of Pound River Lake, Va. (ORH) 17-8, 
17-14, 17-18 
North Fork, Pit River at Alturas, Calif. (SPK) 35-34 
North Fork Skykomish River, Wash. (NPS) 38-26 
North Hampton Beach, North Hampton, N.H. (NED) 
1-44 
North Hartland Lake, Vt. (NED) 1-14, 1-23, 1-28. 
1-48 
North Little Rock, Arkansas River, Ark. (SWL) 28-17 
North Nantasket Beach, Hull, Mass. (NED) 1-46 
North Nashua River, Fitchburg, Mass. (NED) 1-24, 
1-42 
North Nashua River, Lancaster, Mass. (NED) 1-42, 
1-51 
North Pease River Bridge 655, Okla. (SWT) 29-21 
North Platte River, Bank Stabilization, Minatare, 
Nebr. (MRO) 26-20 
North River Dike, N.C. (SAW) 6-28 
North River, Klein Bridge, Mo. (NCR) 23-17 
North River, Marion County, Mo. (NCR) 23-17 
North Sandy Pond, Oswego Co., N.Y. (NCB) 20-38 
North Scenic Rd., Buffalo Twp, Penn. (ORP) 18-26 
North Scituate Beach, Scituate, Mass. (NED) 1-41 
North Second St., Memphis, Tenn. (Wolf River 
Bridge) (LMM) 13-5 
North Shore of Long Island, Suffolk County, N.Y. 
(NAN) 2-36 
North Springfield Lake, Vt. (NED) 1-14, 1-28, 1-48 
North Stratford, N.H. (NED) 1-23, 1-49 
North Wildwood, N.J. (NAP) 3-26 
Northampton, Mass. (NED) 1-23, 1-42, 1-49 
Northeast (Cape Fear) River, N.C. (SAW) 6-25, 6-27 
Northeast Harbor, Maine, (NED) 1-39, 1-46 
Northeast River, Md. (NAB) 4-37 
Northfield, Ill. (NCC) 22-8 
Northfield Brook Lake, Conn. (NED) 1-17, 1-30, 1-50 
Northport Harbor, Mich. (NCE) 21-55 
Northport Harbor, N.Y. (NAN) 2-34 
Norwalk, Conn. (NED) 1-23, 1-42 
Norwalk Harbor, Conn. (NED) 1-39 
Norwalk-Wilton, Conn. (NED) 1-44 
Norwich, Conn. (NED) 1-42, 1-52 
Norwich, N.Y. (NAB) 4-39, 4-42 
Nottoway River, Va. (NAO) 5-19 
Nowood River, Manderson, Wyo. (MRO) 26-33 
Noxubee River, Miss. (SAM) 10-47 
Noxubee River Relief Bridge, Shuqualak, Miss. 
(SAM) 10-6, 10-34, 10-44 
Noyo River and Harbor, Calif. (SPN) 34-5, 34-6 
Nua-Amaluia, Tutuila Island, American Samoa (POD) 
36-14 
Nutwood Drainage and Levee District, Ill. (LMS) 
14-5, 14-8, 14-11 
1-48

INDEX 
O 
O.C. Fisher Dam and Lake, Tex. (SWF) 30-8, 30-16, 
30-20 
Oahe Dam-Lake Oahe, Missouri River Basin, S. Dak. 
and N. Dak. (MRO) 26-8, 26-11, 26-15, 26-18 
Oak Bluffs Harbor, Oak Bluffs, Mass. (NED) 1-46 
Oak Bluffs Town Beach, Mass. (NED) 1-41 
Oak Orchard Harbor, N.Y. (NCB) 20-8, 20-19, 20-30 
Oakdale, Pa. (ORP) 18-20 
Oakford Special Drainage District (NCR) 23-13, 
23-15 
Oakland, Iowa (MRO) 26-23 
Oakland Beach, Warwick, R.I. (NED) 1-41 
Oakland Harbor, Calif. (SPN) 34-1, 34-6, 34-10, 
34-13 
Oates Creek, Ga. (SAS) 8-16 
Obey River, Tenn. (ORN) 15-13 
Obion River, Tenn. (LMM) 13-4 
Occohannock Creek, Va. (NAO) 5-19 
Occoquan Creek, Va. (NAB) 4-37, 4-41 
Ocean City, N.J. (NAP) 3-26 
Ocean City Harbor and Inlet and Sinepuxent Bay, 
Md. (NAB) 4-5, 4-8, 4-33 
Ocean Grove Beach, Swansea, Mass. (NED) 1-46 
Ocean Springs Harbor, Miss. (SAM) 10-49 
Oceana, W. Va. (ORH) 17-21 
Oceanside, Calif. (SPL) 33-24 
Oceanside Beach, Calif. (SPL) 33-24 
Oceanside Harbor, Calif. (SPL) 33-3, 33-11, 33-18 
Ocholockonee (Ochlockney) River, Ga. and Fla. 
(SAM) 10-47 
Oconto Harbor, Wis. (NCE) 21-55, 21-60 
Ocracoke Inlet, N.C. (SAW) 6-8, 6-19 
Ocracoke Inlet Jetty, N.C. (SAW) 6-28 
Ocracoke Island, N.C. (SAW) 6-28 
Oelwein, Fayette County, Iowa 23-17 
Offats Bayou (SWG) 31-36 
Ofu Airstrip, American Samoa (POD) 36-11 
Ofu Small Boat Harbor, American Samoa (POD) 
36-10 
Ogdensburg Harbor, N.Y. (NCB) 20-35, 20-40 
O'Hare Reservoir, Ill. (NCC) 22-8, 22-11, 22-14 
Ohio River, Ill. and Ky. (ORL) (MR+T) 16-30, 16-31, 
42-19 
Ohio River, Ind. (ORL) 16-31 
Ohio River Basin (ORH) (ORL) 16-24, 16-25, 16-26, 
17-14 
Ohio River Basin (Huntington District) (ORH) 17-8 
Ohio River Basin (Louisville Dist.) (ORL) 16-9, 
16-15, 16-17 
Ohio River Basin (Nashville District) (ORN) 15-6, 
15-12, 15-18 
Ohio River Basin (Pittsburgh District) (ORP) 18-7, 
18-12, 18-17, 18-24, 18-25 
Ohio River, Locks and Dams (ORD) 19-6, 19-7 
Ohio River, McMechen, W. Va. (ORP) 18-26 
Ohio River, River Ave., Chester, W. Va. (ORP) 18-26 
Oil City, Pa. (ORP) 18-20 
Okabena Creek at Worthington, Minn. (NCR) 23-13 
Okanogan and Pend Oreille Rivers (NPS) 38-24 
Okanogan River, Wash. (NPS) 38-26, 38-29 
Okanogan River, Omak, Wash. (NPS) 38-26 
Okanogan River, Oroville, Wash. (NPS) 38-26 
Okatibbee Dam, Miss. (SAM) 10-34 
Okatibbee Lake, Miss. (SAM) 10-16, 10-44 
Okeechobee Waterway, Fla. (SAJ) 9-11, 9-28, 9-35, 
9-45, 9-46, 9-48 
Oklahoma City Floodway, Okla. (SWT) 29-19 
Oklawaha River, Fla. (SAJ) 9-12, 9-28, 9-36, 19-46 
Olcott Harbor, N.Y. (NCB) 20-8, 20-19, 20-30 
Old Field Swamp, N.C. (SAW) 6-27 
Old Harbor (Kodiak) Alas. (NPA) 40-14 
Old Harbor, Kodiak Island, Alas. (NPA) 40-12 
Old Hickory Lock and Dam, Tenn. (ORN) 15-14 
Old Highway 82 Bridge, Columbus, Miss. (SAM) 
10-48 
Old River, Calif. (SPK) 35-33 
Old River, La. (MR+T) 42-6, 42-30 
Old River, La. control (MR+T) 42-11 
Old River, Standard Revetments (MR+T) 42-33 
Old River-Cypress Creek, Ark. (MR+T) 42-11 
Old Town Creek, Miss. (SAM) 10-47 
Oldmans Creek, NJ. (NAP) 3-27 
Olean, N.Y. (ORP) 18-20 
Olean, N.Y. (Allegheny River) (ORP) 18-24 
Olinda Trail, Chisago Lakes Township, Minn. (NCS) 
24-34 
Olive Hill, Ky. (ORH) 17-23 
Oliver Lock and Dam (Replacement), Ala. (SAM) 
10-6, 10-31, 10-39 
Olosega Bridge Protection, American Samoa (POD) 
36-14 
Olympia Harbor, Wash. (NPS) 38-4, 38,-15, 38-20, 
38-29 
Omaha, Missouri River, Nebr. (MRO) 26-20 
I-49

Omaha, Nebr. (MRO) 26-16, 26-18 
Onaga Lake, Vermillion Creek, Kan. (MRK) 27-17 
Onandaga Creek, Nedrow, N.Y. (NCB) 20-37 
Onancock River, Va. (NAO) 5-19, 5-21 
Oneida Creek, Oneida, N.Y. (NCB) 20-39 
Oneida Lake, N.Y. (NCB) 20-39 
Oneonta, N.Y. (NAB) 4-42 
Ontonagon Harbor, Mich. (NCE) 21-17, 21-38, 21-50 
Oologah Lake, Okla. (SWL) (SWT) 28-22, 29-6, 
29-14, 29-17, 29-20 
Oostanaula and Coosawatee River, Ga. (SAM) 10-47 
Open Channel Work, Ohio River (ORD) (ORH) 
(ORL) (ORP) 16-3, 17-2, 18-3, 19-3, 19-5, 19-6 
Open River Lewiston to Johnson Bar Landing 
(NPW) 39-22 
Open River Navigation Riparia to Pittsburg Landing 
(NPW) 39-14 
Open River Pasco to Lewiston (NPW) 39-22 
Opposite Hamburg Harbor, Ill. (NCD) 25-10 
Optima Lake, Okla. (SWT) 29-7, 29-14, 29-17 
Oquawka, Mississippi River, Ill. (NCR) 23-17 
Orange River, Fla. (SAJ) 9-47 
Orange Road, Mercer Co., Penn. (ORP) 18-26 
Oregon Slough (North Portland Harbor), Oreg. (NPP) 
37-37 
Orleans, Ind. (ORL) 16-21 
Ormond, Arthur V. L and D (SWL) 28-19 
Oro Grande Wash Channel Improvements, Calif. 
(SPL) 33-25 
Orofino Creek and Clearwater River, Idaho (NPW) 
39-15 
Orowoc Creek, N.Y. (NAN) 2-34 
Orwell Reservoir (Otter Tail River) (NCS) 24-32 
Osage River, Kan. and Mo. (MRK) 27-19 
Osage River, Mo., Lock and Dam (MRK) 27-15 
Osawatomie, Osage (Marais des Cygnes) River, Kan. 
(MRK) 27-19 
Osawatomie, Pottawatomie Creek, Kan. (MRK) 
27-16 
Osborne Creek, Highway 362 Bridge, Prentiss 
County, Miss. (SAM) 10-48 
Osceola Harbor, Ark. (LMM) 13-4 
Oswego Harbor, N.Y. (NCB) 20-9, 20-19, 20-30, 
20-40 
Other Work under Special Authority (NCS) (SPK) 
24-20, 35-23 
Ottowa, Ill. (NCR) 23-17 
Ottawa, Ohio (NCB) 20-14, 20-21, 20-33 
Ottowa Osage (Marais des Cygnes) River, Kan. 
(MRK) 27-16, 27-19 
Ottawa River Harbor, Mich. and Ohio (NCB) 20-35 
Otter Brook Lake, N.H. (NED) 1-15, 1-23, 1-28, 1-48 
Otter County Drainage District No. 2 (MRO) 26-18 
Otter Creek, Vt. (NAN) 2-34 
Otter Creek and Tributaries, Shannon Hills, Ark. 
(SWL) 28-17 
Otter Tail River, Minn. (NCS) 24-32, 24-33 
Ottumwa, Iowa (NCR) 23-13 
Ouachita and Black Rivers, Ark. and La. (Felsenthal 
Canal) (LMK) 12-15 
Ouachita and Black Rivers, Ark. and La., Locks and 
Dams (LMK) 12-14 
Ouachita and Black Rivers below Camden, Ark. 
(LMK) 12-2, 12-9, 12-11 
Ouachita River (MR+T) 42-15 
Ouachita River and Tributaries, Ark. and La. (LMK) 
12-5, 12-12, 12-17 
Ouachita River Levees, La. (LMK) 12-4, 12-9, 12-17 
Ouzinkie Small Boat Harbor, Alaska (NPA) 40-13 
Overton-Red River Waterway, La. (LMK) 12-15 
Owasco Inlet and Outlet, Montville and Dry Creek, 
State Ditch and Crane Brook, N.Y. (NCB) 20-37 
Owasco Inlet, Groton, N.Y. (NCB) 20-39 
Owego, N.Y. (NAB) 4-42 
Owen, Wis. (NCS) 24-34 
Owensboro, Ky. (ORL) 16-20, 16-24 
Owl's Head Harbor, Maine (NED) 1-39 
Owyhee River, Oreg. (NPW) 39-4, 39-9, 39-13 
Oxford, Md. (NAB) 4-38 
Oxford, N.Y. (NAB) 4-17, 4-28 
Oxford Junction, Wapsi River, Iowa (NCR) 23-17 
Oyster Channel, Va. (NAO) 5-19, 5-21 
Oyster Creek, Tex. (SWG) 31-30 
Ozan Creek, Ark. (LMIK) 12-7 
Ozark-Jeta Taylor Lock and Dam (No. 12), Ark. 
(SWL) 28-9, 28-13, 28-20 
Ozark Natl. Rec. Area, Bell Foley and Greers Ferry 
(SWL) 28-18 
Ozona, Channel and Turning Basin, Fla. (SAJ) 9-47 
P 
Paauau Stream, Hawaii (POD) 36-12, 36-15 
Paducah, Ky. (ORL) 16-19, 16-24, 16-29 
Pagan River, Va. (NAO) 5-19 
Pago Pago Airport, American Samoa (POD) 36-11 
I-50

INDEX 
Pago Pago to Nuuuli, American Samoa (POD) 36-11 
Paint Creek at Chillicothe, Ohio (ORH) 17-23 
Paint Creek at Washington Court House, Ohio 
(ORH) 17-23 
Paint Creek Lake, Ohio River Basin, Ohio (ORH) 
17-8, 17-14, 17-19 
Paint Rock River, Ala. (ORN) 15-13, 15-19 
Painted Post, N.Y. (NAB) 4-39, 4-42 
Painted Rock Dam, Ariz. (SPL) 33-5, 33-20 
Paintsville Lake, Ky. (ORH) 17-8, 17-14, 17-19 
Pajaro River, Calif. (SPK) 35-13 
Pajaro River Basin, Calif. (SPK) 35-26 
Palm Beach, side channel and basin 9-47 
Palm Beach County, Fla. (SAJ) 9-20 
Palm Beach County, Fla., from Lake Worth Inlet to 
South Lake Worth Inlet (SAJ) 9-8 
Palm Beach County, Fla., from Martin County Line 
of Lake Worth Inlet and from South Lake Worth 
Inlet to Broward County Line (SAJ) 9-30, 9-41 
Palm Beach Harbor, Fla. (SAJ) 9-12, 9-28, 9-36 
Palmer River, Swansea, Mass. (NED) 1-47 
Paloa Area, American Samoa (POD) 36-11 
Palouse River, Wash. (NPW) 39-12, 39-16, 39-17 
Pamlico and Tar Rivers, N.C. (SAW) 6-8, 6-19 
Pamunkey River, Va. (NAO) 5-19 
Panacea Harbor, Fla. (SAM) 10-47, 10-50 
Panama City Beaches, Fla. (SAM) 10-28, 10-42 
Panama City Harbor, Fla. (SAM) 10-11, 10-32, 10-42, 
10-50 
Pantego Creek and Cucklers Creek, N.C. (SAW) 6-27 
Panther Creek, Curdsville, Ky. (Green River) (ORL) 
16-19, 16-30 
Panther Creek, Sangamon River, Chandlerville, Ill. 
(NCR) 23-17 
Panther Creek, W. Va. (ORH) 17-21 
Paper Mill Creek, Pt. Reyes Station, Calif. (SPK) 
35-40 
Papillion Creek and Tributaries Lakes, Nebr. (MRO) 
26-5, 26-10, 26-13 
Papillion Creek-Platte River Levee (MRO) 26-18 
Parceles Figueroa, P.R. (SAJ) 9-54 
Parish Creek, Md. (NAB) 4-8, 4-25, 4-33 
Park City, Kan. (SWT) 29-20 
Park River, Hartford, Conn. (NED) 1-42, 1-49 
Park River, N. Dak. (NCS) 24-33 
Parker Creek, Va. (NAO) 5-19, 5-21 
Parker Lake, Okla. (SWT) 29-7, 29-14, 29-17 
Parkersburg, W. Va. (ORH) 17-21, 17-23 
Parrotts Creek, Va. (NAO) 5-19 
Parsons, Hambleton, Hendricks, W. Va. (ORP) 18-26 
Pascack Brook, N.J. (NAN) 2-39 
Pascagoula Harbor, Miss. (SAM) 10-11, 10-33, 10-42 
Pascagoula River, Miss. (SAM) 10-27, 10-47 
Pasquotank River, N.C. (SAW) 6-27 
Pass Christian, Miss. (SAM) 10-50 
Pass Christian Harbor, Miss. (SAM) 10-47 
Pass Manchac, La. (LMN) 11-17 
Pass-a-Grille Pass, Fla. (SAJ) 9-47 
Passaic River Basin, NJ. and N.Y., Phase I (NAN) 
2-20, 2-31, 2-39 
Passamaquoddy Tidal Power Project, Me. (NED) 1-43 
Pat Mayse Lake, Tex. (SWT) 29-7, 29-14, 29-17 
Pataha Creek, Pomeroy, Wash. (NPW) 39-15 
Patchogue River, Conn. (NED) 1-39 
Patman, Wright, Dam and Lake, Tex. (LMN) (SVT) 
11-19, 30-11, 30-17, 30-21 
Patoka Lake, Ind. (ORL) 16-9, 16-15, 16-27 
Patoka River, Ind. (ORL) 16-30 
Patriot, Ind. (ORL) 16-21, 16-25 
Patterson (MR+T) 42-13 
Pattonsburg Lake, Grand River, Mo. (MRK) 27-16 
Patuxent River, Md. (NAB) 4-37 
Pauls Valley, Okla. (SWT) 29-21 
Paw Paw Lake, Mich. (NCE) 21-26, 21-41, 21-53 
Pawcatuck, Conn. (NED) 1-23, 1-42 
Pawcatuck Hurricane Barrier 1-23 
Pawcatuck River, Little Narragansett Bay, R. I. and 
Conn. (NED) 1-45 
Pawcatuck River, R.I. and Conn. (NED) 1-39, 1-45 
Pawtucket, R.I. (NED) 1-45 
Pawtuxet Cove, R.I. (NED) 1-39 
Pawtuxet River, Warwick, R.I. (NED) 1-42, 1-48 
Pax, W. Va. (ORH) 17-23 
Payette River, Emmett Sewage Lagoon, Idaho (NPW) 
39-15, 39-17 
Payette Valley, Idaho (NPW) 39-12, 39-16 
Peacock Creek, Liberty County, Ga. (SAS) 8-16 
Peafield, Miss. (MR+T) 42-12 
Pearl River, Jackson East, Jackson, Miss. (LMK) 
12-20 
Pearl River, Miss. and La. (LMK) 12-12, 12-15, 12-21 
Pearl River Basin, Miss. and La. (LMK) 12-5 
Pearl River Basin, Shoccoe Dam, Miss. (LMK) 12-12 
Pearl River, Slidell, St. Tammany Parish, La. (LMK) 
12-6, 12-9, 12-12 
Pearl River Vicinity of Jackson (LMK) 12-9 
I-51

Pearson-Skubitz Big Hill Lake, Kan. (SWT) 29-7, 
29-14, 29-17 
Pebble Creek, Scribner, Nebr. (MRO) 26-5, 26-10, 
26-13, 26-23 
Pecan Creek, Gainesville, Tex. (SWF) 30-23 
Pecatonica River at Darlington, Wis. (NCR) 23-15 
Peconic River, N.Y. (NAN) 2-34 
Pecos, Tex. (SWA) 32-14 
Peekskill Harbor, N.Y. (NAN) 2-34 
Pekin-LaMarsh Drainage and Levee District, Ill. 
(NCR) 23-13, 23-16 
Pelican Harbor, Alaska (NPA) 40-12 
Pembina River, N. Dak. (NCS) 24-28 
Pembina River Lake, N. Dak. (NCS) 24-28 
Pembroke Creek, N.C. (SAW) 6-25 
Pemigewasset River, Holderness, N.H, (NED) 1-47 
Pendleton, Oreg. (NPP) 37-40 
Pendleton Levees, Oreg. (NPP) 37-39, 37-41 
Peninsula Drainage District 1, Oreg. (NPP) 37-38, 
37-41, 37-43 
Peninsula Drainage District 2, Oreg. (NPP) 37-39, 
37-44 
Penny Slough, Ill. (NCR) 23-13, 23-16 
Penobscot River, Me. (NED) 1-39, 1-42, 1-53 
Pensacola Bay, Fla. to Mobile Bay, Ala. (SAM) 10-40 
Pensacola Harbor, Fla. (SAM) 10-12, 10-33, 10-43, 
10-50 
Pensacola Harbor Modification, Fla. (SAM) 10-48 
Pensacola Lake, Okla. (SWL) 28-22 
Pensaukee Harbor, Wis. (NCE) 21-55, 21-60 
Pentwater Harbor, Mich. (NCE) 21-18, 21-38, 21-50, 
21-57 
Peoria, Ill. (NCC) 23-14 
Pepin Harbor, Wis. (NCD) 25-7 
Pepper Creek, Del. (NAP) 3-24 
Pepperell Cove, Me. (NED) 1-39, 1-45 
Perdido Pass Channel, Ala. (SAM) 10-12, 10-33, 
10-43 
Perkins Cove, Ogunquit, Me. (NED) 1-46 
Perley Brook, Ft. Kent, Me. (NED) 1-20, 1-24, 1-31, 
1-37 
Permanent International Association of Navigation 
Congresses (PIANC) 48-1, 48-2 
Perquimans River, N.C. (SAW) 6-25, 6-27 
Perry County Drainage and Levee Districts Nos. 1, 
2, and 3, Mo. (LMS) 14-15 
Perry Lake, Delaware River, Kan. (MRK) 27-5, 
27-10, 27-13, 27-19 
Perry Lake Area (Road Improvements), Kan. (MRK) 
27-16 
Perryville, Ky. (ORL) 16-29 
Perth Amboy, NJ. (NAN) 2-36 
Peru Dike (MRO) 26-18 
Petaluma River, Calif. (SPN) 34-7 
Peters Creek, Roanoke, Va. (SAW) 6-31 
Petersburg Harbor, Alaska (NPA) 40-12 
Petit Jean River, Ark. (SWL) 28-17 
Petite Anse, Tigre, and Carlin Bayous, La. (LMN) 
11-17 
Petoskey Harbor, Mich. (NCE) 21-55, 21-60 
Pettibone Park, La Crosse, Wis. (NCS) 24-13, 24-23 
Peyton Creek, Tex. (SWG) 31-31 
Phillippi Creek Basin, Fla. (SAJ) 9-54 
Phillips Lake, Mass. (NED) 1-42, 1-51 
Philpott Lake, Va. (SAW) 6-15, 6-16, 6-20 
Phoenix, Ariz., and Vicinity (including New River) 
(SPL) 33-5, 33-20 
Pick-Sloan Missouri Basin Program (Kansas City 
Dist) (MRK) 27-5, 27-13 
Pick-Sloan Missouri Basin Program (Omaha Dist) 
(MRO) 26-5, 26-13, 26-18 
Pickwick Landing Lock and Dam, Tenn. (ORN) 15-17 
Pierce, Elkhorn River, Nebr. (MRO) 26-20 
Pierce, Nebr. (MRO) 26-16 
Pig Island Gut, Me. (NED) 1-39, 1-46, 1-53 
Pike Island Locks and Dams, W. Va. (ORD) 19-7 
Pilchuck River, Wash. (NPS) 38-26 
Pilot Rock, Oreg. (NPP) 37-41 
Pine and Mathews Canyons Dams, Nev. (SPL) 33-7, 
33-14, 33-22 
Pine Bluff, Ark. (LMK) 12-17 
Pine Creek, Angle Inlet, Minn. (NCS) 24-27 
Pine Creek Lake, Okla. (SWT) 29-7, 29-14, 29-17 
Pine Flat Lake and Kings River, Calif. (SPK) 35-14, 
35-26 
Pine Ford Lake, Mo. (LMS) 14-4, 14-8 
Pine Mountain Lake, Ark. (SWL) 28-17 
Pine Point Harbor, Scarborough, Me. (NED) 1-46 
Pine River, Mich. (NCE) 21-55 
Pine River Harbor, Mich. (NCE) 21-60 
Pine River Reservoir, Minn. (NCS) 24-31 
Pinellas County, Fla. (SAJ) 9-20, 9-30, 9-41 
Pineville, Ky. (ORN) 15-13, 15-19 
Pineville, La. (LMN) (LMK) 11-18 12-20 
Pineville, Red River, La. (LMK) 12-19 
Pinole Creek, Calif. (SPK) 35-34 
I-52

INDEX 
Pinon Canyon Dam, Trinidad, Colo. (SWA) 32-14 
Pioneer Lake, Kan. (MRK) 27-17 
Pipestem Lake, N. Dak. (MRO) 26-6, 26-10, 26-14 
Piscataquog River, Goffstown, N.H. (NED) 1-47 
Pithlachascotee River, Fla. (SAJ) 9-47 
Pittsburgh, Pa. (Golden Triangle) (ORP) 18-21 
Pittsburgh, Pa. (North Side) (ORP) 18-21 
Pittsburgh, Pa. (The Strip) (ORP)18-21 
Pittsburgh Harbor, Pa. (ORP)18-19 
Pittsburg Landing to Johnson Bar (NPW) 39-14 
Pittsfield, Mass. (NED) 1-23, 1-50 
Placer Creek, Idaho (NPS) 38-26 
Plainfield, Iowa (NCR) 23-17 
Plainview Local Flood Protection Project (SWF) 
30-22 
Plateau Creek near Collbran, Colo. (SPK) 35-40 
Platte River, Ashland, Nebr. (MRO) 26-20 
Platte River, Douglas Co. (Ginger Cove Sewage 
Lagoon), Nebr. (MRO) 26-23 
Platte River, Mo., Channel Improvement (MRK) 
27-16 
Platte River, North Bend, Nebr. (MRO) 26-23 
Platte River and Lost Creek, Schuyler, Nebr. (MRO) 
26-16 
Platte River and Tributaries, Nebr. (MRO) 26-16 
Platte River, Bank Protection, Louisville, Nebr. 
(MRO) 26-20 
Platte River, Brandy, Nebr. (MRO) 26-20 
Platte River, Hansen-Chris Lakes, Bellevue, Nebr. 
(MRO) 26-20 
Platte River, M.U.D. Protection, Cedar Island, Nebr. 
(MRO) 26-20 
Platte River near Schuyler, Nebr. (MRO) 26-16 
Plattsburgh Harbor, N.Y. (NAN) 2-34 
Pleasant Bay, Mass. (NED) 1-45 
Pleasant Creek, Johnson Co., Ind. (ORL) 16-31 
Pleasant Point, Perry, Me. (NED) 1-24, 1-42 
Pleasant River, Maine (NED) 1-39 
Pleasant Valley Levee (MRO) 26-18 
Pleasanton Floodway, Tex. (SWF) 30-22 
Plum Creek, Ky. Spence Co. (ORL) 16-30 
Plum Creek at New Haven Township, Minn. (NCS) 
24-33 
Plum Creek, Bank Stabilization, Aurora, Colo. 
(MRO) 26-19 
Plum Island, Mass. (NED) 1-41 
Plymouth, Pa. (NAB) 4-39, 4-42 
Plymouth Harbor, Mass. (NED) 1-4, 1-6, 1-20, 1-46 
Poca, W. Va. (ORH) 17-22 
Pocomoke River, Md. (NAB) 4-8, 4-25, 4-33 
Poesten Kill, Troy, N.J. (NAN) 2-39 
Pohoiki Bay, Hawaii, Hawaii (POD) 36-10 
Point Graham, Ark. (NPA) 40-13 
Point Judith Pond and Harbor of Refuge, R.I. (NED) 
1-7, 1-26, 1-34, 1-45 
Point of Pines, Revere, Mass. (NED) 1-47 
Point Lookout Harbor (Au Gres River), Mich. (NCE) 
21-18, 21-38, 21-50 
Point Place, Toledo, Ohio (NCB) 20-14, 20-21, 20-34 
Point Pleasant, W. Va. (ORL) 17-21, 17-23 
Point Remove Levee and Drainage District, Conway 
County, Ark. (SWL) 28-17 
Pokegama Reservoir, Minn. (NCS) 24-31 
Pollock Rip Shoals, Nantucket Sound, Mass. (NED) 
1-39 
Poloa Seawall, American Samoa (POD) 36-14 
Poison Bay, Flathead Lake, Mont. (NPS) 38-24 
Pomeroy, Ohio (ORL) 17-22 
Pomme De Terre Lake, Pomme de Terre River, Mo. 
(MRK) 27-6, 27-10, 27-14, 27-19 
Pomona Lake, One Hundred Ten Mile Creek, Kan. 
(MRK) 27-6, 27-10, 27-14 
Pomona Lake, Osage River Basin, Kan. (MRK) 27-19 
Ponce, P.R. (SAJ) 9-42 
Ponce De Leon Inlet, Fla. (SAJ) 9-13, 9-29, 9-36 
Ponce Harbor, P.R. (SAJ) 9-13, 9-29, 9-36 
Ponce Regional, P.R. (SAJ) 9-54 
Pontiac Diversion, R.I. (NED) 1-45 
Pool, Joe, Lake (Lakeview Lake), Tex. (SWF) 30-6, 
30-16, 30-19 
Port Alexander, Alaska (NPA) 40-12, 40-13 
Port Allen Harbor, Kauai, Hawaii (POD) 36-10 
Port Angeles Harbor, Wash. (NPS) 38-24, 38-28 
Port Arthur and Vicinity, Tex., Hurricane-Flood 
Protection (SWG) 31-11, 31-16, 31-28 
Port Austin Harbor, Mich. (NCE) 21-18, 21-38, 21-50 
Port Bay, N.Y. (NCB) 20-35 
Port Chester Harbor, N.Y. (NAN) 2-34 
Port Clinton Harbor, Ohio (NCB) 20-35 
Port Dickinson, N.Y. (NAB) 4-42 
Port Everglades Harbor, Fla. (SAJ) 9-14, 9-29, 9-37, 
9-46 
Port 5 Facility, Bridgeport, Conn. (NED) 1-42 
Port Gamble Harbor, Wash. (NPS) 38-24, 38-28 
I-53

Port Henry Harbor, N.Y. (NAN) 2-34 
Port Hueneme, Calif. (SPL) 33-3, 33-12, 33-18, 33-28 
Port Isabel (SWG) 31-37 
Port Jefferson Harbor, N.Y. (NAN) 2-34 
Port of Kalama, Wash. (NPP) 37-38 
Port Ontario Harbor, N.Y. (NCB) 20-9, 20-19, 20-31 
Port Orchard Bay, Wash. (NPS) 38-24 
Port Orford, Oreg. (NPP) 37-6, 37-24, 37-32 
Port Royal Harbor, S.C. (SAN) 7-5, 7-9, 7-12 
Port San Luis, Calif. (SPL) 33-23 
Port Sanilac Harbor, Mich. (NCE) 21-18, 21-26, 
21-38, 21-50 
Port St. Joe Harbor, Fla. (SAM) 10-47 
Port Townsend, Wash. (NPS) 38-24, 38-31 
Port Washington Harbor, Wis. (NCE) 21-55 
Port Wing Harbor, Wis. (NCE) 21-19, 21-39, 21-50 
Portage, Pa. (ORP) 18-20 
Portage Lake Harbor, Mich. (NCE) 21-18, 21-38, 
21-50 
Portchester Harbor, N.Y. (NAN) 2-38 
Porter Bayou, Miss. (LMK) 12-6, 12-9, 12-12 
Portersville Bay Shoreline, Ala. (SAM) 10-49 
Portland, Ind. (Salamonie River) (ORL) 16-19, 16-30 
Portland, Ohio (ORH) 17-22 
Portland Harbor, Maine (NED) 1-39 
Portneuf River and Marsh Creek, Idaho (NPW) 39-12, 
39-16, 39-17 
Portsmouth Harbor, Va. Channel to Nansemond 
Ordnance Depot (NAO) 5-19 
Portsmouth Harbor and Piscataqua River, Maine and 
N.H. (NED) 1-7, 1-26, 1-35 
Portsmouth-New Boston, Ohio (ORH) 17-21, 17-23 
Portugues and Bucana Rivers, P.R. (SAJ) 9-24, 9-31, 
9-42 
Portville, N.Y. (ORP) 18-20 
Portville, N.Y. (Allegheny River) (ORP) 18-24 
Posten Bayou, Ark. and La. (LMN) (LMK) 11-18, 
12-18, 12-20 
Poteet Floodway, Tex. (SWF) 30-22 
Potlatch River, Ind. (NPW) 39-17 
Potomac and Anacostia Rivers, D.C., Collection and 
Removal of Drift (NAB) 4-9, 4-25, 4-33 
Potomac River and Tributaries at and below 
Washington, D.C., Elimination of Waterchestnut 
(NAB) 4-37 
Potomac River Aquatic Plant Control, Md., Va., D.C. 
(NAB) 4-9, 4-25, 4-34 
Potomac River at Alexandria, Va. (NAB) 4-37 
Potomac River at Lower Cedar Point, Md. (NAB) 
4-37 
Potomac River at Mount Vernon, Va. (NAB) 4-37, 
4-41 
Potomac River below Washington, D.C. (NAB) 4-9, 
4-26, 4-34 
Potomac River North Side of Washington Channel, 
D.C. (NAB) 4-37 
Potowomut River, R.I. (NED) 1-39 
Pottawatomie County, Okla. (SWT) 29-21 
Pottstown, Pa. (NAP) 3-26 
Poverty Point, La. (LMN) 12-20 
Powder River, Arvada, Wyo. (MRO) 26-23 
Powell County High School, Mont. (NPS) 38-26 
Powellhurst Basin, Oreg. (NPP) 37-43 
Powhatan Point, Ohio (ORP) 18-21 
Prairie Du Chien, Wis. (NCD) (NCS) 24-13, 24-23, 
25-7 
Prairie Du Chien, Harbor, Wis. (NCD) 25-10 
Prairie du Pont Levee and Sanitary District, Ill. 
(LMS) 14-15 
Prairie du Rocher and Vicinity, Ill. (LMS) 14-15 
Prattville, Autauga Creek, Ala. (SAM) 10-48 
Preconstruction Engineering and Design (SAW) 6-17 
Prescott Area, Oreg. (NPP) 37-41 
Presque Isle Harbor, Mich. (NCE) 21-19, 21-39, 21-51 
Presque Isle Peninsula, Erie, Pa. (NCB) 20-12, 20-20, 
20-33 
Prestile Stream, Blaine, Maine (NED) 1-42 
Preston Drainage and Levee District, Ill. (LMS) 14-15 
Prestonburg, Ky. (ORH) 17-23 
Prestonville, Ky. (ORL) 16-21, 16-25 
Prevention of Obstructions and Injurious Deposits, 
Baltimore, Md. (NAB) 4-10, 4-26, 4-34 
Price River Price, Utah (SPK) 35-40 
Priest, J. Percy, Dam and Reservoir, Tenn. (ORN) 
15-7, 15-9, 15-18 
Priest Rapids Dam, Wash. (NPS) 38-28 
Princeton, W. Va. (ORH) 17-21, 17-23 
Principal Data Concerning Navigation Lock, Spillway 
Dam, Powerplant and Impoundment (NPW) 39-18 
Prineville Area, Oreg. (NPP) 37-41 
Proctor, Otter Creek Basin, Vt. (NAN) 2-38 
Proctor, W. Va. (ORP) 18-21 
Proctor Creek, Atlanta, Ga. (SAM) 10-49 
Proctor Lake, Tex. (SWF) 30-8, 30-16, 30-20 
I-54

INDEX 
Proctorville, Ohio (ORH) 17-21 
Project Condition Surveys (NPA) 40-4, 40-14 
Prompton Lake, Pa. (NAP) 3-14, 3-18, 3-23 
Prospect Beach, West Haven, Conn. (NED) 1-41, 1-46 
Prosperity Lake, Mo. (SWL) 28-18 
Prototype Breakwater Test Program, Wash. (NPS) 
38-24 
Providence River and Harbor, R.I. (NED) 1-39, 1-45 
Provincetown Beach (Herring Cove), Mass. (NED) 
1-45 
Provincetown Harbor, Mass. (NED) 1-39, 1-45, 1-46 
Provo River, Utah Co., Utah (SPK) 35-40 
Pudding River, Oreg. (NPP) 37-41 
Pueblo Arkansas River, Colo. (Floodway Levee 
Extension) (SWA) 32-14 
Puerco River, Gallup, N.M. (SWA) 32-3, 32-11, 
32-12 
Puget Sound and Its Tributary Waters, Wash. (NPS) 
38-5, 38-15, 38-20 
Pullman, Palouse, Wash. (NPW) 39-16 
Pullman Palouse River, Wash. (NPW) 39-14 
Pultneyville Harbor, N.Y. (NCB) 20-35 
Pumpkinvine Creek, Emerson, Ga. (SAM) 10-48 
Pungo Creek, N.C. (SAW) 6-27 
Pungo River, N.C. (SAW) 6-27 
Punta Salinas, P.R. (SAJ) 9-48 
Punxsutawney, Pa. (Allegheny River Basin) (ORP) 
18-24 
Punxsutawney, Pa., Ohio River Basin, Pa. (ORP) 
18-4, 18-11, 18-16 
Put In Bay, Ohio (NCB) 20-35, 20-38 
Pysht River, Wash. (NPS) 38-26 
Q 
Quail Wash Levee, Joshua Tree, San Bernardino, 
Calif. (SPL) 33-25 
Queens Creek, Va. (NAO) 5-19, 5-21 
Queenstown Harbor, Md. (NAB) 4-37 
Queets River, Wash. (NPS) 38-26 
Quillayute River, Wash. (NPS) 38-5, 38-15, 38-20, 
38-26, 38-28, 38-29 
Quinalt River, Wash. (NPS) 38-26 
Quinby Creek, Va. (NAO) 5-19, 5-21 
Quincy, Ill., Harbor Access Channel (NCR) 23-12 
Quincy, Mass. (NED) 1-23 
Quincy Harbor, Ill. (NCD) 25-8 
Quincy Shore Beach, Quincy, Mass. (NED) 1-41 
Quinnippiac River, Wallingford, Conn. (NED) 1-47 
R 
R and H Act (NCB) 20-40 
R. D. Bailey Lake, W. Va. (ORH) 17-9, 17-15, 17-19 
Raccoon Creek, N.J. (NAP) 3-24 
Raccoon Creek, Baconton, Ga. (SAM) 10-49 
Raccoon Creek, D and L Townships, Ill. (ORL) 16-31 
Raccoon Creek Levee, Ind. (ORL) 16-21 
Raccoon Levee, Ind. (ORL) 16-25 
Raccoon River, Des Moines, Iowa (NCR) 23-17 
Racine, Ohio (ORH) 17-22 
Racine Harbor, Wis. (NCE) 21-57 
Racine Locks and Dam, Ohio (ORD) 19-6, 19-8 
Rahway, NJ. (NAN) 2-36, 2-38 
Rahway, South Branch, NJ. (NAN) 2-36 
Rainier Drainage District, Oreg. (NPP) 37-38, 37-39, 
37-44 
Rancocas River, N.J. (NAP) 3-27 
Randleman Lake, N.C. (SAW) 6-11, 6-20 
Rapid City, Cedar Canyon Dam, S. Dak. (MRO) 
26-19 
Rapid Creek, Idaho (NPW) 39-15 
Rapid Creek, Rapid City, S. Dak. (MRO) 26-16, 26-19 
Rappahannock River, Va. (NAO) 5-19 
Rappahannock River at Bowlers Wharf, Va. (NAO) 
5-19 
Rappahannock Shoal Channel, Va. (NAO) 5-2, 5-15 
Raritan Bay and Sandy Hook Bay, N.J. (NAN) 2-36 
Raritan River, NJ. (NAN) 2-34, 2-38 
Raritan River to Arthur Kill Cutoff Channel, N.J. 
(NAN) 2-14, 2-24, 2-30 
Rathbun Lake, Charitob River, Iowa (MRK) 27-6, 
27-10, 27-14 
Rathbun Lake Fish Hatchery (MRK) 27-16 
Ravenswood, W. Va. (ORH) 17-21 
Rawls Creek, S.C. (SAN) 7-16 
Ray Roberts Lake, Tex. (SWF) 30-9, 30-16, 30-20 
Raybumrn, Sam, Dam and Reservoir, Tex. (SWF) 
30-12, 30-17, 30-20 
Raystown Lake, Pa. (NAB) 4-14, 4-26, 4-36 
Recapitulation Project Levee Tables (FY 1988) 
(MR+T) 42-51 
Reconnaissance and Condition Surveys 
Baltimore, Md., District (NAB) 4-12, 4-41 
Buffalo, N.Y., District (NCB) 20-11 
I-55

Charleston, S.C., District (SAN) 7-6 
Chicago, Ill., District (NCC) 22-5, 22-17 
Detroit, Mich., District (NCE) 21-25, 21-60 
Galveston, Tx., Division (SWG) 31-9 
Jacksonville, Fla., District (SAJ) 9-18, 9-46 
Los Angeles, Calif., District (SPL) 33-28 
Mobile, Ala., District (SAM) 10-50 
New England Division (NED) 1-53 
New York District (NAN) 2-16, 2-33, 2-38, 2-39 
Norfolk, Va., District (NAO) 5-21 
Pacific Ocean Division (POD) 36-2 
Philadelphia, Penn., District (NAP) 3-14 
San Francisco, Calif., District (SPN) 34-4 
Savannah, Ga., District (SAS) 8-6 
Wilmington, N.C., District (SAW) 6-29 
Red Brook Harbor, Bourne, Mass. (NED) 1-39 
Red Creek, N.Y. (NCB) 20-40 
Red Lake and Clearwater Rivers, Minn. (NCS) 24-33 
Red Lake and Red Lake River, Minn. (NCS) 24-27 
Red Lake Falls, Minn. (NCS) 24-33 
Red Lake River, Minn., including Clearwater River, 
Minn. (NCS) 24-13, 24-24 
Red Lake River at Huot, Minn. (NCS) 24-28 
Red Lake River at Red Lake Falls, Minn. (NCS) 24-28 
Red River, Tenn. (ORN) 15-13 
Red River at East Grand Forks, Minn. (NCS) 24-32 
Red River at Fargo, N. Dak. (NCS) 24-32 
Red River at Grand Forks, N. Dak. (NCS) 24-32 
Red River Backwater (MR+T) 42-54 
Red River Backwater Area (MR+T) 42-6, 42-15 
Red River below Denison Dam (Vicksburg District): 
New Projects (LMK) 12-18 
Red River below Denison Dam including Little River 
Basin, Okla. and Ark. (SWL) 28-15 
Red River below Denison Dam, Levees and Bank 
Stabilization (Vicksburg District) (LMK) (SWI) 
12-7, 12-10, 12-13, 29-19 
Red River below Denison Dam (Vicksburg District) 
(LMK) 12-16, 12-18, 12-19 
Red River below Fulton, Ark. (LMK) 12-15 
Red River, Clay City, Ky. (ORL) 16-31 
Red River Emergency Bank Protection (LMK) 12-2, 
12-9, 12-11 
Red River in Vicinity of Shreveport, La. (LMN) 
(LMK) 11-18, 12-19, 12-21 
Red River Lake, Ky. (Kentucky River) (ORL) 16-20 
Red River of the North, Minn. and N. Dak. (NCS) 
24-27 
Red River of the North, Argusville, N. Dak. (NCS) 
24-14, 24-24 
Red River of the North at Breckenridge, Minn. 
(NCS) 24-14, 24-24, 24-28 
Red River of the North at Halstad, Minn. (NCS) 24-28 
Red River of the North at Oslo, Minn. (NCS) 24-28 
Red River of the North at Pembina, N. Dak. (NCS) 
24-28 
Red River of the North Drainage Basin, Minn., 
S. Dak. and N. Dak. (NCS) 24-14, 24-24, 24-32 
Red River Parish, La. (LMN) (LMIK) 11-8, 12-19, 
12-20 
Red River Standard Revetments (MR+T) 42-39 
Red River Waterway, La. (LMK) 12-12 
Red River Waterway, La., Ark., Okla., and Tex. 
(LMK) 12-15 
Red River Waterway-Mississippi River to 
Shreveport, La. (LMK) 12-2, 12-9, 12-11 
Red River Waterway, Shreveport, La., to 
Daingerfield, Tex. (LMK) 12-15 
Red River Waterway-Shreveport, La. to Index, Ark. 
(LMK) 12-7, 12-10, 12-13 
Red Rock Dam and Lake Red Rock, Iowa (NCR) 
23-4, 23-7, 23-11 
Red Run, Clinton River, Mich. (NCE) 21-27 
Red Run Drain-Lower Clinton River, Mich. (NCE) 
21-57 
Red Wing Harbor, Minn. (NCD) 25-7, 25-10 
Redbank and Fancher Creeks, Calif. (SPK) 35-15, 
35-26 
Redbank Creek Lake, Pa. (ORP) 18-21 
Redbird Creek, O'Neil, Nebr. (MRO) 26-20 
Reddies River Lake, N.C. (SAN) (SAW) 6-27, 7-15 
Redmond, John, Dam and Reservoir, Kan. (SWT) 
29-5, 29-13, 29-17 
Redondo Beach Harbor (King Harbor), Calif. (SPL) 
33-3, 33-9, 33-12, 33-19 
Redwater River and Hay Creek, Bell Fourche, S.D. 
(MRO) 26-17 
Redwood City Harbor, Calif. (SPN) 34-7 
Redwood Creek, Humboldt County, Calif. (SPK) 
35-34 
Redwood River below Marshall, Minn. (NCS) 24-28, 
24-33 
Reeds Bay Small Boat Harbor, Hawaii , Hawaii 
(POD) 36-10 
Reedsport Levees, Oreg. (NPP) 37-40 
Reedy River, S.C. (SAN) 7-15 
I-56

INDEX 
Reelfoot Lake-Lake No. 9, Tenn. and Ky. (MR+T) 
42-9, 42-18, 42-30 
Reese River, Battle Mountain, Nev. (SPK) 35-34 
Reevesville, Ill. (Reeves River) (ORL) 16-19, 16-24, 
16-29 
Regulation of Hydraulic Mining and Preparation of 
Plans (CDC) 53-1, 53-5, 53-7 
Regulatory Functions Program (SAM) 10-27 
Regulatory, Sunken Vessel Removal and National 
Emergency Preparedness Activities 51-1, 51-2 
Rehoboth Beach to Indian River Inlet, Del. (NAP) 
3- 26 
Removal of Aquatic Growth, La. (LMN) 11-17 
Removal of Aquatic Growth from Navigable Waters 
in the State of Florida (SAJ) 9-14, 9-29, 9-37, 9-46 
Removal of Sunken Vessels 51-1 
Removing Snags and Wrecks from Mississippi River 
below Mouth of Missouri River and from Old and 
Atchafalaya Rivers (LMK) (LMM) 12-15, 13-4 
Removing Water Hyacinths, Mobile District (SAM) 
10-47 
Rend Lake, Big Muddy River, Ill. (LMS) 14-5, 14-9, 
14-11 
Reno Beach-Howard Farms Area, Ohio (NCB) 20-15, 
20-21, 20-34 
Republican River, Clifton, Kan., Sewage Lagoons 
(MRK) 27-21 
Republican River, Nebr. and Kan. (MRK) 27-19 
Research and Development (LMS) (SAS) 8-9, 14-16 
Reservoirs (ORL) (ORN) 15-18,16-20 
Reservoirs at Headwaters of Mississippi River, Minn. 
(NCS) 24-2, 24-22, 24-26, 24-31 
Revere Beach, Mass. (NED) 1-10, 1-27, 1-36 
Reynoldsville, Pa. (ORP) 18-20 
Rheem Creek, Calif. (SPK) 35-34 
Rhodes Point to Tylerton, Md. (NAB) 4-10, 4-26, 4-34 
Rialto Channel, Rialto, Calif. (SPL) 33-28 
Rice Creek, Fla. (SAJ) 9-47 
Richard B. Russell Dam and Lake, Ga. and S.C. 
(Formerly Trotters Shoals Lake) (SAS) 8-8, 8-12, 
8-15 
Richardson Co. Drainage Dist. No. 8 (MRO) 26-18 
Richland Creek, Ill. (LMS) 14-15 
Richland Lake, Mo. (MRK) 27-17 
Richmond, Va. (NAO) 5-9, 5-14, 5-17 
Richmond Filtration Plant, Va. (NAO) 5-20 
Richmond Harbor, (Deepening) Calif. (SPN) 34-2, 
34-7, 34-10 
Richmond Harbor, Me. (NED) 1-39 
Richmond's Island Harbor, Maine (NED) 1-39 
Richwood and Fenwick, W. Va. (ORH) 17-23 
Ridgecrest, Kern Co., Calif. (SPL) 33-25 
Ridgway, Pa. (Allegheny River Basin) (ORP) 18-24 
Ridgway, Pa. (Elk Creek) (ORP) 18-20 
Ridgway and Vicinity, Pa. (On Clarion River) (ORP) 
18-20 
Right and Left Forks of Beaver Creek, Ky. (ORH) 
17-23 
Rillito River in the Vicinity of Tucson, Gila River and 
Tributaries, Ariz. (SPL) 33-10 
Rio Anton Ruiz-Runta Santiago, P.R. (SAJ) 9-54 
Rio Cibuco, Vega Baja, P.R. (SAJ) 9-5 
Rio Descolabrada, Santa Isabel (SAJ) 9-54 
Rio Grande Basin, N. Mex. (SWA) 32-4, 32-11, 32-12 
Rio Grande Floodway, N. Mex. (SWA) 32-6, 32-11, 
32-12, 32-13 
Rio Guamani, Guayana, P.R. (SAJ) 9-54 
Rio Manati, Barceloneta, P.R. (SAJ) 9-54 
Rio Niqua, Arroyo, P.R. (SAJ) 9-54 
Rio Puerto Nuevo, P.R. (SAJ) 9-42 
Rio Tallaboa-Penuelas, P.R. (SAJ) 9-54 
Ripley, Ohio (ORH) 17-22 
Ripley, W. Va. (ORH) 17-23 
Rippowam River, Stamford, Conn. (NED) 1-47 
Ririe Lake, Idaho (NPW) 39-15 
Ririe Lake, Willow Creek, Idaho (NPW) 39-14 
Rising Sun, Ind. (ORL) 16-21, 16-25 
102 River, Nodaway Co., Missouri, Co. Bridge 
(MRK) 27-21 
River Rouge, Mich. (NCE) 21-56 
Rivers and Harbors Contributed Funds (SAM) 10-29 
Riverdale, West Springfield, Mass. (NED) 1-15, 1-29, 
1-36, 1-49 
Riverland Levee District, Mo. (LMS) 14-15 
Riverside Area, Pasco, Wash. (NPW) 39-15 
Riverview, W. Va. (ORH) 17-22 
Roanoak Lake, Tex. (SWF) 30-22 
Roanoke River, N.C. (SAW) 6-25 
Roanoke River, 50 mile long Channel from Palmyra 
Landing to Weldon (SAW) 6-28 
Roanoke River Basin, Va. and N.C. (SAW) 6-14, 6-30 
Roaring Fork River near Basalt, Colo. (SPK) 35-40 
Roaring River, Wilkes County, N.C. (SAN) 7-15 
Roaring River Lake, N.C. (SAW) 6-27 
Robert F. Henry Lock and Dam, Ala. (SAM) 10-22, 
10-35, 10-45 
I-57

Robert S. Kerr Lock and Dam, Okla. (SWL) (SWT) 
28-20, 29-16, 29-18, 29-20 
Roberts, Ray, Lake, Tex. (SWF) 30-9, 30-16, 30-20 
Robinson Run, Oakdale, Penn. (ORP) 18-26 
Rochester and McCleary's Bluff Levee, Ill. (Wabash 
River) (ORL) 16-19, 16-24, 16-29 
Rochester, Minn. (NCS) 24-15, 24-24 
Rochester, Pa. (ORP) 18-21 
Rochester Harbor, N.Y. (NCB) 20-9, 20-19, 20-31 
Rochester Lake, Cedar River, Iowa (NCR) 23-15 
Rock Creek, Kan. (SWT) 29-21 
Rock Creek, Mont. (NPS) 38-26 
Rock Creek, Morrison, Ill. (NCR) 23-17 
Rock Hall Harbor, Md. (NAB) 4-37 
Rock Island, Ill. (NCR) 23-13, 23-16 
Rock Island District (NCD) 25-3, 25-4 
Rock Island Harbor, Ill. (NCD) 25-7 
Rock River Agricultural Levees, Ill. (NCR) 23-14 
Rockfish Creek, N.C. (SAW) 6-28 
Rockford, Ill. (NCR) 23-5, 23-7, 23-11 
Rockland Harbor, Maine (NED) 1-39, 1-45 
Rockland Lake, Tex. (SWF) 30-11, 30-17, 30-20 
Rockport, Ind. (ORL) 16-21, 16-25 
Rockport and Old Harbors, Rockport, Mass. (NED) 
1-39 
Rockport Harbor, Maine (NED) 1-8, 1-27, 1-35, 1-53 
Rockport Harbor and Pigeon Cove, Rockport, Mass. 
(NED) 1-8, 1-27, 1-35 
Rocky Ford Drainage and Levee District, Ill. (NCR) 
23-13 
Rocky Pass, Alaska (NPA) 40-12 
Rocky River Harbor, Ohio (NCB) 20-35 
Rocy Fork, Ohio (ORH) 17-22 
Rodeo Creek, Calif. (SPK) 35-34 
Rogers City Harbor, Mich. (NCE) 21-57 
Rogue River, Oreg. (NPP) 37-40 
Rogue River Harbor at Gold Beach, Oreg. (NPP) 37-7, 
37-24, 37-32 
Roland Drainage District, Arkansas River, Ark. 
(SWL) 28-17 
Rolling Fork Road, Sevier County, Ark. (SWL) 28-17 
Rollinson Channel, N.C. (SAW) 6-8, 6-19 
Rome, Coosa River, Ga. (SAM) 10-48 
Rome, Ind. (ORL) 16-21, 16-25 
Rome Mohawk River, N.Y. (NAN) 2-38 
Rondout Harbor, N.Y. (NAN) 2-14, 2-24, 2-30 
Roosevelt Campobello International Park, Lubec, Me. 
(NED) 1-11, 1-24, 1-27, 1-36 
Root Creek, Bolivar, N.Y. (ORP) 18-20 
Rose Creek Channel Improvements, San Diego, 
Calif. (SPL) 33-25, 33-28 
Roseau River, Minn. (NCS) 24-15, 24-24 
Rosedale Harbor, Miss. (LMK) 12-15 
Rosendale, N.Y. (NAN) 2-36 
Roseville, Ohio (ORH) 17-9,17-14, 17-19, 17-23 
Rosiclare, Ill. (ORL) 16-19, 16-29 
Rossview Lake, Tenn. and Kan. (ORN) 15-14 
Rossville, Cross Creek, Kan. (MRK) 27-21 
Rota Harbor, Northern Marianas (POD) 36-10 
Rouge River, Mich. (NCE) 21-19, 21-27, 21-39, 
21-51, 21-57 
Rough River, Ky. (ORL) 16-18, 16-24, 16-30 
Rough River Lake and Channel Improvements, Ky. 
(ORL) 16-9, 16-15 
Roughans Pt., Revere, Mass. (NED) 1-20, 1-31, 1-37 
Rouses Point, Lake Champlain, N.Y. (NAN) 2-34 
Rouseville, Pa. (ORP) 18-20 
Rowlesburg Lake, W. Va. (ORP) 18-20 
Royal River, Maine (NED) 1-39 
Ruby River, Wheatly Bridge, near Twin Bridges, 
Mont. (MRO) 26-19 
Rudee Inlet (NAO) 5-6, 5-13, 5-17 
Ruffy Brook, Minn. (NCS) 24-30 
Rush River, N. Dak. (NCS) 24-32, 24-33 
Rushford, Minn. (NCS) 24-28 
Russell, Ky. (ORH) 17-21, 17-23 
Russell and Allison Levee, Ill. (Wabash River) (ORL) 
16-19, 16-24 
Russell, Richard B., Dam and Lake, Ga. and S.C. 
(SAS) 8-8, 8-12, 8-15 
Russian River Basin, Calif. (SPK) 35-16, 35-26, 
35-31, 35-38 
Rutland, Otter Creek, Vt. (NAN) 2-36 
Rutledge Hollow Creek Channel Improvement, 
Poteet, Tex. (SWF) 30-22 
Rye Creek, Mont. (NPS) 38-26 
Rye Harbor, N.H. (NED) 1-39 
S 
S-53, Eau Gailie (SAJ) 9-49 
S-55, Christmas (SAJ) 9-49 
S-57, Ashton (SAJ) 9-49 
S-58, Ashton (SAJ) 9-49 
S-59, Kissimmee (SAJ) 9-49 
S-60, Ashton (SAJ) 9-49 
1-58

INDEX 
S-61, St. Cloud (SAJ) 9-49 
S-62, Ashton (SAJ) 9-49 
5-63, Ashton (SAJ) 9-49 
S-63A, Ashton (SAJ) 9-49 
S-65 Lock, Frostproof (SAJ) 9-49 
S-65A Lock, Avon Park (SAJ) 9-49 
S-65B Lock, Sebring (SAJ) 9-49 
S-65C Lock, Sebring (SAJ) 9-49 
S-65D Lock, Okeechobee (SAJ) 9-49 
S-65E Lock, Okeechobee (SAJ) 9-49 
S-157, Sebastian (SAJ) 9-49 
S-158, Titusville (SAJ) 9-49 
S-193, Okeechobee (SAJ) 9-49 
S-308B, Pohakee (SAJ) 9-49 
S-310, Clewiston (SAJ) 9-49 
Sabana Grande, P.R. (SAJ) 9-54 
Sabine - Neches Waterway, Tex. (SWG) 31-7, 31-16, 
31-25, 31-32, 31-34, 31-38 
Sabine River and Tributaries, Tex. (Echo to Morgan 
Bluff) (SWG) 31-30 
Sabula, Iowa (NCR) 23-13, 23-16 
Sackets Harbor, N.Y. (NCB) 20-35, 20-40 
Saco, Mont. (MRO) 26-16, 26-18 
Saco River, Me. (NED) 1-9, 1-27, 1-35, 1-45 
Sacramento River, Calif. (SPK) (CDC) 35-2, 35-24, 
35-31, 53-3, 53-5, 53-6, 53-8 
Sacramento River, Calif.: Tidal and Flooding Conditions 
35-36 
Sacramento River, Tehama, Calif. (SPK) 35-40 
Sacramento River and Tributaries, Calif. (CDC) 
(Debris Control) 53-2, 53-5 
Sacramento River and Tributaries, Calif., from 
Collinsville to Shasta Dam (SPK) 35-17, 35-27, 
35-32, 35-39 
Sacramento River Deep Water Ship Channel, Calif. 
(SPK) 35-2, 35-24 
Sacred Heart Hospital, Yankton, S. Dak. (MRO) 
26-16, 26-19 
Sag Harbor, N.Y. (NAN) 2-35 
Saginaw River, Mich. (NCE) 21-20, 21-26, 21-39, 
21-41, 21-51, 21-54 
Saint John River Basin, Maine (NED) 1-20 
Saipan Beach Rd., CNMI (POD) 36-14 
Saipan Small Boat Harbor, Northern Marianas 
(POD) 36-10 
Sakonnet Harbor, R.I. (NED) 1-38, 1-45 
Sakonnet River, R.I. (NED) 1-39 
Salamanca, N.Y. (ORP) 18-20 
Salamanoa (Power Transmission Tower), N.Y. (ORP) 
18-26 
Salamonie Lake, Ind. (ORL) 16-10, 16-15, 16-30, 
16-31 
Salem Church Lake, Va. (NAO) 5-20 
Salem Harbor, Mass. (NED) 1-39, 1-45 
Salem River, N.J. (NAP) 3-9, 3-17, 3-21 
Salina, Smoky Hill River, Kan. (MRK) 27-16, 27-19 
Salinas River, Calif. (SPK) 35-34 
Saline Point, La. (LMN) (LMK) 11-8, 12-19, 12-21 
Saline River, Ark. (LMK) 12-15 
Saline River and Tributaries, Ill. (ORL) 16-19, 16-30 
Salisbury, Conn. (NED) 1-23, 1-50 
Salkahatchie River, S.C. (SAN) 7-14 
Salmon Creek at Oakridge, Oreg. (NPP) 37-40, 37-43 
Salmon Creek near Vancouver, Wash. (NPP) 37-40 
Salmon River, Alaska (NPA) 40-13 
Salmon River, Idaho (NPW) 39-17 
Salmon River, Oreg. (NPP) 37-37 
Salmon River, Colchester, Conn. (NED) 1-42, 1-49 
Salt Creek, Ohio (ORH) 17-21 
Salt Creek and Tributaries, Nebr. (MRO) 26-6, 26-11, 
26-14 
Salt Creek Sewage Treatment Plant, Lincoln, Nebr. 
(MRO) 26-20 
Salt Fork, Okla. (SWT) 29-21 
Salt Lake City, Jordan River, Utah (SPK) 35-34 
Saluda River, S.C. (SAN) 7-15 
Salyersville, Ky. (Licking River) (ORL) 16-19 
Salzer Creek, Wash. (NPS) 38-29 
Sam Rayburn Dam and Reservoir, Tex. (SWF) 30-12, 
30-17, 30-20 
Sammamish River, Wash. (NAS) 38-26 
San Acacia to Bosque del Apache Unit (SWA) 32-14 
San Antonio Channel Improvement, Tex. (SWF) 30-9, 
30-17, 30-20 
San Antonio Floodway, Tex. (SWF) 30-22 
San Bernard River Channel (SWG) 31-36 
San Diego Creek, Alice, Tex. (SWG) 31-31 
San Diego Harbor, Calif. (SPL) 33-3, 33-12, 33-19 
San Diego River and Mission Bay, Calif. (SPL) 33-4, 
33-12, 33-19 
San Diego River Channel and Levee, San Diego, 
Calif. (SPL) 33-28 
San Diego River (Mission Valley), San Diego Basin, 
Calif. (SPL) 33-25 
I-59

San Diego (Sunset Cliffs), Calif. (SPL) 33-24 
San Francisco Bay and Delta Model, Calif. (SPN) 
34-3, 34-7 
San Francisco Bay to Stockton, Calif. (John F. 
Baldwin and Stockton Ship Channels) (SPK) 
(SPN) 34-2, 34-7, 35-3, 35-24 
San Francisco Harbor, Calif. (SPN) 34-7 
San Francisco Harbor and Bay (Removal of Drift), 
Calif. (SPN) 34-7 
San Francisco Harbor (Islais Creek), Calif. (SPN) 
34-12 
San Gabriel River, Tex. (SWF) 30-9, 30-17, 30-20 
San Gabriel River to Newport Bay (Surfside-Sunset 
and Newport Beach), Calif. (SPL) 33-24 
San Joaquin River, Calif. (SPK) 35-4, 35-24 
San Joaquin River, Calif.: Cost of New Work for 
Project (SPK) 35-37 
San Joaquin River, Calif.: Project Units (1950 Modification) 
Reclassified and Excluded from Project 
Costs (SPK) 35-37 
San Joaquin River, Madera Co., Rd. 4 Bridge, Calif. 
(SPK) 35-40 
San Juan, P.R. (SAJ) 9-48 
San Juan Dam, Calif. (SPL) 33-27 
San Juan Harbor, P.R. (SAJ) 9-16, 9-29, 9-38, 9-46 
San Leandro Creek, Calif. (SPK) 35-34 
San Leandro Marina, Calif. (SPN) 34-7 
San Leandro Marina (Breakwater), Calif. (SPN) 34-12 
San Eorenzo Creek, Calif. (SPK) 35-34 
San Lorenzo Creek, (Upper Portion) Calif. (SPN) 
34-13 
San Lorenzo River, Calif. (SPK) 35-34 
San Luis Rey River, San Luis Rey River Basin, Calif. 
(SPL) 33-7, 33-14, 33-22 
San Pablo Bay and Mare Island Strait, Calif. (SPN) 
34-7, 34-13 
San Rafael Creek, Calif. (SPN) 34-7 
Sand Cove, Gouldsboro, Me. (NED) 1-43 
Sand Creek Channel Improvement, Kan. (SWT) 
29-19, 29-20 
Sand Hill Cove Beach, R.I. (NED) 1-41 
Sand Hill River, Minn. (NCS) 24-32, 24-33 
Sand Island, Oahu, Hawaii (POD) 36-11 
Sand Island Shore Protection, Oahu, Hawaii (POD) 
36-3, 36-7 
Sand Lake, Okla. (SWT) 29-19 
Sandburg Creek, Spring Glen, N.Y. (NAN) 2-36 
Sanders Creek, Boscobal, Wis. (NCS) 24-34 
Sandusky Harbor, Ohio (NCB) 20-10, 20-20, 20-32, 
20-35 
Sandusky River, Ohio (NCB) 32-35 
Sandusky River, Ream Rd., Sandusky, Ohio (NCB) 
20-39 
Sandusky River, Twsp. Rd. 234, Sandusky Twsp, 
Ohio (NCB) 20-39 
Sandy Bay, Cape Ann, Mass. (NED) 1-39, 1-45 
Sandy Bay (Harbor of Refuge), Cape Ann, Mass. 
(NED) 1-39 
Sandy Creek, Jackson, Tenn. (LMM) 13-5 
Sandy Drainage District, Oreg. (NPP) 37-39, 37-44 
Sandy Hook Bay, NJ. (NAN) 2-35 
Sandy Hook Bay at Leonardo, NJ. (NAN) 2-33, 2-35 
Sandy Hook to Barnegat Inlet, N.J. (NAN) 2-17, 2-25, 
2-31, 2-36 
Sandy Lake Reservoir, Minn. (NCS) 24-31 
Sandy River and Sleepy Lake, Oreg. (NPP) 37-39 
Sangamon River (Mouth), Ill. (NCR) 23-13 
Sangamon River, Riverton, Ill. (NCR) 23-17 
Sanitary District of Beardstown, Ill. (NCR) 23-16 
Sans Bois Navigation Channel, Okla. (SWT) 29-20 
Santa Ana River Basin (and Orange County), Calif. 
(SPL) 33-7, 33-14, 33-22, 33-27 
Santa Ana River Basin, Calif., Devil, East Twin, and 
Warm Creeks Channel Improvements (SPL) 33-25 
Santa Ana River Mainstem, Calif. including 
Santiago Creek, Santa Ana River Basin, Calif. 
(SPL) 33-10 
Santa Barbara Harbor, Calif. (SPL) 33-4, 33-12, 33-28 
Santa Clara River, Fillmore, Calif. (SPL) 33-28 
Santa Clara River Levee Improvement, Santa Clara 
River Basin, Calif. (SPL) 33-26 
Santa Cruz County, Calif. (SPN) 34-12 
Santa Cruz Harbor, Calif. (SPN) 34-3, 34-8, 34-11 
Santa Fe River and Arroyo Mascaras, N. Mex. 
(SWA) 32-14 
Santa Maria Valley Levees, Santa Maria River Basin, 
Calif. (SPL) 33-26 
Santa Paula Creek Channel and Debris Basins 
(including Mud Creek), Calif. (SPL) 33-26 
Santa Rosa Dam and Lake, N. Mex. (SWA) 32-7, 
32-11 
Santa Rosa-Ft. Walton, Fla. (SAM) 10-49 
Santee River, N.C. and S.C. (SAN) 7-14 
Sapelo Harbor, Ga. (SAS) 8-15 
Sarasota County, Fla. (SAJ) 9-41 
Sardis, Ohio (ORH) 17-22 
1-60

INDEX 
Sardis Dam (Dam Safety Assurance) (MR+T) 42-30 
Sardis Lake, Okla. (SWT) 29-7, 29-14, 29-17 
Sasanoa River, Maine (NED) 1-39 
Sasco Hill Beach, Fairfield, Conn. (NED) 1-41 
Satilla River, Ga. (SAS) 8-15 
Saugatuck Harbor and Kalamazoo River, Mich. (NCE) 
21-22, 21-40, 21-52 
Saugerties Harbor, N.Y. (NAN) 2-15 
Saugus and Pine Rivers, Mass. (NED) 1-46 
Sauk River, Wash. (NPS) 38-8, 38-17, 38-21, 38-26 
Sauvie Island Drainage District, Oreg. (NPP) 37-38, 
37-39, 37-44 
Savage River Dam, Md. (NAB) 4-39, 4-42 
Savan Gut-St. Thomas, V.I. (SAJ) 9-54 
Savanna Harbor, Ill. (NCD) 25-7 
Savannah City Park, Tenn. (ORN) 15-19 
Savannah Harbor, Ga. (SAS) 8-4, 8-10, 8-11 
Savannah River above Augusta, Ga. (SAS) 8-15 
Savannah River at Augusta, Ga. (SAS) 8-15 
Savannah River Basin, Ga. and S.C. (SAS) 8-7, 8-16 
Savannah River Basin at Oates Creek, Ga. (SAS) 8-9 
Savannah River below Augusta, Ga. (SAS) 8-5, 8-11, 
8-14 
Saw Mill Run, Penn. (ORP) 18-20 
Saw Mill Run, Salamanca, Penn. (ORP) 18-26 
Sawmill Branch, S.C. (SAN) 7-15 
Sawmill R. Elmsford and Greenburgh, N.Y. (NAN) 
2-36 
Saxman, Alaska (NPA) 40-13 
Saxon Harbor, Wis. (NCE) 21-23, 21-40, 21-53 
Saxonville, Mass. (NED) 1-23, 1-43, 1-51 
Saxtons River, Rockingham, Vt. (NED) 1-23 
Saylersville, Ky. (Licking River) (ORL) 16-19, 16-20 
Saylorville Lake, Iowa (NCR) 23-5, 23-8, 23-11 
Scajaquada Creek, N.Y. (NCB) 20-37 
Scappoose Drainage District, Oreg. (NPP) 37-38, 
37-44 
Scarboro River, Maine (NED) 1-39 
Scenic Drive, Duck Lake, Mich. (NCE) 21-26 
Scheduling Flood Control Reservoir Operations 
Albuquerque, N. Mex., District (SWA) 32-8 
Baltimore, Md., District (NAB) 4-21 
Fort Worth, Tex., District (SWF) 30-11 
Kansas City, Mo., District (MRK) 27-7, 27-11 
Los Angeles, Calif., District (SPL) 33-8 
Mobile, Ala., District (SAM) 10-27 
Omaha, Nebr., District (MRO) 26-6, 26-11 
Portland, Oreg., District (NPP) 37-15 
Sacramento, Calif., District (SPK) 35-20 
Tulsa, Okla., District (SWT) 29-8 
Walla Walla, Wash., District (NPW) 39-4 
Wilmington, N.C., District (SAW) 6-15 
Schuyler, Nebr. (MRO) 21-20 
Schuyler, Lost Creek and Platte River, Nebr. (MRO) 
26-20 
Schuylkill River, Pa. (NAP) 3-9, 3-17, 3-21 
Schuylkill River above Fairmount Dam, Pa. (NAP) 
3-24 
Schulykill River-Fairmont Park, Pa. (NAP) 3-9 
Scioto River at Portsmouth, Ohio (ORH) 17-20 
Sciotoville, Ohio (ORH) 17-22 
Scituate Harbor, Mass. (NED) 1-23, 1-39, 1-46 
Scott, W. Kerr, Dam and Reservoir, N.C. (SAW) 6-14, 
6-17, 6-20 
Scott County Drainage and Levee District, Illinois 
River, Ill. (LMS) 14-15 
Scotts Creek, S.C. (SAW) 7-6, 7-9, 7-13 
Scotts Creek, Va. (NAO) 5-17 
Scottsville, Va. (NAO) 5-9, 5-14, 5-17 
Scranton, Pa. (NAB) 4-39, 4-42 
Scranton, Buffalo, N. Dak. (MRO) 26-19 
Scuppernong River, N.C. (SAW) 6-25, 6-28 
Sea Bright to Ocean Township, N.J. (NAN) 2-17 
Seahom Drainage and Levee District, Ill. (NCR) 
23-13, 23-16 
Searsport Harbor, Maine (NED) 1-39, 1-53 
Seaside Park, Conn. (NED) 1-41 
Seattle Harbor, Wash. (NPS) 38-5, 38-15, 38-20, 
38-28, 38-29 
Sebasticook River, Hartland, Maine (NED) 1-43 
Sebewaing River, Mich. (NCE) 21-23, 21-40, 21-41, 
21-53 
Sebewaing, Sebewaing River, Mich. (NCE) 21-27, 
21-54 
Sec. 6 levees, 1928 Flood Control Act (MR+T) 42-30 
Seekonk River, R.I. (NED) 1-39 
Seldovia Harbor, Alaska (NPA) 40-12, 40-14 
Selkirk Shore State Park, Lake Ontario, N.Y. (NCB) 
20-36 
Seminole Basin-Largo, Fla. (SAJ) 9-54 
Seneca Lake, Geneva, N.Y. (NCB) 20-38 
Seneca Lake, Watkins Glen, N.Y. (NCB) 20-39 
Seneca River, Seneca Falls, N.Y. (NCB) 20-39 
Sergius Whitestone, Alaska (NPA) 40-12 
1-61

Sergius Whitestone Narrows (NPA) 40-14 
Sespe Creek at Fillmore, Ventura Co., Calif. (SPL) 
33-26 
Sesuit Harbor, Mass. (NED) 1-19, 1-27, 1-35 
Sevier River near Redmond, Utah (SPK) 35-34 
Sewage Lagoons, Vale, Oreg. (NPW) 39-15 
Sewage Treatment Plant, Missoula, Mont. (NPS) 
38-26 
Seward, Nebr. (MRK) 27-16 
Seward Harbor, Alaska (NFA) 40-12 
Sewer Outfall, Glendale, W. Va. (ORP) 18-26 
Sewerline Protection, Valley, Ala. (SAM) 10-17, 
10-34, 10-44 
Shad Landing State Park, Md. (NAB) 4-37 
Shallotte River, N.C. (SAW) 6-8, 6-19 
Shallow Creek, Baltimore, Md. (NAB) 4-10, 4-26, 
4-34 
Shark River, N.J. (NAN) 2-35 
Shawneetown, Ill. (ORL) 16-19, 16-21, 16-26, 16-29 
Sheboygan, Wis. (NCE) 21-26 
Sheboygan Harbor, Wis. (NCE) 21-23, 21-40, 21-53 
Sheepshead Bay, N.Y. (NAN) 2-35, 
Sheffield, Mass. (NED) 1-23, 1-50 
Sheffield Lake Community Park, Ohio (NCB) 20-40 
Sheffield Water Intake, Ala. (ORN) 15-19 
Shelburne, N.H. (NED) 1-23, 1-43 
Shell Creek, County Rd. near Columbus, Nerb. 
(MRO) 26-20 
Shell Creek, Nebr. (MRO) 26-17 
Shell Lake, Wis. (NCS) 24-34 
Shelley Area, Snake River, Idaho (NPW) 39-12, 39-16 
Shelton Creek, Wash. (NAS) 38-26 
Shelton Ditch, Oreg. (NPP) 37-41 
Shenango River Lake, Ohio River Basin, Pa. and Ohio 
(ORP) 18-7, 18-12, 18-18, 18-25 
Shepard Road, Mississippi River, St. Paul, Minn. 
(NCS) 24-28, 24-33 
Sherburne, N.Y. (NAB) 4-42 
Sheridan, Wyo. 26-16, 26-19 
Sherwood Island State Park, Conn. (NED) 1-41 
Sheyenne River, N. Dak. (NCS) 24-16, 24-24, 24-30, 
24-33 
Sheyenne River, Harwood, N.Dak. (NCS) 24-34 
Sheyenne River, Valley City, N. Dak. (NCS) 24-16, 
24-24 
Shidler Lake, Okla. (SWT) 29-19 
Shields River, near Clyde Park, Mont. (MRO) 26-16 
Shilshole Bay, Seattle, Wash. (NPS) 38-24 
Shipyard River, S.C. (SAN) 7-5, 7-9, 7-12 
Shoal Harbor and Compton Creek, N.J. (NAN) 2-33, 
2-35 
Shoals, Ind. (East Fork White River) (ORL) 16-21 
Shobe Canyon, Heppner, Oreg. (NPW) 39-15 
Shoreline Erosion Control Demonstration, 
Philadelphia, Penn. District (NAP) 3-11 
Shoreline Frotection Studies (NCB) (NCC) (SAN) 
7-17, 20-16, 22-8 
Short Beach, Conn. (NED) 1-41 
Shoshone River, Bank Protection, Lovell, 
Wyo. (MRO) 26-19 
Shoshone River, Byron, Wyo. (MRO) 26-19 
Shot Pouch Creek, S.C. (SAN) 7-15 
Shrewsbury River, N.J. (NAN) 2-33, 2-35 
Shrimp Basin (SWG) 31-36 
Shufebarger Levee, Ind. (ORL) 16-21 
Shumebarger Levee, Ind. (Wabash River) (ORL) 
16-25 
Shupe Run, Mt. Pleasant, Penn. (ORP) 18-26 
Sid Simpson Project, Ill. (NCR) 23-13 
Sidney, Nebr. (MRO) 26-23 
Sierra Madre Wash Channel, La. Co. drainage area, 
Calif. (SPL) 33-27 
Silver Beach to Cedar Beach, Conn. (NED) 1-41, 
1-45 
Silver Creek, Rome, Ga. (SAM) 10-49 
Silver City, Mich. (NCE) 21-26 
Silver Lake Harbor, N.C. (SAW) 6-9, 6-19, 6-23 
Simmesport (MR+T) 42-13, 42-14 
Simmons Bay, N.C. (SAW) 6-27 
Simpson Creek, S.C. (SAN) 7-15 
Sims Bayou, Tex. (SWG) 31-12, 31-17, 31-28 
Singing Hills Creek, Watauga, Tex. (SWF) 30-23 
Sion Farm, St. Croix, V.I. (SAJ) 9-54 
Sioux City, Floyd, Iowa (MRO) 26-20 
Sioux City, small navigation project (MRO) 26-15 
Sioux City Marina, Iowa (MRO) 26-9 
Sioux Falls, S. Dak. (MRO) 26-16 
Sioux Falls, Big Sioux River, S. Dak. (MRO) 26-19 
Sistersville, Ohio (ORH) 17-22 
Sitka Harbor, Alaska (NPA) 40-12 
Siuslaw River, Oreg. (NPP) 37-7, 37-24, 37-32, 37-40 
Six Runs Creek, N.C. (SAW) 6-28 
Sixes Bridge Lake, Md. and Pa. (NAB) 4-41 
Skaggs Ferry, Black River, Ark. (SWL) 28-17 
1-62

INDEX 
Skagit River, Wash. (NPS) 38-24, 38-26, 38-28 
Skagway Harbor, Alaska (NPA) 40-12 
Skagway River, Alaska (NPA) 40-13 
Skamokawa Creek, Wash. (NPP) 37-8, 37-25, 37-38 
Skamokawa Creek Area, Wash. (NPP) 37-32, 37-42 
Skamokawa (Steamboat Slough), Wash. (NPP) 37-41 
Skiatook Lake, Okla. (SWT) 29-8, 29-14, 29-17 
Skipanon Channel, Oreg. (NPP) 37-8, 37-25, 37-33 
Slaughter Creek, Md. (NAB) 4-37 
Slough Bend, Hickman, N.Y. (MR+T) 42-12 
Slovan, Pa. (ORP) 18-20 
Small Boat Harbor Opposite Chester, Ill. (LMS) 14-13 
Small Boat Harbor Opposite Hamburg, Ill. (LMS) 
14-13 
Small Craft Basin (SWG) 31-36 
Smelt Brook, Mass. (NED) 1-43 
Smith Creek, Colo. (SWA) 32-14 
Smith Creek, Md. (NAB) 4-38 
Smith Creek, Pamlico County, N.C. (SAW) 6-19 
Smith Ferry, Pa. (ORP) 18-21 
Smith River, N.H. (NED) 1-24 
Smith River, Oreg. (NPP) 37-37 
Smithfield, W. Va. (ORH) 17-23 
Smithland, Ky. (ORL) 16-20, 16-24 
Smithland Locks and Dam, Ky. (ORD) 19-9 
Smiths Creek (Wilmington), N.C. (SAW) 6-9, 6-25 
Smithville Channel, Little Platte River, Mo. (MRK) 
27-16 
Smithville Lake, Little Platte River, Mo. (MRK) 27-6, 
27-10, 27-14 
Smithville Lake, Trimble Wildlife Area (MRK) 27-16 
Smoky Hill, Saline, and Solomon Rivers, Abilene, 
Kan. (MRK) 27-19 
Smyma River, Del. (NAP) 3-27 
Snagging and Clearing Activities 
Louisville, Ky., District (ORL) 16-31 
Portland, Oreg., District (NPP) 37-45 
Rock Island, Ill., District (NCR) 23-6, 23-17 
Sacramento, Calif., District (SPK) 35-20 
Vicksburg, Miss., District (LMK) 12-8 
Snake River, Alvarado, Minn. (NCS) 24-34 
Snake River, Blackfoot, Ind. (NPW) 39-15 
Snake River, Heise Bridge Location, Ind. (NPW) 
39-15 
Snake River, Idaho (NPW) 39-17 
Snake River, Stevens, Blackfoot, Ind. (NPW) 39-15 
Snake River, Wyo. (NPW) 39-17 
Snake River Downstream from Johnson Bar 
Landing, Oreg., Wash., and Idaho (NPW) 39-7, 
39-10, 39-22 
Snake River Mouth to Johnson Bar, Oreg.,Wash. and 
Idaho (NPW) 39-14 
Snettisham, Alaska (NPA) 40-6, 40-9, 40-11 
Snohomish River, Wash. (NPS) 38-26, 38-29 
Snoqualmie River, Wash. (NPS) 38-26 
Sny Basin, Ill. (NCR) 23-13, 23-16 
Sny Island Levee Drainage District, Ill. (NCR) 23-13, 
23-16 
Soap Creek, Wash. (NPP) 37-41 
Socastee Creek, Horry County, S.C. (SAN) 7-16 
Socorro Diversion Channel, Tributaries of Rio 
Grande, N. Mex. (SWA) 32-14 
Soddy Daisy, Tenn. Repair (ORN) 15-19 
Soldier River, Ute, Iowa (MRO) 26-23 
Soldiers and Palmetto Creek, Ala. (SAM) 10-49 
Soleduck River Bridge, Wash. (NPS) 38-26 
Somerville Lake, Tex. (SWF) 30-10, 30-17, 30-20 
Sonoma Creek, Calif. (SPK) 35-34 
Sope Creek, Marietta, Ga. (SAM) 10-17, 10-34, 10-45 
Souris River, Velva, N. Dak. (NCS) 24-17, 24-24 
Souris River Basin, N. Dak. (NCS) 24-17, 24-24 
South Amsterdam, Mohawk River, N.Y. (NAN) 2-36 
South Bank Arkansas River, (Head Fourche Island 
to Pennington Bayou), Ark. (SWL) 28-17 
South Bank Arkansas River, Little Rock to Pin 
Bluff, Ark. Tucker Lakes (SWL) 28-17 
South Beardstown and Valley Drainage and Levee 
District, Ill. (NCR) 23-14, 23-16 
South Beardstown Drainage and Levee District, Ill. 
(NCR) 23-14 
South Beloit, Ill. (NCR) 23-15 
South Bristol Harbor, Maine (NED) 1-39 
South Channel, Goverment Island, Oreg. (NPP) 
37-37 
South Coventry Lake, Conn. (NED) 1-45 
South Creek, Martinburg, Nebr. (MRO) 26-20 
South Creek, N.C. (SAW) 6-27 
South Ellenville, N.Y. (NAN) 2-36 
South Fork, Boise River, Idaho (NPW) 39-15 
South Fork, Bon Secour River, Ala. (SAM) 10-49 
South Fork, Ewing, Nebr. (MRO) 26-23 
South Fork Catawba River, Cramerton, N.C. (SAW) 
6-31 
South Fork, Clearwater River, Kooskia-Stites, Idaho 
(NPW) 39-12, 39-15, 39-16 
South Fork of Cumberland River, Ky. (ORN) 15-13 
-63

South Fork of the Santa Clara River, Calif. (SPL) 
33-26 
South Haven Harbor, Mich. (NCE) 21-23, 21-40, 
21-53 
South Mesquite, Mesquite, Tex. (SWF) 30-23 
South Milwaukee Harbor, Wis. (NCE) 21-57 
South Orange, NJ. (NAN) 2-36 
South Platte River, Adams County, Colo. (MRO) 26-6 
South Platte River, Adams County, No. Washington 
St., Water and Sanitary Dist., Colo. (MRO) 26-19 
South Platte River Basin, Colo. (MRO) 26-14 
South Platte River, Commerce City, Colo. (1-270) 
(MRO) 26-23 
South Platte River, Commerce City, Colo. (I-76) 
(MRO) 26-23 
South Platte River, Commerce City, Colo. (State Hwy 
244) (MRO) 26-23 
South Platte River, lift, Colo. (MRO) 26-19 
South Platte River, Kersey, Colo. (MRO) 26-19 
South Platte River Levees and Channel 
Improvements, Chatfield Lake to Ft. Morgan, 
Colo. (MRO) 26-16 
South Platte River, Merino, Colo. (MRO) 26-19 
South Platte River, Platteville, Colo. (MRO) 26-19 
South Plymouth Lake, N.Y. (NAB) 4-41 
South Point, Ohio (ORH) 17-21 
South Portsmouth, Ky. (ORH) 17-21 
South Prairie Creek, Wash. (NPS) 38-29 
South Quincy, Ill. (NCR) 23-8 
South Quincy Drainage and Levee District, Ill. 
(NCR) 23-5, 23-11, 23-14, 23-16 
South River, N.C. (SAW) 6-25 
South River, Conway, Mass. (NED) 1-43, 1-49 
South River Drainage District, Mo. (NCR) 23-14, 
23-16 
South Scenic Rd., Buffalo Twp., Penn. (ORP) 18-26 
South Slough (Charleston), Oreg. (NPP) 37-37 
South St. Paul, Minn. (NCS) 24-33 
South Table Creek, Nebraska City, Neb. (MRO) 26-23 
South Tunbridge Lake, Vt. (NED) 1-45 
South Williamson, Ky. (ORH) 17-23 
Southeast Missouri Port, Missouri (LMS) 14-3, 14-8, 
14-10 
Southern Branch, Va. (NAO) 5-16 
Southern New York Flood Control Projects (NAB) 
4-14, 4-36 
Southport Beach, Conn. (NED) 1-41 
Southport Harbor, Conn. (NED) 1-39 
Southwest Harbor, Maine (NED) 1-39 
Southwestern Jefferson County, Ky. (ORL) 16-4, 
16-13 
Sowashee Creek, Meridian, Miss. (SAM) 10-17, 
10-34, 10-45, 10-48 
Spanish Fork River, Utah (SPK) 35-36 
Spanish Oak Creek, Cedar Park, Tex. (SWF) 30-23 
Spewrell Bluff Lake, Ga. (SAM) 10-48 
Spicket River, Salem, N.H. (NED) 1-47 
Spokane, Wash. (NAS) 38-9, 38-17, 38-21, 38-28 
Spring City, Tenn. (ORN) 15-19 
Spring Lake, NJ. (NAN) 2-39 
Spring Lake Drainage and Levee District, Ill. (NCR) 
23-14, 23-16. 
Springdale, Mass. (NED) 1-43, 1-49 
Springfield, Mass. (NED) 1-23, 1-43, 1-47, 1-49 
Springfield, S.D., Water Intake (MRO) 26-17 
Squantz Pond, New Fairfield, Conn. (NED) 1-43, 1-50 
Squaw Chute at Quincy, Ill. (NCR) 23-12 
Squirrel Creek, Okla. (SWT) 29-21 
Squirrel Hollow, Okla. (SWT) 29-21 
St. Albans Harbor, Lake Champlain, Vt. (NAN) 2-35 
St. Anthony Falls, Lower Lock and Dam, Minn. 
(NCD) 25-5 
St. Anthony Falls, Upper Lock, Minn. (NCD) 25-5 
St. Augustine Harbor, Fla. (SAJ) 9-15, 9-29, 9-46 
St. Catherines Sound, Md. (NAB) 4-10, 4-26, 4-34 
St. Claire River, Channels, Mich. (NCE) 21-58 
St. Claire River Compensating Works, Mich. (NCE) 
21-57 
St. Clair River, Mich. (NCE) 21-20, 21-39, 21-51, 
21-58 
St. Croix, River, Maine (NED) 1-39 
St. Croix River, Minn. and Wis. (NCS) 24-27 
St. Francis and L'Anguille Rivers and Blackfish 
Bayou, Ark. (LMM) 13-4 
St. Francis Basin, Ark. and Mo. (MR+T) 42-8, 42-30 
St. Francis River and Basin, Ark. and Mo. (MR+T) 
42-18 
St. Francis River, Highway 90, Ark. (LMM) 13-5 
St. Georges Island, Ark. (NPA) 40-13 
St. Georges Creek, Md. (NAB) 4-37, 4-41 
St. James, Beaver Island, Mich. (NCE) 21-55 
St. James Harbor, Mich. (NCE) 21-60 
St. Jeromes Creek, Md. (NAB) 4-11, 4-26, 4-34 
St. Johns Bayou, Mo. (MR+T) 42-12 
St. Johns Bayou and New Madrid Floodway (MR+T) 
42-30 
1-64

INDEX 
St. Johns County, Fla. (SAJ) 9-41 
St. Johns River, Fla., Jacksonville to Lake Harney 
(SAJ) 9-15, 9-29, 9-37, 9-46 
St. Johns River and Tributaries and Withlacoochee, 
Kissimmee, and Crystal Rivers, Fla. (SAJ) 9-46 
St. Jones River, Del. (NAP) 3-24, 3-25 
St. Joseph Harbor, Mich. (NCE) 21-21, 21-39, 21-51 
St. Joseph River, Mich. (NCE) 21-55 
St. Louis County Drainage and Levee District No. 1, 
Mo. (LMS) 14-15 
St. Louis District (NCD) 25-3 
St. Louis, levees, costs (MR+T) 42-62 
St. Lucie Inlet, Fla. (SAJ) 9-15, 9-29, 9-37, 9-46 
St. Maries, Idaho (NAS) 38-26 
St. Marks River, Fla. (SAM) 10-47, 10-50 
St. Marys, (Allegheny River Basin) Pa. (ORP) 18-21 
St. Marys, W. Va. (ORH) 17-22 
St. Marys River, Ga. and Fla., and North River, Ga. 
(SAS) 8-16 
St. Marys River (MacArthur Lock Guard Gates), 
Mich. (NCE) 21-57 
St. Marys River, Mich. (NCE) 21-21, 21-40, 21-52, 
21-56 
St. Michael Canal, Alaska (NPA) 40-12 
St. Michaels Harbor, Md. (NAB) 40-37 
St. Patricks Creek, Md. (NAB) 4-37 
St. Paul, Minn. (NCS) 24-18, 24-24, 24-33 
St. Paul and South St. Paul, Minn. (NCS) 24-28 
St. Paul District (NCD) 25-3, 25-4 
St. Paul Harbor, Ark. (NPA) 40-8 
St. Paul Harbor, Minn. (NCD) 25-10 
St. Paul Island, Ark. (NPA) 40-4, 40-11 
St. Peters Creek, Md. (NAB) 4-37 
St. Petersburg Harbor, Fla. (SAJ) 9-46, 9-47 
St. Thomas Harbor, V.I. (SAJ) 9-47 
Stamford, Conn. (NED) 1-20, 1-23, 1-31, 1-37, 1-39 
Stamford Barrier, Conn. (NED) 1-23 
Stamford Harbor, Conn. (NED) 1-45 
Starlings Creek, Va. (NAO) 5-19, 5-21 
Startup, Wash. (NAS) 38-26 
State Highway 156, Okla. (SWT) 29-21 
State Road and Ebner Coulees, Wis. (NCS) 24-17, 
24-24, 24-28 
Staten Island, N.Y. (NAN) 2-36 
Staten Island Rapid Transit Railway Co. Bridge 
Across Arthur Kill, N.Y. (NAN) 2-35 
Ste. Genevieve, Mo. (LMS) 14-11 
Ste. Genevieve County Drainage and Levee District 
No. 1, Mo. (LMS) 14-15 
Stebbins, Ark. (NPA) 40-13 
Steinhatchee River, Fla. (SAJ) 9-47 
Stikine River, Alaska (NPA) 40-4, 40-8, 40-11 
Stillaguamish River, Wash. (NPS) 38-9, 38-17, 38-22 
38-27, 38-28, 38-29 
Stillhouse Hollow Dam, Tex. (SWF) 30-10, 30-17, 
30-20 
Stillwater and Whitefish Rivers, Mont. (NPS) 38-27 
Stillwater Lake, Lackawanna River, Pa. (NAB) 4-18, 
4-28, 4-36 
Stillwater River, Mont. (NPS) 38-27 
Stillwell Drainage District, Oreg. (NPP) 37-40 
Stockton and Mormon Channels, Calif. (SPK) 35-33 
Stockton Harbor, Maine (NED) 1-40 
Stockton Lake, Sac River, Mo. (MRK) 27-8, 27-11, 
27-15, 27-19 
Stone Harbor, N.J. (NAP) 3-26 
Stonehouse Creek, Jefferson Co., Kan. (MRK) 27-16 
Stoner Creek, Ky. (ORL) 16-30 
Stonewall Jackson Lake, W. Va. (ORP) 18-7, 18-13, 
18-18, 18-25 
Stonington Harbor, Conn. (NED) 1-40, 1-45, 1-46 
Stonington Harbor, Maine (NED) 1-40, 1-45, 1-53 
Stony Brook, Wilton, N.H. (NED) 1-43 
Stony Creek, Branford, Conn. (NED) 1-40 
Stratford, Conn. (NED) 1-45 
Streambank Erosion under Special Attention (SAN) 
7-7 
320 Street N. Rock River, Rock Island, Ill. (NCR) 
23-17 
Strington, Ft. Chartres and Ivy Landing, Ill. (LMS) 
14-15 
Strong Creek, Idaho (NPS) 38-27 
Strube Lake - Cougar Additional Unit, (South Fork 
McKenzie) (Modification to Cougar Lake) 
Oreg. (NPP) 37-45 
Stuart, Ill. (NCR) 23-17 
Stuart, Va. (SAW) 6-13, 6-20 
Stuart Gulch Dam, Boise, Idaho (NPW) 39-14, 39-16 
Stumpy Point Bay, N.C. (SAW) 6-25 
Sturgeon Bay and Lake Michigan Ship Canal, Wis. 
(NCE) 21-24, 21-41, 21-53 
Sturgeon Point, Evans, N.Y. (NCB) 20-11, 20-33 
Sturgis, Ky. (ORL) 16-19, 16-24, 16-29 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
1-65

Island Drainage and Levee District No. 1, Ill. 
(NCR) 23-14, 23-16 
Sucker Brook Dam, Conn. (NED) 1-23, 1-43, 1-48 
Sudbury River, Mass. (NED) 1-24 
Sugar Creek, Bellbrook, Ohio (ORL) 16-31 
Sugar Creek, Valdosta, Ga. (SAJ) 9-54 
Sugar Creek Levee, Ind. (ORL) 16-21 
Sugar Creek Levee, Ill. (Wabash River) (ORL) 16-25 
Sugar Hill Reservoir, N.H. (NED) 1-45 
Suisun Bay Channel, Calif. (SPK) (SPN) 34-8, 35-33 
Suisun Channel, Calif. (SPK) (SPN) 34-8, 35-33 
Suisun Point Channel, Calif. (SPK) 35-33 
Sullivan Falls Harbor, Maine (NED) 1-40 
Sullivan Run, Butler, Penn. (ORP) 18-26 
Sulphur Branch, Euless, Tex. (SWF) 30-23 
Sulphur Creek, Heber Springs, Ark. (SWL) 28-25 
Sulphur River, Ark. and Tex. (LMN) 11-17 
Sulphur River Levees, Tex. (SWF) 30-22 
Sultan, Wash. (NPS) 38-29 
Summersville Lake, Ohio River Basin, W. Va. (ORH) 
17-9, 17-15, 17-19 
Sumner Parker Airport, Oreg. (NPP) 37-40 
Sumpawanus (Babylon Creek) Inlet, N.Y. (NAN) 2-35 
Sun Creek, Miss. (SAM) 10-48 
Sun River, Great Falls, Mont. (MRO) 26-18 
Sunbright, Tenn. (Whiteoak Creek) (ORN) 15-19 
Sunbury, Pa. (NAB) 4-39, 4-42 
Sunken Vessel Removal 51-1 
Sunrise Park, Lake Bluff, Ind. (NCC) 22-6 
Sunset Harbor (Bolsa Chica Bay), Calif. 33-23 
Supervision of New York Harbor (Prevention of 
Obstruction and Injurious Deposits) (NAN) 2-15 
Supervision of Norfolk Harbor (Prevention of Obstruction 
and Injurious Deposits) (NAO) 5-7 
Supervisor of New York Harbor (NAN) 2-25, 2-32 
Surry Mountain Lake, N.H. (NED) 1-15, 1-23, 1-29, 
1-48 
Surveillance of Northern Boundary Waters (NCE) 
21-28, 21-41 
Surveys 
Alaska District (NPA) 40-7 
Albuquerque, N. Mex., District (SWA) 32-10 
Baltimore, Md., District (NAB) 4-22 
Buffalo, N.Y., District (NCB) 20-16 
Chicago, Ill., District (NCC) 22-8 
Detroit, Mich., District (NCE) 21-30 
Fort Worth, Tex., District (SWF) 30-13 
Galveston, Tex., District (SWG) 31-13 
Huntington, W. Va., District (ORH) 17-11 
Jacksonville, Fla., District (SAJ) 9-25 
Kansas City, Mo., District (MRK) 27-20 
Little Rock, Ark., District (SWL) 28-10 
Los Angeles, Calif., District (SPL) 33-9 
Louisville, Ky., District (ORL) 16-12 
Memphis, Tenn., District (LMM) 13-2, 13-6 
Mississippi River Commission (MR+T) 42-46 
Mobile, Ala., District (SAM) 10-27 
Nashville, Tenn., District (ORN) 15-1, 15-8 
New England Division (NED) 1-24 
New Orleans District (LMN) 11-20 
New York District (NAN) 2-37 
Norfolk, Va., District (NAO) 5-10, 5-14 
Omaha, Nebr., District (MRO) 26-21 
Pacific Ocean Division (POD) 36-5 
Philadelphia, Penn., District (NAP) 3-14 
Pittsburgh, Penn., District (ORP) 18-10 
Portland, Oreg., District (NPP) 37-7, 37-21 
Rock Island, Ill., District (NCR) 23-6 
Sacramento, Calif., District (SPK) 35-22 
San Francisco, Calif., District (SPN) 34-5 
Savannah, Ga., District (SAS) 8-9 
Seattle, Wash., District (NPS) 38-11 
St. Louis, Mo., District (LMS) 14-16 
St. Paul, Minn., District (NCS) 24-21, 24-35 
Tulsa, Okla., District (SWT) 29-10, 29-22 
Vicksburg, Miss., District (LMK) 12-22 
Walla Walla, Wash., District (NPW) 39-7 
Wilmington, N.C., District (SAW) 6-17 
Susquehanna Basin at Harrisburg, Pa. (NAB) 4-22 
Susquehanna River above and below Havre De 
Grace, Md. (NAB) 4-38 
Susquehanna River at Williamsport, Pa. (NAB) 4-38 
Susquehanna River Flood Control Projects, N.Y. and 
Pa. (NAB) 4-18, 4-36 
Sutton Lake, Ohio River Basin, W. Va. (ORH) 17-9, 
17-15, 17-19 
Suwannee River, Fla. (SAJ) 9-47 
Swan Creek, Toledo, Ohio (NCB) 20-39 
Swan Creek Bank Stabilization, Taney County, Mo. 
(SWL) 28-17 
Swanton Harbor, Vt. (NAN) 2-38 
Sweetwater Creek, N.C. (SAW) 6-28 
Sweetwater River, Sweetwater River Basin, Calif. 
(SPL) 33-7, 33-14, 33-22 
I-66

INDEX 
Swift Creek, N.C. (SAW) 6-25 
Swift Creek, Pitt and Craven Counties, N.C. (SAW) 
6-27 
Swinomish Channel, Wash. (NPS) 38-6, 38-16, 38-21 
Swoyersville, and Forty Fort, Pa. (NAB) 4-39, 4-42 
Sykesville, Pa. (ORP) 18-20 
Syracuse, Ohio (ORH) 17-22 
Syracuse, Oswego River Basin, N.Y. (NCB) 20-37 
T 
Table Rock Lake, Mo. (SWL) 28-10, 28-13, 28-24 
Tacoma, Puyallup River, Wash. (NPS) 38-9, 38-17, 
38-22 
Tacoma Harbor, Wash. (NPS) 38-24 
Tahlequah Creek (SWT) 29-21 
Tahola, Wash. (NPS) 38-27 
Talkeetna River, Alaska (NPA) 40-13 
Tallabinella Creek, Miss. (SAM) 10-17, 10-34, 10-45 
Tallahala Creek Dam, Pascagoula River, Miss. (SAM) 
10-18, 10-34, 10-45 
Tallahatchie and Coldwater Rivers, Miss. (LMK) 
12-15 
Tallapoosa River, Ala. (SAM) 10-47 
Tallow Hill, Ga. (SAS) 8-16 
Talofofo Bay Shore Protection, Guam (POD) 36-13 
Tama, Iowa (NCR) 23-17 
Tamaqua, Pa. (NAP) (NAB) 3-26, 4-22, 4-29, 4-36 
Tampa and Hillsborough Bays, Fla. (SAJ) 9-38 
Tampa Harbor, Fla. (SAJ) 9-17, 9-29, 9-38, 9-39 
Tampa Harbor Branch Channels (SAJ) 9-40 
Tampa Harbor East Bay Channel (SAJ) 9-40 
Tangeman, Little Nemaha River, Nebr. (MRO) 26-20 
Tangier Channel, Va. (NAO) 5-7, 5-13, 5-17 
Tangier Island Shore Protection (NAO) 5-8, 5-13, 
5-17 
Tangipahoa River, La. (LMN) 11-17 
Tanque Verde Creek, Tucson, Ariz. (SPL) 33-28 
Tar River, N.C. (SAW) 6-27 
Tar River and Tributaries, N.C. (SAW) 6-27 
Tar River, Princeville, N.C. (SAW) 6-27 
Tarentum, Pa. (ORP) 18-20 
Tarrytown Harbor, N.Y. (NAN) 2-35 
Taskinas Creek, Va. (NAO) 5-19 
Tau-Faleaso, Tau Island, American Samoa (POD) 
36-14 
Tau Small Boat Harbor, American Samoa (POD) 
36-10 
Taunton River, Mass. (NED) 1-40 
Tawas Bay Harbor, Mich. (NCE) 21-55, 21-60 
Tawas City, Mich. (NCE) 21-26 
Taylor Point, Bourne, Mass. (NED) 1-46 
Taylors Bayou, Tex. (SWG) 31-12, 31-17, 31-28 
Taylorsville, Ky. (Salt River) (ORL) 16-19, 16-24, 
16-29 
Taylorsville Lake, Ky. (ORL) 16-10, 16-16 
Teche-Vermilion Basins, La. (MR+T) 42-14, 42-30 
Telegraph Canyon Creek, Chula Vista, Calif. (SPL) 
33-8, 33-14, 33-22 
Tell City, Ind. (ORL) 16-19, 16-24, 16-29 
Temple Creek, Elk Creek, Penn. (NCB) 20-39 
Ten Mile Creek, De Sota, Tex. (SWF) 30-23 
Ten Mile Creek, Duncanville, Tex. (SWF) 30-23 
Tenants Harbor, Maine (NED) 1-40 
Tenkiller Ferry Lake, Okla. (SWL) (SWT) 28-22, 
29-9, 29-16, 29-18, 29-20 
Tenmile Creek at Marianna, Pa. (ORP) 18-20 
Tennessee River, Tenn., Ala., and Ky. (ORN) 15-3, 
15-9, 15-11, 15-17, 15-18 
Tennessee-Tombigbee Waterway, Ala. and Miss. 
(ORN) (SAM) 10-13, 10-33, 10-43, 10-53, 15-4, 
15-9,15-12 
Tennessee-Tombigbee Wildlife Mitigation (SAM) 
10-44 
Tensas Basin, Ark. and La. (MR+T) 42-6, 42-15, 
42-30 
Tensas River and Bayou, Macon, La. (LMK) 12-15 
Tensas River National Wildlife Refuge (MR+T) 42-30 
Terrain Analysis Center 51-1 
Terre Haute, Ind. (ORL) 16-21 
Terre Haute, Ind. (Conover Levee) (Wabash River) 
(ORL) 16-19, 16-29 
Terre Noire Creek, Ark. (LMK) 12-17 
Terry, David D., Lock and Dam, Ark. (SWL) 28-19 
Teton River, Idaho (NPW) 39-12, 39-16 
Texas City and Vicinity, Tex., Hurricane-Flood 
Protection (SWG) 31-12, 31-17, 31-28 
Texas City Channel, Tex. (SWG) 31-7, 31-16, 31-26, 
31-32, 31-39 
Thames River, Conn. (NED) 1-40, 1-45 
Thames River Basin, Conn., R.I., and Mass. (NED) 
1-21, 1-23, 1-52 
Thatcher Brook, Hill Street Bridge, Gowanda, N.Y. 
(NCB) 20-39 
The Dalles Lock and Dam-Lake Celilo, Wash. and 
Oreg. (NPP) 37-21, 37-28, 37-36, 37-47 
I-67

The Island Lake, Vt. (NED) 1-45 
The Jump-New Orleans, La. (MR+T) 42-11 
The Water Resources Support Center 47-1 
Thebes-Rock Island, Ill. (MR+T) 42-12 
Thimble Shoal Channel, Va. (NAO) 5-6, 5-13, 
5-17 
Thirty Mile Creek, Harlem, Mont. (MRO) 26-23 
Thomas Basin, Ketchiken, Ark. (NPA) 40-5, 40-9, 
40-11 
Thomaston Dam, Conn. (NED) 1-18, 1-30, 1-50 
Thoroughfare Swamp, N.C. (SAW) 6-28 
Three Forks, Mont. (MRO) 26-18 
Three Islands Reservoir, Tenn. (ORN) 15-14 
Three Mile Creek, Mobile, Ala. (SAM) 10-18, 10-28, 
10-34, 10-45 
Three Rivers, Mass. (NED) 1-23, 1-43, 1-49 
Three Rivers, Tex. (SWG) 31-31 
Thumpertown Beach, Eastham, Mass. (NED) 1-45 
Thurman-Hamburg Levee (MRO) 26-18 
Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, 
La. (LMN) 11-17 
Ticonderoga River, N.Y. (NAN) 2-38 
Tijuana River Basin, Calif. (SPL) 33-26 
Tilghman Island Harbor, Md. (NAB) 4-38, 4-41 
Tillamook Bay and Bar, Oreg. (NPP) 37-8, 37-25, 
37-33, 37-42 
Timber Creek, Double Oak, Tex. (SWF) 30-23 
Tinker Creek and Tributaries, Va. (SAW) 6-31 
Tioga-Hammond Lakes, Pa. (NAB) 4-19, 4-28 
Tionesta Lake, Ohio River Basin, Pa. (ORP) 18-8, 
18-13, 18-18, 18-25 
Tiptonville-Obion River (MR+T) 42-12, 42-29 
Tishtony Creek, Mantachie, Miss. (SAM) 10-49 
Toad Suck Ferry Lock and Dam, Ark. (SWL) 28-4, 
28-19 
Tocks Island Lake, Pa., N.J., and N.Y. (NAP) 3-27 
Tocks Island (Relocation of U.S. Route 209 only), 
Pa. (NAP) 3-27 
Todd Swamp, S.C. (SAN) 7-15 
Toledo Harbor, Ohio (NCB) 20-10, 20-20, 20-32 
Tolovana River, Alaska (NPA) 40-13 
Tolu, Ky. (ORL) 16-21, 16-26 
Tom Jenkins Dam, Ohio River Basin, Ohio (ORH) 
17-19 
Tom Jenkins Reservoir, Ohio River Basin, Ohio 
(ORH) 17-10, 17-14 
Tomahawk Lake, Blue River, Kan. (MRK) 27-17 
Tomanovich-Salmon City, Idaho (NPW) 39-12, 39-15 
Tombigbee River, (East Fork) Miss. and Ala. (SAM) 
10-19, 10-34, 10-45 
Tombigbee River at Columbus Port, Miss. (SAM) 
10-13, 10-33, 10-43 
Tombigbee River Tributaries, Miss. and Ala. (SAM) 
10-19, 10-34, 10-45 
Toms River, NJ. (NAP) 3-24, 3-27 
Tongue Point, Oreg. (NPP) 37-42 
Tongue River Lake, N. Dak. (NCS) 24-28 
Topeka, Kansas River, Kan. (MRK) 27-16, 27-19 
Toppenish/Simcoe Creek, Wash. (NPS) 38-29 
Topsail Beach and Surf City, N.C. (SAW) 6-28 
Toronto Lake, Kan. (SWL) (SWT) 28-22, 29-8, 
29-15, 29-18, 29-20 
Torrington, East Branch, Conn. (NED) 1-32, 1-43, 
1-50 
Torringon, West Branch, Conn. (NED) 1-23, 1-43, 
1-50 
Totuskey Creek, Va. (NAO) 5-19 
Touchet River, Waitsburg, Wash. (NPW) 39-15, 
39-16, 39-17 
Toulmins Spring Branch, Pritchard, Ala. (SAM) 
10-49 
Toussaint River, Carrol Twsp, Ohio (NCB) 20-38 
Towanda Lake, Kan. (SWT) 29-19 
Town Beach, Plymouth, Mass. (NED) 1-41 
Town Beaches, Conn. (NED) 1-46 
Town Bluff Dam-B. A. Steinhagen Lake, Tex. 
(SWF) 30-12, 30-17, 30-20 
Town Bluff Hydropower, Tex. (SWF) 30-12, 30-17, 
30-20 
Town Branch Creek, Lockhart, Tex. (SWF) 30-23 
Town Brook, Quincy and Braintree, Mass. (NED) 
1-22, 1-32, 1-37 
Town Creek, Md. (NAB) 4-38 
Town Creek, S.C. (SAN) 7-6, 7-9, 7-12 
Town Creek, Americus, Ga. (SAM) 10-48 
Town Creek, Harrodsburg, Ky. (ORL) 16-19 
Town Neck Beach, Sandwich, Mass. (NED) 1-45 
Town River Bay, Mass. (NED) 1-24 
Townsend Inlet and Seven Mile Beach, N.J. (NAP) 
3-26 
Townshend Lake, Vt. (NED) 1-15, 1-29, 1-48 
Trabuco Dam, Calif. (SPL) 33-27 
Trace Creek, Waverly Park, Tenn. (ORN) 15-19 
Tradewater River, Ky. (ORL) 16-18 
Tranquitas Creek, Kingsville, Tex. (SWG) 31-31 
Tranters Creek, N.C. (SAW) 6-28 
I-68

Trask River, Oreg. (NPP) 37-40 
Treasure Island, Mo. (LMM) 13-5 
Treatment of Yuba River Debris Situation-Restraining 
Barriers Calif. (CDC) 53-2, 53-5 
Tred Avon River, Md. (NAB) 4-11, 4-26, 4-34 
Trempealeau River at Arcadia, Wis. (NCS) 24-33, 
24-34 
Trent River, N.C. (SAW) 6-25, 6-27, 6-28 
Trenton Lake, Thompson River, Mo. (MRK) 27-16 
Trexler Lake, Pa. (NAP) 3-27 
Tributaries and Canals of Boeuf River (MR+T) 42-16 
Tributary of Kill Creek, DeSoto, Kan., Sewage 
Treatment Plant (MRK) 27-21 
Trim Cane Creek, Miss. (SAM) 10-48 
Trimble, James W., L&D (No. 13) Ark. (SWL) 28-20 
Trinidad Lake, Colo. (SWA) 32-7, 32-11 
Trinity River and Tributaries, Tex. (SWG) 31-6, 31-8, 
31-27, 31-32, 31-39 
Trinity River Project, Tex. (SWF) 30-2, 30-15, 30-21 
Triplett Creek, Morehead, Ky. (Licking River) (ORL) 
16-19, 16-30 
Tri-Pond Levee, Ill. (ORL) 16-21, 16-25 
Tri-Pond Levee, Ill. (Wabash River) (ORL) 16-25 
Trout Brook, Dover, Mass. (NED) 1-47 
Troublesome Creek, Hindman, Ky. (ORL) 16-30 
Troy, Ind. (ORL) 16-21, 16-25 
Truckee Meadows, Nev. (SPK) 35-23, 35-30 
Truckee River and Tributaries, Calif. and Nev. (SPK) 
35-34 
Truman, Harry S., Dam and Reservoir, Osage River, 
Mo. (MRK) 27-8, 27-11, 27-15, 27-16, 27-19 
Trumbull Lake, Conn. (NED) 1-43 
Trussville, Ala. (SAM) 10-48 
Truth or Consequences (Hot Springs) Unit, N. Mex. 
(SWA) 32-6, 32-11, 32-13, 32-14 
Tualatin, Oreg. (NPP) 37-40 
Tucannon River, Camp Wooten, Wash. (NPW) 39-14 
Tucannon River, Wooten, Wash. (NPW) 39-15, 39-17 
Tuckahoe River, Md. (NAB) 4-38 
Tucker Creek, Conway, Ark. (SWL) 28-25 
Tuckerton Creek, NJ. (NAP) 3-24 
Tug and Levisa Forks of the Big Sandy River and 
Cumberland River, W. Va., Va., and Ky. (ORN) 
15-5, 15-9 
Tully Lake, Mass. (NED) 1-16, 1-23, 1-29, 1-48 
Tulsa and West Tulsa Levee, Okla. (SWT) 29-19, 
29-20, 29-21 
Turkey Creek, Okla. (SWT) 29-21 
Turkey Creek, S.C. (SAN) 7-15 
Turkey River, Jefferson Township, Iowa (NCR) 23-17 
Turner Creek, Corinth, Miss. (LMM) 13-5 
Turner Prairie, Oreg. (NPP) 37-41 
Turning Basin Extension (SWG) 31-36 
Turpentine Run, St. Thomas, V. I. (SAJ) 9-54 
Turnout Channels, E. Side of Main Channel (SWG) 
31-36 
Turnout Channels, W. Side of Main Channel (SWG) 
31-36 
Tutuila Island Canneries to Breakers Pt., American 
Samoa (POD) 36-6 
Tutuilla Creek, Oreg. (NPP) 37-43 
Turtle Creek, Pa. (ORP) 18-20 
Turtle Creek Channel Improvement, Yukon, Okla. 
(SWT) 29-19 
Tuskahoma Lake, Okla. (SWT) 29-19 
Tuttle Creek Lake, Big Blue River, Kan. (MRK) 
27-6, 27-11, 27-15, 27-19 
Tuttle Creek Lake Road and Bridge, Kan. (MRK) 
27-16, 27-19 
Tuttle Creek Lake (Road Improvement), Kan. (MRK) 
27-17, 27-19 
Twelvemile Bayou, La. (LMN) (LMK) 11-19, 12-20, 
12-21 
Twenty Mile Creek, Airport Rd. Bridge, Frankstown, 
Miss. (SAM) 10-48 
Twin Valley Lake, Wild Rice River, Minn. (NGS) 
24-18, 24-24 
Twitch Cove and Big Thorofare, Md. (NAB) 4-11, 
4-26, 4-34 
Two Harbors, Minn. (NCE) 21-24, 21-41, 21-53 
Two Rivers Dam, N. Mex. (SWA) 32-8, 32-12 
Two Rivers Harbor, Wis. (NCE) 21-24, 21-41, 21-53 
Tyaskin Creek, Md. (NAB) 4-38 
Tybee Island, Ga. (SAS) 8-6, 8-11, 8-14 
Tygart Lake, W. Va. (ORP) 18-3, 18-11, 18-16 
Tygart River, Phillipi, W. Va. (ORP) 18-26 
Tylers Beach, Va. (NAO) 5-19, 5-21 
Tyrone, Pa. (NAB) 4-39 
U 
Umatilla Harbor, Oreg. (NPP) 37-37 
Umatilla River (Echo), Oreg. (NPP) (NPW) 37-40, 
37-41, 39-15 
Umpqua River, Oreg. (NPP) 37-8, 37-25, 37-33 
I-69 
I1 JJLA

Unadilla, N.Y. (NAB) 4-39, 4-42 
Union City, Penn. (ORP) 18-25 
Union City Dam, Pa. (ORP) 18-8, 18-13, 18-18 
Union Lake, Mo. (LMS) 14-15 
Union River, Maine (NED) 1-40 
Union Township Drainage District, Mo. (NCR) 23-14 
Union Village Dam, Vt. (NED) 1-16, 1-29, 1-48 
Uniontown, Ky. (ORL) 16-19, 16-24, 16-29 
Uniontown, Penn. (ORP) 18-20 
Uniontown, Penn. (Monongahela River Basin) (ORP) 
18-24 
Uniontown Locks and Dam, Ky. (ORL) 19-9 
University Wash and Spring Brook, Riverside, Calif. 
(SPL) 33-27 
Unnamed Tributary to Pymatuning (ORP) 18-26 
Upper Chipola River, Fla., from Mariana to its mouth 
(SAM) 10-47 
Upper Gordons Creek, Hattiesburg, Miss. (SAM) 
10-49 
Upper Grand River, Mo. (MRK) 27-16 
Upper Grays River Area, Wash. (NPP) 37-38 
Upper Iowa River, Iowa (NCS) 24-28 
Upper Little Arkansas River, Kan. (SWT) 29-19 
Upper Machodoc Creek, Va. (NAB) 4-38 
Upper Marlboro, Md. (NAB) 4-39, 4-42 
Upper Mississippi River Environmental Management 
Program (LMS) 14-6 
Upper Mississippi River Environmental Management 
Program, Ill., Iowa, Minn., Mo., Wis. (NCR) 23-3, 
23-7, 23-10 
Upper Pointe Coupee Loop Area (MR+T) 42-13 
Upper River Rouge, Mich. (NCE) 21-56 
Upper Thorofare, Md. (NAB) 4-38 
Upper White Oak Bayou, Tex. (SWG) 31-7, 31-12, 
31-28 
Upper White River, Ark. (SWL) 18-16 
Upper Zacate Creek, Loredo, Tex. (SWF) 30-23 
Urban Areas at Alton, Ill. (LMS) 14-15 
Urbanna Creek, Va. (NAO) 5-19 
U.S. Army Cold Regions Research and Engineering 
Laboratory 44-1, 44-2 
U.S. Army Construction Engineering Research 
Laboratory 43-1 
U.S. Army Engineer Topographic Laboratories 46-1 
U.S. Army Engineer Waterways Experiment Station 
45-1 
U.S. Highway 51, Tenn. (LMM) 13-5 
Utica, Ind. (ORL) 16-22, 16-26 
Utica, Ohio (ORH) 17-21, 17-23 
V 
Vaipito Stream, American Samoa (POD) 36-15 
Valdez Harbor, Alaska (NPA) 40-12, 40-14 
Valley City Drainage and Levee District, Ill. (LMS) 
14-15 
Valley Drainage and Levee District, Ill. (NCR) 23-16 
Valleyview, Ill. (NCC) 22-8 
Van Buren, Arkansas River, Ark. (SWL) 28-17 
Van Meter, Iowa (NCR) 23-14, 23-16 
Vanceburg, Ky. (ORH) 17-21 
Vancouver Lake Area, Wash. (NPP) 37-39 
Vatia Area, American Samoa (POD) 36-11 
Vaughn, Mont. (MRO) 26-16, 26-18 
Velva, N. Dak. (NCS) 24-28, 24-33 
Ventnor, Margate and Longport, N.J. (NAP) 3-26 
Ventura Harbor, Calif. (SPL) 33-4, 33-12, 33-20, 
33-28 
Ventura-Pierpont Area, Calif. (SPL) 33-24 
Ventura River Basin, Calif. (SPL) 33-26 
Verdigris River, Kan. (SWT) 29-21 
Vermilion Harbor, Ohio (NCB) 20-35 
Vermillion River and Tribs., S. Dak. (MRO) 26-17 
Vermillion River, Hastings, Minn. (NCS) 24-28, 
24-33 
Vermillion River, Pontiac, Ill. (NCR) 23-17 
Vermillion River, Vermilion (MRO) 26-19 
Verona Lake, Va. (NAB) 4-39 
Veteran's Memorial Levee, Mississippi River, 
Hastings, Minn. (NCS) 24-28, 24-33 
Vevay, Ind. (ORL) 16-22, 16-25 
Vicinity of Nehalem, Oreg. (NPP) 37-40 
Vicksburg District, Bank Revetments and Dikes, 
Mississippi River (MR+T) 42-36 
Vicksburg District, Bank Revetments and Dikes, Red 
River (MR+T) 42-39 
Vicksburg District, Channel Improvements (FY 1988) 
(MR+T) 42-53 
Vicksburg District, levees (MR+T) 42-48, 42-62 
Vicksburg Harbor, Miss. (MR+T) 42-11, 42-30, 42-31 
Vicksburg Lake View, Miss. (MR+T) 42-11 
Victory Lake, Vt. (NED) 1-45 
Villa Park Dam, Calif. (SPL) 33-27 
I-70

INDEX 
Village Creek, Birmingham, Ala. (SAM) 10-19, 
10-34, 10-45 
Village Creek, S.C. (SAN) 7-14 
Village Creek, Jackson-Lawrence Counties, Ark. 
(SWL) 28-17 
Village Creek, White River, and Mayberry Levee 
District, Ark. (SWL) 28-17 
Village of New Athens, Ill. (LMS) 14-15 
Village of Saxtons, Vt. (NED) 1-43 
Vince and Little Vince Bayous, Tex. (SWG) 31-13, 
31-17, 31-28 
Vincennes, Ind. (Wabash River) (ORL) 16-19, 16-20, 
16-22, 16-24, 16-26, 16-29 
Vineyard Haven, Mass. (NED) 1-40 
Vinton Waterway, La. (LMN) 11-17 
Virginia Beach, Va. (NAO) 5-8, 5-14, 5-17 
Virginia Beach Streams Canal Number 2, Va. (NAO) 
5-9, 5-14, 5-17 
Virginia Key and Key Biscayne, Fla. (SAJ) 9-48 
Volga, Iowa (NCR) 23-16
W 
W. Br. Limeston Creek, Manlius, N.Y. (NCB) 20-39 
W.D. Mayo L and D (No. 14) (SWL) 28-20, 29-20 
W. Kerr Scott Dam and Reservoir, N.C. (SAW) 6-14, 
6-17, 6-20 
W.P. Franklin Lock & Dam (SAJ) 9-49 
Wabash River, Ind. (ORL) 16-27, 16-30, 16-31 
Wabash Railroad Bridges, Illinois River, Meredosia, 
and Valley City, Ill. (LMS) 14-13 
Wabash River Basin, Ind., Ill., and Ohio (ORL) 16-18 
Wabasha Harbor, Minn. (NCD) 25-7, 25-10 
Waccamaw River, N.C. and S.C. (SAN) 7-14 
Waccamaw River and Seven Creeks, N.C. and S.C. 
(SAN) (SAW) 6-27, 7-14 
Waco Lake, Tex. (SWF) 30-10, 30-21 
Wahkiakum County Consolidated Diking District No. 
1, Wash. (NPP) 37-38, 37-44 
Wahkiakum County Diking District 4, Wash. (NPP) 
37-39, 37-44 
Waianae Small Boat Harbor, Oahu, Hawaii (POD) 
36-10 
Waiawa Stream, Oahu, Hawaii (POD) 36-15 
Waikiki Beach, Oahu, Hawaii (POD) 36-11 
Wailoa Stream and Tributaries, Hawaii, Hawaii (POD) 
36-12, 36-15 
Waimea Beach, Kauai, Hawaii (POD) 36-13 
Waimea River, Kauai, Hawaii (POD) 36-5, 36-8, 
36-15 
Wake Island Harbor, Wake Island (POD) 36-13 
Waldo Lake Tunnel and Reregulating Works, Oreg. 
(NPP) 37-45 
Waldport, Oreg. (NPP) 37-43 
Wallabout Channel, N.Y. (NAN) 2-35 
Wallace, W. Va. (ORP) 18-20 
Wallace Channel, Pamlico Sound, N.C. (SAW) 6-25 
Wallace Lake, La. (LMK) 12-16, 12-19, 12-20, 12-21 
Wallis Sands State Beach, Rye, N.H. (NED) 1-41 
Wallisville Lake, Tex. (SWG) 31-9 
Wallkill River, N.Y. (NAN) 2-39 
Wallowa River, Weaver Bridge, Oreg. (NPW) 39-15 
Walluski River, Oreg. (NPP) 37-38 
Walnut Bottom Run, Beaver Falls, Penn. (ORP) 18-26 
Walnut Creek, Calif. (SPK) 35-18, 35-27 
Walnut Creek, Clive, Iowa (NCR) 23-17 
Walnut Creek, Hood County, Tex. (SWF) 30-23 
Walnut Creek, Sequin, Tex. (SWF) 30-23 
Walnut Creek Tribs., Austin, Tex. (SWF) 30-23 
Walnut River, Kan. (SWT) 29-21 
Walter, Francis E. Dam, Pa. (NAP) (NAB) 3-17, 
3-22, 4-20, 4-22, 4-29, 4-36 
Walter F. George Lock and Dam, Ala. and Ga. (SAM) 
10-26, 10-35, 10-46 
Wapello Co., Iowa (NCR) 23-17 
Wappinger Creek, N.Y. (NAN) 2-35, 2-36 
Ware, Mass. (NED) 1-23, 1-43, 1-49 
Wareham Harbor, Mass. (NED) 1-40 
Wareham-Marion, Mass. (NED) 1-45 
Wares Creek, Bradenton, Fla. (SAJ) 9-54 
Warner Rd., St. Paul, Minn. (NCS) 24-33 
Warner Road, Mississippi River, St. Paul, Minn. 
(NCS) 24-28 
Warren River, R.I. (NED) 1-40 
Warrenton Diking Districts 1, 2, and 3, Oreg. (NPP) 
37-38, 37-43 
Warroad Harbor and River, Minn. (NCS) 24-2, 24-22, 
24-26, 24-30 
Warroad River and Bulldog Creek, Minn. (NCS) 
24-30 
Warsaw Harbor, Ill. (NCD) 25-8 
Warwick Cove, R.I. (NED) 1-40 
Warwick River, Md. (NAB) 4-38 
Warwood, W. Va. (OPR) 18-21 
1-71

Washington, D.C. and Vicinity (NAB) 4-22, 4-39 
Washington, Pa. (ORP) 18-20 
Washington Aqueduct (NAB) 4-21 
Washington Canal and South River, NJ. (NAN) 2-35 
Washington Harbor, D.C. (NAB) 4-12, 4-26, 4-35 
Washington Island, Wis. (NCE) 21-55 
Washington Island (Harbors at Wisconsin) (NCE) 
21-60 
Washita River, Okla. (SWT) 29-21 
Washougal Area Levees, Wash. (NPP) 37-39 
Water Resources Support Center (WRSC) 47-1 
Water Valley, Ark. and Mo. (SWL) 28-18 
Water Works, Park and Pool, Wellsburg, W. Va. 
(ORP) 18-26 
Waterbury, Conn. (NED) 1-23 
Waterbury, Vt. (NAN) 2-38 
Waterbury Reservoir, Vt. (NAN) 2-36 
Waterbury-Watertown, Conn. (NED) 1-43, 1-50 
Wateree River, S.C. (SAN) 7-14 
Waterford, N.Y. (NAN) 2-38 
Waterloo, Elkhorn River, Nebr. (MRO) 26-20 
Waterloo, Iowa (Bridges) (NCR) 23-14, 23-16 
Waterloo, Nebr. (MRO) 26-16 
Waterman Creek, O'Brien Co., Iowa (MRO) 26-23 
Waterway Connecting Pamlico Sound and Beaufort 
Harbor, S.C. (SAW) 6-9, 6-19, 6-23, 6-29 
Waterway Connecting Port Townsend and Oak Bay, 
Wash. (NPS) 38-24 
Waterway Connecting Swanquarter Bay with Deep 
Bay, N.C. (SAW) 6-25 
Waterway from Empire, La., to Gulf of Mexico 
(LMN) 11-17 
Waterway from Indian River Inlet to Rehoboth Bay, 
Del. (NAP) 3-24 
Waterway from Intracoastal Waterway to Bayou 
Dulac, La. (Bayous Grand Caillou and LeCarpe, 
La.) (LMN) 11-5, 11-11, 11-14 
Waterway from Little Choptank River to Choptank 
River, Md. (NAB) 4-40 
Waterway from White Lake to Pecan Island, La. 
(LMN) 11-17 
Waterway-Norfolk, Va. to Sounds of N.C. (SAW) 
6-25 
Waterway on the Coast of Virginia (NAO) 5-7, 5-13, 
5-17, 5-21 
Watkins Glen, N.Y. (NCB) 20-40 
Watkins-Waubonsie Ditch Levees (MRO) 26-18 
Watts Bar Lock and Dam, Tenn. (ORN) 15-17 
Waukegan Harbor, Ill. (NCC) 22-5, 22-11, 22-14, 
22-16 
Waurika Lake, Okla. (SWT) 29-8, 29-15 
Waverly, W. Va. (ORH) 17-22 
Wax Lake Outlet, La. (MR+T) 42-14 
Waycake Creek, NJ. (NAN) 2-35 
Webb District Improvement Co., Oreg. (NPP) 37-38 
Webbers Falls Lock and Dam, Okla. (SWL) (SWT) 
28-20, 29-10, 29-16, 29-18, 29-20 
Weber River and Tributaries, (Morgan Co.) Utah 
(SPK) 35-36 
Weber River at Oakley, Utah (SPK) 35-40 
Weber River near Morgan City, Utah (SPK) 35-40 
Weeks Bay, Ala. (SAM) 10-49 
Weiser River, Weiser Area, Idaho (NPW) 39-12, 
39-15, 39-16 
Weiser River, Ind. Cambridge-Midvale (NPW) 39-16 
Welcome Creek, S.C. (SAN) 7-16 
Welles Harbor, Midway Island (POD) 36-10 
Wellfleet Harbor, Mass. (NED) 1-40 
Wells Harbor, Maine (NED) 1-9, 1-27, 1-35, 1-40 
Wellsburg, W. Va. (ORP) 18-21 
Wellsville, Ohio, Sec. I (ORP) 18-20, 18-24 
Wellsville, Ohio, Sec. II (ORP) 18-20, 18-24 
Wenatchee Canyons 1 and 2, Wash. (NPS) 38-27 
Wessagusset Beach, Weymouth, Mass. (NED) 1-41 
West Antioch Creek Vicinity, Antioch, Calif. (SPK) 
35-40 
West Atchafalaya Basin, La. (MR+T) 42-13 
West Atchalafaya Floodway, La. (MR+T) 42-13, 
42-14 
West Atchafalaya Floodway between Red River and 
Alabama Bayou (MR+T) 42-13 
West Bank Hurricane Protection Levee, Jefferson 
Parish, La. (LMN) 11-15 
West Branch Chisholm Creek Channel Improvement, 
Kan. (SWT) 29-19 
West Branch of Susquehanna River, Pa. (NAB) 4-19, 
4-36 
West Branch, Westfield River, Mass. (NED) 1-43 
West Bridgewater, Pa. (ORP) 18-21 
West Brookfield Reservoir, Mass. (NED) 1-45 
West Cache Creek, Okla. (SWT) 29-21 
West Canaan Lake, N.H. (NED) 1-45 
West Des Moines, Iowa (NCR) 23-8, 23-12 
West Fork, W. Va (ORH) 17-21 
I-72

INDEX 
West Fork, Foster Creek, Wash. (NPS) 38-27 
West Fork Big Blue River, Fillmore Co., N.E., Bridge 
No. 205 (MRK) 27-21 
West Fork Big Blue River, Fillmore Co., N.E., Bridge 
No. 1125 (MRK) 27-21 
West Fork Big Blue River, Fillmore Co., N.E., County 
Rd. (MRK) 27-21 
West Fork Grand River, Ringgold Co., Iowa, Parker 
Bridge (MRK) 27-21 
West Fork Grand River, Ringgold Co., Iowa, Redding 
Bridge (MRK) 27-21 
West Fork of Mill Creek Lake, Ohio (ORL) 16-11, 
16-16 
West Glendive, Mont. (MRO) 26-18 
West Harbor, Ohio (NCB) 20-10, 20-20, 20-33 
West Haven Beaches, Conn. (NED) 1-46 
West Hickman Area, Hickman, Ky. (LMM) 13-5 
West Hill, Worcester, Mass. (NED) 1-47 
West Hill Dam, Mass. (NED) 1-11, 1-27 
West Kentucky Tributaries, Ky. (MR+T) 42-10, 42- 
19, 42-30, 42-55 
West Little Pine Creek, Etna, Penn. (ORP) 18-26 
West Magnesia Canyon Channel, Calif. (SPL) 33-8, 
33-15, 33-23 
West Matanzas Drainage and Levee District, Ill. 
(NCR) 23-16 
West Memphis Ark. and Vicinity (MR+T) 42-30 
West Muddy Creek and Marys River, Oreg. (NPP) 
37-41 
West Nishnabotna River, Atlantic, Iowa (MRO) 26-23 
West Nishnabotna River, Malvern, Iowa (MRO) 26-23 
West Nishnabotna River, Mills Co. Bridge, near 
Hastings, Iowa (MRO) 26-20 
West Nishnabotna River, Mills Co. Bridge, near 
Malvem, Iowa (MRO) 26-20 
West Nishnabotna River near Hastings, Iowa (MRO) 
26-20 
West of Morrilton, Arkansas River, Ark. (SWL) 28-18 
West Oneonta Lake, N.Y. (NAB) 4-41 
West Papillion Creek, Douglas, Douglas Co., Nebr. 
(MRO) 26-23 
West Point, Chattahoochee River, Ga. (SAM) 10-48 
West Point, Elkhorn River, Nebr. (MRO) 26-20 
West Point, Ky. (ORL) 16-20, 16-26 
West Point, Nebr. (MRO) 26-16 
West Point Lake, Ga. and Ala. (SAM) (SAS) 8-9 
West Point Lake, Chattahoochee River Basin, Ga. and 
Ala. (SAM) 10-26, 10-36, 10-46 
West River, Tripp Co., S. Dak. (MRO) 26-23 
West River, West Haven, Conn. (NED) 1-22, 1-32, 
1-37 
West Run, Munhall, Penn. (ORP) 18-26 
West Springfield, Mass. (NED) 1-16, 1-23, 1-29, 1-36, 
1-49 
West Stewartstown, N.H. (NED) 1-23 
West Tennessee Tributaries, Tenn. (MR+T) 42-9, 
42-18, 42-30, 42-55 
West Terre Haute, Ind. (Wabash River) (ORL) 16-19, 
16-24, 16-29 
West Thompson Lake, Conn. (NED) 1-21, 1-23, 1-31, 
1-52 
West Union, Middle Island, W. Va. (ORH) 17-23 
West Warren, Mass. (NED) 1-23, 1-43, 1-49 
Westchester Creek, N.Y. (NAN) 2-35, 2-38 
Westcott Cove, Conn. (NED) 1-40 
Westerly, R.I. (NED) 1-45 
Western Branch, Va. (NAO) 5-16 
Westfield, Mass. (NED) 1-45 
Westhaven Cove Small Boat Basin (Westport Marina), 
Wash. (NPS) 38-24 
Westland District Improvement Co., Oreg. (NPP) 
37-38 
Weston, Vt. (NED) 1-23, 1-43, 1-49 
Weston Mills, Olean, N.Y. (ORP) 18-20 
Weston Mills, Portville, N.Y. (ORP) 18-20 
Westport, Conn. (NED) 1-45 
Westport, Ky. (ORL) 16-22, 16-25 
Westport District, Oreg. (NPP) 37-38 
Westport Harbor and Saugatuck River, Conn. (NED) 
1-40, 1-45 
Westport River, Mass. (NED) 1-40 
Westport Slough, Oreg. (NPP) 37-37, 37-41 
Westville Lake, Mass. (NED) 1-22, 1-32, 1-52 
Wethersfield, Conn. (NED) 1-23 
Weymouth Back River, Mass. (NED) 1-40 
Weymouth-Braintree, Mass. (NED) 1-23 
Weymouth-Fore and Town Rivers, Mass. (NED) 1-40 
Whartons Bend Rd., Coosa River, Ala. (SAM) 10-49 
Wheeler Creek, Tex. (SWF) 30-22 
Wheeler, General Joe, Lock and Dam, Ala. (ORN) 
15-17 
Wheeling, W. Va. (ORP) 18-21 
Wheeling, W. Va. (North Wheeling) (ORP) 18-21 
Wheeling, W. Va. (Wheeling Island) (ORP) 18-21 
Whiskey and Rock Creeks, Kan. (SWT) 29-21 
White Lake Harbor, Mich. (NCE) 21-25, 21-41, 21-53 
1-73

White Oak Creek, Ohio (ORH) 17-22 
White Oak Dike, Bladen and Pender Counties, N.C. 
(SAW) 6-27 
White River, Ark. (below Newport) (LMM) 13-4 
White River Basin above Beaver Lake, Ark. (SWL) 
28-18 
White River Basin: Ark. and Mo. Lakes (SWL) 28-24 
White River, Batesville, Ark. (SWL) 28-8, 28-12, 
28-25 
White River, Ind. (ORL) 16-18, 16-30 
White River, Newport, Ark. (SWL) 28-8, 28-12, 28-25 
White River, St. Paul, Ark. (SWL) 28-8, 28-12, 28-25 
White River at Highway 14, 1/4 mile east of Oil 
Trough, Ark. (SWL) 28-18 
White River Backwater Levees (MR+T) 42-9 
White River Bank Stabilization, Batesville, Ark. 
(SWL) 28-18 
White River Basin (Little Rock District), Ark. and 
Mo. (SWL) 28-7, 28-13, 28-15 
White River, Jacksonport, Ark. (SWL) 28-18 
White River levees, Augusta to Clarendon and De 
Valls Bluff, Ark. (MR+T) 42-29 
Whitebird Creek, Columbia River Basin, Idaho 
(NPW) 39-12, 39-16 
Whitefish Point, Mich. (NCE) 21-55, 21-60 
Whites and Ewing Creeks, Tenn. (ORN) 15-19 
Whitesburg, Ky. (North Fork Kentucky River) (ORL) 
16-30 
Whitetie River, Grundy Co., Ill. (NCR) 23-17 
Whitiwater, Kan. (SWT) 29-21 
Whitewater River, Ind. (ORL) 16-30, 16-31 
Whitewater River, San Bernadino and Riverside Co., 
Calif. (SPL) 33-8, 33-15, 33-23 
Whitewater River Basin, Calif. (SPL) 33-26 
Whiting, Maine (NED) 1-23 
Whitings Creek, Va. (NAO) 5-19 
Whitlow Ranch Dam, Queen Creek, Ariz. (SPL) 33-5, 
33-20 
Whitmanville Lake, Mass. (NED) 1-43, 1-51 
Whitney Creek, Whitney, Tex. (SWF) 30-23 
Whitney Lake, Tex. (SWF) 30-12, 30-17, 30-21 
Whitney Point Lake, N.Y. (NAB) 4-18, 4-28 
Whitney Point Village, N.Y. (NAB) 4-18, 4-28 
Whittaker Creek, Oriental, N.C. (SAW) 6-29 
Whittier, Alas. (NPA) 40-13 
Wichita and Valley Center Channel Improvement, 
Kan. (SWT) 29-19, 29-20, 29-21 
Wickford Harbor, RI. (NED) 1-40 
Wicomico River, Md. (NAB) 4-12, 4-26, 4-35 
Wiedmer Chemical Drainage and Levee District, 
Mo.(LMS) 14-15 
Wilbur D. Mills Dam (SWL) 28-19 
Wiggins, Miss. (SAM) 10-49 
Wiggle Creek, Homer (MRO) 26-20 
Wilcox, Pa. (ORP) 18-21 
Wild Rice and Marsh Rivers, Minn. (NCS) 24-32, 
24-33 
Wild Rice River, Mahnomen Co., Minn. (NCS) 24-33 
Wild Rice River, Norman Co., Minn. (NCS) 24-33 
Wild Rice River, South Branch and Felton Ditch, 
Minn. (NCS) 24-19, 24-24, 24-33 
Wildcat and San Pablo Creeks, Calif. (SPK) 35-19, 
35-27 
Wilders, Ky. (ORL) 16-24 
Wiley Creek Lake, Oreg. (NPP) 37-41 
Wilkes-Barre, Hanover Township, Pa. (NAB) 4-39, 
4-42 
Willamette Falls Fishladder, Oreg. (NPP) 37-9, 37-41, 
37-43 
Willamette River above Portland and Yamhill River, 
Oreg. (NPP) 37-37, 37-41, 37-42 
Willamette River at Willamette Falls, Oreg. (NPP) 
37-25, 37-33, 37-41 
Willamette River Basin, Oreg. (NPP) 37-15, 37-35, 
37-39, 37-45 
Willamette River Basin, Oreg.-Bank Protection (NPP) 
37-16, 37-27, 37-35, 37-45 
Willamette River Basin Channel Clearing and Snagging 
(NPP) 37-39 
Willapa River and Harbor and Naselle River, Wash. 
(NPS) 38-6, 38-16, 38-21 
Willapa River at Raymond, Wash. (NPS) 38-27 
Willard Beach, South Portland, Me. (NED) 1-41 
William Bacon Oliver Lock and Dam (Replacement), 
Ala. (SAM) 10-28 
William H. Harsha Lake, Ohio (ORL) 16-11, 16-16 
William L. Springer Lake, Decatur, Ill. (NCR) 23-15 
Williamson, W. Va. (ORH) 17-21, 17-23 
Williamsport, Pa. (NAB) 4-39, 4-42 
Williamstown, W. Va. (ORH) 17-22 
Williamsville Reservoir, Vt. (NED) 1-45 
Williston, N.D., Water Intake (MRO) 26-17 
Willoughby Channel, Va. (NAO) 5-19 
Willow Creek, Ind. (NPW) 39-15 
I-74

IINIJLA 
Willow Creek Lake, Heppner, Oreg. (NPP) (NPW) 
37-27, 37-35, 39-16 
Willow Creek Lake, Oreg. (NPW) 39-15 
Willow Creek, Mason City, Iowa (NCR) 23-17 
Willow Island Locks and Dam, W. Va. (ORD) 19-7 
Wilmington Harbor, Del. (NAP) 3-7, 3-10, 3-22 
Wilmington Harbor, N.C. (SAW) 6-10, 6-20, 6-29 
Wilmington, Ill. (NCC) 22-8 
Wilmore, Pa. (ORP) 18-20 
Wilson Creek, Sumter County, S.C. (SAN) 7-15 
Wilson Harbor, N.Y. (NCB) 20-35 
Wilson Lake, Saline River, Kan. (MRK) 27-7, 27-11, 
27-15, 27-19 
Wilson Lock, Ala. (ORN) 15-17 
Wilson Point, La. (MR+T) 42-11 
Wilson Point Harbor, Conn. (NED) 1-40 
Wilson River, Oreg. (NPD) 37-40 
Wilton, N.H. (NED) 1-23 
Winchester Bay, Oreg. (NPP) 37-37 
Winfield L & D (ORH) 17-12 
Winfield Levee, Kan. (SWT) 29-19 
Winnibigoshish Reservoir, Minn. (NCS) 24-31 
Winnipesaukee Lake, N.H. (NED) 1-40, 1-47 
Winona, Minn. (NCS) 24-19, 24-24 
Winona Basin, Minn. (NCD) 25-10 
Winona Harbors, Minn. (NCD) 25-7 
Winooski River, Vt. (NAN) 2-36 
Winslow (Tributaries of Little Colorado River) Little 
Colorado River Basin, Ariz. (SPL) 33-26 
Winsted, Conn. (NED) 1-23, 1-43, 1-49 
Winter Harbor, Maine (NED) 1-40 
Winter Harbor, Va. (NAO) 5-19 
Winthrop Beach, Mass. (NED) 1-41, 1-45 
Winthrop Harbor, Mass. (NED) 1-40, 1-46 
Wisconsin River, Wis. (NCS) 24-27 
Wishart Point Channel, Va. (NAO) 5-20 
Wister Lake, Okla. (SWL) (SWT) 28-22, 29-8, 29-15 
Withlacoochee River, Fla. (SAJ) 9-46, 9-47 
Wolf and Jordan Rivers, Miss. (SAM) 10-47, 10-50 
Wolf-Coffee Lake, Blue River, Kan. (MRK) 27-17 
Wolf Creek Dam-Lake Cumberland, Ohio River 
Basin, Ky. (ORN) 15-8, 15-10 
Wolf Creek, U.S. Highway 45 Bridge, Prentiss 
County, Miss. (SAM) 10-48 
Wolf Creek, Highway 362 Bridge, Prentiss County, 
Miss. (SAM) 10-48 
Wolf River (Memphis Harbor), Tenn. (LMM) 13-4 
Wood Island Harbor and Pool at Biddleford, Me. 
(NED) 1-10, 1-27, 1-35, 1-46 
Wood River Drainage and Levee District, Ill. (LMS) 
14-5, 14-9, 14-11 
Woodbridge Creek, NJ. (NAN) 2-35 
Woodbury, Conn. (NED) 1-23 
Woodbury Creek, NJ. (NAP) 3-24 
Woodcock Creek Lake, Pa. (ORP) 18-9, 18-13, 18-18, 
18-25 
Woodlands, W. Va. (ORP) 18-21 
Woodmont Beach, Conn. (NED) 1-46 
Woodmont Shore, Milford, Conn. (NED) 1-41 
Woodruff, Jim, Lock and Dam, Ga. and Fla. (SAM) 
10-25, 10-35, 10-46 
Woods Hole Channel, Mass. (NED) 1-40 
Woodson Drainage District, Oreg. (NPP) 37-38, 
37-39, 37-44 
Woonsocket, R.I. (NED) 1-23, 1-43, 1-48 
Worcester, Mass. (NED) 1-23, 1-48 
Worcester Diversion, Mass. (NED) 1-43 
Worthington, Minn. (NCR) 23-16 
Wrangell Harbor, Alas. (NPA) 40-5, 40-9, 40-11, 
40-14 
Wrangell Narrows, Alas. (NPA) 40-5, 40-9, 40-11, 
40-12, 40-14 
Wright Patman Dam and Lake, Tex. (LMN) (SWF) 
11-19, 30-11, 30-17, 30-21 
Wright's Creek, N.C. (SAW) 6-25 
Wrightsville Beach, N.C. (SAW) 6-27 
Wrightsville Dam, Vt. (NAN) 2-36 
WTP, Great Miami River, Ross, Ohio (ORL) 16-30 
Wynoochee Lake, Wash. (NPS) 38-10, 38-17, 38-22 
Wynoochee River, Wash. (NPS) 38-27 
Wyoming Valley, Pa. (NAB) 4-22, 4-39 
Y 
Yadkin River Basin, N.C., S.C. (SAW) 6-14, 6-30 
Yakima River at Union Gap, Wash. (NPS) 38-12, 
38-27 
Yakima River, Cle Elum, Wash. (NPS) 38-27 
Yakima River, West Richland, Wash. (NPS) (NPW) 
38-27, 38-29, 39-15, 39-17 
Yakima River, Yakima, Wash. (NPS) 38-27 
Yalobusha River, Miss. (LMK) 12-16 
Yaquina Bay and Harbor, Oreg. (NPP) 37-9, 37-25, 
37-33, 37-42 
I-75

Yaquina Bay and Harbor Small Boat Basin, Oreg. 
(NPP) 37-37 
Yaquina River, Oreg. (NPP) 37-37 
Yatesville Lake, Ky. (ORH) 17-10, 17-14, 17-19 
Yazoo Basin, Miss. (MR+T) 42-7, 42-16, 42-30 
Yazoo Basin Headwater, Miss. (MR+T) 42-53 
Yazoo River, Miss. (LMK) 12-16 
Yazoo Backwater Area (MR+T) 42-53 
Yellow Jacket Creek, Hogansville, Ga. (SAM) 10-48 
Yellowstone River, Bank Protection, Billings, Mont. 
(MRO) 26-19 
Yellowstone River, Glenrdive, Mont. (MRO) 26-16, 
26-23 
Yellowstone River, Greycliff Bridge, Mont. (MRO) 
26-19 
Yellowstone River, Livingston, Mont. (MRO) 26-23 
Yellowstone River, near Miles City, Mont., Water 
Intake and Sewage Lagoon (MRO) 26-19 
Yellowstone River, Reedpoint Bridge, Mont. (MRO) 
26-19 
Yellowstone River, Springdale Bridge, Mont. (MRO) 
26-19 
Yellowstone River, Voges Bridge, near Big Timber, 
Mont. (MRO) 26-19 
Yellowstone River, Water Plant, Livingston, Mont. 
(MRO) 26-18 
Yellowstone River, Yellowstone Co. Bridge, near 
Billings, Mont. (MRO) 26-19 
Yonkers, N.Y. (NAN) 2-36 
York Harbor, Maine (NED) 1-40 
York, Indian Rock Dam, Pa. (NAB) 4-21, 4-29, 4-36 
York River, Va. (NAO) 5-20 
York Spit Channel, Va. (NAO) 5-2, 5-15 
Youghiogheny River, Penn. and Md. (Canalization) 
(ORP) 18-21 
Youghiogheny River Lake, Ohio River Basin, Penn. 
and Md. (ORP) 18-9, 18-13, 18-18, 18-25 
Youngs and Klaskanine River, Oreg. (NPP) 37-39 
Youngs Bay and Youngs River, Oreg. (NPP) 37-42 
Youngs River Dikes, Oreg. (NPP) 37-38 
Youngstown, Ohio (ORP) 18-20 
Z 
Zacate Creek Channel Improvement, Tex. (SWF) 
Zintel Canyon Dam, Wash. (NPW) 39-8, 39-14 
Zippel Bay, Lake of the Woods County, Minn. (NCS) 
24-3, 24-22 
Zippel Bay Harbor, Minn. (NCS) 24-27 
Zumbro River, Minn. (NCS) 24-28, 24-33 
Zumbro River at Genoa, Minn. (NCS) 24-34 
Zumbro River at Jarrett and Millville, Minn. (NCS) 
24-20, 24-24 
30-22, 30-23 
Zanesville, Ohio (ORH) 17-22 
I-76

3 131b4 00 B&bP4 7

